£
<
33
O
\

O
¦Z.
ui
o
% ^
U.S. ENVIRONMENTAL PROTECTION AGENCY
OFFICE OF INSPECTOR GENERAL
New Procedures Aided
Region 5 in Reducing
Unliquidated Obligations
Report No. 13-P-0145
February 13, 2013
Scan this code to
learn more about
the EPA OIG.

-------
Report Contributors:
Heriberto Ibarra
Janet Kasper
Madeline Mullen
Nicole Pilate
Shannon Schofield
Abbreviations
CFR
Code of Federal Regulations
EPA
U.S. Environmental Protection Agency
FMFIA
Federal Managers' Financial Integrity Act
FY
Fiscal year
IA
Interagency agreement
OARM
Office of Administration and Resources Management
OCFO
Office of the Chief Financial Officer
OIG
Office of Inspector General
OMB
Office of Management and Budget
RMDS
Resources Management Directives System
ULO
Unliquidated obligation
Hotline
To report fraud, waste, or abuse, contact us through one of the following methods:
e-mail:	OIG Hotline@epa.gov	write: EPA Inspector General Hotline
phone:	1-888-546-8740	1200 Pennsylvania Avenue, NW
fax:	202-566-2599	Mailcode 2431T
online:	http://www.epa.gov/oiq/hotline.htm	Washington, DC 20460

-------
S74^v
• U.S. Environmental Protection Agency	13-P-0145

|	\ Office of Inspector General	February 13 2013
s
"V—'—J"
s v\|/v S
At a Glance
Why We Did This Review
The U.S. Environmental
Protection Agency Office of
Inspector General conducted
this audit to determine whether
Region 5 is timely liquidating
grant, interagency agreement,
and contract obligations.
Prior OIG reports have
identified concerns with
obligations not being liquidated
when no longer needed. EPA
developed procedures to
strengthen internal controls
over unliquidated obligations.
In fiscal year 2011, the Office of
the Chief Financial Officer
instituted a database to
improve the consistency in
reviewing and managing ULOs.
Our review focused on whether
the corrective actions taken
were effective.
This report addresses the
following EPA Goal or
Cross-Cutting Strategy:
• Strengthening EPA's
workforce and capabilities
New Procedures Aided Region 5 in Reducing
Unliquidated Obligations
For further information, contact
our Office of Congressional and
Public Affairs at (202) 566-2391.
The full report is at:
www.epa.aov/oia/reports/2013/
20130213-13-P-0145.pdf
What We Found
At the beginning of FY 2011, EPA's system for reviewing ULOs indicated that
Region 5 had over $1.7 billion in grant, contract, and interagency agreement
ULOs. During FY 2011, Region 5 liquidated over$1 billion in ULOs, leaving
about $645 million in ULOs remaining at the end of FY 2011. Our review found
an additional $402,445 that, in our opinion, could have been deobligated during
FY 2011. Region 5 deobligated the funds in FY 2012.
Several factors impacted Region 5's ability to liquidate funds, including obtaining
the documentation necessary to close out funding agreements. For three funding
agreements, valued at $616,976, delays in obtaining closeout documentation
delayed deobligation of funds by as many as 10 years. While two contracts were
deobligated, Region 5 is still working to obtain documentation from the other
recipient. Obligations can also remain unliquidated for many years because of
funding recipient delays in starting or completing projects. Some funding
agreements in our sample had been inactive for more than 4 years. However, in
each case, Region 5 provided evidence that the funds were still needed.
Recommendations and Planned Agency Corrective Actions
We recommend that the EPA Region 5 Administrator take action to deobligate
the funds for the remaining closed grant (Town of Scott). We also recommend
that the Chief Financial Officer and the Assistant Administrator for Administration
and Resources Management address issues related to funding agreements
where the obligation is inactive or open with no activity for more than 180 days.
Region 5 took action to close the Town of Scott grant in November 2012. EPA
agreed with the other recommendations.
Noteworthy Achievements
Region 5 deobligated over $1 billion in grants, contracts, and interagency
agreements in FY 2011. The region took action in FY 2012 to deobligate the
funds from agreements where the grant period had expired, with the exception of
one agreement where EPA is still working with the recipient to obtain
documentation to close the grant. During the course of our audit, Region 5 also
took action to remind staff of the procedures for elevating issues preventing
deobligation of funding agreements to managers' attention.
The Office of the Chief Financial Officer implemented the ULO database in
FY 2011 to improve consistency in reviewing and managing ULOs. The database
provides the capability to proactively monitor ULOs and eliminates the use of
manual spreadsheet reports. During interviews, users of the database stated that
it was an excellent replacement for the previous review process.

