APPENDIX OSWER 9283.1-38 This appendix represents data submitted on the status of the progress of recommendations as of the January 2012 tracking and follow up period. The status of the progress of recommendations from prior tracking periods can be found in previous Progress Reports, referenced in the reference section of this report. These reports are available online at http://www.epa.gov/superfund/cleanup/postconstruction/optimize.htm. ------- RSE Recommendations and Progress Toward Implementation Region 2 Site Name: GCL Tie & Treating (Sidney, NY) Recommendation Status EPA ID#: NYD981566417 RSE Report: EPA 542-R-06-016 (December 2006) Progress since the previous progress report Remedy l-'.ITecli\euess 6.1.1 Institute a routine ground water monitoring program 6.1.2 Optional plume delineation 6.1.3 Soil vapor intrusion evaluation Cosl Reduction 6.2.1 Discontinue pumping from the intermediate zone Implemented Implemented Implemented Implemented 6.2.2 Consider modifications to the Under backwashing and solids handling procedures Consideration (contingent of outcome of 6.2.1) 6.2.3 Suggestions for long-term ground Implemented water monitoring 6.2.4 Pilot test bypassing the air stripper Declined 6.2.5 Consider a hybrid time and materials Alternative and fixed-price contract Implemented 6.2.6 Reductions in project management Implemented consistent with steady state system operation Technical lmprn\cmcnl 6.3.1 Relocate equalization tank high-level Implemented switch 6.3.2 Discontinue use and service to Declined generator 6.3.3 Modify use of water levels from Planned operating extraction wells when developing potentiometric surface maps The recommendation is still on hold. At this point, there is no need for modifications. This recommendation would be implemented during the generation of the 2011 annual monitoring well sampling report which is currently being drafted. OSWER 9283.1-38 Appendix July 2012 Page 1 of 37 ------- RSE Recommendations and Progress Toward Implementation Region 2 Site Name: Vineland Chemical Co. (Vineland, NJ) Recommendation Status EPA ID#: NJD0023 85664 RSE Report: EPA-542-R-11-007 (November 2011) Progress since the previous progress report Remedy l\ITec(i\eness 6.1.1 Further characterize extent of contamination 6.1.2 Consider modifications to the groundwater extraction system to assure capture 6.1.3 Additional monitoring of groundwater In progress quality between extraction wells and Blackwater Branch ( osi Reduction 6.2.1 Discontinue automated sampler and do In progress not replace the unit In progress An evaluation is currently underway to further our understanding of contaminant release and migration processes on site. See also 6.1.3 and 6.4.2. In progress Plume capture is under investigation and continues to be evaluated. Elevated levels of arsenic in select areas northwest and southwest of main plant property appear not to be a source, but related to a residual or remnant plume contamination. In the summer/fall of 2011, monitoring wells were installed in 11 locations, 8 were nested (located along the Blackwater Branch) for a total of 19 new wells. 6.2.2 Eliminate routine on-site arsenic sampling 6.2.3 Reduce extraction rates to those that are necessary for plume capture 6.2.4 Evaluate groundwater monitoring costs 6.2.5 Continue to optimize groundwater monitoring program 6.2.6 Focus building heating and lighting on Under key process area consideration 6.2.7 Evaluate chemical usage The team agreed that the risk of turning off the OVA and discontinuing the use of the graphite furnace is minimal, considering we normally treat well below the permitted discharge level of 50ppb, and that most other plants do not have such a conservative sampling setup. The contractor will provide a cost estimate for savings associated with discontinuing the use of the OVA and graphite furnace. The project team will evaluate potential reductions in sampling frequency. This has been discussed, and a further evaluation by US ACE is underway. This has been discussed, and a further evaluation by US ACE is underway. All extraction wells are now computerized. Optimization (for cost and quality control) activities will continue on site. The last round of optimization included: computerization of operations control to reduce labor on site, piping changes to enhance process efficiency/ performance, optimizing chemical usage to reduce costs, and the adjustment of well development protocols. After an exit strategy is decided upon, EPA will ask US ACE and site contractor to determine feasibility and costs associated with recommendations 6.2.6, 6.2.7, and 6.2.8. Under After an exit strategy is decided upon, EPA will ask US ACE and site contractor to determine consideration feasibility and costs associated with recommendations 6.2.6, 6.2.7, and 6.2.8. Planned Under consideration Under consideration Implemented OSWER 9283.1-38 Appendix July 2012 Page 2 of 37 ------- RSE Recommendations and Progress Toward Implementation Region 2 Site Name: Vineland Chemical Co. (Vineland, NJ) EPA ID#: NJD0023 85664 RSE Report: EPA-542-R-11-007 (November 2011) Recommendation Status Progress since the previous progress report 6.2.8 Consider use of a plate and frame filter press to dewater solids In progress The team agreed that an existing plate and frame filter press could be a good way to reduce waste disposal. The RSE team and site contractor will research availability of a unit from another site and provide a cost estimate for removing unit from the existing location, installation and operation. 6.2.9 Consider the use of lime for pH adjustment Declined The team agreed that employing a lime system would have high capital cost and operational issues that make it impractical for this site. 6.2.10 Continue to streamline plant and project staffing In Progress Efficient labor utilization is a primary goal of the project team. 6.2.11 Based on outcome of other recommendations, consider potential for delisting waste sludge Declined A Superfund finding is in place for washed media reuse and evaluating contained-in policy for waste/media disposal practices. The sludge appears to be too concentrated with arsenic to allow for de-listing. Technical lmprn\cmcnl 6.3.1 Refine well rehabilitation practices Implemented Monthly well meetings are conducted to evaluate system performance for optimized extraction and well field pumping is adjusted accordingly. 6.3.2 Discontinue use of curtains and electrical heaters for sand filters Under consideration Site contractor will look into this item and provide recommendations. 6.3.3 Continue with plan to remove soil washing equipment from the site Under consideration Evaluation of soil washing for River Areas/Union Lake still needs to be conducted. As of January 2012, the equipment is still under consideration for use in later phases of this project. 6.3.4 Prepare an annual report In Progress US ACE is currently compiling a report that summarizes work done since 2000. A five year review for Vineland Chemical was finalized in September 2011. Progress Toward Cleanup (ioals 6.4.1 Evaluate potential for natural attenuation and suggested criteria for discontinuing P&T In Progress Continued operation of the P&T is imperative as system shutdown will result in discharges to surface water exceeding the ROD criteria. The US ACE is currently evaluating the potential for MNA. 6.4.2 Active in-situ treatment for arsenic immobilization In Progress Based on the RSE recommendation, an evaluation of arsenic immobilization technologies is underway. Geochemical data was collected in the summer of 2011 to support overall understanding of contaminant release/migration processes, provide baseline data for both immobilization and mobilization enhancement technology strategic planning. More sampling is scheduled for the spring/summer of 2012 6.6.1 Suggested exit strategy In Progress The US ACE is currently carrying out investigations in response to the RSE recommended approach. OSWER 9283.1-38 Appendix July 2012 Page 3 of 37 ------- RSE Recommendations and Progress Toward Implementation Region 2 Site Name: Vineland Chemical Co. (Vineland, NJ) Recommendation Status EPA ID#: NJD0023 85664 RSE Report: EPA-542-R-11-007 (November 2011) Progress since the