Q PQA United States
\/Lrn Environmental Protection Agency
Superfund Permanent Relocation
Statement of Work Template
and Users' Guide
Office of Superfund Remediation and Technology Innovation
Office of Solid Waste and Emergency Response
U.S. Environmental Protection Agency
Washington, DC

-------
Office of Superfund Remediation
and Technology Innovation
OSWER 9230.0-108
August 2004
Superfund Permanent Relocation
Statement of Work Template
and Users' Guide
Office of Superfund Remediation and Technology Innovation
Office of Solid Waste and Emergency Response
U.S. Environmental Protection Agency
Washington, DC
i

-------
Superfund Permanent Relocation Statement of Work Template and Users' Guide
Superfund Permanent Relocation
Statement of Work Template and Users' Guide
Table of Contents
Part 1: Introduction 	 1
Purpose	1
Instructions for the SOW 	 1
Part 2: Property Acquisition and Permanent Relocation - Important Considerations	3
Working With the Community 	3
Working with the US ACE 	5
Appendix A: Estimated Timeframes For Acquisitions and Permanent Relocations 	7
Appendix B: Procedures for the Acquisition of Real Property 	8
Appendix C: Superfund Permanent Relocation Statement of Work for
Residential Real Estate Acquisition and Relocation Assistance 	10
Purpose	10
Primary US ACE Responsibilities 	 10
Task 1: Planning 	 12
Task 2: Coordination and Communication	14
Task 3: Advisory Services 	 16
Task 4: Appraisal and Acquisition 	17
Task 5: Relocation 	20
Task 6: Follow-up 	21
Task 7: Appeals 	21
Task 8: Reporting	22
Task 9: Project Management and Close-out	22
Attachment 1: Property Acquisition/Relocation Statistical Report Form 	23
Attachment 2: Instructions for Property Acquisition/Permanent Relocation
Statistical Report Form 	24
ii

-------
Superfund Permanent Relocation Statement of Work Template and Users' Guide
Parti: Introduction
Purpose
EPA typically works with the United States Army Corp of Engineers (US ACE) to implement
permanent relocation of businesses and residents that are chosen as part of a site remedy. The
purpose of the EPA/US ACE statement of Work (SOW) template is to provide the agencies and
their contractors with instructions on how to implement successful permanent relocations. While
this template suggests steps to follow regardless of the size or complexity of the relocation, it
will need to be adapted for each site. For example, additional requirements may be necessary
if businesses will be relocated. Part II of this Users' Guide is a summary of key issues regional
staff should keep in mind in planning and implementing permanent relocations.
Instructions for the SOW
The SOW template (Appendix C) provides a general description for each of the eight tasks
(planning, acquisition, relocation, advisory services, appeals, reporting requirements, project
management and close out) that EPA and the US ACE must perform when conducting a
permanent relocation.
Throughout the template, reference boxes provide Remedial Project Managers (RPMs) with
suggested information that should be given to the USACE to clarify the acquisition and
relocation processes. The reference boxes emphasize important issues, define terms, and give
examples of challenges Regions may face throughout the permanent relocation process.
Reference boxes should be deleted before the site-specific SOW is finalized. The template is
available as a WordPerfect or MS Word document so that RPMs can use and modify the SOW
as needed.
The SOW template as well as other documents referenced throughout the SOW template can be
found on EPA's Superfund website at http://www.epa.gov/superfund/tools/topics/relocation.
Some of the key documents include:
•	Release of Appraisals for Real Property Acquisition at Superfund Sites Guidance, OSWER
Directive 9200.1-35P, November 2000;
•	Interim Policy on the Use of Permanent Relocations as Part of Superfund Remedial Actions,
EPA 540-F-98-033, EPA Directive 9355.0-71P, June 1999;
•	Superfund Response Actions: Temporary Relocations Implementation Guidance, OSWER
Directive 9230.0-97, April 2002;
•	Process of Handling Appeals of Permanent Relocation Claim Decisions Memo, O SWER
Number 9355.0-88, February 2003; and
•	Superfund Permanent Relocation Statement of Work Template (in MS Word and
WordPerfect).
1

-------
Superfund Permanent Relocation Statement of Work Template and Users' Guide
The U.S. Department of Transportation, Federal Highway Administration, the lead agency for
implementing the Uniform Relocation Assistance and Real Property Acquisition Policies Act of
1970 (URA) (49 CFR Part 24) is, as of the date of this document, leading a multi-Agency
workgroup to update the URA regulations. Please contact your Headquarters Regional
Coordinator and/or the Office of General Counsel (OGC) to learn the status of these revisions
and for additional advice on implementing property acquisitions and relocations. The URA
regulations provide specific rules for conducting permanent relocations. To ensure that
relocations conducted by Potential Responsible Parties (PRPs) meet the same or similar
standards as outlined in EPA policies, the relevant URA requirements should be incorporated
into the Record of Decision (ROD) or Action Memorandum and other enforceable decision
documents. The URA regulations can be accessed at http://www.fhwa.dot.gov/realestate/ua.htm.
2

-------
Superfund Permanent Relocation Statement of Work Template and Users' Guide
Part 2: Property Acquisition and Permanent Relocation
Important Considerations
EPA's close management of all aspects of a permanent relocation, including prompt, effective,
and sustained communication with other Federal Agencies, community residents, and local
authorities, is the key to a successful Superfund relocation. The items listed below are
suggestions given by RPMs and Community Involvement Coordinators (CICs) who have
successfully navigated the permanent relocation process. They are intended to help you
successfully plan, manage, and implement a permanent relocation, while simultaneously
providing some consistency on how to conduct EPA property acquisition and relocation
activities across all the regions.
Historically, property acquisition and permanent relocations have consumed more of the RPM's
time than anticipated. Headquarters strongly encourages RPMs to form a team to efficiently
manage all aspects of the acquisitions and relocations. The team approach brings together people
with a mix of technical, outreach and legal expertise to effectively support the affected
community, while allowing the RPM to focus on implementing the cleanup. However, it is very
important for the RPM to remain actively involved as a key member of the team even as he or
she implements the cleanup.
Since property acquisitions and permanent relocation often take longer to complete than
originally anticipated, Appendix A provides estimated timeframes for each major milestone in
the process. Keep in mind that the actual timeframes will vary, depending on the number of
properties to be acquired and the complexity of issues at the site. One of the milestones is
obtaining approval for property acquisitions. The procedures of coordinating property
acquisition requests through OGC is provided in Appendix B. Contact your Office of Regional
Counsel (ORC) or your Headquarters Regional Coordinator for an example of the memorandum
necessary to receive approval to acquire property. Expect Headquarters to take approximately 30
days to process the approval.
Working With the Community
•	Expect questions about relocation whenever you are conducting a response action in or very
near a residential community. Even if you don't anticipate that relocation (either temporary
or permanent) will be necessary, you should be prepared to answer questions regarding
EPA's consideration of whether or not residents should be relocated.
•	Tell owners and tenants what you know and be honest about what you don't know. Don't tell
them they will be offered relocation unless you know they can be relocated. Never suggest
specific relocation benefits unless you are certain they are entitled to the benefits.
•	Tell residents it is EPA's policy to implement remedies in such a way as to protect public
health without the need for relocation (refer to OSWER Directive, 9355.0-71P, Interim
Policy on the Use of Permanent Relocations as Part of Superfund Remedial Actions, which
provides guidance on making property acquisition decisions).
3

