aJ
L/_
K
Si
/|
|V
Laboratories for the 21st Century
Best Practice Guide
Chilled Beams in Laboratories:
Key Strategies to Ensure Effective Design,
Construction, and Operation
Introduction
Laboratories commonly use far more energy than typi-
cal office buildings, primarily due to the intensive ventila-
tion required to address environmental, health, and safety
concerns. As a result, facility designers and engineers are
constantly seeking new ways to reduce energy consump-
tion while maintaining performance. Active chilled beam
systems are gaining in popularity among laboratory
designers because these systems allow ventilation require-
ments to be decoupled from sensible heating and cooling
loads. This decoupling eliminates the need for reheat
coils for temperature control and reduces the fan energy
required to maintain comfort.
Chilled beam systems are prevalent in European
commercial office buildings but have not yet been widely
applied in the U.S. Such systems offer many compelling
benefits, including high cooling capacities, excellent
performance, and dramatic energy savings for little or no
additional costs over conventional systems
The guide presents best practice strategies for design-
ing, constructing, operating, and maintaining chilled beam
systems in laboratories and is divided into the following
sections:
•	Overview describes how such beams work and
their benefits in a laboratory setting, and presents
three case studies.
•	Designing Chilled Beam Systems discusses sizing
a system, the controls and integration required, and
the challenges of modeling such systems.
•	Construction examines system costs, how to hang
chilled beams, and code compliance.
•	Commissioning, Operations, and Maintenance
summarizes how to commission, operate, and main-
tain chilled beam systems.
•	Appendix A contains a case study of the chilled
beam system installed at the Tahoe Center for
Environmental Sciences laboratory, which is also a
Labs21 partner project.
This guide is one in a series created by the
Laboratories for the 21st Century (Labs21) program,
a joint program of the U.S. Environmental Protection
Agency and U.S. Department of Energy (DOE). Geared
towards architects, engineers, and facilities managers,
these guides provide information about technologies and
practices to use in designing, constructing, and operating
safe, sustainable, high-performance laboratories.
v>EPA
U ited States
En ironmental Protec ion
Agency
U.S. Department of Energy
Energy Efficiency and Renewable Energy
Federal Energy Management Program

-------
LABS FOR THE 21ST CENTURY
Overview
How Chilled Beams Work
Chilled beams (also called induction diffusers) are
fundamentally different from the all-air diffusers used
throughout most U.S. buildings. There are two categories
of commonly used chilled beams: active and passive.
Active chilled beams rely on air handlers supplying
outside air to condition a space and a cold water piping
system that circulates water through integral cooling coils.
The primary airflow from the air handling unit (AHU) to
the zone is introduced through small air jets, which typi-
cally induce three to five times the amount of room air-
flow through the beam's coil (see Figure 1). The induction
process provides local recirculation of room air. Passive
chilled beams rely simply on the natural convection in a
room and have no direct air supply. As heat is transferred
from the room air to the beam's coil, the air is cooled and
falls into the occupied zone. As this occurs, warm room
air up by the ceiling is drawn down through the passive
beam coils (see Figure 2). Passive beams are best suited to
applications with high heat loads and low ventilation air
requirements, and therefore have limited application in
most laboratories. This guide focuses only on active chilled
beams, referred to from this point on simply as chilled
beams.
Chilled beams can accommodate sensible and latent
loads. However, in properly designed laboratory environ-
ments, chilled beams only provide the sensible cooling,
while the central air handling system provides the latent
cooling. This design avoids the additional costs of running
condensate drain piping to each beam in the building.
When designing with chilled beams, there are two critical
considerations: chilled water temperature and humidity
level in the conditioned space. If standard chilled water
(45°F) is used in the chilled beam, there is a risk of condens-
ing water on the coil. To prevent such condensation, the
chilled beam water temperature must be actively main-
tained above the room air dew point. Both of these design
criteria are discussed in further detail under "System
Sizing" (in the "Designing Chilled Beam Systems" section).

////
Ventilation Air
w
r%


\\ (\

y
Mil
—
Coils
t

Ventilation +
Induced Air Induced Air
(1:3 Ratio)
Ceiling

Perforated Metal Casing
Figure 1. Active chilled beam systems use air supplied
from an air handling unit.
Figure 2. Passive chilled beam systems use the natural
convection in a room and have no direct air supply.