previous progress report (irccn Kcmcdialion 6.7.1 Consider combined heat and power 6.7.2 Consider alternatives for iron addition 6.7.3 Postpone lighting retrofit Planned Under Consideration Planned The team agreed that a newer, greener system is desirable, if feasible. The site contractor will get vendor estimates for new gas generator systems (i.e., Bloom Box, or micro turbine). Another added feature to check on is the use of any excess waste heat from the system to be focused on drying the sludge more to decrease waste disposal costs. After an exit strategy is decided upon, EPA will ask US ACE and site contractor to determine feasibility and costs associated with recommendations 6.71, 6.7.2, and 6.7.3. All agreed to try out a new high bay fixture (manufacture brand to be provided by US ACE) before purchasing for the entire plant. OSWER 9283.1-38 Appendix July 2012 Page 4 of 37 ------- RSE Recommendations and Progress Toward Implementation Region 2 Site Name: Tutu Wellfield (Tutu Wellfield, VI) Recommendation Status EPA ID#: VTD982272569 RSE Report: EPA-542-R-11-008 (November 2011) Progress since the previous progress report Remedy l\ITcc(i\eness 6.1.1 Hydraulic Containment 6.1.2 No Additional Downgradient Active Remediation 6.1.3 Curriculum Center Vapor Intrusion Resampling 6.1.4 Include MTBE Analysis Cost Reduction 6.2.1 Improve Contracting Efficiency 6.2.2 Termination of GWTF #2 Operation 6.2.3 Reduce Operator Visits including Decreasing Well Gauging Frequency 6.2.4 Eliminate Emissions Sampling at GWTF #1 Technical lmprn\cmcnl 6.3.0 Remove excess air discharge ducting and consider air strippers with less power requirements Progress Toward Cleanup Coals Planned The site team developed a detailed scope including adding four extraction wells, hooking them up to the system and start-up tasks as well as one additional monitoring well. The site team obtained contractor costs for this work and project costs at over $500,000 not including CDM Smith management versus the RSE estimate of $210,000. Implementation has been delayed due to lack of available funding. The RSE team has not seen the detailed work scope or contractor submittals to comment on the difference between the cost estimates. Implemented The site team has not changed the current approach. Implemented Implemented Deferred to State or PRP Under Consideration Deferred to State or PRP Under Consideration Under Consideration 6.4.0 Considerations for Gaining Site Close Under Out Consideration The vapor intrusion resampling was conducted in December 2011, results are not yet available. Total costs for the work will be about $35,000 versus the $45,000 RSE estimate The site team reports that MTBE analysis is occurring as part of the VOC scan. MTBE results were relatively low or non-detect so that MTBE migration is not a concern. The site team stated that these changes cannot be implemented under the current contract which will run until the turnover to USVI. The USVI should consider the recommendations after the turnover. The site team plans to wait until the hydraulic containment improvements are completed at GWTF #1 before implementing this recommendation. The site team stated that these changes cannot be implemented under the current contract which will run until the turnover to USVI. The USVI should consider the recommendations after the turnover. The site team will consider writing a letter to USVI to eliminate this redundant sampling requirement. The site team noted that analysis is being done by the USEPA CLP lab. The site team plans to wait until the hydraulic containment improvements are completed at GWTF #1 before implementing this recommendation. The site team plans to wait until the hydraulic containment improvements are completed at GWTF #1 before implementing this recommendation. OSWER 9283.1-38 Appendix July 2012 Page 5 of 37 ------- RSE Recommendations and Progress Toward Implementation Region 2 Site Name: Tutu Wellfield (Tutu Wellfield, VI) EPA ID#: VID982272569 RSE Report: EPA-542-R-11-008 (November 2011) Recommendation Status Progress since the previous progress report (irccn Kcmcdialion 6.5.0 Consider alternative effluent discharge Under No further action has been taken to date, and energy sources Consideration OSWER 9283.1-38 Appendix July 2012 Page 6 of 37 ------- RSE Recommendations and Progress Toward Implementation Region 3 Site Name: Mill Creek Dump (Erie County, PA) Recommendation Status EPA ID#: PAD980231690 RSE Report: EPA-540-R-10-014 (February 2010) Progress since the previous progress report Remedy l\ITec(i\eness 6.1.1 Further Characterize Extent of Implemented Contamination 6.1.2 Install Additional Points for Water Implemented Level Measurements 6.1.3 Conduct a Shutdown and Restart Test of the Extraction System 6.1.4 Document the Findings from the Implemented Above Events, Use Findings for Capture Zone Analysis 6.1.5 Automate Chemical Feeds or Provide Declined Appropriate Interlocks to Discontinue Chemical Feeds if One or More Extraction Trenches Discontinue Operation 6.1.6 If Off-Site Shallow Contamination is Implemented Identified and Determined to be Related to the Site, Conduct a Vapor Intrusion Evaluation Cosl Reduction 6.2.1 Discontinue April Sampling Event Implemented 6.2.2 Discontinue Analysis for Dissolved Planned Metals 6.2.3 Streamline Process Sampling Declined 6.2.4 Revisit Data and Reporting Costs Implemented DPT sampling was conducted at 18 locations, with 35 samples collected in August 2010. Results indicate the most offsite locations sampled do not have contamination. Two locations at the northern edge of the site (near the pond) had DCE and vinyl chloride contamination above ROD screening levels. Results are still being evaluated with respect to the modeling and capture zone analysis discussed in 6.1.4. Six new monitoring wells were installed in November 2010, consistent with the RSE recommendation. Implemented Conducted in December 2010. A MODFLOW model has been developed using findings from the above field investigations. Separate comments were provided by the RSE team on the capture zone document and modeling report. It was determined that nothing in the system requires changing, as the one main release occurred as a result of human error. Five residences were sampled in December 2010. Results did not demonstrate a vapor intrusion problem. The April event was conducted in April/May 2011, however it has been discontinued starting in 2012. The site team agrees with this recommendation and will implement it in 2012. With the current treatment plant staffing, the suggested revisions to process monitoring will not result in savings. Therefore, the site team will not make the adjustment. The site team reports that the semi-annual report has been eliminated, resulting in savings of $8,350. No other changes were reported to the data and reporting costs. OSWER 9283.1-38 Appendix July 2012 Page 7 of 37 ------- RSE Recommendations and Progress Toward Implementation Region 3 Site Name: Mill Creek Dump (Erie County, PA) Recommendation Status EPA ID#: PAD980231690 RSE Report: EPA-540-R-10-014 (February 2010) Progress since the previous progress report 6.2.5 Reduce or Eliminate Lime Conditioning of Sludge Technical lmprn\cmcnl 6.3.1 Cleanup of Treatment Plant 6.3.2 Considerations Regarding Treatment Plant Modifications, if Necessary Progress Toward Cleanup Coals 6.4.1 Determining a Path Forward (irccn Remediation 6.5.1 Revised Approach to Metals Removal 6.5.2 Considerations for Renewable Energy at the Site Planned PADEP's contractor will reduce the lime conditioning, initially by 50%, and evaluate the effectiveness. The contractor will then adjust the amounts to determine the optimum conditions. Implemented The treatment plant has been cleaned and organized. Under PADEP, which is responsible for operating the remedy, will need to revisit this Consideration recommendation before making a decision to implement it. Under The site team recognizes the need to determine a path forward and relayed that the Five-Year Consideration Review includes delineation of contamination as an issue to be resolved. Under PADEP, which is responsible for operating the remedy, will need to revisit this Consideration recommendation before making a decision