MUNICIPAL WASTE COMBUSTORS --
BACKGROUND INFORMATION FOR
PROPOSED STANDARDS: COST PROCEDURES
FINAL REPORT
Prepared for:
Michael G. Johnston
U.S. Environmental Protection Agency
Industrial Studies Branch (MD-13)
Research Triangle Park, North Carolina 27711
Prepared by:
Radian Corporation
3200 E. Chapel Hill Rd./Nelson Hwy.
Post Office Box 13000
AUGUST 14, 1989

-------
DISCLAIMER
This report has been reviewed by the Emission Standards Division
of the Office of Air Quality Planning and Standards, EPA, and
approved for publication. Mention of trade names or commercial
products is not intended to constitute endorsement or
recommendation for use. Copies of this report are available
through the Library Services Office (MD-35), U.S. Environmental
Protection Agency, Research Triangle Park NC 27711, or from
National Technical Information Services, 5285 Port Royal Road,
Springfield VA 22161.
/

-------
TABLE OF CONTENTS
Secti on	Page
1.0 INTRODUCTION		1-1
2.0	PROCEDURES FOR NEW PLANTS		2.1-1
2.1	COMBUSTORS AND BALANCE OF PLANT		2.1-1
2.1.1	Modular Units		2.1-2
2.1.1.1	Overview of Technology		2.1-2
2.1.1.2	Capital Cost Procedures		2.1-2
2.1.1.3	Operating Cost Procedures		2.1-4
2.1.2	Mass Burn Units		2.1-5
2.1.2.1	Overview of Technology		2.1-5
2.1.2.2	Capital Cost Procedures		2.1-6
2.1.2.3	Operating Cost Procedures		2.1-6
2.1.3	RDF Units		2.1-9
2.1.3.1	Overview of Technology		2.1-9
2.1.3.2	Capital Cost Procedures		2.1-11
2.1.3.3	Operating Cost Procedures		2.1-11
2.1.4	FBC Units		2.1-12
2.1.4.1	Overview of Technology		2.1-13
2.1.4.2	Capital Cost Procedures		2.1-13
2.1.4.3	Operating Cost Procedures		2.1-13
References		2.1-20
2.2	ELECTROSTATIC PRECIPITATORS			2.2-1
2.2.1	Overview of Technology		2.2-1
2.2.2	Capital Cost Procedures		2.2-1
2.2.2.1	Direct Costs			2.2-1
2.2.2.2	Indirect Costs and Other Costs		2.2-8
2.2.3	Operating Cost Procedures		2.2-12
References		2.2-14
iii

-------
TABLE OF CONTENTS
Secti on	Page
2.3	DRV SORBENT INJECTION		2.3-1
2.3.1	Overview of Technology....-		-		2.3-1
2.3.2	Capital Cost Procedures		2.3-2
2.3.3	Operating Cost Procedures		2.3-6
References		2.3-9
2.4	SPRAY DRYING WITH EFFICIENT PARTICULATE CONTROL		2.4-1
2.4.1	Overview of Technology		2.4-1
2.4.2	Capital Cost Procedures			2.4-1
2.4.2.1	Direct Costs		2.4-2
2.4.2.2	Indirect and Other Costs		2.4-5
2.4.3	Operating Cost Procedures		2.4-5
References		2.4-10
2.5	COMPLIANCE MONITORING		2.5-1
2.5.1	Overview of Technology		2.5-1
2.5.1.1	Continuous Opacity Monitoring		2.5-1
2.5.1.2	Continuous S02 Monitoring		2.5-1
2.5.1.3	Continuous HCt Monitoring		2.5-2
2.5.1.4	Diluent (O^/CO^ Monitoring)		2.5-3
2.5.2	Compliance Monitoring Costs		2.5-3
References		2.5-5
3.0	PROCEDURES FOR EXISTING PLANTS		3.1-1
3.1	OPERATION OF THE EXISTING COMBUSTORS		3.1-1
3.2	COMBUSTOR MODIFICATIONS		3.2-1
3.2.1	Introduction		3.2-1
3.2.2	Capital Cost Procedures		3.2-1
3.2.2.1	Stoker Rehabilitation		3.2-3
3.2.2.2	Refractory-Wall Furnace Reconfiguration		3.2-4
3.2.2.3	Fuel Feeding Modifications		3.2-4
3.2.2.4	Underfire Air Modifications		3.2-5
3.2.2.5	Overfire Air Modifications		3.2-7
3.2.2.5 Combustion Controls and Monitors		3.2-9
3.2.2.7 Auxiliary Fuel Burner Installation		3.2-10
iv

-------
TABLE OF CONTENTS
Section	Page
3.2.2.8	Carbon Monoxide Profiling		3.2-11
3.2.2.9	Economizer for Flue Gas Temperature Control		3.2-11
3.2.3 Operating Cost Procedures		3.2-12
References		3.2-15
3.3	HUMIDIFICATION		3.3-1
3.3.1	Overview of Technology		3.3-1
3.3.2	Capital Cost Procedures		3.3-2
3.3.3	Operating Cost Procedures		3.3-3
References		3.3-6
3.4	PARTICULATE MATTER CONTROL RETROFIT		3.4-1
3.4.1	Installation of a New ESP		3.4-1
3.4.1.1	Capital Cost Procedures		3.4-1
3.4.1.2	Operating Cost Procedures		3.4-1
3.4.2	Increase in ESP Plate Area		3.4-2
3.4.2.1	Capital Cost Procedures		3.4-2
3.4.2.2	Operating Cost Procedures		3.4-2
3.4.3	ESP Rebuild		3.4-3
3.4.3.1	Capital Cost Procedures		3.4-3
3.4.3.2	Operating Cost Procedures		3.4-3
References		3.4-4
3.5	DRV SORBENT INJECTION RETROFIT		3.5-1
3.5.1	Overview of Technology		3.5-1
3.5.2	Capital Cost Procedures		3.5-1
3.5.3	Operating Cost Procedures		3.5-2
References		3.5-3
3.6	SPRAY DRYER RETROFIT		3.6-1
3.6.1	Overview of Technology		3.6-1
3.6.2	Capital Cost Procedures		3.6-1
3.6.3	Operating Cost Procedures		3.6-5
V

-------
TABLE OF CONTENTS
Section	Page
References		3.6-8
3.7	DETERMINATION OF RETROFIT FACTORS AND SCOPE ADDER COSTS		3.7-1
3.7.1	Retrofit Factors		3.7-1
3.7.2	Scope Adders		3.7-1
3.7.2.1	Ducting		3.7-1
3.7.2.2	Stacks		3.7-1
3.7.2.3	Demolition and Replacement		3.7-3
References		3.7-4
3.8	DOWNTIME COSTS FOR RETROFIT MODIFICATIONS		3.8-1
3.8.1	Procedures to Estimate Loss of Steam and
Electricity Sales		3.8-1
3.8.1.1	Loss of Steam Sales		3.8-1
3.8.1.2	Loss of Electricity Sales		3.8-1
3.8.2	Procedures to Estimate Costs from Loss of Tipping
Fees		3.8-3
References		3.8-4
Appendix A COST COMPARISON BETWEEN SPRAY DRYER/FABRIC FILTER AND
SPRAY DRYER/ELECTROSTATIC PRECIPITATOR SYSTEMS		A-l
Appendix B DETAILED COST EQUATIONS		B-l
vi

-------
LIST OF TABLES
Tabl e	Page
2.1-1 CAPITAL COSTS FOR MODULAR MWC's	 2.1-3
2.1-2 CAPITAL COSTS FOR A 860 TON/DAY MASS BURN MWC WITH
(WITHOUT) ELECTRICITY GENERATION	 2.1-7
2.1-3 CAPITAL COSTS FOR A COARSE RDF FACILITY WITH ELECTRICITY
GENERATION (CAPACITY = 850 TONS/DAY MSW, 800 TONS/DAY
RDF)	. 2.1-10
6.1-4 PROCEDURE FOR ESTIMATING CAPITAL COSTS FOR NEW FBC'S
(DECEMBER 1987 DOLLARS)	 2.1-14
2.1-5 ANNUAL OPERATING COST PROCEDURES FOR NEW FBC'S	 2.1-15
2.1-6	PROCEDURE FOR ESTIMATING ANNUAL OPERATING COSTS FOR
FBC'S (DECEMBER 1987 DOLLARS)	 2.1-17
2.2-1	VENDOR QUOTES FOR ESP EQUIPMENT COSTS (IN 1000$
AUGUST 1986)	 2.2-2
2.2-2 SPECIFIC COLLECTION AREA (SCA) REPORTED BY THE ESP
MANUFACTURERS		 2.2-5
2.2-3 AVERAGE SPECIFIC COLLECTION AREA (SCA) CALCULATED FROM
THE MANUFACTURERS' DATA	 2.2-6
2.2-4 COST PROCEDURES FOR ESTIMATING CAPITAL COSTS FOR ESP'S
ON NEW PLANTS	 2.2-11
2.2-5	COST PROCEDURES USED TO ESTIMATE ANNUAL OPERATING COSTS
FOR ESP'S ON NEW UNITS	 2.2-13
2.3-1	PROCEDURES FOR ESTIMATING CAPITAL COSTS FOR DRY SORBENT
INJECTION	 2.3-4
2.3-2 ANNUAL OPERATING COST PROCEDURES FOR DRY SORBENT
INJECTION FOR NEW MWC's	 2.3-7
2.3-3	ANNUAL OPERATING COST PROCEDURES FOR FABRIC FILTERS
FOR NEW MWC's	 2.3-8
2.4-1	VENDOR QUOTES FOR SPRAY DRYER/FABRIC FILTER TOTAL
CAPITAL COSTS (IN 1,000$ AUGUST 1986)	 2.4-3
2.4-2 CAPITAL COST PROCEDURES FOR SD/FF FOR NEW MWC's	 2.4-6
vii

-------
LIST OF TABLES
Table	Page
2.4-3	ANNUAL OPERATING COSTS PROCEDURES FOR SPRAY DRYER/FABRIC
FILTER FOR NEW MWC's		2.4-7
2.5-1	CONTINUOUS MONITORING COST SUMMARY (DECEMBER 1987 DOLLARS)	2.5-4
3.2-1	O&M COST INPUTS (DECEMBER 1987 DOLLARS)		3.2-13
3.3-1	CAPITAL COST PROCEDURES FOR HUM IDIFI CAT I ON		3.3-4
3.3-2 OPERATING AND MAINTENANCE COSTS FOR HUM IDIFICATION		3.3-5
3.6-1	VENDOR QUOTES FOR SPRAY DRYER DIRECT CAPTIAL COSTS
(in 1000$ August 1988)		3.6-2
3.6-2 CAPITAL COST PROCEDURES FOR SPRAY DRYERS		3.6-3
3.6-3	ANNUAL OPERATING COSTS PROCEDURES FOR STAND-ALONE SPRAY
DRYERS FOR NEW MEW's		3.6-6
3.7-1	SITE ACCESS AND CONGESTION FACTORS FOR RETROFITTING
APCD EQUIPMENT AT EXISTING PLANTS		3.7-2
3.8-1	DOWNTIME REQUIREMENTS IN MONTHS		3.8-2
viii

-------
LIST OF FIGURES
Figure	Page
2.2-1 Correlation of ESP equipment costs (in August 1986
dollars) from ESP manufacturers and total plate area... 2.2-3
2.2-2 Relationship between ESP manufacturers' specific
collection area and particulate matter removal	 2.2-7
2.2-3 Correlation of ESP purchase equipment costs with total
plate area for modular ESP's	 2.2-9
2.2-4 Relationship between specific collection area and
particulate matter removal for modular ESP's	 2.2-10
2.4-1 Capital cost estimates of an SD/FF for a Model MB
facility, and RDF facility	 2.4-4
3.6-1 Correlation of SD direct capital costs (in August 1988
dollars) from the SD manufacturers and flue gas
flowrate	 3.6-4
ix

-------
1.0 INTRODUCTION
This report documents the development of cost procedures for costing new
and existing municipal waste combustor (MWC) facilities, associated heat
recovery equipment, humidification equipment, air pollution control devices
(APCD's) for the reduction of particulate matter (PM) and acid gas emissions,
and continuous emission monitoring equipment. Costs presented in this report
are divided into three major cost categories:
•	Capital Costs;
•	Operating and Maintenance (O&M) Costs; and
•	Annualized Costs (total O&M cost plus capital -
related annual charges).
Each of these cost categories is further subdivided into individual cost
elements.
Capital cost elements include direct costs (purchase equipment and
installation costs), indirect costs, and contingencies. Direct costs consist
of the basic and auxiliary equipment, the labor and material required to
install the equipment, plus site preparation and buildings costs. Indirect
costs are those costs which are not attributable to specific equipment items
such as engineering, construction and field expenses, contractor fees, and
start-up and performance tests. Contingencies cover any unpredicted events
and other unforeseen expenses that may arise.
The O&M cost elements include direct and indirect costs. Direct O&M
costs consist of operating and maintenance labor, fuel, utilities, materials
and spare parts, supplies, waste disposal, and chemicals. These costs are
dependent on the combustor capacity utilization. Indirect O&M costs, on the
oiher hand, are totally independent of capacity utilization. These costs
include plant and payroll overhead, real estate and local taxes, insurance,
administrative charges, and replacement parts.
1-1

-------
Total annualized costs are the sum of the direct and indirect O&M costs
and capital recovery costs. Capital recovery costs are determined by
multiplying the total capital costs by the capital recovery factor, which is
based on the assumed interest rate and economic equipment life. A 10 percent
real interest rate and a 15-year equipment life are assumed for the
combustors and control equipment in this report. This translates into a
capital recovery factor of 13.15 percent.
All costs are presented in December 1987 constant dollars. Chapter 2.0
of this report presents the costing procedures for new MWC plants. Included
are procedures to estimate capital, operating and maintenance, and annualized
costs for combustors, combustor-related equipment, flue gas temperature
control, PM control using dry electrostatic precipitators (ESP's), acid gas
control using either dry sorbent injection or spray dryers followed by a
fabric filter for PM control, and continuous emission monitors (CEM's).
Chapter 3.0 presents the costing procedures for existing MWC plants which
include procedures used to estimate costs for operating existing combustors
and for retrofitting emission controls. Emission controls evaluated include
combustor modification, temperature control, PM control (rebuilding an
existing ESP, adding plate area, or installing a new ESP), and acid gas
controls using either dry sorbent injection or spray dryers with an existing
ESP or a fabric filter for PM control.
Appendix A compares the costs between spray dryer/fabric filter and
spray dryer/electrostatic precipitator systems applied to new plants. The
purpose of this comparison was to determine whether (1) the costs of these
systems differ sufficiently to warrant separate costing procedures for each
system and (2) a single procedure can be used. Appendix B presents the
tables summarizing the cost procedures presented in this report.

-------
COST COMPARISON BETWEEN SPRAY DRYER/FABRIC FILTERS (SO/FF)
AND SPRAY DRYER/ELECTROSTATIC PRECIPITATOR (SD/ESP) SYSTEMS
A.1 INTRODUCTION
This appendix compares SD/FF and SD/ESP costs for two model mass-burn
waterwall plants (a 250-tpd plant and a 3,000-tpd plant) at a PM outlet
concentration of 0.01 gr/dscf. Costs presented in the appendix for SD/FF
systems are based on cost procedures discussed in Section 2.4. Cost
procedures presented in this appendix were used for SD/ESP. Lime
requirements are based on a stoichiometric ratio of 1.5:1 for both systems.
The objective of this comparison was to determine whether (1) the costs of
these systems differ sufficiently to warrant separate costing procedures for
each system and (2) a single procedure can be used.
A.2 COST COMPARISON BETWEEN SD/ESP'S AND SD/FF
Costs for SD/ESP's and SD/FF systems are estimated for two model
mass-burn plants.1 Model plant 1 is a 250-tpd plant with two combustors,
whereas model plant 3 is a 3,000-tpd plant with four combustors. These
plants were selected to cover the size range of most MWC facilities. For
both plants, the SD systems are assumed to achieve 90 percent HC1 and 70
percent SO^ removal and an outlet PM emissions of 0.01 gr/dscf at 12 percent
C0ฃ. The following two sections discuss the approach taken in estimating
costs for SD/ESP applied to these model plants and the results of the cost
comparison. The costs for SD/FF systems are based on procedures presented in
Section 2.4 at a stoichiometric ratio of 1.5:1.
A.2.1 Approach Used to Estimate SD/ESP Costs
Table A-l presents purchased equipment cost data for SD/ESP's provided
by five manufacturers. The vendor quotations were based on design
specifications for model mass-burn and refuse-derived fuel (RDF) plants.
Because the costs in Table A-l contain significant scatter, the costs for
vendors A and C were used to develop the capital cost procedure for SD/ESP's
applied to mass-burn combustors. Both manufacturers are experienced in SD
technology. Furthermore, the costs reported by both were consistent and
generally were conservative compared to the other vendor's costs. Limited
A-l

-------
TABLE A-2. CAPITAL AND ANNUALIZED COSTS PROCEDURES FOR MASS BURN MWC'sa,b
Capital Costs (dollars per ton/day of MSW processed)
1.	Mass burn MWC without electrical generation:
Unit Capital Costs - 50,420 (430/Size)0,39
2.	Mass burn MWC with electrical generation:
Unit Capital Costs = 60,700 (430/Size)0,39
3.	Total Capital Costs = Unit Capital Cost * TPD
Annualized Costs
1.	Operating and Maintenance Costs excluding waste disposal:
For mass burn refractory wall MWC,
Costs = (15.7 - 0.00115 TPD) * Total Capital Costs/100
For mass burn waterwall MWC,
Costs = (12.5 - 0.00115 TPD) * Total Capital Costs/100
r
2.	Capital Recovery
Costs - CRF * Total Capital Costs
3.	Waste Disposal of Bottom Ash:
Costs = 1_ * 10Qi~oW^ * tpd * HRS * WDC
aCosts are estimated in December 1987 dollars.
^Size ป combustor MSW feed rate, tons/day
TPD = plant MSW feed rate, tons/day
HRS - hours of operation
CRF - Capital recovery factor, 0.1315 based on 10 percent interest rate and
15-year economic 1ife
WR = weight reduction MSW in the combustor percent
WDC = waste disposal cost rate, dollars per ton (typically $25/ton)
cApplies only to new plants. Capital recovery costs are not estimated for
retrofit applications, since the capital costs are sunk.
A-2

-------
cost data were available from vendor E at other outlet PM emission levels to
substantiate the relative high equipment cost at 0.01 gr/dscf at 12 percent
co2.
Table A-2 presents the capital cost procedures for SD/ESP applied to
mass-burn facilities only. A cost equation was developed relating purchased
equipment costs in Table A-l at an outlet PM emission level of 0.01 gr/dscf
at 12 percent CC.g with flue gas flowrate on a logarithmic basis. The
resultant equipment cost equation updated to December 1987 dollars using the
Chemical Engineering Plant Index is given below:
Equipment Costs, 10^ $ = 5.896 Q0,535
where:
Q - 125 percent of the actual flue gas flowrate, acfm.
Both installation and indirect costs are 60 percent of the equipment costs.
Assuming that the indirect costs are 33 percent of the direct costs, the
direct cost equation for SD/ESP system shown in Table A-2 can be derived.
Total direct cost equations for ductwork and the I.D. fan for SD/FF systems
in Section 2.4 are used directly for SD/ESP systems. To be consistent with
the SD/FF procedures in Section 2.4, costs for installation, indirect capital
costs, and contingencies for SD/ESP are based on the same percentages used in
the SD/FF procedures.
Operating costs for SD/ESP were estimated using Table A-3. These
operating costs are based on lower operating labor requirements (3 man-hours/
shift versus 4 man-hours/shift) and lower fan gas-side pressure drop
requirements (5.5 inches versus 12.5 inches) than those for SD/FF. The
gas-side pressure drop of 5.5 inches is based on a pressure drop of 5 inches
across the SD and 0.5 inches across the ESP. Electricity costs are included
for ESP energization. Additional costs are included for the SD/FF systems
for bag replacement and compressed air. The same cost rates used to estimate
SD/FF operating costs in Section 2.4 are used for estimating operating costs
for SD/ESP systems in December 1987 dollars.
A.2.2 Cost Comparison Results
Tables A-4 and A-5 present costs for both SD/ESP and SD/FF systems
applied to 250- and 3,000-tpd mass-burn plants, respectively. The capital
A-3

-------
TABLE A-2. CAPITAL COST PROCEDURES FOR SD/ESP ON NEW MASS-BURN PLANTS
Total Direct Costs (December 1987 dollars)3
Single SD/ESP Unit: Costs, 103S - 7.087 (Q)0'535
Ductwork: Costs, 103$ = 1.387 * L * Qฐ*S/1000
Fan: Costs, 103$ = 1.875 * Qฐ*96/1000
Multiple Units: Multiply the above costs by the number of units.
Indirect Costs = 33% of total direct costs.
Contingency - 20% of sum of direct and indirect costs.
Total Capital
Investment = Total Direct Costs + Indirect Costs + Contingency Costs.
aQ ซ 125 percent of the actual flue gas flowrate, acfm
L - Duct length, feet
Cost procedures assume that-the total installed costs are 133 percent of the
total direct capital costs.
A-4

-------
TABLE A-3. ANNUAL OPERATING COSTS PROCEDURES FOR
SD/ESP ON NEW MASS-BURN PLANTS
Reference
Operating Labor: 3 man-hours/shift; $12/man-hour	3, 4
Supervision: 15% of operation labor costs	4
Maintenance:
Labor -- 2 man-hour/shift	3, 4
10% wage rate premium
over operating labor wage
Materials -- 2% of direct capital costs	3
Electricity: Electricity costs - $0.046/kwh
?
ESP Energization -- 1.5 watts/ft plate area	5
Fan -- 5.5 inches of water pressure drop	6, 7
Atomizer Auxiliary Equipment --	8
Kw ฆ= 6kw per 1,000 lbs/hr of slurry feed + 15kw
Pump -- 20 feet of pumping height	9
10 psi discharge pressure
10 ft/sec velocity in pipe
Water: Based on water flowrate required for	10
cooling flue gas to 300 F and water cost
rate of $0.50/1000 gal
Lime: Based on lime feed rate to the spray	11
dryer calculated by assuming a stoichiometric
ratio of 1.5:1. Apply appropriate lime
costs in $/ton ($70/ton)
Solid Waste: Calculate solid waste disposal rate	12
collected by the ESP and the spray
dryer and apply appropriate tipping
fee in $/ton. (Assume $25/ton)
A-5

-------
TABLE A-3. ANNUAL OPERATING COSTS PROCEDURES FOR
SD/ESP ON NEW MASS-BURN PLANTS
(Continued)
Reference
Overhead: 60% of the sum of all labor	13
costs (operating, supervisory,
and maintenance) plus materials
Taxes, Insurance, and
Administrative Charges: 4% of total	13
capital costs
Capital Recovery: 15-year life and 10%	14
interest rate
A-6

-------
TABLE A-4. COSTS FOR SO/ESP'S AND SD/FF'S FOR A 250-TPD
MASS-BURN PLANT
Model Plant No. 1
250 tpd Mass-Burn Facility with 2 Combustors
Outlet PM Emissions = 0.01 gr/dscf
SD/FF	SD/ESP
Capital Cost fl.OOO $)
Total Direct	3,270	3,730
Total Indirect	1,080	1,230
Contingency	870	993
Total Capital Costs	5,220	5,960
Operating Costs (1,000$)
Direct Costs:
Operating Labor	96	72
Supervision	14	11
Maintenance Labor	53	40
Materials	65	75
Electricity	62	51
Water	1	1
Lime	50	50
Waste Disposal	81	81
Bag Replacements	15	0
Compressed Air	8	0
Indirect Costs:
Overhead	137	119
Taxes, Insurance. & Administration	209	238
Total Operating Costs	791	738
Annualized Costs
Capital Recovery	687	783
Total Annualized Costs	1,480	1,520
aCosts are 1n December 1987 dollars.

