PB97-963154
                                  EPA/541/R-97/172
                                  January 1998
EPA   Superfund
        Explanation of Significant Difference
        for the Record of Decision:
        City Disposal Corp. Landfill
        Dunn, WI
        6/11/1997

                                           floor

-------
             EXPLANATION OF SIGNIFICANT DIFFERENCES

                                      FOR THE
                    CITY DISPOSAL CORPORATION LANDFILL
                                 DUNN, WISCONSIN
The purpose of this document is to explain and justify changes to a portion of the remedy at the
City Disposal Corporation Landfill (CDCL) Superfund site  In brief, the changes involve
temporary extraction and treatment of contaminated groundwater at the site  According to this
solution, contaminated groundwater will be extracted on-site and transported for off-site
treatment and disposal The extracted groundwater may be treated at a nearby publicly owned
treatment works (POTW) or possibly another nearby Superfund site, the Hagen Farm site   For
further details concerning the nature of these changes, please refer to Section IV herein,
concerning the  "Description of the Significant Differences and the Basis for the Differences "

I.  Introduction

The CDCL site is located on approximately 38 acres of land in section 30, township 6 North,
range 10 East in Dane County, Wisconsin. The landfill was opened in the mid 1960s, and closed
in  1977 Household wastes, industrial wastes, general construction wastes, and debris were
disposed at the site Industrial wastes included, but were not limited to, discarded solvents from
plastics manufacture, paint wastes, oily residues, etc  Total volume of wastes disposed are
approximately 700,000 cubic yards.  Of the twelve cells which existed at the site for waste
disposal, it is believed that Cells 6 and 12 received largely industrial wastes

The site was placed on the National Priorities list in 1984  In 1987 and 1988, various persons
entered into an agreement with the United States Environmental Protection Agency (U.S.  EPA)
for conduct of  a Remedial Investigation and Feasibility Study (RI/FS)  This effort was completed
in  1992, and the RI/FS and a proposed plan for remedial action was placed before the public.
Leading groundwater contaminants associated with the site were found to include tetrahydrofuran
(THF), 2-butanone, acetone, carbon tetrachloride, trichloroethene (TCE), and toluene.

The lead agency for the remedial action at this site is the US. EPA  The State of Wisconsin's
Department of Natural Resources (WDNR) is the support agency for the conduct of remedial
activities at the CDCL site under the authority of the Comprehensive Environmental Response,
Compensation  and Liability Act (CERCLA),  1980 PL 96-510, 42 U.S.C. 9600, et seq..
commonly known as Superfund  In September 1992 the US EPA issued a Record of Decision
(ROD) which outlined the remedy selection process and the selected remediation for this site
This document provides a discussion of significant changes to the manner in which the selected
remedy will be carried out

-------
II.  Requirements to Address Significant Changes

As the lead agency, the U S EPA may determine that a significant change to the selected remedy.
as described in the ROD, is necessary after the ROD is signed  Section 11 7 © of CERCLA
requires that after adoption of a remedial action plan, as described in a ROD

••      (1) if any remedial action is taken,
»•      (2) if any enforcement action under Section 106 is taken, or
••      (3) if any settlement or consent decrees under Section 106 or Section 122 is entered into,
       and if such action, settlement, or decree differs in any significant respects from the final
       plan, the lead agency shall publish an Explanation of Significant Differences (ESD) and the
       reasons such changes were made  (42 US C  9617(c))

The US  EPA, in consultation with the WDNR, has determined that significant changes should be
made to the manner in  which the remedial action plan, as described in the ROD, is carried out
These necessary changes are discussed further in Section IV

The ESD will be available for review in the administrative record  established for the CDCL site
This record is located in both the seventh-floor Records Center at US  EPA offices at 77 West
Jackson Boulevard, Chicago, Illinois and at the  information repository available locally for this
site at the Dunn Town  Hall, which is located at  4155 County Trunk Highway B, McFarland,
Wisconsin  Opportunity  for review is available  during normal business hours US EPA
Remedial Project Manager Russell Hart, (312) 886-4844, or WDNR Project Manager, Mike
Schmoller, (608) 275-3303, may also be contacted
III. Background

A. Site History

In September 1992, US EPA signed a Record of Decision (ROD) calling for placement of a
nonhazardous waste cover over the majority orthe site, placement of a hazardous waste cover
over Cells 6 and 12, landfill gas venting and treatment and groundwater extraction and treatment,
along with appropriate monitoring

