SUPERFUND
                                                                        Cleaning Up New England
                                                                                  PROPOSED PLAN
                       Nyanza  Chemical  Waste  Dump
                       Sudtury River,  MA
                       U.S.  EPA  |  HAZARDOUS WASTE  PROGRAM AT  EPA  NEW  ENGLAND
                                                          THE    SUPERFUND    PROGRAM   protects   human
                                                          health and the  environment by locating,  investigating,  and  cleaning up
                                                          abandoned hazardous waste sites and engaging communities throughout
                                                          the process. Many of these sites are complex and need long-term cleanup
                                                          actions. Those responsible for contamination are  held liable for cleanup
                                                          costs.  EPA strives to return previously contaminated land and ground-
                                                          water to productive use.
   YOUR  OPINION  COUNTS:
   OPPORTUNITIES TO COMMENT  ON THE PLAN
   EPA is accepting  public  comment on this
   proposal from June 25 2010 through July 26,
   2010. The following two public informational
   meetings will include a presentation describing
   the proposed plan, followed by a question and
   answer session.

   A supplemental  public informational meeting
   will focus on the computer model (its calibra-
   tion, sensitivity,  and sources of uncertainty)
   that was developed to evaluate different
   remedial alternatives.

   EPA will begin a formal 30-day public  com-
   ment period. A  Public Hearing has  been
   scheduled for 7:00 p.m.  Monday, July 19,
   2010 at the Framingham Town  Library
   and the public has an opportunity to make
   oral comments for EPA to consider. You may
   also submit written comments - see page  11
   to find out how.
                            Public Informational Meeting - Sudbury
                            Monday, June 21, 2010 at 7:00 p.m.
                            National Wildlife Refuge Complex (GMNWR)
                            73 Weir Hill Road, Sudbury, MA

                            Public Informational Meeting - Framingham
                            Tuesday, June 22, 2010 at 7:00 p.m.
                            Framingham Town Library
                            49 Lexington Street, Framingham, MA

                            Informational Meeting on Computer Modeling
                            Thursday, June 24, 2010 at 7:00 p.m.
                            National Wildlife Refuge Complex (GMNWR)
                            73 Weir Hill Road, Sudbury, MA

                           For further information about these meet-
                           ings, call Jim Murphy of EPA's Community
                           Affairs office at (617) 918-1028, or toll-free at
                           1-888-372-7341,

THE  PROPOSED  PLAN
AT  A  GLANCE

After careful study of the impacts of mercury
released to the Sudbury River from the Nyanza
Chemical Waste Dump  Superfund site,  and  in
consideration of the contaminant  reduction ac-
complished by cleanup activities at other parts
of the site, EPA proposes the following cleanup
actions for the Sudbury River,  which EPA has
defined as "Operable Unit 4" (or "OU4") of the
Nyanza site. This Proposed Cleanup Plan address-
es mercury contamination  in fish  tissue, which
is where mercury from the river accumulates.
These contaminated fish pose an  unacceptable
health risk to recreational anglers who consume
them. There are no other unacceptable risks to
humans or to animals and plants in the river. Con-
sistent with actions at other contaminated sedi-
ment sites, this proposed cleanup  plan relies on
a combination  of different cleanup alternatives
that apply only to specific "reaches" of the river
(refer to the attached map). The Proposed OU4
Cleanup action consists of:
                             continued >
KEY CONTACTS:
DANIEL KEEFE
Project Manager
(617) 918-1327
keefe.daniel@epa.gov

JIM MURPHY
Superfund Community
Involvement
(617) 918-1028
murphy.jim@epa.gov

DAVID BUCKLEY
MassDEP Project Manager
(617) 556-1184
david.buckley@state.ma.us
GENERAL INFO:
EPA NEW ENGLAND
5 Post Office Square
Suite 100
Boston, MA 02109-3912
(617) 918-1111
www.epa.gov/region 1/

TOLL-FREE
CUSTOMER SERVICE
1-888-EPA-7341
&EPA
United States
Environmental Protection
Agency New England
  printed on 100% recycled paper, with a minimum of 50% post-consumer waste, using vegetable-based inks
                       EPA-901-F-00-000
                             June 2010
                                                                                                 SDMS DocID 466645

-------
SUPERFUND   |  HAZARDOUS  WASTE  PROGRAM AT  EPA  NEW  ENGLAND
                PROPOSED  PLAN
    INTRODUCTION  &  HISTORY

    The Nyanza Site was occupied from  1917 through 1978 by several companies that manu-
    factured, among other things, textile dyes  and dye  intermediates. During the period of
    operation, large  volumes of chemical waste were disposed in  burial pits, below ground
    containment structures, and various lagoons scattered throughout the "Hill" section of the
    site. Wastes included partially treated process water,  chemical sludge, solid process wastes,
    solvent  recovery distillation residue,  numerous organic and inorganic  chemicals including
    mercury, and other products. Process chemicals that could not be reused or recycled
    were also disposed of on-site or discharged  into the Sudbury River through a small stream
    referred to as Chemical Brook.

    Mercury was used as a catalyst in the production of textile dyes from 1917 to 1978. Ap-
    proximately 2.3 metric tons (2,300 kg) of mercury were used per year from 1940 to 1970,
    with a total of 45 to 57 metric tons of mercury released to the Sudbury River during this
    period.  From 1970 until the facility closed in 1978, wastes were treated on-site and waste-
    water was discharged to Ashland's town sewer system. These revised treatment practices
    reduced the quantity of mercury released to the Sudbury River to between 23 and  30 kg
    per year or about 200 kg (440 pounds) during the final eight-year period.

    In  1982, the Nyanza site was placed on the  National  Priorities List (NPL) by the U.S. EPA.
    EPA has since divided the site into four  operable units, or OUs. This  division into  OUs
    has allowed EPA to have different teams work separately on  discrete parts  of the site.
    OU1 consists of the former Nyanza plant, inclusive of the landfill at the site; OU2 addresses
    contaminated groundwater;  OUS  addresses  contamination  in  the  Eastern Wetland,
    Chemical Brook, Trolley Brook and Outfall Creek; and OU4 addresses contamination in
    the Sudbury River.

    EPA has completed the cleanup actions selected for OU 1 (consolidation of sludges under an
    impermeable cap) and OUS (removal of contaminated sediments in the wetland, brook and
    creek). Cleanup work is  ongoing at OU2 (extraction of contaminants from groundwater
    and installation of systems to mitigate vapors that might otherwise pass from contaminated
    groundwater into overlying homes). The cleanup action proposed in this plan is for  OU4,
    the Sudbury River.

    EPA has been studying the Sudbury River since the mid-1990s, issuing several research
    papers, three risk assessments, a computer model that shows how mercury moves through
    the river into fish, and most recently the feasibility study that led to this proposed plan.
    Because OU4 is large - the river spans 26 miles from the Nyanza site to its confluence with
    the Assabet River - the study area was divided into  10 "reaches." A "reach" typically rep-
    resents a section of the river with a specific  set of hydrological properties - an  impounded
    area, a fast flowing  area or, in the case of Great Meadows National  Wildlife refuge, an
    expansive wetland.
    Enhanced Natural Recovery (ENR)
    consisting of the addition of a 6-inch
    layer of sand in a portion of Reach 3
    (i.e., Framingham Reservoir 2) with the
    highest levels of mercury contamination
    in sediment. The addition of a sand layer
    effectively accelerates natural recovery
    processes by which contaminated
sediment are normally buried and
diluted.

Monitored Natural Recovery (MNR) in
other reaches of the river. Throughout
much of the river, fish are expected to
become safe for regular consumption
within a reasonable timeframe through
     natural recovery and without any active
     remediation; EPA would continue to take
     samples to monitor this progress.

