-------
                                                       TABLE  3-7  (continued)



tim:
12 i 3ll

12:45
1:00

1 : l>
IrHO


1:45


2:00
U) :
,1, 7:15
Ul
2:30
2:45
2:50
Mntia.
1. 50
•>. Vi
3. Th
Produc- »agbou«e
lon £?.rtf- in e ix
rate, Rnt?[ RAP, AC, tf*mp. | temp..
tph tfiti Iph tph *F *F
319 1V» 15S 9.5 }V> 295

112 151 152 9.2 34» 295
309 145 155 8.5 350 295

310 ISO 152 8.3 J45 295
1U HO 154 9.1 142 - 290


30(i 150 147 9.1 348 294


3OJ 149 149 9.1 340 285

115 152 154 9.3 34? 2S4

305 14? 155 9.1 J45 292
101 14S 150 ft. 9 J48 2««
101 150 142 9.1 145 2«0

percent RAP mix.
sible emissions reading tak*;n after tft;3n.
Riirner Kel«- Wind
HP vmp, tiwt
tfng, aP, ~ 	 ™™~* hufflid™ BarOfliettfr» Speed,
? in. w.c. Wot Dry ity in, Hg oiph Dir, CoatiaeDti
78 4.7 40 49 43 30.52 25 S Scattered clouds. 2nd
outlet teit began 12:11.
71 4.7
70 4.7 . Complete 2nd inlet test at
1:02,
74 4.7
72 it.l 40 49 41 30.50 25-30 S Cl<-«r skies. Asphalt cew-u
.sdiRple taken at 1:30. &£f it\
Ird inlet test at 1:14.
72 4.9 Aggregate tagiple tnkert at
1:55, KAP sample taken at
!:5H.
71 . 5.1

72 4.7 3r<) inlet test completed j:
2:29.
79 5,0 40 49 43 10.48 25 S Scattered cluuds.
79 4.«
79 5.0 Complete 2nd out If t tent.



Two d£$rt»$aE.e -ind two RAP »ni«|i>luA tak^n on rhis (Jat«.  A?xft-g.it^ mninr.irr content  - ft»2 percent and  1.7 pfrci-nt,   RAF moifiLut^ content • 2.0
and 4.3 p#rc
-------
(see Section 3.1,1).  On September 27, the production rate was lowered to
about 270 tons/h due to problems with the loader that was used to fill the
feed bins.  Assuming 310 tons/h as the maximum production capacity of the
plant, then 270 tons/h is 87 percent of capacity.

     The baghouse inlet temperature was measured by a thermocouple in the duct
between the drum and the baghouse.  The mix temperature was measured by a
thermocouple at the lower exit end of the drum.  It should be noted that the
mix temperature for mixes containing RAP is approximately 20° or 30°P lower
than that for conventional mixes.  Plant personnel reported that a lower mix
temperature is usually maintained for RAF mixes to minimize smoking.  It
should also be noted that while the baghouse inlet temperature is generally
lower than the mix temperature when conventional mixes are produced, the
reverse is true when RAP mixes are produced.  Plant personnel reported that a
thermocouple on the drum typically indicated a mid-drum temperature of 600* to
700°F when RAP mixes were produced.  However, this thermocouple was inoperable
during the test period.

     The burner was operated at or close to 100 percent of capacity during
most of the test period,  A fuel  burning rate of  7.75 gai/min of Ko. 5 fuel
oil was reported by plant personnel while the burner was at 100 percent of
capacity.  This fuel rate was read off a flow meter at the burner.  Due to the
inaccessability of  this flow meter and for safety reasons, only the percent of
burner capacity was recorded during testing'.

     The pressure drop across the baghouse was recorded from a water manometer
mounted on the baghouse.  This pressure drop varied from 4.0 to 5.8 in. w.c.
The  low pressure drops were observed during periods of low production or while
RAP mixes were being produced.  These periods presumably corresponded to
periods of lower particulate loading  on  the filter.

     Aggregate sieve/screen analyses  and other data on the product mixes
produced  on September  24, 25,^26, 27.  and 28 are  given in Table 3-8.  It
should be noted that penetration  grade 85-100 asphalt cement was reportedly
used  with conventional mix, and penetration grade  120-150 asphalt cement was
reportedly used with EAP mix.  Samples of both asphalt cements were taken to
determine their viscosity at 14QaF  and smoke points.  Conventional mixes were
produced on the first  4 days of testing  and were  used on  the roadway surface.
A  50  percent RAP mix was produced on  the last day  of  testing and was used on
the  shoulder surface.  Tuc aieVe/screer.  analysis  indicates that the RAP si*
contains  less material that is greater than 3/8  in. or that is fine enough to
pass  a No. 200 sieve than does the  conventional mix.  Plant personnel reported
that  less of the very  fine virgin aggregate is used in RA? nixes than in
convene ions1 mixes,

      The  stack from the baghouse  was  continuously observed during the
testing*  Although  a steam plume  developed when  the ambient temperature was
below about 50°F»  it had no affect  on visible emission readings.

      A large amount of dust was emitted  from the  dust return system under the
baghouse.  This was caused by an  overloading of  this dust return system and
leaks in  the dust  return auger and  pipe.  Additional airborne particulate
                                    3-14


-------
matter was also observed blowing off the virgin aggregate  storage piles and
neighboring fields.  These were taken into consideration while  the visible
emissions were being observed.

3.3  TESTING INFORMATION

     The sampling crew  from GCA set up equipment  arid  prepared  for the  test on
Saturday and Sunday, September 22 and 23.  Due to a  last minute schedule
change by Western, which MBI was not informed of,  the plant  produced RAP mix
on part of Friday and all of Saturday and Sunday,  September  21,  22, and 23,
This drastically reduced the available SAP material  before testing could begin
on Monday, September 23.  Plant personnel reported that their  contract with
the State required that they use all RAP material before conventional  mix
could be substituted for RAF mix.  Although Ton Wagoner, Plant Manager,
requested a waiver of this requirement through Pat Pattison, Vice President of
Western, the State of Nebraska would not grant a  waiver.   Because of the
diminished RAP supply,  one Method 5E test at  the  outlet of the baghouse and
all Polynuclear Aromatic Hydrocarbon (PAH) tests  were cancelled.

     One Method 5E test at Che baghouse  inlet 2nd one at  the baghcusc  outlet
were performed while the plant was producing  conventional  mix  on Monday,
September 24.  Weather  prevented additional  testing  on this  date.

     On Tuesday, September 25, one Method 5E  test was run  at the outlet, and
two Method 51  tests were run at the  iolet.   Both  inlet tests were  invalid,
however, due to a  torn  filter on the first run and sanpling  train  leaks on the
second run.  Only conventional aix was produced, on this date.

     On Wednesday morning, September 26,  one Method  5E test at the  baghouse
 inlet  and one  at  the baghouse outlet were  performed  while  the plant  was
producing conventional  mix.  The production  rate  was lowered in the  afternoon
 to  help control overloading of  the dust  return  vane  feeder system  and  the
resulting dumping  of dust under the  baghouse.  Due to this lower production
rate  and projected short plant  operating time,  no tests were performed on
Wednesday afternoon.

      On Thursday,  September  27, one  Method 5E test at the  baghouse  inlet  and
one at the outlet  were  completed.  Only  conventional mix was produced  on  this
date.  As discussed  in  the  process  monitoring section of this report,  the
nrnrfiirtlft nn raf(» on  this Hs»f.«  wj»s  1 nuetr f.h&n  Ch«r:  riurrnej previous testing.  The
 test  was  stopped  during periods when the production rate dropped below
80  percent of  the  310  tons/h  capacity  observed  on September 23, 24,  and  25.
The plant was  also down during  part  of  this  day due to a loss of air
 prassurs.  The loss  of  air pressure  was  caused  by a stuck valve in tha pulse
 cleaning  mechanism in  the  baghouse.   Compressed  air is used throughout the
 plant to  control  various gates  and  valves.

      On Friday,  September  28,  two  Method 5£  tests were run.at the  baghouse
 outlet, and  three  Method  5E  tests  were run at the baghouse inlet while
 50  percent RAP mix was  produced.   Due  to inadequate RAP material,  additional
 testing was  not  possible.
                                    3-16

-------
     The production rate on this date was lowered by about 7 percent at  about
10:30 a.m. in order to balance plant production with demand by the paving crew
and to slow depletion of the RAP stockpile and thus allow collection of  a
maximum amount of test data without jeopardizing the quality of the data.
                                3-17

-------
                                  SECTION 4.0

                               SAMPLING LOCATIONS
     A diagram of Western Engineering Company's asphalt cement process is
presented in Figure 4-1.  The approximate location and the parameters measured
at each sampling location is also included in this figure.  This section
contains a description of the sampling locations used for this emission test
program.

4.1  BAGHOUSE INLET SAMPLING LOCATION

     Uncontrolled emissions were measured in the duct work between the
knockout chamber and the baghouse.  The flue gas exits the knockout chamber
through a 54" diameter duct.  This duct creates a 180" arc between knockout
and baghouse as shown in Figure 4-2.  A preliminary velocity profile showed
minimal cyclonic flow.  However, stratification of particulate against the
outside wall of the duct was possible.  Sampling for particulate, flow rate,
moisture, TOC and C02~C>2 was performed at the baghouse end of the duct
before it diverged into the baghouse.  This location was the only possible
sampling location.  It was 6" upstream and 6" downstream from closest flow
disturbances requiring 24 sampling point as per EPA Method I.  Figure 4-3
depicts sampling points for this duct.

4.2  BAGHOUSS OUTLET SAMPLING LOCATION

     Controlled emission samples were collected at the outlet stack.  Flue gas
was drawn through the baghouse by an induced draft fan and exited the fan
through a flow control damper located just downstream as depicted by
Figure 4-4.  The gas then traveled vertically up a 12' rectangular stack.  The
sampling ports were located 8 ft downstream of the flow control damper and
4 ft upstream of the stack exit.  Figure 4-5 shows the seven, 3-inch sampling
ports located in the long side o£ a 39.5 by 52 inch rectangular stack.  These
ports were used for particulate, TOC, orsat, gas flow rate and moisture
measurements.

4.3  VISIBLE EMISSION OBSERVATIONS

     Visible emission readings were conducted, at the outlet stack during the
sampling runs.  However, background interference limited the number of runs
that have concurrent readings.  Approximately 3 hours of reading were
                                    4-1

-------
   FLOW RATE
   VISIBIU EMISSIONS       FLOw RATE
   PANICULATE,  TOC        PARTICULATE TOC
   02, CO.,, N2,  MOISTURE   o2,  C02,  N2
                           MOISTURE
                                  \
OUTLET
 STACK
       BAGHOUSE
            c
                "—PRESSURE DROP
^ASPHALT
- CEMENT
  STORAGE

                               FLASH PT
                               SMOKE PT
                               VISCOSITY
                                  MOISTURE
                                  SMOKE POINT
                                                                           VIRGIN
                                                                           AGGREGATE
                                                                           BINS
                                                                           MOISTURE
                                                                           FUEL OIL
              •Visible emission observation location
                     Figure  4-1.   Sampling  locations  and parameters.

-------
                                         Sampling Conducted  for:

                                           -  particulate
                                           -  TOC
                                           -  02, C02,  N2
                                           -  Moisture
                                           -  Flow Rate
                           KNOCK  OUT
                            CHAMBER
                                           ROTARY KILN
Figure 4-2.  Baghouse inlet location.

-------
                         •54
AI2
           812-**-
— - — .
\
X
\
\
\
* • * » * •

DlS
*,
Oi *






3 -•*
                       PORT A
                                                     PORT 8
                                                                 DISTANCE
                                                                  IN  Ineht*
 Si.86
 SO. 38
 47.62
 44.44
• 40, SO
•34.77
                                                                   19.22
                                                                   13.50
                                                                    9.SS
                                                                    6.37
                                                                  •  3.61
                                                                  •  !. 13
                  Figure 4-3.  Baghouse inlet  sampling points.
                                   4-4

-------
                                                                              Sampling  Conducted for:
I
Ln
                                                                                  particulate
                                                                                  TOC
                                                                                  02,  C02, N2
                                                                                  Moisture
                                                                                  Flow  Rate
                                                                  BAGHOUSE
                                Figure 4-4.  Baghouse  outlet sampling location.

-------
^ T | 1 1|
• ' • ' • 1 • ! • *|*
! ! i i_ 	 i 	
, T i i i
m ' » m m • • i •
' . ' 1 L -!— .
r ^ ^ i i i
• •!••* • " i a
*'"*.* * l *
1 ' ' - i
III I
jH AfgB.JHigl ^ * g. ^^
• * 1 * | * | • • »
. _, t _i i -L
^ i r
* A 1 * • , • A ' •——
* ! • L •
\~~ ' '" ' \ \ •
• 1 . •.At A^^_
l * 1 | i '
LJ LJ IJ LI LJ LJ II




	 _ 	 „,.,„. 	 _ ^ * T ^ *



, - „ 	 .„, 	 	 9 T 5 *

* -i«»


 42.S"  3aO"  32.3"   26.0"  18.5"   13.0"  6.5"
  A      8    • C      0      E      f  .    G
Figure 4-5.   Baghouse outlet sampling points,
                  4-6

-------
performed during each production mode as weather permitted.  Figure 4-1 shows
the approximate location of the observer in relation to the outlet stack
during the visible emission readings.

4.4  PROCESS SAMPLE COLLECTION AND MONITORING LOCATIONS

     Grab samples of virgin aggregate and recycled asphalt pavement were taken
directly off their respective conveyor belts.  Figure 4-1 depicted the
locations of these belts along with, the sampling locations for asphalt cement
and fuel oil.  The pressure drop across the baghouse was monitored from a
U tube manometer located on the support structure of the baghouse.  This
manometer was intalled by GCA because the original gauge was unreadable.
                                    4-7

-------
                                  SECTION  5.0

                SAMPLING AND ANALYTICAL EQUIPMENT AND PROCEDURES


     GCA utilized several different sampling procedures to meet the goals of
this test program.  These techniques included EPA Methods 1 through 5E,
Method 9 for visible emission and discrete grab sampling of raw materials.
Each procedure is discussed in the following subsections.

5.1  EPA REFERENCE METHODS

5.1.1  Method 1, Traverse Points

     Sample traverse points for particulate sampling were determined in
accordance to 4QCFR6Q.  This was performed using the most recent revision to
the method as defined in the Federal Register of September 30, 1983.

5.1.2  Method 2, Velocityand Volumetric Flowrate

     A Type—S pitot tube and attached thermocouple was used to determine
velocity and volumetric flowrate of the flue gas streams being sampled.  This
assembly was calibrated as required by the method.

