United States
             Environmental
             Protection Agency
            Office of Water (4503T)
            Washington, DC 20460
                                EPA841-B-09-001
                                December 2009
                                www.epa.gov/owow/nps/lid/section438
I
33

%
   PR
Technical Guidance on Implementing the
Stormwater Runoff Requirements for
Federal Projects under Section 438 of the
Energy Independence and Security Act

-------
                                           Foreword
Stormwater runoff in urban and developing areas is one of the leading sources of water pollution in the
United States. In recognition of this issue, Congress enacted Section 438 of the Energy Independence and
Security Act of 2007 (EISA) to require federal agencies to reduce stormwater runoff from federal
development projects to protect water resources. More recently, the President signed Executive Order
13514 on "Federal Leadership in Environmental, Energy, and Economic Performance" calling upon all
federal agencies to "lead by  example" to address a wide range of environmental issues, including
stormwater runoff. The Executive Order required the U.S. Environmental Protection Agency (EPA), in
coordination with other federal agencies, to publish this Technical Guidance.

EPA worked closely with many federal agencies to develop this Technical Guidance to help federal
agencies in implementing EISA Section  438. The guidance provides a step-by-step framework that will
help federal agencies maintain pre-development site hydrology by retaining rainfall on-site through
infiltration, evaporation/transpiration, and re-use to the same extent as occurred prior to development. The
Technical Guidance provides background information, key definitions, case studies, and guidance on
meeting the new requirements.

Federal agencies can comply with Section 438 by using a variety of stormwater management practices
often referred to as "green infrastructure" or "low impact development" practices,  including, for example,
reducing impervious surfaces, using vegetative practices, porous pavements, cisterns and green roofs.

One of the most exciting new trends in water quality management today is the movement by many cities,
counties, states, and private  sector developers toward the increased use of this next generation stormwater
management practices to help protect and restore water quality. Many federal agencies, including EPA,
are already using a full spectrum of stormwater management practices to reduce the impact of federal
facilities on local watersheds. These projects have produced results  such as reductions in site runoff
volumes and increased stormwater quality, which ultimately lead to more sustainable facilities.

EPA enjoyed the opportunity to work with a number of federal agencies to develop this state-of-the art,
technical guidance and appreciate all their input. We look forward to continuing the dialogue as we all
work to implement this guidance.
                                                  •=•<:
                                                    eter S. Silva
                                                    .ssistant Administrator
                                                   Office of Water
                                                   U.S. Environmental Protection Agency

-------
Section 438 Technical Guidance                                     December 2009

  Technical Guidance on Implementing the Stormwater Runoff Requirements for Federal
         Projects under Section 438 of the Energy Independence and Security Act

INTRODUCTION

In December 2007, Congress enacted the Energy Independence and Security Act of 2007.
Section 438 of that legislation establishes strict Stormwater runoff requirements for federal
development and redevelopment projects. The provision reads as follows:

       "Storm water runoff requirements for federal development projects.  The
       sponsor of any development or redevelopment project involving a Federal facility
       with a footprint that exceeds 5,000 square feet shall use site planning, design,
       construction, and maintenance strategies for the property to maintain or restore, to
       the maximum extent technically feasible, the predevelopment hydrology of the
       property with regard to the temperature, rate, volume, and duration of flow."

The intent of Section 438 of the Energy Independence and Security Act of 2007 (EISA) is to
require federal agencies to develop and redevelop applicable facilities in a manner that maintains
or restores Stormwater runoff to the maximum extent technically feasible.  Until recently,
Stormwater programs established to address water quality objectives have been designed to
control traditional pollutants that are commonly associated with municipal and industrial
discharges, e.g., nutrients, sediment, and metals. Increases in runoff volume and peak discharge
rates have been regulated through state and local flood control programs.  Although these
programs have merit, knowledge accumulated during the past 20 years has led Stormwater
experts to the conclusion that conventional approaches to control runoff are not fully adequate to
protect the nation's water resources (National Research Council, 2008).

Implementation of Section 438 of the EISA can be achieved through the use of the green
infrastructure/low impact development (GI/LID) infrastructure tools described in this guidance.
The intention of the statute is to maintain or restore the pre-development site hydrology during
the development or redevelopment process.  To be more specific, this requirement is intended to
ensure that receiving waters are not negatively impacted by changes in runoff temperature,
volumes, durations and rates resulting from federal projects.  It should also be noted that a
performance-based approach was selected in lieu of a prescriptive requirement in order to
provide site designers maximum flexibility in selecting control practices appropriate for the site.

Section 14 of the Executive Order 13514, Federal Leadership in Environmental, Energy,
and Economic Performance

On October 5, 2009, President Barack Obama signed Executive Order 13514,
"Federal Leadership in Environmental, Energy, and Economic Performance."
Section 14 of the Executive Order provides:

       Stormwater Guidance for Federal Facilities. Within 60 days
       of the  date of this order, the Environmental Protection
       Agency, in coordination with other Federal agencies as

                                           1

-------
Section 438 Technical Guidance                                     December 2009

       appropriate, shall issue guidance on the implementation of
       section 438 of the Energy Independence and Security Act of
       2007(42U.S.C. 17094).

This provision contains two significant elements. First, for the first time, EPA is formally
assigned the responsibility to write and issue the Section 438 guidance, in coordination with
other federal agencies. Second, it establishes a deadline for EPA to do so by December 5, 2009.

Purpose and Organization of this Guidance

The purpose of this document is to provide technical guidance and background information to
assist federal agencies in implementing EISA Section 438. Each agency or department is
responsible for ensuring compliance with EISA Section 438. The document contains guidance on
how compliance with Section 438 can be achieved, measured and evaluated. In addition,
information detailing the rationale for the stormwater management approach contained herein
has been included.

This document is intended solely as guidance. This document is not a regulation nor does it
substitute for statutory provisions or regulations. This guidance does not impose any legally
binding requirements on federal agencies and does not confer any legal rights or impose legal
obligations upon any member of the public. This document does not create a cause of action
against the EPA, other federal agencies, or the United States.

The following information is presented within this document:

Part I: Implementation Framework
       A.  Background
       B.  Benefits and outcomes of the new stormwater performance requirements
       C.  Applicability and definitions
       D.  Tools to implement the requirements of Section 438
       E.  Calculating the 95th percentile rainfall event

Part II: Case Studies on Capturing the 95th Percentile Storm Using Onsite Management
Practices
Case studies representing typical federal installations have been included. The case studies were
selected to demonstrate the feasibility of providing adequate stormwater control for a range of
site conditions and building designs. To the maximum extent technically feasible, each case
study includes a description of a method that can be used to determine the design objectives of
the project based on retaining the 95th percentile storm. Examples of onsite technologies and
practices have also been provided. The case studies are intended to provide examples of
modeling procedures that can be used to quantify treatment system performance and processes
for assessing sites and determining appropriate control techniques to the maximum extent
technically feasible.

-------
Section 438 Technical Guidance                                      December 2009


                           Part I: Implementation Framework

A. BACKGROUND

This section contains background on the causes and consequences of stormwater discharges,
solutions that can be used to address the causes and consequences of stormwater discharges and
how to implement those solutions to comply with Section 438 of EISA.

Alterations to Natural Hydrology and the Impact on Stormwater Runoff
In the natural, undisturbed environment rain that falls is quickly absorbed by trees, other
vegetation, and the ground. Most rainfall that is not intercepted by leaves infiltrates into the
ground or is returned to the atmosphere by the process of evapotranspiration. Very little rainfall
becomes stormwater runoff in permeable soil, and runoff generally only occurs with larger
precipitation events. Traditional development practices cover large areas of the ground with
impervious surfaces such  as roads, driveways, sidewalks, and buildings. Under developed
conditions runoff occurs even during small precipitation events that would normally be absorbed
by the soil and vegetation. The collective force of the increased runoff scours streambeds, erodes
stream banks, and causes large quantities of sediment and other entrained pollutants to enter the
water body each time it rains (Shaver, et al., 2007; Booth testimony, 2008).

As watersheds are developed and impervious surfaces increase in area, the hydrology  of the
watersheds fundamentally changes over time which results in degraded aquatic ecosystems. In
recognition of these problems, stormwater managers employed extended detention approaches to
mitigate the impacts of increased peak runoff rates. However, wet ponds and similar practices
are not fully adequate to protect downstream hydrology because of the following inherent
limitations of these conventional practices (National Research Council, 2008; Shaver, et al.,
2007):

   •   Poor peak control  for small, frequently-occurring storms;
   •   Negligible volume reduction; and
   •   Increased duration of peak flow.

Detention storage targets relatively large, infrequent storms, such as the two and 10-year/24-hour
storms for peak flow rate control. As a result of this design limitation, flow rates from smaller,
frequently-occurring storms typically exceed those that existed onsite before land development
occurred and these increases in runoff volumes and velocities typically result in flows erosive to
stream channel stability (Shaver, et al., 2007).  Section 438 is intended to address the
inadequacies of the historical detention approach to managing stormwater and promote more
sustainable practices that have been selected to maintain or restore predevelopment site
hydrology.

A 2008 National Research Council report on urban stormwater confirmed that current
stormwater control efforts are not fully adequate. Three of the report's findings on stormwater
management approaches are particularly relevant (National Research Council, 2008).

-------
Section 438 Technical Guidance
                   December 2009
      1.  Individual controls on stormwater discharges are inadequate as the sole solution to
         stormwater in urban watersheds;
      2.  Stormwater control measures such as product substitution, better site design,
         downspout disconnection, conservation of natural areas, and watershed and land-use
         planning can dramatically reduce the volume of runoff and pollutant load from new
         development; and
      3.  Stormwater control measures that harvest, infiltrate, and evapotranspire stormwater are
         critical to reducing the volume and pollutant loading of small storms.
     Typical Armuul Water Budget
                         Forested laial
    Typical Annual Water Budget
                                                                   ffM
                                                                     25%
                                                                    Evaporation-Transpiration
 Pre-development Hydrology. Courtesy of C. May,    Post-Development Hydrology. Courtesy of C.
            University of Washington.                      May, University of Washington.
                     40% ova polranspi ration
                                                            30% evapotranspl ration
           15% shallow
           it'lil '..lion
          Natural Ground Cover
                                  25V, deep
                                  infiltration
 10% shallow
 infiltration
7$%-1QO% Impervious Cover
                        5% deep
                        infiltration
             Figure 1. Pre-Development and Post-Development Hydrology. (USDA).

Figure 1 contains two sets of diagrams depicting the water balances at undeveloped and
developed sites. Runoff patterns will vary based on factors such as geographic location, local
meteorological conditions, vegetative cover and soils.  The first set of figures represents
conditions in the Pacific Northwest where storms have a long duration and low intensity, i.e., the
volume of rain in an individual  storm is small.  The second set of figures from the U.S.
Department of Agriculture represents a more generalized set of conditions, but was included to
illustrate that heavily urbanized areas typically cause large increases in runoff.

-------
Section 438 Technical Guidance                                      December 2009

Land cover changes that result from site development include increased imperviousness, soil
compaction, loss of vegetation, and loss of natural drainage patterns, which result in increased
runoff volumes and peak runoff rates. The cumulative impacts of the land cover changes result
in alterations of the natural hydrology of a site, which disrupts the natural water balance and
changes water flow paths. The consequences of these impacts include:

    1.  Increased volume of runoff. With decreased area for infiltration and evapotranspiration
       due to development, a greater amount of rainfall is converted to overland runoff which
       results  in larger stormwater discharges.
    2.  Increased peak flow of runoff. Increased impervious surface area and higher connectivity
       of impervious surfaces and stormwater conveyance systems increase the flow rate of
       stormwater discharges and increase the energy and velocity  of discharges into the stream
       channel.
    3.  Increased duration of discharge. Detention systems generate greater flow volumes and
       rates.  These prolonged higher discharge rates can undermine the stability of the stream
       channel and induce erosion, channel  incision and bank cutting.
    4.  Increased pollutant loadings. Impervious areas are a collection site for pollutants. When
       rainfall occurs these pollutants are mobilized and transported directly to stormwater
       conveyances and receiving streams via these impervious surfaces.
    5.  Increased temperature of runoff. Impervious surfaces absorb and store heat and transfer it
       to stormwater runoff. Higher runoff temperatures may have  deleterious effects on
       receiving streams. Detention basins  magnify this problem by trapping and discharging
       runoff that is heated by solar radiation (Galli,  1991; Schueler and Helfrich,  1988).

The resulting increases in volume, peak flow, and duration are illustrated in the hydrograph  in
Figure 2, which is a representation of a site's stormwater discharge  with respect to time. The
hydrograph illustrates the impacts of development on runoff volume and timing of the runoff.
Individual points on the curve represent the rate of stormwater discharge at a given time. The
graph illustrates that development and corresponding changes in land cover result in greater
discharge rates, greater volumes, and shorter discharge periods. In a natural condition, runoff
rates are  slower than those on developed sites and the discharges occur over a longer time period.
The predevelopment peak discharge rate is also much lower than the post-development peak
discharge rate  due to attenuation and absorption by soils and vegetation.  In the post-
development condition there is generally a much shorter time before runoff begins because of
increased impervious surface area, a higher degree of connectivity of these areas and the loss of
soils and vegetative cover that slow or reduce runoff.

-------
Section 438 Technical Guidance
December 2009
           Q
                                     Post-Development Condition
                                                Pre-Development Condition
                         Figure 2. Post-Development Hydrograph.
                            (Q = volumetric flow rate; t = time)
     Figure 3. Stream Displaying the Effects of Stormwater Runoff and Channel Downcutting.
The Solution: Preserving and Restoring Hydrology
A new approach has evolved in recent years to eliminate or reduce the amount of water and
pollutants that run off a site and ultimately are discharged into adjacent water bodies.

-------
Section 438 Technical Guidance
                                                                December 2009
The fundamental principle is to employ systems and practices that use or mimic natural
processes to: 1) infiltrate and recharge, 2) evapotranspire, and/or 3) harvest and use precipitation
near to where it falls to earth.

GI/LID practices include a wide variety of practices that utilize these mechanisms. These
practices can be used at the site, neighborhood and watershed/regional scales.  In this document
the focus is on site-level practices, which is most consistent with the terms used in Section 438:
"project," "facility," and "property." Although these performance requirements apply at the
project site-level, flexibility exists to utilize nearby areas or areas directly adjacent to the facility
to manage the runoff, i.e., evapotranspirate, infiltrate or harvest and use.  Where justifiable, it
also may be appropriate to evapotranspirate, infiltrate or harvest and use an equivalent or greater
amount of runoff offsite as long as the runoff is discharged or used in the same receiving
sub water shed or watershed.

The purpose of EISA Section 438 is to replicate the pre-development hydrology to protect and
preserve both the water resources onsite and those downstream.  For example, if prior to
development, twenty five (25) percent of the annual rainfall runs directly into the  stream and the
remainder infiltrates into the ground or is evapotranspired into the air, then the post-development
goal should be to limit runoff to twenty five (25) percent of the annual precipitation while
maintaining the correct aquifer recharge rate. This has the benefit, in most cases,  of delivering
water to the stream at approximately the same rate, volume, duration and temperature as the
stream had naturally evolved to receive prior to development. The result will be to eliminate or
minimize the erosion of streambeds and streambanks, significantly reduce the  delivery of many
                                       pollutants to water bodies, and retain historical
                                       instream temperatures.

                                       Restoring or maintaining pre-development hydrology
                                       has emerged as a control approach  for  several
                                       reasons. Most importantly, this approach is intended
                                       to directly address the root cause of impairment.
                                       Current control approaches have been  selected in an
                                       attempt to control the symptoms (peak flow, and
                                       excess pollutants), but this strategy is not fully
                                       adequate because of the scale of the problem, the
                                       cumulative impacts of multiple developments and the
                                       need to manage both site and watershed level impacts.
                                       With current approaches, it is also difficult to
                                       adequately protect and improve water quality because
                                       the measures employed are not addressing the main
                                       problem which is a hydrologic imbalance.

                                       Designing facilities based on the goal of maintaining
                                       or restoring pre-development hydrology provides a
                                       site specific basis and an objective  methodology with
                                       which to determine appropriate practices to protect
                                       the receiving environment.
Figure 4. Parking lot bioswale and
  permeable pavers in Chicago.