-------
TABLE A-5. COSTS FOR SD/ESP'S AND SD/FF'S FOR A 3,000-TPD
MASS-BURN PLANT
Model Plant No. 3
3,000 tpd Mass-Burn Facility with 4 Combustors
Outlet PM emissions =ฆ 0.01 gr/dscf
SD/FF	SD/ESP
Capital Cost (1,000 $)
Total Direct
Total Indirect
Contingency
Total Capital Costs
17,340	20,260
5,720	6,690
4.610	5.390
27,600	32,300
Operating Costs (1.000 S)
Direct Costs:
Operating Labor	192	144
Supervision	29	22
Maintenance Labor	106	106
Materials	347	405
Electricity	629	504
Water	12	12
Lime	594	594
Waste Disposal	975	975
Bag Replacements	184	0
Compressed Air	98	0
Indirect Costs:
Overhead	404	406
Taxes. Insurance. & Administration	1.110	1.290
Total Operating Costs	4,680	4,460
Annualized Costs
Capital Recovery	3.640	4.250
Total Annualized Costs	8,320	8,710
aCosts are in December 1987 dollars.
A-8

-------
c.osts for SD/ESP systems are higher than those for SD/FF systems for both
plants. This is because ESP capital costs are more sensitive to PM removal
requirements than those for FF's. At the removal efficiencies required to
achieve an outlet loading of 0.01 gr/dscf, the capital costs for a SD/ESP are
roughly 15 percent higher than for a SD/FF.
Tables A-4 and A-5 show that operating costs for SD/ESP and SD/FF
systems are essentially the same. For both plants, capital-related operating
costs are greater for an SD/ESP than for an SD/FF. The noncapital-related
costs for an SD/ESP are lower. The magnitude of these cost differences are
roughly equal, resulting in about the same operating costs for both SD
systems.
Because of lower capital costs, annualized costs for SD/FF systems are
roughly 4 percent less than SD/ESP systems for both model plants. The
results from this cost comparison, which showed the annualized costs for both
systems are similar, agreed with those presented in another cost study
prepared for the State of New York.^
A-9

-------
REFERENCES
1.	U. S. Environmental Protection Agency. Municipal Waste Combustion Study:
Costs of Flue Gas Cleaning Technologies, Research Triangle Park, NC.
Publication No. EPA/530-SW-87-021e. June 1987. pp. 2-1 to 2-3.
2.	Bowen, M.L. and M.S. Jennings (Radian Corporation). Cost of Sulfur
Dioxide, Particulate Matter, and Nitrogen Oxide Controls in Fossil Fuel
Fired Industrial Boilers. Prepared for the U. S. Environmental
Protection Agency. Research Triangle Park, NC. Publication No.
EPA-450/3-82-021. August 1982. p. 2-11.
3.	Memorandum from Aul, E.F. et al., Radian Corporation, to Sedman, C.B.,
EPA. May 16, 1983. 30 p. Revised Cost Algorithms for Lime Spray
Drying and Dual Alkali F6D Systems.
4.	Vatavuk, W.M., and R.B. Neveril, Estimating Costs of Air Pollution
Control Systems, Part II: Factors for Estimating Capital and Operating
Costs, Chemical Engineering. November 3, 1980. pp. 157 to 162.
5.	Neveril, R. B. (GARD, Inc.) Capital and Operating Costs of Selected Air
Pollution Control Systems. Prepared for the U. S. Environmental
Protection Agency. Research Triangle Park, NC. Publication No.
EPA-750/5-80-002. p. 3-18.
6.	U. S. Environmental Protection Agency. EAB Control Cost Manual.
Research Triangle Park, NC. Publication No. EPA-450/5-87-001A.
February 1987. p. 6-39.
7.	Letter and attachment from Fiesinger, T., New York State Energy Research
and Development Authority, to Johnston, M., EPA. January 27, 1987.
Draft report on the economics of various pollution control alternatives
for refuse-to-energy plants, p. 6-9.
8.	Reference 7, p. 6-10.
9.	Dickerman, J.C. and K. L. Johnson. (Radian Corporation) Technology
Assessment Report for Industrial Boiler Applications: Flue Gas
Desulfurlzation. Prepared for the U. S. Environmental Protection
Agency. Washington, DC. Publication No. EPA-600/7-79-178i.
November 1979. pp. 5-5 and 5-17.
10.	Letter from Solt, J.C., Solar Turbines Incorporated, to Noble, E., EPA.
October 19, 1984. Development cost for wet control for stationary gas
turbines.
11.	Chemical Marketing Reporter. Volume 233. Number 1. January 4, 1988.
12.	Reference 6, p. 2-29.
A-10

-------
13.	Reference 6,
14.	Reference 2,
15.	Reference 7,
p. 2-31.
pp. 2-17 and 2-18.
pp. 6-1 to 6-17.
A-ll

-------
TABLE B-1. CAPITAL AND ANNUALIZED COST PROCEDURES FOR MODULAR MWC'sa'b
Capital Costs
1.	Modular MWC without heat recovery:
Unit Capital Cost = $24,300 per ton/day of MSW processed
2.	Modular MWC producing steam (without generating electricity):
Unit Capital Cost = $32,500 per ton/day of MSW processed
3.	Modular MWC generating electricity:
Unit Capital Cost = $54,600 per ton/day of MSW processed
4.	Total Capital Costs = Unit Capital Costs * TPD
Annualized Costs^
1.	Operating and Maintenance Costs excluding waste disposal:
For TPD < 150 and HRS < 6,000,
Costs - (10 - 0.23 TPD + 0.006 HRS) * Total Capital Costs/100
Otherwise,
Costs = (15.7 - 0.00115 TPD) * Total Capital Costs/100
2.	Capital Recovery0:
Costs ซ CRF * Total Capital Costs
3.	Waste Disposal of Bottom Ash:
Costs - i_ .(ioo^Wr) * TpD * HRS * WDC
aCosts are estimated in December 1987 dollars.
bTPD = plant MSW feed rate, tons/day
HRS = hours of operation
CRF - capital recovery factor, 0.1315 based on 10 percent interest rate and
15-year economic life
WR ซ weight reduction of MSW in the combustor, percent
WDC - waste disposal cost rate, dollars per ton (typically $25/ton)
cApplies only to new plants. Capital recovery costs are not estimated for
retrofit applications since the capital costs are sunk.
B-l

-------
TABLE B-2. CAPITAL AND ANNUALIZED COSTS PROCEDURES FOR MASS-BURN MWC'sa,b
Capital Costs (dollars per ton/dav of NSW processed)
1.	Mass-burn MWC without electrical generation:
Unit Capital Costs = 50,420 (430/Size)0'39
2.	Mass-burn MWC with electrical generation:
Unit Capital Costs = 60,700 (430/Size)^"39
3.	Total Capital Costs - Unit Capital Cost * TPD
Annualized Costs
1.	Operating and Maintenance Costs excluding waste disposal:
For mass-burn refractory wall MWC,
Costs = (15.7 - 0.00115 TPD) * Total Capital Costs/100
For mass-burn waterwall MWC,
Costs - (12.5 - 0.00115 TPD) * Total Capital Costs/100
2.	Capital Recovery0
Costs = CRF * Total Capital Costs
3.	Waste Disposal of Bottom Ash:
Costs = i_ * 100 "nWR * TPD * HRS * WDC
24	100
aCosts are estimated in December 1987 dollars.
^Size - combustor MSW feed rate, tons/day
TPD = plant MSW feed rate, tons/day
HRS ป hours of operation
CRF = Capital recovery factor, 0.1315 based on 10 percent interest rate and
15-year economic 1ife
WR = weight reduction MSW in the combustor percent
WDC - waste disposal cost rate, dollars per ton (typically $25/ton)
cApplies only to new plants. Capital recovery costs are not estimated for
retrofit applications, since the capital costs are sunk.
B-2

-------
TABLE B-3. CAPITAL AND ANNUALIZED COST PROCEDURES FOR RDF FACILITIES3'5
Capital Costs (dollars per ton/dav of RDF processed)
1. Coarse RD facility:
Unit Capital Costs - 73,600 (400/Size)1^'^
2. F1uff RDF faci1ity:
Unit Capital Costs = 161,880 (315/Size)0-39
3. Total Capital Costs = Unit Capital Costs * TPD
Annualized Costsc
1.	Operating and Maintenance Costs excluding waste disposal:
Costs - (12.5 - 0.00115 TPD) * Total Capital Costs/100
2.	Capital Recovery0:
Costs = CRF * Total Capital Costs
3. Waste Disposal of Bottom Ash:
Costs = i_ * ^ฐฐ1'qWR^* TPD * HRS * WDC
aCosts are estimated in December 1987 dollars.
^Size = combustor RDF feed rate, tons/day
TPD ซ plant MSW feed rate, tons/day
CRF = capital recovery factor, 0.1315 based on 10 percent interest rate and
15-year economic 1ife
WR ป weight reduction of MSW in the combustor, percent
HRS = hours of operation
WDC - waste disposal cost rate, dollars per ton (typically 525/ton)
cApplies only to new plants. Capital recovery costs are not estimated for
retrofit applications since the capital costs are sunk.
B-3

-------
TABLE B-4. PROCEDURE FOR ESTIMATING CAPITAL COSTS FOR NEW FBC'S
(December 1987 dollars)
Total Direct and Indirect Costs:a
Costs, 103$ - 64,900 * TPD * (900/TPD)0'39
Process Contingency: 20% of total direct and indirect costs
Total Capital FBC Costs: Total direct and indirect costs + process
conti ngency
aTPD = plant municipal waste feed rate, tons/day.
B-4

-------
TABLE B-5. PROCEDURE FOR ESTIMATING ANNUAL OPERATING COSTS FOR FBC'S
(December 1987 dollars)
Combustor and Balance of Plant (excludes coarse RDF processing area):
Operating labor (based on 10 man-years. 40 hours/week. S12/hrV:
OL - 10 * 40 * 52 * 12 * (TPD/900) - 277.3 * TPD
Supervision (based on 3 man-years/year. 40 hours/week. 30% wage rate
premium over the operating labor wage):
SPRV = 3 * 40 * 52 * 12 * 1.3 * (TPD/900) = 108.2 * TPD
Maintenance labor (based on 3 man-years/year, 40 hours/week. 10% wage
rate premium over the operating labor wage):
ML - 3 * 40 * 52 * 12 * 1.1 * (TPD/900) = 91.5 * TPD
Maintenance materials: 3% of the total capital costs
Electricity (based on 3 MW power consumption, and electricity rate of
S0.046/kwh):
ELEC = 0.153 * TPD * HRS
Limestone (based on S40/ton for limestone):
LIMESTONE - 0.02 * LFEED * HRS * N
Water (based on 3% blowdown rate and SO.05/1.000 gal):
WC - 1.86 x 10"6 * STM * HRS
Waste disposal (based on tipping fee of S25/hr):
AD - 1.25 x 10"2 * N * HRS * WDR
Overhead: 60% of the sum of all labor costs (operating, supervisory,
and maintenance) plus 60% of maintenance materials costs
Continued
B-5

-------
TABLE B-5. (CONCLUDED). PROCEDURE FOR ESTIMATING ANNUAL OPERATING COSTS
FOR FBC'S (December 1987 dollars)
Coarse RDF Processing Area:
Total Operating and Maintenance Costs (TOT O&M);
TOT O&M = 4.4 x 10"4 * (12.5 - 0.00115 * TPD) * TDI
Taxes. Insurance, and Administrative Charges:
4% of the total capital cost
Capital Recovery (based on 15 year life and 10% interest rate):
13.15% of the total capital cost
aOL * operating labor costs, $/yr
SPRV =ฆ supervision costs, $/yr
ML = maintenance labor costs, S/yr
ELEC = electricity costs, $/yr
HRS - hours of operation per year
LIMESTONE - limestone costs, $/yr
LFEED = limestone feed rate per unit, Ib/hr
N = number of combustors
WC ฆ water costs, $/yr
STM = plant steam production, lb/hr
AD = waste disposal costs, $/yr
WDR = waste disposal rate per unit (bottom and fly ash collected), lb/hr
TPD = plant municipal waste feed rate, tons/day
TDI = total direct and indirect capital costs for FBC plant, $
B-6

-------
TABLE B-6. PROCEDURES FOR ESTIMATING CAPITAL. COSTS
FOR ELECTROSTATIC PRECIPITATORS (ESP'S)a,D
Design Equation for Mass-burn and RDF Facilities:
SCA = -189.29 In H00 - PMEFF)
101.89
Design Equation for Modular Units:
o Use above design equation for large modular units whose flue gas
flowrate (Q) is greater than or equal to 30,000 acfm
o For small modular units whose Q < 30,000
SCA = -285.7 In (100 - PMEFF)
79.6
Purchased Eouipment Costs
ESP for Massburn and RDF plants and large modular plants0:
Costs, 10J $ - (305.2 + 0.00738 * TPA) * RF * N
ESP for small modular plants (Q < 30,000)c:
Costs, 10J $ = 1.08 * (96.3 + 0.015 * TPA) RF * N
ESP Rebuilds: ,
Costs, 10 $ = 0.42 * purchased equipment costs for a new ESP (RF - 1)
Ductwork: 7	n c
Costs, 10"1 $ - 0.7964 * N * RF * Q
Costs, 103 $ = 1.077 * N * RF * Q0,96
Installation Direct Costs
= 67% of purchased equipment costs for new ESP and ESP upgrades
(i.e., addition of new plate area in existing ESP)
= 33% of purchased equipment costs for ESP rebuilds only
(conti nued)
B-7

-------
TABLE B-6. (Continued)
Indirect Costs
- 54% of purchased equipment costs for mass-burn, RDF, and large modular
units with new ESP and ESP upgrades
= $14,000 for small modular units with new ESP and ESP upgrades
= 24% of the purchased equipment costs for ESP rebuilds
Contingency
= 3% of purchased equipment costs
Total Capital Costs
* Purchased equipment costs + installation direct costs +
indirect costs + contingency costs
aCosts are estimated in December 1987 dollars.
kpMEFF =ป particulate matter removal efficiency, percent
SCA - specific collection area, ft /I,000 acfm
Q = 125 percent of the actual flue gas flowrate per ESP unit, acfm
TPA = total plate area, ft
RF - retrofit factor obtained from Table B-16
N - number of ESP units
L ซ duct length, feet
cIncludes taxes and freight of eight percent of the ESP equipment costs. For
retrofit applications requiring additional plate area of the existing ESP,
TPA is the increase in the plate area.
B-8

-------
TABLE B-7. PROCEDURE FOR ESTIHATING ANNUAL OPERATING COSTS FOR ESP'sa,b
Operating Labor0 (Based on 1 manhour/shift. labor wage of >12/hr): OL = 1.5 * N * HRS
Supervision0; 15X of the operating labor cost (OL)
Maintenance Labor0 (Based on 0.5 manhour/shift. 10% wage rate premium over the operating labor wage): ML = 0.825 * N * HRS
Maintenance Materials: 1X of the direct capital costs'*
Electricity for 1.0. fan (Based on 0.5 inch pressure drop W.C. and electricity rate of t0.046/l(wh): FANELEC = 4.50 * tO ' * FLW * N • HRS
2	_ n
Electricity Consumed by ESP (Based on 1.5 watts/ft collection area and electricity rate of to.046/kwh): ESPELEC = 6.9 x 10 • TPA * N * HRS
Ash Disposal (Based on tipping fee of t25/ton): AD = 1.25 x 10 ^ * N * HRS * UDR
Overhead: 60X of the sum of all labor costs (operating, supervisory, and maintenance) plus 60X of maintenance materials costs
CO
i
vC
Taxes. Insurance, and Administrative Charges: 4X of the total capital costs
Capital Recovery (Based on 15 year life and 10X interest rate): 13.15X of the total capital costs
ft	•
For ESP rebuilds, the only annual costs are for an increase in waste disposal and capital recovery. All costs are estimated in December 1987
dollars.
OL	= operating labor costs, S/yr
N	= number of ESP units
HRS = hours of operation
ML	= maintenance labor costs, S/yr
FANELEC = electricity costs for 1.0. fan, S/yr
ESPELEC = electricity costs for ESP, S/yr
FLU = actual flue gas flourate per unit, acfm
AD	= ash disposal costs, S/yr
UDR = waste disposal rate per unit, Ib/hr
ฐLabor costs are estimated only for neu ESP's. The labor costs for ESP retrofits (including upgrades and rebuilds) are zero.
^Direct capital costs are the sum of purchase equipment costs and installation direct costs.

-------
TABLE B-8. PROCEDURES FOR ESTIMATING CAPITAL COSTS FOR DRY SORBENT INJECTIONa,b
Purchased Equipment Costs. 103 t
Lime Storage Silo with Vibrator. Baghouse. and Flow Control Value (Based on 15-dav lime supply)
torage volumes (V) less than or equt
Costs = 1.05 • (34.2 ~ 0.016V) • RF
torage volumes between 2,300 and 4,t
Costs = 2.10 * (34.2 ~ 0.016V) • RF
o For storage volumes (V) less than or equal to 2,300 ft3 (one storage silo per plant).
For storage volumes between 2,300 and 4,600 ft' (two storage silos per plant).
o For storage volume greater than 4,600 ft3 (two storage silos per plant),
Costs i 2.10 * (63 ~ 0.0038V) • RF
2.	Feed Bins
o For duct sorbent injection (one feed bin per combustor),
Costs = 0.0906 • N • RF • (SF)0-6145
o For furnace sorbent injection (two feed bins per combustor),
^	Costs = 0.1812 * N • RF • (SF)0-6145
C
3.	Gravimetric Feeders
o For duct sorbent injection (one feeder per combustor),
Costs = 1.024 • (0.000289 SF ~ 9.293) * N • RF
o For furnace sorbent injection (two feeders per combustor).
Costs = 2.048 • (0.000289 SF ~ 9.293) • N • RF
4.	Pneumatic Conveyor (Based on 400 Feet Length)
Costs = 1.05 * (26.4 ~ 0.0073 SF ~ 0.4 • [12.8 ~ 11.23 SF0-23]) N • RF
5.	Injection Ports
o For duct sorbent injection (one injection port per combustor).
Costs = 1.05 • (22.2 ~ 0.0014 SF) * N * RF
o For furnace sorbent injection (two injection ports per combustor).
Costs = 2.10 * (22.2 ~ 0.0014 SF) * N * RF
(cont i nued)

-------
TABLE B-8. (Continued)
6.	Reactor Vessel (optional for duct sorbent injection to increase flue gas and sorbent contact): Costs = 34 * (0 * 1.25/6,150)""'^
c
7.	Fabric Filter
Costs = 0.1482 * N • RF • q0-7043
8.	Induced Draft Fan
Costs = (1.167 * N * RF • 0096)/1,000
9.	Ductwork
Costs = (0.8627 • N * RF * L * Qฐ"5)/1,000
Installation Direct Costs
= 30X of dry sorbent injection equipment costs ~ 72X of fabric filter and auxiliary equipment costs
Indirect Costs
= 33X of direct costs (equipment ~ installation costs) for dry sorbent injection ~
42X of equipment cost for the fabric filter and auxiliary equipment
Cont ingency
= 50X of the sum of direct and indirect costs
Total Capital Costs
= Total Direct Costs + Indirect Costs + Contingency Costs
sAll costs are estimated in December 1987 dollars.
SF = lime feed rate per unit, Ib/hr
Q = 125 percent of the actual flue gas flourat^ to the fabric filter per unit, acfm
V = lime storage silo volume for the plant, ft
N = number of units
RF = Retrofit factor. For retrofit applications, use retrofit factor of 1.1 for sorbent injection equipment. Retrofit factors for fabric
filter and auxiliary equipment are obtained from Table B-16.
L = duct length, feet
cFabric filters are used for new applications and for retrofit applications uhere no ESP exists. For plants uith existing ESP's, costs for
upgrading the ESP are estimated from Table B-6.

-------
TABLE B-9. PROCEDURES FOR ESTIMATING ANNUAL OPERATING COSTS FOR DRY SORBENT INJECTION3,6
Operating Labor (Based on 2 manhours/shift. wage of >12/hr): CL = 5.0 * M 1 HRS
Supervision: 15X of the operating labor cost (OL)
Maintenance Labor: (Based on 0.5 manhour/shift. IPX wage rate premium over the operating labor wage): ML = 0.825 * N * HRS
Maintenance Materials: 5X of the direct capital costs of the sorbent injection equipment0
Electricity (Based on electricity rate of >0.046/ltwh): ELEC = 5.25 * 10 ' ' (251,850 ~ 52.56 * SF) * N • HRS
Lime: (Based on >80/ton for hydrated lime and acid gas stoichiometric ratio of 2:1): LIME = 0.04 * SF * N * HRS
CD
I
> 1
Overhead: 60X of the sum of all labor costs (operating, supervisory, and maintenance) plus 6PX of maintenance materials costs
Taxes. Insurance, and Administrative Charges: 4% of the total capital costs
Capital Recovery (Based on 15 year life and IPX interest rate): 13.15X of the total capital costs
aAll costs are estimated in December 1987 dollars.
^OL = operating labor costs, S/yr
N = number of units
HRS = hours of operation
ML = maintenance labor costs, $/yr
ELEC = dry sorbent injection electricity costs, $/yr
SF = lime feed rate per unit, Ib/hr
LIME = lime costs, $/yr
CDirect capital costs are the sum of purchase equipment costs and installation direct costs.

-------
TABLE B-10. PROCEDURES FOR ESTIMATING ANNUAL OPERATING COSTS FOR FABRIC FILTERS3,5
Operating Labor (Based on 2 manhours/shift. wage of S12/hr): OL =3.0 * N * HRS
Supervi si on: 15X of the operating labor cost (OL)
Maintenance Labor: (Based on 1 manhour/shift. IPX wage rate premium over the operating labor wage): ML = 1.65 * N * HRS
Q
Maintenance Materials: 5X of the direct capital costs of both the fabric filter and auxiliary equipment
2
Bag Replacement: (Based on >1.35/ft . gross air-to-cloth ratio of 3:1. 2 year bag life, and 10X interest rate): BAG = 0.2593 * 0 * N
-L
Electricity (Based on 12.5 inches U.C. pressure drop and electricity rate of >0.046/lcwh): ELEC = 1.12 x 10 • FLU • N * HRS
Compressed Air (Based on 2 scfm of air/1.000 acfm flue gas and $0.17/1.000 scfm for compressed air): AIR = 2.01 x 10 * FLU * N * HRS
cn	Ash Disposal (Based on tipping fee of >25/ton): AD = 1.25 x 10 ^ ' N ' HRS * UDR
ป—ป
CO
Overhead: 60X of the sum of all labor costs (operating, supervisory, and maintenance) plus 60X of maintenance materials costs
Taxes. Insurance, and Administrative Charges: 4X of the total capital costs
Capitol Recovery (Based on 15 year life and 10X interest rate): 13.15X of the total capital costs
aAll costs are estimated in December 1987 dollars.
^OL = operating labor costs, $/yr
N = number of units
HRS = hours of operation
ML = maintenance labor costs, S/yr
BAG = bag replacement costs, S/yr
0 = 125 percent of the inlet flue gas flowrate per unit, acfm
FLU = actual flue gas flowrate per unit, acfm
ELEC = electricity costs, $/yr
AIR = compressed air costs, $/yr
UDR = ash disposal rate from fabric filter per unit, Ib/hr
cDirect capital costs are the sum of the purchase equipment costs and installation direct costs.

-------
TABLE B-ll. PROCEDURES FOR ESTIMATING CAPITAL COSTS OF STANDALONE
SPRAY DRYER AND SPRAY DRYER/FABRIC FILTERS '
Direct Costs
SD/FF Unitc: Costs, 103 $ - 8.053 * N * RF * (Q)0'517
Stand-Alone SD Unit: Costs, 103 $ = 8.428 * N * RF * (Q)0'460
Ductwork0: Costs, 103 $ = (1.3868 * N * RF * L * Qฐ-5)/l,000
FanC: Costs, 103 $ - (1.8754 * N * RF * Qฐ'96)/1,000
Indirect Costs = 33% of direct costs
Contingency = 20% of sum of direct and indirect costs
Total Capital Investment = Direct Costs + Indirect Costs + Contingency Costs
aAll costs are estimated in December 1987 dollars.
bQ = 125% of the actual flue gas flowrate, acfm
N = number of units
RF = retrofit factor obtained from Table B-16
L = Duct length per unit, feet
cThe total installed costs are assumed to be 133 percent of the direct capital
costs.
B-14

-------
TABLE B-12. PROCEDURE FOR ESTIMATING ANNUAL OPERATING COSTS FOR STAND-ALONE SPRAY DRYERS
AND SPRAY DRYER/FABRIC FILTERS '
Operating Labor for SD/FF (Based on 4 manhours/shift. labor wage of $12/hr): OL = 6.0 * N * HRS
Operating Labor for SD (Based on 2 manhours/shift. labor wage of H2/hr): OL = 3.0 * N • HRS
Supervision: 15X of the operating labor cost (OL)
Haintenance Labor for SD/FF: (Based on 2 manhcurs/shift. IPX wage rate premium over the operating labor wage): ML = 3.3 • N * HRS
Maintenance Labor for SD: (Based on 1 manhour/shift. 10X wage rate premium over the operating labor wage): ML = 1.7 • N * HRS
Haintenance Materials: 2X of the total direct capital costs
Bag Replacement for SD/FF: (Based on t1.35/ft^. gross air-to-cloth ratio of 3:1. 2 year bag life, and 10X interest rate): BAG = 0.2593 • 0 * N
>
- L
Electricity for I.D. Fan for SD/FF (Based on 12.5 inches W.C. pressure drop and electricity rate of t0.046/kwh): FANELEC = 1.12 x 10 • FLW
* N * HRS
Electricity for I.D. Fan for SD (Based on 5.5 inches W.C. pressure drop and electricity rate of >0.0&6/kwh): FANELEC = 4.93 * 10 ^ * FLW • N * HRS
Electricity for Atomizer (Based on 6 ku per 1,000 Ib/hr
of slurry feed + 15 kw and electricity rate of $0.046/kwh): ATELEC = 0.046 * (0.006 • (SF ~ WTR) ~ 15) • N • HRS
Electricity for Pump (Based on 20 feet of pumping height,	,
10 psi discharge pressure. 10 ft/sec velocity in piping): PUMPELEC = 1.291 X 10 • (SF ~ WTR) * N * HRS
Compressed Air for SD/FF (Based on 2 scfm of air/1.000 acfm flue gas and >0.17/1.000 scfm for compressed air): AIR = 2.01 x 10 • FLW • N * HRS
Water: (Based on Flue gas cooling to 300ฐF and $0.50/1.000 gal): WC = 6.00 x 10 ' * WTR * N * HRS
Lime: (Based on $70/ton for quick lime): LIME = 0.035 * SF * N * HRS

-------
TABLE B-12. (Continued)
Ash Disposal for SD/FF (Based on tipping fee of t25/ton): AO = 1.25 x 10 * N * HRS * UOR
Overhead: 60X of the sum of all labor costs (operating, supervisory, and maintenance) plus 60X of maintenance materials costs
Taxes. Insurance, and Administrative Charges: AX of the total capital costs
Capital Recovery (Based on 15 year life and IPX interest rate): 13.15X of the total capital costs
aAll costs are estimated in December 1987 dollars.
OL
=
operating labor costs, 4/yr
N
=
number of units
HRS
=
hours of operation
HL
=
maintenance labor costs, S/yr
BAG
=
bag replacement costs, S/yr
Q
=
125 percent of the actual flue gas flowrate to the fabric filter per unit, acfm
FLU
=
actual flue gas flowrate to the fabric filter per unit, acfm
SF
=
lime feed rate per unit, Ib/hr
UTR
=
water rate per unit, Ib/hr
FANELEC
=
electricity costs for the fan, $/yr
ATELEC
=
electricity costs for the atomizer, i/yr
PUHPELEC
=
electricity costs for the the pumps, $/yr
AIR
=
compressed air costs, S/yr
UC
=
water costs, S/yr
LI HE
=
Iime costs, $/yr
AO
=
ash disposal costs, t/yr
UOR
=
waste disposal rate, Ib/hr

-------
TABLE B-13. PROCEDURES FOR ESTIMATING CAPITAL COSTS FOR HUMIDIFICATIONa,b
Purchased Equipment Costs, 103 $
1.	Humidification Chamber and Pumps:
Costs = (0.438 * Q + 80,220) N * RF/1,000
2.	Ductwork:
Costs = (1.16 * L * Qฐ"5) * N * RF/1,000
Installation Direct Costs = 56% of Purchase Equipment Costs
Indirect Costs	= 32% of Purchase Equipment Costs
Contingency	= 3% of the Purchase Equipment Costs
Total Capital Costs	= Purchased Equipment Costs +
Installation Direct Costs + Indirect Costs
= 191% of Purchase Equipment Costs
aAll costs are estimated in December 1987 dollars.
= 125% of the actual flue gas flowrate, acfm
L = duct length per unit, feet
N = number of units
RF = retrofit factor obtained from Table B-16
B -17

