United States      Office of Environmental    EPA/240/B-05/001
            Environmental Protection   Information          January 2005
            Agency	Washington, DC 20460	
v>EPA     Guidance on Quality
            Assurance for
            Environmental Technology
            Design, Construction,  and
            Operation
             EPA QA/G-11

-------

-------
                                    FOREWORD

       The U.S. Environmental Protection Agency (EPA) has developed an Agency-wide
Quality System, which is authorized by EPA Order 5360.1 A2 (U.S. EPA, 2000a).  The Order
provides that all environmental programs performed by or directly for EPA are to be supported
by individual quality systems that comply fully with the American National  Standard
Specifications and Guidelines for Quality Systems for Environmental Data Collection and
Environmental Technology Programs [American National Standards Institute/American Society
for Quality Control (ANSI/ASQC) E4-1994] (ANSI/ASQC, 1994).  While previous guidance
and requirements documents published by EPA have focused primarily on quality systems for
environmental data collection, this Guidance on Quality Assurance for Environmental
Technology Design, Construction, and Operation describes how to develop a quality system for
environmental technology programs.

       This document provides guidance to EPA program managers and planning teams as well
as to the general public as appropriate. It does not impose legally binding requirements and may
not apply to a particular situation based on the circumstances. EPA  retains the discretion to
adopt approaches on a case-by-case basis that differ from this guidance where appropriate.  EPA
may periodically revise this guidance without public notice.

       This document is one  of the U.S. Environmental Protection Agency Quality System Series
documents. These documents describe the EPA policies and procedures for planning,
implementing, and assessing the effectiveness of the Quality System. After five years from the
date of publication, EPA plans to review this document and either reissue it without
modification, revise it, or remove it from the U.S. Environmental Protection Agency Quality
System Series documents. Questions regarding this document or other Quality System Series
documents should be directed to the Quality Staff at:

                    U.S. EPA
                    Quality Staff (2811R)
                    1200 Pennsylvania Avenue, NW
                    Washington, DC 20460
                    Phone: (202)564-6830
                    Fax: (202)565-2441
                    E-mail: quality@epa.gov

Copies of the Quality System  Series  documents may be obtained from the Quality Staff directly
or by downloading them from its Home Page:

                                 www.epa.gov/quality
EPAQA/G-11                               iii                                January 2005

-------
EPAQA/G-11                                   iv                                    January 2005

-------
                                       PREFACE

       Guidance on Quality Assurance for Environmental Technology Design, Construction,
and Operation provides a technical overview for applying quality assurance (QA) and quality
control (QC) practices to engineering projects involving environmental technologies, an all-
inclusive term used to describe pollution control devices and systems, waste treatment processes
and storage facilities, and site remediation technologies and their components that may be
utilized to remove pollutants or contaminants from or prevent them from entering the environ-
ment.

       This guidance document is intended for use by technical managers and QA staff
responsible for engineering design, construction, and operation, by: (1) providing basic
guidance on applicable QA and QC practices; (2) outlining engineering planning, construction,
and operation processes that may require QA and QC elements; and (3) identifying resources and
references that may be utilized by environmental professionals during the design, construction,
and operation of environmental technologies.

       The guidance discussed is non-mandatory and is intended to be a technical engineering
and QA guide for project managers and QA staff in environmental programs to help them to
better understand when and how QA and QC practices should be applied to engineering work.
That is, it is a resource for users to help them understand the range and scope of QA and QC
practices in support of environmental technologies.  This guidance is not written exclusively for
engineers even though highly-technical engineering terminology and recognized good
engineering principles/practices are used, but may be used by managers with non-engineering
backgrounds. As a further aid, the guidance uses and refers to applicable basic quality principles
when discussing the application of QA and QC during a project.

       Accordingly, this guidance should not be regarded as an engineering manual or as a
complete reference on basic quality principles.
EPAQA/G-11                                 v                                 January 2005

-------
EPAQA/G-11                                   vi                                    January 2005

-------
                          TABLE OF CONTENTS

                                                                   Page
PREFACE	v

CHAPTER 1. INTRODUCTION                                            1
      1.1    PURPOSE AND OVERVIEW  	1
      1.2    BACKGROUND	1
      1.3    INTENDED AUDIENCE 	2
      1.4    TERMS AND DEFINITIONS	3
      1.5    PERIOD OF APPLICABILITY 	3
      1.6    ORGANIZATION OF THIS GUIDANCE DOCUMENT 	4

CHAPTER 2. GENERAL QUALITY SYSTEM PRINCIPLES                     7
      2.1    INTRODUCTION	7
      2.2    GENERAL GUIDING PRINCIPLES	7

CHAPTER 3. PLANNING AND MANAGEMENT                              9
      3.1    PURPOSE AND OVERVIEW  	9
      3.2    QUALITY SYSTEM DESCRIPTION 	9
      3.3    ORGANIZATIONAL STRUCTURE/CHAIN-OF-COMMAND AND
           RESPONSIBILITIES  	10
      3.4    PROJECT TEAM STAFFING  	11
      3.5    COMMUNICATION STRATEGY/PROCEDURES 	13
      3.6    DOCUMENT AND RECORDS CONTROL  	13
           3.6.1  Document Preparation, Review, Approval, and Issuance	14
           3.6.2  Document Distribution and Use 	14
           3.6.3  Document Changes 	15
           3.6.4  Document and Record Storage and Archiving Methods/Criteria  	15

CHAPTER 4. DESIGN OF SYSTEMS                                      17
      4.1    PLANNING AND THE DESIGN PROCESS	17
           4.1.1  Feasibility Studies and Reviews (FSRs) 	19
           4.1.2  Resource Identification and Allocation	20
      4.2    ORGANIZATIONAL AND TECHNICAL INTERFACES	20
      4.3    DESIGN INPUTS  	21
      4.4    DESIGN PROCESS	22
      4.5    DESIGN OUTPUTS 	23
      4.6    DEVELOPMENT OF SYSTEM OPERATION AND MAINTENANCE
           PROCEDURES 	23
      4.7    REVIEW OF DESIGN AND CONSTRUCTION/OPERATIONAL
           ALTERNATIVES	24
      4.8    DESIGN DOCUMENTATION 	25
      4.9    DESIGN VERIFICATION 	25

EPAQA/G-11                          vii                           January 2005

-------
                       TABLE OF CONTENTS (continued)

                                                                         Page
      4.10   DESIGN VALIDATION AND APPROVAL	27
      4.11   DESIGN CHANGES	28

CHAPTER 5. CONSTRUCTION/FABRICATION/INSTALLATION
             OF SYSTEMS AND COMPONENTS                               29
      5.1    INTRODUCTION	29
      5.2    SITE SELECTION AND DEVELOPMENT  	30
      5.3    REVIEW OF RESOURCES  	30
            5.3.1  Financial Resources	31
            5.3.2  Human Resources  	31
            5.3.3  Construction Materials	31
            5.3.4  Supplier Manufacturing Capabilities	32
      5.4    CONTRACTUAL ARRANGEMENTS  	32
      5.5    QUALITY PRACTICES IN PROCUREMENT ACTIVITIES 	35
            5.5.1  Quality Practices in Procurement Planning	36
            5.5.2  Quality Practices in the Evaluation of Suppliers	36
            5.5.3  Quality practices in Proposal Technical Evaluation 	37
            5.5.4  Quality Practices in Work Plans and Other Documents 	37
            5.5.5  Quality Practices in Document Review and Approval 	38
            5.5.6  Considerations in Evaluating Supplier Quality Management Capability 38
            5.5.7  Quality Conditions in Acceptance of Items or Services 	38
            5.5.8  Quality Considerations in Control of Supplier Nonconformance	39
            5.5.9  Quality Considerations in the Use of Commercial-Grade Items	40
      5.6    SCHEDULING AND TRACKING	40
      5.7    COST MANAGEMENT	41
      5.8    MATERIALS MANAGEMENT	41
      5.9    INSPECTION, TESTING, CONTROL, AND TRACKING  	42
      5.10   COMPLETION APPROVALS	43

CHAPTER 6. SYSTEM OPERATION AND MAINTENANCE                     45
      6.1    INTRODUCTION	45
      6.2    PLANNING FOR O&M INPUT AND TRAINING	46
      6.3    O&M CONSIDERATIONS DURING DESIGN PHASE	46
      6.4    O&M CONSIDERATIONS DURING CONSTRUCTION/FABRICATION/
            INSTALLATION PHASE	47
      6.5    SYSTEM START-UP  	48
            6.5.1  Planning the Start-Up Program 	48
            6.5.2  Start-Up Activities	49
EPAQA/G-11                           viii                            January 2005

-------
                       TABLE OF CONTENTS (continued)

                                                                          Page
      6.6    NORMAL/ROUTINE OPERATIONS 	49
            6.6.1  Process Control  	50
            6.6.2  Control of Auxiliaries and Services	50
            6.6.3  Control of Operational Status 	50
      6.7    INSPECTION AND TESTING	51
            6.7.1  Qualifications of Inspection and Test Personnel	51
            6.7.2  Inspection and Testing Specifications	51
            6.7.3  Inspection and Test Status	53
      6.8    HANDLING, STORAGE, PACKAGING, PRESERVATION,
            AND DELIVERY 	54

CHAPTER 7. ASSESSMENT AND VERIFICATION                              55
      7.1    MANAGEMENT/TECHNICAL ASSESSMENT AND RESPONSE 	55
            7.1.1  Types of Assessments 	55
            7.1.2  Control of Nonconforming Items	57
            7.1.3  Corrective and Preventive Action 	58
      7.2    VERIFICATION AND ACCEPTANCE	59
            7.2.1  Verification Tools 	59
            7.2.2  Reconciliation of As-Designed and As-Constructed Projects	60
            7.2.3  Validation	60

REFERENCES	63

APPENDIX A.  TERMS AND DEFINITIONS  	  A-l

APPENDIX B   GOOD ENGINEERING PRINCIPLES/PRACTICES APPLICABLE
               TO ENVIRONMENTAL TECHNOLOGY  	B-l
EPAQA/G-11                            ix                             January 2005

-------
EPAQA/G-11                                   x                                   January 2005

-------
                                      CHAPTER 1

                                   INTRODUCTION

1.1    PURPOSE AND OVERVIEW

       The purpose of this guidance is to provide users with an understanding of the basic
quality assurance (QA) and quality control (QC) procedures that may be used in planning,
implementing, and assessing the design, construction, and operation of environmental
technologies, an all-inclusive term used to describe pollution control devices and systems, waste
treatment processes and storage facilities, and site remediation technologies and their
components that may be utilized to remove pollutants or contaminants from or prevent them
from entering the environment. This guidance is intended to complement the requirements
defined in the American National Standard Specifications and Guidelines for Quality Systems for
Environmental Data Collection and Environmental Technology Programs (ANSI/ASQC E4-
1994) (ANSI/ASQC, 1994) by (1) providing basic guidance on applicable QA and QC practices;
(2) outlining engineering planning, construction, and operation processes that may require QA
and QC elements; and (3) identifying resources and references that may be utilized by
environmental professionals during the design, construction, and operation of environmental
technologies.

       This document is not a manual on engineering design, construction, or operation.  Rather,
it is intended to be a guide for technical project managers and QA staff in environmental
programs to help them to better understand when and how QA and QC practices should be
applied to engineering work. That is, it is a resource for users to help them understand the range
and scope of QA and QC practices in support of environmental technologies. Accordingly,
while this guidance is not written exclusively for engineers, it does use highly-technical
terminology and may be used by managers with non-engineering backgrounds.  As a further aid,
the guidance uses and refers to good engineering principles/practices (GEPs) when discussing
the application of QA and QC during a project.  There are many other texts and manuals in the
literature that can provide more details on the subjects discussed in this guidance.

       Moreover, this document is non-mandatory guidance and all parts of the document may
be used with discretion.  It is not intended to imply any requirements for the use of
environmental technology. Such requirements are defined by appropriate environmental  statute
or regulation, or as part of an applicable extramural agreement (e.g., contract, assistance
agreement) or enforcement agreement, order, or other enforceable document.

1.2    BACKGROUND

       ANSI/ASQC E4-1994 defines a quality system as "... a structured and documented
management system describing the policies,  objectives, principles, organized authority,
responsibilities, accountability, and implementation plan of an organization for ensuring quality
in its work processes, products (items), and services." It further explains, "... the quality system

EPAQA/G-11                                 1                                  January 2005

-------
provides the framework for planning, implementing, and assessing work performed by the
organization and for carrying out required QA and QC."  The present guidance document
presents the basic quality elements for technology implementation.

       The U.S. Environmental Protection Agency (EPA) Quality System conforms to
ANSI/ASQC E4-1994 and bases the implementation of its Quality System on the principles and
practices found in this American National Standard. Part C of the E4 standard provides the
specifications for the design, construction and fabrication, testing, and operation of
environmental technology. As noted above, the term "environmental technology" includes
devices and systems used in environmental programs to duplicate environmental conditions for
test purposes or to control, prevent, treat, or remediate waste in process discharges (e.g.,
emissions, effluents) or the ambient environment. Usually, this term will apply to hardware-
based systems; however, it can also apply to general methods or techniques used for pollution
prevention, source reduction, or containment of contamination to prevent further movement of
the contaminants.

       Quality systems have been developed for a wide range of disciplines and industries.
Within the environmental community, most available guidance on the subject has focused
primarily on data quality issues.  In more recent years, this topic has been broadened to include
the full continuum of environmental projects.  For purposes of this document, the quality system
includes the development and implementation of comprehensive procedures as well as process
checks to ensure compliance with all aspects of environmental technology deployment. Included
in this scope are planning, design, procurement, fabrication, feasibility study, construction,
shakedown, operation, maintenance, and performance evaluation of environmental technologies.
Project management activities such as staffing, budget tracking, and organizational
communication are also included in this scope to the extent that they relate to the quality system.
Because quality assurance related to data generation and management is covered by existing
EPA Quality System guidance, that topic is not discussed in this document.  However, it is
assumed that whenever environmental data are needed to formulate design criteria or equipment
specifications or to evaluate technology performance, the appropriate QA and QC for
environmental data operations will be applied.

1.3    INTENDED AUDIENCE

       This document is intended to provide clear,  coherent, and user-friendly guidance for
project managers, engineering planning teams, and  QA staff.  Because it is technical in nature,
users  should have a general knowledge of the good engineering practices and basic quality
principles used.  Officials in EPA and other state and federal agencies, as well as non-
government organizations, may find it useful for implementing quality systems when deploying
environmental technologies.  The intended audience for this guidance includes QA officers, site
remedial project managers, persons responsible  for  site clean-ups, and other environmental
professionals involved with environmental technology design, construction, and operation. It is
designed to assist all those responsible for writing, reviewing, or approving quality management
plans  or quality assurance project plans for environmental technology  projects.

EPAQA/G-11                                 2                                  January 2005

-------
1.4    TERMS AND DEFINITIONS

       The following definitions indicate how selected key terms are used in this document. A
complete set of terms and definitions will be found in Appendix A.

       Constructor - The party assigned by the developer in charge of technology construction.
       The constructor's role should be specifically defined in the developer/constructor
       contract.

       Design team - The parties responsible for the design of an environmental technology
       application. Depending on the scope of the project, this may consist of one or more
       professionals employed by the developer, or it may include representatives of various
       contractors and subcontractors as well.

       Developer - The organization(s) responsible for site development and technology
       construction/implementation. The developer may be a single organization, as in the case
       of a site-specific treatability study for which the technology developer is also the site
       developer. In other cases, additional parties are involved,  especially in the case of a
       large-scale technology implementation.

       Good engineering principles/practices (GEPs) - A broad set of QA, conservation, and
       safety activities, techniques, and approaches that are commonly accepted throughout the
       engineering profession.

       Owner - The company or organization that has the lead role in the development of the
       project and implementation of the environmental technology in question.  The owner can
       be a private firm that actually owns the property, or it can be a site developer or
       architectural and engineering design firm that has been hired by the owner to manage the
       environmental technology installation from beginning to end, or it may be the private- or
       public-sector organization responsible for clean-up.

       Project team - The parties involved in the construction and/or operation of an
       environmental technology application.  Depending on the scope of the project, this may
       consist of one or more professionals employed by the developer, or it may include
       representatives of various contractors and subcontractors as well.

       Responsible party - An individual or organization that has contributed to contamination
       problems at a site or has assumed site responsibility and is therefore a participant in the
       environmental technology application.

1.5    PERIOD OF APPLICABILITY

       Consistent with the EPA Quality Manual for Environmental Programs (U.S. EPA,
2000b), after five years, EPA plans to review this guidance and either reissue it without

EPAQA/G-11                                 3                                  January 2005

-------
modification, revise it, or remove it from the EPA Quality System series. In addition, this
guidance may be revised within five years if EPA determines that such a need exists.

1.6    ORGANIZATION OF THIS GUIDANCE DOCUMENT

       The structure of this document is based on the organization used in Part C of the E4
standard:

              General
              Planning
              Design of Systems
              Construction/Fabrication of Systems and Components
              Operation of Environmental Technology
              Assessment and Response
              Verification and Acceptance of Systems

The remainder of the document is organized as follows:

              Chapter 2 presents general quality system principles and elements.

              Chapter 3 describes QA and QC practices that should be considered for project
              planning and management,  including quality systems and policies, organizational
              structure, project staffing, communication strategies, and document and records
              control.

       •       Chapter 4 addresses QA and QC practices and related activities that should be
              considered during the design of environmental technologies. Topics discussed as
              they apply to QA and QC include design process planning; organizational and
              technical interfaces; design inputs;  the design process and its outputs;
              development of operation and maintenance (O&M) procedures; review of design
              alternatives; design documentation; and design verification, validation, and
              changes.

