Weekly
             Update
   -or More Information:

       Russ Forba, EPA
         457-5042
     forba.russ@epa.gov

     Diana Hammer, EPA
         457-5040
    hammer.diana@epa.gov

     Keith Large, MT DEQ
         841-5039
       klarge@mt.gov

    Doug Martin, MT NRDP
         444-0234
       dmartin@mt.gov

   Peter Nielsen, Missoula Co.
         258-4968
   Nielsen Pİ ho.missoula.mt.us

         Websites:
     http://www.epa.gov/
   regionS/superfund/sites/
        mt/milltown

    http://www.cfrtac.org
    Milltown Reservoir
    Community Office
^(315 Anaconda St., Milltown, MT)

        Office hours:
    Tuesdays 12:30-3:30 pm
 EPA and DEQ staff are available
  • stop by to talk or just say hi!/
            Milltown    Reservoir
                         Sediments
                  Superfund  Site       ^
Status: The Milltown Reservoir cleanup project is going well — on schedule
for dam removal in spring 2008.  Project personnel have now logged 54,096 hour
without time lost to injury.

Currently.
•  Excavation of the bypass channel continues. Last week work crews removed 30,000 yd3 of
   sediments from the bypass channel. The total volume removed to date is 269,000 yd3. Excava-
   tion continues in two locations, working towards the center of the site. When complete, the by-
   pass channel will be 4100 feet long, 200 feet wide at the top and 100 feet wide at the base. Con-
   tinue to stockpile sediments on site. The bypass channel should be complete in September 2007.
•  Work on the Bypass  channel berm continues.
•  Begin staking in preparation for work on the rail spur from behind the Banner School onto the
   project site.  Once the area is staked out, work on the rail spur sub-grade can begin.  Railroad
   grade construction should take about 1 week to complete. Due to this work, access to the pro-
   ject area will now be the Rustic Road (upper) entrance. The entrance will be gated and posted.
•  Begin preparing the site for construction of the railroad bridge over the bypass channel.
•  Dewatering of the sediments continues to going well.  Envirocon is currently pumping from 19
   dewatering wells on-site, down from 22 active wells last week and 29 the week before (some on-
   site wells dried up and have been shut down). The wells produce approximately 3420 gallons per
   minute (gpm).  Continue to  monitor the water level in the sediments using piezometers. Most of
   the pumped water continues to come from the upstream wells. Current discharges are 3400 gpm
   to the Clark Fork River and 770 gpm to the Blackfoot River. The discharges are monitored for
   arsenic, copper, manganese, and iron.
•  Sedimentation pond will be finished this week.  The headgate and discharge pipes from the
   sedimentation pond to the river have been installed. Now completing the concrete work on the
   outlet. The sedimentation pond will collect storm water from the site and temporarily hold it,
   allowing any suspended solids to settle out before the water is discharged.
   US Army Corps of Engineers will begin removing logs and timber  crib piers in the Blackfoot
   River upstream from the Stimson Lumber Mill this week.
   USACE is finishing up the outer slurry wall  1-90 bridge mitigation. This will aid in keeping the
   grout injected at high pressure from entering the river. A floating walking bridge has been in-
   stalled across the Blackfoot River for the slurry wall work; it will also be use to carry the jet-
   grout hose across the river and allow pedestrian access.
   US Army Corps of Engineers and bridge engineers are designing an articulating wall that will allow
   the high pressure jet-grouting work to  continue.
  These weekly updates are intended
    to provide you with the latest
    information about remediation,
    restoration and redevelopment
  activities at the Milltown Reservoir.

           US EPA Montana Office
           10W.15thSt.,Ste.3200
           Helena, Montana 59626
             1-800-457-2690
                                   SAFETY REMINDER
      DURING CONSTRUCTION. THE CLARK FORK AND BLACKFOOT RIVERS ARE CLOSED TO RIVER
            RECREATION ABOVE AND BELOW THE MILLTOWN DAM AND RESERVOIR AREA.
      Clark Fork River users must exit at the Turah fishing access; Blackfoot River users must
             exit at the Weigh Station access point. VIOLATORS WILL BE FINED.
                  For more information, please call MT FWP at (406) 542-5500.

-------
 Upcoming
 Meetings
 Tuesday,  July 24
 Community Health and
 Safety Committee mtg. 10
 am; Piltzville Fire Station.
 Tuesday,  July 24
 Milltown- Banner
 Community Council Site
 Tour; 11am
 Tuesday,  July 24
 Milltown Reservoir  Rede-
 velopment Working Group
 meeting at the Banner
 Lutheran Church;
 6:30-9:00 pm.
 Saturday,  July 28
 2007 Blackfoot River
 Cleanup Day!  Everyone is
 welcome. Meet at 8 am at
 Rainbow Bend Drive. For
 more info., contact
 George   (244-4622) or
 Marietta (244-5442).
 Wednesday, August 1
 Milltown Cleanup Project
 open house (5:30-6:30
 pm) and public meeting
 (6:30-8:30 pm) in the
 Banner School Gym.
 Learn about the cleanup,
 well monitoring, Trustee's
 restoration plan,
 and tnorek
 i Upcoming work:
     Continue bypass channel excavation
     Continue bypass channel berm construction
     Finish sedimentation pond this week
     Continue rail spur construction from the main
     rail line to the BP/ARCo repository
     Continue pedestrian trail construction along
     Highway 210 E from Fire Station to School
     Begin building the railroad bridge next week
     Work on the abutment underpinning is ex-
     pected to resume next week.
2007


Compacting the base
of the bypass channel
                              Low flows on the Clark
                              Fork expose large logs
  PROJECT  SCHEDULE

       Build haul  roads
       Build flood berms
       1-90 bridge mitigation
       MRL bridge mitigation
       Build bypass channel
       Build pedestrian trail
       Construct  rail  lines
       Rail hauling sediment
       Stage 2 drawdown
       Build coffer dam
       Spillway removal
       Spillway removal
       Sediment removal
       Replace  Hwy 200 bridge
       Dam removal
       Powerhouse removal
       Restoration
       Redevelopment
  09  Restoration         Kfe
       Redevelopment
2010  Restoration
       Redevelopment
2011  Restoration
       Redevelopment
                                                2008
       Bridge over the Blackfoot
       River — for jet-grouting
      , work and pedestrian access
                                                                               :A
                                                          Logs and stumps dug out of
                                                          bottom of the bypass channel.
                                                          Note the size of this conifer!
                 Bypass Channel
                                                                                      Clark Fork River
                                                                                                \

Blackfoot River
                                                                           -
                                                                    I Overview of the Project Area : July 17, 2007

-------