-------
Table 6-3. CALCULATION OF PRIMARY COLLECTION EFFICIENCY FOR ONE
FRENCH-DESIGN SWPB PLANT - RETROFIT CASE DESCRIPTION C.
Fluoride
Generation
Severity Function Time, Generation Rate,
Cell Function Index (A) Minutes (B) . A " B Leakage
Normal Operation
Anode Effects
Anode Changing
Metal Tapping
Bath/Metal Measure-
ment .
Short Side Crust
Breaking
Long Side Crust
Breaking
Bath Addition
Alumina Addition
Other Controls
Totals
Average generation
1 X
5.5 X
6 X
2 X
1 X
4.5 X
7 X
*
1 X
1 X
2.5 X
rate = 1693X
1362 1362 X 5%
3 16 X ")
> 70*
3 48 X J
6 12 X 1
V 51
2 2 X J
10 ' . 45 X 1
1
26 -182 X f
1 1 X S 7Q%
1
20 20 X i
i
1
2 5 X J
1440 1693 X
/ 1440 =1.176 X
Secondary (2°) loading = Generation « Leakage = [0.05 (1376 X) + 0,70
(317 K)] / 1440 = 0
Primary collection
• 100% = n1J76 x
.202 X
efficiency =
- 0.202 X) /
V
[(Generation - 2° loading) / Generation]
1.176 X] ' 1001 = 83%
6-14
1
1
1
1
1
1
1
1
i
1
1
1
1
1
1
1
-------
1
W Table 6-4 shows the calculations for a typical modern American-
design CWPB plant. Compared to Table 6-2, the plant is again assumed
to be computer-controlled, the function time for anode effects being
.m reduced from 6 minutes to 3. The function time for short side crust
™ breaking is zero since there is none; and that for long side crust
,B breaking is halved since a CWPB cell has one crust break area while an
I
I
SWPB cell has two. The cell remains closed during normal operation,
crust breaking, and raw material additions. The leakage rate with the
door closed is estimated at 3 percent. The cell end covers must be
removed for metal tapping and, presumably, for bath/metal measurement
14
'• with an estimated leakage rate of 8 percent. Removal of side covers
during anode effects and anode changing increases the leakage rate to 50
«15
percent. The calculated primary collection efficiency of 95 percent
agrees with measured efficiencies at numerous CWPB plants.
p. Table 6-5 shows the calculations for the HSS plant that is retro-
Mi fit case description A in section 6.3.1. For HSS plants, the function
times for anode changing and short side crust breaking are zero since
ilh these operations are not performed. Plant A estimates that only 20 per-
cent of crust breaking is done with the doors open. This translates to
-------
Table 6-4. CALCULATION OF PRIMARY COLLECTION EFFICIENCY FOR
TYPICAL AMERICAN-DESIGN CWP3 PLANTS
Fluoride
Generation
Severity Function Time, Generation Rate,
Cell Function Index (A) Minutes (B) A • B
Normal Operation IX 1385 1385 X
•—,
Anode Effects 5.5 X 3 15 X
.
Anode Changing 6 X 8 48 X
1
1
1
1
1
Leakage
31 *
f 50% I
)
Metal Tapping 2 X 6 12 X "^ |
Bath/Metal Measure- !
ment . IX 2 2 X
Short Side Crust
1
Breaking 4.5 X 0 OX) •
Long Side Crust
Breaking 7 X 13 91 X
Bath Addition IX 1 IX
Alumina Addition IX 20 20 X
Other Controls 2.5 X 2 5 X
Totals 1440 1580 X
Average generation rate =158CX / 1440 = 1.097 X
I
y*» oo'
I
1
1
Secondary (2°) loading = Generation • Leakage = [g.Q3 (1502 X) + 0.50 —
(64. X) + 0.08 (14 X)] / 1440 - 0.054 X
1
Primary collection efficiency = [(Generation - 2° loading) / Generation] •
• 1001 = Ed. 097 X - 0.054 X) / 1.097 X] ' 100% = 95$
'6-16,
1
1
-------
1
1
«*
1
1
1
1
1
1
K"
1
'
I
1
1
1
1
1
Table 6-5. CALCULATION OF PRIMARY COLLECTION EFFICIENCY- FOR
ONE HSS PLANT - RETROFIT CASE DESCRIPTION A.
Fluoride
Generation , _
Severity Function Time, Generation Rate,
Cell Function Index
Normal Operation 1
Anode Effects 5.5
Anode Changing 6
Metal Tapping 2
Bath/Metal Measure-
ment . 1
Short Side Crust
Breaking 4.5
Long f" Door 7
Side j Closed
Crust * Door 7
Breaking , Open
Bath Addition 1
Alumina Addition 1
Other Controls 2,5
Flex Raise &
Stud Pull 1
Totals
Average generation rate
Secondary (2°) loading
(40 X)] / 1440 = 0.073
Primary collection effi
• 100% = [(1.112 X - 0.
(A) Minutes (B)
X 1386
X 0
X 0
X 2
X 2
x o
X 21
X 5
X 1
X 20
X 2
X 1
1440
= 1601 X / 1440 = 1.112 X
= Generation • Leakage - [
X
ciency = [{Generation - 2°
073 X) / 1,112 X] * 100* =
——
6-17
A " B Leakage
1386 X 5%
OX
0 X
4 X 70%
2 X 5*
OX
147 X 5%
35 X 7Q%
1 X
20 X 5%
5 X
1 X 70%
1601 X
0.05 (1561 X) + 0.70
V
loading) / Generation]
83*
-------
I
I
zero function time. Also, the fluoride generation rate for flex raising •
and stud pulls has been assumed equal to normal operation -- participate
generation rate would not be equal. Cell leakages are assumed identical J
to the French design SWPB plant since the cell has a fixed superstructure.
The calculated primary collection efficiency of 93 percent agrees well ™
with a plant estimated efficiency of 95 percent that is based on proto- •
type testing—see section 6.3.1.3.
This method of calculating primary collection efficiency is not g
very sensitive to errors in function time or duration of hood opening.
For example: at unchanged leakage for normal operation, all other •
leakages listed in Table 6-2 were increased by 10 percent - all in the M
same direction. The calculated primary collection efficiency decreased
less than 2 percent from that shown. •
The 3 percent hood leakage under normal operation (Table 6-4) was
assumed to double to 6 percent. All other operating leakages were held Ji
constant. The calculated primary collection efficiency decreased less m
than 3 percent. Another calculation on this same CWPB cell assumed that
all cell openings were 3 times as frequent as shown in Table 6-4. The •
primary collection efficiency decreased less than 2 percent from that
shown. •
The examples shown in Tables 6-2 through 6-5 apply to specific m
plants and are given to illustrate this method for estimating primary *
collection efficiency. Users of the method should - as a minimum - m
determine the function times for plants that they want to check.
6-18
I
I
-------
I
I
I Extrapolation of the above calculational procedures to VSS cells
is probably without theoretical justification since the hooding is
" radically different. However, Table 6-6 shows such an estimate for
H a typical VSS plant. The function times are the same as in Table 6-2,
except there is no anode changing. Stud blows have been ignored
§ since their severity index is unknown. It is assumed there is no
capture of emissions from all non-normal operations, and a 3 percent
leakage from the anode channel during normal operation. The calculated
_ primary collection efficiency of 80 percent is within the range of VSS
•™ cell performance of 75 to 92 percent given in section 6.1.1.3.
I
I
6.1.3 Primary Exh_aust_Rates.
Operating the cells at the proper primary exhaust rate is important
for efficiency primary collection. Too low an exhaust rate results in
«.
a low collection efficiency; too high a rate results in the primary removal
equipment being oversized and in solids being needlessly entrained from
B the cell surface into the equipment. The proper exhaust rates for a
. given cell design cannot be empirically determined because the total open
™' area of an operating cell's hood is virtually impossible to calculate. Inste?
1
I
I
• 6-19
I
I
-------
Table 6-6. ESTIMATE OF PRIMARY COLLECTION EFFICIENCY FOR
TYPICAL VSS PLANTS
Fluoride
Generation
Severity
Cell Function Index (A)
Normal Operation 1 X
Anode Effects 5.5 X
Anode Changing 6 X
Metal Tapping 2 X
Bath/Metal Measure-
ment . 1 X
Short Side Crust
Breaking 4.5 X
Long Side Crust
Breaking 7 X
9
Bath Addition 1 X
Alumina Addition 1 X
Other Controls 2.5 X
Totals
Average generation rate = 1667
Function Time, Generation Rate,
Minutes (B) . A " B
1367 " 1367 X
***
6 33 X
0 . 0 X
6 12 X ^
* *"
2 2 X
10 '• 45 X
1
26 182 X
1 IX,
20 20 X
2 5 X
1440 1667 X
X / 1440 = 1.158 X
Secondary (2°) loading = Generation * Leakage = [o,03 (1367 X)
(300 X)] / 1440 = 0.237 X
Primary collection efficiency
* 100% = [d.158 X - 0.237 X)
J
1
1
1
I
Leakage
3% *
100% •
-
1
1
1
- 100% m
I
1
1
+ 1.00
1
m
V
= [(Generation - 2° loading) / Generation] m
/ 1.158 X] ' 1001 = 80«
6-20
r^
1
1
1
-------
1
the optimum exhaust rate is usually determined from a cell prototype.
I This rate is that which will continuously maintain a sliqht neoative
•• pressure drop across all the hood openings. The pressure drop can be
measured by sensitive pi tot tubes and anemometers, or proper operation
I
can be visually checked by releasing smoke just outside the openings
7
ind observing the resultant travel path.
•| The proper exhaust rate is most difficult to maintain when the hood
door is open. Some designs maintain it through "dual range ventilation"
W as explained in section 6.1.4. Consideration should also be given to the
'• fact that the hood will inevitably deteriorate with time as the cell
deteriorates. Such deterioration can be held to a minimum, however, by
• maintaining the hoods in proper condition and makino sure that operators
exercise care in handling hood doors.
»~
EPA personnel visited seven primary aluminum plants in the Spring
M| of 1973 to develop data for this guidelines document. For these seven
plants, Table 6-7 shows primary collection efficiencies and primary ex-
• haust rates for retrofits either underway or completed. * * *
•JK The age of the plant and of the control equipment (if different) is
also given. From Table 6-7 it can be concluded that:
I 1. HSS potlines generally require higher primary exhaust rates
than CWPB potlines to achieve the same primary collection
V efficiency.
»•,
• 2. Older CWPB potlines generally require higher primary exhaust
rates than newer CWPB potlines to achieve the same primary
A collection efficiency.
I
I
I
-------
Table 6-7. PRIMARY COLLECTION EFFICIENCY VERSUS STANDARD CUBIC
FOOT PER TON OF ALUMINUM PRODUCED FOR SEVEN PRIMARY
ALUMINUM PLANTS 3,4,13,16-18
1
I
I
J
Cell
type
CWPB
CWPB
CWPB
CWPB
SWPB
VSS
HSS
HSS
Plant
code
D
F
G
G
C
E
B - south
plant
B - south
plant
HSS B - north
1 plant
HSS j A .
i
1
HSS I A
i
Year plant
started up
1939C
1952
1958'
1958
1965
1958
1941
1941
1968
1/2 - 1942f
1/2 - 1968
f
1/2 - 1942
1/2 - 1968
Before/after,
retrofit
Both
Both
Before
After
After6
Both
Before
After
Both
Before
After
Primary
collection
efficiency, f
95
98
65
d
95d
85
81
80
87
95
94
95
Sc*/tone
Al x 106»
5.05 -
4.78 *
4.11 •
4.11
3,44 |
0.67
5.06 •
7.85 1
••
6'8'I
6.57
f
7.09 "
•
FOOTNOTES:
a. Plants have the same codes here and in Section 6.3.
b. As of May 1975, retrofits were in progress at plants D, G, and B-
south, and had been completed within the previous five years'at
plants F, C, E, B-north, and A.
c. Hoods, ducts, fans, and removal equipment were installed in 1949.
d. Collection efficiency will be increased by cell design changes to
effect tighter hood sealing.
e. Plant had no primary control before retrofit.
f. Present ducts, fans, and removal equipment were installed in 1951.
6-22
I
I
I
1
I
I
-------
I
3. Even with higher exhaust rates, older HSS potlines may not
•»j readily achieve primary collection efficiencies as high as
those attainable by newer HSS potlines.
• VSS cells characteristically have lower primary exhaust rates than
either prebake or HSS cells.
IP 6.1.4 Ducting Layouts
« Practice varies among aluminum plants as to the number of cells
™ connected with a single control system. In centralized or "central"
'K installations, an entire potline of 150 or more cells may be ducted to
1
I
I
a single control system; whereas, in decentralized or "courtyard"
installations where smaller control units are usually located in
courtyards between potlines, 20 or fewer cells may be ducted to each
control system. Figures 6-4 through 6-6 illustrate schematically several
to
possible ducting layouts for PB, VSS, and HSS potlines. The manifold
I
I
ducts are generally inside the potroom and elevated above and near the
ft cells. However, some SWPB and VSS potrooms have basements, the primary
exhaust being directed downward into manifold ducts in the basement.
I
The illustrative courtyard installations are patterned after existing
installations and were selected as the bases for the cost analysis in
Section 7. With a courtyard layout, each piece of removal equipment
is a separate module. To control a larger plant, additional modules
are added. The use of courtyard layouts thus eliminates the possible
economy of scale associated with control of larger plants. Further-
more, the control costs can be presented on a cost per ton of aluminum
f
- capacity basis because the control cost per ton does not vary with plant
* 6-23
I
I
-------
20
CELLS
COURTYARD SCHEME (20 CELLS PER MANIFOLD DUCT)
, MANIFOLD DUCT
20 / i MAIN DUCT
? 9 9 9 i? 9/
D 1 I •—
_ K ii —
o .— „, _ i i i
1 J
I ' '
I
66 6 6 id
20
CELLS
/ 99
—i *-*" R
3 — _
ifi
CENTRAL SCHEME (80 CELLS PER MANIFOLD DUCT)
80
MANIFOLD DUCT 4 CELLS
f
9
\ jv
\
\ P 9
i >
i i
I I
i i
h
6 i
MAIN .
DUCT '
-N
9
A
Figure 6-4. Primary collection systems: typical ducting layouts fora
single prebake potline with 160 cells, 2 rooms {R indicates removal equipment).
6-24
I
I
I
I
I
I
I
I
I
1
1
1
I
I
I
I
I
1
I
-------
1
I
I
li
1
I
i
i
i
<
i
i
t
i
i
COURTYARD SCHEME (10 CELLS PER MANIFOLD DUCT )
10
CELLS
10
CELLS
MAIN
DUCT-
- MANIFOLD DUCT
g gg_
R
?l
i
10 10
CELLS CELLS
Figure 6-5. Primary collection systems: typical ducting layout for a
single VSS potline with 160 cells, 2 rooms (R indicates removal equipment).19
1
I
6-25
-------
COURTYARD SCHEME (10 CELLS PER MANIFOLD DUCT )
10
CELLS
10
CELLS
MAIN
DUCT
MANIFOLD DUCT
t —
f?
R
— x r
99
•*.
R
fj do
\
99
•«—
R
ftft
w
-
R
til
ij NV^/ 5 i
-
I j N
R
? 00
^ R
-
J? 9
R
ft i fld 6ti i
* R
i ft
10 10
CELLS CELLS
CENTRAL SCHEME (80 CELLS PER MANIFOLD DUCT)
80
MAIN
MANIFOLD DUCT
9
— CELLS
\ 9 9
9
DUCT \
! i
1 1
i i
A
6 6
i
Fiqure6-6. Primary collection systems; typical ducting layouts fora
single HSS potline with 160 cells, 2 rooms (R indicates removal equipment).
6-26
1
I
I
I
I
I
1
1
I
I
I
1
i
I
I
I
I
I
I
-------
I
I
I
II
1
I
I
I
I
t
i
*
i
i
i
i
i
i
i
i
size. Table 6-8 shows the gas volume relationship to aluminum production
capacity that was used in Sectiqn 7 to determine the required primary
20
control equipment size, and the sizes of the courtyard primary control
21 "
device modules used as the bases for the cost estimates. For com-
parison, Table 6-8 also shows the gas volume relationships and equipment
20 21
capacities used for secondary control. * rtf For an equivalent production
capacity, secondary removal equipment must be larger by at least an
order of magnitude.
Table 6-8. GAS VOLUMES AND CtMTROL DEVICE MODULE SIZES FOR
ECONOMIC IMPACT ANALYSIS20»21
Gas volume to primary control
device, JO6 acf/ton A?
Primary control device module size
Dry systems, acfm-
Wet systems, acfra
Gas volume,to secondary control ...
device, 105 acf/ton A1
Secondary system equipwnt capacity,
10$ acfm
Cell tvpe
Prebake
5.0
100,000
82,000
50
10
VSS
1.0
10,000
7,000
70
10
HSS
7.0
70,000
70
10
Table 6-9 gives 1975 primary collection system capital costs for
22
courtyard and central installations. With a central layout, the
ductwcrk is larger and longer, and thus more expensive.
For a specific retrofit, it is not possible to generalize as to
which approach' is more economical. Central installations are used when
the courtyard is too narrow to install the primary removal equipment.
6-27
-------
Table 6-9. CAPITAL COST COMPARISON BETWEEN COURTYARD AND CENTRAL
PRIMARY COLLECTION SYSTEMS22
(I/annual ton of AT at full capacity, new construction)
(December, 1975)
Cell hoods and
branch duct
Manifold duct
Main duct
Total
CWPB
Courtyard \ Central
8.78
15.46
7.98
32,22
8.78
35.44
3.61
47,83
HSS
Courtyard
8.78
25.45
14.09
48.32
Central
8.11
48.85
3.72
60.68
Dry scrubbing systems--like the fluidized bed and injected alumina processes-
require particularly wide courtyards, A courtyard that is 50 to 60
feet wide may be too narrow for retrofitted dry scrubbing equipment, but
wide enough for retrofitted wet scrubbing equipment. Of the nine plants that
EPA personnel visited in developing this document, the two that had courtyard-
installed dry scrubbing retrofits had courtyards that were 100 to 150 feet wide.
Other considerations, such as flexibility by provision of duct inter-
connections for continued pollution control when part of a control system
may be out of service, and the ease of cleaning deposits from the inside of
ducting, may influence the design of ducting layouts. Maximum collection
efficiencies are realized when the designs provide for continuous exhausting
of all operating cells through removal equipment even when parts of a
potline are being serviced, and when dampers are available to increase the
air flow rate from a cell that may have part of its hooding removed for
cell working or anode replacement (dual range ventilation). Duct pluggage
is a problem in HSS potlines and in poorly operated VSS potlines because
unburned hydrocarbon tars win condense in the ductwork.
6-28
I
I
I
I
I
I
I
I
1
i
i
i
i
i
i
i
i
i
-------
I
(
1
•
I
I
6.2 POTROOM AND ANODE BAKE PLANT RETROFIT REMOVAL EQUIPMENT AND
ITS PERFORMANCE
I This section discusses potroom primary and secondary removal
JL equipment, along with anode bake plant controls. Although the intent
* is to describe retrofit operation and performance, there is no known
• difference in the operation and performance of a specific piece of re-
moval equipment on a new versus a retrofitted primary aluminum plant.
If Hence, the descriptions should apply to both new and retrofit instal-
lations. The removal equipment considered falls into three classes:
• a. Dry scrubbing equipment suitable for potroom primary control.
m b. Wet .scrubbing equipment suitable for potroom primary control
and anode bake plant control.
c. Wet scrubbing equipment suitable for potroom secondary control.
