EIA Technical  Review Guidelines:
Tourism Related Projects

            Volume I Part 2
    Example Terms of Reference
Regional Document prepared under CAFTA DR Environmental Cooperation
Program to Strengthen Environmental Impact Assessment (EIA) Review
 Prepared by CAFTA-DR and U.S. Country EIA and Tourism Experts with support from:

                                        <#***"%
US AID
                 USAID ENVIRONMENT AND LABOR     $
                 EXCELLENCE FOR CAFTA-DR PROGRAM  I
                    CENTBQAMEBICANA DE AMBIENIE Y OESASHOUO

-------
This document is the result of a regional collaboration under the environmental cooperation
agreements undertaken as part of the Central America and Dominican Republic Free Trade Agreements
with the United States. Regional experts participated in the preparation of this document, however, the
guidelines do not necessarily represent the policies, practices or requirements of their governments
and organizations.

Reproduction of this document in whole or in part and in any form for educational or non-profit
purposes may be made without special permission from the United States Environmental Protection
Agency (U.S. EPA), Agency for International Development (USAID), and/or the Central American
Commission on Environment and Development (CCAD) provided acknowledgement of the source is
included.

                                                   EPA/315R11003A July 2011

-------
      EIA Technical Review Guidelines:
      Tourism-Related  Projects
                        Volume  I  Part  2
              Example  Terms  of  Reference
The EIA Technical Review Guidelines for Tourism-Related Projects were developed as part of a regional
collaboration to better ensure proposed tourism-related projects undergoing review by government
officials, non-governmental organizations and the general public successfully identify, avoid, prevent
and/or mitigate potential adverse impacts and enhance potential beneficial impacts throughout the life
of the projects. The guidelines are part of a broader program to strengthen environmental impact
assessment (EIA) review under environmental cooperation agreements associated with the "CAFTA-DR"
free trade agreement between the  United States and  five countries in Central America  and the
Dominican Republic.

The guidelines  and example terms of reference were prepared by regional experts from the CAFTA-DR
countries and the United States in both the government organizations responsible for the environment
and tourism and leading academics designated by the respective Ministers supported by the U.S. Agency
for International Development (USAID) contract for the Environment and Labor Excellence Program and
grant with the  Central America Commission for Environment and Development (CCAD). The guidelines
draw upon  existing  materials from within and outside these countries  and  from international
organizations and do not represent the policies, practices of any one country or organization.

The guidelines are available in English and Spanish on the international websites of the  U.S.
Environmental  Protection Agency (U.S. EPA), the International Network for Environmental Compliance
and Enforcement (INECE), and the Central American Commission on Environment and Development
(CCAD): www.epa.gov/oita/   www.inece.org/   www.sica.int/ccad/  Volume 1 contains the
guidelines with a glossary and  references which track with internationally recognized elements of
environmental  impact assessment; Volume 2 contains Appendices with detailed information on tourism,
requirements and standards,  predictive tools, and international  codes; and Volume 1, part 2 contains
example Terms of Reference cross-linked to Volumes 1 and 2 for resort/hotel/condo developments,
concessions, and coastal and marine projects respectively for use by the countries as they prepare their
own EIA program requirements.
             -.ra-
                 USAID
USAID ENVIRONMENT AND LABOR
EXCELLENCE FOR CAFTA-DR PROGRAM
                              §3  CCAD

-------
[This page is intentionally blank.]

-------
Volume I Part 2 - EIA Technical Review Guidelines:                             EXAMPLE TERMS OF REFERENCE (TORs)
           Tourism
EXAMPLE TERMS OF REFERENCE (TORs)


Terms of Reference are used by countries to describe both general and specific requirements for the
preparation of an environmental impact assessment,  in this instance tailored to proposed projects for
tourism.  Volume 1, Part 2 contains example Terms of Reference (TORs) cross-referenced to Volumes 1
and 2 of the "EIA Technical Review Guideline for Tourism Projects".  The Example Terms of Reference
are printed separately to facilitate use by countries as they prepare their own EIA program requirements
for tourism projects.

Three terms of references (TORs) are provided below as examples for countries to use directly or draw
upon  for  their own TORs  and  guidelines for  tourism projects,  including:   1. Hotel  and  Resort
Developments, 2. Concessions, and 3. Marine and Coastal Tourism.  For each there are two sections to
the TOR:   PART A is an  overview describing  general  expectations for the  preparation of the
environmental impact assessment. PART B addresses detail related to the specific type  of project. All
sections are important guidance for preparation of adequate EIA documents for tourism projects, and
the TORs are cross-referenced to relevant sections of the Guidelines. The three terms of reference are
designed to be applied in combination based on the nature of the proposed project and expectations for
related tourism activities whether or not the related activities are to  be developed,  owned and/or
operated by the same  parties.  For example, resorts located on or near the coast are designed so that
tourist may avail themselves of recreational activities along the coast and it is therefore assumed that it
is relevant to assess the coastal impacts of the foreseeable uses of the coast by patrons of the  resort.
Similarly, if a resort is proposed but is intended to utilize an existing or new proposed golf course, those
impacts should be addressed within the same EIA, and if a resort or hotel complex is located to support
eco-tourism at an adjacent national or local protected area, even if the resort itself does not sponsor
trips to explore those resources, those impacts must be taken into account. The test for relevance is the
"but for" test, whether the  proposed project would  be  proposed and viable  in the absence of these
related activities and whether it is foreseeable that the resources can be affected.

The details in the example TORs address each element of the EIA analysis and documentation  including
what should be included in the description of the proposed project and alternatives;  environmental
setting;  assessment of impacts; mitigation  and monitoring measures; an environmental management
plan; a signed commitment  statement; and key supporting materials, each aligned with the physical,
biological and social-economic-cultural environments.

1. TERMS OF REFERENCE FOR HOTEL AND RESORT DEVELOPMENT
       A. OVERVIEW                                                    3-4
       B. DETAILS FOR HOTEL/RESORT DEVELOPMENT PROJECTS             5-28

2. TERMS OF REFERENCE FOR CONCESSIONS
       A. OVERVIEW                                                    29-30
       B. DETAILS FOR CONCESSIONS PROJECTS                            31-52

3. TERMS OF REFERENCE FOR MARINE AND COASTAL TOURISM
       A. OVERVIEW                                                    53-54
       B. DETAILS FOR COASTAL AND MARINE DEVELOPMENT PROJECTS      55-76
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM

-------
Volume I Part 2 - EIA Technical Review Guidelines:
             Tourism
EXAMPLE TERMS OF REFERENCE (TORs)
[This page is intentionally blank.]
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM

-------
 Volume I Part 2 - EIA Technical Review Guidelines:                            1 EXAMPLE TERMS OF REFERENCE (TOR)
	Tourism	HOTEL/RESORT DEVELOPMENTS


 1  TERMS OF REFERENCE (TOR) FOR HOTEL/RESORT DEVELOPMENTS

 A. OVERVIEW
 These terms of  reference (TOR) describe the minimum  requirements  for the  preparation of the
 Environmental Impact Assessment (EIA) for proposed hotel and resort developments.  Both the TOR and
 the cross referenced "EIA Technical Review Guidelines for Tourism Projects" should be used to establish
 minimally  acceptable conditions for satisfying the requirement to submit an EIA.  There  are three
 different TORs for tourism projects.  Part A, Overview, is common to all three TORs but Part B  is tailored
 respectively to: 1 Hotel and Resort Developments, 2. Concessions, and 3.  Marine and Coastal Tourism.
 The three TORs are structured to facilitate mixing and matching as appropriate to the purpose and need
 for a  proposed project and alternatives.

 The basic format for the EIA document that should be followed is:
           •   Table of Contents
           •   Acronyms and Abbreviations
           •   Executive Summary
           •   General Information
           •   Project and Alternatives Description
           •   Environmental Setting
           •   Assessment of Impacts
           •   Mitigation and Monitoring Measures
           •   Environmental Management Plan
           •   Commitment Statement
           •   Annexes

 In general, the EIA must identify and address:

 •  Applicable  environmental  standards,  norms,  and requirements set forth at the international,
    national, regional and/or local  levels including those designed to meet the objectives of resource
    management and/or  land use plans that may be in effect in  and around the jurisdiction(s) in which
    the proposed project is located. In the absence of such standards, the EIA should establish a set of
    benchmarks that can  be used in the analysis and selection of an alternative.  The Guidelines identify
    standards in use by various countries and international organizations in Appendix C.

 •  Public/Stakeholder concerns related to impacts in and around the proposed project and alternatives
    at least for stakeholders within the geographic scope of potential impact.  The project proponent
    should document specific steps taken to  engage the public and other stakeholders,  and engage
    these publics  as early as possible before undertaking to prepare the EIA. Concerned  publics include:
    local governments, persons  living and working in the vicinity of the  project, those with interests in
    resources that may be affected i.e., indigenous  peoples, and those concerned about protected areas
    and  prime agricultural lands. A summary of public outreach activities, audience, number of persons,
    organizations involved, concerns  raised,  responses  to comments  and actual copies of written
    comments received should be included in the Annex.

 •  All  relevant plans  related to the proposed tourism project, for example, engineering and site
    preparation plans, operations and  decommissioning/closure, environmental management,  and
    mitigation in whatever form these may take.

 •  All phases of the project from feasibility studies to site preparation to operations to closure and also
    plans to expand capacity at the current or adjacent sites.
 CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM

-------
 Volume I Part 2 - EIA Technical Review Guidelines:                             1 EXAMPLE TERMS OF REFERENCE (TOR)
	Tourism	HOTEL/RESORT DEVELOPMENTS

 •  Alternative  approaches to  meeting the  purpose and need  for  the  proposed  tourism project,
    including siting,  designing,  constructing,  operating  and closing the  project firstly to  avoid  and
    prevent, or  secondly  to  reduce  or  minimize adverse  or  improve beneficial environmental or
    socioeconomic impacts. The EIA should assess as appropriate the impacts of a range of reasonable
    and technically feasible alternatives as well as the proposed project. The alternatives to the project
    must include a "no action"  alternative, as well as consideration  of best practices that may not
    otherwise have been incorporated in the proposed project.  Other alternatives should be developed
    as needed to avoid or minimize significant adverse impacts associated with the proposal.

 •  Direct, indirect and cumulative impacts and their significance level.

 •  Uncertainty and how that uncertainty will be addressed through monitoring and contingency plans
    as may be needed to reduce risk of adverse impacts in the future.

 •  Specific commitments, including who is responsible, what  will be done, when and how it will be
    monitored, reported and audited to confirm that commitments are met.

 Finally, a  key part of the TOR is obtaining a legally binding commitment from the project proponent that
 the approved  EIA  will  be implemented  as  presented.   Such  a commitment  adds to the legal
 enforceability of the outcomes of the EIA process.
 CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM

-------
 Volume I Part 2 - EIA Technical Review Guidelines:                               1 EXAMPLE TERMS OF REFERENCE (TOR)
	Tourism	HOTEL/RESORT DEVELOPMENTS



 B.  DETAILS  FOR HOTEL/RESORT DEVELOPMENT PROJECTS


 0   Table of Contents
     A general Table of Contents for the Environmental Impact Assessment (EIA) shall be provided. The
     Table of Contents shall be organized in such a manner as to facilitate the use of the EIA by reviewers
     and project implementers. ElAsfor larger projects should have a more detailed Table of Contents than
     those for smaller projects. At a minimum, the Table of Contents shall include the following:
     •   Acronyms and Abbreviations
     •   Executive Summary
     •   General Information
         o   Objectives and Justification
         o   Project Proponents
         o   Project Team
         o   Legal and Regulatory Framework
     •   Project and Alternatives Description
     •   Environmental Setting
         o   Physical Environment
             •   Geologic Resources
             •   Soil Resources
             •   Water Resources
             •   Air and Climate
             •   Noise and Vibration
             •   Aesthetic Resources
         o   Biological Environment
             •   Vegetation/Flora
             •   Aquatic and Terrestrial Wildlife/Fauna
             •   Ecosystems: Terrestrial, Wetlands, Aquatic, Marine
             •   Endangered or Threatened Species and Habitat
             •   Protected Areas
         o   Social-Economic-Cultural Environment
             •   Socio-Economic Conditions
             •   Infrastructure
             •   Cultural, Archeological, Ceremonial and Historic Resources
             •   Land Use
     •   Assessment of Impacts to resources described in the Environmental Setting
     •   Mitigation and Monitoring Measures
     •   Environmental Management Plan
         o   Overview of Environmental Management Plan Organization and Policy
         o   Project-wide Mitigation Plan
         o   Project-  wide Monitoring Plan
         o   Management of Other On- or Off-Site Pollution Controls and Infrastructure
         o   Contingency Plans
             •   Performance-related Contingency Plan
             •   Natural Disaster Risk Response Plan
             •   Other Risk Response Plans
     •   Signed  Commitment Statement
     •   Annexes
         o   Public Consultation
             •   Public Consultation Plan
             •   Summary of Public Outreach Activities
             •   Summary of Responses to Comments
             •   Copies of Written Comments
         o   Technical Supporting Materials
             •   Maps and Plans, in the sequence mentioned in the EIA document
             •   Charts and Figures
             •   Details about predictive modeling used, calculations and assumptions
             •   Special Studies
         o   References
 CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM

-------
Volume I Part 2 - EIA Technical Review Guidelines:
              Tourism
1 EXAMPLE TERMS OF REFERENCE (TOR)
      HOTEL/RESORT DEVELOPMENTS
1   Acronyms and Abbreviations
    All acronyms and abbreviations used in the EIA must be clearly and succinctly defined and described in
    this section.  This will relieve the reader of the need to search for the first occurrence of a word and the
    citing of the acronym or abbreviation in the text.
    Executive Summary
    A general summary of the EIA shall be provided in this section. The summary shall be written using a
    vocabulary that can be easily understood by the public.  It shall include at least the following
    information about the project from the EIA:
        Objectives and Justification
        Location
        Project Proponents
        Project Description
        Other Project Alternatives
        Environmental Setting
        Evaluation of Impacts
        Mitigation and Monitoring Measures
        Environmental Management Plan
        Issues raised by stakeholders and any outstanding issues
3   General Information

    3.1 Objectives of and Justification for the Proposed Project
3.1.1  Objectives: A statement of the general and specific objectives (purpose) of the
      proposed project, including whether it is a new project, an expansion of an
      existing project (e.g., increase in land area or increase in visitor capacity) or
      modernization of an existing operation.
3.1.2  Justification for the Project: Provide a justification for the proposed project
      (need) highlighting the benefits to surrounding communities and economic
      development of the region and country.

    3.2 Project Proponents
3.2.1  Names, addresses, telephone numbers, and applicable legal documentation of
      proponents (including developers, major equipment  suppliers if part of project
      team, shareholders and providers of financing, and representatives).
3.2.2   Names and contact information for responsible parties within the organization.
3.2.3   Financial viability of the company (including a certified banking statement
       indicating that the company is financially stable and reputable).
3.2.4   Bonding requirements and proof of ability to meet bonding requirements
       sufficient to cover the anticipated costs of environmental management during all
       phases, as well as the costs, by a third party, of decommissioning and long-term
       post-closure liabilities associated with the project.

    3.3 Project Team
    This section shall provide information on the multidisciplinary team that prepares the EIA.  The types
    of professionals included in the team shall be appropriate to the type of project and the type of
    environment in which the project is located and may include (but not be limited to) engineers,
    architects, biologists, geologists, hydrologists, air quality experts, archeologists, anthropologists,
    sociologists and economists. The information provided for each member of the EIA project team
    includes the following:
3.3.1  Names, addresses and registry numbers of contractors.
3.3.2   Names, contact information, qualifications and registry numbers of key
       personnel involved in the study; as well asan affidavit indicating their area of
       participation.
3.3.3   List of professionals/experts participating in the EIA, their areas of expertise,
       degrees, experience, professional registrations and stamps, seals and signatures.

    3.4 Legal and Regulatory Framework
    This section of the EIA shall define the legal framework under which the EIA is being completed listing
    and summarizing requirements or alternatives used as benchmarks, and evidence of non-applicability
    or compliance including:
3.4.1  Information that  demonstrates rights and access:
               C.2 Documentation of
                  Purpose and Need
               C.3.1 General
                  Information


               G.6 Financial
                  Assurance
               C.3.1 General
                  Information
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM

-------
Volume I Part 2 - EIA Technical Review Guidelines:
              Tourism
1 EXAMPLE TERMS OF REFERENCE (TOR)
      HOTEL/RESORT DEVELOPMENTS
   3.4.1.1   Ownership with written authorization
   3.4.1.2   Governmental authorization (if required)
   3.4.1.3   Period of lease/permit/concession agreement
   3.4.1.4   Maps showing the lease/permit/concession area
3.4.2  Applicable environmental standards, norms and requirements set forth at the
       international, national, regional and/or local levels
   3.4.2.1   In the absence of such standards, identify a set of benchmarks used in the
             analysis
3.4.3  Required regulatory approvals and/or permits for all stages and their status
3.4.4  Applicable land use requirements (demonstrate conformity and compliance with
       applicable plans)
3.4.5  Applicable tourism strategies and plans - national, regional, and local
3.4.6  Applicable natural resource management or protected area management plans
       and responsible agency(ies) (demonstrate conformity and compliance with all
       applicable plans)

4    Project and Alternatives Description
     The project proponent shall submit a full description and location of the proposed project and
     reasonable alternatives including ancillary facilities and operations such as the camp/housing for
     construction and operation phases, borrow and disposal areas, sanitary services, waste disposal and
     transportation infrastructure, etc. as addressed through 4.1 to 4.3 below. It shall include at a
     minimum:

     4.1  Location
     The general location of the project and associated activities in terms of:
4.1.1  Political-administrative location (region, district, town  or other relevant political-
       administrative units) with accompanying location map
4.1.2  Means of site access - i.e., by air, river, road, train or vehicle
4.1.3  Latitude and longitude of project area
4.1.4  Maps of project area at a scale of no less than 1:50,000 or as required by the
       regulatory agency
   4.1.4.1   Project plat plan and location on a fold-out 11" X 17" page.
   4.1.4.2   Indicate the project area and the direct and indirect areas of influence for
             the physical, biological  and social-economic-cultural impacts
   4.1.4.3   All drawings should present scale and key coordinates or benchmarks as
             latitude/longitude, Universal Transverse Mercator (UTM) coordinates, or
             local survey plate that can be cross-referenced to  latitude/longitude or
             UTM coordinates
4.1.5  Has the area of the project ever been a tourist destination before?
   4.1.5.1   If so, show other tourist facilities in the area on  the maps, including those
             under construction and, if known, those in the design phase

     4.2  Summary of Proposed Project and Alternatives
     All project alternatives that are reasonable and feasible and meet the purpose and need for the
     proposed project shall be identified, summarized in this section, and evaluated in the EIA as
     appropriate. In addition to the proposed project, such alternatives include alternative locations,
     alternative site configuration of elements of the project, alternative size, and alternative plans for
     construction, operation and decommissioning of the project including best practices that may avoid
     and/or reduce the adverse impacts to the physical, biological or social-economic-cultural
     environments.

     If the project area or the buffer zone of the project area for an alternative is in an ecologically fragile
     are, the description of the alternative must include a clear justification for not opting for another site.
     Identify which alternatives will be carried through the analysis in the  EIA and the basis for that
     decision.

     4.3  Project and Alternatives Details
     The EIA shall provide specific project details for the proposed project and each alternative as identified
     in subsections 4.3.1 through 4.3.8. The level of detail presented shall be the same for the proposed
     project and each alternative evaluated. The following project details shall be provided:
4.3.1  Type and nature of the project
   4.3.1.1   Type (resort, hotel, camping, day use)
   4.3.1.2   Overview of all proposed facilities and activities and their relationship
                C. Project and
                   Alternatives
                   Description
                C.3.2 Overall Project
                   Description
                   Information
                C.3.5 Maps, Diagrams,
                   Site Design and Plan
                C.3.2 Overall Project
                   Description
                   Information
                C.3.4 Project Details

                C.3.5 Project
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM

-------
Volume I Part 2 - EIA Technical Review Guidelines:
             Tourism
1 EXAMPLE TERMS OF REFERENCE (TOR)
     HOTEL/RESORT DEVELOPMENTS
   4.3.1.3   A detailed drawing showing access points, layout of all project
            components including on-site roads, walkways and paths, existing
            structures, topography and natural features such as water bodies,
            wetlands and geologic structures
   4.3.1.4   A summary table showing the type, quantity and size of each component
   4.3.1.5   Expected life of operation
   4.3.1.6   Anticipated use: maximum, minimum and average by month and season
            for:
            • Day use
            • Overnight stays
   4.3.1.7   Recreational, leisure and adventure uses by visitors  of surrounding natural
            and cultural resources
            • Type of use (type of activities, motorized or non-motorized, etc.)
            • Anticipated use (maximum, minimum and average by month and
              season)
4.3.2  Principal project facilities
       Location and design information - primary material of construction (wood, brick,
       stone, etc.), layout and dimensions. Design drawings should be provided for
       each facility, including:  Plan (overhead view), Elevations (front view), Profiles
       (side view) and Sections.
   4.3.2.1   Hotel (including cabins, cabanas and other overnight visitor quarters)
            • Number of rooms by:
                o  Structure (if more than one structure will house rooms)
                o  Number and types of beds (single or double  occupancy beds)
                o  In-room or shared bath/toilet facilities
                o  Other in-room facilities (kitchens, kitchenettes, pools, jacuzzies,
                   etc.)
            • Locations, sizes and types of common bath/toilet  facilities
            • Reception area
            • Hallways, causeways, stairs, elevators, etc.
   4.3.2.2   Restaurant(s) and bar(s)
            • Seating capacity
            • Hours of service
            • Kitchen facilities
   4.3.2.3   Conference center
            • Number and size of meeting rooms
            • Locations and sizes of toilet facilities
            • Hallways, causeways, stairs, elevators, etc.
   4.3.2.4   Entertainment venue (indoor or outdoor)
            • Size and seating capacity
            • Locations and sizes of toilet facilities
   4.3.2.5   Shopping area (mall, arcade, craft market, etc.)
            • Number and size of stores or booths
            • Locations and sizes of toilet facilities
            • Hallways, causeways, stairs, elevators, etc.
   4.3.2.6   Camping
            • Number, type (tent or recreational vehicle) and sizes of sites
            • Site ammenities (tables, benches, barbeque, fire pits, electical hookups,
              etc.)
            • Common facilities
                o  Reception/office
                o  Common room(s)
                o  Bath/toilet facilities
                o  Water taps
                o  Sewage dump stations (for recreational vehicles)
   4.3.2.7   Swimming pool(s)
            • Size (dimensions, water capacity)
            • Water treatment
            • Bath/toilet facilities
                 Alternatives
               C.3.8 Hotel, Resort and
                  Restaurant Facilities
               Table C-3
               C.3.8 Hotel, Resort and
                  Restaurant Facilities
               Table C-3
               14.2.3 Restaurants
               C.3.8 Hotel, Resort and
                  Restaurant Facilities

               13.8 Hotel, Resort and
                  Restaurant Facilities
               C.3.8 Hotel, Resort and
               Restaurant Facilities
               C.3.8 Hotel, Resort and
               Restaurant Facilities
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM

-------
 Volume I Part 2 - EIA Technical Review Guidelines:                                1 EXAMPLE TERMS OF REFERENCE (TOR)
	Tourism	HOTEL/RESORT DEVELOPMENTS

    4.3.2.8   Gym/Exercise room
             • Size
             • Types of equipment
             • Bath/toilet/sauna/steam room/massage facilities
    4.3.2.9   Athletic courts (tennis, basketball, raquet ball, etc.)
             • Types, numbers and sizes
             • Surface  material
             • Fences
    4.3.2.10  Golf course
             • Number of holes
             • Length,  width and layout of each fairway (included maintained ruff)
             • Size and location of each tee, green and hazard
             • Vegetation (tees, fairways, roughs, greens, landscaping, undisturbed
               [natural])
             • Cart  paths
                 o  Widths and layout
                 o  Surface material
                 o  Erosion control
             • Vegetative management
                 o  Irrigation (including grey water systems if applicable)
                 o  Fertilization
                 o  Pest control
             • On-site  support facilities (clubhouse, cart storage, cart repair,
               equipment storage, toilets, bar and/or restaurant [include in 4.3.2.2],
               etc.)
    4.3.2.11  Dock for visitor arrival or recreational activities
             . Types of uses                                                         C9 Marme and Coastal
             • On-site  facilities (equipment storage, toilets, bar and/or restaurant        Table C-5
               [include in 4.3.2.2], etc.)
    4.3.2.12  Dredging (if applicable)
             • Legal authorization for the dredging
             • Name of water body to be dredged                                     C.4.2.2 Dredging Waste
             • Dimensions of area to be dredged
                 o  Map showing extent of dredging operations
                 o  Longitudinal and transversal cross-sections of the area to be
                    dredged
             • Operation description
                 o  Frequency
                 o  Operational hours
                 o  Time table for dredging
             • Equipment Roster, specifying type and quantity by: size, motor size, and
               fuel requirements for each type of dredging equipment
    4.3.2.13  Developed beach
             • Beach uses
             • On-beach structures (recreational equipment rental/storage, bath/toilet
               facilities, bar, restaurant [include in 4.3.2.2] lifeguard towers, sun
               shades,  etc.)
             • Breakwaters and shoreline erosion protection
    4.3.2.14  Walking trails
             • Widths  and layout
             • Surface  material
             • Erosion  control
 4.3.3  Onsite support facilities
        Location and design information - primary material of construction (wood, brick,
        stone, etc.), layout and dimensions.  Design drawings should be provided for
        each facility,  including: Plan (overhead view), Elevations (front view), Profiles
        (side view) and Sections.
    4.3.3.1   On-site walkways
             • Widths  and layout

 CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM

-------
Volume I Part 2 - EIA Technical Review Guidelines:
             Tourism
1 EXAMPLE TERMS OF REFERENCE (TOR)
     HOTEL/RESORT DEVELOPMENTS
            • Surface material
            • Lighting (if applicable)
            • Erosion control
   4.3.3.2   On-site laundry (number and size of washing machines and dryers and
            other equipment)
   4.3.3.3   Staff housing
            • Number of rooms by:
                o  Structure (if more than one structure will house rooms)
                o  Number and types of beds (single or double occupancy beds)
                o  In-room or shared bath/toilet facilities
                o  Other in-room facilities (kitchens, kitchenettes, pools, jacuzzies,
                   etc.)
            • Locations, sizes and types of common bath/toilet facilities
            • Cafeteria [include in 4.3.2.2],
            • Common areas
            • Hallways, causeways, stairs, elevators, etc.
   4.3.3.4   Storage areas and warehouses
            • Locations
            • Sizes
            • Materials to be stored
   4.3.3.5   Parking lots
            • Locations
            • Sizes
            • Lighting
            • Materials (permeability)
   4.3.3.6   Repair shops
            • Activities
            • Locations
            • Sizes
   4.3.3.7   Fuel stations
            • Commercial or for operator use only
            • Locations
            • Number, size and  configuration of tanks (buried or above ground, leak
              protection, etc.)
   4.3.3.8   Electrical energy
            • Consumption, including energy conservation measures
            • Source-offsite
                o  Transmission lines (if necessary)
                o  Substation (if necessary)
            • On-site power generation power
                o  Type
                o  Emissions and noise controls (if applicable)
            • On-site distribution (routes, overhead or buried)
   4.3.3.9   Water supply
            • Requirements (m3/day), including conservation measures
            • Rights
            • Sources
            • Treatment
            • Distribution
   4.3.3.10  Waste handling and disposal
            • Sewers
            • Wastewater treatment
                o  Quantity
                o  Type
                o  Discharge
            • Solid waste
                o  Quantity (kg/day and m3/day), including waste reduction
                   measures
                o  Collection
               Table C-ll
               C.4.1 Water and
                 Sanitation Facilities
               Table C-6
               Table C-8
               C.4.2 Solid and
                  Hazardous Waste
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                       10