-------
Superfund Permanent Relocation Statement of Work Template and Users' Guide
Prepare for a possible change of direction. Before starting, analyze the site to determine what
factors could alter the remedy. Develop criteria for when a change would be indicated, and
have a plan in place to gather data and re-evaluate the situation at key milestones so that a
potential change of remedy will be flagged early. For example, your analysis of the site may
reveal that homes in the area are not structurally sound enough to withstand the underpinning
required to excavate under the homes. In that case, your criteria might limit excavation to a
few feet from the houses. Your plan could include a strategy to use cut lines and cost-based
confirmatory sampling and to identify a cost range that is acceptable; if data at critical
milestones indicate the projected costs may exceed that range, or that excavation may be
required under houses, you will be prepared to re-evaluate whether to acquire the property
and relocate the residents.
•	Be wary of the temporary relocation dragging on longer than anticipated. EPA policy is to
consider property acquisition and/or relocation when a temporary relocation lasts longer than
six months for tenants and one year for owners. It's easy for a temporary relocation, planned
to last a few months, to stretch a few extra months, then a few more months, leading to a
temporary relocation that lasts over a year, increasing costs and frustrating residents.
•	Be aware that the URA provides very different and generally more limited benefits for non-
residential relocations, (businesses, non-profit organizations and farms). Some non-
residential relocations can be challenging to implement and require special knowledge to
avoid costly mistakes. Be careful not to discuss these benefits until you are fully informed of
the scope provided by the URA.
•	Tell residents the types of situations where permanent relocation may be considered and
what information is needed to make that decision. For example, if there is a chance that
subsurface soil contamination may extend under a house, you may want to tell the residents
that the only way to know for sure if their house can be saved is to start the excavation.
•	Keep residents informed. Touch base with them even if you have no new information and
give them a timeline that shows when you think you will know if their house can be saved.
•	Make sure residents know there will be many opportunities to meet individually with the
EPA and the USACE to discuss their concerns.
•	Keep in mind that the community members left behind will also have questions and concerns
about the relocation and its impact on the community. They will have questions about how
the decisions were made to offer relocation, why some received offers and others did not,
and what will happen to the properties EPA acquires. Keep them informed and engage them
in the planning and implementation of the relocation.
•	If translation services are needed, and money and time are of the essence, use community
groups or students in college language programs to translate written materials and oral
presentations. Be creative with your available translation services. Use them to develop site
signs, maps, flyers, and public meeting notices. Provide a formatted English version to
expedite your turnaround time. Take into consideration differences in dialects of the given
4

-------
Superfund Permanent Relocation Statement of Work Template and Users' Guide
language. For instance, Mexican versus Puerto Rican Spanish, and make sure the message is
clear to speakers of all dialects.
•	Consider the use of American Sign Language interpreters or closed captioning, when
communicating with the hearing impaired.
•	Written material must be clear and concise as possible to avoid misunderstandings.
•	Local community members can serve on the relocation team as consultants on critical issues.
The local board of realtors, religious leaders, university officials, and community members
are examples of potential consultants.
•	It is important to understand that acquisition and relocation benefits are different calculations
and should be explained separately. "Just Compensation" is the price an agency must pay to
acquire real property. The price offered by the Agency is considered to be fair and equitable
to both the property owner and the public and is based in part on the amount established in
the approved appraisal report as the fair market value for the property. Property owners are
entitled to "Just Compensation" even if they do not choose to acquire a new residence.
Relocation benefits are determined separately and are based on the additional costs to the
resident to acquire new property and move their belongings. The resident must actually incur
the allowable expenses to be entitled to benefits.
•	It is usually best to have one person explain the "Just Compensation" offer and another the
relocation benefits. This conversation should take place at the same meeting so the residents
understand the difference between the types of compensation but hear the Government's
entire offer at once.
•	Clearly define the roles of the USACE, EPA, and other team members to residents.
•	Trust must be established with the residents. Consistency is important. The USACE may be
the residents' first point of contact on acquisition and relocation questions, but residents may
ask the RPM or CIC questions related to benefit. The team should coordinate answers to
residents' questions to avoid confusion.
•	Relocations involving Native Americans (Tribes) may pose unique issues. Be particularly
sensitive to the history of the U.S. Government's relocation of Tribes and be aware that the
term may generate deep emotions.
•	For all decisions affecting Federally recognized Tribes, EPA is guided both by statute and
policies. CERCLA section 126(b) states that if the Agency finds that "...the proper remedial
action is the permanent relocation of Tribal members away from a contaminated site because
it is cost effective and necessary to protect their health and welfare, such findings must be
concurred on by the affected Tribal government before relocation occurs..." It is EPA policy
that if Tribal members do not concur with the relocation decision, EPA should work with the
Tribal government and community on a site-specific basis to address other cleanup options at
these sites to protect people's health and welfare (OSWER Directive 9355.0-71P).
5

-------
Superfund Permanent Relocation Statement of Work Template and Users' Guide
•	Tribes may put a greater emphasis on verbal communication than written. You may want to
plan extra time for additional individual and public meetings.
Working with the USACE
•	An EPA team member should attend critical meetings with residents. (In order to minimize
inconsistent communications with residents, the USACE Real Estate Project Manager (PM)
should negotiate the acquisition and another person provide relocation assistance advice.)
•	Be sure to stress that the USACE PM assigned to your site must be fully knowledgeable of
the URA and EPA's policies and guidance. EPA's RPMs also should become familiar with
the URA and EPA's policies and guidance.
•	The USACE has real estate experts who can help to determine if relocation is possible, even
before the action is started. For example, in a tight housing market, you may have trouble
finding available comparable housing for residents. If housing is very limited, it may be best
to try and avoid relocation by making changes to the response action. The USACE knows the
URA and can help to evaluate the availability of suitable housing and help explain this
process to property owners and tenants.
•	Be aware that not all USACE District Offices are able to offer EPA the same level of support
and expertise on acquisition and relocation. If you are dealing with a large, complex or
politically sensitive site, or a site with a business relocation, you will need not only experts in
the URA, but also experts in addressing the type of issues you are facing. In these cases, you
may want to request a district office with the needed expertise even if it is not the one you
normally work with. Contact your EPA Headquarters' Regional Coordinator for advice on
getting the right USACE experts to your site.
•	Never turn over the relocation to the USACE and disengage. EPA is ultimately responsible
for the relocation and the RPM must stay involved. While many relocations are implemented
with minimal problems, many are not. When relocations go wrong, they can stop projects,
damage relationships with communities, garner negative media and congressional attention,
and consume everyone's time. Since the RPM may have to make key decisions that affect
residents' lives, the RPM needs to know the community and each resident well.
•	The relocation team should be organized as early as possible to help the RPM determine if
permanent relocation is a viable option. The size and composition of this team will depend
on the scope and complexity of the relocation being considered. The relocation team should
meet often and discuss conversations with residents. EPA should notify USACE of any
relevant discussions to avoid inconsistent communication and an appearance that residents
get a different answer depending on which person answers the question.
6