-------
TABLE B-14. PROCEDURE FOR ESTIMATING ANNUAL OPERATING COSTS FOR HUMIDIFICAT IONa *b
Operating Labor (Based on 0.5 manhours/shift. labor wage of SIZ/hr); OL = 0.75 * N * HRS
Suoervi sion: 15X of the operating labor cost (OL)
Maintenance Labor: (Based on 0.5 manhour/shift. 10X wage premium over the operating labor wage): ML = 0.825 • N * HRS
Maintenance Materials: IX of the total capital cosVs
Electricity for Pumpsc (Based on 20 feet of pumping height, 100 psi discharge	.
pressure. 10 ft/sec velocity in piping, and electrical rate of t0.046/kwh): ELEC = 7.3 X 10 • N * HRS * UTR
Mater (Based on SO.50/1.000 gal)C: UC = 6.0 x 10'5 * UTR * N * HRS
Overhead: 60X of the sum of all labor costs (operating, supervisory, and maintenance) plus 60X of maintenance materials costs
Taxes. Insurance, and Administrative Charges: 4X of the total capital costs
Capital Recovery (Based on 15 year life and IPX interest rate): 13.15% of the total capital costs
aA11 costs are estimated in December 1987 dollars.
b0L	= operating labor costs, $/yr
N	= number of units
HRS	= hours of operation
ML	= maintenance labor costs, S/yr
UTR	= water injection rate, Ib/hr
ELEC	= electricity costs, J/yr
UC	= water costs, S/yr
CUTR = (Tin-Tout) * Os * (1-M01ST/100)/940
where
Tin = inlet flue gas temperature, F
Tout = outlet flue gas temperature, F
Os = flue gas flow rate per unit, scfm
MOIST = moisture content in flue gas, volume percent

-------
TABLE B-15. CONTINUOUS MONITORING COST SUMMARY3
Pol 1utant
compli ance
options	Method
Capital
costs
($1,000)
Operating
costs
($1,000/yr)
Annuali zed
costs
($1,000/yr)
61
8
16
67
10
19
140
74
92
19
15
18
31
4
8
256
103
137
61
8
16
67
10
19
140
74
92
19
15
18
286
107
145
PM only	Opacity'5
Acid gas only SO- (inlet and outlet)
HCt (inlet and outlet)
o2/co
Data Reduction System
Total
PM + acid gas Opacity13
SO? (inlet and outlet)
HCt (inlet and outlet)
e2ZCo2	
Total
aAll costs are reported in December 1987 dollars. For multiple control units,
multiply these costs by the number of units.
^Includes costs for automatic data reduction system.
cBased on 2 certifications/year and maintenance requirements of
0.5 man-hour/day for both opacity and 0-/C0- monitors and 1 man-hour/day for
S05 and HC1 monitors.
J t
Annualized costs include annual operating costs and capital charges on
equipment and installation costs. Capital charges are based on a 15-year
equipment life at 10 percent interest rate.
B-19

-------
TABLE B-16. SITE ACCESS AND CONGESTION FACTORS FOR RETROFITTING
APCD EQUIPMENT AT EXISTING PLANTS
Retrofit
factor
Congestion
level
Guidelines for selecting retrofit factor
1.02
Base case
Interferences similar to a new plant with adequate
crew work space. Free access for cranes. Area
around combustor and stack adequate for standard
layout of equipment.
1.08
Low
Some aboveground interferences and work space
limitations. Access for cranes limited to two
sides. Equipment cannot be laid out in standard
design. Some equipment must be elevated or
located remotely.
1.25
Medium
Limited space. Interference with existing
structures or equipment which cannot be relocated.
Special designs are necessary. Crane access
limited to one side. Majority of equipment
elevated or remotely located.
1.42
High
Severely limited space and access. Crowded
working conditions. Access for cranes blocked
from all sides.
B-20

-------
TABLE B-17. PROCEDURE FOR ESTIMATING SCOPE ADDER CAPITAL COSTS3'b
Direct and Indirect Costs
1.	New Ducting:
Costs, 103 $ = 1.844 * L * N * RF * Q0,5
2.	New I.D. Fan:
Costs, 103 S ป 2.493 * N * RF * Q0"96
3.	New Stacks (costs per stack):
o For a lined acid resistant stack,
Costs, 103 $ - [26.2 + 0.089 * H * (1 + 4.14 * D)] for D > 5
Costs, 103 $ = [26.2 + 0.080 * H * (1 + 4.33 * D)] for D < 5
o For a unlined stack,
Costs, 103 5 ซ [26.2 + 0.0625 * H * (1 + 2.59 * D)] for D > 5
Costs, 103 $ - [26.2 + 0.087 * H * (1 + 2.2 * D)] for D < 5
Continaencv = 20% of the direct and indirect costs
Total Capital Costs = Direct Costs + Indirect Costs + Contingency Costs
aAll costs are estimated in December 1987 dollars.
bL = duct length per unit, feet
N = number of units
RF = retrofit factor obtained from Table B-16
Q = 125% of the actual flue gas flowrate, acfm
H = stack height, feet
D =ป stack diameter, feet
B-21

-------
TABLE B-18. DOWNTIME COST PROCEDURE3
Capital Costsb
Loss of Tipping Fees:
Costs, $	* WDC * HRS * (DT/12)
Loss of Energy (Steam or Electricity):
Costs, $ = IฃD * er * HRS * 0C * (DT/12)
Annualized Costs (Capital Recovery)0
Costs, $ =• CRF * Downtime Capital Costs
aCosts are estimated in December 1987 dollars. Apply only to retrofit
applications.
^WR = weight reduction of waste in the combustor, percent
WDC = waste disposal cost rate, dollars per ton (typically $25/ton)
TPD = plant waste feed rate, tons/day
HRS - hours of operation
DT - downtime, months
ER - energy cost rate, dollars per ton ($24.84/ton for mass burn waterwall
units, $36.16/ton for RDF units, and $19.52/ton for modular and mass
burn refractory units with heat recovery)
cCRF = capital recovery factor, 0.1315 based on 10 percent interest rate and
15-year economic life
B-22

-------
2.0 PROCEDURES FOR NEW PLANTS
This section presents procedures for estimating costs of new MWC plants.
The capital and annualized costs of a new plant include the combustors and
associated equipment, air pollution control devices (APCD's), and continuous
emission monitoring equipment. Section 2.1 presents the procedures for
costing the MWC combustors and associated equipment (denoted as the balance
of plant). Procedures for costing electrostatic precipitators (ESP's), dry
sorbent injection (DSI), and spray drying (SD) are presented in Sections 2.2,
2.3, and 2.4, respectively. Section 2.5 presents compliance monitoring
equipment costs for opacity, HC1, SO^, 0^, and CO2.
2.1 COMBUSTORS AND BALANCE OF PLANT
This section presents procedures for estimating the combustor and
associated equipment costs, excluding the air pollution control devices
(APCD's), for four types of combustors: modular, mass burn, refuse-derived
fuel (RDF), and fluidized bed combustion (FBC). The capital cost procedures
for each combustor type with the exception of fluidized bed combustors were
developed from data presented in Frost and Sullivan.1 The operating cost
procedures were developed from responses to an information request which EPA
sent to MWC operators under authority of Section 114 of the Clean Air Act.
Capital and operating cost procedures for FBC's were developed from vendor
data.
Sections 2.1.1, 2.1.2, 2.1.3, and 2.1.4 present the cost procedures for
modular, mass burn, RDF, and FBC facilities, respectively. Detailed cost
data suitable for direct estimation of capital costs for MWC's of various
types and sizes were not available. Therefore, the procedures presented in
these sections are based on scaling the capital cost of typical size
facilities of each combustor type. The capital costs estimated for these
facilities were all based on Frost and Sullivan (with the exception of FBC's)
to minimize inconsistencies in cost assumptions among combustor types. To
facilitate use of these costs with those presented in subsequent sections of
this report, the original combustor capital cost estimates were revised to
exclude the cost of the APCD. Indirect cost estimations for general
facilities and engineering fees are also based on Frost and Sullivan.
2.1-1

-------
Capital costs were updated from 1985 dollars in Frost and Sullivan to
December 1987 dollars using the Chemical Engineering Plant Cost Index.
2.1.1 Modular Units
2.1.1.1	Overview of Technology. Modula~r combustors are prefabricated
units which are generally used to combust unprocessed MSW. Individual
combustor units typically range in size from 5 to 150 tons per day (tpd).
Modular combustors are of two general designs, starved-air and
excess-air. In typical starved-air combustors, MSW is ram-fed into a
primary combustion chamber with a moving grate. Primary air is fed up
through the grate at substoichiometric conditions. Volatile gases released
from the heated MSW enter a secondary chamber where sufficient air and
supplemental fuel, typically natural gas or oil, are supplied to complete
combustion. Excess-air combustors provide air in excess of stoichiometric
requirements in the primary combustion chamber. Additional air and supple-
mental fuel may be added in a secondary chamber to assure complete
combustion.
Modular combustors which recover energy typically do so in waste heat
boilers following the combustion chambers. The steam produced can be sold
directly to users or used to generate electricity.
2.1.1.2	Capital Cost Procedures. The original modular combustors were
relatively simple in design and had low capital costs. As a result of
subsequent design changes, the capital costs of modular units have increased
but are still relatively low compared to other MWC technologies on a "ton per
day of MSW capacity" basis. However, thermal efficiencies are also lower,
decreasing the cost advantage for facilities when designed primarily for heat
recovery. Because of their modular design, little or no economy of scale
2
exists as a function of facility size.
As shown in Table 2.1-1, capital costs were obtained for a 50 tpd
modular facility without heat recovery and for a 100 tpd facility consisting
of two modular starved-air combustors, one waste heat boiler (17,000 Ib/hr
steam), and an optional 1.475 MW steam turbine. Costs for excess air modular
units are expected to be similar. Based on the costs presented in this
2.1-2

-------
TABLE 2.1-1. CAPITAL COSTS FOR MODULAR MWC's3
Equipment	Costs, 51,000's^
A. Without Heat Recovery
Combustors (1 @ 50 tpd)	1,125
Total0	1,125
Engineering Fees	88
Total Capital Costs	1,210
Unit Capital Costs	$24,300 per
tpd of MSW
processed
B. With Electricity Generation (Without Electricity Generation)1^
Combustors (2 @ 50 tpd)	2,250
Waste Heat Boiler (1 @ 17,000 lb/hr)	770
Turbine/Generator (1 @ 1,475 kW)	2,050 (0)
Total0	5,070 (3,020)
Engineering Fees	390 (232)
= = = s = s = = = = ^ = = = = = = = = = = = s = = s = s =	= = s = s = s = = = s = = s = = = = = = = =	=
Total Capital Costs	5,460 (3,250)
Unit Capital Costs	$54,600 ($32,500)
per tpd of
MSW processed
Reference 1, p. 128.
^December 1987 dollars.
cRepresents total direct costs (sum of the equipment and installation costs)
^Ccsts in parenthesis represent modular MWC's producing steam without
generating electricity.
2.1-3

-------
table, the following procedure can be used to estimate capital costs for
modular faci1ities:
•	Modular facilities without heat recovery ป $24,300 per tpd capacity
•	Modular facilities producing steam	- $32,500 per tpd capacity
•	Modular facilities generating electricity = $54,600 per tpd capacity
The heat recovery boiler and turbine/generator set effectively double the
cost of the faci1ity.
Because modular combustors are packaged units which require little site
preparation or extra equipment, no separate costs were included for general
facilities (foundations and building) or MSW or ash handling systems.
2.1.1.3 Operating Cost Procedures. Annual operating cost procedures
were developed from analysis of cost data provided by five plants with
modular combustors in their responses to the Section 114 questionnaire. All
operating costs except for capital recovery and waste disposal costs were
examined. The approach used in developing the operating cost procedures was
to correlate the ratio of the operating to capital costs with facility
capacity (tpd) and annual operating hours. The following best fit equation
was derived for these facilities, all of which were rated below 150 tpd and
were operating less than 6,000 hours per year:
Ratio = 10 - 0.23 tpd + 0.006 hrs	(1)
where, Ratio = percentage of operating to capital plant costs
tpd = facility waste feed rate, tons/day
hrs = annual operating hours.
For modular facilities outside these size or operating hour limits, the
following equation can be used to estimate annual operating cost based on
mass burn refractory wall facilities as discussed in Section 2.1.2.3:
Ratio - 15.7 - 0.00115 tpd	(2)
It is assumed that the ratio of operating to capital costs for modular and
mass burn refractory wall facilities are similar, since the design and
equipment arrangements of both MWC types are similar (I.e., use of waste heat
boilers for heat recovery).
2.1-4

-------
Capital recovery costs are calculated as 13.15 percent of the total
capital costs, based on a 10 percent interest rate and 15 year economic life.
Waste disposal costs are estimated by the following equation based on a
$25/ton landfill tipping fee:
100 - RED	(HRS)
WDC = $25 * (100) * TPD * (24)	(3)
where, WDC = waste disposal costs, $/yr
RED = weight reduction of MSW within the combustor, percent
TPD * facility waste feed rate, tons/day
HRS = annual operating hours.
Therefore, the total annualized costs are obtained by summing the annual
operating costs calculated from Equations 1 or 2, the capital recovery costs,
and the waste disposal costs estimated from Equation 3. All costs are
presented in December 1987 dollars.
2.1.2 Mass Burn Units
2.1.2.1 Overview of Technology. Mass burn combustors are field-erected
units used to combust unprocessed municipal solid waste. Mass burn
combustors range in unit size from 50 to 1,000 tons/day for a combustor unit
and from 50 to several thousand tons/day for a facility.
In a mass burn combustor, municipal waste is gravity- or ram-fed to a
single combustion chamber. Several different grate designs can be used to
move the waste through the. combustion chamber. Air is supplied in excess of
stoichiometric requirements through the grates (underfire air) and into the
combustion chamber above the grates (overfire air).
Either waterwall or waste heat boilers are used for recovering heat. In
units with waterwalls, boiler tubes are built into the walls of the com-
bustion chamber. Additional heat recovery sections can include superheaters,
economizers, and air preheaters. In units with waste heat boilers, the
combustion chamber is refractory lined and steam is generated downstream of
the combustion chamber.
2.1-5

-------
Electricity is generally produced on-site from steam. Some facilities
sell both electricity and steam. Because of the large quantity of steam
produced by large mass burn units, production and sale of only steam is
unlikely unless a very large industrial facility with a consistent steam
demand is nearby.
Waterwall units are typically larger (100 to 1,000 tons/day per unit)
than units with waste heat boilers (50 to 375 tons/day per unit). Most new
units are of waterwall design. No units are projected to be built without
heat recovery.
2.1.2.2	Capital Cost Procedures. As shown in Table 2.1-2, the
estimated capital cost for a mass burn facility is $60,700 per tpd capacity.
This cost is based on an 860 tpd facility consisting of two 430 tpd
combustors with 174,000 lb/hr of steam capacity and a 20 MW turbine. For the
same facility without a steam turbine, the estimated capital costs are
550,420 per tpd capacity. The capital costs for waterwall units and
refractory units with waste heat boilers are assumed to be roughly equal.
To account for the economy of scale of mass burn facilities, capital
costs reported by Frost and Sullivan were correlated with facility size to
yield the following scaling equation:3
C = 60,700 (430/size)0'39, with electrical generation (4)
0 35
C = 50,420 (430/size) ' , without electrical generation (5)
where, C = new facility capital costs in December 1987 dollars per
tpd
size = size per combustor in tpd.
Capital cost for a combustor is estimated using equations 4 or 5 to calculate
cost on a dollar per tpd basis and then multiplying this cost by plant
capacity in tons per day.
2.1.2.3	Operating Cost Procedures. Annual operating cost procedures
were developed from analysis of cost data provided by six plants (4 of which
were mass burn waterwall and 2 were RDF facilities) in their responses to the
Section 114 questionnaire. The RDF facility operating cost data were
2.1-6

-------
TABLE 2.1-2. CAPITAL COSTS FOR A 860 TON/DAY MASS BURN .
MWC WITH (WITHOUT) ELECTRICITY GENERATION3,0



Costs,
J1,000c


Equ i pment
Purchase
Cost
Inst a Ilation
Cost
Total InstaI led Cost
Uaterwall Combustors
(2 3 430 ton/day)
6,742

3,519

10,261

Refuse Cranes (2)
1,245

498

1,743

weight Scales (2)
614

302

916

Fans and Ducts (2)
1,245

368

1,613

Ash Handling System
2,933

440

3,373

Dump Condenser (1)
778

547

1,325

Stacks (2)
sao

365

1,245

Water Supply and Treatment
1,611

189

1,800

Piping System
3,127

975

4,102

Electrical
1,562

293

1,855

Instruments and Controls
2,073

195

2,268

Insulation and Paint
519

293

812

Cooling Tower (1)
3,105

440

3,545

Turbine/Generator (1 S 20 MW)
6,318
(0)
1,100
(0)
7,418
(0)
Total Capital Costs
General Facilities
32,752
(26,434)
9,524
(8,424)
42,276d
(34,858)d
F oundat ions
2,544
(2,053)
1,664
(1,472)
4,208
(3,525)
Building and Structural
1 .487
C1,200)
172
(152)
1 .659
(1,352)
Total General Facilities
4,031
(3,253)
1.836
(1,624)
5,867
(4,877)
Engineering Fees
--

4,097
(3,624)
4,097
(3,624)
Total Capital Costs
36,783
(29,687)
15,457
(13,672)
52,240
(43,359)
Unit Capital Costs




S60,700 (50,420)
per tpd of
HSW processed
Reference 1, p. 113.
bCosts in parentheses represent mass burn HUC's producing steam without generating
electr i ci ty.
cDecember 19B7 dollars.
dReoresents total direct costs (sum of equipment and installation costs).
2.1-7

-------
analyzed along with the mass burn cost data because of limited data for mass
burn plants and because both combustor types are constructed similarly
(i.e., field erected) and will likely be operated for a similar number of
hours per year. All operating costs except for capital recovery and
waste disposal costs were examined. The approach used in developing the
operating cost procedures was to correlate the ratio of the operating to
capital costs with facility capacity (tpd) and operating hours. The
following best-fit equation was derived for mass-burn waterwall facilities:
Ratio = 12.5 - 0.00115 tpd	(6)
where, Ratio = percentage of operating to capital plant costs
tpd = facility waste feed rate, tons/day.
For mass burn refractory wall facilities, no equation could be derived
due to the limited amount of cost data. However, by comparing the
Section 114 data for waterwall and refractory wall facilities, the operating
to capital cost percentages for refractory facilities were roughly 3 percent
higher than those for mass-burn waterwall facilities. Therefore, to estimate
the annual operating cost for mass-burn refractory wall facilities, the
equation for mass-burn waterwall (Equation 4) was modified to give the
following:
Ratio ซ 15.7 - 0.00115 tpd.	(7)
Equations 6 and 7 are multiplied by equation 5 to estimate annual operating
costs for mass burn waterwall and mass burn refractory wall facilities,
respectively.
Capital recovery costs for both types of mass burn facilities are
calculated as 13.15 percent of the total capital costs, based on a 10 percent
interest rate and 15 year economic life. Waste disposal costs are estimated
by equation 3 presented for modular facilities (Section 2.1.1.3). Therefore,
the total annualized costs are obtained by summing the annual operating costs
calculated from equations 6 or 7, capital recovery costs, and waste disposal
costs calculated from equation 3.
2.1-8

-------
2.1.3 RDF Units
2.1.3.1 Overview of Technology. Refuse-derived fuel MWC's are
field-erected units used to combust processed MSW. Individual RDF combustors
typically combust 180 to 1,200 tons/day of RDF. Plant sizes range from
180 to several thousand tons/day of RDF.
Refuse-derived fuel processing includes removal of noncombustible
materials and shredding of the remaining material. The two types of RDF
considered in this analysis include coarse RDF (cRDF) suitable for combusting
in a specially designed RDF combustor and fluff RDF (fRDF) suitable for
suspension firing in a utility or industrial boiler.
Coarse RDF production generally includes primary shredding and ferrous
metals recovery. The RDF material is reduced in size to 4 to 6 inches. A
weight reduction due to metals recovery of approximately 6 percent is
assumed; energy recovery is nearly 100 percent. Fluff RDF production usually
includes crushing, initial trommel screening, and magnetic separation
followed by primary shredding, air classification, and secondary shredding.
This processing removes oversized combustibles and glass as well :as
nonferrous metals and reduces the size to below 2 inches. The associated
weight reduction is approximately 20 percent of the unprocessed MSW; energy
recovery is roughly 97 percent. Production of both types of RDF includes a
dust control system to prevent fugitive emissions of fine dust generated by
RDF processing equipment.
Existing RDF combustion is based almost entirely on use of cRDF in
spreader strokers. In general with this technology, cRDF is thrown to the
rear of the furnace by a dry-swept stoker. Fine particles are burned in
suspension, and heavier materials fall to the grate and are combusted. A
traveling grate moves the materials to the front of the furnace during which
time combustion is completed. The heat from combustion is recovered using
radiant waterwall and convective heat transfer. Electricity is generally
generated on-site, especially with the larger units. Both electricity and
steam may be sold.
2.1-9

-------
TABLE 2.1-3. CAPITAL COSTS FOR A COARSE RDF FACILITY WITH ELECTRICITY
GENERATION (CAPACITY = 850 TONS/DAY MSW, 800 TONS/DAY RDF)a
Costs, $1,000'sb



Total

Purchase
Installation
Installed
Equipment
Cost
Cost
Cost
Waterwall Combustors (2 @ 400 ton/day)
5,085
2,544
7,629
Front End Loaders (9)
713

713
Primary Shredders (2)
1,016
508
1,524
Weigh Scales (2)
639
307
946
Magnetic Separation System (2)
205
68
273
Fans and Ducts (2)
993
273
1,266
Ash Handling System (2)
2,441
368
2,809
Dump Condenser (1)
916
670
1,586
Dust Control System
508
205
713
Stacks (2)
689
303
992
Water Supply and Treatment
1,985
225
2,210
Piping System
3,663
1,221
4,884
Electrical
1,657
375
2,032
Instruments and Controls
2,339
253
2,592
Insulation and Paint
539
307
846
Cooling Tower
3,586
506
4,092
Turbine/Generator (1 @ 24 MW)
7,627
1,345
8,972
Total Capital Costs
34,601
9,478
44,079C
General Facilities



Foundation
3,945
2,704
6,649
Building and Structural
3.283
388
3.671
Total General Facilities
7,228
3,092
10,320
Engineering Fees

4,512
4,512
Total Capital Costs
41,829
17,082
58,911
Unit Capital Costs


573,600

per tpd of RDF
Reference 1, p. 117;
^December 1987 dollars.
Represents total direct costs (sum of equipment and installation costs).
2.1-10

-------
Fluff RDF has been co-fired with coal in several existing utility and
4
industrial boilers. Of the total heat input, fRDF generally represents less
than 10 percent.
2.1.3.2	Capital Cost Procedures. The cost procedures developed for
RDF-fired MWC's are based on cRDF. As shown in Table 2.1-3, the estimated
capital cost for a cRDF facility is 573,600 per tpd of cRDF capacity. This
cost was based on a cRDF facility designed to process 850 tpd of MSW into
800 tpd of cRDF. The cRDF is combusted in two identical waterwall boilers to
generate 203,000 lb/hr of steam for a 24 MW turbine. The major equipment
items and associated materials and labor costs for the cRDF production/
combustion facility are presented in Table 2.1-3.
Because no data are available from Frost and Sullivan for other cRDF
facility sizes, it is assumed that the economy of scale of RDF facilities is
the same as mass-burn facilities, since both mass-burn and RDF combustors are
field-constructed. Similar indirect installation costs would be incurred for
both MWC types. Therefore, the following equation can be used to estimate
capital cost for cRDF facilities:
C = 73,600 (400/size)0,39	(8)
where, C = new cRDF facility capital costs in December 1987 dollars
per ton of RDF
size = size per combustor in tons RDF/day.
2.1.3.3	Operating Cost Procedures. Annual operating cost procedures
were developed from analysis of cost data as discussed in Section 2.1.2.3.
To estimate the annual operating costs except for capital recovery and waste
disposal costs, equation 6 presented in Section 2.1.2.3 can be used.
Capital recovery costs are calculated as 13.15 percent of the total
capital costs, based on a 10 percent interest rate and 15 year economic life.
Waste disposal costs are estimated using Equation 3 presented in
Section 2.1.1.3. It should be noted that the annual cost procedures do not
include estimates on sale of recoverable material such as metal and glass.
2.1-11

-------
2.1.4 FBC Units
2.1.4.1 Overview of Technology. F1uidized-bed combustors are
field-erected units used to combust RDF. Only three RDF-fired FBC plants are
currently operating in the U. S. Existing and currently planned FBC's are
designed to combust 195 to 500 tpd of RDF. Plant sizes range from 195 to
1,200 tpd of RDF.^ For costing purposes, it is assumed that a cRDF fuel
processing facility is included in the design of the FBC facility. Two basic
FBC designs exist: bubbling bed and circulating fluidized-bed.
In a bubbling-bed combustor, the RDF burns in a turbulent bed of heated
noncombustible material, such as limestone or sand. Typical bed temperatures
are from 1,450 to 1,700ฐF. As with conventional combustors, primary combus-
tion air is introduced underneath the bed, but at a flowrate high enough to
suspend or "fluidize" the solid particles in the bed. Secondary combustion
air is introduced through ports in the upper part of the combustor to complete
the combustion process. If good mixing between air and combustible waste is
achieved, the amount of excess air required for complete combustion is
similar to conventional RDF combustors. In addition, by adding limestone to
the bed, SO^ and HC1 can be removed from the flue gas to reduce acid gas
emissions. Bed material entrained in the flue gas is typically removed by a
cyclone in series with a fabric filter (FF) or an electrostatic precipitator
(ESP).
Circulating fluidized-bed combustors are similar to bubbling-bed
combustors except that the superficial velocities within the bed are 3 to
5 times higher than in bubbling-bed combustors. As a result, a physically
well-defined bed is not formed; instead, solid particles are entrained with
the transport air/combustion gases. Most of the solids are captured by a
cyclone, and are continuously recirculated into the combustor. The solids
still in the flue gas are captured by a downstream FF or an ESP.
Available information on the capital and operating costs of FBC's are
insufficient to distinguish bubbling versus circulating bed designs.
Therefore, a single set of cost procedures has been developed.
2.1-12

