Office of Solid Waste and                          USEPA-542-R-13-014
Emergency Response                            January 16, 2013
(5102G)                                     www. epa.gov/superfiind/cleanup/
                                          postconst ruction/optimize, htm
                                          www.clu-in.org/optimization
                   Optimization Review
 Ogallala Ground Water Contamination Superfund Site
           Operable Unit 2 (Tip Top Cleaners)

                    Ogallala,  Nebraska

-------
                  OPTIMIZATION REVIEW
OGALLALA GROUND WATER CONTAMINATION SUPERFUND SITE
                 OU 2 (Tip TOP CLEANERS)
                   OGALLALA, NEBRASKA
                   Report of the Optimization Review
  Site Visit Conducted at the Ogallala Ground Water Contamination Superfund Site, OU2, on
                         24 July 2012

                           Final
                       16 January 2013

-------
                               EXECUTIVE SUMMARY
USEPA's definition of optimization is as follows:

"Efforts at any phase of the removal or remedial response to identify and implement actions that improve
the action's effectiveness and cost-efficiency. Such actions may also improve the remedy's protectiveness
and long-term implementability which may facilitate progress towards site completion. To identify these
opportunities, regions may use a systematic site review by a team of independent technical experts, apply
techniques or principles from green remediation or Triad, or apply some other approach to identify
opportunities for greater efficiency and effectiveness.  Contractors, states, tribes, the public, andPRPs
are also encouraged to put forth opportunities for the Agency to consider. "

An optimization evaluation considers the following: goals of the remedy; available site data; the
conceptual site model (CSM); remedy performance; protectiveness; cost-effectiveness; and closure
strategy.  A strong interest in sustainability has  also developed in the private sector and within federal,
state, and municipal governments.  Consistent with this interest, optimization now routinely considers
green remediation and environmental footprint  reduction during optimization evaluations. An
optimization evaluation includes reviewing site documents, interviewing site stakeholders, potentially
visiting the site for one day, and compiling a report that includes recommendations in the following
categories:

   •  Protectiveness
   •  Cost-effectiveness
   •  Technical improvement
   •  Site closure
   •  Environmental footprint reduction

The recommendations are intended to help the site team identify opportunities for improvements in these
areas.  In many cases, further analysis  of a recommendation, beyond that provided in this report, may be
needed prior to implementation of the  recommendation. Note that the recommendations are based on an
independent evaluation, and represent the opinions of the evaluation team. These recommendations do
not constitute requirements for future action, but rather are provided for consideration by the Region and
other site stakeholders. Also note that while the recommendations may provide some details to consider
during implementation, the recommendations are not meant to replace other, more comprehensive,
planning documents such as work plans, sampling plans, and quality assurance project plans.

Site-Specific Background

The Ogallala Ground Water Contamination  Superfund site was identified in 1989 through municipal well
sampling. Tetrachloroethene (PCE), a solvent commonly used in dry cleaner operations, was the primary
ground water target chemical of concern (COC) that was identified for remediation purposes. A
comprehensive remedial investigation (RI) was conducted in 1995 and 1996. Additional investigations
were also conducted following completion of the RI to define the plume.

-------
Summary of Conceptual Site Model

The source of the tetrachloroethene (PCE) ground water plume is believed to be associated either with the
release of condensate or equipment leaks containing PCE from the Tip Top Cleaners indoor operations to
the surface/subsurface.  Residual PCE mass released to the subsurface appears to have been immobilized
within the vadose zone and at the capillary fringe above the water table in the immediate vicinity of the
release area at a maximum depth of approximately 16 feet below ground surface (ft bgs). It is surmised
that the released PCE was in relatively small quantities over an extended timeframe, so the total mass of
the PCE released was not at a level that resulted in the generation of pooled dense non-aqueous phase
liquids (DNAPL) layers or extensive vertical migration below the depth of the water table.  The plume
extended to the east-southeast by advection with the flow of the shallow aquifer ground water.  Soil
vapor extraction (SVE), and later soil excavation, has likely mitigated most of the long-term PCE mass
flux to the dissolved phase.

The site contamination is apparently restricted to the unconsolidated alluvial deposits.  These deposits are
largely sandy silt and clay from the surface to depths of 17 ft bgs near the Tip Top site. These fine-
grained materials overlie highly permeable shallow sands and gravelly sands comprising the shallow
aquifer. Ground water flow is to the east to east-southeast.  Ground water on the flow  paths emanating
from the site would appear to discharge to gravel pit lakes south of US Highway 30 or to the South Platte
River.  Based on historical water level measurements, the depth to groundwater fluctuates annually
between approximately 15 and 18 ft bgs.

The plume as depicted in the initial RI reports was quite narrow and at least a half-mile long. Ground
water contamination essentially is limited to PCE. PCE concentrations have been as high as 1,200
micrograms per liter (ug/L) in OU2-MW-2, and concentrations in the  100s of ug/L extended to OU2-
MW-7 in the early 2000s. Recent concentrations have diminished significantly, and detections of PCE
above its ground water remedial action objective (RAO) are limited to monitoring wells within 300 feet of
the source area along North Spruce Street.

Summary of Findings

In-situ chemical oxidation (ISCO) using sodium permanganate was conducted by the United States
Environmental Protection Agency (USEPA) following the issuance of the Record of Decision (ROD)
starting in September 2006 and continuing through the third quarter of 1 2011. ISCO injection events
were also performed prior to the issuance of the ROD as part of the interim response action and served as
an initial pilot/treatability study.  Injection of oxidant occurred at various locations within the plume, but
was primarily concentrated just downgradient of the source area. Building demolition and  soil excavation
was conducted in 2011 to remove remaining source area PCE mass that was contributing to long-term
groundwater mass flux. The ISCO injections were conducted more-or-less quarterly over five years.
Monitoring following treatment is to follow the injection period for another five years  or until the
groundwater RAOs are attained.

Based on a review of the information provided  to the optimization review team, the Site visit conducted
on July 24, 2012, and interviews with persons knowledgeable about the Site, the following are the key
findings from this optimization evaluation:

   •   The remedial strategy used for the site is sound.

   •   The primary data gap for the ground water plume is the full definition of the plume. Based on the
       recent PCE detection in the direct push sampling point along East G Street, it appears that the
       plume is not bounded on the downgradient end. The monitoring network is concentrated on the

-------
       previously observed plume axis, and does not include bounding wells to the north or south of the
       inferred plume. This plume delineation data gap primarily applies to the intermediate and deeper
       zones of the shallow aquifer unit between a depth of approximately 30 and 65 ft bgs. The
       existing monitoring network appears to have delineated the upper portion of the shallow aquifer
       unit to a depth of approximately 30 ft bgs. Monitoring wells MW-10 and MW-11 provide data
       concerning the north and south edges of the plume at locations near but downgradient of the
       source area.

    •  Another potential data gap is the remaining residual PCE mass within the source area shallow
       saturated zone following the soil excavation.  The possibility that more than a minimal level of
       residual mass still remains immobilized within the top of the source area saturated zone could
       result in observed rebound of groundwater concentrations following the completion of the ISCO
       injection events.

    •  The empirical approach that has been used to evaluate the effectiveness of the ISCO treatment
       suggests that permanganate has been distributed throughout the ground water plume, but it is
       difficult to determine the overall treatment level until rebound testing has been performed over a
       sufficient period of time. The ISCO design approach did not account for the natural soil oxidant
       demand or PCE mass that exists in the adsorbed phase or as residual mass remaining in the  source
       area shallow saturated zone. The transect injection approach relies on ground water advection to
       distribute the permanganate throughout the ground water plume to affect treatment.

    •  If the plume is found to exist outside the current network, or a rebound in PCE groundwater
       concentrations is observed following the completion of ISCO treatment, additional permanganate
       injections may be necessary to treat the remaining residual PCE mass, or the Agencies will  have
       to assess the ability of natural  processes (essentially sorption and dispersion) to prevent exposures
       and eventually attain the ground water RAOs.

Summary of Recommendations

Recommendations are provided to improve remedy effectiveness, reduce cost, provide technical
improvement, and assist with accelerating site closure. It should be noted that the Project Team has
elected to be proactive and already has plans to implement most of the recommendations outlined below
based on a review of a draft of this report. Plans, as communicated by the Project Team, to implement
specific recommendations are also described below.  Recommendations and planned response actions
associated with the above criteria are as follows:

    •  The current extent of the ground water plume needs to be more fully verified to assure that the
       very promising concentration  reductions have actually occurred throughout the plume.
       Monitoring points that bound the plume in the cross-gradient and downgradient directions are
       needed. Planned assessment activities communicated by the Project Team include vertical
       profiling and plume delineation in the area of monitoring well MW-8 using a combination of
       various direct-push techniques such as membrane interface probe ([MIP], soil gas measurements),
       electrical conductivity ([EC], mapping tool for soil types), hydraulic profiling tool (measure of
       formation permeability for preferential migration pathway identification), and soil/groundwater
       grab sampling.  The field data collection using these direct-push techniques will be used to
       identify locations for the installation of additional nested monitoring wells within the intermediate
       and deeper zones of the shallow aquifer unit.
                                               in

-------
•   It is also recommended, if logistically feasible, that soil and "grab" groundwater samples be
    collected in the source area as part of the upcoming planned source area monitoring well
    installation or any future Geoprobe site assessment sampling  to measure the level and extent of
    residual PCE mass still remaining. Upcoming planned source area assessment activities
    communicated by the Project Team include the following: 1)  use of MIP/EC to provide vertical
    profiling of PCE mass presence in the saturated zone; 2) installation of monitoring well nests
    (screened in both the shallow and intermediate zones of the shallow aquifer unit) based on the
    initial MIP/EC findings; and 3) collection of two saturated zone source area soil samples for
    analysis of volatile organic compounds (VOCs) and permanganate natural oxidant demand
    (PNOD) to evaluate residual source area PCE mass and provide a quantitative measurement of
    the PNOD for further evaluation of the ISCO design approach.  It should also be noted the
    installation of additional monitoring wells in the source area had been proposed by the project
    team prior to this optimization study.

•   The quarterly sampling at the site should be continued for no  more than another few quarters, and
    then semi-annual sampling could be conducted. This represents a cost reduction of
    approximately $36,000 per year or a total of $108,000 (6 times $18,000 per round).  The Project
    Team has communicated its intent to modify the future ground water sampling frequency to a
    semi-annual basis.

•   Future sampling for downgradient wells could be conducted solely for volatile organic
    compounds (VOCs) by passive diffusion bags (PDBs). The Project Team has communicated its
    intent to modify future ground water sampling events for the downgradient wells to include only
    VOCs using PDBs.