-------
LABS FOR THE
21ST CENTURY
Benefits of Chilled Beams in Labs
Chilled beams, while not appropriate for every labo-
ratory, can offer many benefits compared to the variable-
air-volume (VAV) reheat scheme commonly used in most
standard lab systems (see Figure 3). In the VAV scheme,
boxes with reheat coils, control dampers, and airflow
measurement devices are placed in each zone. While this
system meets building requirements, it uses significant
amounts of fan and reheat energy
The following typical laboratory cases demonstrate
how chilled beams can reduce reheat energy, accurately
meet outside air requirements, and reduce building-wide
systems requirements, compared to VAV systems. The
three cases differ in the amount of air required for ventila-
tion, safety, cooling, and fume hoods.
Case 1. Ventilation Driven Airflow
All laboratories require a fixed amount of ventila-
tion air to maintain safety. This case refers to laboratories
where this "general exhaust" requirement (typically six
air changes per hour) drives the airflow, as distinct from a
fume-hood-driven airflow covered in Case 3.
Laboratories are dynamic buildings with a variety
of rooms, each with their own general exhaust require-
ments. In a typical laboratory HVAC (heating, ventilating,
and air conditioning) system with VAV reheat, the room
with the highest heating load dictates the air temperature
supplied by the central AHU. Each lab space then reheats
the air, as needed. Reheating such high volumes of air for
each room presents a huge potential energy loss. A chilled
beam design avoids this energy loss by supplying a higher
temperature to each zone and dynamically cooling each
space individually. With a fixed amount of ventilation air,
chilled beams control the individual laboratory tempera-
ture by adjusting the flow of chilled or hot water across
the beams to match any changing loads. In this case, using
chilled beams eliminates reheat energy and minimizes
outside air conditioning.
Case 2. Cooling-Load Driven Airflow
When cooling loads in a lab drive the design airflow
rates, the use of chilled beams (which decouple the air and
cooling requirements) can dramatically reduce the size of
air systems.
In a typical VAV reheat system, each space meets its
own cooling load by increasing the volume of cold air
supplied. This situation creates a dependent relationship
between the airflow and the cooling capacity. In a chilled
beam system, cooling is accomplished with pumped
chilled water rather than blown cold air. Water has a
volumetric heat capacity 3,500 times that of air, which
translates to a reduction in fan energy by a factor of seven
in typical pump and fan arrangements. On an annual
basis, the coil in the chilled beam accomplishes at least
half of the cooling with the remaining load handled by
the primary air.1 Furthermore, the ramp-up of air typical
in VAV reheat systems no longer occurs in labs with high
heat loads. In many detailed energy analyses of labs, cool-
ing air and then reheating it can easily account for 20% of
annual HVAC energy costs.1
Chilled Beam System
Fach>^
Ventilation Air
Supplied at 55-70°F
Reduced Duct Size
To exhaust
^ressurizatio
control
:ontrol
Decreased
Floor-to-Floor
Height
Fume
hood in
Alcove
VAV-Reheat System
Reheat Energy
To exhaust
6-20 ACH
Flow
control
Flow Reheat
control coil
Ventilation Air
Supplied at 55°F
Ceiling
55-60 F supply air
= 100% of lab
cooling
Fume
hood in
Alcove
Figure 3. Typical chilled beam and VAV reheat systems in labs. VAV reheat systems use significant amounts of
fan and reheat energy compared to chilled beam systems.

-------
LABS FOR THE
21ST CENTURY
When chilled beam systems are used, ducting can be
downsized and the air handler central system reduced to
handle less than half of the air needed by a typical system.1
The savings realized can be used to pay for the added pip-
ing and chilled beam capital costs. If modest reductions in
floor-to-floor height due to smaller ducting are taken into
account, using a chilled beam system can translate into
an overall savings in construction costs and significantly
reduced operation costs as well.
Case 3. Fume Hood Driven Airflow
The benefits of chilled beams are minimal for labs with
a high density of fume hoods or other process exhaust.
In these labs, higher airflow rates are required for safety,
ducts are sized for these higher airflows, and savings from
reducing ducting and the central system are not possible. If
a building has only a few labs with a high density of fume
hoods, chilled beams can still be a solution in those areas
of the building with a low density of hoods (a maximum of
two hoods per laboratory module). Small VAV boxes with
a heating coil can supply additional air in the labs with a
high density of hoods, while the remaining labs use chilled
beams. In cases like this, careful life-cycle cost analysis will
determine the viability of chilled beam systems.
Designing Chilled Beam
Systems
This section discusses three areas of system design:
system sizing, controls and integration, and energy model-
ing. A chilled beam system designed for a laboratory with
this information in mind can reduce building energy use
and costs compared to a standard VAV reheat system.
System Sizing
The process for sizing a chilled beam system can be
divided into four major steps:
1.	Select the type of beam, based on project perfor-
mance and setpoints.
2.	Select a beam's performance and manufacturer to
match the required beam type.
3.	Determine the zone in which these beams will be
placed and how their proximity to other equip-
ment, such as fume hoods and lighting, will affect
the ceiling arrangement and number of beams.
4.	Optimize the central system and the required air-
flow and temperature of the supply air and water.
Step 1. Select a Beam Type
Chilled beams vary in physical size, cooling capacity,
airflow capacity, and many other parameters, depending
on the manufacturer. For a given laboratory, the beam type
selected typically depends on the following design param-
eters: maximum allowable design pressure drop for both
air and water sides, chilled water supply temperature, sup-
ply air temperature, and allowable noise levels.
Air and Water Pressure Drop
Pressure drops across both the water side and air side
of a chilled beam play a large role in specifying a system.
The pressure drops affect the optimal flow through a chilled
beam and the cooling capacity potential. Typical waterside
pressure drops can range from 10 to 15 feet of water column
(ft w.c.) of head through the chilled beam coil.
On the air side, a chilled beam can be selected to have
a pressure drop up to 1.5 inches (in). However, we recom-
mend designing for no more than 0.5 in when selecting a
beam. Compared with a VAV reheat system, chilled beams
can have a small penalty of 0.25 to 0.5 in of static pressure.
But, this is insignificant compared to the total fan energy of
a VAV system, which typically operates in the range of 3 to
8 in of total static pressure. According to Labs21 guidelines,
for a low-pressure drop design, the supply system pressure
drop should be between 2 to 3 in, so the chilled beam pres-
sure drop can become more significant.2
Chilled beam manufacturers will supply design tables
for selecting the best beam based on these two pressure
drop criteria. Establishing acceptable ranges for these pres-
sure drops first can give guidance to the amount of air that
can be supplied and the possible range of cooling capacities.
Chilled Water Supply Temperature
In a standard lab system, using 45°F chilled water runs
the risk of condensing water on the chilled beam coil in the
diffuser. To prevent such condensation, chilled water needs
to be actively controlled to at least 3 or 4°F above the room
air dew point. Because of this, most chilled beams use
chilled water in the range of 55 to 62°F. This elevated tem-
perature can also lead to other benefits, such as the option
to use water-side economizing or free cooling. In the right
moderate climates, electric chillers can even be eliminated
and chilled water can be produced directly from a cool-
ing tower with a storage tank. In hot and humid climates,
reducing the load and running a dedicated electric chiller
that only serves the chilled beams can increase efficiency
by 15 to 20%.