-------
2.1.4.2	Capital Cost Procedures. Table 2.1-4 presents the capital cost
procedure for FBC's. All costs are estimated in December 1987 dollars. The
procedures do not include the costs for FF's or ESP's. The costs for ESP's
and FF's can be estimated using procedures discussed in Sections 2.2 and 2.3
of this report, respectively.
The direct and indirect cost equation shown in Table 2.1-4 is based on a
vendor cost estimate for two combustors each rated at 450 tpd (i.e., total
Q
plant capacity of 900 tpd). The vendor cost estimate included: combustor
vessel, natural gas preheat system, forced draft and induced draft fans,
tramp removal system, boiler, fuel and limestone storage and metering,
multiclone, instrumentation and control including a boiler management system,
ductwork, freight, and engineering and start-up supervision. However, the
cost estimate provided by the vendor did not include cRDF processing and
other equipment associated with the combustors such as front-end loaders,
primary shredders, weight scales, magnetic separators, stacks, cooling tower,
water treatment and supply, and steam turbine. Because the other equipment
would be the same for both cRDF and FBC facilities, costs for the balance of
plant in Table 2.1-3 (adjusted by size to 900 tpd using the 0.6 power cost
rule) were added to the vendor cost estimates to estimate the total direct
g
cost. Indirect costs for general facilities and engineering fees were based
on percentages of the direct cost estimated by Table 2.1-3.
To estimate the direct and indirect capital cost for other plant, sizes,
it is assumed that the economy of scale of FBC facilities is the same as for
mass-burn and RDF facilities (0.39). Similar indirect installation costs
would be incurred for these boiler types. A 20-percent process contingency
is added to account for the relatively limited application of FBC to MWC's.^
2.1.4.3	Operating Cost Procedures. Table 2.1-5 presents the operating
cost bases for FBC's. Table 2.1-6 presents operating cost equations derived
from Table 2.1-5. The FBC operating procedures are divided into two process
areas: combustor and the balance of plant, and cRDF processing. The direct
operating cost bases for the combustor and balance of plant were based on
information provided by one vendor for labor, electrical consumption, and
water requirements. The maintenance materials costs were determined from
cost data for coal-fired industrial FBC's.^ Lime costs are based on the
2.1-13

-------
TABLE 2.1-4. PROCEDURE FOR ESTIMATING CAPITAL COSTS FOR NEW FBC'S
(December 1987 dollars)
Total Direct and Indirect Costs:3
Costs, 103$ = 64,900 * TPD * (900/TPD)0*39
Process Contingency: 20% of total direct and indirect costs
Total Capital FBC Costs: Total direct and indirect costs + process
contingency
aTPD = plant municipal waste feed rate, tons/day.
2.1-14

-------
TABLE 2.1-5. ANNUAL OPERATING COST PROCEDURES FOR NEW FBC'S
References
Combustors and Balance of Plant
(except coarse RDF processing area)
Operating Labor:
Supervision:
Maintenance Labor:
10 man-years/year, 40 hours/week,
and $ 12/hr for a 900 tpd plant
3 man-years/year, 40 hours/week,
and 30% premium over operating
wage for a 900 tpd plant
3 man-years/year, 40 hours/week,
and 10% premium over operating
wage for a 900 tpd plant
Maintenance Materials: 3% of the total capital costs
Electricity:
Limestone:
Water:
Waste Di sposal:
Overhead:
Taxes, Insurance, and
Administrative:
Capital Recovery of
FBC Facility:
3 MW power consumption for a
900-tpd plant and electricity
costs of S0.046/kwh
$40/ton
3% blowdown rate calculated
from steam production and
$0.50/1,000 gal for water
$25/ton tipping fee and 99%
combustible material in RDF
and spent sorbent collected
60% of the sum of all labor
costs (operating, supervisory,
and maintenance) plus 60% of
the maintenance materials costs
4% of the sum of the total capital
costs
15 year life and 10% interest
rate
6, 12
6, 13
6, 14
11
6
15
6, 16
6, 17
18
18
19
Continued
2.1-15

-------
TABLE 2.1-5 (CONCLUDED). ANNUAL OPERATING COST PROCEDURES FOR NEW FBC'S
References
Coarse RDF Processing Area
Total Operating and
Maintenance:
Taxes, Insurance, and
Administrative:
Capital Recovery of
FBC Facility:
4.4% of the total direct and
indirect capital costs * ratio
of operating to capital costs
from Equation 6 in Section 2.1.2
4% of the sum of the total capital
costs
15 year life and 10% interest
rate
1
18
19
2.1-16

-------
TABLE 2.1-6. PROCEDURE FOR ESTIMATING ANNUAL OPERATING COSTS FOR FBC'S
(December 1987 dollars)
Combustor and Balance of Plant (excludes coarse RDF processing area):
Operating labor (based on 10 man-years. 40 hours/week. S12/hr):
OL = 10 * 40 * 52 * 12 * (TPD/900) = 277.3 * TPD
Supervision (based on 3 man-vears/vear, 40 hours/week. 30% wage rate
premium over the operating labor wage):
SPRV = 3 * 40 * 52 * 12 * 1.3 * (TPD/900) - 108.2 * TPD
Maintenance labor (based on 3 man-vears/vear. 40 hours/week. 10% wage
rate premium over the operating labor wage):
ML - 3 * 40 * 52 * 12 * 1.1 * (TPD/900) = 91.5 * TPD
Maintenance materials: 3% of the total capital costs
m
Electricity (based on 3 MW power consumption, and electricity rate of
S0.046/kwhl:
ELEC - 0.153 * TPD * HRS
Limestone (based on S40/ton for limestone):
LIMESTONE = 0.02 * LFEED * HRS * N
Water (based on 3% blowdown rate and $0.05/1.000 gal):
WC - 1.86 x 10~6 * STM * HRS
Waste disposal (based on tipping fee of $25/hr):
AD - 1.25 x 10"2 * N * HRS * WDR
Overhead: 60% of the sum of all labor costs (operating, supervisory,
and maintenance) plus 60% of maintenance materials costs
Taxes. Insurance, and Administrative Charges:
4% of the total capital cost
Capital Recovery (based on 15 year life and 10% interest rate):
13.15% of the total capital cost
Continued
2.1-17

-------
TABLE 2.1-6 (CONCLUDED). PROCEDURE FOR ESTIMATING ANNUAL OPERATING COSTS
FOR FBC'S (December 1987 dollars)
Coarse RDF Processing Area:
Total Operating and Maintenance Costs (TOT O&M):
TOT O&M = 4.4 x 10"4 * (12.5 - 0.00115 * TPD) * TDI
Taxes. Insurance, and Administrative Charges:
4% of the total capital cost
Capital Recovery (based on 15 year life and 10% interest rate):
13.15% of the total capital cost
OL = operating labor costs, $/yr
SPRV - supervision costs, S/yr
ML = maintenance labor costs, $/yr
ELEC = electricity costs, $/yr
HRS - hours of operation per year
LIMESTONE ซ limestone costs, $/yr
LFEED = limestone feed rate per unit, lb/hr
N * number of combustors
VJC = water costs, $/yr
STM = plant steam production, lb/hr
AD * waste disposal costs, $/yr
WDR = waste disposal rate per unit (bottom and fly ash collected), lb/hr
TPD = plant municipal waste feed rate, tons/day
TDI = total direct and indirect capital costs for FBC plant, $
2.1-18

-------
amount of limestone injected at a cost of $40/ton. This cost is based on a
limestone freight-on-board cost of J20/ton and a transportation cost of
S20/ton, assuming a handling rate of $0.04/ton-mile hauling distance and a
500-mile hauling distance. The cost for waste disposal is determined from
the amount of solids removed by the FBC plus additional fly ash collected by
the downstream particulate control device.
All cost rates are based on December 1987 dollars. The operating labor
wage is the average from those wages in the Department of Commerce Survey of
Current Business for private nonagricultural payrolls and EPRI's Technical
20 21
Assessment Guide. ' Electricity rates are from the Energy Information
22
Administration, Monthly Energy Review.
The annual operating cost procedures for RDF processing facilities in
Section 2.1.3.3 were used to estimate the annual operating costs for the
cRDF processing area. Operating costs for the cRDF processing area are
estimated to be 4.4 percent of the product of total FBC capital cost and the
ratio of operating-to-capital costs for RDF facilities from Equation 6 in
Section 2.1.2.3.
2.1-19

-------
REFERENCES
1.	Frost and Sullivan, Incorporated. As cited in Waste-Energy Boom Seen
Through Century. Coal and Synfuel Technology. March 17, 1986. 259 p.
2.	U. S. Environmental Protection Agency. Small Modular Incinerator
Systems with Heat Recovery: A Technical Environmental, and Economic
Evaluation-Executive Summary. Cincinnati, OH. Publication
No. EPA/SW-797. 1979. p. 5.
3.	Reference 1. p. 105.
4.	Energy and Environmental Research Corporation. Refuse Derived Fuel
Co-firing Technology Assessment. Prepared for the U. S. Environmental
Protection Agency. Research Triangle Park, NC. September 1988.
5.	Energy and Environmental Research Corporation. F1u i d i zed - Bed Combustor
Technology Assessment. Prepared for the U. S. Environmental Protection
Agency. Research Triangle Park, NC. September 1988. pp. 2-13 to 2-24.
6.	Letter from Hansen, J. L., Energy Products of Idaho, to Martinez, J. A.,
Radian Corporation. December 1, 1988. Costs for bubbling fluidized-bed
combustors applied to MWC's.
7.	Letter from Ferm, B., Gotaverken Energy Systems, to Johnston, M. G.,
EPA. March 17, 1989. Costs for circulating fluidized-bed combustors
applied to MWC's. 9 p.
8.	Reference 6.
9.	Garrett, D. E., Chemical Engineering Economics. New York, Van Nostrand
Reinhold. 1989. p. 37.
10.	Electric Power Research Institute. TAG™ - Technical Assessment Guide
(Volume 1: Electricity Supply - 1986). Palo Alto, CA. EPRI Report
No. P-4463-SR. December 1986. p. 3-3.
11.	Young, C. W., et al. (GCA). Technical Assessment Report for Industrial
Boiler Applications: Fluidized-bed Combustion. Prepared for the
U. S. Environmental Protection Agency. Publication No. EPA-600/7-79-178e.
November 1979. pp. 517-553.
12.	Reference 10, p. B-4.
13.	Neveril, R. B. (GARD, Inc.). Capital and Operating Costs of Selected
Air Pollutant Control Systems. Prepared for the U. S. Environmental
Protection Agency. Research Triangle Park, NC. Publication
No. EPA-450/5-80-002. December 1978. p. 3-12.
2.1-20

-------
14.	Devitt, T., P. Spaite, and L. Gibbs (PEDCo Environmental). Population
and Characteristics of Industrial/Commercial Boilers in the U.S.
Prepared for the U. S. Environmental Protection Agency. Research
Triangle Park, NC. Publication No. EPA-600/7-79-178a. August 1979.
462 p.
15.	Jordan, R. J. The Feasibility of Wet Scrubbing for Treating
Waste-to-Energy Flue Gas. Journal of Air Pollution Control Association
(New York). 37:422-430. April 1987.
16.	Letter from Solt, J. C., Solar Turbines Incorporated, to Noble, E., EPA.
October 19, 1984. Development cost for wet control for stationary gas
turbines.
17.	U. S. Environmental Agency. EAB Control Cost Manual. Research Triangle
Park, NC. Publication No. EPA-450/5-87-001 a. February 1987. p. 2-29.
18.	Reference 17, p. 2-31.
19.	Bowen, M. L. and M. S. Jennings (Radian Corporation). Cost of Sulfur
Dioxide, Particulate Matter, and Nitrogen Oxide Controls in Fossil Fuel
Fired Boilers. Prepared for the U. S. Environmental Protection Agency.
Research Triangle Park, NC. Publication No. EPA-450/3-82-021.
August 1982. pp. 2-17 and 2-18.
20.	United States Department of Commerce. Survey of Current Business.
Washington, DC. Volume 68. Number 6. June 1988. p. S-12.
21.	Electric Power Research Institute. TAG'" Technical Assessment Guide
(Volume 1: Electricity Supply - 1986). Palo Alto, CA. Publication
No. EPRI P-4463-5R. December 1986. p. B-4.
22.	Energy Information Administration. Monthly Energy Review:
December 1987. Washington, D.C. Publication No. DOE/EIA-0035 (87/12).
March 1988. p. 109.
2.1-21

-------
2.2 ELECTROSTATIC PRECIPITATORS
2.2.1	Overview of Technology
Electrostatic precipitators are used to control PM emissions from MWC's.
In this process, flue gas flows between a series of high voltage discharge
electrodes and grounded metal plates. Negatively charged ions formed by this
high voltage field attach to particulate in the flue gas, causing the charged
particles to migrate toward the grounded plates. Charged particles that
collect on the grounded plates are periodically removed by rapping or
washing. Key ESP design and operating characteristics influencing ESP
performance are particulate size and resistivity, specific collection area
(SCA, equal to the total surface area of the collection plates divided by the
flue gas flow rate), and the number of ESP fields. When the plates are
cleaned, some of the collected particulate is reentrained in the flue gas.
To ensure good particulate collection efficiency during plate cleaning and
electrical upsets, ESP's have several fields located in series along the
direction of flue gas flow that can be energized and cleaned independently.
Particles reentrained when the dust layer is removed from one field can be
recollected in a downstream field.
2.2.2	Capital Cost Procedures
2.2.2.1 Direct costs. Information on direct equipment costs is
available for ESP's at three PM control levels (0.01, 0.02, and 0.03 gr/dscf
at 12 percent CO,) for mass-burn, modular, and RDF facilities ranging in size
from 100 to 3,000 tpd total plant capacity. These cost estimates, based on
data provided by eight manufacturers, are presented in Table 2.2-1.
The equipment cost data were correlated with total plate area.
Figure 2.2-1 illustrates the "best fit" equation for the data from all of the
ESP vendors except for one. The data from manufacturer "D" in Table 2.2-1 at
a flue gas flowrate of 245,230 acfm were not included in the analysis because
the cost data varied significantly from the rest of the data (refer to the
three solid data points in Figure 2.2-1). Data from manufacturers F and G in
Table 2.2-1 were excluded in Figure 2.2-1, because flue gas flowrates for the
large mass-burn units were not reported. The resultant "best fit" equation
using this approach is:
2.2-1

-------
TABLE 2.2-1. VENDOR QUOTES FOR ESP EQUIPMENT COSTS
(IN lOOOS AUGUST 1986)3

Furnace
Flue gas
f1owrates,
Outlet
PM emissions.
ar/dscf
Vendor
type3
acfm
0.03
0.02
0.01
A
MOD
54,105
240
250
310
A
MOD
86,568
280
290
390
B
MOD
86,568
325
325
325
C
MB
24,523
253
423
440
D
MB
24,523
410
450
570
E
MB
76,000
NAb
640
NA
C
MB
NA
503
828
980
D
MB
NA
1,470
1,640
2,310
F
MB
245,230
1,313
NA
1,750
G
MB
240,000
NA
1,813
2,188
B
MB
190,031
475
475
545
H
MB
126,687
567
576
617
H
RDF
130,843
580
645
781
A
RDF
130,843
780
880
890
H
RDF
196,264
768
832
977
A
RDF
196,264
910
970
980
aMOD = modular; MB- mass-burn, and RDF = refuse-derived fuel.
^NA = not available.
2.2-2

-------
w
OO
I—
OO
o
o
2.4
2.2 -
2 -
1.8
1.6
1.4
1.2 -
1 -
0.8
0.6 H
0.4
0.2 H
tP
Q
o Hp	p
Figure 2.
~ ~
~ ~
~
		ma
~ n Costs (10J$) = 270.1 * 0.00653 * TPA
_i | ! |	| i	i	r i i i	1	
40	60	80	100	120	140	160
TOTAL PLATE AREA, 1000 ft2
Correlation of ESP equipment costs (in August
1986 dollars) from ESP manufacturers and
total plate area.

-------
Purchase equipment cost, 103 $ = 305.2 + 0.00738 * TPA, in (1)
December 1987 dollars
2
where: TPA is the total plate area in ft calculated as the
2
product of the SCA in ft /1000 acfm and the flue gas
flowrate in 1000 acfm.
The flue gas flowrate is assumed to be 125 percent of the design
flowrate to accommodate variations in feed waste composition and operating
2
conditions. Equation 1 was derived using the Chemical Engineering Plant
Index to update the cost equation shown in Figure 2.2-1 to December 1987
dollars and including the cost for taxes and freight. Taxes and freight were
estimated at 8 percent of the equipment cost.3
To estimate the required SCA for new units, the following approach was
taken. Data on SCA's were provided by eight manufacturers, as shown in
4
Table 2.2-2. From this table, the average SCA was calculated for each PM
removal efficiency, as shown in Table 2.2-3. The average SCA's from
Table 2.2-3 were correlated with PM collection efficiency using the
Deutsch-Anderson equation. The Deutsch-Anderson equation is frequently used
to predict ESP performance.^ Using the form of the Deutsch-Anderson
equation, the following equation is derived:
PM collection efficiency, % = 100 - 101.89 * exp(-0.0112 * SCA) or
SCA = -(89.29) * In [(100 - PM collection efficiency, %)/101.89] (2)
2
where SCA = specific collection area, ft /1000 acfm
Figure 2.2-2 presents the "best fit" equation for the average SCA data.
Both equations (Equations 1 and 2) reasonably fit the data. The
2
coefficients of determination (R ) were 0.86 for Equation 1 and 0.97 for
Equation 2. Part of the scatter not explained by Equation 1 may be due to
differences in equipment included in different vendor estimates.
Equations 1 and 2 apply to field-erected ESP's with total plate areas
2
above 6,500 ft and flue gas flowrates above 30,000 acfm. ESP's applied to
2.2-4

-------
TABLE 2.2-2. SPECIFIC COLLECTION AREA (SCA) REPORTED BY THE ESP MANUFACTURERS
Flue Gas	Inlet PM
Flowrate,	Loading,	SCA. ft /1000 acfm. for outlet loading of
Manufacturer	acfm	gr/dscf	0.03	0.02	0.01
A
54,015
0.11
121
182.8
235.3
A
86,568
0.11
142
184.4
239.3
B
86,568
0.11
150
150
150
C
24,523
1.72
285.5
346.7
423.7
D
24,523
1.72
332.1
419.6
675.9
E
76,000
NA
NA
NA
NA
C
245,230
1.72
286
352.2
444.9
D
245,230
1.72
335.7
405.6
634
F
NAa
1.72
325
375
450
G
NA
1.72
360
400
500
B
190,031
1.72
258
258
314
1
NA
1.72
400
500
NA
H
126,687
1.72
345
NA
392
H
130,843
4.63
408.6
NA
544.8
A
130,843
4.63
462.6b
480.8
573b
H
196,264
4.63
404.5
NA
561.3
A
192,264
4.63
463b
527.9
595.1b
aNA - not available.
bThese values were not used to estimate averages SCA values reported in Table 2.2-3.

-------
TABLE 2.2-3. AVERAGE SPECIFIC COLLECTION AREA (SCA) CALCULATED
FROM THE MANUFACTURERS' DATA
Inlet PM
Loading,
gr/dscf at 12% CO2
Outlet PM
Loadi ng,
gr/dscf at 12% C0ฃ
PM Removal
Efficiency,
Precent
ft2/1000'acfm
0.11
0.03

72.7
138
(3)a
0.11
0.02

81.8
172
(3)
0.11
0.01

90.9
208
(3)
1.72
0.03

98.3
332
(9)
1.72
0.02

98.8
397
(8)
1.72
0.01

99.4
500
(B)
4.63
0.03

99.4
406
(2)
4.63
0.02

99.6
504
(2)
4.63
0.01

99.8
553
(2)
^Number in parantheses indicates the number of data points used for the average.
2.2-6

-------
100
98
96
94
92
90
88
86
84
82
80
78
76
74
72


PH reaoval. J-100-101.89 exp(-0.0112 SCA)
10
T
300
1—
500
SCA. Fr/1000 *cfm
Figure 2.2-2. Relationship between ESP manufacturers' specific collection area
and particulate natter reaoval.

-------
smaller modular combustor facilities generally are shop-assembled and are
installed at the facility at a minimal cost. To estimate the costs of this
type of ESP, cost data from one manufacturer were analyzed using the same
approach as for field-erected ESP's.^ The "best fit" equation relating
purchase equipment costs to total plate area (TPA) is:
3
Purchase equipment costs, 10 S = 96.3 + 0.015 * TPA,
in December 1987 dollars (3)
R2 = 0.86
Figure 2.2-3 presents the "best fit" equation for the data from this
manufacturer. Costs received from another ESP manufacturer after Equation 3
was developed are similar to those used to develop Equation 3.^
To estimate the required SCA, the SCA calculated from the manufacturer
cost data was correlated with PM collection efficiency using the
Deutsch-Anderson equation:
PM collection efficiency, % = 100 - 79.6 * exp (-0.0035 * SCA) or
SCA = -(285.7) * 1 n[(100-PM collection efficiency, %)/79.6] (4)
R2 = 0.90
Figure 2.2-4 presents the "best fit" equation for the SCA data.
Table 2.2-4 summarizes the procedure for estimating total capital cost
for ESP's using the above four equations. The SCA required to achieve a
given PM collection efficiency is estimated using either equation 2 or 4.
Purchased equipment costs for the ESP can then be obtained using either
Equation 1 or 3. For the costs of additional ESP units, the costs of a
single ESP are multiplied by the number of required units. Procedures for
estimating the costs of ductwork and fan, and installation direct costs are
O
also presented in Table 2.4-4.
2.2.2.2 Indirect and Other Costs. The cost factors for estimating
indirect costs for field-erected ESP's are based on those presented in
9 10
established EPA cost procedures. ' Because installation and engineering
2.2-8

-------
290
280
270
260
250
240
230
220
210
200
190
160
170
160
150
140
130
D
~
~r
2
T
~r
4
T
(Thousands)
Total Plate Area, SQ.FT.
~r
6
I
8
U
Figure 2.2-3. Correlation of ESP purchase equipment costs with total plate
area for modular ESP's.

-------
100
90
80
u
ป-
ซ
o.
. 70
m
>
i
u
S
60
50
40
300
500
700
900
100
SCA, Ft2/1000 acfm
Figure 2.2-4. Relationship between specific collection area and particulate
matter removal for modular ESP's.

-------
TABLE 2.2-4. COST PROCEDURES FOR ESTIMATING CAPITAL COSTS
FOR ESP'S ON NEW PLANTS3
Purchased Equipment Costs (December 1987 dollars):
Single Field-erected ESP unitb: Costs, 103$ - 305.2 + 0.00738 * TPA
TPA - SCA * Q/1000
PM efficiency % = 100-101.89 exp (-0.0112 * SCA)
Single Shop-assembled ESP unitb,C: Costs, 103 - 96.3 + 0.015 * TPA
PM efficiency % = 100-79.6 exp (-0.0035 * SCA)
Multiple Units: Costs = N * Costs for single ESP unit
Ductwork:	Costs - 0.7964 * L * Q0,5
Fan:	Costs = 1.077 * Q0'96
Installation Direct Costs = 67% of equipment costs .
Indirect Costs = 54% of Purchase Equipment Costs for field-erected ESP's
= 514,000 for shop-assembled ESP's
Contingency = 3% of the Purchase Equipment Costs
Total Capital Investment = Purchased Equipment Costs + Installation Direct
Costs + Indirect Costs + Contingency
TPA ป total plate area, ft	~
SCA = specific collection area, ft /1000 acfm
Q = 125 percent of the calculated flue gas flowrate, acfm
L = Duct length, ft
N - Number of ESP units
includes taxes and freight of 8 percent of the ESP equipment costs.
cApplies only to modular combustors whose flue gas flowrate Q is less than
30,000 acfm.
2.2-11

-------
costs are less for a shop-assembled ESP than for a field-erected ESP,
indirect costs for shop-assembled ESP's are based on the manufacturer's
estimate of $14,000.^ Costs reported in August 1986 dollars were updated to
December 1987 dollars using the Chemical Engineering Plant Cost Index for all
equipment.
2.2.3 Operating Cost Procedures
Table 2.2-5 presents the procedure for estimating annual operating costs
for ESP's. The procedures and factors shown for estimating the various
components of annual operating costs and the references for each are listed
in Table 2.2-5. Operating costs are presented in December 1987 dollars.
To the extent that data are available, cost rates are based on actual
rates in December 1987 dollars. Operating labor wage rate is the average
from those obtained from the U. S. Department of Commerce, in its Survey of
Current Business for private non-agricultural payrolls and the EPRI's
12 13
Technical Assessment Guide. ' Electricity rates were obtained from the
14
Energy Information Administration, in its Monthly Energy Review. An ash
disposal cost rate of S25/ton was used, since typical ash disposal rates
(tipping fees) are between S20 and $30/ton.^
2.2-12

-------
TABLE 2.2-5. COST PROCEDURES USED TO ESTIMATE ANNUAL OPERATING
COSTS FOR ESP'S ON NEW UNITS
Operating Labor:
Supervi si on:
Maintenance:
Labor
Materials
Electricity:
Ash Di sposal:
Overhead:
Taxes, Insurance,
and Administrative
Charges:
Capital Recovery:
I man-hour/shift
15% of operator labor costs
0.5 man-hour/shift,
10% wage rate premium
over operating labor wage
1% of the total capital costs
2
1.5 watts/ft collection area
0.5 inch pressure drop W.C.
$25/ton
60% of the sum of all labor costs
(operating, supervisory, and
maintenance) and 60% of the
maintenance material.
4% of total capital costs
15 year life and 10% interest
rate
References
16
17
17, 18
17
19
20
21
22
22
15
aLabor requirement in the range reported by Reference 16 (from 1/2 to 2 man-
hour/shi ft).
2.2-13

