Pro WCt ion
             . DC 20460
National Municipal
Policy and Strategy

For Construction Grants,
NPDES Permits, and
Enforcement  Under
the Clean Water Act

October 1979

-------
                                     NOTES
     To order this publication, National  Municipal  Policy and Strategy (UNA-13.0)

from EPA, write to:
          General Services Administration (8FFS)
          Centralized Mailing List Services
          Bldg. 41, Denver Federal Center
          Denver, CO  80225
     Please indicate the ordering number and title of publication.

-------
  NATIONAL  MUNICIPAL POLICY AND STRATEGY

For Construction Grants,  NPDES Permits,  and
   Enforcement Under the  Clean Water Act
   U.S.  Environmental  Protection  Agency
        Office of Water Enforcement
    Office  of  Water  Program  Operations
               October  1979

-------
                                    PREFACE
     A majority of municipal dischargers, for a variety of reasons, have not

complied with the Clean Water Act's July 1, 1977 treatment requirements.  These

discharges contribute a substantial pollutant load into the waters of the

United States.



     This National Municipal Policy and Strategy, published after months of

comment and discussion, will serve to guide Regions and States in a productive

period of activity aimed at achieving the Clean Water Act's goals of fishable

and swimmable waters, in part through full municipal  compliance.



     To give effect to this National Municipal Policy and Strategy, I have

directed the Deputy Assistant Administrators for Water Enforcement and Water

Program Operations to produce a Municipal Management System.  I have further

directed the Deputy Regional Administrators to work directly with the Program

Offices to implement the management system.
                                      Douglas MJ Costle
                                        Administrator
                                         -i-

-------
                                    OUTLINE

                                                                   Page

I         Introduction                                               1

II        Legislative Background                                     3

III       Status and Scope of Municipal Noncompliance                5

               o  Description of Noncompliance Problem
               o  Remedies to the Noncompliance Problem

IV        Municipal Noncompliance Classification Process             8

               o  Purpose
               o  301(i)(l) Initial Test
               o  POTWs With Active Grants
               o  POTWs Without Active Grants
               o  POTWs Which Have Completed Construction

V         Issuance of 301(i)(l) Extensions                          16

               o  The Relationship of Section 301(h) to
                    Section 301{i)(l)

VI        Issuance of 309(a)(5){A) Administrative Orders            22

VII       Priorities for Issuance of Extensions and
            Administrative Orders                                   27

               o  Pretreatment Priorities
               o  Funding Availability and Schedule Development

VIII      Treatment More Stringent Than Secondary                   33

IX        Municipal Referral Priority System                        37

               o  Purpose
               o  Scope
               o  Effect of 301(i)(l) Request on Initiated
                    Referrals
               o  Procedure
               o  Special Enforcement:  Public Health and Fragile
                    Ecosystems
               o  Special Enforcement:  Category IV
               o  Implementation

X         Formulating a Municipal Management System                 42
                                     -111-

-------
PART I:  INTRODUCTION



     An analysis of compliance indicates that the majority of publicly-owned

treatment works (POTWs) have not completed construction necessary to meet the

1977 treatment requirements.  Many of these POTWs are eligible for relief fron

enforcement under the Clean Water Act (P.L. 95-217) by the provision in section

301(i)(l) that provides for extensions of the time for compliance until no

later than July 1, 1983.  In response to this and other provisions applicable

to municipalities, EPA has developed a National Municipal Policy and Strategy

for more effectively managing municipal  compliance with the Clean Water Act.

The goal is to integrate permits, enforcement, and construction grant

activities by:
               issuing, to qualified POTWs, extensions with enforceable
               compliance schedules based on grant funding, in the form of
               permits and administrative orders;

               coordinating with States to develop State Project Priority Lists
               which assure that grant funding is allocated to projects
               necessary to meet the enforceable requirements of the Act before
               funding is allocated to other projects, to the extent authorized
               by law; and

               laying the foundation to permanently coordinate grant, permits,
               and enforcement operating practices with the aim of stream!ining
               compliance by municipalities while simultaneously removing
               impediments to enforcement actions, if needed.
     The National Municipal Policy and Strategy under the Clean Water Act

contains:  (1) a process for determining whether a permittee will  be eligible

for a permit extension, be issued an administrative order, or be subject to

referral for judicial action; (2) a brief description of how Construction
                                     -1-

-------
Grant and Permit staffs will coordinate  in the  issuance of  National Pollutant




Discharge Elimination System (NPDES) permits containing actual dates based on



grant schedules as compliance milestones; (3) a brief description of how



Construction Grants and Enforcement staffs will  coordinate  to produce



administrative orders containing grant-based compliance schedules; and  (4) a



brief description of the relationship of permit and enforcement actions to



State Project Priority Lists (PPLs) and the Clean Water Act's enforceable



requi rements.
                                      -2-

-------
PART II:  LEGISLATIVE BACKGROUND







     Section 301(i)(l) provides relief to POTWs which did not have adequate



Federal  funding in time to meet the 1977 treatment requirements.  This section



authorizes permit issuing authorities to grant timely requests for extensions



of the July 1, 1977 treatment deadline, "where construction is required .  . .



to achieve limitations .  . . but . . . (B) the United States has failed to make



financial  assistance under this Act available in time" (emphasis added).  Any



permit issued or modified under section 301(i)(l) must contain, among other



terms and  conditions, "a  schedule of compliance . . . based on the earliest



date by which such financial assistance will be available . . . and



construction can be completed, but in no event later than July 1, 1983"



(emphasis  added).







     Section 216 authorizes the Administrator to remove a project from a



State's priority list, "if the Administrator, after a public hearing,



determines that a specific project will not result in compliance with the



enforceable requirements  of this Act"  (emphasis added).  The enforceable



requirements of the Act include the conditions of an NPDES permit, or where



no permit  applies, any condition which the Regional Administrator determines



necessary to meet applicable criteria for best practicable wastewater treatment



technology (see 40 CFR 35.905).







     Since they also affect compliance with the Clean Water Act, several other



sections have a direct effect on POTWs and the National Municipal Policy and



Strategy.   Sections 307(b) and  (c) and 402(b)(8), as implemented by 40 CFR 403,
                                      -3-

-------
require certain POTWs to have a pretreatment program in place and approved by



no later than July 1, 1983.  Section 301(h) authorizes applications for



modification of the secondary treatment requirements for certain POTWs



discharging into marine and estuarine waters (see 40 CFR 125, Subpart G) --



many POTWs have requested both 301(i)(l) permit extensions and 301(h) permit



modifications.
                                      -4-

-------
PART  III:  STATUS AND  SCOPE OF MUNICIPAL  NONCOMPLIANCE


Description of the Noncompliance Problem


      POTW compliance with  the July  1,  1977 treatment  deadline  has  been

classified as follows:
CATEGORY
CATEGORY III
CATEGORY  I     POTWs that need construction to comply; did  not  significantly
               contribute to the delay  in construction; construction grant
               funding  is or will be available to  assist  in complying; and can
               complete construction by the 1983 deadline.

               POTWs that need construction to comply; did  not  significantly
               contribute to the delay  in construction; construction grant
               funding  through Step 3 is available  to assist  in complying; but
               cannot complete construction by the  1983 deadline.

               POTWs that need construction to comply; did  not  significantly
               contribute to the delay  in construction; for which construction
               grant funding through Step 3 does not appear to  be available by
               July 1,  1983, and consequently, may  not complete construction by
               the 1983 deadline.

