-------
Table 4-4. Design Specifications for AdEdge APU-50LL-CS-S-2-AVH System
Parameter
Value
Remarks
Pre-treatment
Target pH Value after Adjustment (S.U.)
Target Chlorine Residual (as C12)
7.0
1.2
Using CO2
Using NaCIO
Adsorption Vessels
Vessel Size (in)
Cross-Sectional Area (ft2/vessel)
Number of Vessels
Configuration
42 D x 72 H
9.6
2
Series
AD-33 Adsorption Media
Media Bed Depth (in)
Media Quantity (Ib)
Media Volume (ft3)
Media Type
27.5
1,540
44
AD-33
770 Ib/vessel
22 ft3/vessel
In pelletized form
Service
Design Flowrate (gpm)
Hydraulic Loading Rate (gpm/ft2)
EBCT (mm/vessel)
Estimated Working Capacity (BV)
Throughput to Breakthrough (gal)
Average Use Rate (gal/day)
Estimated Media Life (months)
40
4.2
4.1
46,900
7,725,000
12,000
21.5
Based on flowrate of 40 gpm per vessel (8.2
min total EBCT for both lead and lag vessels)
Bed volumes to 10 ug/L total As breakthrough
from lag vessel based on vendor estimate
1 BV = 22 ft3 = 164 gal
Based on 5 hr/day operation at 40 gpm
Estimated frequency of media change-out from
lead vessel based on 12,000 gal/day use rate
Backwash
Pressure Differential Set Point (psi)
Backwash Flowrate (gpm)
Hydraulic Loading Rate (gpm/ft2)
Backwash Frequency (month/backwash)
Backwash Duration (mm/vessel)
Service-to-Waste Fast Rinse Flowrate (gpm)
Fast Rinse Duration (min/vessel)
Wastewater Production (gal/vessel)
10
90
9.4
3-4
20
90
1-4
1,890-2,160
Actual backwash frequency to be determined
-
-
-
-
valve and a rotameter. Further, a solenoid valve interlocked with the well pump
allows gas to flow only when the well pump is turned on.
After flowing out of the control panel, CO2 is injected into water through a CelgardŽ
microporous hollow fiber membrane module housed in a 1.5-in stainless steel
sanitary cross. Table 4-5 lists the properties and specifications of the hollow fiber
membrane module. The sanitary cross is located in a side stream from the main
water line to allow only a portion of water to flow through the membrane module to
minimize the pressure drop. The membrane introduces CO2 gas into water at a near
molecular level for rapid mixing/reaction with water to achieve a quick pH response/
change.
Located downstream from the sanitary cross, a Sentron Ion Sensitive Field Effect
Transistor (ISFET) type silicon chip sanitary pH probe with automatic temperature
compensation continuously monitors pH levels of the treated water and sends signals
back to the pFI/PID controller for pH control.
20
-------
ATSI CO, pH Control
Panel (ATSI)
Source: Applied Technology Systems, Inc. (ATSI)
1.5" Dia. PVC Housed
Membrane w/
1" MNPT Connection
on each end for water
20 Ib or 50lb
Cylinders for
Gas Supply
Ball Valve or Other
Flow Control Valve
Distance to pH probe
(Distance 10')
Horn
Power In
Wellpump
Contacts
C02 Gas
Inlet
4-20 rriAmp
Signal to
Control
Module
BV1
Figure 4-6. Process Diagram of (top) CO2 pH Adjustment System and (bottom)
pH/PID Control Panel
21
-------
Figure 4-7. Carbon Dioxide Gas Flow Control System for pH Adjustment
(Clockwise from Top Left: Liquid CO2 Supply Assembly;
Automatic pH Control Panel; CO 2 Membrane Module; Port for pH Probe)
Table 4-5. Properties of CelgardŽ, X50-215 Microporous
Hollow Fiber Membrane
Parameter
Porosity (%)
Pore Dimensions (urn)
Effective Pore Size (urn)
Minimum Burst Strength (psi)
Tensile Break Strength (g/filament)
Average Resistance to Air Flow (Gurley sec)
Axial Direction Shrinkage (%)
Fiber Internal Diameter, nominal (urn)
Fiber Wall Thickness, nominal (um)
Fiber Outer Diameter, nominal (um)
Module Dimensions (in)
Value
40
0.04x0.10
0.04
400
>300
50
<5
220
40
300
1.5 x3.0
Data Source: Celgard
22
-------
o Throughout the first six-month operational period, the CO2 pH control system
supplied CO2at approximately 14.2 ft3/hr, using about 7 Ib/day (based on a gas
density of 0.117 lb/ft3 and an average operating time of 4.3 hr/day). The CO2 gas
supplied from two 50-lb cylinders provided CO2 for about 14 days before requiring
change-out.
Prechlorination. The existing chlorination system, as shown in Figure 4-3, was upgraded
and installed inside the maintenance building along with the APU-50LL-CS-S-2-AVH
system. The chlorine addition system oxidizes As(III) to As(V) prior to the adsorption
vessels and provides a target chlorine residual of 1.2 mg/L (as C12) for disinfection in the
distribution system. The chlorine feed system, illustrated in Figure 4-8, includes a solenoid-
driven, diaphragm-type metering pump with a capacity range of 0.19 to 8.4 gal/hr (gph), a 50-
gal high-density polyethylene (HDPE) chemical feed tank to store the 10% NaCIO solution,
and a chlorine injection port. The chlorine is injected into raw water line following the CO2
injection and pH probe, but prior to the AP sampling location. Operation of the chlorine feed
system is linked to the well pump so that chlorine is injected only when the well is on.
Chlorine consumption is measured using volumetric markings on the outside of the feed tank.
Figure 4-8. Chlorination Feed System
(Clockwise from Top Left: Chlorine Metering Pump;
HDPE Chemical Feed Tank with Secondary Containment; Chlorine Injection Port)
23
-------
Adsorption. The AdEdge APU-50LL-CS-S-2-AVH system consists of two 42-in-diameter,
72-in-tall pressure vessels configured in series, each containing 22 ft3 of AD-33 media. The
tanks are carbon steel construction, skid mounted, and rated for 100-psi working pressure.
EBCT for the system is 4.1 min in each vessel. The hydraulic loading rate to each vessel is
approximately 4.2 gpm/ft2, based on the design flowrate of 40 gpm.
Each pressure vessel is interconnected with schedule 80 PVC piping and five electrically
actuated butterfly valves, which make up the valve tree as shown in Figure 4-9. In addition to
the ten butterfly valves, the system has two manual diaphragm valves on the backwash line
and six isolation ball valves to divert raw water flow into either vessel, which reverse the lead
lag vessel configuration. Each valve operates independently and the butterfly valves are
controlled by a Square D Telemechanique programmable logic controller (PLC) with a
Magelis G2220 color touch interface screen.
Figure 4-9. Adsorption System Valve Tree and Piping Configuration
Backwash. The vendor recommended that the APU-50LL-CS-S-2-AVH system be
backwashed, either manually or automatically, on a regular basis to remove particulates and
media fines that accumulate in the media beds. Automatic backwash can be initiated by
either timer or differential pressure (Ap) across the vessels. During the backwash cycle, each
vessel is backwashed individually, while the second vessel remains off-line. Backwash is
performed upflow at a flowrate of 90 gpm to achieve a hydraulic loading rate of about 9.3
gpm/ft2. Because the incoming flowrate from the supply well is insufficient to provide the
necessary flow for backwash, supplemental water is supplied from the treated water storage
tank to the head of the system. Each backwash cycle is set to last for about 20 min/vessel of
backwash followed by 1 to 4 min/vessel of service-to-waste fast rinse, generating a combined
total of approximately 1,890 to 2,160 gal/vessel of wastewater.
24
-------
The backwash water produced is pumped to a 12,000-gal fiberglass backwash storage tank
located adjacent to the treated water storage tank (see Figure 4-1). Water from the backwash
storage tank is sent to an on-site wastewater plant and then to a series of four stabilization
ponds, which provide approximately 120 days of storage capacity. If the storage capacity of
the stabilization ponds is exceeded, the discharge goes to a normally dry streambed, where it
ultimately evaporates or percolates into the ground. However, due to the minimal pressure
drop across the vessels throughout the first six months of system operation, system backwash
was not necessary. The pressure drop and the arsenic concentrations across the vessels will
continue to be monitored and a backwash will be scheduled, when needed, during the next six
months of system operation.
Media Replacement. The media in the lead vessel will be replaced once the arsenic
concentration from the lag vessel reaches 10 |o,g/L. After the media replacement in the lead
vessel, flow through the vessels will be switched such that the lag vessel is placed into the
lead position and the former lead vessel with the virgin media is placed in the lag position.
The spent media will be tested for EPA's toxicity characteristic leaching procedure TCLP
before disposal.
4.3 System Installation
The installation of the APU system was completed by AdEdge on November 19, 2005. The following
briefly summarizes some of the predemonstration activities, including permitting, building preparation,
and system offloading, installation, shakedown, and startup.
4.3.1 Permitting. An exception submittal package was submitted to TCEQ by Webb CISD on
April 18, 2005, requesting an exception to use data from an alternative site in lieu of conducting an on-
site pilot study as required under Title 30 Texas Administrative Code (30 TAC) §290.42(g). The
exception submittal included a written description of the treatment technology along with a schematic of
the system and relevant pilot- and full-scale data. In addition, a permit application submittal package
including a process flow diagram of the treatment system, mechanical drawings of the treatment
equipment, and a schematic of the building footprint and equipment layout also was submitted to TCEQ
for permit approval on April 18, 2005. TCEQ requested supplemental information, in a response letter
dated June 3, 2005, to complete their review of the request. In response, supplementary data were
provided by the vendor on July 14, 2005, Battelle on August 22, 2005, and Littlefield of Southwest
Engineers, Inc. on August 29, 2005. Based on a review of the submitted data (which included revised
engineering plans and specifications, dated August 19, 2005) and discussions with the vendor, Battelle,
and EPA, TCEQ granted an exception request and approval to construct the arsenic removal treatment
system on August 31, 2005.
4.3.2 Building Preparation. The existing maintenance shop building as shown in Figure 4-10 had
adequate space to house the planned arsenic treatment system. The maintenance building is a single-story
metal structure with concrete flooring. Additional preparation required the installation of a lockable wire
cage enclosure around the treatment system.
4.3.3 Installation, Shakedown, and Startup. The treatment system arrived on-site on October 13,
2005. Figure 4-11 shows a photograph of the system arriving at the site. AdEdge and ATSI were on-site
for the system installation during the week of November 14, 2005. ATSI performed the installation and
shakedown of the Carbon Dioxide Gas Flow Control System for pH adjustment. Meanwhile, AdEdge
and the local operator performed the arsenic treatment system installation and shakedown work, which
included hydraulic testing, media loading (by hand), and media backwash. The system officially went
online and was put into regular service on December 7, 2005. Battelle was on-site on December 8 and 9,
25
-------
Figure 4-10. Maintenance Shop Building
Figure 4-11. System Being Delivered to Site
26
-------
2005, to inspect the system and provide training to the operator for sampling and data collection. As a
result of the system inspections, a punch-list of items was identified, some of which were quickly
resolved and did not affect system operations or data collection, although several problems related to the
pH adjustment system and the media vessel flow meters surfaced throughout the six-month study period.
Table 4-6 summarizes the items identified and corrective actions taken. In addition, these problems are
discussed in detail in Section 4.4.3.
