-------
APPENDIX F
HYDROCARBON GUIDE
(reproduced with permission from Aerofill, Ltd.)
F-l
-------
Hydrocarbon Guide
The Aerosol fillers guide to using
Hydrocarbon PropeUants
Published in the interests of safe practice by Aerofill Ltd.
-------
M&OflLL
CONTENTS
INTRODUCTION 2
Section 1 Preliminary Considerations 3
Section 2 Notification of Authorities 4
Section 3 Hydrocarbons as Aerosol propellants 5
Section 4 Hydrocarbon Propellant supply 8
Section 5 Small Scale Storage of Hydrocarbon
Propellant 10
Section 6 Bulk Storage of Hydrocarbon Propellant 13
Section 7 Solvent Storage and Use
19
Section 8 Aerosol Filling
Section 9 The Laboratory and Pilot Line
Section 10 Disposal of Waste and Scrap
Section 11 Finished Goods
22
29
32
34
Section 12 Safety and Fire Precautions
35
Section 13 Further Information
39
Bibliography
Aerofill Ltd acknowledges the inclusion of photo reproductions
by kind permission ol:
AEROSOLS INTERNATIONAL LTD
CALOR GAS LTD
40
F-3
-------
INTRODUCTION
2
This handbook has been designed to act as an easy reference book and
guide to aerosol fillers using or considering the use of hydrocarbon
propellents. It is not intended to replace reference to the relevant authorities
and their publications but to highlight their relationship to aerosol filling.
The storage and use of hydrocarbons is governed by various Factory Acts,
statutes and regulations most of which relate, wholly or in part, to its use in
the aerosol industry. In addition the Health and Safety at Work Act places
responsibility on the employer and his mangement to operate in a manner
that safeguards his employees and the public.
The information in this handbook provides a link between the various
statutory regulations, codes of practice and other trade and industrial
publications, indicating how these relate to the storage, handling and
supply to aerosol filling lines of hydrocarbon propellants. It also covers the
safe installation and operation of equipment in the factory and related
matters such as finished product storage and waste disposal. The handbook
is a guide not a definitive instruction manual since each installation will vary.
However, the information given here may help save time, money, eflorl and
risk.
Although the information is biased toward current rules and regulations in
the UK and the experience of Aerofill and its customers, it may be assumed
that, with minor variations, the contents of this handbook will apply to any
installation. Care has been taken to investigate all sources of regulations
which may effect hydrocarbon filling installations but all work should be
carried out with due reference to the authorities indicated at various points
in the text.
The parameters of this handbook have been fixed to deal only with
hydrocarbon propellants and related installation operation and usage. No
attempt is made to argue the case for hydrocarbon propellants or to deal
with formulations which are outside of Aerofill Ltd's field of activity.
Aerofill Limited
Printing House Lane
Hayes
Middlesex UB3 1AP.
Tel: 01-848 4501.
F-4
-------
Section 1
PRELIMINARY CONSIDERATIONS
Hydrocarbons are flammable and explosive, however, if handled and used
properly they offer the aerosol filler several advantages over other
propellants in certain circumstances and formulations. As expected, where
any new undertaking is planned using propellants in the form of
Liquified Petroleum Gases (L.P.G.) with their hazardous possibilities,
there are certain authorities to be consulted. However, the feasibility of
installing and using hydrocarbons can be determined by examining
certain fundamental requirements.
First Is there room for the storage tanks?
L.P.G. storage must be isolated, fig. 1 shows the
required separation distances for bulk storage
above and below ground. Fig 2. shows some
examples of how to apply these separation
distances. Storage is dealt with in more detail in the
relevant chapters.
Second How much propellent will be needed on a dally
and weekly basis?
(Hydrocarbon fill in each can) X (the number of cans
to be filled) X (the number of days between deliveries
and the minimum level to be maintained in the tank.)
Third Are the factory premises adaptable to hydrocarbon
filling?
Space, as indicated by the above, is likely to be a
critical factor and other matters are highlighted in the
following chapters relating to layout, operation and
safe usage.
If these considerations can be satisfied, a deeper study can commence in
consultation with the authorities and suppliers.
F-5
-------
Figure 1.
Separation Distances for Bulk Storage Vessels.
Storage Categories Siting Categories - Distance in Metres
Water Capacity of
Nominal
from Building/Property
Between Vessels
Individual Storage
LPG
Line or Fixed Point of
Vessels in Litres
Capacity
Ignition
ITonnes)
(Above
Under
(Above
(Under
Ground)
Ground)
Ground)
Ground)
Up to 450
0-0.2
None
3
None
1.5
Over 450 to 2.250
0.2-1.0
3
3
0.9
1.5
Over 2.250 to 9,000
1-4
7.5
3
0.9
1.5
Over 9.000 to 135,000
4-60
15
3
1.5
1.5
Over 135.000 to 337,500
60-150
23
5
1.5 or J sum of
1.5
diameter of adjacent
Over 337,500
150-
30
5
vessels, whichever
is the greater.
Storage
Siting Categories - Distance in Feet
Categories
Water Capacity of
Nominal
From Building/Property
Between Vessels
Individual Storage
LPG
Line or Fixed Point of
Vessels in UK Gallons
Capacity
Ignition
(Tons)
(Above
(Under
1Above
(Under
Ground')
Ground)
Ground)
Ground)
Up 10 100
0-0.2
None
10
None
5
Over 100 to 500
0.2-1.0
10
10
3
5
Over 500 to 2.000
1-4
25
10
3
5
Over 2,000 to 30,000
4-60
50
10
5
5
Over 30,000 to 75,000
60-150
75
15
5 or ^ sum of
5
diameter of adjacent
Over 75,000
150-
100
15
vessels, whichever
5
is The greater.
Note 7: The maximum total water capacity of all storage vessels in a group must not be greater than three times the water capacity of
the largest vessel permitted in any particular siting category. The maximum number of vessels in a group must not exceed six.
2: For underground storage vessels up to 2,250 litres (500 UK gallons) water capacity, the distance from the valve assembly on
the manhole cover and the loading/unloading point to the building/property line or any fixed source of ignition must be at least
3m. 110 ft.); for vessels above 2,250 litres 1500 UK gallons), this distance must be at least 7.5m. (25 ft.).
The information given in this chart is based on the Health & Safety Executives' Code of Practice for the Storage of LPG at Fixed
Installations. The Nominal Capacities listed are based on the Specific Gravity of Butane 30 at 0 57 S.G. Conversion must be
made for Propane or intermediate blends.
Separation Distances for the Storage of Cylinders
Min. Separation Distance to Boundary, Building or
Fixed Point of Ignition.
From Nearest Cylinder (where From Radiation
no rsdistion wall exists) Wall where provided.
1 metre Nil Empty & Full
3 metres 1 metre Cylinders must
4 metres 1 metre be separated
within the
compound.
Although the Code of Practice for keeping LPG in Cylinders and similar containers lilts greater LPG capacities we feel that bulk storage
should be given urgent consideration for capacities beyond 4,000 KG*.
Total Storage
LPG Capacity
.50-100 KG
above 100-1,000 KG
above 1,000-4,000 KG.
F-6
-------
fig J
SITE BOUNDARY
SITE BOUNDARY
SITE BOUNDARY
10
in
m
10
FUTURE BUILDING LINE
5.1 Layout lor 20tn Tank showing
extent of separation distance
5 3 In the event that there is
insufficient separation distance
20 th]
NEW BUILDING
5 2 Additional 20tn Tank installed
whilst maintaining separation distance
T)
I
-J
SITE BOUNDARY
5 3 In the event that there is
insufficient separation distance
a 2nd tank may be accommodated
with the use of vertical tanks
site boundary
z
CO
>
tv
p
ur*
CM
Or
n
*2
x
15
BOILER.(J. SERVICES
lOO,
i oa
|_oo
PRODUCTION
WAREHOUSE
office
1
PRUM5
15
-I
3
15
5 4 Although required separation distance has
been satsified the tank is enclosed by
existing buildings with possibility of future
building beyond site boundary giving rise to
poor natural ventilation
5.5 Good layout with tanks isolated with good natural ventilation
& room for extension. Required separation from highly flammable liquids
is observed whilst boiler house & services are well away from tanks
All dimensions are Metric
Examples of tank installations showing separation distances
-------
- 3Mr
Section 2
NOTIFICATION OF AUTHORITIES
Having made your own evaluation of the feasibility, practicality and
desirability of using hydrocarbon propellants you cannot proceed without
notifying the relevant authorities. Knowledge of your requirements and
intentions prior to consulting the authorities will assist and expedite matters.
The authorities you are obliged to consult are:
a) HM Factory Inspectorate
The Factory Inspectorate are divided into areas and within each area
there are Specialist Field Consultant Groups to advise the Local and
Area Inspectors. Especially where there are projects calling for special
consideration, a consultant may be brought in to advise and assist
the company in planning. The Inspector will normally provide
considerable assistance and interpret regulations as they apply to your
particular site. Matters will be expedited if you have scale layout
drawings of your proposal and general data available.
Your local inspector should be known to you with his address on either
your Factory Register or your copy of the Abstract of the Factories Act.
b) Local Planning Authority
Changes and alterations effecting the factory site may need Planning
Permission and in any case the Planning Authority should be informed
of the creation of a hazardous area. The work will have to conform to
Building Bye-laws and regulations with inspection during progress.
Again expediting will be assisted by scale layout drawings.
c) The Fire Prevention Officer
The Fire Prevent ion Officer lor your district should be consulted, usually
attached to the local fire station but sometimes located at the area
headquarters. The Fire Prevention Officer has reporting responsibilities to
H M Factory Inspectorate and his co-operation and clearance is
necessary to obtain the Certificate of Fire Exit' required by the Factories
Act. He will provide recommendation on fire alarms, fire points,
ventilation and the storage and use of Petroleum substances and
Highly Flammable Liquids. He will require information on layout,
quantities of propellant to be stored, storage of finished product and
intended fire precautions.
d) Insurance Company
Advisable, though not obligatory, is early consultation with your insurers
concerning risk cover and precautions they would wish to see.
Compliance with the Fire Prevention Officer's recommendations or
installation by your own choice of a sprinkler system may result in a
favourable premium adjustment.
F-8
-------
e) Works Safety Committee
Under the Health and Safety at Work Act you are obliged to discuss
the project with the Works Safety Committee if you are a company
with official Trade Union representation. If Trade Union recognition
is not established, it is still advisable to consult your employees
especially as you are obliged to instruct and train your employees in
working with hazardous materials.
Section 3
HYDROCARBONS AS AEROSOL
PROPELLANTS
Hydrocarbons comprise a family of petroleum fractions and in respect of
aerosol propeilants we are concerned with propane (Cs He) and butane (C<
Hie) produced generally to British Standard 4250:1975. The hydrocarbon
gases are obtained from three sources: natural gas wells, gas issuing from
crude oil wells and the 'cracking' of crude oil. In the UK, at present, butane
and propane are derived from 'cracking' crude oil, that is breaking it down
into its constituent product or fractions.
Both propane and butane are gases at normal ambient temperatures, but are
readily liquified by the application of relatively low pressures and stored in
bulk vessels at ambient conditions in their liquified state (Liquified
Petroleum Gas). The ratio of gas volume to liquid at standard temperature
and pressure is approximately 274 and 233 to 1 for propane and butane
respectively. This will vary as the gases are blended. The density of the liquid
gas is approximately half that of water whilst the density of the vapour gas is
approximately 1V4 and 2 times that of air.
Liquified Petroleum Gas will burn where its concentration in air lies between
the narrow range of approximately 2% to 10% of vapour gas to air by volume.
Because the gas vapour is heavier than air it will accumulate at low levels in
enclosed and unventilated areas and, since it has a high gas to liquid volume
ratio, small quantities in air can produce an appreciably large volume of
potentially flammable mixture. These may be ignited by any naked flame or
hot surface as well as more subtle ways, such as incendive sparks,
unprotected lights, non-flameproofed electrical equipment and static
electricity.
5
F-9
-------
JiaofJii
Hydrocarbons are therefore hazardous and must be handled and used with
care and attention to safety and by competent and properly trained persons,
as can be seen from the stress placed in the Codes of Practice and attendant
publications indicated in this handbook.
Stanching
As a safety precaution, the hazardous presence of hydrocarbon gas is
signalled by a stenching agent (ethyl mercaptan sulphur or dimethyl
sulphide) added during the production process. All hydrocarbon gas
producing plants make this addition during the process in compliance with
BS 4250. Their process is irrevocably committed and the plant therefore
contaminated by the stenching agent.
Since the aerosol industry's requirement is small in relation to total
hydrocarbon production, non-stenched supply is not commercially viable.
It therefore falls to others to offer a de-stenching or sweetening and
blending process and to arrange distribution to aerosol fillers in
uncontaminated cylinders and bulk tankers. Removal of the stenching agent
is normally by absorption into a molecular sieve.
There are certain special mixtures and blends supplied in relatively small
quantities for use in high grade cosmetic and toi letry formulations; research
and development; and pharmaceutical and medical requirements. These
gases are generally the technically superior ISO-butanes in the unstenched
condition (imported) with de-stenched propane added to obtain the
required vapour pressure. The odour is less noticeable than normal de-
stenched butane and propane.
One of the principal drawbacks from a formulation point of view is the odour
of the commercially available hydrocarbon propellant even after de-
stenching, especially for cosmetic formulations. The source of the crude oil,
over which the propellant suppliermay have little control, may influence the
effectiveness of the de-stenching process.
Grades
To formulate for aerosols using hydrocarbons as a propellant and to cover
the wide range of product requirements, it is necessary to use propane and
butane, or mixtures of both, to produce the required vapour pressure at
25°C (70° F). It is also necessary, at the same time, to identify the grade or
blend of propellant.
The most common grades of hydrocarbon propellant currently in use in the
UK are listed below. As will be seen, these are identified by the vapour
pressure (psig) at 25°C (70°F), a procedure which is similar to that used in
the USA and Canada.
F-10
6
-------
Hydrocarbon propellent 30 = Vapour pressure 2.05 bar (30psig) at 25°C
Hydrocarbon propellant40= mix to produce V.P. 2.72 bar (40psig) at 25°C
Hydrocarbon propellant 48 = mix to produce V.P. 3.26 bar (48psig) at 25° C
Hydrocarbon propellant 110 = vapour pressure 7.5 bar (1 lOpsig) at 25°C
No attempt has been made in this handbook to detail the physical properties
of the various hydrocarbons or the specification of each grade. This
information may be obtained from the propellant suppliers along with
necessary toxicological data.
The foregoing paragraphs relate mainly to UK suppliers of hydrocarbon
propellant. Imported sources are available for butane/propane mixtures, but
the fact that they are not commonly used is probably a reflection of their
price where transport and distribution is a dominant factor. ISO-butane is
not available from UK based refining and must therefore be imported.
7
F-ll
-------
Fig 3
\E7
&
o
lo
5
5
O
0s
CM
£
£
o
144 PIA
LIQUID TAKE-OFF
TARE 46-75 K§6
TAKEN FROM CALOR LTD. DR^ 1455/2
HYDROCARBON CYLINDER
47 K$s CAR6CITY
F-12
-------
O
& ^
3952
11'
8
£ *
^ r
__
152
6'
137O
4' 6"
/52
6'
2 TONNES HYDROCARBON TANK APPROX 3850 LITRES
254
10'
$ &
to c
Vs>
o ^
^ • «l
^ —
4774
15'6*
8534
28'
12 TONNES HYPRO CARBON TANK APPROX Z5,000 LITRES
HYPR0CAR30N TANKS
Z $ 12 TONNES CAPACITY
F-13
-------
Section 4
HYDROCARBON PROPELLANT SUPPLY
Normal butane and propane mixtures to the designations as listed in Section
1 and supplied in the destenched condition are obtainable from Calor Gas
Ltd., Calor House, Windsor Road, Slough SL1 2EO, telephone Slough
23624, and their regional offices.
The destenching process is carried out at their works at Millbrook,
Southampton, from where U.K. distribution is carried out in cylinders and
bulk tankers of up to 15 tonnes capacity.
Calor supply in portable, refillable 47kgs (104lbs) cylinders for laboratory,
pilot plant and small scale production use (fig 3) and 2 tonnes and 12 tonnes
capacity tanks (fig 4). The cylinders are supplied on a 'free loan' basis, but
the 2 and 12 tonnes tanks are supplied on a rental basis, the cost of the
installation, civil engineering, pumps and pipework being totally charged to
the client to become his property.
Although Calor Gas Ltd. offer a full consultancy service for any installation
of hired tanks and for tanks of larger capacity, or installations calling for
underground tanks, these projects must be financed by the client.
Calor Gas Ltd. maintain their own laboratories at Weybridge, Surrey with a
section devoted to aerosol formulations. The company is an active member
of British Aerosol Manufacturers Association and participates in its
technical activities.
Because of technical and commercial constriction, standards for odour are
difficult to establish. The origin of the feedstock will determine the degree to
which the propellant may be sweetened and the size and capacity of the
molecular sieve filter for a given flow rate. Odour acceptance will depend
upon agreement with the supplier and may be monitored by the critical
opinion of the chemist in charge or by agreed standards of repeatability
based on gas chromotography.
After these standards have been agreed it may well be that the user may wish
to install an inline destenching column for further security. However, a flow
capacity related to the weight of molecular sieve will need to be established
by trial.
Molecular sieves are synthetic alumino silicate crystal powders which range
from 1 to 3 microns in diameter and are bound together to form pellets
1.5mm in diameter. The size and position of the metal ions in the crystal
controls the effective diameter of the channels that interconnect the millions
of tiny cavities in each crystal. This micro "sponge like" form permits the
absorption of the molecules of sulphur compounds.