-------
Superfund Permanent Relocation Statement of Work Template and Users' Guide
Appendix A
Estimated Timeframes For Acquisitions and
Permanent Relocations
The estimated timeframes provided below are for approximately 10 residential properties.
Because of contracting requirements, timeframes for a greater number of properties would be
longer, while timeframes for only one or two properties would be shorter. Additional time may
be necessary in working with tribal members and governments.
Preliminary Actions
Gathering of site data, owner/tenant information, and property information 	 15-30 days
Preparation of Real Estate Planning Report (REPR) 	 15 days
Preliminary Work: Contracting for and receiving maps/legal descriptions/	 90-120 days
appraisals/title information
Total time estimated for preliminary actions 	 120-165 days
Headquarters Approval
Review and approval from OSRTI and OGC* 	30 days
Actions Following Receipt of the Real Estate Directive
Comparable housing search 	Within 15 days
Present the Government's offer to buy and the relocation packages 	Within 30 days
Closings (for Government acquisitions) 	 Within 90 days of the
presentation of the offers
Total estimated timeframe for completion of the acquisition 	 220-285 days
After closing, the owners must acquire replacement housing and move (if they have not already
done so) from the property. Residents have up to one year to spend their replacement housing
payment but most are able to acquire replacement property and move within 60 to 120 days.
* OSRTI approves the acquisition and OGC isues a real estate directive to USACE to acquire the
property. The request for approval should be sent jointly to the Directors of OSRTI and OGC.
NOTE: Timeframes listed under "preliminary actions" are dependent upon the time of year that
they are completed (i.e., anticipate longer timeframes if the work is to be completed near the end
of the fiscal year). The timeframe for presentation of the Government's offer to buy and the
relocation package is largely dependent upon the residents' availability. In the unlikely chance
that condemnation is necessary, expect delays.
7

-------
Superfund Permanent Relocation Statement of Work Template and Users' Guide
Appendix B
Procedures for the Acquisition of Real Property
An acquisition by any Federal agency of real property must comply with the following:
1.	Uniform Relocation Assistance and Real Property Acquisition Policies Act of1970 (42 USC
§4601)(URA) and the implementing regulations at 49 CFR part 24;
2.	Restriction on Purchases of Land (41 USC §14);
3.	Approval of Title Prior to Federal Land Purchases (40 USC §255);
4.	Standards for Preparation of Title Evidence in Land Acquisitions by the United States, U.S.
Department of Justice (DOJ), 1970;
5.	Uniform Appraisal Standards for Federal Land Acquisitions, Interagency Land Acquisition
Conference, 1992; and
6.	If applicable, Condemnation of Realty for Sites and Other Uses, (40 USC §§257, 258a,
258b). Also, FRCP 71A.
Additionally, an acquisition by EPA of real property in connection with a Superfund site must be
authorized in accordance with the following:
1.	CERCLA §104(j), Acquisition of Property, "property or any interest in real property ...
needed to conduct a remedial action;"
2.	EPA Delegation 14-30, CERCLA, Acquisition of Property [Office of Solid Waste and
Emergency Response (OSWER) and Office of General Council (OGC) review and
concurrence]; and
3.	EPA Delegation 1-4-B, Real Property and Space [Facilities Management and Services
Division (FMSD) approval and authorization].
Delegation 14-30 requires that when the acquisition of real property costs the Agency $25,000 or
more:
(i)	the Regional Administrator makes a determination that the real property is needed for the
response action, and obtains a "state assurance" under § 104j(2), and
(ii)	OSWER approves the acquisition; and
(iii)	OGC gives written concurrence for the acquisition; and
(iv)	the Director of FMSD authorizes the acquisition of the property under the authority
delegated in Delegation 1-4-B.
8

-------
Superfund Permanent Relocation Statement of Work Template and Users' Guide
Through an internal redelegation, the Director of the OSRTI provides the OSWER approval.
Additionally, through an internal redelegation, the Finance and Operations Law Office (FOLO)
provides the OGC concurrence.
Under Delegation 14-30, OSWER approval is not needed for acquisition of real property valued
at less than $25,000, however, OGC concurrence and FMSD authorization is still required.
•	The approvals set forth above are accomplished by the Region submitting a memo jointly to
OSRTI and FOLO, for acquisitions that cost $25,000 or more (to FOLO only for acquisitions
costing less than $25,000). The memo serves a dual purpose: 1) it helps the Region address
all relevant issues and plan the steps necessary to complete the acquisition, and 2) it sets
forth the facts and legal issues for efficient HQ review. Sample memos are available from
OSRTI and FOLO.
•	40 USC §255, Approval of Title Prior to Federal Land Purchases requires that USACE or
DOJ legal staff prepare a title opinion. This legal opinion is based on a commitment for title
insurance. After the closing, the title insurance company will issue an insurance policy to the
United States.
•	Review and approval of the property appraisal by DOJ or USACE is required under the
URA. The appraisal must meet the Uniform Appraisal Standards for Federal Land
Acquisitions, Interagency Land Acquisition Conference, 1992.
•	Closing on the property (delivery and recordation of documents and payment to the property
owner) is handled by ORC or USACE and the title insurance company.
NOTE: OSRTI and FOLO representatives are available to assist in coordinating these activities.
9