-------
Section 438 Technical Guidance
             December 2009
Using pre-development hydrology as the guiding control principal also allows the designer to
consider climatic and geologic variability and tailor the solutions to the project location. Thus
the need for a one size fits all approach is rendered unnecessary since the design objective is
dictated by the pre-development site conditions and other technicalities of the project site and
facility. Instead of prescribed approaches dictating discharge volumes or flow rates, site
assessments of historical infiltration and runoff rates will inform the designer and provide the
basis for a suitable design. The use of this approach will minimize compliance complications that
may arise from prescriptive design approaches which do not account for  the variability of
precipitation frequencies, rainfall intensities and pre-development land cover and soil conditions
that influence infiltration and runoff.
B. BENEFITS AND OUTCOMES OF THE NEW STORMWATER PERFORMANCE REQUIREMENTS

Implementation of these new stormwater performance requirements in EISA Section 438
provides numerous environmental and economic benefits in addition to reducing the volume of
stormwater runoff:
Benefits to Water Resources:

•  Cleaner Water.  The use of plants, soils and water
   harvesting and use practices can reduce stormwater
   runoff volumes and pollutant loadings and the
   frequency and magnitude of combined sewer
   overflows (volume and pollutant loading
   reductions). These practices are part of a larger set
   of practices called green infrastructure/low impact
   development.
•  Clean and Adequate Water Supplies. GI/LID
   approaches using soil based vegetated infiltration
   systems can be used to recharge ground water and
   maintain stream base flow. By recharging ground
   water aquifers, aquatic ecosystem health is
   maintained and base flows are increased which helps
   ensure more constant flows for drinking water
   withdrawals. Harvesting and reusing rainwater also
   reduces the need to use potable water for  all uses
   and can reduce both the infrastructure and energy
   needed to treat and transport both drinking water and
   stormwater.
•  Source  Water Protection. GI/LID practices provide
   pollutant removal benefits, thereby providing some protection for both ground water and
   surface water sources of drinking water. In addition, GI/LID provides ground water recharge
   benefits.
GI/LID approaches are a set of
management approaches and
technologies that utilize and/or
mimic the natural hydrologic cycle
processes of infiltration,
evapotranspiration and use. GI/LID
practices include green roofs, trees
and tree boxes, rain gardens,
vegetated swales, pocket wetlands,
infiltration planters, porous and
permeable pavements, vegetated
median strips, reforestation and
revegetation and protection of
riparian buffers and floodplains.
These practices can be used almost
anywhere soil and vegetation can be
worked into the urban or suburban
landscape.  They include
decentralized harvesting approaches
such as rain barrels and cisterns that
can be used to capture and re-use
rainfall for watering plants or
flushing toilets.

-------
Section 438 Technical Guidance
           December 2009
Other Social and Environmental Benefits:

•  Cleaner Air. Trees and vegetation improve air quality by filtering many airborne pollutants
   and can help reduce the amount of respiratory illness (Vingarzan and Taylor, 2003).
•  Reduced Urban Temperatures. Summer city temperatures can average  10°F higher than
   nearby suburban temperatures (Casey Trees, 2007). High temperatures are also linked to
   higher ground level ozone concentrations. Vegetation creates shade, reduces the amount of
   heat absorbing materials and emits water vapor - all of which cool hot air (Grant, et al.,
   2003). Reductions in impervious surface and the use of light colored pervious surfaces (e.g.,
   permeable concrete) also can mitigate urban temperatures.
•  Moderate the Impacts of Climate Change. Climate change impacts and effects vary
   regionally, but GI/LID techniques can provide
   adaptation benefits for a wide array of
   circumstances. They can be used to conserve,
   harvest and use water, to recharge ground waters
   and to reduce surface water discharges that could
   contribute to flooding. In addition, there are
   mitigation benefits such as reduced energy
   demand and carbon sequestration by vegetation.
•  Increased Energy Efficiency. Green space helps
   lower ambient temperatures and, when
   incorporated on and around buildings, helps  shade
   and insulate buildings from wide temperature
   swings, decreasing the energy needed for heating
   and cooling. Diverting stormwater from
   wastewater collection, conveyance and treatment
   systems can reduce the amount of energy needed
   to pump and treat the water. Energy efficiency not
   only reduces costs, but also reduces generation of
   greenhouse gases.
•  Community Benefits. Trees and plants improve
   urban aesthetics and community livability by
   providing recreational and wildlife areas. Studies show that property values are higher when
   trees and other vegetation are present. Increased green space also has public health benefits
   and has been shown to reduce crime and the associated stresses of urban living.
Figure 5. Rain water cistern.
C. APPLICABILITY AND DEFINITIONS

Applicability

1.  Who is a "Sponsor" of a project?

Section 438 applies to the "sponsor of any development or redevelopment project involving a
Federal facility . .  ." Section 438 requires that the "sponsor . . . shall use . . . strategies for the
property to maintain or restore . . . the predevelopment hydrology. . ."  The "sponsor" should

-------
Section 438 Technical Guidance                                      December 2009

generally be regarded as the federal department or agency that owns, operates, occupies or is the
primary user of the facility and has initiated the development or redevelopment project. If the
federal agency hires another entity to perform activities such as site construction or maintenance,
the agency should nonetheless be regarded as the sponsor and be responsible to assure
compliance with the requirements of Section 438. The agency sponsor is free to contract out
various duties and responsibilities that are associated with achieving compliance.

2  What is a "Federal facility"?

Section 438 provides that its requirements apply to the "sponsor of any development or
redevelopment project involving a Federal facility . . ."  Section 401(8) of EISA states:  "The
term 'Federal facility' means any building that is constructed, renovated, leased, or purchased in
part or in whole for use by the Federal Government."

3.  What is a "footprint"?

Section 438 applies to a federal  facility "with a footprint that exceeds 5,000 square feet." For the
purposes of this guidance, any project involving a federal facility that disturbs 5,000 square feet
or more of ground area is covered by this guidance. Existing facilities that have an overall
footprint of 5,000 square feet or greater that disturb less than 5,000 square feet of land area as
part of any single development or redevelopment project are not subject to Section 438
requirements. Consistent with the  purpose of Section 438 to preserve or restore pre-development
hydrology, the term "footprint"  includes all land areas that are disturbed as part of the project.

4.  What is "the property"?

Section 438 provides that the  project sponsor "shall use site planning, design, construction, and
maintenance strategies for the property to maintain or restore, to the maximum extent
technically feasible, the predevelopment hydrology of the property." This clause has been
interpreted to mean that the land surrounding the project site is available to implement the
appropriate GI/LID practices where optimal.

Although the performance requirements of EISA Section 438 apply only to the project footprint,
the flexibility exists to utilize  the entire federal property in implementing the stormwater
strategies for the project.

Definitions

95th percentile rainfall event.  The  95th percentile rainfall event represents a precipitation amount
which 95 percent of all rainfall events for the period of record do not exceed.  In more technical
terms, the 95th percentile rainfall event is defined as the measured precipitation depth
accumulated over a 24-hour period for the period of record that ranks as the 95th percentile
rainfall depth based on the range of all daily event occurrences during this period.

The 24-hour period is typically defined as 12:00:00 am to 11:59:59 pm. In general, at least a 20-
30 year period of rainfall record is recommended for such an analysis. This raw data is readily

                                            10

-------
Section 438 Technical Guidance                                     December 2009

available and collected by most airports across the county. Small rainfall events that are 0.1 of an
inch or less are excluded from the percentile analysis because this rainfall generally does not
result in any measureable runoff due to absorption, interception and evaporation by permeable,
impermeable and vegetated surfaces. Many stormwater modelers and hydrologists typically
exclude rainfall events that are 0.1 inch or less from calculations of rainfall events of any storm
from their modeling analyses of rainfall event frequencies. See, for example, the Center for
Watershed Protection's Urban Subwatershed Restoration Manual 3  (available at www.cwp.org).

Federal facility.  The term "federal facility" means any buildings that are constructed, renovated,
leased, or purchased in part or in whole for use by the federal government as defined in section
401(8) of the Energy Independence and Security Act.

Development or  re-development. For the purposes of this provision this term applies to any
action that results in the  alteration of  the landscape during construction of buildings or other
infrastructure such as parking lots, roads, etc, (e.g., grading, removal of vegetation, soil
compaction, etc.) such that the  changes affect runoff volumes, rates, temperature, and duration of
flow. Examples of projects that would fall under "re-development" include structures or other
infrastructure that are being reconstructed or replaced and the landscape is altered. Typical
patching or resurfacing of parking lots or other travel areas would not fall under this requirement.
D. TOOLS TO IMPLEMENT THE REQUIREMENTS OF SECTION 438

Section 438 of the Energy Independence and Security Act of 2007 reads as follows:
       Section 438.  Storm water runoff requirements for federal development projects.
       The sponsor of any development or redevelopment project involving a Federal facility
       with a footprint that exceeds 5,000 square feet shall use site planning, design,
       construction, and maintenance strategies for the property to maintain or restore, to the
       maximum extent technically feasible, the predevelopment hydrology of the property with
       regard to the temperature, rate, volume, and duration of flow.

The intention of EISA Section 438 is  to preserve or restore the hydrology of the site during the
development or redevelopment process.  To be more specific, this requirement is intended to
ensure that aquatic biota, stream channel stability, and historical aquifer recharge rates of
receiving waters are not negatively impacted by changes in runoff temperature, volumes,
durations and rates resulting from federal projects. A performance based approach was selected
in lieu of a prescriptive requirement in order to provide site designers maximum flexibility in
selecting control practices appropriate for the site.

To meet these performance objectives, technically feasible stormwater control practices that are
effective in reducing the volume of stormwater discharge should be used. To implement EISA
Section 438, this guidance recommends that the federal facility use all known, available and
reasonable methods of stormwater retention and/or use to the maximum extent technically
feasible (METF). Tools to implement the requirements of Section 438 are described below and
illustrated in Figure 8.
                                           11

-------
Section 438 Technical Guidance                                      December 2009

Establishing Section 438 Performance Design Objectives
Described below are options site designers can use to comply with Section 438. There may be
situations where Option 1 (retaining the 95th percentile rainfall event) is not protective enough to
maintain or restore the predevelopment hydrology of the project (for example, in some
headwater streams). In these cases, Option 2 (site-specific hydrologic analysis) could be used to
determine the types of stormwater practices necessary to preserve predevelopment runoff
conditions. Option 2 could also be used if predevelopment runoff conditions can be maintained
by retaining less than the 95th percentile rainfall event.  Because a performance based approach
was selected in lieu of a prescriptive requirement in order to provide site designers maximum
flexibility in selecting control practices appropriate for the site, Option 2 was provided in
recognition that there are established methodologies that can be utilized to estimate the volume
of infiltration and evapotranspiration based on site-specific hydrology and thus establish the
predevelopment hydrology performance design objectives.
  Option 1: Retain the 95th Percentile Rainfall Event
One approach to establishing the performance design objectives is to design, construct, and
maintain stormwater management practices that manage rainfall onsite, and prevent the off-site
discharge of the precipitation from all rainfall events less than or equal to the 95th percentile
rainfall event to the maximum extent technically feasible (METF). This objective should be
accomplished by the use of practices that infiltrate, evapotranspire and/or harvest and use
rainwater. The 95th percentile rainfall event is the event whose precipitation total is greater than
or equal to 95 percent of all storm events over a given period of record. For example, to
determine what the 95th percentile storm event is in a specific location, all 24 hour storms that
have recorded values over a 30 year period would be tabulated and a 95th percentile storm would
be determined from this record, i.e.,  5% of the storms would be greater than the number
determined to be the 95th percentile storm.  Thus the  95th percentile storm would be represented
by a number such as 1.5 inches, and this would be the design storm (example 95th percentile
storm events for selected cities are presented in Table 1). The designer would then select a
system of practices, to the METF, that infiltrate, evapotranspire or harvest and use this volume
multiplied by the total area of the facility/project footprint.  Methods and data used to estimate
the 95th percentile event are discussed in Part II of this  document.

For the purposes of this guidance, retaining all storms up to and including the 95th percentile
storm event is analogous to maintaining or restoring the pre-development hydrology with respect
to the volume, flow rate, duration and temperature of the runoff for most sites.  This 95th
percentile approach was identified and recommended because this storm size represents the
volume that appears to best represent the volume that is fully infiltrated in a natural condition
and thus  should be managed onsite to restore and maintain this pre-development hydrology for
duration, rate and volume of stormwater flows. In general, only large storms generate significant
runoff.  In addition, this approach was identified because it employs natural treatment and flow
attenuation methods that are presumed to have existed  on the site before construction of
infrastructure (e.g., building, roads, parking lots, driveways,) and is intended to infiltrate or
evapotranspirate the full volume of the 95th percentile storm.  Because this approach necessitates
the use of practices that generally preclude extended detention, it will also typically address the

                                            12

-------
Section 438 Technical Guidance
                   December 2009
issue of maintaining predevelopment temperatures. However, in cases where there are discharges
to cool water streams or other sensitive receiving waters, additional strategies may be needed to
ensure that stormwater discharges do not result in greater thermal impacts than would occur in
pre-development conditions (Schueler and Helfrich, 1988).

Where technically feasible, the goal of Option 1 is that one hundred percent (100%) of the
volume of water from storms less than or equal to the 95th percentile event over the footprint of
the project should not be discharged to surface waters. In some cases, runoff can be harvested
and used and ultimately may be discharged to surface waters or a sanitary treatment system; such
direct or indirect discharges must be authorized or allowed by the regulatory authority. For
example, if runoff is captured for nonpotable uses such as toilet flushing or other uses that are
not irrigation related, these waters potentially could be discharged into the sanitary sewer system.
Preferred mechanisms for retaining discharges from storms greater than the  95th percentile event
are through overflow or diversion for the volume that exceeds the 95th percentile amount.
Because standard underdrains typically discharge from smaller storms as well, underdrain
designs, if employed, should ensure adequate retention capacity for the 95th  percentile event
volume. For structures such as roofs and paved surfaces  that can increase the temperature of
stormwater runoff, materials that minimize temperature increases (e.g., concrete vs. asphalt;
vegetated roofs) should be considered  and used as appropriate.

Retaining 100 percent of all rainfall events equal to or less than the 95th percentile rainfall event
was identified as Option 1  because small, frequently-occurring storms account for a large
proportion  of the annual precipitation volume,
and the runoff from those storm events also
significantly alters the discharge frequency, rate
and temperature of the runoff.

The runoff produced by these small storms and
the initial portion of larger storms has a strong
negative cumulative impact on receiving water
hydrology and water quality. In areas that have
been developed, runoff is generated from almost
all storms, both small and large, due to the
impervious surfaces associated with
development and the loss of soils and vegetation.
In contrast, natural or undeveloped areas
discharge little or no runoff from small storms
because the rain is  absorbed by the landscape
and vegetation. Studies have shown that
increases in runoff event frequency, volume and
rate can be diminished or eliminated through the
use of GI/LID designs and practices, which infiltrate, evapotranspire and capture and use
stormwater.
Figure 6. Bioretention facility in Oregon.
                                           13

-------
Section 438 Technical Guidance
December 2009
Option 1 was identified because it is a simplified approach to meet the intent of Section 438 in
contrast to Option 2 which requires the designer to conduct a hydrologic analysis of the site
based on site-specific conditions.
    7.0
    6.0
    5.0
    4.0
 £  3.0
    0.0
                                rth
              Table 1. Example 95  Percentile Storm Events for Select U.S. Cities
                         (adapted from Hirschman and Kosco, 2008).
City
Atlanta, GA
Baltimore, MD
Boston, MA
Buffalo, NY
Burlington, VT
Charleston, WV
Coeur D'Alene, ID
Cincinnati, OH
Columbus, OH
Concord, NH
Denver, CO
95tn Percentile
Event Rainfall
Total (in)
1.8
1.6
1.5
1.1
1.1
1.2
0.7
1.5
1.3
1.3
1.1
City
Kansas City, MO
Knoxville, TN
Louisville, KY
Minneapolis, MN
New York, NY
Salt Lake City, UT
Phoenix, AZ
Portland, OR
Seattle, WA
Washington, DC

95tn Percentile
Event Rainfall
Total (in)
1.7
1.5
1.5
1.4
1.7
0.8
1.0
1.0
1.6
1.7

             10%
                     20%
                            30%
                                    40%     50%     60%

                                          Percentile

                                                 cth
                                                           70%
                                                                  80%
                                                                              95%
                                                                          90%     100%
Figure 7. Rainfall Frequency Spectrum showing the 95  percentile rainfall event for Portland, OR
(-1.0 inches)
                                            14

-------
Section 438 Technical Guidance                                      December 2009

Calculating the 95th Percentile Rainfall Event
Section E of this guidance contains information on how to calculate the 95th percentile rainfall
event for a  specific area. A long-term record of daily rainfall amounts (ideally, at least 30 years)
is needed to calculate the 95th percentile rainfall.