-------
Volume I Part 2 - EIA Technical Review Guidelines:
             Tourism
1 EXAMPLE TERMS OF REFERENCE (TOR)
     HOTEL/RESORT DEVELOPMENTS
                o  Separation (if any)
                o  Disposal
   4.3.3.11  Green spaces/landscaping
            • Vegetation types
            • Vegetative management
                o  Irrigation (including grey water systems if applicable)
                o  Fertilization
                o  Pest control
   4.3.3.12  Fencing
4.3.4  Access and transportation
   4.3.4.1   Roads
            • Identify all new and existing roads to be used (including closed roads
              that will be reopened, if applicable)
                o  Traffic volume, operating speeds and trip times
                o  Closed roads that will be reopened
            • Detailed information on any access, on-site and recreational activity
              roads to be constructed or upgraded
                o  Location
                o  Timing of construction
                o  Road surface and shoulder width and barriers
                o  Grade
                o  Construction methods including clearing and grubbing
                o  Construction materials
                o  Compaction
                o  Stream and wetland crossings and associated designs
                o  Animal crossings
                o  Sedimentation and erosion prevention and control structures and
                   practices
                o  Stabilization methods for cuts and fills
                o  Typical elevations for each type and situation of road displaying
                   construction materials, levels of compaction and erosion and
                   sedimentation features
                o  Location and size (area and volume of material) of borrow pits
                o  Lighting (where applicable)
                o  Operation
                o  Closure plan (if applicable)
                o  Traffic volume, operating speeds and trip times
            • Dust control for construction and operation
            • Maintenance
            • Roster for construction and maintenance equipment, specifying type
              and quantity by size, motor size, and fuel requirements
   4.3.4.2   Other transport systems (if applicable)
            • Airstrip
                o  Length and width
                o  Surface material
                o  On-site facilities
            • Rail transport - Same as for Roads with the addition of:
                o  Tightest curves
                o  Track construction materials
                o  Turnouts and sidings
                o  Railroad communications and signaling
            • Waterways
                o  Location, design, construction and operation of docks
                o  Rosters of boats, specifying type and quantity by: size, motor size,
                   and fuel requirements
                o  Maintenance
4.3.5  Best Practices
        Description of standard best  practices to be incorporated into the project.
4.3.6  Construction phase and timetable
               Table C-9
               C.3.7 Transportation:
                  Roads, Pathways,
                  Air Strips, and Boat
                  Facilities
               Table C-2
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                       11

-------
Volume I Part 2 - EIA Technical Review Guidelines:
             Tourism
                                                                 1 EXAMPLE TERMS OF REFERENCE (TOR)
                                                                      HOTEL/RESORT DEVELOPMENTS
                                                                                  C.3.6 Details on
                                                                                     Construction
                                                                                     Procedures
                                                                                  Table C-l
4.3.6.1   Schedule for each phase of construction for all project and ancillary
         facilities (including temporary structures) including, but not limited to:
         • Mobilization
         • Road construction and improvements
         • Land clearing
         • Blasting
         • Erosion and sediment control
         • Excavation and subgrade preparation
         • Foundation preparation
         • Concrete work
         • Construction or installation of each project facility
         • Stabilization of disturbed areas
4.3.6.2   A GANTT or critical path management chart for the entire project, from
         start to finish
4.3.6.3   Borrow and fill material
         • Locations from which fill material will be sourced
         • Locations where fill material will be placed on-site
         • Locations where fill and other construction material will be temporarily
           stockpiled/stored
         • Borrow and spoil disposal
4.3.6.4   Key areas (related to environmental sensitivity/importance) that will
         remain undisturbed during construction (waterways, wetlands, forested
         areas and other "green space," etc.)
4.3.6.5   Erosion control structures such as:
         • Temporary diversions for waterways
         • Erosion control barriers
4.3.6.6   Equipment
         • Equipment Roster, specifying type and quantity by size, weight, motor
           size, and fuel requirements for each piece of equipment or machinery
           used in each activity
         • Transportation mobilization and mobilization frequency
         • Machinery and equipment mobilization routes to be used, as well as the
           features of the ways on which they will be transported, including a map
           of routes, as applicable, and mobilization.
4.3.6.7   Labor during construction
         • Number and type of employees (by local hire and non-local hire) by field
           of expertise
         • Days per week
         • Hours per day
         • Shifts per day
4.3.6.8   Raw materials to be used for construction
         • Give a complete list of the  raw materials and construction materials to
           be used,  indicating the amounts per day, month, and the storage means
         • Include an inventory of chemical, toxic or hazardous substances, active
           elements, sites and storage means, safety aspects regarding
           transportation and handling and any other relevant information
4.3.6.9   Construction camp (if applicable)
           Description of the camp including but not limited to:
         • A map showing all facilities at  a legible scale appropriate to the size of
           the project
             o  Buildings by type (use) and size
             o  Roads
             o  Electrical transmission lines and/or substation
             o  Drainage
         • Water supply and distribution
             o  Distribution system
             o  Use (m3/day)
             o  Rights
             o  Sources
                                                                                  C.6 Manpower and
                                                                                     Local Purchases
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                       12

-------
Volume I Part 2 - EIA Technical Review Guidelines:
             Tourism
                                                                     1 EXAMPLE TERMS OF REFERENCE (TOR)
                                                                           HOTEL/RESORT DEVELOPMENTS
                                                                                    C.6 Manpower and
                                                                                       Local Purchases
            • Waste handling and disposal components
                o  Sewers
                o  Wastewater treatment
                o  Solid waste facilities
            • Energy generation and use requirements
            • Closure or transition from construction camp to onsite employee
              housing
   4.3.6.10  Decommissioning of temporary structures including measures for
            returning the area to pre-construction features
4.3.7  Operation phase
   4.3.7.1   Description of how the project would operate (seasonally, monthly, daily,
            hourly, as appropriate)
   4.3.7.2   Operation information
            • Roster of equipment and machinery to be used during operation,
              specifying type and quantity by size, weight, motor size, and fuel
              requirements for each activity
            • Labor during operation
                o  Number and type of employees (by local hire and non-local hire)
                   by field of expertise
                o  Days per week
                o  Hours per day
                o  Shifts per day
            • Overall energy requirements and sources
            • Raw materials to be used for  operation
                o  List of the raw materials to be used, indicating the amounts per
                   day, month, and the storage means
                o  Inventory of chemical, toxic or hazardous substances, active
                   elements, sites and storage means, safety aspects regarding
                   transportation and handling and any other relevant information
4.3.8  Closure and decomissioning plan
      If it becomes clear that closure will be required, or when the project nears the
      the end of its service life, the project operator shall contact the proper regulatory
      agency(ies) to obtain the environmental guidelines to carry out the closure or
      decommissioning.
   4.3.8.1   The project description shall include at least a general Restoration and
            Closure Plan, recognizing that terms of closure may be very different when
            this phase approaches
   4.3.8.2   The description of restoration measures should include the size of the area
            to be restored as well as concurrent, temporary and final restoration
            measures to be used and their schedules.  For each measure include:
            • Area to be addressed
            • Timing and schedule for executing measures
            • Equipment and structure removal or conversion
            • Remedial measures, including success indicators and  contingency
              measures if initial efforts are unsuccessful

5   Environmental Setting
    Based on information available from the literature, government and special studies or other sources,
    the EIA shall provide information on environmental setting for the different types of physical,
    biological and social-economic-cultural environments for the current situation, important trends and
    predicted situation in the absence of the proposed project. All sources of data must be cited in the EIA
    when and where they are used. Indicate the direct and indirect and cumulative impact areas of
    influence for physical, biological, and social-economic-cultural impacts and basis for defining area.
    This section shall include at a minimum, the following information:

Physical Environment

    5.1 Geologic Resources and Hazards
5.1.1  Cross sections of the geology including soil horizons
   5.1.1.1   Geologic characteristics at all project structure locations and in the area of
                                                                                    C.7 Closure
                                                                                    D. Environmental
                                                                                      Setting
                                                                                    Table D-l
                                                                                    D.2F
D.2 Physical
   Environment
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                         13

-------
Volume I Part 2 - EIA Technical Review Guidelines:
             Tourism
                                                                     1 EXAMPLE TERMS OF REFERENCE (TOR)
                                                                          HOTEL/RESORT DEVELOPMENTS
                                                                                    D.2.1 Geology and
                                                                                      Soils
            influence.
   5.1.1.2   Geological map of the project area and area of influence at a scale of
            1:10,000.
              Submit a map of the area displaying all characteristics described.
              Include geological profiles and cuts, as well as stratigraphic columns.
5.1.2  Topography and slope conditions and geomorphology
5.1.3  Seismicity and stability characteristics
   5.1.3.1   Indicate the general seismic and tectonic features of the surrounding
            areas:
            • Seismic sources close to the project area
            • Seismic history
   5.1.3.2   Volcanic activity (must be provided by all the projects that are located
            within a radius of 30 km from an active volcanic emission center)
            • Indicate the general volcanic features of the area near the site
            • Historical  eruptions
            • Period of recurrence
            • Type of eruptions
            • Affected areas and high risk areas
   5.1.3.3   Describe project areas susceptible to soil liquefaction; planned, active, and
            abandoned mines; karst terrain; and areas of potential ground failure,
            such as subsidence, slumping, and land sliding
    5.2 Soil Resources
    The EIA shall describe baseline soil resources, and make use of maps, tables and accompanying
    narrative text to describe the soils at the project site and along new or reconditioned access routes
    associated with the project and included in the EIA.
5.2.1  Types, capacity and uses
5.2.2  Fertility and potential uses of the land for agriculture
5.2.3  Stability and permeability
5.2.4  Erosion and sedimentation potential
5.2.5  Quantity and quality available for revegetating and restoring the disturbed area
      at time of closure

    5.3 Water Resources
5.3.1  Surface water
   5.3.1.1    Names and locations on maps of all permanent and intermittent streams,
             rivers, wetlands, lakes and reservoirs within the area of influence
   5.3.1.2    Flow (only necessary if water source will be surface water or if wastewater
             will be discharged to surface water)
             • The monthly minimum,  mean and maximum recorded flows in m3/s of
              the river at the diversion point
             • Location of gauging stations where data were gathered to derive the
              curves
             • 2-, 10-, 25-,  50- and 100-year runoff events  and 100-yr floodplain for
              streams and rivers
   5.3.1.3    Seasonal fluctuations in  area and volume of wetlands, lakes and reservoirs
   5.3.1.4    Delineation of watersheds and water drainage pattern in the area of
             influence using cadastral/aerial/remote sensing satellite imageries (map)
             • Runoff characteristics of watersheds
   5.3.1.5    Inventories of consumptive and non-consumptive use
   5.3.1.6    Surface water balance (only necessary if water source will be surface
             water)
             • Existing uses by type and volume
             • Capacity
5.3.2  Groundwater
      Provide a map and identify and describe aquifiers and underground waters
      adjacent to the project, indicating the depth of the water table along with trend
      data:
   5.3.2.1    Hydrogeologic characteristics of the project site including fuel storage
             areas, wastewater discharge areas, and golf courses (vadose zone and
                                                                                    D.2.1 Geology and
                                                                                      Soils
                                                                                    D.2.2 Water Resources

                                                                                    D.2.2.1 Surface Water

                                                                                    D.2.2.2 Marine Waters
                                                                                    D.2.2.3 Groundwater
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                        14

-------
 Volume I Part 2 - EIA Technical Review Guidelines:                                1 EXAMPLE TERMS OF REFERENCE (TOR)
	Tourism	HOTEL/RESORT DEVELOPMENTS

             aquifers)
             • Water table levels (dry and rainy season)
             • Flow regime
             • Flow direction
             • Influences of geologic structures (faults, contacts, bedrock fracturing,
               etc) and surface water bodies
    5.3.2.2   Location and characteristics of all existing springs and wells in the area of
             influence  (on topographic map)
             • Flow/yield data for each spring and well (including water levels in wells)
             • Depth and construction information for each well
             • Existing uses by type and volume
             • Capacity available
    5.3.2.3   Groundwater recharge data
    5.3.2.4   Groundwater potential yield (only necessary if water source will be
             groundwater)
 5.3.3  Water quality (only necessary if project will discharge wastewater, includes
       irrigation, or will use fertilizers and pesticides on landscaped areas)
    5.3.3.1   Existing water quality data
             • Locations of all water quality monitoring stations in and around the
               project  area (with direction and distance from the site)
             • Water quality data for each station for those parameters likely to be
               affected by project construction, operation or maintenance
             • Physical, chemical and biological water quality characteristics, including
               water temperature and dissolved oxygen concentrations
    5.3.3.2   Supplemental sampling and analysis (if existing data is not adequate to
             characterize water quality)
              Sampling and Analysis Program in annex
             • Proposed locations of representative monitoring stations upstream and
               downstream of proposed project activities
             • Monitoring program design with at least a year of baseline data being
               collected
                 o  Parameters (including as appropriate, physical,  chemical and
                     biological)
                 o  Frequency of collection
                 o Analytic methods
    5.3.3.3   Surface water and groundwater standards that apply to the project
             • Current uses
             • Standards for current uses (in the absence of such standards, identify a
               set of benchmarks used in the analysis)

     5.4 Air and Climate
     Baseline information for air resources shall be collected for at least one year or as required by the
     regulatory agency and shall include at a minimum the following:
 5.4.1  Climate and meteorology
    5.4.1.1   Source of data (meteorological station(s) from which climatological data      D.2.3 Air and Climate
             have  been obtained)
    5.4.1.2   Temperature variations
    5.4.1.3   Relative humidity
    5.4.1.4   Solar radiation and evaporation rates
    5.4.1.5   Rainfall (total precipitation,  rainfall intensity,  and duration by month)
    5.4.1.6   Wind Rose (Wind direction and speed, 24 hourly data)
    5.4.1.7   Statistical analysis of the data
    5.4.1.8   Risk of high  impact storms, storm surges, hurricane levels, tropical storms
             frequency and seasonality

     5.5 Noise and Vibration
     Present a description of the noise and vibration levels for receptors near where noise generating
     activities of the project may occur. The EIA shall include:
 5.5.1  Location of monitoring stations
 5.5.2  Daytime and night time noise levels (measured  in decibels)                         D 2 4 Noise and


 CAFTA-DR AND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENT AND LABOR ExcELLENCE-CCAD-USEPA PROGRAM                15

-------
Volume I Part 2 - EIA Technical Review Guidelines:
             Tourism
1 EXAMPLE TERMS OF REFERENCE (TOR)
      HOTEL/RESORT DEVELOPMENTS
5.5.3  Inventory of existing noise sources

    5.6 Aesthetic and Visual Resources
5.6.1  Photos presenting baseline panoramic views of the project site from potential
      viewpoints
5.6.2  Viewsheds or other aesthetic or landscape resources
5.6.3  Existing sources of light contamination

Biological Environment
    The EIA shall provide detailed information on the location and condition of ecosystems in and around
    the project area in the form of narrative, maps and tables, including the following:

    5.7 Vegetation/Flora
5.7.1  Vegetative mapping of  terrestrial and wetland habitats (aquatic and marine if
      appropriate) for project area and areas affected by the project (e.g., project site
      and areas around new roads)
5.7.2  Species and structure (abundance, density, status, plant communities, presence
      of invasive species, etc.)

    5.8 Aquatic and Terrestrial Wildlife/Fauna
5.8.1  Fish and Aquatic  Resources
   5.8.1.1   Identification offish, mussel, macroinvertebrate and other aquatic species
              Spatial and temporal distribution
              Species life stage composition
              Standing crop
              Age and growth data
              Spawning run timing
              Extent and location  of spawning, rearing, feeding and wintering habitat
5.8.2  Wildlife Resources
   5.8.2.1   Species (including status, i.e., endemic, migratory, exotic, endangered,
             threatened, keystone, etc.), life history, and seasonal use
   5.8.2.2   Breeding areas
   5.8.2.3   Mating and brooding areas
   5.8.2.4   Migratory corridors (if applicable)
   5.8.2.5   Important wildlife use areas (roosts, clay licks, etc.)

    5.9 Ecosystems: Terrestrial, Wetlands, Aquatic, Marine
    Much if not all that may be needed to address the environmental setting for terrestrial, wetlands,
    aquatic and/or marine ecosystems may have been covered in Sections 5.7 and 5.8. This section is not
    intended to duplicate that information; rather, it should integrate the information to ensure that the
    structure and function of each ecosystem is adequately presented.

    5.10  Endangered or Threatened Species and Habitats
    Sections 5.7 and 5.8 should identify all species in the project area. This section should highlight all
    endangered and threatened species and critical habitat that potentially occur in the vicinity of the
    project.

    5.11  Protected Areas
    Identify on maps the specific locations and boundaries  of relevant national parks, sanctuaries,
    reserves, etc., as well as any areas proposed for protection.  Provide a brief narrative description of
    each area.

Social-Economic-Cultural Environment

    5.12  Socio-Economic Conditions
    Identify nearby human settlements including the following information for each settlement:
5.12.1  Population (size, gender and age distribution)
5.12.2  Cultural characteristics (religion, ethnic composition, languages spoken, etc.)
5.12.3  Economic activities (employers, employment and incomes)
5.12.4  Tax  base
5.12.5  Crime rates
5.12.6  Literacy rates
5.12.7  Community organizations
                  Vibration
               C.2.5 Aesthetic
                  Resources




               D.3 Biological
                  Environment
               D.3.1 Flora

               D.3.2 Fauna
               D.3.3 Ecosystems
               D.3.4 Endangered or
                  Threatened Species
                  and Habitats

                ).3.5 Protected Areas
                  and Sensitive
                  Ecosystems
               D.4 Social-Economic-
                  Cultural
                  Environment

               D.4.1 Socio-Economic
                  Conditions and

CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                           16

-------
Volume I Part 2 - EIA Technical Review Guidelines:
             Tourism
1 EXAMPLE TERMS OF REFERENCE (TOR)
      HOTEL/RESORT DEVELOPMENTS
5.12.8  Public Health and Safety
   5.12.8.1  Diseases in the project area (including the sources of data and the
             methodology used to collect and analyze the data)
   5.12.8.2  Level of emergency services and access to clinics, doctors and hospitals
   5.12.8.3  Existing practice for assessment of occupational health
5.12.9  Skills, services and goods availability in the communities

    5.13   Infrastructure
    For each human settlement identified in subsection 5.12, describe the infrastructure in or serving the
    settlement, including the following information:
5.13.1 Transportation infrastructure
   5.13.1.1  Roads- Location and condition of all existing roads in the project area  that
             may be used by the project or tourists coming to the project
             •  Surface materials
             •  Erosion and sediment control
             •  Maintenance programs (what, when and whom)
             •  Description of anticipated third-party improvements (government or
               entity other than the proponent)
             •  Traffic capacity, patterns and densities
             •  Safety levels and current circulation issues
   5.13.1.2  Airports and air strips - Locations, conditions, capacities, current uses and
             trends
   5.13.1.3  Other transportation  infrastructure as applicable such as rail, bus,
             pipelines for fueling, harbors for cruise ships, and marinas for boats -
             Locations, conditions, capacities, current uses and trends
5.13.2 Public health  infrastructure
   5.13.2.1  Drinking water supplies and treatment,
   5.13.2.2  Wastewater treatment and management
   5.13.2.3  Solid and  hazardous waste management and treatment
5.13.3 Communications infrastructure
   5.13.3.1  Types of communications systems
   5.13.3.2  Types of transmission (wired or wireless)
   5.13.3.3  Locations of transmission lines (if applicable)
   5.13.3.4  Locations of microwave towers and/or antennae (if applicable)
5.13.4 Energy infrastructure
   5.13.4.1  Types of energy
   5.13.4.2  Sources including location and description of generating facilities in the
             area of influence
   5.13.4.3  Transmission lines and/or pipelines
   5.13.4.4  Fuel storage facilities

    5.14   Cultural, Archeological, Ceremonial and Historic and Resources
    Identify all cultural, archaeological, ceremonial and historic resources within the area of influence,
    including the following information:
5.14.1 Data and maps relating  to archeological, cultural, ceremonial, and historic sites in
      the direct vicinity of the project
5.14.2 Information on indigenous people or other traditional cultures, if any

    5.15   Land Use
    Describe actual and potential land use showing location, size and proximity within and surrounding
    the project area, including land use maps, and to extent possible, integrated into one map.
5.15.1 Population centers, including information and locations of
   5.15.1.1  Schools
   5.15.1.2  Cemeteries
   5.15.1.3  Churches
   5.15.1.4  Other public buildings
   5.15.1.5  Housing (including housing density)
   5.15.1.6  Commercial areas
5.15.2 Agricultural lands
5.15.3 Forested lands
5.15.4 Protected areas (including but not limited to)
                  Resources
               D.4.2 Infrastructure
                  Systems and
                  Equipment

               D.4.2.1 Transportation
                  Infrastructure
                ).4.2.2 Public Health
                  Infrastructure

               D.4.2.3 Communica-
                  tions Infrastructure
                ).4.2.4 Energy
                  Infrastructure
               0.4.3 Cultural,
                  Archeological,
                  Ceremonial and
                  Historic Resources
               D.4.4 Land Use
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                          17

-------
Volume I Part 2 - EIA Technical Review Guidelines:
              Tourism
1 EXAMPLE TERMS OF REFERENCE (TOR)
      HOTEL/RESORT DEVELOPMENTS
   5.15.4.1  National parks
   5.15.4.2  Wildlife refuges
5.15.5 Wetlands and mangroves
5.15.6 Other environmentally sensitive areas
5.15.7 Tourism and recreation areas
   5.15.7.1  Recreation facilities
   5.15.7.2  Eco-cultural-tourist locations
5.15.8 Culturally sensitive areas
5.15.9 Flood plains and water bodies
5.15.10  Coastal zones
5.15.11  Other land uses as appropriate

6   Assessment of Impacts
    The EIA shall provide information on potential impacts (direct, indirect and cumulative) and the
    magnitude and frequency of potential impacts on physical, biological, social-economic-cultural
    resources resulting from construction, operation and closure of the proposed project and alternatives.
    The assessment shall use standardized predictive methods, such as models, to determine the specific
    range of impacts on environmental and socio-economic resources. The EIA shall identify which
    impacts are significant and the criteria used to make this judgment.  Critical data input from project
    description and environmental setting analysis projecting the conditions in the environmental setting
    in the absence of the proposed project shall be used as the baseline upon which potential impacts are
    forecast. The EIA shall also identify sources of data used in the analysis and the uncertainties
    associated with the outputs of each method used.

Physical Impacts

    6.1  Geologic Resources and Hazards
    Potential impacts to geologic resources and potential effects on project structures shall be described
    including but not limited to the following:
6.1.1  Geologic hazards  and  potential effects on project structures
6.1.2  Changes in topography and drainage patterns
6.1.3  Overall assessment of significance of direct, indirect and cumulative impacts for
      all phases of the proposed project based upon analysis of magnitude, frequency,
      scope and duration in context
    6.2 Soil Resources
    Potential impacts to soil resources shall be described. The analysis shall include, but not be limited to
    the following:
6.2.1   Soil quality
   6.2.1.1   Contamination
             • Salinization due to irrigation
             • Use of pesticides and chemical fertilizers
   6.2.1.2   Impacts on use
6.2.2   Erosion, slope alteration, vegetation removal and drainage patterns
   6.2.2.1   Models for soil erosion should be included using methods like USLE,
             defining the areas with high erosion potential
   6.2.2.2   Sediment accumulation and transport
   6.2.2.3   Sediment and hazardous waste removal and disposal
6.2.3   Overall assessment of significance of direct, indirect and cumulative impacts for
       all phases of the proposed project based upon analysis of magnitude, frequency,
       scope and duration in context

    6.3 Water Resources
    Potential impacts to surface water and groundwater shall be described. The analysis shall include but
    not be limited to the following:
6.3.1   Geomorphology
   6.3.1.1   Location of all stream or wetland crossings by access roads.
   6.3.1.2   Modification/diversion in the existing drainage pattern
   6.3.1.3   Bank erosion (surface water discharges, stream crossings and dredging)
   6.3.1.4   Potential for increased flash flooding
6.3.2   Quantity
   6.3.2.1   Impact of water use on surface water and groundwater, including specific
                E. Potential Impacts

                F. Assessing Impacts

                F.I Overview of Using
                  Predictive Tools for
                  an EIA

                F.2 General
                  Approaches for
                  Prediction of
                  Impacts

                Appendix C

                E.2 Physical
                  Environment

                E.2.1 Geology, Soils
                  and Ocean
                  Topography
I                Table E-l

                F.3 Soils and Geology
                  Impact Assessment
                  Tools
                E.2.2 Water Resources
                Table E-2
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                             18

-------
Volume I Part 2 - EIA Technical Review Guidelines:
             Tourism
1 EXAMPLE TERMS OF REFERENCE (TOR)
      HOTEL/RESORT DEVELOPMENTS
            uses
            • Model results
            • Water table levels
            • Well production
            • Spring and stream flows
6.3.3  Quality
   6.3.3.1    Runoff, erosion and sedimentation from roads, disturbed areas and
             stream crossings
             • Sources
             • Receiving waters
             • Concentrations
                o   Physical parameters
                o  Chemical parameters
                o   Biological parameters
   6.3.3.2    Description of impact from wastewater discharges
   6.3.3.3    Chemical contamination from herbicides used for vegetative maintenance
             (fertilizers and pesticides)
   6.3.3.4    Spills and accidents
             • Chemical, hazardous waste and fuel spills
6.3.4  Overall assessment of significance of direct, indirect and cumulative impacts for
      all phases of the proposed project based upon analysis of magnitude, frequency,
      scope and duration in context

    6.4 Air and Climate
    Potential impacts to air resources shall be described including but not limited to the following:
6.4.1  Impacts on ambient air quality
   6.4.1.1   Sources (e.g., windblown dust, fixed and mobile equipment)
   6.4.1.2   Concentrations
   6.4.1.3   Receptors (e.g., communities, schools, soils, water bodies, ecosystems)
6.4.2  Greenhouse gas generation
6.4.3  Overall assessment of significance of direct, indirect and cumulative impacts for
      all phases of the proposed project based upon analysis of magnitude, frequency,
      scope and duration in context

    6.5 Noise and Vibration
    Potential impacts from noise shall be described including but not limited to the following:
6.5.1  Potential noise levels at different representative sites in the project area and in
      communities  near the project area
6.5.2  Potential vibration due to blasting and movement of heavy equipment, and
      related damage to materials and structures
6.5.3  Overall assessment of significance of direct, indirect and cumulative impacts for
      all phases of the proposed project based upon analysis of magnitude, frequency,
      scope and duration in context

    6.6 Aesthetic and Visual Resources
    Potential impacts to Aesthetic Resources, including light pollution, shall be described including but not
    limited to the following:
6.6.1  Impacts on visual  resources and landscapes
6.6.2  Increases in light contamination
6.6.3  Overall assessment of significance of direct, indirect and cumulative impacts for
      all phases of the proposed project based upon analysis of magnitude, frequency,
      scope and duration in context

Biological Impacts
    Potential impacts to biological resources shall be described and quantified including but not limited to
    the following:

    6.7 Vegetation/Flora and Associated Ecosystems
    Describe and quantify alterations in vegetative cover due to:
6.7.1  Deforestation or wetlands destruction
6.7.2  Other vegetative type conversions
               F.4 Water Resources
                  Impact Assessment
                  Tools
               Table F-2
               Table F-3
               Table F-2
               Table F-3
               E.2.3 Air Resources
               Table E-3

               F.5 Air Resources
                  Impact Assessment
                  Tools
               Table F-5
               E.2.4 Noise and
                  Vibration
               Table E-4

               F.6 Noise Impact
                  Assessment Tools

               E.2.5 Aesthetic
                  Resources

               F.7 Aesthetic/Visual
                  Resource Impact
                  Assessment Tools
                     F-6
Table F

E.3 Biol
   Envi
                  Biological
                  Environment
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                        19

