Best Management Practices:  Use of Systematic Project Planning
                     Under a Triad Approach for Site Assessment and Cleanup

                                             September 2010
AUDIENCE AND PURPOSE

This U.S. Environmental Protection Agency (EPA) technical publication is intended for environmental practitioners engaged in
the investigation, design, remediation, and closure or reuse of contaminated sites.  It may be of particular interest to project
managers, senior technical advisors, stakeholders and others who are responsible for project planning, management and
technical execution; as well as non-technical individuals engaged in project participation. This technology bulletin explains
how systematic project planning (SPP),  a comprehensive planning process for environmental cleanup projects, can be used to
plan and execute projects more effectively to achieve the often diverse strategic objectives of all stakeholders, while satisfying
the specific technical and quality objectives required for each stage of a project's life cycle. Derived as a best management
practice (BMP) under the Triad Approach to Site Assessment and Cleanup, SPP has been successfully implemented in each
of the primary regulatory frameworks, including Brownfields, Superfund, Resource Conservation and Recovery Act (RCRA),
underground storage tanks (LIST), and numerous states' voluntary cleanup programs. It has also been used in integrated
regulatory program frameworks.
   THE TRIAD APPROACH

   The Triad Approach (a.k.a., Triad), is a three-pronged approach for managing all forms
   of project uncertainty to improve decision-making and streamline environmental
   cleanup projects.  Triad draws on science and technology advancements and
   practitioner experience to develop strategies for making site work more scientifically-
   defensible, resource-effective, adaptive to changing project needs, and responsive to
   stakeholder concerns.

   The three integrated BMPs of the Triad Approach are:

       •    Systematic project planning (SPP): An efficient method for comprehensive planning, design, and
           implementation for all stages of hazardous waste site investigation and cleanup projects. Generally
           recognized to be common practice for all projects, SPP is uniquely applied and critical to the
           successful design and execution of a Triad-based project.
       •    Dynamic work strategies (DWS):  A sequence of dynamic data collection activities that efficiently addresses
           identified project concerns, which are implemented and managed in the field using real-time information to
           target and manage data and decision uncertainty.  Streamlined workplans, developed in the context of a
           project's regulatory framework, are used to document DWS.
       •    Real-time measurement technologies: Any data generation that enables reliable measurement or collection
           and analysis of environmental media in a time frame that facilitates execution of a DWS. These measurements
           typically result in a much greater density of information and are available to direct field activities in time frames
           shorter than those commonly achieved with conventional sampling  and analytical methods.  Together with the
           DWS, real-time measurement technologies are used to focus when and where collaborative sampling and
           analyses can  provide the greatest benefit.

   The Triad Approach can be used to significantly reduce data collection costs, expedite project schedules, enhance
   stakeholder communication, and improve the quality of project and site decisions.
Office of Solid Waste and Emergency
Response (5203P)
      EPA542-F-10-010
       September 2010
www.brownfieldstsc.org

-------
                                        Use of Systematic Project Planning Under a Triad Approach for Site Assessment and Cleanup
SYSTEMATIC PROJECT PLANNING
Systematic Project Planning is a rigorous project planning process that lays a scientifically defensible foundation for proposed
project activities.  SPP under Triad builds off of existing federal standards and guidance for environmental cleanup project
planning and emphasizes that all data collected  satisfy a defined need.  It involves planning for known decisions and building
in contingencies to accommodate changes in project conditions so that stakeholders are able to facilitate the project through
all key decision-making stages.
As part of the Data Quality
Objectives (DQO)
process,  EPA guidance
requires that all projects
use SPP to develop data
acceptance  and other
project performance
criteria for incorporation in
project quality assurance
project plans (QAPPs).
As the most critical
element for successful
planning  and
implementation of a Triad-
based project,  SPP is a
natural extension of EPA's
DQO process as it
incorporates data quality
with  non-scientific
elements, such as social or economic factors. SPP also places a strong emphasis on using a CSM as the basis for the
planning  of all phases of the project life cycle, from investigation through remediation (cleanup or mitigation) and site closure
(regulatory satisfaction that site risks have been removed or mitigated). The CSM is used during SPP to identify data needs,
design the DWS, and drive the selection of appropriate data collection, analysis, and use methodologies. Inherent to DWS
design is an explicit recognition that spatial heterogeneity is the primary source of uncertainty affecting confident site decision-
making.  Therefore, SPP de-emphasizes determining exact numbers of samples to be collected and analyzed and focuses
more on the dynamic generation of a variety of collaborative data sets.
                       Systematic Project Planning Process
Preparation activities:
    •   Organize the project team of stakeholders and technical resources
    •   Summarize site information in a Preliminary Conceptual Site Model (CSM)
    •   Research potential investigation and remedial technologies
    •   Submit Preliminary CSM and other information to SPP participants in advance of meeting

Meeting activities:
    •   Introduce and confirm roles and authorities of participants
    •   Define site reuse goals and project exit strategy
    •   Identify key site decisions, decision-making processes,  tools and rules
    •   Create a Baseline CSM based on refinement of Preliminary CSM
    •   Use Baseline CSM to identify key data gaps
    •   Identify and quantify acceptable levels of uncertainty
    •   Identify real-time technologies and collaborative data needs
    •   Plan for real-time data management, assessment, visualization and communication
    •   Develop detailed DWS outline, decision logic diagrams  and activity sequencing plan
   DQO Guidance Documents that Support SPP

  EPA Quality Manual for Environmental Programs.
  (EPA 2000, May).

  Guidance on Systematic Planning Using the Data
  Quality Objectives Process. (EPA 2006, February).

  Guidance for Developing Quality Assurance Project
  Plans. (EPA 2002, December).

  Uniform Federal Policy for Quality Assurance Project
  Plans (Manual). (EPA 2005, March).

  Workbook for Uniform Federal Policy for Quality
  Assurance Project Plans (Worksheets;. (EPA 2005,
  March).
                       In addition to addressing scientific issues, SPP also considers
                       financial, contractual, stakeholder, legal, and regulatory issues of a
                       site cleanup, such as budgets, contracts, stakeholder concerns, site
                       reuse, and legal and regulatory issues. While SPP efforts are critical
                       for early project stages,  the BMPs associated with planning can be
                       used with equal effectiveness during subsequent phases to optimize
                       a project throughout its life cycle.

                       Effective SPP efforts should address the following key
                       considerations:

                           •    Building social  capital among project stakeholders.
                           •    Evaluating reuse options and exit strategies.
                           •   Achieving stakeholder consensus on the CSM and data
                               gaps.
                           •    Identifying life cycle project data and resource needs.
Office of Solid Waste and Emergency
Response (5203P)
                                                                       EPA542-F-10-010
                                                                         September 2010
                                                                 www.brownfieldstsc.org

-------
                                        Use of Systematic Project Planning Under a Triad Approach for Site Assessment and Cleanup
        Identifying clear project objectives, timelines and other constraints.
        Developing the basic elements of the DWS and establishing performance metrics.
        Evaluating and planning for managing risk-related uncertainties.
        Other integral considerations, such as green remediation, sustainable reuse and Environmental Justice and
        Community Involvement.
                      More information on SPP may be found at: www.triadcentral.org/mgmt/splan/
         More information about SPP technical tools and components:  www.triadcentral.org/tech/dsp sub.cfm?id=1
Building social capital among project stakeholders
SPP involves many activities, including identifying
stakeholders, articulating objectives, evaluating re-use
goals, building GSM consensus, addressing constraints,
identifying regulatory drivers, and  specifying project
sequencing to maximize the use of available resources.
SPP also includes building 'social capital' between
stakeholders, using a team approach to support
consensus-based decision-making; identifying areas of
contention; and facilitating stakeholder involvement,
investment and accountability.

Stakeholders typically include property owners,
responsible parties, regulatory agencies, local interest
groups or organizations ('community' representation), and technical experts.  The breadth of participation, degree of
involvement, and timing of input from stakeholders will vary based on project-specific conditions and regulatory framework.
For teams to be successful, participants must be committed to working through technical  and non-technical issues in a
collaborative, non-adversarial manner. While disagreements among stakeholders are not uncommon, SPP under Triad
provides a process whereby those disagreements can be resolved to the satisfaction of all interested stakeholders.
                      Social Capital
Social Capital is anything that facilitates individual or collective
action, generated by networks of relationships, reciprocity,
trust, and social norms (Coleman, 1988).  Unlike traditional
forms of capital, social capital is not depleted by use, but in
fact depleted by non-use. As social capital lowers the
transaction costs of working together, it facilitates cooperation.
People have the confidence to invest in collective activities,
knowing that others will also do so.  Four features are
important: relations of trust; reciprocity and exchanges;
common rules, norms, and sanctions; and connectedness in
networks and groups (Pretty, 2003).
                                             Triad Functional Teams

          Stakeholders - Persons from involved organizations with final decision-making authority.
          Core Technical Team - Senior technical experts who design and manage the project.
          Field Team- Middle and junior-level staff who perform onsite technical activities.
Project teams that have membership continuity over the life cycle of a project tend to be successful because the teams will
embody a collective understanding of the technical, economic, and political basis for work done to date and work proposed for
the future. Because such team continuity is not always feasible, new personnel are commonly required to climb a steep,
labor-intensive learning curve based on personal review of large quantities of background documents and other information.
SPP efforts ensure faster and more cost-effective personnel transitions through the use of a robust GSM and quality
documentation of decisions and work completed to date.