to implement it. Declined The site team reports several failures of renewable energy projects in the area (not site related) and will postpone consideration of renewable energy at the site for the foreseeable future. OSWER 9283.1-38 Appendix July 2012 Page 8 of 37 ------- RSE Recommendations and Progress Toward Implementation Region 4 Site Name: Alaric Area Groundwater Plume (Tampa, FL) Recommendation Status EPA ID#: FLDO12978862 RSE Report: EPA-540-R-10-013 (January 2010) Progress since the previous progress report Remedy l\ITcc(i\eness 6.1.1 Carefully Determine an Appropriately Conservative Buffer when Informing the State of Plume Extent Related to Establishing Ground Water Restrictions 6.1.2 Analyze Process Water Periodically for Constituents of Concern from the Helena Chemical Site 6.1.3 Simplify System Controls 6.1.4 Monitor Specific Capacity in Recovery and Reinjection Wells 6.1.5 Interpret Capture Cosl Reduction 6.2.1 Modify VOC Treatment 6.2.2 Consider Discharging to the Shallow Implemented Zone 6.2.3 Characterize GAC Again and Investigate Source of Radioactivity in an Attempt to Dispose of GAC as Non- Hazardous Waste or to Regenerate It 6.2.4 Track Routine O&M Costs Separately from Non-Routine Costs Technical lmpm\cmcnl 6.3.1 Consider the Following Comments to the May 2009 Technical Review by the Site Contractor Under More extensive work on the groundwater plume will be conducted once source area soils are consideration addressed. The timeline for a site-wide FS and final ROD is approximately 3+ years after implementation of the source zone remedy. Implemented After the system was restarted in May 2011, the site team conducted process sampling that included a broader suite of contaminants, including pesticides. This sampling is planned to occur on a semi-annual basis. The site team reports that there were low-level detections of pesticides in some of the recovery wells and that there were no detections in the effluent. Implemented The existing complex control system was simplified. Implemented These monitoring activities will occur during system operation when the system is restarted. Under This item has been discussed, and there is general consensus that it is needed. Consideration Alternative The treatment system has been updated with a new air stripper, new piping, and addition of Implemented sequestering agents. The treated water is now discharged to the shallow aquifer through the existing infiltration galleries. Implemented March 22, 2011 - The previous detection of radioactivity is expected to be a one-time issue. The GAC is due for changeout and will be characterized prior to disposal. Implemented A cost tracking system has been set up for GeoSyntec with separate routine and non-routine line items. Implemented The treatment plant upgrades have been completed. OSWER 9283.1-38 Appendix July 2012 Page 9 of 37 ------- RSE Recommendations and Progress Toward Implementation Region 4 Site Name: Alaric Area Groundwater Plume (Tampa, FL) Recommendation Status EPA ID#: FLDO12978862 RSE Report: EPA-540-R-10-013 (January 2010) Progress since the previous progress report Progress Toward Cleanup Coals 6.4.0 Considerations for Gaining Site Close Alternative Out Implemented In-situ thermal treatment will replace the in-situ chemical oxidation remedy previously used to address source area soils. The other potentially contaminated areas and plume area will be considered once the source area has been addressed. The design for the in-situ thermal remedy is underway. OSWER 9283.1-38 Appendix July 2012 Page 10 of 37 ------- RSE Recommendations and Progress Toward Implementation Region 4 Site Name: Benfield Industries (Waynesville, NC) Recommendation Status EPA ID#: NCD981026479 RSE Report: EPA 542-R-07-020 (September 2007) Progress since the previous progress report Remedy l\ITcc(i\eness 6.1.1 Document potential downgradient Declined receptor locations and adjust monitoring locations if necessary 6.1.2 Consider sampling for dioxins/furans Declined in soil 6.1.3 Document rationale for eliminating In progress metals analysis ( ost Reduction The ROD amendment now planned to be completed by May 2015, and will address this issue. 6.2.1 Do not restart the extraction system Implemented 6.2.2 Consider monitored natural attenuation In progress as the ground water remedy Technical lmpm\cmcnl 6.3.1 Improve sampling and analysis Implemented methods/reports Progress Toward Cleanup Coals 6.4.1 Assess feasibility and cost-benefit of In progress in-situ treatment of remaining soil hot spot(s) 6.4.2 Consider reassessing the cleanup In progress criterion for 1,4-Dichlorobenzene The draft MNA report was completed in July 2011 and reviewers found lines of evidence did not support an MNA remedy without addressing some remaining hot spots. The contractor is currently working on plans to identify and address the remaining hot spots followed by writing the draft ROD amendment. It is anticipate to take three years to complete this assignment by May 2015 (FY 2015). The past five sampling events have used analytical methods that provide reporting limits at or below the current ROD cleanup levels. The ROD amendment is now anticipated to be complete by May 2015. The contractor is currently working on plans to identify and address the remaining hot spots followed by writing the draft ROD amendment. It is anticipate to take three years to complete this assignment by May 2015 (FY 2015) The ROD amendment will now be completed by May 2015. OSWER 9283.1-38 Appendix July 2012 Page 11 of 37 ------- RSE Recommendations and Progress Toward Implementation Region 4 Site Name: American Creosote Works (Pensacola, FL) Recommendation Status EPA ID#: FLD008161994 RSE Report: EPA-540-R-06-068 (June 2006) Progress since the previous progress report Remedy l\ITec(i\eness 6.1.1 Continue revisiting soil cleanup levels In progress and ACLs 6.1.2 Consider potential vapor intrusion Implemented 6.1.3 Revise program for determining GAC Implemented replacement 6.1.4 Evaluate options to implement stronger institutional controls Cosl Reduction Under Consideration 6.2.1 Revise ground water sampling program Alternative Implemented 6.2.2 Review labor costs once system Implemented operation has stabilized Technical lmprn\cmcnl 6.3.1 Re-pipe DNAPL line from treatment Implemented shed to DNAPL storage tank Progress Toward Cleanup Coals 6.4.1 Modifications intended to gain site In progress close-out EPA is in the process of finalizing the Focused FS for ACW. A sitewide ROD is scheduled for summer 2012. There are still discussions of where the low level dioxin impacted soil will be deposited (possible onsite and offsite locations). An air stripper unit was added to the system. This unit will extend the lifetime of the GAC of the system. It is estimated that it will pay for itself in the first year of operation. EPA and FDEP are still looking into implementing institutional controls onsite. The development of groundwater ICs will require more investigation work. The ICs will be included in n sitewie ROD scheduled to be done by September 2012 A sitewide ROD is scheduled for summer 2012. This ROD will revisit the site's groundwater remedy and possibly the cleanup goals. One of the possible remedies is a containment strategy utilizing a barrier wall around the DNAPL source area. OSWER 9283.1-38 Appendix July 2012 Page 12 of 37 ------- RSE Recommendations and Progress Toward Implementation Region 4 Site Name: Cape Fear Wood Preserving (Fayetteville, NC) EPA ID#: NCD003188828 RSE Report: EPA-542-R-05-005 (February 2005) Recommendation Status Progress since the previous progress report Remedy l\ITcc(i\eness 6.1.1 Install and sample a monitoring well Implemented downgradient of MW-16 6.1.2 Sample outer monitoring wells Implemented annually 6.1.3 Do not use water levels from operating Implemented recovery wells or infiltration galleries when generating potentio-metric surface maps Cost Reduction 6.2.1 Contract O&M services and ground water sampling to a local contractor 6.2.2 Eliminate select wells from monitoring program, and reduce sampling and reporting frequency to annually Technical lmpro\cmcnl 6.3.1 Consider alternatives before adding a sequestering agent 6.3.2 Reduce frequency of water