-------
LABS FOR THE
21ST CENTURY
Air Supply Temperature
Most chilled beam systems will supply ventilation
air of 55 to 70°F at a dew point of 50 to 55°F. At 68 to 70°F,
all the cooling is accomplished at the chilled beams and
reheat energy can be eliminated. However, elevated air
temperatures come at a cost. As the approach temperature
between room air and chilled water decreases, the sensible
cooling capacity of the room air also decreases. There is a
tradeoff between the supply air temperature and the num-
ber of chilled beams required to meet the cooling load.
As air temperature is increased, more chilled beams are
required to meet the same load, which can increase costs
and complicate ceiling arrangements.
Noise Requirements
Chilled beams vary in noise level, depending on their
nozzle type and airflow rate. In general, chilled beam
systems operate at or below standard laboratory system
noise levels. For example, with one product, as the pri-
mary air static pressure increased by approximately 0.2 in
w.c., the noise level increased by 7 to 10 decibel (dB). In a
similar way, as airflow rates increased through the beam
by roughly 100 cubic feet per minute (cfm), noise levels
jumped up by as much as 20 dB. The whole point of noise
requirements is that they should be considered when set-
ting limits on pressure drops and airflow rates as a final
check to ensure a reasonable range of sound on a case-by-
case basis, depending on the project.
Step 2. Select Beam Performance
When selecting a chilled beam, it is important to note
that not all beams are created equal. Some beams have a
higher capacity for a given supply air volume. In addi-
tion, some beams include a choice of nozzle types, further
differentiating their performance. Figure 4 displays five
different 6-ft beams, each with the same design conditions
(see Table 1). Beams come in all lengths, from 2 to 10 ft.
Depending on the design requirements, one 6-ft beam can
outperform a competitor's 10-ft beam.
Figure 4 shows the higher output of Manufacturer A's
beams compared to other comparably sized beams. This
company builds more coils per linear foot into their beams
to increase capacity and maintain a nominal beam length,
leading to an increased weight per beam.
Step 3. Determine Zone Layout
The number of chilled beams in a laboratory will
depend on the load density expected, the square footage
of the room, the number and location of fume hoods, and
whether the ceiling is dropped or open. Most labs run in
the range of 5 to 15 watts per square foot (W / sf) and can
accommodate up to 25% of the ceiling space for chilled
beams at higher load densities. Typically, 50% is a high
limit to the amount of ceiling coverage by chilled beams.
As coverage increases, installation and coordination
of chilled beams and lighting can be cumbersome and
Chilled Beam Performance Curves
6-ft Beam Comparison
— Manufacturer A
	Manufacturer B Beam 1
	Manufacturer B Beam 2
	Manufacturer C
	Manufacturer D
35	55 75	95 115 135
Supply Air Volume (CFM)
155
175
195
Figure 4. A comparison of 6-ft beams from different manufacturers shows
that, even with the same design conditions, cooling performance can differ
greatly for a given supply air volume.
Table 1. Various companies were polled
with different design software to gage a
performance curve for their beams. All
initial conditions used are listed here.
Design Data
CHW Flow Rate
1.25 gpm
CHW Temp
57°F
Supply Air Temp
65°F
Room Temp
75°F
Max. Static Air Pressure Drop
0.5 in w.c..
Max. Water Pressure Drop
10.9 ft w.c.
Max Noise Level
34 NC

