EPA
           United States
           Environmental Protection
           Agency
              Municipal Environmental Research  11023 EYI 04/72
              Laboratory           April 1972
              Cincinnati OH 45268
           Research and Development
High Rate Filtration of
Combined Sewer
Overflows

-------
HIGH RATE FILTRATION OF COMBINED SEWER OVERFLOWS
                         by
                   Ross Nebolsine
                  Patrick J. Harvey
                   Chi-Yuan Fan
               Hydrotechnic Corporation
                Consulting Engineers
              New York, New York 10022
                      for the

           Office of Research and Monitoring


        ENVIRONMENTAL PROTECTION AGENCY
                  Project # 11023EYI
                 Contract # 14-12-858

                     April  1972

-------
                     EPA Review Notice
    This report has been reviewed by the Environmental Protection
Agency and approved for publication.  Approval does not signify that
the contents necessarily reflect the views and policies of the
Environmental Protection Agency,  nor does mention of trade names of
commercial products constitute endorsement or recommendation
for use.
                            11

-------
                           ABSTRACT
       Pilot plant studies were conducted at Cleveland's Southerly
Wastewater Treatment Plant in 1970 and 1971, to develop and
demonstrate the capabilities of the deep bed, dual media, high rate
filtrate treatment process for storm caused combined sewer overflows.

       The treatment system is comprised of a drum screen with a 40
mesh screening element  (420 microns opening) followed by a  deep bed,
dual media, high rate filter of five feet of No. 3 Anthracite
(effective size 4 mm) over three feet of No.  612  Sand (effective size 2 mm),
The results show suspended solids removals of 93 percent, with
polyelectrolyte addition, at a filtration rate of 24 gpm/sq ft at an
average influent suspended  solids of 411 mg/1.  Reductions in
biochemical oxygen demand averaged 65 percent.

       Capital costs (ENR=1470) for a high  rate  filtration plant are about
$23,000  per MGD.  Total annual treatment costs, including capital and
operating charges, range from approximately $90,000 per year for a
25 MGD  plant to approximately $390,000 for a 200 MGD treatment
facilities.

       Principal advantages of the proposed system are: high treatment
efficiencies, automated  operation, and limited space requirements as
compared with alternate flotation or sedimentation systems.

       This report was submitted in  fulfillment of Project # 11023  EYI
(Contract 14-12-858) under  the sponsorship of the Office of Research
and Monitoring, US EPA.
                            iii

-------
                          CONTENTS
Section                                                    Page
   I         Conclusions                                     1




   II         Recommendations                                7




   III        Introduction                                     9




   IV         Pilot Plant Facilities                             15




   V         Testing Program                                 25




   VI         Characterization of Combined Sewer Overflows    39




   VII        Screening Results                                47




   VIII       High Rate, Deep Bed Filtration Results            53




   DC         System Performance                              77




   X         Definition of High Rate Filtration Installations     85




  XI         Cost Estimates                                  105




  XII        Process Potential and Future Research Areas       125




  XIII      Acknowledgements                               131




  XIV        References                                      ^33




  XV         Publications




  XVI       Appendices

-------
                           FIGURES

                                                         PAGE

 1       SOUTHERLY WASTEWATER TREATMENT PLANT             12
        LOCATION PLAN

 2       HIGH RATE FILTRATION PILOT PLANT                   16
        FLOW DIAGRAM

 3       COAGULANT TESTING APPARATUS                      17
        SCHEMATIC DIAGRAM

 4       PILOT PLANT FACILITIES                              23

 5       FILTRATION PILOT PLANT                             24
        LOCATION PLAN

 6       SAMPLING POINT LOCATION SCHEMATIC DIAGRAM       29

 7       SUSPENDED SOLIDS MONITOR INSTALLATION            35

 8       SUSPENDED SOLIDS MONITOR READING VERSUS          37
        LABORATORY RESULTS

 9       SOUTHERLY WASTEWATER TREATMENT PLANT DRY        45
        AND WET WEATHER FLOW CHARACTERISTICS

10       MEAN SUSPENDED SOLIDS REMOVALS BY                53
        FILTRATION

11       FILTER BACKWASH EFFLUENT SUSPENDED SOLIDS        74
        VS. TIME

12       BACKWASH WATER SEDIMENTATION CHARAC-            75
        TERISTICS

13       SYSTEM PERFORMANCE SUSPENDED SOLIDS             73
        REMOVAL

14       SYSTEM PERFORMANCE EFFLUENT SUSPENDED           82
        SOLIDS QUALITY

15       SYSTEM PERFORMANCE EFFLUENT BOD  QUALITY         83
                            VII

-------
                        FIGURES

                                                       PAGE

 16    HIGH RATE FILTRATION INSTALLATION PROCESS         88
      FLOW DIAGRAM

 17    HIGH RATE FILTRATION INSTALLATION PLAN            96
      25 MGD CAPACITY

 18    HIGH RATE FILTRATION INSTALLATION PLAN            97
      50 MGD CAPACITY

 19    HIGH RATE FILTRATION INSTALLATION ELEVATION       98
      50 MGD CAPACITY

 20    HIGH RATE FILTRATION INSTALLATION PLAN            100
      100 MGD CAPACITY

 21    HIGH RATE FILTRATION INSTALLATION ELEVATION       101
      100 MGD CAPACITY

 22    HIGH RATE FILTRATION INSTALLATION TYPICAL          102
      FILTER SECTION

 23    HIGH RATE FILTRATION INSTALLATION RENDERING       104

 24    ESTIMATED CAPITAL COST VERSUS DESIGN             106
      CAPACITY

 25    ESTIMATED ANNUAL TREATMENT COST VERSUS          116
      DESIGN CAPACITY

 26    USE OF A MASS CURVE TO DETERMINE THE             122
      REQUIRED STORAGE

27    ESTIMATED CAPITAL COSTS OF STORAGE AND           124
      TREATMENT FOR 200 MGD OVERFLOW
                          viii

-------
                                TABLES

No.                                                           Page

 1      Southerly Wastewater Treatment Plant Effluent            22
        Quality

 2      Water Quality Analysis                                 27

 3      List of Polyelectrolytes                                 33, 34

 4      Characteristics of Combined Sewer Overflow (late        40
        July - early November 1970)

 5      Characteristics of Combined Sewer Overflow (May -      41
        early June 1971)

 6      Characteristics of Dry Weather Sewage Flow             43

 7      Comparison of Screen Types                            51

 8      Results of Polyelectrolyte Selection Tests                56, 57

 9      Suspended Solids Removals by Filtration                 59

10      Settleable Solids Removals  by Filtration                 60

11      BOD and COD Removals by Filtration                    61

12      Total Phosphorus Removals  by Filtration                 62

13      Solids  Removals by Filtration                           64

14      Grease Removals by Filtration                          65

15      Coagulant Selection Tests                              67

16      Suspended Solids Removals with Alum and  Poly-          68
        electrolyte Addition

17      BOD and COD Removals With Alum and Poly-            69
        electrolyte Addition

18      Total Phosphorus Reductions with Alum and              70
        Polyelectrolyte Addition
                            ix

-------
                            TABLES

No.                                                       Page

19     Effect of Storage on Filter Influent                      72

20     System Performance - Settleable Solids Removals         79

21     System Performance - BOD Removals                    80

22     System Performance - COD Removals                    81

23     Summary of Estimated Project Costs for 25 MGD          108, 109
       Treatment Plant

24     Summary of Estimated Project Costs for 50 MGD          110, 111
       Treatment Plant

25     Summary of Estimated Project Costs for 100 MGD        112, 113
       Treatment Plant

26     Summary of Estimated Project Costs for 200 MGD        114, 115
       Treatment Plant

27     Summary of Estimated Annual Costs for 25 MGD         117
       Treatment Plant

28     Summary of Estimated Annual Costs for 50 MGD         118
       Treatment Plant

29     Summary of Estimated Annual Costs ror 100 MGD        119
       Treatment Plant

30     Summary of Estimated Annual Costs for 200 MGD        120
       Treatment Plant

31     Estimated Capital Costs for Various Treatment
       Plant and Storage Capacities                          123
                         x

-------
                          SECTION I

                        CONCLUSIONS


Characterization of Combined Sewer Overflow

       Results of the sampling and analytical program of combined
sewer overflows for pilot plant evaluation at the Southerly Wastewater
Treatment Plant in Cleveland support the following conclusions:

       1.  A total of about  52 overflows a year can be expected.  Most
of them have a duration of 5 to 6 hours.  The majority of overflows
occur from rainfall having an intensity of between 0.3  and 0.5 inch per
hour.

       2.  The concentration  of suspended solids,  settleable solids,
BOD and COD in combined sewer overflow evidenced at the Southerly
Wastewater Treatment Plant in Cleveland was as follows (July to
November, 1970):

                          Suspended   Settleable
                          Solids      Solids       BOD     COD
                           (mg/1)      (ml/1)      (mg/1)   (mg/1)

       Mean                234        5.26        92      308
       Standard Deviation    135 .       3.02        49      143
       Minimum              28        0.2         16       57
       Maximum            1560       19.0        580      711

       3.  The concentration  of suspended solids generally reached a
maximum level within 1/2 hour  after the beginning of the overflow.
Within 3 to 4 1/2 hours the'suspended solids concentrations dropped to
less than 150 mg/1.

       4.  Comparing combined sewer overflow and dry weather flow
contaminant levels for the 1970 sampling period,  average suspended
solids concentration in the  overflow was 25 percent higher than dry
weather flow. The overflow  BOD, COD and median fecal coliform
levels were about 70, 80, and 30 percent,  respectively of the dry
weather flow.

       5.  For the spring sampling period (May to early June, 1971),
suspended solids,  BOD and COD concentrations in combined sewer
overflows were 110, 30 and 20% greater than in dry weather flows,  res-
pectively.

-------
       6.  From the above quality and quantity findings, the combined
sewer overflow is a major pollutional source which should be consid-
ered for adequate handling or treatment.

Evaluation of Treatment Process
       Results of pilot plant testing of drum screening and high rate,
deep bed, dual media filtration process at the Southerly Wastewater
Treatment Plant in Cleveland support the following conclusions:

Screening Test

       1.  Screening must be provided prior to high rate, deep bed,
dual media filtration for longer runs,  lower headlosses  and efficient
filtration.  A drum screen with a screen size No. 40 element  (equiva-
lent to Tyler screen  scale 35 mesh with 420 micron opening size and
43.6 percent open area) is most adequate and  more effective  for rea-
sonable filtration operation than the corresponding No.  20 (Tyler screen
scale 20 mesh with 841 micron opening-s) and No. 3 (Tyler screen scale
3 mesh with 6350 micron openings) screening elements.

       2.  The No.  40 screen was selected as the screening compo-
nent.  Based on composite sampling for each storm event, the full
ranges of contaminant removals by this screen in combined sewer
overflows were 17 to 40 percent for suspended solids; 50 to 73.5 per-
cent for settleable solids; 4.3 to 22.2 percent for BOD and 4.5 to  41.1
percent for COD.

       3.  A slotted screen element,  furnished by UOP  Johnson Divi-
sion, was evaluated.  The criteria used for evaluating the slotted
screen elements versus the mesh screen was the head loss and length
of run in the filtration  operation.  The results  showed that head loss in
the filter columns, when preceded by the slotted screen, is in the
order of four times as great as that preceded by  a mesh type  screen.
Therefore, suspended solids removal  by the slotted screen was not as
effective as  by the mesh type screen.

High Rate, Deep Bed,  Dual Media Filtration Results

       4.  Conclusions are based on sixty nine pilot filtration test
runs conducted in 1970 and 1971  on combined sewer overflows utilizing
the aforementioned system.  Twenty one filtration test runs utilized
selected polyelectrolytes, twenty nine filtration test runs evalu-
ated combinations of coagulants  (alum or ferric chloride) and poly-
electrolytes  on the filtration system,  and nineteen were plain filtra-
tion runs.

-------
       5.  Based on limited pilot test results utilizing a No. 40 mesh
screen element with a high rate filtration unit, a filter media comprised
of five feet of No. 3 Anthracite (effective size 4.0 mm) over three feet
of No. 612 Sand (effective size 2.0 mm) was shown  superior to coarser
or finer media tested and this media was selected as the filtration
component of the treatment system.

       6.  Due to variations of suspended solids concentration in com-
bined sewer overflows,  the removal efficiency of a high rate filtration
system would fluctuate with the influent concentration, whereas the
more important effluent concentration remained comparatively constant.
Results from a typical filtration run at 8 gpm/sq ft with 30 mg/1 alum
and 1.0 mg/1 polyelectrolyte addition are shown as follows:

Number of  Average Influent    Average Effluent
 Samples    Suspended Solids   Suspended Solids      Removal
                  (mg/1)             (mg/1)
    3              '442                 36               92.0
    2              362                 48               86.7
    2              100                 54               46.0

       7 .  It was found that filtration with polyelectrolyte -addition
would yield better effluent quality or higher removal efficiency than
plain filtration.  Suspended solids influent and effluent levels and per-
cent reductions, averaged from six samples per filter run for system
operation with and without polyelectrolyte addition, are indicated as
follows:

 Filtration Rate     Average  Influent     Average Effluent      Removal
   (gpm/sq ft)            (mg/1)	        (mg/1)	    _

 Plain
      10                   165                 30               82
      16                   175                 37               79
      24                   180                 53               70

 With Polyelectrolyte

      8                   400                   8               98
      16                   200                 10               95
      24                   250                 18               93

       8.  It was found that there was no correlation between BOD
 removal and filtration rate.  Results with 1.0 mg/1  polyelectrolyte
 addition are shown as follows:

-------
Filtration
   Rate        Average Influent     Average Effluent       Removal
(gpm/sq ft )        (mg/1)               (mg/1)
     8              67.0                 31.3            57.0
    16              67.0                 27.0            59.7
    24              67.0                 27.5            60.7

       9.  Total phosphorous removal was  improved with alum
addition.  Results of total phosphorous effluent levels and percent
reductions, with and without alum addition, are shown as follows:

  Filtration
    Rate          Average Influent     Average Effluent    Removal
(gpm/sq  ft )             (mg/1)              (mg/1)           (%)
Without Alum
      8                  0.71                0.43          38.0
     16                  0.71                0.39          45.0

With Alum
      8                  0.90                0.24          73.3
     16                  0.90                0.37          58.9

        10.  The addition of alum and polyelectrolyte to enhance pro-
cess performance produced varying results in removals of suspended
solids,  BOD and phosphates.  Process performance was determined by
suspended solids removals, which ranged from 95 to 65 percent
(filtration rates between 8 and 24 gpm/sq ft ).

        11.  It was found that the high rate filtration system was more
efficient in removing inorganic (inert) suspended solids than for or-
ganic (volatile) suspended solids.  As a  possible extension of these
results, the system would be more effective with urban runoff than for
combined sewer overflows,  as suspended solids in urban runoff
have a higher inorganic fraction,

        12.  For filtration with polyelectrolyte addition, filter runs
generally ranged between 4 and  16 hours,  with the length of run
determined by effluent quality deterioration.  Head losses through the
filter media ranged from 5 feet (8 gpm/sq ft )  to 30 feet (24 gpm/sq
ft ).

        13.  Based on limited verification procedure, an inline sus-
pended  solids monitor  (Model 53) furnished by Biospherics Incorporated

-------
has shown promise in correlating results with laboratory determinations
for suspended solids concentrations ranging between 30 and 240 mg/1.

Screening and High Rate Filtration Installation

        14.  Area requirements for full size high rate filtration plants
including drum screening units,  deep bed filtration units,  backwashing
facilities, polyelectrolyte feed facilities,  and hypochlorite addition
facilities (for plants in the range of 25 to 200 MGD capacity) were
estimated as follows:

                                       Design @ 24  gpm/ sq ft
            Plant Capacity               (93% S.S. Removal)

              25 MGD                        3000 sq ft
              50 MGD                        4600 sq ft
             100 MGD                        9300 sq ft
             200 MGD                      16,500 sq ft
        15.  For high rate filtration plant (s) constructed at remote outfall
 locations, it is apparent, from an operational and economic
 standpoint, that the waste backwash waters should be directed
 to the sanitary sewerage system for subsequent treatment at a
 municipal sewage treatment plant.
        16.  A sufficient degree of automation could be incorporated in
the treatment plant so that it could operate with a minimum attendance
for such items as chemical solution preparation and routine maintenance.

        17.  Based  on pilot plant operational experience, an open,
gravity type filtration system is less prone to occurrence of explosive
conditions than a pressure type filter.

Cost Data

        18.  Capital cost data without a backwash sludge handling
facility (ENR = 1470) and total annual costs, including capital and
operating charges,  for high rate filtration plants,  in the range of 25 to
200 MGD treatment capacity, are estimated as follows (design at
filtration rate of 24 gpm/sq ft):

-------
                                                  Total
       Plant Capacity       Capital,Cost        Annual Cost

          25 MGD          $     830,000       $   97,270
          50 MGD             1,312,000          143,000
         100 MGD             2,351,000          256,100
         200 MGD             3,754,600          388,210

       19.  Based on an average suspended solids concentration of
200 mg/1 in a combined sewer overflow and a 300 hours  per year
operating period,  solids handling and disposal costs, incurred by dry-
weather sewage treatment plants in processing waste  screenings and
backwash solids, could range from 3 to 35 percent of the total annual
cost for the combined sewer overflow filtration facility (without sludge
disposal equipment).

-------
                             SECTION II

                        REG OMMENDATIONS
        1.  A demonstration plant for the treatment of combined sewer
overflows utilizing the deep bed, dual media, high rate filtration pro-
cess should be engineered and constructed so that the encouraging
conclusions, judgments and evaluations presented in this report can be
confirmed through the operation of a full scale facility.

        2.  Additional pilot plant  testing should be undertaken to
develop a more complete system, utilizing the same unit process.  By
using a finer screening mesh, and possibly a finer filter media, with a
more comprehensive evaluation of in-line mixing  and coagulation, a
more efficient and economical system may be developed.

        3.  A pilot plant consisting  of microscreening (23 microns) and
finer filter media should be evaluated to obtain a higher quality
effluent.  Suspended solids,  in combined sewer overflow, would be
removed mainly by microscreening and the dissolved and colloidal
contaminants could be reduced in the  filter by using proper powdered
activated  carbon and coagulant dosage.  It is expected that the cost/
benefit ratio would justify optimizing  this system, since basic unit
processes remain the  same with only moderate increase in screen
sizing. Due to the intermittent operation of a full size treatment plant
(about 300 hours per year  in Cleveland), the additional annual costs of
activated  carbon could be justified  by cost-benefit considerations.

        4.  Define in-depth the capability and associated cost factors
for sewage treatment plants to process waste solids from combined
sewer overflow treatment facilities.

        5.  Further define, through additional pilot plant studies and
engineering evaluations, the possibilities of the  deep bed, dual  media
high rate filtration process achieving  higher quality effluent levels; and
al^o in applying this new  process to other areas of water pollution
control, specifically to the treatment  of urban runoff, primary and
secondary treated domestic sewage effluent and high solids river water
(sediment control).

        6.  The high rate filtration process for combined  sewer  overflow
 treatment located in the area  of a domestic wastewater treatment plant
 can be utilized for polishing the  treatment, overloading or process
 malfunction during the majority of the time when it is not raining.

-------
       7.  For a newly designed domestic wastewater treatment plant,
the high rate filtration process can be adopted to handle both dry and
wet weather flow (combined sewer overflow) with an adequate storage
facility.  This dual usage of the high rate filtration process should be
considered.

       8.  An in-line suspended solids monitor,  such as the Bio-
spherics  unit, should be further investigated.  Depending on further
test results, units such as this should be considered as sensing
devices to enhance automation of the filtration process by providing
positive control of effluent suspended solids concentrations.  This
monitor may also provide the important function of producing continuous
and more reliable data.

       9.  The slotted screening element furnished by UOP Johnson
Division was strong, rugged and maintenance free.  Therefore, a
further in-depth study of this screening element should be considered.
Alternate designs of the screen should include the variation of slot
opening, surface wire shape and rod location.

       10.  Prechlorination of combined sewer overflow prior to high
rate filtration process should be further studied.  Due to the advantage
of the mixing effect in the filter bed, prechlorination could improve the
disinfection efficiency.

       11.  Pilot testing should be conducted to develop mathematical
relationships for a high rate  filtration index or parameter to evaluate
filter performance under varying storm generated influent suspended
solids  concentrations.

       12.  In designing or planning of a full size plant, an open,
gravity type filter should be  considered for process efficiency and
operating safety. Also, a study of the high pressure pumping alterna-
tive to the filter columns should be conducted.  There is a possibility
of high turbulence through the pumps causing suspended solids break-
down which could affect filter performance.

       13.  To develop an ultimate disposal system for solid materials
removed from combined sewer overflows,  further study of backwash
sludge characterization, such as sludge density, biodegradability, and
dewatering method,  should be considered.

-------
                          SECTION III

                        INTRODUCTION
General

       The problem of pollution of the nation's waterways from combined
sewer overflows has been well documented (1, 2).  In addition to
pollution from normal domestic sewage and urban runoff
contaminants, combined sewer overflows also contain, in many cases,
significant quantities of industrial waste.  This can be evidenced by
the fact that approximately 40% of the volume of waste waters  currently
processed in municipal sewage treatment facilities are of industrial
origin (3).  Effective pollution control for an area or a waterbody
cannot be achieved without an adequate method or system for handling
the pollutional discharges which occur from combined sewer overflows.

       Recent emphasis has been placed upon developing and  evaluating
systems and treatment processes which will adequately cope with the
combined sewer overflow problem. It is immediately evident that no
matter what degree of advanced waste treatment is provided  at sewage
treatment facilities,  water quality levels cannot be  consistently
maintained without controlling the highly contaminated, high volume,
discharges which are experienced during combined sewer overflow
conditions.  Modern remedial measures generally follow three  avenues:
proper regulation of the sewer system to minimize overflow frequency
and volumes; storage to temporarily detain this high volume, short
duration discharge;  and treatment of combined sewer overflows.  This
study and report is concerned with evaluating a new method  for treating
combined sewer overflow.

       The nature of combined sewer overflow, that is, a highly
pollutional, high volume  discharge, requires a relatively high  rate
treatment process for economical  pollution control.  Deep bed, high
rate filtration, a newer development in the field  of industrial waste-
w,ater treatment,  has demonstrated favorable cost-efficiency factors
when dealing with high volume wastewater discharges, especially where
suspended solids comprise one of the principal contaminants (4, 5).
Thus, it was felt that such a process,  which currently has significant
applicability and usage in the steel industry, might provide  an effective
and efficient solution to the treatment of combined sewer overflows.

-------
       To evaluate the applicability and effectiveness of the high rate
filtration process in removing contaminants from combined sewer
overflows, a testing program was undertaken at Cleveland's Southerly
Wastewater Treatment Plant. The City of Cleveland ranks seventh in
the nation in total area served by combined sewers (44,000 acres), and
is fourth in  population served by combined sewer systems (1,000,000
persons) (2).  As can be expected, Cleveland has a very serious
problem of combined sewer overflows.

Scope oj Project

       The  development and demonstration project at Cleveland's
Southerly Wastewater Treatment Plant evaluated deep bed, high rate
dual media  filtration for treating the combined sewer  overflows
experienced at this sewage  treatment plant.  The project essentially
covered three areas: first, engineering and construction of a pilot plant;
second, testing the efficiency and effectiveness  of the high rate
filtration process in removing combined sewer overflow contaminants;
and lastly,  data evaluation  and design of representative  treatment units
with associated cost estimates.

       The  field testing, sampling and evaluation program was
conducted in 1970, and again in 1971.  The 1970 test work spanned
from July through November  and essentially established the feasibility
of the filtration concept and also the essentially components of the
proposed treatment system.  The 1971 field test work spanned from
May through August and was substantially comprised  of optimizing the
performance of the proposed system via the addition of various
polyelectrolytes and coagulants prior to filtration.

       Two additional tasks, not specifically related to combined sewer
overflow, were incorporated into the overall study.  The  first task was
comprised of a preliminary field test program evaluating deep bed,
high rate filtration as a treatment method for secondary sewage effluent
from activated sludge plants.  The second, somewhat unrelated project
task, included an evaluation of a suspended solids effluent monitoring
system.  Both of these project tasks are  described and reported in
independent sections contained in the appendices of this report.

The Cleveland Situation

       As indicated, the pilot test facility evaluating the applicability
of the high rate filtration process was located at the Southerly Waste-
water Treatment Plant, which receives flow from the Southerly Sewerage
                               10

-------
District of Cleveland.  The Southerly District,  as  shown in Figure 1,
consists of residential, commercial and industrial areas,  encompassing
roughly half of the metropolitan region, both in population as well
as land area.  This district also includes many of  the large industrial
plants located within the greater Cleveland area.  Based on preliminary
1970 Census data,  the Southerly District is estimated to have 600,000
people of the 1,300,000 residing in the Greater Cleveland vicinity.
The Southerly District covers approximately 62,000 acres.

        Generally speaking, the Southerly district  is served by a
combined sewer system and all discharges, including sanitary sewage,
industrial wastewater and urban runoff are conveyed by the system.
Considerable portions of the combined sewer system are believed to
have been built over fifty years  ago.  Most of the  new suburban
areas within the district are provided with separate sewer systems.
However, it is reported that numerous cross connections between
sanitary sewers and storm sewers do exist within  these suburban
communities.

        Precipitation in the study area averages between 30 and 36
inches a year.  The monthly average ranges from 1 to 6 inches, with
the greatest precipitation evidenced in the spring  months. It is
reported that the study area is subject to frequent low intensity rainfalls
which will account for most of the annual runoff in the area.

        The  combined sewer overflow problem in the  study vicinity is an
extremely complicated one. Based on available information, there are
over 600 overflow  structures within the district.  The normal dry weather
flow to the Southerly Wastewater Treatment Plant is  80  million gallons
per day, whereas the hydraulic capacity through the plant is in the range
of 160 million gallons  per day.  It is estimated that  the wet weather flow
in the study area is in the range of two to ten times the dry weather flow,
and causes  a substantial  discharge of combined sewer overflow to the
Cuyahoga River and to Lake Erie (6).

Essentials of High Rate Filtration

        The  history of water filtration began with the use  of slow sand
filters to clarify drinking  water.  These were beds of granular material,
arranged in various acreages, which were doused  with the water to be
filtered.  The  water was  collected after percolating through several
feet of the filter bed.  Usual rates of filtration were in the order of  0. 02
to 0.2 gpm/sq ft.   The development of the rapid sand filtration process
occurred before 1900.  This process requires the prior application of
                          11

-------
    IM
G>
C.
;U
m
                    WESTERLY WASTEWATER
                     TREATMENT PLANT
                                                  LY WASTEWATE
                                                TREATMENT PLANT
      SOUTHERLY WASTEWATER TREATMENT PLANT  LOCATION PLAN

-------
chemicals to effect coagulation. The water is then passed through
clarification tanks where most of the floe formed is settled out prior
to filtration.  These improved filters  provided good water at filtering
rates of 2 gallons per minute per square foot.  However,  of even
greater significance was the fact that they could be cleaned mechanically
without removing the media from the bed.  Much recent attention and
test work in potable water filtration has been given to the feasibility
of filtering at higher rates, up to 10 gallons  a minute per square
foot (7).

       The  general practice of industrial wastewater filtration first
emerged in Europe where the supply of water for industrial  purposes
became limited.  The industrial wastewater filters in Europe were
designed to operate in the general range of 6 to I'D gallons per minute
per square foot.  These units  were designed  to provide reliable treatment
for many years without any great maintenance effort.
       Ultra high rate filtration under study for the treatment of combined
sewer overflow, is similar to the industrial type filtration in
Europe except that two layers of media of different composition are
used (5).  Together, they form a filter bed that is much deeper than
used previously (7 feet or more).  By using dual  media, high capacity
filter bottoms and special backwashing facilities,  the rate of filtration
of wastewater has been increased greatly.

       One of the essential differences between a deep bed, dual media,
high rate filter and its counterpart for potable water treatment is that
the deep bed filter is designed to accept appreciable solids loadings,
on the order of many hundreds of milligrams per liter.  To be most
effective, filtration through media that are graded from coarse to fine in
the direction of filtration is desirable. A  single medium filter cannot
conform to this principle since backwashing of the bed automatically
grades the bed from coarse  to fine in the direction of washing; however,
the concept can be approached by using a  two layer bed.  A typical case
is the use of coarse anthracite particles on top of less coarse sand.
Since anthracite is less dense than sand,  it can be coarse and still
remain on top of the bed after the backwash operation. Another alternate
to achieve filtration through coarse to fine media would be an upflow
filter. But these units  have limitations in that they cannot accept high
filtration rates.
                             13

-------
        Over the past few decades, many theories have been promoted
to describe  the manner and mechanism by which suspended matter is
entrapped within a filter. Tchobanoglous (8) has categorized filter
removal mechanisms into nine areas, which include  straining,
sedimentation, inertial impaction,  interception, chemical adsorption,
physical adsorption,  adhesion and adhesion forces, coagulation-
flocculation, and biological growth.  Just how suspended matter is
intercepted  in depth rather than at the surface  of a high rate filter,
and which mechanism are principally involved, is not yet fully under-
stood.  However, it is presently surmised that due to the longer depth
of travel through the media, the mechanisms contributing to the removal
of suspended material within the filter have a greater change to be
effective  (9).

        The  principal parameters to be evaluated in selecting a high
rate filtration system are media size, media depth and filtration rate.
Since much  of the removal of solids from the water takes  place within
filter media, their structure and composition is of major
importance.  Too fine a media may produce a high quality effluent but
also may cause excessive head losses and extremely short filter runs.
On the other hand media that is too coarse may fail to produce the
desired clarity of the effluent.  Therefore, the selection  of media for
high rate filtration is made by pilot testing using various materials
in different  proportions and at different flow rates.  Depth of media
is limited by head loss and backwash considerations.  The deeper the
bed, the greater the head loss and the harder it is to clean.  On the
other hand,  the media should be of sufficient depth so as to be able to
retain the removed solids within the depth of the media for the duration
of filter run at the design rate without permitting a breakthrough. A
deeper bed also affords greater  opportunity for interplay of the various
forces which are generated within the filter bed.

        The  design filtration rate must be such that the effluent will be
of a desired quality without causing excessive head loss through the
filter, which in turn requires frequent backwashing.  At high filtration
rates, shear forces seem to have significant effect on solids retention
and removal in a high rate filter.  Recent experience  at a high rate
filtration facility treating industrial waste water seem to  reinforce this
theory,  as winter performance of the filtration facility (without chemicals)
was poorer than summer  performance, when water viscosities are
lower due to higher water temperatures (10).  Polyelectrolyte addition
was required during  cold water operating conditions (winter) to maintain
required effluent quality. The addition of polyelectrolyte, and/or
coagulants prior to filtration can have a. significant effect on process
efficiency.

                           14

-------
                         SECTION IV

                   PILOT PLANT FACILITIES
Process Units

       An overall schematic of the pilot plant is shown in Figure 2.
The major elements of the treatment system are a screening  facility
and a deep bed, high rate dual media filter.  As indicated on this
drawing, two storage tanks, 5000 gallons each, equipped with
mixers, were provided between the screen  and the filters.  The purpose
of these tanks was  to provide  sufficient combined sewer overflow
storage to allow extended filtration test runs.

       Briefly, the combined sewer overflow was lifted from the
Southerly Wastewater Treatment Plant junction chamber and  passed
through a drum  type screening unit.  The effluent from the screen
flowed by gravity into the two storage tanks.  Water from the storage
tanks was then pumped into the filtration test columns.

      Four filtration pilot columns were located in the test setup.
Three of the pilot columns were  6-inch diameter plexiglass  tubes,
while the fourth was one foot square.  All of the pilot columns were
of sufficient size to provide reliable removal data in regard  to the
filtration process.  The larger unit gave a better indication  of the effect
of backwashing on the filtration media, as "wall effects" were evidenced
in the smaller test units  during backwashing. Three chemical feeding
systems were included in the pilot plant installation.

       In addition, for the 1971 test work, a coagulant-testing apparatus
was incorporated into the pilot plant equipment.  This apparatus, as
shown in Figure 3,  was comprised of  six 3-inch diameter lucite filter .
columns with associated chemical feeding  equipment.  The coagulant
testing apparatus permitted  simultaneous comparison of the  effect and
efficiency of trying various  coagulants, and  polyelectrolytes, at
various dosages, to the filter influent to improve process performance.
Selected coagulants, polyelectrolytes, and dosages were then utilized
in the pilot columns, from which operational data was obtained
(length of run,  head loss, etc.).

       The flow volumes through each filtration column were controlled
by observing a  flow meter and regulating a valve on the effluent from
the filter.  Pressure gauges were located along the height of the pilot
filtration column to profile head losses throughout the filter depth. A

                              15

-------
C7)
C
50
m


ix>
              _c£:
         0000000000
                                ^
           	=€7
                                  1
  „*.*•

  •P"
  LJ>

  •Hr,
  v*
  * IW,
r*
7~
r*
r*
V*
r*
T*
V*
*r
T°
7UMCTIOM U4*Mftbl^
                                                        PUMUU. O^UUA
                                                      0O0O0000 O'-»
                                                      Vr UI »»
!


u C.





'"' '















-*M






r ?:
Uo_L _ _»
«•% 4= •
1


I
1 1 J
i f
LOO— 1?
f»-/l




I

T~

1




r*
V







1 * t^**. )^i M^ K^ M
¥ ! Tp OOOG
L^^i. 0 «^*- *• «< «6t «r-
rt-/_ _L .
J ii,
r .
>••« . . ,


(F
                                                             *1 ** 40-4
                                                     [u   r-tzj-
                                                           *MP .Wt^M





                                                      aacQHOAJcr ^yruithn^
Uri
                                                                              hEB.
                                                                        CHEMICAL FE£O
                                                                      <»UA»ox
                                                                        PWUO VA.LVC


                                                                        C.HCCX. VA.LVC
                                                                         VJHC. KCLtCF VAkUC


                                                                         . COWUCCTlOW
       HIGH  RATE  FILTRATION  PILOT   PLANT     FLOW  DIAGRAM

-------
31
CD
c
:o
m
              CHEMICAL
             FEED PUMPS'

             (I)-I CHANNEL
      CHEMICAL
      SOLUTION
      (9)-2000ml
      BEAKERS
              *h
                    -CXH
                  _u
FROM STORAGE TANK
                                 ,
-cxH
ir,
                                     IV
       HXh
                                                       HEAD TANK
                                    OVERFLOW
                         -1X3-
                          VI
         v
         \
           N\
         ION\
                               TUBE
                             CONNECTION
                             AND CHECK
                             VALVE (TYR) — ^

                           ANTHRACITE
                                                            SAND

                                                            GRAVEL
IHXH
                            TO SEWER
        COAGULANT TESTING  APPARATUS  SCHEMATIC   DIAGRAM

-------
small compressor was included at the test installation to provide a
source of air for backwashing the filter columns.  Backwash water was
obtained from the existing service water system at the Southerly Waste -
water Treatment Plant.

        Preliminary testing of secondary effluent was accomplished at
the pilot test setup,  as indicated on the schematic drawing.  Waste-
water was collected in a launder of a secondary sedimentation tank, and
pumped via hose to the test  site and to the filter columns.

        Major equipment at the pilot plant included the following:

        1.   Combined Sewer Overflow Pump -   self-priming
centrifugal pump,  manufactured by Barnes Manufacturing Company,
Model 105 C-E, with cast iron body and cast iron open type impeller
with six inch suction and six inch discharge.  The pump was
driven by a  1200 rpm, 10 HP TEFC motor,  operating at 230/460 volts.
The pump and motor were mounted integrally on a base plate.

        2.   Drum Screen - A continuous duty,  gravity flow,  self-
cleaning straining system manufactured by Zurn Industries,Inc.  The
heart of the  screen was a rotating drum type straining element enveloped
with replaceable wire mesh  plate (4'-0" diameter xl'-O" long). Rotating
on its horizontal axis, the straining elements  accepted incoming gravity
flow while partially submerged inside an open chamber.  A jet spray
washed off, debris trapped on the mesh as the drum turns, into an
elongated waste collector located inside the element but above the fluid
level.  The wastewater was  then discharged into a drainage line.

        3.   Pilot Filter Columns - Three six inch diameter
filter columns  - The filter columns were made of transparent plexi-
glass tubing having an outside diameter of seven inches and 3/8"
wall thickness. Each filter was seventeen feet high and consisted
of four sections.  The four  sections were connected by flanges using
1/4 inch bolts. Nine pressure taps, eighteen inches  apart were
provided along the column for measuring head  loss development during
filtration.  Filter media was supported by a plexiglass plate with a
plexiglass nozzle. Above the plate, an eighteen inch gravel layer was
provided to  support the filter media.  A rotameter and  valve were
installed at the filter discharge end for measuring and controlling the
rate of flow.  One filter column - supplied by De Laval Turbine, Inc.
The filter column was 12 inches by 12 inches  in cross section and had
a  nominal height of 18 feet.  Three sides  of the column were made of
steel plate and the front side was made of transparent plexiglass plate.
Nine  pressure taps,  twelve  inches  apart,  were provided along the


                             18

-------
column for pressure measurement.  Filtration rate was controlled by a
rotameter and gate valve on the filter effluent line.

       4.   Backwash Air Compressor - The air compressor was Model
A490K8 - 103-80, oil free type, manufactured by Corkem Pump Company.
The compressor was mounted on an 80 gallon receiver, ASME Code 200
psig working pressure. The unit was complete with pressure gage,
intake filter, hydrostatic relief valve and constant  speed unloaders.
The compressor was driven by a 2 HP drip proof  1750  rpm motor operating
at 230/460 volts.

       5.   Chemical Feed Systems - Each  system  consisting of a
metering pump, mechanical mixer and a chemical solution tank.  The
metering pumps were positive displacement, diaphragm type, with
plastic end.  The pumps were driven by 1/4 HP, single-phase capacitor-
start motors.  The chemical solution tanks were epoxy lined steel,
each having a capacity pf 55 gallons and equipped  with a cover.  The
mixers were driven by 1/4 HP totally enclosed motors.  The mixers
have rubber covered shafts and impellers. The pumps,  chemical
solution tanks and mixers were supplied by Wallace and Tiernan,Inc.

       6.   Steel Tanks

            a.   Combined Sewer Overflow Storage  Tanks

                Two 5,000 gallon steel tanks were provided for
storing incoming combined sewer overflows.  Each  tank was made of
carbon steel plate and equipped with overflow, outlet and drain
connections.  An agitator was  provided for preventing solids settlement
in the tank. The agitator was  driven by a 3 HP totally enclosed motor,
operating  on 230/460 volt,  3 phase, 60 cycle current.  The motor is
integrally mounted on a gear reduction unit  providing an agitator shaft
speed of 350 rpm. The agitator was manufactured by Lightnin Mixing
Equipment Company.  The two  tanks had a total  capacity of 10,000
gallons providing approximately  7 and 4 hours detention time at 16 gpm/sq ft
and 24 gpm/sq ft flux rate, respectively, with the  four filter columns
in operation.

            b.   Backwash Effluent Storage  Tank

                One 1,000 gallon steel tank  was used as the filter
backwash effluent storage tank.'  The tank was made  of carbon steel plate
and equipped with outlet and drain connections.
                             19

-------
        7.   Coagulant - Testing Apparatus

            a.  Head Tank

                To distribute flow to the six filter columns - an
eighteen inch diameter three foot long, transparent plexi-
glass tube was used as filter influent head tank.  Overflow
nozzles were equipped to provide a constant head for filter influent
flow.

            b.  Filter Columns

                Six filter columns, made of three-inch diameter
transparent plexiglass tubing, were installed at the pilot plant site.
Each filter column was eighteen feet high and consisted of three
sections.  The three sections were connected by two Victualic
couplings.

            c.  Chemical Feed System

                 Three peristalic pumps  were installed.  Two
 units provide four channels  each and one unit had one channeL
The pumps were capable of feeding nine  different  chemicals at the
same time.

        8.   Secondary Effluent Pump - A positive  displacement  self-
priming pump was used for delivering secondary effluent to filtration
testing site.  The pump was manufactured by Moyno Pump Division,
Robbins and Myers,Inc., Frame SWG 8 - Type CDQ.  The unit was
mounted on structural steel "L" type base plate and driven by "V"
belts and pulleys covered by suitable belt guard (450 rpm).  The pump
was driven by a 3 HP TEFC motor, operating on 3  phase,  60 cycles,
230/460 volt current.

Test Site
        The pilot plant for testing the applicability of high rate filtration
 for the treatment of combined sewer overflows was located at the Screen
 Building of the Southerly Wastewater Treatment Plant.  This  Plant
 utilizes the activated sludge process for the treatment  of sanitary and
 industrial waste flows from the Cleveland vicinity.  The nature of the
 plant waste is somewhat unique in that the industrial contribution is
 very large, as evidenced by the low BOD/COD ratio of approximately 0.3.
 The dry weather flow to  the plant can, therefore,  be described as
                              20

-------
representative of an urban area with a heavy industralize.d concentration.

       The average dry weather flow to the Southerly Plant is in the order
of 80 million gallons per day.  Under storm conditions,  the plant can
accept 160 MGD through its primary facilities. The Southerly Wastewater
Treatment Plant effects approximately 87 percent removal of suspended
solids and 90 percent removal of biochemical  oxygen demand.  Plant
effluent quality levels are generally in the range of 26 mg/1 suspended
solids and 16 mg/1  biochemical oxygen demand, as shown in
Table 1.

       The pilot plant influent pump,  screening facility, and storage
tanks were located  outdoors adjacent to the Screening Building,  as
shown in  Figure 4.  The filtration test columns, associated backwashing
and chemical feed equipment, coagulant-testing apparatus  and a small
laboratory and storage room, were located inside the Screen Building.
Figure 5 shows the  location of the pilot plant inside the Southerly Waste-
water Treatment Plant.
                               21

-------
                                                  Table 1


                           SOUTHERLY WASTEWATER TREATMENT PLANT EFFLUENT QUALITY*
                                 CLEVELAND, OHIO         (APRIL 1969 - FEBRUARY 1970)
                            Suspended Solids
B.O.D.
DO
to

Month
April
May
June
July
August
September
October
November
December
January
February
Plant
Effluent
Average Minimum
20
20
21
10
15
25
33
27
40
37
44
4
2
7
3
2
2
2
2
3
2
2
(mg/1)
Maximum^
44
62
59
34
32
91
130
61
97
104
100
Removal
Plant
Effluent
(%) Average Minimum
86
88
90
95
94
84
85
85
85
82
80
16
16
12
10
13
17
12
16
15
20
28
2
7
5
7
7
7
4
5
7
10
13
(mg/1)
Maximum
26
25
19
16
20
30
20
24
26
30
55
Removal
&)
84
83
92
92
90
90
93
89
90
87
80
                             * Data from Southerly Waste-water Treatment Plant Process Department

-------
 PILOT PLANT
 PIPING
i MIXER
BACKWASH
TANK
                              6 
-------
K
                  JLIflCTION CHAMBER
                   (OVERFLOW STRUCTURE)
          o
          z
          o
          o
          V)
          V)
                                I I
                                i i
                                ft
                          COMMINUTOR
                           8 DETRITOR
                            BUILDING
                     '/A
                  GRIT
                CHAMBERS
I I
                 FLOW
                METER
                      /\
                         l\
                         II

                         ill
                                                  HIGH- RATE
                                                  FILTRATION
                                                 I EQUIPMENT
                                                   SITE
                   PRIMARY
                                      SETTLING
                    TANKS
                                               HI
          TO CANAL
 FILTRATION   PILOT  PLANT    LOCATION   PLAN
                                             FIGURE  5
                       24

-------
                          SECTION V

                       TESTING PROGRAM

Parameters

       Two distinct types of test parameters were utilized and
evaluated during this study.  The first type  of parameter can be called
or described as design parameters, as they  relate to the major
features and unit sizes of any proposed treatment system.  The second
type can be described as water quality parameters, which are
essentially contaminant levels in and out of the treatment process.

       The two major process units or equipment units in the proposed
treatment system are the drum screen and the deep bed, high rate
filter.  Construction of a full scale treatment plant employing the
process sequence under study would require design parameters for the
screen and for the filtration process.   The  major criteria for the
screen are screen type, screen mesh opening and hydraulic loading.

       Numerous studies have been performed  on various screen types
and screen mesh openings to evaluate their  efficiency in reducing
combined sewer overflow pollutants.  The intention and major
emphasis of this program was not to determine  the optimum removal
characteristics that can be obtained from a  particular screen, but to
select a  screen of sufficient durability and  with sufficient removal
properties that would permit the filtration process to operate in an
efficient and effective manner. Thus, in selecting and operating
the screening facility, Hydrotechnic relied  to a great extent on past
experience and minimized the number of  variables that were changed
throughout the test program.

       The filtration system, which is the heart of the overall process
sequence, can be characterized and described  by the following
parameters:

       Media composition                  Length of filter run
       Media depth                        Head loss
       Filtration rate                       Backwash water volume
       Coagulant addition                  Backwash procedure

       A  definition of these elements allows the construction of a full
scale facility.
                              25

-------
       Water quality parameters or analyses utilized after agreement
with the EPA Project Officer,  are those normally associated with
combined sewer overflows.  Principal emphasis was given to the
following analyses:

           Total Suspended Solids
           Settleable  Solids
           Biochemical Oxygen Demand
           Total Phosphate
           Chemical Oxygen Demand

       Other water quality analyses were also performed, both to
provide a detailed gravity profile of the combined sewer overflow,
and also to provide information as to process performance on a wide
range of wastewater contaminants.  Table 2 is a complete listing
of all water quality analyses utilized  (11,  12),

       Total organic carbon analyses were performed on filter influent
and effluent samples after an automatic analyzer was installed by
Hydrotechnic and EPA at the Southerly Wastewater Treatment Plant.
Turbidity, settleable solids and temperature were determined at the
test site.  The  bulk  of the laboratory analyses were performed by local
commercial laboratories in Cleveland.

       These water  quality parameters can be used to determine the
effectiveness of the treatment process under study in reducing combined
sewer overflow contaminants.  The major water quality parameter for
determining the effectiveness of the treatment process, since the
proposed filtration process is essentially a  solids removal  process, is
suspended  solids.  Insoluble BOD, simultaneously removed along
with suspended solids, and soluble (ionizable) phosphates, rendered
removable by the addition of coagulants, are also significant water
quality parameters.

Program Scope

       The testing program at the Southerly Wastewater Treatment Plant
for combined sewage storm overflows can be viewed as three separate
operations.  The first is the characterization of the combined sewer
overflows. This consisted of sampling combined  sewer overflows
and analyzing samples collected for appropriate water quality
parameters.
                             26

-------
                           Table  2
                    WATER QUALITY ANALYSES
       Analysis
        Method Used
Solids

  Suspended Solids (SS)         Filtered through glass fiber filter (pore
                               size 0.8 micron)  and dried at 103-105°C.
  Volatile Suspended Solids (VSS) Filtered and ignited at 550°C.
  Total Solids (TS)              Evaporated to dryness at 103-105°C.
  Total Volatile Solids  (TVS)     Evaporated and ignited at 550°C.
  Settleable Solids (Set.S.)     Imhoff cone,  by ml/1.
Organic

  Biochemical Oxygen Demand
   (BOD).
  Chemical Oxygen Demand
   (COD) .
  Total Organic Carbon (TOC).

Nutritional

  Total Phosphate (TPO4)
  Soluble  Phosphate (Sol.PO4)
  Total Kjeldahl  Nitrogen (TKN)

jBa c ter ipl og ica 1

  Total Coliforms
  Fecal Coliforms
  Fecal Streptococcus

Other
  Oil and Grease
  PH
  Temperature
  Turbidity
Unblended, diluted and incubated for
5 days at 20°C.
Oxidized by K2Cr2O7 solution.

Dow-Beckman Carbonaceous Analyzer.
       hydrolysis and colorimetry.
Filtration, hydrolysis and colorimetry.
Kjeldahl digestion.
Membrane Filter (pore size 0.45 micron).
Membrane Filter (pore size 0.45 micron).
Membrane Filter (pore size 0.45 micron).
Liquid-liquid extraction.
Electrometric Measurement.
Thermometer.
Hach Colorimeter, Range 0-500 JTU
(Jackson Turbidity Units - Formazin
Standard).
                              27

-------
       The second and third operation involved the proposed treatment
process and was essentially comprised of two individual treatment
components,  a screening facility and  the filtration facility.  Each of
these can be viewed as a separate study, although they are, of
necessity, interrelated in terms  of the overall treatment process and
treatment efficiency.

