-------
3) The amount of sealants used varied considerably for different
mines. Kown and his associates (K0S0) chose the following amounts
for their study which were greater than other studies on this
subject.
Shotcrete - 909 gal per 1000 ft2
HydroEpoxy 156 - 18 gal per 1000 ft2
HydroEpoxy 300 - 32 gal per 1000 ft2
4) The sealant coating applied to drifts of an underground mine
has a limited life of about eight months because the drift area is
mined after pillars are extracted in a room-and-piliar stope
mine.
5) An asphalt emulsion sealant has been tested in the laboratory
and on tailing piles and is found to be an effective, inexpensive
sealant. However, it has not yet been tested in an underground
mine atmosphere.
The cost of coating 530,000 ft2 of drift surfaces in the mine
was $348,100 ($1.45 per ton of ore removed). The floors were not
considered to be coated because ore loaders will destroy the coating on
the semiconsolidated muck. The three sealants were applied every two
months. Cost estimates of other sealants range from $0.30 to $1.10 per
square foot (Fr81) which is comparable to the cost estimates ($0.66 per
square foot) of the sealants used in this study. Because of its high
cost, the Bureau of Mines feels that sealants may only be used
economically in shops, lunchrooms, and possibly high-emanating areas in
intake airways (Frc83).
A recent study by Battelle (B184) of 13 mines shows an average
cost of $5.80 per ton of ore mined ($0.34 per square foot) if 80 per-
cent of the surface is sealed. This EPA-sponsored study has shown that
sealants could reduce the radon emanation from the active stopes of the
mines by 23 percent. If the total mine is included (25 extracted
stopes), only 11 percent of the radon was reduced. This second figure
should be used when determining the amount of radon released from the
mine.
Other studies by the Bureau of Mines (Fra81) have shown that 50 to
75 percent of the radon can be retained in the rock by sealants. The
study by Battelle (B184) shows that a 56 percent reduction in radon
emissions can be achieved by applying sealant to 80 percent of the mine
surfaces.
Bulkheading
Bulkheading of mined-out areas, such as extracted stopes, is the
most common radon control method currently practiced in underground
mines (Ko80). In general, it is used to isolate worked^out areas or
5-7
-------
stopes from workers so that the radon concentrations in the working
areas of the mine will be lower. If the bulkhead is air tight, the
radon behind the barrier will decay to innocuous levels. However, all
bulkheads leak to some extent, and usually a small 3- to 6-inch
ventilation pipe is used as a bleeder pipe to provide negative pressure
in the extracted stope (Fra81) and to allow the contaminated air to be
diverted to the ventilation system. A small fan may be required to
maintain the negative pressure. Ideally, only 10 percent of the air
behind the bulkhead would be diverted to the outside atmosphere. This
air stream can also be connected to an activated carbon filter or trap
to reduce concentrations further.
In an EPA study (Ko80) it was assumed that 12.5 stopes per year
would be sealed using 100 bulkheads. The cost for material, labor, and
maintenance was estimated to be $80,400 or $0.34 per ton of ore
removed. It was also assumed that a six-inch pipe provided a 100 cfm
bleeding rate from each bulkheaded area. In a Battelle study (B184)
the average cost to bulkhead 80 percent of the mine at 13 sites was
only $0.08 per ton of ore. Up to 10 bulkheads in each mine were used
in making these estimates.
An estimate of the effectiveness of reducing radon by this system
was made using many crude assumptions. For the total mine, bulkheading
was estimated to achieve about a 14 percent reduction in radon
emissions (KoSO). A preliminary study conducted by Battelle on an
actual mine indicated that a radon reduction of 35 percent could be
obtained by using bulkheads (DraSO, Th81). Using bulkheads extensively
in a mine can reduce radon emissions up to 60 percent (B184).
Radon Adsorption on Activated_ Carbon
Leakage of high radon concentrations through bulkheads used to
control radon concentrations in mines is another problem. One method
to relieve this problem is to insert a small bleeder pipe in the
bulkhead to provide negative pressure within the enclosed area behind
the bulkhead. This bleeder pipe is usually connected to the exhaust
ventilation system. Although this may prevent exposure to the workers,
the radon emissions to the environment may still be high. An activated
carbon adsorption system may be attached to the radon effluent pipe
before releasing this air to the exhaust ventilation system (KoSO).
An effective radon control system for the bleeder pipes is still
under study. The system chosen by investigators in an EPA study (KoSO)
is shown in Figure 5-3. It consists of two carbon adsorption systems
in series. The flow from the bleeder pipe is filtered to remove dust
particles and radon daughter products. The radon is then adsorbed in
the carbon column. The carbon column is regenerated once a day, using
hot air. The contaminated air from the regeneration is sent through a
second carbon column to again adsorb the radon gas. Occasional drying
may be required in the second column due to buildup of moisture.
5-1
-------
, RADON
I MONITOR
PRIMARY CARBON BED
FILTER BLOWER | (1800 lb«>
100 - 300JCFM
BLOWER
<1-5HP> HEATER
(50KW)
| COOLER
BLOWER
(2HP)
- -to CARBON BED |
(ISOIbs)
CONDENSED
WATER TO
DRUMS
SPARE
PRIMARY
ADSORPTION
CARBON
REGENERATION &
SECONDARY
ADSORPTION
Figure 5-3. Radon removal from mine air by carbon adsorption.
5-9
-------
In evaluating control technology in a model mine, EPA (KoSG) found
that an average of 12.5 activated carbon systems must be installed each
year to treat the contaminated air from the stopes sealed by the bulk-
heads. The capital and operating costs for each unit are as follows:
Capital Cost ofEachUnit
Major equipment $22,000
Auxiliaries & Installation $11,OOP
Total $33,000
annUQlized Cost of Bach_..Unit
Material (carbon, filters, piping) $ 1,000
Utilities (25,000 kwh @ 4s2/kwh) $ 1,000
Labor (0.25 person-year) $ 8,000
amortizing (an avg. 5-year life at 10 percent interest) $ 8,700
Total $18,700
assuming the lifetime of each unit is 5 years and 12.5 units per
year are needed, the cost over five years would be $1,037,500 or $0.86
per ton of ore mined. The carbon system was assumed to be 95 percent
efficient in removing radon.
The effectiveness of the entire system, including bulkheading and
carbon traps, was estimated to be 49 percent. A study by Battelle
(DraSO) estimates a 45-68 percent effectiveness, using absolute
sorption traps in combination with bulkheading. The total cost for
bulkheading and carbon traps would be $1.20 per ton of ore mined for
100 bulkheads. In the study by Battelle (B184) the average cost to
bulkhead with a carbon trap at 13 mines was $0.11 per ton of ore with
an efficiency of 80 percent. Up to 10 bulkheads in each mine were used
for their estimate.
There are some definite disadvantages to the carbon adsorption
system. Skilled operators, usually not available in mining
communities, are necessary to operate and maintain the system, safety
problems to the miners are possible due to interrupted electrical
service or system malfunction. Excess radon concentrations would then
be present. The carbon columns would have to be shielded to prevent
gamma exposure to the miners. The system may not work in wet mines
because of moisture absorption by the carbon.
The system does appear to be technically feasible utilizing
commercial carbons and standard equipment. However, additional
developmental work may be necessary before such a system can be used in
a mine environment. A recent study by Hopke (Ho84) has concluded that
activated carbon can be used for effective cleaning of small volumes of
air such as effluents from a bleeder pipe for a bulkhead.
5-10
-------
Mine,,,, Pr es_sur izat Ion
Positive mine pressurization has been tried several times to force
the radon in the mine atmosphere back into the walls of the mine (Ko80
and Fra81). In general, these efforts have been successful in reducing
the radon concentrations in the mine itself. An "air" sink is necessary
to accept the radon. If the radon is forced through the ore body or
surrounding area to the surface, the radon can decay before coming to
the surface, if the area is impermeable, however, radon levels will
return to previous levels. In tests by the Bureau of Mines (Fra81)t
the radon levels in the mine were reduced by 20 percent (releases to
the atmosphere were not determined). The surrounding soil needs to be
permeable enough to hold radon and allow for its decay, but not so
permeable so as to allow significant increases in surface emissions
(Ko80). The costs of mine pressurization were not available because
the process was in a development stage, in a recent report, Battelle
(B184) concluded that positive pressure ventilation has been proven
ineffective in reducing atmospheric emissions of radon.
Miscellaneous Radon ControlTechnology
Argonne National Laboratory is experimenting with strong oxidizing
agents, such as bromine triflouride and dioxygenyl hexaflouro-antimonate,
to convert the radon to another form that can be absorbed on a scrubber
or absorption bed (FraSl). However, the corrosive and toxic nature of
the reactants makes their use in mines impracticable and questionable.
Battelle (B184) mentions other methods such as cryogenic methods,
chemical removal, and gas centrifuge, but the costs are prohibitive.
The study by Hopke (Ho84) reviewed methods for the removal of radon
from uranium mine effluents. Methods, including cryogenic condensation,
molecular sieves, gas centifugation, semipermeable membranes, and hybrid
systems, do not offer much promise for a practical removal system. They
do suggest the exploration of the class of perfluorinated hydrocarbon
compounds as possible candidate scrubbing fluids for a radon scrubbing
system.
Backfilling of worked-out areas with classified mill tailings is
practiced by mine operators to provide ground support in the mine
(Fr81). This procedure can also reduce ventilation requirements. R
study, by the Bureau of Mines and Kerr-McGee Nuclear, to determine the
effectiveness of reducing radon emissions by backfilling mill tailings
into the mine stopes indicated a net radon reduction of 84 percent from
the stope (FrbSl). This was done for only one stope in a mine. PNL
(B184) estimated an efficiency up to 80 percent if classified mill
tailings and surface sands are used for backfilling with an average
cost of $12.64 per ton of ore mined.
Increasing the height of vents is a possible method to reduce
ground level radon concentrations in ambient air (DraSO). One of the
conclusions based on a theoretical model was that "a 20-meter release
5-11
-------
height reduces the annual average concentration (when compared to a
ground-level release) by about 60 percent at one mile from a source and
by about 30 percent at tee miles from the source." An estimate of cost
is $0.493 - $0.881/ton of ore for a 20-meter stack (Brb84). The
average number of vents for a mine is about 5 (Ja80). Thus, the cost
per mine would be about $3.44 per ton of ore produced.
Vent orientation is an important factor in radon concentrations
near a mine (Drc84). Because of plume rise, concentrations are much
lower when vents are in a vertical configuration (rather than hori-
zontal), resulting in a reduction factor of 80 at sites near a mine
with a vertical vent configuration.
Summaryof Costs and Efficiencies
A summary of the costs and efficiencies of the various radon
control technologies discussed previously is shown in Table 5-3.
Table 5-3, Cost and efficiencies of radon control technologies
for underground uranium mines
Radon reduction Cost
Method (Percent) ($/ton of ore)
Sealant coating
Bulkheading
Bulkheading with activated
carbon
Mine pressurization
Stacks
Backfilling
11 - 56
14 - 60
49 - 80
20
60(a)
80 - 84
1.45
0.08
0.11
-
3.44
12.6'
- 5.80
- 0.34
- 1.20
1
'a'Reduction in exposure to nearby individuals.
5.4 Radionuclide Emission Measurements
Radon-222 is the radionuclide emitted from underground uranium
mines which causes the greatest risk to people. The major source o£
radon-222 emissions to air are the mine vents through which the
ventilation air is exhausted, a large underground mine will usually
have several vents; some mines have as many as 14 vents, Radon-222
emissions from these vents are highly variable and depend upon many
interrelated factors including; ventilation rate, ore grade,
production rate, age of mine, size of active working areas, mining
practices, and several other variables.
Pacific Northwest Laboratories (PNL) has measured the radon-222
emissions from 27 underground uranium mines (fable 5-4) (JaSQ). The
average radon-222 emission rate for these 27 mines was 5,600
-------
Table 5-4. Measurements of radon-222 emissions from
underground uranium mine vents (Ja80)
Mine
A
B
C
D
E
F
G
H
I
J
K
L
R
T
U
V
Y
Z
M
BB
CC
DD
BE
FF
GG
HH
II
Average
Number
of vents
4
6
4
2
14
13
5
10
11
9
4
8
8
5
3
2
1
3
2
5
3
2
5
3
3
2
2
5
Measurements {Ci/y}
1979
7,400
4,700
5,200
3,600
29,800
9,200
2,200
15,200
1,700
7,800
7,000
1,500
15,000
1,900
900
1,000
17,500
-
2,100
2,100
_
-
6,500
2,500
200
1,000
500
6,100
1978
-
4,300
3,900
-
-
9,500
1,500
-
-
8,100
5,900
1,300
14,600
-
-
-
-
2,600
1,500
1,800
2,100
1,000
-
-
100
-
—
4,200
Average
7,400
4,500
4,600
3,600
29,800
9,400
1,800
15,200
1,700
7,900
6,400
1,400
14,800
1,900
900
1,000
17,500
2,600
1,800
2,000
2,100
1,000
6,500
2,500
200
1,000
500
5,600
curies/year. The emissions from individual vents ranged from 2 to 9,000
Ci/year with an average of 1,000 Ci/year.
In addition to the mine vents, radon-222 is emitted to air from
several above-ground sources at an underground uranium mining operation.
These sources are the ore, subore, and waste rock storage piles. PNL
5-13
-------
has estimated the radon-222 emissions from these sources to be about 2
to 3 percent of the emissions from the vents (Ja80). EPA has estimated
the emissions from the above-ground sources to be about 10 percent of
mine vent emissions (Table 5-5),
Table 5-5. Estimated annual radon-222 emissions from underground
uranium mining sources (BPA83b>
Source Average large
(Ci/y)
Mine vent air 3,400
Aboveground
Ore loading and dumping 15
Sub-ore loading and dumping 5
Waste rock loading and dumping 0
Reloading ore from stockpile 15
Ore stockpile exhalation 53
Sub~ore pile exhalation 338
Waste rock pile exhalation 3
Total 3,829
grade = 0.1 percent 1)303. Annual production of ore and
sub-ore = 2 x 10^ MT» and waste rock = 2.2 x 104 MT.
The above-ground sources also emit radionuclides to air as particu-
lates. The particulate emissions result from ore dumping and loading
operations and wind erosion of storage piles. EPA has estimated that
about 2E-2 Ci/y of uranium-238 and 3E-4 Ci/y of thorium- 232 and each of
their decay products would be emitted into the air at a large underground
mine (EPA83b). An assessment of the health risks from these emissions
showed that the risks from the particulate emissions were much smaller
(a factor of 100 less) than the risks from radon-222 emissions (SPA83b) .
Therefore, the health risk assessment presented in the subsequent sections
of this chapter will be limited to radon-222 emissions,
5.5 Reference underground uranium Mine
Table 5-6 describes the parameters of the reference mine which are
used to estimate the radon-222 emissions to the atmosphere and the
resulting health impacts. These parameters were chosen primarily from
information in Tables 5-1 and 5-8. The reference mine has 5 vents in the
configuration as shown in Figure 5-4.
5-14
-------
Table 5-
Reference underground uranium mine
Parameter
Value
Ore grade
Ore production
Days of operation
Number of vents
Vent height(a)
Radon emissions
0.22 percent
112,000 tons/y
250 days/y
5
3 meters
11,000 Ci/y(b)
'a'In estimating radon-222 concentrations in Table 5-9 for releases
with plume rise, the following vent parameters were used: vent
diameter is 1.5 meters, exit velocity is 16.2 meters/sec, and the
exit temperature is 287°K (Drc84).
Ci/y from each vent.
Table 5-7. Summary of radon™222 emissions by age of underground
uranium mine (Ja80)
Mine
A
B
C
D
E
F
G
H
J
K
L
R
U
V
Y
Z
Average
Age
(years)
3
9
9
7
-
-
4
_
_
_
-
_
4
2
6
_
6
New mines
Radon-222 emissions
(Ci/y)
7,400
4,500
4,600
3,600
_
-
1,800
-
-
_
-
-
900
1,000
17,500
—
5,200
Age
(years)
-
_
-
-
21
20
_
21
20
19
29
20
-
_
-
17
21
Old mines
Radon-222 emissions
(Ci/y)
-
_
-
-
29,800
9,400
-
15,200
7,900
6,400
1,400
14,800
-
_
-
2,600
10,900
from measurements made in 1978 and 1979.
5-15
-------
Table 5-8. Estimated ore production of selected
mines, 1982 (Brb84)
Estimated 1982 production
Mine (103 tons/y)
New Mines
(Mines less than 10 years
King Solomon
Velvet
Tony M
Hack Canyon
Pidgeon
Kanab North
La Sal
Heel a
Big Eagle
Golden Eagle
Mt. Taylor
Old Church Rock
Church Rock-East
Rerr-McGee
Section 19
Nose Rock
Mariano Lake
average
Old Mines
(10 years or more)
Sunday
Dermo-Snyder
Wilson-Silverbell
Lisbon
Sheep Mtn.
Church RockHNE
Church Rock- 1
Kerr-McGee
Section 30-East
Section 30-West
Section 35
Section 36
Home stake
Section 23
Section 25
Schwartzwalder
Average
old)
38.0
51.6
137.6
63.1
(a)
(a)
81.7
14.8
16.6
(a)
328.5
28.6
72.3
127.2
(a)
36.8
62
41.7
58.5
16.5
73.3
0
171.9
176.8
119.5
132.4
195.1
111.2
208.9
67.9
198 ,,8
112
operational.
5-16
-------
100 200 300 400 500
METERS
Figure 5-4, Reference underground mine,
5-n
-------
Page Intentionally Blank
-------
mine, the ground level concentrations resulting from emissions from the
reference mine were calculated for both ground level (all horizontal
vents, i.e., no plume rise) and an elevated release (all vertical vents
with plume rise). A ground level release with no plume rise represents
a worst case assumption in terms of the computed ground level radon-222
concentrations. A release with plume rise represents a lower bound
case for computed radon~222 concentrations. The radon concentrations
computed with these two assumptions will cover the range of concentra-
tions which can result from various local influences on plume rise.
Table 5-9 shows the estimated radon~222 concentrations and
resulting working levels and lifetime fatal cancer risks at various
distances from the shaft of the reference mine for releases with and
without plume rise. The most likely radon-222 concentrations at these
locations will fall somewhere within the range of values shown. These
concentrations were computed using EPA's Industrial Source Complex Long
Term Model (Drc84).
The estimated concentrations from ground level releases shown in
Table 5-9 for distances at 500 and 1000 meters from the mine shaft are
worst case situations with locations sited between a series of mine
vents or relatively close (within a few hundred meters) to one of the
vents where all of the vents involved are horizontal (i.e., no plume
rise). It is unlikely at the present time that such extremely high
concentrations actually exist near an underground uranium mine or that
any individual is actually exposed to these high levels. However, as
shown in Table 5-13, several hundred people are living within 1000
meters of underground uranium mine shafts, and these people are esti-
mated to be exposed to increased radon-222 concentrations somewhere
within the range of values shown for these locations in Table 5-9.
Table 5-10 shows estimated equilibrium ratios for radon at various
distances assuming a wind speed of 1 m/sec from the uranium mine.
Estimates of the radon-222 concentration at various distances from an
underground uranium mine with five vents emitting 11,000 Ci/y of
radon-222 are shown in Table 5-9 (Drc84). Also shown in this table are
the estimated lifetime risks of fatal cancer to nearby individuals from
the inhalation of radon~222 decay products produced (inside a house) by
radon-222 concentrations. Table 5-11 shows the relationship between
working levels and risk. The basic assumptions used in developing this
table are discussed in Chapter 8, Volume I. This relationship is not
linear because of competing risks of death from other causes. Using
the relationship between equilibrium ratio and radon concentrations,
the working level inside a structure at the specified distance is
calculated as shown in Table 5-9. Table 5-11 is then used to estimate
the lifetime risk for a person living in a structure 75 percent of the
time near these sites.
To evaluate the extent to which emissions from multiple mines
located close together will influence the radon-222 concentrations in
5-19
-------
Table 5~9« Estimates of working levels and risk of fatal
cancer in buildings at selected distances from
the reference underground uranium
Ground level release
Distance*-
(meters)
b) Radon-
222*-c
Lifetime
•j Working risk to
levels nearby
V poi/ L,J ( A\
individuals^ '
500
1,000
2,000
3,000
5,000
7,000
10,000
27.6
10.2
2.2
1.1
0.5
0.3
0.2
.113
,045
.011
.006
.003
.002
.001
1E-1
5E-2
1E-2
7E-3
3E-3
2E-3
IE-3
(5E-2)
(2E-2)
(5E-3)
(3E-3)
(2E-3)
(IE-3)
(5E-4)
Release with
Radon-
222^c
{ T-vf-t /I
VpUI/ L,
0.4
0.4
0.2
0.2
0.1
0.1
0.1
) Working
x levels
plume rise
Lifetime
risk to
nearby
individuals*-07
.0016
.0019
.001
.001
.0006
.0006
.0006
2E-3
2E-3
IE-3
IE-3
7E-4
7E-4
7E-4
(8E-4)
(9E-4)
(5E-4)
(5E-4)
(3E-4)
(3E-4)
(3E-4)
'a'The lifetime risks were estimated depending on the equilibrium ratios
calculated in the structures at various distances (See Table 5-10).
* 'The distance is measured from the shaft of the model mine. This is
different from the distances shown in Tables 5-8 and 5-9 of the Draft
Background Information Document (EPA83d) where the distances listed
were distances from, vent 5.
values in the first column are based on BEIR-3, NRPB, and EPA
models (see Chapter 8, Volume I). The values in parentheses are based
on UNSCEAR and ICRP risk estimates (see Chapter 8, Volume I).
Table 5-10, Outdoor and indoor equilibrium ratios for radon emitted
from an underground uranium mine at selected distances from the mine''37'
Distance
Time for plume
to reach distance (min)
Equilibrium ratio
(Outdoors)
(Indoors)
-------
Table 5-11. Relationship between working level
risk of fatal cancer
Working level Lifetime risk
.0001
,001
.01
.1
1B-4
1E--3
1E-2
1E-1
(5B-5)
(5B-4)
(5B-3)
(5B-2)
values in the first column are based on BEIR-3, MRPB, and
EPA models (see Chapter 8, Volume I). The values in parentheses
are based on UNSCEAR and ICRP risk estimates (see Chapter 8,
Volume I).
air, PNL carried out a modeling study using the Ambrosia Lake District
of New Mexico as a "case study" (DrbBl). Using a Gaussian diffusion
model, estimates were made of the radon-222 concentrations in air
resulting from emissions from 117 mine vents. Figure 5-5 shows the
distribution of mine vents used in the study and Figure 5-6 the
computed radon-222 concentrations (above background) in air for this
region. Although these computed concentrations are only approximate
values, because of the complexities of this modeling study, the results
Indicate that the radon-222 concentrations in an intensive underground
uranium mining area will be significantly elevated above background,
The vents are also the greatest sources of the radon concentrations in
the immediate area of mining and milling activities, Another study of
multiple mines done by PNL (Drc84) confirms these conclusions. The PNL
also looked at the effect of plume rise on concentrations from multiple
mines due to vertical vents. If it Is assumed that all the vents in a
multiple mine area are vertical, (pluiae rise), the concentrations are
much lower than if the vents are assured to be horizontal (ground level
release).
Two measurement studies were also conducted in the Ambrosia Lake,
Mew Mexico, area to determine the concentrations of radon around
uranium mines and mills. The EPA conducted the first study in November
1975 (BPA75) at the request of the New Mexico Environmental Improvement
Agency and found that ambient outdoor radon concentrations were in
excess of typical background levels. It was suggested that a better
definition of background levels in the area be determined and a
thorough evaluation of specific source terms be conducted.
In 1978 the New Mexico Environmental Improvement Division
conducted a two-year program (Bu83) to determine (1) sources of high
concentrations of airborne radioactivity in uranium producing areas,
(2) radioactivity levels due to background as well as levels associated
with uranium milling and mining activities, and (3) if New Mexico
5-21
-------
> V ..
1^>
& A * ;Sv •
iwt
U\^> 1
-^~ , ^x~ \c
y/^? - ^*\. \j j
L. ^ .^.~**# ^ i™"T
•^-L f*w—'-^ y
7 V *
- >w>X^
^~v ^
(
f—^-f rt. >>
Stun
10km
Figure 5-5, Detailed map of mining area showing mine vent source.
5-22
-------
5
KILOMETERS
5
Figure 5-6. computed radon concentration map for region isopleths CpCi/L)
5-23
-------
standards are being exceeded. Background radon concentrations were
determined at six representative undisturbed locations within the
Grants Mineral Belt, Uranium mines were found to be the priioary cause
of elevated radon concentrations in Ambrosia Lake. Ambient radon
concentrations near uranium mines exceeded the New Mexico radiation
standard for an individual member (3pCi/l) of the public at three of
the nine locations in the study.
Population Risks
The radon decay product exposures and the number of fatal cancers
per year of operation for the reference underground uranium mine are
shown in Table 5-12, These estimates are for a site near Grants, New
Mexico, with a regional population of 36,000 using AIRDOS-EPA to
calculate the radon exposures (Appendix A). The number of fatal
cancers per year of operation of the reference mine is estimated to be
about 0.04 to the regional population and 0.08 to the national
population.
The inert radon gas emitted from mines can be transported beyond
the 50-mile regional cutoff. A trajectory dispersion model developed
by NOAA (Tr79) has been used to estimate the national impact of radon
emissions from the mine. This model calculates the potential radiation
exposure to the U.S. population for radon released from four typical
uranium processing locations. (Descriptions of these typical mill
sites--Casper, Wyoming; Falls City, Texas; Grants, New Mexico; and
Wellpinitj Washington—are given in (Tr79).) Only exposures taking
place beyond the 50-mile regional limit are considered. Details of the
model are given in He75. The model yields radon concentrations (pCi/L)
in air which were converted to decay product concentrations by assuming
that 100 pCi/L of radon corresponds to a decay product concentration of
0.7 WL.
Table 5-12. Annual radon-222 decay product exposures and number
of fatal cancers to the population from radon-222
emissions from the reference underground uranium mine
Regional population Nat ipnal pppulat ion
Source (Person- (Fatal cancers/y (Person- (Fatal cancer s/y
WL-y) of operation}'3' WL-y) of operation)^3'
Underground
uranium mine 2.2 6E-2 (2E-2) 6.2 1E-1 (6E-2)
values in the first column are based on BEIR-3, NEFB, and EPA
models (see Chapter 8, Volume I). The values in parentheses are
based on UNSCEAR and ICRP risk estimates (see Chapter 8, Volume I).
5-24
-------
Uragium^Mi|iTing
An estimate of the total health impact from radon~222 emissions
from all underground uranium mining (using production values for 1982)
may be made by multiplying the number of fatal cancers caused by
emissions from the reference mine by the ratio of the amount of uranium
produced by all underground mines to the amount produced by the
reference mine. This ratio is about 25. The estimate for the regional
population is about two fatal cancers/year and for the national
population is about three fatal cancers/year.
5.8 Reduction ofExposuresthrough Land Control
Rather than control radon emissions at the source, it may be more
practical to limit the exposure to individuals near underground mines
by controlling land near the vents to prevent people from living in
houses in these areas. At the request of EPA, the Pacific Northwest
Laboratory conducted a field study in January and February 1983 to
determine the population, type of ownership, and cost of land around 30
large uranium mines (Brb83). These mines represented about 84 percent
of the uraniura production from underground mines at that time.
Table 5~13 shows the population data gathered from the PNL study.
An estimate was made of all residents within 5 km of the mine shaft by
locating all the residences on a map. The average 1980 census figure
of residents per home in each county was used to estimate the
population. If mines were close together, populations were evenly
distributed among the mines according to the distances from the mines.
Maps showing the distribution of population around these mines are
located at the end of this chapter.
Table 5-14 represents the percent distribution of land ownership
around the 30 surveyed mines. County tax assessors' records were
reviewed for all properties within a 5-km radius of each mine. The
ownership of the land was determined and percentages, according to
three types of ownership (private, mine, or government), are shown for
each mine. Land values for the private land were estimated from:
(1) assessed valuations and applying applicable selling price to
assessed valuation ratios, (2) estimates from local real estate agents,
(3) information supplied by state and county assessors, and (4) local
newspapers. The valuations were based on surface usage and rights
only, since the mineral values would remain intact.
Table 5-15 summarizes the cost of the land around each mine.
Since the land owned by the mine operator or a government agency can
already be controlled, only costs to purchase private land were
determined.
The Schwartzwalder mine near Denver, Colorado, is not included in
the total cost of all surveyed mines shown in Table 5-15 because it is
5-25
-------
not a typical mine site. It is located near a large metropolitan area
and the cost of the land is quite high since the land can be purchased
or subdivided tor mountain resort homes. The mine is also located in a
mountainous region so that radon emissions may be confined in the
immediate area of the mine and any land control which may be necessary
would be relatively small.
The information in Tables 5-13 through 5-15 can be used to obtain
a rough estimate of the cost to control land around underground uranium
mines. The cost to control land within a 2-km radius of the mines
surveyed is as follows:
Total cost Yearly cost
Type of cost (millions) (millions)
Land cost (100 percent contingency
with 10 percent yearly cost) $15.0 $1.5
Structures (100 percent contingency with
amortization over 5 years at 10 percent) 3.8 1.1
Relocation of 420 non-Indian residents
($5,000/person with amortization
over 5 years at 10 percent) 2.1 0.6
Relocation of Indian residences ($18,000/
person- 198 Indians, with amortization
over 5 years at 10 percent) 3.6 1.1
Total yearly cost 4.3
The 10 percent yearly cost assumes that the land value does not
change and thus is a nondepreciated asset. The present worth factor
Cor amortization over a 5 year period using a 10 percent interest rate
is 0.264. This is rounded to 0.3 to account for taxes.
Assuming that the 29 mines produced 84 percent of the underground
mine yearly production of 6,200 tons of 0303 for the industry
(Brb83)» the cost of land control per pound of 0303 can be
estimated as follows:
cost/lb U,0ft = $4,300,000 = $0.41/lb U308
(.84)(6,200X2,000)
If production costs for 0303 are $30/lb, the increased cost to
the industry would be 1 percent of the cost of production. In a
similar manner, it can be calculated that the cost per ton of ore would
be $1.82/ton of ore. This can then be compared to the cost of radon
control technologies in Table 5-3.
5-26
-------
Table 5-13. Population around selected underground
uranium mines (Brb84)
Mine
Sunday
King Solomon
Velvet
Tony M
Hack Canyon
Pidgeon
Kanab North
Derrao-snyder
Wil son-
Si Iverbell
Lisbon
Lasal
Hecla
Big Eagle
Golden Eagle
Sheep Mtn.
Mt. Taylor
Old church
Rock
Church
Rock-MB
Church
Rock- 1
church
Rock-East
Kerr-McGee
Sec 30 East
Kerr-McGee
Sec 30 West
Kerr-McGee
Sec 19
Kerr-McGee
Sec 35
Kerr-McGee
Sec 36
State
Colo.
Colo.
Utah
Utah
Arizona
Arizona
Ar izona
Colo. /Utah
Utah/Colo.
Utah
Utah
Utah
Wyoming
Wyoming
Wyoming
New Mexico
New Mexico
New Mexico
New Mexico
New Mexico
Mew Mexico
Mew Mexico
New Mexico
New Mexico
New Mexico
Distance from
0-1/2
0
0
0
0
1
0
0
0
0
0
0
16
0
0
0
0
9
0
0
0
3
0
0
0
0
0-1
0
0
0
0
1
0
0
5
0
0
0
16
0
0
0
100
9
11
11
0
3
5
0
0
0
0-2
0
0
0
0
1
0
0
21
0
0
53
20
0
0
0
317
70
22
22
9
3
5
0
0
0
mine
0-3
0
0
0
0
1
0
0
49
12
4
101
40
0
6
0
336
139
26
27
57
3
5
4
0
0
(km)
0-4
0
0
0
0
1
0
0
67
20
44
194
73
0
6
0
336
187
31
31
70
3
5
4
0
0
0-5
0
0
0
0
1
0
0
83
23
44
194
73
0
6
12
336
364
31
31
131
3
6
4
0
0
5-27
-------
fable 5-13. Population around selected underground
uranium mines (Brb84) (Continued)
Mint} State
0-1/2
Horaestake
Sec 23 New Mexico 0
Homestake
Sec 25 New Mexico 0
Nose
Rock^9' New Mexico 0
Mar iano
Lake New Mexico 13
Schwartz-
walder^3^ Colorado 3
Totals 42
Distance from mine (km)
0-1 0-2 0-3 0-4 0-5
00334
00000
0 0 0 26 35
44 75 196 274 352
3 63 102 136 147
205 618 1,009 1,375 1,733
population around this mine is not included in the total
because the location is not typical of the industry.
5-28
-------
Table 5-14. Percent distribution of land ownership around
selected underground uranium mines (Brb84)
Mine
Sunday
King Solomon
Velvet
Tony M
Hack Canyon
Pidgeon
Kanab North
Dermo-Snyder
Wi Ison-
silverbell
Lisbon
LaSal
Hecla
Big Eagle
Golden Eagle
Sheep Mtn.
Mt . Taylor
Old Church
Rock
Church Rock
NE
Church Rock
tl
Church Rock
East
Kerr-McGee
Sec 30 East
Kerr-McGee
Sec 30 West
Kerr-McGee
Sec 19
Kerr-McGee
Sec 35
Kerr-McGee
Sec 36
Distance from mine (km)
0-1/2
0/0/100
0/0/100
14/0/86
0/0/100
0/0/100
0/0/100
0/0/100
84/0/16
80/0/20
0/0/100
8/0/92
25/0/75
0/100/0
60/20/20
30/45/25
75/19/6
0/0/100
0/0/100
0/0/100
0/0/100
11/89/0
11/89/0
0/100/0
0/100/0
5/42/53
0-1
0/0/100
0/2/98
10/0/90
0/0/100
0/0/100
0/0/100
0/0/10Q
87/0/13
95/0/5
0/0/100
25/0/75
25/0/75
0/88/12
89/7/4
18/42/40
58/26/16
0/0/100
0/7/93
0/7/93
0/7/93
4/91/5
24/76/0
23/77/0
0/85/15
14/22/64
0-2
0/0/100
0/5/95
6/0/94
0/0/100
0/0/100
0/0/100
0/0/100
84/0/16
95/0/5
6/0/94
34/0/66
48/0/52
0/80/20
85/3/2
5/28/69
58/16/29
0/0/100
0/23/77
0/23/77
0/6/94
2/70/28
17/72/11
46/39/15
8/59/33
27/14/59
0-3
3/1/97
0/3/97
12/0/88
0/0/100
0/0/100
0/0/100
0/0/100
89/0/11
94/0/6
17/2/81
41/0/59
37/0/63
0/8/92
94/1/5
2/18/80
45/13/42
0/0/100
0/13/87
0/13/87
3/4/93
4/78/18
16/69/15
45/39/16
14/55/31
36/8/56
0-4
8/1/91
0/3/97
24/0/76
0/0/100
0/0/100
0/0/100
0/0/100
85/0/15
91/0/9
21/1/78
34/0/66
28/0/72
0/5/95
91/1/8
4/11/85
39/10/51
2/0/98
0/8/92
0/8/92
5/2/93
10/79/11
22/66/12
32/37/31
10/57/33
36/5/59
0-5
10/1/89
0/3/97
27/0/73
0/0/100
0/0/100
0/0/100
1/0/99
81/0/19
81/0/19
16/1/83
26/0/74
21/0/79
1/3/96
90/1/9
12/8/80
39/7/54
3/0/97
0/5/95
0/5/95
3/1/96
13/77/10
27/57/16
29/38/33
14/52/34
39/3/58
See footnotes at end of table.
