&EPA
   United States
   Environmental Protection
   Agency
   Evaluating Renewable Energy Opportunities
   THE APACHE POWDER SUPERFUND SITE, BENSON, ARIZONA
   U.S. Environmental Protection Agency
   Superfund Redevelopment Initiative
February 2011

-------
Table  of  Contents
This document summarizes the renewable energy pre-
feasibility analysis conducted at the Apache Powder
Superfund Site.
Introduction                                    p. 1
Renewable Energy Analysis                      p. 2
Step One: Evaluate Renewable Energy Resources   p. 3
Step Two: Assess Site Suitability                   p. 4
Step Three: Consider Technology-Specific Criteria    p. 6
Step Four: Review Market and Incentives           p. 8
Summary of Findings                            p. 10
Resources                                     p. 12

-------
  ntroduction
For over  10 years,  the  United States Environmental
Protection  Agency  (EPA)  has  been working  with
communities to better understand how Superfund sites can
be returned to beneficial uses and  supporting Superfund
site reuse nationwide.  EPA  also strongly supports the
evaluation  of sites for reuse  through renewable  and
sustainable energy production.   Through efforts  such
as the  Superfund Redevelopment Initiative and  Re-
Powering America's  Lands Initiative, EPA is providing
resources to encourage alternative and renewable energy
generation at these sites.

In 2008, the Apache Powder Superfund Site, located near
Benson, Arizona, presented a  unique opportunity for EPA
to support the evaluation of renewable energy generation.
Ground water and soil contamination from prior disposal
practices was addressed by Apache Nitrogen Products,
Inc.  (ANP) with EPA oversight, and construction of
the  remedy was completed in 2008. ANP continues to
manufacture chemical products on portions of the site
and expressed interest in exploring opportunities for
renewable energy generation on remaining areas of the
site.
With the support of EPA's Superfund  Redevelopment
Initiative,  EPA Region  9  began to look at the site's
potential  for  renewable  energy  development.  A
preliminary screening identified the following key assets:

    •  Excellent solar power generation potential
    •  A large tract of available land ready for reuse
    •  Significant federal, state and local incentives for
      solar energy projects
    •  A willing and enthusiastic site owner

Based  on these assets,  EPA conducted  a  Renewable
Energy  Pre-Feasibility Analysis to provide ANP with
information on the site's potential for renewable energy
development  that could be compatible with the site's
remedy and the on-going manufacturing operations at the
ANP facility. The process and findings of this  analysis are
summarized in this document.
Top: Example of solar arrays installed at Nellis Air Force Base, Nevada. Bottom: ANP facilities at the Apache Powder Superfund Site, 2008.

-------
Renewable  Energy Analysis:  A  Four-Step  Process
A renewable energy pre-feasibility analysis assists site owners, stakeholders and EPA in determining whether a site may
be a candidate for renewable energy technologies. Following the analysis, site owners may develop a more detailed
feasibility study for a particular renewable energy technology or identify development partners and move forward with
renewable energy development. At the site, the four-step process for the analysis included:
   Evaluate Renewable Energy Resource: Determine
   the  availability  of  renewable  energy resources
   and identify the  renewable energy opportunities
   requiring further analysis.

2 Assess  Site  Suitability:  Identify  site-specific
   considerations such as access, topography and slope,
   remedial components, infrastructure,  the  existing
   uses and facilities.
  3  Consider  Technology-Specific   Criteria:   Identify
     technology-specific    considerations    such    as
     infrastructure requirements (including space and size
     requirements), energy generation and storage capacity,
     and costs for installation, operation and maintenance.

  4  Review  Market and  Incentives: Assess the  current
     renewable energy market and identify the federal, state
     and local  incentives available to promote renewable
     energy generation.
 Site Background
 Since 1922, ANP (formerly  the Apache Powder
 Company) has manufactured industrial chemicals and
 explosives.  Historically, these operations produced
 both solid and liquid wastes which were disposed of
 on the property owned and operated by ANP, resulting
 in ground water and soil contamination.