Table 4-6. System Punch-List/Operational Issues
Item
No.
1
2
3
4
5
6
7
Punch-List/
Operational Issues
Well pump hour meter not provided
Leak in CO2 supply system
Flow totalizer for Vessels A and B
reset to zero
In-line pH probe reporting pH >8
Malfunctioning proportioning valve
restricted CO2 injection
In-line pH probe not reporting pH
reading
Flow totalizer for Vessels A and B
reset to zero
Corrective Action(s) Taken
Installed hour meter for well pump
Checked and tightened all connections
and fittings
Vendor notified
No corrective action taken
Flushed pH probe by-pass line and
increased flowrate through by -pass line
Replaced proportioning valve
Replaced pH probe
Vendor notified
Problem likely due to a programming
error; a flash memory card with
necessary programming updates to be
provided by vendor
Resolution
Date
01/09/06
01/11/06
01/12/06
03/13/06
04/24/06
05/30/06
02/22/06
05/23/06
TBD
4.4
TBD = to be determined
System Operation
4.4.1 Operational Parameters. The operational parameters for the first six months of system
operation were tabulated and are attached as Appendix A. Key parameters are summarized in Table 4-7.
From December 8, 2005, through June 9, 2006, the system operated for approximately 787 hr. Because
the well pump hour-meter was not installed during the first 32 days of operation, the average daily
operational time and flowrate over the last 151 days of operation were used to estimate approximate
overall operational time. This cumulative operating time represents a use rate of approximately 18%
during the first six months of system operation. The system typically operated for a period of
approximately 4.3 hr/day.
Flowrates of the system were tracked by instantaneous flowrate readings from the electromagnetic flow
meter/totalizer on each adsorption vessel, and calculated flowrate values based on hour meter and flow
totalizer readings from the same electromagnetic flow meters/totalizers and a preexisting positive
displacement type master totalizer installed at the wellhead. As shown in Figure 4-12, the instantaneous
readings for Vessels A and B, denoted by "" and "A," respectively, were significantly higher than the
corresponding calculated values, denoted by "n" and "A," respectively, with an average value of 52 gpm
for the instantaneous readings and 44 gpm for the calculated values. In addition, the calculated values
based on the electromagnetic flow meters/totalizers were significantly higher than those based on the
master totalizer (denoted by "*" in the figure). Although the results produced by the master totalizer were
closer to the design flowrate of 40 gpm, the calculated values by the electromagnetic flow meters/
totalizers were used as system flowrates. This was based on the belief that readings from the
27
-------
Table 4-7. Summary of APU-50LL-CS-S-2-AVH System Operation
Operational Parameter
Duration
Cumulative Operating Time (hr)
Average Daily Operating Time (hr)
Throughput (gal)
Bed Volumes (BV)(a)
Average (Range) of Flowrate (gpm)
Average (Range) of EBCT per Vessel (min)(a)
Average (Range) of EBCT for System (min)(a)
Average (Range) of Inlet Pressure (psi)
Average (Range) of Outlet Pressure (psi)
Average (Range) of Ap across System (psi)
Average (Range) of Ap across Vessel A (psi)
Average (Range) of Ap across Vessel B (psi)
Value/Condition
12/08/05-06/09/06
787
4.3
2,070,000
12,625
44 (39-53)
3.7(3.1-4.2)
7.5 (6.2-8.4)
41.2 (34-60)
30.1(24-50)
11.2(8-14)
3.2 (1-6)
4.3 (0-6)
(a) Calculated based on 22 ft3 of media in one vessel.
factory-calibrated electromagnetic flow meters/totalizers were more reliable than those from the master
totalizer, for which little information was available regarding its accuracy and installation specifications.
Therefore, for performance evaluation purposes, the data produced by the electromagnetic flow
meter/totalizer on the lag vessel was used to determine system flowrates and total volume treated.
Figure 4-12 also identifies flowrate data that were not consistent with normal operations and caused by an
unintentional resetting of the electromagnetic flow meters/totalizers on two separate occasions. Detailed
discussions regarding the resetting of the totalizers are provided in Section 4.4.3.
During the first six months, the system treated approximately 2,070,000 gal of water based on the
totalizer readings from the lag vessel. The amount of water treated was equivalent to approximately
12,600 BV based on the 22 ft3 of media in one vessel or 6,300 BV based on the 44 ft3 of media in both
vessels. Flowrates to the system ranged from 39 to 53 gpm and averaged 44 gpm. The average system
flowrate was 10% higher than the 40-gpm design value (Table 4-4), which was derived from the 40-gpm
supply well flowrate based on the pump curve provided by the facility. Based on the flows to the system,
the EBCT for the lag vessel varied from 3.1 to 4.2 min and averaged 3.7 min, which was 11% lower than
the design EBCT of 4.1 min.
The APU system pressures were monitored at the system inlet and outlet and between the lead and lag
vessels. The average pressure differential (Ap) across the treatment train, lead vessel, and lag vessel for
the first month of system operation was 10, 3, and 4 psi, respectively. By the end of the first six months
of system operation, the average Ap across the treatment train, lead vessel, and lag vessel were 11,3, and
4 psi, respectively. As such, no pressure increase was observed after 787 hr of system operation or after
treating approximately 2,070,500 gal of water. Noticeable pressure spikes were observed during the last
four months of system operation; however, none of these spikes caused significant increase in Ap across
the treatment train or adsorption vessels. As a result, no media backwash was performed during the first
six months of system operation. Figures 4-13 shows total and differential pressures for each vessel and
the system.
4.4.2 Residual Management. Because neither backwash nor media replacement was performed
during the first six months of system operation, no residual was produced in this reporting period.
28
-------
55 -
50-
45-
S 35 -
2
1
"- 30 H
20 -
15-
-Totalizer Average Flowrate
-Vessel A (Lead) Instantaneous Flowrate
-Vessel A (Lead) Average Flowrate
Vessel B (Lag) Instantaneous Flowrate
Vessel B (Lag) Average Flowrate
10
12/09/05 12/29/05 01/18/06 02/07/06 02/27/06 03/19/06 04/08/06 04/28/06 05/18/06 06/07/06
Date
Figure 4-12. System Instantaneous and Calculated Flowrates
70
50 -
-System Inlet Pressure
-Vessel A (Lead) Inlet Pressure
Vessel B (Lag) Inlet Pressure
-System Outlet Pressure
-Vessel A (Lead) Outlet Pressure
Vessel B (Lag) Outlet Pressure
System Differential Pressure (calculated)
Vessel A (Lead) Differential Pressure (reading;
Vessel B (Lag) Differential Pressure (reading;
12/09/05 12/29/05 01/18/06 02/07/06 02/27/06 03/19/06 04/08/06 04/28/06 05/18/06 06/07/06
Date
Figure 4-13. System Operational Pressures
29
-------
4.4.3 System/Operation Reliability and Simplicity. Operational irregularities experienced during
the first six months of the demonstration study were related to the pH adjustment system and the media
vessel flow meters/totalizers.
As described in Section 4.2, pH adjustment using a CO2 injection module is a process component. On
January 11, 2006, leaks were detected in the CO2 system, resulting in an additional change-out of a CO2
gas cylinder during the sixth week of the system operations. The leaks were tracked to the supply line
where loose fittings were discovered. During the week of March 13, 2006 (the 15th week of operation),
the proportional flow control valve that regulates the CO2 injection rate began operating improperly. The
failure caused the pH levels to remain higher than desired. Based on in-line probe readings, the pH values
averaged 7.8 during that week of operation. The pH control system was switched to operate in the
manual mode until the control valve was replaced on April 24, 2006. On May 3, 2006, the digital screen
on the JUMO pH/PID controller was not displaying the pH measurement. A replacement in-line pH
probe was installed on May 30, 2006, which restored the digital display on the JUMO pFi/PID controller.
The CO2 system failed to consistently adjust the pH to the target value of 7.0, with the pH values
measured by the in-line pH probe varying between 6.5 and 8.2.
On two separate occasions, January 12, 2006, and May 23, 2006, both electromagnetic flow
meters/totalizers malfunctioned, causing the meters to reset and begin totalizing from zero. The failure
was thought to have been caused by a programming error. A flash memory card with the necessary
programming updates was provided by the vendor; and on June 15, 2006, the operator integrated the
upgrades to prevent future reoccurrences of the problems.
Due to the malfunction of the electromagnetic flow meters/totalizers, an effort was made to evaluate their
accuracy by comparing cumulative totalizer readings from each electromagnetic flow meter/totalizer.
The cumulative totalizer readings from the electromagnetic flow meters/totalizers on the lead and lag
vessels were 2,086,700 and 2,070,000, respectively. Based on those cumulative measurements, a
variation of less than 1% was measured through the first six-month operational period.
The system O&M and operator skill requirements are discussed below in relation to pre- and post-
treatment requirements, levels of system automation, operator skill requirements, preventive maintenance
activities, and frequency of chemical/media handling and inventory requirements.
Pre- and Post-Treatment Requirements. Two forms of pre-treatment were required at the Webb CISD
site, i.e., pH adjustment and prechlorination. CO2 was used to lower the pH value of raw water from as
high as 8.2 (Table 4-1) to a target value of 7.0 in order to maintain effective adsorption by the AD-33
media. The CO2 injection point and in-line pH probe used to monitor and control the adjusted pH level,
were installed upstream of the prechlorination injection point. O&M of the pH adjustment system
required routine system pressure checks and regular changesout of the CO2 supply bottles as pressure was
depleted. The operator also recorded a daily pH reading from the in-line probe and performed calibration
of the pH probe, as needed. The use of CO2 for pH adjustment also required additional safety training and
awareness for the operator, due to the added hazards.
For prechlorination, the existing chlorination system was upgraded and installed inside the maintenance
building, which housed the APU-50LL-CS-S-2-AVH system. The upgraded chlorination system, as
discussed in Section 4.2 and shown on Figure 4-8, utilized a 10%NaOCl solution to reach a target
residual level of 1.2 mg/L (as C12). The upgraded chlorination system did not require maintenance or
skills other than those required by the previous system. The operator monitored chlorine tank levels,
consumption rates, and residual chlorine levels.
30
-------
System Automation. The system was fitted with automated controls that would allow for the backwash
cycle to be controlled automatically. The system is also equipped with an automated Carbon Dioxide Gas
Flow Control System, which includes a liquid CO2 supply assembly, an automatic pH control panel, a
CO2 membrane module and an in-line pH probe located downstream of the membrane module. Each
media vessel is equipped with five electrically actuated butterfly valves which are controlled by a Square
D Telemechanique PLC with a Magelis G2220 color touch interface screen. Although not automated, the
system is also equipped with six isolation ball valves to allow for reversible lead lag configuration.
The automated portion of the system did not require regular O&M; however operator awareness and an
ability to detect unusual system measurements were necessary when troubleshooting system automation
failures. The equipment vendor provided hands-on training and a supplemental operations manual to the
operator.
Operator Skill Requirements. The skill requirements to operate the system demand a higher level of
awareness and attention than the previous system. The system offers increased operational flexibility,
which, in turn, requires increased monitoring of system parameters. The operator's knowledge of the
system limitations and typical operational parameters is key in achieving system performance objectives.
The operator was on-site typically five times a week and spent approximately 20 min each day to perform
visual inspections and record the system operating parameters on the daily log sheets. The basis for the
operator skills began with on-site training and a thorough review of the system operations manual;
however, increased knowledge and invaluable system troubleshooting skills are gained through hands on
operational experience.