level measurements, discontinue dissolved oxygen monitoring, and simplify O&M reporting 6.3.3 Add a suffix to well labels to indicate shallow and deep wells Progress Toward Cleanup Coals 6.4.1 Evaluate effectiveness of various remedy components Implemented Implemented Implemented Implemented Implemented Alternative Implemented OSWER 9283.1-38 Appendix July 2012 Page 13 of 37 ------- RSE Recommendations and Progress Toward Implementation Region 4 Site Name: Cape Fear Wood Preserving (Fayetteville, NC) Recommendation Status EPA ID#: NCD003188828 RSE Report: EPA-542-R-05-005 (February 2005) Progress since the previous progress report 6.4.2 Considerations for evaluating thermal Alternative pilot study Implemented The thermal study was completed. The tech. memo evaluating the 3 scenarios was completed. The 3 scenarios evaluated include 1) STAR with ISCO (activiated persulfate), 2) steam injection with ISCO (activiated persulfate), and 3) stabilization on Site with thermal treatment along Reilly Road followed by ISCO ISCO (activiated persulfate). All three of these options would be followed by MNA. A final determination regarding changing the remedy and implement any of these alternatives has not been made at this time. The Site is on schedule to be transferred to the State for implementation LTRA of the existing remedy by July 2012. EPA is looking into the logistics of potentially changing the remedy in the near future. OSWER 9283.1-38 Appendix July 2012 Page 14 of 37 ------- RSE Recommendations and Progress Toward Implementation Region 5 Site Name: Ott/Story/Cordova Chemical Co. (Dalton Township, MI) Recommendation Status EPA ID#: MID060174240 RSE Report: EPA 542-R-02-008s (March 2002) Progress since the previous progress report Cost Reduction 6.2.1 Replace DAS units with tray aerators Declined or packed towers 6.2.2 Reexamine NPDES permit and Declined potentially bypass PACT system 6.2.3 Reduce process monitoring and Implemented analysis 6.2.4 Reduce aquifer monitoring and analysis Implemented 6.2.5 Remove excess equipment and do not Declined construct the planned storage building 6.2.6 Evaluate potential reduction in onsite Implemented presence of US ACE 6.2.7 Remove trailers from site Implemented 6.2.8 Have onsite staff conduct sampling for Alternative OU3 Implemented Technical lmprn\cmcnl 6.3.1 Establish consistent sampling method 6.3.2 Modify program for water-level measurement Progress Toward Cleanup Coals 6.4.1 Establish agreement between the OU2 remedy and ROD Implemented Implemented In progress Consistent with the requirements of the 2007 Five Year Review, a "Remedial Strategy Analysis" continues. The transfer of portions of the LTRA to the State occurred on February 1, 2011. The State of Michigan identified numerous outstanding issues with the remedy. EPA continues to partner with the State to address remedy issues until cleanup goals are reached, including this RSE recommendation. OSWER 9283.1-38 Appendix July 2012 Page 15 of 37 ------- RSE Recommendations and Progress Toward Implementation Region 5 Site Name: Douglas Road/Uniroyal, Inc., Landfill (St. Joseph County, IN) Recommendation Status EPA ID#: IND980607881 RSE Report: EPA 542-R-04-031 (February 2004) Progress since the previous progress report Remedy l\ITec(i\eness 6.1.1 Sample extraction wells annually 6.1.2 Investigate off-site sources and remaining down-gradient impacts Cosl Reduction 6.2.1 Reduce analytical QA/QC 6.2.2 Consider converting cell 3 to an additional infiltration basin Progress Toward Cleanup Coals 6.4.1 Develop an exit strategy Deferred to State or PRP Declined Deferred to State or PRP Alternative implemented Deferred to State or PRP State has taken over monitoring as of November 2011. State has assumed operation of remedy as of November 2011. OSWER 9283.1-38 Appendix July 2012 Page 16 of 37 ------- RSE Recommendations and Progress Toward Implementation Region 5 Site Name: Reilly Tar & Chemical Corp. (Indianapolis, IN) EPA ID#: IND000807107 RSE Report: EPA 542-R-04-035 (February 2004) Recommendation Status Progress since the previous progress report Remedy l\ITcc(i\eness 6.1.1 Install piezometers and monitoring wells to allow for improved evaluation of plume capture 6.1.2 Perform improved plume capture evaluation (Including numerical model) 6.1.3 Consider the need for a modified extraction system Cost Reduction 6.2.1 Consider using extracted water for Declined process and cooling uses Technical lmprn\cmcnl 6.3.1 Minor suggestion for improved O&M Implemented reporting Progress Toward Cleanup Coals 6.4.1 Develop an exit strategy (consider In progress See update for recommendation 6.1.2. Updated modeling in 2012 will facilitate an exit strategy, alternate approach) Implemented In progress PRPs have submitted outline of modeling effort—EPA to provide comments early 2012 for implementation. Declined OSWER 9283.1-38 Appendix July 2012 Page 17 of 37 ------- RSE Recommendations and Progress Toward Implementation Region 5 Site Name: Peerless Plating (Muskegon, MI) Recommendation Status EPA ID#: MID006031348 RSE Report: EPA 542-R-06-011 (February 2006) Progress since the previous progress report Remedy l\ITcc(i\eness 6.1.1 Evaluation of ground water capture Implemented 6.1.2 Modifications to the monitoring Implemented program Cosl Reduction 6.2.1 Eliminate several ground water Implemented treatment processes 6.2.2 Modifications to the monitoring Implemented program 6.2.3 Revise reporting requirements Declined 6.2.4 Review level of operator support Implemented Technical lmpm\cmcnl 6.3.1 Install dust collection system over Declined FeS04 hopper 6.3.2 Install enclosure around air Declined compressor to reduce noise 6.3.3 Initiate a formal O&M program Implemented 6.3.4 Advertise availability of used Implemented equipment on US ACE/EPA web page Progress Toward Cleanup Coals 6.4.1 Assess source area treatment Declined alternatives 6.4.2 Permeable barrier Declined A pumping wells was moved and pumping rates were adjusted to help address capture issues. Additional monitoring wells were installed to monitor capture. A monitoring well to address background concentrations was installed. The State installed 8 new monitoring wells to establish plume limits. The agency continues to monitor these new wells to determine if additional information will be required in the future. Low Flow sampling is used exclusively. The by pass system continues to operate and there is no update at this time. The formal O&M plan has been developed and will continue to be updated as required until the site activities are taken over by the State of MI. The contractor is currently solicity bids to dismantel and remove excess equipment from the Site. OSWER 9283.1-38 Appendix July 2012 Page 18 of 37 ------- RSE Recommendations and Progress Toward Implementation Region 5 Site Name: Baytown Township Ground Water Plume (Lake Elmo, MN) Recommendation Status EPA ID#: MND982425209 RSE Report: EPA-540-R-011-006 (June 2011) Progress since the previous progress report Remedy l\ITcc(i\eness 6.1.1 Implement ISCO in Source Area Under Consideration 6.1.2 Phased Implementation of ISCO, Under Tracer Test Consideration 6.1.3 Consideration of In Situ Biological Under Treatment Consideration 6.1.4 Potential Life Cycle Cost Savings Under Offered by Source Area Treatment Consideration 6.1.5 Additional Source Area Assessment In Progress 6.1.6 Performance-Based Contracting for Source Area Treatment 6.1.7 More Rigorous Evaluation of Hydraulic Barrier Capture Influence 6.1.8 Improvements to the Monitoring Program Cosl Reduction 6.2.1 Reduce Blower Airflow Rate 6.2.2 Adjustments to GAC Management Program 6.2.3 Eventually Replace Class I, Division I Motors 6.2.4 Optimization of the Groundwater Monitoring Program Technical lmpro\cmcnl 6.3.1 Use of More Rigorous MNA Modeling 6.3.2 Continue Evaluation of Groundwater Infiltration System Plugging Under Consideration In Progress In Progress Under Consideration In Progress Under Consideration Under Consideration Implemented The use of ISCO in the source area will be considered as part of an updated FS in early 2012. A work plan for the FS is currently under development. Aspects of this recommendation are in the process of being implemented, including the tracer test. The