5.1.3  Method 3, Fixed Gases.Excess Air and Dry Molecular Weight

     Gas analysis was conducted using a stainless steel sampling probe
attached to the Method 5E probe.  A gas sample was collected by means of a
one way hand pump.  The stainless steel sample line was purged prior to the
collection of the*sample.  An integrated sample was collected into a Tedlar
bag and analyzed with an Orsat analyzer in accordance with EPA Method 3.
Ambient air checks were performed before each orsat analysis as a QC check.

5.1.4  Method 4, Moisture Determination.

     The moisture determination of the flue gas was performed in conjuncton
with the Modified Method 5E tests.  The increase in volume of the impingers
was used to calculate percent moisture of the gas stream.  In addition to
this, a wet bulb/dry bulb apparatus was used in conjunction with a
psychrometric chart to determine the relative humidity of the flue gas at the
inlet and outlet of the baghouse unit.  The wet bulb/dry bulb apparatus
consisted of two thermocouples attached along side each other.  The front end
of the first thermocouple extended out about 3 inches further than the second
                                    5-1

-------
thermocouple.  A cloth sock was placed tightly over the front 2 inches of the
first thermocouple (wet bulb).  Prior to sampling, the cloth sock was
saturated with water.  The two thermocouples were then inserted into the
center of the duct and the temperature of the wet bulb thermocouple was
monitored.  After the temperature of the wet bulb thermocouple stabilized
(reaches equilibrium), the temperature of the dry thermocouple was measured.

5,1,5  Method 5S, Particulate/TOC Concentrations

     Reference Method 5E was utilized to collect particulate matter and total
organic carbon simultaneously from each of the two flue gas sampling
locations, concurrently*

     The RAC StacksamplrTM Method 5E sampling train features:  a stainless
steel buttonhook nozzle; the required probe with pitot tube and thermocouple
attached (as per Method 5 revision of August 18, 1977) and a heated glass
liner with a thermocouple connection; a 4-inch glass filter holder containing
a Reeve Angel 934 AH glass fiber filter which has a collection efficiency of
greater than 99.99 percent*,  a heated filter hot box with  temperature
controller and thermocouple  unit attached to the back half of the glass filter
holder (250 *10°F), four glass impingers, the first (modified) and second
(plated) both containing 100 ml 0.IN NaOH, the third (modified) empty, and the
fourth (modified) containing preweighed silica gel; a leakless lubricated vane
pump; dry gas meter; and an  orifice meter.  A schematic of the Method 5E train
is shown in Figure 5-1.

     A leak check of the entire sampling  train was conducted prior to and at
the conclusion of each sampling run, and  before and after changing or
disconnecting any components of the train during the run.  Leak checks before
the test run and after changing any constituent were conducted at 15-inch Hg
vacuum to ensure a leak rate of no more than 0.02 cfm.  Leak checks conducted
at the end of a  run, and prior to making  any component changes or
disconnecting them to facilitate recovery, were at or above the highest vacuum
obtained during  the run.  The pitot cube  assembly were also leak checked prior
to and after each sampling run to ensure  validity of the  velocity data.
Cyclonic flow angles were also checked at the inlet to the baghouse prior to
the sampling program.

     All Method  5E sample recoveries were performed in the GCA High Cube
      1.   The  front-half  of  the  sample  train,  comprised of  the nozzle, probe
          and  front-half  of  the  filter  holder  was  rinsed  and brushed three
          times  with  spsctro grade  acetone.  (Water  was not used  as a first
          rinse  as  per  the request  of the EPA  Task Officer.  This was a
          modification  of Method 5E.)   The  sample  was  stored in a precleaned
          500  ml amber  glass container,  sealed and labeled  as -FH.

      2.   The  particulate filter and any particulate adheriTng to  the filter
          holder was  removed and placed in  its original plastic petri dish.
          This dish was sealed and  labeled  as  -PF.
                                      5-2

-------
     3.    The  contents  of  each impinger was  measured  for volume increase,  then
          transferred  to precleaned amber glass sample containers.  The
          itnpingers  were then rinsed with 0, IN NaOtt.   These samples were
          labeled  as -IMP  1  and -IMP 2+3.

     4.    The  impingers, back half filter holder and  connecting glassware  was
          then rinsed  3 times with spectro grade acetone.   This was stored in
          another  500 ml amber glass container and labeled -BH.

     5.    The  silica gel impinger was reweighed for moisture gain.

     6.    After recovery all glassware was flushed three tines and rinsed  with
          distilled, deionized water.  Then  it was baked in a drying  oven  for
          1 hour at  lOO^C,  Following this cleaning procedure, the glassware
          was  reassembled  for the next test.

     7.    Field bias blanks  of the acetone,  DDI water, filter and 0.IN NaOH
          were collected prior to the start  of the flue gas testing program,

     8.    The  liquid level was marked on all containers.

     9.    All  samples  were logged on GCA Chain of Custody Record Form.

     10.   Stored in  cooler for transport.

5.1.6  Method  9, Visible Emissions

     Visible emissions from  the baghouse outlet were  conducted when  the
conditions permitted.   Readings were recorded every 15-seconds during each
test period.  The  plume observer noted the location and distance from the
stack that the observations  were made.  Readings were made by a certified
observer.  The results are presented as 6-minute averages.  The decision  to
observe the stack plume was  made solely by the onsite EPA Task Officer on  a
test-by-test basis.

5.1.7  Process Stream Sampling

     Grab 'samples  were collected from the two conveyor belt streams,  the
asphalt cement tank  and the  fuel oil tank.  Approximately 2-3 gallons of
material from the conveyor belts was collected during each emission  run,
quartered and  the two  opposing quarters taken for a 1 gallon sample.   Two
asphalt cement samples was taken directly from a tank truck.  The fuel oil
sample was obtained  from the storage tank.  The analyses conducted on these
samples consisted  of moisture content in the virgin aggregate and the RAP
samples,  smoke point for the RAP sample, flash point, smoke point and
viscosity on the asphalt cement.  The fuel oil is being held pending  analysis.

     The pressure  drop across the baghouse was monitored by MRI personnel
utilizing a U-tube manometer installed by GCA.  Existing equipment proved
faulty nessecitatiag the installation.
                                    5-3

-------
5.2  ANALYTICAL PROCEDURES

     The test program produced samples  from Method  5E for particulate, matter
and total organic carbon (TOO), moisture content  for  virgin aggregate and
recycled asphalt pavement samples,  viscosity,  flash and smoke points  for the
asphalt cement and smoke point for  the  RAP samples.  A description of each
analytical procedure is outlined  below.

     *    Method 5E - Particulate—Gravimetric analysis conducted as  per EPA
          reference Method  5 and  reference Method 5E.  See Figure 5-1 for a
          breakdown of this train.

     «    Solids Moisture Analysis—During each particulate and TOC run, one
          sample of the virgin aggregate and  recycled asphalt pavement was
          collected for moisture  analysis.  The samples were collected in
          plastic containers  and  taken directly to the onsite mobile
          laboratory for moisture analysis.   In the mobile lab, approximately
          200 grams of the  material was weighed into  a tared beaker and dried
          overnight at 105--C.  The  remaining  sample was placed into 1-gal
          metal cans.  The  sample is  then desiccated  and weighed co within
          0.01 gram.

     *    Fjlash and Fire Points on  Asphalt Cement—An aliquot of the asphalt
          cement  sample analyzed  to determine the Flash and Fire points as
          required by ASTM  Designation D92-78.

     *    Smoke Point  for Recycled  Asphalt  Pavement (RAP)—-A reference or
          standard test procedure for the  smoke point has not been
          established.  The smoke point for RAP was conducted as per
          procedures provided by  the  SPA Task Officer.  Each sample was dried
          in a 140aF oven to  constant weight.  500 grams of sample was placed
          into a  sample bowl.  Heat was then  applied  so that the rate of
          temperature  rise  of the sample  was  25°F to  30°F per minute.  When
          the  temperature of  the  sample reached 250°F, the heat was decreased
          so that  the  rate  of temperature  rise was only 5 to 10°F per minute.
          The  temperature /tt  which  the material starts to smoke was recorded
          as smoke point.

     «    Viscosity—The  asphalt  cement samples were analyzed by E. W. Saybolt
          I**         *T»1. „  „. „.  _ T ™ _  „ ™ _ „ _  _.™.™"1_™.— — J JJ _ _—,m,^-»J-.._._._, * >• •* ^*
          WUU2OCi&(¥ »   JL 44 C  dtiilHL/ (L.^5 Cl  WC L C  rtltGl A ¥ if 55^4 JU i.4 O%» Wf fc. \Jkca, i ** •*• ^ **
          using  a vacuum  viscotneter.
                                       5-4

-------
                                                     ;°ROBE LINER
                                                     TEMPERATURE
                                                     SENSOR
                                                              O.IN NoOH
                                                              IMPINGE RS
                                                                e.
 i
Ui
                                                                     •CONICAL
                                                            TfUR       HEATER
                                                            CONTROLLER
 1.   PROBE
 2.   CYCLONE
 3.   FLASK
 4.   PARTICULATE FILTER
 5.   IMPIKCEKS. STANDARD AND MODIFIED
 6.   THERMOMETER                  |£
 7.   CHECK VALVE
 8.   UMBILICAL CORD
 9.   VACUUM GAUGE
10.   COARSE FLOW ADJUST VAL
11.   FINE FLOW ADJUST VALVE
12.   OILER
13.   VACUUM PUMP
14.   FILTER
15.   DRV CAS METER
16.   ORIFICE TUBE
17.   HASTINGS METER
18.   SOLENOID VALVES
19.   HONOHETER
20.   THERMOCOUPLE
21.   PYROMETER
22.   ICE BATH
23.   O.IN NtOtl
24.   SILICA GEL DBS ICC ANT
25.   HOT BOX
                                       Figure 5-1.   Particulate  and TOC sampling train.

-------
                                  SECTION  6.0

                               QUALITY ASSURANCE


     A Test/QA Plan was prepared on September lBt  1984 for this test program.
Most of the procedures described in the Test/QA Plan were followed.  Any
deviations from these procedures are noted in this section.

6.1  CALIBRATION PROCEDURES

     Calibration of the field sampling equipment was performed prior to, and
at the conclusion of the field sampling effort.  Copies of the calibration
sheets were submitted to the field team leader to take on-site, and for the
project file.  Calibrations were performed as described in the EPA publication
"Quality Assurance Handbook For Air Pollution Measurement Systems, Volume III,
Stationary Source Specific Methods, SPA-60Q/4-77-027B."  Equipment calibrated
included the sample metering system, thermocouples, pitot tubes, and nozzles.

6.2  SAMPLE CHAIN OF CUSTODY

     GCA follows sample custody procedures based on EPA recommended source
sampling procedures.  Appendix E presents custody record sheets.  The
importance of uncontaminated reagents, collection media and sample containers
in collecting valid samples was well recognized by GCA.  The collection media
actually became part of the sample itself.

6.2.1  Field Operations

     Preprinted sample tags were used to ensure the required information is
entered in the field.  Each sample, duplicates and blanks had a completely
filled-in sample tag securely attached.  Samples were then sealed with tape
and the level marked on the container.  All samples were logged in the field
sample log.  Samples were the transported  in coolers or trunks which were in
the custody of GCA field crew members.

6.2.2  Laboratory Operations

     Upon arrival at GCA, the samples and their chain of custody sheets were
submitted to the Sample Bank Manager.  Each sample was logged into a large
bound master log and assigned a GCA Control Number, which was unique to that
sample, identifies it and follows it through all operations.  All samples were
                                    6-1

-------
locked in the GCA Sample Bank until required.  The Sample Bank Manager
initiated a page for each sample in the custody notebook and ensured that each
handling of the sample was documented.  Each analyst working with the sample
provided a record of such actions in the custody book, thereby maintaining the
chain of custody on the original sample.

     In addition, 39 samples were delivered to Pollution Control Science Inc.
in Miamisburg, OH, by two members of the CCA field crew, for IOC analysis.
The samples were all contained in 500 ml amber glass bottles and were received
immersed in ice.  Sample bottle label information was transferred to chain-of-
custody forms and were entered .into the PCS laboratory log and each bottle
assigned a five digit PCS sample number.  The samples were then stored at 4°C
until removed for analysis.

6.3  DATA REDUCTION AND VALIDATION

     Extensive QC measures were used to ensure the generation of reliable data
from sampling and analysis activities.  Proper collection and organization of
accurate information followed by clear and concise reporting of the data was a
primary goal i.u tula pcQje<;C«

6.3.1  Data Seduction

     Standardized forms were used to record  sampling and analysis data.  All
forms were filled in by the technician performing the work, then checked and
initialed by other project participants.  Figure 6-1 shows the data flow
scheme  for this "project.

     Data reduction performed  in the field was limited  to EPA Method 5E
testing.  Check  runs for  sample volume, moisture and associated parameters
were performed  to determine percent isokinetics.  Most  data reduction was
performed using  a Compaq  portable computer*

6.3.2   Data VaIidation

     Data validation is the process of  filtering data and accepting or
rejecting it on  the basis of sound criteria.  Supervisory and QC personnel
used validation  methods and criteria appropriate to the type of data and the
purpose of the measurement.

     The  following criteria were used  to evaluate data:

      *    Use  of  approved  cest procedures.

      «    Steady-state operation of the process being tested.

     •    Use  of  properly operating and calibrated equipment.

      •    Use  of  reagents  that have passed QC checks.
                                   6-2

-------
                                     TEST CONDUCTED
                                  DATA SHEET  COMPLETED
                                           I
                                  DATA CHECKED BY TWO
                                   FIELD  CREW MEMBERS
                                            I
                                    DATA SUBMITTED TO,
                                    FIELD TEAM LEADER
                                                                   ERRORS AND OUTLIERS
                                            I
                               PRELIMINARY DATA REDUCTION
                                  CONDUCTED AND CROSS-
                                  CHECKED IN THE FIELD
                                            I
                                    SAMPLES AND DATA
                                    'RETURNED TO CCA
SAMPLES LOGGED IN LAB
 ANALYSES PERFORMED
 SAMPLES  DELIVERED
   TO CONTRACTOR
RESULTS SUBMITTED TO
LABORATORY PRINCIPAL
    INVESTIGATOR
                            "NOTED IN FIELD LOG BOOK
 SAMPLING AND PROCESS
DATA SUBMITTED TO FIELD
PRINCIPAL INVESTIGATOR
                                DATA CHECKED AND
                                 TRANSFERRED TO
                                 COMPUTER SHEETS
                                                                           I
                                                                COMPUTER SHEETS SUBMITTED
                                                                     AND KEYPUNCHED
                                                                           1
                                                                  RESULTS RECEIVED FROM
                                                                COMPUTER.  INPUT NUMBERS
                                                                      CROSS-CHECKED
     FINAL REPORT.^.
       WRITTEN
                                       DRAFT  REPORT
SUBMITTED TO CLIENT
                                                                  CORRECTIONS MADE AND
                                                                RESUBMITTED TO COMPUTER
                            .FINAL RESULTS  RECEIVED
                           Figure  6-1.   Data  flow  scheme.
                                       6-3

-------
     •    Proper chain of custody maintained.

