Public Involvement

On July 22, 2002, EPA and the Massachusetts DEPjointly
issued a new proposed National Pollutant Discharge Elimi-
nation System (NPDES) Permit to Brayton Point Station
and opened a public comment period on the permit. The
agencies held information meetings on August 5 and 6, 2002,
in Somerset, Massachusetts and Bristol, Rhode Island, re-
spectively, to explain the draft permit and answer ques-
tions.  The agencies held public hearings in Somerset and
Bristol on August 26 and 27, 2002, respectively, to accept
comments on the draft permit. The comment period, origi-
nally scheduled to close on September 4, 2002, was ex-
tended to October 4, 2002.

During this 2 1/2 month comment period, EPA received
more than 150 comments from elected officials,  federal,
state and local government agencies, private organizations,
individual citizens and the permittee.  Careful consider-
ation was given to these comments in development of the
final permit.

EPA's response to these comments, published in  a docu-
ment of the same name, specifies which provisions of the
draft permit have been changed in the final permit and the
reasons for the change, and summarizes and responds to
all significant comments on the draft permit submitted dur-
ing the public comment period.  This document can  be
reviewed at:
        www.epa.gov/ne/braytonpoint
        For More Information

Call EPA toll free at 888-372-7341 and ask for
         the following extensions:
   Damien Houlihan
   Engineering Project Manager

   Phil Colarusso
   Biology

   Mark Stein
   Legal

   Angela Bonarrigo
   Community Relations
                    or call
81586
81506
81077
81034
     MA Department of Environmental Protection
      David Johnston, Deputy Regional Director
                 (508) 946-2708
             What Impact will this Permit have on
               Electricity Rates for New England
                            Consumers?
            Even after its upgrades, Brayton Point Station's three
            coal and one oil / gas units will continue to be capable
            of producing more than 1500 megawatts of electricity
            at full capacity, while remaining a low cost producer of
            electricity for New England's energy market.

            Using conservative (i.e., worst case) assumptions, the
            average household, using 500 KWh per month, would
            see long-term  monthly increases of $0.06 to $0.18 in
            electricity rates as a result of
            the construction of a closed-
            cycle cooling system.  The
            short-term  impacts of unit
            outages during the construc-
            tion period could result in a
            short-term rate effect of ap-
            proximately  $0.70   per;
            month, but only for  nine
            months.

                 For More Detailed Information

            The final requirements for Brayton Point Station's ther-
            mal discharges and cooling water withdrawal are
            stated in the Final NPDES permit issued to the plant.
            The permit, along with EPA's response to comments,
            is available for review at the following locations:
   Somerset
 Public Library
1464 County Street
  Somerset, MA
                                                                  Rogers
                                                               Free Library
                                                               525 Hope Street
                                                                 Bristol, Rl
   U.S. EPA
Records Center
1 Congress Street
  Boston, MA
   information is also available for review on the
              world wide web at:

        www.epa.gov/ne/braytonpoint

  All documents may be downloaded and printed.
       (Adobe Acrobat Reader is required)
                                                                              Brayton    Point
                                                                                                               Somerset,  MA
                                                                             Final National Pollutant Discharge Elimination System (NPDES) Permit    October 2003
                                                          EPA has developed a final permit for the Brayton
                                                          Point Station power plant together with the MA
                                                          Department of Environmental Protection (DEP) and
                                                          in close coordination with the Rl Department of
                                                          Environmental Management (DEM) to meet require-
                                                          ments of the Clean Water Act. This permit seeks to
                                                          substantially reduce the facility's impact on Mount
                                                          Hope Bay. Compliance with this permit will be  an
                                                          essential complement to broader public and pri-
                                                          vate efforts to restore and maintain the health of
                                                          Mount Hope Bay and the greater Narragansett Bay
                                                          ecosystem. These other efforts include fishing man-
                                                          agement, projects to improve sewage treatment,
                                                          abatement of pollution from combined sewer over-
                                                          flows, and scientific research.
                                                                                                                                                      Brayton Point Station is the largest industrial source
                                                                                                                                                      affecting Mount Hope Bay.  Based on the scientific analy-
                                                                                                                                                      ses to date, EPA, MA DEP and others have concluded
                                                                                                                                                      that stronger controls are needed on the power plant's
                                                                                                                                                      withdrawal of water from the bay and discharge of
                                                                                                                                                      heated water back to the bay in order to satisfy Clean
                                                                                                                                                      Water Act standards. These limits will help to protect
                                                                                                                                                      the bay and give the fishery a chance to recover.  The
                                                                                                                                                      technology exists for Brayton Point Station to both meet
                                                                                                                                                      the performance standards required by this permit and
                                                                                                                                                      continue to produce reliable,  inexpensive electricity
                                                                                                                                                      for New England.
                                                                                     Mount Hope Bay
                                                                            Winter Flounder Abundance and Flow
                                                                                        versus Year
                                                                                                              L_ w
                                                                                                              o g
                                                                         lei
                                                                                                                   600
                                                                                                                   500
                                                                  400
                                                                              300
                                                                              200
                                                                              100
                                                                                                                     1200
                                                                                                                     1000
                                                                                                                                                                       800
                                                                                                                                                                       600
400
                                                                                                                     200
   03
   Q
"•B.  flJ
1  °-
EE  »
c  .o

'«  O
•i-*
CO  c
   o
                                                                                                                                        Year
                                                                         Fish -X- Flow
                                                                        Fish populations declined by more than 87% after 1984 when Brayton Point Station began a
                                                                        45% increase in cooling water withdrawal from the bay.  (It should also be noted that the
                                                                        facility's thermal discharge increased by a similar percentage at that time). Despite decreased
                                                                        fishing, many species have shown no signs of recovery.  The above graph shows the decline of
                                                                        winter flounder relative to the increase in cooling water use. Similarly dramatic declines can be
                                                                        demonstrated for other fish species as well.	
Average annual losses of
fish eggs and larvae due
to existing cooling water
withdrawals at Brayton
Point Station include:

•    251 million
      winter flounder

•    11.8 billion bay
      anchovy

•    375 million
      windowpane
      flounder

•    3.5 billion
      tautog

-------
          Brayton Point Station s
      Impact  on Mount  Hope Bay
 Located in Mount Hope  Bay at the confluence of the
 Taunton and Lee Rivers, the Brayton Point Station power
 plant produces about 6% of the electricity consumed in
 New England.  In producing this electricity, however,
 Brayton Point Station destroys trillions of marine organ-
 isms each year and significantly alters the temperature
 of the bay.

