BER   LAKE
                               CHEYENNE RIVER INDIAN RESERVATION
                                    TIMBER LAKE, SOUTH DAKOTA
                                                                                          Timber Lake
                                                                                                   March 2009
ACCOMPLISHMENTS
• Conducted RBCA assessment
• Installed 27 MWs
• Excavated and removed 422 yd3 of PCS
• Conducted 2 ISCO injection events
• Constructed interceptor trench for wellhead protection
• Conducted microbial analysis
• Ground-water monitoring

EPA Region 8 performed this work in partnership with the Cheyenne
River Sioux Tribe and with contract support from Avanti Corporation.

PLANNED  ACTIVITIES/
FUTURE  STRATEGIES
• Groundwater monitoring
• Continue ISCO injection and application events to treat groundwater
• Replacement of municipal drinking water well
• Utilize phytoremediation to compliment ISCO in 1 of the source
  areas
• Evaluate other green remediation approaches for potential applica-
  tion at site
SITE  HISTORY
Water samples collected from Municipal Well No. 1 in the early 1990s
contained contaminants which exceeded federal drinking water stan-
dards. Site investigations conducted by the South Dakota Department
of Environment and Natural Resources (SDDENR) identified several
former gas stations and bulk fueling facilities as potential sources for
the contaminants, but no single, clear source was found. Petroleum was
stored at these facilities in both underground storage tanks (USTs) and
aboveground storage tanks (ASTs). Since 1993, EPA has monitored the
groundwater to evaluate site conditions. Contaminant levels for chemicals
of concern (COC) continued to exceed groundwater quality standards
in multiple monitoring wells (MWs). In 2007, a risk-based corrective
action (RBCA) assessment was conducted at the site. Nine new MWs
were installed, developed and sampled. Four MWs that were scheduled
for abandonment were repaired. Petroleum contaminated soil (PCS)
was identified in three locations at the site. Three separate source areas
were identified for the contaminated groundwater and soil at the site. In
2008,422 yd3 of PCS was excavated from three target areas. Additional
site assessment activities were conducted including the installation of
             BENZENE IN GROUNDWATER (MW-13)
  120.00
2100-00
S 80.00
£ 60.00
cp
c 40.00
o>
m 20.00
   0.00
                                               Jan
                                               2008
      TIMBER LAKE
      EPA Region 8 UST Program Technical Contact | Mr. Raymond Faliskie | (303) 312-6124 or faliskie.raymond@epa.gov | www.epa.gov/region8/ust/

-------
  seven soil borings, development and sampling of three new MW and
  installation of one deep in-situ chemical oxidation (ISCO) injection well.
  Two ISCO injection events were conducted at the site.  In December
                                                  2008, an interceptor trench for wellhead protection was constructed. In
                                                  2009, a microbial analysis was conducted to identify benzene degrading
                                                  bacteria at the site.
TIME  LINE
         "Municipal Well No. 1
          was drilled
                          • EPA began groundwater
                           monitoring
                                                                                           RBCA assessment
                                                                                           conducted  9 MWs
                                                                                           installed, 4 MWs
                                                                                           repaired 6 test pits
                                                                                           excavated
    1978 > 1991  1992   1993   1994   1995  1996  1997  1998  1999  2000   2001  2002  2003  2004  2005  2006  2007  2008  2009  2010
   Contamination -
   detected in
   Municipal Well
   No.1
SDDENRsite
investigations
identify several
potential sources
of contamination
422 yd3 of PCS excavated and
removed  2 ISCO injection
events 3 MWs and 1 deep
ISCO injection well installed
interceptor trench constructed
                                                                                         TT
Performed microbial
analysis Ground-
water monitoring
         TIMBER LAKE
         EPA Region 8 UST Program Technical Contact | Mr. Raymond Faliskie | (303) 312-6124 or faliskie.raymond@epa.gov | www.epa.gov/region8/ust/

-------