\       UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
                                WASHINGTON, D.C,  20460
                                        FE3  1 5 2013
                                                                            OFFICE OF
                                                                         SOLID WASTE AND
                                                                        EMERGENCY RESPONSE
                                                     OSWER Directive 9200.2-129

MEMORANDUM

SUBJECT:   Broader Application of Remedial Design and Remedial Action Pilot Project
             Lessons Learned

FROM:      James E. Woolfoid, Director/Jr/k '
             Office of Superfund Remediation and Technology Innovation

TO:         National Superfund Program Managers, Regions 1-10
This memorandum transmits a summary of lessons learned from three completed remedial
design (RD) / remedial action (RA) project management pilots conducted under the Integrated
Cleanup Initiative (ICI) entitled "Broader Application of Remedial Design and Remedial Action
Pilot Project Lessons Learned" (OSWER Directive 9200.2-129).

EPA regional offices have been working over the last two years on nine project management
pilots under the ICI to explore the use of best practices or new ways of improving Ihe efficiency
of Superfund remedial cleanups. Three pilot reports completed during FY12 address aspects of
the Superfund RD/RA process. In each case, significant results were achieved that saved both
time and money. The pilot studies demonstrated time savings of as much as 67%  over traditional
project duration and dollar savings or cost avoidances of between approximately $135,000 and
$584,000.

Attached is a summary of the lessons learned from these three pilots that highlights strategies
that may be especially beneficial to our program. As budgets become increasingly constrained, it
is with great satisfaction that I am able to share these regional success stories. I encourage you
and your project teams to consider application of the approaches examined in these pilots
wherever appropriate.

This memorandum can be found on the OSWER ICI website under Action 17 at:
http://www.epa.gov/oswer/integratedcleanupactions,htm#Action 17. Web links to the final
reports and brief summaries of pilot results are provided below:
                                                                                679343
                                Internet Address (URL) • ntlp v/www epa gov
         RecyclwlrRocyelabI* • Printed wtm Vegetable Oil Based Inks on 100% Poslconsumer. Process Chlorine Free Recycled Paper

-------
South Jersey Clothing .Company / Garden State Cleaners Sites (Region 2): The region focused
on the use of in-house EPA personnel to conduct RD and RA at two neighboring dry cleaners.
Remedial, removal, Environmental Response Team (ERT), US Army Corps of Engineers
(USAGE) and Emergency and Rapid Response Services (ERRS) contract staff worked closely at
these sites to demolish a building and conduct two soil excavations. This collaboration resulted
in three remedial action project completions (RAPCs) one year earlier than planned along with
substantial cost savings even after considering  the increased use of in-house  payroll.
 http://www.epa.gov/oswer/docs/ici/action 17_668687.pdf.

plash Cleaners She (Region 4):  The region applied several approaches to compress the schedule
and accelerate completion of RD/RA work, including overlapping RD and RA activities,
separating implementation of the soil and groundwater work activities, and using the ERRS
contract for RA to excavate soil, install an SVE system, and address a VOC  plume through
enhanced bioremediation at a dry cleaners site. The region achieved construction completion
(CC) one year earlier than expected (reducing cleanup duration by about 50% and saving as
much as 27% of construction  costs), http://www.epa.gov/oswer/docs/ici/action 17_657328.pdf.

Ellenvilie Scrap Iron and Metal Site (Region 2):  Working closely together, HQ and the region,
USAGE and their contractors developed and applied an innovative project delivery technique
("focused project integration") to excavate and consolidate soil from the 24-acre Ellenvilie
property into a capped, 10-acre area. A RAPC  was accomplished in about a third the time
originally expected, and at reduced cost.
http://www.epa.gov/oswer/docs/ici/action 17_656860.pdf.

A summary of progress for all nine pilots can be found at the following website:
 http://www.epa.gov/oswer/docs/ici/action 17_11 -669647.pdf.

Again, many thanks to all that contributed to these substantial efforts.

If you have any questions, please call me or have your staff call Bruce Means (OSRTI) at (703)
603-8815 or John La Padula (Region 2) at (212) 637-4405.

Attachment

cc:    Mathy Stanislaus, OSWER
      Lisa Feldt, OSWER
      Barry Breen, OSWER
      Barnes Johnson, OSRTI
      Becki Clark, OSRTI
      Robin H. Richardson,  OSRTI
      Pamela Barr, OSRTI
      OSWER Office Directors
      David Kling, FFEO
      Elliott Gilberg, OSRE
      Nancy Jones, OSRTI
      Thea Williams, OSRTI

-------
                                 Integrated Cleanup Initiative
             Remedial Design and Remedial Action Pilot Projects
                                    Lessons Learned
                                       (February 13, 2013)

1.0    Introduction

In 2010, EPA's Office of Solid Waste and Emergency Response (OSWER) in partnership with the
Office of Enforcement and Compliance Assurance (OECA) initiated a three-year strategy, the Integrated
Cleanup Initiative (ICI), to identify and implement improvements to the Agency's land cleanup
programs.  The Initiative identified opportunities to integrate and leverage the Agency's authorities to
accelerate  cleanups, address a greater number of contaminated sites, and put these sites back into
productive use while protecting human health and the environment.

