-------
Figure 4-6. Booster Pump and Bag Filter Assembly
Pre-filter - Prior to the treatment system, raw water from the wells passed through a 5-(im
bag filter (Figure 4-6) to remove sediments and/or particles. The filter bag was not changed
for the duration of the demonstration because the pressure drop across the cartridge never
reached 10 psi.
Adsorption - The adsorption system consisted of two 24-in x 72-in adsorption vessels in a
series (lead/lag) configuration (Figures 4-7 and 4-8). Each vessel was designed to contain 7.5
ft3 of Adsorbsia™ GTO™ media supported by 3.0 ft3 of gravel underbedding (only 7.0 ft3 of
media was actually loaded). The vessels were of composite polyethylene and fiberglass
construction.
Based on a design flowrate of 20 gpm, the empty bed contact time (EBCT) was 2.8 min for
each vessel or 5.6 for the lead/lag system. The Ap across a clean lead/lag system was 15 psi.
Backwash - The backwash frequency was determined based on the rate of differential
pressure buildup across the adsorption vessels. The design backwash flowrate was 20 gpm
and the design backwash duration was 10 min. The backwash step was followed with a 4-
min settling period and a 5-min fast rinse at a flowrate of 20 gpm. The total amount of
wastewater produced was 300 gal per vessel, or 600 gal for the lead/lag system.
Media Replacement - Adsorbsia™ GTO™ media is not regenerable and must be disposed
of after it is exhausted. Spent media can be disposed of as a non-hazardous waste after it
passes the EPA TCLP test. The media was expected to last for 21 months and, therefore, not
be disposed of during the study period.
20
-------
4.3
Figure 4-7. Adsorption Vessels
Treated Water Storage and Distribution - The treated water was sent to the 10,000-gal
atmospheric storage tank. A booster pump skid equipped with three Alyan pumps (Model
#CPS 12065) was used to provide pressure to the distribution system. Pump No. 1 is rated at
5 hp [224 ft of H2O], pump No. 2 at 10 hp [150 of H2O], and pump No. 3 at 10 hp [150 of
H2O]). The booster pump skid was connected to a 264-gal hydropneumatic tank, which
turned the well pumps on/off based on a low pressure of 90 psi and a high pressure of 100
psi.
System Installation
Siemens completed installation and shakedown of the system on January 28, 2009. The following briefly
summarizes system installation activities, including permitting, system offloading, installation,
shakedown, and startup.
4.3.1 Permitting. Design drawings and a process description of the proposed treatment system
were submitted to CT DPH by TurnKey Compliance Solution, LLC, a subcontractor to Siemens, on
October 29, 2008. CT DPH provided comments/concerns on December 3, 2008. The comments received
were:
21
-------
Figure 4-8. Adsorption System Valve Tree and Piping Configuration
(1) It was difficult to read the piping and instrumentation diagram (P&ID).
(2) The project might be held up due to issues related to discharge of backwash wastewater
to the sewer.
In response to the comments, TurnKey Compliance Solution provided a clearer copy of the P&ID to CT
DPH and informed CT DPH that the school had already received a wastewater discharge permit from CT
Department of Environmental Protection (DEP) on September 28, 2007. The permit was issued on
December 9, 2008.
Upon receipt of the permit, it was noted that the site owner had to complete an Operator Verification
Form and a Certificate of Completion Form once the system was installed. These forms were submitted
to CT DPH on January 9, 2009.
4.3.2 Installation, Shakedown, and Startup. System components were delivered to the
Woodstock Middle School on January 6, 2009. Installation activities included offloading, staging (see
Figure 4-9), plumbing (from the adsorption vessels to the booster pump and hydropneumatic tanks), and
wiring. Due to the delivery of incorrect solenoid valves with the system, installation could not be
completed until the correct ones were received, which occurred on January 19, 2009. The final
installation and wiring were completed on January 21, 2009.
22
-------
Figure 4-9. Offloading and Staging of Equipment
On January 21, 2009, Siemens inspected the system (see Figure 4-10) and associated piping connections,
verified electrical wiring and relays, and performed hydraulic testing before media loading. Upon
completion, 7.0 ft3 (instead of 7.5 ft3) of media was loaded into each vessel with approximately 34 in of
freeboard above the media beds. Freeboards after gravel loading was not measured. After control heads
were reinstalled, the system was re-pressurized and the adsorption vessels were backwashed individually
at a maximum flowrate of 10 gpm for 20 min (see more detailed discussion about backwash in Section
4.4.2). Afterwards, the control heads were removed to re-measure the freeboards, which remained at 34
in. Sodium hypochlorite (NaOCl) was added to the adsorption vessels on the evening of January 27,
2009, and the system was thoroughly flushed the next day. Samples taken showed negative results for
bacteria.
23
-------
Figure 4-10. Treatment System Installed
(From left to right: Booster Pump, Bag Filter, Adsorption Vessel
A, and Adsorption Vessel B. One Hydropneumatic tank and one
10,000 gal Storage Tank not Shown)
The system remained offline until the arsenic treatment system was inspected by CT DPH on January 29,
2009, and a project completion letter to allow the system to be started was received by the school on
February 3, 2009. The system became operational on February 10, 2009.
After startup, it was realized that the system was not operating against enough back pressure so it was
shut down on February 11, 2009, to facilitate installation of a pressure transducer before the atmospheric
tank. A decision was then made to create the needed back pressure by throttling a ball valve before the
atmospheric tank and the system was turned on again on February 12, 2009. (The pressure transducer
was eventually installed on March 25, 2009.) During hydraulic testing, the inlet pressure to the system
was 10 psi; after the booster pump and with the valve throttled, the inlet pressure was 34 psi.
During installation, the system was set to backwash weekly at a flow rate of 10 gpm. The frequency was
later changed to once every 30 days on February 17, 2009, per Battelle's request.
On February 27, 2009, the operator noticed that readings on the totalizers at the wellheads were
decreasing instead of advancing; however, this problem did not occur again. It also was observed that
only one well pump was operating and with the booster pump in operation the flowrate to the system was
24
-------
a mere 9 gpm instead of the designed value of 20 gpm. Previously with both well pumps operating and
the booster pump turned on, the flowrate to the system was about 20 gpm.
On March 9 and 10, 2009, two Battelle staff members visited the school to inspect the system and
provide operator training. Table 4-4 summarizes the punch-list items and corrective actions taken.
The Battelle staff members observed that the arsenic treatment system was configured in parallel
although the engineering drawing showed that the system should be configured in series as requested
by CT DPH. On March 25 through 27, 2009, Siemens visited the school to correct the system
configuration and several other punch-list items listed in Table 4-4.
Table 4-4. Punch-List Items and Corrective Actions
Date
03/09/09-
03/25/09
02/27/09-
03/24/09
03/09/09-
03/24/09
03/09/09-
04/17/09
03/09/09-
03/27/09
03/09/09-
03/27/09
03/09/09-
03/24/09
03/09/09-
03/24/09
03/09/09-
04/17/09
03/09/09-
03/24/09
03/09/09-
03/24/09
Issue/Problem Encountered
System configured for parallel
operation instead of series operation
Pressure reducing valve (PRV) not
installed per Siemens' design
Pressure switch to trigger booster
pump not installed per Siemens'
design
Pressure to booster pump lower than
vendor-recommended range of 12 to
15 psi
Pressure gauge at inlet incorrect size
(0-100 psi)
Pressure gauge missing on outlet
line leading to atmospheric storage
tank
Incorrect sample taps (4) installed
on treatment system
Leaks observed at T-joint at
distribution booster pump
Backwash flowrate lower than
vendor- recommended flowrate of
20 gpm
Backwash missing a co-current fast
rinse step
Duration between backwash events
too short
Corrective Action
System re-configured for series operation by
opening/closing selected valves
PRV installed to provide extra protection to
the system piping
Pressure switch installed to trigger booster
pump at pressure <60 psi
%-in flowmeter/totalizer and associated
piping after each well pump replaced with
1.5 -in and/or 1-inflowmeter/
totalizer and piping to minimize pressure
loss (this corrective action eventually not
done)
Inlet pressure gauge replaced with a 0-60 psi
gauge
A 0-30 psi pressure gauge installed on outlet
line
All four sample taps replaced with '/4-in
valve with a barb fitting
Leaky T-joint replaced with a new T-joint
Supply line relocated from 264-gal
hydropneumatic tank to 10,000-gal storage
tanking using a 1-in line
A fast rinse duration of 5 min at 20 gpm
added into programming of valve controller
Backwash frequency changed from every 7
days to every 30 days in late February 2009,
then to every 99 days to allow better control
over backwashing by operator
Work
Performed
By
Siemens
Siemens
Siemens
Woodstock
Middle
School
Siemens
Siemens
Siemens
Siemens
Woodstock
Middle
School
Siemens
Siemens
As noted in Section 4.3.3, a booster pump was installed between the well pumps and the adsorption
vessels to provide sufficient pressure for system operation. During Battelle's site visit on March 9, 2009,
the booster pump was bypassed because the pressure transducer required to create back pressure had not
been installed. Several tests were conducted on the system with and without bypassing the booster pump.
25
-------
The pressure at the wellhead was 20 psi, but once the booster pump was turned on, the pressure at the
wellhead decreased to zero. Both with and without bypassing, the pressure after the booster pump was 10
psi. Siemens determined that a pressure loss at the inlet to the booster pump had occurred due to the
small size of the piping that fed into the booster pump. The piping from the well pumps was 1.5 and 1 in,
but the combined flow piping was reduced to % in. This reduced size apparently caused restriction and
had to be changed to 1.5 in to ensure proper functioning of the booster pump. This change, however, was
never made and the booster pump remained bypassed for the entire demonstration study.
4.4 System Operation
4.4.1 Operational Parameters. The operational parameters for the 19-month demonstration study
were tabulated and are attached as Appendix A. Table 4-5 summarizes key parameters. The system
began to operate on February 10, 2009, but logging of operational data did not begin until March 10, 2009
when two Battelle staff members visited the site to inspect the system and provide operator training.
During the first month of operation, the system was turned off for just one day on February 11, 2009, for
installation of a pressure transducer on the far side of the treatment system (before the atmospheric tank)
to create sufficient back pressure on the system. The system, however, was restarted on February 12
without the transducer and a valve at the end of the system was throttled to create the needed back
pressure. The pressure transducer was eventually installed on March 25, 2009.
From March 10, 2009, through the end of the performance evaluation study on September 30, 2010,
Wells No. 1 and No. 2 operated for a total of 560.9 and 562.7 hr, respectively. The total number of days
the system was operating, regardless whether the school was in session or out of session, was 570 days.
Therefore, the average daily system run time was about 1 hr/day (note that Wells No. 1 and No. 2
operated simultaneously).
Based on readings from the totalizers installed at the wellheads, Wells No. 1 and No. 2 produced 259,850
and 284,760 gal of water, respectively, during the entire study period. The amount of water produced by
Well No. 2 was slightly higher (9.6%) than that by Well No. 1. This was reflected by the slightly higher
flowrate of Well No. 2, i.e., 8.9 vs. 8.1 gpm as noted in Section 4.1.
The total amount of water produced by Wells No. 1 and No. 2 was 544,610 gal, which is comparable to
the amounts, i.e., 528,000 and 541,000 gal, registered by the totalizers installed on the influent side of
Adsorption Vessels A and B, respectively. These amounts included the 21,000 and 26,000 gal registered
by Vessels A and B totalizers, respectively, when the system was configured in parallel. Siemens visited
the school on March 25, 2009, to change the system configuration in series.
Well flowrates were calculated by dividing incremental wellhead totalizer readings by respective run
times (after removing obvious outliers). The average flowrate from Well No. 1 was 7.1 gpm and the
average flowrate from Well No. 2 was 7.7 gpm, compared to the 8.1 and 8.9 gpm reported by the operator
prior to the study.
After the flow was combined and boosted, it flowed through Vessels A and then Vessel B before entering
the 10,000-gal atmospheric storage tank. Instantaneous flowrate readings tracked by the flow meters
installed on the inlet of the vessels were constant, ranging from 15.6 to 16.7 gpm and averaging 16.3 gpm
for Vessel A and ranging from 14.7 to 16.9 gpm and averaging 16.4 gpm for Vessel B. These data did
not include those before March 25, 2009, when the system was incorrectly configured in parallel or those
from May 8 through 13, 2009, when the operator reported extremely low flowrate (e.g. 1.7 gpm) through
Vessel A, but normal flow through Vessel B. The lack of flow through Vessel A was due to a defective
seal (loose O- ring), which was repaired by Siemens on May 13, 2009. Once the seal was repaired,
Siemens tested and backwashed the system.