       •       Chapter 5 describes QA and QC practices and related activities that should be
              considered during construction and fabrication of environmental technology
              systems and components. Topics discussed as they apply to QA and QC include:
              site selection; review of resources;  contractual arrangements; procurement of
              supplies, equipment, and services; scheduling and tracking; cost and materials
              management; inspection, testing, control, and tracking; and construction
              certification.

       •       Chapter 6 presents QA and QC practices and related activities that should be
              considered during the operations and maintenance phase of environmental
              technology deployment.  These include planning and training; O&M

EPAQA/G-11                                4                                  January 2005

-------
              considerations during the design, construction, fabrication, system start-up, and
              normal operations phases; inspection and testing; and handling issues.

              Chapter 7 describes quality system practices that should be considered for
              assessment and response during the course of a project as well as during
              verification and acceptance of systems.
EPAQA/G-ll                                  5                                   January 2005

-------
EPAQA/G-11                                   6                                   January 2005

-------
                                     CHAPTER 2
                    GENERAL QUALITY SYSTEM PRINCIPLES
                                      Verification
                                    and Acceptance
                               Assessment and Response
                                  Operation of Systems
                         Construction of Systems and Components
                                   Design of Systems
                                    Quality Planning
GENERAL GUIDING PRINCIPLES applicable to environmental technology design,
construction, and operation

2.1    INTRODUCTION

       This chapter provides an overview of QA principles applicable to process design,
construction, and operation.  Subsequent chapters will provide QA and QC specifications for
specific implementation stages.  While these topics can apply to a wide range of operations, they
have been tailored to meet the objectives of environmental technology design, construction, and
operation.

2.2    GENERAL GUIDING PRINCIPLES

       Quality assurance is the system of operations that provides the user with the knowledge
and assurance that project activities are likely to meet specific project objectives. In addition,
quality control activities document the level of quality obtained during process operations.
While the general environmental community has been provided with numerous guidance
documents that cover specific aspects of quality assurance for environmental data operations,
this guidance document breaks new ground by addressing quality assurance and quality control
for environmental technology applications.
EPAQA/G-11
January 2005

-------
       The following general guiding principles (which are adapted from the E4 standard)
underlay the structure and content of this guidance document:

       Quality planning - All work involving the design, construction, and operation of
       environmental technology should be planned, documented, and controlled as needed to
       achieve conformance with approved quality criteria.

       Design of systems - Processes and procedures should be established and implemented to
       ensure that environmental technologies are designed using sound engineering/scientific
       principles and appropriate quality standards.

       Construction of systems and components - Construction, fabrication, manufacture, and
       erection of systems and components should be performed under appropriately controlled
       conditions according to the drawings and specifications of the approved design.

       Operation of systems - Environmental technologies should be operated in accordance
       with approved design documentation and operating instructions and guides.

       Assessment and response - Work performed during the design, construction, and
       operation of environmental technology that affects quality should be assessed regularly to
       ensure that approved planning and design specifications and operating guides are being
       implemented  as prescribed.

       Verification and acceptance - The performance of environmental technology should be
       verified according to its intended use as documented in approved design specifications.
       When acceptance criteria are not met, deficiencies should be resolved and reassessments
       conducted as  necessary.

       Note that these principles span the three main phases of EPA's Quality System:  planning
(principles 1-2), implementation (principles 3-4), and assessment (principles 5-6).

       Each of these general guiding principles is supported by a set of applicable lower-tier
basic quality principles; these lower-tier principles will be detailed in the remainder of this
document.  In addition, at several points in  subsequent chapters, there will be lists of GEPs that
are pertinent to a particular topic. GEPs are a broad set of QA, conservation, and safety
guidelines that are common to all engineering disciplines and are included in this document as an
aid for those with an  interest in exploring a broader suite of engineering issues and approaches.
However, the primary focus of this document is on engineering QA topics.  See Appendix B for
a more complete list of several categories of GEPs that are most likely to be applicable to the
design, construction,  and operation of environmental technologies.
EPAQA/G-11                                 8                                  January 2005

-------
                                     CHAPTER 3
                          PLANNING AND MANAGEMENT
                                                        Quality Planning
                                                        •  quality systems and policies
                                                        •  organizational structure
                                                        •  project staffing
                                                        •  communication strategies
                                                        •  document and records control
                   ConstructippTof Systems   Components
                          Design of Systems
                          Quality Planning
              GENERAL GUIDING PRINCIPLES
3.1    PURPOSE AND OVERVIEW
 Basic Quality Principle
 Adherence to quality principles and practices in project management, not only in the planning
 stages but throughout the project, is key to the successful implementation of an
 environmental technology.	
       Basic to any technology design and implementation are the planning stages. Planning is
an organized activity, typically begun and driven by the manager to define how to design the
environmental technology; amass qualified personnel; acquire quality components and materials;
and construct, install, and ultimately operate and/or evaluate an environmental technology
meeting the appropriate quality criteria.

3.2    QUALITY SYSTEM DESCRIPTION
 Basic Quality Principle
 Every organization implementing an environmental technology should be driven by a policy
 that defines quality expectations.	
       Quality policies are usually defined at the highest level of a company, corporation, or
government agency. In order to ensure that quality performance is achieved, the organization
EPAQA/G-11
January 2005

-------
quality policy should state the requirement for employee integrity, confirm management's
commitment to meet contractual obligations, and place responsibility for quality with those who
perform the work.  An organizational quality policy should direct the employees to ascend to the
highest possible work ethic, and in turn the organization should provide the resources necessary
to achieve these expectations.

       The corporate or organizational quality policy should be connected to the type of
environmental technology to be tested, maintained, or operated through a project-specific quality
plan.  Identification of the needs and expectations of all involved parties or stakeholders should
be included. The project-specific quality plan is therefore used to guide personnel in performing
appropriate procedures, using specified equipment, and performing specified operational and
maintenance checks. Therefore, the purpose of this plan is to ensure that all  work will be
performed by qualified personnel, to ensure that project objectives can be achieved, and to
document design, construction, and operational quality.  This plan should be carefully reviewed
and scrutinized prior to project initiation.  Subsequent specifications in the plan should be
followed by all personnel. Deviations from planned procedures should occur only with
permission of the party responsible for technology implementation and should always be
documented and approved by QA and technical personnel before being implemented. The
project-specific quality plan for a technology evaluation, therefore, should reflect an agreement
reached among all parties prior to project initiation as to how a process will be evaluated and
how it will be determined to be successful or not successful.  The importance of this approved
and signed document is that it is an agreed-upon plan, laying down the ground rules of
technology implementation and/or evaluation prior to project initiation. This helps define
project objectives and defines how to achieve these objectives.

3.3    ORGANIZATIONAL STRUCTURE/CHAIN-OF-COMMAND AND
       RESPONSIBILITIES
 Basic Quality Principle
 Organizational structure should be defined at every level in which QA and QC activities are
 necessary.	
       The first level of organization for which appropriate QA and QC practices should be
defined is the project owner's organization.  This may be an individual, a private firm, or a
government agency.  The organizational structure should clearly indicate that project
management and QA responsibilities are separate and independent and should clearly define the
lines of communication for all parties.  Following this level is the organization of the individual
project to which the technology operation is to be applied.  Both project management and QA
personnel should report to the highest management levels.  Each program and/or project should
also provide resources designated for QA organizational leaders and QA assessments.
Responsibilities and authority of each level should be defined and individual responsibilities
should be outlined, including those of subcontractors (if any). This is important for those
instances when construction or operation of a technology is stopped because of quality issues

EPAQA/G-ll                                10                                 January 2005

-------
and operations reviewed due to unexpected occurrences.  It is also important that these entities
understand and commit to the organizational goals and project objectives.

       In the example of a hazardous waste site remediation project where a responsible party is
known, the site developer is typically the organization responsible for site development and
technology construction/implementation.  The developer may be a single organization, as in the
case of a site-specific treatability study where the technology developer is also the site
developer.  In other cases, additional parties are involved, especially in the case of a large-scale
technology implementation.  A site developer may subcontract with firms to perform site grading
and material handling; installation of infrastructure, such as sewers, foundations, footers, berms,
and lagoons; installation of specialized equipment, such as boilers or water treatment facilities;
and a variety of other functions. It is important that the site owner enlist the developer and its
subcontractors in following the quality goals and project objectives.

       A state or federal  oversight agency may be involved in projects including regulatory
compliance. For site-specific treatability studies,  a third-party evaluator contracted by the site
owner  or the regulatory agency may be involved.  Local community organizations and
environmental groups may also be involved in these types of evaluations and in full-scale
technology implementations.  The needs of all of these organizations, sometimes referred to as
"interested parties," should be addressed in the planning stages of the project.

3.4    PROJECT TEAM STAFFING
 Basic Quality Principle
 Different phases of a project call for staffing of appropriate and competent personnel for the
 following activities and organizations: site owner/management, design, construction, and
 operation.	
       The project owner/management may fill a variety of staffing roles depending upon the
scope of the project and the experience of the available personnel.  These roles may be limited to
project oversight by using the design firm as the project manager or may include roles in project
management, project design, portions of construction, and process operation. Design,
construction, and operation are likely to involve several organizations employing different
personnel for each of the separate stages. Engineering and design professionals are more likely
to be involved in everyday activities during design, while some of these same personnel are
likely to be in a supervisory or assessment role during construction and operation. Construction
personnel may be involved in the design phase to provide input to limitations on the design
posed by the site or by construction activities.  They may also provide training for system
operation.

       The owner functions include project management and, potentially, any of the other
functions previously described.  Therefore, project managers with sufficient experience in
environmental installations  are the primary project staff sought by the project owner. This

EPA QA/G-11                                 11                                 January 2005

-------
experience would typically include budgeting, scheduling, design reviews, personnel
management, and management of various subcontractors.  In addition, other support personnel
may be needed, including personnel knowledgeable in legal and regulatory requirements and
management controls associated with contracts and management of subcontractors.

       The project team involved in the design (e.g., the site owner, the design firm, and the
construction contractor) should work together to effectively establish and maintain procedures to
complete the definitions of specifications and control and to verify the design of the project to
ensure that specifications are met. Often,  engineers develop the specifications and the design
plans with input from the project owner, regulators, and other team members of interested
parties. Portions of the design may be farmed out to specially design firms as needed. The
project manager for the design firm should appoint personnel not directly involved in the design
to perform periodic design review, verification, and validation. Ideally, a team of experts should
perform design reviews at set intervals.

       Construction personnel should be competent and experienced in the types of construction
to be performed. Construction firms typically have personnel experienced in areas such as
materials handling, metal working, welding and pipe fitting, electrical and plumbing
installations, concrete work and masonry, and carpentry.  The construction contractor may use its
own personnel, subcontract specialty crafts (e.g., electrical and plumbing) or work requiring
specialized equipment (e.g., large cranes), or may utilize day labor (typically for manual labor
requiring a minimum of skill). It is the responsibility of the construction manager to ensure that
the personnel used are qualified and trained to perform the specific planned construction
activities.

       Operations personnel should be competent and experienced in operating environmental
systems similar to the planned project. These personnel may be current employees of the project
owner or may be new hires specifically for the project. Typically, either the design firm or the
constructor, or both, will assist the owner in training personnel on the operation of the system.

       Training programs should include training of management and field personnel to ensure
competency  in the required knowledge and skills necessary for technology deployment.
Subcontractors who are participating in the program should also be trained, including those
added to the program or project at a later date.  Training should be initiated by the project owner
early in the project design phase. Initial training should consist of an overview of the project
goals, QA specifications, and overall and project-specific organizational structure and lines of
communication. As the project progresses from design to construction, training programs and
procedures are constantly updated to cover construction activities, especially any that were not
anticipated in the initial procedures and training. This is often a good time to incorporate
"lessons learned" during the design and initial construction stages, especially in regard to
communication failures or modifications made to improve communication processes.  As the
project moves to the technology implementation phase, key training elements include technology
operational procedures, field responsibilities, and reporting of field operations.  How poorly or
how well systems are performing in the field is communicated to all appropriate personnel.

EPAQA/G-11                                 12                                  January 2005

-------
3.5    COMMUNICATION STRATEGY/PROCEDURES
 Basic Quality Principle
 Effective project planning and implementation depend upon good coordination among all
 parties, which, in turn, depends on effective communication among those same parties.
       The project should be viewed as a whole process from conception to completion, and an
overall communication strategy should be developed for the entire project. Critical information
should be communicated to the correct team members in a timely fashion.  Communication
strategies and procedures  related to technology operation, construction, and design are similar to
other areas of environmental management.  These include development and implementation of
overall program- and project-specific training procedures and implementation of chain-of-
command and lines-of-communication procedures built into the organizational hierarchy.

       During the development of a strategy for communication, mechanisms for ensuring that
communication is occurring throughout the project team should be implemented. This includes
communication with oversight agencies, the developer, the operator, the evaluator, local
communities, associated organizations, or others that have a vested interest in the project.  The
key is to ensure design and/or operation expectations are communicated to all personnel. The
goal should be an overall balance that ensures adequate dissemination of information while
avoiding over-communication.

3.6    DOCUMENT AND RECORDS CONTROL
 Basic Quality Principle
 Documents should be controlled to ensure that the correct documents are being used.
       For the purpose of this guidance
document, the term document control is
defined as the act of ensuring that
program/project-specific documents are
reviewed for adequacy, approved for release
by authorized personnel, and distributed to
and used at the location where the prescribed
activity is performed. Documents that should
be controlled are, at a minimum, those that
specify requirements, prescribe processes, or
establish the design of environmental
processes. Examples include drawings,
specifications, management plans, procedures,
technical reports, test reports, and any
documents pertaining to legal requirements (e.g.,
   Applicable GEPs include:
          backup/duplicate copies;
      •   maintaining/archiving electronic and/or
          paper copies;
      •   distribution/delivery/circulation list for
          control documents;
      •   document/records authentication and
          verification;
      •   document approval procedures; and
          reviews—peer, project level, program
          level, organizational, and legal.
  permits, codes).
EPAQA/G-11
13
January 2005

-------
3.6.1   Document Preparation, Review, Approval, and Issuance

       Project management should identify the individuals or organizations responsible for the
preparation, review, approval, and issuance of controlled documents.  Procedures for controlling
documents should be developed. These procedures should specify that the documents requiring
control be identified and that the documents then be assigned control numbers (e.g., the
document version) and dated. Where applicable, a master list of controlled documents may be
specified for a project (e.g., all design drawings and specifications). Regardless of whether a
master list is generated, document control numbers should be placed on each page of the
document along with the page number, date, and document version. A distribution list for
reviewers and/or document users should be incorporated into the document when possible.
Document control procedures should be implemented when documents are first prepared.

       Documents should be reviewed for adequacy, correctness, and completeness prior to
approval and issuance.  The organization requesting review should identify the specific review
criteria and any pertinent background information. Reviewers should be individuals other than
the document originator and should include the applicable technical specialist(s) of each
organization affected by the document being reviewed.  Other specialists in the fields of QA,
environmental compliance, and safety should also review the documents, as needed. The
document originator should specify the date that comments are due and, as warranted, the form
in which any comments should be transmitted (e.g., document markups, summary memos, or
electronic markups or review copies). The document review procedures should also specify the
approval process. In some cases, each reviewer may be requested to submit an approval when
all comments have been incorporated into the document and the final version  is satisfactory to all
reviewers.  In other cases, the document originator may be responsible for document approval
after incorporating review comments.

3.6.2   Document Distribution and Use

       The distribution and use of controlled documents and forms that document or prescribe
work, including changes and editorial corrections to documents, should be controlled to ensure
that current and approved copies are available for use by those persons doing  the work.  A
limited and known number of copies should be distributed. This is important to prevent
someone not on the distribution list from getting and using a copy that is later superseded but not
distributed to that individual. The effective date should be clearly identified on each controlled
document; when appropriate, the duration that the document is in effect should be indicated.
Documents should be used only for their intended purpose and any caveats  or exclusions should
be clearly marked on the document.  It is important that appendices, attachments, and footnotes
containing such information be included with all copies. As with the distribution and use of
controlled documents, the disposition of obsolete documents should be controlled to avoid
inadvertent use.
EPAQA/G-ll                                14                                 January 2005

-------
3.6.3   Document Changes

       Changes to documents should be reviewed and approved by personnel with similar
expertise to those that performed the original review and approval. Changes should be clearly
noted in the document, and document dates and subsequent versions should reflect that changes
have been made. Procedures for review should normally be the same as those used for the
original document. Minor changes, such as grammar, spelling, and minor formatting changes
would not normally require review.

3.6.4   Document and Record Storage and Archiving Methods/Criteria

       Records should be maintained to reflect the achieved level of quality for completed work
and/or to fulfill any contract or statutory requirements. Federal  records must be maintained in
accordance with applicable Federal records schedules. Record-keeping procedures should
specify what records are to be prepared, reviewed, authenticated, and maintained. Records
should be indexed and classified so that they can be expeditiously identified and retrieved.
Maintenance procedures for records should include provisions for retention, protection,
preservation, traceability,  and retrieval.  Retention times for Federal records are determined by
applicable Federal records schedules.  Other retention times should be determined based on
contractual or statutory requirements or management requirements, whichever is longer.
Documents should be stored in such a manner and location as to protect and preserve the
information contained in the documents. This means that records are to be protected from
damage, loss, and deterioration, whether the records  are in paper or electronic form or both.
Document identification and storage procedures should  ensure that documents can be traced to
their original source and are easily retrievable;  this calls for a systematic approach for document
storage. When evidentiary records are involved, chain-of-custody and confidentiality procedures
should be prescribed and implemented.
EPA QA/G-11                                15                                 January 2005

-------
EPAQA/G-11                                  16                                    January 2005

-------
                                     CHAPTER 4
                                DESIGN OF SYSTEMS
                                                         Design of Systems
                                                           design process planning
                                                           organizational and technical
                                                           interfaces
                                                           design inputs, process, and
                                                           outputs
                                                           development of system O&M
                                                           procedures
                                                           review of design and construction/
                                                           operational alternatives
                                                           design documentation,
                                                           verification, validation, and
                                                           approval
                                                           design changes
               GENERAL GUIDING PRINCIPLES
4.1    PLANNING AND THE DESIGN PROCESS
 Basic Quality Principle
 The engineering/design professional, contractor, or subcontractor (the design team) should
 establish and maintain documented procedures to control and verify the design of the
 "environmental technology" in order to ensure that QA specifications are met.	
       In the design phase of a project, the functional specifications stated during the conceptual
phase are given form, and documents are prepared to define the project for construction and
operation. Planning and managing the design effort involve elements of organization, staff
selection, management, control, and coordination aimed at achieving quality in the project.  The
developer or designee selects a design team, or at a minimum designates an individual, who will
serve as the design team leader for managing the design. The design team leader should prepare
design criteria that will outline the specifications of the design. It is important, therefore, to
define the design team organization and specify responsibilities required for its implementation.