In November 2010, OSRTI identified nine project management pilot studies under this Initiative to
evaluate approaches to achieving site cleanups more efficiently. These pilots were selected to
demonstrate region-specific best practices and new approaches to project management for the Superfund
remedial program. This paper presents an overview of the strategies and measures explored under three
pilots that  studied ways to accelerate work during the remedial design (RD) and remedial action (RA)
phases of cleanup. These pilots all resulted in time and cost efficiencies. Successful strategies  evaluated
were: compressing project schedules by conducting concurrent or overlapping RD and RA activities;
relying more fully on in-house resources to achieve cleanups; the judicious selection and use of
contractors and contract types; use of sampling strategies that minimize analytical and field mobilization
costs; and, enhancing collaboration among partners and stakeholders to facilitate resolution of issues and
concurrence on site management approaches in real time. Descriptions of how these practices were
employed  for the three pilots may be found in the final reports cited below.

The pilot reports indicate that significant time savings and cost savings or avoidances can result from
using these innovative  measures compared to traditional approaches. While these pilots were conducted
at fund-lead sites, many of the measures explored may also have value and could result in cleanup
efficiencies at sites where cleanups are undertaken by private parties or federal facilities. It is
recommended that site managers consider use of these practices at sites wherever appropriate.

2.0    Background and Description of Pilots

In October 2010, at the request of the Director of the Office of Superfund Remediation and Technology
Innovation (OSRTI), a workgroup comprised of senior management (e.g., deputy division directors)
from each  EPA regional office, OSRTI, the Office of Site Remediation and Enforcement (OSRE),  and
the Federal Facilities Restoration and Reuse Office (FFRRO) met to review regional pilot nominations.
Recommendations were developed for the OSRTI Office Director based on their potential to impact the
quality, transparency, and /or speed of cleanups broadly across the Superfund remedial program. For this
reason, projects that were of manageable size, that required only moderate financial resources and that
were expected to be completed within a reasonably short time frame (e.g., one to two years) were given
priority in  the selection process.

The three pilot projects chosen to evaluate nontraditional approaches to achieving site cleanups more
efficiently for sites approaching RD and RA included the Ellenville Scrap Iron and Metal site in

-------
Wawarsing, New York; the Flash Cleaners site in Pompano Beach, Florida; and the South Jersey
Clothing Company and Garden State Cleaners sites in Buena Borough, New Jersey.

       2.1    Ellenville Scrap Iron Metal Site, Region 2, New York

The Ellenville Scrap Iron and Metal site in EPA Region 2 was a 24-acre, former scrap metal reclamation
facility. About ten acres of the site were used for a variety of scrap metal operations and battery
reclamation. The site included a five-acre landfill composed  of construction and demolition debris,
including brick, concrete, wood and metal debris. An adjacent residential property was formerly part of
the facility. Associated soil contamination resulted in the listing of this site on the Superfund National
Priorities List (NPL) in October 2002. The activities identified within the scope of this pilot included
excavation  of contaminated soils and consolidation with existing waste under a newly constructed
landfill cap in accordance with the September 2010 Record of Decision (ROD).

This pilot was designed to accelerate the RD and RA through an "integrated project delivery" approach
which sought to maximize efficiency of procurement, management and  delivery of design and
construction services while maintaining safety and technical  quality. Key elements of the  pilot included
early construction contractor involvement, collaboration among all team members and shared
acceptance  of project objectives and risk. As a result of the pilot, RA construction activities were
accomplished in about a third of the time originally expected (i.e., within one year), and at reduced cost
(saving approximately $584,000). The pilot report may be found at
http://www.epa.gov/oswer/docs/ici/acti onl7_656860.pdf.

       2.2    Flash Cleaners Site, Region 4, Florida

Between 1977 and 2001, dry cleaning operations conducted at the half-acre Flash Cleaners site resulted
in the contamination of soil and groundwater with solvents. In September 2008, this site was added to
the NPL. The September 2010 ROD called for, among other actions, excavation and off-site disposal of
contaminated soils, installation of a soil vapor extraction (SVE) system  for removing contaminants from
beneath the existing building and injection of an emulsified oil substrate into groundwater to enhance
the natural degradation of contaminants.