26
-------
Table 4-5. Summary of System Operation Parameters
Operational Parameter
Duration
Total Operating Time (hr)
Total Operating Days (day)
Average Daily Run Time (hr/day)
Individual Well Production (gal)
Total Well Production (gal)
Throughput (gal)
Calculated Well Flowrate (gpm)(a)
Instantaneous Flowrate (gpm)(a>b)
EBCT (min/vessel)(c)
Hydraulic Loading Rate (gpm/ft2)
Pressure at Wellhead (psi)
Pressure After Booster Pump (psi)(d)
Pressure After Filter Cartridge (psi)
Pressure Prior to Vessel A (psi)
Pressure After Vessel A (psi)
Pressure After Vessel B (psi)
Ap Across Vessel A (psi)
Ap Across Vessel B (psi)
Values/Conditions
03/10/09-09/30/10
560.9 (Well No. 1)
562.7 (Well No. 2)
570
1.0
259,850 (Well No. 1)
284,760 (Well No. 2)
544,610
528,000 (Vessel A)
541,000 (Vessel B)
7.1 [3. 0-9.4] (Well No. 1)
7.7 [2.8-10.5] (Well No. 2)
16.3 [15.6-16.7] (Vessel A)
16.4 [14.7-16.9] (Vessel B)
3. 2 [3. 3-3.1] (Vessel A)
3.2 [3. 5-3.1] (Vessel B)
5.2 [5.0-5.3] (Vessel A)
5.2 [4.7-5.4] (Vessel B)
28.8 [20-36] (Well No. 1)
28.8 [20-36] (Well No. 2)
23.0 [15-32]
21.7 [14-31]
21.2 [13-30]
13.1 [10-23.5]
4.7 [2-11]
8.3 [2-10]
8.4 [1-17.5]
(a) After omitting obvious outliers.
(b) Not including data prior to March 25,
incorrectly configured in parallel.
(c) Based on instantaneous flowrates and
each vessel.
(d) With booster pump bypassed.
2009, when system was
7.0 ft3 (or 52 gal) of media in
Based on 7.0 ft3 (or 52 gal) of media in each vessel and instantaneous flowrate, the average EBCT and
hydraulic loading rate were 3.2 min/vessel and 5.2 gpm/ft2, respectively, compared to the design values of
2.8 min/vessel and 6.4 gpm/ft2.
From March 10 through 24, 2009, while the system was configured in parallel and the booster pump was
bypassed, average pressure readings at the wellheads were 17 and 16 psi at Wells No. 1 and 2,
respectively (see Figure 4-11). Once the system was placed in series and the pressure transducer installed
(with the booster pump still being bypassed), average pressure readings at both wellheads increased to
28.8 psi (Table 4-5). The pressure after the booster pump (with the pump bypassed) was 23 psi (on
average), which was reduced to 21.7, 13.1, and 4.7 psi after the filter cartridge, Vessel A, and Vessel B,
respectively. As shown in Figure 4-11, from March 25 through June 10, 2009, as high as 30 psi was
measured at the inlet to Vessel A and as much as 26 psi pressure differential was measured across the
system. Siemens suggested that the elevated inlet pressure and pressure differential were caused by a
combination of the system not having been thoroughly backwashed since startup and the inlet line to the
system was still at % in. The system was thoroughly backwashed on June 10, 2009 (see Section 4.4.2),
27
-------
Pressure Readings
to
oc
Welll
Well 2
After Booster Pump
After Filter Cartridge
Inlet to Vessel A
After Vessel A
After Vessel B
H-H—hHH 111T^ 1^1111
2/26/09 3/8/09 3/18/09 3/28/09 4/7/09 4/17/09 4/27/09 5/7/09 5/17/09 5/27/09 6/6/09 6/16/09 6/26/09 7/6/09
Date
Figure 4-11. Pressure Readings Across Treatment Train (from March 10 through June 30, 2009)
-------
after which average differential pressure was reduced to 7.9 psi for Vessel A and 7.5 psi for Vessel B.
After June 10, 2009, through the end of the performance evaluation study on September 30, 2010,
pressure readings across the treatment train remained rather similar to those recorded between June 10
through June 30, 2009, and therefore, were not included in Figure 4-11.
4.4.2 Backwash. Each adsorption vessel was designed for a backwash at 20 gpm for 10 min
followed by a fast rinse at 20 gpm for 5 min, generating 300 gal of wastewater. During system
installation, the system was backwashed briefly at a maximum flowrate of 10 gpm for 20 min. On March
10, 2010, when Battelle staff visited the school, backwash of both vessels was attempted. Soon after the
initiation of backwash, a flowrate of 6.3 gpm and a system pressure of 110 psi were observed. Both
flowrate and pressure continued to decrease, ending at 2.2 gpm and 20 psi by the conclusion of backwash.
The flowrates experienced were much lower than the design value of 20 gpm. Water for backwash
originated from the 264-gal hydropneumatic tank located downstream from the 10,000-gal atmospheric
tank and the booster pump skid (Section 4.2). It appeared that the booster pumps were not triggered when
the system pressure reached the 90-psi low pressure setpoint, thus causing the flowrate and pressure to
drop. Siemens recommended that the backwash water line be moved so that it connected to the
distribution system.
The backwash frequency was set initially for once every seven days but changed to once every 30 days on
February 16, 2009 (Table 4-6). The system was then backwashed automatically on March 17, 2009, but
generated only 28 gal of wastewater. Since then, the system was backwashed once every six to eight days
on March 25, March 31, and April 7, 2009, and generated only 30 to 45 gal of wastewater during each
backwashing event (note that only Vessel A was backwashed). This represents a backwash/fast rinse
flowrate of 2.0 to 3.0 gpm, assuming that the backwash and fast rinse durations were 10 and 5 min,
respectively, as set. The low backwash flowrates observed were similar to that encountered during
Battelle's site visit on March 10, 2010, suggesting that the backwash water line had not yet been moved
as recommended by Siemens. Upon completion of installation of a new supply line by the operator on
April 17, 2009, Siemens visited the school on April 27, 2009, to backwash the system and reported a
significantly increased backwash and fast rinse flowrate of 14 gpm. The actual flowrate might have been
higher (28.2 gpm) based on the 845 gal of wastewater produced during the backwash event. The
backwash frequency was reset to 99 days (the maximum allowed) because little or no increase in Ap was
observed across the adsorption vessels.
After backwash on April 27, 2009, Ap across Vessels A and B remained elevated at as high as 10 and
17.5 psi, respectively. Dow chemical believed that the system had still not been backwashed thoroughly
and recommended that each vessel be backwashed for 30 min at the maximum bed expansion. Dow
Chemical's rule of thumb was to backwash each vessel with 15 to 25 BV of water before system startup,
but only approximately 9 BV was used by April 27, 2009. On June 11, 2009, Siemens conducted the 30-
min backwash using approximately 826 gal (or 15 BV) of water for each vessel (see Table 4-6). Upon
completion, Ap across both vessels was reduced to 7 psi and stayed constantly around 7 to 8 throughout
the remainder of the study period.
After June 11, 2009, amounts of wastewater produced during all backwashing events ranged from 540 to
660 gal, excluding three outliers at 1,449 and 1,077 on August 26 and 27, 2009, due to a power outage
and a subsequent system reset, and at 912 gal on March 17, 2010. The amounts of wastewater produced
were very close to the design values of 600 gpm per event (see Table 4-3). However, the backwash
frequency varied from 7 to 77 days, even though the system was set to backwash every 99 days. It
appeared that the backwash timer was not functioning correctly even after being reset a number of times.
A consistent backwashing pattern never occurred during the performance evaluation study.
29
-------
Table 4-6. Summary of System Backwash Operations
Date
02/17/09
03/17/09
03/25/09
03/31/09
04/07/09
04/27/09
05/05/09
05/08/09
05/11/09
05/13/09
05/28/09
06/11/09
07/09/09
08/26/09
08/27/09
09/03/09
10/21/09
11/13/09
12/10/09
01/28/10
03/04/10
03/17/10
06/02/10
06/10/10
07/01/10
09/09/10
Actual
Duration
Between
Backwashes
(day)
_(a)
28
8
6
7
20(b)
8
3
3
2
15
14
28
48
1
7
48
23
27
49
35
13
77
8
21
70
Amount of
Wastewater
Produced
(gal)
-
28
30
45
43
845
214
71
364
562
232
1,653
542
1,449
1,077
540
550
655
656
657
655
912
656
659
660
656
No. of
Vessels
Backwashed
1 (Vessel A)
1 (Vessel A)
1 (Vessel A)
1 (Vessel A)
2
1 (Vessel(c))
1 (Vessel(c))
1 (Vessel(c))
2
1 (Vessel(c))
2
2
?
?
2
2
2
2
2
2
2(d)
2
2
2
2
Remarks
Old backwash piping used until 04/27/09
-
-
-
-
Began to use new backwash piping
-
-
-
-
-
Each vessel backwashed for 30 min
-
System reset due to power surge
System reset due to power surge
-
-
-
-
-
-
-
-
—
—
-
(a) Backwash frequency set at once every 30 days in programmable logic controller (PLC).
(b) Backwash frequency set at once every 99 days in PLC.
(c) Not certain what vessel was backwashed.
(d) Not certain if only two vessels were backwashed.
4.4.3 Residual Management. Residuals expected included backwash wastewater, spent bag
filters, and spent media. No AM nor bag filter was replaced during the study period; therefore, the only
residuals produced was backwash wastewater. Backwash wastewater was discharged directly to the drain
line to the sewer. No backwash wastewater or solids were collected during the performance evaluation
study. The bag filter was not changed during the demonstration study.
4.4.4 System/Operation Reliability and Simplicity. Once placed into series operation, the main
operational issues affecting the system were limited to (1) high inlet and differential pressure across the
two adsorption vessels and (2) random backwash frequency (even though the timer was set for once every
30 or 99 days). The issue of high inlet and differential pressure was addressed through thorough vessel
backwash; the random backwash issue was never resolved during the performance evaluation study.
The system O&M and operator skill requirements are discussed below in relation to pre- and post-
treatment requirements, levels of system automation, operator skill requirements, preventative
maintenance activities, and frequency of chemical/media handling and inventory requirements.
30
-------
Pre- and Post-Treatment Requirements. No pretreatment was required, but the raw water from the wells
passed through a 5-(im bag filter located upstream from the treatment system. The bag filter did not need
to be changed during the performance evaluation study due to lack of solids. The pressure loss across the
bag filter remained between 1 to 3 psi during the entire study period.
System Automation. The system was operated by interlocking well pump alternating on/off controls.
The system also was fitted with automated controls to allow for automatic backwash for both adsorption
vessels. The backwash frequency could be set on the controller but it appeared that that feature never
worked adequately. On May 7 and 8, 2009, Siemens visited the school to change pistons in two
controllers at the top of the vessels and replace an O-ring on the controller that blocked flow to Vessel B.
Operator Skill Requirements. Under normal operating conditions, the skills required to operate the
Adsorbsia™ GTO™ system were minimal. The operator's duties were to record data from the system.
The Woodstock facility is a non-transient, non-community water system. According to CT DPH, all
community and non-transient non-community water systems are required to have their water treatment
plants, distribution systems, and small water systems operated by certified operators. To be certified as a
water treatment plant operator, a person must demonstrate the ability to responsibly operate a plant of the
given classification applied for (i.e., I, II, 111, IV) by passing a written examination. The minimum
education requirement is either a high school diploma or a high school equivalency diploma. Any amount
of educational training beyond high school (12 years) in a field of study applicable to water treatment
may be substituted for an equal amount of the experience requirement; however, one year of experience is
required for all classes. Experience in class means experience gained in operating a particular class plant
or the next lower class providing that the operator has direct responsible charge. Operators must renew
their certificates every three years by meeting specific training hour requirements for renewal. The
Woodstock school operator has a Class I certification.
Preventive Maintenance Activities. There was no regularly scheduled maintenance activity required for
the operation of the treatment system.
4.5 System Performance
4.5.1 Treatment Plant Sampling. Water samples were collected on 40 occasions, including four
duplicate and 21 speciation events at the IN, TA and TB sampling locations. One of the 21 speciation
sampling events took place after September 30, 2010, when logging of operation data officially ended.
Table 4-7 summarizes results of arsenic, iron, manganese, and titanium measured at the four sampling
locations across the treatment train. Table 4-8 summarizes results of other water quality parameters.
Appendix B contains a complete set of analytical results for the demonstration study. The results of the
analysis of the water samples collected throughout the treatment plant are discussed below.
Arsenic. Figure 4-12 contains three bar charts showing concentrations of various arsenic species at the
wellhead (after Wells No. 1 and No. 2 water combined) and after the lead (A) and lag vessel (B)
measured during the 21 speciation events. Total arsenic concentrations in raw water ranged from 17.9 to
29.3 |og/L and averaged 24.7 |o,g/L, existing almost entirely as soluble arsenic. As(V) was the
predominating species, with concentrations ranging from 15.5 to 22.4 (ig/L and averaging 19.6 |o,g/L. The
remaining soluble fraction was As(III), with concentrations ranging from 2.6 to 10.1 (ig/L and averaging
5.8 (ig/L. The presence of As(V) as the predominating species is consistent with elevated DO and ORP
readings measured (i.e., 7.5 mg/L and 311 mV [on average], respectively). Aeration during sampling also
could contribute to the high DO and ORP readings observed. Note that only three sets of DO
measurements were made during the entire study period due to malfunctioning of handheld probes.