5-29
-------
Table 5-14. Percent distribution of land ownership around
selected underground uranium mines (Brb84) (Continued)
Distance from mine (km
(a)
nine
Homestake
Sec 23
Homestake
Sec 25
Nose Rock
Mariano Lake
Schwartz-
Average
0-1/2
74/0/26
100/0/0
0/50/50
0/0/100
100/0/0
20/22/58
0-1
68/0/32
85/0/15
0/50/50
0/0/100
100/0/0
22/20/58
0-2
61/6/33
59/0/41
0/45/55
0/0/100
100/0/0
22/17/61
0-3
50/18/32
58/1/41
0/41/59
0/0/100
100/0/0
23/13/64
0-4
47/11/36
50/2/48
0/38/62
0/0/100
100/0/0
22/12/66
0-5
53/12/35
43/10/47
0/35/65
0/0/100
100/0/0
22/11/67
first figure In the column represents the percent of private
land, the second is land owned by the mine owner, and the third shows
the percentage of land owned by a government agency. For example, in
the case of the Sunday mine (at 0-1/2 km), 100 percent is owned by the
government.
land ownership percentage for the Schwartzwalder mine was not
included in the average for all the mines since the location is not
typical of the industry.
5-30
-------
fable 5-15. Estimated value of private land around
selected underground uranium mines^ (BrbS4)
(In thousands)
Mine
Sunday
King Solomon
Velvet
Tony M
Hack Canyon
Pidgeon
Kanab North
Dermo-Snyder
Wilson-
silverbell
Lisbon
Lasal
Heel a
Big Eagle
Golden Eagle
Sheep Mtn.
Mt, faylor
Old Church Rock
church Rock ME
Church Rock-1
Church Rock- las
Kerr-McGee
Sec 30 East
Kerr-McGee
Sec 30 Vest
Kerr-McGee
Sec 19
Kerr-McGee
Sec 35
Kerr-McGee
Sec 36
0-1/2
NA
MR
5.5
NR
NA
Nft
NA
79.7
39.1
NR
4.0
36.8
NA
35.4
18.0
39.6
Nft
NR
NA
t NA
35.0
31.1
Nft
Nft
3.4
0-1
NA
NA
16.0
NA
NA
Nft
NA
260.4
186.4
Nft
228.4
147.3
NA
209.0
42.3
391.5
Nil
NA
MA
MA
35.0
132,2
194,4
NA
23.5
Distance 1
0-2
NA
NA
36.0
NA
NA
NA
Nfi
922,6
535,8
50.0
920,9
380.0
NA
796.2
42.3
2,523.7
MA
MA
MA
MR
35.0
147.8
844.8
37,0
124.3
from mine
0-3
48.0
Hft
172,8
NA
Nft
MA
MR
1,852.1
1,667.2
306.0
1 , 427 . 8
691.0
m.
2,121.0
42.3
2,834.2
NA
HA
NA
122.2
53.5
157.9
1,229.4
137.8
336.0
(kml
0-4
208.0
MA
603.2
MA
NA
Nft
NA
3,028.9
2,861.6
810.5
2,484.5
965.9
NA
3,584.0
150.0
3,227.4
543.3
NA
NA
355.6
147.6
194.8
1,405.1
168.0
588.0
0-5
384,0
NA
1,048,0
NA
NA
WA
(b)
4,432,8
3,968.7
810.5
2,534.5
1,000.5
NA
5,231.0
898.0
3,918.8
1,443.1
NA
NR
355.6
240.0
235.1
1,532,8
336.0
977.8
See footnotes at end of table.
5-31
-------
Table 5-15. Estimated value of private land around
selected underground uranium mines^a' (Brb84) (Continued)
(In thousands)
Mine
Homes take
Sec 23
Home stake
Sec 25
Nose Rock
Mariano Lake
Schwartz-
walder^c'
Totals
0-1/2
217.8
295.6
NA
NA
880.0
841.0
0-1
528.0
622.2
NA
NA
3,400.0
3,016.6
Distance
0-2
994.1
987.8
MA
NA
15,200.0
9,378.2
from mine
0-3
1,158.7
1,478.0
MA
NA
33,600.0
15,835.8
(km)
0-4
1,485.2
1,632.2
NA
NA
58,400.0
24,443.8
0-5
2,361.8
1,645.6
NA
NA
89,200.0
33,354.6
cost of land (80 percent) and structures (20 percent).
100 acres of patented mining claims.
costs for this mine were not included in the total costs
because the location and cost of land is not typical of the industry.
NA Not assessed; all land owned by either the mine owner or the
government.
5-32
-------
112°S6'
K ,„,_,%(,'"•.-
i> ""C, / ; v>
Jk-
UJ
ft
:•• KnbHs
• > ^ ' ' " ' / •>
s >-^? '-/-ft]
' ; -IA£* - -:/ f
POPUtATIOSI DiSTSIlBlfnON
0-1/a km 0-1 km 0-2 km 0-3 Ism 0-4 tow
HACK
. CANYOM
ALL
LOCATION; POPULATION DISTRIBUTION I o
i 1
123
AMI J.l
I MILES
KILOMETERS
LEGEND:
@ SW@Li OCCUPIED
@ OCCUPIED OWEIUNG
(HO, IS STRUCTURES!
3 MiWS SHAFT
-------
112°3S'
112°30'
POPULATION DISTFU8UTIQN
0-J/2Jm fiM_Nm Q-2Jcm O-SJcm ^jjcro O;Sjgg
KANAB
0 09000
PIGEON 0 00000
01234
1
-j = ^ MtlKS
ag^^__aaa=JaJ»t^4^J? KILOMETERS
@ SIW6LE OCCUPIED I
(2) OCCUPIED DWELL1NS
IS STRUCTURES!
B MINE SHAFT
-------
0-1/2km 0-1 SCOT 0*2 km 0-3 km 0-4 km 9-SScm
. MILES
KILOMETERS
•
(2) OCCUPIED
{SO. ""
a
-------
ALL OCCUPIED
LOCATION; POPULATION
POPULATION DISTRIBUTION
SUNDAY
MILES
JmummA^mJtii^mjg KILOMETERS
« SINGLE OCCUPIED
0 OCCUPIED f
(NO, IS STRUCTURES)
B mim SHAFT
-------
107"S5'
107°50'
107045'
107°40'
*-J
HOWESTAKE SEC Z3OT
x f~^ f \ \ ^
J -x./ I-' _V _ L ^N _».,-^
. (J J ^
POPt'LATION DiSlRIBUTiON
0-1/2km 0-1 km 0-2 fern 0-3 km 0-4 km 0-5 km
LEGEND:
SINGLE OCCUPIED DWELLING
(7) OCCUPIED DWELLING CLUSTER
KEBS-McGEE SEC. 306 3 3 3 333
KERR'-MoGEE SEC. SOW 0 S 6 5 5
KERR-McQEE SgC. 19 0 0 0 4 4
KEBR.-MOGEE SEC. 36 o o o o o o
.38 0 0 0 0 0 0
MOMESTfMCE SEC. 23 0 0 0 334
HOMcSTAKE SEC. 25000 000
{NO. IS STRUCTURES)
B MiNE SHAFT
-------
OLD CHURCN RUf t
CHURCH ROCK HF
CHURCH ROCK K
CHURCH POL US-/*-!
0 (
eTT"
-------
POPULATION DISTRIBUTION
MINE_ _______ 0-1 /2km OilAl1 Qi3-t03 tJli™
44
13
7S 198 274 352
MILES
LEGEND;
• SINGLE OCCUPIED DWELLING
@ OCCUPIED DWELLING CLUSTER
(NO, IS STRUCTURES}
H SHAFT
5-39
-------
107035'
MT.
CIBOLA
ALL OCCUPIED DWELLINGS; DISTRIBUTION
POPULATION DISTRIBUTION
MINE
05jjm
MT.TAYLQR 0 100 317 330 33i
LEGEND:
» SINGLE OCCUPIED DWELLING
(z) OCCUPIED DWELLING CLUSTER
1 2
: MiLES
{NO. IS STRUCTURES)
3 MINE SHAFT
«JI
5-40
-------
MIME, McKINLEY COUNTY, NEW MEXICO
ALL SHAFT LOCATION; POPULATION DISTRIBUTION
POPULATION DISTRIBUTION
MINE 0-1/2km 0-1 km 0-2km Q-Sfwn 0-4km 0-5km
NOSE
ROCK
26
35
« MitES
KILOMETERS
LEGEND:
© SINGLE OCCUPIED DWELLING
@ OCCUPIED DWEtLISMG CLUSTER
(NO. IS STRUCTURES)
H MINE SHAFT
5-41
-------
SAN JUAN
ALL OCCUPIED SHAFT LOCATIONS; POPULATION DISTRIBUTION
MINE
DiRMO-
SNYDEK
WILSON-
SILVERBELL
0 1
POPULATION DISTRIBUTION
(Mkm CK2ton O^Uffi Oj4km 0;6km
S 21 4S 67 83
20 23
i MILES
KflQMITERS
LEGEND:
• SINGtE OCCUPIED DWELLING
(z) OCCUPiED DWELLING CLUSTER
{NO. IS STRUCTURES!
QS MINE SHAFT
5-42
-------
, LjSiQN/taSAL/HECLA
SAN JUAN COUNTY, UTAH
ALL OCCUPIED DWELLINGS; MINE SHAFT
LOCATIONS; POPULATION DISTRIBUTION
POPUlATt
0-1/2fcHi 0-1 tun 0-2ton
U8BON !' 0! S"0
DISTRIBUTION
04fcm 0-SJan
LaSAi
KECLA
0 4 44 44
53 101 194 194
lie! | JTOi .40—73 73
2 3 4 .
6 1 2 a m
iMilES
KILOMETERS
LEGEND:
® SINQLE OCCUPIED DWELLING
(J) OCCUPIED DWELLING CLUSTER
(NO. )S STRUCTURES)
B MINE SHAFT
-------
106°60'
I
r06°46'
tOB°«P'
, :-:-r....
106°36'
TONY M MINE
I3ARFIELD COUNTY, UTAH
ALL OCCUPIED DWELLINGS; MINE SHAFT
LOCATIONS; POPULATION DISTRIBUTION
POPULATION DISTRIBUTION
0-1/2km 0-lfcm 0-2km 0-3km Qj^ftei 0-Bkm
TONYM 0 0 0000
MINE
.MILES
a i * KILOMETERS
LEGEND:
9 SiNGLE OCCUPIED DWSLLiNS.
0 OCCUPIED DWELLING CLUSTER
CNO, IS STROCTURISI
U MINE SHAFT
-------
(SI
\
a OCCUWED i
ALL OCCUPIED DWELLINGS; MINE
LOCATION; POPULATION DISTRIBUTION
-------
BIG EAGLE/SHEEP MOUNTAIN
ALL OCCUPIED DWELLINGS; MINE
MINE
BIG EAGLE
SHEEP
MOUNTAIN
POPULATION DISTRIBUTION
0-172km
-------
1O6"46'
•=06° 36
Ut
BILL SMITH/GOLDEN EAGLE
CONVERSE COUNTY, WYOfyilNG
ALL OCCUPIED DWELLINGS; MINE SHAFT
LOCATIONS; POPULATION DISTRIBUTJOW
MINE
BILL SMITH
GOI.DEW
EAGLE
0 1
POPULATION DISTRIBUTION
0-1/2km Chljcm 0-2 km 0-3 km O£fcm 0-5 km
0
0
0
0
0
0
8
fiSILiS
&
s
8
I KILOMETERS
LEGEND.
® SINGLE OCCUPIED DWiUJNS
© OCCUPIED DWELLING CLUSTER
(NO. IS STRUCTURES!
Q| MINE SHAFT
-------
REFERENCES
B184 Bloomster C. H., Jackson P. 0., Dirks J. A., and Reis J. W.,
Radon Emissions from Underground Uranium Mines, Draft Report,
Pacific Northwest Laboratory, 1984.
BraSl Brown S. H. and Smith R. C., A Model for Determining the
Overall Radon Release Rate and Annual Source Terra for a
Commercial In-Situ Leach Uranium Facility, Proceedings of
International Conference on Radiation Hazards in Mining:
Control Measurement, and Medical Aspects, Colorado School of
Mines, Golden, Colorado, October 1981.
Brb84 Bruno G. A., Dirks J. A., Jackson P. 0., and Young J. K.,
U.S. Uranium Mining Industry: Background Information on
Economics and Emissions, Pacific Northwest Laboratory,
PNL-5035 (UC-2, 11, 51) March 1984.
Bu83 Buhl T., Millard J., Baggett D., Brough T., and Trevathan S.,
Radon and Radon Progeny Concentration in New Mexico's Uranium
Mining and Milling District, New Mexico Health and
Environment Department, 1983.
DOE83 Department of Energy, Statistical Data of the Uranium
Industry, GJQ-1QO(83), Grand Junction, Colorado, January 1983.
Dra80 Droppo J. G., Jackson P. 0., Nickola P. W., Perkins R. W.,
Sehmel G. A., Thomas C. W., Thomas V. W., and Wogman N. A.,
An Environmental Study of Active and Inactive Uranium Mines
and Their Effluents, Part I, Task 3, SPA Contract Report
80-2, EPA, Office of Radiation Programs, Washington, B.C.,
August 1980.
DrbSl Droppo J. G. and Glissmeyer J. A., An Assessment of the Radon
Concentrations in Air Caused by Emissions from Multiple
Sources in a Uranium Mining and Milling Region. A Case Study
of the Ambrosia Lake Region of New Mexico, Pacific Northwest
Laboratory, PNL-4033, December 1981,
Drc84 Droppo J. G., Modeled Atmospheric Radon Concentrations from
Uranium Mines, Draft Report, Pacific Northwest Laboratory,
PNL-52-39, September 1984.
EPA79 Environmental Protection Agency, Radionuclide Impact Caused
by Emissions of Radionuclides into Air in the United States,
EPA 520/7-79-006, EPA, Office of Radiation Programs,
Washington, D.C., August 1979.
5-48
-------
REFERENCES—continued
EPA83a Environmental Protection Agency, Eegulatory Impact Analysis
of Final Environmental Standards for Uranium Mill Tailings at
Active Sites, EPA 520/1-83-010, EPA, Office of Radiation
Programs, Washington, B.C., September 1983.
EPA83b Environmental Protection Agency, Potential Health and
Environmental Hazards of Uranium Mines Wastes, EPA
520/1-83-007, EPA, Office of Radiation Programs, Washington,
B.C., June 1983.
EPA83c Environmental Protection Agency, Final Environmental Impact
Statement for Standards for the Control of Byproduct
Materials from Uranium Ore Processing (40 CFR 192), Volume II,
page A.2-33, EPA 520/1-83-008-2, EPA, Office of Radiation
Programs, Washington, B.C., September 1983.
EPA83d Environmental Protection Agency, Background Information
Document—Proposed Standards for Radionuclide Draft Report,
EPA 520/1-83-001, EPA Office of Radiation Programs,
Washington, D.C., March 1983.
FraSl Franklin J. C., Control of Radiation Hazards in Underground
Mines, Bureau of Mines, Proceedings of International
Conference on Radiation Hazards in Mining: Control
Measurement, and Medical Aspects, Colorado School of Mines,
Golden, Colorado, October 1981.
FrbSl Franklin J. C. and Weverstad K. B., Radiation Hazards in
Backfilling with Classified Uranium Mill Tailings,
Proceedings of the Fifth Annual Uranium Seminar, Albuquerque,
New Mexico, September 20-23, 1981.
Frc83 Written communication between J« C. Franklin of the Bureau of
Mines and W. J. Shelley of the Kerr-McGee Corporation, May
1983.
He75 Heffter J. L., Taylor A. D., and Ferber G. J., A Regional-
Continental Scale Transport, Diffusion, and Deposition Model,
NOAA Tech. Memo, ERL/ARL-50, 1975.
Ho84 Hopke P. K., Leong K, H., and Stukel J. J., Mechanisms for
the Removal of Radon from Waste Gas Streams, EPA Cooperative
Agreement CR 806819, UILU-ENG 84-0106, Advanced Environmental
Control Technology Research Center, 3230 Newmsrk Civil
Engineering Laboratory, 208 Horth Romine Street, Urbana,
Illinois 61801, March 1984,
5-4
-------
REFERENCES—continued
Ja80 Jackson P. O.s Glissmeyer J. A., Enderlin W. I., Sehwendimam
L. C., Wogman N. A., and Perkins R. W., An Investigation of
Radon-222 Emissions from Underground Uranium Mines—Progress
Report 2, Pacific Northwest Laboratory, Richland., Washington,
February 1980.
Ko80 Kown B. T., VanderMast V. C., and Ludwig K. L., Technical
Assessment of Radon-222 Control Technology for Underground
Uranium Mines, ORP/TAD-80-7, Contract No. 68-02-2616, EPA,
Office of Radiation Programs, Washington, D.C., April 1980.
N8C80 Nuclear Regulatory Commission, Final Generic Environmental
Impact Statement on Uranium Milling, NUREG-Q7Q6, Office of
Nuclear Material Safety and Safeguards, NRC, Washington,
D.C., September 1980.
Th81 Thomas W. V., Musulin C. S., and Franklin J. C., Bulkheading
Effects on Radon Release from the Twilight Uranium Mine,
PNL-3693 (UC-11). Prepared for EPA under a Related Services
Agreement with DOE, Pacific Northwest Laboratory, Richland,
Washington, June 1981.
Tr79 Travis C. C., Watson A. P., Me Dowel1-Boyer L, M., Cotter
S. J., Randolph M. L., and Fields D. E., A Radiological
Assessment of Radon-222 Released from Uranium Mills and Other
Natural and Technologically Enhanced Sources, QRNL/NUREG-55,
ORNL, Oak Ridge, Tennessee, 1979,
5-50
-------
Chapter 6: PHOSPHATE INDUSTRY FACILITIES
6. 1
6.1.1 General Descript ion
Phosphate rock is the starting material for the production of all
phosphate products. Mining of phosphate rock is the fifth largest
mining industry in the United States in terms of quantity of material
mined (DM68). Phosphate rock mines of significant commercial
importance are located in Florida, North Carolina, Tennessee, Idaho,
Wyoming, Utah3 and Montana (Figure 6.1-1),
The U.S. production of phosphate rock was estimated to be 57.9
million metric tons in 1978 with production increasing an average of
about 5 percent per year (EPA79). The industry consists of 20 firms
which are currently mining phosphate rock at 31 locations. Another
five mines are expected to be operational by 1983, and four others have
been planned with indefinite start-up dates. Most firms have mining
operations and rock processing plants at the same location, while a few
companies mine in several areas and ship the rock to a central
processing plant. Table 6.1-1 shows the phosphate rock producing
companies, plant locations, 1977 production, and percent of U.S. market.
The southeastern U.S. is the center of the domestic phosphate rock
industry, with Florida, North Carolina, and Tennessee having over 90
percent of the domestic- rock capacity. Florida, with approximately 78
percent of 1978 domestic capacity, dominates the U.S. industry and is
the world's largest phosphate rock producing area. Most of these
plants are located around Polk and Hillsborough counties in Central
Florida, with expansion taking place in Hardee and Manatee counties.
Hamilton County, located in North Florida, is another phosphate rock
producing area.
Tennessee's phosphate rock industry, located in the middle of the
State, has declined in importance over the last several years and is
now the least important rock producing area in the country. The
Tennessee Valley Authority and two private corporations have
discontinued mining in Tennessee, and no new plant expansion is planned.
6.1-1
-------
/ \
Figure 6,1-1. Geographical location of phosphate rock operations.
6.1-2
-------
Table 6.1-1. Phosphate rock producers and capabilities (EPA79)
1977 production „ -
,,. , , , Percent of
„ , , (Metric tons) . . ,
Company and location CinS'i total
International Minerals and Chemicals 11,340 20,5
Bonnie, Florida
Kings ford, Florida
Noralyn, Florida
Agrico Chemical Co. (Williams) 8,618 15.6
Pierce, Florida
Ft. Green, Florida
Occidental Agricultural Chemicals 2,722 4.9
White Springs, Florida
Mobile Chemical 4,264 7.7
Nichols, Florida
Fort Meade, Florida
Brewster Phosphate 3,175 5.7
Brews ter, Florida
Bradley, Florida
U.S. Steel-Agri-Chera, Inc. 1,814 3.3
Ft. Meade, Florida
Gardinier 1,966 3.6
Ft. Meade, Florida
Swift Chemical 2,903 5.3
Bartow, Florida
W.R. Grace & Company 4,808 8.7
Hookers Pr. , Florida
Bonnie Lake, Florida
Manatte Co., Florida
Borden Chemical Company 907 1.6
Teneroc, Florida
Big Four, Florida
T-A Minerals 454 0.8
Polk City, Florida
6.1-3
-------
6.1-1. Phosphate rock producers and capabilities (EPA79)
(Continued)
Company and location
Beker Industries
Dry Valley, Idaho
J. R. Simplot
Ft. Hall, Idaho
Coininco-- American
Garrison s Montana
George Relyea
Garrison, Montana
Texasgulf
Auroras North Carolina
Stauffer Chemical Company
1977 production
(Metric tons)
(103)
1,089
1,814
249
91
4,536
1,950
Percent of
total
2.0
3.3
0.5
0.2
8.2
3.5
Mt. Pleasant, Tennessee
Vernal, Utah
Wooley Valley, Utah
Hooker Chemical Company
Columbia, Tennessee
Presnell Phosphate
Columbia, Tennessee
Monsanto Industrial Chemical Co,
Columbia, Tennessee
Henry, Idaho
454
454
1,814
0.8
0.8
3.3
SurajoarybyRegion
Florida
North Carolina
Tennessee
Western States
78.3
7.8
4.1
9.8
6.1-4
-------
North Carolina possesses a rich phosphate rock deposit in Beaufort
County along the Patalico River. Texasgulf, the only company currently
exploiting this resource, recently expanded plant capacity by 43
percent and has plans for further expansion. Another company has
announced plans for a large operation in Washington, North Carolina.
The western U.S. phosphate rock industry is located in eastern
Idaho, northern Utah, western Wyoming, and southern Montana. This area
accounts for almost six million metric tons per year of the U.S.
capacity, or about 10 percent. Six companies currently operate seven
mines and six processing plants.
The U.S. industry is relatively concentrated as the 10 largest
producers control about 84 percent of the capacity. The two largest
companies control over 34 percent. In the Florida region, two firms
have nearly 44 percent of the State's capacity, while the five largest
companies control over 70 percent (EPA79).
The principal ingredient of the phosphate rock that is of economic
interest is tricalcium phosphate, Ca3(PO/j.)2. However, phosphate
rock also contains appreciable quantities of uranium and its decay
products. The uranium concentration of phosphate rock ranges from 20
to 200 ppm which is 10 to 100 times higher than the typical uranium
concentration in rocks and soils (2 ppm). The radionuclides of
significance which are present in phosphate rock are: uranium-238,
uraniunr-234, thorium-230, radium~226, radon~222, lead-210, and
polonium-210. Because phosphate rock contains elevated concentrations
of these radionuclides, handling and processing the rock can release
radionuclides into the air either as dust particles, or in the case of
radon-222, as a gas.
6.1.2
After phosphate rock ha.s been mined and beneficiated, it is
usually dried and ground to a uniform particle size to facilitate
processing. The drying and grinding operations produce significant
quantities of particulate material (phosphate rock dust).
Phosphate rock is dried, in direct-fired rotary or fluidized-bed
dryers. The rock contains 10-15 percent moisture as it is fed to the
dryer and is discharged when the moisture content reaches 1-3 percent.
Dryer capacities range from 5 to 350 tons per hour (tph), with 200 tph
a representative average.
Crushing and grinding are widely employed in the processing of
phosphate rock. Operations range in scope from jaw crushers which
reduce 12-inch hard rock to fine pulverizing mills which produce a
product the consistency of talcum powder. Crushing is employed in some
locations in the western field; however, these operations are used for
less than 12 percent of the rock mined in the U.S. Fine pulverizing
mills or grinders are used by all manufacturers to produce fertilizer.
Roller or ball mills are normally used to process from 15 to 260 tph.
6.1-5
-------
Some phosphate rock must be calcined before it can be processed.
The need for calcining is determined primarily by the quantity of
organic materials in the beneficiated rock. Since Florida rock is
relatively free of organies, it usually is not calcined. Most
calcining is done in fluidized-bed units, but rotary calciners are also
used. The rock is heated to 14GG°-16QO° F in the calciner to remove
unwanted hydrocarbons. Calciners range in capacity from 20 to 70 tph;
a representative average is about 50 tph (EPA79).
6,1.3 ControlTechnology(TRW82)
At phosphate rock plants, the normal sequence of operation is:
mining, beneficiation, conveying of wet rock to and from storage,
drying or calcining, conveying and storage of dry rock, grinding, and
conveying and storage of ground rock.
Over 98 percent of the phosphate rock produced in the United
States is mined from ground where the moisture content is high enough
to preclude particulate emissions during extraction of the ore. In the
relatively small amount of mining performed in areas where ground
moisture content is not sufficient to prevent emissions, such as the
hard rock areas of Utah and Wyoming, some particulates are generated
during blasting and handling of the overburden and ore body. These
emissions are minimized by wetting the active mining area with water
from tank trucks.
Beneficiation is performed in a water slurry. Since the rock is
wet, it does not become airborne and presents no particulate problem.
Mined rock is normally moved by conveyor belts. Some are open, others
closed for weather protection. In all except the relatively small
plants in the hard rock areas of Utah and Wyoming, the high moisture
content of the rock prevents emission of particulates. Weather-
protected conveyors also offer some emission control in arid or windy
locations.
Particulates from conveying and storage of ground rock are due
primarily to fugitive emissions. Conveying and storage of ground rock
usually takes place in totally enclosed systems, where proper
maintenance will minimize fugitive losses,
Particulate emissions from dryers, calciners, and grinders could
be reduced by applying particulate control equipment to "non-fugitive"
emission sources.
Controlled emission levels from dryers and calciners can vary
considerably from unit to unit, even with the same control device, due
primarily to the effects of feed rock characteristics. Industrial
representatives have indicated that feed rock characteristics greatly
outweigh the effects of dryer or calciner unit types. Several feed
rock characteristics can affect the emission levels and particle size
6.1-6
-------
distribution of the exhaust gas streams. Surface properties affect
emission levels; rough or pitted surfaces can have greater clay
adhesion, resulting in higher emission levels and smaller average
particle size.
During beneficiation, the least-washed rock will have more finess
higher emission levels, and smaller average particle size. The
residence time during which the rock is dried or calcined may also
affect emission levels. Although increasing the residence time may
lower particulate concentration per volume of exhaust gas, the total
weight of particulate emission per weight of feed rock will increase.
Other feed rock characteristics can also cause fluctuations in the
particulate emission levels.
Coarse pebble rock from Florida is beneficiated the least and has
the longest residence time in the dryer of all Eastern rock. Along
with other properties, including hardness and clay adhesion, these
properties cause coarse pebble rock to produce the most adverse, or
worst-case, control levels for Eastern operations. However,
unbeneficiated Western rock has a slightly smaller average particle
size than Eastern rock and represents the most adverse of all feed rock
control situations.
Prjer and J3a_lciner Controls
Phosphate rock calciners and dryers have similar emission
characteristics. Scrubbers are the most common control device used in
the operation of phosphate rock dryers and calciners. Probably the
most important design parameters for scrubbers are the amount of
scrubber water used per unit volume of gas treated (liquid-to~gas
ratio) and the intimacy of contact between the liquid and gas phases.
The latter parameter is generally related to the pressure drop across
the scrubber. Because of the similarities in emissions from dryers and
calciners, scrubbers can attain similar reduction efficiencies; up to
greater than 99.0 percent, for high-energy venturi scrubbers.
Electrostatic precipitators (ESP) can be an economical control
technique. Plate (electrode) voltage and the ratio of plate area to
the volume of gas to be treated are the most important design
parameters of an ESP. Particle resistivity and the ease of cleaning
collected dust from the plates also affect ESP performance.
Electrostatic precipitation is sometimes an economically attractive
control technique in cases where fine dust particles predominate.
Removing fine particles with a venturi scrubber requires relatively
large power inputs (high pressure drops) to achieve the necessary
efficiency. If power cost savings effected by the ESP exceed the
increased capital charges, this system can be more economical than the
venturi scrubber.
Two phosphate rock dryers now use electrostatic precipitators.
One has a conventional dry ESP to control emissions from two rotary
6.1-7
-------
dryers. the precipitator was designed for 95 percent efficiency, but
typically operates at 93 percent. The other uses a wet ESP to control
emissions from two dryers operated in parallel, one a rotary design arid
the other a fluid bed. The ESP was designed for an efficiency of 90
percent, but is probably operating at a higher efficiency because the
gas flow rate is about 60 percent of design capacity. With variation
in plate voltage and plate area, ESP's can be designed to achieve
reduction efficiencies up to greater than 99 percent. A calciner at
one existing operation has a two-stage, dry ESP which operates with an
indicated overall efficiency of 99.8 percent.
No fabric filters are known to be in use for phosphate rock dryer
and calciner emission control. Many industry members believe that
moisture condensation would be a major problem because water droplets
could mix with the clay-like dust mat formed on the fabric media and
cause a mud cake. Were this condition to occur, it would "blind" the
bags. Furthermore, since the dust usually has no economical value, dry
recovery for reprocessing is not an attractive incentive to operators.
High exhaust gas temperatures associated with calciners are also
commonly cited as a major difficulty expected with this type control
device. However, manufacturers of these devices believe fabric filters
can be effective for this application. They state that successful
operation of fabric filters are common in more difficult operations,
such as asphalt plants, cement plants, fertilizer dryers, and the clay
industry. Under proper operating conditions, fabric filters generally
exceed 99 percent efficiency.
Grinder Controls
Dried and calcined rock is ground before it is used for the
manufacture of fertilizers. The grinding or milling circuit operates
under slightly negative pressure to prevent the escape of gases
containing ground rock dust. The system is not airtight; hence, the
air that is drawn into the system must be vented. This vent stream
usually discharges through a fabric filter or, sometimes, a wet
scrubber. Electrostatic precipitators are not used for this operation
at existing facilities.
Fabric filters are normally used to control emissions from
grinders, probably because the dust collected by a fabric filter can be
added directly to the product and thereby increase yields. Also, the
low moisture content of 5 percent or less and low temperatures make
fabric filtration technically and economically feasible. A well
maintained and operated baghouse routinely controls particulate
emissions to levels greater than 99 percent.
In some plants higher moisture content of the ground rock dust
causes difficulty. At these plants, wet collectors are usually chosen
for control. These devices can typically control emissions from 90 to
6.1-4
-------
98 percent depending on the pressure drop. There has been a recent
move toward wet grinding of rock for the manufacture of wet-process
phosphoric acid (WPPA). The rock is ground In a water slurry, then
added to the WPPA reaction tanks without drying. This offers the
advantages of lower fuel costs and ability to meet more stringent
particulate emission regulations. Two companies are now using the wet
grinding process.
6.1.4 Ra dio nuc
Measurements
Phosphate rock dust is a source of particulate radioactivity in
the atmosphere because the dust particles have approximately the same
specific activity (pCi/g) as in the phosphate rock. Very limited data
are available for actual field measurements of radioactivity in
dryer/grinder air emissions. Measurements made by EPA (EPA78) are
summarized in Table 6.1-2.
Table 6.1-2. Radionuclide stack emissions measured
at phosphate rock dryers (EPA78)
Parameter
Total particulates (g/y)
Operating time (hr/y)
Stack emissions (Ci/y)
Uranium-234
Uranium-235
Uranium-238
fhorium-227
Thorium-228
Thoriuni-230
Thoritmr-232
Radium-226
Dryer 1
2.2E+7
4114
7.0E-4
3.0E-5
6. 6E ~4
S.QE-5
1.4E-4
9.7E-5
3.0E-5
9.3E-4
Dryers 3 and 4
5.0E+7
4338
2.6E-3
2»4E-4
2.7E-3
2.0E-4
2.3E-4
2.5E-3
8.0E-5
2.9E-3
More recently, in 1983 and 1984, EPA measured the radionuclide
emissions from phosphate-rock calciners. Because calciners operate at
a higher temperature than dryers, they have the potential for
volatilizing lead-210 and polonium-210. Information on the
measurements made at calciners at elemental phosphorus plants is
presented in Section 6*3, (Note: phosphate rock processing at
6.1-9
-------
elemental phosphorus plants has been analyzed separately from other
phosphate rock processing facilities,} An analysis of the results of
measurements at calciners at wet process phosphoric acid plants has not
yet been completed and the following sections do not include an
assessment of the health impact of radlonuclide emissions from these
calciners.
6.1.5 Reference_Pl_an_t
Table 6.1-3 describes the parameters of a reference phosphate rock
drying and grinding plant which are used to estimate the radioactive
emissions to the atmosphere and the resulting health impacts. The
radioactive emissions from the reference plant are listed in Table
6.1-4, These emissions are representative of dryers with low energy
scrubbers which releases 130 grama of partieulates per MT of rock
processed and of grinders with medium energy scrubbers which release 25
grams of particulates per MT of rock processed.
Table 6.1-3. Reference phosphate rock drying and grinding plant
Parameter
Dryers
Grinders
Number of units^a'
Phosphate rock processing
rate (MT/y)
Operating factor (hr/y)
Uranium-238 content of
phosphate rock (pCi/g)(b)
Stack parameters
Height (meters)
Diameter (meters)
Exit gas velocity (m/s)
Exit gas temperature (°C)
Type of control system
Particulate emission rate (g/MT)
3
2.7E+6
6570
40
20
2
10
60°
Low energy
scrubber
130 (0.26)(c)
4
1.2E+6
6460
40
20
2
10
60°
Medium energy
scrubber
25
units process 145 MT/hr; grinder units process 45 MT/hr.