-------
Volume I Part 2 - EIA Technical Review Guidelines:
             Tourism
1 EXAMPLE TERMS OF REFERENCE (TOR)
     HOTEL/RESORT DEVELOPMENTS
   6.7.2.1   Direct vegetative removal
   6.7.2.2   Indirect (e.g., poisoning by dust and pesticides)
6.7.3  Wildfires
6.7.4  Increased road access in remote areas leading to destruction of existing
      vegetative cover (land use changes)
6.7.5  Spread of noxious or invasive species
6.7.6  Overall assessment of significance of direct, indirect and cumulative impacts for
      all phases of the proposed project based upon analysis of magnitude, frequency,
      scope and duration in context

    6.8 Aquatic and Terrestrial Wildlife/Fauna and Associated Ecosystems
    Describe and quantify alterations in aquatic and terrestrial wildlife populations due to:
6.8.1  Fish and Aquatic Resources
   6.8.1.1   Loss in habitat (e.g., spawning, rearing, juvenile, or adult habitats) from
            changes in water quality due to sedimentation and use of chemicals for
            vegetation maintenance
   6.8.1.2   Disturbance of aquatic resources during construction, operations, or
            maintenance activities, including equipment noise, erosion and
            sedimentation, vehicular movements, or blasting
6.8.2  Wildlife Resources
   6.8.2.1   Loss of habitat, migratory routes/corridors, and breeding areas due to
            changes in vegetative cover/wetlands loss
   6.8.2.2   Disturbance of habitat, migratory routes/corridors and breeding areas due
            to project construction, operation, and maintenance, recreational use, and
            human settlement associated with the project (e.g., noise, vibration,
            illumination, vehicular movement)
   6.8.2.3   Loss or contamination of drinking water for wildlife species
   6.8.2.4   Poisoning (e.g., direct contact with toxic waster/substances)
   6.8.2.5   Animals attracted to garbage and food waste generated at construction
            camps, restaurants and on-site employee housing
   6.8.2.6   Increased hunting
6.8.3  Overall assessment of significance of direct, indirect and cumulative impacts for
      all phases of the proposed project based upon analysis of magnitude, frequency,
      scope and duration in context

    6.9 Endangered or Threatened Species or Habitats
        Describe and quantify impacts to endangered or threatened species or habitats
6.9.1  Biodiversity
6.9.2  Individual species (with special  emphasis on endemic, rare, threatened and
      endangered species)
6.9.3  Overall assessment of significance of direct, indirect and cumulative impacts for
      all phases of the proposed project based upon analysis of magnitude, frequency,
      scope and duration in context

    6.10  Protected Areas

Social-Economic-Cultural Impacts
    The EIA shall assess potential positive and negative impacts to social-economic-cultural resources
    including but not limited to the following:

    6.11  Socio-Economic Conditions
6.11.1  Increased individual incomes
   6.11.1.1  Direct employment at the project
   6.11.1.2  Indirect employment generated  by project activities
   6.11.1.3  Increased purchases from local businesses
   6.11.1.4  Other economic activities stimulated in the community as a result of the
            project
6.11.2  Employment opportunities for local residents
6.11.3  Increased tax base
6.11.4  Displacement and relocation of current settlements, residents or community
        resources
               Table E-5

               E.3.1 Terrestrial
                 Species and
                 Associated
                 Ecosystems

               E.3.2 Aquatic
                  Ecosystems

               F.8 Flora, Fauna,
                  Ecosystems and
                  Protected Areas
                  Impact Assessment
                  Tools
               Table F-2
               E.3.3 Endangered or
                 Threatened Species
                 and Habitats and
                 Protected Areas

               F.8 Flora, Fauna,
                 Ecosystems and
                 Protected Areas
                 Impact Assessment
                 Tools

               E. Social-Economic-
                 Cultural
                 Environment
               Table E-6
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                       20

-------
Volume I Part 2 - EIA Technical Review Guidelines:
             Tourism
1 EXAMPLE TERMS OF REFERENCE (TOR)
     HOTEL/RESORT DEVELOPMENTS
6.11.5   Displacement or disruption of people's livelihoods (e.g., fishing, hunting,
        grazing, farming, forestry and tourism)
6.11.6   Public finance requirements-will more infrastructure need to be built and
        maintained to meet the demands of increased population in the areas of public
        education and public service (water, sanitation, roads, emergency services,
        etc.)
6.11.7   Reduction in quality of life for residents from visual and noise impacts
6.11.8   Change in crime rate (drugs, alcohol, prostitution, etc.)
6.11.9   Change in population (temporary or permanent)
6.11.10 Change in character of community
6.11.11 Change in religious, ethnic or cultural makeup of community
6.11.12 Impacts on public health
   6.11.12.1 Water-related vector diseases (malaria, dengue, etc.)
   6.11.12.2 Health impacts of pesticide and fertilizer use
6.11.13 Impacts on worker health and safety
   6.11.13.1 Identification of hazardous jobs and number of workers exposed with
            duration of exposure
   6.11.13.2 Occupational diseases due to exposure to dust and other project related
            activities such as handling of explosives, solvents, petroleum products, etc.
   6.11.13.3 Identification of physical risks and safety aspects
6.11.14 Potential for fires
6.11.15 Overall assessment of significance of direct, indirect and cumulative impacts
        for all phases of the proposed project based upon analysis of magnitude,
        frequency, scope and duration in context

    6.12  Infrastructure
6.12.1   Transportation  infrastructure
        This section of the EIA addresses impacts of transportation and traffic patterns
        on existing roads. The impacts of new and existing roads on water quality,
        biological resources and land use should be addressed in those respective
        sections. The EIA shall assess potential impacts to transportation systems
        including but not limited to the following:
   6.12.1.1  Potential changes to traffic patterns, densities, and traffic safety issues in
            area affected by project
            • A determination of vehicular traffic density in the project area (before,
              during, and after the proposed activities)
            • Potential for traffic accidents
            • Congestion
            • Noise
   6.12.1.2   Potential impacts to previously inaccessible areas from improvement of
             roads
6.12.2   Public health infrastructure
   6.12.2.1   Increased  need for public health infrastucture
   6.12.2.2   Alterations to public health infrastucture
6.12.3   Communications infrastructure
   6.12.3.1  Increased need for communications infrastucture
   6.12.3.2  Alterations to communications infrastucture
6.12.4   Energy infrastructure
   6.12.4.1  Increased need for energy infrastucture
   6.12.4.2  Alterations to energy infrastucture
6.12.5   Overall assessment of significance of direct, indirect and cumulative impacts
        for all phases of the proposed project based upon analysis of magnitude,
        frequency, scope and duration in context

    6.13  Cultural, Archeological, Ceremonial and Historic and Resources
6.13.1   Destruction during construction
6.13.2   Damage and alteration
6.13.3   Removal from historic location
6.13.4   Introduction of  visual or audible elements that diminish integrity
6.13.5   Neglect that causes deterioration
               F.9 Socio-Economic
                 Conditions,
                 Infrastructure and
                 Land Use
               F.12 Health and Safety
                  Impact Assessment
                  Tools
               E.4.2 Infrastructure:
                  Systems,
                  Equipment,
                  Capacity,
                  Performance
               Table E-7
               F.9 Socio-Economic
                 Conditions,
                 Infrastructure and
                 Land Use
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                       21

-------
Volume I Part 2 - EIA Technical Review Guidelines:
              Tourism
                                                                       1 EXAMPLE TERMS OF REFERENCE (TOR)
                                                                             HOTEL/RESORT DEVELOPMENTS
                                                                                       E.4.3 Cultural,
                                                                                          Archeological,
                                                                                          Ceremonial and
                                                                                          Historic Resources
                                                                                       Table E-8
                                                                                       E.4.4 Land Use
                                                                                       F.9 Socio-Economic
                                                                                          Conditions,
                                                                                          Infrastructure and
                                                                                          Land Use
6.13.6   Loss of medicinal plants
6.13.7   Loss of access to traditional use areas
6.13.8   Damage to resources due to increased visitation promoted by the project
6.13.9   Impacts to previously inaccessible resources from development/improvement
         of roads
6.13.10  Overall assessment of significance of direct, indirect and cumulative impacts
         for all phases of the proposed project based upon analysis of magnitude,
         frequency, scope and duration in context

    6.14 Land Use
6.14.1   Temporary and permanent changes in land use by both area and location
6.14.2   Overall assessment of significance of direct, indirect and cumulative impacts
         for all phases of the proposed project based upon analysis of magnitude,
         frequency, scope and duration in context
6.14.3   Social infrastructure (schools, cemeteries, churches, other public buildings,
         communication systems and  housing)
   6.14.3.1   Increased  need for additional infrastructure
   6.14.3.2   Alterations to social infrastructure
6.14.4   Existing tourism and recreation infrastructure
   6.14.4.1   Change in  tourist activities
   6.14.4.2   Increased  need for tourism and recreation infrastructure
   6.14.4.3   Alterations to tourism and recreation infrastructure
6.14.5   Housing market (during construction and operation and after closure)
6.14.6   Identification of any components of the proposed project that would fall within
         25- or 100-year flood plains
6.14.7   Overall assessment of significance of direct, indirect and cumulative impacts
         for all phases of the proposed project based upon analysis of magnitude,
         frequency, scope and duration in context

7   Mitigation and Monitoring Measures
    This section of the EIA must include measures designed to mitigate potential adverse impacts to
    physical, biological and social-economic-cultural resources from construction, operation and closure of
    the proposed project and alternatives. These shall include measures to avoid and prevent, and if
    needed, to reduce or minimize adverse impacts. The project proponent must include measures
    considered to be "best practices" in the design of all alternatives.

    Here and/or in the Environmental Management Plan section, proposed mitigation shall be described in
    auditable terms and at a level of detail sufficient to demonstrate its effectiveness in addressing the
    concern or performance criterion, including its anticipated level of effectiveness and/or measurable
    performance, and design specifications.

    The monitoring plan must include monitoring throughout the life of the project for each potential
    mitigation to confirm the effectiveness of the measure and support contingency plans to provide
    assurance that the project, at the site preparation, construction, operation, expansion, and closure
    stages will meet applicable environmental requirements/standards by law, and fall within the limits of
    impacts deemed acceptable upon approval of the EIA. Some important items to address in the
    mitigation plan and associated monitoring plans include, but are not limited to the following:

Physical Impacts

    7.1 Geologic Resources and Hazards
7.1.1   Pre-excavation, onsite geological inspection and geotechnical  study protocols to
       determine slope stability and landslide risks
7.1.2   Slopes built and maintained to avoid landslides and favor revegetation and soils
       formation
7.1.3   Slope stabilization by constructing retaining walls, using vegetation, geotextile
       membranes, or other mechanical methods
7.1.4   Blasting Plan, if applicable (summary of  relevant measures with full document in
       Annex)
7.1.5   Use of signage to  mark areas where slopes are not stable as a  preventive
       measure in the event of a landslide
7.1.6   Mitigation measures  unique to  specific alternatives
                                                                                       G. Mitigation and
                                                                                          Monitoring
                                                                                          Measures
                                                                                       Tables G-l, G-2 & G-3
                                                                                       Tables G-6, G-7 & G-8
                                                                                       Tables G-l, G-2 & G-3
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                            22

-------
 Volume I Part 2 - EIA Technical Review Guidelines:                               1 EXAMPLE TERMS OF REFERENCE (TOR)
	Tourism	HOTEL/RESORT DEVELOPMENTS


     7.2 Soil Resources
 7.2.1  Erosion and sedimentation control measures (temporary and permanent)
       including when each will be installed or implemented, how often it will be
       checked and the process for and timing of removal of temporary measures
 7.2.2  Spoil and disposal measures
 7.2.3  Best management practices to minimize soil disturbance
 7.2.4  Decommissioning/Rehabilitation Plan-if needed (summary of relevant measures
       with full document in Annex)
 7.2.5  Restrictions on discharge of pollutants to soil
 7.2.6  Mitigation measures unique to specific alternatives                                    ..

     7.3 Water Resources
 7.3.1  Quality
    7.3.1.1   Water Quality Management Plan (summary of relevant measures with full
             document in Annex)
             • Sewage and domestic wastewater
             • Nonpoint sources - runoff, erosion and sediment control prevention
               measures
    7.3.1.2   Spill Prevention and Containment Plan (summary of relevant measures
             with full document in Annex)
    7.3.1.3   Solid Waste Management Plan (summary of relevant measures with full
             document in Annex)
    7.3.1.4   Hazardous Waste Management Plan (summary of relevant measures with
             full document in Annex)
    7.3.1.5   Transport system construction and maintenance to avoid erosion and
             sedimentation including:
             • Elevation or rerouting
             • Design for proper run-off control and catchment
             • Provision of culverts to allow flow that might otherwise be impeded by
               roadways or other rights of way
             • Appropriate traffic control
    7.3.1.6   Off-road vehicle use restrictions
    7.3.1.7   Waste minimization practices
 7.3.2  Quantity
    7.3.2.1   Water conservation practices
    7.3.2.2   Mitigation measures unique to specific alternatives

     7.4 Air and Climate
 7.4.1  Dust control measures
 7.4.2  Energy conservation measures
 7.4.3  Emissions control measures
    7.4.3.1   Emissions reduction equipment
    7.4.3.2   Maintenance and inspection of equipment and vehicles using combustion
             engines to reduce emissions
 7.4.4  Spill Prevention and Containment Plan (summary of relevant measures with full
       document in Annex)

     7.5 Noise and Vibration
 7.5.1  Noise control measures
    7.5.1.1   Noise reduction technologies (suppression equipment, sound-absorbing
             structures, vibration dampening devices, berms, noise  barriers, etc.)
    7.5.1.2   Rerouting of traffic and other infrastructure related activities to minimize
             impacts of noise and vibration
    7.5.1.3   Time of day limitations on blasting and movement of heavy equipment
             when in  close proximity to houses not being operated during evening
             hours
 7.5.2  Blasting Plan, if applicable (summary of relevant measures with full document in
       Annex)
 7.5.3  Mitigation measures unique to specific alternatives
 CAFTA-DR AND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENT AND LABOR ExcELLENCE-CCAD-USEPA PROGRAM                23

-------
Volume I Part 2 - EIA Technical Review Guidelines:
             Tourism
1 EXAMPLE TERMS OF REFERENCE (TOR)
     HOTEL/RESORT DEVELOPMENTS
    7.6 Aesthetic Resources
7.6.1  Relocation of project to another site
7.6.2  Redesign of placement of project structures on site
7.6.3  Redesign height and location of structures blocking view or producing light
      pollution
7.6.4  Lighting minimization
7.6.5  Visual/Landscape Management Plan (summary of relevant measures with full
      document in Annex)
7.6.6  Mitigation measures unique to specific alternatives

Biological Impacts

    7.7 Vegetation/Flora and Associated Ecosystems
7.7.1  Control of noxious and invasive weeds
7.7.2  Measures to compensate for loss or damage of forests, wetlands or other critical
      ecosystems, including establishment of new protected areas
7.7.3  Restoration/Rehabilitation  Plan for disturbed areas (summary of relevant
      measures with full document in Annex)
7.7.4  Mitigation measures unique to specific alternatives

    7.8 Aquatic and Terrestrial Wildlife/Fauna and Associated Ecosystems
7.8.1  Fish and Aquatic Resources
   7.8.1.1   Scheduling construction to avoid critical or important fish life history
            periods (e.g.,  spawning)
   7.8.1.2   Relocation of sensitive,  threatened or endangered species
   7.8.1.3   Blasting Plan, if applicable (summary of relevant measures with full
            document in Annex)
   7.8.1.4   Mitigation measures unique to specific alternatives
7.8.2  Wildlife Resources
   7.8.2.1   Controls on hunting within the project area
   7.8.2.2   Modify locations of structures and locations and timing of activities to
            avoid critical ecosystems, migratory routes and breeding areas
   7.8.2.3   Scheduling construction to avoid critical or important wildlife history
            periods (e.g.,  breeding,  nesting)
   7.8.2.4   Relocation of sensitive,  threatened or endangered species
   7.8.2.5   Blasting plan, if applicable (summary of relevant measures with full
            document in Annex)
   7.8.2.6   Mitigation measures unique to specific alternatives

Social-Economic-Cultural Impacts

    7.9 Socio-Economic Conditions
7.9.1  Selection of an alternate site for the project, and if not possible then adhering to
      requirements of an internationally recognized Resettlement Action Plan (RAP)
7.9.2  Rehabilitation Program  for people displaced by the project (summary of relevant
      measures with full document in Annex)
7.9.3  Training local residents  for employment in the project
7.9.4  Development of a "Code of Conduct" (with associated training program) for
      workers to show respect to the local populations and their culture and social
      rules
7.9.5  Public Health Program to protect local population from potential health problems
      caused by the project operation (summary of relevant measures with full
      document in Annex)
7.9.6  Development of an Occupational Health, Industrial Safety and Accidents
      Prevention Program with appropriate accident prevention program, reporting
      and periodic review (summary of relevant measures with full document in Annex)
      including provision of routine training and testing,  and proper safety equipment
      such as hearing protection, hardhats, steel-toed shoes, safety railings and fall
      arrestors
              Table G-5
              Tables G-l, G-2 & G-3
              Appendix F

              Table G-4
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                      24

-------
 Volume I Part 2 - EIA Technical Review Guidelines:                                1 EXAMPLE TERMS OF REFERENCE (TOR)
	Tourism	HOTEL/RESORT DEVELOPMENTS

 7.9.7  Spill Prevention and Containment Plan (summary of relevant measures with full
       document in Annex)
 7.9.8  Hazardous Materials Management Plan (summary of relevant measures with full
       document in Annex)
 7.9.9  Mitigation measures unique to specific alternatives

     7.10  Infrastructure
 7.10.1   Transportation infrastructure
         This section of the EIA addresses mitigation measures for transportation and
         traffic patterns on existing infrastructure (roads, airports, air strips, harbors,
         etc.).  Mitigation of impacts of new and existing transportation infrastructure
         on water quality and biological resources and land use should be addressed in
         those respective sections.
    7.10.1.1  Transportation Plan (summary of relevant measures with full document in
             Annex)
             • Placement of traffic signals
             • Establishing, posting and enforcing speed limits for the vehicles that
               transport material
             • Training employees, contractors and subcontractors on measures to
               reduce or avoid potential accidents
             • Hiring and training security personnel devoted exclusively to preventing
               accidents in the access road and controlling the speed of the vehicles
               transporting project material
 7.10.2   Public health infrastructure
 7.10.3   Communications infrastructure
 7.10.4   Energy Infrastructure
 7.10.5   Mitigation measures unique to specific alternatives

     7.11  Cultural, Archeological, Ceremonial and Historic and Resources
 7.11.1   Modify structure and activity locations to avoid significant archeological,
         cultural, ceremonial and historic sites
 7.11.2   If avoidance is not possible, conduct appropriate resource recovery operations
         before disturbing the sites
 7.11.3   Clearly delineate boundaries and post signs identifying existing archeological,
         cultural and historic sites on  roadsides and within the project area boundaries
         so that they are easily recognized by machinery operators, workers and
         tourists
 7.11.4   Development of a training program so that staff recognize and respect
         culturally and archeological sensitive areas
 7.11.5   Development of a code of conduct for activities in indigenous and local
         communities with the consent of and in collaboration with the community
 7.11.6   Provide guests with  information about and interpretation of the local culture
         and cultural heritage, as well as explaining appropriate behavior while visiting
         living cultures and cultural heritage sites
 7.11.7   Development protocols for use during construction and operation stages for
         identifying and responding to archeological, cultural, ceremonial and historic
         sites not identified during the preliminary surveys
    7.11.7.1  In the event such a site is found, they will stop activities at the site and
             report to the government relocation of cultural or historical resources, for
             their physical protection.
 7.11.8   Mitigation measures unique to specific alternatives

     7.12  Land Use
 7.12.1   Criteria and method for calculating compensation for loss of land and crops
 7.12.2   Compensation to farmers and ranchers for crop or forage losses and restore
         lost agricultural lands at the end of the project.
 7.12.3   Compensation to property owners for relocation of their homes in the event
         the relocation is unavoidable
 7.12.4   Mitigation measures unique to specific alternatives
 CAFTA-DR AND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENT AND LABOR ExcELLENCE-CCAD-USEPA PROGRAM                25

-------
Volume I Part 2 - EIA Technical Review Guidelines:
             Tourism
1 EXAMPLE TERMS OF REFERENCE (TOR)
      HOTEL/RESORT DEVELOPMENTS
8   Environmental Management Plan
    The EIA shall include an Environmental Management Plan to prevent, mitigate and monitor each
    impact identified in the EIA. Plans will describe actions to be taken in sufficient detail to provide a
    basis for subsequent auditing of compliance with commitments made in the EIA process including who
    is responsible, how and when it will be implemented, what will be done and what results will be
    achieved, why it is being done, and how to know whether it is effective in addressing the underlying
    concerns. The Environmental Management Plan shall have the following elements:

    8.1 Overview of Environmental Management Plan Organization and Policy
8.1.1  Describe the project management and how environmental management and
      organization relates to  overall project responsibility. Describe the personnel and
      performance accountability system for design, operation, maintenance and
      closure for implementation of mitigation and monitoring measures
8.1.2  Describe the environmental policy that will govern the Project throughout its
      implementation, including at least the objectives, scope, commitment to
      continuous improvement, control and environmental monitoring and good
      relationship with neighboring populations and countries, as well as the
      commitment to internal controls such as compliance and environmental
      monitoring and routine audits
8.1.3  Identify the persons responsible for the implementation of mitigation measures,
      in each phase

    8.2 Project-wide Mitigation Plan including an implementation schedule.  It
        has two elements:
8.2.1  Environmental resource mitigation (such as air, water)
8.2.2  Socio-economic-cultural mitigation (relocation, etc.)

    8.3 Project-Wide Monitoring Plan (usually specific to monitoring of
        surface and ground water)
8.3.1  Short-term and long-term monitoring of resource condition, including but not
      limited to:
   8.3.1.1    Slope stability
   8.3.1.2    Water Quality Monitoring Program
             • Where, how and when monitoring shall be conducted
             • Parameters to be monitored
             • Monitoring frequencies
             • Sampling and analytical protocols to be used
   8.3.1.3    Air Quality Monitoring Program
             • Where, how and when monitoring shall be conducted
             • The Parameters to be monitored
             • The monitoring frequencies
             • The sampling and analytical  protocols to be used
   8.3.1.4    Noise and Vibration
   8.3.1.5    Cultural, ceremonial archeological and historic resources in the vicinity of
             the project
8.3.2  Short-term and long-term monitoring to ensure that the mitigation measures are
      functioning as predicted and that rehabilitation is working

    8.4 Management of Other On- or Off-Site  Environmental Pollution Control
        and Infrastructure
    This section should address management of critical elements of pollution control and infrastructure
    that are not otherwise included in the mitigation plan because they were considered an essential part
    of the proposed project.

    8.5 Contingency Plans
    Contingency plans shall be prepared and described to address a) failure to meet specific performance
    criteria established by law or necessary for the project to meet its commitments in the EIA and b)
    respond to natural and other risks previously identified and mitigated in the EIA in the event
    reasonable and feasible mitigation measures to  address the risks are inadequate.
8.5.1  Performance-related Contingency Plans, indicating the steps that will be taken
      should monitoring indicate that:
   8.5.1.1    Environmental standards are not being met
               H Environmental
                  Management Plan
               Table H-l
               Appendix E
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                        26

-------
 Volume I Part 2 - EIA Technical Review Guidelines:                                 1 EXAMPLE TERMS OF REFERENCE (TOR)
	Tourism	HOTEL/RESORT DEVELOPMENTS

    8.5.1.2   Impacts are greater than predicted
    8.5.1.3   The mitigation measures and/or rehabilitation are not performing as
             predicted
 8.5.2  Natural Disaster Risk Response Plan (assumes that risk identification and risk
       reduction have been addressed in other parts of the EIA)
 8.5.3  Other Risks Response Plans (assumes that risk identification and risk reduction
       have been addressed in other parts of the EIA)
 8.5.4  Contingency plans for maintaining service or reducing downtime in the event of
       accidents or natural catastrophes that disrupt project operation

 9   Signed Commitment Statement
     The EIA shall contain a legally binding signed letter of commitment to meeting the terms of the EIA.
     The statement must be signed by the authorized representative of the proponent company with
     assurance that all financial surety measures as required by the regulatory agency have been met.

 10  Annexes
     These shall be numbered and duly referenced in the text

     10.1   Public Consultation
 10.1.1  Public consultation plan
 10.1.2  A summary of public outreach activities including: audience, number of
         persons, organizations involved, concerns raised, responses to comments
 10.1.3  Summary of response to comments
 10.1.4  Actual copies of written comments

     10.2  Technical Supporting Documents
 10.2.1  Include maps, plans, charts and figures in the sequence mentioned in the EIA
         document
 10.2.2  Zoning maps with resources and results of impacts
 10.2.3  Special Studies if relevant but not readily accessible
 10.2.4  Detailed materials on predictive tools/models and assumptions used for the
         assessment but too detailed for the body of the EIA

     10.3   References
     Submit a list of all references, (books, articles, technical reports and other information sources) cited in
     the various chapters of the EIA study with full biographic references, and the following conventional
     procedures cited in the literature: author, year, title, source, number of pages, and city of publication
     or issuance.
 CAFTA-DR AND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENT AND LABOR ExcELLENCE-CCAD-USEPA PROGRAM                 27

-------
Volume I Part 2 - EIA Technical Review Guidelines:
             Tourism
1 EXAMPLE TERMS OF REFERENCE (TOR)
     HOTEL/RESORT DEVELOPMENTS
[This page is intentionally blank.]
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                       28

-------
Volume I Part 2 - EIA Technical Review Guidelines:                            2 EXAMPLE TERMS OF REFERENCE (TOR)
           Tourism                                                   CONCESSION PROJECTS
2   TERMS OF REFERENCE (TOR) FOR CONCESSIONS PROJECTS

A.  OVERVIEW
These terms  of  reference (TOR) describe the minimum  requirements  for  the  preparation of the
Environmental Impact Assessment  (EIA) for proposed  concessions.   Both the TOR and  the  cross
referenced "EIA Technical Review Guidelines for Tourism Projects" should be used to establish minimally
acceptable conditions for satisfying the requirement to submit an EIA. There  are three different TORs
for tourism projects. Part A, Overview, is common to all three TORs but Part B is tailored respectively to:
1. Hotel and Resort Developments, 2. Concessions, and 3. Marine and Coastal Tourism.  The three TORs
are structured to facilitate mixing and matching as appropriate to the purpose and need for a proposed
project and alternatives.

These TORs  are  focused on specific  types  of concessions dealing with the use of  public land  for
recreational activities such as:
          •   Hiking trails and backcountry camping
          •   Horseback riding
          •   Off road vehicles
          •   Zip lines and canopy walks
          •   River rafting/kayaking/canoeing
          •   Lake-based recreation (boating, skiing, swimming, etc.)
          •   Sport fishing (lake or river)

Many concessions may also  include hotels, restaurants, campgrounds and other such  components.
These components are covered by the TOR for Hotel and  Resort Developments. If the concession is for
marine or coastal tourism, you should also consult the TOR for Marine and Coastal Tourism.

The basic format for the EIA document that should be followed is:
          •   Table of Contents
          •   Acronyms and Abbreviations
          •   Executive Summary
          •   General Information
          •   Project and Alternatives Description
          •   Environmental Setting
          •   Assessment of Impacts
          •   Mitigation and Monitoring Measures
          •   Environmental Management Plan
          •   Commitment Statement
          •   Annexes

In general, the EIA must identify and address:

•   Applicable environmental standards,  norms,  and requirements  set forth  at the  international,
    national, regional and/or local levels including those designed to meet  the objectives of resource
    management and/or land use plans that may be in effect in and around  the jurisdiction(s) in which
    the proposed project is located.  In the absence of such standards, the EIA should establish a set of
    benchmarks that can be used in the analysis and selection of an alternative. The Guidelines identify
    standards in use by various countries and international organizations in Appendix C.