Finally, potroom and anode bake plant best retrofit performance
is summarized. Evolution rates in Section 5.3 are combined with best
retrofit collection and removal efficiencies in Sections 6.1 and 6.2 to
show the overall effect on potroom total fluoride emissions. Evolution
rates in Section 5.3 are combined with best retrofit removal efficiencies
from an EPA contract study to estimate controlled anode bake plant
performance.
I 6.2.1 Potroom Primary Dry Scrubbing
Two types of dry scrubbing systems, fluidized bed and injected
It alumina, are discussed in the following subsections. These systems
• have been applied to many domestic and foreign plants. In addition,
I 6-29
I
I
-------
07
potline effluents, or about 98,5 percent on total fluoride.
1
I
I
one domestic company has been installing its own dry scrubbing
system on two CWPB and two HSS plants. One of these HSS retrofits
is retrofit case description plant A in Section 6.3.1. This dry
scrubbing process is proprietary. However, operating conditions are I
similar to those of the fluidizied bed and injected alumina processes
described below. Total fluoride removal efficiencies are projected to m
be 98-98.5 percent for the two CWPB plants and 97-98 percent for the ||
two HSS plants.
6.2.1.1 FluidizedBed -- Figure 6-7 is a flow diagram of the fluidizied I
bed dry scrubbing process. The fluidized bed dry scrubber employs a
fluidized bed of sandy alumina to contact and chemically absorb HF m
in the cell gas followed by a baghouse to trap particulates. Floury •
alumina will not fluidize and, hence, is not suited for this process
or for the injected alumina process. •
Alumina is continuously fed to the reactor bed in amounts up to
100 percent of the potline feed requirements, and the reacted bed *
material overflows and is used as cell feed. Virtually all of the cell •
gas particulate is trapped in the fluid bed -- perhaps by electrostatic
agglomeration. Fugitive particulate, primarily alumina, is stopped by a fl
bag filter mounted over the reactor. The bags are cleaned intermittently,
and the catch drops back into the fluid reactor bed.'
The vendor of the fluidized bed dry scrubber reports that, with
23-26 I
proper operating and maintenance procedures, this system is capable of 98
percent particulate and 99 percent HF removal efficiencies on prebake I
I
6^30 —
I
I
-------
I
I
I
»
1
I
I
I
i
i
I
i
i
i
i
i
i
i
i
i
i
\
1 \
Jl2
O
1
O
]L
'
0>
8
Q,
c
-D
O
Ul
"D
«
N
E
09
I
O
'T
«D
£
O!
LL
6-31
-------
I
1
1
The fluidized bed dry scrubber has been applied in foreign plants
to VSS cell gases with pilot lights or other devices used to ensure that
27
all burners are lit. The system has not been applied to HSS cell gases.
It has been installed in one domestic VSS plant with a projected re- •
moval efficiency of 98.8 percent.
Dry scrubbing processes afford much less cooling for the cell •
gas than wet scrubbing processes. Since conventional filter fabrics ||
like Dacron or Orion deteriorate above 275°F, the cell gas is usually
25 •
delivered to the fluidized bed at 275°F or below. Typical pressure m
drops are 8 to 10 inches of water across the fluidized bed and 4 to 5
3 78 I
inches of water across the baghouse. A typical power requirement is |
3 29
4.4 horsepower per thousand cubic feet per minute (hp/Mft -rain). M-
1
6.2.1.2 Injected alumina — Figure 6-8 is a flow diaqram of the
- , . j,
injected alumina dry scrubbing process. The process is similar in con- ••
cept to the fluidized bed — reaction of gaseous fluoride with sandy •
alumina followed by baghouse collection of particulate -- except that
the reaction occurs by injecting the alumina into the flowing gas stream '•
rather than by passage of the gas stream through a fluidized bed. The
reaction occurs in a matter of seconds. w
Alumina is continuously fed to the process in amounts up to 100 •
percent of the potline feed requirements. The removal efficiencies
of the injected alumina process are similar to those of the fluidized I
bed. One major difference, however, is that loss of feed to the
fluidized bed (Figure 6-7} will not result in a loss in removal |
efficiency for 8 hours thereafter because of the large alumina inventory •
in the fluidized bed. Loss of feed to the injected alumina process on
I
6-32 _
-------
I
\
I
I
I
I
I
I
I
I
(I
I
t
I
I
I
I
i
i
i
i
t
[A
g£f
UJ ml? ^
M <
J
UJ
t)
a.
<
O
o
o
Q.
O)
c
15
_a
3
i_
O
w
E
ZJ
T3
fl)
O
0)
E
2
o>
ca
o
to
g>
L
6-33
-------
I
the other hand can quickly result in a loss in removal efficiency due
to a low alumina inventory. Recycling a portion of the reacted •
alumina back into the cell gas stream provides some insurance against ^
a total feed loss. •
More than one vendor markets an injected alumina process designed •
for prebake potlines. An Alcan and a Prat-Daniel-Poelman design are
explained in Section 6.3.3. M
Cell gases from VSS potlines have higher concentrations of HF
than prebake cell gases, and they may contain unburned tar fumes. p
Here again, alumina is injected into the flowing gas stream, but from M
this point on, the Alcan process is modified slightly. Provision is
made to separate the bulk of the alumina containing adsorbed HF from I
the portion containing unburned hydrocarbons. The latter minor quantity
of alumina is calcined to remove the tar prior to being returned to the |
cells along with the main portion of the collected alumina. This system
*
does not require that all VSS cell burners be lit all the time."
Comments on temperature limitations for the fluidized bed also M
apply to the injected alumina process. A typical pressure drop is
6 inches of water across bag filters operating at an air-to-cloth ratio of I
3 27
about 6 ft /min per square foot of filter area. A typical power —
3 29 1
requirement is 2.2 hp/Mft -min, m
6.2.2 Potroom Primary and Anode Bajce Plant Viet, Scrubbing m
A potroom primary wet scrubbing scheme that gives removal efficiencies •
comparable to dry scrubbing is the combination control of spray tower
followed by wet ESP, This combination control is most frequently applied •
6-34 1
30 §
-------
I
• to VSS and HSS plants. Spray tower-wet ESP or wet ESP-spray tower con-
trols also effectively remove parti cul ate and fluoride from anode bake
• plant exhaust. Since most of the latter fluoride is gaseous, the spray
I tower — and not the ESP — controls fluoride emissions.
6.2.2.1 Spray Tower — The term spray tower is applied to gas scrubbing
£ devices in which the gas passes through an enclosure at relatively low
velocity and is contacted by water, alkaline liquor or limed water
W liquor sprayed from headers usually in counterflow with the gas. In pre-
• bake or HSS potline service, the units may range from 38,000 to 630,000
actual cubic feet per minute capacity and may spray from 1.7 to 10.0
I gallons of liquor per thousand cubic feet of gas. A typical spray tower
8 in prebake service uses water or limed water and consists of an open
I'
top redwood tower, 12 to 15 feet in diameter and 40 to 70 feet high,
& with cyclonic inlet breeching and a mist eliminator at the top. Liquor
•/ 31
. I may be sprayed down from the top or at several elevations in the tower.
• Spray towers operate at a low pressure drop, typically 1 inch
—
™
32 3
of water. Typical power reouirements are 0.4 to 0.9 hp/Mft -min for
prebake service, 1.0 to 1.3 hp/Mft -min for VSS service, and 0.3 to 0.5
3 29
hp/Mft -min for HSS service. Spray towers cool the cell gas stream
to near ambient temperatures.
'B Properly operated and maintained spray towers can achieve removal
efficiencies for potline HF in percentages ranging from the low to hioh
|i nineties. Compared with other types of wet scrubbing equipment, spray
^ towers show relatively low removal efficiency for fine participates.
• Spray towers in HSS service appear to perform less efficiently than similar
6-35
-------
I
scrubbers in prebake or VSS service. This has been sunnested to be the _
result of an interference by the hydrocarbons in the wetting of the particu- *
31 m.
lates and diffusion of HF to the spray droplets. •
Typical gaseous fluoride removal efficiencies are 95 percent
for prebake potlines, 99 percent for VSS potlines, 93 percent for HSS jj
nn -jo
potlines, and 96 percent for anode bake plant ring furnaces."'00 Typical _
particulate fluoride removal efficiencies are 80 percent for prebake ™
potlines, 75 percent for VSS potlines, and 64 percent for HSS potlines. flj
Additional information on spray towers can be found in many texts
including references 32 and 34. Two points worth mentioning are: jj
1. As with any mass transfer unit, the added increase in ,
fluoride removal efficiency drops off rapidly with each •
subsequent mass transfer stage; therefore, the attainment of •
fluoride removal efficiencies that are higher than those
previously given is most difficult. •
2. Exhaust from a redwood spray tower that is capped with a •
cone mist eliminator can be easily ducted to other control
equipment (such as an ESP) downstream of the tower. On the A
other hand, it is difficult to cap redwood towers that were not
originally designed with caps. Such capping is necessary in
4
ducting the exhaust to downstream control equipment.
I
6.2.2.2 Wet Electrostatic Freetpttator (ESP) - - The electrostatic •
precipitator is a relatively large chamber through which cell gas streams
pass at low velocity, usually 3 to 5 feet per second (ft/sec). In its I
usual form, high negative voltage corona discharge wires are suspended
4p
o-36
I
-------
I
• across the air stream and grounded collector plates form parallel
passageways for the air. The ionizing field surrounding the discharge
|/ wires ionizes part of the gas stream and imparts electric charge to most
ii
'• particles, some positive but most negative. Positively charged particles
™ migrate toward the discharge wires and negatively charged particles
•• migrate to the grounded collection plates. When collected particles
lose their charges, they tend to agglomerate and collect on the surface.
£ The removal efficiency of electrostatic precipitators for many
_ kinds of particulate is improved if the entering gas is conditioned
™ by raising its moisture content. When applied to VSS or HSS potlines,
M precipitators are usually preceded or followed by a spray tower that
II removes most gaseous fluoride. Spray towers preceding precipitators
I also condition the gas. However, for some HSS retrofits, space limita-
tions and requirements for balanced ducting layouts have necessitated
•' removal of the spray towers that would have otherwise preceded the
• ESPs. In these instances, effective gaseous fluoride control and
conditioning is achieved by a scrubbing section in the ESP inlet.
w Electrostatic precipitators fall into two categories: dry ESPs
where the collected particulates are knocked off the plates and wires
by mechanical rapping to be gathered dry in a hopper; and wet ESPs where
.<• the plates and wires are washed with falling water or electrostatically
collected mist with the particulates removed as a slurry. A dry ESP
• followed by a spray tower is not widely applied as primary equipment for
Soderberg cells since it does not prevent the emission of a blue
ft hydrocarbon haze.
» Unlike many types of control equipment, electrostatic precipita-
tors may be designed for almost any selected efficiency. By using
I
6-37
-------
I
conservative design dimensions, by controlling humidity of the incoming
gas, and by operating at high voltage, both wet and dry precipitators |
can achieve 98 to 99 percent removal of potline cell gas particu- »
35 I
lates. Total fluoride removal efficiencies for scrubber-wet ESP
controls vary from 99.2 to 99.9 percent on domestic VSS plants, and I
from 95 to 99 percent on domestic HSS plants.
Electrostatic precipitators operate at a pressure drop of less than J
1 inch of water. Typical power requirements for the wet ESP are 0.66 to 1.36
hp/Mft3~min for VSS service and 1.4 hp/Mft -min for HSS service.9 Liquor "
o 29
requirements are 5 to 10 gal/Mft of gas. Because wet ESPs are usually •
preceded by a wet scrubbing device, they operate at near ambient tempera-
tures in potline service. For anode bake plant service, a typical I
3
power requirement is 3.8 hp/Mft -min, and typical liquor requirements
are 0.3-0.4 gal/Mft3 of gas.29 1
Additional information on ESPs can be found in many texts including •
references 35,36, and 37. Three points worth mentioning are:
I
I
1. The design of the ESP should insure that the plates are not
likely to warp in service. Such warping will cause the affected
sections to short out with a resultant loss in removal efficiency.
2. The design of the ESP should insure that the plates do not I
develop dry spots and short out. One plant reports that
thi_s problem was overcome by installing internal sprays to p
3
continuously irrigate the plates. •
3. Wet ESPs in potline service are subjected to corrosive
operating conditions. For this reason, the ESP internals are I
I
6-38 1
I
-------
• usually of stainless steel construction, and the interior
steel shell walls are lined or coated. Steel ESPs are likely
I to corrode rapidly unless the composition and pH of the feed
liquor are carefully controlled,
6.2.3 Potroom Secondary Wet Scrubbing
| For practical purposes, choice of potroom secondary control is
§ limited to the spray screen scrubber. The term spray screen scrubber is
applied to wet scrubbing equipment in which the liquor is sprayed into a
I gas stream and on to screens or open mesh filters enclosed in a plenum
chamber. The assembly also usually includes a mist eliminator. Gas
J. flow may be powered by exhaust fans, or may be moved by unpowered con-
Jl vection. Figures 6-9 through 6-12 illustrate several designs of spray
" screen scrubber installations that have been used in the primary
• aluminum industry. The particulate removal mechanisms are inertia!
I impaetion on and interception by the liquid droplets or filters. The
I gaseous removal mechanism is absorption into the liquid droplets.
^ The low gas pressure drop across spray screen scrubbers and their
9 relatively low power cost recommends them for secondary, or potroom,
M scrubbing service. For secondary prebake service, typical power require-
ments are 0.3 to 1.0 hp/Mft -min and typical liquor requirements are 3 to
I 10 gal/Mft3 of gas. 29
Table 6-10 gives total fluoride secondary removal efficiencies for
» 3 13 17 42 43
spray screen scrubbers at six existing U.S. plants. ' * * *
Without primary control, all the fluoride generated at the cell is
directed to the secondary scrubbers that remove 80-85 percent of the total
I
6-39
I
I
-------
Figure 6-9. Unpowered roof spray screen.38
6-40
I
I
I
I
I
1
I
I
I
I
I
I
I
I
I
I
I
I
r
-------
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
1
I
o
o
cc
O
c.
O
ui
V Y Y Y Y
Y Y Y Y Y
Y Y Y Y Y
Y Y Y Y Y
I^AAAAAAAA/J
Y Y Y Y Y
A A A A A
A A A A A
A A A A A
23:
A A A A A
A A A A A
3
i_
o
,
ca
k«
Q.
W
O
Q.
"O
£
-------
oc
Sz
5°
CLlil
UJM
en
/ — ^ — .1
0)
.0
.d
3
t_
O
CO
o
(0
2
Q.
tn
CD
OD
o
Q.
<0
0)
3
i
6-42
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-------
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
JO
i_
o
CO
c
0)
£
o
tfi
c
o
E
•a
£
0)
o
D.
co
£
3
fi-43
-------
Cell Type3
SWPB
SWPB -
SWPB
VSS
VSS
VSS
Without Primary
Control
80
-
85.5
-
-
-
With Primary
Control
87
71b
-
75
75
80C
I
Table 6-10 PERFORMANCE OF SPRAY SCREEN SECONDARY SCRUBBERS AT I
SIX EXISTING PRIMARY ALUMINUM PLANTS "
Total Fluoride Secondary Removal Efficiency (%) •
I
I
I
I
I
aSWPB - side-worked prebake; VSS-vertical stud Soderberg. •
^Projection based upon limited testing.
cProjection based upon detailed contractor study.
I
fluoride. With primary control at SWPB and VSS plants, only 10-20 I
percent of the fluoride generated at the cell escapes the hooding and
is directed to the secondary scrubbers. At this reduced fluoride loading, I
Table 6-10 shows that the scrubbers have a removal efficiency of 75-80 m
percent, on the average. The two secondary scrubber efficiency readings
of 80 and 87 percent for the SWPB plant - first line of table - were I
taken at different times, and emission variability and sampling error
are factors to help explain why the two efficiency figures seem reversed; I
i.e., the secondary efficiency should be higher without primary •
control. However, the 87 percent reading was the result of 93 tests,
6-44 • I
I
-------
I
24 hours per test, and 3 tests per week. At this same time, 92 similar
tests showed a primary collection (hooding) efficiency of 83 percent.
I Thus, the value of 87 percent for secondary removal efficiency in the
presence of primary collection seems firmly supported. In addition,
I one alumini-m company had plans to build a new CWPB plant that included
44
• primary control and spray screen scrubber secondary control. They
anticipated achieving a 98 percent primary collection efficiency, so that
• only 2 percent of the fluoride generated at the cell would be directed to
the secondary scrubbers. At this very low loading, they projected a
| secondary removal efficiency of 75 percent. Hence, based on this plant's
_ projected performance and Table 6-10, a secondary removal efficiency of
™ 75_percent should be achievable at almost all plants adding on secondary
• control to existing primary control. Although the above mentioned plant
was not built, it was proposed to a State that has extremely strict fluoride
| emission limitations, and was based on designs by a major engineering firm
_ that is highly experienced in the design of aluminum plants and their
• emission controls. It is therefore clear that both the aluminum manu-
• facturer and the designer were confident that their proposed secondary
scrubber could achieve 75 percent total fluoride removal after primary
I control.
In practice, a scrubber designer would balance costs of the simultaneous
• addition of packing depth and wash water flow increase; both of these
• design factors work to produce increased fluoride removal efficiency.
An additional factor is, that coarser particulate sizes are the easier
I to remove by water scrubbingj addition or improvement of primary hooding
tends to preferentially remove the fine particulate from the secondary
" 6-45
I
I
-------
47
both particulates and HF than does the spray screen, the costs are
I
I
I
stream, thus shifting the size distribution to the larger sizes which
are much easier to scrub out in the secondary scrubbers.
Obviously, either increased packing depth or increased wash water
flow adds to costs. This is why secondary retrofits should not be I
required in most locations (See Section 8.3) and then only if there is
a fluoride problem and costs are balanced against fluoride reduction •
benefits. In addition, secondary scrubbing is rather energy intensive. •
Although more sophisticated scrubbing devices, such as the cross-
flow packed bed scrubber, can achieve higher removal efficiencies for I
I
I
30 to 100 percent greater and the cost effectiveness much lower when
applied to secondary treatment. It is the consensus of the industry
that, for secondary treatment in combination with primary control, the
cost differential would be more effectively invested in improved primary •
collection and removal equipment. Among the alternative secondary
scrubbers only the spray screen is considered economically feasible. |
Two points worth mentioning are: M
1. Although many plants with secondary scrubbing use once-through
water, tighter effluent regulations will require that the water •
be treated and recycled. Recycled treated water has the added
advantage of inhibiting corrosion. g
2. Although Figure 6-9 through 6-12 show secondary equipment lo- .
cated on the roof, the potroom roof at many plants may not ™
support the equipment. This may be particularly true in northern •
plants that are subjected to heavy snowfalls. Installing secondary
controls in the courtyard may be time-consuming and more expensive |
than installing them on the potroom roof. •
6-46
I
-------
I
I
I
6.2.4 Summary of Best Retrofit Performance
6.2.4.1 Potrooms — Table 6-11 shows the effects of various degrees of
I emission control on total particulate and gaseous fluoride potroom emissions,
_ For all four cell types, typical upper and lower evolution limits and
" averages are given,.each based on actual values reported in Table 5-2.
• Best retrofit primary collection efficiencies are taken from Section 6.1,
an upper and a lower 'imit being given for all cell types except CWPB.
I Best retrofit primary removal efficiencies are taken from Sections 6.2.1
_ and 6.2.2, an upper and a lower limit being given for both Soderberg cell
• types. Best retrofit secondary removal efficiency is taken from Section
• 6.2.3.
