§
<
30
\

z
o
^ c>v°
P R 0^
OFFICE OF INSPECTOR GENERAL
Catalyst for Improving the Environment
Evaluation Report
Better Enforcement Oversight
Needed for Major Facilities with
Water Discharge Permits in
Long-Term Significant Noncompliance
Report No. 2007-P-00023
May 14, 2007

-------
Report Contributors:
George Golliday
Renee McGhee-Lenart
Laura Tam
Andrew Creath
Dan Engelberg
Abbreviations
DMR	Discharge Monitoring Report
ECHO	Enforcement and Compliance History Online
EMS	Enforcement Management System
EPA	U.S. Environmental Protection Agency
NPDES	National Pollutant Discharge Elimination System
OECA	Office of Enforcement and Compliance Assurance
OIG	Office of Inspector General
OTIS	Online Tracking Information System
PCS	Permit Compliance System
QNCR	Quarterly Noncompliance Report
SNC	Significant Noncompliance
Cover Photo: Sloss Industries wastewater treatment facility.
(Black Warrior RIVERKEEPER Website photo)

-------
tf£D sr^
/ \ U.S. Environmental Protection Agency	2007-P-00023
?	^	Hffiro rkf Inenortnr (Perioral	May 2007
0*	U ¦ O • L. I I V11 Ul IIIICI I Lul a I UlCvll
Office of Inspector General
At a Glance
PRO"*^
Catalyst for Improving the Environment
Why We Did This Review
We undertook this review to
assess oversight of major
facilities in long-term
significant noncompliance
with water discharge permit
requirements. We sought to
determine if the U.S.
Environmental Protection
Agency (EPA) and States are
taking timely and appropriate
enforcement actions against
facilities in long-term
significant noncompliance.
Background
EPA has authorized 45 States
to administer the National
Pollutant Discharge
Elimination System program,
including enforcement of
discharge permits. EPA still
maintains responsibility for
oversight and ensuring that
Clean Water Act regulations
are enforced. According to
EPA's current guidance,
several basic oversight criteria
define a "well-performing"
compliance and enforcement
program, including (1) timely
and appropriate enforcement
response, and (2) accurate
recordkeeping and reporting.
For further information,
contact our Office of
Congressional and Public
Liaison at (202) 566-2391.
To view the full report,
click on the following link:
www.epa.qov/oiq/reports/2007/
20070514-2007-P-00023.pdf
Better Enforcement Oversight Needed for
Major Facilities with Water Discharge Permits
in Long-Term Significant Noncompiiance
What We Found
EPA did not provide effective enforcement oversight of major facilities with
National Pollutant Discharge Elimination System permits in long-term significant
noncompliance. While flexibility is required in a national program, EPA
inconsistently applied guidance defining timely formal actions. Also, EPA
guidance did not provide meaningful direction on what constitutes "appropriate"
actions. Moreover, for 21 of 56 facilities reviewed, EPA and States did not take
suitable formal enforcement actions to address all instances of significant
noncompliance. At the remaining 35 facilities, none of the actions we could
assess were timely based on criteria in EPA's Enforcement Management System.
EPA and States also did not maintain complete and accurate records of National
Pollutant Discharge Elimination System compliance and enforcement activities.
Many region and State files were incomplete, and data in EPA's information
systems were incomplete and inaccurate. Further, regions and States did not
report inspection-related violations in EPA's Permit Compliance System. We also
noted that bacteria exceedances are not required to be reported as significant
noncompliances.
Timely actions could help minimize the millions of pounds of excess pollutants
released by these facilities. We estimate that up to 51 million pounds of excess
pollutant loads were discharged from July 2002 through June 2005 by 44 facilities
reviewed, representing loads that could be minimized.
What We Recommend
We recommend that the Assistant Administrator for the Office of Enforcement
and Compliance Assurance clarify and implement guidance regarding facilities in
significant noncompliance, implement a quality assurance program, and establish
controls allowing EPA leadership to identify significant noncompliance by
bacteria-only violators. EPA disputed many of our findings, but stated general
concurrence with our recommendations and identified planned actions. However,
the Office of Enforcement and Compliance Assurance's planned actions generally
do not address the intent of our recommendations, and the issues are considered
unresolved.

-------
^tDsx
^	J	WASHINGTON, D.C. 20460
< JML, \	UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
*l PRO"*^
OFFICE OF
INSPECTOR GENERAL
May 14, 2007
MEMORANDUM
SUBJECT: Better Enforcement Oversight Needed for Major Facilities with
Water Discharge Permits in Long-Term Significant Noncompliance
Report No. 2007-P-00023
FROM:
Wade T. Najjum ^ /
Assistant Inspector General, Office of Program Evaluation
TO:
Granta Y. Nakayama
Assistant Administrator, Office of Enforcement and Compliance Assurance
This is our report on the subject review conducted by the Office of Inspector General (OIG) of
the U.S. Environmental Protection Agency (EPA). This report contains findings that describe
the problems the OIG has identified and corrective actions the OIG recommends. Accordingly,
the findings described in the report are not binding upon EPA in any enforcement proceeding
brought by EPA or the Department of Justice. This report represents the opinion of the OIG and
does not necessarily represent the final EPA position. Final determinations on matters in this
report will be made by EPA managers in accordance with established resolution procedures.
The estimated cost of this report - calculated by multiplying the project's staff days by the
applicable daily full cost billing rates in effect at the time - is $932,305.
Action Required
In accordance with EPA Manual 2750, you are required to provide a written response to this
report within 90 calendar days. You should include a corrective action plan for agreed upon
actions, including milestone dates. We have no objections to the further release of this report to
the public. This report will be available at http://www.epa.gov/oig.
If you or your staff have any questions regarding this report, please contact me at (202) 566-0832
or naiiurn. wade@epa. gov; or Dan Engelberg, Director for Program Evaluation, Water Issues, at
(202) 566-0830 or engelberg.dan@epa.gov.

-------
Better Enforcement Oversight Needed for Major Facilities with
Water Discharge Permits in Long-Term Significant Noncompliance
Table of C
Chapters
1	Introduction		1
Purpose		1
Background		1
Noteworthy Achievements		5
Scope and Methodology		5
2	Oversight Limited at NPDES Major Facilities in Long-Term SNC		6
EPA Guidance Misinterpreted and Vague		6
Lack of Suitable Enforcement at 21 Facilities		8
Untimely Enforcement at 30 Facilities		8
Timely Enforcement Helps Minimize Excess Pollutant Discharges		9
Conclusion		9
Recommendation		10
Agency Comments and OIG Evaluation		10
3	Incomplete and Inaccurate Records and Reporting Inhibit
EPA Oversight of NPDES Major Facilities		11
Compliance and Enforcement Files Incomplete		11
EPA's Enforcement Data Systems Inaccurate		12
Many Violations Found During Inspections Not Reported in PCS		13
Bacteria Not Reported as SNC		13
Conclusion		14
Recommendations		14
Agency Comments and OIG Evaluation		14
Status of Recommendations and Potential Monetary Benefits		15
Appendices
A Details on Scope and Methodology		16
B Overall Agency Comments		20
C OIG Evaluation of Overall Agency Comments		23
D Detailed Agency Comments and OIG Evaluation		25
E	Distribution		43

-------
Chapter 1
Introduction
Purpose
We initiated this review to assess oversight of major facilities in long-term
significant noncompliance (SNC) with National Pollutant Discharge Elimination
System (NPDES) permits. The U.S. Environmental Protection Agency (EPA) has
overall responsibility for implementing the NPDES program and ensuring
adherence to Clean Water Act regulatory requirements. We sought to determine
how well EPA is ensuring that timely and appropriate enforcement actions are
taken against NPDES facilities in long-term SNC. We also sought to determine
what excess pollutant loads could be minimized if facilities in long-term SNC for
effluent violations achieved compliance.
Background
The Clean Water Act authorizes the NPDES permit program. The program is
designed to control water pollution by regulating point sources that discharge
pollutants into surface waters of the United States. Point sources are discrete
conveyances, such as pipes from municipal and industrial facilities or man-made
ditches. These facilities are generally classified as major or minor, depending on
size and nature of the discharges. For example, a major municipal treatment plant
typically discharges one million gallons or more per day of wastewater.
Facilities that intend to discharge pollutants into the Nation's waters are required
to obtain an NPDES permit. The permit sets limits on the amount of pollution a
facility can discharge into waterbodies, to protect human health and aquatic
resources. Federal regulations require permitted facilities to monitor discharged
pollutants and periodically report those monitoring results to EPA or States using
Discharge Monitoring Reports (DMRs).
Noncompliance with permit requirements can pose risks to human health and the
environment. Violations of pollutant permit limits can expose aquatic life and
humans to excess levels of toxic or harmful pollutants. Similarly, failure to
submit DMRs means risks to aquatic life and humans are unknown.
EPA Oversight of NPDES Compliance and Enforcement Programs
The EPA Office of Enforcement and Compliance Assurance (OECA) is
responsible for ensuring that the regulated community complies with Federal
environmental statutes, including the Clean Water Act. The Clean Water Act
gives EPA authority to allow States to administer the NPDES program.
1

