UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
                                                                             WSG75
                                                             Date Signed:  June 1, 1994
MEMORANDUM

SUBJECT:   Requirement for a Public Water System Which Takes Fewer than Five Total
             Coliform Samples per Month to Undergo a Sanitary Survey

FROM:      Robert J. Blanco, Director
             Enforcement and Program Implementation Division

TO:          Drinking Water/Ground Water Protection Branch Chiefs Regions I - X

       Over the past few months, a number of questions have arisen on the interpretation of the
requirement for public water systems which take less than five routine total coliform  samples per
month to undergo a sanitary survey.  Specifically, the questions revolve around: (1) what type of
violation should be reported if a system has been taking  fewer than five samples per month and
fails to have a sanitary survey conducted; (2) when does a violation begin; and (3) how such a
system can return to compliance. This memorandum provides guidance on these issues.

       The Total Coliform Regulation at 40 CFR 141.21(d) states:

       Public water systems which do not collect five or more routine samples/month must
       undergo an initial sanitary Survey by June 29, 1994, for community public water systems
       and June 29, 1999, for non-community Water systems.

       Sanitary surveys must be performed by the State or an agent approved by the  State. The
       system is responsible for ensuring the survey takes place.

       The Total Coliform Rule Implementation manual (March 1991) addressed these issues.
On page 8, the manual states:

       The State must report if a required Sanitary Survey to support reduced monitoring was
       not conducted. Please note that a contaminant code cannot be specified for this type of
       violation. Failure to have a Sanitary Survey conducted must be reported as summarized
       below:

       Contaminant Code:               Not applicable - Do not report
       Violation Type:                   28 - Failure to have a Sanitary Survey Conducted
       Begin Date:                      The first day of the compliance period.
       Duration:                        Depends on State requirements.

       Pages D-25 though D-27 of Appendix D of the Implementation Manual deals  with FRDS
reporting and provides detailed guidance and examples of reporting this violation.  I have
attached those pages for your information.

                                          1

-------
                                                                               WSG75
       In addition, the Question and Answer Section of the Implementation Manual dealt with
this topic:

       Question:      Which systems are subject to sanitary surveys?

       Answer:      Sanitary surveys must be conducted for systems which collect fewer than
                    5 samples/month.... Systems can monitor at a frequency of 5
                    samples/month to avoid sanitary surveys  .... the rule does not require
                    systems taking 5 or more samples per month to have sanitary surveys
                    performed.

       The survey provision has frequently been misinterpreted as requiring all smaller
community water systems (those with a population of less than 4,100), and all noncommunity
systems to conduct a sanitary survey.  The survey requirement is not tied to system size, type, or
to the number of samples that the system is required to take [as per 5141.21(a)].  Rather, the
survey requirement is tied to the number of samples that the system actually collects: "public
water systems which do not collect five or more routine samples/month must undergo an initial
sanitary survey... " In effect, the rule offers CWSs serving fewer than 4,100 people and all
NCWSs an option: a) conduct a sanitary survey, or b) increase coliform monitoring to at least 5
samples/month.

       While the questions that we have been asked focus on community water systems, we
want to be clear that the "option" of survey vs.  sampling applies to non-community as well as
community systems.  The only difference between the two system types is the date by which the
option must be exercised -- June 29, 1994 for CWSs and June 29, 1999 for NCWSS.

       Unfortunately, the regulation is not clear on the issue of when a system which opts for
increased monitoring must begin to collect 5 samples/month. A strict interpretation would be
that systems should have made the choice as soon as the Total Coliform rule became effective
(i.e., December 1990). While the preambles to both the proposed and final rules would seem to
support this interpretation the regulation itself is not explicit. What we believe is clear in the
regulation, however, is that the choice must be exercised no later than June 29, 1994 for CWSS,
and June 29, 1999 for NCWSS. As of the last day of June of those respective years, the affected
systems must either have had a survey conducted, or have begun taking (during the June .
compliance period), and continue taking, coliform samples at a rate of 5/month.  I stress the
requirement to continue taking 5 samples/month because once the system makes the choice to
increase its monitoring, it must monitor at that increased rate unless, or until, it undergoes a
sanitary survey.

       If neither of the above requirements  are met the system is in violation of the regulations.
Further, any system which opts for increased monitoring but falls below the minimum of 5
samples/month sometime in the future, will  also be in violation  of the regulations as of the month
that the reduced monitoring occurred.  As noted in the Total Coliform Implementation Manual,

-------
                                                                                WSG75
and discussed earlier in this memo, these violations should be reported as a violation of the
sanitary survey requirement at 40 CFR 141.21(d). The violation need be reported only once.
There can only be one sanitary survey violation every five years for CWSs and one every ten
years for NCWSS. A system which has incurred such a violation can return to compliance either
by:

       -      having a survey conducted, or
       -      increasing its routine monitoring to at least 5 samples a month.  [This increased
              monitoring would apply until a survey is conducted.].

