V.
0 w
% *
% PR0^°* OFFICE OF INSPECTOR GENERAL
Catalyst for Improving the Environment
Evaluation Report
Significant Modifications Needed
To Ensure Success of Fort Worth
Asbestos Demolition Method
Report No. 2004-P-00002
December 19, 2003
4/24/2001
Fort Worth Method
Phase I Demolition

-------
Report Contributors:
Rick Beusse
Stephen R. Schanamann, CIH
Dan Howard
Thane Thompson
Sarah Fabirkiewicz
Darryl Weatherhead
Eric Hanger
Abbreviations:
AHERA	Asbestos Hazard Emergency Response Act
CFR	Code of Federal Regulations
EPA	Environmental Protection Agency
FPA	Final Project Agreement
NESHAP	National Emission Standard for Hazardous Air Pollutants
OAQPS	Office of Air Quality Planning and Standards
OAR	Office of Air and Radiation
OECA	Office of Enforcement and Compliance Assurance
OIG	Office of Inspector General
OPEI	Office of Policy, Economics, and Innovation
ORD	Office of Research and Development
RACM	Regulated Asbestos-Containing Material
QAPP	Quality Assurance Project Plan
s/mm2	Structures Per Millimeter Squared
Cover Photo: Image showing Fort Worth Method - Phase I demolition. Source: Image
obtained from EPA Region 6.

-------
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
WASHINGTON, D.C. 20460
OFFICE OF
INSPECTOR GENERAL
December 19, 2003
MEMORANDUM
SUBJECT:	Final Evaluation Report: Significant Modifications Needed To Ensure
Success of Fort Worth Asbestos Demolition Method
Report No. 2004-P-00002
FROM:	Kwai-Cheung Chan /s/
Assistant Inspector General for Program Evaluation
TO:	Jeffrey R. Holmstead
Assistant Administrator for Air and Radiation
John P. Suarez
Assistant Administrator for Enforcement and Compliance Assurance
J. Paul Gilman, Ph.D.
Assistant Administrator for Research and Development
Richard Greene
EPA Region 6 - Regional Administrator
Jessica L. Furey
Associate Administrator for Policy, Economics, and Innovation
Attached is our final report regarding the design, methodology, and oversight of the Fort Worth,
Texas, Project XL proposal for an alternate method of demolishing structures containing
asbestos. The subject evaluation was conducted by the Environmental Protection Agency's
(EPA) Office of Inspector General (OIG). This report contains findings related to modifications
needed to ensure success of the Fort Worth asbestos demolition method and corrective actions
the OIG recommends. This report represents the opinion of the OIG and the findings contained
in this report do not necessarily represent the final EPA position. Final determinations on
matters in the report will be made by EPA managers in accordance with established procedures.

-------
Action Required
In accordance with EPA Directive 2750, you are required to provide this office with a written
response within 90 days of the final report date. The response should address all
recommendations. For the corrective actions planned but not completed by the response date,
please describe the actions that are ongoing and provide a timetable for completion. Where you
disagree with a recommendation, please provide alternative actions for addressing the findings
reported.
We appreciate the efforts of EPA officials and staff, as well as those of the City of Fort Worth, in
working with us to develop this report. If you or your staff have any questions regarding this
report, please contact me at (202) 566-0832, or Rick Beusse at (919) 541-5747.

-------
Executive Summary	
According to the Environmental Protection Agency's (EPA) National Asbestos
Registry System, over 166,000 asbestos demolition and/or renovation projects
were conducted in the last two years. Since asbestos is a known human
carcinogen, EPA has established stringent work practices to control emissions of
asbestos resulting from demolition projects. Buildings and other structures that
contain sufficient quantities of asbestos, known as regulated asbestos-containing
materials, or RACM, are governed by strict rules specified in EPA's National
Emission Standard for Hazardous Air Pollutants (NESHAP). This rule generally
calls for removing RACM prior to demolition, which can be costly. EPA's Project
XL is a national initiative that encourages testing of alternative ways to achieve
environmental results, as long as those results are superior to those achieved under
current regulations. Projects proposed under Project XL are intended to test new
approaches that could be applied more broadly. Using Project XL, the City of
Fort Worth, Texas, has proposed an alternative method for demolishing selected
structures that possess RACM.
In general, the "Fort Worth Method," as it is known, calls for thoroughly wetting
the structure with a fire hose while it is demolished using a bulldozer or track hoe,
but it does not call for removing all the RACM prior to demolition. The City has
proposed a three-phased approach to obtaining EPA's approval of the Fort Worth
Method. Phase I testing of the proposed Method occurred in 2001 on a small,
single family dwelling of less than three stories that was exempt from the
NESHAP due to the type of structure. Phase II testing is planned for an
abandoned hotel that contains enough RACM to be regulated by the asbestos
NESHAP. If the Phase II demonstration is deemed successful, Fort Worth plans
to conduct Phase III, consisting of multiple demolitions using the Fort Worth
Method. If approved, the Method would then be available for other cities to use
in demolishing similar structures. Other cities have already shown interest in the
Fort Worth Method. In 2000, a Miami University of Ohio/University of South
Carolina survey found that within 35 US cities there was a collective total of more
than 91,000 abandoned buildings in need of demolition. According to one EPA
asbestos expert's estimate, as many as 80 percent of these structures would contain
RACM.
The Office of Inspector General (OIG) initiated this evaluation because of the
national policy implications of this precedent-setting demonstration project, and
because the project involves a new approach to demolishing buildings containing
regulated quantities of asbestos. During our evaluation, we sought to answer three
specific questions that address how the design and methodology of the Fort Worth
Method could be improved and how EPA could improve its oversight of this
l

-------
project and other Innovation proposals. Those questions, as well as summaries of
what we found and recommendations for each, follow.
1.	Is the design and methodology of the Fort Worth Method - Phase II adequate to
demonstrate protection of human health and the environment?
The current design and methodology of the Fort Worth Method is not adequate to
demonstrate protection of human health and the environment. Significant
modifications to the design and methodology will be necessary for EPA to ensure
that the data generated and used to evaluate this project will be valid. For
example, the description of the Fort Worth Method does not identify the key
factors or variables that could be encountered during a demolition, nor does it
specify how these or many other hazardous materials would be handled or treated
to minimize potential exposures. There are also concerns about the adequacy of
the ambient air monitoring that would take place during Phase II, and the Phase II
proposal has not been independently peer reviewed to ensure that it is based on
sound science. This proposal also has significant national policy implications,
because, if determined equivalent to the NESHAP, this demonstration project may
set a precedent that other communities could use in demolishing aging structures
with asbestos.
We recommend that EPA assist Fort Worth in modifying the Fort Worth Method
to produce a single, finalized technical specification document that fully describes
the Fort Worth Method, including the demolition strategy and associated Quality
Assurance Project Plan (QAPP), and that this proposal be externally peer-
reviewed prior to testing.
2.	Does the Fort Worth Method - Phase II meet EPA's key Project XL criteria, including
superior environmental performance, regulatory flexibility, adequate stakeholder
involvement, and transferability to other asbestos demolition projects?
Although initially proposed in September 1999, the Fort Worth Method does not
yet meet EPA's Project XL criteria of superior environmental performance,
appropriate regulatory flexibility, adequate stakeholder involvement, or
transferability. Of 15 external stakeholder groups we interviewed regarding these
four criteria, 13 did not believe that the Fort Worth Method, as currently written,
is either equivalent or superior to EPA's NESHAP. EPA has yet to determine
whether the method is either equivalent or superior to the Asbestos NESHAP.
Also, the regulatory flexibility requirements necessary to approve this proposal
have not been met, and the proposed Fort Worth Method does not utilize a work
practice standard, but rather depends on the analysis of air monitoring samples,
which take several days to analyze. As a result, the Agency and the City of Fort
Worth could be exposed to liability issues from the public if it is later found that
asbestos was released into the environment during the Phase II test.
11

-------
We recommend that EPA work with the City of Fort Worth to develop a Final
Project Agreement that adequately addresses key Project XL Criteria for the entire
proposed project (Phase II and Phase III), and that EPA ensure that Project XL
team concerns are adequately addressed.
3. Has EPA's oversight to date ensured that the Fort Worth - Phase II project will allow
EPA to reach valid conclusions on the effectiveness of such demolition techniques
for each type of asbestos?
EPA's oversight to date has not ensured that the Fort Worth Method-Phase II
proposal will allow the Agency to reach valid conclusions on the effectiveness of
this alternative demolition technique for each type of asbestos. This has occurred
because: (1) after more than 4 years, the Fort Worth Method is not defined in
sufficient detail to allow independent assessment; (2) a Final Project Agreement,
usually established early in an XL project, has yet to be developed; (3)
disagreements among XL team members have not been resolved; and (4) the
proposal has not been peer reviewed. Also, concerns that the Phase I demolition
was not representative have not been satisfactorily addressed. Without significant
modifications, the proposed Phase II demolition may also not be representative of
the effectiveness of such demolition techniques for each type of asbestos. Given
the number of variables involved, it is questionable whether a single test - as
described in the latest proposal - is adequate to statistically determine the success
or failure of a new demolition method in accordance with sound scientific
principles.
EPA is also promoting similar "innovations projects" under the Agency's
Innovations Strategy that raise questions regarding how fundamental project
criteria, such as environmental performance, will be assessed. Because Federal
Register guidance has not been issued for the Innovations Strategy, it is unclear
how these proposals will be handled, how differences in views of project
adequacy will be addressed, how timeframes will be enforced, and whether
external peer review will be required prior to project implementation.
We recommend that EPA develops comprehensive Agency guidance for
conducting oversight of these proposed projects. We recommend that EPA assist
the City of Fort Worth in designing a demonstration project that can be used to
reach complete, reliable, and valid conclusions, and that EPA works with the City
to ensure that the structures chosen for the Phase II demolition contain sufficient
asbestos to provide representative test results. We also recommend that EPA
develop and propose Federal rules and regulations for handling Innovation
Strategy proposals, including the opportunity for public notice and comment.
in

-------
Recent Developments
The EPA Innovations Action Committee, formerly the Reinvention Action
Committee, met on May 12, 2003 and recommended moving forward to Phase II,
provided that certain conditions were addressed, including that the Fort Worth
Method and the Quality Assurance Project Plan for Phase II be peer reviewed.
Further, City of Fort Worth officials met with Agency and OIG officials on
September 29, 2003 and provided additional documentation, including a revised
method dated September 23, 2003. In a September 23, 2003 letter from the EPA
Region 6 Regional Administrator to OPEI, OAR, OECA and ORD, the Regional
Administrator stated that the City of Fort Worth is fully supportive of the need to
meet the requirements under Project XL, including:
•	preparation of a Final Project Agreement;
•	development of a stakeholder plan that includes establishing an effective
stakeholder group;
•	holding public meetings regarding the project.
We believe such commitments by EPA and Fort Worth are steps in the right
direction. However, these commitments also need to fully address the concerns
we have discussed in Chapters 2 and 3 regarding superior environmental
performance, regulatory flexibility, stakeholder involvement, and the precedent
setting nature of Project XL transferability.
Agency Comments and OIG Evaluation
EPA provided a response to our draft report that consolidated the comments of
five EPA offices. Although the Agency did not agree with our presentation of
certain issues, it agreed to implement the majority of our recommendations and
noted that our report would be helpful as it endeavors to carry out tests in a
scientifically sound manner. In addition to technical comments, the Agency
expressed concern with two aspects of the draft report. First, it stated that the tone
of our draft report was "unnecessarily negative" and suggested that we provide
more credit for its recent efforts to work with the City of Fort Worth to improve
the proposed Method. In response, we created a "Recent Developments" section
in the Executive Summary that discusses and gives credit to the Agency for their
recent actions. This information was already provided in Chapters 2 and 4, but we
summarized it in the Executive Summary to ensure that the Agency received
appropriate credit for its recent efforts to work with the City of Fort Worth on this
proposal.
The second Agency concern related to differing interpretations of the precedent-
setting nature of the Phase II test and the Agency's assertion that, "Any concerns
iv

-------
regarding broad use of the alternate method seem premature." Our work shows
otherwise. Project XL was created to provide the regulated community with the
flexibility to develop alternative strategies to replace or modify existing regulatory
requirements on the condition that those strategies produce superior
environmental performance. In our view, and in the views of many stakeholders
we contacted, if EPA were to declare the Fort Worth Phase II test a success, many
fiscally challenged municipalities would pressure the Agency to use this process
to demolish asbestos containing structures in their areas. However, the majority
of stakeholders we contacted believed that the Fort Worth Method needs
significant modifications before it could be considered as potentially equivalent to
the Asbestos NESHAP.
We continue to believe that OIG involvement in projects such as the Fort Worth
Method is both appropriate and timely, especially when such projects have the
potential to impact existing and possibly set new environmental and health
protection precedents. We have made other modifications to the report based on
specific comments from the Agency, and we have included the Agency's
consolidated response in its entirety in Appendix I. Our evaluation of the
Agency's consolidated response is in Appendix J.
v

-------
Table of C
Executive Summary
Chapters
1	Introduction	 1
Purpose	 1
Background	 1
Scope and Methodology	4
2	Significant Modifications Necessary to Ensure
Adequate Protection of Human Health	5
Current Methods of Asbestos Demolition	 5
Fort Worth Method Not Adequately Defined 	6
Proposed Air Monitoring Standard Not Appropriate 	 10
Proposal Not Peer Reviewed 	 11
Recent Developments	 12
Conclusion	 12
Recommendations	 13
Agency Comments and OIG Evaluation	13
3	Key Project XL Criteria Not Addressed	15
Superior Environmental Performance Questionable		15
Regulatory Flexibility Requirements Not Addresses		16
Stakeholder Involvement Incomplete 		17
Transferability of Method Uncertain		18
Development of Final Project Agreement (FPA) Necessary		18
Recent Developments		18
Conclusion		19
Recommendations		19
Agency Comments and OIG Evaluation	19
4	Better Agency Oversight Needed	21
Phase I Conditions Still Not Met	21
Stakeholders Concerns Unaddressed 	 22
Agency Policies and Procedures for Similar
Types of Alternative Proposals Lacking 	23
Recent Developments	 24
Conclusion	25
Recommendations 	26
Agency Comments and OIG Evaluation	27

-------
Appendices
A	The Fort Worth Method	29
B	Details on Scope and Methodology	33
C	Summary of Stakeholder Responses	35
D	Design, Methodology, and Worker Protection
Issues Identified by Stakeholders	37
E	Concerns Regarding the AHERA Clearance Level	43
F	Revised Fort Worth Method (as of Sept. 23, 2003)	 45
G	Analysis of the Revised Fort Worth Method	51
H	Five Attributes of Environmental Data Quality	55
I	EPA Response to Draft Report	57
J	OIG Evaluation of EPA Response to Draft Report	73
K	Distribution 	81

-------
This page intentionally left blank

-------
Chapter 1
Introduction
Purpose
The Office of Inspector General (OIG) initiated this evaluation because of the
national policy implications of this precedent-setting demonstration project, and
because the project involves the demolition of buildings containing regulated
quantities of asbestos. While Phase II of the proposal only focuses on one
demolition, the entire project has a much larger potential impact. The data
generated by the proposal may be used to justify the demolition of as many as 50
buildings containing asbestos in the Fort Worth area. Also, since this proposal
was introduced under Project XL, if the tests are considered successful, other
cities may use the data generated by this project to justify similar demolitions.
Some have already requested information related to this project.
Our evaluation objectives were to determine whether:
1.	The design and methodology of the Fort Worth Method - Phase II are
adequate to demonstrate protection of human health and the environment.
2.	The Fort Worth Method - Phase II meets EPA's key Project XL criteria,
including superior environmental performance, regulatory flexibility,
adequate stakeholder involvement, and transferability to other asbestos
demolition projects.
3.	EPA's oversight to date has ensured that the Fort Worth - Phase II project
will allow EPA to reach valid conclusions on the effectiveness of such
demolition techniques for each type of asbestos.
Background
Asbestos is made up of microscopic bundles of fibers that may become airborne
when disturbed. These fibers get into the air and may be inhaled into the lungs,
where they may cause significant health problems. According to EPA
Publication (EPA-340-1-90-020), "Scientists have not been able to develop a
'safe' or threshold level for exposure to airborne asbestos." However, those
researchers stated that the greater and the longer the exposure, the greater the risk
of contracting an asbestos related disease. Asbestos related diseases include
asbestosis, lung cancer, and mesothelioma.
1

-------
Asbestosis is a serious, progressive, long-term disease caused by inhaling asbestos
fibers. The fibers cause scarring of the lung tissue, which makes it harder for the
lungs to do their job of getting oxygen into the blood. Lung cancer causes the
largest number of deaths related to asbestos exposure. People who work in
occupations involving the mining, milling, manufacturing, and use of asbestos and
its products, including construction and demolition workers, are more likely to get
lung cancer than the general population. Mesothelioma is a relatively rare form of
cancer that is found in the thin lining of the lungs, chest, abdomen, and heart.
Several hundred cases are diagnosed each year in the United States, and most
cases are linked with exposure to asbestos.
Because there is not a safe level of exposure for asbestos, EPA did not promulgate
an asbestos emission standard.1 Instead, the Clean Air Act provides the
Administrator with the authority to promulgate a "work practice standard" if it is
not feasible to establish an emissions standard. Under Section 112 of the Clean
Air Act, asbestos is determined to be a hazardous air pollutant that must be
regulated under EPA's asbestos National Emission Standard for Hazardous Air
Pollutants (NESHAP). The asbestos NESHAP specifies certain work practices
that must be followed during demolitions and renovations of all structures,
installations, and buildings that contain RACM. However, asbestos removal in
accordance with EPA's asbestos NESHAP is costly because the regulations
require that owners and operators take precautions to protect the public by
minimizing the release of asbestos fibers during activities involving the
processing, handling, and disposal of asbestos-containing materials. Also, Section
61.150 of the Asbestos NESHAP requires owners and operators to "discharge no
visible emissions to the outside air" during demolition and renovation activities.
More than 166,000 asbestos demolition and/or renovation projects were
conducted in the two-year period between the first quarter of 2001 and the first
quarter of 2003, according to the National Asbestos Registry System. About 5.7
million cubic feet of RACM are disposed of annually from demolition/renovation
operations, with demolitions comprising approximately ten percent of these
activities. In 2000, a Miami University of Ohio/University of South Carolina
survey found that the 35 responding cities collectively had more than 91,000
abandoned buildings in need of demolition. According to one EPA asbestos
expert's estimate, as many as 80 percent of these structures would contain RACM.
In 20 U.S.C. 3601(a)(l-3) of the Asbestos School Hazard Detection and Control Act of 1980, Congress found that: (1)
exposure to asbestos fibers has been identified over a long period of time and by reputable medical and scientific evidence
as significantly increasing the incidence of cancer and several other severe or fatal diseases, such as asbestosis; (2) medical
evidence has suggested that children may be particularly vulnerable to environmentally induced cancers; and (3) medical
science has not established any minimum level of exposure to asbestos fibers which is considered to be safe for individuals
exposed to the fibers.
2

-------
Project XL Goals
The proposal under review was submitted under EPA's Project XL program, a
national initiative that encourages testing of cleaner, cheaper, and smarter ways to
attain environmental results superior to those achieved under current regulations
and policies, in conjunction with greater accountability to stakeholders. Project
XL was created to provide the regulated community with the flexibility to develop
alternative strategies to replace or modify existing regulatory requirements on the
condition that those strategies produce superior environmental performance.
The Fort Worth Method
The City of Fort Worth submitted a proposal on September, 30, 1999, for an
alternative method to the asbestos NESHAP. Under the Fort Worth Method, the
City proposes to demolish substandard structures that are not in danger of
imminent collapse but which, if left standing, may become structurally unsound
over a period of years. The City proposes to do this without removing all the
regulated asbestos-containing material from the structure. If approved, this
method could change the way that asbestos demolitions are conducted nation-
wide.
The Fort Worth Method calls for structures to be thoroughly and adequately
wetted using fire hydrant water prior to and during demolition, and during debris
loading. The method also calls for using one or more bulldozers to demolish
single story buildings, and a combination of bulldozers and track-hoes to demolish
multi-story buildings. Once demolition is complete, the method states that,
"Debris that is not contaminated by asbestos-containing material will be treated as
construction debris. All other debris will be treated as asbestos-containing
material and will be transported to a licensed disposal site in lined and covered
containers." Appendix A provides a detailed description of the Fort Worth
Method.
The Fort Worth Project XL proposal is divided into three phases:
Phase I - demolition of a small, single-family wood structure - which was
exempt from the NESHAP requirements, occurred on April 22-25, 2001.
Phase II of the project, the demolition of two buildings at the former
"Cowtown Inn", is proposed for the summer of 20042.
If the demolition conducted under Phase I and proposed under Phase II are
determined to be successful, Phase III testing would proceed with the
demolition of as many as 50 additional buildings in the Fort Worth area.
According to a conversation with Region 6 staff in November 2002, the Phase II demolition was intended to be conducted
in January, 2003, but was later deferred to June 2003. However, based on the most recent developments (see Chapter 4),
EPA plans for demolition to occur any time after August 2004.
3

