Final Version-May, 2005
                                 SRI/USEPA-GHG-QAP-34
                                          May, 2005
    Test and Quality Assurance
    Plan
    ECR Technologies, Inc.
    Earthlinked Ground-Source Heat Pump
    Water Heating System
                      Prepared by:
             Greenhouse Gas Technology Center
                Southern Research Institute
                Under a Cooperative Agreement With
            U.S. Environmental Protection Agency

-------
Final Version-May, 2005
                                           EPA REVIEW NOTICE

     This report has been peer and administratively  reviewed by the U.S. Environmental Protection Agency, and
     approved for publication.  Mention of trade names or commercial products does not constitute endorsement  or
     recommendation for use.

-------
Final Version-May, 2005
                                                        SRI/USEPA-GHG-QAP-34
                                                                    May, 2005
        Greenhouse Gas Technology Center
       A U.S. EPA Sponsored Environmental Technology Verification ( EJY) Organization
                    Test and Quality Assurance Plan
                         ECR Technologies, Inc.
                Earthlinked Ground-Source Heat Pump
                         Water Heating System
                                 Prepared By:
                         Greenhouse Gas Technology Center
                            Southern Research Institute
                                 PO Box 13825
                       Research Triangle Park, NC 27709 USA
                             Telephone: 919/806-3456
                                 Reviewed By:
           ECR Technologies, Inc.
           Southern Research Institute Quality Assurance
           U.S. EPA Office of Research and Development

                    Kl  indicates comments are integrated into Test Plan

-------
Final Version-May, 2005
                                    (this page intentionally left blank)

-------
Final Version-May, 2005
         Greenhouse Gas Technology Center
        A U.S. EPA Sponsored Environmental Technology Verification fETr ) Organization
                     Test and Quality Assurance Plan
                           ECR Technologies, Inc.
                Earthlinked Ground-Sourced Heat Pump
                           Water Heating System
This  Test and Quality Assurance Plan has been reviewed and approved by the Greenhouse Gas
Technology Center Project Manager, Quality Assurance Manager, and Center Director, the U.S. EPA
APPCD Project Officer, and the U.S. EPA APPCD Quality Assurance Manager.
Tim Hansen                  Date
Center Director
Greenhouse Gas Technology Center
Southern Research Institute
David Kirchgessner
APPCD Project Officer
U.S. EPA
Date
Bob Richards                 Date
Project Manager
Greenhouse Gas Technology Center
Southern Research Institute
Robert Wright                Date
APPCD Quality Assurance Manager
U.S. EPA
Richard Adamson             Date
Quality Assurance Manager
Greenhouse Gas Technology Center
Southern Research Institute

Test Plan Final: 04 May 2005

-------
Final Version-May, 2005
                                    (this page intentionally left blank)

-------
Final Version-May, 2005
                              TABLE OF CONTENTS
                                                                                 Page

1.0   INTRODUCTION	1-1
     1.1.  BACKGROUND	1-1
     1.2.  EARTHLINKED TECHNOLOGY DESCRIPTION	1-2
     1.3.  HOST FACILITY DESCRIPTION	1-2
     1.4.  VERIFICATION PARAMETERS	1-3
     1.5.  PROJECT ORGANIZATION	1-3
     1.6.  SCHEDULE	1-5

2.0   VERIFICATION APPROACH	2-1
     2.1.  TEST DESIGN	2-1
     2.2.  INSTRUMENTATION	2-1
          2.2.1.  EarthLinked and City Water Flow Meter	2-3
          2.2.2.  EarthLinked Inlet and Outlet Temperature	2-3
          2.2.3.  Hot Water System Supply and Circulating Water Temperatures	2-3
          2.2.4.  Tank #1 Temperature and System Pressure	2-3
          2.2.5.  Test Room Dry Bulb Temperature	2-4
          2.2.6.  Power Consumption	2-4
     2.3.  TEST PROCEDURES AND ANALYSIS	2-4
          2.3.1.  Water Heating Capacity and CoP Test Procedures	2-4
          2.3.2.  Water Heating Capacity Data Analysis	2-5
          2.3.3.  Standby Heat Loss Test Procedure	2-6
          2.3.4.  Standby Heat Loss Analysis	2-6
          2.3.5.  Long Term Monitoring Procedures and Analysis	2-7

3.0   DATA QUALITY	3-1
     3.1.  DATA QUALITY OBJECTIVE	3-1
     3.2.  INSTRUMENT SPECIFICATIONS, CALIBRATIONS, AND QA/QC CHECKS	3-1
     3.3.  INSTRUMENT TESTING, INSPECTION, AND MAINTENANCE	3-3
     3.4.  INSPECTION AND ACCEPTANCE OF SUPPLIES AND CONSUMABLES	3-3

4.0   DATA ACQUISITION, VALIDATION, AND REPORTING	4-1
     4.1.  DATA ACQUISITION AND DOCUMENTATION	4-1
          4.1.1.  Corrective Action and Assessment Reports	4-1
     4.2.  DATA REVIEW, VALIDATION, AND VERIFICATION	4-2
     4.3.  DATA QUALITY OBJECTIVES RECONCILIATION	4-2
     4.4.  ASSESSMENTS AND RESPONSE ACTIONS	4-3
          4.4.1.  Project Reviews	4-3
          4.4.2.  Audit of Data Quality	4-3
     4.5.  VERIFICATION REPORT AND STATEMENT	4-4
     4.6.  TRAINING AND QUALIFICATIONS	4-5
     4.7.  HEALTH AND SAFETY REQUIREMENTS	4-5

5.0   REFERENCES	5-1

-------
Final Version-May, 2005
                                   LIST OF FIGURES
                                                                                 Page
Figure 1-1         Project Organization	1-3
Figure 2-1         Plumbing Schematic and Sensor Locations	2-1
Figure 2-2         Electrical Schematic and Power Meter Locations	2-2
                                    LIST OF TABLES
                                                                                 Page
Table 3-1          Instrument and Accuracy Specifications	3-1
Table 3-2          QA/QC Checks	3-2
                                      APPENDICES
                                                                                 Page
Appendix Al: Power Meter and RTD QA / QC Checks	Al
Appendix A2: Flow Meter Checks and Water Heating Performance Crosscheck	A2
Appendix A3: SUT and Site Information	A4
Appendix B: Electric Power System Emission Reduction Estimates	Bl
Appendix C: Electric Power Simple Cost Savings Estimates	Cl

-------
Final Version-May, 2005
                                   DISTRIBUTION LIST
U.S. EPA
       David Kirchgessner
       Robert Wright

Southern Research Institute
       Stephen Piccot
       Tim Hansen
       Robert G. Richards
       Richard Adamson

ECR Technologies, Inc.
       Hal Roberts
       Russ Bath

Johnson  Research, LLC
       Russ Johnson
                                            in

-------
Final Version-May,  2005
                              List of Acronyms and Abbreviations
ANSI         American National Standards Institute
ASHRAE     American Society of Heating, Refrigeration, and Air-Conditioning Engineers
Btu/h         British thermal units per hour
Btu/y         British thermal units per year
CoP          coefficient of performance
DQI          data quality indicator
DQO         data quality objective
DUT         device under test
ETV         Environmental Technology Verification
g/h           grams per hour
gal           gallon
gph           gallons per hour
kW           kilowatt
psia          pounds per square inch, absolute
psig          pounds per square inch, gauge
QA / QC      quality assurance / quality control
SUT         system under test
tpy           tons per year
                                              IV

-------
Final Version-May, 2005
                                   1.0  INTRODUCTION
1.1.   BACKGROUND

The  U.S. Environmental Protection  Agency's  Office of Research and  Development operates the
Environmental  Technology  Verification (ETV)  program to  facilitate the deployment of innovative
technologies. The program's goal is to further environmental protection by accelerating the acceptance
and use of these technologies.   Primary ETV activities are independent performance verification and
information dissemination. Congress funds ETV in response to the belief that many viable environmental
technologies exist that are not being used for the lack of credible third-party performance data.   With
performance data developed under this program, technology  buyers, financiers, and permitters will be
better equipped to make informed decisions regarding new technology purchases and use.

The Greenhouse Gas Technology Center (GHG Center) is one of several ETV organizations. EPA's ETV
partner, Southern Research Institute (Southern), manages the  GHG Center.  The GHG Center conducts
independent verification of promising  GHG mitigation and monitoring  technologies.  It  develops
verification Test and Quality Assurance Plans (test plans), conducts field tests, collects and interprets field
and other data, obtains independent peer-review input,  reports  findings, and publicizes verifications
through numerous outreach efforts.  The GHG Center conducts verifications according to the externally
reviewed test plans and recognized quality assurance / quality control  (QA / QC) protocols.

Volunteer stakeholder groups guide the GHG Center's ETV activities.   These stakeholders advise on
appropriate technologies for testing, help disseminate results, and review test plans and reports.  National
and international  environmental  policy,  technology,  and regulatory  experts participate in the  GHG
Center's Executive Stakeholder Group.  The group includes industry trade organizations, environmental
technology finance groups, governmental organizations, and other interested parties.   Industry-specific
stakeholders provide testing strategy guidance within  their expertise and peer-review key documents
prepared by the GHG Center.

GHG Center stakeholders are particularly interested in building heating and cooling technologies with the
potential to  improve  efficiency  and reduce concomitant GHG and criteria pollutant emissions.   The
Energy Information Administration reports that in 1999 approximately 3.1 million commercial facilities
in the U.S. consumed about 4.8 x 1012 British thermal units per year  (Btu/y). The portion of this energy
consumption that is attributable to water heating varies significantly by facility type, but it averages about
11%, or 5.3x10" Btu/y.