               POTWs that need construction to comply and are causing signif-
               icant public health or pollution problems, but due to lack of
               position on project priority lists, may require  judicial action
               to assure prompt achievement of NPDES permit requirements.

CATEGORY V     POTWs that have completed construction and are not meeting
               effluent limitations or other NPDES  requirements.

CATEGORY VI    POTWs that need construction to comply and did significantly
               contribute to the delay in construction.
CATEGORY IV
Remedies to the Noncompliance Problem


     Major municipal compliance with the treatment requirements of the Clean

Water Act along with the Major Source Enforcement Effort (MSEE) for industrial

dischargers are the primary water enforcement priorities.  Now that the number

of major industrial sources out of compliance has been reduced, enforcement

actions aimed at significant POTWs which have not installed secondary or more
                                      -5-

-------
stringent treatment will be stepped up in accordance with procedures discussed

in this National Municipal  Policy and Strategy.



     Initially, placing POTWs on enforceable compliance schedules is essential

to an effective municipal  compliance effort.  The methods of accomplishing this

are:
          (1)  Section 301(i)(l) extensions to qualified POTWs, as discussed  in
               Part V;

          (2)  Section 309(a)(5)(A) administrative orders or comparable State
               mechanisms, as discussed in Part VI, to certain POTWs unable to
               comply by July 1, 1983; and

          (3)  Referral for judicial action in appropriate cases, as discussed
               in Part IX.
     A process for determining which compliance response is appropriate  is

described in Part IV.  Procedures and priorities for administering each

response are described in Parts V-IX.



     Table A illustrates the six categories of municipal noncompliance and the

appropriate Regional or NPDES State compliance responses.
                                      -6-

-------
                                                     TABLE  A
                                CATEGORIES  OF  AND RESPONSES  TO  MUNICIPAL  NONCOMPLIANCEV
CATEGORY
Category I
Category II
  and
Category III
Category IV
Category V
Category VI
EXTENSION REQUESTED
NO ECSL?/
          •301 Him  EXTENSION NOT REQUESTED-
                       NONCOMPLIANCE
                        WITH ECSL
Grant 301(i) request;
issue permit with compl.
schedule assuring com-
pletion of construction
by 1983.  Revoke ECSL.
Deny 301(i)  request;
Issue permit, or con-
tinue permit where ESCL
exists, requiring
immediate compl. with
secondary or more
stringent treatment;
Issue 309(a}(5)(A)
Administrative Order(s)
with compl.  schedule
not extending beyond
1983.

Deny 301(i}  request;
referral for judicial
action.

Deny 301(i)  request;
Issue 309(a)(5)(A)
Administrative Order(s)
or referral  for judicial
action.

Deny 301(i)  request;
referral for judicial
action.
Issue permit requiring
immediate compliance
and 309(a)(5)(A) Admin-
istrative Order(s) 3/
with compl. schedule
assuring completion of
construction by 1983.

Issue permit requiring
immediate compl. with
secondary or more strin-
gent treatment; Issue
309(a)(5)(A) Admin-
istrative Order(s) not
extending beyond 1983.
Referral
action.
for judicial
Issue 309(a)(5)(A)
Administrative Order(s)
or referral for judicial
action.
Referral
action.
for judicial
                            COMPLIANCE
                             WITH ECSL
                       Revoke ECSL;  Continue
                       permit and issue
                       309(a)(5)(A)  Admin-
                       istrative Order(s) with
                       compl. schedule assur-
                       ing completion of
                       construction  by 1983.

                       Revoke ECSL;  Continue
                       permit requiring
                       immediate compl. with
                       secondary or  more
                       stringent treatment;
                       Issue 309(a)(5)(A)
                       Administrative Order(s)
                       not extending beyond
                       1983.
                            Monitor
                            compliance
                            with ECSL
                            Not Applicable^'
Referral
action.
for judicial
                       Issue 309(a)(5)(A)
                       Administrative Order(s)
                       or referral  for judicial
                       action.
Referral for judicial
action.
Not Applicable.
                            Not Applicable.
                   Not Applicable.
V  Requests for 301 (h) not Tncluded.   (Note:  301 (h)  requests should be processed  before  30TOT requests").
2/  ECSL means Enforcement Compliance Schedule Letter or a comparable State procedural  mechanism.
3/  A 309(a)(5)(A) Administrative Order or a  comparable State procedural  mechanism.
4/  ECSL policy prohibited the issuance of ECSLs  beyond the  life  of  a NPDES permit  (e.g.,  beyond July  1,  1983).

                                                       -7-

-------
PART IV:  MUNICIPAL NONCOMPLIANCE CLASSIFICATION PROCESS



Purpose

     The process outlined in this part provides a systematic method to

determine whether a POTW should receive a section 301(i)(l) penr.it extension,

be issued a section 309(a)(5)(A) administrative order, or be subject to

referral for judicial action. *



    The flow diagram (Figure A) divides POTWs into two groups -- those with and

those without active grants.  POTWs with active grants which have not

significantly contributed to a delay in funding or completion of construction

will  either be granted 301(i)(l) extensions or issued administrative orders in

lieu of a 301(i)(l) permit extension, depending on whether the POTW submitted a

timely request for an extension and can complete construction by July 1, 1983.

POTWs which have significantly contributed to a delay in funding or subsequent

construction will be candidates for referral  for judicial action, or

administrative orders.  POTWs without active grants, particularly POTWs in

Category III, should be moved into the grant process wherever possible.



301(i)(1) Initial Test

     The 301(i)(l) regulations (40 CFR 125.93) state that no extension can be
* Part IX contains a discussion of when States with administrative penalty
procedures should use administrative penalties first rather than referral for
judicial action.
                                      -8-

-------
                                                                           FIliURE A

                                                     PROCESS FOR CLASSIFYING STATUS OF NONCOMPl YINU POTWi
                                                    NONCOMPLYING
                                                    POTWi
                       ON SCHEDULE
         OFF SCHEDULE
CG/PERMITS REVIEW
CAUSE OF SCHEDULE
DELAY
 POTENTIALLY
 EXCUSABLE
 CONTRIBUTION TO
 DELAY BYPOTW
INSIGNIFICANT OR
NO CONTRIBUTION
TO DELAY BY POTW
   ENFORCEMENT
   ACTION SHORT
   OF REFERRAL
   TO COURT
COMPLIES WITH ACTION
                                                           FUND FROM
                                                           RESERVE OR
                                                           REVISE PRIORITY
                                                           RANKING
          DOES NOT COMPLY
          WITH ACTION
NU1 ON FUNOABIE
PORTION OF PROJECT
PRIORITY LIST
 CAUSING SIGNIFICANT
 WATER QUALITY AND/OR
 PUBLIC HEALTH PROBLEMS
NO
                                                                                                           YES
 REQUEST STATE
 TO HEEXAMINE
 PRIORITY RANKING
                                    YES
                                                     NO


CATEGORY 1
GRANT 301 (.1(1
EXTENSION



CATEGORY II
309UK5HAI
ORDERS
                                                                            FUNDING NOT
                                                                            MADE AVAILABLE
                                                                                  DOES NOT COMPLY
                                                                                  WITH ACTION
                                                                                                     CATEGORY IV
                                                                                                     REFERRAL
                                                                                                     TO COURT

-------
granted unless a POTW requires construction to meet treatment requirements, and
either:

          (a)  The issuance of a notice to proceed under a construction
contract for any segnent of Step 3 project work (or if notice to proceed is not
required, the execution of the construction contract)  occurred before July 1,
1977, but construction could not physically be completed by July 1, 1977
despite all  expeditious efforts by the POTW (see initiation of construction
as defined in 40 CFR 35.905 for Step 3); or

          (b)  Federal financial assistance either was not available, or was
not available in tine for construction required to achieve NPDES permit
lin-itations, and the POTW did not in any significant way contribute to this
unavailability or delay.