Designers opting to use Option 1 need to do the following:

1) calculate or verify the precipitation amount from the 95th percentile storm event (this number
   would be typically expressed in inches, e.g., 1.5", and

2) employ onsite stormwater management controls to the METF that infiltrate, evapotranspire
   or harvest and use the appropriate design volume.

The 95th percentile event can be calculated by using the following procedures below
(summarized from Hirschman and Kosco, 2008, Managing Stormwater in Your Community: A
Guide for Building an Effective Post-Construction Program, Center for Watershed Protection):

   •   Obtain a long-term rainfall record from a nearby weather station (daily precipitation is
       fine, but try to obtain at least  30 years of daily record). Long-term rainfall records can be
       obtained from many sources,  including NOAA at
       http://cdo.ncdc. noaa.gov/pls/plclimprod/poemain.accessrouter?datasetabbv=SOD&countr
       yabbv=&georegionabbv=.
   •   Remove data for small rainfall events that  are 0.1 inch or less and snowfall events that do
       not  immediately melt from the data set.  These events should be deleted since they do not
       typically cause runoff and could potentially cause  the analyses of the 95th percentile
       storm runoff volume to be inaccurate.
   •   Using a spreadsheet or simple statistical package,  sort the rainfall events from highest to
       lowest. In the next column, calculate the percentage of rainfall events that are less than
       each ranked event (event number/total number of events). For example, if there were
       1,000 rainfall events and the highest rainfall event was a 4" event, then 999 events (or a
       percentile of 999/1000, or 99.9%) are less  than the 4" rainfall event.
   •   Use the rainfall event at 95% as the 95th percentile storm event.
  Option 2: Site-Specific Hydrologic Analysis
Another approach to establishing the performance design objective is to design, construct, and
maintain stormwater management practices that preserve the pre-development runoff conditions
following construction. Option 2 allows the designer to conduct a site-specific hydrologic
analysis to determine the pre-development runoff conditions instead of using the estimated
volume approach of Option 1.  Under Option 2, the pre-development hydrology would be
determined based on site-specific conditions and local meteorology by using continuous
simulation modeling techniques, published data,  studies, or other established tools. If the
designer elects to use Option 2, the designer would then identify the pre-development condition
of the site and quantify the post-development runoff volume and peak flow discharges that are
equivalent to pre-development conditions. The post-construction rate, volume, duration and

                                           15

-------
Section 438 Technical Guidance                                      December 2009

temperature of runoff should not exceed the pre-development rates and the predevelopment
hydrology should be replicated through site design and other appropriate practices to the
maximum extent technically feasible. These goals should be accomplished through the use of
infiltration, evapotranspiration, and/or rainwater harvesting and use.  Defensible and consistent
hydrological assessment tools should be used and documented. Additional  discussions of
appropriate methodologies to use in assessing site hydrology have been included in the technical
sections of this document.  See, for example, the discussion of spreadsheet versions or curve
numbers based on the Natural Resource Conservation Service Technical Release 55 (TR-55)
Method in Appendix A of this document.

Development
The pre-development hydrologic condition of the  site is the combination of runoff, infiltration
and evapotranspiration rates and volumes that typically existed on the facility site before
"development" on a greenfields site (meaning any construction of infrastructure on undeveloped
land such as meadows or forests).  In practice, determining the pre-development hydrology of a
given site can be difficult if there is no suitable reference site. As a result, reference conditions
for typical land cover types in the locality often are used to approximate what fraction of the
precipitation ran off, soaked into the ground or was evaporated from  the landscape. The use of
reference conditions can be problematic if suitable data are not available or unique site
conditions exist that do not fit within a typical land use cover type for the area, e.g., meadow or
forest. In cases where suitable data from comparable conditions cannot be found or is otherwise
inadequate to be used in conducting an Option 2 analysis for the specific area being considered
for development or redevelopment, the project sponsor should use the Option 1 analytical
framework.

Re-development
For re-development sites, existing site conditions and uses of the  site can influence the amount of
runoff that can be managed on site through infiltration, evapotransporation and harvest and use
and thus the performance design objective.  In these cases the design process in Figure 8 and
Scenario 9 illustrate the decision processes  that can be used.

In the context of some re-development projects, fully restoring predevelopment hydrology can be
difficult to achieve and Congress recognized this potential difficulty by including the METF
language in the statute.  In these cases, Congressional intent can be best carried out by using a
systematic METF analysis to determine what practices can be implemented at the site to
maintain or store the hydrologic condition of the site. Scenarios 1-8 provide examples of METF
analyses that demonstrate that pre-development hydrology can be achieved.  Scenario 9 provides
an example of an METF analysis that demonstrates that pre-development hydrology cannot be
fully achieved and illustrates the extent to which pre-development hydrology can be restored.

Note: It should also be emphasized that the performance based approach in Option 1 is intended
to be a surrogate for determining the pre-development reference condition and this standard is
intended to be used in cases where it is more practical, cost effective, and/or expeditious than
Option 1, or where it is difficult or infeasible to identify the relevant reference conditions for the
site.
                                           16

-------
Section 438 Technical Guidance                                     December 2009

Determination of Maximum Extent Technically Feasible

Compliance with Section 438 requires that stormwater management measures are implemented
to the maximum extent technically feasible (METF) to maintain or restore the pre-development
hydrology conditions specifically with respect to temperature, rate, volume, and duration of flow.

Performance or design goals based on the pre-development hydrology can be established by
using options such as the following: Retention of the 95th percentile rainfall event (Option 1), or
through a site-specific hydrologic  analysis that estimates the volume of infiltration,
evapotranspiration or onsite stormwater harvesting and use based on site-specific hydrologic
conditions (Option 2).

Technical Infeasibility

For projects where technical infeasibility exists, the federal agency or department sponsoring the
project should document and quantify that stormwater strategies, such as infiltration,
evapotranspiration, and harvesting and use have been used to the METF, and that full
employment of these types of controls are infeasible due to site constraints.  Some western states
place restrictions on harvesting and use due to water rights, however, these requirements do not
necessarily preclude the sponsor of the project from implementing strategies such as infiltration
and evapotranspiration. Documentation of technical infeasibility should include, but may not be
limited to, engineering calculations, geologic reports, hydrologic analyses, and site maps. A
determination that the performance design goals cannot be met on site should include analyses
that rule out the use of an adequate combination of infiltration, evapotranspiration, and use
measures. Examples of where site conditions may prevent the full employment of appropriate
management techniques to the METF include a combination of:

•  The conditions on the site preclude the use of infiltration practices due to the presence of
   shallow bedrock, contaminated soils, near surface ground water or other factors such as
   underground facilities or utilities.
•  The design of the site precludes the use of soil amendments, plantings of vegetation or other
   designs that can be used to infiltrate and evapotranspirate runoff.
•  Water harvesting and use are not practical or possible because the volume of water used for
   irrigation, toilet flushing, industrial make-up water, wash-waters, etc. is not significant
   enough to warrant the design and use of water harvesting and use systems.
•  Modifications to an existing building to manage stormwater are not feasible due to  structural
   or plumbing  constraints or other factors as identified by the facility owner/operator.
•  Small project sites where the lot is too small to accommodate infiltration practices adequately
   sized to infiltrate the volume of runoff from impervious surfaces,
•  Soils that cannot be sufficiently amended to provide for the requisite infiltration rates,
•  Situations where site use is inconsistent with the capture and use of stormwater or other
   physical conditions on site that preclude the use of plants for evapotranspiration or
   bioinfiltration.
•  Retention and/or use of stormwater onsite or discharge of stormwater onsite via infiltration
   has a significant adverse effect on the site or the down gradient water balance of surface
   waters,  ground waters or receiving watershed ecological processes.

                                           17

-------
Section 438 Technical Guidance                                      December 2009

•   State and local requirements or permit requirements that prohibit water collection or make it
    technically infeasible to use certain GI/LID techniques.
•   Compliance with the Section 438 requirements would result in the retention and/or use of
    stormwater on the site such that an adverse water balance impact may occur to the receiving
    surface waterbody or ground water.

Please note that a single one of these characteristics is very unlikely to preclude meeting the
performance standard, but a combination of factors may.

In cases where the facility has a defensible showing of technical infeasibility and can provide
adequate documentation of site conditions or other factors that preclude full implementation of
the performance design goal, the facility should still install stormwater practices to infiltrate,
evapotranspire and/or harvest and use onsite the maximum amount of stormwater technically
feasible. Note: Facilities must still comply with all other applicable federal, state and local
requirements.
                                            18

-------
Section 438 Technical Guidance
                                                                     December 2009
 1.  Determine applicability
                                Requirement: apply to all federal projects with a footprint
                                greater than 5.000 square feet	
 2.  Establish design objective
                                Requirement: maintain or restore pre-developrnent hydrology
                                      OPTIONS
       Total volume of rainfall from 95n
       percent! le storm is to be managed
                  on-site
                                    Determine pre-development hydrology based on site-specific
                                  conditions and local meleorotogy by using continuous simulation
                                 modeling techniques, published data, studies, or other established
                              v	tools. Determine water volume to be managed on-site.	
                                        Design water volume
                                           (to be retained)
 3.  Evaluate design options
                                 Requirement: meet design objective to maximum extent
                                 technically feasible (METF)
                 Design water volume
                    (to be retained)
                   Bio-retention areas
                 Permeable pavements
                  Cisterns / recycling
                             remaining water
                                volume?
Selected
 on-site
 design
 options
                           OFF-SITE OPTIONS
                                (optional)
                                Selected
                             off-site design
                                options
TECHNICAL CONSTRAINT EXAMPLES
•  RGlaining storm water on-site would adversely
  impacl receiving water flows
•  Site has shallow bedrock, contaminated soils.
  high ground water, underground facilities or
  utilities
•  Soil infiltration capacity is limited
•  Site is too small to infiltrate significant volume
•  Non-potable water demand (for irrigation,
  toilets, wash-water, etc.) is toe smalt to
  warrant water harvesting and reuse systems
•  Structural, plumbing, or other modifications to
  existing buildings lo manage stormwater are
  infeasible
•  State or local requirements restrict water
  harvesting
•  State or local requirements restrict the use of
  green infrastructure.'LID
 4.  Finalize design and estimate cost

                         Figure 8.  Section 438 Implementation Process
                                                  19

-------
Section 438 Technical Guidance                                     December 2009

Documenting EISA Section 438 Implementation
Each agency or department is responsible for ensuring compliance with Section 438.  It is
recommended that: 1) the final design and as-built drawings of each facility shall be reviewed
by a registered professional engineer and 2) the agency or department develop and maintain
documentation of the following design criteria for each project subject to Section 438:

    •   Site evaluation and soils analysis
    •   Calculations for the 95th percentile rainfall event or the pre-development runoff volumes
       and rates to identify the volume of stormwater requiring management
    •   Documentation of modifications to the performance design objective based on technical
       constraints (site-specific METF determination)
    •   The site design and stormwater management practices employed on the site
    •   Design calculations for each stormwater management practice employed
    •   The respective volume of stormwater managed by each practice and the system as a
       whole
    •   Operations and maintenance protocols for the stormwater management system

The information should provide the necessary documentation and detail to demonstrate
compliance and operation of stormwater management practices for the entire site.

Common Green Infrastructure/Low Impact Development Tools to Implement Section 438
Although Congress did not prescribe specific practices to be used to implement Section 438 it
can be inferred that one of the goals of the Act was to promote the use of innovative stormwater
management approaches, designs and practices that better protect receiving water quality, flow
regimes and provide other important environmental benefits.  GI/LID are preferred practices, to
be supplemented with or replaced with conventional controls when site specific conditions
dictate.

The GI/LID management approaches and technologies that federal agencies would typically use
enhance and/or mimic the natural hydrologic cycle processes of infiltration, evapotranspiration,
and use.  Federal agencies can also use footprint reduction practices (e.g., building up instead of
out) to reduce their stormwater impact. GI/LID approaches include biological systems and
engineered systems. These include but are not necessarily limited to:

    •   Rain gardens, bioretention, and infiltration planters
    •   Porous pavements
    •   Vegetated swales and bioswales
    •   Green roofs
    •   Trees  and tree boxes
    •   Pocket wetlands
    •   Reforestation/revegetation using native plants
    •   Protection and  enhancement of riparian buffers and floodplains
    •   Rainwater harvesting for use (e.g., irrigation, HVAC make-up, non-potable indoor uses).

GI/LID practices are recommended to implement EISA Section 438 for the following reasons:
    •   cost savings in many cases

                                          20

-------
                                                                   December 2009
Section 438 Technical Guidance

   •   overall environmental performance
   •   pollutant loading reduction capability
   •   pollution prevention focus
   •   effectiveness in managing runoff
       volumes and rates
   •   energy efficient and energy
       conservative
   •   appropriate in a wide range of site
       condition and locations
   •   appropriate for new development and
       redevelopment projects
   •   appropriate at multiple scales of
       development, e.g., site, neighborhood,
       region

For more information on specific GI/LID
practices and how they function, visit:
www. epa. gov/greeninfrastructure and
www.epa.gov/nps/lid.
Cost of Compliance
The cost of complying with Section 438 may
require the use of approaches and techniques
that initially may be more costly to design and implement.  It is anticipated that as the expertise
of the implementing agency or department increases and the demand for GI/LID materials and
equipment increases that the overall costs of the projects will be lower or equivalent to the costs
of constructing conventional stormwater practices.  Initial studies conducted by EPA and others
suggest that the use of GI/LID practices can be cost competitive. Recent evaluations of GI/LID
projects have identified opportunities for cost savings because of reduced infrastructure and site
preparation demands. In addition, longer term studies have indicated that GI/LID practices are
continuing to gain cost efficiency as they are adopted more widely and with greater frequency
thus reducing overall implementation costs.

In Reducing Stormwater Costs through LID Strategies and Practices (EPA 841-F-07-006,
December 2007 - available for download at www.epa.gov/nps/lid), EPA examined 17 case
studies in which conventional  development costs were compared to GI/LID costs. In the great
majority of cases, the GI/LID approach was between 15 and 80 percent less expensive than
conventional control measures because implementation  of GI/LID practices can offset costs of
conventional construction and stormwater management  approaches.  Significant cost savings that
were identified in the report include:

   •   Elimination or reduction of detention ponds
   •   Elimination or reductions of stormwater and CSO treatment and conveyance systems
       such as pipes, storage structures, stormwater treatment devices, and other related
       stormwater infrastructure
   •   Narrower streets with reduced material demands
                                             Figure 9. Disconnected downspout
                                             discharging to planter box.
                                           21

-------
Section 438 Technical Guidance                                      December 2009

    •   Fewer square yards of sidewalks
    •   Reduced land purchases for stormwater control structures

In addition, other benefits were achieved through the use of GI/LID such as more beneficial uses
of land previously dedicated to stormwater devices, increased livability and higher property
values.

There are many different combinations of practices that can be employed at particular sites to
achieve pre-development hydrology.  In selecting the appropriate set of practices to be used at
the site, project sponsors should consider a broad range of factors, including cost-effectiveness of
particular combinations  of practices as applied to the site, as well as the potential for ancillary
cost savings or community benefits (e.g., elimination or reduction of infrastructure costs, or the
creation of attractive green spaces). EPA encourages project sponsors to include these factors in
the planning and design  phases of their projects so as to maximize triple bottom-line (economic,
environmental, and social) results.