•   If a rebound in the PCE ground water concentrations is observed,  an additional  injection event of
    permanganate that includes locations both upgradient (northwest) of the excavation area and
    directly within the source area is recommended. The permanganate dosage should be increased
    to allow injection of adequate oxidant to treat the remaining residual PCE mass and account for
    the demands from any natural organic matter in the soil and aquifer matrix.  The Project Team
    will evaluate PCE rebound during  the future semi-annual ground water sampling events.  If
    needed, additional injections of permanganate will be considered based the observed rebound
    levels.  The scope of any future permanganate treatment events would consider injections both
    upgradient to the northwest of the  source area and within the source area, with the injection
    volumes and dosages based on using the results of the PNOD tests, groundwater analyses, and
    soil analyses to determine the total PCE mass  and corresponding oxidant demand.
                                           IV

-------
                                       NOTICE
Work described herein was performed by the US Army Corps of Engineers (USAGE) Environmental and
Munitions Center of Expertise (EM CX) for the U.S. Environmental Protection Agency (USEPA). Work
conducted by USAGE EM CX, including preparation of this report, was performed under Interagency
Agreement DW96921926. Mention of trade names or commercial products does not constitute
endorsement or recommendation for use.

-------
                                       PREFACE
This report was prepared as part of a national strategy to expand Superfund optimization practices from
site assessment to site completion (the Strategy) implemented by the United States Environmental
Protection Agency (USEPA) Office of Superfund Remediation and Technology Innovation (OSRTI). The
project contacts are as follows:
Organization
USEPA Office of Superfund
Remediation and Technology
Innovation
(OSRTI)
US Army Corps of Engineers,
Environmental & Munitions
Center of Expertise
(Contractor to USEPA)
Key Contact
Jennifer Edwards
Dave Becker
Contact Information
US USEPA Headquarters, 1200
Pennsylvania Ave, NW, Mail Code 5204P,
Washington DC 20460
Edwards.Jennifer(S),epamail.epa.aov
703-603-8762
1600 Capitol Ave., Suite 9200, Omaha, NE
68102-9200
Dave.J.Becker(g),usace.army.mil
402-697-2655
                                            VI

-------
                               LIST OF ACRONYMS
bgs
CERCLA
cm/sec
coc
CSM
DCE
DNAPL
FS
g/kg
ISCO
kg/cu m
Ibs
LTM
MCL
mg/kg
mg/L
NPL
OSRTI
OU
PCE
PDB
PRP
P&T
QAPP
RAO
RI
ROD
RSE
SDWA
sqft
sq m
SVE
TCE
ug/kg
ug/L
VC
voc
USAGE
USEPA
below ground surface
Comprehensive Environmental Response, Compensation, and Liability Act
centimeter per second
chemical of concern
conceptual site model
1,2-cis-dichloroethene
dense, non-aqueous liquid
Feasibility Study
grams per kilogram
in-situ chemical oxidation
kilograms per cubic meter
pounds
long-term monitoring
maximum contaminant level
milligrams per kilogram
milligrams per liter
National Priorities List
Office of Superfund Remediation and Technology Innovation
operable unit
tetrachloroethene
passive diffusion bag
Potentially Responsible Party
pump and treat
Quality Assurance Project Plan
remedial action objective
remedial investigation
Record of Decision
Remediation System Evaluation
Safe Drinking Water Act
square feet
square meters
soil vapor extraction
trichloroethene
micrograms per kilogram
micrograms per liter
vinyl chloride
volatile organic compound
United States Army Corps of Engineers
United States Environmental Protection Agency
                                           vn

-------
                           TABLE OF CONTENTS
EXECUTIVE SUMMARY	i

NOTICE	v

PREFACE	vi

LIST OF ACRONYMS	vii

1.0    INTRODUCTION	1
      1.1    PURPOSE	1
      1.2    TEAM COMPOSITION	2
      1.3    DOCUMENTS REVIEWED	2
      1.4    QUALITY ASSURANCE	3
      1.5    PERSONS CONTACTED	3

2.0    SITE BACKGROUND	4

      2.1    LOCATION	4
      2.2    SITE HISTORY	4
            2.2.1   HISTORIC LAND USE AND OPERATIONS	4
            2.2.2   CHRONOLOGY OF ENFORCEMENT AND REMEDIAL ACTIVITIES	4
      2.3    POTENTIAL HUMAN AND ECOLOGICAL RECEPTORS	5
      2.4    EXISTING DATA AND INFORMATION	5
            2.4.1   SOURCES OF CONTAMINATION	5
            2.4.2   GEOLOGY SETTING AND HYDROGEOLOGY	6
            2.4.3   SOIL CONTAMINATION	6
            2.4.4   SOIL VAPOR CONTAMINATION	6
            2.4.5   GROUND WATER CONTAMINATION	6
            2.4.6   SURFACE WATER CONTAMINATION	7
            2.4.7   SEDIMENTS	7

3.0    DESCRIPTION OF PLANNED OR EXISTING REMEDIES	8
      3.1    REMEDY AND REMEDY COMPONENTS	8
      3.2    REMEDIAL ACTION OBJECTIVES AND STANDARDS	10
      3.3    PERFORMANCE MONITORING PROGRAMS	10

4.0    CONCEPTUAL SITE MODEL	12
      4.1    CSM OVERVIEW	12
      4.2    CSM DETAILS AND EXPLANATION	12
      4.3    DATA GAPS	13
      4.4    IMPLICATIONS FOR REMEDIAL STRATEGY	13

5.0    FINDINGS	14
      5.1    GENERAL FINDINGS	14
      5.2    SUBSURFACE PERFORMANCE AND RESPONSE	14
      5.3    COMPONENT PERFORMANCE	15
      5.4    REGULATORY COMPLIANCE	17
      5.5    COMPONENTS OR PROCESSES THAT ACCOUNT FOR MAJORITY OF ANNUAL COSTS	17

6.0    RECOMMENDATIONS	18
                                      Vlll

-------
       6.1    RECOMMENDATIONS TO IMPROVE EFFECTIVENESS	18
             6.1.1   PLUME VERIFICATION AND DEFINITION	18
             6.1.2   ADDITIONAL MONITORING WELLS	19
             6.1.3   VAPOR INTRUSION ISSUE	20
       6.2    RECOMMENDATIONS TO REDUCE COSTS	20
       6.3    RECOMMENDATIONS FOR TECHNICAL IMPROVEMENT	21
             6.3.1   SAMPLING METHOD SIMPLIFICATION	21
             6.3.2   VERIFICATION OF MONITORING WELL REFERENCE POINT ELEVATIONS	21
       6.4    CONSIDERATIONS FOR GAINING SITE CLOSE OUT	21
       6.5    RECOMMENDATIONS RELATED TO ENVIRONMENTAL FOOTPRINT REDUCTION	22
       6.6    SUGGESTED APPROACH TO IMPLEMENTING RECOMMENDATIONS	23

List of Tables

Table 1.  Optimization Team Composition
Table 2.  Persons Contacted during Optimization Evaluation
Table 3.  In-situ Chemical Oxidation Activities at the Tip Top Cleaners Site
Table 4.  Clean-up goals (Maximum Contaminant Levels) for Site Contaminants
Table 5.  Summary of Recommendations
Figure 1. Site Location and April 2012 PCE Plume
Figure 2. PCE Concentration Trends for Monitoring Wells along Plume Axis
Figure 3. Sample Natural Oxidant Demand for Soils, Geosyntec Consultants, 2011
Attachments

Attachment A: Cost Estimate Back-up Assumptions and Table for Additional Sampling
Attachment B: Site Wise Results for Environmental Footprint Reduction for Sampling Program Change

-------
                                1.0    INTRODUCTION
1.1     PURPOSE

During fiscal years 2000 and 2001, independent Remediation System Evaluations (RSEs) were conducted
at 20 operating pump and treat (P&T) sites (i.e., those sites with P&T systems funded and managed under
Superfund by the United States Environmental Protection Agency (USEPA), other federal agencies, and
by the States).  Due to the opportunities for system optimization that arose from those RSEs, USEPA
Office of Superfund Remediation and Technology Innovation (OSRTI) has incorporated RSEs into a
larger post-construction complete strategy for Fund-lead remedies as documented in OSWER Directive
No. 9283.1-25, Action Plan for Ground Water Remedy Optimization. Concurrently, USEPA developed
and applied the Triad Approach to optimize site characterization strategies, methods and technologies,
including the increased use of conceptual site models (CSMs) as the basis for identifying project data
gaps, and using those gaps to guide the development of site characterization objectives and work plans.
USEPA has since expanded the reach of optimization to encompass reviews at the investigation stage of
projects (such as for the BBM Site). USEPA's definition of optimization is as follows:

"Efforts at any phase of the removal or remedial response to identify and implement actions that improve
the action's effectiveness and cost-efficiency. Such actions may also improve the remedy's protectiveness
and long-term implementability which may facilitate progress towards site completion To identify these
opportunities, regions may use a systematic site review by a team of independent technical experts, apply
techniques or principles from green remediation or Triad, or apply some other approach to identify
opportunities for greater efficiency and effectiveness. Contractors, states, tribes, the public, and
Potentially Responsible Parties (PRPs) are also encouraged to put forth opportunities for the Agency to
consider."

The Strategy also encourages other activities designed to facilitate better site characterization, remedy
selection, and design and construction by applying various techniques and optimization lessons learned to
improve a given project's scope, schedule and cost.

As stated in the definition, optimization refers to a "systematic site review", indicating that the site as a
whole is often considered in the review.  Optimization can be applied to a specific aspect of the remedy
(e.g., focus on long-term monitoring [LTM] optimization or focus on one particular operable unit [OU]),
but other site or remedy components are still considered to the degree that they affect the focus of the
optimization. An optimization evaluation considers the goals of the remedy, available site data, CSM,
remedy performance, protectiveness, cost-effectiveness, and closure strategy. A strong interest in
sustainability has also developed in the private sector and within federal, state, and municipal
governments. Consistent with this interest, OSRTI  has developed a Green Remediation Primer
(http://cluin.org/greenremediation/), and now routinely considers green remediation and environmental
footprint reduction during optimization evaluations. The evaluation includes reviewing site documents,
potentially visiting the site for one day, and compiling a report that includes recommendations in the
following categories:

-------
    •   Protectiveness
    •   Cost-effectiveness
    •   Technical improvement
    •   Site closure
    •   Environmental footprint reduction

The recommendations are intended to help the site team identify opportunities for improvements in these
areas. In many cases, further analysis of a recommendation, beyond that provided in this report, may be
needed prior to implementation of the recommendation. Note that the recommendations are based on an
independent evaluation, and represent the opinions of the evaluation team.  These recommendations do
not constitute requirements for future action, but rather are provided for consideration by the Region and
other site stakeholders. Also note that while the recommendations may provide some details to consider
during implementation, the recommendations are not meant to replace other, more comprehensive,
planning documents such as work plans, sampling plans, and quality assurance project plans.