     Section 301(i)(l) does not authorize the granting of any extensions where
construction cannot be completed by July 1, 1983.  For this reason, the section
301(i)(l) regulations (40 CFR 125.93) require States to certify that funding
will be available in time to ensure compliance by July 1, 1983.  It is
anticipated that award dates for Step 3 grants can be projected with reasonable
accuracy based on the new construction grant requirement for five-year Project
Priority Lists beginning in FY 1980.

POTWs with Active Grants
     POTWs which are either on their grant schedule or had begun a continuous
program of physical construction of the facility before July 1, 1977 (i.e., into
                                      -10-

-------
Step 3) can complete construction by July 1, 1983, and which meet the criteria



of section 301(i)(l) as outlined in 40 CFR 125.93 should be granted 301(i)(l)



extensions.







     Generally, there are two major ways in which POTWs may be off grant



schedules -- (1) preconstruction lag (POTWs that have been awarded grants Dut



have not begun work, primarily at the Step 3 stage), or (2) POTWs that have



begun work but have encountered delays.  Only off-schedule POTWs that can be



considered not to have caused funding or construction delays are immediately



eligible for 301(i)(l) extensions (e.g., preconstruction lag occurred because



State law prohibited the raising of matching local funds prior to the award of



Federal funds).







     Where delays exist, the Region or NPDES States should review the cause and



nature of delay to determine whether compliance would better be assured by



referral for judicial action, or issuance of a 301(i)(l) extension or a



309(a)(5)(A) administrative order.  In determining that a judicial action



should be taken against a POTW for failing to meet the July 1, 1977 deadline,



the Agency has necessarily determined that the failure of the POTW to meet that



deadline is attributable in significant measure to the POTW's own action or



inaction rather than the unavailability of Federal funds.  Since this



determination is dispositive of 301(i)(l) requests, such requests should be



denied for any POTW against which a judicial action for failure to construct



necessary treatment works by July 1, 1977 has been filed or referred.  However,



where no referral for judicial  action is either pending or planned, and if the



cause and nature of any funding or construction delay is less serious, the



Region or NPDES State should exercise its prosecutorial discretion through an



administrative form of enforcement action prior to the 301(i)(l) determination
                                      -11-

-------
to give the POTW an opportunity to demonstrate  its  intention and ability  to



meet the new deadline.







     By using enforcement actions short of referral first, the Region  or  NPDES



State carries out enforcement actions in conjunction with an offer of  Federal



financial assistance.  If a POTW fails to comply with such enforcement  actions,



the subsequent case for referral for judicial action will be strengthened



because Agency program actions appear consistent to the  court.







     If a POTW complies with interim enforcement actions  (confirming that  it  is



taking all reasonable steps to comply with the  Clean Water Act) and  can meet



the 1983 deadline, referral for judicial action is  not necessary, and  a



301(i)(l) extension may be granted.  If the POTW did not  request an  extension



and does not hold an tCSL or cannot meet the  1983 deadline, an administrative



order may be issued.  This approach does not  mean that administrative  orders



are to be the enforcement mechanism of first  choice in all cases.  Where  the



POTW has a history of delay despite efforts by  the  Agency to urge the  POTW to



proceed, referral for judicial action should  be considered the enforcement



mechanism of first choice.







POTWs Without Active Grants



     The right side of the flow chart (Figure A) addresses the three types of



POTWs without an active grant:  (1) those on  the fundable portion of a  State



Project Priority List (PPL), (2) those not on the fundable portion of  a PPL,



and (3) those which completed final construction but are  not meeting required



effluent limitations.  Some POTWs on the fundable portion of a PPL may  not have



applied for a grant.  For those POTWs that fail to  apply  for a construction
                                       -12-

-------
grant  in  a  timely  manner,  appropriate enforcement actions should be taken,




informing such  POTWs  that  funds  are  available and '•.ha1' they have either "X"




days *o  apply  for  a  nrant  or  their 301 (iVl)  reouest will be denied.   !f the




-n-"/ cornlies  and  enters  into  an active nrant posture, a de^.prrinat 'on *T)  issue




a 3(")l'i)'l)  rentes*  or  administrative order can be made has^d on *-.he ^"'l^'tv of




*he DnTW  to  corplete  construction  by July 1,  PP3.
      In + he case  of  r>nTWs  not  on  the ^undable portion of the nnL ,  an
should be nade  to elevate  significant  pnTWs selected by the Person and NPP[S



State into the  ^undahle  portion  of the PPL  (i.e.,  rove pf~lTWs frot" Category  III



to II).  !n all cases, Fnforcement  will  analyze the nature of the violation and



deternine if a  revision  to  the PDTW's  project  ranging appears to he justified.



lf t for example, the  action was  for an effluent violation resulting in serious



strear degradation  (e.g.,  precluding  or restricting beneficial  uses, or



creating public health hazards),  the  Pegional  Administrator should contact the



State to request that the  POTW's  project  be considered for placement in the



^undable range  of the PPL.








     If projects which do  not meet  the enforceable requirements of the Clean



Water Act are proposed for  funding,  the Regional Administrator  should  ask  the



State to revise its PpL  to  rank  the noncomplying "OTW higher -- above  the  fun-



ding line,  if possible (see 40 CFR  35.915).  For example, should the fundable



portion of the  State PPL include  pipe- related  projects beyond the State's



allowance o^ 25 percent  not required  to meet the enforceable requirements  of



the Clean Water Act, the Regional  Administrator may ask  the State to revise its



Project priority List to substitute a  nonconplying POTW  for one or more of the
                                       -13-

-------
pipe projects.  All such requests should be made  through  and  approved  by  the



Regional  prograir, office responsible for PPL management.







     Tne process of reevaluation of project priority does not  increase  the



total  tunas available to the State for water pollution abatement.  Thus,  given



a fixeu dn-.Gi.nt. of dollars allocated, increasing the priority  of  one  project



will decrease that of another.  For states that have developed priority systems



and lists in accordance with the September 21, 197& construction  grant



regulations (see 40 CFk 35.915) and program guidance,  it  is expected tnat



requests for reevaluation will be few and  limited to those cases  where  it



appears new information exists regarding the particular project  in question



that was not considered in establishing the project's  priority.







     When requests are made, the State will be asked to:  (1)  reevaluate  the



original  priority rating, or (2) consider  funding from the Step  1 and  Step 2



grant  reserve.  If the State increases the priority rating or  agrees to fund



from the reserve, then Enforcement, if necessary, will issue  a letter  or



administrative order soliciting an application, and the process  would  follow



the pattern outlined in the section on Active Grants (see pages  10-12).   Should



the State deny increased priority, the POTW should be  considered  to  have  no



Federal funding available by July 1, 1963, and hence may  not  meet the  1983



construction deadline necessary for granting of a 301(i)(l) extension.  Since



the POTW presents a significant pollution  problem, serious consideration  must



then DC given to bringing a judicial action under section 309  of  the Clean



Water Act.