use of in-situ bioremediation will be considered as part of the updated FS (see 6.1.1). This section of the RSE report did not contain a specific recommendation, rather it supports other items in 6.1. A work plan for implementing this recommendation is in preparation (see 6.1.1). This item will be considered in the future if source treatment is planned. MPCA contractor is evaluating capture as part of Annual Report. Region 5 technical staff may be able to assist with this. MPCA is assessing trends, but will not implement a MAROS analysis. Contractor to MPCA is evaluating. One GAC unit has been replaced, and process is in place to require that new units exclude treatment of water delivered by exterior hose bibs. Applicable only in the future when equipment needs replacement. Implemented Passive diffusion bags have been used in some monitoring wells, but not all. MPCA is planning additional MNA monitoring later in 2012. Injection of C02 continues and downhole camera work assesses need for well rehabilitation by jetting. OSWER 9283.1-38 Appendix July 2012 Page 19 of 37 ------- RSE Recommendations and Progress Toward Implementation Region 5 Site Name: Baytown Township Ground Water Plume (Lake Elmo, MN) Recommendation Status EPA ID#: MND982425209 RSE Report: EPA-540-R-011-006 (June 2011) Progress since the previous progress report 6.3.3 Periodic Inspection of Electrical Implemented System and Controls 6.3.4 Optimize Process Flow Configuration Declined for Air Stripping System 6.3.6 Preparation of an Annual Report Implemented 6.3.7 Improvement of Data Management In Progress Progress Toward Cleanup Coals 6.4.0 Implement ISCO, MNA Modeling, Under Capture Zone Analysis (see 6.1.1 above) Consideration MPCA contractor has conducted inspection and has incorporated this into standard site inspection process. MPCA will not implement as it would require adding pumps. Modifications to the annual reports being prepared starting in 2011. MPCA has made some improvements, including use of the EQUIS database. EPA Region 5 offered assistance for this. See 6.1.1 above OSWER 9283.1-38 Appendix July 2012 Page 20 of 37 ------- RSE Recommendations and Progress Toward Implementation Region 5 Site Name: Moss-American (Milwaukee, WI) Recommendation Status EPA ID#: WID03 9052626 RSE Report: EPA-540-R-11-018 (March 2011) Progress since the previous progress report Remedy l\ITec(i\eness 5.1.1 Monitoring program modifications 5.1.2 Additional NAPL investigation Cosl Reduction 5.2.1 NAPL-impacted soil excavation and enhanced dissolved-phase treatment 5.2.2 Limited NAPL-impacted soil removal and installation of additional treatment gate 5.2.3 Ground Water Flow Modification to Enhance Treatment of Existing Funnel and Gate System Planned Planned Under Consideration Under Consideration Declined The State plans on getting a contractor on board later this year to develop and implement a work plan for further characterization, as recommended in 5.1.1 and 5.1.2. In addition, the contractor will be tasked with suggesting other alternatives to meet the objectives of the project. See notes above. Pending outcome of 5.1.1 and 5.1.2. Pending outcome of 5.1.1 and 5.1.2. The site team has deemed this item ineffective and not a viable path forward. OSWER 9283.1-38 Appendix July 2012 Page 21 of 37 ------- RSE Recommendations and Progress Toward Implementation Region 5 Site Name: Wash King Laundry (Pleasant Plains Township, MI) Recommendation Status EPA ID#: MID980701247 RSE Report: EPA-540-R-11-019 (February 2011) Progress since the previous progress report Remedy l\ITec(i\eness 6.1.1 Sample P&T Discharge and Residential Wells for Lead 6.1.2 Complete Institutional Controls 6.1.3 JetEW-5 and Measure/Track Extraction Well Specific Capacity 6.1.4 Evaluate and Manage Soil Vapors Cosl Reduction 6.2.1 Discontinuing Pumping from EW-4 6.2.2 Reduce Metals Analysis 6.2.3 Reconfigure Air Strippers and Possibly Resize Air Stripper Blowers 6.2.4 Modify Groundwater Monitoring Program 6.2.5 Prepare an Annual Report Implemented The site team actually started implementing this the year before the RSE. In Progress The site team has determined that institutional controls are not needed at four of the eight properties. EPA and the State are discussing institutional controls for the other four properties. In the interim, the Health Department, which has the authority to permit supply wells, will not allow wells in the area. Implemented The site team jetted the well, but jetting did not result in sufficient improvements. The well needed to be replaced. The site team replaced the well with a well (EW-8) in a new location upgradient. Alternative The site team evaluated the potential for vapor intrusion at the restaurant building and Implemented concluded that given the condition of the building and no occupancy of the building, vapor intrusion was not a concern. The site team, however, decided to keep operating the SVE system occasionally to reduce vapors that accumulate in the unsaturated zone. Implemented The site team implemented this recommendation. Alternative The site team did not reduce the types of analyses, but did reduce some of the locations where Implemented metals would be analyzed. In Progress Given the flow from the new extraction wells and the capacities of the air strippers, both air strippers are needed. At the suggestion of the RSE team, the site team will revisit discussions with the vendors to see if the blower sizes can be reduced from 25 HP or variable frequency drives can be installed to reduce air flow and electricity usage and still provide adequate treatment. Implemented The site team adopted most of the RSE team's suggestions for modifying the groundwater monitoring program. The site team agrees that savings is likely on the order of $30,000 per year. Declined An additional annual report will not be implemented at this time given the existing quarterly reporting and other recent reporting including two Five-Year Reviews, a Long-Term Monitoring Optimization Report, and the RSE report. OSWER 9283.1-38 Appendix July 2012 Page 22 of 37 ------- RSE Recommendations and Progress Toward Implementation Region 5 Site Name: Wash King Laundry (Pleasant Plains Township, MI) Recommendation Status EPA ID#: MID980701247 RSE Report: EPA-540-R-11-019 (February 2011) Progress since the previous progress report Progress Toward Cleanup Coals 6.4.1 Investigate Sources in Lagoon Area In Progress and Piping to Former Lagoons 6.4.2 Develop an Exit Strategy In Progress Crccn Remediation 6.5.1 Use Dedicated Tubing Declined 6.5.2 Considerations for Renewable Energy Declined at the Site The site team has installed a shallow, intermediate, and deep well in the general vicinity and has identified contamination. EPA Region 5 and the State continue to discuss the path forward for the site. The site team has installed a shallow, intermediate, and deep well in the general vicinity and has identified contamination. EPA Region 5 and the State continue to discuss the path forward for the site. The potential savings (cost and environmental) do not outweigh the field complications associated with implementing this recommendation. The site team has not considered renewable energy for the site. The RSE team suggests understanding the future electricity usage (after air stripper optimization) prior to considering renewable energy. OSWER 9283.1-38 Appendix July 2012 Page 23 of 37 ------- RSE Recommendations and Progress Toward Implementation Region 7 Site Name: 57th and North Broadway (Wichita, KS) EPA ID#: KSD981710247 RSE Report: EPA-540-R-06-067 (June 2006) Recommendation Status Progress since the previous progress report Remedy l\ITcc(i\eness 6.1.1 Perform additional source area Implemented characterization 6.1.2 Consider contingent wellhead treatment at the public water supply well 6.1.3 Consider change to P&T after source characterization, in 53rd Street area 6.1.4 Evaluate whether extent of SVE system is adequate 6.1.5 Consider using air sparging with existing SVE 6.1.6 Continue monitoring of sentinel wells in Bel Aire well field 6.1.7 Evaluate potential for vapor intrusion Implemented Cosl Reduction 6.2.1 Consider immediately taking eastern Implemented 53 rd Street DDC wells out of operation 6.2.2 