31
-------
Table 4-7. Summary of Arsenic, Iron, Manganese, and Titanium Analytical Results
Parameter
As (total)
As (soluble)
As
(paniculate)
As (III)
As(V)
Fe (total)
Fe (soluble)
Mn (total)
Mn (soluble)
Ti (total)
Ti (soluble)
Sampling
Location
IN
TA
TB
IN
TA
TB
IN
TA
TB
IN
TA
TB
IN
TA
TB
IN
TA
TB
IN
TA
TB
IN
TA
TB
IN
TA
TB
IN
TA
TB
IN
TA
TB
Sample
Count
40
40
40
21
21
21
21
21
21
20(a)
21
21
20(b)
21
21
39(o)
40
40
21
21
21
40
40
40
21
21
21
40
40
40
21
21
21
Concentration (jig/L)
Minimum
17.9
0.1
0.1
19.7
0.1
0.1
0.1
0.1
0.1
2.6
0.1
0.1
15.5
O.I
O.I
<25
<25
<25
<25
<25
<25
9.8
O.I
O.I
8.6
O.I
O.I
0.9
1.3
0.8
0.9
0.2
0.3
Maximum
29.3
17.2
5.2
29.1
18.0
5.0
1.5
0.1
0.2
10.1
6.4
1.4
22.4
13.6
4.4
83
<25
<25
33
<25
<25
32.0
1.2
0.7
23.4
0.6
0.8
4.8
98.6
38.3
1.5
2.2
1.7
Average
24.7
.*
.*
25.5
.*
.*
0.2
.*
.*
5.8
.*
.*
19.6
.*
.*
27
<25
<25
<25
<25
<25
17.5
0.2
0.2
16.8
0.2
0.2
1.4
9.5
3.1
1.1
1.2
1.0
Standard
Deviation
2.6
.*
.*
2.2
.*
.*
0.4
.*
.*
1.9
.*
.*
2.2
.*
.*
<25
-
-
<25
-
-
3.5
0.2
0.2
2.9
0.2
0.2
0.6
20.0
6.3
0.2
0.4
0.4
(a) One outlier (i.e., 27.4 ug/L) on 03/10/09 omitted.
(b) One outlier (i.e., 0.4 ug/L) on 03/10/09 omitted.
(c) One outlier (i.e., 189 ug/L) on 06/03/10 omitted.
* Not meaningful for concentrations related to breakthrough; see Figures 4-12 and 4-13
and Appendix B for results.
As shown by the second and the third bar charts, both soluble As(V) and soluble As(III) could be
removed by Adsorbsia GTO™ media™. However, after treating approximately 395,000 gal (or 7,600
BV) of water (1 BV = 7.0 ft3 = 52 gal of media in one tank), arsenic concentrations following the lead
vessel had already reached 10 ug/L. The 7,600 BV experienced was much shorter than the vendor-
projected run length of 108,000 BV. By the end of the performance evaluation study, the arsenic
concentration in the system effluent was 5.2 (ig/L (on October 6, 2010). Figure 4-13 presents arsenic
breakthrough curves.
32
-------
Table 4-8. Summary of Other Water Quality Parameter Results
Parameter
Alkalinity
(as CaCO3)
Fluoride
Sulfate
Nitrate
(asN)
Phosphorus
(asP)
Silica
(as SiO2)
Turbidity
pH
Temperature
Dissolved Oxygen
(DO)
Oxidation-
Reduction Potential
(ORP)
Total Hardness
(as CaCO3)
Ca Hardness
(as CaCO3)
Mg Hardness
(as CaCO3)
Sampling
Location
IN
TA
TB
IN
TA
TB
IN
TA
TB
IN
TA
TB
IN
TA
TB
IN
TA
TB
IN
TA
TB
IN
TA
TB
IN
TA
TB
IN
TA
TB
IN
TA
TB
IN
TA
TB
IN
TA
TB
IN
TA
TB
Unit
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
ug/L
ug/L
ug/L
mg/L
mg/L
mg/L
NTU
NTU
NTU
S.U.
S.U.
S.U.
°C
°C
°C
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
mg/L
Sample
Count
33W
35
35
16
16
16
16
16
16
16
16
16
35
35
35
35
35
35
35
34W
35
11
11
11
10W
10W
gW
3
3
3
12
12
11
15W
\5(a>
I5(a>
I5(e>
I5(e>
\5(e>
16
16
16
Concentration
Minimum
68.1
56.1
56.1
0.3
0.3
0.3
18.1
20.6
19.4
O.05
O.05
O.05
<10
<10
<10
14.0
1.3
3.2
0.1
0.1
0.2
6.3
6.7
5.6
6.5
10.4
11.6
2.8
2.1
2.1
244
243
19.5
58.2
67.0
66.9
52.4
61.8
61.7
4.9
4.7
4.8
Maximum
87.9
93.9
82.8
2.0
0.5
2.4
26.1
27.7
27.2
0.1
O.05
O.05
<10
<10
<10
16.8
17.9
17.1
4.0
19.0
9.3
7.5
7.6
7.5
22.7
22.8
22.8
9.9
9.7
9.8
417
418
396
96.1
89.5
90.6
90.6
84.8
85.9
8.6
7.7
7.2
Average
76
74
73
0.5
0.3
0.5
22.3
23.2
22.8
O.05
O.05
O.05
<10
<10
<10
15.8
13.3
11.7
1.0
2.2
1.3
7.1
7.3
7.0
14.4
15.0
15.5
7.5
6.8
7.2
311
323
274
81.8
79.8
79.1
76.0
74.1
73.4
5.9
5.8
5.7
Standard
Deviation
4.9
6.5
6.3
0.4
0.1
0.5
2.0
2.0
2.0
0.0
-
-
-
-
-
0.7
3.7
3.5
0.8
3.7
1.6
0.3
0.3
0.5
4.3
3.7
3.8
4.1
4.1
4.4
58.4
64.3
126
9.5
6.9
6.8
9.6
7.1
6.9
1.0
0.9
0.8
(a) Two outliers (i.e., 126 and 1 18 mg/L) on 04/21/10 and 06/03/10 omitted.
(b) One outlier (i.e., 62.0 NTU) on 04/07/09 omitted.
(c) Two outliers (i.e., 25.0°C) on 03/10/09 and 06/18/09 omitted.
(d) One outlier each (i.e., 127, 1 12, and 134 mg/L [as CaCO3]) at IN, TA, and TB, respectively, on
10/29/09 omitted.
(e) One outlier each (i.e., 120, 105, and 127 mg/L [as CaCO3]) at IN, TA, and TB, respectively, on
10/29/09 omitted.
33
-------
35 j
30 -
25 -
80
o
15
Ol
0 15-
3
10 -
5 -
0 -
Arsenic Species at Inlet (IN)
~
—
—
—
1 — |
-
-
=
—
=
—
—
—
=
—
[=1 As (participate) ^«As(V)
1=1 As(lll) As MCL (10 ug/L)
—
-
-
—
—
—
—
-
—
—
—
—
—
—
—
-
_
—
«P«?«P«?«?«?«?«P«?«P^?^?^?^?^?^?^?^?^?^?
d*> #• #• ^ #• *X" «*' *>" ' o^ ^ *x'
-------
Arsenic Species after Tank B (TB)
at io
0)
u 15-
O
U
wl
As(Particulate)
-- AsMCL(10ug/L)
1 | pq
_H_
Figure 4-12. Concentrations of Various Arsenic Species at IN, TA and TB
Sampling Locations (Continued)
Why Adsorbsia GTO™ media™ achieved such a short run length is unknown. Iron concentrations in raw
water were mostly below the MDL of 25 ug/L. Manganese concentrations also were low, ranging from
9.8 to 32.0 ug/L, and averaging 17.5 ug/L. Manganese existed almost entirely in the soluble form and
was removed by the media to 0.2 ug/L (on average). Concentrations of competing anions such as
phosphorus and silica also were low, either <10 ug/L (the MDL for phosphorus) or at 15.8 mg/L (as
SiO2). Some silica was removed by the media. Immediately after system startup, silica was reduced to as
low as 1.3 mg/L (as SiO2) following the lead vessel. Silica concentrations gradually increased to the raw
water level after treating 145,600 gal (or 2,800 BV) of water (1 BV = 7.0 ft3 = 52 gal). pH values ranged
from 5.6 to 7.6 and averaged 7.2 throughout the treatment train. This pH range was considered ideal for
arsenic adsorption.
Titanium. Total titanium concentrations in source water were low, ranging from 0.9 to 4.8 ug/L and
averaging 1.4 ug/L. Total titanium concentrations following the lead and lag vessels increased slightly to
9.5 and 3.1 ug/L (on average), respectively, due primarily to leaching of titanium-oxide particles. The
highest detected titanium concentration was 98.6 ug/L.
Other Water Quality Parameters. Alkalinity values ranged from 56.1 to 93.9 mg/L (as CaCO3) across
the treatment train. Concentrations of total hardness, existing primarily as calcium hardness (about
92.9%), ranged from 58.2 to 96.1 mg/L (as CaCO3), and remained essentially unchanged across the
treatment train. Fluoride concentrations ranged from 0.3 to 2.4 mg/L; sulfate from 18.1 mg/L to 27.7
mg/L; both did not appear to be affected by the AM system. Nitrate was not detected in any sample but
one at 0.1 mg/L.
35
-------
Total As Breakthrough Curves
40.0
Throughput (xlOOO gal)
Figure 4-13. Total Arsenic Breakthrough Curves from Lead and Lag Vessels
4.5.2 Distribution System Water Sampling. Prior to the installation/operation of the treatment
system, four first draw baseline distribution system water samples were collected. The first baseline
samples were collected on May 29, 2008, from three locations, i.e., the kitchen sink, the nurses station,
and the staff dining areas. The three additional baseline samples were collected from the kitchen sink
only on Novemeber 14, 2008, December 2, 2008 and January 4, 2009. After system startup, distribution
system water sampling continued on a monthly basis from the kitchen sink. Table 4-9 presents results of
the distribution system water sampling.
The most noticeable change in the distribution samples since system startup was a decrease in arsenic
concentration. Baseline arsenic concentrations ranged from 22.0 to 25.7 (ig/L and averaged 23.1 (ig/L.
After system startup, arsenic concentrations were reduced to 0.6 to 3.5 (ig/L. Iron concentrations were
below the MDL of 25 (ig/L both before and after system startup with a few exceptions at 43, 39, 39 and
32 (ig/L. Baseline manganese concentrations were low, ranging from 1.2 to 7.9 (ig/L and averging 4.3
(ig/L. After system startup, its concentrations remained low for 11 of the 16 sampling events. The other
five events had higher manganese concentrations ranging from 10.6 to 184 (ig/L. Why the concentrations
were elevated is not known.
Lead concentrations of all water samples collected before and after the installation of the treatment
system averaged 1.3 (ig/L within a range of <0.1 to 2.5 (ig/L. Copper concentrations ranged from 85.6 to
480 (ig/L across all sampling locations, with no samples exceeding the 1,300 (ig/L action level both
before and after system startup. The arsenic treatment system did not appear to have an effect on the lead
or copper concentration in the distribution system.
36
-------
Table 4-9. Distribution System Water Sampling Results
Sampling
Event
Date
BLl(a)
BL2
BL3
BL4
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
05/29/08
11/14/08
12/02/08
01/07/09
03/25/09
04/22/09
05/20/09
06/16/09
07/02/09
08/12/09
09/10/09
10/15/09
11/10/09
12/15/09
01/12/10
02/09/10
03/10/10
04/07/10
05/05/10
06/02/10
.0
-*^
sS
a jo
M a
cs a
35 P
hr
16.1
14.4
14.2
15.3
16.0
16.1
NA
13.6
16.3
16.0
188
135
15.5
17.8
16.5
NA
16.5
16.0
16.5
16.5
16.0
16.0
M
a.
S.U.
8.1
8.1
8.1
8.1
8.1
8.1
7.7
7.9
7.6
7.5
7.6
7.6
7.7
7.7
7.9
7.9
7.8
7.7
8.0
8.1
7.9
8.1
Alkalinity00
mg/L
72.5
74.7
72.5
69.1
75.0
65.2
63.3
66.3
68.9
66.3
66.9
66.3
61.1
70.2
70.7
71.1
83.3
77.7
77.6
71.1
71.7
76.0
5«
•<£
ug/L
23.6
22.7
22.1
22.6
25.7
22.0
1.3
2.1
1.7
1.8
1.7
3.5
0.6
3.1
2.2
2.0
2.8
2.4
2.4
3.1
3.0
3.5
1>
u.
ug/L
<25
<25
<25
<25
<25
<25
<25
43
<25
<25
<25
<25
39
<25
39
<25
<25
<25
<25
<25
<25
32
I
ug/L
6.0
6.5
7.9
2.1
2.1
1.2
16.8
12.8
7.5
7.7
10.6
184
20.7
6.8
6.6
4.9
2.8
3.1
3.7
3.4
3.2
2.8
.a
a.
ug/L
1.1
0.3
1.2
1.1
0.9
0.8
1.6
1.5
1.2
1.6
1.4
2.5
2.2
1.1
0.9
1.6
1.3
0.8
1.3
0.1
1.0
1.1
U
ug/L
124
85.6
101
93.6
107
120
480
448
435
384
250
246
248
276
275
240
176
156
165
149
134
108
4.6
(a) First baseline sampling event taking place at three locations, including
school kitchen sink, nurses sink, and staff dining room. All additional
baseline and distribution sampling performed at kitchen sink.
