Cleanup
           Update
   Diana Hammer, US EPA
       457-5040
   hammer.diana@epa.gov

   Keith Large, MT DEQ
       841-5039
      klarqe@mt.gov

   Doug Martin, MT NRDP
       444-0234
    douqmartin@mt.gov

 Peter Nielsen, Missoula Co.
       258-4968
 Nielsen P© ho.missoula.mt.us

       Websites:
    http://www.epa.gov/
  regionS/superfund/sites/
      mt/milltown

   http://wiA
http://www.cfrtac.org
    To view on-going
 activities, please visit:
 http://www.clarkfork.org/
 and click on the webcam.
                                 Milltown  Reservoir
                                           Sediments
                                     Superfund  Site     i
                        Status: The Milltown Project continues to go very well and is on schedule.
                        Project personnel have worked 313,027 hours without time lost to injury.
                                                                                      Issue #88

                                                                                     September 2, 2009
                         REMEDIATION AND RESTORATION
                         •   As of Monday, 2,933,472 tons (~ 2,256,517 cubic yards) of sediment have been excavated,
                            loaded and hauled off-site. This portion of the project should be complete by the end of
                            September 2009—almost exactly two years from the start of sediment hauling by rail.
                         •   Continuing to excavate sediments  from  under the former rail spur area.
                         •   Last week, removed 350 feet of  rail and shortened the train to just 8 cars.   Crews
                            are now switching out trains six times/day and so far have been able to avoid switching out
                            trains during the busy school arrival and departures times. Sediment hauling should be com-
                            pleted by the end of September so there should only be a short overlap with the school
                            schedule. Please bear with us as this phase of the project nears completion.
                         •   As reported in the last update, EPA coordinated with the  State and Minercl, Missoula,
                            and Sanders Counties to select locations of sediment samples along the Clark F~»rk River
                            from Sha-Ron Fishing Access downstream to Thompson Falls.  The results are in and the
                            levels of arsenic are well below levels considered to be  safe for recreational use (levels that
                            were low enough to even be considered safe under residential exposure scenarios).
                         •   Recently, Governor Schweitzer approved the agreement between  the State and  ARCO
                            (and its  representatives) to remove approximately 230,000 cubic yards of material from
                            the area known as  SAA Illb and  deposit the material in the Tunnel Pond repository. This
                            action will result in a wider Clark Fork River f loodplain.  Work in this area  began on Monday,
                            8/31, and should be  complete by December 2009. The Clark Fork Coalition received a grant
                            from the MT Natural Resource Damages  Program for this removal in 2007.
                          •   Installed seven new dewatering wells along the old Milwaukee Rail road grade on the
                            south side of the Remedial Project Area. De-watering this area will  facilitate construction
                            of the buttress along Tunnel Pond and storage of SAA Illb sediments in that repository.
                          •   Implementation of the Restoration Grading Plan continues— Area J:  excavation of mate-
                            rial; hauling material to Area B; construction of river channel and sideVhannels, wetlands,
                            and planting swales.  Work continues in the Remedial Project Area and upstream.

                                                                                                         J
                                                                                                         IS0
  These updates are intended to
   provide you with the latest
  information about remediation,
  restoration and redevelopment
      activities at the
Milltown Reservoir Superfund Site.
^
         US EPA Montana Office
         10 W.I 5th St., Ste.3200
        Helena, Montana 59626
                                                                                                     in
                                                                                                     £

                                                                                                     I
                                                                                                     z
                                                                                                     a.
                                                                                                     1
                                                                                                     I
                                                                                                     O

-------
 Upcoming
    Events
Weds., September 9
NOTE NEW DATE
Milltown Redevelopment
Working Group regular
meeting 6:30 pm at Our
Savior's Lutheran Church
in Banner.  Please join us!

Monday, September 14
Banner Community
Council meeting 7 pm
Banner School  Library.
Last train load of
sediment leaves the
Milltown project area
(exact date TBD)

Sept. 30-October 2
 Waters that Cross
Divides—3 o\rrt Confer-
ence of the Montana
Section of the American
Water Resources Asso-
ciation and the Univer-
sity of Montana Center
for Riverine Science.
The conference will be
held at the Holiday Inn
Parkside in Missoula.  For
more information and to
register, please visit:
http://water.montana.ed
u/awra/registration/
default.asp

October 2009
Milltown Project Update
on the 3Rs: Remediation,
Restoration, and Redevel-
opment. Public meeting
and open house in Banner
(exact date TBD).
On-going and Upcoming work:
•  Continue sediment excavation, hauling, and
   disposal of contaminated sediments;
•  Week of 9/7, remove another 200 feet of
   rail spur to allow excavation
•  Envirocon, US(5S, U of M, and Missoula Co.
   continue surface and groundwater monitor-
   ing of Clark Fork River and wells;
•  NRPD continues to monitor surface water
   for turbidity from upstream activities;
•  FWP continues fish monitoring (caged fish
   and radio-tagged fish) on sections of the
   Blackfoot and Clark Fork Rivers;
•  USSS continues to monitor scour and flow
   conditions on the Blackfoot River;
•  Restoration work continues excavating new
   river channel and stockpiling Buried A-
   horizon soils for later use;
•  Continue restoration work in the very upper
   end of the reservoir (above former Duck
   Bridge) in SAA- IV and V; creating a new
   channel.  Access will be off Rustic Road.
•  Redevelopment/Park planning continues;
•  September 2009: Complete removal and
   rail hauling of over 2.2 million cubic yards
   of contaminated sediments from the
   former Milltown Reservoir area.
  PROJECT SCHEDUU
 2009  Sediment removal
       Rail hauling sediment
       Restoration
       Redevelopment
2010  Restoration
       Redevelopment
2011  Restoration
       Redevelopment
     WARNING
   Safety Reminder
DURING THE MILLTOWN CLEANUP,
THE CLARK FORK AND BLACKFOOT
      RIVERS ARE CLOSED
TO RIVER RECREATION ABOVE AND
   BELOW THE PROJECT AREA.
Clark Fork River users must exit
             the river at Turah
              Fishing  Access;
              Blackfoot River
             users must exit at
              Weigh Station.

       VIOLATORS and
       TRESPASSERS
       WILL BE FINED.
 For more information, contact
  Montana FWP at 542-5500.
                                             9/1/09 Photo at left showing the view
                                             along old Milwaukee railroad grade with
                                             new dewatering wells installed. Rail
                                             road berm will be re-shaped and
                                             re-enforced to make it more stable as
                                             the SAA Illb sediments are added to
                                             the Tunnel Pond repository (area to
                                             left of roadway). Removal of these
                                             sediments should be complete by De-
                                                         Stakes shown in this
                                                         photo (/1/09) taken in the
                                                         upstream Restoration
                                                         Area CFR3 mark the new
                                                         Clark Fork River Channel.
                                                         The bank of young willows
                                                         seen at the right will be
                                                         preserved. Work in this
                                                         area will  be complete
                                                         later this fall (2009).

-------