Characterization of'Combined Sewer Overflow

       Characterization of combined sewer overflows occurring at the
influent junction chamber of the  Southerly Wastewater Treatment Plant
was  performed for fifteen storms, thirteen occurring during  1970
and two occurring during 1971.   Figure 6 shows the location of
sampling points for the test project at Cleveland.  Sampling point #1 is
the combined sewer overflow characteristic sampling point.  Samples
were collected manually.

       A test was initiated, and combined sewer overflow characteriza-
tion  sampling would begin after an observation of rainfall or reported
rainfall within the Cleveland area.  The plant flow meter would be scru-
tinized, and when  the flow rose  above approximately 100-110 MGD
(normal dry weather flow of approximately 80  MGD) sampling would  com-
mence. Samples were collected at 5 minute intervals for the first 30
minutes, and at 30  minute intervals for the next  90 minutes, and at  one
hour intervals for the duration of the combined sewage storm overflow.
This was generally  determined by monitoring the Southerly Wastewater
Treatment Plant influent flow meter, and  when the plant  flow dropped
below approximately 90-100 MGD, it  was assumed that  the combined
sewer overflow conditions had stopped.

Screening

       The screen type used for almost the entire duration of the  test
work at Cleveland was a mesh type screen.  All  system  data and filtra-
tion  data was obtained utilizing  a mesh screen.

       The mesh screen tested included:  No. 3, No. 20 and No. 40
mesh screen.  The characteristics of the three  screen meshes tested
are:
                             28

-------
C-O
ID
             STORM OVERFLOW

                  PUMP
          JUNCTION CHAMBER
                                               SCREEN
                                                 £—"
                                            FILTER  INFLUENT
                                               PUMPS
                                                                       -».To F-3 a F-4
                       BACKWASH WASTEWATER

                           HOLDING TANK
                                                Vo^
                                            n  °^0°
                                            ML
                                                                      V)
                                               FILTER
                                     SCREEN CHANNEL
     CD
     C
     XJ
     m
SAMPLING POINT LOCATION SCHEMATIC DIAGRAM

-------
Mesh Screen                        Tyler Screen
Designation     Screen Opening     Scale Equivalent      Open Area
               (microns) (inches)       (mesh)	( % )

   No.  3        6350    0.250            3                57.6
   No. 20         841    0.0331          20                43.6
   No. 40         420    0.0165          35                43.6

       At the end of the 1971 test work, a series  of tests were per-
formed on a slotted  type screen to see if it could provide the necessary
removals to permit an efficient operation.  The intention and reason for
evaluating the slotted type screen was because of its sturdy construc-
tion.  This testing was accomplished simply by replacing the mesh
element on the rotating drum screen with panels of slotted screen which
were furnished by the Johnson Division of  UOP. Two slot screen types
were tested, as follows:

                                Tyler Screen
          Slot Opening        Scale Equivalent         Open Area
          (microns)(inches)          (mesh)                ( % }
            200     .008               65                 12
            400     .016               35                 21.1

       Referring to Figure 6, sampling  points #2 and #3 were assigned
to the screening unit.  Influent and effluent samples were collected at
30 minute intervals for the first 2 hours of the combined sewer overflow
and at one hour intervals  thereafter, until the duration of the combined
sewer overflow had ended.

       The effluent  from the screening  unit was directed to two 5,000
gallon storage tanks,.which served as storage reservoirs for conducting
filtration tests.

Deep Bed,  High Rate Filtration

       The testing program evaluating  the filtration components of the
proposed system was conducted primarily in two phases.  First, evalua-
tion and selection of system media and filtration rates, and secondly,
optimization of the filtration process via coagulants and polyelectrolyte
addition prior  to filtration.

       Filtration media evaluated included:  four or five feet of
anthracite  over three feet of sand.  The characteristics of the media
are indicated as follows:
                               30

-------
  	Media             Effective Size      Uniformity Coefficient

  No.  4 Anthracite              7.15mm.                1.42
  No.  3 Anthracite              4.0   mm.                1.5
  No.  2 Anthracite              1.78mm.                1.63
  No.  612 Sand                2.0   mm.                1.32
  No.  48 Sand                3.15mm.                1.27

       Media selection was accomplished in the pilot test apparatus (see
 Figure 6).  Referring to this figure, the two key points in the filtration
system were sampling points #4  and #8.  Sampling point
#4 was at the influent of the filter columns and sampling point #8 was
the filtration column effluent.  Sampling points # 5,  6  and 7 were inter-
mediate sampling points along the filtration media depth.  It was an-
ticipated that data obtained from samples at these levels would give an
in-depth picture of which areas  of the filter performed  the major portion
of the  suspended solids removal.  Influent and effluent samples
(points #4 and #8) were taken at thirty minutes,  one  hour, and at hourly
intervals thereafter.

       Sampling point #9 was  at the backwash effluent.  Samples of
backwash effluent provided information as to the nature of the backwash
flow, both on an instantaneous and composite basis.  Backwash efflu-
ent samples, when viewed in conjunction  with a particular backwash
procedure,  can be used as a guide to the effectiveness of filter  clean-
ing.

       The filtration columns were run from 6 to 12 hours, depending
upon head loss and effluent quality.   The  storage tanks provided
sufficient capacity for extended  filter runs.

       As indicated in the previous section, the samples collected
during the testing program were  analyzed for appropriate wastewater
contaminants.  Head loss measurements were taken at each filter
column by reading the various pressure gauges located along the depth
of the  filtration media at one hour intervals, or more frequently.  These
readings can be used to identify and define the energy expended by the
flow in overcoming friction during the filtration run.

       The filter columns were backwashed by using low pressure air
followed by water.  Initially,  after the filtration run had terminated, the
columns were backwashed by low pressure air at approximately  15 scfm
per sq ft  for about 2 minutes.  The air was then turned off, and water
introduced at a rate of 25 to 75 gpm per square foot, for 5 to
10 minutes.   A rate of 30 gpm/sq  ft appears to be sufficient
                               31

-------
for backwashing.  Samples of the backwash effluent (sampling point #9)
were collected.  Both composite and grab sampling methods have been
utilized.  Composite samples give an indication of the total amount of
material removed in the filter backwash, and grab samples define the
pattern and the peaks of backwash solids concentration.

        For the coagulant-testing apparatus  which was utilized to
select optimum coagulants and  polyelectrolytes and appropriate dosages to
be applied prior to filtration, samples were  collected at hourly intervals
for three hours.  These samples were composited over a ten-minute in-
terval at each hour.  A typical test run would be applying six different
polyelectrolytes at the same dosage  to each of the various filter columns
(each column operated at the same filtration rate).  Based on effluent
quality data, the efficiency of one polyelectrolyte versus another could
be determined, based  on suspended  solids reductions.

       When dealing with additions  of alum, lime, and ferric chloride,
effluent samples were  also analyzed for total and dissolved phosphates
in addition to  suspended solids,  since one of the functions of adding
these coagulants was to effectuate phosphate reductions in the process.
Optimum combinations of chemicals determined from the coagulant test
apparatus were then utilized for full  scale pilot runs in the 6-inch
column. A total of 53  polyelectrolytes were evaluated for enhancing
suspended solids removals,  including 9 which were of the potable water
grade, that is, acceptable for potable water usage. A list of polyelec-
trolytes evaluated under this test work is contained in Table 3.

In-line Suspended Solids  Monitor

        An in-situ meter recorder device for rapidly measuring total sus-
pended solids content in the main flow  stream, as furnished by
Biospherics, Inc., was utilized in the combined  sewer overflow filtra-
tion pilot plant works.  Figure  7  shows  the installation of the Biospherics
Model 53 suspended solids monitor.

        According to the manufacturer, this instrument operates (13) on
the principles of measurement by both light transmittance and light
scattering simultaneously.  The operation is step-wise on a 15 second
cycle, in which the  photocell windows  are wiped clean during each
cycle.  When the glass tube is filled with clear water,  the transmittance
cell receives the maximum amount of light and the scatter cell is in com-
plete darkness. When suspended solids are added to the liquid, the
transmittance  photocell will receive less light due to shadows on its
sensing surface and the scatter photocell will receive light due to light
reflection.  The response of each cell is non-linear and,  therefore, not
                              32

-------
                                              Table 3
                                        LIST OF POLYELECTROLYTES
co
CO
Chemical Indust.ies

Atlas Chemical Industries,Inc.
Wilmington, Delaware 19899 (Atlasep)

American Cyanamid Company
Wayne, New Jersey 07470 (Magnifloc)

Calgon Corporation(Coagulant Aid)
Pittsburgh, Pennsylvania 15230

The Dow Chemical Company
Midland, Michigan 48640(Purifloc)

Gamlen Chemical Company (Gamafla)
East Paterson, New Jersey 07407

Hercules Incorporated (Hercofloc)
Hopewell, Virginia 23860

Nalco Chemical Company (Nalcolyte)
Chicago, Illinois 60601
                                                         Type of Polyelectrolyte s
                                                Cationic
                    Nonionic
                      Anionic
105C

521C*,560C
570C*,571C*

227, 228


C-31*, C-41


NC772
                                              810, 814.2
                                              828.1
IN

900N,905N
985N*, 990N*

18(*) (**)
                                                               671
1A1,2A2,3A3,4A4,5A5

835A,836A,860A*
865A

235, 240
25**

A-23*
                  NA710


                  816, 822, 836


                  672, 673, 675H

-------
                                                Table 3

                                                (Continued)
co
                                         LIST OF POLYELECTROLYTES
Chemical Industries

Narvon Mining and Chemical
         Company (Zeta Floe)
Lancaster, Pennsylvania 17604

Reichhold Chemicals,Inc.
Tuscaloosa,Alabama 35401 (Aqua-Rid)

Stein-Hall Chemical (Polyhall)
New York, New York 10016

Swift and Company
Oak Brook, Illinois 60521
                                                          Type of  Polyelectrolytes
                                                 Cationic
                                               C,**  CX**
                                               MRL 91
   Nonionic
WN**
                                               49-700,  49-701  49-704
                                               49-710,  49-711
M402
     Anionic
WA**
295A
                                                                                 X-400
               *
               **
              Approved by EPA For Water Treatment (April 1971)
              With Bentonite Clay

-------
            SUSPENDED  SOLIDS SENSOR
           CONTROL UNIT AND RECORDER
SUSPENDED SOLIDS  MONITOR INSTALLATION
                                  FIGURE 7
                    35

-------
proportional to suspended solids concentration.  However, the result
obtained by dividing the response of the scatter photocell by that of the
transmittance photocell is linear. This division is performed electroni-
cally and the linearity is achieved by carefully positioning the photo-
cells in addition to the electronic division of their signals.  Liquid
color or light bulb intensity are claimed not to cause errors.

       A relationship between the suspended solids monitor readings
and laboratory analyzed suspended solids results  is presented in
Figure 8.  It was found that the readings from the  monitor gave a
reasonable correlation in measuring the suspended solids for concen-
tration range between 30 and 240 mg/1.  Based on a limited verifi-
cation procedure, a great scattering of readings occurred in the lower
range (0 to 30 mg/1)  of  suspended solids concentrations which may have
been caused by deviations in the laboratory bench test;  possible errors
in bench test procedure such as sample preparations; probability of
capturing the same slug analyzed by the suspended solids monitor for
direct comparison with laboratory analysis and the variation of light
absorbing or reflecting characteristics of the suspended solids in the
lower concentration range.  However,  an instrument of this kind showed
a promising potential application for continuous monitoring of suspended
solids level in the filter influent or effluent.

       In order to establish an accurate correlation between the
suspended solids value and the monitor reading, a longer term investi-
gation procedure should be more carefully set up.   Consistent  and
reproducible results  may thus be developed.  Then, the  instrument could
enhance the filtration plant operation by continuously recording the
total suspended solids  content of wastewater for the  control of coagulant
and flocculant feed rate combinations or flocculant feed alone, and by
continuous effluent monitoring for optimizing filter performance and
filtrate quality by furnishing automatic  positive control.
                              36

-------
    280
    240
Q
a:
ro
m

_i
UJ
    200
to
2 ^
O
S o
  2
CO
9co
 I o

Sg

si
QL
CO

CO
          A = 15 MIN. COMPOSITE SAMPLE

          • = GRAB  SAMPLE
    40
     0
                  80     120     160    200

                TOTAL SUSPENDED SOLIDS

               (LABORATORY RESULTS) - mg/l
                                          240
    SUSPENDED SOLIDS  MONITOR  READING

          Vs  LABORATORY  RESULTS-
                                      FIGURE 8
                     37

-------
                         SECTION VI

         CHARACTERIZATION OF COMBINED SEWER OVERFLOWS
       Combined sewer overflow characterization data (sampling point
#1} was collected for thirteen storms during 1970 and for two
storms during 1971.  The key parameters for each  storm are plotted in
Figures Al thru A15 in the Appendix.  Hourly rainfall data (14) is also
indicated on these plots.  The rain gage is located at Cleveland's
Hopkins Airport, at the western extremity of the Southerly Sewerage
District, approximately ten miles west of the  Southerly Wastewater
Treatment Plant.  These plots show the effect of time, in a storm
sequence, on the magnitude of various wastewater pollutants.

       Table 4 contains average data, including maximum and
minimum values, for combined sewer overflow sampling in 1970. Mean
suspended solids levels were 234 mg/1, with a range from 28 to 1560-
702 mg/1.  Biochemical oxygen  demand levels average 92 mg/1, with
values ranging from 16 to 580 mg/1.  Chemical oxygen demand
levels averaged 308 mg/1, with values ranging from 57 to 711 mg/1.

       As is shown on the combined  sewer overflow curves in Appendix A,
concentration peaks, generally  referred to as the "first flush" effect,
were evidenced on storms Nos.  1, 2, 10, 11 and 12, or during five out
of the thirteen combined sewage storm overflows sampled. The most
pronounced concentration peak occurred during storm No. 1, when in
excess of one inch of rainfall fell within one hour.

       The majority of the  1970 combined sewer overflow sampling
was accomplished during the months  of August,  September and October.
In order to profile combined sewer overflow characteristics in the
earlier part of the rainy season, two  storms were sampled during 1971,
one in early May and one in early June. Average results of these spring
storms are presented in Table 5 and individual storm plots presented
in Figures A-14 and A-15 in the Appendix.  The  data contained in Table 5
(spring storm overflows) indicates that the spring storms produce
an overflow of a more highly pollutional nature, as BOD, COD, total
suspended solids and settleable solids values were substantially higher
than those experienced during the remainder of the summer and fall
periods.  As indicated in Table  5, for the spring storms, mean
suspended solids levels were 462 mg/1, mean BOD was 171 mg/1 and
mean COD was 462 mg/1.  Both of the spring storms sampled had
pronounced "first flush" concentration peaks, as evidenced from
Figures A-14 and A-15 in the appendices.

                             39

-------
                                       Table  4
                      CHARACTERISTICS OF COMBINED SEWER OVERFLOWS
                               (late July - early November, 1970)
Analysis

PH
Temperature (°F)
Turbidity (J.T.U.)
Dissolved Oxygen (mg/1)
BOD (mg/1)
COD (mg/1)
TOO  (mg/1)
Total Solids (mg/1)
Suspended Solids (mg/1)
Settleable Solids (ml./I)
Fecal Coliforms
(#x 106/100 mi.)
No. of
Observations
195
137
195
78
197
198
41
177
• 193
195
197
Standard
Mean Deviation
7.0
69
231
3.40
92
308
126
590
234
5.26
4.55*
0.31

125
2.28
49
143
65
150
135
3.02
5.72
Minimum
6.4
60
55
0.98
16
57
30
264
28
0.2
0.09
Maximum
8.
76
640
9.
580
711
280
1238
1560
19
49
6


3







                              * Median

-------
                                       Table 5
                     CHARACTERISTICS OF COMBINED SEWER OVERFLOWS
                               (May  - early June,  1971)
Analysis
PH
Temperature (°F)
Turbidity (J.T.U.)
Dissolved Oxygen (mg/L)
BOD (mg/1)
COD (mg/L)
TOG (mg/1)
Total Solids (mg/1)
Suspended Solids (mg/L)
Settleable Solids (ml/1)
Fecal Coliforms
x (106/100 ml)
Total Coliforms
x (106/LOO ml)
Fecal Strep
x (10V100 ml)
No. of
Observations
16
25
25
24
25
25
25
25
16

Standard
Mean Deviation
6.76
58
373
171
462
814
411
6.98
0.53*
0.273
5.42
196
42.4
145.2
197
178
4.68
.462

Minimum
6.50
50
110
85
196
532
177
1.5
.06


Maximum
7.
64
850
245
759
1275
976
14
2.
10







00
25
13
27.36*
 0.66*
13.15
 0.224
7.0
0.11
62.0
 1.10
                         * Median

-------
       The Southerly Wastewater Treatment Plant serves a very large
drainage area and this  is probably a factor in minimizing "first flush"
effects due to storms occurring in  one portion of the drainage area.
Also, the travel time due to the long sewer runs in this drainage area
has limiting effect.  Another probable factor is  that most of the 1970
data was collected during late summer and fall  periods, when lower
intensity storms are  more likely to occur.  Finally,  it is  also possible
that the sampling procedure missed some concentration peaks.

       Correlating rainfall data and time of combined sewer overflow
at the Southerly Wastewater Treatment Plant is  difficult due to the
size of the Southerly Sewerage District.  Since the  rain gage is located
over ten miles away  from the Southerly Sewage  Treatment Plant, it
is possible that a heavy downpour adjacent to the plant would have a
pronounced effect on combined sewer overflow, without showing a
corresponding effect on rainfall records, or visa-versa.  For example,
the concentration peak in storm No. 1 occurred approximately two hours
after significant rainfall (at rain gage) while the peak in storm No. 12
occurs almost simultaneously with significant rainfall (at rain gage).

       For comparative purposes,  dry weather flow occurring at the
Southerly Wastewater Treatment Plant was  profiled for a  thirty six
hour period (October 10 and 11, 1970).  Sampling was performed at one
hour intervals.  Hydrotechnic Corporation and the EPA Project Officer
decided that  a  "round the clock" profiling of normal dry weather flow
would be beneficial, especially when used for comparative purposes
with storm water overflows.  As shown in Table 6,  mean dry
weather suspended solids were 192 mg/1, with values ranging from
64 to 249 mg/1;  mean BOD was 130 mg/1,  with values ranging from
60 to 185 mg/1;  and  mean COD was 383 mg/1,  with  values ranging
from 164 to 543  mg/1.  As previously mentioned, the BOD/COD
ratio of the wastewater at the Southerly Wastewater Treatment Plant
(approximately 0.3)  is  rather low for a municipal sewage, and is  due to
the heavy concentration and amounts of industrial wastewater discharges
into the system.

       Comparing average combined sewer overflow levels (Table 4)
and dry weather flow contaminant levels (Table 6) for the 1970
sampling period, suspended solids are approximately 25 percent higher
than normal dry weather flow levels; combined  sewer overflow BOD
levels are approximately 70 percent of those experienced during the  dry
weather flow; and COD levels are  comparable for both wastewater
discharges - 383 mg/1 for dry weather flow versus 308 mg/1 for
combined sewer overflow conditions.  The median fecal coliform level
for the dry weather flow at the Southerly Wastewater Treatment Plant was
                               42

-------
                                                Table  6
Co
                              CHARACTERISTICS OF DRY WEATHER SEWAGE FLOW
                                 ( SOUTHERLY WASTEWATER TREATMENT PLANT)
                                  ( 9 AM - 10/28/70 to 3 PM  - 10/29/70)
         Analysis
PH
Temperature (°F)
Turbidity (J.T.U.)
Dissolved Oxygen (mg/1)
BOD (mg/1)
COD (mg/1)
TOG (mg/1)
Total Solids (mg/1)
Suspended Solids  (mg/1)
Settleable Solids (ml/1)
Fecal Coliforms
(#x 106/100 ml.)
   No. of
Observations

    18
    18
    18
    18
    18
    18
    18
    18
    18
    18
    18
                                           Mean
                                                        7.6
Standard
Deviation

    0.155
Minimum
    7.3
Maximum
63
167
2.35
130
383
116
634
192
5.3
15.7*
1.
60
1.
42
112
37
95
68
2.
13.
0

1





5
0
62
81
0.82
60
164
65
441
64
0.5
5.0
65
266
4.5
185
543
1 74
820
249
9.5
62.0
                                   * Median

-------
15.7 x 10  colonies per 100 ml.  The median level for the combined sewer
overflows at the Southerly Plant was approximately 30 percent of this
value.

       For the spring storm period (May-early June), based on data
collected in 1971 (see Table 4),  it appears that combined sewer overflows
at the Southerly Wastewater Treatment Plant are more polluted than raw
sewage (in terms of total suspended solids, BOD, COD). This
comparison underlines the importance of adequately handling or treating
combined sewer  overflows.

       Figure 9  profiles dry weather sewage flow and combined sewer
overflow characteristics of the Southerly Was tewater Treatment Plant for
a consecutive period.  Dry weather sampling (plant influent) was
commenced at 9  a.m. on October 10/1970 and continued until 4 p.m. on
October 29, 1970,  when combined  sewer overflow sampling  procedures
were initiated.  Sampling was terminated at 2 p.m. on October 30, 1970.
This plot shows  the "first flush" concentration peak occurring between
4 p.m. and 5 p.m. (1600 and 1700 hours), depending upon the particular
water quality contaminant observed.  The hydraulic peak or maximum
combined sewer  overflow discharge, occurred at 6 p.m.  (1800 hours).
Although the plant  inflow cannot be directly related to the quantity of the
combined sewer  overflow occurring at the plant  bypass, maximum plant
flow coincides with maximum combined sewer overflow, due to the nature
of the upstream overflow structure. As mentioned previously, rainfall
data and combined sewer overflow  characteristics cannot be directly
related, due to the size of the drainage area and the distance of the rain
gage from the Southerly Wastewater Treatment Plant.

       The more significant characteristics of the combined sewer
overflow at Southerly can be summarized as follows:

       a.  A total of about 52 overflows a year can be expected.  Most
of them have a duration of 5 to 6 hours.  The majority of overflows occur
from storm having a rainfall intensity of between 0.5 and .30 inches/hr
(15).

       b.   The  concentration of suspended solids generally ranged
between 100 and 400 mg/1.  The maximum was 1560 mg/1.

       c.   The  concentrations  of BOD generally ranged between 50 and
200 mg/1.  The maximum was 580 mg/1.
                               44

-------
en
     §p oooopooooogooooooooooooooooo
     o ooooooooooOoooooooOOoooooooo
    _§MwgK§6a2g|«;o|H§g§gii^aioioScOr2SK
                                                                     O O O O O •
                                                                     S 6 - N ki ;
                                         TIME (hours)
100




3 4


3 C
. J

















C
. f


1 s


\ '<


1 J


1 1


h


? i


1 1


i s


? i


» i


3 C
? !


| 5


} \


} ?


' C


1 §


> C
i C


> C
I 1


> C
1 f


:> C
? !


3 C
> C


> C
C


' <


3 C
? f
*-*•

n
x--

| i


; ^


J C
I i


J i


| S


9 C
? !
— *.

3 C
; <


3 «


5 C
2 £


) C
i I


? S


1 f


! f


; f


5 5
Q


|J


? j


J S


> C
> . J


| 1


l§
                                         TIME (hours)
       1200
       400
       200
5600
-500
3400
-300
"200
5 100
         £
                      [.	J	J „_

                     TURBIDITYj
                                SUSPENDED
                            rS£S
              = s
§ §
S iQ
O O O O C?
P P P P P

S9 — w w «
                                 OO
                                 oo
                                 n «
                            OO
                            oo
                            w Ii
O O O o O
 §p P P P P
 O O — pj j*J
                                          R P
                                          in to
                                         TIME (hours)
                                              j£ n to
O O O o

SII§
                                                       0 0 O
                                                       O O O
                                         TIME (hours)
Z!
CD
C

m

CD
                  SOUTHERLY  WASTEWATER  TREATMENT PLANT
               DRY AND  WET  WEATHER   FLOW  CHARACTERISTICS
                       10/28-30/70'
                             PRECIPITATION .37  INCHES

-------
       d.  The concentration of suspended solids generally reached its
maximum with 1/2 hours after the beginning of the combined sewer
overflow.

       e.  In most cases, within 3 to 4 1/2 hours the concentration of
suspended solids in the combined sewer overflow dropped to less
tiietii 150 rag/1.

       f.  Suspended solids levels are higher than those in dry
weather sewage.

       g.  The concentrations of BOD were generally lower than those
in the dry weather sewage except for storms occurring in the spring.
BOD levels were highest in the earlier phases of the combined sewer
overflow.
                          46

-------
                               SECTION VII

                            SCREENING RESULTS

System Testing - Wire Mesh Screen

      The function of the screen in the overall treatment system tested
at the Southerly Wastewater Treatment Plant was to remove coarser
material  (fibrous type,, etc.) that would impede the  filtration operation.
It was felt that the major process unit in the proposed system would be
the deep bed high rate filters.  The screen facility was  operated at a
hydraulic loading (thruput)  of 100 gallons per minute per square foot for
the duration of the pilot testing of screening-filtration.  This level was
set after a review of previous screening tests performed by others.

      Testing accomplished during the first three storms utilized a No.3
mesh screen (equivalent to Tyler Screen scale 3 mesh with 6350 micron
or 1/4 inch openings) ahead of the filter columns.   The  major function of
the testing performed in the early stages was to define screen sizes and
media that could produce reasonable removals and a reasonable length
of filtration run.

      Simply stated, the results of the first three storms demonstrated
that the No.  3 mesh  screen was inadequate for an effective  high rate
filtration operation.  All test filter columns plugged within a few hours,
irrespective of the filter media  utilized.   On one occasion,  the screen
itself plugged.  Inspection of the screen showed that fibrous materials
had matted on the screen.  The matted material resembled primary  paper
mill sludge.

      A  No. 20 mesh screen equivalent to Tyler screen scale 20 mesh
with 841 micron openings was  installed in place of the No.  3 mesh unit.
Operation of the filter test columns, preceded by the No.  20 mesh
screening unit, proved feasible, as reasonable lengths  of filter runs
could be accomplished.  No plugging problems were evidenced.  Com-
plete removal data for the No. 20 mesh screen operation is presented in
Table B-2 in the Appendix. The screening data are summarized as
follows:
                              47

-------
                                Average    Average      Removal
                                Influent    Effluent     	
Suspended Solids  (1)*            470         390         17.0
(mg/1)             (2)              219         173         21.0

Settleable Solids  (1)              10.2        4.8         52.9
(ml/1)             (2)               5.4        2.3         57.4

BOD  (mg/1)       (1)              169         160          5.3
                  (2)               72          56         22.2

COD  (mg/1)       (1)              483         300         37.9
                  (2)              175         146         16.6

      *
       (1)   Run No. 4SF, Average of 5 Samples.
       (2)   Run No. 6SF, Average of 11 Samples.

      Average removals  of suspended solids, for the two storms tested,
approximated 17 to 21 percent.  The range of removal experienced during a
screen test run was quite wide due to the extreme variation of the sus-
pended solids concentration in the raw combined sewer overflow.  For
the two storms tested with the No. 20 mesh screen, the instantaneous
suspended solids removals varied from 0 to 55 percent.  A wide variation in
removal characteristics  of the screening unit was also noted for other
wastewater contaminants.  Previous work done by others on combined
sewer overflow screening has also shown extremely variable removals
in COD and BOD (16), especially in terms of BOD, which of course
could also be  related to the sampling techniques and the reliability of
the BOD test procedure.  In regards to Cleveland,  the fact that a
significant amount of industrial waste containing dissolved organics
Is generated in the Southerly Sewage District might account for the
highly variable removals  of COD and BOD.

      Although the No. 20 mesh screen  permitted a filtration run to last
for a reasonable time, over  6 hours, the head losses experienced
throughout the run were  higher than had been noted in past high rate
filtration testing of industrial waste waters.  Thus, a finer screen was
required,  and a No. 40 mesh screen equivalent to Tyler screen scale 35
mesh with 420 micron opening was selected.  The  No.  40 mesh screen,
although of finer construction than the No. 20  and the No. 3 mesh screen,
can still be described as a sturdy type screen which could last for a
substantial period of time without needing replacement.  In the Hydro-
                               48

-------
technic screen testing and in the selection of various screening sizes
for this pilot program, the larger screen sizes were first utilized on the
basis that the coarser screens would perform without physical failure
for a longer period under the abrasive application of combined sewage
storm overflow treatment. 'Screen failures have been experienced using
finer mesh at another demonstration project  (17).

      Utilizing a finer screen also permitted good filtration operation.
Currently, there are not enough data to compare removal characteristics
of the No. 20 and the No. 40 mesh screen,  although, due to the nature
of the screen opening, better removals are expected by utilizing the  No.
40 mesh screen.  The most significant fact ascertained from the test with
the No. 40 mesh screen was that the head loss through the filter columns
was reduced from that experienced using a No.  20 mesh screen.

      The No. 40 mesh screen was selected as the  screening component
of the overall treatment system.  This  screen appears to have  sturdiness
and strength of construction necessary for extended life, and also pro-
vides sufficient removals of influent suspended solids to permit reason-
able filtration runs  and filtration head  losses. As with most screen
installations, the removals of suspended solids,  BOD and COD cover a
variable range.  The test results  of seven storms  (1970 test) for the No.
40 mesh screen are summarized as follows:

                       Number of    Average    Average     Removal
                        Samples   Influent*    Effluent*
Suspended Solids  (mg/1)    63         176         132        25.3

Settleable Solids (ml/1)     78        5.41        2.15       60.3

BOD (mg/1)                56         75          69         8.2

COD (mg/1)                56        268         209        22.3

     *Average of grab samples through seven combined sewer overflows.

Supplementary Testing - Slotted Screening Element

     At the end of the 1971 field test work, tests were performed to
evaluate the-applicability of a slotted screen element as an alternate to
the mesh type screen which was used throughout all of the prior test
work.  The reason for evaluating the slotted type  screen was due to its
sturdy  construction,  which appears as a potential advantage, consider-
ing the abrasive nature of combined sewer overflows.   The testing was
                               49

-------
accomplished by replacing the mesh screen on the rotating drum with
panels of slotted  screen which were furnished by the Johnson Division
of UOP.  Two screen meshes were tested, as shown on Table 7.

      The criteria used for evaluating the slotted screen elements versus
the mesh screen was filtration operation.  By profiling the head loss in
3 deep bed, high rate filtration column, following the drum screen,
determination can be made whether the screening element is removing a
sufficient amount of fibrous  material (which might impede filter opera-
tion) for efficient system operation.  Since the testing was accomplish-
ed at the end of the test program,  and due to limitations of time and
money, and lack of combined sewage overflow, comparison tests were
performed on raw  sewage instead of combined sewage storm overflow.
These test conditions are  evaluating the capacity of the slotted screens
to remove fibrous material.  As evidenced from Table 7,  head loss
build up in the  filter columns preceded by the slotted  screen is in the
order of  four times as great as that when preceded by a mesh type screen.
Therefore,  material which contributes to filter head loss build up and
filter plugging was  not removed as well in the slotted screen as in the
mesh type screen.  Also,  for the two slotted screening elements tested,
the amount of flow that could be fed through the pilot drum screen sys-
tem was reduced, as versus the mesh type screen.  The lower percent of
open area in the two slotted screen elements (see Table 7)  probably
accounts for the reduced flow.

      In  summary, the two slotted screen elements  tested do not appear
to provide a feasible alternate to the mesh type screen used throughout
the testing program.  Subsequent discussions with Johnson Screen repre-
sentatives indicate that a finer screen opening (slotted variety), with a
larger percent open area than the screening  elements tested, might prove
to be a desirable  screen configuration.  One of the  principal assets
noted was the ease in which material was removed  from the slotted
screen by the water sprays and, due to the heavy construction, no
serious abrasion problems should be evidenced by using a slotted  screen.
                              50

-------
                                                 Table  7
                                          COMPARISON OF SCREEN TYPES
en
          Filtration Rate
            (gpm/ft2)
16

24

32
                                  Mesh Screen
                                                         Slotted Sereen
             Filter Following Mesh       Filter Following Slotted      Filter Following Slotted
             Screen (420 micron.) (1)     Screen (400 micron)  (2)     Screen (200 micron)  (3)
             Length of  Total Headloss  Length of  Total Headless   Length of Total Headless
             Run for.)      (ft.)	Run (hr.)	(ft.)	Run for.)	(ft.)
                                6.0
                                6.0
11
              4.5
5.0
                                                           4.5
             27
35
                           35
              6.0
21
                (1)       43.6% open area - 100 gpm/sq ft   Hydraulic Loading

                (2)       21.1% open area - 45 gpm/sq ft    Hydraulic Loading

                (3)       11% open area - 22 gpm/sq ft    Hydraulic Loading

-------
                         SECTION VIII

             DEEP BED, HIGH RATE FILTRATION RESULTS
Evaluation of Filter Media

       During the initial testing, all the filtration pilot columns,  irre-
spective of the media utilized, plugged when preceded by the No. 3
mesh screen.  Even filtration columns which contained four feet of No.
4 Anthracite (7.15 mm effective size), over four feet of No. 48 Sand
(3.15 mm effective size), or contained eight feet of No.  4 Anthracite
alone, a very coarse media, plugged within a few minutes to an hour.

       Three storms were tested utilizing a No. 20 mesh screen prior  to
the filtration columns.  Three  anthracite sizes were evaluated in con-
junction with No.  612 Sand  (2.0 mm effective size) - four feet of
anthracite over three feet of sand.  The anthracite types  included:

                No. 4 Anthracite (7.15 mm effective  size)
                No. 3 Anthracite (4.0 mm  effective size)
                No. 2 Anthracite (1.78 mm effective  size)

       The results of these storms, summarized on Table B-3 in Appen-
dix B, show that No.  3 Anthracite over No. 612 Sand  proved to be a
workable media since a reasonable  length of filter run could be obtained.
The filtration test  columns utilizing No. 2 Anthracite  in the upper layers
plugged within a few hours. The test column utilizing No. 4 Anthracite,
the coarsest media, plugged in less than one hour as solids were not
retained in the upper layers of the filter and penetrated into, and plugged,
the lower sand layer.  The fine No.  2 Anthracite over the No.  612 Sand
did not prove superior in removal characteristics  to the No. 3 Anthracite
over the No. 612  Sand.  This is evidenced from Table B-3 in Appendix B.
Surprisingly, the  combination  of No. 3 Anthracite over No. 612 Sand
proved superior to the finer  No.  2 Anthracite and Sand combination even
though the No. 2 Anthracite is a finer media.

       When preceded by No. 20 mesh screen, the No.  3 Anthracite -
No.  612 Sand media combination produced  a full range of suspended
solids removals from 51.3 to 78.6 percent  at 16 gpm/sq  ft.  The higher
removal was experienced at an influent filter suspended  solids loading
of 175 mg/1, while the lower filtration efficiency was evidenced at an
influent suspended solids level of 485 mg/1. Curves for all filtration
runs are presented in Appendix  C  .
                                 53

-------
Selection of Screening-Filtration System Components

       The No.  3 Anthracite - No. 612 Sand media was selected for
more extensive testing in conjunction with the No. 40 mesh screen.
The head loss experienced  in the filtration column preceded by the No.
40 mesh  screen was less than that utilizing a No. 20 mesh screen. As
a comparison, at 16 gpm/sq ft , the head loss reading after ten hours
filter operation was 10 feet with a  No. 40 mesh screen versus 14 feet
with a  No.  20 mesh screen.

       The influent suspended solids to the filters for both of these test
runs was in the order of 200 mg/1. At higher filtration rates, the differ-
ence in head loss became even more pronounced and the head loss
were more rapidly increased than at lower filtration rate.

       In the Hydrotechnic test work, head loss  through filter bed was
considered as a key parameter, primarily since the application of the
proposed treatment sequence in a full scale installation would be best
engineered and designed around a gravity filtration system.   Open ves-
sels, which provide an avenue for gas release, appear more desirable
than closed or pressure tanks  when dealing with raw sewage or combined
sewer overflow. The rationale is that potentially explosive gas
accumulations might occur  in pressure vessels, while this condition
would be less prone  to happen in an open gravity filter.  Special  pre-
cautions  and design features would have to be incorporated into the
engineering and operation of a filtration facility for treating combined
sewer overflow which utilized closed tanks or pressure  vessels,
especially in applications  where the dry weather  sewage flow contains
significant quantities of industrial wastes. For example, an explosion
occurred in the one foot diameter pilot filter column  (closed vessel)
several hours after a  filtration run had been performed in  the column, and
after the column was  backwashed.  Possibly  some gas accumulations
expanded and the resulting pressure caused failure of one of the plexi-
glass panels in the large column.

       The head loss in the filter  media during each filtration test run is
indicated in individual data curves in Appendix C.  This head loss does
not include pressure losses that will occur across the filter bottom.
Generally, three curves are presented for each filter run:  the top curve
indicating  the head loss that is experienced through essentially the whole
filter media, and the  other curves  indicating  the  head loss in a certain
depth of  the media, with the media depth measured from the top of the
bed.
                              54

-------
Plain Filtration and Filtration with Poly electrolyte Addition

       Two basic modes of process operation were  evaluated for re-
moving suspended solids and other contaminants  which were in sus-
pended form:  plain filtration and filtration with polyelectrolyte addition.
Plain filtration is simply filtration without chemicals or any additives.
Filtration with polyelectrolyte addition was also evaluated, since
previous data on general filtrations and  on industrial applications of
deep bed, high rate filtration, had shown the merits of utilizing poly-
electrolytes to enhance performance.  The coagulant testing apparatus
was utilized to select polyelectrolytes for full scale filtration runs.
Visual observations and previous experience by others (18) had indi-
cated that filtration test column runs were required to  conclusively
establish the true effect of the polyelectrolyte on filtration removal
efficiency.

       Fifty three polyelectrolytes were evaluated  for enhancing
filtration performance.  All the work, as  previously mentioned, was per-
formed in the coagulant testing apparatus, which permitted simultaneous
evaluation of six different polyelectrolytes at a time.  Results of the
polyelectrolyte evaluation tests are presented in  Table 8.  This  table
indicates that some polyelectrolytes are  better than others in improving
filter performance. Polyelectrolyte selection to be  used in conjunction
with deep bed high rate filtration,  is critical, as  is evidenced from this
table. Four polyelectrolytes produced good removals (88 percent or more)
and three were tested in the pilot filter columns to  obtain operational
data. In general, the anionic polyelectrolytes proved  most effective at
this  particular test site.

       During the 1970 test work, a number of filter runs,were performed
utilizing Nalcolite 671  polyelectrolyte, which was  selected after a series
of jar tests.  Subsequently, in 1971,  the coagulant test apparatus  was
installed and permitted a realistic method of  selecting a polyelectrolyte.
Therefore, the data from the 1970 test work, utilizing  the Nalcolite 671
polyelectrolyte, is not considered applicable to the performance that can
be achieved in the proposed system via  the appropriate polyelectrolyte.

       Complete test results for all the  filtration tests are presented in
Table B-3 through B-6 in Appendix B.  For the recommended system (5
feet of No.  3 Anthracite over 3 feet of No.  612 Sand),  suspended solids
removals with or without polyelectrolyte  addition, are  presented in
Figure 10.  Suspended solids removals increased appreciably with  the
addition of an appropriate  polyelectrolyte and ranged from 90.4 percent at
24 gpm/sq ft  to 96.7 percent at 8 gpm/sq ft at  ah influent concentration
of 300.7 mg/1.  Suspended solids  reduction without polyelectrolytes
                                 55

-------
                             Table 8
             RESULTS OF POLYELECTROLYTE SELECTION TESTS
                                      Total Suspended Solids
Polyelectrolytes

Atlasep 1A1
Atlasep 2A2
Atlasep 3A3
Atlasep 4A4
Atlasep 5A5
Calgon 235
Calgon 240
Gamafloc NA710
Hercofloc 816
Hercofloc 822
Hercofloc 836
Magnifloc 835A
Magnifloc 836A
Magnifloc 860A*
Magnifloc 865A
Nalcolyte 672
Nalcolyte 673
Nalcolyte 675H
Polyhall 295A
Purifloc A23*
Swift X400

Aqua-Rid 49700
Aqua-Rid 49701
Aqua-Rid 49710
Aqua-Rid 49711
Atlasep 105C
Calgon 227
Calgon 228
Gamafloc NC-722
Hercofloc 810
Hercofloc 814.2
Hercofloc 828.1
 Type
Anionic
Anionic
Anionic
Anionic
Anionic
Anionic
Anionic
Anionic
Anionic
Anionic
Anionic
Anionic
Anionic
Anionic
Anionic
Anionic
Anionic
Anionic
Anionic
Anionic
Anionic

Cationic
Cationic
Cationic
Cationic
Cationic
Cationic
Cationic
Cationic
Cationic
Cationic
Cationic
Influent
(mg/1)
204
513
204
181
, 204
250
248
248
164
164
164
236
236
236
181
248
231
231
513
164
513
478
478
478
478
181
250
250
248
236
236
236
Effluent
(mg/1)
60
182
27
13
39
170
63
36
24
32
20
98
95
206
87
72
78
4
250
20
199
252
202
184
244
66
152
188
158
41
194
182
Removal
(*)
71
65
87
93
81
30
75
86
85
81
88
58
60
13
52
71
66
97
51
88
61
47
58
65
49
64
39
25
36
83
18
23
                              56

-------
                            Table 8
                           (Continued)

          RESULTS OF POLYELECTROLYTE SELECTION TESTS
Polyelectrolytes

Magnifloc 521C*
Magnifloc 560C
Magnifloc 570C*
Magnifloc 571C*
Polyhall MRL 91
Purifloc C-31*
Purifloc C-41

Aqua-Rid 49704
Atlasep IN
Magnifloc 900N
Magnifloc 905N
Magnifloc 985N*
Magnifloc 990N*
Nalcolyte 671
Polyhall M402

Calgon No.  18*
Calgon No.  25
Zetafloc WN
Zetafloc WA
Zetafloc C
Zetafloc CX
  Type
Cationic
Cationic
Cationic
Cationic
Cationic
Cationic
Cationic

Nonionic
Nonionic
Nonionic
Nonionic
Nonionic
Nonionic
Nonionic
Nonionic

(1)
(2)
(3)
(2)
(4)
(4)
                                       Total Suspended Solids
Influent
 (mg/1)

  250
  181
  250
  250
  513
  164
  164

  478
  181
  204
  181
  204
  204
  189
  513

  248
  248
  513
  189
  189
  185
Effluent
 (mg/1)

   200
    10
   140
   166
   264
    27
    93

   164
    65
   118
    85
   106
   108
    64
   373

   114
   170
   330
    89
   103
    97
                                                        Removal
20
94
44
34
49
84
43

66
64
42
53
48
47
66
27

54
31
35
53
46
49
*      Approved by EPA for Water Treatment (April 1971)
(1)     Nonionic, High M.W.  Polyelectrolyte Polymer & Bentonite
            Clay Mixture
(2)     Anionic and Bentonite clay or Aluminum Silicate Mixture
(3)     Nonionic and Aluminum Silicate Mixture
(4)     Cationic and Aluminum Silicate Mixture

       Note:  Flux Rate (20-24 gpm/sq ft ), three hour  composite
               samples.
                             57

-------
No. 40 MESH  SCREEN

No. 3  ANTH

No. 612 SAND
              WITH  POLYELECTROLYTE

              WITHOUT POLYELECTROLYTE

              POINTS ARE AVERAGE VALUE
              OF 4 TO 20 GRAB SAMPLES
  o
  s
  LU
  CO
  Q
  O
  CO


  O
  LU
  Q
  z
  LU
  0_
  CO
  ID
  CO
        0
10       20       30       40

    FLUX  RATE  (gpm/sqft)
50
    MEAN SUSPENDED  SOLIDS  REMOVALS  BY
                     FILTRATION
                                        FIGURE 10
                         58

-------
ranged from 37.5 at 40 gpm/sq  ft  to 72.8 percent at 10 gpm/sq ft  at
influent concentration of 152 and 114 mg/1, respectively.  Suspended
solids removal is the chief criterion for process efficiency.  A summary
of filtration test results for two typical combined sewer overflows are
shown on Table 9.
                              Table 9
            SUSPENDED SOLIDS REMOVALS BY FILTRATION
   Filtration   Number     Average
      Rate        of        Influent
  (gpm/sq ft ) _Samples      (mg/1)

  Plain (1970)

       10         13         114
       16         17         205
       24         13         114
       32          4         132
       40          4         152

  With Polyelectrolyte (1. 0 mg/1)
      (1971)
                     Average
                     Effluent
                     (mg/1)
                       31
                       48
                       74
                       80
                       95
                         Removal
                           72.8
                           76.6
                           35.1
                           39.4
                           37.5
        8
       16
       24
6
6
6
300.7
300.7
300.7
10.0
 9.0
28.0
96.7
97.0
90.4
       Similar to suspended solids,  settleable solids removals increase
appreciably with the introduction of appropriate polyelectrolyte,  as shown
in Table  10.  For filtration rates between 8 and 24 gpm/sq ft  with poly-
electrolyte addition, settleable solids removals were 92.8 to 90.7 per-
cent, respectively.  Effluent settleable  solids values are in the order of
0.1 ml/1.
                            59

-------
                             Table 10

            SETTLEABLE SOLIDS REMOVALS BY FILTRATION
Filtration
Rate
(gpm/sq ft )
Plain
(1970, 1971)
10
16
24
32
40
Number
of
Samples


12
6
4
11
7
Average
Influent
(ml/1)


2.0
2.3
2.4
.72
1.9
Average
Effluent
(ml/1)


.07
.3
.3
.13
.4
Removal
(%)


96.5
87.0
87.5
81.9
78.9
With Polyelectrolyte (1.0 mg/1)
   (1971)
       8               6            1.4         0.1          92.8
      16               6            1.4         0.1          92.8
      24               6            1.4         .13          90.7

      Table 11 shows the effect of deep bed, high rate filtration on the
removal of organic pollutants, measured as biochemical oxygen demand
(BOD), and chemical oxygen demand (COD).  BOD removals cover a
variable range, both with and without polyelectrolyte addition to  the
filtration process.  Without chemicals, the reductions  varied from 7.5 to
36.4 percent at filtration rates of 32 and 10 gpm/sq ft and average influent
concentrations of 93 and 77 mg/1,  respectively.  With the addition of poly-
electrolyte, reductions varied from 53.3 to 59.7 percent at filtration rate of
24 and 8 gpm/sq  ft  and an influent concentration of 67 mg/1.  As shown
in Table  11,  two factors seem apparent:  first,  there doesn't seem to be
any significant correlation between filtration rate and BOD removal, and
secondly,  process performance with polyelectrolyte addition is substan-
tially better than without polyelectrolyte addition.  The nature  of the
Cleveland  combined sewer overflow,  one which contains a heavy
industrial contribution, may account for the variable BOD removals.
Also, the reliability and reproducibility of BOD test results  when dealing
with a sewage with industrial waste components may be a factor.

      For removals  of COD, the data without polyelectrolyte addition
generally follows an expected trend, that is better removals at low
filtration rates. These data for  process efficiency with polyelectrolyte
addition do not seem to show a discernible trend  for removals  in filtration
                              60

-------
                                                   Table  11
                                   BOD AND COD REMOVALS BY FILTRATION
en

Filtration
Rate
(gpm/sq ft )
Plain (1970)
10
16
24
32
40

Number
of
Samples

13
20
13
6
4
With polyelectrolyte (1
(1971)
8
16
24

6
6
6

Average
Influent
(mg/1)

77
53
77
93
78
. 0 mg/1)

67.0
67.0
67.0
BOD
Average
Effluent
(mg/1)

49
45
67
86
68


27.0
27.5
31.3


Removal
(%)

36.4
15.1
13.0
7.5
12.8


59.7
59.0
53.3

Average
Influent
(mg/1)

117
118
117
244
139


161.2
161.2
161.2
COD
Average
Effluent
(mg/1)

44
82
83
187
83


44.5
73.5
70.5


Removal
(#)

62.4
30.5
29.1
23.4
40.3


72.4
54.4
55.6

-------
ranges of 8 to 24 gpm/sq ft. This may be due to the fact that suspended
solids removals were substantially similar at 24 gpm/sq  ft  and at 8
gpm/sq ft for process operation with addition of appropriate chemical.
Removals with polyelectrolyte addition ranged from 55.6  to 72.4 percent
at filtration rates of 24 and  8 gpm/sq ft  , respectively.

      More limited data on removals of total organic carbon by filtration
(1970 test data) indicate removals ranging from 42.5 percent at 32 gpm/
sq.ft. with influent and effluent concentrations of 135.7 and 78.0 mg/1,
respectively, to 62.7 percent at 10 gpm/sq ft  reducing  the  influent
concentration from  67.0 to 25.0 mg/1 in the effluent for process
operation with polyelectrolyte addition.  Percentagewise, total organic
carbon  removals are higher than the respective COD removals.