Uranium-238 is assumed to be in equilibrium with its daughter
products.
in Ib/ton.
6.1-10
-------
Table 6.1-4. Radlonuclide emissions from the reference
phosphate rock drying and grinding plant
n ,. ... Emissions (Ci/y)
Had lonuc 1 ide — - •^~
Dryers Grinders
Uranium-238
Uranium-234
Thoriuni-230
Radium-226
Lead-210
Polonium-210
1.4E-2
1.4E-2
1.4E-2
1.4E-2
1.4E-2
1.4E-2
l.OE-3
l.OE-3
l.OE-3
l.OE-3
l.OE-3
l.OE-3
6.1.6 Health Impact Assessment of Reference Plant
The estimated annual radiation doses from radionuclide emissions
from the reference phosphate rock drying and grinding plant are listed
in Table 6.1-5. These estimates are for a model site in central
Florida with a regional population of 1.4E+6. The nearby individuals
are located 750 meters from the plant.
Table 6.1-6 presents estimates of the lifetime risk to nearby
individuals and the number of fatal cancers per year of operation from
these doses.
The lifetime risk to nearby individuals is estimated to be about
1E-5 and the number of fatal cancers per year of operation is estimated
to be 1E-3. These risks result primarily from doses to the lung from
inhalation of radioactive particulates released from drying operations.
6.1.7 Existing EmissionStandards and Air Pollution Controls
No Federal or State regulations currently exist that limit
radionuclide emissions from phosphate drying, calcining, and grinding
operations. Particulate emissions from these sources are limited by
New Source Performance Standards (NSPS) which apply to facilities
constructed after September 1979, or State Implementation Plans (SIPs)
which cover sources operating prior to September 1979.
NSPS limits for phosphate rock processing are 30 g/MT for dryers,
115 g/MT for calciners handling unbeneficiated rock or a blend of
beneficiated and unbeneficiated rock, 55 g/MT for calciners handling
beneficiated rock, and 6 g/MT for grinders.
SIP limits for phosphate rock operations are less stringent than
NSPS limits. Florida, where approximately 80 percent of the industry
6.1-11
-------
is located, has established the most stringent SIP requirements,
limiting emissions from 30, 100} and 500 Cons/hour processing sources
to 30s 36 s and 47 Ib/hour, respectively. SIP limits in the other six
States where commercial facilities are located are 40, 51, and 79
ib/hour for processing rates of 30, 100, and 500 tons/hour-
6.1.8 Alter native^Control Technology
The annualized costs and risk reductions achieved by adding
alternative controls to the reference phosphate rock drying and
grinding plant are shown in Table 6,1-7. Two alternative levels of
control are evaluated for dryers:
1. Reduction of the particulate emissions to 50 g/MT through the
use of medium energy venturi scrubbers or ESP's.
2. Reduction of the particulate emissions to 30 g/MT (level of
New Source Performance Standards—NSPS) through the use of
high energy venturi scrubbers or high energy ESP's.
For grinders, only one alternative level of control is evaluated; the
reduction of the particulate emissions to 6 g/MT (level of NSPS)
through the use of fabric filters or high energy venturi scrubbers.
Table 6.1-5. Annual radiation dose from radioactive particulate
emissions from the reference phosphate rock drying and grinding plant
Nearby individuals Regional population
Organ / / x , / \
vmrem/yj Iperson-rem/yJ
Lung
Endosteum
Red marrow
Kidney
7.2
1.5EH
1.3
1.0
6.0E+1
1.1E+2
9.2
6.8
Table 6.1-6. Fatal cancer risks due to radioactive emissions
from the reference phosphate rock drying and grinding plant
Lifetime risk Regional population
to nearby individuals (Fatal cancers/y of operation),
Dryers 1E-5 1E-3
Grinders IE-6 IE-4
Total 1E-5 1E-3
6.1-12
-------
Table 6.1-7. Annualized cost and risk reductions of alternative
controls for the reference phosphate rock drying and grinding pla
Process _ ^ ,
Control
option^)
JDryers(k) Existing
B-l
B-2
A-l
A-2
Grinders Existing
A-l
A-2
Mission
rate
(g/MT)
130
50
50
3Q(d)
30
25
6
Total
annua 1
cost (°
($1,000)
861
1770
1000
2320
124
4
Fatal cancer risks
Risk to
' nearby
individuals
1E-5
4E-6
4E-6
2E-6
2E-6
1E-6
2E-7
2E-7
Population
(cancer s/y of
operation)
1E~3
4E-4
4E-4
2E-4
2E-4
IE -4
2E-5
2E-5
Cost/fatal
cancer
avoided
(in millions)
1440
2950
1250
2900
1550
50
dryers:
For grinders:
B-l = venturi scrubber (15" W.G.)
B-2 = ESP
A-l = venturi scrubber (25" W.G.)
A-2 = high energy ESP
A-l = venturi scrubber (16" W.G.)
A-2 = fabric filter
(^Incremental cost for installing and operating alternative control
system (i.e., cost above the existing costs).
of control for New Source Performance Standards.
6.1.9 Total Health Impact ofPhosphate Rock Processing Plants
Phosphate rock processing plants (dryers and grinders) release
about 3700 MI of particulate matter per year with the existing level of
control (TRW82). This particulate matter contains about 150 mCi of
uranium-238 and each of its daughter products. These emissions are
estimated to cause about 1E-2 fatal cancers per year of operation.
This estimate was derived from a ratio of the amount particulate matter
released from all plants to the amount released from the reference
facility:
Number of fatal cancers
per year from all plants
3700 MT PM/yr
380 MT PM/yr
X 0.0013 HE/yr (reference
facility)
0.013
6.1-13
-------
6.1.10
The industry incremental annualized costs to retrofit existing
phosphate dryer and grinding units are shown in Table 6.1-8.
To retrofit existing dryers with medium energy venturi scrubbers
would cost an additional $6 million per year and would avoid 0.003
fatal cancers/year, or a cost of $1830 million per fatal cancer
avoided. Retrofitting to the NSPS level (Control Option A) would cost
an additional $12 million per year and avoid 0.008 fatal cancers per
years or a cost of $1530 million per fatal cancer avoided.
Retrofitting the existing grinders to the NSPS levels (Control
Option A) would cost an additional $340,000 per year and avoid 0.0008
fatal cancers per year, or a cost of $430 million per fatal cancer
avoided.
Table 6.1-8. Industry annualized costs and risk reductions for
retrofitting existing phosphate rock dryers and grinders^3'
Control,, ,. Total cost
Process unit . (b) , .,,. %
option (millions)
(c)
Grinders
Fatal cancers
avoided/j
0.34
8E-4
Cost/fatal
cancer avoided
(in millions)
Dryers
B
A
5.5
12.2
3E-3
8E-3
1830
1530
430
(b)jror dryers Option B is a venturi scrubber (15" W.G. )
and Option A is a venturi scrubber (25" W.G.I. For grinders, Option
A is a fabric filter.
^'Incremental cost for installing and operating alternative control
system (i.e., costs above existing costs).
-------
Page Intentionally Blank
-------
REFERENCES
DM68 Dames and Moore, Airborne Radioactive Emission Control
Technology, Report on EPA Contract 68-01-4992, White Plains,
New York, Unpublished.
EPA78 Environmental Protection Agency, Radiation Dose Estimates due
to Air Particulate Emissions from Selected Phosphate Industry
Operations, ORP/EERF-78-1, Office of Radiation Programs,
Montgomery, Alabama, 1978.
EPA79 Environmental Protection Agency, Phosphate Rock Plants,
Background Information for Proposed Standards,
EPA-450/3-79-017, Office of Air Quality Planning and
Standards, Research Triangle Park, North Carolina, 1979.
TRW82 TRW, Particulate Emissions and Control Costs of Radionuclide
Sources in Phosphate Rock Processing Plants. A report
prepared by Stacy G, Smith (TRW Energy and Environmental
Division, Research Triangle Park, N.C.) for Office of
Radiation Programs, December 1982.
6.1-15
-------
6.2 We_t_Proce«4 * NH3 - NH4H2P04 MAP (3)
2NH3 = (NH4)2HP04 DAP (4)
The steps involved in the wet process production of agricultural
fertilizers are summarized in Table 6.2-1. The major sources of
radionuclide emission in particulate dust results in the product drying
and handling areas.
6.2-1
-------
Figure 6.2-1. Flow diagram of Che wet process (EPA79)
6.2-2
-------
6.2.3 .Coroj.^chnolo^ ..... (,TRW82)
Production processes for dxamrnGnium phosphate (DAP) and granular
triple superphosphate (GTSP) are similar. The same process equipment
in certain plants is used to produce both DAP and GTSP on an
alternating basis; therefore, the control equipment for DAP and GTSP
processes is similar. The particulate matter emission points within
the DAP and GTSP production processes are as follows:
- reactor/granulator exhaust(s);
- dryer exhaust;
- cooler exhaust where appropriate; and
screens, mills, and materials handling ventilation system(s)
and exhaust(s) .
Additional particulate matter (PM) emission sources exist in the ground
rock raw materials handling (GTSP only) and final product handling
systems (DAP and GTSP). These sources, however, are mostly "fugitive"
sources and not process sources.
The DAP and GTSP processes currently in operation employ a variety
of wet scrubbing systems on each of the major process exhaust streams.
In most instances, scrubbers are installed in series. Generally,
individual scrubbing systems are designated as "primary," "secondary,"
etc., referring to their order in the series of control devices.
Scrubbing systems have not been installed to control particulate
matter; rather, process economic considerations and flouride emissions
control have prompted installation of the scrubbing systems. In the
DAP process, the primary scrubber uses phosphoric acid as a scrubbing
solution to recover ammonia raw materials that otherwise would be
lost. Without ammonia recovery, the cost of manufacturing DAP is not
competitive. Secondary scrubbing systems have been installed by and
large to control flouride emissions, to ensure worker safety, and to
meet environmental regulations. Secondary scrubbing systems generally
use recirculated process water (pond water) to enhance flouride
removal. Some plants operate tertiary scrubbers for the same reasons.
The primary, secondary, and sometimes tertiary scrubbing systems,
however, also control particulate matter emissions.
The control technologies that can be applied to these PM emission
sources include:
- cyclone systems;
- wet scrubbing systems;
- bag filters; and
- electrostatic precipitators .
In practice, however, electrostatic precipitators have not been
the technology of choice. Moreover, the use of bag filters has been
limited to the cooler exhausts from certain processes and product
6.2-3
-------
screening, milling and handling ventilation system exhausts. This Is
primarily because the major PM emission points (the reactor granulator
exhausts, dryer exhausts, and cooler exhausts on certain processes) are
also emission points for other pollutants. In particular, gaseous
flouride emissions (GTSP and DA?) and gaseous ammonia emissions (DAP
only) are largely unaffected by electrostatic precipitators or
baghcmses. In addition, the moisture in the reactor and dryer exhaust
streams and the sticky nature of the particulate matter in these
streams complicates the use of bag filter devices. Consequently, PM
control technologies applicable to DAP arid GTSP production processes
are realistically limited to dry cyclone systems, wet scrubbing
systems, and bag filters (for dry materials handling sources only).
Dry cyclone systems are routinely employed on dryer, cooler,
screens, and milling operation exhausts to recover entrained product
that otherwise may be lost. As such, the cyclone systems are as much a
part of the process as they are control equipment.
Controls in place were estimated in a survey of 14 plants (25 DAP
and 14 GTSP processes) based on state air permit files and
conversations with plant personnel. Although 100 percent of the DAP
and GTSP production in the United States is not represented in the
survey, based on published production capacity data, greater than 90
percent of domestic production is represented. It was found that
primary scrubbing systems are employed on 100 percent of the existing
processes. Venturi scrubbers make up about 60 to 95 percent of the
primary scrubbers. In addition, secondary scrubbing systems are
employed on about 60 to 80 percent of the existing processes. About
half of the secondary scrubbers in the industry are packed bed
scrubbers. Tertiary scrubbers also are employed on about 8 to 15
percent of the DAP process units (i.e. reactors, dryers, etc.) and 28
percent of the GTSP process units.
6.2.4 Radj.onujy.ji.de J^isj3_ion_ Measuremeiits
EPA has measured radionuclide emission in particulate stack
releases at two wet process phosphate fertilizer plants (EPA78). The
samples were collected on product dryer stacks in accordance with EPA
guidelines established in the Code of Federal Regulations, Title 40,
Part 60. The annual emission rates based on these measurements are
listed in Table 6.2-1.
6.2.5 Reference Facility
Table 6.2-2 describes the parameters of a refereo.ce wet process
phosphate fertilizer plant which are used to estimate the radionuclide
emissions to the atmosphere and the resulting health impacts. The
reference plant produces both diammonium phosphate (DAP) and granular
triple superphosphate (GTSP) from phosphoric acid derived from
phosphate rock. The radionuclide emissions to air from the DAP and
GTSP process stacks of the reference facility are listed in Table
6.2-3. The emissions are representative of plants using only primary
scrubbers to control DAP and GTSP process off gases*
-------
Table 6.2-1, Radionuclide stack emissions at wet process
phosphate fertilizer plants (EPA78)
Parameter
TSP dryer
Plant A
TSP dryer
Plant B
DAP dryer
Plant B
Total participates (g/y) 2.0E+7 1.2E+7 1.5E+7
Operating time (hr/y) 4.6E+3 7.4E+3 7.5E+3
Stack emissions (Ci/y)
Uranium-234
Uratiium-235
Uranium-238
Thorium-227
Thoriurn-228
Thorium-230
Thorium-232
Radium-226
Polonium-210
1.1E-4
ND
9.0E-5
ND
4.0E-5
9.0E-5
ND
3.0E-5
6.3E-4
3.QE-4
2.0E-5
2.7E-4
ND
3.0E-5
2.5E-4
7.0E-5
2.2E-4
NA
2.6E-3
1.9E-4
3.3E-3
ND
8.0E-5
3.0E-3
5.0E-5
2.6E-4
NA
ND Not detectable.
NA Not available.
6.2.6 Health Impact Assessment of Reference Plant
The estimated annual radiation doses from radionuclide emissions
from the reference wet process phosphate fertilizer plant are listed in
Table 6.2-4. These estimates are for a model site in central Florida
with a regional population of 1.4E+6. The nearby individuals are
located 1500 meters south of the reference plant.
Table 6.2-5 presents estimates of the lifetime risk to nearby
individuals and the number of fatal cancers per year of operation from
these doses.
The lifetime risk to nearby individuals is estimated to be about
2E-6 and the number of fatal cancers per year of operation is estimated
to be 6E-4. These risks result primarily from doses to the lung from
inhalation of radioactive particulates released from fertilizer
production.
6.2.7 Existing Emission Standards and Air Pollution Controls
No Federal or State regulations currently exist that limit
radionuclide emissions from wet process phosphate fertilizer plants.
Particulate emissions from these facilities are limited to the
quantities established by the States in their State Implementation
Plans (SIPs) for meeting Ambient Air Quality Standards.
6.2-5
-------
Florida,, where almost 80 percent of the industry is located;, has
the most stringent SIP limits. Phosphate processing operations are
limited to 0.3 Ib/ton of product (150 g/MT of product). The other
States with wet process phosphate fertilizer plants have riot
established specific emission limits for phosphate processing, but
restrict emissions to the levels established in their SIPs for general
processing sources. For sources greater than 30 tons/hour, allowable
emissions are determined by the formula:
where
E = (55.0 x P0.11)-4o,
E = emissions, and
P = the processing rate in tons/hour.
6.2.8 Alternative Control Technology
All wet process phosphate fertilizer plants use primary scrubbers
on the DAP and GTSP exhausts. The annualized costs and risk reduction
of adding alternative controls to the reference wet process phosphate
fertilizer plant are shown in Table 6.2-6.
Table 6.2-2. Reference wet process phosphate fertilizer plant
Parameter
Process
DAP
GTSP
Production rate (MT/y) 5.2E+5 2.7E+5
Operating factor (hr/y) 8160 8160
Radionuclide content of product (pCi/g)(a)
Uranium-238s uranium-234, thorium-230 60 60
Radium-226 5 20
Lead-210, polonium-210 30 30
Stack parameters
Height (meters) 40 40
Diameter (meters) 2 2
Exit gas velocity (m/s) 10 10
Exit gas temperature (°C) 60 60
Type of control system Venturi Venturi
scrubber scrubber
Particulate emission rate (g/MT) 164 100
(a'Data from EPA78. DAP Diammonium phosphate.
GTSP Granular triple superphosphate.
6.2-6
-------
Table 6.2-3. Radionuclide emissions from the
reference wet process phosphate fertilizer plant
,., Hnissions (Ci/y)
Radionuclxde J—~
DAP GTSP Total
Uranium-238
Uranium-234
Thorium-230
Radium-226
Lead-210
Poloniuin-210
5. IE -3
5. IE -3
5.1E-3
4.3E-4
2.6E-3
2.6E-3
1.6E-3
1.6E-3
1.6E-3
5.4E-4
8.1E-4
8. IE -4
6.7E-3
6.7E-3
6.7E-3
9.7E-4
3.4E-3
3.4E-3
DAP Diananonium phosphate.
GTSP Granular triple superphosphate.
Table 6.2-4. Radiation dose rates from radionuclide emissions
from the reference wet process phosphate fertilizer plant
Nearby individuals Regional population
(mrem/y) (Person-rem/y)
Lung
Endosteum
Red marrow
Kidney
1.2
2.2
1.5E-1
6.7E-2
2.4E+1
4.1E+1
2.8
1.3
Table 6.2-5. Fatal cancer risks due to radioactive emissions
from reference wet process phosphate fertilizer plant
Lifetime risk Regional population
Source to nearby individuals fatal cancers/y of operation
DAP and GTSP
process emissions 2E-6 6E-4
DAP Diamttionium phosphate.
GTSP Granular triple superphosphate.
6.2-7
-------
6.2.9
Wet process phosphate fertilizer plants release about 1500 MT per
year of particulates from the DAP and GTSP process stacks with the
existing control systems. This amount of particulate matter contains
about 90 mCi each of uranium-238, uranium-234, and thorium-230 and
lesser quantities of radium-226, polonium- 210, and lead-210. This
estimate is based on the conservative assumption that the specific
activity (pCi/g) of the particulate material released is the same as
DAP and GTSP fertilizers. These emissions are estimated to cause about
0.01 fatal cancers per year. This estimate is based on a ratio of the
amount of particulate material released from all plants to the amount
released from the reference plant in a manner similar to that shown in
Section 6.1.8.
6.2.10 Co s t s and Risk Re due t ion s f or Retrofitti ng Ex i s t i ng Plants
The annualized costs to the industry to retrofit existing
phosphate fertilizer plants with secondary scrubbers are shown in Table
6.1-7. To retrofit existing DAP process exhausts with packed bed
scrubbers (28 percent of the existing production capacity) would cost
an additional $3 million per year and would avoid 0.001 fatal cancers
per year, or a cost of $3 billion per fatal cancer avoided.
Retrofitting GSTP process exhausts with packed bed scrubbers (19
percent of existing production capacity) would cost an additional
1500,000 per year and would avoid 0.0004 fatal cancers per year, or a
cost of $13 billion per fatal cancer avoided.
fable 6.2-6. Annualized costs and risk reductions of alternative controls
for the reference wet process phosphate fertilizer
Process _ . ,
Control
DAP
GTSP
optionvb)
Existing
Alternative
Existing
Alternative
Total
Fatal cancer risks
Emission annual Individual
rate(c) cost lifetime
(g/MT) ($1,000)
164
100 500
100
79 300
risk
2E-6
1E-6
5E~7
4E-7
Population
(cancers/y of
operation)
5E-4
3E-4
IE -4
8E-5
Cost/fatal
cancer
avoided
(in millions)
2.5E+3
1.5E+4
DAP Diammonium phosphate GTSP Granular triple superphosphate.
Source: TRW82.
isting controls are venturi scrubbers. Alternative controls are
packed bed scrubbers in series with venturi scrubbers.
rt iculate material emission rate.
incremental cost for installing and operating alternative control
systems, i.e., additional costs for installing and operating
packed bed scrubbers.
6.2-6
-------
Table 6.2-7. Industry annualized costs and risk reductions for
adding secondary scrubbers to existing wet process phosphate
fertilizer plants^a)
„ , _, 1 Cost/fatal
Total cost/, % Fatal cancers . , „
Process ,...,, ^(.o) •_,,/ cancer avoided
(.millions) avoided/y /, .,,. ^
(in millions;
DAP
GTSP
3
0.5
1E-3
4E-5
1.3E+4
^^Incremental cost of installing and operating packed bed scrubbers
in series with existing venturi scrubbers. IWenty-eight percent of
DAP production capacity and 19 percent of GTSP production capacity
require retrofit.
DAP Diammonium phosphate.
GfSP Granular triple superphosphate.
6.2-9
-------
REFERENCES
EPA78 Environmental Protection Agency, Radiation Dose Estimates due
to Air Particulate Emissions from Selected Phosphate Industry
Operations, ORP/EERF-78-1, Office of Radiation Programs,
Montgomery, Alabama, 1978.
EPA79 Environmental Protection Agency, Radiological Impact Caused by
Emissions of Radionuclides into Air in the United States,
EPA-520/7-79-006, Office of Radiation Programs, Washington,
D.C., 1979.
TRW82 TRW, Industry and Particulate Matter Control Technology
Information for Dianunonium Phosphate and Granular triple
Superphosphate manufacture. A report prepared by TRW
Environmental Division for the Environmental Protection
Agency, Dec 15, 1982.
6.2-10
-------
6 . 3 El -it Psptwrs Plants
6.3.1 General Description
About ten percent of the marketable phosphate rock mined in the
United States is used for the production of elemental phosphorus.
Elemental phosphorus is used primarily for the production of high grade
phosphoric acid, phosphate-based detergents, and organic chemicals. In
1983 approximately 366 thousand tons of elemental phosphorus were
produced .
Phosphate rock contains appreciable quantities of uranium and its
decay products. The uranium concentration of phosphate rock ranges
from about 20 to 200 ppm, which is 10 to 100 times higher than the
uranium concentration in typical rocks and soil (2 ppm). The
radionuclides of significance which are present in phosphate rock are:
uranium-238, uraniunr-234, thorium-230, radium-226, radon-222, lead-210,
and polonium-210. Because phosphate rock contains elevated
concentrations of these radionuclides , handling and processing this
material can release radionuclides into the air in the form of dust
particles. More importantly for elemental phosphorus plants, heating
the phosphate rock to high temperatures in calciners and electric
furnaces can volatilize lead-210 and polonium-210, resulting in the
release of significant quantities of these radionuclides into the air.
There are 6 elemental phosphorus plants in the United States —
located in Idaho, Montana, and Tennessee. Table 6.3-1 shows the
owners, locations, and the estimated elemental phosphorus production
rates for these plants.
6.3.2 Process De s cr i p t ion
Phosphate rock which has been crushed and screened is fed into
calciners where it is heated to the melting point, usually 1300° C.
The calcining serves two purposes: (1) it burns any organic matter
present in the rock, and (2) it transforms the finely divided rock into
large stable agglomerates or nodules which are needed for proper
operation of the reduction furnaces. The hot nodules are passed
through coolers and then to storage bins prior to being fed to electric
furnaces. The furnace feed consists of the nodules, silica and coke.
The proper amount of silica is needed to form slag with the flow
properties necessary to facilitate removal from the furnace. Coke is
added as a carbon source to reduce the calcium phosphate to elemental
phosphorus. A simplified chemical equation for the electric furnace
reactor is as follows:
2Ca3(p04)2 + 6Si02 + IOC = ?4 + 10CO + 6CaSi03 (1)
6.3-1
-------
In addition, the iron naturally present in the rock reacts with
some of the phosphorus to produce FeP. The blended furnace feed enters
the furnaces continually from the top and progresses downward until
reaching the molten layer on the bottom. Phosphorus and carbon
monoxide (CO) are driven off as gases and are vented near the top of
the furnace. The slag and FeP which are continually collecting in the
furnace are periodically "tapped off."
Furnace off-gases pass through dust collectors and then through
water spray condensers. Pnosphorus is cooled to the molten state in
the condensors. The mix of phosphorus and water—phossy water—and mud
go to a processing system where phosphorus is separated and piped to
storage. The clean off-gases leaving the condensors contain a high
concentration of CO and are used as fuel in the calciners. A flow
diagram of the process is shown in Figure 6.3-1.
Table 6.3-1. Location and size of elemental phosphorus plants
Location
Company
(tons/y of phosphorus)
Idaho
Pocatello
Soda Springs
Montana
Silver Bow
FMC Corporation
Monsanto Chemical Co.
Stauffer Chemical Co.
1.3E+5
9.QE+4
4.QE+4
Tennessee
Columbia
Columbia
Mt, Pleasant
Occidental Chemical Co. 5.7E+4
Monsanto Chemical Co. 7.5E+4
Stauffer Chemical Co. 5.GE+4
^Estimated capacity in 1984 (EPA84d).
6*3.3 ControlTechnology
Emissions from calciners are typically controlled by low energy
scrubbers. Emissions from nodule coolers and transfer points and
furnace tap holes are controlled by either fabric filters or wet
scrubbers. Screening plant emissions are usually controlled by fabric
filters. Fugitive dust emissions and radon gas emissions are not
controlled.
6,3-2
-------
INPUT
PROCESS
PRODUCTS &
BY-PRODUCTS
/PHOSPHATE\_
ROCK V~
CALCINER
STACK VENT EXHAUST
CALCINED
NODULES
ELECTRIC
FURNACE
PRECIPITATOR
\
CABBON \
MONOXIDE V
Recycled
CONDENSERS
ELEMENTAL
PHOSPHORUS SALES
CARBON MONOXIDE
FLARE STACK
Figure 6.3-1. Flow diagram of the thermal process for
production of elemental phosphorus.
6.3-3
-------
6.3,4 Radionuclide Emission Measurements
In the period 1975-1980, EPA measured the radionuclide emission
rates from three elemental phosphorus plants. These plants were:
FMC in Poeatello, Idaho (EPA77), Stauffer in Silver Bow, Montana
(AnSla), and Monsanto in Columbia, Tennessee (AnSlb). These tests
included measurements from release points representative of all of the
major process operations in the production of elemental phosphorus.
Measurements were made of the emission rates from: calciners, calciner
coolers, material handling and transfer operations, screening plants,
furnace preparation areas, and furnace tap holes. The stack emission
rates measured during these studies are summarized in Table 6.3-2.
All of the radionuclides are released as particulates except for
radon-222, which is released as a gas. Essentially all of the radon-222
and greater than 95 percent of the lead-210 and polonium-210 emitted
from these facilities are released from the calciner stacks. The high
temperature of the calciners volatilizes the lead-210 and polonium—210
from the phosphate rock, resulting in the release of much greater
quantities of these radionuclides than the uranium, thorium and radium
radionuclides. Analyses of doses and risks from these emissions show
the emissions of polonium-210 and, to a lesser degree, emissions of
lead-210 to be the major contributors to risk from radionuclide
emissions from elemental phosphorus plants (see Section 6.3.5).
In late 1983, EPA conducted extensive additional radionuclide
emission testing at the FMC plant in Pocatello, Idaho (EPA84a, RC84a),
and the Stauffer plant in Silver Bow, Montana (EPA84b, RC84b). Also in
early 1984, EPA conducted some limited emission testing at the Monsanto
plant in Soda Springs, Idaho (EPA84c, RC84c). This testing was limited
to calciner off-gas streams (based on results of previous emission
testing) and focused primarily on lead-210 and polonium~210 emissions,
The principal objectives of these tests were: (1) to obtain additional
information on the lead-210 and polonium-210 emissions in calciner
off-gas streams, (2) to determine the distribution of lead-210 and
polooium-210 by particle size in calciner off-gas streams, and (3) to
obtain a suitable sample for determining the lung-clearance classifi~
cation of lead-210 and polonium-210 in particulates collected from the
calciner off-gas streams.
Reports on this testing have been prepared for each plant as cited
in the above noted references. These reports contain the following
data and information: (l) radionuclide concentrations in the calciner
feed material and the calcined product (nodules), (2) radionuclide and
particulate concentrations and emission rates in calciner off-gas
streams including both inlet and outlet streams of emission control
devices, (3) particle size distribution of both radionuclides and
particulates in calciner off-gas streams including the distribution
for both inlet and outlet streams of emission control devices,
(4) estimates of the annual emission rates for both radionuclides and
>.3-4
-------
Table 6.3-2.
Radionuclide stack emissions measured at elemental
phosphorus plants (1975-1980) ^a)
Parameter
FMC
Idaho
Stauffer
Montana
Monsanto
Tennessee
Rock processing rate (MT/y)">) 1.6E+6 5.3E+5 1.7E+6
Uranium-238 concentration
of rock (PCi/g)(c) 22.0 27.0 <
Calciner stacks emission rate (Ci/y):^e)
Uranium-238 1.2E-3 2.4E-4 2.2E-3
Uranium-234 1.3E-3 2.0E-4 3.2E-3
Thorium-230 2.2E-3 1.2E-4 1.4E-3
Radium-226 1.3E-3 3.5E-4 2.1E-3
Radon-222 - 8.0 9.6
Lead-210 3.0E-3 2.8E-1 4.8E-1
Polonium-210 6.9 2.0E-1 7.5E-1
Other stacks emission rate (Ci/y):
Uranium-238 4.0E-2 6.2E-4 l.OE-2
Uranium-234 4.6E-2 7.0E-4 l.OE-2
Thorium-230 5.3E-3 1.2E-3 1.2E-2
Radium-226 5.9E-3 1.1E-3 9.0E-3
Radon-222 - ND ND
Lead-210 1.5E-2 2.5E-3 ND
Polonium-210 4.0E-1 5.9E-3 2.7E-3
Fraction of input radionuclides
Uranium-238
Uranium-234
Thorium-230
Radium-226
Radon-222
Lead-210
Polonium-210
emitted:
1.2E-3
1.4E-3
2.1E-4
2.0E-4
_
5.1E-4
2.1E-1
6.0E-5
6.2E-5
9.0E-5
9.8E-5
5.7E-1
2.0E-2
1.4E-2
1.4E-3
1.5E-3
1.5E-3
1.7E-3
1.1
5.6E-2
8.8E-2
'a'Emissions are in particulate form except for radon-222 which is
released in gaseous form.
'•"'These processing rates were those estimated for these plants at
time of emission testing.
^c'Uraniuin-238 and its daughter products are assumed to be present in
equilibrium in the rock.
'"'Calciner feed material was a blend of Tennessee and Florida
phosphate rock.
^e'Based on 8760 hours of plant operation.
6.3-5
-------
particuiates, (5) estimates of the efficiency of existing control
systems in removing radionuclides and particuiates, (6) descriptions of
the sampling methods and procedures used during the testing, and
(7) test parameters, such as sample volumes and flow rates used in
testing.
A brief description of the major results obtained during this
testing is presented in the following sections.
The limited sampling at the Monsanto, Soda Springs} Idaho, plant
was due to the unavailability of suitable sampling locations for more
detailed testing. The Monsanto plant releases its calciner off-gas
stream through a large diameter demister. Significant modifications to
the demister and installation of a stack extension are necessary before
emission testing equivalent to that conducted at FMC and Stauffer can
be made at the Monsanto plant, (For more details on sampling problems
at the Monsanto plant see RC84c.)
Resultsof1983-1984 Emission Testing
Process Samp> 1_es_
Table 6.3-3 presents the measured radiomiclide concentrations in
the calciner feed material and product samples for the three plants
studied. For the Stauffer and Monsanto plants, both the lead-210 and
polonium-210 concentrations in the calciner product samples were
significantly lower than the concentrations in the feed material,
reflecting the volatilization of these radionuclides during the
calcining operation. For the PMC plant, only the polonium-210 concen-
tration was significantly lower in the product samples than in the feed
material. This indicates that large quantities of lead™210 are not
volatilized during the calcining operation at the FMC plant,
RadionuclideEmission Rates
Table 6.3-4 presents the measured radionuclide emission rates for
the three plants studied in pCi/hr/calciner and the estimated annual
calciner emission rates. The estimated annual polonium-210 emission
rates are: Monsanto, Soda Springs, Idaho = 21 Ci/yr; FMC, Pocatello,
Idaho = 8,6 Ci/yr; and Stauffer, Silver Bow, Montana = 0.74 Ci/yr. The
estimated annual lead~210 emission rates are: Monsanto, Soda Springs,
Idaho = 5.6 Ci/yr; FMC, Pocatello, Idaho = 0.12 Ci/yr; and Stauffer,
Silver Bow, Montana =0.11 Ci/yr.
ParticleSize Distribution
Table 6.3-5 presents the measured distribution of lead-210 and
polonium-210 by particle size in the calciner off-gas streams at the
FMC and Stauffer plants. These samples were collected using Andersen
cascade irapactors. Similar samples could not be collected at the
6.3-6
-------
Monsanto plant because suitable sampling ports and locations were not
available (RC84c). These data show that for both the FMC and Stauffer
plants, most of the poloni.um-210 was associated with submicron parti-
cles. For the FMC plant, an average of 73 percent of the poloniunt-210
was in a particle size range less than 0.5 microns and 86 percent was
in a range less than 1.5 microns. For the Stauffer plant, an average
of 53 percent of the polonium~21G was in a particle size range less
than 0.5 microns, and about 90 percent was in a range less than 1.5
microns,
Table 6.3-3. Measured radionuclide concentrations
in process samples at elemental phosphorus plants
(1983-1984 emission test results)
R a d i on uc1i d e cone en trations (jgCjl/g_j_
. Fe e d s t oc k Calcined product
Uranium- Lead- Polonium- Uranium- Lead- Polonium-
238 210 210 238 210 210
FMC
Pocatello, 21 26 21 22 27 8
Idaho
Stauffer
Silver Bow, 42 46 40 42
Montana
Monsanto
Soda Springs, 32 150 91 37
Idaho (a)
'a'Blended feed material. This plant recycles both dropout chamber
dust and underflow solids from wet scrubber clarifier.
6.3-7
-------
Table 6.3-4. Radionuclide emissions from caLciners at elemental
phosphorus plant (1983-1984 emission test results)
Plant
Average measured
radionuclide emissions
(uCi/h/calciner)(a)
Uranium- Lead- Polonium-
238 210 210
Estimated total
Number calciner emissions
of (Ci/y)(b)(c)
calciners Uranium- Lead- Polonium-
238 210 210
FMC
Pocatello, 0.28 7.5 540 2
Idaho
Stauffer
Silver Bow, 0.04 7.6 50 2
Montana
Monsanto
Soda Springs, 0.78 760 2900 1
Idaho
0.004 0.12 8.6
0.0006 0.11 0.74
0.006 5.6 21
the FMC plant, emission rates were measured from both calciner units,
and the reported values are the average emission rates for these units. For
the Stauffer plant, emissions for only one of the calciner units (kiln-2)
were measured, and the reported values are the average value for this unit.