The purpose of this pilot was to demonstrate that conducting components of the RD and RA activities
concurrently and utilizing the Emergency and Rapid Response Services (ERRS) contract for the RAs
can result in time and cost efficiencies and shorten the amount of time to reach construction completion.
At the Flash Cleaners site, the  Region achieved construction completion for the site one year earlier than
expected (reducing cleanup duration by about 50% and saving as much  as 27% of construction costs or
approximately $135,000). The pilot report may be found at
http://www.epa.gov/oswer/docs/ici/action!7_657328.pdf.

       2.3    South Jersey Clothing Company (SJCC) and Garden State Cleaners (GSC) Sites,
             Region 2, New Jersey

The SJCC and GSC sites in EPA Region 2 are two separate properties within 500 feet of each other
where soil contaminated with volatile organic chemicals (VOCs) resulted in a commingled groundwater
contamination plume. The GSC site supported a former dry cleaning business which began operating in
1966 and until 1985 discharged wastes through pipes directly into the ground. In 1940, the SJCC facility
began manufacturing and dry cleaning military clothing using solvents and also discharged waste on

-------
site. These sites were added to the NPL in October and March 1989, respectively. The 1991 ROD for
these sites called for SVE to remediate VOC-contaminated soils at both properties and a groundwater
extraction and treatment system located at the SJCC property to address the commingled plume.
Investigations during the long-term response action for groundwater remediation indicated that the SVE
systems used at both sites did not sufficiently address the VOCs in the soil and that these residual VOCs
continued to act as a significant source of groundwater contamination. In September 2010, EPA issued a
ROD amendment which called for, among other actions, acquisition and demolition of the GSC building
and excavation of contaminated soils at both properties.

This pilot was designed to demonstrate efficiencies in time and cost that result from using in-house
(EPA) resources where possible to perform the RDs and RAs for the demolition of the GSC building
and the excavation of the shallow soil contamination at both the GSC and SJCC sites. As a result of the
study, three remedial actions were completed one year earlier than planned and substantial cost savings
were achieved (approximately $485,000) even after considering the in-house payroll costs. The pilot
report may be found at: http://www.epa.gov/oswer/docs/ici/action!7_668687.pdf.

3.0    RD/RA Pilot Project Techniques and  Lessons Learned

In evaluating results, the piloted measures were compared to more traditional approaches to project
management. Results from all three pilots were considered in developing lessons learned that may be
applied more broadly across the Superfund remedial program. A common objective of all of the pilots
was to complete RD and remedial construction activities within a year after the ROD was issued (i.e., by
September 30, 2011). Notably, this goal was achieved for all three pilots.

The following is a summary of the techniques employed and lessons learned from the three pilots and
their potential for broader application to remedial sites. Remedial Project Managers (RPMs) and site
teams are strongly encouraged to consider these techniques as early as possible (even prior to issuance
of the ROD where appropriate) in planning for RD and RA.

       3.1    Early Assurance of RA Project Funding

Of particular significance, OSRTI's'  assurance of RA funding for these projects either before the ROD
was signed (as in the case for the Ellenville site) or soon after (as with the Flash Cleaners, SJCC and
GSC sites) was key in facilitating the regions' ability to accelerate the RD and RA processes. Typically,
projects are delayed (from several to many months) between the RD and the time that RA contractor
procurement begins as sites await "priority" assessment and receipt of RA funding. In all cases, the
early assurance of pilot funding improved overall project management efficiency by allowing project
planning and schedules to reflect project completion rather than interim milestones.

Where early assurance of RA funding for a given project is likely to accelerate site cleanup significantly,
site managers are encouraged to discuss such opportunities with their regional management. It may be
reasonable for a region to request early assurance of RA funding from OSRTI. A favorable OSRTI
decision would depend on a number of factors including the availability of funding and competing
priorities.

-------
       3.2    Project Planning and Management Strategies

Several lessons learned involve early-planning decisions that affect the overarching strategy selected to
address site contamination. These decisions will be shaped by site conditions and engineering challenges
presented by the nature and extent of contamination, and by the availability of program funding, EPA
staff availability and expertise, contract types available, and contract accessibility and capacity.

             3.2.1  Use of in-house resources

       Both headquarters and regional management recognized the benefits of enhancing the traditional
       roles of their staffs for work on the pilots. Using in-house resources saves time and costs by
       avoiding both internal EPA efforts necessary to task a contractor for specific services as well as
       the contractor's cost and other fees.