-------
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
WASHINGTON, D.C. 20460
THE INSPECTOR GENERAL
February 13, 2013
MEMORANDUM
SUBJECT: New Procedures Aided Region 5 in Reducing Unliquidated Obligations
Report No. 13-P-0145
Regional Administrator, Region 5
Barbara J. Bennett
Chief Financial Officer
Craig Hooks
Assistant Administrator
Office of Administration and Resources Management
This is our report on the subject audit conducted by the Office of Inspector General of the U.S.
Environmental Protection Agency. This report contains findings that describe the problems the
OIG has identified and corrective actions the OIG recommends.
Action Required
In responding to the draft report, the Agency provided a corrective action plan for addressing the
recommendations with milestone dates. Therefore, a response to the final report is not required.
The Agency should track corrective actions not implemented in the Management Audit Tracking
System. We have no objections to the further release of this report to the public. This report will
be available at http://www.epa.gov/oig.
If you or your staff have any questions regarding this report, please contact Melissa Heist,
assistant inspector general for audit, at (202) 566-0899 or heist.melissa@epa.gov; or
Janet Kasper, director, Contracts and Assistance Agreements Audits, at (312) 886-3059 or
kasper.ianet@epa.gov.
FROM: Arthur A. Elkins, Jr.
TO
Susan Hedman

-------
New Procedures Aided Region 5
in Reducing Unliquidated Obligations
13-P-0145
Table of C
Chapters
1	Introduction	 1
Purpose	 1
Background	 1
Noteworthy Achievements	 2
Scope and Methodology	 3
2	Region 5 Reduced Unliquidated Obligations by Over $1 Billion		5
EPA Policies Require ULO Reviews	 5
EPA Could Have Deobligated Additional Funds on Expired Projects		5
Closeout Difficulties Were Not Elevated for Effective Resolution	 7
3	Overall Closeout Goals Met But Documentation Delayed Certain
Deobligations	 8
Federal Regulations Encourage Timely Closeouts	 8
EPA Did Not Always Take Action on Delayed Closeouts		8
Required Closeout Documents Were Not Obtained and Funds
Could Not Be Deobligated 	 10
Recommendation	 10
Agency Comments and OIG Evaluation	 10
4	Recipients Can Take Many Years to Use Funds	 11
Inactive Means No Activity for 6 Months or More	 11
Obligations Can Linger for Years Wth No Drawdowns	 12
ULO Database Reports Could be Improved	 13
Recommendations	 13
Agency Comments and OIG Evaluation	 14
Status of Recommendations and Potential Monetary Benefits		15
Appendices
A Agency Comments to Draft Report	 16
B Distribution	 18

-------
Chapter 1
Introduction
Purpose
An unliquidated obligation is described as an obligation or liability that has not
been expended or liquidated. In fiscal year 2011, the U.S Environmental
Protection Agency Office of the Chief Financial Officer released new policies and
procedures and launched a new database to improve and simplify the ULO review
process. The EPA Office of Inspector General conducted this audit to determine if
Region 5 is timely liquidating grant, interagency agreement, and contract
obligations. Region 5 was selected for review because of its large volume of
unliquidated obligations and the large number of grants with no financial activity
for more than 18 months.
Background
The Federal Managers' Financial Integrity Act of 1982 establishes overall
requirements with regard to internal control and requires the agency head to
annually evaluate and report on the controls and financial systems that protect the
integrity of federal programs. Internal controls provide reasonable assurance of
effective and efficient operations, reliable financial reporting, and compliance
with applicable laws and regulations. The Office of Management and Budget
Circular A-123, Management's Responsibility for Internal Control, implements
FMFIA. This circular requires programs to operate and use resources "consistent
with agency missions, in compliance with laws and regulations, and with minimal
potential for waste, fraud, and mismanagement."
EPA's ULOs and management of grants that are eligible for closeout have caused
the OIG, U.S. Government Accountability Office, and Congress to raise concerns.
Prior OIG audits identified ULOs as an area where EPA can improve its ability to
identify and deobligate unneeded funds and improve its OMB Circular A-123
ULO review process. Additionally, Congress has rescinded millions of dollars of
EPA appropriations. These rescissions have forced EPA to take a closer look at its
ULOs and the close out of its grants, contracts, and IAs.
To implement FMFIA and OMB Circular A-123 requirements and to address
OIGs concerns, EPA developed several policies and procedures:
• EPA's Management Integrity Program - FY 2011 Annual Guidance,
Internal Controls Over Financial Activities, requires all Assistant
Administrators and Regional Administrators to develop plans for staffing
the A-123 ULO reviews and training the reviewers. By October 8, 2011,
13-P-0145
1