F-14
-------
£
5
O
rsi
CVJ
3
B O.C. CYLINDER WOP
CONTENTS 50 ka
TARE WEIGHT 55 ka
3dO MM
PIA.
¦*
15'
2110 mm APPRO*
83'
>-
\
/
>
1
\
/
\
/
<
0
\
/
s
ruLi.
/ LTLT nl
s
Jo
rO
1
0
'II
\
*1-
CO
/!!
\
/ 11
\
/ U
\
>
'
B.O.C. DRUM TANK
CONTENTS 385 kg
\ TARE WEIGHT 690 m
Valve 4, termination £ a&a . n? 300 flange
OUTLINE I? DETAILS FROM INFORMATION FROM
BRITISH OXYGEN C* LTD. SPECIAL MASSES
F-15
HYDROCARBON CYLINDERS
50 k« $ 3&5« DRUM TANK
-------
The saturated and spent molecular sieve must be regenerated or discarded
under controlled conditions to enable the hazardous hydrocarbons to safely
disperse and the noxious smell of the sulphur compounds not to cause
offence.
Special blends and mixtures of unstenched ISO-bulane and destenched
propane are supplied by B.O.C. Ltd., Special Gases, Deer Park Road,
London SW19 3UF, telephone 01-542 6677.
As stated in Seclion 3, special grades are supplied for those who require a
technically superior specification which is 99% pure, used principally where
there is a need for less odour and residual contamination. These grades may
be preferred for high class cosmetics and toiletries, research and
development and pharmaceutical and medicinal formulations.
Whilst these grades are more expensive and mostly supplied in returnable
refiliable cylinders of 50kg capacity, they can be supplied in 385kgs
refillable drum tanks (fig. 5). Should a requirement demand a bulk
installation, B.O.C. Ltd., may be willing to investigate the feasibility.
F-16
9
-------
H•produced from
b««1 avails* eopy
Portable cylinders containing propane located outside a building
and connected to a change over valve and pressure reducing valve to
supply gas to appliances within the building through fixed piping.
15 tonnes Propellant Tanker
F-17
-------
wHaofJL!
Section 5
SMALL SCALE STORAGE OF
HYDROCARBON PROPELLANT
Laboratory or pilot line operation and certain small filling operations may
no( require or accommodate even a small fixed bulk storage installation. In
these instances cylinder and drum tank storage may be considered.
Refillable, 47kg (1041b) cylinders are the most common, however their
limited capacity should be taken into account — at an average fill size four
cylinders manifolded together will fill approximately 2,000 aerosols.
For an aerosol filling installation using cylinders, sections of the 'Highly
Flammable Liquids and Liquified Petroleum Gases Regulations 1972" and of
the Health and Safety Executive's 'Code of Practice for the Keeping of
Liquified Petroleum Gas in Cylinders or SimilarContainers' will apply. Other
requirements may be made by local bye-laws, trade recommendations and
good safety sense.
The use of cylinders containing hydrocrabons for aerosol filling can be
divided into tv.o separate categories — Cylinders awaiting use and
Cylinders in use.
a) Cylinders Awaiting Use
Cylinders awaiting use should be stored in open air in a well ventilated
position. The cylinders may be full awaiting use orempty awaiting collection
by the supplier. The part of the Health & Safety Executives 'Code of Practice'
that refers to storage deals mainly with large quantities of cylinders or
cartridges as may be stored in a distribution depot and not an aerosol
factory. Part 2 of the code deals with open air storage areas whilst other
parts refer to safe handling and procedures. For Aerosol use the quantity of
cylinders is not likely to be very large, the total stock required should be
fixed and from this the separation distance governing the area can be
obtained from fig 1. Any boundary, building or fixed source of ignition must
be beyond these distances which may be extended by H.M. Factory
Inspector upon examination of the site and the overall layout of the factory.
In certain circumstances a radiation wall may be permitted to overcome the
problems of borderline situations.
The area should be identified and secured by a chain link fence at least 2
metres high (6 feet) with two outward opening gates. All cylinders should be
stored on their base and in an upright position with protective valve cap in
position. Empty and full cylinders should be segregated and identified.
The area shall be free of drains and at least 3 metres (10 feet) from any other
cylinders containing oxygen, hydrogen, materials of a corrosive or toxic
nature or highly flammable liquids. No combustible materials shall be kept
within the area.
F-18
10
-------
uHrtofliA
Where 385kgs (V4 ton) drum tanks are used, a gantry type lifting tackle may
be needed to unload the tanks, whilst cradle trolleys are used for moving to
point of use. Use chocks to secure the tank.
b) Cylinders In Us*
Cylinders in use, except for special laboratory use and under strict
conditions should not be used inside a building. They should be set up for
use in the open air possibly against an outside wall in a well ventilated place
at least 3 metres (10 feet) from any fixed source of ignition, other cylinders
and Inflammables as stated in a).
Cylinders may be manifolded together, in an approved manner with
changeover valves and non-return valves in the pipeline from cylinder to
manifold to prevent flow from one cylinder to another with the possibility of
danger resulting from high pressures.
Manifolded cylinders may be stood on mechanical platform scales as an
easy indication of use of hydrocarbon from gross and tare-weights. The
cylinders should be secured in the upright position with a supporting cradle
or harness chain around the bodies of the cylinders.
The key or shut-off valve knob should not be removed and it is
recommended that a notice be fixed around the neck of the cylinder in use:
vis
'Cylinder in use — shut-off valve open — do not
tamper with or close except in an emergency without
reference to '
(enter name of suitably qualified and competent person).
The position should be provided with an earth point with earthing strips and
provision for earth continuity from cylinder through to the filling equipment.
Empty cylinders and those not connected to the manifold should be
returned to the storage area for safe keeping.
The cylinder connection to the manifold may be flexible with self seal
coupling. It is preferred that the fixed end be protected by a valve that cannot
freeze open in the event of gross leakage. From the manifold to the filling
equipment there should be rigid fixed pipework in steel to appropriate
British Standard (copper should only be used for vapour lines). Note: under
no circumstances should plastic air line hose and compression fittings be
used.
11
F-19
-------
The pipe route to the filling area should be planned to miss steam pipes,
electrical cables and distribution should be as safe and direct as possible —
planned in co-operation with H.M. Factory Inspector and the Fire Prevention
Officer. Pipes should be identified in compliance with British Standards and
direction of flow indicated. All valves should be fire safe and approved for
L.P.G. Pressure relief valves, vented safely, should be strategically
positioned to prevent any possibility of hydrostatic pressures building up in
the pipework with volume changes of gas due to increases in ambient
temperatures when plant is idle.
Separate pipelines should be installed for each grade of propellant to be
used with proper procedures and description laid down. It is safer to change
over pipelines than purge a single pipeline each time a change of propellant
is made.
Good safety procedures should be carried out by competent persons
properly trained in accordance with the appropriate parts of the relevant
codes.
F-20
-------
15 tonnes Tanker in process of unloading
F-21
-------
Fig. 6.
CD
CD
O
r*
i
L.
¦T
.J
is
z
NOMINAL
BUTANE
CAPACITY
LENGTH
DIAMETER
B
HEIGHT
C
CENTRES
D
20 11m 2.25m 2.6m 8.00m
TONNES 36' 7' 6" 8' 6" 26'
25 12.25m 2.5m 2.25m 8.00m
TONNES 40" 8' 9' 26*
30 7m 3.65m 4.00m 2.5m
TONNES 23' 12' 13' 8'
50 10.25m 3.65m 4.00m 4.25m
TONNES 34' 12' 13' 14'
ALL DIMENSIONS ARE APPROXIMATE FOR EACH CAPACITY AND
MAY VARY WITH MANUFACTURERS DESIGNS
HYDROCARBON TANKS LARGE CAPACITY
-------
Section 6
BULK STORAGE OF HYDROCARBON
PROPELLANT
Experience has shown that the conditions for a bulk installation vary widely
from site to site, the information given in this section therefore represents
acceptable practice and basic guidelines
The size of any bulk tank installation will depend on seven basic
considerations:
a) The maximum daily off-take required.
b) The number of different propellant grades required.
c) The size of tanker delivery and ease of access.
d) The minimum quantity required in the tank to ensure good gravity head
for pumping.
e) The time taken to process an order and receive deliveries.
f) Sudden demand and overtime working potential requirements.
g) Allowance for future increases in demand.
When the approximate overall storage capacity required has been
determined, dimensions can be obtained from fig. 6 which shows nominal
tank sizes. It should be noted that the maximum number of tanks
permissable in a group is six.
Tanks used should be designed for L.P.G. storage in compliance with B.S.
1515:1965 for butane at a working pressure of 7 bar (100 psig) and propane
at 15 bar (220 psig) both at 37.8°C (1008F). In view of the increase in
available grades and developments in formulation work, the use throughout
of propane rated tanks may be considered a wise investment.
The Code of Practice for the 'Storage of Liquified Petroleum Gas at Fixed
Installation' published by the Health and Safety Executive lays down
separation distances which will be determined by the size of the tanks
chosen. (The data in fig 1 differs from the code only by the inclusion of
metric units and the converson of water capacity to nominal L.P.G. capacity.
Water capacity refers to the total fill of the tank whilst L.P.G. capacity must
allow a headspace of 15% for expansion due to increases in ambient
temperature.)
The 'separation distance' is the minimum permitted distance from the tanks
to the site boundary, a building or future building line and any fixed source
of ignition. To this may be added the distance from the hose connection for
tanker unloading, the unloading area being classified as a hazardous area to
13
F-23
-------
ftoad tanker vehicle unloading bay, and the manually operated fixed water drenching system over it.
-------
P.
n
1
n
I '
:
V
>
J
i
t
I
(
—
)
i
15
LEN^FH OF TAN*
— "pp*
_N»
o
I 6
TANK TO INSIDE. 01 FLNCE
u
CONCRETE RAFT
^J
DOUBLE TANK INSTALLATION
SIMPLE TANK. INSTALLATIONS
LADDER & CATWALK IS NORMALLY MOUNTED
AROUND THE MANLID FOR SAFETY. FOR
CLARITY & TO SHOW CONNECTION LADDER
& CATWALK IS SHOWN ADJACENT
TO MANLID
1 Contents Gauge
2 Manlid 560mm dia
3 Pressure Gauge Connection
4 Combined Safety Relief Valves
Vent Pipes & Rain Caps
5 Vapour Return (Balance) Connection
6 Liquid Return from Supply Pump
7 Thermometer Connection
8 Tank Earth Point & Earth Rod
9 Liquid Fill Valve
10 Liquid Supply to Pumps & Filling Lint
11 Fixed Liquid Level Gauge
SEPARATION DISTANCE EXTENDS FROrt
SIDES & ENDS OF TANK(S)
6 RAVEL
CHAIN LHK FlflCt
overall dimensions op tank c position of mam m a Muucmnuc.
VAW ACCORDING TO MAHUF^TWERS PESfGN * COmECT,0m
All dimensions are Metric.
2S0 mm WKWU
360 mm H1^
SITE OUTUHE $ TANK 0LTWL6
TYPICAL FOR 25/50 T0NNE& Tf&>
-------
Zone One up to 1.5 metres (5 feel) and Zone Two up to 4.6 metres (15 feet).
As both Zones demand flameproof electrical equipment, it should be
interpreted that the 4.6 metres should be entered into the separation
distance calculations, as such it would only extend the layout for tanks
under 1 tonne nominal hydrocarbon capacity.
Under certain circumstances the separation distances may be reduced by
the inclusion of a radiation wall or by the installation of a fixed water spray
system. Dispensations of this nature should be sought from the Factory
Inspectorate and the Fire Prevention Officer. Equally, however, distances in
excess of those given in fig. 1 may be required If the site lacks good natural
ventilation.
Any calculations must also take into account the siting of existing or
proposed tanks for solvents or other highly flammable liquids since these
should have a separation distance of 15 metres (50 ft) from any hydrocarbon
tank farm.
Finally the layout should provide access for tankers of up to 15 tonne
capacity using discharge hoses of 9 metres effective length. A turning circle
of 16 metres or a reversing space of 8 metres long must be provided for the
tankers as they are not permitted to reverse into public highways.
Above Ground Storage
The site for above ground vessels should be as level as possible, free of
drains, low lying depressions, pits or water courses. The maximum number
of permitted tanks in a group is six and the total combined water capacity
should not exceed three times the capacity of the largest permitted vessel in
the group. Tank sizes are shown in fig. 6 although dimensions may vary from
one manufacturer to another.
There should be a concrete raft sloped to drain any spillage from beneath
the tanks to a safe evaporation area within the compound. The area should
be protected by a perimeter fence, minimum 2 metres (6 feet) high at a
minimum distance of 1.5 metres from the side or ends of the tanks. The
fence, in chain link, may be erected on a low continuous wall, maximum
height 380 mm (15 inches), to secure the area and prevent trespass or access
by unauthorised personnel (bund walls are not permitted). The fence shall
have a minimum of two outward opening gates which should be non-self-
locking and kept unlocked when the tank farm is in operation — fig. 7.
The footings and plinths for the tanks shall be to appropriate design,
strength and fire resistance, which in turn will depend upon local sub-soil
conditions and water table. A survey should be conducted to check for
buried pipes, drains, culverts and cables which may affect the installation. H
is advisable to mount the tanks on plinths as high as possible (minimum 1.25
metres) to produce a good gravity head into the propellent pumps.
F-26
14
-------
PLklMETER AREA OF PIT 10 BE MAKKfcL> OUT
PLAN VIEW OF SINGLE TANK INSTALLATION /ALL VALVES CONNECTIONS *
FENCE WALL 4 $ATE6 ARE OPTIONAL / FITTINGS ARE MOUNTED ON
BUT IF OMITTED PRECAUTION MUST BE TAKEN / MAN LID COVER INVARIABLE
TO PREVENT SUPERIMPOSED LOADS 4 / TWO ARE NEEDED TO
POSSIBILITY OF DAMAGE TO FITTJNQS / ALL REQUIREMENTS
1!
CD
ix
v
O X
£
lO
t <£>
o to
»o
csj
C*
CO
SUB SOIL
CONCRETE SIDES
6 foundation
water BARRIER'
AT JOINT
CONCRETE RMsr
150 m m AS
I60>«»v1 FOR
SL)P£RlMP06kO
LOADS
c
c ¦
6UB SOIL
WASHED SIFTED
$ DR1EP SAND
TANK FIRMLY
SECURED TO
FOUNDATION
ALL DIMENSIONS
ARE METRIC
F-27
S/TE LAYOUT* SECTOR
FOR UNDERGROUND 7>Mtf
-------
I I
OANKER /
nq y
Smtr SEPARATION DI6T
PERIMETER FENCE
OUTLINE OF PIT
UNDERGROUND TANK
LESS THAN 2250 litre*
CAPACITY
example a
TMtKS NOT EXCEEDING 2250 LITRES WATER CAPACITY
3mtr RAP I US
OF SUPPLEMENTARY WSWHCE
i\
j \
•underground tank
I . OVER 2250 LITRES
| ' CAPACITY
\ -/ lC
T \ / yf RADIUS
u=x^ y | /of 8UPPL£MENTARV
ROAD TANKER
/X PITTANCE
Example B
Tanks over 2250 Litres Water Capacity
Underground tanks have a supplementary stipulation on
separation distance (see note 2 Fig 4). For a road tanker with
delivery hose fixed at tanker the supplementary distance of 3
mtrs (for tanks under 2250 litres capacity) will radiate from
the connection of hose & tank point & if made at the manlid
will be absorbed in the normal separation distance Example A.
For installations of over 2250 litres capacity the
supplementary distance of 7.5 mtrs. will extend beyond the
normal separation distance. Example B.
Where loose hoses are carried by a tanker the supplementary
distances will radiate from the connections to the tank & the F~28
tanker
All dimensions
are metric
Underground tanks
separation layout
-------
Vertical Tanks
Certain savings in space may be achieved by the use of vertical tanks, since
separation distances radiate from tank surfaces.
All the requirements lor the installation of horizontal tanks will apply, to
which must be added the following considerations:
1) A vertical tank installation will be more expensive than an equivalent
size horizontal tank.
2) The greater concentration of weight in the tank and its contents will
require much stronger foundations.
3) Overall height which includes the vent tubes may invoke planning
objections.
4) Height of tank may present Fire Brigade with fire fighting problems.
5) Fixed spray drenching system may be a condition of approval even on a
single tank installation.
Underground Storage
Where conditions for above ground tanks cannot be met, it may be possible
to install underground tanks where the separation distances are reduced
(see fig 8). It should be noted that for vessels up to 2250 litres (500 gallons)
water capacity, the distance for the valve on the manlid and the unloading
point to boundary buildings, building line or any fixed source of ignition
shall be a minimum of 3 metres (1 Ofeet) and for vessels above 2250 litres the
distance shall be a minimum of 7.5 metres (25 feet) — fig 9.
The pit excavated for the tank shall be in waterproofed reinforced concrete,
to suit sub-soil and water table, large enough to permit 1 metre access
between tank and sides for maintenance and inspection. The tank should be
secured to the base and should be covered by a minimum of 600 mm of
washed and sifted sand used to fill the pit. The tank itself should be properly
prepared against corrosion, usually the entire external surface is
shotblasted and zinc coated, bitumastic primer and enamel coats are
applied and the manways or nozzles wrapped in Thermoglazeorequivalent
(cathode protection may be advisable).
The area of the pit above the tank should be finished in concrete to prevent
any superimposed load affecting the tank. The perimeters of the pit area
shall be permanently marked and identified.
