Light-Duty Vehicle Technology

            Cost Analysis, Advanced 8-Speed

            Transmissions
&EPA
United States
Environmental Protection
Agency

-------
           Light-Duty Vehicle  Technology
         Cost Analysis, Advanced 8-Speed
                        Transmissions
                      Assessment and Standards Division
                     Office of Transportation and Air Quality
                     U.S. Environmental Protection Agency
                            Prepared for EPA by
                                FEV, Inc.
                        EPA Contract No. EP-C-07-069
                          Work Assignment No. 3-3
      NOTICE

      This technical report does not necessarily represent final EPA decisions or
      positions. It is intended to present technical analysis of issues using data
      that are currently available. The purpose in the release of such reports is to
      facilitate the exchange of technical information and to inform the public of
      technical developments.
United States
Environmental Protection
Agency
EPA-420-R-11-022
October 2011

-------
                                                                     Report FEV 07-069-303
                                                                           October 3, 2011
                                        CONTENTS
Section                                                                            Page

    Executive Summary	1-1
    1    Introduction	1-2
         1.1  Objectives	1-2
         1.2  Study Methodology	1-2
         1.3  Manufacturing Assumptions	1-5
         1.4  Subsystem Categorization	1-8
    2    Case Study Results	2-9
         2.1  Case Study #1005 Results	2-10
              2.1.1    6-Speed AT Hardware Overview - Baseline Technology
              Configuration	2-10
              2.1.2    8-Speed AT Hardware Overview - New Technology
              Configuration	2-11
              2.1.3    Net Incremental Direct Manufacturing Cost Impact (AT
              Analysis)2-12
         2.2  Case Study #1202 Results	2-15
              2.2.1    6-Speed DCT Hardware Overview - Baseline Technology
              Configuration	2-15
              2.2.2    8-Speed DCT Hardware Overview - Baseline Technology
              Configuration	2-16
              2.2.3    Net Incremental Direct Manufacturing Cost Impact (DCT
              Analysis)	2-19
    3    Glossary of Terms	3-21

-------
                                                                  Report FEV 07-069-303
                                                                       October 3, 2011

                                 LIST OF FIGURES
Number                                                                       Page
Figure 1 -1: Cost Analysis Process Flow Steps and Document Interaction	1-4
Figure 2-1: Illustration of ZF6HP28RWD Transmission	2-10
Figure 2-2: Illustration of ZF 8HP70 RWD Transmission	2-11
Figure 2-3: ZF Automatic Transmission Weight and Torque Comparison Data	2-11
Figure 2-4: Illustration of the Volkswagen DQ250 Wet Dual Clutch Transmission	2-15
Figure 2-5: Cross-sectional illustration of the Volkswagen 6-Speed DCT	2-16
Figure 2-6: 8-Speed Wet DCT Concept Illustration	2-17
                                          11

-------
                                                                Report FEV 07-069-303
                                                                      October 3, 2011
                                      LIST OF TABLES
Number                                                                      Page
Table ES- 1 New Technology Configurations Incremental Unit Cost Impact	1-1
Table 1-1: Summary of Universal Cost Analysis Assumptions Applied to All Case Studies	1-6
Table 1-2: Transmission System, Subsystem and Sub-Subsystem Classification	1-8
Table 2-1:  System Cost Model Analysis Template Illustrating the Incremental Subsystem Costs
Roll Up for an 8-Speed AT compared to a 6-Speed AT	2-14
Table 2-2:  System Cost Model Analysis Template Illustrating the Incremental Subsystem Costs
Roll Up for an 8-Speed DCT compared to a 6-Speed DCT	2-20
                                        111

-------
                                                             Report FEV 07-069-303
                                                                   October 3, 2011

       Light-Duty Vehicle Technology Cost Analysis, Advanced 8-Speed
                                Transmissions

Executive Summary

The United States Environmental Protection Agency (EPA) contracted with FEV,  Inc. to
determine the incremental direct manufacturing costs for a set of advanced,  light-duty
vehicle technologies. The technologies selected  are on the leading edge for reducing
emissions of greenhouse  gases in the  future, primarily in the form of tailpipe carbon
dioxide (CO2).

This report,  the  fourth  in a  series  of  reports,  addresses the direct  incremental
manufacturing cost of two (2) new powertrain configurations, relative to two (2) existing
baseline  configurations, with comparable driver performance metrics.  The complete
costing methodology used in the analysis of these  configurations, as well as the pilot case
study, is  described in "Light-Duty Technology Cost Analysis  Pilot Study (EPA-420-R-
09-020)."
The two (2) new powertrain technology configurations analyzed are:

   •  A  next generation ZF 8-speed automatic transmission, compared to a ZF 6-speed,
      Lepelletier concept-based, automatic transmission
   •  A  6-speed wet dual clutch transmission (DCT), compared to an 8-speed wet dual
      clutch transmission (DCT)

The results for the two (2) case studies are shown below in Table ES-1.
       Table ES- 1 New Technology Configurations Incremental Unit Cost Impact
Case Study
Reference
Number
1005
1202
Technology
Definition
8-Speed AT
replacing a 6-Speed
AT
8-Speed DCT
Replacing a 6-Speed
DCT
Vehicle Class
Large Truck Passenger
or Commercial Vehicle
with Strong Towing
Capabilities
Mid to Large Size Car,
Passenger 4-6
Base
Technology
CS#B1005
6-Speed AT
CS#B1202
6-Speed Wet
DCT
New
Technology
CS#N1005
8-Speed AT
CS#N1202
8-Speed
Wet DCT
Incremental
Unit Cost
+ $61.84
+ $198.14
                                     1-1

-------
                                                               Report FEV 07-069-303
                                                                    October 3, 2011
1   Introduction
1.1  Objectives
The  objective  of this  work  assignment  was  to  determine the  incremental  direct
manufacturing costs for two (2) new advanced light-duty vehicle transmission technology
configurations using the costing  methodology,  databases,  and supporting  worksheets
developed in the previously concluded pilot study (Light-Duty Technology Cost Analysis
Pilot Study [EPA-420-R-09-020]).