-------
LABS FOR THE
21ST CENTURY
installed cost can increase as well. In general, a minimum
of 6 ft on center will ensure a good coverage of the ceiling
without causing too many coordination problems. Figure
5 shows an example of a chilled beam floor plan. The room
supplies air through four chilled beams to maintain venti-
lation requirements.
perpendicular to the fume hood sash and 3 to 5 ft away
from the hood (see Figure 6), so that the airflow supplied
by the beam does not interfere with the smooth airflow to
the hoods. If a laboratory requires that a chilled beam be
mounted parallel to a fume hood, one-directional beams
can be used and some beams allow nozzles to be manually
closed upon building startup.
X 1,1! IS 1
Chilled Beam
Supply Air
Figure 5. Example of a laboratory floor plan using chilled
beams, air diffusers, and fume hoods.
Ceiling Type
Dropped ceilings can increase the throw of air off
a chilled beam. Due to the Coanda effect, airflow will
adhere to any flush surface at the outlet of the chilled beam
and fall farther away from the beam (see Figure 7). This
phenomenon can affect how a floor plan is arranged and
where mixing might occur. With an open ceiling, chilled
beams are hung freely and air will drop closer to the
beams. Most beam manufacturers offer more details on
incorporating this effect into the design.
Lighting needs and seismic supports can also physi-
cally limit the amount of chilled beams each zone can sup-
port. Chilled beams can be designed to incorporate lights
or act as reflective surfaces to bounce light when needed.
Proximity to Fume Hoods
In laboratories, a uniform fume hood-sash airflow
profile must be maintained to ensure safety. At the sash
face, crossing airflows must not exceed 50 fpm or the fume
hood containment may be compromised, triggering an
alarm. In many labs, fume hood placement will constrain
chilled beam layouts. Chilled beams are ideally mounted
Q
Critical Distance
"NUttttttT/y ¦ ¦¦
n\
w\
Fume Hood Sash
Face Velocity
100 fpm
Chilled Beams
Cold Air Flow
Pattern
HliilHV.
Beam Spacing
tttft utr
€T~D=p
Supply Air
if
;;nnumv.
Open vs. Drop Ceiling Air Flow Patterns
6 ACH
Jrop Ceiling
Ventilation Air
Supplied
75 °F (Hot Day)
55 °F (Cold Day)
Figure 6. Fume hood proximity to chilled beams and airflow
patterns. Fume hoods require a uniform sash-face velocity
of 100 fpm to maintain safe containment. Crossing airflow
greater than 50 fpm can cause a loss of containment.
Figure 7. Due to the Coanda effect, air adheres to flush
surfaces and will flow further out from a chilled beam with
a dropped ceiling.
Hydronic Design Considerations: Two or Four Pipe
From a hydronic standpoint, there are two different
types of beams—two pipe and four pipe. Both types can
provide heating and cooling. A four-pipe beam has two
separate coils: one for heating and one for cooling. A two-
pipe beam has a single coil for either heating or cooling.
Four-pipe beams weigh more, due to the increased mass
of the additional coil, and can also cost more in building
and support materials. Depending on how a chilled beam

-------
LABS FOR THE
21ST CENTURY
is plumbed, a two- or four-pipe chilled beam can produce
the same effects. For example, consider a case in which
hot and cold water pipes (supply and return for both)
are plumbed to a chilled beam in a room. That beam can
either have two coils—one for heating and one for cool-
ing (four pipe)—or a single coil with switchover control
valves (two pipe) that switch between heating and cool-
ing as needed. Figure 8 shows how a two-pipe beam can
be plumbed to allow both heating and cooling at a zone
	
O
/JIWWWWW
Chilled Beam

Fume Hood
Flow Control.
Valve
2 Position
Control Valve
5
n:
ce
Figure 8. Two-pipe hot-water/chilled-water (HW/CHW)
switchover controls for chilled beams allows for both
heating and cooling at a zone level.
level. The costs differ for these two approaches, depend-
ing on the application and how much piping is required.
Step 4. Optimize the Central System
If designed properly, a chilled beam system presents
additional opportunities for saving energy and first cost
at the central air handling, hot water, and chilled water
systems. By using supply air ducts only for ventilation
requirements, the size of ducts and central AF1U can both
be reduced, saving space and costs. By eliminating reheat,
the overall hot water system can be reduced in size by
reducing or removing zone heating coils and the neces-
sary hot water pipe. And by using a higher chilled water
supply temperature, smaller and more efficient chilled
water systems can be specified.
This section examines three different components of
designing a central system: dehumidification strategies
at the central air handler, air handler and duct sizing, and
chilled water and hot water systems.
Dehumidification Strategies
Chilled beam systems have a large hurdle to over-
come compared with a standard VAV reheat system—
strict dehumidification of the supply air. Since chilled
beams are most cost effectively used to do only sensible
cooling, dehumidification becomes the job of the central
air handler. If the relative humidity of the supply air is not
controlled, water can condense on the chilled beam cool-
ing coils and drip into the space below. As a precaution,
moisture sensors are often placed on the chilled water
supply lines, and if moisture is detected, the water valve
is closed. However, the problem of how to dehumidify the
supply air still exists.
Dehumidification at a central system is typically
accomplished in a few different ways. One approach
involves cooling outside air with chilled water, condens-
ing moisture out of the air at the coil, and finally reheating
the air with a hot water coil from a boiler plant or some
other heating source. This will indeed dehumidify the air,
but at the expense of increased heating energy use.
Another way is to use a run-around coil (see Figure 9).
In this method, a closed-loop pair of heat exchangers runs
water around a cooling coil and reheats the supply air
for free. This approach achieves the same result as using
hot boiler water, but without an energy loss from burning
natural gas or using electricity.
High	Cooled
Efficiency Water
Filter	Coil
Pre Filter
Run-
Around Supply
Coil /Fan(VFD)
Outside Air
ventilation
Supply Air
Figure 9. A run-around coil dehumidifies supply air but
without burning natural gas or using electricity.
Another, often-discussed method involves using a
face-and-bypass dehumidification system. This process is
similar in theory to dehumidifying with a hot water coil,
except that the heating coil only spans a portion of the
supply air stream. In this way, air bypasses around the
coil when dehumidification is not required, saving on the
coil pressure drop. System control for this method can be
complicated for such a small benefit. For additional heat
recovery and humidification strategies, such as enthalpy
wheels, see the Labs21 Best Practices guide "Energy
Recovery for Ventilation Air in Laboratories."3