The manways or nozzle should protrude sufficiently above the concrete raft
as to allow the lids to be removed for inspection. All relief valves, vent pipes,
liquid and vapour connection points and other fittings shall be mounted on
the lids and be suitably protected against damage. A security fence should
be erected around the perimeter in the same manner as for above ground
tanks.
15
F-29
-------
Below ground tanks should be avoided if possible. They are some two or
three times more expensive to install than above ground tanks and periodic
tests and inspection are also expensive and time consuming, the below
ground siting makes pumping difficult and submersible pumps are not
recommended. The only advantage of underground tanks is the reduction of
the separation distances required to comply with the regulations. It is
strongly advised that specialist technical advice be taken concerning the
problems of underground tanks, corrosion and pumping.
Pumping
The pumps to supply the propellent to the filling machinery, as liquid at the
correct pressure to prevent vaporisation, should be sited within the tank
farm but not underneath the tanks. L.P.G. has no lubricating properties and
low viscosity. The pumps therefore should be designed and approved for
L.P.G. and continously rated. They may be electrically driven multi-stage
centrifugal type or air operated reciprocating.
The pumps should beset as low as possible and be provided with a pressure
relief to discharge back to the vapour phaseof the tank on overload or when
the filling lines have little or no demand.
The pumping pressure to the filling lines will depend upon the typeof filling
machine, the length and diameter of the pipework, the filling offtake and the
need to keep the L.P.G. hydraulic in the pipelines to prevent vaporisation on
sudden surges. It is advisable to have a standby pump for changeover in
case of breakdown, maintenance and repair.
The pumps should be set as low as possible and the tank a minimum of 1 25
metres (4 feet) above on its plinth. Appropriate pipe sizes and a reasonable
minimum liquid level should be maintained in the tank to present adequate
gravity head to the pumps for operation at correct pressures in all conditions
of ambient temperature.
An open-sided shelter in non-combustible materials may be built over the
pumps as a weather shield.
Pipework
All pipework shall be steel with flanges, filling valves, etc., to the appropriate
British Standards. Pipelengths should be welded or flanged, below 50mm
diameter, screwed joints are permitted by the Codes of Practice. Welding to
approved standards is preferred as a better earth continuity is possible; in
any case P.T.F.E. tape should not be used as a joint sealant.
Sections of pipework should be in manageable lengths, firmly mounted with
adequate flexibility for settlement and changes in ambient temperature and
routed to the filling area as approved by H.M. Factory Inspectorate and the
F-30
16
-------
Fig. 10
REQUIREMENTS AND EXTENTOFCLASSIFI ED AREAS FOR FIXED TANKS
For the UK Zone Areas indicate the degree of risk of fire or
explosion from the presence of flammable liquids gases or vapour.
In so far as Hydrocarbon for aerosol use the two applicable Zones
as set out in BS CP 1003 & BS5345 are reprinted below.
Zone 1 An area within which any flammable or explosive substance,
whether gas vapour or volatile liquid is stored, handled or
processed, tnd where during normal operations an explosive
or ignitable concentration is likely to occur in sufficient
quantity to produce a hazard.
Zone 2 An area within which any flammable or explosive substance
whether gas vapour or volatile liquid, although processed or
stored is so well under conditions of control that the
production (or release) of an explosive or ignitable
concentration is sufficient quantity to constitute a
hazard is only likely under abnormal conditions.
Extent of classified area Area classification
Within 5ft (1.5m) in alt directions from Zone 1
the tank connections or shell
Up to 5ft (1.5m) above ground level and Zone 2
within the distances set out for pressure
storage
Factor
Storage tanks
Relief valve
discharge
Within direct path of discharge
Within 5ft (1.5m) in all other directions
from point of discharge
Beyond 5ft (1.5m) but within 15ft
(4 6m) in all other directions from point of
discharge (10ft for tanks not exceeding
2250 litre cup)
Fixed electrical
equipment should not
be Installed
Zone 1
Zone 2
Tank vehicle Within 5ft (1.5m) in all directions from Zone 1
loading and a point where connections are regularly
unloading made or disconnected for product transfer
Beyond 5ft (I.Sm) but within 15ft Zone 2
(4.6m) from point of connection or
disconnection (10ft for tanks not exceeding
2250 litre cup)
Pumps, compressors
and destench Within 5ft (1.5m) in all directions Zone 1
columns
a) Outdoors in open Beyond 5ft (1.5m) but within 15ft Zone 2
air. at or above (4.6m) in all directions (10ft (3m) in
ground level the case of storage vessels not exceeding
500 UK gallons (2250 litres) capacity)
F-31
-------
"\
Fire Prevention Officer. Valves should be approved for L.P.G. and fire safe.
Where relief valves are fitted to prevent build up of hydrostatic pressures,
they should vent to a safe place and be protected for inspection and
maintenance by locked open shut off valves on either side.
If the use of underground pipes is necessary, ideally they should be in a
protective duct, coated and wrapped in suitable protective wrapping
material. The duct should be back filled in washed and sieved sand to at (east
500 mm (16 inches) below the surface. Cathode protection may be
advisable. The duct must be marked and suitable protection provided
against superimposed loads or traffic.
All pipes should be painted and marked for direction of flow and
identification to British Standard 1710 — 1975. Flexible hoses, where
necessary, should be to British Standard 4069 and suitably protected at
each end with shut-off valves. If a self-sealing coupling is used, it should be
with a valve protecting the fixed end.
Information Note: A flameproof enclosure for electrical equipment is one
that will withstand without injury by explosion of flammable gas that may
occur within it, under operating and overload conditions withi n the rating of
the equipment and will prevent the emission of any flame that will ignite
flammable gas that may be in the atmosphere outside the flameproofed
enclosure. Design and application is dealt with in British Standard 229-1957.
A guide to selection for Zone 2 areas is available in British Standard 4137 —
Fig 10.
Intrinisically safe applies to apparatus and circuits where the electrical
energy is so small that any sparking which may occur is incapable of
causing ignition, see British Standard CP. 1003 Part 1 and BS 5345.
Not*:
British Standard 5345-7976 of which pan 1
has been published is intended to update
4 bring into Una with tha International
Eloclrotechnical Commission's (IEC)
requirements for the selection,
installation, A maintenance of Flameproof
6 Intrinsically Sate electrical equipment &
apparatus.
There wilt be a transition period as Parts 2
to 12 are published during which time
certain requirements of other British
Standards will still apply, among lhase are
CP1003, BS229 A BS4137.
F-32
17
-------
Safety Procedures
Good safety procedures must be observed in accordance with the Codes of
Practice for the tank farms and pipe runs. The whole precincts of the area
should be designated non-smoking with suitable notices and restricted to
authorised personnel. The tanks should be checked to ensure that there is
sufficient space to accept deliveries, and each tank should have its
maximum fill capacity clearly marked — this should never be exceeded.
Always ensure that the tanker is connected to an earthing rod before
discharging tanker contents.
All bulk tankers carry an unloading pump, a meter to gauge the discharge
and a flexible unloading hose (9 metres effective length) with standard
connections for the bulk tank. Ideally, the tanker parking space should be
protected with an overhead sprinkler drenching system, but in any case
suitable dry powder fire extinguishers to British Standard 3465 or equivalent
should be located adjacent to the unloading area.
A sample of propellant may be taken for approval before discharge, using a
sampling unit.
The tanker discharge procedure should be agreed beforehand with the
suppliers' technical staff and the management and personnel of the
company who will operate the tank farm, staff must be properly trained in all
aspects of L.P.G.; safety, fault finding, testing, fire fighting and emergency
procedures.
The unloading and factory start up and shut down procedures should be
posted at vantage points, numerically itemised in correct and logical
sequence.
Assuming reasonable conditions, the total turnround time for a tanker of 10
tonnes capacity is about 2-3 hours. It is usual in the UK to be able to
discharge from a tanker without the use of a vapour return line from tank to
tanker for pressure balancing.
At all times a competent member of the company's staff and the tanker driver
should be in attendance during unloading.
The possibility of fire from an outside source affecting the tank farm and
pipeline can be minimised by good plant design and layout, consultation
with professional advice, proper training and discipline.
An adequate water supply should be provided for fire fighting and fixed
spray system which, in case of fire, will drench the fittings equipment and
the tank surfaces at the rate of 10 litre persq. metre. Small installations may
find a 20 mm hose reel adequate. In addition, dry powder portable fire
extinguishers to British Standard 3465 should be located at strategic points
and clearly marked
18
F-33
-------
'No Smoking', 'Keep Out' and other signs as considered appropriate should
be posted at reasonable intervals around the complex. Signs should also be
posted at the approaches beyond the separation distance, preferably with a
fronliertype barrier on the approach road to keep out unauthorised vehicles
especially with petrol engines.
Important Note: L.P.G. fork lift truck and similar vehicles should not have
their fuel cylinders refilled with aerosol propellant.
Although this handbook has been written with hydrocarbon in mind, it is felt
that it also presents an opportunity to stress the need for correct and safe
procedures for the storage and use of solvents, petroleum substances and
Highly Flammable Liquids, since the hazards are similar to L.P.G. and
irrevocably linked in the formulation and filling of aerosols.
As with L.P.G., petroleum substances and highly flammable liquids are
defined by and subjected to the Petroleum Acts and Orders and the Highly
Flammable Liquids and Liquefield Petroleum Gases Regulations 1972, as
well as local regulations and bye-laws as may be applicable. Furthermore,
any proposed installation can only be carried out with the co-operation and
acceptance of your local authorities, H.M. Factory Inspectorate and the Fire
Prevention Officer.
In the case of any solvent or chemical deemed to be covered by The
Petroleum (Consolidation) Act 1928, The Petroleum (Mixtures) Order 1929
and The Petroleum (Inflammable Liquids) Order 1971, a licence to store, mix
and use is required from the County Secretariat. Granting of the licence is in
the main upon clearance by Ihe Fire Prevention Officer of the safe site
layout, handling and use. A schedule of substances is set out in Part 1 of the
Order of 1971, but it should be noted that this schedule is not necessarily
complete and that substances are covered by the Regulations subject to
tests and that have a flash point below 23° C.
Broadly speaking, Highly Flammable Liquids are identified as having a flash
point below32°C subject tocertain tests as laid out in the Highly Flammable
Liquids and Liquefied Petroleum Gases Regulations 1972.
Section 7
SOLVENT STORAGE AND USE
F-3^
19
-------
11
Recommended Minimum separation distances for storage tanks
Capacity
of tank
litres
1000
1000-5000
5000-33000
33000-100000
100000-200000
Total Capacity
of tanks in group
litres
3000
15000
100000
300000
600000
Distance Distance from Bund to
between building, site boundary
tanks or fixed source of igniticn
1 1
1 4
1 6
1 8
1.5 10
NOTE Distances indicated are not subject to a code of practice
& are given as a minimum recommendation subject to
site conditions & opinion of H.M. Factory Inspectorate &
Fire Prevention Officer whose advice should be sought.
FILLING LINE FROM TANKER
DIPSTICK PORT
VENT PIPE WITH
FLAME ARRESTER
SUPPLY PUMP
OUTSIDE BUM
600mm MANLID
v mmmSi
CONTROLLED DRAIN
THROUGH BUND WAR
EARTH ROD (EXTRA EARTH
REQUIRED FOR TANKER)
ALL DIMENSIONS
ARE METRIC
F-35
SEPARATION DISTANCE
$ LAYOUT FOR HFL'6
-------
JUKO-MLL
Other solvents or chemicals with a flash poi nt of up to 66® C, whilst normally
regarded as only flammable, must be regarded as highly flammable if stored
at or approaching temperatures near their flash points.
Storage of these liquids in 200 litre drums and similar smaller containers
should be in the open or in open sided type structures without walls in a well
ventilated position with a bund wall on all sides (maximum height 1.5m) and
a ramp or sill for entrance. The net volume of the bunded area should be at
least 10% above the capacity of the largest container, and the ground should
be impervious to the liquids stored and should be sloped to a spillage drain
for evaporation.
In certain circumstances, a radiation wall, of two hour fire resistance, to the
height of the highest stack may be included (commensurate with good
safety), where required by the layout.
Empty drums must be stored within the area, as they will contain vapour
which is potentially hazardous.
Within the bund area, drums should be a minimum of one metre from the
bund wall and the compound itself a minimum of four metres from any
boundary, building or fixed source of ignition. The compound shall be
separated from any bulk tank installation of L.P.G. by a minimum of six
metres. These distances may be subject to change dependent upon the
geography of the site and consultation with H.M. Factory Inspectorate, the
Fire Prevention Officer and your local authorities.
Any forklift truck of similar handling device for use in the area or the mixing
room should be spark suppressed or flameproofed to H.M. Factory
Inspector's satisfaction.
Certain solvents and chemicals in constant use by the filler may be better
contained and more economically purchased in bulk storage tanks. It is
usual to employ mild steel tanks tested to 0.76 bar (10psig). These cylindical
tanks are generally mounted on plinths and cradles and sized to take the
maximum economic delivery based on daily usage and time taken for
delivery. The site chosen should have good access for tanker discharge.
Ideally, tanks should be sited above ground, sloped to collect spillage away
from the underside of the tanks and surrounded by a bund wall. If more than
one tank is bunded, the area shall be able to contain the net volume of 10%
above the capacity of the largest container (maximum bund height 1.5m). All
pumps and switch gear and valve sets, shall be outside the bund area.
F-36
20
-------
-dlaoMli
Underground tanks may be used to reduce separation distances but these
require special conditions of either vaulted construction or concrete jacket
and asa rule are some two to three times more expensive than similar above
ground installations.
Fig 11 shows the generally accepted safe distances for above ground tanks.
Pipework (suitably marked), into the factory area, should be in accordance
with appropriate British Standards and the routing should be decided in •
consultation with H.M. Factory Inspectorate.
Bulk tanks should not be located inside a building or on roofs.
Mixing
The mixing room or rooms should be totally enclosed and separated from
the production and storage areas of the factory by suitable fire resistant
walls and doors. The whole area should be flameproofed but dispensation in
this regard may be obtained from the H.M. Factory Inspectorate. Certainly
the area in the vicinity of the mixing vessels and holding tanks should be
considered a Zone 2 area (British Standard BS5345). Mixing and holding
vessels should be totally sealed or provided with access lids as small as
possible with good tight fit.
Ventilation should be adequate throughout the whole area, firstly to
eliminate the concentration of any highly flammable vapour likely to be a fire
hazard and secondly to provide a safe fresh air atmosphere for the
protection of the health of personnel under the Health & Safety At Work Act
(see note concerning chemical data sheets and handling and safety
precautions, Sections 9 and 12).
Ventilation rates will beset in co-operation with H.M. Factory Inspectorate,
but as a general rule the two requirements of the preceeding paragraph
should be followed. As the emphasis is on containing the chemicals in
closed containers, mixing, stirring and pumping should be kept to a
minimum (heat input increases evaporation). Where vessel lids must be
opened for the introduction of solvents and ingredients, ventilation should
be from within the vessel to a safe place, so that the velocity over the lid
opening shall be at least 46 metres per minute to prevent evaporation to
surrounding areas
The area under the mixing vessels and the general mixing area should be
bunded or silled and the whole floor fitted wilh gutters to drain to an effluent
sump lor disposal (see Section 10).
The aerosol product filling should be fixed by an area of demarcation
dependent upon the type of machinery and size of operation and is dealt
with in Section 8.
-------
Section 8
AEROSOL FILLING
There is no single piece of legislation that de&ls with aerosol filling; in other
sections of this handbook we have referred to and listed most of the
regulations and laid stress to those of particular reference to hydrocarbon
storage, etc. Certain parts of those regulations apply to aerosol filling, the
most important being The Highly Flammable Liquids and Liquefied
Petroleum Gases Regulations 1972', the interpretation of which, coupled
with the special considerations of aerosols, should govern the approach to
the filling and packaging operations.
From other sections of this handbook it can be readily appreciated that,
whatever the size of the filling operation, we must:
1. Understand the nature of the hazard of hydrocarbon and highly
flammable liquids.
2. Consider the hydrocarbon propellant filler as a Zone 1 area.
3. Consider the surrounding area as a Zone 2 area.
4. Contain the propellant filling operation in as small an area as possible
commensurate with the rate and needs of production and ventilation.
5. Ventilate to remove any hazardous and harmful vapour.
6. Ensure a safe routing of propellant pipework through the factory.
7. Evaluate, install and maintain a safe operating procedure at all times and
for all personnel.
An exact specification for filling cannot be laid down, for it will alter with the
changing circumstances and machinery at each factory and to some extent
upon the requirements of the Factory Inspector and his Field Consultants in
your region. It is therefore unreasonable to expect H.M. Factory
Inspectorate to have a unified and detailed policy for the whole country.
The British Aerosol Manufactuers Association have published a 'Guide to
Safety in Aerosol Manufacture' covering generally aerosol filling using all
types of propellants. We subscribe to its objectives and agree with its
recommendations, good counsel ideas and procedures and commend them
to the reader. We do not wish to repeat them in this section, but to
concentrate on the seven points mentioned earlier, and to show how we feel
the line layout should be tackled, and accept that in the process repetition in
part at least will be inevitable.
1. Understand the nature of the hazard of hydrocarbon and HFL't
In all the preceding sections, we have stressed the nature and the hazards of
hydrocarbons and highly flammable liquids (HFL's) and have quoted and
made reference to Codes of Practice and relevant regulations and
recommendations. Whilst reiterating the seriousness of the hazard, use of
hydrocarbons and HFL's may be safely carried out with containment and
adequate ventilation as the first line of defence.