     •    Collection of the proper amount of particulate on substrates.

     •    Collection of the required blanks.

     All preliminary data and Rough Draft Reports were edited and checked  to
insure that the data presented were accurate and had not been transposed or
misplaced.

6.4  SAMPLING QC PROCEDURES

     The following QC checks were used during the source testing segment of
this project.

     •    Method 2 - Velocity, Plowrate

               Required use of calibrated pitot tubes

               Check ror cyclonic flow

     •    Method 3 - Dry Molecular Weight

               Orsat analysis were conducted in accordance to EPA Method 3

               The analyzer was  leveled and purged with sample gas prior to
               each analysis

               Ambient air checks were conducted

          -    Analyses were repeated until values agreed within 0.3 percent

     •    Method 5E - Partieulate

               Sampling was conducted in accordance to Method 5E with
               modifications as  instructed  by the EPA Project Officer

               All appropriate method and field-bias blanks were collected



     •    Method 9 - Visible Emissions
                   visible emission  observer was certified wic'uin 6 months oi
                the test  program

                VE's were conducted ia  accordance to Method 9 Guidelines
                                      6-4

-------
6.5  ANALYTICAL QU PROCEDURES

6.5.1  Gravimetric Determinations

     •    All samples were dessicated and weighed to a constant weight.

     t    Some gravimetric analyses were conducted in the field, however all
          applicable QC measures were observed.

     •    The balance used was checked with Class S weights before and after
          each weighing session.

     •    Temperature and relative humidity was recorded during each weighing
          session.

6.5.2  TotalOrganic Carbon

     TOG sample were analyzed by PCS Inc.  Included were 5 EPA audit samples.
The results of these analyses are presented in Table 6-1.  In addition,
several samples were also analyzed in replicate to establish 95 percent
confidence intervals.  The results of these analyses are presented in
Table 6-2.

6.5,3  Clean-up Evaluation

     The clean up evaluation results for uncontrolled and controlled method
blank trains are presented in Table 6-3.  Both blank trains were analyzed for
particulate and total organic carbon.  The particulate analysis consisted of
the weight gain from the filter and the front-half acetone rinse of the
sampling train.  For uncontrolled operations the front-half rinse consisted of
the nozzle, the probe, the cyclone and the front half of the filter house.
For controlled operations the front-half rinse consisted of the nozzle, the
probe, the cyclone bypass and the front half of the filter house.

     The total organic carbon analysis for uncontrolled and controlled
operations consisted of a 0.IN sodium hydroxide rinse of the back half of the
sampling train.  This back-half rinse consisted of the three impingers,
back-half filter holder, and connecting glassware for both uncontrolled and
controlled operations.

6.5.4  Ignitability

     An aliquot of p-xylene was analyzed as a quality control sample.  The
reported flash point was 28*C,  The literature value is 27°C,

6.5.5  Smoke Point

     At this time, there is no known quality control sample available to
establish the accuracy of smoke point determinations.
                                     6-5

-------
TABLE 6-1.  RESULTS OF EPA AUDIT SAMPLES PERFORMED BY PCS
               Measured       Reference        Percent
 Sample  ID     TOG  Cog/1)      Cone,  (tng/1)      Error
   EPA-1           95.5             91.5           +4.2

   EPA-2            9.6              6.1           *36.5

   EPA-3            5.4              6.1           -11.5

   EPA-4           96.0             91.5           +4.7

   EPA-5           93.8             91.5           *2.5
                           6-6

-------
TOC A&ALYSIS K
tCS 3*Epl* f
T«»t Rue
I* .tiilc 1 dag;'1 U
feult 2 C^/U
*ir *, j, **; * *S \
.\«J»« it 3 iGg; I/
fiesylt 4 Cog/1)
Ltiwit 5 (og/L)
Result & dag/i)
Result 7 tng/1)
Result S (as/ I)
S»sult 9 Cmg/l)
He4» result i»g/l)
Std. Deviation C«g/ L)
4W)S>i4
5-Ciitlst
260
:&o
150
250
iao
180
209
240
160
222
4CL5
4?06>-67 i €041-70
S-Iniet fe-D-ut'lss
«» »»
113 ;03
200 253
135 ^S
215 219
IfO 212
105 1?S
125 239
104 219
142 230
45, fe 24,6
              ,

-------
         TABLE i-3.   SUMMASf OF CLEANUP
  Particulate
 total organic     "        Train, 1          Train 2
        blanks           uncontrolled      controlled
Front half

  Filter tag)                0.21   ^          0.14

        Csg)    -"             0.73             0.81
Back half

local organic eairlwaCfflg)    10,35            IZ.2.4
                            6-8

-------
6.6  SITE SPECIFIC QUALITY CONTROL

     A new rinse procedure was  developed for this test program.  It was found
in a previous test program that residual acetone remained in the impingers
after rinsing, coatatninating  the total  organic carbon samples.  To alleviate
this problem, additional  steps  were  taken in the sample recovery procedure.
The new rinse procedure  is presented in Section 5.0 of this report.  The new
procedure was checked by  setting up  a sampling train, recovering it, then
analyzing the impinger contents for  TOG.  This was done 3 times.  A blank of
the NaOH impinger solution was  also  checked.  The results qualifying the new
rinse procedure can be found  in Table 6-4.  Lab analysis sheets can be found
in Appendix G.

6.6.1  Test Program Audit

     A systems audit was  conducted on the western engineering test program to
check if appropriate QC measures were followed by the GCA field crew and staff
members.  The audit concentrated on  adherence to the field test/QA plan
prepared for  the program. A  cdpy of this audit report can be found in
Appendix G.

6.7  DISCUSSION OF PROBLEMS WITH EMISSION TESTING

     Several  problems were encountered  during the testing runs.  just below  the requied range of 90 to 110 percent.

     During"Run Nor 2,~ the"f ilter"at _the~ uncontrolled-1'ocation^ripp^d
^tKerefare^vaidinglche_samp.le_for_particulate_measurement.  This sample was
still analyzed and presented  in the  tables.  At the controlled location during
Run No. 2, a  very high vacuum was being drawn by the sample box.  An
investigation of this problem found  that the orifice of a new Andersen,
Greenburg-Smith plated impinger was  too small causing a very high pressure
drop.  LacaJ:ing^thrs^pr.ob.lerozwas-time consuming and a§: a result. t-es-tine .had
to"b'e^:terrainated-because_produc±ion_had:_stapped_f or_;the -> day.  Approximately^
75~perc'ent":o.f—th'ez.sampVingzpolntSL.w.er.e_tes.ted:^^These were the reasons for
scheduling the additional conventional  run (4).

     Other difficulties  encountered  in the test program included:

     •    Filter holder  did not contain wells for thermocouple.

     •,   A  fuse was  blown  in the sampling box during controlled Runs 3 and 6
          controlled.

     •    A malfunction  of  the  sampling pump during uncontrolled Run 4.
                                      6-9

-------
TABLE 6-4.  RESULT OF RINSE PROCEDURES CHECK
Run No.
1
I
2
2
3
3
Probe rinse
NaOH blank
Impinger No.
I
2
1
2
I
2


Concentration mg/1
4.40
2.63
1.53
2.30
2.65
1.52
1.50
1.93
                  •  6-10

-------
     »    A broken U-tube  connector was replaced on Run 6 at the uncontrolled
          location.

     »    During Runs 4 and 5,  testing had to be halted because plant
          production fell  below the required 80 percent of capacity.   Testing
          was restarted when plant production was appropriate.   All of these
          minor difficulties and problems were dealt witli promptly and had no
          effect on sampling results.   The problems encountered are documented
          in the daily sampling log found in Appendix E.

6.8  DEVIATIONS FROM TEST/QA PLAN  •

     Several deviations and alterations from the original test/QA plan were
made.  The first change was in the scope of work.  Since the raw materials
were in limited supply, only 2 recycle runs were recommended.  In addition to
this, no PAH testing was conducted.  The next modification was to the sampling
times at the uncontrolled  location.  Due to extremely high loading, the
sampling time was cut from 72 minutes to 48 minutes.  The test plan also
stated that a wet bulb/dry bulb -apparatus would be used to check moisture
content.  While this was the case, the wet bulb/dry bulb figures were used
only as a cross check to the iopinger volume increase.

     Other deviations made included:

     »    The second impinger in each train was suppose to be a plated
          Greenburg-Smith impinger.  In some cases, the orifice at the tip of
          these impingers  sustained too high of a pressure drop.  The best
          impingers were chosen and used for the remainder of the test program,

     »    Visible emission readings were not taken during all runs because of
          background interference.

     »    In the recovery  of samples,  instead of rinsing 6 times with
          spectrograde acetone, it was done only 3 times.

     *    TOG analysis was not performed by GCA.  It was done by Pollution
          Control Science in Miaioisburg, Ohio.

     •    Cyclonic flow checks were performed only at the inlet location.

     *    No baghouse dust was collected.

     *    No analysis was performed on the fuel'oil sample.


All changes and modifications to the QA/Test Plan were accepted and approved
by the onsite £PA Task Officer.
                                    6-11

-------
   (Jimi'.l SMU.-S
   Crivtr
-------


United States      Office of Air Quality
Environmental Protection  Planning and Standards
Agency         Research Triangle Park NC 27711
Air          "    ~_    	 ~" _
Asphalt Concrete
Industry

Emission Test Report
Western Engineering
Company
Lincoln,  Nebraska

Volume  1
EMS Report 83-ASP-5
April 1985




-------
                                           SCA-TR-fiS-H-C
              f£««l  Report

               Volume  1
             Prepared lot
           Mr.  Cljtd't i.  tile?
£»i»*ion*              Iraoch Cffic« ftf
  Air Qu< 2 icy ?S*ft«iing  and
            tfinagl* Parte, MC  2?? II
      EPA Contrtcc Mo* 6S-02-3S51
     tfork A««ignmenc  No».  05 and 0?
              froject Ho,  S3/05
        SMB  Project No.  83-ASf-S
                       by

               J,  ?r»
            GCA
                       3IVISICK
               April 19*5

-------
                                   DISCLAIMER
     This Final Report has been reviewed by the Emission Standards and
Engineering Division, Office of Air Quality Planning and Standards, Office of
Air, Noise and Radiation, Environmental Protection Agency, and approved for
publication.  Mention of company or product names does not constitute
endorsement by EPA,  Copies are available free of charge to Federal employees,
current contractors and grantees, and nonprofit organizations—as supplies
permit—from the Library Service Office, MD-35, Environmental Protection
Agency, Research Triangle Park, NC 27711.

     Order;  EHB Report-83-AS!>-*5, Volume I.
                                       11

-------
                                    CONTENTS
Figures	     iv
Tables.	      v

   1.0   Introduction 	  ......  	    1-1
         1.1   Objectives ..................  	    l-l
         1.2   Brief Process Description  	  .........    1-2
         1.3   Emissions Measurement Program  .»  	    1-2
         1.4   Description of Report Sections  .............    1-4
   2,0   Summary and Discussion "of Results  ,	,	    2-1
         2.1   Emission Program Results ...  	  ........    2-1
   3.0   Process Description and Operation	    3-1
         3.1   Process Description	    3-1
         3.2   Process Monitoring ..............  	    3-3
         3.3   Testing Information  .....  	  .    3-16
   4.0   Sampling Locations 	  ........  	    4-1
         4.1   Baghouse Inlet Sampling Location ............    4-1
         4.2   Baghouse Outlet Sampling Location  ......  	    4-1
         4.3   Visible Emission Observations  .............    4-1
         4.4   Process Sample Collection and Monitoring  Locations  .  .  .    4-7
   5.0   Sampling and Analytical Equipment and Procedures  .......    5-1
         5.1   EPA Reference Methods.  . 	  .......    5-1
         5.2   Analytical Procedures.	    5-4
   6.0   Quality Assurance. ...........  	    6-1
         6.1   Calibration Procedures  	  .....  	    6-1
         6.2   Sample Chain of Custody  .... 	  .....    6-2
         6.3   Data Reduction and Validation  ......  	    6-2
         6.4   Sampling QC Procedures  ........  	    6-4
         6.5   Analytical QC Procedures	    6-5
         6.6   Site Specific Quality Control.	"  6-9
         6.7   Discussion of Problems  with Emission Testing  	    6-9
         6.8   Deviations front the Test/QA Plan	    6-11
                                       111

-------
                                    FIGURES






Number




 1-1     Asphalt concrete process 	 ..... 	  ....    1-3




 2-1     Six-minute average opacity during conventional operation ...    2-24




 2-2     Graphic representation of visual emission observations  ....    2-25




 3-1     Schematic of aspKalt concrete drum-mix plant .........    3-4




 4-1     Sampling locations and parameters	    4-2




 4-2     Baghouse inlet location	    4-3




 4-3     Baghouse inlet sampling points	  .    4-4




 4-4     Baghouae outlet sampling location  ..............    4-5




 4-5     Baghouse outlet sampling points   	 .....    4-6




 5-1     Participate and TOC sampling train ..............    5-5




 6-1     Data flow scheme	........,..»..'..    6-3
                                       IV

-------
PAGE NUMBERS TO BE CHECKED^
                                     TABLES
Number                                           .                        Page

 2-1     Summary of Particulate and Total Organic Carbon Emission
           During Conventional Operation (English Units)  	  •   2-2

 2-2     Summary of Particulate and Total Organic Carbon Emission
           During Conventional Operation (Metric Units)  	   2-3

 2-3     Summary of Uncontrolled"Particulate and Total Organic
           Carbon Emission During Conventional Operation  .......   2-4

 2-4     Summary of Controlled Particulate and Total Organic Carbon
           Emission During Conventional Operation ,.......,.,   2-5

 2-5     Summary of Particulate and Total Organic Carbon Emission
           During Recycle Operation (English Units)  . 	 ...   2-7

 2-6     Summary of Particulate and Total Organic "Carbon Emission
           During Recycle Operation (Metric Units)  ..........   2-8

 2-7     Summary of Uncontrolled Particulate and Total Organic
           Carbon Emission During Recycle Operation ... 	 ..   2-9

 2-8     Summary of Controlled Particulate and Total Organic Carbon
           Emission During Recycle Operation  ...... 	   2-10

 2-9     Breakdown of Sampling Run Weight Gains  	   2-11

 2-10    Summaries of Impinger Back Half Results During Conventional
           Operation Uncontrolled Total Organic Carbon and Impinger
           Acetone Rinse Values ..... 	 ...   2-13

 2-11    Summaries of Impinger Back Half Results During Conventional
           Operation Controlled Total Organic Carbon and Impinger
           Acetone Rinse Values ......... 	 .....   2-14

 2-12    Summaries of Impinger Back Half Results During Recycle
           Operation Uncontrolled Total Organic Carbon and Impinger
           Acetone Rinse Values ,	   2-15

-------
                                     TABLES
Number                                                                   Page
 2-13    Summaries of Irapinger Back Half Results during Recycle
         Operation Controlled Total Organic Carbon and Impinger
2-14

2-15

2-16
2-17
3-1

3-2

3-3
3-4
3-5
3-6
3-7
3-8
6-1
6-2
6-3
6-4
Summary of Visible Emission Observations During

Summary of Visible Emission Observations during Recycle



Technical Data on Asphalt Concrete Plant Western

Technical Data en the Air Pollution Control Device










Result of Rinse Procedure! Check. .............