1.2  Study Methodology

The first report published, "Light-Duty Technology Cost Analysis Pilot Study (EPA-420-
R-09-020)," covers in great detail the overall costing methodology used to calculate an
incremental cost  delta between various technology configurations.   In summary, the
costing methodology is heavily based on teardowns of both new and baseline technology
configurations having similar driver performance metrics. Only components identified as
being different, within the selected new and baseline technology configurations, as a
result of the new technology adaptation are evaluated for cost.   Component costs are
calculated using a ground-up costing methodology analogous to  that employed  in the
automotive industry.  All incremental  costs for the new technology are calculated and
presented using transparent cost  models consisting  of eight (8) core  cost elements:
material, labor, manufacturing overhead/burden, end item scrap, SG&A (selling general
and administrative),  profit, ED&T (engineering,  design, and testing),  and packaging.
Information on how additional associated manufacturing fixed and variable cost elements
(e.g., shipping, tooling, OEM indirect costs) are accounted for within the cost analysis are
also discussed in the initial report (EPA-420-R-09-020).

Listed below, with the  aid of Figure  1-1, is a high level summary of the ten (10) major
steps taken during the cost analysis process.  For additional information concerning the
terminology used within the ten (10)  steps, please reference the glossary of terms found
at the end of this report.

Step 1;  Using the Powertrain-Vehicle Class Summary Matrix (P-VCSM), a technology
is selected for cost analysis.

Step 2; Existing  vehicle models  are identified for teardown to  provide the basis for
detailed incremental cost calculations.

Step 3;  Pre-teardown Comparison Bills of Materials (CBOM) are developed, covering
hardware that  exists  in the new and  base technology configurations. These high level
CBOM's are informed by the team's understanding of the new and base technologies and
serve to identify the major systems and components targeted for teardown.

                                       1-2

-------
                                                              Report FEV 07-069-303
                                                                    October 3, 2011

Step 4; Phase 1 (high level) teardown is conducted for all subsystems identified in Step
3 and the assemblies that comprise them.  Using Design Profit® software, all high level
processes (e.g., assembly process of the high pressure fuel pump onto the cylinder head
assembly) are mapped during the disassembly.

Step 5; A cross functional team (CFT) reviews all the data generated from the high level
teardown and identifies  which components and assumptions should  be  carried forward
into the cost analysis.  The CBOMs are updated to reflect the CFT input.

Step  6; Phase 2 (component/assembly level)  teardowns  are initiated, based on the
updated CBOM's.  Components and assemblies are disassembled,  and processes  and
operations  are  mapped  in  full detail.   The process  mapping  generates key process
information for the quote  worksheets.  Several databases containing  critical costing
information provide support to the mapping process.

Step  7;  Manufacturing Assumption and Quote Summary (MAQS)  worksheets are
generated for all parts undergoing the cost analysis.  The MAQS  details all cost elements
making up the final unit costs: material, labor,  burden, end item scrap, SG&A, profit,
ED&T, and packaging.

Step 8; Parts with high or unexpected cost results are subjected  to a marketplace cross-
check, such as comparison  with supplier  price  quotes  or  wider consultation  with
company and industry resources (i.e., subject matter experts) beyond the CFT.

Step 9; All costs calculated in the MAQS worksheets are automatically inputted into the
Subsystem Cost Model Analysis Templates (CMAT).   The  Subsystem CMAT is used to
display and roll up all the differential costs associated with  a subsystem. All parts in a
subsystem that  are identified  for costing in the  CBOM are  entered into the Subsystem
CMAT. Also both the base and new technology configurations are included in the same
CMAT to facilitate differential cost analysis.

Step 10;   The final step in  the process is creating the System  CMAT which rolls up all
the subsystem differential costs to establish a final system unit cost. The  System CMAT,
similar in function to the subsystem CMAT, is the document used to  display and roll-up
all the subsystem  costs associated within a system as defined by  the CBOM.  Within the
scope of this cost analysis, the System CMAT provides the bottom line incremental unit
cost between the base and new technology configurations under evaluation
                                       1-2

-------
                                                                          Report FEV 07-069-303
                                                                                 October 3, 2011
1. Technology
Selection
Powertrain Vehicle
Class Summary Matrix
(P-VCSM)
i '
2. Hardware
Selection
Powertrain Package
Proforma
i '
3A. Generate Bill of
Materials - Phase 1

Materials (C-BOM)







                           4. System/Subsystem
                             Disassembly and
                            Process Mapping -
                                 Phase 1

                              (Design Profit®)
Process Flow
Manual & Automated
Document Links
                                   I
                            5. Cross Functional
                               Team (CFT)
                                Reviews
   Databases (Material, Labor, Manufacturing
       Overhead, Mark-up, & Packaging)
  6. Component/
    Assembly
  Disassembly &
Process Mapping -
     Phase 2

  (Design Profit®)
                               3B. Update Bill of Materials - Phase 2

                                 Comparison Bill of Materials (C-BOM)
  7. Generate
Manufacturing
Assumption and
Quote Summary
   (MAQS)
  Worksheets
                                                                              8. Market Place
                                                                                Cross-check
                         9. Subsystem Cost
                             Roll Up

                         Subsystem Cost Model
                          Analysis Template
                         (Subsystem CMAT)
                                                                               10. System Cost
                                                                                 Roll Up

                                                                               System Cost Model
                                                                               Analysis Template
                                                                               (System CMAT)
        Figure 1-1: Cost Analysis Process Flow Steps and Document Interaction
                                              1-4

-------
                                                              Report FEV 07-069-303
                                                                    October 3, 2011
1.3  Manufacturing Assumptions
When conducting the cost analysis for the various technology configurations, a number
of assumptions are made in order to establish a consistent framework for all costing. The
assumptions can be broken into universal and specific case study assumptions.