       Crucial to the design criteria are project objectives that are developed for project
evaluation and detail the measurements or information suitable to meet developer specifications.
It is not adequate to state the objective; there should also be a description of the methods that
will be used to determine whether or not the objectives are achieved.  Precisely defining these
objectives will determine the ultimate ability of measuring project success.  The design team
should therefore define the ultimate goal of their operation when determining project objectives.
EPAQA/G-ll
17
January 2005

-------
       Questions that should be considered as part of project design include the following:  (1)
Is the operation a long-term technology for clean-up of a particular contaminant or site, or is it
for demonstration purposes? (2) Is this technology to be used at other, similar sites also under
the purview of the site responsible party? (3) Will design and construction phases be time
limited in order to meet operation specifications? (4) Who will operate and maintain the
technology?  (5) Who is ultimately responsible for ensuring that technology specifications have
been achieved and, if the technology is for clean-up efforts, who will be responsible for
certifying site clean-up?
       Design criteria should clearly state the
design staffing specifications and selection
criteria and provide the basic guidelines for
initiation and coordination of the design
process, for example, meeting schedules and
budgets while maintaining quality.  Activities
should then be assigned to qualified
personnel equipped with adequate resources.
These plans are updated as the design
evolves.

       Design criteria include the various
GEPs that will drive the design processes.
Designed procedures, equipment, structures,
and facilities should be flexible to the extent
possible to accommodate variations when
required. When toxic or highly dangerous
materials are involved, designs should
include sufficient safeguards with adequate
engineering controls for safe operation.
Interchangeability of resources, such as
materials, personnel, equipment, etc., should
be considered during the design planning
phase as a means to control project cost and
improve system reliability and resilience.
During the design planning stage, the
purchasing and procurement, fabrication and
construction, and the operations and
maintenance teams should be consulted to
avoid compromising financial, logistical,  or
technical situations, after the fact.

       Construction and deployment of an
environmental technology entails that
specific operations be followed and maintained.
  Planners and managers should strive to
  incorporate the following GEPs during design
  planning:
          fail-safe/intrinsically safe design of
          procedures, processes, equipment,
          structures, and facilities;
      •    flexible built-in designed procedures,
          processes, equipment, structures, and
          facilities;
          design of self-correcting procedures and
          processes;
          analysis of availability and
          interchangeability of all resources, such
          as materials, personnel, and equipment;
      •    automatic communication/notification
          procedures and processes among all
          team members;
          integration of planning, design,
          purchasing/procurement, fabrication,
          construction/installation processes, and
          O&M procedures and requirements;
          integration/optimization of human,
          material, energy, and economic
          resources and logistical, political, social,
          environmental, and technical factors;
          modeling and simulation of technical,
          logistical, economic, social,
          environmental, and political systems
          prior to, during, and after
          installation/implementation;
      •    sound project management
          principles/practices; and
      •    automatic shutdown of systems,
          equipment, and processes.
 Because many environmental technologies may
EPAQA/G-11
18
January 2005

-------
be innovative and may have undergone very little field testing, however, the design team is
responsible for achieving quality objectives during construction based upon previously set
standards and performance criteria and based upon their experience and ability to adjust designs
to adapt to new applications and to changing conditions. When the project involves retrofitting
or scale-up of an existing environmental technology, the design team should review and analyze
all available documentation related to the planning and implementation of the original design,
construction, and system operations, and if possible, interview and consult with the previous
design team staff. Incident reports and existing documentation should then be carefully
reviewed and analyzed to avoid potential pitfalls.

4.1.1   Feasibility Studies and Reviews (FSRs)

       In some cases, conceptualizing and planning for construction and deployment of
environmental technologies may entail the development and study of various alternatives.  This
may be particularly true when design decisions involve different choices of technology or
engineering approaches. These are often known as feasibility studies. Such activities are a joint
effort of the technology developer, design team leader, and, if available, the constructor and
operator. The resources spent in formulating, investigating, and studying alternative approaches
to decisions will vary depending on the size and complexity of the project.
       Prior to undertaking the formal design
and development activities, the design team
may conduct FSRs to gain full understanding
and establish a sound working knowledge of
the various technical, logistical, and economic
factors, challenges, and issues involved with
the deployment of the designated
environmental technology at the  specified
site.  Controls  and measures should be
defined, identified, and set in place to allow
updating of the various FSRs during the
course of design, construction, and operation
of the deployed technology.

       Technical feasibility studies include
life cycle analysis, environmental impact
statements, and investigation  of alternative
solutions. The various alternatives studied
will affect project performance and
appearance, life-cycle cost, cost/benefit ratio, schedule of completion, and socioeconomic and
environmental impacts. The number of alternatives chosen for examination, the extent to which
each is subjected to detailed planning evaluation, and whether more than one "preferred"
alternative is selected for final design are key decisions best made early in the project planning
and scoping process.
   In addition to the GEPs listed in Section 4.1,
   designers should consider the following GEPs
   when conducting the various FSRs:
          reuse of materials required for
          technology operation or development;
          reduced use of virgin materials, wastes
          generated, energy sources, and human
          resources;
      •   recycling/recovery of materials, utilities,
          and energy sources;
      •   conservation of materials and energy
          sources;
      •   substitution of materials and energy
          sources with cleaner, better, cheaper,
          more reliable, and more readily
          available alternatives: and
      •   use of interlocks as safety measures.
EPAQA/G-11
19
January 2005

-------
       Logistical feasibility studies include analyses of alternatives for the procurement,
distribution, deployment, maintenance, and replacement of materials and personnel.  Economic
feasibility studies include cost-benefit analyses and analyses of short- and long-term economic
impacts on the community and the region. Cost alternatives that should be carefully analyzed
and considered include design cost, capital cost of construction, operation and maintenance
costs, various life-expectancy or design-life periods, return on investment, cost comparison of
deploying the environmental technology on a full-scale basis versus deploying it in stages, value
of extra cost for aesthetics, and cost/benefit ratios.

       Feasibility studies allow for insight and investigation into all aspects that may impact
technology construction and operation. The FSRs, as stated previously, are important in
considering alternative solutions and determining whether those alternatives can offer a realistic
solution.

4.1.2  Resource Identification and Allocation

       Identification and allocation of resources, including personnel, should be performed
during design planning in order to ensure adequate resources will be available during
construction and operation of a technology. Resource requirements should specify the level of
quality needed to accomplish the stated objectives. The design team may include engineers,
scientists, and perhaps geologists or others familiar with the workings of the process and of the
site being considered for remediation; they should be trained in QA principles and in all standard
operating procedures governing their areas of responsibility. Each professional  discipline plays
a role in offering input into the technology design.  Identification and allocation of the correct
mix of design team professionals is therefore  crucial to achieving the project's technical as well
as economic success.

4.2    ORGANIZATIONAL AND TECHNICAL INTERFACES
 Basic Quality Principle
 Organizational and technical interfaces should be identified during planning stages and
 controlled appropriately during the design efforts.	
       Organizational and technical interfaces include organizations and individuals, such as the
site owner, regulatory agencies, design professional, construction/fabrication contractor,
equipment and materials supplier, and the technology operator.  When the project involves
retrofitting or scale-up of an existing environmental technology, to the extent possible, interfaces
with the previous designers, construction contractors and operators,  and suppliers should be
identified and incorporated into the prevailing organizational structure. Overall project and
technical organizational flowcharts should be used to identify the participating organizations and
individuals and their respective roles, responsibilities,  and authority.
EPAQA/G-11                                 20                                  January 2005

-------
       Typically, the design team leader keeps the developer and design team members
informed on the design's status, normally submitting monthly (or more frequent, if necessary)
progress reports to the owner. These reports contain information on meetings held and work
accomplished in the subject period. Most importantly, design problems and issues should be
recognized as early in the process as possible and reported to the appropriate decision makers
(e.g., technology developer); those problems that may cause a change in scope, budget, or
schedule should be promptly identified, documented, communicated, and resolved among the
participating parties.

4.3    DESIGN INPUTS
 Basic Quality Principle
 Prior to the start of the design phase, the owner and the design, construction, and operations
 teams, separately as well as collectively, should identify all pertinent design characteristics for
 the project.	
       Applicable design inputs, such as conceptual design reports, performance specifications,
regulatory requirements, codes, and standards should be documented and controlled by those
responsible for the design in accordance with the following specifications:

       •       Design inputs should be identified and documented and their selection reviewed
              and approved by those responsible for the design.
       •       Design inputs should be specified and approved on a timely basis and to the level
              of detail appropriate to permit the design work to be carried out correctly in a
              manner that provides a consistent basis for making design decisions,
              accomplishing design verification, and evaluating design changes.
              Changes from approved design inputs and reasons for the changes should be
              identified, approved, documented, and controlled.
       •       Design inputs based on assumptions that call for re-verification should be
              identified and controlled.

       During the design input phase, as part of the technical directives, the developer usually
outlines the desired GEPs (see box) that the design professional can incorporate into the design,
to the extent possible. In addition, early identification of appropriate codes and standards can
prevent reworking plans and specifications and save considerable cost and  delay. Codes and
standards are developed by governmental units  and industry or professional-technical
associations to protect the public's health and safety. Because codes and standards typically
address particular aspects of design, construction, and operation of a technology, the design team
can expect to find a number of codes and standards applicable to a project,  including those
pertaining to civil, mechanical, electrical, structural, and process engineering, as well as
architecture.  Applying codes and standards to the design may sometimes be difficult, especially
for design professionals working on a project in an unfamiliar geographical area (as in the case
EPA QA/G-11                                21                                  January 2005

-------
of a remote but hazardous or toxic waste
site), but is required in order to comply to
specified regulations.

4.4    DESIGN PROCESS
 Basic Quality Principle
 The responsible design organization(s)
 should define, manage, and document the
 design activities on a timely basis and to
 the level of detail appropriate to permit the
 design process to be carried out correctly,
 effectively, and in a timely manner and to
 permit verification that the design meets
 specifications.	
       The following issues should be
addressed as part of the design process:

       •      Design methods, materials,
              parts, equipment, and
              processes that are key to the
              function of the structure,
              system, or component should
              be selected and reviewed for
              suitability of application.
       •      Changes from all
              specifications and standards,
              including the reasons for the
              changes, should be identified, approved, documented, and controlled.
              Applicable information derived from experience, as set forth in reports or other
              documentation, should be made available to cognizant design personnel.
       •      If the design effort is to support an existing technology retrofit or scale-up, the
              designers should take into  account the design inputs, design outputs, and the
              actual performance of the existing products and processes against their respective
              design expectations. Such analyses provide a better understanding of the
              limitations of the technology and the challenges it is likely to face when
              retrofitted and/or scaled up.
   The following GEPs should be considered when
   establishing/developing the design inputs:
      •   reuse of materials required for
          technology operation or development;
      •   reduced use of virgin materials, wastes
          generated, energy sources, and human
          resources;
          recycling/recovery of materials,
          utilities, and energy sources;
          conservation of materials and energy
          sources;
          substitution of materials and energy
          sources with cleaner, better, cheaper,
          more reliable, and more readily
          available alternatives;
          use of commercially available and
          tested materials, products, processes,
          equipment, and supplies;
      •   computerized/remote control of unit
          operations and processes;
      •   use of lockout/tagout procedures and
          equipment during systems
          fabrication/installation and operations;
          and
      •   prevention of calamities through
          process hazard analysis, hazardous
          operations analysis, failure mode and
          effects analysis, fault tree analyses, and
          incident investigations.
EPAQA/G-11
22
January 2005

-------
4.5    DESIGN OUTPUTS
 Basic Quality Principle
 Design output should be documented and expressed in terms that can be verified against
 design criteria (including specific acceptance criteria) and validated.	
       Design output documents should:

       •       meet the design-input specifications,
       •       contain or make reference to acceptance criteria, and
              identify those characteristics of the design that are crucial to the safe and proper
              functioning of the technology and its components (e.g., operating, storage,
              handling, maintenance, and disposal requirements).

       Design output documents are usually reviewed and approved before release. The
distribution of the design output documents should be controlled and, where deemed critical,
verified.

4.6    DEVELOPMENT OF SYSTEM OPERATION AND MAINTENANCE
       PROCEDURES
 Basic Quality Principle
 O&M specifications should be considered in each phase of project planning, design,
 construction, and start-up.	
       In the preliminary design phase, decisions are made relating to site selection and access,
process choice, equipment selection, and other elements that impact operation and maintenance
of the completed project. Since decisions made here limit flexibility in subsequent phases of the
project, O&M coordinators and advisers should be consulted for choices of brands or models of
equipment to be selected, arrangements or layout of facilities, access for equipment repair,
routine operation and maintenance procedures, and other design features that influence O&M
costs and activities.

       Effective operation and maintenance entails up-front planning to ensure that products and
services will perform according to project specifications. The various stages of the project
(planning, design, construction, start-up, and operation) each involve input from O&M staff.
Roles of O&M staff are certainly weighted towards process operation, but if input is not
provided during planning or design, technology processes may suffer from over-design whereby
standard  "off the shelf equipment is not used, or they may  suffer from operations that are
difficult to maintain.  O&M staff input provides a "reality check" for the design and planning
stages  and provides assistance during construction and start-up.
EPAQA/G-ll                                23                                 January 2005

-------
       Environmental technology should be operated in accordance with approved design
documentation and operating instructions and guides. Designers should ensure that the
technology operating guides and manuals include, but are not limited to:

             appropriate controls for materials (including consumables) and measuring and
             testing equipment;
             configuration management;
       •      operating procedures and parameters for specific components and systems
             configuration, including specified safety limits;
       •      spill, fire, and other hazard safety procedures;
       •      process equipment control and maintenance, including specifications during
             abnormal conditions for inspection and test situations and fault and emergency
             conditions;
             special environments, time, temperature, or other factors affecting the quality of
             operation; and
       •      the skill, capability, and knowledge of operators to meet operational,
             environmental, and quality goals. This should be accomplished through the use
             of specific standards, resources, and worker training and certification.

4.7    REVIEW OF DESIGN AND  CONSTRUCTION/OPERATIONAL
       ALTERNATIVES
 Basic Quality Principle
 At appropriate stages of design (e.g., 30, 60, and 90%), formal documented reviews of the
 design are planned and conducted.	
       Design reviews or audits for purposes of validation are cornerstones of the design
professional's QA program. Design review can be carried out by members of the design team or
an independent review board selected for their expertise.  Design audits are performed by
individuals other than members of the design team. Design reviews or audits have the purpose
of establishing the levels of quality of the design by identifying unsound concepts, analyzing the
overall feasibility of the project, eliminating redundancies, and assisting in interdisciplinary
coordination. Participants at each design review should include representatives of all pertinent
functions/disciplines concerned with the design stage being reviewed, as well as other specialist
personnel, as required. Records of all such reviews should also be maintained.
EPAQA/G-ll                                24                                 January 2005

-------
4.8    DESIGN DOCUMENTATION
 Basic Quality Principle
 The design professional should establish and maintain documented procedures for
 identification, collection, indexing, access, filing, storage, maintenance, and disposition of
 design output documents including drawings, calculations, and results, as well as references,
 standards, codes, design basis, and assumptions used in the design process.	
       Under almost all circumstances, design results and outputs are checked, verified, and
certified by a qualified professional belonging to the pertinent discipline.  Peer and QA review
should be incorporated to ensure it will be understandable and meet specifications. When the
project involves technology retrofit or scale-up, the designer should recheck, re-verify and, if
determined to be critical for the current design, even re-certify the design results and outputs of
the preceding version of the technology. Design documentation and records, which provide
evidence that the design and the design verification processes were performed in accordance
with project specifications, should be collected, stored, and maintained in accordance with
documented procedures. The documentation includes not only final design documents (such as
drawings and specifications) and revisions thereto, but also documentation that identifies the
important steps, including sources of design inputs that support the final design. Maintaining
and ensuring quality during the design process entails that specific documentation standards be
followed so that appropriate and relevant information is conveyed to all personnel involved
during the design, construction, and operation phases of the environmental technology.

4.9    DESIGN VERIFICATION
 Basic Quality Principle
 The verification process evaluates the completeness, correctness, and conformance or
 compliance of the design in terms of meeting contractual, method, or procedural
 specifications.	
       At appropriate stages of design, design verification should be performed to ensure that
the design output meets the design stage specifications. The design verification measures should
be recorded. The following measures can be applied to verify the adequacy of the design:

       (a)    Design verification should be performed using one or a combination of the
             following methods:

                    •      performing alternative calculations (calculations or analyses that
                           are made using alternate methods to verify correctness of the
                           original calculations or analyses and the appropriateness of any
                           assumptions, input data used, any computer programs, or other
                           calculation methods used);
EPAQA/G-ll                                25                                 January 2005

-------
                     •       comparing with prevailing/proven design (for example, when the
                            project involves retrofitting or scale-up of existing technology);
                     •       testing under laboratory, field, or simulated conditions (for
                            example, treatability tests and/or mathematical modeling coupled
                            with computer simulation); and
                            reviewing the design stage documents before release.