 Following initial  investigations at the  Site in the
 1980s, ANP removed all contaminated soils, with the
 exception of sediments and soils in several evaporation
 ponds, which were covered, re-graded  and capped
 in 2007. Deed restrictions in the form of a State of
 Arizona Declaration of Environmental Use Restriction
 (DEUR) were also placed on the ponds.
                  VICINITY MAP
          APACHE POWDER SUPERFUND SITE
                  COCHISE COUNTY, ARIZONA
                                           Douglas
                                  Mexico Sonora **9ua
                                           Pneta
The Apache Powder Superfund Site encompasses approximately nine square
miles and is located in a rural area of southeastern Arizona, southeast of
Tucson
 To address ground water contamination in the shallow
    •r-  •   .1      ,1       j     .1           r- .1
 aquifer in the northern and  southern areas of the
 site,  cleanup activities are  underway and long-term
 monitoring will continue. Cleanup activities utilizing green and renewable energy technologies include a constructed
 on-site wetland system. The constructed wetland system treats nitrate -contaminated ground water twenty four hours
 a day, 365 days a year.  This approach avoids chemical usage, energy consumption and waste generation associated
 with traditional treatment methods. During the start-up phase of the wetlands, solar power was used to circulate
 water between the wetland ponds.  Solar power is still used at the wetlands to power the flow meter for the system.

 In September 2008, EPA completed its Construction Completion report for the site, describing all completed cleanup
 activities.  The site is now in the long-term operations and maintenance phase of the Superfund cleanup process.

-------
Step  One:  Evaluate  Renewable  Energy  Resources

The renewable energy analysis for the site began with an assessment of available renewable energy resources, to
identify which renewable energy resource(s) might merit further analysis. Solar and wind were identified using readily
available information. Other renewable energy opportunities, such as biomass and geothermal energy, did not merit
further analysis, due to limited availability or other restrictions.
Regional  Energy  Resources

Wind Energy
In general, wind power can be well-suited to Superfund
sites because  of the size of some  sites and the presence
of transmission lines from previous industrial  facilities.
However, the quality of wind resources varies significantly
across the United States. According to current wind resource
data from  the  National Renewable Energy  Laboratory
(NREL), the site is not located in an area with strong wind
resources. Accordingly, the analysis concluded that the site
is likely not well-located to  support a financially viable
location for a grid-connected wind turbine project.
      This EPA partnership with the Department of Energy
      and NREL is encouraging RE development on current
      and formerly contaminated  land and mine sites. The
      initiative  identifies the  renewable  energy  potential
      of these sites and  provides useful  resources for
      communities,  developers,  industry,  state and  local
      governments and any other parties interested in reusing
      these sites for renewable energy development.

      The  initiative  also provides  the  Renewable Energy
      Interactive Mapping Tool (See the Resources section).
      The Tool makes it possible  to view  EPA's renewable
      energy siting information for contaminated lands and
      mine sites alongside information on renewable energy
      resource availability and relevant Google Earth data.
Solar Energy
Most of the United States has access to adequate-to-good quality solar resources; all of Arizona, including the site,
enjoys  "excellent" quality resources, according to NREL. Arizona is also expected to rely heavily on solar energy
in order to meet future renewable energy requirements like the state's renewable portfolio standard, which requires
that electricity  providers in the  state obtain at minimum  15% of their power from renewable energy resources by
2025. Projections indicate that upwards of 65% of the state's renewable energy demand in 2025 will be met by solar
energy projects. Accordingly, EPA's renewable energy analysis led to the development of a Solar Energy Information
Memorandum in 2008, confirming the need to further investigate the potential for solar energy production at the site.