-------
Assistant and Regional Administrators were required to submit a separate
year-end ULO certification to verify that unneeded funds were deobligated
by the end of FY 2011. The certification must be supported by a review of
the ULO desktop tool.
•	OCFO Policy Procedure RMDS 2520-03, Standard Operating
Procedures: Deobligating Unliquidated Obligations, provides guidance
for the deobligation of grants, contracts, and IAs. It defines a valid
obligation as one for which appropriated funds are still available and an
actual need still exists within the life of that appropriation. An inactive
obligation is an obligation where there has been no activity for 6 months
(180 days).
•	OCFO Policy RMDS 2520-03-P1, Responsibilities for Reviewing
Unliquidated Obligations, establishes procedures for managing ULOs
under Agency funds-out IAs; assistance agreements including grants,
cooperative agreements, and fellowships; contracts; travel; and
miscellaneous items. This policy requires all responsible parties in EPA
regions to conduct complete periodic but at least annual reviews of all
current and prior year ULOs to ensure that all recorded obligations are still
valid and properly documented.
EPA's management of ULOs was one of the reasons the OIG identified efficient
use of available funds as an Agency weakness. In an April 2012 memorandum to
the Chief Financial Officer, the OIG recommended that the efficient use of funds
continue as an Agency-level internal control weakness until the ULO policies and
procedures EPA developed are effectively implemented and assessed. Sound
funds management is critically important, particularly as budgetary pressures
continue to increase. When funds are not deobligated, those funds cannot be used
on other environmental projects and are more susceptible to fraud, waste, and
mismanagement.
Noteworthy Achievements
Region 5 deobligated over $1 billion in grants, contracts, and IAs in FY 2011.
The region took action in FY 2012 to deobligate the funds from agreements where
the grant period had expired, with the exception of one agreement where EPA is
still working with the recipient to obtain documentation to close the grant. During
the course of our audit, Region 5 also took action to remind staff of the
procedures for elevating issues preventing deobligation of funding agreements to
managers' attention.
The Office of the Chief Financial Officer implemented the ULO desktop tool in
FY 2011 to improve consistency in reviewing and managing ULOs. The ULO
tool provides the capability to proactively monitor ULOs and eliminates the use of
manual spreadsheet reports. It includes visual review indicators, the history of the
13-P-0145
2

-------
review, results of staff review, and the ability to export data. During interviews,
users of the ULO tool stated that it was an excellent replacement for the previous
review process and improved monitoring and tracking capabilities.
Scope and Methodology
We conducted this performance audit from February 2012 to November 2012 in
accordance with generally accepted government auditing standards issued by the
comptroller general of the United States. Those standards require that we plan and
perform the audit to obtain sufficient, appropriate evidence to provide a
reasonable basis for our findings and conclusions based on our audit objective.
We believe that the evidence obtained provides a reasonable basis for our findings
and conclusions based on our audit objective.
To determine if Region 5 is timely liquidating grant, IA, and contract obligations,
we obtained and verified the FY 2011 universe of Region 5 grant, IA, and
contract ULOs using the ULO tool. We judgmentally selected 27 samples from
the universe. A judgmental sample is a nonrandom sample selected based on the
opinion of the auditors. The sampled ULOs included at least one grant, IA, and/or
contract from each reason code with an obligation of more than $0 at the end of
FY 2011. The reason code describes the result of the staffs reviews of the ULO,
including whether the obligation was still valid or should be deobligated.
We interviewed Region 5 project officers, contract officers, and grant specialists
with oversight responsibilities for the 27 samples to discuss how they review
ULOs. We compared their processes to EPA policy. We reviewed files for each
sample to identify why the ULO was not deobligated and to verify that EPA had
adequate support for not deobligating the funds. EPA managers in Region 5, the
Headquarters Interagency Agreement Shared Service Center, and the Region 10
Grants and Interagency Agreements Unit were interviewed to discuss root causes
for audit findings. The Shared Service Centers in Region 10 and headquarters are
responsible for administering IAs nationwide, including Region 5.
We obtained grant, IA, and contract information from several EPA data systems:
•	Integrated Grants Management System
•	Financial Data Warehouse
•	Compass Data Warehouse
•	FY 2011 ULO desktop tool
The information systems were adequate to support our analysis of ULOs and each
of our conclusions was reinforced by corroborating information found in the files.
We evaluated Region 5's internal controls regarding ULOs. We determined that
the internal controls were sufficient to reasonably assure effective and efficient
13-P-0145
3

-------
operations, reliable financial reporting, and compliance with applicable laws and
regulations.
We reviewed guidance documents and previous U.S. Government Accountability
Office and EPA OIG reports relevant to our work. We also reviewed FY 2011
FMFIA and A-123 assurance letters from EPA Region 5, Region 10, OCFO, and
the Office of Administration and Resources Management. The OCFO's assurance
letter noted that there were no deficiencies or exceptions found during its FY
2011 test of internal controls regarding ULOs. However, Region 5, Region 10,
and the Office of Administration and Resources Management all noted
deficiencies or issues related to ULOs. These deficiencies included:
•	Inability to deobligate funds which were under the control of the Office of
Regional Counsel, Region 5
•	Lack of followup on deobligation requests
•	Lack of supporting documentation for justification codes selected in the
ULO tool
•	Inclusion of some closed and deobligated funds in the ULO tool
Prior Audit Coverage
Prior EPA OIG reports identified ULOs as an area where EPA can improve its
ability to identify and deobligate unneeded funds and improve its internal
controls. From FY 2008 through FY 2011, the OIG issued six reports that
addressed ULOs:
•	Report No. 11-1 -0069, EPA Did Not Fully Comply With Guidance
Regarding OMB Circular A-123 Unliquidated Obligation Reviews,
January 19, 2011
•	Report No. 1 l-P-0170, EPA Region 3 Reduced Unliquidated Obligations
Under Water Program Assistance Agreements, March 15, 2011
•	Report No. 1 l-P-0228, EPA Should Reduce Unliquidated Obligations
Under Expense Reimbursement Grants, May 16, 2011
•	Report No. 09-P-0241, EPA Has Improved Efforts to Reduce Unliquidated
Obligations in Superfund Cooperative Agreements, But a Uniform Policy
Is Needed, September 22, 2009
•	Report No. 09-P-0086, EPA Should Strengthen Internal Controls over
Interagency Agreement Unliquidated Obligations, January 26, 2009
•	Report No. 08-P-0265, EPA Should Continue Efforts to Reduce
Unliquidated Obligations in Brownfields Pilot Grants,
September 16, 2008
13-P-0145
4