-------
The proposed Phase II demolition site is an old Travelodge motel, consisting of 9
predominantly 2-story buildings in varying states of disrepair, that is located in a
residential community and very near a school. According to the City of Fort
Worth, the positive impacts of the method will include a reduction in crime
havens, increased aesthetic beauty, increased development potential, and
increased community pride. Fort Worth officials estimate that using the Fort
Worth Method on the proposed Phase II structure could reduce demolition costs
by as much as 60% compared to using the NESHAP method. Also, since this
proposal was introduced under Project XL, other cities may use the data generated
by this project to justify similar demolitions, and have already requested
information related to this project. Therefore, the Fort Worth Project XL initiative
will be precedent-setting for asbestos demolition and renovation activities.
Scope and Methodology
We reviewed EPA's policies and guidance concerning Project XL and related
innovations activities. We also reviewed the Fort Worth Project XL proposed
project's design and methodology. We conducted evaluation fieldwork in EPA
offices including the Office of Air Quality Planning and Standards (OAQPS); the
Office of Enforcement and Compliance Assurance (OECA); the Office of
Research and Development (ORD); the Office of General Counsel; the Office of
Policy, Economics and Innovation (OPEI); the Office of Children's Health; the
Office of Environmental Justice; and, Region 6. We also conducted evaluation
fieldwork at the City of Fort Worth, Texas, including touring the proposed Phase
II site with an OIG Certified Industrial Hygienist.
In order to obtain external perspectives of the proposed Fort Worth Method, we
also interviewed 15 external stakeholder groups from industry associations,
environmental groups, academic organizations, and other Federal Agencies. We
selected these groups based on information identified during our research, and
with input from EPA and the City of Fort Worth. Details on the scope and
methodology, a list of documents provided to the stakeholders, and selection of
external stakeholder groups are included in Appendix B.
The evaluation was performed in accordance with the Government Auditing
Standards, issued by the Comptroller General of the United States. We conducted
our fieldwork from February 2003 to July 2003.
4

-------
Chapter 2
Significant Modifications Necessary to
Ensure Adequate Protection of Human Health
Significant modifications to the design and methodology of the Fort Worth
Method will be necessary for EPA to ensure that the data generated and used to
evaluate this project will be valid. The description of the Fort Worth Method,
revised by the City on May 23, 2002, does not identify all the factors and variables
that could be encountered during a demolition or specify how these elements
would be addressed. There are concerns that the proposed air monitoring standard
under this project is not appropriate. Additionally, the Fort Worth Method has not
been independently peer reviewed. As a result, the current design and
methodology is not adequate to demonstrate protection of human health and the
environment.
Current Methods of Asbestos Demolition
Under the current Asbestos NESHAP regulations, there are very specific methods
for demolishing buildings that contain RACM. For buildings that are not in
danger of imminent collapse, the NESHAP Method is the typical demolition
process used. Under the NESHAP Method, the owner-operator must follow all of
the work practice requirements outlined below:
Discharge no visible emissions;
• Remove all RACM from a facility being demolished or renovated before
any activity begins that would break up, dislodge, or disturb the material;
Adequately wet and carefully remove facility components that contain, are
covered with or coated with RACM; and,
Adequately wet RACM that is stripped from facility components during
the operation, or stripping it in an air-tight containment area with a
negative air pressure ventilation and collection system, or in a glove-bag
system designed to contain the asbestos material produced by the
stripping, or wrapped in leak-tight wrapping to contain all the RACM prior
to dismantlement.
Under certain circumstances, an owner-operator may request a variance from the
NESHAP requirements. However, in order to qualify for a variance, the owner-
operator must propose an alternate demolition process that meets requirements
very similar to the NESHAP requirements above.
5

-------
If a structure is unsound and in danger of imminent collapse, it is not possible to
utilize either the NESHAP method or a NESHAP variance because these options
would endanger the safety of asbestos workers. In this situation, the structure
must be demolished utilizing the NESHAP Imminent Hazard method. Using this
method, the owner-operator may demolish the building in an expedient and
straightforward demolition process, often using a bulldozer with a spray of water
to reduce dust. However, even in this case, certain work practices and public
health precautions must be utilized to ensure no visible emissions are released
from the section of the building that contains RACM.
Fort Worth Method Not Adequately Defined
The current description of the Fort Worth Method, dated May 23, 2002, does not
identify the key factors and variables that could be encountered during a
demolition and does not describe how such issues would be addressed. Based on
the current documentation, single-story structures demolished using the Fort
Worth Method will be thoroughly wetted using fire hydrant water and demolished
using one or more bulldozers, while a combination of bulldozers and track-hoes
will be used to demolish multi-story buildings. The walls and interior
components will be leveled on top of the building foundation, and debris will be
loaded prior to removal of the concrete slab if present. Segregation of demolition
debris will be done to the extent feasible to reduce the amount of contaminated
debris that will be treated as asbestos-contaminated waste, and the site will be
graded for future use following completion of the demolition. According to the
method document, "Air monitoring will be conducted in compliance with the
Quality Assurance Project Plan and the Final Project Agreement." Please see
Appendix A for a more detailed description of the Fort Worth Method.
Our evaluation of the Fort Worth Method document indicates that, as currently
written, neither EPA, project officials, nor the public would have a clear
understanding of the method prior to its implementation, and may have difficulty
replicating this method at other locations. For example, it is unclear:
Exactly what RACM would be removed or left prior to demolition of the
structure (Table 2.2 lists the types of materials that should be specifically
addressed in the Method);
How these materials would be tested for RACM;
What instrumentation would be used for testing different RACM;
What detection limits would be used in testing these materials;
How friable RACM (RACM with a high probability of being crumbled,
pulverized, or reduced to powder) would be treated;
How runoff would be controlled, tested, and a determination made as to
whether it contained RACM;
6

-------
How testing would be conducted to determine if RACM is adequately
wetted3; and,
What volume of asbestos must be present in the Phase II and Phase III
structures to provide representative tests for the method.
Also, Section 2C of the Fort Worth Method only provides that the "asbestos
assessment report will allow for the development of a demolition strategy." It is
unclear whether the resultant "demolition strategy" will receive the same level of
scrutiny as is indicated for the asbestos assessment report. The Fort Worth
Method is also unclear as to whether EPA or any other regulatory agency is
required to review and approve the "demolition strategy" prior to its
implementation. Additionally, the Fort Worth Method does not provide for
contingency planning in the event that other types of RACM (besides Thermal
System Insulation and spray-applied fireproofing) are encountered during the
demolition process, nor does it provide for safeguards in the event that
unanticipated conditions cause a health or environmental concern in the area.
Another important unaddressed factor is that the Fort Worth Method does not
provide for an immediately enforceable stopping point that allows regulators to
question if asbestos is being released during demolition. With the various
NESHAP methods, the "no visible emissions" work practice standard allows for a
demolition to be stopped if visible emissions are identified. However, the Fort
Worth Method does not utilize a work practice standard, but rather depends on the
analysis of air monitoring samples, which take several days to analyze. Under the
Fort Worth Method, demolition activities would continue even if visible
emissions were identified, allowing for potential releases of asbestos into the
environment. It is especially important for the Phase II demolition to have an
immediately enforceable stopping point because the proposed Phase II test
structure is located next to a residential neighborhood and a neighborhood school.
A comparative analysis between the NESHAP requirements and the Fort Worth
Method is presented in Table 2.1 below.
The absence of visible emissions is not sufficient evidence of being "adequately wet."
7

-------
Table 2.1: Comparison of Fort Worth Method to NESHAP Requirements
Demolition Method
Comparison
NESHAP
Method
Imminent
Hazard
Method
Fort Worth
Method1




Structurally Sound
Buildings
Yes
No
Yes
Asbestos
Assessment
Yes
No
Yes
Provide notice to State
agency
10 days in
advance
As soon as
possible
2 days in advance
Remove All RACM prior
to demolition
Yes
No
Only large quantities of
Spray-on Fireproofing and
Thermal System Insulation
Adequately Wet RACM
during demolition
Yes
Yes
No2
Discharge No Visible
Emissions
Yes
Yes
No3
Not Dependent on Air
Monitoring Results
Yes
Yes
No4
Immediately Enforceable
Stopping Point
Yes
Yes
No5

1 If the Agency determines that the proposed Fort Worth Method achieves emissions reductions that are equivalent to the current
requirements, then it could be used as an alternative to the current asbestos NESHAP. (See Chapter 3 for a detailed discussion).
2 The Fort Worth Method did not specifically state how testing would be conducted to determine if RACM is adequately wetted.
3 As discussed above, the Fort Worth Method does not employ a work practice standard that requires "no visible emissions" of asbestos.
4 As discussed above, the Fort Worth Method depends on the analysis of air monitoring samples, which take several days to analyze.
5 As discussed above, the Fort Worth Method does not provide for an " immediately enforceable stopping point" that allows regulators to
question if asbestos is being released during demolition
External Stakeholders Views
We asked 15 external stakeholder groups, including industry associations,
environmental groups, and other Federal Agencies to independently review and
assess the current documentation of the Fort Worth Method (See Appendices C
and D). Thirteen of the 15 external stakeholder groups we interviewed do not
believe that the Fort Worth Method is either equivalent or superior to the
NESHAP. Three of the 15 stakeholder groups (the U.S. Department of Housing
and Urban Development, Division of Healthy Homes and Lead Hazard Control;
the International Union of Heat and Frost Insulators and Asbestos Workers; and,
the Environmental Information Association) did not believe that further
development of the Fort Worth Method should continue because the proposed
8

-------
method would be unenforceable, and it could never be conducted without
releasing asbestos into the environment. Twelve of the 15 did not believe that the
method was adequately defined. The remaining groups that did not believe that
the method was adequately defined provided the following suggestions for how
the method could be improved:
Air monitoring should be conducted using a contractor that is independent
from the demolition contractor;
The method documentation should specifically address wetting the inside
of the structure prior to demolition;
A bulldozer should not be used, as specified in the method, because it
could tear up the material and break it down, therefore making it friable;
There should be a third party consultant onsite at each demolition to
actually "sign-off on whether the asbestos materials and the building in
general have been adequately wetted;
The method should specifically describe the distance from the demolition
building where air samples would be collected; and,
The documentation should specify the total allowable volume of asbestos
that can be contained in the building while using this method.
Appendices C and D summarize the comments received from stakeholders we
contacted.
Table 2.2 lists various asbestos containing materials that, based on our work -
including input from stakeholders - we believe need to be specifically defined
with regards to the Fort Worth Method prior to implementation.
9

-------
Table 2.2: Materials That Should Be Addressed in Proposed Fort Worth Method
Asbestos Containing Materials that Need to Be Addressed

Specific Type
of Thermal
System
Insulation4
•	tank insulation
•	pipe insulation
•	elbow/fitting/valve insulation
•	boiler insulation
•	duct insulation
•	cement and patching compound
Surfacing
Material
•	mastic for flooring
•	asbestos-impregnated plaster, stucco
•	spray-applied fireproofing
•	spray-applied surface coatings (popcorn ceiling, vermiculite
treatments)
•	spray applied acoustical or decorative surfacing.
•	troweled-on crows foot texture, splatter texture, and joint
compound.
•	spray-applied surface coatings crows foot texture, splatter texture,
etc.
•	window caulking
Miscellaneous
Material
•	fire curtains in auditoriums
•	fire doors
•	vibration-dampening cloths
•	asbestos-cement tiles, sheets, roofing shingles, and transite
•	asbestos-impregnated roofing cement and asphalt roofing
shingles
•	linoleum or other floor tile
•	roll flooring
•	ceiling tile
•	asbestos-impregnated pipe
Proposed Air Monitoring Standard Not Appropriate
Several stakeholders we contacted suggested that the air monitoring standard
proposed in the Fort Worth Method (the 70 s/mm2 Asbestos Hazard and
Emergency Response Act (AHERA) clearance criterion) is not appropriate for use
in ambient air monitoring around a demolition site because:
It is not health-based;
The original reason for its development - that it represented an average
background contamination level on asbestos testing filters - is no longer
correct; and,
While the method provides that RACM consisting of more than 260 Linear Feet of Thermal System Insulation (TSI) will
be removed, it does not specifically list what materials are classified as TSI.
10

-------
The criterion is an indoor air, post-abatement clearance level that is used
by EPA to determine the success of asbestos abatement work conducted
under full containment, and requires sampling in a finite, enclosed space,
and with a contained volume of air.
More than half of the external stakeholders (8 of 15) we interviewed did not
believe that the AHERA standard was the appropriate measurement for this
Method. One stakeholder commented that the AHERA standard was only
intended to be used as an indoor clearance procedure after asbestos removal had
been conducted, and while containment was still in place. He stated that the air
monitoring outlined under the Fort Worth Method was not an aggressive test that
requires the use of fans and leaf blowers during containment. Another
stakeholder, who was one of the 26 people on the committee that advised EPA on
the development of the AHERA Standard, stated that, "nobody ever said that 70
structures was a safe exposure level, just that it was the lowest level measurable
(at that time) because of background contamination on the filters." Today, based
on sampling performed for the World Trade Center explosions, it has been
determined that background contamination of filters is low enough to accurately
detect asbestos fibers at about 15 s/mm2. Appendix E provides additional details
on the propriety of using the AHERA clearance level in the Fort Worth proposal.
Also, the placement of the ambient air monitors is not adequately addressed in the
Quality Assurance Project Plan (QAPP). The placement of the monitors at a
particular height may not capture all the asbestos fibers released. For example,
some stakeholders suggested that monitoring at multiple heights and multiple
distances may be needed to adequately determine whether asbestos particles
escaped the demolition area. Further, setting monitors at upwind and downwind
locations only, and not monitoring the entire perimeter, may not capture all
asbestos released, as winds may be variable and the dispersing of fibers may not
be predictable. As observed during the Phase I demolition, wind direction varied
significantly.5
Proposal Not Peer Reviewed
The proposed project has not been peer reviewed. The EPA Science Policy
Council Peer Review Handbook dated December 2000 provides that, "Peer review
is intended to uncover any technical problems or unresolved issues in a
preliminary (or draft) work product through the use of independent experts."
Further, that document states that, "Peer review enhances the credibility and
acceptance of the decision based on the work product."
The Quality Assurance Project Plan (QAPP) for the Phase I demolition required that if wind direction varied by more than
67 degrees for more than a 60-minute period, sampling would be terminated. In their April 9, 2002, Phase I Report
Addendum, project officials acknowledged that wind direction varied by more than 67 degrees for more than a 60-minute
period and yet demolition was not halted.
11

-------
Thirteen of the 15 external stakeholder groups interviewed believed the project
should be peer reviewed (See Appendix C). Recently, EPA officials told us they
would have the Phase II proposal externally peer reviewed prior to
implementation.
Recent Developments
City of Fort Worth officials met with Agency officials on September 29, 2003,
and provided additional documentation including a revised method dated
September 23, 2003. The revised method provides more details in some areas.
However, in some cases, these additional details raise further concerns.
According to OECA officials, the revised Method is still insufficient to determine
equivalency to other types of construction and other types of RACM. Of
particular note is that Fort Worth does not plan to conduct any air monitoring at
Project XL demolitions after Phase II. OECA officials remain concerned that a
single test is insufficient to gauge project effectiveness. Additionally, based on
revised cost estimates for the Phase II demolition, the projected 40 to 60 percent
savings that Fort Worth officials envision would only be achieved when air
monitoring is not conducted. As such, we believe this revised method is still not
equivalent to the NESHAP, and portions of the revised Fort Worth Method may
be less protective than the previous version of the Method. Also, a determination
of equivalency utilizing only the results of the Phase II test is not scientifically
sound, because one demolition would not be representative of the various types of
buildings to be demolished, the types of RACM likely to be found, and weather
conditions that could be encountered. Appendix G provides a detailed
comparison of the May 23, 2002, and September 23, 2003, versions of the Fort
Worth Method.
Conclusion
The Fort Worth Method Phase II test - as presently described - does not ensure
protection of human health and the environment. The Method does not provide a
reliable, repeatable, scientifically valid test that can be replicated at other
locations, or that can be used to predict the success or failure of future uses of this
method. Because of the potential national implications of this proposed project, it
is important that project documentation, design, and methodology is detailed and
clear enough that the Agency - as well as interested and affected parties -
completely understand what is being proposed. Further, the air monitoring criteria
used to determine success of the proposal must be appropriate, the method must
be tested on a representative number and type of buildings to ensure statistical
confidence, and the Method should be peer reviewed to assure that decisions
made are based on sound science.
12

-------
Recommendations
We recommend that the Assistant Administrator for Air and Radiation, the
Assistant Administrator for Enforcement and Compliance Assurance, the
Regional Administrator for Region 6, and the Associate Administrator for Policy,
Economics, and Innovation ensure that:
2-1. Agency officials assist Fort Worth in modifying the Fort Worth Method to
produce a single, finalized technical specification proposal, including the
demolition strategy and associated QAPP that:
a.	identifies and adequately describes how each type of RACM that
may be encountered during demolition will be addressed;
b.	better defines the wetting requirements;
c.	is documented in sufficient detail to allow for independent
assessment; and,
d.	is evaluated based on an appropriate air monitoring standard and
monitoring that is representative.
2-2. Agency officials assist Fort Worth in fully describing the air monitoring
that will take place, and to determine whether the air monitoring contractor
would be independent from the demolition contractor.
2-3. Agency officials require that the Fort Worth Method is adequately peer
reviewed prior to implementation.
2-4. Agency officials outline criteria that determines the volume of RACM
necessary to ensure a representative comparison to the NESHAP, and
assist the city in locating a structure that meets these criteria.
Agency Comments and OIG Evaluation
EPA provided detailed comments to our draft report, and where appropriate, we
made revisions. EPA concurred with the specific recommendations outlined in
this chapter. The Agency responded that it has already specified that revising the
Fort Worth Method and the associated QAPP, and peer review of the documents,
are pre-requisites for moving forward with the Phase II test.
The Agency disagreed with several specific findings of our technical evaluation of
the Fort Worth Method. These included the requirement that RACM be
adequately wetted, that no visible emissions be emitted, and that there be an
immediately enforceable stopping point. The Agency stated that these
requirements were included in the various documents associated with the Fort
Worth Method Project XL proposal. However, these requirements are not
13

-------
specifically stated in the Fort Worth Method, and we continue to believe that these
requirements must be included in the Method itself. The Agency's complete
written response to our draft report and our detailed evaluation of that response
are contained in Appendices I and J.
14

-------
Chapter 3
Agreement Lacking on Key Project XL Criteria
Although the City of Fort Worth initially proposed this project in 1999, four key
Project XL criteria outlined in EPA's 1995 Federal Register Notice have not been
adequately addressed, including superior environmental performance, regulatory
flexibility, adequate stakeholder involvement, and transferability. According to
XL requirements, each of these criteria must be satisfactorily demonstrated in
order for an XL project to be deemed successful. The principal reason for the
delay was because a Final Project Agreement, normally written early in an XL
project, has not been developed due largely to internal Agency disagreements
about the adequacy and benefits of the Fort Worth proposal.
In 1997, EPA issued a Federal Register Notice clarifying the Project XL process,
stating that, while the original criteria provided in the 1995 Federal Register
Notice were still important, the first three - superior environmental performance,
regulatory flexibility, and stakeholder involvement - actually defined Project XL.
The following sections discuss the extent to which these three criteria have been
met for the Fort Worth Project XL proposal, as well as the transferability of the
proposal for use in other applications.
Superior Environmental Performance Questionable
The 1997 Federal Register Notice that revised the Project XL process also better
defined how superior environmental performance was to be determined.
According to that revision, a project can meet the superior environmental
performance requirements if it is at least equivalent to the current requirements,
while providing additional benefits, such as a clear reduction of risk, or better
achievement of community and public health priorities. However, a project that
was not considered equivalent to current requirements could not be considered
superior overall. Based on information presented in Chapter 2, it is not clear that
the currently proposed Fort Worth Method is equivalent to the current Asbestos
NESHAP.
EPA's Project XL internal team members have yet to reach agreement on whether
the Fort Worth Method is equivalent to the Asbestos NESHAP. Both OECA and
OAQPS expressed significant concerns about the adequacy of the proposed Fort
Worth Method. Specific concerns raised by both these groups included: the
adequacy of Fort Worth wetting method; the ability of the process to control
releases of asbestos from RACM; possible contamination of demolition
equipment and surrounding area with friable asbestos emissions from building
materials; cleanup of contaminated soils; and, how environmental benefits of the
15