      Table 12  shows the process performance in regard to phosphorus
removal, an important consideration where the effluent is discharged to
a lake.  This table illustrates that total phosphorus removal, with poly-
electrolyte addition, does not seem to be substantially influenced by
filtration rates  in the range  of 8 to 24 gpm/sq  ft - Each of the two poly-
electrolytes shown on the table were considered as an optimum poly-
electrolyte.  The results for the phosphorus reductions utilizing  the two
polyelectrolytes are in the order of 30-50 percent.
                             Table 12

            TOTAL PHOSPHORUS REMOVALS BY FILTRATION
    Filtration       Number       Average     Average
      Rate           of          Influent     Effluent     Removal
   (gpm/sq ft  )     Samples       (mg/1)	(mg/1)	(%}

   With Polyelectrolyte Purifloc A23 (1.0 mg/1)
     (1971)
       8              6           0.71         0.43        39.4
      16              6           0.71         0.39        45.1
      24              6           0.71         0.40        43.7

   With Polyelectrolyte Magnifloc 560C (1.0 mg/1)
     (1971)
       8              6           0.76         0.40        47.2
      16              6           0.76         0.36        52.6
      24              6           0.76         0.55        26.3
                              62

-------
Results on removal of nitrogen, a factor considered critical to lake
eutrophication, in some cases indicates removals ranging from 10.9
to 42.5 percent (filtration without polyelectrolyte - 1970 data) with an
average influent concentration of 8.7 to 23.2  mg/1.  Table B-6 in
Appendix B presents the test results.

      Table 13 gives a further breakdown as to the nature of solids
removals by high rate filtration tested in  1970.   For filtration rates of
10, 16, and 24, gpm/sq ft  , removals are shown for total nonvolatile
solids, total volatile solids, total suspended solids,  total  nonvolatile
suspended solids, and total volatile suspended solids.  The major
deduction from this table is that removals of nonvolatile suspended
solids are greater than removals of volatile suspended solids. In other
words, the inert or inorganic solids  are more amenable to removal by
high rate filtration.  As a possible extension of these  results, one might
suspect that,  as  the nature of the solids  in combined  sewer overflow
becomes more of  a nonvolatile variety than a volatile  suspended  solids
variety, overall system removal of suspended solids would  increase.
Another possible  extension of this data trend suggests that  the filtration
process would be more effective with urban runoff than for combined
sewer overflows, as the nature of the  suspended solids in urban  runoff
normally tends to be more of a nonvolatile suspended  solids or inert
variety, as contrasted to combined sewer overflows  (19).

      Table 14 summarizes the removal data of greases by high rate fil-
tration. As shown by this tabulation,  the test data was  subject to
significant variability,  with removals  ranging from 31.6  to  45.5 at
filtration rates of 32 and 16 gpm/sq  ft with composite influent concen-
tration of 28.4 and 25.5 mg/1, respectively.  The analysis  and inter-
pretation of the greases in sewage has always been a  difficult problem,
especially where significant amounts and varieties of industrial wastes
are present, as in Cleveland.  During the 1970  testing program,  several
results showed extremely high oil and grease  concentrations.  The cause
of these high  values could not be determined but a note on  the result
sheet from the laboratory running the analyses indicated that the residue
experienced at the end of the laboratory test did not resemble normal
ether extractable residue.

      For plain filtration tests, the length of run was  generally in the
range of 6-10 hours for flow rates of 24 gpm/sq ft or less.  Filtration
head losses at 16 gpm/sq ft would generally be less than 15  feet and
ranged up to 30 feet and greater for  the higher filtration rates.  No
deterioration  of effluent quality with time or length of filter run was
normally evidenced for the plain filtration mode of operation. At the end
of a filter run, visual observations revealed that solids had penetrated
throughout the depth of the filter media.
                              63

-------
                                  Table 13
                     SOLIDS REMOVALS BY FILTRATION
Filtration
Rate
(gpm/sq ft )
Number
of
Samples
Average
Influent
(mg/1)
Average
Effluent
(mg/1)

Removal
(%)
Total Nonvolatile Solids
(1970)
10
16
24

5
3
5

202
139
202

162
112
167

19.9
19.4
17.3
Total Volatile Solids
(1970)
10
16
24
Total Suspended

5
3
5
Solids

108
118
180


136
95
175


24.4
19.5
2.8

         (1970)
10 5 116
16 5 116
24 5 116
Total Nonvolatile Suspended Solids
30
37
63
74.0
68.0
45.7
         (1970)
          10            5             54
          16            5             54
          24            5             54

     Total Volatile Suspended Solids
 9
12
26
83.0
78.0
52.0
(1970)
10
16
24

5
5
5

62
62
62

21
23
39

66.0
63.0
37.0
Note: Data from runs using  1.5 mg/1 of Nalcolyte 671
      (not optimum polyelectrolyte control)
                                  64

-------
                             Table 14

                    GREASE REMOVALS BY FILTRATION
   Filtration          Average*        Average*
      Rate             Influent          Effluent        Removal
   (gpm/sg ft  )        (mg/1)             (mg/1)     	
   Plain  (1970)
      16              25.5               13.9          45.5
      24              28.4               16.4          45.1
      32              28.4               19.4          31.6

   With Polyelectrolyte**
     (1970)
      10              10.9                5.5          49.5
      16              23.0                6.5          31.8
      24              28.4               16..4          45.1
      32              48.4               27.5          43.2

   *  Composite sample over 6 hours period.
   ** With Nalcolyte  671 1.5 mg/1  (not optimum polyelectrolyte)

      For filtration with addition of appropriate polyelectrolyte,  test runs
ranged between 3 and 6 hours  before a discernible increase  in effluent
solids was evidenced.  The length of run was terminated at  the point at
which substantial deterioration of effluent quality was evidenced.  The
length of run and head loss  data for this mode of test operation are indi-
cated in Table B-3 in Appendix B.  Head losses were generally below 15
feet, at flux rates of 8 gpm/sq  ft  and ranged up to approximately 40 feet
at flux rates  of 24 gpm/sq  ft   For test runs using Atlasep 4A4, an accu-
mulation of a few inches of material was noted on the surface of the
filter media,  although visual observation indicated that solids had also
penetrated throughout the depth of the  media. No problems  were
experienced in backwashing this accumulation from the top of the  media.
In,a full scale filtration facility, utilizing the deep bed,  high rate fil-
tration process with the addition of appropriate polyelectrolyte,  the
process would be controlled by both head loss and effluent quality, as is
discussed in Section X.

      Removal of coliforms, both fecal and total, via the deep bed, high
rate filtration process does  not seem to be  influenced by filtration rate,
or polyelectrolyte addition. Removal data covers an extremely broad
range with fecal coliform removals varying  from 9.8 to 82.2  percent
                               65

-------
(Table B-4 in Appendix B).  Total coliform removals vary between 0 and
93.4 percent. An interesting observation is that total colitorm removals
are generally higher than fecal coliform removals.  However, the remov-
al of coliforms in the  filter bed is insignificant  for the purpose of dis-
infection.

Filtration with Coagulant Addition - Phosphate Reducing Coagulants

      A major portion  of the 1971 test work was  centered on evaluating
the effectiveness of adding coagulants that would convert soluble phos-
phorus to the insoluble form, with the intention  of subsequently removing
it on the deep bed,  high rate filter.  To evaluate this mode of operation,
a series of preliminary tests were performed in the coagulant testing
apparatus to evaluate chemicals and polyelectrolytes to be used in this
mode  of operation.  Initial testing evaluated alum, ferric chloride, and
lime.   Initial test coagulant dosages were selected by utilizing the
following ratios  by  weight:  2 Alum/P,  1 FeCls/P and 4.5 Ca (OH)2/P.
The 1970 data had indicated an average phosphorus (P) value of
3.3 mg/1 which was utilized to determine initial test  dosages.

      The results of the coagulant selection tests are indicated in Table
15, including one run of lime, one run of ferric chloride, and the rest
with alum. Alum was selected for this application after comparison with
lime and ferric chloride.   In trial runs,  it was found that lime created  a
turbid effluent with plugging problems and that ferric  chloride occasion-
ally produced an orange yellow colored effluent.

      An extended series of tests was performed utilizing various
dosages of alum and various polyelectrolytes, as  shown in Table  15.
Process performance in terms of suspended solids removal and in  terms
of total phosphorus removal was quite variable.   On some occasions,
exceptionally good  removals  (in the order of 90  percent of suspended
solids and phosphates were attained, while on other  occasions, utilizing
similar coagulant dosages and polyelectrolyte dosages, process perform-
ance was very poor (in the order of 30 percent removal or less).

      To evaluate this mode of process operation further,  a  series of
pilot filter column runs were performed to obtain operational data.
Complete results are  presented in Table B-3 (Sheet Nos. 5-7) in
Appendix B.

      Table 16 presents suspended solids removals from three combined
sewer overflows for the process using alum and  various polyelectrolytes.
                               66

-------
                                                          Table  15
                                               COAGULANT SELECTION TESTS
                                              (THREE INCH DIAMETER FILTER)
01
-o
Date

6/1
6/1
6/3
6/3
6/9
6/9
7/8
6/3
6/9
6/9
7/8
7/8
7/14
8/11
7/8
8/11
7/8
7/14
7/8
7/14
7/8
6/1
6/1
Coagulant
Alum
Alum
Alum
Alum
Alum
Alum
Alum
Alum
Alum
Alum
Alum
Alum
Alum
Alum
Alum
Alum
Alum
Alum
Alum
Alum
Alum
50
25
20
40
50
25
30
40
50
25
30
30
30
30
30
30
30
30
30
30
30
mg/1
mg/1
mg/1
mg/1
mg/1
mg/1
mg/1
mg/1
mg/1
mg/1
mg/1
mg/1
mg/1
mg/1
mg/1
mg/1
mg/1
mg/1
mg/1
mg/1
mg/1
FeCla ** 25 ma/1
Ca (OH)






Polyelectrolyte
Magnifloc 56 OC (1 mg/1)
Magnifloc 560C (1 mg/1)
Magnifloc 560C (1 mg/1)
Magnifloc 560C (1 mg/1)
Magnifloc 560C (1 mg/1)
Magnifloc 560C (1 mg/1)
Magnifloc 560C (1 mg/1)
Atlasep 4A4 (1 mg/1)
Atlasep 4A4 ( 1 mg/1)
Atlasep 4A4 (1 mg/1)
Atlasep 4A4 (1 mg/1)
Atlasep 3A3 (1 mg/1)
Atlasep 3A3 (.5 mg/1)
Atlasep 3A3 (.25 mg/1)
Swift X-400 (1 mg/L)
Swift X-400 (1 mg/1)
*Purifloc A-23 (1 mg/1)
*Purifloc A-23 (1 mg/1)
*Purifloc C-31 (1 mg/1)
*Purifloc C-31 (1 mg/1)
Nalcolyte 675H
MagniflocseOC (1 ma A)
2 (120 mg/1) 	






Flux Rate
(qpm/ft2)
20
20
16
16
24
24
20
16
24
24
19
19
24
24
19
16
20
24
20
24
20
20
Filter
Plugged
within 15
minutes
Total
Influent
(mg/1)
214
214
192
192
274
274
244
192
274
274
92
92
84
84
92
54
244
84
244
84
244
214
Very



Suspended Solids
Effluent Removal
(mg/1) %
20
42
24
60
42
18
170
96
6
12
66
82
18
22
54
23
106
26
172
32
144
58
Turbid



90
80
87
69
85
94
30
50
98
96
28
11
79
74
4]
5',
57
69
30
62
41
73
Effluent



Total Phosphorus
Influent
(mg/1)
12.1
12.0
7.5
7.5
.58
.58
.96
7.5
.58
.58
1.05
1.05
.23
.23
1.05
.45
.96
.23
.96
.23
.96
12.0




Effluent
(mg/L)
3.0
4.3
2.0
2.9
.04
.04
.76
5.4
<.01
.03
1.0
.96
.08
.10
.55
.34
.65
.09
.73
.10
.76
3.1




(P)
Removal
%
75
64
73
61
93
93
21
28
98
96
5
10
65
57
48
25
32
61
24
57
21
74




                                     *   Approved by EPA for Potable Water Treatment.

                                     **  Discernable orange color in effluent.

-------
                              Table 16

           SUSPENDED SOLIDS REMOVALS WITH ALUM AND
                      POLYELECTROLYTE ADDITION
  Filtration     Number      Average     Average
     Rate          of         Influent     Effluent      Removal
 (gpm/sq ft )   Samples     (mg/1)	(mg/1)	
  With Alum (30 mg/1) and Purifloc A-23 (1.0 mg/1)
     (1971)
      8            6         159.7        59.7          62.6
     16            6         159.7        54.0          66.2
     24            6         159.7        92.5          42.1

  With Alum (30 mg/1) and Magnifloc 560C (1.0 mg/1)
     (1971)
      8            6         301.7       108.0          64.2
     16            6         324.5       181.0          44.2
     24            6         192.2        48.0          75.0

  With Alum (30 mg/1) and Purifloc C-31 (1.0 mg/1)
     (1971)
      8            4         217.5        38.0          82.5
     16            4         217.5        65.3          70.0
     24            4         222.5        89.0          60.0
      The alum dosage was 30 mg/1 and the polyelectrolyte dosage was
1 mg/1.  The results contained in this tabulation confirm the  fact that
the variable performance,  in terms of suspended solids removal,  occurs
similar to the results obtained in the small-scale coagulant-testing
apparatus. Process performance does improve with decreasing filtration
rate.  Filter length of  run generally varied from three to six hours, with
the run arbitrarily terminated when an appreciable solids breakthrough
was evidenced.  Head loss values range from below 5  feet at a flux
rate of 8 gpm/sq ft  to approximately 40 feet at a flux rate of 32  gpm/
sq ft,  Generally, an  accumulation of 4 to 5 inches  was  noticed on top
of the filter media, as this accumulation would gradually build up
throughout the filtration run.  In addition,  depth penetration of solids
throughout the media was also observed.  In fact, after approximately
two hours, the media appeared saturated with solids.  No backwash
problems were evidenced as the material was readily removed from the
media.
                              68

-------
      Table 17 shows BOD and COD removals by high rate filtration with
alum and polyelectrolyte addition for a typical combined sewer overflow.
The GOD and BOD reductions were approximately equal.  Greater COD
than BOD reductions could be anticipated on the basis of previous
test work at lower filtration rates.
                              Table 17

               BOD AND COD REMOVALS WITH ALUM AND
                        POLYELECTROLYTE ADDITION*
  Filtration
     Rate
 (gpm/sq  ft )
Number
  of
Samples
Average
Influent
 (mg/1)
Average
Effluent
 (mg/1)
Removal
     BOD
     (1971)
       8
      16
      24

     COD
     (1971)
       8
      16
      24
   4
   4
   4
   4
   4
   4
  65.8
  65.8
  65.8
 163.8
 163.8
 163.8
  31.5
  34.5
  30.0
  47.0
 101.5
 126.3
  52.1
  47.6
  54.4
  71.3
  32.0
  22.9
  * With Alum 30 mg/1 and Purifloc C-31  1.0 mg/1.
      As shown in Table 18, total phosphorus reductions at average
influent concentration of 0.9 mg/1 were 73.3, 47.8 and 42.2 percent at
filtration rate of 8,  16 and 24 gpm/sq ft  , respectively.  Similar to the
performance experienced in the coagulant testing apparatus, total phos-
phorus reductions parallel suspended solids reductions.  Comparing in-
fluent and effluent soluble phosphate values, coagulant addition (30 mg/1
alum) prior to filtration converts approximately 65 to 70 percent of the
soluble phosphate present in the wastewater to the insoluble form.

      The actual use of alum in the molar ratio of 2 Al/P should provide com
plete conversion of  soluble phosphate to insoluble aluminum-phosphate.  Th€
lower results obtained indicate that more thorough mixing at the point of
injection should have been accomplished in order to utilize the aluminum
                              69

-------
ion for fast aluminum phosphate formation rather than allowing the
aluminum to be made unavailable for phosphate removal by the slower
reaction to form aluminum hydroxide.
                             Table 18

              TOTAL PHOSPHORUS REDUCTIONS WITH
              ALUM AND POLYELECTROLYTE ADDITION
Filtration
Rate
(gpm/sq ft )
Number
of
Samples
Average
Influent
(mg/1)
Average
Effluent
(mg/1)
 With Alum (30 mg/1) and PuriflocA23 (1.0 mg/1)
     (1971)
       8           6         0.90          0.24
      16           6         0.90          0.47
      24           6         0.90          0.52

 With Alum (30 mg/1) and Magnifloc 560C (1.0 mg/1)
     (1971)
       8           6         0.61          0.16
      16           6         0.57          0.37
      24           6         0.51          0.19
                                                       Removal
73.3
47.8
42.2
73.8
35.0
62.7
      It appears that this mode of process operation is applicable to a
situation where there is a  substantial amount of dissolved phosphate in
the wastewater, and where phosphate removal is of greater importance
than suspended solids removal.

Significance of Storage on Filtration Test Results

      Section IV described the pilot plant sequence and process units
utilized in the test work at the Southerly Wastewater Treatment Plant.
The influent to  the filters was abstracted from a storage tank, equipped
with an agitator to keep solids in suspension. The combined  sewer
overflow was pumped to a  drum screen, whence it flowed  to the
storage tanks.  For most of the test runs,  the storage tank was filled
with a sufficient quantity of combined sewer overflow for  fil-
tration test runs before the duration of the combined sewer over-
flow had elapsed.  The screen was operated throuahout the entire
duration of the  combined sewer overflow, which was determined
                             70

-------
by observing the influent of the Southerly Wastewater Treatment Plant.

      In essence,  since the storage tanks were generally filled within
30 minutes, the filtration portion of the testing was conducted  on a
sample  of wastewater which can be described as characteristic of  the
earlier stages of combined  sewer overflow.  Thus, the average
filter influent during a test run was generally greater in concentration
than the average screen effluent, due to the fact that the filtration in-
fluent sample was  collected during the earlier part of the storm, when
higher suspended solids normally prevail.  Table 19 compares average
screen effluent and average filter influent for the test runs.

      In regard  to.solids sedimentation in the storage tank between the
screening  unit and  the filtration test columns,, it was apparent that the
•nixing devices  set up in the tank were sufficient to prevent deposition,
since no significant accumulations of  solid materials were evidenced at
:he bottom of the tank after a filtration test run.  Therefore, the test set-up
and arrangement, although not exactly identical to the flow sequence that
would occur in an actual full  size plant,  provides data,  which would be
comparable to that  in a full size  treatment facility.

Backwash  Considerations

      At the end of each filtration run, air and water were injected
alternately into the bottom of the filter column over a period of time.
For the  pilot plant backwash operations, air volume was varied from 2.1
to 15.5 scfm/sq ft  over 2.5 to 29 minutes for breaking up the "mud
balls" which accumulated in the filter media. Then, air was stopped
and  backwash water was introduced to flush out all suspended solids
until the filter  media was clean  and the backwash water effluent was
observed  to be clear.

      Backwash water volume used ranged from 1.9 to 8.6  percent of
the total combined sewer overflow filtered  (1970 data) with the median
value at approximately 4 percent.  The range of backwash water rate
employed was 31 to 90 gpm/sq ft  over 4 to 25 minutes of  backwashing.
Due  to  the "wall effect" in the pilot filter column and inaccurate control
of backwash water as well as inefficient backwash outlet design,  an
excessive amount  of wash  water and  air may have been required.

      Well designed high rate filtration plants for steel mill wastewater
treatment systems, normally utilize backwash water rates at 30 gpm/sq
ft for 10 minutes and air at 6 scfm/sq ft for 2 minutes  (20).
                                71

-------
                                                         Table  19


                                        EFFECT OF STORAGE  ON FILTER INFLUENT
                                                       (1970 TEST DATA)
         Rur. Length
                       Suspended Solids (Ave.)
                                                    Ave. BOD
                                                                               Ave. COD
                                                                                                        Ave. Settleable Solids
to
No.
4 SF
*5 SF
6 SF
7 SF
*8 SF
9 SF
10 SF
11 SF
J13 SF
14 SF
of Run
(Hours)
2
-
6
7
-
9
10
6
-
6
Screen Eff.
mq/1
390
-
138
210
-
133
96
137
-
74
Filter Inf.
417
-
144
236
-
121
113
175
-
85
A
+ 27
-
+ 6
+ 26
-
-12
+ 17
+ 38
-
+ 11
Screen Eff.
160
-
57
43
-
80
57
90
-
53
Filter Inf.
172
-
63
54
-
74
75
97
-
64
A
+ 12
-
+ 6
+ 11
•
- 6
+ 18
- 7
-
-11
Screen Eff.
300
-
its
142
-
137
198
280
-
146
Filter Inf. .
350 +50
-
ISO - 5
143 + 1
- -
112 -25
200 + 2
283 + 3
-
133 - 7
Screen Eff.
mg/1
4.8
-
2.4
2.1
"~
2.3
1.6
2.5
"*
0.9
Filter Inf.
4.2
-
2.6
2.8
"
2.1
1.4
3.2
"
1.4
A
-0.6
"
+ 0.2
+ 0.7

-0.2
-0.2
+0.7

+ 0.5
         * -  Insufficient Screen Data

         w
         * -  Storage Tank Not Used

-------
    Figure 11 shows typical suspended solids profiles of backwash
effluent water from various filtration backwashes.  The effluent from the
filter column was normally clear after 4 to 8 minutes  of water flush.
Suspended solids levels in the filter backwash water ranged between 50
and 14,000 mg/1.

    Figure 12 shows settling characteristics of filter backwash solids.
The majority of suspended solids were removed  at a test overflow rate of
approximately 0.7 gpm/sq ft.

    As indicated in Table B-3(Sheet   Nos.  2 and 4) in Appendix B, a  mass
balance between solids removed during a filter run and solids contained
in the filter backwash was developed. In most  cases, a good correlation
was not evidenced, probably influenced by the sampling procedure and
the rapidly changing suspended solids levels in the filter backwash
effluent.
                            73

-------
otiuuu


10,000
^, 5,000
E

W
o
^ 1,000
<0
500
UJ
5
UJ
§ 100
co
50


10











f=
/—









/
h/i
/











/"
/














V
V
V















\
*















V
\
\(
















\
















v
\
\





































10,000
•£, 5,000
£

CO
Q
J 1,000
CO
500
8
0
1
S> 100
(0
50


10




H

^
ffl
/
/
/









-\~\
'
h













\-
\
\
















¥
\
\
















\
















^^
















-^






























""v^
— ^















y
\


              234  56789  10
              BACKWASH TIME (min.)
         0123456789  10
              BACKWASH TIME (min.)
FILTER BACKWASH FROM COLUMN RUN No.4SFn
FILTER BACKWASH FROM  COLUMN RUN No. 4SFII
10,000
"01 5,000
V)
Q
g 1,000
SUSPENDED J
— 01
0 0
0 0
50
10
TER BACI


=


P
m




_A\
4
m
1
/




+
rH






\
\
>












^r
H













^
s












X




















































10,000
o> 5,000
J
CO
Q
jJ 1,000
a 50°
a
UJ
§ 100
CO
50
in



,
/
/
•/—
f—








k
FM
h












v
\
^












\ —
Nd
\
\













\













\


























^^













X












x
0 23456789 10 01234567 8 9 K
BACKWASH TIME (min.) BACKWASH TIME (min.)

-------
    3.0
CT
CD



Q.
UJ
cr


o
U_
o:
LJ
    2.5
^   2.0
1.5
1.0
     .5
                         INITIAL SUSPENDED
                         SOLIDS  1450 mg/l
                         AVERAGE TEMP. 54°F
                      INITIAL SUSPENDED
                      SOLIDS 3310mg/l  0
                      AVERAGE TEMP 53 F
       0        200      400       600      800

                SUSPENDED SOLIDS REMAINING (mg/l)


BACKWASH WATER SEDIMENTATION CHARACTERISTICS
                                            FIGURE 12
                        75

-------
                            SECTION IX

                       SYSTEM PERFORMANCE
       The proposed treatment sequence is comprised of two treatment
components, the screen facility and the high rate filters.  Total system
efficiency was determined by combining the  efficiencies of these two
treatment components. Where only filtration tests were performed, total
system efficiency was determined by combining filtration removals and
average screen removals from  previous test runs.

       The effect of the proposed treatment  system (No.  40 mesh screen
and high rate filters with No.  3 Anthracite over No. 612 Sand)  in regard
to the removal of key water quality parameters is presented in Figures 13
to 15 and Tables 20 through 22.

       During the  screening-filtration system operation, process effi-
ciency varied with influent suspended solids concentration, whereas the
effluent concentration remained comparatively constant (21).  The
following table shows the results of suspended solids removal from a typi-
cal combined sewer overflow filtration test with 30 mg/1 of alum and
1.0 mg/1 of polyelectrolyte addition.  With effluent suspended solids of
36 mg/1, the removal efficiency would be 92 percent at the initial
period of combined sewer overflow when suspended solids concentrations
are about 442 mg/1, whereas the reduction of suspended  solids would
be only 46 percent after the peak overflow period when the influent
concentration is 100 mg/1 and the effluent concentration is 54 mg/1.

                             Average   Average
                             Influent   Effluent
Filtration Rate    Number of      S.S.      S.S.     Removal
  (gpm/sq ft)       Samples      (mg/1)      (mg/1)      (%)
      8              3           442        36       92.0
                     2           362        48       86.7
                     2           100        54       46.0

     16              3           442        82       81.5
                     2           362        60       83.5
                     2           100        64       36.0

       Figure 13 shows the effect of filtration rate upon  the removal of
suspended solids, including the effect of polyelectrolyte on process
efficiency.  Without chemicals, tested in 1970, suspended solids re-
movals ranged from 40 percent  (average of 22 grab samples in 2 filter
runs) at a filtration rate of 40 gpm/sq ft, to 77  percent (average of 8 grab

                               77

-------
No. 40 ME
No. 3 ANT
No. 612 St
100
90
S 80
< 70
O
2
£ 60
S 50
O
<" 40
Q
UJ
g 30
UJ
CL
S§ 20
1 0
0
SH SCREEN 4 WITH POLYELECTROLYTE
• WITHOUT POLYELECTROLYTE
POINTS ARE AVERAGE VALUE
OF 4 TO 20 GRAB SAMPLES
-*-

^i







	 J—

^^







T>.

1-1971 TEST

V>>s^
^
1970 TES






^^ w
-X









»




0
10
20
30
40
          FLUX   RATE (gpm/sq.ft.)
     SYSTEM PERFORMANCE
  SUSPENDED SOLIDS REMOVAL
50
                           FIGURE 13
              78

-------
samples in one filtration) at a filtration rate of 10 gpm/sq ft with an
influent suspended solids concentration range of 160 to 190 mg/1.  With
the addition of an appropriate polyelectrolyte  (1 mg/1) tested in 1971,
suspended solids removal efficiencies significantly improved,  ranging from
91.6 percent (average of 6 grab samples)  at a filtration rate of 24 gpm/
sq ft to 97.7 percent (average of 6 grab samples) at a filtration rate of
8 gpm/sq  ft at an average influent suspended  solids concentration of
250 to 400 mg/1.  With  polyelectrolyte addition,  process  efficiency is
substantially the same at 24  gpm/sq ft as it is at 8 gpm/sq ft although,
as indicated in the previous chapter, head loss build-up  is significantly
greater at 24 gpm/sq ft.

       Settleable solids removals by the  screening-filtration process are
indicated  on Table 20.  For all filtration rates tested, settleable solids
removal generally falls  within the range of 80-90 percent. Without
polyelectrolyte addition, for  filtration rates of 16 gpm/sq ft at an average
influent level of 5.8 ml/1, removals are in excess of 94 percent.  With
the addition of polyelectrolyte and an average influent level of 8.8 ml/1,
system removals of settleable solids are in excess of 98  percent for
filtration rates  of 24 gpm/sq  ft.  Probably the most significant fact from
this table is that settleable solids removals are substantially increased
at 24  gpm/sq ft with the addition of polyelectrolyte.  The proposed system,
with polyelectrolyte addition, essentially removes all of  the settleable
material.

                         Table 20

                   SYSTEM PERFORMANCE

                SETTLEABLE SOLIDS REMOVALS
Filtration
Rate
(gpm/sq ft)
Number
of
Samples
Average
Influent
(ml/1)
Average
Effluent
(ml/1)
                                                     Removal
Plain (1970)
     10
     16
     24
     32
     40
12
13
 8
 5
 8
With Polyelectrolyte  (1971)
     8             6
     16             6
    24             6
5.1
5.8
5.8
3.2
5.1
           5,8
           4.8
           8.8
.07
.35
.67
.51
.4
              .1
              .1
              .13
98.5
94.1
88.5
85.0
90.5
            98.3
            97.9
            98.6
                                79

-------
       Removal efficiencies for BOD are presented in Table 21. This
table shows a wide range of BOD removals for process performance at
various filtration rates.  Without polyelectrolyte addition at filtration
rates of 24 and 16  gpm/sq ft, BOD removals ranged from 39. 5 to 53.2
percent at an influent concentration of 72 mg/1.  With the addition of
polyelectrolyte, improvement in BOD removals  are evidenced, 65.9 to
78.7 percent at rates of 24 and 8 gpm/sq ft for an influent concentration
of 74.4 mg/1.
                        Table 21
                   SYSTEM PERFORMANCE
                      BOD REMOVALS
                                                Removal
Filtration
Rate
(gpm/sq ft)
Number
of
Samples
Average
Influent
(mg/1)
Average
Effluent
(mg/1)
Plain (1970)

      10
      16
      24
      32
      40
13
14
 8
 6
 8
With Polyelectrolyte (1971)
       8            6
      16            6
      24            6
90.0
72.0
72.0
67.8
90.0
         74.4
         74.4
         74.4
49.0
40.0
49.0
52.0
49.0
           27.0
           27.5
           31.3
43.8
53.2
39.5
23.4
49.8
            78.7
            63.5
            65.9
       As can be seen from Table 22, COD removals also exhibit a
wide range of values, with high removals for the mode of operation using
polyelectrolyte addition.   The range of both BOD and COD removals
obtained from the pilot tests  showed that this process could not be ex-
pected to reduce the dissolved organic contaminants in combined sewer
overflows.   Furthermore, due to the industrial component in the waste-
water flow to the  Southerly Wastewater Treatment Plant, BOD and COD
removals are probably related as much to the nature of the flow on
that particular day as they are to the efficiency of suspended solids
removals.
                                80

-------
                               Table 22
                        SYSTEM PERFORMANCE
                           COD REMOVALS
    Filtration
      Rate
   (gpm/sq.ft.)

   Plain (19 70)

        10
        16
        24
        32
        40
Number
  of
Samples
  13
   5
   6
   6
   4
   With Polyelectrolyte
       (1971)
        8            6
       16            6
       24            6
Average
Influent
(mg/1)
188.0
303.3
483.0
213.0
188.0
             208.9
             201.4
             206.7
          Average
          Effluent
           (mg/1)
             44.0
            136.0
            228.0
             49.0
             83.0
            44.5
            73.5
            70.5
Removal
  72.5
  58.8
  59.6
  77.0
  56.5
                          78.7
                          63.5
                          65.9
       As indicated in the previous section, total phosphate removals by
the screening-filtration process,  with polyelectrolyte addition, are in
the order of 30 to 80 percent.  The amount of phosphate removal is
related to that percentage of total phosphate which is in the suspended
form, and amenable to removal by filtration.

       Fecal coliform removals,  as shown in Table B-l,  in Appendix B,
exhibit a wide range of values.  Removals generally lie in a span be-
tween 14,6 to 87.6 percent with an influent range  of 4.3  to 20.7 x 106/
100 ml. reduced to 2.1 to 4.8 x 106/100 ml. in the effluent.  This is
insignificant for disinfection purposes.  A further disinfection process
should be added in conjunction with the screening-filtration system.
Fecal coliform data presented  on  this  table is based on 1970 test work,
which was prior to the system optimization through polyelectrolyte.
addition.

       Figures 14 and 15 show effluent suspended solids and effluent
BOD levels for various test runs, relating effluent quality levels to
filtration rate.
                               81

-------
No. 40 MESH SCREEN
No. 3 ANTH
No. 612 SAND
   200
    80
^  160
o>
   140
cr
   120
   100
* WITH POLYELECTROLYTE
• WITHOUT POLYELECTROLYTE
 POINTS ARE AVERAGE VALUE
 OF 4 TO 20 GRAB SAMPLES
                      20      30      40

                  FLUX   RATE  (gpm/sq.ft.)
                    50
            SYSTEM  PERFORMANCE
   EFFLUENT  SUSPENDED SOLIDS  QUALITY
                                      FIGURE  14
                   82

-------
No. 40 MESH  SCREEN

No. 3  ANTH

No.  612 SAND
                         WITH POLYELECTROLYTE

                         WITHOUT POLYELECTROLYTE


                         POINTS ARE AVERAGE VALUE

                         OF 4 TO 20 GRAB SAMPLES
o

t-

a:


UJ
o
z
o
o
  LJ

  ID
  _l
  U-
  U.
  UJ
200




 180




 160




 140




 120




 100




 80




 60




 40




 20




  0
        0
                          1970 TEST
                          1971 TES
            10       20       30        40


                FLUX RATE  (gpm/sq. ft.)



             SYSTEM  PERFORMANCE

           EFFLUENT BOD QUALITY
                                                50
                                         FIGURE 15
                     83

-------
       The recommended system is a drum screen (No. 40 mesh screen
element)  followed by a deep bed,  dual  media filter (five feet of No. 3
anthracite over three feet of No. 612 sand).   Polyelectrolyte feed is an
essential and critical part of the system to achieve optimum treatment
efficiencies. Data utilizing coagulants ahead of filtration  (contained in
the previous chapter)  showed inconsistency in treatment efficiencies and
at the present stage of development, polyelectrolyte feed alone appears
optimum.

       To summarize, the propos.ed system, with addition of appropriate
polyelectrolyte, achieved the following treatment performance:

       Filtration Rate   	Average Removals (%)	
       (gpm/sq ft  )      Suspended Solids    BOD   Phosphorus

            8                   96             43        66
           16                   95             40        57
           24                   93             40        46

       The average influent suspended solids concentration ranged  50 to
500 mg/1 and the average influent BOD concentration ranged from 30 to
300 mg/1.  Effluent levels at 24 gpm/sq ft  with polyelectrolyte addition
were 15 mg/1 suspended solids and 22  mg/1 BOD, respectively.
                            84

-------
                           SECTION X

       DEFINITION OF HIGH RATE FILTRATION INSTALLATIONS

General Considerations

       The solution to a community or a municipality's problem of
pollution caused by combined sewer overflows will probably be
resolved, in most cases, through a combination of approaches.  The
first would be maximization and utilization of the  storage capacity of
the sewer system, and its proper regulation, to minimize overflow
frequencies and volume.  Another alternative would be to construct
storage facilities which could detain the high volume, short duration
discharges of combined sewer overflows, and retur-n them to a municipal
sewage treatment facility or to a specially designed combined sewer
overflow facility.  A third possibility would be to  pass the combined
sewer overflow directly through a high rate treatment process such as
the system under study in this research project.  These alternatives or
potential solutions  could be incorporated and utilized  together to form
a composite combined sewer overflow pollution control program.  Sewer
separation is not considered, in general, to be a realistic alternative
approach (15).

       The test results and the mode of test operation are indicative
of treatment efficiencies and effluent levels that could be achieved by
passing combined sewer overflow discharges directly through the
proposed treatment  system.   Thus, the nature of the flow to a proposed
screening-filtration treatment process would be one  of a variable
nature.  Depending upon the overflow hydrograph that  would result from
particular combined sewer overflows, the flow to the plant could  change
slightly or change very drastically.  This, of course, would be related
to the type of downpour experienced and also to the  extent of the
drainage area served by the combined sewer overflow facilities.  For
example, in small areas, the combined sewer overflow hydrograph would
peak very sharply after initial rainfall.   For larger systems, that  is
serving extensive areas, the hydrograph would probably be flatter and
peak at a slower rate. Under these conditions,  it would be more
realistic to consider a high rate treatment process to handle combined
sewer overflows. In other words, the  proposed process  is more
applicable to areas where sewer lag times and other factors tend  to
flatten out the combined sewer overflow  hydrograph such that the
treatment facility would not be subject to an immediate hydraulic shock
load.
                           85

-------
       Due to the nature of combined sewer overflow, that is, a
short duration, high flow volume discharge,  it appears likely that, in
many cases, storage will be incorporated into the overall system or
scheme to control pollution from combined sewer overflows. The
economics, desirability, and merits of  storage preceeding high rate
filtration would have to be specifically and individually evaluated for
each particular case.  For example, if a large storage facility was
provided ahead of the filtration  plant, it would probably be possible
to utilize a smaller filtration plant to accommodate the combined sewer
overflow discharge over a longer period of time.   If storage facilities
are provided, consideration must be given to returning the  greatest
portion of the detained combined sewer  overflow to the municipal
treatment plant,  after the combined sewer overflow has terminated.

       In regard to treatment efficiencies, it is not envisioned that a
substantial improvement in process performance could be achieved if
storage was provided ahead of a filtration facility.  As regards overall
system costs, trade-off values  between straight line treatment through a
high rate filtration facility versus storage and treatment of the combined
sewer overflow through a smaller filtration plant cannot  be effectively
evaluated in a general case due to the variable nature of storage costs.

Straight Line Treatment of Combined Sewage Storm Overflows

       In developing conceptual design and cost  data for the high rate
filtration process to treat combined sewer overflow, a straight line
treatment system has been assumed. That is, the combined sewer
overflow would be directed to the filtration plant, without any inter-
mediate  storage step.  No marked improvement in treatment efficiencies
can be achieved  by storage ahead of the filtration process and, in
addition, this process seems most suitable for metropolitan communities,
where space and costs limitations would preclude significant storage
facilities.  The filtration facility would be sized to treat a certain peak
volume of combined sewer overflow, which would, in turn, be determined
from a study of combined  sewer overflow  hydrographs from a defined
drainage area. In other words,  all overflows in volume  equal  to or less
than the design capacity of the  filtration plant would be handled directly.
Selection of this design  hydrograph for sizing the filtration facility would
require an evaluation of water quality levels desired,  the  probability of
overflows occurring in excess of the treatment capacity  at  the filtration
plant, and the general degree of water  quality control required.

        One possible way to accommodate instantaneous combined sewer
overflow peaks in excess of the capacity of the treatment  facilities would
                               86

-------
be to provide storage for this high flow,  short duration excess.  In
terms of total combined sewer overflow volume,  the bulk of the
combined  sewer overflow would pass directly through the high rate
treatment  process, that is, the filtration plant, and a small portion of
the total volume, as a percent, would  be collected in smaller storage
facilities. After the termination of the combined sewer overflow,  the
water collected in the storage facilities could be returned to the
municipal sewage treatment plant, or directed to the high rate filtration
facilities. Of course, selection of plant capacity to treat combined
sewer overflows at a  particular location, in essence, depends on  a
selection  of a "design" combined sewer overflow hydrograph based on
cost-water quality benefit analyses.  Also, the decision to provide
storage for instantaneous flow volumes in excess of plant capacity is
one which would be determined after a cost-water quality benefit
analysis.

Process Sequence

        Based on the results of the testing  program, a conceptual
schematic of the proposed high rate filtration system for the treatment
of combined sewer overflows is presented  in Figure  16.  Combined
sewer overflows would be conveyed from an automated overflow
chamber,  or chambers (in case the centralized filtration system is for
many overflow points), to a low lift pump station. Before entering
the pumping station,  the combined sewer overflow would pass through
a bar rack (screen) for removal of coarse materials which might cause
problems in the  operation,  maintenance or  wear of the low lift pumps.
In certain locations,  where consistent with local topography and sewer
invert,  a low lift pumping facility may not  be required.

        The combined sewer overflow from the low lift pump station
would enter a treatment building and be delivered to drum type screening
units.   The wastewater would be introduced into the center of the  drum
type screen and would pass through the screening mesh into the influent
channel to the filters. As indicated previously, a gravity type design,
that is, open filtration units, are proposed.  The water would be
introduced at the top of the filter and flow  downward through the filter
bed.  The plant effluent could be discharged by gravity to the respective
receiving  water body.

        Filtered wastewater would serve as a source of water for back-
washing filters after the overflow has  attenuated to a sufficient degree.
The filteration building would be provided with low pressure air blowers
as a source of backwash air.  Backwash pumps would be located in the
filtration  facilities to deliver water to the  filters for backwashing. The
                             87

-------
              COAGULANT- POLYELECTROLYTE SYSTEM5
                                           HYPOCHLORITE. SYSTEM
CO
00
       1NFI.UEWY =O	
     c
     33
     m
-*(- DISINFECTION AT PLANT
 OR IN OTHER RACK ITY
                                                                                  TO
                                                                                 sc.WA.ag.
                                                                                TRE.ATMLNT
                                                                                 PLANT
              BLOWERS
                             BACKWASH PUMPS
         HIGH RATE FILTRATION  INSTALLATION   PROCESS FLOW DIAGRAM

-------
treatment building would also include a control area,  office space, a
polyelectrolyte feeding set-up, and a system for adding hydrochlorite
to filter backwash water for the prevention of slime growth on the filter
media.  The operation of the high rate filtration facility would be
completely automated,  and could be left unattended, except for routine
maintenance and periodic delivery of chemicals.  In full size treatment
systems,  chlorine feed for disinfection could be incorporated into the
filtration  facilities.

        Dirty backwash effluent from the filtration facilities and
screenings would be directed into the interceptor running to the sanitary
sewage treatment facility.  The concentrated solids from the drum
screening units  would be passed first through a grinder,  and then
through a trash basket or classification device to insure that very
coarse, settleable  material is not returned to the sewer system.  Sludge
handling facilities should not be located at the filtration site, as this
would prove very costly.   Centralization of material handling facilities
has always  proved  most economical; as an example,  the Southerly
Wastewater Treatment receives sludges from  another plant in Cleveland.

        Under most conditions of treating combined sewer overflow,  it
would be  possible to backwash the filters  after the storm is over.  For
situations where a  continuous overflow lasts for many hours, two back-
wash handling possibilities appear feasible: first, since the filtration
facilities are  located above grade, it is probable that the backwash
from the filtration plant could be discharged downstream of the combined
sewer overflow point.  This could be accomplished by utilizing the
available static head (water level) in the filtration plant, even though
this portion of the combined sewer would probably be flowing full.
Another more remote possibility would  be to return the filter backwash
effluent to the combined sewer upstream of the  overflow  point. Under
this alternate, a certain percentage of backwash solids would be
transported to the sewage treatment facility and the remainder to the
filtration  plant.  The rationale behind this second  alternate is that
when backwash is required,  it would probably be in the latter stages of
a storm when  the flow volumes and solids  levels entering the filter
plant would be reduced.  Therefore,  the filter plant could probably
accept  the additional solids material and flow without any major
problem.

        To insure smooth operations even in areas  with rather  mild sewer
slopes, the material from the screening unit, as shown in  Figure 16  is
passed through a grinder to minimize solids size,  before being discharged
with the filter backwash into the combined sewer.  Since the proposed
                               89

-------
screening filtration system would normally be preceeded by a low lift
pumping facility equipped with a traveling screen (rack), coarser
materials,  which could possibly cause sedimentation problems in
combined sewers having flat or  mild slopes, would be probably removed
at the screening unit.  The nature of the material discharged from the
proposed filtration system in the filter backwash would not cause any
serious problems of deposition in the combined sewer systems.  Also,
the intermittent flushing nature  of the  backwash flow would tend to
disturb  any accumulated solids  in these sewers.

Mode of Operation

        The flow to the filtration facility for treating combined sewer
overflows would be of a variable nature.  It would gradually build  up,
then reach a hydraulic peak, and then recede gradually. Two possible
methods of operation appear feasible.   One method of operation, as is
proposed for a flotation system  in the  treatment of combined sewer
overflows (22), would be to operate the filtration units in sequence,
based on design flow rate.  If a filtration plant had 8 filters designed
to accomodate  100 MGD, or a design rate of 12.5 MGD per filter,  they
would be operated, in turn, as the  flow built up.  For example, if  an
overflow was 12.5 MGD, only one  filter would be operating,  and as the
flow built up higher, additional  filters would be turned on after the
design rate of the filters in operation was exceeded.  The operating unit
would remain on line and function at decreasing filtration rates as the
filter bed became gradually clogged until filter head loss reached a pre-
set value.  The filter would then be ready for backwas-hing.  Filtration  rate
declining from a maximum value to lesser values does not appear to be
cause for any concern,  as this practice is utilized in many water
treatment plants (23), where filters are initially run at high rates,  and
then as the head loss builds  up within the filter, the rate is decreased
and less water is filtered. Actually, it has been reported that this mode
of operation, commonly referred to as  "declining rate filtration"  in the
potable water treatment field, results  in a better quality effluent than
operating at a constant rate for  the duration of the filter run.

        An alternate method of filtration would be to equally divide
whatever flow enters the filtration  facility among the various  filter
units.   This is  the flow control  system that has been successfully
utilized in a gravity industrial wastewater treatment  plant in the
Midwest (10).  In effect, at the beginning of the combined sewer
overflow,  each filter unit would probably be operating below design
rate, and as the storm progressed the  filtration rate on each unit would
build and approach the design loading, depending on the volume of the
                                90

-------
combined sewer overflow.  After the hydraulic peak,  the filtration rate
on each filter unit would decrease as the storm overflow subsided.  This
second mode of operation would be accomplished by flow indicators
and controllers on the effluent end of each filter unit.  Essentially, each
filter unit flow  indicator sends a signal to a central controller, which
sums up  all flow signals from all filters,  divides the flow signal by the
number of units, and returns a signal to each individual filter controller,
assigning each individual unit its respective percentage of the flow.

       In regard to the second mode of operation,  some legitimate
questions may be raised as to whether solids removed at low filtration
rates during the early stages  of the combined sewer overflow will be
sheared off and would show up in the effluent from the  filter during
operation of the filter at peak flow rates and filtration rates.

       The overall percent reductions of  suspended solids experienced
during a  combined sewer overflow in a full size facility would be greater
than evidenced from the constant-flow test work (see Figure 8) due
to the effect of reduced filtration rates as the storm flow subides. If
it is workable, the second mode of operation might provide a greater
overall percent reduction of contaminants by maintaining minimum
filtration rate for the entire combined sewer  overflow.  The optimum
method of operation can only  be conclusively verified through actual
operation in a demonstration plant or full sized facility.

       It must be mentioned, however, that  after the hydraulic peak of
the overflow  occurs (design for peak at 24 gpm/sq  ft),  the flow to the
filtration facility would decline.  When evaluating and translating test
data into design parameters,  it must be remembered that the filtration
rate of a plant would decline  after the hydraulic peak of the sewer over-
flow was reached,  and as such, constant flow test work parameters
cannot be directly applied to  engineering designs,  without considering
the nature of the process  operation, that  is,  filtering at varying rates
throughout the duration of the sewer overflow.

       For filter backwashing,  two types of process control should be
considered: the first parameter would be total head loss through filter
bed and  the second would be  effluent suspended solids concentration.

       For measuring the filter head loss, each filter would be equipped
with a differential pressure transmitter to continuously sense  the loss
of head across the filter and transmit a pneumatic  signal linearly
proportionate to this head loss to a central control panel.  When the
filter head loss would reach a preset value, the differential pressure
switch associated with the filter would be actuated. A contact in this
                                91

-------
switch would open in a stepping switch circuit and the filter would start
to backwash.

       An alternate filter backwash control could be achieved with an
effluent suspended solids monitor.  A continuous reading, light scatter
type suspended solids meter would be installed in each filter effluent
pipe to continuously measure the suspended solids concentration and
transmit the reading  to a recorder at a central control panel. When
the filter breakthrough would suddenly take place and the suspended
solids concentration indicator would reach a  preset level, then a micro
switch would be activated and an alarm would be initiated.  The
operator would check the filter performance condition and start to
backwash the  filter.

Solids Handling Aspects

       As indicated  previously, the backwash from the filtration plant
and the material removed by the 40 mesh screening units should be
delivered to the  sanitary sewerage system for subsequent treatment.
Insofar as the high rate filtration installation would be designed as a
highly automated, unattended facility, the solids or sludge  from this
proposed wastewater treatment system should be handled at another
location, specifically the nearest municipal sewage treatment plant.

       If, for some reason, delivering the backwash into a  sewer carrying
wastewaters to a municipal wastewaters plant were not feasible, some
intermediate form of  solids compaction and dewatering could be
incorporated into the proposed high rate filtration treatment  system.  One
possibility would be to provide settling basins for the filter backwash,
which would remove  backwash solids from the backwash water.  The
overflow from  these  basins would be directed or returned into the
filtration facility. The compacted underflow  could be pumped to the
nearest combined sewer which would carry the sludge material to the
sewage treatment plant.  The sludge volumes  that would result from
treatment of a significant discharge are such that trucking of compacted
sludge seems  to be a remote and very unlikely possibility.

