CUECost WORKBOOK  DEVELOPMENT
              DOCUMENTATION

                    Version  5.0
                     William H. Yelverton
               U.S. Environmental Protection Agency
               Office of Research and Development
            Air Pollution Prevention and Control Division
                Research Triangle Park, NC 27711
                      September 2009
                                           EPA/600/R-09/131

-------
COAL UTILITY ENVIRONMENTAL COST
(CUECost) WORKBOOK DEVELOPMENT
             DOCUMENTATION

                 Version 5.0
                William H. Yelverton
         U.S. Environmental Protection Agency
          Office of Research and Development
       Air Pollution Prevention and Control Division
          Research Triangle Park, NC 27711
                   Prepared by:
                    ARCADIS
            4915 Prospectus Drive, Suite F
                Durham, NC 27713

        ARCADIS EPA Contract No. EP-C-04-023
                 EPA/600/R-09/131
                 September 2009

-------
Abstract
This document serves as a user's manual for the Coal Utility Environmental Cost (CUECost)
workbook and documents its development and the validity of methods used to  estimate
installed  capital  and annualized  costs. The CUECost workbook produces  rough-order-of-
magnitude (ROM) cost estimates (+/-30%  accuracy) of the installed capital and annualized
operating  costs for air pollution control (ARC) systems installed on coal-fired power plants to
control emissions of sulfur dioxide (SO2),  nitrogen oxides (NOX), particulate matter (PM),
mercury  (Hg), and carbon  dioxide (CO2). In general,  system performance is  an input
requirement for the workbook user. The workbook was designed to calculate estimates of an
integrated ARC system or individual component costs for various ARC technologies used in
the  utility  industry.  Twelve  technologies  are   currently in  the  workbook:  flue  gas
desulfurization (FGD)—limestone with forced oxidation  (LSFO) and  with  dibasic  acid  and
lime spray drying  (LSD); particulate matter removal—electrostatic precipitator (ESP)  and
fabric filter  (FF); NOX control—selective catalytic  reduction (SCR), selective non-catalytic
reduction  (SNCR), natural gas  reburning,  and low-NOx burner (LNB); mercury  control-
powdered activated carbon  (PAC)  injection; and  CO2 control— monoethanolamine (MEA)
process, chilled ammonia process (CAP) and sorbent injection  (SI). It is expected that  this
manual  will be  useful to a broad  audience, including:  (1)  individuals  responsible  for
developing and implementing SO2, NOX, PM, Hg, and CO2  control strategies at sources, (2)
state authorities  implementing pollution control programs, and (3) the interested  public at
large. Moreover,  persons engaged in  research and development efforts aimed at improving
cost-effectiveness of air pollution control technology applicable to coal-fired plants  may also
benefit from this  manual.

Note:
The original model was delivered by Raytheon Engineers & Constructors, Inc.  for Eastern
Research  Group, Inc.  under EPA Contract  No.  68-D7-0001.  Subsequent  revision was
completed by Andover Technology  Partners for ARCADIS under EPA Contract No.  EP-C-04-
023. This  version 5.0 was revised and accompanying documentation  prepared by  ARCADIS
under EPA Contract No. EP-C-04-023.

-------
Table of Contents
                            Table of Contents

Section                                                                         Page
Abstract	i
  Acronyms	vi i
Introduction and Summary	1
  Overview	1
  Background	1
  Workbook Description	2
  CUECost WORKBOOK development and documentation document Contents	4
  Project Approach	5
     NOX Control Estimate	5
     Particulate Matter Control Estimates	6
     SO2 Control Estimates	7
     CO2 Control Estimates	7
     Mercury Control Estimates	7
  Default Plant Criteria	8
  Results	8
Getting Started	10
  Hardware and Software requirements / Internet Access	10
  Getting Started	10
Workbook Layout and Methodology	12
  Workbook Layout	12
  Methodology	14
Input and Output Options	20
  Input Data	20
  Output Options	21
Worksheet Validation	22
  FGD Worksheets - LSFO and LSD Technologies	22
  Particulate Matter Control Worksheet	23
  NOX Control Worksheet	25
  Mercury Control Worksheet	27
  Carbon Dioxide Control Worksheet	28
  Validation Summary	29
References	30
Appendix A Terminology Definitions, Abbreviations, Acronyms, and Range Names	33
  A. 1  Definition of Terms	33

-------
Table of Contents
Appendix B Technology Descriptions/Criteria	36
   B.I   Limestone Forced Oxidation Design Criteria	36
   B. 2   Lime Spray Dryer Design Criteria	39
   B.3   Particulate Matter Control Design Criteria	41
   B.4   NOX Control Technology Criteria	42
     B.4.1   Selective Catalytic Reduction Design Criteria	43
     B.4.2   Selective Non-catalytic Reduction Design Criteria	45
     B.4.3   Natural Gas Reburning Design Criteria	47
     B.4.4   Low-NOx Burner Technology Design Criteria 	49
   B.5   Hg Control Technology Criteria	50
     B.5.1   Mercury Removal Models	50
     B.5.2   Mercury Removal by Existing Equipment, fasting equipment	51
     B.5.3   Mercury Reduction by PAC injection, fPAc injection	54
     B.5.4   PAC Injection Models Developed from Full-Scale Data	56
     B.5.5   Mercury Speciation with SCR	62
     B.5.6   Conclusions	69
   B.6   CO2 Control Design Criteria	69
   References	71
Appendix C Design/Economic Criteria	73
   C.I   General Plant Design Criteria	73
   C.2   Economic Criteria	76
Appendix D Cost Algorithm Development/Validation/Sources	77
   D.I   FGD Cost Algorithm  Development	77
   D.2   Selective Catalytic Reduction	78
     D.2.1   Performance Parameters	78
     D.2.2   Capital Costs	79
     D.2.3   Operating and Maintenance Costs	81
     D.2.4   CUECost Validation	83
   D.3   Selective Noncatalytic Reduction	86
     D.3.1   Performance Parameters	86
     D.3.2   Capital Costs	87
     D.3.3   Operating and Maintenance Costs	89
     D.3.4   CUECost Validation	91
   D.4   Natural Gas Reburning	91
     D.4.1   Performance Parameters	91
     D.4.2   Capital Costs	94
     D.4.3   Operating and Maintenance Costs	95
     D.4.4   CUECost Validation	96
   D.5   Low-NOx Burner Technology	98
     D.5.1   Capital Costs	98
     D.5.2   Operating and Maintenance Costs	99
     D.5.3   CUECost Validation	100

-------
Table of Contents
  D.6   Hg Control Technology	100
  D.7   CO2 MEA Control System Cost Algorithm Development	104
     D.7.1   Capital Cost	104
     D.7.2   Operating and Maintenance Costs	105
  D.8   CO2 Cap Control System Cost Algorithm Development	110
     D.8.1   Capital Cost	110
  D.9   CO2 SI Control System Cost Algorithm Development	112
     D.9.1   Preconditioning	113
     D.9.2   Absorber	115
     D.9.3   Blower/ID Fan	119
     D.9.4   Regenerator	120
  References	123
Appendix E INPUT WORKSHEET SCREENS	125
  E.I   Getting Started	125
  E.2   Inputs	126
     E.2.1   Economic Inputs	126
     E.2.2   Power Generation Technique Choices	127
     E.2.3   APC Technology Choices	127
     E.2.5   Particulate Control Inputs	129
     E.2.6   SO2 Control Inputs	129
     E.2.7   Mercury Control Inputs	130
     E.2.8   CO2 Control Inputs	131
Appendix F Programs for Economic Parameters	133
                                                                                        IV

-------
Table of Contents
List of Figures
Page
Figure 1.      CUECost Workbook Map	3
Figure 2.      CUECost Logic Diagram	15
Figure B-l.    Salem Harbor Mercury Removal without PAC Injection (Durham et al., 2001)	54
Figure B-2a.    Gaston Testing	57
Figure B-2b.    Gaston Testing	58
Figure B-3.    Deviation of the Gaston PAC Algorithm	59
Figure B-4.    PPPP Testing	60
Figure B-5.    Deviation from the PPPP PAC Algorithm	60
Figure B-6.    Brayton Point Testing	61
Figure B-7.    Deviation from the Brayton Point PAC Algorithm	62
Figure B-8.    Mercury Oxidation without a Catalyst as a Function of Residence Time, Gas
              Temperature, and HCI Content (Hocquel et al., 2002)	64
Figure B-9.    Mercury Oxidation across  SCR Catalysts and without SCR Catalyst (Hocquel  et
              al., 2002)	64
Figure B-10.    Oxidation of Mercury across C-l SCR Catalyst in PRB-derived Flue Gas
              (Richardson et al., 2002)	65
Figure B-ll.    Effect of Flue Gas Exposure Time on C-l SCR Catalyst Oxidation of Elemental
              Mercury: 700 °F and Space Velocity of 1,450 h"1 (Richardson et al., 2002)	65
Figure D-l.    PAC, Bituminous FF	101
Figure D-2.    PAC, Bituminous ESP	101
Figure D-3.    PAC, Subbituminous FF	102
Figure D-4.    PAC, Subbituminous ESP	102
Figure D-5.    BPAC	102
Figure D-6.    Cost of Mercury Reduction, LS Bituminous Coal and ESP	103


List of Tables                                                                         Page

Table 1.       British to Metric Conversion  Factors	9
Table 2.       Total Capital Requirement Calculation Method	17
Table 3.       Annualized Cost Calculation  Method	19
Table 4.       CUECost-FGD Cost Comparison to FGDCOST by EPRI for Phase 1 Acid Rain
              Installations	23
Table 5.       Comparison of CUECost ESP Sizing Estimates with Raytheon Model	25
Table 6.       Percent Difference between CUECost and Acid Rain Division Studies (Khan and
              Srivastava, 2004) for Retrofit Cases 	27
Table 7.       Estimated Costs of ACI Control Systems according to CUECost	28
Table 8.       Estimated Costs of CO2 Control Technologies with CUECost and  IECM  model	28
Table B-l.     Specific Design Criteria for LSFO	38
Table B-2.     Input for LSD and the  Default Values for the Inputs	41
Table B-3.     Inputs for Particulate Matter Control and Its Default Values	42
Table B-4.     Default Input Parameters  for SCR	45

-------
Table of Contents
Table B-5.     Default Input Parameters for SNCR	47
Table B-6.     Default Input Parameters for NGR	49
Table B-7.     Default Values for LNBT Input Parameters	50
Table B-8.     Predicted Collection of Mercury by ESP according to Eqs. B-19 and B-20	52
Table B-9.     Values of Constants Used in the PAC Injection from Eqs. B-21 and B-22 	56
Table B-10.    Coefficients for Curve Fit Algorithms	58
Table B-ll.    Summary of Results from Full-Scale SCR Mercury Oxidation Tests (Bustard et
              al., 2001)	67
Table B-12.    Default Values for Mercury Control Input Parameters	68
Table C-l.     Snapshot for a Specific Plant and Its Default Parameters	74
Table C-2.     Coal Analysis Library	75
Table C-3.     Economic Inputs	76
Table D-l.     Variable and Constant Parameters for Wet FGD Cost Algorithm	77
Table D-2.     Parameters for LSD Cost Algorithms	78
Table D-3.     Direct Capital Costs for Hot-side SCR (Installed equipment costs)	80
Table D-4.     Indirect Capital Costs for Hot-side SCR	81
Table D-5.     Operating and Maintenance Cost Equations for SCR ($/year)	82
Table D-6.     CUECost with Acid  Rain Division Study Design for SCR (1990 dollars)	84
Table D-7.     Acid Rain Division Study:  SCR Applications	85
Table D-8.     Direct Capital Costs For SNCR (Installed Equipment Costs)	88
Table D-9.     Indirect Capital Costs for SNCR	89
Table D-10.    Annual Operating and Maintenance Costs for SNCR	90
Table D-ll.    CUECost with Acid  Rain Division Study Cases for SNCR (1990 dollars)	92
Table D-12.    Acid Rain Division Study:  SNCR Applications (1990 dollars)	93
Table D-13.    Direct Capital Costs for NGR (Installed equipment cost)	94
Table D-14.    Indirect Capital Costs for NGR	95
Table D-15.    Annual Operating and Maintenance Costs and Savings for NGR	95
Table D-16.    CUECost with Acid  Rain Division Study Cases for NGR (1990 dollars)	97
Table D-17.    Acid Rain Division Study:  NGR Applications (1990 dollars) 	98
Table D-18.    Total Capital Costs for LNBT Retrofit	99
Table D-19.    Annual Operating and Maintenance Costs for LNBT ($/year)	100
Table D-20.    CUECost with Acid  Rain Division Study Cases for LNBT (1990 dollars)	100
Table D-21.    Constants for Eqs.  D-9  and  D-10	101
Table D-22.    Indirect Capital Costs for CO2 Control	105
                                                                                           VI

-------
Acronyms, Units, and Symbols
ACRONYMS
A/C
ACI
AFDC
ARC
APPCD
ARD
BPAC
CAP
CCF
CE
GEMS
CEPCI
CF
CFR
CMU
COHPAC
CUECost
CV
DBA
DC
DCC
DOE
EPA
EPAC
EPRI
ESP
ESPc
ESPh
FF
FGD
GDP
GHG
HHV
IAPCS
Air to Cloth Ratio
Activated Carbon Injection
Allowance for Funds Used During Construction
Air Pollution Control (equipment)
Air Pollution Prevention and Control Division
Acid Rain Division (of EPA)
Brominated Powdered Activated Carbon
Chilled Ammonia Process
Carrying Charge Factor
Chemical Engineering (Magazine)
Continuous Emissions Monitoring System
Chemical Engineering Plant Cost Index
Capacity Factor
Code of Federal Regulations
Carnegie Mellon University
Compact Hybrid Particle Collector
Coal Utility Environmental Cost (model)
Catalyst Volume
Dibasic Acid
Direct Capital
Direct Contact Cooler
Department of Energy
Environmental Protection Agency
Enhanced Powdered Activated Carbon
Electric Power Research Institute
Electrostatic Precipitator
Electrostatic Precipitator (cold)
Electrostatic Precipitator (hot)
Fabric Filter
Flue Gas Desulfurization
Gross Domestic Product
Greenhouse Gas
Higher Heating Value
Integrated Air Pollution Control System
                                                                           VII

-------
Acronyms, Units, and Symbols
ICR
ID
IECM
IGCC
IPM
k
L/G
LNB
LNBT
LNCFS
LOI
LR
LS
LSD
LSFO
MEA
MEL
MHI
NEMS
NETL
NG
NGR
NM
NRMRL
O&M
OFA
ORD
PAC
PC
PCI
PJFF
PM
PPPP
PR
PRB
Information Collection Request
Induced Draft (fan)
Integrated Environmental Control Model
Integrated Gasification Combustion Combination
Integrated Planning Model
Exponential constant used to related coal type, removal efficiency and ash resistivity to
ESP size in terms of the Specific Collection Area (SCA)
Liquid-to-Gas Ratio
Low NOX Burner
Low NOX Burner Technology
Low-NOX Concentric Firing Systems
Loss On Ignition
Learning Rate
Low Sulfur (bituminous coal)
Lime Spray Drying (flue gas desulfurization)
Limestone (flue gas desulfurization)with Forced Oxidation
Monoethanolamine
Magnesium Enhanced Lime
Mitsubishi Heavy Industry
National Energy Modeling System
National Energy Technology Laboratory (DOE)
Natural Gas Combined Cycle
Natural Gas Reburning
Not Measured
U.S. EPA National Risk Management Research Laboratory
Operation and Maintenance
Over-fire air (used to complete coal combustion in some LNBT applications)
U.S. EPA Office of Research and Development
Powdered Activated Carbon
Pulverized Coal
Plant Cost Index
Pulse-Jet Fabric Filter
Particulate Matter
Pleasant Prairie Power Plant
Progress Ratio
Powder River Basin (coal)
                                                                            VIM

-------
Acronyms, Units, and Symbols
PV
RAM
RF
RLCS
ROM
SCA
SCPC
SCR
SDA
SI
SNCR
SV
TAG
TCE
TCR
TEG
TOL
TP
TPC
TPI
TTN
TVA
WACC
Present Value
Random Access Memory
Retrofit Factor
Rubber-Lined Carbon Steel
Rough Order of Magnitude
Specific Collection Area (refers to ESP size in terms of plate area (ft2)/1000 acfm)
Supercritical Pulverized Coal
Selective Catalytic Reduction
Spray Dryer Absorber
Sorbent Injection
Selective Non-catalytic Reduction
Space Velocity
Technical Assessment Guide
Total Cash Expended
Total Capital Requirement
Triethylene Glycol (dehydrator)
Technological Optimism Learning
Tax Paid
Total Plant Cost
Total Plant Investment
Technology Transfer Network
Tennessee Valley Authority
Weighted Average Cost of Capital
                                                                             IX

-------
Acronyms, Units, and Symbols
Units
acfm
gpm
GW
h
hp
kW
kWh
MB
MMacf
MMBtu
MPa
MW
MWe
MWh
ppm
scfm
Actual Cubic Feet per Minute
Gallons Per Minute
Gigawatt
Hour
Horsepower
Kilowatt
Kilowatt Hour
Megabyte
Millions of Actual Cubic Feet
Millions of British Thermal Units
Megapascal
Megawatt
Megawatt (electric)
Megawatt Hour
parts per million
Standard Cubic Feet Per Minute
See Table 1 in the Introduction for units not listed here
Chemical Symbols
CO
C02
H2O
HCI
HCCV
N2O
NH3
NH4+
NH4HSO4
NO
NO2
NOX
S02
S03
SOX
Carbon Monoxide
Carbon Dioxide
Water
Hydrogen Chloride
Bicarbonate
Nitrous Oxide
Ammonia
Ammonium
Ammonium Bisulfate
Nitrogen Oxide
Nitrogen Dioxide
Nitrogen Oxides
Sulfur Dioxide
Sulfur Trioxide
Sulfur Oxides

-------
Getting Started / Installation Guidelines
OVERVIEW

This document  serves as a User's Manual for  the CUECost workbook and documents  its
development  and  the  validity  of  the  methods  used to  estimate  installed capital and
annualized  costs.  The  CUECost economic  analysis workbook produces  rough-order-of-
magnitude  (ROM) cost estimates (±30% accuracy)  of the installed capital and annualized
operating costs  for air pollution  control (ARC) systems installed on coal-fired  power plants.
Costs for  utility ARC systems  are site-specific. These costs are subject  to change with
changes in  technology, labor rates, and material costs. The costs estimated by the CUECost
workbook come from a variety of sources. With that understanding, one may assume, but it
is not guaranteed, that CUECost will produce estimates in the range of accuracy of ±30% of
the actual cost,  which was the goal of this project.

The CUECost workbook was developed in Microsoft Excel workbook format to provide users
with complete insight into the equipment cost estimating methodology. All assumptions are
readily accessible to the user by reviewing the specific equations and references for each
cell in the  worksheets. CUECost is composed of technology-specific  worksheets  with one
common  input  worksheet for all technologies.  This  structure  allows the workbook to  be
expanded to incorporate other technologies in the future.

The original model (1998) was  developed by Raytheon Engineers & Constructors, Inc. for
Eastern Research Group, Inc. under EPA Contract No.  68-D7-0001. Subsequent revision was
completed  by Andover Technology  Partners for  ARCADIS under EPA Contract No.  EP-C-04-
023. This version 5.0 was revised by ARCADIS under EPA Contract No. EP-C-04-023.

Background

The Air Pollution Prevention and Control Division (APPCD) of the National Risk Management
Research Laboratory (NRMRL) contracted for development of a cost estimating workbook for
APC systems on coal-fired power plants. This workbook was developed in  Excel format to

-------
Getting Started / Installation Guidelines
provide the user with more flexibility in modifying the worksheet and outputs to meet the
user's needs for site-specific applications.

The workbook was designed to calculate estimates of an integrated ARC system or individual
component costs for various ARC technologies currently used in the utility industry to reduce
emissions of sulfur dioxide (SO2),  particulate matter (PM), nitrogen oxides (NOX), mercury
(Hg) and (in the future) carbon dioxide (CO2)  generated by coal-fired boilers. Technologies
currently included in the workbook are:
Flue Gas Desulfurization (FGD)
Particulate Matter Removal
Nitrogen Oxide Control
Mercury Control
Carbon Dioxide Control
Limestone with Forced Oxidation (LSFO)
Lime Spray Drying (LSD)

Electrostatic Precipitator (ESP)
Fabric Filter (FF)

Selective Catalytic Reduction (SCR)
Selective Non-Catalytic Reduction (SNCR)
Natural Gas Reburning (NGR)
Low NOX Burners (LNB)

Powdered Activated Carbon (PAC) injection
Monoethanoamine (MEA) Process
Chilled Ammonia Process (CAP)
Sorbent Injection (SI)
WORKBOOK DESCRIPTION

A map of the CUECost  workbook is shown  in Figure 1. This design allows the  addition of
future  technologies by inserting  new  worksheets  into  the  workbook.  The  workbook
calculates both new and retrofit plant costs using a 1.0 factor for a new facility, a 1.3 factor
for  a moderately difficult  retrofit, and a 1.6 factor for a  difficult retrofit. The user is also
given the  option  to  input his  own retrofit  factor  based on  plant-specific information.
Equipment sizing and variable operating costs are derived based on the calculated material
balances for specific process criteria, including flue  gas flow  rate,  pollutant removal rate,
chemical consumption rate, waste production rate, etc.

-------
Getting  Started / Installation Guidelines
Sheet 1 .0 General
Input-General
•Economic Factor
nput


•General Plant Technical Input
•APC Technology Choices
•NOx Control Inputs
•Particulate Control
•SO2 Control Inputs
•Hg Control Inputs
•CO2 Control Input

nputs



  Sheet 4.0 Power Generation
     Output-Power Generation
     •Sizing
     •Engineering Calculations
     •Equations
     •Levelization
     •Normalization
   Output-SO2 Control
   •Sizing
   •Engineering Calculations
   •Equations
   •Levelization
   •Normalization
  Sheet 10.0 Levelization Cal.
   •Carrying Charges
   •Expenses (O&M)
Sheet 2.0 Input Summary
Input-Calculations
•Economic Factor
•General Plant Technical Input
•ARC Technology Choices
•NOx Control Inputs
•Particulate Control Inputs
•SO2 Control Inputs
•Hg Control Inputs
•CO2 Control Input









Sheet 3.0 Output Summary





Summary of Emiss. Gene.
Costs
•SO2 Control Costs
•NOx Control Costs
•PM Control Costs
•Hg Control Costs
•CO2 Control Costs
Total Air Pollution Control Costs
Sheet 5.0 NOx Control
Output-NOx Control
•Sizing
•Engineering Calculations
•Equations
•Levelization
•Normalization





Sheet 8.0 Hg Control
Output-Hg Control
•Sizing
•Engineering Calculations
•Equations
•Levelization
•Normalization








Sheet 1 1 .0 Constant _CC
•Coal Library
•Combustions
•Etc.





















Sheet 6.0 PM Control



Output-PM Control
•Sizing
•Engineering Calculations
•Equations
•Levelization
•Normalization









Sheet 9.0 CO2 Control
Output-CO2 Control
•Sizing
•Engineering Calculations
•Equations
•Levelization
•Normalization





Sheet 1 2.0 Future Cost Projections
•Learning Curves
•Etc.



Figure  1.
CUECost Workbook Map

-------
Getting Started / Installation Guidelines
The first sheet of the workbook functions as the menu of all sheets in the workbook. Users
can follow the link, by clicking the icons, to the input or output for a specific air pollutant
control technology. In this version 5.0, a toolbar was developed, including Main Menu, Go
to Top, User Input, Outputs, and Print Buttons.

All inputs are integrated into one worksheet,  and  outputs for a specific control technology
are listed separately in one worksheet. Economic-related outputs are first listed at the top of
the outputs  worksheet, with engineering-related calculations listed at the bottom. Version
5.0 of the CUECost workbook contains calculations  of the carrying  charges and  levelizing
factors for  expenses  in worksheet  10.0. In  calculating the capital carrying  charges  and
operation and  maintenance (O&M) levelized cost,  a  30-year plant duration was used.  The
calculation  can  be accessed from the worksheet  "1.0 General  Input" by  clicking  the
calculator link.
CUECOST   WORKBOOK   DEVELOPMENT   AND   DOCUMENTATION   DOCUMENT
CONTENTS

This document consists of the following sections:

Overview of CUECost Workbook states the purpose and content of this document.

Getting  Started  presents an  itemized  listing of requirements for the user's computer
system and is followed by a series of installation guidelines for use in installing the CUECost
workbook to the user's hard disk. Instruction is also provided for the first-time user on how
to get started producing a cost estimate using  CUECost. These starting  instructions  include
listings of the input sequence and other preliminary steps for the user to complete prior to
using the CUECost workbook.

Workbook Layout and Methodology presents  a detailed  description of the contents of
each worksheet and provides a layout diagram. This section provides a technical description
of the workbook and discusses how the worksheets are integrated to minimize user input.
The cost estimating methodology is also described, including a logic diagram to illustrate the
calculation sequence that is used to develop capital and annualized cost estimates.

Input and Output Options provides a description of the input and output options available
to the user for cost estimate development.

Worksheet Validation, the final section of the user's manual, summarizes  the validation
procedure that  was followed  during  development and  subsequent testing  of the CUECost
workbook.

Appendix A provides  the definitions of terminology used in the  text and  worksheets.

-------
Getting Started / Installation Guidelines
Appendix B provides process criteria and technology descriptions of equipment included in
each technology cost estimate.

Appendix C presents tabulations of the  primary assumptions that served as the estimate
basis  for the default values  included in  the worksheets, including both  plant design and
economic criteria.

Appendix D discusses the data sources for the cost-versus-capacity algorithms. Previous
publications, vendor quotations, and costs from recent ARC installations served as the basis
for all cost-versus-capacity curves used in the worksheets.

Appendix E provides a  demonstration of the worksheets to show  how the workbook is
used.  Pictures of  the actual Excel screens are provided for easy reference to the screens
shown when running CUECost.

Appendix F provides programs to calculate carrying charges and  levelization of O&M costs.
PROJECT APPROACH

The  workbook  design  allows  the  user to  review all of the  assumptions and  equations
contained in each worksheet and to adjust any of them to fit the user's particular needs. A
multi-worksheet format was selected  to allow the addition of other technologies if future
expansion of the workbook is desired. A separate input  worksheet was assembled, along
with technology-specific  Excel worksheets  that  perform equipment sizing and  economic
calculations for each ARC system.

NOX Control Estimate
NOX control technology design and  cost algorithms are based on research conducted for the
EPA Acid  Rain  Division (ARD) (now  the Clean  Air  Markets  Division), the  EPA Office  of
Research  and Development (ORD), and the U.S. Department of Energy (DOE) National
Energy  Technology  Laboratory  (NETL)  (Frey   and Rubin,  1994).  Design  parameter
calculations for SCR, SNCR, and NGR are taken from the Integrated Air Pollution  Control
System (IAPCS) model, Version 5.0 (Gundappa et al., 1995).

SCR capital cost components  are based on algorithms developed for DOE (Frey and  Rubin,
1994) as  part of the Integrated  Environmental Control Model (IECM).1 For SNCR and  NGR
total capital equipment costs, ARD research was used to update  IAPCS  methodology. The
ARD cost data used to update IAPCS are presented in the following:
1 IECM is a computer-modeling program that performs a systematic cost and performance analysis of emission
control equipment at coal-fired power plants. It is developed for the U.S. Department of Energy by Carnegie Mellon
University and is available at http://www.iecm-online.com (accessed February 13, 2009).

-------
Getting Started / Installation Guidelines
•  "Cost Estimates for Selected  Applications  of  NOX Control Technologies  on Stationary
   Combustion Boilers and Responses to Comments," (EPA, 1998) and

•  "Investigation of Performance  and  Cost of NOX Controls as Applied to Group 2 Boilers,"
   (EPA, 1997).

Low  NOX burner technology  (LNBT) total  plant costs are based on  algorithms presented in
another ARD report (EPA, 1996). The cost estimates presented in the ARD reports are being
used in the NOx-related  rulemaking and have been  reviewed  by  stakeholders associated
with  the rulemaking process. O&M cost algorithms for all technologies  use IAPCS equations
from IAPCS 5.0 (Gundappa  et al.,  1995). Operating  costs are estimated in  the workbook
based  on simplified  material balances calculated within  CUECost based  on  the  inputs
supplied by the user. The ultimate coal analysis, including weight  percent sulfur, carbon,
hydrogen,  oxygen, nitrogen, moisture and  ash, serves  as the   primary  input for  the
combustion calculations performed by the worksheet. The resulting  gas flow is the basis for
the remaining  material  balance calculations.

In this  manual, the  default values for NOX control devices were  generally  adopted from
Integrated  Planning  Model  (IPM)/IECM  models (the   IPM  model   can   be  found   at
http://www.epa.gov/airmarkt/progsregs/epa-ipm/index.html). For NOX  control technologies,
CUECost results were compared to cost data  reported  by the EPA ARD (EPA, 1997; EPA,
1998) for NOX controls applied to utility boilers and Chapter 5 of the IPM manual.  The ARD
reports  are based on an EPA national database  of boilers. Using CUECost's default values for
Retrofit Factor, General Facilities,  etc., should produce capital cost results that are the same
as or very close to the results that would be produced  by the IPM source algorithms.

Particulate Matter Control Estimates
The  particulate matter control   technology cost  estimates  are  based on  IECM  model
constructed by Carnegie Mellon University (CMU) for the DOE (Berkenpas et al., 1999). This
model  was constructed based on a combination  of theoretical equations for  Electrostatic
Precipitator  (ESP) sizing. The theoretical  equations were  modified to  incorporate  the
empirical data obtained from a series  of ESP vendors for installations  firing different coals.
This  framework taken from the CMU model served as the basis for  the CUECost ESP  design
portion  of the  worksheet. The CMU worksheet was based on 150 to 200  actual installations
firing a wider  variety  of fuels. Operating costs are  calculated  using the inlet-flow rate-
versus-expected-power-consumption algorithms.  Maintenance  costs  are calculated as a
percentage of the installed equipment cost.

Fabric filter (FF) costs were  also based on a set of cost equations developed by Berkenpas
et al. (1999)  to relate  the FF size [calculated as a function of the  volumetric flue gas flow
rate  times  the air-to-cloth  ratio  (A/C) selected  by the  user] and the  FF  inlet  flue  gas
volumetric flow rate to determine the  expected cost for the installed system  (Berkenpas et
al., 1999).  Operating costs are calculated using the inlet-flow rate-versus-expected-power-

-------
Getting Started / Installation Guidelines
consumption algorithms. Maintenance costs are calculated as a percentage of the installed
equipment cost.

SO2 Control Estimates
For the FGD technologies, cost-versus-capacity  equations  were based  on  the historical
database (Keeth, 1991) of actual equipment  costs incurred during Phase 1 of the utility
Clean Air Act compliance programs, budgetary quotations for components as  received from
vendors during  early 1998,  and cost data obtained from  industry database  programs
(Srivastava, 2000). These  parametric equations  serve  as the basis for the FGD  system
capital costs calculated by CUECost. Operating  cost equations were formulated based on the
consumption rates estimated in  the  worksheets by the  material  balance calculations.  A
material balance is developed specifically for each FGD  system and provides the chemical
consumption rates, wastes production rates, and flow rates through process equipment that
are used to estimate the  system power consumption.  Operating  labor  requirements are
based on a formula that relates plant size to the number of operating staff needed to run
the FGD equipment, and maintenance costs are calculated as a percentage of the installed
costs for the system.

CO2 Control Estimates
The monoethanolamine (MEA) CO2 control technology cost estimates are  based  mainly on a
report  from the  U. S. DOE/NETL (2007). The cost of a bare erected plant was estimated
based  on 30% of  MEA, currently the most practical  concentration.  For MEA  islands, the
same total plant cost (TPC)  is assumed to occur for KS-1 and MEA solvents. The compressor
island cost, however, depends upon the compressor stages and power consumption through
a regression of cost and compressor power. In  the CUECost design, the details of O&M cost,
which  are the major concern, are listed for  the  users.  The  absorption island  of chilled
ammonia process (CAP) is estimated to be 97% of the bare erected cost of the same size
MEA-type island. Although the pressure of CO2 out of the reflux drum is significantly higher
than from the  MEA process, the investment estimation of the compressor island follows the
same algorithm  as the MEA process,  depending upon only the regressed relation of  cost-
power. Regarding the sorbent injection (SI) option, due to the lack of information for  a full
scale plant, the bare erected cost for absorption island  is estimated with a same size of MEA
island total cost. Detailed values for consumption of  power, steam and cooling water are
given in the engineering calculation section.

Mercury Control Estimates
The effects of  existing equipment on  mercury reduction  were isolated from  the  effects of
powdered activated  carbon  (PAC) injection on mercury reduction, and new algorithms were
developed for  PAC injection. The  PAC injection algorithms include algorithms based on the
results of two  full-scale demonstrations  (Bustard et  al.,  2001; Durham  et al., 2001;
Bustard et al., 2002; Sterns,  2002) as well as algorithms developed from pilot-scale data
(EPA, 2000).

-------
Getting Started / Installation Guidelines
Economic criteria supplied  by the user  are  used by CUECost to calculate the capital and
annualized costs for the selected ARC system. The  user has  the option to use the default
values provided in  the worksheet  if some  of the  input  data requested are not readily
available. For the convenience of users, a levelization calculation worksheet is included in
the CUECost workbook. This worksheet provides carrying charge and levelization factor for
expenses (O&M) in terms of current dollars and constant dollars.
DEFAULT PLANT CRITERIA

The CUECost workbook includes default values for all input parameters. These criteria are
specific to a  generic 500  MW coal-fired power plant located  in Pennsylvania. The specific
design and economic criteria used as defaults are  provided in Appendix C for reference. A
coal library is also included in worksheet 11.0 so that the user can  select a  coal similar to
that actually  burned at the plant if an actual ultimate analysis is not readily available.  User
has the capability to adjust coal properties as desired to create  "user-defined" coal in
worksheet 11.0. The coal  information was  retrieved from the DOE  Coal Sample Bank and
Database at http://datamine.ei.psu.edu/index.php.
RESULTS

The CUECost workbook provides rough-order-of-magnitude (ROM)  cost estimates (±30%
accuracy) for  a wide variety of ARC  technology  scenarios. Cost estimates for different
combinations of control  technologies can  easily be compared  in the results  summaries
presented in five parallel columns on  the  worksheets.  Examples of the input  sheets  are
shown in Appendix E.

CUECost is designed to produce ROM  estimates for a  wide range of plant sizes and coal
types.  However,  appropriate  ranges of plant  size  and operating  conditions  have been
established based on the limits to the database used to construct the cost-versus-capacity
algorithms. Range limits are provided in the worksheet  for each input supplied by the user.
The major criterion  limitation for CUECost is the plant size  range. Algorithms are based on
the assumption that equipment options will be installed at a facility ranging from  100 to
2000  MW in net capacity. All other criteria are  limited  only by their technical validity. The
suggested technical limits for each criterion  are provided in the worksheets when applicable.

It  is  expected that this  document  will be  useful  to  a broad  audience, including:  (1)
individuals responsible for developing and implementing SO2, NOX, PM, Hg, and CO2 control
strategies at sources, (2) state authorities implementing pollution control programs, and (3)
interested public at large. Moreover,  persons  engaged in research and development efforts
aimed  at improving cost-effectiveness of air pollution control technology applicable to coal-
fired plants may also benefit from this document.

-------
Getting Started / Installation Guidelines
Note  that  the cost estimates  provided  in  this study  and  generated by  CUECost are
dependent  upon the various  underlying assumptions, inclusions, and  exclusions utilized in
developing  them. Actual project costs will  differ and can be significantly affected by factors
such  as changes in the  external  environment, the  manner in which  the  project is
implemented,  and other factors which  impact the estimate  basis or otherwise affect the
project. Estimate accuracy ranges are only projections based upon cost estimating methods
and are not guarantees of actual project costs.

EPA policy  is to express all measurements in  EPA documents in metric units. Values in this
document are  given in British units for the convenience of the engineers and other technical
staff accustomed to using the British system. The following conversion factors  presented in
Table 1 can be used to provide metric equivalents.
Table 1.
Abbr.
ac
Btu
°F
ft
ft2
ft3
ft/m
ft3/m
gal
gpm
gr
gr/ft3
hp
in.
Ib
Ib/ft3
Ib/h
mi
psi
rpm
scfm
t/h
British to Metric
British Unit
acre
British thermal unit
deg. Fahrenheit - 32
feet
square feet
cubic feet
feet per minute
cubic feet per minute
gallons (U.S.)
gallons per minute
grains
grains per cubic foot
horsepower
inches
pounds
pounds per cubic foot
pounds per hour
miles
pounds per square inch
revolutions per minute
standard (60 °F) cubic
feet/minute
short tons per hour
Conversion Factors

X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
Conv. Factor
0.405
0.252
0.5556
0.3048
0.0929
0.02832
0.00508
0.000472
3.785
0.06308
0.0648
2.288
0.746
0.0254
0.4536
16.02
0.126
1609
6895
0.1047
1.6077
0.252
Abbr.
ha
kcal
°C
m
m2
m3
m/s
m3/s
L
L/s
g
g/m3
kW
m
kg
kg/m3
g/s
m
Pa
rad/s
nm3/h
kg/s
Metric Unit
hectare
kilocalories
degrees Centigrade
meters
square meters
cubic meters
meters per second
cubic meters/second
Liters
liters per second
grams
grams per cubic
meter
kilowatts
meters
kilograms
kilograms/cubic meter
grams per second
meters
Pascals (Newton/m2)
radians per second
normal cubic
meters/h
kilograms per second

-------
Getting Started / Installation Guidelines
HARDWARE AND SOFTWARE REQUIREMENTS / INTERNET ACCESS

The  CUECost workbook is  written  in  Microsoft Excel  2003 format.  The hardware and
software requirements for CUECost and User's Manual are listed below:
Computer Hardware:

Operating System:
Memory Requirements:
Installation Requirements:
Commercial Support
Software Required:
500 MHz Processor, 256 MB RAM and 100 MB hard drive
Internet access required for down-loading the worksheet from web site
Windows 2000 or higher
3 MB on hard drive for download of CUECost workbook
Download from EPA's Technology Transfer Network (TTN) web site:
http: //www. epa. gov/ttn/catc/products .html
Search for CUECost under heading: Software (Executables & Manuals)
Download to hard drive
Microsoft Excel 5.0 or higher for Workbook
Microsoft Word 6.0 or higher or Adobe Acrobat Reader (latest version
available for free at: http://get.adobe.com/reader/) for User's Manual
GETTING STARTED

After accessing the workbook via the EPA web site and storing the files on the user's hard
drive (note that the files may have to be decompressed using "WinZip"), the User's Manual
may be called up in WordPerfect or Acrobat, depending  upon the format downloaded, and
then printed out for easy access. Each user  should  read the user's  manual to  become
familiar with how CUECost works and where various input and technical data are provided
within  the workbook. After reviewing the user's manual, the user should then call up the
workbook as an  Excel file and begin review of the worksheets contained therein. The file will
                                                                                    10

-------
Getting Started / Installation Guidelines
be active when called up from the web site (after decompression). The user should go to the
home site (cell Al) on the first sheet of the workbook to begin.