                                                            The  Memorandum's  findings  indicated  that
                                                            the availability of excellent solar resources and
                                                            available federal and state policies and incentives
                                                            made solar energy development a potentially
                                                            viable option at the site. Evaluating on-site energy
                                                            demands and infrastructure is another important
                                                            consideration in this first step of evaluating the
                                                            energy resource.
**
                                                            Figure 1: National solar photovoltaics (PV) resource potential
                                                            for the United States. Arizona and the Site have excellent solar
                                                            potential. Source: NREL

-------
Local Demand and  Infrastructure
Energy Needs:  ANP purchases all of its electricity from
Sulphur Springs Valley Electric Cooperative (SSVEC).
Manufacturing  options at the site require a  constant
supply of 1MW to meet base energy demand, with a
2MW daily peak.

Transmission Capacity: Land on ANP property is leased
by SSVEC for use by a 69kV electrical substation with a
line capacity of 40MW.  While the existing substation's
capacity is adequate for current ANP operations, planned
substation and line upgrades will have a 100MW capacity.
Based on this information,  EPA developed two  solar
generation scenarios for further analysis:
On-site Use
•   Provide ANP with an on-site energy source for all or
    a portion of the facility's electrical use
•   Provide  on-site  steam to  support manufacturing
    operations
Grid Use
•   Generate  utility  scale  energy  for the  grid  with
    potential energy and economic benefits to ANP

To further evaluate these energy generation scenarios, the
remaining steps of the analysis focuses on two types of
solar technologies: photovoltaic  (PV) and concentrating
solar power (CSP).
Step  Two:  Assess  Site  Suitability

After determining resource availability and demand,
EPA assessed the suitability of different site areas
for solar development.  First, the effort mapped
existing site conditions. As illustrated in Figure 2,
the site includes several large, flat contiguous areas
unrestricted by natural or constructed features.
Areas shown in green represent land with  a slope
of less than 5%.  Paved roads are shown  in grey
and internal site roads are shown in tan.  Remedial
components  are  indicated  in yellow  and were
excluded from the assessment due to potential
regulatory conflicts. Additional infrastructure such
as rail lines and site facilities are also shown.
                                              Figure: 2 Existing Conditions Suitability Analysis

-------
Potential Solar Development Zones
Based on site features, six potential solar zones were identified (see Figure 3 below). Zone criteria included:
     •   Contiguous areas greater than 15 acres
     •   Areas with less than 5% slope
     •   Road access
     •   Proximity to infrastructure
     •   Areas with washes, remedy components and facilities excluded
At 25+ acres, Zones A, B and C were all large enough to support CSP technology.  All six zones could support PV
technology, which could be installed on areas as small as 15 acres. The resulting area with potential for either CSP or
PV development totalled 185 acres (see
table below for zone acreages).
                                            I
                                            ^
  Potential Solar Zones
  CSP Potential
  Zone A     70 acres
  Zone B     25 acres
  Zone C     35 acres
            130 Total Acres
  PV Potential
  Zones A-C   130 acres
  Zone D     15 acres
  Zone E     20 acres
  Zone F     20 acres
            185 Total Acres
  Net PV/CSP Potential
            185 Total Acres
                                                                                            SITE FEATURES
                                                                                               | Paved Public Road

                                                                                                 Internal Site Roads

                                                                                                 Major Railroad

                                                                                                 Internal Rail Spurs

                                                                                                 Buildings

                                                                                                 Major Washes

                                                                                                 25'Contour

                                                                                                 5'Contour

                                                                                             C	3 Remedy Component
                      Figure 3: Potential Zones for Solar Development

-------
Step  Three:  Consider Technology-Specific  Criteria

The analysis next evaluated each solar technology based on technology-specific opportunities and constraints.  PV
systems use solar electric panels to directly convert the sun's energy into electricity.  CSP systems generate electricity
through the use of long mirrors that focus light on a tube of fluid. The concentrated rays boil the fluid (usually water),
and the resulting steam drives turbines, generating electricity. Facilities at the site already rely on steam in production
processes and could potentially use the steam produced by  CSP systems to meet on-site production demand.  PV
systems and CSP systems could both take advantage of the abundant solar resources available at the site. However,
each technology has specific requirements that may make it more or less suitable for use at the site. The table below
summarizes some of the key differences in technology requirements for CSP and PV systems. CSP systems, for example,
require large, contiguous land areas, use significant amounts of water, and can store energy. PV systems, in contrast, can
be located on smaller land areas, do not use much water, and do not have any storage capacity.