The national optimization strategy includes a system for tracking consideration and implementation of the
optimization recommendations and includes a provision for follow-up technical assistance from the
optimization team as mutually agreed upon by the site management team and USEPA OSRTI.

1.2     TEAM COMPOSITION

The optimization team consisted of the following individuals:
Table 1.
Name
Jennifer Edwards
Dave Becker
Mark Rothas
Affiliation
US USEPA OSRTI
USAGE EM CX
USAGE EM CX
Phone
703-603-8762
402-697-2655
402-697-2580
Email
Edwards.Jennifer@epa.gov
Dave.J.Becker@usace.army.mil

1.3     DOCUMENTS REVIEWED

The following documents were reviewed. The reader is directed to these documents for additional site
information that is not provided in this report.
   •   Removal Action Report, OU 2, TetraTech, October, 2011
   •   Feasibility Study Report Addendum, Black & Veatch, October, 2005
   •   Remedial Investigation Report, Addendum No. 1, Tip Top Cleaners OU2, Black & Veatch,
       August, 2004
   •   Record of Decision, OU 2, February, 2006
   •   Long-Term Remedial Action Source Area Evaluation Report, OU 2, Black & Veatch, February,
       2009
   •   LTRA Quarterly Cleanup Status Reports Nos. 3 (2 Figures only, 2007), 5 (November 2007), 13
       (December 2009), 23 (June 2012), Black &Veatch
   •   Injection Reports, April 2007- April 2011, GSI, various.

   •   Ogallala Water Supply Remedial Investigation Report, Fluor Daniel Environmental Services,
       October 1996

-------
    •   OU2 Site Management Plan, GSI, August 2006

    •   Tip Top Cleaners OU2 Post-Action Plan, Black & Veatch, September 2006

    •   Draft Remedial Action Basis of Design Report, Black & Veatch, April 2006

    •   First Five-Year Review Report, USAGE Kansas City District for US USEPA, September 2011

    •   Work Completion Report for Direct-Push Technology Well Construction and ISCO Treatment,
       Environmental Restoration, Phases II (April 2003) and III (October 2003)

1.4    QUALITY ASSURANCE

This optimization evaluation utilizes existing environmental data to interpret the conceptual site model,
evaluate remedy performance, and make recommendations to improve the remedy. The quality of the
existing hydrogeologic and chemical data is evaluated by the optimization team prior to using the data for
these purposes. The evaluation for data quality includes a brief review of how the data were collected and
managed (where practical, the site Quality Assurance Project Plan [QAPP] is considered), the consistency
of the data with other site data, and the use of the data in the optimization evaluation. Data that are of
suspect quality are either not used as part of the optimization evaluation or are used with the quality
concerns noted.  Where appropriate, this report provides recommendations made to improve data quality.

1.5    PERSONS CONTACTED

The following individuals associated with the site were present for the visit:
Table 2.
Name
Bill Gresham
John Flint
Gary Felkner
Curt McCoy
Affiliation
US USEPA, Region 7
Remedial Project Manager
Nebraska Department of
Environmental Quality
Black & Veatch, Site
Manager
Black & Veatch
Phone
913-551-7804
308-632-0544


Email Address
Gresham .Bill@epamail .epa.gov
john.flint@nebraska.gov



-------
                            2.0    SITE BACKGROUND
2.1     LOCATION

The Ogallala Ground Water Contamination Superfund Site, Tip Top Cleaners OU2, is located at 116
West 5th Street in the central part of Ogallala, Nebraska.  Ogallala is in the west-central portion of
Nebraska, just north of the South Platte River and west of the confluence of the North Platte and South
Platte Rivers.  See Figure 1 for the site location.

2.2     SITE HISTORY

2.2.1        HISTORIC LAND USE AND OPERATIONS

The Tip Top Cleaners site was a dry cleaning establishment located in a neighborhood of mixed
residential and commercial land use.  The dry cleaner was in operation until the 1990s. The building was
used primarily for storage, or was unused for a period of time until April 2011 when the structure was
demolished to allow excavation of remaining contaminated soil at the site. The site is now a concrete-
paved parking area. No change in land use is anticipated.

The ground water contaminant plume extends from the former dry cleaner east-southeast through the
central portion of Ogallala in an area of residential and commercial land use. The plume may extend
south of US Highway 30 into an area of sand and gravel mining.  One residential well located
approximately 1,600 feet downgradient of the site was identified. This well became inoperable in the
mid-2000s and has been properly abandoned.

2.2.2        CHRONOLOGY OF ENFORCEMENT AND REMEDIAL ACTIVITIES

The Ogallala Ground Water Contamination Superfund site was identified in 1989 through municipal well
sampling. Tetrachloroethene (PCE), a solvent commonly used in dry cleaner operations, was the primary
ground water target chemical of concern (COC) that was identified for remediation purposes. Two main
ground water plumes were identified during investigations by Nebraska Department of Environmental
Quality (NDEQ) and USEPA. A southern plume and its sources are addressed under Operable Unit
(OU) 1.  The northern plume originating at Tip Top cleaners was identified by NDEQ in the early 1990s
and is addressed as OU2. A comprehensive remedial investigation (RI) was conducted in 1995 and 1996,
including the OU2 area.  A comprehensive feasibility study (FS) was published in 1997. Additional
investigations, including direct-push ground water sampling, were conducted by NDEQ in 2000 to define
the plume.

USEPA conducted a ground water treatability study for OU2 in 2001 and early 2002 using sodium
permanganate. The study showed promise for the technology.  USEPA  also implemented source control
at the Tip Top Cleaners site by installation of a soil vapor extraction (SVE) system south of the cleaners.
The system ran from February to October 2002.

USEPA conducted additional characterization (including direct-push sampling) and monitoring activities
for ground water through 2004. During the period February 2003 through March 2004, USEPA
conducted injection of permanganate into the ground water plume, primarily in the upgradient half of the

-------
plume. Addendum 1 to the RI Report was published in August 2004.  An addendum to the FS was
published in October 2005. A Record of Decision (ROD) for OU2 was issued in February 2006.

In-situ chemical oxidation (ISCO) using sodium permanganate was conducted by USEPA following the
issuance of the ROD from 2007 until 2011. Injection of oxidant occurred at various locations within the
contaminant plume, but were primarily concentrated just downgradient of the source area.

Additional characterization of the source area was conducted by USEPA in 2008. The work included
direct-push soil sampling and ground water sampling. Based on this work, additional source removal was
planned. Building demolition and soil excavation was conducted by USEPA in 2011.  Soil was excavated
to depths as great as 16 ft bgs on the Tip Top property and portions of adjacent parcels. Excavation was
limited by West 5th Street and to some extent by nearby occupied buildings. At least two additional
monitoring wells, OU2-MW-10 and OU2-MW-11, were installed at some time following the RI
addendum.

Also in 2011, USEPA Region 7 prepared a five-year review for both OU1 and OU2. The primary issue
raised for OU2 was the potential for vapor intrusion in buildings directly over the plume. Limited indoor
air quality testing was conducted during the remedial investigation for OU2 in 2004 and consisted of
Summa canisters placed in the basement of four homes in the OU2 study area. Based on that sampling,
USEPA determined that the risks posed were in the acceptable range.

2.3     POTENTIAL  HUMAN AND ECOLOGICAL RECEPTORS

The contamination in OU1 and OU2 originally threatened both municipal and  domestic wells.  The City
of Ogallala relocated its well field to a location northeast of the city in the early 1990s, and terminated use
of the previously impacted wells. The residential well in the OU2 plume (OU2-Res Well 4 on maps) was
rendered inoperable and properly abandoned in the mid-2000s.

During the RI phase, the OU2 plume was identified as a possible source of impact to the surface water
quality in Gravel Pit Lake south of US Highway 30.  Gravel Pit Lake is potentially in the apparent
migration path of the shallow OU1 plume, and represents another possible exposure point.  The OU2
plume has not impacted the Gravel Pit Lake as indicated by the absence of any OU2 plume constituents in
the surface water samples that have been collected to date. .  No apparent ecological impacts can be
directly related to OU2.

Currently, the only potentially complete pathway may be via indoor air in buildings overlying the plume,
but past sampling has not indicated an unacceptable risk. The USEPA is considering the
recommendations for additional characterization of indoor air impacts in the 2011 five-year review report.

2.4     EXISTING DATA AND INFORMATION

2.4.1       SOURCES OF CONTAMINATION

The source of the PCE contamination was the operation of Tip Top Cleaners.  The exact nature of the
releases is not clear, but  seemed to have been concentrated immediately south  and southeast of the Tip
Top building.  There did not appear to be a relationship between the site contamination and utility
corridors. It appears that the 2011 excavation has removed the bulk of the remaining source mass.

-------
2.4.2       GEOLOGY SETTING AND HYDROGEOLOGY

Ogallala is located in the valley of the South Platte River and is underlain by unconsolidated alluvium
(sediments deposited by streams) related to migration of the South Platte River across its floodplain. This
alluvium overlies poorly consolidated to cemented sediments of the Ogallala Formation. The Ogallala
Formation is Miocene in age and consists of interbedded sand, gravel, silt, and clay largely deposited by
ancestral rivers pre-dating the South Platte. The alluvium and Ogallala Formation, as well as deeper
Tertiary-aged units, comprise the High Plains aquifer system in western Nebraska.

The site contamination is apparently restricted to the unconsolidated alluvial deposits. These deposits are
largely sandy silt and clay from the surface to depths of 17 feet below ground surface (bgs) near the Tip
Top site, but only extend to depths less than 5 ft bgs near the downgradient end of the plume. These fine-
grained materials overlie highly permeable shallow sands and gravelly sands comprising the shallow
aquifer. These sands and gravelly sands have varying amounts of clay and silt and extend to depths of 40
to 50 ft bgs.  The uppermost subunit of the Ogallala Formation at the site is the Ash Hollow Member.
The Ash Hollow is primarily clay and forms a reasonably effective aquitard preventing migration of site
contamination into the more permeable units within the Ogallala Formation. Note that the deeper
portions of the Ogallala Formation to the south have been impacted by COCs originating from OU1.

Ground water is encountered in the sands and gravelly sands, and piezometric heads are slightly above the
contact with the overlying clayey and silty materials, making the shallow aquifer locally confined.
Farther downgradient, the water table occurs in the sands and the  aquifer is unconfmed.  Ground water
flow is to the east to east-southeast as indicated in past reports at the site.  Ground water on the flow paths
emanating from the site would appear to discharge to gravel pit lakes south of US Highway 30 or to the
South Platte River.  Gradients in the shallow aquifer are typically near 0.0015.  Hydraulic conductivities
were estimated in the remedial investigations to be approximately 0.004 centimeters per second (cm/sec)
to 0.3 cm/sec and averaged 0.04 cm/sec. These are typical of sands and gravelly sand.  There is a very
slight downward hydraulic gradient. Variations in the water table elevation are small (a few feet, based
on recent data).