Triad advocates and project managers should facilitate stakeholder involvement and commitment throughout the project life
cycle, particularly during field activities, so that concerns can be managed and addressed in real time.  The role of the project
manager in SPP  is to encourage stakeholders to  engage in the following activities:
        Share knowledge and insights.
        Test assumptions, beliefs and perspectives.
        Evaluate legal, budgetary and technical
        constraints.
              Achieve clarity over different viewpoints.
              Resolve important concerns and interests.
Office of Solid Waste and Emergency
Response (5203P)
                                           EPA542-F-10-010
                                            September 2010
                                     www.brownfieldstsc.org

-------
                                       Use of Systematic Project Planning Under a Triad Approach for Site Assessment and Cleanup
Involving stakeholders in the project planning process and during project execution is particularly critical under Triad in order
to avoid misunderstandings, disagreements, and potential last minute surprises' associated with stakeholder concerns.
Continual stakeholder involvement ensures that all uncertainties and differing viewpoints regarding the GSM are addressed
and that site decision consensus is maintained  among the stakeholders.  In addition, stakeholder involvement helps mitigate
concerns regarding unfamiliar data collection technologies and the decision-making process to be used at the site. Increased
involvement of senior resources at critical times or delegating greater decision-making power to the field team increases
stakeholder confidence in field-based decisions, ensures quality, and optimizes project efficiency.

Identifying clear project objectives, timelines and other constraints
It is critically important that project stakeholders agree on project objectives or goals, timelines, and other primary constraints
before working together to develop a DWS or other project plan. For example, the following are typical questions that parties
seeking a Brownfield redevelopment grant should be prepared  to answer prior to conducting an SPP effort:
        What is the site's planned reuse?
        What is the economic viability of cleanup?
        Who is responsible for cleanup of the site?
        What is the estimated cost for redevelopment of
        the site?
What plans are there for meaningful community
involvement?
Are there environmental justice issues
associated with the site?
Are remedial action objectives (RAOs) specified?
Projects being performed under other regulatory programs, such as Superfund or RCRA, may also benefit from these
advanced considerations, as well as others specific to those programs. An example of this might be evaluating procurement
strategies in the context of the contractual requirements and funding constraints applicable to the project environment.  The
following are examples of questions that are typically considered during SPP under Triad:
    •   What are the site's main environmental issues?
    •   What media and receptors may be affected?
    •   What is the nature and extent of contamination?
    •   What is the fate and transport of contaminants?
    •   Are exposure pathways complete?
    •   What are the site's appropriate cleanup levels?
    •   What data are needed to support implementation
        of potential cleanup remedies?
    •   Will data be sufficient to support cleanup
        objectives?
    •   What real-time measurement technologies exist
        for acquiring those data?
    •   How can the sequencing of project field activities
        be optimized to maximize real-time data use and
        GSM refinement, while minimizing mobilizations?
    •   Do viable treatment or containment technologies
        or other alternatives exist?
What is the preferred remedial alternative?
What data are needed to evaluate remedy
effectiveness?
What metrics will be used to evaluate remedy
performance?
How can system performance be optimized and
operating costs reduced?
How can site closure be documented?
What is the stakeholder comfort level with the
expected performance of real-time technologies?
What innovative tools and strategies are
potentially applicable?
Is a demonstration of methods applicability
(DMA)  needed?
Which  uncertainties pose the greatest threat to
project success and how will they be managed?
Answers to these questions or other critical project elements identified during SPP serve as the basis for developing technical
planning documents such as QAPPs, field sampling plans (FSPs), and construction work plans.  Clear definitions of team
member roles and responsibilities, critical project components, short-, mid-, and long-term milestones, and key decision points
requiring timely stakeholder input help ensure project efficiency.
Office of Solid Waste and Emergency
Response (5203P)
                             EPA542-F-10-010
                              September 2010
                       www.brownfieldstsc.org

-------
                                        Use of Systematic Project Planning Under a Triad Approach for Site Assessment and Cleanup
Developing and evolving a CSM to identify life cycle project data and resource needs
In addition to supporting the identification of data and resource needs, the CSM is an effective BMP for facilitating technical
team communication, maintaining stakeholder consensus, and supporting public information presentations.  Under Triad-
based projects, the CSM is the basis for defining data needs and strategies for uncertainty management and managing them
throughout the project's life cycle.  Simplified  renderings and more complex visualization tools are used  to capture,
communicate,  and exploit all existing information, while enhancing stakeholder understanding of site conditions and focusing
future efforts on key uncertainties or data gaps.

The CSM is an iterative, living representation' of a site that is used to guide the entire cleanup process;  from project planning
to site closure. Accordingly, the life cycle of a CSM is comprised of two milestone deliverables:  Preliminary CSM and
Baseline CSM; and four evolutionary stages:  Characterization CSM Stage, Design CSM Stage, Remediation/Mitigation CSM
Stage, and Post Remedy(s) CSM Stage.

To effectively support project and site decision making,  the CSM  must be updated, or 'evolved', with new information to reflect
revised understandings of site conditions.  This is best achieved when the CSM is evolved in alignment  with the major phases
of an environmental cleanup project's programmatic regulatory requirements. Figure 1 shows how each stage of the CSM life
cycle aligns with the general site investigation, and cleanup process and seven of the primary environmental regulatory
programs, as well as how SPP and the other  Triad BMPs apply to all project phases.

A CSM prepared under Triad is information-intensive, building on the CSM formats typically associated with site investigation
and cleanup efforts. For example, network-receptor diagrams are commonly used as CSMs for Superfund or other sites to
illustrate the connective relationships between sources, pathways, receptors, and exposure routes.  Triad  integrates these
diagrams with  other site information  and data to generate a more comprehensive CSM. The CSM is then  directly used to
identify specific data gaps that drive  the development of the DWS during SPP efforts. A CSM can involve a combination of
narrative, visual, tabular, modeling, and conceptual tools to document site conditions, contaminants and potential sources,
pathways and  receptors of concern,  geologic conditions, hydrogeologic conditions and a host of other valuable site
information. Complex geologic, hyrdogeologic,  and chemical processes are often summarized and  represented by a
simplified block diagram or 3-D visualization.
                                                      A                                              A
Figure 2 shows an example of a Preliminary
CSM developed prior to an SPP effort for a site
in Colorado that included a former
manufactured gas plant (MGP), an above-
ground storage tank (AST), a landfill, a
contaminant plume, and an adjacent river.
This 2-D format provides a simplified
visualization of the 'state of knowledge' for a
site for stakeholders to prepare for an SPP
meeting.
                                                          CACHE LA
                                                         POUDRE RIVER
                                                           LEGEND   NOT TO SCALE
Using the Preliminary CSM as a starting point,
a Baseline CSM is developed during an SPP
effort to provide a visual representation of data
completeness, uncertainties, and potential data
gaps. The Baseline CSM is then used to
develop site-specific sampling designs and
DWS decision logic for the field investigation
effort.  If competing views on the Baseline
CSM are articulated by team members or
stakeholders, these  disparities should
collectively serve as the basis for subsequent
sampling and information collection efforts.
   T

  — ? —
WATER TABLE (APPROXIMATE)
BENZENE AND NAPTHALENE PLUME BOUNDARY
POST-PINEY CREEK ALLUVIUM (UPPER HOLOCENE)
BROADWAY ALLUVIUM (PLEISTOCENE)
PIERRE SHALE
 I / / I  LANDFILL
        CACHE LA POUDRE RIVER
  POUDRE RIVER SITE
FORT COLLINS, COLORADO
                                                PRELIMINARY
                                           CONCEPTUAL SITE MODEL
                                       U.S. EPA REGION VIII
                                      IN COOPERATION WITH
                                BROWNFIELDS TECHNOLOGY SUPPORT CENTER
Figure 2: Preliminary CSM Representation. This Preliminary CSM summarizes
general site information, including primary site attributes, geologic stratigraphy,
groundwater potentiometric surface and flow direction, groundwater-surface
water relationship, and presumed extent of soil and groundwater contamination.
This form of CSM can be an effective method of communicating site conditions
to a diverse audience in an easy-to-understand format.
Office of Solid Waste and Emergency
Response (5203P)
                                                    EPA542-F-10-010
                                                      September 2010
                                              www.brownfieldstsc.org