TCEQ requires that the operator of the treatment system hold at least a Class D TCEQ waterworks
operator license. The TCEQ public water system operator certifications are classified by Class D through
A. Licensing eligibility requirements are based on education, experience, and related training. The
minimum requirements for a Class D license are high school graduate or GED and 20 hr of related
training. Licensing requirements incrementally increase with each licensing level, with Class A being the
highest requiring the most education, experience, and training.
Preventive Maintenance Activities. Preventive maintenance tasks included periodic checks of
flowmeters and pressure gauges and inspection of system piping and valves. Checking the CO2 cylinders
and supply lines for leaks and adequate pressure and calibrating the in-line pH probe also were
performed. Typically, the operator performed these duties while on-site for routine activities.
Chemical/Media Handling and Inventory Requirements. NaOCl was used for prechlorination; the
operator ordered chemicals as done prior to the installation of the APU-50LL-CS-S-2-AVH system. CO2
used for pH adjustment was ordered on an as needed basis. Typically, four 50-lb cylinders were used per
month. As the CO2 cylinders were delivered to the site by the CO2 supplier, empty cylinders were
returned for reuse.
4.5 System Performance
The performance of the system was evaluated based on analyses of water samples collected from raw and
treated water and distribution system.
4.5.1 Treatment Plant Sampling. Table 4-8 summarizes the analytical results of arsenic, iron,
and manganese concentrations measured at the four sampling locations across the treatment train.
Table 4-9 summarizes the results of other water quality parameters. Appendix B contains a complete set
of analytical results through the first six months of operation. The results of the water samples collected
throughout the treatment plant are discussed below.
31
-------
Table 4-8. Summary of Analytical Results for Arsenic, Iron, and Manganese
Parameter
As
(total)
As
(soluble)
As
(paniculate)
As (III)
As(V)
Fe
(total)
Fe
(soluble)
Mn
(total)
Mn
(soluble)
Sampling
Location
IN
AP
TA
TB
IN
AP
TA
TB
IN
AP
TA
TB
IN
AP
TA
TB
IN
AP
TA
TB
IN
AP
TA
TB
IN
AP
TA
TB
IN
AP
TA
TB
IN
AP
TA
TB
Unit
ug/L
ug/L
tig/L
ug/L
tig/L
ug/L
ug/L
tig/L
ug/L
tig/L
ug/L
ug/L
tig/L
ug/L
tig/L
ug/L
ug/L
tig/L
ug/L
ug/L
tig/L
ug/L
tig/L
ug/L
ug/L
tig/L
ug/L
tig/L
ug/L
ug/L
tig/L
ug/L
tig/L
ug/L
ug/L
ug/L
Sample
Count
15
15
15
15
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
15
15
15
15
7
7
7
7
15
15
15
15
7
7
7
7
Concentration
Minimum
46.2
50.2
Maximum
62.9
64.4
Average
56.9
58.6
Standard
Deviation
4.6
4.3
(a)
51.5
50.8
56.5
61.0
53.4
53.6
1.7
3.6
(a)
<0.1
1.2
8.6
8.9
4.9
6.3
3.7
2.7
(a)
35.8
0.5
40.8
3.3
38.5
1.7
2.1
1.1
(a)
13.2
47.7
17.3
57.7
14.9
51.9
1.4
3.3
(a)
<25
<25
<25
<25
<25
<25
<25
<25
2.6
2.9
0.1
<0.1
2.6
3.0
<0.1
<0.1
28.8
<25
<25
<25
<25
<25
<25
<25
5.4
4.6
1.8
5.0
4.2
3.5
1.6
5.1
<25
<25
<25
<25
<25
<25
<25
<25
3.9
3.5
0.3
0.5
3.6
3.2
0.3
0.8
6.0
2.4
0.0
0.0
0.0
0.0
0.0
0.0
0.8
0.6
0.5
1.3
0.5
0.2
0.6
1.9
One-half of detection limit used for samples with concentrations less than detection limit for calculations.
(a) Statistics not provided; see Figure 4-15 for arsenic breakthrough curves.
32
-------
Table 4-9. Summary of Water Quality Parameter Sampling Results
Parameter
Alkalinity
(as CaCO3)
Fluoride
Sulfate
Nitrate
(asN)
Phosphorus
(as PO4)
Silica
(as SiO2)
Turbidity
pH
Temperature
Dissolved
Oxygen
Sampling
Location
IN
AP
TA
TB
IN
AP
TA
TB
IN
AP
TA
TB
IN
AP
TA
TB
IN
AP
TA
TB
IN
AP
TA
TB
IN
AP
TA
TB
IN
AP
TA
TB
IN
AP
TA
TB
IN
AP
TA
TB
Unit
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
NTU
NTU
NTU
NTU
s.u.
s.u.
s.u.
s.u.
°c
°c
°c
°c
mg/L
mg/L
mg/L
mg/L
Sample
Count
15
15
15
15
7
7
7
7
7
7
7
7
7
7
7
7
14
14
14
14
15
15
15
15
15
15
15
15
12
12
12
12
12
12
12
12
12
12
12
12
Concentration
Minimum
305
306
294
312
0.5
0.6
0.5
0.4
104
104
98
100
0.05
O.05
0.05
O.05
O.01
0.01
O.01
0.01
40.6
40.2
13.5
1.7
0.1
0.1
O.I
0.1
8.0
7.1
7.1
7.1
21.3
21.2
21.4
21.4
1.1
1.4
0.9
1.3
Maximum
334
344
342
352
0.9
1.2
1.5
1.0
111
112
114
136
0.05
O.05
0.05
O.05
0.03
0.06
O.03
0.03
43.9
43.5
44.4
45.3
1.1
1.5
1.1
2.0
8.3
8.1
7.6
7.5
27.1
27.2
27.5
27.4
3.1
4.1
3.4
3.5
Average
320
322
321
325
0.6
0.8
0.8
0.7
106
107
108
111
0.05
O.05
0.05
O.05
0.01
0.01
0.01
0.01
41.9
41.9
38.4
35.4
0.5
0.4
0.4
0.5
8.2
7.4
7.3
7.3
25.6
25.7
25.6
25.4
1.7
2.0
1.8
2.0
Standard
Deviation
9
10
12
12
0.2
0.2
0.3
0.2
2.4
3.6
5.9
11.9
0.00
0.00
0.00
0.00
0.01
0.01
0.01
0.01
1.1
1.0
8.3
13.1
0.3
0.4
0.3
0.5
0.1
0.3
0.1
0.1
1.7
1.9
1.9
2.0
0.6
0.7
0.6
0.6
33
-------
Table 4-9. Summary of Water Quality Parameter Sampling Results (Continued)
Parameter
ORP
Free
Chlorine
(as C12)
Total
Chlorine
(as C12)
Total
Hardness
(as CaCO3)
Ca
Hardness
(as CaCO3)
Mg
Hardness
(as CaCO3)
Sampling
Location
IN
AP
TA
TB
AP
TA
TB
AP
TA
TB
IN
AP
TA
TB
IN
AP
TA
TB
IN
AP
TA
TB
Unit
mV
mV
mV
mV
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
Sample
Count
12
12
12
12
12
-
10
11
-
10
7
7
7
7
7
7
7
7
7
7
7
7
Concentration
Minimum
234
309
387
371
0.5
-
0.6
0.7
-
0.7
17.1
19.1
11.6
15.8
11.3
11.9
7.6
9.9
5.8
5.3
4.0
3.3
Maximum
378
679
690
700
2.0
-
1.7
2.1
-
2.1
30.1
30.0
33.0
47.2
22.7
22.8
25.1
29.4
9.0
9.1
10.7
17.9
Average
280
535
594
608
1.0
-
1.1
1.3
-
1.2
22.8
23.0
24.3
26.3
15.5
15.9
16.7
17.9
7.3
7.1
7.7
8.4
Standard
Deviation
44.1
89.0
85.1
104
0.5
-
0.4
0.4
-
0.5
4.9
4.7
6.9
10.7
4.4
4.2
5.7
6.8
1.0
1.2
2.0
4.5
One-half of detection limit used for samples with concentrations less than detection limit for
calculations.
Arsenic. Water samples were collected on 15 occasions (including one duplicate sampling event), with
field speciation performed during seven of the 15 occasions from IN, AP, TA, and TB sampling locations.
Figure 4-14 contains four bar charts showing the concentrations of particulate arsenic, As(III), and As(V)
at four locations for each of the seven speciation events.
Total arsenic concentrations in raw water ranged from 46.2 to 62.9 |o,g/L and averaged 56.9 |o,g/L. As(III)
was the predominating species, ranging from 35.8 to 40.8 (ig/L and averaging 38.5 |o,g/L. As(V) also was
present in source water, ranging from 13.2 to 17.3 |o,g/L and averaged 14.9 |o,g/L. Particulate As
concentrations were lower, ranging from <0.1 to 8.6 |o,g/L and averaging 4.9 (ig/L. The arsenic
concentrations measured were consistent with those collected previously during source water sampling
(Table 4-1).
Chlorination effectively oxidized As(III) to As(V) prior to the adsorption vessels. After chlorination the
average As(III) and As(V) concentrations were 1.7 and 51.9 |og/L, respectively. Free and total chlorine
were monitored at the AP and TB sampling locations to ensure that the target chlorine residual levels
were properly maintained for disinfection purposes. Free chlorine levels at the AP location ranged from
0.5 to 2.0 mg/L (as C12) and averaged 1.0 mg/L (as C12); total chlorine levels ranged from 0.7 to 2.1 mg/L
(as C12) and averaged 1.3 mg/L (as C12) (Table 4-9). The residual chlorine levels measured at the TB
34
-------
Arsenic Species at Wellhead (IN)
Arsenic Species after pH Adjustment and Chlorination (AP)
70
60
As Concentration (fig/L)
D O O O O O
As (participate)
As (III)
OAs(V)
-
-
_
70-
60-
As Concentration (^g/L)
D 0 0 0 0 0
As (paniculate)
As (III)
OAs(V)
12/8/2005 1/5/2006 2/1/2006 3/14/2006 4/11/2006 5/9/2006 6/6/2006 12/8/2005
Date
1/5/2006 2/1/2006 3/14/2006 4/11/2006 5/9/2006 6/6/2006
Date
Arsenic Species after Vessel A(TA)
Arsenic Speciation after Vessel B (TB)
12/8/2005 1/5/2001
4/11/2006 5/9/2006 6/6/2006
12/8/2005 115/2006 2/112006
3/14/2006
Date
4/1112006 5/9/2006 6/6/2006
Figure 4-14. Concentrations of Various Arsenic Species at IN, AP, TA, and TB Sampling Locations
-------
location were similar to those measured at the AP location, indicating little or no chlorine consumption
through the AD-33 vessels.
The total arsenic breakthrough curves shown in Figure 4-15 indicate that the lead vessel removed the
majority of arsenic, existing predominately as As(V), following chlorination. Through the end of the first
six months of system operation, the system has treated approximately 2,070,000 gal of water, equivalent
to 12,600 BV based on the 22 ft3 of media in one adsorption vessel or 6,300 BV based on the 44 ft3 of
media in both vessels. Arsenic breakthrough, based on laboratory analysis of samples collected on June
6, 2006 (approximately 12,100 BV) was 1.1 and 0.8 (ig/L for the lead and lag vessels, respectively. The
12,600 BV of throughput represents approximately 27% of the media capacity estimated to be 46,900 BV
by the vendor (Table 4-4).