-------
LABS FOR THE
21ST CENTURY
Air Handler and Duct Sizing
Properly sizing the central air system in a chilled beam
design is a crucial step. As discussed, chilled beams allow
decoupling of the cooling and ventilation components of a
space, requiring less air. These decreased air requirements
lead to smaller supply ducts, central fans, and mechanical
equipment in general. The savings from using a smaller sys-
tem ripple through the project. Smaller ducts cost less and
require fewer structural supports. The central air handler
costs less since supply airflow is decreased. And overall, the
system can save on floor-to-floor height with smaller duct-
ing. These savings are critical to offset the price of chilled
beams. The price per beam (including manufacturing and
shipping) and the price of installation are quite high since
most contractors are still unfamiliar with them. But taking
into account all their benefits, chilled beam designs remain
an economical and energy-efficient choice. More cost infor-
mation is provided under "Construction."
Chilled Water and Hot Water Systems
In a standard VAV reheat laboratory system, air is
cooled (typically to 55°F) to meet the highest load in the
building and then reheated in all other zones (see Figure 10).
This cooling and heating is typically done with 45°F chilled
water and 180°F hot water. Alternatively, chilled beam
systems use a higher chilled water temperature and lower
hot water temperature. Due to the induced cooling effects
of the beams, chilled water temperatures from a central dis-
tribution system can range from 55 to 60°F. This higher tem-
perature is possible because, when a building is in cooling
mode, each room adjusts its own air temperature without
adjusting the airflow, eliminating the need to chill water to
a temperature that can service the entire building with 55°F
air. In a similar way, heating occurs locally, inducing room
air and eliminating the need to heat the cold supply air from
the central system. In moderate climates, mechanical chillers
can be greatly reduced in size and sometimes even eliminat-
ed. In moderate climates with low wet bulb temperatures,
cooling towers can run in series with a thermal storage
tank, replacing the energy intensive chiller with a waterside
economizer. Chilled water can then be produced at night
and stored for use the following day (see Figure 11).
Controls and Integration
Chilled beams are primarily constant air volume devic-
es. Output response to zone loads are accomplished by
modulating water flow rate, not air volume. Higher water
flow rates are required for cooling as opposed to heating
because there is a smaller temperature difference between
the chilled water and room air temperature. The chilled
water will experience a temperature change of only 5 to
6°F (from 57 to 63°F), requiring a larger flow rate to yield
an acceptable output. On the other hand, heated water can
Standard Laboratory VAV Reheat System
Outside Air Conditions:
Hot Day - 68°-90° Air
Moderate Day - 55°-68° Air
Cold Day - 20°-55° Air
Outside Air
Ventilation Air:
All Days - 55°F Air
5
Chiller
i 65-68 F
iiii
100-120°F
Water
Boi er
Typical Load Lab
Hit
Typical Load Lab
High Load Lab
iiii
Figure 10. In a standard laboratory VAV reheat system, air
is cooled to meet the highest load in the building and then
reheated in all other zones.
Laboratory Chilled Beam System
Outside Air Conditions:
Hot Day - 68"-90°F Air
Moderate Day - 55°-68°F Air
Cold Day - 20°-55°F Air
Outside Air
Ventilation Air:
Hot Day >68°FAir
Moderate Day - 55°-68°F Air
Cold Day < 55°F Air
55-60°F
Water
100-120° F
Water,
Boiler
Cooling Tower
Chilled Beam
— Chilled Beam
—Chilled Beam
Back Up
Chiller
Thermal
Storage Tank
Figure 11. A chilled beam central system can produce
and store chilled water for use the following day.