•   Public/Stakeholder concerns related to impacts in and around the proposed project and alternatives
    at least for stakeholders within the geographic scope of potential impact. The project proponent
    should document specific steps taken to engage the public and other stakeholders, and engage

CAFTA-DR AND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENT AND LABOR ExcELLENCE-CCAD-USEPA PROGRAM              29

-------
 Volume I Part 2 - EIA Technical Review Guidelines:                            2 EXAMPLE TERMS OF REFERENCE (TOR)
	Tourism	CONCESSION PROJECTS

    these publics as early as possible before undertaking to prepare the EIA. Concerned publics include:
    local governments,  persons living and working in the vicinity of the project, those with interests in
    resources that may be affected i.e., indigenous peoples, and those concerned about protected areas
    and prime agricultural lands. A summary of public outreach activities, audience, number of persons,
    organizations  involved, concerns raised,  responses to comments and actual copies of written
    comments received should be included in the Annex.

 •  All  relevant plans  related to the proposed tourism project, for  example, engineering and  site
    preparation plans,  operations and  decommissioning/closure,  environmental  management,  and
    mitigation in whatever form these may take.

 •  All phases of the project from feasibility studies to site preparation to operations to closure and also
    plans to expand capacity at the current or adjacent sites.

 •  Alternative  approaches to  meeting the  purpose and need for  the  proposed  tourism project,
    including siting, designing,  constructing,  operating  and closing the project firstly to avoid  and
    prevent,  or secondly  to  reduce or  minimize adverse or improve beneficial environmental or
    socioeconomic impacts. The EIA should assess as appropriate the impacts of a range of reasonable
    and technically feasible alternatives as  well as the proposed project. The alternatives to the project
    must include a "no action"  alternative, as well as consideration  of best practices that may  not
    otherwise have been incorporated in the proposed project.  Other alternatives should be developed
    as needed to avoid or minimize significant adverse impacts associated with the proposal.

 •  Direct, indirect and  cumulative impacts and their significance level.

 •  Uncertainty and how that uncertainty will be addressed through  monitoring and contingency plans
    as may be needed to reduce risk of adverse impacts in the future.

 •  Specific commitments, including who  is responsible, what  will be  done, when and how  it will be
    monitored, reported and audited to confirm that commitments are met.

 Finally, a key part of the TOR is obtaining a legally binding commitment  from the project proponent that
 the approved EIA will be implemented  as  presented.   Such a  commitment adds to the legal
 enforceability of the outcomes of the EIA process.
 CAFTA-DR AND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENT AND LABOR ExcELLENCE-CCAD-USEPA PROGRAM               30

-------
Volume I Part 2 - EIA Technical Review Guidelines:                                2 EXAMPLE TERMS OF REFERENCE (TOR)
             Tourism                                                          CONCESSION PROJECTS
B.  DETAILS FOR CONCESSIONS PROJECTS

0   Table of Contents
    A general Table of Contents for the Environmental Impact Assessment (EIA) shall be provided. The
    Table of Contents shall be organized in such a manner as to facilitate the use of the EIA by reviewers
    and project implementers. ElAsfor larger projects should have a more detailed Table of Contents than
    those for smaller projects. At a minimum, the Table of Contents shall include the following:
    •   Acronyms and Abbreviations
    •   Executive Summary
    •   General Information
        o   Objectives and Justification
        o   Project Proponents
        o   Project Team
        o   Legal  and Regulatory Framework
    •   Project and Alternatives Description
    •   Environmental Setting
        o   Physical Environment
            •  Geologic Resources
            •  Soil Resources
            •  Water Resources
            •  Air and Climate
            •  Noise and Vibration
            •  Aesthetic Resources
        o   Biological Environment
            •  Vegetation/Flora
            •  Aquatic and Terrestrial Wildlife/Fauna
            •  Ecosystems: Terrestrial, Wetlands, Aquatic, Marine
            •  Endangered or Threatened Species and Habitat
            •  Protected Areas
        o   Social-Economic-Cultural Environment
            •  Socio-Economic Conditions
            •  Infrastructure
            •  Cultural, Archeological, Ceremonial and Historic Resources
            •  Land Use
    •   Assessment of Impacts to resources described in the Environmental Setting
    •   Mitigation and Monitoring Measures
    •   Environmental Management Plan
        o   Overview of Environmental Management Plan Organization  and Policy
        o   Project-wide Mitigation Plan
        o   Project- wide Monitoring Plan
        o   Management of Other On- or Off-Site Pollution Controls and Infrastructure
        o   Contingency Plans
            •  Performance-related Contingency Plan
            •  Natural Disaster Risk Response Plan
            •  Other Risk Response Plans
    •   Signed Commitment Statement
    •   Annexes
        o   Public Consultation
            •  Public Consultation Plan
            •  Summary of Public Outreach Activities
            •  Summary of Responses to Comments
            •  Copies of Written Comments
        o   Technical Supporting Materials
            •  Maps and Plans, in the sequence mentioned in the EIA document
            •  Charts and  Figures
            •  Details about predictive modeling used, calculations and assumptions
            •  Special Studies
        o   References
CAFTA-DR AND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENT AND LABOR ExcELLENCE-CCAD-USEPA PROGRAM                31

-------
Volume I Part 2 - EIA Technical Review Guidelines:
              Tourism
2 EXAMPLE TERMS OF REFERENCE (TOR)
          CONCESSION PROJECTS
1   Acronyms and Abbreviations
    All acronyms and abbreviations used in the EIA must be clearly and succinctly defined and described in
    this section.  This will relieve the reader of the need to search for the first occurrence of a word and the
    citing of the acronym or abbreviation in the text.

2   Executive Summary
    A general summary of the EIA shall be provided in this section. The summary shall be written using a
    vocabulary that can be easily understood by the public. It shall include at least the following
    information about the project from the EIA:
             Objectives and Justification
             Location
             Project Proponents
             Project Description
             Other Project Alternatives
             Environmental Setting
             Evaluation of Impacts
             Mitigation and Monitoring Measures
             Environmental Management Plan
             Issues raised by stakeholders and any  outstanding issues

3   General Information

    3.1 Objectives of and Justification for the  Proposed Project
3.1.1  Objectives: A statement of the general  and specific objectives (purpose) of the
      proposed project, including whether it is a new project, an expansion of an
      existing  project (e.g., increase in land area or increase in visitor capacity) or
      modernization of an existing operation.
3.1.2  Justification for the Project: Provide a justification for the proposed project
      (need) highlighting the benefits to surrounding communities and economic
      development of the region and country.

    3.2 Project Proponents
3.2.1  Names, addresses, telephone numbers, and applicable legal documentation of
      proponents (including developers, major equipment suppliers if part of project
      team, shareholders and providers of financing, and representatives).
3.2.2  Names and contact information for responsible parties within the organization.
3.2.3  Financial viability of the company (including a certified banking statement
      indicating that the company is financially stable and reputable).
3.2.4  Bonding requirements and proof of ability to meet bonding requirements
      sufficient to cover the anticipated costs of environmental management during all
      phases, as well as the costs, by a third party,  of decommissioning and long-term
      post-closure liabilities associated with the project.

    3.3 Project Team
    This section shall provide information on the multidisciplinary team that prepares the EIA.  The types
    of professionals included in the team shall be appropriate to the type of project and the type of
    environment in which the project is located and may include (but not be limited to) engineers,
    architects, biologists, geologists, hydrologists, air quality experts, archeologists, anthropologists,
    sociologists and economists. The information provided for each member of the EIA project team
    includes the following:
3.3.1  Names, addresses and registry numbers of contractors.
3.3.2  Names, contact information, qualifications and registry numbers of key personnel
      involved in the study; as well asan affidavit indicating their area of participation.
3.3.3  List of professionals/experts participating in the EIA, their areas of expertise,
      degrees, experience, professional registrations and stamps, seals and signatures.

    3.4 Legal  and Regulatory Framework
    This section of the EIA shall define the legal framework under which the EIA is being completed listing
    and summarizing requirements or alternatives used as benchmarks, and evidence of non-applicability
    or compliance, including:
3.4.1  Information that demonstrates rights and access:
   3.4.1.1    Ownership with written authorization
               C.2 Documentation of
                  Purpose and Need
                13.1 General
                  Information
               G.6 Financial
                  Assurance
               C.3.1 General
                  Information
               C.3.1 General
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                           32

-------
Volume I Part 2 - EIA Technical Review Guidelines:
              Tourism
2 EXAMPLE TERMS OF REFERENCE (TOR)
          CONCESSION PROJECTS
   3.4.1.2    Governmental authorization (if required)
   3.4.1.3    Period of lease/permit/concession agreement
   3.4.1.4    Maps showing the lease/permit/concession area
3.4.2 Applicable environmental standards, norms and requirements set forth at the
      international, national, regional and/or local levels
   3.4.2.1    In the absence of such standards, identify a  set of benchmarks used in the
              analysis
3.4.3 Required regulatory approvals and/or permits for all stages and their status
3.4.4 Applicable land use requirements (demonstrate conformity and compliance with
      applicable plans)
3.4.5 Applicable tourism strategies and plans - national, regional, and local
3.4.6 Applicable natural resource management or protected area management plans
      and responsible agency(ies) (demonstrate conformity and compliance with all
      applicable plans)

4    Project and Alternatives Description
     The project proponent shall submit a full description and location of the proposed project and
     reasonable alternatives including ancillary facilities and operations such as the camp/housing for
     construction and operation phases, borrow and disposal areas, sanitary services, waste disposal and
     transportation infrastructure, etc. as addressed through 4.1 to 4.3 below. It shall include at a
     minimum:

     4.1  Location
     The general location of the project and associated activities in terms of:
4.1.1 Political-administrative location (region, district, town or other relevant political-
      administrative units) with accompanying location map
4.1.2 Means of site access - i.e., by air,  river, road, train or vehicle
4.1.3 Latitude and  longitude of project area
4.1.4 Maps of project area at a scale of no less than  1:50,000 or as required by the
      regulatory agency
   4.1.4.1    Project plat plan and location on a fold-out 11" X 17" page.
   4.1.4.2    Indicate the project area and the direct and indirect areas of influence for
              the physical, biological and social-economic-cultural impacts
   4.1.4.3    All drawings should present scale and key coordinates or benchmarks as
              latitude/longitude, Universal Transverse Mercator (UTM) coordinates, or
              local survey plate that can be cross-referenced to latitude/longitude or
              UTM coordinates
4.1.5 Has the area  of the project ever been a tourist destination  before?
   4.1.5.1    If so, show other tourist facilities in the area on the maps, including those
              under construction and, if known, those in the design phase

     4.2  Summary of Proposed Project and Alternatives
     All project alternatives that are reasonable and feasible and meet the purpose and need for the
     proposed project shall be identified, summarized in this section, and evaluated in the EIA as
     appropriate. In addition to the proposed project, such alternatives include alternative locations,
     alternative site configuration of elements of the project, alternative size, and alternative plans for
     construction, operation and decommissioning of the project including best practices that may avoid
     and/or reduce the adverse impacts to the physical, biological or social-economic-cultural
     environments.

     If the project area or the buffer zone of the project area for an alternative is in an ecologically fragile
     are, the description of the alternative must include a clear justification for not opting for another site.
     Identify which alternatives will be carried through the analysis in the EIA and the basis for that
     decision.

     4.3  Project and Alternatives Details
     The EIA shall provide specific project details for the proposed project and each alternative as identified
     in subsections 4.3.1 through 4.3.8. The level of detail presented shall be the same for the proposed
     project and each alternative evaluated. The following project details shall be provided:
4.3.1 Type and nature of the project
   4.3.1.1   Type (guided hikes or horseback trips, trail development, off-road vehicles,
             campsites, water sports, etc.)
   4.3.1.2   Overview of all proposed facilities and activities and their relationship
                   Information
                C. Project and
                   Alternatives
                   Description

                C.3.2 Overall Project
                   Description
                   Information
                C.3.5 Maps, Diagrams,
                   Site Design and Plan
                C.3.2 Overall Project
                   Description
                   Information
                C.3.5 Project
                   Alternatives
                Table C-4
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                              33

-------
 Volume I Part 2 - EIA Technical Review Guidelines:                                2 EXAMPLE TERMS OF REFERENCE (TOR)
	Tourism	CONCESSION PROJECTS

    4.3.1.3   A detailed drawing showing access points, layout of all project
             components including on-site roads, walkways and paths, existing
             structures, topography and natural features such as water bodies,
             wetlands and geologic structures
    4.3.1.4   A summary table showing the type, quantity and size of each component
    4.3.1.5   Expected life of operation
    4.3.1.6   Anticipated use: maximum, minimum and average by month and season
             for:
             • Day use
             • Overnight stays (if applicable)
    4.3.1.7   Recreational,  leisure and adventure uses by visitors of surrounding natural
             and cultural resources
             • Type of use (type of activities, motorized or non-motorized, etc.)
             • Anticipated use (maximum, minimum and average  by month and
               season)
 4.3.2  Principal project facilities
        Location and design information - primary material of construction (wood, brick,
        stone, etc.), layout and dimensions. Design drawings should be provided for
        each facility, including:  Plan (overhead view), Elevations (front view), Profiles
        (side view) and Sections.
    4.3.2.1    Hiking trails and backcountry camping
             • Trails
                 o  Widths and layout
                 o  Surface  material
                 o  Erosion  control
             • Camping sites (if applicable)
                 o  Number, locations, capacity per location and layout
                 o  Site amenities (tables, benches, barbeque, fire pits, etc.)
                 o  Bath/toilet facilities
                 o  Water taps
                 o  Fuel sources
                 o  Solid waste management
    4.3.2.2   Horseback riding
             • Trails
                 o  Widths and layout
                 o  Surface  material
                 o  Erosion  control
             • Camping sites (if applicable)
                 o  Number, locations, capacity per location and layout
                 o  Site amenities (tables, benches, barbeque, fire pits, etc.)
                 o  Bath/toilet facilities
                 o  Water taps
                 o  Fuel sources
                 o  Solid waste management
             • Stables
                 o  Location
                 o  Dimensions
                 o  Animal waste management
                 o  Toilet facilities
             • Pastures
                 o  Location
                 o  Dimensions
    4.3.2.3   Off road vehicles
             • Types, number, sizes and fuels of vehicles
             • Trails
                 o  Widths and layout
                 o  Surface  material
                 o  Erosion  control
             • Vehicle  storage

 CAFTA-DR AND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENT AND LABOR ExcELLENCE-CCAD-USEPA PROGRAM                34

-------
 Volume I Part 2 - EIA Technical Review Guidelines:                                2 EXAMPLE TERMS OF REFERENCE (TOR)
	Tourism	CONCESSION PROJECTS

             • Vehicle fueling and repair facilities
             • Toilet facilities
    4.3.2.4   Zip lines and canopy walks
             • Start point, end point and route (for canopy walks)
             • End point
             • Toilet facilities
    4.3.2.5   River rafting/kayaking/canoeing
             • Put in and take out locations
             • Camping or picnicking sites
                 o  Number, locations, capacity per location and layout
                 o  Site amenities (tables, benches, barbeque, fire pits, etc.)
                 o  Bath/toilet facilities
                 o  Water taps
                 o  Solid waste  management
             • Office and equipment storage areas
                 o  Toilet facilities
    4.3.2.6   Lake-based  recreation (boating, skiing, swimming, etc.)
             • Types of uses
             • Dock
             • Developed beach
                 o  Beach uses
                 o  On-beach structures (recreational equipment rental/storage,
                    bath/toilet facilities, bar/store/restaurant [refer to Resort TOR],
                    lifeguard towers, sun  shades, etc.)
                 o  Shoreline erosion protection
                 o  Type and source of beach material (if applicable)
             • Equipment roster (types, numbers and sizes of equipment made
               available to clients)
             • On-site facilities (equipment storage, toilets, etc.)
    4.3.2.7   Sport fishing (lake or river)
             • Types of services  and  equipment provided
             • Facilities
 4.3.3  Onsite support facilities
        Location and design information - primary material of construction (wood, brick,
        stone, etc.), layout and dimensions. Design drawings should be provided for
        each facility, including: Plan (overhead view), Elevations  (front view), Profiles
        (side view) and Sections.
    4.3.3.1   Storage areas and warehouses
             • Locations
             • Sizes
             • Materials to be stored
    4.3.3.2   Parking lots
             • Locations
             • Sizes
             • Lighting
    4.3.3.3   Repair shops
             • Activities
             • Locations
             • Sizes
    4.3.3.4   Fuel stations
             • Commercial or for operator use only
             • Locations
             • Number, size and configuration of tanks (buried or above ground, leak
               protection, etc.)
    4.3.3.5   Electrical energy
             • Consumption, including energy conservation measures
             • Source-offsite
                 o  Transmission lines (if  necessary)
                 o  Substation (if necessary)

 CAFTA-DR AND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENT AND LABOR ExcELLENCE-CCAD-USEPA PROGRAM                35

-------
Volume I Part 2 - EIA Technical Review Guidelines:
             Tourism
                                                                    2 EXAMPLE TERMS OF REFERENCE (TOR)
                                                                             CONCESSION PROJECTS
                                                                                  C.4.1 Water and
                                                                                     Sanitation Facilities
                                                                                  Table C-8
            • On-site power generation power
                o  Type
                o  Emissions and noise controls (if applicable)
            • On-site distribution (routes, overhead or buried)
   4.3.3.6   Water supply
            • Requirements (m3/day), including conservation measures
            • Rights
            • Sources
            • Treatment
            • Distribution
   4.3.3.7   Waste handling and disposal
            • Sewers
            • Wastewater treatment
                o  Quantity
                o  Type
                o  Discharge
            • Solid waste
                o  Quantity (kg/day and m3/day), including waste reduction
                   measures
                o  Collection
                o  Separation  (if any)
                o  Disposal
4.3.4  Access and transportation
   4.3.4.1    Roads
            • Identify all new and existing roads to be used (including closed roads
              that will be reopened, if applicable)
                o  Traffic volume, operating speeds and trip times
                o  Closed roads that will be reopened
            • Detailed information on any access, on-site and recreational activity
              roads to be constructed or upgraded
                                                                                  C.4.2 Solid and
                                                                                     Hazardous Waste
                                                                                  Table C-9
                                                                                   1.3.7 Transportation:
                                                                                     Roads, Pathways,
                                                                                     Air Strips, and Boat
                                                                                     Facilities
                                                                                  Table C-2
                o  Location
                o  Timing of construction
                o  Road surface and shoulder width and barriers
                o  Grade
                o  Construction methods including clearing and grubbing
                o  Construction materials
                o  Compaction
                o  Stream and wetland crossings and associated designs
                o  Animal crossings
                o  Sedimentation and erosion prevention and control structures and
                   practices
                o  Stabilization methods for cuts and fills
                o  Typical elevations for each type and situation of road displaying
                   construction materials, levels of compaction and erosion and
                   sedimentation features
                o  Location and size (area and volume of material) of borrow pits
                o  Lighting (where applicable)
                o  Operation
                o  Closure plan (if applicable)
                o  Traffic volume, operating speeds and trip times
            • Dust control for construction and operation
            • Maintenance
            • Roster for construction and maintenance equipment, specifying type
              and quantity by size, motor size, and fuel requirements
4.3.5  Best Practices
        Description of standard best practices to be incorporated into the project.
4.3.6  Construction phase and timetable
   4.3.6.1   Schedule for each phase of construction for all project and ancillary
            facilities (including temporary structures) including, but not limited to:
                                                                                  C.3.6 Details on
                                                                                     Construction
                                                                                     Procedures
                                                                                  Table C-l
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                       36

-------
 Volume I Part 2 - EIA Technical Review Guidelines:                               2 EXAMPLE TERMS OF REFERENCE (TOR)
	Tourism	CONCESSION PROJECTS

             • Mobilization
             • Road construction and improvements
             • Land clearing
             • Blasting
             • Erosion and sediment control
             • Excavation and subgrade preparation
             • Foundation preparation
             • Concrete work
             • Construction or installation of each project facility
             • Stabilization of disturbed areas
    4.3.6.2   A GANTT or critical path management chart for the entire project, from
             start to finish
    4.3.6.3   Borrow and fill material (if applicable)
             • Locations from which fill material will be sourced
             • Locations where fill material will be placed on-site
             • Locations where fill and other construction material will be temporarily
               stockpiled/stored
             • Borrow and spoil disposal
    4.3.6.4   Key areas (related to environmental sensitivity/importance) that will
             remain undisturbed during construction (waterways, wetlands, forested
             areas and other "green space," etc.)
    4.3.6.5   Erosion control structures such as:
             • Temporary diversions for waterways
             • Erosion control barriers
    4.3.6.6   Equipment
             • Equipment Roster, specifying type and quantity by size, weight, motor
               size,  and fuel requirements for each piece of equipment or machinery
               used in each activity
             • Transportation mobilization and mobilization frequency
             • Machinery and equipment mobilization routes to be used, as well as the
               features of the ways on which they will be transported, including a map
               of routes, as applicable, and mobilization.                               C.6 Manpower and
    4.3.6.7   Labor during construction                                                  Local Purchases
             • Number and type of employees (by local hire and non-local hire) by field
               of expertise
             • Days per week
             • Hours per day
             • Shifts per day
    4.3.6.8   Raw materials to be used for construction
             • Give  a complete list of the raw materials and construction materials to
               be used, indicating the amounts per day, month, and the storage means
             • Include an inventory of chemical, toxic or hazardous substances, active
               elements, sites and storage means, safety aspects regarding
               transportation and handling and any other relevant information
    4.3.6.9   Construction camp (if applicable)
               Description of the camp including but not limited to:
             • A map showing all facilities at a legible scale appropriate to the size of
               the project
                 o  Buildings by type (use) and size
                 o  Roads
                 o  Electrical transmission lines and/or substation
                 o  Drainage
             • Water supply and distribution
                 o  Distribution system
                 o  Use (m3/day)
                 o  Rights
                 o  Sources
             • Waste handling and disposal components
                 o  Sewers

 CAFTA-DR AND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENT AND LABOR ExcELLENCE-CCAD-USEPA PROGRAM               37

-------
Volume I Part 2 - EIA Technical Review Guidelines:
             Tourism
2 EXAMPLE TERMS OF REFERENCE (TOR)
          CONCESSION PROJECTS
                o  Wastewater treatment
                o  Solid waste facilities
            • Energy generation and use requirements (including fuelwood
              consumption and source)
            • Closure or transition from construction camp to onsite employee
              housing
   4.3.6.10  Decommissioning of temporary structures including measures for
            returning the area to pre-construction features
4.3.7  Operation phase
   4.3.7.1    Description of how the project would operate (seasonally, monthly, daily,
             hourly, as appropriate)
   4.3.7.2   Operation information
            • Roster of equipment and machinery to be used during operation,
              specifying type and quantity by size, weight, motor size, and fuel
              requirements for each activity
            • Labor during operation
                o  Number and type of employees (by local  hire and non-local hire)
                   by field of expertise
                o  Days per week
                o  Hours per day
                o  Shifts per day
            • Raw materials to be used for  operation
                o  List of the raw materials to be used, indicating the amounts per
                   day, month, and the storage means
                o  Inventory of chemical, toxic or hazardous substances, active
                   elements, sites and storage means, safety aspects regarding
                   transportation and handling and any other relevant information
4.3.8  Closure and decomissioning plan
      If it becomes clear that closure will be required, or when the project nears the
      the end of its service life, the project operator shall contact the proper regulatory
      agency(ies) to obtain the environmental guidelines to carry out the closure or
      decommissioning.
   4.3.8.1    The project description shall include at least a general Restoration and
             Closure Plan, recognizing that terms of closure may be very different
             when this phase approaches
   4.3.8.2   The description of restoration measures should include the size of the area
            to be restored as well as concurrent, temporary and final restoration
            measures to be used and their schedules.  For each measure include:
            • Area to be addressed
            • Timing and schedule for executing measures
            • Equipment and structure removal or conversion
            • Remedial measures, including success indicators and contingency
              measures if initial efforts are  unsuccessful

5   Environmental Setting
    Based on information available from the literature, government and special studies or other sources,
    the EIA shall provide information on environmental setting for the different types of physical,
    biological and social-economic-cultural environments for the current situation, important trends and
    predicted situation in the absence of the proposed project. All sources of data must be cited in the EIA
    when and where they are used.  Indicate the direct and indirect and cumulative impact areas of
    influence for physical, biological, and social-economic-cultural impacts and basis for defining area.
    This section shall include at a minimum, the following information:

Physical Environment

    5.1 Geologic Resources and Hazards
5.1.1  Topography and slope conditions and geomorphology
5.1.2  Seismicity and stability characteristics
   5.1.2.1   Indicate the general seismic and tectonic features of the surrounding
            areas:
               C.6 Manpower and
                  Local Purchases
               C.7 Closure
               D. Environmental
                  Setting
               Table D-l
               D.2 Physical
                  Environment

               D.2.1 Geology and
                  Soils
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                         38

-------
Volume I Part 2 - EIA Technical Review Guidelines:
             Tourism
2 EXAMPLE TERMS OF REFERENCE (TOR)
          CONCESSION PROJECTS
            • Seismic sources close to the project area
            • Seismic history
   5.1.2.2   Volcanic activity (must be provided by all the projects that are located
            within a radius of 30 km from an active  volcanic emission center)
            • Indicate the general volcanic features of the area near the site
            • Historical eruptions
            • Period of recurrence
            • Type of eruptions
            • Affected areas and high risk areas
   5.1.2.3    Describe project areas susceptible to soil liquefaction; planned, active,
             and abandoned mines; karst terrain; and areas of potential ground
             failure, such as subsidence, slumping, and land sliding

    5.2 Soil Resources
    The EIA shall describe baseline soil resources, and make use of maps, tables and accompanying
    narrative text to describe the soils at the project site and along new or reconditioned access routes
    associated with the project and included in the EIA.
5.2.1  Types, capacity and uses
5.2.2  Stability and permeability
5.2.3  Erosion and sedimentation potential
5.2.4  Quantity and quality available for revegetating and restoring the disturbed area
      at time of closure
               D.2.1 Geology and
                  Soils
    5.3 Water Resources
5.3.1  Surface water
   5.3.1.1   Names and locations on maps of all permanent and intermittent streams,
            rivers, wetlands, lakes and reservoirs within the area of influence
   5.3.1.2   Flow (only necessary if water source will be surface water or if wastewater
            will be discharged to surface water)
            • The monthly minimum, mean and maximum recorded flows in m3/s of
              the river at the diversion point
            • Location of gauging stations where data were gathered  to derive the
              curves
            • 2-, 10-, 25-,  50- and 100-year runoff events and 100-yr floodplain for
              streams and rivers
   5.3.1.3   Seasonal fluctuations in  area and volume of wetlands, lakes and reservoirs
   5.3.1.4   Delineation of watersheds and water drainage pattern in the area of
            influence using cadastral/aerial/remote sensing satellite imageries (map)
            • Runoff characteristics of watersheds
   5.3.1.5   Inventories of consumptive and non-consumptive use
   5.3.1.6   Surface water balance (only necessary if water source will be surface
            water)
            • Existing uses by type and volume
            • Capacity
5.3.2  Groundwater
      Provide a map and identify and describe aquifiers and underground waters
      adjacent to the project, indicating the depth of the water table along with trend
      data:
   5.3.2.1   Hydrogeologic characteristics of the project site including  fuel storage
            areas, wastewater discharge areas, and golf courses (vadose zone and
            aquifers)
            • Water table levels (dry and rainy season)
            • Flow regime
            • Flow direction
            • Influences of geologic structures (faults, contacts, bedrock fracturing,
              etc) and surface water bodies
   5.3.2.2   Location and characteristics of all existing springs and wells in the area of
            influence (on topographic map)
            • Flow/yield data for each spring and well (including water levels in wells)
            • Depth and construction information for each well
               D.2.2 Water Resources

               D.2.2.1 Surface Water

               D.2.2.2 Marine Waters
               D.2.2.3 Groundwater
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                        39

-------
 Volume I Part 2 - EIA Technical Review Guidelines:                                 2 EXAMPLE TERMS OF REFERENCE (TOR)
	Tourism	CONCESSION PROJECTS

             •  Existing uses by type and volume
             •  Capacity available
    5.3.2.3   Groundwater recharge data
    5.3.2.4   Groundwater potential yield (only necessary if water source will  be
             groundwater)
 5.3.3  Water quality (only necessary if project will discharge wastewater)
    5.3.3.1   Existing water quality data
             •  Locations of all water quality monitoring stations in and around the
                project area (with direction  and distance from the site)
             •  Water quality data for each  station for those parameters likely to be
                affected by project construction, operation or maintenance
             •  Physical, chemical and biological water quality characteristics, including
                water temperature and dissolved oxygen concentrations
    5.3.3.2   Supplemental sampling and analysis (if existing data is not adequate to
             characterize water quality)
              Sampling and Analysis Program in annex
             •  Proposed locations of representative monitoring stations upstream and
                downstream of proposed project activities
             •  Monitoring program design  with at least a year of baseline data being
                collected
                o Parameters (including as appropriate, physical, chemical and
                  biological)
                o Frequency of collection
                o Analytic methods
    5.3.3.3   Surface water and groundwater standards that apply to the project
             •  Current uses
             •  Standards for current uses (in the absence of such standards, identify a
                set of benchmarks used in the analysis)

     5.4 Air and Climate                                                             D 2 3 Ajr and c|jmate
     Baseline information for air resources shall be collected for at least one year or as required by the
     regulatory agency and shall include at a minimum the following:
 5.4.1  Climate and meteorology
    5.4.1.1.   Source of data (meteorological station(s) from which climatological data
             have been  obtained)
    5.4.1.2.   Temperature variations
    5.4.1.3.   Relative humidity
    5.4.1.4.   Solar radiation and evaporation rates
    5.4.1.5.   Rainfall (total precipitation, rainfall intensity, and duration by month)
    5.4.1.6.   Wind Rose (Wind direction and speed, 24 hourly data)
    5.4.1.7.   Statistical analysis of the data
    5.4.1.8.   Risk of high impact storms, storm surges, hurricane levels, tropical storms
             frequency and seasonality

     5.5 Noise and Vibration                                                                .
     Present a description of the noise and vibration  levels for receptors near where noise generating        U.Z.I IMOISe ana
     activities of the project may occur. The EIA shall include:                                         Vibration
 5.5.1  Location of monitoring stations
 5.5.2  Daytime and night time noise levels (measured  in decibels)
 5.5.3  Inventory of existing noise sources

     5.6 Aesthetic and Visual Resources                                            C.2.5 Aesthetic
 5.6.1  Photos presenting baseline panoramic views of the project site from potential          Resources
       viewpoints
 5.6.2  Viewsheds or other aesthetic or landscape resources
 5.6.3  Existing sources of light contamination

 Biological Environment
     The EIA shall provide detailed information on the location and condition of ecosystems in and around
     the project area in the form of narrative, maps and tables, including the following:

     5.7 Vegetation/Flora

 CAFTA-DR AND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENT AND LABOR ExcELLENCE-CCAD-USEPA PROGRAM                40

-------
Volume I Part 2 - EIA Technical Review Guidelines:
              Tourism
2 EXAMPLE TERMS OF REFERENCE (TOR)
          CONCESSION PROJECTS
5.7.1 Vegetative mapping of terrestrial and wetland habitats (aquatic and marine if
      appropriate) for project area and areas affected by the project (e.g., project site
      and areas around new access roads)
5.7.2 Species and structure (abundance, density, status, plant communities, presence
      of invasive species, etc.)