(b) asCaCO3.
BL = baseline sampling; NA = not available; NS = not sampled
Lead action level = 15 ug/L; copper action level =1.3 mg/L
System Cost
The cost of the treatment system was based on the capital cost per gpm (or gpd) of the design capacity
and the O&M cost per 1,000 gal of water treated. This required tracking of the capital cost for the
equipment, site engineering, and installation and the O&M cost for media replacement and disposal,
chemical supply, electricity consumption, and labor.
4.6.1 Capital Cost. The capital investment for equipment, site engineering, and installation for the
20-gpm treatment system was $51,895 (Table 4-10). The equipment cost was $30,215 (or 58% of the
total capital investment), including $24,007 for the treatment system and media, $4,308 for vendor labor,
and $1,900 for freight.
The site engineering cost included the cost for the preparation of a process flow diagram and relevant
mechanical drawings of the treatment system, piping, valves, and a backwash discharge line, as well as
submission of a permit application package to CT DPH for approval. The site engineering cost was
37
-------
Table 4-10. Capital Investment Cost for Adsorbsia™ GTO™ Treatment System
Description
Quantity
Cost
% of Capital
Investment Cost
Equipment Costs
24-in Diameter Fiberglass Pressure
Vessels
Adsorbsia™ GTO™ Media
Process Valve/Pipe Rack
Instrumentation (i.e., Controller,
Totalizers/Flowmeters, and Gauges)
Bag Filter and Housing
Booster Pump
Subtotal
Vendor Labor
Shipping
Equipment Total
2
15ft3
Lot
1
1
1
-
-
$5,476
$6,729
$3,928
$1,192
$111
$6,571
$24,007
$4,308
$1,900
$30,215
—
-
-
—
-
-
-
58%
Engineering Cost
Subcontractor Labor
Engineering Total
-
-
$10,110
$10,110
-
20%
Installation Cost
Vendor Labor for System Start Up
Vendor Travel for System Start Up
Subcontractor Material
Installation Total
Total Capital Investment
-
-
-
-
-
$8,185
$2,154
$1,231
$11,570
$51,895
-
-
-
22%
100%
$10,110, or 20% of the total capital investment. All of the site engineering cost was incurred by a
subcontractor, TurnKey Compliance Solutions, LLC.
The installation cost included the vendor travel to the site and vendor labor to unload and install the
system, perform piping tie-ins and electrical work, and load and backwash the media. The installation
cost was $11,570, or 22% of the total capital investment.
The capital cost of $51,895 was normalized to the system's rated capacity of 20 gpm (or 28,800 gpd),
which results in $2594.75/gpm (or $1.80/gpd) of design capacity. The capital cost also was converted to
an annualized cost of $4,898/yr using a capital recovery factor (CRF) of 0.09439 based on a 7% interest
rate and a 20-yr return period. Assuming that the system operated 24 hr/day, 7 day/wk at the design
flowrate of 20 gpm to produce 28,800 gpd, the unit capital cost would be $0.47/1,000 gal. During the 19
month-long demonstration project, the system produced approximately 544,600 gal of water (see Table 4-
5), equivalent to 349,000 gal per year. At this reduced rate of usage, the unit capital cost increased to
$14.03/1,000 gal.
4.6.2 Operation and Maintenance Cost. The O&M cost includes media replacement and
disposal, chemical supply, electricity, and labor, as summarized in Table 4-11. Although media
replacement did not occur during the performance evaluation study, the media replacement cost would
represent the majority of the O&M cost. It was estimated that media replacement would cost $5,808 for
7.5 ft3 of the media, labor, and disposal. This cost was used to estimate the media replacement cost per
1,000 gal of water treated as a function of the projected media run length to the 10-|o,g/L arsenic
breakthrough (Figure 4-14).
38
-------
Table 4-11. Operation and Maintenance Cost for Woodstock Treatment System
Cost Category
Volume Processed (gal)
Value
544,600
Assumptions
From March 10, 2009 through
September 30, 2010;
equivalent to 349,000 gal per
year
Media Replacement and Disposal
Media Replacement and Disposal ($)
Adsorbsia™ GTO™ Media
Replacement and Disposal cost
($71,000 gal)
5,808
See Figure 4-14
For 7.5 ft3 in lead vessel
Chemical Usage
Chemical Cost ($71,000)
0
No chemical usage
Electricity
Electricity Cost ($71,000 gal)
—
Electrical costs assumed
negligible
Labor
Average Weekly Labor (hr)
Annual Labor Cost ($)
Labor Cost per 1,000 gal Treated ($)
Total O&M Cost/1,000 gal
1.6
1,664
4.77
See Figure 4-14
20 min/day for 5 days
At $20/hr for 52 weeks
Total O&M cost = media
replacement and disposal cost
+ $4.77
Comparison of electrical bills provided by the school prior to system installation and since startup did not
indicate any noticeable increase in power consumption by the treatment system. Therefore, electrical cost
associated with operation of the treatment system was negligible. Under normal operating conditions,
routine labor activities to operate and maintain the system consumed approximately 20 min/day or 1.6
hr/week. Assuming an hourly rate of $20/hr, the estimated labor cost would be $4.77/1,000 gal of water
treated.
39
-------
$20.00
-Media Replacement Gost
O$M cost
$15.00
,-- $10.00
s»
o
O
$5.00
$0.00
20
40 60 80 100
Media Working Capacity (BV1000)
120
140
160
Figure 4-14. Media Replacement and Total O&M Cost Curves
40
-------
5.0 REFERENCES
Battelle. 2007. Quality Assurance Project Plan for Evaluation of Arsenic Removal Technology (QAPP
ID 355-Q-6-0). Prepared under Contract No.EP-C-05-057. Task Order No. 0019, for U.S.
Environmental Protection Agency, National Risk Management Research Laboratory, Cincinnati,
OH.
Battelle. 2008. System Performance Evaluation Study Plan: U.S. EPA Demonstration of Arsenic
Removal Technology Round 2a at Clinton Christian School in Goshen, Indiana. Prepared under
Contract No. EP-C-05-057, Task Order No. 0019, for U.S. Environmental Protection Agency,
National Risk Management Research Laboratory, Cincinnati, OH.
Chen, A.S.C., L. Wang, J.L. Oxenham, and W.E. Condit. 2004. Capital Costs of Arsenic Removal
Technologies: U.S. EPA Arsenic Removal Technology Demonstration Program Round 1.
EPA/600/R-04/201. U.S. Environmental Protection Agency, National Risk Management
Research Laboratory, Cincinnati, OH.
Edwards, M., S. Patel, L. McNeill, H. Chen, M. Frey, A.D. Eaton, R.C. Antweiler, and H.E. Taylor. 1998.
"Considerations in As Analysis and Speciation." J. AWWA, 90(3): 103-113.
EPA. 2001. National Primary Drinking Water Regulations: Arsenic and Clarifications to Compliance
and New Source Contaminants Monitoring. Federal Register, 40 CFR Parts 9, 141, and 142.
EPA. 2002. Lead and Copper Monitoring and Reporting Guidance for Public Water Systems.
EPA/816/R-02/009. U.S. Environmental Protection Agency, Office of Water, Washington, D.C.
EPA. 2003. Minor Clarification of the National Primary Drinking Water Regulation for Arsenic.
Federal Register, 40 CFR Part 141.
Wang, L., W. Condit, and A.S.C. Chen. 2004. Technology Selection and System Design: U.S. EPA
Arsenic Removal Technology Demonstration Program Round 1. EPA/600/R-05/001. U.S.
Environmental Protection Agency, National Risk Management Research Laboratory, Cincinnati,
OH.
41
-------
APPENDIX A
OPERATIONAL DATA
-------
Table A-l. EPA Arsenic Demonstration Project at Woodstock, CT- Daily System Operation Log Sheet
Week
No.
1
2
3
4
5
6
7
8
Date
03/10/09
03/11/09
03/12/09
03/13/09
03/16/09
03/17/09
03/18/09
03/19/09
03/20/09
03/23/09
03/24/09
03/25/09
03/26/09
03/27/09
03/30/09
03/31/09
04/01/09
04/02/09
04/03/09
04/06/09
04/07/09
04/08/09
04/09/09
04/14/09
04/17/09
04/20/09
04/21/09
04/22/09
04/23/09
04/27/09
04/28/09
04/30/09
05/01/09
Well Pumps
Operating
time
(hr)
NA
2.1
0.1
0.0
0.0
4.3
0.3
2.9
1.1
0.0
0.0
5.4
0.1
18.2
0.0
0.1
2.5
2.2
0.0
3.8
0.5
0.0
4.1
1.4
0.1
0.1
0.1
4.7
0.1
3.8
1.2
3.2
0.1
Cumulative
Operating
Time
(hr)
NA
2.1
2.2
2.2
2.2
6.5
6.8
9.7
10.8
10.8
10.8
16.2
16.3
34.5
34.5
34.6
37.1
39.3
39.3
43.1
43.6
43.6
47.7
49.1
49.2
49.3
49.4
54.1
54.2
58.0
59.2
62.4
62.5
Vessel A
Instant
Flow
rate
(gpm)
11.1
11.2
7.9
7.9
7.9
5.8
7.9
6.4
6.5
6.5
6.5
15.7
15.8
15.7
15.7
16.1
16.1
16.2
16.3
16.3
16.0
16.0
16.4
16.2
16.2
16.4
16.4
16.4
16.4
15.6
15.6
15.7
15.7
Totalizer
XI 000
(gal)
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
21
21
37
37
38
40
42
42
45
46
46
50
51
51
51
51
56
56
60
61
64
64
Bed
Volumes
Treated
BV
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
404
404
712
712
731
769
808
808
865
885
885
962
981
981
981
981
1,077
1,077
1,154
1,173
1,231
1,231
Vessel B
Instant
Flow
rate
(gpm)
6.1
6.1
9.6
9.6
9.6
11.5
9.6
10.7
10.5
10.5
10.5
15.8
15.8
15.9
15.9
16.0
16.2
16.2
16.1
16.2
16.0
16.0
16.4
16.3
16.1
16.1
16.1
16.0
16.1
15.5
15.6
15.8
15.7
Totalizer
XI 000
(gal)
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
26
26
43
43
43
45
47
47
51
52
52
55
57
57
57
57
61
61
65
66
69
69
Bed
Volumes
Treated*3'
BV
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
500
500
827
827
827
865
904
904
981
1,000
1,000
1,058
1,096
1,096
1,096
1,096
1,173
1,173
1,250
1,269
1,327
1,327
Pressure
Inlet
Pressure
Vessel A
(psi)
8
8
5
5
5
14
8
7
7
7
7
30
30
26
26
26
25
25
25
24
25
25
21
25
24
24
24
23
23
26
29
29
29
Outlet
Pressure
Vessel A
(psi)
9
8
7
7
7
14
8
7
7
7
7
16
14
14
14
13
13
13
13
15
12
12
12
13
13
13
13
13
13
20
23
23
23
Outlet
Pressure
Vessel B
(psi)
3
3
3
2
3
2
2
4
4
4
4
4
4
6
6
6
5.5
5.5
5
5
5
5
5
5
5
5
5
5
5
7
6
6
6
Backwash
Backwash
Totalizer
(gal)
1,818
1,818
1,818
1,818
1,818
1,846
1,846
1,846
1,846
1,846
1,846
1,876
1,876
1,876
1,876
1,921
1,921
1,921
1,921
1,921
1,964
1,964
1,964
1,964
1,964
1,964
1,964
1,964
1,964
2,809
2,809
2,809
2,809
-------
Table A-l. EPA Arsenic Demonstration Project at Goshen, IN- Daily System Operation Log Sheet (Continued)
Week
No.