-------
Fort Worth Method would be compared to the Asbestos NESHAP. These specific
concerns were expressed to Region 6 staff in numerous submissions of written
comments between February 1999 and June 2002.
Although aware that team disagreement had not been resolved, the Reinvention
Action Committee6 decided in January of 2000 that the Fort Worth proposal
should move forward in phases. Phase I, demolition of a single family dwelling
that was exempt from the NESHAP, was conducted in April 2001 in an attempt to
show equivalency to the NESHAP. Over two years after the Phase I test, the
Project XL team members are still unable to agree whether the Phase I test was
successful, or whether the test demonstrated that the current method is equivalent
to the Asbestos NESHAP. As discussed in Chapter 2 above, these issues have yet
to be resolved by the Agency, and have carried forward to the Phase II proposal.
Many of the stakeholders that we interviewed were also concerned about the
adequacy of the proposed air monitoring process. One of these stakeholders
stated,
"It is likely that asbestos emissions could be missed by the air monitors
because the overall testing requirements seemed incomplete. Further, air
monitoring alone is not sufficient. There should be soil samples after the
work was done, and methods that captured and tested wetting water to
ensure that asbestos was not being released into the environment through
a different media. Finally, there should be a comparison test between the
Fort Worth Method and the NESHAP. However, the current method is not
sufficient to serve as a methodology for that comparison test."
Regulatory Flexibility Requirements Not Addressed
In order for a Project XL proposal to be implemented within the scope of the
applicable laws and regulations, a legal mechanism that provides sufficient
regulatory flexibility (e.g., regulatory waiver, site-specific rule-making) must be in
place. Under the Asbestos NESHAP, which implements these requirements of the
Clean Air Act, EPA must publish a notice in the Federal Register that approves an
alternative means of controlling asbestos before it is implemented. This notice
allows the public the opportunity to assess the proposed alternative, and ensures a
process of openness in the development of a new demolition method. Because
EPA has not issued such a Federal Register Notice for the Fort Worth Method, the
Agency has not established the appropriate legal foundation for this demonstration
project.
Reinvention Action Committee membership for each proposal is made up of at least five different organizations (the
relevant Region, the relevant Program office, the Office of Reinvention, the Office of Enforcement and Compliance
Assurance, and the Office of General Counsel), and often more. Each Reinvention Action Committee member is charged
with arbitrating conflicts and making policy decisions within his/her organization as it pertains to XL projects.
16

-------
Additionally, prior to publishing the proposal in the Federal Register, EPA must
make an official determination of equivalency based on the proposed test plan (or
test results). This official determination must include a description of the
procedures followed in testing or monitoring and a description of pertinent
conditions during testing and monitoring. As noted in Chapter 2, numerous
stakeholders have expressed concern regarding the adequacy of the method
description. EPA required a test of the Fort Worth Method in order to provide
sufficient data to determine if the Fort Worth Method was equivalent to the
asbestos standard. However, due to internal disagreements about the Phase I
demolition test results, a determination of equivalency has not yet been made by
the Agency.
Further, EPA may lack the necessary information to make an equivalency
determination because the Phase I demolition using the Fort Worth Method was
not representative of a normal asbestos removal (See Chapter 4 for more details).
In order for a demonstration project to have predictive value for other asbestos
demolition projects, it is necessary for the demolition to be performed in a manner
as close as possible to normal commercial asbestos demolition work. As a result,
moving forward with Phase II without first meeting the regulatory flexibility
requirements of both the Clean Air Act and Asbestos NESHAP could expose the
Agency and the City of Fort Worth to liability issues from the public if it is later
found that asbestos was released into the environment during the test.
Stakeholder Involvement Incomplete
The City has performed some stakeholder involvement activities, including
inviting stakeholders to review and comment on the Phase I proposal documents
on the City's website in 1999. However, according to the 1997 Federal Register
Notice, project sponsors should engage "direct participants" in the development of
the project. According to the Notice, a direct participant "works intensively with
the project sponsors to build a project from the ground up," and "the views of
direct participant stakeholders will strongly influence the details of the project as
well as EPA's ultimate decision to approve or not to approve the project." EPA's
Office of Environmental Justice was not aware of this project, but after reviewing
the proposal, it specifically expressed concern about the level of community
information and stakeholder involvement covered in the current proposal. A
majority of the stakeholders we interviewed were not aware of the Fort Worth
proposal prior to our contacting them, and most raised significant concerns with
the project. Appendix D provides additional details on the views of stakeholders
we contacted.
17

-------
Transferability of Method Uncertain
The Fort Worth Method, as it is known, has not been clearly defined in terms that
provide a clear understanding of what is to be removed during a Project XL
asbestos demolition, making both independent analysis of the Fort Worth Method
and replication by others difficult (See Chapter 2 for details). Twelve of the
fifteen stakeholders groups interviewed did not believe that the method was
sufficiently defined, and ten did not believe that the method could be successfully
"transferred" to another municipality with assurance that it would be properly
replicated with similar results (See Appendix C). As noted by one stakeholder,
there may be inconsistencies in actual application of the Method during the
demolition process (depending on worker knowledge and training, instructions by
the contractor, and/or equipment used), such that starting with a Method that is
not sufficiently detailed significantly increases the likelihood of implementation
problems.
Development of Final Project Agreement (FPA) Necessary
Only the signing of the FPA constitutes the selection of a pilot as a "full fledged"
pilot project, according to the 1995 Federal Register Notice that established
Project XL. The Notice further requires that FPA's address project-specific issues
such as legal authority for project implementation, provisions for regulatory
flexibility for pilot projects, public involvement, specific commitments to
environmental progress, expected environmental results, and enforceability before
implementation. However, nearly four years after the start of this XL project, an
FPA is yet to be written and agreed to by EPA internal stakeholders. The
"estimated timeframes" for when an FPA should be completed is normally less
than 12 months from the date of proposal. This project, however, has continued
for several years without the resolution of key issues.
Recent Developments
In a September 23, 2003, letter from the EPA Region 6 Regional Administrator
for to OPEI, OAR, OECA and ORD, the Regional Administrator wrote that the
City of Fort Worth is fully supportive of the need to meet the requirements under
Project XL, including:
•	preparation of a Final Project Agreement;
•	development of a stakeholder plan that includes establishing an effective
stakeholder group; and
•	holding public meetings regarding the project.
We believe such commitments by Fort Worth are steps in the right direction.
However, these commitments also need to fully address the concerns we have
18

-------
discussed in Chapter 2 and in this chapter regarding superior environmental
performance, regulatory flexibility, stakeholder involvement, and the precedent-
setting nature of Project XL transferability.
Conclusion
Nearly four years after the Fort Worth project was initially proposed, and two
years after the Phase I demolition occurred, core project issues are still in dispute
among various EPA offices. As a result, key Project XL criteria have yet to be
met, superior environmental benefits from this project have not been assured, and
the equivalency of this proposed method has not been determined. Additionally,
moving forward to Phase II without the development of an appropriate regulatory
flexibility mechanism could potentially open the Agency and the City of Fort
Worth to costly liability concerns.
Recommendations
3-1. We recommend that the Assistant Administrator for Air and Radiation, the
Assistant Administrator for Enforcement and Compliance Assurance, the
Associate Administrator for Policy, Economics, and Innovation, and the
Regional Administrator for Region 6 ensure that Agency officials work
with the City of Fort Worth to develop a Final Project Agreement that
adequately addresses key project XL Criteria for the entire proposed
project (Phase II and Phase III), including:
~	determining whether the project can achieve superior environmental
performance;
~	verifying a mechanism for regulatory flexibility;
~	obtaining adequate stakeholder involvement;
~	sufficiently documenting the method so that it can be properly
transferred to other communities with similar results; and,
~	ensuring that all Project XL team concerns are adequately addressed.
Agency Comments and OIG Evaluation
EPA provided detailed comments to our draft report, and where appropriate, we
made revisions. EPA disagreed with several of our statements concerning the
relationship between the Phase I demolition and the remainder of the Fort Worth
Method Project XL demonstration.
We understand that the Phase I demolition was not originally included in the
September 30, 1999, proposal. However, nothing in the additional requirements
for Phase I precluded the Agency from addressing these key Project XL criteria
for the remaining Phases of the demolition project. The Region 6 Conditional
19

-------
Project Approval Letter to the City included the criteria necessary to move
forward to Phase II, including a finding of equivalency from the Administrator. It
remains our position that these key Project XL criteria have not been met. The
Agency's complete written response to our draft report and our detailed evaluation
of that response are contained in Appendices I and J.
20

-------
Chapter 4
Better Agency Oversight Needed
EPA's oversight to date has not ensured that conditions placed on the project in
the 2000 Conditional Project Approval Letter have been met, that problems
related to representativeness and equivalency have been resolved, or that statutory
and regulatory requirements have been satisfied. Additionally, significant
concerns have been raised by Project XL team members, other EPA Regional staff
and interested stakeholders as to whether data to be generated by the Fort Worth
Method - Phase II project will be complete and reliable, and whether the project
will ensure that EPA reaches valid conclusions. Without better oversight, national
policy decisions related to asbestos demolitions could be made based on a
demonstration project that is not representative or transferable to other sites.
Phase I Conditions Still Not Met
Although this project received conditional approval more than three years ago,
EPA oversight has not ensured that conditions placed on the project have been
met. These conditions include determining whether the results of Phase I
demonstrated equivalency and developing a Final Project Agreement. These
conditions were included in a Region 6 Conditional Project Approval Letter to the
City dated January 20, 2000. This letter provided that,
"If the data from the new Phase I supports a finding by the Administrator
that the Fort Worth method is equivalent to the NESHAP method, the
City's originally proposed Phase I will become Phase II and will be
expanded to a wider variety of buildings subject to the asbestos
NESHAP."
Further, the January 20, 2000 letter stated,
"If this determination is that the methods are equivalent, a Final Project
Agreement will be developed and signed, to guide the project through to
and through implementation. If the methods are not found to be
equivalent, the project will end at that time."
The Phase I demolition was conducted more than two years ago (April 2001);
however, the Agency has yet to agree whether Phase I demonstrated equivalency,
and has not issued a finding of equivalency as required in the Conditional Project
Approval Letter. Further, EPA may lack the necessary information to make an
equivalency determination because the demolition was not representative of a
normal asbestos removal for the following reasons:
21

-------
The pace of demolition was much slower than what would occur under
normal conditions;
The amount of water used on the Phase I demolition was not
representative of a normal asbestos removal; and,
The building demolished under Phase I did not contain significant amounts
of spray-applied thermal insulation or asbestos-containing pipe wrap -
asbestos-containing materials which easily become friable.7
Further, the conditions of the QAPP were not met for the Phase I demolition
project. The wind direction varied significantly during the demolition, yet both
the demolition and air sampling continued. The QAPP for this project required
that if wind direction varied by more than 67 degrees for more than a 60-minute
period, sampling would be terminated. In their April 9, 2002, Phase I Report
Addendum, project officials acknowledged that wind direction varied by more
than 67 degrees for more than a 60-minute period and yet demolition was not
halted. In discussions with City of Fort Worth officials, they stated that the winds
reversed exactly 180 degrees one of the days, but they decided to continue the
demolition operation because the shift was exactly 180 degrees and did not
change again. The QAPP conditions regarding wind direction must be clarified
before Phase II demolition is allowed to proceed.
In order for a demonstration project to have predictive value for other asbestos
demolition projects, it is necessary for the demolition to be performed in a manner
as close as possible to normal commercial asbestos demolition work. It is
necessary that demonstration projects contain the types of asbestos that can be
expected to be encountered in normal commercial asbestos demolition. Further, it
is essential that the demolition be conducted in accordance with the Quality
Assurance procedures established to ensure that data obtained are reliable and of
known quality.
Stakeholders Concerns Unaddressed
As discussed in Chapter 3, concerns related to this proposed project have been
raised internally by OAQPS and OECA since 1999. Further, external
stakeholders and other Regional staff members have also expressed concerns. In
the process of our evaluation, we contacted and interviewed 15 external
stakeholder groups to gather their opinions of this proposal. Appendix B
describes the process for identifying these stakeholder groups. One of the groups
believed that the current method was superior, one group believed the method was
equivalent, and 13 groups did not believe the method was either superior or
equivalent. Ten groups we contacted believed that significant modifications
would be needed before the Method could become equivalent to the current
Material that, when dry, may be crumbled, pulverized, or reduced to powder by hand pressure.
22

-------
requirements. Three groups did not believe that further development of the Fort
Worth Method should continue because the proposed method would be
unenforceable. Better EPA oversight and more complete stakeholder involvement
could have resulted in a more timely resolution of these issues.
Two Region 5 employees from the Air Enforcement and Compliance Section
commented to the proposal in a November 18, 1999, memorandum that Region 5
was opposed to the acceptance of the Fort Worth Project XL proposal and raised
several concerns to the XL Team. Further, this proposal was not well received in
March 2002 by participants at the National Conference of State Legislature's 5th
Annual Asbestos Meeting when the proposal was presented by a Region 6
employee. While approximately 100 individuals attended this presentation, none
appeared to speak in favor of the Fort Worth proposal and significant comments
opposing the proposal were made. For example, according to the transcript, one
participant noted that:
"You can't wet a painted ceiling from the bottom. Are you going to poke
holes and saturated ceilings and walls from the backside until you see
water dripping? This seems to me about the money. These guys will be
taking out the asbestos for money. They will lie and this is floor tile on a
grander scale. Is anyone awake here? If this goes through I give you two
conferences from now and everybody will be saying, 'who let this go
through ?' (clapping). "
Some other commenters were more severe in questioning the feasibility of the
proposed Method, with one noting that "In Colorado we feel that outdoor
sampling is a joke..." As a result of the issues discussed above, we believe that
improved EPA oversight and more widespread stakeholder involvement is
necessary to develop and approve an alternative asbestos demolition method.
Agency Policies and Procedures for Similar Types
of Alternative Proposals Lacking
Project XL was one of EPA's early efforts to provide innovative environmental
alternatives. However, Project XL proposals are no longer being accepted
because all such alternative proposals now fall under one of two other EPA
innovations strategies: (1) Environmental Council of the States projects, or (2)
Innovations Strategies. Although both programs are similar to Project XL in that
they provide regulatory flexibility to owners and operators and the opportunity for
cost savings, EPA officials were only able to provide general guidance for how
Environmental Council of the States projects should be carried out in the form of
a Joint EPA/State Agreement, and have not developed policies and procedures for
Innovations Strategies.
23

-------
Unlike Project XL, specific criteria for gauging project success have not been
developed nor published in the Federal Register for these other two innovation
options. While Innovation projects have already been proposed, the Agency's
Innovations guidance is still being developed and no specific criteria have been
developed to date to govern these projects. Consequently, three concerns must be
sufficiently addressed if future innovations projects are to be effectively
administered.
There should be specific guidance regarding the assessment of the
technical merits and enforceability of proposed projects to assure that
expertise within the Agency is fully considered. In this instance, technical
and enforcement concerns by OAQPS and OECA did not appear to be
given sufficient consideration by the Agency co-sponsors prior to the
involvement of the Office of Inspector General. This issue contributed to
dissenting opinions regarding the environmental effectiveness of the
current Fort Worth Method.
Innovations criteria must include a requirement for peer review, especially
when a proposal has significant national policy implications. As discussed
earlier, peer review was not performed on this proposal even though
significant scientific and technical concerns were raised both internally
and externally.
Future Innovations policies should contain required timeframes that are
enforced so that projects cannot continue for years without the resolution
of key issues. We noted that the Environmental Council of the States
agreement includes suggested timeframes for when EPA must make a
decision on whether to accept or reject a proposed project. However, as
discussed above, the Project XL guidance also contained suggested
timeframes and these timeframes were not met.
Recent Developments
EPA is currently considering requiring that the City meet certain conditions that
address some of our concerns before moving to Phase II. However, these
conditions do not address the issue of equivalency. The EPA Innovations Action
Committee, formerly the Reinvention Action Committee, met on May 12, 2003,
and recommended moving forward to Phase II, provided that certain conditions
were addressed. These conditions included:
Requiring the development of a Final Project Agreement (detailing
procedures for the Phase II demolition) by a stakeholder group specifically
assembled for this project.
Requiring EPA staff to work with the City to produce more detailed
method documentation.
24

-------
Requiring that the Method documentation and Quality Assurance Project
Plan for Phase II be peer reviewed.
Reconsidering the proposed Phase II site or ensuring that children in a
nearby school are not exposed to asbestos due to the demolition.
In a September 29, 2003, letter from the EPA Region 6 Regional Administrator to
OPEI, OAR, OECA and ORD, the Regional Administrator wrote that the Region
and the City of Fort Worth plan to take steps to address items recommended by
the Innovation Action Committee, including:
(1)	The use of additional monitors at the adjoining school and
sampling prior to Phase II to establish a background level; and,
(2)	Preparing a remediation plan in case there are emissions.
We believe that these are steps in the right direction. However, there are currently
no sufficient data from Phase I, nor agreement among the XL team members
regarding the results of Phase I, on which to base an equivalency determination.
Further, the revised Phase II proposal attempts to base an equivalency
determination on a single test. As a result, insufficient oversight could allow a
determination of equivalency for an alternative method that has not satisfactorily
established that it will reduce emissions as effectively as the asbestos NESHAP.
Also, while the Agency agrees in its response to our draft report that, "A single
test in Phase 2 is insufficient to serve as a launchpad to implement the Fort Worth
Method," this expectation does not seem to have been effectively communicated
to the City of Fort Worth. The September 23, 2003, revision of the Fort Worth
Method states that the City will only conduct air monitoring during the Phase II
demolition, and afterwards will not conduct further testing of the Method, but
move directly to implementation. We believe that the methodology in this revised
proposal indicates ineffective oversight and communication on the part of the
Agency. Further, this is contrary to the statutory and regulatory requirements
discussed in Chapter 3, and does not satisfy sound scientific processes discussed
above. An alternative emission standard can only be approved after notice and
opportunity for public comment, and valid scientific assurance that the proposed
alternative reduces emissions as effectively as the asbestos NESHAP. Further,
EPA must publish a notice in the Federal Register that approves the alternative
means of controlling asbestos before it is implemented.
Conclusion
Agency oversight should ensure that the tests of alternate methods of asbestos
demolition are representative and that the results of those tests are valid, because
the Agency must use those data to determine if proposed alternatives are
25

-------
equivalent to current requirements. Many internal and external stakeholders have
raised significant concerns related to this project. These concerns should have
been indicators that stakeholder involvement was necessary earlier in the process
to determine whether there was enough support for this project to continue. The
conditions that the Agency is currently considering for the project, including
development of a Final Project Agreement and reconsidering the Phase II site,
would partially address these concerns. However, these proposed conditions do
not address how the Agency will use the data from Phase II, including whether it
will use that data to draw conclusions regarding the equivalency of the Fort Worth
Method.
Recommendations
We recommend that the Assistant Administrator for Air and Radiation, the
Assistant Administrator for Enforcement and Compliance Assurance, the
Associate Administrator for Policy, Economics, and Innovation, and the Regional
Administrator for Region 6:
4-1. Ensure that Agency officials work with the City of Fort Worth to design a
demonstration project that can be used to reach complete, reliable, and
valid conclusions.
4-2. Work with the City to ensure that the structures chosen for the Phase II
demolition contain sufficient asbestos to provide a representative test and
is sited in a remote location.
4-3. Ensure that Agency officials address the key conditions of the Conditional
Project Approval letter, including equivalency and FPA development.
4-4. Ensure that Agency officials specify which legal mechanism will be used
and which technical and process criteria will govern the Fort Worth
Method project in the future, specify how human health will be protected
to at least a level equivalent to the current Asbestos NESHAP, and publish
the proposal in the Federal Register to solicit nationwide input on the
technical merits and enforceability of the proposal.
We also recommend that the Assistant Administrator for Research and
Development and the Associate Administrator for Policy, Economics, and
Innovation work jointly to ensure that:
26