F-38
22
-------
2. Consider the hydrocarbon propellent filler a Zone 1 area
Dangerous area designations are shown in Figure 10 and are abstracted
from the British Standard Code of Practice CP1003 Parts 1.2 and 3,1967 and
BS5345. From these designations and with the inevitable release of a small
quantity of hydrocarbon when the aerosol disconnects from the filling
adaptor, we must accept that the propellent filler orthe total machine (if the
propellant filler is an integral part of the complete aerosol filling machine),
must be considered a Zone 1 area and that electrical equipment must be
flameproofed or intrinsically safe to the appropriate standard.
3. Consider the surrounding ares a Zone 2 area
The Code of Practice CP1003 states that in an indoor situation a Zone 1 area
must be separated to ensure that there is no uncontrolled flow of flammable
liquid gas or vapour from that area to a Zone 2 area or a safe area. We must
accept that the area adjacent to a Zone 1 area must always be considered
Zone 2 by virtue of the aerosol conveyor inlet and outlet openings i n the wall
of the Zone 1 area. Where concentrates are filled separately from propellant
and where those concentrates contain HFL's, that area may be Zone 2
provided proper controls are exercised — fig. 12.
4. Contain the propellant filling operation In as small an area as possible
commensurate with the rate and needs of production and ventilation.
Dependent upon the size of the filling operation, factory space available,
throughput of cans, the type of machinery used, the formulation and valves
to be used; the propellant filling area or booth may vary in size and
layout.The following examples are all based on indoor installations:
a) Manual filling operation (Dual Pak 'equipment) — since the propellant
filling is integral with the complete equipment, the whole should be housed
in a Zone 1 enclosure of sufficient floor area to permit good operation,
access to the equipment for adjustment, space for concentrate header tank
and space to offset possible claustrophobic effects and to provide operator
comfort, see fig. 12-1. Can and valve space should be limited to reasonable
quantities, say 2/3 hour supply; and combustible outer packing materials
should be removed from the area at regular intervals, although passage
through the doors or door opening should be kept to a minimum.
b) Rotary Index type filling (Star Pak 'machinery) — the same
considerations should be taken as in 4a), especially where the propellant
filling is integral with the complete machine, fig. 12-2, but it may be
considerably larger in area if two back to back machines are employed. A
preferred alternative is to segregate the propellant filling by the use of a
selfcontained rotary index unit housed in its own Zone 1 enclosed area, fig.
12-3, whilst the concentrate filling and crimping operations are carried out
on the main rotary index machine housed in a Zone 2 area under
flameproofed conditions; back to back can also be accommodated in this
fashion. The advantage of this alternative is that the main hazard of
hydrocarbon is isolated in an area without the need for operators.
Note: the extent of the Zone 2 concentrate filling area may be reduced if non-
flammable concentrates are used.
23
F-39
-------
f ZONE 2 A
2 AREA
ZONE 2AREA
L_.L _
CANS
1 '
o
Oo oO
PUAL PAK
ZONE 1 AREA
—i—
VALVES
ZONE 2 AREA
ZONE 2 AREA
COMBINED PRODUCT $ PROPELLANTT FILLER
0
O
©
ZONE 1 AREA
ZONE 2 AREA
ZONE Z ARJ
PRODUCT fill
VALVE $ CRIMP
0
fO
o
PROPELLANT FILLER
a
0
\o
ZONE 1 AREA
ZONE ZAREA
EXAMPLES OF FILLING AREAS
Fig 12-1 Hand filling
Complete filling operation enclosed
in Zone 1 Area with local extraction at
filling head level & main extraction at
floor level inlets (min4) so positioned
as to prevent any vapour reaching
Zone 2 area which will extend (or be
enclosed) to a distance as required
by H.M. Factory Inspector.
Fig 12.2 Medium speed filling
Complete filling operation enclosed
in Zone 1 Area with same
considerations as Fig 12-1
Unscrambler may be located in Zone
2 Area if all electrical equipment is
flameproofed.
Fig 12-3. Medium speed filling
Whilst product filling, valving,
crimping is carried out in a Zone 2
area the Hydrocarbon is separately
filled on a smaller machine in a self
contained Zone 1 Area The product
filling area will require its own
Separate ventilation if Highly
Flammable liquids are used.
NOTE: In all cases separate
ventilation may be required for
operator comfort & health protection
Drawings are Schematic & not to scale
-------
L. ZONE 2 AREA f
ZONE 2 AREA
PRODUCT FILL
CRJMP
PROPELlANr FILLER
a
Zr
ZONE ] ARM
ZONE 2 AREA
PRODUCT- FILL
CRIMP
a
PROPELLANT FILLER
ZONE 2 AREA
ZONE I AREA
PRODUCT FILL
| ZONE 2 AREA |
CRIMP
n
ZONE 2 AREA
PROPELLANT FILLER
u
ZONE 1 AREA
=r~^=
ZONE 2 AREA
V
EXAMPLES OF FILLING AREAS
Fig 13-1 Rotary Machine Filling
^ All filling operations housed in Zone
ZONE 2 AREA 1 Area propellant filler requires
>- special ventilation with total Area.
Since area tends to be large this
method is not recommended
Examples 13-2 or 13-3 are preferred.
Fig 13-2 Rotary Machine Filling
The separate enclosure of the
propellant filler in a Zone 1 Area
ensures better extraction with
enclosed Zone 2 Area for the filling of
products containing Highly
Flammable Liquids
Fig 13-3 Rotary Machine Filling
Zone 2 Area to extend to a distance to
satsify the Factory Inspector
7nMF , adfa especially for products with Highly
ZUNL c akca^ Flammable Liquids. Zone 1 Area may
^ be constructed for single or multiple
lines with ventilation to suit.
NOTE: In all cases separate
. ventilation may be required for
-f— operator comfort & health protection.
Drawings are schematic & not to scale
-------
EXTERNAL
WALL
/nff
Fig 14
PRODUCT FILLER 6 CRIMPERS
X)
£>
£
(V
<
CM
LlI
2:
o
N
/=
ZONE 2 AREA
(V
Ui
d
£
O (V
Ik5I-_i
£
IJ' 21
I ii a
ZONE 2. AREA
f
EXTENT OF ZONE 2 AREA INSIDE BUILPlNG MAY" BE 6ET BY H.M. FACTORY IN3PECT0R
AND WILL INCLUDE PRODUCT FlLLlNGj IF INFLAMMABLE 30LV£N]"5 ARE USED
PRODUCT FILLER
ZONE Z AREA
CRIMPER
Z0NE Z AREA ONLY IF
INFLAMMABLE products are filled
ZONE Z AREA
I
THE REMOTE PROPELLANT FILLING BOOTH ENSURES A SAFE ARM
INSIDE THE FACTORY PROVIDING NON FLAMMABLE PRODUCTS ARE FILLED
DRAWINGS ARE SCHEMATIC NOT TO SCALE
LAYOUTS SHOWING FILLING BOOTHS
F-42 EXTERNAL TO MAIN FACTORY 6UIUM63
-------
In all layouts it is advisable to locate the rotary unscrambler tables outside
the filling area and to pass the cans by conveyor through apertures in the
separating walls, so keeping this can feeding, its associated combustible
packing and any fork lift trucks, in a safe area. Filled cans may, of course, be
conveyed from the filling room to the test and final packing operations in the
same manner.
"Dual Pak' and 'Star Pak' are machine names registered by Aerofill Ltd.
c) Rotary filling machines (high speed) — because of the greater output of
these machines, the longer lines employed, the possibility of automatic
valve sorting and insertion, the filling room Zone 2 may be fairly large
with can handling through apertures as in 4b). The propellant filling
machine may be housed in a "walk-in" filling booth, fig. 13-1 or in a more
restricted enclosure fixed to the machine itself, fig. 13-2.
If the former alternative is used with adequate ventilation and a controlled
discipline on the opening of access doors, the rest of the filling room may be
a Zone 2 area; with the latter the area surrounding the machine should be
classified Zone 1 (by virtue of the opening of doors or hatches exposing the
machine and possibly flammable liquid, gas or vapour to the surrounding
area). No great advantage is secured apart from a possible saving in
ventilation, except where a number of filling lines feed a common Zone 1
room, fig. 13-3, for propellant filling.
In situations where the filling room does not have a wall separating it from
the rest of the factory area, Zone 2 conditions will extend, radiating from the
enclosed propellant filling booth for a distance which will be decided upon
by H.M. Factory Inspectorate.
Where space permits or during the consideration of new projects, the use of
a self contained, isolated filling room in open air may be considered as a
further alternative. With this method, the concentrate filled and crimped
cans would be transferred by conveyor through an aperture in the factory
wall to a separate filling room built on the existing building or remote from
the main building — fig. 14. These two alternatives would still be classified
Zone 1 with Zone 2 areas adjacent as indicated If this principle is adopted
the extent of the Zone 2 to Safe Area around the filling booth must be agreed
with H. M. Factory Inspectorate and no subsequent building or intrusion
made.
Where Fluorocarbon propellents are no longer to be used, vapour purging
previously carried out with the use of propellant 12 vapour may be continued
where compatible by the use of compressed gases; where the use of
compressed gases is unsuitable vacuum crimping can be used.
Where an automatic checkweigher is to be sited after the propellant filler but
within the Zone 2 filling room, for ease of data feedback, that machine shall
24
F-43
-------
Flfl 15
FOUR balanced
VENTILATION DUCfS
WITH FLOOR. LEVEL
INLETS
VENTING ROOF LAID
ON RAFTERS WITH
CHAIN RESTRAINTS
0R.SIN/1ILAR.
CAN INLETOUTLETS
MlN. OPENIHq SlZt
FRESH AIR INLET
BRICK
MIN.SIZE POOR WTTh
JRlP-FfcEE RAMP OR SILL
CONCRETE
PUCTlNq EARTH POINT
r
ELEVATION
SECONDARY VENTILATION
AT FILUN6 HEAJ) LEVEL
CANS Ih
/=.-^rr=rE::=:
CANS OUT
PLAN
-------
Fig 16
ROOF MOT SHOWN
ELEVATION
CONCRETE
FLOOR. LEVEL ^RlLL
I—
I
PLAN
Layout shows propellant filler surrounded by a
ventilation channel surmounted by a floor level grill.
The channel leads underground to the vertical
ventilation duct. Care must be taken to design
channel & duct to give a balanced ventilation in all
directions around the machine. An alternative is to
construct two ducts in opposite positions shown
thus Gas Sensors ® moved nearer to doors
fresh air inlet is from above
Drawing is schematic & is not to scale.
Possible scheme for below ground ventilation
F-45
-------
uiL'iaPJii
be flameproofed or intrinsically safe to approved standards. The
checkweigher may be sited outside of the filling room, a reasonabledistance
from the aperture in the filling room wall and be ventilated at conveyor
height.
Filling Room
The filling room enclosure and the propellant filling booth enclosure may be
of brick or double skin steel partitioning sections bolted together and to the
floor with a good seal and earthing bond, windows in clear shatterproof
polycarbonates should be kept to a minimum, but where operators are
permanently present, should be sufficient in size to overcome any
claustrophobic effect. The doors should be smaller than standard, have a
raised threshold, be close fitting in the architraves and open outwards. A
minimum of two doors is recommended — their positioning to be more
suitable for emergency exit than for servicing equipment. The roof shall be
laid or) rafters where necessary, with a good seal, but with corner chain
restrictors common to explosion venting. Ideally, the venting should be
through the roof of the factory, but where high roofs exist, the filling room
and booth may have individual roofs at lower levels, providing there is an
uninterrupted space above. In all cases, the height of the filling room and
propellant filling booth should be adequate to the operation — 3m. may be
considered sufficient for rotary machines.
Since the rooms and booths in our recommendations are square or
rectangular in plan, we would recommend four balanced ventilation ducts in
the corners with openings at near ground level as primary extract and with
secondary ventilation at filling head level, — fig. 15. The gas sensor heads
should be mounted adjacent to the lower duct openings at a side to take
account of the position of the booth doors. The extract should pass through
the roof to the highest possible point away from the roof valleys and rain
water gulleys. Fresh air inlet should be remote from the outlet and should be
so calculated as to supply sufficient air to create a negative pressure within
the booth and be fed in at propellant filling room or booth roof level.
A channel in the floor surrounding the base of the propellant filler connected
with the extract duct and topped with a perforated grille at floor level may be
an alternative method of providing ventilation — fig. 16.
Smoke tracers and a portable velocity meter may be employed to test for
draught patterns and the balancing of ventilation ducts.
In a well designed system, it may be agreed that normal operation will be
conducted at 25% of the L.E.L. An 'orange' warning should be made by the
sensors on detecting this level and above, whilst a 'red' warning (shut down)
could be made when a head reports 50% of the L.E.L.
From the circumstances of the filling layout, consultation with H.M. Factory
Inspector and the factors mentioned earlier plus a safety factor of say 2, a
F-46
25
-------
uJUiOi'JiL
formula for the amount of air in cubic meters per minute to be introduced,
mixed with any hydrocarbon vapour and extracted can be determined and
duct and fan size gauged accordingly.
The time of progression from sensing at 25% of the L.E.L. to 50% of L.E.L.
and shut down procedure may be increased or averted by the switching in of
additional ventilation at the 25% level.
Any ventilation ducts, fans, light fittings and pipework shall not obstruct the
venting roof principle.
All machinery should be guarded to ensure reasonably safe operation and
protection for the workforce, but it should be noted that machine guards do
not in themselves provide protection from the spread of hydrocarbon gas or
vapour.
There may be superimposed upon these recommendations certain
requirements of fire resistant structures in the segregation of Zone 1 and 2
areas from the rest of the factory.
In the packing area, the drive and equipment of the hot water test bath
should be flameproofed with safe means of disposal of reject cans by
automatic conveying or by collection in vented bins (metal) for frequent
removal to a safe place.
Automatic actuator placing machines should be flameproofed and
conveyor height ventilation installed.
Other operations, in particular shrink wrapping, are dealt with in the
B.A.M.A. publication.
S. Ventilate to remove any hazardous and harmful vapour
From the health point of view, there should be adequate ventilation to
remove any toxic and noxious vapours with duct inlets at positions where
any evaporation may occur and certainly at the concentrate filler nozzle
level, with a minimum velocity of 46m. per minute across openings. For
operator comfort within the filling room, air changes should be a minimum
of the order of 25-30 changes per hour.
Ventilation is the first line of defence in the control and elimination of the
hazard of hydrocarbon and should be so used to neutralise the inevitable
release of a very small amount of hydrocarbon when the aerosol valve
disconnects from the propellant filler. This gas amount can be calculated
from the clearances between valve and filling adaptor, the rate of filling
(cans per minute) is known, so is the expansion ratio (liquid gas to vapour)
26
F-47
-------
12 tonnes and 30 tonnes tanks with Fixed Drench Sprinkler System
F-48
-------
TT Fig 17
14 15 16
BRICK
CONCRETE
VIEW SHOWING SECTION OF PROPELLANT FILLING BOOTH
1 Extract Ventilation Duct with Floor Level Inlet
2 Solenoid Shut Off Valve (normally closed) Operated by Gas Sensors
3 Shut Off Valve (locked open — maintenance use only)
4 Hydrostatic Relief Valve
5 Vent Pipe to Atmosphere with Rain Cap
6 Pressure Gauge (Pump Line Pressure)
7 Shut Off Valve
8 Flexible Hose with Self Seal Quick Release Coupling
9 Shut Off Valve
10 Position of Flexible Hose for Gas Purging
11 Bleed Valve with Controlled Leakage into Ventilation Duct
12 Filling Booth Wall
13 Gas Sensor Head
14 Filter 10 Micron
15 Pressure Accumulator
16 Pressure Regulator — Line Pressure down to Machine Operating Pressure
17 Rotary Joint
18 Secondary Ventilation at Can Filling Level (into duct not shown)
19 Rotary Propellant Filling Machine
20 Machine Earthing Point
Drawing is schematic & is not to scale
Scheme for Supply & Connection of Propellant Line to Filling Machine
F-A9
-------
juaowii
of the hydrocarbon, at say 20°C (70°F). We also know that the lower
explosive limit of butane in air is approximately 2%. In order, therefore, to
create a safe atmosphere, we must supply to and mix with the released
hydrocarbon sufficient quantitites of environmental air to produce a mixture
that is below the Lower Explosive Limit (L.E.L.). The actual percentage
below the L.E.L. which may be considered acceptable for normal operation
(for an 'orange' warning and for a 'red' warning as detected by electro-
catalytic monitoring systems) will be determined by the size and layout of
the filling booths and the disposition of the ventilation openings.
The 'orange' warning should be somewhat muted to give warning of level
change without provoking alarm. The 'red' warning should, through the
sensors' relay system, shut off propellant supply at the filler and tank pump
by use of flameproofed 'energised open/normally closed' solenoid valves;
operate evacuation warning and any other procedures agreed with H.M.
Factory Inspector and the Fire Brigade. The shut down procedure will
switch off all electrical supply to the filling line and other equipment.
The ventilation system should be interlocked so that the filling line cannot
be started without the ventilation and the ventilation shall be monitored by
an air flow switch in the ducting that will shut down the line if the air velocity
drops below set levels.
6. Ensure a safe routing of propellant pipework through the factory
Ideally, pipework should be routed from the tank farm to the filler in open air
as far as possible. In its passage inside the factory, the pipework should be
fixed firmly as high as possible but in accessible positions. The pipes should
not be routed alongside electrical ducts or cables, steam pipes or heating
systems, a continuous earth bond shall be maintained and pipes identified
for hydrocarbon and directional flow in accordance with British Standard
1710—1975
Immediately prior to their entry to the propellant filling booth, an emergency
shut down valve should be fitted, with a manual shut off valve immediately
inside the booth. It is advisable to pass incoming propellant through a fine
filter, say 10 micron, to remove any fine particles that may affect seals and 'O'
rings. To eliminate fluctuation in flow and pressure caused by intermittent
demand it may be necessary to fit a hydraulic accumulator; whilst a pressure
regulator should be fitted to reduce line pumping pressure down to that
needed to support pressure filling ratios and filling accuracies. The final
connection to the propellant filler may be flexible, but to British Standard
4089, whilst any quick release couplings should self-seal (all valves should
be fire safe) fig. 17.