-------
Superfund Permanent Relocation Statement of Work Template and Users' Guide
Appendix C
Superfund Permanent Relocation
Statement of Work for Residential Real Estate Acquisition
and Relocation Assistance
At (Site Name) Superfund Site, (City), (State)
Information and Hints for Completing the SOW
It is impossible to develop one SOW for property acquisition and permanent relocation that is
appropriate for all sites. It is expected that the Remedial Project Manager (RPM) will modify this
model SOW to meet site specific requirements. The information boxes throughout this document are
intended to provide the RPM additional information that may assist in modifying this model. Sources
of additional information on this topic are available at http://www.fhwa.dot.gov/realestate/index.htm
or http://www.epa.gov/superfund/tools/topics/relocation/index.htm or by contacting Headquarter"s
Regional Coordinator. This template is meant for residential relocations although business relocations
are mentioned. Non-residential relocations are often much more complicated. The URA provides
different, and generally much more limited, benefits for non-residential relocations (businesses, non-
profit organizations and farms). The RPM should work with the Office of Regional Counsel (ORC),
and when necessary, the Office of General Counsel (OGC) and the appropriate Headquarters
Regional Coordinator for additional tasks that may be necessary. The information boxes are not
intended to be included in the actual SOW. These boxes will need to be deleted before the SOW
is finalized and printed. Both a WordPerfect and MS Word version of this template are available at
the above EPA web page and can be downloaded and edited.
Delete this box by placing the curser on the box, clicking the right button, and selecting the "Delete
Box" option.
Purpose
The U.S. Army Corps of Engineers (US ACE) shall provide to the U.S. Environmental Protection
Agency (EPA), real estate support which includes the acquisition of approximately (number)
residential properties at the (site) in (city), (state) and relocation of displaced persons.
Specifically, USACE will acquire homes, assist with the relocation of the occupants, secure and
maintain unoccupied purchased homes and yards, and provide relocation assistance (advisory
services) as needed. USACE may also acquire non-residential properties, secure and maintain
unoccupied properties and provide relocation assistance as needed to the affected businesses,
non-profit organizations or farms.
Primary USACE Responsibilities
EPA's authority to acquire an interest in real property is provided by the Comprehensive
Environmental Response Compensation and Liability Act (CERCLA), Sec. 104 (j). Acquisitions
will be in accordance with the Uniform Relocation Assistance and Real Property Acquisition
Policies Act of 1970 (URA), as amended, 42 U.S.C. § 4601 et seq., and any relevant regulations
promulgated thereunder, and relevant EPA policies and guidance. The USACE Real Estate
Project Manager (PM) must be fully knowledgeable and familiar with the URA and EPA
10

-------
Superfund Permanent Relocation Statement of Work Template and Users' Guide
policies and guidance related to property acquisition and relocation. All documents furnished by
US ACE to residents and business owners affected by the relocation will be subject to prior EPA
review and approval. The USACE will maintain the acquired property, unless otherwise directed
by EPA, until advised of its disposition by EPA.
In carrying out these responsibilities, the USACE will make its highest priority providing good
customer service to those being relocated. The USACE staff and its contractors will be well
prepared to recognize the economic, psychological, and social impacts of the relocation.
USACE and its contractors should be well prepared to handle the property acquisition and
relocation of displaced persons in a professional manner, always treating residents fairly,
equitably and with respect. They will make every effort to communicate clearly the rights and
options of those being relocated, and they will always strive to provide fair and timely
settlements of claims for relocation assistance.
The USACE may acquire the services of a qualified contractor or other USACE Districts to
assist their staff as well as that of EPA to deal with the fluctuations of needed resources and/or
Information and Hints for Completing the SOW
Relocations can be very time consuming. RPMs need to juggle time commitments to the cleanup
activities, as well as the property acquisitions and relocation issues. Most RPMs with experience
implementing relocations strongly recommend forming a relocation team to efficiently manage the
relocation. This team approach brings together people with a mixture of technical, legal, and
community involvement expertise, as well as an awareness of available local resources to effectively
support the affected community. Roles of each team member should be clearly defined. Use of the
team can allow the RPM to stay involved in the relocation and make the major decisions while other
EPA and USACE relocation experts focus on the details. The team, or key members, should plan to
meet regularly, especially at critical junctures in the acquisition and relocation process. These
meetings will help USACE staff understand the broad scope of activities at the site, while providing
EPA with an opportunity to become aware of any potential acquisition and relocation issues.
At first, team members generally include:
•	A Remedial Project Manager (RPM);
•	A Community Involvement Coordinator (CIC);
•	An EPA Office of Regional Counsel(ORC) attorney; and
•	USACE real estate experts.
If the permanent relocation being considered is large and complex, other team members may be added
to the team to offer specific expertise. These members may include:
•	Regional EPA external affairs/media relations staff;
•	Regional EPA environmental justice office/program staff;
•	Local government representatives;
•	State or Tribal government representatives;
•	Officials from local health and social service agencies; or
•	Officials from the Agency for Toxic Substances and Disease Registry (ATSDR), the Department
of Housing and Urban Development (HUD), and other Federal agencies.
•
Delete this box by placing the curser on the box, clicking the right button, and selecting the "Delete
Box" option.
11

-------
Superfund Permanent Relocation Statement of Work Template and Users' Guide
expertise, as well as increased media and/or Congressional interest in accordance with the URA
and any EPA guidance and policy. To the extent possible, USACE should utilize local
community resources, such as realtors, moving companies, security companies, inspectors, and
appraisers. The USACE will consult with EPA in the selection of contractors, contract types and
contract details. USACE shall provide in its contracts that contractors pay for liquidated
damages for unacceptable delay in project completion.
The USACE shall participate as a member of the team, whose membership may include: EPA's
RPM, EPA's Community Involvement Coordinator (CIC), an EPA attorney from the Office of
Regional Counsel (ORC), and others as determined by the RPM.
Information and Hints for Completing the SOW
The sooner the USACE real estate experts are notified of a potential acquisition and or relocation, the
more likely they will be able to provide the support requested and meet EPA's timeline. Consider
involving USACE even before the decision is made to acquire property. USACE real estate experts
may assist in gathering information necessary for EPA to determine if acquisition and relocation is a
viable option. USACE real estate experts may also assist EPA as it makes its decisions regarding the
duration and scope of easements that may need to be acquired. Even before the ROD is signed,
USACE can provide the RPM with preliminary cost estimates for the proposed plan, initiate
contracting actions for appraisals and title research and provide general information on housing
availability. A preliminary InterAgency Agreement can be initiated to allow the USACE to get
started on this work. This work may be considered similar to other work necessary to develop a
proposed plan and be funded with pipeline funds.
Delete this box by placing the curser on the box, clicking the right button, and selecting the
"Delete Box" option.
Following is a general description of the necessary tasks the USACE will perform, at a
minimum.
Task 1: Planning
1. Attend a kick-off meeting with EPA (all team members including key supervisors should
attend if possible) to discuss each Agency's role and responsibility, and other issues that may
have a bearing on the successful completion of the project. It is important for each agency or
organization to understand EPA's leadership role and to have its own role clearly defined at
the beginning of the project. At this meeting several objectives must be met, including—but
not limited to—the following:
•	EPA will reinforce the fact that EPA remains the lead for all aspects of the response;
•	EPA will stay involved in the implementation of the property acquisitions and relocations
and discuss how EPA will participate;
•	EPA will provide USACE the site history;
12