-------
                                                                                                             Use of Systematic Project Planning Under a Triad Approach for Site Assessment and Cleanup
^^^^^^^^^H Best ^^^^1
^^^^^^^^^^1 General Management VCUP ^^^^1
1 Environmental CSM Life Cycle Practices CERCLA - Superfund RCRA Brownfields UST Varies by IRP/ERP MMRP ^^H
1 Cleanup Steps SPP DWS/ State ^^^^H
^^^^^^^^^^^H RTMT ^^^^^1






















SITE ASSESSMENT
SITE INVESTIGATION
AND ALTERNATIVES
EVALUATION
REMEDY
SELECTION


REMEDY
IMPLEMENTATION




POST-
CONSTRUCTION
ACTIVITIES




SITE COMPLETION






Preliminary CSM
i
Baseline CSM
Characterization
CSM Stage
^
r
Design CSM
Stage
j
Remediation/
Mitigation CSM
Stage



>
Post-R
r*cu



r
emedy
Lorn bidye





>





t























1
i
T







>


















Preliminary Assessment (PA) Facility Assessment Phase 1 Initial Site PA PA PA
cilo incnortinn ,qn (RFA) Environmental Site Characterization <-, c, c.
Site Inspection (SI) Assessment (ESA) , jti , ReSDQnse
National Priorities List (NPL) MR Site Prioritization
No Further Remedial Action Protocol (MRSPP)
Planned (NFRAP)
Remedial Investigation/ Facility Investigation Phase II ESA SI RI/FS RI/FS RI/FS
Feasibility Study (RI/FS) (RFI) Corrective Action NFRAP
Removal Actions - Emergency/ Corrective Measures Plan (CAP)
Time Critical/Non-Time-uitical Study (CMS)
Proposed Plan Statement of Basis Remedial Action Plan Cleanup Selection ROD Proposed Plan Remedy Selection
Record of Decision (ROD) (SB) (RAP) ROD
Final Decision
and Response to
Comments
Remedial Design (RD) Corrective Measure Cleanup and Corrective Action RD RD RD
Remedial Action (RA)- Implementation (CMI) Development . Low.impact site RA RA- Interim Time Critical Removal
Interim and Final cleanup and Final Action (TCRA)
- Risk-based Remedy in RA
remediation Place (RIP) R|P
-Generic remedies
- Soil matrix cleanup
Operational & Functional Period O&M Property LTM O&M Shakedown period Shakedown period
Operation & Maintenance (O&M) On-site inspections Management LTM Operating Property Long Term
Long term monitoring (LTM) and oversight Long-term O&M and Successfully Management
c,-,;. Redevelopment O&M
Activities [Private- ITM
Long Term Response Action and Public-led)
(Fund-lead groundwater/surface
water restoration)
Construction Complete (CC) Certification of CC No Further Action CC Response RC
Preliminary or Final Close Out Completion prope|1y Complete (RC) NFA
Report (PCOR/FCOR) Corrective Action Management NFA
Site Completion -FCOR CoSor^ou,
Site Deletion Controls
O&M as appropriate






















          Abbreviations:
          SPP = Systematic Project Planning
          DWS = Dynamic Work Strategies
          RTMT = Real Time Measurement Technologies
CERCLA = Comprehensive Environmental Response.
Compensation and Liability Act
RCRA = Resource Conservation and Recovery Act
UST = Underground Storage Tanks
TSCA = Toxic Substances Control Act
VCUP = Voluntarily Clean Up Programs
IRP/ERP = Installation Restoration Program/
Environmental Restoration Program
MMRP = Military Munitions Response Program
          Figure 1.  Crosswalk of Regulatory Programs, CSM Life Cycle, and Triad BMPs. Triad provides a flexible and comprehensive framework to facilitate site decisions during the entire site-cleanup process, irrespective
          of the environmental program driving site cleanup. Using SPP. evolving the CSM. and leveraging DWS and RTMT at each key project stage can improve project efficiency and effectiveness.
          Note: The width and gradation of the blue arrows demonstrating BMPs indicate the relative level of effort applied and the resulting impact and value of performing the BMPs at the indicated project stages.
Office of Solid Waste and Emergency
Response (5203P)
                                                                                                                              EPA542-F-10-010
                                                                                                                                September 2010
                                                                                                                       www.brownfieldstsc.org

-------
                                        Use of Systematic Project Planning Under a Triad Approach for Site Assessment and Cleanup
A Characterization GSM utilizing 3-D visualization
(Figure 3) provides a more detailed understanding of
actual site features and the complexity of subsurface
conditions.

During field activities, the Characterization GSM is
used to focus and guide the data collection program
and is updated in real time with newly collected data.
This allows the project team to maintain consensus
on the GSM in support of project decision making.
Site complexity may drive the need to use SPP
practices to incorporate timely input of specialized
expertise for Characterization GSM revision, such as
from a geophysicist or statistician.  This is one
example of how SPP can add value at any stage of a
Triad project life cycle.

When the Characterization GSM is used effectively in
the context of SPP-derived project objectives, site
uncertainty eventually is reduced to a level wherein
stakeholders can confidently agree that  the site is
adequately characterized to proceed with subsequent
                                                      ,000 ppb
                                                      1,000 ppb
                                                      300 ppb
                                                      100 ppb
                       | Sand
                      J Shale
    Vertical exaggeration = 10:1
Figure 3: Characterization CSM Visualization. This 3-D visualization
captures information regarding a chlorinated solvents plume at a site in
Nebraska, including geologic stratigraphy; well locations and screened
intervals; and contaminant concentration, location and depth all in
relation to the local community.  Visualization software and other tools
can be used to calculate contaminant volume and mass, as well as
model fate and transport. Diagram provided courtesy of Sundance
Environmental & Energy Specialists, Ltd.
project phases. At this point, the role of the
Characterization CSM shifts to supporting optimization of decisions for a more diverse set of project needs. For example, the
nature and scale of decisions changes when the project focus changes from collecting data in support of risk assessment to
evaluating data for the purposes of technology selection  and remedial design.

In post-characterization phases, the project team revises the CSM to accommodate the evolution of site information in direct
support of remedy selection and design  (Design CSM stage), remediation or mitigation (Remediation/Mitigation CSM stage),
and site closure (Post-Remedy[s] CSM stage). For example, for a site that is being positioned to achieve closure, SPP and
the Design CSM can be used to facilitate key stakeholder agreement on the specific steps and performance metrics required
to reach closure. The Remediation/Mitigation CSM would then be used to guide remediation/mitigation efforts such as
directing and documenting excavation activities, managing phased remediation programs, managing secular (operable unit
[OU]-based) remediation efforts, and responding to changed conditions encountered in the field. Continuous updating of the
CSM can be used to maintain  stakeholder consensus as remediation/mitigation progresses. The Post Remedy CSM would
then be used to document the attainment of remediation  goals with specific applications such as supporting No Further Action
(NFA) determinations, providing a basis for using statistical methods for remedy evaluation, benchmarking performance
metrics for triggering options in the ROD, and reducing a system design after an agreed period of operations and maintenance
(O&M).

Evaluating and planning for managing risk-related uncertainties
SPP involves careful selection of data gathering tools, quality assurance and quality control (QA/QC) protocols, and
communication strategies to meet project data needs and effectively manage sources of uncertainty. Evaluating known and
probable uncertainties and allocating resources to the development of strategies to control those uncertainties with the
greatest potential impact is essential for the success of a Triad project. Uncertainty is present in all data used to make
decisions, model results, collect samples, analyze or interpret information, and in the relationship between estimations used to
support decision making and the true or actual conditions present at a site.

Comprehensive SPP can help manage decision uncertainty to acceptable levels through CSM development and refinement
and the use of real-time measurement technologies within a DWS framework. A well-designed CSM captures what is known
about a site, but can also be used to illustrate one or more hypotheses of what might be occurring at a site. Thus, the CSM
can be used to support decision-making with variable degrees of uncertainty, as well as to provide the foundation for
Office of Solid Waste and Emergency
Response (5203P)
                                              EPA542-F-10-010
                                               September 2010
                                        www.brownfieldstsc.org

-------
                                       Use of Systematic Project Planning Under a Triad Approach for Site Assessment and Cleanup
developing data-gathering programs to reduce site uncertainties, decreasing decision-making uncertainty to more acceptable
levels.

Development of a DWS requires the participation of diverse stakeholders and support personnel for technical and other inputs.
It also requires the creation of a concise, yet often complex plan of action to reduce site uncertainty, and to do so within the
constraints of cost- and time-critical performance requirements.  Given this environment, an efficient and collaborative DWS
development effort is best managed using SPP.