The average total arsenic breakthrough was significantly higher in both the lead and lag vessels during the
first three months of system operation. For the eight samples collected from December 8, 2005, through
February 28, 2006, the average total arsenic concentrations following the lead and lag vessels were 3.4
and 3.3 |og/L, respectively. In contrast, for the seven samples collected from March 14, 2006 through
June 6, 2006, the average total arsenic concentrations following the lead and lag vessels were 1.3 and 0.9
Hg/L, respectively. Further, laboratory results from two of the first four sampling events (December 8,
2005 and January 17, 2006) showed higher total arsenic concentrations following the lag vessel than
following the lead vessel. System operations are ongoing and the media in the lead vessel will be
recharged once it is completely exhausted or the breakthrough of the lag vessel approaches 10 (ig/L,
whichever comes first.
80 i
70 -
60
50
40 -
30
20
10 -
-At Wellhead (IN)
-After pH Adjustment and Chlorination (AP)
-After Vessel A (TA)
-After Vessel B (TB)
6 8
Bed Volumes (103)
10
12
14
Figure 4-15. Total Arsenic Breakthrough Curves
(Based on 22ft3 of Media in Each Vessel)
36
-------
Competing Anions. Phosphate and silica, which can influence arsenic adsorption, were measured at the
four sampling locations across the treatment train throughout the first six months of the demonstration
study. Phosphorus concentrations were low ranging from <0.01 to 0.06 mg/L (as PO4). Silica
concentrations ranged from 1.7 to 45.3 mg/L. Significant silica concentration reductions (96%, 85%, and
24%, respectively) were noted in samples collected during the first three weeks of operation. Following
the third week of operation the maximum silica concentration reduction was less then 10%. Figure 4-16
represents the silica breakthrough curves from the treatment train.
50
45
40
35
25
o
0 20
ro
15
10
5
At the Wellhead (IN)
After pH Adjustment and Chlorination (AP)
After Lead Vessel A (TA)
After Lag Vessel (TB)
10
12
14
Bed Volume (10
Figure 4-16. Silica (as SiO2) Breakthrough Curves
(Based on 22ft3 of Media in Each Vessel)
Iron and Manganese. Total iron concentrations in raw water were below its detection limit of 25 Lig/L
(Table 4-8). Total iron concentrations across the treatment train also were below the detection limit,
except for two occasions. One total iron concentration was detected on January 17, 2006, at 28.8 Lig/L
and the second on May 23, 2006, at 28.4 Lig/L, both at the IN location. Total manganese levels ranged
from 2.6 to 5.4 Lig/L and averaged 3.9 Lig/L in raw water. Total manganese concentrations in the effluent
from the adsorption vessels showed a slight increasing trend, with <1.8 Lig/L measured after the lead
vessel and <5.0 Lig/L after the lag vessel. Soluble manganese concentrations were similar for the four
sample locations averaging 3.6 Lig/L, 3.2 Lig/L, 0.3 Lig/L and 0.8 Lig/L for IN, AP, TA, and TB,
respectively.
Other Water Quality Parameters. As shown in Table 4-9, pH values of raw water measured at the IN
sample location varied from 8.0 to 8.3 and averaged 8.2. The pH values, following CO2 injection for pH
adjustment, at the AP location, varied from 7.1 to 8.1 and averaging 7.4. The average adjusted pH value
37
-------
of 7.0, at the AP location prior to the adsorption media, is desirable for adsorptive media which, in
general, have a greater arsenic removal capacity when treating water at near neutral pH values. Figure 4-
17 presents the pH values measured throughout the treatment train.
On two separate occasions on January 5 and 17, 2006, the pH values were not reduced following CO2
injection, as indicated by the second and third sets of IN (denoted by "*") and AP data points (denoted by
"") shown in Figure 4-17. The pH values measured, with a portable VWR meter, at the IN sampling
location were 8.1 and 8.0, respectively and the pH values measured at the AP location also were 8.1 and
8.0, respectively. In contrast, the pH values (denoted by "*") measured at the AP location by the in-line
probe were approximately 1.0 unit less than those measured at the same location by the VWR meter. pH
measurements prior to and following these two isolated events suggest that pH values measured by the
VWR meter at the AP location on January 5 and 17, 2006, most likely were the result of instrument or
measurement errors.
8.5
8.0
7.5
7.0
6.5
6.0
,002 proportioning valve malfunctioned.
CO2 system operated in
manual mode until -
proportioning valve was
replaced.
In-line pH probe failure.
--At the Wellhead (IN)
After pH Adjustment and Chlorination (AP)
After Lead Vessel A (TA)
-K- After Lag Vessel B (TB)
IK In-line pH Probe After Adjustment
10
12
Bed Volume (103)
Figure 4-17. pH Values Measured throughout Treatment Train
(Based on 22ft3 of Media in Each Vessel)
Throughout the first six month operational period, pH values reported by the VWR meter were
approximately 0.4 pH units (on average) higher than those reported by the in-line pH probe; however a
common trend is obvious, as illustrated in Figure 4-17. A possible explanation for the variations might be
degassing of dissolved CO2 when the water samples were collected from the AP location, thus resulting in
elevated readings measured by the portable VWR meter.
38
-------
Alkalinity, reported as CaCO3, ranged from 294 to 352 mg/L. The results indicated that the adsorptive
media did not affect the amount of alkalinity in the water after treatment. The treatment plant samples
were analyzed for hardness only on speciation weeks. Total hardness ranged from 11.6 to 47.2 mg/L (as
CaCO3), and also remained constant throughout the treatment train. Sulfate concentrations ranged from
98 to 136 mg/L, and remained constant throughout the treatment train. Fluoride results ranged from 0.4
to 1.5 mg/L in all samples. The results indicated that the adsorptive media did not affect the amount of
fluoride in the water after treatment. DO levels ranged from 0.9 to 4.1 mg/L and averaged 1.9 mg/L.
ORP readings averaged 280 mV in raw water, but increased to an average of 579 mV after chlorination.
4.5.2 Backwash Water Sampling. Backwash was not performed during the first six-month
operational period; however, a backwash is anticipated to occur during the second six-month operation
period.
4.5.3 Distribution System Water Sampling. Prior to the installation/operation of the treatment
system, baseline distribution system water samples were collected from the middle school, high school,
and cafeteria on June 15, July 21, August 24, and September 19, 2005. Following the installation of the
treatment system, distribution system water sampling continued on a monthly basis at the same three
locations, with samples collected on January 5, February 1, March 14, April 11, May 9, and June 6, 2006.
The results of the distribution system sampling are summarized on Table 4-10.
The most noticeable change in the distribution system samples since the system began operation was a
decrease in arsenic concentration. Baseline arsenic concentrations ranged from 49.6 to 99.9 (ig/L and
averaged 68.7 (ig/L for all three locations. After the performance evaluation began, arsenic
concentrations were reduced to <5.0 (ig/L (or 2.4 (ig/L on average), which were similar to the arsenic
concentrations in the system effluent.
Lead concentrations ranged from 0.3 to 2.3 (ig/L, with none of the samples exceeding the action level of
15 (ig/L. Copper concentrations ranged from 6.5 to 565 (ig/L, with no samples exceeding the 1,300 (ig/L
action level. Measured pH values ranged from 7.6 to 8.1 and averaged 7.8, which were 1A of a pH unit
higher than the avearge pH value immediately after the adsorption vessels. Compared to an average value
of 8.2 before the treatment sytem became operational, the lowered pH values did not appear to have
affected the Pb or Cu concentrations in the distribution system.
Alkalinity levels ranged from 305 to 348 mg/L (as CaCO3). Iron was not detected in any of the samples;
manganese concentrations ranged from <0.1 to 2.4 (ig/L. The arsenic treatment system did not seem to
affect these water quality parameters in the distribution system.
4.6 System Cost
System cost is evaluated based on the capital cost per gpm (or gpd) of the design capacity and the O&M
cost per 1,000 gal of water treated. The capital cost includes the cost for equipment, site engineering, and
installation. The O&M cost includes the cost for media replacement and disposal, electrical power use,
and labor.
4.6.1 Capital Cost. The capital investment for equipment, site engineering, and installation of the
Bruni treatment system was $138,642 (see Table 4-11). The equipment cost was $94,662 (or 68% of the
total capital investment), which included $77,082 for the skid-mounted APU-50LL-CS-S-2-AVH unit,
$13,200 for the AD-33 media ($300/ft3 or $8.57/lb to fill two vessels), $2,580 for shipping, and $1,800
for labor.
39
-------
Table 4-10. Distribution System Sampling Results
BJ)
"e-1
a z
Ł H
BL1
BL2
BL3
BL4
1
2
3
4
5
6
Location
BJ)
i 'S
m Q
06/15/05
07/21/05
08/24/05
09/19/05
01/05/06
02/01/06
03/14/06
04/1 1/06
05/09/06
06/06/06
Middle School
1
H
S
"a
a.
3s G
14.5
15.0
15.6
13.0
14.8
15.0
15.0
15.3
10.8
14.7
S3
e.
8.3
8.1
8.2
8.1
7.7
7.9
7.6
7.9
7.6
7.8
^
'"§
^g
<<
334
330
317
330
343
312
310
323
326
305
52.0
54.4
83.1
49.6
2.1
3.4
1.4
3.1
1.3
1.0
'
<25
70.9
<25
<25
<25
<25
<25
<25
<25
<25
a
§
1.9
13.5
2.2
3.3
<0.1
0.4
0.8
0.3
0.3
0.1
1.9
1.2
0.3
1.9
0.8
0.3
0.9
1.0
0.4
1.0
a
O
114
7.3
23.9
40.1
209
119
278
113
86.3
234
High School
1
H
S
=
a
Ť sŤ
x G
14.8
15.3
15.7
13.3
14.5
15.2
15.2
15.0
14.8
14.8
S3
e.
8.3
8.2
8.2
8.1
7.7
8.1
7.8
7.9
7.7
7.7
^
a
^g
<<
330
330
321
330
348
312
314
311
331
309
53.0
79.2
85.8
51.4
3.5
4.4
2.0
5.0
2.0
2.0
'
<25
32.8
<25
<25
<25
<25
<25
<25
<25
<25
a
§
1.2
6.0
1.2
1.5
2.4
0.2
0.8
0.6
0.7
1.9
2.3
2.0
0.9
1.5
2.3
0.8
1.8
1.6
0.7
0.7
a
O
115
44.8
72.5
77.3
308
214
259
337
164
565
Cafeteria
1
H
S
=
a
3 ^
S G
15.0
15.5
15.8
13.5
15.0
15.0
15.3
15.2
14.7
14.6
S3
e.
8.3
8.1
8.2
8.1
7.6
8.1
7.8
7.9
7.7
8.0
^
a
^g
<<
330
330
321
326
334
312
318
315
322
322
77.7
53.3
84.7
99.9
1.4
3.8
1.3
3.6
1.2
0.7
'
<25
<25
<25
<25
<25
<25
<25
<25
<25
<25
a
§
5.9
6.8
2.1
2.4
<0.1
0.6
0.9
0.3
0.1
0.2
11.5
2.9
0.3
1.9
0.5
0.6
0.9
0.8
0.4
0.6
a
O
381
106
23.2
44.4
15.4
250
19.7
16.0
6.5
14.9
Lead action level =15 ng/L; copper action level =1.3 mg/L
Hg/L as unit for all analytes except for pH (S.U.) and alkalinity (mg/L [as CaCO3]).