-------
Currently, 45 States administer the program, including compliance and
enforcement. Where the State is the administering agency, EPA has continuing
overall responsibility for implementing and overseeing the NPDES program. In
the remaining States, EPA is still the administering authority. For certain States,
including Oklahoma and Texas, EPA has compliance and enforcement authority
for some facilities while the States have that authority over others.
According to EPA's current guidance, 1986 Revised Policy Framework for
State/EPA Enforcement Agreements, several basic elements define a "quality"
compliance and enforcement program, including:
•	Timely and appropriate enforcement response
•	Accurate recordkeeping and reporting
Compliance with the nation's environmental laws is the goal of enforcement.
Deterrence of noncompliance is achieved through: (1) a credible likelihood of
detecting a violation, (2) the speed of the enforcement response, and (3) the
likelihood and severity of the sanction. Enforcement is a vital part of encouraging
regulated entities to meet environmental obligations. Additionally, enforcement
levels the playing field with environmentally compliant companies and deters
those who might otherwise profit from violating the law.
Types of Noncompliance
Title 40, Code of Federal Regulations, Section 123.45(a)(2) requires EPA and
States to report when NPDES major dischargers are in noncompliance with their
permit conditions. Reportable noncompliance can include a violation of effluent
limits in NPDES permits, violations of enforcement orders or schedules for
compliance with permit conditions, failure to provide compliance schedule reports,
unauthorized bypasses or discharges, and failure to submit DMRs on time.
SNC is a subset of reportable noncompliance. SNC involves priority violations of
NPDES permit conditions that EPA believes merit special attention, including:
•	Violations of monthly and non-monthly effluent limits for two or more
months during two consecutive quarterly review periods, by (a) 20 percent
for toxic pollutants, such as metals; and (b) 40 percent for conventional
pollutants, such as total suspended solids.
•	Non-effluent violations, such as bypasses or unpermitted discharges,
which cause or have the potential to cause a water quality problem, such
as beach closings.
•	Permit compliance schedule violations.
•	Reporting violations, including failure to submit timely DMRs (filing a
DMR more than 30 days late or not at all).
•	Violations of existing enforcement orders, including judicial or
administrative orders.
2

-------
There are approximately 6,400 active NPDES major facilities. About 4,800
facilities reported being in noncompliance for at least one quarter during our
12-quarter review period (July 2002 through June 2005). About 2,650 of those
facilities were reported to be in SNC for at least one quarter during the same time.
Enforcement Management System Criteria
EPA's national guidance for developing and improving NPDES compliance
tracking and enforcement systems is called the Enforcement Management System
(EMS). According to the EMS, there are three levels of response to all violations.
For some violations, a response may not be necessary. The second level response
is an informal response. An informal enforcement response can be an inspection,
phone call, or a violation letter. Informal responses inform the permittee that the
Agency is aware that a violation occurred. The third level of response is a formal
action. A formal enforcement action:
•	Requires a facility to take action to achieve compliance.
•	Specifies a timetable.
•	Contains consequences for noncompliance that are independently
enforceable without having to prove the original violations.
•	Subjects the facility to adverse legal consequences for noncompliance.
According to the EMS, facilities with SNC violations must receive a formal
enforcement action, from the administering authority, that is timely and
appropriate, or return to compliance within the quarter following the SNC
violation. If formal action is not taken, the State or EPA is expected to produce a
written record clearly justifying why an alternative action (other than a formal
action) was more appropriate. If the State, as the NPDES program authority, does
not take timely and appropriate formal enforcement action, EPA is expected to
take a formal enforcement action.
EMS states a timely formal enforcement action must be taken by the end of the
quarter following the SNC violation. For instance, if a facility experiences an
SNC violation in February of the first quarter, a formal enforcement must be
taken by the administering agency by June 30 of the second quarter.
EMS states an appropriate response for SNC is a formal action. The guidance
states an appropriate formal enforcement action is determined by its effectiveness
and whether the noncomplying facility returns to compliance as quickly as
possible. An appropriate action also establishes a deterrent to future violations
and promotes fairness of government treatment.
Compliance and Enforcement Data Systems and Reports
EPA and States use the Permit Compliance System (PCS) to manage and assess
compliance and enforcement program information. This includes such
3

-------
information as permit issuance, permit limits, facility monitoring data, and
enforcement and inspection activity for facilities regulated under the Clean Water
Act. EPA and States enter compliance and enforcement information directly into
the PCS database. For example, States enter DMR data and information
submitted by NPDES facilities into PCS. A few States submit DMR information
electronically.
The Online Tracking Information System (OTIS) enables EPA staff,
State/local/tribal governments, and Federal agencies to access enforcement and
compliance data from systems like PCS. The public can access the Enforcement
and Compliance History Online Website (ECHO),1 which provides similar data.
Each quarter, the States and/or EPA produce a Quarterly Noncompliance Report
(QNCR) from PCS. The report flags NPDES major facilities that were in
reportable noncompliance with permit requirements during the previous 6 months.
States and EPA regions use the QNCR to determine what actions to take at these
facilities. The QNCR encompasses a rolling 6-month period such that the QNCR
for the second quarter (April through June) captures reportable effluent violations
from January through June. The Watch List is an EPA management tool, not for
public access, that tracks facilities with serious or chronic noncompliance that
have not received formal enforcement action.
PCS reports effluent violations on the QNCR by using a computer comparison of
permitted effluent limits to a facility's actual self-reported monitoring data from
DMRs. If those effluent violations are severe enough, the facilities should be
flagged as SNC for effluent violations. The QNCR is submitted to EPA
headquarters on the last working day of the second month following the QNCR
period.
Compliance Inspections
Inspections are another critical source of compliance and enforcement
information. During inspections, information is gathered to determine
compliance. Inspections include direct observations of facility operations and/or
conditions. Inspections allow EPA and States to determine reliability of a
permittee's self-reported data. They also allow EPA to evaluate compliance with
permit conditions, applicable regulations, and other requirements. The Agency
goal is to have EPA and/or States annually inspect 100 percent of all NPDES
major facilities or equivalent coverage of a combination of major and priority
minor facilities.
1 http://www.epa.gov/echo/.
4

-------
Noteworthy Achievements
OECA piloted the State Review Framework in 2004 to foster dialogue on
enforcement and compliance performance that should lead to improved program
management and environmental results. This framework involves a process for
conducting performance reviews of enforcement and compliance activities in the
States (as well as for non-delegated programs implemented by EPA regions).
In January 2004, OECA initiated the "Watch List," which tracks facilities with
serious or chronic violations of environmental laws that have received no formal
enforcement response. The Watch List for NPDES facilities uses existing data
reported by EPA regions and States to PCS.
EPA, in cooperation with State governments and the Environmental Council of
the States, developed ECHO, which provides integrated compliance and
enforcement information for approximately 800,000 regulated facilities
nationwide. The site allows the public to find inspection, violation, enforcement
action, informal enforcement action, and penalty information about facilities for
the past 3 years.
Scope and Methodology
We conducted our review from January 2005 through December 2006 in
accordance with Government Auditing Standards, issued by the Comptroller
General of the United States. We reviewed EPA's oversight of NPDES major
facilities in long-term SNC using the following quality elements in EPA's 1986
Revised Policy Framework for State/EPA Enforcement Agreements: (1) timely
and appropriate enforcement response, and (2) accurate recordkeeping and
reporting. We interviewed staff in OECA and Office of Water's Office of
Wastewater Management. We interviewed staff in selected EPA regions, as well
as officials and staff in selected States.
We selected 84 of the 132 facilities in long-term SNC, according to EPA data
systems, in EPA Regions 4, 5, and 6 for our review. We reviewed available
compliance and enforcement files to determine their accuracy and completeness
for the 84 NPDES facilities in long-term SNC. We utilized data from PCS and
OTIS to determine the excess pollutant loads released from facilities in long-term
SNC for effluent violations. We evaluated the effectiveness of management
controls and considered findings in prior EPA Office of Inspector General (OIG)
reports.
Details on our scope and methodology are in Appendix A.
5

-------
Chapter 2
Oversight Limited at NPDES Major Facilities
	in Long-Term SNC	
EPA did not provide effective enforcement oversight of major facilities in long-
term SNC with NPDES permits. EPA inconsistently interpreted guidance
defining timely formal actions. Also, EPA's guidance does not provide a means
for determining the appropriateness of actions. Problems with EMS guidance
prevented us from determining whether enforcement actions taken were
appropriate. However, we found that for the 56 NPDES major facilities in long-
term SNC reviewed:2
•	At 21 facilities, EPA and States did not take suitable formal enforcement
actions to address SNC violations during our review period.
•	At the remaining 35 facilities, none of the actions that we could assess
were timely based on the criteria in EPA's EMS.
Timely and appropriate formal enforcement actions are important to minimize
additional pollutants from being discharged into the Nation's waters to ensure
protection of human health and the environment. We estimate that up to
51 million pounds of excess pollutant loads were discharged during our review
period by 44 facilities reviewed, and that represents loads that can be minimized.
EPA Guidance Misinterpreted and Vague
EPA did not consistently interpret its EMS guidance for timely actions, even
though EMS guidance is clear with regard to timeliness. Further, EMS guidance
is unclear regarding appropriateness of enforcement actions and is thus subject to
interpretation. This ambiguity prevented us from evaluating the appropriateness
of the EPA and State formal enforcement actions taken. However, we concluded
that EPA's ambiguous guidance may result in inconsistency in interpretations
between regions and States. Flexibility is needed in any national enforcement
program. Nonetheless, definitions for program fundamentals such as the
timeliness and appropriateness of action are necessary to establish minimum
acceptable performance and oversight.
2 Due to significant EPA data system errors for 27 facilities in Alabama, Michigan, and Texas, as discussed in
Chapter 3, we could only evaluate 57 of the 84 facilities selected for review for timely formal enforcement action.
We also eliminated one additional facility in Tennessee from our sample that was shown to be a minor facility by
OECA.
6