2-19

2-20,
2-18
2-19

3-2

3-5
3-6
3-7
3-9
3-10
3-12
3-15
6-6
6-7
6-8
6-10

-------
                                  SECTION 1.0

                                  INTRODUCTION


     On March 7,  1974,  New Source Performance Standards (NSPS)  were
promulgated for the asphal: concrete industry.  They established a limit  on
particulate matter of 0.04 grams per dry standard cubic foot and a visible
emission limit of 20 percent opacity.  The standards were reviewed in 1979 and
no revisions were proposed.  Another review was initiated in 1982 with the
purpose of investigating the opacity limit of facilities utilizing recycled
asphalt pavement (RAP).  The National Asphalt Pavement Association (NAPA)
requested this review because of concern from members that emissions could be
higher during RAP production.

     Reportedly,  the utilization of RAP produces a "Blue Haze"  plume due  to
the emission of condensible hydrocarbons.  Emission data from selected,
representative sources would be used in the development and/or  review of  the
NSPS regulations for the asphalt concrete industry.  The Western Engineering
Company's facility was selected as an emission test program site based on the
following rationale:            .               '

     •    The plant was suitable for testing and obtaining useful data;

     •    The plant has been successfully tested for compliance with the  NSPSi

     •    The facility is a typical design of a major vendor; and

     •    Western had a known production schedule producing RAP mixes.

l.l  OBJECTIVES

     The objectives of this test program were to obtain and evaluate data on
particulate emissions, .total organic carbon (TOC) , and visible emissions  from
a facility utilizing recycled asphalt pavement.  The Western Engineering
facility was selected and tested during both RAP and conventional production
modes.  A series of simultaneous Method 5E emission tests were conducted  both
at the  inlet and outlet of the control device, in this case a baghouse.   These
tests were conducted to provide a comparison of particulate, TOC, and visible
emissions during the two types of production.
                                  1-1

-------
1.2  BRIEF PROCESS DESCRIPTION

     Figure 1-1 is a layout of a typical asphalt concrete process.  During
conventional production, virgin aggregate from any of 4 storage bins, is
loaded onto a conveyor.  The quantity of aggregate from each bin is controlled
by a computer located in the control room.  The virgin aggregate is fed to Che
burner end of the drum mixer.  Liquid asphalt is injected into the drum mixer
2/3 of the drum length from the burner end and is mixed with the aggregate
material.  As the asphalt concrete mix falls from the drum it is conveyed to a
storage silo for truck load-out.  The gaseous emissions enter a knockout
chamber that reduces the gas velocity and promotes particle settling.  From
the knockout chamber, the gas is drawn through a baghouse that traps the fine
particulate.  The flue-gas is then exhausted to the atmosphere through a
12 foot high rectangular stack.

     Recycle operation differs from conventional operation in that a
percentage of the virgin aggregate is replaced by recycled asphalt pavement
and a different asphalt cement is used.  The RAP is fed to a collar located at
the center of the drum mixex from a separate bin.  The rest of the RAP process
is the same as the conventional process.

1.3  EMISSIONS MEASUREMENT PROGRAM

     The  test program was conducted at the Western Engineering Company's
mobile CMl asphalt concrete plant.  The mobile facility was located on
Route 34,  12 miles west of Lincoln, Nebraska during the last week of
September 1984.  The test program was designed to quantify uncontrolled
(baghouse inlet) and controlled (baghouse outlet) emissions during
conventional and recycle operations.  GCA personnel were responsible for
sampling  and analyzing  process emissions except for TOC analyses which was
performed by Pollution  Control Science of Miamisburg, Ohio.  Midwest Research
Institute (MRI) was responsible for coordinating the  test program with plant
personnel to insure that process conditions and control equipment were
suitable  for testing,  MRI was also responsible for the monitoring and
recording of necessary  data on process and control equipment.

1.3.1  Part iculate^tass

     Total particulate  loading measurements were performed at the baghouse
in Let and ouci.ec, concurrently.  The  tests were cumim. Leu ,iu ayiiordoilCc »ith
EPA Method 5E.  Four  particulate runs,  for both uncontrolled and controlled
emissions,  were performed during conventional operation.  Three uncontrolled
and  two  controlled  runs were performed during recycle operation.

1,3.2  Total Organic Carbon

     Total organic  carbon  (TOC) samples were concurrently collected  at the
inlet and outlet  to the baghouse.  They were collected during the SPA
Method 5E tests mentioned  above.  Each sample consisted of 'organics  chat were
collected in the  impinger  solutions downstream of  the filter holder.  The
                                  1-2

-------
      AGGREGATE
       FEED BINS
                  BURNER
  RAP
FEED BIN
  RAP
FEED PORT
   VYTY
              BAQHOUSE
               PRODUCT
                FEED
                                     STACK
                    STORAGE
                      SILO
                            TRUCK
                                                                  FAN
                      Figure 1-1. Asphalt concrete process,

-------
itnpinger solutions were made up of 0.1 N NaOH,  In addition Co the impinger
solutions, the acetone rinses of the impingers were dried to a constant weight
and gravintetrieally analyzed.

1.3,3  Gas Stream Analysis

     The concentrations of CC>2 and 03 in the gas stream at the inlet and
outlet locations were determined by collecting an integrated sample in a
Tedlar bag and analyzing the sample with an Orsat analyzer.  The analyses were
in accordance with EPA Reference Method 3.

1.3.4  Polynuclear Aromatic Hydrocarbons

     The test program called for one inlet and one outlet test for Polynuclear
Aromatic  Hydrocarbons (PAH).  It was originally believed, at the tine of the
pre~site survey, that there was sufficient reserves of recycled asphalt
pavement for three Method 5E tests and one Modified Method 5E test for PAH.
However, due to scheduling changes, most of the RAP was utilized before the
test program began.  Therefore, no PAH testing was performed.

1.3.5  Visible Emission Observations

     Visible emission observations for opacity were performed concurrently
with the Method 5E runs.  However, due to background  interference
(i.e. clouds) not all of the runs have concurrent visible emission readings.
Readings representative of both operational nodes are included in the report.

1.3.6  Process SampleCollection and Monitoring

     Discrete grab samples of RAP, virgin aggregate,  asphalt cement and fuel
oil were obtained during this test program.  The virgin aggregate samples were
analyzed for moisture content.  The RAP samples were  analyzed for moisture and
smoke point.  Smoke point, flash point and viscosity  analysis of the asphalt
cement samples were also conducted.  The fuel oil sample  is being held for
future analysis.  Monitoring and recording the pressure drop across the
baghouse, along with all other pertinent process paraneters, was the
responsibility of Midwest Research Institute  (MRI).

1.4  DESCRIPTION OF REPORT SECTIONS

     The  remaining sections  contain  the summary and discussion of results in
Section 2.0, Process Description and Operation in Section 3.0, Sampling
locations  in Section 4.0, Sampling and Analytical Equipment and Procedures in
Section  5.0, and Quality Assurance in Section 6.0.
                                    1-4

-------
                                   SECTION  2.0

                        SUMMARY  AND DISCUSSION  OF  RESULTS
     This section discusses the results of the emission test program conducted
at Western Engineering Company's asphalt concrete plant outside Lincoln,
Nebraska.  Controlled and uncontrolled emissions were tested.  The testing was
conducted during the production of conventional mix and 50 percent recycled
asphalt pavement mix.  Problems encountered during this test program are
discussed in Section 6,0.

2.1  EMISSION PROGRAM RESULTS

     The following subsections contain narrative, tables, graphs and figures
pertaining to the specific tests performed.  Each subsection also contains a
discussion of the data.

2.1.1  Particulajie Mass Emission Results

     A modified version of EPA reference Method 5E was used to collect both
uncontrolled and controlled emissions concurrently during conventional and
recycle production.  The results are discussed in the following sections.
Additional information, field data sheets and lab analysis sheets can be found
in Appendices A and 0.

2,1.1,1  Conventional Operation—
     Summaries of particulate and total organic carbon emissions for both
controlled and uncontrolled emissions during conventional operation are
presented in Table 2-1 (English units) and Table 2-2 (metric units).  Four
controlled and uncontrolled sampling runs were performed.  The test plan
originally called for three concurrent runs.  However, problems with Run No. 2
necessitated an additional conventional run as a precautionary measure.  The
four conventional operation runs are designated as 1» 2, 3 and 4.  The
uncontrolled particulate mass loading were 45.700, 112.660, 86.836 and
53.500 grains per dry standard cubic foot, respectively.  The corresponding
controlled particulate loadings were 0.008, 0.025, 0.028 and 0.022 for I, 2, 3
and 4, respectively.  The average controlled particulate loading was
0.021 gr/dscf which is below the present NSPS standard of 0.04 gr/dscf.  The
collection efficiencies of the baghouse for these runs was 99.98, 99.97, 99.96
and 99.95, respectively.  A breakdown of uncontrolled and controlled
conventional emissions can be found in Tables 2-3 and 2-4.
                                   2-1

-------
                                TABLE  2-1.   5UHHARY  OF PARTICULAR AND TOTAL ORGANIC CARBON EMISSION OURINC CONVENTIONAL OPERATION (EHCLISU UNITS)
Kl

N>
Date
Hun
CBiaaion Type

Production Rate (torn/hour)
Procesa Kix Type
Average Opacity (O
(•can, range)
Pirt'culate and Total Organic
Carbon (TOC) Reaulti

(proL*, cyclone and filtrr)
ng - Mil
gr/dicf
lb/hr
Ib/ton production
Collection Efficiency Percent^
Rack Half Caleb - TOC
(iapinger aolutioni aitd riuieii)
•g - nan
gr/dicf
lb/hr
Ib/ton production
Collection Efficiency Percent
Total Catch Particular - TOC
ng - •»!•
gr/dicf
lb/hr
Ib/tun production
Collection Efficiency Herci-nt
09/14/84
1
09/75/84
2
09/26/04
1
Uncontrolled Controlled Uncontrolled Control led Uncontrolled
St
. ?
110
• Convent iona 1
N/A



160499.84 48.40
45.700 0.008
8U89.17 2.115
26.09S 0.007
99.98


c 115.20
0.020
5.01}
0.162
N/A

160499.84 163.60
45.700 0.028
8089.37 7.15
26.095 0.021
99.92

*
»w
311
Conventional
0.25 (0-1.25)



183171.87*
112.660
22849.019
76.470
99


BO. 52
0.049
10.031
0.012
44

181452.39
112.709
22859.05
76.500
99



121.35
0.025
6.860
0.022
.97


100 . 50
0.021
5.5B9
0.018
.SB

221.fi}
0.046
12.45
0.040
.95

09/27/84
4
Average
Controlled Uncontrolled Controlled Uncontrolled Controlled
[
10E1
Conventional



147755.98
86.816
18457.072
59.920
99,


17.10
0.022
4.634
0.015


147793.08
86.860
18461.71
59.910
99,,



171.61
0.028
7. 486
0.024
96


106.70
0.017
4.661
0.015
0

278.31
0.045
12.14
0.019
94

c n
J . V
267
Convent ion* I
N/A



64957.36
53.500
10831.32
40.580



74.16
0.047
9.459
0.03}



126.71
0.022
5.721
0.021
99.95


101.92
0.017
4.601
0.017

f. t.
299
Conventional
0.25 (0-1.25)



144672.15
75.081
15084.140
50.450



61.91
0.039
8.042
0.027
50.85

85011.52
51.547
108165.12
40.610


22B.65
0.019
10.32
0.038
99.91

144716.08
75.120
15092.18
50.470



117.528
0.021
5.545
0.019
99.96


106.08
0.019
4.971
0.017
18.52

223.61
D.uJ1* '
1U.5/
O.OJS
99. »7
         'Invalid run torn filter.
         bC£F b»ed on Ib/br valuei.
         cCoiitaiain«tfld aaaple.