-------
LABS FOR THE
21ST CENTURY
be supplied to a chilled beam at 110°F, above the room
setpoint. The heated water can experience a temperature
change of 30°F or more. Low energy designs use a hot
water supply temperature of 100 to 120°F as a maximum.
This temperature limit allows for the maximum efficien-
cies up to 97% when using condensing boilers. Some
systems will have chilled beams and makeup air diffusers;
care must be taken to size any reheat coils to use this lower
hot water temperature.
Often laboratory buildings need several controls
arrangements depending on the requirements of each
zone. Figure 12, showing one of the control diagrams used
in the authors' laboratory designs, illustrates a possible
mix of components.
H
ZK1
¦ft
~~
|_sMf I
000
Typical chilled beam
controls
General exhaust required for
pressurization and fume hood
turndown
Figure 12. A zone controls diagram for a typical lab
showing a possible mix of components. Often laboratory
buildings need several controls arrangements, depending
on the requirements of each zone.
Energy Modeling Challenges
Modeling chilled beam systems with currently avail-
able software applications can be a challenge, as most do
not have this specific capability. Most modeling programs
are insufficient when it comes to sizing or predicting ener-
gy savings of chilled beam systems and require improve-
ment before they can be relied upon. An exception is
the most recent (April 2009) version of the U.S. DOE's
EnergyPlus simulation tool, which can model chilled
beams. The popular program eQuest, a graphical-user-
interface that runs on DOE-2.2, does not have an exact
chilled beam component; induction units (IU) are the most
similar in concept to chilled beams, but they come with
limited variability. Care must be taken to segregate the
latent load to the AF1U as chilled beams can only deliver
sensible cooling.
Construction
This section explores the costs of installing chilled
beams systems, the methods for hanging the beams, and
code compliance.
Costs
Most mechanical contractors are not yet familiar with
chilled beam technology; the construction industries that
do install them often charge a premium to work on a proj-
ect with chilled beams. This premium should drop as the
technology in laboratories shifts and more people become
involved in designing and constructing these systems.
In an article appearing in Building Design and
Construction, author Dave Barista takes a standard 14,100-
sq-ft lab and does a first cost comparison of a chilled
beam system installation and a standard VAV laboratory.4
Results show that chilled beams cost 84% of a standard
VAV system and chilled beams with built-in lights cost
96%. Each case considers the cost of the beams as well as
the benefits of downsized F1VAC components. In both
cases, the cost of the overall system is less than the stan-
dard, less efficient design.
Hanging Chilled Beams
Most manufacturers recommend mounting chilled
beams in a T-bar ceiling and supporting the weight with
four threaded rods, one at each corner of a beam for sup-
port (see Figures 13 and 14). Some also recommend that
guide wires, typically used for seismic requirements, be
used for support. To line up chilled beams in the ceiling
grid, the beams also need to be adjustable with three
degrees of freedom. In addition, chilled beams need to
move up and down so they can be leveled upon instal-
lation and flush with the ceiling. Because chilled beams
and their supply ductwork are often much shallower than
conventional VAV boxes, they can save on the physical
floor-to-floor height of a building.
A recent installation of chilled beams involved ten
points of support per beam, including six threaded rods
with Unistrut welded axially to the rods and four diagonal
wire attachments for seismic stability. Each beam required
eight hours of labor.

-------
LABS FOR THE
21ST CENTURY
Figure 13. Chilled beams in a T-bar ceiling.
TO BEAM LENGTH. (TYP.)
UP TO 4" IN DIRECTION PARALLEL TO BEAM
LENGTH. (TYP.)
Figure 14, Hanging detail for a chilled beam showing threaded rods.
Manufacturer literature details a less labor-intensive
procedure, one that still involves supporting the weight of
the beam separately from the ceiling. One product installa-
tion manual details the use of threaded rods and Unistrut
channels to support the beam from the slab. Another
manual says the weight of the unit must be supported
separately from the ceiling to avoid stability problems.
Suspension holes are provided for this. The same require-
ment applies to preventing the units themselves from
sagging-
Mechanical and lighting consultants should coordi-
nate closely to develop the best lighting and ventilation
solution for a room. And, to reiterate, placement of chilled
beams close to fume hoods requires careful consideration.
Supply air velocity has to be no more than 30 to 50 fpm at
the fume hood sash.
Code Compliance
CBC Title 24 (based on IBC 2006) Volume 2 1614A.1.12
ASCE 7, Section 13.5.6.2 states that all fixtures shall be
supported directly from the structure with at least two
12-gauge wires located at opposite corners. However,
any fixtures weighing 56 lbs or more shall be supported
directly from the structure above by approved hangers,
and the 12-gauge wires are not required.
When chilled beams are suspended more than 12 in
below the ceiling structure, code requires that four diago-
nal wires, or two opposite diagonal seismic braces, be
used in mounting as an added precaution (see Figure 15).
Figure 15. A seismic wire diagram for mounting chilled
beams showing four diagonal wires as required by code.

-------
LABS FOR THE
21ST CENTURY
Commissioning, Operations,
and Maintenance
Commissioning chilled beams is not much different
than commissioning standard supply diffusers or standard
duct heating and cooling coils. A chilled beam water loop
must be completely purged of any air pockets during
startup and throughout the life of the system. The lower
flow rates through each beam's chilled water coil can make
it tough to purge the air at startup, and care must be taken
to ensure that air is purged at each zone. From experience,
we have found that manual air vents are more reliable
for purging air than automatic air vents. Special attention
must be used when placing manual vents at all high points
in the chilled water piping network.
Chilled beam coils require periodic cleaning; the fre-
quency depends on the filter level used at the AHU and
the amount of dust generated in the lab. Most beams offer
easy coil access from below the ceiling. When designing
a system, it is important to space beams far enough apart
for easy access by maintenance personnel. Maintenance
should include vacuuming the face of the beam coils at
least every three years. Maintenance personnel will need
to be able to access beams from a ladder, often placed in
the aisle between two benches in an occupied and active
lab. This requirement and the unique nature of laboratory
spaces can often drive the placement of beams.
Chilled Beams in Laboratories:
Conclusion
Energy-efficient designs must focus on the entire
system of a building: The impact from one component can
greatly affect the scale of another. For instance, chilled
beams, while individually costing more than a regular
diffuser, impact the central air system of a building and
can generate savings that offset their high costs. This con-
tradicts the "received wisdom" that more energy-efficient
buildings cost more to build.
As with any new technology, chilled beam systems
require care and additional design time to ensure that all
possible problems are avoided. Open discussion among
engineers, contractors, and lab facility owners will help
to speed the successful adoption of this and several
other energy-efficient strategies available to designers to
lower costs and improve the performance of laboratory
facilities.
References
1.	Rumsey, P., Weale, J. "Chilled Beams in Labs:
Eliminating Reheat & Saving Energy on a Budget."
ASHRAE Journal, January 2007, pp 18-23, 25.
2.	Labs21. "A Design Guide for Energy-Efficient Research
Laboratories." Labs For the 21st Century. Labs 21, October
10, 2007. Available online at http:/ / www.labs21century.
gov/toolkit/design_guide.htm.
3.	Labs21. "Energy Recovery for Ventilation Air in
Laboratories." Labs For the 21st Century. Available online at
http:/ / www.labs21century.gov/pdf/bp_recovery_508.
pdf.
4.	Barista, D. "Chill the Ceilings for Cool Energy Savings."
Building Design and Construction, November, 2005.
Available online at http: / / www.labdesignnews.com/
LaboratoryDesign/LD0512FEAT_3.asp.
The active chilled beam details in Figure 14 and 15 are
based on Dadanco product schematics.
For More Information
Barnett, B. "Chilled Beams for Labs: Using Dual Energy
Recovery." ASHRAE Journal, December 2008.
Shultz, C. "Next-Generation Cooling is Looking Up."
Engineered Systems, May 2007. Available online at
http: / / www.esmagazine.com/ Articles/ F eature_Article /
BNP_GUID_9-5-2006_A_10000000000000099257.
Virta, M., Takki, T., Oy, I. WS 07— Air Distribution Systems.
Rehva Workshops at Clima, Rehva Europe, October, 2005.
Available online at http:/ / www.rehva.com/ workshops/
ws_07_lmaija_virta.swf.