Table 6-11 shows that CWPB plants with or without secondary control
I consistently achieve lower average fluoride emissions than do other
cell types. However, CWPB emissions without secondary control are
• matched at those HSS plants that achieve the upper limits of primary
• collection and removal; also, HSS and VSS plants having such upper
limits and additional secondary control perform comparably to CWPB plants,
I but SWPB plants do not.
The emissions in Table 6-11 bracket the performance of individual
• plants, but any given emission does not necessarily correspond to that
m of any specific plant. Known and projected emissions for some actual
plants with best primary and secondary control are given in Table 7-3. In
I addition, Section 6.3.4 gives capsule retrofit descriptions for ten
actual retrofits including the after-retrofit emissions.
I
6-47
I
I
-------
Table 6-11. PERFORMANCE OF BEST RETROFIT EMISSION CONTROLS FOR PRIMARY ALUHINUfl POTROOHS
Cell
Tyge
CWPB
H
•
SWPB
it
it
El
a
vss
(I
M
II
II
It
tt
U
K
II
11
HSS
"
11
It
H
n
ti
it
u
H
With or
Average
Fluoride
Evolution,
Lb F/Ton Al
25
40
65
35
II
45
ii
55
ft
30
II
II
11
45
ti
II
«
55
n
El
tl
30
M
M
II
35
ii
11
ii
45
n
it
Without .Secondary
Primary
Collection
Efficiency, %
95
«
II
85
80
85
80
85
80
90
I*
75
fl
90
75
II
90
11
75
11
95
II
85
ME
95
II
85
If
95
11
85
M
Control
Primary
Removal
Efficiency, %
98.5
II
11
98.5
Ii
11
* n
n
99.9
98,5
99.9
98.5
99.9
98.5
99.9
98.5
99.9
98.5
99.9
98.5
99.0
96.0
99.0
96.0
99.0 '
96.0
99.0
96.0
99.0
96.0
99.0
96.0
6-48
Without Sec-
ondary Control
Average
Fluoride
Emission,
Lb F/Ton Al
1.61
2.57
4.18
5.70
7.42
7.32
9.54
8.95
11.66
3.03
3.40
7.52
7.84
4.54
5.11
11.28
11.76
5.55
6.24
13.79
14.37
1.78
2.64
4.76
5.52
2.08
3.08
5.55
6.44
2.68
3.96
7.13
8.28
With Secondary Control
Average
Secondary Fluoride
Removal Emission,
Efficiency, X Lb F/Ton Al
75 0.67
1.07
1.74
75 1.76
2.17
2.26
2.79
2,76
" 3.41
75 0.77
1.16
11 1.90
2.21
" 1.17
1.73
2. 85
3.32
" 1 .42
2.12
3.48.
" ' 4.06
75 0.66
1.52
" 1.38
2.14
0.77
1.77
" 1.61
2.50
0.99
2.27
2.07
" 3.22
/
1
1
1
1
1
1
1
1
1
1
1
|
•
|
•M
1
1
1
1
1
1
-------
I
I
I
I
I
I
I
I
I
I
I
I
6.2.4.2 Anode Bake Plants — Table 6-12 shows the average evolution,
best retrofit removal efficiency, and resultant emissions for gaseous,
particulate and total fluoride at anode bake plants. All of the
quantities are expressed as pounds of pollutant per ton of aluminum
produced, not per ton of carbon anode produced. The evolution rates
in Table 6-12 are the same as those for ring furnaces shown in Table 5-4.
Hence, they are intermediate between uncontrolled total fluoride emission
factors of 1.6 Ib/ton representing poor cleaning of the anode butts and
of 0.4 Ib/ton representing proper cleaning. The removal efficiencies
are taken from the EPA contract study.48
By comparing Table 6-12 with Table 6-11, it can be seen that the
best retrofit anode bake plant total fluoride emission is much less
than the best retrofit potroom total fluoride emissions. Total fluoride
emissions from CWPB, VSS and HSS potrooms that have secondary control,
lowest possible evolution rates, and best possible primary collection and
removal efficiencies are about the same as uncontrolled total fluoride
emissions from anode bake plants.
Table 6-12. SUMMARY OF ANODE BAKE PLANT BEST RETROFIT PERFORMANCE
1
••
.
Gaseous Fluoride
• Parti cul ate Fluoride
Total Fluoride
1
Average
Evolution,
Ib/ton Al
0.816
0.044
0.859
Removal
Efficiency,
%
95
80
94.2
Average
Emissions,
Ib/ton Al
0.041
0.009
0.050
1
| 6-49
1
-------
I
6.3 RETROFIT CASE DESCRIPTIONS |
This section contains three case descriptions of actual potline •
retrofits underway or completed in the United States as of the summer
of 1973. These case descriptions are for best retrofit controls for I
specific plants and are not necessarily representative of the industry.
The section contains descriptions, engineering information, performance |
results, and cost data for actual retrofits. Since it 1s unlikely that _
any two aluminum plants will face the same problems in retrofitting, one ™
of the objectives of this section 1s to make the States aware of many •
of the varying problems that different plants may encounter. No attempt
has been made to match these case descriptions with the control equipment I
specified in Section 6.2 or to include all types of cells and control
equipment. . "
Instead, engineering descriptions of actual retrofit emission •
controls at three primary aluminum plants are presented. Each case
includes a description of control units, ductwork, supports, fans and I
other accessories, along with practical considerations such as inter-
ferences, spatial relationships, and procurement and construction I
difficulties. Capital and operating costs are accompanied by the •
overall fluoride reductions obtained by the expenditures outlined.
The result is a description of some retrofit controls, each of which •
is practical for its plant and for its owners and each of which will
meet the performance described. For a process as complex as a primary |
aluminum plant, it is evident that a retrofit control must be tailor- _
made and should not be generalized as to costs or even as to method •
of emission control. I
6-50 •
I
-------
I
• The coverage of the three detailed retrofits in this section is
primarily based upon a trip report covering visits to several primary
• aluminum plants plus supplementary drawings, emission estimates, and
cost data subsequently provided by the plants visited. Most of the
• drawings are considered proprietary in nature and hence are not referenced
• in the case descriptions. Retrofits under construction are described
for mid-1973, but estimated construction lead times, completion dates,
• emission data, and costs have been updated.
Following the three detailed case descriptions is a subsection
| containing capsule descriptions of the three retrofits and of retrofits
M at seven other plants. The presentation includes a summary of the actual
retrofit emission reductions and costs for the ten plants.
I Although EPA conducted source tests at several retrofitted plants
in developing the data base for the standard of performance for new
| primary aluminum plants, most of the detailed and capsule descriptions
m are for plants other than the ones tested. Furthermore, descriptions
•• are not given for all the plants tested by EPA. The lettered plant
•codes in the case description are not meant to corresoond to those in
2
the background document for the new plant standards of performance.
I Whenever possible, emission data furnished by the companies have been
included with the ten case descriptions contained herein.
I
I 6-51
I
I
I
-------
6.3.1 Plant A--HSS Cells—Primary Dry Scrubbing Retrofit49
I
I
I
I
This plant has three operating HSS potlines (lines 1, 2 and 4)
with wet scrubbers presently used for primary emission control. Plans
are to retrofit the primary exhaust with two dry scrubbing systems,
one for lines 1 and 2 and one for line 4. The potlines have no I
secondary control and none is planned.
Dry scrubbing has not previously been installed for HSS primary I
control in the United States because of the inherent plugging tendency m
of the unburned hydrocarbons in the primary exhaust. Nevertheless,
tests on a company prototype have shown that the system planned for I
plant A effectively removes fluoride, particulate, and hydrocarbon
from the primary exhaust. However, the long-term effect on metal m
purity and potline operation when using the recovered materials in a •
"closed loop" system is not yet known.
Potline operation, present controls, and the planned retrofit are •
now described, first for lines 1 and 2 and then for line 4. Next the
present emissions and the emissions expected after total retrofit are |
presented. Finally, capital and annual operating costs for the total •
retrofit are estimated.
6.3.1.1 Engineering Description -Lines 1. and 2 »
6.3.1.1.1 Po 11i ne opera t i on — Lines 1 and 2 have a total capacity of |
40,000 short tons of aluminum per year (ton/year). Each line has 120 _
cells set in four rows in one potroom, 30 cells per row. The lines "
were built in 1942 and the present primary controls were installed in 1951. •
6^? • •
I
-------
I
• The cells in lines 1 and 2 are unique in that their anodes are
channel-less. The casing remains stationary, much as in a VSS cell.
• The current-carrying studs move downward with the anode by means of
• vertical slots in the casing. Anode weight limits usage of this
design to small HSS cells.
• The cells in lines 1 and E have total -enclosure hooding with hood
doors extending the full length of both sides of the cell. A mechanized
| time-feed system adds alumina to the cells with the hood doors closed.
M This system consists of four sets of vertical crust punchers and
™ alumina feeders, two sets on each side of the cell. At preset time
• intervals, the puncher makes a hole in the crust and the feeder
immediately dumps alumina into the hole. The result of this system
J is that over 90 percent of the alumina is fed with the doors closed
_ and the cell doors are only open an average of 8 minutes per cell-
• day. The cell doors do have to be opened to work both sides of each
• cell every 24 hours and to raise the flexible current connectors and
pull the bottom row of studs every 10 to 12 days. They also have to
I be opened every 24 hours to tap the molten aluminum from beneath the
cryolite bath.
(L3.1/L2 Present cojrtrojs — Two ducts, one on each end of each cell ,
| pick up the primary exhaust from the top of the cell hooding enclosure
_ and carry it to a circular manifold duct. Primary exhausts from 15
* cells (half of one row) are manifolded together. Total manifold
• exhaust is 30,000 acfm at 150°F, or 2000 acfm per cell.
6-53
•
I
I
-------
I
I
Each manifold originates in the middle of the potroom and qrows
in size from a diameter of 2 feet to a diameter of 4 feet as it proceeds •
to a fan that is outside on the end of the potroom. Each fan is driven
by a IQQ-hp motor and is upstream of a redwood spray tower. Hence, |
lines 1 and 1 have a total of 16 towers, 4 on each end of each potroom. _
Each tower is capped with an inverted cone that serves as a mist elimina- ™
tor. The capping was strictly for design purposes, and there was never •
any intention of adding on control, equipment downstream of the towers
at a later date. J
The plant has experienced emission control problems on lines 1
and 2 because of improper hood sealing and duct pluggage. The cell •
cathode shells tend to bow down in the center of the sides due to lack •
of proper structural support. This tendency makes effective sealing
of the hood doors difficult. Duct pluggage is caused by the hydrocarbons I
present in an HSS primary exhaust and by the fact that the ducts in
lines 1 and 2 are retrofitted and contain design flaws. •
6.3.1.1.3 Aqueous waste -- Water passes once through the spray towers |
and, along with the water discharged from the scrubbers on line 4, _
goes to water treatment. At the water treating facility, water from *
the scrubbers is fed to a circular, ground-level, open-top reactor I
tank about 25 feet in diameter. Lime is added as a slurry from an
elevated 14-foot by 25-foot tank. The water is continuously mixed J
and bled off to a second circular, ground-level, open-top tank for _
continued mixing and reaction but no lime addition. This second •
I
6-54 "
I
-------
I
• tank discharges to a large pond for solids settling. About three-
• fourths of the water is pumped out of the pond and recycled, and about
one-fourth is discharged to a nearby waterway. The effluent discharged
I to the waterway has a pH of 6.8 to 7.0.
Upon conversion of the potlines to dry scrubbing, no scrubbing
I water will be discharged from the plant. The existing water treating
m facility, consisting of reactor tanks and a settling pond, will remain
to handle the plant's cooling water, but there will be no lime treating.
I
I
6.3.1.1.4 Planned retrofit -- The two potrooros comprising potlines 1
and 2 are oriented in a north-south direction. The 60-foot width
of the courtyard between the potrooms will not permit courtyard
I installation of the control equipment. The planned retrofit consists
of ducting all the primary exhaust from lines 1 and 2 to 18 dry scrubbers
I located together in an area north of the potrooms, This is termed
• a central, as opposed to a courtyard, Installation.
Figure 6-13 is a layout of the retrofit for lines 1 and 2. Table
• 6-13 lists the major retrofit items. The ductwork inside the potrooms
will remain unchanged, and the existing fans and spray towers will be
• bypassed. The two circular ducts listed as item 1 in Table 6-13 will
• pick up the exhaust from the eight manifolds servicing the south halves
of both potrooms and convey it north between the potrooms. A new damper
• will be required at the end of each manifold.
6-55
I
I
I
-------
•o
m
o>
5
a.
3
O
>v
CD
0>
cc
CO
3
O)
6-56
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-------
1
1
••V
1
1
•
1
•^•i
1
1
1
Table 6-13. MAJOR RETROFIT ITEMS— PLANT A— LINES 1 AMD 2
1. Two circular elevated mild steel ducts, each 8 feet in diameter
and 700 feet long, convey primary exhaust from the south halves
of potlines 1 and 2 to the retrofit area north of the potlines.
Each duct is designed to handle 150,000 acfm of exhaust at 180°F.
2. Four fans, each driven by an 800-hp motor, designed to handle
150,000 acfm of exhaust at 180°F and 26 inches of water total
pressure drop. Each fan has two inlet dampers and one outlet
damper.
3. Two ground-level rectangular mild steel ducts, each about 200
feet long. Each duct feeds nine reactor-baghouse dry scrubbing
units, reducing in size from a height of 13 feet and a width
of 6 feet to a height of 4 feet and a width of 2 feet.
4. Eighteen mild steel reactor-baghouse dry scrubbers, set in two
rows of nine each. Each scrubber is a rectangular box, 11 feet
by 42 feet and 15 feet high. The top of each scrubber is 40
feet above the ground. Each scrubber has four compartments. Each
compartment has a gas inlet section shaped like an inverted
rectangular pyramid on the bottom and a stack on the top, or a
total of 72 stacks for the 18 scrubbers. The stacks are 15 feet
high, discharging 55 feet above the ground. Each scrubber is
designed to handle 40,000 acfm of exhaust at 180°F. The bag-
houses on each scrubber are cleaned by air pulse, requiring 90
psig compressed air. Each scrubber requires one damper in the
inlet gas line, air activated gravity alumina feed and discharge
devices, and five manually operated alumina shut-off gates.
5, Alumina unloading station containing a hopper with screen to
receive alumina from railroad dump cars. The station is located
immediately north of the potrooms.
6, Combination mild steel air slide about 400 feet long. It is
designed to simultaneously convey 50 ton/hr of fresh alumina
from the new unloading station to the new fresh alumina storage
bin and 20 ton/hr of reacted alumina from the scrubbers to the
four existing 900-ton reacted alumina storage bins that are
located at the north ends of the potrooms. Each end of the air
slide is preceded by an equivalently-sized air lift.
7, Mild steel 1000-ton fresh alumina storage bin located near the
18 dry scrubbers with high, intermediate, and low level bin
indicators. The bin is circular, 38 feet in diameter, with conical
top and bottom. Straight side height is 19 feet. The bottom of
the bin is 45 feet and the top is 95 feet above the ground.
6-57
-------
Table 6-13 (continued). MAJOR RETROFIT ITEMS—PLANT A—LINES 1 AND 2
both air slides and feeds the 20 ton/hr air slide in item 6. Total
length of each slide is about 190 feet.
I
I
8. Two 10 ton/hr mild steel air slides, each slide conveying alumina |
to nine dry scrubbers and equipped with a flow control valve and
a manually operated shut-off gate. Total length of each slide is _
about 230 feet. |
9. Two 10 ton/hr mild steel air slides, each slide conveying reacted
alumina from nine scrubbers to an activator tank that services •
I
10. Three small cylonic dust collectors for alumina transfer and
storage operations. •
11. A 30- by 4U-foot control building with a power substation.
I
I
At the north end of the potrooms, exhaust from the eight manifolds
servicing the north halves of both potrooms joins the two central ducts
as depicted in Figure 6-13. A new damper will be required at the
end of each manifold. The central ducts cross a plant roadway and lower I
into rectangular ducts 7 feet wide and 13 feet high. Each of these ducts
handles the total primary exhaust from one potroom of 300,000 acfm at 1
180°F. Each duct splits and feeds two of the four fans installed on a •
north-south axis. As shown in Figure 6-13, the two north fans move
exhaust from potline 2 to feed the nine dry scrubbers on the north side; I
while the two south fans handle potline 1 and feed the dry scrubbers
on the south side. I
The per-cell primary exhaust rate on lines 1 and 2 should increase •
from 2000 acfm at 150°F to 2500 acfm at 180°F. Hence, the primary "
collection efficiency on lines 1 and 2 should increase. The ducts I
inside the potrooms are undersized for handlinq the increased flowrate,
resulting in a high fan pressure drop requirement and a resultant |
increased power cost. However, it was considered to be more economical •
to leave the internal ducts unchanqed.
I
-------
I
I
Dry scrubbing involves reaction of gaseous fluoride with alumina
p followed by baghouse collection of fluoride and non-fluoride particulate.
_ The scrubbers are sized so that any one in a set of nine can be off-
" line at a given time and the remaining eight will still handle the 300,000
• acfm exhaust.
Considerable solids handling is involved in the retrofit. Presently
I each of the four existing 900-ton alumina storage bins has its own small
alumina unloading station. A new larger alumina unloading station
I is needed to supply fresh alumina to the dry scrubbers. The existing
• stations will be left as a backup. The percentage of the alumina cell
feed that will have to pass through the dry scrubbers is not known, but
I all of the solids handling equipment is being designed for 100 percent
feed. Alumina will normally pass once through the scrubbers before
| being fed to the cells, although it will be possible to recycle alumina
g from two of the four reacted alumina storage bins to the fresh alumina
storage bin. It will also be possible to unload fresh alumina directly
• t to the four reacted alumina storage bins. All of the air slides will
be operated by blowers.
£ The fans, the fresh alumina storage bin, and the dry scrubbers
.— will occupy an area roughly 350 feet long by 150 feet wide. To
•™ accomodate the equipment, a 25-by 100-foot engineering building had to
• be torn down, an existing well had to be covered, and some power lines
had to be moved. The existing control equipment will be left in place
• until the tie-in to the dry scrubbers is made and will then be removed.
Retrofit items that are common to lines 1 and 2 and to line 4 are:
I 1. A 25- by 100-foot bag rehabilitation buildinq.
6-59
I
-------
I
I
2. A 45- by 50-foot compressor building to supply compressed
air to the baghouse (cleaned by air pulse). I
3, A crane to remove the baghouse internals for maintenance.
The funding for the retrofits for lines 1, 2 and 4 was |
approved in July 1972. The retrofit for lines 1 and 2 just discussed _
was operating in September 1974. The retrofit for line 4 to be ™
discussed in the next section was operating in July 1974. Hence •
total installation took 26 months.
6.3.1.2 Engineering Description - Line 4
6.3.1.2.1 Pot!ihe operation — Line 4 has a capacity of 40,000 •
ton/year for a total plant capacity of 80,000 ton/year. Line 4 has •
four rows of 160 cells in two potrooms, or two 40-cell rows per pot-
room. The line was completed in 1969 with a centralized primary control I
system. The cells in line 4 are larger than those in lines 1 and 2,
and the anodes have channels. I
The cells in line 4 have total-enclosure hooding with hood doors •
exteriding the full length of both sides of the cell. A mechanized
feeding system operates with the hood doors closed. However, rather I
than operating at preset time intervals, the potline is computer-
controlled, alumina being added on a demand basis. There are four I
crust punchers and four alumina feeders, two to a side, and the puncher •
and feeder are both in one vertical mechanism. Seventy percent of the
alumina is fed with the doors closed and the cell doors are only open •
an average of 8 minutes per cell-day. As in lines 1 and 2, the cell
doors have to be opened to work the cells, pull the studs, and tap the |
aluminum.