The universal assumptions apply to all technology configurations under analysis.  Listed
in Table 1-1 are the fundamental assumptions.

The  specific  case study  assumptions  are  those  unique  to  a  given technology
configuration.  These include volume assumptions, weekly operation assumptions (days,
shifts, hours, etc.), packaging  assumptions, and Tier 1 in-house manufacturing versus
Tier 2/3 purchase part assumptions. Details on the case study specific assumptions can
be found in the individual MAQS worksheets.
                                       1-5

-------
                                                                               Report FEV 07-069-303
                                                                                      October 3, 2011

   Table 1-1: Summary of Universal Cost Analysis Assumptions Applied to All Case
                                               Studies
Item
Description
Universal Case Study Assumptions
      Incremental Direct Manufacturing Costs
                          A. Incremental Direct manufacturing cost is the incremental
                          difference in cost of components and assembly, to the OEM,  between
                          the new technology configuration and the baseline technology
                          configuration.

                          B. This value does not include Indirect OEM costs associated with
                          adopting the new technology configuration (e.g. tooling, corporate
                          overhead, corporate R&D, etc).
      Incremental Indirect OEM Costs are not
      handled within the scope of this cost
      analysis
                          A. Indirect Costs are handled through the application of "Indirect
                          Cost Multipliers" (ICMs) which are not included as part of this
                          analysis.  The ICM covers items such as	
                          a. OEM corporate overhead (sales, marketing, warranty, etc)
                          b. OEM engineering, design and testing costs (internal & external)
                          c. OEM owned tooling

                          B. Reference EPA report EPA-420-R-09-003, February 2009,
                          "Automobile Industry Retail Price Equivalent and Indirect Cost
                          Multiplier" for additional details on the develop and application of
                          ICM factors.
      Product/Technology Maturity Level
                          A. Mature technology assumption, as defined within this analysis,
                          includes the following:
                          a. Well developed product design
                          b. High production volume
                          c. Products in service for several years at high volumes
                          c. Significant market place competition

                          B. Mature Technology assumption establishes a consistent framework
                          for costing. For example, a defined range of acceptable mark-up
                          rates.
                          a. End-item-scrap 0.3-0.7%
                          b. SG&A/Corporate Overhead 6-7%
                          c. Profit 4-8%
                          d. ED&T (Engineering, Design and Testing) 0-6%

                          C. The technology maturity assumption does not include allowances
                          for product learning.   Application of a learning curve to the
                          calculated incremental direct manufacturing cost is handled outside
                          the scope of this analysis.
                                                 1-6

-------
                         Report FEV 07-069-303
                               October 3, 2011
Item
4
5
6
7
8
9
10
11
12
13
14
Description
Selected Manufacturing Processes and
Operations
Annual Capacity Planning Volume
Supplier Manufacturing Location
OEM Manufacturing Location
Manufacturing Cost Structure Timeframe
( e.g. Material Costs, Labor Rates,
Manufacturing Overhead Rates)
Packaging Costs
Shipping and Handling
Intellectual Property (IP) Cost
Considerations
Material Cost Reductions (MCRs) on
analyzed hardware
Operating and End-of Life Costs
Stranded Capital or ED&T expenses
Universal Case Study Assumptions
A. All operations and processes are based on existing
standard/mainstream Industrial practices.
B. No additional allowance is included in the incremental direct
manufacturing cost for manufacturing learning. Application of a
learning curve to the developed incremental direct manufacturing cost
is handled outside the scope of this analysis.
450,000 Units
North America (USA or Canada)
North America (USA or Canada)
2009/2010 Production Year Rates
A. Calculated on all Tier One (Tl) supplier level components.
B. For Tier 2/3 (T2/T3) supplier level components, packaging costs
are included in Tl mark-up of incoming T2/T3 incoming goods.
A. T 1 supplier shipping costs covered through application of the
Indirect Cost Multiplier (ICM) discussed above.
B. T2/T3 to Tl supplier shipping costs are accounted for via Tl mark-
up on incoming T2/T3 goods.
Where applicable IP costs are included in the analysis. Based on the
assumption that the technology has reached maturity, sufficient
competition would exist suggesting alternative design paths to achieve
similar function and performance metrics would be available
minimizing any IP cost penally.
Only incorporated on those components where it was evident that the
component design and/or selected manufacturing process was chosen
due to actual low production volumes (e.g. design choice made to
accept high piece price to minimize tooling expense). Under this
scenario, assumptions where made, and cost analyzed assuming high
production volumes.
No new, or modified, maintenance or end-of-life costs, were identified
in the analysis.
No stranded capital or non-recovered ED&T expenses were
considered within the scope of this analysis. It was assumed the
integration of new technology would be planned and phased in
minimizing non-recoverable expenses.
1-7

-------
                                                               Report FEV 07-069-303
                                                                     October 3, 2011
1.4  Subsystem Categorization
As with the first case study analysis, a design based classification system was used to
group the various components and assemblies making up the technology configurations.
In general, every vehicle system (e.g., engine system, transmission system, etc) is made
up of several subsystems levels (e.g., the transmission system includes a case subsystem,
geartrain subsystem, internal clutch subsystem, launch clutch subsystem,  oil pump and
filter subsystem, etc.), which, in turn, is made up of several sub-subsystem levels  (e.g.,
the geartrain subsystem  includes the following sub-subsystems: input shaft, output shaft,
transfer shaft, planetary  gear, etc).  The sub-subsystem is the smallest classification level
in which all components and assemblies are binned.

Table 1-2 provides an overview of the  major  subsystems and sub-subsystems included
for each system evaluated within this analysis.  In Section 2, Case Study  Results,  costs
are  presented  for  both  transmission  evaluations  using  these  design  subsystem
categorizations.