Consider better tracking of routine and Implemented non-routine site costs Technical lmpro\cmcnl 6.3.1 Prepare and distribute annual Implemented monitoring reports 6.3.2 Improve site maps Implemented 6.3.3 Report detection levels for 'non-detect' Implemented results Implemented In progress The status is about the same, we've conducted new investigation in December 2011 and obtained additional data for the installation of the extraction well. We have had some issues with the state which delayed this work. Things are progressing better now and hopefuly move forward after we get these latest results. Implemented Declined Implemented OSWER 9283.1-38 Appendix July 2012 Page 24 of 37 ------- RSE Recommendations and Progress Toward Implementation Region 7 Site Name: 57th and North Broadway (Wichita, KS) Recommendation Status EPA ID#: KSD981710247 RSE Report: EPA-540-R-06-067 (June 2006) Progress since the previous progress report Progress Toward Cleanup Coals 6.4.1 Clarify and document date for turnover In progress to State for O&M 6.4.2 Develop consensus on terminating Implemented SVE at Wilko The status is still the same, we have conducted additional investigations in December 2011 and will modify the current remedy by installing an extraction well and some soil removal. After the remedy is operational and effective, the site will be turned over to the state. OSWER 9283.1-38 Appendix July 2012 Page 25 of 37 ------- RSE Recommendations and Progress Toward Implementation Region 7 Site Name: 10th Street Site (Columbus, NE) Recommendation Status EPA ID#: NED981713837 RSE Report: EPA 540-R-10-012 (February 2010) Progress since the previous progress report Remedy l\ITec(i\eness 6.1.1 Evaluate the Need for Further Implemented Evaluation of Potential for Vapor Intrusion Near OHM Facility 6.1.2 Discontinue Pumping at EW-04 and Shift Pumping West to EW-03 6.1.3 Address Calibration Issues with the Flow Model Under Consideration In progress 6.1.4 Address Potential Plume Migration to Implemented the Southeast (Delineation and ICs) and Associated Potential Actions Cosl Reduction 6.2.1 Discontinue ISCO After Contract is Implemented Completed 6.2.2 Continue to Use PDBs Without Implemented Extensive Comparisons 6.2.3 Reductions in Monitoring/Reporting Implemented Two new rounds of vapor intrusion sampling were conducted in 2010, and four more rounds were conducted in 2011. Indoor air samples have been below screening levels, but sub slab samples had exceedances. A soil vapor investigation was conducted in and around the source areas. The site team is moving forward with vapor intrusion mitigation systems at 17 properties in early 2012. Pumping continues at EW-04 and will be reevaluated after the flow model is updated. The capacity of EW-03 has been increased to the maximum extent possible. The modeling was delayed due to delays in obtaining access for the installation of piezometers. The modeling should be completed in the next month or two allowing for consideration of the discontinuing pumping from EW-04. The Region is planning to update the flow model after conducting pump tests at EW-03 and EW-04. The modeling was delayed due to delays in obtaining access for the installation of piezometers. The modeling should be completed in the next month or two. Twelve new wells have been installed for this purpose. The new monitoring wells have non- detect results and effectively delineate the plume. ISCO injections have been discontinued; the last round was in 2009. The site team continues to use PDBs where they correlated well with low-flow sampling results and do not use PDBs where they did not correlate well with low-flow sampling. No further comparison studies are being conducted. Reductions in monitoring/reporting were included in the contract modification, including cutting back to semi-annual sampling and sampling at fewer wells. In 2010, monitoring and reporting cost an estimated $247,465. Actual monitoring and reporting costs in 2011 were lower than expected and actual monitoring and reporting in 2012 are $124,000 (suggesting a cost reduction of 50% and a cost savings of $124,000 per year). OSWER 9283.1-38 Appendix July 2012 Page 26 of 37 ------- RSE Recommendations and Progress Toward Implementation Region 7 Site Name: 10th Street Site (Columbus, NE) Recommendation Status EPA ID#: NED981713837 RSE Report: EPA 540-R-10-012 (February 2010) Progress since the previous progress report 6.2.4 Project Management and Technical Implemented Support Moving Forward Technical lmprn\cmcnl 6.3.1 Measure and Track Specific Capacity Implemented of Wells 6.3.2 Consider VFDs for Extraction Well Declined Pumps Progress Toward Cleanup Coals 6.4.1 Consider Alternate Actions at OHM Implemented Facility 6.4.1 Consider Alternate Actions at OHM Implemented Facility The RSE team's recommendations have been implemented, which has led to significant cost reduction (approximately $190,000). Most cost savings are associated with shifting focus to evaluate other remedial options rather than optimize the AS/SVE system. Earlier costs were incurred for the ART well and groundwater recirculation pilot studies, which were evaluated as potential enhancements to the AS/SVE system. Project management and reporting costs are expected to stay steady at the reduced level in 2011 and 2012. Specific capacity of wells was calculated for the 2009 Annual Report and will be calculated for the 2010 Annual Report. There will not be a significant increase in effort or cost associated with these calculations. VFDs had been looked at during design, but were ruled out because they would not lead to a significant cost impact. The site team is focusing on pinpointing the source, determining the best way to treat source area contamination, and reducing the amount of O&M and pumping time needed. Soil investigations at the OHM facility and two other dry cleaners to the south indicate that higher levels of contamination exist below the other two buildings. The site team prepared a Focused Feasibility Study, and a ROD Amendment and a Remedial Design start are planned by the end of the 3rd quarter of 2012. OSWER 9283.1-38 Appendix July 2012 Page 27 of 37 ------- RSE Recommendations and Progress Toward Implementation Region 8 Site Name: Central City/Clear Creek, Argo Tunnel (Idaho Springs, CO) Recommendation Status EPA ID#: COD980717557 RSE Report: EPA-542-R-07-019 (September 2007) Progress since the previous progress report Remedy l\ITcc(i\eness 6.1.1 Evaluate and decide on need for blowout prevention 6.1.2 Evaluate importance of complete collection and treatment of the Virginia Canyon ground water 6.1.3 Evaluate indoor air quality for metals and confirm medical monitoring for plan workers Cost Reduction 6.2.1 Install new filter presses 6.2.2 Realize savings from improved operations 6.2.3 Improve metals treatment by solids recycling Technical lmprn\cmcnl 0.3.1 Reduce discharge of recycled solids and high pH water to equalization basins 6.3.2 Improve lime feed system 6.3.3 Provide additional compressed air capacity 6.3.4 Reduce solids wasting flow rate In progress An entry into the Argo Tunnel occured on 5/3/2011. The entry team only made it in about 125 feet due to sediment buildup. A conceptual design was prepared and submitted to the State and EPA in November 2011. It estimated the cost of construction for a bulkhead at $413,000. The State is preparing a Request for Qualifications to hire a design engineer. Implemented No further comment. Implemented In progress Alternative Implemented In progress Alternative Implemented Under Consideration Alternative Implemented The State has amended the contract with the engineer to design the conversion of the process to a HDS system. The additional design cost is $363,800. The design is approximately 60% complete. The estimated construction cost has increased to $2,550,000. Once design is complete, the State will request funds to construct the process modifications. No further comment. See update in 6.2.1. Iniplenieiiled No further comment. No further comment. The design for conversion to a HDS system includes installation of a blower to provide aeration to the process. If the conversion is implemented, additional compressed air capacity will likely not be