       Taking the solids handling process one step further, in addition
to providing backwash  sedimentation and compaction basins at'the
filtration site, solids dewatering facilities could also be provided.
Assuming that this sludge material would have dewatering properties as
good as primary sewage, the sludge could be handled by vacuum filter or
centrifuge to produce a desirable dewatered cake.  The dewatered cake
would have to be conveyed by truck to an appropriate incineration plant
                                92

-------
of the nearest sewage treatment plant for final disposal. If ultimate
disposal of solid materials removed from combined sewer overflows was
required at the treatment site, some type of incineration process could
probably be utilized.  As the solids handling aspects of a proposed
combined sewer  overflow treatment process  becomes more involved and
complicated, so does the project cost and the effort in manpower that
is required to handle these facilities.  Further study of backwash sludge
characterization, such as sludge density, biodegradability, nutrient
content, methods of dewatering and iinal disposal of the sludge should
be taken into consideration.

        The proposed treatment system,  equipped with backwash
sedimentation basins,  could function as an  automated and unattended
treatment facility, which is desirable considering the nature and
application of the proposed system.  If  additional solids handling and
processing facilities were to be incorporated into the proposed treatment
system, it is unlikely that the facility could be left unattended and the
overall  treatment process would become much more  expensive.

Conceptual Design

        A full evaluation and study of a  proposed  treatment system requires
that conceptual engineering work be developed in order  to define,
determine and evaluate integral elements of the treatment system,
and to provide a basis for developing some realistic cost figures.  Also,
physical details and arrangements of any proposed treatment installation
are important in  determing whether or not the "public acceptance factor"
would be favorable  for such a treatment facility.  Certain processes and
waste treatment  systems can be housed and arranged economically so
that they can  be located in many areas without public outcry for
architectural, aesthetic or environmental reasons.  For  example, trucking
of sludge solids from a treatment facility or exhaust gases and particulates
from a sludge incinerator might cause public opposition.

        For conceptual design purposes, the low lift pumping facility and
the treatment  plant  have been incorporated into one site.  Centralization
and integration of pumping and treatment facilities  is generally
desirable, although in many cases it is not feasible.  For example, land
availability,  sewer invert, topography,  and a number of physical factors
may make this situation uneconomical or unfeasible. In addition, a
centralized high rate filtration installation to accommodate combined
sewer overflow discharges from various overflow  points may receive flows
from a number of pumping stations located at different points throughout
the combined  sewer system.
                                 93

-------
       A slab on grade type construction is assumed for conceptual
design purposes.  For the treatment portion of the system this is a
realistic assumption, although determining the features of a low lift
pump station is very uncertain, particularly due to an assumed sewer
invert.  As shown in the  following section on cost data, the
evaluation of the treatment plant is considered separately from the
pumping facility, since integrating low lift pumping  costs with
treatment costs is not an accurate or efficient approach.  Pumping and
wastewater conveyance costs are too variable to be  considered  in
terms of developing generalized cost data for a particular process or
treatment system.

       In developing generalized conceptual designs, effort has been
centered on plant sizes ranging from 25  to 200 MGD design
capacity.  This range covers most area of potential application
and provides a sufficient basis for evaluating the merits and cost-
efficiency factors of a high rate filtration system. As a general order
of magnitude reference, a 200  MGD filtration facility could accommo-
date the flow from a  96-inch diameter sewer.

       Treatment plant features are delineated and defined on Figures
16 through 23.  The facilities shown are designed for filtration
rate of 24 gpm/sq ft, with  polyelectrolyte addition for optimum  suspended
solids removal.  These particular wastewater treatment facilities would
be capable of hydraulically accepting an additional wastewater  volume of
approximately 20 percent greater than the design rate of the plant. As
in most,  or normal, wastewater treatment designs, plant hydraulic
capacity is generally set somewhat higher than the plant capacity
dictated  by process considerations.

       As  shown in Figure  16, which was discussed earlier,  the  major
units of the proposed treatment system includes drum screens and high
rate filters.  Additional features include: backwash pumps, backwash
air blowers, which are also essential to the process operation.  A
polyelectrolyte system and a hypochlorite system are also incorporated
into the treatment plant.  Polyelectrolyte will provide for optimum plant
operation in regards to removal efficiencies.  The hypochlorite  system
is required to disinfect the backwash water so that slime growths do  not
occur in  the filter media. This system could also be utilized, if
properly  sized, to provide chlorine for disinfection of the combined sewer
overflow.  Low lift pumping facilities and a bar screen for pump
protection  are also shown on this drawing.  Depending on the nature  and
application in each particular area, the bar screen and low lift  pumps
might be located at a site far removed from the plant.
                                 94

-------
       Figures 17 and 18 show general arrangements for filtra-
tion plants designed to accommodate 25 and 50 MGD of combined sewer
overflow.  The same basic arrangement or module is used in developing
both of these plants. For example, the major difference between the
50 MGD  plant and the 25 MGD plant is that additional filters and drum
screens are added, while the basic arrangement and features of the
facilities remain the same.   This basic treatment arrangement or module
can be developed up to a capacity of 100  MGD, as  shown on both of
these drawings.  The ultimate development of this treatment module
would include 16 filter units,  each filter being 12 feet by 16 feet.

       As  shown in  Figure 19, the facility consists of three basic
areas. Starting from left to right on the drawing, the first portion of the
proposed facility can be  described as a pumping station, housing low
lift pumping units  and a bar rack (screen), to lift combined sewer
overflows into the treatment plant. The second area, or head end of
the treatment plant,  houses the drum screen units, which treat the flow
prior to entering the filters.  These two areas are normally referred to
as the control building portion of the high rate filtration installation.
The third section of this  facility contains the high rate filtration units,
which are the  major treatment elements.

       As  indicated in these figures,  the facility arrangements and
equipment  layouts cannot be described as skimpy, and are the type  of
arrangements that would  be required in many large municipal plants.
Referring to these  figures, the first level in the control building  portion
of the treatment facility includes the variable speed low lift pumping
installation, the bar rack (screen), the chlorine and polyelectrolyte feed
equipment, and the backwash pumps, which extract their source of
water from the plant effluent.   The upper level of the plant includes the
drum screening units, electrical and control areas, and  space allocations
for office,  service areas, etc.

       Briefly,  the flow  sequence begins with the combined sewage storm
overflow being conveyed by gravity to  the treatment facility.  It  first
passes through a bar rack (screen) for  removal of coarser materials which
might impede pump operation.  The combined  sewage storm overflow is
then directed by the low  lift pumps up  to a central distribution channel,
whence the water  is fed by gravity to the rotating drum screening units.
The water enters the center of the screens and flows outward through the
circumference.  Solids are retained on the screen surface and as the
retained  solids reach the top or highest point on the screening
circumference, they are removed by high pressure water sprays.  The
screened effluent  than flows by gravity into a central filter influent flume.
The water is distributed into each of the high rate filters, and subsequently
after filtration,  is discharged by gravity to an effluent sewer.

                                 95

-------
                            PUMP
                                    TREATMENT
ID
05
       POUYELECTROLVTE
          TANKS
       COMBINED SEWER
       OVERFLOW      |
       DIVERSION SEWER
FUTURE ULTIMATE EXPANSION
   TO IS FILTERS
 (IOO MGO CAPACITY)
                                         PLAN
            HIGH  RATE FILTRATION  INSTALLATION - 25  MGD  CAPACITY

-------
                             PUMP
             TREATMENT
to
     o
     c
     3)
     m
     oo
                ®
                       -SPACE ALLOCATED FOR ELECTRICAL ROOM.
                      CONTROL ROOM. OFFICE. AND SERVICE AREA
PLAN AT UPPER FLOOR EL. 25'±
    BUILDING AREA FOR IOO MGD •
                           .J
                                          PLAN
                                                                               FUTURE ULTIMATE
                                                                                EXPANSION
                                                                                TO 16 FILTERS
                                                                               (100 MSP CAPACITY)
             HIGH RATE FILTRATION  INSTALLATION - 50 MGD  CAPACITY

-------
                          PUMP
                     TREATMENT.
CD

CO
          EL.42'±
                                         DRUM SCREEN
                                                             ROOF HATCH
    o
    c
    33
    m


    CO
    PLANT BY-PASS SEWER
                                   BACKWASH PUMPS
COMBINED SEWER

OVERFLOW

DIVERSION SEWER
                                 ELEVATION

      HIGH  RATE  FILTRATION  INSTALLATION  —  50 MGD CAPACITY

-------
       Figure 20 shows a general arrangement for a 100 MGD high rate
filtration installation. The basic filter size for this treatment system
is 18 feet by 20 feet.  As indicated on this drawing,  the plant could be
expanded  to a capacity of 200  MGD, with a total of 16 filters. A
longitudinal section through the 100 MGD high rate filtration facility
is shown in Figure 21.  Basic arrangements and area functions are
similar to the two previously discussed plants (25  and 50  MGD). This
particular treatment plant would be equipped with four drum screens,
each 11 foot 6 inches in diameter by 7 feet long.  There are eight
filter units, with provision for expansion to 16, if this was desired in a
future  stage.  As in the other filtration plant arrangements, a truck
driveway is provided across the bottom floor of the plant to provide
easy access for vehicles and chemical delivers.

       Figure 22 shows  a typical cross section of the filtration portion
of the  treatment plant with the filtration units arranged symetrically
about the  center line of the filter bay. Water is fed through the filter
influent flume then into each individual filter gullet and subsequently
into the filter media bed.  The filtered water flows downward through
the media and filter bottom and out the filter effluent  pipe, dropping
into the plant effluent flume.  The filter arrangement as shown, is some-
what similar to a gravity filtration arrangement common to many potable
water treatment plant, except that the depth of the media is much greater.
The  effluent flume is extended under the entire width  of the filter bay
to provide for sufficient  backwash water storage.  The treated effluent
then flows by gravity to  the appropriate water body.

       Two access areas are  provided, one along the top of the filter
and  one between the filter pipework, near the bottom  of the filter,
which  offers an access corridor for servicing and maintaining  the
automatic valves and flow tubes  that are in integral part of each filter
unit.  Roof hatches are provided  at the top of the filter enclosure,
appropriately located in  the center of each filter unit. Removable back-
wash troughs permit media changing via an overhead crane, with access
through roof hatches.  All  the valves integral to the filtration operation
would  be  automated so that a full time operator would not be required.

       As indicated previously,  the gravity design has a number of
advantages and optimal features. Perhaps two of the most important
are: first, that an open type filter unit provides an access for gas
release through the  media  bed, a possible  problem due to materials
of domestic or industrial origin in the combined sewer overflow; and
secondly, with the gravity type arrangement, an individual filter
unit can be easily isolated from  the remainder of the filters,  without
impeding  filtration operation or requireing a temporary plant shutdown for
maintenance.
                               99

-------
                      PUMP
                            TREATMENT
O
O
   2)
   CD
   c.
   30
   m

   ro
   o
                                                                      FUTURE ULTIMATE

                                                                       EXPANSION

                                                                      TO \
-------
                          PUMP
                                             DRUM SCRE.ENS
           EL.42'±
                1_
           EL.25'i -j
           EL. 13 l

      SAR^RACK.

   PLANT BY-PASS
      SEWER ~QT
    ^COMBINED SEWER
T|   OVERFLOW
—   DIVERSION SE.WER
m
ro
                                                                            HATCH
                                       . ^FILTER INFLJUENT FLUME.
                                   No. I   ' ,  No.3   ;!  No.5  :' N..7
                                      HW|L<-i4'»    •
                                                        FILTER EFFLUENT BASIN
                                                                        LWL EL.-IOS
                                                                               _£'
                                                                                EL. 3! t
                                                                                 rWL. 2O
                                                             -GR E.L.Ot
LOW LIFT
 PUMP
 ••PLANT EFFLUENT SEWER

L BACKWASH PUMPS
                                   ELEVATION
   HIGH  RATE  FILTRATION  INSTALLATION  —   100   MGD  CAPACITY

-------
3)
o
c
33
m

no
ro
      EL.22.O
     GR.E.L.O'
                                                            ROOF HATCH
e.L.<->n't
                                                                OPERATING

                                                               r- WATER LEVE.L

   HIGH  RATE FILTRATION  INSTALLATION - TYPICAL  FILTER SECTION

-------
       Figure 23 is a rendering of a typical high rate filtration
installation.  This particular plant would have a treatment capacity of
 100 MGD, and is the ultimate development of the 25 MGD treatment facility
The proposed facilities can be enclosed so that the nature and functioning
of the equipment inside the facility would not be readily apparent.  With
this proposed arrangement, plants utilizing the high rate filtration process
in facilities of similar design to the one shown in  Figure 23 could be
easily adapted and located in varying parts of a municipality,  without
interfering with the architectural or aesthetic quality of the neighborhood.
Perhaps the most significant advantage of high rate filtration of combined
sewer overflows, in addition to its good removal of a suspended
material and other contaminants, is  the limited space required for a facility
with such a large treatment capacity.  The area requirements for high rate
filtration plants treating combined sewer overflows are shown as follows:

                                      Area Requirements
         Plant Capacity               Desiqn @ 24 gpm/sq ft
             (MGD)                        ( sq ft )   	
                25                         3,000
                50                         4,600
               100                         9,300
               200                        16,500

       The area requirements of a high rate filtration treatment system
would approximate 20 percent or less, of the spare requirements
for an alternate flotation treatment system (design at 3 gpm/sq ft
surface loading) (22).
                         103

-------
OJ
HIGH RATE FILTRATION INSTALLATION - RENDERING

-------
                          SECTION XI

                       COST ESTIMATES

Cost of High Rate Filtration

       In developing unit cost estimates for a particular wastewater
treatment process, it is necessary to make a number of assumptions
defining a treatment  plant which would be typical for many conditions.
This has been accomplished in the preceeding section. Depending on
the location, cost data developed for a particular treatment plant could
be either high or low.  This approach provides general order of
magnitude information which can be utilized to determine what systems
deserve consideration as potential treatment processes to solve the
problem of combined sewer overflows.

       As noted in the preceeding section, general designs were
developed for a treatment facility to accommodate  combined sewer
overflows,including  the integration of a low lift pump  station  with the
treatment essentials.  In arriving at representative cost data that can
be compared with other potential solutions for the  treatment of
combined sewer overflows, the cost of the influent pumping station has
been seperated from  the total cost of the facility,  so that the  costs will
represent costs of the treatment facilities.  Wastewater collection and
conveyance  costs, either to or from the treatment facilities, would
probably be  extremely variable from one installation to another and
would apply to most  processes considered.  The treatment plant costs
presented in the summary curves contained in this section can be
compared with alternate processes or engineering  schemes, with
associated cost-benefit relationships, for the control  of pollution from
combined sewage storm overflows.

       Cost estimates for filtration facilities for treating combined
sewage storm overflows are presented for 25 to 200 MGD
capacity plants.  This range covers most areas of potential application.
The engineering conceptual design shown in the previous  section was
based on a filtration facility utilizing a design rate of 24 gpm/sq ft,
including polyelectrolyte addition .  Total construction costs
of a filtration facility for treating combined sewage storm over-
flows are presented  in Figure 24.   Capital costs data  for the
filtration plant includes:  the cost of equipment,  installation
and construction costs, and a 12 percent allowance for contingencies,
plus a 10 percent allowance for  engineering and administration of the
proposed construction.  Detailed cost breakdowns, estimated for
25 to 200 MGD plant,  including cost data for  low  lift pump station are
                             105

-------
    5.0
O
O
h-

O_

<

O
   4.0
   5.0
   2.0
    1.0
    0



\
\
\
\
\



/













X
\
NOTES

CAPITAL
COST— %
\




-
^



/
\/
s



-UNIT
COST

(.FILTER DESIGN RATE! 24gpm/sqft
2. COSTS INCLUDE DRUM SCREEN
AND FILTRATION PLANT
EQUIPME

.NT AND STR


UCTURE.


\j\s
4O
~\J


30



Of~i
C\J
10



0
D 50 100 150 200
              DESIGN  CAPACITY (MGD)
o
o
o

Iff


H
co
o
ESTIMATED  CAPITAL COST Vs  DESIGN CAPACITY
                                      FIGURE 24
                     106

-------
presented in Tables 23 through 26.

       Estimated total construction costs  (Figure 24) of a filtration
plant for treating combined sewer overflows range from $830,000
for the 25 MGD capacity to $3,754,000 for 200 MGD capacity at
design rate of 24 gpm/sq ft.

       Figure 25 presents total annual costs for  a high rate filtration
plant. These costs are based on 300 hours of facility operation per
year.  Other criteria used in developing  the annual cost are:

       a.   Interest at six percent for 25 years.

       b.   Maintenance at three percent of mechanical equipment
            cost and at two percent of electrical and instrumentation
            cost.

       c.   Labor at $15,000 per man year, including overhead and
            benefits.

       d.   Chemical application of polyelectrolyte to filter influent at
            1.0 mg/L and application of  15 mg/1  chlorine to filter
            backwash.

       e.   Electricity at $.03 per Kw -  Hr.

       Estimated annual cost data ranges  from $97, 270 per year for a
25 MGD  capacity plant to $388,210 per year for a 200 MGD capacity plant.
Annual treatment costs utilizing the high rate filtration process are due
primarily to interest and amortization charges, and are less affected by
the volume of combined sewer overflow to  be treated annually.  Estimated
detailed cost breakdowns for annual operating and maintenance are
presented in Tables 27 through 30.

       The  most significant  costs associated with the high rate filtration
facility are  reflected in interest and amortization payments,  as the
operating costs are minimal due to the automated operation of the
facility and the relatively small number  of hours  of operation per year.
As is evidenced from the previous section, the filtration plant design
and the associated housing of process units, is  one  that would be
suitable for a cold climate.  In warmer areas, and in location where
local engineering  practices permit a more compressed equipment
management, the enclosure  could be taken off the filtration facility
and much of the related process equipment.  It may also be possible to
                             107

-------
                           Table 23

               SUMMARY OF ESTIMATED PROJECT COSTS*

                  FOR 25 MGD TREATMENT PLANT

                              PEAK FILTRATION RATE DESIGNED

                                24 gpm/sq ft     16  gpm/sq ft

I.  PUMPING STATION

   Excavation and Backfill        $    3,800       $     3,800

   Reinforced Concrete               38,500           38,500

   Building                          50,000           50,000

   Bar Screen                        20,000           20,000

   Pump                             80,000           80,000

   Piping                             5,000            5,000

   Heating and Ventilating            10,000           10,000

   Electrical                         40,000           40,000

   Plumbing,Lighting,Interior &etc     20,000           20,000

   Sub-total                     $  267,300       $   267,300

   Construction Contingency          32,000           32, OOP

   Sub-total Construction Cost    $  299,300       $   299,300

   Engineering and Administration      30,000           30,000

   Project Sub-total,
       Conveyance Portion       $  329,300       $   329,300
                             108

-------
                   Table  23 (continued)






II. TREATMENT PLANT
Excavation and Backfill $
Reinforced Concrete
Building
Drum Screen
Filter Media & Filter Bottom
Filter Backwash Pump
Air Blower
Piping
Polyelectrolyte Feed
Chlorination Equipment
Heating and Ventilating
Electrical
Instrumentation
Plumbing , Lighting , Interior & etc .
Sub-total $
Construction Contingency (12%)
Sub-total Construction Costs $
Engineering & Administration (10%)
Project Sub-total
Treatment Portion $
TOTAL PROJECT COSTS $1,
8,000
142,000
81,000
70,000
20,000
20,000
20,000
110,000
20,000
30,000
15,000
50,000
52,000
40,000
678,000
81,000
759,000
71,000
830,000
159,300
$ 11,000
202,000
92,000
70,000
30,000
20,000
20,000
160,000
20,000
30,000
15,000
50,000
70,000
45,000
$ 835,000
100,200
$ 935,200
93,500
$1,028,700
$1,358,000
*  Engineering News Record Construction Cost Index = 1470
                            109

-------
                           Table 24

              SUMMARY OF ESTIMATED PROJECT COSTS*

                  FOR 50 MGD TREATMENT PLANT

                              PEAK FILTRATION RATE DESIGNED
                                24 gpm/sq ft    16  gpm/sq ft

I.  PUMPING STATION

   Excavation and Backfill        $    3,800      $    3,800

   Reinforced Concrete               38,500          38,500

   Building                          50,000          50,000

   Bar Screen                        20,000          20,000

   Pump                            140,000          140,000

   Piping                            10,000          10,000

   Heating and Ventilating            12,000          12,000

   Electrical                        60,000          60,000

   Plumbing,Lighting,Interior & etc.   25,000          25,000

   Sub-total                     $  359,300      $   359,300

   Construction Contingency          43, 100          43, 100

   Sub-total Construction Cost    $  402,400      $   402,400

   Engineering and Administration       40,200          40,200

   Project Sub-total,
       Conveyance Portion       $  442,600      $   442,600
                              110

-------
                       Table 24 (continued)





. TREATMENT PLANT
Excavation and Backfill $
Reinforced Concrete
Building
Drum Screen
Filter Media and Filter Bottom
Filter Backwash Pump
Air Blower
Piping
Polyelectrolyte Feed
Chlorination Equipment
Heating and Ventilating
Electrical
Instrumentation
Plumbing, Lighting, Interior & etc.
Sub-total $ 1
Construction Contingercy(12%)
Sub-total Construction Costs $1
'Engineering & Administration (10%)
Project Sub-total,
Treatment Portion $1
. TOTAL PROJECT COSTS $1
11,000
252,000
102,000
140,000
40,000
20,000
20,000
212,000
20,000
30,000
18,000
60,000
90,000
50,000
,065,000
128,000
,193,000
119,300
,312,300
,754,900
$ 14,000
367,000
122,000
140,000
60,000
20,000
20,000
314,000
20,000
30,000
18,000
60,000
120,000
55,000
$1,360,000
163,200
$1,523,200
152,300
$1,675,500
$2,118,100
*   Engineering News Record Construction Cost Index- 1470
                             ill

-------
                           Table 25

               SUMMARY OF ESTIMATED PROJECT COSTS*

                  FOR 100 MGD TREATMENT PLANT

                              PEAK FILTRATION RATE DESIGNED
                               24  gpm/sq ft     16  gpm/sq ft

I.  PUMP STATION
Excavation and Backfill $
Reinforced Concrete
Building
Bar Screen
Pump
Piping
Heating and Ventilating
Electrical
Plumbing , Lighting , Interior & etc .
Sub-total $
Construction Contingency
Sub-total Construction Cost $
Engineering & Administration
5,300
75,000
112,000
40,000
255,000
15,000
20,000
150,000
30,000
702,300
84,300
786,600
78,700
$ 5,300
75,000
112,000
40,000
255,000
15,000
20,000
150,000
30,000
$ 702,300
84,300
$ 786,600
78,700
   Project Sub-total,
       Conveyance  Portion        $   865,300       $  865,300
                             112

-------
                      Table 25 (continued)
TREATMENT PLANT (continued)
Excavation and Backfill $
Reinforced Concrete
Building
Drum Screen
Filter Media and Filter Bottom
Filter Backwash Pump
Air Blower
Piping
Polyelectrolyte Feed
Chlorinaticn Equipment
Heating and Ventilating
Electrical
Instrumentation
Plumbing , Lighting , Interior & etc .
Sub-total $1,
Construction Contingency(12%)
Sub-total Construction Cost's $2,
-Engineering & AdministrationQ-0%)
Project Sub-total,
Treatment Portion $2 ,
TOTAL PROJECT COSTS $3,
20,000
470,000
210,000
280,000
80,000
36,000
36,000
416,000
30,000
45,000
30,000
90,000
95,000
70,000
908,000
229,000
137,000
214,000
351,000
216,300
$ '20,600
715,000
250,000
280,000
120,000
36,000
36,000
620,000
30,000
45,000 '
30,000
90,000
130,000
80,000
$2,488,000
298,600
$2,786,600
278,700
$3,065,300
$3,930,600
*  Engineering News Record Construction Cost Index = 1470
                              113

-------
                        Table 26

           SUMMARY OF ESTIMATED PROJECT COSTS*

               FOR 200 MGD TREATMENT PLANT

                           PEAK FILTRATION RATE DESIGNED

                            24  gpm/sq  ft     16  gpm/sq fL
I. PUMPING STATION
Excavation and Backfill
Reinforced Concrete
Building
Bar Screen
Pump
Piping
Heating and Ventilating
Electrical
Plumbing, Lighting , Interior &
Sub-total
Construction Contingency
Sub-total Construction Cost
Engineering & Administration

$ 10,700
150,000
224,000
80,000
480,000
25,000
30,000
330,000
etc. 60,000
$1,389,700
166,800
$1,556,500
155,600

$ 10,700
150,000
224,000
80,000
480,000
25,000
30,000
330,000
60,000
$1,389,700
166,800
$1,556,500
155,600
Project Sub-total,
    Conveyance Portion       $1,712,100      $1,712,100
                         114

-------
                      Table 26 (continued)





 .  TREATMENT PLANT
Excavation and Backfill $
Reinforced Concrete
Building
Drum Screen
Filter Media and Filter Bottom
Filter Backwash Pump
Air Blower
Piping
Polyelectrolyte Feed
Chlorination Equipment
Heating and Ventilating
Electrical
Instrumentation
Plumbing, Lighting, Interior & etc.
Sub-Total $3
Construction Contingercy(12%)
Sub-total Construction Costs $3
Engineering & Administration (10%)
Project sub-total,
Treatment Portion $3
TOTAL PROJECT COSTS $5
40,000
800,000
400,000
480,000
160,000
36,000
36,000
548,000
50,000
- 65,000
42,000
130,000
170,000
90,000
,047,000
365,600
,412,600
341,000
,753,600
,465,700
$ 52,000
1,120,000
470,000
480,000
240,000
36,000
36,000
815,000
50,000
65,000
42,000
130,000
240,000
100,000
$3,876,000
465, 100
$4,341,100
434,100
$4,775, 100
$6,487,200
*  Engineering News Record Construction Cost Index = 1470
                             115

-------
    500
    400
o
o
g
•w-
cs>
O
O

J-
z
Ixl
UJ
a:
I
    30O
    200
    100



/
/


/
/
NOTES
1. FILTRATIC
2ANINI IAI I
. MIMliUJML *
3.COST INC
MAINTAN<
ELECTRIC

/
/
IN RATE: 24
DPERATION!
LUDEiAMOR"
:E,CHEMICA
;iTY AND LA

/

gpm/sq ft
300hrs/yr -
flZATION
LS, POWER,
BOR.
              50     100     150

              DESIGN  CAPACITY (MOD)
200
    ESTIMATED  ANNUAL TREATMENT  COST
        Vs  DESIGN  CAPACITY
                               FIGURE  25
                   116

-------
                            Table 2.7

                SUMMARY OF ESTIMATED ANNUAL COSTS*

                   FOR 25  MGD TREATMENT PLANT

                               PEAK FILTRATION RATE DESIGNED
                                 24 gpm/sq it
 I. AMORTIZATION

   6 percent Interest Rate for
        25 years

 n. OPERATING COSTS

   Labor (Includes Overhead
          & Benefits)

   Maintenance

        Mechanical Equipment
        (3%  of Equipment Cost)
$   65,000
    20,000
$    5,250
        Electrical & Instrumentation
        (2% of Equipment Cost)     $     2,040

        Piping (1% of Piping Cost)  $     1,100

    Utilities

        Electrical($. 03/KWH)      $       600

    Chemicals
        Chlorine*1l5 mg/1)        $       100

        Polyelectrolyte(0,5 mg/1)         3,180

    Operating Costs Sub-total      $    32,270

    Total Annual Costs             $    97,270
                 16  gpm/sq ft
$   80,000
$   20,000
$    5,250


$    2,400

$    1,600
                 $


                 $
       600


       100

     3,180
                 $    33,130

                 $   113,130
 *  For Treatment Fortion Annual Cost
**  For Filter Backwash
                              117

-------
                            Table 28

               SUMMARY OF ESTIMATED ANNUAL COSTS*

                   FOR  50   MGD TREATMENT PLANT

                                PEAK FILTRATION RATE DESIGNED
                                 24 gpm/sq ft
 I. AMORTIZATION

   6 percent Interest Rate for
        25 years

II. OPERATING COSTS

   Labor (Includes Overhead
          & Benefits)

   Maintenance
$  102,700
        Mechanical Equipment
        (3% of Equipment Cost)     $

        Electrical & Instrumertation
        (i% of Equipment Cost)     $

        Piping(1% of Piping Cost)  $

    Utilities

        Electrical($.02/KWH)      $

    Chemicals

        Chlorine**( 15 mg/1)        $

        Polyelectrolyte(0.5mg/l)    	

    Operating Costs Sub-total      $

    Total Annual Costs            $
    20,000



     7,430


     3,000

     2,120



     1,200



       200

     6,350
    40,300

   143,000
                  16  gpm/sq ft
$  131,000
$   20,000



$    7,440


$    3,600

$    3,140



$    1,200



$      200

     6,350

$   11,93C

$  172,930
  *  For Treatment Portion Annual Cost.
 **  For Filter Backwash.
                              118

-------
                           Table 29
                SUMMARY OF ESTIMATED ANNUAL COSTS*
                   FOR 100 MGD TREATMENT PLANT
                               PEAK FILTRATION RATE DESIGNED
                                 24 gpm/sq ft
I.  AMORTIZATION

   6 percent Interest Rate for
       25 years

II. OPERATING COSTS

   Labor(Includes Overhead
         & Benefits)

   Maintenance
$  184,000
$   35,000
       Mechanical Equipment
       (3% of Equipment Cost)
$   13,710
       Electrical & Instrumentation
       (2% of Equipment Cost)     $

       Piping(1% of Piping Cost)   $

   Utilities

       Electrical ($.02/KWH)       $

   Chemicals

       Chlorine **(15mg/l)         $

       Poly electrolyte (0.5 mg/1)   	

   Operating Costs Sub-total

   Total Annual Costs
     2,400



       400

    12,720
$   72,100

$  256,100
                  16 gpm/sq ft
$  239,000
    35,000
$   13,710
3,700
4,160
$
$
4,400
6,200
$    2,400



$      400

    12,720

$   74,830

$  313,830
 *  For Treatment Portion Annual Cost
**  For Filter Backwash
                             119

-------
                            Table 30

            SUMMARY OF ESTIMATED ANNUAL COSTS*

               FOR 200 MGD TREATMENT PLANT

                               PEAK FILTRATION RATE DESIGNED
                                24 gpm/sq  ft     16 gpm/sq ft
I.  AMORTIZATION

   6 percent Interest Rate for
       25 years

II. OPERATING COSTS

   Labor (Includes Overhead
         & Benefits)

   Maintenance
$  293,500
    50,000
       Mechanical Equipment
       (3% of Equipment Costs)   $

       Electrical & Instrumentdiion
       (2% of Equipment Cost)    $

       Piping(1% of Piping Cost)

   Utilities

       Electrical ($.02/KWH)      $

   Chemicals

       Chlorine**(15 mg/1)        $

       Polyelectrolyte(0.5mg/l)   	

   Operating Costs Sub-total

   Total Annual Costs
    21,270


     6,000

     5,480



     4,800



       800

     6,360
$   94,710

$  388,210
$  373,400
$   50,000
$   21,270


$    7,400

     8,150



$    4,800



$      800

     6,360

$   98,780

$  472,180
 *  For treatment Portion Annual Cost
**  For Filter Backwash.
                            120

-------
compress the site requirements, especially in the building, resulting
in a reduction of both capital and operating costs in order of 10 to 20
percent.

        The previous paragraphs have delineated  capital and operating
costs associated with high rate filtration installations in the treatment
of combined sewer overflows.  These costs do not include  disposal of
waste  screenings and filter backwash since the proposed system would
discharge these to the municipal sewage treatment plant.

        Solids handling  and disposal costs for municipal sewage
treatment facilities cover a great range, varying  from $5
to $55 per ton of dry solids (24).  Assuming an average
of 200 mg/1 of solids removed, and a combined sewer overflow
treatment plant operation of 300 hours  per year, solids  processing and
disposal costs  incurred by the  municipal  sewage  treatment plant could
range from 3 to 35 percent of the total annual charges for the combined
sewer  overflow treatment facility.

Selection of High Rate Filtration Plant Capacity with Storage

       The selection of the appropriate capacity  for a high rate
filtration plant to treat combined sewer  overflows should be based
on results of a cost effectiveness analysis.  To achieve the highest
cost effectiveness system, an optimum  storage capacity should be
included in defining treatment plant size.  The temporary storage of
combined sewer overflows moderates the peak loadings  contributed
by intense  storms and avoids excessive treatment plant capacity.
However,  the size of  storage area depends on local conditions such as
sewer capacity (in-stream storage) and  land availability (off-stream
storage).  This  approach allows the selection of the highest cost
effectiveness system for each particular situation.

       A typical  example of the estimated capital costs for various
treatment plants and storage capacities is presented in  Table 31.  This
example utilizes  an off-stream  storage tank and is based on a synthetic
outflow hydrograph for combined sewer overflow without consideration of
storage in a main sewer. The overflow hydrograph is based on a peak
flow rate of 200 MGD with a time of concentration of approximately
90 minutes and a total duration of six hours as shown in Figure 26.
                            121

-------
o
_l
_J
<


z
o
3
u.
Q

UJ
O
o
                    MASS  CURVE
      SLOPE = 200 MGD
     0
                            SLOPE = 100 MGD
                     //-2.0 MILLION  GALLONS
                                  OUTFLOW

                                 HYDROGRAPH
                             12345

                               TIME (HOURS)
                                     I
                  23      4

                    TIME  (HOURS)
    USE OF A MASS  CURVE TO  DETERMINE

      THE STORAGE  CAPACITY REQUIRED

      FOR A TYPICAL  STORM OVERFLOW
                    122
                                  FIGURE 26

-------
                           Table 31

        ESTIMATED CAPITAL COSTS FOR VARIOUS TREATMENT
                   PLANT AND STORAGE CAPACITIES

Treatment
Plant
(MGD)

Storage
Tank
(MG)

Treatment Plant
Total Project Cost
($)
Storage
Tank
Cost
($)
                                                            Total
                                                           System
                                                            Cost
                                                             (S)
   200        0            5,465,700            0       5,465,700
   150        0.50         4,700,000          350,000   5,050,000
   100        2.00         3,216,300        1,400,000   4,616,300
    50        4.50         1,754,900        3,140,000   4,894,900
    25        7.15         1,159,300       5,000,000   6,159,300
       Figure 26 is a mass curve for a 6-hour period based on the outflow
hydrograph as shown in the lower right corner of the figure.  The slope
of the mass curve at any time is a measure of the combined sewer
overflow rate at that time.  Plant influent curves representing a uniform rate
of flow are straight lines having a slope equal to the treatment plant
capacity.  The vertical distance between successive tangents represents
the overflow volume beyond plant capacity and indicates the required
storage. This approach is  based on constant draft while the storage
tank is filling during the  overflow event, and it should be  utilized
in conceptual  design.

       As shown in Table 31, and Figure 26 the  storage tank is not
needed for  the treatment  plant capacity having the  same peak rate as the
combined sewer overflow.  By increasing the storage tank  capacity,
the capacity of the  treatment plant can be reduced. The treatment plant
total project cost includes  the plant influent pumping station and the
high rate filtration treatment plant as  shown in Tables 23 through 26.
The storage tank cost is  estimated at  about $700 per 1000  gallons.
Storage  tank costs include  excavation, concrete, 10 percent for
engineering and 12  percent of construction cost for contingency, but
the cost of land is not included.

       Figure 27 shows the estimated costs of storage, treatment and of
the total system. The optimum  point for system  design consideration is
the sag  point on the total system cost curve.  By considering the
reduction of pollutional loading, the highest cost effectiveness for
the 200  MGD peak combined sewer overflow rate is the 100 MGD high
rate filtration plant in conjunction with a 2 million gallon off-stream
storage  tank.

                               123

-------
     8.0
     7.0
NOTES

I. TOTAL SYSTEM COSTS INCLUDE
  STORAGE AND TREATMENT COSTS.

2. TREATMENT COSTS INCLUDE COST
  OF INFLUENT PUMP STATION AND
  HIGH RATE FILTRATION PLANT.

"3. STORAGE COST IS BASED ON
  CONCRETE TANK COSTING $ 700
  PER 1000 GALLONS OFSTORAGED
  VOLUME.
                   TOTAL
                   SYSTEM
                   COSTS
                   STORAGE
                   FACILITIES
                    COSTS
                50       100      150      200
           TREATMENT  PLANT CAPACITY-(MGD)

ESTIMATED CAPITAL COSTS OF  STORAGE AND

    TREATMENT FOR 200 MGD OVERFLOW

                                         FIGURE  27
                      124

-------
                               SECTION XII

               PROCESS POTENTIAL AND FUTURE RESEARCH AREAS
Treatment of Combined Sewer Overflows

      The screening-filtration system delineated in the previous section,
with the addition of appropriate polyelectrolyte, produces suspended
solids removals in the order of 95% or better, which is a highly efficient
system.  Much of the the test work under the 1971 field program was
directed at enhancing process performance in regard to phosphate remov-
al,  by the addition of phosphate removing coagulants (alum, etc.)  The
test results from this mode of filtration operation indicated that phos-
phate removal efficiency was less than desired, in the order of 60%
removal at 8-16 gpm/sq ft, due to the inability of the system to produce,
with consistency, a  low suspended solids effluent.  Under certain  test
runs, using identical coagulant and polyelectrolyte dosages from pre-
viously successful test runs,  poor efficiencies were reported both in
regard to phosphates and suspended solids.  Visual observations of the
filter media during a test run (alum plus polyelectrolyte) revealed that
the filter media became saturated with solids (visually) a  few hours
after the test run had commenced. A possible reason for the high sus-
pended solids in the effluent from a filter under this mode of test
operation is due to the nature of the floe.  The floe formed (alum  plus a
few hundred mg/1 of influent suspended solids) seems very fluffy,,
voluminous, and difficult to retain within the filter media. This indicates
:hat excess alum may have  been  converted to aluminum hydroxide.

      Based on work on secondary effluent filtration (25) that is,  filtering
:he  effluent from an activated  sludge plant, if the influent solids  to the
filter could be reduced to a level in order of 50 mg/1 or less, the suspended
solids removal might improve  substantially, and concurrently, the phosphate
removal.  To accomplish this  may require the use of a much finer screen
mesh ahead of the filter than was used throughout the testing program.

      Additional pilot plant testing should be conducted to develop a
more complete system, utilizing the same unit process.  By using a finer
screening mesh and a finer filter media,  with a more comprehensive study
of in-line mixing and coagulation, a more efficient and economical sys-
tem could be developed.

      To achieve a higher  degree of treatment for removing dissolved
 BOD and phosphate  as well as suspended solids in combined sewer
                               125

-------
overflows, a pilot plant consisting of microscreening (23 micron
openings) followed by filtration with finer media should be evaluated.
Suspended solids would be removed mainly by microscreening. By
introducing the proper dosage of powdered activated carbon and
coagulant ahead of the filtration unit, the dissolved and colloidal
contaminants could be removed by carbon adsorption and coagulation,
and eventually intercepted by the filter  media.  Probably the cost/benefit
ratio would justify optimizing this system, since basic unit processes
remain the same with only a moderate increase in screen sizing.
Due to the intermittent operation of a full size treatment plant (about
300 hours per year in Cleveland).  The additional annual costs of
activated carbon could be justified by cost-benefit considerations.

      A slotted screening element furnished by UOP Johnson Divi-
sion was strong, rugged  and maintenance free.  Further study of the
slotted  screening elements should be considered.   Redesign of the
components,  such as the variation of slot opening, the shape of surface
wire and support rod, and the location of the support rod may be
found appropriate for increasing allowable hydraulic loadings.

      The Biospheric's in-line suspended solids monitor should be
further investigated  in a  pilot study.  The calibration procedure should
be more carefully  set up  to obtain a consistent and reproducible
correlation. This unit then could be considered as a sensing device
to enhance automation of the filtration process by providing positive
control  of effluent suspended solids concentration.

      Tests on microscreening  (16) indicate that fine screening can
produce a low suspended solids effluent, below 50 mg/1.  Thus,  for a
high efficiency system,  suspended solids would be removed mainly by
microscreening, and phosphates, BOD and other contaminants in
dissolved or colloidal form may be trimmed in filter by using coagulant
and powdered activated carbon addition.  Microscreening followed by
deep bed,  high rate  filtration seems a possible alternative system to
produce a very high  quality effluent.  This system  should be further
studies because in areas such as the Great Lakes and others where
stringent control and regulation of phosphate inputs to a water body are,
or will be, required,  a system such as the one just described may be of
applicability.
                             126

-------
      Another possibility for improving system consistency and perfor-
mance, when adding phosphate reducing coagulants,  might be to under-
take more test work with additional polyelectrolytes and coagulant aids,
etc., to see if a coagulant combination can be developed which will
permit a consistently high degree of suspended solids and phosphate
removal.  However current indications are that the finer screen is the
best way to increase process performance.

Treatment of Secondary Effluent from an Activated Sludge Process

      Test data in Appendix D  shows that secondary effluent levels from
an activated sludge process can be limited to approximately 5 mg/1
suspended solids at filtration rates of up to 30 gpm/sq ft.  The basic
concept of deep bed high rate filtration for secondary effluent is essen-
tially the same as the theory involved in the treatment of combined sewage
storm overflow.  The major differences are the lower level of solids to be
handled, and the requisite effluent water quality.  Based on the data
contained--in Appendix D, indicating that filtration is capable  of control-
ling solids levels to below  10 mg/1, this process may be applicable to
situations where a marginal removal of solids and BOD is required to
meet water quality criteria.  The major potential  advantages of the high rate
deep bed filter for secondary effluent are:  first,  due to the high filtration
rate, the space requirements, and secondly, because of this high fil-
tration rate,  the economics  of this process are favorable over shallower
filters  operating at much lower  filtration rates.

     Analogous to the approach taken in regard to combined sewage
storm overflow filtration, a  higher quality product water may be obtained
by adding various chemical  coagulants  prior to the deep bed filter. For
example, alum, lime, and possibly iron coagulants and polyelectrolyte,
applied in proper combination and dosage, might  produce an effluent or
product water with low residuals of suspended solids, biochemical
oxygen demand, and phosphates.  Through the addition of phosphate
reducing coagulants (alum,  lime, iron salts),  it may be possible to com-
press or eliminate the flocculator-clarifiers or solids contact clarifiers
that are normally associated with phosphate removal.  In many cases,  a
filter is required  after these units anyway, to reduce phosphate levels to
low concentrations.

      Based on the preliminary  test results contained in Appendix D, a
research and development grant was applied for and obtained to evaluate
high rate, deep bed filtration in treating secondary effluent from an
activated sludge  plant.
                           127

-------
      Under this activated sludge plant secondary effluent testing pro-
gram (26), the selected media (5  feet - No. 3 Anthracite over 3 feet -
No. 612 Sand) for combined sewer overflow treatment was also evaluated
in terms of its capability for polishing secondary effluents.  Test
data has confirmed the applicability of this combined sewer overflow
media to reducing suspended solids, BOD, and phosphates to low
residuals.

Urban Runoff Treatment and Sediment Control

      Additional areas of application for the deep bed high rate filtration
process are in the treatment of urban runoff and also in treating flows
from particular rivers for sediment control.  As shown in Table B-5  the
high rate filtration system was more effective in reducing fixed suspended
solids than volatile suspended solids from combined sewer overflows.
Since the nature of urban runoff would be similar to that of combined
sewer overflows, except that the suspended solids would be of a more
fixed or inorganic nature, the proposed treatment system would probably
be more effective in treating urban runoff than it would  be in handling
combined sewer overflow discharges.  In regard to sediment control, past
data by Hydrotechnic (27) has demonstrated that high rate filters can
remove inorganic solids such as those that would  normally be associated i
with erosion.  It may be practical to filter discharges of entire rivers
which contribute heavily to the sediment problem.  This might
prove to be a more economical and preferable method of handling the
problem than periodic dredging of rivers  to maintain navigable channels,
since dredging creates a pollution problem.

Dual Purpose of Utilization of High Rate Filtration Process

      In Cleveland,  the total duration of the overflows  from the combined
sewer system is approximately 300 hours per annum. This indicates
the possibility of utilizing dual purpose  treatment plants based on
the high rate filtration process (15).  Such installations would treat
combined sewer overflows when they occur and in between such periods,
for over 95 percent of the time, the filtration process would treat other
wastewaters depending on the location of the process.

      For a  high rate filtration process for combined sewer overflow
treatment located in the area of the domestic wastewater treatment plant, the
filtration process can be utilized for polishing the treatment plant effluent
as well as  to protect the effluent quality during plant overloading or
process malfunction.

                            128

-------
      For a newly designed physical-chemical process to treat domestic
wastewater, the high rate filtration process can be adopted to handle both
dry and wet weather flow, including combined sewer overflows in
conjunction with an adequate storage facility.

      The economical benefits of such dual purpose utilization of the
high rate filtration process should not be overlooked.
                            129

-------
                          SECTION XIII

                      ACKNOWLEDGMENTS
       This project was undertaken through sponsorship of the U.S.
Environmental Protection Agency.

       U.S. Environmental Protection Agency
       Office of Research and Monitoring	
           Municipal Technology Branch
           1901 North Fort Meyer Drive
           Arlington, Virginia 22209

           National Environmental Research Center
           Edison Water Quality Research Division
           Storm and Combined Sewer Technology Branch
           Edison, New Jersey 08817

       Acknowledgment is made to Mr. William Rosenkranz, Chief of the
Municipal'Technology Branch, Mr. Francis J. Condon,  Project Manager,
and initial  Project Officer Mr. Edmund Struzeski for  their interest,
encouragement and guidance on this project.

       Acknowledgment is made to Project Officer Mr.  Richard Field,
Chief of Storm and Combined Sewer Technology Branch for his interest and
guidance during  the course of the  1971 testing program, and for his review
and many valuable comments and  suggestions on the final report.

       Acknowledgment is made to Dr. Sidney A.  Hannah, Supervisory
Research Chemist, and Mr.  James Kreissl  of the Advanced Waste Treat-
ment Research Laboratory, National Environmental Research Center,
Environmental Protection Agency,  for performing and providing the com-
bined sewer overflow suspended solids particle count,  and for reviewing
the final report.

       The project  testing program was conducted in Cleveland, Ohio.

       City of Cleveland
         Department of Public Utilities
         Division of Water Pollution  Control
          1825 Lakeside Avenue
         Cleveland, Ohio 44114
                                131

-------
         Southerly Wastewater Treatment Plant
         6000 Canal Road
         Cleveland, Ohio 44125

       Acknowledgment is made to Mr. C.A. Crown, Commissioner of the
Division of Water Pollution Control,  and  Mr. Ray Roth, Assistant Com-
missioner of Southerly Wastewater Pollution Control Center for providing
the pilot plant site.  Thanks are due  to Messrs.  Nabil Ghoubriel,
Superintendent,  other members of the staff of the Southerly Wastewater
Treatment Plant, and former Director  Mr.  W. Tresville for their assis-
tance with background information.   Thanks  are also due to Messrs.  E.
Martin, E. Newbauer and  J.N. Donahue,  who supported this project as
members of the city's Clean Water Task Force.

       The project was  conducted by the consulting engineering  firm.

         Hydrotechnic Corporation
         641  Lexington Avenue
         New York,  N.Y. 10022

       The project was  conceived by Mr. Ross Nebolsine, President,
who provided general guidance and high level review throughout its
duration.   General consultation and  review was  also provided by Mr.
Ivan Pouschine, Jr., Vice President and Mr. Albert S. Toth,  Vice
President.

       The project was  managed for  most of its duration by Patrick J.
Harvey, Division Engineer, who also prepared the draft report.

       In the  initial project stages,  including engineering and construc-
tion of the pilot plant facilities, this assignment was managed by Mr.
Harold J. Kohlmann,  Manager Engineer.  Mr. Chi-Yuan Fan, Principal
Engineer, was in charge of the daily technical aspects of the project,
supervising a  field team and an office staff.  On site field testing was
directed by Mr.  George  Vercelli,  Senior Engineer, and later by Mr. Rey
Morales, Engineer.

       A special note of acknowledgment is due Dr. John C. Eck, who
served as a consultant to Hydrotechnic Corporation on this project.
                            132

-------
                          SECTION XIV

                           REFERENCES
 1.     "Pollutional Effects  of Stormwater and Overflows from Combined
       Sewer Systems -A Preliminary Appraisal", U.S. Department of
       Health, Education and Welfare, Public Health Service,  Division
       of Water Supply and Pollution Control, November 1964.