       For the SJCC/GSC sites, much of the work ordinarily conducted by EPA's remedial action
       contractor (RAC) or the US Army Corps of Engineers (USAGE) was accomplished by EPA
       staff. EPA Region 2's remedial staff prepared streamlined RDs for the soil excavation work for
       both sites. OSRTI's Environmental Response Team (ERT) provided design sampling support to
       refine the assessment of soil contamination. Analytical  support was provided by the Region 2
       laboratory and ERT's fixed and mobile laboratories (both operated by ERT's Scientific,
       Engineering, Response and Analytical Services (SERAS) contractor). Remedial and removal
       program staff prepared a streamlined RD for the demolition of the GSC building. A regional On-
       Scene Coordinator (OSC) directed the ERRS contractor's demolition of the building and soil
       excavations at both properties. The Region's RPM prepared the RA reports for all three
       activities. Comparing the actual costs of the RDs and RAs to a cost estimate for a more
       traditional approach (i.e., a RAC scenario) suggests a cost savings or avoidance of about 50% in
       remedial design costs and 30% in remedial action costs, or about 40% overall. Had the Region
       used a RAC contractor to conduct the design and to procure and manage a constructor, the
       Region may have spent as much as $478,000 more on design and construction costs. The greatest
       dollar savings were realized through the use of in-house staff to conduct RD and RA project
       planning and report preparation. In addition, the use of in-house resources is estimated to have
       accelerated project completion by approximately six months.

       For the Ellenville site, OSRTI assigned a senior RD/RA expert to support the Region and to
       facilitate and coordinate pilot activities at the site. Recognizing that the Ellenville site would
       present a significant challenge due to the areal extent of contamination and the magnitude and
       scope of the remedy, this individual provided "boots-on-the-ground" support. While a customary
       approach  for OSRTI coordination with regional offices may involve only periodic project
       reviews and consultation on selected issues with an occasional (if any) site visit, the OSRTI
       coordinator role for Ellenville involved regular meetings with the site team, and numerous site
       visits during the year-long pilot. Overall, the site team believes this individual was very effective
       in providing much needed support for regional project management activities and in
       troubleshooting issues requiring OSRTI assistance (e.g., funding requests) and as such was
       critical to the success of the pilot.

       For the Flash Cleaners site in Region 4, the Region used its removal  contractor (ERRS) to
       conduct all three components of the remedial action. The RPM served in the role of the OSC and
       oversaw the construction activities associated with the soil and groundwater remedies.
                                               4

-------
Traditionally, construction management and oversight activities are managed by a RAC
contractor or the USAGE. The Region estimates that it may have spent as much as $135,000 (or
27 %) more had a RAC contractor been used for the RAs.

       3.2.2  Strategic use of contract support

Site managers should consider which contracting mechanism may be most efficient given site-
specific circumstances, the nature of the work to be conducted and associated uncertainties.

   Use of preplaced contracts (e.g., RAC, ERRS) for RD and RA can streamline the
   delivery of support services and improve the overall cost effectiveness of projects by
   avoiding the time involved in placing site-specific procurements. EPA considers the
   ability to access rapidly prequalified firms which have significant hazardous waste
   experience and a proven track record on specific types of work such as RD, RA or long-term
   response actions to present significant advantages for Superfund site remediation. In
   particular, preplaced contracts are available for use as EPA's funding becomes available. For
   these reasons, most of the remedial program's contracts are of this nature. The agency's
   acquisition strategies seek to preplace contracts with specific expertise that can be used when
   needed to  support site work. However, not all preplaced contracts are appropriate for every
   type of work. Site managers should consider the specific nature and scope of work to be
   conducted at a given site as well as the timing and availability of funding in planning for
   remediation. In fact, it may be significantly less efficient to use one contract type over
   another depending on circumstances.

   In each of these three pilots, regions relied on preplaced, prequalified contractor support to
   conduct the work. However, site managers used nontraditional  contract types. At Flash
   Cleaners, Region 4 used its RAC contractor to perform the RDs and its ERRS contractor to
   conduct the RA. For the SJCC/GSC sites, Region 2 used ERT's SERAS contract for
   assessment of soil contamination and its own ERRS  contractor to conduct the RAs. For the
   Ellenville pilot, the preplaced contracts used for RD and RA were held by the USAGE and
   were accessed through an Interagency Agreement (IA).

   Use of cost-reimbursable type task orders (e.g., time and materials, indefinite delivery
   /indefinite quantity) can provide important response flexibilities in the field where new
   sources of contamination may be discovered, site conditions may change or challenges
   arise unexpectedly. The cost-reimbursement type contracts used for work under each pilot
   allowed the project teams to respond to changed conditions without the need for contractual
   modifications.