On machine changeover, the unwanted propellant within the machine may
be safely purged by plugging the quick release coupling into a valve in the
vent ducting to permit controlled release that will not overload the system.
F-50
27
-------
7. Evaluate, Install and maintain a tale operating procedure at all times and
tor all personnel
The sections of the B.A.M.A. 'Guide to Safety in Aerosol Manufacture'
dealing with aerosol filling and subsequent testing and packing should be
referred to; these recommendations and suggestions, together with
procedural recommendations in the Health & Safety Executive's Code of
Practice, etc; and the additional recommendations that we have set out in
this handbook may be collated with numerical references to serve as official
procedures for your company:
a) Start up procedure
b) Operational procedure
c) Shut down procedure
d) Changeover procedure
e) Emergency procedure
These procedures will vary according to the circumstance of each factory,
its size, type and number of filling lines, a layout service plant and equipment
and other factors. It is part of the Aerofill Service to undertake this task and
to work with company representatives to produce a series of satisfactory
procedures and to operate a check list service in order that necessary up-
dating and maintenance of the procedures is carried out.
28
F-51
-------
^aaaoj?Jii
Section 9
THE LABORATORY AND PILOT LINE
Most aerosol filling operations will be supported by laboratory facilities for
formulation, test and evaluation and perhaps process and quality control
with pilot line operation in larger companies. It therefore follows that the
scale of the laboratory operation will be proportional to the total size of the
enterprise.
There is no single statutory regulation governing the operation of a
laboratory and such as do apply do so in part. Abstracts from the Shops,
Offices and Railways Act: the Highly Flammable Liquids and L.P. Gases
Regulation; Regulations for Storage and Use of HFL's and Solvents; the
Petroleum Consolidation and Mixtures Order 1928 and 1929 for storage
mixing and use; the Medicines Act where appropriate as well as sensible and
applicable parts of the various codes of practice identified in this handbook
may all apply.
Where not governed by mandatory requirements, the laboratory layout and
operation should be dictated by good safety sense in the same manner
applicable to the main factory area and staff properly trained and instructed
in the handling and use of hazardous materials.
Advice should be sought from H.M. Factory Inspectorate, the Fire
Prevention Officer and from the technical advisory service of the supplier of
propellants, solvents and raw materials.
In any event, the suppliers of these raw materials are required to present you
with technical datasheets for each material, that identifies its physical
properties, its hazards (flammability, flash point, toxicity etc.) safe handling,
precautions and emergency action if required. These information sheets are
mandatory under the Health & Safety At Work Act.
As the data contained in these information sheets applies to your total
workforce in the factory as well as the laboratory, it is sensible that the
Laboratory Manager be entrusted with the duty of requesting, receiving,
cataloguing and ensuring thai safe handling, mixing and use procedures
based on these information sheets be disseminated throughout the factory
in a correct manner.
Your Factory Doctor should be informed, consulled for advice and good
procedures.
The design, construction and set-up of the laboratory will, of course,
depend upon the size of the total undertaking, but it is unlikely that the
supply of hydrocarbon will be required in anything larger than refillable
cylinders. The cylinders awaiting use or empty awaiting collection by the
supplier will be stored as set out in Section 5.
-------
Those cylinders in use should be stored in the open at least on an outside
wall in a well ventilated place with separation from other combustables, high
flammable liquids and other gas cylinders. The cylinders should be chained
secure in an upright condition suitably marked and identified as to their
purpose, the key or shut-off valve knobs should not be removed and it it is
recommended that a notice be fixed around the neck of the cylinders in use:
vis
'Cylinder in use — shut-off valve open.
Do not tamper or close except in emergency
without reference to '
(enter name of suitably qualified and
responsible person).
If the laboratory is small, sample filling may be carried out in a fume cabinet
that is completely flameproof and properly ventilated to a safe area; the front
cover should be lowered as low as is practicable for hand operation of
propellant filling. The air flow of ventilation across the opening should not
be less than 46 metres per minute.
Whilst the filling of samples is in progress, all ignition sources in the
laboratory should be turned off, a portable gas detector should be used to
monitor the operation.
Ideally, the fume cabinet should be located on an outside wall and as
isolated as possible, certainly from naked lights or flame and any source of
ignition.
On a larger scale, the filling by laboratory °'io' or Dual Pak equipment
including the product filling should be enclosed in a self-contained room
well ventilated to a safe area with at least 25-30 air changes per hour. All
equipment should be flameproofed and gas detectors strategically placed to
sense unwarranted concentrations of hydrocarbon and able to bring a halt
to filling until the atmosphere is cleared Personnel should be trained to shut
down and evacuate in the event of excessive escape.
A pilot line operation using a Dual Pak or the larger Star Pak equipment
should be contained in a room which, in turn, should be considered a Zone 1
area and flameproofed and treated accordingly as with a production line of
this type mentioned in Section 8.
Hot water leak and container testing should be carried out on all aerosols
more especially since they will be formulated for test and evaluation and
should be given 100% inspection. Leak test should be stringent to prevent
unwarranted accumulation in store rooms and hot store.
-------
- S.Mr
Actualors should be fitted with a screwing action to prevent any
hydrocarbon present in the dip tube being released by accidental operation
of the valve.
Test spraying, evacuation tests and residue tests, etc., should be conducted
in a fume cabinet with good ventilation with fan rate guaged to the rate of
spray testing.
It is normal to expect that filled samples will be stored at ambient and
elevated temperatures and for this reason we again stress the importance of
the leak inspection. Leakage under hot storage conditions, of between
20°C-25°C, presents a greater hazard, since the hot store cannot be
continuously ventilated to combat gas leaks. Detection units should be
installed within the store to provide adequate warning of hydrocarbon gas
and to switch on ventilation to clear the accumulation whilst switching off
the source of heat.
In all cases it is recommended that windows in the room, fume cabinets and
the filling room be fitted with clear polycarbonate sheet and that these
windows be kept to the minimum area.
Personnel should wear cotton overall clothing to obviate static, should wear
eye protection and be properly trained and instructed in safety procedures.
F-54
-------
JUSOjull
Section 10
DISPOSAL OF WASTE AND SCRAP
Regardless of the efficiency of any operation, there will be waste and scrap
and since this contains highly flammable liquids, toxic materials and
hydrocarbons, and combinations of all three, the disposal of this waste
should be tackled with care and a sensible appreciation of its hazard.
Waste, whether liquid, solid or scrap aerosols is subject to the Control of
Pollution Act 1974 which lays down certain controls, whereby the burden of
responsibility for safe removal and disposal is chiefly with the aerosol
manufacturer. Using the correct procedure, notify the local authorities of
the nature and amount of waste; the contractors name and address; the
location of approved disposal site; the nature of the disposal means. The
local authorities in the disposal area if outside of the jurisdiction of the local
authorities applicable to the manufacturer's works, should also be notified.
For disposal, we should consider two distinct categories: 1) Liquid and/or
solid waste — Aerosol concentrates, left over concentrates after a run,
surplus or obsolete and reject mixes, washings in either water or solvent
thereby contaminated. 2) Scrap aerosols — Line scrap; empty, full or
partly full, laboratory and quality control scrap; and obsolete aerosols from
whatever source.
1) Llquld/tolld watte
It is extremely unlikely that any company engaged in the production of
aerosols may be granted any consent for the disposal of waste into surface
water or foul drains.
However, consultation with your water and/or local authorities will establish
what'permitted quanitities'may beaccepted; any such waste would need to
be biodegradeable and in quantities acceptable to the drainage/river system
or the filter beds. At the very best the waste water from the hot water test
baths may be acceptable under certain conditions.
It therefore follows that the concentrate mixing and the area in the vicinity of
the product fillers be drained to a sump for periodic removal and disposal
within the requirements of the Act.
2) Scrap aerosols
There are two methods of dealing with scrap aerosols.
i) Shredding — this process passes the scrap through powerful jaws from a
funnel type hopper which punctures and shreds the can into manageable
pieces. This releases the hydrocarbon propellant to evaporate around the
32
F-55
-------
machine and the product to be drained by gravity down chutes for collection
in a sump. This type of installation needs proper siting under flameproof
conditions with the best possible separation distances from any fixed
source of ignition. The machine, chutes and sump should be well ventilated
to a safe height and the plant operated at frequent intervals throughout the
working day as the scrap is produced; rather than operating for a set period
to process the day's scrap in one quick batch. The hopper should be fed in
small quantities on a 'little and often' basis for good safety, for an
overworked shredder can release an appreciable amount of vapour gas in a
very quick time, i.e. a scrap rate of 0.5% and a fill of 10,000 units with a 50gm
butane fill will produce a flammable cloud in air to the order of 60 cu. mtrs.
(2000 cu. ft.) and as the machine can shred the 25 cans of scrap of the
example in less than 3 minutes, the gravity of the hazard may be readily
appreciated.
ii) Tip disposal — this method may be more acceptable where there is
insufficient 'natural ventilation' for a shredding operation. Within the
requirements of the Act and with proper procedure, it is possible for tip
operators, where sanctioned, to supply on a hire/demurrage basis a large
open skip (20-30 cubic metres) for collection and transport of scrap to the
tip. It is necessary to site the skip in a well ventilated area with a suitable
portable shield to prevent the ingress of rain diluting any ensueing liquid
waste for possible leakage on public highway during transport from the
factory. To prevent the possibility of leakage due to pressure from weight of
cans in the skip, it is recommended that scrap aerosols are fitted with an
overcap and that scrap is bulldozed immediately upon receipt at the tip to
prevent any unauthorised salvage.
In all cases it is recommended that the Factory Inspectorate and the Fire
Prevention Officer be consulted concerning the siting of shredding
machines or portable skips.
Local authorities have the power of inspection under the Act.
Those companies who may wish to consider on site treatment of trade
effluent should note that this is only economic for very large operations or
where waste is produced from other processes as well as aerosols. This
treatment is not total, leaving a concentrated sludge to be disposed of as laid
down in the Act.
Incineration ol waste may be_considered but again demands high
throughput or a specially designed project in conjunction with a fuel
burning boiler.
F-56
33
-------
Section 11
FINISHED GOODS
The storage of finished goods in the factory warehouse area may be
governed in some way by local regulations and bye-laws. Apart from these
requirements aerosols, dependent upon formulations and contents, may be
governed by:
a) The Petroleum Mixtures Act and Orders, wherein a petroleum licence is
required (see section 7) to store, mix and use products containing
petroleum substances within the meaning of the Act. Advice may be sought
from Fire Prevention Officer and County Secretariat.
b) The Highly Flammable Liquids and Liquified Petroleum Gases
Regulation 1972, applies to aerosols containing more than 500cc of total
contents. Aerosols containing in excess of 500cc are classified as flammable
when they contain more than 45% or 250gms of liquids with a flash point of
less than 32°C (90°F) aggregated with any flammable gas. Aerosols
classified as flammable must be labelled 'Flammable — do not use near fire
or flame' in accordance with agreements with H.M. Factory Inspectorate and
stored in a fire resistant structure as set down in the regulations.
In the interests of safe storage, the filler is advised to check against
accidental spraying and release of hydrocarbons due to weight of stored
and palletised aerosols:
1) In cases and cartons, check the total weight of the stack against the
collapse resistance of the carlon and overcap.
2) Check total weight of stack against collapse resistance of overcap when
shrinkwrapping is used without support from any outer carton.
It is recommended that smoking be prohibited throughout the whole
storage area and notices displayed.
It is recommended that there be adequate gangways and that goods are not
left in these gangways.
The warehouse should be dry and as cool and as well ventilated as possible
Hydrocarbon filled aerosols should not be stored in basements orareas with
open drains.
34
F-57
-------
All storage should be away from stoves, radiators, boilers and other heat
sources.
Adequate means of fire fighting and fire exit should be provided in
consultation with the Fire Prevention Officer.
Section 12
SAFETY AND FIRE PRECAUTIONS
The possibility of any outbreak of fire can best be minimised by sound
engineering in the initial design and layout of the tank installation and the
filling line, and also by a critical analysis of each facet of the total operation
and its hazards. In co-operation with authorities and competent advice,
written procedures for start up, shut down and operation of emergency
procedures should be produced. From these masters an itemised checklist,
numbered and in logic sequence should be prepared and used for each
individual part of the process. Tanks, pumps, valves, pipelines, etc., should
be given numerical or alpha-numeric references and identified on the
checklist. Ideally, the procedures should be a two man operation and
signatures obtained to record the correct operation and sequence of each
phase.
Staff of adequate education and training should be instructed in these
procedures, not just to follow a sequence of operations but with a
knowledge of the principles of the operations and the need for adherence to
the discipline.
Maintenance and leak check procedures should be drawn up and a 'permit
to work' system installed where maintenance or overhaul is required. The
work and conditions of any subcontractor should be closely controlled and
monitored at all times.
Periodic meetings of all concerned in the total operation should be held and
from this feed back update, revision and improvementof procedures may be
made.
F-58
35
-------
Adequate water supply either mains or from storage tanks should be
provided for fire prolection, hose reels may be suitable for smal I installations
but fixed spray systems are strongly recommended both within the factory
and at the tank farm (favourable insurance premiums may result). The
strategy for fire precautions should be aimed at keeping a fire unconnected
with the hydrocarbon storage or use from effecting the hydrocarbon
installation as well as protecting the hydrocarbon installation itself.
The production and warehouse areas of the factory may be protected by a
sprinkler system with individually fused spray heads, but it may be preferred
to protect areas such as the mixing room tanks, solvent tanks and the
hydrocarbon installation with a total deluge system where a number of spray
heads in a group or groups are activated automatically from the fuse bulb in
any one spray head. The system should also be capable of manual
operation. In the case of the hydrocarbon tanks, in an emergency the
surface area shall be drenched at a rate 10 litres per square metre (0.2 gals,
per square foot) whilst pump sets, destench columns etc. should also be
covered by the water spray heads.
Suitable fire points and alarm systems should be installed in consultation
with the insurance Company and the Fire Prevention Officer. The sprinkler
installation company can also advise on good practices and on the setup of a
master control and enunciator to give fire incident location warning. Gas
sensor modules should be located in a position that can be monitored
during normal working hours and is easily accessible for the local Fire
Brigade.
The Fire Prevention Officer and Insurance Company may be consulted for
advice on number, type and siting of hand fire fighting appliances. It should
be noted that CO2 and Dry Powder units to British Standard 3465 may be
used on hydrocarbon — foam units are not considered suitable.
All operators should wear cotton or similar non-static producing clothing.
All matches and smoking materials should be prohibited in the factory area
and advice sought from the Fire Prevention Officer and H.M. Factory
Inspectorate concerning the type, wording and location of No Smoking and
other warning and instructional signs.
According to the category of Zone areas, all electrical equipment shall be
flameproofed to British Standard Code of Practice CP1003 and BS5345 and
the selection to British Standard BS4137, with design to British Standard
BS229. Where intrinsically safe equipment is required, this shall also be to
CP1003 certified by the manufacturer.
Other standards applicable to t^e electrical equipment and fire alarms may
be found in the Bibliography of Standards and Codes of Practice at the rear
of the handbook.
36
F-59
-------
30 tonnes tank showing Double destench column
F-60
-------
JH'.AOi'JU
The gas sensors, may be electro-catalytic suitable for hydrocarbons and as
described in the Department of Employment Technical Data Note No.45.
'Industrial Use of Flammable Gas Detectors'. These units usually have two
adjustable settings which trigger relays to actuate shut down valves, alarms,
etc. In accordance with agreed procedures.
The units may be used in the presence of fluorocarbons, however, in
extreme circumsntances the hot element may become inhibited due to
possible coating by chlorine from the fluorocarbon vapour. This does not
cause any permanent damage and will be burnt off by hydrocarbon passing
over the element, the response time may be slightly impaired.
A method to offset this problem is to fit a blanking cap overthe sensing head
during the filling of fluorocarbons.
Multi-point infra red sensor/analyser systems may also be used and may be
considered where fluorocarbon and hydrocarbon propellants are filled
simultaneously causing concern regarding the possible contamination of
the electro-catalytic systems.
The principle of the infra red system is to extract a sample of the atmosphere
in the monitored area and to convey the sample in cyclic pulses via plastic
tubes to the remotely located analyser which may be calibrated to give
warnings at appropriate levels of the L.E.L.
These systems usually employ a number of sampling tubes (multi-point)
leading to one analyser and the frequency and sequence of the samples
from the tubes would be decided upon examination of each separate
installation. The tubes may be of lengths up to 500 metres which, in turn,
may affect the response time.
The units must be recalibrated from time to time using trace gases for the
appropriate orange and red warning levels of the L.E.L. Since the instrument
module is remote from the sensing head a portable two way phone system
may be used by the two man team for calibration purposes at a time when the
production unit is shut down.
Precautions should be taken against static electricity by ensuring good
design of instal lation and earth continuity throughout the tank farm, pumps
and pipework, filling machinery as well as solvent storage, handling mixing
and filling. Precautions should also be taken within the laboratory.
Static is the electrification of materials through physical contact and separation
(single or multi-cycle) and the resultant static effects stem from the positive and
negative charges so formed. The generation of static cannot be prevented; it is
inherent in the interface of any dissimilar materials.