 2.     "Problems of Combined Sewer Facilities and Overflows  1967",
       American Public Works Association, Federal Water Pollution
       Control Administration, U.S. Department  of the Interior,
       December 1, 1967.

 3.     "The Economics of Clean Water - Volume  I - Detailed Analysis",
       U.S. Department of  the Interior, Federal Water Pollution Con-
       trol Administration,  March, 1970.

 4.     A.S.Toth, "Progress in Steel Plant Wastewater Treatment",
       paper presented at Chicago Section of Association of Iron and
       Steel Engineers, April 4,  1967.

 5.     R.Nebolsine and RJ.Sanday, "Ultra  High Rate Filtration,  a
       New Technique for Purification and Reuse of Water", Iron and
       Steel Engineer, December, 1967.

 6.     "Master Plan for Pollution Abatement - Cleveland, Ohio",
       Havens and Emerson - Consulting Engineers, June,  1968.

 7.     W.L.Harris, "High  Rate Filter Efficiency", Journal of American
       Waterworks Association, 62:515 (August, 1970).

 8.     G. Tchnobanoglous, "Filtration Techniques in  Tertiary Treat-
       ment", Journal Water Pollution Control Federation,  42:603
       (April, 1970).

 9.     "Ultra High Rate Filtration -A New Technique  for Purification
       and Reuse of Water", Hydrotechnic Corporation - Consulting
       Engineers, March,   1967.

10.     V.F.Frank and J.P.Gravenstreter, "Operating Experience with
       High Rate Filters",  paper presented at Water Pollution Control
       Federation Annual Convention, Chicago,  Illinois, September,
       1968.
                            133

-------
11.    "Methods for Chemical Analysis of Water and Wastes", U.S.
       Environmental Protection Agency (1971).

12.    "Standard Method for Examination of Water and Wastewater",
       Thirteenth Edition, American Public Health Association, New
       York (1971).

13.    "Technical  Manual Model 53 and Model 54 Effluent Monitor" ,
       Biospherics Incorporated, Rockville,  Maryland.

14.    "Local Climatological Data - Cleveland Hopkins Intl.Airport",
       U.S. Department of Commerce, Environmental Data Service.

15.    R.Nebolsine, P.J.Harvey and C.Y.Fan, - "Ultra High  Rate
       Filtration System for Treating Overflows from Combined Sewers",
       Paper presented at Water Pollution Control Federation Annual
       Convention, San Francisco,  October,  1971.

16.    "Microstraining and Disinfection of Combined Sewer Overflows",
       Cochrane Division, Crane Company,  Federal Water Quality
       Administration,  Contract No. 14-12-136, June,  1970.

17.    "Rotary Vibratory Fine Screening of Combined Sewer Overflows",
       Cornell,  How land, Hayes and  Merryfield - Consulting Engi-
       neers and Planners, Federal Water Quality Administration,
       Contract No. 14-12-128, March,  1970.

18.    S.A.Hannah et al, "Control Techniques for Coagulation -
       Filtration", Journal American Water Works Association, 59:1149
       (September, 1967).

19.    R.J.Burns et al,  "Chemical and Physical Comparison of Com-
       bined and Separate Sewer Discharges", Journal Water  Pollution
       Control Federation, 40:112 (January,  1968).

20.    "Ultra High Rate Filtration Design Criteria", Hydrotechnic
       Corporation - Consulting Engineers,  New York,  N.Y.

21.    Richard Field, "Management and Control of Combined  Sewer
       Overflows", Paper presented at 44th Annual Meeting of the New
       York Water Pollution Control Association, New York, January,
       1972.
                            134

-------
22.    D.G.Mason, "The Use of Screening/Dissolved-Air Flotation
       For Treating Combined Sewer Overflows", Rex Chainbelt, Inc. ,
       Combined Sewer Abatement Technology, Federal Water Quality
       Administration, p. 123,  June, 1970.

23.    H.E.Hudson, Jr. ,  "Declining-Rate Filtration", Journal American
       Waterworks Association, 51:1455 (November, 1959).

24.    R.S.Burd, "A Study of Sludge Handling and Disposal", Federal
       Water Pollution Control Administration,  Office of  Research and
       Development,  May, 1968.

25.    R.Nebolsine and J.C.Eck,  "Tertiary Treatment of Sewage by
       The Ultra  High Rate Filtration Process", Paper presented at 44
       Annual Meeting of the New York Water Pollution Control  Asso-
       ciation, New York, January,  1972.

26.    "Ultra High  Rate Filtration of Activated Sludge Plant Effluent",
       Hydrotechnic Corporation - Consulting Engineers, Environmen-
       tal Protection Agency, Project #17030, HMM.

27.    "Enlargement of Water Intake System, Pumping, Filtration and
       Chlorination for the La Plate Refinery",  Hydrotechnic Corpo-
       ration - Christian! and Nielsen - Diesel Electromechanica, New
       York, June,  1967.
                          135

-------
                      SECTION XV

                    PUBLICATIONS
R. Nebolsine, P.J.  Harvey and C. Y. Fan, "Ultra High Rate
Filtration System for Treating Overflow from Combined Sewers, "
Paper presented  at Water Pollution Control Federation Annual
Convention, San Francisco, October 1971.

R. Nebolsine and J.C. Eck, "Tertiary Treatment of Sewage by the Ultra
High Rate Filtration Process, "  Paper presented at  44th Annual
Meeting of the New York Water Pollution Control Association,  New York,
January 1972.
                            137

-------
                           SECTION XVI

                           APPENDICES

                                                             Page

A.   Combined Sewer Overflow Characteristics
     Figures A-1 through A-15	     141-155

B.   Combined Sewer Overflow Filtration Test Results
     Table B-l: Screening and Filtration System Perfor-
     mance (1970 and 1971 Test Data)	     156-158

     Table B-2: Screening Performance  (1970 Test Data).  . .  .     159

     Table B-3: Filter Performance (1970 and 1971 Test
               Data)	     160-167
     Table B-4: Coliform Reduction by Filtration
               (1970 Test Data)	     168
     Table B-5: Solids  Reduction by Filtration
                (1970 Test Data)	     169-170

     Table B-6: Phosphate, Nitrogen and Grease  Reduction
               by Filtration (1970 Test Data)	    .171-172

C.   Combined Sewer Overflow Filtration Tests
     Filter Performance  Curves, Figures C-l through C-138.  .     173-310

D.   Secondary Effluent Filtration Tests	     311-312
     Filter Performance  Curves, Figures D-l through D-19. .  .     313-331
     Table D-l: Secondary Effluent Filtration Test Results. .      332

E.   The Effect of Pumping on Particle Size in Overflows.  . .  .     333
     Table E-l: Combined Sewer Overflow Suspended Solids
               Particle Counter Run No. 1	     334-335
     Table E-2: Combined Sewer Overflow Suspended Solids
               Particle Counter Run No. 2	     336-337
     Table E-3: Combined Sewer Overflow Suspended Solids
               Particle Counter Run No. 3	     338-339
                            139

-------
cs
"01 2OOO
J 1800
to 1600
3 1400
O 1200
OT 1000
8 800
Z 600
Ijj 400
OT 200
to 0
1300
1200
— 1 100
"01 IOOO
J 900
800
to 700
Q 600
O 500
OT 400
< 30°
1- 200
1- 100
0
IOOO
900
"^ 700
J 600
. 500
ri 4O°

!\
J\
j\\
fl\V
Js \
1 M '"
r
,





y
X
^\
V
V



























^-TURBIDI


\
X>M
""-'




~





^- ._




TV




1 — ^.














x
"^^
**••-•











*, ~~
/













^-— •

.^"













^

















SI




















JSPENC
SOLIDS
















>ED





















































.
i


,^j
j



A
r




\
\ (
\/
V




\J





I -^
wr
\




w
'^*,


1
/



X^
^



f 	



'OTAL



„,,--




MHOTM,



"*» 	 *




""••••••


SOLID



-.-»



/
/




t
^*

qc







^.^•~








v ••






































ITTLEABLE SOLIDS
•




\

































































i
i /\
i/
L










^










»C^J*









^y
^"^







^
f
*"»»--






/
^/
s
^•^









-COD -


x^>
.--



-TX*









—








/
•£-













BOD -













































^888888888
j^iooowow^uj
                        TIME (hours)
COMBINED  SEWER  OVERFLOW CHARACTERISTICS
  7/29/70  DAILY  PRECIPITATION 1.26  INCHES
FIGURE Al
                     141

-------
    -31
    v
    i  "
    &  •=
    Ul
    o:
    Q-   n
01 £<->w
,§ 1800
CO 1600
O 1200
W !000
S 800
§ 600
UJ 400
OT 200
CO 0
1300
1200
— 1100
"o. 1000
J 900
eoo
2 700
O 500
OT 400
< 30°
1- 200
K 100
0
1000
900
^ 700
J 600
. 500
d 40°
 500
0 400
55 300
§ 200
K- 100
L o
— 26
v. 24
J 22
20
• 2 a
_l 6
1- % «
2
- 3 o
• < 8
UJ 6
- 1- 4
- uj ^
L « o
r 200
ieo
c: i eo
"S, 140
5 1 20
. 100
- S BO
• m 60
4O
20
°c
c


















-SUSPEND
- SOLIDS









FD
— ~c






I
/
v\
^?-r






/
/
r***







\
VM








*• ^








— — *






/
/
J





A
V
\





^
/


s
--•"


T










URBIDI



L^n
— •**




-


TY






















































9F























\ i
Y






/*






\
^
TTLEABLE SOLI









*ti



k^~



~— >








•+*+**
DS










~

^









x/
"

^m.
7
/
r





'V
\
1


\





n
/


k 	



y
v-'





rOTAL


—_.



^^^^^




•^
v"



*« -





SOLID



»


































































































ft
V
r
i





x
r
.A
^.







B0n



V"
\
v




~"y
/







^-^








•••—I
'







X
^^










»— —








^
.«• —






/
7
fsrsi






re


-






).D.-


































3OOOOQQOOQ
3OOOOOOOOO
?~ 3:se28SJOCJ*
TIME (hours)
COMBINED  SEWER  OVERFLOW  CHARACTERISTICS
  8/I9/7O
DAILY  PRECIPITATION 0.31 INCHES
                                      FIGURE  A 2
                     142

-------
"o> 2000
CO 1600
§ 1400
0 1200
OT 1000
S 800
§ 600
£ 400
CO 200
CO 0
1300
1200
'"" i inn
"£> 1000
J 900
800
W 700
° 600
0 500
W 400
J 300
1- 200
H- 100
0
1000
900
C 800
15> 700
,§ 600
. 500
d 40°

n O 01 c
itt
o:
a o
r 1000
1- 800
3 700
600
£ 500
5 400
5 300
§ 200
1- 100
0
— . 26
5: 24
J 22
20
- 2 8
_J 6
- u 2
j 0
- < 8
U, 6
1- 4
• W 0
r 200
1 80
:r i eo
- ^, 140
^ 1 20
. 100
§ 80
CD 60
40
20
°C
C


























*?! 1
<















H







SPENDE
50LIDS













•n















^*












fl<=—
p^.~













~« — .














^-•^













/
J
~^S










T
/ '























URBIDI1
















ry








































































































































•>
i

A
r







x
^^
u_.

pu






T


-— v

— •










OTAL


"*%••
- — >



,x
'*"

\









SOLID










c








































-SETTLEABLE SOLIDS





































































































-COn


• fc-'*







/<
^








» "*
^








*..„

"^~«








^^i
•i







f
•£_
• .•











son














































































3888888888
ogcjj6ei^
-------
    0.

    CJ
    u
    a:
    a.
       2.0
       1.5
    .-  1.0
,§ 1800
CO 1600
§ 1400
0 1200
"* IOOO
S 800
§ 600
£ 400
CO 200
CO 0
1300
1200
~ 1 100
^i IOOO
J 900
800
CO 700
- 600
O 500
W 400
H 200
1- 100
0
IOOO
900
"o> 700
J 600
. 500
Q
d
,J 300
200
100
n
2 900
1- 800
3 700
600
£ 500
5 400
§ 200
H- 100
L 0
) SETTLEABLE SOLIDS (ml/1)
- — ro
n a> o — — — — — wwrjr
3 o o oiv&a>OK>-ba>-t*c
^ i^o
E i ? n
.100
• S 6°
40
20

















/
<-V
~AV/





/
,y
V











v-TURBID



te


01







TY-








SPENDED


















SOLiC










)C







































































































,

X
p







y
y
^/

y\
f
/o
O




T
/ '











OTAL
















SOLID




















ETTLEABLE SOLID
















'






































































































































A/
yflWi
-~*







s., f
\ ^
V
\





/
/






B0n -




p n n -



'








































































































































                                     O
                                     O
                         TIME (hours)
COMBINED SEWER OVERFLOW CHARACTERISTICS
  8/30/70  DAILY PRECIPITATION < 0.05 INCHES
                                       FIGURE A 4
                      144

-------
    -35
     0)
        2.0
        1.5
     Q.

     O
     UI
     tr
     CL
.5
£ i ftnn
<0 1600
§ 1400
O 1200
00 1000
S 800
§ 600
£ 400
OT 200
to 0
1300
1200
" 1 100
"£> 1000
J 900
800
g 700
— 600
0 500
OT 400
<{ 300
0 2°°
1- 100
0
1000
900
•*^ pnn
"S. 700
-§ 600
. 500
d 40°
 500
5 400
85 200
h- 100
0
~ 26
V; 24
J 22
20
• Q 18
_l 1 6
O 1 A
to
LJ
i | o
' < 8
U 6
1- 4
LJ 2
40 0
200
1 80
c: i eo
"^ 140
S 1 20
. 100
Q
m 60
40
1
f













































L
J^
X
V"\





/
/
X
,'
..»*





V/
Y

L% ^
>r



T
/ '


	 e







URBID






TV





















SUSPENDED SOLIDS























































































































n
j V


r
/







/
V

^^^








_^



^*S






- T
/ '



._<:









OTAL








1
1
SOLID






ETTLEABLE




























SOLID















c


































































































4
•V
r.
in
I
/




1

/
\
V
\
\




i-*"
V-
x



, — -~



_COn







Rf









) D

































































































DOOOOOOOOO
5ooooo oooo
3w6
-------
T3
o>
1 l'5
Z
o
PRECIPITAT
D 01 C








V//A



r77?
































































,§ 1800
(/) 1600
° 1400
O 1?">0
W 1000
S 800
§ 600
£ 400
(/) 200
W 0
!300
1200
^> 1000
J 900
800
2 700
— 600
0 500
05 400
< 30°
H 200
t- 100
0
1000
900
C 800
"o. 700
.§ 600
. 500
d 4°°
 50O
- 5 ^oo
CD 300
j§ 200
t- 100
L 0
•x" 24
• J 22
2O
Q 8
_l 6
OT 4
2
111
' < 8
UJ 6
• t- 4
- t 2
L w 0
r 200
1 80
~ 1 60
"o. 140
-§ 1 20
. 100
' § 8°
CD 60
40
20
0
C
^


































/
'v
/\









^
"-^




















—





/
J
J~-
*
•'




^-Tl




*^x^







RBIDI"









ry.
T











-SUSPENDED
















SOLI








-)C .












































































\ /
\/
y

\/
V







s
\
'

s
s









. — ••






















t
»
/
'


*







>^-v


t
/ -








^_ -

.










rOTAL












SOLI

3ETTLEABLE


















DS


SOLIL














iq .




































































.









- 	
, v^
k~~.









•^r









, 	 •
















t
/
ji
*c~
\




6





>~r<



O.D.




D.D.


























































































^888888888
f
-------
"o> 2000
j= 1800
co 1600
0 1200
OT 1000
S 800
§ 600
£ 400
en 200
(n o
1300
1200
"o> 1000
3 90°
800
 700
. 500
O
d
(j 300
200
100
0
PRECIPITATION (inches)
) SETTLEABLE SOLIDS (ml/I) TURBIDITY (JTU)
	 ro _rooJ*o>t*a>c°otV't*o>a>otv-t>a> ooooooooooo o 01 o m c
^» 140
E ion
. 100
- S 80
• S 60
40
20
0
C
C
C

































-SUSPEND
- SOLIDS







-SE













:TT
so












LEi
LIC
















- n

\














«
\y?













^*-
.—*•






\BL
) S~^










F


\ *








i^
VIV
n
'\














— —














==±









V"











**•%


^^















l^^M!














^— •










*>x_
s^~












^^l















S-— •













>^>~^»
^— i










m_]m^_

\








/
y«
.-*














/
/
ZL-
• — •>.





i
/ '
r

*•**

















• "••.

^—






















JRBIDr

— —

.—




•QTAL



^^






x""'



•»,


• ..










rv


__








SOLIC







•*»— i








»— ~-













•y





1C
t&


_




•













-•-









»— •










































. r on







•
•A
^^-^







X
^**








x%--
•»*—








*•— •
— V








— ..

^.







,—• • •







/
/
••/..

••.pi i







-B.OD-


^-».

•— —^




I^^MV







f

—






*•«
'

W^^M







^"

-• .






*


m^tf^^






•*'


• *





.*



^^

^§88888888
j^fib ooowSSSsS
TIME (hours)
COMBINED  SEWER OVERFLOW  CHARACTERISTICS
  9/18/70
DAILY PRECIPITATION 0.51  INCHES
                                     FIGURE A 7
                    147

-------
o> 2000
j= 1800
CO 1600
° 1400
O 1200
*" 1000
S 800
§ 600
g 400
CO 200
CO   0
-55
o>
o i •;
z
0 1 0
1.0
?
0- S
o '5
UJ
cc
Q. n
mri n










£%







































































































IUUU
5 900
1- 800
600
> 500
5 400
m 300
§ 200
1- 100
n























- T"!
1 1


A
'j
V






JRBIDI'


y ^
/*
'




^,^~^




rw .
1 Y-v
I
/
m
*t^

XV








•~-~^
	 -'








^^f^f









"









— i -«









^^J
._"»





A
/
/
s-



su
s

\
\
— .^





SPEND
.OLIDS



c-V
^v_

/
/




Fn
7
/























t-~f~










  1300
  1200
- I 100
"o> 1000
J 900
  800
CO 700
— 600
O 500
OT 400
-J 300
  100
    0
       _l
       °
       to
       LJ
  1000
  900
C 800
"w 700
^ 600
  500
  400
  300
  200
  100
    0
 .
d
         200
         180
       cr i eo
       ^ 140
       ^ 1 20
        . 100
          8°
          60
          40
          20
       m
O
O
           00
               C.O.Dr
                oo
                0Q
                                o
                                0
                                    o
                                    0
                                           ^L
                                             V
                                                B.O.D.-
o
0
o
0
o
0
o
0
                                TIME (hours)
 COMBINED  SEWER  OVERFLOW CHARACTERISTICS
    9/23/70   DAILY  PRECIPITATION 0.18   INCHES
                                                 FIGURE A 8
                            148

-------
•<»
(0
.c
0 . c
Z
o , 0
g
£L 5
O
UJ
o:
^- n















hH



TTTT|
























































,§ 1800
CO 1600
§ 1400
O 1200
W 1000
S 800
§ 600
£ 400
CO 200
CO   0
  1300
  1200
— I 100
^5> 1000
J 900
  800
CO 700
— 600
O 500
OT 40O
< 30°
I- 200
K IOO
  1000
  900
C 800
"o> 700
J 600
  500
  400
  300
  200
  100
    0
 .
d
IUUU
^900
1- 800
600
£ 500
5 400
5 300
JJ5 200
1- 100
n

























^








^11













5PENDED
Xxk



X




NS



'P^s
V








SOLID





















































1
1
1
~^—




T
/ '











URBIDI













TY
















       _
       S
       3
       h-
          26
          24
          22
          20
          18
          1 6
          14
          1 2
          10
            -SETTLEABLE
            — SOLIDS--
                                          T
                                           TOTAL  SOLIDS
1 80
~ 160
^, 140
J 1 20
. IOO
Q
ri 60
40
20
°C
c












































-C.O.D.-









*
\
s






\
^
s_
•\
\






/
/

\
"N







-BOD-



	 ^
/



•——
\
X







••-•-..

— ^






^
•'

S






,-"








	 -








s-
''








— —









	









^•*~~








^"






3OOOOOOOOO
3OOOOOOOOO
jcvi^fcbooocG^f'to 06
                               TIME (hours)

 COMBINED  SEWER OVERFLOW  CHARACTERISTICS
   10/6/70    DAILY  PRECIPITATION 0.63  INCHES       FIGURE  A 9
                           149

-------
"oi 2000
t. 1800
OT 1600
3 1400
0 1200
OT 1000
S 800
§ 600
W 400
(0 200
V) 0
1300
1200
— 1100
"o> lOpO
3. 9°o
800
OT 700
2 600
O 500
OT 400
^ 300
1- 200
1- 100
0
1000
900
C 800
o> 700
J 600
500
d 40°
<_j 300
200
100
0
PRECIPITATION (inches)
.— ~ r\
w O oi t
— o
IOOO
3 900
t- 800
3 700
600
£ 500
O ^OO
55 300
•§ 200
1- 100
0
v 24
J 22
20
CO
^^ o
J 6
- 8 4
- LJ 2
- ^j Q
: 3 J
UJ ^
r 200
1 60
CT 160
°^> 140
J 1 20
. 100
• S 8°
• 2 60
40
20
0
C
C
c




































-SUSPEND
- SOLIDS












ED
—^





































SETTLEABL
- SOLIDS-















f
/
jf^f







A.





















i
,J
T""
E,
s


4
















— /









~ — -


•*>_













/ '













H^^M













•^>










v
•^

v
V













s».










«.—


x^













— —










	

^-—














— -.










— ~

•i— •














•- —







\
\
\


•-•— ^N












/
/
JL















_ T
/T









rOTAL




— ,


	 ^-«






















JRBIDI'


^-=








"• —






SOLIC

k
'•*>.





..^












TV -
1 Y


•=:






>c
>o -



~~—















•&=*•










^
**

"^~























C C























^iii
>PRi





it
X









-— —
"• —








— — i
— —








^ ^
^9M^







^•Ji
>•



















s
X.







---*










1 **«»
— ~.








^

^






I
t-






.O.D

•«fc^_




















--^

>888888 888
i2S£S2wwo M t u>
TIME (hours)
COMBINED  SEWER OVERFLOW  CHARACTERISTICS
  10/12/70
DAILY PRECIPITATION 0.54  INCHES
                                     FIGURE A 10
                     150

-------
PRECIPITATION (inches)
. r* r~ h
O 01 O Oi *C
















































^^^f^



— -~







11 m i






























s§ 1800
CO 1600
3 1400
0 1200
1000
8 800
§ 600
UJ 400
CO 200
CO 0
1300
1200
— 1 IOO
"o« 1000
J 900
800
CO 700
2 600
0 500
W 400
J 300
1- 200
t- IOO
0
1000
900
C 80Q
"01 700-
J 600
. 500
o
% 300
200
IOO
0
IUUU
3 900
I- 800
3 700
600
£ 500
5 400
DO 300
§ 200
H- IOO
L o
~ 26
i 24
J 22
20
2 18
-1 1 6
: a !2o
• % 8
a ;
t- 4
w 0
r 200
180
C 1 60
"5, 140
.§ 1 20
. IOO
• § BO
• m 60
40
20
e
c
'"





^v
\
\

v
1



































JRBIDITY-^






k










fc__








—









-—
<<








su








SPE
OL







:ND
DS







ED.














































,\t
/
/ »
\
\J)






	
A
/n


/
/

V /
/*
/




\l
\
u







\f~~-
\
s

"







^-'

s*





P
\
\

~ •*




TO'
,^'

•J
1
SETTLEABLE SOLIDS-^"
1









•AL


- ••







S


y
\
^





)LI




•^






DS































































































-_
ff t^'
J





t
/
t ^^



/
/
,/


^-^



V


\

V
N







.....

^=ss





X
^

^"






»_


"^^.







***.
•a i^






v/
'*"
^-








_ —





j
'•

=^<




/r~



^—





B,0



C.Q.





,D,



D.
























?8888888||
                         TIME (hours)




COMBINED SEWER OVERFLOW  CHARACTERISTICS


  IO/2I/70   DAILY PRECIPITATION 0.2I INCHES      ri/^i IDC A n
                                       FIGURE A II
                      151

-------
     •a!
     o>
     JC
     <->
     c
     s
     cc
          z.o

          1.5

          1.0
o> 2000
,§ 1800
to 1600
3 1400
O 1200
rn
  1000
  800
  600
  400
  200
    0
Q
UJ
  1300
  1200
— I 100
"£. 1000
,§ 900
  800
to 700
^ 600
O 500
W 400
^ 300
i- ioo
° 100
    o
  1000
  900
~ 800
~o> 700
,§ 600
 . 500
Q
d
d 300
  200
  100
       1000
       ; 900
       • 800
       ; 700
        600
       • 500
      Q
      CD
      o:
         300
         200
         100
           0
                      r
SUSPENDED
 SOLIDS
      to
      Q
      UJ
      1-
      Hi
      »
£.*>
24
22
20
8
6
2
0
8
6
4
2



1
\
11
K
/i S
























\
\













y
\
S












^__












i_J--^












"*•
X











,-*
^x1











•»,_













±^








































SETTLEABLE



S<


DLI
•~ — ,
DS

^^
— \
\
\
\

























^^











^














        400
        360
      c
                               TIME (hours)
COMBINED  SEWER  OVERFLOW  CHARACTERISTICS
  10/29/70    DAILY  PRECIPITATION 0.22  INCHES       _
                                                FIGURE  A12
                           152

-------
PITATION (inches)
~ ~ K
Jl 0 01 C
0
LJ
CC
**• 0



•"""







L«J













m









iMi.li


















tyy/vs




w,































J 1800
en 1600
§ 1400
0 1200
OT 1000
S 800
§ 600
UJ 400
CO 200
CO 0
1300
1200
* — i inn
'o. 1000
J 900
800
W 700
° SOO
0 500
OT 400
J 300
1- 200
° 100
0
1000
900
C 800
"o> 700
J 600
. 500
d 40°
«J 300
200
100
n
IUUU
1- 800
3 700
600
>: 500
5 400
55 300
§ 200
1- 100
0
) SETTLEABLE SOLIDS (ml/1)
- — t\>
r>o>O — — 	 — Mroror
3 o O oro*O)O>OM*ooo'^*c
^ 140
E I O A
. 100
• d 60
40
20
n















































su















SPEND
OLIDS







ED









^^



















































































TOTAL SOLIDS







SE1



TL
OL


EAE
DS


)LE
— i







— —



i — -








^x
>

\
*\









»-•"-



^








.*••"























— "










f
A


















-TURBIDIT
_i i

— '
-









	 1— f- 1


















^-..



^-^.









"*•-












-^^













"•\


••^







































































































































\


*-^






/
^**f

-~-






-^.^


****.







"•••^










"^7
^ ^—









•







J
	 4.

~~*~-&






< —
—
s —
-






B.O.

C-0







D.

D.












                        TIME (hours)
COMBINED  SEWER  OVERFLOW  CHARACTERISTICS
  11/2/70
DAILY  PRECIPITATION  1.47 INCHES
                                      FIGURE A 13
                     153

-------
      "5J
      o>
inc
      Z
      O
      I
      CL
      O
      UJ
      CC
      Q.
          2.0


          1.5


          1.0


          .5


           0
J 1800
en 1600
§ 1400
O 1200
W 1000
S 800
§ 600
UJ 400
W 200
O)   0
1UUU
H 800
3 700
600
£ 500
Q 400
m 300
§ 200
H 100
n











































































%
\
•V
•I'






r
?








-\
\

~*





,—'
i
'

\
^•m
"""




'UR


—




BID


11 ••«
,«»*T




TY
_
V
.^^





5US
S(
*•





PEI
5LI







MDE
DS








U













  1300
  1200
c: 1100
"o. 1000
J 900
  800
W 700
0 500
OT 400
J 300
1- 200
H 100
  1000
  900
C 800
^> 700
J 600
 . 500
Q
  400
O
J 300
  200
  100
    0
       2
       U
       UJ
       «
£O
24
22
20
1 8
16
12
1 0
8
6
4
200
1 80
1 60
140
1 20
100
60
40
20
0
C
C
^


































































































m

m
u\





v
s








s




\_







/
\/
^*


=*s



A
/\
r i










^_
^ r

t
» ,
V
S£-
(



TOT
iOL
/s^
^ S

FTL
SOL


Al
IDS

\
\
EAf
IDS
.
-—L*
\T








3LE
»
X
















































































































f\
I \
\ V
VJ
1
l-/^-
f




,A
/ '



N
^




k^
\



ss
^•^





\^
^


• 1






x__









— /
^

— **,





/—

-^^

_^—
^




B.O



C.O





D,



L).






















3OOOOOOOOO
3000999900
fio6ow6w4f-
-------
^» 2000
E i fton
3 1400
0 1200
w 1000
S 800
§ 600
£ 400
W 200
to 0
1300
1200
"o> 1000
J 900
800
g 700
- 600
0 500
OT 400
< 30°
1- 200
1- 100
0
1000
900
C 800
"£> 700
.§ 600
500
ci 40°
 500
5 400
5 300
§ 200
1- 100
0
5: 24
- J 22
20
• % 18
_l 16
0 ,4
tn ' *
12
j 10
H 4
UJ 2
L w 0
200
1 80
tr leo
CT 140
J 1 20
. 100
- § so
- oi 60
40
20
C
C
































































































SU
S























SPEND
OLIDS
1



^



•j»»ji




















ED









•^

ll
IX
tfv
Ivl ? \
Ml *
u '
q
>NAi|







/
^
\
\
V^
%>



















































































































































^.
1 «
} /
*
A
'\
I
^



,\
\
'\
\
1





X
^







\




^~—




















. T
' \



* 	



JRE



—s;





.,
u
7s
f
's. 	



X



roT
OL

••--



ior








Y_




x-
0





AL
OS

*•*'







,


ETTLEABl
SOLIDS
L I I
^
^r-




















.




e _


















































































































V

B.O


xra




•--•

.D-


*N
"^



•v
^
s

i
/
*S





ls—
A
\


c,o




•""*


^-—

D,-



-
\
'

-7-
/
J





,
*















3OOOOOOOOQ
3OOOOOOOOO
                        TIME (hours)
COMBINED  SEWER  OVERFLOW CHARACTERISTICS
  6/7/71
DAILY PRECIPITATION 0.47 INCHES
                                      FIGURE  AI5
                     155

-------
              TABLE   B-l  (SHEET  No.l)
COMBINED SEWER OVERFLOW
FILTRATION
TESTS
SYSTEM PERFORMANCE
Run
4SF II
4SF III
SSFI*
5SF II*
3SFIII*
6SF I
6SF HI
7SF HI
8SF1
SSFI
9SFII
9SF III
9ASF III
10SFI
10SFI1
10SF HI
10ASF HI
11SFI
11SF 11
11SFIII
13SF II
13SF III
13SFIV
14SFI
14ASFI
Screen
Size
(Mesh)
20
20
20
20
20
20
20
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
Filter
Media
48"t4 Anth.**
36"*612 Sand
48"« Anth.**
36"#612 Sand
48 "»4 Anth.**
36"#612 Sand
48"*4Anth.**
3 6 "#612 Sand
48"#3 Anth.
36"4612 Sand
48"t3 Anth.
36"#612 Sand
60"*3 Anth.
36-4612 Sand
60"#3 Anth.
3 6 "41612 Sand
60"»3 Anth.
36"»612 Sand
48"t3 Anth.
36"#612 Sand
48"#3 Anth.
361'»612 Sand
60"t3 Anth.
36"t612 Sand
60 -#3 Anth.
36"t612 Sand
48"* 3 Anth.
36"*612 Sand
48"*3 Anth.
36"*612 Sand
60"»3 Anth.
3 6 "f 612 Sand
60"t3 Anth.
36"#612 Sand
4B"»3 Anth.
36"»612 Sand
48"»3 Anth.
36"*612 Sand
60"*3 Anth.
36"#612 Sand
48"#3 Anth.
36"#6I2 Sand
48 "#3 Anth.
36"* 612 Sand
48"*3 Anth.
36"* 612 Sand
48"#3 Anth.
3 6 "#612 Sand
48 "t3 Anth.
36"#612 Sand
Flux
Rate
fapm/it2)
24
24
16
16
16
24
16
16
32
24
40
1.0
40
32
16
24
24
32
16
24
24
16
10
16
32
(1970 TEST DATA)
Poly
Feed
(mg/1)
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
.5
.5
2.0
2.0
1.5
1.5
1.5
.5
.5

Suspended
Solids
60.7
59.2
60.6
75.9
63.4
71.1
83.1
81.5
5S.1
46.4
48.4
77.5
31.9
63.7
83.0
71.9
81.3
52.7
68.1
66.6
64.3
74.7
79.3
63.8
67.1
% Re
moval of Contaminants bv Screen and Filter
Settleable
Solids
86.4
82
77
86
85
88
94
86
69
75
81
98
90
85
82
87
85
87
93
99
90
95
95
94
95
.2
.6
.5
.9
.5
.1
.7
.1
.3
.6
.5
.5
.0
.1
.3
.6
.1
.7
.2
.1
.7
.4
.1
.2
B. 0. D.
22.3
26.3
35.4
39.2
24.1
39.5
53.2
25.5
23.4
22.7
22.6
43.8
49.8
76.9
20.1
33.9
10.8
34.9
35.9
33.1
24.3
32.3
33.3
31.2
33.6
C. O
59
59
56
58
46
28
34
35
77
48
.6
.6
.9
.8
.5
.5
.5
.9
.0
.3
56. S
72
41
39
50
48
53
52
58
57
43
51
54
36
16
.5
.5
.3
.5
.0
.8
.8
.9
.5
.5
.5
.4
.8
.1
Fecal
52.0
52.0
-
-
-
71.4
64.2
-
-
34.7
78.0
87.1
86.7
40.7
65.4
74.1
87.6
14.6
29.0
33.3
-
-
-
43.9
48.7
Results of Screen Performance Were Basi



Filter Columns Plugged
td on Previous Filter Run




  NOTE: RESULTS OF SCREEN PERFORMANCE WERE BASED ON 1970 TESTING DATA
                                1K6

-------
           TABLE   B- I  (SHEET  No.2)
COMBINED
SEWER OVERFLOW FILTRATION TESTS
SYSTEM
Run
No. _
17SF II
17SF [II
17SFIV
18SFI1
18SF III
18SF IV
19SF HI
19SF IV
19ASF II
19ASF IV
19BSF 11
19BSF IV
19CSF II
19CSF IV
20SF II
20SF III
20SF IV
20ASF II
20ASF III
21SF III
21SF IV
21ASFII
21ASF11I
Screen
Size
(Meshl
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
(1971
Filter
Media






Q
Z
I
O
z
s
X
u
H
<
K
H
z
"
z
k







nw
Rate
(gpm/ft
10
16
24
e
24
16
8
16
24
32
16
16
16
16
24
16
8
16
16
8
16
8
24
PERFORMANCE
TEST DATA)
Poly Coagulant
Feed
;fl (mg/1)
0
0
0
Atlas 4A4
1.0
Atlas 4A4
1.0
Atlas 4A4
1.0
Mag.560C
1.0
Mag.S60C
1.0
Mag.560C
1.0
Mag.560C
1.0
0
Mag.560C
1.0
Here. 836
1.0
Here. 836
1.0
Atlas 4A4
1.0
Atlas 4A4
1.0
Atlas 4A4
1.0
Atlas 4A4
1.0
Atlas 4A4
1.0
SwlftX-400
1.0
SwlftX-400
1.0
SwiftX-400
1.0
SwlftX-400
1.0
Feed
(mg/1)
0
0
0
0
0
0
Alum
30.0
Alum
30.0
Alum
30.0
Alum
30.0
Alum
30.0
Alum
30.0
Alum
30.0
Alum
30.0
FeCl3 25.0
FeCl3 25.0
FeClj 25.0
Alum
30.0
Alum
30.0
Alum
30.0
Alum
30.0
Alum
30.0
Alum
30.0
% Removal of Contaminants by Screen and Filter
Suspended
Solids
77.6
72.8
62.2
67.7
38.6
41.3
72.8
56.9
81.0
64.4
51.8
56.9
59.8
72.9
58.2
83.4
92.2
71.0
65.5
67.8
49.0
56.0
54.8
Settleable
95.5
94.
6
94.8
97.
84.
85.
97.
91.
93.
91.
60.
76.
76.
78.
93.
93.
93.
5
8
2
8
2
8
7
0
7
0
3
8
9
8
89.6
86.1
95.
-
-
3


95.0
B. 0. D.
11.0
19.2
35.3
41.7
37.9
16.9
23.7
23.2
31.8
39.1
26.2
38.3
29.5
53.8
-
37.1
41.9
40.6
39.8
54.7
28.0
52.0
58.3
52.1
56
49
35
41
-
53
-
60
65
32
59
74
38
-
.8
.7
.0
.1

.9

.3
.8
.6
.5
.4
.7

47.2
71
76
61
74
61
61
64
.6
.4
.5
.4
.5
.5
.5
NOTE:  RESULTS OF SCREEN PERFORMANCE WERE BASED ON 1970 TESTING DATA
                          157

-------
           TABLE  B-l (SHEET No.3)
COMBINED SEWER OVERFLOW
Screen
Run Size
22SF II 40
22SF 111
22SF IV
22ASFII
22ASF III
22ASFIV
22BSF II
22BSF III
22BSF IV
22CSF II
22CSF III
22CSF IV
23SF II
23SF III
23SFIV
23ASF 11
23ASF III
23ASF IV
23BSF II
23BSF III
23BSF IV
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
SYSTEM
(1971
Filter
Flux Poly I
Rate Feed
Media (gpm/ftz) (ma/1)
8 SwlftX-400
1.0
16 SwlftX-400
1.0
24 SwlftX-400
8 Atlas 3A3
1.0
16 Atlas 3A3
1.0
24 Atlas 3A3
1.0
D 8 Purlfl.A-23
2 1.0
16 Purlfl.A-23
1.0
24 Purlfl.A-23
° 1.0
^ 8 Purlfl.A-23
n 1.0
X
„ 16 Purlfl,A-23
H 1.0
S 24 Purlfl.A-23
£ i.o
H
2 8 Atlas 4A4
* 1.0
16 Atlas 4A4
°
o 24 Atlas 4A4
u> I.O
24 Purlfl.A-23
I.O
16 Purlfl.A-23
1.0
8 Purifl.A-23
1.0
24 Maj.560C
1.0
8 Maj.S60C
1.0
16 Maj.S60C
1.0
FILTRATION TESTS
PERFORMANCE
TEST
Coagulant
Feed
(mg/1)
Alum
30.0
Alum
30.0
Alum
30.0
Alum
30.0
Alum
30.0
Alum
30.0
Alum
30.0
Alum
30.0
Alum
30.0
Alum
30.0
Alum
30.0
Alum
30.0
0
0
0
0
0
0
0
0
0
DATA)
% Removal of Contaminants bv Screen and Filter
Suspended
Solids
82.4
83.1
81.9
82.6
61.2
46.2
71.6
74.3
55.9
86.7
86.8
69.6
97.6
97.9
92.9
93.7
94.2
93. S
81.8
98.3
97.9
Settleable
Solids
99
91
84
93
82
75
96
67
-
.1
.3
.4
.3
.4
.9
.3
.4

96.7
86
73
97
97
96
94
93
94
79
79
79
,1
.7
.0
.1
.1
.0
.9
.0
.2
.2
.2
B. 0. D.
65.5
63.3
63.5
-
50.9
30.4
37.2
59.2
48.7
56. 9
52.9
58.9
82.7
80.4
75.6
71.3
70.3
48.1
57.9
63.7
63.1
C. 0. D.
70.8
64
61
-
-
.1
.4


33.2
60
-
-
77
52
40
75
70
72
56
67
53
65
78
63
.9


.8
.3
.7
.8
.5
.4
.6
.9
.4
.9
.7
.5
NOTE: RESULTS OF SCREEN PERFORMANCE WERE BASED ON 1970 TESTING DATA
                          158

-------
TABLE B-2
COMBINED SEWER
OVERFLOW FILTRATION
TESTS

SCREEN PERFORMANCE
Suspended

Run
No.
•-' 4SF
cn
CD
5SF
6SF
7SF
9SF
10SF
11SF
12SF
13SF
14SF
14ASF

Screen Size
20 Mesh
20 Mesh
20 Mesh
40Mesh
40 Mesh
40 Mesh
40 Mesh
40 Mesh
40 Mesh
40 Mesh
40 Mesh
Inf.
Avg.
(mg/l)
470
—
219
265
161
155
190
—
193
94
48
Eff.
Avg.
(mg/l)
390
—
173
210
133
93
137
—
144
74
36
(1970 TEST DATA)
Solids Settleable Solids
Inf.
% Removals Avg .
ml/1
17.0 10.2
—
21.0 5.4
20.8 4.4
17.4 5.1
40.0 3.2
27.9 8.8
7.6
25.4 6.S
21.3 3.4
__
Eff.
Avg.
ml/1
4.8
—
2.3
2.1
2.3
1.6
2.5
3.5
2.4
0.9
—

% Removals
52.9
-
57. 4
52.3
54.3
50.0
71.6
53.9
63.7
73.5
-
Inf.
Avg.
(mg/l)
169
—
72
49
90
61
94
-
99
59
67
B. O. D.
Eff.
Avg.
(mq/1)
160
—
56
43
80
57
90
-
94
52
60

Inf.
% Removals Avg.
(mg/l)
5.3 483
—
22.2 175
12.3 154
11.1 188
6.6 240
4.3 475
455
5.1 202
11.9 165
11.7 172
C. O. D.
Eff.
Avg.
(mg/l)
300
—
146
142
137
190
280
374
193
146
134

% Removals
37.9
-
16.6
7.8
27.1
20.8
41.1
17.8
4.5
11.5
22.1

-------
TABLE  B-3 (SHEET No.I)
COMBINED
SEWER OVERFLOW FILTRATION TESTS
FILTER PERFORMANCE
Suspended Solids
Run No.
4SF-II
1—1 4SF-III
CD
O
5SF-!
5SF-II
5SF-III
6SF-I
6SF-III
7SF-HI
8SF-1
9SF-I
9SF-II
9SF-III
9ASF-III
Media
48" #4 Anth.
36" #6 12 Sand
48" #3 Anth.
36" #612 Sand
48" #4 Anth.
48" #6 12 Sand
48" #4 Anth.
36" #612 Sand
48" #3 Anth.
36" #612 Sand
48" #3 Anth.
36" #612 Sand
60" #3 Anth.
36" #612 Sand
60" #3 Anth.
36" #612 Sand
60" #3 Anth.
36" #612 Sand
48" #3 Anth.
36" #612 Sand
48" #3 Anth.
36" #612 Sand
60" #3 Anth.
36" #6 12 Sand
60" #3 Anth.
36" #612 Sand
Flux
Rate
(qpm/ft2)
24
24
16
16
16
24
16
16
32
24
40
10
40
Poly
Feed Temp
(mq/1) PH (°F)
0 7.10 70
0 7.13 70.0
0 7.1 75.5
0 7.0 75.5
0 7.0 74.5
0 6.85 72
0 7.47 71.5
0 7.08
0 7.40 -
0 7.20 64
0 7.20 61.6
0 7.20 64
0 7.0 67
Inf.
Avg.
(mq/1)
417
390
485
470
420
173
173
205
93
114
152
114
91
Eff.
Avg. % Removal
(mq/1)
185 55.6
187 52.1
236 51.3
140 70.2
190 54.8
63 63.6
37 78.6
48 70.6
52 44.0
74 35.1
95 37.5
31 72.8
75 17.6
(1970 TEST DATA)
Settleable Solids
Inf. Eff. Inf.
Avg. Avg. % Removal Avg.
(ma/1) (mg/1) (mg/1) .
4.5 1.3 71.1 172
4.5 1.7 62.2 167
5.0 2.5 50.0 92
5.0 1.5 70.0 85
4.S 2.0 5S.6 83
2.6 0.7 73.1 63
2.5 0.35 86.0 66
2.5 0.7 72.0 53
1.8 1.2 33,3 60
2.0 1.1 45 77
2.2 0.9 59.1 78
2.0 0.07 96.5 77
1.9 0.4 78.9 95
B. O. D.
Eff.
Avg. % Removal
(mo/1)
141 18.0
130 22.2
69 25.0
60 29.4
64 22.9
49 22.2
40 39.4
45 15.1
52 13.3
67 13.0
68 12.8
49 36.4
71 25.3

Inf.
Avg.
(ma/1)
350
350
270
240
220
140
149
118
175
117
139
117
190
C.O.D.
Eff.
Avg. % Removal
(mq/1)
228 34.9
210 40.0
160 40.7
136 43.3
162 26.4
120 14.3
117 21.5
82 30.5
49 72.0
83 29.1
83 40.3
44 62 . 4
110 42.1
T.O.C.
Inf. Eff. % Removal
Avq . Avo .
-
.
-
-
-
-
-
-
-
-
-
-

-------
                                  TABLE   B-3 (SHEET No.2)
cn
COMBINED SEWER
OVERFLOW
FILTER
Run
No,
4 SF-II
4SF-II1
5SF-I
5SF-II
SSF-III
6SFM
6SF-1II
7SF;III
BSF-1
9SF-I
9SF-I1
9SF-1II
9ASF-IH
Media
48"44 Anth.
36*4612 Sand
48*43 Anth.
36 "4612 Sand
48*44 Anth.
48*4612 Sand
48*44 Anth
36*4612 Sand
48*43 Anth.
36*612 Sand
48*43 Anth.
36*4612 Sand
60*43 Anth.
36*4612 Sand
60*43 Anth.
36*4612 Sand
60*43 Anth.
36*4612 Sand
48"43Anth.
36*4612 Sand
48*43 Anth.
36*4612 Sand
60*43 Anth.
36*4612 Sand
60"43Anth.
Flux Poly
Rate Feed
fa cm/It2) (ml/1)
24 0
24 0
16 0
16 0
16 0
24 0
16 0
16 0
32 0
24 0
40 0
10 0
40 0
FILTRATION TESTS
PERFORMANCE
(1970 TEST DATA)
Water
Terminal Length
Head Loss of Run
(Ft.) (Hr.)
— 1.0
36.0 5.0
— 1.5
— 3.5
22.0 8.2
29.8 5.0
16.1 11.0
17.5 16.0
16.5 10.0
34.0 10.0
22.5 2.0
9.0 10.0
18.7 5.0
Total Volume
Filtered
306
1,655
1,440
714
1,812
7,200
2,431
3,536
4,410
14,400
1,020
1,380
2,760
Rate
qpm/ftz
70
66
SO
69
62
50
75
79
75
50
60
71
60
Length
Mln.
11.4
18.4
9.3
IS
19.5
5.8
11.3
7
5
4.5
6.9
4.6
4.5
Tot.Vol.
SSL 	
170
270
455
224
267
290
189
115
85
225
88
74
61
« Total
Water
Filtered
—
16
31.5
31.3
14.7
4.0
7.3
3.3
1.9
1.6
8.6
5.4
2.3
Air
Scfm Length
Ft2, Mln.
14 3
13.5 3.3
12 4
14 3
18 3
10.5 4
13.5 4
IS 4
IS 3.5
12 5
16.5 3.5
18 4
13.5 2.5

Filter
Area
(Ft. 2)
.213
.223
1.00
.213
.223
1.00
.223
.223
.223
1.00
.213
.223
.223
Susi
Total S.S.
In Influent
aba)
1.068
5.38
5.83
2.79
6.35
10.39
3.50
6.04
3.42
18.21
0.874
1.31
2.09

Total S.S.
In Effluent
.047
2.58
2.83
0.83
2.79
3.7B
0.75
1.41
1.94
8.88
0.806
0.35
1.72
Quantity
Theoretically
Removed In
Column flbsl
1.021
2.80
3.00
1.96
3.56
6.61
2.75
5.63
1.48
9.33
.068
.96
.37
Susp. Sol.
Removed In
Backwash
1.6
-
9.5
1.82
3.2
5.51
1.81
3.61
1.28
-
-
1.7
_
          36*1612 Sand