     Determining the appropriate compliance response (301(i}(1)  permit



extension, administrative order, or referral) is clearly  dependent on  grant
                                      -14-

-------
funding.  Since a delay may be experienced in the development of more complex



PPLs, the processing of some 301(i)(l) requests may be deferred until fiscal



year 1980, and in the case of some minors, beyond fiscal year 1980.







POTWs Which Have Completed Construction



     POTWs that have completed construction and are not meeting their NPDtS



permit limitations are not eligible for 301(i){l) extensions and are candidates



for various enforcement remedies.







     Section 203(e) of the Clean Water Act authorizes the Administrator, at



the grantee's request, to provide technical and legal assistance in the



administration and enforcement of contracts necessary to construct treatment



works.  The extent of this assistance will depend upon available resources.



The construction grant regulations (40 CFR 35.970) indicate the request must



generally be made in writing, and States may also provide such assistance.  The



grantee is responsible for enforcing all contracts necessary to build the POTW



independently of EPA.
                                      -15-

-------
PART V:  ISSUANCt OF 301(i)(l) EXTENSIONS
     Issuing or modifying NPUES permits to incorporate 301(i)(l) extensions  is

direct"y relateo to the construction grant process, and close coordination and

snarui.; or i-.Tor-nation between the two program offices is required.  Similarly,

av-arjiny or amencing grants to POTWs that are issued 301(i)(l) extensions must

also be coordinated so that fixed permit compliance milestones ensure that

major construction grant dates are enforceable and consistent with grant

agreements.  Since the great bulk of program coordination will occur through

the 3Gl(i)(l) mechanism, the following chart (Figure B) illustrates how the

Permits and Construction Grants staff must work together to  formulate 301(i)(l)

permit terms and conditions and award construction grants to POTWs with

301(i)(l) extensions.  The same coordination must take place in formulating

compliance schedules in administrative orders (see Part VI).



     As shown, a suggested sequence of activities beginning  in fiscal year

1979 for implementing the 301(i)(l) process at the Regional and State level

would be as follows:
          (1)  Permits staff will provide the  list of 301(i)(l) applicants  to
               the Grants staff.

          (2)  Grants staff will determine which of the applicants  are  on the
               fundable portion of the PPL and supply the grants  schedule to
               Permits staff.

          (3)  Permits and Enforcement staff will simultaneously  prepare
               additional permit and compliance  information  in accordance with
               the suggested processing priorities in Part VII.

          (4)  Permits staff will determine which of the 301(i)(l)  applicants
               have active grants through use  of the Grants  Information Control
               System (GIGS) and will extract  necessary project information
               from GIGS.  If the information  is not available from GIGS, then
               Grants will furnish all necessary information to Permits.
                                      -16-

-------
                                             FIGURE B

                    APPROACH TO PERMIT ISSUANCE FOR APPROVED 301 nidi EXTENSIONS
                            APPROVED 301 ullll
                            CANDIDATES
                           IN ACCORDANCE WITH
                           PRIORITY ISSUANCE
                           RANKING
                   COMPLETE AWT REVIEW [IF APPLICABLE)
                   TO ENSURE CORRECT EFFLUENT
                   LIMITATIONS AND TO PROJECT GRANT
                   FUNDING
                      PRELIMINARY DETERMINATION
                      BY GRANTS PERMITS ON PERMIT
                      TERMS AND COMPLIANCE
                      SCHEDULES
                            (OPTION)I


                      GRANTS AND PERMITS MEETING     j
                      WITH MUNICIPALITY OR DISTRICT   '
                      (PRE PERMIT PUBLIC NOTICE OR     |
                      PRE GRANT APPLICATION STAGE)   ,
                                          GRANTS STAFF DERIVES SCHEDULES
                                          FROM GRANTS INFORMATION
                                          (PROJECT LIST OR EXISTING
                                          GRANT AGREEMENT!
               (OPTION)
(PROPOSED DISCHARGE!
          I
                           GRANTS FINALIZES
                           GRANT AGREEMENT
                            PERMITS PREPARES
                            DRAFT PERMIT
                             PERMITS PUBLIC
                             NOTICES
                             DRAFT PERMIT
          (IF
          .NEEDED)
   CHANGE IN PERMIT BASED ON
   COMMENTS. AMEND GRANT IF
   NECESSARY
                       PERMIT ISSUES FINAL PERMIT
                       REFERENCING GRANT. GRANTS
                       AWARDSGRANT, REFERENCING
                       PERMIT
          I	
ENTER COMPLIANCE SCHEDULE
INTO MONITORING SYSTEM IN
ACCORDANCE WITH REGIONAL/STATE
MUNICIPAL MANAGEMENT SYSTEM
                                               -17-

-------
     The remaining 3Gl(i)(l) applicants not covered by the Permit Compliance



System ;PCb) or uICS would be the unfunded projects.  Processing of 301(1)(1)



requests from  ^nfunded POTWs should be delayed until the State Project



Priority List has oeen properly adjusted in fiscal year 1980.







     A final list of eligible extension candidates should be developed by the



Permits staff and sent to the Water Division,  where effluent limitations are



established Dased upon water quality standards, the Water Quality Management



staff generally will provide the effluent limitations; the Permits staff is not



expected to aevelop water quality-related effluent limitations.  When a  project



is either undergoing review for treatment more stringent than secondary  or  is



awaiting such review pursuant to Office of Water Program Operations, Program



Requirements Memorandum (PRM 79-7), an NPLiES permit should not be issued prior



to completion of that review (.see Part VIII).  The Permits staff will review



these effluent limitations for legal and procedural  (not technical) adequacy to



assure that they are supportable and enforceable.  If the Permits staff  is  not



satisfied that the limits are supportable and enforceable, Permits should inform



Grants and Water Quality Management of the nature of their concerns and  attempt



to reach mutual agreement on effluent limitations.  Once the limits are



acceptable, construction schedules will be developed by either Grants or



Permits staff based on the project list and/or schedule in existing grant



agreements and concurred on by both programs.
                                      -18-

-------
     Once the schedule and effluent limitations information  is available,

the Permits staff will develop a draft permit based on information received

from the Construction Grants and Water Quality Management staffs, and the

Grants staff will develop a proposed grant award agreement.



     The draft and final permit must include a compliance schedule which

contains actual  milestones derived from the grants process.   The PCS and GICS

systems have been reviewed, and the necessary and discretionary grant events

that will make up the milestone dates will be listed in the Compliance and

Grants Interaction Systems Workgroup Report (see Part X).  At a minimum, the

compliance scheaule should contain dates for submission of the grant

application to the State, project completion dates, the date for completion of

construction, pretreatment milestones (see the Rhett-Miller memorandum on

pretreatment program coordination dated November 28, 1978), and the date for

achievement of final  effluent limitations. *



     Whenever possible, representatives knowledgable of both Permits and

Construction Grants programs should be at meetings with the grantee/permittee

to discuss the information placed in the draft NPDES permit and grant

conditions.  A pre-public notice, conference, and/or grant preapplication

conference may also resolve certain permit problems before the permit is issued

and thus reduce the number of evidentiary hearing requests.
* For a discussion of interim compliance date slippage, see 40 CFR
122.31(f)(3).
                                     -19-

-------
If no pre-public notice conference is held, the permittee  should  be  made  aware




of the proposed schedule and allowed to comment on the schedule before  public



notice of the permit is given.