-------
Chapter 2
Region 5 Reduced Unliquidated
Obligations by Over $1 Billion
At the beginning of FY 2011, the ULO tool indicated that Region 5 had over $1.7
billion in grants, contracts, and interagency agreement ULOs. Of the $1.7 billion,
over $1 billion in ULOs was liquidated during FY 2011, leaving about $645
million in ULOs remaining at the end of FY 2011. A judgmental sample found an
additional $402,445 in expired obligations in FY 2011 that the OIG believes
could have been deobligated. EPA policy requires annual reviews of ULOs and
requires resource officials to certify that appropriate deobligations have been
made on regionally administered contracts, grants, and IAs. Regional
management stated that our sample included unusual circumstances or anomalies.
Region 5 took action during FY 2012 to liquidate all of the sample transactions
identified in this chapter and to remind staff of the process for elevating issues
relating to the deobligation of funds to managers' attention. When funds on
expired projects are not deobligated, those funds cannot be used on other
environmental projects.
EPA Policies Require ULO Reviews
EPA Policy RMDS 2520-03-P1, Responsibilities for Reviewing Unliquidated
Obligations, effective October 1, 2010, states that the regional senior resource
official is responsible for ensuring that staff review all ULOs administered by
their region. The senior resource official must certify that "appropriate
deobligation has been made on Regional travel and small purchases, as well as
regionally-administered contracts, grants, and IAs."
EPA Policy RMDS 2520-03, Deobligating Unliquidated Obligations, discusses
reviews of unliquidated obligations that are required by law. EPA must annually
ensure that all recorded obligations are still valid and properly documented.
EPA Could Have Deobligated Additional Funds on Expired Projects
In FY 2011, Region 5 deobligated approximately $45 million in contract, grant,
and IA obligations. We found an additional $402,445 in expired obligations, less
than 1 percent of total deobligations, which the OIG believes Region 5 could have
deobligated. During its FY 2011 review of obligations, Region 5 did not
deobligate 3 of the 27 grants, IAs, and contracts in our sample even though the
funds were no longer needed (table 1). Region 5 could have deobligated the funds
from the 3 agreements because the projects had expired between 1 to 4 years prior
to the end of FY 2011. EPA did deobligate the funds in FY 2012.
13-P-0145
5

-------
Table 1: Details of sampled
rant, IA, and contract that have expired
Project name
Type
Project
period end
date
Unliquidated
amount as of
9/30/2011
Amount as of
July 2012
Ecorse Ml
Grant No.
96580201
Grant
09/30/2007
$309,192.75
$0
US Army Corps
of Engineers
IA No.
94758001
IA
3/31/2010
59,249.93
0
CH2M Hill
Contract No.
68W60025
Contract
09/30/2007
34,002.40
0
Total


$402,445.08
$0
Source: OIG analysis.
The following provides details on the funding agreements that should have been
deobligated in FY 2011:
•	The City of Ecorse, Michigan, grant expired on September 30, 2007, with
$309,192.75 remaining, and it could have been closed and deobligated.
Based on Office of Regional Counsel advice, Region 5 suspended the
award but did not deobligate the grant because there was a pending
investigation. Under 40 CFR § 30.72(a)(1), the closeout of an award does
not affect the right of EPA to disallow costs and recover funds.
The grant's original project period began October 1, 2005. As early as
June 30, 2006, EPA found that the grantee had accomplished minimal
work and failed to submit progress reports for five consecutive quarters,
beginning with the quarter ending June 30, 2006. EPA took action to
prevent the recipient from drawing down funds. On October 15, 2009
(2 years after the project period ended), the Office of Regional Counsel
informed the grant specialist to wait to close the grant until further notice.
In its FY 2011 Assurance Letter, Attachment 3, Region 5 identified the
Ecorse grant as a remaining corrective action because it was still in dispute
and on hold by legal counsel. Based on 40 CFR § 30.62, which in part
refers to enforcement remedies for noncompliance with grant awards,
Region 5 management believes that its legal counsel's recommendation to
suspend the award pending the results of the investigation warranted
deference. After receiving clearance from legal counsel, EPA deobligated
the remaining funds on July 18, 2012.
•	The U.S Army Corps of Engineers IA expired on March 31, 2010.
However, it took over a year to close and deobligate the funds for this IA.
According to Region 10's Grants and Interagency Agreement unit, all
work performed under this IA or under any associated contracts had been
successfully completed. On March 17, 2011, EPA's Cincinnati Finance
Center indicated that the IA balance could not be reconciled due to a
13-P-0145
6