required. OSWER 9283.1-38 Appendix July 2012 Page 28 of 37 ------- RSE Recommendations and Progress Toward Implementation Region 8 Site Name: Central City/Clear Creek, Argo Tunnel (Idaho Springs, EPA ID#: COD980717557 C°) RSE Report: EPA-542-R-07-019 (September 2007) Recommendation Status Progress since the previous progress report 6.3.5 Consider construction of an on-site In progress See update in 6.2.1 solids disposal repository as a contingency to disposal at a landfill 6.3.6 Additional improvements In progress The additional permanent lime storage is still on hold because they have lower funding priority than the other items. OSWER 9283.1-38 Appendix July 2012 Page 29 of 37 ------- RSE Recommendations and Progress Toward Implementation Region 9 Site Name: Modesto Ground Water Contamination (Modesto, CA) Recommendation Status EPA ID#: CAD981997752 RSE Report: EPA-542-R-02-008o (December 2001) Progress since the previous progress report Remedy l\ITcc(i\eness 6.1.1 Monitor subsurface performance of Implemented SVE system 6.1.2 Assign responsibility for evaluating Implemented monitoring and performance data 6.1.3 Analyze capture zone Implemented 6.1.4 Delineate plume (if necessary) Implemented Cosl Reduction 6.2.1 Consider alternate discharge locations Declined - Discharge to storm sewer - Reinject to subsurface 6.2.2 Simplify system (remove equalization Implemented tank, simplify filtration system, and remove transfer pump) 6.2.3 Regularly evaluate need for ion Implemented exchange units Technical lmpro\cmcnl 6.3.1 Relocate vacuum breaker Implemented 6.3.2 Install valving for backwashing carbon Implemented and ion exchange units 6.3.3 Monitor extraction well performance Implemented 6.3.4 Modify SVE system to address high Declined operating temperatures 6.3.5 Regularly evaluate need for vapor Declined phase carbon 6.3.6 Properly convert PID readings to PCE Implemented concentrations 6.3.7 Improve accuracy of SVE flow Implemented 6.3.8 Adjust membrane around Baker tank Alternative Implemented OSWER 9283.1-38 Appendix July 2012 Page 30 of 37 ------- RSE Recommendations and Progress Toward Implementation Region 9 Site Name: Modesto Ground Water Contamination (Modesto, CA) Recommendation Status EPA ID#: CAD981997752 RSE Report: EPA-542-R-02-008o (December 2001) Progress since the previous progress report 6.3.9 Improve drainage to secondary sump 6.3.10 Add fans to the control panel 6.3.11 Relocate vapor phase carbon for the groundwater treatment system 6.3.12 Add phone line for data acquisition Progress Toward Cleanup Coals 6.4.1 Initiate screening of final remedy 6.4.2 Measure DO and ORP in monitoring wells Implemented Implemented Implemented Implemented In progress Implemented Discovery of possible new source area requires additional investigation and will delay the FS and selection of final remedy. OSWER 9283.1-38 Appendix July 2012 Page 31 of 37 ------- RSE Recommendations and Progress Toward Implementation Region 9 Site Name: Pemaco Maywood (Los Angeles County, CA) Recommendation Status EPA ID#: CAD980737092 RSE Report: EPA-540-R-11-005 (July 2011) Progress since the previous progress report Remedy l\ITec(i\eness 6.1. IB Add monitoring well in D-zone 6.1.1A Potentially add pumping or monitoring wells in C-zone. 6.1.2 Collect vapor sample from trunk line VE-1 to assess vapor intrusion risk ( osi Reduction 6.2.1 Reduce monitoring well sampling from 374 to 192 or fewer samples per year. 6.2.2 Reduce process sampling of water from about 120 to fewer than 52 per year and vapor from 168 to fewer than 40 per year Planned The site team is planning to install a new D-zone monitoring well by April 2012. The cost for the new well is expected to be $37,200 which is $17,200 more than the RSE estimate. Implemented The site team converted a C-zone monitoring well into an extraction well to increase pumping. Implemented Implemented Implemented 6.2.3 Reduce vapor extraction points (SVE Implemented and DPE) from about 55 to about 25. Rebound test well groups. Reduce groundwater extraction points from about 56 to about 24 (including 3 DPE points). Reduce blower use. Simplify system. The site team sampled all 7 of the wells along the VE-1 line (as well as the 48 vapor extraction wells). The sampling indicated that vapor intrusion is not an issue in this location. The sampling cost about $5,000 which is within the $15,000 RSE estimate that included contingent sampling. The site team reports that sampling has been reduced from 432 wells costing $442,800 per year to 206 samples per year (73 wells sampled semiannually and 15 wells sampled quarterly). The site team projects a savings of about $230,000 per year associated with this reduction; this is more than the $ 145,000 or greater savings estimated in the RSE because the original number of samples had been underestimated in the RSE. On the call, the site team reported that they are currently evaluating the recommended reduction to eliminate sampling influent headers and intermediate process locations that are not useful for system operation decisions. Since the call, the site team further evaluated reducing process sampling and has reportedly decided to eliminate all sampling of influent headers and intermediate process locations for both vapor and groundwater, as per RSE recommendations. As of this date, only combined influent and effluent samples will be collected monthly at a potential savings of about $54,000 per year in labor and ODC costs. The site team has reduced operating vapor extraction wells to 16 and reduced groundwater pumping to 29 wells (including 6 DPE wells) at a 17 gallon per minute total How rate. The system has been operated with one blower for an estimated $40,000 annual power cost savings. The site team will consider performing rebound sampling only on well groups, as recommended in the RSE, at an expected savings of $28,000. The site team already considered using an existing "polishing blower" once DPE wells are no longer in use, but determined it would not produce the necessary vacuum. The design engineer will consider using a smaller blower (37 hp) to replace the currently operating (75 hp) liquid ring blower. He will also consider how to simplify the control system and enhance the efficiency of the bag filtration system to reduce labor costs. OSWER 9283.1-38 Appendix July 2012 Page 32 of 37 ------- RSE Recommendations and Progress Toward Implementation Region 9 Site Name: Pemaco Maywood (Los Angeles County, CA) Recommendation Status EPA ID#: CAD980737092 RSE Report: EPA-540-R-11-005 (July 2011) Progress since the previous progress report 6.2.4 Reduce operator labor to one FTE or In progress less. Eliminate manned off-hour security. 6.2.5 Reduce project management costs. In progress Technical lmprn\cmcnl 6.3.1 Improve reporting Progress Toward Cleanup Coals Implemented 6.4.1 Establish SSRLs for determination of Implemented SVE well closures and resample at baseline locations for remediation confirmation Crccn Kemedialion 6.5.0 Use local staff for groundwater monitoring Declined The site team reports that they have reduced plant personnel from three full-time to two full- time and one part-time staff at a savings of about $36,000 per year based on the $820,000 per year costs reported during the RSE and the $392,000 for six months of O&M reported for the follow-up call. Further reductions have not been made due to the high volume of maintenance, the frequency of process data collection which has not been reduced, and site policy of having 2-person crews perform O&M. Off-hour security also remains because of concerns regarding vandalism and other crime in the area. The site team is currently evaluating other methods for achieving adequate security without manned personnel. In addition, the team is looking at ways of further reducing operator labor, as suggested by the RSE. The RSE recommendation was to reduce project management (including technical support and reporting) costs in line with the simplified system and reduced monitoring from about $400,000 per year to achieve costs of $150,000 per year or less.The site team notes that ongoing costs were reduced in the second half of 2011 and optimization efforts continue. Project management costs were about $152,000 for