Real-time measurement technologies can help manage uncertainty by producing sufficient quantities of data quickly enough to
direct the progress of characterization  or remediation activities while they are underway. Often, SPP efforts on a Triad project
include planning and completing a DMA effort to ensure data of appropriate quality, as agreed to by the stakeholders, will be
collected using the selected or proposed real-time measurement technologies, innovative sampling strategies, or both. A
DMA refers to an initial testing of field equipment and procedures, fixed-base laboratory methods, communication and
information sharing strategies, and data recording and management to ensure that deployment of the technologies will be
successful during full field mobilization.
                   Detailed information on performing DMAs in support of Triad projects is available at
                      www.clu-in.org/download/char/demonstrations of methods  applicabilitv.pdf.
Once the data collection tools are selected, it is important to establish decision criteria and collaborative data relationships that
will be used during dynamic work activities. Designing appropriate data management and communication strategies during
SPP is also critical to ensure  timely stakeholder review, input and decision making, and documentation at the point of data
generation. Doing so will maximize the benefits of real-time information and ensure effective management of high density
data sets.

Leveraging the efficiency of DWS
DWS are designed to focus sampling efforts to improve project efficiency and reduce uncertainty. A well-designed and
executed DWS can result in project life cycle cost and time savings (see Figure 4). Impediments to using DWS as a means to
manage and constrain decision uncertainty can include inadequate site access, unique contaminants, restrictive media, and
regulatory limitations to using a dynamic
sampling approach.  Procurement practices and
contract language may need to be slightly
modified to include optional activities and
grouping of related activities so resources can be
shifted on an as-needed basis and overall costs
can be managed downward.
3 ma

 I
Non-dynamic work plans specify the exact type,
quantity, quality, and location of data collection
prior to any field activities.  Uncertainty
management under non-dynamic approaches
primarily focuses on analytical uncertainty, which
is often one of the smallest contributors to overall
site decision uncertainty. Conversely, DWS
approaches focus on heterogeneity, spatial and
temporal factors, which tend to be the largest
contributors to overall decision uncertainty. DWS
approaches also consider real-time management
 O
 O
 t

 I
  0>
Triad
            Non-dynamic
              Approach
                  Time
Figure 4: Dynamic approaches vs. non-dynamic approaches. This graph
illustrates the level of effort, cost and time required for the Triad Approach
(orange curve) is less than a comparable project performed using a non-
dynamic cleanup approach (green curve).
of project resources, enhancing efforts to collect the appropriate data necessary to comply with the requirements of the
sampling and analysis plan. The increased flexibility and real-time feedback embodied in the DWS approach results in
significant decreases in data gaps, which is the primary driver of site remobilization and extended characterization efforts.
Office of Solid Waste and Emergency
Response (5203P)
        8
                                 EPA542-F-10-010
                                  September 2010
                           www.brownfieldstsc.org

-------
                                       Use of Systematic Project Planning Under a Triad Approach for Site Assessment and Cleanup
At many sites, Baseline GSM assumptions that form the basis for designating sampling frequency and locations need to be
updated early during field activities.  Without real-time information and a flexible DWS approach to target areas of concern,
project teams can encounter difficulties in reacting to these GSM discrepancies during a single mobilization. Each
mobilization can identify additional data needs that require changes to the GSM, subsequent data collection, and
corresponding work plan development, which significantly affect the project schedule and lead to cost inefficiencies. In recent
years, more project teams have identified the need to develop geologic and hydrogeologic context for data derived from
chemical analyses in order to appropriately interpret those results. High-density information, collected using a DWS and
integrated into an  evolving GSM, leads to placement of sampling locations, monitoring wells, and well screen intervals to best
represent site conditions and  manage perceived or actual uncertainties. EPA recently published companion Technology
Bulletins about performing DMAs, managing and interpreting data, and using DWS under a Triad approach, which are
available at www.brownfieldstsc.org.

Summary
The interplay between building social capital, defining clear project objectives, developing a comprehensive GSM  to identify
data and resource needs, and evaluating and managing risk and uncertainties are unique characteristics of Triad-based
projects.  Using the SPP process under Triad to drive project design can improve overall project efficiency and decision
certainty on environmental cleanup project for sites under various regulatory frameworks. Projects at all stages of the cleanup
process can benefit from the use of a robust SPP effort throughout the life cycle of the project, beginning with site assessment
and investigation and continuing through cleanup design and implementation, and even long-term remediation system
optimization.

While Triad's emphasis on more comprehensive upfront SPP may increase initial project resource requirements, projects with
SPP efforts performed at collaboration-intensive stages of the project can save significant time and costs, provide more
defensible decisions as the project progresses, and ultimately result in more effective and efficient cleanup. The success of
SPP under Triad results from establishing consensus on the Baseline GSM and a clear exit strategy, and focusing and
adjusting resources based on project needs driven by the life cycle evolution of the GSM. Additionally, the use of DWS and
real-time measurement technologies help improve project efficiency during implementation while at the same time improving
decision certainty. Achieving stakeholder consensus on reuse goals and the strategy and plan for site cleanup improves a
project team's ability to perform risk management, address redevelopment concerns, ensure the scientific and legal
defensibility of results, and achieve site closeout as efficiently as possible.

FREQUENTLY ASKED QUESTIONS

How does SPP under Triad differ from conventional approaches to project planning?
Relative to traditional  project execution, SPP under Triad stresses up-front involvement and buy-in of all stakeholders (that is,
social capital) that could potentially affect site decisions during the entire project life cycle.  Stakeholder focus is on developing
an exit strategy intent on reaching project objectives or goals quickly and in a cost-effective manner while maximizing
resources and protectiveness. The value of building team trust and demonstrating technical competence among interested
parties cannot be  overstated. Stakeholder involvement in SPP under Triad allows the identification and management of non-
technical factors that can have significant project impacts at the beginning of the project, as well as at critical planning-
intensive project phases. The process seeks to educate all team members on the technical and economic implications of
meeting individual stakeholder needs so that the team can develop an exit strategy that is amenable to all members. SPP
under Triad also places greater emphasis on the use of a GSM that evolves to support specific project phases, the use of
DWS, real-time measurement technologies, collaborative data sets, and unique procurement characteristics.  SPP under Triad
seeks to  identify project goals and subsequent data needs clearly and specifically to utilize coordinated data collection efforts
to indicate what needs to be done at a site.  Triad SPP minimizes surprises, conflicting data, changes in stakeholders' roles,
and the effects of  personnel changes.

How do project managers address SPP during procurement fora Triad project?
Triad practitioners are developing a growing collection of information about the implementation of Triad best management and
technical practices, such as SPP. Project managers should plan for and allocate resources necessary to complete SPP and
associated work products, including  GSM visualizations, DWS decision logic diagrams and DMAs. Specifically, the dynamic

Office of Solid Waste and Emergency                                                                 EPA542-F-10-010
Response (5203P)                                         9                                          September 2010
                                                                                            www.brownfieldstsc.org

-------
                                        Use of Systematic Project Planning Under a Triad Approach for Site Assessment and Cleanup
nature of Triad-based projects require that relevant procurement issues be addressed—namely, to provide the flexibility and
adaptability during project implementation that is crucial to the success of a Triad project. EPA has summarized some of the
available options in a document entitled Understanding Procurement for Sampling and Analytical Services Under a Triad
Approach, available at www.brownfieldstsc.org/procurement.cfm that highlights methods and strategies that have been
successfully used to procure technical services under a Triad framework.  This document includes examples and lessons
learned from actual Triad projects implemented in the federal, state, local and private sector arenas.

What are some the keys to success in Triad procurement efforts?
    •   Involving the contracting staff in the planning process before the final procurement strategy is identified. Experienced
        contracting staff can identify the best contract mechanism and approach to provide for the flexibility and adaptability
        required  under the Triad approach while maintaining appropriate controls over the contract and the project.

    •   Using unit costs to allow better estimation and tracking of project costs.  A unit cost under Triad is defined as a
        combination of discrete activities managed together that can be used as a basis for estimating and tracking costs.
        Unit costs are  typically vendor-specific but can be customized to meet the specific needs of a project.  Developing
        options and unit rates based on the anticipated data needs of a project will increase the flexibility of procurement and
        project efficiency. A planning process that allows decision-makers to understand the specific services and equipment
        to be provided and the associated 'units' is essential for a successful procurement.  For example, using unit costs in
        a Triad project allows the project manager flexibility in ordering field services while at the same time being able  to
        calculate costs. The contractor will provide unit costs for each type of activity, e.g., $2,000 per day for direct push
        soil sampling.  The project manager then orders the amount via technical direction, such as conducting up to 10 days
        of services during one or more 10-day field effort cycles.

    •   Clearly identifying how flexibility will be incorporated into the project while maintaining control over overall  project and
        contract objectives. This requires up-front planning to establish (1) clear decision criteria for  data collection; (2) clear
        methods and lines of communication to  facilitate rapid decision-making, including real-time meetings and effective
        coordination among decision-makers; (3) a clear understanding of the cost implications of scope changes and how
        optional tasks  will be triggered  and managed; (4) a rationale for 'ranges' of samples to be collected and analyzed;
        and (5) clear decision  rules for how sampling locations may be determined and revised in the field.  Using unit costs
        within a fixed budget, Triad teams can identify initial sampling locations, technologies and analyses, use a DWS to
        place additional locations or collect collaborative data, and end with a maximum or threshold value for the number of
        locations and analyses a procurement and/or field effort can accommodate.