2.4.3       SOIL CONTAMINATION

Soil contamination was delineated at the Tip Top Cleaners site. Concentrations of PCE observed in soil
during the Source Area Evaluation were as high as 45,000 micrograms per kilogram (ug/kg) in shallow
soil under the southern portion of the building  slab. PCE concentrations were typically hundreds of ug/kg
in soils at depth outside the building. Confirmatory soil samples taken at the completion of source
excavation were generally below 100 ug/kg (and all were below a stated soil remediation goal of
550 ug/kg). The soil excavation essentially went to the water table or the top of the aquifer.

2.4.4       SOIL VAPOR CONTAMINATION

Soil vapor concentration data were not available.

2.4.5       GROUND WATER CONTAMINATION

Figure 1 shows the most recent ground water contaminant plume  (April 2012).  Ground water
contamination is essentially limited to PCE. Limited detections of TCE have been observed, generally
below the MCL of 5 micrograms per liter (ug/L).  PCE concentrations have been as high as  1,200 ug/L in
OU2-MW-2, and concentrations in the 100s of ug/L extended to OU2-MW-7 in the early 2000s.
Concentrations had exceeded the 5 ug/L PCE clean-up level in

-------
OU2-MW-8, the farthest downgradient well directly along the axis of the OU2 plume.  Recent
concentrations have diminished significantly, and detections of PCE above its clean-up level are limited
to monitoring wells within 300 feet of the source area along North Spruce Street. Concentrations in other
monitoring wells have largely declined to non-detectible levels as of April 2012.

The plume as depicted in reports is quite narrow and at least a half-mile long. Based on profiling done
using passive-diffusion bag (PDB) samples in shallow monitoring wells, the concentrations are well
distributed in the upper part of the shallow aquifer.  Monitoring wells OU2-MW-11 and OU-2-MW-10
are deeper, and PDB profiling in the screened interval in OU2-MW-10 also suggests the groundwater
plume is limited to the upper part of the shallow aquifer, at least in the upgradient portion of the plume.

A recent (within the past year) direct-push sampling location just north of OU2-MW-8 at the inferred
downstream end of the OU2 plume had PCE detections greater than 30 ug/L.

2.4.6        SURFACE WATER CONTAMINATION

Although sampling is conducted as part of OU2 at the Gravel Pit Lake south of US Highway 30, and
contaminants have been previously detected in the lake, no PCE has been detected there.  The OU2 plume
has not impacted Gravel Pit Lake as indicated by the absence of OU2 plume constituents in the surface
water of the Gravel Pit Lake.  Past detected contaminants in surface water samples (TCE, DCE, and VC)
are more similar to those found in the OU1  plume, though these could possibly be reductive
dechlorination daughter products of PCE. The sampling of the lake for the purposes of the OU2 remedy
could be discontinued, though continued sampling for the purposes of the OU1 remedy would likely be
required.  Since the analysis of the samples for OU1 purposes would likely include quantification of the
normal EPA SW846 method 8260B list, including PCE, the results of sampling of the lake for OU1
purposes should be shared with the OU2 project team.  .

2.4.7        SEDIMENTS

No sediment contamination related to OU2 has been identified.

-------
    3.0    DESCRIPTION OF PLANNED OR EXISTING REMEDIES


3.1    REMEDY AND REMEDY COMPONENTS

According to the OU2 ROD, the selected remedy included the following components:

           Treatment of ground water through ISCO using sodium permanganate
           Continued monitoring of the ground water quality
           Limiting access to ground water through enforcement of the City of Ogallala ordinance
           prohibiting the use of ground water for domestic use in the city limits
           Conducting a comprehensive survey of residential well use.
           Implement whole-house treatment for any residential wells in use.
           Installing additional monitoring wells

The ISCO injections were conducted quarterly over five years beginning in September 2006.  Monitoring
following treatment is to follow the injection period for another five years or until clean-up levels are
attained.

The City of Ogallala does have an ordinance in place that precludes the use of ground water for domestic
use within the city limits. It is presumed that all potentially impacted domestic wells have been identified
and only one, residential well 4, was in the path of the OU2 plume.  Additional monitoring wells have
been installed since the ROD, and recently additional wells have been proposed for the former Tip Top
Cleaners source area itself.

Table 1 summarizes the ISCO injections that were done following the issuance of the ROD. Additional
injections were also done prior to the ROD but the locations were not certain. No further ISCO injections
are planned pending evaluation of the ongoing monitoring results and rebound testing.

-------
Table 3. In-situ Chemical Oxidation Activities at the Tip Top Cleaners Site
Date
December 2001
Treatability Study
January 2003 l thru
August 2005 (10
events)
September/December
20062
March/June 2007
September/December
2007
March/June 2008
September/December
2008
March/June 2009
September/December
2009
March/June 20 10
September 20 10
December 20 10
March/June 20 11
Total Injection
Volume
Gallons of
40%
Permanganate
Injected
10
1,373
(minimum)
384
384
262
262
186
192
192
192
96
121
242
3,896
Area 1
Area 2
Area 3
Areas 4&5
Area 6&7
12 injection pts, locations uncertain
None
6 pts, 17-26'
SEof
cleaner
building
6 pts, 17-26'
SEof
cleaner
building
33 pts, W,E,
N, SE of
building
27 pts, W,E,
N, SE
14 pts, E
only
14 pts, E
only
14 pts, E,
SE
14 pts, E,
SE
14 pts, E,
SE
10 pts, N,
NW,E
10 pts, N,
NW,E
2 19 pts,
mostly
downgradie
ntof
cleaners
10 pts, 16-
31' for
some
rounds and
none in
other
rounds
12 pts, 16-
25' both
sides of
street
12 pts, 16-
25' both
sides of
street.
12 pts
12 pts
12 pts
12 pts
12 pts, W
side of
street only
12 pts
12 pts
24 pts
24 pts
231 pts
10 pts,
15-30'
5 pts, 16-
25'
5 pts, 16-
25'
None
6 pts
6 pts
6 pts
6 pts
6 pts
6 pts
6 pts
6 pts
113 pts
12 pts 13-28'
in Area 4
12 pts 12-27'
in Area 5
6 pts 12-39'
in Area 4, 5
pts 11 -37 'in
Area 5
6 pts 12-39'
in Area 4, 5
pts 11 -37 'in
Area 5
None
None
None
None
None
None
None
None
None
36 pts in Area
4 and
33 pts in Area
5
9 pts, on East
CSt, 11-26'
upgradient of
these Areas
for some
rounds or
none for other
rounds
5 pts 11-20'
in Area 6, 6
pts 11 -20 'in
Area 7
5 pts 11-20'
in Area 6, 6
pts 11 -20 'in
Area 7
None
None
None
None
None
None
None
None
None
20 pts near
Area 6
7 pts in Area
7
'Each injection was
2Each injection was
10 gal of 5% permanganate solution per 3 feet
10 gal of 5% permanganate solution per 3 feet

-------
3.2     REMEDIAL ACTION OBJECTIVES AND STANDARDS

The ROD for OU2 identified the following RAOs:

           Prevent ingestion of ground water containing site contaminants in excess of current
           regulatory standards
           Prevent degradation of surface water by ground water in excess of Nebraska Surface Water
           Criteria for PCE
           Restore the aquifer to MCLs within a reasonable timeframe (i.e.,  20 years)
           Prevent further contaminant migration in ground water

The clean-up goals (MCLs) for the site contaminants are summarized in Table 4.

Table 4. Clean-up goals (Maximum Contaminant Levels [MCLs]) for Site Contaminants.
Contaminant of Concern
Carbon tetrachloride
1 , 1 -Dichloroethylene
Cis-l,2-Dichloroethylene
Tetrachloroethylene
Trichloroethylene
Vinyl Chloride
MCL (ug/L)
5
7
70
5
5
2
3.3     PERFORMANCE MONITORING PROGRAMS

The monitoring network at the Tip Top Cleaners OU2 site involves 18 permanent monitoring wells that
have essentially been sampled quarterly since the initiation of permanganate injections. All but one of
these wells are screened in the shallow alluvial aquifer. Two locations (OU2-MW-5/5B and OU2-MW-
7/7B) have paired wells, one screened over 10 feet in the upper portion of the shallow aquifer, and the
other (with a "B" designation) screened over 20 feet in the deeper portion of the shallow aquifer. Two of
the newest wells, OU2-MW-10 and -11, have longer screens (30 feet) that span much of the shallow
aquifer. One well, RW1, was installed for other purposes at the City's maintenance yard.  Sampling of a
former residential well (designated "Res Well 4" in tables in the  Cleanup Status Report) occurred until
October 2007, after which the well was found inoperable or abandoned.

The monitoring well locations have generally been located based on past direct-push sampling or the
observations from existing monitoring wells. As a result, most of the monitoring wells for OU2 are
located along the initially observed axis of the PCE plume. The closest permanent monitoring wells to the
former Tip Top Cleaners building were located on the west side of Spruce Avenue, perhaps 100 feet
downgradient of the site. Recent reports from Black and Veatch have proposed additional monitoring
points at the Tip Top site itself.

Analysis of ground water has included volatile organic compounds (VOCs) for all rounds, and for metals
and geochemical parameters for selected rounds, most recently in August 2011. Field measurements are
made for oxidation-reduction potential, pH, temperature, specific conductance, and dissolved oxygen,
based on the observations made during the site visit.  Permanganate is qualitatively assessed based on the
intensity of the purple/pink color of samples. Color intensity is matched to a table of standard colors and
a number between 0-10 is assigned (though this scale was not consistently used - early in the program, a
scale of 0-3 was used).
                                             10

-------
Water level measurements are also made at the time of the quarterly sampling events. Reports of the
results include water levels data from a few monitoring points from the northeast edge of the OU1 study
area. These include USEPA-9A and USEPA-11A.  Surface water elevations are measured in Gravel Pit
Lake at point SW-1.
                                              11

-------
                       4.0   CONCEPTUAL SITE MODEL
This section discusses the optimization team's interpretation of existing characterization and remedy
operation data to explain how historic events and site characteristics have led to current conditions. This
CSM may differ from that described in other site documents.

4.1     CSM OVERVIEW

The site is conceptually simple as the vadose zone source has largely been removed and the ground water
plume is limited to the shallow sand and gravel aquifer. Remedial actions have removed a substantial
amount of the mass that had been released.