ECR Technologies, Inc. (ECR) has addressed this issue with their EarthLinked water heating system.  The
system incorporates a ground-sourced heat pump into a building's water heating system.  ECR states that
the  EarthLinked system may provide up to 70 % reduction in power consumption when compared to
electric water heating systems of equivalent capacity.   This  reduced energy consumption  would  also
reduce emissions from the electric power system's generators or natural gas combustion in direct-fired
systems. Broad utilization of such technologies could have  a  significant beneficial impact on GHG and
pollutant emissions.

This verification  is intended to quantify  the EarthLinked  system's performance  as  installed  in a
commercial  setting with credible measurement procedures  and analysis  techniques.   It  will assess
performance parameters of interest  to potential water  heater purchasers, users, regulatory  bodies, the
                                               1-1

-------
Final Version-May, 2005
public, and other stakeholders.  This test plan discusses the EarthLinked heat pump as the device under
test (DUT).  Its integration into the "real world" host facility is known as the system under test (SUT).

This test plan explicitly describes test equipment and procedures or by reference to existing American
National Standards Institute (ANSI) or American Society of Heating, Refrigerating, and Air-Conditioning
Engineers (ASHRAE) standards.  The following sections discuss the verification approach and specify
QA / QC procedures approved by independent reviewers.
1.2.   EARTHLINKED TECHNOLOGY DESCRIPTION

The EarthLinked system consists of two or more 50- or 100-foot copper refrigerant loops installed in the
ground, a compressor, a heat exchanger, refrigerant liquid flow controls, and an active charge control
refrigerant reservoir.   The EarthLinked  system is  unique because it circulates  non-ozone depleting
refrigerant (R-407c, R-134a) through the copper earth loops.  Other ground-source heat pumps circulate
either water or an antifreeze solution through plastic earth loops and then to a refrigerant heat exchanger.
The EarthLinked system's direct heat transfer from the refrigerant to the earth improves efficiency.

The liquid refrigerant absorbs heat from the ground, which is typically at a constant temperature  year
round (45-80 °F, depending on location), and vaporizes.  A compressor raises the refrigerant pressure and
routes it to a heat exchanger.  There, the vapor condenses and yields the latent heat of vaporization to
domestic water circulating through a heat exchanger. Refrigerant is then returned to the earth loops via a
patented refrigerant flow control device.

As installed at the test facility, this system preheats water in a commercial 120-gallon storage tank.  The
preheated water transfers to  a second commercial water heater which brings it to the required  130 °F
temperature.

The EarthLinked system consumes power in the compressor and hot water circulation pump, and has no
direct emissions.  ECR states that typical EarthLinked heating systems will initially be focused on small
commercial applications, such as restaurants and laundries.
1.3.   HOST FACILITY DESCRIPTION

The Lake Towers Retirement Community, located in Sun City Center, FL, will serve as the host facility.
Tests will occur at the Sun Terrace, a one-story building with two residential wings for assisted living.
Each wing has  15 rooms, each with a small vanity sink.  Other domestic hot water (DHW) uses include
two shower rooms, two utility closets, four nurses'  stations, and a kitchen.

The facility's DHW source consists of two 15 kilowatt (kW), 480 V electric water heaters.  Valves and
piping allow each tank to operate individually or in series. Each tank has sufficient capacity to serve the
facility by itself. Tank #1 can be heated either by the EarthLinked system or its electric elements. Cold
city water enters Tank #1 for the initial heating cycle.  The EarthLinked  system operates most efficiently
when heating cold water, so this configuration is optimal.

As the facility consumes DHW, the heated water transfers to Tank #2. A recirculation pump cycles hot
water from Tank #2 through the building's DHW piping and back to  Tank #2.  This tank maintains the
water temperature with its electric elements and the circulation ensures the immediate availability of hot
water at each tap.
                                               1-2

-------
Final Version-May, 2005
1.4.   VERIFICATION PARAMETERS

A series of short-term tests and long-term monitoring will determine the performance of the EarthLinked
system  as compared to the baseline electric resistance-type hot water heater.  Industry-accepted ANSI /
ASHRAE heat pump water heater test methods [1] will form the basis for the short-term tests. Short-term
test verification parameters are:
     •  water heating capacity at low and elevated temperatures, British thermal units per hour
        (Btu/h)
     •  DUT coefficient of performance (CoP) at low and elevated temperatures, dimensionless
     •  standby  heat  loss rate, Btu/h, and standby energy  consumption, kW, while operating
        with EarthLinked system at 120 ± 5 °F

Long-term monitoring will determine the  SUT performance in normal daily use.  Long-term verification
parameters are:
     •  difference between SUT electrical power consumption with and without the EarthLinked
        system, kW
     •  estimated EarthLinked CO, CO2,  and NOX emission changes as compared to the baseline
        electric water heater, grams per hour (g/h) or tons per year (tpy)
     •  estimated simple cost savings based on the price of electricity saved
1.5.   PROJECT ORGANIZATION
Figure 1-1 presents the project organization chart.
                U.S. EPA
            APPCD Project Officer
             David Kirchgessner
               U.S. EPA
      APPCD Quality Assurance Manager
            Robert Wright
          Southern Research Institute
           Quality Assurance Manager
              Richard Adamson
Southern Research Institute
 Environment and Energy
   Department Director
     Steve Piccot
                                            ETV GHG Center Director
                                                 Tim Hansen
     GHG Center
   Project Manager and
   Field Team Leader
     Bob Richards
ECR Technologies
   Joe Parsons
                               Advanced Energy
                                  Stakeholder
                                    Group
                                 Figure 1-1.  Project Organization
The GHG Center has overall verification planning and implementation responsibility.  The GHG Center
will coordinate  all participants' activities; develop, monitor, and  manage schedules;  and ensure the
                                                1-3

-------
Final Version-May, 2005
acquisition and  reporting of data consistent with the strategies in this test  plan.  The GHG Center
Director, Mr. Tim Hansen, will:
     •   review the test plan and report for consistency with ETV operating principles
     •   allocate appropriate resources for the verification
     •   oversee GHG Center staff activities

Mr. Joe Parsons of ECR is the technology developer's primary point of contact.  He or his designee will:
     •   review the test plan and report with respect to accuracy in the technology description and
        its application
     •   coordinate ECR's installation of the EarthLinked system, plumbing, fittings, or other
        permanent equipment that will remain at the site
     •   coordinate weekly operations during the long-term monitoring period

The GHG Center project manager, Mr. Bob Richards, will:
     •   coordinate the test plan, report, and Verification Statement writing and  review process
     •   oversee the field team leader's activities
     •   ensure collection, analysis,  and reporting of high-quality data and achievement of all
        data quality objectives (DQO)s
     •   maintain communications with all test participants
     •   perform budgetary and scheduling  review

The project manager will have authority to  suspend testing for health and safety reasons or if the QA/QC
goals presented in Section 3.0 are not being met.

Mr. Richards will also serve as the field team leader and will supervise all field operations. He will assess
data quality and will have the authority to repeat tests as deemed necessary to ensure achievement of data
quality goals.  He will:
     •   coordinate the installation of required plumbing fittings with ECR
     •   supervise and coordinate subcontractor activities
     •   install and remove temporary power- and water-metering equipment
     •   operate the water heater controls during the short-term tests
     •   collect interim test data for use in consultations with the project manager
     •   download data during the long term monitoring period
     •   perform other QA / QC procedures as described in Section 3.0

The field team leader will communicate test results to the project manager for review during the course of
testing.   The  field team  leader  and  project manager will collaborate on  all major project  decisions
including the need for further test runs or corrective actions.

The GHG Center QA manager, Mr. Richard Adamson, or his designee will review this test plan. He will
independently reconcile the measurement results with the data quality objectives  as part of a planned
audit of data quality. He will also review the verification test results, report, and conduct the audit of data
quality  described in  Section 4.0.  The QA manager will  report all internal audit and  corrective action
results directly to the GHG Center Director who will provide copies to the project manager for inclusion
in the report.

EPA's Office  of Research and Development will provide oversight and QA support for this verification.
The  Air Pollution Prevention and Control Division project officer, Dr. David  Kirchgessner,  and QA
manager, Mr.  Robert Wright, will review and approve the test plan and report to ensure that they meet
                                               1-4

-------
Final Version-May, 2005
EPA  QA goals and  represent sound scientific principles.  Dr.  Kirchgessner will  be responsible  for
obtaining final test plan and report approvals.
1.6.   SCHEDULE


The  tentative schedule of activities for the ECR EarthLinked ground source heat pump water heater
verification test is:

          Verification Test Plan Milestones                     Dates
          GHG Center internal draft development                 20 Dec. 2004 -15 Apr. 2005
          ECR review                                        18 Apr. 2005 - 27 Apr. 2005
          Industry peer review and plan revision                  29 Apr. 2005 - 06 May. 2005
          EPA review                                        09 May 2005 - 23 May 2005
          Final test plan posted                                23 May 2005

          Verification Testing and Analysis Milestones
          Short term testing                                   23 May 2005 - 27 May 2005
          Long term testing                                   28 May 2005 - 24 Jun. 2005


          Verification Report Milestones
          GHG Center internal draft development                 6 Jul. 2005 - 29 Jul. 2005
          ECR review                                        01 Aug. 2005 -15 Aug. 2005
          Industry peer review and report revision                 22 Aug. 2005 - 06 Sep. 2005
          EPA review                                        09 Sep. 2005 - 23 Sep. 2005
          Final report posted                                   30 Sep. 2005
                                                1-5

-------
Final Version-May, 2005
                                                     1-6

-------
Final Version-May,  2005
                            2.0 VERIFICATION APPROACH

This section describes  the GHG Center's verification approach,  the test  design, data collection, and
analytical methods.  The testing procedures and nomenclature generally conform to those provided in
ANSI / ASHRAE Standard 118.1-2003 [1] for testing "Type V" heat pump water heaters.  The following
subsections discuss test methods in detail and note any exceptions to the ANSI / ASHRAE specifications.