    5.8 Aquatic and Terrestrial Wildlife/Fauna
5.8.1 Fish and Aquatic  Resources (for water-based concession activities)
   5.8.1.1.   Identification offish, mussel, macroinvertebrate and other aquatic species
             •  Spatial and temporal distribution
             •  Species life stage composition
             •  Standing crop
             •  Age and growth data
             •  Spawning run timing
             •  Extent and  location of spawning, rearing, feeding and wintering habitat
5.8.2 Wildlife Resources (for land-based concession activities)
   5.8.2.1.   Species (including status, i.e., endemic, migratory, exotic, endangered,
             threatened, keystone, etc.), life history, and seasonal use
   5.8.2.2.   Breeding areas
   5.8.2.3.   Mating and brooding areas
   5.8.2.4.   Migratory  corridors (if applicable)
   5.8.2.5.   Important wildlife use areas (roosts, clay licks, etc.)

    5.9 Ecosystems: Terrestrial, Wetlands, Aquatic, Marine
    Much if not all that may be needed to address the environmental setting for terrestrial, wetlands,
    aquatic and/or marine ecosystems may have been covered in Sections 5.7 and 5.8.  This section is not
    intended to duplicate that information; rather, it should integrate the information to ensure that the
    structure and function of each ecosystem is adequately presented.

    5.10  Endangered or Threatened Species and Habitats
    Sections 5.7 and 5.8 should identify all species in the project area. This section should highlight all
    endangered and threatened species and critical habitat that potentially occur in the vicinity of the
    project.

    5.11  Protected Areas
    Identify on maps the specific locations and boundaries of relevant national parks, sanctuaries,
    reserves, etc., as well as any areas proposed for protection.  Provide a brief narrative description of
    each area.

Social-Economic-Cultural Environment

    5.12  Socio-Economic Conditions
    Identify nearby human settlements including the following information for each settlement:
5.12.1  Population (size, gender and age distribution)
5.12.2  Cultural characteristics (religion, ethnic composition, languages spoken, etc.)
5.12.3  Economic activities (employers, employment and incomes)
5.12.4  Tax  base
5.12.5  Crime rates
5.12.6  Literacy rates
5.12.7  Community organizations
5.12.8  Public Health and Safety
   5.12.8.1.  Diseases in the project area (including the sources of data and the
             methodology used to collect and analyze the data)
   5.12.8.2.  Level of emergency services and access to clinics, doctors and hospitals
   5.12.8.3.  Existing  practice for assessment of occupational health
5.12.9  Skills, services and goods availability in the communities

    5.13  Infrastructure
    For each human settlement identified in subsection 5.12, describe the infrastructure in or serving the
    settlement, including the following information:
5.13.1  Transportation infrastructure
   5.13.1.1.  Roads- Location and condition of all existing roads in the project area that
             may be used by the project or tourists coming to the project
             •  Surface materials
               D.3 Biological
                  Environment

               D.3.1 Flora
               D.3.2 Fauna
               D.3.3 Ecosystems
               D.3.4 Endangered or
                  Threatened Species
                  and Habitats

               D.3.5 Protected Areas
                  and Sensitive
                  Ecosystems
               D.4 Social-Economic-
                   Cultural
                   Environment

               D.4.1 Socio-Economic
                   Conditions and
                   Resources




               D.4.2 Infrastructure
                   Systems and
                   Equipment
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                           41

-------
Volume I Part 2 - EIA Technical Review Guidelines:
             Tourism
2 EXAMPLE TERMS OF REFERENCE (TOR)
          CONCESSION PROJECTS
            •  Erosion and sediment control
            •  Maintenance programs (what, when and whom)
            •  Description of anticipated third-party improvements (government or
               entity other than the proponent)
            •  Traffic capacity, patterns and densities
            •  Safety levels and current circulation issues
   5.13.1.2. Airports and air strips - Locations, conditions, capacities, current uses and
            trends
   5.13.1.3. Other transportation infrastructure as applicable such as rail, bus,
            pipelines for fueling, harbors for cruise ships, and marinas for boats -
            Locations, conditions, capacities, current uses and trends
5.13.2  Public health infrastructure
   5.13.2.1. Drinking water supplies and treatment
   5.13.2.2. Wastewater treatment and management
   5.13.2.3. Solid and hazardous waste management and treatment
5.13.3  Communications infrastructure
   5.13.3.1. Types of communications systems
   5.13.3.2. Types of transmission (wired or wireless)
   5.13.3.3. Locations of transmission lines (if applicable)
   5.13.3.4. Locations of microwave towers and/or antennae (if applicable)
5.13.4  Energy infrastructure
   5.13.4.1. Types of energy
   5.13.4.2. Sources including location and description of generating facilities in the
            area of influence
   5.13.4.3. Transmission lines and/or pipelines
   5.13.4.4. Fuel storage facilities

    5.14  Cultural, Archeological, Ceremonial and Historic and Resources
    Identify all cultural, archaeological, ceremonial and historic resources within the area of influence,
    including the following information:
5.14.1  Data and maps relating to archeological, cultural, ceremonial, and historic sites
        in the  direct vicinity of the project
5.14.2  Information on indigenous people or other traditional cultures, if any

    5.15  Land Use
    Describe actual and potential land use showing location, size and proximity within and surrounding
    the project area, including land use maps, and to extent possible, integrated into one map.
5.15.1  Population centers, including information and locations of
   5.15.1.1.  Schools
   5.15.1.2.  Cemeteries
   5.15.1.3.  Churches
   5.15.1.4.  Other public buildings
   5.15.1.5.  Housing (including housing density)
   5.15.1.6.  Commercial areas
5.15.2  Agricultural lands
5.15.3  Forested lands
5.15.4  Protected areas (including but not limited to)
   5.15.4.1.  National parks
   5.15.4.2.  Wildlife refuges
5.15.5  Wetlands and mangroves
5.15.6  Other  environmentally sensitive areas
5.15.7  Tourism and recreation areas
   5.15.7.1.  Recreation facilities
   5.15.7.2.  Eco-cultural-tourist locations
5.15.8  Culturally sensitive areas
5.15.9  Flood plains and water bodies
5.15.10 Coastal zones
5.15.11 Other  land uses as appropriate
               D.4.2.1 Transportation
                  Infrastructure
               D.4.2.2 Public Health
                  Infrastructure
                ).4.2.3 Communica-
                  tions Infrastructure
               D.4.2.4 Energy
                  Infrastructure
               0.4.3 Cultural,
                  Archeological,
                  Ceremonial and
                  Historic Resources
               D.4.4 Land Use
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                          42

-------
Volume I Part 2 - EIA Technical Review Guidelines:
              Tourism
2 EXAMPLE TERMS OF REFERENCE (TOR)
          CONCESSION PROJECTS
6   Assessment of Impacts
    The EIA shall provide information on potential impacts (direct, indirect and cumulative) and the
    magnitude and frequency of potential impacts on physical, biological, social-economic-cultural
    resources resulting from construction, operation and closure of the proposed project and alternatives.
    The assessment shall use standardized predictive methods, such as models, to determine the specific
    range of impacts on environmental and socio-economic resources. The EIA shall identify which
    impacts are significant and the criteria used to make this judgment.  Critical data input from project
    description and environmental setting analysis projecting the conditions in the environmental setting
    in the absence of the proposed project shall be used as the baseline upon which potential impacts are
    forecast. The EIA shall also identify sources of data used in the analysis and the uncertainties
    associated with the outputs of each method used.

Physical Impacts

    6.1  Geologic Resources and Hazards
    Potential impacts to geologic resources and potential effects on project structures shall be described
    including but not limited to the following:
6.1.1     Geologic hazards and potential effects on project structures
6.1.2     Changes in topography and drainage patterns
6.1.3     Overall assessment of significance of direct, indirect and cumulative impacts
         for all phases of the proposed project based upon analysis of magnitude,
         frequency, scope and duration in context

    6.2  Soil Resources
    Potential impacts to soil resources shall be described. The analysis shall include, but not be limited to
    the following:
6.2.1     Soil quality
   6.2.1.1.   Contamination (accidental spills of fuel, oil or other hazardous substances)
   6.2.1.2.   Impacts on use
6.2.2     Erosion, slope alteration, vegetation removal and drainage patterns
   6.2.2.1.   Models for soil erosion should be included using methods like USLE,
             defining the areas with high erosion  potential
   6.2.2.2.   Sediment accumulation and transport
6.2.3     Overall assessment of significance of direct, indirect and cumulative impacts
         for all phases of the proposed project based upon analysis of magnitude,
         frequency, scope and duration in context

    6.3  Water Resources
    Potential impacts to surface water and groundwater shall be described. The analysis shall include but
    not be limited to the following:
6.3.1     Geomorphology
   6.3.1.1.   Location  of all stream or wetland crossings by roads and trails
   6.3.1.2.   Modification/diversion in the existing drainage pattern
   6.3.1.3.   Bank erosion  (stream crossings, shore developments  and dredging)
   6.3.1.4.   Potential for increased flash flooding
6.3.2     Quality
   6.3.2.1.   Runoff, erosion and sedimentation from roads, trails, disturbed areas and
             stream crossings
             • Sources
             • Receiving waters
             • Concentrations
                 o  Physical parameters
                 o  Chemical parameters
                 o  Biological parameters
   6.3.2.2.   Description of impact from wastewater discharges
   6.3.2.3.   Spills and accidents (chemicals, hazardous wastes and fuel spills)
6.3.3     Overall assessment of significance of direct, indirect and cumulative impacts
         for all phases of the proposed project based upon analysis of magnitude,
         frequency, scope and duration in context
                E. Potential Impacts
                F. Assessing Impacts

                F.I Overview of Using
                  Predictive Tools for
                  an EIA

                F.2 General
                  Approaches for
                  Prediction of
                  Impacts

                Appendix C

                E.2 Physical
                  Environment

                E.2.1 Geology, Soils
                  and Ocean
                  Topography
                Table E-l

                F.3 Soils and Geology
                  Impact Assessment
                  Tools
                E.2.2 Water Resources
                Table E-2

                F.4 Water Resources
                  Impact Assessment
                  Tools
               Table F-2
               Table F-3
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                            43

-------
Volume I Part 2 - EIA Technical Review Guidelines:
             Tourism
2 EXAMPLE TERMS OF REFERENCE (TOR)
          CONCESSION PROJECTS
    6.4 Air and Climate
    Potential impacts to air resources shall be described including but not limited to the following:
6.4.1    Impacts on ambient air quality
   6.4.1.1.  Sources (e.g., windblown dust, fixed and mobile equipment)
   6.4.1.2.  Concentrations
   6.4.1.3.  Receptors (e.g., communities, schools, soils, water bodies, ecosystems)
6.4.2    Greenhouse gas generation
6.4.3    Overall assessment of significance of direct, indirect and cumulative impacts
        for all phases of the proposed project based upon analysis of magnitude,
        frequency, scope and duration in context

    6.5 Noise and Vibration
    Potential impacts from noise shall be described including but not limited to the following:
6.5.1    Potential noise levels at different representative sites in the project area and in
        communities near the project area
6.5.2    Overall assessment of significance of direct, indirect and cumulative impacts
        for all phases of the proposed project based upon analysis of magnitude,
        frequency, scope and duration in context

    6.6 Aesthetic and Visual Resources
    Potential impacts to Aesthetic Resources, including light pollution, shall be described including but not
    limited to the following:
6.6.1    Impacts on visual resources and landscapes
6.6.2    Increases in light contamination
6.6.3    Overall assessment of significance of direct, indirect and cumulative impacts
        for all phases of the proposed project based upon analysis of magnitude,
        frequency, scope and duration in context

Biologic Impacts
    Potential impacts to biological resources shall be described and quantified including but not limited to
    the following:

    6.7 Vegetation/Flora and Associated Ecosystems
    Describe and quantify alterations in vegetative cover due to:
6.7.1    Deforestation or wetlands destruction (associated with construction and
        fuelwood use)
6.7.2    Other vegetative type conversions
   6.7.2.1.  Direct vegetative removal
   6.7.2.2.  Indirect (e.g., poisoning by dust and pesticides)
6.7.3    Wildfires
6.7.4    Increased road and trail access in remote areas leading to destruction of
        existing vegetative cover (land use changes)
6.7.5    Spread of noxious or invasive species
6.7.6    Overall assessment of significance of direct, indirect and cumulative impacts
        for all phases of the proposed project based upon analysis of magnitude,
        frequency, scope and duration in context

    6.8 Aquatic and Terrestrial Wildlife/Fauna and Associated Ecosystems
    Describe and quantify alterations in aquatic and terrestrial wildlife populations due to:
6.8.1    Fish and Aquatic Resources
   6.8.1.1.  Loss in habitat (e.g., spawning, rearing, juvenile, or adult habitats) from
            changes in water quality due to sedimentation
   6.8.1.2.  Disturbance of aquatic resources during construction, operations, or
            maintenance activities, including equipment noise, erosion and
            sedimentation, or vehicular movements
   6.8.1.3.  Poisoning from fertilizers and pesticides
   6.8.1.4.  Increased fishing
6.8.2    Wildlife Resources
   6.8.2.1.  Loss of habitat, migratory routes/corridors, and breeding areas due to
            changes in vegetative cover/wetlands loss
               E.2.3 Air Resources
               Table E-3

               F.5 Air Resources
                  Impact Assessment
                  Tools
               Table F-5
               E.2.4 Noise and
                  Vibration
               Table E-4

               F.6 Noise Impact
                  Assessment Tools

               E.2.5 Aesthetic
                  Resources

               F.7 Aesthetic/Visual
                  Resource Impact
                  Assessment Tools
               Table F-6

               E.3 Biological
                  Environment
               Table E-5

               E.3.1 Terrestrial
                  Species and
                  Associated
                  Ecosystems
               E.3.2 Aquatic
                  Ecosystems

               F.8 Flora, Fauna,
                  Ecosystems and
                  Protected Areas
                  Impact Assessment
                  Tools
               Table F-2
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                         44

-------
Volume I Part 2 - EIA Technical Review Guidelines:
             Tourism
2 EXAMPLE TERMS OF REFERENCE (TOR)
         CONCESSION PROJECTS
   6.8.2.2.   Disturbance of habitat, migratory routes/corridors and breeding areas due
            to project construction, operation, and maintenance, recreational use, and
            human settlement associated with the project (e.g., noise, vibration,
            illumination, vehicular movement)
   6.8.2.3.   Loss or contamination of drinking water for wildlife species
   6.8.2.4.   Poisoning (e.g., direct contact with toxic wastes/substances)
   6.8.2.5.   Animals attracted to garbage and food waste generated at construction
            camps and campsites
   6.8.2.6.   Increased hunting
6.8.3    Overall assessment of significance of direct, indirect and cumulative impacts
        for all phases of the proposed project based upon analysis of magnitude,
        frequency, scope and duration in context

    6.9 Endangered or Threatened Species or Habitats
    Describe and quantify impacts to endangered or threatened species or habitats
6.9.1    Biodiversity
6.9.2    Individual  species (with special emphasis on endemic, rare, threatened and
        endangered species)
6.9.3    Overall assessment of significance of direct, indirect and cumulative impacts
        for all phases of the proposed project based upon analysis of magnitude,
        frequency, scope and duration in context

    6.10  Protected Areas

Social-Economic-Cultural Impacts
    The EIA shall assess potential positive and negative impacts to social-economic-cultural resources
    including but not limited to the following:

    6.11  Socio-Economic Conditions
6.11.1   Increased  individual incomes
   6.11.1.1. Direct employment at the project
   6.11.1.2. Indirect employment generated by project activities
   6.11.1.3. Increased purchases from local businesses
   6.11.1.4. Other economic activities stimulated in the community as a result of the
            project
6.11.2   Employment opportunities for local residents
6.11.3   Increased  tax base
6.11.4   Displacement and relocation of current settlements, residents or community
        resources
6.11.5   Displacement or disruption of people's livelihoods (e.g., fishing, hunting,
        grazing, farming, forestry and tourism)
6.11.6   Public finance requirements-will more infrastructure need to be built and
        maintained to meet the demands of increased population in the areas of public
        education and public service (water, sanitation,  roads, emergency services,
        etc.)
6.11.7   Reduction in quality of life for residents from visual and noise impacts
6.11.8   Change  in  crime rate  (drugs, alcohol, prostitution, etc.)
6.11.9   Change  in  population (temporary or permanent)
6.11.10 Change  in  character of community
6.11.11 Change  in  religious, ethnic or cultural makeup of community
6.11.12 Impacts on public health
6.11.13 Impacts on worker health and safety
   6.11.13.1. Identification of hazardous jobs and number of workers exposed with
            duration of exposure
   6.11.13.2. Identification of physical risks and safety aspects
6.11.14 Potential for fires
6.11.15 Overall assessment of significance of direct, indirect and cumulative impacts
        for all phases of the proposed project based upon analysis of magnitude,
        frequency, scope and duration in context

    6.12  Infrastructure
               E.3.3 Endangered or
                 Threatened Species
                 and Habitats and
                 Protected Areas

               F.8 Flora, Fauna,
                 Ecosystems and
                 Protected Areas
                 Impact Assessment
                 Tools

               E. Social-Economic-
                 Cultural
                 Environment
               Table E-6

               F.9 Socio-Economic
                 Conditions,
                 Infrastructure and
                 Land Use
               F.12 Health and Safety
                  Impact Assessment
                  Tools
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                       45

-------
Volume I Part 2 - EIA Technical Review Guidelines:
             Tourism
2 EXAMPLE TERMS OF REFERENCE (TOR)
          CONCESSION PROJECTS
6.12.1  Transportation infrastructure
        This section of the EIA addresses impacts of transportation and traffic patterns
        on existing roads. The impacts of new and existing roads on water quality,
        biological resources and land use should be addressed in those respective
        sections. The EIA shall assess potential impacts to transportation systems
        including but not limited to the following:
   6.12.1.1. Potential changes to traffic patterns, densities, and traffic safety issues in
            area affected by project
            • A determination of vehicular traffic density in the project area (before,
              during, and after the proposed activities)
            • Potential for traffic accidents
            • Congestion
            • Noise
   6.12.1.2. Potential impacts to previously inaccessible areas from improvement of
            roads
6.12.2   Public health infrastructure
   6.12.2.1. Increased need for public health infrastructure
   6.12.2.2. Alterations to public health infrastructure
6.12.3   Communications infrastructure
   6.12.3.1. Increased need for communications infrastructure
   6.12.3.2. Alterations to communications infrastructure
6.12.4   Energy infrastructure
   6.12.4.1. Increased need for energy infrastructure
   6.12.4.2. Alterations to energy infrastructure
6.12.5   Overall assessment of significance of direct, indirect and cumulative impacts
        for all phases of the proposed project based upon analysis of magnitude,
        frequency, scope and duration in context

    6.13  Cultural, Archeological, Ceremonial and Historic and Resources
6.13.1   Destruction during construction
6.13.2   Damage and alteration
6.13.3   Removal from historic location
6.13.4   Introduction of visual or audible elements that diminish integrity
6.13.5   Neglect that causes deterioration
6.13.6   Loss of medicinal plants
6.13.7   Loss of access to traditional use areas
6.13.8   Damage to resources due to increased visitation promoted by the project
6.13.9   Impacts to previously inaccessible resources from development/improvement
        of roads
6.13.10 Overall assessment of significance of direct, indirect and cumulative impacts
        for all phases of the proposed project based upon analysis of magnitude,
        frequency, scope and duration in context

    6.14  Land Use
6.14.1   Temporary and permanent changes in land use by both area and location
   6.14.1.1. Immediate project area
   6.14.1.2. Surrounding areas (induced by economic development)
   6.14.1.3. In previously inaccessible areas now accessible due to improvement of
            roads
6.14.2   Overall assessment of significance of direct, indirect and cumulative impacts
        for all phases of the proposed project based upon analysis of magnitude,
        frequency, scope and duration in context
6.14.3   Social infrastructure (schools, cemetaries, churches, other public buildings,
        communication systems and housing)
   6.14.3.1. Increased need for additional infrastructure
   6.14.3.2. Alterations to social infrastructure
6.14.4   Existing tourism and recreation infrastructure
   6.14.4.1. Change in tourist activities
   6.14.4.2. Increased need for tourism and recreation infrastructure
   6.14.4.3. Alterations to tourism and recreation infrastructure
               E.4.2 Infrastructure:
                  Systems,
                  Equipment,
                  Capacity,
                  Performance
               Table E-7

               F.9 Socio-Economic
                  Conditions,
                  Infrastructure and
                  Land Use
               E.4.3 Cultural,
                  Archeological,
                  Ceremonial and
                  Historic Resources
               Table E-8


               F. 10 Cultural,
                  Archeological,
                  Ceremonial and
                  Historic Resources
               E.4.4 Land Use
               F.9 Socio-Economic
                 Conditions,
                 Infrastructure and
                 Land Use
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                        46

-------
Volume I Part 2 - EIA Technical Review Guidelines:
              Tourism
2 EXAMPLE TERMS OF REFERENCE (TOR)
          CONCESSION PROJECTS
6.14.5   Housing market (during construction and operation and after closure)
6.14.6   Identification of any components of the proposed project that would fall within
         25- or 100-year flood plains
6.14.7   Overall assessment of significance of direct, indirect and cumulative impacts
         for all phases of the proposed project based upon analysis of magnitude,
         frequency, scope and duration in context

7   Mitigation and Monitoring Measures
    This section of the EIA must include measures designed to mitigate potential adverse impacts to
    physical, biological and social-economic-cultural resources from construction, operation and closure of
    the proposed project and alternatives. These shall include measures to avoid and prevent, and if
    needed, to reduce or minimize adverse impacts. The project proponent must include measures
    considered to be "best practices" in the design of all alternatives.

    Here and/or in the Environmental Management Plan section, proposed mitigation shall be described in
    auditable terms and at a level of detail sufficient to demonstrate its effectiveness in addressing the
    concern or performance criterion, including its anticipated level of effectiveness and/or measurable
    performance, and design specifications.