BL = Baseline Sampling; NA = Not Available
-------
Table 4-11. Capital Investment Cost for APU-50LL-CS-S-2-AVH System
Description
Quantity
Cost
% of Capital
Investment
Equipment Cost
APU Skid-Mounted System (Unit)
AD-33Media(ft3)
Shipping
Vendor Labor
Equipment Total
1
44
$77,082
$13,200
$2,580
$1,800
$94,662
68
Engineering Cost
Vendor Labor/Travel
Subcontractor Labor/Travel
Engineering Total
$11,800
$12,500
$24,300
18
Installation Cost
Subcontractor Labor
Vendor Labor
Vendor/ Subcontractor Travel
Installation Total
Total Capital Investment
-
$12,574
$4,860
$2,246
$19,680
$138,642
14
100
The engineering cost included the cost for preparing three submittal packages for the exception request,
permit application, and supplemental information for the permit (see Section 4.3.1). The engineering cost
was $24,300, or 18% of the total capital investment.
The installation cost included the equipment and labor to unload and install the skid-mounted unit,
perform piping tie-ins and electrical work, load, and backwash the media, perform system shakedown and
startup, and conduct operator training. The installation cost was $19,680, or 14% of the total capital
investment.
The total capital cost of $138,642 was normalized to the system's rated capacity of 40 gpm (57,600 gpd),
which resulted in $3,466/gpm of design capacity ($2.41/gpd). The capital cost also was converted to an
annualized cost of $13,086/yr using a capital recovery factor (CRF) of 0.09439 based on a 7% interest
rate and a 20-year return period. Assuming that the system operated 24 hours a day, 7 days a week at the
system design flowrate of 40 gpm to produce 21,024,000 gal of water per year, the unit capital cost would
be $0.62/1,000 gal. Because the system operated an average of 4.3 hr/day at 44 gpm (see Table 4-7),
producing 2,070,000 gal of water during the six-month period, the unit capital cost increased to
$3.16/1,000 gal at this reduced rate of use.
4.6.2 Operation and Maintenance Cost. The O&M cost included the cost for such items as
media replacement and disposal, CO2 usage, electricity consumption, and labor (Table 4-12). Although
media replacement did not occur during the first six months of system operation, the media replacement
cost would represent the majority of the O&M cost and was estimated to be $11,190 to change out the
lead vessel. This media change-out cost would include the cost for media, underbedding, freight, labor,
travel, spent media analysis, and media disposal fee. This cost was used to estimate the media
replacement cost per 1,000 gal of water treated as a function of the projected lead vessel media run length
at the 10 |o,g/L arsenic breakthrough from the lag vessel (Figure 4-18).
The chemical cost associated with the operation of the treatment system included the cost for NaCIO for
prechlorination and CO2 gas for pH adjustment. NaCIO was already being used at the site prior to the
41
-------
installation of the APU unit for disinfection purposes prior to distribution. The presence of the APU
system did not affect the use rate of the sodium hypochlorite solution. Therefore, the incremental
chemical cost for chlorine was negligible. The 50-lb CO2 cylinder was replaced weekly during the first
six months of system operation. Each change-out costs $31.52 and includes the replacement and delivery
charges. The CO2 costs for the first six months of operation were calculated to be $828 or $0.40/1,000
gallons of water treated.
Comparison of electrical bills supplied by the utility prior to system installation and since startup did not
indicate a noticeable increase in power consumption. Therefore, electrical cost associated with operation
of the system was assumed to be negligible.
Under normal operating conditions, routine labor activities to operate and maintain the system consumed
20 min per day, 5 days per week, as noted in Section 4.4.3. Therefore, the estimated labor cost was
$0.41/1,000 gal of water treated.
Table 4-12. Operation and Maintenance Cost for APU-50LL-CS-S-2-AVH System
Cost Category
Volume Processed (gal)
Value
2,070,000
Assumptions
Through June 9, 2006
Media Replacement and Disposal Cost
Media Replacement ($)
Underbedding and Freight for
Media and Gravel Shipping ($)
Travel and per diem ($)
Vendor and Subcontractor Labor ($)
Media Disposal ($)
Subtotal
Media Replacement and Disposal
($/l,000 gal)
$6,600
$330
$1,000
$2,160
$1,100
$11,190
See Figure 4-18
$300/ft3 for 22 ft3 (one media
vessel)
Including spent media analysis
Based upon lead vessel media run
length at 10-|ag/L arsenic
breakthrough from lag vessel
CO 2 Usage
CO2 Gas ($/l,000 gal)
$0.40
Based on consumption of CO2 for
pH adjustment (50-lb bottles)
Electricity Cost
Electricity ($/l,000 gal)
$0.001
Electrical costs assumed negligible
Labor Cost
Average Weekly Labor (min)
Labor ($/l,000 gal)
Total O&M Cost/1,000 gal
100
$0.41
See Figure 4-18
20 mm/day
Labor rate = $19.50/hr
Based upon lead vessel media run
length at 10-|ag/L arsenic
breakthrough from lag vessel
42
-------
o
o
O&M cost
Media replacement cost
$0.50
$0.00
20
30 40 50 60 70
Media Working Capacity, Bed Volumes (xlOOO)
80
90
100
Note: One bed volume equals 22 ft (165 gal)
Figure 4-18. Media Replacement and Operation and Maintenance Cost
43
-------
5.0 REFERENCES
Battelle. 2004. Revised Quality Assurance Project Plan for Evaluation of Arsenic Removal Technology.
Prepared under Contract No. 68-C-00-185, Task Order No. 0029, for U.S. Environmental
Protection Agency, National Risk Management Research Laboratory, Cincinnati, OH.
Battelle. 2005. Final System Performance Evaluation Study Plan: U.S. EPA Demonstration of Arsenic
Removal Technology at the Webb Consolidated Independent School District in Bruni, Texas.
Prepared under Contract No. 68-C-00-185, Task Order No. 0029 for U.S. Environmental
Protection Agency, National Risk Management Research Laboratory, Cincinnati, OH.
Chen, A.S.C., L. Wang, J. Oxenham, and W. Condit. 2004. Capital Costs of Arsenic Removal
Technologies: U.S. EPA Arsenic Removal Technology Demonstration Program Round 1.
EPA/600/R-04/201. U.S. Environmental Protection Agency, National Risk Management
Research Laboratory, Cincinnati, OH.
Edwards, M., S. Patel, L. McNeill, H. Chen, M. Frey, A.D. Eaton, R.C. Antweiler, and H.E. Taylor.
1998. "Considerations in As Analysis and Speciation." J. AWWA, 90(^:103-113.
EPA. 2001. National Primary Drinking Water Regulations: Arsenic and Clarifications to Compliance
and New Source Contaminants Monitoring. Fed. Register, 40 CFR Parts 9, 141, and 142.
EPA. 2002. Lead and Copper Monitoring and Reporting Guidance for Public Water Systems.
EPA/816/R-02/009. U.S. Environmental Protection Agency, Office of Water, Washington, DC.
EPA. 2003. Minor Clarification of the National Primary Drinking Water Regulation for Arsenic.
Federal Register, 40 CFR Part 141.
Wang, L., W. Condit, and A. Chen. 2004. Technology Selection and System Design: U.S. EPA Arsenic
Removal Technology Demonstration Program Round 1. EPA/600/R-05/001. U.S.
Environmental Protection Agency, National Risk Management Research Laboratory, Cincinnati,
OH.
44
-------
APPENDIX A
OPERATIONAL DATA
-------
Table A-l. EPA Arsenic Demonstration Project at Bruni, TX - Daily System Operation Log Sheet
Week No.
1
2
3
4
5
6
7
8
9
10
11
Day of
Week
Thu
Fri
Mon
Tue
Wed
Thu
Fri
Mon
Tue
Wed
Thu
Fri
Mon
Tue
Wed
Thu
Fri
Mon
Tue
Wed
Thu
Fri
Mon
Tue
Wed
Thu
Fri
Mon
Tue
Wed
Thu
Fri
Mon
Tue
Wed
Thu
Fri
Mon
Tue
Wed
Thu
Fri
Mon
Tue
Wed
Thu
Fri
Mon
Tue
Wed
Thu
Fri
Date
12/08/05
12/09/05
12/12/05
12/13/05
12/14/05
12/15/05
12/16/05
12/19/05
12/20/05
12/21/05
12/22/05
12/23/05
12/26/05
12/27/05
12/28/05
12/29/05
12/30/05
01/02/06
01/03/06
01/04/06
01/05/06
01/06/06
01/09/06
01/10/06
01/11/06
01/12/06
01/13/06
01/16/06
01/17/06
01/18/06
01/19/06
01/20/06
01/23/06
01/24/06
01/25/06
01/26/06
01/27/06
01/30/06
01/31/06
02/01/06
02/02/06
02/03/06
02/06/06
02/07/06
02/08/06
02/09/06
02/10/06
02/13/06
02/14/06
02/15/06
02/16/06
02/17/06
Well
Operational
Hours
hr
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
4.2
2.4
4.5
NA
10.9
5.0
4.4
4.9
2.7
6.6
2.9
3.4
2.4
3.9
4.7
10.5
8.4
6.6
5.6
13.6
3.4
3.0
2.5
2.2
4.8
1.5
2.0
2.9
5.6
Vessel A
Flowrate
gpm
NA
53
50
50
50
50
49
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
50
50
50
50
50
50
52
50
NA
52
50
51
51
51
NA
NA
51
52
51
51
51
52
51
52
51
51
52
52
50
52
52
51
51
50
Cumulative
Totalizer
gal
NA
23,794
35,319
38,069
48,075
51,866
57,415
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
92,686
96,835
103,668
116,084
131,789
142,134
148,763
6,614
NA
35,434
48,544
60,350
73,080
79,955
98,481
106,034
114,427
121,235
131,558
143,267
172,144
194,479
213,083
227,540
262,989
271,073
279,832
286,120
292,035
304,459
308,325
313,473
321,089
335,365
Usage
gal
NA
23,794