2.1.   TEST DESIGN

The GHG Center will first conduct a series of short-term tests to determine the DUT performance.  ECR
will install the  EarthLinked system  on Tank #1, with provisions to operate either the tank's electric
heating elements or the EarthLinked system.  GHG Center test personnel will isolate Tank #1 from the
facility's DHW system during the short-term tests;  the building will operate on Tank #2 during this
period.

The short-term tests will determine:
    •   DUT water heating capacity while raising the lowest achievable city water temperature
        (likely to be approximately  72 °F in Florida in June) 20 °F or to whatever temperature
        can be achieved over a 60-minute period, whichever occurs first, Btu/h
    •   DUT water heating capacity while raising the water temperature from 110 to  130 °F or
        over a 60-minute period (whichever occurs first), Btu/h
    •   CoP at the lower and elevated temperatures, dimensionless
    •   DUT standby heat loss rate, Btu/h and standby energy consumption, kW, at 120 °F

At the conclusion of the short-term series, test personnel will configure the SUT  for normal operations
such that Tank #1  initially heats incoming city water while Tank #2  maintains the  circulating water
temperature.  Test  personnel will  install  a second power  meter on Tank #2 to monitor  its power
consumption.

Long-term monitoring will begin with the Tank #1 heating elements operating for one week while the
EarthLinked system is  disabled.   The  second week, ECR operators will  set the controls so that the
EarthLinked system provides Tank #1 water heating  service. Test personnel will  download the data by
telephone, and this pattern will be repeated for at least four weeks.

Long-term monitoring results will allow assessment of:
    •   difference between SUT electrical power consumption with and without the EarthLinked
        system, kW
    •   estimated EarthLinked CO, CO2, and NOX emission changes as compared to the baseline
        electric water heater, g/h or tpy
    •   estimated simple cost savings based on the price of electricity saved
2.2.   INSTRUMENTATION

Figure 2-1 shows the water piping schematic diagram and the proposed test instrument locations. Figure
2-2 depicts the electrical wiring schematic and the power meter locations.
                                              2-1

-------
Final Version-May, 2005
                                                           Flow meter moved to monitor hot
                                                           water use during long-term monitoring
                                                                Pressure gauge installed
                                                                 temporarily prior to tests to
                                                                 acquire tank pressure
                                                                Temperature monitoring probe
                                                                 inserted into tank anode port
                                                                 ncorporates 6 evenly-spaced
                                                                 temperature sensors
EarthLinked heat pump
 temperature sensor com-
 pression fittings installed
 to face water flow
                                                                                                  EarthLinked heat pump
                                                                                                  flow meter location:
                                                                                                  at least 20 diameters from
                                                                                                  nearest upstream and 5
                                                                                                  diameters from nearest
                                                                                                  downstream disturbance
                                                                                                   valve, elbow, etc.
                                                                            Test room
                                                                            dry bulb
                                                                            temperature
                                                                            sensor
                          Figure 2-1. Plumbing Schematic and Sensor Locations
                                                                                                  Note:
                                                                                                  Tank#1  disconnect
                                                                                                  configured to switch
                                                                                                  between EarthLinked
                                                                                                  heat pump or tank
                                                                                                  elements.  They cannot
                                                                                                  operate at the same time.
                       Figure 2-2.  Electrical Schematic and Power Meter Locations
                                                         2-2

-------
Final Version-May, 2005
2.2.1.  EarthLinked and City Water Flow Meter

Water flow determinations to and from  the EarthLinked  system, combined with its  inlet  and outlet
temperature difference, will allow an independent calculation of the heating effect (see Section 3.2). The
ANSI / ASHRAE accuracy specification for flow rates is ± 1.0 %.

This verification will employ an Omega Model FTB-909 flow meter installed as shown in Figure 2-1. An
Omega Model FSLC-64 transmitter will condition the flow meter's pulse output.  An Agilent / HP Model
34970A will totalize and log the pulse output.  Accuracy of this system will be ± 0.5 %  of reading. The
nominal K factor for the flow meter is 322 pulses per gallon, but a pretest calibration will document
actual average K factor.

Note that test personnel will relocate the flow meter to the city water supply line at the beginning of the
long term monitoring period (see  Figure 2-1). This will allow normalization of the varying hot water use
rates throughout the period (see Section 2.3.5).
2.2.2.  EarthLinked Inlet and Outlet Temperature

The Type V (tank incorporated) verses Type IV (tankless) water heater QA / QC crosscheck discussed in
Section 3.2 requires EarthLinked inlet and  outlet temperatures.   The  ANSI /  ASHRAE accuracy
specification for the Type IV heat pump inlet and outlet temperature difference  is ± 0.2 °F.  This
verification will employ Class A 4-wire platinum resistance temperature detectors (RTD) whose specified
accuracy, including the Agilent / HP Model 34970A  datalogger,  is ± 0.6 °F.  This means  that the
combined accuracy for temperature difference will be ±0.8 °F, based on the specifications.  While this
combined accuracy does not meet the method specifications for Type IV water heaters, it is sufficient for
the QA / QC check.  The GHG Center will perform pretest calibrations and it is likely that an RTD pair
will be available whose combined accuracy is better than ± 0.8 °F.  Also,  analysts will account for and
report the achieved accuracy and its potential effects on the results.

Test personnel will install the direct immersion-type RTDs through compression fittings located as shown
in Figure 2-1.
2.2.3.  Hot Water System Supply and Circulating Water Temperatures

These  sensors  will contribute  to  system diagnostics and  data normalization  during the  long  term
monitoring period.  They will consist  of externally-mounted  Class  A 2-wire  RTDs wrapped  with
insulation.  Accuracy for the expected operating range is ± 1.4 °F.
2.2.4.  Tank #1 Temperature and System Pressure

The datalogger will record Tank # 1 temperatures from a probe inserted through one of the anode fittings
located in the tank's top.  Test personnel will temporarily remove the anode to allow probe access. The
temperature probe will incorporate 6 Class A 4-wire RTDs spaced throughout its length such that the tank
is divided into 6 equal portions from top to bottom.
                                              2-3

-------
Final Version-May,  2005
The ANSI / ASHRAE accuracy specification for water temperature is ± 2 °F.  RTD specified accuracy
will be ± 0.6 °F.

Determination of the water specific volume (see Sections 2.3.4, Eqn. 2-4 and 3.2, Eqn. 3-1) requires the
water pressure in pounds per square  inch, absolute (psia).  Test personnel will acquire the system gage
pressure, psig, by temporarily installing a Bourdon-type pressure gauge in the tank's anode fitting prior to
testing.  They will obtain local ambient pressure from a climbing altimeter or the barometric pressure as
corrected for altitude.  The ANSI / ASHRAE method has no specification for this  measurement, but the
bourdon gauge will be accurate to ± 3 % or better.
2.2.5.  Test Room Dry Bulb Temperature

The datalogger will record the test room dry bulb temperature from a single Class A 4-wire RTD located
at head height. The ANSI / ASHRAE accuracy specification for air temperature is ± 1 °F.  RTD specified
accuracy will be ± 0.6 °F.
2.2.6.  Power Consumption


The ANSI / ASHRAE accuracy specification for the power sensor (kW) is ± 1.0 %.

Power Measurements ION 7500 / 7600 power meters will record real power consumption at Tank #1 and
Tank #2 Power meter accuracy is ± 0.15 %.  Test personnel will install 0.3  % metering accuracy  class
current transformers (CTs) on each phase conductor.  The combined kW accuracy will be ± 0.3 % of
reading.
2.3.   TEST PROCEDURES AND ANALYSIS

Sections  2.3.1 through  2.3.4 discuss  the  short-term test procedures and  analyses while long term
monitoring appears in Section 2.3.5.  Note that nomenclature and equation symbols generally conform to
those cited in ANSI / ASHRAE Standard 118.1 [1].

2.3.1.  Water Heating Capacity and CoP Test Procedures

Test personnel will first perform the ANSI / ASHRAE water heating capacity and CoP tests for Type V
heat pump water heaters. Tests will incorporate at least 3 valid test runs at low and elevated temperatures,
or 6 total.

1.  Adjust supply and bypass valves for building DHW supply from Tank #2 and to isolate Tank # 1.
2.  Disconnect Tank #1 power, relieve the tank pressure, remove the protective anode on top of the tank,
and install the pressure gauge.
3.  Restore the  system pressure and record the pressure gauge reading as the system pressure.
4.  Relieve the tank pressure, remove the gauge, and install the Tank #1 temperature probe.
5.  Drain the tank completely, and refill with the coldest possible city water.
6.  Enable and verify data logging. The ION power meters will acquire kW data at 1-second intervals;
compute  and log 1-minute averages. The Agilent  datalogger will acquire all temperatures at 5-second
intervals; a laptop computer will calculate and log 1-minute averages.
                                             2-4

-------
Final Version-May, 2005
7.  Disable  Tank #1 heating elements,  record the mean tank temperature, T^o (the average of the 6
internal tank temperatures), and enable the EarthLinked system.  Note that all  manual field  records
(except for the system pressure recorded in Step #3) serve as diagnostic tools and start / stop signals only.
Analysts will calculate reported test results from the datalogger files after tests are completed.
8. Continue the test until Tmh has increased by 20 °F or until 60 minutes have elapsed. Record the final
mean tank temperature, T^f, and actual elapsed time (to the second) for the final T^f reading.
9. Perform the Type V vs. Type IV water heater cross check as outlined in Appendix A-2.
10. Repeat steps 5 through 8 until three valid test runs are completed.
11. Raise the mean  Tank #1 temperature, either with the heat pump or heating elements, to 110 °F.
12. Enable and verify data logging.
13.  Disable Tank #1 heating  elements, record the initial mean tank temperature, T^o, and enable the
EarthLinked system.
14. Continue the test until Tmh has increased by 20 °F or until 60 minutes have elapsed. Record the final
mean tank temperature, T^f, and actual elapsed time (to the second) for the final T^f reading.
15. Admit cold water into the tank while discharging heated water until T^ is less than 110 °F.  Raise the
mean tank temperature back to 110 °F.
16. Repeat steps 11 through 14 until three valid test runs are completed at the elevated temperature.
17. Acquire DUT and test facility data as noted in Appendix A-3.
18. Relocate flow meter for long term monitoring.
19. Configure valves and electric power controls for the  first long term monitoring cycle. Note the date,
start time, and configuration on the form in Appendix A-2.
2.3.2.  Water Heating Capacity Data Analysis