NOTE: The CUECost workbook can be modified bv the user. To ensure its integrity,
a copy of the  original  worksheet should be saved in a separate file  in  a new
directory and all other copies saved under different file names.

The default values provided  in the  worksheet will  allow the user to immediately run a test
case and print output sheets to test the existing printer setup routine. Familiarity with Excel
worksheet software is required to modify the workbook to correct printing problems.

The  input  requirements for the worksheet are itemized in the section titled "Input and
Output Options"  of this user's manual. The user should first obtain  the necessary input data
for all cases to be evaluated. Up to  ten cases can be run simultaneously for direct on-screen
comparison of results. Up to twelve  site-specific  coal analyses can  be added  to the ten
columns available in  the coal library  for use in any series of estimating  runs. This  file can
then be saved for use in the future. The existing default values  can be deleted by entering
values in the library cells,  and then saving the new  file for future  use under a different file
name. The input cells are colored blue for identification by the user.

When running the workbook for the first time, it would be best to save your input data to a
separate file  on  a regular basis. The worksheet  provides the capability to  select  from a
variety of system options, picking  alternate control technologies  and combinations of the
component options provided.
                                                                                  11

-------
Workbook Layout and Methodology
WORKBOOK LAYOUT

Figure 1  provides the basic layout of the various sheets currently included  in the CUECost
workbook. The following descriptions apply to the individual worksheets.

Worksheet Menu
Upon opening CUECost, the user can  enter the menu by clicking the "Menu" tab. The menu
provides  easy links to specific control technologies. The  user  can  also  use the CUECost
toolbar. The toolbar offers quick access to  many  functions while  working in a  particular
worksheet.

This worksheet menu provides the primary user interface and basic instructions on how to
proceed.  The  interface consists  of a  series of buttons  the  user  selects  based on  the
technology cost estimates desired and the part of the workbook to be reviewed at  that time.
Note  that  when  the user selects a specific technology  for  evaluation,  the inputs  for
preceding technologies  must  be fulfilled  according  to  the selected  air pollutant control
sequence.  For example, if both selective catalytic  reduction (SCR) and limestone forced
oxidation (LSFO) technologies  are selected; inputs for SCR must be completed prior to  the
inputs for LSFO.

Worksheet  1.0  = General Input - This worksheet contains three  subsections:  Economic
Factors, Power Generation Technology and ARC Technology Choices (only for pulverized coal
application). Through this worksheet, the user constructs the basis  for all pollutant control
technology-related estimates. The various columns in this worksheet  are described below:

•   Column B provides a text description of the cells in each row.

•   Column C defines the units that should be used for the input to the cells  in  each row.

•   Column  D  supplies  a  suggested  range of  input values based  on technical  limits  or
    worksheet validity limitations.

	12

-------
Workbook Layout and Methodology
•  Column E is a listing of the default values included in the worksheet.

•  Columns F  through O provide entry points for values specific for up to ten simultaneous
   case evaluations.

Worksheet 2.0  =  Input Summary  -  This  sheet summarizes  economic  input,  power
generation technology choices, and air pollutant control technology choices specified in the
general input worksheet.

Worksheet 3.0 = Output Summary - This worksheet summarizes all ARC technology outputs
from a specific technology evaluation.  A filter function  is provided  in this worksheet for the
user to select the preferred outputs easily.

Worksheet 4.0 = Power Generation - This worksheet is specifically designed to evaluate the
investment and  O&M costs of a specific type of  power generation  technology such as
subcritical, supercritical,  ultra-supercritical, integrated  gasification combined  cycle (IGCC),
and Oxyfuel.

Worksheet 5.0 = NQy Control  -  NOX calculations  are  completed on this worksheet.  The
results of the  combustion calculations provided in worksheet 1.0 "Constants_CC" are used
to calculate the material balance for  the  NOX systems. These values  are  then used to
calculate the expected costs for the various cost areas using algorithms developed for the
CUECost workbook.

Worksheets 6.0  = PMF,  7.0  = SO?, 8.0 = Hq,  9.0 = COZ Control Technologies - These
worksheets perform the same function as Sheet 5.0 for the other ARC technologies.

Sheet 10.0 = Levelization Calculations - This worksheet is specifically designed for the user
to calculate carrying charges and non-carrying expenses.

Worksheet 11.0 = Constants CC - This worksheet contains range name definitions, tables of
constants used by the workbook (such as the molecular weights of compounds), and other
macros used by the CUECost workbook. This worksheet also contains the coal library and
the combustion calculation sequence used  for all  of the material balances performed in the
other process-specific worksheets.

In general, the methodology employed  in the workbook for cost  development follows the
format used by the IAPCS  model (Gundappa  et al., 1995), providing  installed capital and
operating costs for the selected technologies.  The calculation sequence takes advantage of
the vertical arrangement  of the worksheet. A series of tables presents the equations (and all
variables used in these equations) contained  in  each  cell and the units  of the calculated
results. Descriptive  material is included in the documentation to define  the  purpose and
method employed within various subsections of the  worksheets.
                                                                                  13

-------
Workbook Layout and Methodology
METHODOLOGY

The calculation sequence used in the worksheets to estimate capital and annualized costs is
summarized in the following material. Additional details regarding the specific equations and
interrelationships between  sections of the worksheets can be found in this documentation
provided in Appendix D. The worksheet design will accommodate  the  addition of alternate
ARC  technologies by inserting  new  worksheets for system cost estimation and technical
calculations that will  use the common input sections and common economic calculations.
The cost worksheet allows the user to select the technologies of interest and calculates the
associated costs for each control system based on the data that the  user enters to define
site-specific conditions.  Figure 2 is the logic diagram for the workbook and illustrates how
the capital and annualized  costs for ARC equipment are calculated. The  methodology and
the calculation sequences used by CUECost are described  below in the following material.

Step 1
This  step begins with  input  worksheets and can  be split into two sub-steps.

Sub-step 1
The user is first asked to select the "1.0 General Input" worksheet. This worksheet provides
a general description of the power  plant and desired combination  of ARC  technologies.
Following the  initial process selection, the user enters the necessary technical parameters
specific to the project. Default values are provided for all inputs. The  inputs are separated
into the following distinct sections:

•  Economic Factor
   Inflation adjustment factors are used for cost  adjustment from algorithm development
   years to current cost basis year. User can  select  either gross domestic product (GDP) price
   deflator or chemical  engineering cost index (Chem Index) for cost adjustment. GDP price
   deflator can be obtained from the Bureau of Economic analysis, and the Chem Index can
   be obtained from the journal of Chemical Engineering.  Carrying charges (current dollars,
   constant dollars, first year constant dollars and first year current dollars.) and levelization
   factors for expenses (current and  constant dollar based on  a 30-year lifecycle of plant)
   follow  the  definition in  EPRI TAG Technical Assessment Guide (EPRI TR-102276-V1R7
   volume 1, 1993). For the convenience of user, carrying charges and  levelization factors for
   expenses can be calculated  by clicking the calculator  link. Once the inputs in worksheet
   10.0 are given by the user, the outputs are automatically sent back to worksheet 1.0.

•  General Plant Technical Inputs (boiler operation,  coal analysis, excess air, etc.)
                                                                                   14

-------
Workbook Layout and Methodology
Technical Inputs:
- Plant Description
- Boiler Operation
- Coal Analyses
- Excess Air

APC Process Inputs:
- Process Selection
- Operating Criteria
- Equipment Sparing





Combustio
- Gas Flow
- Gas Com]
- Chemical
i
APC Mate
- Inlet Gas
- Inlet Gas
- Reagent C
- Waste Ge
i
nCalc.:
Rate
)osition
Usage
r
r. Balance:
Tlow Rate
Compos.
onsump.
deration
r
Oper. Parameters:
- Chemical Usage
- Waste Disposal
- By-product Rate





Economic Inputs:
- Inflation Rate
- Escalation Rates
- Fixed Charge Rate
- Consumable Costs
i
Equipmenl
- Installed 3
- Installed (
Major C
i
Utility Con
- Power
- Steam
- Water
r
Cost:
/Subsys.
^ost of
omponents
r
sumption:





Indirect Cost Inputs:
- Engineering %
- General Facilities
- Contingency
- Retrofit Factor
i
Total Ca

r

pital Cost

Variable Operating

i
L



Fixed Cost
- Maintenar
- Operating
$/hr. & # o
i
Factors:
ice %'s
f operators
r
First-year and
Levelized Operating
Cost Results
1

k
Figure 2.
CUECost Logic Diagram
                                                                                                          15

-------
Workbook Layout and Methodology
•  For the power generation technology selection, the user can select sub-critical,  super-
   critical, ultra super-critical, IGCC, or oxyfuel. When IGCC or oxyfuel power generation is
   selected, there will be no control technologies related to them in this version.

•  ARC Technology Choices(NOx/SO2/PM/Hg/CO2)
   This section  is of importance  because it tells the system what plant configuration is
   desired. As  aforementioned, there will  be no technology selected when IGCC or oxyfuel
   power generation technology is selected.

Sub-step 2
After users complete common input, the user then can access a specific control technology
as described  in the ARC Technology Section for process specific input, fully exploiting  the
convenience of the toolbar  attached to this workbook. Default values are provided for all
inputs.

Step 2
After the  user  has entered the technical inputs,  the workbook  performs the combustion
calculations in  the Constants_CC worksheet. The flue gas flow  rate and  composition  are
calculated  in  this step.  The  results of  these  calculations   are  summarized  in  the
Constants_CC worksheet.

Step 3
Using the results of the combustion calculation and the APC-specific technical inputs,  the
necessary material balance calculations are performed. Reagent consumption and waste
generation are calculated based on the  inlet gas flow  and composition (see ARC technology
worksheets).

Step 4
Following  the calculation of the material balance, the equipment costs associated  with  the
specific equipment  areas  (ARC  worksheets)  are  calculated.  The   largest equipment
components for each area  [absorber,  induced draft (ID) fan,  etc.] are  broken  out and
estimated separately.  All  capital  costs are installed costs  (i.e.,  they  include  all  costs
associated with  the  installation  of  the  subsystem  or  component). These installation
expenditures  include the costs for the following:

•  Earthwork

•  Concrete

•  Structural steel

•  Piping

•  Electrical

	16

-------
Workbook Layout and Methodology	


•  Instrumentation and controls

•  Painting

•  Insulation

•  Buildings and architectural.

Costs for demolition are treated  as  an input,  assuming that the user  can provide the
expected costs for any demolition that might be  required at a specific site. The items listed
above, when added to the bare equipment cost, are equivalent  to "A" in the calculation
sequence for the capital cost shown in Table 2.

Table 2.      Total Capital Requirement Calculation Method
             Installed Process Capital Cost              =                 A
               General Facilities at % of A               =                 B
       Engineering and Home Office Fees at % of A        =                 C
            Contingency at % of (A + B + C)             =                 D
                Total Plant Cost (TPC)                  =             A+B+C+D
               Total Cash Expended (TCE)               =       TPC x Adjustment Factor*
      Allowance for Funds During  Construction (AFDC)      =        AFDC % (input) x TPC
              Total Plant Investment (TPI)               =            TCE + AFDC
                  Preproduction Costs                   =                 F
                   Inventory Capital                    =                 G
            Total Capital Requirement (TCR)             =            TPI + F + G
* Adjustment Factor is based on the years of construction, the inflation rate, and the escalation rate.
The factor reduces the cost of the  capital investment due to the purchase of components prior to the
completion of the construction period, allowing the TCR to be expressed in a single-year dollar value.

Step 5
Adding the  costs listed above  to the  uninstalled bare equipment  costs results in the total
direct field cost for the installed equipment  (ARC  worksheets). The  installed equipment costs
(bare equipment cost multiplied by an  installation factor composed of various cost accounts
listed above—earthwork, steel, piping,  etc.) for each component include the typical indirect
field  costs, such as field staff and legalities, craft fringes and insurance, temporary facilities,
construction equipment and tools, and  an allowance for start-up and testing.  Allowances for
taxes are also  included  in the final installed cost for each  subsystem.  The  Total Installed
Cost then serves as the  basis for  the calculation of the engineering and  general  facilities
cost   components  and  the  contingency cost associated  with the  project capital  cost.
Escalation of the capital cost  is then  performed  using  the GDP  Index or CE  Index (see
Economic Indicators  found  on  the last page of each  issue of the Chemical Engineering
magazine) for the year selected by the  user as the basis for the cost estimate.

	17

-------
Workbook Layout and Methodology
For most equipment areas and components, a cost algorithm is supplied to relate installed
component cost to  the component capacity.  The worksheet was constructed to allow the
user to generate cost estimates for units ranging from 100 MW to 1000 MW and for facilities
firing almost any coal.

Step 6
In addition to the equipment costs, the ARC worksheets also calculate operating parameters
(chemical usage,  waste disposal,  byproduct rate, etc.) after the  calculation of the material
balances (ARC  worksheets). The  usage and  production  rates serve as the  basis for the
calculation  of the variable operating cost components. The workbook uses the operating
parameters and the calculated utility consumption (electrical energy, steam, water, etc.) to
calculate  the   variable  operating  costs.  The  annualized  cost  calculation  method  is
summarized in Table 3.

Step 7
Finally,  the total  capital  and  operating costs are used to calculate the levelized constant
dollars and also first-year annualized current dollars. Operating costs belong to the  non-
carrying  charge category. Operating costs will be levelized at the 30-year  level (L30) at
constant dollars.  Both of these  costs (for  both capital and  operating components) are
represented in  absolute  ($/year)  and normalized  terms  (i.e., mills/kWh or $/kW). These
costs are  summarized in the summary  worksheet  for direct  comparison  of  case  cost
estimates and printing of  output summaries.
                                                                                   18

-------
Workbook Layout and Methodology
Table 3. Annualized Cost Calculation Method
Fixed O&M Costs
Operating Labor
Maintenance Labor/Materials
Administrative/Support Labor
Labor Rate x 8760 x Number of Operators Added
= Maintenance Factor x Installed Capital Cost
0.3 x (Operating Labor + Maintenance Labor)
A
B
C
Variable Operating Cost
Chemicals
Solids Disposal
Water Cost
Power
Steam
= Chemical Cost x Consumption Rate/Year
Waste Disposal Cost x Waste Production Rate/Year
Water Cost x Water Consumption Rate
= Power Cost x Power Consumption Rate
Steam Cost x Steam Consumption Rate
D
E
F
G
H
Carrying Charges
Carrying Charges
= Total Capital Requirement x Carrying Charge Rate
I*
Annualized Constant Cost
First Year Current Cost
(A+B+C+(D+E+F+G+H)xCapacity Factor)xL(SO) +1   =

(A+B+C)+(D+E+F+G+H)xCapacity Factor +1
*When calculating levelized/annualized constant cost, I =total capital requirement (TCR) x constant $
carrying charge rate.
When calculating first year current cost, I =total capital requirement (TCR) x first year current $
carrying charge rate.
L(30), levelization factor for 30 year service life, can be calculated with worksheet 10.0. Results are
automatically sent back to worksheet  1.0.
                                                                                        19

-------
Input and Output Options .
INPUT DATA

The  worksheet "1.0 general inputs" starts with default,  inputs, represented with "D", in
worksheet 1.0. The user can change the "D" to its defined value for a site-specific estimate.
Input  cells are colored blue  for  highlighting  purposes.  Each  column is specific to  an
individual case. Duplicate data for each case can simply be copied  over into the remaining
columns rather than entered individually for each case.

The  general input worksheet is divided  into various sections for clarity. The detailed input
requirements are listed below with a brief description of the content  of each:

1. Economic Factors - These economic data define the basis for the cost estimates that are
   produced,  including  the  basis  year,  inflation rates, escalation rates,  capital carrying
   charges, non-carrying expense (O&M), operating labor rates, chemical costs, and  utility
   costs. The economic factors apply to all the control technologies.

2. Power Generation  Technology - These criteria define  the operating conditions  at the
   facility  under  investigation. Fuel characteristics, heat rate, location conditions,  etc., are
   requested  in this section. These data are  then used  as the  basis  for the  combustion
   calculations and definition of the plant ambient conditions.

3. Air Pollution Control system definition - This is a section of the utmost importance where
   the user can select from among various ARC technology configurations for a specific site.
   Each specific site can contain one or all of the ARC subsystems.

3.1 Nitrogen Oxides Control technology - All data required to define the NOX control system
    are requested in this section. The  user also selects the type of control system that is
    desired: selective  catalytic  reduction (SCR), selective  non-catalytic reduction (SNCR),
    natural gas reburn  (NGR) technology, or low-NOx burner technology (LNBT)  [including low
    NOX  burners  (LNB) for pulverized coal boilers,  and  low-NOx concentric  firing systems
    (LNCFS) for tangentially fired boilers].

	20

-------
Input and Output Options .
3.2 Particulate Matter Control Technology - All data required to define the particulate matter
    control system  are  entered  in this section. The  user  also selects the  type  of  control
    system that is desired, ESP or a FF, and what type of fabric filter is selected.

3.3 Sulfur Dioxide Control Technology  - This section provides a series of inputs that define
    the  operating conditions  for the scrubber system. In this section the user can define
    conditions that are specific to vendor data, or the default values can be used to determine
    the  generic costs for the  FGD system. The option to use a dibasic acid (DBA)  additive is
    also  provided. The  DBA  acts as a buffer in  the  SO2 absorption reaction,  potentially
    reducing  the operating costs  for the FGD system and  improving  performance at some
    sites.

3.4 Lime Spray Dryer FGD Process Definition - The data inputs on this worksheet are similar
    to the inputs  for the LSFO worksheet.  Once again the  process operating conditions are
    defined for each case being considered.

3.5 Mercury  Control Technology  -  All data required  to  define the Hg control system are
    requested in this section.  The user selects the type of sorbent that is desired: enhanced
    PAC (EPAC), PAC, or other. The user also specifies the design and operating conditions of
    the  pulse-jet fabric filter (PJFF) downstream of PAC if desired.

3.6 Carbon Dioxide Control Technology - All data required to define the CO2 control  system
    are  input in this section. The user selects the type of process: MEA,  CAP, or SI.
OUTPUT OPTIONS

The  input  values  are then summarized  in  the Input Summary worksheet.  The Output
Summary worksheet compiles the results  generated by the technology-specific worksheets.
The tables are constructed for use in printing the output sheets.  A summary table is also
available in the section  of Summary of  Emissions and Generation.  The output summary
table  primarily provides  the  cost estimates  generated for  all of  the control technologies
selected for each case. More detailed breakdowns of each technology  cost estimate  are also
generated  in  the  technology-specific  worksheets  to  identify  the  components  of  the
estimates.  To  obtain outputs from the workbook, the user can return to the General Input
Sheets, ensure that the  workbook has been  recalculated by pressing the  F9  button, and
then click on the Print buttons provided for printing. The user can also enter any worksheet
of interest and click on the print icon. The workbook is set up to  automatically print all of
the cost related material  in each worksheet.

The workbook also  allows the user to select any specific portion of an individual worksheet
that is of interest and print out that material only. A specific range can be selected and that
section printed using the  standard Excel methodology.
                                                                                   21

-------
Worksheet Validation
The CUECost workbook was constructed to allow the user to have the maximum flexibility to
modify it to generate site-specific cost estimates without requiring an extensive amount of
input  data. The  technology worksheets were developed using different  sets of cost and
design data. The basis for each set of parametric design and cost equations is described in
the following section.

FGD WORKSHEETS - LSFO AND LSD TECHNOLOGIES

The equipment design  parameters and cost data are based on a combination of vendor
quotes and a  historical  database of installed power  projects  (Keeth et  al., 1991).  Cost-
versus-capacity curves were constructed based on this historical information combined with
vendor  quotations  from  both  installed  FGD  systems  and  budgetary  quotes  received
specifically for this CUECost project. Many of the sources of information that were used in
this development of the  FGD system  costs are not available  to the public  due to the
proprietary nature of the information and the project-specific sensitivity of the cost data.

This equipment  cost database was assembled  based on  the  experience gained  at FGD
installations for 10-15 plants ranging in size from 300 to 2000 MW. Equipment cost data is
produced  by compiling  data taken  from these  10 to  15  actual  installations,  vendor
quotations for  construction  contracts,  and  budgetary  quotations  obtained  in  1998
specifically to support this CUECost project. The budgetary quotes for large equipment  items
were  received from one to six vendors depending on the component. The accuracy of the
CUECost is validated by comparing the results generated by  the CUECost model to published
cost  data for many of  the  Phase 1  FGD  systems installed  in  response to acid  rain
regulations.  The validation of the  data used in  the  development of these algorithms is
described  in Appendix D.

The cost estimates from CUECost were compared to the  results generated by other models,
including the  comparison to the  Electric Power Research Institute's (EPRI) FGDCOST model
(Keeth et  al., 1991). EPRI's FGDCOST  model has been used throughout the utility industry

	22

-------
Worksheet Validation
for the last seven years and has demonstrated its ability to estimate site-specific costs well
within ROM accuracy requirements. The CUECost estimates were found to agree well with
the results generated by the FGDCOST model when allowance was made for the changes in
the technology  that  have occurred since the  FGDCOST  model  was constructed,  the
escalation of costs, and  the reduced level of design  data that is required  by the CUECost
workbook.

CUECost was also used to calculate cost estimates for many of the  Phase  1 FGD systems.
Actual installed cost data have been published in various sources for these systems. These
data were compared to  the estimates generated by the CUECost workbook and CUECost
reproduced these actual  costs within an accuracy of ±12%. Table 4  provides the results of
this comparative  analysis for previously installed FGD  systems.

Table 4.     CUECost-FGD Cost Comparison to FGDCOST by EPRI for Phase 1 Acid Rain
            Installations
un-
Petersburg
Cumberland
Conemaugh
Ghent
Gibson
Bailly
Milliken
Navajo
"•SS1*
657
2600
1700
511
668
600
316
2250
Sulfur
%
3.50
4.00
2.80
3.50
3.50
4.50
3.20
0.75
%
95
95
95
90
91
95
98
92
vSi
317
200
195
215
247
180
348
236
CUECost,
$/kW
291
187
179
229
218
196
362
213
% Difference
-8.20
-6.50
-8.20
+6.5
-11.70
+8.9
+4.0
-9.75
PARTICULATE MATTER CONTROL WORKSHEET

The  particulate  matter control  sizing equations were based  on  previously published
correlations  developed  by CMU  (Berkenpas  et  al.,  1999).  This  development process is
described in  Appendix D. The CMU model was constructed using design information supplied
by multiple vendors.

The CMU model used a  modified version of the Deutsch-Anderson equation (Edgar, 1983) to
relate removal efficiency to collection area and gas flow rate for various coals as part of the
ESP sizing calculations.  The original Deutsch-Anderson equation was found to be inaccurate
for removal  efficiencies  above 95%. Various empirical models were developed to overcome
this inaccuracy, and the CMU model chose to use the White  version  (White, 1977) of the
modified Deutsch equation provided below (Eq. 1):
                                                                                23

-------
Worksheet Validation
   h = 1- exp {-A/V H wk}k                                                     (Eq. 1)

where
h = collector removal efficiency
A = collector area, ft2
V = volumetric flue gas flow rate, actual cubic feet per minute (acfm)
wk = precipitation rate parameter
k = constant varying with coal  type.

The  wk and  k values used in the  CMU  ESP  sizing equations (Berkenpas, 1999)  were
correlated with the calculated  total ash  resistivity (based on the ash analysis provided by
the user or the default database in worksheet 11.0), and separate k curves were developed
for groups of coals that have similar sulfur content. The modified sizing  worksheet provides
the expected  specific collection area (SCA)  for the ESP, and a new set of cost equations was
developed to  relate the  ESP  size (calculated from  the  SCA and the  ESP inlet  flue gas
volumetric flow rate) to the expected  cost for the installed system.

The ESP equations provided in  the CMU model were reviewed and compared to the expected
ESP  sizes in  terms of SCA, evaluating  the  various types of coals listed in Table 5. The
"Raytheon" SCA data  provided in Table 5  were calculated using a series of  parametric
equations developed by Raytheon Co.2 These equations  were derived  from SCA data for
utility  coal-fired  installations  over the past  25 years  obtained  by  Raytheon  Co.  and
incorporated into a proprietary model used for confirmation of vendor data and specification
preparation. As can be seen in Table 5, the  CUECost workbook calculates SCA values that
are within ±12% of the values  generated by the Raytheon model.

The costs generated by CUECost were compared to the current  IAPCS results for the  same
plant sizes and coals.  The results were within 30% of the IAPCS cost estimating model
(Gundappa et  al.,  1995)  over a  range of SCA values from  300 to 600. The  FF  cost
algorithms (one for pulse jet design and one  for reverse gas) were developed from 10  to 12
firm price quotations (obtained during 1992-1997) for each FF design. The coal-fired boilers
ranged in size from 50 to 500 MW.
'- The Raytheon database is proprietary.

	24

-------
Worksheet Validation
Table 5.
Comparison of CUECost ESP Sizing Estimates with Raytheon Model
Coal Type
Indiantown
WV-EPRI
Low S Bituminous
Keystone
India
Logan, WV
ND Lignite
UT-EPRI
UT-Alternate
Rosebud, MT
WY-PRB
Test Coal
Pitts 8
Carneys
TX Lignite
OH Alternate
IL #6
Armstrong, PA
Jefferson, OH
Sulfur
Content,
%
1.09
0.66
0.97
1.09
0.5
0.89
0.94
0.53
0.66
0.56
0.37
2
2.13
2
1.16
4.7
3.25
2.6
3.43
Removal
Efficiency, %
99.4
99.2
99.4
99.3
99.9
99.7
99.4
99.5
99.6
99.5
99.3
99.1
99.2
99.1
99.8
99.6
99.5
99.3
99.6
Raytheon
SCA*
385
418
403
393
965
569
376
446
435
482
558
287
272
288
549
247
276
277
321
CUECost SCA*
429
375
424
386
883
502
411
442
482
459
558
283
285
281
549
259
261
274
326
%
Difference
+ 11.43
-10.29
+5.21
-1.78
-8.50
-11.78
+9.31
-0.90
+ 10.80
-4.77
0
-1.39
+4.78
-2.43
0
+4.86
-5.43
-1.08
1.56
  SCA = square feet of plate area per 1000 actual cubic feet per minute of flue gas flow
NOX CONTROL WORKSHEET

For NOX control technologies, CUECost results were compared to cost data  reported by the
EPA Acid  Rain Division for NOX controls applied to  utility boilers  (Khan and  Srivastava,
2004), and Chapter 5 of the IPM manual.3 The Acid Rain Division  reports (EPA,  1997; EPA,
1998) are based on an  EPA national database of boilers (Khan and  Srivastava,  2004). The
1990 Clean Air Act Amendments required the EPA to examine NOX control technology costs,
and the resulting Acid Rain Division studies (EPA, 1997; EPA, 1998) were used and reviewed
during  the rule-making  process. A comparison was made for four cases with  various boiler
types,  boiler sizes (100 to 400  MW)  and coals burned. The  boiler design and operating
parameters  for each  case were input  into CUECost to obtain capital and operating  and
maintenance costs. In some cases the capital cost estimating  algorithms in these sources
3 available at: http://www.epa.gov/airmarkets/proqsreqs/epa-ipm/index.html and can be downloaded at
http://www.epa.gov/airmarkets/proqsreqs/epa-ipm/docs/Section-5.pdf.
                                                                                    25

-------
Worksheet Validation
already included provisions for retrofit factor, general facilities,  engineering, contingency,
and other factors that, using CUECost methodology, are in addition to equipment costs. So
it was necessary  to adjust for these  additional  costs in arriving at the equipment  cost
algorithms for CUECost.  For this reason,  the algorithms programmed into CUECost may be
different from those shown in the IPM report  or the Acid Rain Division reports (Khan and
Srivastava, 2004).  However,  using CUECost's default values for retrofit factor, general
facilities, etc., should produce capital cost results that are the same as or very close to the
results that would be produced by the IPM source algorithms.

Different approaches were taken to verify or validate the costs predicted by CUECost for the
various NOX control technologies. For SCR, SNCR and  NGR, design parameters used for the
ARD study cases  (EPA,  1997; EPA, 1998) were used to  calculate  preliminary operating
parameters and costs with CUECost. Algorithms for SCR in  CUECost were compared  to the
ARD study costs to validate the algorithms. However, the ARD data were incorporated into
the algorithms for SNCR and NGR. As a result, the cost comparisons for these technologies
were  conducted to benchmark the algorithms and evaluate how well they track the  ARD
data.  The percent differences  found for the four boiler cases are presented in Table 6.
Differences range  in magnitude from 0 to 11% for total plant costs and from 0 to 22% for
operating and maintenance costs.

SNCR capital  costs are determined from  the IPM  and are documented in Chapter 5  of the
IPM manual (http://www.epa.QOv/airmarkets/proqsreQS/epa-ipm/index.html), which can be
downloaded at httD://www.eDa.qov/airmarkets/Droqsreqs/eDa-iDm/docs/Section-5.Ddf.

The algorithms used to estimate costs for  LNBT in CUECost were taken from an Acid  Rain
Division study (EPA, 1996). The cost data upon which the algorithms were based represent
actual LNBT retrofit cases. The capital  cost comparison shows  0% difference, as expected,
because  the algorithms are based solely on ARD data. A comparison is not presented for
operating and maintenance costs because these costs are  highly boiler specific.
                                                                                 26

-------
Worksheet Validation
Table 6. Percent Difference between CUECost and Acid Rain Division Studies (Khan
and Srivastava, 2004) for Retrofit Cases *

Cyclone

Fired

Midwestern Bituminous


140
Boiler
400
Wet Bottom
Vertical Fired Wall Fired
Eastern Bituminous
Size (MW)
100 259
Total Plant Costs
SCR (50% removal)
SNCR (50% removal)
NGR (35% removal)
4%
8%
-11%
0%
0%
-7%
8% -4%
12% 4%
-12% -12%
O&M Costs
SCR (50% removal)
SNCR (50% removal)
NGR (35% removal)
-12%
8%
-11%
-18%
0%
-7%
-16% -22%
12% 4%
-12% -12%
  Note: Percent Difference = (Acid Rain Costs - CUECost Results) x 100 /Acid Rain Costs
MERCURY CONTROL WORKSHEET

Mercury control technologies  included in CUECost are co-benefit controls from air pollution
control technology used for other pollutants  and sorbent-based mercury-specific controls.
Mercury control technology cost and performance estimates are determined by algorithms
described  in U.S.  EPA (2003), Staudt, Jozewicz, and Srivastava (2003), Srivastava, Staudt,
and Jozewicz (2004), as well as in Appendix F of this manual.

In addition to the impact of sorbent cost on operating cost of mercury control technologies,
calculations include estimates of the impact  of  parasitic load and filter  replacement (if a
fabric filter is retrofit) and the impact the  sorbent may have on fly ash marketability when
the sorbent and fly ash are collected in the same  PM control device.

Capital cost estimating methodology was made consistent with other technologies with the
sole exception that we included Process Contingency for Hg Control in addition to the other
cost factors because of the relative newness of Hg control technologies. The user may input
a Process Contingency  percentage  in the Input worksheet  or accept the  default Process
Contingency value of 5%.

Detailed review of mercury control technologies, performance, and future improvements can
be  found  elsewhere  (Srivastava et  al.  2004;  EPA  2003).  One  of  the most  promising
technologies to control mercury emissions from coal-fired power plants is SI, especially the
activated carbon injection (ACI). Table 7 provides the estimated capital and O&M costs of an
ACI control system from CUECost.
                                                                                   27

-------
Worksheet Validation
Table 7.
Estimated Costs of ACI Control Systems according to CUECost*
ARC Configuration
ACI +Cold-side ESP
ACI +Cold-side ESP
+ Wet FGD System
Capital Cost
(2005$/kW)
19.41
19.41
O&M Cost
(2005$/MWh)
4.06
4.06
Hg Removed by
Sorbent Injection
(Ib/yr)
240.7
188.9
Control Cost
(2005$/lb Hg
removed)
53,380
68,013
ACI+ Dry Scrubber
+ Fabric Filter
           3.17
0.32
290.7
3,844
* Note: 500 MW, Wyoming Powder River Basin (PRB) coal, activated carbon injection, capacity
factor = 65%, 80% Hg removal.
CARBON DIOXIDE CONTROL WORKSHEET

Carbon  dioxide (CO2) control technologies included in CUECost are based on MEA solvent,
chilled ammonia and sorbent injection. These technologies, as described in Appendix B.6 of
this manual, generally include absorption/regeneration  island and compressor island. The
capital cost of the CO2 control facility in the CUECost is the lump-sum of the individual costs
and given by a regressed equation based on  currently available bare erected plant cost from
the DOE report (2007). As there is no  SI based CO2 control  technology adopted  in a power
plant, its capital cost  is estimated to a  comparable cost  for MEA  process. For all  the control
technologies, the compressor island cost is regressed on the basis of power consumption of
compressors.  Gas  flow rate and  specific variable  costs are estimates and determined by
algorithms  described  in Appendix D. Table  8 summarizes the estimated  capital and O&M
costs  of CO2-related control technologies from CUECost.
Table 8.
Estimated Costs of CO2 Control Technologies with CUECost and IECM model.


Total Plant Cost (TPC), Million $
Total Capacity Requirement
(TCR), Million $
O&M
Fixed O&M, Million $/yr
Variable O&M, Million $/yr
$ (constant)/ton CO2

MEA
350.8
388.3

12.3
76.4
51
CUECost
CAP
322.1
353.1

11.36
42.6
34

SI
350.8
380.2

12.3
39.0
34
IECM
MEA*
232.2
273.3

7.3
103.7
37
Note: estimates are based on a 580 MW plant, firing Illinois bituminous coal. The plant
capacity factor is 65% and demands a 90% CO2 removal efficiency. Capital cost is calculated
for the base year of 2006.
*The MEA data was calculated with the IECM model developed by CMU. The IECM program can be
downloaded from http://www.iecm-online.com/iecm_dl.html.
                                                                                   28

-------
Worksheet Validation
VALIDATION SUMMARY

Costs for  utility ARC systems are site-specific. These costs are subject  to  change with
changes in technology, labor rates, and material costs. The costs estimated by the CUECost
workbook  come from a variety of sources. With  that understanding, one may assume, but it
is not guaranteed, that CUECost will produce estimates in the range of accuracy of ±30% of
the actual cost, which was the goal of the CUECost development.  The operating cost
estimates  are more straightforward  than the capital cost estimates, relying  more on the
accuracy of the input  data supplied by the user.  The  calculation  sequences for these
estimates  have been verified on  a  cell-by-cell basis during  the  course of the workbook
development. The documentation  provided in Appendix F also allows any  user to verify a
specific  calculation sequence  that might be  in  question at some  point in  the future. The
economic  calculation methods used have been  well established for many years throughout
the utility  industry,  and have been  documented  in the  EPRI Technical Assessment Guide
(Ramachandran, 1989).
                                                                                 29

-------
References
Berkenpas, M. B.;  Frey, H.C.; Fry, J. J.; Kalagnanam, J.; Rubin, E. S. "Integrated
Environmental Control Model (Technical Documentation)," Prepared for the Federal Energy
Technology Center (U. S. Department of Energy). May 1999.

Bustard,  J., Durham, M.,  Lindsey, C., Starns,  T., Baldrey,  K.,  Martin, C.,  Schlager, R.,
Sjostrom, S., Slye, R., Renninger,  S., Monroe,  L,  Miller, R., Chang,  R., 2001. "Full-Scale
Evaluation of Mercury Control with  Sorbent Injection and COHPAC at Alabama Power E.G.,
Gaston",  DOE-EPRI-U.S. EPA-A&WMA Power Plant Air Pollutant Control "Mega" Symposium,
August 20-23, 2000, Chicago, IL.

Bustard,  J., Durham, M.,  Lindsey, C., Starns,  T., Baldrey,  K.,  Martin, C.,  Schlager, R.,
Sjostrom, S., Slye, R.,  Renninger, S., Monroe,  L., Miller, R., Ramsey,  C., 2002. "Gaston
Demonstrates Substantial Mercury Removal with  Sorbent Injection", Power Engineering, vol.
106, no.  11.
DOE/NETL. 2007.  Cost and  Performance Baseline  for Fossil  Energy Plants  (DOE/NETL-
2007/1281).

Durham, M., Bustard, J., Schlager, R., Martin, C., Johnson, S., Renninger, S.,  2001. "Field
Test Program to Develop Comprehensive Design, Operating Cost Data for Mercury Control
Systems  on  Non-Scrubbed  Coal-Fired  Boilers",  AWMA 94th  Annual  Conference and
Exhibition, Orlando, FL, June 24-28 2001.
Edgar, T. T., 1983. Coal Processing and Pollution Control. Houston, TX. Gulf Publishing Co.

EPA, 1996. "Cost-effectiveness of Low-NOx Burner Technology Applied to Phase I, Group  1
Boilers,"  prepared  by Acurex Environmental Corporation for EPA Acid Rain Division. This
report is  available to the public from EPA's Office of Air and Radiation, Acid Rain Division,
Washington, DC 20460 (ph. 202-564-9085).

	30

-------
References
EPA, 1997. "Investigation of Performance and Cost of NOX Controls as Applied to Group 2
Boilers," EPA, Washington, DC. This report is available to the public from EPA's Office of Air
and Radiation, Acid Rain Division, Washington, DC 20460 (ph. 202-564-9085).

EPA, 1998.  "Cost Estimates for  Selected  Applications of NOX Control Technologies on
Stationary Combustion Boilers and Responses to Comments," EPA, Washington,  DC.  This
report is available to the public from EPA's  Office of Air and Radiation, Acid Rain  Division,
Washington, DC 20460 (ph. 202-564-9085).

EPA, 2000, Performance and Cost of Mercury Emission control Technology  Applications on
Electric Utility Boilers, EPA-600/R-00-083.

EPA, 2003.  "Performance  and  Cost  of  Mercury  and  Multipollutant Emission  Control
Technology Applications on Electric Utility Boilers," EPA-600/R-03-110, October 2003.

EPRI, 2000, An Assessment of Mercury Emissions from U.S. Coal Fired Power Plants, EPRI,
Palo Alto, CA.