-------
EPA Inconsistently Interprets Guidance for Timely Actions
During our review, we were given inconsistent interpretations of what EPA
considers timely. In a 1999 EMS memo, OECA's water enforcement division
director wrote that for a formal enforcement action to be considered timely, it
must be taken by the end of the quarter following the SNC violation. In other
words, if a facility experiences an SNC violation in February of the first quarter,
then a formal enforcement action must be taken by the administering agency by
June 30 of the second quarter - the last day of the quarter - to be timely.
Although we believe the policy in the EMS memo is clear on the definition of
"timely," and the memo has not been rescinded, EPA allows other interpretations.
For example:
•	In response to an earlier version of our report, EPA asserted that timely
enforcement actions could be 60 days later than the timely definition
above.
•	In subsequent data submissions to the OIG, EPA noted that a timely
response must occur within 6 months of the facility appearing and
remaining on the QNCR. This implies EPA has up to a full year from the
time of an SNC violation to provide a response.
EPA's stated that "not only is there flexibility in the EMS language itself
regarding timeliness, but the fact that the EMS is a guidance document and not a
regulation infers flexibility." However, that is inconsistent with written guidance
in EMS, which provides a clear definition of timely.
EPA Guidance Does Not Address Appropriateness of Actions
EMS guidance states that the appropriate response to an SNC violation is
a formal action that should ensure that the facility returns to compliance
expeditiously, creates a deterrent effect, and is fair. However, the guidance does
not state how expeditiously facilities should come back into compliance after an
action is taken. In fact, EPA staff stated that "appropriate" is defined flexibly and
a formal action can address the same violations for many years. Since EPA has
no clear criteria, we could not determine if the formal actions taken were
appropriate.
We questioned whether the outcome of some formal actions was appropriate. For
example, EPA took a formal enforcement action in 1988 against the East Chicago
Sewage Treatment Plant.3 According to OECA, that action "renders all effluent
exceedances (sic) resolved pending since that time." East Chicago has been in
SNC for effluent violations - including pollutants such as phosphorus, chlorides,
and sulfates - in every quarter from 1996 to June 2005. During the 3 years of our
3 EPA issued Pretreatment Administrative Orders on January 25, 1993, and September 20, 2004. The September
2004 order addressed pretreatment issues found during an audit.
7

-------
review period, East Chicago discharged between 76,000 and 230,000 pounds of
excess phosphorus and between 12,000,000 and 38,000,000 pounds of excess
chlorides. We could not determine the excess loadings of sulfates. Seventeen
years after formal action, as of June 2005, the facility still had excess discharges
to waters that were currently impaired.
Lack of Suitable Enforcement at 21 Facilities
Of the 56 NPDES major facilities in long-term SNC that we were able to assess,
EPA and States did not take suitable formal enforcement actions to address all
SNC violations against 21 of them during the 3-year period July 2002 through
June 2005. Some facilities received informal actions, such as letters of violation.
According to the EMS, facilities with SNC violations must receive a formal
enforcement action, from the administering authority, that is timely and
appropriate, or return to compliance within the quarter following the SNC
violation. Specifically:
•	Eight of the 21 facilities in SNC during our review had not received a
formal action as of June 2005, according to OECA.
•	The remaining 13 facilities were operating under enforcement orders
issued prior to the time period, but these actions did not address all
violations for which the 13 facilities were in SNC.
For example, the Lafayette Sewage Treatment Plant in Tennessee received formal
action regarding only two of three pollutants for which it was in SNC. During our
review period, this facility was in SNC for effluent violations for six quarters for
ammonia-nitrogen, seven quarters for settleable solids, and two quarters for total
suspended solids. The Tennessee Department of Environment and Conservation
issued an Administrative Order in April 2002 to address ammonia-nitrogen and
total suspended solids violations. However, the Order did not address the
settleable solids violations. This facility discharged between 15,000 and 182,000
pounds of excess settleable solids from July 2002 to June 2005. The facility
discharges to a stream that is impaired for organic enrichment and low dissolved
oxygen, and Lafayette's excess settleable solids discharges could be further
worsening the existing water quality impairments.
Untimely Enforcement at 30 Facilities
EPA and States took 57 formal enforcement actions to address SNC violations
between July 2002 and June 2005 at 35 facilities.4 We were able to assess 45 of
4 Some facilities received more than one enforcement action. Thus, a facility may have had one action judged
untimely and another in which timeliness could not be determined. This explains the apparent inconsistency in the
total number of facilities associated with untimely actions and actions whose timeliness could not be determined.
A total of 35 facilities were included in the assessment.
8

-------
the 57 actions at 30 facilities for timeliness and, based on EMS criteria, none of
the 45 was timely.
For example, EPA issued an Administrative Order against ConocoPhillips
Company on August 14, 2003, to address effluent violations for selenium
beginning July 2002. The action was untimely because it was not taken by
December 2002 (the end of the next quarter), as required by EMS. According to
PCS, the facility continued to exceed selenium permit limits through June 2005.
Our calculations show that this facility discharged about 950 pounds of selenium
above its allowable permit level between July 2002 and June 2005. Selenium is
toxic to aquatic life and some wildlife and harmful to humans.
We could not determine the timeliness of the remaining 12 formal actions at
10 facilities because available information was flawed. Specifically, the
enforcement actions did not explain what SNC violation was being addressed or
when the SNC violations occurred. Without this information, we would not
determine whether the action was timely. For example, the Consent Decree
issued against the City of Columbiana Wastewater Treatment Plant in Alabama
on December 10, 2003, simply accelerates an existing compliance schedule for a
Consent Order issued on March 21, 2002. This action does not directly link to an
SNC violation. Therefore, we could not address timeliness.
Timely Enforcement Helps Minimize Excess Pollutant Discharges
Timely actions are important because they can help deter or minimize
environmental impact. The sooner SNC is identified and formal enforcement
actions taken, the sooner the excess pollution can be controlled. We estimate that
up to 51 million pounds of excess pollutant loads were discharged from July 2002
through June 2005 by 44 of the facilities we reviewed.5 Seventeen of those
facilities discharged excess pollutants into already impaired waters.
Conclusion
EPA has not provided its regions and States with clear and consistent guidance for
taking timely and appropriate enforcement actions. Incomplete and misleading
guidance reduces the effectiveness of regions' and States' oversight of NPDES
facilities. At the Agency level, we concluded that EPA does not provide effective
oversight over the regions and States. Noncompliance with permit requirements
can pose risks to human health and the environment through exposure to excess
levels of toxic or harmful pollutants.
5 Due to a lack of data in EPA's data system, we could only calculate a range of pollutant discharges for some
facilities. See Appendix A for more details.
9

-------
Recommendation
We recommend that the Assistant Administrator, Office of Enforcement and
Compliance Assurance:
2-1 Clarify and implement the EMS guidance to ensure that timely and
appropriate formal enforcement actions are taken against NPDES facilities
in SNC.
Agency Comments and OIG Evaluation
EPA agreed to clarify the EMS guidance by rescinding the 1999 OECA
memorandum in conflict with the EMS. EPA's planned action is to eliminate the
guidance that clarifies when timely enforcement action should be taken. While
reducing the ability to measure the effectiveness of enforcement actions increases
the flexibility to define all actions as timely, it does not meet the intent of the
recommendation. EPA's detailed response and OIG's evaluation are in
Appendices B, C, and D. The OIG has incorporated technical corrections and
clarifications from EPA's response into the final report as appropriate.
10

-------
Chapter 3
Incomplete and Inaccurate Records and Reporting
Inhibit EPA Oversight of NPDES Major Facilities
Records of compliance and enforcement activities were often incomplete and
inaccurate. Specifically:
•	Many region and State files were incomplete.
•	Data in EPA's information systems were incomplete and inaccurate.
•	Regions and States did not report inspection-related violations in PCS,
although EPA required such reporting.
An accurate history of the compliance and enforcement activities at a facility is
important for oversight and making future enforcement decisions. The lack of
accurate information inhibits EPA's ability to provide effective oversight to
NPDES major facilities and thus protect human health and the environment from
excess levels of toxic or harmful pollutants. During our review, we also found
that bacteria exceedances are not required to be reported as SNC, but we think
such reporting should be considered.
Compliance and Enforcement Files Incomplete
Many EPA and State compliance and enforcement files were incomplete for
NPDES major facilities. We reviewed EPA and State files to determine if they
were complete by comparing enforcement information from EPA and State file
reviews to formal enforcement actions listed in PCS/OTIS. Some of the
information in the compliance and enforcement files did not match the
information recorded in EPA's data systems. Table 3-1 on the following page
shows the results of comparing enforcement files with EPA's data system
information. Additionally, 12 formal enforcement actions in the EPA and State
files were not listed in EPA's data systems. We also found one action listed in
OTIS for which we could find no other evidence in either PCS or EPA and State
files. Incomplete files and data systems prevent EPA from having the needed
information to provide effective oversight.
11

-------
Table 3-1: Completeness of EPA and State Enforcement Files
Region
State
Actions
reported by
PCS/OTIS
No. of those
actions found
in EPA files
Percent
complete
No. of those
actions found
in State files
Percent
complete
Region 4
Alabama
8
5
63%
8
100%

