U.S. Environmental Protection Agency  Region III
    Sharon Steel Corporation   Fairmont Coke Works Superfund Site
                                       Fairmont, West Virginia
                                        Project Overview
  Cleanup Continues - Redevelopment Plans Underway
                              November 2008
ExxonMobil Environmental Services Company, the United States Environmental Protection Agency (EPA)
and West Virginia Department of Environmental Protection (WV DEP) continue coordinated efforts to
clean and return the Sharon Steel Corporation - Fairmont Coke Works Site in Fairmont, West Virginia to
productive use (see site map, below). The site looks very different than it did during its nearly 60 years of
operation.  Old, dilapidated buildings have been torn down,  and a comprehensive environmental
assessment and cleanup is moving toward completion. The three project partners have worked for more
than a decade to prepare the property for redevelopment. Much of the work is being carried out under
EPA's Project XL, a program developed to test innovative environmental management strategies. A key
element of the site work is the recycling of waste materials from two historic landfills.  The material is
excavated, mixed with coal and other materials, then shipped off-site for use as fuel in a local power plant.
This recycling work is continuing and is expected to be complete in 2009. Work in several areas of the site
has already been completed, which allows for future site plans to move forward. Through the City of
Fairmont, the master plan for revitalizing the property includes construction of a hotel, indoor water park,
and a convention center.
The Sharon Steel Corporation-Fairmont Coke Works
Site (site) is located on the eastern bank of the
Monongahela River in the northeast portion of the City
of Fairmont, Marion County, West Virginia (see site map).
The site is being cleaned under the Federal Superfund
Program, which is administered by EPA. The site covers
about 107 acres, 57 of which were used for coke
production processes as well as waste disposal and
treatment operations. The remaining 50 acres stretch
across a wooded hillside that descends to the
Monongahela River at the western portion of the site.
Land surrounding the site is a mixture of industrial,
commercial, and residential properties.

There are four areas at the site that have been the focus
of the remediation efforts. Work in the North Landfill
and By-Products area has been completed. Work in the
South Landfill continues. ExxonMobil has also completed
work in another area of the site, referred to as the coal-
storage and coke-handling area, near the entrance to the
facility. EPA is currently reviewing an assessment that
concludes no further action is necessary in this area.
The remaining efforts include completing the South
Landfill and addressing the Light Oil Storage area.

Operational History
The Fairmont Coke Works facility was originally built in
1918 by the Standard Oil Company of New Jersey (the
corporate predecessor to Exxon) for the production of
coke, fuel derived from coal, and for the refinement of its
associated by-products. In 1948, Sharon Steel Corporation
purchased the property and continued coke production
operations until closing the facility in May 1979.

While the plant was in operation, wastes generated during
the coke and by-product production process were
disposed at various locations on the site property. During
normal plant operations, two ponds were used to store
accumulated waste sludge, and the wastes were
periodically excavated from the ponds and stored in two
nearby pits. These ponds and the other waste disposal
locations at the site have been the focus of the extensive
cleanup work completed to date.
                  ?;;   #W/if(x
                  •z             cini
Cleanup History and Progress
Cleanup efforts have been underway at the site for nearly
two decades. The first significant effort was completed in
August and September 1990, when Sharon Steel removed
2.2 million pounds of waste tar from the on-site sludge
disposal areas and transported the materials to a certified
off-site landfill.

In 1993, EPA initiated the comprehensive environmental
cleanup effort at the site. During a three-year period, EPA
stabilized the site and addressed a number of hazards by
removing in excess of 55,000 tons of sludges and debris
and more than 330,000 gallons of wastewaters and other
liquids. In addition, EPA stabilized acidic tar sludges from
both on-site waste ponds, graded the site to effectively
collect and treat rain water before it enters the
Monongahela River, and covered the North Landfill with a
temporary soil cover.

Although EPA's efforts were extensive, more work was
necessary.  The site was included in the  Superfund Program
in 1996, making the property eligible for federal attention
during cleanup.  Since Sharon Steel was  liquidated in
bankruptcy court in 1991, EPA identified ExxonMobil as
the potentially responsible party for remedial work- EPA
and ExxonMobil signed an agreement on September 17,
1997 to implement a Remedial Investigation and Feasibility
Study. This agreement outlined the process to be carried
out at the site and identified a range of appropriate actions.
In November 1997, ExxonMobil approached EPA with a
proposal to conduct a Project XL pilot at the site.
Project XL was created by EPA to test the idea that
innovative environmental management strategies, which
allow more flexibility in scheduling and technical
approach, could result in a faster and more thorough
cleanup. In May 1999, EPA approved ExxonMobil's
proposal, making it the first Superfund Site in the country
to be addressed under Project XL. EPA, the WV DEP,
ExxonMobil, and the Fairmont Community Liaison Panel
signed the Final Project Agreement, which outlined the
process for the project.