-------
4-5.
Agency officials develop a single guidance document for all proposals
submitted under the Agency Innovations Strategy that provides
fundamental criteria and is published in the Federal Register, including:
requiring assessment of the technical merits and enforceability of
proposed projects;
ensuring that relevant expertise within the Agency is appropriately
considered; and,
requiring peer review of proposals that have significant national
policy implications, to ensure that national policy decisions are
based on sound science.
Agency Comments and OIG Evaluation
EPA provided detailed comments to our draft report, and where appropriate, we
made revisions. EPA agreed with all our recommendations in this chapter except
for recommendation 4-5. EPA considered recommendation 4-5 to be beyond the
scope of this project. Further, EPA disagreed with several of our statements
concerning the requirements of the 2000 Conditional Project Approval Letter, as
well as our assessment of the Phase I demolition. The Agency stated that it is
committed to ensuring that the project is well defined, based on scientifically
valid principles, and shaped through full and open dialogue with a broad
stakeholder group. The need to further refine the Fort Worth Method as it
presently exists, as well as the Quality Assurance Project Plan (air, water, waste
monitoring specifics) for the Phase II test, is a prerequisite set out by the IAC.
We are encouraged with the Agency's intentions regarding better clarification of
the method, external peer review, stakeholder involvement, and development of a
Final Project Agreement. We note, however, that these intentions have yet to be
realized after four years of effort. Therefore, we continue to believe our
observations and recommendations in this chapter are warranted. For example, in
Response 27 (Appendix I), the Agency stated, "...the Phase I test was slower and
not fully representative of a NESHAP removal..." and yet the Agency and Fort
Worth have continued to move forward with the proposed project as if the Phase I
test were fully representative. We agree that the Phase I demolition was not fully
representative of a NESHAP demolition. Therefore, use of Phase I data should
not be used to determine equivalency to the NESHAP.
Regarding recommendation 4-5, EPA officials have told us that no additional
alternative proposals will be conducted under Project XL, and that new alternative
approaches to existing regulations will be carried out under other Agency
initiatives, such as the Agency's Innovations Strategy. For example, EPA's
September 30, 2003, Strategic Plan relies on the Agency's Innovation Strategy for
providing flexibility to the regulated community. We note that, whereas Project
XL performance criteria were established prior to initiation of any proposals and
27

-------
were published in the Federal Register, no similar performance criteria has been
established or published in the Federal Register for EPA's Innovations Strategy.
Therefore, we believe that recommendation 4-5 continues to be an appropriate
step to assure that such projects are evaluated based on sound science, irrespective
of the name of the program or initiative under which they are carried out. We also
believe that the Federal Register notice-and-comment process will allow for
nationwide input on the technical merits and enforceability of any such proposals.
We are pleased that the Agency's Strategic Plan envisions that such future projects
will be clearly defined, based on sound science, and employ a full, open,
transparent, and inclusive stakeholder process. The Agency's complete written
response to our draft report and our detailed evaluation of that response are
contained in Appendices I and J.
28

-------
Appendix A
Fort Worth
The Fort Worth Method
[May 23, 2002 Version]
1.	Declaration of Substandard Structure
The City of Fort Worth Minimum Building Standards Code provides procedures to order the
repair or demolition of structures that may endanger the life, health, and safety of the occupants
or the public.
-	If a structure does not meet the Minimum Building Standards Code, the Code
Compliance Department will give the owner notice to bring the structure into
compliance.
-	If the structure is not brought into compliance, a hearing will be held before the City's
Building Standards Commission. All owners, mortgagees, and lien holders of the
property will be given notice and given an opportunity to comment at the hearing.
-	The Building Standards Commission may, after notice and hearing, declare a structure to
be substandard, and specify in its written order a reasonable time for the structure to be
vacated, secured, repaired, or demolished by the owner.
-	If the Building Standards Commission's order to vacate, secure, repair, remove, or
demolish the building is not complied with within the allotted time, the City may
demolish the building at the City's expense, and assess a lien against the subject property
for costs.
2.	Asbestos Assessment and Abatement
Once the decision has been made that the City will proceed with the demolition of a structure,
the facility will have a thorough asbestos assessment conducted by an EPA accredited and TDH
licensed asbestos inspector who will prepare a written report of the findings.
a.	The assessment will identify asbestos-containing building materials (ACBM) and their
locations in accordance with the Asbestos Hazard Emergency Response Act (AHERA),
Asbestos School Hazard Abatement Reauthorization Act (ASHARA), and Texas
Asbestos Health Protection Act (TAHPA) requirements.
b.	The assessment report will be compiled by the asbestos inspector and reviewed for
completeness and quality by an asbestos management planner or asbestos consultant.
29

-------
c. The asbestos assessment report will allow for the development of a demolition strategy.
If regulated asbestos containing materials (RACM), consisting of more than 160 SF of
spray-on fireproofing or more than 260 LF of thermal system insulation (TSI), are
encountered in a single structure, then removal specifications will be prepared and the
identified material will be removed prior to demolition by a TDH-licensed asbestos
abatement contractor.
3.	Worker protection
a.	The City will require its demolition contractors to comply with all applicable OSHA
regulations for worker protection including but not limited to 29 CFR 1910 and 29 CFR
1926.
b.	The City will contract with an asbestos consultant, licensed by the Texas Department of
Health (TDH), to provide oversight of the demolition process. The consultant will have
a certified industrial hygienist (CIH) on staff.
4.	Demolition Method
a.	Facilities will be demolished one structure at a time.
b.	Demolition contractors will have daily safety meetings prior to work commencement to
ensure safe demolition of the structure(s).
c.	The demolition method will vary by the size and type of facility and types of RACM.
Demolitions will be performed by heavy equipment only. No explosives will be used to
explode or implode structures, and burning will not be utilized to demolish structures.
Multi-family residential structures typically range from one to four stories. Commercial
structures typically range from one to two stories.
i.	Heavy equipment. Typically, one or more bulldozers will be used to demolish
single story buildings, and a combination of bulldozers and track-hoes will be
used to demolish multi-story buildings.
ii.	Wetting. A structure will be thoroughly and adequately wetted using fire
hydrant water applied with a variable rate 11-G (11 gpm) or 30-G (30 gpm)
nozzle prior to, during demolition, and during debris loading. A water meter (or
equivalent device) will be installed at the water hydrant to measure the volume
of water used during demolition of the structure. The water will be delivered as
a mist or concentrated stream. Direct high-pressure water impact of RACM will
be prohibited. The demolition debris will be adequately wet at all times and kept
wet during handling and loading into containers for transport to a licensed
disposal site.
iii.	Collapsing structure inward. The majority of the walls and interior components
will be leveled on top of the building foundation, and debris will be loaded prior
to removal of the concrete slab if present.
30

-------
iv.	Segregation of demolition debris. Segregation of demolition debris will be done
to the extent feasible to reduce the amount of contaminated debris that will be
treated as asbestos-contaminated waste. Debris that is not contaminated by
asbestos-containing material will be treated as construction debris. All other
debris will be treated as asbestos-containing material. Any segregation of the
waste will be the responsibility of an onsite Asbestos NESHAP trained
individual. The asbestos-containing material will be transported to a licensed
disposal site in lined and covered containers.
For example, if RACM is isolated on the structure, the contractor will be advised
to demolish the other areas of the structure first, taking care not to disturb the
RACM, and to load the demolition debris separately. Then the part of the
structure containing the RACM will be demolished and that debris will be
disposed of as asbestos-containing material.
v.	Grading. The site will be graded for future use following completion of the
demolition.
d. No engineering controls are planned to be in place during the demolition other than
adequately wetting the demolition materials.
5.	Storm W ater Protection
Demolition projects typically have a minimal to moderate amount of runoff depending on the site
location and site conditions.
a.	Asbestos has not been identified as a priority or secondary pollutant in storm water
runoff within Fort Worth, and the City expects minimal, if any, asbestos impact on
runoff from any demolition site. The USEPA relevant standards for asbestos are:
Drinking Water Standard: 7 million fibers/liter (40 CFR 141.23 (a)(4)(i))
Reportable Quantity: One pound (40 CFR 302.4 (a) Table 302.4).
Note: The City does not expect to exceed either standard and actually expects to have
minimal to no impact on runoff from asbestos and demolition debris.
b.	Best management practices will be used to control runoff to the maximum extent
practicable. Runoff from the job site will be controlled using a combination of natural
drainage, manmade drainage channels, and silt fencing as applicable.
6.	Air Monitoring
Air monitoring will be conducted in compliance with the Quality Assurance Project Plan and the
Final Project Agreement.
7.	Disposal
a. As stated above in Section 4.c.iv., segregation techniques will be used during demolition
in an effort to reduce the amount of contaminated debris that has to be treated as asbestos
31

-------
contaminated waste. Segregation of waste will be the responsibility of the onsite
NESHAP-trained individual.
b.	Demolition debris will be kept adequately wet during loading and transporting to a waste
disposal site.
c.	Demolition debris will be loaded onto trailers using a track-hoe or similar equipment.
Typically, the contractor will use construction trailers capable of holding 20 cubic yards
of waste material.
d.	Vehicles used to transport asbestos-containing waste material to the landfill must be
covered with a tarp, and must be clearly marked during loading and unloading of waste.
Transportation will be immediate and by a direct route.
e.	The City will not mandate that its demolition contractors use a specific landfill for
disposal. The job specifications for demolitions would state that disposal shall be in
accordance with all Federal, State and local requirements. The contractors will be
allowed to decide which landfill is a viable option. The City will not pay the contractors
until it has received properly completed manifests.
f.	The City will maintain waste disposal records for a minimum of two years.
8. Decontamination
Care will be taken to reduce the potential contamination of other job sites by equipment. Heavy
equipment involved in the handling of asbestos-containing material may be decontaminated by:
a.	Thoroughly rinsing the equipment components that come in contact with the
asbestos-containing material. On-site water supply (e.g., fire hose) will be utilized.
b.	Collection of rinse water on-site into natural depression, tarp lined area, "baby" pool, etc.
The collection will be cleaned and disposable equipment will be disposed of as part of
the asbestos-containing material.
c.	Trailers utilized to transport asbestos-containing material will be cleaned as above or
lined with a disposable liner that will be disposed of along with the final load at the
licensed landfill.
d.	Hand tools, if used, will be thoroughly rinsed with the rinse water captured on-site in a
similar manner to the heavy equipment.
e.	Workers handling or coming in contact with asbestos-containing material will wear
disposable Tyvek suits or equivalent, respirators (as necessary), and gloves (as
necessary). All disposable safety equipment including used respirator cartridges will be
disposed of as asbestos-containing material.
32

-------
Appendix B
Scope and Methodology
To assess whether the Fort Worth Method - Phase II adequately protects human health and meets
the key Project XL criteria, we reviewed numerous statutory, regulatory, and guidance
documents. These included the Clean Air Act, the Asbestos Hazard Emergency Response Act
(AHERA), the Asbestos School Hazard Detection and Control Act (ASHERA), and the Asbestos
National Emission Standard for Hazardous Air Pollutants (NESHAP). Further, we reviewed
numerous Federal Register Notices that were issued during the development and evolution of the
Agency's Project XL Program, as well as EPA Project XL Program guidance documents. We
also reviewed a prior GAO report, Overcoming Obstacles to Innovative State Regulatory
Programs, (GAO-02-268). This report discussed the challenges faced by state, county, or
municipal governments when proposing and implementing alternatives to existing federal
regulations.
In order to better understand the proposed Fort Worth Method - Phase II demolition process, the
evaluation team, including our Certified Industrial Hygienist, toured the proposed Phase II
demolition site. We also reviewed numerous Fort Worth Method documents, including the Fort
Worth Method document, the Project XL Proposal document, and the Quality Assurance Project
Plan. We also interviewed staff from the Fort Worth Method Project XL Team, including
officials from OECA, OAQPS, ORD, OPEI, and Region 6. We collected and reviewed various
written comment documents that were produced by each of these team members.
In order to ascertain the views of external stakeholders regarding the efficacy of this proposal, we
contacted a total of 15 industry associations, environmental groups, and other Federal Agencies.
We provided them with the following Fort Worth Method Documents:
—	The Fort Worth Method Document, dated May 23, 2002;
—	Table - 1: Comparison of the Asbestos NESHAP and the Fort Worth Method for
Demolition of Substandard Structures (developed by Fort Worth, undated);
—	Asbestos Management in the Demolition of Substandard Structures as a Nuisance
Abatement, dated September 30, 1999 (in two parts); and,
—	Quality Assurance Project Plan: Ambient Air Monitoring for Asbestos During
Demolition of Substandard Structures in City of Fort Worth, Texas (Project XL).
After providing these documents, we scheduled structured interviews with each stakeholder
group and requested information and input on the Fort Worth Project XL proposal and the
current Fort Worth Method documentation, including:
whether site preparation, material assessment, and demolition procedures for
RACM is adequately described;
whether work practice requirements for wetting/Misting No Visible Emissions is
adequate;
33

-------
whether the design and methodology of the proposed asbestos demolition method
is adequate to protect human health;
the expected environmental performance of the proposed asbestos demolition
method; and,
whether the method should be peer reviewed before moving forward.
In selecting the external stakeholder groups, we first obtained input from internal stakeholders,
including the City of Fort Worth, Region 6, OAQPS, ORD, OPEI and OECA by providing a list
that we developed based on organizations that commented on the most recent revision of the
Asbestos NESHAP, research, interviews and our knowledge. We then requested that those
stakeholders respond whether the groups on the list are essential and add other organizations to
the list that they believe are essential to contact that are not on the list.
After each internal stakeholder had made their selections, we used the responses to identify all of
the groups that two or more internal stakeholders had recommended that we interview. We also
judgmentally selected organizations that were identified by only one internal stakeholder as
"Essential". All groups identified by OPEI were interviewed because all groups they identified
were also identified by at least one other internal stakeholder. Region 6 first responded that we
should not eliminate any of the original list, but then recommended that we not contact one
group. We then contacted the selected organizations to determine if they would agree to review
the Fort Worth Method Proposal and participate in an interview with the OIG.
The list below identifies the 15 external stakeholder organizations that agreed to be interviewed:
Agency for Toxic Substances and Disease Registry
American Thoracic Society
California Air Resources Board
Cole-McDonald Environmental Consulting, Inc.
•	Environmental Information Association
•	Environmental Institute
HUD, Division of Healthy Homes and Lead Hazard Control
International Union of Heat and Frost Insulators and Asbestos Workers
Laborer's Health and Safety Forum of North America
National Association of Demolition Contractors
National Conference of State Legislatures
National Institute of Building Sciences
NIOSH, Office of Engineering and Physical Hazards
OSHA Office of Compliance
Sierra Club
34

-------
Appendix C
Summary of Stakeholder Responses



Technical Assessment
Yes
No





Useable for Very Friable Materials
1
14

Useable for Friable Materials
2
13

Useable for Non-Friable Materials
11
4



Documentation Assessment
Yes
No





Adequate Definition of Method
3
12

Ensure Accurate Replication
5
10

Provide Reliable Results
5
10

Sci'\c as an Adcquak- Model
5
10



Human Health Protection
Yes
No





Adequate Design
3
12

AHERA Measure Appropriate
7
8



Overall Environmental Performance
Yes
No





Superior to the NESHAP
1
14

Equivalent to the NESHAP
1
14

Does not meet the NESHAP
13
2



Peer Review
Yes
No





Peer review prior to Phase II demolition
13
2



Page 35

-------
Page 36

-------
Appendix D
Design, Methodology, and Worker Protection
Issues Identified by Stakeholders
Design and Methodology Issues

Agency for Toxic
Substances and
Disease Registry
ATSDR indicated that, "After my review of the Fort Worth Method, I am inclined towards the use
of this method in the demolition of structures containing very friable, friable, and non-friable
ACM. It is understood that the ACM will be wetted during the demolition phase (disassembling of
the structure, staging and loading of ACM debris, decontamination of equipment, and the
transportation to an approved waste facility)." However, I do have some questions:
During the wetting process of the structure disassembly, will the wetting process of the ACM
include a surfactant? If not, the addition of a biodegradable surfactant would aid in the reduction of
airborne asbestos fibers from very friable and friable ACM debris and dust.
During transportation of the wetted ACM to an approved disposal facility, is the ACM in a wetted
state throughout the procedure? If not, the ACM in transport should be wet throughout the process
of transportation to its final destination and disposal.
During transportation of the wetted ACM to an approved disposal facility, is the ACM in a wetted
state stored in a leak proof container, and not exposed to the open atmosphere? If not, the ACM
should be stored in such a leak proof container so as to be totally enclosed during transportation. In
addition, a simple cover over the ACM would not suffice. The wetted ACM would dry out quickly
(especially during hot days and with wind drying), thus introducing dry ACM dust and debris to the
atmosphere. The ACM should be stored during transportation, in a leak proof and totally rigid
container.
American Thoracic
Society
It is likely that asbestos emissions could be missed by the air monitors because the overall testing
requirements seemed incomplete. In the QAPP, Section B 1.1 calls for 10 sampling locations, 5
upwind and 5 downwind. Overall, this is an appropriate strategy, but there did not seem to be
enough monitors to capture all of the likely emissions. Further, air monitoring alone is not
sufficient. There should be methods that capture and test wetting water to ensure that asbestos was
not being released into the environment through a different media. Finally, there should be a
comparison test between the Fort Worth Method and the NESHAP. However, the current method
is not sufficient to serve as a methodology for that comparison test.
California Air
Resources Board
The AHERA requirement was supposed to be used as a clearance after asbestos removal had been
conducted under containment. [AHERA] is an aggressive test when used on schools and fans and
leaf blowers are used to test for asbestos while containment is still in place. The Fort Worth
Method would not be an aggressive test. The perimeter monitoring would not represent sufficient
air flow and may not reflect what is actually in the air. It is not clear how far away the monitors
would be [from the demolition].
Cole-McDonald
Environmental
Consulting, Inc.
There should be a 3rd party contractor onsite to observe the process and verily that the demolition
is conducted correctly. Some of the requirements (such as following all applicable OSHA
requirements) were in the Method document, but the document also references the QAPP regarding
some of the technical requirements.
Environmental
Information
Association
The Fort Worth Method does not meet the current NESHAP requirements. However, the method
could be used effectively on some non-friable materials, but this is currently allowed under the
NESHAP. "Better enforcement of existing regulations is more important than relaxing the current
NESHAP requirements." "Relaxing the current requirements will open the door to lower quality,
less enforced demolitions." With the problems that EPA has had with Libby and the World Trade
Page 37

-------

Center issues, this project seems like the wrong thing to be doing. Also, the only benefits that were
cited by the proposal were reduction in costs. "To be looking at a rule change exclusively on costs
isn't the right thing to do. The likelihood of a contractor messing this up is much higher than
messing up the current NESHAP requirements."
Environmental
Institute
The sampling plan does not address what will happen if the air samples come back and indicate
that there was an asbestos release that exceeded the level. There are not provisions in the plan for
what will happen, what the City will do, or how the municipality will deal with the liability issues
that may occur as a result of exceeding the asbestos level. "This contingency should be planned
for, and it is not there." "If you go to the preamble of the AHERA statute, then 70 is an acceptable
level, because statute says that 70 it is an acceptable level for school children to be exposed to."
However, there is an issue with the sampling plan. According to the QAPP, TEM analysis would
be conducted on samples collected on the machinery and the personnel. However, if this is the
case, then it should be applied to the perimeter samples as well. According to the QAPP, the
perimeter air samples will be analyzed with PCM, rather than TEM. They assumed that this was
due to the overall costs. However, this seemed backwards, and that TEM should be dropped on the
personnel, and added to the perimeter. The current analysis process is more stringent in analyzing
the samples on the workers and the machinery, and less stringent on analyzing the samples that
would indicate whether asbestos is being released off-site. TEM should be added to the perimeter
testing, but that if doing TEM on all samples were too costly, then the TEM should be added on the
perimeter samples and dropped from the personnel and machinery samples.
HUD, Division of
Healthy Homes and
Lead Hazard Control
HUD commented that the method does not meet the NESHAP, and that after reading the
comparison table, they realized what the Fort Worth Method was attempting to do. The Fort
Worth Method is trying to jump from the NESHAP to the eminent collapse exemption, and this
would change the whole approach to the NESHAP. HUD further commented that they have had
experience with conforming to the asbestos NESHAP and this proposal attempts to avoid a lot.
HUD stated that it only addresses over 160 square feet of spray-on fireproofing or more than 260
LFofTSI.
International Union
of Heat and Frost
Insulators and
Asbestos Workers
Where will the air monitoring stations be located? This is too variable, regarding the movement of
air. Perimeter monitoring should be conducted on all sides to capture any asbestos released. Also,
asbestos fibers can remain airborne for days. What is to say that all of the fibers that are released
from the site will be captured by the monitors. "They are using AHERA because they think that
they can pass that requirement, but they will ignore what they want to ignore. The demolition will
not be contained, and there will be no aggressive tests, such as use of a leaf blower to stir up the
dust, like the ones required under AHERA containment clearance." "The samples will miss the
material." "There is maybe a 1% chance that fibers will be captured using this method." This
proposal is no where near the requirements that are there to be met. This design and methodology
could lead to a larger exposure of asbestos than would be achieved under the required processes of
containment. The last line of defense is the "plastic bubble." "Using the proposed method, can the
City of Fort Worth guarantee that the ground is clean? What about the liability that the City may
incur by conducting this process and then later learning that it had contaminate the soil with
asbestos. Will the public end up paying to clean up these demolition sites someday when they
become Brown fields?"
Laborer's Health and
Safety Forum of
North America
The Fort Worth Method did not meet the NESHAP requirements. Laborer's said that this method
was not appropriate for friable materials, that it was not equivalent to the NESHAP, and should not
be used in lieu of the NESHAP. Laborer's did state that it may be okay for non-friable materials,
and thought that was the intention of the Fort Worth Method, because the Table that was submitted
along with the proposal (Table 1) stated that, "Spray-on fireproofing and large quantities of thermal
system insulation will be addressed under full containment conditions."
Laborer's stated that, based on their interpretation of the Fort Worth Method, that it only applied to
structures with less than the NESHAP asbestos threshold of 160/260. As a result, Laborer's
evaluated the method from the perspective that it would be used for demolitions with non-friable
materials using mechanical means. Laborer's stated that the method seemed sound for this limited
scope, although he had some questions regarding the air monitoring.
Page 38