    •   Considering use of a two-part approach to procurement in which the up-front development of the Preliminary GSM and
        the SPP (including the Baseline GSM and DWS) are procured as a separate activity from the field implementation
        services can assure the project scope is  well-defined before funds are allocated.  A two-part approach can provide the
        buyer with several advantages.  For example, if the buyer does not possess the necessary technical expertise, this
        approach gives the buyer the ability to procure the expertise needed to develop a DWS with sufficient technical detail for
        the statement of work to procure the field services. In addition, this approach gives the buyer the ability to increase
        competition for the work by allowing a broader universe of contractors to bid on the field work component. A two-part
        approach is also useful in cases where different contractors have different skills and areas of expertise.

What tools are available to help with SPP?
There are a variety of tools and strategies to assist project teams with SPP at EPA's Triad Best Management Inventory
available at www.triadcentral.org/ref/ref/index.cfm.These tools are comprehensive and are not intended to list required
activities for SPP under Triad but rather to identify many of the issues that should be considered or addressed.  Users are
encouraged  to evaluate the potential effect on their projects from items in these checklists and inventories to determine which
have the greatest potential effect on project success and then apply resources appropriately to address these.

At contentious sites or those with team functionality  problems, the use of a third-party facilitator with Triad expertise can
provide tremendous advantages to  move projects from historical impasses toward a common goal.  The facilitator can assist
each side with technical or non-technical issues,  encourage all sides to articulate project needs,  and then work with
Office of Solid Waste and Emergency                                                                  EPA542-F-10-010
Response (5203P)                                         10                                           September 2010
                                                                                              www.brownfieldstsc.org

-------
                                        Use of Systematic Project Planning Under a Triad Approach for Site Assessment and Cleanup
stakeholders to develop actionable goals. Triad technical support and SPP facilitation is available through the BTSC technical
support team at www.brownfieldstsc.org/request support.cfm and interested stakeholders are encouraged to seek assistance
from experienced Triad practitioners such as members of the Triad Community of Practice (CoP) at
www.triadcentral.org/user/cop/.

Distance collaboration tools such as virtual meetings, Web conferences, ftp sites, and secure project team Web pages are
increasingly being utilized to facilitate SPP for Triad projects.  Traditional meetings can be augmented using these tools, thus
limiting the need for extensive travel or multiple live stakeholder meetings that can be logistically difficult to coordinate.
Although face-to-face SPP meetings are extremely valuable for social capital aspects of many Triad projects, these additional
resources provide economic and scheduling benefits by expediting document preparation and review, assisting with schedule
and budget development, technical scope development, and a host of other project components.

Triad project teams can also use simple tables to track, resolve and prioritize sampling and non-sampling uncertainties
identified during SPP (Figure 5).  These tables allow stakeholder and core technical team members to discuss potential
resolutions and assign responsibility to specific core technical or field team members to address sampling and non-sampling
uncertainties recognized during DWS planning. Prioritization of sampling  and information needs based  on these tables allows
development of activity sequencing to focus existing resources and plan for future efforts.

                                                       SiteXYZ
                          Uncertainties for which sampling is required (i.e., to be incorporated into the Work Plan)
No.
1








Uncertainty
XRF and ICP
correlations.

Field based action
levels?




Recommended
Resolution
TAL (metal)
XRF (Manufacturer, model,
software, source or x-ray
tube?)

Encourage contractor to
evaluate newer hand held
units to allow real time
measurement in the field.
Type of information
required
Demonstration of method
applicability.

Evaluate DLs, count times,
sample prep, matrix
variability.



Quality
SW-846 or CLP
collaborative
methods.

Develop XRF SOP?




Quantity
10-20% of total
XRF samples.

Front loaded QC
during DMA.




Responsibility
EPAHQ








Priority
High








                                         Uncertainties for which sampling is not required
No.
1
Uncertainty
Reuse scenarios for
processing area?
Reuse scenarios for
wetlands area?
Recommended
Resolution
Agree on industrial reuse
scenarios.
Develop recreational
exposure scenarios and
assess ecological risk.
Type of information
required
Signed agreement from EPA
region, township, state.
What records do we need?
Are hunters or fisherman
using resources as a food
source?
Quality
Signed agreement
from EPA region,
township, state.
State agreement to
restrict thee use of
annex area as state
managed resource?
Quantity
EPAHQ
8/2008
EPA risk
assessor USFWS
8/2008
Responsibility
High
Priority

Figure 5:  Project teams can use a relatively simple tool like this to track major sources of site uncertainty.  The recommended resolutions,
information requirements, and priority of uncertainties can be an effective tool for project and site decision-making.

Project managers are encouraged to identify resources for data management and decision assistance.  Although many
Decision Support Tools (DSTs) are beneficial for DWS, they are often identified during SPP and can support some planning
activities like sampling design and estimation of GSM certainty.  Project managers, site owners, environmental consultants
and others use DSTs in a variety of ways to support activities such as site assessment and remediation, data management
and visualization, and optimization.

Developing contingencies for drilling platforms, sample collection, sampling design, and field or laboratory analysis strategies
are also considered during SPP.  Since many project activities result in a few surprises and no project team can anticipate all
potential technical and non-technical issues that may arise, a simple process of prioritizing contingencies based on potential
impact to project success allows project teams to manage tasks and determine appropriate resources (Figure 6).
Office of Solid Waste and Emergency
Response (5203P)
11
      EPA542-F-10-010
       September 2010
www.brownfieldstsc.org

-------
                                        Use of Systematic Project Planning Under a Triad Approach for Site Assessment and Cleanup
                                                                         High
                                                                       i
                                                                       O)
                                                                       o
                                                                       O
                                                                        Low
                                                                                                        High
                                                                               Likelihood of Occurrence
                                                                   Figure 6: Example decision matrix for prioritizing
                                                                   project contingencies.  Project teams can use simple
                                                                   decision tools like this to determine the appropriate
                                                                   resources to apply to a project. Prioritizing and
                                                                   assessing the contingencies based on the degree of
                                                                   impact to the project and likelihood of occurrence is an
                                                                   effective way to manage uncertainty-based risks.
During Triad projects, DSTs have been used to assist project teams
in managing data, identifying sampling locations, groundwater
modeling, data contouring, managing uncertainty, and other critical
project aspects.  DSTs used in environmental applications also
include numerous statistical data and modeling packages, from both
commercial and public sources.  EPA recently published a matrix of
publicly-available DSTs including several that are beneficial to SPP
and available at www.frtr.gov/decisionsupport.

Simple decision assistance spreadsheets (Figure 7) allow
stakeholders to track and address GSM uncertainties, identify areas
of data needs, evaluate stakeholder consensus or outlier opinions,
determine when sufficient data have been collected, document
decision rationale, and screen potential remedial options for
effectiveness.  These spreadsheets are developed on a project-
specific basis based on technical and programmatic site settings,
project data objectives,  and desired outcomes. How questions are
phrased,  scoring ranges, and potential answers  must be agreed upon
by stakeholders.  In addition, all members must be committed to
consensus, engaged, and invested in the process in order to use these types of tools effectively.  At a minimum, when geared
toward answering principle GSM or study questions, these tools can be effective in highlighting areas of contention when
some stakeholders do not articulate concerns during SPP meetings. They can also identify, document, and rationalize
stakeholder positions.

How do you evaluate the effectiveness of SPP?
It is sometimes difficult to estimate when SPP efforts are sufficient to meet project goals and objectives. Ideally, SPP has
been most effective if it facilitates the project reaching a clearly-defined conclusion or other important stage acceptable to the
stakeholders. While there is always room for improvement, SPP is effective when sufficient information has been gathered,
reviewed, and used to structure a DWS so the potential for success is  high. For cost and timing reasons, it is desirable to
achieve as  much as possible or logical initially without the need for continual major adjustments and remobilizations.
Nevertheless, for even small efforts, some refinements will be needed  as more is learned. The key to successfully reducing
mobilizations, for example, lies in building in sufficient flexibility to the proposed approach and existing plans so some degree
of change can be managed in real-time.