6-60
I
1
-------
I
• 6.3.1.2.2 P res en t contrg1s — Every cell has a duct at each end that
carries the primary exhaust from the top of the cell hooding enclosure
• to a circular manifold duct. Primary exhaust from 10 cells — 25 percent
of one cell row — is manifolded together. These are a total of 16
B cell gas ^ni folds for line 4. The exhaust rate is 4400 acfm per cell
• at 180°F.
The two potrooms in line 4 are west of lines 1 and 2 and are also
• oriented in a north-south direction. The control equipment for line 4
is southwest of the line 4 potrooms and constitutes a central
• installation. Two elevated circular steel ducts running south along
• the west side of the westernmost potroom pick up the sixteen 4-foot
manifold ducts, four at a time. Each set of four pickups consists of
• one manifold from each of the four cell rows in the pot!inc. The
elevated ducts increase in size from a diameter of 6 feet to a diameter
I of 10 feet as they proceed south. The two ducts jointly handle all of
— the exhaust from the preceding manifolds.
* Near the south end of the potroom, each elevated circular duct
• divides in too, tiirns west, and lowers to a pair of ground-level fans.
The four fans are installed on a north-south axis as shown in Figure 6-14,
I Each fan is driven by a 500-hp motor and is rated at 218,000 acfm, a
_ capacity exceeding the 4400 acfm per cell exhaust rate. Flow is dampered
B during normal dual-fan operation, and if one fan is not operating, the
• exhaust rate only drops 30 to 40 percent in the respective feeder duct,
not 50 percent.
• " Exhaust from each pair of fans is recombined into a rectangular
steel duct. The two rectangular ducts proceed west, then north
I
I
to four cement blockhouse scrubbers in one building. One rectangular
6-61
-------
1000-ton
ALUMINA 8!
0 15 30 60
J I —
SCALE, ft
N
150,000 acfm
FAN WITH 700-hpN
MOTOR
EXISTING DAMPER
AND DUCT-
_
CONTROL
BUILDING
MJRY SCRUBBER
UNIT
I
^r ^ - "t
_^r j. |-»
m |
NEW DAMPER <^ O
4fi — •=
I .„ ^> •* —
iH — 1—
1 ~^^ *S —
1 „ FROM POTL
TT
Figure 6-14. Retrofit layout -- plant A -• line 4.
6-62
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-------
I
I
I
duct feeds two scrubbers from the east side of the building and the
other feeds two scrubbers from the west side.
Each of the four scrubbers has three gas inlets to a single spray
I chamber, the inlets being on the same horizontal plane. There is a bank
of nine countercurrent sprays at each inlet. The gas flows upward
• through the chamber and out the top through a single exit. Near the
• top is another bank of countercurrent sprays, with a mist eliminator
above this bank. Gas enters the scrubbers at 150 to 160°F and leaves
I at about 5°F above ambient temperature. Hence scrubbing causes a
loss of thermal stack lift.
| Rectangular wooden ducting conveys the. exhaust from the four
_ scrubbers to a common inlet on a single stack that discharges to the
™ atmosphere 500 feet above grade.
• The plant has experienced less emission control problems on line 4
than on lines 1 and 2. The cell cathode shells do not bow down in the
J center of the side, making tight hooding possible. The ducts are better
designed to handle the hydrocarbons in the primary exhaust.
• Water passes once through the cement blockhouse scrubbers and,
• along with the water discharged from the scrubbers on lines 1 and 2,
goes to water treatment. The operation of the water treating facility is
I
described in subsection 6.3.1.1.3.
I 6.3.1.2.3 Planned retrofit -- The planned retrofit consists of rerouting
the line 4 primary exhaust downstream of the fans. The primary exhaust
| will go to 18 dry scrubbers located together in an area west of the
— blockhouse scrubbers — again a central installation. The existing
" scrubbers will be bypassed.
I 6-63
I
-------
I
Figure 6-14 is a layout of the retrofit for line 4, and Table 6-14 I
lists the major retrofit items. The ducting to the f=ms will remain
unchanged. The existing fans will be modified to handle the increased I
pressure drop requirement. Primary exhaust fron all four fans is •
ducted together as shown. Hence, four fans handle both potrooms of
line 4 and feed all 18 dry scrubbers as pictured in Figure 6-14. I
The per-cell primary exhaust rate on line 4 should not increase
as a result of the retrofit. Hence, there should be no increase in |
the primary collection efficiency. «
The dry scrubbers are sized so that at least two of the 18 can be
off-line at a given time and the remaining scrubbers will still handle I
the 600,000 acfm exhaust. Originally the plant planned to manifold
the 72 stacks and convey all the scrubbed line 4 primary exhaust to the |
existing 500-foot stack. However, a private firm did a meteorological «
study that indicated that it was not necessary to go to the stack in order *
to achieve ambient air quality standards. The plan now is not to use I
the stack. One advantage in not using it is the ability to pinpoint
broken bags. The 72 stacks could be tied in to the existing stack at a |
later date. —
As in the retrofit for lines 1 and 2, considerable solids
handling is involved in the line 4 retrofit. The existing alumina I
unloading station is adequate to supply fresh alumina to the dry
scrubbers. All of the solids handling equipment is being designed |
for 100 percent feed. Although one-pass feeding to the scrubbers is •
planned, it will be possible to recycle alumina from the reacted alumina
storage bin to the fresh alumina storage bin. It will also be possible I
6-64
I
I
-------
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Table 6-14. MAJOR RETROFIT ITEMS—PLANT A—LIKE 4
1. Four fans, each modified to handle 150,000 acfm at 180°F and 20
inches of water total pressure drop and driven by a 700-hp motor.
Modification will include a new damper on the outlet of each fan.
2, Two yround-level rectangular mild steel ducts, each about 150
feet long, feeding into one rectangular duct about 200 feet long.
The latter duct feeds all 18 reaetor-baghouse dry scrubbing units,
reducing in size from a height of 13 feet to a height of 4 feet.
3. Eighteen mild steel reactor-baghouse dry scrubbersf set in two
rows of nine each. Each scrubber is a rectangular box, 11 feet
by 42 feet and 15 feet high. The top of each scrubber is 40 feet
above the ground. Each scrubber has four compartments. Each
compartment has a gas inlet section shaped like an inverted
rectangular pyramid on the bottom and a stack on the top, or a
total of 72 stacks for the 18 scrubbers. The stacks are 15 feet
high, discharging 55 feet above the ground. Each scrubber is
designed to handle 40,000 acfm of exhaust at 180°F. The baghouses
on each scrubber are cleaned by air pulse, requiring 90 psiq com-
pressed air. Each scrubber requires one damper in the inlet qas
line, air activated gravity alumina feed and discharge devices,
and five manually operated alumina shut-off gates.
4. Combination mild steel belt conveyor-air slide about 500 feet
long. The 24-inch belt conveyor is designed to handle 100 ton/hr
of fresh alumina. An existing belt conveyor transports alumina
uphill from the existing unloading station east of the line 4
potrooms to the top of the existing 2750 ton reacted alumina
storage bin. This bin is located between and above the two line 4
potrooms, centered along the length of the potrooms. The new
conveyor transports alumina from the existing conveyor up a slight
grade to the top of the new fresh alumina storage bin — item 5.
The 20-ton/hr air slide returns reacted alumina from the scrubbers
to the existing reacted alumina storage bin. The air slide is
preceded by a 20-ton/hr air lift.
5. Mild steel, 1000-ton fresh alumina storage bin located near the
18 dry scrubbers with high, intermediate, and low level bin
indicators. The bin is circular, 38 feet in diameter, with
conical top and bottom. Straight side height is 19 feet. The
bottom of the bin is 45 feet and the top is 95 feet above the
ground.
6. Two 10-ton/hr mild steel air slides, each slide conveying alumina
to nine dry scrubbers and equipped with a flow control valve and
a manually operated shut-off gate. Total length of each slide
is about 190 feet.
6-65
-------
I
Table 6-14 (continued). MAJOR RETROFIT ITEMS-PLANT A— LINE 4 |
7. Two 10-ton/hr mild steel air slides, each slide conveying reacted I
alumina from nine scrubbers to an activator tank that services
both air slides and feeds the 20-ton/hr air slide in item 4. •
Total length of each slide is about 230 feet. |
8, Four small cyclonic dust collectors for alumina transfer and _
storage operations. •
9. A 20- by 25-foot control buildinq.
to unload fresh alumina directly to the reacted alumina storage bin. All I
of the air slides will be operated by blowers.
The fresh alumina storage bins and the dry scrubbers will occupy •
an area roughly 220 feet long and 110 feet wide. Nothing had to be •
torn down or moved to accomodate the equipment. The existino cement block-
house scrubbers, located east of the dry scrubbers, will continue to I
operate until the tie-in to the dry scrubbers is made and will not be torn
down afterwards. |
The fate of the existing waste treating facility is explained in •
subsection 6.3.1 .1.3.
Retrofit items common to line 4 and to line 1 and 2, and estimated I
installation times are given at the end of subsection 6.3.1.1.4.
6.3.1.3 Emissions Before and After Retrofit
Tables 6-15 and 6-16 present data on before and after £
retrofit emissions provided by the operating company in mid- _
1973 and re-submitted in October 1974. Table 6-15 shows the •
quantities of fluoride and parti cul ate generated at the cells, the •
t
6-66 |
I
-------
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Table 6-15. BEFORE RETROFIT EMISSIONS—PLANT A—LINES 1,2, AND 4
(Ib/ton AT)
Fluoride (as F~)
Gaseous
Particulate
Total
Particulate
Dry solids
Condensibles
Total
. Generation,
19.0
1L4L
30.0
114.3
12.8
127.1
Emissions
Primary
5.0
iL5_
7.5
20.1
9.0
29.7
. Secondary
0.6
1.2
1.8
9.5
0.9.
10.4
Total
5.6
3.7
9.3
29.6
9.9
39.5
Removal
13.4
7.3 '
20.7
84.7
2.9
87.6
Table 6-16. AFTER RETROFIT EMISSION ESTIMATES—PLANT A—LINES 1,2, AND 4
(Ib/ton A!)
Fluoride (as F")
Gaseous
Particulate
Total
Parti cul ate
Dry solids
Condensibles
Total
Generation
19.0
11.0
30.0
114.3
-12.8
Emissions
Primary
0.4-0.6
0.2-0.4
0.6-1.0
2.0-3.0
1.5-2.5
127.1 . | 3.5-5.5
Secondary
0.5
1.1
1.6
6.0
0.5
• 6.5 •
Total
0.9-1.1
1.3-1.5
2.2-2.6
8.0-9.0
2.0-3:0
;io. 0-12,0
Recove rv
18.0
9.6
27.6
105.8
in. 3
116.1
6-67
-------
I
quantities emitted from the present primary control equioment and the •
secondary building roof monitors, and the quantities removed by the •
primary control equipment that eventually become solid and liquid
waste. All of the quantities are expressed as pounds of pollutant per I
ton of aluminum produced (Ib/ton Al). The fluoride values are expressed
as fluoride ion. Dry solid particulate includes particulate fluoride as |
well as alumina and carbon. Condensibles could be alternately labeled _
"C6H6 Solubles" or "Hydrocarbon Tar Fog and Gas." •
The generation and emission levels in Table 6-15 correspond to a •
primary collection efficiency of 94 percent, a primary removal efficiency
of 73 percent, and an overall control efficiency of 69 percent on total |
fluoride for plant A. These levels also correspond to a primary collection —
efficiency of 92 percent, a primary removal efficiency of 75 percent, and *
an overall control efficiency of 69 percent on total particulate. Overall I
control efficiency on hydrocarbon condensibles is only 23 percent.
Table 6-16 shows the quantities of fluoride and particulate that are J
expected to be emitted after the dry scrubbing retrofit is installed by _
late 1974, and the quantities recovered and recycled to the cells. The *
emissions are preliminary estimates based on prototype tests mentioned in •
the introduction of this case description. Although the retrofit does not
include secondary control, secondary emissions should be reduced through •
increased primary collection. This improved collection should be brought
about by the increase in the per-cell primary exhaust rate on lines 1 and 2, •
mentioned under subsection 6.3.1.1.4, and by better hood sealing and •
improved operating practices throughout the plant.
I
•6-68
I
I
-------
I
The emission levels in Tables 6-15 and 6-16 are averages.
I However, the preliminary nature of the data upon which the
primary emissions in Table 6-16 are based necessitates stating
• these emissions in ranges.
• The generation and emission levels in Table 6-16 correspond to a
primary collection efficiency of 95 percent, an average primary removal
I efficiency of 97 percent, and an average overall control efficiency of
92 percent on total fluoride for plant A. They also correspond to a
m primary collection efficiency of 95 percent, an average primary removal
• efficiency of 96 percent, and an average overall control efficency of
91 percent on total parti cul ate. Average overall control efficiencyon
I hydrocarbon condensibles should increase to 80 percent.
The 105.8 Ib/ton Al of dry solids that are expected to be recovered
I after retrofit includes 52.4 Ib/ton Al of alumina. This alumina and the
^ 27.6 Ib/ton Al of fluoride are considered to be the only valuable
" materials recovered.
•• Three conclusions that can be drawn from Table 6-16 are;
1. The expected total fluoride emissions for this existing plant
|< are somewhat higher than the EPA standard of performance for
_ new primary aluminum plants of 2.0 Ib/ton Al.
• 2. After retrofit this plant should be well within the existing
• State emission standard of 15 pounds of soT1d_ parti cul ate
per ton of aluminum produced. The retrofit is being installed
I
I
I
6-69
-------
I
I
to bring the plant into compliance with the State partieu-
late standard. The State has no fluoride emission standard, I
According to company personnel, plant emissions have not
resulted in any fluoride vegetation damage. The plant is |
located in an industrial region. •
3, The retrofit should simultaneously bring about low emission ™
levels of fluoride, solid particulate, and hydrocarbon. •
The generation and emission levels in Tables 6-15 and 6-16 show
that the ratio of total particulate to total fluoride at plant A is |
4.24 for generation, 4.25 for total (primary and secondary) emissions —
before retrofit, and 4.58 for average total emissions after retrofit. •
I
6.3.1.4 Capital and Annual Operating CostsofRetrofit
6.3.1.4.1 Capital costs — Table 6-17 presents actual capital costs |
and estimates for the total retrofit furnished by the company in «
December 1974 and broken down into the major retrofit items. Al-
though the installation is complete, not all of the final figures are I
known. Assuming an annual aluminum capacity of 80,000 tons, $11,313,000
is equivalent to a capital cost of $141 per annual capacity ton. I
The largest cost item in Table 6-17 is ductwork. Of the $1,819,000, •
$1,600,000 is estimated for the collector ducts on lines 1 and 2.
Equipment purchase costs for fans, reactors, and baghouses amount I
to $200,000, $500,000, and $987,000 respectively. Costs of the
seven small cyclonic dust collectors listed in Tables 6-13 and 1
I
I
6-70
I
-------
1
1
1
1
•B
1
1
1
1
1
1
1
1
1
1
1
Table 6-17. RETROFIT CAPITAL CQST:ESTIMATE-rpLANT :A— LINES.! ,2, AMfl 4
Direct--Capital
Ducts
Fans
Reactors
Baghouses
Alumina transfer
Alumina storage
Electrical
Instrumentation and sampling
Bag maintenance
Compressed air
Capital spares
Subtotal
Di rect — NonCajJi tal
Preoperating expense
Equipment testing
Subtotal
Indirect—Capital
Engineering
Contingency
Escalation
Subtotal
Project total
$1,819,000
341 ,000
1,775,000
1,269,000
1,196,000
415,000
975,000
320,000
670,000
458,000
60,000
$9,298,000
$ 150,000
35,000
$ 185,000
$1,830,000
-
-
$1,830,000
$11,313,000
* 6-71
I
-------
I
6-14 are covered under alumina transfer and storage in Table 6-17. |
Site preparation costs total $367,000 and are covered under ducts, fans,
reactors, and alumina storage in Table 6-17; the costs include •
building and equipment demolition both before and after retrofitting. •
Of the $320,000 for instrumentation and sampling, the control bull diners
are estimated at $68,000, instrumentation at $220,000, and sampling at |
$30,000. All of the sampling cost is for gas sampling; part of it for
sample ports and part for sampling equipment. The $670,000 for bag •
maintenance covers the cost of the aforementioned (see subsection •
6.3.1.1.4) bag rehabilitation building, a mobile crane and associated
equipment. The $458,000 for compressed air covers the cost of the I
aforementioned compressor building and associated equipment. Of the
$1,830,000 for engineering, engineering performed by the operating •
company is estimated at $200,000; plant engineermo at $60,000; con- '•
struction management at $200,000; and contract engineering, fee, and
procurement at $1,160,000 for a total actual engineering cost of I
$1,620,000. There are no contingency and escalation costs since total
installation is complete. I
All of the ducts, reactor-baghouses, bins, and conveyors are mild •
steel construction. This is a cost advantage that a dry control retrofit
enjoys over a wet ESP retrofit, as the latter normally requires 316 I
stainless steel construction.
The book value of all assets to be retired as a result of the •
retrofit was $801,214 as of December 31, 1971. Approximately •
50 percent of these assets will be demolished or abandoned in place.
I
6-72 • I
I
-------
I
• The remaining assets, including fans, motors, pumps, and steel
• ductwork, may have some salvage value if they can be sold. Because
of the uncertainty of the disposition and recoverable value of
I these assets, tfieir salvage value has been ignored by the company
in its capital cost estimate.
" The company has done considerable development work at this plant
• and at other locations. These development costs are not reflected
in Table 6-17.
|
6_.3.T_.4.2_ Annua1 .operating costs -- Table 6-18 is a company estimate
I of what the gross and net annual.operating costs of the total retrofit
should be during the first year of operation. Net annual, operating cost
| for the before-retrofit control is estimated to be $292,800.
^ Assuming a daily aluminum production of 205 tons equivalent to an
™ annual production of 74,825 tons, the gross annual operating cost in
'• Table 6-18 of $741,450 amounts to $9.91 per ton. Making the same
assumptions, the net annual operating cost of -$65,128 amounts to
| -$0.87 per ton. The negative net annual operating cost does not
m represent profit because capital-related charges are not'included.
™ Most of the items under gross annual operating cost in Table 6-18
• are self-explanatory. The electric power rate is equivalent to 2.99
mills per kilowatt-hour, which is very low for the United States. Part
jj of the power requirement is for producing compressed air for bag clean-
• 1ns-
I
I 6-73
I
-------
Table 6-18. RETROFIT ANNUAL OPERATING COST ESTIMATE—PLANT
LINES 1, 2, AND 4
Gross Annual Operating Cost
Based on 1975 (first year of operation) cost levels.
