Greenhouse Gas Technology Verification Center
  A USEPA Sponsored Environmental Technology Verification Organization
         Testing and Quality Assurance Plan for the
          C. Lee Cook Division, Dover Corporation
                      Static Pac® System
                           Prepared By:
                       Southern Research Institute
               Greenhouse Gas Technology Verification Center
                   Research Triangle Park, NC   USA
                       Telephone: 919/403-0282
                           For Review By:
              C. Lee Cook Division, Dover Corporation
                    ANR Gas Pipeline Company   ^
              The Oil and Gas Industry Stakeholder Group
                 USEPA Quality Assurance Team      [
                           July 20, 1999

-------
                             TABLE OF CONTENTS
                                                                          Page

1.0   BACKGROUND AND INTRODUCTION	1

2.0   TECHNOLOGY DESCRIPTION AND VERIFICATION APPROACH	3
     2.1.  STATIC PAC SYSTEM DESCRIPTION	3
     2.2.  VERIFICATION PARAMETERS AND THEIR DETERMINATION	6
          2.2.1.  Approach	6
          2.2.2.  Phase I Static Pac Evaluation	10
          2.2.3.  Phase II Static Pac Evaluation	15
     2.3.  SITE SELECTION, DESCRIPTION, AND STATIC PAC
          INSTALLATION	18
          2.3.1.  Site Selection and Description	18
          2.3.2.  Static Pac Installation and Operation	19
     2.4.  FIELD TEST OVERVIEW	20
          2.4.1.  Continous Leak Rate Measurements	20
          2.4.2.  Manual Leak Rate Measurements	21
     2.5.  SCHEDULE OF ACTIVITIES	23

3.0   DATA QUALITY  OBJECTIVES	24
     3.1.  CONTINUOUS MEASUREMENTS	24
     3.2.  MANUAL  MEASUREMENTS	25
     3.3.  PROJECTIONS	27

4.0   DATA QUALITY  INDICATORS	27

5.0   SAMPLING/ANALYTICAL AND QA/QC PROCEDURES	29
     5.1.  CONTINUOUS FLOW MEASUREMENTS	29
     5.2.  MANUAL  LEAK RATE MEASUREMENTS	30
          5.2.1.  Blow-down Valve, and Pressure Relief Valve	30
          5.2.2.  Miscellaneous Components	32
          5.2.3.  Unit Valves	32
     5.3.  DATA ACQUISITION	33

6.0   DATA REDUCTION, VALIDATION, AND REPORTING	34
     6.1.  DATA REDUCTION	34
          6.1.1.  Continuous Measurements	34
          6.1.2.  Manual Measurements	35
          6.1.3.  Gas Savings and Payback period	35
          6.1.4.  Unit Conversions	35
     6.2.  DATA REVIEW AND VALIDATION	36
     6.3.  DATA ANALYSIS AND REPORTING	37

7.0   AUDITS	39

8.0   CORRECTIVE ACTION	39

9.0   PROJECT ORGANIZATION	39

10.0  TEST PROGRAM HEALTH AND SAFETY	40

11.0  REFERENCES	42

-------
                                     APPENDIX









Appendix A    Static Pac Operator's Manual - Automatic Control System




Appendix B    Static Pac Operator's Manual - Manual Control System

-------
                         1.0    BACKGROUND AND INTRODUCTION

The Environmental Technology Verification (ETV) program was established by the United States
Environmental  Protection Agency (EPA) in response  to  the  belief that there are  many viable
environmental  technologies which are  not being used  for the  lack  of credible  third-party
performance testing.  With the performance data developed under the program, technology buyers
and permitters  in the United  States and abroad will be  better  equipped to make informed
environmental technology purchase decisions.  In late 1997, EPA selected Southern Research
Institute  to manage  1  of 12  ETV verification entities:  The Greenhouse  Gas  Technology
Verification Center (the Center). Eleven other ETV entities are currently operating throughout the
United States conducting third-party verifications in a wide range  of environmental media and
industries.

In March of 1997, the Center met with  members of the  Executive Stakeholder Group.  In that
meeting  it was decided  that the  oil and gas  industries  were  good candidates for third-party
verification of methane mitigation and monitoring technologies. As  a consequence, in June  1998,
the Center hosted a meeting in Houston,  Texas with operators and vendors in the oil and natural
gas industries. The objectives of the meeting were to: (1) gauge the need for verification testing in
these  industries, (2) identify specific technology testing priorities, (3) identify broadly acceptable
verification and testing strategies, and  (4)  recruit industry stakeholders.   Industry participants
voiced support  for the Center's mission, identified a need for independent third-party verification,
and prioritized specific technologies and verification strategies. Since the Houston meeting, a  19
member Oil and Gas Industry Stakeholder Group was formed, vendors of GHG mitigation devices
were solicited in several top-rated technology areas, and verification testing of one compressor leak
mitigation device has started.

C. Lee  Cook Division of the  Dover Corporation has committed to participate in  a long-term
independent verification  of their rod leak prevention technology.  C. Lee  Cook's Static Pac1 is
designed to reduce methane  leaking  from  compressor  rod seals during periods of compressor
shutdown without full depressurization.  There are over 13,000 natural gas compressors operating
in the United States alone, a significant number of them experiencing frequent shutdowns.  When
the compressor remains pressurized during  these periods, rod leaks continue at rates similar to
1 Static Pac is a registered trademark of the C. Lee Cook Division of Dover Corporation.
                                            -1-

-------
those during normal operation. According to the Gas Research Institute/Environmental Protection
Agency study "Methane Emissions From the Natural Gas Industry ("GRI Study"), compressor rod
seal  leaks during periods of shutdown represent a major source of methane  emissions, and a
significant loss of economic and natural resources.

A test of the Static Pac device will be carried out at a compressor station operated by ANR Pipeline
Company (ANR) of Detroit, Michigan. This Test Plan describes the technology to be tested, and
outlines the Center's plans to conduct the verification in a field setting.

Field testing of the Static Pac is scheduled to begin at the ANR site in June  1999, and will continue
for a 4 to 6 month period. After initial installation and testing is complete, the Center will issue a
Phase  I Report, containing installation  and initial verification measurements data (September
1999). After all testing is complete, a Phase II  Report will be issued which contains longer-term
technical and economic  performance  verification data  (2 months after-completion  of  the field
evaluation).  The specific verification parameters associated with the Phase 1 and Phase  II efforts
are listed below. Determination of each parameter is discussed in Section 2.2.

Phase I Static Pac Evaluation:
       •   Document initial gas  savings for primary baseline  operating conditions (Case  1
           and Case 2, see Section 2.2)
       •   Document capital, installation, and shakedown requirements and costs
Phase II Static Pac Evaluation:
       •   Document annualized gas savings for primary baseline conditions
       •   Document methane emission reduction
       •   Calculate and document Static Pac payback period
Phase  I  goals  will  be achieved  through  observation, collection  and analysis  of direct gas
measurements, and use of site operator logs and vendor supplied cost information.

A primary goal of Phase II is determination of the Static Pac payback period. As a practical matter,
the Center cannot conduct direct testing for the several years that would be required to determine
payback entirely through direct gas and other measurements or for the myriad of variations in the
frequency and duration of compressor operating/shutdown cycles. Thus, several Phase II goals will
be accomplished through  a combination of medium-term measurements (3  to 6  months),  data
                                           -2-

-------
extrapolation techniques, and collecting and  presenting data adequate to  calculate  payback for
various operating/shutdown cycles. Extrapolation and other assumptions will be transparent in the
final report, allowing readers to make alternate assumptions and assessments if they wish.


            2.0    TECHNOLOGY DESCRIPTION AND VERIFICATION APPROACH

2.1.    STATIC PAC SYSTEM DESCRIPTION

The  Static Pac is  a gas leak  containment device designed  to  prevent rod packing leaks from
escaping into the  atmosphere  during  compressor shutdown  periods.  The Static  Pac  system is
installed in a conventional packing case by replacing several cups (typically 2) in the low-pressure
side of the packing case (see Figure 1).

Upon shutdown of the compressor, the compressor control system activates the  Static Pac control
system and a pressurized gas is used to move  a piston along the  outer shell of the Static Pac seal,
wedging a lip seal  into contact with the rod (see Figures 1 and 2).  When the actuating pressure is
lowered, the piston retracts, releasing the Static Pac seal. Leaks that normally occur during periods
of shutdown are reported by Cook to be completely or nearly eliminated.

Because the Static Pac  requires  modification of the conventional packing case,  resulting in  a
"missing seal", it is speculated that increase in rod emissions can occur while the compressor is in
operating mode.   However, industry  experience suggests that  the Static Pac  should not  affect
normal sealing during compressor operation.  The Center has been unable to locate  reliable data
that verified this.   Therefore, the verification test will include assessment of the effect (if any) of
the Static Pac  on normal  sealing  performance  during  compressor  operation.   This will be
accomplished by fitting one rod on the test engine with a Static Pac and the second rod with a new
conventional packing.  A second engine will be fitted  in the same  manner to  provide  duplicate
measurements.
                                           -3-

-------
liSTATIC-PAU is a negisierea
Trademark of C.  LEE COOK and
covered by Patent No, 446901?:'
                                              —
                      STATIC-PAC
                          KIT--i
   SEAL IS ACTUATED ONLY WHEN ROD IS AT REST[
      WHEN DEACTIVATED, NO ROD CONTACT,
      V/HEN ACTIVATED. SEAL CONTACTS ROD
J5
•
••.>w-i ••.--.
i
•



U^i


I


— M — 	 H
: '
:-v.ia 1
1
1
1
                                        -J
    Figure 1-a. The Static Pac Activation and Deactivation Process
                       -4-

-------
V
                          %w?3
                                                                  "7\
                                            3
                                               ft
                                               i
                Figure 1-b. Rod Packing Cutaway With Static Pac
                               - 5 -

-------
2.2.    VERIFICATION PARAMETERS AND THEIR DETERMINATION

2.2.1.  Approach

Because the Static Pac operates only when the compressor is shut down, the gas savings depend on
the number and  duration of shutdown periods.   In addition,  changes in operating procedures
associated with installation of the static seal must be considered in determining net gas savings.