-------

Laborer's stated that, overall, this proposal left a bad taste in his mouth. Laborer's didn't know
exactly what was covered by the proposal, and what was not. Laborer's said that on the surface, it
looked adequate for materials that were non-friable, and for volumes of asbestos that were below
the NESHAP, but that Laborer's was concerned about what precedents may be set, and how it may
be interpreted in the future.
Laborer's stated that the method should not be used for Very Friable or Friable materials.
However, Laborer's did state that it may be able to be used for non-friable materials, if some
modifications were made, as discussed regarding air monitoring methods and clarification of the
specific assessment and demolition processes.
National Association
of Demolition
Contractors
With regards to Air Monitoring, the City does not specifically state who will conduct the air
monitoring, or if it will be paid for by the City or the contractor. It should be the City using an
independent contractor. If it were the contractor, it would be like the fox guarding the henhouse.
A bulldozer should not be used because the tracks could tear up the material (break it down making
it friable). An excavator should be used instead.
Also, the documents do not spell out who will determine whether the demolition material, after it is
on ground, is contaminated or non-contaminated. This determination should be done by a third
party hired by the City, not the contractor. Contaminated waste should not end up at the landfill. It
is important to identify who will determine separation, because, "We don't want asbestos
containing materials to end up in the recycling stream."
Further, there are numerous types of pipe wrap and while some may be okay, some cannot be
adequately wetted. Water will not work on some materials (specifically, "mag-block" elbows,
fittings, etc.) and the minute someone hits these materials it will become airborne. If materials
have been painted over several times, water might not get in. The degree of friability does matter.
As an indicator, (AHERA) is appropriate. This measurement requires TEM analysis, which is very
expensive. The method should use PCM and if any fibers are found then use TEM. However, the
asbestos could be removed for what it would cost for the TEM analysis. The savings would not be
40-60% (as estimated by the City). Savings will be closer to 10 percent if sampling was reduced.
Also, the savings estimate did not include the chance that more materials may have to be taken to
an asbestos landfill, and it would be tough to argue that any of the debris was not contaminated.
National Conference
of State Legislatures
NCSL said that states already have enough troubles with enforcing the current requirements and
just believe that this (Fort Worth Method) will simply cause more problems with both enforcement
and compliance. Further, the states think their jobs are difficult at best, and while they would
welcome a change, it would need to be viable and workable for BOTH the contractors and the
enforcers.
NCSL did not believe that the method was sufficient for either very friable or friable materials, and
said that some states are even debating the safety of leaving floor tiles in place, so was unsure
about the use of the method for this level of materials. The Fort Worth Method is not as protective
as the current NESHAP. However, some states would like to see EPA revisit the NESHAP
requirements, and if some of the requirements were removed that would make the entire regulation
more enforceable, then the states may be willing to make that trade-off. NCSL also said that the
Fort Worth Method should be peer reviewed. However, this review should include state and
federal regulators, the regulated community, and those that are or will be impacted by a change to
the NESHAP.
National Institute of
Building Sciences
As one of the 26 people on a committee that advised EPA on this measure [AHERA], the 70
structures was the lowest level measurable because of contamination of the filters. Nobody ever
said that 70 structures was a safe level. Also, this measure is specific to inside containment. The
standard should be the average upwind, ambient levels, which is well below the AHERA standard.
If the method works, there should be no statistical difference between the upwind and downwind
samples.
Page 39

-------
NIOSH, Office of
Engineering and
Physical Hazards
The lack of a contingency plan was an issue. Specifically, that the method is relying on TEM
results for Phase I and Phase II, and these take time to process. Therefore, the people supervising
the demolition are not going to be in the position to know if asbestos has been released or
concentrations were elevated above the allowable limit until after the release has occurred. Also,
there will certainly be times when measured readings exceed the allowable limit, and where no
visible emissions were witnessed. The AHERA is appropriate because, since the 70 structures per
mm is actually based on the statistical LOD of the TEM method, an adequate safety factor is
introduced. Also, a PCM-equivalent site analysis is required by the QAPP that can be used to
compare with health-based standards (if detectable asbestos concentrations are ever detected.)
Sierra Club
The method is unclear as to the amount of material that can be left in the structure, and the level
that triggers the need to remove materials prior to demolition. The big concern is the wetting
procedures, because they aren't planning on removing the ACM before demolition. Asbestos may
migrate during the demolition. How you can wet the outside of a building and get the ACM
adequately wet. Do not see how the method was going to get the interior duct work wet. Also, I
didn't see any methods for public safety, including required fencing, warning signs, barricades, etc.
This is considered site preparation, and it was not included in the method. There should be
procedures for how the site will be managed when the crew is not working, such as overnight and
over weekends, etc. Finally, with regards to friable and Class II materials, there are concerns with
the use of heavy machinery during demolition.
How will they keep materials wet during the off hours. With regards to the heavy equipment used
during the demolition, there was no mention of wipe sampling or cleaning protocols for that
machinery. Asbestos gets everywhere, and can easily go into the machinery block, air filter, etc.,
and it is possible that maintenance workers could be exposed if equipment decontamination is not
specified. Will they be inside wetting, or just outside, and how they know if thoroughly wet if not
checking inside the wall covering.
Once soil is contaminated, it is very expensive to get asbestos out of it. Once rubble is on the
ground, it is very difficult to segregate the material. It is going to have to be kept wet, excavated
down to the soil, and then hauled to an Asbestos landfill. Further, certain types of asbestos, such as
amosite, does not wet well, so this could pose an additional problem.
The method should be assessed on a site-by-site basis, and not generalized across all buildings.
The data from the Amanda Avenue site (pre-Phase I test) demonstrated a several-fold difference
between the upwind and downwind levels, and the results to support the method do not identify the
types of ACM that are on the site. This exposure indicates that the method is not doing a very good
job of containing the asbestos. Also, since this was included in the proposal, one would assume
that the method most likely had worse results/data that were not included. Either Ft. Worth is not
wetting the structure sufficiently, or that there are flaws in the overall process.
While the Quality Assurance/Quality Controls (QAQC) are elaborate, nowhere in the QAPP were
there specific amounts that stated a pass-fail level. This is important. Also, while the QAPP
covered EPA requirements, it did not cover the OSHA requirements very well. There was no
provision for down-stream asbestos sampling for surface and storm-water runoff. They
recommended that the method explicitly state the number of monitors, and where they will be
placed both upwind and downwind. Unless the tests uses a statistically significant number of
monitors to capture asbestos during demolition, there is no way to determine if the test has
identified the "worse-case scenario" of asbestos release. Air monitoring needed to be done every
time that the method was performed, and should not be exempted on days where it expected to rain.
While these documents address asbestos issues, it should also have a general paragraph or two that
required the identification of other hazards, such as mercury ballasts from fluorescent lights,
Leaking Underground Storage Tanks, and lead paint.
Page 40

-------
Worker Protection Issues

Agency for Toxic
Substances and Disease
Registry
There did not seem to be sufficient "worker education" information. There should be
information regarding the type and amount of training necessary in order to do the Fort Worth
Method.
International Union of
Heat and Frost
Insulators and Asbestos
Workers
The use of the bulldozers/heavy equipment increases the likelihood of releases that could
impact the machinery operators, and we do not believe that worker's safety is sufficiently
addressed in the method either. "Whenever you work with asbestos, you must take steps to
protect the workers and protect the environment."
OSHA Office of
Compliance
Site Preparation: With regards to all material identified in Tables A-C, there was no discussion
for establishing a "regulated area," which is required by OSHA if TSI, Surfacing materials, or
Class I asbestos work is being conducted. Further, there are no procedures for decontamination
of workers, including the provision of showers. Also, if an alternative demolition procedure is
going to be conducted, that the entity responsible for the demolition is required to retain a
project designer that will develop an alternative procedure for conducting Class I asbestos
work. The Fort Worth Method does not include these provision.
Material Assessment: It was unclear if the correct AHERA material assessment would be
conducted (in accordance with 40 CFR 763(e)). It was assumed they would conduct the
assessment in accordance with these requirements, but it was not specifically stated.
Demolition Procedures: The demolition procedures are just not clear enough, and do not
provide enough information regarding how the demolition process would be conducted. The
method needs to include the requirement for there to be a "competent person" on sight during
demolition. Also, the method was not detailed enough, "one guy could do this one way, and the
next guy could do it totally different." "To get consistency, this needs to be a lot more detailed
on how everything will get done." The method does not ensure that the OSHA required
procedures for developing an alternative work practice will be followed. Need to determine
how they will ensure that exposures will be below the OSHA PEL, including the requirement
that there be a competent person on site.
Sierra Club
The whole section on Worker's Protection is minimal, especially related to the respirator
requirements. The only Personal Protection Equipment (PPE) mentioned is a Tyvek suit, and
the method states that a respirator is optional. That shouldn't be left to the contractor to decide.
Also, PPE should include eye protection, hard hat, gloves, and safety shoes. Also, employee
training requirements were not addressed, and personal sampling was not mentioned, including
a personal sampling plan, procedures, or sampling protocols.
Page 41

-------
Page 42

-------
Appendix E
Concerns Regarding the AHERA Clearance Level
The Quality Assurance Program Plan (QAPP) for Fort Worth's Project XL uses the EPA indoor post-abatement
clearance level to determine success in outdoor asbestos abatement work. This clearance level was developed as
part of the regulations implementing the Asbestos Hazard Emergency Response Act (AHERA). Under the AHERA
regulations, there are two alternatives for clearance of interior school areas following abatement:
1.	Ten samples must be taken and analyzed using Transmission Electron Microscopy (TEM) using the
sampling and analytical protocol specified in the regulation (40 CFR 763, Appendix A to Subpart E).
Five samples are to be taken from outside the abatement area, and considered as background. Five
samples are to be taken from inside the abatement area after abatement but with protective plastic
sheeting still in place. The average of the outside samples is compared statistically using the students'
T-test. If the inside average is not larger, to a 95% confidence interval, than the outside average, the
area may be considered clean.
2.	As an alternative, so that fewer samples would be required, the inside samples could be compared to the
estimated asbestos background contamination level which analysts found in the mixed cellulose ester
(MCE) filters used when the sampling/analytical protocol was developed in the early 1980's. Three
indoor sampling/analysis results could be compared to the background contamination level - 70
structures per millimeter squared. If the average of the analysis results was less than 70 s/mm2, the
abatement could be considered complete. Appendix A (mandatory) to the AHERA regulation is a
sampling, TEM analysis, and clearance protocol for determination whether a school building area can be
re-occupied after asbestos abatement work.
40 CFR 763.90(a)(i)(3)further provides that "...An action shall be declared complete when...the average asbestos
concentration of the three blank fields described in Appendix A to the subpart is below the fiber background level,
as defined in Appendix A of this subpart, of 70 structures per square millimeter (70 s/mm2)."
In neither of these alternatives was the clearance criterion based on health considerations. EPA chose to allow
these alternatives because the policy toward all carcinogens was, and is, that there is no safe level of exposure to a
known human carcinogen, and the only permissible approach toward a carcinogen must be to minimize exposure to
the lowest level possible. In the one alternative, this meant background air levels in a clean area; in the other, it
meant the background contamination level of the analytical filter commonly in use. Thus, the AHERA clearance
criterion was an economically expedient alternative which, if followed carefully, could ensure the lowest asbestos
air levels then measurable using the AHERA analysis protocol. As a result, the AHERA criterion is not health-
based.
Further, with respect to the differences discussed above, research conducted on sampling performed for the World
Trade Center explosions indicates that the background asbestos contamination level now expected for MCE filters
used in TEM sampling is 15-20 s/mm2. In addition, an earlier draft of the Project XL QAPP, (August 17, 2000)
which utilized an ISO analytical method (ISO 10312:1995, Ambient Air - Determination of Asbestos Fibers -
Direct Transfer TEM Method), calls for a quality control level of 10 structures/mm2 for filter media (section
B.5.2.1). If the original AHERA criterion were again used to select the clearance level, the AHERA clearance level
would now be 10-20 s/mm2. The AHERA regulation has not, however, changed along with this technological
improvement.
Page 43

-------
Page 44

-------
Appendix F
Revised Fort Worth Method
[September 23, 2003 Version]
1. Declaration of Substandard Structure
a.	The City of Fort Worth Minimum Building Standards Code (MBSC)1 establishes the minimum
standards for the continued use and occupancy of all types of buildings and structures within the City of
Fort Worth, regardless of the date of their construction, in order to safeguard the public health, safety
and welfare and to protect property. When a structure does not meet these standards, the City's
Department of Code Compliance is tasked with enforcing the MBSC and requiring the owner to bring
the structure into compliance or to demolish it. When the owner fails to comply, the City has two routes
by which it can require that action be taken:
1.	an administrative hearing before the Fort Worth Building Standards Commission, pursuant to
Chapter 7, Article IV, of the Fort Worth City Code, to order the owner to bring the structure
into compliance with the MBSC or demolish it;
2.	or a civil suit, pursuant to Texas Local Government Code Chapter 54, subchapter B2, for a
mandatory injunction to compel the structure's demolition or repair.
b.	When the owner fails to bring the structure into compliance with the MBSC or to demolish it, despite an
administrative order or mandatory injunction, the City itself may opt to demolish it.
c.	In some instances, the City may have taken possession of the facility through property tax foreclosure,
subsequent to the administrative or judicial order. The City must then acquire the approval of the other
local taxing entities prior to demolishing the structure. These include Tarrant County, Tarrant County
College, Tarrant County Hospital District, Tarrant Regional Water District, and the various independent
school districts located within Fort Worth.
2. Asbestos Assessment and Removal
a.	Once the decision has been made that the City will proceed with the demolition of a structure, the City
will contract for a thorough asbestos assessment of the facility, conducted by an asbestos inspector3 with
Environmental Protection Agency accreditation and a Texas Department of Health (TDH) license. The
City will obtain an administrative search warrant to gain access to the site for purposes of the
assessment.4 The asbestos inspector will prepare a written report of the findings.
b.	The assessment will identify asbestos-containing building materials (ACBM) and their location within
the facility in accordance with the requirements of the
Reference to Appendix A of the new method.
Reference to Appendix B of the new method.
325 Texas Administrative Code §295.50
4Texas Code of Criminal Procedure, Article 18.05
Page 45

-------
Asbestos Hazard Emergency Response Act (AHERA), 15 USC §§2641 et seq.
Asbestos School Hazard Abatement Reauthorization Act (ASHARA), 20 USC §§4011 et seq., and
the
Texas Asbestos Health Protection Act (TAHPA), Texas Occupations Code, Chapter 1954.
c. The assessment report will be written by the asbestos inspector and reviewed for completeness and
quality by a TDH-licensed asbestos management planner5 or asbestos consultant.6
3. Worker protection
While performing demolitions under the Fort Worth Method, worker protection measures will be handled as
follows:
a.	By contract, the City will require its demolition contractors:
1.	to comply with all applicable Occupational Safety and Health Administration (OSHA) regulations
for worker protection including but not limited to 29 CFR 1910 and 29 CFR 1926; and
2.	to comply with the National Emission Standard for Hazardous Air Pollutants for Asbestos
(Asbestos NESHAP) by providing a NESHAP-trained individual to oversee the demolition
process.
b.	During Phase 2 of the City of Fort Worth Project XL project, the City will separately contract with a
TDH-licensed asbestos consultant to provide third-party oversight of the demolition process. The
consultant will have a certified industrial hygienist (CIH) on staff that will actively participate in the
development of the Quality Assurance Project Plan (QAPP), work methods, etc. This third-party
oversight will not be required following a determination by the EPA that the Fort Worth Method is
equivalent, for the purpose of proceeding to Phase 3.
4. Demolition Method
a. There are five (5) categories of substandard structures the City of Fort Worth encounters when pursuing
nuisance abatement:
Category 1. Structure that does not meet the definition of facility under the Asbestos NESHAP.
Category 2. Structure that meets the definition of facility under the Asbestos NESHAP, but that
contains no asbestos-containing materials (ACM);
Category 3. Structure that meets the definition of facility under the Asbestos NESHAP, and that
contains ACM but does NOT exceed the NESHAP thresholds:
(Regulated asbestos containing material (RACM) is less than 260 linear feet on pipes,
160 square feet on other facility components, or 35 cubic feet offacility components
where the length and area could not be measured previously.)
S25 Texas Administrative Code, §295.51
6Ibid, §295.47
Page 46

-------
Category 4. Structure that meets the definition of facility under the Asbestos NESHAP, that is
being demolished under an order of a state or local governmental Agency, issued
because the building is structurally unsound and in danger of imminent collapse (and
thus can be demolished with RACM in situ pursuant to the Asbestos NESHAP); and
Category 5. Structure that meets the definition of facility under the Asbestos NESHAP, and that
contains RACM above the Asbestos NESHAP threshold. The Fort Worth Method
applies only to Category 5 structures, with the limitations stated herein.
If the asbestos assessment report for a Category 5 structure identifies RACM above the Asbestos
NESHAP thresholds in the form of spray-on fireproofing (SOF) or thermal system insulation (TSI) in
any structure, the City will then request the preparation of removal specifications for the SOF and TSI.
SOF and TSI above the Asbestos NESHAP threshold will be completely removed prior to demolition, in
accordance with state and federal law by a TDH-licensed asbestos abatement contractor7. RACM other
than SOF or TSI will remain in situ during the demolition. The Fort Worth Method demolition will then
proceed as if the structure meets the Asbestos NESHAP definition of structurally unsound and in danger
of imminent collapse.
In addition to the standard requirements of the Asbestos NESHAP, the following criteria will be applied
to the Fort Worth Method:
1.	The Fort Worth Method will be used to demolish structures ranging from one-to-three stories
only.
2.	Facilities will be demolished one structure at a time.7
3.	Demolition contractors will have daily safety meetings prior to work commencement to ensure
safe demolition of the structure (s).
4.	During demolition, loading, and disposal the demolition debris will be maintained adequately wet
as defined by the Asbestos NESHAP.8
5.	Demolitions will be performed by heavy equipment only. No explosives will be used to explode
or implode structures, and burning will not be utilized to demolish structures.
A.	Heavy equipment. Typically, one or more bulldozers will be used to demolish single-story
buildings, and a combination of bulldozers and track-hoes will be used to demolish
multi-story buildings (not to exceed three-stories).
B.	Wetting. A structure will be thoroughly and adequately wetted with water using a variable
rate nozzle prior to demolition, during demolition, and during debris loading. Direct
high-pressure water impact to the RACM will be prohibited. The variable rate nozzle will
be capable of delivering water ranging from a mist to a concentrated stream. The demolition
debris will be kept adequately wet at all times, including during handling and loading into
containers for transport to a licensed disposal site. During the Phase 2 demolitions, a water
Id, §295.45 Fort Worth Method Revised 9-23-2003 Page 6.
40 CFR §61.141 states: "adequately wet means sufficiently mix or penetrate with liquid to prevent the release
of particulates. If visible emissions are observed coming from asbestos- containing material, then that
material has not been adequately wetted. However, the absence of visible emissions is not sufficient evidence
of being adequately wet." Fort Worth Method Revised 9-23-2003 Page 7.
Page 47