Operating Supplies
Bags: 28,080 installed + 5% damaged = 29,484 replaced
once per 18 months or 19,656 per year
19,656 replaced 9 5.50 each =
Other supplies (15% of operating labor)
Operating Labor
Bag change-out @ 3 bags/manhour @ $8.55/mannour
19,656 X $8.55
3
Operating and control: 1 operator/shift = 8,760
manhours at $10.31/manhour
Fan and duct cleaning: 7,500 manhours § $7.60/manhour
Maintenance
Labor: 11,484 manhours @ $12.47/manhours
Material: 57% of labor
Outside contract: Painting @ $140,000/5 years
Power
49,056 megawatt-hours @ $2.99
Total Gross Annual Operating Cost
Value of Recovered Material
Alumina Recovered: 1960 ton/year @ $96.80/ton
Aluminum Fluoride Recovered: 1690 ton/year @ $365/ton
Total Value of Recovered Material
Net Annual Operating Cost
6-74
A—
$108,108
30,500
$138,608
$ 56,020
90,316
57,000
$203,336
$143,205
81,627
28,000
$252,832
$146,677
$741 ,450
$189,728
616»850
$806,578
-$ 65,128
1
1
1
1
1
1*
'
1
i
I
•
-------
I
I
As mentioned in subsection 6.3.1.3, only the recovered alumina
•; and fluoride are considered to be valuable materials. The amount of
recovered alumina is estimated from a recovery rate of 52.4 Ib/ton Al
I and an annual production of 74,825 tons. The amount of recovered
aluminum fluoride is estimated from a recovery rate of 27.6 Ib/ton Al
ii (Table 6-16) equivalent to 45.2 pounds of aluminum fluoride containing
• 61.1 percent fluoride, and an annual production of 74,825 tons. The
latter estimate assumes that both gaseous and particulate fluoride
I ion will be returned to the cells as aluminum fluoride. An alumina
cost of $96.80 per ton is equivalent to 4.8 cents per pound. A cost
I of $365 per ton for aluminum fluoride containing 61.1 percent fluoride
_ is equivalent to 29.9 cents per pound of fluoride. By comparison, an
EPA contract study gives 1971 recovered alumina and fluoride values
•
I
I
of 3.2 and 25 cents per pound, respectively. The value of recovered
materials has increased due to rather significant increases in the
I value of alumina which reflects the recent changes in bauxite prices
_ around the world, as well as some increase in the value of fluorides.
H Het annual cost includes the above operating costs along with
• capital -related charges. Such charges include depreciation, interest,
administrative overhead, property taxes, and insurance. These were
• not furnished by the company and, hence, are not included in Table 6-18.
Based on a "capital recovery" factor of 11.683 percent, an "administrative
• overhead" factor of 2 percent, and a "property taxes and insurance"
• factor of 2 percent, capital related charges would amount to 15.683
percent of capital cost for this retrofit. The "capital recovery"
• factor covers depreciation and interest and is based on a 15-year equip-
6-75
-------
I
ment life and 8 percent interest. Capital related charges for
this retrofit thus amount to 15.683 percent of $11,313,000 — or I
$1,774,218. Adding these charges to Table 6-18 would result in a n**oss
annual cost of $2,515,668 and a net annual cost of $1,709,090. I
I
6.3.2 Plant B—HSS Cells—Primary Wet ESP Retrofit51 |
This plant's reduction facilities include two HSS plants — a
south plant and a north plant. Primary control presently consists |
of wet scrubbers, but plans are to retrofit the primary exhaust with •
31 wet electrostatic precipitators, 10 for the south plant and 21 for
the north plant. The plants have no secondary control and none is I
planned.
Wet ESPs are being installed because: I
1. The presence of a cryolite recovery plant to handle the «
scrubber-ESP effluents makes dry scrubbing less attractive. *
2. Aluminum product purity at plant B is high, among the •
highest in the nation. According to plant personnel, dry
scrubbing with attendant recycle would lower this purity. g
3. High energy scrubbers would require excessive power inputs _
to achieve the desired control. ™
4« The cross flow packed bed scrubber with TelleretteR packina I
applied to an HSS potline will plug after only 30 minutes of
operation. |
5. Although the floating bed scrubber does not plug, it cannot
attain as high a level of control as the ESP. . ™
I
6-76
I
-------
I
I
m Potline operation, present controls, and the planned retrofit
I
* are now described, first for the south plant and then for the north
• plant. Next the present air emissions and the emissions expected after
retrofit are presented. Then the plant's present water treating
• facility and the changes to it necessitated by the retrofit are
explained. Finally, capital and annual operating costs for the total
• retrofit are estimated.
| 6.3.2.1 Engineering Descri ption '_-_- South Plant
I 6. 3.2.1.1 Potline operation -- The south plant has three potlines and
a total capacity of 70,000 ton/year. Each potline has 124 cells set in
'• four rows in one potroom for a plant total of 372 cells. The ootrooms
• have sidewall ventilation. The plant was built in 1941 and expanded
™ in 1952.
I The cells have total -enclosure hooding with manually operated steel
roll-down hood doors extending the full length of both sides of each
| cell. Pollutants continuously escape from the top of the cell enclosure
_ and also from the hood doors when they are open. The doors have to be
™ opened frequently to add alumina to the cryolite bath by working the
• cell, to tap the molten metal layer from beneath the bath, and to
insert and remove studs from the anode block while raising the flexible
I'
current connectors.
I
I
6-77
I
-------
I
I
6.3.2.1.2 Present controls — Four 8-inch ducts, two on each end
of each cell, pick up the primary exhaust from the top of the cell I
hooding enclosure and carry it to a circular manifold duct. Each
manifold handles primary exhaust from 15 or 16 cells. The primary |
exhaust rate is 2000 to 2500 acfm per cell at 200°F. •
Each manifold leads to a fan that is driven by a 50-hp motor
and is located just outside the potroom. Originally each fan was •
upstream of one Douglas fir spray tower, each potroom having eight
spray towers apiece. However, four of the 24 towers have been replaced |
by two larger towers, the larger towers each handling exhaust from two •
fans or manifolds. Each tower is capped with an inverted cone. The
20 smaller towers are each about 8 feet in diameter and 35 feet high, I
and the two larger towers are each about 15 feet in diameter and 50 feet
high. By way of comparison, the peaks of the adjacent potrooras are 39 feet |
high and the tops of the roof monitors are 22 feet above the peaks, for _
a total building height of 61 feet. •
The towers are equipped with dual sprays that are fed with a cir- I
culating alkaline solution that contains 2 prams of fluoride per liter of
solution. Because fine sprays plug, plant personnel consider it essential g
to use a coarse spray and thoroughly wet the walls of the tower in order
to maximize gaseous and particulate fluoride removal efficiency. ™
6.3.2.1.3 Planned retrofit — Figure 6-15 is a layout of the south I
plant retrofit and Table 6-19 lists the major retrofit items. The •
three potrooms are oriented in a northeast-southwest direction. The
I
6-78 I
I
-------
s
o
o
p
o
a.
O
o
a.
i
o
o
E
o
Q.
gs
§
jO
Q-
O
&
m
3
o
6-79
-------
I
I
Table 6-19. MAJOR RETROFIT ITEMS—PLANT B—SOUTH PLANT
I
1. Several circular elevated mild steel ducts conveying primary
exhaust to two retrofit areas southeast and southwest of the .
plant. For each area, 4-foot ducts combine and orow into I
one 14-foot duct that reduces in size to 7 feet as it feeds
5 ESPs.
2. Ten fans, each driven by a 300-hp rotor and upstream of an ESP. •
Each fan is designed to handle 100,000 scfm of exhaust at about
4 inches of water total pressure drop. •
3. Ten steel ESPs each designed to handle 100,000 scfm of exhaust.
Each ESP is a rectangular box 29 feet square and 29 feet high with _
a stack discharging about 80 feet above the ground. Each ESP I
has a gas side-inlet section of flattened rectangular pyramidal ™
shape.
4. A 20- by 50-foot control building. I
I
planned retrofit consists of ducting all the primary exhaust from •
potroom J and half from potroom K to five ESPs located together as shown
in Figure 6-15, and ducting all the primary exhaust from potroom L and I
the other half from potroom K to five ESPs also located together. Each
set of five ESPs is termed a central installation. I
The per-cell primary exhaust rate will be increased from 2000-2500 m
acfm at 200°F to 3500 aefm at 200°F, increasing the south plant's
primary collection efficiency. The ducts inside the potrooms are •
presently oversized, so they will not have to be modified to handle
the increased flowrate. Primary collection efficiency will also be I
improved by installing new motorized doors on the cells and sealing •
the top of each cell's hooding enclosure with glass wool.
6-80 *
I
I
-------
I
™ Redirecting the south plant's primary exhaust from courtyard
•/ to central controls will require a balanced ducting layout design
that ensures equal pressure and flowrates in all of the 12 manifolds
• that are serviced by each set of 5 ESPs.
The ducting changes for this central retrofit will be external
• to the potrooms. The existing fans and spray towers will be bypassed.
• All of the spray towers will eventually be torn down, but many will
have to be torn down during the installation to make room for the
• ducting shown in Figure 6-15, This will mean that portions of the
plant will run uncontrolled for varying periods of time during the
I installation. Nothing but the spray towers will have to be torn
« down as a result of the south plant retrofit.
Removal of the existing spray towers will force the wet ESPs
I to act as absorbers for gaseous fluoride and require that liouor be
fed to the inlet sections of the ESPs. Plant personnel hope to control
I corrosion of the ESP steel internals by controlling the composition and
_ pH of this feed liquor. Even so, they anticipate having to rebuild the
™ internals every 10 years.
• Estimated installation times are given at the end of Subsection
6.3.2.2.
6.3.2.2 Engineering_Pe_scrjptjpn_ - North Plant
• 6.3.2.2.1 Pot!ine operation — The north plant also has three potlines
• and has a capacity of 140,000 ton/year for a total plant capacity of
210,000 ton/year. Each potline has four rows of 168 cells in two pot-
I
I 6-81
I
-------
6-82
I
I
rooms, or two 42-cell rows per potroom, for a plant total of 504
cells. The potrooms have sidewall and basement ventilation. The g
plant was built in 1968. _
The cells are elevated slightly above the floor and have total- •
enclosure hooding with mechanically operated aluminum doors extending •
the full length of both sides of each cell. Comments on emissions from
the top of the cell enclosure and on door opening for the south plant I
also apply to the north plant.
6.3.2.2.2 Present controls — Four ducts, two on each end of each
cell, pick up the primary exhaust from the top of the cell hooding |
enclosure and carry it to a circular manifold duct. One manifold _
handles primary exhaust from 14 cells. The primary exhaust is 3600 *
scfm per cell. I
Each manifold proceeds to a 50,000 scfm fan that is driven by a
125-hp motor, is located outside the potroom, and is upstream of a ]
spray tower. Figure 6-16 shows the general location" of the 36 spray _
towers at the north plant. Each tower is 13 feet in diameter and is •
capped with an inverted cone that connects to a 5-foot stack. This •
stack discharges to the atmosphere about 70 feet above the ground.
By way of comparison, the peaks of the potrooms are 54 feet hiqh I
and the tops of the roof monitors are 8 feet above the peaks, for
a total building height of 62 feet. The towers are fed with the same •
alkaline solution as the towers at the south plant. •
I
I
I
-------
I
I
I
mm
1
•
o
1
1
1
•
1 D
1
1
1
1
•
0
1
1
1
)TROOM
£
a
oo
a.
(O
LU
1
j
a
V
i
1
IU
1-
>»
cc
Si
a
oo
DTROOM
0.
a
00
n
oo
D
oo
OTROOM
a.
a
oo
D
oo
a
00
OTROOM
CL
D
00
D
oo
a
oo
OTROOM
a.
a
oo
D
oo
o
oo
OTROOM
a.
'N.
D I
o g
a.
T3
(0
c
o
to
o
a
1
CL
.C
i
O
c
t
D 2
O 5
Q.
'f -
5
0®
>1
8 ^1
1* 1
g yj TJ-
*~ < fc
0 O £C
«' 1 05 3 O
CB«
Q «-ul ilo
o
1
. 6-83
1
-------
I
I
6.3.2.2.3 PIamed retrgf 11 — Figure 6-16 is a layout of the north
plant retrofit and Table 6-20 lists the major retrofit items. The •
south end of the north plant is 1100 feet northwest of the north end
of the south plant. The planned retrofit consists of adding 21 ESPs I
downstream of the existing fans and spray towers. The plan is to install
three 50,000 scfm wet ESPs on the outside of each of the two end I
buildings, one per spray tower, and three-: 100,000 scfm wet ESPs in each •
of the five 51-foot wide courtyards between potrooms and between pot-
lines (see Figure 6-16). Each of the latter ESPs will handle the exhaust I
from two spray towers, one from each adjacent building.
Primary collection efficiency should not increase at the north •
plant as a result of the retrofit because the north plant already in- m
corporates all of the same modifications that are expected to increase
collection efficiency at the south plant. The per-cell primary exhaust I
rate will remain at 3600 scfm. The existing fans and spray towers and
all the ductwork upstream of the spray towers will not be changed, and I
nothing will have to be torn down as a result of the north plant retrofit. •
Downstream of each tower a 5-foot duct will carry the towsr exhaust
from the tower's inverted cone to the inlet section of the adjacent ESP. 8
There will also be a valving arrangement to vent the tower exhaust to
the atmosphere if the ESP is inoperative, |
At the north plant, liquid will be fed to the inlet section of the _
ESPs and will pass through an ESP before passing through its associated •
spray tower(s). As at the south plant, plant personnel hope to control I
corrosion by controlling the composition and pH of the liauor, but
anticipate rebuilding the ESP internals every 10 years. |
6-84
I
I
-------
I
I
Table 6-20. MAJOR RETROFIT ITEMS—PLANT B—NORTH PLANT
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
1. Six steel ESPs, each designed to handle 50,000 scfm of exhaust.
Each ESP is a rectangular box 29 feet by 14 feet and 29 feet high
with a stack discharging about 80 feet above the ground. Each
ESP has a gas side-inlet section, of flattened rectangular
pyramidal shape,
2. Fifteen steel ESPs, each designed to handle 100,000 scfn of
exhaust. Each ESP is a rectangular box 29 feet square and 29
feet high with a stack discharging about 80 feet above the ground.
Each ESP has a gas side-inlet section of flattened rectangular
pyramidal shape.
3. Seven 8- by 20-foot control buildings, one for each set of three
ESPs.
It was necessary to have the wet ESP tailor-made to the plant.
It was also necessary to prove its operability before makinci a total
plant commitment. For these reasons, and because of the limited
availability of funds and manpower, the retrofit was completed in
phases.
In late 1970, design was started on a pilot 50,000 scfm unit on
the north plant. As of September 1973, one more 50,000 scfm unit and
three 100,000 scfm units were operating on the north plant. These
five units comprise Phase I of the retrofit. Phase II involves
installing the remaining 16 ESPs on the north plant, and Phase III
involves installing the 10 ESPs and accompanying fans and ductwork on
the south plant.
Plant 8 completed Phases I and II in January 1975 and, as of
March 1975, planned to complete all three phases by June 1975. It
- 6-85
I
-------
I
I
will then have been about 4-1/2 years from the start of development
through total plant installation. Had the pilot unit not proven •
operational, this time could have been much longer.
Because the plant's engineering design capabilities increased •
with operating experience, each subsequent phase has taken less time
to design than the former. By necessity, work on a subsequent phase •
begins before the installation of the former phase is completed. •
6.3.2.3 Emissions Before and After Retrofit
I
Tables 6-21 and 6-22 reflect estimates of emissions before and
after retrofit provided by the company. All of the quantities are •
expressed as pounds of total fluoride ion per ton of aluminum pro-
duced (Ib/ton Al). The tables show the quantities generated at the |
cells, the quantities emitted from the applicable primary control equip- _
ment and the secondary building roof monitors, and the quantities removed "
by the primary control equipment that eventually become either cryolite fl
or liquid waste. The overall plant average is a weighted average
based on the north plant accounting for 67 percent of plant B's pro- £
duction. _
The generation estimates in Tables 6-21 and 6-22 are based on a ™
statistical analysis for the 10-month period beginning June 1, 1972, •
and ending April 1, 1973. Plant personnel selected this time interval
because the total plant was at full production and had the fewest •
in-process variables to distort the results. Data from other time
periods would, of course, be somewhat different. *
I
6-86 •
I
-------
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Table 6-21. BEFORE RETROFIT MAXIMUM EMISSIONS—PLANT B—NORTH
AND SOUTH PLANTS
(lb total F"/ton Al)
North plant
South plant
Overall plant
average
Generation
38.2
50.0
42.1
Emissions
Primary
3.6
4.0
Secondary
1.9
10.0
Total
5.5
14 jO
8.3
Removal
32.7
36.0
33.8
Table 6-22. AFTER RETROFIT MAXIMUM EMISSION ESTIMATES—PLANT B—
NORTH AND SOUTH PLANTS
{lb total F"/ton Al}
North plant
South plant
Overall plant
average
Generation
38.2
50.0
42.1
-Emissions
Primary
0.7
1.4
Secondary
1.9
5.1
L Total
2.6
6.5
3.9
Removal
35.6
43.5
38.2
6-87
-------
The method of analyzing the data was taken from Probability and
52
I
I
Statistics for Engineers.' Sample averages and standard deviations •
were calculated from data derived from the plant's standard monthly
sampling program. In this program, the plant samples the input to and jj
the output from 6 to 10 spray tower fume control units and the output _
from 4 to 6 roof monitor locations. Different locations are sampled •
each month. The plant's objective is to sample every location across •
the plant once every 6 months.
The average pounds of total fluoride generated per day was computed |
on a monthly basis by adding the average daily emissions from the —
monitors to the average daily spray tower inputs per month per plant. •
The monthly average pounds of total fluoride generated per ton of aluminum •
produced was then computed for each of the 10 months by dividing each such
average generation per month per plant by that plant's average daily I
production rate for the month. The average and the standard deviation
for the 10-month period in each plant was then computed from the 10 •
monthly averages. The Kolomogorov-Smirnov Test was conducted on the data •
derived for each plant and it was determined that a normal distribution
provided a good fit for each plant and for the total plant. The generation I
estimates in Tables 6-21 and 6-22 represent 95 percent tolerance limits
at a 95 percent confidence level. •
The primary and secondary emissions in Tables 6-21 and 6-22 are •
computed by applying estimated primary collection and removal efficiencies
to the above generation estimates. Estimated primary collection and I
I
6-88 •
I
-------
I
removal efficiencies for Table 6-21 are 95 and 90 percent, respectively,
I for the north plant, and 80 and 90 percent, respectively, for the south
w plant. Estimated primary collection and removal efficiencies for Table 6-22
are 95 and 98 percent, respectively, for the north plant, and 90 and 97
• percent, respectively, for the south plant. Assuming a zero percent
secondary removal efficiency, the above primary collection and removal
jj efficiencies correspond to overall control efficiencies before retrofit
. for the north and south plants of 86 and 72 percent, respectively; and to
™ overall control efficiencies after retrofit for the north and south plants
• of 93 and 87 percent, respectively.
Although not shown in Tables 6-21 and 6-22, the retrofit should
I increase the total participate primary removal efficiency from 55 to
98 percent, and the hydrocarbon primary removal efficiency from a control
" level of 8 to 10 percent up to a control level of 92 to 94 percent, the
• latter being a ten-fold increase. The hydrocarbons comprise a substantial
portion of the small-diameter particulate that the present scrubbers are
• incapable of removing.
Table 6-23 contains revised June 1974 company estimates of emissions
• after retrofit. The sampling methods and statistical treatment are the
• same as for Table 6-22. However, the data are averages rather than 95
percent tolerance limits and are computed over a 14-month period of full
I production that includes the 10-month period used for Table 6-22. Also,
the primary emission estimates at both the north and south plants are 95
• percent confidence level estimates based on actual testing of primary
• emissions at the north plant. Twelve months of emission testing in 1972
yielded an average total emission before retrofit of 5.4 Ib F/ton Al.