the second half of 2011 or about $304,000 per year. The site team noted that the reporting improvements began with 2011 reports and represent a $60,000 portion of the project management costs. The site team is currently using a total VOC level of about 100 ppbv to decide vapor extraction well status and agreed that a more formal standard would be useful for further decisions. The site team resampled the baseline locations and found only three locations above action levels. The site team reported that staff from San Diego (rather than northern California as reported in the RSE) are conducting the monthly process sampling. OSWER 9283.1-38 Appendix July 2012 Page 33 of 37 ------- RSE Recommendations and Progress Toward Implementation Region 10 Site Name: Northwest Pipe & Casing (Clackamas, OR) Recommendation Status EPA ID#: ORD980988307 RSE Report: EPA 542-R-07-018 (September 2007) Progress since the previous progress report Remedy l\ITcc(i\eness 6.1.1 Improve delineation of Plume 1 to the south 6.1.2 Finalize institutional controls (ICs) on Parcel A 6.1.3 Continue/conclude efforts to evaluate potential for vapor intrusion on Parcel A Cosl Reduction (> 2 I I M111111i;ilc iipeialKin nf (i( \Vs Technical lmpm\cmcnl (> ' I ke\ ise sequencnm lor ailleclnm Mie- u ide ualer le\ el dala Progress Toward Cleanup Coals 6.4.1 Clarify and document goals for active remediation 6.4.2 Implement in-situ bioremediation to reduce highest VOC concentrations, in conjunction with natural remediation Implemented Implemented Implemented Implemented Implemented In progress In progress ICs were finalized for the Northwest Development Company portion on Parcel A in October 2010. There are no outstanding issues concerning the Vapor Intrusion issue at the ODOT property. Vapor Intursion Risk Assessment found risk to within the acceptable range. The site team continues to monitor removal action, will be completing modeling to help determine how to proceed. Modeling should be completed by 4th quarter FY12. FS will be completed in FY 2012, expect ROD amendment by end of 2013, based on the removal action and the addition of the soil ammendment it is unlikely that additional action will occur at the site except for monitoring. OSWER 9283.1-38 Appendix July 2012 Page 34 of 37 ------- RSE Recommendations and Progress Toward Implementation Region 10 Site Name: Boomsnub/Airco (Hazel Dell, WA) Recommendation Status EPA ID#: WAD009624453 RSE Report: EPA-542-R-02-016 (September 2002) Progress since the previous progress report Remedy l\ITcc(i\eness 6.1.1 Conduct a hydro-geological analysis Implemented 6.1.2 Evaluate potential management Implemented options for extraction and discharge 6.1.3 Considerations for potential extraction Implemented and discharge options 6.1.4 Consider other discharge options Implemented Cosl Reduction 6.2.1 Eliminate ion exchange effluent tank Implemented and pump 6.2.2 Improve electric work for air stripper Implemented Technical lmprn\cmcnl 6.3.1 Consider limitations of passive Implemented technologies 6.3.2 Develop an exit strategy In progress We are addressing an orphan in-coming TCE plume that does not appear to be related to the sources of the Superfund site. This is delaying the finalization of an exit strategy. OSWER 9283.1-38 Appendix July 2012 Page 35 of 37 ------- RSE Recommendations and Progress Toward Implementation Region 10 Site Name: Wyckoff/Eagle Harbor (Bainbridge Island, WA) Recommendation Status EPA ID#: WAD009248295 RSE Report: EPA-542-R-05-013 (March 2005) Progress since the previous progress report Remedy l\ITcc(i\eness 6.1.1 Select a final remedy Cost Reduction 6.2.1 Simplify existing treatment plant 6.2.2 Install upgradient sheet pile Implemented Implemented Declined 6.2.3 Remove steam injection/ extraction Planned system and apply cap 6.2.4 Conduct water budget analysis Implemented 6.2.5 Upgrade extraction system Implemented 6.2.6 Replace the existing treatment plant Implemented 6.2.7 Augment monitoring in lower aquifer Implemented Technical lmpm\cmcnl 6.3.0 Other related items Planned - Improve monitoring approach - Monitor seeps on beach - Consider new extraction points Groundwater extraction system upgrades were completed in Fall 2011. Upgrades include new extraction well pumps and installation of groundwater level pressure transducers. Shakedown process of GWTP will be completed in Winter 2012. Operation and maintenance of GWTP will be turned over to the State of Washingon in April 2012, for at least a period of years while EPA works on feasiblity analysis of completing the permanent remedy. Completion of new GWTP made old treatment plant obsolete. Old treatment plant is being demolished as of Winter 2011. Fieldwork has indicated that aquitard is not present in the SE corner of the site. Groundwater evaluations has shown that a sheet pile wall is not necessary to ensure that containment is maintained in this portion of the site. Cap design and construction is still on hold pending completion of feasiblity analysis of implementing a permanent source removal remedy. Demolition of old groundwater treatment plant completed in July 2011. Demolition of remaining existing infrastructure (steam injection well field) is also on hold. Replacement of existing product and water pumps and installation of pressure transducers in monitoring wells completed in Fall 2011. Construction of new GWTP was completed in May 2009. Old treatment plant is being demolished as of winter 2011. Further seep monitoring along East Beach and North Shoal areas of site is currently being planned for Spring 2012. OSWER 9283.1-38 Appendix July 2012 Page 36 of 37 ------- RSE Recommendations and Progress Toward Implementation Region 10 Site Name: Colbert Landfill (Spokane County, WA) Recommendation Status EPA ID#: WAD980514541 RSE Report: EPA-540-R-11-020 (October 2010) Progress since the previous progress report Remedy l\ITcc(i\eness 6.1.1 Add Monitoring Well West of CP-W3 Planned 6.1.2 Include 1,4-Dioxane in Future Planned Residential Sampling (At Some Frequency) 6.1.3 Tighten Institution Controls Regarding Under Groundwater Use and Document Approach Consideration Regarding 1,4-Dioxane Detections Technical lmprn\cmcnl 6.3.1 Modifications to Water Level Maps Implemented 6.3.2 Other Suggested Modifications to Implemented Quarterly Reports Progress Toward Cleanup Coals 6.4.1 Consider Shut-Down Test of In Progress Remaining Active Extraction Wells The County plans to implement this recommendation, and will include this new monitoring well in the work plan to be submitted for the P&T shut-down test. The work plan is expected in the spring of 2012, with well installation potentially in summer of 2012. The County plans to include 1,4-Dioxane in future residential sampling using the same methodology employed for residential sampling of other site COCs. The RPM indicated that he plans to discuss the adequacy of the existing institutional controls with an attorney within approximately one month, and hopes to have that legal opinion within the next three months. To date there is no cost impact associated with this recommendation, and the extent to which any costs are incurred will likely depend on the information provided by the EPA attorney. The County indicated that the number of locations is too numerous to post, but is now including all data collected during the reporting period. The County indicated there is no need to highlight water levels from extraction wells since those are not used in the contouring. There should be no cost impact associated with the implementation of this recommendation. The recommendation that non-detect values be reported as below a specific detection limit such as "<5" rather than "ND" has been implemented, and the recommendation that quarterly reports include an executive summary to highlight significant observations or results from that quarter is planned for future reports. There should be no cost impact associated with the implementation of this recommendation. The County has accepted this recommendation and plans to submit a draft work plan for the shut-down test in spring of 2012 to be reviewed by stakeholders, with potential implementation in summer of 2012. OSWER 9283.1-38 Appendix July 2012 Page 37 of 37 ------- |