-------
discrepancy. The finance center stated that closeout of the IA should not
proceed until the balance was reconciled. On November 29, 2011, the IA
was closed and the remaining $52,458.66 was deobligated.
• The project period for the CH2M Hill contract ended September 30, 2007,
with $34,002 remaining. We did not observe any requests for closeout
documents or attempts to deobligate the funds until almost 4 years after
the project period ended. On September 26, 2011, an amendment was
submitted to the finance center to deobligate the remaining funds. The
finance center partially deobligated the funds. The previous contracting
officer stated that he forgot to follow up to ensure that all of the remaining
funds were deobligated. On February 27, 2012, the current contracting
officer requested the contractor's release form and final invoices. EPA
received the contractor's release form dated March 2, 2012, and final
closeout voucher dated March 29, 2012. The remaining funds were
deobligated on May 17, 2012. EPA should have requested the contractor's
release sooner and followed up when only a portion of the funds was
deobligated.
Closeout Difficulties Were Not Elevated for Effective Resolution
Region 5 staff did not always take appropriate action to ensure that expired
projects were deobligated. We were told that our sample included unusual
circumstances or anomalies. During the course of our audit, Region 5 issued an
e-mail to its staff members which reminded them of the grant and contract
closeout procedures and instructed them to elevate closeout issues to the
appropriate manager for assistance. Because the Agency has deobligated the
funds for the grant, IA, and contract mentioned in this chapter and has instructed
Region 5 staff to elevate closeout documentation issues to its managers,
Region 5's actions have addressed the issues in this chapter. Therefore, we have
no further recommendations.
13-P-0145
7

-------
Chapter 3
Overall Closeout Goals Met But Documentation
Delayed Certain Deobligations
Overall, Region 5 is meeting Agency grant closeout goals. Of the judgmental
sample of 27 obligations reviewed during the audit, Region 5 did not take action
to close out 1 grant and 2 contracts because documentation needed to close out the
obligations had not been received. A recipient did not timely respond to
documentation requests and staff did not elevate the issues to management. Grants
should be closed when all administrative action and work is done. Contract
closeout occurs when there is evidence of final payment and physical completion.
When funds on expired projects are not deobligated, those funds cannot be
redirected to other environmental projects.
Federal Regulations Encourage Timely Closeouts
As discussed in 40 CFR § 31.50, a federal agency is to close out a grant award
"when it determines that all applicable administrative actions and all required
work of the grant has been completed." It also states that within 90 days after the
expiration or termination of the grant, the grantee must submit all required
financial, performance, and other reports.
Likewise, Federal Acquisition Regulation Subpart 4.804 states that contract
closeout occurs upon receipt of evidence of final payment and evidence of
physical completion. The contract task orders mentioned in this chapter are
indefinite delivery, indefinite quantity contracts and cost-plus-fixed-fee
contracts.1 To allow for completion of indirect cost rate audits, the regulation
states that contracts should be closed within 36 months of the month in which the
contracting officer receives evidence of physical completion.
EPA Did Not Always Take Action on Delayed Closeouts
In FY 2011, Region 5 deobligated 90 percent of the grants that closed that year.
Region 5 did not take action during FY 2011 to close out 1 grant and 2 contracts
of the 27 obligations reviewed during the audit. Region 5 was still awaiting
closeout documentation and allowed these projects to remain open for up to 10
years after project periods ended. Region 5 has since deobligated both of the
1 An indefinite delivery, indefinite quantity contract "provides for an indefinite quantity, within stated limits, of
supplies or services during a fixed period." In addition,"[t]he contract must require the Government to order and the
contractor to furnish at least a stated minimum quantity of supplies or services." FAR 16.504(a)(1). "A cost-plus-
fixed-fee contract is a cost reimbursement contract that provides for payment to the contractor of a negotiated fee
that is fixed at the inception of the contract.. .but may be adjusted as a result of changes in the work to be performed
under the contract." FAR 16.306(a).
13-P-0145
8

-------
contracts, but the grant remains open. Table 2 presents details of the sampled
grant and contracts that were originally not closed out.
Table 2: Details of sampled grant and contracts that needed closeout
Project name
Type
Project period
end date
Unliquidated
amount as of
09/30/2011
Amount as of
July 2012
Town of Scott,
Grant No.
XP00E27701
Grant
10/31/2010
$35,600.00
$35,600.00
Weston TO #3
Contract No.
GS10F0117
Contract
09/30/2006
108,097.72
0
Ecology and
Environment
Contract No.
68W60011
Contract
12/17/2000
473,278.06
0
Total