11,525
2,750
10,006
3,791
5,549
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
35,271
4,149
6,833
12,416
15,705
10,345
6,629
6,614
NA
28,820
13,110
11,806
12,730
6,875
18,526
7,553
8,393
6,808
10,323
11,709
28,877
22,335
18,604
14,457
35,449
8,084
8,759
6,288
5,915
12,424
3,866
5,148
7,616
14,276
Average
Flowrate
gpm
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
41
46
24
NA
44
44
45
43
42
NA
NA
41
47
44
42
46
44
47
43
43
40
49
42
45
43
43
43
44
42
Pressure
Differential
psi
NA
3.0
3.0
3.0
3.0
3.0
3.0
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
1.0
2.0
1.0
1.0
3.0
4.0
4.0
5.0
NA
5.0
5.0
4.0
5.0
4.0
NA
NA
3.0
3.0
4.0
5.0
5.0
4.0
5.0
5.0
4.0
4.0
4.0
5.0
5.0
5.0
4.0
1.0
2.0
2.0
Vessel B
Flowrate
gpm
NA
51
48
48
48
49
48
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
48
49
48
48
48
49
50
52
NA
53
51
52
51
52
NA
NA
53
53
53
52
52
53
53
53
51
51
53
53
51
53
53
52
52
52
Cumulative
Totalizer
gal
NA
19,174
30,304
32,962
42,634
46,290
51,661
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
85,630
89,621
96,210
108,229
123,309
133,247
139,601
6,727
NA
36,043
49,412
61,429
74,407
81,422
100,350
108,614
116,547
123,472
133,918
145,866
175,129
197,638
216,459
231,048
266,801
274,942
283,796
290,139
296,107
308,620
312,504
317,684
325,362
339,775
Usage
gal
NA
19,174
11,130
2,658
9,672
3,656
5,371
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
33,969
3,991
6,589
12,019
15,080
9,938
6,354
6,727
NA
29,316
13,369
12,017
12,978
7,015
18,928
8,264
7,933
6,925
10,446
11,948
29,263
22,509
18,821
14,589
35,753
8,141
8,854
6,343
5,968
12,513
3,884
5,180
7,678
14,413
Average
Flowrate
gpm
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
39
44
25
NA
45
45
46
44
43
48
47
39
48
45
42
46
45
48
43
44
40
49
42
45
43
43
43
44
43
Pressure
Differential
psi
NA
5.0
4.0
4.0
4.0
4.0
4.0
NA
NA
NA
NA
5.0
NA
NA
NA
NA
5.0
NA
4.0
4.0
4.0
4.0
5.0
5.0
5.0
5.0
5.0
5.0
5.0
5.0
5.0
5.0
NA
NA
5.0
5.0
5.0
5.0
5.0
5.0
5.0
5.0
5.0
5.0
5.0
5.0
5.0
5.0
5.0
5.0
5.0
5.0
System
Inlet Pressure
psi
NA
40
40
38
38
38
39
NA
NA
NA
NA
40
NA
NA
NA
NA
40
NA
40
36
36
38
38
36
38
38
40
42
38
38
38
38
NA
NA
38
42
40
38
40
38
36
36
38
42
38
40
38
38
50
44
36
36
Outlet
Pressure
psi
NA
30
30
28
28
28
29
NA
NA
NA
NA
30
NA
NA
NA
NA
30
NA
32
28
26
28
28
26
28
28
30
32
28
28
28
28
NA
NA
26
30
38
26
28
26
26
26
26
30
26
28
26
26
38
32
26
26
Pressure
Differential
psi
NA
10
10
10
10
10
10
NA
NA
NA
NA
10
NA
NA
NA
NA
10
NA
8
8
10
10
10
10
10
10
10
10
10
10
10
10
NA
NA
12
12
2
12
12
12
10
10
12
12
12
12
12
12
12
12
10
10
Cumulative
Volume
Treated
gal
NA
19,174
30,304
32,962
42,634
46,290
51,661
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
85,630
89,621
96,210
108,229
123,309
133,247
139,601
146,328
NA
175,644
189,013
201,030
214,008
221,023
239,951
248,215
256,148
263,073
273,519
285,467
314,730
337,239
356,060
370,649
406,402
414,543
423,397
429,740
435,708
448,221
452,105
457,285
464,963
479,376
Cumulative
Bed Volumes
Treated ''"
BV
NA
117
185
201
260
282
315
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
522
546
587
660
752
812
851
892
NA
1,071
1,153
1,226
1,305
1,348
1,463
1,514
1,562
1,604
1,668
1,741
1,919
2,056
2,171
2,260
2,478
2,528
2,582
2,620
2,657
2,733
2,757
2,788
2,835
2,923
pH
NA
6.64
6.82
6.88
6.80
6.84
6.88
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
6.85
6.94
6.94
6.92
6.85
6.91
6.88
6.92
NA
6.94
6.95
6.91
NM
6.89
NA
NA
6.93
6.76
6.76
6.82
6.62
6.51
6.58
6.62
6.56
6.61
6.63
6.62
6.76
6.71
6.67
6.74
6.67
-------
Table A-l. EPA Arsenic Demonstration Project at Bruni, TX - Daily System Operation Log Sheet (Continued)
Week No.
12
13
14
15
16
17
18
19
20
21
Day of
Week
Mon
Tue
Wed
Thu
Fri
Mon
Tue
Wed
Thu
Fri
Mon
Tue
Wed
Thu
Fri
Mon
Tue
Wed
Thu
Fri
Mon
Tue
Wed
Thu
Fri
Mon
Tue
Wed
Thu
Fri
Mon
Tue
Wed
Thu
Fri
Mon
Tue
Wed
Thu
Mon
Tue
Wed
Thu
Fri
Mon
Tue
Wed
Thu
Fri
Date
02/20/06
02/21/06
02/22/06
02/23/06
02/24/06
02/27/06
02/28/06
03/01/06
03/02/06
03/03/06
03/06/06
03/07/06
03/08/06
03/09/06
03/10/06
03/13/06
03/14/06
03/15/06
03/16/06
03/17/06
03/20/06
03/21/06
03/22/06
03/23/06
03/24/06
03/27/06
03/28/06
03/29/06
03/30/06
03/31/06
04/03/06
04/04/06
04/05/06
04/06/06
04/07/06
04/10/06
04/11/06
04/12/06
04/13/06
04/17/06
04/18/06
04/19/06
04/20/06
04/21/06
04/24/06
04/25/06
04/26/06
04/27/06
04/28/06
Well
Operational
Hours
hr
5.4
3.1
2.2
2.3
2.2
5.1
2.2
2.1
NA
1.3
1.9
0.7
0.9
1.6
1.9
3.0
5.4
4.8
5.0
5.4
5.7
7.8
10.1
11.0
5.2
6.5
5.2
7.7
3.8
6.3
14.7
8.5
6.1
10.1
7.3
5.8
7.9
12.0
18.5
15.4
9.4
8.1
8.5
9.0
7.2
12.4
15.8
8.8
5.7
Vessel A
Flowrate
gpm
52
51
52
52
52
53
52
52
NA
NA
49
52
50
52
52
50
51
51
52
52
52
49
52
51
52
52
51
52
53
46
51
52
51
48
52
52
53
51
52
52
49
52
53
51
49
52
52
49
53
Cumulative
Totalizer
gal
349,543
357,906
363,712
369,820
375,462
388,999
395,397
400,388
NA
403,939
408,768
410,597
412,952
417,448
422,421
430,465
447,253
460,094
473,291
487,179
501,498
522,266
550,641
582,679
596,177
612,520
625,670
647,997
657,686
674,693
714,575
738,606
754,237
780,646
798,657
813,257
834,182
867,024
915,364
953,590
980,223
1,003,256
1,026,074
1,052,191
1,069,814
1,104,268
1,151,908
1,175,787
1,189,735
Usage
gal
14,178
8,363
5,806
6,108
5,642
13,537
6,398
4,991
NA
3,551
4,829
1,829
2,355
4,496
4,973
8,044
16,788
12,841
13,197
13,888
14,319
20,768
28,375
32,038
13,498
16,343
13,150
22,327
9,689
17,007
39,882
24,031
15,631
26,409
18,011
14,600
20,925
32,842
48,340
38,226
26,633
23,033
22,818
26,117
17,623
34,454
47,640
23,879
13,948
Average
Flowrate
gpm
44
45
44
44
43
44
48
40
NA
46
42
44
44
47
44
45
52
45
44
43
42
44
47
49
43
42
42
48
42
45
45
47
43
44
41
42
44
46
44
41
47
47
45
48
41
46
50
45
41
Pressure
Differential
PSi
1.0
1.0
1.0
1.0
1.0
1.0
2.0
2.0
NA
NA
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
2.0
1.0
2.0
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
2.5
Vessel B
Flowrate
gpm
53
52
53
53
53
54
53
53
NA
NA
50
53
51
53
53
51
52
52
53
53
53
51
53
53
53
53
52
52
53
47
52
53
52
49
53
53
54
52
53
53
50
53
54
50
49
53
53
50
54
Cumulative
Totalizer
gal
354,107
362,573
368,442
374,611
380,319
393,999
400,371
405,522
NA
409,117
413,981
415,820
418,191
422,751
427,788
435,993
453,096
466,107
479,476
493,527
507,994
529,111
558,031
590,675
604,398
620,897
634,183
656,918
666,722
684,032
724,554
749,092
765,045
792,082
810,333
825,086
846,505
880,032
929,620
968,494
995,672
1,019,217
1,042,523
1,069,065
1,086,721
1,121,440
1,169,626
1,193,750
1,207,751
Usage
gal
14,332
8,466
5,869
6,169
5,708
13,680
6,372
5,151
NA
3,595
4,864
1,839
2,371
4,560
5,037
8,205
17,103
13,011
13,369
14,051
14,467
21,117
28,920
32,644
13,723
16,499
13,286
22,735
9,804
17,310
40,522
24,538
15,953
27,037
18,251
14,753
21,419
33,527
49,588
38,874
27,178
23,545
23,306
26,542
17,656
34,719
48,186
24,124
14,001
Average
Flowrate
gpm
44
46
44
45
43
45
48
41
NA
46
43
44
44
48
44
46
53
45
45
43
42
45
48
49
44
42
43
49
43
46
46
48
44
45
42
42
45
47
45
42
48
48
46
49
41
47
51
46
41
Pressure
Differential
PSi
5.0
5.0
5.0
5.0
5.0
5.0
5.0
5.0
NA
NA
4.0
5.0
5.0
5.0
5.0
5.0
5.0
5.0
5.0
5.0
4.0
2.0
0.0
1.0
1.0
0.0
2.0
0.0
0.0
2.5
0.0
2.5
2.5
2.5
2.5
4.0
4.0
4.0
5.0
5.0
4.0
4.0
5.0
4.0
4.0
5.0
5.0
5.0
5.0
System
Inlet Pressure
PSi
38
38
38
40
38
42
38
38
NA
NA
56
44
36
36
38
34
40
38
38
38
38
54
38
40
60
42
36
48
38
59
38
36
40
52
38
42
38
36
40
38
50
54
36
60
42
38
38
58
36
Outlet
Pressure
PSi
26
26
26
36
26
28
26
26
NA
NA
46
32
24
24
26
22
28
26
26
26
26
44
26
26
50
30
24
36
24
48
26
24
28
40
26
30
24
24
28
26
38
44
24
50
30
26
24
48
24
Pressure
Differential
PSi
12
12
12
4
12
14
12
12
NA
NA
10
12
12
12
12
12
12
12
12
12
12
10
12
14
10
12
12
12
14
11
12
12
12
12
12
12
14
12
12
12
12
10
12
10
12
12
14
10
12
Cumulative
Volume
Treated
gal
493,708
502,174
508,043
514,212
519,920
533,600
539,972
545,123
NA
548,718
553,582
555,421
557,792
562,352
567,389
575,594
592,697
605,708
619,077
633,128
647,595
668,712
697,632
730,276
743,999
760,498
773,784
796,519
806,323
823,633
864,155
888,693
904,646
931,683
949,934
964,687
986,106
1,019,633
1,069,221
1,108,095
1,135,273
1,158,818
1,182,124
1,208,666
1,226,322
1,261,041
1,309,227
1,333,351
1,347,352
Cumulative
Bed Volumes
Treated "'"
BV
3,010
3,062
3,098
3,135
3,170
3,254
3,293
3,324
NA
3,346
3,376
3,387
3,401
3,429
3,460
3,510
3,614
3,693
3,775
3,861
3,949
4,078
4,254
4,453
4,537
4,637
4,718
4,857
4,917
5,022
5,269
5,419
5,516
5,681
5,792
5,882
6,013
6,217
6,520
6,757
6,922
7,066
7,208
7,370
7,478
7,689
7,983
8,130
8,216
PH
6.78
6.86
6.78
6.88
6.80
6.84
6.88
6.86
NA
NA
6.99
6.93
7.02
6.96
7.68
7.53
7.73
8.12
8.22
7.56
7.42
7.33
7.38
7.61
7.64
7.60
7.70
NA
7.54
7.31
7.51
7.35
7.40
7.38
7.66
7.31
7.34
7.49
7.30
7.58
7.41
7.30
7.28
6.91
7.02
7.15
7.28
6.91
7.03
>
-------
Table A-l. EPA Arsenic Demonstration Project at Bruni, TX - Daily System Operation Log Sheet (Continued)
Week No.