   Use of the ERRS contracts for RA provides the Agency direct access to construction
   expertise  which can reduce or eliminate administrative costs and time associated with
   subcontracting such expertise. Regions 2  and 4 used their preplaced and flexible ERRS
   contracts to accelerate delivery of RA construction services, facilitate real-time site cleanup
   decision making and reduce acquisition expenses. This contract type may be especially
   appropriate for RA activities that are relatively straightforward.  Using the ERRS contract to
   implement the RAs saved time and money when compared, for example, with using the RAC
   for construction. Because the ERRS contract is designed to provide construction services, the
   ERRS contractor performs most of the work (with oversight by EPA) using its own
   construction personnel (e.g., response managers, operators, cleanup technicians). Moreover,
                                        5

-------
          because the ERRS contract is designed to allow EPA to respond quickly, the ERRS
          contractor can mobilize in the field in anywhere from several hours to one or two days
          depending on the scope of work and site circumstances. Also, as work progresses and field
          conditions change due to unanticipated events or new information, the ERRS contract SOW
          can be modified immediately upon need.

          In contrast, the RAC was designed to assist EPA in conducting longer-term activities, such as
          RI/FSs and more complex RDs and RAs, which require developing a more detailed SOW
          and work plan and negotiating the scope and cost of the effort. This may take a week or two
          or more and would require EPA to devote additional staff time as well as pay for the
          contractor for its time during this process. Also, because the RAC was not designed to
          perform construction activities directly, it must subcontract the construction work to another
          firm which requires additional procurement time. Consequently, the RAC process costs the
          Agency more money than it would incur if the ERRS contractor were used, as EPA would be
          paying both contractors to get the work done. Further, as field conditions change or new
          information comes to light, modifications and/or expansion of the SOW must be negotiated,
          a process which may take several days,  or even weeks or more (depending on the changes to
          be negotiated). The discovery and management of the underground storage tanks found at
          both the GSC and Flash Cleaners properties would have taken longer and cost more under a
          RAC scenario since the change in scope and cost would have had to have been negotiated.
          As a result, there were time savings of several months immediately realized by using the
          ERRS contract for this work.

          Use of the RI/FS contractor (e.g., RAC) to conduct the RD may save time and money. For both
          the Ellenville and the Flash Cleaners sites, the RD contracts were awarded to the RAC
          contractor which had conducted the RI/FS. Having these contractors familiar with the sites
          and the nature and extent of contamination saved time in beginning the  RDs.

             3.2.3   Use of parallel (versus sequential) work schedules

       Certain elements of the RD and RA were conducted concurrently at the Flash Cleaners and
       Ellenville sites which both facilitated and reinforced the need for collaboration between the RD
       and RA contractors from design through RA. At Flash Cleaners, the RD contractor prepared the
       soil design separately from the groundwater design which permitted the soil RA to begin as soon
       as the soil design was substantially complete. While the ERRS contractor was on site conducting
       the soil RA, the groundwater RD was completed. The Region then tasked the ERRS contractor to
       implement the groundwater RA. At the Ellenville site, the Region initiated  planning for
       construction during the RD. As a result, the construction contractor was able to identify
       subcontractors and material suppliers, and begin developing the construction schedule  early in
       the project. Further, the RA workplan was prepared during the remedial design. Conducting
       certain elements of the RDs and RAs concurrently may significantly compress the overall project
       schedule for a site.

       3.3    Working Relationships among Project Team Members

A key factor in the success of each pilot was the collaboration, communication and commitment among
partners to achieve the common goals of the project. In general, relationships involving all team
members and partners were developed early and continued throughout the pilot process with the goal of
achieving project completion, rather than individual milestones (such as a specific  activity or project
                                              6

-------
deliverable). Based on the results of the three pilots, RPMs are encouraged to develop strong working
relationships among site team members.

             3.3.1  Collaborative approaches to project completion

       Pilot results suggest that planning for early collaboration among site team members and defining
       expectations for each member were integral to obtaining their commitment to the project, its
       work schedule and its ultimate success.

       For example, at the Ellenville Scrap Iron and Metal site, team members signed an informal
       partnering agreement to foster collaboration, demonstrate commitment and promote shared
       acceptance of project objectives and risk. Signatories included EPA's OSRTI and regional staffs,
       the USAGE and its contractors and representatives of the New York State Department of
       Environmental Conservation (NYSDEC). As part of its commitment, the NYSDEC assigned
       dedicated staff early in the process. This early state involvement avoided schedule delays to
       either meet state requirements or allow for state decision making. Of particular note, was the
       NYSDEC's willingness to ensure that the RD was in conformance with state permit
       requirements. NYSDEC agreed that with approval of the final RD, permit equivalences
       (typically applied for after the final RD is completed) for the RA would be approved as well. The
       RD met the substantive requirements of major permits for a soil erosion and sediment control
       plan, community air monitoring plan, storm water pollution prevention plan (state pollutant
       discharge elimination system), wetlands mitigation and solid waste facility closure.