In estimating total annual emissions, it was assumed that both calciner
units have the same emission rates.
'"'Based on 7400 hours of calciner operation (i.e.
factor).
85 percent operating
'•'-'The conversion of measured emission rates to annual emission estimates
for the FMC plant includes an adjustment for processing rate where appli-
cable (see EPA84a),
= 3-
-------
Table 6.3-5, Measured distribution of lead-210 and polonium-210
by particle size in calciner stack outlet streams at elemental
phosphorus plants (1983 emission test results)^a'
Plant
Approximate
particle size range
(D-50)(microns)
Percent of total
Lead-210
Polonium-210
FMC
Pocatello,
Idaho
Stauffer
Silver Bow,
Montana
>10
3-10
1,5-3
0.9-1.5
0.5-0.9
<0.5
>10
3-10
1.5-3
0.9-1.5
0.5-0.9
<0.5
10
13
9
10
14
44
<1
3
5
14
22
53
7
5
4
6
5
73
2
4
4
17
25
50
^•'Particle size measurement using cascade impactors could not be made
at Monsanto, Soda Springs, Idaho,' because suitable sampling ports and
locations were not available.
Lung-Clearanee Classification Studies
Samples of particulates collected frotn the calciner off-gas
streams at FMC and Stauffer were sent to the Pacific Northwest
Laboratory for testing to determine the lung-clearance classifications
(for use in ICRP lung model)(ICRP66) of lead-210 and polonium-210 in
these particulates. These lung-clearance classifications were
determined by measuring dissolution rates of these radionuclides in
simulated lung fluid. For each plant, testing was conducted on samples
containing particulates in the range of 0 to 3 microns and 3 to 10
microns. A detailed description of the test methods used and results
obtained are presented in PNL-5221 (Ka84). Table 6,3-6 summarizes the
dissolution data for lead~210 and polonium-210 in simulated lung fluid
for these particulate samples.
The results of these tests show that both the lead-210 and the
polonium-210 dissolved only very slowly in the simulated lung fluid.
More than 99 percent of these radionuclides remained undissolved even
after 60 days of testing. Based on these tests, it was concluded that
both lead-210 and polonium-210 in these materials should be considered
Class Y for calculations with the ICRP lung model (i.e., the model used
in EPA in dose calculations).
6.3-9
-------
Table 6.3~6. Dissolution of lead-210 and polonium-210
from parCiculate samples collected from off-gas streams
at FMC and Stauffer elemental phosphorus plants
Sample
„, . particle size
Plant / . %
(micron)
FMC 0-3
Pocatello,
Idaho
3-10
Stauffer 0-3
Silver Bow,
Montana
3-10
Dissolution
t ime ( days )
1.0
3.0
10.0
20.2
37.0
59.0
1.0
3.0
10.0
20.2
37.0
59.0
1.0
2.9
8.9
20.8
40.8
59.0
1.0
2.9
8.9
20.8
40.8
59.0
Fraction of
210pb remaining
undissolved
0.9984
0.9973
0.9968
0,9962
0.9956
0.9950
0.9933
0.9744
0.9682
0.9618
0.9554
0.9490
0.9999
0.9999
0.9994
0.9991
0.9983
0.9978
1.0000
0.9999
0.9990
0.9991
0.9985
0.9979
Fraction of
210po remaining
undissolved
0.9997
0.9990
0.9984
0.9980
0.9979
0.9978
0.9991
0.9988
0.9979
0.9970
0.9943
0.9914
0.9997
0.9996
0.9989
0.9986
0.9981
0.9980
0.9997
0.9993
0.9992
0.9948
0.9942
0.9940
6.3-10
-------
6,3.5 HealthImpact A^£Ji5jE!B!i!l^^ Plants
Tables 6.3-7 and 6.3-8 show the estimated annual calciner emission
rates and stack parameters for each of the six operational elemental
phosphorus plants. These values were used in. estimating the radiation
doses and fatal, cancer risks from these plants.
Table 6.3-9 presents the radiation doses to the lung from radio-
nuclide emissions from calciners at elemental phosphorus plants. Almost
all of the radiation risk from radionuclide emissions from calciners at
these plants results from these lung doses. The lung-clearance
classifications and particle size distributions (AMAD) used in
estimating these doses (ICRP Task Group Lung Model) are shown below:
Clearance Particle Size
RadJ.£micHde_ Class i f ic at ion AMAD
Lead~210, Polonium~210 Y(a) 0.3
Uranium-238, Uranium-234, Y l
Thorium-230
Radium-226 W^b) l^b)
'a'Based on experimental data obtained during emission testing.
^ 'Based on values recommended by ICRP (ICRP66) when experimental
values not available.
Table 6,3-10 presents estimates of the lifetime risk to the nearby
individuals and the number of fatal cancers to the regional population
from radionuclide emissions from calciners at elemental phosphorus
plants. The doses and rislcs to the nearby individuals were calculated
for a location 1500 meters from the plant in the predominant wind
direction. The doses and risks to the regional population were
calculated using the population distribution of the actual plant site.
Table 6.3-11 shows the number of people living within 80 km of these
sites and the source of the meteorological data used in these
calculations.
The fatal cancer risks from radionuclide emissions from calciners
at elemental phosphorus plants result primarily front inhalation of
polonium-210. To illustrate this point, Tables 6,3-12 through 6.3-15
show the doses to the various organs and the relative significance of
various pathways, organs, and radionuclides to the fatal cancer risks
from radionuclide emissions from calciners at both the FMC and
Monsanto, Idaho, plants.
6.3-11
-------
Table 6.3-7. Estimated annual radionuclide emissions
from elemental phosphorus plants^a^
Emissions (Ci/y)
Plant
Uranium-238^b-) Lead-210
Poloniura~210
FMC(c>
Pocatello, Idaho
Monsanto^c '
Soda Springs, Idaho
Monsanto'-0-'
Columbia, Tennessee
Stauffer^
Silver Bow, Montana
Stauffer^)
Mt. Pleasant, Tennessee
Occidental^
Columbia, Tennessee
4E-3
6E-3
2E-3
6E-4
2E-4
2E-4
0.1
5.6
0.4
0.1
0.05
0.05
9
21
'0.
0.
0.
0.
6
7
1
1
(b)
'Emission rates based on 7400 hrs per year of calciner operation
(i.e., 85 percent operating factor).
(c)
(d)
In using these data in estimating radiation doses and risks for
these plants, equal quantities of uranium-234, thorium-230, and
radium-226 were assumed to be emitted along with the uranium-238.
This assumption is supported by data in Table 6.3-2 which shows that
uranium~238 is in equilibrium (within about a factor of 2) with
uranium-234, thorium-230, and radium-226 in the calciner off-gas
streams. In any case, however, as noted previously, these radio-
miclides do not contribute significantly to the doses and risks from
radionuclide emissions from calciners at elemental phosphorus plants.
Based on measurements during EPA testing.
Estimates based on the following percent releases of radionuclides
entering the calciners: polonium-210 = 10 percent, lead-210 = 5 per-
cent uranium-238 = 0.02 percent (i.e., similar to percent releases
for the reference plant in EPA83).
6.3-12
-------
Table 6*3-8. Calciner stack emission characteristics
Plant
FMC
Pocatello, Idaho
Monsanto
Soda Springs , Idaho
Monsanto
Columbia, Tennessee
Stauffer
Silver Bow, Montana
Stauffer
Ml. Pleasant, Tennessee
Occidental
Columbia, Tennessee
Stack height Heat emission
(meters) (calories/sec)
30 8.8E+5
31 2.0E+6
35 l.OE+6
27 3.0E+4
35 6.0E+5
31 L.2E+6
Table 6.3-9. Radiation dose to lung from radion.ucLi.de
emissions from elemental phosphorus plants
Plant
FMC
Pocatello, Idaho
Monsanto
Soda Springs, Idaho
Monsanto
Columbia, Tennessee
Stauffer
Silver Bow, Montana
Stauffer
Mt. Pleasant, Tennessee
Occidental
Columbia, Tennessee
Nearby individuals Regional population
Lung (mrem/y) Lung (person-rem/y }
290 1170
610 750
30 310
60 122
6 33
5 65
6.3-13
-------
Table 6.3-10. Fatal cancer risks from radionuclide
emissions from elemental phosphorus plants
Plant
Lifetime risk to
nearby individuals
Regional population
{Fatal cancers/y
of operation)
FMC 5E-4
Pocatello, Idaho
Monsanto 1E~3
Soda Springs , Idaho
Monsanto 6E-5
Columbia, Tennessee
Stauffer 1E-4
Silver Bow, Montana
Stauffer 1E-5
Mt. Pleasant, Tennessee
Occidental 9E-6
Columbia, Tennessee
0.027
0.018
0.007
0.003
0.001
0.002
Table 6.3-11, Population within 80 km of elemental phosphorus plants
and source of meteorological data used in dose and risk calculations
Plant
Number of people
within 80 km^
Source of
meteorological
FMC
Pocatello, Idaho
Monsanto
Soda Springs, Idaho
Stauffer
Silver Bow, Wyoming
Monsanto
Columbia, Tennessee
Stauffer
Mt. Pleasant, Tennessee
Occidental
Columbia, Tennessee
1.4E+5
8.0E*4
7.7E+4
7.7E+5
6.0E+5
8.0E+5
Pocatello, Idaho
Pocatello, Idaho
Butte, Montana
Nashville, Tennessee
Nashville, Tennessee
Nashville, Tennessee
(fl>Based on 1970 Census.
a from National Climatic Center, Asheville, North Carolina.
6.3-14
-------
Table 6.3-12. Radiation dose rates to various organs
from radionuclide emissions from calciners
at elemental phosphorus plants^3'
IMC Monsanto
Organ Pocatello, Idaho Soda Springs, Idaho
(mrem/y) (mrem/y)
Lung
Kidney
Liver
Endosteutn
Red Marrow
290
10
2
1
0.3
610
18
4
6
0
.9
'Doses to individuals located 1500 meters from the plant in
predominant wind direction.
Table 6.3-13. Fatal cancer risks to nearby individuals
from radionuclide emissions from calciners at
elemental phosphorus plants by cancer type
Lifetime risk to nearby individuals
Cancer FMC Monsanto
Pocatello, Idaho Soda Springs, Idaho
Lung 5E-4 1E~3
Urinary 2E-6 3E~6
Liver 1E-6 2E-6
Lukemia 3E-7 9E~7
Bone 3E-8 1E-7
6.3-15
-------
Table 6.3-14, Fatal cancer risks to nearby individuals
from radionuclide emissions from calciners at
elemental phosphorus plants by radionuclide^8'
Percent of total risk
Radionuclide FMC Monsanto
Pocatello, Idaho Soda Springs, Idaho
Uraniura-234, -238 0.2 0.2
Thorium-230 0.1 0.1
Radium-226 0.01 0.01
Lead-210 1 26
Polonium-210 98 74
^a'These estimates do not include contributions from radon-222
emissions from the calciner. However, previous estimates (EPA83)
showed that radon~222 emissions from calciners at elemental phos-
phorus plants cause only small additional fatal cancer risks, i.e.,
about one percent of the total risk.
Table 6.3-15. Fatal cancer risks to nearby individuals from
radionuclide emissions from calciners at elemental
phosphorus plants by pathway
Pathway
Inhalation
Ingestion^3'
Other
Percent of
FMC
Pocatello, Idaho
99.3
0.7
<0.1
total risk
Monsanto
Soda Springs, Idaho
99.5
0.5
<0.1
intakes used were those for an urban/low productivity site
(see Appendix A).
6.3-16
-------
6.3.6 Alternative Control Technology
An analysis of the cost and polonium~210 removal efficiency for
alternative control systems for reducing polonium-210 emissions from
calciner off-gas streams at the FMC and Monsanto Idaho plants was
carried out for EPA by the Midwest Research Institute (MRl84a, MRl84b).
A summary of these analyses is shown in Table 6.3-16. These plants
were analyzed because they have the highest polonium-210 emissions.
Reducing the polonium-210 emissions will also reduce the lead-210
emissions.
Tables 6.3-17 and 6.3-18 show the risk reduction and cost of con-
trol at various selected polonium-210 emission rates for the FMC and
Monsanto (Idaho) plants, respectively. A more detailed analysis of the
costs and risk reductions, as well as the economic impacts, of
alternative polonium-210 emission rates for these plants is presented
in a regulatory impact analysis of emission standards prepared for EPA
by Jack Faucett Associates (EPA84d).
Table 6.3-16. Cost of alternative control systems for
reducing polonium-210 emissions at FMC and
Monsanto elemental phosphorus plants'3'
Control
system
Scrubber
15-in AP
30-in &P
45-in &P
ESP
200 SCA(b
300 SCA
400 SCA
Fabric
filter
210-Po
removal
(%)
65
77
83
> 72
83
90
98
FMC
Capital
cost
( $ millions)
2.1
2.8
3,7
5.2
5.9
6.7
7.3
Plant
Annualized
cost
( $ millions)
1.6
2.5
3.5
1.4
1.5
1.7
1.9
Monsanto Plant
Capital
cost
(& millions)
1.1
1.5
2.0
2.9
3.2
4.3
4.2
Annualized
cost
( $ millions)
0.9
1.4
2.0
0.8
0.9
1.1
1.3
(a)From Midwest Research Institute Reports (MRl84a and MRl84b) and based
on January 1984 dollars.
^b^SCA-Specific Collection Area in ft2/1000 acfm.
6.3-17
-------
Table 6.3-17. Cost of added controls and risk reduction at selected
poloniura-210 emission rates from calciners at FMC plant
Fatal cancer risks
Polonium-
210
emission
rate (Ci/y)
Current
emissions
2.5
Lifetime risk
to nearby
individuals
5E-4
1E-4
Regional
population
(Fatal
cancers/y
of operation)
0.027
0.008
Risk reduction
Regional
population Control
(Fatal system
cancers/y
of operation)
0.019 Medium
Cost
( $ millions)
capital-
annualized
5.9 1.5
5E-5
0.003
energy
ESP
0.024 High 6.7 1.7
energy
ESP
Table 6.3-18. Cost of added controls and risk reductions at selected
polonium-210 emission rates from calciners at Monsanto (Idaho) Plant
Fatal cancer risks
Polonium-
210
emission
rate (Ci/y)
Current
emissions
10
2,5
1.0
Lifetime risk
to nearby
individuals
1E-3
5E~4
IE-4
5E-5
Regional
population
(Fatal
cancers/y
of operation)
0.018
0.009
0.002
0.001
Risk reduction
Regional
population
(Fatal
cancers/y
of operation)
0.009
0.016
0.017
Control
system
-._-.
15 in AP
scrubber
High
energy
ESP
Fabric
filter
Cost
($ millions)
capital-
annual ized
1.1 0.9
4.3 1.1
4.2 1.3
6.3-18
-------
REFERENCES
AnSla Andrews V. E., Emissions of Naturally Occurring Radioactivity
from Stauffer Elemental Phosphorus Plant, ORP/LV-81-4, EPA,
Office of Radiation Programs, Las Vegas, Nevada, August 1981.
AnSlb Andrews V. E. , Emissions of Naturally Occurring Radioactivity
from Monsanto Elemental Phosphorus Plant, ORP/LV-81-5, EPA,
Office of Radiation Programs, Las Vegas, Nevada, August 1981.
EPA77 Environmental Protection Agency, Radiological Surveys of
Idaho Phosphate Ore Processing~~Ihe Thermal Plant,
ORP/LV-77-3, EPA, Office of Radiation Programs, Las Vegas,
Nevada, 1977.
EPA83 Environmental Protection Agency, Office of Radiation
Programs, Draft Background Information Document, Proposed
Standards for Radionuclides, EPA 520/1-83-001, EPA, Office of
Radiation Programs, Washington, D.C., March 1983.
EPA84a Environmental Protection Agency, Office of Radiation
Programs, Emissions of Lead~210 and Polonium-210 from
Calciners at Elemental Phosphorus Plants: FMC Plant,
Pocatello, Idaho, EPA, Office of Radiation Programs,
Washington, B.C., June 1984.
EPA84b Environmental Protection Agency, Office of Radiation
Programs, Emissions of Lead-210 and Polonium-210 from
Calciners at Elemental Phosphorus Plants: Stauffer Plant,
Silver Bow, Montana, EPA, Office of Radiation Programs,
Washington, B.C., August 1984.
EPA84c Environmental Protection Agency, Office of Radiation
Programs, Emissions of Lead-210 and Polonium-210 from
Calciners at Elemental Phosphorus Plants: Monsanto Plant,
Soda Springs, Idaho, EPA, Office of Radiation Programs,
Washington, B.C., August 1984.
EPA84d Environmental Protection Agency, Regulatory Impact Analysis
of Emission Standards for Elemental Phosphorus Plants, Office
of Radiation Programs, Washington, D.C., EPA 520/1-84-025,
October 1984.
Ka84 KaIkwarf D.R. and Jackson P.O., Lung-Clearance Classification
of Radionuclides in Calcined Phosphate Rock Dust, PNL-5221,
Pacific Northwest Laboratories, Richland, Washington, August
1984.
6.3-19
-------
REFERENCES (Continued)
ICRP66 International Radiological Protection Commission Task Group
on Lung Dynamics, Deposition and Retention Models for
Internal Dosirnetry of Human Respiratory Track, Health Phys.
12:173-207, 1966.
MRl84a Midwest Research Institute, Analysis of Achievable Po~-210
Emissions and Associated Costs for PMC's Pocatello, Idahos
Plant, Midwest Research Institute, Raleigh, North Carolina,
August 1984.
MRl84b Midwest Research Institute, Analysis of Achievable Po-210
Emissions and Associated Costs for Monsanto's Soda Springs,
Idaho, Plant, Midwest Research Institute, Raleigh, North
Carolina, September 1984.
RC84a Radian Corporation, Emission Testing of Calciner Off-gases at
FMC Elemental Phosphorus Plant, Pocatello, Idaho, Volumes I
and II, Prepared for U.S. Environmental Protection Agency
under Contract No. 68-02-3174, Work Assignment No. 131,
Radian Corporation, P.O. Box 13000, Research Triangle Park,
NC, 1984.
RC84b Radian Corporation, Emission Testing of Calciner Off-gases at
Stauffer Elemental Phosphorus Plant, Silver Bow, Montana,
Volumes I and II, Prepared for U.S. Environmental Protection
Agency under Contract No. 68-02-3174, Work Assignment No.
132, Radian Corporation, P.O. Box 13000, Research Triangle
Park, NC, 1984.
RC84c Radian Corporation, Emission Testing of Calciner Off-gases at
Monsanto Elemental Phosphorus Plant, Soda Springs, Idaho,
Volumes I and II, Prepared for U.S. Environmental Protection
Agency under Contract No. 68-02-3174, Work Assignment No,
133, Radian Corporation, P.O. Box 13000, Research Triangle
Park, NC, 1984.
6.3-20
-------
Chapter 7: MINERAL EXTRACTION INDUSTRY FACILITIES
Metal Mines,Hills, and Smelters
Almost all industrial operations involving the removal and
processing of ores to recover metals release some radionuclldes into
air. This chapter presents an assessment of the radionuclide emissions
from the aluminum, copper, zinc, and lead industries. These industries
were studied because they involve the processing of large quantities of
ore and because they all Involve pyrometallurgical processes which have
the greatest potential for radionuclide emissions.
For the aluminum industry the assessment includes emissions from
an alumina plant and aluminum reduction plants. The assessments of the
copper and zinc industries include assessments of mine, mill, and
smelter emissions. Finally, smelter emissions for the lead industry
are assessed.
7.1 Aluminum Industry
7.1.1 General Description
Bauxite is the principal aluminum ore found in nature. The ore is
processed at the mine to produce alumina (R^OgK the basic feed in
the aluminum reduction process. Aluminum metal is produced by the
reduction of alumina in a molten bath of cryolite. The production of
aluminum differs from other primary metals in that no purification of
the metal produced in the electric cells is needed; contaminants in the
ore are removed in the milling rather than the smelting phase of the
process.
Of the 12 domestic companies producing primary aluminum, only
Alcoa and Reynolds perform all stages of production, from domestic
mining through the primary metal stage. Almost all of the bauxite used
in aluminum production is imported. Five other domestic firms own
bauxite and/or alumina facilities in other countries and import raw
materials. Only 5 of the 12 firms that own primary aluminum plants
also own domestic plants producing the input product, alumina. These
five companies (Aluminum Company of America, Kaiser Aluminum and
7.1-1
-------
Table 7.1-1. Location and size of primary aluminum production plants
(DOI80)
Location
Alabama
Arkadelphia
Jones Mills
Listerhill
scottsboro
Indiana
Evansville
Kentucky
Hawesville
Sebree
Company
Reynolds Metals Company
Reynolds Metals Company
Reynolds Metals Company
Revere Copper & Brass Co.
Aluminum Company of America
National Southwire
Anaconda Aluminum Company
Capacity
(1000 MT/y)
56
103
166
95
239
148
148
Louisiana
Chalmette
Lake Charles
Maryland
Frederick
Missouri
Mew Madrid
Kaiser Aluminum & Chemical Corp, 215
Consolidated Aluminum Corporation 30
Eastalco Aluminum Company
Noranda
145
115
Montana
Columbia Falls
North Carolina
Badin
Anaconda Aluminum company
Aluminum Company of America
148
103
Massena
Massena
Ohio
Hannibal
Oregon
The Dalles
Troutdale
Tennessee
Alcoa
New Johnsville
Aluminum Company of America 177
Reynolds Metals Company 104
Ormet Corporation 215
Martin-Marietta Aluminum Co. 75
Reynolds Metals Company 104
Aluminum Company of America 182
Consolidated Aluminum Corporation 119
7.1-2
-------
fable
1-1. Location and size of primary aluminum production plants
(Continued)
Location
Texas
Point Comfort
Palestine
Rockdale
San Patrlcio
Washington
Ferndale
Goldendale
Longview
Mead
Ravenswood
Tacoma
Vancouver
Wenatchee
Total
Company
Capacity
(1000 MT/y)
Aluminum Company of America 153
Aluminum Company of America 13
Aluminum Company of America 268
Reynolds Metals Company 94
Intalco Aluminum Corp. 215
Martin-Marietta Aluminum Company 99
Reynolds Metals Company 174
Kaiser Aluminum & Chemical Corp. 182
Kaiser Aluminum & Chemical Corp. 135
Kaiser Aluminum & Chemical Corp. 66
Aluminum Company of America 95
Aluminum Company of America 173
4354
Chemical Corporation, Reynolds Metals Co., Martin Marietta Aluminum
Co,, and Ormet Corp.) own 73 percent of the current U.S. primary
aluminum capacity (St78).
There are currently 32 operating primary aluminum smelters in the
United States (Table 7.1-1). With one exception, all of the plants are
located in rural areas. Population densities in the vicinities of the
plants range from 12 to 62 persons per square kilometer (EPA79).
7.1-2 Pjrocess_Descri£t ion
Bauxite ore is processed at the alumina plant to produce alumina
using a modified "American Bayer" process. EPA measurements indicate
that the ore is elevated in both uranium-238 and thorium-232 with
concentrations of 6.8 and 5.5 pci/g (EPA82). The data in Table 7.1-2
show that most of the radioactivity in the ore is associated with the
impurities rather than the alumina product.
Of the 32 aluminum reduction plants in the United States, ail but
one produce aluminum in electric furnaces (cells) by the Hall-Hiroult
process. In the Hall-Hiroult process, alumina (Ai^Og) is reduced
electrolytically in a molten bath of cryolite (NaAlFg). The Aluminum
Company of America's pilot plant in Palestine, Texas, employs aluminum
chloride as the electrolyte.
7.1-3
-------
Table 7,1-2. Radionuclide concentrations in alumina
plant process samples (EPA82)
Samp
Uranium- 238 Thorium- 232
Bauxite ore 6.8 5.5
Alumina kiln feed 0.05 0.05
Alumina product 0,28 0.2
Red mud 7.5 5.0
Brown mud 5.5 12.5
Two basic types of cells are used by the industry: prebake and
Soderberg. The chief difference between the two types is the means by
which carbon is supplied to the reduction cells. At prebake plants,
both center- and side-worked cells use preformed carbon anodes baked
into a solid mass. Soderberg cells use carbon anode paste which is fed
to the cell continuously.
Both types of reduction cells are operated at temperatures in
excess of 950° C, the melting point of the cryolite. Approximately
2.6 metric tons of raw materials, along with large quantities of
electricity, are required to produce 1 MT of aluminum. The breakdown
of raw materials is shown in Table 7.1-3.
Table 7.1-3. Raw materials used in producing aluminum (EPA77)
Raw material MT Feed/MT ftl produced
Alumina (A1203) 1.9
Cryolite (NaAlF6) 0.03-0.05
Aluminum Fluoride (Al?3) 0.03-0.05
Fluorspar (CaF2) 0.003
Petroleum Coke 0.455-0.490
Pitch Binder 0.123-0.167
Carbon (cathode) 0.02
The particulate emissions from the process reflect the composition
of the feed materials, and include alumina, carbon, cryolite, aluminum
fluoride, and trace elements. Generation of particulate emissions
varies with the type of cells. At prebake plants, particulate
emissions from the anode furnace range from 0.5 to 2.5 kg/MT of
7.1-4
-------
aluminum produced, with 1.5 kg/MT being a typical value (EPA76).
Participate emissions generated by the cells vary from 5.95 to 88.5
kg/MT, with 40.65 kg/MT being typical (EPA76).
Materia 1 s
No evidence could be found that the quality of feed materials
varies to any significant degree, Radionuclide concentrations for
input materials are given in Table 7.1-4.
Table 7.1-4. Radionuclide concentrations of
feed materials to aluminum plants (KPA82)
Radionuclide concentration (pCi/g)
Feed material __. ...
Uranium-238 ~ ~~ Thorium 232"
Alumina 0.10 <0.2
Aluminum Fluoride O.U <0.2
Cryolite 0.11 <0.2
7.1.3 Con t r o 1 Techno logy for P r _ima ry_ Aluminumgejduc_t lonJPl arit_s
Controls for emissions from aluminum plants are either primary or
secondary controls. Primary controls handle the emissions captured by
the cell hoods, while secondary controls are used to treat the entire
building effluent, including cell emissions that escape the primary
hoods. Primary controls are used at all plants, but secondary controls
are generally used only by the plants that employ soderberg cells
(EPA79).
Control devices used for primary control vary widely from plant to
plant, and include multicyclones, dry and fluid bed alumina adsorbers
followed by fabric filters or electrostatic precipitators, and spray
towers with spray screens. Not only do the efficiencies of these
devices vary over a considerable range (70 to 99-f percent), but the
collecting hoods for the various types of cells range from less than 80
percent to greater than 95 percent capture efficiency (EPA79).
7.1.4 Radiqnuc1ide Emissions
Emissions from the alumina kilns and red mud kilns at an alumina
plant are given in Table 7.1-5. The low radioactivity of alumina is
reflected in the low radionuclide emissions from the alumina kilns.
Emissions of radionuclides from the red mud sinter kiln were below
measurable concentrations except for lead-210, polonium 210, and
7.1-5
-------
radon-222. The high temperature of the kiln causes a large fraction of
lead-210 and polonium 210 to be volatilized.
Table 7.1-5. Radlonucllde emissions from the surveyed alumina plant
(RPA82)
Etnissions (Ci/y)
Radlonuc1ide "
Alumina kilns Red mud kilns
Uranium-238
Uranium 234
Radium 226
Radon- 222
Lead-210
Polonium-210
8 . 7E--3
5.7E-3
2.71-3
2,75
4.8E-2
4.0E-2
Particulate material emitted from an aluminum reduction plant
contains radionuclide concentrations (pCi/g) similar to or greater than
the concentrations in the alumina processed. Because of the high
temperatures of the reduction cells, lead-210 and polonium-210 are
volatilized and released in greater quantities than the other
radioriuclides in the alumina. EPA has measured the radionuclide
emissions from an aluminum reduction plant. The emission estimates for
the reference aluminum reduction plant are based on data from these
measurements.
7.1.5 Reference Fac 1.1 it.les
Measured emissions from a single alumina plant were used to
estimate health impacts for alumina production.
Table 7.1-6 describes the parameters of a reference aluminum
reduction plant which are used to calculate the radionuclide emissions
to air and the resulting health impacts and to give a general idea o£
plant parameters.
Since the currently operating facilities have similar particulate
emission rates and use roughly the same process and feed stocks, one
reference plant characterizes the primary aluminum source category. It
uses center-worked prebake cells, the most commonly used equipment now
in operation. The capacity chosen (136,000 metric tons/y of aluminum)
is approximately the average size of all existing plants. A capacity
factor of 0.94 is applied to the plant, the 1979 industry-wide average
(DOI80).
7.1-
-------
Table 7.1-6. Reference aluminum reduction plant
Parameter Value
Capacity 136,000 MT/y aluminum
Capacity factor 0.94
Type of equipment Center-worked prebake cells
Stack Parameters
Main stack
Height 36 m (4 stacks)
Diameter 3 m
Exit gas velocity 80 m/s
Exit gas temperature 160° C
Roof monitor
Height 10 m
Diameter 1.2 m
Exit gas velocity 0.01 m/s
Exit gas temperature 37° C
Anode bake plant
Height 30 m
Diameter 1.8 m
Exit gas velocity 4.5 m/s
Exit gas temperature 96° C
As of 1975, 95 percent of all plants had at least primary control
of particulate emissions, and 73 percent were reported to have "best"
primary control; only 11 percent had "best" primary plus secondary
control (EPA79). It is presumed that "best" primary control consists
of the best available hooding, plus a fluidized-bed scrubber since this
unit can achieve the highest reported control efficiencies (97-99
percent removal). Based on this information, the reference plant is
equipped with a fluidized-bed scrubber for primary control. The plant
has no secondary control equipment. As for the anode bake plant, a
spray scrubber constitutes the particulate control system.
Sadionuclide emissions for the reference plant were based on
actual measurements of radionuclide concentrations in the particulate
emissions from an existing plant. The resulting releases are listed in
Table 7.1-7.
7.1-7
-------
Table 7.1-7. Radionuclide emissions from the
reference aluminum reduction plant
Emissions (Ci/y)
Uranium-238
Uranium-234
Thorium-230
Ra d i urn- 226
Lead-210
Polonium~210
Thorium-232
Radium-228
Main stack
6.8E-5
6.8E-5
2.4E-4
5.5E-5
3.2E-4
2.7E-4
—
' Roof monitor
8.1E-9
8.1E-9
3.8E-8
7.4E-9
2.0E-7
2.0E-7
2.9E-8
2.9E-8
Anode bake plant
8.0E-5
8.0E-5
4.0E-5
6.0E-5
2.0E-4
2.0E-4
3.2E-5
3.2E-5
main stack emissions were used to calculate doses from
aluminum reduction plant.
7.1.6 Health Impact Assessment
The estimated annual radiation doses and health risks from the
emissions from the alumina plant are given in Tables 7.1-8 through
7.1-10. These estimates are for a rural site with a regional population
of 6E+5.
Table 7.1-8. Radiation dose rates from radioactive participate
emissions from the surveyed alumina plant
Organ
Nearby individuals
(mrem/y)
Regional population
(person-rem/y)
Lung
Red marrow
Endos teum
Breast
Liver
1.7E-2
0.2
2.0
7.5E-2
4.6E-1
15.8
2.63
38.0
0.26
1.35
7.1-8
-------
Table 7.1-9. Annual radon decay product exposures from radort-222
emissions from the surveyed alumina plant
Nearby individuals Regional population
Source "%r.T , 6, ^ 5TT ,
(.WL-y; (.person-WL-y;
Stack 8.5E-10 8E-4
Table 7.1-10. Fatal cancer risks from radionuclide
emissions from the surveyed alumina plant
Lifetime risk Regional population
to nearby individuals (Fatal cancers/y of operation)
Particulates
Radon-222
Total
1E-6
9E-10^a) 4E-lo(b)
1E-6
4E-4
]_E-§(a)
4E-4(a)
SE-S^b)
4E-4(b)
on BEIR-3, NRPB, and EPA models (see Chapter 8, Volume I).
(b)]Jased on USCEAR and ICRP risk estimates (see Chapter 8, Volume I).
The estimated annual radiation doses from radionuclide emissions
from the reference aluminum reduction plant are listed in Table 7.1—11,
These estimates are for a rural site with a regional population of
2.7E+5.
Table 7,1-12 presents estimates of the lifetime risk to nearby
individuals and number of fatal cancers per year of operation from
these doses.
Table 7.1-11. Radiation dose rates from radionuclide
emissions from the reference aluminum reduction plant
-. Nearby individuals Regional population
(mrem/y) (person-rem/y)
Lung
Red marrow
Endosteum
Breast
Liver
Kidney
7.2E-4
0.1
5.3E-1
6.9E-2
3 . 7E-1
1.2
1.29
.35
1.63
,23
1.10
4.06
7.1-9
-------
Table 7,1-12. Fatal cancer risks due to radionuclide emissions
from the reference aluminum reduction plant
Lifetime risk Regional population
to nearby individuals (Fatal cancers/y of operation)
Aluminum
reduction plant 8E-7 7E-5
(particulates)
7.1.7 Existing Emission Standards andAir Pollution Controls
No Federal or state regulations currently exist that limit
radionuclide emissions from alumina plants or aluminum reduction
plants. Particulate emissions from these sources are limited to the
quantities established by the states in their State Implementation
Plans (SIPs) for meeting Ambient Air Quality Standards.
Several states have established specific SIP limits for aluminum
reduction plants, ranging from 15 to 20 Ibs/ton of aluminum produced.
In states where no specific limits have been established for aluminum,
emissions from these sources are regulated according to the limits
established in the SIPs for general processing sources.
7.1-10
-------
REFERENCES
DQ180 U.S. Department of the Interior, 1980, Mineral Commodity
Summaries, Bureau of Mines, January 1980.
EPA76 Environmental Protection Agency, Compilation of Air Pollution
Emission Factors, Second Ed., Part B, AP-42, Feburary 1976.
EPA77 Environmental Protection Agency, Technical Guidance for
Control of Industrial Process Fugitive Participate Emissions,
EPA-450/3-77-010, March 1977.
EPA79 Environmental Protection Agency, Primary Aluminum: Draft
Guidelines for Control of Fluoride Emissions from Existing
Primary Aluminum Plants, EPA-450/2-78-049, February 1979.
EPA82 Environmental Protection Agency, Emissions of Naturally
Occurring Radioactivity from Aluminum and Copper Facilities,
EPA 520/6-82-018, Las Vegas, Nevada, November 1982.
St78 Stamper J. W. and Kurtz H. F., Mineral Commodity
Profile-Aluminum, U.S. Department of the interior, Bureau of
Mines, Washington, D.C.