21
F-61
-------
*dttctfiLL
To reduce the risk of ignition, the following guidelines should be observed:-
1. Reduce risk of static built-up by firm fixing of all equipment and
pipework to reduce vibration and use anti-static materials
wherever possible.
2. Ensure all equipment is adequately bonded and checked regularly
for continuity, to prevent accumulation of charges and differences in
electrical potential occurring.
3 Flameproof all electrical equipment and avoid naked light and
incendive sparking.
4. Ventilate well and adopt good safety and checking procedures to
leakage or accumulation of ignitable mixture.
In our opinion, the statements in this Section represent good practice and
therefore form recommendations. Any compliance does not confer
immunity from relevant statutory or legal requirements.
-------
JS&OAIL!
Section 13
FURTHER INFORMATION
Aerofill Limited, as a major supplier of aerosol filling equipment, will be
happy to provide advice and assistance to existing and prospective
customers on installations using any category of propellent.
In recognition of the trend towards the use of hydrocarbons as
aerosol propellants, considerable research has been undertaken. Much of
the data obtained, as may be generally applied, is contained in this
handbook. Our sales engineers, supported by our internal engineering
expertise, will provide such assistance in interpretation to particular
installations as may be practical.
Copies of the main Statutes, Codes of Practice and other publications
mentioned in the text may be supplied with this handbook or obtained from
Aerofill. These are charged for, simply saving the time, effort and research of
customers obtaining them direct from the various sources. These
mandatory requirements are supported by our 19 years of accumulated
experience in the industry.
Aerofill Limited
Printing House Lane
Hayes
Middlesex UB3 1AP.
Tel: 01-848 4501.
39
F-63
-------
Bibliography
In anticipation of a need Aerofill Ltd have acquired a stock of the principal
publications mentioned in this handbook. This stock enables the readerto
obtain a library of Codes of Practice, Recommendations, British Standards
and other publications from one source.
1. Code of Practice for the storage of LPG at fixed installation — Health
& Safety Executive.
2. Code of Practice for the keeping of LPG in Cylinders and Similar
Containers — Health & Safety Executive.
3. Code of Practice for Electrical Apparatus associated equipment for the
use in explosive atmosphere of gas or vapour — British Standard
CP1003 — 3 parts.
4. Code of Practice for the selection, installation and maintenance of
electrical apparatus for use in potentially explosive atmospheres
— British Standard 5345.
5. Code of Practice for Fire Precautions in chemical plant — British
Standard CP 3013.
6. Flameproof enclosure of Electrical Apparatus — British Standard 229.
7. Guide to the selection of Electrical Equipment for the use of Division
(now referred to as Zone) 2 Areas — British Standard 4137.
8. Rubber Hose and Hose Assemblies for LPG Lines — British Standard
4089.
9. Specification for Identification of Pipelines — British Standard 1710.
10. Petroleum Acts 1928-1929 — H.M. Stationery Office.
11. Petroleum (Inflammable Liquids) Order 1971 -• H.M.S.O.
12. The Highly Flammable Liquids and Liquiefied Petroleum Gas
Regulations 1972 — H.M.S.O.
13. Guide to Safety in Aerosol Manufacture — British Aerosol
Manufactures Association.
14. Threshold Limit Values — Technical Data Note — Health &
Safety Executive.
15. Industrial use of Flammable Gas Detectors — Technical Data Note
— Health & Safety Executive.
Additionally there are many other Codes of Practice, Recommendations
and British Standards that cover every facet of an installation which may be
easily compiled from the lengthy Bibliography that will be found in the
appendix of the aforementioned list of publications.
Representation to the following may be made for full lists of publications on
the subjects of>
1. Tanks, pipelines, pumps, valve-fittings foundations and installations in
respect of LPG.
2. Electrical apparatus, lights, fire alarms and wiring.
3. Fire precautions, appliances, sprinkler systems and installation.
F-64
40
-------
4. Good operational practices. Codes of Practice etc.
British Standards Institution
2 Park Slreet
London W1A 2BS
Tel: 01-629 9000
Publications from: 101 Pentonvitle Road
London N1 9ND
Tel: 01-837 8801
The Liquiefied Petroleum Gas Industry Technical Association
All publications obtainable from: William Culross & Son Ltd
Coupar
Angus
Scotland
Her Majesty's Stationery Office
49 High Holborn
London WG1V GHB
For: Acts of Parliament & Statutory Orders
Health & Safety Executive publications
British Aerosol Manufacturers Association
Alembic House
93 Albert Embankment
London SE1 7TV
Tel: 01-582 1115
Fire Protection Association
Afdermary House
Queen Street
London EC4N 1TJ
Tel: 01-248 5222
The information in this guide is as accurate as possible but Aerofill
Ltd cannot accept any responsibility should it be found that the
information is inaccurate or incomplete, or becomes so, as a result of
future developments.
Printed in England by Lithgow Printers Ltd., East Sussex.
Designed by Jonathan Cantor & Assocs., London.
41 F-65
-------
-------
APPENDIX G
METRIC (SI) CONVERSION FACTORS
G -1
-------
APPENDIX G
METRIC (SI) CONVERSION FACTORS
Quantity
To Convert
From
To
Multiply By
Length:
in
cm
2.54
ft
m
0.3048
Area:
in2
cm2
6.4516
ft2
m2
0.0929
Volume:
in3
cm3
16.39
ft3
m3
0.0283
gal
m3
0.0038
Mass (weight):
oz (avoir.
)
kg
0.0283
lb
kg
0.4536
short ton
(ton)
Mg
0.9072
short ton
(ton)
metric ton (t)
0.9072
Pressure:
atm
kPa
101.3
mm Hg
KPa
0.133
psia
kPa
6.895
psig
kPa*
(psig)+14.696)x(6.895)
Temperature:
°F
cc*
(5/9)x("F-32)
°C
K*
"C+273.15
Caloric Value:
Btu/lb
kJ/kg
2.326
Enthalpy:
Btu/lbmol
kJ/kgmol
2.326
kcal/gniol
kJ/kgmol
4.184
Specific-Heat
Capacity:
Btu/lb-c F
kJ/kg-"C
4.1868
Dens ity:
lb/ft3
kg/m3
16.02
lb/gal
kg/m3
119.8
Concentration:
oz/gal
kg/m3
quarts/gal
cm3/m3
25,000
Flowrate:
gal/min
m3/ain
0.0038
gal/day
m3/day
0.0038
ft3/min
m3/day
0.0283
Velocity:
ft/min
m/min
0.3048
ft/sec
m/sec
0.3048
Viscosity:
centipoise
(CP)
Pa-s (kg/m-s)
0.001
^Calculate as indicated
G-2
-------
APPENDIX H
AEROSOL FORMULATIONS
H-1
-------
The following tables present current formulations for several aerosol
products in the categories of:
• Personal Products (Tables H-l through H-6);
• Household Products (Tables H-7 through H-10);
• Automotive/Industrial Products (Tables H-ll and H-12);
• Paints and Finishes (Table H-13);
• Insect Sprays (Tables H-14 and H-15);
• Food Products (Table H-16); and
• Animal Products (Table H-17).
The formulations list typical product weight, chemical compound names, and
composition by percent and weight as "propellant" and "other."
H-2
-------
TABLE H-l. HAIRSPRAY FORMULATIONS
Average
Product
Propellant
Other
Weight
Product Formula
oz.
%
oz.
%
oz.
Hair Spray: Reg Hold - 1 (l)a
10.10
Gantrez ES-225 (50% in EtOH)
0.00
4.00
0.40
N,N,-Dimethyl-octadecylamine
0.00
0.29
0.03
Dimethyl Phthalate
0.00
0.03
0.00
DC Fluid #193
o.oo
0.02
0.00
Fragrance
0.00
0.10
0.01
S. D. Alcohol 40-2 (Anhydrous)
0.00
67.56
6.82
Propellant A-31 or A-40
28.00
2.83
0.00
TOTAL
10.10
28.00
2.83
72.00
7.27
Hair Spray: Reg Hold - 2 (1)
10.10
Gantrez ES-225 (50% in EtOH)
0.00
4.00
0.40
Amino-methyl-propanol (95%)
0.00
0.09
0.01
DC Fluid #193
0.00
0.02
0.00
Fragrance
0.00
0.10
0.01
De-ionized Water
0.00
8.79
0.89
S. D. Alcohol 40-2 (Anhydrous)
0.00
61.00
6.16
Propellant A-31 or A-40
26.00
2.63
0.00
TOTAL
10.10
26.00
2.63
74.00
7.47
Hair Spray: Reg Hold - 3 (1)
10.10
Resyn 28-2930 (100%)
0.00
2 . 50
0.25
Amino-methyl-propanol (95%)
0.00
0.20
0.02
Dimethyl Phthalate
0.00
0.03
0.00
DC Fluid #193
0.00
0.04
0.00
Disodium Dodecylsulfosuccinate
0.00
0.20
0.02
Sodium benzoate
0.00
0.08
0.01
Fragrance
0.00
0.15
0.02
De-ionized Water
0.00
16.00
1.62
S. D. Alcohol 40-2 (Anhydrous)
0.00
44.80
4.52
Dimethyl ether
36.00
3.64
0.00
TOTAL
10.10
36.00
3.64
64.00
6.46
(Continued)
H-3
-------
TABLE H-l. (Continued)
Average
Product Propellant Other
Weight
Product Formula oz. % oz. % oz.
Hair Spray: Reg Hold - 4 (1) 10.10
Resyn 28-2930 (100%)
0.00
2.50
0.25
Amino-methyl-propanol (95%)
0.00
0.18
0.02
DC Fluid #193
0.00
0.06
0.01
Disodium Dodecylsulfosuccinate
0.00
0.20
0.02
Sodium benzoate
0.00
0.08
0.01
Fragrance
0.00
0.15
0.02
De-ionized Water
0.00
32.00
3.23
S. D. Alcohol 40-2 (Anhydrous)
0.00
28.83
2.91
Dimethyl ether
36.00
3.64
0.00
TOTAL 10.10
36.00
3.64
64.00
6.46
"Indicates sources of formulation data (see References at end of this
Appendix).
H- 4
-------
TABLE H-2. SHAVING GEL/CREAM FORMULATIONS
Average
Product
Propellant
Other
Product Formula
oz. %
oz.
%
oz.
Shaving Gel (2)
8.00
Stearic acid (95% purity)
0.00
2.00
0.16
Palmitic acid (97% purity)
0.00
5.80
0.46
Polyoxyethylene cetyl ether
0.00
1.00
0.08
Hydroxyalkyl cellulose
0.00
0.07
0.01
Carbopol 934
0.00
0.18
0.01
Propylene glycol dipelargonate
0.00
2.75
0.22
Sorbitol (70% solution)
0.00
10.00
0.80
Propylene glycol
0.00
3.30
0.26
Triethanolamine
0.00
4.20
0.34
Water
0.00
67.95
5.44
n-butane
0.55
0.04
0.00
n-pentane
0.00
2.20
0.18
TOTAL
8.00 0.55
0.04
99.45
7.96
Shaving Cream - 1 (1)
8.00
De-ionized Water
0.00
74.90
5.99
Lauric/Mystiric Acids
0.00
1.50
0.12
Stearic Acid (Triple X)
0.00
6.00
0.48
Lauryl/Myristyl Diethanolamine
0.00
0.50
0.04
Triethanolamine (99%)
0.00
3.90
0.31
Cetyl Alcohol, N. F.
0.00
0.50
0.04
Glycerin - 96%, U. S. P.
0.00
5.80
0.46
Mineral Oil, N. F. Grade
0.00
2.40
0.19
Methyl p.hydroxybenzoate
0.00
0.10
0.01
n.Propyl p.hydroxybenzoate
0.00
0.03
0.00
Fragrance
0.00
0.67
0.05
Lanolin Derivative
0.00
0.50
0.04
Propellant A-46
3.20
0.26
0.00
TOTAL
8.00
3.20
0.26
96.80
7.74
(Continued)
H-5
-------
TABLE H-2. (Continued)
Average
Product
Propellant
Other
Weight
Produce Formula
oz.
%
oz.
%
oz.
Shaving Cream - 2 (1)
8.00
De-ionized Water
0.00
79.50
6.36
Lauric/Mystiric Acids
0.00
1.00
0.08
Stearic Acid (Triple X)
0.00
7.00
0.56
Lauryl/Myristyl Diethanolamine
0.00
2.00
0.16
Sodium Hydroxide
0.00
0.50
0.04
Potassium Hydroxide
0.00
2.25
0.18
Glycerin - 96%, U. S. P.
0.00
4.00
0.32
Polyvinylpyrrolidone K30
0.00
0.15
0.01
Fragrance
0.00
0.30
0.02
Lanolin Derivative
0.00
0.20
0.02
Propellant A-46
3.10
0.25
0.00
0.00
TOTAL
8.00
3.10
0.25
96.90
7.75
Shaving Cream - 3 (1)
8.00
De-ionized Water
0.00
78.10
6.25
Lauric/Mystiric Acids
0.00
0.70
0.06
Stearic Acid (Triple X)
0.00
8.00
0.64
Sodium Lauryl Sulfate (30% Water
Solution)
0.00
1.50
0.12
Potassium Hydroxide
0.00
0.40
0.03
Triethanolamine (99%)
0.00
3.00
0.24
Glycerin - 96%, U. S. P.
0.00
2.50
0.20
Methyl p.hydroxybenzoate
0.00
0.10
0.01
n.Propyl p.hydroxybenzoate
0.00
0.04
0.00
Fragrance
0.00
0.36
0.03
Lanolin Derivative
0.00
2.00
0.16
Propellant A-46
3.30
0.26
0.00
TOTAL
8.00
3.30
0.26
96.70
7.74
H-6
-------
TABLE H-3. DEODORANT/ANTIPERSPIRANT FORMULATIONS
Average
Product
Propellant
Other
Product Formula
oz. %
oz.
%
oz.
Antiperspirant - (1)
4.00
Aluminum Chlorohydrate
0.00
8.00
0.32
Quaternium 18 Hectorite
(Bentonite 38)
0.00
0.82
0.03
S. D. Alcohol 40-2 (Anhydrous)
0.00
0.80
0.03
Dimethylsilicone (500 cstks.)
0.00
1.50
0.06
Isopropyl Myristate
0.00
1.00
0.04
Cyclomethicone F-251
0.00
7.63
0.31
Perfume Oil
0.00
0.25
0.01
Propellant A-31 or A-46
80.00
3.20
0.00
TOTAL
4.00 80.00
3.20
20.00
0.80
Personal Deodorant -1 (1)
4.00
Irgasan DP-3000* Germicide
0.00
0.11
0.00
Propylene Glycol
0.00
1.50
0.06
Fragrance
0.00
0.35
0.01
S. D. Alcohol 40-2 (Anhydrous)
0.00
58.00
2.32
Iso-butane (A-31)
40.00
1.60
0.00
TOTAL
4.00 40.00
1.60
59.96
2.40
Personal Deodorant - 2 (1)
4.00
Benzthionium Chloride
0.00
0.20
0.01
Dipropylene Glycol
0.00
1.05
0.04
Fragrance
0.00
0.25
0.01
S. D. Alcohol 40-2 (Anhydrous)
0.00
68.50
2.74
Propellant Blend A-46
30.00
1.20
0.00
16 w.% Propane in Iso-butane
TOTAL
4.00 30.00
1.20
70.00
2.80
(Continued)
H-7
-------
TABLE H-3. (Continued)
Average
Product Propeilant Other
Product Formula
oz. %
oz.
%
oz.
Personal Deodorant - 3 (1)
4.00
Methyl p-Hydroxybenzoate
0.00
0.03
0.00
n.Propyl p-Hydroxybenzoate
0.00
0.06
0.00
Benzyl p-hydroxybenzoate
0.00
0.08
0.00
Propylene Glycol, U. S. P,
0.00
1.03
0.04
Fragrance
0.00
0.30
0.01
S. D. Alcohol 40-2 (Anhydrous)
0.00
63.50
2.54
Propeilant Blend A-46
35.00
1.40
0.00
16 w.% Propane In Iso-butane
TOTAL
4.00 35.00
1.40
65.00
2.60
Personal Deodorant - 4 (1)
4.00
Irgasan DP-3000* Germicide
0.00
0.12
0.00
Dipropylene Glycol
0.00
2.00
0.08
Zinc Phenolsulfate***
0.00
1.00
0.04
Fragrance
0.00
0.38
0.02
S. D. Alcohol 40-2 (Anhydrous)
0.00
13.35
0.53
De-ionized water
0.00
47 .00
1.88
Sodium Benzoate
0.00
0.15
0.01
Dimethyl ether
36.00
1.44
0.00
0.00
TOTAL
4.00 36.00
1.44
64.00
2.56
*2,4,4'-Trichloro-2'-hydroxydiphenylether
H-8
-------
TABLE H-4. COLOGNE FORMULATIONS
Average
Product Propellant Other
Weight
Product Formula oz. % oz. % oz.
Cologne - 1 (1) 2.00
Fragrance
0.
,00
4.
,00
0.
08
Di-n.butyl Phthalate
0.
,00
2.
.00
0.
04
Sodium Saccharinate
0.
,00
0.
.01
0.
.00
FD&C and/or D&C Dye Solution
0.
00
0.
09
0.
.00
S. D. Alcohol 40 of 39C (Anhydrous)
0.
00
65.
00
1.
.30
De-ionized Water
0.
,00
13.
00
0.
.26
HFC-152a or HFC-22
15.
,90
0.
32
0,
.00
TOTAL 2
.00
15,
.90
0.
,32
84.
.10
1.
.68
Cologne - 2 (1) 2
.00
Fragrance
0.
.00
4
.00
0,
.08
S.D. Alcohol 40 or 39C (Anhydrous)
0.
00
76.