-------
LABS FOR THE
21ST CENTURY
Appendix A: Tahoe Center
for Environmental Sciences,
A Case Study
The Tahoe Center for Environmental Sciences (TCES),
which opened in August 2006, is one of the first labora-
tories to incorporate chilled beams in the U.S. Located
in Incline Village, Nevada, the 40,000-sq-ft research
and teaching laboratory is a joint venture between the
University of California, Davis and Sierra Nevada College
for studying the Lake Tahoe environment. The building
has 10,000 sq ft dedicated to research and educational
laboratory space (see Figure A-l).
The laboratory HVAC
system uses chilled
beams in all of the labs
except for two cooling
intensive labs, which use
fan coils for peak cooling.
Ventilation air is supplied
at 68°F when outside air
temperatures are higher.
A free cooling chilled
water system generates
chilled water at 55 to 65°F
to the beams, which then
cool the labs as needed.
On cold days when
outside air temperatures
are below 55°F, outside
air is heated to 55°F and
ventilation air is heated at
each lab. When outside air
temperatures are between
55 and 70°F, outside air is
not treated and chilled beams provide heating and cooling
as needed.
This strategy results in no reheat energy use. The
minimum ACH during occupied hours for ventilation and
safety are six air changes per hour. During unoccupied
hours, the second floor Sierra Nevada College labs are
reset to a minimum of four ACH. The strategy of decou-
pling the ventilation system from sensible heating and
cooling requirements allowed for a 33% reduction in the
ducting and air handler sizing.
The most compelling aspect of this project was its
cost efficiency. Ducting, airshaft, and air handler sizes
were significantly reduced, saving almost $20,000 (see
Table A-l). However, due to the high cost of the induc-
tion diffusers (they had never been used in Nevada, and
contractors and regulatory agencies were unfamiliar with
the product) the construction cost of this system was
comparable to a standard mechanical system. The design
team did have difficulties with the design budget due to
additional time spent analyzing the system as compared
to standard systems. Further time was spent explaining
and justifying the design to the owners and contractors.
Table A-1. Approximate cost comparison of standard system
design and chilled beam design for the Tahoe Center for
Environmental Sciences.

Standard System Design
Chilied Beam
Design


OA Air Handier Sizing
27,000 cfm
18,000 cfm
Ductwork
37,500 lb
30,000 lb
Exhaust Fan Capacity
27,000 cfm
18,000 cfm
Cooling System Capacity
35 tons
20 tons
Floor to Ceiling Height1
9ft
10ft
Mechanical System2 Cost
§741,000
$722,000
1.	Floor-to-floor height kept constant; chilled beam allowed for ceiling to be
raised 1 ft.
2.	Laboratory portion of the building is 10,000 ft2 or 25% of the building. HVAC
costs include laboratory systems only.
Chilled beams made it possible to eliminate reheat
and red lice the HVAC energy for the building by 57%.
Several other strategies were integrated into the build-
ing, including waste heat recovery from the exhaust air,
a cogeneration system where waste heat is reclaimed
for heating outside air, a 100% free cooling chilled water
system that generates chilled water stored in tanks in cool
evening hours, and a 30-kilowatt photovoltaic system that
covers 10% of the electrical demand of the building.
Field Testing
Two labs at the Tahoe Center were tested over a three-
day period in August 2008 to see how the chilled beams
were performing. Fog tests using water vapor demon-
strated the flow path of air induced through the chilled
beam (Figure A-2).
Figure A-1. The Tahoe
Center for Environmental
Sciences is one of the first
U.S laboratories to use
chilled beams.