7.1-11
-------
Page Intentionally Blank
-------
7.2 CongerIndustry
7,2.1 GeneralDescription
Copper ores are milled to produce a concentrate containing copper,
sulfur, iron, and some insoluble material (primarily silica and
aluminum). This concentrate is the basic feed to the copper smelter
that eventually produces the refined copper product. Copper mills and
smelters are located near copper mines. Copper concentrates and
precipitates are generally smelted by melting the charge and suitable
fluxes in a reverberatory furnace. Prior to smelting, part or all of
the concentrates may receive a partial roast to eliminate some of the
sulfur and other impurities.
The 15 operating primary copper smelters in the United States and
their capacities are listed in Table 7.2-1. Total production of
primary copper in 1978 was 1.5 million metric tons (Sc79).
ftll primary copper smelters are located in rural areas with low
population densities. Ninety percent of U.S. copper smelter capacity
is located in the arid and semi-arid climates of Arizona, Montana,
Nevada, New Mexico, Texas, and Utah. The other 10 percent are in
Washington, Michigan, and Tennessee, areas of moderate to high
precipitation. The sites tend to be quite large and generally contain
associated mining and milling operations.
Most companies perform all production processes from mining
through refining. Seven of the eight companies that own smelters also
operate mines and own refineries; Cities Services, which owns the
smallest of the smelters, is the only exception (Sc79).
7.2.2 Process Description
The three major steps in the smelting of copper are roasting,
smelting, and converting. All of these processes result in releases of
sulfur dioxide and particuiate matter in process off-gas. Each step in
the smelting process is described below.
Roasting
Roasting is the first step in the process of copper smelting. In
the roaster, copper ore concentrates are heated to a high temperature
(550° C) in an oxidizing atmosphere which partially drives off some
of the sulfur as sulfur dioxide (in addition to producing particuiate
emissions). Seven of the fifteen domestic copper smelters have
roasters; four plants feed ore concentrates to a rotary dryer to reduce
moisture before smelting; and three feed concentrates directly to the
furnace with no pretreatment.
7.2-1
-------
Table 7.2-1. Primary Copper Smelters in the United States, 1978
(Sc79)
Plant
location
Arizona
Hayden
Miami
Hayden
San Manuel
Morenci
Douglas
A jo
Michigan
White Pine
New Mexico
Hurley
New Mexico
Hidalgo
New York
McGill
Tennessee
Copper Hill
Texas
El Paso
Utah
Gar fie id
Washington
Tacoma
Total
Company
ASARCO, Inc.
inspiration consolidated
Kennecott Copper Corp.
Magma Copper Company
Phelps Dodge Corporation
Phelps Dodge corporation
Phelps Dodge Corporation
Copper Range Company
Kennecott Copper Corp.
Phelps Dodge Corporation
Kennecott Copper Corp.
cities Services Company
ASARCO, Inc.
Kennecott Copper Corp,
ASARCO, Inc.
Capacity
(1000 Mf)
163
136
73
181
161
115
63
82
73
127
45
20
104
254
91
1688
First year
of operation
1890
1958
1950
1942
1910
1950
1905
1939
1976
1907
1845
1905
1907
1890
^Rebuilt as of 1979.
7.2-2
-------
All domestic copper smelters use smelting furnaces to melt and react
copper concentrate and/or calcine in the presence of silica and limestone
flux to form two immiscible liquid layers, one being the slag or waste
layer containing most of the iron and silica compounds and the other
containing copper and iron sulfide and other metals, referred to as matte
copper. Smelting is conducted in either reverberatory or electric
furnaces. Reverberatory furnaces are refractory-lined, box-shaped
structures heated by either natural gas, oil, or coal. Reverberatory
smelting furnaces are more common than electric furnaces. Currently, 2
out of 15 smelters use electric furnaces to smelt copper. Electric
furnaces have basically the same construction as reverberatory furnaces,
Converting
The converter processes matte copper from the reverberatory furnace
by removing iron compounds and converting to copper at high temperatures
(550 to 800° C). The resulting blister copper is further purified by
processing in a refining furnace and by electrolytic refining.
7.2,3 Cpnt rojl Techno logy
Of the 15 primary copper smelters currently operating, 11 use
reverberatory furnaces and 7 have roasters. Of these 7, 4 use
multi-hearth roasters while the other 3 use fluid-bed roasters. The
actual smelting process used by those plants with reverberatory furnaces
does not differ from facility to facility. Acid gas cleanup plants have
been installed on all but three currently operating smelters to treat
converter off-gases. A cyclone, a water spray chamber, and an
electrostatic precipitator (ESP) are used to clean these gases prior to
their entering the SO2 plant. Off-gases from the reverberatory furnace
are controlled via an ESP in virtually all of the operating plants.
Three of the four multi-hearth roasters currently operating treat their
roaster off-gases by using ESPs.
7.2.4 Radionuclide Emission Measurements
EPA has recently carried out radionuclide measurement studies at
both an underground copper mine and mill and an open pit copper mine and
mill (EPA82). The results of these studies indicate that radon-222 is
the only significant radionuclide emitted from the underground mine. At
the open pit mine and mill, radioactive particulates and radon-222 are
emitted, primarily during truck loading and dumping and crushing
operations.
The measurement studies also included analysis of radioactivity in
various process samples. Table 7.2-2 lists the uranium-238 and
thorium- 232 concentrations in process samples from both the underground
mine and mill and the open pit mine and mill.
7.2-3
-------
Table 7.2-2. Radionuclide concentrations in surveyed copper mine
and mill process samples (EPA82)
Type
of
sample
Ore
Concentrate
Underground mine and mill
Uranium- 238 Thorium- 232
(pCi/g) (pci/g)
0.79 0.62
0.65 0.07
Open pit mine and mill
Uranium- 238 Thorium- 232
{pci/g) (pci/g)
2.2 3.1
1.4 1.1
Particulate material emitted from a copper smelter contains
radionuclides in concentrations (pCi/g) similar to or greater than the
ore concentrates. Because of the high temperatures of the roasting and
smelting, some radionuclides (particularly lead-210 and poloniura-210)
may be volatilized and released in greater quantities than the other
radionuclides in the ore concentrates.
Very little information has been available to date on radionuclide
emissions from copper smelters. EPA has recently surveyed two copper
smelters, and the data from these studies were used in estimating
radionuclide emissions from the reference copper smelter.
7.2.5 Reference Facilities
Actual emissions data from EPR's measurement studies were used to
assess potential health impacts from the underground mine (Table 7.2-3)
and open pit mine and milling complexes (Table 7.2-4).
Table 7.2-3. Radionuclide emissions from the
underground copper mine (EPA82)
_., Emissions
Radionuclide ,„,, .
(Ci/y)
Radon-222 6.5
Table 7.2-5 describes the parameters of a reference copper smelter
which were used to estimate the radioactive emissions to the atmosphere
and the resulting health impacts. The capacity of the plant is 56,000
MT/y of copper, the average size of all existing plants without roasters,
The capacity factor chosen for this plant is 0.75. Main stack heights
for facilities without roasters range from 61 to 228 meters. The con-
trol equipment applied to the reference facility was chosen to repre-
sent typical equipment on actual copper sraelters.
7.2-4
-------
Table 7.2-4, Radionucllde emissions from copper mill,
open pit mine, and concentrator (EPA82)
„ ,. ... Emissions
Radionuciide ,_. , ,
Uranium-238 3.1E-4
Uranium-234 3.8E-4
Radium-226 1.8E-4
Radon-222 1.9
Lead-210 1.9E-3
Total annual emissions of radionuclides from the reference copper
smelter are given in Table 7.2-6. These values were derived from data
on radionuclide releases from an existing plant. Reported release
rates were adjusted to account for differences between the actual and
reference facility in annual particulate emissions and total capacity.
Table 7.2-5. Reference copper smelter
Parameter Value
Capacity 56,000 MT/y
Capacity factor 0.75
Type of equipment used Reverberatory furnace
Stack Parameters
Main stack
Height 183 m
Diameter 2,6 m
Exhaust gas velocity 28 m/s
Exhaust gas temperature 135° C
Reid plant
Height 30.4 m
Diameter 1.8m
Exhaust gas velocity 16.5 m/s
Exhaust gas temperature 79° C
Particulate Emission Rate
Main stack 247 kg/h
Acid plant 11 kg/h
7.2-5
-------
Table 7.2-6. Radionuclide emissions front the reference
copper smelter (southwestern site)
Radionuclide
Uranium-238
Uranium~234
Thorium-230
Radium-226
Lead-210
Poloalum~210
Thorium-232
Thorium-228
Emissions
(Ci/y)
4.0E-2
4.0E-2
2.1E-3
1.5E-3
6.5E-2
3.0E-2
1 . 2E-3
1.3E-3
7-2.6 Health Impsct_ Ass e ssment
The estimated radiation doses from radionuclide emissions from the
underground mine and mill, the open pit mine and mill, and the
reference copper smelter are listed in Tables 7.2-7 through 7.2-10.
These estimates are for a low population density southwestern site with
a regional population of 3.6E+4.
Table 7.2-11 presents estimates of the lifetime risk to nearby
individuals and number of fatal cancers per year of operation resulting
from these doses.
Table 7.2-7. Annual radon decay product exposures from radon-222
emissions from the underground copper
Nearby individuals Regional population
(WL~y) (person-WL~y)
Mine vent 2.5E-5 4.2E-4
'a/Based on a ground level release.
7.2-6
-------
Table 7.2-8. Radiation dose rates from radioactive particulate
emissions from the open pit copper mine and
» Nearby individuals Regional population
(mrem/y) (person~rem/y)
Lung
Red marrow
Endosteum
Breast
Liver
1.1E+1
1.6
2.5E+1
2.2E-2
9.9E-2
2.1E-1
2.8E-2
4.5E-1
4.2E-4
1.8E-3
^a'Based on a 10-meter stack height.
Table 7.2-9. Annual radon decay product exposures from radon-222
emissions from the open pit copper mine and mill
_ Nearby individuals Regional population
Source J ,„_ % t TIT %
(WL-y) Cperson-WL-y)
Stack 7.2E-6 1.2E-4
Table 7.2-10. Radiation dose rates from radionuclide particulate
emissions from the reference copper smelter (southwestern site)
n Nearby individuals Regional population
(mrem/y) (person-rem/y)
Lung 2.0E-1 0.95
Red marrow 3.2E-3 1.4E-2
Endosteum 4.5E-2 0.21
Breast 2.9E-4 1.2E-3
Liver 2.2E-3 8.7E-3
7.2-7
-------
Table 7.2-11. Fatal cancer risks from radlonuclide
emissions from the underground copper mines the open pit copper mine
and mill 3 and the reference copper smelter
Source
Particulates
Radon-222
Total
Lifetime risk Regional population
to nearby individuals (Fatal cancers/y of operation)
Underground copper mine
IE-7
4E-5U)
4E-5U)
2£-5
4E-8
Particulates
Radon-222
Total
Particulates
Open pit copper mine and mill
2E-5
9E-6(a) 4E-7
-------
REFERENCES
EPA82 Environmental Protection Agency, Emissions of Naturally
Occurring Radioactivity from Aluminum and Copper Facilities,
SPA 520/6-82-018, Las Vegas, Nevada, November 1982.
Sc79 Schroeder H. J., Mineral commodity Proflies--Copper, U.S.
Department of the Interior, Bureau of Mines, Washington, D.C.,
1979,
7.2-9
-------
Page Intentionally Blank
-------
3 g tnc Indus t i_y
Zinc Is usually found In nature as a sulfide ore called
sphalerite. The ores, which usually contain impurities of lead,
cadmium, and traces of other elements, are processed at the mine to
form concentrates typically containing 62 percent zinc and 32 percent
sulfur. These concentrates are processed at the smelter to recover
zinc metal.
The five operating primary zinc production facilities in the
United states and their capacities are listed in Table 7.3-1. Total
production capacity for primary zinc in 1980 was 401,000 metric tons.
The domestic demand for zinc is expected to grow at a rate of about
2 percent per year through 1985 (ca78).
In the past 10 years, U.S. demand for zinc metal has grown slowly,
but U.S. smelting capacity has declined by over 50 percent. Plants
closed because they were obsolete, could not meet environmental
standards, or could not obtain sufficient concentrate feed.
Consequently, the metal has replaced concentrate as the major form of
import. This situation is expected to continue.
7.3.2 Process_Descjrigt_ioji
A zinc smelter produces 99.99+ percent zinc from the approximately
62 percent zinc concentrate feed produced by the mill. The zinc
concentrates are roasted at approximately 600° C to convert sulfur to
sulfur dioxide an
-------
Table 7.3-1. Location size of primary zinc production plants
CCa78)
, „ First year Capacity
Location Company _ . . ,_. , *• ,,m\
r J of operation (Thousands of MT)
Idaho Bunker Hill 1928 95
Kellogg
-------
Table 7.3-2. Radionuclide emissions from the zinc mine
and mill (EPA82)
Radionuclide
Uranium- 238
Uranium- 234
Thorium- 230
Radium- 226
Radon 222
Lead- 210
Polonium- 2 10
Thorium- 232
Thorium- 228
Emissions
(Ci/y)
1.8E-3
1.8E-3
1.5E-3
8 , 2E- 4
2.3E+2
2.6E-3
2.2E-3
6.QE-4
4.7E-4
Particulate material emitted from a zinc smelter contains
radionuclides in concentrations similar to or greater than the
concentrations in the materials processed. Because of the high
temperatures to which the concentrates are heated, some of the
radionuclides {particularly lead-210 and polonium 210} may be
volatilized and released in greater quantities than the other
radionuclides in the ore concentrates.
7.3,5 ReferenceFacilities
Actual emissions from a mine and mill complex (chosen because of
the high working level measurements reported for the mine, and high
production rates) were used to estimate health impacts from these
sources.
Table 7.3-3 describes the parameters of a reference zinc smelter
which were used to estimate the radioactive emissions to the atmosphere
and the resulting health impacts.
The reference zinc smelter has a total production capacity of
about 88,000 MT/y, typical of the industry. The plant produces zinc by
electrolytic reduction and operates at an annual capacity factor of
0.80, the 1976 industry-wide average (DO176). The flow rate was
derived by adjusting available data for differences in capacity and
capacity factor. The stack height and diameter were estimated from
available data.
Roaster off-gases are treated for dust removal by a cyclone in
series with an electrostatic precipitator. The cleaned gases are then
passed through a sulfur dioxide (302) plant. Off-gases from the
electrolytic reduction step are vented directly to the atmosphere.
7.3-3
-------
The total annual radionuclide emissions for the reference zinc
smelter are listed in Table 7.3-4.
Table 7,3-3. Reference zinc smelter
Parameter
Value
Process
Capacity
Capacity factor
Radionuclide concentration
of input ore'a'
Uranium- 238
Thorium- 232
Stack Parameters
Number
Height
Diameter
Exhaust gas velocity
Exhaust gas temperature
Electrolytic reduction
88 E+3 KT/yr zinc
0.8
0.18 pCi/g
0,08 pCi/g
1
100 meters
2 meters
20 m/s
150° C
measurements by EPA (EPA82) at a zinc smelter.
Table 7.3-4. Radionuclide emissions from the reference zinc smelter
Radionuclide
Uranium- 238
Uranium- 234
Thorium- 230
Radium- 226
Radon- 222
Lead- 210
Polonium- 210
Thorium- 23 2
Thorium- 228
Emissions
(Ci/y)
5.6E-4
3.7E- 4
1 . 4E- 3
4.5E-3
2 . 8E- 1
2.5E- 2
1.5E-3
3 . 4E- 4
3.4E-4
7.3-4
-------
7.3.6. Hgalth jinga.c_t__Assessmeu^
The estimated annual radiation doses from the radiotiuclide emissions
of the zinc mines mill, and smelter are listed in Tables 7.3-5 through
7.3~8« These estimates are for a rural site with a regional population
of 6E+5. The lifetime risk to nearby individuals and number of fatal
cancers per year of operation are shown in Tables 7.3-9 and 7.3-10.
Table 7.3-5. Radiation dose rates from radioactive particulate
emissions froai the zinc mine and
.. Nearby individuals Regional population
Organ / , , 6, / \
(mrem/y) ^person-rem/yj
Lung
Red marrow
Endosteum
Breast
Liver
4.1
3.6E-1
5.8
4.7E-3
2.1E-2
14.1
1.27
20.1
1.8E-2
8.1E-2
(a'Based on Arkansas population.
Table 7.3-6. Annual radon decay product exposures from radon-222
emissions from the zinc mine and mi
_ Nearby individuals Regional population
(WL-y) (person-WL-y)
Mine vent 1E-4 4E-1
'a'Based on Arkansas population.
Table 7.3-7. Annual radon decay product exposures from radon-222
emissions from the zinc smelter
„ Nearby individuals Regional population
(WL-y) (person-WL-y)
Zinc smelter 5.3E-10 6E-5
7.3-5
-------
Table 7.3-8. Radiation dose rates from radionuclide
emissions from the reference zinc smelter^-3'
_ Nearby individuals Regional population
• (mrera/y) (person-rem/y)
Lung
Red marrow
Endosteum
Breast
Liver
l.OE-2
1 . 7E-3
2.2E-2
2.4E-4
1.4E-3
1.12
2.0B-1
2,5
2.7E-2
1.6E-1
'a'Based on Arkansas population.
Table 7.3-9. Fatal cancer risks from radionuclide
emissions from the zinc mine and mill'*^
„ Lifetime risk Regional population
to nearby individuals (Fatal cancers/y of operation)
Particulates
Radon-222
Total
7E-6
2E-4(b) 8E-5^C)
2E-4(b) 9E-5^C)
3E-4
8E_3(b) 4£_3(c)
9E-3^b) 4E-3(c)
on Arkansas population.
on BEIR-3, NRPB, and EPA models (see Chapter 8, Volume l).
on USCEAR and ICRP risk estimates (see Chapter 8, Volume I).
Table 7.3-10. Fatal cancer risks from radionuclide
emissions from the reference zinc smelter^3'
Lifetime risk Regional population
to nearby individuals (Fatal cancers/y of operation)
Particulates 2E-8 4E-5
Radon-222 7E-10(b) 3E-10(C) lE-6^b) 6E-7^C)
Total 2E~8(b»c) 4E-5(b,c)
(a)Based on Arkansas population.
(k)Based on BEIR-3, NRPB, and EPA models (see Chapter 8, Volume I).
(c)Based on USCEAR and ICRP risk estimates (see Chapter 8, Volume I).
7.3-6
-------
7.3.7 ExistjLng_Emtss.ion Standards and a.ir__polj.utlon__Con.trQ|.s
No Federal or state regulations currently exist that limit
radionuclide emissions from zinc smelting. Participate emissions £rom
zinc smelting are regulated by New Source Performance standards (*)SPS)
for plants built after October 1974, or by the limits established in
State Implementation Plans (Sips) for meeting Ambient Air Quality
Standards. The NSPS for zinc smelting is less than 50 mg/Dry Standard
Cubic Meters.
7.3-1
-------
REFERENCES
Ca78 Cammarota V. A., Jr., Mineral Commodity Profiles-Zinc,
MCP-12, U.S. Department of the Interior, Bureau of Mines, Hay
1978.
DOI76 Department of Interior, Preprint from the 1976 Bureau of
Mines Minerals Yearbook: Zinc, Washington, D.C., 1976.
EPA82 Environmental Protection Agency, Emissions of Naturally
Occurring Radioactivity: Underground Zinc Mine and Mill,
EPA 520/6-82-020, Las Vegas, Nevada, November 1982.
7,3-8
-------
7,4 Le ad Indus t ry
7.4.1 General JDes£ri£jtlon
Galena (PbS), frequently containing cerussite (PbCO^) and
anglesite (PbSO^), is the principal lead-bearing ore found in
nature. A sulfide ore, galena contains small amounts of copper, iron,
zinc, and other trace elements (EPA75). in the smelting process, lead
bullion (95-99 percent lead metal) is separated from ore concentrates
(45-80 percent lead).
Table 7.4-1 lists the location and size of the primary lead
smelters. Three facilities have integrated smelter/refinery complexes
and two facilities (RSARCO's El Paso and East Helena smelters) ship
their drossed lead bullion to the company's Omaha refinery for final
processing. Refinery operations, including those co-located with
smelters, are not considered part of the primary lead source category.
Three of the smelters are located in southeastern Missouri and
process only ores from the Missouri lead belt. The smelters located in
Texas and Montana are custom smelters, designed to handle larger
variations in ore composition than the Missouri smelters. Both
domestic and foreign ores are smelted at the western plants.
The design capacities of the primary lead smelters, expressed as
annual lead metal output, range from 82,000 to 204,000 tons. Total
production from primary smelters in 1979 was 594,000 tons (DOC80),
7.4.2 Process_ ..Dejscjripj: ion
Lead smelting involves three distinct processes: sintering, to
convert the ore from a r.ulfide to an oxide or sulfate form and prepare
the feed materials for furnaeing; furnacing, to reduce the oxide feed
to lead metal; and dross ing, to reduce the copper content of the lead
bullion from the furnace. After dressing, additional refining steps,
as dictated by the specific impurities present and the intended end-use
of the product, are performed to yield the purified lead metal.
7.4.3 Contrp i_Techng;logjy_
Off-gases from the sintering machine and the blast furnace are the
most significant sources of particulate emissions from the lead
smelting process; together these two sources account for more than 95
percent of particulate emissions.
Sintering^ Machines
Particle size distribution of particulate matter entrained in
off-gas from sintering machines indicated that the majority of
particles are less than 10 microns in diameter. This relatively small
particle size precludes the use of mechanical collectors or wet
7.4-1
-------
Table 7.4-1. Location size of primary lead production plants
(D0177)
Location
Idaho
Missouri
Boss
Glover
Herculanium
Company
Bunker Hill
Amax- Homes take
RSRRCO
St. Joe Minerals
First year
of operation
capacity
(Thousands of
tons of Pb)
1911 117
1968 127
1968 100
1892 220
rebuilt 1970's
Montana
East Helena
ASARCO
1888
82
Texas
El Paso
Now shut down.
RSARCO
1887
82
scrubbing systems, which decrease in efficiency substantially with
decreasing size of the particle collected. Consequently, five of the
six existing lead sintering machines use fabric filters for participate
emission control; the sixth employs an ESP (IERL79). The final control
devices, in many cases, are preceded by ballon flues or settling
chambers for gravitational collection of more massive particles before
of f-gases enter the ESP or fabric filter.
Sinter off-gas is typically fed to an acid plant for recovery of
sulfur dioxide after particulate cleaning, as described above. Effi-
cient operation of the acid plant requires gases containing 5 percent
or more SC>2. The circuit of gases through the sinter machine may be
quite complex with weak (in sc^) gases being recirculated through an
upstream section of the machine to enrich the SC>2 content before
going to the acid plant.
B1ast Furnaces
The majority of particles in the lead blast furnace off-gas are
smaller than 10 microns in diameter. Consequently, all blast furnace
systems currently in operation are serviced by baghouses. The
particulate collection efficiencies of baghouses treating lead blast
furnace off-gas is roughly 99 percent.
7.4-2
-------
7.4.4 IiiOTiulde^ ^Emisjjigris
Particulate material emitted from a lead smelter contains
radionuclides in concentrations similar to or greater than the
concentrations in the materials processed. Since enrichment takes
place when nuclides volatilize during the high-temperature phase of
production, the concentration of some radionuclides will be higher in
the particulates than in the original ore. EPA has recently measured
the radionuclide emissions at a lead smelter, and results of these
measurements are used in this report. Radionuclide emissions are
presented in Table 7.4-3.
7.4.5 Re f erence Fac il i t y
Table 7.4-2 describes the parameters of the reference facility
which were used to describe the radioactive emissions to the atmosphere
and the resulting health impacts.
The reference lead smelter has a capacity of 220,000 MT lead per
year, typical of existing plants. The plant operates at a load factor
of 0.92 which was the industry-wide average for 1979 (DOC80). There
are two stacks at the plant — a main stack and an acid plant tail gas
stack. For calculational purposes, however, emissions were treated as
coming from one stack.
7.4.6 Health Impact Assessment of Reference Smelter
The estimated radiation doses from radionuclide emissions from the
reference lead smelter are listed in Table 7.4-4. These estimates -are
for a rural site with a regional population of 2.9E+5.
Table 7.4-5 presents estimates of the maximum individual lifetime
risk and number of fatal cancers per year of operation of the reference
smelter.
7.4.7 Existing Emission Standards and Air Pollution Controls
No Federal or state regulations currently exist that limit
radionuclide emissions from lead smelting. Particulate emissions from
lead smelters are regulated by New Source Performance Standards (NSPS)
for plants built after October 1974, or by State Implementation Plans
(SIPs). The NSPS for lead sintering machines, blast furnaces, and
dross furnaces is less than 50 mg/Dry Standard Cubic Meters.
7.4-3
-------
Table 7.4-2. Reference lead smelter
Parameter Value
Capacity 2.2E+5 MT/yr lead
Capacity factor 0,92
Radionuclide concentration
of input ore:
Uranium-238 0.9 pCi/g
Thorium-232 0.5 pCi/g
stack Parameters
Number 1
Main stack
Height 30 meters
Diameter 1 meter
Exit gas velocity 9 m/s
Exhaust gas temperature 90°C
Acid plant stack
Height 30 meters
Diameter 1.8 meters
Exhaust gas velocity 1.7 m/s
Exhaust gas temperature 93°C
Table 7.4-3. Radionuclide emissions from the
reference lead plant
Radionuclide Emissions^8)
(Cl/y)
Uranium-238 8.6E~3
Uranium™234 8.6E~3
Thorium-230 7.3E-4
Radium 226 5.9E-4
Lead-210 2.6E-2
Polonium-210 2.IE-2
Thorium-232 7.0E-4
Thorium-228 7.OB-4
stack only.
7.4-4
-------
Table 7,4-4, Radiation dose rates from radionuclide
emissions from the reference lead smelter
Organ
Nearby individuals
(mrem/y)
Regional population
(person-rem/y)
Lung
Red marrow
Endosteum
Breast
Liver
4.8
1.2E-1
1.8
9.9E-3
5.9E-2
6.9E+1
1.8
2.6E+1
0.17
1. 01
Table 7.4-5. Fatal cancer risks due to radionuclide emissions
from the reference lead smelter
Source
Lifetime risk
to nearby individuals
Regional population
(Fatal cancers/y of operation)
Particulates
8E-6
1.6E-3
7.4-5
-------
REFERENCES
DOC80 U.S. Department of Commerce, U.S. Industrial Outlook for 200
Industries with Projections for 1984, Washington, D.C., 1980.
DOI77 U.S. Department of the Interior, Lead Mineral Commodity
Profiles--Lead, Washington, D.C., December 1977.
RPA75 Environmental Protection agency, Development for Interim Final
Effluent Limitations Guidelines and Proposed New source
Performance Standards for the Lead Segment of the Nonferrous
Metals Manufacturing Point Source Category, EPA 440/1-75/032-9,
Washington, D.C., February 1975.
I8RL79 Industrial Environmental Research Laboratory, Control of
Particulate Emissions in the Primary Nonferrous Metals
Industries, NTIS Report No. PB-80-151822, Cincinnati, Ohio,
December 1979.
7.4-6
-------
APPENDIX A
ASSESSMENT METHODOLOGY
-------
Page Intentionally Blank
-------
APPENDIX A: ASSESSMENT METHODOLOGY
CONTENTS
Page
A.I Introduction A-5
A. 2 Reference Facility A-5
A.3 Generic Sites A-5
A.4 Source Characterization A-6
A.5 Environmental Pathway Modeling Computer Programs A-6
A.6 Individual Assessment A-10
A, 7 Collective Assessment A-ll
A.8 AIRDQS-EPA Parameters and Input Data A-12
A.9 DARTAB—Dose and Risk Tables A-14
References A-21
TABLES
A-l Characteristics of the generic sites A-7
A-2 Sources of food for the maximum individual A-ll
A-3 Some site parameters used with AIRDOS-EPA A-13
A-4 Cattle densities and vegetable crop distributions
for use with AIRDOS-EPA A-15
A-5 Site independent parameters used for AIRDOS-EPA
generic site assessments A-17
A-6 Element dependent factors used in AIRDOS-EPA assessments A-19
A-3
-------
Page Intentionally Blank
-------
Appendix A: ASSESSMENT METHODOLOGY
A.I Introduction
The general methodology used in the generic assessments presented in
this report consisted of the following parts:
1) a description of a reference facility for the source category,
2) a choice of one or more generic sites appropriate to the source
category,
3) an assignment of a source term (Ci/y) and source related
quantities (e.g., release height, pj.ume rise),
4) a calculation of individual and collective doses and risks due to
air immersion, ground surface exposure, inhalation, and ingestion of
radionuclides,
Assumptions made at each step were intended to be realistic without
underestimating the impact of a release. The following sections describe
these steps in more detail. (See Appendix B for health risk assessment
details. )
A*2 Reference Facility
For each source category, a reference facility was designated. In
some instances (e.g., nuclear power plants), extensive information was
available on release rates and source considerations influencing
dispersion (e.g., release height and exit velocity). In such cases, a
reference facility was designed to represent an average facility for the
source category. For other source categories (e.g., radiopharmaceutical
industry), industry wide information was sparse. In these cases, data
for a particular facility considered representative of the source
category were used for the assessment.
A.3 Generic Sites
Generic sites were characterized for the purpose of assessing
different source categories. These sites were chosen by
A-5
-------
first identifying locations of facilities within each source category and
then identifying a few of them which typified the types of locations
where such facilities might be located. Factors which entered into this
judgment included geographic location, population density, and food crop
production.
On the basis of similarities between representative sites for the
different source categories, seven generic sites (designated A, B, Cs D,
E, F, and G) were chosen which were believed to adequately represent
potential sites for all of the source categories considered. For some
source categories, one site was sufficient (e.g., uranium mining) while
others required several sites to represent the source category (e.g.
fossil fuel power plants). While the data used to characterize the
generic sites were obtained for specific locations, there would not
necessarily be a facility at that location for any specific source
category.
Sites A and B represent urban and suburban locations, respectively.
Site A characterizes a very large metropolitan city: the maximum case
with respect to population density and overall population within 80 kin
(New York City, New York). Site B represents the near suburbs of a large
Midwest city (St. Louis, Missouri). Site C was selected to depict the
phosphate industry since this location has a heavy concentration of
phosphate mining and milling (Polk County, Florida, near Bartow). Site D
represents a rural setting in the central portion of the United States
(near Little Rock, Arkansas). Site E exhibits the characteristics
associated with the uranium industry and other mining endeavors (Grants,
New Mexico). Site F is a remote, sparsely populated location in the
Northwest which represents a minimal impact on the general population
(near Billings3 Montana). Site G (near Pocatello, Idaho) is
representative of elemental phosphorous processing sites. Table A~l
gives the important characteristics of these generic sites.
A.4 Source Characterization
Sources were characterized by the release rate (Ci/year) of each
emitted radionuclide. An effective release height was assigned to each
source based on the release height and any expected plume rise. In
general, no credit was given for plume rise unless it was clearly
indicated,
A.5 Environmental Pathway Modeling^Computer Programs
AIRDOS-EPA (Mo79) was used, as discussed in Volume I, Chapter 6, to
calculate the individual and collective radionuclide concentrations for
these assessments.
A-6
-------
Table A-l. Characteristics of the generic sites
Site A—New York
Meteorological data:
Stability Categories:
Period of Record:
Annual Rainfall:
Average Temperature:
Average Mixing Height:
Population (0-8 km):
(0-80 km):
Dairy Cattle (0-80 km):
Beef Cattle {0-80 km):
Vegetable Crop Area:
(0-80 km)
New York/LaGuardia (WBAN=14732)
A-F
65/01-70/12
102 cm
12.10 c
1000 in
9.23E+5 persons
1.72E+7 persons
1.72E+5 head
1.17E+5 head
3.77E+4 ha
Site B--Missouri
Meteorological data:
Stability Categories;
Period of Record:
Annual Rainfall:
Average Temperature:
Average Mixing Height:
Population: (0-8 km):
(0-80 km):
Dairy Cattle (0-80 km):
Beef Cattle (0-80 km):
Vegetable Food Crop Area:
(0-80 km)
St. Louis/Lambert (WBAN=13994)
A-G
60/01-64/12
102 cm
11.50 c
600 m
1.34E+4 persons
2.49E+6 persons
3.80S+4 head
6.90E+5 head
1.64E+4 ha
A-7
-------
Table A-l. Characteristics of the generic sites—continued
Site C—Florida
Meteorological data:
Stability Categories:
Period of Becord:
Annual Rainfall:
Average Temperature:
Average Mixing Height:
Population: (0-10 km):
(0-80 km):
Dairy Cattle (0-80 km):
Beef Cattle (0-80 km):
Vegetable Crop Area:
(0-80 km)
Orlando/Jet Port (WBAN=12S15)
A-E
74/01-74/12
142 cm
22.0° c
1000 m
1.55E+3 persons
1.51E+6 persons
2.75E+4 head
2.57E+5 head
1.39E+4 ha
Site D—Arkansas
Meteorological data:
Stability Categories:
Period of Record:
Annual Rainfall:
Average Temperature:
Average Mixing Height:
Population: (0-8 km):
(0-80 km):
Dairy Cattle (0-80 km):
Beef Cattle (0-80 km):
Vegetable Crop Area:
(0-80 km)
Little Rock/Adams (WBAN=13963)
A-F
72/02-73/02
127 cm
14.8° C
600 m
1.18E+4 persons
5.89E+5 persons
1.19E+4 head
2.57E+5 head
2.94E+3 ha
A-8
-------
Table A-l. Characteristics of the generic sites~-continu«
Site E —New Mexico
Meteorological data:
Stability Categories:
Period of Record:
Annual Rainfall:
Average Temperature:
Average Mixing Height:
Population: (0-8 kin):
(0-80 km):
Dairy Cattle (0-80 km):
Beef Cattle (Q-8Q km):
Vegetable Crop Area:
(0-80 km)
Grants/Gnt-MiIan (WBAN=93057)
A-F
54/01-54/12
20 cm
13.20 c
800 m
0 persons
3.6QE+4 persons
2.30E+3 head
8.31E+4 head
2.78EH-3 ha
Site F—Montana
Meteorological data:
Stability Categories:
Period of Record:
Annual Rainfall:
Average Temperature:
Average Mixing Height:
Population: (0-8 km):
(0-80 km):
Dairy Cattle (0-80 km):
Beef Cattle (0-80 km):
Vegetable Crop Area:
(0-80 km)
Bill ings/Logan
A-F
67/01-71/12
20 cm
8.10 c
700 m
0 persons
1.30E+4 persons
1.86E+3 head
1.47E+5 head
1.77E+4 ha
(WBAN=24033)
A-9
-------
Table
Characteristics of the generic si.tes~~conti.nued
Site G—Idaho
Meteorological data:
Stability Categories:
Period of Record:
Annual Rainfall:
Average Temperature:
Average Mixing Height:
Population: (0-10 km):
(0-80 km):
Dairy Cattle (0-80 km):
Beef Cattle (0-80 km):
Vegetable Crop Area;
(0-80 km)
Pocatello (WBAN=24156)
A-F
54/01-62/12
27.4 cm
7.80 c
615 ra
4.17E+4 persons
1.40E+5 persons
1.72E+4 head
1.45E+5 head
1.44E+5 ha
Air concentrations are ground level sector averages. Dispersion is
calculated from annual average meteorological data. Depletion due to dry
deposition and precipitation scavenging is calculated for particulates
and reactive vapors.