9
10
11
12
13
14
15
16
17
Date
05/04/09
05/05/09
05/06/09
05/07/09
05/08/09
05/11/09
05/13/09
05/14/09
05/15/09
05/18/09
05/19/09
05/21/09
05/22/09
05/26/09
05/27/09
05/28/09
05/29/09
06/01/09
06/02/09
06/03/09
06/04/09
06/05/09
06/09/09
06/10/09
06/11/09
06/15/09
06/16/09
06/17/09
06/18/09
06/19/09
06/22/09
06/23/09
06/24/09
06/25/09
06/26/09
06/29/09
07/02/09
Well Pumps
Operating
time
(hr)
4.5
0.7
3.5
0.6
0.0
5.0
4.7
3.8
0.1
0.0
2.9
6.4
0.0
0.1
4.3
0.1
0.1
4.3
0.0
3.8
0.1
1.2
4.6
4.8
0.1
4.4
0.3
2.0
2.2
0.1
3.6
0.1
0.0
0.1
0.0
0.0
0.3
Cumulative
Operating
Time
(hr)
67.0
67.7
71.2
71.8
71.8
76.8
81.5
85.3
85.4
85.4
88.3
94.7
94.7
94.8
99.1
99.2
99.3
103.6
103.6
107.4
107.5
108.7
113.3
118.1
118.2
122.6
122.9
124.9
127.1
127.2
130.8
130.9
130.9
131.0
131.0
131.0
131.3
Vessel A
Instant
Flow
rate
(gpm)
15.8
15.6
15.8
15.8
1.7
1.1
15.9
16.1
15.9
15.9
15.6
16.0
15.8
16.1
15.8
15.8
16.0
15.9
16.0
16.0
16.2
16.2
16.2
16.1
16.4
16.2
16.1
16.1
16.2
16.5
16.4
16.3
16.3
16.3
16.4
16.3
16.5
Totalizer
X1000
(gal)
68
68
72
72
72
73
77
80
80
80
83
89
89
89
92
93
93
97
97
100
100
102
106
110
110
115
115
117
119
119
122
122
122
123
123
123
123
Bed
Volumes
Treated
BV
1,308
1,308
1,385
1,385
1,385
1,404
1,481
1,538
1,538
1,538
1,596
1,712
1,712
1,712
1,769
1,788
1,788
1,865
1,865
1,923
1,923
1,962
2,038
2,115
2,115
2,212
2,212
2,250
2,288
2,288
2,346
2,346
2,346
2,365
2,365
2,365
2,365
Vessel B
Instant
Flow
rate
(gpm)
15.8
15.6
15.8
15.8
14.7
15.4
16.1
16.1
15.9
15.9
15.8
16.0
15.9
16.0
16.1
16.0
16.2
16.3
16.3
16.2
16.2
16.3
16.2
16.1
16.4
16.5
16.4
16.5
16.5
16.5
16.8
16.4
16.5
16.5
16.7
16.5
16.5
Totalizer
X1000
(gal)
74
74
77
78
78
83
87
90
91
91
93
99
99
99
101
103
103
107
107
111
111
112
117
121
121
125
126
128
130
130
133
133
133
133
133
133
134
Bed
Volumes
Treated*3'
BV
1,423
1,423
1,481
1,500
1,500
1,596
1,673
1,731
1,750
1,750
1,788
1,904
1,904
1,904
1,942
1,981
1,981
2,058
2,058
2,135
2,135
2,154
2,250
2,327
2,327
2,404
2,423
2,462
2,500
2,500
2,558
2,558
2,558
2,558
2,558
2,558
2,577
Pressure
Inlet
Pressure
Vessel A
(psi)
28
29
28
29
18
13
26
26
26
26
27
27
27
26
26
25
25
26
26
26
26
27
27
27
20
20
20
20
20
20
20
20
20
20
20
20
20
Outlet
Pressure
Vessel A
(psi)
23
23
24
22
18
14
17
18
18
16
17
17
17
17
17
17
17
18
18
18
18
18
18
18
18
13
12
13
13
12
13
13
12
12
12
12
12
Outlet
Pressure
Vessel B
(psi)
6
6
6
6
6
6
6
6
6
6
6
6
6
5
5
5
5
5
5
6
5
5
5
5
5
6
6
6
6
5
6
5
5
5
5
5
5
Backwash
Backwash
Totalizer
(gal)
2,809
3,023
3,023
3,023
3,094
3,458
4,020
4,020
4,020
4,020
4,020
4,020
4,020
4,020
4,020
4,252
4,252
4,252
4,252
4,252
4,252
4,252
4,252
4,252
5,905
5,905
5,905
5,905
5,905
5,905
5,905
5,905
5,905
5,905
5,905
5,905
5,905
-------
Table A-l. EPA Arsenic Demonstration Project at Goshen, IN- Daily System Operation Log Sheet (Continued)
Week
No.
18
19
20
21
21
22
23
24
25
26
27
28
29
30
31
Date
07/09/09
07/14/09
07/15/09
07/21/09
08/03/09
08/05/09
08/07/09
08/10/09
08/14/09
08/17/09
08/19/09
08/26/09
08/27/09
08/28/09
08/31/09
09/01/09
09/03/09
09/08/09
09/09/09
90/10/09
09/11/09
09/15/09
09/17/09
09/21/09
09/22/09
09/24/09
09/28/09
09/30/09
10/01/09
10/05/09
10/08/09
10/13/09
10/15/09
10/16/09
10/21/09
10/22/09
Well Pumps
Operating
time
(hr)
3.5
0.0
0.1
0.0
3.8
18.6
0.1
0.1
0.4
0.0
1.4
3.3
0.1
4.0
0.0
0.0
4.3
3.8
0.1
1.4
2.8
4.1
4.5
0.1
4.5
4.7
3.9
0.1
4.3
0.0
8.2
3.9
1.4
3.3
4.6
3.9
Cumulative
Operating
Time
(hr)
134.8
134.8
134.9
134.9
138.7
157.3
157.4
157.5
157.9
157.9
159.3
162.6
162.7
166.7
166.7
166.7
171.0
174.8
174.9
176.3
179.1
183.2
187.7
187.8
192.3
197.0
200.9
201.0
205.3
205.3
213.5
217.4
218.8
222.1
226.7
230.6
Vessel A
Instant
Flow
rate
(gpm)
16.3
16.2
16.2
16.4
16.3
16.5
16.2
16.4
16.4
16.5
16.5
16.1
16.2
16.5
16.3
16.5
16.4
16.2
16.2
16.0
16.3
16.2
16.2
16.2
16.3
16.4
16.4
16.5
16.3
16.5
16.5
16.5
16.2
16.4
16.5
16.4
Totalizer
X1000
(gal)
126
126
126
126
130
147
147
147
148
148
148
152
152
156
156
156
160
163
163
165
167
171
175
175
180
184
188
188
192
192
200
203
205
208
212
216
Bed
Volumes
Treated
BV
2,423
2,423
2,423
2,423
2,500
2,827
2,827
2,827
2,846
2,846
2,846
2,923
2,923
3,000
3,000
3,000
3,077
3,135
3,135
3,173
3,212
3,288
3,365
3,365
3,462
3,538
3,615
3,615
3,692
3,692
3,846
3,904
3,942
4,000
4,077
4,154
Vessel B
Instant
Flow
rate
(gpm)
16.7
16.6
16.6
16.7
16.5
16.7
16.5
16.5
16.5
16.7
16.7
16.2
16.4
16.9
16.4
16.6
16.3
16.2
16.3
16.3
16.4
16.5
16.5
16.4
16.3
16.5
16.4
16.5
16.4
16.4
16.6
16.4
16.4
16.3
16.5
16.5
Totalizer
X1000
(gal)
137
137
137
137
141
158
158
159
159
159
159
163
163
167
167
167
171
175
175
176
179
182
187
187
191
196
199
199
203
204
211
215
216
220
224
228
Bed
Volumes
Treated*3'
BV
2,635
2,635
2,635
2,635
2,712
3,038
3,038
3,058
3,058
3,058
3,058
3,135
3,135
3,212
3,212
3,212
3,288
3,365
3,365
3,385
3,442
3,500
3,596
3,596
3,673
3,769
3,827
3,827
3,904
3,923
4,058
4,135
4,154
4,231
4,308
4,385
Pressure
Inlet
Pressure
Vessel A
(psi)
20
20
19
19
19
19
19
19
19
19
20
22
20
20
19
19
20
18
19
20
20
20
21
20
20
20
21
20
20
20
21
20
21
20
20
20
Outlet
Pressure
Vessel A
(psi)
12
12
12
12
12
13
13
12
12
12
12
14
12
12
11
11
12
12
12
12
12
12
12
12
12
11
12
12
12
12
12
12
12
12
12
12
Outlet
Pressure
Vessel B
(psi)
5
5
5
5
5
5
5
5
5
5
4
4
4
5
4
5
4
4
4
4
4
4
5
5
5
5
4
4
5
11
11
11
11
11
5
5
Backwash
Backwash
Totalizer
(gal)
6,447
6,447
6,447
6,447
6,447
6,447
6,447
6,447
6,447
6,447
6,447
7,896
8,973
8,973
8,973
8,973
9,513
9,513
9,513
9,513
9,513
9,513
9,513
9,513
9,513
9,513
9,513
9,513
9,513
9,513
9,513
9,513
9,513
9,513
10,063
10,063
-------
Table A-l. EPA Arsenic Demonstration Project at Goshen, IN- Daily System Operation Log Sheet (Continued)
Week
No.
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
Date
10/26/09
10/28/09
10/29/09
11/02/09
11/04/09
11/09/09
11/13/09
11/17/09
11/19/09
11/24/09
12/01/09
12/04/09
12/07/09
12/10/09
12/14/09
12/15/09
12/17/09
12/21/09
12/22/09
12/23/09
12/30/09
01/05/10
01/07/10
01/08/10
01/12/10
01/12/10
01/19/10
01/20/10
01/27/10
01/28/10
02/02/10
02/05/10
02/09/10
02/10/10
02/18/10
Well Pumps
Operating
time
(hr)
3.7
6.0
0.0
6.2
2.9
6.0
3.8
3.1
5.1
4.1
3.6
4.9
3.7
3.9
4.4
0.1
4.5
3.9
0.0
4.2
0.1
0.4
4.1
3.6
2.8
5.5
2.5
1.9
4.7
3.7
6.0
3.6
3.9
0.0
4.6
Cumulative
Operating
Time
(hr)
234.3
240.3
240.3
246.5
249.4
255.4
259.2
262.3
267.4
271.5
275.1
280.0
283.7
287.6
292.0
292.1
296.6
300.5
300.5
304.7
304.8
305.2
309.3
312.9
315.7
321.2
323.7
325.6
330.3
334.0
340.0
343.6
347.5
347.5
352.1
Vessel A
Instant
Flow
rate
(gpm)
16.5
16.3
16.3
16.3
16.5
16.3
16.6
16.5
16.2
16.6
16.5
16.3
16.4
16.2
16.3
16.4
16.4
16.6
16.6
16.4
16.7
16.5
16.1
16.5
16.3
16.5
16.2
16.4
16.5
16.2
16.3
16.4
16.2
16.5
16.2
Totalizer
X1000
(gal)
219
225
225
231
234
239
243
247
251
255
258
263
266
270
274
274
279
282
282
286
286
287
291
294
297
302
304
306
311
314
319
323
326
326
331
Bed
Volumes
Treated
BV
4,212
4,327
4,327
4,442
4,500
4,596
4,673
4,750
4,827
4,904
4,962
5,058
5,115
5,192
5,269
5,269
5,365
5,423
5,423
5,500
5,500
5,519
5,596
5,654
5,712
5,808
5,846
5,885
5,981
6,038
6,135
6,212
6,269
6,269
6,365
Vessel B
Instant
Flow
rate
(gpm)
16.5
16.2
16.4
16.3
16.7
16.4
16.7
16.4
16.6
16.8
16.7
16.4
16.5
16.4
16.4
16.2
16.3
16.5
16.8
16.5
16.6
16.7
16.7
16.6
16.4
16.3
16.3
16.3
16.3
16.3
16.4
16.5
16.3
16.5
16.4
Totalizer
X1000
(gal)
231
237
237
243
245
251
255
258
263
267
270
275
278
282
286
286
291
294
295
299
299
299
303
306
309
314
317
319
323
326
332
335
339
339
343
Bed
Volumes
Treated*3'
BV
4,442
4,558
4,558
4,673
4,712
4,827
4,904
4,962
5,058
5,135
5,192
5,288
5,346
5,423
5,500
5,500
5,596
5,654
5,673
5,750
5,750
5,750
5,827
5,885
5,942
6,038
6,096
6,135
6,212
6,269
6,385
6,442
6,519
6,519
6,596
Pressure
Inlet
Pressure
Vessel A
(psi)
20
20
20
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
22
21
21
21
22
21
22
23
22
22
22
22
Outlet
Pressure
Vessel A
(psi)
12
12
12
12
11
12
12
12
12
13
13
11
12
12
13
13
13
13
13
13
12
13
13
13
12
12
13
13
13
13
14
14
13
13
12
Outlet
Pressure
Vessel B
(psi)
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
Backwash
Backwash
Totalizer
(gal)
10,063
10,063
10,063
10,063
10,063
10,063
10,718
10,718
10,718
10,718
10,718
10,718
10,718
11,374
11,374
11,374
11,374
11,374
11,374
11,374
11,374
11,374
11,374
11,374
11,374
11,374
11,374
11,374
11,374
12,031
12,031
12,031
12,031
12,031
12,031
-------
Table A-l. EPA Arsenic Demonstration Project at Goshen, IN- Daily System Operation Log Sheet (Continued)
Week
No.