-------
meter (or equivalent device) will be installed at the water hydrant to measure the volume of
water used during demolition of the structure.
C.	Collapsing structure inward. The majority of the walls and interior components will be
leveled on top of the building foundation, and debris will be loaded prior to removal of the
concrete slab if present.
D.	Handling of demolition debris.
i.	When portions of a structure that do NOT contain RACM can be segregated so that
they can safely be demolished without disturbing the area(s) of the structure that
contain(s) RACM, these portions will be demolished to allow the debris to be
disposed at a proper landfill as non-RACM debris. The area(s) of the structure
containing RACM will be demolished and the associated debris disposed as regulated
asbestos- containing waste. Segregation will only be used when practical (e.g., a
warehouse building that is approximately 5,000 square feet in size and contains
RACM in the office area that consists of approximately 1,000 square feet then the
4,000 square feet of open warehouse and NON-RACM will be segregated to the
extent practicable to ensure RACM is properly disposed).
ii.	When portions of a structure that do NOT contain RACM cannot be segregated as in
4.c.5.D.i. above, they will be demolished in a manner (where possible) to allow the
NON-ACM to help contain the RACM during the demolition (e.g., non-ACM allowed
to buffer the RACM from ambient air during demolition and subsequent loading). All
demolition debris will be disposed as regulated asbestos-containing waste.
E.	Grading. The site will be graded for future use following completion of the demolition.
d. Other than adequately wetting the demolition materials, no engineering controls will be in place during
the demolition.
5. Storm Water Protection
a.	Demolition projects typically have a minimal to no amount of runoff depending on the site location and
site conditions.
b.	Asbestos has not been identified as a priority or secondary pollutant in storm water runoff within Fort
Worth, and the City expects minimal-to-no asbestos impact on runoff from any demolition site. The
USEPA relevant standards for asbestos are:
1.	Drinking Water Standard: 7 million fibers/liter (40 CFR 141.23 (a)(4)(i)); and
2.	Reportable Quantity: One pound (40 CFR 302.4 (a) Table 302.4).
c.	Construction site best management practices will be used to control runoff to the maximum extent
practicable. Runoff from a job site will be controlled using a combination of natural drainage, manmade
drainage channels, and silt fencing as applicable.
d.	For large construction sites (five acres or greater) and small construction sites (one acre or more, but
less than five acres), all applicable federal and state regulations pertaining to storm water discharges
from construction sites will be followed. This includes the development and implementation of a storm
Page 48

-------
water pollution prevention plan (SWPPP) and the submittal of a Notice of Intent (NOI) to the Texas
Commission for Environmental Quality (TCEQ) (for large sites) or the posting of a site notice (for small
sites).
6.	Air Monitoring
During the process of showing the Fort Worth Method to be equivalent to the Asbestos NESHAP, air
monitoring will be conducted in compliance with the applicable Quality Assurance Project Plan and the Final
Project Agreement. No air monitoring will be performed during Fort Worth Method demolitions following
the determination of equivalency under Phase 2. Fort Worth Method demolitions will follow the Asbestos
NESHAP for structures that are structurally unsound and in danger of imminent collapse.
7.	Disposal
a.	As stated above in Section 4.C.D., segregation techniques will be used during demolition in an effort to
reduce the amount of RACM debris. A NESHAP-trained individual will be required on-site to monitor
the demolition process as well as the handling of the waste.
b.	Demolition debris will be kept adequately wet during loading and transporting to a waste disposal site.
c.	Demolition debris will be loaded into end-dump trailers using heavy equipment. Typically, the
contractor will use construction trailers capable of holding 20 cubic yards of waste material.
d.	End-dump trailers used to transport regulated asbestos-containing waste material to a licensed landfill
will be covered with a tarp, and will be clearly marked during loading and unloading of waste.
Transportation will be immediate and by a direct route.
e.	Disposal will be in accordance with all federal, state and local requirements. A contractor will be
allowed to decide which licensed landfill is a viable option.
f.	The City will retain a copy of all waste shipment records, including a copy of the waste shipment record
signed by the owner or operator of the designated waste disposal site, for a minimum of two years.
8.	Decontamination
a.	Care will be taken to reduce the potential contamination of other job sites by equipment. Heavy
equipment involved in the handling of regulated asbestos-containing material may be decontaminated
by:
1.	Thoroughly rinsing the equipment components that come in contact with the regulated asbestos-
containing material. On-site water supply (e.g., fire hose) will be utilized; and
2.	Rinse water will be controlled on-site and allowed to naturally evaporate or be absorbed into the
ground. Disposable equipment will be disposed as part of the regulated asbestos-containing
material.
b.	End-dump trailers utilized to transport regulated asbestos-containing material will be cleaned as in 8.a.
above, or lined with a disposable liner that will be disposed along with the final load at the licensed
landfill.
Page 49

-------
c. By contract, the demolition contractor will be required to comply with all applicable OSHA regulations
that may include the use of personal protective equipment (PPE) such as Tyvek suits or equivalent,
respirators (as necessary), and gloves (as necessary). All disposable PPE will be disposed as regulated
asbestos-containing material.
Page 50

-------
Appendix G
Analysis of the Revised Fort Worth Method
City of Fort Worth Officials met with Agency officials on September 29, 2003 and provided
additional documentation, including a revised method dated September 23, 2003. The revised
method provides more details in some areas. However, in some cases, these additional details
raise further concerns. We believe this revised method is still not equivalent to the NESHAP,
and portions of the revised method may be less protective than the previous. Also, a
determination of equivalency utilizing the results of the Phase II test only is not scientifically
sound because one demolition would not be representative and the various types of buildings to
be demolished, and the types of RACM and weather conditions that could be encountered.
Table H.l below provides a comparison of the May 23, 2002 and September 23, 2003 versions
of the Fort Worth Method.
Table H.1: Comparison of the Revised Fort Worth Method.
Comparison of Revise
'd Fort Worth Method
Fort Worth Method
May 23, 2002 version
The method indicated that it would remove spray-
on fireproofing and thermal system insulation, but
did not define what specific materials would fall
into these categories.
Fort Worth Method
September 23, 2003 version
The revised method still does not specifically
define what materials will be included in the spray-
on fireproofing and thermal system insulation
categories.
The method was unclear as to what air monitoring
processes would be used during the 30-50 Phase
III demolitions that would be conducted after the
Phase II demolition was completed.
No air monitoring is planned after Phase II.
The method did not include an independent, third
party observer that would monitor the demolition
and disposal of asbestos-containing materials and
demolition debris.
The revised method specifically states that an
independent, third party observer would only be
used to verily the Phase II demolition, and would
not be used in the Phase III demolitions that would
occur afterwards. Therefore, there may be a
conflict of interest issue because the method does
not require a qualified independent observer to
monitor demolition activities after the completion
of Phase II.
The method did not adequately define or describe
how RACM would be adequately wetted, or what
testing would be conducted to determine if RACM
left in the structure was adequately wetted during
the demolition.
The revised method did not change or modify the
wetting processes that will be used during
demolition.
Page 51

-------
The method did not include an immediately
enforceable stopping point, but rather relied on the
results of air monitoring to determine if asbestos
fibers had been released.
The revised method still does not include an
immediately enforceable stopping point, and
specifically indicates that after Phase II, even air
monitoring will be discontinued. Further, specific
air monitoring procedures to be conducted under
Phase II are still to be determined and therefore
cannot be evaluated at this time.
The method was unclear regarding the criteria that
would be used to determine if a structure would be
demolished using the Fort Worth Method.
The revised method provides specific criteria for
determining if a structure can be demolished using
the Fort Worth Method, and that criteria is much
less stringent than the requirements necessary to
meet the Imminent Hazard exemption of the
NESHAP.
While the revised method states that, "The Fort Wort demolitions will follow the Asbestos
NESHAP for structures that are structurally unsound and in danger of imminent collapse,"
the method contradicts this statement by including items that are less stringent than the
structurally unsound exemption. For example, the imminent hazard exemption under the
NESHAP includes the requirement that no visible emissions be allowed from the section of
the building where RACM was contained, however, this requirement is not mentioned in
the revised Fort Worth method. Therefore it is unclear what does and does not apply.
We also requested that key officials from OECA and OAQPS, who are both familiar with
the Asbestos NESHAP and this project, provide us with their views of the revised Fort
Worth Method. The OECA representatives response include the following concerns:
•	"... this process cannot comply with the no visible emission standard.
•	"Phase 2 is insufficient to determine equivalency especially to other types of
construction and other types of ACM or the same types of ACM with significantly
different concentrations of asbestos. "
•	"This one test will not be sufficient to allow the demolition of additional structures
of different construction. They expect to extrapolate the results of Phase 2 beyond
that which is prudent. "
•	"In my opinion the QAPP and monitoring proposal is fatally flawed and cannot
give us the accuracy and precision needed to make the [equivalency] determination
required by the CAA statute. "
•	"This project will not achieve superior environmental results, it may just be
cheaper."
•	"...the revised method does not meet the intent of Project XL, because these project
are supposed to be 'a model of how EPA should work with all environmental
stakeholders."This Method discriminates against the private sector so it does not
reach the XL goal of 'all stakeholders'. "
Page 52

-------
We agree with OECA's concern that a single test will not be sufficient to make a
determination of equivalency. Based on the recent revision, the Fort Worth method will
only be tested in one side by side comparison at one specific demolition site, and then the
city will request that an equivalency determination be issued by the Agency. If this version
of the proposal is approved, and an equivalency determination is issued by the Agency, a
method that is deemed successful in one individual instance will be allowed to be used for
other demolitions throughout the City of Fort Worth. However, one individual test is not
adequate to determine the success or failure of a new demolition method. One data point
(demolition), without comparison to any other similar data points within a controlled
sample, will not provide a statistically significant pool of data that will allow the Agency to
make an equivalency determination that utilizes sound scientific principals. While opinions
vary within the field of statistics as to what comprises a sufficient sample size necessary to
develop a statistically significant level of confidence, it is statistically impossible to predict
future success from one single data point, because there are not other points of comparison.
Further compounding the test of this method is the overall number of unique or
independent variables that are likely to be encountered during different demolitions. Under
typical scientific methods, the researcher attempts to isolate one specific independent
variable within a pre-determined number of samples, and then attempts to compare the
occurrence of that one specific variable to determine if those results can be generalized with
statistically significant confidence across a larger population. However, in the case of the
Fort Worth proposal, the Phase III demolitions will include different types of buildings,
with different types and volumes of asbestos-containing materials, under different types of
conditions (temperature, wind speed, precipitation, etc.).
More specifically, in the September 29, 2003 meeting with EPA, city officials provided a
briefing document that lists the types of buildings that they plan to demolish. This list
includes bowling alleys, bars, taverns, grocery stores, automotive service stations/stores,
churches and shopping malls. However, Fort Worth proposes to test the method only once,
on one specific type of structure (an abandoned hotel), and will then attempt to use the
results of that one test to predict the outcome of using this method on other structures. We
do not believe that one test will provide sufficient data to accurately predict the outcome of
other demolitions when using this method. The method must be tested on a sufficiently
sized sample of similar structures in order to scientifically demonstrate its validity. One
single test will not provide a comparable or statistically significant data set necessary to
determine if the success or failure of the Phase II demolition can predict the success or
failure of any other future demolition where the Fort Worth method is used.
Page 53

-------
Page 54

-------
Appendix H
Five Attributes of Environmental Data Quality
According to EPA's data quality objectives order (Order 5360.1), five attributes of data should be known
before the data is used for regulatory decisions. These are described below.
Attribute
Definition
Precision
; Precision is the average amount of variability experienced in measuring emissions;
it is sometimes expressed as a relative standard deviation, such as plus or minus
15 percent. The lower the percentage, the more precise the data.
Accuracy
: Accuracy refers to the amount of bias that a measurement may have. For example,
an improperly calibrated piece of testing equipment may bias a reading.
Completeness
Completeness refers to the number of readings that must be taken before a
confident judgment can be made. For example, if 4 of 5 readings yield the same
information, decision makers may say that a reliable profile of the facility's emissions
exists.
Representativeness
• Representativeness involves a qualitative assessment as to whether a reading fairly
represents the emissions from a facility. Factors that could affect representativeness
include the methods used and weather conditions at the time the readings were
taken.
Comparability
; Comparability is the ability to fairly compare emissions results from the same facility
at different times. Using different sampling and testing equipment, or different
methodologies, could result in an inability to make such comparisons.
Page 55

-------
Page 56

-------
Appendix I
EPA Response to Draft Report
December 2, 2003
MEMORANDUM
SUBJECT: Comments on Draft Evaluation Report: Significant Modifications Needed To
Ensure Success of Fort Worth Asbestos Demolition Method
Assignment No. 2002-000654
FROM: Richard E. Greene /s/
Regional Administrator Region 6
Jeffrey R. Holmstead /s/
Assistant Administrator for Air and Radiation 6101A
John P. Suarez /s/
Assistant Administrator for Enforcement
and Compliance Assurance 2201A
J. Paul Gilman, Ph.D. /s/
Assistant Administrator for Research
and Development 8101R
Jessica L. Furey /s/
Associate Administrator for Policy, Economics,
and Innovation 1101A
TO:	Nikki L. Tinsley, Inspector General
Office of Inspector General 2410T
Thank you for the opportunity to review and comment on the Office of Inspector General's
Draft Evaluation Report "Significant Modifications Needed to Ensure Success of Fort Worth
Asbestos Demolition Method". Both Fort Worth and the Agency are committed to an open and
transparent process that provides an opportunity for public comment and peer review and we
welcome your comments on the project.
Your comments raise some legitimate questions, many of which we believe the City and
the Agency are discussing or have resolved, for example, incorporating comprehensive
monitoring into our plan as well as a strong peer review process. Along those lines, we wanted to
raise two points with regard to your draft report: the tone, which seems unnecessarily negative,
and the nature of phase 2, which is merely a test and not a broad authorization of a method.
Page 57

-------
Nature of Phase 2
The draft report also does not appear to recognize that we are still at an early stage
of this project. Any concerns regarding broad use of the alternate method seem
premature. We have completed a preliminary Phase I test on a structure that is not within
regulatory jurisdiction, and on the basis of that test, have merely decided to proceed with a
second test on a building that is subject to the NESHAP regulation. It is, however, simply a test.
If that test fails, then the method must be changed or abandoned. No broadly applicable change
will occur unless and until the tests prove to be successful, and the Agency has gone through a
regulatory process with full public comment.
The prospect of the new method proving to be successful is an important one, however,
since Mayors around the country have been unable to address all of the delapidated and dangerous
buildings in their communities due to cost constraints associated with the traditional NESHAP
method. If the alternative method proves to be equally effective and protective, it can be carried
out at far lower cost, thereby enabling cities to rid more communities of buildings needing
demolition, buildings which far too often have become homes to drug dealers or that simply pose
dangers to children as attractive nuisances. We are endeavoring to carry out these tests in a
scientifically sound manner so that we make the best decisions we can, and many of your
comments are helpful in that process.
Negative Tone of OIG Report
The OIG report seems to have an unnecessarily negative tone. We are concerned
that negative comments were included in the draft report and were emphasized, while
positive comments were not provided. There were numerous positive and meritorious
comments made by the XL partners that were not included in the OIG draft report. For
example, ORD provided comments on Phase I regarding the potential utility of a more economical
demolition technique, assuming equal environmental protection. Also, Region 6 commented on
the urgency of demolishing many buildings that were being used for drug houses and crime
centers, etc. The end result of omitting potentially balanced, positive comments leaves the draft
report reader with a somewhat slanted and unnecessarily negative impression.
Similarly, several major OIG draft report concerns (e.g., peer review, committing EPA
staff to work with Fort Worth to better document the method, etc.) have already been addressed by
the Innovative Action Council (IAC). These major concerns received strong OIG criticism in the
beginning of the draft report, including the Executive Summary. However, not until page 24 does
the OIG acknowledge that these issues are being addressed. Also, there is severe criticism of the
Phase I site for not being a NESHAP class structure and for not doing side by side comparisons,
when the XL team was prohibited from conducting the first test on NESHAP structures. The
structure used in the Phase 1 test was expressly chosen because it was not a NESHAP-regulated
structure.
We would encourage you to examine the content of the report, as well as the tone.
See Appendix J
Note 1
See Appendix J
Note 2
Page 58

-------
Next Steps
As you know, your staff reviewed and commented on the beginning phases of a
multi-year project that is continuing to evolve. Fort Worth and the Agency have not
reached agreement on the methodologies and processes for Phase II of the project and
discussions are ongoing. We hope to reach agreement by January 30, 2004, in order to
submit the documents for peer review and public comment.
Since many of the documents your staff reviewed were under development, changes have
been made to the documents which render many of the reports, observations, and comments out of
date. However, in an effort to provide useful responses for your final report, we have referenced
the updated documents, where appropriate, and note that many of the documents are still under
discussion.
Please find attached EPA's coordinated comments to the Draft Report and to the Inspector
General's Recommendations. If you have any questions, please contact David Bond
(214) 665-6431.
Attachment(s)
See Appendix J
Note 3
Page 59

-------
Comments on the Office of Inspector General Draft Evaluation Report
"Significant Modifications Needed to Ensure Success of Fort Worth Asbestos Demolition
Method" (Assignment No. 2002-000654, dated October 17, 2003)
Executive Summary
Page i	Statement: The City has proposed a three-phased approach to obtaining EPA's
approval of the Fort Worth Method. Phase I testing of the proposed Method
occurred in 2001 on a small building that did not possess enough RACM to be
regulated by the asbestos NESHAP. Phase II testing is planned for a large,
abandoned hotel that contains enough RACM to be regulated by the asbestos
NESHAP.
Response 1: There appears to be a common misunderstanding throughout the
report with respect to the structure selected for the Phase I test. The
structure selected for the Phase I test was specifically selected because
it did not trigger NESHAP regulations; that allowed for an early,
small scale test without the need for regulatory exemptions. EPA required
that Phase I be added to the proposal submitted by Fort Worth, that the
structure MUST NOT trigger NESHAP regulations, and that sufficient
asbestos be in the structure to meet evaluation criteria. The structure that
was selected contained 3438 sq ft of surfacing materials containing 2-percent
chrysotile, a sufficient amount to meet evaluation criteria. If the Phase I test
had failed the evaluation criteria, the project would have ended. Because it
was successful, the Agency now plans to proceed with a second test on a
building that would trigger NESHAP regulations.
Page ii	Recommendation: EPA assist Fort Worth in modifying the Fort Worth Method to
produce a single, finalized technical specification document that fully describes the
Fort Worth Method, including the demolition strategy and associated Quality
Assurance Project Plan (QAPP), and that this proposal be externally peer-reviewed
prior to testing.
We recommend that EPA work with the City of Fort Worth to develop a Final
Project Agreement that adequately addresses key project XL Criteria for the entire
proposed project (Phase II and Phase III), and that EPA ensure that Project XL
team concerns are adequately addressed.
We recommend that EPA develops comprehensive Agency guidance for
conducting oversight of these proposed projects. We recommend that EPA assist
the City of Fort Worth in designing a demonstration project that can be used to
reach complete, reliable, and valid conclusions, and that EPA works with the City
to ensure that the structures chosen for the Phase II demolition contain sufficient
asbestos to provide representative test results. We also recommend that EPA
develop and propose Federal rules and regulations for handling Innovation
proposals, including the opportunity for public notice and comment.
See Appendix J
Note 4
Page 60

-------
Response 2: EPA concurs with the majority of the recommendations. The XL
criteria were considered in our decision to undertake at least a
preliminary phase of the Fort Worth's proposed project (Phase 1).
We will continue to employ criteria such as these as we move forward
to design and implement Phase 2. We will insure that there is a robust
stakeholder process, and an appropriate legal mechanism for this phase of the
project. EPA has already determined that a prerequisite for going forward
with the Phase 2 test includes having the Method and the QAPP peer-
reviewed. In addition EPA will work with the city on a project agreement
that addresses the appropriate criteria. (Note: These recommendations and
EPA response are set out in more detail in Chapters 2, 3 and 4.)
See Appendix J
Note 5
Pg ii
Response 3:
Pg iii
Response 4:
Statement: Although initially proposed in September 1999, the Fort Worth
Method does not yet meet EPA's Project XL criteria of superior environmental
performance, appropriate regulatory flexibility, adequate stakeholder involvement,
or transferability.
The Agency does not agree with this statement. See response 18, 20
and 23.
Statement: Given the number of variables involved, it is questionable
whether a single test - as described in the latest proposal - is adequate to
statistically determine the success or failure of a new demolition method in
accordance with sound scientific principles.
EPA agrees with the IG on this assessment and has begun discussions for
additional tests with the City.
See Appendix J
Note 6
Main Report
Chapter One - Introduction
Pgs 1 & 5 Statement: This proposal was introduced under Project XL, other cities may use
the data generated by this project to justify similar demolitions. Some have already
requested information related to this project.
Response 5: We disagree with this statement. There has been no change to
NESHAP that would allow another city to use the Ft. Worth method.
The project is a test to help determine whether a later change to the
NESHAP may be viable; if the test is unsuccessful, there will be no
basis for a later change to the NESHAP that could be used by many cities.
Both Fort Worth and EPA want the pilot process to be open, therefore as the
pilot proceeds other cities may request information. The test is of broad
interest because if it is successful in showing an equivalently protective
method at much lower cost, it has the potential to help many cities demolish
dangerous, abandoned buildings.
See Appendix J
Note 7
Page 61