Ground surface and soil concentrations are calculated for those
nuclides subject to deposition due to dry deposition and precipitation
scavenging.
The output from AIRDOS-EPA contains calculated radionuclide intakes
and external exposure. This file is used as input to DARTAB (Be81) to
produce the dose and risk tables used in the individual and collective
assessments. The dose and risk conversion factors used for these
calculations are discussed in Volume I, Chapter 8.
A.6 Individual Assessment
The nearby individuals were assessed on the following basis:
A-10
-------
1) The nearby individuals for each source category are intended to
represent an average of individuals living near each facility within the
source category. The location on the assessment grid which provides the
greatest lifetime risk (all pathways considered) was chosen for the
nearby individuals.
2) The organ dose-equivalent rates in the tables are based on the
calculated environmental concentrations by AIRDOS-EPA. For inhaled or
ingested radionuclides, the conversion factors are the 70-year values.
3) The individual is assumed to home-grow a portion of his or her
diet consistent with the type of site. Individuals living in urban areas
were assumed to consume much less home produced food than an individual
living in a rural area. We assumed that in an agriculturally
unproductive location, people would home-produce a portion of their food
comparable to residents of an urban area, and so we used the urban
fraction for such nonurban locations. The fractions of home produced
food consumed by individuals for the generic sites are shown in Table
A-2. Trial runs showed little difference between assuming that the
balance of the nearby individuals' diet comes from the assessment area or
from outside the assessment area.
Table A~2. Sources of food for the maximum individual
Food Urban/Low productivity Rural
(Sites A, Bs E-G) (Sites C & D)
Fl F2 F3 Fl F2 F3
Vegetables .076 0. .924 .700 0. .300
Meat .008 0. .992 .442 0. .558
Milk 0. 0. 1. .399 0. .601
Fl and F2 are the home-produced fractions at the individuals'
location and within the 80 km assessment area, respectively. The balance
of the diet, F3, is considered to be imported from outside the assessment
area with negligible radionuclide concentrations due to the assessed
source. Fractions are based on an analysis of household data from the
USDA 1965-1966 National Food Consumption Survey (USDA72).
A. 7
The collective assessment to the population within an 80 km radius
of the facility under consideration was performed as follows:
A-ll
-------
1) The population distribution around the generic site was based on
the 1970 census. The population was assumed to remain stationary in time,
2) Average agricultural production data for the state in which the
generic site is located were assumed for all distances greater than 500
meters from the source. For distances less than 500 meters no
agricultural production is calculated,
3) The population in the assessment area consumes food from the
assessment area to the extent that the calculated production allows. Any
additional food required is assumed to be imported without contamination
by the assessment source. Any surplus is not considered in the
assessment.
4) The collective organ dose-equivalent rates are based on the
calculated environmental concentrations. Seventy-year dose commitment
factors (as for the individual case) are used for ingestion and
inhalation. The collective dose equivalent rates in the tables can be
considered to b.e either the dose commitment rates after 100 years of
plant operation, or equivalently, the doses which will become committed
for up to 100 years from the time of release for one year of plant
operation.
A,8 AIRPOS-EPA Parameters and Input Data
Site independent parameter values'used for AIRD0S-EPA are summarized
in Table A-5. Element dependent factors (Ba81) are listed in Table A-6.
Mixing Height and_Deposition
Table A-3 summarizes the mixing heights, rainfall rates, and
scavenging coefficients used for the generic sites. A dry deposition
velocity of 0.0018 m/s was used for participates and 0.035 m/s for
reactive vapors (e.g., elemental iodine) unless otherwise indicated.
The average mixing height is the distance between the ground surface
and a stable layer of air where no further mixing occurs. This average
was computed by determining the harmonic mean of the morning mixing
height and the afternoon mixing height for the location (Ho72)» The
rainfall rate (USGS70) determines the value used for the scavenging
coefficient. Sites E through G are relatively dry locations as reflected
by the scavenging coefficients.
Meteorological Data
STAR (an acronym for JiTability Mray) meteorological data summaries
were obtained from the National Climatic Center, Ashevilles North
Carolina. Data for the station considered most representative for each
generic site were used. Generally, these data are from a nearby
A-12
-------
airport. The station used is identified by the corresponding WBAN number
In Table A-l. These data were converted to AIRDOS format wind data using
the utility program listed in Appendix A of EPA80,
Table A-3. Some site parameters used with A1RDOS-EPA
Average mixing Rainfall Scavenging
Generic height rate coefficient
site (m) (cm/y) (s~^)
Site A
Site B
Site C
Site D
Site E
Site F
Site G
1000
600
1000
600
800
700
615
102
102
142
127
20
20
27
l.OE-5
l.OE-5
1.4E-5
1.3E-5
2.0E-6
2.0E-6
2.7E-6
Dairy andBeefCattle
Dairy and beef cattle distributions are part of the AIRDOS-EPA
input. A constant cattle density is assumed except for the area closest
to the source or stack in the case of a point source, i.e., no cattle
within 500 m of the source. The cattle densities are provided by State
in Table A-4. These densities were derived from data developed by NRG
(NRC75). Milk production density in units of liters/day-square mile was
converted to number of dairy cattle /square kilometer by assuming a milk
production rate of 11.0 liters/day per dairy cow. Meat production
density in units of kilograms/day-square mile was changed to an equiva-
lent number of beef cattle/square kilometer by assuming a slaughter rate
of .00381 day~l and 200 kilograms of beef/animal slaughtered. A
180-day grazing period was assumed for dairy and beef cattle.
Ve ge tab 1 e C r o pAre a
A certain fraction of the land within 80 km of the source is used
for vegetable crop production and is assumed to be uniformly distributed
throughout the entire assessment area with the exception of the first 500
meters from the source. Information on the vegetable production density
in terms of kilograms (fresh weight)/day-square mile were obtained from
NRG data (NRC75). The vegetable crop fractions (Table A-4) by State were
obtained from the production densities by assuming a production rate of 2
kilograms (fresh weight}/year~square meter (NRC77).
A-13
-------
The population data for each generic site were generated by a
computer program, SECPOP (At74), which utilizes an edited and compressed
version of the 1970 United States Census Bureau's "Master Enumeration
District List with Coordinates" containing housing and population counts
for each census enumeration district (CE0) and the geographic coordinates
of the population eentroid for the district. In the Standard
Metropolitan Statistical Areas (SMSA) the CED is usually a "block group"
which consists of a physical city block. Outside the SMSAs the CED is an
'enumeration district," which may cover several square miles or more in a
rural area.
There are approximately 250S000 CEDs in the United States with an
average population of about 300 persons. The position of the population
centroid for each CED was marked on the district maps by the individual
census official responsible for each district and is based only on
personal judgment from inspection of the population distribution on the
map. The CED entries are sorted in ascending order by longitude on the
final data tape.
The resolution of a calculated population distribution cannot be
better than the distribution of the CEDs. Hence, in a metropolitan area
the resolution is often as small as one block, but in rural areas it may
be on the order of a mile or more.
A.9 DARTAB—Dose and Risk Tables
The intermediate output files of ingestion and inhalation intake and
ground level air and ground surface concentrations of radionuclides were
processed by DARTAB (BeSO) using dose and risk conversion factors (see
Volume I, Chapters 7 and 3) to produce the dose and risk assessments for
this report.
-------
Table A~4. Cattle densities and vegetable crop
distributions for use with AIRBOS-EPA
State
Alabama
Arizona
Arkansas
California
Colorado
Connecticut
Delaware
Florida
Georgia
Idaho
11 lino is
Indiana
Iowa
Kansas
Kentucky
Louisiana
Maine
Maryland
Massachusetts
Michigan
Minnesota
Mississippi
Missouri
Montana
Nebraska
Nevada
New Hampshire
New Jersey
New Mexico
New York
Dairy cattle
density
#/kn»2
7.02E-1
2.80E-1
5.9QE-1
2,85
3.50E-1
2.50E-1
2,72
1.37
8.63E-1
8.56E-1
2,16
2.80
3.14
8.00E-1
2.57
9.62E-1
8.G7E-1
6.11
3.13
3.51
4.88
8.7GE-1
1,89
9,27E~2
8.78S-1
5.65E-2
1.58
3.29
1.14E-1
8.56
Beef cattle
density
#/km2
1.52E+1
3.73
1.27E+1
8.81
1.13E-H
3.60
6.48
1.28E+1
1.43E+1
7.19
3.33E+1
3.34E + 1
7.40E+1
2.90E + 1
2 . 6 5E +1
1.08E + 1
7.65E-1
1.09E+1
2.90
7.90
1.85E+2
1.75E+1
3.43E+1
7.29
3.50E+1
1.84
1.40
4.25
4.13
5.83
Vegetable
crop fraction
km^/km^
4.16E-3
2.90E-3
1.46E-3
1.18E-2
1.39E-2
7.93E-3
5.85E-2
6.92E-3
2.17E-3
7.15E-2
2.80E-2
2.72E-2
2.43E-2
5.97E-2
3.98E-3
4.35E-2
S.97E-2
I.11E-2
4.96E-3
1.70E-2
3.05E-2
1.07E-3
8.14E-3
8.78E-3
2.39E-2
8.92E-3
6.69E-2
1.82E-2
1.38E-3
1.88E-2
A~15
-------
Table A-4. Cattle densities and vegetable crop
distributions for use with AIRDOS-EPA--continued
State
North Carolina
North Dakota
Ohio
Oklahoma
Oregon
Pennsylvania
Rhode Island
South Carolina
South Dakota
Tennessee
Texas
Utah
Vermont
Virginia
Washington
West Vlrgina
Wisconsin
Wyoming
Dairy cattle
density
#/km2
1.26
6.25E-1
4,56
7.13E-1
4.53E-1
6.46
2.30
7.02E-1
8.85E-1
2.00E-1
5.30E-1
4.46E-1
8.88
1.84
1.50
6.00E-1
1.43E+1
5.79E-2
Beef cattle
density
#/km2
1.02E+1
1.18E + 1
2.03E+I
2.68E + 1
4.56
9 = 63
2.50
8.87
2.32E+1
2.11E + 1
1.90E4-1
2.84
4.71
1.31E+1
5.62
6,23
1.81E+1
5.12
Vegetable
crop fraction
km^ /km^
6.32E-3
6.29E-2
1.70E-2
2.80E-2
1.59E-2
1.32E-2
4.54E-2
1.84E-3
1.20E-2
2.72E-3
5.77E-3
1.83E-3
LOSE -3
8.70E-3
5.20E-2
1.16E-3
1.78E-2
1.59E-3
A-16
-------
Table A~5. Site independent parameters used for AIRDOS-EPA
generic site, assessments
Symbolic
variable
BRTHRT
T
DDI
TSUBH1
TSUBH2
TSUBH3
TSUBH4
LAMW
TSUBE1
TSUBE2
YSUBV1
YSUBV2
FSUBP
PS UBS
De script ion
Breathing Rate (cm^/h)
Surface buildup time (days)
Activity fraction after washing
Time delay-pasture grass (h)
Time delay-stored food (h)
Time delay-leafy vegetables (h)
Time delay-produce (h)
Weathering removal rate
factor (h~l)
Exposure period-pasture (h)
Exposure period-crops or leafy
vegetables (h)
Productivity-pasture (dry
weight) (kg/m2)
Productivity-crops and leafy
vegetables (kg/ra--)
Time fraction-pasture grazing
Pasture feed fraction-while
Value
9.17E+5
3.65E+4
0,5
0.0
2.16E+3
336.
336.
2.10E-3
720.
1.44E+3
.280
.716
0.40
QSUBF
TSUBF
UV
UK
UF
UL
TSUBS
pasture grazing 0.43
Feed or forage consumption
rate (kg-dry/day) 15.6
Consumption delay time-milk (d} 2.0
Vegetable utilization rate (kg/y) 176.
Milk utilization rate (kg/y) 112.
Meat utilization rate (kg/y) 85.
Leafy vegetable utilization
rate (kg/y) 18.
Consumption time delay-meat (days) 20.
A-17
-------
Table A~5. Site independent parameters used for AIRDOS-EPA
generic site assessments (Continued)
Symbolic
variable
Description
Value
FSUBG
FSUBL
TSUBB
P
TAUBEF
MSUBB
VS UBM
Rl
R2
Produce fraction (garden of interest) 1.0
Leafy veg fraction (garden of
interest) 1.0
Soil buildup time (y) 100.
Effective surface density of soil
(kg/m2) 215.
Meat herd-slaughter rate
factor (d~l) 3.81E-3
Mass of meat of slaughter (kg) 200.
Milk production rate of cow (L/d) 11.0
Deposition interception fraction-
pasture 0.57
Deposition interception fraction-
leafy vegetables 0.20
A-18
-------
Table A~6« Element, dependent factors used in AIRDQS-EPA assessments
Element
Ac
Ac
Ag
Am
As
Ba
Be
Bi
Ce
Cm
Co
Co
Gr
Cr
Cs
Eu
Fe
Ga
La
Mn
Mo
Nb
Pa
Pb
Po
Po
Pr
Pu
P
Ra
learance
c lass
Y
W
Y
Y
W
D
W
W
Y
Y
W
Y
D
Y
D
Y
W
W
W
Y
D
W
Y
W
I)
D
W
Y
W
W
I)
Y
Y
D
W
Fl
0.10E-2
Q.1QE-2
G.5QE-1
0.10E-2
0.30E-1
0,10
0.20E-2
0.5QE-1
0.10E-3
0.10E-2
0.50E-1
0.50E-1
0,10
0.10
0.95
0.10E-3
0.10
0.10E-2
0.20E-1
0.10E-1
0.95
O.LOE-3
0.10E-3
0 . 10
0,95
0.95
0.10E-1
0.10E-2
G.30E-1
0 , 10
0.10
0.10E-3
0.30E-4
0,80
0.20
*m
(d/L)
2.0E-5
2.0E-5
3 . OE -2
3.6E-5
6 . 2E -5
3.5E-4
9.1E-7
5.QE-4
2.0E-5
2.0E-5
2.0E-3
2.0E-3
2.0E-3
2.0E-3
5.6E-3
2.0E-5
5.9E-5
5.QE-5
9 . 7E -6
2.0E-6
9 . 9E -3
2,OE-5
2.0E-5
8.4E-5
1.4E-3
3.5E-2
2.0E-2
5.0E-6
8 , 7£ -5
1 . 2E-4
1.2E-4
2.QE-5
5.3E-8
1.6E-2
5.9E-4
Ff
(d/kg)
1.6E-6
1.6E-6
1.7E-2
1.6E-6
2.0E-3
3.2E-3
l.OE-3
1.3E-2
1.2E-3
1.6E-6
1,3.6-2
1.3E-2
2.4E-3
2.4E-3
1.4E-2
4.8E-3
4.0E-2
1.4
2.6E-1
1.5E-3
7 . OE -3
2.0E-4
2 , OE -4
8.0E-4
8.0E-3
3.0E-2
2.8E-1
1.6E-6
9.1E-4
8.7E-3
8.7E-3
4.7E-3
1.9E-8
4.6E-2
5.0E-4
Biv.
l.OE-2
l.OE-2
6.0E-1
9.8E-3
3.9E-3
6.1E-2
1.7E-3
6.0E-1
2.6E-2
1.3E-3
3.7E-2
3.7E-2
2.4E-2
2.4E-2
1.4E-1
l.OE-2
9.3E-3
L.OE-3
1.5
5.2E+1
2.0E-1
4.2E-3
4.2E-3
3.9E-2
3,4
2.1E-1
3 . 8E -2
l.OE-2
1 , 4E -1
4.2E-3
4.2E-3
l.OE-2
6.7E-3
4.4E+0
l.OE-1
Biv,,
2.5E-3
2.5E-3
1 , 5E -1
1.5E-3
1.7E-2
2 , OE™ 1
4. 2E-4
1.5E-1
6.2E-3
1.7E-3
9.3E-3
9.3E-3
6.0E-3
6.0E-3
9.1E-3
2.5E-3
2.3E-3
2.5E-4
3.8E-1
1.3E + 1
5.5E-2
1.1E-3
1.1E-3
9.8E-3
2.2E-1
5.2E-2
9.4E-3
2.5E-3
4.8E-3
2.6E-4
2.6E-4
2.5E-3
1.1E-3
1.1
2.0E-2
A~19
-------
fable A-6. Element dependent factors used in AIRDOS-EPA assessments
(Continued)
Element
Rb
Ru
Ru
Sb
Sn
Sr
S
Tb
Tc
Th
Th
Tl
U
U
Y
Zn
Zr
Clearance
c lass
D
W
Y
W
W
D
D
Y
W
W
Y
W
Y
D
W
W
W
Fl
0.95
0.40E-1
0.40E-1
0.50E-1
0.50E-1
0,20
0.95
0 . 10E-3
0.80
0.10E-2
0.10E-2
0.95
0.20E-2
0.50E-1
0.10E-3
0.50
Q.20E-2
J?L)
1 . 2E -2
6.1E-7
6.1E-7
2.0E-5
1.2E-3
1.1E-3
1.6E-2
2.0E-5
9.9E-3
5.0E-6
5.0E-6
2.2E-2
1.4E-4
1.4E-4
2, OS -5
l.OE-2
8.0E-2
Ff
(d/kg)
3.1E-2
1.8E-3
1.8E-3
4.0E-3
8.0E-2
3.0E-4
l.OE-1
4.4E-3
8.7E-3
1.6E-6
1.6E-6
4.0E-2
1.6E-6
1.6E-6
4.6E-3
3.0E-2
3.4E-2
Bivl
2.5E-1
1 . 7E-1
1.7E-1
1.1E-1
2.0E-2
2.4
2.4
1 . OE-2
2.2E+2
6.3E-3
6'. 3E-3
1.0
2.1E-2
2. IE -2
1.1E-2
3.9E-1
6.8E-4
Biv2
6.3E-2
1.6E-2
1.6E-2
2.8E-2
5.0E-3
2.2E-1
5.9E-1
2.6E-3
1.1
3.5E-4
3.5E-4
2.5E-1
4.2E-3
4.2E-3
4. 3E-3
9.8E-2
1.7E-4
A-20
-------
REFERENCES
At74 Athey T. W.s R. A. Tell, and D. E. Janes, 1974, The Use of
an Automated Data Base in Population Exposure Calculations,
from Population Exposures, Health Physics Society,
CONF-74018, October 1974.
Ba81 Baes C. F, III and R. D. Sharp, A Directory of Parameters
Used in a Series of Assessment Applications of the
AIRDOS-EPA and DARTAB Computer Codes, ORNL-5710, Oak Ridge
National Laboratory, Oak Ridge, Tennessee, March 1981.
Be81 Begovich C. L., K. F, Eckerman, E.G. Schlatter, S.Y. Ohr,
and R. 0. Chester, 1981, DARTAB: A program to combine
airborne radionuclide environmental exposure data with
dosimetric and health effects data to generate tabulation
of predicted impacts. ORNL/5692, Oak Ridge National
Laboratory, Tennessee, August 1981.
EPA80 Environmental Protection Agency, Radiological Impact Caused
by Emissions of Radionuclides into Air in the United
States, EPA 520/7-79-006, EPA, Office of Radiation
Programs, Washington, D.C., December 1980.
Ho72 Bolzworth G. C., 1972, Mixing Heights, Wind Speeds, and
Potential for Urban Air Pollution Throughout the Contiguous
United States, Report AP-101, U. S. Office of Air Programs
1972.
Mo79 Moore R. E,, C. F. Baes III, L. M. McDowell-Boyer, A. P.
Watson, F. 0. Hoffman, J, C. Pleasant, C. W. Miller, 1979,
AIRDOS-EPA: A Computerized Methodology for Estimating
Environmental Concentrations and Dose to Man from Airborne
Releases of Radionuclides, EPA 520/1-79-009, EPA Office of
Radiation Programs, Washington, D.C. 20460, December 1979.
USDA72 United States Department of Agriculture, 1972, Food
Consumption of Households in the United States (Seasons and
Year 1965-1966}, Household Food Consumption Survey
1965-1966, Report No. 12, Agricultural Research Service,
USDA, Washington, DC (March 1972).
USGS70 U.S. Geological Survey, 1970, The National Atlas, U. S.
Department of the Interior, Washington, D.C.
A-21
-------
-------
APPENDIX B
R&DIONUCLIDB EMISSIONS TO AIR FROM FORMER
MANHATTAN ENGINKERING DISTRICT AND
ATOMIC ENERGY COMMISSION SITES
(FU5RAP)
-------
Page Intentionally Blank
-------
B: RADIONUCL1DE EMISSIONS TO AIR
MANHATTAN ENGINEERING DISTRICT AMD
ATOMIC ENERGY COMMISSION SITES
CFUSRAP)
CONTENTS
Page
B.I Background B-5
B.2 Current Status B-5
B.3 Potential for Airborne Releases B-13
B.4 Site Summaries B-13
B.5 Discussion B-16
TABLES
B-l Formerly Utilized Sites Remedial Action Program (FUSRAP)
Sites, March 1983 B-6
B-2 FUSRAP sites with legislative authority for remedial action B-ll
B-3 FUSRAP sites without legislative authoirty for remedial
action B-13
FIGURE
B-l Radon concentration near the tailings pile B-18
B-3
-------
Page Intentionally Blank
-------
Appendix B: RADIONUCLIDE EMISSIONS TO AIR
MANHATTAN ENGINEERING DISTRICT AMD
ATOMIC ENERGY COMMISSION SITKS
(FUSRAP)
The original program for the development and use of atomic energy,
established by the Army Corps of Engineers' Manhattan Engineering
District (MED) and continued by the Atomic Energy Commission (ABC), was
conducted under contract at Federally-, privately-, and institutionally-
owned sites. When the contract terminated, the sites were decontami-
nated according to the health and safety criteria then in effect and
were released for unrestricted use. Changing radiological criteria
prompted the ABC to re-examine the radiological status of these sites
in 1974, to determine if further remedial actions were required,
This re-examination was continued under the Energy Research and
Development Administration (ERDR) and the Department of Energy (DOE)
and was expanded to include radiological surveys of former HED/ASC
sites. When the results of several site surveys showed that remedial
actions would be necessary, the DOE initiated the Formerly Utilized
Sites Remedial Action Program (FUSRAP) to identify all former MED/ABC
sites and to resolve any site radiological problems. As of March 1983,
36 sites had been designated as FUSRAP sites. These sites, their
locations, and present owners are listed in Table B-l.
B.2 current_Status
Of the 36 FUSRAP sites, determinations that remedial actions are
required have been made for 22 sites and are pending for the remaining
14 sites. As shown in Table B-l, DOB has legal authority for carrying
out remedial actions under the provisions of the Atomic Energy Act of
1954, as amended, at only 14 of the 36 FUSRAP sites. The status of
remedial actions at these 14 sites is summarized in Table B-2. At 3 of
the 14 sites, no determination has been made that remedial actions are
required. At six sites,, some actions have been initiated. Remedial
actions have been completed at five sites,
At the 22 remaining sites (see Table B-3), the DOE's authority
extends only to characterizing the radiological status of the site,
determining the need for remedial action (completed for 11 sites), and
-------
fable B-l. Formerly Utilized Sites Remedial Action Program
(FUSRAP) Sites, March 1983
CO
Site/Location
* I. Acid/Pueblo Canyon
Los Alamos, NM
2, Albany Metallurgical Research Center
Albany, OR
* 3. Ashland Oil Co, (No. 1}
Tonawanda, NY
4, Ashland Oil Co.
-------
Table B-l. Formerly Utilized sites Remedial Action Program
(PUSRAP) Sites, March 1983 (Continued)
Site/Location
Ownership
Designated
for reaiedial
action
Authority for
remedial action
S3
*1Q. Gardiner, Inc.
Tampa, PL
11, w. R. Grace & Co.
Curtis Bay, MD
*12. Guterl Steel Corp.
Lockport, NY
13. Harshaw Chemical Co.
Cleveland, OH
14. Iowa State University
Ames, IA
*15, Kellex/Pierpoint Research Facility
Jersey City, NJ
*16, Linde Rir Products
Tonawanda, NY
17. Niagara Falls Storage Site
(Vicinity Properties)
Lewiston, NY
Gardiner, Inc. Yes
¥. R. Grace & Co. Pending
Guterl Special Steel Co., Yes
Simmons Steel Division
Harshaw Chemical Co. Pending
Iowa State University Pending
Municipality of ftmes
Delco-Levco, Yes
Pierpolnt Associates
Union carbide Corp., Yes
Linde Air Products Division
Town of Lewiston, Fort Yes
Conti Corp., S. Washuta,
Niagara Mohawk Power Co.,
the Somerset Group, Inc.,
U.S. Air Force, Services
Corporation of America
Mo
No
NO
MO
Yes
See footnote at end of table.
-------
Table B-l. Formerly Utilized Sites Remedial Action Program
(PUSRftP) Sites, March 1983 (Continued)
Site/Location
*18. Mallinckrodt, inc.
St. Louis, MO
*19. Middlesex Landfill
Middlesex, NJ
*20, Kiddlesex Sampling Plant,
fSMdlesex and Piscataway, NJ
21. Mont iceIlo (Vicinity Properties)
Mont ice Ho, UT
*22, National Guard Rrmory,
Chicago, IL
23. Olin Chemical Corp.
Joliet, IL
*24« Palos Park Forest Preserve
Cook County, IL
25, Pasadena Chemical Co,
Pasadena, TX
Ownership
Designated
for remedial
action
Mallinckrodt, inc. Yes
Borough of Middlesex, Yes
Middlesex Presbyterian
Church
U.S. Government, Yes
Multiple Private Ownership
Multiple Private Ownership Pending
State of Illinois Pending
Olin Mathieson Chemical Pending
Corporation
Cook County Forest Yes
Preserve District
Pasadena Chemical Co. Yes
Authority for
remedial action
No
Yes
Yes
Mo
NO
NO
No
*26. St. Louis Airport Storage Site
St. Louis, MO
St. Louis JVirport
Authority
Yes
No
See footnote at end of table,
-------
Table B-l. Formerly Utilized Sites Remedial Action Program
(FUSRAP) Sites, March 1983 (Continued)
Site/Location
Ownership
Designated
for remedial
action
Multiple Private Ownership Yes
Seaway Industrial Park Yes
Development Co., Inc.
U.S. Army Yes
Ms. L. Shpack Yes
Unknown Pending
Vulcan Cyclops, Inc. Pending
University of California Yes
University of Chicago Pending
Authority for
remedial action
ro
vO
27, St. Louis Airport Site
(Vicinity Properties)
St. Louis, MO
*28, Seaway Industrial Park
Tonawanda, NY
*29. Seneca Army Depot
RomuIus, NY
*30, Shpack Landfill
Norton, MA
31. Staten Island
Staten Island, NY
*32, Universal Cyclops, Inc.
Aliquippa, PA
33. University of California
Berkeley, CR
*34. University of Chicago
Chicago, IL
Yes
No
No
Yes
No
Yes
Yes
See footnote at end of table.
-------
CEJ
t-*
o
Table B-l. Formerly Utilized Sites Remedial Action program
(FUSRAP) Sites, March 1983 (Continued)
Site/Location
Ownership
Designated
for remedial
action
Authority for
remedial action
35, Ventron Corporation
Beverly, MR.
36. Watertown Arsenal
Watertown, MA
Thiokol Corporation Pending
Watertown Redevelopment Pending
Corporation
No
No
*Sites for which Radiological Survey Reports are publicly available; see References,
-------
Table B-2, FUSRAP sites with legislative authorityW for remedial action
Status of remedial action as of March 1983
Site name
and location
Determine
need and
authority
Prel Jminary
engineering
completed
Select
action
options
Design
engineering
initiated
NEPA
process
completed
Select
remedial
action
Design
engineering
completed
Remedial
action
completed
Acid/Pueblo Canyon,
Los Alamos, NH
Albany Metallurgical
Research Center,
Albany, OR
Bayo Canyon,
Los Alamos, NM
Chupadera Mesa, White Sands
Missile Range, NM
E.I. OuPont DeNemours
00 & Co., Oeepwater, N3
c- Kellex/Pierpoint Research
Facility, Jersey City, NJ
Linde Air Products,
Tonawanda, NY
Niagara Falls Storage Site
(Vicinity Properties)
(Formerly the Late Ontario
Ordnance Works)
(1) 19 acres of disposal
faciIi ty
(2) central and west ditches
(3) remaining 30 properties
See footnotes at end of table.
-------
Table B-2. FUSRAP sites with legislative authority^3' for remedial action (Continued)
OB
?
to
Site name
and location
Status of remedial actjgn_as of terch 1983 :
Determine Preliminary Select Design NEPA Select Design
need and engineering action engineering process remedial engineering
authority cosipletecl options initiated completed action completed
Middlesex Municipal X
Landfill, Middlesex, MJ
Middlesex Sampling Plant,
Hiddlesex and Piscataway, NO
(1) 33 Off-site properties X
(2) On-site X
St. Louis Airport
Storage Site,
(Vicinity Properties)
St. Louis, HO
Shpack Landfill,
Morton, HA
University of California,
Berkeley, CA
University of Chicago,
Chicago, IL
XV V V
A A A
(remedial action suspended pending site of NJ
action on selection of disposal site)
^Authorized by the Atonic Energy Act of 1954 and amendments.
Status Legend: X - Phase completed; P - Partially completed
Remedial
action
-------
Table B-3. FUSRAP sites without legislative authority^3)
for remedial action
Status of remedial action
as of March 1983
Site name and location Designated Preliminary
for remedial engineering
action completed
Ashland Oil Co. (No. 2), Tonawanda, NY
Ashland Oil Co. (No. 1), Tonawanda, NY
Clecon Metals Inc., Cleveland, OH
Conserv, Inc., Nichols, FL
Gardiner, Inc., Tampa, FL
Guterl Steel Corp.s Lockport, NY
Harshaw Chemical Co., Cleveland, OH
Iowa State University, Ames, IA
Mallinckrodt , Inc., St. Louis, MO
Monticello (Vicinity Properties), UT
National Guard Armory, Chicago, IL
01 in Chemical Co., Joliet, IL
Palos Park Forest Preserve s
Cook County, IL
Pasadena Chemical Company, TX
Seaway Industrial Park, Tonawanda, NY
Seneca Army Depot, Romulus, NY
St. Louis Airport Storage Site,
St. Louis, MO
Staten Island, NY
Universal Cyclops Inc., Aliquippa, PA
Ventron Corporation, Beverly, MA
W. R. Grace and Co., Curtis Bay, MD
Watertown Arsenal, Watertown, MA
P
X
X
X
X
X
P
P
X
P
P
P
X
X
X
X
X
P
P
P
P
P
X
P
X
P
X(b)
P
{^Radiological, surveys, determinations of need for remedial actions,
and planning for these sites were conducted under the authority
of the Atomic Energy Act of 1954, as amended. No legislative
authority exists for conducting remedial actions at these sites.
'"'Department of Array is responsible for remedial action. No further
action required under FUSRAP,
Status legend: X - Phase Completed, P- Partially Completed.
B-13
-------
planning. Completion of remedial actions at these sites will require
DOE to obtain additional legislative authority.
8• 3 Potentia 1 for Airborne Re leases
To assess the potential for airborne releases of radioactive
materials from FUSRAP sites, we have reviewed all of the Radiological
Survey Reports which are publicly available (see References). These
reports cover 22 of the 36 sites. For the sites where no Radiological
Survey Reports are available, we reviewed "A Background Report for the
Formerly Utilized Manhattan Engineering District/Atomic Energy
Commission Sites Program" (DOE/BV-0097), to determine the potential for
significant airborne releases, Although the information contained in
this document is mainly descriptive, it does not appear that any of
these sites has a greater potential for airborne release than the sites
for which Radiological Survey Reports are available?
Based on our review, eight representative sites were selected for
further study including the St. Louis storage site which appears to
have the greatest emissions of radionuclides to air. The other seven
sites were selected randomly, and indicate the range of potential
releases from FUSRAP sites. All of these sites have been designated
for remedial action.
B.4 Site Summaries
St. Louis Airport, St. Louis. MO
This 21.7 acre site adjacent to the St. Louis Airport was used to
store residues of contaminated scrap from the Mallinckrodt Chemical
Corporation's uranium-processing operation. Residues were stored in
the open, in steel drums, and in an open concrete pit. All residues
were removed from the site during 1966 and 1967.
The radiological survey of the site identified significant surface
and subsurface contamination both on- and off-site. Measurements of
external gamma radiation 1 meter above the surface ranged from near
background levels (10 yR/hr) to 330 yR/hr. The highest measurement
was off-site, and continuous exposure could result in an integrated
dose equivalent of approximately 2.9 rent/year. Radon flux measurements
averaged 6.3 pCi/m^-sec, equivalent to an annual Rn-222 source term
of approximately 17 Ci. On-site radon-222 measurements ranged from 30
to 130 fCi/L, and airborne concentrations of Ra-226, Th-230, Pb-210,
U-238, and Ac-227 near the west fence (the point of highest
concentrations), 14 fci/m3f 13 fci/in3, 30 fci/m3, 5 fCi/m3, and
1.6 fei/nr', respectively.
*This judgment does not apply to the Niagara Falls storage Site.
We are waiting for DOE Monitoring Reports on this facility, and will
update our findings as necessary when we have reviewed the data.
-------
The 10-acre site was used to dispose of 8,000 tons of residue from
ore processing operations at the Linde Air Products refinery. The
residue, containing approximately 0.54 percent uranium, was spread over
two-thirds of the site. In 1974, 6,000 cubic yards of residue were
removed to the adjacent Seaway Industrial Park (see below), and the
site developed for oil storage.
The radiological survey of the site identified extensive soil
contamination. External gamma radiation 1 meter above the surface on
the site ranges from 17 tiR/hour (or slightly above the 8-14 yR/hour
background level in the area) to 190 jjR/hour, and averaged 33
nR/hour over the entire site. Continuous exposure to the highest and
average measured gamma radiation would result in an integrated dose
equivalent of approximately 1.6 rem/year and 0.3 rem/year,
respectively. In addition, a radon flux of 7 pCi/m-^-sec was
estimated as the average for the entire 10-acre site. This would
result in an annual radon source terra of approximately 9 ci.