 Table 1-2: Transmission System, Subsystem and Sub-Subsystem Classification
Subsystem
Externally Mounted Component
Case(s)
Gear Train
Internal Clutch
Launch Clutch
Oil Pump and Filter
Mechanical Control
Electrical Control
Park Mechanism
Sub-Subsystem
Lift Eye, Vent Cap, Bracket, Bolting
Transaxle Case, Transaxle Housing, Covers, Bearing Race,
Plug, Actuator
Input Shaft, Output Shaft, Transfer Shaft, Sun Gear,
Planetary Gear, Ring Gear, Counter Gear, Differential
Gear, Bearing (Roller, Needle)
Sprag Clutch, Clutch & Brake Hub, Disc and Plate, Piston,
Snap Ring, Bearing (Roller, Needle), Synchronizer
Torque Converter, Clutch Assembly, Flexplate, Flywheel
Oil pump, Cover, Oil Filter, Oil Cooler, Oil Squirter,
Pipes/Tubes
Valve Body Assembly, Mechanical Controls (e.g., Shift
Forks), Sealing Elements, Bearing Elements, Plugs & Cups
Controller, Solenoid, Sensor, Switches, Wiring Harness
Rod/Shaft/Pin, Spring, Pawl, Bracket, Bolt
                                        1-8

-------
                                                             Report FEV 07-069-303
                                                                  October 3, 2011
2   Case Study Results
The incremental direct manufacturing cost impact for the 6-speed to 8-speed automatic
transmission (AT) comparison and the 6-speed to 8-speed wet dual clutch transmission
(DCT) are shown above in

Within Section 2.0, for each case study, a brief description of the performance attributes
of both the baseline and new technology configurations are provided.  In addition a high
level overview of key hardware content is included for each technology evaluated.

In the 6-speed DCT to 8-speed DCT analysis, no 8-speed DCT hardware was available at
the time of the analysis.  Using the 6-speed DCT as the foundation, the FEV team made
some  basic assumptions on how the 6-speed DCT could be modified to produce an 8-
speed variant. The assumptions can be found in the respective section.

Following the  system performance and hardware overviews for each case study, the
increment direct  manufacturing cost impact is  summarized at  a subsystem level in  a
system Cost Model Analysis Template (CMAT).

Because  each  case  study  consists of a large  quantity of component and assembly
Manufacturing and Assumption Quote Summary (MAQS) worksheets, hard copies were
not included as part of this report.  However, electronic copies of the MAQS worksheets,
as well as all other supporting case study documents (e.g.,  Subsystem CMATs, System
CMATs), can be accessed at http;//www.epa.gov/otaq/climate/publications.htm
                                      2-9

-------
                                                              Report FEV 07-069-303
                                                                   October 3, 2011
2.1  Case Study #1005 Results
Case Study #1005 analyzed the direct incremental manufacturing cost for updating from
a ZF 6-speed, Lepelletier concept, automatic transmission to a next generation 8-speed
automatic transmission.

2.1.1  6-Speed AT Hardware Overview - Baseline Technology Configuration
               Figure 2-1: Illustration of ZF 6HP28 RWD Transmission

The 6-speed automatic transmission selected for the baseline analysis was the ZF 6HP28
RWD transmission (second generation of ZF 6HP26). This transmission is/has been used
in various applications including the BMW Series 3 Coupe and the X5 SUV in the 2007-
2012 timeframe.  The ZF 6-Speed transmission incorporates a Lepelletier AT gearing
configuration which utilizes a single planetary gear set along with a Ravigneaux gear set.
The use  of a Lepelletier configuration allowed ZF to add an  additional gear without
sacrificing size, weight and part content over the existing 5-speed AT. In fact the 6-speed
AT weighs approximately  12% less, and has  29% fewer parts, than its predecessor.
(Source: SAE Technical Paper 2003-01-0596).  Listed below are a few design parameters
for the 6-speed AT.

      •  Total of five (5) shift elements, two (2) open shift elements per gear

      •  Three (3) clutches and two (2) brakes

      •  Full planetary gear set and a Ravigneaux gear set

      •  The total weight of the transmission, including  Automatic Transmission Fluid
         (ATF),  is approximately 92.5kg.  The maximum output torque rating is 650
         Nm.
                                      2-10

-------
                                                                Report FEV 07-069-303
                                                                      October 3, 2011
2.1.2 8-Speed AT Hardware Overview - New Technology Configuration
               Figure 2-2: Illustration of ZF 8HP70 RWD Transmission

The ZF 8-speed automatic transmission (AT), the successor to the ZF 6-speed AT, was
selected for the analysis representing the new advance technology configuration. The ZF
8-speed RWD transmission (8HP70) (Figure  2-2)  was a complete  redesign of the
existing Lepelletier-based 6-speed transmission family, which originally launched in the
2001 timeframe.  The implementation of a revolutionary gearing system, consisting of 4
planetary gear sets, controlled by an equivalent number of shift elements as compared to
the ZF 6-speed AT, supports a net 6% overall fuel economy improvement relative to its
predecessor.  In addition to maintaining the same overall installation dimensions, the new
8-speed transmission has a higher torque to weight ratio as shown below in Figure 2-3.
                    ZF Automatic Transmissions - Weight Comparison
                    Torque [Mm]
                              300    400   500    600    700    800
                 (Source: ZF Published Document "The Freedom to Exceed Limits",
  http://www.zf.com/media/media/en/document/corporate_2/products_3/innovation_l/8hp_l/8HP_de_2007s.pdf)

     Figure 2-3: ZF Automatic Transmission Weight and Torque Comparison Data
                                       2-11

-------
                                                             Report FEV 07-069-303
                                                                   October 3, 2011
Design parameters for the 8-speed AT,  for comparison  to the ZF 6-speed AT,  are
presented below.

      •  Five (5) shift elements, two (2) open shift elements per gear.

      •  Three (3) disk clutches and two (2) brakes

      •  Four (4) planetary gear sets.