-------
REFERENCES
1.	U.S. Environmental Protection Agency. Municipal Waste Combustion Study:
Costs of Flue Gas Cleaning Technologies. Research Triangle Park, NC.
Publication No. EPA/530-SW-87-021e. June 1987. 121 p.
2.	Letter from Sedman, C.B., EPA, to Chang, J. Acurex Corporation.
July 14, 1986. EPA guidelines for costing flue gas cleaning
technologies for municipal waste combustion.
3.	Turner, J.H., et al. Sizing and Costing of Electrostatic Precipitators,
Part II: Costing Considerations. Air Pollution Control Association
(New York). 38:715 - 726. Hay 1988.
4.	Reference 1.
5.	Radian Corporation. Background Information Document for Nonfossil Fuel
Fired Boilers. Prepared for the U.S. Environmental Protection Agency.
Research Triangle Park, NC. Publication No. EPA 450/3-82-007.
March 1982. p. 4-31.
6.	Letter and attachments from Martinez, J.A., Radian Corporation, to
Graham, G., PPC Industries. June 20, 1988. Costs for electrostatic
precipitators applied to small modular combustors.
7.	Letter and attachments from Childress, J., United McG111 Corporation, to
Martinez, J.A., Radian Corporation. July 28, 1988. Costs for
electrostatic precipitators applied to small modular combustors.
8.	Reference 3.
9.	Reference 3.
10.	U.S. Environmental Protection Agency. EAB Control Cost Manual.
Research Triangle Park, NC. Publication No. EPA 450/5-87-001A.
February 1987. p. 2-6.
11.	Reference 6.
12.	Electric Power Research Institute. TAG"' - Technical Assessment Guide
(Volume 1: Electricity Supply - 1986). Palo Alto, CA. Publication
No. EPRI P-4463-SR. December 1986. p. B-4.
13.	United States Department of Commerce. Survey of Current Business.
Washington, D.C. Volume 68. Number 6. June 1988. p. S-12.
14.	Energy Information Administration. Monthly Energy Review:
December 1987. Washington, D.C. Publication No. DOE/EIA-0035 (87/12).
March 1988. p. 109.
2.2-14

-------
]5. Reference 17, p. 3-16.
16.	Vatavuk, W. M., and R. B. Neveril, "Estimating Costs of Air Pollution
Control Systems, Part II: Factors for Estimating Capital and Operating
Costs," Chemical Engineering. November 3, 1980. pp. 157-162.
17.	Neveril, R. B., (GARD, Inc). Capital and Operating Costs of Selected
Air Pollution Control Systems. Prepared for U.S. Environmental
Protection Agency. Research Triangle Park, NC. Publication No. EPA
450/5-80-002. December 1978. p. 3-12.
18.	Reference 17,	p.	3-14.
19.	Reference 17,	p.	3-18.
20.	Reference 17,	p.	5-2.
21.	Reference 10,	p.	2-29.
22.	Reference 10,	p.	2-31.
2.2-15

-------
2.3 DRY SORBENT INJECTION
2.3.1 Overview of Technology
Dry sorbent injection is being examined as a control option for achieving
moderate acid gas control and indirectly increasing dioxin control for MWC's.
Two basic variations of this technology exist:
•	furnace sorbent injection in which alkali sorbent is injected
through the overfire air ports into the furnace, and
•	duct sorbent injection in which the sorbent is injected into either
a duct or a reactor vessel upstream of the particulate control
system.
Particulate control following sorbent injection can be accomplished by either
an ESP or fabric filter.
Sorbent injection technologies have been used commercially on MWC's in
Europe and Japan since 1979.1 Japanese duct injection technology generally
uses a high-temperature (approximately 500ฐF) ESP ฃor particulate matter
collection. European duct injection technology incorporates a fabric filter
(FF) for particulate control with typical FF inlet temperatures of 350ฐF.
Furnace and duct sorbent injection systems have recently been installed and
tested at several MWC's in the U. S. In addition, significant testing of
furnace and duct injection applied to coal-fired systems for SOg control has
occurred. However, data on the comparative performance and the cost of
different sorbent injection approaches for MWC's are limited.
The basic chemistry for acid gas control is the reaction of calcium or
sodium sorbent with HC1 and SO^ to form chloride, sulfite, and sulfate salts.
The degree of acid gas control is a function of sorbent feed rate, the
extent of flue gas and sorbent mixing, the flue gas temperature, and the PM
control device. For moderate levels of acid gas control, sorbent can be
injected directly into the furnace or the flue gas duct. For higher levels of
control, a separate reactor vessel can be used that is designed to enhance
flue gas and sorbent mixing and provide additional reaction time. Flue gas
hunidification with water sprays or additional heat recovery in an economizer
or air preheater can be used to reduce flue gas temperature. Procedures for
estimating the costs of flue gas temperature reduction using humidification
are presented in Section 3.5.
2.3-1

-------
Based on similarities in equipment requirements, the capital costs for
furnace and duct injection are expected to be generally similar. As a result,
a "generic" cost procedure was developed to estimate the capital and operating
costs for both types of sorbent injection. Major equipment associated with
both technologies consists of a storage silo, a pneumatic feeding system for
transferring sorbent from the storage silo to feed bins, feed bins with
2
gravimetric metering systems, and pneumatic sorbent injectors. For duct
sorbent injection, a venturi or a reaction vessel with mixing baffles is
provided to ensure adequate gas-to-sorbent mixing. For furnace sorbent
injection, sorbent will be injected through the overfire air ports or separate
injection ports in the combustor. For new systems, a FF is assumed for PM
control because of its enhanced acid gas and dioxin removal capabilities
compared to an ESP.
Primary operating costs include labor, maintenance materials,
electricity, and sorbent. Labor, maintenance material, and electricity cost
are expected to be generally similar for both duct and furnace sorbent
injection. Because of the greater amount of data on calcium-based sorbents,
the cost procedures assume use of hydrated lime (Ca(OH)2)• For furnace
injection, limestone (CaCO^) or lime (CaO) can be used which may be less
expensive.
2.3.2 Capital Cost Procedures
The direct capital cost of sorbent injection equipment depends on the
flue gas and sorbent flowrates. These two parameters, in turn, depend on MSW
feed rate and composition, excess air levels, flue gas temperature, sorbent
quality and utilization rate, and emission control requirements. Based on a
simple material balance that assumes all of the sulfur and chlorine in the MSW
are converted to S02 and HC1, sorbent throughput requirements can be
calculated using the following equation:
Llm(lb/hr)Rate " 74-] * (2,000/24) * TPD * [%S/32 + XC1/71] * CAG/PURITY
where:
TPD = tons per day of MSW, based on 125 percent of the design capacity
to accommodate variations in feed waste composition and
operating conditions ,
2.3-2

-------
%S ป percent sulfur in the MSW,
%C1 = percent chlorine in the MSW,
CAG = calcium-to-acid gas molar ratio (i.e., stoichiometric
ratio), and
PURITY = weight percent of calcium in the lime.
Based on available data for duct sorbent injection, a value of 2 for CAG is
expected to achieve removal efficiencies of 80 percent for HC1 and 40 percent
4
for S09. For furnace sorbent injection, a CAG value of 2 is expected to
'	5
achieve 70 percent removal of HCl and 70 percent removal of SC^. PURITY is
assumed to be 90 percent.
Procedures for calculating direct capital costs for the individual major
equipment items shown in Table 2.3-1 were derived from data in standard cost
6 7 8
estimating manuals and manufacturer estimates. ' ' Cost for a reactor vessel
is based on a vaned, stainless steel tank with one second of flue gas
q
residence time. Installation costs are assumed to be 30 percent of the
equipment costs.^ Indirect costs, also shown in Table 2.3-1, are calculated
as a percentage of total direct costs. These indirect cost rates are the same
as those used for estimating the indirect capital costs of a spray
dryer/FF (presented in Section 2.4-1). The equations in Table 2.3-1 estimate
costs in December 1987 dollars. The costs were escalated to December 1987
dollars using the Chemical Engineering Plant Cost Index for all equipment.
Capital costs for pulse jet FF's with a net air-to-cloth ratio
of 4:1 are estimated using equations for single units.^ Direct and indirect
capital costs as a function of flue gas flowrate can be estimated from these
equations. Installation and indirect costs for FF's are 72 and 42 percent of
12
the equipment cost, respectively. The flue gas flowrate is based on
125 percent of the design flowrate to accommodate variations in feed waste
composition and operating conditions. The costs for FF and auxiliary
equipment are in December 1987 dollars. Contingency is included to account
for unforeseen costs (50 percent of the direct and indirect cost) during
installation and start-up due to the relative lack of operating experience of
dry sorbent injection systems applied to MWC's.^ Projected equipment life is
15 years.
2.3-3

-------
TABLE 2.3-1. PROCEDURES FOR ESTIMATING CAPITAL COSTS FOR DRY SORBENT INJECTION
Purchased Equipment Costs. 103 $
1.	Lime Storage Silo with Vibrator. Baghouse. and Flow Control Value (Based on 15-dav lime supply)
o For storage volumes (V) less than or equal to 2,300 ft' (one storage silo per plant).
Costs = 1.05 * (34.2 ~ 0.016V) * RF
o For storage volumes between 2,300 and 4,600 ft' (two storage silos per plant),
Costs = 2.10 * (34.2 + 0.016V) * RF
o For storage volume greater than 4,600 ft' (two storage silos per plant).
Costs = 2.10 * (63 .+ 0.0038V) * RF
2.	Feed Bins
o For duct sorbent injection (one feed bin per combustor),
Costs = 0.0906 * N * RF * (Sf)ฐ"6U5
o For furnace sorbent injection (two feed bins per combustor),
Costs = 0.1812 * N * RF * (SF)ฐ"6U5
3.	Gravimetric Feeders
o For duct sorbent injection (one feeder per combustor).
Costs = 1.024 * (0.000289 SF + 9.293) * N * RF
o For furnace sorbent injection (two feeders per combustor).
Costs = 2.048 * (0.000289 SF ~ 9.293) * N * RF
4.	Pneumatic Conveyor (Based on 400 Feet Length)
Costs = 1.05 * (26.4 + 0.0073 SF + 0.4 * [12.8 ~ 11.23 SF023]) N * RF
5.	Injection Ports
For duct sorbent injection (one injection port per combustor).
Costs = 1.05 * (22.2 + 0.0014 SF) * N * RF
o For furnace sorbent injection (two injection ports per combustor).
Costs = 2.10 * (22.2 ~ 0.0014 SF) * N * RF

-------
TABLE 2.3-1. (Continued)
6.	Reactor Vessel (optional for duct sorbent injection to increase flue gas and sorbent contact): Costs = 34 * (0 * 1.25/6,150)"'^
ฃ
7.	Fabric Filter
Costs = 0.1482 ซ N * RF * Q0.7043
8. Induced Draft Fan
Costs = (1.167 * N * RF * 0ฐ'96)/1,000
9. Ductwork
Costs = (0.8627 * N * RF * L * 0ฐ"5)/1,000
Installation Direct Costs
= 30% of dry sorbent injection equipment costs ~ 72% of fabric filter and auxiliary equipment costs
Indirect Costs
= 33% of direct costs (equipment ~ installation costs) for dry sorbent injection ~
42% of equipment cost for the fabric filter and auxiliary equipment
Co
ฆ
cn
Cont i ngencv
= 50X of the sum of direct and indirect costs
Total Capital Costs
= Total Direct Costs ~ Indirect Costs ~ Contingency Costs
8All costs are estimated in December 1987 dollars.
bSF = lime feed rate per unit, Ib/hr
Q = 125 percent of the actual flue gas flowrat^ to the fabric filter per unit, acfm
V = lime storage silo volume for the plant, ft
N = number of units
RF = Retrofit factor. For retrofit applications, use retrofit factor of 1.1 for sorbent injection equipment. Retrofit factors for fabric
filter and auxiliary equipment are obtained from Table A-14. For neu units, RF = 1.0.
I = duct length, feet
cFabric filters are used for new applications and for retrofit applications where no ESP exists. For plants with existing ESP's, costs for
upgrading the ESP are estimated from Table B-4.

-------
2.3.3 Operating Cost Procedures
Table 2.3-2 presents procedures for estimating operating costs for dry
sorbent injection alone. Operating costs for humidification are presented in
Section 3.5. The operating and maintenance labor requirements and maintenance
materials for sorbent injection are based on typical values for coal-fired
boilers. Electricity costs are based on electrical requirements to operate
the pneumatic feed systems. Lime costs are based on the amount of lime
injected. Equations for electricity and lime were taken from Reference 10.
Table 2.3-3 presents procedures for estimating operating costs for FF's.
The operating and maintenance labor requirements are based on those from
established EPA procedures, with the exception of maintenance materials.
Because maintenance material requirements for FF's can vary directly with the
size of the unit, maintenance material costs are assumed to be calculated at
five percent of the direct capital costs. This percentage is the same one
used for dry sorbent injection to estimate maintenance material costs. The
cost of bag replacement assumes a 2-year bag life, which is typical for FF's.
A gross air-to-cloth ratio of 3:1 is used.
Electricity to operate the I.D. fan is calculated using a total pressure
drop of 12.5 inches of water, 7 inches of water across the FF and 5.5 inches
for the additional ductwork and dry sorbent injection. The cost of compressed
air for the pulse jet FF's is estimated from established EPA procedures. The
costs for solids disposal are determined from the amount of solids collected
by the FF and a tipping fee of $25/ton.
All cost rates are based on December 1987 dollars. The operating labor
wage is the average from those obtained from the Department of Commerce Survey
of Current Business for private nonagricultural payrolls and EPRI's Technical
Assessment Guide.Electricity rates will be obtained from the Energy
Information Administration, Monthly Energy Review.^ Operating hours per year
can be varied to meet model plant specifications.
Indirect operating costs such as taxes, insurance, and administrative
charges are based on percentages of the capital costs. Payroll and plant
overhead are based on a percentage of the labor and material costs.
2.3-6

-------
TABLE 2.3-2. ANNUAL OPERATING COST PROCEDURES FOR
DRY SORBENT INJECTION FOR NEW MWC's11


References
Operating Labor:
2 manhour/shift
14
Supervision:
15% of operator labor costs
18
Maintenance Labor:
0.5 manhour/shi ft, 107. premium
over operating labor wage
18, 19
Materials:
5% of total direct costs
20, 21
Electricity:
(52.56 * (lime feed rate3) + 251,850) *
(electricity costs) * (hours of
operation/8,760)
22
L i me :
4.38 * (lime feed rate3) * (lime cost) *
(hours of operation/8,760)
22
Overhead:
60% of the sum of all labor costs
(operating, supervisory, and
maintenance) plus maintenance material
23
Taxes, Insurance,
and Administrative
Charges:
4% of total capital costs
23
aLime feed rate in lb/hr is based on 100 percent capacity of waste processed.
2.3-7

-------
TABLE 2.3-3. ANNUAL OPERATING COST PROCEDURES
FOR FABRIC FILTERS FOR NEW MWC's
Operating Labor:
Supervi sion:
Maintenance Labor:
Materi als:
Bag Replacement:
Electricity:
Compressed Air:
Sol id Waste:
Overhead:
Taxes, Insurance,
and Administrative
Charges:
Capital Recovery:
2 manhour/shift
15% of operator labor costs
1	manhour/shift, 10% wage rate premium
over operating labor wage
5% of direct capital costs
$ 1.35/ft^ for teflon coated fiberglass;
2-year 1i fe
Calculated based on fan requirements
for inches of water pressure drop
across FF
2	scfm/1,000 acfm flue gas
Apply appropriate tipping fee in S/ton
(Assume $25/ton)
50% of the sum of all labor costs
(operating, supervisory, and
maintenance) plus materials
4% of total capital costs
15-year life and 10% interest rate
References
24
24
18, 24
20
25
26
27
28
23
23
29
2.3-8

-------
REFERENCES
]. Radian Corporation. Municipal Waste Combustors - Background Information
for Proposed Standards: Post-Combustion Technology Performance.
EPA-450/3-89- 27 c. August 1989.
2.	Reference 1.
3.	Letter from Sedman, C.B., EPA, to Chang, J., Acurex Corporation.
July 14, 1986. EPA guidelines for costing flue gas cleaning technology
for municipal waste combustion.
4.	Reference 1.
5. Reference 1.
6.	Callaspy, D.T. Dry Sorbent Emission Control Prototype Conceptual Design
and Cost Study. Presented at the First Joint Symposium on Dry SO- and
Simultaneous SO^/NO^ Control Technologies. November 1984.
7.	Process Plant Construction Estimating Standards. The Richardson Rapid
System. Volume 4. 1982. p. 100-45.
8.	Stearns Catalytic Corporation. Economic Evaluation of Dry-Injection Flue
Gas Desulfurization Technology. Prepared for Electric Power Research
Institute. Palo Alto, CA. EPRI No. CS-4343. January 1986. Appendix A.
9.	Garrett, D.E. Chemical Engineering Economics. Van Nostrand Reinhold,
New York. 1989. p. 298.
10.	Radian Corporation. Industrial Boiler Furnace Sorbent Injection
Algorithm Developed. Prepared for U. S. Environmental Protection Agency.
Research Triangle Park, NC. Contract No. 68-02-3994. May 1986. p. 10.
11.	U. S. Environmental Protection Agency. Municipal Waste Combustion Study:
Costs of Flue Gas Cleaning Technologies. Research Triangle Park, NC.
Publication No. EPA/530-SW-87-021e. June 1987. p. 3-6.
12.	Reference 10, pp. 9 and 10.
13.	Electric Power Research Institute. TAG"-Technical Assessment Guide
fVolume I: Electricity Supplv-1986). Palo Alto, CA. Publication No.
EPRI P-4463-SR. December 1986. p. 3-3.
14.	U. S. Environmental Protection Agency. EAB Control Cost Manual.
Research Triangle Park, NC. Publication No. EPA-450/5-87-001A. February
1987. p. 5-42.
15.	Reference 13, p. B-4.
2.3-9

-------
16.	United States Department of Commerce. Survey of Current Business.
Washington, D.C. Volume 68. Number 6. June 1988. p. S-12.
17.	Energy Information Administration. Monthly Energy Review:
December 1987. Washington, D.C. Publication No. D0E/EIA-0035 (87/12).
March 1988. p. 109.
18.	Reference 10, p. 12.
19.	Neveril, R.B., (GARD Inc.). Capital and Operating Costs of Selected Air
Pollution Control Systems. Prepared for U. S. Environmental Protection
Agency. Research Triangle Park, NC. Publication No. EPA 450/5-80-002.
December 1978. p. 3-12.
20.	Reference 10, p. 11.
21.	Reference 8, p. 1-9.
22.	Kaplan, N. et al. Control Cost Modeling for Sensitivity and Economic
Comparison. Proceedings from the 1986 Joint Symposium on Dry SO- and
Simultaneous SC^/NO Control Technologies, EPRI CS-4966, Volume z.
23.
Reference
14,
p. 2-31.
24.
Reference
10,
p. 2-31.
25.
Reference
14,
p. 5-39 and
26.
Reference
20.

27.
Reference
14,
p. 5-45.
28.
Reference
14,
p. 2-29.
29.
Reference
19,
p. 3-16.
2.3-10

-------
2.4 SPRAY DRYING WITH EFFICIENT PARTICULATE CONTROL
2.4.1	Overview of Technology
Spray drying is designed to control SC^ and HC1 emissions. When used in
combination with an efficient particulate control system, spray drying can
also control CDD/CDF, PM, and metals emissions. In the spray drying process,
lime slurry is injected into a spray dryer (SD) vessel. The water in the
slurry evaporates to cool the flue gas, and the lime reacts with acid gases to
form salts that can be removed by a PM control device. The simultaneous
evaporation and reaction increases the moisture and particulate content in the
flue gas. The particulate exiting the SD vessel contains fly ash plus calcium
salts, water, and unreacted lime.
Spray drying is commonly used in combination with either a fabric
filter (FF) or an electrostatic precipitator (ESP) for PM control. Both
combinations have been used for MWC's in the United States, although SD/FF
systems are more common and may be more effective for CDD/CDF, PM, and metals
control. Two basic designs of FF's are available:" reverse air and
pulse jet. In a reverse air FF, flue gas flows through unsupported filter
bags, leaving the particulate on the inside of the bags. The particulate
builds up to form a particulate filter cake. Once an excessive pressure drop
across the filter cake is reached, air is blown through the filter in the
opposite direction, the filter bag collapses, and the filter cake falls off
and is collected. In a pulse jet FF, flue gas flows through supported filter
bags leaving particulate on the outside of the bags. To remove the built-up
particulate filter cake, compressed air is introduced through the inside of
the filter bag, the filter bag expands and the filter cake falls off and is
collected. The cost procedures are based on pulse jet FF systems.
2.4.2	Capital Cost Procedures
Vendor capital cost estimates for SD systems combined with either an ESP
or a FF applied to three types of MWC's (mass-burn, modular, and RDF) were
obtained for systems designed to achieve 90 percent HC1 and 70 percent SO,
^ i
removal and PM emissions of 0.01, 0.02, and 0.03 gr/dscf at 12 percent CO^.
A cost comparison of SD/FF and SD/ESP systems designed to achieve a PM
emission rate of 0.01 gr/dscf at 12 percent COj is presented in Appendix A for
2.4-1

-------
two mass-burn facility capacity sizes (250 and 3,000 tons/day of MSW). This
comparison indicates that, at this PM control level, costs for SD/FF and
SD/ESP systems are very similar, with the annualized costs for SD/FF's being
slightly lower than for SD/ESP's. Although cost procedures presented in this
section focus on SD/FF systems, they are representative of costs for SD/ESP
systems.
Cost procedures for stand-alone SD systems (i.e., without a FF) are
presented in Section 3.6. These procedures were developed based on the SD/FF
data plus supplemental cost quotes from three SD manufacturers. These cost
procedures are intended to assist in evaluating methods to retrofit SD systems
at existing plants already equipped with efficient PM control devices.
2.4.2.1 Direct Costs. Direct costs for an SD/FF system include
purchased equipment cost for an SD, FF, induced draft (1.0.) fan, and ducting.
The SD components include a reaction vessel, atomizer, lime feed preparation
equipment, and solids handling equipment. The SD is sized based on a
stoichiometric ratio (moles of calcium per mole of both SC^ and HCl in the
flue gas entering the spray dryer) of 1.5:1. The FF cost 1s based on a
pulse-jet type unit operated at a net air-to-cloth ratio of 4:1 and a gross
air-to-cloth ratio of 3:1.
Costs for single SD/FF units were based on cost data provided by two
manufacturers as shown in Table 2.4-1. The data from these two manufacturers
were used to estimate installed capital costs of SD/FF systems for all furnace
2
types and are plotted as a function of flue gas flowrate in Figure 2.4-1.
The costs are approximately the same for any combustor type at the same
flowrate. There are two reasons for this. First, the cost of the FF is
assumed to be sensitive only to flue gas flowrate and is unaffected by PM
grain loading. Second, the inlet SO^ and HCl concentrations in the flue gas
were assumed to be essentially the same for all facility types. Inlet SO2 and
HCl concentrations primarily depend on the MSW composition (particularly
sulfur and chlorine contents) and MSW heating value. The values for these
three factors assumed for the three facility types result in approximately the
same S02 and HCl concentrations.
2.4-2

-------
TABLE 2.4-1. VENDOR QUOTES FOR SPRAY DRYER/FABRIC FILTER TOTAL
CAPITAL COSTS (IN $1,000 AUGUST 1986)a
Flue gas
Furnace flowrates, Outlet PM emissions, ar/dscf at 12% CO^c
Vendor type	acfm	0.030.02	"O.ol
c
MB
24,523
1,712
1,712
1,762
c
MB
245,230
5,262
5,262
5,624
G
MB
245,230
6,000
6,000
6,000
installed capital costs reported are the purchase costs for one unit
multiplied by a 1.6 adjustment factor. Auxiliary equipment costs are not
i ncluded.
^MB = mass-burn.
c0utlet grain loading from fabric filters.
tmg.017
secti on.2-4
2.4-3

-------
100
i
8'
tt
I
10
Oulto Loading:
0.01 grttacf
	ฉ—
0.09grMocf
O.UgrMocf
y*MA| - Mc r
Figure 2.4-1. Capital cost estimates of an SD/FF for a model MB facility, and
RDF facility.2
2.4-4

-------
Table 2.4-2 summarizes the capital cost procedures for single SD/FF
units. These procedures are based on achieving a PM control level of
0.01 gr/dscf at 12 percent CO^-^ The equation was developed from
Figure 2.4-1.
From Table 2.4-2, the total direct costs can be estimated for single
units by knowing the inlet flue gas flowrate and the length of ductwork
needed. The flue gas flowrate is based on 125 percent of the design flowrate
to accommodate variations in feed waste composition and operating conditions.
To estimate the costs of multiple units, the direct costs of a single SD/FF
unit including auxiliary equipment are multiplied by the number of units.
2.4.2.2 Indirect and Other Costs. To be consistent with established EPA
methodology, the equations were adjusted to distinguish direct costs (i.e.,
purchased equipment and installation costs) from indirect capital costs (i.e.,
engineering costs, construction and field expenses, contractor fees, start-up
and performance test costs). To separate these costs, indirect costs are
assumed to be 33 percent of the direct capital costs.^ Contingency is assumed
to be similar to that applied to fossil-fuel fired boilers.^ Interest during
construction and working capital is not included for air pollution control
devices.^ Costs are reported in December 1987 dollars. The Chemical
Enqineerinq Plant Cost Index for all equipment was used to escalate costs from
August 1986 dollars.
2.4.3 Operating Cost Procedures
Table 2.4-3 presents the procedure for estimating operating costs. In
general, the references in this table have been used in previous EPA cost
analyses.
The operating and maintenance labor requirements for SD/FF are based on
those used in fossil fuel industrial boiler cost analyses and assume that
operating and maintenance labor costs bases would be essentially the same for
coal-fired industrial boilers and MWC facilities. However, the maintenance
material cost for SD/FF systems applied to MWC facilities is usually lower
than the cost for systems at coal-fired boiler facilities, since uncontrolled
S02 emissions are much higher from coal-fired boilers. Because SO^
concentrations are lower at MWC facilities, less concentrated slurries can be
2.4-5

-------
TABLE 2.4-2. CAPITAL COST PROCEDURES FOR SD/FF FOR NEW MWC'S3
Total Direct Costs (December 1987 dollars)
Single SD/FF Unitb: Costs, 103 S = 8.053 (Q)0,517
Ductworkb: Costs, 103 S = [1.3868 * L * Qฐ*5]/l,000
Fanb: Costs, 103 S = [1.8754 * Q0,96]/1,000
Multiple Units: Multiply the above costs by the number of units
Indirect Costs - 33% of total direct costs
Contingency = 20% of sum of direct and indirect costs
Total Capital Costs = Total Direct Costs + Indirect Costs + Contingency Costs
aQ * 125 percent of the actual flue gas flowrate, acfm
L - Duct length, feet
^Assumes that the total installed costs are 133 percent of the direct capital
costs.
2.4-6