    The monitoring plan must include monitoring throughout the life of the project for each potential
    mitigation to confirm the effectiveness of the measure and support contingency plans to provide
    assurance that the project, at the site preparation, construction, operation, expansion, and closure
    stages will meet applicable environmental requirements/standards by law, and fall within the limits of
    impacts deemed acceptable upon approval of the EIA. Some important items to address in the
    mitigation plan and associated monitoring plans include, but are not limited to the following:

Physical Impacts

    7.1 Geologic Resources and Hazards
7.1.1     Pre-excavation, onsite geological inspection and geotechnical study protocols
         to determine slope stability and landslide risks
7.1.2     Slopes built and maintained to avoid landslides and favor revegetation and
         soils formation
7.1.3     Slope stabilization by constructing retaining walls, using vegetation, geotextile
         membranes, or other mechanical methods
7.1.4     Use of signage to mark areas where slopes are not stable as a preventive
         measure in the event of a landslide
7.1.5     Mitigation measures unique to specific alternatives

    7.2 Soil Resources
7.2.1     Erosion and sedimentation control measures (temporary and permanent)
         including when each will be installed or implemented, how often it will be
         checked and the process for and timing of removal of temporary measures
7.2.2     Spoil  and debris disposal measures
7.2.3     Best management practices to minimize soil disturbance
7.2.4     Decommissioning/Rehabilitation Plan-if needed (summary of relevant
         measures with full document in Annex)
7.2.5     Restrictions on discharge of pollutants to soil
7.2.6     Mitigation measures unique to specific alternatives
7.2.7     Water Resources
7.2.8     Quality
   7.2.8.1.  Water Quality Management Plan (summary of relevant measures with full
            document in Annex)
            • Sewage and domestic wastewater
            • Nonpoint sources - runoff, erosion and sediment control prevention
               measures
   7.2.8.2.  Spill Prevention and Containment Plan (summary of relevant measures
            with full document in Annex)
   7.2.8.3.  Solid Waste Management Plan (summary of relevant measures with full
            document in Annex)
   7.2.8.4.  Hazardous Waste Management Plan (summary of relevant measures with
            full document in Annex)
                5. Mitigation and
                  Monitoring
                  Measures
               Tables G-l, G-2 & G-3
               Tables G-l, G-2 & G-3
               Appendix D
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                           47

-------
Volume I Part 2 - EIA Technical Review Guidelines:
             Tourism
2 EXAMPLE TERMS OF REFERENCE (TOR)
         CONCESSION PROJECTS
   7.2.8.5.   Transport system construction and maintenance to avoid erosion and
            sedimentation including:
            • Elevation or rerouting
            • Design for proper run-off control and catchment
            • Provision of culverts to allow flow that might otherwise be impeded by
              roadways or other rights of way
            • Appropriate traffic control
   7.2.8.6.   Off-road vehicle use restrictions
   7.2.8.7.   Waste minimization practices
7.2.9    Quantity
   7.2.9.1.   Water conservation practices
7.2.10   Mitigation measures unique to specific alternatives

    7.3 Air and Climate
7.3.1    Dust control measures
7.3.2    Energy conservation measures
7.3.3    Emissions control  measures
   7.3.3.1.   Emissions reduction equipment
   7.3.3.2.   Maintenance and inspection of equipment and vehicles using combustion
            engines to reduce emissions
7.3.4    Spill Prevention and Containment Plan (summary of relevant measures with full
        document in Annex)
7.3.5    Hazardous Materials Management Plan (summary of relevant measures with
        full document in Annex)
7.3.6    Mitigation measures unique to specific alternatives

    7.4 Noise and Vibration
7.4.1    Noise control measures
   7.4.1.1.   Noise reduction technologies (suppression equipment, sound-absorbing
            structures, vibration dampening devices, berms, noise barriers, etc.)
7.4.2    Mitigation measures unique to specific alternatives

    7.5 Aesthetic Resources
7.5.1    Relocation of project to another site
7.5.2    Redesign of placement of project structures on site
7.5.3    Redesign height and location of structures blocking view or producing light
        pollution
7.5.4    Lighting minimization
7.5.5    Visual/Landscape  Management Plan (summary of relevant measures with full
        document in Annex)
7.5.6    Mitigation measures unique to specific alternatives

Biological  Impacts

    7.6 Vegetation/Flora and Associated Ecosystems
7.6.1    Control of noxious and invasive weeds
7.6.2    Restoration/Rehabilitation Plan for disturbed areas (summary of relevant
        measures with full document in Annex)
7.6.3    Mitigation measures unique to specific alternatives

    7.7 Aquatic and Terrestrial Wildlife/Fauna and Associated Ecosystems
7.7.1    Fish and Aquatic Resources
   7.7.1.1.   Scheduling construction to avoid critical or important fish life history
            periods  (e.g.,  spawning)
   7.7.1.2.   Relocation of sensitive, threatened or endangered species
   7.7.1.3.   Mitigation measures unique to  specific alternatives
7.7.2    Wildlife Resources
   7.7.2.1.   Controls on hunting within the project area
   7.7.2.2.   Modify locations of structures and locations and timing of activities to
            avoid critical ecosystems, migratory routes and breeding areas
   7.7.2.3.   Scheduling construction to avoid critical or important wildlife history
               Table G-5
               Fables G-l, G-2 & G-3

               Appendix F
               Table G-4
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                       48

-------
 Volume I Part 2 - EIA Technical Review Guidelines:                                2 EXAMPLE TERMS OF REFERENCE (TOR)
	Tourism	CONCESSION PROJECTS

             periods (e.g., breeding, nesting)
    7.7.2.4.   Relocation of sensitive, threatened or endangered species
    7.7.2.5.   Mitigation measures unique to specific alternatives

 Social-Economic-Cultural Impacts

     7.8 Socio-Economic Conditions
 7.8.1    Selection of an alternate site for the project, and if not possible then adhering
         to requirements of an internationally recognized Resettlement Action Plan
         (RAP)
 7.8.2    Rehabilitation Program for people displaced by the project (summary of
         relevant measures with full document in Annex)
 7.8.3    Training local residents for employment in the project
 7.8.4    Development of a "Code of Conduct" (with associated training program) for
         workers to show respect to the local populations and their culture and social
         rules
 7.8.5    Public Health Program to protect  local population from potential health
         problems caused by the project operation (summary of relevant measures with
         full document in Annex)
 7.8.6    Development of an Occupational  Health,  Industrial Safety and Accidents
         Prevention Program with appropriate accident prevention program, reporting
         and periodic review (summary of relevant measures with full document in
         Annex) including provision of routine training and testing, and proper safety
         equipment such as  hearing protection, hardhats, steel-toed shoes, safety
         railings and fall arrestors
 7.8.7    Spill Prevention and Containment Plan (summary of  relevant measures with full
         document in Annex)
 7.8.8    Hazardous Materials Management Plan (summary of relevant measures with
         full document in Annex)
 7.8.9    Mitigation measures unique to specific alternatives

     7.9 Infrastructure
 7.9.1    Transportation infrastructure
         This section of the EIA addresses mitigation measures for transportation and
         traffic patterns on existing infrastructure  (roads, airports,  air strips, harbors,
         etc.).  Mitigation  of impacts of new and existing transportation infrastructure
         on water quality and biological resources and land use should be addressed in
         those respective sections.
    7.9.1.1.   Transportation Plan (summary of relevant measures with full document  in
             Annex)
             • Placement of traffic signals
             • Establishing, posting and enforcing speed limits for the vehicles that
               transport material
             • Training employees, contractors and subcontractors on measures to
               reduce or avoid potential accidents
             • Hiring and training security personnel devoted exclusively to preventing
               accidents in the access road and controlling the speed of the vehicles
               transporting project material
 7.9.2    Mitigation measures unique to specific alternatives

     7.10  Cultural, Archeological, Ceremonial and Historic and Resources
 7.10.1   Modify structure and activity locations to avoid significant archeological,
         cultural, ceremonial and historic sites
 7.10.2   If avoidance is not possible, conduct appropriate resource recovery operations
         before disturbing the sites
 7.10.3   Clearly delineate boundaries and  post signs identifying existing archeological,
         cultural and historic sites on roadsides and within the project area boundaries
         so that they are easily recognized by machinery operators, workers and
         tourists
 7.10.4   Development of a training program so that staff recognize and respect


 CAFTA-DR AND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENT AND LABOR ExcELLENCE-CCAD-USEPA PROGRAM                49

-------
Volume I Part 2 - EIA Technical Review Guidelines:
             Tourism
2 EXAMPLE TERMS OF REFERENCE (TOR)
         CONCESSION PROJECTS
        culturally and archeological sensitive areas
7.10.5   Development of a code of conduct for activities in indigenous and local
        communities with the consent of and in collaboration with the community
7.10.6   Provide guests with information about and interpretation of the local culture
        and cultural heritage, as well as explaining appropriate behavior while visiting
        living cultures and cultural  heritage sites
7.10.7   Development protocols for use during construction and operation stages for
        identifying and responding to archeological, cultural, ceremonial and historic
        sites not identified during the preliminary surveys
   7.10.7.1.  In the event such a site is found, they will stop activities at the site and
            report to the government relocation of cultural  or historical resources, for
            their physical protection.
7.10.8   Mitigation measures unique to specific alternatives

    7.11  Land Use
7.11.1   Criteria and method for calculating compensation for loss of land and crops
7.11.2   Compensation to farmers and ranchers for crop or forage losses and restore
        lost agricultural lands at the end of the project.
7.11.3   Compensation to property owners for relocation of their homes in the event
        the relocation is unavoidable
7.11.4   Mitigation measures unique to specific alternatives

8   Environmental Management Plan
    The EIA shall include an Environmental Management Plan to prevent, mitigate and monitor each
    impact identified in the EIA.  Plans will describe actions to be taken in sufficient detail to provide a
    basis for subsequent auditing of compliance with commitments made in the EIA process including who
    is responsible, how and when it will be implemented, what will be done and what results will be
    achieved, why it is being done, and how to know whether it is effective in addressing the underlying
    concerns.  The Environmental Management Plan shall have the following elements:

    8.1 Overview of Environmental Management Plan Organization  and Policy
8.1.1    Describe the project management and how environmental management and
        organization relates to overall project responsibility. Describe the personnel
        and performance accountability system for design, operation, maintenance
        and closure for implementation of mitigation and monitoring measures
8.1.2    Describe the environmental policy that will govern the Project throughout its
        implementation, including  at least the objectives, scope, commitment to
        continuous improvement, control and environmental monitoring and good
        relationship with neighboring populations and countries, as well as the
        commitment to internal controls such as compliance and environmental
        monitoring and routine audits
8.1.3    Identify the persons responsible for the implementation of mitigation
        measures, in each phase

    8.2 Project-wide Mitigation Plan including an implementation schedule. It
        has two elements:
8.2.1    Environmental resource mitigation (such as air, water)
8.2.2    Socio-economic-cultural mitigation (relocation, etc.)

    8.3 Project-Wide Monitoring Plan (usually specific to  monitoring of
        surface and ground water)
8.3.1    Short-term and long-term monitoring of resource condition, including but not
        limited to:
   8.3.1.1.   Slope stability
   8.3.1.2.   Water Quality Monitoring Program
            • Where, how and when monitoring shall be conducted
            • Parameters to be monitored
            • Monitoring frequencies
            • Sampling and analytical protocols to be used
   8.3.1.3.   Noise and Vibration
   8.3.1.4.   Cultural, ceremonial archeological and historic resources in the vicinity of
               H. Environmental
                 Management Plan
               Table H-l
               Appendix E
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                       50

-------
Volume I Part 2 - EIA Technical Review Guidelines:
              Tourism
2 EXAMPLE TERMS OF REFERENCE (TOR)
          CONCESSION PROJECTS
             the project
    8.4 Short-term and long-term monitoring to ensure that the mitigation
        measures are functioning as predicted and that rehabilitation is
        working

    8.5 Management of Other On- or Off-Site Environmental Pollution Control
        and Infrastructure
    This section should address management of critical elements of pollution control and infrastructure
    that are not otherwise included in the mitigation plan because they were considered an essential part
    of the proposed project.

    8.6 Contingency Plans
    Contingency plans shall be prepared and described to address a) failure to meet specific performance
    criteria established by law or necessary for the project to meet its commitments in the EIA and b)
    respond to natural and other risks previously identified and mitigated in the EIA in the event
    reasonable and feasible mitigation measures to address the risks are inadequate.
8.6.1    Performance-related Contingency Plans, indicating the steps that will be taken
        should monitoring indicate that:
   8.6.1.1.   Environmental standards are not being met
   8.6.1.2.   Impacts are greater than predicted
   8.6.1.3.  The mitigation measures and/or rehabilitation are not performing as
             predicted
8.6.2    Natural Disaster Risk Response Plan (assumes that risk identification and risk
        reduction have been addressed in other parts of the EIA)
8.6.3    Other Risks Response Plans (assumes that risk identification and risk reduction
        have been addressed in other parts of the EIA)
8.6.4    Contingency plans for maintaining  service or reducing downtime in the event
        of accidents or natural catastrophes that disrupt project operation

9   Signed Commitment Statement
    The EIA shall contain a legally binding signed letter of commitment to meeting the terms of the EIA.
    The statement must be signed by the authorized representative of the proponent company with
    assurance that all financial surety measures as required by the regulatory agency have been met.

10  Annexes
    These shall be numbered and duly referenced in the text

    10.1  Public Consultation
10.1.1  Public consultation plan
10.1.2  A summary of public outreach activities including: audience, number of
        persons, organizations involved, concerns raised, responses to comments
10.1.3  Summary of response to comments
10.1.4  Actual copies of written comments

    10.2  Technical Supporting Documents
10.2.1  Include maps, plans, charts and figures in the sequence mentioned in the EIA
        document
10.2.2  Zoning maps with resources  and results of impacts
10.2.3  Special Studies if relevant but not readily  accessible
10.2.4  Detailed materials on predictive tools/models and assumptions used for the
        assessment but too  detailed  for the body of the EIA

    10.3  References
    Submit a list of all references,  (books, articles, technical reports and other information sources) cited in
    the various chapters of the EIA study with full biographic references, and the following conventional
    procedures cited in the literature: author, year, title, source, number of pages, and city of publication
    or issuance.
               B.2 Public Participation
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                           51

-------
Volume I Part 2 - EIA Technical Review Guidelines:
             Tourism
2 EXAMPLE TERMS OF REFERENCE (TOR)
          CONCESSION PROJECTS
[This page is intentionally blank.]
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                        52

-------
 Volume I Part 2 - EIA Technical Review Guidelines:                            3 EXAMPLE TERMS OF REFERENCE (TOR)
	Tourism	COASTAL AND MARINE PROJECTS

 3  TERMS OF REFERENCE (TOR) FOR COASTAL AND MARINE
    DEVELOPMENT PROJECTS

 A. OVERVIEW
 These terms of reference  (TOR) describe  the  minimum requirements for the preparation  of the
 Environmental Impact Assessment (EIA) for proposed coastal and marine tourism.  Both the TOR and the
 cross referenced "EIA Technical Review Guidelines for Tourism Projects" should be used to establish
 minimally acceptable conditions for satisfying the  requirement to submit  an EIA.  There are three
 different TORs for tourism projects. Part A, Overview, is common to all three TORs but Part B is tailored
 respectively to: 1. Hotel and  Resort Developments, 2. Concessions, and 3. Marine and Coastal Tourism.
 The three TORs are structured to facilitate mixing and matching as appropriate to the purpose and need
 for a  proposed project and alternatives.

 These TORs are focused on specific types of coastal and marine tourism activities such as:
           •   Docks
           •   Marinas
           •   Developed beaches
           •   Marine recreational activities (boating, sailing, jet skiing, diving, snorkeling, etc.)
           •   Sport fishing

 Many marine and coastal tourism developments may also include hotels, restaurants, campgrounds and
 other such components.   These components  are covered  by the  TOR  for  Hotel  and  Resort
 Developments.

 The basic format for the EIA document that should be followed is:
           •   Table of Contents
           •   Acronyms and Abbreviations
           •   Executive Summary
           •   Project and Alternatives Description
           •   Environmental Setting
           •   Assessment of Impacts
           •   Mitigation and Monitoring Measures
           •   Environmental Management Plan
           •   Commitment Statement
           •   Annexes

 In general, the EIA must identify and address:

 •  Applicable  environmental  standards, norms, and  requirements  set forth  at  the  international,
    national, regional and/or local levels including those designed to  meet the objectives of resource
    management and/or land use  plans that may be in effect in and around the jurisdiction(s) in which
    the proposed project is located.  In the absence  of such standards, the EIA should establish a set of
    benchmarks that can be used in the analysis and selection of an alternative. The Guidelines identify
    standards in use by various countries and international organizations in Appendix C.

 •  Public/Stakeholder concerns related to impacts in and around the proposed project and alternatives
    at least for stakeholders within the geographic scope of potential impact. The project proponent
    should document specific steps taken to  engage the  public and  other  stakeholders, and engage
    these publics as early as possible before undertaking to prepare the EIA. Concerned publics include:
    local governments, persons living and working in the vicinity of the project, those with interests in
    resources that may be affected i.e., indigenous peoples, and those concerned about protected areas
    and prime agricultural lands. A summary of public outreach activities, audience, number of persons,
 CAFTA-DR AND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENT AND LABOR ExcELLENCE-CCAD-USEPA PROGRAM              S3

-------
 Volume I Part 2 - EIA Technical Review Guidelines:                            3 EXAMPLE TERMS OF REFERENCE (TOR)
	Tourism	COASTAL AND MARINE PROJECTS

     organizations  involved, concerns  raised,  responses to comments and actual copies of written
     comments received should be included in the Annex.

 •   All  relevant plans related to the proposed tourism project, for example, engineering and  site
     preparation plans,  operations and  decommissioning/closure,  environmental management,  and
     mitigation in whatever form these may take.

 •   All phases of the project from feasibility studies to site preparation to operations to closure and also
     plans to expand capacity at the current or adjacent sites.

 •   Alternative  approaches to meeting the  purpose and need for  the  proposed  tourism project,
     including siting, designing, constructing,  operating  and closing the project firstly to  avoid  and
     prevent,  or secondly  to  reduce  or  minimize adverse or  improve beneficial environmental or
     socioeconomic impacts. The  EIA should assess as appropriate the impacts of a range of reasonable
     and technically feasible alternatives as  well as the proposed project. The alternatives to the project
     must include  a "no action"  alternative, as well as consideration  of best practices that may  not
     otherwise have been incorporated in the proposed project.  Other alternatives should be developed
     as needed to avoid or minimize significant adverse impacts associated with the proposal.

 •   Direct, indirect and cumulative impacts and their significance level.

 •   Uncertainty and how that uncertainty will be addressed through monitoring and contingency plans
     as may be needed to reduce risk of adverse impacts in the future.

 •   Specific commitments, including who  is responsible, what  will  be done, when and how it will be
     monitored, reported and audited to confirm that commitments are met.

 Finally, a  key part  of the TOR is obtaining a legally binding commitment from the project proponent that
 the approved EIA will  be implemented as  presented.   Such a commitment adds  to the legal
 enforceability of the outcomes of the EIA process.
 CAFTA-DR AND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENT AND LABOR ExcELLENCE-CCAD-USEPA PROGRAM               54

-------
Volume I Part 2 - EIA Technical Review Guidelines:                               3 EXAMPLE TERMS OF REFERENCE (TOR)
             Tourism                                                     COASTAL AND MARINE PROJECTS
B.  DETAILS FOR COASTAL AND MARINE DEVELOPMENT PROJECTS

0   Table of Contents
    A general Table of Contents for the Environmental Impact Assessment (EIA) shall be provided. The
    Table of Contents shall be organized in such a manner as to facilitate the use of the EIA by reviewers
    and project implementers. ElAsfor larger projects should have a more detailed Table of Contents than
    those for smaller projects. At a minimum, the Table of Contents shall include the following:
    •   Acronyms and Abbreviations
    •   Executive Summary
    •   General Information
        o   Objectives and Justification
        o   Project Proponents
        o   Project Team
        o   Legal and Regulatory Framework
    •   Project and Alternatives Description
    •   Environmental Setting
        o   Physical Environment
            • Geologic Resources
            • Soil Resources
            • Water Resources
            • Air and Climate
            • Noise and Vibration
            • Aesthetic Resources
        o   Biological Environment
            • Vegetation/Flora
            • Aquatic and Terrestrial Wildlife/Fauna
            • Ecosystems: Terrestrial, Wetlands, Aquatic, Marine
            • Endangered or Threatened Species and Habitat
            • Protected Areas
        o   Social-Economic-Cultural Environment
            • Socio-Economic Conditions
            • Infrastructure
            • Cultural, Archeological, Ceremonial and Historic Resources
            • Land Use
    •   Assessment of Impacts to resources described in the Environmental Setting
    •   Mitigation and Monitoring  Measures
    •   Environmental Management Plan
        o   Overview of Environmental Management Plan Organization and Policy
        o   Project-wide Mitigation Plan
        o   Project- wide Monitoring Plan
        o   Management of Other On- or Off-Site Pollution Controls and Infrastructure
        o   Contingency Plans
            • Performance-related Contingency Plan
            • Natural Disaster Risk Response Plan
            • Other Risk Response Plans
    •   Signed Commitment Statement
    •   Annexes
        o   Public Consultation
            • Public Consultation Plan
            • Summary of Public Outreach Activities
            • Summary of Responses to Comments
            • Copies of Written Comments
        o   Technical Supporting Materials
            • Maps and Plans, in the sequence mentioned in the EIA document
            • Charts and Figures
            • Details about predictive modeling used, calculations and assumptions
            • Special Studies
        o   References
CAFTA-DR AND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENT AND LABOR ExcELLENCE-CCAD-USEPA PROGRAM                55

-------
Volume I Part 2 - EIA Technical Review Guidelines:
              Tourism
                                                                       3 EXAMPLE TERMS OF REFERENCE (TOR)
                                                                            COASTAL AND MARINE PROJECTS
1   Acronyms and Abbreviations
    All acronyms and abbreviations used in the EIA must be clearly and succinctly defined and described in
    this section.  This can relieve the reader of the need to search for the first occurrence of a word and the
    citing of the acronym or abbreviation in the text.

2   Executive Summary
    A general summary of the EIA shall be provided in this section. The summary shall be written using a
    vocabulary that can be easily understood by the public. It shall include at least the following
    information about the project from the EIA:
             Objectives and Justification
             Location
             Project Proponents
             Project Description
             Other Project Alternatives
             Environmental Setting
             Evaluation of Impacts
             Mitigation and Monitoring Measures
             Environmental Management Plan
             Issues raised by stakeholders and any  outstanding issues

3   General Information

    3.1 Objectives of and Justification for the  Proposed Project
3.1.1  Objectives: A statement of the general  and specific objectives (purpose) of the
      proposed project, including whether it is a new project, an expansion of an
      existing  project (e.g., increase in land area or increase in visitor capacity) or
      modernization of an existing operation.
3.1.2  Justification for the Project: Provide a justification for the proposed project
      (need) highlighting the benefits to surrounding communities and economic
      development of the region and country.
                                                                                      C.2 Documentation of
                                                                                         Purpose and Need
                                                                                      C.3.1 General
                                                                                         Information

    3.2 Project Proponents
3.2.1  Names, addresses, telephone numbers, and applicable legal documentation of
      proponents (including developers, major equipment  suppliers if part of project
      team, shareholders and providers of financing, and representatives).
3.2.2   Names and contact information for responsible parties within the organization.
3.2.3   Financial viability of the company (including a certified banking statement
       indicating that the company is financially stable and reputable).
3.2.4   Bonding requirements and proof of ability to meet bonding requirements
       sufficient to cover the anticipated costs of environmental management during all
       phases, as well as the costs,  by a third party, of decommissioning and long-term
       post-closure liabilities associated with the project.

    3.3 Project Team
    This section shall provide information on the multidisciplinary team that prepares the EIA. The types
    of professionals included in the team shall be appropriate to the type of project and the type of
    environment in which the project is located and may include (but not be limited to) engineers,
    architects, biologists, geologists, hydrologists, air quality experts, archeologists, anthropologists,
    sociologists and economists. The information provided for each member of the EIA project team
    includes the following:
3.3.1  Names, addresses and registry numbers of contractors.
3.3.2   Names, contact information, qualifications and registry  numbers of key
       personnel involved in the study;  as well asan affidavit indicating their area of
       participation.
3.3.3   List of professionals/experts participating in the EIA, their areas of expertise,
       degrees, experience, professional registrations and stamps, seals and signatures.

    3.4 Legal and Regulatory Framework
    This section of the EIA shall define the legal framework under which the EIA is being completed listing    C.3.1 General
    and summarizing requirements or alternatives used as benchmarks, and evidence of non-applicability       Information
    or compliance, including:
3.4.1  Information that demonstrates rights and access:
                                                                                      G.6 Financial
                                                                                         Assurance
                                                                                      C.3.1 General
                                                                                         Information
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                           56

-------
Volume I Part 2 - EIA Technical Review Guidelines:
              Tourism
3 EXAMPLE TERMS OF REFERENCE (TOR)
     COASTAL AND MARINE PROJECTS
   3.4.1.1   Ownership with written authorization
   3.4.1.2   Governmental authorization (if required)
   3.4.1.3   Period of lease/permit/concession agreement
   3.4.1.4   Maps showing the lease/permit/concession area
3.4.2  Applicable environmental  standards, norms and requirements set forth at the
       international, national, regional and/or local levels
   3.4.2.1   In the absence of such standards, identify a set of benchmarks used in the
             analysis
3.4.3  Required regulatory approvals and/or permits for all stages and their status
3.4.4  Applicable land use requirements (demonstrate conformity and compliance with
       applicable plans)
3.4.5  Applicable tourism strategies and plans - national, regional, and local
3.4.6  Applicable natural resource management or protected area management plans
       and responsible agency(ies) (demonstrate conformity and compliance with all
       applicable plans)

4    Project and Alternatives Description
     The project proponent shall submit a full description and location of the proposed project and
     reasonable alternatives including ancillary facilities and operations such as the camp/housing for
     construction and operation phases, borrow and disposal areas, sanitary services, waste disposal and
     transportation infrastructure, etc. as addressed through 4.1 to 4.3 below. It shall include at a
     minimum:

     4.1  Location
     The general location of the project and associated activities in terms of:
4.1.1  Political-administrative location (region, district, town  or other relevant political-
       administrative units) with accompanying location map
4.1.2  Means of site access - i.e., by air, river, road, train or vehicle
4.1.3  Latitude and longitude of project area
4.1.4  Maps of project area  at a scale of no less than 1:50,000 or as required by the
       regulatory agency
   4.1.4.1   Project plat plan and location on a fold-out 11" X 17" page.
   4.1.4.2   Indicate the project area and the direct and indirect areas of influence for
             the physical, biological  and social-economic-cultural impacts
   4.1.4.3   All drawings should  present scale and key coordinates or benchmarks as
             latitude/longitude, Universal Transverse Mercator (UTM) coordinates, or
             local survey plate that can be cross-referenced to  latitude/longitude or
             UTM coordinates
4.1.5  Has the area of the project ever been a tourist destination before?
   4.1.5.1   If so, show other tourist facilities in the area on  the maps, including those
             under construction and, if known, those in the design phase

     4.2  Summary of Proposed Project and Alternatives
     All project alternatives that are reasonable and feasible and meet the purpose and need for the
     proposed project shall be identified, summarized in this section, and evaluated in the EIA as
     appropriate. In addition to the proposed project, such alternatives include alternative locations,
     alternative site configuration of elements of the project, alternative size, and alternative plans for
     construction, operation and decommissioning of the project including best practices that may avoid
     and/or reduce the adverse impacts to the physical, biological or social-economic-cultural
     environments.

     If the project area or the buffer zone of the project area for an alternative is in an ecologically fragile
     are, the description of the alternative must include a clear justification for not opting for another site.
     Identify which alternatives will be carried through the analysis in the  EIA and the basis for that
     decision.