22
23
24
25
26
27
Day of
Week
Mon
Tue
Wed
Thu
Fri
Mon
Tue
Wed
Thu
Fri
Mon
Tue
Wed
Thu
Fri
Mon
Tue
Wed
Thu
Fri
Tue
Wed
Thu
Fri
Mon
Tue
Wed
Thu
Fri
Date
05/01/06
05/02/06
05/03/06
05/04/06
05/05/06
05/08/06
05/09/06
05/10/06
05/11/06
05/12/06
05/15/06
05/16/06
05/17/06
05/18/06
05/19/06
05/22/06
05/23/06
05/24/06
05/25/06
05/26/06'"'
05/30/06
05/31/06
06/01/06
06/02/06
06/05/06
06/06/06
06/07/06
06/08/06
06/09/06
Well
Operational
Hours
hr
10.3
7.4
11.3
9.6
10.4
16.6
9.4
11.5
10.1
10.1
21.4
2.8
2.5
7.6
8.9
13.9
7.5
9.3
20.5
6.7
14.3
10.9
5.7
7.3
5.7
4.2
10.6
11.2
10.2
Vessel A
Flowrate
gpm
53
52
50
50
44
51
52
50
50
52
52
49
52
51
46
52
49
51
52
50
50
45
52
53
52
44
52
52
52
Cumulative
Totalizer
gal
1,215,584
1,234,603
1,267,350
1,293,809
1,319,455
1,361,583
1,387,691
1,421,409
1,449,175
1,474,621
1,530,575
1,537,194
1,543,390
1,563,262
1,586,222
1,624,747
9,644
35,965
93,797
110,177
143,981
171,468
185,133
203,556
217,127
227,171
253,528
286,015
313,234
Usage
gal
25,849
19,019
32,747
26,459
25,646
42,128
26,108
33,718
27,766
25,446
55,954
6,619
6,196
19,872
22,960
38,525
9,644
26,321
57,832
16,380
33,804
27,487
13,665
18,423
13,571
10,044
26,357
32,487
27,219
Average
Flowrate
gpm
42
43
48
46
41
42
46
49
46
42
44
39
41
44
43
46
21
47
47
41
39
42
40
42
40
40
41
48
44
Pressure
Differential
psi
2.5
2.5
2.5
2.5
2.5
2.5
2.5
5.0
4.0
5.0
5.0
5.0
6.0
6.0
4.0
5.0
5.0
5.0
6.0
6.0
5.0
6.0
6.0
5.0
4.0
4.0
5.0
6.0
6.0
Vessel B
Flowrate
gpm
54
53
51
51
45
52
53
50
51
53
52
49
52
51
47
52
49
52
52
50
51
46
52
53
53
45
53
53
53
Cumulative
Totalizer
gal
1,233,777
1,252,930
1,286,025
1,312,756
1,338,555
1,380,917
1,407,248
1,441,360
1,469,389
1,495,067
1,551,451
1,558,049
1,564,205
1,584,309
1,607,542
1,646,303
1,665,455
1,691,932
14,918
31,398
65,035
92,786
106,485
125,055
138,591
148,595
175,113
207,864
235,373
Usage
gal
26,026
19,153
33,095
26,731
25,799
42,362
26,331
34,112
28,029
25,678
56,384
6,598
6,156
20,104
23,233
38,761
19,152
26,477
14,918
16,480
33,637
27,751
13,699
18,570
13,536
10,004
26,518
32,751
27,509
Average
Flowrate
gpm
42
43
49
46
41
43
47
49
46
42
44
39
41
44
44
46
43
47
12
41
39
42
40
42
40
40
42
49
45
Pressure
Differential
psi
5.0
5.0
5.0
5.0
2.5
5.0
5.0
5.0
5.0
5.0
5.0
4.0
6.0
5.0
4.0
5.0
5.0
5.0
5.0
5.0
5.0
5.0
6.0
5.0
3.0
3.0
5.0
5.0
5.0
System
Inlet Pressure
psi
42
38
48
60
58
36
38
40
44
38
44
52
40
38
56
38
38
34
36
58
36
40
38
46
50
52
44
36
48
Outlet
Pressure
psi
30
26
36
50
48
24
26
28
32
26
32
40
26
26
46
26
26
24
24
46
24
28
24
42
42
42
32
24
36
Pressure
Differential
psi
12
12
12
10
10
12
12
12
12
12
12
12
14
12
10
12
12
10
12
12
12
12
14
4
8
10
12
12
12
Cumulative
Volume
Treated
gal
1,373,378
1,392,531
1,425,626
1,452,357
1,478,156
1,520,518
1,546,849
1,580,961
1,608,990
1,634,668
1,691,052
1,697,650
1,703,806
1,723,910
1,747,143
1,785,904
1,805,056
1,831,533
1,846,451
1,862,931
1,896,568
1,924,319
1,938,018
1,956,588
1,970,124
1,980,128
2,006,646
2,039,397
2,066,906
Cumulative
Bed Volumes
Treated ''"
BV
8,374
8,491
8,693
8,856
9,013
9,271
9,432
9,640
9,811
9,967
10,311
10,352
10,389
10,512
10,653
10,890
11,006
1 1 , 1 68
11,259
11,359
11,564
11,734
11,817
11,930
12,013
12,074
12,236
12,435
12,603
pH
6.95
7.42
NA|e)
NA|el
NA'"
NA'"
NA|el
NA|el
NA|e)
NA'"
NA'e)
NA|el
NA|e)
NA|el
NA""
NA1"
NA'"
NA'"
NA'"
NA'"
7.01
NA|e)
NA|el
NA'"
6.78
7.01
6.89
6.85
6.86
>
1 ' Bed volume = 22 cu.ft. or 164 gallons (equivalent to the volume of media in one vessel)
(t>1 Bed volumes calculated based on Vessel B usage
(cl Totalizer for Vessel A re-set on 01/12/06 and 05/23/06.
(dl Totalizer for Vessel B re-set on 01/12/06 and 05/26/06.
(e| In-line pH probe not operational.
NA = not available
Highlighted cells indicate calculated values.
-------
APPENDIX B
ANALYTICAL DATA
-------
Table B-l. Analytical Results from Treatment Plant Sampling at Bruni, TX
Sampling Date
Sampling Location
Parameter Unit
Bed Volume
Alkalinity (CaCO3)
Fluoride
Sulfate
Nitrate (as N)
Total P (as PO4)
Silica (asSiO2)
Turbidity
pH
Temperature
DO
ORP
Free Chlorine (as
CI2)
Total Chlorine (as
CI2)
Total Hardness
(as CaCO3)
Ca Hardness (as
CaCO3)
Mg Hardness (as
CaCO3)
As (total)
As (soluble)
As (particulate)
As (III)
As(V)
Fe (total)
Fe (soluble)
Mn (total)
Mn (soluble)
10A3
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
NTU
S.U.
°C
mg/L
mV
mg/L
mg/L
mg/L
mg/L
mg/L
M9/L
M9/L
M9/L
M9/L
M9/L
M9/L
M9/L
M9/L
M9/L
12/08/05(a)
IN
-
317
0.5
104
<0.05
0.03
41.8
0.3
8.2
26.6
1.8
325
-
-
17.1
11.3
5.8
51.4
53.1
<0.1
35.8
17.3
<25
<25
4.3
4.2
AP
-
321
0.6
104
<0.05
0.1
41.5
<0.1
7.4
26.7
2.3
679
1.0
1.6
19.3
13.4
5.9
62.2
61.0
1.2
3.3
57.7
<25
<25
4.3
3.4
TA
NA
330
0.5
103
<0.05
<0.03
13.5
<0.1
7.1
24.8
0.9
387
0.1
0.3
27.9
17.2
10.7
3.9
3.4
0.5
2.9
0.6
<25
<25
1.8
1.6
TB
NA
352
0.4
100
<0.05
<0.03
1.7
<0.1
7.3
24.7
1.3
371
-
-
47.2
29.4
17.9
4.0
2.2
1.8
1.6
0.5
<25
<25
5.0
5.1
12/13/05(b)
IN
-
326
-
-
-
<0.03
43.3
<0.1
8.2
24.1
1.5
379
-
-
-
-
-
55.7
-
-
-
-
<25
-
3.7
-
AP
-
330
-
-
-
<0.03
43.5
0.1
7.2
24.0
1.5
592
0.6
-
-
-
-
55.8
-
-
-
-
<25
-
3.4
-
TA
0.2
330
-
-
-
<0.03
25.7
0.2
7.2
24.0
1.8
499
-
-
-
-
-
3.6
-
-
-
-
<25
-
1.1
-
TB
0.2
321
-
-
-
<0.03
6.4
0.2
7.2
23.0
2.0
425
-
-
-
-
-
3.5
-
-
-
-
<25
-
1.1
-
01/05/06
IN
-
334
0.5
104
<0.05
<0.03
41.7
0.2
8.1
23.5
2.1
234
-
-
19.4
12.0
7.4
51.5
56.5
<0.1
40.4
16.1
<25
<25
3.9
3.7
AP
-
334
0.6
104
<0.05
<0.03
42.3
0.4
8.1
23.5
2.2
533
2.0
2.1
19.1
11.9
7.2
60.1
51.3
8.7
1.5
49.8
<25
<25
3.3
3.3
TA
0.6
312
0.6
112
<0.05
<0.03
34.2
0.2
7.4
23.2
2.1
671
-
-
11.6
7.6
4.0
1.8
1.3
0.4
1.2
0.2
<25
<25
<0.1
<0.1
TB
0.6
312
0.7
114
<0.05
<0.03
31.8
0.2
7.3
23.1
2.0
686
1.5
2.1
15.8
9.9
5.9
1.5
1.3
0.2
1.2
<0.1
<25
<25
<0.1
0.2
01/17/06
IN
-
334
-
-
-
<0.03
43.8
1.1
8.0
25.7
2.4
257
-
-
-
-
-
58.8
-
-
-
-
28.8
-
4.5
-
AP
-
330
-
-
-
<0.03
42.8
0.4
8.0
25.9
1.6
538
1.5
1.8
-
-
-
60.4
-
-
-
-
<25
-
4.4
-
TA
1.2
321
-
-
-
<0.03
39.9
0.6
7.1
25.1
1.5
690
-
-
-
-
-
4.6
-
-
-
-
<25
-
0.5
-
TB
1.2
312
-
-
-
<0.03
39.6
0.3
7.1
24.2
1.4
700
1.7
1.7
-
-
-
6.3
-
-
-
-
<25
-
0.2
-
02/01/06
IN
-
320
0.5
105
<0.05
<0.03
41.7
0.7
8.1
26.7
1.3
239
-
-
23.7
17.0
6.7
61.4
54.3
7.1
40.8
13.5
<25
<25
3.2
3.6
AP
-
320
0.6
104
<0.05
<0.03
42.6
0.3
7.1
26.5
1.4
465
1.6
1.5
22.2
16.9
5.3
56.2
50.8
5.4
3.1
47.7
<25
<25
3.4
3.5
TA
2.0
342
0.5
98
<0.05
<0.03
41.6
0.2
7.3
26.2
1.5
605
-
-
33.0
25.1
7.9
3.4
3.0
0.4
2.9
0.1
<25
<25
<0.1
<0.1
TB
2.0
325
0.6
103
<0.05
<0.03
38.9
0.3
7.4
26.2
1.3
680
1.7
1.7
17.1
13.8
3.3
2.8
2.9
<0.1
2.4
0.5
<25
<25
<0.1
<0.1
(a) Chlorine measurements taken on 12/09/05.