       (b)     The particular design verification method should be identified and its use
              justified.

       (c)     The results of design verification should be documented, including the
              identification of the verifier.

       (d)     Design verification should be performed by competent individuals or groups other
              than those who performed the original design (but they may be from  the same
              organization). If necessary, this design verification may be performed by the
              originator's supervisor providing that:

                     •       the supervisor did not specify a singular design approach or rule
                            out certain design considerations and  did not establish the design
                            inputs used in the design,
                            the supervisor is the only individual in the organization competent
                            to perform the verification, and
                     •       the determination to use the supervisor is documented and
                            approved in advance.

       (e)     Design verification should be performed at appropriate times during the design
              process.

                            Verification should be performed before release for procurement,
                            manufacture, construction, or release to another organization for
                            use in other design work.
                     •       Design verification should be completed before relying on the item
                            to perform its function.

       (f)     The extent of the design verification should be based on the complexity of design,
              risk, uniqueness of the design, degree of standardization, technology's state of the
              art, and similarity with previously proven designs. When the design  has been
              subjected to a verification process in accordance with this standard, the
              verification process need not be duplicated for identical designs.
EPAQA/G-ll                                 26                                 January 2005

-------
       (g)     Use of a previously proven design should be controlled as follows:

                    •      The applicability of standardized or previously proven designs
                           should be verified with respect to meeting pertinent design inputs
                           for each application.
                           Known problems affecting standard or previously proven designs
                           and their effects on other features should be considered.
                    •      The original design and associated verification measures should be
                           adequately documented and referenced in the files of subsequent
                           application of the design.
                    •      Changes in previously verified designs prompt re-verification.
                           Such re-verifications should include the evaluation of the effects of
                           those changes on the overall previously verified design and on any
                           design analyses upon which the design is based.

       (h)     Design verification and approval should be performed in a timely manner.

4.10   DESIGN VALIDATION AND APPROVAL
 Basic Quality Principle
 Design validation is performed through assessments (see Chapter 7) to ensure that the
 designed products, processes, and procedures conform to defined user needs.	
       Validation is confirmation by examination and provision of objective evidence that the
particular requirements for a specific intended use are fulfilled. Typically, design validation
follows successful design verification and occurs prior to installation and/or final deployment.
When design adequacy is to be validated by qualification tests or pre-operational test runs, the
tests are identified and the test configurations are clearly defined and documented.  Testing
demonstrates adequacy of performance under conditions that simulate the most adverse design
conditions. Operating modes and environmental conditions in which the item should perform
satisfactorily should be considered in determining the most adverse conditions.  Test results
should be documented and evaluated by the responsible design organization to ensure that test
specifications have been met.  Test results should then be reviewed and validated by an
independent individual (outside the organization) technically competent to understand the
particular item or product under study.

       If validation testing indicates that modifications to the item are called for to obtain
acceptable performance, the modification should be documented and the item modified and
retested or otherwise validated to ensure satisfactory performance. When tests are performed on
models or mockups, applicable scaling laws are normally identified or established and verified.
The results of model test work are then subjected to error analysis, when applicable, prior to use
in final design work.
EPAQA/G-11                                27                                 January 2005

-------
4.11   DESIGN CHANGES
 Basic Quality Principle
 All design changes and modifications should be identified, documented, reviewed, and
 approved by authorized personnel before their implementation using clearly defined
 documented procedures.	
       Design changes should be controlled in accordance with the following instructions:
       (a)     Changes to final designs, field
              changes, and nonconforming
              items dispositioned "use as is"
              or "repair" should be justified
              and subject to design control
              measures commensurate with
              those applied to the original
              design.

       (b)     Design control measures for
              changes should include
              provisions to ensure that the
              design analyses for the item
              are still valid.
   Designers should consider the following GEPs
   when addressing design changes:
      •   worker training/retraining, including
          hands-on training;
          worker registration/certification;
      •   certification/permitting of work
          procedures, processes, equipment, and
          environment; and
          routine/periodic inspections, testing and
          compliance audits of systems,
          procedures, processes, equipment, etc.
       (c)     Changes should be approved by the same groups or organizations that reviewed
              and approved the original design documents.

       (d)     If a significant design change becomes necessary because of an incorrect original
              design, the design process and design verification methods and implementing
              procedures should be reviewed and modified as appropriate.  These design
              deficiencies should also be documented.

       (e)     Field changes should be incorporated into the applicable design documents.

       (f)     Design changes that affect related implementing procedures or training programs
              should be communicated to the appropriate organizations.
EPAQA/G-ll
28
January 2005

-------
                                     CHAPTER 5

                 CONSTRUCTION/FABRICATION/INSTALLATION
                          OF SYSTEMS AND COMPONENTS
                 Construction of Systems and Components I
                           Design of Systems
                            Quality Planning
                                                  Construction of Systems
                                                  and Components
                                                  • site selection and development
                                                  • review of resources
                                                  • contractual arrangements
                                                  • procurement
                                                  • scheduling and tracking
                                                  • cost management
                                                  • materials management
                                                  • inspection, testing, control,
                                                    and tracking
                                                  • completion certification and
                                                    approval
5.1
        GENERAL GUIDING PRINCIPLES

INTRODUCTION
 Basic Quality Principle
 Quality in the construction, fabrication, and installation phase of a project is achieved by
 establishing, implementing, and maintaining documented procedures to control and verify that
 technical specifications and QA and QC criteria are met.	
       Project planning for the construction, fabrication, and installation of an environmental
technology should be undertaken by the developer or the lead agency.  The technology developer
may decide to contract with a design professional or the constructor to perform the design and
planning activities. Once design and planning activities are completed, the developer may then
contract with a construction professional to fabricate the environmental technology. Alternately,
the technology developer may perform these assignments "in-house."  Either method involves
being responsible for specific compliance with the specifications for the project, including
planning and enforcement of site safety programs (designated in a separate health and safety
plan); means, methods, and sequencing of construction; management; meeting applicable codes,
permit requirements, and other public agency regulations pertaining to his/her operations; and
quality control related to construction activities as discussed in this chapter.
EPAQA/G-ll
                                    29
January 2005

-------
5.2    SITE SELECTION AND DEVELOPMENT
Basic Quality Principle
Project site specifications should be
established and documented.



Site selection and development
activities may take place during the planning
and design phases. It should be confirmed,
for example, that site selection is appropriate
for the specific environmental technology
being constructed based upon levels of
c? r
contamination present at the chosen site.
Other aspects of site development typically
include, but are not limited to, construction of
access roads; extension of utilities to the site;
traffic control measures including detour
routes; and relocation of utilities, highways,
and other facilities. Utility extensions and
relocations are frequently performed by the
applicable utility, although such activities
may be included in the overall project
j r j
construction contract. Considerations of cost,
construction sequencing and scheduling, site
congestion, safety, and contractor
qualifications will all impact the decision on
site selection considerations.

5.3 REVIEW OF RESOURCES
GEPs that are applicable to site selection and
development include:
• analysis of availability and
interchangeability of resources, such as
materials, personnel, and equipment;
site surveys, including topographical,
geological, hydrogeological,
hydrological, seismic, wind and weather
patterns, as well as social and
economical factors;
• automatic communication/notification
procedures and processes among all
integration of planning, design,
purchasing/procurement, fabrication,
construction/installation processes, and
O&M procedures and requirements;
modeling and simulation of technical,
logistical, economic, social,
environmental, and political systems
prior to, during, and after
installation/implementation;
• use of lockout/tagout procedures and
equipment during systems
fabrication/installation and operations;
and
prevention of calamities through process
hazard analysis, HAZOP, FMEA, fault
tree analysis, and incident investigation.


Basic Quality Principle
Management should identify resources available, how they are allocated, and associated
responsibilities for resource allocation.
       The planning procedures should specify the intended source of required resources and the
funding for personnel, materials, and equipment.  Resources available to the responsible party,
design professional, and constructor for project construction may place constraints on project
activities and influence the decisions pertaining to project specifications, planning and design,
contracting strategies, and construction operation and quality.  It is the responsibility of project
management and, ultimately, of senior management to ensure that resources for quality
assurance are available.  Reporting procedures and delineation of responsibilities for resource
reviews should be established.  In addition, such reviews should result in the establishment of
EPAQA/G-ll
30
January 2005

-------
procedures and mechanisms for securing the needed resources for construction within the
framework of prevailing local, state, and federal regulations.
                                                Applicable GEPs for financial resources include:
                                                    •   design of self-correcting procedures and
                                                       processes and
                                                    •   integration of planning, design,
                                                       purchasing/procurement, fabrication,
                                                       construction/installation processes, and
                                                       O&M procedures and requirements.
5.3.1  Financial Resources

       The technology developer or
responsible party is in charge of securing
funds to plan, design, and construct the
project. This may be a cooperative effort
between several different parties and/or
agencies.  The availability  of these funds,
beginning with the onset of the planning
phase, will be critical to completion of the
project in a timely fashion  and to the ultimate quality of the project. Adequate funding of "up
front"  activities, such as preliminary planning, hydrogeological studies, alternative
investigations, and other activities to delineate design criteria and project specifications, is
crucial to adequately define the  design and reduce the risk of unanticipated events during
construction.  This can include,  for example, additional funding for verification of contaminant
levels  at the site in order to ensure operational success of the technology. The completion of a
project in a manner that ensures the quality of the constructed system entails that the financial
interests of all members of the project team (responsible party, design professional,  constructor,
suppliers, subcontractors, specialty fabricators, etc.) be considered.  Financial capabilities should
be considered in the planning stages as well as in the contractual and implementation phases of
the project.
5.3.2  Human Resources

       During the initial stages of project
planning, the responsible party evaluates the
human resource needs of the project.
Continuity of key management and
professional staff and the availability of a
skilled workforce are important factors that
contribute to the quality of the project.
Project team staffing was discussed in detail
in Section 3.4.

5.3.3  Construction Materials
                                                GEPs that apply to the management of human
                                                resources include:
                                                       analysis of availability and
                                                       interchangeability of all resources, such
                                                       as materials, personnel, and equipment;
                                                    •   integration/optimization of human,
                                                       material, energy, and economic
                                                       resources and logistical, political, social,
                                                       environmental, and technical factors
                                                       during each critical phase of the project;
                                                    •   worker training/retraining, including
                                                       hands-on training; and
                                                       worker registration/certification.
       The availability and cost of materials
for construction influence planning, design, and construction operations. In planning
construction activities, the responsible party or authorized representative should evaluate the
availability and cost of specific materials in the local market, transportation costs for materials
not available locally, storage and preparation procedures, and scheduling aspects related to
EPAQA/G-ll
                                             31
January 2005

-------
transportation and specially prepared
materials. Material costs can include
specialty products requiring fabrication;
however, off the shelf availability of such
items should be investigated to ensure that
material costs are kept to a minimum.  All
such considerations should be evaluated early
in the planning stages to ensure timely
completion of the project using quality
materials.

5.3.4   Supplier Manufacturing
       Capabilities

       Specialized equipment may call for
sophisticated manufacturing capabilities that
are available only from a limited number of
suppliers. Environmental technologies often involve this type of equipment.  This can include,
for example, specialized sampling equipment used to monitor technology success or specialty
products required for technology construction.  In order to ensure completion of the project on
time, it is important that such materials and suppliers be identified at the early stages of planning
and steps be taken to assess manufacturing and delivery capabilities. In addition, material
specifications may be used to document project needs and ensure quality components are
manufactured. A review of the manufacturer's implemented quality system, as well as
implementation of external quality oversight (audits or inspection of large scale specialty items),
are important. (See Chapter 7 for further discussion of assessments.)

5.4    CONTRACTUAL ARRANGEMENTS
  Applicable GEPs for construction materials
  include:
      •   reuse of materials required for
         technology operation or development
      •   reduced use of virgin materials, wastes
         generated, energy sources, and human
         resources;
         recycling/recovery of materials, utilities,
         and energy sources;
         conservation of materials and energy
         sources;
         substitution of materials and energy
         sources with cleaner, better, cheaper,
         more reliable, and more readily
         available alternatives.
 Basic Quality Principle
 The responsible party or technology developer should implement applicable contracting
 requirements for project design and construction.	
       Since most contracting issues are not directly related to QA, the details of contracting and
procurement activities will not be covered in detail in this document.  However, because there
are some critical QA elements that should be addressed in contracting and procurement
activities, associated roles and responsibilities for technical  and QA personnel will be discussed
here and in Section 5.5.  While contracts are usually negotiated in a different part of the
company or organization, technical personnel usually will be required to have some
involvement. Generally, and subject to applicable procurement regulations and requirements,
technical personnel furnish a statement of work (including detailed construction blueprints)
outlining technical tasks that will be required on the part of the contractor and will recommend
qualified contractors following technical evaluations of proposals.
EPAQA/G-ll
32
January 2005

-------
       Any procurement actions undertaken
by EPA or other Federal departments and
agencies based on this guidance must comply
with applicable procurement regulations
(e.g., Federal Acquisition Regulation) and
requirements.  This guidance is not intended
to change or replace any applicable
procurement regulations required by the user
organization, including Federal and State
regulations and statutes.  Similarly, use of
this guidance by a non-government
organization may be subject to contract or
other requirements for procurement.

       In general, contractual documents
usually include four basic elements: (1)
solicitation documents, (2) contract forms,
(3) contract conditions, and (4) plans and
specifications.  The types of solicitation
documents will depend on the contract
mechanism and form selected.  Regardless of
contract type, documentation related to
requests for proposal, technical statement of
work and specifications, qualification
statements, formal solicitation documents,
technical questions and responses, and other
correspondence leading up to the selection of
the constructor are part of the contract record
and should be properly controlled from
initiation of the solicitation process through
completion of the project. This is likely to be
a requirement of the procurement process and
is an important practice from a quality stand
point.  Again, applicable Federal
procurement regulations and policies will
determine the appropriate contractual arrangement for Federal users.

       Also part of the typical contractual  record are contract conditions, including milestone
and completion dates, general and supplementary conditions, terms and methods of payment,
indemnifications, risks and liabilities assumed by each party, warranties and guarantees, and
contract termination conditions. Plans and specifications typically include detailed design
drawings for facilities to be constructed, materials specifications, specifications for construction
or modification of utilities, and any other applicable drawings and specifications, such as field
change orders, appropriate sign-offs at various phases of construction, and as-built drawings.
  Applicable GEPs for constructual contracts
  include:
      •   design of self-correcting procedures and
         processes;
         analysis and interchangeability of all
         resources, such as materials, personnel,
         and equipment;
      •   automatic communication/notification
         procedures and processes among all
         team members;
         integration of planning, design,
         purchasing/procurement, fabrication,
         construction/installation processes, and
         O&M procedures and requirements;
         integration/optimization of human,
         material, energy, and economic
         resources and logistical, political, social,
         environmental, and technical factors
         during each critical phase of the project;
      •   sound project management
         principles/practices;
      •   worker training/retraining, including
         hands-on training;
      •   worker registration/certification;
         certification/permitting of work
         procedures, processes, equipment, and
         environment;
      •   use of automatic safety/corrective action
         triggers in technical, logistical, political,
         social, environmental, and economic
         situations; and
      •   routine/periodic inspections, testing and
         compliance audits of systems,
         procedures, processes, and equipment,
         etc.
EPAQA/G-11
33
January 2005

-------
Applicable legal requirements and specific administrative requirements of the site owner will
dictate how long and in what form these and other contractual documents should be retained.
The control of contract documents has been addressed in the publication, The Uniform Locations
of Subject Matter and Information in Construction Documents (ASCE,  1981).

       Standardization of construction contracts, in particular, is desirable in order to simplify
the solicitation process and reduce the cost of soliciting bids and responding to such inquiries.
Additionally, the use of standardized contract forms and language reduces the chance of errors
and misunderstandings among the various parties. Many professional organizations and various
industry associations have worked individually and jointly to develop standard forms, contracts,
general conditions, and other contractual documents with this goal in mind.  Examples of
"standardized" contracts may be obtained from the Engineers Joint Contract Document
Committee, the American Institute of Architects, and the Attorney General's Chamber.  In
addition, a  standardized form of contractual conditions has been prepared and is widely
recognized for international work. The form  was prepared by the International Federation of
Consulting Engineers (FID 1C) in consultation with lending institutions and constructor
associations.  The form can be found in Conditions of Contract for Works of Civil Engineering
Construction (FIDIC, 1992). A guide to the use of FIDIC conditions was published in 1989 and
is available through the American Consulting Engineers Council (ACEC) (ACEC, 1989).

       It is important that organizational and technical interfaces be established in the
contractual process and clearly defined in the contractual documents. The construction team
leader establishes the project specifications and communicates them to the team members,
provides commensurate funding, encourages  cooperation and communication among all team
members, ensures adherence to project specifications, and establishes a schedule that is adequate
to complete the project in a quality fashion. As part of project definition, it is critical that quality
expectations be translated into clear, concise written specifications.  In many cases, the design
professional will assist in defining project specifications based upon agency expectations and
QA and QC objectives. This process of defining project requirements may be iterative.
However, it is important that they be fully defined as early as possible in the pre-design  stage of
the project. Ideally, the constructor's project supervisor or operations manager should be
involved in these discussions so as to better document quality expectations for implementation
by procurement personnel in the appropriate contract documents.