     4.3  Project and Alternatives Details
     The EIA shall provide specific project details for the proposed project and each alternative as identified
     in subsections 4.3.1 through 4.3.8.  The level of detail presented shall be the same for the proposed
     project and each alternative evaluated. The following project details shall be provided:
4.3.1  Type and nature of the project
   4.3.1.1   Type (dock, marina, developed beach, marine recreational activities, etc.)
                .
                C.3.2 Overall Project
                   Description
                   Information
                C.3.5 Maps, Diagrams,
                   Site Design and Plan
                C.3.2 Overall Project
                   Description
                   Information
                C.3.4 Project Details
                C.3.5 Project
                   Alternatives
                Table C-5

CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                               57

-------
 Volume I Part 2 - EIA Technical Review Guidelines:                                3 EXAMPLE TERMS OF REFERENCE (TOR)
	Tourism	COASTAL AND MARINE PROJECTS

    4.3.1.2   Overview of all proposed facilities and activities and their relationship
    4.3.1.3   A detailed drawing showing access points, layout of all project
             components including on-site roads, walkways and paths, existing
             structures, topography and natural features such as water bodies,
             wetlands and geologic structures
    4.3.1.4   A summary table showing the type, quantity and size of each component
    4.3.1.5   Expected life of operation
    4.3.1.6   Anticipated use: maximum, minimum and average by month and season
             for:
              •  Day use
              •  Overnight stays (if applicable)
    4.3.1.7   Recreational, leisure and adventure uses by visitors of surrounding natural
             and cultural resources
            • Type of use (type of activities, motorized or non-motorized, etc.)
            • Anticipated use (maximum, minimum and average by month and season)
 4.3.2  Principal  project facilities
        Location and design information - primary material of construction (wood, brick,
        stone, etc.), layout and dimensions.  Design drawings should be provided for
        each facility, including: Plan (overhead view), Elevations (front view), Profiles
        (side view) and Sections.
    4.3.2.1   Dock
             • Size
             • Uses
             • On-dock facilities (office/control point, toilets, fueling,
               bar/store/restaurant [refer to Resort TOR], storage, etc.)
             • On-shore facilities (office/control point, toilets, bar/store/restaurant
               [refer to  Resort TOR], storage, etc.)
    4.3.2.2   Marina
             • Size
             • Number of slots/moorings
             • Breakwaters
             • Dredging requirements (if applicable)
             • In-marina facilities (office/control point, toilets, fueling,
               bar/store/restaurant [refer to Resort TOR], storage, etc.)
             • On-shore facilities (office/control point, toilets, bar/store/restaurant
               [refer to  Resort TOR], storage, etc.)
    4.3.2.3   Dredging (if applicable)
             • Legal authorization for the dredging
             • Name of water body to be dredged
             • Dimensions of area to be dredged
                 o  Map showing extent of dredging operations
                 o  Longitudinal and transversal cross-sections of the area to be
                    dredged
             • Operation description
                 o  Frequency
                 o  Operational hours
                 o  Time table for dredging
             • Equipment Roster, specifying type and quantity by: size, motor size, and
               fuel requirements for each type of dredging equipment
             • Disposal  site to be used
                 o  Beneficial use of sediment or alternatives evaluation
                 o  Disposal site evaluation, if new site is proposed
    4.3.2.4   Developed beach
             • Beach uses
             • On-beach structures (recreational equipment rental/storage, bath/toilet
               facilities, bar, restaurant [refer to Resort TOR], lifeguard towers, sun
               shades, etc.)
             • Breakwaters and shoreline erosion protection
             • Type and source of beach material (if applicable)

 CAFTA-DR AND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENT AND LABOR ExcELLENCE-CCAD-USEPA PROGRAM                58

-------
Volume I Part 2 - EIA Technical Review Guidelines:
             Tourism
                                                                    3 EXAMPLE TERMS OF REFERENCE (TOR)
                                                                         COASTAL AND MARINE PROJECTS
   4.3.2.5   Marine recreational activities (boating, sailing, jet skiing, diving, snorkeling,
            etc.)
            • Types of uses
            • Dock
            • Equipment roster (types, numbers and sizes of equipment made
              available to clients)
            • On-site facilities (equipment storage, toilets, etc.)
   4.3.2.6   Sport fishing
            • Types of services and equipment provided
            • Facilities
4.3.3  Onsite support facilities
       Location and design information - primary material of construction (wood, brick,
       stone, etc.), layout  and dimensions.  Design drawings should be provided for
       each facility, including: Plan (overhead view), Elevations (front view), Profiles
       (side view) and Sections.
   4.3.3.1   On-site walkways
            • Widths and layout
            • Surface material
            • Lighting (if  applicable)
            • Erosion control
   4.3.3.2   Storage areas and warehouses
            • Locations
            • Sizes
            • Materials to be stored
   4.3.3.3   Parking lots
            • Locations
            • Sizes
            • Lighting
   4.3.3.4   Repair shops
            • Activities
            • Locations
            • Sizes
   4.3.3.5   Fuel stations
            • Commercial or for operator use only
            • Locations
            • Number, size and configuration of tanks (buried or above ground, leak
              protection, etc.)
   4.3.3.6   Electrical energy
            • Consumption, including energy conservation measures
            • Source-offsite
                o  Transmission lines (if necessary)
                o  Substation (if necessary)
            • On-site power generation  power
                o  Type
                o  Emissions and noise controls (if applicable)
            • On-site distribution (routes, overhead or buried)
   4.3.3.7   Water supply
            • Requirements (m3/day), including conservation measures
            • Rights
            • Sources
            • Treatment
            • Distribution
   4.3.3.8   Waste handling and disposal
            • Sewers
            • Wastewater treatment
                o  Quantity
                o  Type
                o  Discharge
            • Solid waste
                                                                                   Table C-ll
                                                                                   C.4.1 Water and
                                                                                      Sanitation Facilities
                                                                                   Table C-8
                                                                                   C.4.2 Solid and
                                                                                      Hazardous Waste
                                                                                   Fables C-9 & C-10
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                        59

-------
Volume I Part 2 - EIA Technical Review Guidelines:
             Tourism
3 EXAMPLE TERMS OF REFERENCE (TOR)
     COASTAL AND MARINE PROJECTS
                                                                                   1.3.7 Transportation:
                                                                                      Roads, Pathways,
                                                                                      Air Strips, and Boat
                                                                                      Facilities
                                                                                   Table C-2
                o  Quantity (kg/day and m3/day), including waste reduction
                   measures
                o  Collection
                o  Separation (if any)
                o  Disposal
4.3.4  Access and transportation
   4.3.4.1   Roads
            • Identify all new and existing roads to be used (including closed roads
              that will be reopened, if applicable)
                o  Traffic volume, operating speeds and trip times
                o  Closed roads that will be reopened
            • Detailed information on any access and  on-site roads to be constructed
              or upgraded
                o  Location
                o  Timing of construction
                o  Road surface and shoulder width and barriers
                o  Grade
                o  Construction methods including clearing and grubbing
                o  Construction materials
                o  Compaction
                o  Stream and wetland crossings and associated designs
                o  Animal crossings
                o  Sedimentation and erosion prevention and control structures and
                   practices
                o  Stabilization methods for cuts and fills
                o  Typical elevations for each type and situation of road displaying
                   construction materials, levels of compaction and erosion and
                   sedimentation features
                o  Location and size (area and volume of material) of borrow pits
                o  Lighting (where applicable)
                o  Operation
                o  Closure plan (if applicable)
                o  Traffic volume, operating speeds and trip times
            • Dust control for construction and operation
            • Maintenance
            • Roster for construction and maintenance equipment, specifying type
              and quantity by size, motor size, and fuel requirements
   4.3.4.2   Other transport systems (if applicable)
            • Airstrip
                o  Length and width
                o  Surface material
                o  On-site facilities
            • Rail transport - Same as for Roads with the addition of:
                o  Tightest curves
                o  Track construction materials
                o  Turnouts and sidings
                o  Railroad communications and signaling
4.3.5  Best Practices
        Description of standard best practices to be incorporated into the project.
4.3.6  Construction phase and timetable
   4.3.6.1   Schedule for each phase of construction for all project and ancillary
            facilities (including temporary structures) including, but not limited to:
               C.3.6 Details on
                  Construction
                  Procedures
               Table C-l
              Mobilization
              Road construction and improvements
              Land clearing
              Blasting
              Erosion and sediment control
              Dredging
              Breakwater construction
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                       60

-------
 Volume I Part 2 - EIA Technical Review Guidelines:                               3 EXAMPLE TERMS OF REFERENCE (TOR)
	Tourism	COASTAL AND MARINE PROJECTS

             • Excavation and subgrade preparation
             • Foundation and pilings preparation
             • Concrete work
             • Construction or installation of each project facility
             • Stabilization of disturbed areas
    4.3.6.2   A GANTT or critical path management chart for the entire project, from
             start to finish
    4.3.6.3   Borrow and fill material
             • Locations from which fill material will be sourced
             • Locations where fill material will be placed on-site
             • Locations where fill and other construction material will be temporarily
               stockpiled/stored
             • Borrow and spoil disposal
    4.3.6.4   Key areas (related to environmental sensitivity/importance) that will
             remain undisturbed during construction (waterways, wetlands, forested
             areas and other "green space," etc.)
    4.3.6.5   Erosion control structures such as:
             • Temporary diversions for waterways
             • Erosion control barriers
    4.3.6.6   Equipment
             • Equipment Roster, specifying type and quantity by size, weight,  motor
               size, and fuel requirements for each piece of equipment or machinery
               used in each activity
             • Transportation mobilization and mobilization frequency
             • Machinery and equipment mobilization routes to be used, as well as the
               features of the ways on which they will be transported, including a map
               of routes, as applicable, and mobilization.
    4.3.6.7   Labor during construction                                               C.6 Manpower and
             • Number and type of employees (by local hire and non-local hire) by field      Loca' Purchases
               of expertise
             • Days per week
             • Hours per day
             • Shifts per day
    4.3.6.8   Raw materials to be used for construction
             • Give a complete list of the raw materials and construction  materials to
               be used, indicating the amounts per day, month, and the storage means
             • Include an inventory of chemical, toxic or hazardous substances, active
               elements, sites and storage means, safety aspects regarding
               transportation and handling and any other relevant information
    4.3.6.9   Construction camp (if applicable)
               Description of the camp including but not limited to:
             • A map showing all facilities at a legible scale appropriate to the size of
               the project
                 o  Buildings by type (use) and size
                 o  Roads
                 o  Electrical transmission lines and/or substation
                 o  Drainage
             • Water supply and distribution
                 o  Distribution system
                 o  Use (m3/day)
                 o  Rights
                 o  Sources
             • Waste handling and disposal components
                 o  Sewers
                 o  Wastewater treatment
                 o  Solid waste facilities
             • Energy generation and use requirements (including fuelwood
               consumption and source)
             • Closure or transition from construction camp to  onsite employee

 CAFTA-DR AND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENT AND LABOR ExcELLENCE-CCAD-USEPA PROGRAM                61

-------
Volume I Part 2 - EIA Technical Review Guidelines:
             Tourism
3 EXAMPLE TERMS OF REFERENCE (TOR)
     COASTAL AND MARINE PROJECTS
              housing
   4.3.6.10  Decommissioning of temporary structures including measures for
            returning the area to pre-construction features
4.3.7  Operation phase
   4.3.7.1   Description of how the project would operate (seasonally, monthly, daily,
            hourly, as appropriate)
   4.3.7.2   Operation  information
            • Roster of equipment and machinery to be used during operation,
              specifying type and quantity by size, weight, motor size, and fuel
              requirements for each activity
            • Labor during operation
                o  Number and type of employees (by local hire and non-local hire)
                   by  field of expertise
                o  Days per week
                o  Hours per day
                o  Shifts per day
            • Raw materials to be used for operation
                o  List of the raw materials to be used, indicating the amounts per
                   day, month, and the storage means
                o  Inventory of chemical, toxic or hazardous substances, active
                   elements, sites and storage means, safety aspects regarding
                   transportation and handling and any other relevant information
4.3.8  Closure and decomissioning plan
      If it becomes clear that closure will be required, or when the project nears the
      the end of its service life, the project operator shall contact the proper regulatory
      agency(ies) to obtain the environmental guidelines to carry out the closure or
      decommissioning.
   4.3.8.1   The project description shall include at least a general Restoration and
            Closure Plan, recognizing that terms of closure may be very different when
            this phase  approaches
   4.3.8.2   The description of restoration measures should include the size of the area
            to be restored as well as concurrent, temporary and final restoration
            measures to be used and their schedules.  For each measure include:
            • Area to be addressed
            • Timing and schedule for executing measures
            • Equipment and structure removal or conversion
            • Remedial measures, including success indicators and contingency
              measures if initial efforts are unsuccessful

5   Environmental Setting
    Based on information available from the literature, government and special studies or other sources,
    the EIA shall provide information on environmental setting for the different types of physical,
    biological and social-economic-cultural environments for the current situation, important trends and
    predicted situation in the absence of the proposed project. All sources of data must be cited in the EIA
    when and where they are used.  Indicate the direct and indirect and cumulative impact areas of
    influence for physical, biological, and social-economic-cultural impacts and basis for defining area.
    This section shall include at a minimum, the following information:

Physical Environment

    5.1 Geologic Resources and Hazards
5.1.1  Cross sections of  the geology including soil horizons
   5.1.1.1   Geologic characteristics at all project structure locations and in the area of
            influence.
   5.1.1.2   Geological map of the project area and area of influence at a scale of
            1:10,000.
              Submit a map of the area displaying all characteristics described.
              Include geological profiles and cuts, as well as stratigraphic columns.
5.1.2  Topography and slope conditions and geomorphology
5.1.3  Seismicity and stability characteristics
               1.6 Manpower and
                  Local Purchases
               C.7 Closure
                ). Environmental
                  Setting
               Table D-l
               D.2 Physical
                  Environment

               D.2.1 Geology and
                  Soils
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                         62

-------
Volume I Part 2 - EIA Technical Review Guidelines:
             Tourism
3 EXAMPLE TERMS OF REFERENCE (TOR)
     COASTAL AND MARINE PROJECTS
   5.1.1.3   Indicate the general seismic and tectonic features of the surrounding
            areas:
            • Seismic sources close to the project area
            • Seismic history
   5.1.1.4   Volcanic activity (must be provided by all the projects that are located
            within a radius of 30 km from an active volcanic emission center)
            • Indicate the general volcanic features of the area near the site
            • Historical eruptions
            • Period of recurrence
            • Type of eruptions
            • Affected areas and high risk areas
   5.1.1.5   Describe project areas susceptible to soil liquefaction; planned, active, and
            abandoned mines; karst terrain; and areas of potential ground failure,
            such as subsidence, slumping, and land sliding

    5.2 Soil Resources
    The EIA shall describe baseline soil resources, and make use of maps, tables and accompanying
    narrative text to describe the soils at the project site and along new or reconditioned access routes
    associated with the project and included in the EIA.
5.2.1  Types, capacity and uses
5.2.2  Fertility and potential uses of the land for agriculture
5.2.3  Stability and permeability
5.2.4  Erosion and sedimentation potential
5.2.5  Quantity and quality available for revegetating  and restoring the disturbed area
      at time of closure
               D.2.1 Geology and
                  Soils
    5.3 Water Resources
5.3.1  Marine water
   5.3.1.1   Currents
   5.3.1.2   Wave patterns
   5.3.1.3   Bathymetry
   5.3.1.4   Substrate
            • Composition
            • Structure
5.3.2  Fresh water
   5.3.2.1   Names and locations on maps of all permanent and intermittent streams,
            rivers, wetlands, lakes and reservoirs within the area of influence
   5.3.2.2   Flow (only necessary if water source will be surface water or if wastewater
            will be discharged to surface water)
            • The monthly minimum, mean and maximum recorded flows in m3/s of
              the river at the diversion point
            • Location of gauging stations where data were gathered to derive the
              curves
            • 2-, 10-, 25-,  50- and 100-year runoff events and 100-year floodplain for
              streams and rivers
   5.3.2.3   Seasonal fluctuations in  area and volume of wetlands, lakes and reservoirs
   5.3.2.4   Delineation of watersheds and water drainage pattern in the area of
            influence using cadastral/aerial/remote sensing satellite imageries (map)
            • Runoff characteristics of watersheds
   5.3.2.5   Inventories of consumptive and non-consumptive use
   5.3.2.6   Surface water balance (only necessary if water source will be surface
            water)
            • Existing uses by type and volume
            • Capacity
5.3.3  Groundwater
      Provide a map and identify and describe aquifiers and underground waters
      adjacent to the project, indicating the depth of the water table along with trend
      data:
   5.3.3.1   Hydrogeologic characteristics of the project site including fuel storage
            areas, wastewater discharge areas, and golf courses (vadose zone and
                ).2.2 Water Resources
               D.2.2.2 Marine Waters
               D.2.2.1 Surface Water
               D.2.2.3 Groundwater
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                        63

-------
 Volume I Part 2 - EIA Technical Review Guidelines:                                3 EXAMPLE TERMS OF REFERENCE (TOR)
	Tourism	COASTAL AND MARINE PROJECTS

             aquifers)
             • Water table levels (dry and rainy season)
             • Flow regime
             • Flow direction
             • Influences of geologic structures (faults, contacts, bedrock fracturing,
               etc) and surface water bodies
    5.3.3.2   Location and characteristics of all existing springs and wells in the area of
             influence  (on topographic map)
             • Flow/yield data for each spring and well (including water levels in wells)
             • Depth and construction information for each well
             • Existing uses by type and volume
             • Capacity available
    5.3.3.3   Groundwater recharge data
    5.3.3.4   Groundwater potential yield (only necessary if water source will be
             groundwater)
 5.3.4  Water quality
    5.3.4.1   Existing water quality data
             • Locations of all water quality monitoring stations in and around the
               project  area (with direction  and distance from the site)
             • Water quality data for each  station for those parameters likely to be
               affected by project construction, operation or maintenance
             • Physical, chemical and biological water quality characteristics, including
               water temperature and dissolved oxygen concentrations
    5.3.4.2   Supplemental sampling and analysis (if existing data is not adequate to
             characterize water quality)
              Sampling and Analysis Program in annex
             • Proposed locations of representative monitoring stations upstream and
               downstream of proposed project activities
             • Monitoring program design  with at least a year of baseline data being
               collected
                 o  Parameters (including  as appropriate, physical, chemical and
                     biological)
                 o  Frequency of collection
                 o Analytic methods
    5.3.4.3   Water quality standards that apply to the project (marine and fresh water)
             • Current uses
             • Standards for current uses (in the absence of such standards, identify a
               set of benchmarks used in the analysis)

     5.4 Air and Climate
     Baseline information for air resources shall be collected for at least one year or as required by the
     regulatory agency and shall include at a minimum the following:                                D.2.3 Air and Climate
 5.4.1  Climate and meteorology
    5.4.1.1   Source of data (meteorological station(s) from which climatological data
             have  been obtained)
    5.4.1.2   Temperature variations
    5.4.1.3   Relative humidity
    5.4.1.4   Solar radiation and evaporation rates
    5.4.1.5   Rainfall (total precipitation,  rainfall intensity,  and duration by month)
    5.4.1.6   Wind Rose (Wind direction and speed, 24 hourly data)
    5.4.1.7   Statistical analysis of the data
    5.4.1.8   Risk of high  impact storms, storm surges, hurricane levels, tropical storms
             frequency and seasonality

     5.5 Noise and Vibration
     Present a description of the noise and vibration  levels for receptors near where noise generating
     activities of the project may occur. The EIA shall include:                                      D.2.4 Noise and
 5.5.1  Location of monitoring stations                                                    Vibration
 5.5.2  Daytime and night time noise levels (measured  in decibels)
 5.5.3  Inventory of existing noise sources


 CAFTA-DR AND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENT AND LABOR ExcELLENCE-CCAD-USEPA PROGRAM                64

-------
Volume I Part 2 - EIA Technical Review Guidelines:
             Tourism
3 EXAMPLE TERMS OF REFERENCE (TOR)
     COASTAL AND MARINE PROJECTS
    5.6 Aesthetic and Visual Resources
5.6.1  Photos presenting baseline panoramic views of the project site from potential
      viewpoints
5.6.2  Viewsheds or other aesthetic or landscape resources
5.6.3  Existing sources of light contamination

Biological Environment
    The EIA shall provide detailed information on the location and condition of ecosystems in and around
    the project area in the form of narrative, maps and tables, including the following:

    5.7 Vegetation/Flora
5.7.1  Vegetative mapping of  terrestrial and wetland habitats (aquatic and marine if
      appropriate) for project area and areas affected by the project (e.g., project site
      and areas around new roads)
5.7.2  Species and structure (abundance, density, status, plant communities, presence
      of invasive species, etc.)

    5.8 Aquatic and Terrestrial Wildlife/Fauna
5.8.1  Fish and Aquatic  Resources
   5.8.1.1   Identification offish, mussel, macroinvertebrate and other aquatic species
             • Spatial and temporal distribution
             • Species life stage composition
             • Standing crop
             • Age and growth data
             • Spawning run timing
             • Extent and location  of spawning, rearing, feeding and wintering habitat
5.8.2  Wildlife Resources
   5.8.2.1   Species (including status, i.e., endemic, migratory, exotic, endangered,
             threatened, keystone, etc.), life history, and seasonal use
   5.8.2.2   Breeding areas
   5.8.2.3   Mating and brooding areas
   5.8.2.4   Migratory corridors (if applicable)
   5.8.2.5   Important wildlife use areas (roosts, clay licks, etc.)

    5.9 Ecosystems: Terrestrial, Wetlands, Aquatic, Marine
    Much if not all that may be needed to address the environmental setting for terrestrial, wetlands,
    aquatic and/or marine ecosystems may have been covered in Sections 5.7 and 5.8. This section is not
    intended to duplicate that information; rather, it should integrate the information to ensure that the
    structure and function of each ecosystem is adequately presented.

    5.10  Endangered or Threatened Species and Habitats
    Sections 5.7 and 5.8 should identify all species in the project area. This section should highlight all
    endangered and threatened species and critical habitat that potentially occur in the vicinity of the
    project.

    5.11  Protected Areas
    Identify on maps the specific locations and boundaries  of relevant national parks, sanctuaries,
    reserves, etc., as well as any areas proposed for protection. Provide a brief narrative description of
    each area.

Social-Economic-Cultural Environment

    5.12  Socio-Economic Conditions
    Identify nearby human settlements including the following information for each settlement:
5.12.1  Population (size, gender and age distribution)
5.12.2  Cultural characteristics (religion, ethnic composition, languages spoken, etc.)
5.12.3  Economic activities (employers, employment and incomes)
5.12.4  Tax  base
5.12.5  Crime rates
5.12.6  Literacy rates
5.12.7  Community organizations
5.12.8  Public Health and Safety
   5.12.8.1   Diseases in the project area (including the sources of data and the
               C.2.5 Aesthetic
                  Resources
               D.3 Biological
                  Environment
               D.3.1 Flora
               D.3.2 Fauna
               D.3.3 Ecosystems
               D.3.4 Endangered or
                  Threatened Species
                  and Habitats

               D.3.5 Protected Areas
                  and Sensitive
                  Ecosystems
               D.4 Social-Economic-
                  Cultural
                  Environment

               D.4.1 Socio-Economic
                  Conditions and
                  Resources
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                           65

-------
Volume I Part 2 - EIA Technical Review Guidelines:
             Tourism
                                                                      3 EXAMPLE TERMS OF REFERENCE (TOR)
                                                                           COASTAL AND MARINE PROJECTS
                                                                                     D.4.2 Infrastructure
                                                                                        Systems and
                                                                                        Equipment
                                                                                      .4.2.1 Transportation
                                                                                        Infrastructure
            methodology used to collect and analyze the data)
   5.12.8.2  Level of emergency services and access to clinics, doctors and hospitals
   5.12.8.3  Existing practice for assessment of occupational health
5.12.9  Skills, services and goods availability in the communities

    5.13  Infrastructure
    For each human settlement identified in subsection 5.12, describe the infrastructure in or serving the
    settlement, including the following information:
5.13.1  Transportation infrastructure
   5.13.1.1  Roads- Location and condition of all existing roads in the project area that
            may be used by the project or tourists coming to the project
            • Surface materials
            • Erosion and sediment control
            • Maintenance programs (what, when and whom)
            • Description of anticipated third-party improvements (government or
              entity other than the proponent)
            • Traffic capacity, patterns and densities
            • Safety levels and current circulation issues
            • Surface materials
            • Erosion and sediment control
            • Maintenance programs (what, when and whom)
   5.13.1.2  Airports and air strips - Locations, conditions,  capacities, current uses and
            trends
   5.13.1.3  Other transportation  infrastructure as applicable such as rail, bus,
            pipelines for fueling, harbors for cruise ships, and marinas for boats -
            Locations, conditions, capacities, current uses and trends
5.13.2  Public health infrastructure
   5.13.2.1  Drinking water supplies and treatment
   5.13.2.2  Wastewater treatment and management
   5.13.2.3  Solid and  hazardous waste management and treatment
5.13.3  Communications infrastructure
   5.13.3.1  Types of communications systems
   5.13.3.2  Types of transmission (wired or wireless)
   5.13.3.3  Locations of transmission lines  (if applicable)
   5.13.3.4  Locations of microwave towers and/or antennae (if applicable)
5.13.4  Energy infrastructure
   5.13.4.1  Types of energy
   5.13.4.2  Sources including location and description of generating facilities in the
            area of influence
   5.13.4.3  Transmission lines and/or pipelines
   5.13.4.4  Fuel storage facilities

    5.14  Cultural, Archeological, Ceremonial and Historic and Resources
    Identify all cultural, archaeological, ceremonial and historic resources within the area of influence,
    including the following information:
5.14.1  Data and maps relating to archeological, cultural, ceremonial, and historic sites
        in the direct vicinity of the project
5.14.2  Information on indigenous people or other traditional cultures, if any

    5.15  Land Use
    Describe actual and potential land use showing location, size and proximity within and surrounding
    the project area, including land use maps, and to extent possible, integrated into one map.
5.15.1  Population centers, including information and locations of
   5.15.1.1  Schools
   5.15.1.2  Cemeteries
   5.15.1.3  Churches
   5.15.1.4  Other public buildings
   5.15.1.5  Housing (including housing density)
   5.15.1.6  Commercial areas
5.15.2  Agricultural lands
5.15.3  Forested lands
                                                                                     ).4.2.2 Public Health
                                                                                        Infrastructure
                                                                                     ).4.2.3 Communica-
                                                                                        tions Infrastructure
                                                                                     D.4.2.4 Energy
                                                                                        Infrastructure

                                                                                     0.4.3 Cultural,
                                                                                        Archeological,
                                                                                        Ceremonial and
                                                                                        Historic Resources
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                          66

-------
Volume I Part 2 - EIA Technical Review Guidelines:
              Tourism
3 EXAMPLE TERMS OF REFERENCE (TOR)
     COASTAL AND MARINE PROJECTS
5.15.4   Protected areas (including but not limited to)
   5.15.4.1  National parks
   5.15.4.2  Wildlife refuges
5.15.5   Wetlands and mangroves
5.15.6   Other environmentally sensitive areas
5.15.7   Tourism and recreation areas
   5.15.7.1  Recreation facilities
   5.15.7.2  Eco-cultural-tourist locations
5.15.8   Culturally sensitive areas
5.15.9   Flood plains and water bodies
5.15.10  Coastal zones
5.15.11  Other land uses as appropriate

6   Assessment of Impacts
    The EIA shall provide information on potential impacts (direct, indirect and cumulative) and the
    magnitude and frequency of potential impacts on physical, biological, social-economic-cultural
    resources resulting from construction, operation and closure of the proposed project and alternatives.
    The assessment shall use standardized predictive methods, such as models, to determine the specific
    range of impacts on environmental and socio-economic resources. The EIA shall identify which
    impacts are significant and the criteria used to make this judgment.  Critical data input from project
    description and environmental setting analysis projecting the conditions in the environmental setting
    in the absence of the proposed project shall be used as the baseline upon which potential impacts are
    forecast. The EIA shall also identify sources of data used in the analysis and the uncertainties
    associated with the outputs of each method used.