4.2     CSM DETAILS AND EXPLANATION

The source of the PCE ground water plume is believed to be associated either with the release of
condensate or equipment leaks containing PCE from the indoor dry cleaner operations to the
surface/subsurface. The historical soil and ground water sampling data would indicate that it is very
unlikely that there is any pooled accumulation zones/layers of dense, non-aqueous phase  liquid (DNAPL)
at the site. Residual PCE mass released to the subsurface appears to have been immobilized within the
vadose zone and at the capillary fringe above the water table in the immediate vicinity of the release area
at a maximum depth of approximately 16 ft bgs.  The immobilized PCE mass then served as the source of
the mass flux to ground water via dissolution into surface infiltration and ground water flow. It is
surmised that the released PCE was in relatively small  quantities  over an extended timeframe, so the total
mass of the PCE released was not at a level that resulted in the generation of pooled DNAPL layers or
extensive vertical migration below the depth of the water table (i.e., PCE mass not large enough to
overcome the  capillary pore pressures that would have  displaced  water from the soil pore structure to
allow for continued downward vertical migration).

The plume extended to the east-southeast with the flow of the shallow aquifer ground water.  SVE, and
later soil excavation, has likely mitigated most of the long-term PCE mass flux to the  dissolved phase.
The downgradient end of the plume probably  underlies areas of industrial land use and the South Platte
River floodplain. There is little to no natural biodegradation of dissolved phase PCE occurring at the site.
Available dissolved oxygen and oxidation-reduction potential data that was reviewed  suggests  that the
shallow aquifer conditions are predominantly  aerobic, whereas PCE preferentially biodegrades under
anaerobic conditions. The plume may be or have been subtly influenced by other stresses on the aquifer,
including production, domestic, and remediation wells. These may include the City of Ogallala municipal
wells, Residential Well 4 or other domestic wells, RW1 at the City Maintenance Yard, or OU1 activities.

Permanganate injections have introduced oxidant that has reacted with both the residual and dissolved
phase PCE mass and natural organic matter in the soil.  The permanganate reactions have been
concentrated in the area just downgradient of the source, as that is where the bulk of the injections have
occurred.
                                              12

-------
4.3     DATA GAPS

The primary data gap for the ground water plume is the full definition of the plume. The monitoring
network is concentrated on the previously observed plume axis, and does not include bounding wells to
the north or south of the inferred plume.  Based on the recent PCE detection in the direct push sampling
point along East G Street, it appears that the plume is not bounded on the downgradient end.  There is no
upgradient/background well near the source.  This plume delineation data gap primarily applies to the
intermediate and deeper zones of the shallow aquifer unit between a depth of approximately 30 and 65 ft
bgs.  The existing monitoring network appears to have delineated the upper portion of the shallow aquifer
unit to a depth of approximately 30 ft bgs. Monitoring wells MW-10 and MW-11 provide data
concerning the north and south edges of the plume at locations near and downgradient of the  source area.

Other possible data gaps involve the direction of ground water flow and the natural oxidant demand.  The
ground water flow directions are difficult to fully discern based on the wells, including EPA-7. Flow
could be due east or even locally southeast.  The survey datum for top-of-casing of monitoring well
EPA-MW7 is suspect, and will be re-established at the earliest cost-effective opportunity according to
feedback from the Project Team. Consequently, the suspect ground water elevation results for this
monitoring well cannot be used when evaluating the ground water table elevations and flow direction,
which makes the determination of ground water flow more difficult. The  lower oxidant injection mass
applied to the downgradient portion of the plume may not have been sufficient to address the oxidant
demand posed by the  PCE mass and natural soil organic matter in that portion of the treatment area,
resulting in incomplete reaction with the contaminant.

Another potential data gap is the remaining residual PCE mass within the  source area following the soil
excavation. It is common for a substantial percentage of any release mass to migrate and become
immobilized within the capillary/smear zone immediately above the depth of groundwater, as well as the
top of the vadose zone through displacement of water from the soil pore structure. Neither soil
excavation nor vadose zone treatment technologies such as SVE can effectively remove source area mass
that has accumulated at these depths corresponding to high water saturation levels. Significant levels of
residual PCE mass remaining within the shallow source area saturated zone could result in observed
rebound of groundwater concentrations following the completion of the ISCO injection events.

4.4     IMPLICATIONS FOR REMEDIAL STRATEGY

The remedial strategy used for the site is sound.  Filling of the data gaps will result in a more robust
monitoring network and increased certainty in the conclusions about the permanganate injections. If the
plume is found to exist outside the current network, or a rebound in PCE groundwater concentrations is
observed following the completion of treatment, additional permanganate injections may be necessary to
treat the remaining residual PCE mass, or the Agencies will have to assess the ability of natural processes
(essentially sorption and dispersion) to prevent exposures and eventually attain  the ground water RAOs.
                                              13

-------
                                    5.0    FINDINGS
5.1     GENERAL FINDINGS

The observations provided below are not intended to imply a deficiency in the work of the system
designers, system operators, or site managers, but are offered as constructive suggestions in the best
interest of the USEPA and the public. These observations have the benefit of being formulated based
upon operational data unavailable to the original designers. Furthermore, it is likely that site conditions
and general knowledge of ground water remediation have changed over time.

5.2     SUBSURFACE PERFORMANCE AND RESPONSE

The implemented remedy appears at face value to have been largely successful as the downgradient PCE
groundwater concentrations have dropped significantly. See Figure 2 for graphs of the concentrations
over time in selected monitoring wells.  In order to verify the success of the program, some data gaps
need to be addressed, however.

The recent detection of 10s of ug/L of PCE  in a direct-push sample north of OU-MW-8 raises a question
of the definition of the plume. The persistent PCE concentrations in ground water just downgradient of
the former Tip Top Cleaners site also  suggest that one of the following influences may still be serving as
a source of PCE mass flux to ground water: there may still be diffusion-limited mass-flux (i.e., matrix
diffusion) originating from the source area or immobilized within finer-grained aquifer soil units; or more
than a minimal level of residual mass  still remains immobilized within the top of the source area saturated
zone that continues to dissolve into ground water flow. Either of these potential PCE mass scenarios
could continue to impact ground water quality in the absence of additional reactive permanganate.

The recent water levels near Spruce Street suggest a more eastward flow (e.g., in April 2012, the water
levels in wells along the east side of Spruce Street are all within 0.02 feet and define a north-trending
piezometric contour). The OU2 plume would be expected to be parallel to the nearby OU1 shallow
plume, unless there is some mechanism that can explain converging flow (e.g., a pumping  well or
preferred high permeability pathway).  Neither is known to currently exist based on available data. In
fact, the reduction in municipal, remedial, and household irrigation pumping in the past 20 years may
have removed possible causes for past converging flow. If ground water movement (and thus the plume)
has become more easterly, the plume axis may have shifted somewhat to the north. The plume is likely to
be quite narrow, given the small source footprint and the high ground water flux. The highly linear
monitoring network would not be able to distinguish between actual remediation and a shift in the
location of the plume axis.  Although it is likely that the plume has been largely successfully treated,
without bounding monitoring points, it is not possible to exclude a shift in the plume axis as the cause for
the declining downgradient concentrations.

The water levels at monitoring well EPA-7 seem inconsistent with the water levels in nearby OU2
monitoring wells. For example, water levels in April 2012 suggest a southward flow near the Tip Top
site if monitoring well EPA-7 water levels are used.  It may be that the survey benchmark/reference of the
measurement point for this well (and possibly monitoring wells EPA-9A and -11A) may differ from the
survey basis for the OU2 wells. As discussed in Section 4.3, the Project Team reported that survey datum
for top-of-casing of monitoring well EPA-MW7 is suspect, and will be re-established at the earliest cost-
effective opportunity.
                                              14

-------
The extent of the plume downgradient of East G Street has not been determined. Even though there may
not be complete exposure pathways to the east-southeast, the plume is not currently fully defined and it
cannot be assured that no exposure exists. This plume delineation data gap primarily applies to the
intermediate and deeper zones of the shallow aquifer unit between a depth of approximately 30 and
65 ft bgs.  The existing monitoring network appears to have delineated the upper portion of the shallow
aquifer unit to  a depth of approximately 30 ft bgs.  Monitoring wells MW-10 and MW-11 provide data
concerning the north and south edges of the plume at downgradient locations near the source area.

As discussed in Section 4.3, it is difficult to evaluate the level of the residual source area PCE mass that
may still remain in the shallow saturated zone, as well as the effectiveness of the upgradient ISCO
injections at treating the source area.  Even though permanganate injection events occurred upgradient
and just to the east of the source  area, and permanganate was placed in the bottom of the excavation that
could have affected a level of treatment of any remaining residual PCE mass, no direct injections have
occurred directly within the shallow aquifer below the source area to date. Soil and/or groundwater
sampling has not been performed within this shallow source area saturated zone to measure the level of
residual PCE mass that may still remain and serve as a continuing long-term source of mass flux to
ground water.  It is also difficult to determine the influence of immobilized PCE within finer-grained
aquifer soil units that can result in long-term matrix diffusion impacts to ground water.  Either one of
these PCE mass scenarios could  pose a constraint to achieving the ground water RAOs or significantly
increase the timeframe.

The water levels and PCE concentrations at the site of the Tip Top building, itself, would be useful data
for assessing the potential for continuing contaminant concentrations. An upgradient well would verify
flow directions in the vicinity of the former source.

The monitoring frequency has been quarterly at the site. Given the extensive history of sampling and the
lack of exposure points, the sampling frequency could be reduced without sacrificing the ability to detect
significant changes.  Additional quarterly sampling through 2012 would be appropriate to assess the
impact of the permanganate injections, but subsequent sampling could be less frequent. The Project
Team has communicated its intent to modify the future ground water sampling frequency to a semi-
annual basis.

5.3     COMPONENT PERFORMANCE

The ISCO injection design approach and protocol was established based on injection volumes and
protocol used during the treatability study performed during the interim removal action that was included
in the Basis of Design Report (BVSPC June 1, 2006).  Since the results of the treatability study showed
decreasing PCE concentrations, the injection design protocol was determined to be an effective approach
and thus was carried through to the full-scale treatment program.

The ISCO treatment program involved the injection of approximately 23,000 gallons of 5% sodium
permanganate solution into the shallow aquifer over a number of years.  At a 5% (by weight)
concentration, there would be about 0.42 pounds (Ibs) of permanganate per gallon. Therefore, just less
than 10,000 Ibs (4.54xl06 grams) of permanganate have been injected into the aquifer. The design for the
injection appears to have been based on calculations of the dissolved phase PCE mass in the aquifer, the
mass of permanganate needed to react with the contaminant mass, and a multiplier of four to serve as a
safety factor to account for other natural soil and aquifer material oxidant demand. This is not
necessarily consistent with current practice (e.g., USEPA, 2006). Natural organic matter and reduced
geochemical species (e.g., ferrous iron) may represent a substantial additional oxidant demand. Sorbed
                                               15

-------
and diffusion-limited contaminant mass in low permeability aquifer soil units typically represent a greater
percentage of the total contaminant mass than what resides in the dissolved phase, which equates to a
significantly greater oxidant mass requirement than what was accounted for in the design approach.
Remaining source area residual PCE mass could represent an even greater increase in the oxidant demand
for that part of the treatment area, which also was not accounted for in the original design approach.