       As project challenges presented themselves,  the integrated management approach used for the
       Ellenville pilot made decision making a collaborative and more efficient process often avoiding
       problems before they occurred.  The work was also managed to achieve project completion as
       opposed to more traditional interim milestones (e.g., a 65% design document). The team used a
       process called "focused project integration" which allows informed decision making early in the
       project where significant value or savings can be gained.

       At the Flash  Cleaners site, the RPM established collaborative relationships among all site team
       members (including the state and RD and RA contractors) which provided focus on common
       goals, procedures and cleanup outcomes that were consistent with expectations of the team
       members. The site team also worked hard to establish a high level of trust with the  community.
       This facilitated EPA's ability to use innovative approaches (e.g., early planning for RA, use of
       enhanced bioremediation for contaminated groundwater) to  streamline traditional remedial
       action at the  site. Further, the RPM's frequent on site presence demonstrated team commitment
       and dedication to collaborative processes, and it facilitated real-time decision making and the
       ability of the team to react to the unexpected (e.g., newly discovered underground storage tanks).

       At the SJCC/GSC  sites, many team members contributed to the RD and  RA. The regional
       remedial and removal staff, drawing on the services of the ERT and the USAGE, worked closely
       together over a short period of time to accomplish the cleanup. In order to do so, effective
       collaboration and communication among site team members was critical. It facilitated field work,
       development and review of documents, information sharing, and strengthened accountability for
       meeting deadlines. In addition, since the RDs were completed in-house with the RPM and the
       OSC's preparing the building demolition RD and the RPM's preparing the soil excavation RDs,
       these staff were familiar with  the details of the RDs and able to provide RA contractor oversight
       and direction in the field, resolving issues in real time as they arose.
                                              7

-------
              3.3.2  Enhanced communication between RA contractor and RD contractor

       Having team members primarily responsible for RD activities in early and close communication
       with team members providing RA support was a critical element which contributed to the
       success of all three pilots. In fact for all three pilots, team members providing RA support were
       brought on early and those who performed RD activities were available during construction to
       discuss and facilitate resolution of issues.

       At the Ellenville site, the RA contractor was issued a task order for preconstruction services
       shortly after ROD approval. The term "preconstruction services" refers to engaging the
       construction contractor during the RD as opposed to hiring the services of a construction
       contractor after the RD is completed. This approach allows informed decision making early in
       the project where significant value or savings can be gained. Value engineering-like savings (or
       cost avoidance)  were achieved by obtaining input from the construction contractor during the
       design  phase. In addition to the cost avoidance, the schedule was accelerated as a result of the
       early constructor involvement.

       At Flash Cleaners, the  Region tasked the ERRS contractor to provide comments on the 90% RD
       for the  soil remedy and to begin scoping work for remedy construction. In fact, before the 100%
       soil RD was approved, the RA contractor had prepared the site-specific health and safety plan,
       met with the RPM and RD contractor to discuss remedy implementation, completed the
       subcontractor award process for drilling of the SVE wells and completed the soil excavation and
       backfilling, thereby advancing the start of the soil remedy by six weeks. In other words, the 90%
       RD was judged  sufficient to permit both the start and completion of the soil excavation and
       backfilling portions of the soil remedy. The Region also specifically tasked its RD contractor to
       be on site during the soil and groundwater RA activities to assist the RPM during construction in
       resolving any issues that arose.

       At the SJCC/GSC sites, Region 2's RPM and OSC worked closely throughout the year-long pilot
       planning the work schedule, collaborating on the RDs and overseeing construction activities.
       This facilitated discussion and resolution of issues that arose during the project.

       3.4    Project Risk Management  Techniques to Minimize Unexpected Delays

Each site presents a number of site-specific project management challenges that are unique to the nature
of work required for remediation and the time it will take to achieve project completion. These include
unanticipated events or circumstances that may occur as work progresses that can delay the project
schedule.  Examples are unexpected increases in contaminant volumes, the discovery of underground
storage tanks or contaminant sources and extreme weather events. The impact of such delays can be
minimized by anticipating their potential occurrence and planning appropriate response  strategies and/or
ensuring that appropriate expertise is available to assist should unexpected circumstances arise. Such
contingency planning should be tailored to the complexity of site work.