       In negotiated contract selection, qualifications statements may be solicited and evaluated
(usually by technical staff), in accordance with applicable procurement regulations and
requirements, to determine the constructor best qualified to perform the desired work. The
responsible organization solicits proposals from potential offerers; the award is made  on the
basis of satisfying proposal elements defined  by the organization or contracting entity. Such
elements typically include:

       •       understanding of the project demonstrated by the constructor (based on the
              supplied scope of work);
EPAQA/G-ll                                34                                  January 2005

-------
       •       approach to the project, including utilization of unique and cost-effective
              approaches;
       •       proposed unit or lump-sum cost of the work, including fees;
              key management and supervisory personnel to be assigned to the project,
              including the role specified and the availability or commitment of these
              personnel; and
              plans and staffing to ensure compliance with safety, quality control,
              environmental, and other regulatory issues.

       Additional elements that may be included are:

              proposed schedule with milestones and completion date(s);
              organization of project activities;
              use of local resources (materials, labor, etc.);
              availability of crafts, use of subcontractors, and minority and small business
              involvement;
       •       business information, such as labor and overhead costs, insurance, and
              contracting policies; and
       •       design of temporary structures, utilities, and transportation services.

       The interfaces between the technical personnel and the procurement/contracting
personnel should be clearly defined and implemented to ensure that all technical needs are
communicated to the procurement/contracting personnel for implementation in accordance with
applicable regulations and requirements. As shown in the following section, it may be necessary
for the technical and QA personnel to interact with the procurement/contracting personnel to
address quality requirements during various steps in the  procurement process to ensure the
acquisition of satisfactory items or services from the final contractual arrangements.

5.5    QUALITY PRACTICES IN PROCUREMENT ACTIVITIES
 Basic Quality Principle
 The responsible party and participating organizations, including the design professional,
 construction contractor, and facility operators should ensure that procured products and
 services meet established technical and QA objectives and that they perform as specified.
       Quality should be an integral element of every procurement activity in the life cycle of an
engineering project involving environmental technology. The following general discussions
indicate points in a general procurement process where important quality control and quality
assurance practices should be defined by technical and QA personnel for implementation by
procurement/contracting personnel in accordance with applicable procurement regulations and
requirements.  These discussions are intended to provide guidance to technical personnel
regarding their roles and responsibilities on quality-related actions that may need to be applied
EPA QA/G-11                                35                                  January 2005

-------
during the procurement phases in engineering projects so that accurate and effective technical
advice can be given to the procurement/contracts personnel.

5.5.1   Quality Practices in Procurement Planning

       Early planning of and a systematic approach to procurement activities are important to
ensure project quality, particularly for items and services that are integral to fabrication or
construction of equipment necessary to the engineering project.  It is important that
organizational responsibility be identified and documented for applicable QA and QC activities
such as specification of QA and QC requirements in the contract documents, pre-award audits
and inspections to determine contractor capabilities, and technical and quality reviews of
submitted bids or proposals.  Typically, these activities will be performed by technical or QA
personnel working with the procurement or contracting personnel.  In addition, it is important
that the sequence of actions (e.g., completion of a purchase requisition will occur before supplier
bids are requested or a purchase order is awarded) and applicable milestones (e.g., signatures,
award date, delivery of supplies or services, etc.) be documented and comply with any applicable
procurement regulations or contract requirements. Standard elements of the procurement
process typically include preparation, review, and change control of procurement documents;
identification and selection of procurement sources; preparation of statement of work or
specifications; evaluation and award of bid or proposal; verification of receipt and acceptance of
the item or service;  evaluation of supplier performance; and quality assurance records.

5.5.2   Quality Practices in the Evaluation of Suppliers

       Supplier selection is based partly upon the purchaser's technical  evaluation of the
supplier's capability to provide the items or services in accordance with the specifications
established in the procurement documents and subject to applicable procurement regulations and
requirements.  Identification of those within the organizations responsible for supplier source
evaluation, including the appropriate QA organization, is important to ensure that quality
supplies and services are procured. In most cases, these technical personnel will be responsible
for determining whether or not the engineering design specifications have been satisfied in the
supplier's proposal. Development and implementation of standardized evaluation and award
procedures is also important to maintain the integrity of the selection process and ensure that
supplier selection results in quality supplies and services.  Supplier evaluation should ideally
include a review of the supplier's history for satisfactorily providing similar products and
services. Alternatively, an evaluation  of the supplier's QA program, including quantitative or
qualitative documentation of past performance, may be performed (usually by technical
personnel) when permitted or authorized by applicable procurement regulations and
requirements.  In the case of suppliers that are new and do not have documentation of past
performance, the supplier's technical and QA capabilities can be assessed based on an evaluation
of the supplier's facilities, personnel, and quality program.
EPAQA/G-11                                 36                                 January 2005

-------
5.5.3   Quality Practices in Proposal Technical Evaluation

       The solicitation proposal evaluation process determines the extent to which the supplier
conformed to the specifications of the procurement document (e.g., request for proposal).  This
evaluation is typically performed by a team of contract specialists, technical experts, and QA
personnel, subject to applicable procurement regulations and requirements. This process
evaluates the skill and experience of the supplier's technical personnel; other technical
considerations, such as the technical approach identified by the supplier; supplier past
performance and production capability; QA program organization, procedures, and personnel;
and any exceptions noted or changes in technical approach and specifications recommended by
the supplier.  Any such exceptions, recommended changes, or deficiencies identified during the
evaluation should be resolved (or a commitment obtained from the supplier to resolve the issue),
in accordance with applicable procurement regulations and requirements, before the contract is
awarded.  It is advisable that the purchaser's technical and QA personnel conduct a QA
management review and confirm the acceptability of the supplier's QA provisions before the
contract is awarded and/or work is started.

5.5.4   Quality Practices in Work Plans and Other Documents

       Work plans and similar documents are often part of the quality assurance plan, and, in
such cases, should include the following technical elements consistent with applicable
procurement regulations and requirements:

       •       A scope of work detailing the technical and administrative (e.g., progress reports)
              specifications.

              Other technical specifications, such as design bases (identified and referenced);
              design drawings and other  documents (e.g., codes regulations, procedures, etc.);
              and tests, inspections, hold points, or acceptance criteria used to monitor and
              evaluate supplier performance.

       •       QA provisions, including (1) QA specifications and documentation, (2) pass-
              down specifications that the supplier is required to incorporate into any sub-tier
              procurement documents, and (3) applicable QA documents from the purchaser if
              those are to be implemented in lieu of supplier QA procedures.

              Documentation of QA and QC procedures that may be outside normal industry
              standards such as usually would be specified in a standard operating procedure.
              This is especially important for suppliers of services. For example, a supplier
              may be using a standard operating procedure that is industry-accepted but may
              not satisfy specific project  specifications. This type of situation would benefit
              from additional monitoring to  ensure project specifications are achieved.
EPAQA/G-ll                                 37                                  January 2005

-------
5.5.5   Quality Practices in Document Review and Approval

       Procurement documents should be reviewed by trained personnel with access to and
understanding of the procurement scope and requirements, and in accordance with applicable
procurement regulations and requirements.  Typically, the contractual aspects of these
documents are reviewed by procurement/contracting personnel and the technical (and QA)
aspects are reviewed by technical and QA personnel. Comprehensive review against the
document requirements may help to ensures full compliance with procurement procedures.  This
review should help the responsible organization select the best-qualified supplier.  This, in turn,
increases the likelihood that appropriate and sufficient-quality supplies will be procured, thus
helping to ensure that project quality is maintained. Reviews should be performed and
documented, along with any changes, in accordance with applicable procurement regulations and
requirements prior to the procurement document being issued to the supplier.

5.5.6   Considerations in Evaluating Supplier Quality Management Capability

       In some circumstances in the engineering project process, it may be appropriate to
require a supplier to have a quality system that conforms to a recognized consensus standard like
ISO 9001:2000, Quality Management Systems - Requirements (ISO, 2000), as permitted in the
Federal Acquisition Regulations in 48 CFR Part 46.  In order to confirm that its quality system
conforms to such standards, the supplier may demonstrate its conformity through a certification
process.  Such certificates are widely recognized and accepted, and may provide the customer
with increased assurance that the supplier is capable of performing at a level that meets the needs
of the customer.  However, certification alone may not be sufficient to ensure that the supplier
can perform to expectations in providing specific products and services.  It may be necessary to
assess or audit the supplier's performance directly. These audits are generally allowed under
Federal procurement regulations and are typically  conducted by customer's technical and QA
personnel. The specifications for the audits are derived from the approved procurement
documents and specifications.

5.5.7   Quality Conditions in Acceptance of Items or Services

       Typically, acceptance by the purchaser of items or services received from the supplier
will involve four parts, subject to applicable procurement regulations and requirements:

             source verification,
       •      receiving inspection,
       •      post-installation testing, and
       •      supplier certification of conformance.

       Source verification involves acceptance of any goods or services by the purchaser based
on monitoring, auditing, or other surveillance activities performed by the supplier. The extent of
monitoring and the inspection intervals should be determined based upon the complexity and/or
importance of the purchased item or service and previous experience with the supplier and in

EPA QA/G-11                                38                                 January 2005

-------
accordance with applicable procurement regulations and requirements.  Documented evidence of
acceptance of the item or service is then furnished to the receiving party.  Typically, such
inspections are performed by technical personnel and/or QA personnel.

       Receiving inspection is used by the purchaser to accept an item in accordance with
established inspection procedures, which, in turn, are driven by the established product
specifications and applicable procurement regulations and requirements. The inspection verifies,
as applicable, product identification and configuration, dimensions, physical characteristics,
cleanliness, and lack of damage.  Inspections also include a review of the adequacy and
completeness of supplier documentation.  Accordingly, it is expected that the technical personnel
conducting the inspections should have the necessary knowledge of the specifications and skills
to evaluate the received items.

       Post-installation testing is used frequently in engineering projects to verify that an item
meets the specifications of the purchaser. It is critical that the purchaser's specifications be fully
documented in advance of the project and that acceptance criteria be mutually agreed upon by
the purchaser and supplier.  This testing can be in the form of an onsite audit of the equipment
supplied. A flow meter, for example, may be tested by calibration after installation to ensure
that accuracy and precision specifications meet supplier and purchaser QC specifications.
Again, such testing typically performed by technical personnel who will advise the
procurement/contracting personnel regarding the acceptability of the items.

       In lieu of or in addition to the above acceptance methods, the purchaser may require that
the supplier provide a certificate  of conformance with applicable technical standards or criteria
(such as ISO  9001 mentioned earlier).  The certificate identifies the purchased material or
equipment along with the purchase order or other identification number traceable to the
procurement  document.  This certificate should identify the codes, standards, specifications, or
other procurement requirements met by the item. It is important that this certificate be signed or
otherwise authenticated by a responsible official. For example, this certificate of conformance
may be an American Society for  Testing and Materials certification or other similar
authentication that the product performs as specified.  Verification of such certificates of
conformity is typically performed by technical personnel who will advise the
procurement/contracting personnel regarding the acceptability of the items.

5.5.8  Quality Considerations  in Control of Supplier Nonconformance

       The purchaser and supplier should document an agreed-upon process for handling items
that do not conform with procurement document specifications and in accordance with
applicable procurement regulations and requirements. At a minimum, the supplier should report
nonconforming items to the purchaser within the allotted time frame and utilize the mechanism
set up for nonconformance procedures.  It is important, therefore, that such procedures establish
specific guidelines for handling nonconforming items.  In any case, the purchaser ultimately
verifies the disposition of the nonconforming items.  The technical guidelines should be provided
EPA QA/G-11                                 39                                  January 2005

-------
by the technical personnel to the procurement/contracting personnel, who will conduct
discussions with the supplier in accordance with applicable regulations and requirements.

5.5.9   Quality Considerations in the Use of Commercial-Grade Items

       The design may specify commercial-grade items.  The items should be clearly identified
in the design drawing or specifications by the technical personnel and conveyed to the
procurement personnel.  Any source selection specifications should also be identified in the
procurement document from the manufacturer's published product description in accordance
with applicable procurement regulations and requirements. Alternative suppliers, product
grades, or products typically may be utilized only if the purchaser approves the change or
replacement. Acceptance by the purchaser will be based on verification by technical personnel
in the design organization that the alternative commercial product performs the intended function
and meets design specifications in accordance with applicable procurement regulations and
requirements.  Acceptance of commercial grade items should be based upon (1) inspection or
testing by the purchaser to ensure that the item meets manufacturer's specifications, (2)
verification that the item received was the item  ordered, (3) confirmation that no damage was
sustained during shipment, and (4) confirmation that appropriate documentation was received
and is acceptable. Technical personnel are responsible for advising the procurement/contracts
personnel regarding the technical acceptability of commercial grade items.

5.6    SCHEDULING AND TRACKING
 Basic Quality Principle
 Early construction planning by the responsible party, design professional, and constructor
 enables schedule milestones to be included in the construction contract.
       Significant issue dates for design elements and key delivery dates for supplies, materials,
and factory-fabricated items should be included in the construction schedule to integrate design,
procurement, and construction before construction begins. Other relevant schedule dates, such
as utility hookups or changeovers, should be included. It is important that the schedules be
based upon labor workforce availability and realistic production rates and quantities.  Equally
important is that the responsible party recognizes the necessity for preparing, coordinating,
reviewing, and approving shop drawings and other submittals and allows sufficient time for such
reviews.

5.7     COST MANAGEMENT
 Basic Quality Principle
 During the construction and fabrication of system components, the constructor's (and all
 subcontractors') estimates should be tracked, refined, and updated.	
EPAQA/G-ll                                40                                 January 2005

-------
       Documented procedures should be established that will allow control and tracking of
construction costs for each phase/area/activity of the construction as well as for the overall
project. Work productivity should also be tracked to identify problem areas.  Identifying and, if
necessary, correcting cost trends early in the process should help prevent overruns, quality
problems, and disputes.

5.8    MATERIALS  MANAGEMENT
 Basic Quality Principle
 The constructor should establish a documented plan to control and track purchasing,
 receiving, special storage, and in-storage maintenance of materials for the project and the
 time frame.
       A documented plan may include a system that will key material deliveries to the project
schedules.  The availability of materials should be a prime consideration any time the project
schedule is revised. Productivity and quality often suffer when crews are started and stopped
repeatedly due to material shortages. Construction materials will generally fall into one of two
major classes: in situ materials and manufactured items.

       In situ materials include soils and rocks used for backfill, construction bases (e.g., gravel
bases for roads and foundations), or components of site structures (e.g., clay used in landfill and
lagoon liners and berms, limestone in cement, or gravel in concrete). Depending upon the
material requirements, these materials may be excavated at the site or may be shipped from local,
regional, or national suppliers. Transportation of these materials should be considered in
construction scheduling, especially during severe weather.  Stockpiles onsite may be  used to
provide a steady supply of materials; the location and footprint of such stockpiles should be
considered during site planning.

       Manufactured items include a wide variety of materials. Examples include metal or
plastic piping; paints and sealers; liners or other plastic products;  structural steel; electrical
conduit, wiring, circuit breaker, switches, and other electrical components; motors, pumps, and
other mechanical installations; plywood, particle board, and other wood and timber products;
brick and other masonry products; and asphalt. As with in situ materials, identification of
suppliers, establishment of contractual relationships, development of quality specifications, and
consideration of schedule are all important elements of materials management. Materials quality
specifications may be established by broadly-accepted standards developed by organizations,
such as the American Society for Testing and Materials, the American Concrete Institute,
Institute of Electrical and Electronic Engineers, and so forth. Alternatively, site-specific
standards may be developed by the design firm.  A good list of acceptance standards  for a variety
of materials is presented in the American Society of Civil Engineers guide, Quality in the
Constructed Project: A Guide for Owners, Designers and Constructors (ASCE, 2000).
EPA QA/G-11                                 41                                 January 2005

-------
5.9    INSPECTION, TESTING, CONTROL, AND TRACKING
 Basic Quality Principle
 An important part of the work planning process is to identify the items and processes to be
 inspected or tested, the parameters or characteristics to be evaluated, the techniques to be
 used, the acceptance criteria, any hold points, and the organization responsible for
 performing the tests and inspections.	
       Inspection and testing of specified items and processes are conducted using established
acceptance and performance criteria. The acceptance of items and processes is made by and
documented by qualified and authorized personnel. It is important that equipment used for
inspections and tests be calibrated. An inspection and testing program for the
construction/fabrication/installation of environmental technology should be in accordance with
the following key specifications.

       First, it is important that a planning program be implemented for the inspection, testing,
and monitoring of materials.  Several objectives should be considered:

              the quality of supplies should be verified in accordance with specified procedures,
              the inventory of supplies and materials should also be monitored to ensure the
              continuity of construction activities, and
       •       the workmanship and adherence to technical specifications should be verified for
              specially-fabricated materials and equipment.

       Second, a thorough and comprehensive inspection, testing, and monitoring program
should be implemented. This may involve the inspection of supplies and materials in process  at
the supplier location.  Alternatively, inspections may be made of goods ready for shipment from
the supplier or as received by the constructor or the contractor.

       Third, the performance of inspections and testing, as well as the results, should be fully
documented.  This is critical in cases where problems and defects occur and there is a
disagreement between the receiver and the supplier as to the quality of the product or material or
as to who is responsible. Since such problems  cannot be predicted, it is important that thorough
documentation be an integral part of the  inspection and testing process.