Frey, C.H. and E.S.  Rubin, 1994. "Development of the Integrated  Environmental Control
Model:  Performance  Models of Selective Reduction  (SCR)  NOX Control  Systems; Quarterly
Progress Report to Pittsburgh Energy Technology Center, U.S. Department of  Energy, from
Center for Energy and Environmental Studies, Carnegie Mellon University," Pittsburgh, PA.
Document number DE-AC22-92PC91346-11

Gundappa, M., L.  Gideon, and E. Soderberg, 1995. "Integrated Air Pollution  Control System
(IAPCS),  version  5.0,  Volume 2:  Technical Documentation,  Final," EPA,  Air and Energy
Engineering  Research Laboratory, Research Triangle Park, NC, EPA-600/R-95-169b (NTIS
PB96-157391).

Keeth,  R.  J., Baker,  D. L., Tracy,  P. E., Ogden,  G.  E.,  and Ireland,  P. A.,  1991. Economic
Evaluation of  Flue Gas Desulfurization System.  No. GS-7193, Research  Project  1601-6.
EPRI. Palo Alto, CA.

Khan, S.,  and  Srivastava, R. "Updating Performance and Cost of NOX Control  Technologies
in  the  Integrated Planning  Model",  EPA-EPRI-DOE Combined Power Plant  Air  Pollution
Control Mega Symposium, August 30-September 2, 2004, Washington,  DC.

Ramachandran, G., 1989. "TAG™ Technical Assessment Guide," EPRI Report No. P-6587-L,
Volume 1: Rev.6.

Srivastava R. K. "Controlling SO2 emissions: A review of technologies." U.S. Environmental
Protection Agency EPA/600-R-00/093, 1999

Srivastava, R.  K., Staudt, J., Jozewicz,  W. "Preliminary Estimates of Performance and Cost
of Mercury Emission Control Technology Applications on  Electric Utility Boilers: An  Update",
                                                                                 31

-------
References
EPA-EPRI-DOE Combined Power Plant Air Pollution Control Mega Symposium, August 30-
September 2, 2004, Washington, DC

Starns, T., Bustard, J.,  Durham,  M.,  Lindsey, C.,  Martin,  C., Schlager,  R., Donnelly,  B.,
Sjostrom, S.,  Harrington, P.,  Haythornthwaite,  S., Johnson, R., Morris,  E., Chang,  R.,
Renninger, S., 2002, "Full-Scale Test of Mercury Control with  Sorbent Injection and an ESP
at Wisconsin  Electric's  Pleasant Prairie Power Plant", AWMA 95th Annual Conference and
Exhibition, Baltimore, June 23-27 2002.
Staudt,  J.E.; Jozewicz, W.;  Srivastava, R.  "Modeling  Mercury Control with  Powdered
Activated  Carbon", AWMA Paper  03-A-17-AWMA, Presented at the Joint EPRI  DOE EPA
Combined Utility Air Pollution Control Symposium, The Mega Symposium, May 19-22, 2003,
Washington, D.C.

White, Harry J., 1977. "Electrostatic Precipitation of Fly Ash," J. Air Pollution. Control Assoc.,
March 1977, Volume 27, No. 3, pp. 206-217.
                                                                                 32

-------
Appendix A
A.1    DEFINITION OF TERMS

Allowance for  Funds Used During Construction  (AFDC) - Represents the time value  of
money during  the construction period. AFDC is calculated based on the weighted cost of
capital, compounded on an annual basis throughout the  period, and applied to all funds
spent during each year. This cost is added to the Total Cash Expended to  obtain TPI. See
Table 2 for the use of the AFDC factor. The AFDC factor is input by the user, and is a
function of the years of construction and the discount rate.

Ammonia  Slip  = The un-reacted ammonia that exits an SCR or SNCR process, and exits
the stack with  the flue gas. Ammonia slip is expressed as a concentration in the exit gas
or as a percentage of the mass of ammonia input to the process.

Battery Limits  = The boundary  limits  within  a  plant  used  to define  the equipment
components contained in a subsystem.

Capacity Factor  (CF)  - Equivalent to the ratio  of the total energy  output  over a time
period  divided  by the total gross energy generating capacity of the unit. Typically the CF
is input as the  expected average value over the remaining plant life.

Carrying Charge Factor (CCF) - Amount of revenue per dollar of investment that must be
collected from  customers in  order to pay the carrying charges on that investment. The
CCF is expressed as a decimal that is multiplied by the  original investment to obtain a
carrying charge in  terms of dollars. The carrying charge rate can  be a present value  or
levelized quantity over a specified period  of time (up to the  book life), or an annual
quantity in a specific year of life. The factor includes the return on debt, return on equity,
income and property taxes, book depreciation,  rate of return  to  shareholders,  and
insurance.
                                                                                  33

-------
Appendix A
Constant Dollar - Cost estimate presented  in terms  of the  base year dollars without
including the impact of inflation over the plant life. However, real escalation is included in
the calculation of future year  costs. Constant  dollar analysis  requires the  use of a
discount rate that does not include inflation.

Contingency  -  A capital cost included  in  the estimate to cover the costs for additional
equipment or other costs that are expected to be  incurred during a project after the detailed
design is completed. These are funds that  are expected to be spent during  implementation
of the final  project.  The  contingency  is  factored as a  percent of  process  capital plus
engineering,  home office and general facilities.

Current Dollar - A cost analysis that includes the  effects of  inflation and real escalation. The
discount rate used for current dollar analyses is equivalent to  the return required to attract
investment capital and  is equivalent to the weighted  average of the return on equity and
return on debt.

Engineering and Home Office Costs - Derived as a percentage of the total direct capital cost.
This indirect cost includes the costs for an  architectural/engineering company and for home
office engineering expenses  by  the user's  company. This value typically ranges from 5 to
20% of the Process Capital,  with the percentage varying  based on the level of complexity
for equipment installation (e.g.,  a new plant might have a value of 5 to 10% while a retrofit
might experience engineering costs closer to 15-20%).

General Facilities - Includes costs for items such as  roads, office buildings,  maintenance
shops, and laboratories. The indirect cost for these facilities typically ranges from 5 to 20%
of the Process Capital.

Heat  Rate  -  Equivalent  to  the  fuel energy content  (Btu)  required to  produce 1 kWh of
electric  energy. Fuel  energy content  is  typically  based on  the higher  heating value of the
fuel.

Inflation Rate  -  Equivalent to  the  rise in prices caused by  an increase in the  available
currency and credit without a proportionate increase in availability of goods and services of
equal quality. The inflation rate does not include the effects of real escalation.

Operating Costs - Operating costs for each  technology are expressed  in terms of both $/kW-
year and  mills/kWh.  The $/kW-year  costs are considered to be  an expression of annual
costs  and, therefore,  include the capacity factor in the  calculation. The  mills/kWh values are
considered instantaneous values, and, therefore,  do not include  the  capacity factor in their
calculation.

Present Value (PV)  -  Monetary  equivalent to the  amount of money at a point in time other
than that at which the amount of money is  paid or received.

	34

-------
Appendix A
Process Capital - Total installed cost of all process equipment.

Total  Capital Requirement (TCPO - Equivalent to the Total Plant Cost,  AFDC, plant startup
costs, and inventory capital.

Total  Plant  Cost  (TPC) -  Equivalent to  the total  installed  cost for all plant  equipment,
including  all direct  and  indirect  construction  costs,  engineering, overheads, fees,  and
contingency.
                                                                                    35

-------
Appendix B
B.I    LIMESTONE FORCED OXIDATION DESIGN CRITERIA

In a limestone with forced  oxidation (LSFO) system, the flue gas is contacted with slurry
containing approximately 15% calcium carbonate and sulfate solids. The  aqueous sulfite
formed  by SO2  absorption  is oxidized  to  sulfate  by  forced  air  injection in the tower
recirculation tank to  produce slurry with essentially 100% conversion of calcium sulfite to
sulfate. The series of chemical reactions that occur in an LSFO absorber and reaction tank is
described in Eqs. B-l and B-2:

   SO2 Reaction:  CaCO3 (s) + SO2 (g) +  1/2 H2O -> CaSO3 • 1/2 H2O + CO2       (Eq.  B-l)

   Sulfite Oxidation:  CaSO3 • 1/2 H2O +  1/2 O2 + 3/2 H2O -> CaSO4 • 2 H2O      (Eq.  B-2)

The CUECost  workbook requires that the user input new values for the slurry recycle rate
(Liquid to  Gas Ratio = L/G) whenever the SO2 removal efficiency across the FGD system is
changed versus the  current 95% removal  rate included  as the base case default value.
Typically the  increase in removal efficiency above this  95% level will require significant
increases in the recycle rate. A value of  140 gallons/1000 actual cubic feet (L/G) would  be
typical for a 97% removal system versus the 125 value for a 95% system. Therefore, the
pump sizes and power consumption required in the FGD system would increase significantly.
Values for the limestone feed rate (stoichiometric feed ratio default =  1.05  moles of CaCO3
per mole of SO2 removed) also remain constant with changes in the removal efficiency, but
can be modified by the user if additional vendor information is available.

The slurry produced by the  FGD system can  be thickened and pumped directly to a  gypsum
stack for final disposal, vacuum filtered  or centrifuged for landfill disposal, or washed and
dewatered for commercial wallboard production.
                                                                                 36

-------
Appendix B	

The LSFO Process  Equipment includes the Reagent Handling and Preparation, SO2 Control
System, and the Byproduct Handling.
Reagent Handling and Preparation includes the following:
•  Reagent storage
•  Reagent feed
•  Ball mill and hydroclones
•  DBA acid tank.

SO2 Control System includes:
•  SO2 removal system
•  Absorber tower
•  Spray pumps, spray nozzles, associated piping.

Byproduct Handling includes:
•  Waste/byproduct handling system
•  Thickener system.

ID Fans and Ductwork are:
•  Booster fans needed for the system
•  Ductwork between components.

Chimney  is:
•  Cost of replacement chimney and associated foundations.

Support equipment is:
•  Electrical support equipment and modifications not included elsewhere.

An alternative  design option is provided in the LSFO system to include the addition of DBA.
This additive helps to buffer the SO2  absorption  reaction, increasing the available alkalinity
in the slurry. Addition of DBA allows the system to be designed with lower recycle rates and
potentially a lower  limestone feed rate while maintaining the removal efficiency.
	37

-------
Appendix B
Specific design criteria for LSFO are shown in Table B-l. The default values provided in the
worksheet are  considered typical for  operating FGD systems  recently installed in the U.S.
Reagent costs  are typically based on the  costs stated in the journal Chemical  Marketing
Reporter.

Table B-l.    Specific Design Criteria  for LSFO
Description
Year equipment placed in service
SO2 Removal Required
L/G Ratio
Design Scrubber with Dibasic Acid Addition?
(1 = yes, 2 = no)
Adiabatic Saturation Temperature
Reagent Feed Ratio
(Mole CaCO3/ Mole SO2 removed)
Scrubber Slurry Solids Concentration
Reheat Air Temperature
Pressure
Stacking, Landfill, Wallboard
(1 = stacking, 2 = landfill, 3 = wallboard)
Number of Absorbers
(Max. Capacity = 900 MW per absorber)
Absorber Pressure Drop
Reheat Required?
(1 = yes, 2 = no)
Amount of Reheat
Reagent Bulk Storage
Reagent Cost (delivered)
Landfill Disposal Cost
Stacking Disposal Cost
Credit for Gypsum Byproduct
Retrofit Factor
Maintenance Factor (% of TPC)
Contingency (% of Installed Cost)
General Facilities (% of Installed Cost)
Engineering Fees (% of Installed Cost)
Time for Retrofit to use for TCE and AFDC factors
Units
year
%
gal / 1000 acf
Integer
°F
Factor
Wt. %
°F
in. H2O
Integer
Integer
in. H2O
Integer
°F
Days
$/ton
$/ton
$/ton
$/ton

%
%
%
%
years
Range

90-98%
95-160
1 or 2
100-170
1.0-2.0



1,2,3
1-6

1 or 2
0-50











Default
2004
95%
125
1
127
1.05
15%
440
1
1
1
6
1
25
60
$15
$30
$6
$2
1.3
3%
15%
5%
10%
2
                                                                                   38

-------
Appendix B	


B.2    LIME SPRAY DRYER DESIGN CRITERIA

In a lime spray dryer (LSD) process the flue gas exiting the air heaters enters a spray dryer
vessel. Within  the vessel,  an  atomized  slurry of lime and recycled solids contacts the flue
gas stream. The sulfur oxides in the flue gas  react with the lime and fly ash alkali to form
calcium salts.

The chemical  reactions associated with the  SO2 removal from the flue gas are provided
below (Eqs. B-3 through B-6):

   Lime Hydration:  CaO + H2O -> Ca(OH)2                                     (Eq. B-3)

   SOX Reaction (1): Ca(OH)2 + SO2 ->  CaSO3 • 1/2 H2O + 1/2 H2O              (Eq. B-4)

   SOX Reaction (2): Ca(OH)2 + SO3 + H2O -> CaSO4 • 2 H2O                    (Eq. B-5)

   Sulfite Oxidation: Ca(OH)2 + SO2 + H2O + 1/2 O2 -> CaSO4 • 2 H2O            (Eq. B-6)

The water entering with the slurry vaporizes,  lowering the temperature and  raising the
moisture content of the scrubbed gas.  A  particulate  matter control device downstream  of
the spray dryer  removes the dry solids and fly ash  that did  not fall out in the vessel. A
portion of the  collected  reaction products and fly  ash solids  is recycled to the  slurry feed
system. The remaining solids are transported to a landfill for disposal.

The CUECost  workbook responds to changes  in  the  removal  efficiency  and any  other
parameter by  using the input values entered by  the user and  recalculating the material
balance on that  new basis. No  other changes in the worksheet are done automatically in
response to changes in parameters. The CUECost  workbook does modify the solids recycle
rate  as the coal sulfur content is  modified. The modification  is  done with a  look-up
tabulation of recycle values associated with various coal  sulfur percentages. A look-up table
is embedded in worksheet  11.0 Constants_CC of the CUECost workbook.

The LSD system  incorporates five specific equipment areas:

•  Reagent handling and preparation

•  SO2 control system

•  Byproduct handling

•  ID fans and ductwork

•  Support equipment.

The Reagent Handling and  Preparation includes the following:
                                                                                 39

-------
Appendix B	


•  Lime storage and preparation

•  Lime slaker.

SO2 Control System includes:

•  SO2 removal system

•  Absorber tower

•  Spray pumps, spray nozzles, associated piping.

Byproduct Handling includes:

•  If LSD system is installed upstream of existing ESP, this includes modifications to existing
   ESP due to increased solids handling and gas with more moisture

•  Otherwise, SDA and new FF or SDA  and new  ESP need to be added. Their costs can
   further be calculated for ESP and FF calculations in the ESP and FF worksheet.

ID Fans and Ductwork are:

•  Booster fans needed for the system

•  Ductwork between components.

Support Equipment is:

•  Electrical support equipment and modifications not included elsewhere

The  annual  Maintenance (component of  the operating cost), additional General Facilities,
and  Engineering factors provided  in Table B-2 are multiplied by the installed equipment
capital cost  to obtain an estimate of these costs to the utility. The Contingency factor is
applied to  the total bottom line cost (Equipment Installed  Cost plus  Site Facilities and
Engineering)  and  represents an  estimate of the  capital that  will be  expended  but not
accounted for in  the estimate due to the level of detail  included in the system design for this
cost  worksheet.
                                                                                  40

-------
Appendix B
Table B-2.    Input for LSD and the Default Values for the Inputs
Description
SO2 Removal Required
Is SDA being retrofit upstream of existing ESP?
(0 = no, 1 = yes)
Adiabatic Saturation Temperature
Flue Gas Approach to Saturation
Recycle Slurry Solids Concentration
Number of Absorbers
(Max. Capacity = 300 MW per spray dryer)
Absorber Material
(1 = alloy, 2 = RLCS)
Spray Cooler Pressure Drop
Reagent Bulk Storage (days)
Reagent Cost (delivered)
Dry Waste Disposal Cost
Retrofit Factor
Maintenance Factor (% of TPC)
Contingency (% of Installed Cost)
General Facilities (% of Installed Cost)
Engineering Fees (% of Installed Cost)
Project Duration (years)
Units
%
integer
°F
°F
Wt. %
integer
integer
in. H2O
integer
$/ton
$/ton

%
%
%
%
integer
Range
90-95%
0,1
100-170
10-50
10-50
1-7
1 or 2










Default
90%
0
127
20
35%
1
2
1
30
$65
$30
1.3
2%
15%
5%
10%
2
B.3    PARTICULATE MATTER CONTROL DESIGN CRITERIA

In a particulate control system,  the flue gas exiting the air heaters  enters an  ESP or FF
through the inlet manifold. In an ESP, the particulate matter is electrically charged by the
electric fields generated. This charge helps to move the particles to  the  collecting plates'
surfaces, and  holds  them in place  until  the  collected material can  be discharged  into the
collecting  hoppers.  ESPs are  available  in  a  wide  variety  of  designs  and  construction
materials; collecting  plate design, size and spacing; electrode design;  etc. These variations
in design among vendors are not addressed in this worksheet, and are  not expected to drive
the final system cost estimates  beyond the stated  ROM estimate accuracy. The dry fly ash
material is typically transferred to final disposal silos by a pneumatic conveying system.

Within the  FF, the particulate matter is collected on  filter bags suspended vertically within
the FF  vessel.  The  particulate  matter is physically removed from the  gas as it passes
through the filter bags, by impacting both the bag fibers and the filter cake that collects on
the surface  of the bags. Periodically,  individual FF  compartments are  mechanically cleaned
by reversing the gas flow or using a pulse jet design that uses pressurized air to force the
collected fly ash off the bags  and into  the collection  hoppers. The two design  options
                                                                                    41

-------
Appendix B
(reverse gas and  pulse jet) are available as options in the worksheet. The air-to-cloth  ratio
(square feet  of cloth required per 1000  actual cubic feet per minute  of flue gas flow)
identifies the  size of the FF required, quantifying the amount of cloth area required to treat
a given gas flow  rate. Once again, the ash is typically transferred  to the waste  silo  by a
pneumatic conveying system.

The  CUECost  workbook  responds to  changes in  the removal efficiency and any other
parameter  by using the  input values entered by  the  user and recalculating the material
balance on that new  basis.  No other changes in the worksheet are done automatically in
response to changes in parameters. The model does modify the solids collection rate as the
coal ash content is modified.

Specific design criteria associated with particulate  matter control are summarized in Table
B-3 below:

Table B-3.    Inputs for Particulate Matter Control and Its Default Values
Description
Units
Value
Particulate Matter Control
Outlet Part. Matter Emission Limit
Particulate Matter Control Process
(1 = Fabric Filter, 2 = ESP)
Ibs/MMBtu
integer
0.03
1
Fabric Filter
Fabric Filter Type
(1 = Reverse Gas, 2 = Pulse Jet)
Gas-to-Cloth Ratio
Bag Life
integer
acfm/ft2
years
2
1.8
5
Electrostatic Precipitator
Specific Collection Area (SCA)
ft2 Collecting Plate/
1000 acfm Gas
Calculated based on ash
composition and
collection efficiency
B.4    NOX CONTROL TECHNOLOGY CRITERIA

Four NOX control technologies are included in CUECost:

•  Selective Catalytic Reduction (SCR)

•  Non-Selective Catalytic Reduction (SNCR)
   Natural Gas Reburning (NGR)

   Low NOX Burners (LNB).
                                                                                  42

-------
Appendix B
The process design criteria and assumptions that serve as defaults within the worksheet are
described in the following sections.

B.4.1 Selective Catalytic Reduction Design Criteria
Selective catalytic  reduction (SCR) is a post-combustion nitrogen oxides (NOX) reduction
process where  NOX in the flue  gas  is reduced  to  nitrogen (N2)  and water  (H2O)  using
ammonia (NH3)  as a reductant. The reduction  occurs  in the  presence  of a  catalyst at
reaction temperatures between 600 and 750 °F. SCR systems are typically based on one of
two designs:

•  A hot-side, high-dust SCR where the SCR system  is located between the economizer and
   air preheater

•  A cold-side, low-dust SCR where the  SCR is typically located downstream of the air heater
   and particulate control device

•  In a variation of this design, the SCR system can be located further downstream, after the
   flue gas desulfurization (FGD) system (often called a tail-end SCR system).


The CUECost algorithms  estimate costs for hot-side, high-dust systems, because hot-side
systems have been used on most SCR applications (EPA, 1996).

An SCR system reduces NOX concentrations in the flue gas using ammonia as the reducing
agent in a series of gas-phase reactions in the presence  of a catalyst to form nitrogen and
water. The chemical reactions for these  reduction reactions are provided below:

   4 NH3 + 4 NO + O2 -> 4 N2 + 6 H2O                                        (Eq. B-7)

   4 NH3 + 2 NO2 + O2 -> 3 N2 + 6 H2O                                       (Eq. B-8)

Small fractions of the ammonia can also be oxidized to alternate forms of nitrogen oxides:

   2 NH3 + 2 O2 -> N2O + 3 H2O                                              (Eq. B-9)

Some of the residual ammonia will also react with trace concentrations of the sulfur oxides
in the flue gas in the reactions shown  below.

   NH3 + SO2 + 1/2 O2 + H2O -> NH4HSO4                                   (Eq.  B-10)

   2 NH3 + SO3 +  H2O -> (NH4)2SO4                                         (Eq.  B-ll)

The solids formed in this  reaction can contribute to catalyst fouling and contamination of fly
ash.
                                                                                 43

-------
Appendix B
The key  operating parameters that affect the performance  and, consequently, the capital
and operating cost of SCR systems include the allowable  NH3 slip emissions,  the  space
velocity,  the NOX reduction efficiency, and the NH3/NOX molar ratio. For SCR systems, these
parameters are interrelated, and their values depend on the type of SCR application  (high-
dust or tail-end) and the desired performance levels. Ammonia slip  emissions are controlled
by the SCR system design. Typically SCR catalyst suppliers  provide a guarantee of 2 ppm
over the  catalyst life. Since the  2  ppm  NH3 slip is guaranteed at the end of the catalyst's
life, the initial NH3 slip emissions will be very low (<1 ppm).  For this reason, ammonia slip
does not  affect the catalyst volume calculations in CUECost.

The space velocity is the primary  parameter used  to specify catalyst volume. If the user
does not input a value for space velocity, CUECost calculates space velocity based on the
NOX reduction efficiency and the  NH3/NOX molar ratio. For SCR, NOX reduction efficiency can
range from approximately 60 to 95%, but systems are typically designed to achieve 70 to
90% removal. The NH3/NOX molar ratio generally ranges from about 0.7 to 1.0. Ammonia
can be injected  at  a greater than 1:1  stoichiometric  ratio to  increase NOX reduction
efficiency, but NH3slip would also increase significantly.

CUECost  estimates capital costs for reactor  housing, initial catalyst, ammonia  storage and
injection  system, flue gas handling including ductwork and induced draft fan modifications,
air preheater modifications and miscellaneous direct costs, including ash  handling and water
treatment additions  that typically are  modified due to  the increased  concentrations of
ammonium salts in the collected fly ash.

Operating and maintenance costs include NH3, catalyst replacement and disposal, electricity,
steam, labor and maintenance costs. Annual catalyst replacement costs are based on the
catalyst life. For  example, if the catalyst  life is 3 years and there are three catalyst sections,
then one-third of the catalyst is replaced each year. The catalyst disposal cost reflects the
cost of disposing of the spent catalyst. A typical  value of 48  Ib/ft3 was used for the catalyst
density to  calculate  the  mass of the  spent catalyst. Default input values  for SCR are
presented in Table B-4. The default inputs were  taken from EPA's ARD studies  (EPA,  1996)
where  available. Unit costs are escalated from 1995 dollars to 2004 dollars using Chemical
Engineering Magazine cost indices.
                                                                                   44

-------
Appendix B
Table B-4.    Default Input Parameters for SCR
Description
Inlet NOX level
NH3/NOX Stoichiometric Ratio
NOX Reduction Efficiency
Space Velocity (Calculated if zero)
Time to first catalyst replenishment (years)
Ammonia Cost
Catalyst Cost
Solid Waste Disposal Cost
Maintenance (% of installed cost)
Retrofit Difficulty Factor
Contingency (% of installed cost)
General Facilities (% of installed cost)
Engineering Fees (% of installed cost)
Mercury Oxidation Rate - bituminous coal
(removal if downstream)
Mercury Oxidation Rate - subbituminous coal
Duration of Project (years)
Units
Ib/MMBtu
decimal
decimal
1/h
integer
$/ton
$/m3
$/ton
%
decimal
%
%
%
%
%
integer
Range

0.7-1.0
0.60-0.90

2-5











Default
calculated
0.9
0.90
0
3
400
5000
11.48
0.66%
1.5
15%
5%
10%
90.0%
0.0%
2
6.4.2 Selective Non-catalytic Reduction Design Criteria
The  selective  non-catalytic  reduction  (SNCR)  process  involves injection of a  nitrogen-
bearing  chemical  (usually  NH3  or  urea)  into  boiler  flue  gases  within  a  prescribed
temperature range  (typically 1600 to  2000 °F). The  NH3 or urea [CO(NH2)2]  selectively
reacts with NOX  in the flue gas to convert it to N2. For the  NH3-based  SNCR process, either
aqueous or anhydrous NH3 is injected into the flue gas where the temperature is between
1600 and  1900 °F. Most  of the NH3 reacts with NO and oxygen in the gas stream to form N2
and  H2O.  For the CO(NH2)2-based  SNCR process, an  aqueous solution of CO(NH2)2  is
injected into the flue gas at one or more locations in the upper furnace and/or convective
pass. The CO(NH2)2 reacts with  NOX in the flue gas to form N2, H2O, and carbon  dioxide
(CO2). The chemical reactions for this conversion process are not well  defined, consisting of
a series of dissociation reactions at the elevated gas temperatures in the boiler gas path.
The following summary  equation describes the overall reaction that is occurring, while the
actual reaction mechanism is a  long series of dissociation  and chemical  reactions between
various free radicals.
                                                                                  45

-------
Appendix B	


Urea Reaction:

   CO(NH2)2 + 2 NO + 1/2 O2 -> 2 N2 + CO2 + 2 H2O                          (Eq. B-12)

Ammonia Reactions:
   4 NH3 + 4 NO + O2 -> 4 N2 + 6 H2O                                        (Eq. B-13)

   4 NH3 + 2 NO2 + O2 -> 3 N2 + 6 H2O                                       (Eq. B-14)

CUECost allows the user to select either CO(NH2)2 or NH3 as the SNCR reagent. The user is
asked to specify the  NOX reduction efficiency and  the stoichiometric molar ratio of reagent
to  NOX.  SNCR can  achieve  NOx-reduction  efficiencies  ranging  from 30  to  70%.
Approximately 50% reduction is typical. The SNCR process requires stoichiometric reagent-
to-NOx ratios of greater than 1:1 to achieve significant  NOX removal. The ratio can range
from about  0.5 to 2.5,  but will  typically fall  within the  range of 1 to 2. The NH3  and
CO(NH2)2 injection  rates are then calculated based on the stoichiometric ratio, inlet NOX and
boiler heat input.

For the CO(NH2)2-based SNCR process, the user chooses  wall  injectors, lances, or both. Wall
injectors are  nozzles installed in the upper furnace  waterwalls.  In-furnace lances protrude
into the upper furnace or convective pass and allow better mixing  of the reagent with the
flue gas. In-furnace lances require either  an air- or water-cooling circulation system. If the
user enters values for both wall injectors and lances, then costs include both lances and wall
injectors.  If wall injectors are to be used  alone, then the user enters zero for both the
number of lance levels and the number of lances.  Similarly, if lances  are to be  used alone,
the user enters zero for both the number of injector levels and the number of wall injectors.
CUECost uses input  parameters for the  number  of injectors and  lances  unless the user
wants these parameters to be calculated from the number  of levels. If the  user inputs zero
for the  number of injectors and  also inputs  the  number  of injector levels, CUECost will
calculate the number of injectors. Similarly, if the user inputs  zero for the number of lances,
the number of lances will be calculated  from the number of lance levels.  For the NH3-based
SNCR process, the  user can choose either steam or air as the atomizing medium. Based on
the user's choice, an annual operating cost for steam or electricity usage is calculated.

The main equipment areas in the battery limits for SNCR  include the reagent receiving area,
storage  tanks, and recirculation system;  the injection system, including injectors,  pumps,
valves,  piping, and  distribution  system; the control system;  and  air compressors.  In
addition, NH3-based SNCR systems use electrically powered vaporizers to vaporize the  NH3
prior to  injection.

Operating labor costs are based on two  person-hours required per 8-hour shift of operation.
The annual cost of the reagent is the major operating  cost item  for  the process and  is
calculated as the product of the reagent usage in tons/year  and the cost in dollars per ton of
                                                                                  46

-------
Appendix B
pure reagent. Electricity, water, and steam requirements are  based on vendor information.
The cost of steam or air for atomization of reagent is included as an operating cost.

Default  input values for SNCR are presented  in Table B-5. The default  inputs were taken
from  studies by  EPA's Acid  Rain Division (EPA, 1996; EPA,  1997;  EPA,  1998)  where
available.  Unit  costs  are  escalated from 1995  dollars to 2004 dollars using Chemical
Engineering Magazine cost indices.

Table B-5.    Default Input Parameters for SNCR
Description
Inlet NOX level
Reagent (l:Urea 2:Ammonia)
Number of Injector Levels
Number of Injectors
Number of Lance Levels
Number of Lances
Steam or Air Injection for Ammonia (1: Steam, 2: Air)
NOX Reduction Efficiency
NH3/NOX Stoichiometric Ratio
Urea/NOx Stoichiometric Ratio
Urea Cost
Ammonia Cost
Retrofit Factor
Maintenance (% of installed cost)
Contingency (% of installed cost)
General Facilities (% of installed cost)
Engineering Fees (% of installed cost)
Duration of Project (years)
Units
Ib/MMBtu
integer
integer
integer
integer
integer
integer
fraction
decimal
decimal
$/ton
$/ton
decimal
%
%
%
%
integer
Range







0.30-0.70
0.8-2.0
0.8-2.0








Default
calculated
1
3
18
0
0
2
0.50
1.2
1.2
400
300
1.3
1.5%
15%
5%
10%
1
6.4.3 Natural Gas Reburning Design Criteria
Natural gas reburning (NGR) involves substituting natural gas for a portion of the pulverized
coal supplied to the primary combustion  zone and injecting the natural gas downstream of
the primary combustion zone to form a reducing zone in which  NOX compounds are reduced
to N2. Combustion air for the reburning  fuel (natural gas) is injected further downstream.
Because the main combustion zone of furnaces employing this  technology operates in its
normal manner, gas reburning is  applicable to a wide range  of wall-, tangential-, and
cyclone-fired boilers.
                                                                                 47

-------
Appendix B
Boiler modifications for gas reburning involve installation of additional  fuel injectors and
associated piping and control valves. In the burnout zone, key components include overfire
air (OFA) ports,  a windbox, ductwork, and control dampers. Installation of the gas injectors
and OFA ports requires waterwall modifications. Adequate residence time must be available
both in  the reburn zone and the burnout zone to maximize NOX reduction and to minimize
unburned carbon losses. Consequently, for retrofit applications, adequate space between
the top burner row and  the furnace exit must be  available  for appropriately locating the
reburn fuel injectors and OFA ports.

The fraction of boiler heat input contributed  by  natural gas combustion (reburn fraction)
depends on the desired NOX removal efficiency. The  relationship between the reburn fraction
and NOX reduction  efficiency applies for  NOX reduction efficiencies from 55 to  65% and
corresponding reburn fractions from 0.08  to  0.20.  In CUECost, these are the valid  input
ranges  for the  NOX  removal  efficiency  and  reburn  fraction. If the  user inputs  both
parameters within the valid ranges, the input values are used for  cost calculations. If only
one parameter is outside  the  valid  range, that  parameter  is calculated using  the  other
parameter. If both input values are outside of the valid  ranges, a default reburn fraction  of
0.15 is  used  with a corresponding 61% NOX removal efficiency. The  installed costs of gas
injectors, OFA ports, and related equipment  are included in the NGR cost worksheet. Also
included in the NGR cost worksheet is the cost associated with piping natural gas to the
boiler from the metering station located at the utility plant fence-line.

In general, natural  gas reburning  reduces the boiler operating costs  associated with  coal-
and ash-handling process areas, including  maintenance, electricity, and  ash  disposal. Fuel
costs are generally higher,  because the price of natural gas is typically higher than the price
of coal. Maintenance costs  for operating the  NGR system are estimated at 2%  of the total
plant cost, plus a maintenance credit for operating the coal handling process at reduced coal
feed  rates.   Savings  from reduced  fly   ash  disposal  are  estimated  only  for  retrofit
applications. The incremental fuel cost  for firing gas is estimated by multiplying the amount
of gas burned by the fuel  price difference between gas and coal.  Default values for NGR
input  parameters are  presented  in Table  B-6. The default  inputs were taken  from ARD
studies  (EPA, 1996)  where available. Unit costs are escalated  using Chemical Engineering
Magazine cost indices.
                                                                                   48

-------
Appendix B
Table B-6.    Default Input Parameters for NGR
Description
Uncontrolled NOX level
NOX Reduction Efficiency
Gas Reburn Fraction
Waste Disposal Cost
Natural Gas Cost
Retrofit Factor
Maintenance (% of installed cost)
Contingency (% of installed cost)
General Facilities (% of installed cost)
Engineering Fees (% of installed cost)
Duration of Project (years)
Units
Ib/MMBtu
fraction
fraction
$/ton
$/MMBtu

%
%
%
%
integer
Range

0.55-0.65
0.08 - 0.20








Default
calculated
0.61
0.15
11.48
9.00
1.30
1.5%
15%
2%
10%
1
6.4.4  Low-NOx Burner Technology Design Criteria
Low-NOx  burner  technology  (LNBT)   limits  NOX formation  by  controlling  both  the
stoichiometric and temperature  profiles of the  combustion process in each burner flame
envelope. This control is achieved with design features that  regulate the aerodynamic
distribution and mixing of the fuel and air, yielding one or more of the following conditions:

•  Reduced O2 in the primary combustion zone, which limits fuel NOX formation;

•  Reduced flame temperature, which limits thermal NOX formation; and

•  Reduced residence time at peak temperature,  which  limits thermal NOX formation.

Low  NOX burner designs  for wall-fired  boilers can  be  divided  into two general categories:
"delayed combustion"  and  "internally staged."  Delayed combustion  LNBT  is designed to
decrease flame turbulence (thus delaying fuel/air mixing) in the primary combustion zone,
thereby establishing a fuel-rich  condition in the  initial stages of combustion. Internally
staged LNBT is designed to create stratified fuel-rich and fuel-lean conditions in or near the
burner. In  the fuel-rich regions, combustion occurs under  reducing conditions, promoting
the conversion of  fuel nitrogen  to N2 and  inhibiting fuel NOX formation. In the fuel-lean
regions,  combustion  is completed  at  lower temperatures,  thus  inhibiting thermal NOX
formation.

Conventional tangentially-fired  boilers consist of corner-mounted vertical burner assemblies
from which fuel and air are injected into the furnace. The fuel and air nozzles are directed
tangent to  an imaginary circle  in the center of the  furnace,  generating a rotating fireball in
the center of the boiler. Each corner has its own windbox that supplies primary air through
                                                                                  49

-------
Appendix B
the air compartments located above and below each fuel  compartment. For tangentially-
fired boilers, LNBT changes the  air flow through the windbox by decreasing the amount of
primary air and directing secondary air away from the fireball and toward the furnace wall.

Default  input parameters for LNBT and suggested ranges are  presented in Table  B-7. The
user selects the boiler type and the retrofit difficulty. CUECost calculates total capital cost as
a function of boiler size. The NOX  reduction efficiency input does not affect the capital cost
estimate, but is used to estimate emissions reduction.

Table B-7.    Default Values for LNBT Input Parameters
Description
Uncontrolled NOX level
Boiler Type (T:T-fired, W:Wall)
Burner Type
1 = LNBor LNC1,
2 = LNBand OFA or LNC2,
3=LNC3
Retrofit Difficulty Factor
General Facilities
Engineering
Contingency
Duration of Project (years)
Units
Ib/MMBtu
letter
integer
number
percent
percent
percent
integer
Range








Default
calculated
T
1
1.3
5.0%
10.0%
15.0%
1
B.5    Hg CONTROL TECHNOLOGY CRITERIA

Injection of powdered activated carbon (PAC) has been developed and tested at full scale on
coal-fired  utility boilers.  Test programs  have  been  performed on  a utility  boiler  firing
subbituminous coal  with  a  downstream cold-side  ESP,  on utility boilers firing  bituminous
coal  with a downstream  cold-side ESP, and  firing bituminous coal with a compact hybrid
particle collector (COHPAC) arrangement  (upstream  hot-side  ESP  with  downstream
baghouse after the air preheater). Performance models were developed.

B.5.1  Mercury Removal Models
EPA's  Information Collection Request  (ICR)4 showed  that  mercury released from  coal
combustion may be  partly removed  from the exhaust gases by existing equipment without
additional retrofit technology. The  existing  equipment may be one  or more pieces  of
equipment that  contribute to mercury removal.
'Available at http://www.epa.gov/icr/
                                                                                 50

-------
Appendix B	


If /equipment is equal  to the fraction of mercury removed from the boiler gases by a piece of
equipment,  then  (1 - /"equipment) equals the fraction of mercury remaining in the gases after
that piece of equipment. The fraction of mercury remaining after n pieces of equipment is
equal to

Fraction of mercury remaining after n pieces of equipment =

    L\l ~~ 'equipment lj  X (. 1 "'equipment 2) X 11  ~~ 'equipment 3) X . . . X ^1 — requjpment nJJ    l^q. D-ljJ

Therefore, the total mercury removal fraction = /Votai

    /Total = 1 ~ [(1 ~ /equipment!.) X (l~/equipment 2) X (1 ~ /equipments) X ... X (1 - /equipment n)] (Eq. B-16)

If one of the pieces of equipment is PAC  injection, then the total mercury removal fraction =
/Total =

    1 — [(1 — 'equipment l)  X (1-/equipment 2) X  (1 — /equipment 3) X ... X (1 — / PAC injection) X ... X (1 — /equipment n)] C^Q1

where
f PAC injection is the fraction of mercury removed by PAC injection.

If PAC injection  is simply  added to  existing  equipment and  the  removal  effects of the
existing equipment are combined into one term, then we can represent Eq. B-17 as

    /Total = 1 ~ [(1 ~ /existing equipment) x (1 - fpAC injection)]                           (Eq. B-18)

where
/"existing equipment is the removal fraction of the existing equipment.