     After me permittee has made any comments on the draft  permit,  the Permits



staff will puDlish notice of tne draft permit and make any chanyes resulting



from trie public notice.  Permits and Construction Grants staffs should  then




jointly determine if such chanyes to the draft permit may  affect  the existing



or proposed construction grant award.  If  so, the grant should be  adjusted



accordingly.  The Permits staff would then  issue the permit  in final form.



depending on the circumstances, the  final  permit may be issued either before or



after the award of the construction  grant.  Where the grant  award  satisfies



permit requirements, Grants staff should reference the NPDES permit  number  in



tne grant, and Permits staff should  reference the construction grant award



identification number  in the permit.  It is not necessary  to defer grant  award



until the permit is issued, unless significant permit issues directly affect



the type of project for whicn the award is  intended.  However, if  an



evidentiary neariny is requested and granted on construction grant-related



issues, both programs  must again coordinate to share information  necessary  to




resolve the evidentiary hearing (e.g., how  schedules were  developed, etc.).  No



grants to PuiWs should be awarded that relate to the permit  issue  in question



while relevant portions of the permit are  stayed by the evidentiary  hearing.



Once the eviaentary hearing is resolved, Permits should issue a final permit



and Construction Grants should make  necessary amendments to  the grant award.
                                       -20-

-------
The Relationship of Section 301(h) to Section 301(i)(l)

     In the Regions and NPDES States which have POTWs discharging  into iiarine

or estuarine waters, almost all POTWs which submitted preliminary  applications

for section 301(h) permit modifications also requested 301(i)(l) permit

extensions.  Where the POTWs submit final applications for 301 (h)  permit;

modifications, the 301(h) application should be processed first. *  If the

301(h) is granted, it will be the basis for the new compliance schedule and the

301(i)(l) request becomes moot.   If the 301(h) is denied, the 301(i)(l) request

should then be considered in the  same manner as other 301(i)(l)  requests.

Specifically, if the POTW can complete construction by July 1, 1983, the

request should be granted; if the POTW cannot complete construction by July 1,

1983, the request should be denied and a 3Q9(a)(5)(A) order may  be  issued not

extending beyond July 1, 1983.



     In some cases, the delay pending the 301(h) determination will force a

POTW in Category  I into Category  II, and a 309(a)(5)(A) order must  be  issued

rather than a 301(i)(l) extension.  In order to minimize this occurance, POTWs

should be advised to proceed with construction until they reach  the critical

point at which further construction will depend on EPA's decision  concerning

the 301(h) application.
* See 40 CFR 125 Subpart G, "Modification of Secondary Treatment Requirements
for Discharges into Marine Waters."
                                     -21-

-------
PART VI:  ISSUANCE OF 309(a)(5)(A) ADMINISTRATIVE ORDERS








     where construction cannot be completed by July 1, 1983, a 309(a)(5)(A)



order Must be issued.  The objective of issuing section 309(a)(5)(A;



administrative orders in lieu of 301(i)(l) extensions is to establish an




enforceable schedule for compliance based on progress which can be made up to



19b3 -- even tnough the schedule does not require completion of construction.



The following flow chart (Figure C) illustrates an approach to issuance of



section 309(a)(5)(A) administrative orders (or comparable State procedural



mechanisms) when used as a means to obtain an enforceable compliance schedule.








     Section 309(a)(5)(A) administrative orders in lieu of  301(i)(l) extensions



must always be issued (and notice given to the public} in conjunction with an



underlying permit which requires compliance with the July 1, 1977 treatment



requirements, except as described in Part VIII for treatment more stringent



than secondary.  Where section 309(a)(5)(A) administrative  orders in lieu  of



301(i)(l) extensions are appropriate, compliance schedules  in the



administrative order will be determined by the identified dates on which



funding either is available  in an existing grant agreement  or wi11 be available



in projected grant funding derived from the approved Project Priority List.




The coordination between Enforcement and Grant programs in  the issuance of



these orders should  be the same  as that discussed  in Part V.








     The  contents of these 309(a)(5)(A) administrative orders will differ



slightly  depending on whether the administrative order is for a POTW in



Category  I,  II, or  III.  Each administrative order  is to contain  a compliance



schedule  which reflects milestone dates derived from the grant process.   Since
                                       -22-

-------
                             FIGURE C

              APPROACH TO THE ISSUANCE OF§309 (a)(5)(A)
                       ADMINISTRATIVE ORDERS
  POTW INELIGIBLE FOR A§301 d)
  EXTENSION BECAUSE IT CANNOT
  COMPLY BY 1983 OR IT FAiLED TO
  APPLY IN TIME FOR AN EXTENSION
    GRANTS/ENFORCEMENT
    EXAMINES PROJECT PRIORITY
    LIST FOR FUNDING STATUS
     IDENTIFY PROJECTS
     UNDERGOING AWT REVIEW
     AND COMPLETE REVIEW
      GRANTS/ENFORCEMENT
      FORMULATES
      COMPLIANCE SCHEDULE
        POTW APPLIES FOR
        GRANT ASSISTANCE.
        IF NECESSARY
      ENFORCEMENT DRAFTS
      ADMINISTRATIVE ORDER
GRANTS FINALIZES GRANT SCHEDULES
    ENFORCEMENT FINALIZES AND
    ISSUES ADMINISTRATIVE ORDER
    ALONG WITH NPDES PERMIT
GRANTS AWARDS GRANT
(REFERENCING
ADMINISTRATIVE ORDER)
                                                    T
 COMPLIANCE SCHEDULE ENTERED
 INTO TRACKING SYSTEM (IN
 ACCORDANCE WITH THE
 MUNICIPAL MANAGEMENT SYSTEM)
                                23-

-------
construction grants are awarded  in steps, and the  funding  may  not  be  continuous



\except for combined Step 2+3 grants;, issuance of  succeeding  administrative



orders r.ay often oe necessary.   In no event  should  an  administrative  oroer



contain a compliance schedule extending beyond July  1,  1983, the final  date  for



•r.unicipal compliance established by Congress  in section 301 •'}(!}.  Thus, the



last compliance cate in the adniinistrative order will  be the last  identified



cate in tne PuTW's grant schedule prior to July 1,  1983, even  if that  date only



takes the PuTw through part of the construction grant  process  and  toward  final



1 innts.







     PuT'wS in uategory I which have not requested  301(i)(l) extensions  and



which do not hold tCSLs may be issued administrative orders.   It should be



noted that only one administrative order need be issued for each POTW  in



Category I in this case.  This administrative order will move  the  permittee



through the entire grant process toward completion  of  construction  by July 1,



lyt>3 (see Part V).







     POTWs in Categories II and  III cannot receive  301(i)(l} extensions because



construction will  not be completed by July 1, 1983.  Such  POTWs should  be



issued 309(a)(5)(A) administrative orders. Each administrative order  should



reflect one step in the permittee/grantee's  construction grant award  and  should



require compliance with the requirements of  that step  by the final  date for the



completion of the step, or July  1, 1983, whichever  is  earlier.







     In Category II, a POTW may  not currently be funded beyond facility planning



(Step 1), requiring issuance of an administrative order in which the  final
                                      -24-

-------
compliance date will  be  the  Step  1  completion  date.   Subsequent  administrative



orders would be issued  incrementally,  with  compliance  schedules  reflective the



las': dates of each  construction grant  award.   Public  notice need not  be given



for orders subsequent to  the  *irst.








     In Category  .'I!, ^ore than one  administrative  order  -nay he  necessary to



carry the POTW as far as  possible  through  the  construction  grant process by



July 1, !9P?, as  grant milestones  are  Identified.   Again, public rotice need



not be given for  orders  subsequent  to  the  first.