Typical natural oxidant demands for soil have ranged from less than 1 gram oxidant/kilogram of soil
(g/kg) to over 60 g/kg according to a study performed by Geosyntec Consultants (Figure 3).  If one even
assumes a natural oxidant demand as low as 0.5 g/kg, the mass of oxidant injected would treat
approximately 9xl06 kg of dry soil. Assuming a dry density of 1,300 kilograms per cubic meter (kg/cu
m), this would represent just over 7,000 cu m.  Further assuming a treated thickness of 3 meters (most
injections were over the upper 10 feet), this would represent approximately 2,400 square meters (sq m) or
27,000 square feet (sq ft) - 100 by 270 feet. This would represent a very small fraction of the overall
plume footprint.  Based on this very rudimentary evaluation, it is possible that the ISCO injections may
not have introduced an adequate mass of permanganate, particularly in the downgradient portion of the
plume.

The ISCO design approach using  injection transects represents more of a barrier wall concept than a grid
approach to the injections. This type of barrier wall treatment concept relies on ground water advection to
transport the injected permanganate and disperse it throughout the plume. The ISCO design did not
include any type of tracer studies  or ground water modeling to evaluate the level of oxidant dispersion
and delivery that would occur throughout the plume. An empirical approach using the visible observation
of permanganate coloring throughout the monitoring network, as well as the trend in PCE groundwater
concentrations, has been used to evaluate the effectiveness of the permanganate delivery and dispersion
throughout the plume. Based on this empirical approach, it appears that the injection spacings have
generally been effective in the delivery of permanganate to portions of the plume  downgradient of the
various injection transects. However, the limited number of monitoring wells, as  well as inconsistencies
in the reported observation of observed coloring in the collected ground water samples (especially in the
source  area), makes it difficult to make conclusions regarding the overall  effectiveness of the
permanganate delivery throughout the plume. The adequacy of the monitoring network is critical to the
evaluation of the barrier wall injection approach that has been used.

The injections were focused in Areas 1 and 2 near the source (about 60%  of the volume/mass was injected
in these areas). Most of the injection points were downgradient of the Tip Top Cleaners source area.
Only limited injections occurred north and west of the former Tip Top Cleaners building. These
injections (and leached permanganate from the permanganate that was placed at the bottom of the site
excavation prior to backfilling)  represent the only oxidant mass that would potentially treat contaminant
that exists below the former building site.  It is not clear if this would be adequate. April 2012 sampling
suggests that residual permanganate exists along Spruce Street and in the  vicinity of OU2-MW-3.  Mass
diffusing from the source  area would potentially react with this residual mass.

As discussed above, the real metric for the success of the injections is the observed reductions in the PCE
ground water concentrations, as well as the observed distribution of permanganate.  If the PCE ground
water concentrations are substantially reduced and do not significantly rebound, and the permanganate
appears to have been well distributed, then the injections were successful. Based  on the  sampling of the
existing monitoring well network, it appears the plume has been greatly reduced and only the area
immediately downgradient of the  source area (i.e., up to the first row of downgradient injection transects
along Spruce Street) may  have persistent low concentrations of PCE. Additional  rebound sampling, as
planned, will provide verification of the success of the injection program (and soil excavation conducted
in 2011). If significant rebound is observed, particularly in the original Tip Top Cleaners source area,
ISCO injections specifically into this source area (below the area of vadose zone soil excavation) would
                                               16

-------
likely be warranted.  If additional definition of the plume identifies other areas of PCE contamination
requiring treatment, other injection locations/events may be appropriate.

5.4     REGULATORY COMPLIANCE

The project appears to have complied with regulatory requirements.

5.5     COMPONENTS OR PROCESSES THAT ACCOUNT FOR MAJORITY OF ANNUAL
        COSTS

As the remedy does not involve active treatment and no further permanganate injection activities are
planned, the site costs are related primarily with sampling, analysis, and report preparation.  Approximate
recent site contract costs for such activities are under $80,000/year.  This would include project
management. Assuming quarterly sampling represents the bulk of the work, each sampling event may
cost approximately $18,000.  Labor costs for sampling, including mobilization from Kansas City, per
diem costs, would probably be about $10,000. The analysis would probably cost less than $3,000.
Report generation would account for the remaining balance.  These costs appear to be reasonable.
                                           17

-------
                           6.0   RECOMMENDATIONS
Several recommendations are provided in this section related to remedy effectiveness, cost control,
technical improvement, and site closure strategy. Note that while the recommendations provide some
details to consider during implementation, the recommendations are not meant to replace other, more
comprehensive, planning documents such as work plans, sampling plans, and quality assurance project
plans.  It should be noted that the Project Team has elected to be proactive and already has plans to
implement most of the recommendations outlined below based on a review of a draft of this report. Plans
recently communicated by the Project Team to implement specific recommendations are also described
below.

Cost estimates provided herein have levels of certainty comparable to those done for CERCLA Feasibility
Studies (-30%/+50%), and these cost estimates have been prepared in a manner generally consistent with
USEPA 540-R-00-002, A Guide to Developing and Documenting Cost Estimates During the Feasibility
Study, July, 2000. The costs presented do not include potential costs associated with community or public
relations activities that may be conducted prior to field activities. The costs and environmental footprint
impacts of these recommendations are summarized in Table 1.

Overall, the remedy appears to have been quite successful.  Sections 4.0 and 5.0 of this report, however,
have identified possible questions regarding the CSM and the effectiveness of the implemented remedy to
achieve aquifer restoration. The recommendations related to improving effectiveness in Section 6.1 are
focused on addressing the identified data gaps, but do not represent all  of the information that may be
needed to complete the CSM and appropriately modify the remedies. The recommendations in Section 6.1
do not discuss improving the ability of the existing strategy to restore ground water.  These
recommendations are presented in Section 6.4, where various remedial strategies are considered for
moving forward if additional work identifies that the remediation has not been as complete as thought.

The optimization team identified opportunities to reduce the monitoring cost of operating the existing
ground water remedies; however, the optimization team believes that the questions about the existing
CSM makes providing cost reduction recommendations uncertain, as the level of effort for the monitoring
may need to be changed. Minor recommendations for technical improvement are presented in
Section 6.3.

6.1     RECOMMENDATIONS TO IMPROVE EFFECTIVENESS

6.1.1        PLUME VERIFICATION AND DEFINITION

The current extent of the ground water plume needs to be more fully verified to assure that the very
promising concentration reductions have actually occurred throughout the plume.  Monitoring points that
bound the plume  in the cross-gradient and downgradient directions are needed.  One recommended
approach would be to perform direct-push ground water sampling transects of three to four points  at three
locations, perhaps along Spruce Street, East B Street, and East G Street. In addition, an additional
transect should be conducted to  the east of East G Street (possibly south of East 1st Street along the
projection of East H  Street or East I Street) to verify the downgradient extent of the PCE plume identified
north of OU2-MW-8. This would require access to commercial properties on the south side of East 1st
Street.
                                              18

-------
The estimate to implement the recommended additional groundwater delineation work scope discussed
above would be $15,000 for the initial Geoprobe delineation assessment employing transects
downgradient and around the perimeter of the plume with associated groundwater sampling. Detailed
backup and assumptions for these cost estimates are provided in Attachment A.  Costs represent FS level
preliminary estimates, and should not be used for budgetary purposes without further refinement of the
work scope and detailed line item costs.

Upcoming planned assessment activities recently communicated by the Project Team include vertical
profiling and plume delineation in the area of monitoring well MW-8 using a combination of various
direct-push techniques such as membrane interface probe ([MIP], soil gas measurements), electrical
conductivity ([EC], mapping tool for soil types), hydraulic profiling tool ([HPT], which measures
formation permeability for preferential migration pathway  identification), and soil/groundwater grab
sampling.  The field data collection using these direct-push techniques will be used to identify locations
for the installation of additional nested monitoring wells within the intermediate and deeper depths of the
shallow aquifer unit.

6.1.2       ADDITIONAL MONITORING WELLS

Based on the results of these verification transects, additional permanent monitoring points may then be
needed. If in the somewhat unlikely event that the plume has indeed shifted northward based on the
sampling results for one  or more of the transects, a monitoring well on the current plume axis would be
needed, and another well further north to bound the plume. The current wells would be used to generally
bound the plume on the south. An additional monitoring well would be required at the downgradient end
of the plume, even if no additional contamination is observed, to act as a defining point for the end of the
plume.  If contamination is observed farther downgradient, additional downgradient transects may be
needed to bound the plume.

An on-site source area monitoring well is needed to determine concentrations at the location of the former
Tip Top Cleaners site, and to verify the effectiveness of the recent soil excavation and assess rebound
from the permanganate injections in the source area.  An upgradient/background well may also be
appropriate if there is any reason to question the impact from other sources/sites, or if impacts to ground
water may have occurred from site operations (or vapor transport) in the upgradient direction.

A total of $17,000 to  $24,000 would be required to install five to nine additional permanent monitoring
wells (no groundwater sampling included). Detailed backup and assumptions for these cost estimates are
provided in Attachment A.

It is also recommended, if logistically feasible, that soil and "grab" groundwater samples be collected
during the installation of the recommended monitoring well and any future Geoprobe assessment
activities performed in the source area.  A representative number of shallow saturated zone soil samples
and a "grab" ground water sample could be collected from the boring associated with the planned
monitoring well installation immediately downgradient of the source area. As it would be located near
the suspected source area towards the southern and southeastern ends of the former building, it could
correspond to the location of the hand auger borings HA-1  thru HA-3 conducted for the pre-excavation
source assessment that exhibited the highest PCE soil concentrations. During any other recommended
direct-push work at the site, additional sampling could be conducted within the capillary fringe and
uppermost portion of the saturated zone at other locations near the former Tip Top Cleaners building.
This level of source area sampling would provide an indication of the remaining residual PCE mass that
could serve as a long-term source of continuing mass flux to ground water that may lead to observed
rebound at the downgradient monitoring wells.  Alternatively, if the results from future ground water
                                               19

-------
sampling events show evidence of rebound, then an additional mobilization would be required to perform
this recommended source area sampling to target locations and depths for further treatment.  As discussed
in Section 6.4 in more detail, upcoming planned source area groundwater delineation activities
communicated by the Project Team include vertical profiling of PCE mass presence in the saturated zone
and installation of monitoring well nests (screened in both the shallow and deeper zones of the shallow
aquifer unit) based on the initial findings from the vertical profiling. One or more source area monitoring
wells had been proposed prior to the optimization study.