In this effort, data from full-scale  tests of mercury reduction were used to formulate models
for mercury reduction from existing equipment and  from PAC injection.  Full-scale data for
mercury  removal by existing  equipment  are available from the ICR data. Full-scale testing
results for  mercury reduction from  PAC injection  are  available from  the Department of
Energy's field testing  programs  at  Southern Company's Gaston plant,  Wisconsin  Electric
Power Company's  Pleasant Prairie power  plant  (PPPP) and  at  PG&E National Generating
Group's Brayton Point and Salem Harbor plants.

B.5.2 Mercury Removal by Existing Equipment, fexisting equipment
Through  statistical analysis of the ICR data, EPRI  (2000)  shows that mercury reduction is a
function of both emission  control equipment configuration and a function of chlorine content
of the coal, and in  some cases a  function of the  SO2 emissions level from the boiler. EPRI
(2000)  provides algorithms  to  estimate  mercury  capture  as  a  function  of the  plant
configuration, the coal chlorine content, and the SO2 emissions. These algorithms are:
                                                                                     51

-------
Appendix B


Algorithm  1 (cold-side ESP):

   Existing equipment = Ci x In [(coal Cl, ppm)/(SO2, in Ib/MMBtu)] + C2

where
Ci and C2  = Algorithm 1 constants

Algorithm  2 (all other categories):
                                                                           (Eq. B-19)
 xisting equipment
             = Ci X In (C03l CI, ppm) + C2
                                                                           (Eq. B-20)
where
Ci and C2 = Algorithm 2 constants
Minimum and maximum allowable values are set for the results of Equations B-19 and B-20.
Values of Ci and C2, minimum and maximum are shown in the left columns in Table B-8 for
hot and cold side ESP operating conditions.

According to Eqs.  B-19 and B-20,  the predicted mercury reduction efficiencies for conditions
at Gaston  (Bustard et al., 2001; Durham et al., 2001; and Bustard et al., 2002),  Pleasant
Prairie power  plant (PPPP)  (Bustard et al., 2001;  Durham et al., 2001), Brayton  Point
(Durham et al., 2001)  and at Salem Harbor (Durham et al., 2001) are presented  in Table
B-8.

Table B-8.    Predicted Collection of Mercury by ESP according to Eqs. B-19 and B-20


ESPc
ESPh
Chlorine, % by weight in coal
Coal Chlorine, ppm
Flue Gas SO2, Ib/MMBtu
Ci
0.1233
0.0927
C2
-0.3885
-0.4024
Min
0.0%
0.0%
Max
55.0%
27.0%
Gaston
0.03
300
0.650
PPPP
0.0015
15
0.360
Brayton
Point
0.08
800
0.820
Salem
Harbor
0.03
300
0.500
Predicted Mercury Reduction

12.6%
7.1%
46.0%
40.0%

ESPc = cold-side ESP
ESPh = hot-side ESP
Source: EPRI (2000)

Gaston fires bituminous coal and has a hot-side ESP followed by an air preheater and then a
low-pressure pulse-jet FF for a COHPAC arrangement (Bustard et al., 2001; Durham et al.,
2001; and  Bustard et al., 2002). EPRI (2000) did not include algorithms for facilities with
this  arrangement. One  might expect that  the  mercury  reduction  without  PAC  might
                                                                                  52

-------
Appendix B
correspond approximately to the predicted  mercury reduction in Table B-8 for a hot-side
ESP  (ESPh). Under the conditions  at Gaston, predicted  mercury reduction equals 12.6%.
However, tests at Gaston showed negligible mercury removal. But considering the range of
variability in the  possible  results, the difference may be reasonable. However, this example
demonstrates that this algorithm will not give precise values, but  reasonable estimates.

At the Pleasant Prairie power plant (PPPP)  (Starns et al., 2002), a facility firing  PRB coal
with  a cold-side ESP (ESPc), the test results showed about 5% actual mercury removal from
existing equipment compared to about 7% as estimated by the algorithm of (EPRI 2000) for
the conditions at PPPP, and shown in Table B-8 (Bustard et al., 2001; Durham et al., 2001).
Therefore, the value estimated  by the algorithm is approximately in the same range. The  15
ppm chlorine content of the coal used at PPPP (which is much lower than that of most other
PRB  sites) probably contributes to the low removal by the existing equipment. With chlorine
content more typical of a  PRB  coal, around 100 ppm or more, the algorithm predicts that
mercury would be reduced by a greater amount.

For Brayton  Point, a facility firing bituminous coal and equipped with an ESPc, the algorithm
of EPRI (2000)  produces an estimated mercury reduction by existing  equipment of about
46% (see Table B-8) versus an  actual  measured removal efficiency of 32% (Durham et al.,
2001).  These  values, which  are  in about the  same range,  further illustrate  that the
algorithm  of EPRI (2000) is not exact, but approximate,  at estimating  mercury removal  by
existing equipment.

At Salem Harbor, a facility firing bituminous coal and equipped with an ESPc, 87% mercury
reduction  from existing equipment was measured  (Durham  et  al., 2001). This  measured
value compares to about 40% estimated from the algorithm of EPRI  (2000) as shown in
Figure B-l.  The significant difference can  be explained as follows:   First, Salem  Harbor
operates with fly ash loss on ignition (LOI) in the range of 25-35%. According to Bustard et
al. (2001),  this  fly ash  loss  is approximately  equivalent to a  carbon  loading of 60-84
Ib/MMacf in  the exhaust stream. This value is higher than a  typical plant's inject rate. So,
the carbon present  in the fly ash  has  likely contributed to a very high intrinsic capture of
mercury. Second, temperature  plays a role in  intrinsic  mercury capture.  Because Salem
Harbor  has  the ability to  increase its ESP  inlet temperature through operation of steam
heaters, parametric tests of intrinsic mercury removal as a function of temperature could  be
performed. Figure B-l shows the results of that testing under various firing conditions and
also  with data taken from another test using low  sulfur bituminous coal (not the baseline
coal). The trend is quite clear that increasing temperature reduces intrinsic mercury capture
from around 90% down to around  10%. Thus, mercury  absorption  by fly ash  is enhanced
when flue gas is cooled. Cooling the flue gas can enhances mercury uptake by flash.

However, when  PAC is injected, its  large capacity for mercury absorption allows the sorbent
to be operated at temperatures of 350 °F or higher. As such, spray cooling usually promotes
little or  nearly zero mercury absorption by PAC.
                                                                                 53

-------
Appendix B
Because a facility's  mercury reduction by existing equipment may be significantly different
from what the algorithm of EPRI (2000) determines, this algorithm should be used with care
and only for making approximate  estimates. As the measurements at Salem  Harbor clearly
indicate, LOI or other ash qualities and gas temperature can have a  very significant impact
on the level of mercury being  removed by existing equipment and may be worth including
as parameters in this algorithm at some future date when  more information  is available.
Therefore,  the algorithm of  Equation B-20 and  EPRI  (2000) may provide  reasonable
estimates  in  many  cases. But there is a  chance that actual  mercury capture may differ
significantly  from  what Equation  B-20   predicts.  For   any  specific  facility,  actual
measurements of mercury removal, if available,  should be used.
   100!

    90

    80

    70
 >
 SS  60
    40
    30
    20
    10
     270
                        0A
O17-19% LOI (45 Ib/M Macf)
X 20-24% LOI (55 Ib/M Macf)
A 25-29% LOI (68 Ib/M Macf)
• >30%LOI
H30-35% LOI, C1, High Load
A 21-27% LOI, C2, High Load
<>LS bitum coal
                 290
                             310         330
                           Temperature (degrees F)
                                                    350
                                                                370
Figure B-l.   Salem Harbor Mercury Removal without PAC Injection (Durham et al., 2001)
6.5.3  Mercury Reduction by PAC injection, fPAC injection
EPA (2000) has algorithms developed from pilot-scale data for mercury reduction on boilers
equipped  with  PAC  injection.  In  this  work,  we  have made  the  following  model
improvements:

1. The algorithms of EPA (2000)  were developed from pilot-scale  tests and characterize
   total  mercury reduction  from  both  PAC injection and  from existing equipment as a
   function of PAC injection concentration.  When using the algorithms of EPA (2000), it is
   necessary  to  have a different PAC injection algorithm for each type  of  equipment
   configuration,  including upstream equipment. These PAC injection algorithms may have
   to be updated as  new information  regarding mercury control from existing  equipment
                                                                                  54

-------
Appendix B
   becomes available. In the effort described in this paper, the mercury reduction from PAC
   injection was  isolated from that of the other equipment. Therefore, as we gain more
   information on reduction of mercury from equipment other than PAC injection, it should
   not be necessary to perform new regressions on the PAC injection models and  it will also
   be  possible to assess the fate  of mercury  in equipment that  is  either  upstream  or
   downstream of the PAC injection  system.
2. The  algorithms  of EPA  (2000) are of a  form where it is possible for Hg removal  to
   approach  100% by  injection  of very  high  concentrations of PAC. As will  be shown,
   experience at  PPPP showed that  under some circumstances it is not possible to achieve
   such extremely  high reduction of mercury emissions with PAC injection. Therefore, the
   algorithm for  mercury reduction from PAC  injection was  modified  to permit an upper
   limit to mercury removal that may  be less than 100%.
3. Because the algorithms of EPRI  (2000) are based on  the full-scale ICR  data,  it  is
   desirable  to  use them  to characterize  mercury  reduction from  existing equipment.
   However, it is  not possible  to integrate the algorithms of EPRI (2000) into  the approach
   used in EPA (2000).  By treating the mercury reduction from PAC injection independently
   from mercury reduction  from  other equipment,  it is possible to use the algorithms  of
   EPRI (2000) to characterize mercury reduction from existing equipment.

In the case  of  PPPP,  PAC injection  test results demonstrated that mercury  reduction
behaved asymptotically with a  maximum achievable mercury reduction from PAC that is well
below 100%, regardless of PAC injection  rate.  For this reason, the equation that is used  in
EPA (2000) to characterize the relationship between mercury reduction and  PAC injection

   % Hg reduction  = n. = 100  x ffrom PAC injection = 100-[A/(M+B)/VC]              (Eq. B-21)

where
M = the mass injection rate of  PAC (in  Ib/MMacf) and A, B, C are curve-fit constants
determined with available data.

   % Hg reduction  = n. = 100  x ffrom PAC injection = 100 x D-[A/(M + B)/VC]          (Eq. B-22)

where
D = the asymptotic fraction of  mercury reduction that is approached but is not achieved.

Constants A,  B, C, and D appearing in  Eq. 8 are  specified for a given plant configuration and
gas temperature.  At  this  time,  these constants can  only be  developed   for  full-scale
applications similar to the  conditions  where full-scale data  exists.  For some other boiler
configurations there is test data available  from  pilot-scale (Bustard et  al.,  2001)  tests that
can be used until  full-scale data becomes  available. For other configurations where neither
full-scale  nor  pilot-scale data  exists,  the constants can be  developed as data  becomes
available from future tests.  The constants A,  B, C and  D  used  in CUECost are listed in Table
B-9.
                                                                                  55

-------
Appendix B
Table B-9.    Values of Constants Used in the PAC Injection Eqs. B-21 and B-22
Coal
Bituminous
Bituminous
Bituminous
Bituminous
Bituminous
Bituminous
Subbituminous
Subbituminous
Subbituminous
Subbituminous
Subbituminous
Subbituminous
FF retrofit
in flight
in flight
in flight
FF
FF
FF
in flight
in flight
in flight
FF
FF
FF
PAC Capacity
EPAC
PAC
other
EPAC
PAC
other
EPAC
PAC
other
EPAC
PAC
other
A
0
-0.6647

0
1.6944

0.8837
3.308

0
-0.4318

B
1.207
2.1232

2.5007
-1.1267

0.4485
0.754

2.5007
1.9551

C
-0.2277
-0.0665

-2.2097
-0.0009

-0.575
-0.5925

-2.2097
-0.8937

D
100%
100%

100%
100%

100%
70%

100%
100%

6.5.4  PAC Injection Models Developed from Full-Scale Data
For the purpose of modeling, we are interested in estimating the  necessary  PAC injection
rate to achieve a specified level of mercury control. Therefore, we  developed  algorithms of
PAC injection  rate  as  a  function of desired  mercury  reduction by  PAC.  So, rather  than
plotting mercury reduction versus PAC injection  concentration, as is done  in Bustard et al.
(2001; 2002)  and Starns et al.  (2002),  we have reversed the axes from those shown in
these references.

In these tests (Bustard et al., 2001;  Bustard et al.,  2002; Starns, 2002)  several different
PAC sorbents were tested. The different PAC sorbents will be designated on the legends of
the figures. In  this effort, we did  not  have specific information  regarding  the  sorbent
properties of the tested sorbents. Therefore, since we did  not want to conjecture on the role
of particular sorbent properties on  mercury removal  performance, we  did  not evaluate
sorbent choice effects  except to determine whether  or not sorbent type has an effect on
performance under a particular condition.

Gaston
Figure B-2a shows  mercury collection results measured from an on-line mercury analyzer
during testing  conducted  at Gaston. Data are plotted as PAC injection concentration versus
mercury reduction  percent. Data include results obtained with several  different  sorbent
types (Bustard et al.,  2001).  Figure B-2a  also shows a  curve  developed in  the  form of
Equation  B-22  to  approximately  correspond  to  the results  achieved   at  Gaston.   The
coefficients  for the algorithm  are  listed  in Table B-10.  At  Gaston the choice of sorbent
appeared to have little  or no impact on performance.  At mercury removal rates in the range
                                                                                  56

-------
Appendix B
of 92-96%, mercury reduction is less sensitive to changes in PAC injection rate. Figure B-2b
shows the data for 92-96%  mercury  reduction  in greater detail. The enclosed  region  on
Figure B-2b includes  the estimated 95% confidence range for  these mercury reduction
data.5 Figure B-3, a plot of deviation of the predicted and  measured  PAC injection  rate,6
demonstrates this trend in another way.  For most mercury reduction  levels, the deviation
between model and actual PAC injection rates is only about 10%. For mercury reduction in
excess of 90%, however, the deviation is higher on a percentage basis.  While Figure B-3
shows that at  high removal  rates the  deviation between the model and  measured value
expressed as a percent of predicted level is -30% to +40%, in fact this range of values only
corresponds to a range of under ± 1 Ib/MMacf. The  high percentage  of the deviation  is due
to the actual values being relatively small at Gaston.
       4.5
       4.0 -
       3.5 -
=. 3.0 -
c
g
"TO  2.^.

§  2.0 -
o
<->  1.5 -j
O
tS  1.0
0)
I?
   0.5 H
       0.0
            R-squared of algorithm 68%
                95% confidence area for all data
                over 90% reduction of mercury.
           0   10   20   30   40   50   60   70   80   90   100  110
                              Percent Hg Removal
Data provided by Jean Bustard, ADA Environmental Services, September 16, 2002

Figure B-2a.  Gaston Testing
5 95% confidence range for Hg reduction and for PAC injection concentration are determined by ±2 standard
deviations from the arithmetic mean, with correction for sample size.
6 Calculated as (actual rate - predicted rate) / predicted rate and expressed in percent.
                                                                                      57

-------
Appendix B
Table B-10.   Coefficients for Curve Fit Algorithms
Plant
Gaston
PPPP
Brayton
Point
Algorithm

a
b
c
a
b
c
A
53
150
140
145
300
300
300
B
0.1
5
1
3
3
0
1.5
C
2
1
1
1
0.8
0.8
0.8
D
1.00
0.72
0.69
0.705
1.13
1.05
1.09
Sorbent Type
FGD, PAC 20
FGD
(14 micron
fraction)
FGL
Insul
FGD and FGD I
FGL
Insul
Note 1: Algorithms were developed for a specific plant and a specific sorbent.
Note 2: A, B, C, and D are coefficients for curve fit.
        0.5 -

        0.0
                    Includes the 95% confidence area for
                    all data over 90% reduction of
                    mercury.
           90
91
92
98
99   100
                            93    94    95    96    97
                                Percent Hg Removal

Data provided by Jean Bustard, ADA Environmental Services, September 16, 2002

Figure B-2b.  Gaston Testing
                                                                                       58

-------
Appendix B
     50%

     40% -

     30%
            deviation = (actual PAC rate minus predicted PAC rate) divided by predicted PAC rate
  2  20%
I 10%
£
Q.
®  0%
0)     ;
I -10% -
  I -20% -
  ra
  '>
  ° -30% -

    -40% -
                40
                        50
                                60
                                        70
                                                80
                                                        90
                                                               100
                         Percent Hg Reduction from PAC
Figure B-3.   Deviation of the Gaston PAC Algorithm
Pleasant Prairie Power Plant
Figure B-4 shows mercury collection  results measured from an  on-line mercury analyzer
during testing conducted at PPPP.  Data include results with several different sorbent types.7
Figure B-4 also shows a data  point for the total mercury removal as measured by the
Ontario  Hydro  method.  The  Ontario  Hydro  method shows  a somewhat  higher,  but
nevertheless a  similar,  mercury  removal as the  on-line  mercury analyzer used for the
testing. Two curves were developed in the form of  Equation 9 to correspond to  specific sets
of data and are plotted on Figure  B-4. The coefficients of these algorithms (A,  B, C, D) are
listed in Table B-10. Unlike the  results  at  Gaston,  at PPPP the choice of sorbent has  a
significant effect, possibly a  result of the fact that at Gaston there is a downstream fabric
filter, which  provides improved sorbent-gas contact, while at  PPPP all  of the mercury
absorption had to occur in the duct. Figure  B-5  is  a  plot of deviation of the predicted and
measured PAC injection rate.8 Had one algorithm been used for all of the sorbents, the
deviations would have been very  high in  some cases. Nevertheless there is enough scatter
in some of the data  that, even with different algorithms for each sorbent, deviation can be
on the order of 40%. Note that the one  data point with very high percent deviation (over
70%) was actually at a  low removal rate and the absolute difference  between the algorithm
results  and  measured results was quite  small.  For other plants  with conditions similar to
those at PPPP  (sub-bituminous  coal),  some  consideration should be made for  the sorbent
type.

7 Data provided by Jean Bustard, ADA Environmental Services, September 16, 2002.
8 Calculated as (actual rate - predicted rate) / predicted rate.
                                                                                     59

-------
Appendix B
          45

          40

          35

          30

          25

          20
I
o
o
I
'•B
0)
          15 -

          10 -

           5 -

           0
           R-squared of algorithms
           algorithm b and FGL
           99%
           algorithm c and Insul (7 micron)
           98%
           algorithm a and FGD (14 micron) data
           85%
             0
  *  FGD
  •  FGD (14 microns)
  A  FGL
  X  Insul (7 micron)
—CD— algorithm a
—O—algorithm b
^^"algorithm c
  +  Ontario Hydro
                                                              excluded from r-
                                                              squared calculation
                   20             40            60
                   % Hg removal from PAC injection
Data provided by Jean Bustard, ADA Environmental Services, September 16, 2002

Figure B-4.    PPPP Testing


              deviation = (actual PAC rate minus predicted PAC rate) divided by predicted PAC rate
    o
    0.
    I
    O
    1
    Q.
    •s



60%

40%
20%

0% -


20%
4CIOA -
the absolute difference was under




















X

0 35 4



0.5lb/MMacf




XFGD (14 microns), algorithm a



X Insul (7 micron)
i
i i
i i
i
i
v

X



>

A









<



A
A X V
I £—1 1 I /
0 45 50 55


X '
60X



6
X

1 1 1
1 1 1
1 1 1












5 7



                                Percent Hg Reduction from PAC

Figure B-5.    Deviation from the PPPP PAC Algorithm
                                                                                               60

-------
Appendix B
Bravton Point
Figure B-6 shows results  of  testing at Brayton  Point.  Data  include results with  several
different sorbent types. 7 Figure B-6 also shows curves developed in the form of Equation 9
that correspond to specific sorbent types. The coefficients of these algorithms are listed  in
Table B-10. Like PPPP and unlike the results at Gaston, at  Brayton  Point the  choice  of
sorbent appears to have a significant effect. When considered with the PPPP results,  this set
of results provides further evidence that the  sorbent choice  may have a greater impact
when a downstream fabric filter is  not installed.  While  good correlation is possible for all
data with algorithm c (R2 =  77%), improved correlation was possible by using different
correlations for different sorbents, as demonstrated by the higher correlations of algorithms
a and  b with  the sorbents indicated on Figure B-6.  Figure  B-7 shows  that the predictive
accuracy of the algorithms across a broad mercury removal  range does not change much.
However, Figure B-7 shows that improved accuracy will result  if the algorithm is tailored  to
the sorbent.  For algorithm c,  maximum  deviation ranges from -60%  to  +50%.  But, by
tailoring the algorithm  to the sorbent, as shown for Alt Sorbent  1 with algorithm b and FGD1
with algorithm a, the deviation  is reduced sharply.
        30
      c-
      u
      ro
25  -
      5 20 --
      o
R-squared of algorithm
algorithm c and all data
77%
algorithm b and Alt. Sorbent 1 data
86%
algorithm a and FGD, FGD1 & FGD (SOS
off)   85%
      ~  15
      u
      o
      O
      o
      =  5
10
 *  FGD1
 •  Alt. Sorbent 1
 A  FGD (SOS off)
 X  FGD
-O— algorithm a
-O—algorithm b
^"algorithm c
                     20         40        60
                        % Hg removal from PAC injection
                                                    80
                                                              100
Figure B-6.   Brayton Point Testing
                                                                                    61

-------
Appendix B
             deviation = (actual PAC rate minus predicted PAC rate) divided by predicted PAC rate


(1)
•s
o
0.
S
1
Q.
•5
C

-------
Appendix B	



•  The space velocity of the catalyst

•  The temperature of the reaction

•  The concentration of ammonia

•  The age of the catalyst

•  The concentration of HCI in the flue gas stream.

Bustard et al. (2001) showed  that, in tests on a laboratory combustor, mercury oxidation
without a  catalyst was enhanced  with higher Cl concentration (higher HCI  in the flue gas)
and that oxidation increased with  residence time and at lower temperatures, as shown  in
Figure B-8. Hocquel et al. (2002) also describe the results of laboratory tests of oxidation  of
mercury across  SCR  catalysts.   The  results  of these  tests,  shown   in  Figure  B-9,
demonstrated that the  catalyst significantly increased the amount of mercury that oxidized
to mercuric chloride.

In Richardson et al. (2002), tests of mercury oxidation by SCR catalyst  were  conducted
using simulated  flue gas and slip-streams from actual units. Results showed similar trends
for both simulated flue gas and slip-streams from actual units with the exception that the
effect of  increasing space velocity  appeared  somewhat more significant with the slip-
streams. Multiple  catalyst types  were tested  with similar results  obtained. According  to
Bustard et al. (2001), at space velocities in the range of 400 h"1, mercury oxidation was  in
the range of about 80% to 90%  for fresh  catalyst.  However, the oxidation  rate falls off
quickly with increased space velocity; oxidation might be in the range of 30-80%  at a space
velocity of 4000  h"1. The wide range of oxidation performance at a space velocity of 4000 h"1
is  the result  of the influence of other factors  - temperature, ammonia and possibly other
effects.

As shown  in Figure B-10, Richardson et al. (2002)  showed that oxidation of mercury across
fresh  SCR catalyst was  highest at temperatures in the  range of 550 °F and lowest  in the
range of 800 °F, consistent with  the fact  that oxidation of mercury to mercuric chloride
occurs mostly at lower temperatures.
                                                                                   63

-------
Appendix B
     100
                                                              1200
                       2345

                           Retention time [s]
                                                              400
Figure B-8.   Mercury Oxidation without a Catalyst as a Function of Residence Time, Gas
              Temperature, and HCI Content (Hocquel et al., 2002)
  i1 —        35-cells
  Is
  « 2   8Q    plate-type
  c o
CD

'S
0

I
(O
        60
        40
        20
             22-ceils
             without catalyst
                                    f
        510       540      570
                                    600       630

                                  Temperature [K]
                                                      660
                                                              690
                                                                       720
Figure B-9.   Mercury Oxidation across SCR Catalysts and without SCR Catalyst (Hocquel et
              al., 2002)
                                                                                        64

-------
Appendix B
                                     *- 7WF; o»mNH3    I
                                     O- TOO'F:
                                    -*— «ST:
                                    «• 7eOf,!)pp«>NH3 (ESP hint)
                        aOOQ   19000
                        Sp.ce Veloclly (hr")
Figure B-10.  Oxidation of Mercury across C-l SCR Catalyst in PRB-derived Flue Gas
             (Richardson et al., 2002)
The  presence of ammonia,  which is the NOX reducing reagent  normally  used  in SCR
systems, was shown by  Richardson  et al. (2002)  to  inhibit  the  oxidation of elemental
mercury. This effect  is most pronounced  with  catalyst that  has been exposed to boiler
exhaust gases for a number of months. As shown in Figure B-ll, mercury oxidation  without
ammonia present remained between 80% and 90% after 4200  hours (about six months) of
exposure to boiler gases  at  a space  velocity of 1450 IT1. When exposed to 300  ppm of
ammonia, fresh  catalyst continued to oxidize 80-90% of the elemental mercury.  However,
after 4200 hours of exposure no oxidation was measured across the  catalyst when ammonia
was present.
          wo    i,0DQ   i.soo   2,000   2,500
                         Tim* (hrtj
                                   3,0DQ    3,500   4,000
Figure B-ll.  Effect of Flue Gas Exposure Time on C-l SCR Catalyst Oxidation of Elemental
             Mercury: 700 °F and Space Velocity of 1,450 h'1 (Richardson et al., 2002)
                                                                                   65

-------
Appendix B
Oxidation of elemental mercury to mercuric chloride across an SCR catalyst, therefore, may
be a function of: space  velocity, temperature, ammonia concentration, and  catalyst  life.
Other factors, such as fly ash characteristics, are also believed to play a role.

Bustard et  al. (2002) describe the  results of a program that evaluated mercury oxidation
across full-scale utility boiler SCR systems. A summary of the results of these tests is shown
in the first four entries in Table B-ll. Testing was  performed at four coal-fired electric utility
plants  having catalyst age ranging from around 2500 hours to about 8000 hours. One plant
fired subbituminous  coal and three other  plants fired  eastern  bituminous  coal. The  test
results showed high  levels of mercury  oxidation  in two of the three plants  firing eastern
bituminous coal and  insignificant oxidation at the other two  plants (one firing bituminous
coal  and the other  subbituminous).  However, for both of the plants  where  little or no
mercury oxidation was measured (SI and S3) over 85% of the  mercury at the particle
control  device  inlet  was already  in  the  non-elemental  (oxidized) form.  For the  one
bituminous coal fired plant with low  mercury oxidation (S3), over 50% of the mercury at the
SCR inlet was already in the oxidized form. At the plant firing subbituminous coal (SI),
mercury oxidation was fairly low. But, due to the high carbon in  that plant's fly ash, the
elemental  mercury  was  apparently adsorbed onto the  ash, resulting in high  particulate
mercury levels. Finally, in contrast with the studies of Hocquel et al. (2002) and Richardson
et al. (2002), ammonia appeared to have little or no effect on  mercury oxidation on these
actual, full-scale facilities.

Subsequent tests  on  sister units at those plants and at other plants are shown in the second
four entries in Table B-ll. All of the  units fired bituminous coal and showed that mercury
oxidation was generally enhanced to  high levels of oxidized mercury at the  SCR outlet. In
each case where  a scrubber was installed the mercury removal was high.  For the unit with
an ESP and no scrubber,  mercury removal was not improved by the SCR.

At this point in time, the understanding of the effects of SCR catalyst on mercury oxidation
is fairly limited. Clearly,  mercury oxidation is substantial under some conditions,  but  less
significant under others.  However, significant mercury oxidation by SCR catalyst appears to
occur  with  bituminous  coal  and oxidation  may  be less certain  with  PRB  coals.  Where
bituminous coal  was fired  with  an SCR and  an  FGD, high levels  of  mercury  removal
generally occurred.

Default values for mercury control input parameters are shown in Table B-12.
                                                                                   66

-------
Appendix B
Table B-ll.    Summary of Results from Full-Scale SCR Mercury Oxidation Tests (Bustard et al., 2001)

Power Plant
S1.650MW
gross
Cyclone, ESP

S2, 1360 MW
gross, Wall,
ESP+FGD
(MEL)


S3, 750 MW
gross,
Tangential, ESP

S4, 704 MW
gross, Cyclone,
scrubber

684 MW gross,
Wall, ESP+FGD


800 MW gross,
Tangential, ESP

1360MW
gross, Wall,
ESP+FGD
(MEL)

Cyclone, Lime
venturi scrubber


Catalyst Vendor,
Type,
SV (h-1)
Cormetech
Honeycomb
1800

Westinghouse
Phtp

nZD

KWH
Honeycomb
-3930

Cormetech
Honeycomb
2275

Halder-Topsoe
"corrugated"
-3750"?


Cormetech
Honeycomb
3800

C&l Ceramics
Plate
2125

Honeycomb
22/5

Catalyst
Age

8000 h

3.5
months



1 ozone
season


1 ozone


2 months

2 seas
2 layers
repl. after
1st season

2 ozone
seasons


2 ozone
seasons


Coal
Type

PRB

OH Bit



PA Bit
blend


KYBit


PAAA/V Bit


KYAA/V Bit


OH Bit


KYBit


Sin
Coal
(%)

0.2

3.9



1.7


2.9


3.6


1


3.9


3.1


Cl in Coal
(ppm)

<60

1640



1150


360


470


1000


520


750 bypass
250 w/SCR


NH3 Slip
(ppm)

2*

0.1



0.8


0.2


0.3


0.1


0.5


0.1


S03
ppm

0.4*

33*



24


16#


10.6


14


30


12


Cl
ppm

1.5*

108*



81 #


19

Not
Measu
red
(NM)

NM


NM


NM


Oxidized mercury
content,
SCR in/out
Unit 2: 8% -18%; net
10%; small increase;
1 OH sample
48% -91%; net 43%;
significant increase;
2 OH samples
No effect of alkali
injection (Unit 1)
55% -65%; net 10%;
small increase; 2 OH
samples
35% -61%; net 26%; for
2nd coal in sister unit; 2
OH samples
9% -80%; net 71%;
significant increase; 2
OH samples

Oxidation to 80+%; Net
+38% increase


Oxidation to 80+%; Net
+21% increase


Oxidation to 80+%; Net
+33% increase

Oxidation to 60+%; Net
+20% increase; "More"
oxidation if 1 outlier data
not used

Oxidized mercury
content, w/o and w/
SCR, PM inlet
5% -8%; net 3%;
small increase;
1 OH sample each

73% -97%; net 24%;
significant increase;
2 OH samples each

77% -67%; net -10%;
possible filter effects
due to reactive ash
Not tested in 2nd
coal/sister unit
56% -87%; net 31%;
significant increase; 2
OH samples each
Oxidation to 95%; Net
+15%
(using data from sister
unit w/o SCR)
Oxidation to 89%' Net
-0%
(using data from sister
unit w/o SCR)

Oxidation to 95+%;
Did not test w/o SCR

Oxidation to 90+%;
Net +39%
Cl in coal changed
between tests

Total Hg Removal
across PM+FGD, w/o
and w/ SCR
60% -65%; net 5%;
small increase- within
experimental error; 1
OH sample each
51% -88%; net 37%;
significant increase;
FGD removed 94% of
oxidized Hg; 2 OH
samples each
16% -13%; net -3%;
within experimental
error; 2 OH samples
each
Not tested in 2nd
coal/sister unit
46% -90%; net 44%;
significant increase; 2
OH samples each

Significant increase to
90+%; net +40%


No effect; actually lower
Hg removal in ESP (-
6% vs 23%)


-85% Hg removal; Did
not test w/o SCR


Significant increase to
90+%; net 47%

Fffort nf MH,
onHg
Oxidation
(SCR in/out)

No effect

Not tested



Small neg.
effect.
Not tested in 2nd
coal/sister unit

Small negative
effect


Not tested


Not tested


Not tested


Not tested

NH3, Cl, S03 - Sampled at SCR outlet unless noted (* - ESP outlet, # - Particulate control inlet)
                                                                                                                          -67

-------
Appendix B
Table B-12.   Default Values for Mercury Control Input Parameters
Description
Units
Range
Default
Sorbent Injection Inputs
Hg GEMS (0=no, l=yes)
Hg Reduction Required from Coal
Sorbent Type, 1 = EPAC, 2=PAC, 3=other
Maximum Temperature before Spray Cooling
Sorbent Recycle Used?
Spray Cooling Desired?
EPAC Cost (delivered cost of brominated PAC)
PAC Cost (delivered)
Other Sorbent Cost (delivered)
Does sorbent adversely impact fly ash sales?
(0=no, l=yes)
Before Sorbent Injection,
Fly Ash Sold (1) or Disposed of (2)
Revenue from Fly Ash Sales
Dry Waste Disposal Cost
Retrofit Factor
Maintenance Factors (% of Installed Cost)
Process Contingency, % of process capital
General Facilities (% of Installed Cost)
Engineering Fees (% of Installed Cost)
Project Contingency
Duration of Project (years)
integer
percent

deg F
yes/no
yes/no
$/ton
$/ton
$/ton
integer
1 or 2
$/ton
$/ton

%
%
%
%
%
integer
0 or 1


up to 325 F





0 or 1

0 to 35
1 to 25







1
80.0%
2
325
no
no
$1,500
$1,000
$1,000
1
2
$6.00
$6
1.30
5%
5%
5%
10%
15%
1
PJFF downstream of PAC Inputs
PJFFto COHPAC (i.e., TOXECON), 0=no, l=yes
Cost of Bags, installed ($/bag)
Estimated Number of Bags/MW
Average bag life
Pressure Drop
Outlet Emissions
Retrofit Difficulty Factor
Process Contingency, % of process capital
General Facilities, % of Process Capital
Engineering, Home Office, etc.
% of Process Capital and General Facilities
Project Contingency, % of Process Capital and
Gen Facilities
Owner's Overhead and costs
Inventory Capital and Prepaid Royalties, etc.
Maintenance, % of process capital and excluding bags
Period of construction, yrs
0 or 1
$/bag
integer
years
iwc
Ib/MMBtu

%
% of process
capital
%


% of process
capital

















1
$80
20
5
8
0.012
1.30
5%
5.0%
10.0%
15%
5.0%
1.0%
1%
1
                                                                                  68

-------
Appendix B
6.5.6  Conclusions
Correlations for mercury removal from coal-fired power plants have been  developed  in the
CUECost model, incorporating information on mercury removal from existing equipment that
was  developed from the  ICR data in  EPRI  (2000). CUECost also  incorporates  mercury
removal from injection of PAC, as developed from full-scale demonstrations of PAC  injection
where  data are available. Algorithms developed  with  CUECost  should  be  continuously
updated and modified as more information  becomes available on experience with  mercury
removal.

The following summarize some important findings that influence modeling mercury removal:

•  The CUECost workbook that permits isolation of the effects of different air pollution control
   equipment  on the fate of  mercury will  facilitate  modeling  combined  effects with PAC
   injection over a wide range of boiler configurations and scenarios without the need for new
   regressions of PAC injection test data. Impact of a  specific piece  of equipment can  be
   estimated with models best suited for that equipment.

•  PAC injection followed  by a fabric filter results in  much lower injection  concentrations
   being necessary for a given level of mercury reduction than for PAC injection followed by a
   cold-side ESP. Thus, economic  modeling may show that in some cases the additional
   capital cost of a fabric  filter may be justified  by reduced  operating  costs associated with
   PAC consumption.

•  Sorbent selection appears  to have little effect on performance when PAC injection  is
   followed by a fabric filter. But sorbent choice appears to have  a significant effect when
   PAC injection is followed by an ESP.

•  As  demonstrated  by the Salem Harbor  test results,  LOI and temperature can have a
   significant effect on the  mercury  removal by existing equipment. For this reason, the
   correlations of EPRI (2000), which do  not include these effects, do not always provide an
   accurate indication of mercury removal by existing equipment.

•  In some cases PAC injection without a downstream fabric filter may not be  able to achieve
   very  high  mercury  removal  rates  of  90%  or more, regardless  of  PAC  injection
   concentration.
B.6    CO2 CONTROL DESIGN CRITERIA

In a  monoethanolamine (MEA)-based CO2 control system, a continuous scrubbing system is
used to separate CO2  from the flue  gas. The system  consists of an MEA island and a
compressor island. The temperature of flue gas coming out the wet scrubber system is often
higher  than the temperature required by the  MEA process. Therefore, in order for CO2 to be
efficiently  scrubbed  and to reduce solvent losses, the flue gas must be cooled down  below
50 °C.  As  SO2 reacts with MEA, the concentration of SO2 prior to  the absorber should be low


	69

-------
Appendix B	


(<10 ppm) to reduce the losses and degradation of MEA by SO2.  NaOH scrubbing is often
required before the absorber.

Flue gas then flows through the absorber where CO2  binds to MEA. The CO2-rich solution
leaves  the absorber and  passes  through  the  heat  exchanger and  finally  enters  the
regenerator where CO2 is released from MEA by external heat from steam supply or natural
gas burning. The hot CO2 lean solvent then  flows back to the heat exchangers where it is
cooled, and then is sent  back to the absorber. To supplement the  MEA losses, fresh MEA is
added. Eqs. B-23 and B-24 show this cycle.

CO2 absorption:

   2R-NH2 +  CO2 (g) -> R-NH3++R-NH-COO"                                  (Eq. B-23)

MEA regeneration:

   R-NH-COO" + R-NH3+  (heat) -> CO2+2R-NH2                              (Eq. B-24)

The regeneration of MEA consumes a great  deal of energy when the MEA concentration is
low in  the solvent. Inhibitors are  therefore  added to  the  solvent to increase  the MEA
concentration. In the worksheet, a  typical MEA  concentration is 30% with the addition of
inhibitors.

In sorbent injection (SI)  to capture  CO2, a continuous scrubbing system is used  to separate
CO2 from the  flue gas. The system consists of a sorbent absorption and regeneration  island
and a compressor island. The flue gas coming out of the wet scrubber system  is  cooled to
relatively low  temperatures  (30 to 35 °C) for the easy capture of CO2 by the sorbent. When
SO2 reacts with  sorbent to degrade  the sorbent, the concentration of SO2  prior to  the
absorber should  be lowered,  in general <10  ppm, to  minimize  sorbent consumption. As
such, additional scrubbing is required  before the absorber. Flue gas then flows through the
absorber where CO2 binds to sorbents. The CO2-rich sorbent leaves the absorber and passes
through the heat exchanger in the  regenerator where CO2 is released from sorbent  under
the assistance of external heat.