E. CALCULATING THE 95TH PERCENTILE RAINFALL EVENT

A long period of precipitation records, i.e., a minimum of 10 years of data, is needed to
determine the 95l percentile rainfall event for a location. Thirty years or more of monitoring
data are desirable to conduct an unbiased statistical analysis. The National Climatic Data Center
(NCDC)  provides long-term precipitation data for many locations of the United States. You can
download climate data from their Web site (www.ncdc.noaa.gov) or by ordering compact discs
(NOTE: The NCDC charges a fee for access to their precipitation data). Local airports,
universities, water treatment plants, or other facilities might also maintain long-term
precipitation records.  Data reporting formats can vary based on the data sources. In general,
each record should include the following basic information:

    •   Location (monitoring station)
    •   Recording time (usually the starting time of a time-step)
    •   Total precipitation depth during the time-step

In addition to the above  information, a status flag is sometimes included to indicate data
monitoring errors or anomalies. Typical NCDC flags include A (end accumulation), M (missing
data), D (deleted data), or I (incomplete data).  If there  are no flags, the record has passed the
quality control as prescribed by the NCDC and has been determined to be a valid data point.

There are several data processing steps to determine the 95th percentile rainfall event using a
spreadsheet.  These steps are summarized below:

    1.  Obtain a long-term 24-hr precipitation data set for a location of interest (i.e., from the
       NCDC website).

    2.  Import the data into a spreadsheet. In MS Excel [Data / Import External Data / Import Data]
                                           22

-------
Section 438 Technical Guidance
                                                             December 2009
   3.
Rearrange all of the daily precipitation records into one column if the original data set has
multiple columns of daily precipitation records.

1
A LJL^ c
Date Prep
	 2 	 | 1/2/1921 0.05
3
4
5
6
7
8
Q
1/3/1921 0
1/4/1921 0
1/5/1921 0.33
1/6/1921 0.08
1/7/1921 0.08
1/8/1921 0.19
; D








1JCM1QTI n
   4.  Review the records to identify if there are early periods with a large number of flagged
       data points (e.g., erroneous data points). Select a long period of good recording data that
       represents, ideally, 30 years or more of data. Remove all of the extra data (if not using the
       entire dataset).

   5.  Remove all flagged data points (i.e., erroneous data points) from the selected data set for
       further analysis.

   6.  Remove small rainfall events (typically less than 0.1 inches), which may not contribute to
       rainfall runoff. These small events are categorized as depressional storage, which, in
       general, does not produce runoff from most sites.

1
2
3
4
5
6
7
8
q
A
Date
1/5/1921
1/8/1921
1/14/1921
2/6/1921
2/11/1921
2/20/1921
2/28/1921
inn q?i
B | C D
Prep
0.33
0.19
1.04
0.12
0.63
1.33
0.43
n 11
       Note: Steps 4 through 6 can be processed by applying data sort, delete and
       re-sort spreadsheet functions. In MS Excel [Data / Sort]

   7.  Calculate the 95th percentile rainfall amount by applying the PERCENTILE spreadsheet
       function at a cell. In MS Excel [=PERCENTILE(precipitation data range,95%)]

1
2
3
4
	 5 	
6
7
B
ZZAZJ 	 B 	 L_c_
Date Prep
1/5/1921 0.33
1/8/1921 0.19
1/14/1921 1.04
2/6/1921 0.12
2/11/1921 0.63
2/20/1921 1.33
ino/icm n JQ
II 	 D 	 LljL

=PERCENTILE(B:E
1.52





_JZZfZ

3,95%)






                                           23

-------
Section 438 Technical Guidance
December 2009
       Note: The PERCENTILE function returns the nth percentile of value in the entire
       precipitation data range.  This function can be used to determine the 95th percentile storm
       event that captures all but the largest 5% of storms.

   8.  The 95th percentile was calculated in the previous step. However, if the user would like
       to see this information represented graphically and get a relative sense of where
       individual storm percentiles fall in terms of rainfall depths, the following methodology
       can be used. Derive a table showing percentile versus rainfall depth to draw a curve as
       shown below. The PERCENTILE spreadsheet function can be used for each selected
       percent. It is recommended to include at least 6  points between 0% and 100% (several
       points should be between 80% and 100% to draw an accurate curve).

1
2
3
4
5
F.
^^A^J^JL <•
Date Prep
1/5/1921 0.33
1/8/1921 0.19
1/14/1921 1.04
2/6/1921 0.12
i/1-mqii OKI
; D
Percentile
0%
10%
20%
30%
/i n<>/,.
E F G
Rainfall
=PERCENTILE(B:B,D2)
=PERCENTILE(B:B,D3)
=PERCENTILE(B:B,D4)
=PERCENTILE(B:B,D5)
= PFPrFMTII FfF!-R HR}
	 1 A E
3 C 1 D 1 E 1 F 1 G
JMDate prcp Percentile Rainfall
Tj 1/5/1921 0.33 0% 0.1
Tl 1/8/1921 0.19 10% 0.13
Tl 1/14/1921 1.04 20% 0.17
5 2/6/1921 0.12 30% 0.22
Tl 2/11/1921 0.63 40% 0.28
Tl 2/20/1921 1.33 50% 0.36
9 1 3/3/1921 0.13 70% 0.6
IF 3/9/1921 0.31 80% 0.79
IT 3/13/1921 0.46 85% 0.93
J2J 3/25/1921 0.47 90% 1.16
111 3/28/1921 0.12 93% 1.35
J4] 4/1/1921 0.36 94% 1.44
J5] 4/9/1921 0.69 95% 1.52
11] 4/15/1921 0.24 96% 1.65
J7] 4/17/1921 0.32 97% 1.82
Hi 4/18/1921 0.55 98% 2.068
l9J 4/23/1921 0.69 99% 2.508
"20l 4/24/1921 0.19 99.5% 3.049
71 Ann/1971 1 ju inn% 7 OR



"55
tainfall depth
J CO 4


H
i
j
K





	


— — i




	







	


	 i




	


>_ 	 — i




—


_ — — i




—


,— ^-




—


.^— *




—


_—-•




	

- ^
y*




	 i
1
j
1

L

0% 10% 20% 30% 40% 50% 60% 70% 30% 90% 100%
Percentile

Use the spreadsheet software to create of plot of rainfall depth versus percentile, as shown above.
      -th
The 95  percentile storm event should correlate to the rainfall depth calculated in step 7,
however the graph can be used to calculate rainfall depths at other percentiles (e.g., 50%, 90%).
                                           24

-------
Section 438 Technical Guidance                                     December 2009

               Part II: Case Studies on Capturing the 95th Percentile Storm
                           Using Onsite Management Practices

INTRODUCTION

This section contains nine case studies that are intended to be representative of the range of
projects that are subject to the requirements legislated in Section 438 of the Energy
Independence and Security Act. The facility examples in the case studies were selected to
illustrate project scenarios for differing geographic locations, site conditions, and project sizes
and types.  As noted in Part I, all projects with a footprint greater than 5,000 square feet must
comply with the provisions of Section 438. What this means is that both new development and
redevelopment projects should be designed to infiltrate, evapotranspirate, and/or harvest and use
runoff to the maximum extent technically feasible (METF) to maintain or restore the pre-
development  hydrology of the site. Scenarios 1-8 are examples of sites where it was technically
feasible to design the stormwater management system to retain the 95th percentile storm onsite.
Scenario 9, however, was provided as an example of an METF analysis where site constraints
allowed the designers to retain only 75% of the 95th percentile storm.

Given the site-specific nature of individual projects, the case study scenarios described herein do
not include site specific design features such as runoff routing, specific site infiltration rates, the
structural loading capacity of buildings, etc. in terms of stormwater practice selection.

It should be noted that an example of Option 2, which requires a site-specific hydrologic
analysis, has not been provided in this document because of the complexity of factors  and the
lack of general applicability such an analysis would have.

Background
Numerous approaches exist for determining the volume of runoff to be treated through
stormwater management. Retaining stormwater runoff from all events up to and including the
95th percentile rainfall event was identified as Option 1 because small, frequently-occurring
storms account for a large proportion of the annual precipitation volume. Using GI/LID
practices to retain both the runoff produced by small  storms and the first  part of larger storms can
reduce the cumulative impacts of altered flow regimes on receiving water hydrology, e.g.,
channel degradation and diminished baseflow. For the purposes of this guidance, retaining all
storms up to and including the 95th percentile storm event is analogous to maintaining  or
restoring the pre-development hydrology with respect to the volume, flow rate, duration and
temperature of the runoff for most sites.

Determination of the 95th Percentile Rainfall Event
The 95th percentile rainfall rainfall event was determined using the long-term daily precipitation
records from the National Climate Data Center (NCDC, 2007). By analyzing the frequency and
rainfall depths from daily rainfall records over 24-hour periods, the 95th percentile storm event
can be determined. From a frequency analysis viewpoint, the 95th percentile event is the storm
event that is greater than or equal to 95% of all storms that occur within a given period of time.
Regional climate conditions and precipitation vary across the U.S. Because of local values, it is
essential that  the implementing agency or department establish the 95th percentile storm event for

                                           25

-------
Section 438 Technical Guidance                                     December 2009

the project site since the control volume may vary depending on local weather patterns and
conditions.

Onsite Stormwater Management Practice Determinations
For the purposes of the case study scenarios, the following four categories of practices were
selected as the most appropriate practices for implementing Section 438 requirements:
bioretention, permeable pavements and pavers, cisterns, and green roofs. These practices were
selected based on known performance data and cost. For each case study, the same hierarchy of
selection criteria was used, i.e., the most cost effective practices were considered before other
practices were considered. Bioretention practices were considered first because these systems
generally have the lowest cost per unit of stormwater treated (Hathaway and Hunt, 2007). Thus,
if the bioretention system could not be designed to adequately capture the desired runoff volume,
permeable pavement and pavers, cisterns, and  green roofs were considered in that order based on
relative cost.  In most cases a combination of practices was selected as part of an integrated
treatment system. It should be noted that all treatment systems were designed to accomplish the
goal of capturing the 95th percentile rainfall event onsite. Examples of onsite stormwater
management practices selected for each site are presented in the results section. For the Boston,
MA site, it was assumed that bioretention was not feasible in order to simulate a situation where
space was severely limited; as a result, interlocking modular pavers were selected as the most
cost-effective stormwater management to capture the requisite design volume.  To further
illustrate the range of site conditions designers may encounter, and how site conditions impact
the selection of appropriate control options, Scenario #3 (Cincinnati, OH) was re-analyzed as
Scenario #8. In Scenario #8, it was assumed that the site had clay soils and low infiltrative
capacity.  Given these site conditions, the range of potential control options was more limited
and a combination of modular paving blocks, a green roof, and cisterns was ultimately selected
based on cost and site suitability factors.

For purposes of these modeling exercises, a number of assumptions were associated with each
category of practice. These assumptions are not necessarily an endorsement of a particular
design paradigm, but rather were used to keep a somewhat conservative cap on the scenarios in
order to demonstrate the feasibility of the approach. For example, bioretention retrofits can and
should often be located in prior impervious locations; however, in all modeled scenarios
bioretention was restricted to currently landscaped areas. The assumptions were:

   •  Bioretention areas: On-lot retention of stormwater through the use of vegetation, soils,
       and microbes to capture, treat and infiltrate runoff.

       It is assumed bioretention practices would be installed within currently landscaped
       pervious areas or that pervious areas would be created for bioretention cells. While
       termed bioretention, these systems are  designed to provide infiltration as well as
       temporary storage.  Bioretention areas  would be designed to accept up to a depth of 10
       inches of water across the surface of the bioretention cell (see Appendix A). The
       conceptual design of this storage depth would occur within the media and/or could be
       included as ponded storage. Further design storage beyond the 10 inches would be
       acceptable (and encouraged) above the media on a site-by-site basis with ponded depth
       generally not to exceed 12 inches.

                                           26

-------
Section 438 Technical Guidance                                      December 2009
       Uniform infiltration was assumed across the entire base of the bioretention cell. No
       additional media underneath the amended soils were included in the designs with
       infiltration rates in this layer governed by the in situ soils. Underdrains were not modeled
       directly but could be applied at the point of storage overflow such that no overflow
       occurs until the design depth of 10 inches is saturated. This approach was selected to
       maximize the storage and infiltration benefits of these systems.  Designs utilizing
       underdrains at the base of the bioretention cell do not store the requisite volumes because
       the media is permeable and the underdrain conveys the runoff offsite through the
       underdrain before it can be infiltrated. Because standard underdrains typically discharge
       from smaller storms as well, underdrain designs, if employed, should ensure adequate
       retention  capacity for the 95th percentile event volume.

       The bioretention footprint for modeling purposes was calculated as one uniform area that
       did not include side slopes. There is an expectation that actual bioretention cell
       construction would be distributed throughout the site with targeted locations based on
       hydrology (natural flow paths) and soils with greater infiltrative capacity. Side slopes
       may increase the surface excavation area required to accommodate the footprint and
       freeboard of these systems depending on the design or the bioretention system.

       Porous/permeable pavement: Transportation surfaces constructed  of asphalt, concrete
       or permeable pavers that are designed to infiltrate runoff.

       Infiltration was modeled for the entire porous pavement area with drainage pipes used
       only as overflow outlets. This design was chosen to maximize infiltration capabilities of
       the system.  While many types of porous pavement systems can be used, modular block
       type pavers were generally applied in this design category under the assumption that they
       typically  include sufficient volumetric storage in the media layer.  [Note:  Other types of
       porous pavement applications are available that support heavy loads and can be designed
       to temporarily store and infiltrate  runoff beneath the surface of the pavement.]

       For these systems, an equivalent of 2 inches of design storage depth was assumed. This
       design depth could be achieved by specifying  10 inches of media depth that had 20%
       void space.  Similarly, this could be achieved by designing six inches of media depth
       above the bottom surface, with specified media containing 33% void space. This
       alternative would have the overflow outlet at the 6 inch depth providing an equivalent
       water storage depth of 2 inches.

       The soils under the paver blocks may require or be  subjected to some compaction for
       engineering stability.  As a result, infiltration into underlying soils was modeled
       conservatively by applying the minimum infiltration rate for each soil type
       (see Appendix A).

       Generally, porous pavement is not recommended for high traffic areas or loading bays
       Because of this the  scenarios assumed that only a percentage of total parking and road
       areas on a site can be  converted to porous pavement.  The assumed maximum percentage

                                           27

-------
Section 438 Technical Guidance                                      December 2009

       applied in the scenarios was set at 60% of the total paved area. Guidance on porous
       pavements is available at:
       http://cfpub.epa.gov/npdes/greeninfrastructure/technology.cfmtfpermpavements

   •   Cistern: Containers or vessels that are used to store runoff for future use.

       Cisterns were modeled in cases where green roofs were not feasible or where it was
       necessary to include additional storage volume to meet the goal of onsite rainfall runoff
       capture. The sizes of cisterns would be calculated based on site-specific rainfall, site-
       specific spatial and structural conditions, use opportunities and rates, and consideration of
       cost per volume of storage. For simplicity, cistern volume was reported as a total
       volume. This total volume could be subdivided into any number of cisterns to provide
       the total necessary storage but should be based on the impervious area and runoff
       quantities which will flow to the cistern. The most efficient cost per volume storage
       would need to be considered on a site-by-site basis (see Appendix A).

   •   Green roof: Roof designed with light weight soil media and planted with vegetation.

       Frequently, green rooftop area is limited by structural capacity. In addition, other rooftop
       equipment may need to be accommodated in this space including HVAC systems and air
       handlers. For this reason, and to provide a somewhat conservative rate of application, it
       was assumed for these modeling analyses that up to 30% of a roofs impervious area
       could be converted into a green roof. Green roof area was assumed to have 1 inch of total
       effective stormwater storage, i.e., a 2.5 inch media depth with 40% void space (see
       Appendix A).

General Approach
Using site aerial photos, spatial analysis should be conducted to estimate the land cover types
and areas for each site. The surface conditions of each site can be digitized using geographic
information systems (GIS) techniques.  Alternatively, computer-aided design (CAD) drawings
can be used to estimate the surface area of each land cover type.  The schematic in Figure 10
illustrates the processes used for selecting and determining the overall size of stormwater
management practices for each site.
                                           28

-------
Section 438 Technical Guidance
                                 December 2009
                           Stormwater
                     Management Analysis &
                         Design Process
  Collect spatial data from aerial
   photos (determine pervious
     and impervious areas)
 Collect historic rainfall
data from nearest station
Determine the 95th percentile
    24-hour rainfall event
                                      Z
                  Estimate the current runoff
       Select onsite control measure options
               Check whether control
                  measure options
                 meet performance
                 goals performance
    Determine the size(s) of control measure(s)
                  Select control
             measure(s) to fit the site
             and confirm performance
                           Yes
                                               No
                      1. Select alternative control measures
                        using METF analysis and site
                        limitations to determine appropriate
                        runoff control measures if
                        performance goals cannot be
                        achieved
                           and/or
                      2. Exercise optional offsite runoff
                      management approach and select
                      appropriate control measures
                       Determine location and size(s) of
                       onsite or off-site control measures
      Design and implement control measure(s)
         Figure 10. Flow chart depicting the process for determining control measures
                    using the 95* percentile, 24-hour, annual rainfall event.
                                           29

-------
Section 438 Technical Guidance                                     December 2009

The following steps provide more detailed information on acquiring and calculating the
necessary data to complete the processes indicated in Figure 10. This methodology was used in
the scenario analyses that follow.