Normal compressor shutdown procedures  vary  from station to station.  In general, the  following
procedures are used:
        •   Depressurize/blow-down all  pressure  (except  a small residual  pressure to
           prevent air inleakage) and vent the gas, either partially or completely, to the
           atmosphere,
        •   Maintain pressure, either with or without the unit isolation valves open,
        •   Depressurize to a lower pressure, either venting the gas to the atmosphere or to
           the station fuel system, or
        •   A combination of these procedures.
Adding a Static Pac to a compressor will result in varying levels of net gas savings and emission
reductions depending  on the current shutdown procedure. Evaluation of net emission reductions
for Static Pac operation requires  quantifying any  significant leak rate  changes resulting from
normal Static Pac operation and related changes in operating procedures.

A station that currently leaves compressors pressurized during shutdown will realize net savings
simply from the decrease in the rod packing leak rate due to the action of the static seal.  If a station
that currently blows down its compressors during shutdown were to add static seals, it is presumed
that the station would also go to a pressurized shutdown condition.  In this case, the savings result
from the eliminated blow-down and the unit valve leak (the unit valves are prevented from leaking
because the unit now remains pressurized). There is also the potential for increases in emissions at
components now exposed to pressure during shutdown.  This includes the rod packing (if the static
seal is not 100 percent effective, valves, fittings, and other components.

-------
Table 1 shows the relationship between operating procedures and emission changes for common
compressor system shutdown scenarios.

   Table 1. Common Shutdown Scenarios and Emissions Changes with Static Seals
CH4 SOURCE
Current shut
down procedure
Procedure with
static seal
CASE #1
Pressurized
shutdown with
unit valves open
n/c
CASE #2
Blow-down/
100% vent to
atmosphere
Pressurized
shutdown
CASE #3
Pressurized
shutdown with
unit valves
closed
n/c
CASE #4
Depressurize to a
lower pressure
a. Vent to
atmosphere
b. Vent to fuel
system
Pressurized
shutdown
CASE #5
Depressurize/ vent
to fuel system,
then vent to the
atmosphere
Pressurized
shutdown
Emissions Changes with Static Seal
Rod Seals
Blow-down
volume
Unit valves
Blow-down
valve
Pressure relief
valve
Misc. valves,
fittings, flanges,
etc.
Decrease
n/c
n/c
n/c
n/c
n/c
small increase?
Decrease
Decrease
Increase
Increase
Increase
decrease
n/c
n/c
n/c
n/c
n/c
small increase?
a. decrease
b. decrease
a. decrease
b. n/c
a. increase
b. increase
a. increase
b. increase
a. increase
b. increase
small increase?
decrease
decrease
increase
increase
increase
NOTES: n/c - no change/effectively no change
The  evaluation of the  Static  Pac performance at  ANR Pipeline  Company will  focus  on two
operating conditions, the pressurized when in idle mode operating condition (Base Case 1) and the
compressor blow-down when idle operating condition  (Base  Case 2).   These  two  operating
procedures  appear to represent the normal approach to  compressor shutdown.  Based on data
contained in the GRI methane study (GRI 1996), about 57 percent of idle transmission compressors
are maintained at operating pressure and 38  percent are blown-down to atmospheric.  A smaller
percentage (less than 5 percent) are blown-down to a lower pressure (in some cases venting to the
fuel system).  The following discussion highlights the verification issues for each case and outlines
measurement and data collection activities needed to implement the verification test.
                                          -7-

-------
Case 1.  The baseline for this case is a compressor that normally maintains full operating pressure
during idle periods.  The addition of the Static Pac should eliminate leaks that occur during idle
periods and cause no increase in the leak rate while the compressor is operating.

Continuous measurements of the rod packing leak rate will be made during the entire test period.
Emissions reductions will be determined by comparing uncontrolled emissions (with the Static Pac
disabled) with emissions controlled by the Static Pac. A second measure of uncontrolled emissions
will be obtained based on measurements of emissions during idle periods from a second rod on the
same engine using conventional  packing.   This  arrangement will be  repeated on two  separate
engines in order to provide a more reliable and robust data set.

Continuous leak rate measurements on the control rods during operation will be used as a  baseline
for verifying that the Static Pac does not cause any increase in the operating  leak rate of the rod
packing.

Disabling the  Static Pac is a manual operation that will  require Center test personnel or  a site
operator to manually disable the  Static Pac during a shutdown period for a  sufficient period to
allow the  packing to cool and representative measurements to be obtained (several hours).  This
will  require  a scheduled  shutdown  and  will  be conducted during  each  of three intensive
measurement periods to be conducted at the start of the test, at the end of Phase I, and at the end of
the test.  If additional quantifications are needed (due to variability in the leak rate or changes in
operating conditions), site personnel can be called upon to perform additional shutdowns.

In addition, it is possible that there is a relationship between operating emissions and idle emissions
with the Static Pac disabled.  Data collected during the intensive measurement periods will allow
assessment of whether there  is  a  correlation.  If a correlation is found, then  operating emissions
immediately before  and after each  shutdown  period could  be used  to refine the analysis by
providing greater  capture of emissions changes over time.

To verify that the Static Pac does  not cause any increase in the operating leak rate of the rod
packing,  continuous leak rate measurements will  also be made on a second unit fitted with new
seals at the time of Static Pac installation.

-------
Because the unit pressure is essentially unchanged during both operating and idle periods, all other
component leak rates (pressure relief valve, blown-down valve,  unit valves, and miscellaneous
flanges, valves, and fittings) can be anticipated to remain constant after installation of the Static
Pac. This will be verified by manual measurements before and after installation.

Case 2.  The baseline for this condition is a compressor that normally blows down from operating
pressure  to a minimum  pressure level  during  idle periods.   At such  times, the pressure  on
compressor components is reduced to near zero and any rod  packing, pressure relief valve and
blown-down valve leaks cease.  However, any leaking gas from the unit valves  isolating the
compressor is lost.  The gas leaks into the compressor system and passes to the atmosphere through
the open blown-down valve to the open-ended blow-down line.  Based on available data, this loss
from the unit valves can be  substantial (see Table 2). To address this, unit valve leak rates will be
measured (manually) periodically during the study.

In addition, the compressed  gas contained in the  compressor lines is lost during the blow-down.
This will be  calculated  based on  known volumes of compressor components and  operating
pressure.

For Case 2, emissions reductions are gained by changing the shutdown procedure to leaving the
compressor pressurized during idle periods. This eliminates losses due to the blow-down volume
and unit valve leaks.  The  Static Pac serves to eliminate the  increase in rod packing emissions
during idle periods that results from leaving the unit pressurized.

In order to determine net gas savings, any increase  in leaks from  the pressure relief valve, blow-
down valve, and various flanges, connectors, and valves due to leaving the unit pressurized must be
measured.  The sum of any increase in leaks from these components  offsets the gas savings
described above.

Components that require quantification of gas leak rate during the evaluation are identified in Table
2. The table also presents estimates of the  leak rate for each component (GRI 1996) and indicates
gas savings or loss associated with each component for each test scenario.

-------
                         Table 2. Leak Sources, Emissions, and Gas Savings
Emissions Sources
Compressor Seal
Compressor Seal

Blow-down Volume
Unit Valves
Blow-down Valve
Pressure Relief Valve
Misc. Components
Compressor Seal
Compressor Seal
Notes
Unit Idle, Pressurized
Unit Operating

Loss eliminated due to
change in operating
procedure associated
with static seal
Loss eliminated due to
change in operating
procedure associated
with static seal
Unit Idle, Pressurized
Unit Idle, Pressurized
Unit Idle, Pressurized
Unit Idle, Pressurized
Unit Operating

Gas Savings/Loss Associated with
Emissions Packing (Mcf/yr)
high
2,212
(0)
2,212
2,750
2,916
(587)
(256)
(75)
(0)
(0)
4,748
low
84
(0)
84
220
67
(235)
(0)
(52)
(0)
(0)
0
avg
670
(0)
670
825
1,491
(436)
(149)
(64)
(0)
(0)
1,668
Gas Savings/Loss
Case 1 Savings
Case 1 Loss
Case 1 Net Gas
Savings
Case 2 Savings
Case 2 Savings
Case 2 Loss
Case 2 Loss
Case 2 Loss
Case 2 Loss
Case 2 Loss
Case 2 Net Gas
Savings
2.2.2.  Phase I Static Pac Evaluation

Document Initial Gas Savings for Baseline Operating Conditions (Case 1. Case 2)

Initial gas leak prevention effectiveness will be determined and reported in the Phase I Report after
at least 4 weeks of continuous monitoring data and two sets of manual leak tests have  been
collected and analyzed.  Net gas savings will be determined separately for Case 1 and Case 2 as
discussed above.

For Case 1, the savings  consist solely of the gas prevented  from leaking from the  rod packing
during idle periods. This is the difference between the leak rate without the Static Pac and the leak
rate (if any) with the Static Pac.  The leak rate without the Static Pac (uncontrolled emissions) will
                                           -10-

-------
be measured directly by disabling the  Static  Pac during  scheduled shutdowns.  It may  also be

possible  to  use the running leak rate (when  the  Static Pac  is inactive)  as  a surrogate  for

uncontrolled emissions  - provided that a sound correlation can be established between the  running

leak rate  and true uncontrolled emissions.  Finally, if it is determined that the Static Pac causes any

increase in emissions during operation, these emissions must be subtracted from the gas savings.


This is represented mathematically in Equation 1.


                           G_1i = [Qd  -Qs]*t     (Eqn. 1)

Where,
G_l = gas savings for Case 1, scf
Qd - uncontrolled leak rate (Static Pac disabled), scfm
Qs - average hourly leak rate (cfm) during shutdown, scfm
t - shutdown period (minutes) = [te - ts]
       ts - time at start of shutdown period
       te - time at end  of shutdown period
I = shutdown interval


Alternatively,  if correlation  analysis supports using running emissions before and  after each

shutdown period as a  surrogate  for uncontrolled emissions, then  the  refined formula  for gas
recovery is given by Equation la.


                    G_1 i = [Qr(te) - Qr(ts)]/2 - Qs] * t     (Eqn. 1 a)


where,
Qr(t) - running leak rate (cfm) at time "t" - corrected for correlation with the uncontrolled rate Qd
Qs - average hourly leak rate (cfm) during shutdown
t - shutdown period (minutes) = [te - ts]
       ts - time at start of shutdown period
       te - time at end  of shutdown period

In both cases (Equations 1 and la), the Total gas savings for the test period is



                         G_1 = ZG_1j -Vm         (Eqn. 1b)
                                          -11-

-------
where Vm is the increase in operating emissions (if any) over the test period due to the Static Pac.
Vm will be determined based on comparison with rod leak rate measurements on a duplicate unit
fitted with new seals at the same time the Static Pac is installed.