-------
TABU J-7,   SWUM C* PAfttlCUlATfc AW I«t»t ORGANIC CA*«U«I EHlSSIW OWING CffltrttWIOKIl, Wlfclf JON tHETVlC IWIM)
But*
Horn
CaiMtoit %p*
•.*«.. F,..«,r, 1,«P 
PtoilucitM ft*c« tkf/ft
^£«*i« HI* tygr*
alwraM* f^wifj* III
C*rkioTf*iri*';uTti '
PTMI Half C«teh-P*rfict»l«t*
g^g ff^iKS.!^!
i2&lj«E J i«>fi tffici*fsey t>«««*s»^
lack H»if Cilch ~ fOC
mf - mmmm
?. *e*
c.iiKii«crticiMef r«»f.t
Tal»l C««h p*rtieitl.t* - TOC
•|/4i«»
§/•
Collection efdcieBtr Pcreenl
*lo»*ljd ryn (orn lilmr.
^Cgt fcaatd an jbf'sir vilue«.
09/14/44 Ot«J/S4 Ot/2li/B4 ftt/JJ/14
1 1 1 * 4»sr*t«
bn.-.ont s ,.J (,-!J CoBttotlfd (fntonl ml 1*4 COM r»t ittd thWOOtrot I«t Coot rolled iinccn'it rsl S*d Conlrali»d llr.io.'iir!..'! 1?1 C.i.ij s,-j! Jf.i!
S.-S *.* J.» 5,5 S-4
71.1 t»,4 W.S SI. ft ?}.J
Con»»wia«al Conv^ntieAil C«4«*Mii C«a««r»lJt»«i*l (qnventio-nol
H/A O.ll (0-1. J4> Urt Krt O.JJ tO-t.Jf)

,
«»«„» 41,40 IIJJH.il* l!J,J} l«i»?S5.fi 1JI.4J S4»J},J« 1Z*.IJ r448Ji,lS llJ.M
10*5*4, ]J i»,JQ aj?r}8.04 ST.« »>»&Sl.tS §*.» HJJ«»,J4 JO.J1 !II?Jf.»f 4J.47
10 If .144 0.2S4 »?t.9() C.tM Z»S,.5» 0.143 t3M,2« O.rtJ »00,>«ft 0,«»
u.130 o.wi j«.J2c 9>iw Je,iws §.»ti io,i» o.oii Ji.i«.o o,0e«
«.» »».»r W.M «*.*> ».M

e 114,10 <0.)2 IPO.tO If, If 10&.W 74.lt 181, »1 4],»J 106.01!
45, IS 112,09 it,« iQ.Jl J».W 107. M »,» IV.40 47. /«
P.*J4 %,'im ft.SWt O.SI4 03SJ 1,1*8 Q.SfrO I.Oi) tl,***
O.tKM BfOl* 0.00* O.OOT tt.009 O.Ol* 0.80S O.OU O.SCSB
«/* 44.44 8 50. ij Jl.it

it,Mtf,K4 ISJ.M ttj4ji,j9 tty.K i*w*j.iw ??*,jj fsioi.si tii.ss w4»j».ei ju.ftt
IUD.24 O.SQ !«SO,t^ 1,17 212t.ll 1 . 5 J U*b.4l I.S* rtOi.SJ l,*l
13. 11 0.011 U.7* 0,11 30, Jl 0.02 W.H ft.lklf li.JS- 8,01?
».»J »»,fi M.M *f,ft Ht.SI



-------
                      TABLE 2-3.  SUHKART OF UNCONTROLLED  PART1CULATE  AND TOTAL ORGANIC CARBOH EMISSION DUSINC CONVENTIONAL OPERATION
Run Number 1
Date . 9/24/84
Volute Caa Sanpled (rtitf) 56.116
Stack C«« Flow »•!.' (dscfn) 20,638
Stack Tenparaturr, *K 779 '
Percent Hoiiture by Volume 22.3
Percent loakinetic 89.1
Production Bate (ti.n/hr) 310
Pruceai ffix Type Conventional
Petticulate and Tot.il Organic
Carbon (TOC> geiulla
Front Half Catch-Part iculate
(probe, cyclone and filter)
fS 160499.84
gr/
Convent ianal


147755.98
86.84
18157. 0>2
59.92

37.10
0.012
4.634
0.015
4
9/27/84
23.924
23.630
271
18.6
99.8
267
Convent iooal


84957.36
10835.866
40.58

74.16
0.047
9.459
0.035
Average

32.66
23,182
274
20.4
99.8
299
Conventional


144672.15
75.08
1SOB4.40
50.4,5

63.93
0.039
8.042
0.027
         run torn filter.



^Contaminated ia*pl.:.

-------
                       TABLE  2-4.   SUMMARY  OP  CONTROLLED  ("ARTICULATE AN& TOTAL ORGANIC CARBON EMISSION DURING CONVENTIONAL OPERATION
Ryn Nuober
Date
Volume CM* Sanpled (dscf)
Stack Oia Flow Rite (decfn.)
Stack Ttaptricure, *F
Percent Hoiature by Volume
Percent loikinetic
Production Rate (ton/br)
Procest Mix Tyf»«
Particulars and Total Organic
Carbon (TOC) Reiults
fj Front Half Catch-Part icu lite
U»
Bg
gr/dscf
Ib/hr
Ib/ton preduccioii
Back Hi If Catch - TOC
Kg ~ wtaB
gr/dscf
Ib/hr
Ib/ton production
1
9/2*/84
W.500
29,597
256
19.0
98.7
310
Convent ioital




48.40
0.006
2,115
0,00?

115.20
0.020
S.035
0.162
2*
9/25/84
74,098
11,448
25J
17.7
101,1
111
Convent ionai




123.35
0.025
6.860
0,022

100.50
0.021
5. 589
0,018
3
9/26/84
93.270
31,527
248
17.9
101,3
3oa
Conventional




HI. 63
0.028
7.486
0.024

106.70
O.OU
4.661
0.015
4
f/27/84
90.568
11,032
253
16.9
97.9
267
Conventional




126.73
0.022
5.721
0.021

101.92
0.017
4.601
0.0172
Average

87.109
30,901
2S2
17.9
99.8
299
Conventional




117,53
0.021
5.540
0.019

106. 08
0.019
4.971
0.017
*Invilid run torn filter.

-------
2.L.I.2  Recycle Operation-
     Table 2-5 v  jlish units)  and Table 2-6 (metric units) present the
results of uncontrolled and controlled emission testing during recycle
operation.  The three uncontrolled and two controlled recycle operation test
runs are designated 5, 6 aid 7  (uncontrolled only).  Uncontrolled particulate
mass loadings for the respective runs were 7.085, 10.939 and 8.655 gr/dscf the
corresponding controlled particulate loadings were 0,008 gr/dscf for 5 and
0,006 gr/dscf for 6.  The average controlled emissions during recycle
operation was 0.007/dscf which is well below the NSPS limit of 0.04 gr/dscf.
The collection efficiencies for 5 and 6 were both above 99,9 percent.
Tables 2-7 and 2-8 provide additional information on uncontrolled and
controlled recycle emissions.

 2.1.1,3  Breakdown of Sampling Run Weight Gains—
     A breakdown of the sampling run weight gains for both conventional and
recycle operation is presented in Table 2-9.  This table provides the weight
gain from the filter, front half and the acetone blank correction factor.
This correction factor is calculated from the weight gain of a spectro grade
acetone blank per ml and multiplied by the amount of acetone wash used in the
dry down  procedure.

2.1.1.4   Discussion of Particulate Emissions During Conventional and Recycle
          Froductioo—
     One  of  the objectives of this test program  was to compare the particulate
loadings  during conventional and recycle production modes.  Several general
observations were made based on the data presented  in Tables 2-1 through 2-8.
These  include;

      *   Compliance  with  the NSPS particulate emission  standards of
          0,04 gr/dscf was met for all runs.

      *   The collection efficiency of particulate  by  the  baghouse was above
          99.9  percent for all sampling runs.

      During  conventional operation,  the uncontrolled emissions were much
higher than  during  recycle operation.  This  is due  to  the  use of much  finer
material, mostly  sand, being used during conventional  production.  During
recycle production,  50 percent of  the material fed  to  the  drum was recycled
asphalt pavement.

      One conclusion that can be drawn for  these  data  is  that during
conventional operation,  the  particulate  loadings are higher than during
 recycle operation.   Therefore, any  increase  in opacity during recycle
operation, cannot  be attributed to paniculate.

2.1.2  Total Organic  Carbon Results

      Total Organic  Carbon  (TOG)'samples were collected  simultaneously  with  the
particulate  mass  samples from  the uncontrolled and  controlled locations
utilizing the Modified Method  5i  sampling  train.  The  0.1  N NaQft impinger
 solutions and rinses were  analyzed  for TOC  using a Beckaan Model  915
                                    2-6

-------
                       TABLE 2-5.   SUMMARY OF PARTICIPATE  AND TOTAL ORGANIC CARBON EMISSION DURING RECYCLE OPERATION (ENGLISH UNITS)
Date
Run
Eolation Type
flaghoute Pressure Drop (in/ll2p)
Production Rat* (tons/hour)
Process Mix Type
Average Opacity (X)
(mean, range)
Pjirticutate and Total Organic
Carbon (TOG) Remit a
Front Half Catch-Part ioilate


gr/dacf
ro lb/hr
| Ib/ton production
Collection Efficiency Percent1"
Back Half Catch - TCC
(inpinger solution! and riniei)
rag * an*
gr/dacf
Ib/hr
Ib/ton production
Total Catch Particulate - TOC
mg - mas*
gr/dacf
Ib/hr -
Ib/ton production
Collection Efficiency Percent
9/28/84 9/28/84 9/28/84
56 7 Average

4.3 4.7 4.7 4.6
329 313 307 316
RAP RAP RAP RAP

4.5 (3.5-5) H/A N/A 4.5 (3.5-5)

.
• -

11507.23 40,46 17136.08 35.23 13817.09 ' 14li3.47 37.84
7.085 0.008 10.939 0.006 8.65S B.890 0.007
1414.622 1.674 2085.637 1.483 1648.721 1716.330 1.578
4.300 0.005 6.660 0.003 5.370 5.426 0.005
99.9 99.9 N/A 99.9


54.53 321.90 173.24 295.55 63.84 97.21 308.71
0.034 0.062 0.111 0.053 0.04O O.062 0.057
6.704 13.319 21.085 12.440 7.617 11.802 12.879
0.020 0.040 0.067 0.038 0.025 0.037 0.040
—49.25 41.01 N/A -6.98
11561.76 362.36 17309.32 -330.78 13880.93 14250.68 346.56
7.119 0.070 11.050 0.059 8.695 8.950 0.064
1421.33 L4.99 2106.72 13.92 1656.34 1728.13 14.46
4.320 0.045 6,730 0.043 5.395 5.460 0.045
98.96 99.35 W/A 99.18
*No controlled run conducted.
^CEP b««ed on Ib/hr values.

-------
                                 TAIII.E  2-6.   SUHKARY  OF  PAHTICULATE  AND TOTAL ORGANIC CARBON EMISSION DURING RECYCLE OPERATION (METRIC UNITS)
N>
A,
Uate
Run
Enitaion Type
• Baghoute Preaaure Drop (in/lljO)
Product ion Race (kg/()
tioeett Hit Type
Average Opacity (t)
(•ean, range)
Fjrticulate and Total Organic
Carbon (TOC) Remlti
Front Half Catch-Port i cul at e
(probe, cyclone and filLor)
xg - naaa
ng/dacoi
8/<
g/kg production
Collection Efficiency Pirii-eni'
Back Half Catch - TOC
•g - oaaa
ng/d9c»
»/•
g/kg production
Collection Efficiency Percent
Total Catch FartlcuiaK - TOC
•g ~,maaa
ng/d.co
«/•
g/kg production
Collection Efficiency Percent
9/3B/B4
5
Uncontrolled Controlled
4.3
82. »
RAF

*.5 (J.5-5)




11507.2} 40.46
16208 .08 18.10
178.738 0.211
2.1)0 0.0025
99.9

S4.53 371.90
77.78 141.81
O.UA5 1.678
0.010 0.020
-49.25

mt>l,7l> 362.16
16ZSS.86 160.11
179.081 1.889
2.160 0.02)
°B.gi
9/28/84 9/28/84
D 7 Average
Uncontrolled Controlled Uncontrolled Controlled* Uncontrolled Controlled
4.7 4.7 4.6
78.9 77.4 79.7
RAP RAP RAP

N/A N/A 4.5 (3.5-5)
.>



17136.08 35.21 11817.09 14153.47 37.84
25013,30 11.73 19799.72 20140.17 16.01
262.780 0.18? 207.734 116.251 0.198
3.310 0.002) 2.680 2.713 0.0025
99.9 N/A 99.9

173.24 295.55 61.84 97.21 308.72
253.93 121.25 91.51 140.92 1)0.85
2.660 1.567 0.960 1.487 1.623
0.014 0.020 0.012 0.019 0.020
41.01 N/A ; -6.98

17309.32 330.78 11880.93 14250.68 346.56
25267.21 ' 114.98 19891.23 20481.29 146.86
265.440 I.7S4 208.694 217.740 1.821
3.164 0.022 2.692 2.730 0.021
99. H N/A 99.18
          *No  controlled run conJuct

          'CEP bated on g/« values.

-------
TABLE 2-7.  SUMMARY OF UNCOrfTROLLED PART1CUUTE AND TOTAL ORGANIC CARBON EMISSION DURING RECYCLE
                                                                                                 OPERATION
Hun Nuvber

Date
Volume Cut Sampled (d«cf)
Stack Gas Flow Race (dicfn)
. Stack Tenpcraeure, "F
Percent loakinetic
Production Rate (ton/hr)
Proceia Mix Type
Particular* and Total Organic
I Carbon (TOC) knult.
Front Naif Catch-Particulat*
(probe, cyclone and filter)
ng
gr/fltcf
Ib/hr
Ib/ton production
Back Half Catch - TOC
(inpingtr solution! and rinaea)
ng - nasi
gr/dacf
Ib/hr
Ib/ton production


9/28/84
24.315
23,294
340
20.5
103. 5
329
RAP




11)07.23
7. 085
1414.622
4.30


S4.53
0.034
6.704
0.020


9/28/84
24.279
22,244
346
21.1
104.6
313
RAP




17136.08
10.939
2085.637
6.66


17J.24
0.111
21.085
0.067

7
9/28/84
24.917
21,194
349
23.1
106.7
307
RAP




13817.09
8.655
1648.721
5.37


63.84
0.040
7.617
0.02S

Average

24.503
22,244
34}
21.96
104.93
316
RAP




14153.47
8.890
1716.330
5.436


97.21
0.062
11.B02
0.037

-------
                                TABLE 2-8.   SUMMAR* OF CONTROLLED PARTICIPATE AND TOTAL ORGANIC CARBON  EMISSION  DURING  RECYCLE OPERATION
to
 I
Run tiunber
Due
Volune Can S.iMpLeJ (Jicf)
Stack C» Fl;.w R.lttf (dicta)
Stack TcBptrutur.:, 'f
Percent Moisture by VoluM
Percent lotkinetic
Production Hjtr (ton/br)
Proceia MIK Tyi>«
Parttculate :inU 1'ntal Organic
Carbon (TOC) R»»uU«

(probe, cycliine ;mJ filter)
•g
(r/d
-------
TABLE 2-9.  BREAKDOWN OF SAMPLING RUN WEIGHT GAINS
Date
Tine
Sample
description
Front half Blank corr. Filter & front
Filter "C. weight gain acetone half we.
(g) (g) (g) (g)
Conventional Controlled
9/24/84
9/25/84
9/26/84
9/27/84
9/24/84
9/25/84
9/26/84
9/27/84
1330-1601
1254-1830
0932-1154
0906-1641
1337-1715
1256-1526
1007-1102
0904-1408
LI-BO-M5E/I-1
LI-80-H5E/I-2
LI-BO-W5E-1-3
LI-BO-M5E/1-4
H-BI-M5E/I-1
LI-BI-M5E/I-2
LI-BI-M5E/I-3
L1-BI-M5E/I-4
0.01535
0.09207
0.1123
0.07726
Conventional
0.37783
0.26053
0.27436
0.71857
0.03413
0.03208
0.06043
0.05077
Uncontrolled
160.12961
183.11814
147.48802
84.24214
Unconventional Controlled
9/28/84
9/28/84
0815-1204
1231-1450
LI-BO-H5E/I-5
LI-BO-M5E/I6-6
0.01334
0.02145
0.02932
0.01438
Air Emissions
0.001
0.0008
0.0011
0.0013
Air Emissions
0.0076
0.0068
0.0064
0.00335
Air Emissions
0.001
0.0006
0.04948
0.12415
0.17273
0.12803
160.50744
183.37867
147.76238
84.96071
0.04266
0.03583
Acetone wash
volume
(ml)
325
285
375
450
2565
2250
2125
1100
325
200
Total
(g)
0.04848
0.12335
0.17163
0.12673
160.49984
183.37187
147.75598
84.95736
0.04166
0.03523
Unconventional Uncontrolled Air Emissions
9/24/84
9/28/84
9/28/84
0820-1043
1126-1302
1334-1429
LI-BI-M5E/I-5
Ll-BI-M5i/I-6
LI-BI-M5E/I-7
0.65816
0.40776
0.44267
10.85087
16.73242
13.37652
0.0018
0.0041
0.0021
11.50903
17.14018
13.81919
610
1400
700
11.50723
17.13608
13.81709

-------
analyzer.  The analyses were performed by Pollution Control Sciences Inc. in
Miaoisburg, Ohio,  The TOG results are designated as back half catches in Data
Tables 2-1 through 2-8 and are discussed in this section.