In the CAP, CO2 is absorbed in an ammoniated solution at 32 °F. Cooling the flue gas to
such a  low temperature is a  necessary step within the process. As the result of flue gas
cooling, moisture in the flue gas is also condensed, leading to less actual flue gas flow  rate
through the booster fan.  In the absorption process, the formation of aqueous ammonium
carbonate  [(NH4)2CO3] with the precipitation of ammonium  bicarbonate [(NH4)HCO3] solids
at low temperatures optimizes the energy demand, improves CO2 removal efficiency, and
reduces ammonia slip. The formation of ammonium bicarbonate solids is a reversible
reaction. With heat in the regenerator, the ammonium bicarbonate  solids are dissolved with
eventual evolution of ammonia, water and CO2 gases. The CO2 stream leaves the
regeneration vessel from the CAP at a  higher pressure than the other two CO2 processes

	70

-------
Appendix B
(MEA and SI) which results in fewer stages of downstream CO2 compression. The ammonia
and water reaction products are stripped and condensed from the resulting gas stream for
reuse as reagent and flue gas wash solvent (Sherrick, B. 2008).

Gas exiting the regenerator must be compressed and dehydrated to accommodate transport
and disposal. Moist CO2 from  the CO2 regenerator's reflux drum enters the compressor at
21 °C (69 °F) and nominally 160 kPa (23 psi). CO2 is compressed  in a six-stage integrally
geared compressor. Intercoolers  between stages cool the gas using chilled water from the
plants' cooling tower. After exiting the compressor, and presumably a final heat exchanger,
the CO2 is dried to <  20 ppm water in a triethylene glycol (TEG)  dehydrator. Dry gas exiting
the dehydrator is at 15.27 MPa (2215  psi) and  51 °C (124 °F) (DOE 2007).
REFERENCES

Bustard,  J., Durham, M.,  Lindsey, C., Starns, T., Baldrey, K., Martin, C., Schlager,  R.,
Sjostrom, S., Slye,  R., Renninger,  S., Monroe, L, Miller,  R., Chang, R., 2001. "Full-Scale
Evaluation of Mercury Control with  Sorbent Injection and COHPAC at Alabama Power E.G.,
Gaston",  DOE-EPRI-U.S. EPA-A&WMA Power Plant Air Pollutant Control "Mega" Symposium,
August 20-23, 2000, Chicago, IL.

Bustard,  J., Durham, M.,  Lindsey, C., Starns, T., Baldrey, K., Martin, C., Schlager,  R.,
Sjostrom, S., Slye,  R., Renninger,  S., Monroe, L., Miller, R.,  Ramsey, C., 2002. "Gaston
Demonstrates Substantial Mercury Removal with Sorbent Injection", Power Engineering, vol.
106, no.  11.

DOE,  2003, National Energy Technology Laboratory Mercury Field Evaluation - PG&E NEG
Salem Harbor Station  -  Unit 1, Project No. 00-7002-76-10,  Field Evaluation  Summary
Report, January 2003.

DOE/NETL. 2007. Cost and  Performance Baseline for Fossil Energy  Plants ( DOE/NETL-
2007/1281).

Durham,  M.,  Bustard, J., Schlager,  R., Martin, C.,  Johnson, S.,  Renninger, S., 2001. "Field
Test Program to Develop Comprehensive Design,  Operating  Cost Data for  Mercury Control
Systems   on  Non-Scrubbed  Coal-Fired  Boilers", AWMA  94th Annual  Conference  and
Exhibition, Orlando,  FL, June 24-28  2001.

EPA, 1996, "Cost-effectiveness of Low-NOx Burner Technology  Applied to Phase I, Group 1
Boilers,"  prepared by Acurex Environmental  Corporation for EPA Acid Rain Division. This
report is  available to the public from EPA's Office  of Air and Radiation, Acid Rain Division,
Washington, DC 20460 (202-564-9085).

EPA, 2000, Performance and  Cost of Mercury Emission control  Technology Applications on
Electric Utility Boilers, EPA-600/R-00-083.

	71

-------
Appendix B
EPRI, 2000, An Assessment of Mercury Emissions from U.S. Coal Fired Power Plants, EPRI,
Palo Alto, CA.

Gundappa, M., L.  Gideon, and E. Soderberg, 1995, "Integrated Air Pollution Control System
(IAPCS), version  5.0, Volume2:  Technical  Documentation,  Final" EPA, Air and  Energy
Engineering Research Laboratory, Research  Triangle Park,  NC,  EPA-600/R-95-169b (NTIS
PB96-157391).

Hocquel, M., Unterberger, S., Hein, K., Bock, J., 2002, "Behavior of Mercury in Different Gas
Cleaning Stages", International Conference on Air Quality, September 9-12, 2002, Crystal
City, VA.

Richardson, C., Machalek,  T.,  Miller, S., Dene,  C., and Chang, R.,  2002,  "Effect of  NOX
Control  Processes on Mercury Speciation in Utility Flue Gas", International Conference on Air
Quality, September 9-12, 2002, Crystal  City, VA.

Sherrick, B.; Hammond,  M.; Spitznogle, G.; Murashin, D.; Black, S.; Cage, M.; CCS  with
Alstom's Chilled Ammonia Process at AEP's  Mountaineer Plant,  Present in the Power Plant
Mega Symposium. Baltimore, MD.  2008.

Starns,  T., Bustard,  J., Durham,  M., Lindsey, C., Martin, C., Schlager, R., Donnelly, B.,
Sjostrom,  S.,  Harrington,  P.,  Haythornthwaite,  S.,  Johnson, R.,  Morris, E.,  Chang,  R.,
Renninger, S., 2002, "Full-Scale Test of Mercury  Control with Sorbent Injection  and an ESP
at Wisconsin Electric's Pleasant Prairie  Power Plant", AWMA  95th Annual Conference  and
Exhibition, Baltimore, June 23-27 2002.
                                                                                  72

-------
Appendix C
C.I   GENERAL PLANT DESIGN CRITERIA

The  plant design and  operating default  values  provided  below  were taken from  the
criteria  established  by EPA's Integrated  Air  Pollution Control System (IAPCS) model
(Gundappa et al., 1995) and were generally replaced with IPM/IECM values (Table C-l).
The user can override any default value as long as the value input is within the range of
the parameter stated on the  worksheet. Table C-2 lists  the coal  analysis embedded in
Sheet 11.0 Constant_CC  (Coal Analysis Library).  More information for coal analysis  can
be found from DOE coal bank and database (http://datamine.ei.psu.edu/index.php).
                                                                                 73

-------
Appendix C
Table C-l.    Snapshot for a Specific Plant and Its Default Parameters
Plant Information
Cost Basis -Year
(For Power Generation Estimation only)
Location - State
Power Generation Technologies
General Plant Factors
Gross Plant output
Net Plant Output
Plant Heat Rate
Plant Capacity Factor
Coal Type
Price of Coal
Other Operating Information
Percent Excess Air in Boiler
Uncontrolled NOX from Boiler
Air Heater Inleakage
Air Heater Outlet Gas Temperature
Inlet Air Temperature
Ambient Absolute Pressure
Pressure After Air Heater
Moisture in Air
Ash Split:
Fly Ash
Conversion of SO2 to SO3
Units




MW
MW
Btu/kWh
%

$/MMBtu

%

%
°F
°F
in. Hg
in. H2O
Ib/lb dry air

%

Range

All States


500-800
500-750

40-90%














Default
2005
PA
1

580
500
10,500
65%
5
2.05

120%
algorithm
12%
300
80
29.4
-12
0.013

80%
1.0%
                                                                                  74

-------
Appendix C
Table C-2.    Coal Analysis Library

Go Back to Input Sheet

COAL ANALYSIS LIBRARY

Index Number
Coal Name
Coal Cost







$/MMBtu
PROXIMATE ANALYSIS (ASTM, as rec'd)
Moisture - Enter below in Ultimate Analysis
Volatile Matter
Fixed Carbon
Ash - Enter below in Ulti


COAL ULTIMATE ANALYSIS (AS
Moisture
Carbon
Hydrogen
Nitrogen
Chlorine
Sulfur
Ash
Oxygen
TOTAL
Mercury
Modified Mott Spooner HHV (B

COAL ASH ANALYSIS (ASTM, a
SiO2
AI2O3
TiO2
Fe2O3
CaO
MgO
Na2O
K20
P2O5
SO3
Other Unaccounted for
TOTAL

wt%
wt%
mate Analysis


aTM, as rec'd)
wt%
wt%
wt%
wt%
wt%
wt%
wt%
wt%
wt%
mg/kg
Btu/lb

s rec'd)
wt%
wt%
wt%
wt%
wt%
wt%
wt%
wt%
wt%
wt%
wt%
wt%

Coal 1, Wyoming
PRB: 8,227 Btu,
0.37% S, 5.32%
ash




1
Wyoming PRB
1.50


31.39
33.05

100.00


30.24
48.18
3.31
0.70
0.003
0.37
5.32
11.87
99.99
0.10
8,227


35.51
17.11
1.26
6.07
26.67
5.30
1.68
2.87
0.97
1.56
1.00
100.00
PRB
Coal 2,
Armstrong,
PA: 13,100
Btu, 2.6% S,
9.1% ash




2
Armstrong, PA
1.50


36.20
48.70

100.00


6.00
71.55
4.88
1.40
0.000
2.60
9.10
4.47
100.00
0.10
13,100


46.92
21.00
2.40
20.20
3.25
2.65
0.90
0.30
0.00
1.38
1.00
100.00
Bituminous
Coal 3,
Jefferson,
OH:
11,922
Btu, 3.43%
S, 13% ash




3
efferson, Ol
1.50


37.20
44.80

100.00


5.00
65.72
4.53
1.21
0.100
3.43
13.00
7.01
100.00
0.10
11,922


51.35
30.00
1.80
9.00
4.50
2.00
0.40
0.20
0.16
0.59
0.00
100.00
Bituminous
Coal 4, Logan,
WV: 12,058
Btu, 0.89% S,
16.6% ash




4
Logan, WV
1.50


35.40
43.00

100.00


5.00
65.99
4.75
0.70
0.100
0.89
16.60
5.97
100.00
0.10
12,058


50.68
29.00
1.70
9.00
5.50
1.00
0.40
0.90
0.60
1.22
0.00
100.00
Bituminous
Coal 5, No. 6
Illinois:
10,100 Btu,
4% S, 16%
ash




5
No. 6 Illinois
1.50


33.00
39.00

100.00


12.00
55.35
4.00
1.08
0.100
4.00
16.00
7.47
100.00
0.10
10,100


50.82
19.06
0.83
20.00
3.43
3.07
0.60
0.37
0.17
1.22
0.43
100.00
Bituminous
Coal 6,
Rosebud, MT:
8,789 Btu,
0.56% S,
8.15% ash




6
Rosebud, MT
1.50


36.40
30.30

100.05


25.20
51.52
3.29
0.69
0.100
0.56
8.15
10.49
100.00
0.10
8,789


27.00
19.00
1.08
9.00
18.50
2.40
2.80
0.45
0.42
18.85
0.50
100.00
Subbituminous
Coal 7, Lignite,
ND: 7,500 Btu,
0.94% S, 5.9%
ash




7
Lignite, ND
1.50


42.00
20.10

100.00


32.00
45.06
2.80
1.50
0.100
0.94
5.90
11.70
100.00
0.10
7,500


29.80
10.00
0.40
9.00
21.40
10.50
4.40
0.49
0.00
14.01
0.00
100.00
Lignite
Coal 8, DOE HS:
12,676 Btu, 3%
S, 9% ash




8
DOE HS
1.50


40.40
47.50

100.00


3.10
69.82
5.00
1.26
0.120
3.00
9.00
8.70
100.00
0.10
12,676


29.00
17.00
0.74
36.00
6.50
0.83
0.20
1.20
0.22
7.30
1.01
100.00
Bituminous
Coal 9, DOE
LS: 14,175
Btu, 0.6% S,
3.8% ash




9
DOE LS
1.50


44.00
50.00

100.00


2.20
78.48
5.50
1.30
0.120
0.60
3.80
8.00
100.00
0.10
14,175


51.00
30.00
1.50
5.60
4.20
0.76
1.40
0.40
1.80
2.60
0.74
100.00
Bituminous
Coal 10, DOE
PRB: 8,304
Btu, 0.48% S,
6.4% ash




10
DOE PRB
1.50


30.79
32.41

100.00


30.40
47.85
3.40
0.62
0.003
0.48
6.40
10.82
99.97
0.07
8,304


31.60
15.30
1.10
4.60
22.80
4.70
1.30
0.40
0.80
16.60
0.80
100.00
PRB
Coal 11, K
Fuel: 11,718
Btu, 0.38% S,
6.42% ash




11
KFuel
1.50


40.20
45.50

99.62


7.50
66.70
4.80
1.00
0.030
0.38
6.42
13.20
100.03
0.04
11,718


28.40
17.30
1.60
6.00
23.50
4.00
1.40
0.27
2.43
13.63
1.47
100.00
PRB
Coal 12, Med
S: 11,570
Btu, 1.5% S,
8.15% ash




12
Med S
1.50


36.19
43.80

100.00


11.86
65.12
4.22
1.33
0.380
1.50
8.15
7.44
100.00
0.10
11,570


51.35
30.00
1.80
9.00
4.50
2.00
0.40
0.20
0.16
0.59
0.00
100.00
Bituminous
                                                                                                                          75

-------
Appendix C	



C.2    ECONOMIC CRITERIA

Economic inputs for CUECost workbook calculations are shown in Table C-3.

Table C-3.     Economic Inputs
Description
Cost Basis, Year Dollars
Service Life (Levelization Period, years)
Sales Tax Rate
Escalation/Inflation Adjustment (GDP or Chem Index*)
Units
date
integer
%

Range



Cor D
Economic Factors During Construction Period
Construction Labor Rate
Prime Contractor's Markup
Current Inflation Rate
Current Escalation Rates
After Tax Discount Rate (Current $'s)
Capital Carrying Charges
First-year Carrying Charge (Current $'s)
Levelized Carrying Charge (Constant $'s)
Non-Carrying Expense (O&M)
Levelizing Factor (L30) (Constant $'s)
Variable Cost Factors
Operating Labor Rate (include benefit)
Power Cost
Steam Cost
Demineralized Water
Makeup Water
$/h
%
%
%
%

%
%



$/h
Mills/kWh
$/1000 Ibs
$/lb
$/1000 Ib






Calculator






Default
2008
30
6%
GDP

$35
3%
2%
3%
9%

16%
8%

1.48

$25.0
60
3.5
$0.0030
$0.05
* Chem Index  =Chemical Engineering Magazine - Plant Index updated in each issue. This is the user
input value for the year selected. The model divides the input value by the January 1998 index value
to determine the escalation factor that is needed.
                                                                                     76

-------
Appendix D
D.I   FGD COST ALGORITHM DEVELOPMENT

The cost algorithms associated with the flue gas desulfurization processes were developed
based on historical data  and new equipment quotations received  by Raytheon during 1998
for some of the major equipment items. Algorithm development began with derivations from
Raytheon's in-house historical database. These data sets were then modified by adding  the
additional data points from the new budgetary quotations, and then deriving  new equations
to represent the costs for equipment areas and for specific large pieces of equipment.

Performance data were  sent to multiple vendors for one or two  of the major equipment
components identified in each cost area. These vendor contacts included a minimum of four
vendors in each case.  Responses to cost data requests were received from  a minimum of
one and  normally three or more of the vendors solicited.  Where vendor responses were
limited due to refusals  or  delayed responses, additional data sources were  obtained from
recent projects to add to the data base of cost information for specific components. The cost
data requests were made over the expected range of component sizes that could be used in
the CUECost estimating workbook. LSFO capital cost algorithms are shown in Table D-l.

Table D-l.    Variable and Constant Parameters for Wet FGD Cost Algorithm

LSFO Process
Equipment
ID Fans and
Ductwork
Chimney
Support Equipment
x =
MW
Chimney acfm
Chimney acfm
MW
Equation
(x x 1000 x A x
x^B)/1.3
(A x x + B)/1.3
(A x x + B)/1.3
A=
4456.5
1.6225
3.4736
B =
-0.6442
3,000,000
5,000,000
=(0.0003 x x^3-1.0667 x x^2 + 1993.8 x
x+1177674) x 1.22
                                                                                77

-------
Appendix D	


LSFO Process Equipment  includes the  Reagent Handling and  Preparation,  SO2  Control
System, and the Byproduct Handling. The capital costs for these equipments are described
in Appendix B.I.

LSD  capital cost algorithms are shown in Table D-2.

Table D-2.    Parameters for LSD Cost Algorithms

Reagent Handling and
Preparation
SO2 Control System
Byproduct Handling
Flue Gas Handling and
ID Fans
Chimney Modification
Support Equipment
X=
pph lime
Inlet gas acfm
pph byproduct
(if upstream of
existing ESP)
If new ESP or FF
acfm
KW
MW
Equation
(Ax+B)/1.3
(Ax+B)/1.3
(Ax+B)/1.3
A=
136.84
9.262
31.124
B=
3,000,000
5,000,000
2,000,000
Determined by ESP and FF Worksheets
(Ax+B)/1.3
(Ax+B)/1.3
2.9232
3.4
3.00E+06
0
(-1.211 x x^2+2704.2 x x +1354716.2) x 1.22
The capital costs for LSD Process Equipments are described in Appendix B.2.

D.2   SELECTIVE CATALYTIC REDUCTION

D.2.1 Performance Parameters
The key operating parameters that affect the performance and, consequently, the capital
and operating costs of SCR systems include the allowable NH3 slip emissions, the space
velocity, the NOX reduction efficiency, and  the  NH3/NOX molar ratio.  For SCR systems
these parameters  are interrelated,  and their values  depend on  the type  of  SCR
application (high-dust or tail-end)  and the desired  performance levels. Ammonia slip
emissions  are  controlled  by the SCR system design.  Typically SCR catalyst suppliers
provide  a  guarantee of  2  ppm over the  catalyst  life. Since the 2 ppm  NH3  slip  is
guaranteed at the end of  the catalyst's life, the initial NH3 slip emissions  will be very low
(<1  ppm).  Ammonia  slip  is  not taken  into  consideration  in the catalyst  volume
determination. The  space velocity  is the primary parameter used to  specify  catalyst
volume. If the user does not input a value for space velocity, CUECost calculates it based
on the NOX reduction efficiency and the NH3/NOX molar ratio (molecular weight of NOX =
molecular  weight of NO2):
                                                                                 78

-------
Appendix D	


Space Velocity

   SV = 6131.06 / 3 x (n)-°-241 x (NH3:NOX ratio)'2'306                          (Eq. D-l)

where
SV = space velocity, 1/h
n = NOX reduction efficiency, fraction
NH3:NOX ratio = stoichiometric ratio of NH3 to NOX.

The NOX reduction efficiency (n) and molar ratio of NH3 to  NOX (NH3/NOX ratio) are user-
specific  input values. The gross catalyst volume and  NH3 injection rate are determined from
the following equations taken from IAPCS sources (Gundappa et al., 1995):

Ammonia Injection Rate

   NH3  = 3.702 x  10"4 x NH3:NOX ratio x BSIZE x HTR x NOX                  (Eq. D-2)

where
NH3 = ammonia injection rate, Ib/h
BSIZE = boiler size, MW
HTR = net heat rate, Btu/kWh
NOX = inlet NOX emissions, Ib/MMBtu
CV = gross catalyst volume, ft3
Q = flue gas volume flow rate, SCFH.

Gross Catalyst Volume

   CV = Q/SV                                                             (Eq. D-3)

where
SV= space velocity.

D.2.2 Capital Costs
CUECost estimates capital costs for  reactor housing, initial catalyst,  ammonia storage and
injection system, flue gas handling including ductwork  and induced draft fan modifications,
air preheater modifications and miscellaneous direct costs, including ash handling and water
treatment additions. CUECost equations for SCR direct capital costs are shown  below.

For all  items except flue gas handling, cost  algorithms are based  on  regression models
developed for the Integrated Environmental Control  Model (IECM) (Frey and Rubin, 1994).
The IECM regression models were developed from cost data for 12 coal-fired power plants
(Robie   and  Ireland,  1991).  The flue gas  handling  cost  algorithm  is taken from the
Integrated  Air Pollution  Control System  (IAPCS) model, version 5.0  (Gundappa  et al.,
1995).  Costs derived from the IAPCS equations for flue gas handling were  found  to be on

	79

-------
Appendix D
the same order of magnitude as costs reported by the Acid Rain Division study (EPA, 1997;
EPA, 1998). IECM equations (Frey and Rubin,  1994) were used for the other direct capital
cost items because they are based on more current cost data than IAPCS (Gundappa et al.,
1995). Installation  costs  for  items such as  structural  supports, foundations, concrete,
earthwork are accounted for in the cost data  used to develop the IECM and IAPCS equations
and, therefore,  are  not  a separate item in CUECost.  Plant  cost indices from Chemical
Engineering Magazine are included in the equations to  update direct capital costs. Direct
capital costs for hot-side SCR are shown in Table  D-3.

Table D-3.    Direct Capital Costs for Hot-side SCR (Installed equipment costs)
 Reactor Housing
 DC r= 18.65 x Nr,totx (CV/ Nr,tot)^0.489 x 1000 x RF x PCI/ 357.3

 Ammonia Storage and Injection System
 DC NH3 = 50.8 x (NH3)/V0.482 x 1000 x RF x PCI / 357.3

 Flue Gas Handling: Ductwork and Fans
 DC fgh = 143.66 x[Gfg x (750+460) / (70+460)^0.694 x RF x PCI / 314.0

 Air Preheater Modifications
 DC aph,mod=  1370 x Nt,aph x  (UAt,aph/ 4.4 / 10^67 Nt,aph)^0.8 x 1000 x RF x  PCI / 357.3

 Miscellaneous Direct Costs
 DC misc = [100 + 300 x (BSIZE/ 550)^0.6] x 1000 x RF x PCI / 357.3
where
Gfg =  flue gas volumetric flow rate for SCR ductwork, scfm
Nr,tot = Number of SCR reactors
Nt,aPh  = total number of air preheaters
RF =  retrofit factor
PCI = chemical engineering plant cost index from Chemical Engineering Magazine
    = 388 for  1998 dollars, 314.0 for 1982 dollars and 357.3 for IECM base year dollars
UAt,aph =  product of universal heat transfer coefficient and heat exchanger surface area

      =   Qaph   , Btu/°R

q aph = heat transfer  =     Flue gas scfm x 60 x 7.9 x (Tfiue aas. out -1 fiue aas. m)	
                                         0.7302 x 530
dTLM, aph = log-mean temperature difference
       = 	LL flue aas. in^ Ta|r. out ) " (Tf|ue gas, out ^_L air. inJ	
                 flue gas, in ~ ' air, out ) /(.' flue gas, out ~  ' air, inJJ
                                                                                  80

-------
Appendix D
The  flue gas  inlet temperature (Tf|Ue gas, m) and the outlet temperature (Tflue gas, out) are
assumed to be the respective typical values of 725 and 600 °F.

Capital  costs  for  instruments  and controls,  sales  tax  and  freight are calculated  from
percentages of the equipment cost subtotal. The equipment cost subtotal is the sum of the
equations listed  above. For  instruments and  controls and freight, the  respective  default
percentages are  2% and 5%. The sales tax rate is a user input value. The total direct cost is
determined by applying the retrofit factor to the capital equipment cost subtotal, which is
the sum of the equipment costs listed above as well as instruments and controls, sales tax
and  freight.  The  retrofit factor is a  user input value  that  ranges from  one for new
applications to three for the most difficult retrofit cases. Equations for indirect capital  costs
are given in Table D-4.

Table D-4.     Indirect Capital Costs for Hot-side SCR
 General Facilities =  Total Direct  Cost with  Retrofit  x General Facilities (%  of installed
 cost)
 Engineering fees = Total Direct Cost with Retrofit x Engineering Fees (% of installed cost)
 Contingency = Total  Direct Cost with Retrofit x Contingency (% of installed cost)
 Total Plant Investment = Sum of Total Direct Cost with Retrofit, General Facilities,
 Engineering fees, Contingency taking into account allowance for funds during construction
 Preproduction = Total Plant Investment x 0.02 + One month fixed operating costs  +
                           One month variable operating costs (at full capacity)
 Initial Ammonia  (60 days) = NH3 x 24 x CF x 60 x UCNH3/ 2000
 Initial Catalyst = CV  x UCCAT
where
CF = capacity factor, fraction
UCNH3 = ammonia cost rate, $/ton
UCcAT = unit cost of catalyst, $/ft3
CV = gross catalyst volume, ft3
NH3= Ammonia injection rate,  Ib/h.

D.2.3  Operating and Maintenance Costs
Operating and maintenance costs include NH3, catalyst replacement and disposal, electricity,
steam,  labor and  maintenance costs.  The  CUECost  operating  and  maintenance cost
equations presented below are based on IAPCS equations (Gundappa et al.,  1995).  IAPCS
equations were selected  instead of IECM equations  (Frey and  Rubin, 1994)  for operating
and maintenance costs because the level of detail required for IAPCS input parameters was
closer to that of other CUECost inputs. Additionally, the  parameters affecting operation and
maintenance costs  are not  likely to  have changed significantly since the IAPCS equations
were  developed.  With the  exception of catalyst  replacement  costs, the equations from

	81

-------
Appendix D
IAPCS were derived from data  reported by  TVA for the high-dust  system (Maxwell and
Humphries,  1985).  Annual catalyst replacement costs are based on the catalyst life.  For
example, if the catalyst life is 3 years, then one-third of the catalyst  is  replaced each year.
The  catalyst disposal cost reflects the  cost  of  disposing of the spent catalyst. Catalyst
disposal  is  typically  included  in  the  purchase  cost  of the catalyst. As  a  result,  the
recommended default for this  line item  is zero. However, an equation  is included to allow
the user to  estimate a disposal  cost, if  applicable. A typical value of 48 Ib/cubic foot was
used  for the catalyst density to calculate the mass of the  spent catalyst. Operation and
maintenance cost equations for SCR are shown Table  D-5.

Table D-5.    Operating and Maintenance Cost Equations for SCR ($/year)
 Ammonia Cost = (8,760/2,000) x (NH3 x CF x UCNH3)

 Catalyst Replacement Cost = CV/N x UCCAT

 Catalyst Disposal Cost = 48 x Catalyst Replacement Cost x
                           2,000 x UCCAT

 Electricity = (-545,133 + S.SOlxG) x (CF / 0.628)  x UCELEc

 Steam = (-14.91 + 33.29 x NH3 xCF) x UCSTEAM

 Operating Labor = (1,341 + 5.363 x BSIZE) x UCOL

 Maintenance Costs = Maintenance (%) x TPC
where
BSIZE= boiler size, MWe
CF= capacity factor, fraction
CV= gross catalyst volume, ft3
G = flue gas flow rate, acfm
N = overall catalyst life, years
Maintenance (%) = annual maintenance cost as a percent of total plant cost
TPC = total direct and indirect capital costs, $
UCCAT= catalyst cost, $/ft3
UCELEc = electricity rate, $/kWh
UCoL = operating labor wage, $/person-h
UCNH3= ammonia cost rate, $/ton
       = steam rate, $/MMBtu
       = solid waste disposal rate, $/ton
NH3= Ammonia injection rate, Ib/h.
                                                                                  82

-------
Appendix D
D.2.4  CUECost Validation
Total plant costs and operating and maintenance costs estimated by CUECost algorithms
were compared to current cost data  developed and validated by EPA's ARD. Cost and design
information for four applications of SCR on various boiler types, boiler sizes and coals was
taken from a 1996 Acid Rain Division (ARD) study (EPA,  1996)  (Tables D-6 and D-7). The
design  information  for these SCR  applications  was  used to evaluate  equations  from
CUECost. Total plant capital costs  include the  reactor housing, initial catalyst, ammonia
storage and injection system, flue gas handling including ductwork and induced draft fan
modifications,  air preheater  modifications  and  miscellaneous  direct costs,  including ash
handling  and  water treatment additions.  Other direct  capital  costs  for taxes, freight,
instruments and  controls and initial  inventory  are included  in the comparison of direct
capital  costs. The total  plant cost includes direct  costs listed above as well as indirect capital
costs for engineering, general facilities and contingencies. Chemical engineering plant cost
indices from Chemical Engineering Magazine were used to  normalize costs in consistent year
dollars.

The percent difference between ARD study costs and the  CUECost estimates for total plant
costs ranged from -4% to +8% for the cases evaluated.  Operation and maintenance costs
estimated by CUECost are  23 to 31% lower than those estimated by the ARD study. The
largest difference appears to be the catalyst replacement cost.
                                                                                  83

-------
Appendix D
Table D-6.    CUECost with Acid Rain Division Study Design for SCR (1990 dollars)*





Selective Catalytic Reduction
Cyclone-Fired




Midwestern
Wet-Bottom
Vertical-
Fired
Wall-
Fired
Eastern Bituminous
Boiler Size (MW)
150
400
100
259
CUECost with Acid Rain Division Design Parameters
Input Parameters Taken from Acid Rain Division Study
NOX Reduction Efficiency fraction
NH3/NOX Molar Ratio fraction
Inlet NOX Ibs/MMBtu
Design Parameters Calculated by CUECost
Ammonia Injection Rate Ib/hr
Gross Catalyst Volume ft3
Flue Gas at Air Heater Outlet SCFM
0.50
0.50
1.4

340
1,385
273,571
Capital Costs Using Acid Rain Division Design Parameters ($
Reactor Housing and
Ammonia Handling and
Flue Gas Hand 1 ing :Ductwork and Fans
Air Preheater Modifications
Misc. Other Direct Capital Costs
Initial Catalyst
Total Capital Equipment Cost
Freight, Sales Tax and Inst. & Controls
Total Plant Cost (TPC)
TPC ($/kW)
% Difference from Acid Rain Division Study
1,188
1,097
2,238
481
309
485
5,798
691
8,590
57.3
4%
0.50
0.50
1.3

884
3,883
766,250
1000)
1,967
1,739
4,574
1,096
453
1,359
11,188
1,278
16,353
40.9
0%
0.50
0.50
0.95

155
935
182,280

981
752
1,689
348
270
327
4,367
525
6,489
64.9
8%
0.50
0.51
0.92

399
2,485
482,464

1,582
1,185
3,318
757
379
870
8,090
939
11,884
45.9
-4%
O&M Costs usina Acid Rain Division Desian Parameters f$1000/vear)
Ammonia
Catalyst Replacement
Catalyst Disposal
Electricity
High-dust SCR Steam
Maintenance
O&M Total
% Difference from Acid Rain Division Study
157
162 '
0.10
112
34
122
586
-23%
407
453
0.28
366
88
225
1,539
-24%
72
109
0.07
66
15
92
354
-31%.
184
290
0.18
220
40
165
899
-30%
  Source: EPA, 1997; EPA, 1998
                                                                                  84

-------
Appendix D
Table D-7.    Acid Rain Division Study: SCR Applications*
Selective Catalytic Reduction
Cyclone-Fired
Midwestern Bituminous
Wet-Bottom
Vertical- Wall-Fired
Fired
Eastern Bituminous
Boiler Size (MW)
150 400
100
259
Acid Rain Division Costs and Design Parameters
Design Parameters from Acid Rain Division
NOX Reduction Efficiency fraction
NH3/NOX Molar Ratio fraction
Inlet NOX Ibs/MMBtu
Ammonia Injection Rate Ib/hr
Gross Catalyst Volume ft3
Flue Gas at Air Heater Outlet SCFM
Acid Rain Division Capital Costs {$ 1000)
SCR Reactors/Ammonia Storage
Piping/Ductwork
Electrical/PLC
Draft Fans
Platform/Insulation/Enclosure
Air Preheater Modifications
Total Capital Equipment Cost
Total Plant Cost (TPC)
TPC ($/kW)
Acid Rain Division O&M Costs ($ 1000/year)
Power Consumption
Ammonia Consumption
Catalyst Consumption
General Maintenance

0.50 0.50
0.50 0.50
1.4 1.3
339 882
3,690 10,020
292,924 821,164

3,180 7,040
945 1,600
450 720
1,065 1,760
180 440
285 520
6,105 12,080
8,242 16,308
55.05.0 40.8

56 200
156 408
430 1,168
123 246

0.50
0.50
0.95
155
2,571
191,279

2,150
860
460
650
100
250
4,470
6,035
60.4

55
72
300
89

0.50
0.51
0.92
398
6,675
498,215

4,921
1,528
803
1,166
285
466
9,169
12,378
47.8

140
184
779
183
 O&M Total
* Source: EPA, 1997; EPA, 1998
764
2,023
516
1,286
                                                                                     85

-------
Appendix D	


D.3   SELECTIVE NONCATALYTIC REDUCTION

D.3.1 Performance Parameters
The CUECost workbook allows the user to select either urea [CO(NH2)2] or ammonia (NH3)
as the SNCR reagent. The user  is asked to specify the NOX  reduction efficiency and the
stoichiometric ratio of reagent to  NOX (molecular weight of NOX = molecular weight of NO2).
The  NH3 and CO(NH2)2  injection  rates in pounds of  pure  reagent  per  hour are then
calculated based on the stoichiometric ratio, inlet NOX and boiler heat input:

Urea Injection Rate

   Urea = 6.5 x 10"4 x UREA:NOX ratio x BSIZE x HTR x NOX                  (Eq. D-4)

Ammonia Injection Rate

   NH3 = 3.702 x 10"4 x  NH3:NOX ratio x BSIZE x HTR x NOX                  (Eq. D-5)

where
Urea = CO(NH2)2 injection rate, Ib/h
NH3 = NH3 injection rate,  Ib/h
BSIZE = boiler size, MWe
HTR  = net heat rate,  Btu/kWh
NH3:NOX ratio = stoichiometric ratio of NH3to NOX
NOX = inlet NOX emissions, Ib/MMBtu
UREA:NOX ratio = normalized stoichiometric ratio of CO(NH2)2 to NOX (i.e., moles of reagent
   nitrogen to moles of uncontrolled NOX).

For the CO(NH2)2-based SNCR process, the user may select to use wall  injectors, lances, or
both. Wall injectors are nozzles installed in the upper furnace waterwalls. In-furnace lances
protrude into the upper furnace or convective pass and  allow  better mixing of the reagent
with  the flue gas. In-furnace lances require  either  an air-  or  water-cooling circulation
system. Additionally, since the  location of the temperature  window  changes with load,
multiple levels  of injectors and/or lances will  be required for  effective  NOX reduction over
the operating load range of the boiler. If the user specifies a number of injector lance levels,
but inputs zero  for the number  of injectors or lances, CUECost calculates  the number of
injectors or lances using the equations  below:

   NI = (8.6  +  0.03 x BSIZE - 0.013 x Red) x NIL                              (Eq. D-6)

   NL = (2 + 0.013 x BSIZE) x NLL                                           (Eq. D-7)

where
NI =  number  of wall injectors
Red = NOX reduction efficiency, %

	86

-------
Appendix D
NIL = number of injector levels
ML = number of lances
BSIZE = boiler size, MW
NLL = number of lance levels.

If the user enters values for both wall injectors and lances, then costs include both lances
and wall injectors.  If wall injectors are to be used alone, then the user enters zero for both
the number of lance levels and the number of lances. Similarly, if lances  are to be used
alone, the user enters zero for both the number of injector levels and wall injectors. For the
NH3-based SNCR process, the user can choose either steam or air as the atomizing medium.
Based on the user's choice, an annual operating cost for steam and/or electricity usage is
calculated.

D.3.2 Capital Costs
The main equipment areas in the battery limits for SNCR include the reagent receiving area,
storage tanks, and  recirculation system; the injection system,  including  injectors,  pumps,
valves, piping,  and  distribution  modules; the control system; and  air compressors.  In
addition,  NH3-based  SNCR systems  use vaporizers to vaporize the NH3 prior to injection.
The capital  costs are estimated  using modified equations from IAPCS v.5.0 (Gundappa,
1995).  The IAPCS  equations were modified to incorporate  the extensive  current cost data
developed and validated by EPA's ARD. IAPCS is a  computer model developed for the EPA
NRMRL-RTP (formerly the Air and Energy Engineering  Research Laboratory) to estimate
costs and performance  for emission control  systems applied to coal-fired  utility  boilers.
IAPCS was developed in the 1980s and has been updated over the years. Documentation for
the latest revision  to IAPCS  (Gundappa, 1995),  completed in  1995, presents equations in
1982 dollars, with  adjustments  made using  cost indices to normalize  costs to other-year
dollars.