  •  Limited Action for Reach 8 including
     monitoring of contamination levels in fish
     to insure they are stable or declining,
     even if they do not decline to levels that
     would permit regular consumption by
     recreational anglers.

  •  "Institutional Controls" throughout the
     river - i.e., community outreach as well
     as posting and maintenance of signs
     advising against fish consumption where
     fish  are unsafe for regular consumption.
     There are currently multiple State fishing
     advisories due to mercury.

 •   No Action for Reaches 5 and 7 since
     there are no unacceptable risks to either
     a child or an adult recreational angler in
     these reaches.

  •  Reviews will also be conducted every
    five years to evaluate the effectiveness
     and  adequacy of the remedial measure.

The cost of the proposed remedy is estimated at
$8.5 million. A more detailed description of the
proposed plan begins on page 7.

EPA  is also seeking comment on  EPA's finding
that  the  cleanup represents the least-damaging
practical alternative  regarding potential impacts
to the aquatic environment in and around the
river.  Page 9 contains more  detail regarding
this  finding. This Proposed  Plan  summarizes
parts of the Draft Feasibility Study. The entire
text  of the  Feasibility Study  can  be  found at
www.epa.gov/region1/superfund/sites/
nyanza.  In September 2010,  EPA expects to
have reviewed all public comments and will  issue
a Record of Decision (ROD) describing the  cho-
sen cleanup  plan. The  ROD and a summary of
responses to public comments will then  be made
available to the public via the internet and at the
site information  repositories and at the Ashland
Public Library.

In  accordance  with the Comprehensive  Envi-
ronmental  Response,  Compensation,  and Li-
ability Act (Section 117), the statute which cre-
                                                                                                                                page 2

-------
SUPERFUND  |   HAZARDOUS WASTE  PROGRAM  AT  EPA NEW  ENGLAND
                                                                    PROPOSED  PLAN
                                                             Remedial Alternatives Summary
                                                        Nyanza Chemical Waste Dump Superfund Site
                                                             Operable Unit 4 - Sudbury River
                                                                Ashland, Massachusetts

Alternatives
Alternative 1
Alternative 2
Alternative 3A
Alternative 3B
Alternative 3C
Alternative 4A
Alternative 4B
Alernative 5A
Alternative 5B
Alternative 5C
Alternative 5D
Remedial Action
No Action
Limited Action (LA)
Sitewide Monitored Natural Recovery (MNR)
Enhanced Natural Recovery in Reach 3 > 10ppm
Enhanced Natural Recovery in Reaches 3, 4 and
6 > 2ppm
In Situ Containment in Reach 3
In Situ Containment in Reaches 3, 4 and 6
Dredging > 10ppm in Reach 3
Dredging > 10ppm in Reach 3, In Situ Capping in
Reaches 3, 4 and 6
Dredging > 2ppm in Reach 3
Dredging > 2ppm in Reaches 3, 4 and 6
Sudbury River Reaches
2
NA
LA
MNR
MNR
MNR
MNR
MNR
MNR
MNR
MNR
MNR
3
NA
LA
MNR
Thin Layer
Placement
Thin Layer
Placement
Capping
Capping
Partial
Removal
Partial
Removal/
Capping
Removal
Removal
4
NA
LA
MNR
MNR
Thin Layer
Placement
MNR
Capping
MNR
Capping
MNR
Removal
5
NA
LA
NA
NA
NA
NA
NA
NA
NA
NA
NA
6
NA
LA
MNR
MNR
Thin Layer
Placement
MNR
Capping
MNR
Capping
MNR
Removal
7
NA
LA
NA
NA
NA
NA
NA
NA
NA
NA
NA
8
NA
LA
LA
LA
LA
LA
LA
LA
LA
LA
LA
9
NA
LA
MNR
MNR
MNR
MNR
MNR
MNR
MNR
MNR
MNR
10
NA
LA
MNR
MNR
MNR
MNR
MNR
MNR
MNR
MNR
MNR
  Notes:

  1) Reach 1 is upstream of the Nyanza source area and therefore is not included in this summary.
  2) Since there was no actionable risk identified for Reaches 5 and 7 they are not included in this summary.
  Hg = total mercury
  MeHg = methylmercury
  mg/kg = milligrams per kilogram
  MNR = Monitored Natural Recovery
ated EPA's Superfund program, and the National
Contingency  Plan  Section  300.430(f)(2), this
document summarizes EPA's  cleanup proposal.
For detailed information on the options evaluat-
ed for the site, see the Feasibility Study available
for review at the information repositories at the
Ashland Town Library and EPA's Five Post Office
Square office in Boston.
MERCURY:
WHERE  IT COMES  FROM,
WHAT  IT  DOES

Mercury in the environment comes from specific or
"point" sources such as Nyanza, from atmospheric
sources,  and from other  diffuse  or  "non-point"
sources. Combustion of municipal solid waste and
combustion  of fossil fuels for power generation are
prime examples of atmospheric sources of mercu-
ry. Nationally, the northeast has been recognized
as an area of increased atmospheric deposition of
mercury. Recently there have been significant re-
gional and federal efforts to limit non-point sources
of mercury, including  EPA's  Clean Air  Mercury
Rule, which creates performance standards and
establishes  permanent, declining caps on mercury
emissions.
                                                                                                                                           page 3

-------
SUPERFUND   |  HAZARDOUS  WASTE PROGRAM  AT  EPA  NEW  ENGLAND
                                                                  PROPOSED  PLAN
Despite these efforts, mercury remains present in
the environment at levels that have led the Massa-
chusetts Department of Public  Health (MassDPH)
to maintain a State-wide fishing advisory. The State-
wide advisory warns  children  and women who
are or may become pregnant (i.e., the populations
most sensitive to mercury) not to consume fish
from any body of fresh water in the State.

At the Sudbury  River, the former Nyanza facility
presents an additional source of mercury. Thus, the
concentration of mercury in the Sudbury River sed-
iment (and as methylmercury in the surface water
and fish) is a combination of mercury from historic
Nyanza discharges as  well as  more recent atmo-
spheric deposition. Since 1986, in addition to the
state-wide fish advisory, MassDPH has established
a Sudbury River-specific fish advisory, which warns
all segments of the population (not just children and
women who are or may become pregnant) against
consumption offish from the Sudbury River. Both
advisories remain in effect today.
HOW  MERCURY AFFECTS
YOUR  HEALTH

There  are several  different  types of mercury.
Although   some   are   more  dangerous  than
others, all are toxic. While mercury does not pres-
ent a cancer risk to human health,  it does  have a
number of non-cancer health affects. Depending on
the type and amount, exposures to mercury can
damage the nervous system,  brain, kidneys, liver
and immune system. One form of mercury, meth-
ylmercury, is extremely poisonous and can damage
the brain even at low levels of exposure. Children
are most sensitive to mercury toxicity The devel-
oping brains and nervous systems of children are
very sensitive to mercury and may be  irreversibly
damaged by it. Children and adults can be exposed
to methylmercury by eating certain types of fish.
Children can also  be exposed to mercury in the
womb  if their  mothers  eat foods contaminated
with this toxin. Because  of the high sensitivity to
developing children, mothers who are pregnant, or
may become pregnant, are similarly at an increased
risk for  negative health effects from the consump-
tion of mercury-contaminated fish.
The concentration of mercury in fish and the associ-
ated risk to humans from consumption offish is not
directly proportional to the concentration of total
mercury in sediment. Most of the mercury that is
absorbed by fish is mercury that has combined with
organic matter in the river to form methylmercury,
a compound  which is more "bio-available" (and
more toxic) than pure mercury.  Certain parts of
the river are more efficient than others at convert-
ing pure or elemental mercury into methylmercury
- for example, the expansive wetlands in the Great
Meadows  National Wildlife  Meadows (Reach 8)
are an environment that is particularly efficient at
converting elemental mercury into the methylmer-
cury that tends to end up in fish tissue. This means
that fish in this part of the river have relatively high
mercury (i.e.,  methylmercury) concentrations even
though the sediment there is far less contaminated
than the sediment in other parts of the river.
RISK  -  WHY  IS CLEANUP
NEEDED?