Bavo Canyon Area., Los Rlamps. MM
Bayo Canyon was used from 1943 through 1961 as an experimental
area for high explosives. Test assemblies of natural and depleted
uranium using lanthanum-140 as a tracer were exploded in the area,
dispersing approximately 1.3 curies of natural uranium, 1.2 curies of
depleted uranium, and between 30 and 40 curies of strontium-90 (present
as a contaminant of lanthanum-140). An additional 85 and 120 curies of
strontium-90 were deposited in waste handling facilities in the area
and some fraction migrated into the subsurface environment. The area
was decontaminated in 1963, and most of the debris was removed. The
area is currently used as a recreational area, although residential
development has been proposed.
The radiological survey of the site shows no statistically
significant difference between the airborne concentrations of Sr-90 or
uranium in the Bayo Canyon area compared with other northern New Mexico
locat ions.
Clecon Metals, Inc., Cleveland, OH
Two of the three buildings at this 3.5 acre industrial site were
used in the production of granular thorium metal for MED/ABC. The
contamination in these buildings was removed or covered due to
construction modifications after the thorium operations were ended.
The radiological survey of the site indicates that most of the
contamination is within the two buildings used for thorium processing.
However, some surface contamination is present. External gamma expo-
sure rates 1 meter from the surface average approximately 3 pR/hour
higher than the normal 10 yR/hour in the area. Continuous exposure
B-15
-------
would result in an Incremental dose above normal background of
approximately 26 rarera/year. The average concentration of thorium-232
in the soil is 6 pCi/g. Assuming 6 pCi/g fh-232, resulting in
6 PCi/m^-sec Rn~220f the annual source term for Rn-220 is estimated
to be approximately 2.7 ci,
LJ^^
The 700-acre Chambers Works site is adjacent to Deepwater, NJ,
MED/AEC operations involving uranium conversion were conducted at
three buildings at the site and a low-level radioactive burial ground
(licensed by New Jersey), Only one of the three buildings used for
MED/AEC work is still standing.
The radiological survey of the site identified some surface
contamination (primarily next to the remaining processing building),
but the primary cause for remedial action is contamination of the
building itself. The highest external gamma radiation level 1 meter
above the surface was 23 pR/hour, with most measurements in the range
of 3-6 pR/hour. Continuous exposure at the highest exposure rate
would result in an integrated dose equivalent of approximately
0.2 rera/year. Radon daughter concentrations in air ranged from 0.0001
to 0.0006 WL.
!JMl£sex_J^^
MED/ABC operations involving the sampling, weighing, assaying, and
storing of uranium and thorium ores were conducted at six buildings on
this 9.6 acre site.
The radiological survey of the Middlesex Sampling Plant, identified
extensive soil contamination and elevated external gamma exposure rates
and radon and radon daughter concentrations. External gamma readings
1 meter above the surface ranged from 22 pR/hour to 147 pR/hour.
The highest measurements were made both near the center of the site and
along the site boundary. Continuous exposure at the maximum rate could
result in an integrated dose of approximately 1.3 rein/year. The
average radon emanation rate for the site was 3.2 pci./m2-sec, or
approximately 4 ci/year,
Off-site measurements were also made at the facility, and indicate
widespread contamination beyond the site. External gamma levels as
high as 235 yR/hour were measured off-site, and radon daughter
concentrations ranged from 0.004 to 0,014 WL in off-site residences and
commercial buildings,
Seaway _ Industrial Pa^k,-iiiTon.awand_a,__MY
The site covers approximately 100 acres, of which 13 acres
adjacent to the Ashland Oil Company were used to receive approximately
6,000 cubic yards of uranium-processing residue.
B-16
-------
The radiological survey identified significant surface
contamination in the three areas where residues from the Ashland Oil
property were dumped. External gamma levels as high as 80 pR/hour
were measured; continuous exposure could result in an integrated dose
equivalent of approximately 0.7 rem/year. The radon emanation rate
from the site Is estimated at 5 pci/m^-sec, equivalent to an annual
release of about 8 Ci of Rn-222.
Seneca flrmy Depot, Romulus. WY
Eleven munitions bunkers at the facility were used to store
pitchblende ore. When MED/ftEC activities terminated, the bunkers
reverted to use as munitions bunkers.
A radiological survey of the site indicates that significant
contamination of the bunkers occurred. However, this contamination is
limited to the bunkers themselves and the soil immediately surrounding
the entrances. Most of the measurements of soil were at background
levels, and it does not appear that this facility has any significant
potential for airborne contamination or direct gamma irradiation
outside the bunkers.
B.5 Discussion
It is reasonable to assume that the most significant airborne
emission from a typical FUSRAP site during normal conditions (not
during decommissioning operations) is that of radon. To estimate radon
concentrations from the reported emission rates and site areas, we used
Figure B-l. This figure presents radon concentrations in pCi/liter as
a function of distance from the center of a tailings pile, for various
pile sizes and a fixed radon emission rate of 280 pCi/m^-sec. The
figure suggests that the radon concentration at the fencepost is rather
insensitive to pile size.
For the above eight sites, on-site radon concentrations in the
range of 0.1 to 0.2 pCi/liter are estimated, with fencepost concen-
trations in the range of 0.025 to 0.05 pel/liter. These radon con-
centrations translate into radon daughter levels of 0.001 to 0.002 WL
on-slte, and 2.5X10"4 to 5.0X1Q"4 WL at the fencepost. The levels
at the fencepost are in the range of 0.008 to 0.017 of the 10 CFR 20
MFC (3 pci/liter). The estimated lifetime risk of fatal cancer at
the fencepost to the nearby individuals is in the range of 3X10"4 to
6X10"4.
B-17
-------
20
80 ha
10-
<
-------
REFERENCES
1. "A Background Report for the Formerly Utilized Manhattan
Engineering District/Atomic Energy commission sites Program," U.S.
Department of Energy, September 1980.
2, "A Report to Congress to Accompany the Proposed Residual
Radioactive Material Control Act." Draft Report, U.S. Department
of Energy, ORNL/Sub-80/13829/1, June 1980.
3. "Formerly Utilized MED/AEG sites Remedial-Action Program,
Radiological Survey of Kent Chemical Laboratory, The University of
Chicago, Chicago, Illinois, September 7-13, 1977, Final Report,"
U.S. Department of Energy, DOE/EV-0005/25, May 1982.
4. "Formerly Utilized WED/ABC Sites Remedial-Action Program,
Radiological Survey of Ryerson Physical Laboratory, The'University
of Chicago, Chicago, Illinois, September 11-25, 1976, Final
Report," U.S. Department of Energy, DOE/EV-0005/23, May 1982.
5, "Formerly Utilized MED/AEC Sites Remedial-Action Program,
Radiological Survey of Site A, Palos Park Forest Preserve,
Chicago, Illinois, Final Report," U.S. Department of Energy,
DOE/EV-0005/7, April 1978.
6. "Formerly Utilized MBD/REC Sites Remedial-Action Program,
Radiological Survey of the fishland Oil Company, (Former Haist
Property), Tonawanda, Mew York, Final Report," U.S. Department of
Energy, DQE/EV-GGQ5/4, May 1978.
7. "Formerly Utilized MED/AEC Sites Remedial-Action Program,
Radiological Survey of the Bayo Canyon, Los Alamos, Mew Mexico,
Final Report," U.S. Department of Energy, DOE/BV-0005/15, June
1979.
8. "Formerly Utilized MED/AEC Sites Remedial-fiction Program,
Radiological Survey of the Building Elite 421, United States
tfatertown Arsenal, Watertown, MA, Final Report," U.S. Department
of Energy, DOE/EV-OQ05/19, February 1980.
9. "Formerly Utilized MED/AEC Sites Remedial-Action Program,
Radiological Survey of the E.I. DuPont DeNeroours and Co.,
Deepwater, New Jersey, Final Report," U.S. Department of Energy,
DOE/EV-0005/8, December 1978.
10. "Formerly Utilized MED/REC Sites Remedial-Action Program,
Radiological Survey of the Former GSA 39th Street Warehouse,
1716 Pershing Road, Chicago. Illinois, Final Report," U.S.
Department, of Energy, DOE/EV-0005/9, January 1978,
3-19
-------
REFERENCES
(Continued)
11. "Formerly Utilized MED/AEC Sites Remedial-Retion Program,
Radiological Survey of the Former Horizons Inc., Metal Handling
Facility, Cleveland, Ohio, Final Report," U.S. Department of
Energy, DOE/EV-0005/10, February 1978.
12. "Formerly Utilized MED/AEC Sites Remedial-Action Program,
Radiological Survey of the Former Linde Uranium Refinery,
Tonawanda, New York, Final Report," U.S. Department of Energy,
DOE/EV-OOQ5/5, May 1978.
13. "Formerly Utilized MED/AEC Sites Remedial-Action Program,
Radiological Survey of the Former Simonds Saw and Steel Co.,
Lockport, Mew York, Final Report," U.S. Department of Energy,
DOE/EV-0005/17, November 1979.
14. "Formerly Utilized MED/ABC Sites Remedial-Action Program,
Radiological Survey of the Former Virginia-Carolina chemical
Corporation Uranium Recovery Pilot Plant, Nichols, Florida, Final
Report," U.S. Department of Energy, DOE/EV-0005/18, January 1980.
15. "Formerly Utilized MED/AEC Sites Remedial-Action Program,
Radiological Survey of the George Herbert Jones Chemical
Laboratory, The University of Chicago, Chicago, Illinois, June
13-17, 1977, Final Report," U.S. Department of Energy,
DQE/EV-Q005/26, May 1982.
16. "Formerly Utilized MED/AEC sites Remedial-Action Program,
Radiological Survey of the Middlesex Municipal Landfill,
Middlesex, New Jersey, Final Report," U.S. Department of Energy,
DOE/EV-0005/20, April 1980.
17. "Formerly Utilized MED/AEC Sites Remedial-Action Program,
Radiological Survey of the Middlesex Sampling Plant, Middlesex,
New Jersey, Final Report," U.S. Department of Energy,
DOE/EV-OOQ5/1, November 1977.
18. "Formerly Utilized MED/AEC Sites Remedial-Action Program,
Radiological Survey of the Museum of Science and Industry,
57th Street and Lake Shore Drive, Chicago, Illinois, Final
Report," U.S. Department of Energy, DOE/EV-0005/13, February 1979.
19. "Formerly Utilized MSD/AEC Sites Remedial-Action Program,
Radiological Survey of the Seaway Industrial Park, Tonawanda,
New York, Final Report," U.S. Department of Energy, DOE/EV-0005/6,
May 1978.
B-2Q
-------
REFERENCES
(Continued)
20. "Formerly Utilized MED/R.BC Sites Remedial-Act ion Program,
Radiological Survey of the Seneca Army Depot, Romulus, New York,
Final Report," U.S. Department of Energy, DOE/EV-0005/11, February
1979.
21. "Formerly Utilized MED/AEC Sites Remedial-Action Program,
Radiological Survey of the Site of a Former Radioactive Liquid
Waste Treatment Plant (TA-45) and the Effluent Receiving Areas of
Acid, Pueblo, and Los Alamos Canyons, Los Alamos, New Mexico,
Final Report," U.S. Department of Energy, DOS/EV-0005/30, Hay 1981,
22. "Formerly Utilized MED/AEC Sites Remedial-Action Program,
Radiological Survey of the St. Louis Airport Storage Site,
St. Louis, Missouri, Final Report," U.S. Department of Energy,
DOE/EV-0005/16, September 1979.
23. "Formerly Utilized MED/AEC Sites Remedial-Action Program,
Radiological Survey of the Universal Cyclops Inc. Titusville
Plant, (Formerly Vulcan Crucible steel Company) Aliquippa,
Pennsylvania, May 2-8, 1978, Final Report," U.S. Department of
Energy, DOE/EV-0005/33, May 1982.
24. "Formerly Utilized KED/AEC Sites Remedial-Action Program,
Radiological Survey of the West Stands, New Chemistry Lab and
Annex, and Ricketts Laboratory, The University of Chicago,
Chicago, Illinois, August 31-September 2, 1977, Final Report,"
U.S. Department of Energy, DOE/EV-0005/34, May 1982.
25. "Radiological Survey of Properties in the Middlesex, New Jersey,
Area, Supplement, Final Report," U.S. Department of Energy,
DOE/EV-0005/1, March 1981.
26. "Radiological Survey of the Former Kellex Research Facility,
Jersey city, New Jersey, Final Report," U.S. Department of Energy,
DOE/EV-0005/29, February 1982.
27. "Radiological Survey of the Former Uranium Recovery Pilot and
Process Sites, Gardiner, Incorporated, Tampa, Florida, Final
Report," U.S. Department of Energy, DOS/EV-0005/21, March 1981,
28. "Radiological Survey of the Mallinckrodt Chemical Works,
St. Louis, Missouri, Final Report," U.S. Department of Energy,
DOE/EV-0005/27, December 1981.
29. "Radiological Survey of the Shpack Landfill, Norton,
Massachusetts, Final Report," U.S. Department of Energy,
DOE/EV-0005/31, December 1981.
B-21
-------
REFERENCES
(Continued)
30. "Draft Environmental Impact Statement for Standards for the Control
of Byproduct Materials from Uranium Ore Processing (40 CFR 192),"
U.S. Environmental Protection Agency, EPA 520/1-82-022, March 1983.
B-22
-------
APPENDIX C
RADON EMISSIONS FROM DEPARTMENT OF ENERGY AND
NUCLEAR REGULATORY COMMISSION LICENSED FACILITIES
-------
Page Intentionally Blank
-------
APPENDIX C: RADON EMISSIONS
OF AND NUCLF.AR REGULATORY
COMMISSION LICENSED FACILITIES
CONTENTS
Page
C.I DOE Facilities C-5
DOE References C~2Q
C.2 Nuclear Regulatory Commission Source Material Licensees C-21
NEC References C-29
TABLES
C-l ^2%adon concentrations (pCi/1) at the Niagara Falls
storage site C-ll
C-2 Surface area, volume, and content of the Weldon Spring
Raffinate Pits C-13
C-3 Radioactive wastes stored in Weldon Spring Quarry C-15
C-4 Radon concentrations at the Weldon Spring site, 1982 c-56
FIGURES
C-l Feed Materials Production Center Environmental Features c-7
C-2 Radioactive waste storage locations and fencepost radon
monitors C-9
C-3 Weldon spring Raffinate Pits area C-12
C-4 Weldon Spring Quarry site C-17
C-5 The Middlesex Sampling Plant site C-18
C-6 Fansteel Metals Plant site C-22
C-7 Molycorp Plant site C-24
C-8 Stepan Chemical plant site c~25
C-9 Diagram of the Kerr-McGee facility C-27
C-3
-------
Page Intentionally Blank
-------
Appendix C: RADON EMISSIONS FROM DEPARTMENT
OF ENERGY- AND NUCLEAR REGULATORY
COMMISSION-LICENSED FACILITIES
This report presents information on radon emissions from
Department of Energy (DOE) and Nuclear Regulatory Commission (NRG)
licensed facilities.
C.1 DOEFacilities
To determine which DOE sites have radon emissions, we reviewed
environmental monitoring, radiological survey, hazard characterization,
engineering evaluation, and environmental assessment reports prepared
for DOE facilities. Our review of these sources identified four sites
where uranium residues and wastes are stored or where previous
operations involving uranium and thorium resulted in significant
contamination of soils.* Releases of "^radon from these sites are
found to be large enough to cause radon concentrations at the site
boundaries that are detectable in the presence of the naturally
occurring radon,**
Identified as having potentially significant radon releases are
the following five sites: (1) Feed Materials Production Center (FMPC),
Fernald, OH; (2) Niagara Falls Storage Site (NFSS), Lewiston, NY;
(3) Weldon Spring Site (WSS), Weldon Spring, MO; (4) Middlesex Sampling
Plant (MSP), Middlesex, NJ; and (5) Monticello Uranium Mill Tailings
Pile (MUMT), Monticello, Utah. Brief descriptions of each of these
sites, the source of the radon emissions3 and the approximate amounts
of radon emissions are presented below.
The Feed MaEerialsProduct ion Center
The FMPC, near Pernald, OH, is a prime contractor site operated by
National Lead of Ohio (NLO) for the DOE, The FMPC produces purified
* Once our literature review was completed, we verified the
comprehensiveness of our findings during conversations with
cognizant DOE personnel. We believe that the sites covered in
this report are the only DOE facilities where radon emissions are
large enough to be of concern.
** The source term at the Weldon Spring Site also includes 220rac|oll
from the thorium wastes at the sites.
C-5
-------
uranium metal and components for use at other DOE facilities. Feed
materials include ore concentrates, recycled uranium from spent reactor
fuel, and various uranium compounds. Thorium can also be processed at
the site. Only minor amounts of radon are released from the production
operations conducted at the site. The primary source of radon
emissions at the FMPC is pitchblende residues stored in two concrete
storage tanks. As shown in Figure C-l, the storage tanks are located
on the western portion of the site, south of the chemical waste pits
and approximately 325 meters from the western site boundary.
The pitchblende residues were received from the Mallinckrodt
Uranium Refinery in St. Louis, MO, during the period that the
Mallinckrodt plant was operated for the Atomic Energy Commission
(AEC). Until June 1983, the residues were owned by AFRIMET (the U.S.
subsidiary of the Belgian firm that originally supplied the ores) and
stored under a lease storage agreement with the DOE. Upon expiration
of the agreement, AFRlMBT paid a reported fee of eight million dollars
and transferred ownership of the residues (and additional residues
stored at the NFSS, see below) to the United States (St83).
The residues are reported to have a radium concentration of
0.2 ppm, equivalent to about 200,000 pCi/g 226Ra. The 8,790 metric
tonnes of residue contain almost 1,760 curies of radium. Residues are
stored in two concrete tanks. Earthen berms have recently been erected
around the tanks to reduce gamma exposure. PMPC is awaiting the result
of an engineering analysis before placing earthen covers on top of the
concrete covers of the tanks (St83). The placement of earthern covers
on the tanks could result in lower radon emissions as well as reduced
gamma exposures .
No measurements of current emission rates of radon- 222 on these
tanks are available. However, data from the 1981 monitoring report
(NL082), show average radon concentrations at the site boundaries
ranging from 0.28 to 0.70 pci/l. These data are presented below. The
locations of the monitors are shown in Figure C-l.
concentrations in Air
at the FMPC Boundary, 1981
Location Number ____ KaQ3§ ___
of of Maximum Minimum Average
..... Monitor __ ___S§SEl§s ______ B£i/l ______ pCi/ 1 ___ pjgi/1
BS1 4 0.94 0.11 0.58
BS2 4 1.35 0.17 0.61
BS3 3 0.60 0.13 0.42
BS4 4 0.66 0.05 0.34
BS5 3 0.40 0.08 0.28
BS6 4 0.80 0.34 0.57
BS7 3 1.07 0.30 0.70
C-6
-------
Figure C-l
MATERIALS PRODUCTION CENTER
ENVIRONMENTAL FEATURES
BOUNDARY AIR SAMPLING STATIONS
SCAtE - !" = 1380'
C-7
-------
Data frost an off-site monitor located approximately 13 kilometers
east-northeast of the site showed an average "2^ concentration of
0.67 pci/l, while a single measurement at a location eight kilometers
west-northwest indicated 0.36 pel/I.
The Niagara Falls Storage site
The NFSS in Lewiston, NY, is a DOE surplus facility, operated by
Bechtel National, Inc. The 77-hectare site is part of the former Lake
Ontario Ordnance Works, and is used solely for the storage of uranium
and pitchblende residues. The residues are stored in six buildings
that were originally part of the facility's water treatment plant and
in a spoils pile north of Building 411 (see Figure c-2). The major
residues stored at the NFSS are summarized below:
Major Pitchblende Residues Stored
at the DDE-Niagara Palls Storage Site
Residue
I.D.
Storage
Location
Weight
Metric
Tonnes
Volume
m3
Surface
Area, m2
226Radiunt
Content
;-65
,-30
,-50
'-32
;ands
Bldg. 434
Bldg. 411
Bldgs. 413-414
Recarb. Pit
Bldg. 410
Spoil Pile, N
of Bldg, 411
3,530
7 , 460
1,700
130
2
7,470(b)
3,080
6,020
1,624
110-336
117
1.860U)
562
unknown
175 unknown
7,084(b) 37,373
200 ppb
-10 ppb
-10 ppb
unknown
unknown
~3 ppb
Source: Ba81
(a) these residues are partially covered by water.
(b) approximate weight and volume at time of emplacement; con-
taminated material includes ~11,340 m^ of overburden and
~35,QQQ m3 of contaminated soil. Unknown quantities of
wastes have been added to the pile during remedial actions at
the NFSS.
As noted, the residue storage buildings at the NFSS were originally
part of the facility's water treatment plant. The K-65 residues are
stored in Building 434 (see Figure C-2), which is the old water header
tank for the system.. The tank is a concrete silo, 50 meters tall. The
top loading port of the silo was capped and sealed during the fall of
-------
DOE-NFSS FENCELINE
o
Figure C~2
RADIOACTIVE WASTE
STORAGE LOCATIONS AND
FENCEPOST RADON MONITORS
,_E—K_s— n__)|— |_._|i—»—»,— «
i 34 i|
434
DOE-NIAGARA FALLS STORAGE SITE
LOCATION MATERIAL
BiDQ.410
411
411
414
434
MIDDLESEX SAND STORAGE
(flECARB I»IT> F-33
L-30 RESiOUi
L-50 •
K-65
If PlalcMt R
-------
1980. The other residue storage buildings are isolated from the 434
silo, on the southwest section of the site. Buildings 413-414 are also
water storage tanks, approximately 19 meters in diameter. Buildings
410, 411, and the recarbonation pit are located adjacent to the 413-414
storage tanks. The R-10 spoils pile is north of Building 411. The
spoils pile originally contained the R-10 wastes, but contaminated soil
and materials from on-slte and off-site cleanup activities have also
been placed on the pile.
Radon monitoring at the NFSS during 1980 and 1981 showed radon
concentration at the site boundary west of the R-10 spoils pile in
excess of the DOE standard of 3,0 pci/l. To reduce exposures, a new
fenceline was established 145 meters west of the former western
exclusion boundary and remedial actions were initiated to reduce radon
emissions from the site. Much of the cleanup, which is scheduled for
completion during 1985, centers on cutting and diking the R-1Q spoils
pile, Additional effort is being placed on sealing buildings and
cleaning up contaminated portions of the site (Ba84). The effective-
ness of these activities can be partially seen by comparing the 1981
and 1982 radon concentrations at the site boundary, Annual average
concentrations reported in the 1981 and 1982 Environmental Monitoring
Reports (Be82 and Be83a) are presented in Table c-1. Figure C-2 shows
the monitoring locations corresponding to the monitor ID'S given in the
table. Radon monitoring results for 1983 should be available by May of
1984, The 1983 data should confirm or deny the effectiveness of the
remedial actions that have been taken at the NFSS.
The We 1 don sjgr InejL _S 1 te
The WSS, near Weldon Spring, MO, is a DOE surplus facility
operated by Bechtel National, Inc. Like the NFSS, it is used for the
storage of uranium and thorium wastes. The site consists of two
separate properties: the 2l-hectare Raffinate Pits site; and the
3.6-hectare Quarry site, located about six kilometers southwest of the
Raffinate Pits area,
The Raffinate Pits area (see Figure c-3) is a remnant of the
tfeldon Spring chemical Plant. During the period that the chemical
plant was operated for the Atomic Energy Commission, the four raffinate
pits received residues and waste streams from the uranium and thorium
processes conducted at the facility. Pits one and two contain
neutralized raffinates from uranium refining operations and washed slag
residues from uranium metal production operations. Pits 3 and 4 contain
uranium wastes similar to those contained in Pits 1 and 2. in addition,
they contain thorium contaminated raffinate solids from processing
thorium recycle materials. During decontamination of the chemical
Plant, drummed wastes and contaminated rubble were disposed of in Pit 4.
The surface areas, volumes, and contents of the pits are summarized in
Table c-2. Surface water (varying in depth with the seasons) always
C-iO
-------
Table C-l, '^Radon concentrations (pci/1)
at the Niagara Palls storage site
Monitor
I.D.
01
02
03
04
05
06
07
08
09
10
11
12
13
14
15
Average
1981(a)
0.91
0.32
0.30
0.31
0.30
0.48
1.33
4.06
4.82
4.75
1.40
1.10
NR
MR
NR
Average
1982(b,c)
1.15
NR
0.60
0.71
0.62
0.65
1.02
2.32
2.97
1.93
0.89
0.83
0.88
0.68
0.76
Sources: Be82 and Be83a
(a) Measurements made by Mound Laboratory.
(b) Measurements made by Bechtel National, inc.
(c) According to Be82, the monitors used by
Bechtel average approximately 25 percent
higher than the monitors used by Mound.
C-ll
-------
ARMY FENCE LtNE
B'igure C-3
Weldon Spring Raffinate Pits Area
-------
Table e~2. surface area, volume, and content of the
Weldon Spring Raffinate Pits
Pit
1
2
3
4
TOTALS
Constructed
1958
1958
1959
1964
Surface
area
(acres)
1.2
1.2
8.4
15.0
25.8
Total pit
volume
(yd3)
18,500
18,500
166,700
444,400
648,100
Total
waste
volume
(yd3)
17,400
17,400
129,600
55,600
220,000
Percent
filled
94
94
78
12
Total
uranium
content
(kg)
9,100
9,100
91,000
27,600
136,800
Total
thorium
content
(kg)
...
—
500
63,600
64,100
Source: 8e83b
C-13
-------
covers the residues in Pits 3 and 4. Pits 1 and 2 are usually covered
by water as well, but evaporation during the months can leave
the residues exposed,
The Quarry site (see Figure C-4), located about six kilometers
southwest of the Raffinate Pits area, was initially used by the U.S.
Army to dispose of TNT-contaminated rubble from the Weldon Spring
Ordnance Works. The quarry was first used to dispose of radioactive
wastes in 1959, when the ABC deposited thorium residues in drums.
During 1963 and 1964, approximately 32,000 re3 of uranium- and
radium-contaminated building rubble, process equipment, and
contaminated soil generated during the demolition of the Destrehan
Street Feed Plant in St. Louis, were dumped in the quarry. In 1966,
additional drummed and uncontained thorium residues were deposited when
process equipment was removed from the Weldon Spring chemical Plant.
Additional TNT-contaminated stone and earth, disposed of later in 1966
by the Army, covers these thorium residues. The final deposits to the
quarry were made in 1968 and 1969, when the Array's decontamination of
the Chemical Plant generated approximately 4,600 ra3 of contaminated
equipment and rubble. Table C-3 summarizes the radioactive wastes
stored in the quarry.
Environmental monitoring in the vicinity of the two disposal areas
Includes a network of 15 radon monitors. Table C-4 summarizes the
results of the WSS radon monitoring network during the period December
1981 - September 1982, The sampling locations of the monitors at the
Raffinate Pits and the Quarry are shown in Figures C-3 and C-4,
respectively. The off-site monitors are located north of the Raffinate
Pits area. The results presented in Table C-4 are for total radon,
including background.
The Middlesex SamplingPlant
The MSP, Middlesex, MJ, was used by the Manhattan Engineering
District and the Atomic Energy Commission between 1S43 and 1967, for
sampling, weighing, assaying, and storing uranium and thorium ores.
After termination of operations at the site in 1967, it was decontami-
nated and released to the U.S. Marine Corp for use as a training
center. Radiological surveys of the site and nearby private properties
discovered widespread contamination from windblown materials and use of
material from the site as fill. The DOE took responsibility for the
site and its cleanup. The cleanup, which was completed in 1982,
consisted of recovering contaminated soils from off-site properties and
removing contaminated soil areas from the site. All materials were
consolidated in a storage pile on the southern portion of the site (see
Figure C~5).
The temporary storage pile at the site is approximately 91 meters
by 121 meters and 1,7 meters high. More than 31,000 metric tonnes of
contaminated soil are contained in the pile. The average radium
C-14
-------
Table C" 3. Radioactive wastes stored in Weldon Spring Quarry
Date
deposited
Volume
Radioactive
materials
(kg)
Comments
3,8 percent 1959
thorium residues
185 4,500 Drummed residues; volume
estimated; most of the
residues below quarry
water; principal source
of radioactivity:
radium- 228.
Destrehan Street 1963 -
Plant demolition 1964
rubble
50,000
Contaminated equipment,
building rubble, estimate
of uranium and thorium
content not available;
principal source of
radioactivity:
radium-226.
3 percent 1966
thorium residues
555 11,800 Drummed residues; volume
estimated; stored above
water level; principal
source of radioactivity:
radium 228.
tfeldon Spring
Chemical Plant
rubble
1968
1969
5,555
Contaminated equipment,
building rubble; uranium
and thorium content and
radioactivity not avail-
able; principal sources
of radioactivity:
radium-226 and
radium- 228.
TOTALS:
56,295
16,300
C-15
-------
Table C~4. Radon concentrations at the
Weldon Spring site, 1982
December 1981- April 1982-
Sampling March 1982 September 1982 Average
location^ (pci/l) (pCi/1) (pCi/1)
R-l
R-2
R- 3
R-4
R-5
R--6
R-7
R-8
R-9
R-10
R-ll
R- 1.2
R-l 3
R-l 4
R- 15
0.58
0.35
0.27
0.30
0.84
0.40
0.48
0.86
1.07
0.30
0,51
0.12
0.25
0,23
0.15
0,53
0.55
0.26
0.16
0.24
0,32
1.03
0.92
1.55
0,52
0.47
0,13
0.30
0.18
0.41
0,56
0.45
0.27
0.23
0.54
0.36
0.76
0.89
1.31
0.41
0.49
0.13
0.28
0.21
0.28
Source: Be83b
locations R--1 through R-5 are at the boundary of the
Raffinate Pits area, R-6 through R-ll are at the boundary of
the Quarry area, and R- 12 through R-15 are off- site, north of
the Raffinate Pits area.
C-16
-------
*"**""? Upper
I Gflte
TLD (T) WD
0 OO
Figure C-4
Weidon Spring Quarry site
-------
o
J-—I
CO
-------
concentration is estimated to be 79 pCi/g, so that there are about 2,5
curies of 226ra(j£um £n ^le pi_ie. xhe pile is covered with a hyplon
cover, which serves both to stabilize the pile and reduce the radon
£lux from the wastes. The radon flux from the pile, with cover
installed, is estimated to be 8«4 pCi/m^-sec (Fo79).
No monitoring data for the MSP were found. Given the proximity of
the waste pile to the site boundary, and the estimated radon flux from
the pile5 it is possible that radon concentrations exceed background at
the site boundaries. Based on calculated concentrations presented in
the environmental statement for inactive mill tailings sites (EPA82),
we estimate that boundary concentrations at the MSP coula be as high as
0.5 - 0.7 pCi/1.
The Monticello Uranium Mill Tailings Pile
The Monticello Uranium Mill Tailings Pile (MUMI) is located at
Monticello, Utah, and has been inactive since 1960. About 900,000 tons
of uranium mill tailings were impounded in four separate areas covering
about 40 acres total. The mill was purchased by the Federal Government
in 1948 and operated by the AEC to recover uranium from 1949 to January
1960 when it was permanently shutdown. The Government owns the
tailings site. In addition, some offsite contaminated properties at
Monticello are included under DOE's FUSRAP program (see Appendix B).
Uranium ore was processed by both acid and carbonate leaching and thus
the tailings exhibit properties of both of these processes (Ab83,
AEC63, AEC66, BFEC76).
The tailings were stabilized in 1961 by grading and leveling the
tailings and the dikes made of tailings. The tailings were then
covered with about one foot of pit run gravel and dirt, folloxved by one
foot of top soil which was seeded with local vegetation (AEC63).
Further demolition and decontamination activities were conducted in
1974 and 1975 to reduce radiation levels at the site and improve the
esthetic quality (BFEC76).
Radiation measurements at the site were primarily for external
gamma radiation. These levels were reduced by stabilization to a range
of 2 to 3 about background levels. Radon emission measurements ranged
from 175 to 675 pCi/m2-see for the 4 areas covered by tailings
(Ab83). EPA estimated the total radon emissions from the pile using
methods described in EPA83. It was assumed the ore processed at the
site averaged 0,2 percent uranium, which was typical for ore processing
during the 1950"s. Thus, the radium content is 560 pCi/g tailings.
For the 40-acre site with 2 feet of cover materials, the annual
emission of radon is about 2800 Ci. The cover material is not
effective in retaining radon, according to an analysis by Rogers (Ro81).
C-19
-------
DOE REFERENCES
Ab83 Abramiuk I. N., et al., Monticello Remedial Action Project
Site Analysis Report, Grand Junction Operations, GJ-10(83),
Draft, November 1983.
AEC63 U.S. Atomic Energy Commission, Erosion Control, Uranium Mill
Tailings Project, Monticello, Utah. Grand Junction Office,
December 20S 1963.
AEC66 U.S. Atomic Energy Commission, Supplement to the Report of the
Monticello Mill Tailings Erosion Control Project, Monticello,
Utah. Grand Junction Office, Supplement to RMO-3005,
April 20, 1966.
Ba81 Battelle Columbus Laboratories, A Comprehensive
Characterization and Hazard Assessment of the DDE-Niagara
Falls Storage Site, BMI-2074 REV., Columbus, OH, June 1981.
Ba84 Telephone conversation with Mr. J. Baublatz, U.S. DOE, Surplus
Facilities Management Office, January 1984.
Be82 Bechtel National, Inc., Niagara Falls Storage Site (NFSS):
Environmental Monitoring Report, Calendar Year 1981,
10-05-202-001, Oak Ridge, TN, May 1982.
Be83a Bechtel National, Inc., Niagara Falls Storage Site (NFSS):
Environmental Monitoring Report, Calendar Year 1982,
10-05-202-002, Oak Ridge, TN, May 1983.
Be83b Bechtel National, Inc., Weldon Spring Site (WSS):
Environmental Monitoring Report, Calendar Year 1982,
10-05-201-002, Oak Ridge, TN, June 1983.
BFEC76 Bendix Field Engineering Corporation, Uranium Ore Stockpile
Site Decontamination and Mill Site Foundation Removal,
Monticello, Utah. BFEC-1976-7, June 1976.
EPA82 U.S. Environmental Protection Agency, Final Environmental
Impact Statement for Remedial Action Standards for Inactive
Uranium Processing Sites (40 CFR 192), EPA 520/4-82-013, Vol.
1, October 1982.
EPA83 U.S. Environmental Protection Agency, Final Environmental
Impact Statement for Standards for the Control of Byproduct
Materials from Uranium Ore Processing (40 CFR 192), EPA
520/1-83-008-1, Vol. 1, September 1983.