-------
Superfund Permanent Relocation Statement of Work Template and Users' Guide
•	EPA will develop a draft timeline of all key milestones;
•	EPA will provide the US ACE with all known demographic information regarding the
residents, such as the number of residences and businesses, children, pets, and if there are
any cultural or special needs;
•	EPA will discuss the current or anticipated interest from the media, elected
representatives and community or activist groups; and
•	EPA will answer any questions the US ACE may have to help in developing the relevant
cost and planning documents.
2.	USACE shall become familiar with information provided by EPA at or before the kickoff
meeting. That information may include:
•	The site history;
•	Work completed to date;
•	A timeline of key milestones in the cleanup that may impact the relocation;
•	The number of houses that need to be acquired and the number of residents (owners and
tenants) that need to be relocated;
•	Residents with special needs such as the elderly, families with children, and residents
with disabilities;
•	The number of non-English-speaking residents and the language they speak;
•	Information residents have about the relocation;
•	The number of businesses that will require relocation;
•	Whether mobile or manufactured residential homes must be acquired or moved;
•	Any outside groups working with the residents, e.g., an advocate;
•	The community members' willingness to relocate; and
•	Any particular local government, congressional or media attention on the site response or
the relocation.
3.	USACE will prepare a Real Estate Planning Report (REPR), or functional equivalent, for the
necessary acquisitions outlining the work to be completed, the estimated cost, and the
schedule for the work to be conducted and completed. The scope and depth of this document
will be determined by EPA. USACE shall delineate in this report all the tasks which will be
undertaken to ensure effective compliance with the URA and efficient implementation of
13

-------
Superfund Permanent Relocation Statement of Work Template and Users' Guide
permanent relocation. The document shall indicate who will be involved in the property
acquisition activities (title reviews, appraisals, negotiations, closing, etc.), and how these
activities will be conducted (in-house vs. contract).
Information and Hints for Completing the SOW
The RPM should give clear directions regarding what information should be contained in the REPR,
especially in terms of the scope of the report. REPR may not be necessary for small acquisitions such
as easements. Most REPRs that involve permanent relocation of residents and/or nonresidential
properties should include the following: background information on the site and the specific
properties to be acquired (this information will most likely come from existing site documents and is
helpful in documenting a need to acquire the properties); preliminary cost estimates including
USACE's administrative costs as well as the costs expected to be incurred by the USACE or its
contractors in acquiring the properties and relocating the residents and/or businesses; and a timeline
of when the work may be completed.
Delete this box by placing the curser on the box, clicking the right button, and selecting the
"Delete Box" option.
4.	Discuss the role of each member of the relocation team including the role of the EPA RPM
and CIC, and USACE Real Estate Project Manager (PM) when talking with residents.
5.	Lay out the process of notifying EPA's RPM of meetings requiring his/her involvement.
6.	If and when cost increases or schedule delays occur or are anticipated, USACE shall notify
the EPA's RPM as soon as the cost increase or schedule delay is known or suspected. This
action will be followed with the submission of an updated project cost estimate and/or time
schedule.
7.	The USACE Real Estate PM will delegate a point of contact (POC) for questions and
inquiries made by residents regarding their relocation and their relocation benefits.
8.	USACE will provide documents in the native language of the community.
9.	USACE will provide translators, when necessary, including sign language translators, at
public and private meetings.
Task 2: Coordination and Communication
Consistent and ongoing communication between USACE, EPA, and the community is critical.
1. USACE will be on site or otherwise available to meet with tenants and property owners.
Expectations regarding the items listed below should be clearly communicated between the
two agencies. The size and complexity of the relocation may be factors determining the need
for on-site availability. There are critical points in the acquisition/relocation process when
USACE availability will be essential, such as:
14

-------
Superfund Permanent Relocation Statement of Work Template and Users' Guide
•	All public meetings where relocation may be discussed;
•	Most meetings with individual tenants and property owners;
•	During and immediately after the release of appraisals;
•	During and immediately after the release of comparable housing;
•	During and immediately after the presentation of EPA's offer to acquire the property and
the comparable housing and relocation benefits package;
•	While residents are searching for replacement housing, especially in tight housing
markets;
•	On scheduled weeknights and weekends to meet with residents who work during the day;
•	At the closing of property acquisitions; and
•	Other times when residents may want a special meeting.
Information and Hints for Completing the SOW
EPA should decide which meetings between the USACE and the residents it wants to attend. USACE
must provide EPA with advance notice of these meetings with residents, tenants, and other owners.
The frequency may depend on the scope and complexity of the action and the interest or concerns of
the action held by the community. Refer to Part II of the Superfund Permanent Relocation Statement
of Work and Users ' Guide, "Important Considerations'' for additional tips on working with the
USACE and the community.
Delete this box by placing the curser on the box, clicking the right button, and selecting the "Delete
Box" option.
2.	When USACE conducts scheduled meetings with residents such as those listed below,
USACE will notify EPA in advance of:
•	Public meetings, including public availability sessions;
•	The release of appraisals; and
•	The discussions with each resident of EPA's offer to acquire their property and the
relocation benefits.
3.	USACE will provide the same attention to the questions and concerns of the community left
behind after the relocation as it does for those being relocated.
4.	The USACE should communicate any concerns these community members have to EPA.
15

-------
Superfund Permanent Relocation Statement of Work Template and Users' Guide
5.	All inquiries from the media or Members of Congress should be forwarded to EPA.
6.	USACE will provide the name and phone number of the EPA and USACE point-of-contact
to displaced persons.
Information and Hints for Completing the SOW
The team may determine that a toll-free phone number or a web page should be established to provide
property owners quick access to the relocation specialists, information, or site updates. USACE may
be tasked to respond to these information requests.
Delete this box by placing the curser on the box, clicking the right button, and selecting the "Delete
Box" option.
Task 3: Advisory Services
1. USACE shall provide relocation services and assistance to the occupants (homeowners and
tenants) of the residences pursuant to the requirements of the URA and any relevant
regulations promulgated thereunder. Information on the acquisition and assistance should be
provided verbally and in writing. These relocation services include, but are not limited to:
•	Explaining the government's offer to acquire their property, the housing differential,
rental or downpayment assistance payments and how they will be calculated, as well as
other financial assistance that may be provided;
•	Providing information on availability and costs of comparable replacement dwellings for
the purposes of calculating relocation benefits;
•	At a minimum, contacting residents a few days after their appraisals and benefits are
discussed and asking if they have any questions or concerns;
•	Explaining eligibility requirements;
•	Explaining procedures for obtaining assistance;
•	Supporting those residents who decide to locate housing on their own or with local real
estate agents;
•	Coordinating between government agencies and services (Housing and Urban
Development (HUD), Health and Human Services (HHS), USACE, EPA and
local/county governments);
•	Explaining the appraisal process;
•	Working closely with individuals and families in identifying comparable homes to ensure
their unique family needs are addressed;
16

