Soda Ash Manufacturing
Monitoring Checklist
&EPA
United States
Environmental Protection
Agency
Final Rule: Mandatory Reporting of Greenhouse Gases
What Must Be Monitored for Each Soda Ash Manufacturing Line?
If NOT using a CEMS, measure these parameters...
Site-specific emission factor method:
D Process vent flow rate from mine water
stripper/evaporator during annual
performance test (pounds/hour)
D Stack gas volumetric flow rate per minute
(dscfm)
Hourly carbon dioxide (CO2)
concentration (percent CO2)
CO2 mass emission rate
(metric tons/hour)
Alternative calculation method:
D Monthly inorganic carbon content in trona
input by daily measurement
(percent by weight)
D Monthly inorganic carbon content in soda
ash output by daily measurement
(percent by weight)
Other parameters:
D Monthly mass of trona input (tons)
D Monthly mass of soda ash output (tons)
D Monthly consumption of trona or liquid
alkaline feedstock (metric tons)
D Monthly production of soda ash (tons)
If using a CEMS:
In addition to the monitoring requirements under 40 CFR subpart C for the
Tier 4 Calculation Methodology, measure these parameters...
D
Monthly consumption of trona or liquid
alkaline feedstock (metric tons)
D
Monthly production of soda ash (tons)
See also the information sheet for Soda Ash Manufacturing (EPA-430-F-09-036R) at:
www.epa.gov/climatechange/emissions/downloads/infosheets/sodaashmanufacturing.pdf.
Soda Ash Production Monitoring Checklist
Mandatory Reporting of Greenhouse Gases
Page 1 of 1
40 CFR 98, subpart CC
September 2009
------- |