Tennessee
7
4
57%
4
57%

Total
15
9
60%
12
80%
Region 5
Indiana
4
2
50%
1
25%

Michigan
4
2
50%
1
25%

Total
8
4
50%
2
25%
Region 6
Oklahoma
12
10
83%
5 (of 9)*
55%*

Texas
22
12
55%
5 (of 10)*
50%*

Total
34
22
65%
10 (of 19)*
53%*
*When calculating completeness of State files, we did not consider actions taken against facilities for which
EPA retains primary enforcement authority.
Source: EPA OIG review
EPA's Enforcement Data Systems Inaccurate
EPA's data systems used to track NPDES enforcement program are inaccurate.
EPA's data systems do not accurately reflect the SNC status of facilities. Once a
formal enforcement action is issued for an SNC violation, a facility should be
designated as "resolved pending" for that violation, according to Title 40, Code of
Federal Regulations, Section 123.45. However, OECA states that Regions 4, 5,
and 6 (the three regions reviewed) do not designate facilities in "resolved
pending." Thus, facilities in these regions may appear to remain in SNC status in
EPA's data systems for a long time despite operating with an existing
enforcement action.
EPA's data system incorrectly classified Michigan facilities in SNC for DMR
violations due to data system errors in Michigan. These errors have existed since
2003. EPA's PCS data system showed that 30 facilities from Michigan were in
long-term SNC. However, OECA reviewed the facilities' status and determined
that 27 of the facilities were not actually in SNC.6 OECA stated that Michigan
was having problems entering DMR information into PCS in a timely manner.
Staff from Michigan Department of Environmental Quality also noted that their
data system was not capable of correctly communicating with PCS and that SNC
data was not available through their system at the time we interviewed them.
However, the data entry and transmission problems continue, which seriously
compromises EPA's oversight of Michigan's NPDES facilities.
6 We excluded 25 Michigan facilities with significant data errors from our analysis. Two other facilities, one from
Alabama and one from Texas, were also excluded for similar reasons. See Appendix A for more details.
12

-------
In a related matter, EPA staff stated that once a facility receives a violation for
submitting DMRs late, that violation will continually show as a violation in
EPA's data systems until regions or States manually correct the problem. EPA
needs to ensure its data systems are accurate so it can provide proper oversight to
regions and States.
Many Violations Found During Inspections Not Reported in PCS
Despite EPA requirements, most EPA regions and States do not enter into PCS
violations found during inspections. OECA reported that no States in EPA
Regions 1, 2, 5, 7, 9, and 10 reported these violations in Fiscal Year 2005.
Inspections allow EPA and States to determine the reliability of the permittee's
self-reported data and evaluate compliance with permit conditions and applicable
regulations. Entering these violations into PCS allows EPA and States to track
these violations and report them.
EPA currently requires data entry of violations found during inspections (called
single-event violations) for NPDES major permittees in PCS in the single event
category. However, most States are not performing this procedure. Staff from
EPA Region 4 stated that EPA does not ensure that States enter single event
violation data from inspections. Staff from EPA Regions 5 and 6 acknowledged
that entry of single event violations is required. Failing to enter inspection-related
violations in PCS may prevent these types of violations from being identified and
acted upon.
Bacteria Not Reported as SNC
We noted numerous and significant exceedances of bacteria permit limits at 37 of
84 facilities we reviewed. Almost 75 percent of the exceedances would be
classified as SNC using the criteria for conventional pollutants. The
violations ranged up to 59,000 percent of the permit limit. None of these
violations was reported as SNC in PCS or OTIS because bacteria are not a
pollutant subject to SNC criteria. Since these violations are not classified as SNC,
they would likely not be reported on the QNCR that regions and State use to
address facilities with significant violations.
Although SNC reporting is not required, bacteria are a leading cause of water
quality impairments across the nation. When present at levels exceeding water
quality standards, bacteria can make swimmers ill and contaminate shellfish for
human consumption. Our review only discovered the significant bacteria
violations because those facilities had SNC violations for other pollutants. In the
absence of other SNC violations, EPA and States may not address significant
bacteria violations.
Because this issue was outside the scope of our review of long-term SNC, we did
not conduct a separate review focused on the extent of bacteria-only violations
13

-------
and the adequacy of the response to them. However, it is enough of a concern
that it warrants further review by OECA.
Conclusion
While EPA has overall responsibility for implementing and overseeing the
NPDES program, EPA generally has to rely on the States for information. EPA
cannot attest to the reliability of records and data for those facilities in long-term
SNC. Incomplete and inaccurate records and information represent a
management control weakness. EPA cannot rely on NPDES enforcement and
compliance data from its internal systems being complete or accurate. Also,
enforcement and compliance records maintained by regions and States are
incomplete and inaccurate. OECA needs to implement a quality assurance
program that, at a minimum:
•	Assesses accuracy of region and State compliance and enforcement files.
•	Verifies status of facilities in SNC.
•	Verifies that formal actions taken are correctly entered into EPA systems.
•	Assures reporting issues (with Michigan and others) are resolved or reports
annotated to disclose known inaccuracies.
•	Verifies that all EPA regions and States are entering violations found as a
result of inspections in PCS.
Recommendations
We recommend that the Assistant Administrator, Office of Enforcement and
Compliance Assurance:
3-1 Implement a quality assurance program addressing the completeness of
compliance and enforcement files, accuracy of EPA data systems, and
reporting in PCS the violations found during inspections.
3-2 Establish controls allowing EPA leadership to identify significant
noncompliance by bacteria-only violators for enforcement action.
Agency Comments and OIG Evaluation
EPA generally concurred with our recommendations. However, OECA's
response that its existing actions and processes provide a reasonable amount of
quality assurance is not responsive to Recommendation 3-1. We consider the
issue unresolved. For Recommendation 3-2, we accept OECA's response.
OECA will need to provide us with an action plan and milestone dates for when
the proposed actions will occur. EPA's detailed response and OIG's evaluation
are in Appendices B, C, and D. The OIG has incorporated technical corrections
and clarifications from EPA's response into the final report as appropriate.
14

-------
Status of Recommendations and
Potential Monetary Benefits
RECOMMENDATIONS
POTENTIAL MONETARY
BENEFITS (In $000s)
Rec.
No.
Page
No.
Subject
Status1
Action Official
Planned
Completion
Date
Claimed
Amount
Agreed To
Amount
2-1	10 Clarify and implement EMS guidance to ensure
that timely and appropriate formal enforcement
actions are taken against NPDES facilities in SNC.
3-1	14 Implement a quality assurance program addressing
the completeness of compliance and enforcement
files, accuracy of EPA data systems, and reporting
in PCS the violations found during inspections.
3-2 14 Establish controls allowing EPA leadership to
identify significant noncompliance by bacteria-only
violators for enforcement action.
Assistant Administrator,
Office of Enforcement and
Compliance Assurance
Assistant Administrator,
Office of Enforcement and
Compliance Assurance
Assistant Administrator,
Office of Enforcement and
Compliance Assurance
1 0 = recommendation is open with agreed-to corrective actions pending;
C = recommendation is closed with all agreed-to actions completed;
U = recommendation is undecided with resolution efforts in progress
15

-------
Appendix A
Details on Scope and Methodology
We conducted our review from January 2005 through December 2006 in accordance with the
Government Auditing Standards, issued by the Comptroller General of the United States.
We interviewed staff in OECA and the Office of Water's Office of Wastewater Management to
determine applicable compliance and enforcement guidance and criteria for EPA regions and
States. We reviewed NPDES major facilities in long-term SNC. We classified facilities as being
in long-term SNC if they had been in SNC for 8 of 12 quarters from the third quarter of 2002 to
the second quarter of 2005 in PCS. However, due to continual updating of EPA data systems,
7 of the facilities selected were classified in SNC for only 7 of 12 quarters by the end of our field
work.
We selected EPA Regions 4, 5, and 6 for review because they have the highest concentration of
NPDES major permits with 3,506 facilities (55 percent of the universe). Further, of EPA's
10 regions, they are ranked high in the number of long-term SNC facilities (see Table A-l).
Table A-1: Number of SNC Facilities/Ranking of Regions
Regions
No. of Long-Term
SNC Facilities
Ranking
Region 4
38
4th
Region 5
51
2nd
Region 6
43
3rd
Source: EPA OIG Review
Although EPA Region 2 had the highest number of long-term SNC facilities, many were in the
territory of Puerto Rico, and we chose not to review that region due to travel and time
constraints. We interviewed staff in all three regions selected for review. We also interviewed
EPA Region 7 staff during the preliminary research phase of our review.
We reviewed 84 of the 132 facilities in long-term SNC in EPA Regions 4, 5, and 6 according to
PCS. These 84 facilities represent about 1.3 percent of the total number of active NPDES major
facilities from 2002 through 2005. We selected facilities by choosing two States from each of
the three EPA regions reviewed (see Table A-2). We interviewed staff in those States to gather
information about compliance and enforcement programs.
Table A-2: Facilities Reviewed by State
Regions
States
No. of Facilities
Reviewed
Region 4
Alabama
8
Tennessee
12
Region 5
Indiana
8
Michigan
30
Region 6
Oklahoma
4
Texas
22
Source: EPA OIG Review
16