2.1.2.1  Conventional Operation—
     Table 2-1 (engiish units) and Table 2-2 (metric units) present the TOC
results  for both uncontrolled and controlled operation during conventional
production.  For uncontrolled operation the TOC  loadings were 0.049, 0.022 and
0.0^7 gr/dscf for Runs 2, 3 and 4, respectively.  Run No. 1 at the
uncontrolled location was voided because of a contaminated sample.  No TOC
results  for this test are presented in the data  tables.  The controlled TOC
loadings during conventional operation were 0.020, 0.021, 0,01? and 0.017 for
Runs 1,  2, 3 and 4, respectively.  It should be  noted that, for run No, 2 only
about 73 percent of the sampling points were tested due  to process shut down.
It is believed that this had a minimal affect on the quality of the data.  The
collection efficiencies of  the baghouse for Run  2, 3 and 4 were 44.6, 0 and
50.8, respectively.  Tables 2-3 and 2-4 present  more detailed uncontrolled and
controlled data for TOC emissions.

2.1,2,2  E,2Cwcl2 Operation——
     TOC results for uncontrolled and controlled emissions during recycle
operation are presented in Table 2-5 (engiish units) and Table 2-6 (metric
units).  Additional TOC information for uncontrolled and controlled emission
can  be found  in Tables 2-7  and 2-8.  The uncontrolled TOG  loadings were 0.034,
0.111 and  0.040  for Run 5,  6 and 7, respectively.  Time  constraints permitted
the  collection of only two  controlled emission samples.  The results of these
TOC  test were 0.062 gr/dscf for Run 5 and  0.053  gr/dscf  for Run 6.  The
collection efficiencies   for Run 5 and 6 were -49.2 and  41.0, respectively as
 shown in Table 2-6,

2,1.2.3  Discussion of Results—
     The TOC  results  for  uncontrolled emissions  during  conventional operation
 ranged  from  0.022  to  0.049  gr/dscf.  The average TOC  loadings was
 0,039 gr/dscf.   For controlled conventional  emissions,  the  loadings only
 varied  from  0.017  to  0.020  with an average loading of  0.019 gr/dscf.  For
uncontrolled  emission during  recycle operation  the TOC  loading  results ranged
 froa 0.034 gr/dscf  to 0,111 gr/dscf.  The  average value  was 0.062 gr/dscf.
The  controlled emissions  varied from 0.053 to 0.062 gr/dscf.

      The average TOC  loading  at the controlled  locations increased from
 0.019 gr/dscf during  conventional operation to  0,057 during  recycle
 operation. - It was  expecte-i that  there would  be  a similar  elevation in TOC at
 the  uncontrolled location during  recycle operation.  The data did not show
 this expected rise  in TOC loading.  This  inconsistency  can be explained  as
 follows.

      For controlled Runs  5  and  6  and  for uncontrolled  Run  5, replicate TOC
 samples were  analyzed 9  times  each  ~.o establish  a 95 percent confidence
 interval.  The  results of these tests  indicate  that  the  TOC*'results of this
 test program could  vary  an  average of +22.8 rag/1. This  value corresponds co
 9 percent to 65  percent  of  the TOC  sample  results.  The  highest variability  in
 results were encountered  with  the  sample with  the lowest concentrations.  The
                                     2-12

-------
TABLE 2-10.  SUMMARIES OF 1KPIHCER BACK HALF RESULTS DURING CONVENTIONAL OPERATION UNCONTROLLED TOTAL ORGANIC CARBON AND 1MPINGEK ACETONE RINSE VALUES



(Si
i— »
w



Run
Date
-Valuae Ga* Saapled (dscf)
• Stick Oat Flow Rate (dscln)
Production Rate (t«ms/hr)
Process Hix Typ*

Back Half Impinger Catch
Eg
gr/dacf
Lb/hr
Ib/ton production
Percent Acetone Rtnte Catch
of Total Inpingtr Catch
t
9/24/8A
56.116
20,638
110
CON
Acetone
TOC Rinte
a 109.91
0.011
5.541
0.018

«/*


Total
109.91
0.031
5. 541
0.018




TOC
80.52
0.049
10.031
O.OJJ


2
S/25/84
24.816
23,662
111
CON
Acetone
Rime
75,89
0.047
9.456
0.030

48.48


Total
156.41
0,0%
19.490
0.062




TOC
3J.1
0.022
4.634
0.01S


3
9/26/84
2S. 810
24,798
308
CON
Acetone
Rime
43. 37
0.025
5.418
0.018

53. 99


Total
80.4?
0.047
10.052
0.033




TOC
74. It
0.047
9.459
O.OJ5


4
9/27/84
23.924
23,630
267
CON
Acetone
Rime
412.63
0.260
52.629
0.197

84.96
Average
32.66
23,182
299
COM

• Total
486.79
0.307
62.088
O.J3I



TOC
63.93
0.039
8.042
0.027


Acetone
Rinse
177.30
0.110
22.501
0.082

75.5
b
Total
241.23
0.149
10.540
0.108


  not include run 1.

-------
     TABLE I'll.  SUMMARIES OF K-VIHCER BACK HALF RESULTS  DURING COHVEHTIONAL OPERATION CONTROLLED TOTAL ORGANIC CARBON AND IMPINGE* ACETONE RINSE VALUES
Run
Date
Voluoe Ca* Sampled (ducf»
Stick Kit Flow Rice dliclu)
Production Rite (toiu/hi)
PTOCCII Hi* Typ«
rx)
1
>— Bick Hi If Inplnger Catch
•g
gr/dicf
Ib/ton production
1
9/24/84
90.100
29.597
310
Convention*)
Acetone
TOC Rime Total
113.2 53.32 170.52
C.020 0.010 0.030
5.035 2.418 7.453
C.OI6 0.008 0.024
1
9/25/84
74.098
11.448
311
Conventional
Acetone
TOC Rinee Total
100.3 104.58 205.08
0.021 0.022 0.043
5.589 3.816 11.40
0.018 0.019 0.043
1
9/26/BJ, J
93.270
11.527
308
Conventional
Acetomi
TOC Rinte Total
106.7 61.61 168.31
0.017 0.010 0.017
4.661 2.691 7.352
0.015 0.009 0.024
4
9/27/64
90.S68
11.032
267
Convent ion* 1
Acetona
TOC Rinte
101.92 49.74
0.017 0.008
4.601 2.245
0.017 0.008
Average

87.109
30.901
199





Convention*!
Acetone
Total TOC Kinte Total
151.66 106.08 67.81 173
O.O23 0.019 O.OIIS 0
6.846 4.971 3.292 8
0.026 0.017 0.011 0
.89
.0315
.163
.026
of Total lapinger C»lih
32.S
                          4J. 7»
                                                  36.71
                                                                            12.81
                                                                                                      39.Hi

-------
Ut
                       TABLE  2-12.   SUMMARIES OF  IMPINGER  BACK HAtP RESULTS DURING RECYCLE OPERATION UNCONTROLLED TOTJU. ORCABIC CARBON
                                    AND  IKPINCER  ACETONE RINSE VALUES
Run
Date
Volume Gaa Sampled (dscf)
Stack Gas Flow Rate (dscfm)
Production Race (tons/hi)
Process Mix Type

Back Half Impinger Catch
mg
gr/d*cf
0.126 Ib/hr
Ib/ton production
5
9/28/84
24.315
23,294
329
RAP
Acetone
tOC Rin«e Total
54.43 26.31 80.84
0.034 0.061 0.095
6.704 3.230 9.934
0.020 0.010 0.030
6
9/28/84
24.279
22,244
313
RAP
Acetone
TOC Rinee
173.24 58.05
0.111 0.037
21.085 7.065
0.067 0,023
7
- 9/28/84
24.917
21,194
307
RAP
Acetone
Total TOC Rinse
231.29 63.84 153.10
0.148 0.040 0.096
28.150 7.617 18.261
0.090 0.025 0.059
Average

24.503
22,244
316.3
RAP
Acetone
Total TOC Rinse
216.94 97.21 79.15
0.136 0.062 0.065
25.880 11.802 9.518
0.084 0.037 0.030







Total
176.36
0.126
21.320
0.0670
            Percent Acetone Rinse Catch
            of Total  Impinger Catch
32.55
25.03
70.58
42.77

-------
EPA audit TOG sample resulcs also show high variability at low concentrations.
The 95 percent confidence interval for Run 6 uncontrolled was +28.3 mg/1.  If
similar confidence intervals were applied to the remainder o£ the test
samples, then a accurate interpretation of the TOC data cannot be made.  Based
on this fact and the limited quantity of data, no conclusions or correlations
between convention and recycle operations can be made.  The back half
emissions section provides explanations for inconsistencies in TOC data
including the negative removal efficiencies.

     Additional information on lab results, TOC audit  sample results and
confidence interval determination can be found in Appendix G.

2.1.3   Impinger Residue Film

     These samples consisted of  the  impinger acetone rinses which were used to
remove  the black film material condensed on the impingers and glassware.  The
acetone rinses were dried to a constant weight and added to the TOC values.
These resulcs for the conventional and recycle operation are discussed in the
following sections.

2.1.3.1  Conventional Back Half  Emissions—
     Table 2-10 contains back half emission data for conventional uncontrolled
operation.   The total TOC loadings for Runs 2, 3 and 4 were 0.096, 0.047 and
0,307 gr/dscf, respectively.  No TOC value was obtained for Run  1 because of  a
contaminated sample.  The average  back half TOC  loading for conventional
operation was 0.149 gr/dscf with an  average of  75.5  percent of the loading
coming  from- the acetone  rinses of  the glassware.  The  corresponding
conventional controlled  data is  presented  in Table 2-11.  For Runs 1,2,3 and
4 the  back half TOC  loadings were  0.30,  0.043, 0.017 and 0.025 gr/dscf,
 respectively.  The  average  controlled back half TOC  loading for  conventional
operation was 0.031  gr/dscf with an  average of  39,8  percent resulting  from the
acetone rinses.

 2.1.3.2 Recycle  Back Half  Emissions—
      Back half TOC  loadings for  uncontrolled  recycle operation are presented
 in Table  2-12.  The TOC  loadings were 0.095,  0.148 and 0.136 gr/dscf  for
Run 5,  6  and 7,  respectively.  The average total  loading was 0.126 gr/dscf
with an average of  42.8  percent  of the  load  found  in the acetone rinses.  Only
 two controlled  recycle runs were conducted.   The  back  half  results for these
 two runs  were O.iOo and  0.065  gr/dscf for Runs  5  and 6,  respectively.  The
 average controlled  back  half  loading was 0.088  gr/dscf.  The  average  loading
 found in the acetone rinse  was 34.2 percent.  Results  for  controlled  back  half
 emissions  can be  found on Table  2-13.

 2.1,3.3  Discussion of Impinger  Back Half Results—
      The back half  TOC results are difficult  to  interpret.  The  back  half
 emission results  show that  from  20 to 85 percent  of  Che total  load can adhere
 to the glassware  and must be  rinsed off  with  acetone.   Data Tables  2-1
 through 2-8 do  not  account  for this fact and  present only  the TOC values
 obtained from the impinger  solutions.  In addition to  this,  the  95 percent
 confidence interval established  for some of the TOC  samples  show high
 variability.  Based on these  facts,  the  conclusion can be  made  that  the  data
                                      2-16

-------
           TABLE 2-13,  SUMMARIES OF IHPINGER BACK HALF RESULTS DURING RECYCLE OPERATION CONTROLLED TOTAL ORGANIC CARBON
                        AND IMPINGER ACETONE RINSE VALUES
Run
Date
Volume Gas Sampled (dscf)
Stack Gas Flow Rate (ttscfm)
Production Rate (tons/hr)
•j3 Process Hix Type
Back Half Impinger Catch TOC
ng 321.90
gr/dicf 0.062
Ib/hr 13.319
Ib/ton production 0.040
Percent Acetone Rinse Catch
of Total Impinger Catch
5
9/28/84
80.787
25,087
329
RAP
Acetone
Rinse
238.86
0.046
9.883
0.030
42.85
6 7a
9/28/84
89,495 H/A
27,567
313
RAP
Acetone Acetone
Total TOC Rinse Total TOC Rinae Total
560.76 295.55 82.59 378.14
0.108 0.053 0.015 0,068
23.202 12.440 3.476 15.916 H/A
0.070 0.038 0.011 0.049
21.84
Average

85,14
26,327
321
RAP
Acetone
TOC Rinse
308.72 160.72
0.057 0,031
12.879 6.679
0.040 0.021
34,15
'





Total
469.44
0.088
19.558
0.061

*No controlled run conducted.

-------
for IOC shown in Data Tables 2-1 through 2-8 are highly questionable.  The
fact that varying amounts of TOG can adhere to the glassware helps explain the
inconsistencies in ehe TOC data including the negative removal efficiencies.
The back half emission results in Tables 2-9 through 2-12 probably gives a
better indication of TOC loading than those provided in Tables 2-1 through 2-8.