      •  Lost torque is reduced by 33% compared to a 6-speed.

      •  Gear set efficiency exceeds 98%

      •  The total weight of the  transmission (as measured),  including ATF, is  89kg.
         The maximum output torque rating is 700 N*m



2.1.3  Net Incremental Direct Manufacturing Cost Impact (AT Analysis)

As discussed in the initial report (EPA-420-R-09-020), the costing methodology employs
an exclusion approach to costing. Following  completion of the  comparison bill  of
materials (CBOMs),  the cross functional team began the process  of analyzing  the
differences between hardware on the six (6) and eight (8) speed automatic transmissions.
A component function and design analysis was performed, eliminating  many parts and
components  from further costing analysis. A baseline cost from which an incremental
cost for the 8-speed was established. The majority  of incremental cost increase of the 8-
speed over the 6-speed was associated with the additional gearing.

It was obvious from the transmission teardown assessment that in addition to ZF's goal
for  improving overall performance with their new  8-speed automatic transmission
relative to the  6-speed predecessor, ZF  also focused on optimizing cost and weight. In
regard to the 6-speed automatic transmission, many of innovative ideas implemented into
the 8-speed automatic could have been incorporated into a new 6-speed if it were to be
redesigned.  The most obvious new technology advance  (NTA) would be adopting a
similar drum and  carrier  system, which would conceivably  have the same benefits
(compact packaging, streamlined and less costly to  assemble) recognized by the 8-speed
automatic. As part of this analysis, no additional work was conducted to determine what
the financial impact would be on the 6-speed automatic by employing some of these new
technology advances  and material cost  reduction concepts. The  net incremental direct
manufacturing cost shown below is solely based on the physical hardware evaluated.
                                      2-12

-------
                                                               Report FEV 07-069-303
                                                                    October 3, 2011

Table 2-1 shows the net incremental direct manufacturing cost between the 8- and 6-
speed automatic  transmissions.   In  evaluating the physical hardware,  the  6-speed
automatic was analyzed to be less expensive to manufacture by approximately $62. Note
that  when  the 8-speed  transmission was redesigned, several  other functional  and
performance  updates  not driven by  the  added gear  ratios  were  incorporated (e.g.,
modified hydraulic control strategy, spool valve material,  friction discs, as well as a
newly-developed  torque  converter).   These modifications were not  estimated in the
analysis since they are independent of the gear ratio addition and modifications.

As shown in Table 2-1 many of the transmission subsystems where deemed cost neutral.
Much of the cost  analysis work was focused on the cost difference in the gear train and
internal clutch subsystems.   An  internal  clutch subsystem cost save of $12.56 was
calculated for the 8-speed AT.  However the 8-speed AT gear train subsystem increased
in cost by $74.40 resulting in a net incremental direct manufacturing cost of $+61.84.
                                      2-13

-------
                                                            Report FEV 07-069-303
                                                                  October 3, 2011
Table 2-1: System Cost Model Analysis Template Illustrating the Incremental Subsystem
            Costs Roll Up for an 8-Speed AT compared to a 6-Speed AT
SYSTEM & SUBSYSTEM DESCRIPTION
i



1
2
3
4
5
6
7
8
9
10


g> Sub-Subsystem Description

02 TRANSMISSION SYSTEM

| 01 EXTERNAL COMPONENTS:
| 02 CASE(S):
| 03 GEAR TRAIN:
| 04 INTERNAL CLUTCHES:
| 05 LAUNCH CLUTCHES:
| 06 OIL PUMP & FILTER:
| 07 MECHANICAL CONTROLS:
| 08 ELECTRICAL CONTROLS:
| 09 PARK MECHANISM:
| 10 MISCELLANEOUS ITEMS:

SUBSYSTEM ROLL-UP

SYSTEM & SUBSYSTEM DESCRIPTION
i



1
2
3
4
5
6
7
8
9
10


gj> Sub-Subsystem Description

02 TRANSMISSION SYSTEM

| 01 EXTERNAL COMPONENTS:
| 02 CASE(S):
| 03 GEAR TRAIN:
| 04 INTERNAL CLUTCHES:
| 05 LAUNCH CLUTCHES:
| 06 OIL PUMP & FILTER:
| 07 MECHANICAL CONTROLS:
| 08 ELECTRICAL CONTROLS:
| 09 PARK MECHANISM:
| 10 MISCELLANEOUS ITEMS:

SUBSYSTEM ROLL-UP

SYSTEM & SUBSYSTEM DESCRIPTION
I



1
2
3
4
5
6
7
8
9
10


$ Sub-Subsystem Description

02 TRANSMISSION SYSTEM

| 01 EXTERNAL COMPONENTS:
| 02 CASE(S):
| 03 GEAR TRAIN:
| 04 INTERNAL CLUTCHES:
| 05 LAUNCH CLUTCHES:
| 06 OIL PUMP & FILTER:
| 07 MECHANICAL CONTROLS:
| 08 ELECTRICAL CONTROLS:
| 09 PARK MECHANISM:
| 10 MISCELLANEOUS ITEMS:

SUBSYSTEM ROLL-UP
NEW TECHNOLOGY PACKAGE COST INFORMATION
8 Speed ZF Automatic Transmission
Manufacturing
Material






$ 75.79







$ 125.37
Labor






S 27.13







$ 67.94
Burden






S 78.47







$ 171.32
Total
Cost
Assembly)






S 181.39







$ 364.63
Markup
Scrap






S 1.34







$ 2.26
SG&A






S 12.69







$ 24.77
Profit






S 11.51







$ 22.62
ED&T-R&D






S 4.58







$ 9.17
Total Markup
Cost
Assembly)






S 30.12







$ 58.82
Total
Packaging
Cost
Assembly)






s







S
Net
Component/
Impact to OEM






S 211.50







$ 423.44

BASE TECHNOLOGY PACKAGE COST INFORMATION
6 Speed ZF Automatic Transmission
Manufacturing
Material
