       Finally, a quality assurance program is vital to the inspection and testing  program. It is
important that any monitoring, measuring, testing, and data collection equipment be properly
selected and utilized.  Equipment selection entails that the equipment measure the parameter
within the established acceptance range.  Therefore, the testing equipment should be properly
sized such that its measurement range and accuracy meets those standards established for the
product or material.  In addition, the testing equipment should have a precision range that
encompasses the agreed-upon tolerance limits for the product. As has been discussed
previously, the acceptance range and tolerance  limits should be established in advance, agreed


EPAQA/G-ll                                42                                 January 2005

-------
upon with the supplier, and fully documented in the appropriate contractual documents.  Not
only should the measurement instrument be properly selected, it should be properly used and
controlled to ensure the reliability of testing results. The equipment should be used according to
the manufacturer's instructions for that equipment. Frequent performance and documentation of
equipment calibration is important, especially under harsh operating conditions.  Zero checks
and calibration with known standards are typically the minimum calibration specifications.
Additional calibration procedures may include measurement of internal standards (standard
incorporated into the matrix to be measured) or other more sophisticated QA procedures.
Equally important to the selection and calibration of testing equipment are the qualifications of
inspection and test personnel. Training in inspection and testing procedures, equipment use and
calibration, and proper procedures to document inspections and tests is critical to the success of
any quality assurance program.

5.10   COMPLETION APPROVALS
 Basic Quality Principle
 During the planning phase of the project, specifications for construction completion
 certification and approvals of external agencies and other groups should be established,
 documented, and communicated with appropriate individuals.	
       Environmental technology construction projects may have two levels of approvals:  (1)
internal and (2) external/independent/regulatory. Internal certifications and approvals consist of
the design professional verifying/authenticating and certifying for the responsible party the
completion of part or all of the construction/fabrication/installation.  When a project is
completed (or critical portions thereof), many agencies require some sort of release or affidavit,
or both, certifying that work has been done substantially in accordance with the appropriate
contract documents. Furthermore, information on the location or completeness of record
drawings and certain project-specific design/construction documents may be required. In
addition to formal regulatory review, environmental projects involving other stakeholders (e.g.,
local communities, environmental groups, etc.) may require approval by these stakeholders or
their technical representatives.
EPAQA/G-ll                                43                                  January 2005

-------
EPAQA/G-11                                  44                                   January 2005

-------
                                      CHAPTER 6
                     SYSTEM OPERATION AND MAINTENANCE
                    Construction of Systems    Components
                           Design of Systems
                            Quality Planning
                                                          Operation of Systems
                planning and training
                O&M considerations during
                design
                O&M considerations during
                construction/fabrication/
                installation
                system start-up
                normal/routine operations
                inspection and testing
                handling, storage, packaging,
                preservation, and delivery
               GENERAL GUIDING PRINCIPLES
6.1    INTRODUCTION
 Basic Quality Principle
 O&M factors influence life-cycle costs, continuity of service, durability, public health and
 safety, environmental impact, and other features of the completed environmental technology
 project/program/facility.	
       The operational characteristics and maintenance of the project after completion determine
the success in meeting project objectives. Consideration of O&M specifications in each phase of
project planning, design, construction, and start-up is therefore desirable. For all projects, active
participation of the developer from an O&M viewpoint adds to the developer's understanding of
the design criteria and the effort to translate the design specifications into an operating facility
meeting project specifications.  In the planning and design of the project, the O&M concern is
with input to and review of design-phase activities; in the construction phase, the concern is with
construction observation and inspection; in the start-up phase, the concern is with verification,
testing, and acceptance; and in the operational phase, the concern is with the operation and
maintenance of the constructed project. O&M procedures are normally established and
documented to ensure control and compliance for each of the various stages of the project as
discussed below.
EPAQA/G-ll
45
January 2005

-------
6.2    PLANNING FOR O&M INPUT AND TRAINING
 Basic Quality Principle
 The developer may select from a number of options providing for consideration of the various
 O&M issues as they influence design, construction, and operation of the environmental
 technology.	
       The following issues should be addressed while planning for O&M:

             The developer may appoint a member of the O&M staff as project coordinator to
             advise the design professional and the constructor from the O&M standpoint. For
             this assignment the developer should find an experienced individual, preferably a
             candidate to head up the operations team for the completed facility.

       •      The developer may contract with the design professional to have an experienced
             professional member of the design team or a qualified consultant provide the
             appropriate O&M advice and review.

             The developer may delegate members of the O&M staff to work under the design
             professional in observation and/or inspection of construction activity during the
             construction phase.  This assignment provides an opportunity for O&M personnel
             to become familiar with the project while performing construction phase duties.

       •      The developer may delegate members of the O&M staff to work with the design
             professional and constructor during the start-up phase of the project.

             The developer may contract with the design professional and/or constructor to
             provide review of and advice for operation and maintenance programs for some
             defined time after the project has been taken over by the operating staff.

6.3    O&M CONSIDERATIONS DURING DESIGN PHASE
 Basic Quality Principle
 Decisions made during the design phase relating to site selection and access, process
 choice, equipment selection, and other elements of the project will impact O&M of the
 completed project and limit flexibility in subsequent phases of the project.	
       Reviews stressing the operability and maintainability of various features of the project
are scheduled at appropriate points in the design phase and at final design. The frequency and
depth of these reviews vary with the size and complexity of the technology to be deployed.
Reviews from an O&M perspective normally include the following:
EPAQA/G-11                               46                                 January 2005

-------
       Physical plant considerations - Size and layout of working space to be provided;
       suitability of equipment types, including efficiency in operation, maintenance schedule,
       and costs for the equipment; provisions for bypassing and isolation equipment for
       maintenance; specialized services, such as laboratory and chemicals; staff amenities;
       efficient land utilization; specific layout of equipment, process, and control systems to
       provide O&M accessibility; lay-down space and removal paths; appropriate flexibility
       and redundancy in equipment and controls; and provisions for adequate manufacturer-
       supplied materials, and spare parts information should be considered.

       Control strategies - Alternative strategies on efficiency of operations and staffing.

       Life-cycle cost considerations - Building materials and equipment.

       Environmental considerations - Provisions to mitigate odors, noise, and undesirable
       aesthetic effects, as well as the possible need for a public-relations program.

       Safety considerations - Equipment, protective devices, etc.

       Personnel - Budget planning and O&M staffing.

       During the design phase, the developer is responsible for communicating needs,
constraints, expectations,  and requirements regarding performance, operation,  and maintenance
of the proposed facility and for providing timely reviews. The developer is also responsible for
providing adequate O&M input and determining (with the help of the design professional and the
O&M coordinator) O&M budget and staffing requirements.  The design professional is then
responsible for preparing  the plans and specifications incorporating O&M considerations.

6.4     O&M CONSIDERATIONS DURING CONSTRUCTION/FABRICATION/
       INSTALLATION PHASE
 Basic Quality Principle
 The construction phase of the project provides an opportunity for the developer's O&M
 coordinator to make the transition from the advisory and reviewer roles of the design phase to
 more active roles.
       Activities contributing to project construction that can provide valuable information for
O&M personnel include:

              inspection and testing of materials and equipment;
              observation of installation and testing of equipment by the constructor;
              observations of construction activities pertaining to utility routing and locations,
              installation problems affecting O&M, and arrangements of project elements as
              they affect operational safety and maintenance; and

EPAQA/G-ll                                47                                 January 2005

-------
              assistance to the design professional in preparation and review of the O&M
              manuals and procedures.
6.5    SYSTEM START-UP
 Basic Quality Principle
 The O&M staff are key players in the start-up of any project.
       The purpose of start-up phase activities is to demonstrate that project elements
constructed or installed by the constructor are in working order, and that the facility performs as
planned by the developer and the design professional.  This activity gives the O&M staff the
opportunity to become familiar with the project under the guidance of the constructor and design
professional.  Start-up of an environmental technology may require the organization and training
of a start-up group composed of representatives from the developer, design professional,
constructor and O&M staff.

6.5.1   Planning the Start-Up Program

       Responsibility for organizing and leading the start-up program is generally part of the
developer agreement with the constructor. With responsibility for start-up established, the start-
up team is assembled with representation from the design professional, constructor, and
developer, with particular emphasis on representation from the O&M staff. Activities of the
team in planning for start-up include:

       •       preparing and reviewing start-up programs and procedures,
       •       determining construction completion status,
              planning for supervision of system testing and correlation of deficiencies, and
              reviewing final inspection reports  and project closeout submittals.

       Planning for an environmental technology/treatment system/facility start-up calls for a
well-defined approach and documented procedures and methods for:

       •       hazardous operations review/analysis,
       •       safety checking/testing,
              operator training,
              system start-up (start-up procedures),
              standard operating procedures, and
              emergency shutdown procedures.

       The interaction and  exchange of information among the principal parties involved in the
project may be outlined in a start-up manual along with planning, scheduling, testing, and other
activities planned by the start-up team. Start-up manuals should be structured to fit the project.
EPAQA/G-ll                                 48                                 January 2005

-------
Simple, direct, and brief language is preferred. Aids such as forms, checklists, and tabulations
are useful.

6.5.2   Start-Up Activities

       Project start-up activities demonstrate the integration of various constructed systems into
a unified facility.  Start-up activities are generally based on the premise that project elements
completed by the constructor have met the material, workmanship, and performance
specifications. Start-up activities are structured to:

              determine that each component of the project is in working order;
              determine that these components can be integrated to operate as a facility, which
              performs as planned by the developer and design professional;
              provide a means of training O&M personnel  in the operation of each of the
              components and of the completed facility (O&M during the start-up of the project
              provides opportunity for the O&M staff to view technology operations with
              guidance from the design professional and the constructor);
       •      validate O&M instructions and manuals prepared by the design professional or
              others;
              check the file of record documents (plans, specifications, manufacturers'
              operating instructions, maintenance instruction, etc.) for appropriate scope and
              detail; and
       •      serve as a vehicle for acceptance of the constructor's completed contract and
              turnover of the facility to the O&M staff for operation.

6.6    NORMAL/ROUTINE OPERATIONS
 Basic Quality Principle
 Documented procedures should be established prior to the start of the operating phase and
 refined, fine-tuned, and updated, as needed, for all substantial activities that constitute the
 system operation.	
       The post-construction, post-start-up operating phase of the project is generally the sole
responsibility of the developer and the O&M staff.  The O&M staff works with and/or through
the constructor in seeking enforcement of all applicable warranties (and performance standards)
and correction of any defects found in the constructor's work. The O&M staff may also wish to
consult with the design professional to request clarification and amplification of operating and
maintenance manuals, to seek advice in fine-tuning project operations, and to ask for assistance
in testing and evaluating performance for conformance to design criteria and project
specifications. Established documented procedure should include the following:
EPAQA/G-ll                                 49                                 January 2005

-------
       Process control and monitoring - To ensure that process output (the product or
       discharge stream) complies with reference standards/codes, quality plans, and/or
       documented procedures, and stays within the permissible tolerance criteria.

       Equipment control and maintenance - To ensure that each piece of equipment within a
       process, process train, or system performs its intended task with the appropriate degree of
       accuracy and reliability.

       Technology operating guides also provide helpful information about systems and
processes.  They normally include, but are not limited to:

       •       appropriate controls for measuring and testing equipment;
       •       operating procedures and parameters for specific components and system
              configurations, including specified safety limits;
              process equipment control and maintenance;
              special environments, time, temperature, or other factors affecting the quality of
              operation; and
       •       the skill, capability, and knowledge of operators to meet operational,
              environmental, and quality objectives.

6.6.1   Process Control

       Process control  activities may be documented by instructions, procedures, drawings,
checklists, or other appropriate means. These means ensure that process parameters are
monitored and controlled and that specified environmental conditions are maintained.

6.6.2   Control of Auxiliaries and Services

       When the quality of systems operation  is directly affected, auxiliary materials, utilities,
and consumables (e.g., water, compressed air,  electric power, and chemical feed stocks) should
be controlled and verified periodically to ensure uniformity of their effect on the systems
involved in accordance with established procedures.  Only qualified and accepted services or
items and consumables should be used during the operation of systems.

6.6.3   Control of Operational Status

       The status of the operating system is controlled to ensure conformance with the approved
operating procedures and specifications. Status indicators with tolerance limitations should be
provided to display the operating status of systems and components of systems as described in
the design and operating instructions and guides. The use of status indicators will help to
prevent inadvertent operation or removal from operation of systems or components when such
actions would adversely affect performance of the systems, constitute an operational safety or
environmental hazard, or violate statutory/regulatory compliance requirements.  (Note:  Such
EPAQA/G-11                                50                                  January 2005

-------
situations include the loss of data that are difficult or impossible to reproduce and may result in
the unplanned release of pollutants in excess of established limits.)

6.7    INSPECTION AND TESTING
 Basic Quality Principle
 The O&M organization should establish and maintain documented procedures for receiving,
 in-process, and final inspection and testing in order to verify that specifications are achieved.
 Provided in this section are inspection and testing specifications for engineering applications.
       Areas of inspection include:

              equipment, parts, spare parts, system components, hardware, software, and
              supplies;
       •       process feed/inputs;
       •       other processing materials; and
       •       treated materials and products/by-products.

6.7.1   Qualifications of Inspection and Test Personnel

       Each person who verifies conformance of O&M activities for the purpose of acceptance
should be qualified to perform the assigned inspection task. Inspections by persons during on-
the-job training for qualification should be performed under the direct observation and
supervision of qualified personnel.

6.7.2   Inspection and Testing Specifications

A.     Planning for Inspection and Testing

       Inspection is not a separate QA function. It is a line implementation function and test
planning should be performed and documented.  This includes:

              identification of the item to be tested or the treatment processes/operations where
              inspections are necessary;
              identification of the test specifications or the characteristics to be inspected and
              the identification of when, during the treatment process,  inspections are to be
              performed;
       •       identification of the testing, inspection, or process monitoring methods to be
              employed;
              identification of acceptance criteria, including the desired levels of precision and
              accuracy (when statistical sampling is to be used to verify the acceptability of the
              subject items or materials, the statistical sampling method should be based upon
              recognized standard practices);

EPA QA/G-11                                51                                  January 2005

-------
       •      identification of sampling activities;
       •      methods to record inspection or test results;
       •      selection and identification of the measuring and testing equipment to be used to
              perform the test or inspection;
              the process used to ensure that the equipment being utilized for inspection or
              testing is calibrated and is of the proper type, range, accuracy, and tolerance to
              accomplish the intended function;
       •      provisions for ensuring that prerequisites for the given test or inspection have
              been met, including hardware and software needs, personnel training and
              qualification, and suitably controlled environmental conditions; and
       •      any mandatory hold points.

B.     Receiving or Hold Point Inspection and Testing

       The O&M staff should ensure that incoming materials or products are not used or
processed until they have been inspected or otherwise verified as conforming to specifications.
Verification of the specifications should be performed in accordance with the project-specific
quality plan and/or documented procedures. When incoming material or product is released for
urgent treatment/processing purposes prior to verification, it should be positively identified and
recorded in order to permit immediate recall and re-treatment in the event of nonconformity to
specifications.

       Hold points are used to control work or activities that are not to proceed without the
specific consent of the designated representative or organization placing the hold point.  The
specific hold points should be specified in appropriate documents. Only the organization or
representative responsible for the hold point may waive the hold point inspection requirement.
Consent to waive specified hold points is recorded prior to continuation of work beyond the
designated hold point.

C.     In-Process Inspection and Testing

       Items or materials in process are inspected and/or tested as necessary to verify quality.  If
inspection of processed items is impossible or disadvantageous, indirect control by monitoring of
processing/treatment methods, equipment, and personnel should be provided. When a
combination of inspection and process monitoring methods is used, monitoring should be
performed systematically to ensure that the specifications for control of the process and the
quality of items are met throughout the duration of the treatment process.

D.     Final Inspection and Testing

       Final inspections include a review of the results and verification of the resolution of all
non-conformities identified by earlier inspections. Treated materials are inspected and tested for
completeness or other characteristics as required to verify the quality and conformance of the
materials to the applicable specifications. Reprocessing or further treatment of the treated

EPAQA/G-ll                                 52                                 January 2005

-------
materials subsequent to final inspection normally entails reinspection or retesting, as appropriate,
to verify acceptability.

E.     In-Service Inspection and Testing

       In-service inspection or surveillance of structures, systems, or components of the
environmental technology should be planned and executed by or for the organization responsible
for their operation. Inspection and testing methods should be established and executed to verify
that the characteristics of the subject material continue to remain within specified limits.
Inspection and testing methods include evaluations of performance capability of key equipment,
verification of calibration and integrity of instruments and instrument systems, and verification
of maintenance, as appropriate.

F.     Inspection and Test Documentation

       The O&M staff should establish and maintain records that provide evidence that the
components and processes of the environmental technology and the materials involved,
including the feed matrices, treatment chemicals and supplies, and the treated residuals, have
been inspected and/or tested.  These records should clearly indicate whether the subject item has
passed or failed the inspections and/or tests according to defined acceptance criteria. Inspection
and test results are then evaluated by  qualified individuals within the O&M organization to
ensure that all test and inspection specifications have been satisfied. When the item fails to pass
any inspection and/or test, the procedure for control and replacement of the nonconforming item
would apply. Inspection and test documentation should identify:

       •      items or materials inspected and/or tested;
       •      the date of inspection and/or test;
              the name or unique identifier of the inspector/tester who documented, evaluated,
              and determined acceptability;
              the method of inspection and/or the applicable test specifications, plans, and
              procedures, including revisions;
       •      the inspection and/or test criteria, sampling plan, or reference documents
              (including revision designation) used to determine acceptance;
       •      the results;
       •      the identification of the measurement and testing equipment used during the
              inspection and/or test,  including the identification number and the calibration due
              date; and
       •      reference to any information on actions taken in connection with nonconformities,
              as applicable.