-------
We reviewed compliance and enforcement files for 84 NPDES facilities in long-term SNC. We
reviewed files to confirm enforcement actions taken by EPA and States as reported in PCS and
OTIS, determined whether timely formal enforcement actions were taken at facilities, and
determined the completeness of the compliance and enforcement files. To do this, we verified the
SNC status and formal actions taken at each facility through OTIS. We relied on the
classification system in PCS and OTIS to indicate whether an action was formal or informal.
During file reviews, we documented only those actions classified as formal - such as
administrative orders and consent orders - and compared them to information from PCS and
OTIS to confirm that our data were complete. Finally, we compared the formal actions taken
against each facility with the facility's SNC status in PCS and OTIS to determine if timely
formal enforcement actions were taken consistent with criteria from EPA's EMS document.
We could not assess the appropriateness of enforcement actions because the EMS does not state
how expeditiously facilities should come back into compliance after an action is taken. This
ambiguity prevented us from evaluating the appropriateness of the EPA and State formal
enforcement actions taken.
Of the 84 initial facilities we evaluated, 25 of the 30 facilities in Michigan were excluded from
our timeliness analysis due to EPA data system errors. Additionally, one facility each in Texas
and Alabama were excluded for similar issues. We also excluded one facility because it was a
minor facility even though OECA's data systems showed it as a major facility in SNC. We
analyzed the remaining 56 facilities to determine if timely formal enforcement actions were
taken to address SNC. Due to EPA data system inaccuracies, 2 of the 56 facilities that were
classified as major facilities in PCS were actually minor facilities for part of our 3-year
evaluation period. As such, we evaluated these facilities only for that period of time when the
facilities were considered major facilities.
Because 21 facilities did not have actions taken during our review period, we only identified and
analyzed formal enforcement actions at the remaining 35 facilities. We reviewed 69 actions
from these 35 facilities. We excluded 12 of those 69 actions from our analysis for timeliness
(8 addressed sludge or sludge reporting violations that were not directly related to the SNC
violations, 3 addressed citizen complaints at specific facilities, and 1 represented a parallel action
that allowed the State to assume primary enforcement authority from EPA). Thus, we evaluated
57 formal actions.
To evaluate timeliness for the 57 formal actions, we reviewed each individual action found
during the file reviews and from OTIS to determine the following information: (1) the date the
formal action was taken, (2) the specific SNC violations the action addressed, and (3) the dates
the violations occurred. We then determined the length of time between the dates the actions
were taken and the dates the violations occurred. We compared the violations and formal actions
to the 3-year compliance status history as shown in OTIS for each facility on a quarterly basis.
We compared the length of time between violation and action with EPA's EMS criteria for
timeliness. If the length of time exceeded the time period allowed by the criteria, the action was
found to be untimely. Although we conducted an extensive file review on each facility, we did
not have enough information on 12 formal actions to determine whether they were timely.
17

-------
We analyzed data from OTIS and PCS to determine the excess pollutants released from facilities
in long-term SNC for effluent violations. We calculated the excess pollutant load by
determining the pollutant load each facility is permitted to discharge and subtracting that load
from the pollutant load each facility actually discharged when it violated its permit limits. We
determined the pollutant load actually discharged from facility DMR information by multiplying
the actual effluent flow times the actual effluent pollutant concentration times a constant of 8.34.
EPA uses this formula to determine mass-based permit limitations and was reviewed by staff
from EPA's Office of Wastewater Management. We calculated the permitted pollutant load for
each facility using the same formula and each individual facility's pollutant permit limits. We
summed the daily excess pollutant loads for each facility over the 3-year time period from the
third quarter of 2002 through the second quarter of 2005.
In certain cases, OTIS did not report actual effluent pollutant concentrations. However, the
percentage by which the permit limit was exceeded was reported in OTIS. In this case, we back-
calculated the actual effluent pollutant concentration using the pollutant permit limit and the
percentage by which the permit limit was exceeded as reported by PCS. Since the percentage
exceedance is calculated by PCS automatically using the data as reported by each facility on its
DMRs, this method did not compromise the accuracy of the actual effluent pollutant
concentration. Five of the 84 evaluated facilities were listed as SNC for effluent violations, but
OTIS had no information indicating which effluent limits were violated or by what percentage.
For this reason, we did not include those five facilities in our analysis.
Due to varying availability of information for each facility, we calculated both minimum and
maximum excess pollutant loads. If the required information for each facility - including design
and actual reported flows, permit effluent limits, and actual effluent concentrations - was
available in the detailed facility reports from PCS, then it was not necessary to determine
minimums and maximums. However, if the only information available was the design flow,
permit limit, and the percentage by which the facility exceeded its permit limit from the detailed
facility report, then we calculated both minimum and maximum excess pollutant loads. This is
because the 3-year compliance status by quarter only lists the highest monthly percentage by
which the facility violated its permit limits in that quarter. The magnitude of any violations in
other months for that quarter was unknown. Both minimum and maximum excess pollutant load
were calculated to account for this uncertainty.
While interviewing EPA region and State staff, we also sought to obtain information on what
tools and best practices are available to help address facilities in long-term SNC.
Management Controls
We identified the following management controls as applicable to our objectives:
Effectiveness of Program Operations: We evaluated the effectiveness of the
compliance and enforcement program by determining if EPA and States were providing
timely and appropriate enforcement actions to facilities in long-term SNC, and if EPA
provided effective oversight to selected regions and States. Details on what we found are
in Chapter 2.
18

-------
Validity and Reliability of Data: We evaluated the validity and reliability of PCS/OTIS
data by comparing it with the data found in EPA regions and State files. We compared
the number and types of formal enforcement actions in PCS/OTIS for the 84 facilities we
reviewed with the information found in EPA and State files. Details on what we found
are in the Chapter 3.
Compliance with Applicable Laws and Regulations: In our evaluation, we determined
whether regions and States were following EMS guidance in addressing facilities in SNC
with timely enforcement actions. We found problems in the guidance provided. Details
on what we found are in Chapter 2.
Prior Coverage
We reviewed the following prior EPA OIG audits as they pertained to our review:
•	Water Enforcement: State Enforcement of Clean Water Act Dischargers Can Be
More Effective, 2001-P-00013, August 14, 2001.
•	North Carolina NPDES Enforcement and EPA Region 4 Oversight, 2000-P-00025,
September 28, 2000.
•	Kansas National Pollutant Discharge Elimination System Program, E1HWF7-07-
0022-8100089, March 31, 1998.
•	Region 10's National Pollutant Discharge Elimination System Permit Program,
E1HWF7-10-0012-8100076, March 13, 1998.
19

-------
Appendix B
Overall Agency Comments
March 30, 2007
MEMORANDUM
SUBJECT: OECA Comments on Draft Report, "Better Oversight Needed for Maj or
Facilities with Water Discharge Permits in Long-Term Significant
Noncompliance"
FROM: Granta Y. Nakayama
Assistant Administrator
TO:	Dan Engelberg
Director, Water Issues, Office of Program Evaluation
Office of Inspector General
The Office of Enforcement and Compliance Assurance (OEC A) appreciates the opportunity
to review and comment on the February 28, 2007 Office of Inspector General (OIG) draft report
titled, "Better Oversight Needed for Major Facilities with Water Discharge Permits in Long-
Term Significant Noncompliance." This draft report was revised after OIG received OECA's
extensive comments in October 2006 on its initial August 2006 draft report. The revised draft is
an improvement over the initial draft. However, despite exhaustive efforts by OECA and
Regional staff to provide well-documented comprehensive comments and to be available for
follow-up consultation, significant factual inaccuracies and misinterpretations remain. These
undermine the credibility of OIG's analysis and diminish the value of its recommendations.
These include:
•	Inaccurate Interpretation of National EPA Enforcement Guidance and Policy. Despite
OECA's attempts to clarify the operation of its guidance and policy, OIG fails to
recognize the difference between regulatory requirements and EPA guidance and, as a
result, applies EPA's timely and appropriate enforcement response guidelines as a rigid
requirement. OIG's draft report fails to consider the deliberate flexibility provided to
Regions and states in EPA's guidance resulting in inaccurate OIG findings such as, "at 22
of the 57 facilities reviewed, EPA and the states did not take sufficient formal
enforcement action," and "at the remaining 35 facilities, none of the actions were timely."
In stark contrast, OECA's assessment of the 57 facilities indicated that the vast majority
(approximately 53 or 93%) of facilities included in the OIG review received an adequate
response to address the SNC violations.
•	Inaccurate Data Analysis. At least seven facilities (three in Region 4 and four in Region
6) should not have been included in OIG's analysis because they were not classified as
20

-------
major facilities during all or part of the evaluation period and, therefore, would not have
been screened for SNC violations by EPA. A request for change in a facility's status is
submitted in writing from a Region to OECA's Office of Compliance. Status change
dates are not archived in EPA's Permit Compliance System (PCS) or Facility Registry
System; they are documented in manual files maintained in the Regional offices. OECA
provided information on this issue in its October 2006 response to OIG's original report,
yet OIG did not remove these facilities from its February 2007 draft report. OIG
continued to misinterpret data in its analysis and inaccurately concluded that these
facilities were majors. In other instances, OIG failed to acknowledge that many SNC
violations reviewed were already addressed under existing enforcement orders and
compliance schedules (i.e., the facility was in "resolve pending" status in PCS), and thus
did not require any additional enforcement. Lastly, facilities were included in the
analysis even though a known state-wide data system problem resulted in incorrect SNC
determinations.
• No Acknowledgement of Ongoing Efforts to Improve Records and Reporting. OIG's
draft report fails to consider OECA's ongoing efforts to work with Regions and states,
through the State Review Framework (SRF), the Watch List, and ECHO processes, to
improve record keeping and reporting associated with compliance monitoring and
enforcement activities. OECA believes that its existing efforts are responsive to OIG
recommendation 3-1 to implement a quality assurance program addressing the
completeness of compliance and enforcement files and recommendation 3-2 to address
significant bacteria violations. By not recognizing these recent efforts to establish better
management controls and accountability, the draft report leaves the impression that
OECA is not actively addressing issues such as timely enforcement and accurate
recordkeeping of enforcement files.
Despite numerous concerns with the underlying analysis in this draft report, OECA largely
accepts OIG's three recommendations and, as noted in the bullet above, is already implementing
two out of the three recommendations. Of the remaining recommendation, 2-1, to clarify and
enforce EMS guidance, OECA is prepared to implement the part of the recommendation that will
clarify the guidance. In response, OECA commits to rescind the 1999 OECA memorandum that
conflicts with the NPDES Enforcement Management System (EMS). This will be discussed
with the Regional NPDES Enforcement Branch Chiefs at the national NPDES meeting in April,
2007. OECA does not, however, concur with the balance of recommendation 2-1, to enforce the
EMS, as the EMS does not impose a set of enforceable standards.
This draft report reflects continuing problems with the overall OIG evaluation process,
including: poor communication during the analysis leading to the use of incomplete and/or
inaccurate information, broad findings that are not supported by the data used, lack of
acknowledgment of ongoing efforts by OECA, Regions, and states to address the problem being
evaluated, exclusion of relevant information which would directly impact findings and
recommendations, and failure to weigh the benefits of OIG's recommendations against the
resource burdens and procedural barriers they will entail and the competing needs and demands
they will displace. A specific example of poor communication during this evaluation is the fact
that even after receiving detailed written comments from OECA and having face-to-face
21