2.1,4  Visible Emission Results

     Visible emission observation reading were taken by a certified reader.
The opacity of a plume can be -assigned the greatest degree of accuracy when
viewed under conditions where a contrasting background is present.  During
most of the test week overcast skies, creating a bad background, prevented
readings from being  taken.  Readings for both conventional and recycle
production that were obtained are discussed below.

2.1.4.1  Visible Emissions During Conventional Operation-
     Opacity readings were performed during conventional  test Run 2.  Approxi-
mately 3 hours of readings-were conducted.  Table  2-14 present the 6 minute
averages for this time period.  The results are also represented graphically
in Figure 2-1.  The  average opacity during  this conventional test was
0.25 percent.  The maximum 6 minute opacity was 1.25 percent.  Field data
sheets for these readings can be found in Appendix A.

2.1.4.2  Visible Emissions During Recycle Operation-
     Table 2-15 presents  the results of  the visible emission observation
readings conducted during recycle production.  Graphic representation of  these
results  is shown in  Figure 2-2.  These readings were performed during recycle
test 5 and continued into Run 6 and  7.   The average 6 minute average opacity
during these readings was 4.50  percent.  The maximum 6 minute average opacity
for  this period was  5.0  percent.  Field  data sheet for these opacity readings
can  be found in Appendix  A.

2.1.4.3  Discussion  of Visible  Emission  Results—
     The average opacity  rose from  0.25  percent during conventional  opertion
to 4.5 during  recycle operation.  The particulate  emissions data  show that the
controlled particulate emission during  recycle operation  are well  below the
controlled particulate emissions during  conventional operation.   Therefore,
 the  increase  in opacity  during  recycle operation  is not due to particulate
emissions and  probaDiy due  to an  increase  in condensibie  hydrocarbon emissions.

 2.1.5  Moisture Determinations  of  Process  Samples

     Discrete  grab  samples  of virgin aggregate and recycled asphalt  pavement
were obtained  during each of  the  sampling  runs.  A representative  portion of
 these  samples  was weighed,  dried and reweighed to  determine weight  loss due to
moisture.

2.1.5.1  Conventional Operation Moisture Results—
     A total of  four samples  of virgin aggregate  were  taken one for  each
conventional  run.  The  samples  were obtained directly  from the feed
conveyors.  Table  2-16A  presents  the moisture determination result for
                                    2-18

-------
        TABLE 2-14.  SUMMARY OF VISIBLE EMISSION OBSERVATIONS DURING
                     CONVENTIONAL OPERATION
Date
Run No.
Time
Average opacity
 for 6 minutes
9-25-84 2 1300
1312
1318
1500
1506
isia
1518
1524
1530
1536
1542
1548
1554
1600
1606
1612
1618
1624
1630
1636
1642
1648
1654
1700
1706
1712
1718
1724
1730
1736
1.25
0.625
0.625
0
0.208
0
0.416
0
0
0
0
0.208
0.208
0.208
0
0.416
0
0.208
0.208
0
0.208
0
0.416
0.833
0.208
0.416
0.208
0.208
0.208
0.625 AVE 0.25
                                   2-19

-------
TABLE 2-15.  SUMMARY OF VISIBLE EMISSION OBSERVATIONS DURING RECYCLE OPERATION
Dace Run No. Time
9-28-84 5 1032
1038
1044
'1050
1056
1102
1108
1117
1122
1128
1134
11 40

1146
1152
1158
1204
1210
1216
1222
6 1228
1239
1245
1251
1257
1303
1309
1315
1327
7 1333
1339
1357
1403
1409
1415
1421
1427
1433
1439
1445
1451
1457
Average opacity
for 6 minutes
3.54
4.58
4.37
4.79
5.0
4.37
5.0
5.0
4.79
4.16
4.79
4.58-

4.79
4.58
4.37
4.58
4.37
4.32
4.58
4.58
4.79
4.58
4.79
4.37
4.58
4.58
4.79
4.79
4.58
5.0
4.79
4.79
4.37
5.0
4, 53
4,79
4.58
4.37
4.79
4.37
5.0 "• AVG. 4.50
                                     2-20

-------
conventional operation.   The average moisture content of virgin aggregate
during conventional testing was 2.4 percent.  The field data sheets can be
found in Appendix D.

2,1.5.2  Recycle Operation Moisture Results—
     A total of 4 samples were taken for moisture determination during recycle
production.  One virgin aggregate sample and one RAP sample for each recycle
test run.  No sample was taken for 7 uncontrolled.  The results of these tests  '
are presented in Table 2-16B.  The average moisture content of the virgin
aggregate during recycle operation was 3,3 percent.  The average moisture
content of the recycled asphalt pav.ement samples was 3.1 percent.  Field data
sheet for these determinations are in Appendix D.

2.1.6  Smoke Point Determinations

     Two recycled asphalt pavement samples were collected during recycle
production.  The results of the stnoke point tests are shown in Table 2-17.
The average smoke point temperature for the RAP samples was 352°F.

2,1.7  flash foint Determinations

     Two different types of asphalt cement are used during production, one is
used during conventional production, the other during recycle production.   One
asphalt cement sample was taken for each production mode.  The results of the
flash point testing are presented in Table 2-18,

2.1.8  Viscosity of Asphalt Cemenc_ Saagles^

     The two asphalt cement samples were also analyzed for viscosity.  The
viscosity results are presented in Table 2-19.

2.1.9  Fuel Oil Sample

     One fuel oil sample was taken and retained for possible analysis.
                                    2-21

-------
TABLE 2-16.  SUMMARY OF PROCESS SAMPLE MOISTURE MEASUREMENTS




             TABLE 2-16A.  CONVENTION OPERATION

Run No*
C-l
02
C-3
C-4

Date
9-24-84
9-25-84
9-26-84
9-27-84

Time
1436
1520
1045
1015
Virgin aggr«
Sample
wt. g
314.5
274.7
224.6
217.2
igace
Moisture
by weight %
2.1
2.0 .
2.3
3.2
               TABLE  2-16B.   RECYCLE OPERATION
Virgin aggregate
Run No.
R-l
R-2
Sample
Date Time wt. g
9-28-84 0920 212.5
9-28-84 1355 217.1
Moisture
by weight %
4.3
1.7
Recycle asphalt pavement
Time
0925
1358
Sample
wt. g
214.3
203.5
Moisturt
by weight %
2.0
4.1
                           2-22

-------
               TABLE 2-17.  SUMMARY OF SMOKE POINT DETERMINATIONS
Run
Collection
   date
   Time
   Sample
    type
    Smoke
    point
temperature °P
R-l

R-2
 9-28-84

 9-28-84
   0925

   1358
    RAP

    RAP
     344

     360
               TABLE 2-18.  SUMMARY OF FLASH POINT DETERMINATIONS
Run
 Date
Time
Sample
 type
         Flash
         point
     temperature "C
Conven-   9-24-84
  tional

Recycle   9-28-84
               1422
                1356
             Asphalt: cement


             Asphalt cement
                          244 °C
                          218°C
            TABLE 2-19.  VISCOSITY RESULTS OF ASPHALT CEMENT SAMPLES
Sample
Conventional
Recycle
Temp.
"F
140
140
Vacuum
(mm of Hg)
300
300
Viscosity
(poises)
1,153
876
                                      2-23

-------
D-
4-
3-
n-

i
L r
ol nlnnl


J
J-f • • i | ! 1
I20C 1300 1400 ISOO . I60O 1700 I8C
TIME
Figure 2-1.  Six-minute average opacity during conventional operation.

-------
 I
NJ

Ul
                  - 4-
                  o
                  
-------
                                          3,0

                       PROCESS DESCRIPTION AND OPERATION
     This section provides a. brief description of the asphalt concrete plant
operated by Western Engineering Company, Inc., (Western) near Lincoln,
Nebraska.  The procedures used to monitor the operation of the asphalt
concrete plant during both conventional and recycle operation are also
presented in this section.

3.1  PROCESS DESCRIPTION

     A description of the Western asphalt concrete plant (including the
emissions control system) is presented in this section.

3.1.1  Process Equipment Description

     Western operates a portable CMI plant presently located on Highway 34
between Lincoln and Seward, Nebraska.  The plant normally operates 11 to
12 hours per day, 6 days per week.  Technical data on the plant are presented
in Table 3-1.

     The operation of this plant is typical of drum-mix plants.  Figure 3-1 is
a schematic of the production process for a typical drum-mix asphalt concrete
plant.  Western has four feed bins for virgin aggregate and one feed bin for
the recycled asphalt pavement (RAP).  Aggregate from each bin is metered onto
a conveyor according to the type of mix desired and transported to the burner
end of the rotating drum.  The programmable controller unit automatically
delivers the proper amount of each aggregate to the feed belt.  The aggregate
is heated and moves down the drum as the drum rotates.  When mixes containing
RAP are  produced, the RAP  is added tangentially to the drum midway between the
burner end and the terminal end.  The RAP is mixed with the heated virgin
aggregate; then the asphalt cement is injected into the drum countercurrent to
the direction of the aggregate flow at a point about 5 feet down the drum from
the RAP  entry point.  No recycling agents are used by Western.  (The Nebraska
Department of Transportation specifies that a 120 to 150 penetration grade
asphalt  cement be used in mixes containing RAP).  The final product drops out
the terminal end of the drum at a temperature of about 290°F for RAP mixes or
about 305°F for conventional mixes.  The final product is lifted to a
100-ton-capacity surge bin that is insulated but not heated.
                                   3-1

-------
              TABLE 3-1.  TECHNICAL DATA ON ASPHALT CONCRETE PLANT
                          WESTERN ENGINEERING COMPANY, INC.
             Plant designation
Type plant

Mobility

Plant manufacturer

Model   UDM-190Q

Date purchased

Capacity—rated/typical,  cons/h  (see  text)
 Burner—manufacturer
        model  No.
        rating,  raillion Btu's
        blower,  scfra

 Drum size—diameter,  ft
            length,  ft

 Product  temperature—conventional,  °F
                      leogch, ft

 Asplialt"No.  of tanks
          storage capacity,  gal
          grade

          heater fuel

 Storage—capacity,  tons
          type
          insulated
Drum-mix

Portable

CMI



19783

430/300-330

Mr.
Hauck
JB  630-133
133.7
7,300

9,5/8.5^
40

275*290
40
 30,000 gal
 85-1000  or
 120-150  pen.=
 No.  2 fuel

 100
 Surge bin
 Yes
 aDrum modified in February or March 1983.

 ^Burner end of drum has larger diameter.

 C85-100 penetration grade asphalt cement used for conventional mix',
  120-150 penetration grade asphalt cement used for recycle mix.
                                      3-2

-------
     This plant is rated at 430 tons/h at 4.5 percent moisture removal but is
usually operated at about 300 to 350 tons/h.  The actual production capacity
of an asphalt concrete plant is influenced by weather, type mix produced,
moisture content of aggregate and RAP, and usage race of the paving crew.

     Daring this testing at the Western plant, the highest production rate
that could be .maintained was approximately 310 tons/hr which was actually
slightly below the normal usage rate of the paving crew.  Plant personnel
indicated that the most important factor in this lower production capacity was
probably the cold and windy weather conditions experienced during the
testing.  These conditions caused more of the heat from the flame to be lost
to the surroundings as radiant and convective heat from the outside surface of
the drum than would be lost during warmer and less windy weather.  Also, more
heat was required to heat the cold aggregate and inlet air than would be
required under summer conditions.

     At a production rate of 310 tons/h, the dust return mechanism between the
baghouse and the dryer-drum at the Western plant was overloaded when
conventional surface mixed was produced.  The excess dust overflowed onto the
ground and had to be manually removed.  Dust overloading was less during
production of mixes containing RAP.

3.1.2  Emission Control System Description

     The process emissions from  the drum-mix plant are evacuated from the
discharge end of the drum and go through a knockout chamber to remove large
particles and to slow the exhaust gas stream.  From the knockout chamber, the
emissions are ducted to a negative-pressure baghouse.  The specifications for
the baghouse are presented in Table 3-2.

     At startup, the baghouse is preheated  for several 30-second intervals
before aggregate is fed into the drum.  The shutdown procedures  involve
allowing the baghouse to run through  its normal cleaning cycle while the drum
is cooling and the surge bin is  being unloaded.

     The bags in the baghouse were laundered and about 25 percent were
replaced when the  plant was moved to  its present site  in August  1984.  Since
that time, new seals have been installed on all the bags to ensure that no air
leaks would occur.  The baghouse was  "visolite" inspected on September 19,
several bags were  replaced, and  the baghouse was again "visolite" inspected on
September 20  before testing began on  September 24.

3.2  PROCESS MONITORING

     The operation of the drum-mix plant and  the baghouse was monitored during
testing on September 24, 25, 26, 27,  and 28.  Tables 3-3 through 3-7 provide a
list of the process and control  device  information that was obtained during
this period.

     Although the  design production rate of this plant is reported by CMI to
be 430 tons/hr at 4.5 percent moisture  removal, during this testing the
highest production rate that could be maintained was approximately 310 tons/h
                                    3-3

-------
AGGREGATE FROM
STORAGE
ASPHALT FflOM STORAGE
                                  RECYCLED ASPHALT
                                      PAVEMENT
                                                               PRODUCT  TO STORAGE
                                                                                                      TO
                                                                                                   ATMGSI'lltltt
                                BAGIIOUSE
                                                                                                 TREl
                                     DUST RECYCLED
                                     TO  PROCESS
                     Figure  3-1.  Schematic of asphalt concrete  drum-mix plant.

-------
        TABLE 3-2.  TECHNICAL DATA ON THE AIR POLLUTION CONTROL DEVICE
                    WESTERN ENGINEERING COMPANY, INC.
Type

Manufacturer

Total air flow rate

Age of baghouse

Number of bags

Bag material

Bag dimensions
  diameter
  length

Total cloth area

Pressure drop

Bag cleaning mechanism

Date current bags installed

Air-to-eloth ratio

Fan motor size

Baghouse outlet

Dust disposal
Negative pressure baghouse

Aeropulse

56,000 acfm

5 years

900

14 oz./ft2 Nomex


4.5 in.
8.5 ft

9,200 ft*

5 in.  w.c.