I
I
I
6-89
-------
Table 6-23. AFTER RETROFIT AVERAGE EMISSION ESTIMATES—PLANT B—
NORTH AND SOUTH PLANTS (ib total F/ton Al)
North plant
South plant
Overall plant
average
Generation
32.1
31.1
31.8
Emissions
Primary
0.25
1.10
Secondary
1.6
4.0
Total
1.85
5.1
2.9
Removal
30.25
26.0
28.9
The primary and secondary emissions in Table 6-23 correspond to
primary collection, primary removal, and overall control efficiencies
of 95, 99.2, and 94 percent, respectively, for the north plant; and of
87, 96, and 34 percent, respectively, for the south plant.
From Table 6-22 it can be seen that the maximum expected total
fluoride emissions of 3.9 Ib/ton Al for this existing plant after
retrofit is about twice that of the EPA standard of performance for
new primary aluminum plants of 2.0 Ib/ton Al. The average expected
total fluoride emission of 2.9 Ib/ton Al in Table 6-23 is somewhat
higher than the average expected total fluoride emission for plant A
of 2.4 Ib/ton Al shown in Table 6-16. However, as can be seen by com-
paring the efficiencies for plant B with those for plant A in Section
6.3.1.3, the total fluoride primary removal efficiency for the wet ESP
retrofit at plant B is the same or higher than the 96 percent primary
removal efficiency for the dry scrubbing retrofit at plant A. The
expected total fluoride emissions at plant B are higher than those
expected at plant A because the primary collection efficiency of the
6-90
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-------
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
south plant at plant B after retrofit is estimated to be only
87-90 percent. The primary collection efficiency at plant A and at
the north plant of plant B are both estimated to be 95 percent after
retrofit.
6._3_.2._4 Water Treatment
6.3.2.4.1 Current practice-- Fluoride is removed from the primary exhaust
in the north and south plant spray towers into a recirculating liquor
stream. Fluoride is recovered from this liquor as standard grade (90
percent) cryolite in a cryolite recovery plant. This recovery is
illustrated in Figure 6-17;
ALKALINE LIQUOR
LIQUOR
FROM
SCRUBBING TOWERS
THICKENERS
SLUDGE OR
UNDERFLOW
NaOH
OVERFLOW
BLEED
TO
RIVER
DIGESTER
C02
PREC1PITATOR
TANK
ALKALINE LIQUOR
LIQUOR TO
SCRUBBING TOWERS
{30 grams/liter TOTAL SODA)
CRYOLITE
Figure 6-17. Flow diagram — plant B — cryolite recovery plant.
6-91
-------
with recycle as practiced at plant B» or lime treatment with either re
cycle or subsequent adsorption on activated alumina.
56
I
I
The lowering of the pH in the precipitator tank causes cryolite
precipitation. |
At the spray towers, the recirculating liquor oicks up some of _
the sulfur dioxide that is generated at the reduction cells. This •
causes a sulfate buildup in the liquor, and it is necessary to bleed a •
small portion of the liquor to control the sulfate level. The bleed
is controlled by a constant volume regulator. It goes directly to a jj
waste water discharge sump where it is thoroughly mixed before being
discharged to a nearby waterway. ™
Plant B also recovers fluoride from its spent potliner. It used •
to buy potliner from other plants, byt no longer does this due to
stricter water effluent standards. £
53
Plant B water effluent loadings are presented in an EPA study. —
Plant B in this document is plant J in the EPA study. Plant B I
I
net effluent loadings include fluoride and suspended solids loadings
of 2.2 and 3.8 Ib/ton Al, respectively. By comparison, the recom-
mended 30-day effluent limitations for the primary aluminum industry I
to be achieved by July 1, 1977, are 2 and 3 Ib/ton Al for fluoride and
suspended solids, respectively; and the recommended daily effluent •
limitations are 4 and 6 Ib/ton Al, respectively.0 These limitations •
are considered to be attainable through the application of the best
practicable control technology. For wet scrubbing systems, best I
practicable control technology is defined as cryolite precipitation
I
6-92 • •
I
-------
I
•
•
Table 6-21 shows that 33.8 pounds of total fluoride are removed
by the spray towers per ton of aluminum produced. Plant personnel
did not provide an estimate of the fluoride recovered from potliners.
• If we assume the latter to be 20 Ib/ton Al (see Figure 5-5), then the
cryolite recovery plant handles 53.8 Ib/ton Al of fluoride. If it is
,1 assumed that there is TOO percent recovery of fluoride from the pot-
• liners and that the plant's net effluent fluoride loading of 2.2 Ib/ton
Al is all attributable to cryolite recovery, then it can be concluded
§that the cryolite plant fluoride recovery efficiency for plant B is
95.9 percent.
I
6.3.2.4.2 Changes due to retrofit— Presently the hydrocarbons collected
Q in the recirculating scrubber liquor cause foaming in the cryolite
recovery plant when treating the resultant sludge. Such foaming can
• make it extremely difficult to operate sludge treating equipment and
• can result in airborne fluoride emissions. The plant can process in
spite of the present foaming, but, as noted in subsection 6.3.2.3,
• the retrofit is expected to result in a ten-fold increase in the hydro-
carbon collected. If foaming is a direct function of the hydrocarbon
1 content in the sludge, then something must be done.
m The plant has investigated three possible solutions. The first
two involve oxidizing the hydrocarbons and the third involves con*
• trolling cryolite plant process variables so foaming does not occur.
The oxidation methods considered are direct calcination in a
,1 rotary kiln and the Zimpro wet oxidation process. Direct calcination
• is difficult to operate, has high energy requirements and high operating
| 6-93
I
-------
I
I
costs, and probably will require one more wet ESP to control emissions. «
The performance of the Zimpro process on this type of sludge is not
well known and the capital costs are quite high. •
The plant hopes to be able to identify the process variables that
affect foaming and thus accomplish a solution with considerably lower |
capital costs. As of March 1975, it was not known if oxidation _
would be required, ™
The plant has no immediate plans to reduce the effluent loadings B
associated with its bleed stream.
6.3.2.5 RetrofitCapital and Annual Operating Costs
6.3.2.5.1 Capital costs—Table tf-24 is a spring 1973 estimate of the •
total retrofit capital costs for the north plant, south plant, and the •
sludge treatment project broken down into the major retrofit items.
Assuming-an annual aluminum capacity of 210,000 tons, $23,457,500 is |
equivalent to a capital cost of $112 per annual capacity ton.
Plant B furnished the direct costs in Table 6-24. Reduction cell •
sealing, new motorized doors, and new fans at the south plant will •
increase primary collection efficiency. Two new thickeners, one for
each plant, are included under phases II and III in Table 6-24; but jj
in reality, they are part of cryolite recovery. New thickeners are
needed to handle the higher flowrate and higher fluoride loading re- •
suiting from the retrofit and to remove smaller particulate. Smaller •
particulate removal is required because the ESPs will, have finer
spray nozzles than the present spray towers, and finer nozzles are more I
likely to plug,
6-94
I
-------
1
1
1
1
1
1
1
1
1
1
1
1
V
1
i
i
Table 6-24. RETROFIT CAPITAL COST ESTIMATE— PLANT B
Direct costs
Reduction cell
sealing
Motorized doors
Ducts
Fans
Electrostatic
precipitators
Foundations
Drains, pumps,
and piping
Thickeners
Electrical
Control buildings
Equipment sales tax
Subtotal s
North plant
Phase I
Not
broken
down
Phase II
-
-
$520,000
-
4,810,000
200,000
200,000
400,000
380,000
42,000
328,000
$1,480,000 j $6,880,000
South plant
Phase III
$200,000
280,000
1,395,000
160,000
3,430,000
300,000
100,000
300,000
1,115,000
30,000
365,000
$7,675,000
Sludge treatment costs
Site preparation and foundation $127,000
Slurry tank and pumps 33,500
Centrifuae, kiln, feed screw,
"afterburner and scrubber 705, onu
Treated solids handling equipment 101,000
_Electrical 156,000
Wet oxidation equipment, including
foundations and electrical
387,500
Subtotal— sludge treatment including sales tax $2,010,000
6-95
-------
Table 6-24 (continued). RETROFIT CAPITAL COST
Subtotal Phase I
Phase II
Phase III
Sludge treatment
Subtotal direct costs
Indirect costs
Engineering
Contingency
Escalation
Subtotal indirect costs
Subtotal direct costs
Project total cost
ESTIMATE—PLANT B
$1 ,480,000
6,880,000
7,675,000
2,010,000
$18,045,000
$1,804,500
1,804,500
1,804,500
5,412,500
18,045,000
$23,457,500
Sludge treatment costs are shown for the equipment associated with
both direct calcination and wet oxidation because
that, regardless of the alternative selected, they
$2 million for suitable sludge treatment equipment
plant personnel believed
will probably spend
, The sludge treat-
merit equipment will be installed on land that is presently used to store
used potliners. The site preparation costs for si
6-24 represent the funds necessary to prepare this
udge treatment in Table
land.
Plant B did not furnish indirect costs. Engineering, contingency,
and escalation costs in Table 6-24 are each based
of 10 percent of direct capital.
6-96
on arbitrary factors
1
1
1
1
1
1
1
1
1
1
1
1
1
-------
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
The plant B retrofit would have been
been constructed of 316 stainless steel,
more costly had the ESPs
the normal material of con-
struct! on for wet ESPs applied to an aluminum plant. As mentioned on
subsection 6.3.2.1.3, the plant hopes to control corrosion of the
221 internals but still anticipates rebuilding the internals every
10 years.
The assets to be retired as a result
essentially no book value.
Table 6-25 is an October 1974 update
of the planned retrofit have
of the total retrofit capital
costs for the north plant, south plant, and the sludge treatment pro-
jects. Assuming an annual aluminum capacity of 210,000 tons, $19,300,600
is equivalent to a capital cost of $92 per annual capacity ton. The
direct costs in Table 6-25 are from the company. The indirect engineering
cost is based on an arbitrary factor of
There are no escalation and contingency
nearing completion.
10 percent of direct capital.
costs since installation is
Table 6-25. REVISED RETROFIT CAPITAL COST
ESTIMATE—PLANT B
Direct costs
North plant
South plant
Sludge treatment
Subtotal
Indirect costs
Engineering
Conti ngency
Escalation
Project total cost
$8,871,000
7,675,000
1,000,000
$17,546,000
$1,754,600
-
$19,300,600
-------
I
I
6.3.2.^.2 Annual operating costs— Table 6-26 is a company estimate
of year-to-year additional gross and net annual operating costs for •
operating the ESPs after the plant has been retrofitted. Assuming
an annual aluminum production equal to the annual capacity of 210,000 g
tons, $171,000 for operating the ESPs amounts to $0.81 per ton. Plant ^
personnel stated that, even though these additional costs are quite •
modest, annual operating costs for plant B's present system are •
substantial. However, plant personnel are not able to break out the
present emission control annual operating costs. Also, although jj
an estimate of annual operating costs for sludge treatment was not
obtained, plant personnel stated that its operating costs should be "
considerably smaller than that shown for the ESPs in Table 6-26. ft
The planned retrofit will not directly recover any valuable
material; hence, the zero credit. Generally, the value of the •
fluoride recovered in an aluminum plant that has a wet scrubbing
system and cryolite recovery is offset by the operating costs of
recovering the fluoride. I
The capital-related charges that are part of net annual cost were
not furnished by plant B and are not included in Table 6-26. Based on a |
"capital recovery" factor of 14.903 percent, an "administrative over- .
head" factor of 2 percent and a "property taxes and insurance" factor *
of 2 percent, capital related charges would amount to 18.903 percent of •
capital cost for this retrofit. Since the plant anticipates rebuilding
the ESPs every 10 years, the "capital recovery" factor covering
6-98
I
I
I
-------
1
1
1
I
I
•
1
1
1
1
•i
1
1
1
1
1
1
1
1
1
Table 6-26. RETROFIT ANNUAL OPERATING COST ESTIMATE— PLANT
NORTH AND SOUTH PLANTS . . : :
-~— - •—•••• ~- — - '•••---' U-.-LJJl-l - -~,-™,.r- ^— .-
Gross annual operating cost
Operating labor and materials $56,
Utilities
Fuel
Electricity 40,
Water 5,
Maintenance labor and materials 70,
Total gross annual operating cost $171,
Value of recovered materials
Net annual operating cost $171,
depreciation and interest is based on a 10-year equipment li
percent interest. Capital related charges for this retrofit
B—
•IMMlMMHHI
000
-0-
000
000
000
000
-0-
000
fe and 8
thus amount
to 18.903 percent of $19,300,600— or $3,648,000. Adding these
charges to Table 6-26 would result in gross and net annual costs of
$3,819,000.
6-99
-------
6.3.3.1 Engineering Description
6.3.3.1.1 Potliiie operation—The plant was built in 1965 using
I
I
6.3.3 Plant C--Prebake Cells--Primary Injected Alumina Dry
Scrubbing Retrofits?
This plant has three side-worked prebake potlines. As built, •
the potlines had only secondary control consisting of wet scrubbers, ft
but all three potlines were recently retrofitted with primary control
systems. Hoods were installed on the cells, and the primary cell gas •
exhausts were directed to injected alumina dry scrubbers.
In the following sections, potline operation, secondary controls •
with associated water treatment, and the primary retrofit are described; •
Next the emissions before and after total retrofit are presented; and
capital and annual costs for the total retrofit are estimated. I
I
European technology. Its three computer-controlled potlines have a
total capacity of 265,000 ton/year. Each potline has 240 cells in •
4 rows of 60 cells per row, installed in 2 buildings, for a plant total
of 720 cells. Each building consists of 2 single-row potrooms with I
side-wall ventilation on the outside walls and a corridor between the •
center walls, so that there are 4 potrooms per potline or 12 potrooms
for the whole plant. The cells are set into the potroom floor, but •
the potrooms have no basements.
consists of three small rectangular carbon anode blocks, two copper m
branch rods to a block - six rods to an assembly. The six branch rods
are connected to a center rod that introduces electrical current. The I
I
6-100 •
-------
I
I
cells are designed for 4 volts and 130,000 amperes, and are among
• the lowest-voltage cells in the industry.
,ft 6.3.3.1.2 Secondary control^ system—The as-built secondary controls
consisted of 30 fiberglass Ceilco.te scrubbers per building, on a floor
£ on top of the corridor between the potrooms but under the building
— roof. Each scrubber thus handled four cells. To reduce water effluent
™ discharges, only 17 scrubbers per building are now operating -- about
• every other one — and each thus handles emissions from about 7 cells.
Each scrubber consists of a horizontal spray section with 80 co-
• current spray nozzles, a 40-hp fan on the inlet, and a slat mist
eliminator on the outlet. Each scrubber handles 104,000 scfm at 20 to
• 22°C and discharges through a 12- by 18-foot rectannular stack 18 inches
• above the peak of the potroom. This peak is 52 feet above the ground.
A 40-hp pump recirculates the scrubbing water at 1200 aal/min from a
• hold tank beneath the scrubber. A small amount of water is bled off
this scrubbing loop to a water treatment plant.
• The secondary control system as installed cost $10 million.
• 6.3.3.1.3 Hater tregtrngirt—In the water treatment plant, water from the
scrubbers is treated with sodium aluminate to form cryolite. The
• cryolite is filtered on a vacuum drum filter and then dried in a kiln
• and recycled to the cells. This cryolite is of poor quality,
The water treatment plant was installed in 1971 for $1.45 million.
I
6-101
I
I
-------
I
I
6.3.3Jl_._4 Primary control retrofit—Overall control efficiency with •
just the secondary system was low, and plant management started
investigating improved control in 1970. After experimenting with g
small hoods over the gas holes in the crust, they constructed a _
Quonset hut over a cell to find out what was being emitted. They •
determined that fine particulates were the most difficult to control, •
installed a 20-cell ESP, and ran it for 6 months. The level of control
obtained by ESP was not satisfactory. They also considered the venturi •
and determined that it lacked the proper level of control. At about
that time, the plant designers had been investigating bag collectors, •
and the plant decided to abandon wet scrubbing for the injected alumina •
dry scrubbing system. The retrofit that was completed in the Spring of
1973 consisted of installing primary collection systems and injected •
alumina primary removal equipment on all three potlines.
6.3.3.1.5 Primary collection retrdf it—Side-worked prebake cells must
be worked manually along the entire side of a cell. Hence, the gas |
collection skirt at plant C consists of two nonsegmented doors, one _
on each side of the cell. Some of the cells have doors operated by air ™
cylinder, others by air motor. •
The doors have to be open about 10 percent of the time to change
anodes and to add alumina by manually working the cells. The 20 J
cells whose primary exhausts were directed to the ESP prototype
have doors that must also be opened to tap aluminum. The remaining »
700 cells have small tapping doors in the cell doors, so the cell •
doors remain closed during tapping.
6-102 I
I
-------
I
I
• A door closes with its bottom edge on the potroom floor. This
edge has an asbestos cloth seal. The closing doors hit the floor
•
•
forcefully, generating considerable dust. The doors are made of steel
because gas jets from the cells can cause holes in aluminum doors.
In the middle of the cell superstructure, two circular ducts
pick up the primary exhaust and direct it upwards to a horizontal
I
(
J2~incb circular branch duct that runs along the centerline of the
• cell. The primary exhaust rate is about 3000 acfm per cell at 200°F.
Duct headers run along the corridors between the potrooms, each
| header picking up branch ducts from 30 cells per potroom in line 1
P and 15 cells per potroom in lines 2 and 3. The headers are rectangular
™ and increase in size as they pick up more branch ducts. An average
M size is about 2 feet by 4 feet. Two headers join at the top of the
corridor, one from each potroom, and the common duct passes throuah
£ the roof to the control equipment in the courtyard. A secondary
_ scrubber has been removed to accomodate each common duct. Line 1 has
• two common ducts, and two scrubbers were removed per building. Lines 2
• and 3 have four common ducts, and four scrubbers were removed per building,
Nothing else had to be torn down or moved to accomodate the retrofit
• equipment.
M ^jj-'JbJUfi
^jj-'JbJUfi P r J ma ry remo va 1 re trofrt — Each potline has two injected
alumina units located in the courtyards between its two buildings,
each unit servicing half of each building. Figure 6-18 is a general
flow diagram for the injected alumina process at plant C. The process
m
• 6-103
I
-------
(0
(0
CO
O
00
CD
k.
3
6-104
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-------
I
involves reaction of gaseous fluoride with the alumina to be fed to
•> the cells followed by baghouse solids collection. Alumina is injected
into the flowing gas stream and the reaction occurs in a matter of
g reconds. As designed, 100 percent of the alumina fed to the cells
— should pass through the units. 97 percent passage is actually achieved.
• Plant C's retrofit is somewhat unusual in that the fans are located
• downstream of the baghouses. This location helps keep the fan blades
from scaling. Scale deposits will cause the fans to lose their dynamic
ff balance. However, a downstream fan location requires that the bag-
houses operate under negative pressure, and a negative operating pressure
• requires a stiffer baghouse structure.
'• Potline 1 has injected alumina control units designed by Prat-
Daniel -Poel man (POP) and potlines 2 and 3 have control units designed
• by Alcan. The order of retrofit was 2-3-1. Both desiqns are unique
in this country and will now be described in detail.
I
6^3.3.1.7 POP design — Figure 6-19 is a schematic of the retrofit and
•
'm>
Table 6-27 lists the major retrofit items for one of the two control
units on potline 1. Each unit has a total of 12 Venturis, 12 baghouses,
6 fans, and 6 stacks.
| 6.3.3.1 .8 Alcan design— Figure 6-20 is a schematic of the retrofit
^ and Table 6-28 lists the major retrofit items for one of the four
'•* control units on potlines 2 and 3. There are no Venturis in the
• Alcan design. Each unit has a total of 22 baghouses, 22 fans and
22 stacks.