An important  consideration in this approach is that it may take some time after start up for the
running leak rate to stabilize.  Thus, Qr(te) should be obtained once the leak rate has stabilized.  For
the Phase 1 evaluation, cumulative gas savings and hourly average gas savings during idle periods
will be calculated and reported as Case 1 gas savings. Details of the measurement methods, tests to
be conducted,  QA/QC and schedule are given in Section 5.

For Case 2, gas savings consists of the blown-down volume (times the number of idle periods) and
the unit valve  leak rate (times the duration of idle periods).  In addition, there are gas losses due to
leakage from  the blown-down valve, pressure relief valve and miscellaneous components (see
Table 2).  An  additional loss is any gas that escapes past the Static Pac (since the baseline for this
case is  a blown-down compressor, rod packing leakage would be  zero).  For Case 2, the gas
savings for each idle period will be calculated as follows.

    G_2j = BDV +  Quv * [te - ts] - [Qprv + Qbdv + Qmisc + Qs(t)] * [te - ts] (Eqn. 2)

Where,
Gj is the gas savings cf
BDV is the blow-down volume, cf
Quv is the unit valve leak rate, cfm
Qprv is the pressure relief valve leak rate, cfm
Qbdv is the blow-down valve leak rate, cfm
Qmisc is the aggregate leak rate for miscellaneous components
Qs(t) is the leak rate (cfm) during shutdown at time "t"
The total gas savings for the test period is

                          G_2 = ZG_2j  -Vm        (Eqn. 1b)

where Vm is (once again) the total increase in operating emissions (if any)  over the test period due
to the Static Pac.
                                           -12-

-------
The blow-down volume for the test unit has been calculated by ANR personnel to be 200 cf at 800
psi or roughly 55,000 scf.  For the other components, manual leak rate measurements will be
needed.  These measurements will be made during intensive measurement periods at the start and
end of the Phase 1 evaluation.  Details of the measurement methods, tests to be conducted, QA/QC
and schedule are given in Section 5.

Document Capital. Installation, and Shakedown Requirements and Costs

C. Lee Cook has prepared installation instructions for the Static Pac system.  These instructions are
outlined in Table 3.  The Static Pac will be installed by ANR site personnel, with supervision and
guidance provided by a C. Lee Cook engineer. The ANR staff will also conduct leak checks on the
complete system, and correct loose fittings or valves.  Center personnel will be on-site throughout
the installation and shakedown process, and will document any  modifications made or difficulties
encountered.  The  Center  will  also  document key decisions made  regarding  placement  of
equipment or adjustments made for site-specific conditions.

C. Lee Cook will provide an Operator's Manual that provides instructions on start-up activities and
routine monitoring and maintenance requirements (see Appendix  A and Appendix B).  For the
start-up instructions, the manual  lists  step-by-step procedures  for: initiating Static Pac start-up,
obtaining optimum gland activation pressure, checking for its design activation pressure, and
verifying functionality of integral monitoring sensors. The Center will document any problems
encountered or  changes made to the start-up  and  shakedown activities,  and report the  final
procedures in the Verification Report.

To determine the payback period, it will be necessary to document accurately  Static Pac capital and
installation costs.  Table 4 is a listing of the capital equipment required to assemble and install the
Static  Pac.  This  table includes  preliminary cost data, and identifies where final data will be
obtained.  The list is specific to the  conditions encountered at the  host site (e.g., shaft diameter.)
The staff performing the installation will provide the piping, valves, and fittings.  Although the list
is  believed to  be complete, C. Lee Cook may add or  delete items necessary to accommodate site
specific conditions.  The Center will obtain the "as-built"  equipment list  from C. Lee Cook after
installation is complete, and will document total equipment and installation costs based on invoices
and labor logs.   The Center will multiply the  logged hours by the hourly rates charged by all
participating contractors and ANR staff to calculate total installation cost. The sum of the capital
                                           -13-

-------
equipment costs and installation costs will represent the net Static Pac initial cost.  This cost will
not include the capital or installation costs associated with the flow monitors and other devices
required for the verification test.
                  Table 3.  Preliminary Static Pac Installation Instructions
A.
B.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
The Static Pac sealing system is installed in accordance with standard station
procedures for replacement of rod seals.
The Static Pac control will automatically engage and disengage the compressor
packing Static Pac with commands from the engine control system when properly
installed. Install as follows:
Disconnect the starting air command signal from the engine control system from the
pilot of the starting air valve and connect it to bulkhead Number 5 of the Static Pac
control.
Connect the pilot of the starting air valve to bulkhead Number 1 of the Static Pac
control.
Install a tee fitting in the ignition command line from the engine control panel and
connect the branch of the tee to bulkhead Number 3 of the Static Pac control. (If an
ignition-ON command signal is not available, the fuel-ON signal can be used instead.)
Connect bulkhead Number 2 to pilot (operator) of high pressure valve 100-1.
Connect high-pressure gas supply to blocked inlet port of valve 100-1.
Connect Static Pac to opposite port.
Pipe third port (vent) to a safe, unrestricted vent system to atmosphere.
Connect bulkhead Number 4 to indicator 19 R-l, after indicator has been positioned
in desired location.
Connect 60 to 125 psig filtered gas supply to bulkhead Number 6.
Installation is complete.
                                            -14-

-------
              Table 4. Documentation of Initial Capital and Installation Costs
Description
Units
Required
Price/Unit
Source of
Data
Capital Equipment Costs:
Static Pac Case for 4: Rod GMW
Renewal Rings
Automatic Control PAY 502957
Miscellaneous Tubings, Fittings
2
2
1

$2,650.29
$797.79
$1,638.00
$200.00
C. Lee Cook
C. Lee Cook
C. Lee Cook
Station
Purchase
Records
Installation Costs:
Static Pac Assembly Installation
(includes time required to remove cylinder,
install Static Pac, make Control System
adjustments, and check the system
16 hours
$45 -$65 /hour
Station
Maintenance
Logs
2.2.3.  Phase II Static Pac Evaluation

The Phase II evaluation represents an extended period of performance testing and includes trends
analyses to project emissions beyond the period of the field test.  Calculation of the payback period
based on these  measurements and analyses  is another key element of Phase II.  Phase  II will
represent up to 4 months of continuous rod packing leak rate measurements and at least 3 intensive
periods of manual measurements.  A discussion of verification issues and actions  for each Phase II
verification parameter are given in the following sections.

Document Annualized Gas Savings for Primary Baseline Operating Conditions

Case 1 and Case 2 gas savings for each idle period during the entire  field test will be computed in
the same manner as for the Phase  1 testing (see Equations 1 and 2).  Since the test will not span an
entire year, it will be necessary to project gas savings over this longer period.  The most direct
method would be to simply compute average gas savings over  the  study period (for Case 1 and
Case 2) and multiply by the number of expected idle hours during a year. However, this approach
could yield an overly conservative estimate of annual gas savings - especially for Case 1 (see the
"Average Gas Savings" in Figure 2).
                                         -15-

-------
It is expected that rod packing emissions (and possibly the leak rates for other components) will
increase  over time.  Since Case  1  gas savings are due entirely to eliminating rod packing leaks
during idle  periods, neglecting an  increasing leak trend would  lead to an underestimate  of gas
savings over  an extended period of  time.  It is  also possible that leak rates for components
contributing to Case 2 gas savings and losses could change over time.  Thus, it is  necessary  to
consider any trend in emissions from all the components of interest that is revealed by the test data.

To  determine annual gas  savings, an increasing trend in  gas savings in the test  data will be
projected in two straightforward  ways: a conservative case, and a likely case.  The  conservative
case assumes that the gas savings rate after the test will not be lower than the gas savings rate at the
end of the test (unless a component is repaired or  replaced).  The likely case attempts, based on
available data, to project future increases in emissions, and take this into account in calculating gas
savings (see Figure 2).
   ro 2
            Shaded areas represent gas savings
            	 Study average
            I    I Measured during study
            I    I Conservative Projection
            I    I Likely Projection
                      M easured
                      Savings
            Time (Months)
                                                                                          12
                            Figure 2.  Methods of Projecting Gas Savings
Document Methane Emission Reduction

The net methane emission reduction is simply the cumulative gas savings calculated as described in
the previous sections. The measured leak rates for the major components will be reported to allow
users to assess the trends observed, use alternate assumptions and data interpretations, and apply
results of this evaluation to differing operating conditions as needed.
                                            -16-

-------
Calculate and Document Static Pac Payback Period

Payback occurs when the capital and operating costs (including cost of money) of the Static Pac are
balanced by the value of the gas  saved.  The operating and maintenance costs for the Static Pac
system is expected to be minimal, but will be documented and included in payback calculations.

Complete O&M logs  on both the Static  Pac  and the compressor will be maintained.  This will
include  selected monitored parameters for the engine/compressor system, and manual logs of key
O&M activities. Table 5 lists the operational and maintenance parameters that will be collected.

         Table 5. Operational and Maintenance Data to be Collected During Testing
Description
Source of Data
Static Pac, Compressor, and Engine Operating Parameters Logged:
Engine rpm
Rod temperature (both rods)
Unit discharge pressure
Unit discharge temperature
Unit suction pressure
Static Pac actuation status
Operating
Station
Data
Maintenance Requirements Logged:
Labor required to start/stop the system, conduct routine leak
checking on the entire Static Pac assembly, repair leaks, respond
to malfunctions, and perform Static Pac adjustments
Equipment replacement or repair costs for failed units
Labor required to replace or repair failed units
Compressor/Engine downtime costs caused by failures in the
Static Pac apparatus
Operator logs
Periodic checks on Static Pac actuator pressure and adjustment as necessary will be performed.
After initial measurements are complete, the site operators will perform routine Static Pac control
system operational  checks in  accordance with the O&M instructions for the  Static  Pac, and  if
                                           -17-

-------
significant deviations from specifications are present, the Operator's Manual will be followed to

determine appropriate action.  The time required to conduct these activities will be logged.  In the

event that any of the  Static Pac components fail and need repair or replacement,  ANR site

personnel will log the purchase  cost of each component, and the time and materials expended in

installing and checking the new  components.  Although unlikely, if failure in the Static Pac system
causes malfunctioning of the compressor or the engine, ANR site operators will be consulted to help
quantify the costs associated with the failure.


The procedure for calculating payback is outlined below.

1.  Total cost will be  determined by  adding the  Static Pac capital costs, installation  costs, and
   O&M costs determined as outlined above.  Capital costs will be amortized over the payback
   period assuming a discount  rate  of return of 10 percent.  Payback is achieved when the total
   cost = the value of the gas saved.