The only significant site-related risk to humans comes
from consuming mercury-contaminated fish on a fre-
quent basis (i.e., more than 25 meals per year). In a
risk assessment completed in 1999, EPA determined
that direct contact (e.g., swimming, wading, walking)
or incidental  ingestion of mercury in surface water
or sediment was well below the level that would con-
stitute a significant risk to human health. EPA also
determined in a prior assessment that there were
no other Nyanza-related contaminants in the river
other than mercury that might constitute a signifi-
cant risk to humans.

The  human  health risk from the consumption of
mercury-contaminated  fish was reported  in  the
2006 Supplemental Human Health Risk Assessment
and other follow-up studies.  In EPAs determination
of human  health risk, the average concentration of
mercury in fish within each reach was measured. This
was done by collecting 10 bass, 10 perch, and 10
catfish from each reach - more  than 300 fish from
all 10 reaches. These particular species offish were
used because they are caught frequently and are tar-
get species for  consumption. The human health as-
sessment also includes exposure assumptions - that
is, how much fish a person might eat in a year. Us-
ing data from comparable studies in Maine, EPA as-
sumed that a recreational angler; that  is, the person
most likely to eat the most fish taken from the river,
would eat 50 fish meals per year, half of which would
come from the Sudbury River. This  assumption is
conservative - for example, it assumes that children
would consume fish at this frequency  notwithstand-
ing the state-wide fish advisory that warns children and
women who are or might become pregnant from eat-
ing any fish caught in any freshwater body in the State.

The risk assessment also calculated risks to subsis-
tence anglers - people assumed to rely on fish from
the Sudbury River for all or most of their protein in-
take. However,  because EPA has found no evidence
of subsistence fishing in the Sudbury River, EPA has
decided  not to base cleanup decisions on subsistence
fishing scenarios.

EPA  uses standard toxicological data  and other as-
sumptions (e.g., human body weight, fish filet weight)
to develop reach-specific "hazard  index" (or "HI")
figures for non-cancer effects on human  health; one
for a child and one for an adult,  based on consump-
tion offish caught from each reach of the river. The
higher the HI, the higher the risk. Generally, an HI
greater than 1.0 indicates an unacceptable exposure
from eating fish in a given reach. The His for each
reach for both children and adult recreational anglers
are listed in the table below:
               Hazard Index
                      C
     Reach 1*
     Reach 2
     Reach 3
     Reach 4
     Reach 5
     Reach 6
     Reach 7
     Reach 8
     Reach 9
     Reach 10
 *Reach 1 is upstream of the Nyanza site and is one
 of two reference areas.
1.0
1.8
2.1
1.3
0.9
1.3
1.0
1.3
1.5
1.4
0.5
1.0
1.2
0.7
0.4
0.7
0.5
0.7
0.9
0.7
                                                                                                                                       page 4

-------
SUPERFUND  |  HAZARDOUS WASTE  PROGRAM  AT  EPA  NEW  ENGLAND
                                                               PROPOSED  PLAN
In  general,  risks  throughout the river are low;
Reach 3 (Framingham Reservior 2) presents the
greatest risk. Specifically Reaches 2, 3, 4, 6, 8, 9,
and 10 were found to  pose varying  degrees  of
risks to a child  recreational angler. Only Reach 3
was found to pose an unacceptable risk to both
a child and adult recreational angler. The  maxi-
mum  HI  for children was 2.1  and attributable
to fish caught and consumed from Reach 3. The
His for the other reaches were between  1 and
2,  with Reaches  1, 5, and 7 at or below 1.0 for
children and adults.

EPA also evaluated whether contamination  in
the river poses an unacceptable risk to the en-
vironment - that is to say animals which inhabit
or utilize the river - and found that it did not
pose a risk. The  2008  Final Supplemental  Base-
line Ecological  Risk Assessment reports the re-
sults of these studies. The assessment measured
the concentration of mercury in various media
(blood, feathers,  eggs)  for animals living in the
Sudbury River  watershed as well as those which
reside in sediment  (crayfish and mussels) and
surface water (fish). These concentrations were
then compared to literature values - i.e., values
in  published research found to have "no effects"
or "low effects" on certain species. The majority
(225 out of more than 229 measurement end-
points) of the concentrations from the Sudbury
River samples were either below the "no effects
level" or below the "low effects level."  Thus, the
ecological  risk  assessment concluded that con-
tamination in the Sudbury River is not likely  to
result in population-level risk to animals or  other
organisms in or adjacent to this resource.
RISK SUMMARY:

  •  The only significant risk to human health
     is from eating fish contaminated with
     mercury, except in Reaches 5 and 7
     where there are no risks to human
     health. There is also no significant risk to
     animals or other organisms in or
     adjacent to the river.

  •  There are  no risks to human health  from
     direct contact  (e.g., swimming, wading,
     walking) or incidental ingestion of
     mercury in surface water or sediment in
     any part of the river.

     EPA assumes that the maximum reason-
     able exposure  to mercury is to a child
     and adult recreational angler, who is
     assumed to consume 50 fish meals per
     year, half of which are assumed to come
     from the Sudbury River, consisting of
     equal parts of  3 local species (bass,
     perch and catfish)

     Based on the preceding, a likelihood of
     adverse health effects for the following
     receptors were documented:
         X   to a child (in 7 reaches); and
         X   to an adult (in  1  reach).
REMEDIAL  ACTION
OBJECTIVES  FOR
SUDBURY  RIVER

EPA has determined that the risk to recreation-
al anglers is an unacceptable threat to human
health. The OU4 Feasibility Study was devel-
oped to identify cleanup options to address
this threat. A first step in this process was to
develop remedial action objectives (RAOs) -
goals by which cleanup alternatives identified
in the Feasibility Study can be evaluated. The
RAOs for the Sudbury River are (1) to prevent
the ingestion of mercury-contaminated  fish to
the extent that such ingestion would result in
an unacceptable risk to human health; and (2)
to reduce the amount of mercury available to
fish in sediment and/or surface water to ensure
mercury concentration in fish tissue no longer
presents an unacceptable risk, except in Reach
8. According to the risk calculations described
above, mercury concentrations in fish must
be reduced to 0.48 parts per million  (ppm, or
milligrams  per kilogram) to avoid unacceptable
risks to a child recreational anglers, the most
sensitive population.

The first RAO focuses on  mercury concentra-
tions in fish, because the only unacceptable risk
is from consumption of these fish; prevention of
consumption  is one way to  achieve the neces-
sary risk reduction. The second RAO focuses on
Sudbury River
 sediment and/or surface water. This is because
 sediment cleanups are one of the more effective
 ways (apart from discouraging fish consumption)
 of cleaning up surface water, which in turn is es-
 sentially the  only way  to make  fish tissue less
 contaminated and safe for human consumption.