Concentrating  Solar  Power  (CSP) and Photovoltaic  (PV):  Key Differences
       Solar
   Technology Type


        CSP


         PV
                 Acres per MW


                    3-8
                  acres / MW

                    4-10
                  acres / MW
Minimum Practical
    Acreage


  40 - 50 acres


      N/A
   Site Needs
Large, contiguous,
   level area
    Flexible
Storage
Capacity


  Yes


  No
*Estimates can vary based on specific technology
Estimated Annual
  Water Usage*


   Significant


   Negligible
                                                                                                 /
                                                          Inverter
                                                            and
                                                        Transformer
Solar Tracking Array
Photovoltaic systems make use of highly purified
silicon that functions to convert sunlight directly
into electricity, which can be used in place or
supplied and distributed to the power grid, as
depicted above.
                                                                                     Image Source: U.S. EPA
                                                                         Steam condenser
              Concentrating solar power systems indirectly
              generate electricity and essentially consists of
              two parts: one part that collects solar energy and
              converts it to heat and the other that converts
              the heat energy to electricity (see image to the
              right). This system can generate power around
              the clock through the use of its thermal storage
              capabiliies, not just when the sun is shining.
                                                                                           Receiver
                                            Generator
                                                  Turbine'
                                                                                  Parabolic Troughs
                                                                                  Image Source: U.S. Department of Energy

-------
Comparative  Analysis
To further understand the implications of CSP and PV systems for solar power generation at the site, EPA conducted a
comparative analysis of capital and operations costs for a 5MW PV installation and a 10MW CSP installation. Findings
from the analysis are presented in the table below.
                                  Estimated    Est|mated                     Estimated Annual   Estimated Annual
 _ .   _  .       _     Acres per   _  ....  _.     Land Area   Estimated Capita        «».. r.            m *
 Solar Technology Type      MJ     Facility Size               Cost ($ 1000)*        O&M Cost         Water Usage
                                    (MW)       (acres)                           ($ 1000)*          (gallons)
 MW
 CSP Trough
 No Storage
 No Storage Air Cooled
 With Six-hour Storage
 Linear-Fresnal
 Reflector

 PV

 Thin Film
 (fixed axis)
             10
             10
             10
             10
  50
  50
  80
 30
$45,000 -
 60,000


$65,000 -
 70,000


$50,000 -
 65,000


$30,000 -
 35,000
$1,250- 1,500
$1,250- 1,500
$1,400- 1,600
20,000,000
 2,300,000
$1,300-1,600    25-30,000,000
                       30-40     $25,000-30,000     $400-600
20,000,000
                                                  Negligible
 Crystalline Silicon
 (fixed axis)
4-5
20-25     $30,000-36,000      $450-600
                                    Negligible
 PV Tracking
                       40-50     $35,000-40,000    $900-1,100
                                                  Negligible
*Estimates based on 2009 cost approximations to provide a relative comparison of the two different technologies.

As outlined  in the table  above, minimal capital investment anticipated  for  solar
technology ranges from approximately $25 million for a 5MW PV facility to up to $70
million for a 10MW CSP facility. In general, CSP systems can generate more power
on less land but require significant amounts of water in comparison with PV systems.
Additional technology-specific considerations include:


  •   CSP economic  viability  is  most  likely achieved at 200-3OOMW  facilities.
      However, the potential for re-purposing the  steam produced by CSP technology
      could increase the viability of a smaller facility at the site.