-------
TABLE  B-3 (SHEET No.3)
COMBINED
SEWER
OVERFLOW FILTRATION TESTS
FILTER
Suspended Solids
Run No. Media
10SF-I 48" t3 Anth.
36" #612 Sand
1—1 10SF-II 48" #3 Anth.
<-" 36" #612 Sand
CO
10SF-III 60" #3 Anth.
36" #612 Sand
10ASF-III 60" #3 Anth.
36" #612 Sand
11SF-I 48" #3 Anth.
36* #612 Sand
11SF-II 48" #3 Anth.
36" #612 Sand
11SF-IU 60" #3 Anth.
36" #612 Sand
13SF-II 48" #3 Anth.
36" #612
13SF-III 48" #3 Anth.
36" #612 Sand
13SF-IV 48" #3 Anth.
36" #612 Sand
14SF-I 48" #3 Anth.
36" #612 Sand
14ASF-1 48" #3 Anth.
36" #612 Sand
Flux
Rate
(qpm/ft2)
32
16
24
24
32
16
24
24
16
10
16
32
Poly
Feed Temp
(mg/1) £H (°F)
0 6.7 65.5
0 6.8 64.4
0 6.8 64.6
.5 7.15 65.7
.5 7.1 66.1
2.0 7.2 66.2
2.0 7.2 66.2
l.S 7.07 62.0
l.S 7.07
1.5 7.07 62.0
.5 7.0 56.6
.5 7. OS 58
Inf.
Avg.
(mq/1)
132
113
113
148
175
149
149
144
144
144
85
60
Eff.
Avg.
fmq/1) % Removal
BO 39.4
32 71.7
53 53.1
46 68.9
115 34.3
66 55.7
69 53.7
69 52. I
49 66.0
40 72.2
39 54.0
25 58.3
PERFORMANCE
(1970 TEST DATA)
Settleable Solids
Inf.
Avg.
(mq/1)
1.7
1.4
l.S
2.15
3.3
2.9
2.9
2.4
2.4
2.4
1.4
0.72
Eff.
i Avg.
(mg/lL ;
0.51
0.50
0.38
0.62
1.5
0.65
0.08
0.6S
0.28
0.3
0.31
0.13
Inf.
Avg.
ift Removal (mg/t)
70.0 93
64.3 72.5
74 . 7 72
71.2 66
54.5 100
77.6 100
97.2 100
72.9 94
88.3 94
87.5 94
77.9 64
81.9 61
B. O.
Eff.
Avg.
(mq/1)
86
62
51
63
68
67
70
75
67
66
50
46
D.
Inf.
Avg.
% Removal (mg/1)
7.5 244
14.5 192
29.2 192
4.S 151
32.0 287
33.0 287
30.0 287
20.2 193
28.7 193
29.8 193
21.9 133
24.6 134
C. O. D. T. O. C.
Eff. Inf. Eff.
Avg. Avg. Avg.
(mq/1) % Removal (mq/1) (mq/1)
187 23.4
120 37.5
126 34.4
88 41.7
230 19.9 135.7 78
200 30.3 133 71
207 27.9 133 92.2
114 40.9 67.0 40.7
98 49.2 67.0 31.1
92 52.3 67.0 25.0
95 28.6 50.0 33
127 5.2 46.0 37
-r-
-
-
42.5
46.6
30.7
39.3
53.6
62.7
34.0
19.6

-------
                               TABLE   B-3 (SHEET No.4)
00
COMBINED
SEWER OVERFLOW FILTRATION TESTS
FILTER PERFORMANCE
Flux Poly Terminal
Run Rate Feed Head Loss
No. Media fa cm/ft2) (ml/1) (Ft.)
10SF-I 48"»3Anth. 32 0 14.8
36"#612 Sand
10SF-II 48'*3Anth. 16 0 12.5
36"#612 Sand
10SF-III 60"#3Anth. 24 0 11.2
36"#612 Sand
10ASF-II1 60"#3 Anth. 24 .5 16.8
36 "#612 Sand
11SF-I 48"#3Anth. 32 .5 13.8
36"#612 Sand
11SF-I! 48"#3 Anth. 16 2.0 8.0
36 "#612 Sand
11SF-III 60"#3Anth. 24 2.0 25.0
3 6 "#612 Sand
13SF-II 48"#3Anth. 24 1.5 16.0
3 6 "#612 Sand
13SF-IH 48"#3Anlh. 16 1.5 4.7
36"*612 Sand
13SF-IV 48"*3Anlh. 10 1.5 5.2
36"#612 Sand
14SF-I 48"t3Anth. 16 .5 2.3
3 6 "#612 Sand
14ASF-I 48"»3Anth. 32 .5 22.3
Length
of Run
(Hr.l
3.0
10.5
10.5
10.0
3.5
10.0
10.0
10.5
10.5
10.5
6.0
8.0
(1970 TEST DATA)
Water
Total Volume % Total
Filtered Rate Length Tot. Vol. Water
(Gal.) gpm/ft2 Mln. Gal. filtered
5,760 49 10 490 8.5
2,142 60 9.6 122 5.7
3,475 71 4 64 1.8
3,310 — — — —
6,720 66 10.7 711 10.6
2,040 90 2.5 47 2.3
3,210 52 4 47 1.4
3,213 70 25 371 4.2
2,328 31 14 95 4.1
1,335 32 13.5 91 6.8
5,760 — — — —
15,560 — — — —
Air , Suspended Solids Mass Balance Analysis
Filter Total S.S. Total S.S.
Scfm Length Area In Influent In Effluent
Ft2 Mln. . (Ft.2) (Lbs) (Lbs)
10 4 1.00 6.33 3.84
15.5 4 .213 2.02 0.57
12 3 .223 3.27 1.53
— — .213 4.02 1.27
6.8 10 1.00 9.80 6.45
2.4 6 .213 2.53 1.12
2.1 3 .223 4.0 1.90
4.0 3 .213 3.85 1.85
4.1 29 .223 2.78 .95
4.0 9 .213 1.60 .44
— — 1.00 4.08 1.87
— — 1.00 7.66 3.29
Quantity
Theoretically
Removed in
2.49
1.4S
1.74
2.75
3.35
1.41
2.11
2.00
1.83
1.16
2.21
4.46
Susp. Sol.
Removed In
Backwash
1.86
.51
—
-
2.05
.695
8.0
1.19
.36
—
—
           36"*612 Sand

-------
                        TABLE  B-3 (SHEET No.5)
            COMBINED  SEWER  OVERFLOW  FILTRATION  TESTS
                          FILTER  PERFORMANCE
                                 (1971 TEST DATA)
                     Suspended Solids	Scttleable Solids	BOP	COD	Total Phosphorus
Run No.
17SF1I
17SFIII
17SFIV
18SFII
18SFI1I

19SFIII
19SFIV
19ASFII
19A8FIV
19BSFII
19BSFIV
Flux
Rate
faom/ft2)
10
16
24
8
24

8
16
24
32
16
16
Coagulan
Feed
(mq/1)
0
0
0
0
0
g

Alum
30.0
Alum
30.0
Alum
30.0
Alum
30.0
Alum
30.0
Alum
t Polymer
Feed
(mo/1) pH
0
0
0
Atlas 4A4 6.8
1.0
Atlas 4A4 6.8
1.0
1.0
Mag. 560C 6.7
1.0
Mag. 560C 6.7
1.0
Mag. S60C 6.8
1.0
Mag. S60C 6.8
1.0
7.2
Mag. S60C 7.3
Temp.
(°F)
53
S3
53
62
62

68
68
69
69
70
70
Inf.
Avg.
. (mq/1)
223.9
209.5
214.8
362.3
362.3
362 5

301.7
324.5
192.0
192.0
278
221
Eff.
Avg.
(mq/1)
66
74.8
10E.8
153. 3
292.4
256 7

108.0
181.0
48.0
90.0
176.3
125.3
% Removal
70.5
64.3
50.3
57.5
19.3
29. 1
64.2
44.2
75.0
53.1
36.6
43.3
Inf.
1 Avg.
(mq/1)
2.3
2.3
2.4
3.3
3.3
3.1
3.8
3.8
2.0
2.0
2.5
'2.5
Eff.
Avg.
(mo/1)
.2
.3
.3
.2
1.2

.2
0.8
0.3
.4
2.4
1.4
% Removal
91.3
87.0
87.5
93.9
63.6

94.7
78.9
85.0
80.0
4.0
44.0
Inf.
Avg.
tag/1)
279.2
259.2
257.5
173.2
173.2
154*8
425
457.5
37
37
43.7
44.8
Eff.
Avg.
(mq/1)
275. 8
232.5
185.0
112.3
119.8
142 1 7
360
390
28
25
35.8
30.7
Inf. Eff. Inf. Eff.
% Removal Avg. Avg. % Removal Avg. Avg. % Removal
(mg/1) (mg/1) (mg/1) (ma/1)
1.2 265 165.3 37.6
10.3 265 149 43.8
28.2 301 196.8 34.6
35.2 488.3 412. S 15.5
30.8 488.3 373.8 23.4

15.3 138.5 83.0 40.1 .61 .16 73.8
14.8 -- -- — .57 .37 35.0
24.3 141 72.7 48.4 .51 .19 62.7
32.4 141 62.7 55.5 .51 .20 60.8
18.1 173.8 152.2 12.4 .50 .31 38.0
31.5 177.8 93.7 47.3 .50 .21 58.0
Length of Total
Run Head Loss
(Hours) (ft.)
6.0 4.2
6.0 6.2
4.0 28.8
5.5 4.6
5.5 10.9
5.5 8.7
5.5 10.3
5.5 23.1
3.0 31.4
3.0 39.3
6.0 X17.5
6.0 12.9
  Modto
60- No. 3 Anlh.
36- No. 612 Sand

-------
TABLE B-3 (SHEET No.6)
COMBINED SEWER OVERFLOW FILTRATION TESTS
FILTER PERFORMANCE

(1971 TEST DATA)
Suspended Solids Settleable Solids BOD
Flux Coagulant Polymer Inf. Eff. Inf. Eff. Inf. Eft.
Rate Feed Feed Temp. Avg. Avg. % Removal Avg. Avg. % Removal Avg. Avg.
Run No. (
-------
                                                     TABLE    B-3  (SHEET  Ho.7)
                                  COMBINED   SEWER   OVERFLOW   FILTRATION   TESTS
                                                        FILTER    PERFORMANCE
                                                                  (1971  TEST DATA)
                                                Suspended Solids
                                                                Settleable Solids
                                                                                  BOD
                                                                                                   COD
                                                                                                               Total Phosphorus
en
                                                                                                  89.3   13.3


                                                                                                  85.5   49.3
       Flux  Coagulant Polymer          Inf.  £ff.           Inf.  Elf.         Inf.   Eff.          Inf.  Eff.          Inf.  Eff.
       Rate    Feed   Feed       Temp Avg.  Avg. '% Removal   Avg. Avg. % Removal Avg.  Avg.  % Removal  Avg.  Avg.  % Removal  Avg.  Avg. % Removal
Run No.  (gpm/ft2) (ma/I)   fag/1)    PH I°F)  (mo/1) (mg/1)	(mo/11 (ma/1)	 (mo/1)  (mg/1)	(mo/11 (mg/1)	(mq/1) (mq/11

22SFIII


22SFIV


22ASFII


22ASFIII


22ASFIV


22BSFII


22BSFI1I


22BSFIV


22CSFII


22CSFIII


22CSFIV


23SFII


       Media

    60" No. 3 Anth.
    36" No. 612 Sand
16
24
8
16
24

8

16

24

8

16

24

8

Alum
30.0
Alum
30.0
Alum
30.0
Alum
30.0
Alum
30.0
Alum
30.0
Alum
30.0
Alum
30.0
Alum
30.0
Alum
30.0
Alum
30.0
0

Swift x-400 7.5 69 322.7
1.0
Swift x-400 7.5 69 322.7
1.0
Atlas 3A3 7.2 60 251.0
1.0
Atlas 3A3 7.2 60 251.0
1.0
Atlas 3A3 7.2 60 251.0
1.0
Purlfl.
1.0
Purlll.
1.0
Purlfl.
1.0
Purlfl.
1.0
Purlfl.
1.0
Purlfl.
1.0

A-23 6.6 51 159.7

A-23 6.6 51 159.' 7

A-23 6.6 51 159.7

C-31 6.j 50 217.5

C-31 6.5 SO 217.5

C-31 6.5 SO 222.5

Atlas 4A4 7.1 49 300.7
1.0

71
77
57,
128
177

59

54,

92.

38,

65.

89.

10.

.7
.0
.3
.0
.5

.7

.0

.5

,0

,3

.0

0

77.8
76.1
77.1
49.0
29.3

62.6

66.2

42.1

82.5

70.0

60.0

96.7

2.4 .5 79.2 100.0 40.8
2.4 .9 62.5 100.0 40,5
1.9 .2 84.2 43.7 26.2
1.9 .8 57.8 43.7 23.8
1.9 1.1 42.1 43.7 33.8

2.3 .2 91.3 43.0 30.0

2.3 1.8 21.7 43.0 19.5

- - - 43.0 24.5

1.9 .15 92.2 65.8 31.5

1.9 .63 66.8 66. 8 34.5

1.9 1.2 36.8 65.3 30.0

1.4 <0.1 92.8 66.3 12.7

59.2
59.5
40.4
45.5
22.7

30.2

54.7

43.0

52.1

47.6

54.4

80.8

1.0
1.0
.82
.82
.82
.90
.90
.90
.68
.68
.68
.51
.59
.50
.58
.52
.24
.47
.52
.14
.29
.50
49.0
41.0
39.0
29.3
36.6
73 J
47.8
42.2
79.4
57.4
23.5
6.0
3.0
6.0
6.0
6.0
6.0
3.0
5.0
4.0
4.0
4.0
                                                                                                                           Length of   Total
                                                                                                                             Run  Head Loss
                                                                                                                            (Hours)    (ft.)
22.2


14.3


 2.14


 5.1


13.5


 4.2
                                                                                                                                   5.4


                                                                                                                                   9.2


                                                                                                                                  12.0

-------
TABLE  B-3 (SHEET No.8)
Flux Coagulant
Rate Feed
Run No. (gpm/ft2) (mg/1)
23SFIII 16 0
23SFIV 24 0
23ASFI1 24 0
23ASFIII 16 0
23ASFIV 8 0
23BSF11 24 0
23BSFIH 8 0
23BSFIV 16 0
Media
60" No. 3 Anth.
36" No. 612 Sand
COMBINED SEWER OVERFLOW FILTRATION TESTS
FILTER PERFORMANCE
(1971 TEST DATA)
Suspended Solids Settleable Solids BOD COD Total Phosphorus

Polymer Inf. Elf. Inf. Eff. Inf. Eff. Inf. Eff. Inf. Eff. Length of Total
Feed Temp. Avg. Avg. % Removal Avg. Avg. %-Removal Avg. Avg. % Removal Avg. Avg. % Removal Avg. Avg. % Removal Run Head Loss
(mg/1) pH C°FJ (mo/1) (mg/1) (mg/1) (mg/1) (mg/1) (mg/1) (mg/1) (mg/1) (mg/1) (mg/1) (Hours) (ft.)
Atlas 4A4 7.1 49 300.7 9.0 97.0 1.4 <0. 1 92.9 66.3 14.5 78.1 189.2 72.5 61.7 - - - 5.0
1.0
Atlas 4A4 7.1 49 300.7 28.0 90.7 1.4 .13 90.7 66.3 18.0 72.9 189.2 67.8 64.2 - - 5.0
1.0
Purlfl. A23 7.5 50 210.7 17.7 91.6 .7 < 0. 1 85.7 44.8 14.3 68.1 156.2 48.7 68.8 .71 .40 43.7 4.0
1.0
Purlfl. A23 7.5 50 210.7 16.3 92.3 .7 <0.1 85.7 44.8 14.8 67.0 156.2 65.2 58.3 .71 .39 45.1 6.0
1.0
Purlfl. A23 7.5 50 210.7 18.0 91.5 .7 <0.1 85.7 44.8 25.8 42.4 156.2 60.5 61.3 .71 .43 39.4 6.0
1.0
Mag. 560C 6.9 50 392.8 94.0 76.1 2.0 1.0 50.0 67.0 31.3 53.3 161.2 70.5 55.6 .76 .55 26.3 3.0
1.0
Mag. 560C 6.9 SO 392.8 8.9 97.7 2.0 <0.1 50.0 67.0 27.0 59.7 161.2 44.5 72.4 .76 .40 47.2 6.0
1.0
Mag. 560C 6.9 50 392.8 7.0 98.2 2.0 0.1 50.0 67.0 27.5 59.0 161.2 73.5 54.4 .76 .36 52. 6 4.0
1.0


19.9
40.9
12.3
9.7
5.3
26.7
6.6
12.3



-------
TABLE  B-4
COMBINED
SEWER OVERFLOW FILTRATION TESTS
COLIFORM
Run
Mo-
4SF-II
4SF-11I
ssr-i
ssr-ii
ssr-m
6SF-I
6SF-III
7SF-III
8SF-HI
9SF-1
9SF-11
9SF-1H
9ASF-I1I
10SF-!
10SF-II
10SF-III
10ASF-1I!
11SF-1
USF-II
USF-1II
13SF-I1
13SF-1I1
13SF-IV
14SF-1
14ASF-I
Media
48"44Anth.
36"V612Sand
48"43Anth.
36-4612 Sand
4 8 "44 Anth.
48 "#612 Sand
48-44 Anth.
36-4612 Sand
48"43 Anth.
36-4612 Sand
48"43 Anth.
36-4612 Sand
60 -43 Anth.
36-4612 Sand
60 "43 Anth.
36 "4612 Sand
60"43 Anth.
36-4612 Sand
48 "43 Anth.
36-4612 Sand
48-43 Anth.
36-4612 Sand
60*43 Anth.
36-4612 Sand
60-43 Anth.
36*4612 Sand
48"43 Anth.
36-4612 Sand
48"43 Anth.
36"*612 sand
60 "43 Anth.
36-4612 Sand
60"43 Anth.
36-4612 Sand
48"t3Amh.
36"f612 Sand
48"»3 Anth.
36-4612 Sand
60 "*3 Anth.
36-4612 Sand
48-43 Anth.
36-4612 Sand
48-43 Anth.
36-4612 Sand
48 "43 Anth.
36"4 612 Sand
48 "43 Anth.
36*4612 Sand
48"43 Anth.
36'4612Sand
Flux'
Rate .
24
24
16
16
16
24
16
16
32
24
40
10
40
32
16
24
24
32
-16
24
24
16
10
16
32
REDUCTION BY FILTRATION
(1970 TEST DATA)
Fecal Conform Total Conform
Inf.Avg. Eff.Avg. mf.Avg. Eft. Avg.
Poly .No.xlO6 No.xlO6. % . xlO6 X106 *
Feed 1 100ml ' 1 100ml ' Removal ' 100ml ' ' 100ml ' Removal
0 1.6 1.2 25 — — —
0 1.3 1.2 7.6 — — —
0 .93 .7 24.8 33.0 — —
0 .85 .8 5.8 33.0 11.0 66.6
0 .74 .4 46.0 33.0 — —
0 1.8 .8 55.5 1.9 — —
0 1.7 1.0 41.3 1.9 — —
0 3.1 — — 7.0 15.0 0
0 1.0 .8 20.0 7.6 2.8 63.2
0 15.2 13.7 9.8 29.5 11.4 61.4
0 — 4.6 — 29.5 10.0 66.1
0 15.2 2.7 82.2 29.5 4.0 86.4
0 3.2 2.8 12.5 52.5 26.7 49.2
0 5.1 4.8 11.0 16.0 22.0 0
0 4.6 2.8 39.2 16.0 25.3 0
0 4.6 2.1 54.4 16.0 19.2 0
D.5 1.8 1.0 44.4 5.6 3.9 30.3
0.5 11.0 10 9.2 79.7 51.5 35.3
2.0 11.0 8.3 24.6 79.7 41.0 48.5
2.0 11.0 7.8 29.1 79.7 47.0 40.4
1.5 4.1 2.8 31.7 24.3 6.B 72.0
1.5 4.1 2.7 34.2 24.3 1.2 66.2
1.5 4.1 2.8 31.7 15.0 1.0 93.4
0.5 3.5 2.3 34.2 21.0 16.3 22.4
0.5 3.3 2.0 39. ^ 15.3 5.5 64.1
   168

-------
           TABLE  B-5 (SHEET No. I)
COMBINED  SEWER OVERFLOW FILTRATION TESTS
      SOLIDS  REDUCTION  BY  FILTRATION
                  (1970 TEST DATA)
                                      Total Volatile Solids

Flow
Run Flux
No. Media fej»m/ftz)
4SF-1I 48"»4Anlh.
36"#612 Sand
4SF-III 48"MAnth.
36"(t612 Sand
SSF-I 48"#-1Anth.
36"*612 Sand
5SF-II 48"#4Anth.
36"t612 Sand
SSF-III 48"#3Anth.
,_. 36"*612Sand
CD
/Q 6SF-I 48"#3Anth.
36"#612 Sand
6SF-HI 60"*3Anth.
36"#612 Sand
7SF-III eO'tUAnl1).
36"*612 Sand
8SF-III 60"»3Anth.
36"#612Sand
9SF-I 48"#3Anth.
36"*6I2 Sand
9SF-II 48"#3Anth.
36"*612 Sand
9SF-HI 60"43Anth.
36"»6l2Sand
9ASF-III 60"it3Anlh.
36"*612 Sand
IOSF-1 48"
-------
                                                  TABLE    B-5  (SHEET  No.2)
                           COMBINED   SEWER    OVERFLOW   FILTRATION    TESTS
                                         SOLIDS   REDUCTION    BY    FILTRATION
                                                                 (1970  TEST  DATA)
                                                                                      Total "olatile Solids
                                           Grab
Run
No^

11SF-I


11SF-II


11SF-1II


13SF-II


13SF1II






14SF-I


14ASF-I
                 Flux  Feed   Avg.  Avg.  Inf.   Eff.   %                                    %        Inf.   Eff.   %        Inf.   E«.   %                 %
      Media     (gum/ft2) mg/1   ITU   ITU   Avg.   Avg.  Removal   Inf.  Elf.  * Removal  Inf.  Eff.   Removal   Avq.  Avg.   Removal   Avq.   Avg.  Removal   Inf.  Eff.  Removal
      48"#3Anth.
      36"*612 Sand
      48"#3Anth.
      36"»612Sand
      60"*3Anth.
      36"*612 Sand
      48"*3Anth.
      36"»6I2 Sand
      4S"#3Anth.
      36 "»612 Sand
      48"#3Anth.
      36"#612 Sand
      48"»3Anth.
      36"*612 Sand
      48"*3Anth.
      36"#612 Sand
Flow  Poly   Inf.    Eff.
Flux  Feed   Avg.  Avg.  Inf.   Eff.   %
/ft2)  mg/1   TTU   ITU   Avg.   Avg.

 32   .5     178   135   582   532   8.6


 16   0      170   106   565   447   20.8


 24   2.0    170   111    565   509   9.9


 24   1.5    167   109   435   351   19.3


 16   1.5    167   102   435   314   27.8



 10   1.5    167   100   435   318   26.8


 16   .5    111     67   301   262   12.9



 32   .5     62     46   386   371   3.9
                                                             Composite
                                                                                                  Composite
                                                                                                                         Total Nonvolatile Solids
 —   512   —



478   468  2.1


478   453  5.2


378   319  15.6


378   296  21.7



378   265  30.0


280   240  14.3


204   227   0
                                                       180   175  2.8


                                                       180   167  7.2



                                                       180   136  24.4


                                                       118   95  19.5
                                                                US    99    13.9


                                                                115    91    20.8



                                                                US    82    28.7


                                                                116    99    14.6
202   167   17.3


202   149   26.3



202   162   19.9


139   112   19.4
  263   220  16.4


  263   205  22.0



  263   183  30.5


  164   HI   14.0


  131   149  0
Run
N°-
         Media
Flux
Rate
                                         Total Suspended Solids
                                                                             Volatile Suspended Solids
                                                                                                                       Nonvolatile  Suspended Solids
Poly   Inf.   Eff.    %                11        In'-    Eff.  *                *        Inf.    Eff.    %                     %
Feed   Avg.  Avg.   Removal   Inf.  Eff.  Removal   Avg.   Avg.   Removal   Inf.  Eff.  Removal   Avg.    Avg..   Removal    Inf.    Eff.    Removal
         48 "#3 Anth.
         36"#612 Sand
         48"*3 Anth.
         36"#612 Sand
         48"»3 Anth.
         36>'# 612 Sand
         48"#3 Anth.
         36"ttG12 Sand
         48"*3 Anth.
         36"#612 Sand
24       1.5    116   63    45.7      —    —   —


16       1.5    116   37    68.0      —    —   —


10       1.5    116   30    74.0      —    —   —


16       0.5    83    49    41.0      110    45   —


32       0.5    —   —    —       86    60   31
                                           62    39    37.0     —   —    —       54     26     52.0


                                           62    23    63.0     —   —    —       54     12     78.0


                                           62    21    66.0     —   —    —       54     9      83.0


                                           48    33    31.2     71   34    52.0     36     16     56.0



                                           —    T—    —      70   46    33.5     —     —     —
39


'.7
                                                                                                                                         11


                                                                                                                                         13

-------
                                       TABLE   B-6  (SHEET  No.l)


                    COMBINED   SEWER   OVERFLOW   FILTRATION   TESTS


          PHOSPHATE,  NITROGEN  AND  GREASE   REDUCTION   BY FILTRATION

                                                    (1970  TEST DATA)





                         	Total Phosphate		Soluble Phosphate	  	Nitrogen	   	Grease	
                         	Grab	     Composite	   	Grab	   	Composite	Composite	       Composite	
              Plow    Poly   Inf.   Eff.          Inf.   Eff.          Inf.   Eft.          Inf.   Eff.          Inf.   Eft.          Inf.  Eff.
Run            Flux    Feed   Avg.  Avq.   «      Avg.   Avg.  *      Avg.  Avg.  *       Avg.   Avg.   %      Avg.   Avg.   *       Avg.  Avg.   %
No.    Media    qmp/ft^  mq/1   mq/1  mq/1   Removal   mq/1   mg/1  Removal   mg/1  tnq/1  Removal   mq^   mq/1   Removal  mg/1   mq/1   Removal   mq/1  mq/l   Removal

4SF-H . 48"44 Anth.  24     ' 9     —   —     —     __—      ___      —   —     ____     __     _
     36"4612 Sand

4SF-HI 48"#3Anlh.  24      0     —   —     —     2.SO   2.40  14.3      —   —    -      —   —     —    18.2   14.8   18.6     —   —     —
     36-4612 Sand

5SF-I  48"43Anth.  16      0     —   —     ____      ___      _—     —     ___      ___
     48"t612 Sand

5SF-II 48"44 Anth.  16      0     —   —     ____      ___      _—     ____      ___
     36"*612 Sand

5SF-III 48"43Anth.  16      0     —   —     —     ___      ___     _    —     ____      ___
     36-4612 Sand

6SF-I  48-43Anth.  24      0     —   —     —     0.75   0.40 46.6     —   —    —     —    —     —    23.2   24.9   0      16.2  19.-3    0
     36-4612 Sand

6SF-III 60"43Anth.  16      0     —   —     —     0.75   0.60 20.0     —   —    —     —     —     —    23.2   19.9   14.2     16.2  32.7    0
     36"4612Sand

7SF-III 60"43Anth.  16      0     —   —     —     1.00   1.25   C       —   —   —     —    —     —    10.2   6.6   35.1     6.4  3.8    40.6
     3 6 "4612 Sand

8SF-III 60'43Anth.  32      0—   ——     —    ——      —   —   —     —_     —    __-_     ___
     36-4612 Sand

9SF-I  48'43Anth.  24      0     —   —     —     0.40   0.03 90.0     —   —   —     —    —     —    11.1   9.9   10.9     20.9  20.6   l.S
     36 "#612 Sand

9SF-H 4B"«Anth.  40      0     —   —     —     0.40   —   —       —   —   —     ___    u.i    _   _      _   _     _
     36"*612 Sand

9SF-III 60"»3Anth.  10      0     —   —     —     0.40   0.30 85..S     —   _   _     _    —     _    H.I   8.4   24.2     20.9  7.5    44.2
     36-4612 Sand

9ASF-III 60-«Anth.  40      o—   —————       —   —   —     —    —     —    —__      —   _    _
     36'* 612Sand

-------
                TABLE  B-6 (SHEET No.2)
     COMBINED  SEWER  OVERFLOW  FILTRATiON  TESTS
PHOSPHATE, NITROGEN AND  GREASE  REDUCTION BY FILTRATION
                        (1970 TEST DATA)

               Total Phosphate       I..I_T	^Soluble Phosphate
Run
No.
103P-I
•— ' 10SF-II
•V]
00
losr-m
_ Media
4fl"#3Anlh.
36"#612 Sand
48"#3Anth.
3 6 "#612 Sand
60'#3Anlh.
3 C -it 612 Sand
10ASF-III60"#3Anth.
3 6 "#612 Sand
11SF-1
11SF-I!
11SF-1II
13SF-II
13SF-III
13SF-IV
14SF-I
• 14ASF-I
48"#3Anth.
36"#612 Sand
48"#3Anth.
36"#612 Sand
60"#3Anth.
36"#612 Sand
48"#3Anth.
36"#612Sond
48"t3Anth.
36"#612Sand
48"*3Anth.
36"t612 Sand
48"»3An«h
36"»612 Sand
48"#3Anth.
36"»612 Sand
Flow
Flux
gmp/ft2
32
16
24
24
32
16
24
24
16
10
16
32
Grab
Poly Inf. Iff.
Feed Avg. Avg.
mq/1 n.g/1 mg/1
0 — —
0 — —
0 — —
.5 — —
.5 — —
2.0 — —
2.0 — —
l.S 10.5 6.6
l.S 10.5 5.8
l.S 10. 5 6.8
0.5 10.1 9.8
0.5 11.1 11.9
Cor
Inf.
% Avg.
Removal mq/1
— 1.6
— 1.6
— 1.6
- -
— 0.6
— 0.6
— 0.6
37.1 6.0
44.7 6.0
35.1 6.0
3.0 14.0
0 11.0
oposlte
Eff.
Av9.
mq/1
-
1.3
l'.3
-
1.4
1.3
1.1
6.8
8.1
5.4
8.8
11.0
Grob Composite Composite
Inf. Eff. Inf. Eff. Int. Eff.
"X Avg . Avg . % Avg . Avg . % Avg . Avg . %
Removal rcq/1 mq/1 Removal mq/1 mq/1 Removal mq/1 mq/1 Removal
— ___ — — —8.7— —
18.7 — — — — — — 8.7 7.0 19. S
18.7 — — — — — — 8.7 7.0 19.5
_ ___ ___ ___
0 — — — — — — 22.1 12.7 42.5
0 — — — — — — 22.1 16.5 25.4
0 — — — — — — 22.1 18.9 14.5



37.1 3.2 2.9 9.4 2.9 2.6 10.4 9.5 7.4 22..
0 28.3 3.8 — 6.0 4.9 18.3 10.2 11.1 0
Composite
Inf.
Avg.
mgil
25.5
2S.5
25.5
-
28.4
28.4
28.4
10.9
10.9
10.9
23.0
48.4
V.i.
Avq.
mg/1
-
13.9
18.5
-
19.4
5.8
16.4
47.5
22.4
5. 5
6.5
27.5
*
Removal
-
45. 5
27.4
-
31.6
79.6
45.1
0
0
49.5
31.8
43.2

-------
CO
    600
    200
            >Z
                 INFLUENT
<:uu
I 150
d
d
oi 100
Rrt
	 1
4\

.
^ 	 INF
•FFLUEN

LUENT
T









.
**uu
«? 300
E_^
5
Q 200
o
inn
N
/
>
^-INFL

v — EFF
JENT

-UENT









                    468
                     TIME  (HOURS)
                                       10
12
SCREEN20.MESH. FILTER MEDIA-lJL In. NaJ- ANTH./lg. in. No. 6'2 SAND
DATE 9/3/70  FLUX RATE	24.

RUN
                              gpm/ft'
COMBINED SEWER OVERFLOW FILTRATION TEST
                                      FIGURE  Cl
                        173

-------
 o
 s
 111
 or
 UJ
100
 90
 80
 70
 60
 50
 40
 30
 20
 10
  0
                    s.s.
                    C.O.D.
                      B.O.D.
 UJ
 X
       20
       10
          0
              DEPTH (IN.)
                 468
                  TIME  (HOURS)
10
12
SCREEN 2P_MESH. FILTER MEDIA. 4J_in.No._l_ANTH./-36_in.No._§_i2__sAND
HATF 9/3/70 n IIY RATE	24	^/ft2
RUN No. 4SF1I
COMBINED  SEWER  OVERFLOW FILTRATION  TEST
                                           FIGURE C2
                          174

-------
t»uu
400
200
r\

X •

— =^

^ 1
, \
"••*._.*-
"^1
N—
MFLUENT

^v.
_,--*
^^




EFFLUENT












d
d
oi
200



100



  0
                   INFLUENT
                     EFFLUENT
DUU
^ 400
E
d
d 200
o
n


•^%<
	 *• -



.--"••
^C^
v_EF



/—INFLUENT
*<
mm ••
:FLUENT

















        0
                468

                 TIME  (HOURS)
                                        10
12
SCREEN20MESH FILTER  ME PI AM- in. No.-l- ANTH./-1§. in. No. 6'2 SAND
                        24
                          gpm/ft'
DATE 9/3/70 FLUX RATE-

RUN No. 4SFIII

COMBINED  SEWER  OVERFLOW  FILTRATION TEST

                                       FIGURE C3
                        175

-------
 §
 o
 5
 LJ
 CC

 cr
 CO

 CO

 O
 _1

 Q

 <

 LJ
      20
10
                      DEPTH (IN.)
         0
               468


                TIME (HOURS)
10
12
                        3 AMTH/36 in
SCREEN20.MESH. FILTER MFDIA 48  m.


DATE 9/3/70 FLUX RATE _ 24 _


RUN N0.4SF1H


COMBINED SEWER OVERFLOW FILTRATION TEST


                                        FIGURE C4
                        176

-------
V)
o>
£^

d
Q
CQ
OVJVJ
400
200
0
150
100
50
O
^
"* ?'
L.
— T"
V


>


NFLUENT

-EFFLUE

NT





















^

/—IN FLU
FFLUEN

ENT
T










 O
 d
^ww
200
100
n
.5:
>

INFLUEN
[FFLUEN

T
T










                     468

                      TIME  (HOURS)
         10
12
SCREEN^OMESH. FILTER MEDIA!§-in.No._i_ANTH./A^ in.No.612 SAND
                                   2
DATE 9/8/7Q  FLUX RATE	II.
gptn/ft1
RUN No. 5SFI	

COMBINED gEWER  OVERFLOW FILTRATION  TEST

                                       FIGURE C5
                       177

-------
1 W
90
80
H 70

/
,V
/
/




x^~S.S.

FB.O.D.

— C.O.D.









































 CO
 05
 O
 _l

 Q
 <
 LJ
      20
10
                DEPTH (IN.)
         0
               468

                TIME  (HOURS)
10
12
SCREEN20.MESH. FILTER MEDIA. 48 . in.No.-±-ANTH./-l§in.No. 6>2  .SAND

DATE 9/8/70 FLUX RATE	\&	^n^

RUN No. 5SFI	

COMBINED  SEWER OVERFLOW FILTRATION TEST

                                         FIGURE  C6
                         J.78

-------
toUU
«? 400
E
3 20°
n
V
""N

EFFLUE
X^


— r- ****
^•HNFL
NT -,
^e^-



UENT





















q
Q
CO
     150



     100



     50



      0
                    INFLUENT
                    EFFLUENT
 6
 o
    300



    200



     100



      0
                     INFLUEN
                      FLUENT
                     468

                      TIME  (HOURS)
                                        10
                                              12
SCREEN20MEsH. FILTER MEDIAA§_ in. NaJJ-ANTH./-Jg- in. No. 6l2 SAND
                                    2
                         16
                               gpm/ft'
DATE 9/8/70  FLUX RATE-

RUN Mn 5SFII

COMBINED  SEWER  OVERFLOW  FILTRATION TEST

                                       FIGURE C7
                       179

-------
1 W
90
^ 80
^ 70
g 60
1 50
LJ
" 40
a:
£ 30
£ 20
10
n


\
\

4
J

1



/<
s ^


/^/
/ \\
\
Y
\

r-S.S.



rC.O.D.

/-B.O.C









.






















 cn
 w
 o
 LJ

 X
       20
10
                       DEPTH (IN.)
                        •81
                — 45
                       /- 27
                      468

                       TIME  (HOURS)
                                   10
12
SCREEN20_MESH. FILTER MEDIA.18_in.No.J_ANTH./-liin.No._§I2__SAND


HATF 9/8/70  niiv RATE	li	ffl"1/"2


RUN No. 5$FU


COMBINED  SEWER OVERFLOW FILTRATION TEST


                                          FIGURE C8
                         180

-------
3
600


400
      0
               EFFLUENT
                            —INFLUENT
d
o
CD
o>


 Q
 O
 6
        0
                 468

                  TIME (HOURS)
10
12
SCREEN2p_MESH. FILTER MEDIA-i*L in. No._l_ ANTH./J*6 in. No.6R.SAND

HATF 9/8/70  FLUX RATE	L§	9Pm/ft2

RUN No. 5SF1II

COMBINED  SEWER  OVERFLOW  FILTRATION TEST

                                       FIGURE C9
                        181

-------
 CO
 _J
 o
 S
 UJ
 o:
 H
 U.

 CO
 CO
 o
 _J

 o
 <
 LJ
       20
10
                                    DEPTHdN.)
                      468

                       TIME  (HOURS)
                                   10
12
SCREEN2P.MESH. FILTER MEDIA.^8_in.No.^_ANTH./16 in.No._6i2__SAND

DATE 9/8/70 FLUX RATE	£	5?"/ft2


RUN No. 5SFHI


COMBINED  SEWER OVERFLOW FILTRATION TEST


                                          FIGURE CIO
                        182

-------
CO
300

200

100

  0
                   -INFLUENT
                             - EFFLUENT
o>

d
o
CD
     300
o>
 c
 d
                     4      6      8
                      TIME  (HOURS)
                                    10
SCREEN2QMESH. FILTER MEDIA-Jg_ \n. No.-3—ANTH./-36 jn. No. 6'2 SAND
HATF 9/19/70  FLUX  RATE.__li__9prn/ft2
RUN Mn 6SFI
COMBINED  SEWER OVERFLOW FILTRATION TEST
                                        FIGURE Cll
                        183

-------
1 ww
90
80
2 70
V)
g 60
i so
UJ
40
o:
* 30
u~ 20
10
n



j
—"

Vx
\s
\
V.




/ — S.S.
r
*- 	 l

-C.O.D.
X
^..— .
*"• — i
n




-\
\

^"^s*4
/-*
^- B.O.D.






























 CO
 CO
 o
 UJ
 X
      20
10
       0
                            DEPTH (IN.)
         0
               468
                TIME  (HOURS)
10     12
                             /36 in Mn 612
SCREEN20MESH. FILTER MFHIA 48 ?n,Mn 3
HATF 9/19/70  n iiv RATE _ £4
RUN MQ 6SFJ
COMBINED SEWER OVERFLOW  FILTRATION TEST
                                        FIGURE CI2
                       184

-------
CO
o>
^
d
o
CD
o>
6^
 d
 o
 d
        0
468

 TIME  (HOURS)
10
12
SCREEN2Q.MESH. FILTER MEDIA-&CL in. Na_2_ ANTH./_2£. in. No._£12_SAND

DATE 9/19/70  FLUX RATF     16     gpm/ft2

RUN No. 6SFJIE

COMBINED  SEWER OVERFLOW FILTRATION TEST

                                        FIGURE C13
                        185

-------
CO

i
o
LJ
a:
UJ
 LL
      100
      80


      70
       10


       0
            B.O.D.
X-
    =y
                 ,  N.
                  c.o.o.


 H
 u.

 CO
 CO
 o
 LJ
 X
      20
                                          DEPTH (IN.)
         0
                      468

                       TIME  (HOURS)
                             10
12
SCREEN2Q_MESH. FILTER MFDIA 60  in.MO 3  MTH./36 8n i^n 612 SAMR

DATE_9/i9/70_ FLUX RATE	L§	iE"1/^2

RUN No. 6gF?{l

COMBiNED  SEWER OVERFLOW FILTRATION TEST

                                          FIGURE CI4
                        186

-------
CO

CO
 ci
 o
 CD
                      LUENT
                    EFFLUENT
o>
E^
 d
 o
 d
        0
468

 TIME  (HOURS)
10
12
SCREEN40.MESH. FILTER MEDIAE in. No._£_ANTH./_3_6 in. No..£i2LSAND

DATF 9/23/70  FLUX RATF     16     gptn/ft2

RUN Nn 7SFBI

COMBINED  SEWER OVERFLOW FILTRATION ..TEST

                                        FIGURE CIS
                        187

-------
 ^g

 CO
 LJ
 oc
 oc
 LJ
 I-
 CO
 CO
 O
 LJ
 X
       20
10
                                           DEPTH (IN.)
         0
                468
                 TIME (HOURS)
10
12
SCREEN.4QMESH. FILTER MEDIA.j60_in.No.-l-ANTH./-3£in.No.  612  SAND
DATE 9/23/70  FLUX RATE	!§	W"/"2
RUN NoT-SFJK
COMBINED  SEWER OVERFLOW FILTRATION TEST
                                          FIGURE CI6
                        1S8

-------
CO
CO*
o>
£
O
CD
 Ci
 q
 o
        0
468
 TIME  (HOURS)
10
SCREEN.1P.MESH. FILTER  MEDIA^O- in. Na-3_ ANTH./-36 jn. No. 6'2 SAND
DATE 9/28/70 FLUX RATE	32	W"2
RUN No. 8SFIII
COMBINED  SEWER  OVERFLOW FILTRATION  TEST
                                       FIGURE C 17
                      189

-------
 o
 5
 LJ
 OH

 an
 LJ
 H
 U.

 eo
 eo
 o
 _i

 o
 <
 LU
      20
10
                                         DEPTH (IN.)
                      468

                       TIME (HOURS)
                                  10
12
SCREEN 10_MESH. FILTER MFH|A 60 in MO 3 ANTH/36inN»  612  gAMP

HATF 9/28/70  PINY RATE	32	.W"/"2


RUN No. 8SFI{I

COMBINED  SEWER OVERFLOW FiLTRATJON  TEST

                                         FIGURE CIS
                       190

-------
o>
 CO
o>
E^
q
O
CD
                     468

                      TIME  (HOURS)
10
12
SCREEN40.MESH  FILTER MEDIA-48-in. Nal_ ANTH./-16-m. No.^l2_SAND

DATE 10/6/70  FLUX RATF   24     gpm/ft2

RUN No. 3SFI

COMBINED SEWER  OVERFLOW FILTRATION  TEST
                                       FIGURE CI9
                       191

-------
 i
 o
 5
 LJ
 cc
 LJ
 H
 u.
 o
 _J

 Q
 <
 LJ
 X
       20
10
                              DEPTH (IN.)
          0
                468

                 TIME  (HOURS)
10
12
SCREEN40.MESH. FILTER  MEDIA.-48_in.No._3_ANTH./_36.in.No._6i2_SAND

HATF 10/6/70  FIIIV RATE  34	iP"171^

RUN No.9S£I	

COMBINED  SEWER OVERFLOW  FILTRATION  TEST

                                          FIGURE C20
                        192

-------

r
FLUENT










low
| 100
ci
d
cri 50
o
vm
r1
Z-EF
FLUENT

FLUENT












*j\j\j
^ 200
E^
Q
0 100
O
n
^— INF
1.
~=
LUENT

EFFLUE


NT









        02468
                     TIME  (HOURS)

SCREEN4QMESH. FILTER MEDIAA8_ in. No.^_
    10/6
            FLUX RATE.
                       40
                                      10
                                      in.
12
                                          612
 SAND
RUN No.9SFII_
COMBINED  SEWER  OVERFLOW FILTRATION TEST
                                     FIGURE CZI
                      193

-------
1 \J\J
90
80
x-»
* 70
V)
< 60
i so
UJ
40
o:
* 30
_i
u- 20
10
n





v-C.O.C
\ y
V
/
^*






.

r-B.O.D.










































 H
 u.

 (S)
 (f)
 o
 _l

 Q
 <
 UJ
      20
10
          DEPTH (IN.)

           81
                      468

                       TIME (HOURS)
                                  10
12
                                      612
                                          _gANP
SCREEN JO MESH. FILTER MFDIA 48^n.No 3 ANTH/36 in

HATF 10/6/70  pi iix RATE _ 15 _ ^pm/ft2

RUN No.-E?FlI_

COMBINED SEWER OVERFLOW  FILTRATION TEST

                                         FIGURE C22
                        194

-------
CO

CO*
d
d
CQ
150


100



50
 NFLUENT
	C.
                   -7
                                  LUENT
    -300
 O
 6
        0     2



SCREEN4QMESH. FILTER MEDiAi>P_in.
                    468

                     TIME  (HOURS)
                                   10
                                  12
             10
                            ANTH./.^. in. NO.

                              2
                                              SAND
                          9pm/ft
HATF 10/6/70 FLUX

RUN No.SSFW

COMBINED SEWER OVERFLOW FILTRATION TEST
                                      FIGURE  C23
                       195

-------
      100
 CO

 i
 o
 5
 Ltl
 a:
 a:
 UJ
 f-
 co
 05
 O
 _l

 Q
 <
 LJ
      20
10
                      468

                       TIME  (HOURS)
                                  10
12
SCREEN!£MESH. FILTER MEDiA.^°_in.No._L_ANTH./.l§.in.No._§iL_sAND

HATF 10/6/70  Fl IIV RATE	!Q	Spm/ft2

RUN No. 9SFill

COMBINED SEWER OVERFLOW  FILTRATION TEST

                                         FIGURE  C24
                        196

-------
    300
d
d
CD
Q
Q
o
IQVJ
100
50
0
300
200
100
0
C

>
^-EF
Y~IN
- ••
FLUENT
FLUENT
*•• ••












-7-
^—E

	
FFLUEN'
-INFLUE
*-•*•
T
NT








) 2 4 6 8 10 12
                     TIME (HOURS)
                                ANTH./M. in. No. 6I2_SAND
                              gpm/ff
SCREEN^OMESH. FILTER MEDIA^O_ jn.