For example, the Ellenville project team utilized a collaborative process that identified potentially
adverse events, estimated likelihood of their occurrence, quantified the potential impact of the events on
the project, and developed mitigation strategies in advance of their potential occurrence. These
risk/response scenarios  were tracked and updated as site work progressed. A "risk register" was used to

-------
summarize and display these scenarios for all team members. Scenarios addressed environmental,
external, engineering/design, construction and project management risks. Time was set aside regularly to
discuss these risks and update mitigation scenarios. As a result, when unexpected situations were
encountered in the field, appropriate response decisions could be made in an expedited fashion based
upon the scenarios outlined in the risk register. Several scenarios identified in the risk register occurred
during construction at Ellenville. These included, among other things, the discovery of battery casings in
an unanticipated location (beneath an on  site residential structure), increases in contaminant volumes,
the unexpected discovery of a buried tanker truck and an extreme weather event (hurricane-force winds
and rain). The site team estimated that the mitigation strategies in place as a result of the risk register
minimized schedule impacts by approximately one month, a significant amount of time given the pilot's
duration of just over one year.

At the Flash Cleaners, SJCC and GSC sites which represented less complex remediation challenges,
while such risks were anticipated, the mitigation strategies were tailored to the complexity of site work.
For these sites, project risk management strategies relied on use of cost reimbursable task orders. This
approach allowed the on site RPM, OSC  and ERRS contractors to respond to unexpected circumstances
without the traditional administrative requirements associated with use of a RAC contract. For example,
underground storage tanks were discovered at both the Flash Cleaners and GSC properties but were
addressed through the use of the ERRS contractors with only minimum delay for the on site team and
without the need for lengthy administrative adjustments to the contract SOW.

       3.5     Streamlined Remedial Design

Several  measures  were utilized successfully to streamline the RD process and compress the delivery
schedule thereby saving time and money for these projects. As a result, site managers are encouraged to
consider their application at other sites, where appropriate.

          3.5.1   Tailoring the RD to the specific needs of the project

       For all three pilots, the design process was compressed and certain intermediate RDs were not
       prepared which saved time and cost in the preparation and review of these documents.  In
       addition, for the SJCC and  GCS pilot, the project team decided to eliminate the preliminary RD
       as well. This was possible primarily as a result of the close working relationships established
       among project team members and their common commitment to completion of the project (rather
       than deliverables). These close project team relationships facilitated the elimination of
       unnecessary  standard deliverables and review loops and ensured focus of needed deliverables on
       project-specific requirements. In addition, at the Flash Cleaners site, the RD was split into two
       parts, one  for soil and the other for groundwater. This permitted the RA activities for soil to
       begin as soon as the RD for soil was substantially complete, and while the RD for groundwater
       continued.

          3.5.2   Abbreviating RDs

       As a result of the nature of the work, the Ellenville, SJCC/GSC and Flash Cleaners pilots applied
       the concept of "just enough design" and included only the specifications and details necessary
       for the specific actions, rather than the more detailed specifications traditionally discussed in
       generic guidance.

-------
          3.5.3   Beginning the design process prior to finalizing the ROD

       Beginning basic pre-design tasks as the ROD is finalized shortens the time needed to finalize the
       design and begin RA once the ROD is issued.  Therefore, thought should be given as early as
       possible to the best mechanism for conducting different components of the RD. For example, for
       the Flash Cleaners site, Region 4 awarded the  RD contract and began the RD while preparing the
       ROD. The Region tasked its RAC contractor which had performed the RI/FS to conduct the RD,
       because this contractor was already familiar with the site.  Similarly, for the Ellenville pilot, EPA
       entered into an IA with the USAGE to initiate  the RA constructor procurement prior to issuing
       the final ROD.1 The RD was completed within six months of the fmalization  of the ROD (a task
       that might have taken a year or longer under a more traditional scenario). It is important to note
       that such  early planning is generally only possible where and when there is high confidence that
       changes to the proposed remedy are unlikely (e.g., when there are few viable  remedial options,
       where there is confidence that a particular overarching remedial strategy is favored by
       stakeholders, and/or when comments on the proposed plan have been evaluated and are judged
       not likely to impact such early planning).

       3.6     Sampling Strategies

The SJCC/GSC, Flash Cleaners and Ellenville pilots utilized several time-saving sampling strategies
which may also be appropriate to use at other sites.

          3.6.1   In-field analysis for quick data turnaround

       At the SJCC/GSC sites, as part of the RD sampling, the ERT was asked to delineate the extent of
       soil contamination in order to estimate the volumes  of soil to be excavated at both sites.  Having
       the ERT's mobile laboratory on site shortened the turnaround time for analytical results and
       facilitated the collection and analysis of additional samples when needed to complete design
       drawings.