I
6-105
I
-------
EXHAUST
FROM
POTROOMS
REACTED
ALUM IN
TO EXISTING
DAY BINS ON
BOTH BUILDINGS
iXHAUST
FROM
POTROOMS
8ft,
FAN
CONTINUOUS
LOW PRES-
SURE CON-
VEYING
SYSTEM
Figure 6-19. Retrofit schematic -- plant C -- POP design (Venturis, ducts,
fan, stack, and solids handling are depicted for one pair of baghouses only).
6-106
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-------
I
I
I
I
I
1
I
I
I
i
I
I
1
I
I
I
I
I
I
Table 6-27. MAJOR RETROFIT ITEMS—PLANT C--PDP'DESIGN
1. Two 8-foot ducts, one from each building (see Figure 6-19),
join opposite ends and sides of an 8-foot horizontal duct.
This horizontal duct runs underneath the control unit and feeds
six paired venturi-baghouse subsections.
2. Six pairs of vertical Venturis. Gas flows upward through the
Venturis each of which has two injection ports - one for fresh
alumina and one for reacted alumina that is recycled from the
baghouse. The ratio of recycled to fresh alumina is fixed at
20:1.
3. Six pairs of baghouses. Each baghouse handles 30,000 acfm of
200°F primary exhaust. Gas flow entering and leaving a baghouse
is horizontal. Gas leaving one of the two baghouses in each pair
passes horizontally through the opposite baghouse but not through
the bags—there is no process connection—and the two baghouse
exhausts join downstream of the opposite baghouse. Each baghouse
is a rectangular box 18 feet square and 20 feet high with art
inverted pyramid bottom gas inlet. The top of each baghouse is 40
feet above the ground. The bags are cleaned by shaking with reversed
air flow. At the end of every 30 seconds, one baghouse is shaken
for 4 seconds. Thus the total cycle time for all 12 baghouses is
6 minutes.
4, Six 250-hp fans located at ground level. Each fan exhausts a pair
of baghouses (60,000 acfm) and discharges to a 60-foot stack.
5. A 100-ton fresh alumina bin.
6. A continuous low-pressure conveying system to convey reacted and
unrecycled alumina to the existing day bins on top of both pot-
line 1 buildings.
7, Local controls mounted on the baghouse structure.
8. A roof of simple truss design covering the Venturis, baghouses,
and local controls. The roof is about 20 feet above the tops
of the baghouses and is supported by 14 I-beams, 7 to a side.
6-107
-------
— \*s— •***- x^ywv.*
^T
< \
X*Q \
iig
<
— 1 f "S
* " — r^
v_>
i j__"T">
v^
^. 1 ' J» >.
«— 1 — ( >
\^
~* — 1 /"N
( ]
\-J
M r ^*s
* ' — f ]
\->
^ i f -^
1 — T
V-/
x
t»tf
S
4«»
u.
< ,
uj QZ
DC Z ~~
IHUSE
3Cc^ O cc ^
^^ 3" ^ ^ ffi
^~ O {3 yj ^UJ
Z?tau.Mi-
' v^—s^A/K^i
V
§§E >-
«~H«a jX^
\_
-4
^»
\_
•4
/^~*"
\_
«|
^
\_
-*
y^-*-
X.
•4
' >^
,s \__
OD
mi y* »
"S
o3
1<
6-108
— *
i —
i '
k"L
<
< •
<
xz
2s
OCD
s
N >
X
^ \
N
\\
i«»
00
i.
ll
5
o
i.
1
1
1
1
•sj*-v*x-s-/»->~Tir-
,. 1
iii i •> s in ^^
2Sz§
ifpte !
Z°-O>. 5 M
OXuj'* | •
> I
onXen— ^
° - 1
Iff * .
g|J g •
-------
1
1
I
1
1
1
I
1
1
1
1
Table 6-28. MAJOR RETROFIT ITEMS— PLANT C--ALCAN DESIGN
1, Two 6-foot ducts, one from each building (see Figure 6-20),
join an 8-foot duct that runs underneath the control unit
and feeds 11 baghouses. The horizontal duct reduces in diameter
after each pair of take-offs. There are three alumina injection
ports -two for recycled alumina and one for fresh— in the 8-foot
duct upstream of the control unit. The ratio of recycled to fresh
alumina is variable from one to 10.
2. Ductwork identical to that just described under item 1 to feed
a control unit that is installed to the right, and in reverse,
of the control unit shown in Figure 6-20.
3. Twenty-two baghouses in 2 groups of 11 each as shown in Figure 6-20.
Each baghouse except the eleventh (nearest the bin) has a twin
beyond the plane of the paper. Each baghouse handles 16,400 acfm
of 200°F primary exhaust. Gas flow entering and leaving a baghouse
is vertical. Each baghouse is a rectangular box 10 feet square
and 18 feet high with an inverted pyramid bottom gas inlet. The
top of each baghouse is about 50 feet above the ground. The bags
are cleaned by a variable 15- to 30-second high pressure jet air
pulse.
4. Twenty-two 60-hp fans, one for each baghouse (16,400 acfm).
Each fan sets on top of its respective baghouse and discharges
to a stack. The stacks discharge to the atmosphere 60 feet above
the ground.
5. A 100-ton fresh alumina bin.
6. A batchwise high-pressure conveying system to alternately convey
reacted and unrecycled alumina to the existing day bins on top -
of each potline building.
7. Local controls mounted on the baghouse structure.
6-109
-------
I
I
6.3.3.1.9 Retrofit increments of progress—Table 6-29 presents the
time increments of progress for each of the three ootline retrofits. 'fl
As Table 6-Z9 shows, the four major contracts were awarded at different
times for lines 2 and 3, but for Hne 1 they were awarded all at once.
Compliance testing for line 2 started after several weeks of shakedown _
operation, approximately on September 15, 1972. The line 1 retrofit was •
operational when EPA personnel visited plant C on May 9, 1973. •
For each of the potline retrofits, only 9 to 10 months elapsed
between the date that the first contract was awarded and the date that •
both control units on that potline were operational. However, as mentioned
in subsection 6.3.3.1.4, the plant started investigating improved control •
in 1970, which was 3 years prior to all control units being operational. •
6.3.3.2 Emissions Before and After Retrofit
1
Table 6-30 shows average emissions before and after retrofit
furnished by the company in October 1974. All of the quantities are I
expressed as pounds of total fluoride ion per ton of aluminum produced
(Ib/ton Al). The table shows the quantities generated at the cells; |
the quantities directed to the injected alumina primary removal equip- _
ment after retrofit (primary collection); the quantities escaping ™
collection (secondary loading); the primary, secondary, and total •
emissions; the quantities removed by the secondary equipment that are
sent to the cryolite recovery plant; and the quantities recovered by ,1
the dry primary retrofit and recycled to the cells. _
6-110
I
I
-------
I
I
I
I
I
1
I
I
I
I
I
I
I
I
I
I
I
I
I
O-
1
I/)
LJ
ce;
to
o
s:
yj
D:
o
oc
fc
tr
CJi
CM
I
(U
_Q
(8
en
_ . .
r»% r- CM CM >5
CSV CO "*%."-%. _= **•>
r— +-> 'r- U £• •*•»
O VI ** -r- ••- -M *-
s_-o >» «o c i. c ~s. o O) c/1 O O -Q O Q} 4-*
OS- ••-> tfl S-*-1 «*- 4J 1C O
"S 0} I/I i— -M
-M «3-C T3+-> -M-M U re U
O
CO
VC
4->
5
JSfc,
x^
O
•a-
to
.,—
£=
co
r—
*+*^
cn
CM
t*
"*
-M
C
—>
^«%,
CM
o
CM
CO
"I—
c
ZD
en
CM
en
CM
4^
*r"*
:§
CM
f"*"*
"""•v
**.
ca
"~
4f
ZD
CM
•^
CM
10
"O
a>
-M
0)
^~
O.
E
O
u
c
o
4J
O
3
S_
4J
WJ
C
o
C-^
(C
z.
re
y*
CM
r».
in
•—
^
CM
LO
i—
o
•"7
CM
f*"*«
****%
in
pMW
00
.
r»-
in"
i«*
IB
c:
o
•r-
-P
to
5-
O)
Q.
O
4->
'g
2Z}
JQ
(O
«B
>
-------
Table 6-30. EMISSIONS BEFORE AND AFTER RETROFIT-PLANT C-
LINES 1, 2, AND 3
(Ib total F"/ton Al)
Emissions
Generation
Primary collection
Primary emission
Secondary loading
Secondary emission
Total emission
Secondary removal
Primary recovery
Before
retrof i t
45.5
-
-
44.5
9.0
9.0
35.5
-
After
retrof i t
45.5
37.8
0.4
6.7
0.9
1.3
5.8
37.4
Monthly average inlet loadings to the primary and secondary con-
trol systems were 37.76 and 6.72 Ib F/ton Al in September 1974. The
generation level of 45.5 Ib/ton Al is the sum of these loadings, plus
a rough approximation that building leakage is 1.0 Ib/ton Al. These
loadings and the secondary emission of 9.0 Ib/ton Al before retrofit
were measured with the plant operating at capacity. The primary and
secondary emissions of 0.4 and 0.9 Ib/ton Al are based on 92 and 93
tests, respectively, during January-September 1974 when the plant
was at or near full production. For these nine months, testing typi-
cally consisted of three tests per week on both the primary and secondary
fi-119
I
I
I
I
I
I
I
1
I
I
I
I
I
I
I
I
1
I
I
-------
I
|| systems. Each of the three tests was for emissions from a different
_. potline and lasted 24 hours. Plant personnel have not been able to
determine any difference between the performance of the POP units and
M that of the A!can units.
The emissions before retrofit in Table 6-30 correspond to a secon-
| dary removal efficiency of 80 percent and an overall control efficiency
_ (including building leakage) of 78 percent on total fluoride for plant
•
* C. The emissions after retrofit correspond to a primary removal
• efficiency of 99 percent, a secondary removal efficiency of 87 percent,
a primary collection efficiency of 83 percent and an overall control
I efficiency (including leakage) of 95 percent on total fluoride for
plant C.
H Two conclusions that can be drawn from the above efficiencies and
M Table 6-30 are:
1. Without secondary control, a primary collection efficiency
I of 83 percent would result in a secondary emission of 7.7
Ib/ton Al and a total emission of 8.1 Ib/ton Al for total
I
fluoride after retrofit.
2. The retrofit reduced by 84 percent the quantity of total
fluoride that is removed by the secondary control system and
• sent to the water treatment plant. This in turn has reduced
the plant water effluent discharges.
I
I
I
I
I
6-113
-------
I
6.3.3^3 Retrofit Capital and Annual Costs I
6.3.3.3.1 Capital costs—Table 6-31 presents the total retrofit '••
capital cost for the three potlines broken down into the major retrofit
items. Assuming an annual capacity of 265,000 tons, $14,300,000 for I
retrofit is equivalent to a capital cost of $54 per annual capacity ton.
The duct costs in Table 6-31 include all ductwork from the cells •
to the 8-foot horizontal ducts underneath the control units. The •
control unit costs include the remaining ductwork, Venturis, baghouses,
fans, stacks, and solids handling for all the A!can and POP units, I
Nondistributed costs are primarily, but not exclusively, related to
the control units and include such things as utilities (primarily I
compressed air) and instrumentation. Research and development (R&D) •
costs include only the development work that eventually became part
of the retrofit. Hence, the costs are included for the hoods on the •
20 cells whose primary exhausts were directed to the ESP prototype,
but not for the ESP itself. Plant personnel are unable to determine |
the remaining R & D costs from their records. All contractor engineering _
and the plant R & D engineering costs that pertain to the installed ™
retrofit are included in the Table 6-31 costs. Plant oersonnel are •
unable to determine the remaining plant engineering costs from their
records. |
The secondary scrubbers were the only assets that were retired
as a result of the retrofit. They were installed for $1,166,000, «
were being depreciated over a 20-year life, and when retired had a •
book value of $907,000.
I
6-114
I
I
-------
I
1
Table 6-31. RETROFIT CAPITAL COST—PLANT C-
-- LINES 1, 2 AND 3
• Hoods $3,160,000
Ducts 1,190,000
J Emission control units 7,970,000
II Nondistributed costs 1,250,000
• Research and development 730,000
• Total $14,300,000
I ~
jj 6.3.3.3.2 Annual costs—Table 6-32 gives annual costs for both the
f primary injected alumina retrofit and the secondary scrubbers as
furnished by the company in March 1975. Assuming an annual aluminum
'• production equal to the annual capacity of 265,000 tons, the total
retrofit annual cost amounts to $12.99 per ton; the total secondary
|| scrubber annual cost amounts to $7.07 per ton; and the plant's ool-
— lution control annual cost amounts to $20.06 per ton. The total retro-
• fit annual operating cost of $936,000 amounts to $3.53 per ton.
• The cost of producing compressed air for the retrofit is included
in maintenance materials. The plant pays no royalty costs for the
m Alcan or the Prat-Daniel-Poelman designs. The secondary scrubbers are
leased. Hence the depreciation cost of $1,190,000 is rent, and there
• are no charges for interest or taxes.
I
_ 6-115
I
-------
In Table 6-32, no credit is given for the alumina and fluoride
recovered by the retrofit because the plant accounting s.ystem does
not credit these recovered materials. Assuming a fluoride recovery
rate of 37.4 Ib/ton of aluminum produced (see Table 6-30), an annual
aluminum production of 265,000 tons, and a fluoride cost of $0.25 per
pound,50 the value of the recovered fluoride would be $2,477,750
per year.
Table 6-32. 1974 ANNUAL COST—PLANT C— LINES 1, 2, AND 3
Operating costs;
Labor incl . dir. supv.
Supplies
Electricity
Water
Maintenance materials & labor
Bag replacement
Subtotal
Capital -related charges:
Depreciation
Interest
Insurance
Taxes
Administrative & overhead
Subtotal
Total
Injected
Al umi na
Retrofit
413,000
20,000
130,000
152,000
221 ,000
936,000
973,000
1,317,000
9,000
176,000
32,000
2,507,000
3,443,000
Secondary
Scrubbers
141,000
38,000
104,000
21 ,000a
355,000
659,000
l,190,000a
7,000a
17,000
1,214,000
1,873,000
Both
554,000
58,000
234,000
21 ,000
507,000
221 ,000
1,595,000
2,163,000
1,317,000
16,000
176,000
49,000
3,721,000
5,316,000
Estimated.
6-116
1
i
1
1
1
1
I
1
1
1
1
I
1
1
1
I
1
1
1
-------
I
I 6.J.4 Case Description Summary
Table 6-33 shows actual retrofit emission reductions and cost
• for potroom retrofits at ten primary aluminum plants. ' EPA
• personnel had visited seven of these plants (A-6) at the time the
detailed case descriptions were developed. Since any one of these
• seven could have served as a retrofit case description, a comparison
table and a rating sheet were prepared to select the best cases.
| The three cases that have been selected (plants A, B and C)--
• together with the discussion of primary collection, primary removal
* and secondary removal systems — are believed to adequately cover
• primary aluminum fluoride retrofit control techniques.
The emission numbers in Table 6-33 are average total primary
(J and secondary total fluoride emissions expressed as pounds of fluoride
ion per ton of aluminum produced. The Increase in plant K emissions
" after retrofit is explained in subsection 6.3.4.2. The capital costs
• Include direct and indirect costs. The indirect costs Include
engineering and, where a retrofit is underway, contingency and
I escalation costs. However, as noted in Section 6.3.3, not all the
engineering costs are included in the plant C retrofit. Except for
• plants G and M, the retrofit costs are final or, where the retrofit
• is still underway, are the customary accurate appropriation reauest
estimates. Plant G costs are based on written vendor quotations and
I should thus be reasonably accurate. Since the accuracy of plant M
costs is questionable, this plant is separated from the others in
•
•j
I
I
Table 6-33. The capital costs are also shown adjusted to April 1974
using plant cost indices from Chemical Engineering^ magazine.
-------
LO
I—
•4_'
o
o.
c
•Met
iO
I- C
<1> O
o'^>
I—*'5"
(B "
13 4-»
C >
C O
H3 O
O
** ^.
•o in
OJ •—
3 «i~
"CP C
' i.
CJ "*^^
ro (/)
Q. C
f"d o
O -M
1 * 1 <
C S»
>
o •*->
as **-
O CO i — CC
«:C«C«""C C""D i""**- ""•il" (*} CM
r** LO c!n vo cr* i^» ^5 CT^ ii!''l~
"~
OOOOC3CDOOO
Ol«OOOOOOO
OCOOOOOOOCD
IjO CSI f"p (**"% UTS |_O IrnU C3 f"""1
,„- - fV5 i,/^ OO ^u(i? OO i*'"* 00 CJ^i
i— CM i — CM CM
T3 ^,
C^ f i C5 "i" ^ ** ^£ ^*^ «SC LjJ
O2 £Q CO CO CO QO
r^ Q Q_ r\ Q Q t/^ C/^ t/1
3S33;3^^(jOt/'l(/)
C_> CJ O O (/") > 1C ^ D^
f~
"J
cn
CM
t—
in
r—
""
C^
1—
co
in •
CD
O
O
o
CO
I-—
.
!£
to
t/1
5*
6-118
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-------
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
fEN PRIMARY ALUMINl
r~~
OS
S
to
to
??
Q
^
^*"
L/l
z
o
pi
3
•"""*
LLl
_
o
(— 1
to
|iii t
*£T
MlC..
LLJ
1—
u_
o
L^
1
^
«B-
o
S
rf
a.
w
^— »
T3
CU
^
ft—
4-)
1
C^ * *
€*^ CO
1 LU
O
f-~
CU
u
CU
(Q
-Q
CU
S.
Q-
"O s/i
Qi r—
J- "cu
O U
2
i?
•o cu
V) t-
cu
o
CQ {/>
O-
3 T3
fl 3
" t/»
I/I
i— fO
CU +J
o
CU N
(0 E
.Q O
CU -E
s-
O. I
T3 CO
J^ Z
o **
5 >
1 r™>
S- r—
CU CU
•P U
c
CU O)
u s-
cu
s-
ca 01
a. -o
3 O
<_3 tO
U)
o
I/)
I/)
*f™
CU
cu
•r™
J-
o
3
r—
««-
,_
rt3
o
-P
s-
(O
T3
O
O
CU
tn
•o
c
>^
E
T
Q.
CU
CTi
S-
O)
ja1
•
T3
CU
O
s_
1 *
CU
S-
co
c
r—
-1- *
o
D.
CU
o
OJ
jc:
^.
i —
c
o
f—m ^
_Q O
o
(tJ i.C
V)
-4_J
O i/I
^y^ ^™J
it "3
i/)
«=C CO
2 of
O T3
I/)
Q)
•O
2
*U
C
»r~
4->
«/»
O
U
ro
c
•r—
•P
(O
s-
o>
o.
o
_
to
•a
c.
c
1C
4->
0)
z
t t
"r»*
« O
01 C
XI I/I
fO CU
i— O
•r- T3
10
> I/I
(0 1/9
O
•P &-
o ro
c
* n
4-> Q»
cu -o
C'E
• •> O
4-> ZJ
O C
U
•o
crs c
^™ ^o
-M s-
o
T3 H-
O)
C/» t/)
lO -P
CU -r-
$- T3
IS
CU
-l_j
I/)
O
C»J
C7)
C
•»—
s_
OJ
o
o
«
3
^
R)
4->
CU
c
X)
CU
ro
SI
a
CU
-o
i/i
(O
CO
E
c
CT>
i/)
CU
>•
• ^
+J
CD
3
<£'
6-119
-------
I
I
I
Plants A and B furnished the additional net annual operating cost and *
plant C furnished the additional gross annual operating cost for their •
retrofits as shown in Table 6-33. Additional net annual operating cost
is also shown for plant M. These annual operating costs do not include jj
capital-related charges.