Water heating capacity (§ 10.3.2 of [1]) is:

                       (  C   ^
                    v *     p  \*(T   -T   }
                    V  \ ^  %  \  \-mhf  lmM)

               Qh =    l  V_,  \	+&                           Eqn-2-1
                            \Jh  I0h)

       where:
               Qh =  Water heating capacity, Btu/h
               V = Storage tank capacity, gal (116.3 for this test series)
               Cp =   Specific heat of water at the mean of Tmhf and Tmho (from [2]), Btu/lb.°F
               Cfg  = Volume conversion factor, 7.48055 gal/ft3
               v = Specific volume of water at the mean system pressure (from [3]), ft3/lb
               Tmhf = Final mean tank temperature (as the average of all 6 in-tank sensors), °F
               Tmho = Initial mean tank temperature (as the average of all 6 in-tank sensors), °F
               ta  = Final time stamp, h
               toh =  Initial time stamp, h
               Qhs  =  Mean storage tank heat loss rate as calculated in Section 2.2.4, Btu/h or as
                      estimated from manufacturer's data  (341.2 Btu/h for this test series)


Electric power usage is:

                     C  *(Z }
               Qhe=ge                                    Eqn. 2-2.
                                               2-5

-------
Final Version-May, 2005
       where:
               Qhe = Electric power consumption as Btu/h
               Cge = Power conversion factor, 3412 Btu/kWh
               Zh = Electric energy consumption, kWh

Note that Zh will consist of the individual 1-minute average kW readings, summed over the test run, and
normalized to a 60-minute mean. For example, if each 1-minute average is 0.134 kW, and the test run is
48 minutes long, the summed values would be 6.432 kW over 48 minutes.  This is equivalent to 8.04
kWh.

CoP is:

               Cop =-±-*_                                  Eqn. 2-3.
                      Qhe

Analysts will calculate water heating capacity, electric power consumption, and CoP separately for each
test run.  The report will cite the lower and elevated temperature results as the mean and sample standard
deviation for each set of three test runs at the lower and elevated temperatures, respectively.


2.3.3.  Standby Heat Loss Test Procedure

Test personnel will conduct 3 standby heat loss test runs immediately following the last water heating
capacity  test run.   Note  that the  ANSI / ASHRAE  method  specifies  that  the  test room dry-bulb
temperature must be regulated at 75 ± 1 °F. This will not be possible at the host facility, but testers will
acquire and report test room temperatures and the data analysis will allow for different temperatures.

1. Enable datalogging and adjust the EarthLinked system controls to bring the mean tank temperature to
120 °F.
2. Verify that the EarthLinked system cycles off at the selected temperature and that the datalogger is
operating properly.
3. Monitor the collected data for one complete cooling and heating cycle.  The EarthLinked system must
cycle on  as the tank cools and off as it achieves its setpoint in accordance with the manufacturer's control
algorithm.  Continue monitoring for at least three full cooling and heating cycles.


2.3.4.  Standby Heat Loss Analysis

The datalogger record will include the  1-minute mean tank temperatures (as the average of all six in-tank
temperature sensors), test room temperatures, and power consumption rates. The tank heat loss parameter
for each complete cooling / heating  cycle is:

                       T    —r
                    t  I  mhsf   ahsf  \ ^ T 7 ^
                    In	— * V * -
                       T   —T         C  *v
               Lhs =     mfeo    ^  ,    fg                         Eqn. 2-4
                            \flis  ' Ofe /
       where:
               Lhs  = Heat loss parameter, Btu/h.°F
                                              2-6

-------
Final Version-May, 2005
               Tmhsf =  Final mean tank temperature (as the average of all 6 in-tank sensors), °F
               Tahsf = Final test room dry bulb temperature, °F
               Tmhso =  Initial mean tank temperature (as the average of all 6 in-tank sensors), °F
               Tahs0 = Initial test room dry bulb temperature, °F
               V  = Storage tank capacity, gal
               Cp =  Specific heat of water at the mean of Tmhf and Tmho (from [2]), Btu/lb.°F
               Cfg = Volume conversion factor, 7.48055 gal/ft3
               v =  Specific volume of water at the mean of Tmhf and Tmho (from [3]), ft3/lb
               tfts = Final time stamp for the individual cooling / heating cycle, h
               tohs = Initial time stamp for the individual cooling / heating cycle, h

Analysts will calculate the mean heat loss parameter as the average of the 3  individual results from the
monitored cooling / heating cycles.

The tank's heat loss rate (used in Eqn. 2-1) is:

                   _      3 VmM  ~ TahO )+(T,nhf ~ T ahf )                                ,
       where:
                   = Heat loss rate, Btu/h
               V/hs — llCdU 1USS IdUC, JJUU/11
               Lhs,mean =  Mean heat loss parameter, Btu/h.°F
               Tmho = Initial mean tank temperature (as the average of all 6 in-tank ^^^^
               Taho = Initial test room dry bulb temperature, °F
               Tmhf = Final mean tank temperature (as the average of all 6 in-tank sensors),
               Tahf = Final test room dry bulb temperature, °F
sensors), °F

        op
2.3.5.   Long Term Monitoring Procedures and Analysis

During the long-term monitoring period, the two power meters will monitor electricity consumption for
both tanks. System operators will alternate between EarthLinked and resistive element heating at Tank #1
on a weekly schedule for at least 4 weeks.

Analysts will report Tank #1 power consumption separately as overall mean real power consumption
while operating from the EarthLinked system and from the heating elements. They will also report Tank
#2 power consumption as it maintains the circulating water temperature.  This will allow an assessment of
the heating power consumed by  the Tank #2 circulating flow.

The difference between SUT electrical power consumption with and without the EarthLinked system will
be:

               ^kW = ^ kW,EarthLinked ~ ^ kW .elements                         -bC[n. 2-O

        where:
               AZkw = Change in electrical power consumption, kW
               Zkw,EanhLmked = Mean power consumption, both tanks, during EarthLinked operations, kW
               Zkw.eiements = Mean power consumption, both tanks, during resistive element heating, kW
                                               2-7

-------
Final Version-May,  2005
Mean real power consumption (Zkw) for each tank will be the sum of the one-minute average kW divided
by the number of minutes during each monitoring cycle.

Analysts will also calculate power consumption for each tank, normalized to the hot water used and the
temperature rise during each long-term cycle. This will be:

                          n         7
                         V^^ kW
                         'T FRr.n * 0.01667* AT1
                          el    Cj/y            a                     -i—i   /•* ^7
                ™fed =	                    Eqn. 2-7
                                   n

       Where:
               Qnormaiized = Normalized power consumption for Tank a, kW/gal.°F
               n = Number of minutes in the monitoring period
               Zkw =  Sum of Tank #1 and Tank #2 mean electric power consumption
                for each minute, kW
               FRdty =  Mean city water flow rate for each minute, gph
               0.01667 =  hours per minute
               AT = Tank # 1 temperature rise for each minute, °F

Note that AT is the difference between the mean of the Tank #1 six in-tank temperature sensors and Tsuppiy
(see Figure 2-1).

Appendix B provides the procedure for  estimating emission  reductions.  The procedure correlates the
estimated annual electricity savings in MWh with Florida and nationwide electric power system emission
rates in Ib/MWh.  For this verification, analysts will assume that the EarthLinked system operates
continuously throughout the year with the  electric power savings as measured during the long-term
monitoring period.

Appendix C provides  the procedure for estimating simple  cost savings based on the  Florida and
nationwide prices for retail electricity at "commercial" rates.   Similar to emissions reductions, analysts
will assume that the EarthLinked system operates continuously throughout the year with the electric
power  savings as measured during the long-term monitoring period.  The EarthLinked system does not
use auxiliary fuel, nor is it intended as a power source, so their potential costs or revenues need not be
considered for this verification.
                                              2-8

-------
Final Version-May,  2005
                                 3.0
DATA QUALITY
3.1.   DATA QUALITY OBJECTIVE

The GHG Center selects test methods and instruments for all verifications to ensure a stated level of data
quality in the reported results.  The data quality objectives (DQOs) are based on the  GHG Center's
stakeholder guidelines, measurement accuracies achieved during previous verifications, test method, and
instrument specifications. The resulting DQOs for the short-term tests and long-term monitoring are:

    •   determine EarthLinked water heating capacity and CoP to within ± 5 %
    •   determine the power consumed by the  baseline and EarthLinked systems (during long-
        term monitoring) to within ± 0.4 %

Each test measurement contributes to the verification parameters  according to the equations in Sections
2.3.2 through 2.3.4.  Each measurement is linked to accuracy specifications,  or data quality indicator
(DQI) goals which, if met, ensure achievement of the DQOs.  The accuracy specifications quoted below,
compounded through the applicable equations according to standard root-mean-square techniques, are the
source of the DQOs.  Reference [4] provides examples of compounded accuracy derivations.

The project manager will calculate and report  the achieved DQO based  on the actual  instrument and
measurement accuracies, as  documented by specific instrument calibrations, manufacturer certifications,
etc.