 This second  RAO has  an exception for Reach
 8, the Great  Meadows Wildlife  Refuge. In this
 reach, sediment concentrations are low (gener-
 ally between 1 and 3 ppm), yet fish tissue con-
 centrations remain marginally above safe levels
 (HH1.3  for a child angler).  EPA believes that
 the risk in  Reach 8 is largely attributable not to
 Nyanza  mercury in  sediment, but a)  to ongo-
 ing mercury deposits from the atmosphere and
 other non-point sources and b) to the chemical
 and  biological conditions in this wetland, which
 convert  even  small amounts of mercury in the
 reach into  significant concentrations of methyl-
 mercury in fish. In fact, it appears that even  if
 natural  recovery processes eliminated unaccept-
 able risks to human health attributable to Nyan-
 za-related  mercury, fish from this Reach might
 still be unsafe to eat due to ongoing atmospheric
                                                                                                                                 page 5

-------
SUPERFUND  |  HAZARDOUS  WASTE  PROGRAM  AT EPA NEW  ENGLAND
                                                               PROPOSED  PLAN
pollution. On this basis, EPA has determined that
it is inappropriate to clean up sediment and/or
surface water in Reach 8, because doing so is un-
likely to significantly reduce fish tissue concentra-
tions.  EPA's only goal in Reach 8,  therefore,  is
the first RAO, which aims to prevent ingestion of
contaminated fish,

EPA  believes that, over time,  risks in Reach  8
from  Nyanza-related  contamination should at-
tenuate,  but hydrological factors  make fish in
this reach vulnerable to even small  amounts of
mercury contamination, whether from the atmo-
sphere or other non-point  sources. As part of
its proposed remedy for the river, EPA will con-
tinue to monitor fish tissue data to ensure that
fish tissue concentrations in Reach 8 decrease or
at least remain more or less stable over time.
EPA will also ensure that institutional controls
remain in place to advise against consumption of
contaminated fish.
DESCRIPTION  OF  CLEANUP
ALTERNATIVES  FOR THE
SUDBURY  RIVER

In  the Feasibility Study  (FS) EPA considered a
full range  of options to address contamination
and risks at a  Superfund site before selecting a
remedy Only those alternatives that meet EPA's
threshold criteria of protecting human health and
complying with other  environmental  laws are
summarized below, except that a "no action" al-
ternative is also presented as a  baseline. A more
detailed description and analysis of each  alter-
native developed is presented  in the Feasibility
Study, which is also available for public comment.

The cleanup options, or remedial alternatives, that
were  evaluated in detail and were considered for
the Sudbury River are summarized below.

Alternative 1: No Action
The No Action alternative would not involve any
type of work other than Five Year Reviews (i.e.,
reports every five years  by EPA on conditions in
the river). No monitoring data would be generat-
ed and no institutional controls (beyond those in
existence) would be implemented to  potentially
reduce or limit the consumption of contaminated
fish. EPA is required to evaluate this alternative
by EPA's Superfund regulations, so as to provide
a baseline for comparison to other alternatives.
Alternative 1 Cost: $ 0

Alternative 2: Limited Action
The Limited Action alternative  is the same as
Alternative 1, but relies on institutional controls
               Sudbury River
- e.g., posting offish advisory signs, public out-
reach and education - as a means of discourag-
ing fish consumption and thereby reducing the
risk to human health and may include monitor-
ing. There are naturally-occurring processes that
are expected to reduce mercury concentrations
in sediment and ultimately to reduce concentra-
tions of mercury in fish. These processes include
physical  processes  (sedimentation and burial of
contaminated  sediments)  and  biological  (bio-
degradation)  and chemical (sorption) processes
that act together to reduce the risk posed by a
contaminant.  In most reaches, fish contamination
would decline to acceptable levels within a rea-
sonable  timeframe - i.e., within  approximately
30 years through these natural  processes.  But
in Reach 3  it is expected to take more than 70
years, and  in Reach 8 fish contamination  is ex-
pected to  remain at unacceptable levels  for  a
much longer period of time due to atmospheric
sources  of mercury.
Alternative 2 Cost: $ 192,000

Alternative 3: Monitored Natural Recovery
and  Enhanced Natural Recovery
Three variations of this alternative were evalu-
ated (Alternatives 3A, 3B, and 3C). Alternative
3A utilizes  Monitored Natural Recovery (MNR)
for all reaches except Reach 8. This would con-
sist  of monitoring natural processes to confirm
that  reductions in fish tissue concentrations are
occurring in those reaches where reductions are
expected. Monitoring would also be conducted
in Reach 8 to insure concentrations are stable
or decreasing. Institutional controls (signs, public
outreach) would also be implemented. Alterna-
tives 3B and 3C are similar to Alternative 3A,
except they contemplate the placement of a thin
layer of sand on top of more highly contaminat-
ed sediments. The use of a sand layer in conjunc-
tion  with monitoring is  referred to as Enhanced
Natural   Recovery  (ENR).  In Alternative  3B  a
6-inch thin layer of sand would be placed at loca-
tions in  Reach 3 where total mercury in surface
sediment uniformly exceeds 10 ppm, which con-
stitutes  about 70% of the reach. Alternative 3C
evaluated the placement of sand over sediments
with mercury above 2  ppm; this includes all of
Reach 3, and large portions of Reach  4 and 6.
Under alternatives  3B and 3C, the level of mer-
cury contamination  in fish in all reaches except
Reach 8 is expected to decline to  acceptable lev-
els within a reasonable timeframe (i.e., less than
30 years).
Alternative 3A Cost: $1,070,000
Alternative 3B Cost: $8,500,000
Alternative 3C Cost: $22,190,000

Alternative 4: In-situ Containment
Alternatives 4A and 4B are similar to Alternative
3A;  however they consist of two variations of
"in-situ  containment." In-situ containment  relies
on the  installation  of an isolation barrier over
                                                                                                                                  page 6

-------
SUPERFUND  |  HAZARDOUS  WASTE PROGRAM AT  EPA  NEW  ENGLAND
                                                               PROPOSED PLAN
contaminated sediment. In-situ  containment is
different from a thin layer  of sand:  while the
sand would  mix with and dilute contaminated
sediment, the in-situ containment would function
to prevent  direct contact  with contaminated
sediment, reducing resuspension and providing
chemical and physical isolation of contaminants.
Alternative 4A would  apply the  barrier over
sediments in Reach 3 only (Reservoir 2) where
mercury concentrations exceed  2 ppm; Alterna-
tive 4B would apply the barrier over sediments
exceeding 2 ppm of mercury in Reaches 3, 4 and
6. Institutional controls (signs,  public outreach)
would also be implemented and regular monitor-
ing would be included in both alternatives. Under
alternatives 4A  and 4B, fish contamination in  all
reaches except Reach 8 is expected to decline to
acceptable levels within a reasonable timeframe
(i.e., less than 30 years).
Alternative 4A Cost:       $24,310,000
Alternative 4B Cost:       $48,910,000

Alternative 5: Sediment Removal
Alternatives  5A  through  5D  consist  of four
variations of a  sediment  removal.  Sediment
removal  (via dredging)  relies  on the  physical
removal  of  mercury-contaminated sediments
to reduce the  mercury concentration in fish.
Some of the removal  alternatives would  be
implemented in  tandem with  other technolo-
gies, such as containment.  Specifically, Alter-
native  5A contemplates removal of sediment
with mercury greater than 10 ppm (regard-
less of depth) and would apply only to Reach
3  (Reservoir 2).  Alternative 5B evaluates the
effectiveness  of removing Reach  3 sediments
with mercury greater than 10 ppm  and capping
lesser-contaminated portions of Reach 3 as well
as portions of Reach 4 and Reach 6. Alternative
5C contemplates sediment  removal in Reach
3 where mercury is  greater than 2 ppm - ef-
fectively the entire reach. Alternative 5D, the
most comprehensive removal alternative, evalu-
ates removal of sediment having mercury con-
centration greater than 2 ppm  from Reaches 3,
4 and 6. In all of these alternatives, institutional
controls (signs, public outreach) would be  im-
plemented along with regular monitoring activi-
ties. Under  all  these alternatives, 5A through
5D, fish contamination in  all   reaches except
Reach  8  is expected to  decline to acceptable
levels within a reasonable timeframe (i.e., less
than 30 years).
Alternative 5A Cost:       $59,710,000
Alternative SB Cost:       $88,510,000
Alternative 5C Cost:       $99,820,000
Alternative 5D Cost:       $213,920,000
A CLOSER  LOOK
AT  EPA'S  PROPOSAL

After careful study of the remedial alternatives
evaluated for the Sudbury River, EPA proposes
Alternative 3B as the final  remedy. This is based
on EPAs analysis of the nine criteria for remedy
selection prescribed by the National Contingency
Plan (NCP); this analysis is provided on page 9.
Alternative 3B includes:

  •  Enhanced Natural Recovery (ENR), or
     the placement of 6-inch layer of sand
     over sediments in Reach 3 that have at
     least 10 ppm of mercury contamination,
     to be followed by regular monitored
     natural recovery.  This area is located
     north of the Fountain Street Bridge and
     extends to the Reservoir No. 2
     (Brackett Reservoir) dam.