In March  1993, US EPA issued a Unilateral Administrative Order (UAO) which called for the
private conduct of necessary remedial design and remedial act'on (RD/RA) to bring about
execution of the ROD  The UAO was issued to a potentially responsible party, Waste
Management of Wisconsin, Inc., associated with the site

Conduct of the remedial work at the CDCL site has proceeded in two distinct phases  Source
control elements of the  remedy have been given first priority, such that design activity performed

-------
in  1994 emphasized appropriate site cover and gas venting  It was reasoned that a reduction in
infiltration of precipitation through the waste mass would help in simplifying groundwater control
efforts  Hence, following remedial design approval by the agencies, installation of the landfill gas
collection system and clay cap was performed from June through October 1995  Work on the
collection system involved the excavation of trenches followed by the installation of piping  The
cap included a 2-foot thick clay cap over the entire landfill, a 40-mil high density polyethylene
geomembrane cap and geonet/geotextile composite drainage layer over Cells 6 and 12, and an 18-
inch cover soil and 6-inch topsoil layer over the entire landfill  An on-site clay deposit was
investigated and found to be suitable for cap construction, thereby removing a concern expressed
by WDNR and the public about the potential difficulty of bringing in truckloads of clay from an
outside source.

Once this work was complete, attention shifted to groundwater control elements of the remedy
In  late 1995-early 1996, a pump test was convicted at the site to assist in providing an estimate of
extraction rates necessary to capture the plume of groundwater contaminants  Treatability tests
were conducted using site water samples to help determine the most efficient and cost-effective
means of removing groundwater contaminants
B. Summary of Site Contamination Regarding Groundwater
For conceptual purposes, the site has been divided into six area zones so as to characterize
groundwater contamination.  Area zones I, IV, and VI are located east of Badfish Creek,
southeast of the landfill, and southwest of the landfill, respectively. Organic chemical compounds
have been found to be either at nondetectable levels or otherwise are at negligible levels in
groundwater associated with these areas. Area VI is considered an upgradient zone

Areas II and V are located north and east of Cell 12, respectively, while Area III is north of Cell
6  Sampling of groundwater wells in Area III resulted in findings of THF and TCE at levels of 12
and 8 ug/1, respectively. TCE was found at a level of 11 ug/1 in Area V. Area II revealed sharply
higher findings. At a depth of 58 feet, 2-butanone was detected at a concentration of
approximately 520,000 ug/1, THF at a level oc 170,000 ug/1, and toluene was 2000 ug/1  At the
greater depth of 78 feet, concentrations of these contaminants dropped significantly  2-butanone
was 240 ug/1, THF at 2,100 ug/l, and toluene was at 43 ug/l
C.  ROD Provisions


The original ROD was signed for the site on September 28, 1992  The ROD addressed the
collection and treatment of contaminated groundwater  However, the US. EPA and WDNR
have since determined that there is a need to make changes in the execution of the remedy with

-------
                                           4

regard to contaminated groundwater management  These changes are discussed in the following
section
IV. Description of the Significant Differences and the Basis for the Differences
A.  Description

As described in the ROD, CDCL groundwater management was to have entailed on-site treatment
of collected groundwater and discharge to nearby Badfish Creek in accordance with appropriate
effluent limitations  Commencement of remedial action for groundwater management at CDCL
was not contemplated until all pertinent design steps involving groundwater were complete

However, US EPA and WDNR believe that there is significant advantage to be realized by early
commencement of remedial action for groundwater management at CDCL  This would likely
involve temporary shipment of collected groundwater from CDCL to another compatible facility,
and a combined discharge from the other facility Badfish Creek would not be the expected
receiving water for the discharge  A series of events leads to this conclusion

B.  Basis

As noted in Section III A of this document, treatability tests have been performed in an effort to
determine the most efficient and cost-effective means of  removing groundwater contaminants
The Groundwater Treatability Study Report which summarized these efforts gave equal weight to
two leading approaches  to possible permanent groundwater treatment at CDCL These
approaches consisted of either biological treatment  as might be carried out in a  sequencing batch
reactor, or a combination of UV-oxidation supplemented by air stripping  The report
recommended further pilot work, but noted that the ultimate decision could be aided if steady-
state extraction conditions could be realized at the CDCL site

Both WDNR and US. EPA strongly advocate that any necessary further field study to refine
these treatment techniques not be  performed as  a " ;tand alone" item  Rather, we believe that
commencing interim aclio.i as soon as possible to extract the contaminated groundwater and
provide temporary off-site treatment would help bring about - if not steady-state conditions - then
at least more predictable contaminant concentrations which may help in determining the long-term
means of groundwater treatment at CDCL