-------
TABLE 2.4-3. ANNUAL OPERATING COSTS PROCEDURES FOR
SPRAY DRYER/FABRIC FILTER FOR NEW MWC's3
Reference
Operating Labor: 4 manhours/shift; $12/manhour	8, 9
Supervision: 15% of operating labor costs	10
Maintenance:
Labor: 2 manhours/shift; 10% wage rate premium	9
over operating labor wage
Materials: 2% of direct capital costs	11
Bag Replacement:
p
Bags: $ 1.35/ft for teflon-coated fiberglass;	12
2-year life for SD/FF;
Bag replacement cost not included for SD only
Electricity: Cost Rate = $0.046/kwh
Fan: 12.5 inches of water pressure drop	13, 14
Atomizer: 6kW/l,000 lbs/hr of slurry feed + 15kW	15
Pump: 20 feet of pumping height	16
10 psi discharge pressure
10 ft/sec velocity in pipe
Compressed Air: 2 scfm air/1,000 acfm flue gas;	17
$0.11/1,000 scfm of air
Water: Calculate water flowrate required for cooling the flue
gas to 300 F; water cost = $0.50/1000 gal
18
Lime: Based on lime feed rate calculated for a given	19
stoichiometric ratio; lime cost = $70/ton
Solid Waste: Calculate solid waste collected by the spray	20
dryer and fabric filter using PES program and
apply appropriate ash disposal fee in $/ton;
Assume $25/ton
(continued)
2.4-7

-------
TABLE 2.4-3. (Continued)

Reference
Overhead: 60% of the sum of all labor costs (operating,
supervisory, and maintenance) plus materials
21
Taxes, Insurance, and
Administrative Charges: 4% of total capital costs
21
Capital Recovery: 15-year life and 10% interest rate
22
aAll costs are in December 1987 dollars.
2.4-8

-------
used to achieve the same removal efficiency, which in turn result in less
erosion of equipment and potential for plugging. Therefore, the maintenance
23
material cost was estimated at 2 percent of the direct capital cost.
Estimating the material cost at 2 percent of the direct capital cost
corresponds to 1.25 percent of the total capital costs.
The costs of bag replacement assumes a 2-year bag life, which is a
24
typical bag-life for FF's. A gross air-to-cloth ratio of 3:1 is used.
Electricity costs include electricity consumed by the I.D. fan, atomizer, and
slurry pumps. Electricity consumed by the I.D. fan is calculated using a
pressure drop of 12.5 inches of water across the SD/FF. Atomizer electrical
25
requirements are based on the amount of slurry feed. Slurry pumping
requirements are estimated from assumed pumping height, discharge pressure,
26
and fluid velocity in pipe used in previous cost analysis. The costs for
compressed air for pulse-jet FF's are estimated from the air usage rate of 2
27
scfm/1,000 acfm of flue gas. The stoichiometric ratio (moles of calcium per
mole of SOj and HCl in the inlet flue gas) assumea is 2.5 to achieve 90
percent SOg and 97 percent HCl removals.
All cost rates are based on December 1987 dollars. The operating labor
wage rate used is the average from those in the Department of Commerce, Survey
of Current Business for private nonagricultural payrolls and EPRI's Technical
28 29
Assessment Guide. ' Electricity rates are from the Energy Information
Administration, Monthly Energy Review.^ The freight-on-board (FOB) costs for
quick lime (calcium oxide, CaO), $45/ton bulk, are from the Chemical Marketing
31
Reporter; an additional cost of $25/ton is assumed for transportation, based
on a hauling rate of $0.05/ton-mile and a 500-mile hauling distance. For
estimating ash disposal costs, a tipping fee of $25/ton is used. For new
plants, the operating costs will be based on the assumption of 8,000 hours of
operation per year; however, operating costs can be calculated for any number
of operating hours.
2.4-9

-------
REFERENCES
1.	U. S. Environmental Protection Agency. Municipal Waste Combustion
Study: Costs of Flue Gas Cleaning Technologies, Research Triangle
Park, NC. Publication No. EPA/530-SW-87-021e. June 1987. 121 pp.
2.	Reference 1, p. 4-10.
3.	Reference 1.
4.	Letter from Sedman, C.B., EPA, to Chang, J., Acurex Corporation.
July 14, 1986. EPA guidelines for costing flue gas cleaning technology
for municipal waste combustion.
5.	Bowen, M.L. and M.S. Jennings. (Radian Corporation.) Cost of Sulfur
Dioxide, Particulate Matter, and Nitrogen Oxide Controls in Fossil Fuel
Fired Industrial Boilers. Prepared for the U. S. Environmental
Protection Agency. Research Triangle Park, NC. Publication No.
EPA-450/3-82-021. August 1982. p. 2-11.
6.	Reference 4.
7.	U. S. Environmental Protection Agency. EAB Control Cost Manual.
Research Triangle Park, NC. Publication No. EPA-450/5-87-001A.
February 1987. p. 2-6.
8.	Memorandum from Aul, E.F., et al., Radian Corporation, to Sedman, C.B.,
EPA. May 16, 1983. 36 pp. Revised Cost Algorithms for Lime Spray
Drying and Dual Alkali FGD Systems.
9.	Neveril, R.B. (GARD, Inc). Capital and Operating Costs of Selected Air
Pollution Control Systems. Prepared for the U. S. Environmental
Protection Agency. Research Triangle Park, NC. Publication
No. EPA-450/5-80-002. p. 3-12.
10.	Reference 7, p. 5-43.
11.	Electric Power Research Institute. TAG"*-Technical Assessment Guide
(Volume 1: Electricity Supply-1986). Palo Alto, CA. Publication
No. EPRI P-4463-SR. December 1986. p. 3-10.
12.	Reference 7, p. 5-39 and 5-43.
13.	Reference 7, p. 5-45.
14.	Letter and attachment from Fiesinger, T., New York State, Energy Research
and Development Authority, to Johnston, M., EPA. January 27, 1987.
Draft report on the economics of various pollution control alternatives
for refuse-to-energy plants, p. 6-9.
15.	Reference 1, p. 4-23.
2.4-10

-------
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
Dickerman, J.C. and K.L. Johnson. (Radian Corporation.) Technology
Assessment Report for Industrial Boiler Applications: Flue Gas
Desulfurization. Prepared for the U.S. Environmental Protection
Agency. Washington, DC. Publication No. EPA-600/7-79-178i.
November 1979. pp. 5-5 and 5-17.
Reference 7, pp. 5-46 and 5-52.
Letter from Solt, J.C., Solar Turbines Incorporated, to Noble, E., EPA.
October 19, 1984. Development cost for wet control for stationary gas
turbines.
Chemical Marketing Reporter. Volume 233. Number 1. January 4, 1988.
Reference 7, p. 2-29.
Reference 7, p. 2-31.
Reference 5, pp. 2-17 and 2-18.
Reference 17.
Reference 12.
Reference 1.
Reference 18.
Reference 19.
Reference 11, p. B-4.
United States Department of Commerce. Survey of Current Business.
Washington, D.C. Volume 68. Number 6. June 1988. p. S-12.
Energy Information Administration. Monthly Energy Review:
December 1987. Washington, D.C. Publication No. D0E/EIA-0035 (87/12),
March 1988. p. 109.
Reference 21.
2.4-11

-------
2.5 COMPLIANCE MONITORING
Continuous emission monitoring (CEM) systems are used to determine
compliance with emission limits for MWC facilities. The following sections
describe monitoring systems for opacity, SO2, HC1, 0^ and CO^. Section 3.1
discusses the types of combustion control monitors required for good
combustion practices.
2.5.1 Overview of Technology
2.5.1.1	Continuous Opacity Monitoring*. Stack opacity can be
continuously measured using emission measurement systems based on the
principle of transmissometry. Transmissometry measures the attenuation of
visible light by particulate matter in stack effluent. Light from a lamp
source is projected across the stack to a light sensor. The degree of
attenuation (opacity) reflects the amount of light adsorbed and scattered by
the particulate matter in the effluent.
The EPA regulations (Appendix B of 40 CFR Part 60) require the opacity
monitoring system to operate for a minimum of 168 hours within certain
performance specifications without unscheduled maintenance, repair, or
adjustment. The regulations set forth minimum performance criteria for the
following system parameters: calibration error (<3 percent), 24 hour zero
drift (<2 percent), 24 hour calibration drift (<2 percent), and response time
(10 seconds maximum). During or before installation, it is necessary to
calibrate, zero, and span using calibration filters and to perform all
alignments.
To validate accuracy, as required in 60.13(d), instruments automatically
perform simulated zero and span calibration checks at selectable intervals
(usually daily). It is also usually necessary to have an air purge system to
prevent accumulation of particulate from condensing on the optical surfaces.
Maintenance is typically required on an as-needed basis (usually weekly).
This involves cleaning all filters, checking the optical alignment and the air
purge system, and recalibrating the instrument.
2
2.5.1.2	Continuous SO^ Monitoring . Continuous monitoring of SOj
emissions is typically accomplished by irradiating a given volume of sample
air by ultraviolet (UV) or infrared (IR) light and measuring either the
2.5-1

-------
energy absorbed or the resulting fluorescence of the SO2 molecules.
Commercially available units differ in design and method, but in general it is
necessary to: (]) collimate the light from the original source to provide a
narrow band; (2) prepare the sample for analysis; and (3) increase the
signal-to-noise ratio of the final signal via phase-sensitive detection,
second derivative spectroscopic measurement, or other techniques.
All SO^ monitoring systems required under NSPS must have complete zero
and span calibration checks performed daily. If not, a weekly manual check is
recommended. About every month, it is necessary to clean, service, and
readjust the instrument. The actual maintenance schedule needed depends on
the instrument and the site of application. Instruments utilizing filters,
chillers, sample dryers, or support gases typically require more maintenance.
Continuous monitoring systems must be installed at sampling locations
where representative measurements can be made of the total emissions from the
affected facility, or can be corrected so as to be representative. The SC>2
monitoring system must be capable of operating for a 168-hour minimum within
certain performance specifications without unscheduled maintenance, repairs or
adjustments. The regulations (Appendix B of 40 CFR Part 60) set forth minimum
performance criteria for the following system parameters: accuracy
(<20 percent) and 24-hour calibration drift (2.5 percent of span). The
calibration drift is determined using calibration gases (i.e., gases of known
concentrations), gas cells, or optical filters. The relative accuracy is
determined by measuring pollution concentrations with EPA reference methods
while concurrently operating the continuous monitoring system.
2.5.1.3 Continuous HC1 Monitoring. The EPA has not published
performance specifications for HC1 monitors, but is currently evaluating the
reliability, accuracy, and reproducibility of various monitoring systems. The
outcome of this evaluation will determine which monitoring systems will serve
as the basis for any ensuing EPA performance specifications for continuous HC1
monitors.
In brief, four types of extractive monitors are being evaluated and are
available commercially. The first type is a wet chemical batch process.^ A
sample of the flue gas passes through an automatic bubbler system, and the
HCl-laden liquor is sprayed against a specific ion electrode. The second type
2.5-2

-------
4
is a nondispersive infrared (NDIR) analyzer. This instrument determines the
HC1 concentration of the sample flue gas by ratioing the peak heights of the
flue gas and reference gas. Both types of monitors are certified for CEM
applications in West Germany.
5
The third type uses a tape sampler. A sample of gas is exposed to a
chemically impregnated tape. The HC1 in the flue gas reacts with the
chemical on the tape leaving the tape stained. The instrument determines the
HC1 concentration by measuring the reduction in transmissivity of the tape.
The last type of monitoring system is based on continuous spectrophotometry.^
A sample of flue gas is contacted with a thiocyanate reagent stream in a
column. The reagent leaving the column, which contains adsorbed HC1, is fed
to the spectrophotometer to obtain an HC1 signal. These two types are not
certified for CEM applications in West Germany.
2.5.1.4 Diluent (Op/CO,, Monitoring).^ Diluent monitors are an integral
part of an SO^ or HC1 continuous monitoring system. Diluent concentrations
(Og or CC>2 on a percent basis) are required to convert actual concentrations
of SO2 or HC1 to concentrations at either 7 percent or 12 percent
Continuous monitoring of 0^ is based on the paramagnetic properties of
O2 molecules and their response to nonhomogeneous magnetic fields or by oxide
cell differential voltages. Monitoring CC^ is accomplished through infrared
absorption methods.
2.5.2 Compliance Monitoring Costs
Table 2.5-1 summarizes the continuous monitoring costs associated with PM
only, acid gas only, and PM and acid gas controls combined. Except for HC1
and operating costs for SOj and monitors, the monitoring costs are the same
as those used by EPA in developing NSPS for both small and industrial steam
0
generation units. Costs for HC1 monitors and operating costs for a combined
8 9
SO2/O2 monitor are based on recent information. '
The capital costs were updated to December 1987 dollars using the
Chemical Engineering Plant Cost Index for all equipment, while the operating
costs were updated to the same time bases using the Bureau of Labor
Statistics' Producer Price Index for all Industrial commodities. An automatic
data reduction system is included in all options shown in Table 2.5-1.
2.5-3

-------
TABLE 2.5-1. CONTINUOUS MONITORING COST SUMMARY
(December 1987 Dollars) '
Pollutant	Method
Capi tal
Costs
($1,000)
Operating
Costs .
($1,000/yr)
Annuali zed
Costs
($1,000/yr)
61
8
16
67
10
19
140
74
92
19
15
18
31
4
8
256
103
137
61
8
16
67
10
19
140
74
92
19
_IS
18
286
107
145
PM	Opacity3
Acid Gas	SO, (inlet and outlet)
HCt (inlet and outlet)
0,/CO-
Data Reduction System
Total
PM + Acid Gas Opacity3
S0? (inlet and outlet)
HCt (inlet and outlet)
02^2	
Total
3Includes costs for automatic data reduction system.
^Based on 2 certifications/year and maintenance requirements of 0.5 man-hour/
day for opacity and 0-/C0- monitors and I man-hour/day for SO- and HC1
monitors.
Annualized costs include annual operating costs and capital charges on
equipment and installation costs. Capital charges are based on a 15-year
equipment life at 10 percent interest rate.
2.5-4

-------
REFERENCES
1.	Radian Corporation. Industrial Boiler NSPS Issue Papers' Issue Paper
No. 7 Compliance Monitoring Costs. Prepared for the U.S. Environmental
Protection Agency. Research Triangle Park, N.C. September 1980.
pp. A3 and A-4.
2.	Reference 1. pp. A-l and A-2.
3.	Letter and attachments from Rigo, H.G., Rigo and Rigo Associates,
Incorporated, to Russo, G.P., Connecticut Resources Recovery Authority.
November 18, 1986. p. 1. Draft position papers on technical questions
concerning Connecticut waste-to-energy projects.
4.	Reference 3.
5.	Reference 3. p. 2.
6.	Reference 5.
7.	Reference 1. pp. A-3 and A-4.
8.	Kiser, J.V., "More on Continuous Emissions Monitoring", Waste Age.
June 1988. p. 124.
9.	Memorandum from Peeler, J., Entropy Environmentalists, Inc., to Riley,
G., EPA. June 1, 1988. Review of Draft MWC Compliance Monitoring
Document.
10.	Radian Corporation. Industrial Boiler SCL Cost Report. Prepared for the
U.S. Environmental Protection Agency. Research Triangle Park, N.C.
Publication No. EPA-450/3-85-013. November 1984. p. 2-23.
11.	Reference 1. p. 3.
2.5-5

-------
3.0 PROCEDURES FOR EXISTING PLANTS
This section presents procedures for estimating costs for existing
municipal waste combustion (MWC) plants. Most procedures presented in this
section rely on those procedures discussed for new plants. However,
additional procedures are developed which are unique to existing plants such
as costs for combustion modifications to the combustors, flue gas cooling
using humidification, and downtime associated with either the installation of
the air pollution control device (APCD) or modifications to the combustor.
This section also provides a methodology to assess the higher costs of
installing APCD's at existing plants, compared to new plants, using retrofit
factors.
Section 3.1 presents procedures for estimating costs for operating the
existing combustor. Procedures for estimating costs of combustion
modifications are presented in Section 3.2. Section 3.3 provides the
procedure for estimating costs for flue gas temperature control using
humidification. Sections 3.4, 3.5, and 3.6 discuss estimation of costs for
particulate matter control, dry sorbent injection, and spray drying,
respectively. Section 3.7 present the methodology to determine retrofit
factors and additional site-specific costs. Downtime costs associated with
the installation of an APCD or modifications to the combustor at an existing
plant are discussed in Section 3.8.
3.1 OPERATION OF THE EXISTING COMBUSTORS
No capital costs are estimated for the combustors and other equipment
associated with the balance of plant, because these costs are sunk and are
independent of the costs for retrofitting additional APCD's. Therefore, only
the operating costs of the combustors and the balance of the plant are
considered. Operating costs procedures for new combustors and the balance of
plant are presented in Section 2.1 and are assumed to be the same for existing
plants. For existing plants, capital recovery costs are not included in the
total operating costs.
3.1-1

-------
3.2 COMBUSTOR MODIFICATIONS
3.2.1	Introduction
This section describes the methodology and assumptions used to estimate
capital and annual costs associated with combustor modifications needed to
1 2
ensure good combustion for MWC's. ' The organization of this chapter is as
fol1ows:
•	Section 3.2.2 discusses the approach used to estimate capital costs
for each of the combustion modifications, including all assumptions.
An example calculation is provided for each retrofit.
•	Section 3.2.3 provides a methodology for estimating annual costs for
MWC plants.
The Chemical Engineering Plant Cost Indices are used to convert costs to
December 1987 dollars.
3.2.2	Capital Cost Procedures
Capital cost estimates were calculated for each retrofit component and
expressed as a direct, installed cost, unless otherwise noted. When
uninstalled equipment costs are provided, an installation factor is applied:
Direct Capital Cost (DCC) = 1.45(Equipment Cost)
The installation factor applies to delivered equipment in a solids processing
pi ant. ^
Capital costs that may vary based on unit size must be scaled using
factors. For example, the cost of a modification, C, at a unit of a given
size is scaled for a unit of different size by the following equation:
Cj - C2 (TPDj/TPD^"
where:
Cj = scaled capital cost of equipment at unit #1;
C^ - capital cost of equipment at unit #2;
3.2-1

-------
TPDj = capacity (tons per day) of unit #1; and
TPD2 = capacity (tons per day) of unit #2.
The exponent n varies according to the retrofit application. It is assumed
that the volumetric heat release (Btu/ft^-hr) is constant for similar
combustor types (i.e., mass-burn waterwall, RDF-fired, etc.). Therefore, for a
given design, unit firing capacity (tons per day) scales directly with furnace
volume. Consequently, a change in a given design feature will vary as the
cube root of each resulting change in dimension modifications, and the
exponent is 0.667. In the case of retrofitting a row of overfire air nozzles,
where a one-dimensional change is required (along the width of the combustor),
the exponent is 0.333. Perry's Chemical Engineers' Handbook also applies
4
typical exponents for various pieces of equipment. The exponent values
range from 0.30 to 1.00 depending on the specific equipment. As noted in
Perry's Chemical Engineer's Handbook, use of exponents to estimate costs
results in a slightly higher probable error (10 to 50 percent) than study
estimates (up to 30 percent).
Indirect capital costs (ICC) and contingencies must be applied to the
direct capital costs (DCC) estimates.^ Indirect capital costs, which include
general facilities and engineering and home office costs, etc., are calculated
as 30 percent of DCC:
ICC - 0.30(DCC).
A single contingency is applied to the DCC:
Contingency - 0.20(DCC).
The 20 percent contingency factor is applied in all cases except when a
retrofit is judged to be especially difficult, such as with stoker (grate)
3.2-2

-------
replacement; a contingency factor of 30 percent is used in this case. The
total plant capital cost (TPC) is calculated as follows:
TPC = DCC + ICC + Contingency.
The following subsections describe the costing methodology for specific
retrofit elements, including:
•	Stoker rehabilitation,
•	Refractory-wall furnace reconfiguration,
•	Fuel feeding modifications,
•	Underfire air modifications,
•	Overfire air modifications,
•	Monitoring/control modifications,
•	Auxiliary fuel burner installation, and
•	Economizer installations for flue gas temperature reduction.
3.2.2.1 Stoker Rehabilitation
This modification includes demolition and replacement of existing stoker,
drives, siftings hopper, siftings conveyor, and structural steel. It is also
assumed that a new stoker is equipped with a ram feeder.
•	Chesner reports direct capital costs for stoker rehabilitation for
four 250-tpd units to be $4,160,000 (in December 1984 dollars) based
on quotes from two stoker equipment suppliers.
•	Assume single unit cost for 250-tpd unit is $1,040,000.
•	Apply CEP index:
12/84 - 324.3
12/87 - 332.5
Unit Cost - 1,040,000 (332.5/324.3) = $1,066,000.
•	Apply scaling factor and account for number of units:
DCC = 1,066,000 (TPD/250),677(number of units).
3.2-3

-------
•	Example: Estimate the direct capital cost of replacing traveling
grates with new reciprocating grates in two 375-tpd units:
DCC = 1,066,000 (375/250) 677 (2) = $2,797,000.
3.2.2.2	Refractorv-Wal1 Furnace Reconfiguration
This modification includes material and labor for reconstructing the
combustion chambers and refractory-lined flues, including structural steel and
refractory brickwork. It is assumed that new overfire air nozzles and
sampling ports are included in the new furnace design.
•	Chesner reports direct capital costs for furnace reconfiguration for
four 250-tpd units to be $6,072,000 (12/84 dollars).
•	Assume single unit cost for a 250-tpd unit is $1,518,000.
ป Apply CEP index:
12/84 - 324.3
12/87 - 332.5
Unit Cost = $1,518,000(332.5/324.3) = $1,556,000.
ป Apply scaling factor:
DCC = 1,556,000(TPD/250),667(number of units).
•	Example: Estimate the direct capital cost of reconstructing two
120-tpd refractory wall combustors:
DCC - 1,556,000(120/250)*667(2) = $1,903,000.
3.2.2.3	Fuel Feeding Modifications
Ram Feeder - This modification includes material and labor, including the
hydraulic system, for a new ram feeder, plus any necessary modifications to
the feed chute.
•	Nashville Thermal reports 1979 direct capital (installed) costs of
ram feedecs (one dual ram for each of two 360-tpd units) to be
$360,000/
ft Assume that the unit cost is $180,000 for dual rams and $90,000 for
single ram. (Single rams can be used for grates with widths up to
8 feet.)
3.2-4

-------
•	Apply CEP Index:
1979 (yearly average) - 247.6
12/87 - 332.5
DCC - 90,000(332.5/247.6) = $121,000 per ram feeder.
•	Example: Estimate the direct capital cost of retrofitting one ram
on each of two 120-tpd units with 8-foot wide grates:
DCC - $121,000(2) - $242,000.
RDF Metered Feeder - This modification includes installing metered
feeding modules, consisting of two hoppers, one ram feeder, and one
variable-speed drive conveyor per module.
8
•	Equipment cost = $150,000 per module.
•	Apply installation factor to obtain direct capital cost:
DCC = $150,000(1.45) = $217,500 per module.
•	Example: Estimate the direct cost of retrofitting metered feeding
modules on two 300-tpd RDF-fired facilities. Assume two
distributors per unit and one module per distributor:
DCC = $217,500(2 modules/unit)(2 units) - $870,000.
3.2.2.4 Underfire Air Modifications
Segmented Underfire Air Supplies - This modification includes installing
segmented, separately controllable underfire air plenums.
•	Laval in estimated the direct capital cost of five new underfire air
plenums to be $153,000 Canadian (2/85) for the Quebec City
Incinerator.
Assume cost for one plenum = $153,000/5 = $30,600.
•	Convert to U.S. dollars:^ $Canadian = 1.35 ($U.S.)
$U.S. - 30,600/1.35 - $22,700 (2/85 dollars).
•	Apply CEP Index:
2/85 - 325.4
12/87 - 332.5
3.2-5

-------
(22,700)(332.5/325.4) = 23,200.
•	Apply scaling factor:
(Quebec City'is a 250-tpd unit.)
DCC - 23,200(TPD/250),6^7(h)(number of units),
where h = number of plenums.
•	Example: Estimate the direct capital cost of installing a single
underfire air plenum to the drying grate section of two 120-tpd
uni ts:
DCC - 23,200(120/25),667(1)(2) - $28,400.
Underfire Air Preheat - This modification includes a natural gas burner
sized to provide sufficient heat input to raise combustion air temperatures
from 68ฐF to 300ฐF.
ซ Example: Determine the size and direct capital cost of an auxiliary
fuel burner required to preheat underfire air supplied to the drying
grate. Assume that the unit size is 250 tpd.
250 tpd(2000 lb/ton)(day/24 hr)(hr/60 min) = 347 lb/min MSW.
Assume that the combustor operates at 150 percent excess air and
that stoichiometric air requirements are 3.25 lb air/lb waste.
Total air requirements are:
(347 lb/min)(3.25 lb air/lb waste)(2.5) = 2820 lb air/min.
Assume that 70 percent of total air is supplied as undergrate air,
and 20 percent of undergrate air is supplied to the drying grate.
(2,820 lb/min)(.70)(.20) = 395 lb/min at 68ฐF.
Q = mcp T
where: Q	=	heat input,
m	-	395 lb/min (mass flowrate),
c	ซ=	0.24 Btu/lb F (specific heat of air at standard
p conditions), and
T	ป	300 - 68 - 232 F.
Q = (395 lb/min)(0.24 Btu/lbฐF)(232ฐF)(60 min/hr) = 1.32 106 Btu/hr
Use a 1.4 x 10^ Btu/hr burner.
3.2-6

-------
•	MITRE reports capitalficosts of burners ranging from capacity of
9.2 x 10 to 1.5 x 10 Btu/hr to be $1200 per burner.
•	Apply CEP Index:
1981 (yearly average) - 297.0
12/87 - 332.5
1,200 (332.5/297.0) = 1340.
•	Apply installation factor to obtain direct capital cost:
DCC = 1,340(1.45) = $1,950 per burner.
3.2.2.5 Overfire Air Modifications
Flow modeling/thermal analysis studies are required in most cases prior
to modifying overfire air systems. Overfire air modifications made at
refractory-wall MWC's and tube and tile waterwall MWC's will usually require
only new ducting, dampers, and nozzles. New overf^-e air rows in
(nenibrane-wall MWC's are assumed to require installation of new waterwall tube
panels.
12
Flow Modeling/Thermal Analysis Studies - These analyses include flow
visualization studies, mixing and dispersion measurements, and flow
distribution studies on a built-to-scale physical model. In addition,
mathematical modeling is included as part Df the thermal analysis.
Cold flow modeling - $75,000
Thermal analysis - $50.000
Total	$125,000
Ducting and Dampers -
•	Ducting Capital Costs:^3 C - 1.1 (L)(Q)^'^,
where L = Length (ft) and
Q = 125 percent of the actual flue gas flowrate (acfm).
ซ Example: Estimate direct capital costs of ductwork and dampers
required to supply overfire air to two rows of nozzles. Assume a
gas flowrate of 21,400 acfm. Assume that the overfire air system
3.2-7