6.7.3   Inspection and Test Status

       The inspection and test status  of an item should be identified by suitable means, which
indicates the conformance of the item with regard to inspection and tests performed. The

EPAQA/G-ll                                 53                                 January 2005

-------
identification of inspection and test status should also be maintained, as defined in the project-
specific quality plan and/or documented procedures, throughout the O&M of the treatment
process in order to ensure that only items and materials that have passed the inspections are used,
installed, or dispatched.

6.8    HANDLING, STORAGE, PACKAGING, PRESERVATION, AND DELIVERY
 Basic Quality Principle
 Documented procedures should be established and maintained for handling, storage,
 packaging, preservation, and delivery of product.	
       Additional QA-related O&M aspects include the following:

       Handling - The O&M organization should provide safe and proven methods for
       handling products in order to prevent damage or deterioration.

       Storage - Designated storage areas or stock rooms are used to prevent damage or
       deterioration of product, pending use or delivery.

       Packaging - Packing, packaging, and marking processes (including material use) should
       be controlled to the extent necessary to ensure conformance to specifications.

       Preservation - Appropriate methods for preservation of products should be applied.

       Delivery - The O&M staff should be responsible for the protection of the quality of
       product after final inspection and testing.
EPAQA/G-11                                54                                 January 2005

-------
                                     CHAPTER 7
                         ASSESSMENT AND VERIFICATION
                            Verification
                           and Acceptance
                       Assessment and Response
                            gration of Systems
                   Construction of Systems and ConTp
                           Design of
                           Quality Planning
                                                  Assessment and Response
                                                  •  types of assessments
                                                  •  control of nonconforming items
                                                  •  corrective/preventive action
                                                  Verification and Acceptance
                                                  •  verification tools
                                                  •  reconciliation of as-designed
                                                    and as-constructed projects
                                                 \
7.1
        GENERAL GUIDING PRINCIPLES

MANAGEMENT/TECHNICAL ASSESSMENT AND RESPONSE
 Basic Quality Principle
 Assessment provides the basic program structure to ensure that quality specifications are
 maintained.
       This section summarizes the role of assessments in environmental technology projects
and how the results of assessments are used.  For more information on how to conduct technical
audits and assessments, see Guidance on Technical Audits and Related Assessments (EPA QA/G-
7) (U.S. EPA, 2000c).

7.1.1   Types of Assessments

       Work performed during the design, construction, and operation of environmental
technology that affects quality should be assessed regularly to ensure that approved planning
steps, design specifications, and operating guides are being implemented as prescribed. When
acceptance criteria are not met, deficiencies are normally resolved and reassessments conducted
as necessary.  Appropriate corrective actions are taken and their adequacy confirmed and
documented in response to deficiencies or nonconformities. Under most circumstances the
organization performing assessments has sufficient authority and freedom from the activities
being assessed to carry out its responsibilities. Persons conducting external or third-party
assessments should also be technically qualified and knowledgeable of the items and activities
being assessed. In addition, the owner/developer may have a need to conduct internal or first-
party assessments.
EPAQA/G-ll
                                    55
January 2005

-------
       The types and frequencies of independent assessments are usually based upon the
relevant control levels assigned to the items and activities under the cognizance of the
organization. In addition, the participant organizations responsible for the performance of
activities important to compliance application, waste characterization, or the isolation of waste
within the disposal/treatment system should implement a program of surveillance and audits.
The program is then planned and documented and should include both routine surveillance of
those activities and audits to establish compliance with all aspects of the project-specific QA
plan to determine its adequacy and effectiveness.

       Periodic assessments or audits may also be desirable throughout the process life cycle.
Audit timing should be addressed. Is a process audited only once at the beginning, periodically
throughout its life cycle, or perhaps when changes in operation or personnel occur?  Selecting
qualified personnel for audits  is important to the success of the audit. Personnel should be
chosen based on two primary  factors: (1) the expertise appropriate to review the process or
operation being audited and (2) experience in performing audits.  Often a team approach is
appropriate to provide these qualifications. In many instances a technical expert and QA auditor
can work together to  provide the  combined expertise suitable for the audit.  This is particularly
useful during technology operation or evaluation. This approach would usually be applied as
part of a technical systems audit conducted early in the operation life cycle.  Technical experts
can provide invaluable expertise in evaluating design, construction, and operation of
environmental technologies.  The technical expert provides the knowledge and experience
adequate to address all parts of the process audited, while the QA auditor provides the
understanding  of the  audit process, helping to focus the audit on those activities that are most
critical. The QA auditor can also provide leadership in terms of how to frame questions, what
type of follow-up questions might be appropriate, and how to couch audit findings so as to
maximize management support.

       Audit procedures and checklists should be developed and reviewed by the team before
beginning the audit.  Thought should be put into the process flow (beginning with receipt,
testing, and acceptance of materials, through operational aspects, and ultimately ending with the
finished product or completed project).  Audit questions should be clear, concise, and
nonjudgmental.  Potential follow-up questions should be anticipated and, where appropriate,
decision trees applied.  Another important aspect of audit planning is addressing the issue of
responsibility or authority to suspend work if audit findings show that the process is out of
compliance with regulatory or QA criteria. Should the process be halted or operational changes
evaluated if deficiencies are noted during the course of an audit? Serious findings may be
identified. How are they reported?  How are they brought to the  attention of appropriate
personnel? When should work be suspended for reassessment?

       Basic assessments include quality control or technical assessments and management
audits. These assessments are designed to provide a review of project performance  that is
unbiased by the pressures of meeting construction schedules and budgets. An example of a
quality control assessment is the technical systems audit. This is an audit of design,
construction, or operational systems to ensure that procedures defined in planning documents are

EPAQA/G-11                                 56                                  January 2005

-------
being carried out properly. The project planning document should be used as a guide when
performing these assessments.

       Management audits and assessments, on the other hand, are evaluations of program or
project management quality.  These are performed by managers, or designated internal or
external experts, to periodically assess the performance of their organizations. The results of
these audits should be used to implement corrective measures, where necessary, and as input into
the organization's continuous improvement process. In many cases, such assessments are an
integral part of management review.

       Surveillances are observations of a specific technical activity  on an extended basis. The
surveillance process consists of monitoring or observing to determine whether an item, activity,
system, or process conforms to specifications. Surveillances are intended to accomplish the
following:

       •       monitor work in process,
              document compliance or noncompliance with established specifications and
              procedures,
       •       identify actual and potential conditions adverse to quality,
       •       obtain timely corrective action commitment from cognizant managers for
              identified conditions adverse to quality,
              provide notification to responsible managers of the status and performance of
              work under surveillance, and
       •       confirm timely implementation of corrective action.

       Assessments should be performed using the written procedures related to the activity
being assessed. Elements that have been selected for assessment are then evaluated against
specifications. Objective evidence is obtained to determine if those elements are being
implemented effectively. Conditions requiring prompt corrective action should be reported
immediately to management of the monitored organization. Conditions adverse to quality  should
also be documented and corrected according to the discussion in Section 7.1.3 below.

7.1.2  Control of Nonconforming Items

       Documented procedures should be established and maintained in order to ensure that
items and materials that do not conform to specifications are prevented from unintended use,
installation, or release.  This control should provide for identification, documentation,
evaluation, segregation (when practical),  and disposition of nonconforming products, and
notification to the functions concerned.

       Identification of nonconforming items by marking, tagging, or other methods should not
adversely affect the end use of the item. The identification should be legible and easily
recognizable. If identification of each nonconforming item is not practical, the container,
package, or segregated storage area, as appropriate, is then identified.

EPAQA/G-ll                                57                                 January 2005

-------
       Nonconforming items should be segregated, when practical, by placing them in a clearly
identified and designated hold area until properly dispositioned. When segregation is
impractical or impossible due to physical conditions, such as size, weight, or access limitations,
other precautions should be employed to preclude inadvertent use of a nonconforming item.

       Nonconforming item characteristics are to be reviewed, and recommended dispositions of
nonconforming items should be proposed and approved in accordance with documented
procedures.  Further processing, delivery, installation, or use of a nonconforming item is then
controlled pending an evaluation and  an approved disposition by authorized personnel.

       The responsibility for review and authority for the disposition of nonconforming product
should be defined.  Personnel performing evaluations to determine a disposition should have
demonstrated competence in the specific area they are evaluating, have an adequate
understanding of the specifications, and have access to pertinent background information.

       Disposition of nonconforming product and the technical justification for the disposition
should be identified and documented. Nonconformity of an item may be disposed through:

       •      reworking or retreating to meet the specifications,
             accepting with or without repair or remedy by concession,
             regrading for alternative treatment or applications, or
             rejecting or scrapping.

       The description of the nonconformity that has been accepted and the description of the
repair or remedy is then recorded to denote the actual condition. Repaired, reworked, and/or
retreated product should be reinspected, retested, and/or reassessed in accordance with the
project-specific quality plan and/or documented procedures.

7.1.3  Corrective and Preventive Action

       The participant organization should establish and maintain documented procedures for
implementing a corrective  and preventive action program.  Any corrective or preventive actions
taken to eliminate the causes of actual or potential nonconformities are to be appropriate to the
magnitude of the problems and commensurate with  the risks encountered. The responsible
organization should implement and record any changes to the documented procedures resulting
from corrective and preventive action.

       The procedures for corrective  action should include:

       •      effective handling of client, customer or regulatory complaints, and reports of
             product nonconformities;
       •      investigation of the cause of nonconformities relating to product, process, and
             quality system, and recording the results of the investigation;
EPAQA/G-11                                58                                 January 2005

-------
       •       determination of corrective action that will eliminate the cause of
              nonconformities; and
       •       application of controls to ensure that corrective action is taken and that it is
              effective.

       The procedures for preventive action should include:

       •       the use of appropriate sources of information, such as processes and work
              operations that affect product quality, concessions, audit results, quality records,
              service reports, and customer complaints to detect, analyze, and eliminate
              potential causes of nonconformities;
              determination of the steps to be taken to deal with any problems requiring
              preventive action;
              initiation of preventive action and application of controls to ensure that it is
              effective; and
       •       confirmation that relevant information on actions taken is submitted for
              management review.

       Refer to U.S. EPA, 2000c for more information on corrective and preventive actions.

7.2    VERIFICATION AND ACCEPTANCE
 Basic Quality Principle
 Verification is confirmation by examination and provision of objective evidence that specified
 requirements have been fulfilled. Though it is related to the concept of assessment,
 verification is usually considered an ongoing line management responsibility, rather than as
 independent oversight.	
7.2.1   Verification Tools

       Verification involves identifying what goals should be met at various stages of operation
or evaluation and whether these goals are still achievable.  In some instances, for example, re-
evaluation of the process being used or evaluated may merit consideration. Updating of QC
specifications during the course of operation, changes in operation or construction activities, or
re-evaluation of set standards may be called for if operation does not proceed as planned. If re-
evaluation shows that initial QC specifications are not adequate, then the implementation plan
should identify a process for ensuring that appropriate changes can be incorporated and that
appropriate procedures for approval are followed. Who reviews the process? Who approves
changes? How many steps  of review are involved?  Review processes are included at different
stages of design, construction, and operation. These can be conducted prior to initiation of
operational start-up, subsequently as periodic reviews, or after major events, such as operational
maintenance.
EPAQA/G-11                                59                                  January 2005

-------
       Verification reviews provide a basic means of assessing the conformance to
specifications of any process or operation.  Appropriate technical reviews conducted within the
project ensure that project objectives are being or have been met. The key to conducting
successful reviews is to incorporate personnel who have the appropriate expertise to review the
portion of the project in question.  Qualifications of those being  solicited should be assessed by
line management before dedicating the resources for the review.

       Peer reviews can be similar to technical reviews.  They are conducted by someone who
was not involved previously in the planning process, but who has suitable qualifications to
provide valuable, previously unsolicited information.

       Document/records reviews should be performed to assess whether appropriate and
complete records are being maintained.  Records to be reviewed should include draft and final
reports, plans, procedures, and specifications; technical and peer review comments; steps taken
to incorporate comments; technical drawings and specifications; and any inspection or audit
reports.

       Management oversight typically involves informal inspections and observation of
processes. Project managers may perform such oversight as a way of observing day-to-day
activities and ensuring that the system is operating as called for in specified procedures. The
observer may not use any formal checklist, but rather may use his/her experience with similar
operations and knowledge of operating procedures to identify any obvious problems or failures
to operate the system as planned

       Results of the verification review process are recommendations reported to project
management, whose responsibility is to determine if review recommendations should be
implemented.  Contentious issues may be discussed with all personnel, but ultimate
responsibility to make organizational or project improvements resides with project management.

7.2.2   Reconciliation of As-Designed and As-Constructed Projects

       In constructed projects, discrepancies may develop between the contract documents and
the as-constructed project. Such discrepancies are a consequence of field conditions that are
different from those envisioned during design or construction problems whose resolutions result
in a contract change.  Reconciliation of as-designed and as-constructed conditions may involve
the development and implementation of a procedure to determine compliance with design
documents by the material supplier, fabricator, erector, constructor, etc., and the review and
approval of any necessary changes.

7.2.3   Validation

       Depending on the scale and sensitivity of the project, there may be a separate validation
step in addition to verification. Validation is normally performed under defined operating
conditions and on the final product, but may be appropriate in earlier stages prior to product

EPAQA/G-11                                60                                 January 2005

-------
completion. Validation activities are used to demonstrate that the designed product is an
acceptable representation of the process or the system for which it is intended, and that the
product performs within defined limits for each applicable parameter.

       In contrast to verification, validation is typically performed by an independent third
party. Project methods, test data (including any software-generated results), and conclusions
should be documented in a form that can be understood by an independent individual technically
competent to understand the particular item under study.  The documentation is then reviewed to
assess the correctness of the documentation in meeting the validation test specifications.
EPA QA/G-11                                 61                                  January 2005

-------
EPAQA/G-11                                  62                                   January 2005

-------
                                   REFERENCES

American Consulting Engineers Council (ACEC), 1989. Guide to the Use ofFIDIC Conditions
       of Contract for Works of Civil Engineering Construction.  Fourth edition. Washington,
       D.C.

American National Standards Institute/American Society for Quality Control (ANSI/ASQC),
       1994.  Specifications and Guidelines for Quality Systems for Environmental Data
       Collection and Environmental Technology Programs, American National Standard
       ANSI/ASQC E4-1994.  Milwaukee, Wisconsin.

American Society of Civil Engineers (ASCE), 1981. The Uniform Locations of Subject Matter
       and Information in Construction Documents. #1910-16. Reston, Virginia.

American Society of Civil Engineers (ASCE), 2000. Quality in the Constructed Project: A
       Guide for Owners, Designers, and Constructors. Second edition. Reston, Virginia.

International Federation of Consulting Engineers (FID 1C), 1992.  Conditions of Contract for
       Works of Civil Engineering Construction. Fourth edition. Geneva, Switzerland.

International Organization for Standardization (ISO), 2000. ISO 9001:2000. Quality
       Management Systems - Requirements.  Geneva, Switzerland.

Project Management Institute (PMI), 2000.  A Guide to the Project Management Body of
       Knowledge (PMBOKฎ Guide), 2000 Edition, ANSI/PMI 99-001-2000. Newtown Square,
       Pennsylvania.

U.S. Environmental Protection Agency, 2000a. Policy and Program Requirements for the
       Mandatory Agency-Wide Quality System,  5360.1 A2. Washington, D.C.

U.S. Environmental Protection Agency, 2000b. EPA Quality Manual for Environmental
       Programs, 5360 Al. Washington, D.C.

U.S. Environmental Protection Agency, 2000c. Guidance on Technical Audits and Related
       Assessments, EPA QA/G-7. EPA/600/R-99/080. Washington, D.C.
EPAQA/G-11                               63                                January 2005

-------
EPAQA/G-11                                  64                                   January 2005

-------
                                     APPENDIX A

                              TERMS AND DEFINITIONS

Activity - An all-inclusive term describing a specific set of operations or related tasks to be
performed, either serially or in parallel (e.g., research and development, field sampling,
analytical operations, equipment fabrication), that in total result in a product or service.

Assessment - The evaluation process used to measure the performance or effectiveness of a
system and its elements. As used here, assessment is an all-inclusive term used to denote any of
the following: audit, performance evaluation, management systems review, peer review,
inspection, or surveillance.

Audit  - The systematic, independent, and documented process for obtaining audit evidence and
evaluating it objectively to determine the extent to which  audit criteria are fulfilled [ISO 9000].

Auditee - The organization being audited.

Auditor - A person qualified to perform audits.

Authenticate - The act of establishing an item as genuine, valid, or authoritative.

Calibration - Comparison of a measurement standard, instrument, or item with a standard or
instrument of higher accuracy to detect and quantify inaccuracies and to report or eliminate those
inaccuracies by adjustments.

Characteristic - Any property or attribute of a datum, item, process, or service that is distinct,
describable, and/or measurable.

Confidentiality procedure - A procedure used to protect confidential business information
(including proprietary data and personnel records) from unauthorized access.

Configuration - The functional, physical, and procedural characteristics of an item, experiment,
or document.

Conformity - The fulfillment of requirements [ISO 9000].

Consensus standard - A standard established by a group representing a cross section of a
particular industry or trade, or a  part thereof.

Constructor - The party assigned by the developer in charge of technology construction. The
constructor's role should be specifically defined in the developer/constructor contract.
EPAQA/G-ll                                A-l                                 January 2005

-------
Contractor - Any organization or individual that contracts to furnish services or items or
perform work.

Corrective action - Action to eliminate the causes of a detected nonconformity or other
undesirable situation [ISO 9000].

Client - Any individual or organization for whom items or services are furnished or work
performed in response to defined requirements and expectations. See also Participant and User.

Deficiency - An unauthorized deviation from acceptable procedures or practices, or a defect in
an item.

Demonstrated capability - The capability to meet procurement technical and quality
specifications through evidence presented by the supplier to substantiate its claims and  in a
manner defined by the customer.