-------
meetings to discuss those comments, OIG staff never contacted EPA staff with any follow-up
questions or clarifications in the course of re-writing the draft report. OECA would like to work
with the OIG to improve communication and the overall evaluation process.
Attached are OECA's detailed comments on the analysis, findings, and recommendations in
the February 28, 2007 draft report. If you have any questions, please call Mark Pollins at
202-564-4001.
Attachments
cc: Walker Smith, OCE
Randy Hill, OCE
Mark Pollins, OCE
Michael Stahl, OC
Lisa Lund, OC
David Hindin, OC
Doug Mundrick, Region 4
Cheryl Newton, Region 5
Mike Michaud, Region 6
22

-------
Appendix C
OIG Evaluation of Overall Agency Comments
OECA took issue with the overall OIG evaluation process, expressing concerns about the
conclusions reached in analysis, poor communications during the evaluation, and the belief that
data collected was incomplete or inaccurate. OECA also disagreed with the OIG assessment that
its oversight needed improvement. Specifically OECA stated that:
•	OIG inaccurately interpreted National EPA Enforcement Guidance and Policy.
•	OIG included facilities that were not classified as major facilities during all or part of the
evaluation period.
•	OIG did not acknowledge OECA's ongoing efforts to improve its records and reporting.
Despite OECA's numerous concerns with the underlying analysis, OECA stated it generally
accepted OIG's recommendations and was in the process of implementing them. OECA's
detailed responses, along with the OIG's evaluation, are provided in Appendix D.
The detailed OECA response focuses on denying existence of oversight issues, while agreeing to
implement most of the recommended actions. OECA's criticism of the evaluation for poor
communication and faulty analysis is rooted in OECA's rationale that written policies can be
ignored or interpreted to allow OECA "flexibility" to claim timely and appropriate performance
under almost all circumstances. OIG understands OECA's rationale; we simply do not accept
that it is valid. OIG's conclusion that OECA has not acted in a timely manner is based on
written policy and criteria that OECA prefers to ignore. In fact, one of OECA's corrective
actions will be to rescind the policy memorandum clarifying the standard for timely enforcement.
The OECA response is illustrative of the control environment that allowed the conditions
addressed in the report to exist. Management is responsible for communicating the objectives of
internal control and ensuring the organization is committed to sustaining an effective internal
control environment. Management's philosophy and operational style set the tone within the
organization culture. Culture is defined by management's leadership in setting values of
integrity and ethical behavior but is also affected by the relationship between the organization
and central oversight agencies. Management's commitment to establishing and maintaining
effective internal control should cascade down and permeate an organization's control
environment, which aids in the successful implementation of internal control systems. In our
opinion, the OECA response is a reflection of weakness in the overall management control
environment of the organization.
Inaccurate Interpretation of National EPA Enforcement Guidance and Policy
This is a disagreement over how to measure EPA's effectiveness ensuring the compliance with
the Clean Water Act and how accountable for achieving results it is. EPA's desire for total
flexibility undermines the use of internal controls to ensure timely and appropriate enforcement
response. OECA interprets the national enforcement guidance and policy, EMS, as granting it
23

-------
total flexibility about when and how to enforce against significant noncompliance. Using this
interpretation, OECA concluded that its response was "adequate" 93 percent of the time.
We carefully applied OECA's own guidance set out in the EMS to determine how well EPA
regions and States are fulfilling their enforcement responsibilities. The EMS represents OECA's
own enforcement principles for EPA regions and States. The EMS provides clear and consistent
guidance on what constitutes a timely enforcement response. In brief, the EMS states that a
formal enforcement response must be taken before the end of the quarter following the quarter in
which EPA and/or States designate a facility in SNC. The memorandum OECA wants to rescind
clarifies this point.
Inaccurate Data Analysis
OECA's response actually addresses the inaccurate data in their systems, rather than inaccurate
data analysis on the part of OIG. OECA objected to the records of some of the facilities we
included in our sample taken from their data system, PCS. We agree with OECA that their
systems contain inaccurate data and recommended that they develop a quality assurance program.
OECA requested that seven facilities in our review should be removed. We will remove one of
the seven. Decherd WWTP in Tennessee was not designated a major discharger until after our
study period. We have removed Decherd from our findings. We had included this facility in our
study because EPA listed this minor facility as being in SNC during our study period in the PCS
database. Also, Windermere and Munford Lagoon were not major facilities during all of our
review period although PCS showed them in significant noncompliance during that time. Both
facilities were in significant noncompliance for at least three quarters after they became majors.
Since the facilities did not receive timely action while they were major facilities, we will keep
them in our analysis. We disagree with EPA about the other four facilities.
OECA stated that we failed to acknowledge many SNC violations reviewed that were already
addressed under existing enforcement orders and compliance schedules. On the contrary, we
considered whether a facility was in "resolved pending" as indicated by EPA data systems and
data submitted to us by OECA.
OECA also stated that we retained several facilities in our review in spite of a known state-wide
data system problem that resulted in incorrect SNC determinations. Again, we disagree. We did
not evaluate the timeliness of enforcement actions at 25 of the 30 Michigan facilities due to the
state-wide data problem. According to Region 5 staff, Michigan's data system problems related
only to discharge monitoring reporting and compliance schedule reporting. For that reason, we only
included facilities in our analysis that had other types of violations. The five Michigan facilities we
analyzed had effluent violations for at least two consecutive quarters. Even though we did not
evaluate the timeliness of enforcement actions at the 25 facilities, we did report on the obvious
oversight problems that exist from a State having system with unreliable data for several years.
No Acknowledgement of Ongoing Efforts to Improve Records and Reporting
We included the efforts OECA mentioned in its response in the Noteworthy Achievements
section of the report.
24

-------
Appendix D
Detailed Agency Comments and OIG Evaluation
#
OECA Response,
Section/Page
OECA Comments
(Attachment 1 of its response)
OIG Response
1
At a Glance,
page 1
OECA's specific responses to each of the
findings and recommendations are detailed
below. The description of the
recommendations should be modified
accordingly.
See responses below.
2
At a Glance,
page 1
OECA questions the accuracy of OIG's
estimate of the pounds of excess pollutant
released. As discussed below, there is
sufficient reason to believe that the OIG's
selection of facilities used to calculate a
hypothetical estimate of pollutants discharged
is flawed due to OIG's inaccurate
interpretations of EPA's national enforcement
guidance. Further, the OIG erroneously
assumes that when an enforcement action is
concluded, compliance is immediate.
• To illustrate, the OIG presents an
estimate of the range of pollutants in
excess of permit limits released by using
data calculated for 45 facilities that the
OIG found to be in SNC for the 3-year
period from July 2002 through June 2005.
However, many of these facilities were
operating under consent orders that
provided a schedule for return to
compliance. As violating facilities
complete the necessary plant upgrades
allowing them to meet the original permit
limits, pollutant reductions are achieved.
Because of the infrastructure changes that
are often needed to correct compliance
problems, the OIG cannot expect that
pollutant reductions will be immediately
gained upon completion of an
enforcement action.
Our selection of facilities used to calculate
the estimate of pollutants discharged was
not flawed. Our estimates of excess
pollutants released represent actual effluent
pollutant concentrations as reported by
NPDES facilities and recorded in EPA's
database, OTIS.
We analyzed data from OTIS and PCS to
determine the excess pollutants released
from facilities in long-term SNC for effluent
violations. We calculated the excess
pollutant load by determining the pollutant
load each facility is permitted to discharge
and subtracting that load from the pollutant
load each facility actually discharged when
it violated its permit limits. We determined
the pollutant load actually discharged from
facility DMR information by multiplying
the actual effluent flow times the actual
effluent pollutant concentration times a
constant of 8.34. EPA uses this formula to
determine mass-based permit limitations
and was reviewed by staff from EPA's
Office of Wastewater Management. We
calculated the permitted pollutant load for
each facility using the same formula and
each individual facility's pollutant permit
limits. We summed the daily excess
pollutant loads for each facility over the
3-year time period from the third quarter of
2002 through the second quarter of 2005.
As such, our estimates would implicitly
consider any reductions being achieved as a
result of consent orders or plant upgrades.
Our analysis does not expect that pollutant
reductions are the immediate result of
enforcement actions. We did the analysis to
determine the impact on the environment
when a facility is not in compliance with its
NPDES permit. It may take years for a
facility to come back into compliance under
25

