Infiltration/Inflow
Introduction
As part of facilities planning for municipal wastewater treatment facilities, the grantee must
demonstrate that contributing sewer systems are not, and will not be, subject to excessive
infiltration or inflow. This brochure informs grantees and facility planners on how to determine
whether excessive I/I exists, and how to certify that excessive I/I has been sufficiently reduced
through sewer rehabilitation.

"Infiltration" occurs when groundwater enters a sewer system through broken pipes, defective
pipe joints, or illegal connections of foundation drains. "Inflow" is surface runoff that enters a
sewer system through manhole covers, exposed broken pipe and defective pipe joints, cross
connections between storm sewers and sanitary sewers, and illegal connection of roof leaders,
cellar drains, yard drains, or catch basins.

Virtually every sewer system will have some infiltration or inflow. Guidelines have been
developed to help determine what amount of infiltration and inflow is considered "excessive."
To make this determination, infiltration and inflow must be evaluated separately as discussed
below.
Determination of Non-Excessive Infiltration
Based on Needs Survey data from 270 Standard Metropolitan Statistical Area Cities, the national
average for dry weather flow is 120 gallons per capita per day (gpcd). This includes domestic
wastewater flow, infiltration and nominal industrial and commercial flows. This average dry
weather flow should be used as an indicator to determine the limit of non-excessive infiltration.
If the average daily flow per capita (excluding major industrial and commercial flows greater
than 50,000 gpd each) is less than 120 gpcd (i.e., a 7-14 day average measured during periods of
seasonal high groundwater), the amount of infiltration is considered non-excessive.

The 120 gpcd flow rate guideline has been incorporated into EPA's final Construction Grant
Regulations. These regulations provide that no further infiltration analysis work is required if the
120 gpcd guideline is not exceeded. If the average daily dry weather flow (DWF) exceeds 120
gpcd, the grantee may request special approval from the EPA Regional Administrator to proceed
with project design without further infiltration studies. To receive such approval, the grantee
must demonstrate that the increased flows due to infiltration can be cost-effectively treated, and
that sufficient funding is available to pay for the local share of project construction and operating
costs. In such cases, the incremental cost of treatment capacity over and above 120 gpcd is not
eligible for EPA construction grant funding.

-------
Infiltration/Inflow
The grantee's basic options regarding determination of non-excessive infiltration are listed
below:

If Average DWF* <120 gpcd:
    •   Grantee may proceed with project design and construction without further infiltration
         study.
    •   Grantee may investigate rehabilitation alternatives for specific sections of sewer system
         where excessive infiltration has been documented.

If Average DWF* marginally exceeds 120 gpcd:
    •   Grantee may request special approval from EPA Regional Administrator to proceed
         with the project without further study of infiltration correction alternatives.
    •   Grantee must demonstrate that project is cost-effective (i.e., that treating increased
         flows due to infiltration is less costly than sewer rehabilitation).
    •   Grantee must demonstrate that sufficient funds are available for the local share of
         project cost, including capital and operating costs.
    •   The treatment facility must be sized to treat the total flow including infiltration;
         however, the incremental cost of treatment capacity above 120 gpcd is not eligible for
         EPA construction grant funding.


If Average DWF* >120 gpcd, and Special RA Approval is not granted:
    •   Further studies must be conducted to quantify excessive infiltration and evaluate
         alternative corrective measures.
    •   Based on results of these studies, the most cost-effective sewer rehabilitation program is
         selected, and the treatment plant is sized to handle the infiltration that cannot be cost-
         effectively removed.
    •   Upon approval of the proposed rehabilitation program by EPA, grantee may proceed
         with project design and construction. Total project cost (including sewer rehabilitation
         costs) is eligible for construction grant funding.

* Highest average daily flow recorded over a 7-14 period during a period of seasonal high groundwater.

-------
Infiltration/Inflow
Determination of Non-Excessive Inflow
A statistical analysis of data from Sewer System Evaluation Survey (SSES) studies representing
more than 45 different sewer systems (i.e., separate sanitary sewer system) indicated a strong
correlation between inflow rate and service area population. Based on these data, the average wet
weather flow (WWF) after removal of excessive inflow (i.e., that which can be cost-effectively
removed) is 275 gpcd. This flow rate should be used as an indicator of non-excessive inflow.