                    Total Cost = (Gas Savings) * (GP)    (Eqn. 3)

   Where:  Total Costs = sum of capital, installation, O&M costs and cost of money
            Total Gas  Saved = net volume  of methane (SCF) required to achieve payback
            GP = gas price ($2/MCF)

2.  Total gas savings over the payback period will necessarily include measured and projected values.
   Savings will be projected in the same manner as described for determining annual gas savings. For
   each case,

             Total Gas Saved = Gas  Saved Test + Gas Saved Est  (Eqn 4)

   Where:     Gas SavedTest = total  measured net volume of gas saved during the test period.
               Gas SavedEst = total  estimated net volume of gas to be saved after the test period.
The payback projections will, likewise include a conservative and a likely case.  These will be
calculated just as described for projecting annual emissions reductions - except over the payback
period.
2.3.    SITE SELECTION, DESCRIPTION, AND STATIC PAC INSTALLATION



2.3.1.  Site Selection and Description


The natural gas  transmission engine/compressor  selected  to host this evaluation is operated  by

ANR Pipeline Company.  This station  operates six  Cooper-Bessemer engines (8-cylinder, 2000

Hp), each equipped with two-stage reciprocating compressors operating in series (4,275 cubic inch
                                          -18-

-------
displacement, 4" rods).  Geographic location was not seen as a significant factor in the evaluation,
but extremes of environment, very hot or very cold, were avoided.

The low speed engines at the test site are not typical of newer high speed engines in use, but the
rods and packings have the same basic design and functionality as most reciprocating compressors
used now  and planned  for use  in the  future  within  the  transmission  sector.   Reciprocating
compressors are the dominant types in use, although newer compressor designs, such as  screw-
type, are beginning to be placed into service.  The rod packing system used at this station is typical
of those being built or retrofitted within the  industry.  The  rod  packing is essentially a dry seal
system, using a few ounces of lubricant per day.  Traditionally, wet seals, which use  high-pressure
oil  to form a barrier against escaping gas, have been employed.  According to the natural Gas
STAR  partners, dry seal  systems  have come  into  favor  recently  because  of  lower  power
requirements, improved compressor and pipeline operating efficiency and performance, enhanced
compressor reliability, and reduced maintenance.  The STAR industry partners report that about 50
percent of new seal replacements consist of dry seals.

In order to provide  necessary experimental  controls (see Section  2.2), the Emissions Packing will
be installed on one compressor on each of two engines (engine Id's 801  and 802). The packing on
the second rod on each  engine will be replaced with a new packing  at the same  time that the
Emissions Packing is installed. The two engines are the same age and have similar operating hours
(this is part of ANR's operating practice).  They were both overhauled at the same time in 1996,
including replacement of the rod packings.  Actual operating hours on each engine will be  logged
at installation.  ANR's operation and maintenance practices are the same  for each of the units.
2.3.2.   Static Pac Installation and Operation

The host site presents a typical installation for the Static Pac system and no application specific
engineering is required.   The Static Pac system is designed to  accommodate the conditions
(pressure, existing sealing system) at the test site. The Static Pac will be installed in a  modified
packing case  with new seals.  A representative of C. Lee  Cook has  visited the test site and
confirmed all necessary requirements. The Static Pac will be installed by a Cook representative on
one rod on each of two engines.  This will require two separate actuation systems.  Costs used for
determining payback will be based on equipment needed for installation on a single engine with a
                                           -19-

-------
single actuator. As normal operations dictate, operators will perform and document normal system
maintenance and adjustments to maintain Static Pac performance, maximizing gas containment.
2.4.    FIELD TEST OVERVIEW

The  field testing will include both continuous and  manual  measurements.   The continuous
measurements will quantify the gas savings from the rod packing leaks due to the action of the
Static Pac during idle periods.  These measurements allow quantification of the Case 1 gas savings
(for  a compressor that remains pressurized while  shut down).   The manual  measurements are
necessary to quantify leak rates for the unit valves, blown-down valve, pressure relief valve and
miscellaneous components that make up additional data needed to quantify Case 2 gas savings (for
a compressor that would normally blow-down prior to installing the Static Pac).
2.4.1.  Continous Leak Rate Measurements

At the test compressors, emissions from the packing case vent and fugitive emissions from around
the rod are both vented into the distance piece or doghouse and then vented to atmosphere through
the doghouse vent.  The doghouse vent and oil drain are the only paths by which the leaking gas
can leave the doghouse. For the test, the doghouse drain will be sealed using a liquid trap so that
all emissions will be forced out the doghouse vent.  To measure these emissions, flow meters will
be installed on the doghouse vent lines for each of the compressors to be tested.

The station operates automatically and compressors are shut down or brought on  line on demand.
Continuous  measurements and automated  data logging are needed  to be  certain of measuring
emissions during each shutdown period.  The meters must present a minimal restriction to flow in
order not to influence the leak rate, have a wide range, and be resistant to oil vapor present in the
emissions.

The meters  selected for the test are a type  of rate meter (similar to a rotameter)  designed for
measuring methane emissions from sludge digesters, landfills, and other low-pressure applications.
They  have wide range (25 : 1 turndown), a very  low pressure drop (2 -inches water) and should not
be affected by oil mist present in the emissions. The meters produce a 4-20 mA full-scale linear
                                          -20-

-------
output that will be recorded locally on a datalogger equipped with modem communications. Hourly
averaged leak rate data will be stored continuously on site and retrieved remotely once each day for
review.  The data will be archived at the Center's Research Triangle Park, NC facility.

During installation and  during periodic intensive measurement periods, the methane concentration
of the gas leaking from the doghouse will be measured with a portable hydrocarbon analyzer. At
these times, flow meter performance will be checked against direct measurements using GRI's Hi-
Flow™ device.
2.4.2.  Manual Leak Rate Measurements

Manual measurements will be made of leak rates for the unit valves, blow-down valve, pressure
relief valve and miscellaneous components.

The  leak  rate for the unit  valves will be measured  at an existing port located  immediately
downstream of the unit valve  in the suction  line to the  compressor (see Figure 3).  With the
compressor shut down and blown-down, any unit valve leak will exit through the opened port. The
leak rate will be measured with GRI's Hi-Flow™ device.
                           Figure 3. Unit Valve Sampling Port
                                          -21-

-------
The leak rates for the blow-down valve and pressure relief valve will be made with the unit shut
down and pressurized.  The leak rate for the  blow-down valve will be measured  at the flange
located at the exit of the valve (see Figure 4).  To make this measurement it will be necessary to
unbolt the flange.  The flange will then be separated about 1-inch and a disk will be inserted and
clamped into place.  The disk will capture the leak and direct it outward.  The disk will be made of
high-density polyethylene about  1-inch thick and machined to fit the flange.  A  borehole will be
provided radially into the disk that will allow any leaking gas to escape for measurement using the
Hi-Flow.
                      Figure 4. Blown-down Valve Sampling Location

The pressure relief valve normally vents through a 4-inch standpipe extending to the roof of the
compressor building. The simplest way to measure the leak rate is to cap the standpipe, allowing a
port to channel emissions for measurement using the Hi-Flow.

The miscellaneous components at the test site consist of metering ports and valving used to recover
gas to the fuel system during shutdowns (the host station normally vents to the fuel system during
shutdowns). Significant leaks are not expected at these locations; however, all components will be
soap screened and any leaks identified will be quantified using the  Hi-Flow or the EPA protocol
tent/bag method, where needed.
                                          -22-

-------
The manual leak rate measurements will require scheduled shutdowns that proceed as follows:
       •   Unit shutdown - remains pressurized,  leak rates for the pressure relief valve,
           blow-down valve and miscellaneous components will be  measured (several
           hours)
       •   Static Pac disabled, Hi-flow determination  of leak rate and continuous flow
           monitoring (at least one hour)
       •   Unit blown-down, unit valve leak rate measured (about one hour)
       •   Unit brought back on line
Nearly one full day will be needed to conduct this suite of measurements.

The  station has  agreed  to a limited number of scheduled shutdowns.   These will be  used to
characterize the quantities as discussed above, but will not contribute to the gas savings during idle
periods.  It is  proposed to conduct 3  such scheduled shutdowns during the first week of the test,
after installation of the static seal and after the rod packing (with the static seal) has had time to
stabilize (approximately 24 hours). In order to address possible changes over time, this series of
measurements will be repeated on two other occasions  at approximately 2 months and 4 months
after installing the SS. Thus, the manual measurements  will be repeated a total of 9 times in order
to capture the magnitude and variability of the various quantities involved.


2.5.    SCHEDULE OF ACTIVITIES

A site survey visit has already been completed.  Field testing is scheduled to begin in June  of 1999,
but the exact date of start-up will depend on the availability of equipment and the extent to which
difficulties are encountered during start-up and shakedown. Uncertainty in the start-up date impacts
the dates for the subsequent activities in the schedule.

Allowing  time for data analysis  to be completed, a draft Phase I Report should be available for
review in  September, 1999.  All field activity should be completed by October 30, 1999. A draft
Phase II Report  should be available  no  later than  December 31, 1999.  A  final Phase I Report
should be available for distribution in November, 1999 and a final Phase  II Report  should  be
available for distribution in February,  2000.
                                           -23-

-------
                             3.0   DATA QUALITY OBJECTIVES

Data quality objectives state the values of key data quality indicators for each measured quantity.
These objectives must be achieved in order to draw conclusions from the measurements with the
desired level of confidence.  The process of establishing data quality objectives  for measurements
starts with determining the desired level of confidence in the primary verification parameters (e.g.,
confidence level in the verified payback period).

The next step  is to identify all measured values impacting the primary verification parameters, and
determine  the  error allowed.   Formal error propagation techniques can  help  to systematize these
determinations.  With error propagation, the cumulative effect of all measured variables on the primary
data quality objective can be determined.  This allows  individual measurement methods to be chosen
which perform well enough to satisfy the data quality objective for the primary verification parameter.

The primary quantitative objective for this study is to establish the payback period associated with
installation and use of the Static Pac.  Inherent in this  objective is documentation of the Static Pac's
gas loss reduction performance.  Based on meetings with the Stakeholders, a payback period of
three years would represent acceptable performance.  An error in this value  of about +/- 3 to 4
months, or about 10 percent, is used as a basis in determining the data quality requirements.