-------
is designed to provide 40 percent of total air flow (8,560 acfm).
At standard conditions, Q = 1.25(8,560) = 10,700 acfm.
Assume ducting length requirements are 100 feet.
C = 1.1(100)(10,700)- $11,400(equipment cost).
•	Damper Capital Costs: Chemical Engineering. December 29, 1980
presents cost curves for rectangular dampers.
•	Estimate costs of a damper to install in ducting. Assume that the
damper is manually controlled and has a 1.5 ft cross-sectional
area. The damper equipment cost is $400 (in December 1977 dollars).
Apply CEP Index:
12/77 - 210.3
12/87 - 332.5
400(332.5/210.3) ซ= $600 per damper (equipment cost).
Total equipment cost = Ducting costs + damper costs
$11,400 + 600 = $12,000.
Apply installation factor:
Total DCC = 1.45(12,000) - $17,400.
Insulation for Ducting - Capital costs for ducting insulation vary from
3.5 to 22 percent of direct capital costs for ducting. Selection of the
appropriate factor is based on flue gas temperature.^
• Example: Assume that ducting carries preheated air at a temperature
of 300 F and that capital costs for the ducting are $20,000.
Estimate direct capital costs of insulation.
Perry's Chemical Engineers Handbook (Table 25-51) specifies a range
of 3.5 to 6 percent of ducting costs over $17,000. Select 6 percent
as conservative number.
C - 20,000(0.06) = $1,200.
Apply installation factor:
DCC - 1.45(1,200) - $1,740.
3.2-8

-------
Membrane Wall Overfire Air Nozzle -
•	Laval in reports direct capital costs for one row of nozzles
installed at Quabec City Incinerator to be $40,000 (Canadian
2/85 dollars).
•	Convert to U.S. dollars:
$U.S. = SCanadian/l.35
SU.S. - 40,000/1.35 = 29,600 (2/85 dollars).
•	Apply CEP Index:
2/85 - 325.4
12/87 - 332.5
DCC = 29,600(332.5/325.4) = $30,200 per row.
•	Apply scaling factor:
(Quebec City is a 250-tpd unit.)
DCC = 30,200(TPD/250) '^(number of rows) (number of units).
•	Example: Estimate direct capital costs for two new overfire air
rows per unit for two 1000-tpd combustors:
DCC = 30,200(1000/250)-333(2 rows/unit)(2 units) - $192,000.
3.2.2.6 Combustion Controls and Monitors
Fully Automatic Combustion Controller - This modification includes all
hardware and software required for converting a manual combustion control
system to a fully automatic control (programmable logic controller).
•	Direct capital costs for one unit are $200,000.^'^ฎ
•	Additional units can be installed in control scheme using the same
hardware. Incremental capital costs are restricted to those costs
required for installation. Assume that the direct capital cost of
an automatic controller for more than one combustor is:
DCC - 200,000[1 + 0.45(N - 1)],
where N = number of combustors, and
installation factor = 45 percent of equipment costs.
DCC - 200,000 + 90,000(3 - 1) - $380,000.
3.2-9

-------
Monitors - Display readouts and data loggers are included for each
monitor. Air flow monitors are venturi flow meters with pressure transducers,
,19
Direct capital cost of in situ CO/t^ monitors - $45,000
19
• Direct capital cost of in situ CO monitor - $22,000
•	Direct capital cost of air flow pressure monitors for underfire air
plenums and overfire air headers - $1,500 per plenum or row of
overfire air nozzles.
Oxygen Trim Control - This modification includes installation of a
control loop which adjusts underfire air flowrate and/or plenum distribution
based on feedback signals from an 0ฃ analyzer.
•	Hampton, VA plant manager reports direct capital costs to be $25,000
for two 100-tpd units.
•	Assume that these costs are fixed, per unit costs:
DCC = $12,500/combustor.
3.2.2.7 Auxiliary Fuel Burner Installation
ซ Gas pipeline costs:
DCC =ป $50,000 per 1/2 mile22.
•	Auxiliary gas burners - Capital costs of dual-fuel burner packages,
including blowers, igniters, safety panels, and controls, are
available for the following burner sizes. An installation factor
of 45 percent is applied to obtain direct capital costs.
Burner size (Btu/hr)	Equipment Cost	Direct Capital Cost
10.5	$16,000	$23,200
30.0	$25,500	$37,000
45.0	$35,000	$50,800
60.0	$42,000	$60,900
Burner equipment costs for sizes other than those provided above
should be extrapolated based on size, and the 45 percent
installation factor should then be applied.
• Example: Estimate the capital cost of providing auxiliary fuel to a
facility with three 300-tpd combustors. Assume the nearest source
of gas is one mile away, and each combustor requires two burners,
each rated at 35 x 10 Btu/hr.
3.2-10

-------
DCC of pipeline = $100,000 and
Cost of one 35 x 10 Btu/hr burner = $31,400.
Apply installation factor:
DCC = 1.45(31,400) = $45,500.
Total direct capital costs for burners = $45,500 and
(2 burners/unit) (3 units) = $273,000.
Total direct capital costs ซ 100,000 + 273,000 - $373,000.
3.2.2.8	Carbon Monoxide Profiling
This activity includes two days labor for three men in the field plus
travel and reporting. Sampling is assumed to include 0^, carbon monoxide
(CO), and temperature measurements in a 16-point array under six variable air
distribution settings. Carbon monoxide profiling is required on only one
combustor when multiple units of identical design are in place:
DCC = $10,000 (Reference 24).
3.2.2.9	Economizer for Flue Gas Temperature Control
This modification includes a separate economizer module designed to
reduce flue gas temperatures from 600ฐF to 450ฐF, along with the addition of
ducting and a bypass damper.
•	Equipment cost = $45,000 (1986 dollars) for an economizer-sized to
handle flue gases from four 75-tpd units (300-tpd total).
•	Apply CEP Index:
1986 - 318.4
12/87 - 332.5
45,000(332.5/318.4) = $47,000.
•	Apply installation factor:
DCC = $47,100(1.45) = $68,100.
•	Apply scaling factor:
DCC - 68,100(TPD/300),59.
3.2-11

-------
•	Example: Estimate the direct capital cost of installing one
economizer for three 50-tpd units:
DCC = 68,100(150/300)'59 = $45,200.
3.2.3 Operating Cost Procedures
Total annual costs include annual operating and maintenance (O&M) costs
and annualized capital costs. Table 3.2-1 presents a summary of inputs used
to estimate annual costs. The costs provided for each plant are incremental
0&M costs. For example, if a plant is equipped with auxiliary fuel burners at
baseline, it is assumed that the fuel is used for start-up and shutdown, and
no incremental 0&M cost is applied to the plant for auxiliary fuel
consumption. Plants without auxiliary burners in place will incur additional
costs for fuel consumption. The following examples illustrate the calculation
of annualized costs associated with combustion controls.
•	Example: A mass-burn refractory-wall MWC consisting of three
250-tpd combustors must add auxiliary fuel burners and operate the
burners during start-up and shutdown. The facility maintains a five
per week operating schedule. Determine the size of burners required
to provide 60 percent of rated thermal load and estimate natural gas
consumption costs.
Combustor	_ (250 ton/davH2000 1b/tonH4500 Btu/lb)
thermal load	(24 hr/day)
= 94 x 106 Btu/hr
Assume for a refractory-wall facility that gas is fired for six
hours during start-up and two hours during shutdown. Assume that
the plant operates 50 weeks/year, and start-up/shutdown occurs
weekly.
Total gas use = (50 wk/yr)(6 + 2 hours)(56 x 10ฎ Btu/hr)(3 units)
- 67.2 x 109 Btu/yr
3.2-12

-------
TABLE 3.2-1. O&M COST INPUTS (DECEMBER 1987 DOLLARS)
Item
Value
Direct ODeratina Costs

Operating Labor
$12.00/hour
Supervision
15 percent of operating labor
Maintenance Labor
110 percent of operating labor
(assume 1 hr/shift for
maintenance of controls and
moni tors)
Maintenance Materials
100 percent of maintenance labor
Natural Gcis
$4.50 per 106 Btu
Water
$0.50 per 1000 gallons
S teaii;
$5.30 per 1000 lb
Sol id Was e Disposal
$25 per ton
Indirect (Deratina Costs

Overlive
60 percent of all labor costs
(operating, supervisory, and
maintenance) plus 60 percent
maintenance materials
Taxes, Insurance, and
Administrative Charges
4 percent of total plant capital
costs
Capitcl Recovery
15 year life and 10 percent
interest rate
CRF - 	^
(1 + i)" - 1
where i = interest rate and
n = number of years
CRF = J - .1315
(l.l)1* - 1
3.2-13

-------
Using a gas cost of $4.50/10^ Btu:
C = (67.2 x 109 Btu/yr)(4.50/106 Btu) = $302,000/yr
• Example: Determine the annual costs for a combustion retrofit at the
plant in the above example. Total plant capital costs are assumed to be
5500,000, including installation of CO and monitors.
Direct Costs:
Assume 1 hr/shift (3 hr/day) maintenance of monitors and
controls.
Maintenance Materials = (3 hr/day)(5 day/wk)(50 wk/yr)(S13.20/hr) -
$10,000/yr,
Maintenance Materials - $10,000/yr (100% of maintenance labor)
Gas costs = $302,000/yr, and
No additional operating labor is required.
Total Direct Annual Costs = 10,000 + 10,000 + 302,000 - $322,000.
Indirect Costs:
Overhead = 0.6(maintenance labor + maintenance materials).
Overhead = 0.6(20,000) ซ= $12,000.
Taxes, Insurance and Administrative Charges = .04(total plant
capital costs) - .04(500,000) - $20,000.
Annualized capital = .1315(500,000) = $66,000 assuming 15 year
facility life and 10 percent weighted cost of capital.
Total Indirect Annual Cost = Overhead + Taxes, Insurance, and
Administrative + Annualized Capital
= $12,000 + $20,000 + $66,000 = $98,000.
Total annual cost = Direct Cost + Indirect Cost
- $322,000 + $98,000 = $420,000/yr.
3.2-14

-------
REFERENCES
1.	Radian Corporation and Energy and Environmental Research Corporation.
Municipal Waste Combustors - Background Information for Proposed
Guidelines for Existing Facilities. Prepared for U. S. Environmental
Protection Agency. Publication No. EPA-450/3-89-27e. August 1989.
2.	EER. Municipal Waste Combustion Study: Combustion Control of MSW
Combustors to Minimize Emission of Trace Organics. Prepared for U. S.
Environmental Protection Agency. June 1987. Publication
No. EPA/530-SW-021C.
3.	Perry, Robert H. and Don Green. Perry's Chemical Engineers' Handbook
(Sixth Edition). New York: McGraw-Hill, 1984, p. 25-70.
4.	Reference 3, p. 25-69.
5.	U. S. Environmental Protection Agency. EAB Control Cost Manual (Third
Edition). Research Triangle Park, NC. Publication
No. EPA-450/5-87-001A. February 1987.
6.	Chesner Engineering and Black and Veatch Engineers. Energy Recovery from
Existing Municipal Incinerators. New York State Energy Research and
Development Authority (NYSERDA) Report No. 85-14. November 1984.
p. 43-85.
7.	Telecon. Conversation between J. Jackson, Nashville Thermal, and
P. Schindler, EER, on April 6, 1988.
8.	Telecon. Conversation between Tom Giaier, Detroit Stoker, and
P. Schindler, EER, on May 13, 1988.
9.	Lavalin. National Incinerator Testing and Evaluation Program (NITEPk
Quebec Urban Community MSW Incinerator Program Planning. Part 2 Final
Report. Prepared for Environment Canada. April 1985.
10.	Wal1 Street Journal. Foreign Exchange. February 7-27, 1985.
11.	MITRE Corporation. The Estimation of Hazardous Waste Incineration Costs.
MTR-82W233. January 1983. p. 55.
12.	EER in-house estimate provided by D. Moyeda.
13.	U. S. Environmental Protection Agency. Municipal Waste Combustion Study:
Costs of Flue Gas Cleaning Technologies. Research Triangle Park, NC.
Publication No. EPA/530-SW-87-021e. June 1987.
14.	Vatavuk, W. and R. Neveril. "Part IV - Estimating the Size and Cost of
Ductwork." Chemical Engineering. December 29, 1980, p. 73.
15.	Reference 1, Table 25-51, p. 25-70.
3.2-15

-------
16.	Reference 5, p. 7-3.
17.	Reference 5, p. 7-3.
18.	Telecon. Conversation between Rob Busby, Bailey Controls, and
P. Schindler, EER, on May 17, 1988.
19.	Compilation of vendor quotes obtained by S. Agrawal, EER, for EPA/OSWER.
Documented in letter to Robert Holloway, EPA/OSWER. April 8, 1987.
20.	Waukee Flo-meter Price List. Waukee Engineering Company Bulletin No.
1-1274-R8- Milwaukee, WI. April 1, 1987.
21.	Information provided to EPA and EER during visit to NASA/Langley Waste to
Steam Plant, Hampton, VA. July 6, 1988.
22.	Telefax from Dan Hughes, Florida Gas Transmission Company, to
W.S. Lanier, EER. April 12, 1988.
23.	Vendor cost quotes provided to EER by Ed Flammang, North American
Manufacturing Company, Cleveland, OH. August 11, 1988.
24.	EER in-house estimate provided by 2. Frompovich.
25.	Telecon. Conversation between Col. Frank Rutherford, Tuscaloosa Solid
Waste Authority and P. Schindler, EER. May 26, 1988.
3.2-16

-------
3.3 HUMIDIFICATION
3.3.1 Overview of Technology
Humidification is used to cool the flue gas entering the particulate
matter (PM) control device. Humidification can be used separately or in
combination with dry sorbent injection. The primary objective of cooling
is to reduce the temperature of the flue gas entering the PM control device
to below that at which post-combustion formation of dioxin is suspected to
occur (approximately 450ฐF).
The quantity of water required is a function of the temperature,
flowrate, and moisture content of the flue gas at the inlet to the
humidification chamber and the temperature reduction required.^
Qw = (TrT0) * Qs * (1 -WTR/100)/940	(])
where: Q = water required for flue gas coolir^, lb/hr;
w
T. ฆ inlet flue gas temperature, F;
Tq = outlet flue gas temperature, ฐF;
Qs = flue gas flowrate, scfm; and
WTR = moisture content of the inlet flue gas, volume percent.
Flue gas temperatures at the combustor exit for refractory-wall
combustors generally ranged from 1,400 to 1,600ฐF; for waterwall
combustors, temperatures ranged from 400 to 600ฐF.
For units already using quench towers for flue gas cooling (primarily
refractory-wall systems without heat recovery), the water feed rate is
increased to achieve the additional cooling. For units without an existing
flue gas cooling system, a humidification chamber is installed. The
humidification chamber diameter is sized for a flue gas velocity of
2
10 feet/second and a chamber length-to-diameter (L/D) ratio of 3 to 1. To
minimize PM fallout and impingement of wetted solids on chamber walls, no
baffles or other internals are used. Pressure nozzles are used for water
atomization.
A secondary effect of cooling the flue gas entering the PM control
device is a reduction in flue gas volume (i.e., acfm) and a corresponding
3.3-1

-------
increase in the specific collection area (SCA) thereby enhancing the PM
collection efficiency of the ESP. However, because MWC ESP's operate at
temperatures above the temperature of maximum particle resistivity (300 to
400ฐF for most fly ashes), decreasing flue gas temperature may in some
instances increase fly ash resistivity enough to create ESP back corona
problems and impair PM collection efficiency. Because of the current lack
of information on resistivity-temperature relationships for MWC fly ash,
this analysis assumes that humidification does not alter particulate
resistivity enough to cause ESP operating problems. As a result, the
impact of humidification on ESP performance is estimated based solely on
the change in SCA due to flue gas volume reduction.
3.3.2 Capital Cost Procedures
Capital costs are estimated for existing facilities without an
existing flue gas cooling system. Direct capital costs include the
humidification (evaporative cooling) chamber including the vessel and
supports, water spray system and controls, and duct modifications. Direct
equipment cost for the humidification chamber are based on the flue gas
3
flowrate using the following equation:
Equipment Costs ($) = 0.372 * Q + 67,980	(2)
where: Q is 125 percent of the actual inlet flue gas flowrate (acfm)
to accommodate variations in waste composition and operating
4
conditions.
The costs estimated by equation 2 are in December 1987 dollars.
Originally, the costs were in December 1977 dollars and were adjusted to
December 1987 dollars using the Chemical Engineering Plant Cost Index for
all equipment. The equipment costs are then adjusted for retrofit
difficulty based on the procedures described 1n Section 3.7.1.
Costs for instrumentation, taxes, freight, and installation are
estimated using indirect cost factors for venturi scrubbers.^ The
3.3-2

-------
resultant procedure for estimating capital cost is summarized in
Table 3.3-1.
3.3.3 Operating Cost Procedures
Table 3.3-2 presents procedures for estimating operating and
maintenance (O&M) costs for the humidification chamber. Because of the
simple design and operating requirements of the system, O&M labor and
maintenance materials are assumed to be at the low end of those presented
in Reference 6 (i.e., using the wet scrubber labor and materials
requirements). Other O&M costs include water and the electricity used by
the pumps. All costs are based on December 1987 dollars. An operating
labor wage of the $12/hr was used. This wage was the average of the labor
wages reported by both the Department of Commerce Survey of Current
Business for private nonagricultural payrolls and EPRI's
7 8
Technical Assessment Guide for utility power plants. ' The labor wage
reported by EPRI in January 1985 dollars was updated to December 1987
dollars using the Bureau of Labor Statistics' Producer Price Cost Index for
all industrial commodities, prior to averaging. An electricity cost of
$0.046/kWh was obtained from the Energy Information Administration
g
Monthly Energy Review. Equipment life is assumed to be 15 years.
3.3-3

-------
TABLE 3.3-1 CAPITAL COST PROCEDURES FOR HUM ID1FICAT ION10'11
Equipment Costs (December 1987 dollars)
1.	Humidification Chamber and Pumps:3
Cost, $ ฆ= 0.372 * q + 67,980
2.	Ductwork
Cost, $ = 0.981 * L * Q0,5
Retrofit Purchase Equipment Costs = 1.18 * Equipment Costs * Retrofit
Factor (from Section 3.7)
Installation Direct Costs = 0.56 * Purchased Cost
Indirect Costs*3 * 0.35 * Purchased Cost
Total Capital
Costs	= Purchased Equipment Costs + Installation Direct Costs +
Indirect Costs
= 1.91 * Purchased Costs
aQ - 125 percent of the actual flue gas flowrate, acfm
L - Duct length, feet.
''includes a contingency of 3 percent of the purchased costs.
3.3-4

-------
TABLE 3.3-2 OPERATING AND MAINTENANCE COSTS FOR HUMIDIFICAT ION
Operating Labor:
Supervision:
Maintenance Labor:
Maintenance
Materials:
Water:
Electricity:3'^
Overhead:
Taxes, Insurance,
and Administrative
Charges:
Capital Recovery:
0.5 man-hours/shift; wages of S12/hr
15% of operating labor costs
0.5 man-hours/shift
10% wage premium over operating labor wages
1% of total capital investment
0.00012 * Q * (hours of operation) *
(water cost1?, S/1000 gal)
cost of SO.50/1000 gal
-4
1.587 x 10 * Q * (hours of operation) *
(electricity costs, S/kWh)
cost of SO.046/kWh
60% of the sum of all labor costs (operating,
supervisory, and maintenance) and maintenance
materi als
4% of the total capital costs
15-year life and 10% interest rate
References
6, 8
12
12
13
14
15
15
15
Q =* water injection rate, lb/hr, (from Equation 1 in Section 3.3.1).
w
'Assume 20 feet of pumping height, 100 psi discharge pressure, and
10 ft/sec velocity in pipe.
3.3-5

-------
REFERENCES
1.	PEI Associates, Inc. User's Manual for the Integrated Air Pollution
Control System Cost and Performance Program (Version 2). Prepared for
the U. S. Environmental Protection Agency. Research Triangle Park,
NC. Contract No. 68-02-3995. April 1985. p. 4-16.
2.	Neveril, R.S. (GARD Inc.) Capital and Operating Costs of Selected Air
Pollution Control Systems. Prepared for U. S. Environmental
Protection Agency. EPA-450/5-80-002. December 1978. p. 4-40.
3.	Reference 2. p. 4-41.
4.	Letter from Sedman, C.B., EPA, to Chang, J. Acurex Corporation. July
14, 1986. EPA guidelines for costing flue gas cleaning technologies
for municipal waste combustor.
5.	Reference 2. p. 3-11.
6.	Reference 2. p. 3-14.
7.	United States Department of Commerce. Survey of Current Business.
Washington, D.C. Volume 68. Number 6. Jur^ 1988. p. S-12.
8.	Electric Power Research Institute. TAG - Technical Assessment Guide
(Volume 1: Electricity Supply - 1986). Palo Alto, CA. Publication
No. EPRI P-4463-SR. December 1986. p. B-4.
9.	Energy Information Administration. Monthly Energy Review:
December 1987. Washington, D.C. Publication No. DOE/EIA-0035 (87/12).
March 1988. p. 109.
10.	Reference 2. p. 4-41.
11.	U. S. Environmental Protection Agency. Municipal Waste Combustion
Study: Costs of Flue Gas Cleaning Technologies. Research Triangle
Park, NC. Publication No. EPA/530-SW87-021e. June 1987.
12.	Reference 2. p. 3-12.
13.	Reference 5. p. 4-23.
14.	Letter from Solt, J.C., Solar Turbines Incorporated, to Noble, E.,
EPA. October 19, 1984. Development cost for wet control for
stationary gas turbines.
15.	U. S. Environmental Protection Agency. EAB Control Cost Manual.
Research Triangle Park, NC. Publication No. EPA-450/5-87-001A.
February 1987. p. 2-31.
3.3-6

-------
3.4 PARTICULATE MATTER CONTROL RETROFIT
This section discusses three electrostatic precipitator (ESP) control
alternatives for reducing PM emissions from existing MWC facilities. These
alternatives are: installation of a new ESP (discussed in Section 3.4.1),
increasing the plate area of an existing ESP (Section 3.4.2), and rebuilding
an existing ESP to improve performance (Section 3.4.3).
3.4.1 Installation of a New ESP
The procedures for estimating ESP capital costs for new plants (described
in Section 2.2.2) are applicable to the procedures used for existing plants.
The existing plant cost procedures include site-specific retrofit factor and
scope adders used to estimate the cost of demolition, replacement, relocation
of existing equipment, new ducting, and stacks, if needed.
3.4.1.1	Capital Cost Procedures. The procedures developed for
estimating the capital costs of ESP's for new plants (described in
Section 2.2.4.1) are used to estimate the direct costs of major equipment,
including the fans and ash handling. Estimated duct lengths are required to
calculate duct costs for connecting the ESP to an existing plant. The
estimated direct costs of new equipment and ducts are then multiplied by
site-specific retrofit factors determined by the procedures described in
Section 3.7.1.
Total direct capital costs for retrofit are calculated as the sum of the
adjusted equipment costs fclus any scope adders. Scope adders are additional
significant costs for items, such as chimneys or demolition, that are required
for an accurate estimate of the ESP retrofit. Determination of scope adder
costs is described in Section 3.7.2.
After the total direct capital costs have been estimated, the remainder
of the capital cost procedure (for indirect and contingencies costs) is the
same as for ESP's installed in new plants as described 1n Section 2.2.4.1.
3.4.1.2	Operating Cost Procedures. Operating costs for retrofit ESP's
are estimated using the same procedures as those for new plants discussed in
Section 2.2.4.2. The costs of taxes, insurance, and administrative charges
are estimated as a fraction of the total retrofit capital costs. The proposed
3.4-1

-------
procedures also allow operating hours to be varied to reflect model plant
specifications.
3.4.2 Increase in ESP Plate Area
Additional ESP plate area is installed when the existing ESP is too small
to achieve the desired PM control. Addition of plate area is accomplished by
installing a new ESP in series with the existing ESP. This approach results
in minimum facility downtime and will simplify cost estimation relative to the
addition of plate area to the existing ESP.
3.4.2.1	Capital Cost Procedures. The procedures developed for
estimating the capital costs of ESP's for new plants (described in
Section 2.2.4.1) are used to estimate the direct costs of installing
additional ESP plate area. First, the required particulate removal efficiency
is calculated based on the PM emission limit desired and the inlet PM
concentration. This removal efficiency is then used to calculate the required
specific collection area (SCA) using either equation 2 or 4 presented in
Section 2.2.4.1. Next, the SCA of the existing ESP is subtracted from the
calculated SCA to determine the additional SCA required. The additional SCA
required is used to calculate the additional plant area requirement and the
direct costs of the second ESP using equations 1 or 3 in Section 2.2.4.1. The
required duct length is estimated for each model plant based on the equipment
configuration for that plant. The estimated direct costs of the new ESP and
ducts are then multiplied by a site-specific retrofit factor determined
according to the guidelines discussed in Section 3.7.1. Appropriate scope
adders are costed based on procedures described in Section 3.7.2.
After the total direct capital costs have been estimated, the remainder
of the capital cost procedure (for indirect and contingency costs) are the
same as for ESP's installed in new plants presented in Section 2.2.4.1.
3.4.2.2	Operating Cost Procedures. Operating costs for the second ESP
are estimated using procedures for new plants discussed in Section 2.2.4.2.
Only those costs associated with the second ESP are included. Because
operating, supervision, and maintenance labor are available for the existing
ESP, it is assumed that no additional labor requirements are necessary to
operate and maintain the second ESP.
3.4-2