Design - Specifications, drawings, design criteria, and performance requirements. Also the
result of deliberate planning, analysis, mathematical manipulations, and design processes.

Design change - Any revision or alteration of an approved and issued design.

Design review - A documented evaluation by a team, including personnel such as the
responsible designers, the client for the work or product being designed, and a QA
representative, but other than the original designers, to determine if a proposed design will meet
the established design criteria and perform as expected when implemented.

Design team - The parties responsible for the design of an environmental technology
application.  Depending on the scope of the project, this may consist of one or more
professionals employed by the developer,  or it may include representatives of various contractors
and subcontractors as well.

Developer - The organization(s) responsible for site development and technology
construction/implementation.  The developer may be a single organization, as in the case of a
site-specific treatability study for which the technology developer is  also the site developer.  In
other cases, additional parties are involved, especially in the case of a large-scale technology
implementation.

Document - Information and its supporting medium [ISO 9000].

       NOTE:        A document may be any written, electronic, or pictorial information
                     describing, defining, specifying, reporting, or certifying activities,
                     requirements, procedures, or results.
EPAQA/G-11                                A-2                                January 2005

-------
Entity - That which can be individually described and considered, such as a process, product,
item, organization, or combination thereof.

Environmental data - Any measurements or information that describe environmental
processes, locations, or conditions; ecological or health effects and consequences; or the
performance of environmental technology. For EPA, environmental data include information
collected directly from measurements, produced from models, and compiled from other sources
such as data bases or the literature.

Environmental data operations - Work performed to obtain, use, or report information
pertaining to environmental processes and conditions.

Environmental programs - Activities involving the environment, including but not limited to
characterization of environmental processes and conditions; environmental monitoring;
environmental research and development; laboratory operations on environmental samples; and
the design, construction,  and operation of environmental technologies.

Evidentiary records - Records identified as part of litigation and subject to restricted access,
custody, use, and disposal.

Expedited change - An abbreviated method of revising a document at the work location where
the document is used when the normal change process would cause unnecessary or intolerable
delay in the work.

Extramural agreement - A legal agreement between EPA and an organization outside EPA for
items or services to be provided. Such agreements include contracts, work assignments, delivery
orders, cooperative agreements, research grants, state and local grants, and EPA-funded
interagency agreements.

Financial assistance - The process by which funds are provided by one organization (usually
government) to another organization for the purpose of performing work or furnishing services
or items. Financial assistance mechanisms include grants, cooperative agreements, and
government interagency  agreements.

Finding - An assessment conclusion that identifies a condition having a significant effect on an
item or activity. An assessment finding may be positive or negative and is normally
accompanied by specific examples of the observed condition.

Good engineering principles/practices - A broad set of QA, conservation,  and safety activities,
techniques, and approaches that are commonly accepted throughout the engineering profession.

Grade - The category or rank given to entities having the same functional use but different
requirements for quality.
EPAQA/G-11                               A-3                                January 2005

-------
Graded approach - The process of basing the level of application of managerial controls
applied to an item or work according to the intended use of the results and the degree of
confidence needed in the quality of the results.

Guideline - Conformity evaluation by observation and judgement accompanied as appropriate
by measurement, testing, or gauging  [ISO 9000].

Independent assessment - An assessment performed by a qualified individual, group, or
organization that is not a part of the organization directly performing and accountable for the
work being assessed.

Inspection - Examination or measurement of an item or activity to verify conformance to
specific requirements.

       NOTE:       Inspection may include activity such as measuring, examining, testing, or
                    gauging one or more characteristics of an entity and comparing the results
                    with specified  requirements in order to establish whether conformity is
                    achieved for each characteristic.

Item - An all-inclusive term used in  place of the following: appurtenance, facility, sample,
assembly, component,  equipment, material, module, part, product, structure, subassembly,
subsystem, system, unit, documented concepts, or data.

Management - Those individuals directly responsible and accountable for planning,
implementing, and assessing work.

Management system - A system to establish policy and objectives and to achieve those
objectives [ISO 9000].

May - Denotes permission but not a  requirement.

Measurement and testing equipment - Measuring instrument, software, measurement
standard, referenced material or auxiliary equipment or combination thereof to realize a
measurement process [ISO 9000].

       NOTE:       Such equipment may include tools, gauges, instruments, sampling devices
                    or systems used to calibrate, measure,  test, or inspect in order to control or
                    acquire data to verify conformity with specified requirements.
Method - A body of procedures and techniques for performing an activity (e.g., sampling,
chemical analysis, quantification) systematically presented in the order in which they are to be
executed.
EPAQA/G-ll                               A-4                                January 2005

-------
Must - Denotes a requirement that has to be met.

Nonconformity - Non-fulfillment of a requirement [ISO 9000].

       NOTE:       A nonconformity may include a deficiency in characteristic,
                    documentation, or procedure that renders the quality of an item or activity
                    unacceptable or indeterminate.

Objective evidence - Data supporting the existence or variety of something [ISO 9000].

       NOTE:       Objective evidence may include any documented statement of fact, other
                    information, or record, either quantitative or qualitative, pertaining to the
                    quality of an item or activity, based on observations, measurements, or
                    tests which can be verified.

Observation - An assessment conclusion that identifies a condition (either positive or negative)
which does not represent a significant impact on an item or activity.  An observation may
identify a condition which does not yet cause a degradation of quality.

Organization - A company, corporation, firm, enterprise, or institution, or part thereof, whether
incorporated or not, public or private, that has its own functions and administration.

Organizational structure - The responsibilities, authorities, and relationships, arranged in a
pattern, through which an organization performs its functions.

Owner - The company or organization  that has the lead role in the development of the  project
and implementation of the environmental technology in question.  The owner can be a private
firm that actually owns the property, or  it can be a site developer or architectural and engineering
design firm that has been hired by the owner to manage the environmental technology
installation from beginning to end, or it  may be the private- or public-sector organization
responsible for clean-up.

Participant - When used in the context of environmental programs, an organization, group,  or
individual that takes part in the planning and design process and provides special knowledge or
skills  to enable the planning and design  process to meet its objective.

Peer review - A documented critical review of work generally beyond the state of the art or
characterized by the existence of potential uncertainty.  The peer review is conducted by
qualified individuals (or organizations) who are independent of those who performed the work,
but are collectively equivalent in technical expertise (i.e., peers) to those who performed the
original work. The peer review is conducted to ensure that activities are technically adequate,
competently performed, properly documented, and satisfy established technical and quality
requirements.  The peer review is an in-depth assessment of the assumptions, calculations,
extrapolations, alternate interpretations, methodology, acceptance criteria, and conclusions

EPAQA/G-ll                                A-5                                 January 2005

-------
pertaining to specific work and of the documentation that supports them. Peer reviews provide
an evaluation of a subject where quantitative methods of analysis or measures of success are
unavailable or undefined, such as in research and development.

Performance evaluation - A type of audit in which the quantitative data generated in a
measurement system are obtained independently and compared with routinely obtained data to
evaluate the proficiency of an analyst or laboratory.

Pollution prevention (P2) - An organized,  comprehensive effort to systematically reduce or
eliminate pollutants or contaminants prior to their generation or their release or discharge to the
environment.

Procedure - A specified way to carry out an activity or process [ISO 9000].

Process - A set of interrelated or interacting activities which transforms inputs into outputs [ISO
9000].

       NOTE:        Examples of processes include analysis, design, data collection, operation,
                     fabrication, and calculation.

Project - unique process consisting of a set of coordinated and controlled activities with start
and finish dates, undertaken to achieve an objective conforming to specific requirements
including constraints of time, cost, and resources [ISO 9000].

Project team - The parties involved in the construction and/or operation of an  environmental
technology application. Depending on the scope of the project, this may consist of one or more
professionals employed by the developer,  or it may include representatives of various contractors
and subcontractors as well.

Responsible party - An individual or organization that has contributed to contamination
problems at a site or has assumed site responsibility and is therefore a participant in the
environmental technology application.

Qualified services - An indication that suppliers providing services have been evaluated and
determined to meet the technical and quality requirements of the client as provided by approved
procurement documents and demonstrated by the supplier to the client's satisfaction.

Quality - The degree to which a set of inherent characteristics fulfills requirements [ISO 9000].

       NOTE:        Quality may relate to a product or service regarding its ability to meet the
                     stated or implied needs and expectations of the user.

Quality assurance  - Part of quality management focused on providing confidence that quality
requirements will be fulfilled [ISO 9000].

EPAQA/G-11                                A-6                                 January 2005

-------
       NOTE:       Quality assurance may include management activities involving planning,
                    implementation, assessment, reporting, and quality improvement to ensure
                    that a process, item, or service is of the type and quality needed and
                    expected by the customer.

Quality assurance manager  - The individual designated as the principal manager within the
organization having management oversight and responsibilities for planning, coordinating, and
assessing the effectiveness of the quality system for the organization.

Quality assurance project plan  - A formal document describing in comprehensive detail the
necessary QA, QC, and other technical activities that must be implemented to ensure that the
results of the work performed will satisfy the stated performance criteria.

Quality control - Part of quality management focused on fulfilling quality requirements [ISO
9000].

       NOTE:       Quality control includes technical activities that measure the attributes and
                    performance of a process, item,  or service against defined standards to
                    verify that they meet the stated requirements established by the customer.

Quality improvement - Coordinated activities to direct and control an organization with regard
to quality [ISO 9000].

       NOTE:       Quality improvement is a management program for improving the quality
                    of operations. Such management programs generally entail a formal
                    mechanism for encouraging worker recommendations with timely
                    management evaluation and feedback or implementation.

Quality indicators - Measurable attributes of the attainment of the necessary quality for a
particular environmental decision. Indicators of quality include precision, bias, completeness,
representativeness, reproducibility, comparability, and statistical confidence.

Quality management - That aspect of the overall management system of the organization that
determines and implements the quality policy.  Quality management includes strategic planning,
allocation of resources,  and other systematic activities (e.g., planning, implementation, and
assessment) pertaining to the quality system.

Quality management plan - A formal document that describes the quality system in terms of
the organizational structure, functional responsibilities of management and staff, lines of
authority, and required interfaces for those planning, implementing, and assessing all activities
conducted.

Quality system - A structured and documented management system describing the policies,
objectives,  principles, organizational authority, responsibilities, accountability, and

EPAQA/G-11                               A-7                                 January 2005

-------
implementation plan of an organization for ensuring quality in its work processes, products
(items), and services. The quality system provides the framework for planning, implementing,
and assessing work performed by the organization and for carrying out required QA and QC.

Readiness review - A systematic, documented review of the readiness for the start-up or
continued use of a facility, process, or activity. Readiness reviews are typically conducted
before proceeding beyond project milestones and prior to initiation of a major phase of work.

Record (quality) -  document stating results achieved or providing evidence of activities
performed [ISO 9000].

       NOTE:       A record is a document that furnishes objective evidence of the quality of
                    items or activities and that has been verified and authenticated as
                    technically complete and correct. Records may include photographs,
                    drawings, magnetic tape, and other data recording media.

Reproducibility - The precision, usually expressed as variance, that measures the variability
among the results of measurements of the same sample at different laboratories.

Research development/demonstration - Systematic use of the knowledge and understanding
gained from research and directed toward the production of useful materials, devices, systems, or
methods, including prototypes and processes.

Self-assessment - An assessment of work conducted by individuals, groups, or organizations
directly responsible  for overseeing and/or performing the work.

Service - The result generated by activities at the interface between the supplier and the
customer, and by supplier internal activities to meet customer needs. Such activities in
environmental programs include design, inspection, laboratory and /or field analysis, repair, and
installation.

Should - Denotes a guideline or recommendation whenever noncompliance with the
specification is permissible.

Significant condition - Any state, status, incident, or situation of an environmental process or
condition, or environmental technology in which the work being performed will be adversely
affected sufficiently to require corrective action to satisfy quality objectives or specifications and
safety requirements.

Specification - A document stating requirements [ISO 9000].

       NOTE:       A specification is a document stating requirements and which refers to or
                    includes drawings or other relevant documents.  Specifications should
                    indicate the means and the criteria for determining conformity.

EPAQA/G-11                                A-8                                January 2005

-------
Source reduction - Any practice that reduces the quantity of hazardous substances,
contaminants, or pollutants.

Standard operating procedure (SOP) - A written document that details the method for an
operation, analysis, or action with thoroughly prescribed techniques and steps, and that is
officially approved as the method for performing certain routine or repetitive tasks.

Supplier - An organization or person that provides a product [ISO 9000].

       NOTE:       A supplier includes any individual or organization furnishing items or
                    services or performing work according to an agreement between two
                    parties, such as a contract or financial assistance agreement. This is an
                    all-inclusive term used in place of any of the following: vendor, seller,
                    contractor, subcontractor, fabricator, or consultant.

Surveillance (quality) - Continual or frequent monitoring and verification of the status of an
entity and the analysis of records to ensure that specified requirements are being fulfilled.

Technical review - A documented critical review of work that has been performed within the
state of the art.  The review is accomplished by one or more qualified reviewers who are
independent of those who performed  the work, but are collectively equivalent in technical
expertise to those who performed the original work.  The review is an in-depth analysis and
evaluation of documents, activities, material, data, or items that require technical verification or
validation for applicability, correctness, adequacy, completeness, and assurance that established
requirements are satisfied.

Technical systems audit - A thorough, systematic, onsite, qualitative audit of facilities,
equipment, personnel, training, procedures, record keeping, data validation, data management,
and reporting aspects of a system.

Traceability - The ability to trace the history, application, or location of that which is under
consideration [ISO 9000].

       NOTE:       In a calibration sense, traceability relates measuring equipment to national
                    or international standards, primary standards, basic physical constants or
                    properties, or reference materials.

User - When used in the context of environmental programs, an organization, group, or
individual that utilizes the results or products from environmental programs. A user may also be
the client for whom the results or products were collected  or created.

Validation - Confirmation, through provision of objective evidence that the requirements for a
specific intended use or application have been fulfilled [ISO 9000].
EPAQA/G-ll                                A-9                                 January 2005

-------
       NOTE:       For example, environmental data may be validated as having satisfied
                    specific precision and bias objectives.

Verification - Confirmation, through provision of objective evidence that specified
requirements have been fulfilled [ISO 9000].

       NOTE:       For example, environmental data claiming to satisfy specific precision and
                    bias objectives may be verified if the claim is true.

Work - the process of performing a defined task or activity

NOTE:       Work may include, but not be limited to, research and development, field
             sampling, analytical operations, and equipment fabrication.
EPAQA/G-11                               A-10                                January 2005

-------
                                     APPENDIX B

         GOOD ENGINEERING PRINCIPLES/PRACTICES APPLICABLE TO
                         ENVIRONMENTAL TECHNOLOGY
 DESIGN
        Fail-safe/intrinsically safe design of procedures, processes, equipment, structures, and
        facilities (e.g. alarms, gauges, relief valves, cut-off switches)
     •   Flexible built-in designed procedures, processes, equipment, structures, and facilities
     •   Design of self-correcting procedures and processes
 RESOURCE UTILIZATION
        Reuse of materials required for technology operation or development
     •   Reduced use of virgin materials, wastes generated, energy sources, and human
        resources
     •   Recycling/recovery of materials, utilities, and energy sources
     •   Conservation of materials and energy sources
        Analysis of availability and interchangeability of all resources, such as materials,
        personnel, and equipment
        Substitution of materials and energy sources with cleaner, better, cheaper, more
        reliable, and more readily available alternatives
 PROCESS OPERATIONS
        Use of commercially available and tested materials, products, processes, equipment,
        and  supplies
     •   Computerized/remote control of unit operations and processes
     •   Site surveys, including topographical, geological, hydrogeological, hydrological,
        seismic, wind and weather patterns, as well as social and economic factors
 PROCESS INTEGRATION
     •   Automatic communication/notification procedures and processes among all team
        members involved in technology implementation
     •   Integration of planning, design, purchasing/procurement, fabrication,
        construction/installation processes, and operation and maintenance procedures and
        requirements
        Integration/optimization of human, material, energy, and economic resources as well
        as logistical, political, social, environmental, and technical factors during each critical
        phase of the project
     •   Modeling and simulation of technical, logistical, economic, social, environmental and
        political systems prior to, during, and after installation/implementation
EPAQA/G-11                               B-l                                January 2005

-------
 PROJECT MANAGEMENT
        Sound project management principles/practices—for example, those outlined by the
        Project Management Institute (PMI) in^4 Guide to the Project Management Body of
        Knowledge (PMI, 2000)
 WORKER TRAINING
     •   Worker training/retraining, including hands-on training during technology
        construction and operation
     •   Worker registration/certification
     •   Certification/permitting of work procedures, processes, equipment, and environment
 SAFETY CONTROL MEASURES
        Automatic shutdown of systems, equipment, and processes
     •   Use of automatic safety/corrective action triggers in technical, logistical, political,
        social, environmental, and economic situations
     •   Use of interlocks as safety measures
     •   Use of lockout/tagout procedures and equipment during systems
        fabrication/installation and operations
        Prevention of calamities, such as spills, leaks,  runaway reactions, and
        explosions/implosions through process hazard analysis, hazardous operations analysis,
        failure mode and effects analysis, fault tree analysis, and incident investigations
 DOCUMENTATION CONTROL
     •   Backup/duplicate copies of documentation
     •   Maintaining/archiving electronic and/or paper copies
     •   Distribution/delivery/circulation list for control documents
     •   Document/records authentication and verification
 VERIFICATION PROCEDURES
     •   Document approval procedures
     •   Reviews—peer, project level, program level, organization, and legal
        Routine/periodic inspections, testing, and compliance audits of systems, procedures,
        processes, equipment, etc.
EPAQA/G-ll                              B-2                                January 2005

-------