       Finally, when the definition of significant noncompliance  (SNC) for the total coliform
rule was established, there was no provision made for an SNC for a sanitary survey violation
since the date of violation was so far in the future. Now that the June 1994 deadline is upon us, I
would like your opinion on whether we should establish SNC criteria for a sanitary survey
violation. As I see it, establishing an SNC definition for this type of violation would clearly
demonstrate that EPA (and the States) believe in the importance of sanitary surveys. However, I
recognize the competing demands of implementing and enforcing the program. I would like
your opinions on this issue and, if you support the creation of an SNC definition for this type of
violation, what that definition should be.  Please send your comments on this issue by June 17 to
Betsy Devlin, who can be reached at (202) 260-5550 [telephone]  or (202) 260-4656 [fax].

       I hope that this clarifies the interpretation of this regulation. Should you have Any
questions, please contact Betsy Devlin at (202) 260-5550  or Ray Enyeart at (202) 260-5551.

Attachment

cc:    PWSS  Section Chiefs
       PWSS Enforcement Coordinators
       FRDS Coordinators

-------
                                                                              WSG75


C.     Sanitary Survey M&R Violations

       A sanitary survey M&R violation is issued to PWSs that fail to have a sanitary survey
conducted at the required frequency.

       1.     FRDS-II Input Format

       When reporting to FRDS in DTF format, the primacy agency must provide the following
data:
r> + ci
No.
C101
cnoi
C1105
C1107
1-/CIUI JJ/1G1UG11U
Name Description
PWS-ID
VIO-ID
VIO-TYPE
VIO-COMP-PERIOD-BEGIN-DATE
The PWS ID number
An ID for the violation
The violation type
The date the compliance
Comment/
Value


28
mmddyy
         (See note #1, page D-26)

Cllll    VIO-COMP-PERIOD-MONTHS
                        period began

                        The duration of the
                                                                         42, 50, 102,
                                               compliance period in months   120
                                                                         (See note #2
                                                                         page D-26)
       The primacy agency may optionally report the following data:
                                     Data Element
No.
Name
                                                Description
                                                                     Comment/Value
         Instead of reporting Cllll, VIO-COMP-PERIOD-MONTHS,
         Report:

 C1109   VIO-COMP-PERIOD-END-DATE    The date the compliance     mmddyy
                                          period ended

      Figure 17 illustrates a completed FRDS-II data capture form for reporting a sanitary
survey monitoring and reporting violation.  Figure 18 illustrates the FRDS-II DTF transactions
which equate to the completed data capture form. Refer to FRDS-II Data Entry Instructions
documentation for further details.

-------
                                                                                WSG75
Notes:

1 -     For purposes of illustration, the scenario and example below assumes that the State has
       adopted the NPDWR sampling dates, frequencies, etc. by reference. Of course, if the
       State chooses, they can adopt more stringent requirements.

       To illustrate what must be reported to FRDS for the compliance period begin date,
       consider the following:

       A PWS collecting fewer than 5 routine samples per month must undergo an initial
       sanitary survey by June 29, 1994 (for CWSS), or by June 29, 1999 (for NCWSS).
       Thereafter, the system  must undergo another sanitary  survey every five years (ten years
       for NCWSs using only protected and disinfected groundwater) after the initial sanitary
       survey.

       A community PWS that regularly collects 3 routine samples per month (a system that
       serves between 2,501 and 3,300 persons) has an initial sanitary survey conducted on May
       31, 1992.  Its next sanitary survey must be conducted  by no later than May 30, 1997
       (within 5  years of the date of the initial sanitary survey).

       If we assume that the systems second sanitary survey was not conducted  by May 30,
       1997, a sanitary survey M&R violation must be reported to FRDS with a compliance
       period begin date of June 1, 1992. This is one day after the initial sanitary survey was
       conducted, and it is the first day of the compliance period for which a sanitary survey
       was not conducted. The violation would be given a compliance period duration of 60
       months.

2-     Since the effective date of the TCR regulation is January, 1991, the community PWS
       deadline of June  29, 1994, is 42 months after the effective date of the rule, and the non-
       community water system deadline of June 29, 1999, is 102 months after the effective
       date.1

       Therefore, for systems that fail to have the initial  sanitary survey conducted, the
       compliance period duration would be a maximum of 421 months for community PWSs, or
       a maximum of 1021 months for non-community PWSs.
       1 At State discretion, more stringent requirements can be adopted. If a State adopts more
stringent requirements, the compliance period durations of 42, 102, 60, and/or 120 months would
be replaced, as appropriate, with the more stringent State specific values.

-------
                                                                         WSG75
For systems that fail to have a subsequent sanitary survey conducted (after the initial
sanitary survey period), the compliance period duration would be 601 months (1201
months for NCWSs using only protected and disinfected groundwater).

-------