Project teams can also waste time when documentation is insufficient and they have to redo work because the determined
result(s) cannot be adequately verified. Every job is unique; there is no one method for assuring  that SPP is complete.
However, some of the items that many projects have in common and products that can be expected from a thorough SPP
effort at the start  of a project include:
        Preliminary GSM to identify data gaps
        Defined roles and responsibilities
        Clear project goals and objectives
        Resource utilization plan
        Project schedule and milestones
        Plan to evaluate practical constraints
        (DMA design)
        Decision-making criteria and alternatives
        Focused QA/QC program design
                                                                 •   Consensus on identified data gaps and priorities
                                                                 •   Methods for data collection and communication
                                                                 •   Contingency plan for problem resolution
                                                                 •   Real-time data management and communication
                                                                     strategy
                                                                 •   Required level of documentation
                                                                 •   List of potential remedies and exit strategies
                                                                 •   Determination of and plan to assess performance
                                                                     metrics
Office of Solid Waste and Emergency
Response (5203P)
                                                        12
      EPA542-F-10-010
       September 2010
www.brownfieldstsc.org

-------
                                            Use of Systematic Project Planning Under a Triad Approach for Site Assessment and Cleanup
 Technical Factors
 T-1        Are all above-grade and/or sub-grade contaminant release tnechanism(s) identified at the site?       1.0       3-60-90%      3.00
             If the source of the original contaminant release is no longer in use, has it been properly
             decommissioned, abandoned, demolished, or removed
             If the facility is active, are routine leak test performed with adequate detection limits to prove that
             leakage is absent?
             If the facility is active, are routine accidental spills adequately contained to prevent a pathway to
             the subsurface?
 T-2       Is the presence of mobile -and/or residual-phase LNAPL in the vadose and saturated zones well     1.0       4 - >90%      400
           understood?                                                                                   Complete
             Have measurements of in-well LNAPL thicknesses been made in monitoring well(s)?
             Have soil and qroundwater samples been collected and physically observed for LNAPL?
             Have LNAPL indication tools (laser-induced fluorescence, ribbon sampler, Sudan IV dye, etc.)
             been used?
             Have contaminant partitioning equations been used to back-calculate the potential presence of
             free-phase LNAPL using soil and/or qroundwater sample results?	
 T-3       Is the source material (e.g., mobile-, residual-, or sorbed-phase contamination that emits mass to
    	the soil gas or groundwater) geometry well characterized?	
             Has the lateral extent of source material been defined to within an appropriate tolerance?
             Has the vertical extent of source material been defined to within an appropriate tolerance?
             Are inconnections of multiple sources, if present well characterized?
             Has contaminant distribution and lithology been correlated (e.g., is the LNAPL trapped within low
             permeability litholoqv)?
             Has the mass fraction of contaminants in the LNAPL-phase been estimated?
 Total Technical Factors	19.20%
 Maximum Possible Technical Factor Score                                                                                 26 40%
 Total Technical Factor Conceptual Site Model Certainty                                                                      72 7%
 Criteria that are answered "1 - <30% Complete" are highlighted in RED and, if given a high importance, should be further characterized.
 Criteria that are answered "2 - 30-60% Complete" are highlighted in Orange and, if given a high importance, should be further characterized.
 TOTAL SCORE INTERPRETATION
           The site is well characterized and suitable as a basis for remedial decision makinq.
           The site is adequately characterized and may be suitable for remedial decision making. Increased
 60-90%    certainty in some factors may be desired prior to remedy design.
           Site characterization is inadequate for use as a basis for most remedial action decisions. Additional
 30-60%    work is prudent to improve certainty.
           The site is poorly understood and should not be used as a basis for remedial decision making.
 <30%	Additional work is required to improve certainty.	
 Figure 7: Example of a CSM-based site decision tool.  This relatively simple yet sophisticated spreadsheet identifies and prioritizes
 further characterization and data needs at the site based on CSM certainty. The questions and scoring range used in the spreadsheet
 were developed based on site-specific project objectives and conditions.  Table provided courtesy of CH2M Hill.

How important is the CSM in the SPP Process?
Developing and evolving a CSM that addresses the unique needs of each major stage in a project's life cycle is essential to
any project's success. The core technical team should select a platform for the CSM that can be easily revised  as more site
information is learned, such  as geology, hydrogeology, well completions, sampling locations, and contaminant distributions.
Building a project information repository using a relational database tool is essential. Using a visualization platform, where site
information can be viewed in three dimensions, preferably in a temporal context, is a highly-effective method of
communicating, reaching consensus and building social  capital with stakeholders.  EPA information on data management and
interpretation tools is available at www.brownfieldstsc.org/pdfs/Management and Interpretation  of Data.pdf.

How does SPP ensure a cohesive team once work begins?
Developing a sense of teamwork and trust comes from well-defined roles and responsibilities.  Clear project goals and
objectives keep everyone on a project team, including stakeholders, engaged and confident that the project is moving in the
right direction.  Project resources should target areas where the highest uncertainties exist and the greatest social capital will
be realized.  Practical constraints must be tested to make sure a DWS is logistically viable and can flow smoothly.

Empowering field teams with pre-defined  decision  criteria and logic ensures that a project moves along with limited delays or
interruptions. A focused QA/QC program targeting the site conditions and uncertainties with the greatest potential to affect the
project results in efficient use of resources and  builds continued trust among the parties involved.  Real-time data sharing via
the internet continues to nurture  trust among all interested parties and allows for the development of strategies to resolve

Office of Solid Waste and Emergency                                                                         EPA542-F-10-010
Response (5203P)                                             13                                              September 2010
                                                                                                      www.brownfieldstsc.org

-------
                                       Use of Systematic Project Planning Under a Triad Approach for Site Assessment and Cleanup
problems quickly as they arise. A well-established executive record of documentation makes it possible for the decisions to be
independently verified once a project is complete.  The resulting documentation ensures that decisions are defensible and the
work will not need to be redone later.  Potential remedies and exit strategies are the end goal of most projects, so keeping
these items in the forefront of project planning provides maximum efficiencies.  As more is learned about a site and the GSM
is updated, the project team can focus on what is needed to achieve exit strategy success and shed excess efforts that
become less aligned with a project's needs.

How is SPP documented?
SPP is documented through a variety of formal and informal means.  The initial and perhaps most important SPP
documentation are the  Baseline GSM and accompanying uncertainty tables or other similar documentation. Additional
documentation includes Sampling and Analysis Plans (SAPs) and Quality Assurance Project Plans (QAPPs) that are
developed after the SPP effort. When written for a Triad-based investigation, these documents outline the SPP as an
important component of development of data collection schemes and uncertainty management strategies.  Communication
methods, such as memorandums, meeting notes and project team covenants formally document the SPP process.  These
methods are particularly useful to document stakeholder participation and buy-in for Triad-based investigations.  Informal
communication methods such as project websites and electronic bulletin boards help facilitate information exchange in
support of the SPP process.  Informal methods also help accelerate problem resolution compared to formal document
comment,  revision, and submission schedules.

SUMMARIES OF SUCCESSFUL SPP

Example 1:  Cache La Poudre River Site, Fort Collins, Colorado
  An effective SPP effort combined with the development and life cycle revision of a GSM allowed separate project teams
  to achieve and maintain site consensus, enabling them to make critical decisions in support of successful characterization
  and remediation of a highly-complex DNAPL site.
In May 2003, EPA Region 8 initiated a Targeted Brownfield Assessment (TBA) to further evaluate environmental issues
related to the Cache La Poudre River Site (Site), a former manufactured gas plant (MGP) located in Fort Collins, Colorado.
The existence of dense non-aqueous phase liquids (DNAPL) beneath the City of Fort Collins (City) property had not yet been
well-documented, nor was the transport mechanism understood as to how this material was reaching the river. A Triad
Approach project was recommended to expand sampling and analytical coverage at the Site including use of SPP, a DWS
and real-time measurement technologies to complete the delineation and evaluation of transport pathways for contaminants.

The project leveraged all  key SPP elements, including developing social capital through a stakeholder group and a series of
site planning meetings, identifying project objectives, and designing sampling and data management activities to achieve
project objectives.  Prior to SPP, the core technical  team developed a Preliminary GSM based on a review of existing data
from previous investigations. The Preliminary GSM indicated that potential threats to human health and the environment
included discharge of contaminated groundwater to the river and direct contact with contaminated surface water and
sediments.

During Preliminary GSM development, the core technical team noted that previous bedrock surface maps for the Site were
problematic and led to a number of conflicting theories of contaminant migration from the upgradient former MGP, leading  to
the identification of significant uncertainties regarding the GSM. Stakeholders continued to disagree over potential sources of
DNAPL material detected in the river during the TBA field efforts, resulting in competing Baseline CSMs and each of the
parties pursuing slightly different investigative strategies for their portions of the project.  However, because of positive social
capital developed through the SPP effort, the stakeholders were able to use the interest in achieving a single GSM consensus
as a common basis for discussing and addressing these disagreements.  This collaboration enabled the core technical team
to define sampling and information collection strategies that targeted uncertainties and refined Site understanding.  By
acknowledging multiple CSMs,  addressed individual concerns and interests of the stakeholders were addressed, which helped

Office of Solid Waste and  Emergency                                                                EPA542-F-10-010
Response (5203P)                                        14                                        September 2010
                                                                                          www.brownfieldstsc.org

-------
                                        Use of Systematic Project Planning Under a Triad Approach for Site Assessment and Cleanup
to further build social capital and direct planned dynamic field activities to address data gaps associated with these competing
CSMs.