Collecting spatial data for a site
    1.  Collect an aerial orthophotograph for the desired site.
    2.  Digitize land use/land  cover conditions using GIS techniques.  If CAD drawings of the
       site exist, they can be used to estimate land cover area (pervious, impervious).
    3.  Categorize the digitized or planned land use/land cover based on surface hydrologic
       conditions, e.g., rooftop, pavement, and pervious/landscaped area.
    4.  Estimate the size of each land use/land cover category (by polygon).

Determining the 95th percentile, 24-hr rainfall event
    1.  Obtain a long-term 24-hr precipitation data set for the location of interest (i.e., from the
       NCDC Web site or other source).
    2.  Import the data into a spreadsheet. In MS Excel [Data / Import External Data / Import Data]
    3.  Rearrange all of the daily precipitation records into one column if the original data set has
       multiple columns of daily precipitation records.
    4.  Remove all flagged data points (i.e.,  erroneous data points) from the selected data set for
       further analysis.
    5.  Remove small rainfall events (typically less than 0.1 inches) that may not contribute to
       rainfall runoff. These  small storms often produce little if any appreciable runoff from
       most sites and for modeling purposes are typically considered as volume  captured in
       surface depression storage.
    6.  Calculate the 95th percentile rainfall volume by applying the PERCENTILE spreadsheet
       function to a range of data cells. The PERCENTILE function returns the nth percentile
       value  in the specified precipitation data range. This function can be used to determine the
       95th percentile storm event that captures all but the largest 5% of storms. In MS Excel
       [PERCENTILE(precipitation data range,95%)]

Estimating Current Runoff and Placing onsite control measures to capture the 95th percentile
rainfall event
    1.  Collect spatial data for a site, e.g., rooftop, pavement, and pervious  areas  as above.
    2.  Check soil type (USDA mapping, borings, or onsite testing) for the  site to determine
       infiltration parameters. For this modeling, many of the assumptions that pertain to
       generalized soils groups and their infiltration properties come from  the EPA Stormwater
       Management Model (SWMM 4.x) manual (see Appendix A).
    3.  Determine the current  runoff volume that would occur during a 24 hour period by
       applying the 95th percentile rainfall to the existing site conditions (land use  and soil
       properties) as above using a hydrologic model (such as TR-55 or  SWMM). For this
       analysis, it is assumed that the rainfall amount is distributed over  a 24 hour period.
       Actual rainfall event duration (and intensity) was not considered for determining rainfall
       runoff (however, timing was considered when modeling infiltration).
    4.  Determine flow paths so that management practice placements are in locations where
       flows can be intercepted and routed to practices.  Because this is a site specific effort and
       may require detailed topographic information or further surveys this would be a task to be

                                           30

-------
Section 438 Technical Guidance
December 2009
       completed onsite and therefore is not included as a part of the modeling scenario
       exercise.
    5.  Select onsite control practices to capture the current 95th percentile runoff event; base the
       selection of appropriate options on site conditions, areas available for treatment options,
       and other factors such as site use and other constraints.

Note: The steps above have been generalized for the purposes of this guidance.  It is
recommended that a qualified professional engineer determine or verify that stormwater
management practices are sized, placed, and designed correctly.  It should also be noted that the
methodology to determine rainfall amount used a 24 hour time period based on daily records.
Actual rainfall events may have occurred  over shorter or longer time periods. Similarly, for
modeling purposes, the 24 hour rainfall amount was  distributed to pervious and impervious areas
(and management practices) as a uniform  event occurring during a 24-hour period. A large
dataset (greater than 50 years) was used to reasonably represent rainfall depth on a daily bases.
It stands to reason that more frequent, shorter duration precipitation events are better represented
than less frequent, longer duration precipitation events.

Scenarios
Eight locations were selected for the 9 case studies as shown in Figure  11 and Table 2.  Case
study numbers 3 and 8 were both  developed based on the Cincinnati, Ohio facility, although the
site parameters were altered to represent differing site conditions and design constraints. Annual
average rainfall depths for these locations range from 7.5 inches to 48.9 inches. Analyses of the
95th percentile rainfall events for these locations produced rainfall depths that range from 1.00
inch to 1.77 inches (Table 2).
                                                                           orfolk
                 Figure 11. Locations for Analyzing Onsite Control Measures.
                                            31

-------
Section 438 Technical Guidance
December 2009
The government facilities in the 8 case study locations were selected because they represent
generic sites from the major climatic regions of the U.S. These facilities also were selected
because the sites have a range of site characteristics that can be used to illustrate different site
designs and stormwater management options, e.g., pervious, roof, and pavement areas (Table 3).
Site sizes ranged from 0.7 to 27 acres with percent site imperviousness area ranging from 47% to
95% of the site. Aerial photos of the sites are included along with site specific rainfall runoff
and soil results.

Table 2. Summary of Rainfall Data for the Seven Locations.
No
1
2
3
4
5
6
7
8
Location
Charleston, WV
Denver, CO
Cincinnati, OH
Portland, OR
Phoenix, AZ
Boston, MA
Atlanta, GA
Norfolk, VA
NCDC Daily Precipitation Data
Period of record
1/1/1948 - 12/31/2006 (59 yrs)
1/1/1948 - 12/31/2006 (59 yrs)
1/1/1948 - 12/31/2006 (59 yrs)
1/1/1941 - 12/31/2006 (66 yrs)
1/1/1948 - 12/31/2006 (59 yrs)
1/1/1920 - 12/31/2006 (87 yrs)
1/1/1930 - 12/31/2006 (77 yrs)
1/1/1957 - 12/31/2006 (50 yrs)
Coverage
99%
96%
96%
98%
99%
99%
100%
99%
Rainfall Depth (inches)
Annual
average
43.0
15.2
36.5
35.8
7.5
41.9
48.9
45.4
95th percentile
rainfall event
1.23
1.07
1.45
1.00
1.00
1.52
1.77
1.68
The results of the spatial analyses were summarized and divided into three land cover categories;
rooftop, pavement, and pervious area, as shown in Table 3.

Table 3. Summary of Land-use Determinations of the Study Sites.
No
1
2
3
4
5
6
7
8
Location
Charleston, WV
Denver, CO
Cincinnati, OH
Portland, OR
Phoenix, AZ
Boston, MA
Atlanta, GA
Norfolk, VA
Facility Spatial Info (acres)
Rooftop
0.1
0.5
1.6
8.8
0.2
0.9
3.9
0.9
Pavement
0.4
1.9
8.0
16.9
0.7
1.5
10.8
0.55
Pervious
0.2
2.0
9.4
1.3
1.1
1.1
6.2
0.15
Total
0.7
4.5
19
27
2
3.5
21
1.6
Site
Imperviousness
73%
55%
51%
95%
47%
69%
70%
91%
Methods for Determining Runoff Volume

Direct Determination of Runoff Volume
Runoff from each land cover was estimated using a simplified volumetric approach based on the
following equation:

      Runoff = Rainfall - Depression Storage - Infiltration Loss

Again, this methodology does not consider routing of runoff; therefore slope is not considered
when calculating on a volumetric basis.
                                           32

-------
Section 438 Technical Guidance                                       December 2009
Infiltration loss is calculated only in pervious areas (e.g., there is no infiltration in impervious
areas). In this analysis, infiltration was estimated using Horton's equation:

       t11  ./min ~"~ Vmax Jmin) &

       where, Ft= infiltration rate at time t (in/hr)
       fmjn = minimum or saturated infiltration rate (in/hr)
       /nax = maximum or initial infiltration rate (in/hr)
       k = infiltration rate decay factor (/hr) and
       t = time (hr) measured from time runoff first discharged into infiltration area

Infiltration loss for the 24-hr rainfall duration was estimated by the following equation with
assumptions of a half hour At and uniform rainfall distribution in time:

       Infiltration Loss = X (/'A0

To more accurately describe the dynamic process of infiltration associated with Horton's
equation, infiltration loss was integrated over a 24-hour period using a half hour time step while
applying the maximum and minimum infiltration rates (in/hr) with time using the appropriate
soil decay factor.  The results of this process are further illustrated in Appendix A.

Once runoff from each land cover was estimated, the total runoff from a site can be obtained
using an area-weighted calculation as shown below:

       Runoff^ = {(RunoffI00fXAI00f)+(RunOjffpavement X^pavement)+(^WWOJ/7pervious >MperviouS)}/^site

Where Runoff^ = total runoff from the site (inches); Asae = site area (acres); Runoffmof= runoff
from rooftop (inches); Aroof = rooftop area (acres); Runoffvmemsni = runoff from pavement area
(inches); ^pavement = pavement area (acres); Runoffperv[ous = runoff from pervious area (inches);
and ^pervious = pervious area (acres).

An example demonstrating how to calculate runoff by applying the Direct Determination method
is presented below using the Charleston, WV (Scenario #1) site condition presented in Tables 2
and 3.

       Runoffroof      = 95th Rainfall - Depression Storage
                     = 1.23-0.1 = 1.13 inches

       Runoffpwemeni   = 95th Rainfall - Depression Storage
                     = 1.23-0.1 = 1.13 inches

       Runoffperv[ous   = 95th Rainfall - Depression Storage - Infiltration Loss
                     = 1.23 - 0.1 - 9.73 = 0 inches (i.e., no runoff because the result is a
                       negative number)
                                            33

-------
Section 438 Technical Guidance                                     December 2009

       Runoff^ ={(RunqffroofxAroof)+(Runqffpiivemeni xApavemeni)+(Rimqffperv[ous x,4pervious)}/,4site
                ={(1.13 x0.10)+(1.13xQ.41)+(0 xQ.19)}/0.7 = 0.82 inches

Infiltration loss was estimated based on soil type B by applying the Horton equation as described
above. Because the volume removed from surface runoff through infiltration was substantial, no
runoff occurred from the pervious area.

In cases where sites had limited physical space available for stormwater management, a series of
practices was used (e.g., treatment train) to simulate the runoff and infiltrative behavior of the
system. For example, if there was inadequate area and infiltrative capacity to infiltrate 100
percent of the 95th percentile storm event within a bioretention system another onsite
management practice was selected to manage the runoff that could provide the necessary
capacity. In this manner, excess runoff was routed to another management practice in the series
of treatment cells where possible.

Two types of soils were considered for every site: hydrologic soil group B and C (except  for
scenario 8 in which hydrologic soil group D was used). Group B soils typically have between 10
percent and 20 percent clay and 50 percent to 90 percent sand and either loamy sand or sandy
loam textures with some loam, silt loam, silt,  or sandy clay loam soil textures placed in this
group if they are well aggregated, of low bulk density, or contain greater than 35 percent  rock
fragments.  Group C soils typically have between 20 percent and 40 percent clay and less than 50
percent sand and have loam,  silt loam, sandy clay loam, clay loam, and silty clay loam soil
textures with some clay, silty clay, or sandy clay textures placed in this group if they are well
aggregated, of low bulk density, or contain greater than 35 percent rock fragments (USDA-
NRCS, 2007). The application of these hydrologic soil groups was intended to give reasonable
and somewhat conservative estimates of infiltration capacity.

General hydrologic parameters in this analysis were assumed as follows (see Appendix A for
citations of assumptions):

   •  Depression storage (or initial abstraction)
           o   Rooftop: 0.1 inches
           o   Pavement: 0.1 inches
           o   Pervious area: 0.2 inches

   •  Horton Infiltration parameters
           o   Hydrologic Soil Group B
                 •  Maximum infiltration rate: 5 in/hr
                 •  Minimum infiltration rate: 0.3 in/hr
                 •  Decay factor: 2 /hr

           o   Hydrologic Soil Group C
                 •  Maximum infiltration rate: 3 in/hr
                 •  Minimum infiltration rate: 0.1 in/hr
                 •  Decay factor: 3.5 /hr

                                           34

-------
Section 438 Technical Guidance                                     December 2009
   •   Design storage assumptions of control measures
          o   Bioretention: up to 10 inches (but variable based on balancing necessary storage
              volume, media depth for plant survivorship, and surface area limitations)
          o   Green roof:  1 inch (2.5 inches deep media with 40% void space)
          o   Porous pavement: 4 inches (10 inches deep media with 40% void space)

Other Methods for Estimating Runoff Volume
Runoff from a site after applying the 95th percentile storm can be estimated by using a number of
empirical, statistical, or mathematical methods. Several methods were considered in this
analysis. The Rational Method can be used to estimate peak discharge rates and the Modified
Rational Method can be used to develop a runoff hydrograph. The NRCS TR-55 model can be
used to predict runoff volume and peak discharge.  TR-55 can also be used to develop a runoff
hydrograph. The EPA Stormwater Management Model (SWMM) can be used to simulate
rainfall-runoff, pollutant build-up and wash-off, transport-storage-treatment of Stormwater flow
and pollutants, backwater effects, etc. for a wide range of temporal and spatial scales. The
SWMM model can be fit to model a small site with a distributed system.  Hydrologic Simulation
Program - Fortran (HSPF, USD A) is a watershed and land use based lumped model that can be
used to compute the movement of water and pollutants when evaluating the effects of land use
change, reservoir operations, water quality control options, flow diversions, etc. In general,
regionally calibrated modeling parameters are incorporated into HSPF. QUALHYMO is a
complete hydrologic and water quality model, which can be used to factor in snowmelt or soil
moisture conditions or to simulate system behavior based on infiltration and ET, ground water
storage tracking, baseflow and deep volumetric losses, and other variables.

Many of the existing tools for analyzing distributed systems use some part or all of the principles
or formulae of the modeling approaches highlighted above. For example, the Emory ville
spreadsheet control measure model (Emeryville, CA) uses a runoff coefficient (i.e., Rational
Method) for analyzing lot-level to neighborhood-scale control measure sizing. The Green
Calculator (Center for Neighborhood Technologies) estimates the benefit of onsite GI/LID
options on a neighborhood-scale by applying the curve numbers (i.e., TR-55) and the Modified
Rational Method.  The Northern Kentucky Spreadsheet Tool uses a TR-55 based approach for
control measure sizing on neighborhood or site level spatial scales.  The WWHM (Western
Washington Hydrology Model) is a regionally calibrated HSPF model intended for use in sizing
Stormwater detention and water quality facilities to meet the Washington  State Department of
Ecology standards. WBM-QUALHYMO is a Canadian model used in conjunction with the
Water Balance Model (WBM). This model can be used to continuously simulate Stormwater
storage routing, stream erosion, drainage area flow routing, and snowmelt runoff (and ultimately
freeze-thaw). Table 4 contains a summary of these  different methods based on generic modeling
features.
                                          35

-------
Section 438 Technical Guidance
December 2009
Table 4. Potential Methods for Analyzing Control Measures.
Model Considerations
Temporal
scale
Spatial
scale
Outputs
Single Event
Continuous
Simulation
Lot-level
Neighborhood
Regional
Peak
Discharge
Runoff
Volume
Hydrograph
Water Quality
Rational
Method
Yes
No
Yes
Yes
Yes
Yes
Yes
Yesa
No
TR-55
Yes
No
Yesb
Yes
Yesc
Yes
Yes
Yes
No
SWMM
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Direct
Determination
Yes
Possible
Yes
Yes
No
No
Yes
No
Possible
HSPF
Yes
Yes
No
Possible
Yes
Yes
Yes
Yes
Yes
QUALHYMO
Yes
Yes
No
Possible
Yes
Yes
Yes
Yes
Yes
 a Modified Rational Method
 b No less than 1 acre.
 0 No more than 25 square miles (up to 10 subareas).
From the viewpoint of modeling both lot-level and neighborhood scale projects, the Rational
Method, NRCS TR-55,  SWMM, and Direct Determination approaches were selected for use in
scenario analyses.  Strength and weakness of these methods are presented below:

Table 5. Comparison of approaches for determining runoff volume.
Method
Direct
Determination
Rational
Method
TR-55
SWMM
Strengths
• Methodology for runoff determination
is same as SWMM
• Models basic hydrologic processes
directly (explicit)
• Simple spreadsheet can be used
• Method is widely used
• Simple to use and understand
• Method is widely used
• Simple to use and understand
• Method is widely used
• Can provide complete hydrologic and
water quality process dynamics in
stormwater analysis
Weaknesses
• Direct application of Morton's method may
estimate higher infiltration loss, especially at
the beginning of a storm
• Does not consider flow routing
• Cannot directly model storage-oriented onsite
control measures
• May not be appropriate for estimating runoff
from small storm events because depression
storage is not well accounted for
• Needs a number of site-specific modeling
parameters
• Generally requires more extensive experience
and modeling skills
Each method requires specific parameters for estimating runoff from a site. Runoff coefficients
for the Rational Method are assumed to be 0.9 for rooftop and pavement areas, and 0.1 and 0.135
for Group B and C soil pervious areas, respectively (Caltrans, 2003).  The slope of the pervious
area was assumed to be an average of 2%.  Applying these runoff coefficients for each surface,
the overall area-weighted runoff coefficient can be determined.
                                          36

-------
Section 438 Technical Guidance                                     December 2009

When applying the NRCS TR-55 method, Curve Numbers (CNs) should be determined for each
drainage area.  For rooftop and pavement areas the CN was assumed to be 98, and pervious area
CN was determined on the basis of the hydrologic soil group and the status of grass cover
condition. Curve numbers for pervious areas were assumed to be 61 and 74 for Group B and C
soils, respectively, with an assumption of over 75% grass cover. The overall  CN can be
estimated by using an area-weighted calculation (USDA-SCS, 1986).