DATE IO/6/7Q  FLUX RATE   40

RUN No. 9ASEUI

COMBINED SEWER OVERFLOW  FILTRATION  TEST
                                      FIGURE C25
                      197

-------
 V)
 
-------
CO
CO*
300

200

100
                       ENT
                   EFFLUENT
IOU
\
? inn
£ IUU
d
d
• crv
CD OU
n

3

HNFLU
FFLUEN

ENT
T










ouu
c? 200
0*
d 100
o
n
?__
3

y — INF
^^^^ ^^
FLUEN1

LUENT











        0
                468
                 TIME  (HOURS)
10
12
SCREEN4QMESH. FILTER MEDIAlg- in. No.-3- ANTH./^S. in. No. 6I2 SAND
DATE 10/12/70  FLUX RATE	^2	gpm/ft2
RUN No. IQSFI
COMBINED  SEWER  OVERFLOW  FILTRATION TEST
                                        FIGURE C27
                        199

-------
 CO
 §
 o
 5
 lij
 o:
      100
      90
      80
      70
      20
       10
       0
                    B.O.D.
            C.O.D.
 H
 u.
 CO
 CO
 o
 _J
 Q
 <
 LJ
                       DEPTH (IN.)
10
         0
                468
                TIME  (HOURS)
10
\2
SCREEN 10.MESH. FILTER MFDIA 48  ?n.Mo 3  ANTH/36 ip N» 612  gANp
HATF I0/l2/70niiy RATE     32    .gpm/ff2
RUN M» IQSFI
COMBINED  SEWER OVERFLOW FILTRATION TEST
                                          FIGURE  C28
                        200

-------
    300
Q
d
CD
0
o
    300
    200
0
                     i      r
                    INFLUENT
                     468
                      TIME  (HOURS)
                                       10
12
                        16
                  in. NaA_ ANTH./1§. in. No. 6l2 SAND

                       qpm/ft2
     J^MESH. FILTER

DATE 10/12/70 FLUX RATE

RUN No. 'OSFII

COMBINED SEWER OVERFLOW FILTRATION TEST
                                       FIGURE C29
                      201

-------
 CO

 §
 o
 s
 111
 cr
 o:
 UJ
 i-
 CO
 CO
 o
 UJ

 X
      20
10
         0
                468


                TIME  (HOURS)
10
12
SCREEN 40.MESH. FILTER MEDIA.48  in.No.-A-_ANTH./J6_in.No. 6' 2  SAND



DATE IP/ '2/70  FLUX RATE _ 16


    Mn IOSF1I
COMBINED  SEWER OVERFLOW FILTRATION TEST

                                         FIGURE C30
                       202

-------
o>
e^

O)
C/J
O>
E^
q
q
ori
 q
 o
 d
        0
10
12
               2468
                      TIME  (HOURS)

SCREEN 4QMESH. FILTER ME PI A^P- in. NoJL ANTH./J*! in. No. 612 SAND

HATP 10/12/70  FLUX RATF   24     gpm/ft2

RUN No. tOSFJII

COMBINED  SEWER  OVERFLOW  FILTRATION TEST
                                        FIGURE C3I
                         203

-------
 o^
 C/3
 _J
 >
 O
 5
 LJ
 a:
 or
 LJ
 Q
 <
 LJ
 X
      20
       10
         0
468
 TIME  (HOURS)
10
12
SCREENiP_MESH. FILTER MEDIA.JQ-ln.Na-1-ANTH.XJ^-ln.No. 62° ..SAND
DATE '0/12/70  FLUX RATE	24	flpm/ft2
RUN NoJOSFllI
COMBINED  SEWER OVERFLOW FILTRATION TEST
                                         FIGURE  C32
                        204

-------
CO

CO
1

ci
O
CD
iJW
$ 200
Q 100
o
n

	

x— -IN
,_>

FLUENT
- — — —


	


^^^^
FLUEN1



                     468

                      TIME  (HOURS)
SCREEN40MESH. FILTER MEDIA

DATE'0/13 770  FLUX RATE	

RUN NolOAlfJll
in. No._
                                        10
                                        in.
                   12
                                               SAND
                          24    gpm/ft^  pOLY NALCO 671

                                              0.5mg/l
COMBINED SEWER  OVERFLOW FILTRATION TEST
                                       FIGURE  C33
                      205

-------
 o
 2
 LJ
 o:

 tr
 LJ
 h-
90


80


70


60


50


40


30


20


10


 0
                         S.Sr
 H
 u.
 CO
 o
 Ul
 X
       20
 10
                                           DEPTH C IN.)
          0
                468

                 TIME (HOURS)
10
12
SCREEN40_MESH. FILTER MEDIA. JO_in.No._3_ANTH./36_in.No._6l2__SAND

DATF 10/13/70 FL||Y RATF    24     gpm/ffZ pmY  NALCO  671

RUN NO.IOASF1I1                                  ^^


COMBINED  SEWER  OVERFLOW FJLTRATiON TEST


                                           FIGURE C34
                          206

-------
 CO
vJV^VV

200

100

n



X**
X
r-^
^p
'


r— 1
\
. \*^
>
	 **x<



|
NFLUENT

*"* ^^
*s^
^"s
>x^





^ — EFFLUEN'
1


















o>

d
o
ad
100



50


 0
          INFLUENT
                      EFFLUENT
tuu
JFLUEN'
,sf
-<
\_
.
^
EFFLUE


:NT






        o.
468

 TIME  (HOURS)
                                   10
12
SCREENJ^OMESH. FILTER MEDiAl8_in.NaJL.ANTH./-Hin.No.lLi_

HATF 10/21/70 FLUX RATfr    32    gpm/ft2 po|_Y NALCO 671

RUN N. MCCT                                   ^^
COMBINED  SEWER  OVERFLOW  FILTRATION TEST
                                       FIGURE  C35
                        207

-------
1 ww
90
^ 80
^ 70
< 60
| 50
UJ
40
o:
£ 30
H 20
10
n




\
A
/\
/ \
— — -






r-S.S.
'^^ /
\ /N
""v>
L-






X
/
»•-**
C.O.D.






























 u.
 V)
 o
 UJ
 I
      20
10
                      468

                       TIME  (HOURS)
                                  10
12
SCREEN 1P_MESH. FILTER MFDIA 48 in.M0 3  ANTHy36 ln Nft 612  gANn

HATF 10/21/70  FLUX RATE    32    .gpm/ft^   POLY  NALCO  671

      IIOCT                                     0.5mg/1
RUN No.iiSFl	                                   	2_

COMBINED  SEWER  OVERFLOW  FILTRATION TEST

                                         FIGURE C36
                       208

-------
o>
CO
300


200


100


  0
          EFFLUENT^
                                INFLUENT
     150


     100


     50


      0

              EFFLUENT-A
     400
     100
        0
                468
                 TIME  (HOURS)
         10
    12
SCREEN^OMESH. FILTER MEDIA!**- in. No._3_ ANTH./J! in. NO. 6I2 SAND
DATE 10/21/70 FLUX RATE.

RUN N
                     16
gpm/ft'
                                  POLY.
NALCO 671
   2.0mg/l
COMBINED  SEWER  OVERFLOW  FILTRATION TEST
                                        FIGURE C37
                       209

-------
 CO
 _l
 <

 O
 S
 LJ
 IT


 CC
 LU
 J-
 co
 CO
 O
 _J

 Q
 <
 UJ
       20
10
          0
                468

                 TIME  (HOURS)
10
12
SCREEN40.MESH. FILTER  MEDIA.4JB_in.No._2_ANTH./-^S.in.No._£12_SAND

DATE_IO/21/LZQ_ FLUX RATE    '6	Wm/ft2   POLY NALCO 671

       I1CFTT                                  '    2-0mg/l
RUN No.MSFII                                      	

COMBINED  SEWER  OVERFLOW FILTRATION  TEST

                                           FIGURE  C 38
                         210

-------
CO

05
o>
E^
d
O
DQ
     400
     100
        0
468

 TIME  (HOURS)
10
12
SCREENlQMESH. FILTER MEDIA*?-0- in. No.JL_ ANTH./Jg. in. No.612 SAND

DATF 10/21/70 FLUX  RATE._24	gpm/ft2  POLY NALCO 671
       IIOCTIT                                   2.0mg/l
RUN Mn liSFIIT                                   	2~

COMBINED  SEWER OVERFLOW  FILTRATION TEST
                                         FIGURE C39
                       211

-------
 CO


 i
 o
 5
 UJ
 a:

 cc
 UJ
 CO
 o
 Ul

 X
      20
       10
                       468

                        TIME  (HOURS)
                                           DEPTH (IN.)
                                          10
                12
SCREEN 4Q_MESH. FILTER MEDIA.-6CLin.No.-S-ANTH.A3§.in.No.
                                                   SAND
DATE 10/21/70 pmx RATE


RUN MnliSFIU
                         24
.gpm/ft2
                                        POLY.
NALCO 671
                                                2.0mq/l



COMBINED  SEWER  OVERFLOW FILTRATION TEST


                                          FIGURE C 40
                         212

-------
 en
 en
o>
E^
d
o
CD
0»
 C>
 d
     300
     200
     100
         0
                     468

                      TIME  (HOURS)
         10
12
SCREEN4Q.MESH. FILTER MEDIANS-in. No._3_ANTH./_36 in. No._612_SAND
                                    o

DATE H/2/70  FLUX RATE-
                         24
RUN No.J3SfB
gpm/ftc  POLY NALCO 671
               l.5mg/l
COMBINED  SEWER OVERFLOW FILTRATION TEST
                                        FIGURE C4I
                        213

-------
 i
 o
 s
 UJ
 QC

 tr
 ui
 U_


 to
 to
 o
 UJ

 X
      20
10
                      468


                       TIME  (HOURS)
                                   10
SCREEN,10MESH. FILTER MEDIA.i8_in.No.J_ANTH./-3S-in.No._&12_SAND


HATF li/2/70  FLUX RATE	^4	SE"1/'*2   POLY. NALCO 671


RUN Mn I3SFI1
                                         l.5mg/I
COMBINED  SEWER OVERFLOW  FILTRATION TEST


                                          FIGURE C 42
                         214

-------
 o>
 E^

 CO

 CO
 0>


 d
 o
 DQ
 o>
 •*~f
 d
 o
 d
                       468

                        TIME  (HOURS)
10
12
 SCREEN4Q.MESH. FILTER  MEDIA4B_ in. Na_i_ ANTH./_^6 in. No._SiZ.SAND

 HATF 11/2/70  FLUX RATE._i6__9pm/ft2  POLY. NALCO 671
      i-^QFin                                    l.5mg/l
RUN N" '3ShJU

COMBiNED  SEWER  OVERFLOW  FILTRATION  TEST
                                          FIGURE C43
                         215

-------
 CO


 i
 o
 s
 UJ
 (T

 tr
 UJ
 h-
 CO
 CO
 o
 UJ

 X
       20
       10
                      468

                       TIME  (HOURS)
                                           DEPTH (IN.)


                                             93
                                          10
12
SCREEN ICLMESH. FILTER MEDIA.d8_in.No._3_ANTH./_^6in.No._6i2


DATE H/2/70 FLUX RATE _ LS


RUN No.
                                                  SAND
                                        PQLY. NAL°Q 67'
                                                l5mg/\
COMBINED  SEWER OVERFLOW  FILTRATION  TEST


                                          FIGURE C 44
                         216

-------
 C/5
300

200

100
                   V
                 NFLUEN
 Q
 d
 m
 Q
 6
 0
     300 p^
     20°
100
       0
                     468
                      TIME  (HOURS)
SCREEN40MESH. FILTER MEDIANS-in.
DATE 11/2/70   FLUX RATE	10	
RUN N0.13SFTV
                                   10
                                          12
                                   in. No. 612 SAND
                          _gpm/ft2  pOLY NALCO 671
                                         l.5mg/l
COMBINED  SEWER  OVERFLOW  FILTRATION TEST
                                       FIGURE C45
                        217

-------
 £;

 CO

 >
 O
 s
 LU
 (T

 a:
 u


 il
 h-
 U_
 ^-*

 CO
 CO
 O
 _J

 Q
 <
 LJ
 I
       20
10
          0
                468
                 TIME  (HOURS)
                                     DEPTH (IN.)
10
12
SCREEN4jO_MESH. FILTER MFD|A 48

DATElL/2V_ZP__ FLUX RATE    I0

RUN No. 13SFIV
                        o. 3  ANTH./!6-in.No. 612

                          gpm/ft^   pOLY  NALCO  671
                                          l.5mg/l
COMBINED  SEWER  OVERFLOW  FILTRATION  TEST

                                           FIGURE C46
                          218

-------
co
CO
     300
     200
     100
       0
                              INFLUENT

                              EFFLUENT
o»
E,
Q
O
m
 q
 o
 d
     300
     200
     100
       0
                              INFLUENT
                             EFFLUENT
         0
                      468

                       TIME  (HOURS)
         10
12
SCREENED MESH. FILTER MEDIATE- in.

DATE H/14/70 FLUX RATE	|6_

RUN No J4SFI
                                   ANTH./-3.6 in. No._6J2_SAND

                                     2  POLY.-NALCO 671
gpm/ft
                                                0.5mg/l
COMBINED  SEWER  OVERFLOW FILTRATION TEST
                                         FIGURE C47
                         219

-------
 c
 to


 >
 O
 5
 UJ
 
-------
CO
     300
     200
     100
                INFLUE!^
                                     -EFFLUENT
o>
£^

q
Q
CD
     150


     100



     50


      0
                                   V
                                     EFFLU
          NT
          ENT
 O
 6
     300
     200
     100
        0
                      468

                      TIME  (HOURS)
         10
   12
SCREEN^O MESH. FILTER MEDIA.UL in. No. J_ ANTH./-!§. in. No.612 SAND
                                    ,2
DATE H/15/70  FLUX RATE

RUN No. '4ASFI
                          32
gpm/ft'
                                        POLY.
NALCO 671
                                               0.5mg/l


COMBINED  SEWER OVERFLOW  FILTRATION TEST
                                        FIGURE C49
                        221

-------
 i
 o
 5
 LJ
 (T

 o:
 u
 i-
 co
 (/)

 O
 UJ

 X
       20
10
          0
                                    DEPTH (IN)
               4      6 ,    8


                TIME  (HOURS)
10
12
SCREENi°_MESH. FILTER MFD|A 42  in.Mo 3  AMTH./36 '» N»


HATF  11/15/70 pi MY RATE     32



RUN N
                                POLY NALCO  671

                                         0.5mg/l
COMBINED  SEWER OVERFLOW FILTRATION  TEST


                                         FIGURE C50
                         222

-------
q
0
o
        234
         TIME  (HOURS)
FILTER MEDIA-6-0- in. NoJL
                                            ,6
                    POLY..
in. No. 6I2
 0  	mg/l
    	mg/l
                                         0
DATE 5/5/71  FLUX RATEJP	gpm/ftz
f  r, No.'7bFlI
COMBINED SEWER OVERFLOW FILTRATION TEST
                                       FIGURE C5I
                        223

-------
\\J \J
Q n
3 \j
ftn
O V
g 70
1 \J
(/}
< fin
\j\j
i 50
UJ
K 40
cc
£ 30
LJ
C 20
10
0
30
u_
^ 20
(0
CO
3
§ 10
UJ
X
0
(
SCREEN 4P_M
PATF 5/5/'




















•




d
/
»
1
•
/
*
i — "


rTSS
-j-


^


^1



^^


,-COD
/. —

^— BOD




' 	 .


^m —





DEPTH.dN.)


•• •
^^MM^i^M
^^m-^m^f^m


^^
D 1 \
ESH. FILTER MEDI
71 Fl HY RATF
RUM N« I7SFII


^SS5


: "


=====


:f^
2 3 4 5 (
TIME (HOURS)
A 60 jp.No 3 AMTM/36 in.Nln. 612 5
10 „

>m/ft2 CC
^Att 0 r
MY 0 r

96
72
54
•N
>AND
ng /I
ng /I.
COMBINED SEWER OVERFLOW FILTRATION TEST
                  FIGURE C52
224

-------
q
Q
CD
o>
E_^
q
q
d
o»
E
<

O
     300
     200
     100
                      23456

                       TIME  (HOURS)

 SCREEN^OMESH. FILTER MEDIA-6-0- in. No.JLANTHV-^J in. NO. 612 SAND

                                         	P_mg/l
                                         	Q_mg/|
POLY..
DATE 5/5/71   FLUX RATE-J6	gpm/ft2

RUN Mn I7SFIII

COMBINED SEWER  OVERFLOW  FILTRATION TEST

                                        FIGURE  C53
                         225

-------
l\J \S
ar\
9 \J
Of)
O\J
?
— • 70
i \j
t/>
< cr\
O \J
i 50
UJ
K 40
(T
£ 30
Li
u. 20
10
0
30
P
'u.
- 20

w
3
§ 10
UJ
X
0
i
Sr.RFFN40M
HATF 5/5/"






















w
\
N
•••^.,

^S"
s'





-
^* • ^
"'t
L
\ /
\


TSS -
m/ft2 PC
>W FIL


— — —
— — —
4
)
ITH./^6- in
1AG


— — -^
^ 	 •
5 (
No 612 <
0 ,
11 Y 0 ,
TRATION TE
(IN.)
96
69
•^
5AND
Tig/I
Tig/I
ST
                  FIGURE C54
226

-------
CO
d
d
oi
d
0
d
E^

£L
                     2      3      4     5     .6

                       TIME (HOURS)


 SCREENIOMESH. FILTER MEDIA^P- in. NaJL ANTH./JSS m. NO. 6>2 SAND

 HATF 5/5/7J  FLUX RATE 24 .  gpm/ft2 COAG	Q—mg/l
                                  POLY..
_Q	mg/l
 RUN NO.JZSEIV.

 COMBINED  SEWER  OVERFLOW  F8LTRATION TEST

                                         FIGURE C55
                         227

-------
     100
CO



I

Ul
a:
3
UJ
X
      80


      70
      40
      30
      20
       10
                                            DEPTH.QN.)
TIME
                             34

                             (HOURS)
SCREEN4P.MESH. FILTER MEDIA.-60_jn>No_3_ANTH./_36 in.No.^l2. SAND


DATE  9/5/71  FLUX RATE-24	gpm/ft2 COAG	£—m9'!
      ,7QFn/               y      POLY	Q—mg/l
RUN Mn I7SF1V


COMBINED  SEWER OVERFLOW FILTRATION TEST


                                         FIGURE C56
                       228

-------

CO
^
q
Q
CQ
£_
q
q
d
e
     600
     300
     100


      0
     600


     4.00
      0
     1.00
     .40
                        EFR
                                    INF.
                        EFF.
                         EFR
                                    INF.
        0      I       23456

                       TIME  (HOURS)


 SCREENiP.MESH. FILTER MEDIA-gP- in. NaJL. ANTH./-36 jn, NQ. 612 SAND
      6/7/71  FLUX RATE_8__gpm/ft* COAG..
                                               0
                                                 .mg/l
RUN No.]8SFII_                      POLY.ATLA.4A4lrOmg/|

COMBINED  SEWER OVERFLOW  FILTRATION TEST

                                         FIGURE C57
                         229

-------
£

i
UJ
01

 CO
 (0

 3

 §
 UJ
 X
      20
10
         0
                234

                 TIME (HOURS)
                                            DEPTH. (IN.)
SCREENiP_MESH. FILTER MEDIA.^P_fn.No.^_ANTHy_36 in.No. 612 SAND
DATE—l/Z/ZL FLUX RATE

RUN M» 18SF1I
                 8
                    -gpm/ft
2 COAG..
.mg/l
                           POIY ATLA.4A4 I.Omg/1
COMBINED  SEWER OVERFLOW  FILTRATION TEST

                                          FIGURE C58
                       230

-------
600
5 400
w! 200
CO
0
_ 300
I 200
d
DQ 0
0
600
^ 400
d
q 200
o
0
1.00
1 -80
E .60
^ .40
£ .20
P 0
(
SCREENS
OATF 6/1




. 	 -"^

*x^
^

r
•-•C

-INF.
•«i^«=!=;







^._. _
^-^






X
/


^EFF

	 -
	 ,




^^**v
EFR —

/-INF
7~

MNF,
— •



•*^,,^
"^














•)
>MESH. Fl
V7I FI
«.,.. .,_ !ftSF!H





LTER ME
UX RATE





















23456
TIME (HOURS)
"DIA^O in No 3 ANITH/36 in. No. 612
:24

gpm/ft2 <
1
:,OAG o
pni Y ATLA.4A4 .0
                                       mg/|
COMBINED SEWER OVERFLOW FILTRATION TEST
                                 FIGURE C 59
                    231

-------
co


I

UJ
IT

cr
UJ
                                             DEPTH.ON.)
u.
 CO
 CO

 3
 UJ

 X
          01234


                        TIME  (HOURS)



SCREENiP_MESH. FILTER  MEDIA.-6p_in.No._3_ANTH./-36 in.No._6]2 SAND


     6/7/71  c. ny RATF  24   	/*»2 COAG..    °
                            qpm/ft	
                            gpm/n  pnt Y ATLA.4A4 l.Omg/1

RUN No. I8SFIU ,


COMBINED  SEWER  OVERFLOW FILTRATION TEST


                                           FIGURE Ceo
                        232

-------
600
5 400
w! 200
CO
0
_ 300
1* 200
d
§ 100
0
600
£ 400
o 200

-------
 CO

 I
 111
 OL
 (T
 UJ
 to
 co
 3
 UJ
 X
       20
       10
        0
          0
                                            DEPTH.QN.)
234
 TIME  (HOURS)
SCREENi?_MESH. FILTER MEDIA. 60 in.No.A_ANTH./-36.in.No.^i2_ SAND
DATE  6/7/71 ,FLUX RATE_J6	gpm/ft2 {%ffiATLA4A4 , 0^|
RUN No.tQSFiV                              '    ^m°
COMBINED  SEWER OVERFLOW FILTRATION TEST
                                          FIGURE C62
                       234

-------
V)
9
E,
d
Q
GQ
 0
 o
E
600

400

200

  0
150
100

 50

  0
300

200

 100

  0
|.00
 .80
 .60
     .20
      0
        0
                   \
                        INF.
                       INF.
                       EFF
                       INF.
                              EFF.
                I      23456
                        TIME  (HOURS)
 SCREEN^OMESH. FILTER  MEDIA-6-0- in. NaJL. ANTHV-JS in. NO. 6|2 SAND
 DATF 6/20/71  FLUX RATE  8    gpm/ft2 COAG. ALUM.  30.0 mg/i
        .^em                       PQLY. MAG.560CI.O mg/|
 RUN No.J9SFIH
 COMBINED  SEWER OVERFLOW  FILTRATION  TEST
                                          FIGURE C63
                         235

-------
 V)



 I

 Ul
 tr

 GC
 UJ
 u.
 CO

 3
 UJ

 X
       20
       10
                                            DEPTH. (IN.)
          0      I      23456


                       TIME  (HOURS)



SCREEN 40.MESH. FILTER MEDIA.^P_in.No.A_ANTH./-3iin.No.^i2 SAND
RUN No.


COMBINED  SEWER  OVERFLOW  FILTRATION TEST


                                         FIGURE C64
                       236

-------
o>
E^

d
Q
OD
 O
 c>
E^

CL
O

                      23456

                        TIME (HOURS)

 SCREEN4QMESH. FILTER MEDIA-^P- in. No..3— ANTH./-36. jn. No. 512 SAND

 HATF 6/20/71  FLUX RATE_l6_gpm/ft2 COAG .ALUM.  30 .mg/i
        l
-------
     100
£
V)


I

UJ

-------
300
E^
w! 100
CO
0
_. 150
| 100
Q
O
CD 50
0
300
c? 200
d
Q 100
o
0
|00
^ .80
E* .60
^ .40
_j
f. .20
e o



r-INF.

^\
^
->
	 1


-EFR











r
" — •—'-•.
T





^ INF.-



-INF.
	 	 _ m __
-EFF.





~\^-~-
^^^.
*^n







INF.
	

• !•

— \
	 V—
_^<
*^\-


-EFF.



















EFF.










       0      I       23456
                      TIME  (HOURS)
SCREEN^P-MESH. FILTER MEDIA-§°- in. NoJL- ANTH./.36 jn. No. 612 SAND
DATE 6/21/71   FLUX RATE  24  gpm/ft2 COAG. ALUM.    30 mq/|
      ,QACcTT                     pftiv MAG.560CI.Om0/l
RUN No. I9ASFII
COMBINED  SEWER  OVERFLOW  FILTRATION  TEST
                                        FIGURE C67
                        239

-------
I
UJ
tr
UJ
b
u_
 3
 UJ
 I
100
90
80
70
60
50
40
30
20
 10
  0
 30
       20
       10
                                             DEPTH.(IN.)
          0      I      2      3      4      56
                        TIME  (HOURS)
SCREEN40.MESH. FILTER  MEDIA. JO_in.No.A_ANTH./36_in.No.^l2 SAND
HATF  6/21/71  pi iiv RATE_24__aDm/ft2 COAG.AUJM	3Q_mg/|
UAIt	I-LUA KAIt	gpm/TT  pnt y MAG.560C I.Omn/l
RUN N0.19ASFII
COMBINED  SEWER  OVERFLOW FILTRATION TEST
                                           FIGURE C68
                        240

-------
300
«? 200
^ 100
CO
0
_ 150
£ 100
d
ci
cci 50
0
300

-------
I
UJ
cc
or
LU
H
to
CO
3
o
<
UJ
X
     100
      90
      80
      70
      60
      50
      40
      30
      20
       10
       20
       10
                        96
                        72
                        54
                                             DEPTH. (IN.)
          0123456
                        TIME  (HOURS)
SCREEN4P.MESH. FILTER MEDIA.^P_in.No.J_ANTH./_liin.No.l!2. SAND
D/VTF  6/21/71  Ft ux RATE  32  Qpm/ft2 COAG.ALUM	3p_mg/i
DATE	FLUX KATE	gpm/ft  pn| Y MAG.560C 1.0 mq/l
RUN Mn I9ASF1V
COMBINED  SEWER  OVERFLOW FILTRATION TEST
                                           FIGURE C70
                        242

-------
600
5 ^OO
^ 200
CO
0
_ 150
f 100
d
d
oi 50
0
300
«? 200
6^
d 100
o
0
|.00
^ .80
E .60
^ .40
_i
£ .20
2 0
SCREENS
DATF 6/




—-£
—— —

— 1 WF
, 	 -

— » —
"•*•- —
>
c^
v«
v
s
\






™— «^___





,^
^^••s

INF.— v
•••— •— JL
»— — •—


• "^ssaJ^

>^r
^•^
*• 1 !•
:INF.
_,— — '
*— "*^
EFF.—^


^EFF.


"^
7— 	 1
f





e±r_
•KKMKBKaKIB







0
3 MESH. Fl
22/71 pi
RUN Mn I9BSFII
COMBINED SE

r
	 £-
*" -
LTER Ml
_UX RATI
EWER i

-INF.
— _-.

^
x^


	 	 	

\
V


m-*^*
&^^

-EFF.


*^-" —
^^x


2 3 4 5 .6
TIME (HOURS)
rDIA ^° in Mn ^ AWTW /36 in Mn 612 RANH
EI6

gpm/ft2
r.OAfi ALUM 30 mg/l
POI Y 0 mn/l
OVERFLOW FILTRATION TEST
FIGURE C7I
243

-------
1
UJ
(T
tr
UJ
3
111
X
                                            DEPTH. (IN.)
                      234
                       TIME  (HOURS)
SCREEN4P.MESH. FILTER MEDIA. J^_in.No._3_ANTH./-36 in.No. 612. SAND
DATE  6/22/71  FLUX RATE—I6-	
RUN Mft I9BSF1I
COMBINED  SEWER OVERFLOW  FILTRATION TEST
                                         FIGURE C 72
                       244

-------
600
«? 400
OT! 200
03
0
_ 150
|T 100
d
c>
OQ 50
0
300
«? 200
Q 100
o
0
1.00
£ -80
E .60
j '40
2 .20
g 0
<
SCREEN4C
pATF 6/2





— — """
^^






wt* *^ ^ ••• •
HPHHiMIHMHH
EFfi





,-'"
m "



—••——«

INF. -A

~ 	 -«.

*-^-*
^-^
EFR

*"**«*,
T-



•^7"

INF. — ^
1^^ ^^



L-e
INF—.
^^^
-EFR

»
	 ^


^\
"^^_
^^«*.


— "^^


^
~~^






D
5 MESH. Fl
2/71 n
RUN No 19BSFIV


_— . 	



LTER ME
.UX RATE

INF.— i
	 1






^
^^^f.

2 3 '
TIME (HOURS
'DIA 60 m Mft 3 j
:I6 <

gpm/ft2 '


	
\ 	
^— EFF
*
>)
IVNTH./-3-^
-^OAR AL


	 —
— — — «


5 .6
in, No 612 .SAND
UM. 30 mn/l
poi Y MAG. 560 C .Omg/I

COMBINED SEWER OVERFLOW FILTRATION TEST
                FIGURE C73
245

-------
g
tO
I
UJ
cr
tr
UJ
                                            DEPTH.QN.)
to
§
§
UJ
X
         0123456
                       TIME  (HOURS)

SCREEN 1P.MESH. FILTER MEDIA.j60_in.No._3_ANTH./-3i.in.No.^l2. SAND
RUN NQ.19BSF1V
COMBINED  SEWER OVERFLOW FILTRATION TEST
                                         FIGURE C74
                       246

-------
eo
o>
E^
q
Q
CD
Q
Q
d
E_

Q.
O

                      2     3     4      5     .6

                       TIME  (HOURS)

 SCREENiP-MESH. FILTER MEDIA-§P_ in. NoJL ANTH./l6- jn. NO. 612 SAND

 DATE 6/23/71  FLUX RATE  '6  gpm/ft2 COAG. ALUM    30 mg/i
        ,QrQpTI                     POLY. HERC. 836 1.0 mq/.
 RUN No. I9CSFH

 COMBINED  SEWER OVERFLOW FILTRATION TEST

                                          FIGURE C75
                         247

-------
I

UJ
(T

cr
UJ
en

3
UJ

X
                   234


                    TIME (HOURS)
SCREEN 40 MESH. FILTER MEDIA.-6Q_in.No._3_ANTHiA36 in.No.^l2_ SAND



DATE-^SrFLUX «™-*—w«z S£?u^jlS/!
RUN MO I9CSFII


COMBINED SEWER OVERFLOW FILTRATION TEST


                                    FIGURE C76
                    248

-------
300
^

\/-
_\
-INF.
S
/





/-INF.
*fc^ 	





INF.
•• —



* 	


	 ' —


^


^^
EFF. -

EFF.-


^s^

^==


_^^
^J






D
I MESH. Fl
3/71 p.
RUN Mn I9CSF1V
COMBINED SE

INF.-
	 • 	

^t^^"^

LTER ME
UX RATE
WER (


~^ -*»***"
*«*•



2
TIME
IDIA-60_
r 16
)VERFl






EFF-
3
(HOURS
in No 3 i
gpm/ft2 '
.OW Fl





V
^

"-•*••-.




» 5 6
\}
^NTH./^6 jn. No. 612 SAND
SOAG Fe Cl3 15 mg/|
pni Y HERC.836 .0 mrj/i
LTRATION TEST
FIGURE C77
249

-------
I

UJ
(T

CC
UJ
u.
(O
w

3
UJ

X
      20
      10
                                           DEPTH. (IN.)
                                                 96

                                                 72

                                                 54
                I
                      234


                       TIME  (HOURS)
SCREENIO.MESH. FILTER MEDIA. 6° in.NO.


r»ATF 6/23/71  niix RATE—I^


RUN Nc
                                               SAND


                                             '5 mg/l
                                 pniY HERC.836f.Om9/l
COMBINED  SEWER  OVERFLOW FiLTRATION  TEST


                                         FIGURE C78
                      250

-------
CO
ci
d
CD
o
0
o
     300
     200
     .60

     .40

     .20

      0

                         INF.
                                   r-
   EFF.
                                               ,6
       0      I       2345

                      TIME  (HOURS)


SCREEN4P.MESH. FILTER MEDIA_§P_ in. Na_3_ ANTH./36 jn. No..6i2 SAND
 DATE.
             FLUX  RATE _?4	gpm/ft2
     FeCIs    25 mg/i
Pf» v ATLA.4A4 I.Omg/l
 RUN No.EQSFjjL

 COMBINED  SEWER OVERFLOW RLTRATIQN TEST

                                          FIGURE C79
                         251

-------
E
to
I
Ul
IT
(T
UJ
 CO
 3
 Ul
 X
100
90
80
70
60
50
40
30
20
 10
  0
 30
       20
       10
                                             DEPTH. (IN.)
          0123456
                        TIME  (HOURS)
SCREEN40.MESH. FILTER  MEDIA. JO-in.No.^_ANTH./_36 in.No.^Li. SAND
DATE  6/29/71 FLUX
RUN No.20SFtt_
                             COAG.£fi-£l3
                             pniYATLA4A4I.Omg/l
COMBINED  SEWER  OVERFLOW FILTRATION TEST
                                           FIGURE C 80
                       252

-------
CO

CO
d
Q
m
d
q
d
o»
E
<

O
    300



    200



    100


     0
                          INF.
                EFF.
                                                .6
                     2345

                       TIME  (HOURS)


SCREEN^ MESH. FILTER  MEDIA-§°_ in. No.JL_ ANTH./J36 jn. NO. 612 SAND

HATF 6/29/71  FHIV RATE-J6_ gpm/ft2 COAG.±eCi3	?5_mq/l
       ^^^F-,«                      pni V ATLA.4A4 1.0 mn/i
RUN No.^PSFJU

COMBINED SEWER  OVERFLOW  FILTRATION TEST

                                          FIGURE C8I
                          253

-------
g
I
UJ
(T
OC
UJ
h-
eo
3
UJ
X
100
90
80
70
60
50
40
30
20
 10
      30
      20
       10
       0
          0
                                             DEPTH.dN.)
                 234
                  TIME  (HOURS)
SCREEN 40.MESH. FILTER MEDIA. 60 in.No.-3— . ANTH./-^§-in.No.^lg- SAND
DATE  6/29/71  FLUX RATE_16
RUN N0.20SFHL
                                         25.mg/|
                             pniY ATLA.4A4I.OmQ/l
COMBINED  SEWER OVERFLOW  FILTRATION  TEST
                                          FIGURE C82
                       254

-------
CO
CO
d
Q
CD
Q
O
     300

     200

     100

       0
EFR-
                         -INR
                        I—mr.
0*
E^
o.
_j

O

                      23456
                        TIME  (HOURS)

 SCREEN4QMESH. FILTER  MEDIA-6-0- in. NaJL- ANTH./-3§ in. No. 6'2 SAND
 HATF 6/29/71  FLUX RATE_J_ gpm/ft2 COAG. Fe CI3—25_mg/|
       onotrnr                      POLY. ATLA. 4A4 mg/|
 RUN N0.2QSFTV

 COMBINED  SEWER OVERFLOW  FILTRATION TEST
                                          FIGURE C83
                         255

-------
CO
I
Ul
OC.
(T
UJ
H
U.
CO
3
UJ
X
100
90
80
70
60
50
40
30
20
      10
      30
      20
       10
S  X
                          TSS
                      L*  A
                              X
                           NX
                                BOD
                  COD
                     ^
                                           DEPTH.dN.)
         0      I      23456
                       TIME  (HOURS)
SCREEN 40MESH. FILTER MEDIA.^O_in.No.J_ANTH./-36 in.No.^12. SAND
DATE^/29/IL.FLUX RATE-Ji-gpm/ft
RUN N0.2QSRV
COMBINED  SEWER OVERFLOW FILTRATION TEST
                                         FIGURE C84
                       256

-------
o>
e^

CO
CO
o«

d
Cj
CD
 Q
 o
o»
E
 O
                                               .6
                     2345

                      TIME  (HOURS)

SCREEN4.?.MESH. FILTER MEDIA-IP- in. Na-3_ ANTH./-36 jn. No. 612 SAND
 DATE 6/30/71   FLUX  RATE

 RUN N0.20ASFH
                           gpm/ft*
ALUM.   30 mg/l
                                  pni Y ATLA. 4A4I.Omg/i


COMBINED  SEWER OVERFLOW FILTRATION  TEST

                                         FIGURE C85
                         257

-------
     100
CO
I
UJ
ir
£
LJ
u.
CO
3
§
UJ
X
     80
      60
      50
      40
      30
      20
      10
      30
      20
      10
                 r-
                   TSS
*£
    V
COD  ^ \
                                          DEPTH.(IN.)
                     234
                      TIME  (HOURS)
                                         3. 6J2 SAND
                                COAG. AjJJM___3p_mg/1
SCREEN 40MESH. FILTER MEDIA. 60 }n.No.-3.
DATE  6/30/7. FLUX RATE^>_gpm/ft<  pn, Y ATLA 4A4 ,.0
RUN No.IQASFH
COMBINED SEWER OVERFLOW .FILTRATION TEST
                                        FIGURE C86
                      258

-------
300
«? 200
w! 100
(O
0
_ 150
| 100
d
d
DQ 50
0
300
MFSH. Fl
HATF 6/30/71 F|
RMM Mn 20ASFm



""

1
LTER ME
.UX RATE




EFF


INF-j
	 L












2 3 4 5 . .6
TIME (HOURS)
rDIA^O in Mr. 3 ANTH./36 in Wo 612 SANO
- 16

gpm/ft2 <
-OAR ALUM. 30 mg/l
Pfti Y ATLA. 4A4 .0 mrj/i

COMBINED SEWER OVERFLOW FILTRATION TEST
                FIGURE C87
259

-------
CO
I
UJ
(T
cr
UJ
                                            DEPTH.QN.)
CO
CO
3
UJ
X
         01234
                       TIME  (HOURS)
SCREENiP_MESH. FILTER MEDIA.j60_in.No.^_ANTH./-36 in.No. 6i2_ SAND
DATE_-6/30/7LFLUX RATE_16_gpm/ft2 COAfl.^^mj/J
RUN Mn 20ASFTH
COMBINED  SEWER OVERFLOW  FILTRATION TEST
                                          FIGURE C88
                       260

-------
en
o»
d
QQ
Q
o
g
300

200

100

  0
150
100

50

 0
300

200

100

  0
LOO
.80
.60
.40
.20
  0
                             — INF.
                	^Z
                              -EFF.
                          INF.
                                       EFF
                           INF.
                         -
                          EFF.
                                        INF.
           I
                                                .6
                     2345
                       TIME  (HOURS)
SCREEN^OMESH. FILTER MEDIA.1P- in. NoJL_ ANTH./_1§ in. No. 6I2 SAND
PATF 7/11/71   FLUX RATF  8   npm/ft2  COAG.ALUM.	30_mg/l
       Olot1ir                       POIY SWIFT X-400I.Om0/»
RUN No. 21SFIII
COMBINED  SEWER  OVERFLOW FILTRATION TEST
                                          FIGURE C89
                          261

-------
1 W
90
CO
< 60
1 50
UJ
* 40
cc
b
10
30
P
~ 20
CO
CO
3
§ 10
UJ
X
0
(
SCREEN10.M
IWF 7/11/1



,






y r
*v>sC
\ ^>
^^B>B


—•II ' '"





D 23-
TIME (HOURS1
ESH. FILTER MEDIA._§Q_in.No._3_Afs
n Fl NY RATF 8 nnm/f*2 CC
RUN No.glSFm
COMBINED SEWER OVERFLC
.... . .






MHM«M_li
•—^^^••MKM
4 5 i
}
ITH./^i.in.No. 6]2_ j
iLY SWIFT.X-400 l.0r
(IN.)
96
51 a<
^
5AND
Tig/I
no/1
)W FILTRATION TEST
                  FIGURE C90
262

-------
300
5 200
"> 100
C/3
0
_ 150
| 100
d
d
cti 50
0
300
MESH. Fl
/7I Fl
RUN No 2ISF1V




— *****^
1
LTER ME
.UX RATE


r-INF.
\


r-EFF
/
— ^ 	 -fc=*~~*z




?•" ar=






23456
TIME (HOURS)
rDIA ^0 in Mo 3 ANTH/36 in. No. 612 SAND
:I6

gpm/ft2 <
-nAfi ALUM 30 mQ/i
POLY SWIFT X-400 1.0 mV|

COMBINED SEWER OVERFLOW FILTRATION TEST
                 FIGURE C9I
263

-------
to

o
UJ
OL
tr
H

-------
CO
0»
d
CQ
 d
 Q
 o
     300
     200
                              INF.
                        /—INF.
/— INF.
                                      EFF.
                 7
     100
      0
    150
    100

     50

      0
    300

    200

     100

      0
    1.00
^    .80
f    .60
•***
^    A°
££    .20
P     0
        0      I      23456
                       TIME  (HOURS)
 SCREEN4QviESH. FILTER MEDIA-60_ in. Na-3__ ANTHV-M jn. No. 612 SAND

 DATE-^;FLUX RATE-^9pm/"2
 RUN No.?IASpJI
 COMBINED SEWER  OVERFLOW  FILTRATION  TEST
                                          FIGURE C93
                         265

-------
g
1
2
cc
UJ
i-
 V)
 w
 3
 UJ
 I
       20
       10
          0
                                             DEPTH.QN.)
                                                  72896
                                                  54
234
 TIME  (HOURS)
SCREEN 12.MESH. FILTER MEDIA. 6°...in.No.-3_ANTH./-36.in.No.^l2. SAND
DATE^m^L. FLUX RATE_^_9pm/f,^
RUN No.EiASFll
COMBINED  SEWER OVERFLOW  FILTRATION TEST
                                          FIGURE C94
                        266

-------
300
5 ^oo
^ 100
0
_ 150
| 100
d
d
CD 50
0
300
£ 200
0 100
o
0
1.00
JF '80
E .60
5 -40
? .20
? 0
(
SCREEN4C
OATF 7/13





	


r
-_1-


INF.
"^^


/—EFF.
L^

















rINF.
jL—



.—•



^-INF.
J. 	 »«



	 •«-



jC^FF-



EFR-
— — -"— •



— «*







~7
^nz







3
}MESH. Fl
/7I Fl
RUN No 2IASRK


r
	 £.
ii 	 •••lum.i
LTER ME
.UX RATE


-INF.
•"EOBKn on
«— «—
2
TIME
:DIA.60_
:24



EFF.-
, .»,««-«-••
.^— — ™*
3
(HOUR?
in. Na_3_ ^
gpm/ft2 <


— \
••^•ll^ •MB,,
^
S)
^^TH /36
COAG.AL



"^—^

5 6
in. No._£i2_SAND
JM. 30 m«/l
Pfflv SWIFT X-400LOmj/l
COMBINED SEWER OVERFLOW FILTRATION TEST
                FIGURE C95
267

-------
CO
<

i
Ul
u.
u.
0)
3
§
UJ
X
      20
       10
                                             DEPTH. (IN.)
                                                  96
                                                  69
                                                  51
          0123456
                        TIME  (HOURS)
SCREEN.19.MESH. FILTER  MEDIA.  60 in.No.JL.ANTH./-36 in.No.J6J2. SAND
                                       ALUM    30 rnq/l
     ^/i3/7LFLUXRATE_24_yKlll/11  pOLY§^FOt4QQlDmg/l
RUN No. 21 ASF|ll
COMBINED  SEWER  OVERFLOW FILTRATION TEST
                                           FIGURE C96
                        268

-------
600
5 4<>0
E^
OT! 200
(/}
0
_ 150
| 100
d
d
cd 50
0
300
JF 200
E^
d"
d 100
6
0
1.00
£ -80
E .60
^ .40
_i
g .20
P 0
(
SCREENS
PATF 7/1





• •








	
/
_/ —


-<
^^s
^*»

EFF. -
•• —
/-INR
\
\
\ \

/
/^

^
^*
^^.^— — ^«"

	
-EFF.
—

"-^
EFF
— -i— — —
X.
\
'• •

^— -
INR -
'—






D
>MESH. Fl
9/71 FI
RUN N0.22SF1L
COMBINED SE


^^
^^^

LTER ME
_UX RATE
WER C
^~^^"™"™

' 	 ^.

2
TIME
:DIA-6P_
r 8
>VERFl
	

EFF.
'*— 	

3
(HOUR?
in. Na3 _
gpm/ft2
.OW Fl

* INF.—
-

~~T—
_/
F^^

•-— •=
INE —
n
•J 	

4
5)
fl,MTH/36
COAG-AL

>--
	 ^-1

— .— 	
• 	 -^


7 —
7 /
/
/


5 6
in. No. 612 SAND
DM. 30mn/I
pniv SWIFT X-400I.Om^/i
LTRATION TEST
                FIGURE C97
269

-------
1 \J\S
90
80
« 70
to
< 60
i 50
UJ
C 40
cc
ui 30
Li
u. 20
10
0
30
u.
~ 20
CO
CO
3
§ 10
UJ
X
0
<
SCREEN±?_M
HATF 7/19/













•mm^—*
•HBIM
TSS-
— ^— ^
>\
;>'<
**





~\_^
^\
BOD-7
»——*•—
V
T^<*
COD-





\
\
>f
^7\
-j \







...—• '•"1
— — «--- '
*» ^^*
rx
^i






^^x^
•v^
,x
\\
TP-A
•»
1

DEPTH.


— •«i^««


•— ««— ^
D I 2 :
TIME
ESH. FILTER MEDlA._6P_in.
7! PI IIY RATP 8
RUN N0.22SE1L
COMBINED SEWER OVERFLC


•• ii
3
(HOURS1
No.JL_AN
m/f12 «
IW FIU


I! '


— — — •
'—
* 5 (
I
rrH./_5£in.No.J>!2_ <
iAfi ALUM 30 r
H..Y SWIFT X-400I.Or
FRATION TE$
(IN.)
96
a
72
54
•*
>AND
ng/1
ng/l
5T
FIGURE C98
270

-------
600
5 4-00
OT! 200
CO
0
_ 150
| 100
d
c>
cci 50
0
300

-------
CO


I

UJ
IT

cr
H
u_
to
CO

3

o
<
UJ
X
SCREEN 40_MESH.
                                              DEPTH.QN.)
                       23456

                        TIME (HOURS)


                    MEDIA.-60_in.No.J_ANTH./-56.in.No._612 SAND
DATE_7/J9/7I  FLUX RATE  '6    gnm/ft2 COAG.ALUJV! - 30_mg/l

    - oootrm         -       Pni.YSWIFTX-400IXXnq/l
RUN Mn 22SF11I


COMBINED SEWER OVERFLOW FILTRATION TEST


                                            FIGURE C 100
                        272

-------
    600
CO
d
d
ti
d
0
o
    200
                            v

                              vf
                                   INF.
                                     .
                     2     3     4      5    »6

                       TIME  (HOURS)


 SCREEN4QMESH. FILTER MEDIA-60. in. Na.3_ ANTH./-36 jn. No. 612 SAND
 DATE  7/19/71  FLUX RATE  24

 RUN No. £2SFIV
                           gpm/ft'
ALUM.    50 mg/l
                                 POIY SWIFT X-4QOI.Omg/1


COMBINED SEWER  OVERFLOW FILTRATION TEST

                                        FIGURE C101
                         273

-------
I
yj
ir
tr
ui
u.
CO
CO
3
u
X
     100
      90
      80
      70
      60
      50
      40
      30
      20
      10
       0
      30
      20
       10
                                             DEPTH.QN.)
          0123456
                        TIME  (HOURS)
SCREEN dP. MESH. FILTER  MEDIA.j6p_in.No.^_ANTH./-36_in.No. 6]2_ SAND
  TF  7/19/71
                        24__aDm/ft2 COAG.     - 30,mg/|
                            gpm/n  pnl YSwiFTX-4001.Qmg/l
RUN No. 22SFTV
COMBINED  SEWER  OVERFLOW FILTRATION  TEST
                                           FIGURE CI03
                        274

-------
300
^
	
«-«——•



















D
^MESH. Fl
0/71 Fl
RUN N", 22ASFII

INF.— v
^^»^j^J«i

y-INF.
•
_, 	 --
«*•

1
LTER ME
.UX RATE

,NF.-,
	 J.



••™ •"•"•••'
EFF.-


— CS



— - —



r==*-

, — 	 "
EFF.-^



2 3
TIME (HOURS
"OIA 60 i" M« 3
:8

gpm/ft2


•—""•"•"""
_y


EFF-
••«•

^^^
i



*
>)
(\NTH./_36
COAG.4U


«• •—



=^=-

^x
"•v^
"** 	



5 6
in. No. 612 SAND
JM 30 mo/I
POI v ATLA.3A3 .5 mg/l

COMBINED SEWER OVERFLOW FILTRATION TEST
FIGURE CI03
275

-------
I
UJ

CO
3
§
UJ
X
     100
      90
      80
      70
      50
      40
      30
      20
      10
       0
      30
      20
      10
         0
                    TP
                         TSS
                                      BOD
                                      COD
                                           DEPTH. (IN.)
                                                72 a 96
                                                54
                      234
                       TIME (HOURS)
                                               SAND
SCREEN!P_MESH. FILTER MEDIA._6P_in.
DATE_IZ2QZ^_FLUX RATE-^gpm/ft* ™Gy£™^™5 %',\
RUN No.a££SEJ]
COMBINED  SEWER  OVERFLOW  FILTRATION TEST
                                         FIGURE CI04
                       276

-------
300
 100
en
0
_ 150
f 100
d
o
CD 50
0
300
.

iH«*i""— •"


EFF.


— ' "^^s,
EFF-


J


II •"
~J~






D
>MESH. Fl
3/71 n
p,,N Mo22ASFJIl
,-INF.
^L._ ..
*-* — .
^^•**i

LTER ME
.UX RATE


^^
**^

— —
==— =


*^w«
=T
EFF— ^

^^-S
s^**



23456
TIME (HOURS)
•QIA 60 in Mr, 3 AWTH / 36 in kn 612 SANO
r 16

gpm/ft2 (
-OAR ALUM. 30 mg/l
POI Y ATLA.3A3 . S mg/l

COMBINED SEWER OVERFLOW FILTRATION TEST
                FIGURE CI05
27?

-------
in

-------
o>
d
Q
CD
o
6
E_
a
O
    100

    50

     0
    300

    200

    100

      0
    1.00
    .80
    .60
    .40
    .20
     0
INF.

                                  P.
                                               .6
       0       I      2345
                       TIME (HOURS)
SCREEN4.0.MESH. FILTER MEDIA-§0- in. NoJL. ANTH./.36 jn. NQ. 612 SAND
HATF 7/20/71  FLUX RATE 24   gpm/ft2 COAG ALUM    3Q_mg/|
      OOAcriV                     pQLY.ATLA.3A3 .5 mg/|
RUN No.22ASFtY
COMBINED  SEWER OVERFLOW  FILTRATION  TEST
                                         FIGURE CI07
                         279

-------
g
co
P_jn.No^ANTHy_36In. No. Jill SAND

                 RATE -24	gpm/ft2
RUN N0.22ASF1Y

COMBINED  SEWER OVERFLOW FILTRATiON TEST

                                         FIGURE CI08
                       280

-------
300

m 50
0
300
£ 200
0 100
o
0
1.00
J -80
E .60
* .40
_j
^ .20
£ 0
(
SCREENS
HATF 7/2



	

^~
INF.— \
	 1

	 • 	
^^.^
r— EFF
J— -
s^
X
• .

^--
— • — -






	 ^^ ^






—•—•——
Mii^-i^«^—

r'NF.