-------
Superfund Permanent Relocation Statement of Work Template and Users' Guide
•	Explaining the relocation process (appraisals, benefits and the key milestones);
•	Providing transportation, if needed, to displaced persons in order to inspect available
housing;
•	Providing advice and explanations of other programs and sources of assistance available
to displaced persons;
•	Providing assistance in planning for decisions that need to be made or actions that need
to be taken by the individual being displaced;
•	Helping residents prepare their applications for assistance and other related forms; and
•	Explaining appeal rights and EPA's appeal process.
2.	The USACE shall be responsible for the processing, assessment, and payment of all
appropriate relocation assistance claims and appeals.
3.	USACE will provide homeowners with a clear and detailed explanation of what potential
expenses may or may not be compensated for under the URA. This will include a clear
statement of what the differential payment is and how it will be calculated.
Task 4: Appraisal and Acquisition
Information and Hints for Completing the SOW
The URA has requirements for conducting appraisals. Information on how to conduct appraisals that
meet the URA requirements is available at DOT/FHWA's web page,
http: //www. fhwa. dot. gov/realestate/apprais .htm. The RPM or other EPA member of the relocation
team should, in most cases, attend meetings with the property owners when appraisals are released.
Delete this box by placing the curser on the box, clicking the right button, and selecting the "Delete
Box" option.
1.	USACE shall prepare a map identifying each property to be acquired and the owner of each
property. The USACE also shall prepare a legal description and tract map, showing the
location of each property (revision of existing documents is acceptable). If specifically
requested by EPA or required for execution of the project, USACE also shall perform a
boundary survey and establish markers as necessary for acquisition.
2.	USACE shall provide EPA with title evidence of each property as required by the Standards
for the Preparation of Title Evidence in Land Acquisition by the United States (1970)
prepared by the U.S. Department of Justice. The form of the title evidence shall be
Certificates of Title or Policies of Title Insurance. The USACE shall further provide a title
opinion based on its delegation from the Department of Justice. The USACE shall provide a
list of recorded easements and other actual and potential encumbrances which may be
applicable to the subject property.
17

-------
Superfund Permanent Relocation Statement of Work Template and Users' Guide
3. USACE shall ensure the expeditious completion and review of appraisal reports for each
property element identified for acquisition. All appraisals shall be performed by a certified
appraiser and in accordance with the Uniform Appraisal Standards for Federal Land
Acquisition (1992) issued by the Interagency Land Acquisition Conference and Procedural
Guide for the Acquisition of Real Property by Government Agencies, each of which shall be
reviewed and approved by a USACE review appraiser.
Information and Hints for Completing the SOW
EPA should determine what additional instructions should be provided to appraisers. For example, it
is EPA's policy to appraise properties as if they were not contaminated by the Superfund site
hazardous substances.
Delete this box by placing the curser on the box, clicking the right button, and selecting the "Delete
Box" option.
4.	Prior to an appraiser contacting property owners, the USACE Real Estate PM and the
appraiser shall meet with EPA to review and approve instructions to the appraiser. In
conducting the appraisals, assume that the property is free of the hazardous substance that
prompted the response action. USACE shall encourage each owner to participate in the
appraisal of the property that he/she owns, and shall schedule the appraisal walk-through
date based on the owner's availability. USACE Real Estate PM or an EPA representative
shall participate in each appraisal walk-through. During each appraisal walk-through, the
USACE or EPA representative shall ask the property owner which removable fixtures the
owner intends to move and shall record whether each item of value will be moved or left on
the premises. Attached to the appraisal shall be a page listing the salvage value of each item
moved from the premises. If the property is contaminated and EPA will not decontaminate
the property, or if the real property will be sold rather than demolished, the salvage values do
not need to be determined.
5.	Salvage of fixtures and/or real property features may be reserved by the owners upon
approval from the USACE. The owners will be required to remove any such items on their
own after the property has been acquired, or no less than (specify a time period or date) prior
to initiation of demolition activities by EPA, whichever is first.
6.	Make sure all residents sign a release of liability form before they enter property once it has
been acquired.
7.	With prior approval from EPA, an owner may obtain his/her own appraisal and be
reimbursed for that expense. Owner initiated appraisals must meet the same standards and
requirements as the appraisal secured by the USACE. See Release of Appraisals for Real
Property Acquisition at Superfund Sites Guidance, OSWER Directive 9200.1-3 5P,
November 2000. This document is available on-line at http://www.epa.gov/oerrpage/
superfund/tools/topics/relocation.
18

-------
Superfund Permanent Relocation Statement of Work Template and Users' Guide
8.	The US ACE shall present property appraisals to the property owners as stated in the OSWER
Directive 9200.1-3 5P, Release of Appraisals For Real Property Acquisition at Superfund
Sites, November 2000.
9.	Based on the approved appraisal, USACE shall advise owners of the government's estimate
of the fair market value of the property and conduct negotiations with each owner. The
USACE Real Estate PM shall be on-site during (specify times) and during scheduled evening
and weekend hours to accommodate residents not available during the day. EPA shall be
informed of the dates of such scheduled negotiations sufficiently in advance for EPA to
attend such negotiations, at the option of EPA.
10.	The USACE shall prepare a negotiator's report (a written summary of the negotiations for
each tract).
11.	The USACE shall provide closing services for each property to be acquired. These services
shall include:
•	Procurement of checks for the acquisition;
•	Preparation of deeds and other closing papers;
•	Conducting closings with EPA representatives present (at EPA's discretion); and
•	Performing all activities necessary to acquire title by direct purchase.
12.	USACE shall coordinate with EPA on all procedures and standards to be used in closing on
the properties. A USACE attorney shall attend all closings for government acquisitions. Title
to all properties shall be in the name of the United States of America and its assigns. A final
title assembly, including final title opinion, shall be prepared by USACE for each tract
acquired.
13.	In the unlikely event that condemnation of a property is necessary, the USACE will consult
with EPA's Offices of Regional and General Counsel on the procedures to follow. After the
decision to condemn is approved by EPA, the USACE shall prepare all necessary
condemnation documents including a Declaration of Taking for execution by the Director of
Facilities Management and Services Division, EPA Headquarters. EPA Headquarters will
coordinate with the regional office and the USACE on the approval process for condemning
the property. The USACE will cooperate with and assist EPA and the Department of Justice
in prosecuting the condemnation through completion.
14.	If condemnation becomes necessary, a new appraisal will be required and the contamination
will be considered.
15.	The USACE will maintain the purchased property, including items such as grass cutting,
snow removal, security, etc., unless otherwise directed by EPA, until advised of its
disposition by EPA in accordance with the executed State Superfund Contract (SSC) upon
completion of the remedial actions. The acquisition and subsequent relocation will be in
accordance with the URA.
19