     Administrative orders are  intended  to  be  managed  like  301(i}(l)



extensions.  Thus,  a  PQTW's compliance with  its  administrative  order  should be



monitored as would  a  301(i)(l)  extension,  and  the enforcement  response to any



violations of such  an administrative order  would be carried out  in  accordance



with procedures delineated in a Region or  State's Enforcenent  wanagement System



(see Part X).








     Should a NPPES State propose  to grant  a 3ni(i)(l)  extension to a POTW in



Categories II, III, IV, V, or VI,  the Region should object  to  and  if  necessary,



veto ''he permit.  When a NPDES  State proposes  to issue  an administrative order



in lieu of a 301(i)(l) extension to a POTW  within Categories  II  or  III,  the



Region should closely review the administrative  order  to  assure  that  it



comports with this National Municipal Policy and Strategy.   If the  order does



not comport with  this Policy and Strategy,  for example, because  the State



administrative order goes beyond July 1, 1983, the Region  should request that
                                     -25-

-------
the order be issued in confornity with this Policy  and  Strategy.   If  the  State



does not so modify the administrative order, the  Region  should  inform the



PCT'w and the State that the State order  is without  authority  and  that



compliance with it alone will not protect the  POTW  fron  Federal enforcement.



Further, the Region always retains  its right to take  enforcement  action



independent of any State enforcement action.
                                      -26-

-------
PART VII:  PRIORITIES FOR ISSUANCE OF EXTENSIONS AND ADMINISTRATIVE ORDERS



     Optimum use of resources is required in the issuance of modified permits

and administrative orders and the awarding of construction grants if the 1983

deadline is to be ~:et.  Following is the priority in which these activities

should occur:



                   PRIORITY FOR ISSUING 301(i)(1) EXTENSIONS

                    AND 309(a)(5)(A) ADMINISTRATIVE ORDERS

     1.   Active Grants with Pretreatment Requirements

               —Step 3
               --Step 2
               --Step 1

     2.   Grantees on Fundable (One Year) Portion of Project Priority List

          (Grants not yet awarded)

               —Step 3
               --Step 2
               —Step 1

     3.   Active Major Grantees (Funded from Previous Project Priority List)

               --Step 3
               —Step 2
               —Step 1

     4.   Active Minor Grantees (Funded from Previous Project Priority List)

               --Step 3
               --Step 2
               --Step 1

     5.   Unfunded
                                     -27-

-------
     This priority ranking tatces several considerations  into account  including



tne Agency's emphasis on toxic substances control, funding availability,



aMiit> to formulate fixed date permit  scnedules, and size ana environmental



effect of the discharge.








Pretreatinent Priorities



     The General P^etreatment Regulations (40 CrK 403) require POTws  with



design *Iows ot greater than 5 mgd to develop pretreatment programs  (PGTWs with



flows of 5 i.igd or less may be required  to develop a pretreatment program  in



certain circumstances).  Compliance schedules for development of pretreatment



programs must be incorporated into all  such  permits when the permits are



reissued or modified (e.g., when a permit is reissued or modified to



incorporate a 3Gl(i)(1) extension).  Some NPDES States have the authority to



place pretreatment compliance schedules in permits prior to the approval of



State pretreatment programs.  Where NPUES States do not  have the authority to



write pretreatment compliance schedules prior to State pretreatment  approval,



the NPUES permit must contain a reopener or modifier clause (see 40  CFR



4U3.1G(d)(1)) and the permit must be subsequently modified, or revoked and



reissued.  Alternatively,  in those NPDES States lacking  such pretreatment



authority, issuance of NPDES permits to POTWs with pretreatment requirements



may be deferred until the  State obtains this authority.








     Federal funding for the development of pretreatment programs is  available



under the Construction Grants Program.  The construction grants regulations



^40 CFR Subpart E) require the completion of certain elements of the



pretreatment program prior to award of  Step 2 grants after June 30,  1980, the
                                     -28-

-------
completion of the remaining elements prior to award of Step 3 grants after
December 31, 1980, and the approval of a POTW pretreatment program by the 90
percent completion stage of Step 3.  The pretreatment regulations (40 CFR 403)
require POTW pretreatment program approval  by July 1, 1983, or three years
after the permit is either modified or reissued, whichever is earlier.  It is
anticipated that it will take up to six months after submission of the program
to obtain approval.  Accordingly, submission of an approvable pretreatment
program should be six months before the 90 percent Step 3 completion stage, or
2-1/2 years after the permit is modified or reissued, or January 1, 1983,
whichever is earlier.

     Given the above deadlines, the first order of priority of the Construction
Grants Program must be to amend existing grants as soon as possible to provide
for development of pretreatment programs.  Similarly, issuance of permits to
provide for pretreatment programs is of top priority.

Funding Availability and Schedule Development
     The second order of priority is POTWs  on the fundable portion of the
Project Priority List.  These POTWs represent the fiscal  year's workload for
the Construction Grants Program and will  require construction to comply with
NPDES permit limitations.

     The priority established for issuing 301(i)(l) extensions requires Step 3
projects to be processed first, Step 2 second, and Step 1  last.   The rationale
in support of this hierarchy is that, generally speaking,  more information is
available at the later steps in the grant process.  Additionally, schedules
                                     -29-

-------
with shorter time intervals and hence with a greater accuracy will be



developed, thus either minimizing or reducing the possibility of formal permit



modification due to the inclusion of unrealistic dates in the NPDES permit.  In



the case of schedule development for Step 2 and Step 3 projects for which



facility planning requirements (Step 1) have been completed, the States or



Regions are to establish the appropriate time intervals required to complete



Step 2 and Step 3 projects, and, together with the dates of funding



availability contained in the State's PPL, to specify accurate _fixed dates for



initiation and completion of the step.  A key point to note is since funding is



available for these POTWs, 301(i)(l) permits are required to contain fixed



schedule dates.







     Many of the factors which led to the utilization of the "trigger date"



schedule in the past have either become moot or less relevant.  Thus the Agency



has reevaluated its position regarding continued utilization of this type of



schedule and the 301(i) regulations (40 CFR 125.94 (a}(l)) now requires use of



fixed dates.







     Of the three step grant process, Step 1, which provides for development of



facility plans, has been the most difficult to maintain on schedule.  A number



of other Federal statutes (e.g. the Historic Preservation Act, Endangered



Species Act, National  Environmental Policy Act, Wild and Scenic Rivers Act, and



certain Executive Orders) establish requirements which may affect the scope of



the planning process and hence the completion date in mid-course.   The scope



of the project may also be revised as a result of the public hearing required



prior to approval of the facility plan under the Construction Grant



regulations.
                                     -30-

-------
     In recognition of the above, the  fixed  schedule approach adopted  in  the



NPDES regulations distinguishes Step 1 schedule development  from  that  of  Steps



2 and 3.  Under this approach, the Step  1 schedules would  be based  upon the



expected date of the Step 1 award, in  consideration of availability of Federal



funding, and establishment of an appropriate time period to  complete Step  1



work, based on the estimated project scope and the project's ranking on the PPL



for Step 2 funding.  Fixed dates would then  be incorporated  in  the  NPDES  permit



and would also serve as the basis for  the grant period in  the subsequent  grant



award.   The permit may be conditioned  to expire at that completion  date.   For



active Step 1 grants for which the permit is expected to expire prior  to



completion of the Step 1 project and for which permit reissuance  is urgent, it



must be determined if planning has progressed to the point where  a  completion



date can be specified and the required schedule (40 CFR 35.917-1(a)) for



completion of Steps 2 and 3 is available.  Where this information is available,



the schedule should be checked against the PPL.  If the schedule  dates precede



dates of funding availability, the schedule  should be adjusted  to reflect  the



earliest expected date of grant eligibility.  If those dates fall outside  the



fundable range of current allotments,  the Regions or States  should  assume



appropriations to the extent indicated in the Agency's annual operating



guidance.  In the event facilities planning  has not sufficiently  progressed to



establish Step 2 and Step 3 schedules, the permit should be  conditioned to



expire or be modified shortly after the date of project completion  contained in



the Step 1 grant awarded as previously discussed.