-------
#
OECA Response,
Section/Page
OECA Comments
(Attachment 1 of its response)
OIG Response



a consent decree. During that time, a
facility with effluent violations is still
discharging pollutants into the water above
its permitted limits.
3
At a Glance,
page 1
There is an error in the shaded background
summary - EPA "authorizes" (not "delegates")
states to administer the NPDES program.
The final report was revised to reflect this
comment.
4
Chapter 1, page 1
EPA Oversight of NPDES Compliance and
Enforcement Program, p. 2: The placement of
the statement, "EPA is expected to take formal
enforcement action when states fail to take
timely and appropriate action" in the first
paragraph of this section, which discusses
Clean Water Act (CWA) authority and the
NPDES program, implies that the CWA
mandates when EPA shall take enforcement
action. The CWA does not address this issue.
The statement itself is an accurate
representation of information presented in
the EMS. The statement was moved to the
section discussing the EMS criteria on
page 3.
5
Chapter 1,
pages 1-2
Furthermore; the statement inaccurately
represents EPA guidance on this issue (see the
August 25, 1986 James Barnes Memorandum
to the Regions, "Revised Policy Framework
for State/EPA Enforcement Agreements
(Barnes Memo)). The Barnes Memo
recommends consultation with a state to
determine whether the state is moving
expeditiously to resolve the violation ~ it does
not contemplate automatic formal Federal
action once a recommended deadline for state
action has passed. The Memo specifies that
timeframes are not intended to be rigid
deadlines for action. It explains that because
authorized states have primary responsibility
and EPA clearly does not have the resources
to take action on or review in detail any and
all violations, EPA will circumscribe its
actions to certain cases and areas and will take
action based on specific listed factors in the
Memo. Further, the Barnes Memo
acknowledges that because EPA will not, in
most cases, receive real time data, Regions are
not expected to be able to take direct
enforcement action following the exact same
timeframes as those that apply to the
administering agency. Finally, the Barnes
Memo does not require formal enforcement
action in every instance. The Memo
establishes that an appropriate response is to
be determined by the administering agency
based upon a consideration of what is needed,
and that the form of the enforcement response
must achieve compliance. The redraft
suggested below is an accurate interpretation
of EPA guidance and does not imply, as does
OIG's draft language, that immediate federal
The EMS was finalized in 1989, at least
2 years after the Revised Policy Framework
for State/EPA Enforcement Agreements
(Barnes Memo). The EMS constitutes a
system for translating compliance
information into timely and appropriate
enforcement actions. Also, EMS provides
the flexibility for each administering agency
to develop management procedures which
are best suited to its operations and
resources with the goal of most efficiently
translating compliance information into
timely and appropriate enforcement action.
Thus, the flexibility desired by OECA was
implicitly considered during development of
the EMS and the language regarding timely
and appropriate formal enforcement actions
to address SNC violations.
Any ambiguity regarding timely and
appropriate language in the EMS was
resolved in an October 6, 1999, OECA
memorandum that provided the Water
Enforcement Division's official
interpretation of the EMS's language
regarding the "begin date" for the period
allowed for a timely and appropriate
enforcement response to a SNC violation.
The memo further states that EMS requires
that a formal action must be taken to
prevent the SNC violation from being
reported on a second QNCR and, under
QNCR rules, this can be accomplished only
if the enforcement action is taken during
this "following" quarter. Further, the use of
26

-------
#
OECA Response,
Section/Page
OECA Comments
(Attachment 1 of its response)
OIG Response


action is required when the period for timely
state actions has passed, or that such action
must be formal.
•	Delete "EPA is expected to take formal
enforcement action when states fail to
take timely and appropriate action" from
first paragraph on page 2."
•	Add new paragraph after the two bullets
in the second paragraph of this section
that includes "EPA's guidance indicates
that EPA may consider taking direct
enforcement action where: a state
requests EPA action, where the state
enforcement response is not timely or
appropriate, in cases or program areas
setting national precedents, or where
there is a violation of an EPA order or
consent decree. In deciding whether to
take enforcement EPA will consider
whether: the case is nationally significant,
risk or damage to the environment or
public health is significant, the violator
stands to gain significant economic
benefit, or there are repeat patterns of
violations and violators."
•	Add a new paragraph for remaining text
beginning, "Compliance with the nation's
environmental laws. . ."
this "begin date" is consistent with the
timeframe for violation status calculations
PCS makes for the QNCR and SNC.
No change made.
6
Chapter 1, page 2
Types of Noncompliance, p. 2: OIG's
description of the QNCR regulations does not
distinguish between reportable noncompliance
(RNC) and significant noncompliance (SNC).
Reporting RNC at NPDES majors is a
regulatory requirement. Identifying,
addressing, and tracking SNC violations (a
subset of RNC) is not a regulatory
requirement - it is a management tool used to
prioritize violations and focus enforcement
resources. In contrast to a regulatory
requirement, there is inherent flexibility - by
design ~ in the application of a
policy/management tool.
• "Revise citation as follows" . . .
Section 123 .45(a)(2)."
The report was revised to include the
detailed citation.
7
Chapter 1,
pages 2-3
Enforcement Management System Criteria, p.
3: In this chapter, OIG acknowledges the
flexibility within the EMS for the permitting
authority to exercise discretion in deciding
which of a range of possible responses (no
response, informal action, formal action) to
take in addressing violations, including SNC
violations. That acknowledgment does not
carry through the end of page 3 or through the
According to the EMS, facilities with SNC
violations must receive a formal
enforcement action from the administering
authority that is timely and appropriate, or
return to compliance within the quarter
following the SNC violation. If formal
action is not taken, the State or EPA is
expected to produce a written record clearly
justifying why an alternative action (other
27

-------
#
OECA Response,
Section/Page
OECA Comments
(Attachment 1 of its response)
OIG Response


rest of the draft report. For example in
numerous places on pages 6-8, OIG's
findings are based solely on whether "formal"
enforcement actions were taken - in contrast
to its earlier acknowledgement on p. 3 that a
range of responses are available. The EMS
includes the expectation that SNC violations
receive a formal enforcement action.
However, it also acknowledges that there may
be circumstances when formal enforcement
action is not taken and the administering
agency is expected to have a written
justification for why the alternative action was
more appropriate.
• "Replace "formal enforcement action"
with "enforcement action" at page 3 and
pages 6-8.
than a formal action) was more appropriate.
If the State, as the NPDES program
authority, does not take timely and
appropriate formal enforcement action, EPA
is expected to take a formal enforcement
action. Our file and database review at
EPA and States found no written
justifications for not taking formal
enforcement actions.
No change made.
8
Chapter 1, page 3
Compliance and Enforcement Data Systems
and Reports, p. 4: The second and fourth
sentences in the third paragraph need to be
rewritten to distinguish between
"noncompliance" and "reportable
noncompliance."
•	Revise second sentence as follows: "The
report flags NPDES major facilities that
were in reportable noncompliance with
permit or enforcement order requirements
during the previous six months."
•	Revise fourth sentence as follows:
"reportable effluent violations."
While our original statement is accurate, we
made these revisions in our final report.
9
Attachment 1,
Chapter 1, page 3
Scope and Methodology, p. 5, 6, 8: The total
of 132 facilities stated in paragraph 2 on p. 5
as well as in paragraph 4 on p. 15 in Appendix
A does not match the total of 128 facilities
reflected in Table A-l in Appendix A.
Further, at pages 6 and 8 the following
sentences are inconsistent:
•	"At the remaining 35 facilities, none of
the actions that we could assess were
timely based on the criteria in EPA's
EMS" (page 6),
•	"We were able to assess 45 of the 57
actions at 30 facilities for timeliness and,
based on EMS criteria, none of the 45
was timely" (page 8),
•	We could not determine the timeliness of
the remaining 12 formal actions at 10
facilities because available information
was not adequate" (page 8).
The total numbers of facilities represented in
the three bullets above are inconsistent (e.g.,
30 facilities, 35 facilities and 40 facilities).
•	Please clarify, correct and provide
Appendix A was revised so that the
facilities in Table A-l add to 132 facilities.
We evaluated the timeliness of actions at
35 total facilities. Some facilities received
more than one enforcement action. Each
action was assessed individually, thus one
facility may have had an action judged
untimely and another action for which we
could not assess the timeliness. Thus, 45
actions at 30 of the 35 facilities were
untimely. We could not determine the
timeliness of the remaining 12 actions that
occurred at 10 of the 35 facilities. The
apparent inconsistency stems from the
overlap that occurred during our analysis
because facilities may have had more than
one action. Thus, an action was classified
as either untimely or not assessed. In
contrast, a facility with more than one
action could be included as both untimely
and not assessed. We added clarifying
language in the report.
28

-------
#
OECA Response,
Section/Page
OECA Comments
(Attachment 1 of its response)
OIG Response


accurate facility and enforcement action
totals.