If the average daily flow during periods of significant rainfall (i.e., any storm event that creates
surface ponding and  surface runoff; this can be related to a minimum rainfall amount for a
particular geographic area) does not exceed 275 gpcd, the amount of inflow is considered non-
excessive. This calculation should exclude major commercial and industrial flows (greater than
50,000 gpd each). If wet weather flows do not exceed 275 gpcd, the grantee may proceed with
project design and construction without further study of inflow correction alternatives. However,
if the treatment plant experiences hydraulic overloads during storm events, further study is
required regardless of the wet weather flow (i.e., even in cases where WWF is less than 275
gpcd).

The determination of non-excessive inflow is made as follows:
If WWF* <_275 gpcd, and the treatment plant does not experience hydraulic overloads during
storm events:
    •   Grantee may proceed with project design and construction without further inflow
        studies.
    •   Grantee may investigate rehabilitation alternatives for specific sections of the sewer
        system where excessive inflow has been documented.

If WWF*>275 gpcd, or the treatment plant experiences hydraulic overloads during storm events:
    •   Further studies must be conducted to quantify excessive inflow and evaluate alternative
        corrective measures.
    •   Based on results of these studies, the most cost-effective sewer rehabilitation program is
        selected, and the treatment plant is sized to handle the inflow that cannot be cost-
        effectively removed.
    •   Upon approval of the proposed rehabilitation program by EPA, the grantee may proceed
        with project design and construction. Total project cost  (including sewer rehabilitation
        cost) is eligible for construction grant funding.
    * Highest daily flow recorded during a storm event.

-------
Infiltration/Inflow
I/I Cost-Effectiveness Analysis
Before obtaining a grant for sewer system rehabilitation, the grantee must determine the amount
of infiltration and inflow that can be cost-effectively removed. This is essentially an estimate of
the point at which the cost savings (i.e., reduction in transport and treatment cost less the cost of
the rehabilitation program) is maximized. Generally, the planned I/I reduction (i.e., the target
sought in a sewer rehabilitation project) is determined on the basis of a cost-effectiveness
analysis. Figure 1 illustrates how the planned I/I reduction target is established from cost curves
developed  in the cost-effectiveness analysis. A separate cost-effectiveness analysis should be
done for infiltration alternatives and for inflow alternatives.
                                                   Total cost curve
                                                   Transport and
                                                   treatment cost
                                                      curve
                                                Planned
                                               reduction
                                      infiltration or Inflow Reduction
                             Figure 1  Cost-Effectiveness Analysis

-------
Infiltration/Inflow
Certification of I/I Rehabilitation Performance
At the end of the one-year performance period (i.e., one year after initiation of sewer system
operation), the grantee must certify that the rehabilitation project has achieved an acceptable
level of I/I reduction. Ideally, this means that the planned I/I reduction target is achieved at a cost
not exceeding that projected in the cost-effectiveness analysis. However, past experience has
shown that it is difficult to measure the effectiveness of an I/I rehabilitation program simply by
comparing flow data before and after sewer rehabilitation.

A sewer rehabilitation project will be considered certifiable as long as the project is cost-
effective (i.e. transport and treatment cost savings exceed rehabilitation costs). Figure 2
illustrates how to determine the minimum acceptable I/I reduction using the transport and
treatment cost curve from the cost-effectiveness analysis. A separate determination should be
made for infiltration and for inflow, consistent with the original cost-effectiveness analysis.

The actual cost of the rehabilitation program (i.e., the "sunk cost") should include design costs
and the cost of the SSES study, as well as the cost of the sewer rehabilitation itself. The actual I/I
reduction is  determined by  comparing post-construction flow to the flow data collected during
the SSES study. The post-construction flow data should be based on plant flow records.
Monitoring flows at multiple points throughout the sewer system is not recommended.
                                                         Transport and
                                                         treatment cost
                                                           curve
                                                                    tOO-
   Minimum
acceptable reduction
                                                    Planned
                                                    reduction
                                       % Infiltration or Inflow Reduction
                         Figure 2 Determining Acceptable Range of I/I Reduction