.00
1,
,52
Iso-butane A-31
t
o
.00
0.
.40
0,
.00
TOTAL 2,
1 o
o
20.
1 o
O
0.
.40
00 I
°
.00
1
.60
H-9
-------
TABLE H-5. OTHER HAIR PRODUCTS FORMULATIONS
Product Formula
Average
Product
Weight
oz.
Propellant
oz,
Other
oz.
Hair Mousse - 1 (1)
10.00
Polyquaternlum 4
0.00
0.60
0.06
Dimethacone
0.00
0.15
0.02
Arquad T-50
0.00
0.10
0.01
Octoxynol 9
0.00
0.15
0.02
Emulsifying Wax NF
0.00
0.15
0.02
Deionized Vater
0.00
75.B5
7.58
Perfume Oil
0.00
0.10
0.01
S.D. Alcohol 40-2 Anhydrous
0.00
14.90
1.49
Propane/Iso-butane (A-46)
8.00
0.80
0,00
TOTAL
10.00
8.00
0.80
92.00
9.20
Hair Mousse - 2 (1)
10.00
Polyquaternium 11
0.00
1.32
0.13
Polyquaternlum 4
0.00
1.00
0.10
Silicone
0.00
0.15
0.02
Lexein CP-125
0.00
0.20
0.02
Lexein S620
0.00
0.14
0.01
Aloe Vera
0.00
0.05
0.01
PEG-150
0.00
0.26
0.03
Quaternium 52
0.00
0.20
0.02
Polysorbate 20
0.00
0.05
0.01
Deionized Water
0.00
85.42
8.54
Fragrance
0.00
0.21
0.02
S.D. Alcohol 40-2 Anhydrous
0.00
3.00
0.30
Propellant BIP-55
8.00
0.80
0.00
TOTAL
10.00
8 .00
0. B0
92.00
9.20
Hair Lusterizer - 1 <1)
10.00
Isodecyl Oleate
0.00
5.00
0.50
Odorless Mineral Spirits
0.00
35.00
3.50
Mink Oil
0.00
0.10
0.01
Fragrance
0.00
0.10
0.01
S.D. Alcohol 40-2 Anhydrous
0.00
19.80
1.98
Propane/Iso-butane (A-46)
40.00
4.00
0.00
TOTAL
10.00
40.00
4.00
60.00
6.00
H-10
-------
TABLE H-6. MEDICINAL AND PHARMACEUTICAL FORMULATIONS
Average
Product Propellant Other
Weight
Product Formula oz. % oz. % oz.
Beta-Adrenergic Bronchodilator 0.50
Formula (1)
Terbutaline Sulfate
0.00
0.71
0.00
Sorbitan Trioleate
0.00
1.00
0.01
CFC-11
24.57
0.12
0.00
CFC-114
24.57
0.12
0.00
CFC-12
49.14
0.25
0.00
TOTAL
0.50
98.29
0.49
1.71
0.01
iginal Contraceptive Mousse (1)
2.50
Nonxynol 9
0.00
8.00
0.20
Lauric/Myristic Acids
0.00
2.50
0.06
Stearic/Palmitic Acids
0.00
3.50
0.09
Triethanolamine
0.00
2.20
0.06
Glyceryl Monostearate
0.00
2.50
0.06
Polyoxyethylene (20)
0.00
0.00
Sorbitan Mono-oleate
0.00
2.50
0.06
Polyoxyethylene (20)
0.00
0.00
Sorbitan Mono-laurate
0.00
3. 50
0.09
Polyethylene 600 Glycol
0.00
1.50
0.04
Polyvinylpyrrolidone K-30
0.00
1.00
0.03
Benzethonium Chloride, USP
0.00
0.20
0.01
Deionized water
0.00
67.60
1.69
Propellant A-46
5.00
0.13
0.00
TOTAL
2.50
5.00
0.13
95.00
2. 38
H-11
-------
TABLE H-7. HOUSEHOLD CLEANER FORMULATIONS
Average
Product
Propellant
Other
Product Formula
oz.
%
oz.
%
oz.
Oven Cleaner - 1 (1)
12.00
Sodium Hydroxide
0.00
5.00
0.60
Sodium Nitrite
0.00
0.20
0.02
Triethanolamine - 99%
0.00
1.00
0.12
Tetrosodium EDTA - 38%
0.00
1.00
0.12
Deionized Water
0.00
87.80
10.54
Iso-butane (A-31)
5.00
0.60
0.00
TOTAL
12.00
5.00
0.60
95.0
11.40
Oven Cleaner - 2 (1)
12.00
Potassium Formate
0.00
6.00
0.72
Potassium Acetate
0.00
6.00
0.72
Calcium Dodecylbenzene Sulfonate
0.00
3.00
0. 36
Compatible Thickener
0.00
0.50
0.06
Sodium Nitrite
0.00
0.20
0.02
Deionized Water
0.00
78.30
9.40
Iso-butane (A-31)
6.00
0.72
0.00
TOTAL
12.00
6.00
0.72
94. 00
11.28
Rug & Carpet Cleaner Product
(1) 20.00
Sodium Lauryl Sulfate
(Very low in Chloride)*
0.00
1.60
0.32
Magnesium Lauryl Sulfate
(Very low in Chloride)**
0.00
1.20
0.24
Sodium Lauryl Sarkosinate
30% in water***
0.00
3.00
0.60
Styrene Maleic Anhydride Copolymer
15% in water
0.00
20.00
4.00
Optical Brightener; as Calcofluor SD
(Optional)
0.00
0.02
0.00
Ammonium Hydroxide (28% NH3
in water)
0.00
0.16
0.03
Fragrance
0.00
0.08
0.02
Deionized Water
0.00
66. 44
13.29
Iso-butane A-31
7.50
1. 50
0.00
TOTAL
20.00
7.50
1.50
92.50
18.50
(Continued)
H* 12
-------
TABLE H-7. (Continued)
Product Formula
Average
Product
Weight
oz.
Propellant
oz.
Other
oz.
Window Cleaner - 1 (1)
12.00
Isopropanol - 99%
0.00
4.00
0.48
Propylene Glycol Monoethyl Ether
0.00
3.00
0.36
Ammonium Lauryl/Myristyl Alcohol
0.00
0.20
0.02
Sodium Nitrite
0.00
0.10
0.01
Ammonia (29% NH3 in water)
0.00
0.20
0.02
Deionized water
0.00
89.00
10.68
Iso-butane A-31
3.50
0.42
0.00
TOTAL
12.00
3.50
0.42
96.50
11.58
Window Cleaner - 2 (1)
12.00
Isopropanol - 99%
0.00
5.00
0.60
Propylene Glycol Monoethyl Ether
0.00
2.50
0.30
Sodium Lauryl Sulfate
0.00
0.20
0.02
Lauryl Di-isopropanolamide
0.00
0.10
0.01
Sodium Nitrite
0.00
0.20
0.02
Ammonia (29% NH3 in water)
0.00
0.20
0.02
Deionized water
0.00
88.50
10.62
Iso-butane A-31
3.30
0.40
0.00
TOTAL
12.00
3.30
0.40
96.70
11.60
Window Cleaner - 3 (1)
12.00
Isopropanol - 99%
0.00
4.00
0.48
Butoxyethanol
0.00
2.00
0.24
Lauryl Di-isopropanolamide
0.00
0.10
0.01
Ammonium Lauryl/Myristyl Alcohol
0.00
0.10
0.01
Sodium Nitrite
0.00
0.10
0.01
Ammonia (29% NH3 in water)
0.00
0.20
0.02
Deionized water
0.00
90.00
10.80
Iso-butane A-31
3.50
0.42
0.00
TOTAL
12.00
3.50
0.42
96.50
11.58
(Continued)
H-13
-------
TABLE H-7. (Continued)
Average
Product Propellant Other
Weight
Product Formula oz. % oz. % oz.
Disinfectant Cleaner - (1) 12.00
Sodium meta-Silicate 5-Hydrate
0.
.00
0,
.10
0.
00
Tetrasodium EDTA (38% A.I. in
Water)****
0.
.00
4.
.12
0,
,50
BTC 2125M (50% A.I. in Water)
0.
,00
0.
.40
0.
04
Sodium Benzoate
0.
,00
0.
.10
0.
01
Sodium Tetraborate 10-Hydrate
0,
,00
0.
.10
0.
01
Morpholine
0.
.00
0.
,20
0.
.02
Ammonium Hydroxide (29% NH3 in
water)
0.
,00
0,
.10
0.
13
Atlas G-3821 Non-ionic Surfactant*****
0.
.00
0,
.50
0.
06
Butyl Cellosolve
0,
.00
6,
.00
0.
,72
Potassium Hydroxide (45% A.I.
in Water)
0,
.00
0,
.05
0,
.01
Fragrance
0
.00
0,
.15
0
.02
Deionized water
0
.00
80
.18
9
.62
Iso-butane A-31
7.00
0.
.84
0,
,00
TOTAL
12.00
7.00
0.
.84
93,
.00
11,
,16
* As Maprofix 563, by the Onyx Division of Witco Chemical Co.
** As Maprofix Mg.
*** As Maprosil 30.
**** Tetrasodium Ethylenediamine-tetraacetate, such as Cheelox BF-13, or
Versene 30 (Dow).
***** By ICI America, Inc.
H-14
-------
TABLE H-8. ROOM DEODORANT/DISINFECTANT FORMULATIONS
Average
Product
Propellant
Other
Weight
Product Formula
oz.
%
oz.
%
oz.
Air Freshener - 1 (1)
8.00
Fragrance
0.00
1.00
0.08
Odorless Petroleum Distillates
0.00
6.28
0.50
Lampolamide 5 Liquid (Croda)
0.00
0.72
0.06
Sodium Benzoate
0.00
0.15
0.01
Deionized water
0.00
59.85
4.79
Propellant A-60
32.00
2.56
0.00
TOTAL
8.00
32.00
2.56
68.00
5.44
Air Freshener - 2 (1)
8.00
Fragrance
0.00
1.50
0.12
Propellant A-60
90.00
7.20
0.00
Dimethyl Ether
8.50
0.68
0.00
TOTAL
8.00
98.50
7.88
1.50
0.12
Air Freshener - 3 (1)
8.00
Fragrance
0.00
2.00
0.16
Odorless Petroleum Distillates
O.OO
6.00
0.48
S.D. Alcohol 40-2 (Anhydrous)
0.00
38.00
3.04
Deionized water
0.00
4.00
0.32
Propellant A-60
50.00
4.00
0.00
TOTAL
8.00
50.00
4.00
50.00
4.00
Room Disinfectant - 1 (1)
8.00
o.Phenyl-phenol (95% purity)
0.00
0.11
0.01
S.D. Alcohol 40-2 (Anhydrous)
0.00
73.38
5 .87
Fragrance
0.00
0.11
0.01
Sodium Benzoate
0.00
0.20
0.02
Morpholine
0.00
0.20
0.02
Deionized water
0.00
21.00
1.68
Carbon Dioxide
5.00
0.40
TOTAL
8.00
5.00 0.40
95.00 7.60
(Continued)
H-15
-------
TABLE H-8. (Continued)
Average
Product Propellant Other
Weight
Product Formula oz. % 02. % oz.
Room Disinfectant - 2 (1) 8.00
BTC-2125M (50% in Water)
0.00
0.28
0.02
Atlas G-271 (35% in Water)
0.00
0.12
0.01
S.D. Alcohol 40-2 (Anhydrous)
0.00
52,07
4.17
Fragrance
0.00
0.11
0.01
Sodium Benzoate
0.00
0.22
0.02
Morpholine
0.00
0.20
0.02
Deionized water
0.00
25.00
2.00
Propellant Blend A-40
22.00
1.76
0.00
TOTAL
8.00 22.00
1.76
78.00
6.24
H-16
-------
TABLE H-9. LAUNDRY AID FORMULATIONS
Average
Product
Propellant
Other
Product Formula
oz.
%
oz.
%
oz.
Pre-laundry Cleaners - 1 (1)
16.00
Linear primary or secondary alcohol
polyglycol ether (2-4 mol ETO)
0.00
12.00
1.92
Linear primary or secondary alcohol
polyglycol ether (7-10 mol ETO)*
0.00
12.00
1.92
Diethylene Glycol Monomethyl Ether
0.00
12.00
1.92
Sodium Laurate/Myristate
0.00
0.40
0.06
Isopropanol - 99%
0.00
4.00
0.64
Low-odor n.Paraffinic or iso.Paraffinic
Solvent (C10-C14 hydrocarbons)
0.00
20.00
3.20
Ammonium Hydroxide (28% NH3 in water)
0.00
0.50
0.08
Fragrance (Typically lemon/lime)
0.00
0.50
0.08
Enzyme Concentrate (Optional)
0.00
1.00
0.16
Deionized Water
0.00
30.10
4.82
Propane A-10B or Propellants A-B5
7.50
1.20
0.00
TOTAL
16.00
7.50
1.20
92.50
14.80
Pre-laundry Cleaners - 2 (1)
16.00
Linear primary or secondary alcohol
polyglycol ether (7-10 mol ETO)*
0.00
10.00
1.60
Diethylene Glycol Monomethyl Ether
0.00
5,00
0.80
Isopropanol - 99%
0.00
5,00
0.80
Low-odor n.Paraffinic or iso.Paraffinic
Solvent (C10-C14 hydrocarbons)
0.00
76.70
12.27
Fragrance (Typically lemon/lime)
0.00
0.50
0.08
Carbon Dioxide
2.80
0.45
0.00
TOTAL
16.00
2.80
0.45
97.20
15.55
Spray Starch - 1 (1)
16.00
Amaizo No, 513 Pearl Starch
0.00
2.30
0.37
Sodium Tetraborate 10-Hydrate
0.00
0.30
0.05
Silcone Emulsion LE-463,346 or equal
0.00
0.40
0.06
Silcone Antifoam Emulsion
0.00
0.15
0.02
Sodium Nitrite or Sodium Benzoate
0.00
0.15
0.02
Fragrance
0.00
0.02
0.00
Glutaraldehyde (50%) or
0.00
0.00
Formaldehyde (37% in Water)
0.00
0.04
0.00
Optical Brightener
0.00
0.02
0.00
Deionized Water
0.00
91.10
14.58
Iso-butane
5.50
0.88
0.00
TOTAL
16.00
5.50
0.88
94.50
15.12
(Continued)
H-17
-------
TABLE H-9. (Continued)
Product Formula
Average
Product
Weight
oz.
Propellant
% oz.
Other
% oz.
Spray Starch - 2 (1)
16.00
Penford Gum 290 or Equilvalent
0.00
2.75
0.44
Sodium Tetraborate 10-Hydrate
0.00
0.40
0.06
Silcone Emulsion LE-463,346 or equal
0.00
0.50
0.08
Silcone Antifoam Emulsion
0.00
0.10
0.02
Fragrance
0.00
0.03
0.00
Glutaraldehyde (50%) or
Formaldehyde (37% in Water)
0.00
0.06
0.00
Deionized Water
0.00
90.16
14.43
Iso-butane
6.00
0.96
0.00
TOTAL
16.00
6.00
0.96
94.00
15.04
Spray Starch - 3 (1)
16.00
EO-Size 5795 Starch or Equivalent
0.00
3.00
0.48
Sodium Tetraborate 10-Hydrate
0.00
0.45
0.07
Silcone Emulsion LE-463,346 or equal
0.00
0.44
0.07
Silcone Antifoam Emulsion
0.00
0.10
0.02
Sodium Nitrite or Sodium Benzoate
0.00
0.10
0.02
Fragrance
0.00
0.03
0.00
Glutaraldehyde (50%) or
Formaldehyde (37% in Water)
0.00
0.04
0.01
Deionized Water
0.00
90.00
14.40
Iso-butane
5.84
0.93
0.00
TOTAL
16.00
5.84
0.93
94.16
15.07
Absorbent Silica Cleaner - (1)
7.00
Fumed Silica Powder
0.00
6.00
0.42
1,1,1-Trichloroethane
0.00
68.00
4.76
Isopropanol - 99%
0.00
10.00
0.70
Fragrance
0.00
0.05
0.00
Propane A-108
15.95
1.12
0.00
TOTAL
7.00
15.95
1.12
84.05
5.88
May be replaced with octyl or nonyl phenol polyoxyethylene (9-13 mol ETO)
of other non-ionics of similar HLB value.
H-18
-------
TABLE H-10. WAX/POLISH FORMULATIONS
Average
Product
Propellent
Other
Weight
Product Formula
oz.
%
oz.
%
oz.
Furniture Polish - 1 (1)
14.00
Wax S and Wax N (1:1 ratio)
Hoechst
0.00
1.25
0.18
Silicone Emulsion LE-461
(50% A.I.) UCC
0.00
1.40
0.20
Silicone Emulsion LE-462
(50% A.I.) UCC
0.00
0.35
0.05
Arlacel C (Non-ionic surfactant)
1CI Am.
0.00
0.15
0.02
Isopar C or E
0.00
2.00
0.28
Lemon Oil, Technical Grade
0.00
0.75
0.11
Glutaraldehyde (50% A.I.) UCC
0.00
0.05
0.01
Sodium Nitrite
0,00
0.05
0.01
Deionized Water
0.00
87.00
12.18
Iso-butane A-31
7.00
0.98
0.00
TOTAL
14.00
7.00
0.98
93.00
13.02
Furniture Polish - 2 (1)
14.00
Wax S and Wax N (1:1 ratio)
Hoechst
0.00
1.25
0.18
Silicone Emulsion LE-461
(50% A.I.) UCC
0.00
1.40
0.20
Silicone Emulsion LE-462
(50% A.I.) UCC
0.00
0.35
0.05
Arlacel C (Non-ionic
surfactant) ICI Am.
