FINAL
             Guidance For Reviewing Extension Requests Under 1412(b)(10)
                               Of The Safe Drinking Water Act
PURPOSE

       This document provides guidance concerning how EPA interprets the authorities and limitations of
Section 1412(b)(10) of the Safe Drinking Water Act (SDWA). For the purpose of this document State refers
to EPA Regions and States exercising primary enforcement responsibility under the SDWA. Under certain
conditions, this provision allows States to provide up to a two year extension of the date by which public water
systems must comply with a new or revised National Primary Drinking Water Regulation.  It also provides
recommendations to State Directors on the procedures they may want to follow in using this authority.

       The SDWA provisions and EPA regulations described in this document contain legally binding
requirements.  This document does not substitute for those provisions or regulations, nor is it a regulation itself.
Thus, it does not impose legally-binding requirements on EPA, States, or the regulated community, and may not
apply to a particular situation based upon the circumstances. EPA and State decision makers retain the
discretion to adopt approaches on a case-by-case basis that differ from this guidance where appropriate. Any
decisions regarding a particular facility will be made based on the applicable statutes and regulations.
Therefore, interested parties are free to raise questions and objections about the appropriateness of the
application of this guidance to a particular situation, and EPA will consider whether or not the recommendations
or interpretations in the guidance are appropriate in that situation. EPA may change this guidance in the future.

BACKGROUND

The SDWA, as amended in 1996, generally requires compliance with national primary drinking water
regulations 3 years after promulgation.  The Amendments also allow compliance deadlines to be extended for
up to an additional 2 years if it is determined that additional time is needed for capital improvement projects to
comply with a maximum contaminant level (MCL) or treatment technique (TT). This is specified in Section
1412 (b)(10) of the SDWA:
        "A national primary drinking water regulation promulgated under this section (and
        any amendment thereto) shall take effect on the date that is 3 years after the date on
        which the regulation is promulgated unless the Administrator determines that an
        earlier date is practicable, except that the Administrator, or a State (in the case of
        an individual system), may allow up to 2 additional years to comply with a maximum
        contaminant level or treatment technique if the Administrator or State (in the case of
        an individual system)determines that additional time  is necessary for capital
        improvements."
       \	s
1412(b)(10) Guidance                                                                         Page 1 of 7

-------
Furthermore, the responsibilities of the States have been further explained in the legislative history1 for this
provision:

•      "The Administrator may establish an earlier date for compliance as part of the regulation, if an extended
       period is not necessary for design and construction. The Administrator is also authorized to extend
       the compliance period for an additional 2 years (up to a total of 5 years) in the promulgated regulation
       where the additional period is necessary for construction activities that may be necessary to
       comply."[bold added]

•      "In addition to the Administrator's authority to extend the period beyond the 3 years by rule, a State
       may extend the compliance period for particular public water systems in that State that need up to an
       additional 2 years for the design and construction of treatment facilities or alternative water supplies
       to comply." [bold added]

•      "The Administrator is authorized to provide case-by-case extensions for particular systems in States
       that do not have primary enforcement responsibility under section 1413."[bold added]

A State may grant extensions to an MCL or TT under 1412(b)(10) on a case-by-case basis only when
additional time has not been incorporated into the rule. Under the authority of this provision, compliance with a
regulation may not be extended to beyond five years after the rule publication.  In other words, a system's
application for an extension would only apply to those rules with a compliance deadline of less that 5 years from
promulgation (e.g., Interim Enhanced Surface Water Treatment Rule). Additional extensions may be granted
through the exemption provision of Section 1416. States are granted authority to issue extensions by the
federal law and do not need a parallel State statute  or regulation.

EPA Regions will provide case-by-case extensions  for individual systems in States that do not have primacy or
interim primacy (a state has interim primacy if they have submitted a complete primacy application package).
The extension only applies to a time frame for compliance with an MCL or TT.  A system is still obligated to
comply with all other provisions of the regulation such as  monitoring and reporting.