C-20
-------
DOE REFERENCES (Continued)
Fo79 Ford, Bacon and Davis Utah, Inc., Environmental Analysis of
the Former Middlesex Sampling Plant and Associated Properties,
Middlesex, New Jersey, FBDU 230-005, Salt Lake City, UT, April
1979.
NL082
National Lead of Ohio, Inc., Feed Materials Production
Center: Environmental Monitoring Annual Report for 1981,
NLCO-1180, Cincinnati, OH, May 1981.
Ro81 Rogers V. C. and G. M. Sandquist, Long- Term Integrity of
Uranium Mill Tailings Covers, Report to the Nuclear Regulatory
Commission, RAE-21-1 (Rev. 1), August 1981,
St83 Telephone Conversation with Mr. S, Stief, Safety Division, Oak
Ridge National Laboratory, December 1983.
C-21
-------
C,2
Commission Source Material Licensees
Facilities that could have potentially significant radon emissions
are those which process material containing greater than 0.05 percent
by weight of uranium or thorium (source material). Such facilities are
required to be licensed by the Nuclear Regulatory Commission. The NRC
has licensed more than five hundred facilities to possess and use
source material. We relied on information provided by personnel in the
NRC's Material Licensing Branch to identify facilities with potentially
significant radon emissions. Listed below are the six facilities so
provided.
Facility
Fanstee1, Inc.
Muskogee, Oklahoma
Molycorp
York, Pennsylvania
Stepan Chemical
Maywood, New Jersey
vistron Corp.
Lima, Ohio
Licensed Amount of
Sour ce Ma t e r ia 1
30 MT 0.1% U
67 MT 0.22% Th
45 MT Natural Th
0.1 MT Natural U
9500 yd3 0.1% Th
8600 yd3 0.1% Th
15 MT UsOe plus
catalysts containing
50 MT U
Kerr-McGee
Rare Earths Facility
West Chicago, Illinois
Mallinckrodt Co.
St. Louis, Missouri
1400 MT Th02
20 MT UaOe
27,1 MT U in Natural and
Synthetic Ores
30 MT Th in Natural and
Synthetic Ores
The dockets for each of these facilities were examined. However,
only a limited amount of information on radon emissions from these
sites was found. Each is described below.
Fansteel, Inc.
The Fansteel Metals Plant is on a 110-acre site near Muskogee,
Oklahoma. Raw materials are processed to extract tantalum and
columbium, and the liquid residues containing uranium and thorium are
pumped to settling ponds where the solids settle out and the liquid is
processed and disposed of. The site layout is shown in Figure C-6.
There is no scale shown on Figure C-6; however, the proposed basic
C-22
-------
AUG 1 5 1883
LEGEND
L: Total Retention Lagoons
(listed in Appendix A)
P: Treatment Ponds
(listed in Appendix B)
W: Ground Water Monitoring Location
Figure C-6
C-23
-------
residue pond toward the bottom is 570 feet long (east to west) by 277
feet wide (north to south) measured from the inside top or the dikes,
The facility is licensed to possess no more than 30 MT of natural
uranium and 6? MT of natural thorium. We could not determine how much
material is actually on hand; however, the licensee requested approval
in March 1983 to construct the proposed pond shown on Figure O6
because pond 8 (to the northwest of the proposed pond) will be full
within two years .
The Molycorp plant at York, Pennsylvania (site layout shown in
P'igure C-7), operates a rare earth extraction process which produces
about 26 MT/month (dry weight) of residues containing 0.65 wt% thorium
and 0.002 wt% uranium. These residues are currently put into 55-galion,
plastic- bag- lined, steel drums pending future disposal. Apparently
there are plans to approximately double production. Current plans for
disposal of the residues call for them to be added to the tailings
being disposed of at a Nuclear Regulatory commission licensed tailings
impoundment at Sweetwater, Wyoming. A measurement at the south plant
boundary, near the vent scrubber, indicates a radon concentration o£
0.002-0.003 working levels,
In addition to these residues, which are apparently going to be
disposed of, there was reference to about 800 cubic yards of contami-
nated earth at the York plant, and a thorium slag waste pile at a
Washington, Pennsylvania, facility. We could not. obtain information
on these potential sources of radon, apart from one statement that the
radiation level at the surface of the contaminated earth at the York
plant was as high as 580 pR per hour (SR per year),
2 . 3 SbejEtart, Chemica 1
Stepan Chemical does not use source material; however, its plant
is on land formerly owned by the Maywood Chemical company, who between
1895 and 1959 operated a process which resulted in thorium waste.
Because there were no restrictions on disposal of such waste during
this period, it was simply put in piles at various places on the
Maywood Chemical Co. property, some of which was later sold. The site
and some of the surrounding property (including some residential
property) have been found to be contaminated with thoriura. The Nuclear
Regulatory commission is presently negotiating with Stepan chemical
regarding the steps to be taken to clean up the area. The plant site,
along with measured radiation levels in yR/hour, is shown in
Figure c-8. Apparently there are (according to the license) about 8600
cubic yards of 0.25% thorium residues buried in the area identified as
"Burial III" on Figure C-8. No information, was available regarding the
amounts in other (off-* site) areas. The Nuclear Regulatory Commission
has stated that the otf-site contamination does not pose any immediate
threat to public health and safety. The Nuclear Regulatory Comiission
C-24
-------
PLANT PLOT PLAN
TTt-zrv
to%»S «.^-
earth
chloride resi3ug 'storage
;r^:r™
WINDSOR 5T
Air samcie iocaiioris are m itctc 'voe
nurr.oe'S in -Iotic 'yes C'S gc^r-c s«."/ew Cd
MOLYBDCNUM
JQji? • _£?
Figure C-7
C-25
-------
o
N,Y. SUSQUEHANNA & WESTERN
I I I II I M I I I I I I 333
54 20 !"»
65
/*•
I
o
42'
/
c-'
HOV3B
-------
has noted that there is a potential for a few persons living in some of
the residences to receive radiation doses in excess of the accepted
limits for members of the public.
Vis t ron Corgora_t ion
Vistron at one time manufactured uranium-bearing catalysts but
does not do so any longer. As of 1976, 420 MT of catalysts containing
about 50 MT of uranium and about 15 MT of UaOa were stored in the
Vistron Plant, This material is stored in sealed drums in an abandoned
warehouse on the plant site. The measured radiation level at one foot
from the surface of these drums was 0.4 mrem/hr for the drums
containing catalysts and 1.1 mrem/hr for the drums containing UaOe,
Kerr-McGee
Liquid waste from the production of thorium and rare earth
elements was generated at the West Chicago site from 1932 to 1973. The
site layout is shown in Figure C-9. Plans for its decommissioning are
currently underway. The Nuclear Regulatory Commission, in its final
environmental statement related to the decommissioning (NUREG-Q9Q4, May
1983), recommended that all radioactive material be stabilized and
stored on-site for an indefinite period, with ultimate disposal to be
determined later. The amounts of ThOa and UaOa are as shown
be low:
Quantity, MT
Location ThOa UaOs
Ore residue pile 210 3
sediment pile (near 470 6
Building 18)
Ponds 1-3 760 12
The Nuclear Regulatory Commission has estimated current releases to
be 70 Ci/yr of radon-222 and 14,000 Ci/yr of radon-220, and doses of
<1 Kirem/yr to the whole body. 4 mrem/yr to the bone, 25 mrem/yr to the
lung, and 260 mrem/yr to the bronchial epithelium of the nearest
resident. With the recommended action, these doses would be reduced to
zero.
MallinckFodt Company
The Mallinckrodt Company's columbium-tantalum processing facility in
St. Louis, Mo., is licensed to possess 27.1 MT of uranium and 30 MT of
thorium in natural and synthetic ores. The docket for this facility
(40-6563) does not contain information on the layout of the facility or
the location of the uranium and thorium ore storage areas at the site.
Nor does the docket contain data on radon emissions or boundary
C-27
-------
STREET
ZOO
j Residue ('B
/ Pile
\Jj>
FIGURE C-9. DIAGRAM OF THE KERR-McGEE FACILITY
Adapted from ER. Figure 2,5,1.
C-28
-------
concentrations. Our attempts to obtain such Information from the
(both from headquarters and the cognizant regional office) were
unsuccessful. Estimates of the actual amounts of material stored at
the site or of the radon emissions from the materials are not available,
029
-------
NRG REFERENCES
The following documents were used in preparing the NRC section of
this report and are available for inspection in the NRC Public Document
Room under the appropriate docket number.
1- Fansteel, Inc. (Docket 40-7580)
USNRC, Draft Safety Evaluation Report Related to New Waste
Treatment Pond No. 9, 1983.
2. Holycorp (Docke. t 40-8794)
Application for source material license, 1981.
Eberline Instrument Corp. report of Radiation survey of Molycorp
Plant at York, Pennsylvania, 1981.
Molycorp Response to NRC Notice of violation, 1981.
3. Stepan ChemicaI (Docket 40-6610)
NRC Report on Thorium Contamination in the Area of Maywood and
Rochelle Park, New Jersey, 1981.
4- VistronCorp. (Docket40-7604)
Letter from R.C. Shower (Vistron) to J.M. Bell {NRC), February 24,
1976.
Letter from O.K. DOSS (Vistron} to K.S. Dragonette (NRC),
January 13, 1976.
5. Kerr McGee (.Docket 40-2061)
USNRC, Final Environmental Statement Related to the Decommissioning
of the Rare Earths Facility, West Chicago, Illinois, NUREG-0904,
May 1983.
6. Mallinckrodt Company (Docket 40-6563)
e-3o
-------
APPENDIX D
-------
Page Intentionally Blank
-------
APPENDIX D
DEPARTMENT OF ENERGY GOCO FACILITIES*
(Governtaent-OwBed, Contractor-Operated Facilities) where contractors
are subject to DOE Procurement Regulation 9-50.704™2(a)
Responsible
Field Office
California
1. a. Lawrence Berkeley Laboratory SAN
University of California
Berkeley, California
b. Dormer Laboratory SAN
University of California
Berkeley, California
c. Chemical Biodynamics Laboratory SAN
University of California
Berkeley, California
d, Dymo Facility (Building 934) SAN
University of California
Berkeley, California
Principal Contractor:
University of California
Berkeley, California 94720
2, a. Lawrence Livermore Laboratory SAN
University of California
End of East Avenue
Livermore, California
b, Lawrence Livermore Laboratory - Site 300 SAN
17 miles east of Livermore on Corral Hollow Road
Livermore, California
Principal Contractor:
University of California
P.O. Box 808
Livermore, California 94550
See key to abbreviations on page D-21.
D-3
-------
Responsible
Field Office
California (continued)
3. Sandia Laboratories, Livemore AL
End of East Avenue
Livemore, California
Principal Contractor:
Western Electric, Inc.
Livermore, California 94550
4, 130 Robin Hill Road NV
Goleta, California
Principal Contractor:
EG&G, Inc.
130 Robin Hill Road
Goleta, California 93017
5. a. Energy Technology Engineering Center SAN
DOE Triangle at Santa Susana
Canoga Park, California
b. Energy Technology Engineering Center SAN
Two DOE-owned buildings, total about
5,000 square feet, outside DOE triangle
Canoga Park, California
Principal Contractor:
Rockwell International
Atomics International Division
P.O. Box 1449
Canoga Park, California 91304
6. Stanford Linear Accelerator Center SAN
2572 San Hill Road
Menlo Park, California
Principal Contractor:
Stanford University
P.O. Box 4349
Stanford, California 94305
7. 2801 Old Crow Canyon Road NV
San Ramon, California
Principal Contractor:
EG&G, Inc.
P.O. Box 204
San Ramon, California 94583
D-4
-------
Responsible
gield^Office
California (continued)
8. Research and Development building, Project No. 37 OR
2525 West 190th Street
Torrance, California
Principal Contractor:
AiResearch Manufacturing Company
A Division of Garrett Corporation
2525 West 190th Street
Torrance, California 90509
Colorado
1. Rocky Plats Plant AL
25 miles northwest of Denver - Highway 93
Between Boulder and Golden, Colorado
Principal Contractor:
Rockwell International
Atomics International Division
P.O. Box 464
Golden, Colorado 80401
2. Solar Energy Research Institute CH
Contract No. EG-77-C-01-4042
Golden, Colorado 80401
Principal Contractor:
Solar Energy Research Institute
1617 Cole Boulevard
Golden, Colorado 80401
3. DOE Compound GJ
Grand Junction, Colorado
Principal Contractor:
Bendix Field Engineering Corporation
P.O. Box 1569
Grand Junction, Colorado
Connecticut
1. Knolls Atomic Power Laboratory SNR
Windsor Site
Windsor, Connecticut
D-5
-------
Responsible
Field Office
Connecticut (continued)
Principal Contractor:
General Electric Company
P.O. Box 545
Witidsors Connecticut 06095
Florida
1. Pinellas Plant AL
5 miles southeast of Largo on Bryan Dairy
and Belcher Roads
St. Petersburg, Florida
Principal Contractor:
General Electric Company
P.O. Box 11508
St. Petersburg, Florida 33733
2. Sandia Laboratories Mobile and Remote Range Facility AL
Building 1690
Cape Canaveral, Florida 32920
Principal Contractor:
Western Electric, Inc.
P.O. Box 5800
Albuquerque, New Mexico 87115
Hawaii
1. Sandia Laboratories AL
Barking Sands, Kauai, Hawaii
Principal Contractor:
Western Electric, Inc.
P.O. Box 478
Waimeas Kauai, Hawaii 96796
2. Communications and Scientific Station AL
Haleakalas Mauis Hawaii
Principal Contractor
Western Electric, Inc.
Pacific Area Support Office
P.O. Box. 9186
Haleakala, Maui, Hawaii
D~6
-------
Responsible
Field Office
Idaho
I. Idaho National Engineering Laboratory ID
40 miles west of Idaho Falls, on U.S. Highway 20
Principal Contractors:
EG&G Idaho, Inc. ID
Argorme National Laboratory CH
Exxon Nuclear Idaho Company, Inc. ID
Westinghouse Electric Corporation PNR
Resident Construction Contractor:
Morrisori-Knudsen Company, Inc. ID
Project Construction Contractors,"
Jones-Boecon (J-B) ID
Catalytic, Inc. IB
2. Idaho Falls, DOE, Office Building ID
550 Second Street
Idaho Falls, Idaho 83401
3. Contractor Operated Facilities
a. Computer Science Center ID
1155 Foote Drive
Idaho Falls, Idaho 83401
b. Computer Science Technical Support building ID
1520 Sawtell
Idaho Falls, Idaho 83401
c. Technical Support Building Addition ID
1580 Sawtell
Idaho Falls, Idaho 83401
d. First Street Building ID
550 First Street
Idaho Falls, Idaho 83401
e. Idaho Falls Warehouse Building ID
3600 Bombardier Boulevard
Idaho Falls, Idaho 83401
f. Idaho Falls Library Building Basement ID
457 Broadway
Idaho Falls, Idaho 83401
D-7
-------
Responsible
Field Office
Idaho (continued)
g. Idaho Geothermal - Raft River Project ID
Cassia County - approximately 50 miles
southeast of Burley off U.S. 30 on
approximately 5,000 acres of National
Resource Land and other lands within
the boundaries of DOE application for
withdrawal filed with the BLM and
assigned Serial Register No. I - 7435
Principal Contractor:
EG&G Idaho, Inc.
1955 Fremont
Idaho Falls, Idaho 83401
4. Willow Creek Office Building ID
1955 Fremont
Idaho Falls, Idaho 83401
Principal Contractors:
EG&G Idaho, Inc.
Exxon Nuclear Idaho Company, Inc.
Morrison-Knudsen Company, Inc.
Catalytic, Inc.
rilinois
1. Argonne National Laboratory CH
9700 South Cass Avenue
Argonne, Illinois 60439
Principal Contractor:
Argonne Universities Association
P.O. Box 307
Argonne, Illinois 60439
2. Fermi National Accelerator Laboratory CH
Off Kirk Road on West Boundary
Batavia, Illinois 60510
Principal Contractor:
University Research Associates, Inc.
2101 Constitution Avenue
Washington, D.C. 20037
D-8
-------
Field Office
Iowa
1. Ames Laboratory CH
a. Reactor Building - Scholl Road
b. Physics Addition Building
c. Laboratory and Office Building
d. Spedding Hall - Spammell Drive
e. Metallurgy Building - Spammell Drive
f. Metals Development - Spammell Drive
g. Warehouse Building - Maintenance Area
h. Mechanical Maintenance - Maintenance Area
i. Painting and Air Conditioning Shop - Maintenance Area
Principal Contractor:
Iowa State University
Ames, Iowa 50011
Kentucky
1. Paducah Gaseous Diffusion Plant OR
Paducah, Kentucky
Principal Contractor:
Union Carbide Corporation
P.O. Box 1410
Paducah, Kentucky 42001
Maryland^
1. WE Headquarters Building HQ
Germantown, Maryland
Principal Contractor;
Calculon Corporation
c/o U.S. Department of Energy
Washington, B.C. 20545
Massachuse 11 s
1. Bates Linear Accelerator CH
Middletott, Massachusetts
Principal Contractor:
Massachusetts Institute of Technology
77 Massachusetts Avenue
Cambridge, Massachusetts 02139
D~9
-------
Field Office
Missouri
1. Kansas City Plant AL
Bannister Road and Troost
Kansas City, Missouri
Principal Contractor:
The Bendix Corporation
P.O. Box 1159
Kansas City, Missouri 64141
2. Weldon Springs Retention Basin and Quarry OR
Off U.S. Highway 70 West
Weldon Springs, Missouri
Principal Contractor:
National Lead Company of Ohio
P.O. Box 39158
Cincinnati, Ohio 45329
Montana
1. Magnetohydrodynatnic, Component Development and ID
Integration Facility
53.16 acres near the Butte Industrial Park,
approximately 5 miles south of Butte, Montana
Principal Contractor:
Kaiser Engineers (Construction)
Montana Energy Research and Development
Institute (Operations)
MHD Site Office, P.O. Box 3562
Butte, Montana 59701
Nevada
1. 2753 South Highland Avenue NV
Las Vegas, Nevada
Principal Contractors:
Holmes & Narver, Inc.
2753 South Highland Avenue
Las Vegas, Nevada 89114
Wackenhut Services, Inc.
2753 South Highland Avenue
Las Vegas, Nevada 89114
D-10
-------
Nevada (continued)
Computer Sciences Corp.
2753 South Highland Avenue
Las Vegas, Nevada 89114
2. Nevada Test Site NV
Mercury, Nevada
Principal Contractors:
Reynolds Electrical & Engineering Co., Inc.
P.O. Box 14400
Las ?egas, Nevada 89114
Westinghouse Electric Corporation/Advanced
Energy Systems Division
P.O. Box 327
Mercury, Nevada 89023
3. Tonopah Test Range AL
47 miles southeast of Tonopah
Tonopah, Nevada
Principal Contractor:
Western Electric, Inc.
P.O. Box 871
Tonopah, Nevada 89049
4. a. 680 East Sunset Road NV
Las Vegas, Nevada
b. 6367 Escondido Road NV
Las ¥egass Nevada
Principal Contractor:
EG&G, Inc.
P.O. Box 1921
Las Vegas, Nevada 89101
5, a. 25 Wyandotte Street NV
b. Las Vegas, Nevada
b. 2300 West Rancho Drive, Suite 216 NV
Las Vegas, Nevada
c. 3084 South Highland Drive NV
Building 65 7, and 8
Las Vegas, Nevada
D-U
-------
Responsible
Field Office.
Nevada (Continued)
Principal Contractor:
Reynolds Electrical & Engineering Co., Inc.
P.O. Box 14400
Las Vegas, Nevada 89114
6. North Las Vegas Facility NV
316 East Atlas Circle
North Las Vegas, Nevada
Principal Contractor:
EG&G, Inc.
P.O. Box 1921
Las Vegas, Nevada 89101
New Jersey
1. Princeton Plasma Physics Laboratory . CH
"C" Site and "A" Site on the Forrestal Campus
Princeton, New Jersey
Principal Contractor:
Princeton University
P.O. Box 682
Princeton, New Jersey 08540
2. Burns & Roe Services Corporation CH
Contract No. DE-AC02-79ET14850
Oradell, New Jersey 07649
Principal Contractor:
Burns & Roe Services Corporation
496 Kinderkamack Road
Oradell, New Jersey 07649
NewMexico
1. Sandia Laboratories, Albuquerque AL
Kirtland Air Force Base - East
Albuquerque, New Mexico
Principal Contractor:
Western Electric, Inc.
P.O. Box 5800
Albuquerque, New Mexico 87115
D-12
-------
Responsible
Field Office
New Mexico (Continued)
2, Sandia Laboratories Mobile and Remote AL
Range Facility
Building 1137-1
White Sands Missile Range, New Mexico 88002
Principal Contractor:
Western Electric, Inc.
P.O. Box 5800
Albuquerque, New Mexico 87115
3. Inhalation Toxicology Research Institute AL
Kirtland Air Force base - East
Albuquerque, New Mexico
Principal Contractor:
Lovelace Medical Foundation
Building 9200, Area Y
KAFB - East
Albuquerque, New Mexico 87115
4, EG&G Operations NV
Kirtland Air Force Base - West
NC-135 Area
Albuquerque, New Mexico
Principal Contractor:
EG&G, Inc.
c/o Nevada Site Manager
KAFB - West
P.O. Box 4339
Albuquerque, New Mexico 87106
5. Los Alamos Scientific Laboratory AL
Los Alamos, New Mexico
Principal Contractor:
University of California
P.O. Box 1663
Los Alamos, New Mexico 87544
6. 1100 4th Street NV
Los Alamos, New Mexico
Principal Contractor:
EG&G, Inc.
P.O. Box 809
Los Alamos, New Mexico 87544
D-13
-------
Responsible
Field Office
7. 901 Trinity Drive AL
Los Alamos, New Mexico
Principal Contractor:
The Zia Company
901 Trinity Drive
Los Alamos, New Mexico 87544
8. Waste Isolation Pilot plant AL
32 miles SE of Carlsbad
Principal Contractor:
Western Electric, Inc.
1502 West Stevens Street
Carlsbad, New Mexico 88220
9. Fenton Hill Geothermal Site - TA-57 AL
45 miles west of Los Alamos
Principal Contractor
University of California
P.O.. Box 1663
Los Alamos, New Mexico 87544
10. Ross Aviation AL
Albuquerque Sun Port
Albuquerque, New Mexico
Principal Contractor:
Ross Aviation, Inc.
P.O. Box 9124
Albuquerque, New Mexico 87119
New York
1. Brookhaven National Laboratory CH
Off William Floyd Parkway
Upton, New York
Principal Contractor:
Associated Universities, Inc.
Upton, New York 11973
2. Knolls Atomic Power Laboratory SNR
River Road
Niskayuna, New York
Principal Contractor:
General Electric Company
P.O. Box 1072
Schenectady, New York 12301
D-L4
-------
Responsible
Field Office
New York (continued)
3. Knolls Atomic Power Laboratory SNR
Kesselriog Site
West Miltonj New York
Principal Contractor:
General Electric Company
P.O. Box 1072
Schenectady, New York 12301
4, Niagara Falls Boron Plant OR
Model City, New York
Principal Contractor;
National Lead Company of Ohio
P.O. Box 39158
Cincinnati, Ohio 45329
Ohj.p_
1. Portsmouth Gaseous Diffusion Plant OR
Off Highway U.S. 23
Piketon, Ohio
Principal Contractor:
Goodyear Atomic Corporation
P.O. Box 628
Piketon, Ohio 45661
2. Mound Facility AL
Miamisburg, Ohio
Principal Contractor:
Monsanto Research Corporation
P.O. Box 32
Miaraisburg, Ohio 45342
3. Feed Materials Production Center OR
6 miles north of Cincinnati - off Highway
U.S. 50 bypass west
Fernald, Ohio
Principal Contractor:
National Lead Company of Ohio
P.O. box 39158
Cincinnati, Ohio 45239
D-15
-------
Responsible
Field Office
Pennsylvania
1. Bettis Atomic Power Laboratory PNR
West Mifflin, Pennsylvania
Principal Contractor:
Westinghouse Electric Corporation
P.O. Box 79
West Mifflin, Pennsylvania 15122
2. Pittsburgh Energy Technology Center CH
4800 Forbes Avenue
Pittsburgh, Pennsylvania 15213
Principal Contractor:
General Electric Company
MATSCO
P.O. Box 7507
Philadelphia, Pennsylvania 19101
3. Shippingport Nuclear Power Station PNR
Shippingport, Pennsylvania
Principal Contractor:
Duquesne Light Company
P.O. Box 57
Shippingport, Pennsylvania 15077
South Carolina
1. Savannah River Plant SR
18 miles south of Aiken on State Route 125
Aiken, South Carolina
Principal Contractors:
E.I. du Pont de Nemours and Company
Aiken, South Carolina 29801
University of Georgia
Drawer E
Aiken, South Carolina 29801
Tennessee
1. Oak Ridge National Laboratory OR
Bethel Valley Road - About 12 miles
from Oak Ridge
Oak Ridge> Tennessee
D-16
-------
Responsible
Field Office
Tennessee (continued)
1. Oak Ridge National Laboratory (continued)
Principal Contractor:
Union Carbide Corporation
P.O. Box X
Oak Ridge, Tennessee 37830
2. Y-12 Plant OR
Bear Creek Road - About 1.5 miles
from Oak Ridge
Oak Ridges Tennessee
Principal Contractor:
Union Carbide Corporation
P.O. Box Y
Oak Ridge, Tennessee 37830
3. Oak Ridge Gaseous Diffusion Plant OR
Oak Ridge Turnpike - About 8 miles
from Oak Ridge
Oak Ridge, Tennessee
Principal Contractor:
Union Carbide Corporation
P.O. Box P
Oak Ridge, Tennessee 37830
4. Comparative Animal Research Laboratory OR
1299 Bethel Valley Road
Oak Ridge, Tennessee
Principal Contractor:
University of Tennessee
P.O. Box 1071
Knoxvilles Tennessee 37901
5. a. New Museum OR
Tulane Avenue
Oak Ridge, Tennessee
b. Medical Division Complex OR
Vance Road
Oak Ridge, Tennessee
c. Atmospheric Turbulence and Diffusion Laboratory OR
South Illinois
Oak Ridge, Tennessee
D-17
-------
Responsible
Field Jgffice
Tennessee (continued)
Oak Ridge National Laboratory (continued)
d. Warehouse Bays 4, 5 and part of 3 of OR
Building 1918-T2
Warehouse Road
Oak Ridge, Tennessee
e. Special Training Division OR
Building 2714 (F, G, and Annex) and 2715
Laboratory Road
Oak Ridge, Tennessee
Principal Contractor:
Oak Ridge Associated Universities
P.O. Box 117
Oak Ridge, Tennessee 37830
6. a. Water Treatment Facilities OR
Oak Ridge, Tennessee
b. Building 1916-T2
Warehouse Road
Oak Ridge, Tennessee
Principal Contractor:
The Rust Engineering Company
P.O. Box 587
Oak Ridge, Tennessee 37830
7. Charlotte Hall and Cheyenne Hall OR
Oak Ridge Turnnpike
Oak Ridge, Tennessee 37830
Principal Contractor:
Union Carbide Corporation
P.O. Box Y
Oak Ridge, Tennessee 37830
Texas
1. Pantex Plant AL
21 miles northeast of Amarillo, 2 miles north
of U.S. Highway 60
Amarillo, Texas
Principal Contractor:
Mason & Hanger - Silas Mason Co., Inc.
P.O. Box 647
Amarillo, Texas 79177
D-18
-------
Responsible
Field Office
Washington
1. Solvent Refined Coal Pilot Plant OR
Fort Lewis, Washington 98433
2. Hanford Project RL
5 miles north of Richland Federal Building
Riehland, Washington
Principal Contractors:
Rockwell International
Rockwell Hanford Operations
P.O. Box 250
Richland, Washington 99352
Battelle-Pacific Northwest Laboratory
P.O. Box 999
Richland, Washington 99352
&CS Richland, Inc.
P.O. Box 300
Richland, Washington 99352
Hanford Environmental Health Foundation
P.O. Box 100
Richland, Washington 99352
J.A. Jones Construction Company
801 First Street
Richland, Washington 99352
United Nuclear Industries, Inc.
P.O. Box 490
Richland, Washington 99352
Vitro Engineering Corporation
P.O. Box 296
Richland, Washington 99352
Westinghouse Hanford Company
P.O. box 1970
Richland, Washington 99352
3. 700 Area RL
Richland Federal building
825 Jadwin Avenue
Richland, Washington
D-19
-------
Responsible
Field Office
Washington (Continued)
3. 700 Area (Continued)
Principal Contractors:
Rockwell International
Rockwell Hanford Operations
Battelle-Pacific Northwest Laboratory
BCS Richland, Inc.
Hanford Environmental Health Foundation
United Nuclear Industries, Inc.
Vitro Engineering Corporation
Westinghouse Hanford Company
4. 703 Building RL
Knight Street
Richland, Washington
Principal Contractors:
Rockwell International
Rockwell Hanford Operations
Battelle-Pacific Northwest Laboratory
BCS Richlands Inc.
Hanford Environmental Health Foundation
5. a. 712 Building RL
Northgate Drive
Richland, Washington
b. 1100 Area RL
Stevens Drive
Richlandj Washington
c. Columbia Bank Building RL
1100 Jadwin Avenue
Richland, Washington
D-20
-------
Responsible
Field Office
Washington (continued)
d, Tannadore Building RL
1155 Jadwin Avenue
Richlandj Washington
e. Richland Sky Park RL
Terminal Building
Richland Airport
Richland, Washington
Principal Contractor:
Rockwell International
Rockwell Hanford Operations
P.O. Box 250
Richland, Washington 99352
6. 747 Building RL
Knight Street
Richland, Washington
Principal Contractors:
Hanford Environmental Health Foundation
BattHe-Pacific Northwest Laboratory
7. a. 748 Building RL
Swift Street
Richland, Washington
b. Medical-Dental Building RL
Swift Street
Richland, Washington
Principal Contractor:
Hanford Environmental Health Foundation
P.O. Box 100
Richland, Washington 99352
8. 3000 Area RL
First Street
Richland, Washington
Principal Contractor:
J, A. Jones Construction Company
801 First Street
Richland, Washington 99352
D-21
-------
Responsible
Field Office
Washington (continued)
9. a. Port of Benton Building RL
2592 George Washington Way
Richland, Washington
b. Hanford Square 1 Building RL
3080 George Washington Way
Richland, Washington
c. Group V Building RL
3200 George Washington Way
Richland, Washington
d. GESA Building RL
723 Parkway
Richland, Washington
e. Robert Young Building RL
1933 Jadwin Avenue
Richland, Washington
f. Robert Young Building RL
1955 Jadwin Avenue
Richland, Washington
g. Hanford Square 4 Building RL
3060 George Washington Way
Richland, Washington
h. Sigma III Building RL
316 George Washington Way
Richland, Washington
i. Sigma IV Building RL
3170 George Washington Way
Richland, Washington
Principal Contractor:
Battelle-Pacific Northwest Laboratory
P.O. Box 999
Richland, Washington 99352
10. Robert Young Building RL
1933 Jadwin Avenue
Richland, Washington
D-22
-------
Responsible
Field Office
Washington (continued)
Principal Contractor:
Vitro Engineering Corporation
P.O. Box 296
Richland, Washington 99352
11. a. Jadwin Building
1135 Jadwin Avenue
Richland, Washington
b. 3190 Building
3190 George Washington Way
Richland, Washington
c. 3180 Building
3180 George Washington Way
Richland, Washington
Principal Contractor:
Westinghouse Hanford Company
P.O. Box 1970
Richland, Washington 99352
Puerto Rico
1. a. Nuclear Research and Training Center
Rio Piedras, Puerto Rico
b. Nuclear Research and Training Center
Mayaguez, Puerto Rico
c. El Verde Terrestrial Ecology Station
Loquillo National Forest
Puerto Rico
RL
RL
RL
OR
OR
OR
Abbreviations:
AL - Albuquerque
CH - Chicago
OR - Oak Ridge
RL - Richland
SAN - San Francisco
NV - Nevada
GJ - Grand Junction
SNR - Schenectady Naval Reactor
ID - Idaho
PNR - Pittsburgh Naval Reactor
HQ - Headquarters
D-23
-------
(Fieast read Instruction! on she reverse be}o,
1. REPORT N<
EPA 520/1-84-022-2
3. RECIPIENT'S ACCESSION
4, TJTL.E AND SUBTITLE
Background Information Document (Volume II)
(Integrated Risk Assessment)
Pittal Rules for Radionuclides
5. REPORT DATE
October 22, 1984
6, PERFORMING ORGANIZATION COD6
7. AUTHORCSt
8. PERFORMING ORGANIZATION REPORT NO,
9. PERFORMING ORGANIZATION NAMi AND ADDRESS
Environmental Protection Agency
Office of Radiation Programs
Washington, B.C. 20460
10, PROGRAM ELEMENT NO.
11, CONTRACT/GRANT NO,
12. SPONSORING AGENCY NAME AMD ADDRESS
13, TYPE OF REPORT AND PERIOD COVERED
14. SPONSORING AGENCY CODE
15. SUPPLEMENTARY NOTES
16. ABSTRACT
This report serves as a background information document in support of
the Environmental Protection Agency's final rules for sources of emissions
of radionuclides pursuant to Section 112 of the Clean Air Act.
This report presents an analysis of the public health impact caused by
radionuclides emitted into the air from facilities that are the subject of
this rulemaking. These facilities are examined as six major source
categories: (1) Department of Energy (DOE) facilities, (2) Nuclear
Regulatory Commission licensed facilities and non-DOE Federal facilities,
(3) coal-fired utility and industrial boilers, (4) uranium mines, (5)
phosphate industry facilities, and (6) mineral extraction industry
facilities,.
For each source category, we present the following information; (1) a
general description of the source category, (2) a brief description of the
processes that lead to the emissions of radionuclides into air, (3) a
summary of emissions data, and (4) estimates of the radiation doses and
health risks to both individuals and populations.
7.
KEY WORDS AND DOCUMENT ANALYSIS
DESCRIPTORS
b.lDENTlPlERS/OPEN ENDED TERMS
c, COSATI Field/Group
Clean Air Act
Radionuclides
Radon
DOE Facilities (Department of Energy)
Nuclear Regulatory Commission licensed
facilities
Uranium mines Phosphate Industry
8. DISTRIBUTION STATEMENT
Unlimited
19, SECURITY CLASS (This Report)
Unclassified
21. NO. OF PAGES
474
20, SECURITY CLASS (Thispage)
Unclassified
22. PRICE
EPA Fofui 2220-1 (R*», 4-77) PREVIOUS EDITION is OBSOLETE
-------