(b) Water quality measurements taken on 12/15/05.
IN = at wellhead; AP = after pH adjustment; TA = after Tank A; TB = after Tank B.
NA = not available.
-------
Table B-l. Analytical Results from Treatment Plant Sampling at Bruni, TX (Continued)
Sampling Date
Sampling Location
Parameter Unit
Bed Volume
Alkalinity
(CaCO3)
Fluoride
Sulfate
Nitrate (as N)
Total P (as PO4)
Silica (asSiO2)
Turbidity
pH
Temperature
DO
ORP
Free Chlorine
(as CI2)
Total Chlorine
(as CI2)
Total Hardness
(as CaCO3)
Ca Hardness (as
CaCO3)
Mg Hardness (as
CaCO3)
As (total)
As (soluble)
As (particulate)
As (III)
As(V)
Fe (total)
Fe (soluble)
Mn (total)
Mn (soluble)
10A3
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
NTU
S.U.
°C
mg/L
mV
mg/L
mg/L
mg/L
mg/L
mg/L
M9/L
M9/L
M9/L
M9/L
M9/L
M9/L
M9/L
M9/L
M9/L
02/15/06
IN
-
324
-
-
-
<0.03
41.5
1.0
8.1
26.7
1.1
258
-
-
-
-
-
61.2
-
-
-
-
<25
-
3.2
-
AP
-
324
-
-
-
<0.03
42.3
1.5
7.2
26.9
1.6
546
0.6
0.7
-
-
-
64.4
-
-
-
-
<25
-
3.1
-
TA
2.8
316
-
-
-
<0.03
43.3
1.1
7.3
27.0
1.5
631
-
-
-
-
-
4.2
-
-
-
-
<25
-
0.6
-
TB
2.8
328
-
-
-
<0.03
40.2
2.0
7.2
27.1
2.1
663
0.9
1.0
-
-
-
3.9
-
-
-
-
<25
-
0.3
-
02/28/06(a)
IN
-
322
314
-
-
-
<0.03
<0.03
40.6
40.7
0.4
0.4
NA
NA
NA
NA
-
-
-
-
-
61.8
57.6
-
-
-
-
<25
<25
-
5.1
5.4
-
AP
-
314
318
-
-
-
<0.03
<0.03
41.6
41.0
0.2
0.2
NA
NA
NA
NA
NA
NA
-
-
-
61.9
57.4
-
-
-
-
<25
<25
-
3.2
4.6
-
TA
3.3
322
310
-
-
-
<0.03
<0.03
41.8
41.5
0.2
0.3
NA
NA
NA
NA
-
-
-
-
-
2.7
2.6
-
-
-
-
<25
<25
-
<0.1
<0.1
-
TB
3.3
335
327
-
-
-
<0.03
<0.03
41.3
41.2
0.2
0.2
NA
NA
NA
NA
NA
NA
-
-
-
2.2
2.4
-
-
-
-
<25
<25
-
<0.1
<0.1
-
03/14/06
IN
-
314
0.7
107
<0.05
<0.01
41.5
0.6
8.2
26.3
1.6
238
-
-
20.1
13.3
6.8
60.3
51.9
8.3
38.7
13.2
<25
<25
4.1
4.1
AP
-
310
0.8
107
<0.05
<0.01
40.6
0.4
7.3
26.7
1.7
569
0.8
1.1
21.2
13.9
7.3
62.3
53.5
8.9
1.9
51.6
<25
<25
3.2
3.1
TA
3.6
322
0.8
106
<0.05
<0.01
41.1
0.3
7.3
26.5
1.3
657
-
-
22.2
14.3
8.0
2.2
1.5
0.7
1.3
0.2
<25
<25
0.3
0.3
TB
3.6
327
0.8
106
<0.05
<0.01
38.7
0.7
7.3
26.6
2.3
662
1.0
1.2
24.2
15.6
8.5
1.7
1.5
0.2
1.3
0.2
<25
<25
0.2
0.2
03/28/06(b)
IN
-
325
-
-
-
;
41.7
0.9
8.2
26.5
1.5
259
-
-
-
-
-
46.2
-
-
-
-
<25
-
4.9
-
AP
-
321
-
-
-
-
42.1
0.9
7.5
27.2
1.8
309
0.5
1.2
-
-
-
50.2
-
-
-
-
<25
-
3.7
-
TA
4.7
325
-
-
-
;
42.6
0.9
7.6
27.4
1.8
532
-
-
-
-
-
1.4
-
-
-
-
<25
-
0.3
-
TB
4.7
325
-
-
-
;
42.1
0.8
7.5
27.4
1.9
587
0.9
1.0
-
-
-
1.1
-
-
-
-
<25
-
0.1
-
04/11/06(c)
IN
-
311
0.7
106
<0.05
<0.01
40.9
0.7
NA
NA
NA
NA
-
-
30.1
22.7
7.4
55.4
51.5
3.8
36.5
15.0
<25
<25
3.5
3.6
AP
-
307
0.8
106
<0.05
<0.01
40.2
0.5
NA
NA
NA
NA
NA
NA
30.0
22.8
7.2
57.2
51.6
5.6
0.5
51.1
<25
<25
3.5
3.4
TA
6.0
315
0.8
107
<0.05
<0.01
40.5
0.5
NA
NA
NA
NA
-
-
27.9
21.3
6.6
1.0
0.8
0.2
0.5
0.3
<25
<25
<0.1
<0.1
TB
6.0
315
0.8
108
<0.05
<0.01
42.7
0.6
NA
NA
NA
NA
NA
NA
29.6
22.6
6.9
0.6
0.6
<0.1
0.4
0.2
<25
<25
<0.1
<0.1
(a) Water quality parameters not measured.
(b) Water quality measurements taken on 04/05/06.
IN = at wellhead; AP = after pH adjustment; TA = after Tank A; TB = after Tank B.
NA = not available.
-------
Table B-l. Analytical Results from Treatment Plant Sampling at Bruni, TX (Continued)
Sampling Date
Sampling Location
Parameter Unit
Bed Volume
Alkalinity (CaCO3)
Fluoride
Sulfate
Nitrate (as N)
Total P (as PO4)
Silica (as SiO2)
Turbidity
pH
Temperature
DO
ORP
Free Chlorine (as CI2)
Total Chlorine (as CI2)
Total Hardness (as
CaCO3)
Ca Hardness (as
CaCO3)
Mg Hardness (as
CaCO3)
As (total)
As (soluble)
As (particulate)
As (III)
As(V)
Fe (total)
Fe (soluble)
Mn (total)
Mn (soluble)
10A3
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
NTU
S.U.
°C
mg/L
mV
mg/L
mg/L
mg/L
mg/L
mg/L
M9/L
M9/L
M9/L
M9/L
M9/L
M9/L
M9/L
M9/L
M9/L
04/25/06(a)
IN
-
331
-
-
-
<0.01
40.8
0.2
8.2
26.5
1.3
327
-
-
-
-
-
56.5
-
-
-
-
<25
-
3.1
-
AP
-
344
-
-
-
<0.01
40.8
0.2
7.4
26.3
1.6
603
0.8
1.1
-
-
-
59.5
-
-
-
-
<25
-
2.9
-
TA
7.7
331
-
-
-
<0.01
41.3
0.7
7.3
26.7
1.6
650
-
-
-
-
-
1.1
-
-
-
-
<25
-
<0.1
-
TB
7.7
344
-
-
-
<0.01
41.2
0.1
7.4
26.6
2.0
623
0.7
0.8
-
-
-
0.9
-
-
-
-
<25
-
<0.1
-
05/09/06(b)
IN
-
310
0.9
111
<0.05
<0.03
41.8
0.2
8.1
27.1
1.3
279
-
-
28.6
19.7
9.0
62.9
54.3
8.6
40.2
14.1
<25
<25
3.3
3.3
AP
-
306
1.2
112
<0.05
<0.03
42.3
0.2
7.2
27.2
1.8
499
1.1
1.2
29.3
20.2
9.1
63.8
55.4
8.4
0.7
54.6
<25
<25
3.1
3.1
TA
9.5
294
1.5
113
<0.05
<0.01
42.7
0.2
7.3
27.5
2.1
610
-
-
26.8
18.3
8.5
1.0
0.8
0.2
0.5
0.3
<25
<25
<0.1
<0.1
TB
9.5
314
1.0
113
<0.05
<0.01
42.1
0.3
7.3
27.3
2.4
643
1.5
1.5
29.8
21.1
8.8
0.6
0.6
<0.1
0.5
0.1
<25
<25
<0.1
<0.1
05/23/06(c)
IN
-
313
-
-
-
<0.01
42.8
0.3
8.3
21.3
3.1
271
-
-
-
-
-
54.8
-
-
-
-
28.4
-
3.9
-
AP
-
326
-
-
-
<0.01
41.6
0.5
7.6
21.2
4.1
546
0.5
0.8
-
-
-
50.4
-
-
-
-
<25
-
2.9
-
TA
11.0
338
-
-
-
<0.01
41.7
0.3
7.5
21.4
3.4
597
-
-
-
-
-
1.3
-
-
-
-
<25
-
<0.1
-
TB
11.0
318
-
-
-
<0.01
38.1
0.2
7.5
21.4
3.5
636
0.6
0.7
-
-
-
0.6
-
-
-
-
<25
-
<0.1
-
06/06/06(d)
IN
-
305
0.7
107
<0.05
<0.01
43.9
0.6
8.2
26.4
2.1
299
-
-
20.2
12.4
7.8
58.5
52.3
6.2
37.0
15.3
<25
<25
2.6
2.6
AP
-
318
0.8
112
<0.05
<0.01
43.2
0.5
7.3
26.6
2.6
537
0.9
0.9
19.8
12.2
7.6
57.6
51.6
6.1
0.8
50.8
<25
<25
3.0
3.0
TA
12.1
313
0.8
114
<0.05
<0.01
44.4
0.7
7.2
27.1
2.1
594
-
-
21.0
13.0
8.0
1.1
1.1
<0.1
0.7
0.5
<25
<25
<0.1
<0.1
TB
12.1
318
0.8
136
<0.05
<0.01
45.3
0.8
7.3
27.1
2.2
620
0.7
0.8
20.5
12.7
7.8
0.8
0.8
<0.1
0.6
0.2
<25
<25
0.1
<0.1
(a) Water quality measurements taken on 04/20/06.
(b) Water quality measurements taken on 05/04/06.
(c) Water quality measurements taken on 05/12/05.
(d) Water quality measurements taken on 06/01/06.
IN = at wellhead; AP = after pH adjustment; TA = after Tank A; TB = after Tank B.
NA = not available.
-------