6.1.3       VAPOR INTRUSION ISSUE

The five-year review report raised questions about the potential for vapor intrusion  into buildings
overlying the OU2 plume and recommended that this pathway be more fully characterized. This
optimization report endorses this recommendation, if it is discovered that the plume remediation was not
as complete as it appears. Furthermore, this report assumes the vapor intrusion issue for both OU2 and
OU1 will be appropriately pursued through actions recommended by the five-year review, and tracked
separately from these optimization recommendations.

6.2     RECOMMENDATIONS TO REDUCE COSTS

Since the primary cost at the site is for continued monitoring for concentration rebound following the
completion of the permanganate injection, the only way costs can be reduced is by modifying the nature
of the monitoring program.  The quarterly sampling at the site should be continued  for no more than
another few quarters, and then semi-annual sampling could be conducted. Such sampling reduction
would not significantly affect the ability to verify adequacy of the remediation, since rebound effects tend
to occur slowly and should be more evident closer to the source area. Semi-annual sampling would still
allow sufficient time to implement additional remedial measures, if needed, without the plume migrating
further or posing  an unacceptable risk to a potential receptor.  If semi-annual sampling is begun in mid-
2013, that would  have provided approximately two years of quarterly sampling, more than enough to
assess fluctuations. Conditions at the site are not so dynamic as to require more frequent sampling
beyond mid-2013. Annual sampling may be appropriate if only low concentrations are observed
following two to three years of semi-annual sampling. Note that this would be a minor or possibly
significant change to the OU2 ROD, as this ROD unfortunately specifies quarterly sampling until
concentrations reach the RAOs. This change, if considered minor, would require a memorandum to the
administrative record documenting the change in sampling frequency, or at most would require an
Explanation of Significant Difference.

This reduction in sampling frequency would reduce the USEPA-funded sampling effort by six sampling
events by mid-2016. This represents a cost reduction of approximately $36,000 per year or atotal of
$108,000 (6 times $18,000 per round). The Project Team has communicated its intent to modify the
future ground water sampling frequency to a semi-annual basis.

The monitoring program could be reduced further by excluding wells from sampling. If the  results of the
verification sampling outlined in section 6.1 determined that the remaining plume is limited to areas west
of East A Street, monitoring wells downgradient of OU2-MW-4 (eight shallow wells, including USEPA-
11A) could be excluded from the monitoring program.  This would clearly reduce sampling labor,
analytical costs, and report effort/cost. Since the outcome of the verification sampling is not known, these
reductions in cost are not quantified, but could be 30% of the per-round costs.  The  project team is
encouraged, though, to consider such network reductions in the future based on those results. Note that
any wells excluded from the sampling program should not be decommissioned as they potentially provide
useful water level information for both OU2 and OU1. Well decommissioning would be done following
                                              20

-------
full attainment of OU2 remedial goals.  Lastly, sampling of Gravel Pit Lake should be conducted under
OU1, not under OU2, as contaminants identified in these samples do not include PCE, though the VOC
results should be shared with the OU2 project team.

6.3    RECOMMENDATIONS FOR TECHNICAL IMPROVEMENT

6.3.1       SAMPLING METHOD SIMPLIFICATION

The current program uses PDBs for VOC analysis combined with micro-purging to collect samples for
geochemical parameters and metals. Given the current good understanding of the geochemistry and the
lack of significant concentrations of oxidation-sensitive metals (i.e., chromium and selenium), future
sampling for downgradient wells could be conducted solely for VOCs by PDBs. Grab samples to provide
qualitative color evidence of the persistence of the permanganate could be obtained from near-source
wells using disposable bailers or Hydrasleeve® samplers. This would somewhat reduce both the time
necessary to conduct sampling and sampling complexity. This may even allow hiring of local sampling
staff that would reduce travel and labor costs, though the cost savings from this have not been calculated.
The Project Team has communicated its intent to modify future ground water sampling events for the
downgradient wells to include only VOCs using PDBs.

6.3.2       VERIFICATION OF MONITORING WELL REFERENCE POINT ELEVATIONS

The unusual water levels in some of the USEPA-series monitoring wells installed south of the main OU2
plume suggests that it would be prudent to assure that the measurement reference points for the water
levels are consistent with those  of the other OU2 monitoring wells.  When the recommended monitoring
well(s) are installed and are surveyed, it is strongly recommended to have the surveyor resurvey all
monitoring wells in the network. Assuming that a surveyor from North Platte or Scottsbluff, NE would
conduct the work, it is estimated that the cost would not exceed $3,000.  These costs do not include a
project team member meeting the surveyor at the site and leading them to the wells. As discussed in
Section 4.3, the Project Team reported that survey datum for top-of-casing of monitoring well EPA-MW7
is suspect and will be re-established at the earliest cost-effective opportunity.


6.4    CONSIDERATIONS FOR GAINING SITE CLOSE OUT

The existing site close-out strategy appears to have been successful. In the event that confirmatory
sampling verifies that the remaining plume is very limited to areas near the former source, and that any
downgradient contamination north of OU2-MW-8 is also very limited, sampling would be continued
beyond 2016 at an annual frequency (or less) until results for PCE are below RAOs.

If verification sampling recommended in Section 6.1 indicates that the plume is more extensive than
recently believed, additional permanganate injections would be required to address these portions of the
plume.  A similar strategy to what has been previously implemented would be appropriate, with some
modification.  Permanganate injection dosage for areas not previously treated needs to explicitly consider
the natural soil and aquifer material oxidant demand in addition to that required to  react with the
contaminant.

In the source area, if continued  sampling of existing monitoring wells and the sampling of the
recommended new Tip Top source area well suggest that PCE concentration rebound has occurred, an
additional injection event of permanganate that includes areas both upgradient (northwest) of the
excavation area and directly within the  source area is recommended. Again,  the dosage should  be
increased to allow injection of adequate mass to treat the remaining residual PCE mass (determined based
                                             21

-------
on soil sampling data instead of dissolved phase groundwater data) and account for the demands from any
remaining natural organic matter in the soil and aquifer matrices.

As discussed in Section 6.1.1, an adequate level of soil sampling should be performed within the shallow
saturated zone to properly quantify the remaining residual PCE mass. Representative soil samples
corresponding to the injection depth should also be collected and analyzed for total natural oxidant
demand.  If the level and extent/thickness of any residual PCE mass layer is significant, a grid type of
injection approach within the defined source area would be more effective than the current transect
approach. Upcoming planned source area assessment activities communicated by the Project Team
include the following: 1) use of MIP/EC to provide vertical profiling of PCE mass presence in the
saturated zone; 2) installation of monitoring well nests (screened in both the shallow and deeper zones of
the shallow aquifer unit) based on the initial MIP/EC findings; and 3) collection of two saturated zone
source area soil samples for analysis of volatile organic compounds (VOCs) and permanganate natural
oxidant demand (PNOD) to evaluate residual source area PCE mass and provide a quantitative
measurement of the PNOD for further evaluation of the ISCO design approach. PNOD analyses were
performed during the past source area soil excavation activities, but these soil samples were from the
vadose/capillary zone where the silty-clay content (and corresponding organic carbon content) is higher
than the more permeable sandy soil content predominant in the shallow aquifer unit, so the PNOD
measurements may not have been representative for design evaluation purposes.

The transect approach to the injections would still be recommended for the scenario where some rebound
is occurring because of matrix diffusion or adsorbed phase mass covering a larger downgradient area of
the plume beyond the source area (i.e., source area residual PCE mass and its relative depth/thickness
does not warrant further treatment). Additional monitoring would be needed following this injection
event to determine if additional rebound would occur.

6.5     RECOMMENDATIONS RELATED TO ENVIRONMENTAL FOOTPRINT
        REDUCTION

Since the site does not currently have any active remediation, there is not much of an environmental
footprint relative to some other post-ROD Superfund sites. The footprint is largely generated by
sampling activities. There would also be an environmental footprint for any work to install additional
monitoring wells at the site. The reduction in sampling frequency from quarterly to semi-annual would
result in a reduction of environmental footprint of the remedy. For purposes of estimating a reduction in
the footprint for greenhouse gases and other related metrics, it was assumed that three years of post-
treatment sampling would remain to be performed, which would result in the elimination of six ground
water sampling events total.  At that point in time, any continued LTM program would likely occur on an
annual basis under any scenario that would be considered, so it is not accounted for in the footprint
reduction calculations.

To quantify this change, the Site Wise environmental footprinting tool was used. Though this tool does
not precisely match the approach or quantify all of the metrics recommended by USEPA in its February
2012 guidance document "Methodology for Understanding and Reducing a Project's Environmental
Footprint", it provides a quick and useful estimate of environmental benefits from this change.  The
footprint due to the implementation of additional direct-push sampling transects and the installation of
additional monitoring wells was not computed  using Site Wise as the exact scope of these activities are not
yet known.

The reduction in footprint for the reduction in sampling assumes that the sampling team mobilizes from
Kansas City, Missouri to the site. The use of low-flow sampling techniques was assumed (i.e., need to
                                              22

-------
operate a generator during sampling), though use of PDBs is recommended above. A single mobilization
was assumed for each sampling event involving a single light-duty truck and two sampling personnel. A
total of 16 monitoring wells would be sampled over a two-day period. The sampling pump/generator was
assumed to operate for a period of 15 minutes per monitoring well (4 hours total). Based on a review of
the various sampling reports, it was assumed that no investigation-derived wastes would be generated for
collection and off-site disposal. The reductions in the following footprint metrics were estimated:

    •  3.3 metric tons of greenhouse gases mostly due to vehicle mobilization;

    •  4.2 million BTUs of energy consumption mostly due to vehicle mobilization;

    •  1.4xlO~3 metric tons of nitrous oxides mostly due to vehicle mobilization;

    •  4.3xl9"5 metric tons of sulfur oxides due to vehicle mobilization; and

    •  4. IxlO"4 metric tons of PM10 due to vehicle mobilization and operation of the generator.

6.6     SUGGESTED APPROACH TO IMPLEMENTING RECOMMENDATIONS

The reduction in sampling frequency described in section 6.2 should be considered for implementation in
mid-2013 (so there are eight post-injection quarterly sampling rounds). The simplification of the
sampling method suggested in section 6.3.1 could be implemented with the next sampling round.  This
could be implemented regardless of the other recommendations. Other reductions in sampling at
monitoring well locations as described in 6.2 are contingent on the outcome of the plume verification in
6.1.1. Monitoring will be on-going until MCLs are attained, per the ROD.