-------
Infiltration/Inflow
If the actual I/I reduction is greater than the minimum acceptable I/I reduction derived from
Figure 2, the rehabilitation project can be certified as meeting performance objectives. However,
it should be noted that treatment plant design capacity is based on the planned I/I reduction
projected in the SSES study. If the actual I/I reduction is significantly less than planned, redesign
may be required to increase treatment capacity. Therefore, every effort should be made to
develop realistic estimates of the amount of I/I that can be cost-effectively  removed. As an I/I
project proceeds from initial planning through design and construction, certain assumptions
made during the cost-effectiveness analysis may prove to  be invalid. This could affect the cost-
effectiveness of the project and the determination of minimum acceptable I/I reduction. For
example, if the actual rehabilitation cost is greater than projected, the range of acceptable I/I
reduction is reduced (see Figure 3). If the reduction in transport and treatment costs is not as
great as expected, this will also reduce the acceptable range.
                                               T
                             Acceptable range
                             based on projected —-*»
                                costs
                              Acceptable range_
                               based on actual "
                                  ' COStS
                                                        Transport and
                                                        treatment cost
                                                           curve
                                     Minimum
                                 acceptable reduction
                                               SO
Planned
reduction
                                                                    100
                                      %lnfiltration or Inflow Reduction
                       Figure 3 Effect of Underestimating Project Costs
Therefore, it is important to recalculate the acceptable range of I/I reduction at different stages of
the project (e.g., after approval of SSES study; after completion of design and preparation of
detailed cost estimates; after receipt of construction bids; and at completion of various
construction phases) using updated cost estimates or actual cost data.
As the minimum acceptable I/I reduction limit approaches the planned I/I reduction target, the

-------
Infiltration/Inflow
cost-effectiveness of the project should be reevaluated. The risk of the project not achieving the
minimum acceptable I/I reduction increases as the acceptable range derived from Figure 2
diminishes. If there is evidence that actual rehabilitation costs will be much higher than
projected, it may be advisable to reassess the objectives of the rehabilitation program, and
modify the scope of work accordingly.
Summary
This brochure presents an overview on how to approach the implementation of an infiltration/
inflow correction program. A schematic of the process is presented in Figure 4. The basic steps
are as follows:
1.   Determine if excessive infiltration exists using 120 gpcd guidelines.
2.   Determine if excessive inflow exists using 275 gpcd guideline.
3.   If infiltration and inflow are non-excessive, proceed with project design based on measured
    flow data.
4.   If either excessive infiltration or excessive inflow exists, conduct sewer system evaluation
    survey (SSES) study.
5.   Select most cost-effective sewer rehabilitation alternative.
6.   Implement sewer system rehabilitation; verify project cost-effectiveness as updated cost data
    become available.
7.   Upon completion of project (i.e., at end of one-year performance period), certify that I/I
    reduction is within acceptable range.
Determine cost
effective removal
rates


Design sewer
rehabilitation
program
                  Yes
                                                                 Ifiiplornont
                                                                 corrective
                                                                  action
                                                               Not
                                                             acceptable
                                          Re-evaluate
                                            cost
                                          effectiveness
                      Implement
                       project
Assess project
results: compare
 to acceptable
   results
                                                            Acceptable
Use measured
 inflow rate
 for treatment
 plant design
                                                                  Certify
                                                                 project to
                                                                   EPA
              Figure 4  I/I Project Flow Chart

-------
Infiltration/Inflow
To achieve affirmative project certification, the estimates of rehabilitation cost and I/I reduction
must be realistic. Underestimating project cost can invalidate the conclusions of the cost-
effectiveness analysis conducted as part of the SSES study. It is important to include all cost
items in the cost estimates (the cost of service line rehabilitation should be included even though
it is not grant eligible).

Sewer rehabilitation programs can significantly reduce transport and treatment costs, and
therefore should be given serious consideration. However, the cost-effectiveness of such projects
must be carefully evaluated to assure that rehabilitation is justified. The requirements for project
certification now mandate that project cost-effectiveness be confirmed at the completion of the
project. Grantees and their engineers should carefully assess their I/I correction plans to be sure
that project certification requirements can be  satisfied.

Further guidance on this  subject is available from U.S. EPA Regional Offices and delegated
State agencies.

-------