As part of Project XL, ExxonMobil committed to
completing the cleanup  of the site under a phased
approach to achieve the overall goal of releasing the
property for redevelopment.

Fairmont Community Liaison  Panel
The Fairmont Community Liaison Panel was established
to serve as a forum for  open discussion of topics related
to the Fairmont Coke Works Site. Members of the
Fairmont community and representatives of theWV DEP,
EPA, and ExxonMobil all participate on the panel.

The panel meets to foster interaction, the exchange of
facts and information, and the expression of individual
views of participants, leading to consensus input. Through
the panel, those overseeing  and performing the work seek
direct and meaningful input  regarding the cleanup of the
site and its return to productive use.
                 P   '",.-,.

-------
Recent Progress
ExxonMobil started the current phase
of the cleanup work in February 2003.
The focus has been on the North and
South Landfills. In this area,
ExxonMobil's contractor ARCADIS is
excavating waste material and
processing recovered material by
blending it with coal and other
materials. This reprocessing is used to
produce a reusable fuel product.
Approximately 8,000 to  12,000 tons of
material is shipped off-site each month
- more than 416,000 tons to date -
and consumed at a local  power plant.
To date, the fuel produced in the recycling effort has
been used to generate over 445,000  megawatts of
electricity, which is enough to power more than 34,000
typical West Virginia homes for one year. The landfill
recycling effort is scheduled to be complete in mid
2009. Material that cannot be recycled is shipped for
disposal offsite.

In other areas of the site, rain water that comes into
contact with contaminated soils continues to be
collected and treated.

Investigations to determine the amount of
contamination at the Light Oil Storage area were
completed in February 2008. A cleanup plan for this
area was submitted to EPA and VW DEP in October
2008. Remediation of this area is anticipated to occur
during the fall  of 2008. Additional accomplishments at
the site include closing, regrading, and vegetating the
North Landfill.
View of site restoration activities underway in
recently remediated North Landfill Basin
View of recently completed erosion and sediment
control repair activities and site restoration in the
South Landfill Swale
                 Redevelopment Plans
                 The primary goal of the cleanup efforts is to prepare the
                 site for redevelopment. The City of Fairmont is working
                 with The Water Works LLC to develop a master plan, and
                 efforts to secure financing are underway. The current vision
                 for the property - depicted on the map below - includes
                 construction of a conference center, a 70,000 square foot
                 indoor water park big enough to accommodate 3,000
                 visitors, and a six-story 300 suite hotel on the river front.
                 Additional redevelopment plans are under consideration by
                 the City of Fairmont.  The ExxonMobil / EPA / WV DEP
                 project team is coordinating with the city to make property
                 and information available as needed.

                 Several areas of the site - including the hillside at the
                 southern end of the property and portions of the land
                 across the northern end - are ready for the first phase of
                 redevelopment. A  number of other areas are scheduled to
                 be released for redevelopment activities by the end of 2008.
                 The agencies and ExxonMobil expect the site to be ready
                 for the city's revitalization plans in the middle of 2009.
                                                                                                          Sharon Steel Corporation - Fairmont Coke Works Site
                                                                                                                   Project Contacts & Public Information

                                                                                   There are a variety of sources of information about the Sharon Steel Corporation - Fairmont Coke Works site.
                                                                                   You can visit the Marion County Public Library or contact one of the project representatives listed below.
                                                                                   In addition, meetings of the Fairmont Community Liaison Panel, which take place on a periodic basis, are open
                                                                                   to the public. The panel meeting dates are provided to local media outlets.  For information about the panel,
                                                                                   contact Mary Green, panel facilitator. If you would like to be added to the project mailing list to receive
                                                                                   periodic updates about the site, please contact Carrie Deitzel, EPA's Community Involvement Coordinator.
USEPA Region III
1650 Arch Street
Philadelphia, PA  19103-2029
24-Hour Superfund Hotline
  800.553.2509  (toll free)

Mary Green
Facilitator
Fairmont Community Liaison Panel
800.250.3868 (toll free)
mgreen@anngreencomm.com
Carrie Deitzel (3HS43)
EPA Region III
Community Involvement Coordinator
1.800.553.2509x45525
deitzel.carrie@epa.gov

Marion County Public  Library
321 Monroe Street
Fairmont, WV 26554
304.366.1210
Eric Newman
EPA Region III
Remedial Project Manager
1.800.553.2508x43237
newman.eric@epa.gov

Tom Bass
WV DEP Project Manager
Environmental Resource
Specialist
304.926.0499 ext. 1274
Thomas.L.Bass@wv.gov
                                                  EPA's Update on the Sharon Steel Corporation - Fairmont Coke Works Superfund Site
                                                   S?
            U.S. Environmental Protection Agency
            Region III
            Carrie Deitzel, 3 HS43
             1650 Arch Street
            Philadelphia, PA 19103

-------