As new regulations are promulgated, systems will begin to evaluate the adequacy of their treatment processes
to determine if they will satisfy compliance requirements for these rules. During the evaluation process some
systems will conclude that, despite best efforts to do so, they will not be able to satisfy compliance requirements
(i.e., meet an MCL or TT) and submit applications to their State for extensions under 1412(b)(10).
            Report of the Committee on the Environment and Public Works United States Senate on S. 1316, 104th
    Congress - 1st Session, pg. 49
1412(b)(10) Guidance                                                                           Page 2 of 7

-------
                               HYPOTHETICAL EXAMPLE - ABC SYSTEM
        ABC System is seeking an extension to comply with the new HAAS MCL set by the Stage 1
        Disinfectant/Disinfection Byproducts Rule (Stage 1 DBPR).

        ABC System uses surface water as a source and serves 10,000 or more people. Note: For the Stage
        1 DBPR, only Subpart H systems (systems using surface water or ground water under the direct
        influence of surface water) that serve 10,000 or more people may apply for an extension, since all
        other affected systems have up to five years to comply.
GUIDANCE

Three general areas the State should consider when reviewing requests for extensions are:

    •   qualification criteria,

    •   conditions of the extension, and

    •   interim treatment measures

Before a system may be granted an extension it should satisfy the qualification criteria and agree to the
conditions and measures deemed necessary by the State.

QUALIFICATION CRITERIA

To qualify for an extension, a water system should meet the following criteria:

Demonstrate a need for an extension.
           •   The system  should show that without an extension they would not be able to meet a new MCL
               or TT specified in the regulation.
           •   The proposed capital improvement should facilitate compliance.
           •   An additional aspect is to allow systems to be progressive (e.g., forethought to design with
               future rules in mind).

        | ABC  System performed a study over an 18-month period and found while operating under optimum
          conditions they could not meet the new standards (0.060  mg/L) for the group of five haloacetic acids
        I (HAAS), on a consistent basis.
1412(b)(10) Guidance                                                                              Page 3 of 7

-------
The system should document their "Good Faith" efforts to meet the original compliance date  of the
       regulation.
           •  A system should demonstrate that they initiated steps towards compliance in a reasonable
              period of time after the promulgation date of the rule. A reasonable period can include time for
              a system to discuss their options with the State prior to initiating any activities. Additionally,
              when evaluating a system's "Good Faith" effort toward compliance, the State may wish to
              consider other factors such as compliance history.
           •  A system which did not take steps towards compliance, or has only started to do so in the
              months immediately preceding the compliance date has not demonstrated a "good faith" effort.

        /^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
         In February 1999, shortly after rule publication, ABC System evaluated their plant and determined it
         would not satisfy new regulations. ABC based the determination on monitoring done after
         optimization of current processes. Therefore, in January 2000, in good faith ABC initiated renovation
        Wnd upgrade activities on an expedited time line.

Demonstrate that the scope and/or complexity of the capital improvements warrant the length  of the
       extension.
           •  Extensions should be granted for only the period necessary to complete the required capital
              improvements.  While 1412(b)(10) allows for extensions of up to two years, extensions for the
              full time should only be granted where the scope of the proposed  improvements justifies the
              length of the time requested.
          ABC System initiated construction activities to upgrade their plant to incorporate granular activated
         carbon (GAC) treatment to reduce HAAS levels. Although ABC System began construction in
         January 2000 (two full years prior to the initial compliance deadline for Stage 1 DBPR), construction
         would not be completed until April 2003. Thus, ABC System requested an extension for compliance
        \with the HAAS MCL. Through the negotiation with the State, ABC Systems received a 1.5 year
EXTENSION CONDITIONS

Systems will likely propose a plan that includes critical milestones and a time-line with a final compliance date.
Often these conditions will be refined through negotiations with the State. The State may wish to consider
documenting the conditions of the extension through a memorandum of understanding signed by both parties or
by signing-off on the system's plan once negotiations are completed. The conditions of an extension should, at a
minimum, contain:
1412(b)(10) Guidance                                                                           Page 4 of 7

-------
Compliance schedules with critical milestones.
   •  A system should present a realistic construction schedule to complete their capital improvement efforts.
      Schedules should be based upon the scope/complexity of the capital improvement.
                 •   Critical milestones are those which would indicate that significant progress towards
                     construction goals are being realized.
   •  While developing the compliance schedule, the State and system should discuss and document the
      implications of missed milestones (e.g. violation of National Primary Drinking Water Regulation) and
      remedies for the delay.