Labor
















Burden
















Total
Cost
Assembly)
















Markup
Scrap
















SG&A
















Profit
















ED&T-R&D
















Total Markup
Cost
Assembly)
















Total
Packaging
Cost
Assembly)





s










Net
Component/
Impact to OEM





S 137.53








$ 361.60

INCREMENTAL COST TO UPGRADE TO NEW TECHNOLOGY PACKAGE
Manufacturing
Material




$
$ 14.46
S (5.97)
s
s
s
s
s
s

S 8.49
Labor




s

S (4.13)
s
s
s
s
s
s

$ 15.11
Burden




s


s
s
s
s
s
s

S 28.20
Tota.
Cost
(Component/
Assembly)




s


s
s
s
s
s
s

$ 51.80
Markup
End Item
Scrap




s


s
s
s
s
s
s

S 0.69
SG&A




s


s
s
s
s
s
s

$ 4.27
Profit




s


s
s
s
s
s
s

$ 3.74
ED&T-R&D




s

S (0.27)
s
s
s
s
s
s

$ 1.34
Total Markup
Cost
(Component/
Assembly)




s
S 10.12
S (0.08)
s
s
s
s
s
s

$ 10.04
Total
Packaging
Cost
(Component/
Assembly)




s
s
s
s
s
s
s
s
s

S
Net
Component/
Assembly Cost
Impact to OEM




s
S 74.40
S (12.56)
s
s
s
s
s
s

$ 61.84
                                     2-14

-------
                                                               Report FEV 07-069-303
                                                                     October 3, 2011
2.2  Case Study #1202 Results
Case Study #1202 analyzed the direct incremental manufacturing cost for updating from
a 6-speed, wet dual clutch transmission (DCT) to an 8-speed, wet DCT.

2.2.1  6-Speed DCT Hardware Overview - Baseline Technology Configuration
                                        Oil cleaner
                                                         Oil cooler
                  Selector lever cable
                                                                 Manual gearbox
               Parking lock
                                                                          Oil pump
  Bevel box (quattro)
                                                              Mechatronics
                                              Reverse shaft
    Figure 2-4: Illustration of the Volkswagen DQ250 Wet Dual Clutch Transmission

The baseline technology configuration selected for the  analysis was  the  Volkswagen
(VW) 6-speed, wet, dual clutch transmission  (DCT); model number DQ250.   Other
industry  naming conventions  for  this technology  configuration include  twin-clutch
gearbox or dual shift gearbox (DSG).  The basic components of the DCT include a twin
clutch pack assembly driving  two (2) coaxial input shafts.   Power from the engine is
transmitted to the input shafts through a dual-mass flywheel which is connected in series
to the twin-clutch pack.  Each  input shaft, dependent on the selected gear, is designed to
mesh with one (1)  of two (2) output shafts.  Upon reverse  gear selection, there is an
intermediate shaft which engages with both input shaft one (1) and output shaft two (2).
There are four (4) shift  forks,  two (2) on  each output shaft,  hydraulically activated into
one of two positions from their neutral home position. The controls for the  DCT, which
include the hydraulic controls,  electronic controls, and various sensors and actuators, are
                                       2-15

-------
                                                              Report FEV 07-069-303
                                                                    October 3, 2011

integrated into a single module VW refers to as a Mechatronic unit. The total weight of
the transmission module, including the dual-mass flywheel, is approximately 94 kg. The
maximum output torque rating for the DQ250 transmission is 350Nm.

2.2.2  8-Speed DCT Hardware Overview - Baseline Technology Configuration

At the time of the study, there were no 8-speed DCTs available in the market to support
the cost analysis. Therefore a modified approach was taken for this  case study.  Using
the 6-speed wet DCT as the foundation, the FEV team developed some basic assumptions
on how the 6-speed DCT could be modified to produce an 8-speed variant. Using the 6-
speed parts and some concept sketches, the team created a bill of material for the 8-speed
DCT.  The 8-speed DCT is only a simple concept of what an 8-speed DCT may look like
at a high  level; providing sufficient information to  develop an  incremental  direct
manufacturing cost.   Figure 2-5 provides a cross-section view of the baseline 6-speed
wet DCT.
                   Dual mass flywheel
            (Source: Audi Service Training Manual, 6-speed twin-clutch gearbox 02E S tronic)

        Figure 2-5: Cross-sectional illustration of the Volkswagen 6-Speed DCT
For the 8-speed DCT concept, the input, output and reverse drive shafts were extended
between the 3rd and 4th gear such that a 7th and 8th synchronized gear set could be added

                                      2-16

-------
                                                              Report FEV 07-069-303
                                                                    October 3, 2011

in (Reference Figure 2-6).  In addition to the added synchronized gear sets, associated
components such as shift forks, hydraulic cylinders and pistons, fork detents, solenoids
and hydraulic control valves were added to the BOM. These components are not shown
in Figure 2-6 below.  Further,  additional considerations for modifying the front and rear
cases, valve body, channel plate, input shafts, output shafts and pump shaft were included
in the assumptions.
                 Figure 2-6: 8-Speed Wet DCT Concept Illustration
Additional assumptions made by the DCT evaluation team while developing the 8-speed
DCT concept included the following:
                                      2-17

-------
                                                        Report FEV 07-069-303
                                                              October 3, 2011