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
Date
02/23/10
02/24/10
02/26/10
03/01/10
03/04/10
03/09/10
03/10/10
03/17/10
03/23/10
03/25/10
03/30/10
04/06/10
04/07/10
04/09/10
04/14/10
04/21/10
04/27/10
04/29/10
05/04/10
05/06/10
05/07/10
05/11/10
05/12/10
05/13/10
05/14/10
05/17/10
05/18/10
05/19/10
05/21/10
05/27/10
05/28/10
06/01/10
06/02/10
06/03/10
06/08/10
06/10/10
06/11/10
Well Pumps
Operating
time
(hr)
4.4
0.0
4.9
0.0
5.6
8.3
0.0
11.7
7.2
3.6
6.3
7.4
0.0
3.7
12.0
0.1
4.4
0.0
7.9
3.9
0.2
3.6
3.7
0.0
3.7
0.1
3.7
5.8
4.2
5.5
3.7
1.8
1.7
0.1
6.2
4.3
5.0
Cumulative
Operating
Time
(hr)
356.5
356.5
361.4
361.4
367.0
375.3
375.3
387.0
394.2
397.8
404.1
411.5
411.5
415.2
427.2
427.3
431.7
431.7
439.6
443.5
443.7
447.3
451.0
451.0
454.7
454.8
458.5
464.3
468.5
474.0
477.7
479.5
481.2
481.3
487.5
491.8
496.8
Vessel A
Instant
Flow
rate
(gpm)
16.4
16.3
16.4
16.4
16.4
16.5
16.5
16.5
16.7
16.5
16.5
16.5
16.5
16.4
16.5
16.6
16.6
16.6
16.6
16.4
16.5
16.5
16.4
16.6
16.4
16.4
16.3
16.4
16.5
16.6
16.5
16.4
16.3
16.3
16.4
16.5
16.5
Totalizer
X1000
(gal)
335
335
340
340
345
352
352
363
370
374
380
387
387
390
402
402
406
406
413
417
417
421
424
424
428
428
431
437
441
446
450
451
453
453
459
463
467
Bed
Volumes
Treated
BV
6,442
6,442
6,538
6,538
6,635
6,769
6,769
6,981
7,115
7,192
7,308
7,442
7,442
7,500
7,731
7,731
7,808
7,808
7,942
8,019
8,019
8,096
8,154
8,154
8,231
8,231
8,288
8,404
8,481
8,577
8,654
8,673
8,712
8,712
8,827
8,904
8,981
Vessel B
Instant
Flow
rate
(gpm)
16.4
16.3
16.5
16.5
16.3
16.7
16.7
16.6
16.8
16.6
16.5
16.6
16.6
16.5
16.5
16.6
16.6
16.6
16.6
16.5
16.5
16.6
16.5
16.3
16.5
16.6
16.7
16.5
16.5
16.5
16.3
16.4
16.3
16.4
16.6
16.5
16.5
Totalizer
X1000
(gal)
348
348
352
352
357
365
365
376
383
386
392
400
400
403
415
415
419
419
427
430
430
434
437
437
441
441
445
450
454
459
463
465
466
466
472
476
481
Bed
Volumes
Treated*3'
BV
6,692
6,692
6,769
6,769
6,865
7,019
7,019
7,231
7,365
7,423
7,538
7,692
7,692
7,750
7,981
7,981
8,058
8,058
8,212
8,269
8,269
8,346
8,404
8,404
8,481
8,481
8,558
8,654
8,731
8,827
8,904
8,942
8,962
8,962
9,077
9,154
9,250
Pressure
Inlet
Pressure
Vessel A
(psi)
22
21
21
21
22
22
22
22
21
21
20
20
20
20
20
20
20
19
19
19
19
20
19
19
19
18
20
20
20
19
19
18
19
19
19
20
20
Outlet
Pressure
Vessel A
(psi)
13
13
13
13
13
14
13
14
13
13
13
13
12
12
12
12
12
12
12
12
12
12
12
12
12
12
12
12
12
11
11
11
11
11
11
12
12
Outlet
Pressure
Vessel B
(psi)
5
5
5
5
5
5
5
5
5
5
5
5
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
Backwash
Backwash
Totalizer
(gal)
12,031
12,031
12,031
12,031
12,686
12,686
12,686
13,598
13,598
13,598
13,598
13,598
13598
13,598
13,598
13,598
13,598
13,598
13,598
13,598
13,598
13,598
13,598
13,598
13,598
13,598
13,598
13,598
13,598
13,598
13,598
13,598
14,254
14,254
14,254
14,913
14,913
-------
Table A-l. EPA Arsenic Demonstration Project at Goshen, IN- Daily System Operation Log Sheet (Continued)
Week
No.
65
66
67
68
70
71
72
73
74
75
76
77
78
Date
06/15/10
06/17/10
06/18/10
06/30/10
07/01/10
07/06/10
07/08/10
07/14/10
07/16/10
07/29/10
07/30/10
08/04/10
08/09/10
08/10/10
08/13/10
08/18/10
08/19/10
08/30/10
09/01/10
09/02/10
09/08/10
09/09/10
09/10/10
09/14/10
09/15/10
09/17/10
09/21/10
09/29/10
09/30/10
Well Pumps
Operating
time
(hr)
0.3
3.5
3.0
5.4
0.0
0.1
0.0
0.0
4.0
0.0
0.0
0.1
3.5
0.1
0.2
0.0
0.0
3.3
4.9
0.1
3.7
3.7
0.1
4.0
4.1
3.8
3.8
12.3
0.1
Cumulative
Operating
Time
(hr)
497.1
500.6
503.6
509.0
509.0
509.1
509.1
509.1
513.1
513.1
513.1
513.2
516.7
516.8
517.0
517.0
517.0
520.3
525.2
525.3
529.0
532.7
532.8
536.8
540.9
544.7
548.5
560.8
560.9
Vessel A
Instant
Flow
rate
(gpm)
16.4
16.4
16.1
16.4
16.5
16.2
16.1
16.2
16.2
16.3
16.3
16.3
16.3
16.5
16.5
16.3
16.4
16.2
16.4
16.3
16.1
16
16.3
16.2
16.1
16.2
16.0
16.3
16.3
Totalizer
X1000
(gal)
467
471
474
479
479
479
479
479
483
483
483
483
486
486
487
487
487
490
494
494
498
501
501
505
509
513
516
528
528
Bed
Volumes
Treated
BV
8,981
9,058
9,115
9,212
9,212
9,212
9,212
9,212
9,288
9,288
9,288
9,288
9,346
9,346
9,365
9,365
9,365
9,423
9,500
9,500
9,577
9,635
9,635
9,712
9,788
9,865
9,923
10,154
10,154
Vessel B
Instant
Flow
rate
(gpm)
16.4
16.6
16.3
16.5
16.3
16.3
16.4
16.5
16.6
16.5
16.5
16.5
16.4
16.6
16.5
16.6
16.6
16.5
16.3
16.3
16.3
16.3
16.3
16.3
16.4
16.5
16.2
16.5
16.4
Totalizer
X1000
(gal)
481
485
487
493
493
493
493
493
496
496
496
496
500
500
500
500
500
504
508
508
511
515
515
519
523
526
530
541
541
Bed
Volumes
Treated*3'
BV
9,250
9,327
9,365
9,481
9,481
9,481
9,481
9,481
9,538
9,538
9,538
9,538
9,615
9,615
9,615
9,615
9,615
9,692
9,769
9,769
9,827
9,904
9,904
9,981
10,058
10,115
10,192
10,404
10,404
Pressure
Inlet
Pressure
Vessel A
(psi)
20
20
20
19
19
18
18
18
19
17
18
18
18
18
18
18
18
18
18
18
18
18
18
18
18
19
20
18
18
Outlet
Pressure
Vessel A
(psi)
12
12
12
11
11
10
10
10
11
10
10
10
10
10
10
10
10
10
10
10
10
10
10
11
11
11
12
11
11
Outlet
Pressure
Vessel B
(psi)
4
4
4
3
3
3
3
3
3
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
3
2
2
Backwash
Backwash
Totalizer
(gal)
14,913
14,913
14,913
14,913
15,573
15,573
15,573
15,573
15,573
15,573
15,573
15,573
15,573
15,573
15,573
15,573
15,573
15,573
15,573
15,573
15,573
16,229
16,229
16,229
16,229
16,229
16,229
16,229
16,229
NA = not available
(a) BV based on 7.5 cubic feet of media in each vessel
-------
APPENDIX B
ANALYTICAL DATA
-------
Table B-l. Analytical Results from Long-Term Sampling at Woodstock, CT
Sampling Date
Sampling Location
Parameter Unit
Bed Volume
Alkalinity
(as CaCO3)
Fluoride
Sulfate
Nitrate (as N)
Phosphorus
(asP)
Silica (as SiO2)
Turbidity
pH
Temperature
DO
ORP
Total Hardness
(as CaCO3)
Ca Hardness
(as CaCO3)
Mg Hardness
(as CaCO3)
As (total)
As (soluble)
As (particulate)
As (III)
As(V)
Fe (total)
Fe (soluble)
Mn (total)
Mn (soluble)
Ti (total)
Ti (soluble)
103
mg/L
mg/L
mg/L
mg/L
Hg/L
mg/L
NTU
s.u.
°c
mg/L
mV
mg/L
mg/L
mg/L
Hg/L
Hg/L
Hg/L
Hg/L
Hg/L
Hg/L
Hg/L
Hg/L
Hg/L
Hg/L
Hg/L
03/10/09
IN
TA
-
74.8
0.4
21.7
<0.05
<10
15.4
0.1
7.1
25.0
2.8
260
85.8
77.1
8.6
27.7
27.8
<0.1
27.4
0.4
<25
<25
20.6
19.8
1.3
1.1
56.1
0.3
21.8
<0.05
<10
1.3
0.3
6.7
25.0
2.1
259
71.4
63.7
7.7
0.3
0.3
<0.1
0.4
<0.1
<25
<25
0.5
0.5
2.5
0.2
TB
-
56.1
0.3
21.4
<0.05
<10
3.2
2.3
6.6
25.0
2.1
257
74.5
67.3
7.2
0.8
0.9
<0.1
0.9
<0.1
<25
<25
0.7
0.7
6.2
0.3
03/25/09
IN
-
76.0
-
-
-
<10
14.0
0.7
NA
NA
NA
NA
-
-
-
23.5
-
-
-
-
<25
-
18.7
-
1.1
-
TA
0.4
63.3
-
-
-
<10
2.7
11.0
NA
NA
NA
NA
-
-
-
0.3
-
-
-
-
<25
-
0.4
-
28.2
-
TB
0.5
59.1
-
-
-
<10
4.4
2.2
NA
NA
NA
NA
-
-
-
0.6
-
-
-
-
<25
-
0.4
-
15.7
-
04/07/09
IN
-
81.2
0.3
22.7
<0.05
<10
14.5
0.4
NA
NA
NA
NA
72.9
67.2
5.7
22.8
23.1
<0.1
4.9
18.2
29
<25
14.8
13.9
1.1
0.9
TA
0.9
71.6
0.4
27.7
<0.05
<10
7.0
62.0
NA
NA
NA
NA
69.8
64.3
5.5
0.3
1.0
<0.1
0.3
0.8
<25
<25
1.2
0.5
75.8
1.5
TB
1.0
69.3
0.5
21
<0.05
<10
5.1
2.5
NA
NA
NA
NA
68.9
63.4
5.5
0.5
0.9
<0.1
0.3
0.6
<25
<25
0.3
0.3
4.5
0.6
04/21/09
IN
-
75.4
-
-
-
<10
15.3
0.4
NA
NA
NA
NA
-
-
-
26.3
-
-
-
-
<25
-
14.2
-
1.4
-
TA
1.0
65.7
-
-
-
<10
7.6
2.2
NA
NA
NA
NA
-
-
-
0.8
-
-
-
-
<25
-
0.2
-
26.2
-
TB
1.1
65.7
-
-
-
<10
5.6
1.3
NA
NA
NA
NA
-
-
-
0.7
-
-
-
-
<25
-
0.3
-
5.6
-
05/06/09
IN
-
77.6
0.4
21.6
<0.05
<10
16.7
0.4
NA
NA
NA
NA
96.1
90.6
5.5
26.1
27.3
<0.1
6.4
20.9
29
<25
19.2
19.0
1.4
1.3
TA
1.4
70.3
0.4
22.1
<0.05
<10
10.8
19.0
NA
NA
NA
NA
89.2
84.0
5.2
1.2
1.4
<0.1
0.6
0.8
<25
<25
0.4
0.4
33.4
0.9
TB
1.5
67.9
0.3
22.0
<0.05
<10
6.8
0.4
NA
NA
NA
NA
87.8
82.6
5.2
0.5
0.6
<0.1
0.3
0.3
<25
<25
0.3
0.3
1.4
0.6
-------
Table B-l. Analytical Results from Long-Term Sampling at Woodstock, CT (Continued)
Sampling Date
Sampling Location
Parameter Unit
Bed Volume
Alkalinity
(as CaCO3)
Fluoride
Sulfate
Nitrate (as N)
Phosphorus
(asP)
Silica (as SiO2)
Turbidity
PH
Temperature
DO
ORP
Total Hardness
(as CaCO3)
Ca Hardness
(as CaCO3)
Mg Hardness
(as CaCO3)
As (total)
As (soluble)
As (particulate)
As (III)
As(V)
Fe (total)
Fe (soluble)
Mn (total)
Mn (soluble)
Ti (total)
Ti (soluble)
103
mg/L
mg/L
mg/L
mg/L
Hg/L
mg/L
NTU
s.u.