          3.6.2   End point sampling to avoid post-excavation confirmatory sampling

       At the onset of the RAs for the soil excavations at the SJCC/GSC sites, end point  samples were
       collected  to establish the cut lines for the excavations using the "computer aided design and
       drafting"  (CADD) drawings as a guide.  Similar work was conducted at the Flash  Cleaners site.
       In both cases, samples were  analyzed prior to excavation to determine if soil concentrations met
       the soil cleanup criteria. The term "end point sampling" refers to the process by which sample
       locations  are selected to define the boundary or outline of the area to be excavated. Sample
       collection and analyses are performed before excavation begins. If the soil sample concentrations
       meet soil  cleanup criteria, the excavation can proceed to the predefined boundaries and post-
       excavation confirmatory sampling would not be required. In  addition, as an extra measure to
       ensure the excavation boundary is completely  defined before excavation begins and thus to avoid
       the possible need for a second round of sampling, a  second set of samples may be obtained at the
       same time as the first set, a few feet beyond the excavation area identified on the design or
       CADD drawings. The second set of samples is also  sent to the laboratory but not analyzed until
       the results from the first set of samples are received. If data from the first set of samples indicate
1OSRTI directed USAGE to initiate the RA constructor procurement under an IA prior to the ROD; however, the region
initiated the procurement for RD on the date of ROD signature.
                                              10

-------
       that soil concentrations meet the cleanup criteria, then the second set of samples is not analyzed.
       If any of the first set of samples indicates that soil cleanup criteria are not met, then selected
       samples from the second set are analyzed. This approach allows the cut lines to be clearly
       defined before the excavation proceeds. Collecting all of the samples before excavation keeps the
       field sampling team's time to a minimum and avoids the need for a second mobilization. For the
       work at SJCC/GSC, only a few of the second set of samples required analysis to ensure that
       cleanup numbers were achieved.

       At the Ellenville site, during the RD, endpoint sampling was used whenever possible in
       characterizing the extent of contamination. This was  done to prevent delays in landfill cap
       construction and the backfill of excavated areas while waiting for confirmatory results from the
       laboratory. This approach contributed significantly to the completion of RD activities in six
       months, a task that might have taken a year or longer otherwise.

          3.6.3  Early sample analysis for waste acceptance

       At the SJCC/GSC sites, in order to expedite the off-site disposal process and ensure the
       excavated soil would meet the waste acceptance criteria of the disposal facility, samples were
       also collected from areas of the sites where elevated concentrations of VOCs were identified.
       These samples were collected at the beginning of the RAs  and submitted to a state-certified
       laboratory for analysis to ensure that the excavated soil would be accepted by the waste disposal
       facility.

       Performing analyses on site and conducting end point sampling and waste acceptance sampling
       at the same time (prior to beginning excavation), can minimize the number of sampling events,
       reduce analytical costs and expedite the excavation and backfilling process and completion of
       RA activities.

4.0    Conclusion

This paper summarizes the lessons learned from conducting  three RD/RA pilot projects at NPL sites
which were selected to demonstrate new techniques or best practices for the management of fund-lead
remedial projects. As demonstrated by these pilots, managing a site remediation project with a focus on
its completion (rather than on interim milestones) can allow  RPMs to structure a project delivery
approach with greater efficiency, placing many activities on  parallel or staggered schedules as opposed
to linear or sequential tracks. For each of these pilots, regions accelerated the RD and RA and realized
significant cost efficiencies for their sites.

Projects were selected based on their manageable scope, a requirement for only moderate financial
resources and a reasonably short project duration time frame (e.g., one to two years). Measures explored
by the pilot studies included new strategies  involving project planning and management, increased use
of in-house resources, strategic use of contractor support, improved sampling efficiencies, enhanced
collaboration and communication among project team members and compression of traditional remedial
process components.

Results of the pilot studies demonstrated that significant time savings (estimated to be as much as 67%
over traditional project duration) may be gained depending on project scope, the areal extent of
contamination and site complexities. In addition, savings or cost avoidances ranging between

                                              11

-------
approximately $135,000 and $584,000 were estimated for these pilots. These values represent
significant savings given the work undertaken for these projects.

Site teams are strongly encouraged to consider these project management approaches as early as
possible in planning for RD and RA activities. Where early assurance of RA funding or other
headquarters resources for a given project is likely to accelerate site cleanup significantly, site managers
are encouraged to discuss such opportunities with regional management to decide whether to request
such support from OSRTI.  A favorable OSRTI decision would depend on a number of factors including
the availability of funding, the availability of appropriate in-house expertise, and competing priorities.

When considering the application of these measures at other sites, site-specific reviews will be necessary
because not  all of the approaches explored are appropriate for all sites. It is also noted that certain
approaches will require increased focus and effort on the part of the EPA site manager, regional
management, headquarters, contractors and states. These added resource demands should be considered
alongside the advantages of an accelerated cleanup for the community, the region and the national
program. Lastly, while these pilots  were conducted on fund-lead sites, many of the measures may have
value and could result in cleanup efficiencies at sites where cleanups are undertaken by private parties or
federal facilities.
                                               12

-------