  •  Monitoring of natural recovery processes
     (MNR) in the other reaches of the river,
     excluding Reach 8 (Great Meadows
     National Wildlife  Refuge) and Reaches 5
     and 7 (where there is no significant risk).

  •  Monitoring of Reach 8 to ensure
     mercury concentrations in fish tissue
     are stable or decreasing. (This
     monitoring program  is not referred to
     as MNR because it is unclear whether
     natural processes are adequate to allow
     this part of the river to fully recover.)

  •  Implementation of institutional controls
     (i.e., posting offish advisory signs and
     public outreach to discourage excessive
     consumption of contaminated fish)
     throughout the river.

  •  Periodic Five-Year Reviews of remedy
     protectiveness and performance.
ENR:  Enhanced Natural  Recovery consists
of the placement of a thin layer of sand over
existing contaminated  sediment that exceeds
mercury concentrations of 10 ppm.  The sand
would be placed in the downstream section of
Reservoir 2, located in Reach 3 between Foun-
tain Street and the Reservoir No. 2 Dam.  The
area is estimated to be approximately 84 acres;
it is the only part of the river, other than Reach 8,
where natural processes alone are not expected
to be adequate over a reasonable period of time
to eliminate  unacceptable risks from consuming
fish.  The placement of sand in this quantity is
anticipated to  be equal to  approximately  400
years of natural sedimentation,  which should
result in a significant dilution of mercury concen-
trations in sediment and thus in lower fish tissue
contamination. Because excess water from the
reservoir flows over the dam continually (even
in  non-flood conditions), adding sand to  the
bottom is not expected to increase the surface
water level in the reservoir  or result in any loss
of any flood  storage capacity. During pre-design
studies, additional analysis regarding  grain  size
and sediment stability may  be  required as  well
as studies to determine the optimum substrate
to encourage re-colonization of the sand layer
by benthic organisms.

MNR: Monitored Natural Recovery is  pro-
posed for other  river reaches,  excluding Reach
8,  Reach 5, and Reach 7 (the latter two due to
the lack of actionable risk in those reaches). Ac-
cording to EPAs computer model, fish tissue  con-
tamination is projected to continue to attenuate
such that the target fish tissue  concentration of
mercury (which should allow for unlimited recre-
ational angling) should be achieved in a reasonable
amount of time (i.e.,  less than  30 years) in the
reaches where MNR is proposed. This is unlike
Reach 3, where MNR alone is  not expected to
achieve the target fish tissue concentration with-
out the enhancements identified above. It should
be noted that certain reaches (i.e., Reaches 2, 9,
and 10) were not part of the computer model's
simulation of MNR.  However, the rate of natu-
ral recovery  in  these reaches is anticipated to be
similar to the modeled reaches, and thus these
reaches should attain  remedial goals over similar
timeframes (i.e., less than 30 years).
                                                                                                                                  page 7

-------
SUPERFUND  |   HAZARDOUS  WASTE  PROGRAM  AT  EPA  NEW  ENGLAND
                                                                PROPOSED PLAN
Fish Tissue  Monitoring:  A  baseline  of fish
tissue  concentrations  was  established  during
previous site investigation studies. As part of the
proposed remedy, monitoring will be conducted
in all reaches (except possibly  Reaches 5 and 7,
where there  is no unacceptable risk to human
health) and will likely consist of the collection of
a single species (bass) every five years and three
species (bass, perch and catfish) every  10 years
so as to allow for the recalculation of human
health risk. The first round of  monitoring activi-
ties will be performed five years after the Record
of Decision is issued.

Limited Action in Reach 8: The Great Mead-
ows National Wildlife Refuge is a unique hydro-
logical  environment encompassing  3,600 total
acres, of which  approximately 1,100 aces are
routinely (annually) flooded. As discussed above,
wetlands, like those in  GMNWR, have a signifi-
cantly higher rate of methylation than other river
environments. The wetlands are very efficient at
converting  mercury contamination  into methyl
mercury, where it is much more readily absorbed
into the food chain. Concentrations of mercury
in fish in Reach 8 are elevated even though the
sediment concentration of mercury is relatively
low  (between 1  and 3 ppm).   Because of this
efficient methylation, and because  of  on-going
atmospheric deposition of mercury, EPAs com-
puter model predicts that even a very extensive
attempt to  excavate   contaminated sediments
would result  in only marginal  reductions in fish
tissue concentrations.  In light of these facts, and
in light of the relatively low risks, EPA proposes
to  rely on  institutional controls  (signs, public
outreach discouraging consumption  of contami-
nated fish from the Sudbury River) to address
contamination in Reach 8. EPA will  continue to
monitor Reach 8, to verify that fish tissue con-
centrations are declining or stable. EPA believes
that, over time, risks in Reach 8 from  Nyanza-
related contamination will attenuate but that fish
may continue to be contaminated at unsafe lev-
els, due to the interaction between atmospheric
pollution and conditions in the reach that tend to
favor mercury accumulation in fish tissue.

Institutional Controls:
The current state fishing advisory and local Sud-
bury River fish advisory will function as a compo-
nent of informing the population against  eating
mercury-contaminated fish taken from the Sud-
bury River.  If these measures were discontinued,
EPA would  evaluate the need for additional mea-
sures. EPA will also implement a public outreach
and education program and install signs  to en-
sure safe consumption habits are followed.

Five-Year Reviews:
EPA would  perform Five-Year  Site  reviews to
confirm the effectiveness and adequacy  of the
above measures.

IMPACTS  TO THE  LOCAL
COMMUNITY  DURING
REMEDY  IMPLEMENTATION
Remedial activities are expected to have minimal
impact on the adjacent communities of Ashland
and  Framingham.  Alternative  3B  - Enhanced
Natural Recovery (ENR) entails the placement
of an approximately 6-inch-thick layer of sand in
the downstream portion of Reach  3 (Reservoir
No. 2) between the Fountain Street bridge and
the Reservoir No. 2 Dam (refer to  attached Fig-
ure); this area is approximately 84 acres.  This
will involve the use of heavy equipment, trans-
portation  of materials  used for capping,  and
construction of a temporary staging area.  Traf-
fic and noise impacts  will be minimized to the
extent possible. Monitoring activities will be con-
ducted every five years and will have virtually no
impacts on the community.

A  variety of potential staging and work areas
were  evaluated  in the  FS; however, one area
looks  to  be  the most favorable and is  included
in  this Proposed Plan to illustrate one poten-
tial option for implementation of the proposed
remedy. This area is  approximately 2.5 acres
and is  located just south of the Sudbury River
and Fountain Street  (near  the  Fountain Street
Bridge). Materials could be delivered to this area
by road or possibly by rail.  Sand delivery by rail
may be both cost effective as well as reduce im-
pacts to local traffic patterns. The use of rail or
trucking and the specific staging location will be
developed during the remedial  design phase of
the cleanup.