  •   Facilities larger than 5MW would also require substation and line upgrades that
      could be met as part of planned upgrades.
                                                                                    Top: Tracking PV panels follow the
                                                                                   sun to allow for increased solar
                                                                                   capture. Bottom: Fixed axis PV
                                                                                   panels aligned to be south facing.

-------
Step  Four:  Review  Market  and  Incentives

Finally, EPA's renewable energy analysis looked at market conditions and the availability of federal, state and local
incentives to help make solar development at the site viable. The analysis found that the site is located in a growing
solar market and ANP could benefit from both policy-based and financial incentives.

Solar Energy Market

In general, Arizona has excellent solar resources statewide and there are expectations for a growing market for renewable
energy development, based on several factors:

  •   The state's dependence on natural gas as a source of electricity, given the price volatility of natural gas
  •   The state's proximity to large potential solar markets
  •   Intellectual capital resources at in-state universities and research centers
Across the state, the amount of installed grid-tied solar capacity has steadily increased:
  •   PV system installations quadrupled in Arizona between 2008 and 2009
  •   In 2009, 23MW of PV capacity was installed in Arizona.  This capacity is expected to increase significantly in
     coming years, with large projects like  the proposed 280MW Solana solar thermal project in Gila Bend
  •   Arizona ranked fourth nationally in installed solar energy capacity in 2009 (behind California, New Jersey and
     Colorado)
   Generation and Sale of Electricity
   Utilities or their affiliates provide power generation, high-voltage transmission lines and low-voltage distribution.
   Energy providers can sell their power in two primary ways: wholesale and retail.  Power sold at "wholesale" is
   primarily done for large-scale utility providers.  Power sold at "retail" is usually done for individual customers
   or facilities.
   Two types of purchasing agreements are commonly used by energy generators and utilities:
     •  Retail Purchasing Agreement: May be advantageous for the provider and the buyer if an individual facility owner
        (such as ANP) can provide inexpensive land access to an energy developer in  exchange for cheaper utility rates
        for a set number of years. Additionally, this option may work well if there are too many costs associated with the
        developer's ability to access the utility grid.  In this case, the individual facility may benefit from consuming all
        energy generated on site.
     •  Wholesale Purchasing Agreement: May be more economically beneficial to a landowner/energy developer if a
        utility company is looking to increase its overall power generation.

-------
Renewable  Energy  Incentives
The analysis found that, in Arizona, there are significant incentives available to facilitate the development of renewable
energy projects for solar energy.  Incentives are available at the local, state and federal levels and include both policy-
based incentives (e.g., renewable portfolio  standards) and financial incentives (e.g., tax credits and rebates).  The
incentives identified by the analysis are presented below.

                     Incentive Description
      Federal
    Incentives
Business Energy Tax Credits: 30% tax credit to partially offset the upfront installed cost
of a solar system. Also known as Investment Tax Credits (ITCs)
Modified Accelerated Cost Recovery:  Current method of accelerated asset depreciation
required by the United States income tax code
Clean Renewable Energy Bonds (CREBs): Bonds to provide a federal tax credit for the
bond owner in lieu of interest payments from the issuer.
       State
    Incentives
  Renewable  Energy Standard (RES):  Arizona has legislated a 15% RES by 2025.
  Investor-owned utilities serving retail customers will be subject to the standard. Further,
  by 2011, 30% of renewables must come from distributed generation sources such as
  commercial and residential projects.  The 15% RES goal is mandatory for investor-
  owned utilities, energy cooperatives must also meet renewable energy goals.

  Renewable Energy Credits (RECs):  RECs are tradable commodities decoupled from
  electricity generation. An REC is equal to IMWh of power generated in the course of
  one year from a renewable source. RECs can amount to 30-70% of a solar project's
  anticipated revenue stream.  Market prices for RECs can vary significantly, Arizona's
  RES allows RECs to be banked and withdrawn at a later date.