Progress reports corresponding to critical milestones.
           •   The State should request progress reports as frequently as is necessary to perform oversight of
               the system. We do not intend to create any undue reporting burden by requesting information
               that is not critical to determining the system's compliance with the negotiated compliance
               schedule.
           The ABC System proposed the following critical milestone to discuss in their progress reports durin
           the extension period:
           •       Groundbreaking for the GAC system
           •       50% building completion
           •       GAC installed - to include results of pilot test run
           •       Building construction complete, and
           •       Plant operating with GAC  system fully operational
Compliance with interim measures for public health protection as determined by the State.
           •  During the extension period the system should make reasonable efforts to meet the intent of the
              provisions established in the rule. Measures that can be taken within the scope of the system's
              current operation should be established and complied with to provide a level of public health
              protection while capital improvements are on ongoing.  Interim measures are discussed further
              in the following section.

Provide an opportunity for a  system's customers to respond/comment to a notice of an
       extension.
           •  It is important that the public which is served by the system is informed of the purpose of the
              extension and has an opportunity to provide input to the system and the  State.
           •  The system should consider publishing a "Notice of Availability" of a public hearing as an
              opportunity to explain and receive feedback on the extension.

Notice of the extension in the  annual Consumer Confidence Report (CCR) [note: applies only  to
       community water systems (CWSs)].
           •  A CWS should explain to their customers the reason they pursued an extension.
           •  The notice should explain the issues surrounding the extension and the interim measures the
1412(b)(10) Guidance                                                                            Page 5 of 7

-------
               system will take to ensure that the quality of service will not be compromised.
           •   The CWS is required to publish their compliance monitoring results in the CCR.
          ABC System agreed to notify their customers of the extension to the HAAS compliance date in their
          annual CCR. Note: The system would not be in violation of the MCL/TT or be required to report
          under the Public Notification Rule, but they are required to report any compliance monitoring results
          in the CCR (if they are a CWS).
The State may wish to have a system issue a Public Notice, or a statement in the CCR if the MCL
       or TT for which the extension was granted is exceeded.
           •   A system is not required to issue a public notice during the extension period for an exceedence
               of an MCL or TT.  The State may wish to encourage the system to notify their customers of
               any exeedences as part of the system's responsibility to keep the public informed of any issues
               related to public health and the water supply.
        For ABC System, conditions of an extension include submitting quarterly sample data and notifying the
        public if the annual average for HAAS exceeds 0.060 mg/L.
INTERIM MEASURES

EPA believes that it is important to consider each system's potential for achieving meaningful overall risk
reduction through reasonable interim treatment requirements. Some possibilities the States may wish to
consider include the following:

    •    Change the treatment process, type of treatment, or point of treatment.

         ABC System will optimize treatment in their plant to improve precursor removal and minimize the       •
                                                                                             W
        I formation of disinfection byproducts.
   •  Implement a main flushing program in areas with high detention times and/or biofilm
      problems.

   •  Minimize the use of certain sources.

   •  Provide alternate solutions for sensitive populations (e.g., bottled water, point-of-use, or point-
      of-entry devices).

In all cases, EPA believes that it is essential to evaluate all potential interim treatment requirements in terms of
their impact on disinfection byproduct formation, microbial protection, corrosion control, and other public

1412(b)(10) Guidance                                                                            Page 6 of 7

-------
health issues.  States should consider the net gain in public health protection when establishing interim treatment
requirements.
1412(b)(10) Guidance                                                                                Page 7 of 7

-------