The staging area may  consist of a large  dock on
piers and will be used  to store and transfer sand
to the actual placement equipment. Depending
on the location of the waterfront  staging area
as well as method of sand delivery (rail versus
truck) a conveyor system could be used to move
material from  the  primary staging area (south
of Fountain  Street) to  the waterfront  staging
area. In that way re-routing of traffic on Fountain
Street  could likely  be avoided.  The placement
of the sand can be completed using a variety of
methods. It  is likely that sand from the water-
front staging area would be transferred to a mo-
bile (floating) barge. The mobile barge would be
used to applied sand  to the bottom sediments
via hydraulic (wet) methods such as a by mixing
sand with water and applying as a slurry through
a pipe, or by mechanical (dry) methods such as
broadcast spreading - such as is typically used
when fertilizing. A variety of equipment is available

Sudbury River
                                                                                                                                   page 8

-------
SUPERFUND  |  HAZARDOUS WASTE  PROGRAM  AT  EPA  NEW  ENGLAND
                                                                                                             PROPOSED  PLAN
that can be used for both and the final methodol-
ogy will be determined during remedial design.

Since  some intrusive  work would be required,
best work practices would be utilized to protect
surrounding environmental receptors from erod-
ing soil and/or sediment as well as stormwater
run-off from staged materials. Engineering con-
trols such as hay bales or silt curtain would be
implemented as a means  of reducing the trans-
port of contaminated sediments adjacent to the
work areas. Traffic control  plans will be devel-
oped  in coordination with local police and noise
will be  minimized  to the extent  possible. Air
monitoring will be  conducted during the work
and engineering controls such as misting will be
used if necessary for dust  suppression.

It is estimated that Alternative 3B would require
2 years for construction and implementation.
PUBLIC  NOTICE  OF
IMPACTS  TO WETLANDS
AND  AQUATIC  RESOURCES

Several state and federal laws regulate activities
in and around floodplains, wetlands and rivers,
including the  remedial action proposed  in this
plan. For example, under a federal wetlands ex-
ecutive order,  EPA is required to  minimize the
destruction, loss or degradation of wetlands and
to preserve and enhance the natural and  ben-
eficial values of wetlands. Using these principles,
EPA is further required to select  the least en-
vironmentally  damaging  practicable alternative
for reducing environmental risks at the site. Simi-
larly, EPA is also required  by Section 404 of the
Clean Water Act to avoid discharging fill mate-
rial  into rivers if there is a practicable  alterna-
tive that would have less adverse impact on the
aquatic ecosystem. EPA has determined that the
proposed remedy is a discharge of fill material,
and it involves unavoidable adverse impacts to
wetlands and aquatic resources, primarily in the
form of the deposition of the thin  sand layer  in
Reach 3, which is a  federally-regulated wetland.
EPA has evaluated  the  applicable regulations,
including Section 404 of the Clean Water Act,
                                              and identified the proposed action as the least
                                              damaging  practical alternative to protect feder-
                                              ally regulated  wetlands and aquatic  resources
                                              from  contamination  in sediments  and  surface
                                              water. EPA expects that the thin sand layer will
                                              help prevent mercury  from bioaccumulating in
                                              fish and other organisms, and that the  impacts
                                              to the river bottom from putting down the layer
                                              will be temporary and minor; benthic  organisms
                                              will quickly re-colonize  the sand layer. Other  al-
                                              ternatives considered for Reach 3 either would
                                              do nothing about mercury in the river or would
                                              have short-term impacts on  the benthic environ-
                                              ment that would either be as severe (e.g., in-situ
                                              containment) or more severe (e.g.,  dredging).
                                              See  "Compliance with  Applicable  or Relevant
                                              and  Appropriate Requirements (ARARs)"  be-
                                              low for further discussion on wetland impacts.
                                              Through this Proposed Plan, EPA is also solicit-
                                              ing public comment concerning its determination
                                              that the alternative chosen  for Reach 3 is the
                                              least  damaging practicable alternatives for  pro-
                                              tecting wetland resources.
                                              HOW DOES  EPA  CHOOSE
                                              A  FINAL CLEANUP PLAN?

                                              EPA uses nine criteria to compare alternatives
                                              and select a final cleanup plan. Of the nine, pro-
                                              tection  of human health  and the environment
                                              and compliance with other environmental  laws
                                              (known as  applicable or relevant and appropri-
                                              ate requirements, or "ARARs") are considered
                                              threshold requirements that must be met by the
                                              selected remedy. EPA balances its consideration
                                              of alternatives with  respect to long-term effec-
                                              tiveness and permanence; reduction of toxicity,
                                              mobility or  volume through treatment; short-
                                              term  effectiveness;  implementability; and cost.
                                              State  and community concerns are modifying
                                              criteria and may prompt EPA to modify the pre-
                                              ferred alternative or choose another alternative.
                                              Following are definitions of the nine criteria.

                                                1. Overall protection of human  health and
                                                  the environment: Will it protect you
                                                  and the plant and animal life on  and
                                                  near the site? EPA will not choose a plan
                                                  that does not meet this basic  criterion.
  2. Compliance with Applicable or Relevant
     and Appropriate Requirements (ARARs):
     Does the alternative meet all federal and
     state environmental statutes, regulations
     and requirements?

  3. Long-term effectiveness and
     permanence: Will the effects of the
     cleanup plan last or could contamination
     cause future risk?

  4. Reduction of toxicity, mobility or
     volume through treatment:  Using
     treatment, does the alternative reduce
     the harmful effects of the contaminants,
     the spread of contaminants,  and the
     amount of contaminated material?

  5. Short-term effectiveness:  How soon will
     site risks  be adequately reduced?  Could
     the cleanup cause short-term hazards to
     workers,  residents or the environment?

  6. Implementability: Is the alternative
     technically feasible?  Are the right goods
     and services (i.e. treatment machinery,
     space at an approved disposal facility)
     available for the plan?

  7. Cost:  What is the total  cost of an
     alternative over time?

  8. State acceptance:  Do state
     environmental agencies agree with
     EPA's proposal?

  9. Community acceptance: What
     objections, suggestions or
     modifications does the public offer
     during the comment period?
EVALUATION  OF
ALTERNATIVES  UNDER
THE  NINE CRITERIA

This section summarizes EPA's evaluation of
how well each of the cleanup alternatives de-
scribed above (including the alternative
                                                                                                                                 page 9

-------
SUPERFUND  |   HAZARDOUS  WASTE  PROGRAM  AT  EPA  NEW  ENGLAND
                                                                PROPOSED PLAN
proposed in this plan) meets the first seven
criteria. A fuller description is provided in the
Feasibility Study Report. Once comments from
the state and the community are received, EPA
will select the final cleanup plan.

Overall Protection of Human Health
and the  Environment
Alternative 1 (No Action) does not protect hu-
man health in that it allows for unlimited expo-
sure to contaminated fish (not withstanding the
fishing advisories which may be maintained  by
others agencies). All the other alternatives pro-
tect human health  and the environment. How-
ever, Alternatives 2 and 3A are less protective
because they merely discourage fish consump-
tion through fish advisories and public outreach,
without doing anything to accelerate the natural
attenuation of contamination in fish. These two
alternatives also rely on routine monitoring to
ensure that fish tissue levels are  decreasing (or,
in the case  of Reach  8, decreasing or remaining
stable). All  other alternatives (including 3B, the
alternative proposed in this plan) protect human
health and the environment by reducing the avail-
ability of mercury to fish in portions of the river,
thus leading to a reduction in mercury in fish tis-
sue over time. These alternatives also include fish
advisories, public outreach and monitoring.