  Solar Energy Property Tax Exemption: Applies to  "solar energy devices and any other
  device or system designed for the production of solar energy for onsite consumption."

  Commercial/Industrial Solar Energy Tax Credit Program:  10% of the installed cost of
  a solar device, not to exceed  $50,000 per business  per tax year.
   Local Utility
    Incentives
  Upfront incentives (purchase price incentives):  One-time, upfront incentive or rebate
  based on the size of the solar system. SSVEC offers both commercial and residential
  solar rebates.

  Production-based incentives: An incentive paid out based on actual kWh production of
  a renewable energy system over time instead of an initial, upfront incentive payment.

-------
Summary  of   Findings

The  Renewable  Energy Pre-Feasibility Analysis for
the Apache Powder Superfund site yielded several key
findings, including:

  •   The site could potentially support direct use and
      utility-scale solar development (PV preferred)

  •   Solar energy development could be compatible
      with the site's existing characteristics

  •   A project would face high upfront capital costs
      for both CSP and PV systems (approximately $25
      million for PV and $35 million for CSP)

  •   The ability to use incentives and obtain a long-
      term power purchase agreement would likely be
      critical for the economic viability of a utility-scale
      project at the site

Land  Availability
The site has sufficient acreage in areas with appropriate
slope  and infrastructure access to support a solar energy
project. Analysis identified 100-130 acres of contiguous
land and up to 185 acres of non-contiguous land that could
be suitable. Analysis did not include remedy component
areas, since sufficient acreage was available elsewhere on
the site. The available acreage could support a 15-45MW
PV facility.  Alternatively, the acreage could support a
20MW CSP facility that includes a storage capacity of up
to six  additional hours or a 40MW facility with no storage
capacity.

Potential solar energy generation scenarios include on-
site use and grid use.  On-site use will not cover all of
ANP's energy needs but could provide ANP with an on-
site energy  source to reduce peak  electricity demand.
Grid use could generate utility-scale energy for the grid
with potential energy use and economic benefits for ANP.
Solar Technologies
Analysis of solar technologies focused on a 5MW PV
installation and a  10MW CSP installation.  Currently,
the economic viability of a CSP system is most likely
achieved at 200-300MW facilities, although the potential
for repurposing the steam produced by CSP technology
could increase the viability of a smaller facility at the site.
However, water resource availability and cost challenges
in the  southwest could make the  technology  difficult
to implement due to its significant water requirements.
The minimal capital  investment anticipated for  solar
technology at the  site range from approximately $25
million for a 5MW PV facility to up to $70 million for a
10MW CSP facility.  Facilities larger than 5MW would
also require substation and line upgrades.

In conclusion, the site could potentially support both CSP
and PV technologies. Given the large  amount of acreage
available, solar energy development would be compatible
with the site's existing characteristics.  However,  there
are high-upfront capital costs for installation of both CSP
and PV technologies. ANP's ability to use incentives and
obtain a long-term power purchase agreement  is likely
critical to the economic viability of a utility-scale project
at the site.
    5MW r
    4MW
    3MW
    2MW
    1 MW
I  |  December
Q  June
I  |  Annual Average
                              ' Apache Peak Demand
                              1 Apache Baseload Demand
                                                                          12
                                                                                18
                                                                                     24 Hours
                                                           Hypothetical daily generation for a 5MW PV array demonstrates
                                                           how an on-site facility could help reduce peak electricity demand.

-------
Next Steps
Based on the potential opportunities highlighted in the
Renewable Energy Pre-Feasibility Analysis, ANP moved
forward with two potential solar projects: a solar awning
and canopy for existing facilities and a utility-scale solar
development.
Solar Awning and Canopy
In November of 2010, ANP completed construction of a 41
kW solar canopy. The solar canopy offsets approximately
45% of ANP's annual office energy use, saving $6,000
annually. ANP was able to construct this system utilizing
various  federal, state and local tax credits, resulting  in
minimal capital investment on the  part of the company.
The structure does not impact the integrity of the building
and  is  designed   to  be   completely  free-standing on
perimeter steel beams. The beams  will be covered  with
stucco to blend with the existing architecture.
Utility-Scale Solar Project
Following  discussions with an  energy developer, the
capped ponds on site were identified as an ideal setting for
installing a solar project.  The closed ponds are expected
to support a 1MW facility.  Further development would
expand onto adjacent land included in the pre-feasibility
analysis.

