CHANGE FORTHE
BETTER WITH
ENERGY STAR
Service & Product Provider Success Story
Service & Product Provider Partner
LighTec, Inc.
35 Depot Street
Merrimack, NH 03054
Business: Energy Services Company (ESCO)
Kathy Beliveau
Sales and Marketing Manager
Phone: (603) 424-2165/ Fax: (603) 424-4312
Email: Kathyb@lightec.net
Customer
New Hampshire Ball Bearings, Inc.
155 Lexington Drive
Lanconia, NH 03246
Business: Rod End and Spherical Bearings
Herb Parkhurst
Facilities and Environmental Manager
Phone: (603) 524-0004/ Fax: (603) 528-4869
Email: hparkhurst@nhbb.com
New Hampshire Ball Bearings receives new environment friendly, energy efficient lighting system.
Project Scope
As part of its commitment to excellence in environmental performance, New Hampshire Ball Bearings, Inc.
(NHBB) partnered with LighTec, Inc. to install an innovative lighting system at its Astro Division in Laconia, New
Hampshire. The objective of the project was to replace the 400 watt Metal Halide fixtures with more efficient 3
and 4 lamp T5 High Output fixtures, saving $118,000 per year with a payback period of under a year and one-
half.
Project Summary
The project targeted energy conservation through prescriptive lighting design, customized to meet or exceed the
customer's requirements.
•	Energy Savings
The new lighting system reduced electricity consumption by 50%, from 2.2 million to 1.1 million kWh,
achieving a savings of nearly $118,000 per year. It also reduced the yearly atmospheric output of
carbon dioxide by 1.5 million pounds, sulfur dioxide by 13,000 pounds, and nitrogen oxide by 6,000
pounds. Additionally, maintenance costs were reduced by 49%.
•	Investment
The full cost of the project was approximately $245,000 with an adjusted cost of $166,000 through an
incentive from Public Service of New Hampshire, a utility company.
•	Financial Return
The project payback period was 1.4 years. This new lighting system was one of a number of measures
undertaken by NHBB to enhance environmental performance, increase operational efficiency, pursue
goals of continuous improvement, and meet or exceed the expectations of stakeholders.
•	Other Benefits
Employees now enjoy an improved and safer work atmosphere generated by the new lighting system.
Monitoring & Verifying Energy Savings
Energy readings were taken prior to the project's commencement and again upon the project's completion.
LighTec also monitored the utility bills pre- and post-installation to quantify real savings.
Distinguishing Value
LighTec, Inc. stands behind its projects with superior customer service, professionalism, quick turn around time
for problem resolution, and continuous technical support for up to 5 years. This project demonstrated the cost
effectiveness of lighting retrofits, especially in conjunction with utility rebates.
»EPA
United States
Environmental Protection
Agency

-------