Lean  Government
                        Florida Submerged Lands and Environmental Resources
                                  Permit Process Kaizen Event Case Study
 Summary
 In Florida, the Department of Environmental Protection's (FDEP) Submerged Lands and Environmental Resource Permitting
 Program (SLERP) addresses dredging, filling, and construction in wetlands and other surface waters. The program is designed to
 ensure that activities do not degrade water quality or degrade habitat for aquatic or wetland dependent wildlife. To protect the
 environment, developers must obtain an Environmental Resource Permit before beginning any construction activity that would
 affect wetlands, alter surface water flows, or contribute to water pollution.

 In response to observations that there were inefficiencies in the 30-day permit review process, FDEP's Northwest District Office
 conducted a Lean kaizen event to streamline the SLERP "Dredge and Fill" permitting process. This event was held in August 2009
 with support from U.S. EPA Region 4. In the existing process, the time from receipt of a permit application to when it reached a
 processor was taking as much as 10 days.  As an application is required to be reviewed by a processor in 30 days or less, there
 was sometimes only 20 days left for a full technical review.

 The objectives of the four-day Lean event were to introduce participants to Lean tools and to create an implementation plan to
 eliminate waste from the Dredge and Fill permit application process. Participants also wanted to develop efficiencies that would
 be transferable to other FDEP processes. The Lean event team designed a new, streamlined process in the  event and identified a
 series of actions to eliminate inefficiencies, simplify the process, and improve the quality of applications. Implementation
 activities have continued since the event, and FDEP has achieved a 50 percent reduction in the time it takes for an
 application to reach a processor for technical review.
 Results
 With implementation since the Lean event, FDEP has achieved the following results:
 •  Reduced lead time of the process from 6.5 days to 0-3 days (greater than 50% reduction))
Scope of the Lean Project
Project Scope:  FDEP SLERP Dredge and Fill permit application process from receipt of application until it reaches the proc-
essor for technical review
Goals of the Lean Event

    •   Reduce time of the first phase of the Dredge and Fill application process by 50%.

-------
Process Changes

During the kaizen event, FDEP
participants developed "current
state" and "future state" maps of the
process. Participants then developed
an implementation plan to work
toward the future SLERP process
based on the following key process
improvement areas.

•   Improve the quality of
    applications by informing the
    public on proper application
    requirements.
•   Decrease application transmittal
    time by obtaining permission to
    e-mail scanned copies of
    applications to the US Army
    Corps of Engineers (USAGE).
•   Move scan and fax equipment
    closer to staff.
•   Minimize or eliminate the
    distribution and copy process.
•   Increase communication
    efficiency with applicants by
    requesting an e-mail address on
    the application.
•   Streamline process steps
    between Administrator and
    Supervisor.
•   Minimize the time an application
    spends in the queue by
    implementing visual signals.


Implementation
 Figure i: Current State Process Map














. A,
/ \


W Ik
Env. Supervisor 4
and/or check


date
->


'
Check for previous

Make co
foi USACoE
'




•*

Spr,,d,lĞ,t
Figure 2: Future State Process Map
and/or check
-
P,ği,cti,,Po,-Ği,
*
n,,M^,,™ =„==,.
-
Fill out Excel I
Spreadsheet p
E-Scan or e-fax |
Enter "distributed by"
-J Place InR Y G bins

-
of each day ' *
into purple box
Since the event, participants have been working to implement the streamlined process. Key implementation activities have
included:

•   Defining the criteria for a complete application - More specific instructions on using the fee list and completing an
    application have been provided on the cover sheet, and an application is no longer complete without correct fees.

•   Collecting data metrics on complete vs. incomplete applications - The staff maintains an internal  spreadsheet which tracks
    receipt of a dredge and fill application and fees and the spreadsheet tracks when an application goes to and is received from
    a processor. This spreadsheet allows the team to collect data metrics on complete applications. An application is no longer
    complete without correct fees.
•   Tracking the number of days an application takes to get to the Processor - Average time from administrative staff to
    processor is currently 0-3 days.

-------
•   Installing color-coded hanging file folders to send visual signals on status to teammates - green, yellow, red, and clear wall pock-
    ets have been installed and are being utilized.

•   Holding 30-minute check-ins each morning to review folders and make appropriate staff notifications - Supervisors are maintain-
    ing the 30-minute meetings. These meetings are used to discuss the status of applications and subsequent information for com-
    menting agencies. Additional discussions regarding commenting agencies are done via email.

•   Acquiring permission to scan application documents and e-mail them to USAGE -The current operating agreement between FL
    DEP and USAGE dictates the receiving of a hard copy. FL DEP has been unable to gain permission from State Lands Title Check to
    change from fax to email.  These changes will eventually save time and money
•   Acquiring and installing all-in-one copier access-The current budget has prevented the purchase of all-in-one copiers, which
    would save additional time and resources.
The primary purpose of the Lean event was to allow more time in a 30-day review cycle for the processors to review Dredge and Fill
permit applications. By implementing the Lean implementation plan, the team has accomplished a 50 percent reduction in the time it
took for an application to reach a processor, thereby allowing more time for review.
EPA received positive feedback from the post Lean event survey, but most participants expressed skepticism over the ability and wili-
ness to implement the plan. The SLERP Administrator has since retired, but the Lean team has been able to implement the Lean recom-
mendations and maintain these critical improvements. FL DEP continues to face budget constraints, but implementing the Lean plan
has proven to help save time and will help to save shrinking state resources.
Shortly after the Lean event on the dredge and fill process, the original Lean team  and a few new participants conducted another value
stream mapping event focused on the referral process for State Board items regarding State Lands. The Northwest District is interested
in implementing Lean across the entire District and became a member of the Jacksonville Lean Consortium to benefit from shared
learning and networking on Lean-based continuous improvement efforts.
         For More
      Information:
Florida DEP Lean Event
Latoya D. Miller, US EPA Region 4, (404) 562-9885, miller.latoya@epa.gov
Suganthi Simon, US EPA Region 4, (404) 562-9384, simon.suganthi@epa.gov
 Barbara Ruth, SLERP Administrator, FDEP, (850) 595-8300 xii28,
    Barbara. Ruth @dep.state.f I.us
 Brandy M. Smith, Administrative Assistant, FDEP Water Facilities Program NW District,
    (850) 595-8300x1155, Brandy.M.Smith@dep.state.fl.us

 EPA Lean Government Initiative
 Jamie Burnett, EPA OPEI, (202) 566-2305, burnett.jamie@epa.gov
 Kimberly Green-Goldsborough, EPA OPEI, (202) 566-2355,
  green-goldsborough.kimberly@epa.gov
 http://www.epa.gov/lean/leangovernment
United States
Environmental Protection
Agency
                Office of Policy,
                Economics and Innovation
                (1807T)
     June 2010
EP A- 100-F-10-024

-------