The addition of the 7th an 8th gear to the 6-speed DCT does provide fuel efficiency
savings
Engine torque and transmission capacity are matched
The target vehicle(s) can accommodate the additional length of the transmission
Additional length of output shafts do not cause shaft bending issues which lead to
NVH problems
Additional length of the reverse shaft does not cause shaft bending issues
Center distances of the output shafts within the transmission cases will not be the
same for six and eight speed DCT transmissions
Output shaft diameters and splines configurations will change to accommodate the
seventh and eighth gears
Change gear internal diameters and splines will all change to accommodate the
seventh and eighth gears
Bearing supports for the output shafts ends will need to be adequately sized to
support the torques and loads
 All input and output change gear outside diameters will change and the resulting
ratios and number of teeth will fit into the launch through overdrive ratio
requirements
Final drive ratios for the output driven gear and the two drive gears will change to
accommodate the eight forward and one reverse gear ratios
The schematics show a separate synchronizer assembly for both the 7th and 8th
change gears
The schematics shown with this report are only intended to represent the
additional and modified components required to go from a six-speed to an eight-
speed DCT.
These transmission schematics do not represent a fully functional design of an
eight-speed DCT
                                2-18

-------
                                                              Report FEV 07-069-303
                                                                    October 3, 2011

2.2.3  Net Incremental Direct Manufacturing Cost Impact (DCT Analysis)

Table 2-2 shows the net incremental, direct manufacturing cost between the 6-speed wet
DCT and 8-speed wet DCT.  In the evaluation, the 8-speed wet DCT was analyzed to be
more expensive to manufacture by  approx $198.  The major cost increment of the 8-
speed DCT was the additional content in the mechanical controls subsystem at $106.15
Included in this  add  cost are the  7th and  8th gear synchronizers,  hubs,  shift  fork
assemblies, spool valves and solenoids.  Modifications to the valve body to accommodate
the additional function an
included in this subsystem.
the additional function  and hardware for the 7th  and 8th gear set addition was also
The next largest contributor to the added cost was the gear train subsystem at $64.04.
Included in this subsystem were the additional 7th and 8th input and output gears plus the
additional  modification  to  both  input  and  output  shafts  and  the reverse  shaft.
Modifications  to the case accounted for  the majority of remaining costs  contributing
$20.85 to the net incremental direct manufacturing cost.
                                      2-19

-------
                                                            Report FEV 07-069-303
                                                                  October 3, 2011
Table 2-2: System Cost Model Analysis Template Illustrating the Incremental Subsystem
           Costs Roll Up for an 8-Speed DCT compared to a 6-Speed DCT
SYSTEM & SUBSYSTEM DESCRIPTION
I



2
3
4
5
6
7
9
10


I
a
Sub- Subsystem Description

02 TRANSMISSION SYSTEM







02 CASE(S):
03 GEAR TRAIN:
04 INTERNAL CLUTCHES:
05 LAUNCH CLUTCHES:
06 OIL PUMP & FILTER:
07 MECHANICAL CONTROLS:
08 ELECTRICAL CONTROLS: (Combined w/ Mechnical Controls)
09 PARK MECHANISM:
10 MISCELLANEOUS ITEMS:

SUBSYSTEM ROLL-UP

SYSTEM & SUBSYSTEM DESCRIPTION
I



2
3
4
5
6
8
9





SOSA



S
S
S

>



Prp,«



S
S
S

>



EOST-RSD



S
S
S

$



Assambly)



S
S
$ 10.40
S

$



Packaging



S
S
S
S

$



COStOEM30tt°



S 20.85
$ 64.04
S 106.15
S

$ 7.10

S 198.14

BASE TECHNOLOGY PACKAGE COST INFORMATION
6 Speed Wet DCT







, -


9






, -








S -

Total
Cost
Assembly)




,

Markup
E-sdjr




, -







, -







, -







S -

Total Markup
Cost





,

Packaging





, -

Consonant/





S


INCREMENTAL COST TO UPGRADE TO NEW TECHNOLOGY PACKAGE






>
S 5.50
$ 20.23
$
$
$
S
S
S 1.82




9





>
> 1.19
> 5.5S
»
»
>
S
S
S 2.78









$
$ 14.17
$ 38.23
$ -
$ -
$
S
S
S 2.50



Tot.l
0=,, '
Assambly)



>
> 20.85
> S4.04
»
»
>
S
S
S 7.10



Markup
E-sdjr



>
» -
» -
» -
» -
>
S
S
S








>
» -
» -
» -
» -
>
S
S
S








>
» -
» -
» -
» -
>
S
S
S








$
$ -
$ -
$ -
$ -
$
S
S
S



Total Markup
Cost
Assambly)



$
$
$
$
$
$
S
S
S



Packaging
Assambly)



$
$
$
$
$
$
S
S
S



Componant/




$
$ 20.85
$ 64.04
$
$
$
S
S
S 7.10

S 198.14
                                     2-20

-------
                                                               Report FEV 07-069-303
                                                                    October 3, 2011
3   Glossary of Terms
Assembly: generally refers to a group of interdependent components joined together to
perform  a defined function (e.g.,  turbocharger  assembly,  high pressure fuel pump
assembly, high pressure fuel injector assembly).

Buy:  is the terminology used to identify those components or  assemblies as ones in
which a manufacturer would purchase versus manufacture.   All parts designated as a
"buy" part, within the analysis, only have a net component cost presented.  Typically
these  types of parts are considered commodity purchase parts  having industry established
pricing.

CBOM (Comparison Bill of Materials): is a system bill of materials, identifying all the
subsystems, assemblies,  and components associated with the technology configurations
under evaluation.   The CBOM records all the high level  details of the technology
configurations under study, identifies those items which have  cost  implications as a result
of the new versus base technology differences, documents the study assumptions, and is
the primary document for capturing input from the cross functional team.

Component: is the lowest level part within the cost analysis. An assembly is typically
made up  of several components acting together to perform a function (e.g., the turbine
wheel in  a turbocharger  assembly).  However,  in some cases  a  component can  act
independently performing a function within a sub-subsystem  or subsystem (e.g., exhaust
manifold within the exhaust subsystem).

Cost  Estimating  Models: are  cost estimating tools, external to  the Design Profit®
software, used to calculate operation and process parameters  for primary manufacturing
processes  (e.g.,  injection  molding, die casting,  metal  stamping,  forging).     Key
information calculated from the costing  estimating tools  (e.g., cycle times, raw material
usage, equipment size) is inputted into the Lean Design® process maps supporting the
cost analysis.  The Excel base cost estimating models are developed and validated by
Munro & Associates.