$616,975.78
$35,600.00
Source: OIG analysis.
The following provides details on the grant and contracts that were not closed out
because required documents were not available:
•	The Town of Scott grant project period ended on October 31, 2010, at
which time Region 5 should have initiated closeout procedures. During
FY 2011 and 2012, Region 5 communicated several times with the grantee
to request documents to officially close the grant. The project officer
stated that the grantee stopped communicating with them and no longer
answered phone calls which made it difficult to close out and deobligate
any remaining funds. EPA extended the grant until July 31, 2012, and the
grantee has until November 1, 2012, to submit invoices to support eligible
costs.
•	The Weston contract should have been closed out and funds deobligated
since the project period ended September 30, 2006, over 6 years ago. A
review of the contracting officer files showed no project activity or
requests for closeout documents for more than 4 years. The project officer
had retired and the Agency could not locate the project officer's file. The
Agency stated that the release of claims (required for closeout) was
received and the task order was deobligated on October 4, 2011. EPA
should have started the closeout process and obtained the release of claims
when the project period ended.
•	The Ecology and Environment contract project period ended
December 17, 2000, with $473,278.06 remaining, and closeout procedures
should have been initiated at that time. The contracting officer indicated
that these were oil cleanup funds. According to Region 5, the contracting
manager made the decision not to deobligate the funds because she felt
13-P-0145
9

-------
that it was better to hold onto the Oil Spill Reimbursable Authority funds
to pay the final invoice. In March and April 2012, EPA made final
payment to the contractor which resulted in a $0 available balance and
closed the contract.
Required Closeout Documents Were Not Obtained and Funds Could
Not Be Deobligated
For the samples under review, projects were not closed out timely because
required closeout documentation was not obtained. Region 5 has a procedure for
elevating concerns about obtaining closeout documentation for grants. Region 5's
process calls for sending a letter requesting closeout documentation when the
grant expires and additional letters when requested documentation is not received.
This process was not followed for the Town of Scott project. On September 11,
2012, Region 5 sent an e-mail to its grants specialists reminding them of the
region's closeout procedures and that they should timely elevate issues when
there are delays in obtaining necessary closeout documents.
In the case of the Weston contract, there was no evidence that documentation
needed to close out the contract was requested for 4 years. Promptly elevating
closeout delays to management may have resolved the delays more efficiently. On
September 21, 2012, Region 5 management sent an e-mail to contracting staff
reminding them of the procedures for closing contracts and stating that if there are
concerns, they should be elevated. Region 5's corrective action addresses the
issues relating to the closeout of contracts.
Recommendation
We recommend that the Regional Administrator, Region 5:
1. Close out the Town of Scott grant and deobligate any funds remaining
after the required documents are obtained.
Agency Comments and OIG Evaluation
Region 5 took action to address the recommendation. EPA disbursed the remaining
funds to the recipient on November 5, 2012, and closed the grant. EPA's actions
addressed the recommendation.
13-P-0145
10

-------
Chapter 4
Recipients Can Take Many Years to Use Funds
Grant and IA recipient delays in starting projects and requesting reimbursement
create the appearance that funds are not needed. EPA policy defines inactive
obligations as those in which there has been no activity for six months (180 days)
or more. In our sample, three of 27 obligations were inactive even though the
performance period for the grant or IA had not expired. Some of the obligations
have been inactive for more than 4 years. When funds are not used, the Agency's
anticipated environmental outcomes are delayed or may become unattainable.
Inactive Means No Activity for 6 Months or More
EPA Policy Number 2520-03 defines inactive obligations as those in which there
has been no activity for 6 months (180 days) or more.
For grants, EPA Order 5700.6 A2 CHG 2, Policy on Compliance, Review and
Monitoring, states that during programmatic baseline monitoring, areas to be
reviewed may include "whether expended and remaining funds are reasonable."
EPA has taken some action to address the issue of the lack of drawdowns in
recent years:
•	EPA developed a timely payment term and condition to address grant
recipients that have a history of accumulating ULOs without adequate
justification. This term and condition may help reduce grant ULOs in the
future.
•	EPA's Office of Wastewater Management issued the Management Plan
for the Timely Award and Completion of Special Appropriations Act
Project Grants, effective October 1, 2011, to facilitate the timely award
and completion of congressional earmark grants. According to the
guidance, recipients with no financial activity for 5 months must submit a
written explanation of the reason for the inactivity.
•	The purpose of the EPA's Grants Policy Issuance 12-06, Timely
Obligation, Award and Expenditure of EPA Grant Funds, effective
October 1, 2012, is to ensure the timely obligation, award, and expenditure
of EPA grant funds. The policy states that regional program offices may
not approve grants where it is anticipated that drawdown of a substantial
portion of federal funds will be delayed until the end of the project period,
without the approval of the responsible National Program Manager.
13-P-0145
11

-------
EPA's recent actions may help to prevent lack of drawdowns in the future,
but extra attention by EPA staff will still be required.
Obligations Can Linger for Years With No Drawdowns
A few Region 5 grants were open for years with no drawdowns. In 3 of 27
obligations reviewed, we found that recipients of two grants and an IA had not
drawn down funds for about 4 years (table 3). EPA told us that funds were still
needed for each of these cases.
Table 3: Details of sampled grants and IA not drawing down funds
Project
name
Type
Award Date
Unliquidated
amount
as of 9/30/2011
Amount as of
August 2012
Rockford
Grant
03/18/2008
$1,700,000
$1,501,829
Grant No.