Cost and  design  information was available  in  a  1996  ARD study (EPA,  1996)  for  six
applications of urea-based (50%  solution) SNCRs on various boiler types  and sizes. The
design  information for these cases  was input to  the IAPCS model, and the capital cost
estimates from IAPCS were compared to the ARD study estimates (EPA, 1996). The ratio of
the ARD  study costs to costs calculated using IAPCS equations was determined for each
case. The ratios were then averaged, and the resulting average ratio was incorporated into
each IAPCS  capital cost equation.  The ratios were determined for Total Direct Capital Cost.
Itemization  of equipment  in major equipment areas varied between IAPCS and the ARD
study so  that unique ratios could  not be established for each equipment  area. As a result,
the same ratio was added to each equipment cost equation. This approach  was applied for
both urea-  and ammonia-based SNCR, because  the capital costs do not vary significantly
between the two processes (EPA, 1996). The algorithms for SNCR  direct capital costs are
presented below. Plant cost indices from Chemical Engineering Magazine are included in the
equations to update  direct capital costs. Direct capital costs for SNCR are  shown in  Table
D-8.
                                                                                 87

-------
Appendix D	


Table D-8.    Direct Capital Costs For SNCR (Installed Equipment Costs)

Urea-Based SNCR Process

Urea Storage & Handling  = 38,143 x (Urea/8.7)0-417 x 0.915 x PCI/ 357.6

Urea Injection = (117,809 + 10,477 x NI +  53,111 x NL) x 0.915 x PCI/ 357.6

Misc.  = (96,082 +106 x BSIZE + 898 x  NI + 2,433 x NL)  x 0.915  x PCI / 357.6

Air Heater Modifications = 11.2 x (acfm)0-772 x 0.915 x PCI / 357.6

Ammonia-Based SNCR Process

Ammonia Storage = 63,822 x (BSIZE)0-6 x 0.655 x PCI /  357.6

Handling, Injection, Controls

Air Heater Modifications = 11.2 x (acfm)0-772 x 0.655 x PCI / 357.6	

where
Urea = urea injection rate, Ib/h
NH3 = ammonia injection rate, Ib/h
NI = number of wall injectors
NL = number of lances
acfm  = flue gas volumetric flow rate at air heater inlet, ft3/min.
PCI = chemical engineering plant cost index from Chemical Engineering Magazine
    = 388 for 1998 dollars and 357.6 for 1990 dollars.
Capital costs for instruments and controls, sales tax and freight are assumed to be included
in the algorithms listed above because they are updated with ARD costs that include these
items. The total direct cost with retrofit is determined by applying the retrofit factor to the
capital equipment cost subtotal, which  is the sum of the equipment costs listed above. The
retrofit factor is a user input value that ranges from one for new applications to three for
the most difficult retrofit cases. Equations for indirect capital costs are given in Table D-9.
                                                                                  88

-------
Appendix D
Table D-9.    Indirect Capital Costs for SNCR
 General Facilities = Total Direct Cost with Retrofit x General Facilities (% of installed
 cost)

 Engineering fees = Total Direct Cost with Retrofit x Engineering Fees (% of installed cost)

 Contingency = Total Direct Cost with Retrofit x Contingency (% of installed cost)

 Total  Plant Investment =  Sum of Total  Direct  Cost  with Retrofit, General  Facilities,
 Engineering fees, Contingency taking into account allowance for funds during construction

 Preoroduction =  Total Plant Investment x 0.02+ One Month Fixed Operating  Costs +
  One Month Variable Operating Costs (at full capacity)

 Initial Ammonia  (60 days) = NH3 x 24 x CF x 60 x UCNH3 /2000

 Initial Urea (60 davs)  = NH3 x 24 x CF x 60 x UCUREA /2000
where
CF = capacity factor, fraction
UCNH3 = ammonia cost rate, $/ton
       = CO(NH2)2 cost rate, $/ton.
D.3.3  Operating and Maintenance Costs
The  operating  and  maintenance  cost equations  for  SNCR,  taken  from  IAPCS  v.5.0
(Gundappa, 1995), are shown below. Equations for the urea- and ammonia-based processes
are shown separately  in the table. As in  IAPCS, the operating  labor costs are  based on
2 person-hours required  per 8-hour shift of operation. The default for maintenance labor
and materials costs is 4% of the total direct and indirect capital cost. The annual cost of the
reagent is the major operating cost item for the process and is calculated as the product of
the reagent usage in tons/year and the cost in  dollars per ton of pure  reagent. Electricity,
water,  and  steam requirements are  based on  vendor  information. The increase  in the
energy  requirement  for steam  or  air atomization  is  included  in  the  operating  cost
algorithms. Annual operating and maintenance costs for SNCR are shown in Table D-10.
                                                                                  89

-------
Appendix D	


Table D-10.   Annual Operating and Maintenance Costs for SNCR

Urea-Based SNCR Process ($/vear)

Operating and Supervisory Labor = 0.25 x 8,760 x UC0L

Maintenance Labor and Materials = Maintenance (%) x TPC

Reagent Requirement = Urea x 8760 x CF/2,000 x  UCUREA

Electricity Requirement =  (5.97 + 0.29 x NI + 0.87 x NL) x 8760x CF x UCELEC

Water Requirement = (1.0 x NI + 2.5  x NL) x 60 x 8760 x CF/1,000 x UCH2o

Ammonia-Based SNCR Process ($/vear)

Operating and Supervisory Labor Requirement = 0.25 x 8,760 x UC0L

Maintenance Labor and Materials Cost  = Maintenance (%) x TPC

Reagent Requirement = NH3 x 8760 x CF/2,000 x UCNH3

Steam Requirement  (for steam atomization) = BSIZE x 99.2 x 8,760 x CF/1,000 x UCSTEAM

Electricity Requirement (for steam atomization) = BSIZE x 0.12  x 8,760 x CF x UCELEC

Electricity Requirement (for air atomization) = BSIZE x 4.23 x 8,760 x CF x UCELEC

where
TPC = total direct and indirect capital costs, $ (see Table 3-1)
UCELEc = electricity rate, $/kWh
UCH2o = unit cost water, $/l,000 gallon
UCNH3 = NH3 cost rate, $/ton
       = steam rate, $/MMBtu
       = CO(NH2)2 cost rate, $/ton.
                                                                                90

-------
Appendix D
D.3.4  CUECost Validation
To determine how successfully the  IAPCS algorithms were modified  using the ARD data,
CUECost was run using the design information upon which the ARD cases were based. Total
plant costs and operating and  maintenance costs estimated using CUECost were compared
to the costs developed by ARD (EPA, 1996). Results from this comparison  are presented in
Tables  D-ll and D-12.

Total plant costs presented below include  reagent storage and  handling, injection  system,
air  heater  modifications, and  miscellaneous direct capital  costs.  Total  plant costs also
include  indirect  capital  costs  such  as engineering, general facilities and  contingencies.
Chemical Engineering Magazine plant cost indices were  used to report  costs in  consistent
year dollars.

The percent difference between ARD study costs and the CUECost estimates for total plant
costs ranged from -15% to +7% for the cases evaluated. Operation and maintenance costs
estimated  by CUECost are 0  to 12% greater than those  estimated by the  ARD study (EPA,
1996).

D.4    NATURAL GAS REBURNING

D.4.1  Performance Parameters
The fraction of boiler heat input contributed by natural gas (reburn fraction) depends on the
desired NOX removal  efficiency. The  relationship between  the  reburn fraction and NOX
reduction efficiency, taken from IAPCS v.5.0, is based on vendor information  and review of
NGR performance data:

   RBFRAC = (NOxEFF - 0.48)/0.86                                           (Eq. D-8)

where
RBFRAC = boiler heat  input contributed  by natural gas (fraction)
NOX EFF =  NOX reduction efficiency (fraction).

The relationship applies for  NOX reduction  efficiencies from  55 to 65% and  yields reburn
fractions from 0.08 to  0.20. In CUECost,  these are the  valid  input ranges for the NOX
removal efficiency and reburn  fraction.  If the user inputs both parameters within the valid
ranges, the input values are used for cost calculations. If only one parameter is  outside of
the valid range, that parameter is calculated using the other parameter. If both input values
are outside of  the  valid ranges,  a  default  reburn fraction  of 0.15  is  used  with  a
corresponding 61% NOX removal efficiency.
                                                                                 91

-------
Appendix D
Table D-ll.   CUECost with Acid Rain Division Study Cases for SNCR (1990 dollars)*






Cyclone-!


Midwest
Bitumin

Selective Noncatalytic Reduction 150
Ired Wet-Bottom
Vertical- Wall-Fired
Fired
ern Eastern
ous Bituminous
Boiler Size (MW)
400 100 259
CUECost with Acid Rain Division Design Parameters
Default Input Parameters
Number of Injectors integer 1 8
Number of Lances integer 0
Urea/NOX Stoichiometric Ratio fraction 0.90
36 18 36
000
0.90 0.90 0.90
Desisn Parameters calculated by CUECost
Urea Injection Rate Ib/hr 2, 1 39
Air Heater Inlet ACFM ACFM 611,455 1
Capital Costs
Urea Storage
using Acid Rain Division Design Parameters ($ 1000)
& Handling 451
Urea Injection 364
Controls/Miscellaneous 152
Air Heater Modifications 39 1
Total Capital
Equipment Cost 1 ,358
Total Plant Cost (TPC) 1,833
TPC($/kW) 12.2
% Difference from Acid Rain Division Cost Study -7
5,297 973 2,439
712,635 407,633 1,078,935

658 324 476
589 364 589
203 146 185
865 286 605
2,314 1,120 1,855
3,124 1,513 2,505
7.81 15.1 9.67
7 -15 6
O&M Costs using Acid Rain Division Design Parameters ($1000/vear)
Operating and Supervisory Labor 46
Maintenance
Reagent
Electricity
Water
O&M Total
% Difference
Labor and Materials 27
1,102
3
2
1,181
from Acid Rain Division Cost Study 8
46 46 46
47 23 38
2,730 501 1,257
535
525
2,832 575 1,350
0 12 4
  Source: EPA, 1996
                                                                                 92

-------
Appendix D
Table D-12.   Acid Rain Division Study: SNCR Applications (1990 dollars)*
Selective Noncatalytic Reduction
Cyclone-Fired
Midwestern
Bituminous
Wet-I
Vertical-
Fired
ottom
Wall-Fired
Eastern Bituminous
Boiler Size (MW)
150
400
100
259
Acid Rain Division Costs and Design Parameters
Design Parameters from Acid Rain Division
Number of Injectors
Number of Lances
Urea/NOX Stoichiometric
Economizer Outlet
Ratio
integer 1 8
integer 0
fraction 0.90
ACFM 648,029
36 18
0 0
0.90 0.90
1,812,657 416,969
36
0
0.90
1,085,858
 Acid Rain Division Capital Costs f$ 10001
 Tanks, Pumps & Injectors
 Pipes/Valves/Heat Tracing
 Electrica!/PLC
 Platform/Insulation/Enclosure
 Total Capital Equipment Cost
 Total Plant Cost (TPC)
                           TPC ($/kW)
 Acid Rain Division Q&M Costs ($ 1 OOP/year)
 Coal Consumption
 Power consumption
 Ash Disposal
 General Maintenance
 Urea Consumption
 Water Consumption
 O&M Total

* Source: EPA, 1996
615
510
180
135
1,000
680
160
280
480
530
180
90
673
725
155
155
1,440

1,980
 13.2
1,094
2,120

2,920
  7.3
2,824
1,280

1,770
 17.7
 512
1,709

2,357
  9.1
74
19
3
31
961
7
198
59
7
48
2,494
18
36
7
1
27
437
3
97
31
3
37
1,119
7
1,295
                                                                                              93

-------
Appendix D
D.4.2  Capital Costs
Direct  capital cost equations for NGR are  presented  below. The first equation  includes the
installed  costs  of gas injectors,  OFA ports, and related  equipment. This equation was
developed  by  modifying  the IAPCS equation  for  the  same equipment  area  [Cost =
6,644,400  x (BSIZE/500)0'214]  to  reflect  recent cost estimates from an ARD  study (EPA,
1996). The ARD  study  estimated  NGR  costs for four different boiler sizes. To bring the
IAPCS  model up  to  date, the constant  in the  equation  (6,644,400)  was replaced  with a
variable.  Then the equation was set equal to each of the  ARD cost cases, and the equation
was solved to determine a new constant. The results showed that the new "constant" varied
linearly with boiler size. Therefore,  the constant in the IAPCS equation was replaced with an
expression that is a function of boiler size (BSIZE x 3238 +  1504675).

The second equation shown  includes the costs associated with  piping  natural gas to the
boiler from the metering station located at the utility plant fence line. The equation was
derived by fitting an exponential curve to ARD costs for natural gas piping. Plant cost indices
from Chemical Engineering Magazine are included in the  equations to update direct capital
costs. Direct capital costs for NGR are shown in Table D-13.

Table D-13.  Direct Capital Costs for NGR (Installed equipment cost)

Fuel  injectors, overfire air ports, associated piping, valves, windbox,  and control dampers
                                 " '17e    PCI
                           500 )     357.6
                                                                PCI
Gas pipeline from fence line to boiler = 372xexp (2.64xlO"3x BSIZE)>
                                                               357.6
where
BSIZE = Boiler capacity (MW)
PCI = chemical engineering plant cost index from Chemical Engineering Magazine
    = 388 for  1998 dollars and 357.6 for 1990 dollars.

Capital costs for instruments and controls, sales tax and freight are assumed to  be included
in the algorithms listed above  because they are updated with ARD costs that include these
items. The total  direct cost with retrofit is determined by applying the retrofit factor to the
capital equipment cost subtotal, which  is the sum of the equipment costs listed  above. The
retrofit factor is a user input value that ranges from 1 for new applications to 3 for the most
difficult retrofit cases. Equations for indirect capital  costs are given in Table D-14.
                                                                                  94

-------
Appendix D
Table D-14.   Indirect Capital Costs for NGR
 General Facilities = Total Direct Cost with Retrofit x General Facilities (% of  installed
 cost)

 Engineering fees = Total Direct Cost with Retrofit x Engineering Fees (% of installed cost)

 Contingency = Total Direct Cost with Retrofit x Contingency (% of installed cost)

 Total  Plant Investment =  Sum of Total  Direct  Cost  with  Retrofit, General Facilities,
 Engineering fees, Contingency taking into account allowance for funds during construction

 Preproduction =  Total Plant Investment x 0.02+ One Month Fixed Operating Costs + One
               Month Variable Operating Costs (at full capacity)
D.4.3  Operating and Maintenance Costs
In general, natural gas  reburning reduces the boiler operating costs associated with coal-
and ash-handling process areas, including maintenance, electricity,  and  ash  disposal. Fuel
costs are generally higher, because the price of natural gas is typically higher  than the price
of coal per unit of energy. The  equations  used  by CUECost and  taken from IAPCS for
estimating operating costs and savings are given below. The electricity requirement for coal
and ash handling processes decreases in proportion to the amount of reburn fuel used. The
default for maintenance  costs for operating the NGR system is 1.5% of the total plant cost.
The empirical equation for estimating waste disposal savings includes a reduction of bottom
and fly ash as a result of firing gas. As in IAPCS, savings from reduced fly ash disposal are
estimated only for retrofit applications. The incremental fuel cost for firing gas is estimated
by multiplying the amount of gas burned by the fuel price difference between gas and coal.
Annual operating and maintenance costs and savings for NGR are shown in Table D-15.

Table D-15.   Annual Operating and Maintenance Costs and Savings for NGR
 Electrical Consumption Savings ($/year)
 ELEC = 9.51 x 107 x Qin x CF x RBFRAC/HHV x UCELEc

 Maintenance Cost ($/vear)
 MAINT = Maintenance (%) x TPC - 1387.5 x RBFRAC x (BSIZE/500)0'6

 Waste Disposal Savings ($/vear)
 WASTE =  [BA x RBFRAC + (NR - 1) x 4.336 x RBFRAC x  PPHPRT x CF] x UCWASTE

 Natural Gas Consumption Cost ($/vear)
 GAS = Qin x RBFRAC x 8,760 x CF x (UCGAS - UCCOAL)	
                                                                                  95

-------
Appendix D
where
Qin = boiler heat input, MMBtu/h
CF = capacity factor, dimensionless
HHV = higher heating value of coal, Btu/lb
UCELEc = electricity rate, $/kWh
TPC = total plant capital costs, $
BA = bottom ash rate, tons/year estimated from:
        BA = BAF x  ASH x, 500/HHV x Qin x 8,760 x CF/2,000
        where
        BAF = bottom ash factor,  dimensionless
        ASH = percent ash in coal, wt.%
NR = retrofit status,  1 for new "grass root" installation (retrofit factor = 1) and 2 for retrofit
   application (retrofit factor > 1)
PPHPRT = fly ash rate, Ib/h
UCWASTE = waste disposal rate, $/ton
UCGAS = gas rate, $/MMBtu
UCCOAL = cost for coal, $/MMBtu.

D.4.4  CUECost Validation
Total plant costs and operating and  maintenance costs estimated by CUECost algorithms
were compared  to current cost data  developed and validated by EPA's ARD (See Tables
D-16 and D-17). Four applications of NGR for various boiler types,  boiler sizes and  coals
were evaluated  with CUECost. The design information provided  by ARD for the four  NGR
applications was used to evaluate the direct capital cost equations from CUECost.

Total plant costs presented  below include the fuel injectors,  overfire air ports, associated
piping, valves, windbox, and control  dampers  and the gas pipeline from the fence line to
boiler. The total  plant costs include direct costs listed above as well as indirect capital  costs
for engineering,  general  facilities  and contingencies.  Chemical Engineering Magazine  plant
cost indices were used to report costs in consistent year dollars.

The percent difference between ARD  study costs and the CUECost estimates for total  plant
costs  ranged from 0 to  11% for the cases evaluated.  Operation and maintenance  costs
estimated by CUECost are 7 to 12% lower than those estimated by the ARD study.
                                                                                  96

-------
Appendix D
Table D-16.   CUECost with Acid Rain Division Study Cases for NGR (1990 dollars)*
Natural Gas Reburning
Cyclone-Fired
Midwestern Bituminous
Wet-B
Vertical-
Fired
ottom
Wall-Fired
Eastern Bituminous
Boiler Size (MW)
150 400
100 259
 CUECost with Acid Rain Division Design Parameters
 Design Parametersfrom AcidRain Division
 Gas Reburn Fraction

 Capital Costs using Acid Rain Division Design Parameters f$ 1000)
 Gas Pipeline from Fenceline to Boiler
 Fuel Injectors, Overfire Air Ports and Associated
 Piping, Valves, Windbox and Control Dampers
 Total Capital Equipment Cost
 Total Plant Cost (TPC)
           TPC($/kW)

 % Difference from Acid Rain Division Cost Study
2,000
2,720

3,590
 23,9

   11
 Q&M_Costs using Acid Rain Division Design Parameters ($1000/vear)
 Electrical Consumption Savings
 Maintenance
 Waste Disposal Savings
 Natural Gas Consumption
 O&M

 % Difference from Acid Rain Division Cost Study

  Source: EPA, 1996
3,470
4,863

6,419
 16.1
1,684
2,315

3,056
 30.6

    0
2,646
3,606

4,760
 18.4
(54)
54
(43)
1,467
1,423
-11
(152)
96
(122)
4.110
3,933
-7
(34)
46
(23)
866
855
-12
(89)
71
(61)
2.290
2,212
-12
                                                                                               97

-------
Appendix D
Table D-17.   Acid Rain Division Study: NGR Applications (1990 dollars)*
Natural Gas Reburning
Cyclone-Fired
Midwestern Bituminous
CHAPTER 2
Vertical-
Fired
WET-
Wall-Fired
Eastern Bituminous
Boiler Size (MW)
150 400
100
259
 Acid Rain Division Costs and Design Parameters
 Design Parameters from Acid Rain Division
 Gas Return Fraction                                  0.16        0.16        0.16        0.16

 Acid Rain Division Capital Costs ($1000)
 Fuel Piping System                                   510        1040        500         803
 Burners/OFA                                       585        1840        540        1191
 Electrical/BMS Modifications                          735        1000        750         907
 Windbox/Duct/Modifications                           165         120         60         104
 Platform/Insulation/Demolition                         405         520        410         466
 Total Capital Equipment Cost                         2,400       4,520       2,260       3,471

 Total Plant Cost (TPC)                               3,225       6,080       3,050       4,662
         TPC($/kW)                                21.5         15.2        30.5         18.0

 Acid Rain Division O&M Costs ($1 OOP/year)
 Coal Consumption
 Ash Disposal
 General Maintenance
 Natural Gas Consumption
 O&M Total                                        1,607       4,236        969       2,510
* Source: EPA,  1996
(1,630)
(50)
50
3,239
(4,564)
(141)
93
8.848
(1,201)
(27)
47
2.150
(3,184)
(71)
71
5,694
D.5   LOW-NOx BURNER TECHNOLOGY

D.5.1  Capital Costs
CUECost estimates capital  costs for retrofitting tangentially-fired and wall-fired boilers with
LNBT.  The cost algorithms are based on a study  of LNBT by ARD  (EPA, 1996). The study
obtained  information  from   56  boilers--35   wall-fired  and  21  tangentially-fired.  The
information provided for these retrofit cases was  used to develop empirical equations that
estimate total capital  cost for  LNBT retrofits  as  a function  of boiler size.  CUECost only
addresses retrofit installations because most new boilers include LNBT in their base design.

The "bottom-line" costs include direct capital costs and indirect costs such as engineering,
general facilities,  and contingencies. The scope of direct costs collected for the ARD study
includes (1) for the burner  portion:  burners  or  air and coal nozzles,  burner  throat and
                                                                                        98

-------
Appendix D
waterwall  modifications and  windbox  modifications;  (2)  for  applicable combustion  air
staging: waterwall modifications or panels,  windbox modifications, and ductwork; and  (3)
scope adders or supplemental equipment such as replacement or additional fans, dampers,
or igniters necessary for the LNBT. The scope of installed LNBT retrofit capital costs includes
materials, construction and installation labor, engineering, and overhead costs (40 CFR, Part
76, Appendix B).

The ARD study found that capital costs vary greatly depending on the scope of the retrofit
and the degree  of modification  necessary. As  a result,  the cost  data  were statistically
separated into subsets of high and low cost  cases for each boiler type. Cost equations were
then developed by ARD for the high and low cost subsets, as well as for the entire set of
cost data. The CUECost user selects from any of the three ARD cost equations based on  the
estimated retrofitting  difficulty: high, average or low.  The equations are given in  1995
dollars and include the user input Chemical  Engineering  Magazine plant cost index (PCI) to
escalate to the desired cost year. Total capital costs for LNBT retrofit are shown in Table D-
18.

Table D-18.   Total Capital Costs for LNBT Retrofit

Tangential-fired Boilers
High Cost: 57.04 x (300/BSIZE)/V0.679 x 1000 x BSIZE x PCI / 357.6
Average Cost: 21.20 x (300/BSIZE)^0.35 x 1000 x BSIZE x PCI/ 357.6
Low Cost:  11.71 x 1000 x BSIZE x PCI / 357.6

Wall-fired  Boilers
High Cost: 27.72 x (300/BSIZE)/V0.573 x 1000 x BSIZE x PCI / 357.6
Average Cost: 15.37 x (300/BSIZE)/V0.35 x 1000 x BSIZE x PCI/ 357.6
Low Cost:  6.53 x  (300/BSIZE)^0.857 x 1000 x BSIZE x PCI/ 357.6	

where
BSIZE = boiler size, MW
PCI = Chemical Engineering Plant Cost Index for desired cost basis year.

A cost comparison between CUECost  and IAPCS cost algorithms was not possible because
design and economic parameters were not given in the ARD study of NGR technology.

D.5.2  Operating and Maintenance Costs
The  only  direct  operating  costs associated with  LNBT are for maintenance labor and
materials. No energy penalty is assumed to be incurred  with this technology.  Costs for  the
controls, administration and support labor, including overhead, are 30% of the maintenance
labor costs. Annual operating and maintenance costs for LNBT are shown in Table D-19.
                                                                                 99

-------
Appendix D
Table D-19.   Annual Operating and Maintenance Costs for LNBT ($/year)

Maintenance Labor = TPC ($) x Maintenance Labor (0.8%)
Maintenance Materials = TPC ($) x Maintenance Materials (1.2%)
Administration/Overhead = Maintenance Labor ($/year) x 30%	

where
Maintenance Labor = Annual  maintenance labor cost, $/year
Maintenance Materials = Annual maintenance materials cost, $/year
Administration/Overhead = Annual costs, $/year
TPC = Total Plant Costs ($).

D.5.3 CUECost Validation
Total  plant costs estimated by CUECost for the four boiler sizes examined for the other NOX
technologies are shown in Table D-20. The CUECost algorithm  for total plant cost is identical
to the cost function presented by the ARD study of LNBT (EPA,  1996). A comparison is not
presented for operating  and maintenance costs  because these costs are  highly boiler-
specific.

Table D-20.   CUECost with Acid Rain Division Study Cases for LNBT (1990 dollars)*
Low NO., Burner Technology
CUECost Total Plant Cost ($ 1000)
Wail-Fired
T-Fired
150
Boiler Si
400
ze (MW)
100
259
Average Case
2,938
4,053
5,559
7,668
2,258
3,114
4,191
5,781
 % Difference from Acid Rain Division Study
 Wall-Fired
 T-Fired
  Source:  EPA, 1996
0
0
0
0
0
0
0
0
D.6    HG CONTROL TECHNOLOGY

The algorithm of PAC control cost has the form

   x = MIN(X,D)

   y = Logio(Injection Rate) = Ax2+Bx + C
                        (Eq. D-9)

                       (Eq. D-10)
                                                                                100

-------
Appendix D
where X is  the  mercury reduction fraction desired and the  injection  rate is expressed in
Ib/MMacf. A, B,  and C are provided in the table below. D is  used  to specify  the  maximum
fraction of  mercury that can  be removed,  essentially an upper  limit.  In CUECost,  D is
actually multiplied by 0.99  so that the maximum removal that can be calculated equals  99%
of D. Calculation results are shown in Figures D-l through D-5.

Constants for Eqs. D-9 and D-10  are shown in Table D-21.
Table D-21.  Constants for Eqs. D-9 and D-10

PAC, Bituminous FF
PAC, Bituminous ESP
PAC, Subbituminous FF
PAC, Subbituminous ESP
Treated PAC, Subbituminous FF
Treated PAC, Subbituminous ESP
Treated PAC, Bituminous ESP
A
1.6944
-0.6647
-0.4318
3.308
0.0
0.8837
0.0
B
-1.1267
2.1232
1.9551
0.754
2.5007
0.4485
1.207
C
-0.0009
-0.0665
-0.8937
-0.5925
-2.2097
-0.575
-0.2277
D
1.0
1.0
1.0
0.7
1.0
1.0
1.0
           Log Injection Rate vs Reduction
                 Bituminous FF
     60% 65% 70%  75%  80%  85%  90%  95% 100%
                    reduction
                                              Figure D-l.   PAC, Bituminous FF

                                              y =  1.6944X2 - 1.1267x - 0.0009
                                              R2 = 0.8409
                                              x <  100%
           Log Injection Rate vs Reduction
                Bituminous ESP
         10% 20% 30% 40% 50% 60% 70% 80% 90%  100
                    reduction              "
                                              Figure D-2.   PAC, Bituminous ESP

                                              y = -0.6647X2 + 2.1232x - 0.0665
                                              R2 = 0.8797
                                              x < 100%
                                                                                   101

-------
Appendix D
            Log Injection Rate vs. Reduction
                  Subbituminous FF
     0.8
     0.6 -
     0.4-
     0.2 -
      0 -
    -0.2 -
    -0.4 -
    -0.6 -
    -0.8
        -/-=-
:_-Q.4318x + 1.9551X - 0.8937
     R2 = 0.9_55 _!_
       0%
          10%  20%  30% 40% 50%  60%  70% 80%  90% 100%
                       Reduction
Figure D-3.    PAC, Subbituminous FF

y = -0.4318x2 + 1.9551x - 0.8937
R2 = 0.955
x < 100%
             Log Injection Rate vs Reduction
                  Subbituminous ESP
     1.6
                 Iog10 (injection)
                -best fit
                   • U./b4x - U.5925
           10% 20%  30% 40%  50% 60%  70% 80%
                        redn
                                           Figure D-4.    PAC, Subbituminous ESP

                                           y = 3.308x2 + 0.754x - 0.5925
                                           R2 = 0.7856
                                           x < 70%
    0.8 T—
    0.6
    0.4
    0.2
  £  0
  ro
  2 -0.2 ]
    -0.4
             Log Injection Rate vs Reduction
            	BPAC	
              BPAC In Flight, Parametric
              in-flight best fit
                        BPAC FF
                       -FF best fit
                           y = 2.5007X - 2.2
                              R2 = 0.6062
                                      097
      0%  10%  20%  30%
                       %  50%  60%  70%  80%  90%  100%
                        reduction
                                             Figure D-5.    BPAC
  Treated PAC, Subbituminous FF
  y = 2.5007X - 2.2097
  R2= 0.6062
  x < 100%

  Treated PAC, Subbituminous ESP
  y = 0.8837X2 + 0.4485x - 0.575
  R2  = 0.8497
  x < 100%
                                                                                            102

-------
Appendix D
The algorithm of PAC control cost was incorporated into CUECost and a lookup table, located
in the Constants_CC worksheet, and developed to ease users' selection. To  use the lookup
table  in the  CUECost workbook, a three-digit index key is  constructed  by summing the
following digits:

   •   100 or 200 for bituminous or subbituminous coal, respectively
   •   10 or 20 for in-flight or filter capture, respectively
   •   1, 2, or 3 for enhanced PAC (denote  EPAC, such as brominated PAC), standard PAC,
       or other sorbent, respectively.

For example, a PRB coal fired boiler with a cold-side ESP and using enhanced PAC would
have an index  key of 211. If the same  boiler  were retrofit  with a PJFF for a TOXECON
arrangement and standard PAC were used, the index key would then be 222.

For the purpose of CUECost, subbituminous  and  lignite coals are treated the  same way. For
all practical purposes, the two  categories are bituminous and low  rank. In  reality some
bituminous coals  with very  low  chlorine levels may behave more like low rank coals and
some low rank coals with unusually high chlorine  may behave more like bituminous coals.
This issue will be addressed in the future.

Sample Calculations
To see how the new algorithms worked, some calculations of control cost were made. Figure
D-6 shows comparison calculations for cost of controlling mercury for various situations on a
500 MW low sulfur bituminous coal-fired boiler equipped with an ESPc as a function of total
mercury removal.
            Cost of Mercury Reduction
             LS Bituminous Coal and ESP
    3.00
    2.50

    2.00 |
 =  1.50
    0.00
•LS Bituminous Coal with
 CS-ESP and EPAC
•LS Bituminous Coal with
 CS-ESP and PAC
                 Percent Total Reduction
Figure D-6.   Cost of Mercury Reduction, LS Bituminous Coal and ESP
                                                                                  103

-------
Appendix D
In all calculations, addition of sorbent is assumed to cause fly ash in contact with sorbent to
be disposed of at a differential cost of $30/ton. Also, the cost of sorbent is assumed to be
$1000/ton for standard PAC and $1500/ton for EPAC.

As shown in Figure D-6, EPAC incurs the lowest cost while maintaining the same level of Hg
removal efficiency. For this reason, a TOXECON retrofit with PAC  is not  cost effective
compared to EPAC. However, if fly ash is currently land filled, the differential disposal cost is
negligible and an estimated 0.38 mills/kWh could be deducted from the cost of controlling
mercury with sorbent injection upstream of an ESP (Staudt et al., 2003).
D.7   CO2 MEA CONTROL SYSTEM COST ALGORITHM DEVELOPMENT

The cost algorithms associated with the CO2  MEA control processes were developed based
on DOE/NETL dataset in 2007 (DOE 2007). Algorithm development began with derivations
from DOE/NETL  database  by running a series of data regressions and identified suitable
equations.  These datasets  were then utilized  to predict the  cost  by  assuming the MEA
concentration was at 30%. The  derived regression equations represent a typical MEA
operating plant for equipment areas and for specific O&M costs.

D.7.1 Capital Cost
The MEA island  contains a pretreatment unit, a CO2 absorber, and a CO2 stripper. Costing
has been based  on  the most recent DOE/NETL (2007) cost analysis of MEA CO2 capture.
MEA mainly reacts with two moles of amine and one mole of CO2. Mitsubishi Heavy Industry
(MHI) has developed  a new solvent (named KS-1) primarily reacting with one  mole of amine
and one mole of CO2. Little information has  been found for the specific cost of the KS-1
based system. The capital  costs found in MHI presentations did not provide sufficient detail
to determine a  comparable basis for Bare  Erected Costs. Further, these cost  estimates
aggregated the recovery island and the  compression island costs. As the KS-1 contains the
same processes as the MEA, bare erected  costs for the KS-1 island  are therefore calculated
in the same manner as the MEA island bare erected costs. As a regression of DOE dataset,
the model MEA island cost will be:

   Y=69,412,748 x X0'5741                                                  (Eq. D-ll)

where
Y = bare erected cost, 2007 $
X = CO2 capture, metric ton/h.

Gas  exiting the  CO2 stripper  must be  compressed and  dehydrated to  accommodate
transport and disposal. In  DOE's model  (DOE/NETL,  2007), moist CO2 from  the CO2
stripper's reflux drum enters the compressor at 21  °C (69  °F) and nominally 160 kPa (23
psi). CO2 is compressed in a 6-stage integrally geared compressor. Intercoolers between
stages  cool the  gas  using chilled water from the  plant's cooling tower. After exiting the

	104

-------
Appendix D
compressor and presumably a final heat exchanger, the CO2 is dried to <20 ppmv water in
a TEG dehydrator. Dry gas exiting the dehydrator is at 15.27 MPa (2215 psi) and 51 °C
(124  °F).  Regression  of the two  coal-fired plants and one natural gas  combustion plant
cases presented results in a power law model for capital costs scaled to the power used for
compression raised to 0.5429 power. This regression is based  on  a very limited data set.
The uncertainty of the capital estimate increases as conditions deviate from those used in
model development. As the result, the model compressor island cost will be

   Y=103,045 x X °-5429                                                    (Eq. D-12)

where
Y = bare erected cost, 2007 $
X = compressor power, kW.

Indirect capital costs for CO2 control are shown in Table D-22.

Table D-22.   Indirect Capital Costs for CO2 Control
 General Facilities = Total  Direct Cost with  Retrofit  x  General Facilities (% of installed
 cost)
 Engineering fees = Total Direct Cost with Retrofit x Engineering Fees (% of installed cost)
 Contingency = Total Direct Cost with Retrofit x Contingency (% of installed cost)
 Total Plant Investment = Sum of Total Direct Cost with Retrofit, General Facilities,
 Engineering fees, Contingency taking into account allowance for funds during construction
 Preoroduction = Total Plant Investment  x 0.02 + One month fixed operating costs +
                           One month  variable operating costs (at full capacity)
 Inventory = 0.5% Total Plant Cost (TPC)	
D.7.2 Operating and Maintenance Costs
Steam
Steam is used in the reboiler of the CO2 stripper to reverse the CO2 reactions that took place
in the CO2 absorber.  In addition to the heat required for CO2 regeneration, some steam is
used evaporating water in the stripper. In the recent DOE analysis (DOE/NETL, 2007), 1529
Btu/lb CO2 were required to regenerate CO2 in most cases for coal combustion while 1590
Btu/lb CO2 were required for natural gas combined cycle  (NGCC) (DOE, 2007). The major
portion of this difference arises from the lower concentration of CO2 in the NGCC gas. Rao
(2002) reported a  range of steam use of 3800-4000  kJ/kg CO2 (1636-1723 Btu/lb  CO2).
Steam use  at the  KS-1 installation  at a Malaysia  urea plant was 3270 kJ/kg CO2 (1409
Btu/lb CO2)  with a feed gas containing  8% CO2 on a dry basis. Data  presented  by DOE
(2007) and Rao  (2002) suggest that the steam requirement decreases with increasing CO2
concentration. Steam  consumption in the reboiler  is estimated  in this  model  based on a
power law curve fit re-created from MHI's presentation  of steam  use.  Assuming the CO2

	105

-------
Appendix D
concentration is on a dry  volumetric basis, this model  predicts  3140 kJ/kg CO2 steam
consumption for an 8%  CO2 flue gas as documented  for the Malaysia facility, a 4% error.
Assuming  there is  no significant difference for different MEA processes, the steam use for
regenerating MEA solvent in the worksheet will be regressed as:

   Y = 4109.2 x X'0-13                                                      (Eq. D-13)

where
Y = energy demand, kJ/kg CO2
X = CO2 concentration, %.

Cooling Water Makeup
Cooling  water will  be used to remove heat from the direct contact cooler (DCC) during
pretreatment, remove heat  generated in the absorber, condense steam in the reflux drum
of the CO2 stripper, remove heat from the lean solvent returned from the CO2 stripper, and
remove  heat generated  by the compressor. As  a  budgetary estimation of cooling water
makeup, we simplify the total use of cooling water makeup as:

Cooling water makeup = Loss due to DCC + Lump-sum Loss from  MEA island + Loss from
compressor island.

Enthalpy of the  flue gas  entering the direct contact cooler is calculated based on mass flows
and temperatures  exiting from the previous unit operation, for example,  wet scrubbers.
Enthalpy of the gas flow exiting the direct contact cooler is based on the mass flow exiting
the direct  contact cooler, assuming the exiting gas  is  saturated with water. Heat loss from
the direct contact cooler is  then  calculated as the  difference between  the above  two
enthalpies. Although the pretreatment may also involve  SO2 polishing, this heat duty is
expected to be inconsequential in comparison with the heat duty of condensing water vapor
from the flue gas.

The MEA island  cooling water requirement is estimated based on the steam  requirement for
the CO2 stripper reboiler. The heat supplied to the  reboiler is sufficient to  reverse the CO2
absorption, evaporate water and increase the enthalpy of the stripper effluent. The heat of
reaction is removed in heat exchangers associated with the absorber. Steam is condensed in
the stripper reflux drum  and returned as reflux. Enthalpy of the stripper effluent in excess of
the heat  transferred  to the stripper  influent  must  be  removed  in a  heat  exchanger
associated with  the  absorber; the  lean  solvent from the  stripper is cooled to a lower
temperature than the rich solvent effluent from the absorber. For simplicity, the heat input
from steam will  be  equal to the heat rejected through cooling water evaporation.

Intercoolers are heat exchangers located between compressor  stages with  an intention to
reduce the temperature of the gas, and, in turn, to protect  the compressor from heat
damage and reduce the  power requirements. Chilled water is required for this purpose. The
heat duty  is assumed to be a fraction of power used  by the compressors,  as shown in  Eq.

	106

-------
Appendix D
(D-14).  The fraction is equal to the overall compressor  efficiency which is  equal to the
isentropic efficiency of the compressor multiplied by the efficiency of the drive. The energy
losses from the drives are assumed to flow to the surrounding environment, not to the CO2
compression. In general,  the isentropic efficiency is assumed  to be 84% and the  drive
efficiency of the electric motor is 95%. Consequently, the overall efficiency is 80%.


               8W                                                       (Eq. D-14)
               .
        0.84

The  makeup  cooling water  flow  rate  (gpm)  is  equal to  evaporation  rate  of water
(approximately 2 gpm per 1 million Btu/h of heat)  multiplied by an appropriate correction
factor: l/(cycle of concentration-1). The cycles of concentration = chlorides in tower water/
chlorides in makeup water.

Power
The power used in the MEA Island  is primarily consumed by an induced draft fan after the
direct contact cooler. Pumps used to recirculate condensate and the MEA solvent represent
the remainder of the MEA island power demand.

Power used  in  the  induced draft fan  is  estimated  based on the average volumetric flow
entering  and  exiting the fan and the pressure differential across the fan.  The recent DOE
model (DOE,  2007) indicates a pressure  differential of 0.014 MPa (2 psi) across this fan to
overcome the pressure drop in the absorber. Gas is assumed to enter the fan saturated with
water at  32 °C from the direct contact absorber. The recent  DOE  model  (DOE, 2007)
indicates a temperature rise across the fan of 17 °C for  PC cases; an outlet temperature of
49 °C will be used  in all  cases. The pressure difference across the absorber  with the MHI
design using  structured  packing is  substantially less  than the  power  required  with  a
randomly packed column. MHI claimed the pressure differential is  1/7 that of conventional
MEA technology. Assuming isentropic compression and a k of 1.4,  a temperature rise of 2
°C is  estimated across the fan using MHI's design. The fan  inlet temperature is therefore
assumed to be 47 °C. The flue gas entering the fan is expected to be at nearly atmospheric
pressure.  An  overall  efficiency  of 80% will  be used  to calculate the  expected  power
requirement of the fan. Consequently, the power required by fan will be:

   Power (HP) = Gas flow (acfm) x AP(psi)/229/efficiency                     (Eq. D-15)

At this stage of estimation, the  power for all the remaining pumps is estimated at 0.006
kWh/kg CO2 removed, the average  MEA island power use for PC units in the 2000 and 2004
analysis. Since the DOE 2007 analysis reflects similar steam requirements  for PC units and
NG-fired  units, the loading of the MEA and the parasitic  power is assumed  to  be similar for
PC and NG-fired units. No new power requirements could be assessed from the DOE 2007
analysis since the fan power is added to the rest of the MEA system  power  requirements.
Though a higher  recirculation  rate in the  DCC  is anticipated  for  the NG-fired units,  this
power consumption was disregarded at this level of analysis.