Payback occurs when the total cost of the Static Pac  (amortized capital and installation costs, and
operation  and maintenance  costs) equals the  savings that the  system provides  (net gas loss
prevented). For the field test, the costs will be based on actual costs and the errors are zero.  Gas
loss  reduction  will  be measured directly  during the  study,  then projected for the  periods
immediately before and after the test is done. Specific data quality objectives address the error in
the direct measurements only;  however, a discussion of the  errors in the projections is also
provided below.
3.1.     CONTINUOUS MEASUREMENTS

For a three year payback to occur for Case 1, the gas savings rate would have to average about 9.5
cfm - or 4.75 cfm per rod (assuming $10,000 total cost for two rods, gas value of $2/MCF, and 33
percent downtime). This implies a minimum gas savings rate of interest of about 0.5 cfm per rod
(-10 percent of 4.75 cfm) based on a 10 percent error in the payback period.
                                           -24-

-------
As  discussed above (see Equation 1), the gas savings for each idle period will be taken as the
difference between the leak rate with the static seals disabled (or a surrogate using the running leak
rate) and the leak rate with the static seals engaged.  By error propagation, the total error in the
difference is the sum of the absolute error in each measurement (in measured units). The accuracy
of the  meters is +/-  2 percent  full scale and the full-scale range of the meters is about 3-scfm
methane, so the absolute error is +/- 0.06 scfm.  The total error in the  difference (the gas savings) is
then +/- 0.12 scfm. This is well below the minimum leak rate of interest, and meets the 10 percent
data quality objective for a three year payback**. For payback periods longer than about 9 years
(gas savings  rates  less than 1.6 scfm/rod), the +/-  10 percent objective might not be met. The
minimum response of the meters chosen for the test is to a flow of about 0.125-scfm methane.

**For completeness, it should be noted that this assumes that the percentage errors during each idle
period  are roughly consistent. This is because the total gas savings is computed as the sum of the
gas savings for each idle period over the duration of the test.  By propagation, the error in the total
gas savings is the sum of the errors in the gas savings for each idle period. If the  fractional, or
percentage error for each idle period is the same, then the percentage error in the total gas savings
is the same as the error for each  idle period.


3.2.    MANUAL MEASUREMENTS

Manual measurements will be  based on use of GRI's Hi-Flow device and/or EPA's  protocol
tent/bag method.  The GRI Hi-Flow device draws a metered volume of ambient air past the leak
interface to capture the leaking  gas. Flow metering is accomplished using a thermal anemometer
calibrated to flow.   The  concentration  of methane in  the sample  stream is  measured using a
Bascom-Turner CGI-201 hydrocarbon analyzer which has an effective range from about 500 ppm
to greater than 50 percent methane. The leak rate is determined simply as the product of flow and
concentration.

The device can meter sample flows in the range from about 4 to 8 scfm.  This gives the device an
effective leak rate quantification range from about 0.02 to 4 scfm.  The device has been shown in
laboratory testing to be able to  quantify leak rates to within  10 percent of the actual value  (Lott,
1995).
                                           -25-

-------
Since the Hi-Flow draws a high volume of air past the sample point, it will be important to take
measures to ensure that the sampler does not act to increase the leak rate by pulling excess gas
from the leak source.  This issue is important for this test since some of the leak points to be tested
are expected to be passive, very low-pressure seeps to the atmosphere. These locations include the
doghouse vent and the unit valve sampling port.

This issue can be effectively addressed with proper sampling technique. The Hi-Flow is capable of
leak quantification over a range of sample flows.   The sample flow used must be no higher than
necessary to capture the leak.   Repeated measurements at different sample flows can be  used to
verify that  this occurs.  Initially, the leak  should  be quantified using the lowest  possible sample
flow.  The measurement is then repeated at a higher flow.  If the measured leak rate remains
constant at both flows, this indicates that the leak has been completely captured and that no excess
gas has been sampled.  If the leak rate increases at the higher flow, this could indicate better leak
capture or sampling of excess gas. To control for this ambiguity, leak capture should be ensured by
constructing a partial enclosure around the  Hi-Flow  sampling hose  and the leak interface that
allows ambient dilution air to enter, but effectively channels all leaking gas to the Hi-Flow.

It is possible that some leaks may not be readily quantifiable using the Hi-Flow device. This would
be the case if the leak interface were such that the Hi-Flow  alone could not capture the leak.  In
such cases, EPA's tent/bag method may be used.  EPA's tent/bag method is nominally accurate to
within +/- 20 percent (EPA 1993), but has been shown to be capable of accuracies better than +/-
10 percent when carefully applied (SRI 1996).  Thus, the methods should be capable of producing
data at or near the desired level of confidence.

As a practical matter, the real limitation on the accuracy and the representativeness of the manual
measurements is their relative infrequency.  Although the frequency  of a measurement does not
affect the accuracy of an individual measurement,  a larger number of measurements does improve
the "accuracy" (i.e., decrease the confidence interval for the mean).  For this reason, the  manual
measurements will be repeated in triplicate during  each of the three intensive measurement periods
planned for the overall test (Phase I and Phase II). If significant variability is encountered in the
three samples, three additional samples will be collected.

The other quantity to be considered for Case 2 is the blow-down volume.  This will be quantified
based pressure readings at the  station controls, and the volume of piping and manifolds in the
                                           -26-

-------
compressor system.  These valves are  critical for station operation and the accuracy of station
metering is carefully checked and documented.   Station calibration records will be obtained and
corded. Unit pressure (measured at the station) will be used to convert the volume to scfm.


3.3.     PROJECTIONS

As discussed above (Section 2.2), projections beyond the test period will  include a conservative
case and a likely case.  In both cases, idle periods will be based on the previous year's operation for
the test unit. In the conservative case, emissions projections are straight lined from the end of the
test  period and the uncertainties  are  small - no  more  than uncertainty  in  the  final set  of
measurements used for the projected value.  In the  likely case, projections will be based on the
trends  in the measured data.  In this case, the uncertainty may be estimated based on the fit of the
projected curve to the measured data.


                             4.0    DATA QUALITY INDICATORS

This section specifies data quality indicators that  will be used as measures of data quality for the
test data and states how values for each indicator will  be determined through calibrations, QC
checks, and other appropriate measures.  This is presented in Table 6.
                                           -27-

-------
Table 6. Data Quality Indicators

Measurement
Doghouse Vent
Emissions


Unit Valve Leak Rate


How down valve leak
rate


Pressure relief valve
leak rate

Msc. components
leak rate

Method
Continuous
flow meter


H-Flow


H-Flow



H-Flow


H-Flow or EPA
Tent/Bag

Range
0.2to4scfin
methane


O.lto4scfin
methane


O.lto4scfin
methane


O.lto4scfin
methane

O.lto4scfin
methane
Completeness/
Frequency
90%ofhounydata
over test period


9 total measurements
(3 sets of 3)


9 total measurements
(3 sets of 3)


9 total measurements
(3 sets of 3)

9 total measurements
(3 sets of 3)

Accuracy
2% full scale,
or+/-0.2scfin
methane


10%


10%



10%


10%


Precision
2 % of reading


10%


10%



10%


10%

How Verified/
Determined
Comparison
against manual
flow tube
measurements
Laboratory
calibration against
NIST certified
mass flow meter
Laboratory
calibration against
MST certified
mass flow meter
Laboratory
calibration against
NIST certified
mass flow meter
Repeat
measurements
-28-

-------
                 5.0   SAMPLING/ANALYTICAL AND QA/QC PROCEDURES

5.1.     CONTINUOUS FLOW MEASUREMENTS

Static Pac leak prevention is determined using a flow meter on each doghouse vent to measure any
leaks. The meters selected for the test are a type of rate meter (similar to a rotameter) designed for
measuring methane emissions from sludge digesters, landfills, and other low-pressure applications.
Since they are rate meters, they will require external temperature and pressure correction to obtain
flow readings at standard  conditions.    Since the  meters  will be vented to  atmosphere, local
barometric pressure data will be used to correct for  pressure. Gas temperature is not expected to
vary significantly (within data quality objectives), therefore, temperature corrections will be based
on spot checks conducted during the manual measurement intensives.

The  flow meters and barometric pressure transducer will be installed and tied in to the data
acquisition system approximately one week before the Static Pac installation.  This will provide a
record of normal  operations prior  to  installing  the Static Pac  and  allow time for testing and
shakedown.

The flow meters are  designed to operate unattended  continuously after installation.  Configuration
testing will be completed during the initial shakedown period.  This will  include manufacturer's
startup checks and reasonableness and manual flow  checks.  In addition, manual checks of meter
performance will be  conducted using the  Hi-Flow.  A sampling port will be provided upstream of
the meters that allows the meters to be isolated and emissions to vent directly into  the Hi-Flow.
The manufacturer  is providing a calibration certificate for each of the flow meters.  The  meters
should not require re-calibration over the duration of the test.

Once the system is operational, average hourly flow data will be reviewed daily.  The daily  review
will include  reasonableness screening as well as emissions trends and changes that could indicate
system problems.
                                           -29-

-------
5.2.    MANUAL LEAK RATE MEASUREMENTS

A general description of the manual measurements of the leak rates for the unit valves, blow-down
valve, pressure relief valve and miscellaneous components is given in Section 2.4. The manual leak
rate measurements will require scheduled shutdowns that proceed as follows:

       •   Unit shutdown - remains pressurized. Leak rates for the pressure relief valve,
           blow-down valve  and miscellaneous components will be  measured (several
           hours). The gas recovery system will be disabled for the testing.
       •   SS  disabled.  Leak rate recorded by continuous flow monitor and Hi-Flow
           measurement (at least one hour)
       •   Unit blown-down, unit valve leak rate measured (about one hour)
       •   Unit brought back on line
Nearly one full day will be needed to complete this suite of measurements.  The station has agreed
to a limited number of scheduled shutdowns. It is proposed  to conduct three such scheduled
shutdowns during the first week of the test, after installation of the  SS and after the rod packing
(with the  SS)  has had  time to stabilize  (approximately 24 hours).  In order to address possible
changes over  time, this  series of measurements will  be repeated on two other  occasions  at
approximately 2  months  and 4  months  after installing the  Static  Pac.   Thus, the manual
measurements will be repeated a total of 9 times in order to capture  the magnitude and variability
of the various quantities involved.

Detailed procedures for each type of measurement follow.