On December 3,  1996, U.S. EPA  and Waste Management of Wisconsin, Inc. representatives
appeared at a meeting of the Dunkirk Township board to discuss one possible means of
performing interim action, which would be to utilize the nearby Hagen Farm  groundwater
treatment facility for receipt of groundwater originating from CDCL  CDCL and Hagen Farm
groundwater and means of treatment now employed at Hagen Farm are compatible  In US

-------
EPA's view, the leading concerns raised at that time were the indeterminate length of time for
groundwater hauling to be conducted, and the possibility of numerous daily trips between the
sites

In February 1997, WDNR and US EPA received a modified plan concerning execution of the
interim action  This plan was distributed to representatives of both Dunn and Dunkirk
Townships The time frame for conduct of the action had been considerably shortened, so as not
to exceed six months   Also, the number of truck trips from CDCL to the as yet unnamed
receiving destination had been reduced considerably. Under most circumstances, water would not
be hauled more than five days per week, and usually only once daily On Mondays or following
holidays, 2-3 trips to the receiving destination may be necessary to work off volume
accumulated  The appropriate de?fination might be any facility capable of providing adequate
treatment of the CDCL water such that satisfactory effluent results are achieved

In Wisconsin, major elements of the National Pollutant Discharge Elimination System (NPDES)
and Resource Conservation and Recovery Act (RCRA) have been delegated to the State  Hence,
the primary regulating body over such matters as appropriate hauling manifests, any necessary
waste permits, appropriate degree of treatment prior to discharge, etc , would be handled by the
WDNR Local ordinances concerning compatibility and lack of interference with publicly owned
treatment works (POTW) would also require attainment, as appropriate. The interim receiving
facility could then be any facility which satisfactorily meets permit requirements and effluent
limitations in accordance with appropriate waste management steps  In the case of a POTW,
provided that Waste Management of Wisconsin, Inc. made ample demonstration to the POTW
that the water would not interfere or pass through the POTW without sufficient treatment, and
that the WDNR was satisfied  the receiving POTW had an acceptable compliance history, the
transaction should be able to occur.

WDNR and US. EPA expect that the interim action could be conducted from roughly the June-
December 1997 time  period.  At  the end of that time, monitoring results would be compiled, and
a commitment made to a permanent treatment concept to be conducted at CDCL During 1998,
it would be expected  that all groundwater treatment design would be completed, and a permanent
groundwater treatment facility established at the CDCL site

Three extraction wells would serve the CDCL site for this interim period  Usage would  be made
of the well from which samples were obtained for treatability study. This well is located in the
highly contaminated Area II zone noted earlier in this document.  Another extraction well has
been installed elsewhere within Area II, approximately 100 feet from the first extraction  well.  A
third extraction well has been installed in Area III  The CDCL extraction wells were installed
near the end of 1996   Commencement of shipments of CDCL water could begin by June 1997,
pending adequate demonstration of effluent attainment, no-interference, and waste management
issues

-------
Both WDNR and US  EPA see considerable potential advantage to be gained through this
interim action  Actual groundwater remedial action could commence at CDCL perhaps a year
ahead of what would be possible otherwise, plus the insight gained in noting contaminant levels
encountered during this time would provide valuable information in selecting the appropriate
permanent treatment mechanism
V. Affirmation of the Statutory Determination

The US  EPA and the WDNR believe that the remedy proposed in this ESD remains protective
of human health and the environment, and complies with state and federal requirements that are
legally applicable or relevant and appropriate to this remedial action The proposed remedy is
also more cost effective than the remedy currently in the ROD   In addition, this revised remedy
approach continues to utilize permanent solutions ar"1 treatment technologies to the maximum
extent practicable for this site
VI. Support Agency Comments

The WDNTl, as the support agency, has had an opportunity to comment on this ESD  WDNR
agrees with the modification to remedial action as described in this ESD
VII. Public Participation Activities

The ESD will be added to the administrative record for the CDCL site.  US. EPA has developed
several Fact Sheets since the ROD was executed to inform interested parties as to CDCL site
progress. U.S EPA has provided both Dunn and Dunkirk Townships, in which are located the
CDCL and Hagen Farm sites, respectively, a copy of the interim remedial action plan
                                  	
William E. Muno, Director/                                 Date
Superfund Division
US  Environmental Protection Agency

-------