°c
mg/L
mV
mg/L
mg/L
mg/L
Hg/L
Hg/L
Hg/L
Hg/L
ug/L
Hg/L
Hg/L
Hg/L
Hg/L
Hg/L
Hg/L
05/19/09
IN
-
68.1
-
-
-
<10
16.8
0.8
7.0
13.2
9.9
391
-
-
-
26.5
-
-
-
-
<25
-
17.9
-
1.1
-
TA
1.6
70.7
-
-
-
<10
11.9
1.5
7.4
13.3
8.6
387
-
-
-
1.6
-
-
-
-
<25
-
0.4
-
10.2
-
TB
1.8
73.2
-
-
-
<10
8.5
1.0
7.5
13.2
9.8
383
-
-
-
0.7
-
-
-
-
<25
-
0.2
-
0.8
-
06/04/09
IN
-
77.9
0.3
23.4
<0.05
<10
15.9
0.9
NA
NA
NA
NA
83.2
78.3
4.9
25.6
25.9
<0.1
4.2
21.7
49
<25
18.9
17.6
1.3
1.0
TA
1.9
75.8
0.3
22
<0.05
<10
12.2
1.0
NA
NA
NA
NA
80.3
75.6
4.8
1.7
1.8
<0.1
0.6
1.2
<25
<25
0.3
0.3
1.6
0.8
TB
2.1
69.5
0.3
22.6
<0.05
<10
8.7
0.9
NA
NA
NA
NA
78.0
72.9
5.1
0.6
0.6
<0.1
0.5
0.1
<25
<25
0.3
0.3
0.9
0.6
06/17/09
-------
Table B-l. Analytical Results from Long-Term Sampling at Woodstock, CT (Continued)
Sampling Date
Sampling Location
Parameter Unit
Bed Volume
Alkalinity
(as CaCO3)
Fluoride
Sulfate
Nitrate (as N)
Phosphorus
(asP)
Silica (as SiO2)
Turbidity
PH
Temperature
DO
ORP
Total Hardness
(as CaCO3)
Ca Hardness
(as CaCO3)
Mg Hardness
(as CaCO3)
As (total)
As (soluble)
As (particulate)
As (III)
As(V)
Fe (total)
Fe (soluble)
Mn (total)
Mn (soluble)
Ti (total)
Ti (soluble)
103
mg/L
mg/L
mg/L
mg/L
Hg/L
mg/L
NTU
s.u.
°c
mg/L
mV
mg/L
mg/L
mg/L
ug/L
ug/L
Ug/L
Ug/L
Ug/L
Ug/L
Ug/L
Ug/L
ug/L
Ug/L
Ug/L
08/05/09
IN
-
72.9
2.0
22.8
<0.05
<10
15.9
0.4
NA
NA
NA
NA
82.4
75.0
7.4
28.3
28.1
0.2
7.0
21.0
<25
<25
23.4
23.4
1.2
1.2
TA
2.8
77.5
0.4
21.3
<0.05
<10
15.6
6.6
NA
NA
NA
NA
84.4
77.0
7.3
<0.1
<0.1
<0.1
<0.1
<0.1
<25
<25
0.2
0.2
27.0
1.3
TB
3.0
72.9
2.4
23.9
<0.05
<10
11.7
1.9
NA
NA
NA
NA
81.0
73.9
7.1
<0.1
<0.1
<0.1
<0.1
<0.1
<25
<25
0.3
0.3
6.5
1.7
08/13/09*0
IN
-
70.9
-
-
-
<10
15.0
1.3
7.0
22.7
NA
309
-
-
-
23.6
-
-
-
-
60
-
12.1
-
1.1
-
TA
2.8
77.7
-
-
-
<10
15.3
0.8
7.3
22.8
NA
356
-
-
-
2.8
-
-
-
-
<25
-
0.3
-
3.3
-
TB
3.1
70.9
-
-
-
<10
11.1
1.2
7.2
22.8
NA
373
-
-
-
0.9
-
-
-
-
<25
-
0.3
-
0.8
-
08/27/09
IN
-
70.0
0.3
26.1
0.1
<10
15.8
1.4
7.2
18.9
NA
244
85.7
79.8
5.8
26.8
26.5
0.2
6.3
20.3
39
<25
16.3
16.1
1.1
1.1
TA
2.9
72.3
0.3
24.5
<0.05
<10
14.6
6.4
7.5
20.1
NA
260
79.0
73.8
5.3
3.6
3.5
<0.1
1.6
1.9
<25
<25
0.9
0.6
98.6
2.2
TB
2.9
72.3
0.4
22.2
<0.05
<10
11.8
9.3
7.3
20.8
NA
265
79.5
74.3
5.2
1.2
1.2
<0.1
1.0
0.2
<25
<25
0.7
0.8
38.3
1.7
09/10/09
IN
-
68.5
68.5
-
-
-
<10
<10
15.9
16.2
1.2
3.0
7.3
15.3
NA
294
-
-
-
24.0
23.6
-
-
-
-
67
66
-
17.8
17.8
-
1.2
1.2
-
TA
3.2
66.7
66.7
-
-
-
<10
<10
13.0
12.9
0.9
1.5
7.4
14.4
NA
402
-
-
-
1.2
1.1
-
-
-
-
<25
<25
-
0.2
0.2
-
2.1
2.5
-
TB
3.4
61.1
64.8
-
-
-
<10
<10
11.0
10.7
0.4
0.8
7.3
14.7
NA
396
-
-
-
<0.1
<0.1
-
-
-
-
<25
<25
-
0.2
0.2
-
2 2
1.2
-
-------
Table B-l. Analytical Results from Long-Term Sampling at Woodstock, CT (Continued)
Sampling Date
Sampling Location
Parameter Unit
Bed Volume
Alkalinity
(as CaCO3)
Fluoride
Sulfate
Nitrate (as N)
Phosphorus
(asP)
Silica (as SiO2)
Turbidity
PH
Temperature
DO
ORP
Total Hardness
(as CaCO3)
Ca Hardness
(as CaCO3)
Mg Hardness
(as CaCO3)
As (total)
As (soluble)
As (particulate)
As (III)
As(V)
Fe (total)
Fe (soluble)
Mn (total)
Mn (soluble)
Ti (total)
Ti (soluble)
103
mg/L
mg/L
mg/L
mg/L
Hg/L
mg/L
NTU
s.u.
°c
mg/L
mV
mg/L
mg/L
mg/L
ug/L
ug/L
Ug/L
Ug/L
Ug/L
Ug/L
Ug/L
Ug/L
ug/L
Ug/L
Ug/L
09/22/09
IN
-
68.5
0.3
22.5
<0.05
<10
14.9
0.2
6.3
14.7
NA
256
81.7
76.2
5.6
20.2
19.7
0.5
2.6
17.1
<25
<25
17.8
17.6
1.6
1.5
TA
3.5
75.9
0.3
22.9
<0.05
<10
14.0
0.4
7.2
15.0
NA
243
82.7
77.2
5.6
3.6
3.6
<0.1
1.3
2.3
<25
<25
0.1
0.1
2.0
1.5
TB
3.7
72.2
0.3
27.2
<0.05
<10
11.4
0.3
6.9
15.1
NA
71.4
80.3
74.7
5.6
0.9
0.9
<0.1
0.6
0.3
<25
<25
0.1
0.1
1.3
1.2
10/15/09
IN
-
77.6
-
-
-
<10
14.3
0.5
NA
NA
NA
NA
-
-
-
22.3
-
-
-
-
<25
-
16.9
-
1.4
-
TA
3.9
77.6
-
-
-
<10
12.9
0.5
NA
NA
NA
NA
-
-
-
2.1
-
-
-
-
<25
-
0.2
-
1.3
-
TB
4.2
70.2
-
-
-
<10
11.0
0.2
NA
NA
NA
NA
-
-
-
<0.1
-
-
-
-
<25
-
0.1
-
1.0
-
10/29/09
IN
-
70.6
0.6
21.9
<0.05
<10
16.1
2.6
6.7
13.0
NA
344
127
120
7.0
24.1
23.9
0.2
7.9
16.0
83
<25
18.6
17.8
1.7
1.4
TA
4.3
69.6
0.3
23.3
<0.05
<10
15.0
3.2
7.4
13.2
NA
326
112
105
7.0
4.2
4.3
<0.1
1.1
3.1
<25
<25
0.3
0.3
2.3
1.5
TB
4.6
71.9
0.4
23.5
<0.05
<10
12.7
3.8
7.4
13.4
NA
19.5
134
127
7.1
0.6
0.5
<0.1
0.2
0.3
<25
<25
0.2
0.4
1.4
1.2
11/10/09
IN
-
75.2
79.8
-
-
-
<10
<10
16.8
16.8
0.4
0.3
NA
NA
NA
NA
-
-
-
21.6
21.1
-
-
-
-
<25
<25
-
20.1
19.3
-
1.1
1.2
-
TA
4.6
79.8
79.8
-
-
-
<10
<10
16.1
15.9
1.1
1.2
NA
NA
NA
NA
-
-
-
5.9
5.8
-
-
-
-
<25
<25
-
<0.1
<0.1
-
2.6
2.4
-
TB
4.8
77.5
79.8
-
-
-
<10
<10
14.0
13.6
0.3
0.3
NA
NA
NA
NA
-
-
-
1.1
1.0
-
-
-
-
<25
<25
-
<0.1
<0.1
-
1.6
1.4
-
CO
-------
Table B-l. Analytical Results from Long-Term Sampling at Woodstock, CT (Continued)
Sampling Date
Sampling Location
Parameter Unit
Bed Volume
Alkalinity
(as CaCO3)
Fluoride
Sulfate
Nitrate (as N)
Phosphorus
(asP)
Silica (as SiO2)
Turbidity
PH
Temperature
DO
ORP
Total Hardness
(as CaCO3)
Ca Hardness
(as CaCO3)
Mg Hardness
(as CaCO3)
As (total)
As (soluble)
As (particulate)
As (III)
As(V)
Fe (total)
Fe (soluble)
Mn (total)
Mn (soluble)
Ti (total)
Ti (soluble)
103
mg/L
mg/L
mg/L
mg/L
Hg/L
mg/L
NTU
s.u.
°c
mg/L
mV
mg/L
mg/L
mg/L
ug/L
ug/L
Ug/L
Ug/L
Ug/L
ug/L
Ug/L
Ug/L
ug/L
Ug/L
Ug/L
12/01/09
IN
-
76.3
0.5
23.6
<0.05
<10
16.5
4.0
7.1
12.8
NA
337
81.1
75.8
5.3
24.4
24.9
<0.1
7.2
17.7
32
<25
13.7
13.8
1.2
1.1
TA
5.2
78.6
0.5
24.1
<0.05
<10
15.7
0.7
6.7
14.2
NA
323
83.7
78.2
5.5
5.3
5.3
<0.1
1.6
3.7
<25
<25
0.1
0.1
2.6
1.0
TB
5.4
74
0.4
24.4
<0.05
<10
13.5
2.4
5.6
12.8
NA
324
81.1
75.7
5.3
0.9
0.9
<0.1
0.5
0.5
<25
<25
0.1
0.1
1.0
0.9
12/15/09
IN
-
86.7
-
-
-
<10
15.9
0.3
NA
NA
NA
NA
-
-
-
22 2
-
-
-
-
35
-
15.6
-
1.4
-
TA
5.3
77.8
-
-
-
<10
15.8
1.3
NA
NA
NA
NA
-
-
-
5.7
-
-
-
-
<25
-
0.2
-
3.9
-
TB
5.5
73.3
-
-
-
<10
14.5
0.4
NA
NA
NA
NA
-
-
-
1.5
-
-
-
-
<25
-
0.2
-
1.5
-
12/30/09
IN
-
78.1
0.6
23.0
<0.05
<10
16.4
1.9
NA
NA
NA
NA
86.3
80.3
6.0
29.3
29.1
0.2
7.0
22.0
<25
<25
16.8
16.5
1.5
1.3
TA
5.5
75.7
0.4
25.4
<0.05
<10
15.4
2.6
NA
NA
NA
NA
83.7
77.8
5.9
6.0
6.1
<0.1
2.1
3.9
<25
<25
0.1
0.1
1.8
1.5
TB
5.8
82.8
0.4
25.4
<0.05
<10
13.5
2.0
NA
NA
NA
NA
84.3
78.4
6.0
1.5
1.6
<0.1
0.7
0.9
<25
<25
<0.1
<0.1
1.5
1.2
01/12/10
IN
-
74.5
-
-
-
<10
16.6
0.8
NA
NA
NA
NA
-
-
-
24.5
-
-
-
-
<25
-
17.5
-
1.2
-
TA
5.7
67.9
-
-
-
<10
15.6
0.7
NA
NA
NA
NA
-
-
-
6.0
-
-
-
-
<25
-
0.1
-
1.8
-
TB
5.9
72.3
-
-
-
<10
14.2
0.2
NA
NA
NA
NA
-
-
-
1.3
-
-
-
-
<25
-
<0.1
-
1.1
-
-------
Table B-l. Analytical Results from Long-Term Sampling at Woodstock, CT (Continued)
Sampling Date
Sampling Location
Parameter Unit
Bed Volume
Alkalinity
(as CaCO3)
Fluoride
Sulfate
Nitrate (as N)
Phosphorus
(asP)
Silica (as SiO2)
Turbidity
PH
Temperature
DO
ORP
Total Hardness
(as CaCO3)
Ca Hardness
(as CaCO3)
Mg Hardness
(as CaCO3)
As (total)
As (soluble)
As (particulate)
As (III)
As(V)
Fe (total)
Fe (soluble)
Mn (total)
Mn (soluble)
Ti (total)
Ti (soluble)
103
mg/L
mg/L
mg/L
mg/L
Hg/L
mg/L
NTU
s.u.