3.2.   INSTRUMENT SPECIFICATIONS, CALIBRATIONS,  AND QA/QC CHECKS
Table 3-1 lists the instruments to be used in this verification test, their expected operating ranges, and
accuracies or DQI goals.
Table 3-1. Instrument and Accuracy Specifications
Measurement
Variable
EarthLinked
system water flow
EarthLinked
system water inlet,
outlet temperatures
Tank#l
temperatures
Test room
temperature
System pressure
Tank#lkW
Tank #2 kW
Expected
Operating Range
10 gpm
70 - 140 °F
60 - 90 °F
20 - 40 psig
0- 15 kW
Instrument
Mfg., Model,
Type
Omega FTB-
905 turbine
Omega or
Controlotron 4-
wire RTD
Ametek fluid-
filled Bourdon
gauge
Power
Measurements
ION 7500
Power
Measurements
ION 7600
Instrument
Range
3 - 29 gpm
0 - 250 °F
0 - 60 psig
0 - 125 kW
Measurement
Frequency
Every 5
seconds, record
1 -minute
averages
Beginning of
tests
Every second,
record 1-
minute
averages
Accuracy
Specifica-
tion"
+ 0.5 %
+ 0.6 °F
+ 3%
+ 0.15%
How Verified /
Determined
NIST-traceable
calibration within 2
years
NIST-traceable
calibration within 6
years; pretest
crosscheck
                                              3-1

-------
Final Version-May, 2005
Table 3-1. Instrument and Accuracy Specifications
Measurement
Variable
Current trans-
formers (for kW)
Tank #1 volume,
gal
Expected
Operating Range
0- ISA
120, nominal
Instrument
Mfg., Model,
Type
Flex-Core
Model 191-151
metering class
Instrument
Range
0- 150 A
Measurement
Frequency

Note: Tank volume measured during original
fabrication
Accuracy
Specifica-
tion"
+ 0.3 %
+ 3.3%
How Verified /
Determined
Manufacturer's
certificate
Gravimetrically as
part of statistical
process control
"Accuracy is % of reading unless stated as absolute units.
Table 3-2 summarizes QA / QC checks which the field team leader will perform before and during the
short-term tests.  These checks are intended only as field diagnostics.  This is because, if the instruments
function in the field as they did in the laboratory, it is reasonable to expect that calibration and accuracy
specifications have not changed.
Table 3-2. QA/QC Checks
System or
Parameter
EarthLinked system
flow rate
Tank #1 and Tank
#2 real power
consumption
Temperature sensors
Water heating
capacity
QA / QC Check
Zero check"
Full flow check"
Voltage and current field
reasonableness checks with
Fluke 335 clamp meter
Laboratory cross checks
between power meters
Ambient cross check
Cross check between Type
V (tank) and Type IV
(flow) test methods"
When
Performed
Immediately prior
to first test run
Prior to testing
Prior to
installation
After each short-
term test run
Expected or Allowable
Result
Ogpm
9-11 gpm
Voltage within + 2 %
Current within + 3 %
kW readings within + 1 % of
each other
All within + 1.5 °F of each
other
Result within + 6.4 % of each
other
Response
Troubleshoot and repair
sensors
Consult with EarthLinked
representative
Troubleshoot and repair
sensors
Troubleshoot and repeat
the test run
"Procedure provided in Appendix A-2
This verification is based on the ANSI / ASHRAE test method for Type V heat pump water heaters which
incorporate a storage tank. Testers will, however, collect sufficient data to quantify the water heating
performance  for Type  IV systems, or as if it did not have  a storage tank.   While the Type IV
determination's accuracy will not meet the ANSI / ASHRAE test specifications, the results will serve as a
cross check against the Type V determinations. Analysts will calculate the Type IV performance for each
minute during the tests as:
                                                                          Eqn.3-1
       where:
               Qhm = Heat capacity for minute m, Btu/h
               FRhn =  EarthLinked water flow rate during minute m, gpm
               Tohn = EarthLinked outlet temperature during minute m, °F
               Tlhn = EarthLinked inlet temperature during minute m, °F
               Cp =  Specific heat of water at the mean of Tohn and Tlhn (from [2]), Btu/lb.°F
               Cfg  = Volume conversion factor, 7.48055 gal/ft3
                                              3-2

-------
Final Version-May, 2005


              v  = Specific volume of water at the mean system pressure (from [3]), ft3/lb

The mean water heating capacity for each test run will be:
               QH=~	                                               Eqn.3-2
                      n

       where:
               Qh = Mean water heating capacity, Btu/h
               n  = number of minutes in the short-term test run under consideration

Analysts will consider the test run results calculated according to Section 2.3.2 to be valid if they are
within ± 6.5 % of the results calculated here.
3.3.   INSTRUMENT TESTING, INSPECTION, AND MAINTENANCE

Test personnel will assemble and commission all equipment as anticipated to be used in the field prior to
departure.  They will, for example, assemble the Tank #1 temperature probe and ensure  that all
temperature sensors provide values within ± 1 °F prior to departure.  Any faulty sub-components will be
repaired or replaced before starting the verification tests.  Test personnel will maintain a small supply  of
consumables and frequently needed spare parts at the  test facility.   The field team leader or project
manager will  handle major  sub-component  failures  on a  case-by-case basis  such as by  renting
replacement equipment or buying  replacement parts.  In accordance with the GHG Center  Quality
Management Plan, test personnel will subject all test equipment to the  QA / QC checks discussed earlier
prior to demobilization.

3.4.   INSPECTION AND ACCEPTANCE OF SUPPLIES AND CONSUMABLES

Test personnel will inspect all test equipment and evaluate its conformance to the specifications above
prior to acceptance. The field team leader will maintain copies of NIST-traceable calibration certificates,
records of QA / QC checks, and other information.
                                             3-3

-------
Final Version-May, 2005
                                                     3-4

-------
Final Version-May,  2005
              4.0  DATA ACQUISITION, VALIDATION, AND REPORTING
4.1.   DATA ACQUISITION AND DOCUMENTATION

Test personnel will acquire the  following electronic data and generate the following documentation
during the verification:

Electronic Data

The ION 7500 and 7600 power meters will poll their sensors once per second.  They will then calculate
and record one-minute averages throughout all tests. The field team leader will download the one-minute
data directly to a laptop computer during the short-term tests.  GHG Center personnel will download the
data by telephone during the long term monitoring period.

An Agilent / HP Model 34970A datalogger will record all temperature and flow meter data once every 5
seconds.  The field team leader will download the  data directly during short-term tests while GHG Center
will download the data by telephone during the  long  term monitoring period.  Analysts will use Excel
spreadsheet routines to calculate one-minute averages from the 5-second snapshots.

The electronically-recorded one-minute averages (except for the manually-logged water system pressure
data) will be the source data for all calculated results.

Documentation

Printed or written documentation will include:
    •   Daily test log, including water system pressure data, starting and ending times for test
        runs, notes, etc.
    •   Appendix A forms which show the results of QA / QC checks
    •   Copies of calibrations and manufacturers' certificates
    •   Corrective action reports, as needed

The GHG Center will archive all  electronic data, paper files,  analyses, and reports  at their Research
Triangle Park, NC office in accordance with their quality management plan.
4.1.1.  Corrective Action and Assessment Reports

A corrective action will occur if audits or QA / QC checks produce unsatisfactory results or upon major
deviations from this test plan.   Immediate corrective action  will enable quick response to  improper
procedures, malfunctioning equipment,  or suspicious data.   The corrective action process involves the
field team leader, project manager, and QA Manager. The GHG Center QMP requires that test personnel
submit a written corrective action request to document each corrective action.

The field team leader will most frequently identify the need  for corrective actions.  In such cases, he or
she will immediately notify the project  manager.  The field team leader, project manager, QA Manager
and other project personnel, will collaborate to take and document the appropriate actions.
                                              4-1

-------
Final Version-May, 2005
Note that the project manager is responsible for project activities.  He is authorized to halt work upon
determining that  a serious problem exists.   The  field team  leader is  responsible for implementing
corrective actions identified by the project manager and is authorized to implement any procedures to
prevent a problem's recurrence.
4.2.   DATA REVIEW, VALIDATION, AND VERIFICATION

The project manager will initiate the data review, validation, and analysis process.  At this stage, analysts
will classify all collected data as valid, suspect, or invalid. The  GHG Center will employ the QA/QC
criteria specified in Section 3.0 and the associated tables. Source materials for data classification include
factory and on-site calibrations, maximum calibration and other errors, etc.

In general, valid data results from measurements which:
    •   meet the specified QA/QC checks,
    •   were collected when an instrument was verified as being properly calibrated,
    •   are consistent with  reasonable  expectations (e.g.,  manufacturers'  specifications,
        professional judgment).

The report will incorporate all valid data.  Analysts  may  or may not consider suspect data, or it may
receive special treatment as will be specifically indicated. If the DQO cannot be met, the project manager
will decide to continue the test, collect additional data, or terminate the test and report the data obtained.

Data review and validation will primarily occur at the following stages:
    •   on site ~ by the field team leader
    •   before writing the draft report ~ by the project manager
    •   during draft report QA review and audits ~ by the GHG Center QA Manager

The field team leader's primary on-site functions will be to install and operate the test equipment.  He will
review, verify, and validate certain data (QA / QC check results,  etc.) during testing.  The log forms in
Appendix A provide the detailed information he will gather.

The QA Manager will use this test plan  and documented test methods as references with which to review
and validate the data and the draft report.  He will review and audit the data in accordance with the GHG
Center's  quality management plan.  For example, the QA Manager will randomly select raw data and
independently calculate the verification parameters. The comparison of these calculations with the results
presented in the draft report will yield an assessment of the GHG Center's QA/QC procedures.
4.3.   DATA QUALITY OBJECTIVES RECONCILIATION

A fundamental component of all verifications is the reconciliation of the collected data with its DQO.  In
this case, the DQO assessment consists of evaluation of whether the stated methods were followed, DQIs
achieved, and overall accuracy is as specified in Section 3.0.  As discussed in Section 4.2, the field team
leader and project manager will initially review the collected data to ensure that they are valid and are
consistent with expectations. They will assess the data's accuracy and completeness as they relate to the
stated QA / QC goals.  If this review  of the test data shows that QA / QC goals were not met, then
immediate corrective action may be feasible, and will be considered by the project manager.  DQOs will
be reconciled after completion of corrective actions. As part of the internal audit of data quality,  the
GHG Center QA Manager will include an assessment of DQO attainment.
                                              4-2

-------
Final Version-May, 2005
4.4.   ASSESSMENTS AND RESPONSE ACTIONS

The field team leader, project manager, QA Manager, GHG Center Director, and technical peer-reviewers
will assess the project and the data's quality as the test campaign proceeds.  The project manager and QA
Manager will independently oversee the project and assess its quality through project reviews, inspections
if needed, and an audit of data quality.