In SWMM modeling, infiltration was modeled using Horton's equation.  The same infiltration
parameters and depression storage  values used in the direct determination method of runoff
treatment volume described earlier were applied to the SWMM analyses. The average slope of
the pervious area was again assumed to be 2%. The same uniform rainfall distribution and time
step was applied for the SWMM model runs.

Runoff Methodology Results
Stormwater management practice sizes (and depth) were determined using the Direct
Determination approach to capture the volume of runoff generated in a 95th percentile rainfall
event at each location. Total acreage,  impervious area, the 95th percentile rainfall event, the
current expected runoff for the 95th percentile rainfall event, and the future runoff with
stormwater management controls were reported for each site.  Results were summarized for the
two soil types (three soil types for scenarios #3 and #8 in Cincinnati).  The spatial location of
onsite control measures was also illustrated in the site aerial photo figures.  Note that site
practices were placed only on undeveloped or landscaped areas without regard for true flow
paths or technical feasibility. It may be preferred to place practices in existing impervious areas,
if possible. For the purposes of this modeling exercise, the least cost and most practical solutions
were used, i.e., locating bioretention systems on undeveloped or landscaped areas.  On an actual
site, flow paths would be determined and berms and swales might be used to route runoff to
areas that are most suitable for infiltration. In other cases, areas that are currently impervious
could be modified to accept runoff, e.g., impermeable pavements removed and replaced by
permeable, sidewalks could be redesigned to include sidewalk bioretention cells and streets
could be designed with flow through or infiltration curb bumpouts/raingardens.

To compare other approaches of runoff estimation, alternate methodologies were also employed
for three scenarios. TR-55 was used for Scenario #1 (Atlanta), the Rational Method was applied
to Scenario #2 (Denver), and the SWMM was run for Scenario #7 (Charleston).

Although flood control is not the focus of this guidance, most localities have flood control
requirements that will need to be considered in designing control measures to comply with
Section 438. For flood control purposes, TR-55 was used to model the 10 year frequency design
storm for each site under the assumption that all stormwater management practices were in place.
The 10-year design storms were selected from the NRCS TR-55 Manual (USDA, 1986) for both
the Eastern U.S.  and the Western U.S. Precipitation Frequency Maps
(www.wrcc.dri.edu/pcpnfreq.html). The 10-year frequency design  storm was selected because it
represents a common design standard used by state and local governments in  order to manage
peak rates of runoff and prevent flooding.
                                           37

-------
Section 438 Technical Guidance                                     December 2009

COST ESTIMATES FOR SELECTED SCENARIOS
Scenarios #2 and 7 include cost estimates comparing the capital costs for a design to comply
with Section 438 (retention of the 95th percentile rainfall event) and capital costs for a traditional
stormwater management design (e.g., typical curb and gutter, off-site pond for stormwater
management). These costs are based on average unit costs to construct both traditional and
GI/LID controls.
                                          38

-------
Section 438 Technical Guidance
December 2009
Scenario #1 - Charleston, WV
A 0.7-acre site with 73% impervious area was selected from Charleston, West Virginia (Figure
12).  If the 95th percentile rainfall event (1.23 inches) occurred on the existing site (i.e., with no
control measures), 0.82 inches of runoff using the Direct Determination method would be
generated and require management. The runoff from the 95th percentile rainfall event could be
retained by the installation of bioretention systems totaling 0.03 acres if hydrologic soil group B
is present, or 0.06 acres if hydrologic soil group C (Table 6) is the predominant soil type on the
site.  Assuming that bioretention practices are placed in areas that are currently pervious or
landscaped, a total of 0.2 acres of pervious area would be available for the placement of
bioretention systems.  The effective design storage depth within the designated bioretention area
was  8 inches.
         (£3 Bio-retention
          ^^^^^^^^^^^m
Figure 12. Actual Site and Onsite Control Measures (Charleston, WV)

Table 6. Estimated Sizes of Onsite Control Measures for Scenario #1 (Charleston, WV)
Total Area (acres)
Estimated Imperviousness (%)
95th Percentile Rainfall Event (inches)
Expected Runoff for the 95th Percentile Rainfall Event (inches)
Stormwater Management Area Required

Bioretention estimated by Direct Determination method (acres)
Bioretention estimated by SWMM (acres)
Off-site storage necessary to control the 10-yr
event of 3.9 inches (acre-ft)
With onsite controls
Without onsite controls
0.7
73%
1.23
0.82
Hydrologic Soil Group
B
0.03
0.03
0.10
0.16
C
0.06
0.05
0.12
0.17
Note: The two hydrologic methods used (direct determination and SWMM) estimated similar
bioretention sizes.
                                            39

-------
Section 438 Technical Guidance
December 2009
Scenario #2 - Denver, CO
A 4.5-acre site with 55% impervious area was selected from Denver, Colorado (Figure 13).  If
the 95th percentile rainfall event (1.07 inches) occurred on the existing site (i.e., with no control
measures), 0.53 inches of runoff from the site would be generated and require management. The
runoff from the 95th percentile rainfall event could be retained by the installation of bioretention
systems totaling 0.16 acres if the hydrologic soil group B is present or 0.3 acres if hydrologic soil
group C (Table 7) is the predominant soil type on the site. Assuming that bioretention practices
are only placed in areas that are currently pervious or landscaped, a total of 2 acres of pervious
area is available for the placement of bioretention systems. The design storage depth of media
within the designated bioretention area was 6 inches.
               Figure 13. Actual Site and Onsite Control Measures (Denver, CO)

Table 7. Estimated Sizes of Onsite Control Measures for Scenario #2 (Denver, CO)
Total Area (acres)
Estimated Imperviousness (%)
95th Percentile Rainfall Event (inches)
Expected Runoff for the 95th Percentile Rainfall Event (inches)
Stormwater Management Area Required

Bioretention estimated by the Direct Determination method (acres)
Bioretention estimated by Rational Method (acres)
Off-site storage necessary to control the
10-yr event of 3.2 inches (acre-ft)
With onsite controls
Without onsite controls
4.5
55%
1.07
0.5 3
Hydrologic Soil Group
B
0.16
0.16
0.35
0.64
C
0.3
0.28
0.52
0.64
                                           40

-------
Section 438 Technical Guidance
December 2009
Cost estimates were also developed for this scenario (Table 8) to compare the costs of installing
onsite control measures to retain the 95th percentile rainfall event versus the costs to install
traditional stormwater management controls (e.g., curbs and gutters combined with off-site
retention such as extended detention wet ponds). In a GI/LID scenario, the bioretention cell
would occupy a specified area.  This same area in a traditional design would be covered in turf
since the pond would typically be offsite and not occupy the area planted in turf.  Table  8
includes this cost under the traditional column. Note: typical land development practices involve
mass clearing and grading so little or no pre-existing vegetation is typically retained. It is also
assumed that the use of GI/LID practices would require less underground infrastructure because
the traditional design typically routes stormwater underground to an off-site pond via pipes or
culverts while GI/LID practices are designed to manage runoff onsite and as close to its source as
possible. They are also dispersed across the site and routing occurs through surface drainage via
bioswales and overland flow. As a result GI/LID practices do not require as much or any hard or
grey infrastructure. The cost estimates were developed for Hydrologic Soil Group B.

Table 8. Estimated Costs for Scenario #2 (Denver, CO)
Sizes of Onsite Control Practices

Rainfall depth
(in)
Bioretention (acres)
Paver blocks (acres)
Green roof (acres)
Off-site Pond
WQV (ac-ft)
10-Yr Fid Cntr (ac-ft)
Total Off-Site Requirement (ac-ft)
Land Area (assumes avg 3 ft depth)
% of the site

Controls for 95th Percentile Event
1.07
0.1
0
0
-
0.15
0.15
0.05
2.8%

Traditional Stormwater Controls




0.18
0.14
0.32
0.11


Costs of Onsite Control Practices
Biorention/alternative
Off-site Pond
Infrastructure
WQV (ac-ft)
10-Yr Fid Cntr (ac-ft)
Pipe
Inlet
Land Area (assumes $300K/acre)
Sum
% difference from Traditional
$32,495

$10,073
$8.990
$9.920
$14,500
$75,978
-17.3%
$4,187
$14,833
$9,527
$16,982
$14,880
$31,500
$91,909

                                            41

-------
Section 438 Technical Guidance
December 2009
Scenario #3 - Cincinnati, OH
A 19-acre site with 51% impervious area was selected in Cincinnati, Ohio (Figure 14).  If the
95th percentile rainfall event (1.45 inches) occurred on the existing site (i.e., no control measures
were in place), 0.68 inches of runoff from the site would be generated and require management.
The runoff from the 95th percentile rainfall event could be retained by the installation of
bioretention systems totaling 0.8 acres if the hydrologic soil group B is present or 1.3 acres if
hydrologic soil group C (Table 9) is the predominant soil type on the site.  Assuming that
bioretention practices are only placed in areas that are currently pervious or landscaped, a total of
9.4 acres of pervious area is  available for the placement of bioretention systems.  The design
storage depth of media within the designated bioretention area was 8 inches.
                                   'Ğ•—•£-*•
              Figure 14. Actual Site and Onsite Control Measures (Cincinnati, OH)

Table 9. Estimated Sizes of Onsite Control Measures for Scenario #3 (Cincinnati, OH)
Total Area (acres)
Estimated Imperviousness (%) ^^^^^^^^^^^^^^^H
95th Percentile Rainfall Event (inches)
Expected Runoff for the 95th Percentile Rainfall Event (inches)
Stormwater Management Area Required

Bioretention estimated by the Direct Determination (acres)
Off-site storage necessary to control the 10-yr
event of 4.2 inches (acre-ft)
With onsite controls
Without onsite controls
19
51%
1.45
0.68
Hydrologic Soil Group
B
0.8
2.42
3.29
C
1.3
3.24
3.73
                                            42

-------
Section 438 Technical Guidance
December 2009
Scenario #4 - Portland, OR
A 27-acre site with 95% impervious area was selected in Portland, Oregon (Figure 15).
              If the
  -th
95  percentile rainfall event (1.0 inches) occurred on the existing site (i.e., no control measures),
0.86 inches of runoff would be generated and require management.  This site has the greatest
imperviousness among the 7 sites.

Given these site conditions, there is not enough pervious area to manage the entire runoff volume
discharged by the 95th percentile rainfall event with bioretention.  As a result, other practices
were evaluated and selected. The practices integrated into the design included a green roof,
cisterns, and porous pavement. Based on the technical considerations of constructing and
maintaining control measures at the site, it was assumed that approximately 30% of the available
pervious area could be converted into bioretention cells; 20% of total rooftop area could be
converted into green roofs;  40%  of paved area could be converted into paver blocks; and 50,000
gallons of total volume could be  captured in cisterns for use on this urbanized site.  Using this
system of four different practices, all runoff for the 95th percentile rainfall event would be
retained (Table 10).
                                                     Bio-retention     Porous Pavement
               Figure 15. Actual Site and Onsite Control Measures (Portland, OR)
                                            43

-------
Section 438 Technical Guidance
December 2009
Table 10. Estimated Sizes of Onsite Control Measures for Scenario #4 (Portland, OR)
Total Area (acres)
Estimated Imperviousness (%)
95th percentile Rainfall Event (inches)
Expected Runoff for the 95th Percentile Rainfall Event (inches)
Stormwater Management Area Required

Paver block area estimated by Direct Determination (acres)
Bioretention estimated by Direct Determination (acres)
Green Roof estimated by Direct Determination (acres)
Cistern volume estimated by Direct Determination (gallons)
Off-site storage necessary to control the 10-yr
event of 3.7 inches (acre-ft)
With onsite controls
Without onsite controls
27
95%
1.00
0.86
Hydrologic Soil
B
1.4


Group
C
3.5*
0.4
1.7
50,000
5.37
7.70


5.62
7.71
 *The size of porous pavement area was increased because the other control options were maximized based on
A total of 1.3 acres of the site is pervious area or landscaped of which, 0.4 acres (30% of the
pervious area) could be converted to bioretention cells that have a storage depth of 10 inches. Of
the 8.8 acres of current rooftop area, 1.7 acres (20% of the rooftop area) could be retrofitted into
green roof areas. Of the 16.9 acres of paved area, 1.4 acres (8% of the paved area) for hydrologic
soil group B,  or 3.5  acres (20% of the paved area) for hydrologic soil group C, of paver block
systems could be implemented.  One or more cisterns (as indicated in Figure 15) could be used to
capture up to 50,000 gallons of runoff from rooftop areas. Note: The high percentage of
imperviousness of the site (95%) requires that all infiltration designs be based on resident soil
type and design volumes, or with adequate sub-bases or amended soils.
                                           44

-------
Section 438 Technical Guidance
                                    December 2009
Scenario #5 - Near Phoenix, AZ
A 2-acre site with 47% impervious area was selected near Phoenix, Arizona (Figure 16).  If the
95th percentile rainfall event (1.0 inches) occurred on the existing site (i.e., with no control
measures), 0.42 inches of runoff would be generated and require management. The runoff from
the 95th percentile rainfall event could be retained by installing bioretention systems totaling 0.06
acres if the hydrologic soil group B is present or 0.1 acres if hydrologic soil group C (Table 11)
is the predominant soil type on the site.  Assuming that bioretention practices are only placed in
areas that are currently pervious or landscaped, a total of 1.1 acres of pervious area is available
for the placement of these practices.  The design storage depth of media within the designated
bioretention area was 6 inches. Note: If the design storage depth were increased to 10 inches,
the off-site storage necessary for the  10-year event could be reduced to 0.03 acre-ft for type B
soils and 0.08 acre-ft for type C soils.
                Figure 16. Actual Site and Onsite Control Measures (Phoenix, AZ)

Table 11. Estimated Sizes of Onsite Control Measures for Scenario #5 (Phoenix, AZ)
 Total Area (acres)
 Estimated Imperviousness (%
 95th Percentile Rainfall Event (inches)
 Expected Runoff for the 95th Percentile Rainfall Event (inches)
 Stormwater Management Area Required
       Bioretention estimated by the Direct Determination (acres)
    Off-site storage necessary to control
   the 10-yr event of 2.4 inches (acre-ft)
   With onsite controls
Without onsite controls
                                1.00
                                0.42
                        Hydrologic Soil Group
                                                             B
                         0.06
0.05
0.18
                                        C
              0.1
0.12
0.18
                                             45