Costing Databases: refer to the five (5) core databases which contain all the cost rates
for the analysis.  The material database lists all the materials used throughout the analysis
along with the estimated price/pound for each.  The labor  database captures various
automotive, direct labor, manufacturing jobs  (supplier and OEM),  along  with the
associated mean hourly labor rates.  The manufacturing overhead rate database contains
the cost/hour for the various pieces of manufacturing equipment assumed in the analysis.
A mark-up database assigns a percentage of mark-up for each of the four (4) main mark-
up categories (i.e., end-item scrap,  SG&A, profit, and ED&T),  based on the industry,
supplier size, and complexity classification. The fifth database, the packaging database,
contains packaging options and costs for each case.
                                       3-21

-------
                                                              Report FEV 07-069-303
                                                                    October 3, 2011

Lean Design® (a module  within the Design  Profit® software): is used to create
detailed process flow charts/process maps. Lean Design® uses a series of standardized
symbols, each base symbol  representing a group of similar manufacturing  procedures
(e.g., fastening, material modifications, inspection).   For each group, a Lean Design®
library/database exists  containing  standardized  operations  along with the associated
manufacturing information and specifications for each operation.  The information and
specifications are used to generate a net operation cycle time.  Each operation  on  a
process flow chart is represented by a base symbol, operation description, and operation
time, all linked to  a Lean Design® library/database.

Make: is the terminology used to  identify those components or assemblies as ones in
which a manufacturer would produce internally versus purchase.  All parts designated as
a "make" part, within the analysis, are costed in full detail.

MAQS (Manufacturing  Assumption  and Quote  Summary) Worksheet:  is the
standardized template  used  in  the  analysis  to  calculate  the  mass  production
manufacturing cost,  including supplier mark-up,  for  each system,  subsystem and
assembly quoted in the analysis.  Every component and assembly costed in the analysis
will  have a MAQS  worksheet.  The worksheet is based on a standard OEM (original
equipment  manufacturer) quote sheet modified for improved costing transparency and
flexibility in sensitivity studies.  The main feeder documents to  the MAQS  worksheets
are process maps and the costing databases.

MCRs  (Material Cost Reductions): is a process  employed to  identify and capture
potential design  and/or manufacturing  optimization  ideas  with  the  hardware under
evaluation.  These savings could potentially  reduce  or  increase the differential costs
between the new  and  base technology configurations, depending on whether an MCR
idea  is for the new or the base technology.

Net  Component/Assembly Cost Impact to  OEM: is defined as the net manufacturing
cost  impact per unit, to the OEM, for a  defined component, assembly,  subsystem or
system.  For components produced by the  supplier base,  the net manufacturing cost
impact  to   the   OEM  includes  total   manufacturing   costs  (material,   labor,  and
manufacturing  overhead),   mark-up  (end-item   scrap   costs,  selling,  general  and
administrative costs, profit,  and engineering  design  and testing costs) and packaging
costs. For OEM internally manufactured components, the net manufacturing  cost impact
to the OEM includes total manufacturing costs and packaging costs; mark-up costs are
addressed through the application of an indirect cost multiplier.

NTAs  (New Technology  Advances):  is a process employed to  identify and capture
alternative advance technology ideas which could be substituted for some of the existing
hardware under evaluation.  These advanced technologies,  through improved function
                                      3-22

-------
                                                              Report FEV 07-069-303
                                                                    October 3, 2011

and performance, and/or cost reductions, could help increase the overall value of the
technology configuration.

Powertrain Package Proforma: is a summary worksheet comparing the key physical
and performance attributes of the technology under study with those of the corresponding
base configuration.

Process Maps:  are  detailed process  flow  charts used to capture the  operations and
processes,  and  associated key manufacturing variables, involved in manufacturing
products at any level (e.g., vehicle, system, subsystem, assembly, component).

P-VCSM  (Powertrain-Vehicle Class Summary Matrix): records the technologies
being evaluated, the applicable vehicle classes  for each technology, and key parameters
for vehicles or vehicle systems that have been  selected to represent the new technology
and baseline configurations in each vehicle class to be costed.

Quote:  refers to the analytical process of establishing a  cost for a component  or
assembly.

Sub-subsystem: refers  to a group of interdependent assemblies and/or components,
required to create a functioning sub-subsystem.  For example, the air induction subsystem
contains several sub-subsystems including the following: turbocharging, heat exchangers,
and pipes, hoses and ducting.

Subsystem: refers to a group of interdependent sub-subsystems,  assemblies  and/or
components, required to  create a functioning subsystem. For example, the engine system
contains several subsystems including the following: crank drive subsystem, cylinder
block subsystem, cylinder head subsystem, fuel induction subsystem, and air induction
subsystem.

Subsystem CMAT (Cost Model Analysis Templates): is the document used to display
and roll up all the sub-subsystem, assembly and component incremental costs associated
with a  subsystem (e.g.,  fuel  induction, air  induction,  exhaust),  as defined by the
Comparison Bill of Material (CBOM).

Surrogate part: refers to a part similar in fit, form and function as the part required for
the cost analysis. Surrogate parts are sometimes used in the cost analysis when actual
parts are unavailable.  The cost of a surrogate part is considered equivalent to the cost of
the actual part.

System: refers to a  group of interdependent  subsystems, sub-subsystems,  assemblies
and/or components, working together  to create a vehicle primary function (e.g., engine
system,  transmission  system, brake system, fuel system, suspension system).
                                      3-23

-------
                                                              Report FEV 07-069-303
                                                                    October 3, 2011

System CMAT (Cost Model Analysis Template): is the document used to display and
roll up all the subsystem  incremental  costs associated with a system (e.g., engine,
transmission, steering), as defined by the CBOMs.
                                      3-24

-------