5.2.1.  Blow-down Valve, and Pressure Relief Valve

The  leak rates for the blow-down valve  and pressure relief valve will be measured with the unit
shut down and pressurized. The leak rate for the blow-down valve will be measured at the  flange
located at the exit of the valve (see Figure  3).  To make this measurement it will be necessary  to
unbolt the flange. The flange will then be  separated about 1 inch and a disk will be inserted and
clamped into place.  The disk will capture the leak and direct it outward radially. The disk will be
made of high-density polyethylene about 1  inch thick and machined to fit the flange.  A borehole
                                          -30-

-------
will be provided radially into the disk that will allow any leaking gas to escape for measurement
using the Hi-Flow. The procedure is as follows:
        •   Shutdown the unit, leaving pressurized. Vent gas recovery system should be
           disabled.
        •   Record suction and discharge line pressures (obtain from station operator).
        •   Unbolt the flange and jack up the blow-down vent pipe approximately 1-2
           inches.
        •   Insert the leak capture disk and clamp into place.
        •   Complete Hi-Flow measurement of leak rate.
        •   Log all results in the field data log.
The  pressure  relief valve normally vents  through a standpipe extending to the  roof of the
compressor building. The simplest way to measure the leak rate is to cap the standpipe, allowing a
port to channel emissions for measurement using the Hi-Flow.  The procedure is as follows:

        •   The unit should still be shut down and pressurized.
        •   Record suction and discharge line pressures (obtain from station operator).
        •   Ascend to the roof of the compressor building - observing station safety rules
           (tie-offs).
        •   Cap vent pipe with ported sampling cap.
        •   Complete Hi-Flow measurement of leak rate.
        •   Log all results in the field data log.

Quality control for the blow-down and pressure relief valve measurements consists of checking the
proper function of the Hi-Flow (function check, zero/span check, leak check) and ensuring that the
Hi-Flow has been  calibrated in the laboratory since the  last set of manual measurements was
performed (a calibration certificate should be attached to the Hi-Flow).  The laboratory calibration
of the Hi-Flow consists of (1) calibrating the  flows against a laboratory mass flow meter which has,
in turn, been calibrated against a NIST traceable orifice transfer standard and (2) calibrating the
hydrocarbon analyzer according to manufactures specification (zero and 2.5 percent methane) with
the  addition  of a span gases at  10,  50, 75 and  100 percent methane.   Documentation  of  all
calibrations will be maintained on file.
                                           -31-

-------
5.2.2.  Miscellaneous Components

The miscellaneous components at the test site consist of metering ports, the bypass valve and the
vent gas recovery system used to recover gas to the fuel  system during shutdowns (the host station
normally vents to the fuel  system during shutdowns). These tests will be conducted with the unit
shut down and fully pressurized.  Significant leaks are not expected at these locations; however, all
components will be soap screened and any leaks identified will be quantified using the GRI High
Flow  (Lott, 1995) or the EPA protocol tent/bag method (EPA  1993).  Sampling/analytical and
QA/QC procedures for these methods are published elsewhere (EPA 1993, Lott 1995).  With either
method, the basic principle is to measure the methane concentration in a known volume of clean air
and compute the leak rate as the product of the methane concentration and the sampling rate.

In both cases, a Bascom-Turner CGI-201  methane analyzer will be used to determine methane
concentration.   The CGI-201 is very stable and need only be calibrated prior to each  set of
intensive  measurements.  Calibration will be done in  the  Center's  Research Triangle Park, NC
laboratory facility using  a certified gas mixture. Field checks consist of an automated zero  cycle
conducted prior to each set of measurements.
5.2.3.  Unit Valves

After the leak rates for the blown-down valve, pressure relief valve, and miscellaneous components
have been measured, the unit will be blown-down to measure the combined leak rate from both unit
valves. Whenever the unit is shut down, the suction and discharge lines are connected via a bypass
valve and line.  The combined leak rate for the unit valves will be measured at an existing port
located immediately downstream of the suction side unit valve. With the compressor blown-down,
the combined leak from both unit valves will exit through the sampling port. The leak rate will be
measured with the Hi-Flow. The procedure is as follows.
           Blow-down the unit (station operator).
           Open the sampling port.
           Complete high flow measurements of the leak rate.
           Log all results in the field data log.
Quality control for the unit valve measurements is the same as for the other manual measurements
using the Hi-Flow for quantification.
                                          -32-

-------
5.3.    DATA ACQUISITION

Each continuous flow meter produces a 4 to 20 mA linearized output over the full-scale range of
the sensor. The barometric pressure transducer provides a linear  0 to 5 VDC output.  All signals
will be logged using a Campbell 2IX data logger with a serial connection to a laptop computer.
The laptop computer will provide  remote access to the logger via modem communications.  A
telephone connection will be made available at the station for daily data downloads  and status
checks.  Power for all components will be provided from the station 24V DC power supply which
is  equipped with a battery back-up system.  The logger will read data continuously and provide
aggregation of sampled data into hourly values.

In addition to the direct measurements, data on engine and compressor operation that relate to the
test are  stored in the station computer and  will be  retrieved  and  transmitted  to  the  Center
periodically.  Table  7 lists all parameters that  will be collected  and stored by  both the  Station
computer and the project data system and their purpose.

Data will be checked daily and summary statistics and  trend plots will be generated to check for
unusual or changing  conditions.  Details of the daily review are given in Section 6. Data will be
automatically downloaded from the DAS each midnight. Summary statistics and time series plots
will be produced from the data and reviewed at the start of each day.
                                           -33-

-------
                    Table 7.  Data Record Contents and Significance
PARAMETER
Date
Time
Rod Seal #1 Leak Rate
Rod Seal #1 Gas Temperature
Rod Seal #2 Leak Rate
Rod Seal #1 Gas Temperature
Baromtric pressure
Engine RPM
Unit Suction Pressure
Unit Discharge Pressure
SIGNIFICANCE


Leak rate
Temp. Correction for #1 leak rate
Leak rate
Temp. Correction for #2 leak rate
Pressure correction for #l/#2 leak rates
Unit on/off status
Unit operating status
Unit operating status
                 6.0   DATA REDUCTION, VALIDATION, AND REPORTING

6.1.    DATA REDUCTION

This  section documents  calculations  that  will  be used  to obtain final  results  from  raw
measurements.


6.1.1.  Continuous Measurements

The continuous flow meters provide a linearized 4 to 20 mA output over the full scale range of the
sensor. The reading in cfm (at calibrated conditions) is given by:

acfm = (mA - 4)/16 * FS

where, mA is the mA output from the  meter electronics and FS is the full-scale reading in cfm.

The meters will be calibrated specific to methane at 70 degrees F. and  1 atmosphere pressure. To
adjust for variations in gas temperature and pressure and correct to standard conditions.
scfm = acfm * (P/760 * 294.26/T)A0.5
                                         -34-

-------
where P is the absolute barometric pressure  (torr) at the  site  and T is the gas temperature (in
Kelvins). The exponent of 0.5 (square root) is necessary due to the physics of rate meters.
6.1.2.  Manual Measurements

Leak rates for the blow-down valve, pressure relief valve, and unit valves are determined using the
Hi-Flow which measures sample flow and concentration.  The flow will be calibrated specific to
methane in the laboratory and the calibration parameters (slope and  intercept) will be  used to
convert directly from the thermal anemometer output (arbitrary units) to flow rate (in scfm) as
follows.

scfm = v * m + b

where v is the anemometer output, m is the slope of the calibration curve, and b is the intercept.

If miscellaneous components are found to be leaking (using soap solution), then the leak rates will
be quantified using the GRI high flow or the EPA protocol (Method 21) tent/bag method. For each
of these methods, the leak rate  is found as the product of the methane  concentration  and the
sampled flow rate.  The methane concentration will be read directly from a Bascom-Turner CGI-
201 analyzer calibrated specific to methane.


6.1.3.  Gas Savings and Payback period

Formulae for calculating gas savings (Case 1 and Case 2) and for determining the payback period
are given in Section 2.2 of this plan.


6.1.4.  Unit Conversions

Engineering units in common  use  at the test site and within the host industry will be used for
reporting and summarizing results.  For pressure, the units are psi or inches water column.   For
flow, the units are cfm and scfm  (1 atmosphere, 70 degrees F or 294.26 K). For gas velocity, the
units are fpm. For concentration,  percentage by volume or ppm are used.
                                           -35-

-------
6.2.     DATA REVIEW AND VALIDATION

Calibrations and quality  control checks for each measurement  are  described in Section 5  -
Sampling and Analytical  Procedures.  Table 8 summarizes the calibrations and  quality control
checks to be performed.  Upon review, all data collected will be classified as either valid, suspect
or invalid. In general, valid results are  based on measurements meeting data quality objectives.
All data are considered valid unless a specific performance limit is exceeded or operational check
is failed.

It is often the case that anomalous data are identified in the process of data review.  All outlying or
unusual values will be investigated as fully as possible using test records and  logs.  Anomalous
data may be considered suspect if no specific operational cause to invalidate the data are found.
All data - valid, invalid, and suspect will be included in the final report.  Report conclusions will be
based on valid data only.  The reasons for excluding any data will be justified in the report. Suspect
data may be included in the analyses, but may be given special treatment as specifically indicated.
All continuous sensor data will be reviewed on a daily basis.  All anomalous or outlying values will
be identified and investigated to find a cause for the unusual condition. Manual measurements data
will be reviewed in the field  as  they are  collected and  any anomolous conditions  will be
documented in field log book and, if possible, corrected.
                                           -36-

-------
Table 8. Summary of Calibrations and QC Checks
Measurement
Continuous flow
measurements
(including flow rate,
temperature and
pressure)
Manual Hi-Flow
measurements
Manual EPA Method 21
Cal/QC Check
Hi-Flow verification
Sensor diagnostics
Data review
Hi-Flow zero, span
and response checks
Laboratory
calibration
Methane analyzer
calibration
Flow system
calibration
Flow system leak
check
When Performed/
frequency
Startup and during bi-
monthly intensive
measurement periods
Startup and daily
Daily
Each measurement
Prior to startup and intesive
measurement periods
Prior to startup and intesive
measurement periods
Prior to startup and intesive
measurement periods
Each measurement
Expected or
Allowable
Result
+/- 10 %
Agreement
No error condition
Reasonable
values/trends
+/- 5 percent of
calibrated values
obtain calibration
slope and intercept
set to standard
obtain calibration
slope and intercept
no leak
Response to Check
Failure or Out of Control
Condition
Identify cause of discrepancy
and correct
Identify cause of any problem
and correct
Identify cause of any problem
and correct, flag suspect data
Identify cause of any problem
and correct
n/a
n/a
n/a
Identify cause of any problem
and correct
6.3.    DATA ANALYSIS AND REPORTING

After data reduction, review and validation, the primary Phase 1 data analyses will include the
following:
       •   Document  initial  gas  savings (methane  emission  reduction) for primary
           baseline operating conditions

           The gas savings and methane emission reduction is the amount of gas that is
           prevented from leaking to the atmosphere either by the static seals themselves
           (Case I) or by changes in shut down procedure associated with installation of
           the static seals (Case II).