-------
Pg 3
Statement: Appendix A provides a detailed description of the Fort Worth Method.
Response 6: Appendix A has been superseded. The latest version submitted by the
City was given to a representative of the IG's office at a September 29,
2003, meeting.
See Appendix J
Note 8
Pages 4 & 9 Statement: In order to obtain external perspectives of the proposed Fort
Worth Method, we also interviewed 15 external stakeholder groups from industry
associations, environmental groups, academic organizations, and other Federal
Agencies. We selected these groups based on information identified during our
research, and with input from EPA and the City of Fort Worth. Details on the
scope and methodology, and selection of external stakeholder groups are included
in Appendix C.
Response 7: EPA is unable to respond to this statement based on the fact that we
are uncertain what the interviewees were given to review for the
purposes of the interviews. The report should include the document(s)
that were provided to the stakeholders, for their review, so that
everyone who reads the report will be able to know what is being commented
on.
See Appendix J
Note 9
Page 6	Statement: Our evaluation of the Fort Worth Method document indicates that, as
currently written, neither EPA, project officials, nor the public would have a clear
understanding of the method prior to its implementation, and may have difficulty
replicating this method at other locations. For example, it is unclear:
(Bullets not at issue removed from for this document)
How these materials would be tested for RACM;
What instrumentation would be used for testing different RACM;
What detection limits would be used in testing these materials;
Response 8: EPA does not agree with the statements, concerning testing. There
appears to be a misunderstanding concerning elements of the Ft.
Worth Method. The Fort Worth Method is an alternative demolition
work practice and does not propose changing RACM testing
requirements. The RACM will be tested as stated in the NESHAP (i.e.,
40 CFR part 763 subpart E Appendix E). EPA will work with the city to
clarify this point in subsequent versions of the method.
See Appendix J
Note 10

Page 7	Statement: "Another important unaddressed factor is that the Fort Worth Method
does not provide for an immediately enforceable stopping point... . With the
various NESHAP methods, the "no visible emissions" work practice standard
allows for a demolition to be stopped if visible emissions are identified. However,
the Fort Worth Method does not utilize a work practice standard, but rather
depends on the analysis of air monitoring samples, which take several days to
analyze."
Page 62

-------
Response 9: EPA does not agree with this statement. The Fort Worth Method is
indeed a work practice, as is the NESHAP method. The Fort Worth
Method addresses the same activities as does the NESHAP, including:
asbestos assessment prior to demolition, adequate wetting, demolition
process, waste and water handling, and waste disposal. The air
sampling protocol (which is embodied in the QAPP) is not an intrinsic part of
the Fort Worth Method. We are conducting air sampling (and water and soil
sampling) solely as a means of measuring the effectiveness of the City's
method against the NESHAP method. As part of the Phase 2 test, we will be
monitoring air emissions during the demolition of a building by the NESHAP
method, as well as during a demolition by the Fort Worth Method. In
addition, the Fort Worth Method does include the no visible emissions
requirement - and any demolition would be stopped if visible emissions are
identified.
See Appendix J
Note 11
Page 8	Statement: Table 2.1 Comparison of Fort Worth Method to NESHAP
Requirements
Response 10: EPA does not agree with this table. For example, on the row labeled gee Appendix J
"Adequately wet RACM during demolition" appears a "No" for the ^ote ^
Fort Worth Method. The "No" should be "Yes." As stated		
previously, the Fort Worth Method contains the same requirement to
adequately wet RACM as does the NESHAP. On the row labeled "Discharge
No Visible Emissions" another "No" appears for the Fort Worth Method.
This also should be "Yes," since the Fort Worth Method includes this
requirement (see Table - 1 in Fort Worth's proposal document). Next, on the
row labeled "Immediately Enforceable Stopping Point," the "No" for the
Fort Worth Method should be a "Yes", since, like the NESHAP method, the
Fort Worth method would stop demolition if visible emissions were identified.
Finally, the entry on the row labeled "Not dependent on Air Monitoring
Results" should be a "Yes" instead of "No." As discussed above, the Fort
Worth Method is a demolition work practice. Air monitoring is not a feature
of the Method, but a means of demonstrating whether the Method is
equivalent to the Asbestos NESHAP.
Page 10 Recommendation: Table 2.2: Materials that should be Addressed in the Proposed
Fort Worth Method.
Response 11: EPA agrees with the recommendations on identifying the types of asbestos in
this table. The suggestions are quite helpful and will be of assistance in
further defining the method.
Pages 10 & 11 Statement
Several stakeholders we contacted suggested that the air monitoring standard
proposed in the Fort Worth Method (the 70 s/mm2 Asbestos Hazard and
Page 63

-------
Emergency Response Act (AHERA) clearance criterion) is not appropriate for use
in ambient air monitoring around a demolition site because:
It is not health-based;
The original reason for its development - that it represented an average
background contamination level on asbestos testing filters - is no longer
correct; and,
The criterion is an indoor air, post-abatement clearance level that is used by
EPA to determine the success of asbestos abatement work conducted under
full containment.
More than half of the external stakeholders (8 of 15) we interviewed did not
believe that the AHERA standard was the appropriate measurement for this
Method. One stakeholder commented that the AHERA standard was only intended
to be used as an indoor clearance procedure after asbestos removal had been
conducted, and while containment was still in place. He stated that the air
monitoring outlined under the Fort Worth Method was not an aggressive test that
requires the use of fans and leaf blowers during containment. Another stakeholder,
who was one of the 26 people on the committee that advised EPA on the
development of the AHERA Standard, stated that, "nobody ever said that 70
structures was a safe exposure level, just that it was the lowest level measurable (at
that time) because of background contamination on the filters." Today, based on
sampling performed for the World Trade Center explosions, it has been determined
that background contamination of filters is low enough to accurately detect
asbestos fibers at about 15 s/mm2.
Response 12: EPA agrees in part with this statement. Demolitions will not be
carried out under full containment procedures. The AHERA standard
of 70 s/sq mm (drawing about 1000 liters of air) equates roughly to an
airborne concentration of about 0.015 asbestos structures/cc. The first
order for evaluation of the effectiveness of the demolition was to do a
statistical test on the upwind versus downwind concentrations to determine if
a statistically significant difference existed; if so, the process failed (assuming
that the test on the NESHAP method passed). The problem with this
approach is identical to the problem that was faced in developing the AHERA
standard, in that if the background concentrations are non-detect and
anything is measured in the downwind, the test cannot be passed (i.e., the
difference will always be significant) because of the way the statistical tests
perform the mathematical calculations. Recognizing this possibility, a second
test scenario was added and the AHERA test was chosen for convenience.
While AHERA is not a health-based standard, it is conservative and is judged
suitable by the Agency for reoccupancy of the building by children, who are
at the highest risk for asbestos-related disease. As with all the documents,
these equivalency determinations will be subject to review and possible
change during this process.
See Appendix J
Note 13
Page 64

-------
Page 11 Statement: The placement of the ambient air monitors is not adequately addressed
in the proposed method.
Response 13: EPA refers the Inspector General to the QAPP, since the placement of
the air monitors is not a part of the method document. They are a
part of the QAPP as the monitoring will only take place during the
testing of the method. In addition, the QAPP has been revised and
will be reviewed and peer reviewed and possibly revised again to strengthen
the air monitoring.
See Appendix J
Note 14
Page 11 Statement: The placement of the monitors at a particular height may not capture
all the asbestos fibers released.
Comment: For example, some stakeholders suggested that monitoring at multiple
heights and multiple distances may be needed to adequately determine whether
asbestos particles escaped the demolition area.
Response 14: EPA agrees with this comment and it has been incorporated into the draft
QAPP for the Phase 2 test. It has also been suggested some sampling be done
from monitors suspended above the demolition area. All samples are taken
with the intent that they will represent the whole population and you need to
take a sufficient number to have confidence that a subset of the population
has the same statistical tendencies that can be inferred on the population as a
whole.
Page 11 Comment: Recently, EPA officials told us they would consider having the Phase II
proposal peer reviewed prior to implementation.
Response 15: EPA agrees with the comment and based on decisions made during the
May 12, 2003, IAC meeting, peer review is now a pre-requisite to
moving forward with the Phase 2 test.
See Appendix J
Note 15
page 12 Statement: Of particular note is that Fort Worth does not plan to conduct any air
monitoring at Project XL demolitions after Phase II. OECA officials remain
concerned that a single test is insufficient to gauge project effectiveness.
Response 16: EPA agrees that air monitoring should be conducted as part of this
and any subsequent Phase 2 tests of the Fort Worth demolition
method. EPA and the City are discussing additional monitored tests
of the method as an addition to the Phase 2 test. OECA officials are
satisfied on this point.
See Appendix J
Note 16
Page 13 Recommendation: We recommend that the Assistant Administrator for Air and
Radiation, the Assistant Administrator for Enforcement and Compliance
Assurance, the Regional Administrator for Region 6, and the Associate
Administrator for Policy, Economics, and Innovation ensure that:
Page 65

-------
2-1
Agency officials assist Fort Worth in modifying the Fort Worth Method to
produce a single, finalized technical specification proposal, including the
demolition strategy and associated QAPP that:
a.	identifies and adequately describes how each type of RACM that may
be encountered during demolition will be addressed;
b.	better defines the wetting requirements;
c.	is documented in sufficient detail to allow for independent
assessment; and,
d.	is evaluated based on an appropriate air monitoring standard and
monitoring that is representative.
2-2. Agency officials assist Fort Worth in fully describing the air monitoring
that will take place, and to determine whether the air monitoring contractor
would be independent from the demolition contractor.
2-3. Agency officials require that the Fort Worth Method is adequately peer
reviewed prior to implementation.
2-4. Agency officials outline criteria that determines the volume of RACM
necessary to ensure a representative comparison to the NESHAP, and assist
the city in locating a structure that meets these criteria.
Response 17: EPA concurs with these specific recommendations. The Agency has already
specified that revising the method and QAPP, and peer review of the
documents, are pre-requisites for moving with the phase 2 test.
Agreement Lacking on Key Project XL Criteria
Page 15 Statement: Although the City of Fort Worth initially proposed this project in 1999,
four key Project XL criteria outlined in EPA's 1995 Federal Register Notice have
not been adequately addressed, including superior environmental performance,
regulatory flexibility, adequate stakeholder involvement, and transferability.
According to XL requirements, each of these criteria must be satisfactorily
demonstrated in order for an XL project to be deemed successful. The principal
reason for the delay was because a Final Project Agreement, normally written early
in an XL project, has not been developed due largely to internal Agency
disagreements about the adequacy and benefits of the Fort Worth proposal.
Response 18: EPA does not agree with this statement. See Response 2.
As stated in Response 1, EPA required that the Phase 1 test be added
to the proposal, and the slow pace of the project to date is largely a
result of the logistics involved in actually carrying out and evaluating the
Phase 1 test.
Page 66
See Appendix J
Note 17

-------
The Phase 1 test was required to give the Agency more information about the
Fort Worth Method prior to making a decision to proceed to FPA
development. No regulatory flexibility was needed to conduct Phase 1 and we
developed the processes and methods for the Phase 1 test with Fort Worth
and the Texas Department of Health. All involved Agency offices concurred
on this plan.
Superior Environmental Performance Questionable
Page 15 Statement: Based on information presented in Chapter 2, it is not clear that the
currently proposed Fort Worth Method is equivalent to the current Asbestos
NESHAP.
EPA's Project XL internal team members have yet to reach agreement on whether
the Fort Worth Method is equivalent to the Asbestos NESHAP. Both OECA and
OAQPS expressed significant concerns about the adequacy of the proposed Fort
Worth Method.
Response 19: The reason that the Agency is conducting multiple tests is precisely to See Appendix J
determine whether the Fort Worth method is equivalent to the	Note 18
NESHAP method. Successful completion of the Phase 1 test does not 	
mean that EPA thinks that the Fort Worth Method has been proven
broadly equivalent to the Asbestos NESHAP. See Responses 1 and 18. All
EPA program and legal offices involved in the project simply decided that the
criteria for success under the Phase 1 test have been met, and that the project
should proceed to a Phase 2 test with certain pre-requisites as a result of the
May 12, 2003, IAC meeting.
Page 16 Statement: Although aware that team disagreement had not been resolved, the
Reinvention Action Committee decided in January of 2000 that the Fort Worth
proposal should move forward in phases.
Response 20: EPA would like to clarify this statement. There appears to be a	§ee Appendix J
misunderstanding as to the decision making process in Project XL. If Note 19
the staff team is unable to come to agreement, it is the responsibility of 	
the Reinvention Action Council (now Innovation Action Council), not
Committee to resolve those differences and make a decision on the issues. The
opposing views of the Fort Worth XL project were presented to the RAC
(now IAC) and the decision was made to proceed in January of 2000, and
views were presented again to the IAC in May of 2003 and a decision was
made to proceed with a Phase 2 test of the Fort Worth method.
Page 16 Statement: Phase I, demolition of a building containing too little asbestos
to be regulated under the NESHAP...
Response 21: EPA disagrees with this statement. See Response 1.
See Appendix J
Note 20
Page 67

-------
Page 16 Statement: One of these stakeholders stated,
"It is likely that asbestos emissions could be missed by the air monitors
because the overall testing requirements seemed incomplete. Further, air
monitoring alone is not sufficient. There should be soil samples after the
work was done, and methods that captured and tested wetting water to
ensure that asbestos was not being released into the environment through a
different media. Finally, there should be a comparison test between the
Fort Worth Method and the NESHAP. However, the current method is not
sufficient to serve as a methodology for that comparison test."
Response 22: EPA disagrees with the statement. It appears that the stakeholder
misunderstood the procedures followed in the Phase 1 test and the
phases of the project in general. See Response 1, 8, 9,10 and 14. The
soil was tested before and after the demolition. The water used on the
site was tested for asbestos content to assure that it was not providing asbestos
to the site. The Phase 2 test will include the comparison requested.
Regulatory Flexibility Incomplete
Page 16 Statement: In order for a Project XL proposal to be implemented within the scope
of the applicable laws and regulations, a legal mechanism that provides sufficient
regulatory flexibility (e.g., regulatory waiver, site-specific rule-making) must be in
place. Under the Asbestos NESHAP, which implements these requirements of the
Clean Air Act, EPA must publish a notice in the Federal Register that approves an
alternative means of controlling asbestos before it is implemented. This notice
allows the public the opportunity to assess the proposed alternative, and ensures a
process of openness in the development of a new demolition method. Because
EPA has not issued such a Federal Register Notice for the Fort Worth Method, the
Agency has not established the appropriate legal foundation for this demonstration
project.
Response 23: EPA would like to clarify the XL process. The FPA is negotiated,
signed by principal stakeholders, and its availability for review is
published in the Federal Register prior to the Agency issuing an
appropriate implementing legal mechanism. There are ongoing
discussions to continue this project outside of Project XL. If this decision is
made, the project will meet many of the technical & process standards
envisioned in XL and will have an appropriate legal mechanism. The IG's
office is aware of these discussions as they were present at a meeting on
September 29, 2003, where options were discussed.
Stakeholder Involvement Incomplete
Page 17 Statement: The City has performed some stakeholder involvement activities,
including inviting stakeholders to review and comment on the Phase I proposal
documents on the City's website in 1999. However, according to the 1997 Federal
Page 68
See Appendix J
Note 21
See Appendix J
Note 22

-------
Register Notice, project sponsors should engage "direct participants" in the
development of the project. According to the Notice, a direct participant "works
intensively with the project sponsors to build a project from the ground up," and
"the views of direct participant stakeholders will strongly influence the details of
the project as well as EPA's ultimate decision to approve or not to approve the
project."
Response 24: EPA is committed to a full and open process and to engaging a diverse
group of stakeholders as we develop fair and safe tests of the Fort
Worth Method under Phase 2. EPA will insure there is a transparent
and inclusive stakeholder process as part of the project, whether the
project proceeds under Project XL or another similar process.
See Appendix J
Note 23
Page 19 3-1. We recommend that the Assistant Administrator for Air and Radiation, the
Assistant Administrator for Enforcement and Compliance Assurance, the
Associate Administrator for Policy, Economics, and Innovation, and the
Regional Administrator for Region 6 ensure that Agency officials work
with the City of Fort Worth to develop a Final Project Agreement that
adequately addresses key project XL Criteria for the entire proposed project
(Phase II and Phase III), including:
determining whether the project can achieve superior environmental
performance;
verifying a mechanism for regulatory flexibility;
obtaining adequate stakeholder involvement;
sufficiently documenting the method so that it can be properly
transferred to other communities with similar results; and
ensuring that all Project XL team concerns are adequately addressed.
Response 25: EPA concurs with the recommendation that there be a written agreement that
addresses important projects, EPA will also address elements, such as
environmental performance, stakeholder involvement, transferability, and the
appropriate legal mechanism(s). It is not clear whether the project will
proceed in Project XL.
Chapter 4 Better Agency Oversight
Page 21 Statement: EPA's oversight to date has not ensured that conditions placed on the
project in the 2000 Conditional Project Approval Letter have been met, that
problems related to representativeness and equivalency have been resolved, or that
statutory and regulatory requirements have been satisfied
Response 26: EPA does not agree with the above statement. This statement
continues and perpetuates the misunderstanding of the Phase 1 test.
See Response 1. EPA is committed to ensuring that the project is well
defined, based on scientifically valid principles, and shaped through
See Appendix J
Note 24
Page 69

-------
full and open dialogue with a broad stakeholder group. The need to further
refine the Fort Worth Method as it presently exists, as well as the Quality
Assurance Project Plan (air, water, waste monitoring specifics) for the Phase 2
test, is a prerequisite set out by the IAC. EPA will conduct formal peer
reviews of these documents and present them to the stakeholder group for
review as well. The QAPP will include provisions for protecting public health
during any Phase 2 tests through broader monitoring of asbestos levels in the
area around the test sites and through the ability to halt a test demolition
immediately upon detecting visible emissions. Fort Worth also has agreed to
prepare for EPA and stakeholder review a remediation plan in the event of
unplanned asbestos release during any Phase 2 demolition. Both Fort Worth
and EPA are committed to designing a pilot that will provide sufficient
information for evaluation of the Fort Worth Method against the existing
NESHAP method. Finally, EPA will ensure that the range of conditions
under which the Fort Worth Method is validated, assuming successful
demonstration tests, defines the limits for eventually broadening use of the
Method.
Page 22 Statement: Further, EPA may lack the necessary information to make an
equivalency determination because the demolition was not representative of a
normal asbestos removal for the following reasons:
~	The pace of demolition was much slower than what would occur under
normal conditions;
~	The amount of water used on the Phase I demolition was not representative
of a normal asbestos removal; and
~	The building demolished under Phase I did not contain significant amounts
of spray-applied thermal insulation or asbestos-containing pipe wrap -
asbestos-containing materials which easily become friable.
Response 27: EPA disagrees with much of this statement. The Phase 1 test was
simply intended to be a preliminary, small scale test to inform EPA on
whether the Fort Worth method has promise and should be tested on a
structure regulated under the NESHAP.
Although the pace of the Phase I test was slower and not fully representative
of a NESHAP removal, it is EPA's opinion that the pace was sufficient to
validate the study. There appears to be confusion as to the findings of the
Phase 1 demolition. Phase 1 was the first test of the Fort Worth Method. If
the IG is referring to this test, there is no "normal" water use for this method.
If the IG is referring to other removals such as NESHAP or AHERA, the
comment doesn't relate as Fort Worth is a different technology. In summary,
increased water use is not necessarily bad as it would tend to maximize
wetting effectiveness. Some of the review team members are of the opinion
that the water use during Phase I could have been increased. The third
comment on the issue that the types of asbestos were not inclusive of pipe
See Appendix J
Note 25
Page 70