•"••"••—«
EFF-

r
— *-
.— .— —






}
>MESH. Fl
.1/71 Fl
RUN Mn 22BSFII
COMBINED SE
^^ ^^^^



•••^•^•••i^^
LTER ME
.UX RATE
WER C
"^v/^

EFF-

	 •
2
TIME
:DIA_6_P_
:8
)VERFL
-INF.
— — — •
— T


— •— ^—
^


~—*—
^EFF.

-INF.^x*

"\
^
^^
3
(HOURS
in. NaA_ i
gpm/ft2
.OW Fl











=^^5:

... 	






^5.6
k \
\NTH /36 in Nrt, 612 SAND
mar, ALUM. 30 mg/i
pnivPURIFL.A-23I.Omg/i
LTRATION TEST
                 FIGURE CI09
281

-------
\\J\J
90
RO
Ov
g 70
I \J
<

COD

^^ff ^^
*^^





x\_
•^
• •l^^ fc
— »-«H
7 	






^"T1*
V"
,><
\
\
\
\

DEPTH.(IN.)


••••MM
•••MMiMi


=H
D I J
ESH. FILTER MEDI
71 Fl L1X RATF
RUN No22BSFlI


r* -
!TiT 	 ••-


^r=E
> 3
TIME (HOURS1
A 60 fp NO 3 AK
8 nr

>m/ft2 «


— •-
-"
^ !
I
ITH./-J§ in
mfi ALU^


— -
"•
5 (
NO 612 <
/I 30 r
M YPURIFLA-23I.Or

96
72
54
•H
>AND
ng/l
ng/l
COMBINED SEWER OVERFLOW FILTRATION TEST
                   FIGURE  CIIO
282

-------
o»
£^

c/j

CO
d
d
CD
 d
 q
 6
o>
E
 <

 O
        0
                    334

                      TIME  (HOURS)
SCREEN^OMESH. FILTER
                                          jn. No.-6[2_sAND
 DATE  7/21/71  FLUX RATE-Ji— Qpm/ft2 COAG .ALUM .   |Q mq/l

 RUN N0.22BSQII                    POLY-EfflEUtaiam,/.


 COMBINED  SEWER^QyE^FLQ^L^^
                                         FIGURE Clli
                         283

-------
to

I
cr
LJ
 u.
to
3
 Ul
 X
       20
       10
        0
                                              DEPTH.QN.)
96
69

51
                       234
                        TIME  (HOURS)
SCREEN 40 MESH. FILTER MEDIA. 6°  in.No.J_ANTH./-^§.in.No.^lg. SAND

HATF  7/21/71 niiy RATE  '6    qpm/ft2 COAG.ALUM	3p_mg/l
UM.C.	ri_u* n««t	gpm/n     YPURIFL.A-23I.OmQ/l
RUN No.?2BSQU                                      9

COMBINED SEWER  OVERFLOW FILTRATION  TEST

                                           FIGURE CU2
                        284

-------
300
£ 200
w! 100
(0
0
_ 150
1 100
ci
m' 50
0
300
t? 200
0 100
o
0
1.00
C .80
o»^
E .60
5 '40
£ .20
g 0
(
SCREEN^
PATF 7/



L_/
	 •

-INF.
_^/
/ EFF.

Vr*^""
_7\

X,
"^


SSS!=^







f^*~""~'~'











D
>MESH. Fl
21/71 p.
RUN No,22BSFJV
A
—^

** — -=

-^- —


LTER ME
.(M RATE

^-INF.
^" "^^•^•^•••iW



— -^^——
LEFF.

-INF.
-^^=-
-EFF.


	



••"••"" ^



•• ••



••«»»



^ i*1*"


^^•)
(VNTH./^6-
COAG.AL
«. 	
s_
\
\


5 .6
jn Wft 612 SANH
JM. 30 mq/l
POLY PURIFL.A-23 .Omg/l

COMBINED SEWER OVERFLOW FILTRATION TEST
FIGURE CII3
285

-------
g
to

I
UJ
(T
Ul
h-
CO
3
UJ
X
                       23456
                        TIME  (HOURS)

SCREEN 19.MESH. FILTER  MEDIA.jSQ_in.No.^_ANTH./-36.in.No.^i2. SAND

HATF  7/21/71  miY RATE—24__nDm/n2 COAG.ALAJM	3p_mg/|
UAit	.	t-LUXKAit	gpm/n  POLY.PURiFl=A23LOmg/l

RUN MO 22BSFIV

COMBINED  SEWER OVERFLOW FILTRATION TEST

                                           FIGURE CII4
                       286

-------
V)
d
d
CD
d
0
o
    300


    200



    100


      0

    150


    100



    50


     0

    300


    200



    100



      0
    1.00

    .80

    .60
     .20

      0
        0
                          INF.
                       EFF.
                        INF.
                          EFF
                        INF
                 EFF.
                        INF.
                       EFF.
         12345

                 TIME  (HOURS)


^MESH. FILTER  MEDIA-6P- in. N(X3_ ANTH./-36. in.
                                                30
                                            mg/l
DATE_I/22/7L_ FLUX RATE  8   gpm/ft2 COAG.AU|WL_

      oorccn                      POLY.PyRifkC^LL
RUN N0.22CSFJI

COMBINED  SEWER  OVERFLOW FILTRATION TEST

                                          FIGURE CII5
                         287

-------
to
I
UJ
ATF  7/22/71 FIIIV RATE   8    	,**2 COAG.ALUM	30_mg/l

RUN Mo 22CSRI
                                        .	_
                                    pn|YPURlFL.C-3ll.Omg/i
COMBINED SEWER OVERFLOW  FILTRATION TEST

                                           FIGURE CII6
                        288

-------
CO
o>
q
o
CD
d
o
300

200

100
  0
150
100

50

 0
300

200

100

  0
1.00
.80
.60
     .20
      0
        0
                         INF.
                       EFR
                         INF.
                        EFF.
           I
                                               .6
                     2      3
                       TIME (HOURS)
SCREEN^QMESH. FILTER  MEDIA-6-0- m. NaJL_ ANm/-36 jn. NO. s<2 SAND
DATE 7/22/71  FLUX RATE-16.
RUN Mn 22CSR11
                            gpm/ft2  COAG.ALUM	30_mg/|
                                   Pfti vPURIFL.C-51 I.Omg/i
 COMBINED  SEWER OVERFLOW FILTRATION TEST
                                          FIGURE CII7
                         289

-------
w
_l
I
UJ
cr

3
§
Id
X
100
90
80
70
 so
 40
 30
 20
 10
  0
 30

 20

 10
--T
                   BOD
                      ^
                               TSS
                                   -y
                                   \
                                              DEPTH.(IN.)
          0      I      23456
                        TIME  (HOURS)
SCREEN 4QLMESH. FILTER MEDIA. 60 in.No.^-ANTH./-36.in.No.^lg- SAND
DATE_7/22/7l  FLUX RATF  l6   opm/ft2 COAG.^UJM	3p_mg/|
UAIt	I-LUA KAIt	gpm/ft pn| YpUR|FLC-3II.Omn/l
RUN N0.22CSFI11,
COMBINED  SEWER OVERFLOW  FILTRATION TEST
                                           FIGURE CII8
                        290

-------
     300
w
d
§
Q
o
100
50
 0
300
200
100
  0
1.00
-80
.60
.40
.20
  o
        0
                       INF.
                       INF.
                          -.
               	1^
           I
                     234
                       TIME (HOURS)
SCREENlOMESH. FILTER MEDIA_§P_ in. NoJL_
r>ATF 7/22/71  FLUX RATE 24   gpm/ft2
RUN No.22CSFLV
>     .6

in. No.j6l2_SAND
     30
                                   PQI v PURIFL.O-3H.O mj/i
 COMBINED  SEWER OVERFLOW FILTRATION TEST
                                          FIGURE CH9
                         291

-------
CO
I
UJ
a:
DC
u
CO
CO
3
 UJ
 X
100
90
80
70
60
50
40
30
20
 10
  0
 30

 20

 10
         0
 TSS
X
                       „
                        TP
BOD
                                    COD
                                            DEPTH.(IN.)
                 234
                  TIME  (HOURS)
SCREEN4jp_MESH. FILTER MEDIA._iP_in.No.A_ANTH./^6 in.No. J]2. SAND
DATE_Z/2g/ZLFLUX
RUN N0.22CSFIV
COMBINED  SEWER OVERFLOW FILTRATION TEST
                                          FIGURE C120
                       292

-------
Q
2
0
o
e
    600

    400

    200
      0
    150
    100

    50

     0
    300
    200

    100

      0
    |.00
    .80
    .60
    .40
    .20
                        EFF.
                                      INF.
                   EFF.
                   EFF.
                              INF.
                              INF.
                           W
                        EFF.
                                 INF
                                               .6
       0       I      2345
                       TIME  (HOURS)
SCREEN 4P_ MESH. FILTER MEDIA-6Q- in. Na J_ ANTH./-36 in. No. 6'2 SAND
      7/24/71
                  RATE—§	gpm/ft2 COAG.
                                   pnivATLA. 4A4 l.<
rmg/l
 RUN No.23SFII
 COMBINED  SEWER OVERFLOW FILTRATION TEST
                                          FIGURE CI2I
                         293

-------
CO
I
UJ
OC
tr
UJ
u.
CO
CO
3
Q
UJ
      100
      90
      80
      70
      60
      50
      40
      30
      20
       10
       0
       30

       20

       10
                                TP
                               -BOD
                                      TSS
                                       COD
                                             DEPTH. (IN.)
                                                   96
                                                   72
                                                   54
                                                 6
          01234
                        TIME  (HOURS)
SCREEN 1P_MESH. FILTER  MEDIA._6P_in.No._
DATE 7/24/71  FLUX RATE-JL— gpm/f,  pn| Y ATLA.4A4 LQ mQ/1
RUN N0.23SFII
COMBINED  SEWER  OVERFLOW FILTRATION  TEST
                                           FIGURE CI22
                                   ANTH./-3-^.in.No.-ii2. SAND
                                             0    mg/l
                       294

-------
o»

CO
CO*
o>
d
Q
ffi
 Q
 O
 O
O
600

400

200

  0
150
100

 50

  0
300

200

100

  0
I..OO
.80
.60
 .40
 .20
  0
                                 INF.
                         EFF.
                               INF.
                       EPP

                               INF.
                         EFR
                                 INF
                                           .6
        0       I      2      3      4
                        TIME  (HOURS)
 SCREEN^QMESH. FILTER MEDiA-£P_ in. Na J_ ANTH./-16 jn. NO. 612 SAND
                                                   .mg/l
                                         0
DATE 7/24/71 FLUX RATE_1^	gpm/ft2  COAG             .
                                   POLY ATLA. 4A4 1.0 mq/\
       OTJOtTIlT                       rv/L-i	my/ i
RUN Nn 23SFIU
COMBINED  SEWER  OVERFLOW FILTRATION TEST
                                          FIGURE CI23
                          295

-------
 <
 i
 UJ

 en
 
-------
o>
§
 Q
 o
E_
a.
    600

    400

    200
      0
    150
    100

    50

     0
    300
    200

    100

      0
    1.00
    .80
    .60
    .40
    .20
      0
                  EFF.
                   EFF.
                                       INF.
                               INF.
                         EFF.
                              INF.
                         EFF.
                                  INF.
                                                .6
       0       I      2345
                       TIME  (HOURS)
SCREEN^O MESH. FILTER  MEDIA-!0- jn. Na_3_ ANTH./J36 jn. MQ. 612 SAND
DATE	7/24/71 FLUX RATE  24  gpm/ft2
                                             0
             	mg/l
pni Y ATLA 4A4 1.0 mg/i
 RUN N0.23SF1V
 COMBINED  SEWER  OVERFLOW FILTRATION TEST
                                           FIGURE C125
                         297

-------
CO
I
UJ
(T
(T
UJ
H
(O
(/>
3
UJ
X
100
90
80
70
60
50
40
30
20
      10
      30
      20
       10
COD
                                            DEPTH.QN.)
         0123456
                       TIME  (HOURS)
SCREEN 1P_MESH. FILTER MEDIA. 60 in.No.-^ANTH./-3-!.in.No.^i2- SAND
DATE-Z/M/ZLFLUX
RUN N0.23SFIV
COMBINED  SEWER OVERFLOW  FILTRATION  TEST
                                          FIGURE CI26
                       298

-------
CO
o>
d
cd
d
q
0
300

200

100
  0
150
100

50

 0
300
200

100

  0
100
.80
.60
.40
.20
  0
                       INF.
                EFF.
.£
                         INF.
                               INF.
                       __-£_.
                                      EFF
                                     EFF.
 SCREEN4P.MESH. FILTER
 234
   TIME  (HOURS)
        in. NoJI_
                                     •     .6

                                     in.No.JLL2_SAND
                                     	Q	mg/|
 DATE 7/24/71  FLUX RATE  24  gpm/ft2  COAG      A---, „  -
       «,AQFU                     PQLY.PUraFLA-23tlOmq/|
 RUN No. 23ASFH;
 COMBINED  SEWER OVERFLOW FILTRATION  TEST
                                          FiGURE CI27
                         299

-------
I
UJ
cc
tr
UJ
H
u.
to
3
UJ
X
100
90
80
70
60
50
40
30
20
 10
  0
 30

 20

 10
             TSS
          0
                             \f
                                     COD
                -TP
                     \
                       V
                                             DEPTH. (IN.)
           1
234
 TIME  (HOURS)
SCREEN £2 MESH. FILTER MEDIA.JSp_Jn.No._3_ANTH./-l§.in.No.^i2_ SAND
DATE J/i4/2_ FLUX RATE-24_gprn/ft2
RUN N0.23ASFU
COMBINED  SEWER  OVERFLOW  FILTRATiON TEST
                                          FIGURE CI28
                        300

-------
300
^ 200
w! 100
0
_ 150
| 100
d
m 50
0
300
MFSH FI
nATF 7/24/71 FI
RUN Nn23ASFIIl
^
^^

^ 	
^
LTER ME
.UX RATE
^ /
^<^
..***'
— *~^

-INF.

	 • 	
EFF.


"""*""•"••
— 7 	
J


**^ 	
•^^
^^«


2 3 4 5 .6
TIME (HOURS)
"DIA 6^ in Nft 3 ANTH /36 in. No. 612 SAND
r 16

gpm/ft2 (
-OAfi 0 mg/|
pniYPURIFL.A-23,.0^/,

COMBINED SEWER OVERFLOW FILTRATION TEST
                 FIGURE CI29
301

-------
I
UJ
(C
UJ
3
 UJ
 X
100
 90
 80
 70
 60
 50
 40
 30
 20
 10
  0
 30

 20

 10
                               BOD
COD-
                                            V
                                               DEPTH. (IN.)
                   96
                   69
                   51
          0      I       23456
                         TIME  (HOURS)
SCREEN 4Q.MESH. FILTER MEDIA 60_in.No.A_ANTH./-36 in.No.^12. SAND
HATE 7/24/71   FI iix RATE   l6   aom/ft2 COAG	Q	mg/1
wr* I L» •	—.-...,—, I \-f\Jf\ I \r* | L_ ——.—..—.-.—-. ^plH/ I I  f^/^i w Ql ID! C"l  A ^^t I C\  /I
RUN NQ.23ASFIV                                   ^m9
COMBINED  SEWER  OVERFLOW FILTRATION TEST
                                            FIGURE CI30
                         302

-------
300
5 20°
E^
^ 100
CO
0
_ 150
| 100
a
C)
oi 50
0
300
«? 200
e^
d
d 100
o
0
1.00
£ -80
E .60
* .40
_i
f* .20
P 0
<
SCREEN^
HATF 7/2




**••»
' 	 	





^~~






	



/-INF.
JL — — -
-i I. i ••"•

^
A-EFF
/

— 	
X

•' .


w,
^ 	 (



IT -•-.•=


	

^EFF.
/-INF.
-L-— .




=^— I


	




"V-EFF^


	








D
^MESH. Fl
.4/71 n
RUN M» 23ASF1I1
COMBINED SE
^
^
X
X

LTER ME
.UX RATE
WER (
^^
^^
^-^


/-INF.
i---

^EFF.


^^» «^V ^HB




^"^ ^




2 3 4 5 .6
TIME (HOURS)
:DIA 60 'n Mft 3 ANTH / 36 in. No. 612 SAND
:8
)VERFI
gpm/ft2 (
-OW F
-OAG 0 mg/l
pnivPURIFLA-23, .Om0/l
LTRATION TEST
                 FIGURE CI3I
303

-------
I
UJ
oc
cr
u
H
3
UJ
I
      20
       10
                                             DEPTH.dN.)
                                                  96

                                                  72
                                                  54
                       234
                        TIME  (HOURS)
SCREENiP_MESH. FILTER  MEDIA.-60_in.No.J_ANTH./-36.in.No.li2_ SAND
DATE 7/24/71  FLUX RATE—S

RUN N0.23ASRV
                                                 .mg/l
                                   PQI Y PURIFLA-23,I.Omg/ I

COMBINED  SEWER  OVERFLOW FILTRATION TEST

                                           FIGURE CI32
                       304

-------
    600
d

§
ci
Q
o
    lO'O


    50


     0
    300


    200


    100


     0
    1.00

    -80
    .60

    .40

    .20

     0
                             /-INF.
                                     EFF.
                                          EFF
              I
                                              ,6
                     2345

                      TIME  (HOURS)

SCREEN 4P.MESH. FILTER MEDIA-§°_ in. NoJL_ ANm/_36 in. NO. 612 SAND
HATF 7/26/71


RUN No.23BSFII
                 RATE -24	gpm/ft2
                                             0
.mg/l
                                   POLY. MAG.560C 1.0 mg/1


 COMBINED SEWER  OVERFLOW FILTRATION  TEST

                                         FIGURE C133
                         305

-------
t/)
I
U!
cr
a:
Ui
u_
3
LJ
T.
100
90
80
70
60
50
40
30
20
 10
          0
                                             DEPTH.ON.)
                 234
                  TIME  (HOURS)
                                            SAND
SCREEN 1Q.MESH. FILTER  MEDIA. 6O in.No.A^.ANTH./-36 in.N
HATF  7/26/71  n ux RATE— 24__QDm/f*2 COAG -- <2 - mg/l
UA.fe - hLUXKAIt - gpm/ft  pn| YMAG.560C 1.0 mg/l
RUN Nn 23BSF1I
COMBINED  SEWER OVERFLOW FILTRATION  TEST
                                           FIGURE CI34
                        306

-------
600
^ 400
°i 200
CO
0
_ 150
£ 100
d
ai 50
0
300
«? 200
o*
Q IOO
0
0
|.00
•"* Of)
*L 60
* .40
£ .20
H 0
(
SCREEN^
^ /
-------
I \J\J
_ 80
^" 7f)
i \J
00
_J
^r 60
1 50
UJ
* 40
(T
u 30
_j
C 20
10
0
30
P
u_
~ 20
00
00
3
§ 10
UJ
X
0
(
SCREEN 4P.M
ftATF 7/26/'










.
TSS-








-r^
_/
X









^

BOD





**^^ /
^.
s_

-^
TP--



— —
-COD
V
V
x
^^^^ ^^^^^
\ ""
\
\
s


DEPTH.(IN.)


^fm^mm


£^S
D i ;
ESH. FILTER MEDI
71 Tl 1 IY BATF


^


— —
===


— *•
^ '-"


^
> 3 4 5 (
TIME (HOURS)
A 60 |p No 3 AMTW/36inWrt 612 <
8
RUN No.^SSEE
COMBINED SEWER OVERFLC
>m/ft2 «
)W FIL

o ,
^IY MA6.560CI.O^
TRATION TEJ
96
69
51
i%
SAND
ng/l
tig/ 1
5T
                  FIGURE CI36
308

-------
CO
0>


d
c>
CD
0
o
    600


    400
    200
                              EFF
                                            INF
o

               1234

                       TIME  (HOURS)


 SCREEN1P.MESH. FILTER MEDIA.6.0- in. Nl Y MAG. 560 C I.Omg/l


 COMBINED  SEWER OVERFLOW FILTRATION TEST

                                          FIGURE CI37
                         309

-------
l\J \J
90
80
^ TO
g 60
2 50
UJ
01 40

\
\


^^
-BOD

^.^
/*
i 	 / *
*
/
/


riss
\
\
\

*:sN
»*^_ ^
\x
\
\

^
/
1
I
1
,/
^^
/\

\
%
•

DEPTH. (IN.)


ssss


***&
D J
ESH. FILTER MEDI
'71 PI IIY PATF




^<
^*-^^

^=


^-•^
, — ——

I 3 4 5 (
TIME (HOURS)
A 60 jp Wo 3 AMTH/36in Mo 612 <
16
_,,.2 COAG. 0 l
UAit ..,^,^,^ y^,,,,,, pOLY MA(it>60CI.O,
RUN N0.23BSRV
COMBINED SEWER OVERFLOW FILTRATION TES
96 a 72
54
•%
>AND
ng/1
Tig/I
>T
                   FIGURE CI38
310

-------
                             APPENDIX D

                HIGH RATE FILTRATION OF SECONDARY EFFLUENT

         In addition to the major emphasis of the testing project at
Cleveland, that is, treatment of combined sewer overflows, a series of
tests were conducted on secondary effluent from the Southerly Waste -
water Treatment Plant.  Twenty test column runs were performed on
secondary effluent.  The media utilized in the testing was  as follows:

                                 Effective  Size    Uniformity
           Filter Media               (mm)         Coefficient

         No. 1 Anthracite               0.66           1.62
         No. 1 1/2 Anthracite          0.98           1.73
         No. 2 Anthracite               1.78           1.63
         No. 1220 Sand           .     0.95           1.41
         No. 2050 Sand                0.45           1.33

         Summarized results of the testing are indicated in Table Dl.
Data curves for all the test runs are indicated in Figures Dl through D19.
Media combinations utilized included:  48 inches of No. 1 Anthracite over
36 inches of No. 2050 Sand,  48 inches of No. 1 1/2 Anthracite over 36
inches of No.  2050 Sand,  and 48 inches of No. 2 Anthracite over 36
inches of No.  2050 Sand.   In some of the test runs, alum and  poly-
electrolyte were also utilized.  Filtration rates tested range from 10
gpm/sq ft to 30 gpm/sq ft.  A run was attempted at 45 gpm/sq ft, but
was discontinued when the pressure loss (head loss) generated through
the filter media was beyond range  of readings obtainable in the test
column gauges.

         The five media combinations  mentioned were evaluated under
runs  1SE through runs 10SE, as  shown in Table Dl. Unfortunately, due
to the low influent suspended solids levels,  it is difficult  to draw any
conclusions regarding the  various media.

         The combination of 48  inches  of No.  1 1/2 Anthracite over 36
inch'es of No.  1220 Sand was selected  for testing in conjunction with the
chemical additives.  The range  of influent suspended solids during these
six final test runs was in  a higher range than had been experienced in
the testing program.  The three  column runs performed under the 11 SE
test series had an average  influent suspended solids of 13.7 mg/1, with
a maximum of 32 mg/1.  The influent solids level in test series 12 SE was
18.4 mg/1. of suspended solids, with a maximum of 40 mg/1 of suspended
solids. These  solids levels are representative of a situation where a
                              311

-------
filter might be applicable.  Polyelectrolyte and alum were added to the
filter influent in both series 11 SE and 12 SE.  In test series 11 SE, 0.5
mg/1 polyelectrolyte was  added plus  5 mg/1 of alum; and in Series 12 SE,
1 mg/1 of polyelectrolyte  and 5 mg/L  of alum were added.  In these last
six test runs, utilizing chemical addition, the high rate filter produced
suspended solids consistently below 10 mg/1 throughout the test run,  as
shown in the data curves.  Even more interesting is the fact that
changing the filtration rate  from  10 gpm/sq.ft. to 30 gpm/sq.ft. had a
negligible effect on the performance of the filter, as evidenced by the
average  effluent quality values for the test runs.  Average effluent
quality approximated  4 to 6 mg/1.

         To summarize, the most important conclusion evidenced from
this test data is that, with  chemical addition, effluent suspended solids
can be controlled to below  10 mg/1 at filtration rates of 30 gpm/sq ft
and with lengths of filter runs in excess of four hours.  Head loss ex-
perienced during these latter filtration tests  with chemicals varied from
6.5 to 35.5 feet.
                             312

-------
      20
 CO
 Q
 _j
 o
 CO
 LJ
 Q
 Z
 LJ
 QL
 CO
 ID
 CO
 CO
 CO
 o
 UJ
 10
      40
 ~    30
20
       10
        0
                                           DEPTH (IN)
                          6    8     10

                         TIME  (HOURS)
                                    12
14    16
FILTER MEDIA 48  jn.No.LJ/2_ ANTH./_36_in No.2Q5PSAND/l8 in. GRAVEL

DATE 8/7/70  FLUX RATE	24	9Pm/ff2
RUN No.lSEII__

SECONDARY EFFLUENT FILTRATION TEST

                                       FIGURE D I
                         313

-------
 CO
 Q
 _J
 o
 Q
 U
 Q
 Z
 u
 Q-
 H
 LL


 CO


 §
 UJ
      20
       15
       10
       0

      20
       15
10
       0
                                     93-
                                   DEPTH (IN.)
                                 IN.-
         0    2     4    6     8    10    12    14   16

                         TIME  (HOURS)

FILTER MEDIA 48   in.No. il/L ANTH./_36_ jn No.?25?SAND/I8 in. GRAVEL

DATE 8/7/7°   FLUX RATE	!§	^pm/ft2

RUN NoJSEfiL

SECONDARY  EFFLUENT FILTRATION  TEST


                                      FIGURE D 2
                         314

-------
 CO
 Q
 _j
 o
 CO

 Q
 UJ
 Q
 Z
 UJ
 Q.
 CO
 D
 CO
 h-
 Lu

 CO
 CO
 O
 LJ
 X
FILTER MEDIA:

DATE_8/7/70
                         6     8    10

                         TIME  (HOURS)

               in. No. ' 1/2 ANTH./_36_ in No.?2§?SAND/l8 in. GRAVEL

             FLUX RATE _ ^     9pm/ff2
RUN No ISE1V

SECONDARY  EFFLUENT  FILTRATION TEST
                                      FIGURE D 3
                         315

-------
CD"
CO
Q
_J
O
CO
Ld
Q
2
UJ
CL
CO
3
CO
Lu
CO
CO
O
Q
<
UJ
 0
16
14
12
10
 8
 6
 4
 2
 0
         0
                                           DEPTH (IN,)
                                           39-
IN.-
                                    18    21
       24
               3    6     9    12    15
                         TIME  (HOURS)
FILTER MEDIA j48_ in.No. M/2_ ANTH./.36. ;n No.2^?SAND/18 in- GRAVEL
DATE 8/18/70  FLUX RATE	!Q	9Pm/ff2
RUN NolSEIV
SECONDARY EFFLUENT FILTRATION TEST
                                       FIGURE D 4
                        316

-------
  -
 CO
 Q
 _J

 co

 Q
 LJ
 O
 z
 LJ
 Q.
 CO
 Z)
 CO

 CO


 3
       8
0
2
                 INF;
           EFF,
                  6    8    10

                 TIME  (HOURS)
                                         12
14   16
FILTER MEDIA 48	jn.No..
     9/14/
             FLUX  RATE
               ANTH/36_ in Nor.™SAND/I8 in. GRAVEL
                   10     gpm/ft2
RUN Nn 3SEIV

SECONDARY  EFFLUENT FILTRATION TEST
                                      FIGURE D 5
                         317

-------
 CO
 g
 _j
 o
 CO

 o
 LU
 O

 LU
 CL
 CO

 CO
 CO
 CO
 O
 _J
 UJ
                         34567

                        TIME (HOURS)

FILTER MEDIA 48   in.No._i_ ANTH/_3£. in No£25?SAND/l8 in. GRAVEL

DATE 9/15/70   FLUX  RATF     15      W™'"2
RUN No.lSElV

SECONDARY  EFFLUENf FILTRATION  TEST

                                      FIGURE D 6
8
                        318

-------

CO
g
_j
o
CO

O
UJ
o
z
LJ
Q.
CO

CO
 CO
 8
       8
               INF,
  EFr
                         345

                        TIME (HOURS)
                                      8
FILTER MEDIA 48   in.No. J_ ANTH/M. in No.2^?SAND/l8 in. GRAVEL
DATE.
     9/16/70
FLUX RATE
              30
gpm/ff
RUN No.SSETV

SECONDARY EFFLUENT FILTRATION  TEST
                                     FIGURE D 7
                        319

-------
       10
            NF
 CO
 o
 _i
 o
 CO

 0
 u
 o

 LJ
 Q.
 CO

 CO
 CO
 CO
 O
 UJ
       0
         012345

                         TIME  (HOURS)


FILTER MEDIA 48   in.No._!_ ANTH/_36_in No?.259sAND/l8 in. GRAVEL

DATE 9/21/70  FLUX RATE    '0	9pm/ff2

RUN No.ZSElV

SECONDARY  EFFLUENT  FILTRATION TEST


                                      FIGURED 8
8
                         320

-------
       8
 CO
 Q
 _J
 O
 co

 Q
 UJ
 Q
 2
 UJ
 Q.
 CO

 CO
 CO
 CO
 O
 UJ
 X
        0
                        EFF
                                            DEPTH (IN)
                        TIME  (HOURS)

FILTER MEDIA _!§_ in.No._L_ ANTH/3§_ jn No^QS AND/18 in. GRAVEL

                                 9pm/ff2
10/14/70   FLUX RATE
                         5
RUN NQ.9SE1V
SECONDARY  EFFLUENT FILTRATION TEST
                                      FIGURE D9
                        321

-------
CD"
CO
Q

_J
O
CO

Q
LU
Q
Z
LU
Q.
CO

CO
 CO
 CO
 O
 LJ
                         345

                         TIME  (HOURS)
8
FILTER MEDIA  48_ in.No:_I_ ANTH./36_in No.2Q5C^AND/l8 in. GRAVEL
DATE 107 207 70 FLUX RATE	10	9P^/ft2
RUN N0.9SE1V

SECONDARY  EFFLUENT  FILTRATION  TEST

                                      FIGURE D 10
                       322

-------
       8
co
Q
_j
o
CO

Q
UJ
Q
2
UJ
Q.
CO
ID
CO
       0
 CO
 CO
 o
 LJ
                         345

                         TIME  (HOURS)
              7
                                                    8
FILTER MEDIA  48 m.Mo.l 1/2 ANTH/36 in Nlo.l220.gANn/l8 in. GRAVEL
                          10
gpm/ff
DATE 12/3/70  FLUX RATE _
RUN No.iOSEIL

SECONDARY  EFFLUENT  FILTRATION TEST
                                      FIGURE  D II
                         323

-------
       8
o"
 CO
 Q
 _j
 o
 CO

 o
 UJ
 Q
 z
 UJ
 Q.
 CO

 CO
 CO
 CO
 o
 UJ
        3 -
       0
                                            DEPTH (IN)
                         345

                        TIME  (HOURS)
7
8
FILTER MEDIA 48_in.No.U/2 ANTH/_36_ in NoJ£2QSAND/18 in. GRAVEL

DATEJ2/3/70  FLUX RATE__J5L	gpm/ff2

RUN MniOSEIII

SECONDARY  EFFLUENT  FILTRATION TEST


                                      FIGURE   D 12
                        324

-------
       8
o"
5

CO
g
_i
o
CO

Q
LU
O
z
LJ
Q.
CO

CO
 C/)
 O)
 O
 LJ
                                  EFF'
INF
                                            DEPTH (IN)
                         345

                        TIME  (HOURS)
             8
FILTER MEDIA 48  in.Nol 1/2 AMTH 736 in Nol220 SAND/18 in  GRAVEL

HATr 12/3/70  FLUX RATE	30	9P^^2
RUN MnlOSEIV

SECONDARY  EFFLUENT FILTRATION TEST

                                      FIGURE  D  13
                         325

-------
     32
CO
Q
_1
O
CO

Q
LJ
O
Z
UJ
Q_
CO

CO
CO
8
Q
<
     24
      16
       8
      0
                                           DEPTH (IN)
                                                    8
               I     234567

                         TIME (HOURS)

FILTER MEDIA _4§	in.No.LJ/2_ ANTH./li. in No!i?jO SAND/18 in. GRAVEL

HATF 12/7/70  FLUX RATF    10      9Pm/ff2

RUN No.iiSEIl

SECONDARY  EFFLUENT FILTRATION TEST

                                       FIGURE  D 14
                        326

-------
 CO
 g
 _i
 o
 CO

 Q
 LJ
 Q
 Z
 UJ
 0.
 CO

 CO
 J-
 u_


 CO
 CO
 o
 UJ
      32
      24
16
8
        0
                 EFE
                                        DEPTH (IN)
                          345

                         TIME  (HOURS)
                                               8
FILTER MFHIA 48  in.No.LJ/L ANTH/3JL in NoJ220 SAND/18 in. GRAVEL
                          15
                           gpm/ff
DATF 12/7/70  FLUX RATE-

RUN Mn. USEIII

SECONDARY  EFFLUENT  FILTRATION  TEST
                                      FIGURE  D  15
                         327

-------
CO
9

_i
o
CO

o
LU
Q
z
LU
Q.
CO

CO
CO
CO
O
Q
<
UU
                        TIME  (HOURS)
                                gpm/ft'
FILTER MEDIA_48__in.No.U/2 ANTH./36_in

DATE 12/7/70  FLUX  RATE	30

RUN Mn MSEIV

SECONDARY  EFFLUENT FILTRATION  TEST
                                    SAND/18 in- GRAVEL
                                     FIGURE D 16
                       328

-------
 CO
 Q

 _l
 O
 CO

 Q
 UJ
 Q
 Z
 UJ
 CL
 CO
 ID
 CO
 CO
 CO
 O
 UJ
10
                         345

                        TIME  (HOURS)
                                            8
FILTER MEDIA 48  in.No.I 1/2 ANTH/M. jn NoJ22Q SAND/18 in. GRAVEL
                         10
                         gpm/ff
DATE 12/8/70  FLUX RATE-
RUN No.J2SEU

SECONDARY EFFLUENT FILTRATION TEST

                                     FIGURE DI7
                        329

-------
 0)
 o
 Q
 UJ
 O
 z
 UJ
 Q_
 h-
 u_

 O)
 05
 O
 _J

 Q
 <
 UJ
                         345

                        TIME  (HOURS)
8
FILTER MEDIA 48  in.No.U/2 ANTH/36_ in No.2EQ SAND/18 in. GRAVEL

DATE 12/8/70  FLUX RATE __J5	^pm/ft2
RUN NoJ^SEHl

SECONDARY EFFLUENT FILTRATION  TEST

                                     FIGURE  D  18
                       330

-------
      40
en
Q
Q
UJ
Q
2
UJ
0.
 UJ
      30
      20
      10
                                            DEPTH (IN)
                         345

                        TIME  (HOURS)
8
FILTER MEDIAJ^_jn.No.J_l/2ANTH./16_inNo.!22psAND/l8in.  GRAVEL

HATF 12/8/70  FLUX RATE	£fi	gpm/ft2

RUN Kin I2SEIV

SECONDARY  EFFLUENT FILTRATION TEST

                                      FIGURE D 19
                        331

-------
                                                                  TABLE     D-l
HIGH-
RATE
Suscended Solids







00
CO
CO











Run
1SE-II
1SE-1II
1SE-IV
2SE-IV
3SE-1V
4SE-IV
5SE-1V
6SE-IV
7SE-IV
8SE-1V
9SE-1V
10SE-II
10SE-II1
10SE-1V
USE- 11
11SE-III
11SE-IV
12SE-II
12SE-III
12SE-IV
Media
48 "41 1/2A
36"»2050S
48"»1 1/2A
36"*2050S
48"*1 1/2A
36"»2050S
48"*! 1/2A
36"*2050S
48"(tlA
36"2050S
48"#1A
36-#20SOS
48"*1A
36"»2050S
4B"»2A
36"»2050S
48"»2A
36"*20SOS
48"*1A
36"»2050S
48"#2A
36"4tl220S
48"*1 1/2A
36"*1220S
48 "*1 1/2A
36"*1220S
48 "(tl 1/2A
36"#1220S
48"*1 1/2A
36"(tl220s
48"#t 1/2A
36"»1220S
48"#1 1/2A
36"*I220S
48 "*1 1/2A
36"*122CS
48 "tl 1/2A
36"*1220S
48 "tl 1/2A
3G"»1220S
Flux
Rate
(qpm/ll
24
Id
10
10
10
IS
.30
45
10
15
10
10
IS
30
10
15
30
10
15
30
Chemical Infl.
feed Tenp.
~i (mq/1) °1'
None 77
None 77
None 77
None 78
None 71
None 75
None 75
None —
0.5 Poly 76
1.0 Alum.
0.5 Poly 78
1.0 Alum.
1.0 Poly 66
S.OAlum.
None 55
None 55
None 55
0.5 Poly 55
S.OAlum.
0.5 Poly 55
S.OAlum.
0.5 Poly 55
S.OAlum.
1.0 Poly 57
S.OAlum.
1.0 Poly 57
S.OAlum.
1 . 0 Poly 57
S.OAlum.
Int.
Avq.
jmq/1)
10.1
10.1
10.1
6.2
4.3
3.6
4.1
Eft.
Avg.
(mg/l)
4.5
3.9
3.6
2.2
0.27
0.34
2.2
Ave.
Removal
55.4
61.4
64.4
64.5
93.7
90.6
47.6
FILTRATION OF SECONDARY EFFLUENT
Turbiditv Total Grqanic Carbon Total Phosphate
Inf.
Avg.
(ITU)
42
42
42
21
23
40
18
Efi.
Avg.
(ITU)
36
31
29
16
18
15
12
Avg. Ini. Eff. Avc1. Inf. Eff. Avg. Terminal
Removal Avq. Avg. Removal Avg. Avg. Removal Head Loss
X (mq/1) (ng/1) * (mq/1) 
24 — — — — — — 13.7
22 — — — 3.2 2.5 21.9 11.7
62 — — — 2.0 1.8 !0.0 13.7
33 — — — — — — 2J.1
UNABLE TO ATTAIN 45 GPM/FT2 WITHIN RANGE OF PRESSURE GAUGES — — — — —
4.3 0.14 96.8 15 10 33 — — — 4.3 4.1 4.7 17.3
5.3
9.0
5.5
5.5
5.5
13.7
13.7
13.7
18.4
18.4
18.4
2.3
1.6
0.32
0.25
0.86
4.9
4.6
5.4
6.6
4.9
5.3
66.0
82.3
94.2
95.4
84.3
64.3
66.4
60.6
64.1
73.4
71.2
13
36
18
18
18
23
23
23
31
31
31
S
25
8
11
8
9
14
11
21
17
14
38 — — — — — — 18.4
31 — — — 1.24 1.1 11.3 31.7
56 — — — — — — 5.4
39 — — — — — — 10.1
56 — — — — — — 27.0
61 — — — — — — 29.0
39 — — — — — — 30.0
52 — — — - - — 35.5
32 10 8 20 — — — 6.5
45 10 8 20 — — — 9.0
55 10 7 30 — — — 33'. S
Backwash
Length Total Vol. Total XTotal Air
of Run Filtered Volume Volume Rate
(Mrs.) (Gals.) (Gals.l Tillered Scfm
12 3670 63.5** 1.7 5
12 2650 71.3** 2.7 5
12 1530 63. S** 4.2 0
14 1780 240** 13.5 IS
12 1530 — — —
10 H'lO 74.2** 3.9 10
5 1910 79.5** 4.2 10
6 763 49.1*** 6.4 7
4 763 — — —
S 636 82.6*** 7.7 2.5
8 1020 — — —
8 1660 — — —
8 3060 — — —
7.5 954 — — —
6.5 1350 — — —
4 1530 — — —
8 1020 — — —
0 1660 — — —
8 3060 — — —
*  Calculations Based on Composite Samples
**  Calculations Based on Flow Rate Times Time of Backwash
*»* Calculations Based on Wat,er Depth i.i Backwash Tank

-------
                            APPENDIX E

    THE EFFECT OF PUMPING ON PARTICLE SIZE IN OVERFLOWS

        Tables E-l through E-3 show the effect of pumping on particle
size, as determined by particle counter analysis.  These analyses were
performed by the AWT Research  Laboratory (Cincinnati) on samples
taken before and after the pilot  plant influent pump, that is, at the
Junction Chamber, and at the Pump Discharge.

        The data indicate   an increase in the number of smaller
particles after pumping.  For example, for particle sizes equal to or
larger than 40.173 microns, the  number of particles per milliliter in the
Junction Chamber samples were approximately forty-five  percent
greater than in the Pump  Discharge samples.
                               333

-------
                 Table  E-t

COMBINED SEWER OVERFLOW SUSPENDED SOLIDS
       PARTICLE COUNTER RUN No. 1*
Particle
Diameter
(Microns)
60.995

54.523

45.987

40.173

36.499

31.885

28.311

25.307

21.345

18.646

16.941

14.800

13.140

11.746

9.907

8.655

* Sampling


Junction Chamber
N/ML
.

1.

12.

60.

123.

306.

779.

1356.

2697.

4616.

6276.

9346.

16318.

21432

31763

42786

Time: 12/3/70
% Cumul.
«•


0.7

2.7

4.6

8.5

15.4

21.3

30.4

38.6

43.5

50.1

60.2

65.4

72.4

77.1

79.9
15:30

Pump
N/ML
1.

2.

6.

24.

55.

174.

563.

1099.

2475.

4393.

6183.

9506.

16822.

23498.

36806.

51361.



Discharge
% Cumul.

0.0

0.2

1.0

1.9

4.3

9.7

14.9

23.8

31.6

36.7

43.5

53 . 6

60.1

68.7

74.6

77.9

                       334

-------
        Table  E-l (Continued)
Particle
Diameter
(Microns)
7.863

6.869

6.099

5.452

4.598

4.017

3.649

3.188
REMARKS:

Junction
N/ML
52116.

66246.

90582.

116270.

171705.

242127.

313267.

406437.

Chamber
% Cumul .

82.9

86.4

89.1

92.8

95.8

98.0

100.0


Pump
N/ML
6285.7.

80786.

112093.

142806.

207240.

284525.

358348.

440158.

Discharge
% Cumul.

81.5

85.9

88.9

93.0

96.2

98.3

100.0

N/ML: Number of particles equal to or greater than
given particle diameter.
% C.umul: Cumulative percentage
by volume
for each
particle diameter range (Cumulative by weight assuming all
particles'have the same density).
                 335

-------
                      Table E-2

     COMBINED SEWER OVERFLOW SUSPENDED SOLIDS
             PARTICLE COUNTER  RUN No. 2*
Particle
Diameter
(Microns)
60.995

54.523

45.987

40.173

36.499

31.885

28.311

25.307

21.345

18.646

16.941

14.800

13.140

11.746
*•
9.907

8.655


Junction
N/ML
__

2.

17.

90.

215.

535.

1461.

2840.

6928.

12851.

17962.

25628.

35796.

41996.

49844..

55433.


Chamber
% Cumul.
—
-

0.6

2.4

4.6

8.6

16.5

24.9

41.3

56.2

65.2

74.8'

83.5

87.3

90.4

91.8

92.6

Pump
N/ML
1.

1.

9.

62.

146.

350.

912.

1652.

3683.

6529.

9012.

12875.

19086.

23666.

30565.

36895.


Discharge
% Cumul.

0.0

0.5

2.7

5.1

9.4

17.3

24.7

38.2

50.1

57.3

65.4

74.1

.78.7

83.3

85.9

87.5
* Sampling Time:  12/3/70  17:30
                         336

-------
Table E-2 (Continued)
Particle
Diameter
(Microns)
7.863

6.869

6.099

5.452

4.598

4.017

3.649

3.188

Junction
N/ML
60130.

66331.

89663.

106291.

143522.

184510.

220173.

249837.

Chamber
% Cumul.

93.4

95.4

96.4

97.9

98.9

99.6

100.0


Pump
N/ML
42130.

50045.

67860.

84087.

120565.

166554.

210269.

262880.

Discharge
% Cumul.

89.1

91.6

93.2

95.7

97.6

98.9

100.0

    337

-------
                     Table E-3

      COMBINED SEWER OVERFLOW SUSPENDED SOLIDS
             PARTICLE COUNTER RUN No. 3*
Particle
Diameter
(Microns)
60.995
54.523

45.987

40.173

36.499

31.885

28.311

25.307

21.345

18.646

16.941

14.800

13.140

11.746

9.907

8.655


Junction
N/ML
-
1.

7.

36..

68.

159.

399.

695..

•1329.

2130..

2903.

'4413.

9681.

17609.

40509.

66667.


Chamber
%. Cumul .


0.5

1.9

3.0

5.3

9.4

13.0

18.0

22.1

24.8

28.5

37.5

47.1

65.4

78.5

85.2

Pump
N/ML
-
1.

5.

20.

51.

130.

338.

580.

1158.

1972.

2728.

4151.

8031.

13280.

. 30406.

57688.


Discharge
% Cumul.


0.3

1.0

2.1

4.1

7.7

10.6

15.2

19.3

22.0

25.6

32.2

38.5

52.3

66.0

74.7
* Sampling Time:  12/3/70  20:30
                        338

-------
Table E-3 (Continued)
Particle
Diameter
(Microns)
7.863

6.869

6.099

5.452

4.598

4.017

3.649

3.188

Junction
N/ML
85845.

107328.

128822.

147593.

170150.

185587.

199965.

212483.

Chamber
% Cumul.

90.6

94.3

96.6

98.4

99.1

99.6

100.0


Pump
N/ML
82343.

118032.

156225.

191797

232515.

257370.

276875.

285497..

Discharge
% CunrjuJ.,,

83.7

90.2

94.5

97.8

99.0

99.7

100.0

        339

-------
1
ylccession Number
w
2

Subject Field & Group
SELECTED WATER RESOURCES ABSTRACTS
INPUT TRANSACTION FORM
      Organization

      Hydrotechnic Corporation,  Consulting Engineers
      641 Lexington Avenue,  New York,  New York 10022
      Title
      High Rate Filtration of Combined Sewer Overflows
  10
Authors)
Ross Nebolsine
Patrick J. Harvey
Chi-Yuan Fan
      16
                                        Project Designation
                                      EPA. ORM Project #11023EYI. Contract #14-12-858
                                    21
                                        Note
  22
Citation

"Water  Pollution Control Research Series 11023EYI 04/72
  23
£c56mfei'h(e;(!rSewIesP Overflow, *Deep bed, dual media, high rate filtration, *Drum
screen, Anthracite, Sand,  Suspended Solids,  Biochemical Oxygen Demand,
Chemical Oxygen Demand, Coliforms,  Precipitation, Urban Runoff,  Activated
Sludge Plant Effluent, Cost Estimates.
  25
      Identifiers (Starred First)
      *Combined Sewers, Cleveland, Ohio
      Abstract
      Pilot plant studies were conducted at Cleveland's Southerly Wastewater Treatment
Plant in 1970 and 1971,  to develop and demonstrate the capabilities of the deep bed,  dual
media,  high rate. filtrate treatment process for storm" caused combined sewer overflows.
      The treatment system is comprised of a drum screen with a 40 mesh screening elemenl
(420 microns opening) followed by a deep bed,  dual media, high rate filter of five feet of
No.  3 anthracite (effective size 4 mm) over three feet of No.  612 Sand  (effective size 2 mm).
The results show suspended solids removals of 93 percent, with polyelectrolyte addition, at
a filtration   rate of 24 gpm/sq ft at an average influent suspended solids of 411 mg/1.
Reductions in biochemical oxygen demand averaged 65 percent.
      Capital costs (ENR=1470) for a high rate filtration plant are about $23, 000 per mgd.
Total annual treatment costs,  including  capital and operating charges,  range from approx.
$90, 000 per yr for a 25 MGD plant to approx. $390, 000 for a 200 MGD treatment facility.
      Principal advantages of  the proposed system are: high treatment efficiencies,  auto-
mated operation,  and limited space requirements as compared with alternate flotation
or sedimentation systems.
      This report was submitted in fulfillment of Project #11023EYI (Contract 14-12-858)
under the sponsorship of the Office of Research and Monitoring,  USEPA.
  Abstractor
  Chi-Yuan Fan
Institution
Hydrotechnic Corporation,
                                                    Consulting Engineers
   WR:I02 (REV. JULY 1969)
   WRSIC
                       SEND, WITH COPY OF DOCUMENT, TO: WATER RESOURCES SCIENTIFIC INFORMATION CENTER
                                                U.S. DEPARTMENT OF THE INTERIOR
                                                WASHINGTON, D. C. 20240

                        •fr U. S. GOVERNMENT PRINTING OFFICE: 1978 — 657-060/1517

-------