BF00E45801




Ohio EPA
Grant
12/21/2008
2,106,925
2,106,925
Grant No.




XP00E59101




Indian Health
IA
9/27/2007
81,400
12,173
Service




IA No.




94817901




Total


$3,888,325
$3,620,927
Source: OIG analysis.
The following describes grants and an IA with long periods of inactivity from
Table 3 above:
•	Since the Rockford Brownfield grant was awarded 4 years ago, there was
one drawdown in July 2012. After the initial project period expired
January 31, 2011, with no activity, Region 5 increased the initial award
amount by $500,000. According to Region 5 staff, under this type of grant
funds are not disbursed until after the loan review process is completed
and eligible costs are incurred. The project officer explained that delays
occurred after Chicago lost its 2016 Olympics bid and slated projects fell
through. The project officer also stated that EPA and the state have
reviewed the cleanup plans and ground breaking is expected to start in
May 2012. Despite assurances that this project is now on track toward
completion, when funds remain idle it appears that they are not needed.
•	The Ohio Environmental Protection Agency has not drawn down any
funds since the original award on December 21, 2008. During a 2010 on-
site review, Region 5 found that while the Ohio Environmental Protection
Agency had conducted work, there were no requests for payment.
Region 5 recommended that the Ohio Environmental Protection Agency
submit requests for payments semiannually. EPA files did not include a
response from the Ohio Environmental Protection Agency to the report
13-P-0145
12

-------
issued in March 2011. Region 5 staff explained that special appropriations
grants present challenges.
• Region 5 did not take effective action when the Indian Health Service did
not draw down funds for more than 4 years after the project period began
October 1, 2007. The Indian Health Service did not draw down funds from
October 10, 2007, to January 26, 2012. The project period for this IA
expired at the end of 2010. It was amended June 1, 2011, to provide more
time and the project period was extended until December 31, 2011.
ULO Database Reports Could Be Improved
Region 5 was required to review over 3,000 lines of ULOs in the FY 2011 ULO
tool. The ULO tool does not highlight grants, IAs, and contracts which are
inactive and have had no activity for 180 days. EPA began to use the ULO tool
during FY 2011, and it was the first time such an extensive review of obligations
was required. Previously, ULO reviews only included obligations inactive for 180
days or more. Management explained that it did not seem efficient to review
every obligation and that it was easier to make mistakes than it was in the past.
We believe that obligations which have had no activity for long periods of time
need to be distinguished from other obligations so that there is more attention on
the older ULOs. If the ULO tool reports would highlight the older obligations, it
would focus management's attention on these obligations. Even though Agency
policy states that an obligation is considered inactive after 180 days, Region 5
expressed concern that given the nature of the two loan programs (Brownfields
and State Revolving Loan programs), a longer "no activity trigger" may be
appropriate. At 180 days, it is likely that all the grants would trigger greater
attention, thus diverting management attention from other instances where actual
problems may exist.
Recommendations
We recommend that the Chief Financial Officer:
2.	Revise the ULO desktop tool to separately identify obligations that have
been inactive for 180 days or more.
We recommend that the Assistant Administrator for Administration and
Resources Management:
3.	Assess the effectiveness of the Office of Water practice of requiring
written explanations from recipients when funds are not drawn for
5 months and whether it should be applied to other types of financial
agreements.
13-P-0145
13

-------
Agency Comments and OIG Evaluation
EPA agreed with both recommendations. By January 31, 2013, OCFO will restore
the functionality of the ULO desktop tool that highlights obligations that have
been inactive for 180 days. The Office of Grants and Debarment will review the
effectiveness of the Office of Water's practice of requiring written explanations
from recipients to determine whether the practice should be expanded to other
assistance agreements and interagency agreements. Based on the results of the
review, a recommendation will be made to the Grants Management Council.
Based on the council's response to the recommendation, the Office of Grants and
Debarment will make the necessary changes to its policies effective
October 1, 2013. The Agency actions, when implemented, should address the
recommendations.
13-P-0145
14

-------
Status of Recommendations and
Potential Monetary Benefits
POTENTIAL MONETARY
RECOMMENDATIONS	BENEFITS (In $000s)
Rec.
No.
Page
No.
Subject
Status1
Action Official
Planned
Completion
Date
Claimed Agreed-To
Amount Amount
1
10
Close out the Town of Scott grant and
deobligate any funds remaining after the
required documents are obtained.
C
Regional Administrator,
Region 5
11/05/2012