     Schedules for which Step 1 activities have been completed  prior to permit



reissuance should be developed based upon the grantee's submitted schedule and



Federal  funding availability, allowing for reasonable Agency review time.
                                     -31-

-------
Agency review time should be established based on State and Regional



experience, average review times as determined from Grants Information Control



System (GIGS) data, Regional workplans, output commitments, or the Zero Base



Budgeting process.







     In the case of segmented projects where more than one Step 2 or Step 3



grant exists or is expected to be awarded, schedules should be developed as



previously discussed for each significant project segment for inclusion in the



NPDES permit.  For this purpose, a significant project segment is one for which



completion is necessary in order for the permittee to meet final permit



limitations or a project for which a delay would result in delay of attainment



of final  effluent limits by the date established in the NPDES permit.  If there



is any question concerning whether a project segment is significant under this



definition, Grants, Permits, and Enforcement staff should jointly arrive at a



final determination.  Individual or multiple permit schedules should clearly



identify  the associated construction grant project number.







     Priority numbers 3 and 4 are consistent with past policy for issuance of



NPOES permits.  Priority number 5 is self-explanatory.
                                     -32-

-------
PART VIII:  TREATMENT MORE  STRINGENT  THAN  SECONDARY




     In considering the  fiscal year 1979 appropriations  bill  for the

construction grants program,  the  Appropriations  Conference Conmittee indicated

that the Administrator must  personally  approve  all  projects  providing  treatment

more stringent than secondary (see Appropriations  Conference Committee Report,

Amendment No. 23).  The  Report states that  Federal  funds  may be awarded for

construction of such advanced treatment with  an  incremental  cost of more than

$1,000,000 only if the Administrator  personally  determines that it  will

definitely result  in significant  water  quality  and  public health improvements.

The advanced treatment review requirement  will  affect  the permit process and

enforcement under  the Clean  Water Act in a  number  of ways.




     During the grant award  review period  for advanced  projects, some  NPOES

permits requiring  treatment  more  stringent  than  secondary will  expire.   Since
                                            •
compliance schedules and final effluent limitations  in  the reissued NPDES

permit depend upon the results of the review, these permits  should  not  be

reissued until the initial  review is completed  in  accordance with the  Office of

Water Program Operations, Program Requirements Memorandum (PRM) 79-7.   However,

advanced projects  are to be  promptly  identified.




     In all  cases  where  the  NPDES permit, whether  current or expired,  requires

treatment more stringent than  secondary and the  PRM review has  not  been

completed, enforcement of effluent limitations requiring  the more stringent

treatment should be deferred  pending completion  of the  review.   The POTW

should proceed with any  fundable  steps which can be taken toward achievement
                                      -33-

-------
of secondary treatment as long as such steps are not  incompatible with  the



more stringent facility design.







     In some cases (e.g., where 1977 NPDES permit requirements have not



been clearly established and the NPDES permit has expired),  it may be



necessary to issue a section 309(a)(5)(A) administrative order (absent  an



underlying NPDES permit) which incorporates interim effluent  limitations



and a schedule of compliance to assure progress toward the  installation of



secondary treatment.







     Five possible determinations may be expected from the  PRM review



process:







     (1) The more stringent project as proposed is fully justified and  is



     fully fundable (although the project may not currently  be on the



     fundable portion of the Project Priority List);  or







     (2) The more stringent level of treatment required of  the POTW was



     based on incorrect or inadequate water quality analysis  and, therefore,



     the more stringent portion of the project as proposed  is not required



     and is not fundable, but a lesser level of treatment  is  justified  and



     is fundable; or







     (3) The more stringent level of treatment required of  the POTW was



     based on incorrect or inadequate water quality analysis, and advanced



     treatment may not be required to satisfy water quality  requirements,



     but additional information is needed to determine what  is the



     appropriate and fundable treatment  level; or
                                     -34-

-------
     (4) The more stringent level of treatment is justified but a reeval-
     uation of the cost-effective analysis and/or design of the entire
     project or portion of the project is recommended to arrive at a less
     costly treatment alternative or configuration; or

     (5) Treatment greater than secondary is required to achieve more
     stringent State requirements, but the greater level of treatment has
     been determined by the PRM review to be ineligible for construction
     grant funding, and the State has chosen not to relax its requirements.

     Should the PRM review result in determinations (1) or (2) above, the
POTW will fall into one of the categories of POTWs as outlined in Part III
and should be dealt with accordingly.

     Determinations (3) or (4) above could result in funding being deferred
for the entire facility or any element of the facility pending the further
information gathering and subsequent analysis.   In these situations,
although the final PRM review is not complete, the process previously dis-
cussed for determining eligibility for a 301(i)(l) extension under Part IV
of this document should be applied.   Should application of this process
result in a POTW falling into Categories I, II or III as outlined in Part
III, the appropriate requirements of any construction grant or grant amend-
ment awarded the POTW for purposes of gathering additional information are
to be incorporated into the NPDES permit or 309(a)(5)(A) order, whichever
instrument is applicable under this National Municipal Policy and Strategy.
                                    -35-

-------
     If the PRM review results in determination  (5), the reissued permit



must contain final effluent limitations which are necessary to meet the more



stringent State requirements.  However, since the more stringent treatment



will not be Federally funded in these instances, enforcement of these permit



requirements calls for special consideration.  For Federally-issued permits,



there should be a commitment from the non-NPDES  State prior to permit



issuance to enforce the more stringent requirements.







     With regard to enforcement by EPA, if the POTW has not significantly



contributed to construction delays, enforcement  of more stringent than



secondary requirements imposed pursuant to determination (5) should be



postponed, and a construction schedule taking the POTW through to completion



of that portion of the project which the PRM review has determined to be



fundable (secondary treatment at a minimum) should be required, generally by



means of a section 309(a)(5)(A) administrative order.  If, however, the POTW



subsequently violates its compliance schedule, action to enforce the more



stringent treatment requirements consistent with the Municipal Referral



Priority System (see Part IX) is appropriate.  Even though a POTW has ex-



peditiously completed construction to the fundable treatment level, the more



stringent requirements are legally enforceable.







     The State nay elect to relax its more stringent requirements to the



level which has been determined by EPA's PRM review to be fundable.  In that



case, the NPDES permit may be modified to require the less stringent final



effluent limitations, and a compliance schedule  for achievement of the



fundable treatment level should be established.
                                     -36-

-------
PART  IX:  MUNICIPAL  REFERRAL  PRIORITY  SYSTEM

Purpose
      The Municipal Referral Priority System  (MRPS)  is  a  system  for  identifying
and setting priorities  for case  referrals  to  the  Department  of  Justice  by  EPA
and to State  Attorneys  General by  the  State.   This  system  assumes  that
enforcement actions  short of  referral,  if  appropriate, have  been taken  and did
not achieve the desired  results.