-------
Section 438 Technical Guidance
                             December 2009
Scenario #6 - Boston, MA
A 3.5-acre site with 69% impervious area was selected in Boston, Massachusetts (Figure 17). If
the 95th percentile rainfall event (1.52 inches) occurred on the existing site (i.e., with no control
measures), 0.98 inches of runoff would be generated and require management. Given these site
characteristics, there is adequate area to place appropriately sized bioretention cells to capture the
95th percentile storm event.  However, for the purposes of this analysis, unspecified conditions
preclude the use of bioretention.  As a result, a paver block system was selected as the best onsite
control measure and the system was designed such that the necessary design parameters could be
achieved by storing some of the volume in the paver media and by infiltrating the remainder of
the volume. The runoff from the 95th percentile rainfall event could be retained by installing a
paver block area totaling 0.4 and 0.8 acres assuming soil types B and C, respectively (Table 12).
For the purposes  of this case study, a total of 1.5 acres of parking lot was made available to
accommodate the paver block system.  The area retrofitted with paver blocks  would primarily be
dedicated for use as parking stalls.
                Figure 17. Actual Site and Onsite Control Measures (Boston, MA)

Table 12. Estimated Sizes of Onsite Control Measures for Scenario #6 (Boston, MA)
 Total Area (acres)
 Estimated Imperviousness (%)
                               69%
 95th Percentile Rainfall Event (inches)
 Expected Runoff for the 95  Percentile Rainfall Event (inches)
 Stormwater Management Area Required
                       Hydrologic Soil Group
                                                                  B
            Paver block area estimated by Direct Determination (acres)
                         0.4
    Off-site storage necessary to control
      10-yr event of 4.5 inches (acre-ft)
   With onsite controls
0.59
0.71
Without onsite controls
0.89
0.96
                                             46

-------
Section 438 Technical Guidance
December 2009
Scenario #7 - Atlanta, GA
A 21-acre site with 70% impervious area was selected in Atlanta, Georgia (Figure 18). If the
95th percentile rainfall event (1.77 inches) occurred on the existing site (i.e., with no control
measures), 1.17 inches of runoff would be generated and require management.  The runoff from
the 95th percentile rainfall event could not be adequately retained solely with bioretention
systems. Based on the technical considerations of constructing and maintaining control
measures at the site, it was assumed that up to 15% of the pervious area could be converted into
bioretention cells and up to 40% of paved area could be converted into a paver block system. If
the stormwater management techniques used on the site includes both bioretention and paver
blocks as presented in Table 13, then all runoff for the 95th percentile rainfall event would be
controlled.
                Figure 18. Actual Site and Onsite Control Measures (Atlanta, GA)

Table 13. Estimated Sizes of Onsite Control Measures for Scenario #7 (Atlanta, GA)
Total Area (acres)
Estimated Imperviousness (%)
95th Percentile Rainfall Event (inches)
Expected Runoff for the 95th Percentile
Rainfall Event (inches)
Stormwater Management Area Required


Bioretention estimated by the Direct Determination (acres)
Paver block area estimated by the Direct Determination (acres)
Bioretention estimated by TR-55
Paver block area estimated by TR-55
Off-site storage necessary to control
10-yr event of 6.0 inches (acre-ft)
With onsite controls
Without onsite controls
21
70%
1.77
1.17
Hydrologic Soil Group
B
C
0.9
0.9
0.8**
o**
5.85
7.25
3.2*
0.9
1.84
6.62
8.49
 *The size of porous pavement was increased because the bioretention already reached its
 maximum size based on the site-specific design assumptions.
 **Because TR-55 estimated smaller runoff in this scenario, bioretention can retain all of the 95th
 percentile runoff if the site has soil group B.
                                             47

-------
Section 438 Technical Guidance
December 2009
For the example site in Atlanta, GA, areas of 1.8 acres for hydrologic soil group B, and 4.1 acres
for hydrologic soil group C, would be required to manage the runoff discharged from a 95th
percentile rainfall event. Assuming that bioretention practices are only placed in areas that are
currently pervious or landscaped, a total of 6.2 acres of pervious area is available for the
placement of bioretention systems.  The design storage depth of media within the designated
bioretention area was 10 inches. Permeable pavement systems could be used to treat the
remaining volume on the 10.8 acres of existing paved area.

In applying the TR-55 model, the overall curve numbers for the site were 87 and 91 for Group B
and C soils, respectively. TR-55 was used to estimate 0.73 inches of runoff for soil group B and
0.97 inches for soil group C, which are smaller numbers than the  1.17 inches of runoff estimated
by the Direct Determination method. As a result, the sizes of the onsite control measures
designed using the TR-55 model were smaller than those designed using the Direct
Determination method. Note: It is recommended that caution be exercised when using TR-55 to
model storms less than 0.5 inches per event. See application of TR-55 in Table 5.

Cost estimates were also developed for this scenario (Table  14) to compare the costs to install
onsite control measures to retain the 95th percentile rainfall event, and costs to install traditional
stormwater management controls (e.g., primarily curb and gutter with off-site retention). The
cost estimates were developed for Hydrologic Soil Group B.

Table 14. Estimated Costs for Scenario #7 (Atlanta, GA)
Sizes of Onsite Control Practices

Rainfall depth
(in)
Bioretention (acres)
Paver blocks (acres)
Off-site Pond
WQV (ac-ft)
10-Yr Fid Cntr (ac-ft)
Total Off-Site Requirement (ac-ft)
Land Area (assumes avg 3 ft depth)
% of the site
Controls for 95th Percentile Event
1.77
0.94
0.86
-
0.84
0.84
0.28
8.5%
Traditional Stormwater Controls



1.75
0.0
1.75
0.58


Costs of Onsite Control Practices
Biorention/alternative
Paver block/alternative
Off-site Pond
Infrastructure
WQV (ac-ft)
10-Yr Fid Cntr (ac-ft)
Pipe
Inlet
Land Area (assumes $300K/acre)
Sum
% difference from Traditional
$232,923
$236,878
$0
$39,648
$54,827
$52,080
$84,000
$700,356
9.9%
$30,617
$88,409
$72,888
$0
$191,095
$79,360
$175,000
$637,368

                                           48

-------
Section 438 Technical Guidance                                      December 2009

Scenario #8 - Cincinnati, OH
A 19-acre site with 51% impervious area was selected in Cincinnati, Ohio (Figure 19).  If the
95th percentile rainfall event (1.45 inches) occurred on the existing site (i.e., with no control
measures), 0.68 inches of runoff would be generated and require management.  The runoff from
the 95th percentile rainfall event could be retained by the installation of bioretention systems
totaling 0.8 acres if the hydrologic soil group B is present or 1.3 acres if hydrologic soil group C
(Table 9) is the predominant soil type on the site. Assuming that bioretention practices are only
placed in areas that are currently pervious or landscaped, a total of 9.4 acres of pervious area is
available for the placement of bioretention systems.  The design storage depth of media within
the designated bioretention area was 8 inches.

Scenario #8 represents an alternative to the Cincinnati, scenario in #3 (Figure 14).  In this case,
hydrologic soil group D was selected to represent the soil characteristics present for the entire
site.  Alternatively, simulations could have been run under the assumption that the use of
infiltration practices were precluded by contaminated soils or high ground water tables.  Under
these site conditions, bioretention options are severely limited and cannot be used to adequately
capture the entire 95th percentile storm event. As a result, options such as cisterns and green
roofs were considered. In the absence of management practices, the 95th percentile rainfall event
discharges 1.45 inches of stormwater and 0.53 inches of this runoff is captured by onsite
depression storage. The difference, 0.92 inches of runoff, would then require capture and
management. Based on the technical considerations of constructing and maintaining controls at
the site, it was assumed that up to 20% of pervious area can be converted into bioretention areas;
up to 30% of paved area can be converted into porous pavement; and up to 30% of the rooftop
area can be converted into green roofs. Cisterns can be added to the system if additional storage
volume is required. It should be noted that green roofs were selected lowest in the hierarchy of
practices evaluated because of cost and potential structural issues associated with  design and
placement on existing buildings. By  using the four onsite control options as presented in Table
15, all  runoff for the 95th percentile rainfall event would be retained. From a management
perspective, it was assumed that the design storage depth within the designated bioretention area
was 6 inches because of the low infiltration rates adopted for this scenario.
                                            49

-------
Section 438 Technical Guidance
December 2009
              Bio-retention  E=i Green Roof     Porous Pavement (   ] Cistern  ^ .
             ^—              	^f .— i.  •	w— _ ' •- _
              Figure 19. Actual Site and Onsite Control Measures (Cincinnati, OH)
Table 15. Estimated Sizes of Onsite Control Measures for Scenario #8 (Cincinnati,
Total Area (acres)
Estimated Imperviousness (%)
95th Percentile Rainfall Event (inches)
Expected Runoff for the 95th Percentile Rainfall Event (inches)
Stormwater Management Applied
Bioretention estimated by Direct Determination (acres)
Paver block area estimated by Direct Determination (acres)
Green Roof estimated by Direct Determination (acres)
Cisterns estimated by Direct Determination (gallons)
19
51%
1.45
0.92
Hydrologic Soil Group D
1.9
2.4
0.5
13,000
       OH)
This site contains a total of 9.4 acres of pervious area, 8.0 acres of paved area, and 1.6 acres of
rooftop area.  If 1.9 acres (20%) of the pervious area were converted to bioretention cells; 2.4
acres (30%) of parking lot converted to paver blocks; and 0.5 acres (30%) of rooftop area were
retrofitted to green roof areas for this site, then 97% of stormwater runoff from the 95th percentile
storm would be captured on site. By also adding one or more cisterns (as indicated in Figure 19),
an additional  13,000 gallons could be captured, thus illustrating that 100% of the rainfall from
the 95th percentile event can be managed onsite with GI/LID practices.
                                            50

-------
Section 438 Technical Guidance
                         December 2009
Scenario #9 - Norfolk, VA
A 1.6 acre site with 91% impervious area was selected from Norfolk, Virginia. Table 16
contains the land use categories for the site. Figure 20 depicts the site and associated facilities.
Site specific factors based on an METF analysis allow management of 75 % of the 95th percentile
storm onsite (1.27 inches).  The remaining portion of the 95th percentile rainfall event (0.41
inches would be discharged off of the site.

Table 16. Land Use Determination After Redevelopment
Land Use
Building
Parking
Streets/Sidewalks
Undeveloped
Total
Acres
0.90
0.35
0.20
0.15
1.60
Site Coverage Percent
56.3
21.9
12.5
9.3
100%
         SHEETS:
         CS101.CG101.CU1Q1
SHEETS:
CS1Q2.CG102.CU1Q2
         SHEETS:
         C$103, CG103,
         CU103
                                                                       SHE!~
                                                                    t CS104,
                                                                       CG'04,
        SHEETS:
        CS10S,
        CG105,
        GUI 05  ..'
                          CG-oe,
                       V CU106
                        Figure 20. Proposed Redevelopment Scenario
                                             51

-------
Section 438 Technical Guidance
 December 2009
                                                           Redevelopment Site
                                 Norfolk
1
                                                 Naval Station
                                                   Norfolk
     Norfolk
   Naval Station
                         Figure 21. Location of Facility (Norfolk, VA)

Site conditions and intended uses limited the number of practices that were technically feasible
to use onsite to manage runoff. For example, the use of a green roof was not feasible because the
project includes the construction of an airplane hanger which lacks the structural strength to
support a green roof. Cisterns were also not included in the set of suitable practices based on the
analysis, which considered the number of people and amount of daily water use at the site, i.e.,
40 people x 3.5 toilet flushes per day would use only 280 gallons of runoff per day or 2,000
gallons per week. Stormwater use for HVAC make-up would also be negligible based on the
typical cooling system design. To put things in perspective, if the hanger rooftop covers the
entire building footprint, 41,000 gallons of runoff would be generated from a 1.68 inch rainfall.
Assuming a drawdown of 2,000 gallons per week based on toilet flushing, the users would only
use 5% of the 95th percentile event. Because of the relatively large volume of water that would
need to be collected and used, cisterns were not considered a feasible option to manage a
significant volume of runoff at the site.

However, site  conditions did allow for the use of both permeable pavement and bioretention
practices. Approximately 0.15 acres (6,500 sf) of the proposed site is undeveloped and available
for bioretention. Based on Department of Defense facility requirements, ten percent of the
parking area is designed with landscaping, usually around the perimeter and in landscaped
islands.  If this  ten percent were designed as bioretention cells, then 0.035  acres of bioretention
would be achieved. If bioretention cells were also placed in about  30% of the undeveloped area
of the project,  then an additional 0.045 acres of bioretention could be implemented. Note: not all
undeveloped land was assumed to be available for bioretention because of conflicts with site
                                           52

-------
Section 438 Technical Guidance
December 2009
utilities, security and anti-terrorism requirements and slopes that limited the use of infiltration
practices directly adjacent to the hanger.
                                              Bio-retention (  J  Porous Pavement
               Figure 22. Actual Site and Onsite Control Measures (Norfolk, VA)

Table 17. Estimated Sizes of Onsite Control Measures for Scenario #9 (Norfolk, VA)
Total Area (acres)
Estimated Imperviousness (%)
95th Percentile Rainfall Event (inches)
Expected Runoff for the 95th Percentile Rainfall Event (inches)
Stormwater Management Area Required
Porous Pavement estimated by Direct Determination method (acres)
Bioretention estimated by Direct Determination method (acres)
1.6
91%
1.68
1.50
Hydrologic Soil Group D
0.21
0.08
The bioretention cells were designed with an effective storage depth of 10 inches, which
included a depth from media surface to outlet of 10 inches.  In this case study, state regulations
precluded the project from taking credit for the storage potential provided by the void space
within the bioretention cell media. Similarly, approximately 0.55 acres of the proposed site is
impervious due to parking lots, streets, and sidewalks. Due to manufacturer's recommendations
that permeable pavement materials not be used in applications subject to heavy loads and
potential pollutant exposure the access roads and parking lot access isles were assumed to be
constructed from conventional impervious concrete or asphalt. Thus 60% of the parking area
(primarily parking stalls and sidewalks), which is about 38% of the entire paved area, is assumed
to be suitable for paver blocks. A high water table at the site limited the modeled net storage
depth under paver blocks placed in the parking areas and sidewalks to four inches. This storage
was calculated using the assumption that the pavement sub-base of 12 inches would have a
minimum void space of approximately 30%.
                                           53

-------
Section 438 Technical Guidance
December 2009
COMPARISON OF THE RUNOFF ESTIMATION METHODS
As illustrated in each of the case studies above, runoff of the 95th percentile storm was estimated
in order to size onsite control measures.  These estimates were produced by applying four
different methods: the Direct Determination method, the Rational Method, the NRCS TR-55, and
the EPA SWMM. The results comparing each of these methods for scenarios 1-7 are presented
in Table 18.

Table 18. Comparison of the estimated runoff (unit: inches)
Method
Soil Groups
1
2
3
4
5
6
7
Charleston, WV
Denver, CO
Cincinnati, OH
Portland, OR
Phoenix, AZ
Boston, MA
Atlanta, GA
Direct
Determination
B
0.82
0.53
0.68
0.86
0.42
0.98
1.17
C
0.82
0.53
0.68
0.86
0.42
0.98
1.17
Rational Method
B
0.83
0.57
0.73
0.86
0.46
0.99
1.17
C
0.84
0.59
0.76
0.86
0.48
1.00
1.19
TR-55
B
0.36
0.12
0.26
0.63
0.06
0.51
0.73
C
0.53
0.26
0.46
0.71
0.17
0.70
0.97
SWMM
B
0.82
0.53




1.19
C
0.83
0.53




1.23
As shown in the above table, the estimated runoff results from direct determination, the Rational
Method, and SWMM are relatively similar. Runoff volumes using TR-55 are lower than the
other estimates. SWMM modeling results using NRCS 24-hour rainfall distributions were nearly
identical to the results based on uniform distribution.