The technology being proposed by the developer is high
concentration photovoltaic (HCPV) technology that uses
a two-axis tracking system.  This technology was chosen
over CSP because of its low water use.  ANP anticipates
that five or more MW of power could be generated on the
southern area of the site.

Two potential partners have been identified for the project
-  a  local partner interested in sponsoring renewable
energy projects and a manufacturer with a technology
well-suited to the site.  The next step will be to  identify
a utility interested in buying the electricity generated by
the project.
Lessons Learned
The development of renewable energy technologies is a
complex process reliant on available incentives, multiple
parties,  market conditions and  other factors  that have
to be  identified and managed throughout a project.  As
the Renewable Energy Pre-Feasibility Analysis for  the
Apache Powder Superfund site illustrates, contaminated
lands  can provide opportunities for significant renewable
energy projects that contribute  to a sustainable future.
Key lessons learned from this process that could help
guide  similar projects at contaminated lands across  the
country include:

  •   A pre-feasibility analysis, as outlined  here, can
      assist in  determining whether a site might be a
      candidate for renewable energy technologies and
      merit additional evaluation.

  •   While utility-scale renewable  energy projects can
      be complex, public-private partnerships and other
      resources help ensure that these complexities can
      be addressed and managed.

  •   Solar projects can be located in many places and at
      different scales

Since  the  inception of the Superfund  program, EPA
has been  building  on  its  expertise  in conducting
site characterization  and  remediation to ensure  that
contamination is not a barrier to  the reuse of property.
Today, consideration of future use is an integral part of
EPA's cleanup programs, from initial site investigations and
remedy selection through to the design, implementation,
and operation and maintenance  of a site's remedy. EPA
is working nationwide with public and private partners
like ANP to encourage solar and other renewable energy
development  opportunities on current  and formerly
contaminated lands. Please see the Resources section on
the next page for additional information.

-------
    Resources
    Region 9 Superfund:  http://www.epa.gov/region9/superfund

    Superfund Redevelopment Initiative: http://www.epa.gov/superfund/programs/recycle

    Re-Powering America Renewable Energy Interactive Mapping Tool:  http://epa.gov/renewableenergyland/mapping_tool.htm

    Solar Energy Industries Association (SEIA) and the Prometheus Institute. "US Solar Industry: Year in Review." June 2009.

    U.S. Department of Energy. National Renewable Energy Lab. "Power Technologies Energy Data Book." August 2006.

    U.S. Environmental Protection Agency. Office of Solid Waste and Emergency Response. "Siting Clean and Renewable
    Energy on Contaminated Lands and Mining Sites." September 2008.

    Solar Energy Industries Association: http://www.seia.org

    Database of State Incentives for Renewables & Efficiency (DSIRE): www.dsireusa.org

    EPA Renewable Energy Maps: http://www.epa.gov/renewableenergyland

    DOE Solar Energy Technologies Program: http://wwwl.eere.energy.gov/solar

    National Renewable Energy Lab (NREL) Solar Research:  http://www.nrel.gov/solar

    NREL Renewable Energy Resource Maps: http://www.nrel.gov/renewable_resources

    NREL Solar Advisor Model: https://www.nrel.gov/analysis/sam
&EPA
      United States
      Environmental Protection
      Agency
      Andria Banner
      Environmental Scientist and Remedial Project Manager
      U.S. EPA Region 9

      (415)972-3189
      benner.andria@epa.gov

-------