The core technical team solicited the involvement of all Site stakeholders in the development of a decision making strategy
that outlined data collection activities and critical decisions to reach site remediation and closure.  The City, in conjunction with
EPA, the former MGP property owners, and consultants representing each potentially impacted property within the study area,
identified the primary objective of establishing a connection between potential source areas at the Site and coal tar
contamination found in the adjacent river. A second objective was to assess a former municipal landfill at the Site for closure
in accordance with State of Colorado requirements. The core technical team designed data collection efforts to support these
objectives in anticipation of future redevelopment planned at the Site. The sampling and data management activities identified
during the SPP included a combination of both traditional field approaches and  DWS using innovative means for high
resolution data collection to assure the reliability of site decisions.

Working collaboratively on various portions of the project, all stakeholders reached consensus about the source of the material
found in the river, which resulted in refining the Characterization GSM.  Following the TBA activities, the potentially
responsible party (PRP) conducted a Superfund removal action to excavate contaminated materials found in river sediments.
At the same time, EPA conducted a site  assessment (SA) to further identify potential pathways and source areas for DNAPL,
obtain data to refine the Design GSM, determine the nature and extent of dissolved contaminants, and generate data to
support implementation of the proposed  remedy.  Removal  action and SA activities indicated MGP-related contaminants were
flowing above and within fractured bedrock and discharging to the river, and that more recent diesel and gasoline spills from
nearby gas stations and a fuel depot were acting as solvents or mobilizing agents to the viscous coal tar materials.
Stakeholders agreed to a remedial design in 2004 and construction of a sheet pile barrier with hydraulic controls and
groundwater treatment system was performed in early 2005.

The use of SPP benefitted the project in  several critical ways. SPP helped stakeholders work through areas of disagreement
towards a common goal.  The original judgmental sampling plan was cooperatively revised by the stakeholders during SPP, to
include use of a DWS and innovative field-based technologies, which significantly improved Site decision making compared to
traditional strategies and investigation methods.  The  life cycle revision of the GSM allowed  the core technical team to clearly
communicate gaps in available data and illustrate the  benefits of potential  sampling and data management activities.  The
combination of these BMPs directly facilitated the successful characterization and remedy construction of this highly-complex
site to the satisfaction of all stakeholders in 2 years. More information on this site case study is available at
www.brownfieldstsc.org/pdfs/PoudreRiverCaseStudY.pdf.

Example 2: Milltown Redevelopment  Site,  Milltown, New Jersey
  The SPP process allowed for integrated stakeholder involvement, resulting in expedited completion of the project, and
  enabling the site developer to confidently confirm a decision to continue development.
Milltown Redevelopment (Site) is a Brownfields site located in Milltown, New Jersey.  The City of Milltown (City) and Middlesex
County (County) were interested in restoring the Site to active reuse as soon as possible. A Stage 2 Site
Investigation/Remedial Investigation (SI/RI), as defined under New Jersey state guidance, was conducted using the Triad
Approach in 2004.  Triad was applied to evolve the Characterization GSM in a single investigation to determine any
outstanding issues and reduce uncertainty enough to determine whether redevelopment was economically feasible to the
satisfaction of Site stakeholders.

A diverse stakeholder group, consisting of representatives from Federal, state, and local agencies, as well as a potential site
developer, was formed to plan, conduct, and oversee the project.  The stakeholders identified several concerns through a
series of SPP meetings, including the potential presence of buried drums and materials and the management of the large
volume of data that would be generated by field analytical methods over a relatively short, 2-month time frame.  This allowed
the core technical team to target specific areas for higher density information and highlighted the need for a robust Baseline
GSM to target sampling at appropriate depths and locations.

Office of Solid Waste and Emergency                                                                 EPA542-F-10-010
Response (5203P)                                        15                                          September 2010
                                                                                            www.brownfieldstsc.org

-------
                                       Use of Systematic Project Planning Under a Triad Approach for Site Assessment and Cleanup
The primary project objectives identified by the core technical team during SPP included:  (1) define Site reuse restrictions;
(2) identify potential Site impacts to a nearby water body used for recreational purposes; and (3) estimate the cost of cleanup.
The core technical team also developed a Baseline GSM for use in understanding site geology, hydrology, contaminant
distributions, and the potential  completeness of pathway receptor networks.  As little was known about the Site's complex
history, the core technical team planned to use field-based measurement technologies in a DWS framework to focus
resources and increase the density of information in support of delineating potential source areas and groundwater plumes.
Analyses were to be performed using a field-based command center, laboratory and data  processing trailers.

The core technical team and stakeholders derived detailed procedures for decision making that would abide by the
requirements of the New Jersey Technical Regulations (Tech Regs)  and still allow for the  majority of work to be performed in
the field.  The learning curve was steep for the stakeholder group as a whole, because of the diverse backgrounds of the
stakeholder members.  The Tech Regs also posed a unique challenge  because they were developed to support primarily
fixed-base laboratory, multiple phase projects. A robust SPP effort enabled the core technical  team to address each of these
challenges  and an approach was developed that combined  several levels of data quality into a decision hierarchy, allowing
significant flexibility for the field team during execution of the DWS. The decision hierarchy consisted of three  different tiers.
Tier 1 included laboratory methods and reporting packages as described in the Tech Regs, Tier 2 included similar methods
performed in the field with less rigorous reporting packages, and Tier 3 included test kits and direct sensing tools.

The DWS was used to rapidly  delineate areas of concern (AOCs). Decision logic diagrams provided in  the DWS work plans
were used in conjunction with the Characterization GSM to guide investigative activities and data quality requirements, as well
as to guide 'step out' sampling activities to ensure that characterization was substantively  complete before leaving the field. In
less than one week the field team identified a leaking underground storage tank as the source  of the chlorobenzene plume,
had source material pumped out of the tank, and delineated the extent  of the plume.

Immediately preceding the field effort, the field team discovered a vat under a formerly used loading dock that had been
obscured by heavy brush. Although the vat may have been discovered during a conventional study, the DWS provided a
flexible means to adapt the sampling strategy immediately after the discovery was made in the field without modifying the
written plans.  The DWS provided clear direction to the field team and the means for quick concurrence on the sampling
strategy from  project stakeholders.  The chlorobenzene plume was then delineated in approximately 4 days after 63
groundwater and 28 soil samples were collected from 46 sampling locations.

As further data were collected  regarding the distribution of the contaminants, a secure, project-specific website on the EPA
Environmental Response  Team (ERT) Web server was used to update stakeholder understanding of the Site.  Maps were
posted, along with progress reports and information about meeting times and places. The website allowed stakeholders,
including those remote from the Site, to review tables and maps summarizing the core technical team's updated
understanding of the plume at  the end of each day and then provide  input for the next day's sampling.  In addition, daily and
weekly project briefing meetings were held with the stakeholders throughout the effort, strengthening project social capital and
facilitating shorter review times.

Through the SPP process and the integrated stakeholder involvement,  sufficient information was gathered in a single
mobilization to support a decision to continue with Site  redevelopment.  The field team was able to sample more than 400
locations in approximately 5 weeks.  At present,  several of the areas addressed during the cleanup are  ready for re-
development and only the chlorobenzene plume remains as a significant issue. The success of the effort was directly related
to the effectiveness of the SPP effort that included developing a Baseline GSM and related DWS, developing clear project
objectives,  and establishing clear roles and responsibilities,  decision  criteria and QA/QC requirements.

More information on this site case study is available on the Triad Resource Center website at
www.triadcentral.org/user/includes/dsp  profile.cfm?Project  ID=30.
Office of Solid Waste and Emergency                                                                 EPA 542-F-10-010
Response (5203P)                                        16                                          September 2010
                                                                                            www.brownfieldstsc.org

-------
                                       Use of Systematic Project Planning Under a Triad Approach for Site Assessment and Cleanup
Example #3: Hartford Hydrocarbon Plume Site, Hartford, Illinois
  The development of a Baseline GSM and DWS during SPP efforts, and the continual refinement of the GSM through the
  design phase of the project supported continual involvement of stakeholders in the decision making process, helping to
  optimize the site investigation, increase project efficiency and provide the basis for effective design.
In May 2004, the EPA signed a legal agreement with the Hartford Working Group (HWG) to investigate and clean up the
refined petroleum products associated with Hartford Plume Site (Site), located in Hartford, Illinois. In late 2004, the U.S. EPA
Superfund Technology Support Center (STSC) was asked to evaluate the planned approach for field activities at the Site. In
particular, the STSC was asked to review the site characterization results obtained using cone penetrometer testing (CPT)
technology equipped with a laser induced fluorescence tool (LIF). Utilizing the principles of the Triad Approach, EPA Region 5
on-scene coordinators (OSCs), State of Illinois Environmental Protection Agency (I EPA) representatives and members of the
HWG participated in an SPP effort.