Table 19. Applicability of the methods for analyzing onsite control measures
Purpose
Planning Tool
Preliminary Design
Detailed Design
Actual Assessment (Long-term)
Water Quality
Direct
Determination
Applicable
Applicable
Not applicable
Not applicable
Not applicable
Rational Method
Applicable
Applicable
Not applicable
Not applicable
Not applicable
TR-55*
Applicable
Applicable
Not applicable
Not applicable
Not applicable
SWMM
Applicable
Applicable
Applicable
Applicable
Applicable
 *Use with caution when applying this method for small storms
CONCLUSIONS

Although sites varied in terms of climate and soil conditions, in most of the scenarios selected,
the 95th percentile storm event could be managed onsite with GI/LID systems.  There are other
infiltration, evapotranspiration and capture and use stormwater management options available
than those used in these analyses. These options provide site managers additional flexibility to
choose appropriate systems and practices to manage site runoff.
                                          54

-------
 Section 438 Technical Guidance                                    December 2009

 REFERENCES

 Booth, Derek Direct Testimony. 2008. Pollution Control Hearings Board for the State of
 Washington, Puget Soundkeeper Alliance and People for Puget Sound; Pierce County Public
 Works and Utilities Department; City of Tacoma; The Port of Seattle; Snohomish County; Clark
 County; and Pacificorp and Puget Sound Energy, Appellants, vs. Department of Ecology,
 Respondent, and King County; City of Seattle; Port of Tacoma, and Washington State
 Department of Transportation, Intervenors, August 2008.

 California Department of Transportation (Caltrans). 2003. Caltrans Storm Water Quality
 Handbooks. California Department of Transportation.

 Casey Trees. 2007. The Case for Trees-Relieffrom Summer Heat,
 www.casevtrees.org/resources/casefortrees.html.

 Galli, John. 1991.  Thermal Impacts Associated with Urbanization and Stormwater Best
 Management Practices in Maryland, Anacostia Restoration Team for the Maryland Department
 of the Environment, Washington, DC.

 Grant, Gary, Luke Engleback and Barry Nicholson. 2003.  Green Roofs: Their Existing Status
 and Potential for Conserving Biodiversity in Urban Areas, Report Number 498, English Nature
 Research Reports.

 Hathaway, 1, and W.F. Hunt. 2007. Stormwater BMP Costs. North Carolina Department of
 Environment and Natural Resources.
 www.bae.ncsu.edu/stormwater/PublicationFiles/DSWC.BMPcosts.2007.pdf.

 Hirschman, David and John Kosco. 2008. Managing Stormwater in Your Community: A Guide
for Building an Effective  Post-Construction Program, Center for Watershed Protection,
 www. cwp. org/postconstruction.

 Holz, Thomas Written Direct Testimony. 2008. Pollution Control Hearings Board for the State
 of Washington, Puget Soundkeeper Alliance and People for Puget Sound; Pierce County Public
 Works and Utilities Department; City of Tacoma; The Port of Seattle; Snohomish County; Clark
 County; and Pacificorp and Puget Sound Energy, Appellants, vs. Department of Ecology,
 Respondent, and King County; City of Seattle; Port of Tacoma, and Washington State
 Department of Transportation, Intervenors, August 2008.

 Horner, Richard Direct Testimony.  2008. Pollution Control Hearings Board for the State of
 Washington, Puget Soundkeeper Alliance and People for Puget Sound; Pierce County Public
 Works and Utilities Department; City of Tacoma; The Port of Seattle; Snohomish County; Clark
 County; and Pacificorp and Puget Sound Energy, Appellants, vs. Department of Ecology,
 Respondent, and King County; City of Seattle; Port of Tacoma, and Washington State
 Department of Transportation, Intervenors, August 2008.
                                          55

-------
Section 438 Technical Guidance                                    December 2009

National Climatic Data Center (NCDC). 2007. NCDC precipitation data, CD-ROM, National
Climatic Data Center.

National Research Council. 2008. Urban Stormwater Management in the United States, The
National Academies Press, Washington, DC.
Shaver, E., R. Horner, J. Skupien, C. May, and G. Ridley. 2007. Fundamentals of Urban Runoff
Management: Technical andlnstituti
Management Society, Madison, WI.
Management: Technical and Institutional Issues - 2nd Edition, North American Lake
Schueler, T. and M. Helfrich. 1988.  "Design of Wet Extended Detention Pond Systems," Design
of Urban Runoff Controls, L. Roesner and B. Urbonas eds., American Society of Civil
Engineers, New York, NY.

Schueler, T and H. Holland. 2000. The Practice of Watershed Protection: Techniques for
Protecting our Nation's Streams, Lakes, Rivers, and Estuaries. Center for Watershed Protection,
Ellicott City, MD.

U.S. Department of Agriculture, Natural Resources Conservation Service. 2007.  National
Engineering Handbook, title 210-VI. Part 630, chapter 7. Washington, DC.
http://directives.sc.egov.usda.gov/.

U.S. Department of Agriculture, Soil Conservation Service. 1986. Urban Hydrology for Small
Watersheds. Technical Release No. 55. Second Edition. Washington, D.C.

U.S. Environmental Protection Agency, Managing Wet  Weather with Green Infrastructure,
www. epa. gov/greeninfrastructure.

Vingarzan and Taylor. 2003. Trend Analysis of Ground Level Ozone in the Greater Vancouver/
Fraser Valley Area of British Columbia, Environment Canada - Aquatic and Atmospheric
Sciences Division.

Wisconsin DNR. 2008. Impact of Redevelopment on TSS Loads, Runoff Management, available
at http://www.dnr.state.wi.us/runoff/pdf/rules/nrl5 I/Impact of RedevTSSLoads  021308.pdf.
                                          56

-------
Section 438 Technical Guidance
December 2009
APPENDIX A: Runoff Methodology Parameter Assumptions

Runoff from each land cover was estimated by the following equation:

       Runoff = Rainfall - Depression Storage - Infiltration Loss               (1)

Depression Storage
Reference depression storage (inches)
Reference
1
2
3
Impervious
0.05-0.1
0.01 -0.11
0.1
Pervious
0.1 -0.3
0.02-0.6
0.2
1. ASCE, (1992). Design & Construction of Urban Stormwater Management Systems. New York, NY.
2. Marsaleck, J., Jimenez-Cisreros, B., Karamouz, M., Malmquist, P-R., Goldenfum, J., and Chocat, B.
  (2007). Urban Water Cycle Processes and Interactions. Urban Water Series, UNESCO-IMP, Tyler &
  Francis.
3. Walesh, S. G. (1989).t/r/>aĞ Surface Water Management. John Wiley & Sons, Inc.

Based on the above reference data, depression storage (or initial abstraction, the rainfall required
for the initiation of runoff) to the direct determination method was assumed as follows:
   •  Rooftop: 0.1  inches
   •  Pavement: 0.1 inches
   •  Pervious area: 0.2 inches

Infiltration
Infiltration loss occurs only in pervious areas. In this analysis, infiltration was estimated by
Horton's equation:
       t11   ymin ~"~ (/max yminj
        (2)
       where, Ft = infiltration rate at time t (in/hr),
      fmin = minimum or saturated infiltration rate (in/hr),
      /nax = maximum or initial infiltration rate (in/hr),
       k = infiltration rate decay factor (/hr), and
       t = time (hr) measured from time runoff first discharged into infiltration area

Reference infiltration parameters
Maximum infiltration rate (in.hr), fmax
Infiltration
(in/hr)
Sandy
Loam
Clay
Partially dried out with
No vegetation
2.5
1.5
0.5
Dense vegetation
5
3
1
Dry soils with
No vegetation
5
3
1
Dense vegetation
10
6
2
Reference: Huber, W. C. and Dickinson, R. (1988). Storm Water Management Model User's Manual,
Version 4. EPA/600/3-88/00la (NTIS PB88-236641/AS), U.S. Environmental Protection Agency,
Athens, GA.
                                           57

-------
Section 438 Technical Guidance
December 2009
Minimum infiltration rate (in/hr),
Hydrologic
Soil Group
A
B
C
D
Infiltration (in/hr)
0.45-0.30
0.30-0.15
0.15-0.05
0.05-0
A: well drained sandy; D: poorly drained clay
Reference: Huber, W. C. and Dickinson, R. (1988). Storm Water Management Model User's Manual,
Version 4. EPA/600/3-88/00la (NTIS PB88-236641/AS), U.S. Environmental Protection Agency,
Athens, GA.

Decay coefficient, k
Soils
Sandy
$
Clay
k (sec1)
0.00056
0.00083
0.00115
0.00139
k (hr1)
2
3
4
5
Reference: Huber, W. C. and Dickinson, R. (1988). Storm Water Management Model User's Manual,
Version 4. EPA/600/3-88/00la (NTIS PB88-236641/AS), U.S. Environmental Protection Agency,
Athens, GA.

Based on the above reference data, infiltration parameters to the direct determination method
were assumed as follows:
    •   Hydrologic Soil Group B
       •  Maximum infiltration rate: 5 in/hr
       •  Minimum infiltration rate: 0.3 in/hr
       •  Decay factor: 2 /hr
    •   Hydrologic Soil Group C
       •  Maximum infiltration rate: 3 in/hr
       •  Minimum infiltration rate: 0.1 in/hr
       •  Decay factor: 3.5 /hr
    •   Hydrologic Soil Group D
       •  Maximum infiltration rate: 1 in/hr
       •  Minimum infiltration rate: 0.02 in/hr
       •  Decay factor: 5 /hr

Infiltration loss for the 24-hr rainfall duration was estimated by the following equations with
assumptions of a half hour A^:
                             th
       Infiltration Loss at the n  time-step = (f-M)= {(f^ + /J/2)
       Integrated Infiltration Loss for 24 hours =
        (3)
        (4)
                                            58

-------
Section 438 Technical Guidance
December 2009
Integrating infiltration loss during 24 hours with a half hour At
time-
step
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
t(hr)
0
0.5
1
1.5
2
2.5
3
3.5
4
4.5
5
5.5
6
6.5
7
7.5
8
8.5
9
9.5
10
10.5
11
11.5
12
12.5
13
13.5
14
14.5
15
15.5
16
16.5
17
17.5
18
18.5
19
19.5
20
20.5
21
21.5
22
Infiltration rate (in/hr) a
SoilB
5
2.03
0.94
0.53
0.39
0.33
0.31
0.30
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
0.3
SoilC
3
0.60
0.19
0.12
0.10
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.1
SoilD
1
0.100
0.027
0.021
0.02
0.02
0.02
0.02
0.02
0.02
0.02
0.02
0.02
0.02
0.02
0.02
0.02
0.02
0.02
0.02
0.02
0.02
0.02
0.02
0.02
0.02
0.02
0.02
0.02
0.02
0.02
0.02
0.02
0.02
0.02
0.02
0.02
0.02
0.02
0.02
0.02
0.02
0.02
0.02
0.02
Infiltration volume (inches) b
SoilB
0
1.757
0.741
0.368
0.230
0.179
0.161
0.154
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
0.15
SoilC
0
0.901
0.198
0.076
0.054
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
SoilD
0
0.275
0.032
0.012
0.01
0.01
0.01
0.01
0.01
0.01
0.01
0.01
0.01
0.01
0.01
0.01
0.01
0.01
0.01
0.01
0.01
0.01
0.01
0.01
0.01
0.01
0.01
0.01
0.01
0.01
0.01
0.01
0.01
0.01
0.01
0.01
0.01
0.01
0.01
0.01
0.01
0.01
0.01
0.01
0.01
                                           59

-------
Section 438 Technical Guidance
December 2009
45
46
47
48
22.5
23
23.5
24
0.3
0.3
0.3
0.3
0.1
0.1
0.1
0.1
0.02
0.02
0.02
0.02
Sum: Infiltration loss during 24 hours c
0.15
0.15
0.15
0.15
9.743
0.05
0.05
0.05
0.05
3.430
0.01
0.01
0.01
0.01
0.769
a Calculated infiltration rate at each time by Equation (2)
b Calculated infiltration volume from the previous time to the current time by Equation (3)
0 Integrated infiltration volume for 24 hours with a half hour M by Equation (4)

Based on the above calculation, 24-hr infiltration losses for pervious areas and bioretention areas
were modeled as follows:
    •   Soil Group B: 9.743 inches
    •   Soil Group C: 4.430 inches
    •   Soil Group D: 0.769 inches

Infiltrations of underlying soils at paver blocks were modeled conservatively by applying the
minimum infiltration rate for each soil type (Infiltration loss =fmm ' 24) because the soils under
the paver blocks may require or be subjected to some compaction for engineering stability. The
estimated infiltration losses for each soil are presented  below:
    •   Soil Group B: (0.3 in/hr) • (24 hrs) = 7.2 inches
    •   Soil Group C: (0.1 in/hr) • (24 hrs) = 2.4 inches
    •   Soil Group D: (0.02 in/hr) • (24 hrs) = 0.48 inches

Design Storage of Management Practices

Bioretention
Reference
1
2
3
4
5
6
Ponding
(inches)1
up to 12
6- 12
6-12

up to 6
6-18
Mulch
(inches)
2-4
(optional)
2-3

2-3

as
needed
Soil
media (ft)
1-1.5
2.5-4
2-4
1.5-4
1.5-2
2-4
Soil Media
Porosity
about 40%
about 40%


30 - 40%

Underdrain
bioretention systems utilize infiltration
rather than an underdrain
recommended, especially if initial
testing infiltration rate < 0.52 in/hr

if necessary
Optional
if necessary
1. State of New Jersey. (2004). New Jersey Stormwater Best Management Practices Manual
  www.nj.gov/dep/stormwater/tier A/pdf/NJ SWBMP 9.1 print.pdf.
2. Maryland Department of the Environment (MDE), (2000). 2000 Maryland Stormwater Design Manual,
  Volumes I & II, prepared by the Center for Watershed Protection and the Maryland Department of the
  Environment, Water Management Administration, Baltimore, MD.
  www.mde.state.md.us/Programs/WaterPrograms/SedimentandStormwater/stormwater design/index.asp.
  Ponding is a measure of retention capacity
                                            60

-------
Section 438 Technical Guidance
December 2009
3. Clar, M. L. and R. Green, (1993). Design Manual for Use ofBioretention in Storm Water Management,
  prepared for the Department of Environmental Resources, Watershed Protection Branch, Prince
  George's County, MD, prepared by Engineering Technologies Associates, Inc. Ellicott City, MD, and
  Biohabitats, Inc., Towson, MD.
4. U.S. Environmental Protection Agency. (1999). Storm Water Technology Fact Sheet: Bioretention.
  EPA 832-F-99-012. Office of Water. US Environmental Protection Agency. Washington, D.C.
  www. epa. gov/owm/mtb/biortn .pdf.
5. Prince George's County. Bioretention Design Specifications and Criteria. Prince George's County,
  Maryland.
  www.co.pg.md.us/Government/AgencyIndex/DER/ESG/Bioretention/pdf/bioretention design manual
  .pdf.
6. City of Indianapolis. (2008). Indianapolis Stormwater Design Manual.
  www.sustainindy.org/assets/uploads/4_05_Bioretention.pdf

Paver Blocks
Reference
1
2
3
Media (inches)
12 or more
9 or more
12-36
Void Space
40%
40%
40%
1. Univ. of California at Davis. (2008). Low Impact Development Techniques: Pervious Pavement.
  http://extension.ucdavis.edu/unit/center for water and  land use/pervious_pavement.asp.
2. AMEC Earth and Environmental, Center for Watershed Protection, Debo and Associates, Jordan Jones
  and Goulding, and Atlanta Regional Commission. (2001). Georgia Stormwater Management Manual
  Volume 2: Technical Handbook www.georgiastormwater.com/.
3. Subsurface Infiltration Bed. www.tredyffrin.org/pdf/publicworks/CH2 - BMP4 Infiltration Bed.pdf

Green Roofs
Reference
1
2
3
Media (inches)
3-4
1 -6
2-6
1. Charlie Miller. (2008). Extensive Green Roofs. Whole Building Design Guide (WBDG).
  www.wbdg.org/resources/greenroofs.php.
2. Great Lakes WATER Institute. Green Roof Project: Green Roof Installation.
  www.glwi.uwm.edu/research/genomics/ecoli/greenroof/roofmstall.php.
3. Paladino & Company. (2004). Green Roof Feasibility Review. King County Office Project.
  http://your.kingcounty.gov/solidwaste/greenbuilding/documents/KCGreenRoofStudy Final.pdf

Based on the above reference data, design storages to the direct determination method were
assumed as follows:
    •  Bioretention: up to 10 inches (depending on practice used, site conditions, etc.)
    •  Green roof: 1 inch (2.5  inches deep media with 40% void space)
    •  Porous pavement: 4 inches (10 inches deep media with 40% void space)

Factors that influence total storage available include, ponding depth, available media void space,
and supplemental storage if the system is designed with gravel or open pipes underneath the
media.
                                             61

-------