Physical Impacts

    6.1  Geologic Resources and Hazards
    Potential impacts to geologic resources and potential effects on project structures shall be described
    including but not limited to the following:
6.1.1     Geologic hazards and potential effects on project structures
6.1.2     Changes  in topography and drainage patterns
6.1.3     Overall assessment  of significance of direct, indirect and cumulative impacts
         for all phases of the proposed project based upon analysis of magnitude,
         frequency, scope and duration in context

    6.2  Soil Resources
    Potential impacts to soil resources shall be described. The analysis shall include, but not be limited to
    the following:
6.2.1  Soil quality
   6.2.1.1    Contamination  (accidental spills of fuel, oil or other hazardous substances)
   6.2.1.2    Impacts on use
6.2.2  Erosion, slope alteration, vegetation removal and drainage patterns
   6.2.2.1    Models for soil  erosion should be included using methods like USLE,
             defining the areas with high erosion potential
   6.2.2.2    Sediment accumulation and transport
6.2.3  Overall assessment of significance  of direct, indirect and cumulative impacts for
      all phases of the proposed project  based upon analysis of magnitude, frequency,
      scope and duration in context

    6.3  Water Resources
    Potential impacts to surface water and groundwater shall be described.  The analysis shall include but
    not be limited to the following:
6.3.1  Geomorphology
   6.3.1.1    Location of all stream or wetland crossings by access roads
   6.3.1.2    Modification/diversion in the existing drainage pattern
   6.3.1.3    Bank and shore erosion (stream crossings,  shoreline developments and
             dredging)
   6.3.1.4    Potential for increased flash flooding
6.3.2  Quantity
   6.3.2.1    Impact of water use on surface water and groundwater, including specific
             uses
             • Model results
                F. Assessing Impacts
                F.I Overview of Using
                  Predictive Tools for
                  an EIA

                F.2 General
                  Approaches for
                  Prediction of
                  Impacts

                Appendix C

                E.2 Physical
                  Environment

                E.2.1 Geology, Soils
                  and Ocean
                  Topography
                Table E-l

                F.3 Soils and Geology
                  Impact Assessment
                  Tools
                E.2.2 Water Resources
                Table E-2

                F.4 Water Resources
                  Impact Assessment
                  Tools
                Table F-l
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                             67

-------
Volume I Part 2 - EIA Technical Review Guidelines:
             Tourism
3 EXAMPLE TERMS OF REFERENCE (TOR)
     COASTAL AND MARINE PROJECTS
            • Water table levels
            • Well production
            • Spring and stream flows
6.3.3  Quality
   6.3.3.1   Salt water intrusion from well withdrawals
   6.3.3.2   Runoff, erosion and sedimentation from roads, disturbed areas and stream
            crossings
            • Sources
            • Receiving waters
            • Concentrations
                o   Physical parameters
                o   Chemical parameters
                o   Biological parameters
   6.3.3.3   Description of impact from wastewater discharges
   6.3.3.4   Spills and accidents (chemicals, hazardous wastes and fuel spills)
6.3.4  Overall assessment of significance of direct, indirect and cumulative impacts for
      all phases of the proposed project based upon analysis of magnitude, frequency,
      scope and duration in context

    6.4 Air and Climate
    Potential impacts to air resources shall be described including but not limited to the following:
6.4.1  Impacts on ambient air quality
   6.4.1.1   Sources (e.g., windblown dust, fixed and mobile equipment)
   6.4.1.2   Concentrations
   6.4.1.3   Receptors (e.g., communities, schools, soils, water bodies, ecosystems)
6.4.2  Greenhouse gas generation
6.4.3  Overall assessment of significance of direct, indirect and cumulative impacts for
      all phases of the proposed project based upon analysis of magnitude, frequency,
      scope and duration in context

    6.5 Noise and Vibration
    Potential impacts from noise shall be described including but not limited to the following:
6.5.1  Potential noise levels at different representative sites in the project area and in
      communities  near the project area
6.5.2  Potential vibration due to blasting and movement of heavy equipment, and
      related damage to materials and structures
6.5.3  Overall assessment of significance of direct, indirect and cumulative impacts for
      all phases of the proposed project based upon analysis of magnitude, frequency,
      scope and duration in context

    6.6 Aesthetic and Visual Resources
    Potential impacts to Aesthetic Resources, including light pollution, shall be described including but not
    limited to the following:
6.6.1  Impacts on visual  resources and landscapes
6.6.2  Increases in light contamination
6.6.3  Overall assessment of significance of direct, indirect and cumulative impacts for
      all phases of the proposed project based upon analysis of magnitude, frequency,
      scope and duration in context

Biologic Impacts
    Potential impacts to biological resources shall be described and quantified including but not limited to
    the following:

    6.7 Vegetation/Flora and Associated Ecosystems
    Describe and quantify alterations in vegetative cover due to:
6.7.1  Deforestation or wetlands and mangrove destruction
6.7.2  Other vegetative type conversions
   6.7.2.1   Direct vegetative removal
   6.7.2.2   Indirect (e.g., poisoning by dust and pesticides)
6.7.3  Wildfires
6.7.4  Increased access to remote areas leading to destruction of existing vegetative
               Table F-2
               Table F-3
               F.5 Air Resources
                  Impact Assessment
                  Tools
               Table F-5
               E.2.4 Noise and
                  Vibration
               Table E-4

               F.6 Noise Impact
                  Assessment Tools
               E.2.5 Aesthetic
                  Resources

               F.7 Aesthetic/Visual
                  Resource Impact
                  Assessment Tools
               Table F-6
               E.3 Biological
                  Environment
               Table E-5

               E.3.1 Terrestrial
                  Species and
                  Associated
                  Ecosystems
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                        68

-------
Volume I Part 2 - EIA Technical Review Guidelines:
             Tourism
3 EXAMPLE TERMS OF REFERENCE (TOR)
     COASTAL AND MARINE PROJECTS
      cover (land use changes)
6.7.5  Spread of noxious or invasive species
6.7.6  Overall assessment of significance of direct, indirect and cumulative impacts for
      all phases of the proposed project based upon analysis of magnitude, frequency,
      scope and duration in context
    6.8 Aquatic and Terrestrial Wildlife/Fauna and Associated Ecosystems
    Describe and quantify alterations in aquatic and terrestrial wildlife populations due to:
6.8.1  Fish and Aquatic Resources
   6.8.1.1   Loss in habitat (e.g., spawning, rearing, juvenile, or adult habitats) from
            changes in water quality, sea floor and destruction of coral
   6.8.1.2   Disturbance of aquatic resources during construction, operations, or
            maintenance activities, including equipment noise, erosion and
            sedimentation, pile driving and vehicular movements
   6.8.1.3   Increased fishing
6.8.2  Wildlife Resources
   6.8.2.1   Loss of habitat, migratory routes/corridors, and breeding areas due to
            changes in vegetative cover/wetlands loss
   6.8.2.2   Disturbance of habitat, migratory routes/corridors and breeding areas due
            to project construction, operation, and maintenance, recreational use, and
            human settlement associated with the project  (e.g., noise, vibration,
            illumination, vehicular movement)
   6.8.2.3   Loss or contamination of drinking water for wildlife species
   6.8.2.4   Poisoning (e.g., direct contact with toxic wastes/substances)
   6.8.2.5   Animals attracted to garbage and food waste generated at construction
            camps, restaurants and on-site employee housing
   6.8.2.6   Increased hunting
6.8.3  Overall assessment of significance of direct, indirect and cumulative impacts for
      all phases of the proposed project based upon analysis of magnitude, frequency,
      scope and duration in context

    6.9 Endangered or Threatened Species or Habitats
    Describe and quantify impacts to endangered or threatened species  or habitats
6.9.1  Biodiversity
6.9.2  Individual species (with special emphasis on endemic, rare, threatened and
      endangered species)
6.9.3  Overall assessment of significance of direct, indirect and cumulative impacts for
      all phases of the proposed project based upon analysis of magnitude, frequency,
      scope and duration in context

    6.10  Protected Areas

Social-Economic-Cultural Impacts
    The EIA shall assess potential positive and negative impacts to social-economic-cultural resources
    including but not limited to the following:

    6.11  Socio-Economic Conditions
6.11.1  Increased individual incomes
   6.11.1.1  Direct employment at the project
   6.11.1.2  Indirect employment generated  by project activities
   6.11.1.3  Increased purchases from local businesses
   6.11.1.4  Other economic activities stimulated in the community as a result of the
            project
6.11.2  Employment opportunities for local residents
6.11.3  Increased tax base
6.11.4  Displacement and relocation of current settlements, residents or community
        resources
6.11.5  Displacement or disruption of people's livelihoods (e.g., fishing, hunting,
        grazing, farming, forestry and tourism)
6.11.6  Public finance requirements-will more infrastructure need to be built and
        maintained to meet the demands of  increased population in the areas of public
               E.3.2 Aquatic
                  Ecosystems

               F.8 Flora, Fauna,
                  Ecosystems and
                  Protected Areas
                  Impact Assessment
                  Tools
               Table F-2
               E.3.3 Endangered or
                  Threatened Species
                  and Habitats and
                  Protected Areas

               F.8 Flora, Fauna,
                  Ecosystems and
                  Protected Areas
                  Impact Assessment
                  Tools

               E. Social-Economic-
                  Cultural
                  Environment
               Table E-6

               F.9 Socio-Economic
                  Conditions,
                  Infrastructure and
                  Land Use
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                       69

-------
Volume I Part 2 - EIA Technical Review Guidelines:
             Tourism
                                                                    3 EXAMPLE TERMS OF REFERENCE (TOR)
                                                                         COASTAL AND MARINE PROJECTS
                                                                                   F.12 Health and Safety
                                                                                      Impact Assessment
                                                                                      Tools
        education and public service (water, sanitation, roads, emergency services,
        etc.)
6.11.7   Reduction in quality of life for residents from visual and noise impacts
6.11.8   Change in crime rate (drugs, alcohol, prostitution, etc.)
6.11.9   Change in population (temporary or permanent)
6.11.10 Change in character of community
6.11.11 Change in religious, ethnic or cultural makeup of community
6.11.12 Impacts on public health
6.11.13 Impacts on worker health and safety
   6.11.13.1 Identification of hazardous jobs and number of workers exposed with
            duration of exposure
   6.11.13.2 Identification of physical risks and safety aspects
6.11.14 Potential for fires
6.11.15 Overall assessment of significance of direct, indirect and cumulative impacts
        for all phases of the proposed project based upon analysis of magnitude,
        frequency, scope and duration in context

    6.12  Infrastructure
6.12.1   Transportation infrastructure
        This section of the EIA addresses impacts of transportation and traffic patterns
        on existing roads. The impacts of new and existing roads on water quality,
        biological resources and land use should be addressed in those respective
        sections. The EIA shall assess potential impacts to transportation systems
        including but not limited to  the following:
   6.12.1.1  Potential changes to traffic patterns, densities, and traffic safety issues in
            area affected by project
            • A determination of vehicular traffic density in the project area (before,
              during, and after the  proposed activities)
            • Potential for traffic accidents
            • Congestion
            • Noise
6.12.2   Public health infrastructure
   6.12.2.1  Increased  need for public health infrastructure
   6.12.2.2  Alterations to public health  infrastructure
6.12.3   Communications infrastructure
   6.12.3.1  Increased  need for communications infrastructure
   6.12.3.2  Alterations to communications infrastructure
6.12.4   Energy infrastructure
   6.12.4.1  Increased  need for energy infrastructure
   6.12.4.2  Alterations to energy infrastructure
6.12.5   Overall assessment of significance of direct, indirect and cumulative impacts
        for all phases of the proposed project based upon analysis of magnitude,
        frequency, scope and duration in context

    6.13  Cultural, Archeological, Ceremonial and Historic and Resources
6.13.1   Destruction during construction
6.13.2   Damage and alteration
6.13.3   Removal from  historic location
6.13.4   Introduction of visual or audible elements that diminish integrity
6.13.5   Neglect that causes deterioration
6.13.6   Loss of medicinal plants
6.13.7   Loss of access to traditional  use areas
6.13.8   Damage to resources due to increased visitation promoted by the project
6.13.9   Impacts to previously inaccessible resources from development/improvement
        of roads
6.13.10 Overall assessment of significance of direct, indirect and cumulative impacts
        for all phases of the proposed project based upon analysis of magnitude,
        frequency, scope and duration in context
                                                                                   E.4.2 Infrastructure:
                                                                                      Systems,
                                                                                      Equipment,
                                                                                      Capacity,
                                                                                      Performance
                                                                                   Table E-7

                                                                                   F.9 Socio-Economic
                                                                                      Conditions,
                                                                                      Infrastructure and
                                                                                      Land Use
                                                                                   E.4.3 Cultural,
                                                                                     Archeological,
                                                                                     Ceremonial and
                                                                                     Historic Resources
                                                                                   Table E-8

                                                                                   F. 10 Cultural,
                                                                                     Archeological,
                                                                                     Ceremonial and
                                                                                     Historic Resources
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                       70

-------
Volume I Part 2 - EIA Technical Review Guidelines:
              Tourism
3 EXAMPLE TERMS OF REFERENCE (TOR)
     COASTAL AND MARINE PROJECTS
    6.14  Land Use
6.14.1  Temporary and permanent changes in land use by both area and location
   6.14.1.1  Immediate project area
   6.14.1.2  Surrounding areas (induced by economic development)
   6.14.1.3  In previously inaccessible areas now accessible due to improvement of
             roads
6.14.2  Social infrastructure (schools, cemeteries, churches, other public buildings,
        communication systems and housing)
   6.14.2.1  Increased need for additional infrastructure
   6.14.2.2  Alterations to social infrastructure
6.14.3  Existing tourism and recreation infrastructure
   6.14.3.1  Change in tourist activities
   6.14.3.2  Increased need for tourism and recreation infrastructure
   6.14.3.3  Alterations to tourism and recreation infrastructure
6.14.4  Housing market (during construction and operation and after closure)
6.14.5  Identification of any components of the proposed project that would fall within
        25- or 100-year flood plains
6.14.6  Overall assessment of significance  of direct, indirect and cumulative impacts
        for all phases of the proposed project based upon analysis of magnitude,
        frequency, scope and duration in context

7   Mitigation and Monitoring Measures
    This section of the EIA must include measures designed to mitigate potential adverse impacts to
    physical, biological and social-economic-cultural resources from construction, operation and closure of
    the proposed project and alternatives. These shall include measures to avoid and prevent, and if
    needed, to reduce or minimize adverse impacts. The project proponent must include measures
    considered to be "best practices" in the design of all alternatives.

    Here and/or in the Environmental Management Plan section, proposed mitigation shall be described in
    auditable terms and at a level of detail sufficient to demonstrate its effectiveness in addressing the
    concern or performance criterion, including its anticipated level of effectiveness and/or measurable
    performance, and design specifications.

    The monitoring plan must include monitoring throughout the life of the project for each potential
    mitigation to confirm the effectiveness of the measure and support contingency plans to provide
    assurance that the project, at the site preparation, construction, operation, expansion, and closure
    stages will meet applicable environmental requirements/standards by law, and fall within the limits of
    impacts deemed acceptable upon approval of the EIA.  Some important items to address in the
    mitigation plan and associated monitoring plans include, but are not limited to the following:

Physical Impacts

    7.1 Geologic Resources and Hazards
7.1.1   Pre-excavation, onsite geological inspection and geotechnical study protocols to
       determine slope stability and landslide risks
7.1.2   Slopes built and maintained to avoid  landslides and favor revegetation and soils
       formation
7.1.3   Slope stabilization by constructing retaining walls, using vegetation, geotextile
       membranes, or other mechanical methods
7.1.4   Blasting Plan, if applicable (summary of relevant measures with full document in
       Annex)
7.1.5   Use of signage to mark areas where slopes are not stable as a preventive
       measure in  the event of a landslide
7.1.6   Mitigation measures  unique to specific alternatives

    7.2 Soil Resources
7.2.1   Erosion and sedimentation control measures (temporary and permanent)
       including when each will be installed  or implemented, how often it will be
       checked and the process for and timing of removal of temporary measures
7.2.2   Spoil and debris disposal measures
7.2.3   Best management practices to minimize soil disturbance
7.2.4   Decommissioning/Rehabilitation Plan-if needed (summary of relevant measures
                E.4.4 Land Use

                F.9 Socio-Economic
                  Conditions,
                  Infrastructure and
                  Land Use
               G. Mitigation and
                  Monitoring
                  Measures
               Tables G-l, G-2 & G-3
               Tables G-9
               Tables G-l, G-2 & G-3
               Appendix D
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                            71

-------
Volume I Part 2 - EIA Technical Review Guidelines:
             Tourism
                                                                   3 EXAMPLE TERMS OF REFERENCE (TOR)
                                                                       COASTAL AND MARINE PROJECTS
      with full document in Annex)
7.2.5  Restrictions on discharge of pollutants to soil
7.2.6  Mitigation measures unique to specific alternatives

    7.3 Water Resources
7.3.1  Quality
   7.3.1.1   Water Quality Management Plan (summary of relevant measures with full
            document in Annex)
            • Sewage and domestic wastewater
            • Nonpoint sources - runoff, erosion and sediment control prevention
              measures
   7.3.1.2   Spill Prevention and Containment Plan (summary of relevant measures
            with full document in Annex)
   7.3.1.3   Solid Waste Management Plan (summary of relevant measures with full
            document in Annex)
   7.3.1.4   Hazardous Waste Management Plan (summary of relevant measures with
            full document in Annex)
   7.3.1.5   Transport system construction and  maintenance to avoid erosion and
            sedimentation including:
            • Elevation or rerouting
            • Design for proper run-off control and catchment
            • Provision of culverts to allow flow that might otherwise be impeded by
              roadways or other rights of way
            • Appropriate traffic control
   7.3.1.6   Off-road vehicle use restrictions
   7.3.1.7   Waste minimization practices
7.3.2  Quantity
   7.3.2.1   Water conservation practices
7.3.3  Mitigation measures unique to specific alternatives

    7.4 Air and Climate
7.4.1  Dust control measures
7.4.2  Energy conservation measures
7.4.3  Emissions control measures
   7.4.3.1   Emissions reduction equipment
   7.4.3.2   Maintenance and inspection of equipment and vehicles using combustion
            engines to reduce emissions
7.4.4  Spill Prevention and Containment Plan (summary of relevant measures with full
      document in Annex)
7.4.5  Hazardous Materials Management Plan (summary of relevant measures with full
      document in Annex)
      Mitigation measures unique to specific alternatives
7.4.6

    7.5 Noise and Vibration
7.5.1  Noise control measures
   7.5.1.1   Noise reduction technologies (suppression equipment, sound-absorbing
            structures, vibration dampening devices, berms, noise barriers, etc.)
   7.5.1.2   Rerouting of traffic and other infrastructure related activities to minimize
            impacts of noise and vibration
   7.5.1.3   Time of day limitations on blasting and movement of heavy equipment
            when in close proximity to houses not being operated during evening
            hours
7.5.2  Blasting Plan, if applicable (summary of relevant measures with full document in
      Annex)
7.5.3  Mitigation measures unique to specific alternatives

    7.6 Aesthetic Resources
7.6.1  Relocation of project to another site
7.6.2  Redesign of placement of project structures on site
7.6.3  Redesign height and location of structures blocking view or producing light
      pollution
                                                                                 Table G-5
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                     72

-------
Volume I Part 2 - EIA Technical Review Guidelines:
             Tourism
3 EXAMPLE TERMS OF REFERENCE (TOR)
     COASTAL AND MARINE PROJECTS
7.6.4  Lighting minimization
7.6.5  Visual/Landscape Management Plan (summary of relevant measures with full
      document in Annex)
7.6.6  Mitigation measures unique to specific alternatives

Biological Impacts

    7.7 Vegetation/Flora and Associated Ecosystems
7.7.1  Control of noxious and invasive weeds
7.7.2  Measures to compensate for loss or damage of forests, wetlands or other critical
      ecosystems, including establishment of new protected areas
7.7.3  Restoration/Rehabilitation Plan for disturbed areas (summary of relevant
      measures with full document in Annex)
7.7.4  Mitigation measures unique to specific alternatives

    7.8 Aquatic and Terrestrial Wildlife/Fauna and Associated Ecosystems
7.8.1  Fish and Aquatic Resources
   7.8.1.1   Scheduling construction to avoid critical or important fish life history
            periods (e.g., spawning)
   7.8.1.2   Relocation of sensitive, threatened or endangered species
   7.8.1.3   Blasting Plan, if applicable (summary of relevant measures with full
            document in Annex)
   7.8.1.4   Mitigation measures unique to specific alternatives
7.8.2  Wildlife Resources
   7.8.2.1   Modify locations of structures and locations and timing of activities to
            avoid critical ecosystems, migratory routes and breeding areas
   7.8.2.2   Scheduling construction to avoid critical or important wildlife history
            periods (e.g., breeding, nesting)
   7.8.2.3   Relocation of sensitive, threatened or endangered species
   7.8.2.4   Blasting plan, if applicable (summary of relevant measures with full
            document in Annex)
   7.8.2.5   Mitigation measures unique to specific alternatives

Social-Economic-Cultural Impacts

    7.9 Socio-Economic Conditions
7.9.1  Selection of an alternate site for the project, and if not possible then adhering to
      requirements of an internationally  recognized Resettlement Action Plan (RAP)
7.9.2  Rehabilitation Program for people displaced by the project (summary of relevant
      measures with full document in Annex)
7.9.3  Training local residents for employment in the project
7.9.4  Development of a "Code of Conduct" (with associated training program) for
      workers to show respect to the local populations and their culture and social
      rules
7.9.5  Public Health Program to protect local population from potential health problems
      caused by the project operation (summary of relevant measures with full
      document in Annex)
7.9.6  Development of an Occupational Health, Industrial Safety and Accidents
      Prevention Program with appropriate accident prevention program, reporting
      and periodic review (summary of relevant measures with full document in Annex)
      including provision of routine training and testing, and proper safety equipment
      such as hearing protection, hardhats, steel-toed shoes, safety railings and fall
      arrestors
7.9.7  Spill Prevention and Containment Plan (summary of relevant measures with full
      document in Annex)
7.9.8  Hazardous Materials Management  Plan (summary of relevant measures with full
      document in Annex)
7.9.9  Mitigation measures unique to specific alternatives
               Tables G-l, G-2 & G-3
              Appendix F
                 Compensatory
                 Mitigation for Loss
                 of Aquatic
                 Resources
               Table G-4
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                      73

-------
 Volume I Part 2 - EIA Technical Review Guidelines:                                3 EXAMPLE TERMS OF REFERENCE (TOR)
	Tourism	COASTAL AND MARINE PROJECTS


     7.10   Infrastructure
 7.10.1  Transportation infrastructure
         This section of the EIA addresses mitigation measures for transportation and
         traffic patterns on existing infrastructure (roads, airports, air strips, harbors,
         etc.).  Mitigation of impacts of new and existing transportation infrastructure
         on water quality and biological resources and land use should be addressed in
         those respective sections.
    7.10.1.1 Transportation Plan (summary of relevant measures with full document in
             Annex)
             • Placement of traffic signals
             • Establishing, posting and enforcing speed limits for the vehicles that
               transport material
             • Training employees, contractors and subcontractors on measures to
               reduce or avoid potential accidents
             • Hiring and training security personnel devoted exclusively to preventing
               accidents in the access road and controlling the speed of the vehicles
               transporting project material
 7.10.2  Public health infrastructure
 7.10.3  Communications infrastructure
 7.10.4  Energy Infrastructure
 7.10.5  Mitigation measures unique to specific alternatives

     7.11   Cultural, Archeological, Ceremonial and Historic and Resources
 7.11.1  Modify structure and activity locations to avoid significant archeological,
         cultural, ceremonial and historic sites
 7.11.2  If avoidance is not possible, conduct appropriate resource recovery operations
         before disturbing the sites
 7.11.3  Clearly delineate boundaries and post signs identifying existing archeological,
         cultural and historic sites on roadsides and within the project area boundaries
         so that they are easily recognized by machinery operators, workers and
         tourists
 7.11.4  Development of a training program so that staff recognize and respect
         culturally  and archeological sensitive areas
 7.11.5  Development of a code of conduct for activities in indigenous and local
         communities with the consent of and in collaboration with the community
 7.11.6  Provide guests with information about and interpretation of the local culture
         and cultural heritage, as well as explaining appropriate behavior while visiting
         living cultures and cultural heritage sites
 7.11.7  Development protocols for use during construction and operation stages for
         identifying and responding to archeological, cultural, ceremonial and historic
         sites not identified during the preliminary surveys
    7.11.7.1 In the event such a site is found, they will stop activities at the site and
             report to the government relocation of cultural or historical resources,  for
             their  physical protection.
 7.11.8  Mitigation measures unique to specific alternatives

     7.12   Land Use
 7.12.1  Criteria  and method for calculating compensation for loss of land and crops
 7.12.2  Compensation to farmers and ranchers for crop or forage losses and restore
         lost agricultural lands at the end of the project.
 7.12.3  Compensation to property owners for relocation of their homes in the event
         the relocation is unavoidable
 7.12.4  Mitigation measures unique to specific alternatives

 8   Environmental Management Plan
     The EIA shall include an Environmental Management Plan to prevent, mitigate and monitor each
     impact identified in the EIA. Plans will describe actions to be taken in sufficient detail to provide a
     basis for subsequent auditing of compliance with commitments made in the EIA process including who
     is responsible, how and when it will be implemented, what will be done and what results will be
     achieved, why it is being done, and how to know whether it is effective in addressing the underlying

 CAFTA-DR AND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENT AND LABOR ExcELLENCE-CCAD-USEPA PROGRAM                 74

-------
Volume I Part 2 - EIA Technical Review Guidelines:
             Tourism
3 EXAMPLE TERMS OF REFERENCE (TOR)
     COASTAL AND MARINE PROJECTS
    concerns. The Environmental Management Plan shall have the following elements:

    8.1 Overview of Environmental Management Plan Organization and Policy
8.1.1  Describe the project management and how environmental management and
      organization relates to overall project responsibility. Describe the personnel and
      performance accountability system for design, operation, maintenance and
      closure for implementation of mitigation and monitoring measures
8.1.2  Describe the environmental policy that will govern the Project throughout its
      implementation, including at least the objectives, scope, commitment to
      continuous improvement, control and environmental monitoring and good
      relationship with neighboring populations and countries, as well as the
      commitment to internal controls such as compliance and environmental
      monitoring and routine audits
8.1.3  Identify the persons responsible for the  implementation of mitigation measures,
      in each phase

    8.2 Project-wide Mitigation Plan including an implementation schedule.  It
        has two elements:
8.2.1  Environmental resource mitigation (such as air, water)
8.2.2  Socio-economic-cultural mitigation (relocation, etc.)

    8.3 Project-Wide Monitoring Plan (usually specific to monitoring of
        surface and ground water)
8.3.1  Short-term and long-term monitoring of resource condition, including but not
      limited to:
   8.3.1.1   Slope stability
   8.3.1.2   Water Quality  Monitoring Program
            • Where, how and when  monitoring shall be conducted
            • Parameters to  be monitored
            • Monitoring frequencies
            • Sampling and analytical protocols to be used
   8.3.1.3   Air Quality Monitoring Program
            • Where, how and when  monitoring shall be conducted
            • The Parameters to be monitored
            • The monitoring frequencies
            • The sampling and analytical protocols to be used
   8.3.1.4   Noise and Vibration
   8.3.1.5   Cultural, ceremonial archeological and historic resources in the vicinity of
            the project
8.3.2  Short-term and long-term monitoring to ensure that the mitigation measures are
      functioning as  predicted and that rehabilitation  is working

    8.4 Management of Other On- or Off-Site Environmental Pollution Control
        and Infrastructure
    This section should address management of critical elements of pollution control and infrastructure
    that are not otherwise included in the mitigation plan because they were considered an essential part
    of the proposed project.

    8.5 Contingency Plans
    Contingency plans shall be prepared and described to address a) failure to meet specific performance
    criteria established by law or necessary for the project to meet its commitments in the EIA and b)
    respond to natural and other risks previously identified and mitigated in the EIA in the event
    reasonable and feasible mitigation measures to address the risks are inadequate.
8.5.1  Performance-related  Contingency Plans, indicating the steps that will be taken
      should monitoring  indicate that:
   8.5.1.1   Environmental standards  are not  being met
   8.5.1.2   Impacts are greater than predicted
   8.5.1.3   The mitigation measures and/or rehabilitation are not performing as
            predicted
8.5.2  Natural  Disaster Risk  Response Plan (assumes that risk identification and risk
      reduction have been addressed in other parts of the EIA)
8.5.3  Other Risks Response Plans (assumes that risk identification and risk reduction
      have been addressed in other parts of the EIA)
               H Environmental
                  Management Plan
               Table H-l
               Appendix F
                  Compensatory
                  Mitigation for Loss
                  of Aquatic
                  Resources
               Appendix E Sampling
               and Analysis Plan
CAFTA-DRAND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENTAND LABOR ExcELLENCE-CCAD-USEPA PROGRAM
                                                                                                       75

-------
 Volume I Part 2 - EIA Technical Review Guidelines:                                 3 EXAMPLE TERMS OF REFERENCE (TOR)
	Tourism	COASTAL AND MARINE PROJECTS

 8.5.4 Contingency plans for maintaining service or reducing downtime in the event of
       accidents or natural catastrophes that disrupt project operation

 9   Signed Commitment Statement
     The EIA shall contain a legally binding signed letter of commitment to meeting the terms of the EIA.
     The statement must be signed by the authorized representative of the proponent company with
     assurance that all financial surety measures as required by the regulatory agency have been met.

 10  Annexes
     These shall be numbered and duly referenced in the text

     10.1   Public Consultation
 10.1.1  Public consultation plan
 10.1.2  A summary of public outreach activities including: audience, number of
         persons, organizations involved, concerns raised, responses to comments
 10.1.3  Summary of  response to comments
 10.1.4  Actual copies of written comments

     10.2  Technical Supporting Documents
 10.1.5  Include maps, plans, charts and figures in the sequence mentioned in the EIA
         document
 10.1.6  Zoning maps with resources and results of impacts
 10.1.7  Special Studies if relevant but not readily accessible
 10.1.8  Detailed materials on predictive tools/models and assumptions used for the
         assessment but too detailed for the body of the EIA

     10.3   References
     Submit a list of all references, (books, articles, technical reports and other information sources) cited in
     the various chapters of the EIA study with full biographic references, and the following conventional
     procedures cited in the literature: author, year, title, source, number of pages, and city of publication
     or issuance.
 CAFTA-DR AND US COUNTRY EXPERTS SUPPORTED BY USAID-ENVIRONMENT AND LABOR ExcELLENCE-CCAD-USEPA PROGRAM                76

-------