Property Cleanup Schedule
South Minneapolis Residential Soil Contamination Site
South Minneapolis, Minnesota
April 2009
START
PROPERTY CLEANUP
SUMMER 2009
Franklin
pFINISH
PROPERTY CLEANUP
FALL 2011
CMC
Lite Yard
Site
Powderhorn
Park
Lake Park
EPA's planned approach
This figure represents EPA's planned approach to the work schedule for the South Minneapolis
Residential Soil Contamination Superfund Site. EPA hopes to begin cleaning up properties this summer, if
funding is granted. It may take over 2 years to complete cleaning up the more than 480 properties. We
plan to begin work in the northeast area and work clockwise around the site area. As we get closer to
starting work a more specific schedule will be announced.
Contact Tim Prendiville for questions on the cleanup at 312-886-5122, or prendiville.timothy@epa.gov.
------- |