-------
wrap and spray-applied thermal is only valid if Fort Worth intends to use this
procedure on structures with significant quantities of this type materials. If
so, additional demonstrations would be necessary. However, the Phase 1
structure was considered to contain asbestos similar to structures that will
qualify for demolition under the Ft. Worth Method.
Agency Policies and Procedures for Similar Types of Alternative Proposals Lacking
Page 23 Statement: Project XL was one of EPA's early efforts to provide innovative
environmental alternatives. However, Project XL proposals are no longer being
accepted because all such alternative proposals now fall under one of two other
EPA innovations strategies: (1) Environmental Council of the States projects or (2)
Innovations Strategies.
Response 28: EPA does not agree fully with this statement. The Agency currently is
promoting innovative pilot projects under the Joint EPA/State
Agreement to Pursue Regulatory Innovation and also the State
Innovation Grant Program. Innovation projects may or may not
involve federal regulatory flexibility. There is no program named
"Innovations Strategies." Should the Agency undertake additional
innovation projects in the future that require regulatory changes, EPA will
ensure that they are clearly defined, based on credible science, shaped
through an open stakeholder process, designed to give us useful information
about alternatives to existing programs, and thoroughly evaluated prior to
affording broader implementation.
See Appendix J
Note 26
Page 25 Statement: The September 23, 2003 revised method proposes no additional testing
during Phase III demolitions, but rather moved directly to implementation of the
Fort Worth Method.
Response 29: A single test in Phase 2 is insufficient to serve as a launchpad to
implement the Fort Worth Method. While this was the original plan
under the Ft. Worth Method, more test are needed for a broad finding
of equivalency. The City and EPA are in discussions to conduct
additional tests as necessary to gather adequate scientific data to determine if
the Fort Worth method is equivalent to the NESHAP before seeking a broadly
applicable regulatory change.
See Appendix J
Note 27
Pages
25 & 26 We recommend that the Assistant Administrator for Air and Radiation, the
Assistant Administrator for Enforcement and Compliance Assurance, the Associate
Administrator for Policy, Economics, and Innovation, and the Regional
Administrator for Region 6:
Page 71

-------
4-1.
Ensure that Agency officials work with the City of Fort Worth to design a
demonstration project that can be used to reach complete, reliable, and
valid conclusions.
4-2. Work with the City to ensure that the structures chosen for the Phase II
demolition contain sufficient asbestos to provide a representative test and is
sited in a remote location.
4-3. Ensure that Agency officials address the key conditions of the Conditional
Project Approval letter, including equivalency and FPA development.
We also recommend that the Assistant Administrator for Research and
Development and the Associate Administrator for Policy, Economics, and
Innovation work jointly to ensure that:
4.4 Agency officials develop a single guidance document that provides
fundamental criteria and is published in the Federal Register, including:
requiring assessment of the technical merits and enforceability of
proposed projects;
ensuring that relevant expertise within the Agency is appropriately
considered; and,
requiring peer review of proposals that have significant national
policy implications, to ensure that national policy decisions are based
on sound science.
Response 30: Recommendations: EPA concurs with recommendations 4.1 and 4.2.
In addressing recommendation 4.3, while we agree to follow the spirit
of the conditional approval and will work with the City of Ft. Worth
to meet these goals it may not be in the formal Project XL process.
EPA considers recommendation 4.4 to be beyond the scope of this project.
See Appendix
Note 28
Page 72

-------
Appendix J
OIG Evaluation of EPA's Response to the Draft Report
EPA provided a response to our draft report that consolidated the comments of five EPA offices.
Although the Agency did not agree with our presentation of certain issues, it agreed to implement the
majority of our recommendations and noted that our report would be helpful to them as they endeavor
to carry out tests in a scientifically sound manner. In addition to technical comments, the Agency
discussed two aspects of the draft report. First, they stated that the tone of our draft report was
"unnecessarily negative." We address this assertion in our specific responses, and have made changes
as appropriate. For example, we have given more prominence early in the report to the Agency's
plans to work with Fort Worth to improve the Method and have it peer reviewed prior to
implementation. We do not agree that there was a negative tone in draft report. There is a difference
between a negative tone and presenting negative results. The report calls into question many key
aspects of the proposed Fort Worth Method, and we have recommended processes, procedures, and
design elements that should be employed to assure a valid test is conducted.
The second Agency concern related to differing interpretations of the precedent-setting nature of the
Phase II test. We are concerned with the several contradictory aspects of the Agency's response. For
example, in its response, EPA states, "Any concerns regarding broad use of the alternate method seem
premature...it is simply a test." However, this statement seems to be contradicted with other
statements in EPA's response, such as, "The test is of broad interest because if it is successful in
showing an equivalently protective method at much lower cost, it has the potential to help many cities
demolish dangerous, abandoned buildings."
We believe that any test of the method should be well planned out and defined in advance, along with
well defined and agreed upon criteria for success, and that this XL project has implications for
demolition activities across the nation. Consequently, it is much more than just a test. Further, we
believe that OIG involvement in projects such as the Fort Worth Method is both appropriate and
timely, especially when such projects, as indicated in the Agency response, have the potential to
impact existing and possibly set new environmental and health protection precedents.
We are also concerned with EPA's response because Agency officials acknowledge that they have yet
to agree on what they plan to do under this demonstration project, even though this project has been
ongoing since 1999. In responding to our draft report, the Agency stated:
"Fort Worth and the Agency have not reached agreement on the methodologies and processes for
Phase II of the project and discussions are ongoing. We hope to reach agreement by January 30,
2004, in order to submit the documents for peer review and public comment."
We believe that if the recommendations outlined in this report are carried out, ongoing disagreements
- such as how many tests will be conducted, what the criteria for evaluation of results will be, what
will be tested, and what the timeframes of the project will be - will move towards effective
resolution.
Our specific responses to Agency comments are listed below.
Page 73

-------
Transmittal Memorandum
Note 1 -	We continue to believe that OIG involvement in projects such as the Fort Worth
Method is both appropriate and timely, especially when such projects have the
potential to impact existing and possibly set new environmental and health protection
precedents. Further, while EPA is still in an early stage of this Project XL Demolition
project, the Agency has been working with the City of Fort Worth for over four years
to develop this Method and has been unable to date to alleviate internal EPA
stakeholder concerns. Also, the Agency is aware of the interest that many cities have
exhibited in the outcome of the Fort Worth Project XL proposal, as those cities have
indicated interest in using the Fort Worth Method. We are aware of the desire of
many municipalities to address the on-going problem of abandoned or structurally
unsound buildings, but - as noted in our report - over 165,000 asbestos demolition
and renovation projects were conducted in the last 2 years without needing to change
the existing Asbestos NESHAP.
Note 2 -	We have made modifications to the report based on specific comments from the
Agency, including creating a "Recent Developments" section in the Executive
Summary that discusses and gives credit to the Agency's most recent planned actions.
However, there is a difference between a negative tone and presenting negative
results. During the development of our Draft Report, we presented the information
obtained in a straightforward, factual, accurate manner. Based the responses that we
received from stakeholders we contacted, the majority believed that the Fort Worth
Method needs significant modifications before it becomes equivalent to the Asbestos
NESHAP, and a few did not believe it was possible that the Fort Worth Method
would ever be equivalent to the Asbestos NESHAP. This is what we reported. We
employed a sound methodology for soliciting stakeholder comments on the design of
the proposed Method, including contacting all stakeholders identified by two or more
groups involved in the proposed project. Nonetheless, the Fort Worth Method can be
significantly enhanced if the Agency publishes the proposed Method in the Federal
Register and solicits nationwide comment on the technical merits and enforceability
of the proposal.
Note 3 -	We are encouraged that the Agency plans to have the proposed project externally peer
reviewed and to obtain public comment on the technical merits and enforceability of
the proposal. However, we remain concerned with the amount of time this project has
taken, and the evolving nature of the Fort Worth Method description. For example, as
discussed in Chapter 3, the Final Project Agreement (including stakeholder
involvement activities), normally concluded within 12 months from the date of
proposal, has yet to be finalized (this project was proposed on September 30, 1999).
Also, after more than four years, the Agency and the City of Fort Worth have not yet
agreed on a fully defined demolition methodology. Prior to providing information to
the stakeholder groups listed in Appendix C, we contacted Region 6 and requested
that they verify that the documents were the most up-to-date available. At the time of
the request (March, 2003), Region 6 staff confirmed that the IG had the most recent
version of these documents. Further, as evidenced in the Recent Development
Page 74

-------
Sections in Chapters 2 and 4, and in Appendix G, we have also assessed the
September 23, 2003 version of the Fort Worth Method. As noted in the report, as
technical aspects of the proposed Method have been more fully described and
documented, additional concerns have been raised, such as the fact that no air
monitoring would be employed after the Phase 2 demolition is completed.
Note 4 -	We agree that the Phase I structure was chosen because it was a single family
dwelling of less than three stories, and was therefore exempt from the Asbestos
NESHAP due to the type of structure, and have modified the report accordingly.
However, for the reasons discussed in Chapter 4, we do not agree with the Agency's
conclusion that the Phase I demolition was successful as a demonstration of the Fort
Worth Method. The Phase I demolition was not representative of a normal asbestos
removal because the pace of demolition was too slow, the amount of water used was
excessive, and a key procedure listed in the Quality Assurance Project Plan (QAPP)
regarding wind variability was not followed. Additionally, the Fort Worth Method
used in Phase 1 was not clearly defined in terms that provided a clear understanding
of the RACM that would be removed during a Project XL asbestos demolition,
making both independent analysis of the Fort Worth Method and replication by others
difficult. (See note 25 for additional discussion of Phase 1 concerns).
Note 5 -	We are pleased that the Agency concurs with and plans to implement the majority of
our recommendations. We would like to clarify that the peer review should include
review by external organizations.
Note 6 -	As discussed in Chapters 2, 3, and 4, we do not agree with the Agency's position that
the Fort Worth Method meets the Project XL criteria for superior environmental
performance, appropriate regulatory flexibility, adequate stakeholder involvement,
and transferability. See OIG responses to Agency comments 18, 20, and 23.
Note 7 -	As outlined in the 1994 Federal Register Notice establishing Project XL, "The pilots
are intended to test new approaches that could conceivably be incorporated into the
Agency's programs or in other industries, or other facilities in the same industry. EPA
is therefore most interested in pilot projects that test new approaches that could one
day be applied more broadly." The transferability criteria of Project XL thus indicates
that this demonstration project should be able to be transferred to other organizations
or communities that are facing the same situation as Fort Worth. Our statement
regards the transferability expectation for Project XL demonstration projects. We
have added language on Page 1 of the report to clarify this point.
Note 8 -	We were aware of and had already included in our Draft report a copy of the
September 23, 2003 revision of the Fort Worth Method, which was discussed in our
"Recent Developments" sections in Chapters 2 and 4; this has also been added to the
Executive Summary. This revised Method is also presented in its entirety in
Appendix F, along with an analysis of this version of the Fort Worth Method.
Regarding the version of the Fort Worth Method provided to the stakeholders for
review, we confirmed in March 2003 that we had the most up-to-date version of the
Page 75

-------
Fort Worth Method before distributing it to the various stakeholders listed in
Appendix C.
Note 9 -	During our field work activities, we forwarded all documents that we planned to send
to the stakeholders (identified in Appendix C) to the Region 6 Project XL coordinator
for this project. At the time of the request (March 2003), Region 6 staff confirmed
that the IG had the most recent version of these documents. We have listed these
documents in Appendix B.
Note 10 - We are pleased that the Agency will work with the City of Fort Worth to clarify the
RACM testing requirements and to ensure that future versions of the Fort Worth
Method clearly state that the RACM testing requirements to be employed are those
stated in the current Asbestos NESHAP (40 CFR, Part 763).
Note 11 - We continue to believe that the proposed Fort Worth Method does not adequately
address the criteria for immediately stopping the demolition. Neither version of the
Fort Worth Method (see Appendices A and F) uses the phrase "no visible emissions,"
nor does either version clearly address the authority for an inspector to halt demolition
work if visible emissions are observed. In our view, these provisions should be
specifically stated in the Method to avoid later debate and uncertainty.
Note 12 - Regarding the row labeled "Adequately wet RACM during demolition," we refer
specifically to Section 4(c)(ii) "Wetting" of the May 23, 2002 method, "A structure
[emphasis added] will be thoroughly and adequately wetted..." Further, Section
4(c)(5)(B) of the September 23, 2003 Method uses the same statement. Both
documents indicate that the "structure" will be adequately wetted, but does not
specifically state that RACM inside the structure will be adequately wetted.
Regarding no visible emissions, please see Note 11 above. While "no visible
emissions" was discussed in the 1999 Fort Worth Method Proposal document, no
language regarding visible emissions was carried forward from the proposal
documents to the Fort Worth Method.
Regarding an immediately enforceable stopping point, as noted above in Note 11, the
Fort Worth Method does not include language requiring work to stop if visible
emissions are observed.
Regarding dependency on air monitoring results, we maintain that the Fort Worth XL
project is dependent on air monitoring because the QAPP stipulates that air
monitoring results will determine successful project completion. Further, the City
states that the Fort Worth Method will save approximately 40 to 60 percent over the
NESHAP method. However, the majority of these savings would only be realized on
demolitions where no air monitoring is conducted.
Note 13 - We acknowledge the difficulties in applying the AHERA clearance level to ambient
asbestos testing. We also agree that the AHERA clearance level is not a health-based
Page 76

-------
standard. As discussed in Appendix E, the AHERA clearance level was intended to
measure the lowest asbestos air levels then measurable using the AHERA analysis
protocol. Currently, substantially lower levels can be measured due to lower filter
background contamination levels. For example, as discussed in Appendix E, levels of
10 to 20 structures per cubic centimeter can now be measured due to improvements in
filter technology. Consequently, we believe that the AHERA clearance level of 70
structures per cubic centimeter should be revisited, and any standard based on these
assumptions should be revisited. Further, the adequacy of this testing level for
determining re-occupancy of an enclosed area of a building does not make it an
adequate clearance level for ambient air monitoring.
Note 14 - We agree with this statement, and have modified the statement in the body of the
report.
Note 15 - Please see Note 5 regarding external peer review.
Note 16 - Please see Note 18 regarding our discussion of the Agency's Response 19.
Note 17 - We understand that the Phase I demolition was not originally included in the
September 30, 1999 proposal. However, nothing in the additional requirements for
Phase I precluded the Agency from addressing these key Project XL criteria for the
remaining Phases of the demolition project. It remains our position that these key
Project XL criteria have not been met.
Note 18 - We remain concerned that, after more than four years, agreement on the number of
tests to be conducted to demonstrate equivalency to the Asbestos NESHAP has not
been obtained. While the Agency asserts that there will be multiple tests, this point
does not seem to have been effectively communicated to the City, since the
September 23, 2003 Fort Worth Method - the most recently revised version - still
indicates that only one Phase II test will be conducted. Also, as discussed in Chapter
4, the Region 6 Conditional Project Approval Letter to the City dated January 20,
2000 included the criteria necessary to move forward to Phase II. This required that
the data from the Phase I demolition support a finding of equivalency from the
Administrator, and that the City of Fort Worth develop a Final Project Agreement.
Agency oversight has not ensured that either of these criteria have been met. In this
instance, the Agency failed to follow its own written procedures and requirements for
this project.
Note 19 - We have changed the word Council to Committee regarding the RAC/IAC. Further,
we understand the decision-making process of the IAC that is outlined in the Project
XL criteria. The impact of the IAC's decision-making process was discussed in Note
18.
Note 20 - We have discussed this issue with the Agency, and have addressed it in Note 4.
Page 77

-------
Note 21 - We believe that the Agency may have misunderstood the intent of this stakeholder's
comment. The stakeholder expressed concern that run-off from the site be captured
and tested to determine if asbestos from the structure was being carried away from the
site in a different medium. Further, we continue to have this concern based on
Section 8(a)(2) of the September 23, 2003 revised Fort Worth Method, which states
that, "Rinse water will be controlled on-site and allowed to naturally evaporate or be
absorbed into the ground." We believe that this is a potential health hazard because
any asbestos present in the rinse water will be left on-site in a friable condition.
Note 22 - In three of its responses to our Draft, the Agency has mentioned that it is considering
continuing the Fort Worth Method under a different process. Specifically, it states,
"There are ongoing discussions to continue this project outside of Project XL;"
"...whether the project proceeds under Project XL or another similar process;" and, "It
is not clear the project will proceed in Project XL." We are concerned that the
Agency has not determined which regulatory vehicle the Agency will use to move this
project forward, if it does not utilize Project XL. Accordingly, we have added
recommendation 4-4 in Chapter 4 which requests that the Agency officials specify
which legal mechanism will be used and which technical and process criteria will
govern the Fort Worth Method project in the future, specifically how human health
will be protected to at least a level equivalent to the current Asbestos NESHAP.
Note 23 - We are pleased that the Agency plans to use a full, open, transparent, and inclusive
stakeholder process. However, we are concerned that stakeholder involvement has
not yet been conducted. Further, the Agency does not appear to have addressed
stakeholder comments to date. As discussed in Chapter 4, this stakeholder input
includes numerous technical concerns provided by EPA staff and external
stakeholders, as well as the stakeholders that we interviewed. Nonetheless, the Fort
Worth Method can be significantly enhanced if the Agency publishes the proposed
Method in the Federal Register and solicits nationwide comment on the technical
merits and enforceability of the proposal, and we have included this in
recommendation 4-4 in Chapter 4.
Note 24 - We believe that this response from the Agency validates the concerns that we have
outlined in Chapter 4 of the report. After four years of developing this project, the
Agency's plans discussed in this response have yet to be fully developed and
implemented.
Note 25 - We are concerned with the Agency's statement that the Phase I demolition was "not
fully representative of a NESHAP removal..." while still attempting to maintain that it
was representative. For reasons discussed below, we believe that the Phase I
demolition was not representative of an Asbestos NESHAP removal. Therefore, in
our view, use of Phase I data should not be used to determine equivalency to the
NESHAP.
Both the contractor that conducted the Phase I demolition, and the City of Fort Worth
Engineer, agreed that under normal circumstances about two to four hours of time
Page 78

-------
would have been sufficient to demolish the Phase I structure, in lieu of the 2 days that
were spent actually demolishing the Phase I structure. We do not believe that the
pace of the Phase I demolition would be representative of the pace that would be used
if the Fort Worth Method were approved for commercial use.
We are also concerned that the more than 11,000 gallons of water used during the
Phase I test would not likely have been used during a two to four hour demolition. In
our view, use of water at this rate on larger structures is not realistic.
As a Project XL proposal, since the Method may potentially be applied to structures
throughout the nation, we believe that the Fort Worth Method document should
address representative types and quantities of RACM that would be encountered
throughout the country.
Note 26 - The "Innovations Strategies" referred to in this statement references the Innovation
Strategy as discussed in the September 30, 2003 document, "2003-2008 EPA
Strategic Plan: Direction for the Future." Nonetheless, we are pleased that -
irrespective of the program name under which such activities may be undertaken in
the future - the Agency is committed to ensuring that such projects are clearly
defined; based on sound science; employ a full, open, transparent, and inclusive
stakeholder process; and use the Federal Register notice-and-comment rulemaking
process to solicit nationwide input on the technical merits and enforceability of the
proposal.
Note 27 - We agree with this comment. As discussed in Note 18, we are concerned that the
number of tests to be performed has yet to be determined.
Note 28 - We made the recommendation for the development of a single guidance document
because of our concerns about the Fort Worth XL Project. However, the Agency
outlines its reliance on the Innovation Strategy in the September 30, 2003 Strategic
Plan, as discussed in Note 26. As a result, we believe that this would be an
appropriate step to assure that Innovations Strategy projects are evaluated based on
sound science. It is our position that, irrespective of the program name under which
such activities may be undertaken in the future, we believe that EPA should ensure
that such projects are clearly defined; based on sound science; employ a full, open,
transparent, and inclusive stakeholder process; and use the Federal Register notice-
and-comment process to solicit nationwide input the technical merits and
enforceability of the proposal.
Page 79

-------
Page 80

-------
Appendix K
Distribution
EPA Headquarters
Assistant Administrator for Air and Radiation
Assistant Administrator for Enforcement and Compliance Assurance
Assistant Administrator for Research and Development
Associate Administrator for Policy, Economics, and Innovation
Audit Follow-up Coordinator, Office of Air and Radiation
Audit Follow-up Coordinator, Office of Policy, Economics, and Innovation
Audit Follow-up Coordinator, Office of Research and Development
Audit Follow-up Coordinator, Office of Enforcement and Compliance Assurance
Audit Follow-up Coordinator, Office of Air Quality Planning, and Standards
EPA Region 6
Regional Administrator
Audit Follow-up Coordinator
City of Fort Worth
Mayor
Environmental Management Department
Office of Inspector General
Inspector General
Assistant Inspector General for Program Evaluation
Assistant Inspector General for Human Capital
Assistant Inspector General for Planning, Analysis, and Results
Assistant Inspector General for Congressional and Public Liaison
Counsel
Science Advisor
Product Line Directors
Editor
Human Resource-Center Managers
Page 81

-------