       •   Document capital, installation, and shakedown requirements and costs

           This is a broad  assessment of effort and costs required to  install the  Static Pac and
           ensure that it is operating properly. Any problems encountered during installation and
           shakedown - and their resolutions will be described. Capital and installation costs will
           be based on the actual installed cost for the  system. For the test, flow sensors are being
           installed  that might not be  installed in  a normal  situation. Once  the  system is
           operational, host site personnel will be interviewed to determine whether flow sensors
           to document gas savings would be considered necessary in a permanent installation.
                                           -37-

-------
The following is a preliminary outline of the content of the Phase 1 verification report.
                                    Preliminary Outline
                             C. Lee Cook Static Pac Seal System
                                Phase I Verification Report

Verification Statement

Section 1 Executive Summary

               ETV Overview
               Verification Objectives
               Technology Description
               Verification Approach
               Verification Results and Performance Evaluation
                       Initial gas  savings  (methane  emission reduction)  for  primary baseline
                       operating conditions
                       Installation and Shakedown Requirements
                       Initial Capital and Installation Costs
               Data Quality Assessment
Section 2 Verification Test Design and Description
               Static Pac Description
               Site Selection, Description, and Static Pac Installation
               Verification Parameters and Their Determination
                       Initial gas  savings  (methane  emission reduction)  for  primary baseline
                       operating conditions
                       Installation and Shakedown Requirements
                       Initial Capital and Installation Costs
               Sampling and Analytical Procedures
                       Continuous Measurements
                       Manual Measurements
                       Data Acquisition System
               Quality Assurance and Quality Control Measures
                       Calibration Procedures
                       Quality Control Checks, Audits, and Corrective Actions
                       Data Reduction
                       Data Validation
                       Data Analysis and Reporting
Section 3 Phase I Verification Results and Evaluation

                       Initial gas  savings  (methane  emission reduction)  for  primary baseline
                       operating conditions
                       Installation and Shakedown Requirements
                       Initial Capital and Installation Costs
                       Data Quality Assessment
Section 4 Additional Technical and Performance Data from C. Lee Cook Division
References
                                            -38-

-------
The  Phase II  report will  include key data  from the Phase I report.  The Phase II report will
incorporate  the  results from the  entire evaluation process,  and  will  focus on  longer-term
performance of the system and the payback period.  Phase II verification parameters include:
        •   Annualized gas savings for primary baseline conditions
        •   Methane emission reduction
        •   Calculate Static Pac payback period
                                       7.0   AUDITS

An internal systems audit is planned for this test.   The audit will be conducted by Southern's
independently  managed QA  staff.    This  will include  field  verification, procedural, and
documentation  components using this plan as the basis for the audit.  An external audit may  be
performed at EPA's discretion by EPA QA staff or a qualified contractor.  A performance audit  on
sensors used in the study is not considered necessary since the Hi-Flow will be laboratory certified
before each intensive measurement period and the  continuous flow meters  are  rugged devices
designed for industrial applications. An internal audit of data quality will be conducted once data
collection and analyses are complete.  The final report will contain a summary of results from  all
audits.
                                8.0    CORRECTIVE ACTION

Table 8 in Section 6.2 lists allowable values for each of the calibrations and quality control checks
and also indicates actions to be taken in response to an out of control condition.  Other issues may
arise that require corrective actions or plan changes to ensure that data quality objectives are met.
Southern's quality management plan provides general procedures for corrective action that will be
followed in such instances.
                              9.0    PROJECT ORGANIZATION

Southern  Research  Institute's  Greenhouse Gas Technology  Verification Center  has overall
responsibility for planning and ensuring successful implementation of the verification test. C. Lee
Cook is providing the Static Pac technology, equipment, and engineering for the test installation.
ANR Pipeline is providing access to the host site, and logistical and manpower assistance in the
installation and operation of the Static Pac, and in conducting the test. Good working relationships
                                           -39-

-------
have been established between the  Center, C. Lee Cook, and ANR which have proved valuable in
the planning up to this stage.  All parties have signed a formal agreement (documented in the Letter
of  Commitment  and  associated  documents)  specifying  details  of financial,  technical,  and

managerial responsibilities.


EPA's APPCD is the sponsor of the ETV Greenhouse  Gas Pilot and is providing broad oversight
and QA support for the project. The project organization is presented in Figure 5.
          EPA
   ETV GHG Pilot Manager
       EPA - APPCD
     David Kirchgessner
          EPA
    ETV GHG QA Manager
       EPA - APPCD
       Kaye Whitfield
  Southern Research Institute
   ETV GHG Center Director
       Stephen Piccot
ETV GHG Center Deputy Director
     Sushma Masemore
 Southern Research Institute
  ETV GHG Technical Staff
       Eric Ringler
      Tony Eggleston
                  C. Lee Cook
                  Bob Borders
                                                                         Southern Research Institute
                                                                              QA Manager
                                                                              Leslie Schnoll
Southern Research Institute
       QA Staff
       Scott Bell
Southern Research Institute
 ETV GHG QA Coordinator
      Brian Phillips
                              ANR Pipeline
                              Ron Sanders
                             Marylyn Wenzel
                            Figure 5. Project Organization
                         10.0   TEST PROGRAM HEALTH AND SAFETY

This section applies to Center personnel only.  Other organizations involved  in the project have
their own health and safety plans - specific to their roles in the project.


Since the site  is part of a pipeline facility, ANR's safety policies are regulated in part by the US
Department of Transportation.  The Center previously provided a scope of work equivalent to the
                                               -40-

-------
scope  of this plan to the National  Compliance  Management  Service  Company, which is a
compliance and  safety program management company specializing in DOT regulated industries.
Their assessment is that the  Center's on-site job function is not covered  by the  Research and
Special Programs Administration, DOT pipeline safety regulations covered by 49 CFR Parts 192,
193, and 195. If the scope of work changes significantly, this determination would be re-evaluated.

Southern staff will comply with all known  ANR,  state/local and Federal regulations  relating to
safety at ANR's  Celestine compressor station. This includes use of personal protective gear (flame
resistant clothing, safety glasses, hearing protection, safety toe shoes) as required and completion
of site  safety orientation (site hazard awareness, alarms and signals, etc.).

Other than normal industrial hazards, the most significant hazard at the Station is the potential  for
explosive concentrations of natural gas.  Southern plans to use only intrinsically safe apparatus in
the compressor building.  Should use of any equipment not so rated be required, Southern will not
use this equipment until advised by site personnel that it is safe to do so.

Some test procedures will require that special safety precautions be observed.  In particular, when
conducting manual sampling  of the blow-down valve leak rate, the  automated blow-down valve
control should be disabled to prevent a blown-down during sampling.
                                           -41-

-------
                                  11.0   REFERENCES

US Environmental Protection Agency. Appendix A, NSPS Test Methods. 40CFRPart60. 1999.

US Environmental Protection Agency.  Natural Gas STAR Program.   World  Wide  Web
(www. epa.gov. gasstar).

US Environmental Protection Agency.  Protocol for Equipment Leak Emissions Estimates, EPA-
453/R-93-026, June 1993.

Gas  Research  Institute/US Environmental Protection Agency.   Methane  Emissions  from the
Natural Gas Industry.  GRI-94/0257-EPA-600/R-96-080. June, 1996.

Howard,  Touche.  Methane Emissions from  Natural  Gas Customer Meters:  Screening  and
Enclosure studies. Indaco Air Quality Services, July 1992.

Hummel, Kirk E., Lisa M. Campbell,  and Matthew R. Harrison. Methane Emissions from the
Natural Gas Industry, Volume 8:  Equipment  Leaks. GRI-94/0257.25. Gas Research Institute.
Chicago,  IL. June 1996.

Lott, R.A., Howard, T., and Webb M. New Technology for Measuring Leak Rates. American Gas
Association Operating Proceedings. 1995.

Lott, Robert A., Indaco Air Quality Services, Inc. GRI Hi-FlowTM Sampler for Leak  Detection
and Measurement, June 1998.

Southern  Research Institute.  Evaluation of the High Volume  Collection  System (HVCS) for
Quantifying Fugitive Organic Vapor Leaks, EPA/600/SR-95/167, February 1996.

Southern  Research Institute. Environmental Technology Verification Greenhouse Gas Technology
Verification Quality Management Plan.  Research Triangle Park, NC. October, 1998.
                                         -42-

-------
      APPENDIX A

Static Pac Operator's Manual
 Automatic Control System
          -43-

-------
STA7IC-PAC - Compressor Rod Pao'xln? Shut-down Sealing  System
AUTOMATIC CONTROL SYSTEM - Drawing B1-3328-4

                          INSTALLATION AJJD OPERATION

A.  INSTALLATION
The Static-Pae Automatic Control  13 designed  to  bo  used  with a
engine control system which includes  a  pneumatically  operated  cranking  air
valve, pneumatic ignition  switch, and/ar  a  pneuaatieaily operated fuel  gas
valve,

The Statlo-Pac control will automatically engaga and  disengage the compressor
packing Statie-?aeis) with eomcands from  the  engine control  system wtten
properly installed.

The starting air comKsod signal  from  tha  engine  cor.tr si  system is to be
diseonnectec from  tha pilot gf th* starting air  valve end connected to
bu.lXhead ng_._ 5 of  tee Statlo-Pao  control.  Tn*  pilot  of  the  starting air valve
should be comeestd to bulkhgB.4_tio. i_ of  the  Statia-Pac  control.  Install a
tee fitting in the ignition Bor.msnd lin*  from the engine oontrsl panel  and
connect the branch of the  tee to  bulkhead no. 1  of  the Static-?ao control Cf
an ignitisn-ON eo.imiRd signal is  not  av§iisbla,  the fu«l-GK  sigTisi =an  be uaed
instead).  Connect bulkhead .-.p.  2 to  pilot  (operator) of high pressure  valve
• SQ-1 ; connest high pressiire gas  supply to  blocKcd  inlet port of valve 10S-1.,
softnect Ssatie-?ac{s) to opposite port, pipe  third  port  (vent) to a safe,
unrestricted vent  system to atmosphere.  Connect ^ulkhead__no. U to indicator
V5R-1 , after indicator ha.s b«en  positioned  in desired location,  Connect 60 to
12s ?sig filtered  supply air to  bulkhead  no.  _S.   Installation is corr.plete,


3,
Engirss/eomprassor  is  stopped.   Supply sir and engine panel Starting Air and
Ignition  (or  fuel)  coraand  signals are connected to Static-Fas control,  Htgh
pressure  gss  is  connected  to  t'ns  inlat sf oorttrol valv« 100-1 which is pipsd
to Static-Facts)  and  to  vent.