Compliance with Applicable or Relevant
and Appropriate Requirements (ARARs)
Despite the absence of active remediation, Al-
ternatives 1, 2,  and 3A would meet ARARs. All
other alternatives are also  expected to comply
with ARARs,  except for ARARs related to mini-
mizing impacts  on wetlands and  related aquatic
resources. The  wetlands order, Section 404 of
the Clean Water Act  and several other state
laws require  EPA to avoid adverse impacts to
wetlands and other aquatic environments, unless
there is no  practicable alternative with lesser ef-
fects. Alternatives 1,  2 and  3A would not cause
impacts;  however, they would also do nothing
to reduce mercury in fish tissue, particularly in
Reach  3 in a reasonable amount of time. All the
active remediation  alternatives (Alternatives 3B
through 5D)  have an adverse impact - the thin
sand layer, the  cap,  and the dredging all consti-
tute a  temporary degradation  of the river bot-
tom  environment, which is a wetland. Thus the
question is  which  alternative  constitutes  the
practicable alternative  with  the  least adverse
effects on the aquatic environment. EPA  has
determined that Alternative 3B (the  proposed
remedy), which would place a thin layer of sand
over sediments in Reach 3, and Alternative  4A,
which would  place an "in situ containment"  cap
over Reach 3, have essentially the same impact
on the aquatic environment, and constitute the
alternatives that have the  least adverse impact.
Like  the other active remediation alternatives,
these alternatives reduce fish tissue contamina-
tion  to  acceptable levels in  much of the river
within a reasonable timeframe. They differ from
the other active remediation alternatives in two
significant ways:  (1) more than the other active
remediation alternatives, Alternatives  3B and 4A
have impacts on only a small portion of the river,
i.e., Reach 3,  (2) they do not involve significant
re-suspension of contaminated sediments, as do
the removal/dredging technology contemplated
by Alternatives 5A through  5D. On  this basis,
EPA  believes that Alternatives 3B and 4A are the
active remediation alternative that best comply
with  the wetlands executive order, Section 404
and the state wetlands regulations.

Long-term Effectiveness and Permanence
Under the  No Action alternative,   long-term
risks would remain unaddressed. All other alter-
natives rely,  in varying  degrees, on institutional
controls such as the posting of warning signs for
long-term effectiveness. Since these types of con-
trols are not enforceable  and compliance  with
such  warnings is  difficult to track, alternatives
that  rely more heavily  on these controls (such
as Alternatives 2) may be less effective in  the
long-term compared to other, more active alter-
natives.  The active remedial  alternatives (Alter-
natives 3B through 5D) are expected to reduce
fish tissue mercury concentrations and, there-
fore, would achieve protectiveness sooner than
Alternatives  1, 2 and 3A.  The removal alterna-
tives (Alternatives 5A through 5D) are expected
to take longer to attain protectiveness due to po-
tential resuspension of contaminated  sediment,
but do result  in the permanent removal of more
contaminated sediment from the river. To ensure
the long-term protectiveness of Alternatives 3B,
3C, 4A, and 4B, further design work would be
necessary to ensure the stability and integrity
of sand or other capping materials to be placed
in  the river pursuant  to  these  alternatives.
Long-term maintenance and monitoring activi-
ties would be conducted as necessary.

Reduction of toxicity, mobility
and volume through treatment
The alternatives that do not contemplate active
remediation  (Alternatives 1, 2, and 3A) do not
reduce toxicity,  mobility or volume of mercury
in the river. All other alternatives partially satisfy
this criterion: the thin  sand layer  (3B and  3C)
and the cap (4A and 4B) reduce the  mobility
and toxicity  of mercury significantly - reducing
the amount  that is capable of bio-accumulating
in fish and thereby  controlling the only threat
to human  health in the river. The dredging and
removal alternatives (5A through 5D) are more
effective still  at meeting this criterion, removing
significant  quantities of mercury from the river
entirely; however, the material must be removed
and disposed offsite.

Short-term effectiveness/impacts
As no active remediation is proposed for Alter-
native 1, this would not result in any short-term
risks to on-site  workers or adverse effects to
the environment or community  during  imple-
mentation. The  time required  to  implement
Alternative 2 would be minimal since it only in-
volves maintaining  institutional controls. Alter-
native 3A adds a monitoring component, which
would allow for verification of the effectiveness
of the site-wide remedy; this monitoring would
pose few short-term risks to workers during im-
plementation as sampling techniques employed
would be traditional and non-harmful to the en-
vironment or surrounding community. Alterna-
tive 2 could also include monitoring activities.
The remaining alternatives all have short-term
impacts. The alternatives that limit active reme-
diation to  Reach 3 (Alternative 3B, 4A, 5A and
5C) would  obviously have fewer short-term
impacts than the alternatives that propose re-
mediation across several reaches (Alternatives
4B, 3C,  5B, and 5D). A more significant differ-
ence is that  the sand and capping alternatives
(3B, 3C, 4A, 4B) may have fewer short-term
                                                                                                                                  page 10

-------
SUPERFUND   |  HAZARDOUS  WASTE  PROGRAM  AT  EPA  NEW ENGLAND
                                                                 PROPOSED  PLAN
impacts than the dredging alternatives (5A, 5B,
5C, 5D), because it is faster and easier to place
material over a riverbed  than  to  dredge it up.
With the  dredging alternatives there  is also
the potential for sediment re-suspension, which
could cause a temporary  elevation  in fish tissue
concentrations.  Overall, among the alternatives
that  go  beyond  monitoring and institutional con-
trols,  the  proposed alternative (3B) appears to
have the fewest  short-term impacts, because put-
ting down a thin  sand layer is relatively simple and
because this activity would be limited to Reach 3.

Implementability
Implementability is primarily related to three fac-
tors: technical feasibility (i.e., can it be constructed,
is  it  reliable);  administrative  feasibility;  and the
availability of services and materials to implement
the remedy. All the alternatives are readily imple-
mentable  and rely on established technologies,
though the larger the scope of the remedy, the
greater the effort required to construct. Alterna-
tives 5A through 5D are relatively large construc-
tion projects, but projects  as large or larger have
been  conducted at numerous sites across the
country. Thin-layer capping (Alternatives  3B and
3C) and in-situ containment (Alternatives 4A and
4B) have also been successfully completed at oth-
er sites and employ readily available technologies
and materials. There is also sufficient land area for
staging as well as road and rail access to the site.

Cost
Costs for each  alternative are outlined above.
Alternative  1  (No Action) is the least costly of
proposed alternative to implement. Alternatives
2  (Limited Action)  and Alternative 3A  (MNR)
requires little cost to complete compared to ac-
tive remediation. Comparing the active remedial
alternatives, Alternative  3B  is the least costly,
followed by 3C, 4A, 4B, 5A, 5B, 5C and 5D  in
ascending order.

State Acceptance
State acceptance will be evaluated  based on  com-
ments the State submits during the comment period.

Community Acceptance
Community acceptance will be evaluated based on
comments submitted during the comment period.
WHY  EPA  RECOMMENDS
THIS  CLEANUP  PROPOSAL

EPA proposes Alternative 3B, MNR with Enhanced
Natural Recovery via thin layer sand  capping, with
Limited Action in Reach 8 for several reasons. First, it
is protective and more effective than the alternatives
that don't involve active remediation (Alternatives 1,
2, and 3A). Whereas Alternative 3B takes active steps
to reduce the contamination  in fish in the most con-
taminated reach of the river, Alternatives 1, 2 and 3A
rely mainly on fish advisories to discourage consump-
tion of contaminated fish  although Alternative 3A
also adds a monitoring component.  Second, except
in Reach 8, Alternative 3B is expected to reduce fish
contamination to acceptable levels to approximately
the same extent as the other, more intensive alterna-
tives evaluated, yet it costs much less than any other
active  remediation alternatives. Third, it  has the least
impact on wetlands of any active remediation alterna-
tive, in that it buries and dilutes mercury that would
otherwise remain available for methylation, it has con-
struction impacts on smallest area of the river of all ac-
tive alternatives, and it does not involve re-suspension
of contaminated  sediments. With regard to Reach 8,
EPA believes that Limited Action is the best alterna-
tive given the amount of risk reduction that would be
achieved with active remediation in  light of the rela-
tively low concentrations of mercury in the sediment.