The project required developing social capital through outreach and engagement of the stakeholder group, defining clear
project objectives, defining  regulatory threshold limit criteria that would drive the project, defining timelines and roles and
responsibilities, developing DWS for each portion of the investigation, and developing methods for communicating project
results and real-time data management activities. Representatives of HWG were included in SPP activities because of their
knowledge of Site conditions that might affect the design of remedial activities.  The working group met monthly throughout the
majority of the  project to solicit feedback and keep the stakeholders informed of results and the design of follow on activities.

Objectives were agreed upon in a series of SPP meetings with all five of the responsible parties and their consultants,
representatives from the state, EPA, and local village representatives. The EPA requested that STSC provide input to work
plans as they were  developed to identify key goals to be accomplished through the employment Triad. Because of the large
size of the Site and the complexity of the environmental issues, multiple work efforts were required and planned to be
implemented in a sequential fashion.

SPP began by developing a Baseline GSM based largely on a review of previous investigations conducted by consultants
representing both the EPA  and the HWG. The Baseline GSM was used to guide subsequent investigations to fill data  gaps
specific to agreed project objectives, as well as to identify geologic and hydrogeologic controls on the movement of vapors
and free product. Taking into consideration the product thickness across the Site, the hydrogeologic gradients, as well as the
project objectives, the proposed sampling plan was modified to target the boundary of the free product plume instead of
maintaining static grid sample locations.  Results from testing the Characterization GSM indicated that potential threats from
vapors would likely  be controlled by the proximity  of hydrocarbons to the surface and the permeability of the underlying
geologic formations. The sampling plan was amended to address data gaps made evident by the Characterization GSM,
which further helped identify resource needs at the Site.

The Preliminary GSM presentation was designed  to facilitate  agreement between parties involved with implementation of
characterization and remedial strategies for the Site.  Through refinement of the Baseline GSM, stakeholders reached
consensus on what was required to meet project objectives before new field activities were undertaken. Stakeholders then
agreed to outline a  path forward using a DWS, where applicable, to  make additional decisions to address data gaps through
refinement of the Characterization GSM.

Investigations were sequenced using a master schedule so data could be used to develop the Design GSM to support
remedial design.  Field-based technologies and real-time data management tools were utilized to fill data gaps and update the
Characterization  GSM.  The DWS focused on  areas of the Characterization GSM with the highest uncertainty,  primarily near
the edges of the plume in a downgradient direction and near the discontinuous edge of the conductive sand bodies located
beneath the Site. A primary project objective was met by addressing uncertainties about the removal of free product beneath
the Site by identifying where product thicknesses and hydrocarbon saturations were potentially the greatest.
Office of Solid Waste and Emergency                                                                 EPA 542-F-10-010
Response (5203P)                                       17                                          September 2010
                                                                                           www.brownfieldstsc.org

-------
                                      Use of Systematic Project Planning Under a Triad Approach for Site Assessment and Cleanup
Implementing an efficient remedy was supported by all elements of Triad. The aggressive use of SPP focused on refining the
GSM through its life cycle stages and efficiently communicating results was extremely important to the ultimate success of the
project.  A well-documented DWS, which clearly defined how data would be used to support decision-making, limited project
delays.  The collaborative use of differing sources of information, designed during SPP, improved project efficiency.  A
continuously updated Design GSM was used during a series of SPP meetings as the basis to scope additional work and
establish contingencies and options that might need to be built into the remedial designs planned at the Site. Social capital
was built through the regular meetings and the rapid nature with which the project was conducted.  Residential concerns were
addressed quickly  by EPA and the other stakeholders and issues mitigated as quickly as possible.  A full case study for this
site will be published in 2009 and be available at www.brownfieldstsc.org/publications.cfm.

SOURCES OF ADDITIONAL INFORMATION

Communities and project teams interested in implementing the Triad Approach are encouraged to contact the BTSC for more
information and for successful examples of Triad applications. More detailed information on SPP and on the Triad Approach
can be found in the Brownfields Technology Primer Series document Using the Triad Approach to Streamline Brownfields Site
Assessment and Cleanup, which is available at www.brownfieldstsc.org. Project profiles, case studies, and other information
on applying Triad within a variety of regulatory frameworks can be found at www.triadcentral.org.  The BTSC provides other
technical bulletins related to best management and technical practices embodied in the Triad approach such as Use of
Dynamic Work Strategies Under a Triad Approach for Site Assessment and Cleanup—Technology Bulletin and
Demonstrations of Method Applicability Under a Triad Approach for Site Assessment and Cleanup—Technology Bulletin.
Additional documents providing critical information on  related issues such as Green Remediation and Vapor Intrusion are also
available through the BTSC.

REFERENCES

Coleman, James S.  (1988).  Social Capital in the Creation of Human Capital, article in The American Journal of Sociology,
Vol. 94,  Supplement: Organizations and Institutions:  Sociological and Economic Approaches to the Analysis of Social
Structure, pp. S95-S120.

EPA.  (2008, August). Demonstrations of Method Applicability Under a Triad Approach for Site Assessment and Cleanup -
Technology Bulletin. Office of Superfund Remediation and Technology Innovation.  EPA 542-F-08-006.
www.brownfieldstsc.org.

EPA.  (2007, August). Considerations for Applying the Triad Approach, Hartford Area Hydrocarbon Plume Site, Hartford,
Illinois.  Office of Superfund Remediation and Technology Innovation.  EPA 542-R-06-008.

EPA.  (2007, May). Management and Interpretation of Data Technology Bulletin. Office of Superfund Remediation and
Technology Innovation. EPA542-F-07-001.  www.brownfieldstsc.org.

EPA.  (2006, February). Guidance on Systematic Planning Using the  Data Quality Objectives Process. EPA QA/G-4.
EPA/240/B-06/001. www.epa.gov/gualily/gs-docs/g4-final.pdf.

EPA.  (2006).  Triad Project Profile: Use of an On-site Laboratory and Decision Support Tools to Delineate a Range of
Organic Compounds and Metals in Soil and Groundwaterat the Milltown Redevelopment Site, Milltown, New Jersey.
www.triadcentral.org.

EPA.  (2005, March).  Workbook for Uniform Federal Policy for Quality Assurance Project Plans. Part 2A:  UFP-QAPP
Workbook.  EPA-505-B-04-900C.
www.epa.gov/fedfac/pdf/ufp wbk 0305.pdf.

EPA.  (2005, March).  Uniform Federal Policy for Quality Assurance Project Plans. Parti: UFP-QAPP Manual.  EPA-505-B-
04-900A. www.epa.gov/fedfac/pdf/ufp  gapp v1 0305.pdf.
Office of Solid Waste and Emergency                                                                EPA542-F-10-010
Response (5203P)                                       18                                         September 2010
                                                                                          www.brownfieldstsc.org

-------
                                      Use of Systematic Project Planning Under a Triad Approach for Site Assessment and Cleanup
EPA.  (2005). Innovations in Site Characterization Case Study:  The Role of a Conceptual Site Model for Expedited Site
Characterization Using the Triad Approach at the Poudre River Site, Fort Collins, Colorado. Office of Superfund Remediation
and Technology Innovation.  EPA 542-R-06-007.  www.clu-in.org.

EPA.  (2003, June).  Using the Triad Approach to Streamline Brownfields Site Assessment and Cleanup. Brownfields
Technology Primer Series.  EPA 542-B-03-002.  www.brownfieldstsc.org.

EPA.  (2002, December). Guidance for Quality Assurance Project Plans. EPA QA/G-5. EPA/240/R-02/009.
www.epa.gov/quality/qs-docs/g5-final.pdf.

EPA.  (2000, May). EPA Quality Manual for Environmental Programs. CIO 2105-P-01-0 (formerly 5360 A1).
www.epa.gov/irmpoli8/ciopolicy/2105-P-01-0.pdf.

Pretty, Jules.  (2003). Social Capital and the Collective Management of Resources; article in Science, Viewpoint, Vol. 302, p.
1913,12 December 2003.

Triad Resource Center.  (2008).  Accessed July 2008, from www.triadcentral.org.

NOTICE AND DISCLAIMER

This bulletin was prepared by EPA's Office of Solid Waste and Emergency Response under EPA Contract Nos. 68-W-02-034
and EP-W-07-078. The information in this bulletin is not intended to revise or update EPA policy or guidance on how to
investigate or cleanup sites.  Mention of trade names or commercial products does not constitute endorsement or
recommendation for use. This bulletin can be downloaded from  EPA's Brownfields and Land Revitalization Technology
Support Center at www.brownfieldstsc.org.
                                   For technical inquiries regarding this bulletin, contact:

                                         Stephen Dyment, EPA OSWER/OSRTI
                                       dvment.stephen@epa.gov or 703.603.9903

                                          Michael Adam, EPA OSWER/OSRTI
                                        adam.michael@epa.gov or 703.603.9915
Office of Solid Waste and Emergency
Response (5203P)
19
      EPA542-F-10-010
       September 2010
www.brownfieldstsc.org

-------