Supply air  ant^ra  through  bulkhead no. 5 to the inlet of vBlve_9-i..  If 9-" is
sot aanually  latched  alos*d,  air  pssssa through 9-1 to bulkhssa no. 2 and
buljggjse  no.  H,   Pressure  frea bulkhead no.__2 ersgagea pilot  (operator) of
valve  '00-'^  sniftir.j valve 3« that high preasurt gas passes through valve  ts
St»tic-?acTs)  on compressor,  causing them to engsgi.  Pressure fro^i bulkhead
no, g  is  routed  to  ts imilcgtsr ;jj^l, shifting it to tht red position to show
that u-.e  £tatio-?aa! s)  ars sngaged,
  Dover  Corporaticn/C. Lee Ccok Division    LauiswilU,  Kentucky    June  3,  1'331
                          -44-

-------
 STATIC -PAC - Compressor Hse  Packing  Shut-down Sealing Sysi.ec             p?ce 2
 AUTCMATIC CONTROL SYSTEM - Drawing 81-3328-J

 Wiisp. the engine control syatea sends  the  starting air cocaand signal to
 biil'icieaj no . ..... St air will flow to  shuttle  valve IS-.'  and on through flow
 control valve ~\~z_ in the unrestricted  direction to  iased lately fill voluble
 chan: tier 2C-5, ahiftir.g valve 9-1 .  Valve  $T1|  when shifted vants bulkheac's g $
 J^,  allowing valve ..... ^00-1_ to vent  the Static-Pac(s) and indiaator ^fr-l which
 returns ta the oisck position.   Tne Static-Pacts) are nnw
 Simultaneously, air is flowing thrcugh  flew  control  valve ;.3-1_ in the
 restricted  direction to slowly fill voliae chamber; 2Q-'<  which la connected to
 the  pilot of valve jM..  Valve 13-1_ is "ad Quoted  for  a 15 second delay after
 wilio1"'  vaIv.e^S_"1 shifts to the open position,  allowing pressure to flow through
 bulkhead  no. 1  to the pilot of starting  air  valve, cranking the engine.  The
 Use delay  inures that the Static-Facts) are disefigag*d before the erglna
 rails.  At  the  proper tine, the engine control panel  will send a Ignitlon-ON
 (or  Fuel-OS) signal  to Static-Pac control bulkhead no.  3.  Tnis signal will
 rsr.ain  'r,t.ile engine  is running and through shuttle valye_!5_-l  vtll keep aignsa
 to pilot  valve  \DO~1 vented, keeping Statia-?ac
-------
                                                  GG'/£/?/C,i££ CfCX

                                                    £r/7r/£ -'
                                                              4 -J3 -8^
                                              C OM
                                                              TO
t
                                                      t2j.
                                i
                                                  \   7to>!
|||J
               s
                           V ^
                                                               rvTS'wr
                                                              / tifttK
       -4 u
       ~  H
       JJ \A
       '
                           y H) "C 
                                                             ?
                                                •/we
                                         ra
                       -46-

-------
      APPENDIX B

Static Pac Operator's Manual
  Manual Control System
          -47-

-------
 STVT1C-PAC - Compressor Bod Packing Shutdown Sealing System
 SASUAL CONT30L SYSTEM - Drawing Bl-33i)6-ii

                           INSTALLATION AMD OPERATION

 A.   tSSTALLATICN
•The  Static-Pac Kar.usl Control is designed to be U3ed with engine/ compressors
 which use manually optrated cranking air valves and manually operated  fuel  gis
 valves.  An  Automatic version 13 available for automatically controlled
 machines.

 The  Static-Pae control will automatically engage and disengage  tne  compressor
 packing Statis-Pae(a} with eoraaands derived tram tha normal oanual  starting
 sequence tihen properly Installed.

 Using an existing tap or a n,ew bee fitting, a tubing coaneatiors  is  aadc  froa tha
 engine  aide  of the manual starting air valvs to bulkhead ita . 5  of the
 Stfitie-?aa control.  Relay val.ve_i01-' is shipped loose and should  be  mounted
 aloss to the canual fual gas valve.  Again usin| an existing tap or a  new tee
 fitting, sake a tubing scr.naetien frca a point In the «nglne fael gas  line  on
                 of the manual fuel" gas valve to the pilot of relay
          ^
 ' Q |~ 1 .   Cotsnest a t'jbing Una from Statie-Fac b'jlJdread no. 7  to  We  'normally
 closed  iniet port of vglve T0'~4 and a tubing lint frca t'na outlet of the
 valvt  to  bulkhaad^no^  3-  Connect bulkh&aQ rto. 3 to pilot {operator)  of high
 pressure  v_al_ve ISC-':  sonnect high preaaure gas supply to blocked  ir.lat part
 of  valve  jOC-'i ,  connect St«tia-?ae(a) to opposite port, pips  third port Cvtnt)
 to  a safe, 'jar 8 striated vent systsn -o atmosphere.  Connect bulkhead  no. U  to
 indicator  1 9.R^' , after indisator has beer, positioned in desired  loostiOTi,
 Connect 60 to  1S5 psig filtered supply air to bu.lkheaii no. _6.  Installation is
 o oa pi etc ,
B.  OPERATION

Engine/compressor ia stopped.   Supply air and Starting Air  are nonnested  to
Statie-Pao  control,   Fuel  gas  is as-nn acted ta the pilot of  relay valva  101-1 ,
fiigh  prasaure gas is connected ta the inlet of control valve  100-1  which  is
piped  to  Statis-Faci'a)  and to  vent.

Supply air  enters through  bulkhead ao. 6 to the Inlet of vilvc |-J_,   If 9-t i»
sot aanuaily  latchta closed ,  air passes through 9-1 ta bulkhead no ,  S and
          no.  j.   Pressure  froa byl khaad no .  2 engages pilot (operator)  of
v»ly«..10a~i... shifting valve so tr.as Jiisr. prsaaure gas passes  through valve  to
Static-Pacts)  on  corner eascr ,  causing then to engage.  Presiure  fron  ^ulkiieHd
na .  U  is  routed  ts ta i.idicBtg.r .l.g.R-' ,  anifting it to the red position  to  show
t*a" "tie  Statio-Pac's) are engaged,
 Dover  Corporation/^.  Lee  Cook Division    Uiuisville, Kantueky    Juns  |,  1993
                               -48-

-------
 S?ATIC-PAC  - Compressor Roc! Packing Shut-down Sealing  Systen             Page 2
 MANUAL  CONTROL SYSTEM - Drawing E'--3^6-"

 BEFORE ....... SfAfiTIJtC £HSINEj_  Saise lacci; cri Statie-Pae control  vglye_5«l to
An  auxilliary back-yp  circuit is prsvided to disengage  die  Statis-?aata)
should  the operator  fail to raise *fte valve latch.  Vfrien  the  oanual  engine
starting  air  valve  is  opened, starting air will be applied  through
r.q . _5 to  the  pilot  of  valve 8-1 , causing it to opin.   This  allows  supply air
to  flow ta  ahyttle  valva ig»l_ and an through flow control valve  13-^  in the
unrestricted  Direction to  imcsediattiy flU vo 1 ua e Qfrajitbqr _J|g-j_ •  shifting valve
g-1 .  Valy«__9-M_  when  shifted v«nts buiteeads 2 A 4 , allowing  valva_JIOO-l  to
vent she  Static-PacCs) and  indicator ,'9R-^ which returns to the  black
position.   Jteta  that  this  is a baeK-yp circuit only and that  aanual
          Reat should  always be used.
After the engine  has  "aaen purged, the nsanaal fuel gas valve  is  opened.   This
appliss gas  praasure  So  tr.e pilot of relay valya .^|_^1 causing  it  to open and
allow supply air  to  flow from bulkhead r.o. 7 back to bulkhead  no.  3..  This
signal will  reaiin *Aiil« angina is running and throug.h shuttle  valve 1g-1 will
jtaep signal  ta  pilot  valve t;.Q-t ver.tad, Xesplng Static-Pacts)  or,  compressor
disengaged .

me engine is r.ow mnr.ir.g with ths Statlc-PaoCa) on tiia aosprtssor disangag&d.

v"heis the engine la stopped by closing the msnual fuel valve, reley valve lOt-1,
will close, venting  the  pressure froa bulkhead no. 3.  The  air  trapped  in
veljanc ahamber 30-1  will be slowly ventec through flow eastrol  valve 13-1 in
the restricted direction and on through shuttle vs',v9 '^5-1  to 'Bulkhead jno^
!•  j[alve__ ij-1 is  adjusted  to provide a tiae delay (up so  two ainutasj  bafore
valva 5-1  shifts "o  permit  the ar.glna/conipressor to come ta  a full  stop before
angaging  the compressor  Static-Pacts),  nhen tha prsssura  is rtmoveti from the
pilot; of  valve 9-1 ,  the  valve will return to the eternally  spen  position
          press'urt  to flow through from BulXheae no.... ..... 6 to b.'jlMlfijgjL--?Q-i ........ 3. ........ JLi
        valve  '00-'  to  apply pressure ts the Static-Pae< s)  sad  v> jjTglaator
1QH-1, retyrnlsg is  to  the  red position "STATIC-PACK s} EMGiCSD".

Tne 5tatia-Pac sontrol can  be operated manually to diaengaga the eoEpressor
Static-Facts)  for  maintenance wheft -he er.gine/coapreasor is  3"nut down.   Raise
th» red Lever  on vBlv;9_9^1  to disengage We Statie-PaeCs} ,  lower tho lover to
re-engage,  Should tr.8 lever be accidentiv left in the aanually disor.gaged
paaitiqr.,  it will  automatically return to r.ornal after she  next start/stop
 Dover Corporatiors/C,  Lea  Cosk Divisisn    Louisville, Kentuoky    Jiir.a  8,  1983
                         -49-

-------
-50-

-------