4.4.1.  Project Reviews

The project manager will  be responsible for conducting the first complete project review and assessment.
Although all project personnel are involved with ongoing data review, the project manager must ensure
that project activities meet measurement and DQO requirements.

The  GHG Center Director will  perform the  second project review.  The  director is responsible for
ensuring   that the  project's  activities adhere  to  the  ETV  program  requirements and  stakeholder
expectations.   The GHG  Center Director will  also ensure  that the field team leader has the equipment,
personnel, and resources to complete the project and to deliver data of known and defensible quality.

The  QA  Manager will perform  the  third review.   He is responsible for ensuring that the project's
management systems function as required by the quality management plan.  The QA Manager is the GHG
Center's final reviewer, and he is responsible for ensuring the achievement of all QA requirements.

ECR personnel and selected GHG Center stakeholders and/or peer reviewers will then review the report.
Technically competent persons who are familiar with the project's technical aspects, but not involved
with project activities, will function as peer reviewers. The peer reviewers will provide written comments
to the project manager.  ECR will also have the opportunity to insert  supplemental unverified information
or comments into  a dedicated report section.

The GHG Center  will submit the draft report to EPA  QA personnel, and the project manager will address
their comments as needed.  Following this review, the report  will undergo EPA management reviews,
including the GHG Center Director, EPA ORD Laboratory Director, and EPA Technical Editor.
4.4.2.  Audit of Data Quality

The  audit of data quality is an evaluation of the  measurement, processing, and data analysis steps to
determine if systematic errors are present.   The QA  Manager,  or  designee, will randomly  select
approximately 10 percent of the data.  He will  follow the  selected  data through  analysis and data
processing. This audit is intended to verify that the data-handling system functions correctly and to assess
analysis quality.  The QA Manager will also include an assessment of DQO attainment.

The  QA Manager will route audit results to the project manager for  review, comments, and possible
corrective actions.  Project records will document the  results.   The project manager will take  any
necessary corrective action  needed and will respond by addressing the  QA  Manager's comments in the
report.
                                              4-3

-------
Final Version-May, 2005
4.5.   VERIFICATION REPORT AND STATEMENT

The  report will  summarize each verification parameter's results as discussed in  Section 2.0 and will
contain sufficient raw data to support findings and allow others to assess data trends, completeness, and
quality.  The report will clearly characterize the verification parameters, their results, and supporting
measurements as determined during the test campaign. It will present raw data and/or analyses as tables,
charts, or text as is best suited to the data type.  The report will contain additional information about the
SUT and the host facility such as ground loop installation data, etc.  The report will  also contain a
Verification Statement, which is a 3 to 5 page document summarizing the technology, the test strategy
used, and the verification results obtained.

Examples of the  reported values include the mean and 95-percent confidence intervals for:
     •    short-term test verification parameters listed in Section 2.1
     •    city water supply temperatures during short-term tests
     •    test room ambient temperatures during the standby heat loss tests

The  report will also cite the long-term monitoring results and indicate the range of city water supply and
test room ambient temperatures.

The  project manager will  submit the  draft report and Verification Statement to the QA Manager and
GHG Center Director for review. A preliminary  outline of the report is as follows:

                                       Preliminary Outline
      ECR EarthLinked Ground Source Heat Pump Water Heating System Verification Report

Verification Statement

Section 1.0:    Verification Test Design and Description
              Description of the ETV program
              EarthLinked System and Host Facility Description
               Overview of the Verification Parameters and Evaluation Strategies

Section 2.0:   Results
               Water Heating Capacity
               CoP
              Long-term Monitoring Results
              Estimated Emissions Reductions
              Estimated Simple Cost Savings

Section 3.0:   Data Quality

Section 4.0:   Additional Technical and Performance Data Supplied by ECR (optional)

Section 5.0:   References

Appendices:   Raw Verification or Other Data
                                               4-4

-------
Final Version-May, 2005
4.6.   TRAINING AND QUALIFICATIONS

This test does not require specific training or certification beyond that required internally by the test
participants  for their own activities.  The GHG Center's field team leader is a licensed professional
engineer with approximately 15 years experience in field testing of air emissions from many types of
sources.   He  is familiar with  the test  methods and standard  requirements that will be used in the
verification test.

The project manager has performed numerous field verifications under the ETV program, and is familiar
with  EPA and  GHG  Center  quality  management  plan requirements.   The QA Manager  is  an
independently appointed individual whose responsibility is to ensure the GHG Center's conformance with
the EPA approved QMP.

4.7.   HEALTH AND SAFETY REQUIREMENTS

This section applies to GHG Center personnel only.  Other organizations involved in the project have
their own health and safety plans which are specific to their roles in the project.

GHG Center staff will comply with all known host, state/local and Federal regulations relating to safety at
the test facility.  This includes use of personal protective gear  (such as safety glasses,  hard hats, hearing
protection, safety toe shoes) as required by the host and completion of site safety orientation.
                                              4-5

-------
Final Version-May, 2005
                                                     4-6

-------
Final Version-May,  2005
                                    5.0  REFERENCES

[1]  ANSI /ASHRAE Standard 118.1-2003:  Method of Testing for Rating Commercial Gas, Electric, and
Oil Service Water Heating Equipment, American Society of Heating, Refrigerating and Air-Conditioning
Engineers, Inc.  Atlanta, GA. 2003

[2]  Handbook of Chemistry and Physics, 60th Edition, "Specific Heat of Water", page D-174, CRC Press.
Boca Raton, FL. 1980

[3]  Handbook of Chemistry and Physics, 60th Edition, "Steam Tables—Properties of Saturated Steam and
Saturated Water", page  E-18, CRC Press. Boca Raton, FL.  1980

[4]   Distributed  Generation  and Combined Heat and Power Field Testing Protocol—Appendix G:
Uncertainty Estimation, Association  of State  Energy Research and Technology Transfer Institutions.
2004. Available from .
                                              5-1

-------
Final Version-May, 2005

-------
Final Version-May, 2005
                                           Appendix A

-------
Final Version-May,  2005
Project ID:
                     Appendix A-l.  Power Meter and RTD QA / QC Checks
Location:
Power Meter Sensor Checks
Note: Acquire at least 3 separate readings for each phase. All ION voltage and current readings must be
within 2 % or 3 %, respectively, of the corresponding DVM reading.
Tank #1 power meter: Make:                 Model:                 Serial No:

Voltage
Current
Date: Signature:

Phase A
ION






DVM






Tank #2 power meter: Make:
Date:

Voltage
Current
% diff






Phase B
ION






DVM






% diff






Model:
Signature:
Phase C
ION






Serial No:
DVM






% diff









Phase A
ION






DVM






% diff






Phase B
ION






DVM






% diff






Phase C
ION






DVM






% diff






RTD Ambient Crosschecks
Note:  Allow RTDs to equilibrate in ambient conditions for at least !/2 hour. All RTD readings must be within +1.5
°F of each other.
       Date:
Signature:
Ref.
1
2
3
4
5
6
7
8
9
spare
RTD ID #










Description / location










°F (at DAS)










                                         -Al-

-------
Final Version-May, 2005


         Appendix A-2.  Flow Meter Checks and Water Heating Performance Crosscheck

Flow Meter Checks

Record at least 3 flow rates each while EarthLinked heat exchanger pump is disconnected and while it is
running.  Zero flow should be < 2.9 gpm.  Full flow should be between 9 and 11 gpm.
Date: 	       Signature: 	
Make: 	Model: 	Serial #: 	Mean K (pulses per gallon): 	
               Pulse/min =
                          60(PulseCount)
                              T
                              L ela
                                                    gpm=-
                                psed
                                                          Pulse/min
                                                             ~K
Zero flow
Full Flow
T «
1 elansed' s






PulseCount






Pulse/min






gpm






OK?






Type V vs. Type IV Crosscheck

Type V water heating capacity, Qtypev, Btu/h, should agree with Type IV capacity, Qtypeiv, to within 6.4 %.
        116.3*
               7.48055*v
                         * [T   —T  )
                          V mhf  L mhO )
                                     - + 341.2
                                                                                 7.48055 *v
                   \ Jll   Mil /

       Where: Cp (specific heat) and v (specific volume) are obtained from the tables below
               Tmhf and Tmho are the initial and final tank temperatures taken as the mean of all 6 tank
                 temperature sensors during each test run, °F
               (ta - toh) = type V test run duration, s
               FRAvg = overall mean of one-minute EarthLinked system flow rates for each test run, gpm
               Tohn-Tjhn = overall mean of one-minute temperature differentials across the EarthLinked
                 system for each test run, °F
Cp depends on average tank water temperature over the entire test run, Tavg =
                                                                       T
                                                                       1
                                                                        mhf
                                                                                     v depends on
system pressure.  System pressure is the sum of the pressure gauge psig and ambient psia. Ambient psia
is the location station pressure, Pbar, as recorded by the local weather radio and corrected for altitude or as
measured by a climbing altimeter. Note that psia = "Hg * 0.4911541.
Date:
psig:
                    Signature:
               _Pbar:
P
                                  syst
                                  ;ystem •
                                          -A2-

-------
Final Version-May, 2005
                                   Appendix A-2, Continued