Table 6-33 shows as much as a three-fold variation 1n cost for
actual retrofits. Real-life differences between plants that can
affect the cost include: the need to tear down varying types of
existing control; the possible need to tear down other equipment and I
buildings; the extent to which support structure for the retrofit
already exists; and, the need for installing or modifying primary |
collection systems. The latter Includes the extent of modification •
that is dictated by potroom layout and by cell geometry and operating
requirements. m
To further illustrate the complexity of real-life situations,
the vendor of the fluidized bed claims that the installation cost of |
fluid-fzed bed removal equipment can vary greatly, from as low as about .
' I
$30 per annual ton on some new prebake installations to levels such m
as shown for Plant D 1n Table 6-33 ($117 per annual ton). This four- •
58
fold variation In cost Is largely determined by the following factors:
1. The volume of cell gas to be treated per ton of metil •
produced. Smaller and older design prebake cells, such as •
those of Plant D» generite as much as twice the gas volume
of some newer cell designs on a cubic foot per ton basis. I
I
6-120 - I
I
-------
I
• 2. The physical layout of the existing plant, which affects:
a. The length of the duct svstem.
I b, The availability of alumina storage tanks for storage
• both preceding and following the fume treatment system.
c. The available space for locating the fume treatment svstenn.
• d. The access to the area by large construction equipment
used to erect the reactors, baghouses, etc.
| e. The availability of sufficient electrical power close to
m the site chosen for the control equipment.
• This section Illustrates the point that for a process as complex
• as a primary aluminum plant, a retrofit control must be tailor-made
and should not be generalized as to costs or even as to method of
• emission control.
•L In the following subsections, capsule descriptions of each of
the ten actual retrofits are given by cell type.
I
retrofit in July 1974. A total of 25 reactor-baghouses units were
I installed, along with supporting equipment, to replace 30 courtyard
rotocl one- to- spray tower fume control units on the five plant
I potlines. Total system capacity is 1,250,000 acfm. The retrofit
m did not improve primary collection efficiency, although the capital
cost included replacing the side shields on all 650 cells with new
• identically-designed covers. There was no secondary control before
or after retrofit. Total retrofit capital cost was $11,766,900
| which included the cost of removing and relocating the former control
_ equipment.
6-121
6.3.4.1 Center-worked PrebakeCells
Plant D completed a central primary fluidized bed dry scrubbing
-
-------
I
Plant F completed a courtyard primary fluidized bed dry scrubbing •
retrofit on one of its five potlines in May 1970, A total of 10
reactor-baghouse units were installed, along with supporting equip- |
ment, to replace three courtyard dry ESP-to-dual spray tower fume _
control units. Total system capacity is 400,000 acfm, and the ™
retrofit did not improve primary collection efficiency. There •
was no secondary control before or after retrofit. Total retrofit
capital cost was $1,772,000. This did not include the cost of g
removing the six spray towers. The three ESPs were left in
place because it was considered too costly to remove them. •
Plant G has 12 courtyard dual multic!one-to-quadruple spray I
tower primary control units and plans to install a primary courtyard
fluidized bed or injected alumina dry scrubbing retrofit on all six •
potlines by July 1978. As of January 1975, the retrofit capital •
cost estimate for the dry scrubbers was $28 million, the median of
three vendor preliminary estimates. The retrofit also includes im- I
proved primary collection efficiency by modifications to the plant's
1032 cells. These modifications included tighter sealing between the •
hood side shields and around the anode stems, replacement of the curved •
side shields with braced, flat side shields, and installation of new
end doors. Cost of these hooding modifications is estimated at $3 mil- I
lion for a total retrofit cost of $31 million. Table 6-33 shows the
I
combined emission reductions and costs for the hooding-dry scrubbing
retrofits. Plant G has no secondary control before or after retrofit.
6-122
I
I
I
I
-------
I
I
m ' Plant H plans to install a central primary control injected alumina
dry scrubbing retrofit on all five potlines by November 1976. Present
I controls on four of the five potlines are courtyard primary multi-
clone-to-spray tower units and 50 secondary cyclone scrubbers per
| potline along one edge of the potroom roof. Present controls on the
• other potline are primary central Venturis with no secondary controls.
™ The retrofit includes new hoods on all 700 cells which will improve
• primary collection efficiency to such a degree that the company plans
to abandon all secondary controls. As of February 1975, the total
g retrofit capital cost was estimated at $28,046,000, equivalent to
_ $216 per annual ton in Table 6-33. This figure does not include any
™ costs for dismantling existing equipment. In addition, plant H plans to
m install two parallel sets of spray cyclone scrubber-to-wet ESP
controls on its uncontrolled anode bake plant at a cost of
I $2,150,000.
• 6.3.4.2 Side-worked Prebake Cells
The Plant C retrofit is described in detail in Section 6.3.3,
• In April 1973, plant C completed a courtyard primary injected
alumina dry scrubbing retrofit on all three potlines. There are
• six control modules with a total system capacity of 2,160,000 acfm.
• Former control consisted only of 180 roof-mounted secondary spray
scrubbers. By necessity, the retrofit included the hooding of all
I 720 cells. The total retrofit capital cost of $14,300»000 included
the removal of 20 secondary scrubbers.
• 6-123
I
-------
I
Plant K plans to retrofit its one potline with a central _
primary injected alumina dry scrubbing system and to abandon the •
present spray screen secondary controls along the entire peak of I
the potroom roof. The retrofit also includes hooding all 90 cells and
oversizing the removal equipment to handle primary exhaust J
from an additional 48 cells that are part of a possible plant expan- —
si on. The total retrofit capital cost was estimated to be $4,250,000 •
in Harch 1975. The plant plans to abandon secondary control because •
they consider a projected capital cost of $56 per annual ton for water
treatment of their once- through scrubbing water to be economically ex- |
cessive. The before retrofit emission of 7.7 Ib F/ton Al is an average _
for the first five months of operation in 1974. The after- retrofit •
emission of 10.6 Ib F/ton Al is based on an average generation level •
of 53 Ib F/ton Al for the same five months and a projected
plant overall control efficiency of 79.86 percent. The actual emis- •
si on level will not be known until the retrofit has been completed in
the summer of 1975 and then operated for several months. Plant personnel |
are hopeful that emissions will average 6-7 Ib F/ton Al. •
6.3.4.3 Horizontal Stud Soderberg Cells
The Plant B retrofit is described in detail in Section 6.3.2. •
Former controls inert courtyard primary spray towers. The plant is •
installing fifteen 100,000 scfm and six 50,000 sefm courtyard pri-
mary spray tower- to-wet ESP units on the six potrooms comprising I
two- thirds of its capacity, and ten 100,000 scfm central primary
wet ESP-only units on the three potrooms conprising the other one- •
third. The former does not include improved primary collection while •
the latter does. Improved collection on the latter includes an in-
creased exhaust rate, new doors, and better sealing on 372 cells. I
6-124
-------
I
_ Estimated retrofit completion date is June 1975. There was no secon-
™ dary control before or after retrofit. An October 1974 total retrofit
• capital cost estimate of $19,300,000 does not include costs of removing
any of the 22 existing spray towers for the central retrofit.
• The Plant A retrofit is described in detail in Section 6.3.1.
The plant has installed a central primary dry scrubbing retrofit in
• * two locations, each having 18 reactor-baghouse units and handling
• two potroorns, or half the plant's capacity. For half the capacity,
the retrofit involves bypassing the 16 spray towers at the ends of the
I potrooms and improving primary collection efficiency on all 240 cells
by an increased primary exhaust rate. For the other half, the
| retrofit involves using the central ductwork of the existing cement
• blockhouse scrubbers and not improving primary collection efficiency.
* Total system capacity for the whole plant is 1,200,000 acfm. The
I1 retrofit was operational in September 1974. There was no secondary
control before or after retrofit. A December 1974 total retrofit
| capital cost estimate of $11,313,000 includes demolition costs for
_ half the retrofit. The bypassed spray towers ana a 25- by
• 100-foot building were torn down, but the cement blockhouse scrubbers
• were not.
• 6.3.4.4 Vertical Stud Soderberg Cells
Plant E completed a secondary retrofit in November 1970 and a
I primary retrofit in February 1972 on all five of its potrooms. The
secondary retrofit consisted of abandoning previously retrofitted
I roof monitor spray screen scrubbers and installing a new dormer-
. tunnel design that is shown in Figure 6-10, one dormer tunnel along
one entire edge of each potroom roof. The primary retrofit
I
I
6-125
-------
I
consisted of adding eight 12,000 acfm and four 6,000 acfm wet
ESPs downstream of 20 previously retrofitted courtyard bubbler- |
scrubbers. The ESP retrofit did not improve primary collection _
efficiency. Table 6-33 shows the combined emission reduction and •
costs for the dormer- tunnel and ESP retrofits. Retrofit capital •
costs were $4,155,078 and $1,662,701 for the secondary and primary
retrofits, respectively. The primary retrofit included removal of I
the plant's 20 mul tic! ones,
Plant M has ten potrooms, courtyard mul tic! one- to- •
ventuH primary controls and no secondary control. It has been •
developing a foam scrubber secondary control system. If this scrub-
ber proves too ineffective or costly, the plant will revert to In- I
stalling spray screen secondary controls. An EPA contract study
estimated that, in December 1973, roof mounted powered spray screen I
scrubbers would cost $20,688;000 or $115 per annual ton to reduce total •
fluoHde emissions to 1.8 Ib F/ton Al . There would be 60 scrubbers
and 60 fans per potroom, or 600 apiece for the plant. Total system I
capacity would be 25,800,000 acfm with a I1quid-to-gas ratio of 5
gallons per thousand acfm. The retrofit would also Include 20 recir-, •
culating pumps, 10 recirculating tanks, six miscellaneous pumps, and •
one clarlfier. The scrubber water would be lime treated. The con-
tractor estimated that final installed costs for other systems, such •
as a foam scrubber, would not vary more than about 30 percent from
that of the spray screen. A December 1973 annual Ized operating cost I
estimate of $1,723,000 1s equivalent to $9.57 per ton. •
6-126
I
-------
I
• 6.4 DESIGN, INSTALLATION AND STARTUP TIMES FOR RETROFIT CONTROLS
The emission control retrofit cases studied and described in
£ Section 6.3 have shown that the upgrading of fluoride emission controls
or the initiation of control for a primary aluminum plant is a major
• engineering undertaking. Such a project does not involve the instal-
• lation of one simple item of control equipment, but instead involves
complex controls which may be several in number. Associated with the
• controls are storage and surge tanks, conveyors, fans, and long lengths
of huge ductwork along with the necessary foundations, structural
I steelwork and electrical drive systems.
• Table 6-34 shows the approximate sequence of activities which are
necessary to design and install an improved air emission control system
• in a primary aluminum plant. The sequence of work outlined is not
necessarily normal, but it should apply to periods such as the summer of
| 1974, when structural steel had particularly long delivery time.
_ Obviously, such steel would be ordered as soon as possible—in fact,
even before the full requirement is known. Thus, some parts of item 5
• may not be firm until item 7 and item 11 are done. Similarly, it will
be understood that other items of Table 6-34 may overlap in time.
I Figure 6-21 illustrates that the activities in a big engineering
_ job—such as retrofitting controls to a primary aluminum plant—tend to
™ progress in a continuous, non-stepwise manner. This is because there is
• so much to do; at a given time, numerous items are in various stages of
design, procurement, and construction. The four curves in Figure 6-21
I show the typical progress for the named activites throughout
I
I 6-127
I
-------
I
Table 6-34. SEQUENCE OF MAJOR ACTIVITIES IN DESIGN AND CONSTRUCTION
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18..
19.
20.
21.
\Jt ft 4. I\ l_l!Jtu'%J.LV/** v WM » ' \V«— 1 V/l \ * *» 1 w ** •* >^ i £. i * v* * i \ j. i if 11 % i i \i-\ss i*.m\jt i i i_.* 1 1 * i
Process design and flow diagram.
Engineering flow diagram and preliminary plot plans.
Specification and procurement of major items such as dry scrubbers,
and fans. Long delivery items first.
Ductwork and piping arrangements, specification, and procurement.
Structural steel design.
Foundation design.
Specification of minor items, obtainable without complete drawings,
such as pumps and materials handling equipment.
Design of electrical starters, switchgear and distribution system.
Specification of instruments.
Receipt of certified dimension drawings of dry scrubbers, storage
tanks, conveyors, fans.
Dimension drawings for ductwork.
Release of foundation and structural steel drawings.
Start construction. Site preparation, necessary removals or
relocations will have already taken place.
Complete the pipe and ductwork takeoffs, and drawings for field
supports.
Release drawings and material listings for construction.
Complete underground installations.
Complete foundations.
Delivery of structural steel and major items of equipment.
Erect major items of equipment.
Install ductwork and conveyors.
Install piping.
6-128
1
1
1
1
•
1
1
1
1
1
1
1
1
-------
I
m Table 6-34 (continued). SEQUENCE OF MAJOR ACTIVITIES IN DESIGN AND
• CONSTRUCTION OF AIR EMISSION CONTROL FOR AN EXISTING PRIMARY ALUMINUM
* PLANT
I
22. Install electrical.
•i 23. Install instrumentation.
• 24. Startup.
25. Source testing and analytical.
I 26. Compliance with air pollution control regulations.
I
• the job. The relative positions of the curves vary with the actual job
and the graph is diagrammatic only. However, each line tends to approach
I linearity in the 25-75 percent completion interval. This figure shows
that process design usually continues into the early stages of procurement.
| Engineering also continues well into the construction period. For this
m reason, total time requirements are best estimated from experience and
cannot be derived by adding the time requirements for design, ordering,
I manufacture, delivery, installation and startup as can be done for one .
simple control.
| One important step that is almost wholly out of control of the
_ customer or the control official is the construction item delivery
™ time. Table 6-35 gives some historical delivery times for items which
'• are very important in installing emission controls at primary aluminum
plants. The historical variation is somewhat obscured because data
• extending back to the Korean war period (when deliveries were very
._ long) is not available. However, deliveries greatly increased
• from 1973 to 1974, and many lead times passed all previous
I
6-129
I
-------
LU
UJ
O CJ
o c csrr
a: a: 3:0
a. D_
S-
o
E
IB
C
O
in
41
0)
u
a
O
C
O
1X5 4J
4-1 U
C
o
01 S-
5- Q.
D.
(U C
S- O
u -Jj
(O J-
E +->
E wi
(O C
s_ o
Ol O
,
Q J-
4-»
I/)
• 3
i— -O
CM C
I '•-
S-
-------
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
z:
o
X*.
LU
h-S
O •>
oein
z I—
O Z
O «*
_l
O 0.
O =3
UJ 2E
o: i— i
or_i
SE «st
ua s:
L— 1 — 1
1-1 01
CL.
o a:
f i ^^
u.
yj i/j
1-1 O
^^
t^
>- z
Of O
LU O
>
1"— 1
_J
UJ
o
in
10
CU
JD
rfl
I—
10
jn:
s-
n>
a)
DC
1/1
a>
(U
in
ai
e
>,
OJ
OJ —
Q
*
3%
I
£
yi
o
er>
S
31
o
en
OJ
1-1
C
o
o
3
i-
C
O
o
> ^
f— S- +->
.- fl3 IO * — '
Hi -r- -0 O
k o c >
5 „ & 5 o
8 ? M ^ S
ir> « o " v]
A — » Z «t v |
^f CM CM CO OO CM CO
m co CM
tn f>
°V i T CM <*) r^
,_ l^» p-» «— <— ^
CM i— •—
O «*
7 T o
) (/> O ^ ^
S_ 0 C $- +-> 0) <1>
I 4J 3 fl -i- O i — I—
1 > a u_ < s: LU u-i
6-131
-------
I
bounds. Table 6-3E represents the experience of an aluminum company I
doing its own purchasing. Another company reports up to 52 weeks for
delivery of switchgear. 6' A contractor reports 61 weeks for blowers; |
62
and about 65 weeks for motors over 40 HP. Deliveries may depend •
partly upon quantity bought, continuity of business through the years,
and most-favored customer status. Fabrication and shipping consumes a •
significant fraction of the total time required to design and install
emission controls. |
The actual time in years that was required to add retrofit controls _
to eight aluminum plants is given in Table 6-36. Plant codes are the *
same as in Section 6.3. Except for plant F, the whole plant was retrofitted •
in each case. Only plants C, E, and H had secondary control and only
plant E improved its secondary control, at a cost of about 65 percent of |
its total retrofit expenditure. Plant B built and operated a pilot _
plant during two of the 4-1/2 years of retrofit activity. The completion •
time of 5-1/2 years for plant S includes 3 years for improved cell •
hooding and 3 years for dry scrubber installation. The 3 years for
improved hooding is due to a claimed economic advantage for modifying |
cells over the normal 3-year life of their cathode linings. Had plant G
so elected, the dry scrubber installation could have proceeded simultaneously •
with cell hooding improvements, reducing the completion time to about 3 •
years.
The actual time requirements shown in the last column of Table 6-36 I
are probably greater - on the average - than needed for enforcement
purposes. In spite of the large capital tied up, there is no return, •
and the usual economic incentive for haste in startup is lacking. Any •
interferences with production during installation of controls are
I
6-132
I
-------
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
O
O
o
I—I
to
CD _J
01 CL.
o s:
i
UJ c£
i—i >-
O "-•
•-« a:
H- D-
O
13
ce.
IS)
o
o
cn
cu
CD
C.
*!""
.n|i*j ji i
•r- C'wT
3 O $~
CT i- ^
,
4-J Ift
C >> C
(0 4*^ O
1— T- 4->
Q {J % — -*
r— >
res 5-
CT< >)
E -0 S-
»r« ' C ^3
•O ns E
O >>"^"
O C7) S- $-
^: c — o s- *-
CO >,0 0. JU
U S?J= 1 -g
to «/> -Q
"0 £ •— S~ 5
01^1- a> s-
>.S- CP XJ *i
2.O. O JQ f»
I 3 ^
O.Q. 26 *- ?^
E<^ C3
g g g
o o^ o
o o o
o o g
" ^** , "
^ !— I—
000
C3 O O
o o o
o m in
CM CM r—
O3 CQ
to Q- ex.
IE CO C3
02 <_> Q
..
CM
^*"~
1
CM
- .. .
4_
«3
T3
O
O
O)
>> «
S- "
Wet ESP-prima
i Dormer tunnel
o
o
o
o
o
00
LfC
o
CD
Q
£/>
>
UJ
CM
I
•—
t
E
•t—
1-
Q,
1
CU CU
xi c
jQ »f»
3 r—
i- -M
O O
10 O.
o
o
o
o
o
00
,__
o
CO
CM
ro
CQ
CJ
u_
CM
^^*
m
5_
•o
T3
C
(O
en
C
T3
0 >,
0 J_
JC (0
E
I
i
j Improved eel"
scrubbers-prl
o
o
o
*
o
o
o
r_
oo
, _ — -^... —
o
• o
o
o
in
CM
m
o.
0
0
CM
>,
•a
•Q
C
(O
C ^
T3 E
§r
4= O.
I
CU ft)
0X5
x>
™^I[J "?*l
(U &-
> o
O