Pulse jet

August 19843

6.3:1

2-100 hp each

Rectangular steel stack

Recycled to drum
aCurrent bags were installed new in August 1983.  They were laundered and
 reinstalled in August 1984.
                                     3-5

-------
                            TABLE  3-3.   PROCESS  AND CONTROL  INFORMATION—SEPTEMBER 24,  1984
       I*rouli*e~                       R,t£ltou£«            Htif it«?r                        li»*ta~                    Wind
       i ion    A|u?r**"                 inlet      Mi*      ***i-                T«?*m»*      t*v**                -—.-__—___.,,»

1 IIM;   tfili      tjih     i pit    tp»*     *F        *F        I      in. w«c.   Mel   ftry    try      In. HA     "P**    t*ir»         C.       110      ID.)       S.J*     Uf*    50      71      ?4.4?       Lrt     K     Cloudy ukttff,  No V.K.


I ; in   i.M      tOH      i)     li.4      »^S       Tin      MM!       S.A                                                   Outlet *#•£ begaa 1:10,
                                                                                                                      inlet test be^«n 1;)?,
I:.'.'. JIH 111) ii U.6 l'7(t
:> 11.1 29i 0 11.7 272
2:1fl 10H 291 (i 11,7 27)
1*1
p, i;0i) 111 I'M 0 li.J >m
t;fi 112 2«*7 O 1S.M 2RH
1:H» JDS 2-J1 II ll.fi 281!
l:iV TO* 194 11 11. « 2?5
4: 11.4 274
*:'Hi 111 298 II U,4 272
5: It ll» JIW H li.l 27O
„„„..
1. Convent ional aurla^R mitt.

Hit 'Ml 5. A
1.1(1 Inn S.4S Lovcreil pruUuct ion race Co
1111 IDA S.h ' Aiphal t cr.ment sa«pli- taken
Kll ino S.i.5 49 t^ fit 29,92 15 E Atrnn-xat e snnple titken >t
111) inu f.&
i
lit '»5 >,4
nn mo 5,t
110 1011 t.4 V> tfc <»H , 29.91' in t; i;l<...dy s(sip», Kr> V.t,
IDS '»t i.4,
1'lft *(8 ^,6 Outlet t«-»t c<>"|»l*t* 49 5t A« 29.92 IS E Clnud? ikiei. Ha V.E.
readings.
110 in t.A
10? inn t.fi
ion inn 5,6 Inlet tc.l co«pirt«l 5:15.




-------
                           TABLE  3-4.   PROCESS AND CONTROL INFORMATION—SEPTEMBER 25,  1984
w
Tirae
9:11
12-54
1:00

1:15

3:00

J:I5
Proiluc-
t inn
rat«',
tph
305
117
115

31)8

305

110
fiatc,
cph
290
30-?
ino

29)

290

295
inlet
RAP, AC, I4»*np. t
tph tph "T
0 14.7 2SO

0 15.2 275

0 14.', ?!5

0 14,6 375

0 14.5 ?80
Hi*
t t'JSIp . ,
•F
120



no

312

JI1
Burnrr
set™ Temp.
£ in. v.e. «*>r ftry
inn 5,fc "18 ' \i

100 ».* 44 51

KM) 5.6

illf) 5.6 45 54

1OO "i.5
R*U- Wind
lujtn id~ B«t]fontt!£ iir , Speeu ,
ity in. Hg mph I>i r. Cotmntnts

?1 29. Q2 30 SE Flant down from 9:^0- l?;30
deck.

l»t inlet test bepan 12:56.
57 31.31 30 SE Mu«tl>r clear skies. V,E.
readings taken.
Plant down from 1:31-2:45
creu.



4.4 ' in. 11 25 SE Clear ikiei. V.E. reading*
taken.
Completed lit inlet lest

at
3:26. Collected aggregate

3:30
3:45
4:1)0

4:15
4:10
4:45
5:00
5:15

5:30
5:45


312
J15
311

310
309
311
310
112

111
304


297
300
298

29ft
295
296
295
297

296
290


0 14. « 2«3 '
n 14,, 2*0
0 14.8 270

ii 14,2 ion
0 14.1 270
0 14.* 270
il 14.5 268
0 14. J 265

0 14.* 260
fl 14.1 365


J2n
111
in"»

MO
101
3OO
3»7
2<*

293
295


100 5.*
90 5.4
inn 5,6 45 55

ion 5.5
100 5.7
ion s.f,
ino 5.6 45 ">5
ino 5.7

100 1,6
ino s.6

•ample *t 3:20.

2nd inlet test begun at 4
'<4 3tl.1l 25 SE Clear skiea. V.E. readin
taken.



•M VI. 3 J 25 SE
Completed outlet test at
5:15.



:57
H*








2nd inlet teat completed at
5:49.

                                                       Ccnnt inueJ)

-------
                                                                               TABLE  3-4   (continued)
                 ProJac-                           ft.^lmii.t*'             Burner                            IU-Li~                      Wind
                  I inn     Ax*r**-                    inlet       Mix       ,>t-i -                  T (*&{•>*       t ive                  -».-.™.-™.™_,».*«
                  race,     p m<,   MAI11    Ai:,       ( I-HWJ*. ,     |«nii]t*,     ( hiv.,     if,       „„,_,._,_    (HIM id--   tijtrcnweter,   Sj»*etl,
                  t|ih       tph     i f»li     t |*M       *F         "I*         t      in. w.c.    W^t   l»ry     i£y        In.  Hg      »ph      0j r>
          6 ;00   3W^       2 ?.«      f>      |), J      2f»S        10?       MM*       ^ .*»       i 2    *?        4O       JO. 14         22


          ft: IS   2K8       2?>      i*      11.4      2?1        HU       1'W       ^.?

          ^no   >m       2'^      s^      11.S      j?:i        VHt       K*0       S.A                                                            PUut sliut down for day.
         I.    *:onv«-!"t ivn.il  »iiii;*t-,- mij(€                                         6.    2n-l  tr»l^l test  invjlid *1w*» Iw  leaks in sanpling t,r*in.
         2.    Viftbln  DH this iliiM*.                     ^-    v'i-M  ],•.'.! i-\i>  *  ?.?*> Kiiiymtn  Jt  100 pL-rcPnl  burner cap
         1.    ls£  Inlet cest  tc«v;iH.i iiu*» to tan* tiller.                       *%.    A^^r.-tf.iti» j»«if.£iir%'  co»le«C * 2.fl  percent.
 l
CD

-------
                                       TABLE 3-5.   PROCESS AND  CONTROL  INFORMATION—SEPTEMBER 26,  1984
                  tion    AKRr*-                 Inli"
                  r.ttf,    Rili',   K.U',   AC.     temf
          Time    tph      tph     Iph    tph      *F
                                                         Hurner                         Rel»-                    Wind
                                                 Mix      set-                Temp.      tSvt'                „____———_
                                                tpm|>»,    ting,     AP»	.   humid-   Sariwaerer,   Speed,
                                                 "f        1      in.  «.c.    Wet   llry    ity       in.  tig      »ph     Dir.
 9:30   305

 «:A1   105

m:fln   307

10:1 i   till
                                          4,3
                                          14.5

                                          11.3
               J78


               275

               273
                                                            310
                                                            m
                                                            3 no

                                                            inn
100


loo

If HI

ino

KM
                                           1.5

                                           i.S

                                           5.7
                                                                                       18
                                                                                                             M.*ia
                                                                                                                                  NW    Cloudy -.ki.'j.  No V.f.
                                                                                                                                       readines taken.

                                                                                                                                       Outlet t*«t begun a:3-.
                                                                                                                                        Inlet test: bVftun IO:C*
                                                                                                     sj
                                                                                                              «.•>;»
           10:30   3i>!

           10;4^   JOT
                         0     lii.t

                         •I     14.0
                                                                     1 1>0       5 , *
CO
vo
           1 I ;iW   }07
           11:15   1(M
                                          11.1
                                    II      14.1
                                                                     inn
                                                            Ml-      1111
                                                                              '..<•
                                                                                             -5
                                                                                                     >»
                                                                                                             w.w
                                                                                                                             Inlet  Celt
                                                                                                                             11:02.
                                                                                                                                       Cloiidv ji
                                                                                                                                                      Nn V.F..
11:10   102

11:45   2»7

12:00   301
                           2HJ
0     1J. t

a     ii,7

<)     11.9
                                                            297

                                                            Iftrl
                                                                              '1.5
                                                                                                                                        ur 1
           11:30
                                          13.*
                                                                     IIHt
                                                                              5.5
                                                                                       39    47     47
                                                                                                             W.4R
                                                                                                                        10
                                                                                                                                  NW    ClnuJy skies.  Ho V.
          Not«3:

          ).   Convent ianal  ^tirfa^a' (nin.

          1.   Plant dawn fr»m II:19-7iO» for rrpjirs U'li.iin off  v«nv  feeder).
          4,   Production rat* lt»v/«Ttf^ at 2:OO to control  rfn»t  lit r.
          S.   Cancelled test  in  aft*rn*ton dut* to !nw product ton  rate an«l short projected run time.
          6.   Afgjgreiate noifltur* content v 2.4 percent.                       "

-------
                           TABLE  3-6.  PROCESS AND  CONTROL INFORMATION—SEPTEMBER 27,  1984
 1
I-*
o
Hroiluc- ft;iptuiui»e Huriier
cinit AR^r**™ inlet Miw Kft~
rate, Kar*"» HAP, AC, t***p. , ti-nfi,, ting*
TJBHJ , tph I |>I| tph tpli *F *F I
9:«n 2f>B 251 0 IJ.5 110 3(15 40


•
»:I5 269 2-S6 0 12.5 2*5 W2 «5
9:"i»l 2I>8 155 (» 17.0 JnO l.'.fl >0
9:'i5 ZAS 25J 0 13.4 270 WO 4ft
IO:fiO 35 :">5 45


1:45 2ft4 J5L' 0 IJ.J 2«» 1HB 4»
2:00 25H 24'. 0 12.2 JJO ?«« «O

2:15 26? 251. 0 11,1 J?i Till 40





J:15, 211 25« 0 12,9 250 IfiO 50
4:00 2J1 26<( 0 12.5 165 JOO 50
Relj- Hind

in'. ».<-. Wfi Dry it) in, Hfj «|>ti Dir. CoanenEi
4.7 44 4t 8*. 10. )0 5 H Cloudy iki*«. Ho r.J.
readin^M. Inlet ttft begun
9:04. Outlet tetc b^jun
9:06,
4.1
4.H
4.H
4.B :,k 49 M 1d.ll 5 N Cloudy ikle*. Ho V.E.
', reading*.
5.) Agyrenate sampled at iS:l5.
5.4
5.1 Production rate lowered 4u*
to bulldotcr probleaj. Teit
•topped from 10:45-2:00.
».fc
5.2 4I> 51 hi 10.)} $ N Cloudy tkiei. No V.E.
couplet* at 2:08.
4.9 riant production rate doun
Iron 2:21 until about 1:00
due to bulldozer problem.
fltat down froi* about 3;15~
3:30 due to lo*c of air
2:21 until 4:01.
4. a
5.0 46 54 54 10.11 Z E Cloudy •*<**, Ho t?.t.
                                                        (con! inited)

-------
                                                              TABLE  3-6  (continued)


Timp
4 MS
V.30
i:40

rroduc-
rttf.
Cph
276
27i
273


p.lti-, BAP,
1 |>h I pli
21.1 0
2h2 0
2S9 0

R.ighouae ttnrniT Rula- Wind


f ph *F "*f 7 in. w.c. Vet Dry ily in. Hft nph Dir. CofflEicnta
12. fl 2o« 295 52 VO
12.1 2*>H 318 VI l>. 9
17. f> 2n% 2°A i"> 4.4 Outlet test complete at
4:41.
Notes :
I.   Convent.nortl  curTac** mix.                                                                              ,
2.   No visible  rtraissions rend due tu clouily nkiuft.
1*   General  production  rate  lower on thii date Ju*»  l^ jirf>Hl^ro,t with th*» bn I tdnrr-r that WJDI used  to  load i»K£ rebate into the feed bin*.  T#gt  was  i topped
     during l wo  periods  uht-n  prodirCtinn rate "aB hehtv 2^0  tph*
&.   PJant  down  from ^Sont 1:15 until 3:30 iluf* to plant  n»r  pr^^siirt* J^fin,                       >
5.   Aggregflte moisture  cnntoot " 1^1 percent.

-------
                                 TABLE  3-7,    PROCESS AND  CONTROL  INFORMATION—SEPTEMBER  28,  1984
        l*rt**lwc-                          ftngiioiisc            Burnt-r                           Rel*-                      "-Jind
         (Mill    AKfcr«'~                   ifilt'l       Hil      *t*l"                  TI?IIIJI.      t I ve                  *._^__--*-——-
         c;*t»-.     KOC» „   SAP.   ^i-,      t*>np. ,     i**Mp.,    linK*     AP,       '—'~—'	   humid-    ft*ro«eier,   Sp«*cd.
1 IMF-     I fill       t (lit     {|*ti    t |>li       *K        *F        t       in,  u.c.    Mt't    llry    ity        in.  H}t      R|>h     Dir.
 H;(iu    }S<       1/1     HI     HI.I      12(1       ?«<>      Km       4.8       IS    la      71        10.^5        5      St     Cl       l?a      110    HJ.J      UO       3'W      10ft       4.4                                                           lit  •iu(l«t l«*t h*j|«n8!|S.
                                                                                                                                      lit  inlrt ir«t b^fan H:l$.
                                                                                                                                      1»(  intrt tr«l he^an A:20.

 H: 1.1    l)l       In1)      |i.<>    !•).<)      Ui)       :H*i      I on       ',.;                                                          Hl.int  iluwn at H:it i
                                                                                                                                     (ruck  short •««•.


                                                                                                     '                               r^iHiir i fl.  Culled

                                                                                                                                     Viillect  DAP nani|>ie at 9:2S.

 9: ifl    111       IhS      |Sd    .«,!      1|S       2«t)      Kill       f..«                                                          Plant  Jiiwn »: M-lli; I' 
                                                                                                                                     I fMt1'*  ?:h»irla4***

|H:','i    HH       ItiJ      Jh<>    9.7      J.',»       1US       Hi       4.0       J">    '.S      S«        1(1.42       |;1      SE     Kr«t;irt  test,  Partly cl.iuJy
                                                                                                                                     »ki«f>.  V.K. rcailinz hP)!it«
                                                                                                                                     Ji  Id; In.

|ii:»>    117      .IS'.      IS.*    ".(.      1«       Mil       ">       1.1

l»!is    i.!l       ISH      ISI    v.s      (in       ,'HI       ?i"       .',.<>                                                          i;UB|>l,.  V.fc.


llr'.S   1li>       I*>(V      do    «.l     tl»       J.I  S      <;•!      *4.'i

I?:«M    !.•'•       B'.      IS»    «.',     li»        Ml       JS       fc.«                                                          l-t«l>l.