-------
Superfund Permanent Relocation Statement of Work Template and Users' Guide
Task 5: Relocation
1.	The USACE shall review real estate for sale in the (city) area that is comparable to the
properties to be acquired. The USACE shall meet with each owner/occupant and provide
information on the most nearly comparable dwelling (as defined in the URA, Section 24.2
(d)), and shall additionally list other comparable real estate in the area. USACE shall submit
to EPA a real estate package identifying the most comparable dwelling and other comparable
dwellings within 48 hours of the negotiations meeting with the residents.
2.	USACE will provide a property owner 30 days to review the government offer. Residents
may request an extension of this deadline. The USACE, with EPA's concurrence, may grant
a reasonable extension to allow owners time to review the information.
3.	Whenever a program or project cannot proceed on a timely basis because comparable
replacement dwellings are not available within monetary limits for owners or tenants as
specified in § 24.401 or § 24.402, the USACE shall provide additional or alternative
assistance under the provision of replacement housing of last resort. Any proposal for
provision of last resort housing shall be coordinated with EPA's RPM before the offer is
made to the residents.
Information and Hints for Completing the SOW
Tenants who have occupied their primary residence for at least 90 days are entitled to benefits as
described in 49 CFR 24.402, including a rent differential (the rent differential is the difference
between the rent they are currently paying and the rent of a comparable rental unit.). If the
comparable rental unit rent is higher than the rent at the primary address, multiply the difference by
42 months. The difference is called the rent differential.
Delete this box by placing the curser on the box, clicking the right button, and selecting the "Delete
Box" option.
4.	USACE should determine rent differentials for all tenants as described in 49 CFR 24.402. It
is EPA's policy that rent differentials greater than $10,000 should be made in installment
payments rather than a lump sum payment. The number and timing of the installment
payments should be determined by the team. If a tenant plans to use his or her rent
differential as part of a down payment on the purchase of a new home, USACE should
provide the lump sum payment at the time of closing on the new home.
5.	In the case of last resort housing, including last resort housing for tenants, the USACE will
provide detailed documentation to EPA on the extent of the housing search and the results of
that search. USACE also should notify EPA if the most appropriate comparable housing
includes features not available in the property to be acquired, for example, if the comparable
has significantly more square footage than the housing to be acquired.
6.	Since housing of last resort payments can be very high, it is critical that every effort be made
to find comparable housing within a reasonable price range. If at least one comparable
replacement house cannot be found, document the extent of the housing search conducted
20

-------
Superfund Permanent Relocation Statement of Work Template and Users' Guide
and the justification for most appropriate comparable housing. The team should keep in mind
that in some cases, more costly housing comes with higher property taxes and sometimes
increased utility costs. The URA does not currently provide for these increased costs, and
some residents may have trouble paying them or may not be able to afford them.
Information and Hints for Completing the SOW
There are several options available for moving resident's personal property. The best option may
depend on the desire of the residents and scope and complexity of the move. All displaced owner-
occupants or tenants are entitled to payment for their actual moving and related expenses as described
in the regulations, §24.301. USACE may arrange for a moving company to pack and move personal
property, or the residents may work directly with a moving company and seek reimbursement for
actual, reasonable expenses. Residents also have the option to receive a fixed payment for moving
expenses. This payment shall be determined according to the applicable schedule approved by the
Federal Highway Administration found at http://www.fhwa.dot.gov/realestate/fixsch96.htm. The
USACE should ensure that the moving company offers proper warranties for their work including
replacement value for damaged property.
Delete this box by placing the curser on the box, clicking the right button, and selecting the "Delete
Box" option.
7.	USACE shall work with the relocation team and the residents to determine the best method
of moving personal property. If it is determined that the government will make the moving
arrangements, USACE will arrange (under contract as determined by USACE) for packing
and moving of the residents' personal property to the replacement housing. If the residents
are to make arrangements to have their personal property moved, USACE will provide
instructions (2 or 3 bids from reputable moving companies who provide appropriate
warranties are required) and reimbursement to the residents. Finally, USACE will provide a
fixed payment to residents who prefer to use the move schedule (Uniform Relocation
Assistance and Real Property Acquisition Policies Act, Residential Moving Expense and
Dislocation Allowance Payment Schedule). The move schedule can be found at
http://www.fhwa.dot.gov/realestate/fixsch96.htm. USACE should coordinate with property
owners to assure they are available or have a representative available at the property when
movers are working.
8.	USACE will process and pay all relocation assistance claims deemed appropriate.
Task 6: Follow-up
After the relocation, USACE should arrange a follow-up meeting with each property owner and
tenant to discuss any problems. The EPA RPM or other key team member should attend these
meetings.
Task 7: Appeals
USACE should follow procedures documented in OSWER Directive 9355.0-88, Process of
21

-------
Superfund Permanent Relocation Statement of Work Template and Users' Guide
Handling Appeals of Permanent Relocation Decisions, February 13, 2003.
Task 8: Reporting
1.	During the project, USACE shall provide a monthly summary to EPA's RPM. The summary
should be submitted within 15 calendar days of the completion of the reporting period and
contain, at a minimum, the work performed by USACE during the reporting period: project
costs to date; an estimate of remaining costs to project completion; status of contracts
administered by the USACE; summaries of all contacts with representatives of public
interest groups and state or local government; and summaries of all problems encountered.
2.	The URA requires that the lead Agency, DOT/FHWA, report periodically on the real
property acquisition and relocation activities under the URA. EPA will report annually to the
lead Agency which will in turn report to Congress. To meet its reporting requirements, EPA
developed a Property Acquisition/Relocation Statistical Report Form that captures the data
DOT/FHWA may request. USACE shall complete the site-specific Property
Acquisition Relocation Statistical Report Form, attached here as Attachment 1 (Attachment 2
provides instructions for completing the form), soon after September 30, but no later than
November 15, of every fiscal year. If a project ends within the fiscal year, the USACE may
complete this form and submit it at that time. A copy of the form should be provided to the
EPA RPM and a second copy should be sent to USEPA, the Regional Support Branch
1,2,6,9,10, Office of Superfund Remediation and Technology Innovation, mail code 5202G,
1200 Pennsylvania Ave. NW, Washington DC, 20460.
Task 9: Project Management and Close-out
Information and Hints for Completing the SOW
Some records must be retained with the Administrative Record, others are necessary to support cost
recovery and any appeals or suits against the government brought by relocated residents. Other
records may be less significant. Regions should work with ORC and their records management
experts to determine which records should be retained and forwarded to EPA.
Delete this box by placing the curser on the box, clicking the right button, and selecting the "Delete
Box" option.
After completion of the acquisition and relocation process and conveyance of all property
interests to the State, all files, maps, and other documents related to the acquisition and
relocation (including all originals) should be forwarded to EPA Headquarters Facilities
Management Services Division within 180 days. The USACE also shall provide the RPM with a
summary of the expenditures and the remaining balance in the IAG to be returned to EPA.
22