°c
mg/L
mV
mg/L
mg/L
mg/L
ug/L
ug/L
Ug/L
Ug/L
Ug/L
Ug/L
Ug/L
Ug/L
ug/L
Ug/L
Ug/L
01/27/10
IN
-
78.2
0.3
19.9
<0.05
<10
16.7
0.9
NA
NA
NA
NA
69.5
64.1
5.4
25.5
25.4
<0.1
5.6
19.8
53
<25
19.8
18.1
2.0
1.2
TA
6.0
80.5
0.3
20.9
<0.05
<10
15.6
0.5
NA
NA
NA
NA
67.0
61.8
5.2
6.2
6.1
<0.1
1.9
4.2
<25
<25
0.1
0.1
2.8
1.2
TB
6.2
73.6
0.3
19.4
<0.05
<10
15.1
0.4
NA
NA
NA
NA
66.9
61.7
5.2
1.6
1.6
<0.1
0.8
0.8
<25
<25
0.1
0.1
1.3
1.2
02/09/10
IN
-
82.3
82.3
-
-
-
<10
<10
15.9
16.3
1.3
1.0
NA
NA
NA
NA
-
-
-
17.9
18.5
-
-
-
-
<25
<25
-
13.0
13.0
-
1.1
1.0
-
TA
6.3
77.7
73.1
-
-
-
<10
<10
14.8
14.6
1.0
1.2
NA
NA
NA
NA
-
-
-
7.2
7.0
-
-
-
-
<25
<25
-
0.2
0.2
-
1.4
1.4
-
TB
6.5
80.0
77.7
-
-
-
<10
<10
13.5
13.7
1.5
1.1
NA
NA
NA
NA
-
-
-
1.4
1.4
-
-
-
-
<25
<25
-
0.2
0.2
-
1.5
1.4
-
02/24/10
IN
-
80.0
0.4
21.8
<0.05
<10
15.6
0.7
NA
NA
NA
NA
89.2
83.5
5.7
22.5
23.2
<0.1
4.7
18.5
<25
<25
21.5
19.0
1.9
1.0
TA
6.4
77.7
0.4
21.9
<0.05
<10
14.4
0.4
NA
NA
NA
NA
78.1
73.1
5.0
7.3
7.2
<0.1
2.5
4.7
<25
<25
0.3
0.1
1.6
0.8
TB
6.7
75.4
0.3
22.6
<0.05
<10
13.3
0.5
NA
NA
NA
NA
74.3
68.7
5.5
1.5
1.5
<0.1
0.7
0.8
<25
<25
<0.1
<0.1
1.5
0.8
03/10/10
-------
Table B-l. Analytical Results from Long-Term Sampling at Woodstock, CT (Continued)
Sampling Date
Sampling Location
Parameter Unit
Bed Volume
Alkalinity
(as CaCO3)
Fluoride
Sulfate
Nitrate (as N)
Phosphorus
(asP)
Silica (as SiO2)
Turbidity
PH
Temperature
DO
ORP
Total Hardness
(as CaCO3)
Ca Hardness
(as CaCO3)
Mg Hardness
(as CaCO3)
As (total)
As (soluble)
As (particulate)
As (III)
As(V)
Fe (total)
Fe (soluble)
Mn (total)
Mn (soluble)
Ti (total)
Ti (soluble)
103
mg/L
mg/L
mg/L
mg/L
Hg/L
mg/L
NTU
s.u.
°c
mg/L
mV
mg/L
mg/L
mg/L
Hg/L
Hg/L
Hg/L
Hg/L
ug/L
Hg/L
Hg/L
Hg/L
Hg/L
Hg/L
Hg/L
03/25/10
IN
-
74.1
0.5
18.1
<0.05
<10
15.6
0.4
NA
NA
NA
NA
77.0
71.6
5.5
23.8
23.9
<0.1
7.7
16.2
<25
<25
16.9
19.2
4.8
1.2
TA
7.2
71.9
0.3
22.0
<0.05
<10
14.7
0.8
NA
NA
NA
NA
78.4
72.7
5.7
8.6
8.7
<0.1
2.7
5.9
<25
<25
<0.1
<0.1
1.6
1.3
TB
7.4
76.3
0.5
20.8
<0.05
<10
14.1
0.4
NA
NA
NA
NA
79.0
73.5
5.5
2.2
2.2
<0.1
0.6
1.5
<25
<25
<0.1
<0.1
1.6
1.1
04/07/10
IN
-
75.6
-
-
-
<10
16.1
0.3
NA
11.9
NA
417
-
-
-
25.1
-
-
-
-
<25
-
32.0
-
1.4
-
TA
7.4
75.6
-
-
-
<10
15.7
0.2
NA
11.9
NA
418
-
-
-
9.8
-
-
-
-
<25
-
0.2
-
1.6
-
TB
7.7
80.0
-
-
-
<10
15.9
0.3
NA
-
NA
-
-
-
-
2.5
-
-
-
-
<25
-
0.1
-
1.3
-
04/21/10
IN
-
126
0.3
21.7
<0.05
<10
15.7
1.6
NA
NA
NA
NA
58.2
52.4
5.8
26.2
26.2
<0.1
4.2
22.0
47
<25
15.8
14.8
1.5
1.2
TA
7.7
80.0
0.4
24.4
<0.05
<10
15.6
1.5
NA
NA
NA
NA
73.2
67.5
5.7
10.3
10.8
<0.1
1.7
9.2
<25
<25
0.2
0.1
1.6
1.2
TB
8.0
82.3
0.4
21.2
<0.05
<10
15.6
1.9
NA
NA
NA
NA
72.9
67.3
5.6
2.7
2.8
<0.1
0.9
1.9
<25
<25
0.1
<0.01
1.4
1.3
05/06/10
IN
-
87.9
-
-
-
<10
15.6
0.9
NA
NA
NA
NA
-
-
-
27.7
-
-
-
-
<25
-
17.3
-
1.1
-
TA
8.0
80.9
-
-
-
<10
15.5
0.5
NA
NA
NA
NA
-
-
-
11.4
-
-
-
-
<25
-
0.1
-
1.3
-
TB
8.3
78.6
-
-
-
<10
15.2
0.9
NA
NA
NA
NA
-
-
-
2.8
-
-
-
-
<25
-
<0.1
-
0.9
-
Cd
-------
Table B-l. Analytical Results from Long-Term Sampling at Woodstock, CT (Continued)
Sampling Date
Sampling Location
Parameter Unit
Bed Volume
Alkalinity
(as CaCO3)
Fluoride
Sulfate
Nitrate (as N)
Phosphorus
(asP)
Silica (as SiO2)
Turbidity
PH
Temperature
DO
ORP
Total Hardness
(as CaCO3)
Ca Hardness
(as CaCO3)
Mg Hardness
(as CaCO3)
As (total)
As (soluble)
As (particulate)
As (III)
As(V)
Fe (total)
Fe (soluble)
Mn (total)
Mn (soluble)
Ti (total)
Ti (soluble)
103
mg/L
mg/L
mg/L
mg/L
Hg/L
mg/L
NTU
s.u.
°c
mg/L
mV
mg/L
mg/L
mg/L
ug/L
ug/L
Ug/L
Ug/L
Ug/L
Ug/L
Ug/L
Ug/L
ug/L
Ug/L
Ug/L
05/18/10
IN
-
76.3
0.3
20.2
<0.05
<10
15.9
1.0
NA
NA
NA
NA
84.3
78.5
5.8
23.5
22.3
1.2
3.1
19.2
<25
<25
16.8
17.7
1.2
1.1
TA
8.3
76.3
0.3
20.6
<0.05
<10
16.3
0.5
NA
NA
NA
NA
86.5
80.6
5.9
11.2
11.9
<0.1
4.1
7.8
<25
<25
0.1
0.1
1.4
1.1
TB
8.6
76.3
0.3
22.2
<0.05
<10
15.3
1.1
NA
NA
NA
NA
86.9
80.9
6.0
2.7
2.6
<0.1
0.8
1.9
<25
<25
<0.1
<0.1
1.2
1.0
06/03/10
IN
-
118
-
-
-
<10
16.1
1.4
NA
NA
NA
NA
-
-
-
27.7
-
-
-
-
189
-
21.0
-
1.8
-
TA
8.7
93.9
-
-
-
<10
17.9
1.5
NA
NA
NA
NA
-
-
-
15.6
-
-
-
-
<25
-
0.1
-
7.0
-
TB
9.0
78.2
-
-
-
<10
17.1
0.7
NA
NA
NA
NA
-
-
-
5.2
-
-
-
-
<25
-
<0.1
-
2.4
-
06/15/10
IN
-
-
-
-
-
-
-
-
NA
NA
NA
NA
-
-
-
26.0
26.8
<0.1
7.3
19.5
<25
<25
15.4
14.8
1.1
0.9
TA
9.0
-
-
-
-
-
-
-
NA
NA
NA
NA
-
-
-
16.6
18.0
<0.1
6.4
11.6
<25
<25
0.2
0.2
2.4
1.1
TB
9.3
-
-
-
-
-
-
-
NA
NA
NA
NA
-
-
-
4.4
4.6
<0.1
1.4
3.2
<25
<25
0.1
<0.1
1.3
1.0
07/14/10
IN
-
-
-
-
-
-
-
-
NA
NA
NA
NA
-
-
-
25.4
27.9
<0.1
6.2
21.7
25
<25
16.1
15.3
1.5
0.9
TA
9.2
-
-
-
-
-
-
-
NA
NA
NA
NA
-
-
-
15.1
16.6
<0.1
3.1
13.6
<25
<25
0.2
0.1
4.2
1.1
TB
9.5
-
-
-
-
-
-
-
NA
NA
NA
NA
-
-
-
4.1
4.3
<0.1
0.8
3.5
<25
<25
<0.1
<0.1
1.5
1.0
-------
Table B-l. Analytical Results from Long-Term Sampling at Woodstock, CT (Continued)
Cd
Sampling Date
Sampling Location
Parameter Unit
Bed Volume
Alkalinity
(as CaCO3)
Fluoride
Sulfate
Nitrate (as N)
Phosphorus
(asP)
Silica (as SiO2)
Turbidity
PH
Temperature
DO
ORP
Total Hardness
(as CaCO3)
Ca Hardness
(as CaCO3)
Mg Hardness
(as CaCO3)
As (total)
As (soluble)
As (particulate)
As (III)
As(V)
Fe (total)
Fe (soluble)
Mn (total)
Mn (soluble)
Ti (total)
Ti (soluble)
103
mg/L
mg/L
mg/L
mg/L
Hg/L
mg/L
NTU
s.u.
°c
mg/L
mV
mg/L
mg/L
mg/L
ug/L
ug/L
Ug/L
Ug/L
Ug/L
ug/L
Ug/L
Ug/L
ug/L
Ug/L
Ug/L
08/10/10
IN
-
-
-
-
-
-
-
-
NA
NA
NA
NA
-
-
-
25.2
26.1
<0.1
3.7
22.4
53
<25
9.8
8.6
1.2
0.9
TA
9.3
-
-
-
-
-
-
-
NA
NA
NA
NA
-
-
-
17.2
17.1
0.1
5.6
11.5
<25
<25
0.2
0.1
1.7
1.1
TB
9.6
-
-
-
-
-
-
-
NA
NA
NA
NA
-
-
-
4.3
4.2
0.1
1.3
2.9
<25
<25
<0.1
0.1
1.2
1.0
09/14/10
IN
-
-
-
-
-
-
-
-
NA
NA
NA
NA
-
-
-
27.1
25.6
1.5
10.1
15.5
31
33
17.0
15.4
1.2
1.0
TA
9.7
-
-
-
-
-
-
-
NA
NA
NA
NA
-
-
-
13.6
14.8
<0.1
3.5
11.4
<25
<25
0.1
<0.1
3.0
1.0
TB
10.0
-
-
-
-
-
-
-
NA
NA
NA
NA
-
-
-
4.3
4.4
<0.1
1.3
3.1
<25
<25
<0.1
<0.1
1.6
1.0
10/06/10
IN
-
-
-
-
-
-
-
-
NA
NA
NA
NA
-
-
-
24.7
25.8
<0.1
5.9
19.9
52
<25
17.2
17.8
0.9
0.9
TA
-10.2
-
-
-
-
-
-
-
NA
NA
NA
NA
-
-
-
15.3
15.4
<0.1
2.8
12.6
<25
<25
0.2
0.1
2.1
0.9
TB
-10.4
-
-
-
-
-
-
-
NA
NA
NA
NA
-
-
-
5.2
5.0
0.2
0.6
4.4
<25
<25
0.1
0.1
1.0
0.9
-------