 Each day, the station withdraws nearly one billion gallons
 of water from the bay and circulates it through the facil-
 ity to condense the steam used to produce electricity.
 The water is then discharged back to the bay at elevated
 temperatures of  up to 95° Fahrenheit. This "once
 through" cooling system  has contributed to the col-
 lapse of the Mount Hope Bay fishery in the following
 ways:

 •     Destroying trillions of organisms. Water
 taken from the bay by the facility contains trillions of
 organisms, including  billions  of fish  eggs and larvae.
 These organisms are pulled through (or "entrained")
 in the facility and killed by severe physical and chemi-
 cal impacts and extreme water temperatures. For ex-
 ample, 251 million winter flounder larvae, 3.5  billion
 tautog eggs and 375 million windowpane flounder eggs
 are harmed in an average year.

 Cooling water withdrawals also create a water velocity
 at the intake pipes which traps (or "impinges") many
juvenile and mature fish against the intake screens. For
 example, in 1999, more than 75,000 Atlantic Menha-
 den were killed during a month long impingement event.

 Altogether, trillions of organisms are lost to entrain-
 ment and impingement each year, including species of
 commercial and recreational importance, and forage fish
 and other organisms integral to the food web.

 •     Dramatically altering the water tem-
 perature in the bay. As a result of Brayton Point
 Station discharges of heated water, the temperature in
 the bay is about 1.5° Fahrenheit greater than other simi-
 lar water bodies locally.  This is a significant tempera-
 ture difference in a fragile ecosystem. Altering the natural
 temperature of the bay has degraded the habitat, mak-
 ing areas inhospitable to native fish species, disrupting
 normal fish migration, and undermining the balanced,
 indigenous community offish that should exist in Mount
 Hope Bay.
                                What Does EPA's Permit Require?
Consistent with the Clean Water Act, EPA is requiring thermal
discharge limits that protect the marine life that should thrive
in Mount Hope Bay. In addition, EPA is setting cooling water
intake flow limits so that Brayton Point Station's cooling sys-
tem reflects the best  technology available to minimize  the
facility's adverse environmental impacts.  The permit specifi-
cally requires Brayton Point Station to:

 •      Reduce total annual heat discharge to the bay by 96%,
from 42 trillion British Thermal Units (BTUs) a year to  1.7
trillion BTUs a year, and
 •      Reduce water withdrawal from the bay by approxi-
mately 94%, from nearly 1 billion gallons a day to 56 million
gallons a day. This flow requirement is consistent with well-
established closed-cycle cooling technology using wet,
mechanical draft cooling towers for generating units 1
through 4.

Compliance with these permit limits will eliminate annual
fishery losses by an estimated 94% and improve habitat
quality, thereby  helping to give the bay an opportunity to
recover.
                                                              Protecting Mount  Hope  Bay
While many federal, state and local efforts have been under-
way to protect Mount Hope Bay and the larger Narragansett
Bay estuary, Brayton Point Station has continued to operate
with nearly the same "once-through" cooling technology that
was installed almost 40 years ago. Requiring the power plant
to meet limits consistent with modern cooling system equip-
ment complements these other efforts, which include:

 •     Sewage treatment improvements in Fall River, includ-
ing a $115 million combined sewer overflow abatement pro-
gram, being implemented to meet state and federal water qual-
jty requirements.

        Strict commercial and recreational fishing limits have
 been imposed in Massachusetts and Rhode Island for Mount
 Hope Bay in an effort to help restore fish stocks. Mount
 Hope Bay, and most areas of upper Narragansett Bay, is closed
 to commercial trawlers.  In addition, recreational fishing  for
 winter flounder is closed for 10 months of the year. A small
 recreational fishing effort is  allowed for two months of  the
 year.
               •      At the regional level, the National Ma-
              rine Fisheries Service has spent $160 million
              in the last 10 years buying back fishing ves-
              sels and licenses from fishermen in the north-
              east to reduce fishing pressure on  ground-
              fish, including winter flounder. Moreover, ad-
              ditional stringent federal fishing restrictions
              are expected to be put in place next year.

               •      Enhancing  knowledge about  the
              Narragansett  Bay estuary  and implementing
              activities to protect and restore the estuary
              and its resources through the Narragansett
              Bay Estuary  Program,  which has spent  ap-
              proximately $15  million in federal and state
              matching funds on this effort since 1984.

 Brayton Point Station's cooling water system has contributed
 to the collapse of the fishery and  inhibited  its recovery, even
 as steps to reduce fishing pressure and improve  pollution
 controls are being taken to facilitate the bay's recovery.   Up-
 grading the facility's cooling  system with modern technolo-
 gies that cut water withdrawals and thermal discharges  will
 enable Brayton Point Station to reduce its  harmful effects on
 Mount Hope Bay while continuing to generate electricity for
 New England. These improvements are expected to allow
 the fishery to recover and restrictions on fishing to  be eased.

-------