2
13
Revise the ULO desktop tool to separately
identify obligations that have been inactive for
180 days or more.
0
Chief Financial Officer
01/31/2013

3
13
Assess the effectiveness of Office of Water
practice of requiring written explanations from
recipients when funds are not drawn for 5
months and whether it should be applied to
other types of financial agreements.
0
Office of Administration
and Resources
Management
10/01/2013

1 0 = recommendation is open with agreed-to corrective actions pending
C = recommendation is closed with all agreed-to actions completed
U= recommendation is unresolved with resolution efforts in progress
13-P-0145
15

-------
Appendix A
Agency Comments to Draft Report
January 09, 2013
MEMORANDUM
SUBJECT: Response to Office of Inspector General Draft Report No. OA-FY12-0306
New Procedures Aided Region 5 in Reducing Unliquidated Obligations
FROM: Susan Hedman
Regional Administrator
TO:	Melissa M. Heist
Assistant Inspector General for Audit
Thank you for the opportunity to respond to the recommendations in the audit report titled, "New
Procedures Aided Region 5 in Reducing Unliquidated Obligations " As requested in the
December 12, 2012 transmission from OIG, Region 5 worked with Office of the Chief Financial
Officer and the Office of Administration and Resources Management on this response. This
memorandum summarizes the Agency's position on each of the three report recommendations.
AGENCY'S OVERALL POSITION
As you will see below in the chart, the Agency agrees with the three recommendations. Region
5 has completed the corrective action suggested in recommendation 1. Corrective actions for
recommendations 2 and 3 are in progress.
AGENCY'S RESPONSE TO SPECIFIC REPORT RECOMMENDATIONS
Number
Recommendation
Intended Corrective
Action(s)
Estimated Completion
& Contacts
1
Close out the Town of Scott
grant and deobligate any funds
remaining after the required
documents are obtained.
The Las Vegas Finance Center
made final payment of the
remaining funds on November
5, 2012 and has financially
closed this grant.
Completed
Contact: Sharon Green,
Region 5 GMO (312)
353-5661
2
Revise the ULO desktop tool to
separately identify obligations
that have been inactive for 180
days or more.
OCFO disabled this function in
the FY 2012 ULO Desktop
Tool due to issues with the
data migration of the "last
action date." OCFO will
restore the functionality of the
ULO Desktop Tool that
The planned completion
date for this corrective
action is January 31,
2013.
Contact: Adam Fett,
Program Analyst, OFM
13-P-0145
16

-------


highlights obligations that have
been inactive for 180 days.
(202) 564-5314
3
Assess the effectiveness of the
Office of Water's practice of
requiring written explanations
from recipients when funds are
not drawn for 5 months and
whether it should be applied to
other types of financial
agreements.
OGD will review this practice
and evaluate whether the
Agency should expand the
practice to other assistance
agreements and to interagency
agreements.
OGD will obtain
feedback from the EPA
grants/IA management
community and make a
recommendation to the
Grants Management
Council (GMC) at the
2013 summer meeting.
If the GMC determines
that this practice should
be expanded to other
programs, OGD will
make necessary changes
to existing ULO review
policies and develop
implementing terms and
conditions that will go
onto effect October 1,
2013.
Contacts: Jennifer
Hublar, OARM OGD
(202) 564-5294
We appreciate the efforts of the audit team and the team's responsiveness to our comments on
initial discussion drafts of this report. If you have any questions regarding this response, please
contact Dale Meyer, Region 5 Comptroller at (312) 886-7561 or Eric Levy, Region 5 Audit
Coordinator at (312) 353-3611.
cc: Janet Kasper
Bharat Mathur
Cheryl Newton
Cyndy Colantoni
Nanci Gelb
Sandy Womack
Howard Corcoran
Jennifer Hublar
Maryann Froehlich
Cheryl Varkalis
Barbara Freggens
Sandy Dickens
Stefan Silzer
Jeanne Conklin
Adam Fett
Dale Meyer
Betty White
Patricia Bamford
Sharon Green
Eric Levy
13-P-0145
17

-------
Appendix B
Distribution
Office of the Administrator
Regional Administrator, Region 5
Assistant Administrator for Administration and Resources Management
Agency Follow-Up Official (the CFO)
Agency Follow-Up Coordinator
General Counsel
Associate Administrator for Congressional and Intergovernmental Relations
Associate Administrator for External Affairs and Environmental Education
Director, Office of Grants and Debarment, Office of Administration and Resources Management
Director, Grants and Interagency Agreements Management Division,
Office of Administration and Resources Management
Director, Office of Regional Operations
Deputy Regional Administrator, Region 5
Assistant Regional Administrator, Region 5
Audit Follow-Up Coordinator, Office of the Chief Financial Officer
Audit Follow-Up Coordinator, Office of Administration and Resources Management
Audit Follow-Up Coordinator, Office of Grants and Debarment
Audit Follow-Up Coordinator, Region 5
13-P-0145
18

-------