Acquire specific volume and specific heat from following table.  Enter table at Psystem for specific volume.
Enter table at Tavg for specific heat.  Use linear interpolation for values between those given.
Specific Volume
system*
psia
24.08
29.82
34.24
39.18
44.68
49.20
54.08
59.35
v, ft3/lb
0.01691
0.01701
0.01707
0.01714
0.01721
0.01726
0.01732
0.01738
Specific Heat
T
*avg)
op
60
70
80
90
100
110
120
130
cp,
Btu/lb.°F
0.99963
0.99868
0.99816
0.99797
0.99799
0.99817
0.99847
0.99889
Type V Water Heating Performance
Parameter
CD
V
Tjnhf (final tank temp)
T^o (initial tank temp)
Tmhf " Tjnho
tfh (final time stamp)
toh (initial time stamp)
ta - toh (difference, s)
VtypeV
Run 1 Values









Run 2 Values









Run 3 Values









Type IV Water Heating Performance
Parameter
CD
V
FRAvg (overall mean of one-
minute flow rates)
T0hn -Tjhn (overall mean of one-
minute differential
temperatures)
QtvpelV
Qtvpev vs. Qtypeiv % Difference
Acceptable? (within + 6.5 %)
Run 1 Values







Run 2 Values







Run 3 Values







Long Term Monitoring Period

Start date: 	  Time:

Signature: 	
Circle one: {EARTHLINKED}  {TANK ELEMENTS}
                                         -A3-

-------
Final Version-May,  2005
                           Appendix A-3.  SUT and Site Information
Date: 	  Signature:
SUT Data
Description: 	
Mfg:  	Model:	   Serial No.:

Temperature rise: 	°F at	gph      Nominal CoP:  	

Loop Data
Designer: 	   Installer: 	
Tubing material: 	 Dia: 	Number of loops/bores:
Loop length each: 	Total length: 	 Bore diameter:  	  Depth:

Water table encountered? 	   Water table depth 	

Grouting method / material (describe): 	
Soil type / description (from driller's log):
Notes (Is installation representative?  Problems encountered?  Exceptions made?):
Site Data
Note: record number and type of hot water uses only.

Residence rooms: 	Fixtures (describe):  	

Utility rooms:  	Fixtures (describe):  	

Kitchens:  	 Fixtures (describe):  	

Nurse Stations: 	Fixtures (describe): 	

Baths/Spa: 	 Fixtures (describe):  	

Other: 	Fixtures (describe):  	

Daytime staff (function / number):  	

Nighttime staff (function / number): 	
Number of residents at start of tests:
Number of residents at end of long-term monitoring:
                                         -A4-

-------
Final Version-May, 2005
                                           -A5-

-------
Final Version-May, 2005


                                          Appendix B
                      Electric Power System Emissions Reduction Estimates

The  verification report will  provide  estimated  emissions  reductions (or increases) as compared to
aggregated electric power system (EPS) emission rates for the state in which the apparatus is located
(Florida for this verification).  The report will also include estimated reductions based on aggregated
nationwide emission rates. Analysts will employ the methods described in this Appendix.

A DG asset or power-saving device, when connected to the EPS, will change the overall EPS emissions
signature. As an example, a zero-emission generator, such as a hydroelectric power plant, will  decrease
EPS CO2 emissions on a Ib/MWh basis.  The potential emissions reduction (or increase) for DG is the
difference between the EPS and DG  emission rates, multiplied by the expected power generation or
savings rate:

               Reduction^ = (EREPS:i - ERDO:i) *MWhDO:Ann                         Eqn. Bl

       Where:

               Reduction; = annual reduction for pollutant i, pounds per year (Ib/y)
               EREPS;  = EPS emission rate for pollutant i (see below), pounds per megawatt-hour
                         (Ib/MWh)
               ERoG.i  = DG emissions rate for pollutant i, Ib/MWh
               MWhDG Ann = annual estimated DG power production or device-based power savings,
                             megawatt-hours per year (MWh/y)

The potential emissions reduction for a power savings device is simply:

               Reduction = EREPS:i *MWhDevice,Ann                                Eqn. B2
Values for ERDG,i are  available from the performance verification results.  Estimated MWhDG,Ann or
MWhDevice A™ should also be available from the verification results.  This estimate depends on the specific
verification strategy and its derivation should be clearly described in the test plan and verification results.
A simple  example is the power production  or power savings multiplied  by the annual availability or
capacity factor.  For example, a 200 kW fuel cell which operates at full capacity 75 percent of the time
can be expected to generate 1314 MWh annually.

EREPS; for specific pollutants can vary widely because the EPS may obtain its power from many different
generators. The generation mix can change dramatically from hour to hour, depending on market forces,
system operations, wheeling practices, emergencies, maintenance, and other factors.  Many different
approaches have been suggested for estimating EREPS15 but no consensus has been achieved.

The following estimation methodology is simple, it uses peer-reviewed carbon dioxide (CO2), nitrogen
oxide (NOX), mercury  (Hg),  and sulfur  dioxide  (SO2)  data  available from the  US  Environmental
Protection Agency's "EGRID" database, and it provides some  analysis flexibility.

EGRID is available from www.epa.gov/cleanenergy/egrid/download.htm.   At this writing, data is
available through 2000. Data through 2003 will likely be available in late 2005.  Figure B-l shows the
introductory screen prompts which provide year 2000 emission rates for Florida.
                                         -Bl-

-------
Final Version-May,  2005
                 •• eGRID2002PC, Version 2.01 - Main Selection Screen
                     Search Filters  Import/Export  Interchange

                  Aggregation Level

                   '  Power Plant

                     State
            " Select One or Multiple Entities *
                     Electric Generating
                     Company (EGC)

                   r US Total

                   Grid Regions:

                    r NERC Region

                    <" eGRID Subregion

                      Power Control Area (PCA)
ALABAMA (AL)
ALASKA (AK)
ARIZONA (AZ)
ARKANSAS (AR)
CALIFORNIA (CA)
COLORADO (CO)
CONNECTICUT (CT)
DELAV/ARE (DE)
DISTRICT OF CgUJMBIA [DC)
                             Enter text to search for:
GEORGIA (GA)
HAWAII (HI)
IDAHO (ID)
ILLINOIS (IL)
IN DIANA (IN)
IOWA (IA)
KANSAS (KS)
KENTUCKY (KY)
LOUISIANA (LA)
MAINE (ME)
MARYLAND [MD]
MASSACHUSETTS (MA)
MICHIGAN (Ml)
MINNESOTA (MN)
MISSISSIPPI (MS)
MISSOURI (MO)
MONTANA (MT)
NEBRASKA (NE)
NEVADA (NV)
                      Figure B-l.  Florida Aggregated Emissions Introductory Screen

Double-clicking the state of interest brings up the emissions data, as shown in Figure B-2.
5 eGRID 2002PC, Version 2.01 - State Level Data fx]

State: [FLORIDA
Capacity 	
IMW): I 46,041.1
Emissions Profile
Annual CO 2
Annual SO 2
Annual NOX
Help Previous

(MMBlu) 1,616,637,109 [MWh]: I 191,906,639 3M Data Year: 1 2000 _*j
T f 1
Generation Resource Mix Sjate Import/Export Data

iDisplaj1 emission
I rates for fossil,
I coal/oil/gas
Display Ozone
Season NOX Data
Emissions (tons) Output Rate (Ibs/MWh) Input Rate (Ibs/MMBtu)
| 136,293,930.61 (~~ 1,420.42 j 168.61
| 579,623.25 | 6.04 |~~ 0.72
| 322,813.74 | 3.36 | 0.40
Annual Hg tt | 2,499.63 | 0.0130 | 0.0016
8 Annual mercury (Hg) emissions are in Ibs; Hg emission rates are in Ibs/GWh and Ibs/BBtu
                              Figure X-2. Florida EPS Emission Rates for 2000
                                                    -B2-

-------
Final Version-May, 2005
Figure B-3 provides the nationwide emission rates for 2000.
       ft eGRID2002PC, Version 2.01 - United States Level Data
                 ILINITED STATES
                                                                             Help I   Ptevi
         Capacity
Heat Input
Generation
            (MW):  ) 864,905.7    [MMBtuJ: I 29,221,854,977      [MWhJ:   3,810,305,466
                                                          Data Year:  2000 '
            Emissions Profile
                                   Generation Resource Mix
                            U.S. Generation and Consumption
                                      Data
                                                                                        Display emission
                                                                                        rates for fossil,
                                                                                          coal/oil/gas
                                                                             Display Ozone
                                                                           Season NOX Data
                              Emissions (tons)
                      Output Rate (Ibs/MWh)    Input Rate (Ibs/MMBlu)
                Annual CO 2
                Annual S02
                Annual NOX
                Annual Hg tt
  2,652,901,442.24
    11,513,033.84
     5,644,353.87
       103,554.66
I
1,392.49
I
181.57
           6.04
                           0.79
           2.96
                           0.39
                                                              0.0272
                                0.0035
                8 Annual mercury (Hg) emissions are in Ibs; Hg emission rates are in Ibs/GWh and Ibs/BBtu.
                               Figure B-3. Nationwide Emission Rates
These results  form the  basis  for comparison.  Table B-l  provides emissions offsets  estimates for a
hypothetical 200 kW fuel cell located in Florida.
Table B-l. Example Fuel Cell Emissions Offsets Estimates

Pollutant
EREPS (from EGRID),
Ib/MWh
ERDG (from
verification tests),
Ib/MWh
EREPS - ERDG, Ib/MWh
DG capacity, kW
Estimated availability
or capacity factor
MWhDaAm
Emission offset, Ib/y
Florida
CO2
1420
1437
.17°
NOX
3.36
0.13
3.23
200
75%
1314
-22400
4250
Nationwide
CO2
1392
1437
-45"
NOX
2.96
0.13
2.83
200
75%
1314
-59130
3720
"Negative numbers represent an increase over the EPS emission rate
Note that this fuel cell  increases the overall  EPS CO2 emission rate if electricity generation alone  is
considered.  The increased CO2 emissions in this  example would be balanced by the fuel cell's heat or
chilling power production if it is in combined chilling / heat and power (CHP) service.  Each verification
test plan  must provide a specific accounting methodology for electricity production and CHP utilization
                                             -B3-

-------
Final Version-May, 2005
because it is impossible to consider all the permutations here.  The  simplest case, that the unit really
operates  at a constant power output, predictable availability (or capacity factor), and that all the heat
produced is actually used, is not necessarily true for every installation.  Also, the CHP application may
displace units fired by various fuels (electricity, heating oil, natural gas, etc.) with their own efficiencies
and emission factors. Each verification strategy should explicitly discuss these considerations as part of
the specific emissions offset calculation.