-------
Attachment 1
Property Acquisition/Relocation Statistical Report Form
Federal Fiscal Year Ending Sept. 30, 20	.
Superfund Site:	
City/County:	State:	 Date of Report:
Part A. Real Property Acquisition under the Uniform Act
1) Total Number of Parcels Acquired (Ownerships)

2) Number of Parcels in Line 1 Acquired by Condemnation

3) Number of Parcels in Line 1 Acquired by Administrative Settlement (Above initial offer-see 24.102 (I))

4) Compensation - Total Costs (Including 24.106; Excluding appraisal costs, negotiator fees and other administrative
expenses)

Part B. Residential Relocation under the Uniform Act
5) Total Number of Residential Displacements (Households)

6) Residential Moving Payments - Total Costs

7) Replacement Housing Payments - Total Costs

8) Number of Last Resort Housing Displacements in Line 5 (Households)

9) Number of Tenants Converted to Homeowners in Line 5 (Households using 24.402©))

10) Total Costs for Residential Relocation Expenses and Payments (Sum of lines 6 and 7; excluding administrative costs)

Part C. Nonresidential Relocation under the Uniform Act
11) Total Number of Non-Residential Displacements

12) Non-Residential Moving Payments - Total Costs (Including 24.305)

13) Non-Residential Reestablishment Payments - Total Costs

14) Total Costs for Nonresidential Relocation Expenses and Payments (Sum of lines 12 and 13; excluding EPA/USACE
administrative costs)

Part D. Relocation Appeals under the Uniform Act
15) Total Number of Relocation Appeals (Residential & Non-Residential)


-------
Superfund Permanent Relocation Statement of Work Template and Users' Guide
Attachment 2
Instructions for Property Acquisition/Permanent Relocation
Statistical Report Form
1.	Report coverage. This report covers all relocation and real property acquisition activities
conducted under the Comprehensive Environmental Response Compensation Liability Act
(CERCLA) subject to the provisions of the Uniform Relocation Assistance and Real Property
Acquisition Policies Act of 1970, as amended.
2.	Report period. Activities shall be reported on a Federal fiscal year basis, i.e., October 1 through
September 30.
3.	Where and when to submit report. Submit a copy of this report to EPA Headquarters, Attention
OSRTI, Regional Support Branch 1,2,6,9,10, 5202G, 1200 Pennsylvania Ave. NW, (5202G),
Washington DC, 20460 as soon as possible after September 30, but NOT LATER THAN
NOVEMBER 1. Acquisitions and/or relocations that are completed during the fiscal year may be
reported any time in that fiscal year. The information will be tabulated and forwarded to the
DOT/FHWA who has the responsibility for reporting this information to Congress.
4.	How to report relocation payments. The full amount of a relocation payment shall be reported as
if disbursed in the year during which the claim was approved, regardless of whether the payment
is to be paid in installments.
5.	How to report dollar amounts. Round off to the nearest dollar all money entries in Parts A, B and
C of this section.
6.	Regulatory references. The references in Parts A, B, C and D of this section indicate the subpart
of the regulations pertaining to the requested information
Part A. Real Property Acquisition Under the Uniform Act
Line 1. Report all parcels acquired during the report year where title or possession was vested during
the reporting period. The parcel count reported should relate to ownerships and not to the number of
parcels of different property interests (e.g., fee, perpetual easement, temporary easement, etc.) that
may have been part of an acquisition from one owner. For example, an acquisition from a property
that includes a fee simple parcel, a perpetual easement parcel, and a temporary easement parcel
should be reported as 1 parcel not 3 parcels. (Include parcels acquired without Federal financial
assistance, if there was or will be Federal financial assistance in other phases of the project or
program.)
Line 2. Report the number of parcels reported on Line 1 that were acquired by condemnation.
Include those parcels where compensation for the property was paid, deposited in court, or otherwise
made available to a property owner pursuant to applicable law in order to vest title or possession in
EPA through condemnation authority.
Line 3. Report the number of parcels in Line 1 acquired through administrative settlement where the
purchase price for the property exceeded the amount offered as "Just Compensation" and efforts to
negotiate an agreement at that amount have failed.
24

-------
Superfund Permanent Relocation Statement of Work Template and Users' Guide
Line 4. Report the total of the amounts paid, deposited in court, or otherwise made available to a
property owner pursuant to applicable law in order to vest title or possession in the acquiring Agency
in Line 1.
Part B. Residential Relocation Under the Uniform Relocation Act
Line 5. Report the number of households which were permanently displaced during the fiscal year by
project or program activities and moved to their replacement dwelling. The term "households"
includes all families and individuals. A family shall be reported as "one" household, not by the
number of people in the family unit.
Line 6. Report the total amount paid for residential moving expenses (actual expense and fixed
payment).
Line 7. Report the total amount paid for residential replacement housing payments including
payments for replacement housing of last resort provided pursuant to § 24.404 of this part.
Line 8. Report the number of households in Line 5 who were permanently displaced during the fiscal
year by project or program activities and moved to their replacement dwelling as part of last resort
housing assistance.
Line 9. Report the number of tenant households in Line 5 who were permanently displaced during
the fiscal year by project or program activities, and who purchased and moved to their replacement
dwelling using a down payment assistance payment under this part.
Line 10. Report the total sum costs of residential relocation expenses and payments (excluding
Agency administrative expenses) in Lines 6 and 7.
Part C. Nonresidential Relocation Under the Uniform Act
Line 11. Report the number of businesses, nonprofit organizations, and farms which were
permanently displaced during the fiscal year by project or program activities and moved to their
replacement location. This includes businesses, nonprofit organizations, and farms, that upon
displacement, discontinued operations.
Line 12. Report the total amount paid for nonresidential moving expenses (actual expense and fixed
payment.)
Line 13. Report the total amount paid for nonresidential reestablishment expenses.
Line 14. Report the total sum costs of nonresidential relocation expenses and payments (excluding
Agency administrative expenses) in Lines 12 and 13.
Part D. Relocation Appeals
Line 15. Report the total number of relocation appeals filed during the fiscal year by aggrieved
persons (residential and nonresidential).
25

-------