-------
3.4.3 ESP Rebuild
An ESP rebuild can be used with existing ESP's with PM removal
efficiencies lower than those predicted in either Figures 2.2-2 or 2.2-4 for a
new ESP with equivalent SCA. Rebuild of an ESP includes replacing worn or
damaged internal components (plates, frame, and electrodes), upgrading
controls and electrical systems for more effective energization, and flow
modeling to evaluate gas distribution. The ESP rebuild does not include
making design changes to the existing ESP, such as changes to the
plate-electrode geometry or addition of collection area.
3.4.3.1	Capital Cost Procedures. The procedures developed for
estimating the capital costs of ESP's for new plants (described in
Section 2.3.4.1) are used to estimate the direct costs of ESP rebuild. Based
on contacts with ESP vendors, a typical cost for rebuilding an existing ESP is
roughly 30 percent of the total capital cost of a new ESP of equivalent size,
1 2
but can be as high as 50 percent of the new ESP cost. '
The recommended procedure for estimating the total capital costs for ESP
rebuild is to use 30 percent of the cost for a new ESP. This factor assumes
equipment costs of 42 percent of the cost of a new ESP plus installation and
indirect equipment cost multipliers of 0.33 and 0.27, respectivelyThese
indirect cost multipliers are lower than those used for new ESP's because:
(1) new foundations, supports, piping, insulation, and painting are not
required and (2) engineering and erection expenses are reduced relative to the
costs for a new ESP. Site-specific retrofit factors are not used since the
rebuild is performed within the existing ESP.
3.4.3.2	Operating Cost Procedures. The operating and maintenance costs
after ESP rebuild are the same as before the rebuild with the exception of
additional waste removal. The additional waste removal requirements are based
on the incremental reduction of PM achieved after the ESP is rebuilt.
3.4-3

-------
REFERENCES
1.	Telecon, Lamb, Linda, Radian Corporation, with Gawrelick, Gary,
Research-Cottrell. February 18, 1988. Rebuild Costs for ESP's.
2.	Telecon. Martinez, John, Radian Corporation, with Gawrelick, Gary,
Research-Cottrell. April 11, 1988. Additional cost information on ESP
rebuilds.
3. Turner J.H. et al. Electrostatic Precipitators (draft section). In:
EAB Control Cost Manual, U. S. Environmental Protection Agency. Research
Triangle Park, NC. Publication No. EPA-450/5-87-001A. February 1987.
p. 6-56.
3.4-4

-------
3.5 Dkr SORBENT INJECTION RETROFIT
3.5.1	Overview of Technology
Cost procedures are presented in Section 2.3 for the injection of dry
sorbent into the furnace or duct of a new plant. The major distinctions
between the design of sorbent injection systems for most existing facilities
versus new facilities are (1) the reuse of an existing ESP rather than a new
fabric filter for PM control, and (2) the higher capital costs to reflect the
difficulty of a site-specific retrofit. For existing facilities not equipped
with an E:>P, new fabric filters can be used.
Another retrofit option for duct sorbent injection at existing facilities
is to :njact dry sorbent following an existing spray humidification chamber.
In this option, the flue gas leaving the combustor is cooled by humidification
to 350cF before it enters the ESP, or to 300ฐF in the case of a fabric filter.
Dry sorbent is injected after the gas is humidified to minimize cake buildup
in the duct.
3.5.2	Capital Cost Procedures
The procedures developed for estimating the capital costs of dry sorbent
injection for new plants are used to estimate the direct capital cost of major
equipment and ductwork for retrofit installations. Because the major
equipment components of dry sorbent injection (reagent storage and handling
system) can be located in remote areas, difficulties associated with spacial
constraints (i.e., access/congestion) and underground obstructions is
generally minimal. Based on the application of dry sorbent injection to
coal-fired utility boilers, the direct capital cost for new plants is
increased by 10 percent to account for the estimated costs of modifying an
existing duct in the case of duct sorbent injection, modifying an existing
overfire air system in the case of furnace sorbent injection, or modifying an
existing humidification chamber.^
The total direct capital costs for retrofit also include the cost of any
scope adders such as additional ducting or existing equipment demolition that
is required to accurately estimate dry sorbent injection retrofit costs at a
specific site. Additional ductwork can be estimated using cost equations in
Section 2.3. Scope adders are defined in Section 3.7.2. Determination of
scope adder costs is also described in Section 3.7.2.
3.5-1

-------
After the total direct capital costs have been estimated, tire remainder
of the capital cost procedure for estimating indirect capital costs and
contingencies is the same as for dry sorbent injection at a new plant
presented in Section 2.3.4.1.
3.5.3 Operating Cost Procedures
Operating costs for retrofit dry sorbent injection installations are
estimated using the same procedures discussed in Section 2.3.4.2 for new
plants. Operating costs for existing plants are higher than for new plants of
equivalent sizes because the maintenance expenses are affected by access and
congestion difficulties. This increased cost is handled by calculating
maintenance materials as a percentage of the total capital investment. The
costs of taxes, insurance, and administrative charges are based on the total
retrofit capital costs.
3.5-2

-------
REFERENCE
1. Radian Corporation. Retrofit Costs for S02 and NO Control Options at 50
Coal-Fired Plants (Draft Report). Preparea for the U. S. Environmental
Protection Agency. Research Triangle Park, NC. Contract No. 68-02-4286.
February 1988.
3.5-3

-------
3.6 SPRAY DRYER RETROFIT
3.6.1	Overview of Technology
Spray dryers (SD) combined with fabric filters (FF) can be retrofitted at
existing plants where very high levels of CDD/CDF and acid gas control are
required. Key technology considerations include reconfiguration of the
ducting between the combustor outlet and stack, and the availability of space
for installing sorbent handling equipment, SD vessel, FF, and ash disposal
facilities.
Stand-alone SD costs were developed for this study to evaluate the costs
of retrofitting a new SD in front of an existing particulate control device.
Cost procedures presented in Sections 3.6.2 and 3.6.3 can be applied to
estimate SD retrofit costs at existing plants. In most cases, the existing
particulate control device is an ESP. For cases where it is determined that
additional plate area is required to handle the increase in fly ash loading to
the ESP caused by the SD, costing procedures presented in Sections 2.2 and
3.4.2	for modifying ESP's to add plate area should be used.
3.6.2 Capital Cost Procedures
The procedures developed for estimating the capital costs of SD/FF
systems for new plants (described in Section 2.4.4) can be used to estimate
the direct capital cost of major equipment and ducts for retrofit
installations. Required duct lengths are used to estimate the duct costs for
connecting the SD system to an existing plant. The estimated direct costs of
new equipment and ducts are then multiplied by site-specific retrofit factors
determined by the procedures in Section 3.7.1.
Capital costs for stand-alone SD systems are based on quotes obtained
from three manufacturers.1-3 These quotes, shown in Table 3.6-1, exclude the
costs of any particulate control device. As discussed in Section 2.4, direct
capital costs were correlated with flue gas flowrates. The direct capital
cost equation in Table 3.6-2 for a single SD unit was developed from these
2
quotes. The correlation coefficient (R ) for this equation is 0.81.
Figure 3.6-1 shows the relationship of both the predicted SD direct capital
costs and the vendor costs with flue gas flowrate. The accuracy of the
3.6-1

-------
TABLE 3.6-1. VENDOR QUOTES FOR SPRAY DRYER DIRECT CAPITAL COSTS
(in 1000$ August 1988)
Vendor
Combustor
Type3
Combustor.
Size, tpd
Flue gas
Flowrate,
acfm
Direct
Capital Costs
A
KB/ WW
100
24,000
890
A
MB/RC
250
49,000
1,225
A
RDF
300
82,800
1,575
A
MB/WW
750
210,000
2,725
A
RDF
1,000
393,000
3,930
B
MB/WW
100
24,000
850
B
MB/RC
250
49,000
1,400
B
RDF
300
82,800
900
B
MB/WW
750
210,000
2,500
B
RDF
500
196,500
2,150
C
MB/WW
100
24,000
1,300
C
MB/RC
250
49,000
2,170
C
RDF
300
41,400
1,650
C
MB/WW
750
210,000
3,430
c
RDF
500
196,500
2,560
MB/WW = mass burn/waterwal1
MB/RC = mass burn/rotary combustor
RDF = refuse-derived fuel
^tpd = tons burned per day
3.6-2

-------
TABLE 3.6-2. CAPITAL CCST PROCEDURES FOR SPRAY DRYERS3
Total Direct Costs (December 1987 dollars)
Single SD Unit only: Costs, 103 $ = 8.428 (Q)0-460 * N * RF
Ductwork^: Costs, 103 $ = [1.3868 * L * Qฐ'5]/1,000 * N * RF
Fanb: Costs, 103 $ - [1.8754 * Qฐ'96]/1,000 * N * RF
Multiple Units: Multiply the above costs by the number of units
Indirect Costs = 33% of total direct costs
Contingency = 20% of sum of direct and indirect costs
Total Capital Costs =ป Total Direct Costs 1- Indirect Costs + Contingency Costs
aQ = 125 percent of the actual flue gas flowrate. acfm
L = Duct length, feet
N = Number of units
RF = Retrofit factor, dimensionless
^Assumes that the total installed costs are 133 percent of the direct capital
costs.
3.6-3

-------
~
u Vendor costs
Predicted costs
~
\
i	1	1	1	1	~i	r
100	200	300
(Thousands)
FLUE GAS FLOWRATE. ACFM
Correlation of SO direct capital costs (in August 1988 dollars)
from the SD Manufacturers and flue gas flowrate.

-------
ฑiV percent. It should be noted that the costs shown in this figure are
reported in Augjs1 1988 dollars and that the flue gas flowrate is the actual
flue gas flowrate. The SD direct capital cost equation in Table 3.6-2 was
oerivtd by c'd-escal at ing the predicted cost curve shown in Figure 3.6-1 to
December 1987 cjlUrs using the Chemical Engineering Plant Index and by
ccrrectirg fot :I.percent of the actual flue gas flowrate. Comparing the
direc*. c.t;t.a 1 ei^ts for SD with those for SD/FF estimated using procedures in
Se'!. 2.-L the SD '..osts are generally between 50 and 60 percent of the costs
for a S!/m for f , v.? yas flowrates ranging from 25,000 to 400,000 acfm. These
fiue flowrjlvr c.r, er the range of flowrates from small modular units to
1 ar^e RDf units, rcr F.SP reuse, the costs of additional plate area, if any,
o:tir;;ated from pr?r<.-cures presented in Section 3.4.2 should be included.
The required diiCt length is estimated for each model plant based on the
r-r-cuosed air poll :::on control device (APCD) equipment configuration for that
v-U'it. The	direct costs of new equipment and ductwork are then
tipl icd by s• re-satcific retrofit factors described in Section 3.7.1.
The U>t=i direct capital cost for retrofit is calculated as the sum of
:he adjusted new ^quicment costs plus any scope adders. Scope adders
incorporate additional capital costs for items such as chimneys or demolition
thst ere required for SD retrofit. Determination of scope adder costs is
described in Section 3.7.2.
After the total direct capital cost has been estimated, the remainder of
the capital costing procedure for indirect capital costs and contingencies
is the same as for SQ-'FF installation at a new plant (see Section 2.4.2).
3.0.3 Operating Cost procedures.
Operating costs for retrofit SD/FF installations are estimated using the
saint procedure: as for new plants in Section 2.4.3. Table 3.6-3 presents the
annual operating cost procedures for stand-alone SD's. Annual operating costs
for the SD system alone exclude costs associated with the PM control device,
such as bag replacement, compressed air, and solid waste costs. Operating
labor, supervision, and maintenance labor costs for the SD alone are half
those for a similar SD/FF system. Electricity costs for the I.D. fan are
based on 5.5 inches of water pressure drop for an SD compared with
3.6-5

-------
TABLE 3.6-3. ANNUAL OPERATING COSTS PROCEDURES FOR STAND-ALONE
SPRAY DRYERS FOR NEW MWC's3
Operating Labor:
Supervision:
Maintenance:
Labor:
Materials:
Electricity:
Fan:
2 man-hours/shift; $12/man-hour
15% of operating labor costs
1 man-hour/shift; 10% wage rate
premium over operating labor wage
2% of direct capital costs
Cost Rate = $0.046/kwh
5.5 inches of water pressure drop
Reference
4, 5
6
5
7
4, 5
Atomizer:
Pump:
Water:
Lime:
Overhead:
6kW/l,000 lbs/hr of slurry feed + 15kW
20 feet of pumping height
10 psi discharge pressure
10 ft/sec velocity in pipe
Calculate water flowrate reguired for
cooling the flue gas to 300 F; water
cost = $0.50/1000 gal
Based on lime feed rate calculated by
assuming a stoichiometric ratio of
1.5:1; lime cost = $70/ton
60% of the sum of all labor costs
(operating, supervisory, and maintenance)
plus materials
8
9
10
11
12
Taxes, Insurance, and
Administrative Charges: 4% of total capital costs
12
Capital Recovery:
15-year life and 10% interest rate
13
All costs are in December 1987 dollars.
3.6-6

-------
12.5 inc'ias of water pressure drop for a SD/FF. Operating costs for ESP reuse
are estimated from procedures presented in Section 3.4.2 for additional ESP
plate area.
Operating costs for existing plants are higher than for new plants of
equivalent size, since maintenance expenses will be affected by access and
congestion difficulties. This increased cost is handled by calculating
maintenance materials as a percentage of the total capital investment; The
costs of taxes, insurance, and administrative charges are based on total
retrofit capital costs. These procedures also allow operating hours to be
varied to meet model plant specifications.
3.6-7

-------
REFERENCES
1.	Letter and attachment from Weaver, E.H., Belco Pollution Control
Corporation, to Johnston, M.G., EPA. September 28, 1988. Retrofitting
of spray dryers to existing MWC's.
2.	Letter and attachment from Buschmann, J.C., Flakt Incorporated-, to
Johnston, M.G., EPA. October 27, 1988. Costs for spray dryers applied
to MWC's.
3.	Letter and attachment from Murphy, J.L., Wheelabrator Air Pollution
Control, to Johnston, M.G., EPA. November 18, 1988. Costs for spray
dryers applied to MWC's.
4.	Memorandum from Aul, E.F., et al., Radian Corporation, to Sedman, C.B.,
EPA. May 16, 1983. 36 p. Revised Cost Algorithms for Lime Spray Drying
and Dual Alkali FGD Systems.
5.	Neveril, R.B. (GARD, Inc.). Capital and Operating Costs of Selected Air
Pollution Control Systems. Prepared for the U. S. Environmental
Protection Agency. Research Triangle Park, NC. Publication No.
EPA-450/5-80-002. December 1978. p. 3-12.
6.	U. S. Environmental Protection Agency. EAB Control Cost Manual.
Research Triangle Park, NC. Publication No. EPA-450/5-87-001A.
February 1987. p. 2-6.
7.	Electric Power Research Institute. TAG^-Technical Assessment Guide
(Volume 1: Electricity Supply-1986). Palo Alto, CA. Publication No.
EPRI P-4463-SR. December 1986. P. 3-10.
8.	Reference 1, p. 4-23.
9.	Dickerman, J.C. and K.L. Johnson. (Radian Corporation.) Technology
Assessment Report for Industrial Boiler Applications: Flue Gas
Desulfurization. Prepared for the U. S. Environmental Protection Agency.
Washington, DC. Publication No. EPA-600/7-79-178i. November 1979.
pp. 5-5 and 5-17.
10.	Letter from Solt, J.C., Solar Turbines Incorporated, to Noble, E., EPA.
October 19, 1984. Development cost for wet control for stationary gas
turbines.
11.	Chemical Marketing Reporter. Volume 233. Number 1. January 4, 1988.
12.	Reference 7, p. 2-29.
3.6-8

-------
13. Bowen, M.L. and M.S. Jennir-~s. (Radian Corporation). Cost of Sulfur
Dioxide, Particulate Matter, and Nitrogen Oxide Controls in Fossil Fuel
Fired Industrial Boilers. Prepared for the U. S. Environmental
Protection Agency. Research Triangle Park, NC. Publication No.
EPA-450/3-82-021. August 1982. pp. 2-17 and 2-18.
3.6-9

-------
3.7 DETERMINATION OF RETROFIT FACTORS AND SCOPE ADDER COSTS
The costs of air pollution control device (APCD) installation at an
existing plant are greater than at a new facility due to higher construction
costs imposed by site access and congestion, longer duct runs caused by space
limitations, 2nd the need to demolish and relocate some existing facilities.
Procedures for estimating these costs at MWC's were adapted from procedures
developed for the Electric Power Research Institute (EPRI) for retrofitting
APCD's at existing electric generating plants.* These additional costs are
divided into two types of adjustments: retrofit multipliers (discussed in
Section 3.7.1) and scope adders (discussed in Section 3.7.2).
3.7.1	Retrofit Factors
Site-specific retrofit factors can be estimated based on access and
congestion problems associated with retrofitting APCD's at existing plants.
Depending on the level of accessibility and congestion, one of four factors
(ranging from 1.02 to 1.42) is recommended based on the guidelines shown in
Table 3.7-1. The total direct costs of new APCD equipment excluding ductwork
2
are multiplied by this retrofit factor to estimate retrofit costs.
3.7.2	Scope Adders
Scope adders are site-specific costs for additional ducting, chimneys,
demolition, or any other major items that can be included in retrofit cost
estimates in addition to the main control system equipment. Estimating
procedures for some common scope adders are described here.
3.7.2.1	Ducting. Direct capital costs for ducts are estimated using the
equation described in Section 2.2 for new plants. The duct costs are then
multiplied by the retrofit factor from Section 3.7.1 to estimate the direct
capital cost of ducts for existing plants. Depending on chimney and APCD
tie-in difficulties at the model plant, the ductwork retrofit factor may be
different than that chosen for the APCD.
3.7.2.2	Stacks. The installed capital cost of stacks 1s estimated from
equations developed for industrial boilers.^ Total direct and Indirect
capital cost data from one manufacturer were correlated into separate
equations for lined and unlined stacks, and for stacks larger and smaller than
3.7-1

-------
TABLE 3.7-1. SITE ACCESS AND CONGESTION FACTORS FOR
RETROFITTING APCD EQUIPMENT AT EXISTING PLANTS3
Retrofit
factor
Congestion
level
Guidelines for selecting retrofit factor
1.02
Br.re Case
Interferences similar to a new plant with adequate
crew work space. Free access for cranes. Area
around combustor and stack adequate for standard
layout of equipment.
1.08
Low
Some aboveground interferences and work space
limitations. Access for cranes limited to two
sides. Equipment cannot be laid out in standard
design. Some equipment must be elevated or
located remotely.
1.25
Medium
Limited space. Interference with existing
structures or equipment which cannot be relocated.
Special designs are necessary. Crane access
limited to one side. Majority of equipment
elevated or remotely located.
1.42
High
Severely limited space and access. Crowded
working conditions. Access for cranes blocked
from all sides.
Reference 4.
3.7-2

-------
5 feet In diameter (stacks larger than 5 feet in diameter and 100 feet tall
are normally tapered). For a lined acid-resistant stack, the equations for
direct and indirect capital cost, updated to December 1987 dollars, are:
Cost, 103 $ = [26.2 + 0.089 x (HJ x (1 + 4.14 D)] for D > 5 ft and
Cost, 103 $ = [26.2 + 0.080 x (H) x (1 + 4.33 D)] for D < 5 ft
For an unlined stack, the equations are:
Cost, 103 $ ป [26.2 + 0.0625 x (H) x (1 + 2.59 D)] for D > 5 ft and
Cost, 103 S - [26.2 + 0.087 x (HJ x (1 + 2.20 D)] for D < 5 ft,
where
H = stack height, ft and
D ~ stack diameter, ft.
To estimate the total capital costs, the direct and indirect costs are
increased by 20 percent to account for contingency.
3.7.2.3 Demolition and Replacement. Costs for demolition of existing
buildings required for installation of new APCD equipment are estimated
according to EPRI guidelines.^ In general, demolition cost is estimated by
multiplying the amount of material to be demolished or moved (i.e., square
feet of building space) by an appropriate cost factor in Reference 5. These
estimates are made on a plant-specific basis as needed. Costs for demolition
or replacement of existing equipment such as ductwork, fans, and ESP's are
assumed to be the same as the costs for installing the same equipment.
3.7-3

-------
REFERENCES
1.	Stearns Catalytic Corporation. Retrofit FGD Cost-Estimating Guidelines.
Prepared for Electric Power Research Institute. Palo Alto, CA.
Publication No. CS-3696. October 1984.
2.	Reference 1. pp. 4-1 to 4-3.
3.	Bowen, M.L. and M.S. Jennings (Radian Corporation). Costs of Sulfur
Dioxide, Particulate Matter, and Nitrogen Oxides Controls on Fossil
Fuel-Fired Industrial Boilers. Prepared For the U. S. Environmental
Protection Agency. Research Triangle Park, NC. Publication
No. EPA-450/3-S2-021. August 1982. p. 2-11.
4.	Reference 1. p. 5-4.
5.	Reference 1. pp. 4-9 to 4-14.
3.7-4

-------
3.8 DOWNTIME COSTS FOR RETROFIT MODIFICATIONS
In many situations, the retrofit equipment cannot be installed during a
normally scheduled maintenance shutdown and thus will result in additional
downtime and loss of MWC revenues during retrofit. The loss of revenue is
mainly from: (1) a loss of steam and/or electrical sales and (2) a loss of
tipping fees from receiving MSW. It is assumed that the work force at the
facility would be productive during the downtime period and that the cost of
idle workers can be ignored.
To estimate the downtime costs due to loss of revenue, the length of
downtime required to install the APCD must be estimated. Table 3.8-1 presents
ranges of unit downtimes required to apply combustion control and install
various APCD's on existing MWC facilities. Once the downtime period is
estimated, Sections 3.8.1 and 3.8.2 present the procedures used to estimate
costs for the loss of steam and electrical sales and the loss of tipping fees,
respectively. Costs attributed to the loss of revenue are treated as a
one-time cost that is annualized over the useful life of the APCD.
3.8.1 Procedures to Estimate Loss of Steam and Electricity Sales
3.8.1.1	Loss of Steam Sales. To estimate the costs of loss of steam
during downtime, the amount of steam that would have been generated during the
downtime period is multiplied by a sales price for steam (typically in dollars
per 1,000 lb of steam). A typical steam price in December 1987 dollars is
$5.50/1,000 lb of steam.^ For example, the lost revenues from steam sales for
a facility normally producing 10,000 lb/hr of steam are $1,320 per day (i.e.,
$5.50/1,000 lbs steam times 10,000 lbs steam/hr times 24 hours).
3.8.1.2	Loss of Electricity Sales. The cost of lost electricity sales
is estimated by multiplying the amount of lost electricity generation by the
electricity price. The electricity price is assumed to be the same as the
electrical cost rate used in this report to estimate APCD electricity costs
($0.046/kWh in December 1987 dollars). Applying this procedure, the cost of
lost electricity sales for a facility with a 1,000 kW capacity turbine is
$1,100 per day (i.e., $0.046/kWh times 1,000 kW times 24 hours).
3.8-1

-------
TABLE 3.8-1. DOWNTIME REQUIREMENTS IN MONTHS'
Combustor
downtime
(months)
Combustion Modifications
ESP-Rebuild
ESP-Add plate area
Retrofit Spray Dryer
Retrofit Sorbent Injection
Humidi fication
0.Z5-4
1-2
0.5-11
l'
0.5-1*
0.25-1
aReference 2.
^If there are significant space limitations, up to an additional
6 months could be required.
3.8-2

-------
3.8.2 Prccsdures to Estimate Cofts from Loss of Tipping Fees
Downtime costs associated with loss of tipping fees are estimated by
multiplying an appropriate tipping fee (typically $25/ton) by the increase in
tonnage of solid waste disposal. The increase in solid waste is the
amount of feed that would have been reduced in the combustor plus the fly ash
that would have been collected by the existing PM control device, if the
combustor were operating during the downtime period. For example, if the
weight of MSW fed to a 100 tpd combustor is reduced by 75 weight percent
during combustion (including bottom ash and fly ash), the tonnage of solid
waste to be disposed would increase from 25 tpd during combustor operation up
to 100 tpd when the unit is shut down. The increase in solid waste disposal
costs is approximately $1,880, based on a S25/ton tipping fee (i.e., $25/ton
times 75 tons per day).
3.8-3

-------
REFERENCES
Electric Power Research Institute. TAC-Technical Assessment Guide
(Volume 1: Electricity Supply]986). Palo Alto, CA. EPRI
No. P-4463-SR, December 1986. p. B-4.
Memorandum from White, D.M. and J.T. Waddell, Radian Corporation, to
R.E, Myers, EPA/1 SB. June 3, 1988. Time Requirements for Retrofit of
Particulate Matter (PM), Acid Gas, and Temperature Control Technologies
on Existing Municipal Waste Combustors (MWC's).
3.8-4

-------
TECHNICAL REPORT DATA
fPlease read Jnsimcnons un ihe reverse bejore comptelingi
1. REPORT NO.
EPA-450/3-89-27a
3. RECIPIENT'S /^CESSION fclO_
>6 90 lo 4 0 4 0 MS
4. title andsubtitle
Municipal Waste Combustors - Background Information foi
Proposed Standards: Cost Procedures
S. REPORT DATE
August 1989
6. PERFORMING ORGANIZATION CODE
7. AUTHOR(S)
8. PERFORMING ORGANIZATION REPORT NO.
9. performing organization name and address
Orrice of Air Quality Planning and Standards
U. S. Environmental Protection Agency
Research Triangle Park, North Carolina 27711
IC. PROGRAM ELEMENT NC
ii contract/grant no
68-02-4378
12. sponsoring agency name and aodress
DAA for Air Quality Planning and Standards
Office of Air and Radiation
U.S. Environmental Protection Agency
Research Triangle Park, North Carolina 27711
13. TYPE OF REPORT AND PERIOD COVERED
F inal
14 SPONSORING AGENCY CODE
200/04
15 SUPPLEMENTARY NOTES

16. ABSTRACT
Cost Procedures for the costing of new and existing municipal waste combustor
facilities and associated equipment are presented. Cost procedures are developed
for combustors, heat recovery equipment, humidification equipment, air pollution
control devices for the reduction of particulate matter and acid gas emissions, and
continuous emission monitoring equipment.
Costs in this report are divided into capital costs, operating and maintenance
costs, and annualized costs. Costs associated with retrofitting existing facilities
are also presented.
17,	KEY WORDS AND OOCUMENT ANALYSIS
a. DESCRIPTORS
b. 1 DENT1 F 1E RS/OPEN ENDED TERMS
c. COSATI Field,'Croup
Air Pollution
Municipal Waste Combustors
Incineration
Pollution Control
Costs
Air Pollution Control
13B
18. DISTRIBUTION STATEMENT
19. SECURITY CLASS /This Report;
Unclassified
21 NO. CP PAGES
I *
w
20. SECURITY CLASS ( This page /
Unclassified
22. PRICE
EPA Form 2220-1 (Rซป. 4-771 previous edition is obsolete

-------