EPA  believes that Alternative 3B  meets  the two
threshold criteria  of overall   protection of human
health and the  environment  and  compliance with
ARARs and represents the best balance of the other
criteria and, thus, is proposing this remedy for state
and public comment.


NEXT  STEPS

This summer/fall, EPA expects to have reviewed
and evaluated all comments  received on this pro-
posal  and will sign a Record of Decision, which is
a document that describes the  chosen  cleanup
plan. The Record of Decision and a summary of re-
sponses to any  public comments (the Responsive-
ness Summary)  will then be made available to the
public at the Ashland Public Library  and at EPAs
Records Center in Boston,  and via  the  internet.
EPA will announce the final decision on the cleanup
plan through the local media and via EPAs website.
HOW  YOU  CAN
COMMENT  ON  EPA'S
CLEANUP  PROPOSAL

During the 30-day formal comment period,
EPA will accept formal written comments
and hold a hearing to accept formal verbal
comments. EPA uses public comments to
improve the cleanup proposal. To make a
formal comment you need only speak during
the Public  Hearing on July 19, 2010 at 7 pm
at the Framingham Town Hall or submit writ-
ten comments during the 30-day comment
period no  later than July 26, 2010.

Provide EPA with your written  comments
about the  Proposed Plan, postmarked  no
later than July 25, 2010 to:
Daniel Keefe, Project Manager
U.S. EPA New England
5 Post Office Square, Suite 100
Mail code: OSRR07-1
Boston, MA 02109-3912
Or, submit comments by e-mail to:
keefe.daniel@epa.gov or
Fax comments to:  617-918-0327.

Although  EPA cannot respond to  comments
submitted   at the Public  Hearing, EPA will
respond to both your oral and written  com-
ments in  the  written  Responsiveness  Sum-
mary  that will be included with the Record
of Decision. EPA will review the transcript of
all formal comments received  at the hearing,
and all written comments received during the
formal comment period, before making a final
cleanup decision.

The fact that EPA  responds to formal  com-
ments in writing at  the time  the  Record of
Decision is issued, does not mean that EPA
cannot answer questions. EPA will be  hold-
ing three  informational meetings in June as
indicated on page 1  to  answer any questions
about the  Proposed Plan.

Your formal  comment will become  part of the
official public record. The  transcript of comments
and EPAs written responses will be issued in a
document  called a Responsiveness Summary
when  EPA  releases the final cleanup decision.
                                                                                                                                      page  11

-------
                    Targ«AiK»    Kivor Roaches
                    |    | Primmy
,^'CoratyBoTOtay   I    I
/\/ Watoshod Bomfay

|   ~\ Sudhury Em* Watershed
OPERABLE DMT 4 LOCUS -
SUDBURY RIVER REACHES

-------
              Alternatives Comparison
     Nyanza Chemical Waste Dump Superfund Site
Operable Unit 4 -Sudbury River, Ashland, Massachusetts

Timeframe to Implement *
Timeframe to Remediation Goals**
Comparison Criteria
Overall Protectiveness
Compliance with ARARs
Long-Term Effectiveness
Reduction of TMV
Short-Term Effectiveness
Implementability
Cost (in Millions)
State Acceptance
Community Acceptance
Alt. 1
No Action
0 Years
>70 Years

m
0
m
m
m
0
$0.0
Alt. 2
Limited
Action
2 Years
>70 Years

S
0
S
m
s
0
$0.2
Alt. 3A
Sitewide MNR
2 Years
>70 Years

S
0
S
H
S
0
$1.1
Alt. 3B
ENR in Reach
3 > 10ppm
3 Years
<30 Years

0
0
0
s
0
0
$8.5
Alt. 3C
ENR in
Reaches 3, 4,
6 > 2ppm
4 Years
<30 Years

0
S
0
S
0
0
$20.8
Alt. 4A
In Situ
Containment
in Reach 3
3 Years
<30 Years

0
0
0
S
0
0
$24.3
Alt. 4B
In Situ
Containment
in Reaches 3,
4 and 6
4 Years
<30 Years

0
S
0
S
0
0
$48.9
Alt. 5A
Dredging >
10ppm in
Reach 3
3 Years
<30 Years

0
S
0
s
0
0
$59.7
AltSB
Dredging >
10ppm in
Reach 3, In
Situ
Containment
in Reaches 3,
4 and 6
4 Years
<30 Years

0
S
0
s
0
0
$88.5
Alt. 5C
Dredging >
2ppm in
Reach 3
4 Years
<30 Years

0
S
0
S
0
0
$99.8
Alt. 5D
Dredging >
2ppm in
Reaches 3, 4
and 6
5 Years
<30 Years

0
S
0
S
0
0
$213.5
To Be Determined After Public Comment Period
To Be Determined After Public Comment Period
Notes: 0 S IE
Alt = Alternative Meets Partially Meets Fails to Meet the
TMV = Toxicity, Mobility and Volume Criteria Criteria Criteria
* Includes a 1 to 2 Year Period to Complete Remedial Design
** Defined to mean attainment of both remedial action objectives: a) prevent consumption of contmainated fish through advisories; and b) reduction of mercury in fish to acceptable levels (except in Reach 8).

-------
                                                                                                                                  Contaminant Legend

                                                                                                                                    • Surfieial Sedimen! Sample
                                                                                                                                       Average Segment Surface
                                                                                                                                       Total Mercury (mg.'fcg)

                                                                                                                                                lit kg
                                                                                                                                j	1  Segment 3
                                                                                                                                    -J  Avg = 5.7 m^-kg
                                                                                                                                       Segment -4
                                                                                                                                       Avg = 9.5 nrg'kq
                                                                                                                                       Segment 5
                                                                                                                                       Avg * 27.9 nig'Kg
D:ita: 03/29; 10
                RnvJukin No. OD
                                    • Railroad
                                    • County B
                                    ' Municipal Boundary
Secdnda
Local Ro
                                                                         id/. Access Ra
                                     Highway&^Major Roads     - -• Vehicular Trail
                                     Primary Read. Limited Access
                                     Primary Road. Not Limited Access
1 Segment Break
1  Surface Water
]  Reach 2
  Reach 3
  Reach 4
           FIGURE B
  CONTAMINANT DISTRIBUTION
NYANZA CHEMICAL WASTE DUMP
        SUPER FUND SITE
     OU4 - SUDBURY RIVER
  ASHLAND. MASSACHUSETTS

-------
                       AREA OF DETAIL:  POTENTIAL STAGING AREA
                                                                                  Conveyor Belt Delivery
                                                                                  System to Sand Barge
Drawn By DttC I Clwsk*J Bv 5WH
                      Legend

* Railroad                                ,

• Cwtity Bondary        — Secondary Road

" Municipal Boundary         Local Road, Access Ramp '

• Highways/Major RoatfS      Vehicular Trail

- Primary Road. Lim(ted Accafifi

• Primary Road. Not Limited Access
                                                                    " Reach 2

                                                                     ReschS
                                                                     Reach 4
POTENTIAL STAGING AREA DETAIL
     REACH 3 SEGMENTS
NYANZA CHEMICAL WASTE DUMP
      SUPERFUND SITE
    OU4 - SUDBURY RIVER
  ASHLAND. MASSACHUSETTS

-------