     Referral  for judicial action  against  POTWs which  failed  to meet  the July  1,
1977 treatment requirements can  have one or more  of  the  following  results:

     o  assessment of penalties  for past violations  in accordance with  the
        April  11, 1978  Penalty Policy Memorandum
     o  imposition of judicially enforceable  compliance  schedules
     o  penalties for noncompliance with the  judicially  imposed schedules
     o  appointment  of  a special master
     o  sewer  hook-up bans as authorized by section  402(h) of the Clean Water
        Act
     o  the availability of the  funding necessary for  completion of
        construction as a result of 309(e} of  the Clean  Water Act
 NPDES States  which  have the authority to  assess  administrative penalties
should do so first,  because administrative penalties contain  some (but  not  all)
elements present in  the referral process and may achieve the  desired  results
more expeditiously than referral for judicial  action.
NOTE:  Judicial action against POTWs which did not significantly contribute to
       delays in construction and for which judicial action is necessary to
       assure the availability of construction grant funding will not ordinarily
       seek assessment of penalties for past violations.
                                       -37-

-------
Scope
     Candidates for judicial action under the MRPS are: (1) all POTWs for which
construction is needed but which do not qualify for a 301(i)(l) extension and
will not receive a 309(a)(5)(A) administrative order (Category VI): (2)
recipients of section 301(i)(l) permit extensions, 301(h) permit modifications,
ECSLs, or administrative orders which subsequently violate such extensions,
ECSLs or administrative orders; and (3) POTWs which have completed construction
but are not meeting the final effluent limits or other requirements of permits
(Category V).  POTWs in Category IV which are subject to referral as a means of
moving the POTW into Category II are discussed in a separate section in this
Part entitled, Special Enforcement.

Effect of 301(i)(1) Request on Initiated Referrals
     In determining that a judicial action should be taken against a POTW for
failing to meet the July 1, 1977 deadline, the Agency has necessarily
determined that the failure of the POTW to meet that deadline is attributable
in a significant measure to the POTW's own action or inaction rather than the
unavailability of Federal funds alone.  Since this determination is dispositive
of 301(i)(l) requests, requests in these cases should be denied for any POTWs
against which such a judicial action has been filed or referred.  The initiated
referral shall continue unaffected by the MRPS.

Procedure
     The referral priority rank for a POTW is based on the POTW's size and
treatment level, with possible adjustments if certain factors are present.  The
                                     -38-

-------
referral  priority ranking of each POTW within either an EPA Region or a NPDES

State should be derived as follows:
     (1)  List all major POTWs in the Region or State according to population
          served, from the largest to the smallest (regional sewer authorities
          should be ranked according to the total population served by the
          regional POTW); and

     (2)  Rank those POTWs into three population-served groups (POTWs with
          populations greater than or equal to 100,000, POTWs with populations
          from 50,000 to 99,999, and all other POTWs); and

     (3)  Within each of these three population groups, rank the POTWs
          according to current treatment level:

          (a)  POTWs with no treatment  (raw sewage dischargers).

          (b)  POTWs with primary treatment installed and waste treatment
               requi red.

          (c)  POTWs with primary treatment installed and secondary treatment
               required.

          (d)  POTWs with intermediate treatment installed and advanced
               waste treatment required.

          (e)  POTWs with intermediate treatment installed and secondary
               treatment required.

          (f)  POTWs with secondary treatment installed and advanced waste
               treatment required.

          (g)  POTWs with secondary treatment installed but not in compliance
               with effluent limitations.

          (h)  POTWs with advanced wastewater treatment installed but not in
               compliance with effluent limitations.

     (4)  Within each of the eight current treatment  level groups, rank POTWs
          according to the following eight priority factors in order of
          importance:

          (a)  Significant drinking water use/public  health hazard;

          (b)  Fisheries,  shellfish and protected areas, and/or scenic and
               recreational  areas threatened;
                                       -39-

-------
          (c)  Failure to develop adequate pretreatment programs or to operate
               an approved program under 40 CFR 403, or have had a spill  of
               toxic and/or hazardous materials within the previous calendar
               year;

          (d)  Reconstruction lag greater than twelve months (see Office of
               Water Program Operations, Program Requirements Memorandum 78-12),

          (e)  PGTW is eligible but has not applied for a grant (more than six
               months late),

          (f)  POTW is eligible but has not applied for a grant (less than six
               months late);

          ( g)  Blatant disregard of standard operation and maintenance (O&M)
               procedure;

          (h)  Poor O&M practices which have detrimental  effects on POTW
               performance.
Special Enforcement:  Public Health and Fragile Ecosystems

     Development of a referral  priority list should not be perceived as

restricting the Region's discretion to immediately pursue actions against other

significant municipal pollution sources where violations of a POTW's NPDE5

effluent criteria result in a threat to the general public health and safety in

an area.  The POTW would move into a top priority position for the allocation of

Regional and State resources, overriding the normal order of referral as

established by the MRPS.



     Consideration for  special  enforcement may be given on a case-by-case basis

for municipalities causing damage to fragile ecosystems, defined as fisheries

or special  recreational areas.   Such requests should be made in writing to the

Deputy Assistant Administrator  for Water Enforcement.
                                     -40-

-------
Special Enforcement:  Category  IV
     Additionally, selected POTWs which would otherwise fall  into Category  III
should be candidates for referral when the POTWs are causing  either significant
threats to the public health and safety or damage to fragile  ecosystems, and
they are low on the State Project Priority List.  In these cases, the referral
mechanism is the best or only one available to assure prompt  achievement of
NPDES permit requirements.

Implementation
     EPA Regional Offices are required to use the MRPS to produce lists of
identified Regional and NPDES State municipal referral candidates.  As POTWs
fail to meet the terms and conditions of their ECSLs, administrative orders,
permit modifications or extensions, or are deemed to be enforcement candidates
under MRPS, they should be added to the MRPS lists and ranked accordingly.
Candidates ranked according to MRPS include those POTWs in the municipal Major
Source Enforcement Effort (MSEE) which have violated the July 1, 1977 statutory
deadline for the installation of secondary treatment technology.
                                     -41-

-------
PART X:  FORMULATING A MUNICIPAL MANAGEMENT SYSTEM



     An overall Municipal Management System (MMS) will serve as the key

mechanism through which EPA Regional and State Enforcement and Grants staffs

develop formal operating procedures to support preparation of compliance

schedules in 301(i)(l) extensions and 309(a)(5)(A) administrative orders as

well as to respond to instances of noncompliance when they occur.  While the

emphasis of this system will be on updating the current Enforcement Management

System (EMS), numerous grants management activities must be added.



     Four work groups were specified in the "Interim National Municipal Policy

and Strategy" (September 1978).  These workgroups, comprised of State and EPA

representatives, met in the period from November 1978 through March 1979 and

addressed the following subjects:



     o  Permits and Grants interaction

     o  Compliance and Grants information systems

     o  Noncompliance response guidance

     o  State-U.S. EPA cooperation



The products of the four municipal workgroups are designed to provide a more

detailed framework for Regional and State program managers to implement the

policies herein.  The municipal workgroup products provide for:



     o  Issuing effective NPDES permits

     o  Developing a common data link between the Permit Compliance System (PCS)
        and the Grants Information Control System (GICS)
                                     -42-

-------
o  Implementing a consolidated noncompliance response guide for
   coordinating Grants and Enforcement response

o  Developing formal Regional and State operating procedures for dealing
   with POTWs

o  Instituting time frame controls for implementing action steps specified
   in the MMS
                                -43-

-------