It is  useful, however, to continue this example.  Assume that the fuel cell provides a constant 800,000
British thermal units per hour (Btu/h) to a domestic hot water system, thus displacing an electric-powered
boiler. This heat production is equivalent to 234 kW, which would  require approximately 239 kW of
electricity from the EPS at 0.98 water heating efficiency (source: ASHRAE Standard 118.1-2003, §9.1).
The  fuel cell would therefore save approximately 15700 MWh annually at 75 percent capacity factor.
Table B-2 shows the resulting emissions offsets estimates.
Table B-2. Example CHP Emissions Offsets Estimates

Pollutant
EREPS (from EGRID),
Ib/MWh
ERDG (from
verification tests),
Ib/MWh
EREPS - ERDG, Ib/MWh
DG capacity, kW
Estimated availability
or capacity factor
MWhDG,Am
Emission offset, Ib/y
Florida
C02
1420
0"
1420
NOX
3.36
0"
3.36
239"
75%
15700
2.23x10'
(11 100 tons)
52800
(26.4 tons)
Nationwide
CO2
1392
0"
1392
NOX
2.96
0"
2.96
239"
75%
15700
2.19x10'
(10900 tons)
46500
(23.2 tons)
"Emissions are zero here because the electricity production offset estimate included them.
*Based on the power required to run an electric-fired boiler at 98 % water heating efficiency.
In this CHP application, the fuel cell represents a considerable net annual CO2 emissions reduction for
Florida of 2.23 x!07lb/y.

This approach is generally conservative because it does not include transmission and distribution (T&D)
losses. T&D losses vary between approximately 3 to 8 percent depending on dispatch practices, the unit's
location with respect to the EPS generator actually being displaced, and other factors.  This means that
100 kW of energy at the DG unit's terminals will actually displace between 103 and 109 kW (and the
associated emissions) at the EPS generator.

EGRID provides numerous  other aggregation options, and the reader may wish to  conduct  other
comparisons, such as for a particular utility, North American Electric Reliability Council (NERC) region,
or control area.
                                          -B4-

-------
Final Version-May, 2005
                                          Appendix C.
                          Electric Power Simple Cost Savings Estimates

The  performance verification report will provide estimated simple cost savings  as  compared to the
average retail price of electricity for the state in which the device under test (DUT) is located (Florida, for
this verification). Simple cost savings will also be based on the average nationwide retail price. Analysts
will employ the methods described in this Appendix.

The  simple cost savings is the annual estimated device-based power savings multiplied by the average
retail price of electricity:
                                      MWh      *RP   *103
                                      1V1WIIDUT .„„  Kf dec  1U
                   o-   i  ^  j. o  •           UUkAnn     elec                -w^   /-\ i
                   Simple Cost Savings =	           bqn. L1
       where:
               Simple Cost Savings = estimated annual device-based cost savings, dollars
               MWhDUT Ann = annual estimated device-based power savings, MWh
               RPeiec = average retail price of electricity, cents/kWh
               103 = conversion factor from MWh to kWh
               100 = conversion factor from cents to dollars

The  value for estimated MWhDUTAnn should  be available from the verification results.  This estimate
depends on the specific verification strategy and its derivation should be clearly described in the test plan
and verification results.  A simple example is the power production or power savings multiplied by the
annual availability or capacity factor. For example, a 200 kW fuel cell which operates at full capacity 75
percent of the time can be expected to generate 1314 MWh annually.

Varying values for RPeiec can be found in many resources.  This methodology of estimating  economic
payback uses the Energy Information Agency's (EIA) Table 5.6.A. Average Retail Price of Electricity to
Ultimate Customers  by End-Use  Sector,  by State to  find RPeiec-   This  table is  available  from
http://www.eia.doe.gov/cneaf/electricity/epm/table5_6_a.html. Table C-l provides data for 2004.
Table C-l.
Census Division
and State
New England
Connecticut
Maine
Massachusetts
New Hampshire
Rhode Island
Vermont
Middle Atlantic
New Jersey
New York
Pennsylvania
East North

Central
Illinois
Indiana
Michigan
Average Retail Price of Electricity to Ultimate Customers by End-Use Sector"
Residential
11.78
10.24
12.51
12.29
11.95
13.36
12.68
11.22
10.03
14.44
9.21

7.94

7.7
7.03
8.47
Commercial
10.57
8.48
12.99
10.9
10.79
11.89
11.33
9.94
8.34
11.67
8.46

7.17

6.94
6.23
7.88
Industrial
8.08
7.47
4.57
8.89
10.31
9.71
8.1
6.23
8.11
6.31
5.82

4.65

4.75
4.13
5.25
Transportation
5.2
5.46
—
5.08
~
—
—
7.1
10.92
6.8
7.08

5.51

4.94
8.45
8.92
All Sectors
10.61
9.12
10.6
11.08
11.19
12.12
11.02
9.6
8.96
11.75
7.91

6.55

6.49
5.54
7.29
                                          -Cl-

-------
Final Version-May,  2005
Table C-l. Average Retail Price of Electricity to Ultimate Customers by End-Use Sector"
Census Division
and State
Ohio
Wisconsin
West North
Central
Iowa
Kansas
Minnesota
Missouri
Nebraska
North Dakota
South Dakota
South Atlantic
Delaware
District of
Columbia
Florida
Georgia
Maryland
North Carolina
South Carolina
Virginia
West Virginia
East South
Central
Alabama
Kentucky
Mississippi
Tennessee
West South
Central
Arkansas
Louisiana
Oklahoma
Texas
Mountain
Arizona
Colorado
Idaho
Montana
Nevada
New Mexico
Utah
Wyoming
Pacific Contiguous
California
Oregon
Washington
Pacific
Noncontiguous
Alaska
Hawaii
U.S. Total
Residential
7.94
8.91
7.09
8.79
7.16
7.91
6.22
6.07
6.26
7.2
7.87
8.45
7.06
8.76
7.07
7.57
8.07
7.73
7.42
6.01
6.88
7.04
6.15
7.96
6.86
8.68
7.09
8.07
6.82
9.34
7.74
7.88
7.64
5.83
7.7
10.11
8.27
7
6.7
9.86
11.92
7.15
6.37
16.5
12.22
20.01
8.58
Commercial
7.37
6.95
5.79
6.46
6.24
5.92
5.23
5.48
5.82
6.46
7.15
7.23
6.55
7.8
7.15
9.18
6.77
7.09
5.85
5.39
6.86
6.98
5.7
8.03
7.05
7.5
5.68
7.93
6.28
7.79
7.12
7.39
7.31
5.14
7.21
9.7
7.39
5.51
5.66
8.49
9.27
6.38
6.19
14.7
10.74
17.93
7.81
Industrial
4.6
4.79
4.35
4.25
4.42
4.93
3.79
3.99
4.12
4.32
4.58
5.06
1.01
5.76
4.77
4.28
4.74
4.13
4.3
3.78
3.71
3.72
3.13
4.65
4.09
5.49
4.01
6.06
4.54
5.7
4.82
5.24
5.73
3.41
4.06
6.29
4.78
3.6
3.89
6.19
7.79
4.05
3.79
14.1
7.47
15.66
5.01
Transportation
8.26
—
5.36
—
—
6.72
3.87
—
—
—
5.25
—
2.57
7.53
5.05
5.83
~
~
7.07
5.7
13.95
—
—
13.95
7.23
—
7.9
—
7.11
5.31
—
5.29
—
~
~
~
5.43
6.55
6.56
6.08
6.46
—
6.51
All Sectors
6.62
6.86
5.85
6.29
6.03
6.28
5.37
5.24
5.53
6.33
6.9
7.08
6.4
8.07
6.48
6.93
6.87
6.17
6.27
5.09
5.59
5.65
4.55
6.78
6.02
7.23
5.5
7.24
6.01
7.65
6.66
7.21
7.05
4.91
6.14
8.44
6.87
5.3
4.93
8.54
9.9
6.16
5.68
15.15
10.88
17.72
7.32
                                           -C2-

-------
Final Version-May, 2005
         Table C-l. Average Retail Price of Electricity to Ultimate Customers by End-Use Sector"
                      Residential     Commercial    Industrial     Transportation
All Sectors
 Census Division
    and State
" Source: Energy Information Administration, Form EIA-826, "Monthly Electric Sales and Revenue Report with
State Distributions Report."	
Continuing  the  example from  above, Table  C-2 provides  the  estimated simple cost  savings  for  a
hypothetical 200 kW fuel cell located in Florida. This example uses the average retail price listed for all
sectors.  Individual  verification test plans may opt to use the average price for the sector (residential,
commercial, industrial, or transportation) that is most applicable to the DUT. This should be specified in
the test plan.
Table C-2. Fuel Cell Estimated Economic Payback

DUT capacity, kW
Estimated availability or capacity factor
MWhDUT,Am
RPekc, cents/kWh
Estimated Economic Payback, dollars
Florida
200
75%
1314
8.07
$106,040
Nationwide
200
75%
1314
7.32
$96,185
This approach is generally conservative because the actual prices are often the result of negotiation and
subject to local regulation or market forces.
                                           -C3-

-------