0.00
1.25
0.18
Isopar C or E
0.00
33.00
4.62
Lemon Oil, Technical Grade
0.00
0.60
0.08
Glutaraldehyde (50% A.I.) UCC
0.00
0.03
0.00
Sodium Nitrite
0.00
0.05
0.01
Deionized Water
0.00
44.57
6.24
Iso-butane A-31
17.50
2.45
0.00
TOTAL
14.00
17.50
2.45
82.50
11.55
(Continued)
H-19
-------
TABLE H-10. (Continued)
Average
Product Propellant Other
Weight
Product Formula oz. % oz. % oz.
Wood Panel Polish (1) 14.00
D. C. 536 Fluid*
0.00
2.00
0.28
D. C. 200 Fluid**
0.00
2.00
0.28
Uitcamide 511 -
Witco Chem. Co.
0.00
1.00
0.14
Isopar L and/or Isopar
M - Exxon
0.00
26. 50
3.71
Isopar K - Exxon
0.00
65.20
9.13
Fragrance
0.00
0.05
0.01
Isopropanol (Anhydrous)
0.00
0.25
0.04
Carbon Dioxide
3.00
0.42
0.00
TOTAL
14.00 3.00
0.42
97.00
13.58
* An aminofunctional polydimethyl-siloxane copolymer - Dow Corning
Corporation
** Dimethylsiloxane polymer - Dow Corning Corp. (12,500 cstks)
H-20
-------
TABLE H-ll. MAJOR AUTOMOTIVE/INDUSTRIAL PRODUCT FORMULATIONS
Product Formula
Average
Product
Weight
oz.
Propellant
oz.
Other
oz.
Spray Lubricant (2)
Mineral Oils
Isobutylene polymers
Propellant
TOTAL
Carburetor/Choke Cleaner (2)
Aliphatic/Aromatic Hydro-
14.00
14.00
12.00
5.00
0.00
0.00
0.70
5.00 0.70
90.00
5.00
95.00
12.60
0. 70
0.00
13.30
carbons (e.g., Toluene,
0.00
88.00
10.56
Acetone)
Butane
12.00
1.44
0.00
TOTAL
12.00
12.00
1.44
88.00
10.56
Engine Starting Fluid (1)
8.96
Diethyl ether
0.00
91.00
8.15
Carbon Dioxide
9.00
0.81
0.00
TOTAL
8.96
9.00
0.81
91.00
8.15
Rotary Tablet Machine Die
14.00
Lubricant - 1 (1)
Lecithin
0.00
2.00
0.28
Sorbitan Trioleate
0.00
0.50
0.07
Ethanol (Anhydrous)
0.00
2.50
0.35
CFC-113
0.00
70.00
9.80
CFC-12
25.00
3.50
0.00
TOTAL
14.00
25.00
3.50
75.00
10.50
H-21
-------
TABLE H-12. FORMULATIONS FOR MISCELLANEOUS AUTOMOTIVE/INDUSTRIAL AEROSOLS
Product Formula
Average
Product
Weight
oz.
Propellant
oz.
Other
oz.
Gasket Adhesive (1)
16.00
Isopropanol
0.
,00
10.
,00
1.
.60
Resin 80-1211
0.
,00
5.
,00
0,
.80
Stabilite Ester Number 3
0,
,00
5
,00
0
.80
Methylene Chloride
0.
,00
50,
.00
8.
.00
Xylenes
0.
,00
10,
.00
1.
.60
Propellant Blend A-70
20,
.00
3.
.20
0
.00
TOTAL
16.00
20
.00
3.
,20
80
.00
12
.80
Brake Cleaner (3)
Alcohol (methanol or
ethanol) or chlorinated
solvents-propellant not
specified
TOTAL
Spray Undercoating (2)
Pigment
Propellant (unspecified
non-CFC VO)
Solvent (unspecified
non-CFC VO)
Total
Tire Inflator/Sealant (4)
Unspecified non-CFC VOs
(One "active"ingredient
also serves as propellant)
Total
18.10
18.10
12.00
0.00 100.00 18.10
25.00 3.00
0.00 0.00 100.00 18.10
0.00 50.00 6.00
0.00
0.00 25.00 3.00
12.00 25.00 3.00 75.00 9.00
11.00
0.00 100.00 11.00
11.00
0.00 0.00 100.00 11.00
(Continued)
H- 22
-------
TABLE H-12. (Continued)
Average
Product Propellant Other
Product Formula
oz.
%
oz.
%
oz.
Vinyl/Upholstery Cleaner (1)
18.00
Sodium Lauroyl Sarcoslnate
(30% A.I. in Water)
0.00
1.50
0.27
Sodium Lauryl Sulfate Powder
USP (CI- free)
0.00
1.55
0.28
Dupanol WAT
0.00
1.10
0.20
Ammonium Hydroxide (26-28%)
0.00
0.09
0.02
Silicone SM-62 General Electric
0.00
0.90
0.16
Perfume
0.00
0.05
0.01
Isopar C Exxon
0.00
2.75
0.50
Sodium meca-Silicate 5-Hydrate
0.00
0.10
0.02
Deionized Water
0.00
85.96
15.47
Propellant Blend A-46
6.00
1.08
0.00
TOTAL
18.00
6.00
1.08
94,00
16.92
Electronic Cleaners (5)
16.00
CFC-113
75.00
12.00
Propellant (CFC-12)
25.00
4.00
TOTAL
16.00
25.00
4.00
75.00
12.00
Engine Degreaser (1)
14.00
Non-ionic Surfactants
0.00
5.00
0.70
Xylenes
0.00
20.00
2.80
Deodorized Kerosene
0.00
72.00
10.08
Carbon Dioxide
3.00
0.42
0.00
TOTAL
14.00
3.00
0.42
97.00
13.58
Windshield De-icer (1)
16.00
Methanol-Technical Grade
0.00
54.00
8.64
Propylene Glycol - Technical
Grade
0.00
18.00
2.88
Deionized Water
0.00
25.00
4.00
Morpholine
0.00
0.10
0.02
Span 80 or Igepal CO-410 Non-
ionics
0.00
0.05
0.01
Sodium Benzoate
0.00
0.05
0.01
Carbon Dioxide
2.80
0.45
0.00
TOTAL
16.00
2.80
0.45
97.20
15.55
H- 23
-------
TABLE H-13. PAINT/PRIMER/VARNISH FORMULATIONS
Average
Product Propellant Other
Weight
Product Formula oz. % oz. % oz.
Paint - Acrylic Metallic (1) 12.00
Acryloid B72 (50% A.I.)
0,
,00
8.
,00
0.
96
Acryloid A101 (40% A.I.)
0,
,00
1,
,00
0.
12
Gold Powder #6238
0.
.00
4,
.00
0.
,48
Propylene Glycol Monomethyl Ether
0.
00
2.
.00
0.
,24
Nonylphenoxy Polyethoxy Ethanol
0.
,00
0,
.10
0,
,01
Toluene
0.
.00
28,
.20
3,
,38
Xylenes
0.
,00
12.
,40
1,
,49
Acetone
0.
,00
15,
.40
1,
,85
Hydrocarbon Propellant Blend A-85
28
.90
3.
.47
0,
.00
TOTAL
12
.00
28
.90
3.
.47
71,
.10
8~
"53
Paint - Acrylic (1)
12,
.00
Corboset 514H (40% A.I.)
0.
.00
25
.00
3,
.00
Tint Aid (Black WD-2350)
0,
.00
5
.00
0
.60
Titanium Dioxide Powder (R-940)
0,
.00
1
.00
0
.12
Propylene Glycol Monomethyl Ether
0,
,00
5
.00
0
.60
Isopropanol
0,
.00
8
.00
0
.96
Nonylphenoxy Polyethoxy Ethanol
0.
.00
0
.35
0
.04
Fluoroacrylic FC-430 Surfactant
0,
.00
0
.02
0
.00
Hi-Sil T-600 (Silica)
0
.00
0
. 14
0
.02
Magnesium Aluminum Silicate
0.
.00
0
.30
0
.04
De-ionized Water
0,
.00
10
.19
1
.22
Dimethyl Ether
45
.00
5
.40
0
.00
TOTAL
12.
.00
45
.00
5,
.40
55
.00
6~
"60
(Continued)
H-24
-------
TABLE H-13. (Continued)
Average
Product Propellant Other
Product Formula
oz.
%
oz.
%
oz.
Paint - Alkyd - 1 (1)
12.00
Tint Aid (Black WD-2350)
0.00
5.00
0.60
Beckosol 13-400 (75% A.I.)
0.00
13.00
1.56
Ammonium Hydroxide (29% NH3)
0.00
1.15
0.14
Titanium Dioxide Powder (R-940)
0.00
2.00
0.24
Propylene Glycol Monomethyl Ether
0.00
5.00
0.60
Isopropanol
0.00
8.00
0.96
Nonylphenoxy Polyethoxy Ethanol
0.00
0.45
0.05
Fluoroacrylic FC-430 Surfactant
0.00
0.02
0.00
Hi-Sil T-600 (Silica)
0.00
0.14
0.02
Magnesium Aluminum Silicate
0.00
0.12
0.01
Drier: Cobalt Hydro Cure II
0.00
0.10
0.01
Drier: Zirconium Cem
0.00
0.08
0.01
De-ionized Water
0.00
19.94
2.39
Dimethyl Ether
45.00
5.40
0.00
12.00
45.00
5.40
55.00
6.60
Paint - Alkyd - 2 (1)
12.00
Tint Aid (Black UD-2350)
0.00
5.00
0.60
Beckosol 13-400 (75% A.I.)
0.00
13.00
1.56
Ammonium Hydroxide (29% NH3)
0.00
1.15
0.14
Propylene Glycol Monomethyl Ether
0.00
5.00
0.60
Isopropanol
0.00
8.00
0.96
Nonylphenoxy Polyethoxy Ethanol
0.00
0.50
0.06
Fluoroacrylic FC-430 Surfactant
0.00
0.02
0.00
Hi-Sil T-600 (Silica)
0.00
0.14
0.02
Magnesium Aluminum Silicate
0.00
0.15
0.02
De-ionized Water
0.00
22.04
2.64
Dimethyl Ether
45.00
5.40
0.00
TOTAL
12.00 45.00
5.40
55.00
6.60
H- 25
-------
TABLE H-14. SPACE INSECTICIDE FORMULATIONS
Average
Product Propellant Other
Weight
Product Formula oz. % oz. % oz.
Total Release Insect Fogger - (1) 12.50
Pyrethrum Extract - 20%
0.00
2.00
0.25
Piperonyl Butoxide; Technical
0.00
1.00
0.13
Pertroleum Distillates
0,00
12.00
1.50
1,1,1-Trichloroethane
0.00
55.00
6.88
Propane A-106
30.00
3.75
0.00
TOTAL
12.50
30.00
3.75
70.00
8.75
Insecticide (2) 14.00
Pyrethins
0.00
0.25
0.04
Piperonyl butoxide
0.00
0.80
0.11
Petroleum distillates
0.00
1.04
0.15
Inert ingredients
0.00
0.91
0.13
(Emulsifier/Corrosion Inhib)
Inert ingredients (Water)
0.00
67.00
9.38
Butane/Isobutane
30.00
4.20
0.00
TOTAL
14.00
30.00
4.20
70.00
o
CO
CJ\
H- 26
-------
TABLE H-15. RESIDUAL INSECTICIDE FORMULATIONS
Average
Product Propellant Other
Weight
Product Formula oz. % oz. % oz.
Insect Repellent (6) 14.00
n,n-dimethyl-m-toluamide
0.00
19.00
2.66
Other isomers
0.00
1.00
0.14
2,3,4,5-bis-(2-butylene)
0.00
1.00
0.14
tetrahydro- 2 -furaldehyde
n-octyl dicycloheptene
0.00
4.00
0.56
dicarboximide
Inerts (alcohol and propellant)
30.00
4.20
45.00
6.30
TOTAL
14.00
30.00
4.20
70.00
9.80
it and Roach Killer (6)
11.00
d-trans-Allethrin
0.00
0.05
0.01
Piperonyl butoxide
0.00
0.10
0.01
N-Octyl dicycloheptene
0.00
0.17
0.02
dicarboximide
0-Isopropoxyphenyl
0.00
0.50
0.06
methyl carbonate
Petroleum distillate
0.00
86.25
9.49
Propellant
12.90
1.42
0.00
TOTAL
11.00
12.90
1.42
87.07
9.58
H-27
-------
TABLE H-16. MAJOR FOOD PRODUCTS FORMULATIONS
Product Formula
Average
Product
Weight
oz.
Propellant
oz.
Other
oz.
Whipped Cream (7)
Synthetic Dairy Cream
Nitrous oxide
TOTAL
11.00
11.00
17.50
0.00
1.93
17.50 1.93
82.50
82.50
9.08
0.00
9.08
Frypan Spray (7)
Corn oil, grain alcohol,
lecithin
Propellant
6.00
0.00
31.00 1.86
69.00
4.1 4
0.00
TOTAL
6.00
31.00 1.86
69.00
4.14
H- 28
-------
TABLE H-17. ANIMAL PRODUCTS FORMULATION
Average
Product Propellant Other
Weight
Product Formula oz. % oz. % oz.
Flea and Tick Spray 7.00
for Dogs - (6)
2-chloro-l(2,3,5-trichlorophenyl)
0.00
0.99
0.07
vinyl dimethyl phosphate
Inerts (incl. propellant)
5.00 0.35
94.01
6.58
TOTAL 7.00
5.00 0.35
95.00
6.65
H- 29
-------
REFERENCES FOR APPENDIX H
1. Nelson, T.P., and S.L. Wevill. Aerosol Industry Success in Reducing CFC
Propellant Usage. EPA-600/2-89-062 (NTIS PB90-143447). U.S.
Environmental Protection Agency, Research Triangle Park, NC, November
1989.
2. Jones, A., H. Rich, G. Sewell, M. Rogozen, and N. Katz. Photochemically
Reactive Organic Compound Emissions (NTIS PB88-216940).* U.S.
Environmental Protection Agency, Region 2, New York, NY, November 26,
1986. (») EPA-902/4-86-001.
3. Examination of brake cleaners at a local auto supply store, Radian
Corporation, Austin, TX, June 1989.
4. Examination of tire sealant at local auto parts store, Radian
Corporation, Austin, TX, September 1988.
5. Uphouse, H.G. Industrial Aerosol Sprays. Aerosol Age, January 1983.
6. Control Techniques for Reducing Emissions of Photochemically Reactive
Organic Compounds from Consumer and Commercial products. B/834-025-
29a/#14, Science Applications International Corporation for the U.S.
Environmental Protection Agency, Region 2, New York, NY, September 30,
1987.
7. Johnsen, Montfort A. The Aerosol Handbook, Second Edition. Dorland
Publishing Company, Mendham, NJ, 1982.
H-30
-------
TECHNICAL REPORT DATA
(Please read Inurvctians on the rcvenc before comptr
1. REPORT NO. 2.
EPA-600/2-91-0 56
3
a. title and subtitle
Manual for Non-CFC Aerosol Packaging: Conversion
from CFC to Hydrocarbon Propellants
5. REPORT DATE
September 1991
6. PERFORMING ORGANIZATION CODE
7. AUTHOR(S)
K.M. Adams, K. E. Hummel, T. P. Nelson, and
S. L. Wevill
8. PERFORMING ORGANIZATION REPORT NO.
9. PERFORMING ORGANIZATION NAME AND ADDRESS
Radian Corporation
P. C. Box 201088
Austin, Texas 78720-1088
10. PROGRAM ELEMENT NO.
11. CONTRACT/GRANT NO.
68-D0-0125, Task 8
12. SPONSORING AGENCY NAME AND ADDRESS
EPA, Office of Research and Development
Air and Energy Engineering Research Laboratory
Research Triangle Park, North Carolina 27711
13. TYPE OF REPORT AND PERIOD COVERED
Task Final; 12/90-7/91
14.SPONSORING AGENCY CODE
EPA/600/13
15.supplementary notes AEERL project officer is N. Dean Smith. Mail Drop 62B, 919/541-
2708.
16 ABSTRACT
The report provides technical assistance to aerosol product marketers and
fillers in other nations now faced with eliminating chlorofluorocarbons (CFCs) un-
der the terms of the Montreal Protocol. It addresses the issues of hydrocarbon
propellant supply, product reformulation, equipment conversion, and safety concerns
for both the manufacturing plaints and the aerosol products themselves. Because
stratospheric ozone provides protection from biologically damaging ultraviolet-B
radiation, and because CFCs have been strongly implicated in the thinning of the
Earth's stratospheric ozone layer, there is an urgent need to eliminate production
and use of the CFCs. In the U. S., CFCs were banned for use as propellants from
nearly all aerosol products as early as 1978. In place of the CFC propellants,
liquified hydrocarbons such as propane, n-butane, and isobutane were found to be
acceptable substitutes for most aerosol products.
17. KEY WORDS AND DOCUMENT ANALYSIS
a DESCRIPTORS
b.IDENTIFIERS/OPEN ENDED TERMS
c. cosati Field/Group
Pollution Propane
Halocarbons Butanes
Ozone Packaging
Stratosphere
Ultraviolet Radiation
Aerosols
Hydrocarbons
Pollution Control
Stationary Sources
Chlorofluorocarbons
13 B
07 C
07B 13 D
04A
20F
07D
IB. DISTRIBUTION STATEMENT
Release to Public
19. SECURITY CLASS (ThisRepon)
Unclassified
21 OF PAGES
218
20. SECURITY CLASS (This page)
Unclassified
22. PRICE
EPA Form 2220-1 (9 73)
|
-------