_ 107

-------
Appendix D
The  larger share of the  power consumed  in the  compressor island  is associated  with
compression of the  CO2.  At the study level of estimation, power required to run the TEG
dehydrator is  ignored. Power consumed  by the intercoolers  is contained  in  the power
required for compression  as pressure loss across  the intercooler. The efficiency of the drive
is included in the overall efficiency of the compressor.

Each stage of the compressor is nearly isentropic as there is limited surface area within the
stage to  remove  heat  in  large compressors. Heat is, therefore, largely removed between
stages by heat exchangers. Power consumption for compression is assumed to be isentropic
in  each stage with  an efficiency factor applied  to  correct for  non-ideal behavior of the
compressor. Due to  high  pressures involved, the  power estimate must account for the  non-
ideal behavior of the gas  as well. The deviation from ideal gas behavior is corrected with a
compressibility factor (Z). The estimation procedure  used for Z is shown in Appendix F. An
overall efficiency  of 0.80 has been  used consistent with the DOE (2007) analysis. The
overall compression  work is then calculated for each stage of compression as follows (Ulrich,
1984).
             _ ~     k~l
         RTls7 ( P ~\ k
                                                                          (Eq. D-16)
    m    k-l
where
PI= inlet pressure of the compressor
P2=outlet pressure of the compressor
TI= inlet gas temperature, K
R=188.9 J/(kg x K) for CO2,
k=1.28 for CO2.  Ratio of constant pressure to constant volume heat capacity
m= flow  rate of gas, kg/s.
n=0.8, overall  efficiency
Z=compressibility factor (See appendix F for calculation).

The power requirement for compression appears to decrease with each additional stage of
compression. This work advantage is offset somewhat by the cost of the interstage coolers
and the pressure drop between each of the stages. Because of the pressure drop across the
interstage cooler, the pressure of the gas exiting a stage is slightly higher than the pressure
of the gas entering the successive stage. At this level of estimation,  a  constant pressure
drop of 0.01 MPa (1.5 psi)  per cooler is assumed.

Generally, the power required and costs of  a  compressor are minimized when the same
amount of compression  work is accomplished in each stage. Since compressibility can vary
from nearly 1  to 0.5 in these compressors, the  compression ratio in installed equipment is
likely to  be different in each stage. This effect is most dramatic  in the supercritical region
where  compressibility  will  be  managed by  controlling the stage inlet  temperature.  For
computational  simplicity, the pressure ratio of the final stage of compression is estimated to

	108

-------
Appendix D
be 30% higher than the other stages if the final pressure is supercritical. The pressure ratio
for each of the preceding stages is evenly distributed prior to considering the pressure drop
of the interstage cooler.
                                                                         (Eq-D-17)
The overall compressor efficiency  includes the isentropic efficiency of the compressor and
the efficiency of the drive. The work lost to the drive efficiency  is assumed lost to the
environment and not transferred to the CO2. The isentropic efficiency is assumed to be 84%
while  the  overall  efficiency is  assumed  to  be  80%;  the  resulting drive efficiency of the
electric motor is 95%.

                                                                         (Eq. D-18)
        0.84

During estimation, the average Z is 0.8 for the first n-1 stage compressors, and equal P2/Pi
is also assumed for the first n-1 stage compressors.

Cost of MEA
MHI  estimated  MEA consumption  at 0.45  kg MEA/metric  ton  CO2  for its  CO2 capture
technology.  For the other MEA based processes,  Rao (2002) reported a range of 0.5-3.1
kg/metric ton CO2  and  a  typical  value of 1.5  kg  MEA/metric ton  CO2.  For  estimation
purposes, the consumption rate of MEA  employed in the  worksheet will be at the typical
value of 1.5  kg MEA/metric ton CO2 for MEA process. Inhibitors are added to the absorber to
prevent corrosion. The cost of inhibitors is estimated at 20% cost of MEA.

Cost of NaOH
Sodium hydroxide is used to  bring down the SO2 concentration in the influent gas to less
than 10 ppm and to regenerate the MEA from the sulfate  salts. The consumption of NaOH
for SO2  removal is based on the removal  of SO2 from the influent gas.  For the consumption
of NaOH in the reclaimer, no data  on sodium  hydroxide use were found in MHI papers or
presentations for  KS-1. Rao (2002) reported a typical value of 0.13  kg NaOH/metric ton
CO2. This value will be used in the worksheet.

Cost of Activated Carbon
Activated carbon is used to remove high  molecular weight  products. Rao (2002) reported a
typical value of 0.075 kg carbon/metric ton CO2. MHI claims a  consumption of 0.06 kg
carbon/metric ton CO2. As the difference is not significant and the impact on the total cost is
minor, a typical value of 0.075 kg carbon/metric ton CO2 will be used in the worksheet.
                                                                                109

-------
Appendix D
D.8   CO2 CAP CONTROL SYSTEM COST ALGORITHM DEVELOPMENT

The algorithm developed for CO2 CAP control was based on the system description and data
sets  in  the DOE/NETL report (DOE  2007).  The algorithm for  capital  cost  is developed
through the comparisons with the MEA process. O&M  cost is estimated  based upon the
system description by Sherrick et al. (2008).

D.8.1 Capital Cost
As with  the MEA process, the CO2 CAP control system contains a pretreatment unit, a CO2
absorber,  and  a CO2 stripper  in the absorption island.  The only cost information found to
date for the CAP is based on analysis presented at Lyon,  France in 2007  (EPRI, 2007). This
analysis aggregates the total plant cost for a 3891 MMBtu/h  supercritical  pulverized coal
(SCPC) plant with and without CAP and with MEA CO2 capture.

For  modeling  purposes,  the bare erected  cost  of the CAP  separation  island  will  be
approximated as a fixed fraction of the modeled cost for a comparable MEA island. The total
cost  of the CAP CO2 capture, CAP separation island and compression  island is estimated
based on the difference in TPC of the SCPC with CAP and the SCPC without CAP to be $120
million. Though this approach includes plant effects other than the CO2 capture system costs
such as steam  takeoffs, turbines,  condenser, and  chilled water  systems, this  shortcut is
considered expedient in lieu of replicating the entire  plant economic analysis. To return
these costs to the  bare erected cost basis, a constant escalation factor, 23% in aggregate,
is applied.  The  estimated bare erected cost of the CAP CO2 capture is  $97.6 million. The
bare erected cost  of the  MEA system  analyzed  in the DOE/NETL report (2007) is $111.8
million.

The capital costs associated with a CAP and MEA CO2 capture are expected to be distributed
differently  between the separation island and the compression  island. The compression
island for  the CAP is expected to  be significantly cheaper than the compression island  for
MEA due  to  the  high pressure,   >400  psi,  output of the  CAP  regenerator; the MEA
regenerator is  evaluated at 27.2 psia. The cost of the CAP separation island  and the MEA
separation  island  is estimated  by  subtracting the  estimated cost   of  the  respective
compression islands from their respective bare erected costs of the CO2 capture. The power
requirement of  the CAP compression island is estimated  assuming 400  psia inlet pressure,
1217 psia  outlet pressure, and 69 °F  (21  °C) inlet temperature  using  a  single stage
compressor. Using the  correlation developed from the DOE/NETL report (2007), the 6277
KW compressor estimated for the CAP CO2 capture would have  a  bare erected  cost of $11.9
million in 2007, January 2000 bare erected costs are estimated at $9.1 million. Using the
correlation  developed in the DOE/NETL report (2007), the 29730 kW compressor specified
for the MEA CO2 capture would have a bare erected cost of $27.6 million in 2007. January
2000 bare erected costs are estimated at $21.2 million.

The estimated bare erected cost of the CAP separation island is  $88.5 million. The estimated
bare erected cost for the MEA separation island in the 2000 Parsons study  is $90.6 million.

	110

-------
Appendix D
The CAP separation island bare erected  costs are estimated  at 97.7% of the  comparable
cost of an MEA separation island.

Electricity
The main power consumers in the CAP  separation island are expected to be the blower
upstream of the absorber,  recirculation  pumps, and chiller. The Alstom analysis  provides
parasitic power for the overall study plant without providing details on power requirements
for compressor, blower, pumps, or chillers. The relative power consumption of each function
is  expected  to  change  with  inlet  gas composition and  temperature.  Since  detailed
information is not available, process conditions will be assumed to fix power consumption.

Power  used  in the induced draft fan is  estimated  based  on the average volumetric flow
entering  and  exiting the fan and the pressure differential  across the fan.  The  recent DOE
model  (2007) indicates  a pressure differential  of  0.014  MPa (2  psi) across  this fan to
overcome the pressure drop in the absorber. Gas is assumed to enter the fan saturated with
water  at  32 °C  from the  direct  contact  absorber. The  recent  DOE model  indicates  a
temperature rise across the fan of 17 °C for PC  cases; an  outlet temperature of 49 °C will
be used in all cases. An 80% overall efficiency is assumed for the fan.

The power for  pumping is assumed  to  be 0.006 kWh/kg CO2  removed. This value was
derived from the DOE/NETL report (2007) for MEA CO2 capture.

The chiller is used to cool the flue gas exiting the ID fan prior to the absorber and to remove
the heat of reaction. The flue gas is assumed to exit the fan at 49  °C  (saturated at 32 °C)
and will be cooled to saturation at 2 °C with the chiller. The heat load at the absorber will be
approximated using the steam heating duty of the regenerator, 267 Btu/lb CO2. Power use
by the chiller will be approximated as 1/4 total  cooling duty of the  chiller. The chiller is a
mechanical chiller for removing heat.

Steam
Steam  is used in the CAP CO2 capture to reverse ammonium bicarbonate back to  NH3 and
CO2 (NH3HCO3+heat=NH3+CO2+H2O). The Alstom analysis  (DOE/NETL, 2007) uses  179,500
Ib/h low pressure steam  in the  recovery of 710,423  Ib/h  of CO2,  0.253 Ib steam/lb CO2.
Assuming 1058 Btu/lb steam can be  utilized, 267 Btu/lb CO2 is required. The heat duty  is
very close to the heat  of reaction  suggesting minimal  reflux  in the regenerator and
extraordinarily efficient heat transfer in the  cross flow heat  exchanger between the absorber
and regenerator.

Cooling Water
The cooling water duty is obtained by subtracting the sum of the other energy flows  out of
the CAP island from the energy flows into the CAP island;  the energy flows out of the CAP
island must balance the energy flows into the CAP island.
                                                                                Ill

-------
Appendix D
Specific enthalpy of the flue  gas  entering the  CAP island  will  be calculated based  on
temperature and composition information resulting from operation  of the prior unit. Much of
the water in the flue gas will be condensed in  pretreatment contributing enthalpy to a CAP
water balance.

Specific enthalpy of the flue gas exiting the CAP island will be  calculated based on the mass
balance composition assuming 90% CO2 removal,  100% SO2 removal, and water saturation;
no significant removal of other gases is anticipated in the absorber. Though the exhaust
temperature from the CAP island is  not known, Alstom includes a second direct contact heat
exchanger to recover some  of the heat removed in preconditioning (DOE/NETL, 2007). The
temperature of the gas exiting the CAP island is assumed  to be the wet bulb temperature of
the flue gas entering the CAP island.

CO2 exiting the  stripper reflux drum and leaving the CAP island is estimated to be pure CO2
saturated  with water. The temperature of the CO2  exiting the stripper reflux drum in the
MHI design was not known but is assumed to be 21 °C as found in the MEA island analysis.

Steam is primarily used in the reboiler to regenerate solvent and produce concentrated CO2.
Steam use is estimated by the net  heat required for regeneration, based on the amount of
CO2 recovered, 267 Btu/lb CO2.

The heat balance in  the water streams is difficult to estimate with  certainty because the
amount of fresh makeup water added to scrub the absorber outlet gas is not known for the
MHI design. It is not clear whether the scrubbing water is derived from the direct contact
cooler or fresh  makeup  water. For  estimation purposes,  the  water used for scrubbing the
absorber outlet gas is assumed to be derived entirely from the direct contact cooler. The net
amount of water condensed is therefore the  difference in  the water in the flue gas entering
the CAP island and the water in the gases leaving the CAP island  in the stack gas and CO2
gas streams. The specific enthalpy of  the net condensed water is estimated at 5 °C warmer
than the wet bulb temperature of the flue gas entering the CAP island.

Work  is transferred to the flue  gas and  working  fluids through the action of blowers and
pumps. All this  work is assumed to be powered by  electricity. The electric motors driving
this equipment are assumed to be 95% efficient; 5% of the electric power used is assumed
lost to the ambient environment and  does not contribute  to the energy balance around the
CAP island.

D.9    CO2 SI CONTROL SYSTEM COST ALGORITHM DEVELOPMENT

Sorbent-based CO2 capture can be  developed  in a variety of configurations  to conform to
sorbent properties and market constraints. For this estimate,  sorbent-based CO2 capture is
assumed to utilize  an internally cooled moving bed reactor for CO2  sorption.  Sorbent
regeneration is assumed to require indirect steam  in a separate moving bed reactor. Parallel
to MEA costs, sorbent-based CO2 capture costs will be estimated with two islands: a sorbent
island  and a compressor island. Sorbent island  costs will require inputs  specific to the

	112

-------
Appendix D
sorbent system.  As there is no base plant for comparison, the capital cost for the sorbent
island will be estimated based on major components and modified to a comparable cost by
MEA island. The  costs for compressor island will be modeled in the same way as described
in the MEA process.

The  sorbent  island consists of three major  subsystems: preconditioning, sorption, and
regeneration.

D.9.1  Preconditioning
Preconditioning  is assumed to  be required  for most sorbent applications to  prevent
condensation on  the sorbent. If the absorption temperature is less than 5 °C above the flue
gas supply temperature,  a DCC  is assumed to be  required  to  cool the gas and remove
moisture.  For  absorption  temperatures  greater than  5  °C  above  the   island  inlet
temperature, it is assumed that preconditioning is not required.

During  pretreatment, water  is circulated  through  a  direct  contact  cooler  resulting  in
condensation of  water from the flue gas.  The condensed water is recycled through a heat
exchanger to reduce the water temperature and is  then sprayed back into the direct contact
cooler. A slip stream of condensed water is purged from the direct contact cooler prior to
the heat exchanger.  The heat duty of the heat exchanger is estimated as the  difference
between the enthalpy of the flue gas entering  the  direct contact cooler and the enthalpy of
the gas exiting  the  direct contact cooler plus the enthalpy difference  of the  moisture
condensed in the direct contact cooler. Enthalpy of the  flue gas entering the direct contact
cooler  is calculated based on mass flows and temperatures exiting previous unit operation.
Enthalpy of the gas flow exiting the direct contact cooler is based on the mass flow exiting
the direct  contact cooler assumed to be saturated with water at 5 °C less than the absorber
temperature;  a   35  °C  absorber temperature  would  require  a  30 °C  DCC  exhaust
temperature. Enthalpy of the  moisture condensed from the flue  gas is based on the mass
flow of moisture  condensed and a temperature 5 °C lower than the wet bulb temperature of
the flue gas entering  the DCC. For applications after a wet FGD, the gas entering the DCC is
essentially saturated and  the inlet temperature  is equal to the wet  bulb  temperature.
Though the pretreatment may also involve SO2 polishing, this heat duty is expected to be
inconsequential in comparison with the heat duty  of condensing  water vapor from the flue
gas.

Direct Contact Cooler
Water  recirculating within the DCC is assumed to  be cooled in a counter-current  shell and
tube heat exchanger. Cooling  water is assumed to be available at 16 °C and  is discharged
from the heat exchanger  at 27 °C. Condensed water enters the DCC  5 °C cooler than the
inlet flue gas wet bulb temperature (T-5) and discharges  10 °C  cooler than  the absorber
temperature  (Ta-10). Using an overall heat transfer coefficient  of  1200 J/(m2 s °C), the
surface are of the heat exchanger can be estimated as:
                                                                                113

-------
Appendix D _


            Q   life -10-16)/(7;. - 5 - 27)1
         = -!=—*-^ - ^-^ - ^                               (Eq. D-19)
           1200   (ra -10-ie)- (T; -5-27)

   Q = heat duty in J/s
   Ta = absorber temperature in °C
   Tt = inlet flue gas wet bulb temperature in °C

The maximum surface  area in a single unit is assumed to be 1000 m2. The number of heat
exchangers is estimated  by dividing the total surface area by 1000 m2 and  rounding up to
the next largest integer. The bare module cost  of  these heat exchangers can  then  be
estimated using a power  law:

                        /-  , ,  \O.S6
   Cosf(2002$) = n • 80,000 — ^-                                          (Eq. D-20)
       V      '
where
A= surface area, m2
n=number of exchangers.

DCC Recirculation Pump
The amount of water recirculating through the heat exchangers and to the DCC is calculated
based on the heat duty  of the DCC  and the temperature change  of the water across the
DCC.
                                                                        (Eq.D-21)
               4,187,000

where
Ta= temperature gas at the inlet of absorber, C
Ti=temperature of gas at the inlet of the direct contact cooler, C
Q= heat duty removed by the direct contact cooler, J/Q.

At this level of estimate, a single centrifugal pump is assumed to be associated with each
heat exchanger.

                      /• . \ 0.40
   (2002$) = 71 • 19200*^                                                (Eq. D-22)
Power consumption will depend greatly on the pressure drop through the nozzles and the
type of pump selected. For costing purposes, power consumption will assume an 85% pump
efficiency and a 95% drive efficiency and a 350 kPa  (51 psi) pressure drop.
                                                                               114

-------
Appendix D
    P(kW) = n.   *                                                       (Eq.D-23)
     V   !     0.85.0.95

where
P=power consumption, kW.

D.9.2 Absorber
Though  the absorber  in  a  dry sorbent  system may  be  engineered in a  variety of
configurations, at this time a counter-current moving bed is assumed. Hot sorbent from the
regenerator is assumed to be added to the top of the  moving bed at the regeneration
temperature and  loaded  sorbent removed  from the  bottom of the moving  bed at the
sorption temperature. Conditioned flue gas is assumed to enter the  bottom of the reactor
heated slightly above DCC exhaust due to the compression of a  blower and to exhaust the
absorber at the regeneration  temperature. The absorber is assumed to be cooled with non-
contact  cooling water to cool  the sorbent  from  regeneration temperature to  absorption
temperature and maintain the sorbent at absorption temperature during carbon capture.

Absorber Feed Conveyer
Due to the anticipated conveying capacity, 3-belt conveyors are assumed to collect, raise,
and distribute the absorber  feed for each  conveying  system.  Each conveyer system  is
assumed to be limited to 0.66  m3/s and a 20° incline. Estimating the cost of the absorber
feed conveyer requires  estimation of the  volume of sorbent to  be fed and  the conveying
distance and height. The estimated volume of sorbent to be fed  depends on  estimated CO2
loading and sorbent bulk density which demands the input by the user.

           = CO2 •L/p                                                     (Eq. D-24)

where
V=estimated volume of sorbent to be fed, m3/s
CO2 = removal rate (kg  CO2/s)
L = sorbent loading (kg  CO2/kg sorbent)
p = bulk density (kg sorbent/m3).

Given the user supplied  height [m], the length of the lifting conveyor is:


    D,=	7	r                                                          (Eq. D-25)
      '  sin(20°)

where
AZ=supplied height, m
D|=length of the lifting conveyor, m.
                                                                               115

-------
Appendix D
For estimation purposes, the collection and distribution conveyors are  assumed to run the
length of the absorber. The length of the absorber is estimated with the user supplied face
velocity of the inlet flue gas and an assumed width of 6.1 m (20 ft).
     Dc=Dd=
                                                                          (Eq.  D-26)
where
Dc = length of collection, m
Dd= length of distribution, m
Va = gas volumetric flow into absorber (m3/s)
n = number of conveyor systems
F = face velocity of gas (m/s).

Cost of the entire conveyor system, excluding drive, is estimated as:

    (2002$) = n • [25000 + 2200 • (Dc + D, +Dd)]
                                                                          (Eq.  D-27)
Conveyor Drives
Each conveyor is assumed to be driven by an electric motor. The power for the conveyor is
estimated with  the  length, lift, and loading of the conveyor; conveyor speed is assumed
constant for this estimate. A constant 80% efficiency is assumed for each drive. The power
required for collection and distribution is assumed equal.
    P - P  -
    rc — rd —
3.91 + 0.07245 • D + 0.0295 • 0.4
                                             91.42
                                                    • V • p
                                                   \     '
(Eq. D-28)
where
PC = power for the collection conveyor, kW
Pd = power for the distribution conveyor, kW.

Power required for lifting
         3.91 + 0.07245 •£>, +0.0295*  0.4
                                         91.45
                                                  ' AZ*F*p
                                                                          (Eq. D-29)
where
PI = power of lifting conveyor, kW.

The total cost for drives for conveyers is estimated as:
                                                                          (Eq.  D-30)


                                                                                116

-------
Appendix D
Absorber
At this  stage  of  estimation, the moving  bed costs will  be  based on  the cost  of  heat
exchangers plus the cost of a shell. The cost of the shell will be estimated based on volume.

                   fV   A7^°'55
   (2002$) = 11300* -2-^	                                               (Eq. D-31)
                   \   F  )

where
Va = gas volumetric flow into absorber (m3/s)
AZ = height of the absorber (m)
F = face velocity of gas (m/s).

Absorber costs are assumed to be driven by the heat removal requirement. Heat is removed
with  non-contact cooling water. The  heat duty of the absorber is approximated by the heat
of adsorption and  the sensible heat of the sorbent less the sensible heat of the flue gas.

   Q = Qa+Qs-Qf                                                       (Eq. D-32)

where
Q = total heat, kJ
Qs = adsorption heat, kJ
Qs =  sensible heat of sorbent, kJ
Qt=sensible heat  of the flue gas,  kJ.

The heat of sorption is estimated base on  the required CO2 removal and the user supplied
specific heat of sorption.

   Qa=CO2»AH                                                         (Eq. D-33)

where
Qs = adsorption heat, kJ
CO2 = CO2 removal (kg/s)
AH = specific heat of sorption (J/kg CO2).

The sensible heat  of the sorbent is estimated using the user supplied sorbent heat capacity

   Q,=Cp*V*p*(T,-Ta)                                                (Eq. D-34)

where
Qs= sensible heat of sorbent, kJ
Cp=specific heat capacity, kJ/kg
\/=volume of sorbent per hour

	117

-------
Appendix D
Tr= Temperature at the outlet of regenerator, °C
ra=Temperature at the outlet of the absorber, °C.

Flue gas enters the absorber at a  temperature close to the absorption temperature and exits
the absorber  at  regeneration temperature; there  is heat removal associated with  the
exhausting flue gas.  For estimating  purposes, the sensible heat of the exhaust gas rising
from  the  absorber inlet  temperature to the regeneration temperature  will  be used  to
estimate this heat removal. The sensible heat should  be summed for each component of the
flue gas exhausting the absorber. The heat associated with SOX, NOX, and CO is expected to
be  minimal and/or unaffected  by CO2.  Water condensation  is likely in many sorption
schemes. The condensed water is then evaporated during sorbent regeneration,  which is, in
turn,  condensed in the  reflux to  produce  nearly pure CO2. The heat required and released
from the  absorber and regenerator can be canceled out,  leaving only heat removals across
only the reflux.

                                                                          (Eq.D-35)
where
Qf= sensible heat of the flue gas, kJ
Cp = the specific heat capacity of flue gas component., kJ/kg. °C
m = the mass of the gas component, kg
Tr.= temperature of the flue gas out of the regenerator, °C
TJ= temperature of flue gas after the direct contact cooler, °C.

The heat exchanger surface  areas   are estimated from the  heat removal requirement and
the temperature driving force. The overall heat transfer coefficient is likely a function of the
sorbent and  the gas velocity. The user-specified  heat  transfer coefficient  is  assumed
constant across the absorber for this estimate; a default of 250 J/(m2s °C) will be assumed.
Potential for condensation on heat exchange tubes will be ignored for this estimate.
                         -27)]   (& -Qf)  ln[(rr -27)/fc -16)]
                                                                          \ EU . L^~OO )
      —           7      \                   7       \  7      \
        U         (27-16)           U       (rr-27)-(rfl-16)

where
Qa.= adsorption heat, kJ
U = heat transfer coefficient, default at 250 J/(m2 s °C)
Qs = sensible heat of sorbent, kJ
Qf = sensible heat of the flue gas, kJ
Tr = temperature of the flue gas out of the regenerator, °C
Ta = temperature of the flue gas out of the absorber, °C.

For costing  purposes, the  heat exchange  is assumed to  be  performed in U-tube  heat
exchangers with  a maximum surface area of 1000 m2.

_ 118

-------
Appendix D
    (2002$) = H • 360
                         '74
                                                                          (Eq. D-37)
where
n = number of exchangers
A = total surface area of exchangers, m2
(2002$) = purchase price of the material in 2002 dollars.

D.9.3 Blower/ID Fan
At this stage of costing, a blower is specified based on the anticipated pressure drop across
the absorber bed  without  additional  consideration of  bypassing or system  failure. The
pressure drop across the absorber, AP, will be estimated employing user provided head loss
(Pa/m) across the  sorbent and the user provided sorbent height  (m) used in the absorber
pricing. The blower is assumed to be adiabatic. At this stage, a constant heat capacity ratio
of 1.4 will be used. For cases where the direct contact cooler is used to cool the gas to 5 °C
below the absorber temperature, the fluid power is estimated:
     Wf =
                                    P+AP
                                           ,0.286
                                                                          (Eq. D-38)
where
Wf = work performed by the fan, kW
m = flow rate of the flue gas, kg
R = gas constant, 8.314, JKernel"1
PI = flue gas pressure before the absorber, pa/m
AP = head loss across the absorber, pa/m.

Purchase price of the blower is then estimated as:

    (2002$) =3170 9Wf
                     0.60
                                                                          (Eq. D-39)
The enthalpy (AH) increase of the gas is estimated using a constant efficiency of 80%.
          W^
         0.80
The power consumption (P) will include drive efficiency, assumed to be 95%
                                                                          (Eq. D-40)
                                                                                119

-------
Appendix D
        A TJ
   P = -                                                              (Eq. D-41)
       0.95

D.9.4  Regenerator
Carbon dioxide will  be recovered  in a regenerator, analogous to a stripper for the MEA
process. The gas recovered from the regenerator is expected to consist of nominally the CO2
and water removed by the absorber without significant contamination. At this point, the
regenerator  is expected to rely on temperature  swing with a  regeneration temperature
significantly  higher than the sorption temperature. The regenerator, expected to be large
and capable of accepting solid feed, is expected to operate at near atmospheric pressure.
The  loaded  sorbent  is  expected  to enter the top of the  regenerator at the absorber
temperature and be  heated to near  the regeneration temperature.  For this  estimate,
exhaust gases are assumed to  be withdrawn from below the top of the sorbent bed at
regenerator temperature to avoid potential condensation issues. Lean sorbents are removed
from the bottom  of the regenerator at regeneration temperatures.

Regenerator Feed Conveyer
At this stage, the regenerator is assumed to be the same size and shape as the absorber.
For cost estimates,  the conveyors are assumed to cost the same  as the absorber feed
conveyors.

Conveyor Drives
The cost of  conveyor drives is estimated in the same manner as the absorber conveyor
drives. The sizes of the  conveyor  drives  are expected  to be slightly  larger than estimated
due to the mass of CO2  and water absorbed on the sorbent. The volume of the sorbent is
assumed  to remain  unchanged while the  density increases. Therefore the product of
volumetric flow and density, the  mass flow, is equal to the mass flow of absorbent feed plus
the CO2 and  water absorbed.

Regenerator
The regenerator, comprised of shell and  heat exchanger, is priced in the same way  as the
absorber. The  shell price is  estimated to  be the same  as the absorber shell since they are
assumed to be the same dimensions.
    (2002$) = 11300*  -2-^ -                                              (Eq. D-42)
                   I  F   )
where
Va = gas volumetric flow into regenerator, m3/s
AZ  = height of the regenerator, m
F = face velocity of gas, m/s.

The heat exchanger required to reverse the heat of absorption is calculated as
                                                                               120

-------
Appendix D
    Qr=Qa=CO2*AH                                                     (Eq. D-43)

where
CO2 = CO2 removal, kg/s
AH  = specific heat of sorption, J/kg CO2
Qr=heat required for sorbent regeneration, kJ
Qa=heat released for sorbent absorption, kJ.

The heat exchangers are required to (1) heat the sorbent and absorbed CO2 and water (as
gases) to regeneration temperatures and (2) to reverse the adsorption process.

                                                                          (Eq.D-44)
where
Cp = specific heat capacity, kJ/kg. °C
V = gas volumetric flow into regenerator, m3/s
p = density of the gas, kg/m3
m = mass of the sorbent
Tr= temperature of gas at outlet of the regenerator, °C
Ta= temperature of gas at outlet of the absorber, °C.

At this stage of estimation, heat is  assumed to be provided from  saturated condensing
steam at 150 °C. The overall heat transfer coefficient is assumed to be equal to the overall
heat transfer coefficient used in the absorber.

    A        a      , a*in[(i5o-ra)/(i5o-rr)]
    A= - 7 - r-H -- 7 - r -                            (Eq. D-45)
       tf .(150-7;)         U*(T,-Ta)

where
A = surface area of the exchangers, m2
Tr = temperature of gas at outlet of the regenerator, °C
Ta = temperature of gas at outlet of the absorber, °C
Qr= heat required for sorbent regeneration, kJ
Qa = heat  released for sorbent absorption, kJ
U = heat transfer coefficient, default at 250 J/(m2 s °C).
For costing  purposes,  the  heat exchange  is assumed to be  performed in  U-tube heat
exchangers with a maximum surface area of 1000 m2.

                    (/i Y'74
    (2002$) = n• 360•  —                                                   (Eq. D-46)
                                                                                121

-------
Appendix D
Gas Cooler
A cooler/partial condenser will bring the CO2 and steam down to a low temperature ahead of
compression.  For  this estimate, the gas exit temperature is assumed  to be  21  °C.  The
amount of heat removed is equal to the sensible heat of cooling the CO2 and water vapor
plus the latent heat of condensing the water, 2.541 106 J/kg.

    Q = 2.541. 106 .mwater + ^(c p\ •mi*(T,-2l)                             (Eq. D-47)
mi = mass of the sorbent
Tr = temperature of gas at outlet of the regenerator, °C
Q = heat removed by the exchanger, kJ/s

Cooling water is assumed  to enter the gas cooler at 16 °C and  exit at 27 °C.  For  this
estimate,  an  overall heat transfer  coefficient  of  250 J/(m2s°C)  is assumed. The heat
exchange surface area is estimated assuming countercurrent flow
          C/«(rr-32)
where
A = surface area of the exchangers, m2
Tr = temperature of gas at outlet of the regenerator, °C
Q = heat removed by the exchanger, kJ/s
U = heat transfer coefficient, default at 250 J/(m2 s °C).

The maximum surface area in a single unit is assumed to be 1000 m2. The number of heat
exchangers is estimated  by  dividing the total surface area  of a  unit by  1000 m2  and
rounding up to the next largest integer. The bare module cost of these heat exchangers can
then be estimated using a power law:

                         /-  ,,  \0.86
   Corf(2002$) = n» 80,000 — ^-                                           (Eq. D-49)
        v      '
                                                                               122

-------
Appendix D
REFERENCES

DOE/NETL. 2007. Cost and  Performance Baseline  for  Fossil  Energy Plants  (DOE/NETL-
2007/1281).

EPA, 1996. "Cost-effectiveness of Low-NOx Burner Technology Applied to Phase I, Group 1
Boilers,"  prepared by Acurex  Environmental Corporation for EPA Acid Rain Division. This
report is  available to the public from EPA's Office of Air and Radiation, Acid Rain Division,
Washington, DC 20460 (202-564-9085).

EPRI, 2000.  "Evaluation  of  Innovative Fossil  Fuel  Power Plants with CO2 Removal,"
Document #1000316.  Co-sponsored by Dep't. of Energy (Office of Fossil Energy / NETL)
Interim Report, December 2000. Requests for copies of this report should  be directed to the
EPRI Distribution  Center, 207 Coggins  Drive,  P.O.  Box 23205, Pleasant Hill,  CA 94523,
(800) 313-3774.

EPRI,  2007.  "Chilled  Ammonia  Process  Update,"   May  24,   2007.  Lyon,  France.
http://www.CO2captureandstorage.info/docs/capture/10th%20cap%20network%20web%20
files/K%20-%20Rhudy%20-%20Chilled%20Ammonia%20as%20solvent.pdf

Frey, C.H. and E.S. Rubin,  1994, "Development of the Integrated Environmental Control
Model:  Performance Models of Selective  Reduction (SCR) NOX  Control Systems; Quarterly
Progress  Report to Pittsburgh  Energy Technology Center, U.S. Department of Energy, from
Center for Energy and Environmental Studies, Carnegie Mellon University," Pittsburgh, PA.

Gundappa, M., L. Gideon, and  E. Soderberg,  1995, "Integrated Air Pollution Control System
(IAPCS),  version  5.0,  Volume 2:  Technical  Documentation, Final," EPA, Air and Energy
Engineering  Research Laboratory,  Research  Triangle Park, NC, EPA-600/R-95-169b (NTIS
PB96-157391).

Maxwell,  J. D. and L. R. Humphries, 1985, "Economics of Nitrogen Oxides,  Sulfur Oxides,
and Ash  Control  Systems  for Coal-Fired Utility Power  Plants," Environmental  Protection
Agency, Air and Energy Engineering Research Laboratory, Research Triangle Park, NC,
EPA-600/7-85-006 (NTIS PB85-243103).

Merrow,  E. W., L. McDonnell, and  R. Y. Arguden, 1988. Understanding  the Outcomes of
Megaprojects:  a  Quantitative  Analysis  of Very Large Civilian Projects. Santa  Monica, CA:
RAND Corp.

Presto, A. A., and E. J. Granite, 2006. Survey of Catalysts for Oxidation of Mercury in Flue
Gas. Environmental Science &  Technology 40 (18):5601-5609.

Rao, Anand. 2002. A Technical,  Economic and Environmental Assessment of Amine-Based
CO2 Capture Technology for Power Plant Greenhouse Gas Control.  DOE Contract No.: DE-
FC26-OONT40935

	123

-------
Appendix D
Robie,  C.P. and  P.A. Ireland, 1991, "Technical Feasibility and Cost of Selective Catalytic
Reduction  (SCR)  NOX  Control,"  GS-7266,  Prepared  by  United  and  Engineers  and
Constructors, Inc. for the Electric Power Research Institute, Palo Alto, CA.

Rubin,  E. S., M. Antes, S. Yeh, and M. Berkenpas, 2006. Estimating the Future Trends in the
Cost of CO2 Capture Technologies. Report No.  2006/6. Cheltenham, UK: IEA Greenhouse
Gas R&D Programme (IEA GHG).

Sherrick, B.;  Hammond, M.; Spitznogle, G.; Murashin,  D.; Black, S.; Cage,  M., 2008. CCS
with Alstom's Chilled Ammonia Process at AEP's Mountaineer Plant. Presented in the Power
Plant Mega Symposium. Baltimore, MD. 2008

Staudt, J.E.; Jozewicz, W.; Srivastava, R., 2003.  Modeling Mercury Control  with Powdered
Activated  Carbon, AWMA  Paper 03-A-17-AWMA.  Presented  at the Joint EPRI DOE  EPA
Combined Utility Air Pollution Control Symposium, The Mega Symposium, May 19-22, 2003,
Washington, D.C.

Taylor,  M., E. S. Rubin, and D.A Hounshell, 2003.  The effect of  government actions on
technological  innovation for SO2 control. Environmental  Science & Technology 37 (20):4527
- 4534.

Ulrich,  Gael D., 1984. A guide to Chemical Engineering Process Design and Economics, John
Wiley and Sons, Inc., New York, NY.

Wright, T. P.  1936. Factors affecting the cost of airplanes, Journal of Aeronautical Sciences,
3 (2):122-128.
                                                                                124

-------
Appendix E
E.I    GETTING STARTED

After downloading the workbook to the hard drive, the first thing to do is to  create a copy of
the workbook and save  it under a  different  name. Once the workbook has been saved to the
hard  drive,  it can be opened using Microsoft Excel 5.0 or a newer version of  Excel.

The workbook will  originally open to  the "1.0 General Input Sheet". This is the  worksheet
where all of the  necessary inputs are entered. However, a  main  menu is  created for the user
where all of the  sheets are linked with buttons. The screen the user will encounter is:

                                             Main Menu
                Air Pollution Control Technology,
                                     1.0 Economic INPUT
                                  2,0General PlantlNPUT
                          3.0 Air Pollution Control Technologies!
                                                                      10.0 Leuelization CALCULATIONS
                                                                   4.0 Power Generation CALCULATIONS
     Go To Main Menu
               INPUT Selections  Print Functions
            Kyi Irptjf output * FrsntButftrK*
        Go to TOP OUTPUT Se|ect!ons
3.1 NOX Control INPUT j

 3.2PM Control INPUT!