The plume verification direct-push sampling as described in 6.1.1 should be implemented.  Additional
monitoring well installation to redefine the plume axis and lateral limits would be conducted only if the
results of the plume verification find that the plume may have shifted. An additional downgradient
monitoring well would need to be installed regardless of the other results to define the downgradient
extent of the plume.  A source area monitoring well should be also installed at the Tip Top Cleaners site
to verify PCE concentrations in the immediate area of the recent excavation, regardless of the other
results. The verification of the monitoring point reference elevations recommended in section 6.3.2 could
easily be  done in conjunction with the surveying required for these new wells. Additional permanganate
injections as described in 6.4 would only be considered if the plume has been found to be more  extensive
than currently inferred, or if concentrations rebound in the source area or immediately downgradient  due
to remaining source area residual PCE mass or matrix diffusion influences.
                                             23

-------
Table 5.  Summary of Recommendations
Recommendation
6.1.1 Plume
Verification and
Definition
6.1.2 Additional
Monitoring
Wells
6.1.3 Vapor
Intrusion:
Recommendation
From FYR
6.2 Reduce
Monitoring
Frequency
6.3.1 Simplify
Sampling
Methods
6.3.2 Verify
Monitoring Well
Survey
6.4 Additional
Permanganate
Injection
Reason
To assure that
the plume has
been remediated
Additional
monitoring
wells required
to monitor
delineated
plume and
source area
conditions
Verify that, if
plume still
exists, no
unacceptable
risk exists via
indoor air
Quarterly
sampling no
longer necessary
to meet project
decision needs
Sampling
should be
primarily for
VOCs, so PDBs
are adequate
Assure
consistent
reference
elevations for
piezometric
measurement at
OU2
If the plume is
found to be
persistent,
additional
permanganate
injection may be
needed
Additional
Capital Costs
($)
$15,000
$17,000-24,000
Not Determined
(addressed in
five-year
review)
None
None
$3,000
Unknown at this
time. Depends
on the results of
additional
sampling.
Estimated
Change in
Annual Costs
($)
$0
$5000 if no
other reductions
in monitoring
network, but
could be offset
by eliminating
other wells (see
sec. 6.2)
Not Determined
($36,000) Does
not include any
reductions in
the network.
Such reductions
could reduce
costs an
additional
$5,000.
Not determined
(included in
savings for
section 6.2)
None
Unknown at
this time. It is
not clear
relative to what
reference any
cost savings
would be
calculated.
Estimated
Change in
Life-Cycle
Costs ($)*
$0
$15,000
Not Determined
($108,000)
Not determined
(included in
savings for
section 6.2)
None
Unknown at
this time. It is
not clear
relative to what
reference any
cost savings
would be
calculated.
Estimated
Change in
Life-Cycle
Costs ($)**
One-time cost
Limited
discount over 3
years
Not Determined
Limited
discount over 3
years
Not Determined
None
Unknown
Numbers in parentheses are reductions in cost.
                                              24

-------
Figures

-------
Figure 1.  Site Location and April 2012 PCE Plume
       •                     '       .... —           -	
                                                                                                                            A/
                                                                                                                                iDasftsd W^e-e lireredj

                                                                                                                                fiesdenSial'.Vell No 4


                                                                                                                                Hisicucal Injection Pom
                                                                                                                            \-f - ,'.as .!,-*•• iq!i-€-ricr*e*ceptwel
                                                                                                                            *Jrt'-o3 an; RjE'de'tal Wdl No. 4
                                                                                                                            (Lower Aquifer Zone)
                                                                                                                           OgallaJa Groundwater Site - OU2
                                                                                                                                Ogallala, Nebraska
                                                                                                                            Groundwaler Flow Direction and
                                                                                                                              Contaminant Contour Map
                                                                                                                            Upper Aquifer Zone - April 2012
                                                                                                                           £1 BLACK&VEATCH

-------
Figure 2. PCE Concentration Trends for Monitoring Wells along Plume Axis
  10000
   1000
    100
     10 --
      1
      Apr
    0.1
-01  Sep-02  Jan-04 May-05  Oct-06  Feb-08   Jul-09   Nov-10 Apr-12  Aug-13
                                                                              MW-2
                                                                              MW-3
                                                                              MW-4
                                                                              MW-5
                                                                              MW-6
                                                                              MW-7
                                                                              MW-8
                                                                              MW-10

-------
Figure 3. Sample Natural Oxidant Demand for Soils, Geosyntec Consultants, 2011.
    Soil Type vs. Oxidant Demand
            500
Soi
	   *-^  ' *	

^Bed-"'"Coarsej (pine ^Silty ^ 'Clayey] C~
.^Rocky ^gand J ySand,, vSandy '-Sand J L	
                                           V   ")
                                           Jl __ )

-------
Attachment A:  Cost Estimate Back-up Assumptions and Table for Additional
Sampling

Basis: 1) Initial delineation would use a Geoprobe rig to install temporary wells or sample groundwater using
a peristaltic pump. Three to four transects would be performed downgradient and around the perimeter of
the plume, with three to four sample locations per transect. For costing purposes, it is assumed a total of 12
boring locations would be sampled. This work scope would take two field days to complete. Each location
would be sampled for VOCs with three additional QC samples (15 samples total) using normal laboratory
turnaround time.  2) Permanent monitoring wells would be installed based on the delineation results.  A total
of five to nine monitoring wells would be installed.  This work scope would take two to three field days to
complete (based on three wells/day). Well construction would be flush-mounted, 2-inch PVC completed to a
depth of 30 ft bgs. The wells would be developed immediately upon installation using disposable bailers or
a downhole pump (i.e., no surging would be performed). Sampling costs and collection/disposal costs for
soil cuttings and purge water were not included. 3) All boring locations would be blind drilled with no split-
spoon sampling or borehole logging. 4) Contractor labor hours account for travel from Kansas City (8 hours
each way), preparation of a boring location map and well completion logs, compilation of analytical data,
and field work related project management. 5) Costs  associated with preparation of a work plan or final
report were not included. It is assumed that the groundwater delineation field work and sampling results
would be incorporated into already budgeted periodic status reports.
       Cost Item                    Unit Cost
I)      Geoprobe Delineation

       Driller Mobilization           $1,000
       Geoprobe (1 person)           $l,500/day
       Proj ect Manager              $ 125/hour
       Geologist                    $80/hour
       CAD                        $65/hour
       Vehicle/PID/Expenses         $350/day
       Analytical/Shipping           $200/sample
       Well Materials                $100/well
       TOTAL

II)     Permanent Well Installations

       Driller Mobilization           $1,500
       Drill Rig (2 people)            $2,500/day
       Well Materials                $500/well
       Purge Pump                  $50/day
       Proj ect Manager              $ 125/hour
       Geologist                    $80/hour
       CAD                        $65/hour
       Vehicle/PID/Expenses         $350/day
       Survey Equipment             $100/day
       TOTAL
Unit
lump sum
2 days
6 hours
50 hours
4 hours
2 days
15 samples
12 wells
lump sum
2-3 days
5-9 wells
2-3 days
6 hours
50-65 hours
6 hours
2-3 days
2-3 days
Subtotal
$1,000
$3,500'
$800
$4,000
$300
$700
$3,400'
$1.400'
@$15,000
$1,500
$5,800-$8,700'
$2,900-$5,200'
$100-$200'
$800
$4,000-$5,200
$400
$700-$!,100
$200-$300
@$17,000-$24,000
Notes:  1) A 15% subcontractor mark-up was included in this subtotal to provide a conservative estimate.
       2) Subtotals were rounded off as appropriate.
       3) Unit costs are for cost estimating purposes only, and do not reflect actual contractual rates.
       4) Costs represent Feasibility Study level preliminary estimates, and should not be used for
       budgetary purposes without further refinement of the work scope and detailed line item costs.

-------
    Attachment B:   SiteWise Results for Environmental Footprint  Reduction for
    Sampling Program Change
Sustainable Remediation Summary - Longterm Monrtonng
Activities
Consumables
Transportation-Personnel
Tr;]nspcr3tio"-Equipment
Equpn^nt Jse 3^4 Wise
Re;- 'dun hj" :! r:;
Tola
CMS
Emissions
metric ton
000
330
0.00
003
0.00
334
Percent
Total
%

99.0

1.0

100.0
Total Energy
Used
MMBTU
C.OE*00
4.2E*01
O.OE'OO
4.5E-01
O.OE'OO
4.22E-OI
Percent
Total
%

98.9

1.1

100.0
Water
Consumption
gallons
NA
NA
NA
O.OE-HJO
NA
OOOE»00
Percent
Total
%
NA
NA
NA
0.0
NA
00
NOx
Emissions
metric ton
NA
1.4E-03
O.OE»00
4.8E-05
O.OE'OO
: 42E-03
Percent
Total
°-'D

96.6

34

1000
SOx
Emissions
metric ton
NA
43E-05
O.OE*00
O.OE*00
OOE»00
4 3JE-05
Percent
Total
£

1000



1000
PM10
Emissions
metric ton
NA
2.0E-04
O.OE*00
2.2E-04
O.OE*00
4 I2E-04
Percent
Total
ft

47.6

52.4

IOC. I]
Accident Risk
Fatality
NA
9.4E-05
OOE*00
O.OE*00
O.OE'OO
a 36E-05
Percent
Total
%
NA
100.0



100.0
Accident Risk
Injury
NA
T.5E-03
O.OE*00
O.OE*00
O.OE*00
7.53E-03
Percent
Total
«i
NA
100.0



1000
Additional Sustainability Metrics
                               Footprint Reduction
Non-Hazardous Waste
Landfill Space (tons)
Hazardous Waste Landfill
Space (tons)
Topsoil Consumption (yd3)
Costcf Pr,-fE,e :•;.'
Lor I- :M :- - 'i~ . rv
Q.O
O.D
O.D
0.0
0.1
Total electricity replacement (MWhf
Total electricity replacement (mmBtu)
_andfill gas reauclion iTetricton C02 e)
.-- .- r1' ': . . i " • .! _ '_ J &l

SC- i?^issixs -iietrictcni
-",1 ii if :'i ., ': '-''.".'
O.OOE^OO
O.OOE+00
O.OOE+00
C DO—CO
O.OOE+00
O.OOE+00
: VE-LJ
                      GHG Emissions
 • Consumables        • Transportation- Personnei   Transportation-Equipment
 • Equipment Use and Misc  r-Residual Handling
                      Water fl^risumption
•Consumables        • Transportation-Personnel   Transportation-Equipment
• Equipment Use and Misc  . Residua) Handling
                                                                            Enercj-y. Consumption
•Consumables        • Transportation-Personnel  Transportation-Equipment
• Equipment Use and Misc  •• i Residual Handling
                                                           • Consumables
                                                           Transportation-Eq uip men!
                                                           ••Residual Handling
                           • Transportation-Personnel
                           • Equipment Use and Misc

-------