-------
LABS FOR THE
21ST CENTURY
Figure A-2. hog machine used at the Tahoe Center
showing the airflow pattern of a chilled beam.
The measured data painted a promising picture,
with the chilled beams showing excellent performance.
They supplied 80 to 90% of the cooling to the labs while
responding to fluctuations in loads and outside air tem-
perature. Figure A-3 shows the room air temperature
remained relatively constant, with temperatures fluctuat-
ing only +1.5°F, even as outside air temperature fluctuated
by nearly 20°F.
Lessons Learned
Several great lessons came from the Tahoe Center
building regarding how best to design laboratories with
chilled beams. One of the largest hurdles was simply intro-
ducing a new piece of technology to both the owner and
contractor. Concerns about their actual performance ability,
as well as maintenance and installation, had to be very thor-
oughly explained and the whole design team had to study
the science of how the system would operate to assure any
questions were answered during the design phase.
Coordinating with the different contractors and
placing large beams in the ceiling with lights was another
great lesson learned. On several beams, lights and support
structures had to be modified to fit all the components.
Another important lesson involved maintenance of
the whole building system and component interactions.
For instance, at one point, air filters in the central system
clogged and greatly reduced the cooling capacity the
chilled beams. In another case, a few chilled beams in one
lab had to be re-purged of trapped air, a process easily
accomplished with manual air vents placed on the highest
Room Air Temperature Control
Using Chilled Beams
/
¦ Chilled Beam Cooling
• Outside Air Temperature
— Room Air Temperature
Date and Hour of Trending
Figure A-3. In a test of two lab rooms using chilled beams at the Tahoe Center, room air temperature remained a relative
constant 70°F as outside air temperatures rose and fell.

-------
LABS FOR THE 21ST CENTURY
$125,000
$100,000
Cooling
$75,000
Fans
57%
Savings
$50,000
Heating
~
Cooling
$25,000
Fans
Fleating
$0
Baseline
Designed
points of the piping. Most issues were minimal in their
overall impact and easily avoid ed with thorough commis-
sioning and maintenance.
Conclusions
The energy savings and subsequent annual cost sav-
ings were very impressive (see Figure A-4). Over the last
few years, the energy bills collected show the building's
usage are just below the design conditions and exceed the
labs in cool, dry climates from the Labs21 benchmarking
database (see Figure A-5).
The Tahoe lab is in a climate that does not require as
much cooling as many other climates in the U.S. In more
challenging climates (more hours of heating and cooling)
the reduction in outside air will result in greater heat-
ing and cooling savings. In climates where more cooling
is required, savings from reheat reduction will also be
greater. Where significant dehumidification is required,
savings from reducing reheat can be maintained with a
run-around coil that provides free precooling and free
reheat in the ventilation air handler.
Figure A-4, Baseline and designed estimated annual
energy costs for cooling, heating and fans (based on
DOE2 models, assuming $0.11/kWh and $1,03/therm)
for the Tahoe Center for Environmental Sciences.
Building Annual Energy Costs
(estimate based on 30,802 gsf, $1.25/therm, $0.118/kWh)
$400,000 -
$350,000 -
g $300,000 -
to
U $250,000 -
>
U)
km
c $200,000 -
111
i $150,000 -
c
<
$100,000 -
$50,000 -
$- -I
TCES-actual	TCES-actual TCES-baseline. TCES-proposed. Labs 21 - All Lab Labs 21-Lab in
(based on 07-08	(based on 06-07 DOE2 model DOE2 model Buildings Cool, Dry Climate
bills)	bills)
Figure A-5. Tahoe Center for Environmental Studies annual energy costs based on energy consumption. The chart
shows the actual annualized energy bills and well as the modeled building and Labs21 benchmarking data.

-------
LABS FOR
THE
21ST CENTURY
Acknowledgments
Authors
Peter Rumsey, P.E.
Neil Bulger
Joe Wenisch
Tyler Disney
Rumsey Engineers
Contributors and Reviewers
Mike Walters
Affiliated Engineers, Inc.
Dan Amon, P.E.
U.S. Environmental Protection Agency
William Lintner, P.E.
U.S. Department of Energy
Paul Mathew, Ph.D.
Lawrence Berkeley National Laboratory
Technical Editing and Layout
Julie Chao
Alice Ramirez
Creative Services Office (CSO)
Lawrence Berkeley National Laboratory
Source for Images
Figure 1 (bottom), Figure 2 (bottom) and
Figure 13 (right) were provided
by Affiliated Engineers, Inc.
All other images provided by the authors.
For More Information
On Chilled Beams in Laboratories:
Peter Rumsey, P.E.
Rumsey Engineers
99 Linden Street
Oakland CA 94607
510 663 2070
prumsey@rumseyengineers.com
On Laboratories for the 21st Century
Dan Amon, P.E.
U.S. Environmental Protection Agency
1200 Pennsylvania Ave., N.W.
Washington, DC 20460
202-564-7509
amon.dan@epa.gov
William Lintner, P.E.
U.S. Department of Energy
Federal Energy Management Program
1000 Independence Ave., S.W.
Washington, DC 20585
202-586-3120
william.lintner@ee.doe.gov
Best Practices Guides on the Web
www.labs21century.gov / toolkit / bp_guide.htm
Laboratories for the 21 st Century
i	\ U S. Environmental Protection Agency
U32, | Office of Administration and Resources Management
www.epa.gov/iabs21 century/
In partnership with the
U.S. Department of Energy
Energy Efficiency and Renewable Energy
Federal Energy Management Program
www.eere.energy.gov/femp
Prepared at the
Lawrence Berkeley National Laboratory
June 2009

-------