 3.3 SO2 Control INPUT |

 3.4 Hg Control INPUT;


 3.5 CO2 Control INPUT!
5.0 NOX Control CALCULATIONS

 i.O PM Control CALCULATIONS

7.0 SO2 Control CALCULATIONS

 8.0 Hg Control CALCULATIONS


9,8 CO2 Control CALCULATIONS
                                                                                               125

-------
Appendix E
E.2    INPUTS

As  the  user  proceeds  down  following  the  menu,  (s)he  will  encounter  the  following
worksheets:

•   Power Generation Technique Choices
•   Air Pollution Control (APC) Technology Choices
•   General Plant Technical Inputs
•   Economic Inputs
•   Limestone Forced Oxidation (LSFO) Inputs
•   Lime Spray Dryer (LSD) Inputs
•   Particulate Control Inputs
•   NOX Control Inputs
•   Hg Control Technology Inputs
•   CO2 Control Amine Technology Input

E.2.1  Economic Inputs
This  is the area  of the worksheet where the economic factors  are input. These factors are
used in developing  the  capital and O&M costs for the control technologies.
Item/Description                            Units
Economic Factor
  Cost Basis -Year Dollars                       year-
  Service Life (Levelization Period)                  years
  Sales Tax                                %
  Escalation/Inflation Adjustment (GDP or Chern Index)   ^

    Construction Labor Rate                     S/h
    Prime Contractor's Markup                     %
    Inflation Rate                            %
    Escalation Rate                           %
  Capital Carrying Charges
    First-year Carrying Charge (Current S's)             %
    Levelized Carrying Charge (Constant S's)             %

  Non-Carrying Expense (OS.M)
    Levelizing Factor (L30) (Constant S's}

  Variable Cost Factors
    Operating Labor Rate (include benefit)             S/h
    Power Cost                            Mills/kWh
    Steam Cost                            s/1000 Ibs
    Demineralized Water                        s/!b
    Makeup Water                          s/1000 Ib
                                              Range
                                                      Default
Calculator
2006
30
6%
GDP
S35
3%
2%
3%
9%
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
          S25.0
           60
           3.5
         SO.0030
          SO.05
User needs to  click the icon of calculator, a quick worksheet pops  up to facilitate calculating
carrying charges and levelization factors.
                                                                                              126

-------
Appendix E
INPUT	

Factors during Operation (for Carrying Charge and levelization)
  Return of Debt
  Ratio of Debt
  Return of Equity
  Ratio of Equity
  Property Taxes and Insurance
  Income Tax
  Investment Tax Credit
  Book life of the Piant
  Average (price) Inflation rate (Long-Term)
  Depreciation method
   (1= 30 Yr Straight Line; 2=30 Yr Straight Une;3=2Q Yr ARCS Schedule)
  Consumables (O&.M) Escalation
                          3
                                     3
                                                          50%
                                                          10%
                                                          30
                                                          3%
                                                               50%
                                                               10%
                                                               50%
                                                   50%
                                                   10%
                                                    30
OUTPUT
Carrying Charges
  First-year Carrying Charge (current S's)7"
  Levefszed Carrying Charge (current S's)
  First-year Carrying Charge (constant S's)
  Leveiized Carrying Charge (constant S's)*
Non-Carrying Expense
  Levelizing Factor (L30) (Current S's) ( for O&M)
  Levelizing Factor (L3Q) (Constant S's) ( for O&M)*
                  15.9%  15.9% IS.9% 15.9%  15.9%
                  11.4%  11.4% 11.4% 11.4%  11.4%
                  11.7%  11.7% 11.7% 11.7%  11.7%
                   8.3%  8.3%  8.3%  8.3%  8.3%
                   2.08
                   1.49
            2.08
            1.49
       2.08
       1.49
2.08
1.49
2.08
1.49
15.9%
11.4%
11.7%
8.3%

2.08
1.49
                                        15.9% 15.9%  15.9%
                                        11.4% 11.4%  11.4%
                                        11.7% 11.7%  11.7%
                                        8.3%  8.3%  8.3%
2.08
1.49
2.08
1.49
2.08
1.49
£.2.2  Power Generation Technique Choices
This  is  the  area  of  the  worksheet  where  the  user  can  choose  what  power  generation
technique  will  be  evaluated.  The  following  screen  shows how  this area  looks  and  what
options are available.
               t->Zitfj ^rKt Tec lire \-t;,;
ItemfDescription
Plant Information
  Cost Basis -Year (For Power Generation Estimation only)
  Location - State
  Power Generation Technologies

  General Plant Factors
   Gross Plant output
   Net PI ant Output
   Plant Heat Rate
   Plant Capacity Factor
  Coal Type

   Price of Coal
  Other Operating Information
   Percent Excess Air in Boiler
   Uncontrolled NOx from Boiler
   Air Heater Inleakage
   Air Heater Outlet Gas Temperature
   Inlet Air Temperature
   Ambient Absolute Pressure
   Pressure After Air Heater
   Moisture in Air
   Ash Split:
     Fly Ash
   Seismic Zone
   Conversion of SO2 to SO3
                                                      Units
                                                                Range
500-800
500-750
  MW
  MW
 BtufkWh
   K        40-90%
   Goto Coal Data
   *F
   T
  in. Hg
 in. HjO
Ibrflb dry air
 integer
                       Default

                        2005
                         PA
                         1
  580
  500
 10,500
  65%
   5

  2.05

 120%
algorithm
  12%
  300
                                                                                                    Case 2
                                                                                                                 Case 3
              1-5
            80%
              1
            1.0%
D
D
3
|l=Suberitical; 2=Sup<
580
D
D
D
2
D
D
2
srCritical;
580
D
D
D
2
D
D
2
3=Ultra-SuperCritic
580
D
D
D
2
See Coal Tupes
D
D
, " D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
£.2.3  APC Technology Choices
This  is the  area  of the worksheet  where the  user can  choose what control technologies are
needed. The following screen shows how this area looks and  what options are available.
                                                                                                                   127

-------
Appendix E
APC Technology Choices
NOx Control
Combustion Control (0=no additional control, 1 = combustion control)
Post Combustion Control (0=none. 1 = SCR, 2 = SNCR, 3 « NGR)
Particular Control (0= none. 1 = Fabric Filter, 2 = ESPc. 3=ESPh]
SO2Control
(0=none, 1 = LSFQ, 2 = LSD]
Additional Mercury Control with Sorbent Injection?
(0=no, l=yes)
If Sorbent Injection, add downstream PJFF?
(0=no, 1=PJFF)
CO2 Control (0-none, 1-CAP, 2-MEA, 3-Sorbent)


integer
integer
integer
integer

integer

integer

Integer


0,1 1
0, 1, 2, 3 1
0, 1, 2, 3 2
0, 1, 2 1

Oorl 1

Oor1 1

0, 1, 2, 3 1


1111
1111
1111
1111

1111

1111

1311
E-2.4   NOX Control Inputs

Data necessary  for sizing and costing  the NOX control  processes  are input in the  worksheet
below.  This  information  is used  with  the  combustion  calculations  to  size  one of the  four
processes.
3.1 NOX Control Technoloy

I temf Descri pti on
Combustion Technology Selected?
  Uncontrolled NQx level
  Boiler Type
  Burner Type
  Retrofit Difficulty Factor
  General Facilities
  Engineering
  Contingency
  Duration of Project

SCR Technology Selected?
  inlet NOx level
  Nr-yNQxStoichiometric Ratio
  NOK Reduction Efficiency
  Space Velocity (Calculated if zero)
  Time to First Catalyst Replenishment
  Ammonia Cost
  Catalyst Cost
  Solid Waste Disposal Cost
  Retrofit Difficulty Factor
  General Facilities (% of Installed Cost)
  Engineering Fees (% of Installed Cost)
  Contingency (% of Installed Cost)
  Duration of Project
  Maintenance (% of Installed Cost)
  Co-benefit Application
   Mercury Oxidation Rate - bituminous coal
   Mercury Oxidation Rate - subbiluminous coal

SNCR Technology Selected?
  Inlet NOx level
  Reagent
              Range
  IWMMBtu
   W:Wall
2=LNB and OF A
   number
   percent
   percent
   percent
    years
  IWMMBtu
   NH^QK
   Fraction
    years
    $Kon
 0.740
0.60-0.90
               2-5
  IWMMBtu
   integer    Urea 2:Arnrnoni
Default

calculated
T
1
1.3
5.0%
10.0%
15.0%
1

calculated
0.9
0.90
0
3
400
5000
11.48
1.5
5%
10%
15%
2
0.66%
90.0%
0.0%

calculated
1
Casel
Selected
D
D
D
D
D
D
D
D
Selected
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
Ci
Not Selected
D
D
Case 2
Selected
D
D
D
D
D
D
D
D
Selected
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
Not Selected
D
D
Case 3
Selected
D
D
D
D
D
D
D
D
Selected
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
Not Selected
D
D
                                                                                                                       128

-------
Appendix E
£.2.5 Particulate Control Inputs
Data  necessary  for sizing  and costing  the  participate control equipment are input into  the
worksheet below. This information  is used with the combustion  calculations to  size either an
ESP or FF.
3.2 PM Control Technology

ItemlDescription

Outlet Particulate Emission Limit

Fabric Filler Selected
  Pressure Drop
  Type (1 = Reverse Gas, 2 = Pulse Jet)
  Gas-to-Cloth Ratio
  Bag Material (RGFF fiberglass only)
   (1 = Fiberglass, 2 = Nomex, 3 = Ryton)
  Bag Diameter
  Bag Length
  Bag Reach
  Compartments out of Service
  Bag Life
  Retrofit Factor
  Contingency (% of installed cost)
  General Facilities (% of installed costj
  Engineering Fees (% of installed cost)
  Project Duration
  Maintenance (% of installed cost)

ESP Selected
  Strength of the electric field in the ESP = E
  Plate Spacing
  Plate Height
  Pressure Drop
  Retrofit Factor
  Contingency (% of Installed Cost]
  General Facilities (% of Installed Costj
  Engineering Fees (% of Installed costj
  F'roiect Duration
 Units

Ibs/MMBtu
 in. H2D
 Integer
 ACFMft!
 Integer

 inches
  feet
           Range
   fl.
 in. HjD
Default

 0.03
  6
  2
  3.5
  2

  6
  20
  3
 10%
  5
  1.3
 15%
 10.0
  12
  36
  3
 1.3
 15%
 5%
 10%
  2
 Selected
    D
    D
    D
    D

    D
    D
    D
    D
    D
    D
    D
    D
    D
    D
    D

Mot Selected
    D
    D
    D
    D
    D
    D
    D
    D
    D
Case 2
D
Selected
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
Not Selected
D
D
D
D
D
D
D
D
D
CaseS
D
Selected
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
Not Selected
D
[i
D
D
D
D
D
D
D
£.2.6  SO2 Control Inputs
Data  necessary for sizing  and costing  an  SO2 control system  are  input into the worksheet
below. This information  is used with the combustion calculations to design the system.
                                                                                                         129

-------
Appendix E
3.3 SO2 Control Technology

I temlDescri pli on
Lime Spray Dryer Selected?
 SQz Removal Required
 is SDA being retrofit upstream of existing ESP? [0 = no, 1 = yes)
 Adiabatic Saturation Temperature
 Flue Gas Approach to Saturation
 Recycle Slurry Solids Concentration
 Number of Absorbers
  (Max. Capacity = 300 MW per spray dryer)
 Absorber Material
  (1 = Alloy,2 = RLCS)
 Spray Cooler Pressure Drop
 Reagent Bulk Storage
 Reagent Cost (delivered)
 Dry Waste Disposal Cost
 Retrofit Factor
 Contingency (% of installed Cost)
 General Facilities (% of installed Cost)
 Engineering Fees (% of Installed Cost)
 Project Duration
 Maintenance Factor (% of TPC)

LSFO Selected?
 Year Equipment Placed in Service
 SOS Removal Required
 UG Ratio
 Design Scrubber with Dibasic Acid Addition?
  (1 = yes, 2 = no)
 Adiabatic Saturation Temperature
 Reagent Feed Ratio
integer
  *F
  T
Wt. %
integer

integer

in. H£l
 days
 IKon
                                                               Range

                                                               70-95%
                                                                0,1
                                                               100-170
                                                               10-50
                                                               10-50
                                                                1-7

                                                               1or2
Default

 90%
  0
  127
  20
 35%
  1
                                                                            1
                                                                           30
                                                                           $65
                                                                           $30
                                                                           1.3
                                                                           15%
                                                                           5%
                                                                           10%
    Casel
Not Selected
     D
     D
     D
     D
     D
     D
   Case 2       Case 3
Not Selected   Not Selected
     D           D
     D           D
     D           D
     D           D
     D           D
     D           D
Selected
year
%
gal I 1000 acf
integer
T
Factor

90-98%
95-160
1or2
100-170
1.0-2.0
2004
95%
125
1
127
1.05
D
D
D
D
D
D
Selected
D
D
D
D
D
D
Selected
D
D
D
D
D
D
E.2.7  Mercury Control Inputs
This  is  where  the data  necessary  for  sizing  and  costing the  mercury control processes are
input. This information  is  used  with the  combustion calculations to size powdered activated
carbon  (PAC) and  pulse-jet fabric filter (PJFF) processes.
                                                                                                                   130

-------
Appendix E
3.4  Mercury Control Technology

ltem4Description                                           Units
Sorbent Injection Technology Selected?
   HgCEMS lo-no, 1-yes)                                    integer
   Hg Reduction Required from Coal                             percent
   Sorbent Type, 1-EPAC, 2-PAC, 3=olher
   Maximum Temperature before Spray Cooling                        T
   Sorbent Recycle Used?                                     Yes/No
   Spray Cooiing Desired?                                     Yes/No
   EPAC Cost (Delivered Cost of Treated PAC)                        »on
   PAC Cost (Delivered)                                      Won
   Other Sorbent Cost (Del i vered]                                Van
   Before Sorbent Injection, Fly Ash Sold (1) or Disposed of (2]              1 or 2
   Does Sorbent Adversely Impact Fly Ash Sales? (0=no, 1=yes)            integer
   Revenue from Fly Ash Sales                                 &Son
   Dry Waste Disposal Cost                                    Won
   Retrofit Factor
   Process Contingency, % of Process Capital                         %
   General Facilities [% of Installed Cost)                            %
   Engineering Fees (% of Installed Cost)                            %
   Project Contingency                                        %
   Duration of Project                                        years
   Maintenance Factors (% of Installed Cost]                          %

PJFF Downstream of PAC Selected?
   PJFF to COHPAC (ie, TOXECON), 0=no, 1=yes                      0 or 1
   Cost of Bags, I nstal I ed (Ubag)                                 Jfcag
   Estimated SElagsMW                                      integer
   Average Bag Life                                         years
   Pressure Drop                                           in. H2O
   Outlet Emissions                                        Ib/MMBtu
   Retrofit Difficulty Factor
   Process Contingency, % of Process Capital                         %
Range

 Oor1
 M25
 Oor1
 Oto35
 1to25
Default

1
0.8
2
325
No
No
1500
1000
1000
1
0
6
6
1.3
5%
5%
10%
15%
1
5%

1
80
20
5
a.o
0.012
1.3
5%
Casel
Selected
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
Selected
D
D
D
D
D
D
D
D
Case 2
Selected
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
D
Selected
D
D
D
D
D
D
D
D
 Case 3
Selected

   D
   D
   D
   D
   D
   D
   D
   D
   D
   D
   D
   D
   D
   D
   D
   D
   D
   D
   D

Selected
   D
   D
   D
   D
   D
   D
   D
   D
£-2.8   CO2 Control Inputs
This  is  where the data necessary for sizing  and  costing the CO2 control  processes  are input.
This  information is  used  with  the combustion  calculations  to  size  amine-based CO2  control
processes.
                                                                                                                       131

-------
Appendix E
3.5 Carbon Dioxide Control Technology

i ' ' f i1' ^ ^ i 11 r t ' i* } ^ *t IK , o ' f lin k * •(
1 temfDescri pti an
Chilled Ammonia Process Selected?
Efficiency of COj removal
Flue gas temperature out of direct contact cooler
Rue gas temperature entering Hie absorber
Flue gas temp exiting the absorber
CO; temperature exiting the stripper reflux
Cycle of Concentration for Cooling Water
Reagent of Ammonia
Concentration of Ammonia
Price of Ammonia (28%)
Ammonia slip to flue gas
Regenerator Pressure
Compressor
CO; Product Pressure
CO2 compressor stage
Number of operator
Retrofit Factor
Maintenance Factor (% of TPC)
Contingency (% of installed Cost)
General Facilities (% of Installed Cost)
Engineering Fees (% of Installed Cost)
Time for Retrofit
MEA Process Selected?
Efficiency of CO; removal
KS-lorOtherMEA
Cycle of Concentration for Cooling Water
Reagen Price
Price of ME A
Price of NaOH ( 20% solution)

i' 1 llf ' *v , ' l' 4
Units

%
T
T
T
T


%
Won
ppm
Psi

psi



%
%
%
%
years

%
1=KS-1, 2= MEA


Bon
Won

iin k * ^ ' t . i
Range

MO
35
30-32
32-50
65-72
2-10

28-30%
100-200
2-10
300-600

500-2500
3
6-8







90%

2-10




l\t I L *l V ^
Default

90%
35
32
35
70
5

28%
150
5
400

2200
3
8
to
3%
15%
10%
7%
2

90%
1
5

2142
413

i 1 I Jl 1 >'t r •}
Casel
Selected
D
D
D
D
D
D

D
D
D
D

D
D
D
D
D
D
D
D
D
Not Selected
D
1
D

D
D

1, t 1 ilr 1 i ^
Case 2
Not Selected
D
D
D
D
D
D

D
D
D
D

D
D
D
D
D
D
D
D
D
Not Selected
D
2
D

D
D

t ' »«• i *
Case3
Selected
D
D
D
D
D
D

D
D
D
D

D
D
D
D
D
D
D
D
D
Not Selected
D
1
D

D
D
                                                                            132

-------
Appendix F
The  programs included in this appendix  are for calculations of  economic  parameters,
including the  TEC, TPI, current $  carrying charge, constant $  carrying charge, first year
current $ carrying charges, first year constant $ carrying charges, and levelization factors.
Comments were added  in each program for clarity.
'This module contains functions to calculate the Economic parameters
'This function calculates TCE value
'Arguments:  inflation rate, float; escalation, float; period, float
Function TCE (inflation, escalation, period)
 EA = (1 + inflation) x (1 + escalation) -  1
 TCE = PV(EA, period,  -1) x (1 + EA) / period
End Function

'This function calculates TPI value, the parameters
'Inside the parenthesis already show what you should input
Function TPI(inflation,  escalation, interest, period)
 EA = (1 + inflation) x (1 + escalation) -  1
 Z = (1  + interest)/ (1 + EA)
 TPI = (Z A  period - 1)
 TPI = TPI / period
 TPI = TPI / (Z - 1)
End Function

'This function calculates Current Carrying  Charge
'Arguments:  rd (cost of debt), float;  wd(ratio of debt), float; re(cost of equity), float;
'we (ratio of equity), float;PTI (property tax and insurance), float; T ( tax), float;
'ITC (investment tax credit), float; BL(book life), float; depreMethod (depreciation method"),
integer
                                                                                    133

-------
Appendix F
Function CurrentCC(ByVal rd, ByVal wd, ByVal re, ByVal we, ByVal PTI, ByVal T, ByVal ITC,
ByVal BL, ByVal depreMethod)
 rd = rd
 wd = wd
 re = re
 we = we
 PTI = PTI
 T = T
 ITC = ITC

 Dim Arcs(21) As Double
 'Define depreciation rate for each year
 Dim Depr(31) As Double
 'Loop variable
 Dim i As Integer
 'Calculate  the weighted average cost of capital (WACC)
 Dim EFI As Double
 'Straight line depreciation
 Dim sltxdp As Double
 sltxdp = 1 / BL
 'Cumulative CC x  V in the EPRI formula
 'Detail of the original formula can be seen in TAG-Technical Assessment Guide, Vol. 3,
 'Fundamentals and Methods, Supply-1986, EPRI P-4463-SR
 Dim SP As Double
 SP = 0
 V current value factor in the EPRI formula
 Dim V As Double
 'Deferred income tax
 Dim DT As Double
 'tax paid
 Dim TP As Double
 'tax depreciation rate
 Dim TD As Double
 'Carrying charge
 Dim cc As Double
 'An annuity factor in EPRI formula
 Dim A As Double
 'temp variable of rd
 Dim rdTemp As Double
 'temp variable of re
 Dim reTemp As Double
 'Book depreciation rate net of ITC
 Dim BD As Double
 BD = (1 -  ITC)/ BL

	134

-------
Appendix F
  'Remaining book value
  Dim SB As Double
  SB = 1 - ITC
  'Assign value to ACRS schedule
  Arcs(O) = 0
  Arcs(l) = 7.5
  Arcs(2) = 6.9
  Arcs(3) = 6.4
  Arcs(4) = 5.9
  Arcs(5) =5.5
  Arcs(6) = 5.1
  Arcs(7) = 4.7
  Arcs(8) = 4.5
  Arcs(9) = 4.5
  Arcs(lO) = 4.5
  Arcs(ll) = 4.5
  Arcs(12) = 4.5
  Arcs(13) = 4.5
  Arcs(14) = 4.5
  Arcs(15) = 4.5
  Arcs(16) = 4.4
  Arcs(17) = 4.4
  Arcs(18) = 4.4
  Arcs(lO) = 4.4
  Arcs(20) = 4.4
  'Assign value 0 to initialize the array
  A = 0#
  'Compute return rate used to determine carrying charges
  EFI = (wd x  rd + we x  re)
  For i =  LBound(Depr) To UBound(Depr)
  Depr(i) = 0
  Next i
  'Calculate tax depreciation with 3 cases, we assume that the book life is greater than the
depreciation life
  'Calculate straight line tax depreciation
  If (depreMethod = 1) Then
  'For straight line tax depreciation over book life
  For i = 1 To BL
   Depr(i) = 1 / BL
  Next i
  'For straight line tax depreciation over ACRS
  Elself (depreMethod = 2) Then
  For i = 1 To 20
   Depr(i) = 1/20

	135

-------
Appendix F
  Next i
  'ForACRS depreciation schedule
 Else
  For i = 1 To 20
   Depr(i) = Arcs(i) / 100
  Next i
 End If

 'Start loop  over the book life
 For i = 1 To BL
  'Present value factor
  V = (1 + EFI) ^ (-i)
  If (EFI <> 0)  Then
   A= (1-V)/(EFI)
  Else
   A = i
  End If
  'tax depreciation rate
  TD  =  Depr(i)
  'return on  equity
  reTemp =  SB x re x we
  'return on  debt
  rdTemp =  SB x rd x wd
  'deferred income tax
  DT  =  (TD - sltxdp) x T
  'tax paid.
  TP = T / (1 - T) x (BD - TD + DT + reTemp)
  ' year by year carrying charges
  cc = BD + DT + rdTemp + reTemp + TP + PTI
  'cum. present value of carrying charge
  SP = SP + cc x V
  'Depreciation  book value, net def.  tax
  SB  =  SB - BD -  DT
 Next i
 'earn/Charges  =  SP / A
 CurrentCC  = SP / A
 End Function
'This function calculates  first year Current Carrying Charge
'Arguments: rd  (cost of debt), float;  wd(ratio of debt), float; re(cost of equity), float;
'we (ratio of equity), float;PTI (property tax and insurance), float; T ( tax), float;
'ITC (investment tax credit), float; BL(book life), float; depreMethod (depreciation method),
integer
                                                                                 136

-------
Appendix F
Function firstYearCurrentCC(ByVal rd, ByVal wd, ByVal re,  ByVal  we,  ByVal  PTI, ByVal T,
ByVal ITC, ByVal BL, ByVal depreMethod)

 rd = rd
 wd = wd
 re = re
 we = we
 PTI = PTI
 T = T
 ITC = ITC

 Dim Arcs(21) As Double
 'Define depreciation rate for each year
 Dim Depr(31) As Double
 'loop variable
 Dim i As Integer
 'Calculate the weighted average cost of capital (WACC)
 Dim EFI As Double
 'straight line depreciation
 Dim sltxdp As Double
 sltxdp =  1 / BL
 'cumulative CC x V in the EPRI formula
 'Detail of the original formula can be seen in TAG-Technical Assessment Guide, Vol. 3,
 'Fundamentals and Methods, Supply-1986, EPRI P-4463-SR
 Dim SP As Double
 SP = 0
 'V current value factor in the EPRI formula
 Dim V As Double
 'deferred income tax
 Dim DT As Double
 'tax pa id.
 Dim TP As Double
 'tax depreciation rate
 Dim TD As Double
 'Carrying charge
 Dim cc As Double
 'A annuity factor in EPRI formula
 Dim A As Double
 'temp variable of rd
 Dim rdTemp As Double
 'temp variable of re
 Dim reTemp As Double
 'book depreciation rate net of ITC
 Dim BD As Double

	137

-------
Appendix F
 BD = (1 - ITC)/ BL
 'remaining book value
 Dim SB As Double
 SB = 1 - ITC
 'assign value to ACRS schedule
 Arcs(O) = 0
 Arcs(l) = 7.5
 Arcs(2) = 6.9
 Arcs(3) = 6.4
 Arcs(4) = 5.9
 Arcs(5) =5.5
 Arcs(6) = 5.1
 Arcs(7) = 4.7
 Arcs(8) = 4.5
 Arcs(9) = 4.5
 Arcs(lO) = 4.5
 Arcs(ll) = 4.5
 Arcs(12) = 4.5
 Arcs(13) = 4.5
 Arcs(14) = 4.5
 Arcs(15) = 4.5
 Arcs(16) = 4.4
 Arcs(17) = 4.4
 Arcs(18) = 4.4
 Arcs(lO) = 4.4
 Arcs(20) = 4.4
 'assign value 0 to initialize the array
 A = 0#
 'compute return rate  used to determine carrying charges
 EFI = (wd x  rd + we  x re)
 For i =  LBound(Depr) To UBound(Depr)
  Depr(i) = 0
 Next i
 'calculate tax depreciation with 3 cases, we assume that the book life is greater than the
depreciation life
 'calculate straight line tax depreciation
 If (depreMethod = 1) Then
  'for straight line tax depreciation over booklife
  For i = 1 To BL
   Depr(i) = 1 / BL
  Next i
  'for straight line tax depreciation over ACRS
 Elself (depreMethod = 2) Then
  For i = 1 To 20

	138

-------
Appendix F
   Depr(i) = 1/20
  Next i
  'for ACRS depreciation schedule
 Else
  For i  = 1 To 20
   Depr(i) = Arcs(i) / 100
  Next i
 End If
 For i = 1 To 1
  'Prsent value factor
  V = (1 + EFI) ^ (-i)
  If (EFI <> 0) Then
   A=  (1-V)/(EFI)
  Else
   A =  i
  End If
  'tax depreciation rate
  TD = Depr(i)
  'Return on equity
  reTemp = SB  x re x we
  'Return on debt
  rdTemp = SB  x rd x wd
  'Deferred income tax
  DT = (TD - sltxdp) x T
  'tax paid.
  TP = T / (1 - T) x (BD - TD + DT + reTemp)
  ' Year by year carrying charges
  cc =  BD + DT + rdTemp + reTemp + TP + PTI
  'cum. present value of carrying charge
  SP = SP + cc x V
  'Depreciation book value, net def.  tax
  SB = SB - BD - DT
 Next i
 'carryCharges = SP / A
 firstYearCurrentCC = SP/ A
 End Function
                                                                               139

-------
Appendix F
'This function calculates constant Carrying Charge
'Arguments: rd (cost of debt), float; wd(ratio of debt), float; re(cost of equity), float;
'we (ratio of equity), float;PTI (property tax and insurance), float; T ( tax), float;
'ITC (investment  tax  credit),  float;  BL(book life),  float; inflation, float;  depreMethod
(depreciation method), integer

Function ConstantCC(ByVal rd,  ByVal  wd, ByVal re, ByVal we, ByVal PTI,  ByVal T,  ByVal
ITC, ByVal BL, ByVal inflation, ByVal depreMethod)

 rd = rd
 wd = wd
 inflation = inflation
 re = re
 we = we
 PTI = PTI
 T = T
 ITC = ITC

 Dim Arcs(21) As Double
 'Define depreciation rate for each year
 Dim Depr(31) As Double
 'loop variable
 Dim i As Integer
 'Calculate the weighted average cost  of capital (WACC)
 Dim EFI As Double
 'Straight line depreciation
 Dim sltxdp As Double
 sltxdp = 1 / BL
 'Cumulative CC x V in the EPRI formula
 'Detail of the original formula can be seen in TAG-Technical Assessment Guide, Vol. 3,
 'Fundamentals and Methods, Supply-1986, EPRI P-4463-SR
 Dim SP As Double
 SP = 0
 'V current value factor in the EPRI formula
 Dim V As Double
 'Deferred income tax
 Dim DT As Double
 'tax paid.
 Dim TP As Double
 'tax depreciation rate
 Dim TD As Double
 'Carrying charge
 Dim cc As Double
 'An annuity factor in EPRI formula

	140

-------
Appendix F
 Dim A As Double
 'temp variable of rd
 Dim rdTemp As Double
 'temp variable of re
 Dim reTemp As Double
 'book depreciation rate net oflTC
 Dim BD As Double
 BD = (1  - ITC)/ BL
 'Remaining book value
 Dim SB As Double
 SB = 1 - ITC
 'Assign value to ACRS schedule
 Arcs(O) = 0
 Arcs(l) = 7.5
 Arcs(2) = 6.9
 Arcs(3) = 6.4
 Arcs(4) = 5.9
 Arcs(5) =5.5
 Arcs(6) =5.1
 Arcs(7) = 4.7
 Arcs(8) = 4.5
 Arcs(9) = 4.5
 Arcs(lO) = 4.5
 Arcs(ll) = 4.5
 Arcs(12) = 4.5
 Arcs(13) = 4.5
 Arcs(14) = 4.5
 Arcs(15) = 4.5
 Arcs(16) = 4.4
 Arcs(17) = 4.4
 Arcs(18) = 4.4
 Arcs(lO) = 4.4
 Arcs(20) = 4.4

 'Assign value 0 to annuity
 A  = 0#
 'Compute return rate used to determine carrying charges
 'Calculate rd and re without inflation
 rd = (1 + rd) / (1 +  inflation) - 1
 re = (1 + re) / (1 +  inflation) - 1
 EFI = wd x  rd + we  x re
 'Initialize depreciation value in the depreciation array.
 For i = LBound(Depr) To UBound(Depr)
  Depr(i)  = 0
                                                                                  141

-------
Appendix F
 Next i
 'Calculate tax depreciation with 3 cases, we assume that the book life is greater than the
depreciation life
 'Calculate straight line tax depreciation
 If (depreMethod = 1) Then
  'For straight line tax depreciation over book life
  For i = 1 To  BL
   Depr(i) = 1  / BL
  Next i
  'For straight line tax depreciation overACRS
 Elself (depreMethod = 2) Then
  For i = 1 To  20
   Depr(i) = 1/20
  Next i
  'forACRS depreciation schedu\e
 Else
  For i = 1 To  20
   Depr(i) = Arcs(i) / 100
  Next i
 End If
 'start the loop over the book life
 For i = 1 To BL
  'Present value  factor
  V = (1 + EFI) ^ (-i)
  If (EFI <> 0) Then
   A=  (1-V)/(EFI)
  Else
   A =  i
  End If
  'Tax depreciation rate
  TD =  Depr(i)
  'return on equity
  reTemp = SB x re x we
  'return on debt
  rdTemp = SB x rd x wd
  'Deferred income tax
  DT =  (TD - sltxdp) x T
  'tax paid.
  TP = T / (1 - T) x (BD - TD  +  DT + reTemp)
  'Year by year carrying charges
  cc =  BD + DT + rdTemp + reTemp + TP + PTI
  'Cum. presents value of carrying charge
  SP = SP + cc x V
  'Depreciation book value, net def. tax

                                                                                 142

-------
Appendix F
  SB = SB - BD - DT
 Next i
 'carryCharges = SP / A
  ConstantCC = SP / A
 End Function
'This function calculates first year Current Carrying Charge
'Arguments: rd (cost of debt), float; wd(ratio of debt), float; re(cost of equity), float;
'we (ratio of equity), float;PTI (property tax and insurance), float; T ( tax), float;
'ITC (investment  tax  credit),  float;  BL(book life),  float; inflation, float;  depreMethod
(depreciation method), integer
Function  firstYearConstantCC(ByVal rd, ByVal wd, ByVal re, ByVal we, ByVal  PTI, ByVal T,
ByVal ITC, ByVal BL, ByVal inflation, ByVal depreMethod)

 rd = rd
 wd = wd
 inflation = inflation
 re = re
 we = we
 PTI = PTI
 T = T
 ITC = ITC

 Dim Arcs(21) As Double
 'Define  depreciation rate for each  year
 Dim Depr(31) As Double
 'Loop variable
 Dim i As Integer
 'Calculate the weighted average cost of capital (WACC)
 Dim EFI As Double
 'Straight line depreciation
 Dim sltxdp As Double
 sltxdp = 1 / BL
 'Cumulative CC x V in the EPRI formula
 'Detail of the original formula can  be seen in TAG-Technical Assessment Guide, Vol. 3,
 'Fundamentals and Methods, Supply-1986, EPRI P-4463-SR
 Dim SP  As Double
 SP = 0
 'V current value factor in the EPRI formula
 Dim V As Double
 'Deferred income tax
 Dim DT As Double
 'tax paid.
 Dim TP  As Double
 'tax depreciation rate

	143

-------
Appendix F
 Dim TD As Double
 'Carrying charge
 Dim cc As Double
 'An annuity factor in EPRI formula
 Dim A As Double
 'temp variable of rd
 Dim rdTemp As Double
 'temp variable of re
 Dim reTemp As Double
 'book depreciation rate net oflTC
 Dim BD As Double
 BD = (1 - ITC)/ BL
 'Remaining book value
 Dim SB As Double
 SB = 1  - ITC
 'Assign  value to ACRS schedule
 Arcs(O) = 0
 Arcs(l) = 7.5
 Arcs(2) = 6.9
 Arcs(3) = 6.4
 Arcs(4) = 5.9
 Arcs(5) =5.5
 Arcs(6) = 5.1
 Arcs(7) = 4.7
 Arcs(8) = 4.5
 Arcs(9) = 4.5
 Arcs(lO) = 4.5
 Arcs(ll) = 4.5
 Arcs(12) = 4.5
 Arcs(13) = 4.5
 Arcs(14) = 4.5
 Arcs(15) = 4.5
 Arcs(16) = 4.4
 Arcs(17) = 4.4
 Arcs(18) = 4.4
 Arcs(lO) = 4.4
 Arcs(20) = 4.4

 'Assign  value 0 to annuity
 A  = 0#
 'Compute return rate used to determine carrying charges
 'Calculate rd and re without inflation
 rd = (1 + rd) / (1 + inflation) - 1
 re = (1 + re) / (1 + inflation) - 1
                                                                                  144

-------
Appendix F
 EFI = wd x rd + we x re
 'Initialize depreciation value in the depreciation array.
 For i = LBound(Depr) To UBound(Depr)
  Depr(i) = 0
 Next i
 'Calculate tax depreciation with 3 cases, we assume that the book life is greater than the
depreciation life
 'Calculate straight line tax depreciation
 If (depreMethod = 1) Then
  'For straight line tax depreciation over book life
  For i = 1 To  BL
   Depr(i) = 1  / BL
  Next i
  'For straight line tax depreciation overACRS
 Elself (depreMethod = 2) Then
  For i = 1 To  20
   Depr(i) = 1/20
  Next i
  'ForACRS depreciation  schedule
 Else
  For i = 1 To  20
   Depr(i) = Arcs(i) / 100
  Next i
 End If
 'Start the loop over the  book life
 For i = 1 To 1
  'present value factor
  V = (1 + EFI) ^ (-i)
  If (EFI <> 0) Then
   A=  (1-V)/(EFI)
  Else
   A =  i
  End If
  'Tax depreciation rate
  TD = Depr(i)
  'Return on equity
  reTemp =  SB x re x we
  'Return on debt
  rdTemp =  SB x rd x wd
  'Deferred income tax
  DT = (TD - sltxdp) x T
  'tax paid.
  TP = T / (1 - T) x (BD - TD + DT + reTemp)
  ' Year by year carrying  charges

	145

-------
Appendix F
  cc = BD + DT + rdTemp + reTemp + TP + PTI
  'Cum. present value of carrying charge
  SP = SP + cc x V
  'Depreciation book value, net def.  tax
  SB = SB - BD - DT
 Next i
 'carry Charges = SP / A
 firstYearConstantCC = SP / A

End Function
'This function calculate current levelization for O&M cost
'Arguments: rd (cost of debt), float; wd(ratio of debt), float; re(cost of equity), float;
'we (ratio of equity), float; BL(book life), float; inflation, float; escalation, float
Function currentl_L(rd, wd, re, we, BL, inflation, escalation)
 inflation = inflation
 escalation = escalation
 rd =  rd
 wd = wd
 re =  re
 we = we
 'Define discount (weighted average cost of capital)
 Dim discount
 discount = wd x rd + we x re
 Dim EA
 EA = (1 + inflation) x (1 + escalation)  - 1
 Dim k
 k= (1 + EA)/ (1 + discount)
 Dim An
 An = ((1 + discount) ^ BL - 1) / (discount x  (1 + discount) ^ BL)
 Dim Ln
 Ln =  (k x (1 - k ^ BL)) / (An x (1 - k))
 currentLL = Ln

End Function

Function constantLL(rd, wd, re, we, BL,  inflation, escalation)
 inflation = inflation
 escalation = escalation
 rd =  rd
 wd = wd
 re =  re
 we = we
                                                                                    146

-------
Appendix F
 rd = (1 + rd)/ (1 + inflation) - 1
 re = (1 + re) / (1 + inflation) - 1
 Dim discount
 discount = wd x  rd + we x re

 Dim EA
 EA = (1 + escalation) - 1
 Dim k
 k = (1 + EA) / (1 + discount)
 Dim An
 An = ((1 + discount) ^ BL - 1) / (discount x (1 + discount) ^ BL)
 Dim Ln
 Ln =  (k x (1 - k ^ BL)) / (An x (1 - k))
 constantLL = Ln
  'constantLL = re
End Function
The function below is a function to calculate the compressibility of compressors across the
compressor island in  CO2 compression

'Define a function
Function CompressionPower(initialPressure, finalPressure, numOfStage, CompressionTemp)
   Dim pressureRatio As Double
   Dim pressureOfEachStage(lO) As Double
   Dim Z(10) As Double
   Dim i As Integer
   Dim averageZ
   'initalize pressure
   pressureOfEachStage(O) = initialPressure
   'initalize Z
   If pressureOfEachStage(O) > 800 Then
     Z(0) = 0.5
   Else
     Z(0) = 1-0.4/ 800 x  pressureOfEachStage(O)
   End If

   pressureRatio  =   ((finalPressure +   1.5  x  numOfStage)  /  initialPressure)  ^  (1# /
numOfStage)
   'calculate Z factors
   CompressionPower = 0#

   For i  = 1 To numOfStage

	147

-------
Appendix F
     pressureOfEachStage(i) = pressureOfEachStage(i - 1) x pressureRatio
     'calculate outlet Z
     Z(i) = 1-0.5/ 2000 x pressureOfEachStage(i)
     If Z(i) < 0.5 Then
        Z(i) = 0.5
     End If

     'calculate inlet Z
     If pressureOfEachStage(i - 1) > 800 Then
      Z(i - 1) = 0.5
     Else
      Z(i - 1) = 1 - 0.4 / 800 x pressureOfEachStage(i - 1)
     End If
     'Calculate average Z
     averageZ =  (Z(i) + Z(i - 1)) / 2
     CompressionPower = CompressionPower + 188.9  x (CompressionTemp + 273.15) x
1.28 x averageZ / (1.28 - 1) x (pressureRatio ^ (0.28 / 1.28) - 1) / 0.8
   Next
End Function
                                                                                148

-------