10
Chapter 2,
pages 3-4
"EPA Guidance Misinterpreted and
Inadequate, p. 6 - 7: OECA strongly disagrees
with OIG's statements that the EMS guidance
that describes timely and appropriate
enforcement actions is inadequate. On the
contrary, the EMS provides fully adequate
guidance on timely and appropriate
enforcement responses for various types of
violations, including those designated as SNC.
OIG acknowledges at page 6 that
"Flexibility is needed in any national
enforcement program" yet contradicts this
statement by continuing to apply the EMS as a
set of rigid requirements (rather than flexible
guidance). The OIG fails to recognize that a
flexible enforcement response is necessary to
manage the NPDES enforcement program.
The need for flexibility is even greater today
than when the guidance was first established
because of the significant expansion of the
universe of regulated entities covered by the
NPDES program without a corresponding
increase in EPA resources.
On page 6, OIG states that "EMS
guidance is unclear regarding appropriateness
of enforcement actions ..." OECA strongly
disagrees - the EMS is very clear that an
appropriate response should,"... reflect the
nature and severity of the violations, and,
unless there is supportable justification, the
response must be a formal enforcement action,
or a return to compliance by the permittee . . .
In the rare circumstances when formal
enforcement action is not taken, the
administrating agency is expected to have a
written record that clearly justifies why the
alternate action (informal enforcement action
OECA's comment is directly contradicted
by its October 6, 2006, response, which
states "that its guidance documents are
indefinite in regard to the timeliness
standard."
Our report states that EPA has indistinct
guidance to determine if actions are
appropriate because the guidance does not
state how expeditiously facilities should
come back into compliance after an action
is taken.
Our report states that we believe the
guidance is clear on the definition of
"timely." However, we were given
inconsistent interpretations of what EPA
considers timely.
EMS states a timely formal enforcement
action must be taken by the end of the
quarter following the SNC violation. For
instance, if a facility experiences an SNC
violation in February of the first quarter, a
formal enforcement must be taken by the
administering agency by June 30 of the
second quarter.
The October 6, 1999, memorandum
Drovidcs clarification of existins EMS
language concerning timely and appropriate
enforcement response to SNC. The memo
represents the Water Enforcement
Division's official interpretation of the EMS
language concerning timely and appropriate
enforcement. OECA states that the memo
has not been rescinded. OECA has chosen
not to implement the memo, but the memo
is the current guidance. We are concerned
that OECA is more concerned about current
practice than implementing current
guidance.


or permit modification) was more
appropriate" (see EMS, Chapter 11,
Attachment B, p .2 and page 7 of this
document).
On pages 6-7, the OIG states that
"EMS guidance is clear with regard to
timeliness" in one paragraph yet relies on a
subsequent October 6, 1999 OECA
memorandum in another paragraph to define
what is timely. The OIG relies on this
memorandum and not the EMS guidance that
reflects current practice. OECA agreed in its
October 2006 meeting with OIG to rescind the
1999 OECA memorandum that conflicts with
the EMS. OECA also stressed that 1999
29

-------
#
OECA Response,
Section/Page
OECA Comments
(Attachment 1 of its response)
OIG Response


memo is not being implemented by
Headquarters and the Regions.

11
Chapter 2, page 4
OECA disagrees with the OIG's conclusions
on page 7 regarding whether the response to
East Chicago was appropriate. The
implication that there was inadequate
enforcement attention at this site between
1988 and 2004 is not valid (see attachment 2
for a PCS list of all formal and informal
actions at the facility, including available
compliance schedule milestones).
It is unclear how the OIG calculated
the range of excess pollutant loadings for East
Chicago. It is unclear if the OIG used the
actual flow data taken from the DMRs during
its file review, or used design flow data from
PCS. Flow data are not available in OTIS.
Since the 1988 consent order, EPA and/or
Indiana have issued the following formal
actions: a pretreatment administrative order
in January 1993, a State-agreed order in
November 2003 (not shown in OECA's
attachment 2), and a pretreatment
enforcement action in 2004. A stipulated
court order was completed in October 1991.
All other actions included in the attachment
are informal actions, such as phone calls
and warning letters.
Despite these actions, East Chicago had
12 consecutive quarters of effluent
violations from July 2002 through June
2005. We evaluated the agreed order and
determined it was untimely because it
addressed violations from March and April
2000. We could not make a determination
on the pretreatment enforcement action
taken in 2004 due to a lack of information
in PCS and the data files.
As stated in our report, we question the
appropriateness of an enforcement action
taken in 1988 that, according to OECA,
"renders all effluent violations resolved
pending since that time," while the facility
continues to violate permits limits and
discharges to an impaired waterbody.
For this facility, our estimate of pollutant
loadings used the design flow. The report's
scope and methodology clearly lays out how
we calculated the excess pollutant loadings.
12
Chapter 2, page 5
Insufficient Formal Actions at 22 Facilities, p.
8: OECA is reluctant to accept this finding
without further evaluation under a correct
interpretation of the guidance. This reluctance
is based on OECA's experience reviewing the
facilities that the OIG examined in its August
2006 draft report wherein its findings were
dramatically different than OIG's findings
(e.g., 53 or 93% received an appropriate
enforcement response). As explained in
OECA's response to the August 2006 draft
report, OIG's inaccurate interpretation of the
EMS, failure to consider whether a facility
was in "resolved pending" status, and the
exclusion of relevant information, results in
inaccurate findings. The same problems exist
in this draft report.
See OIG response to comments 7 and 10
above.
We found that 22 facilities (21 facilities
once Decherd is removed, see response to
comment #23) in SNC received insufficient
formal actions and 30 facilities did not
receive timely actions. We stated that we
could not judge the appropriateness of the
actions because OECA had not clearly and
unambiguously defined how quickly a
facility must come into compliance. OECA
stated that 53 facilities received an
appropriate response, but it failed to state 53
received a timelv response.
We considered whether a facility was in
30

-------
#
OECA Response,
Section/Page
OECA Comments
(Attachment 1 of its response)
OIG Response



"resolved pending" as indicated by PCS or
OTIS and OECA submitted data. We
found that 13 facilities had received no
formal action during our review period but
had received actions prior to the start of our
review period. We considered these actions
in our review. However, we found that all
13 facilities had unaddressed SNC
violations during our review period.
As stated in Chapter 3, OTIS data for
Regions 4, 5, and 6 do not show facilities
with active enforcement actions as resolved
pending even though they are required to do
so. Thus, OECA's data systems do not
show the correct enforcement status of
facilities, as required by regulation.
13
Chapter 2, page 5
OECA bases its findings on follow-up
discussions with Regional staff - to OECA's
knowledge it does not appear that the OIG
based its findings on follow-up discussions
with Regional staff.
The fact that we disagree with OECA on
many of the facts and inferences in this
report does not imply that we ignored EPA's
views. On the contrary, we carefully
reviewed all written comments and verbal
comments made at the numerous meetings
we attended with OECA and regional staff.
Following completion of field work and
submission of our discussion draft to OECA
on May 26, 2006, we met with OECA
and/or regional staff on June 7, June 29,
October 24, October 26, and November 8,
2006. Further, OECA submitted data on
November 16 (in response to the November
8 meeting with OECA and regional staff)
that reflected consultation with regional
staff.
14
Chapter 2, page 5
OECA disagrees with the statement that"...
facilities with SNC violations must receive a
formal enforcement action ... or a return to
compliance within the quarter following the
SNC violation." OIG's statement, excerpted in
part, from the EMS implies that every SNC
violation requires a formal enforcement
action. In fact, the EMS provides flexibility to
Regions and states to address SNC - the EMS
allows that an appropriate response may be
formal or informal, with justification, or that a
facility may return to compliance on its own.
As stated previously, the OIG's draft report
does acknowledge that informal actions are an
option; however, the report focuses solely on
whether EPA or the states took formal
enforcement action at the 57 facilities. By
only evaluating whether a formal enforcement
action had been taken, the evaluation ignores
the provisions in the EMS which allow an
See OIG response to comments 7 and 10
above.
Alabama and/or EPA should have issued a
formal enforcement action by the end of
September 2004. The informal action was
issued after the facility had been in SNC for
four consecutive quarters.
31

-------
#
OECA Response,
Section/Page
OECA Comments
(Attachment 1 of its response)
OIG Response


informal enforcement response. The EMS
recognizes that an informal enforcement
response may be the most appropriate
response given the circumstances of the case.
Informal responses are used successfully by
EPA and states to address SNC violations.
• For example, Alabama issued a Notice of
Violation (NOV) to Centerville to address
chlorine total residual. The NOV resulted
in the permittee changing its treatment
technology for disinfection and
submitting a schedule for making such
change. Clearly, this informal action
induced the permittee to take corrective
action.

15
Chapter 2, page 5
The draft report fails to acknowledge the
compliance status classification of "resolved
pending," i.e., a permittee in compliance with
enforcement order and on track to achieve
compliance pursuant to a compliance schedule
but has not yet achieved full compliance with
permit conditions. OECA believes that the
OIG misinterpreted SNC violations for
several facilities as being "unaddressed by
enforcement action" when in fact, they were
addressed. Below are just a few examples of
facilities that were resolved pending during
OIG's 12 quarter review period :
We considered whether a facility was in
"resolved pending" as indicated by PCS or
OTIS and OECA submitted data. We found
that 13 facilities had received no formal
action during our review period but had
received actions prior to the start of our
review period. We considered these actions
in our review. However, we found that all
13 facilities had unaddressed SNC
violations during our review period.
As stated in Chapter 3 of our draft report,
OTIS data for Regions 4, 5, and 6 do not
show facilities with active enforcement
actions as resolved pending even though
they are required to do so. Thus, OECA's
data systems do not show the correct
enforcement status of facilities, as required
by regulation. To overcome this issue, OIG
utilized OECA's own extensive data
collection efforts provided on November 16,
2006.
See OIG response to comments 16 to 19
below.
16
Chapter 2, page 6
City of Attalla, AL - Alabama issued an
administrative consent order on February 26,
2002, to this facility addressing violations of
effluent limits for BOD5 mass and
concentration, TSS mass, TSS % removal,
BOD5 % removal, pH, and Toxicity, and for
Sanitary Sewer Overflows. The consent order
required return to compliance within 1095
days upon the effective date of the order.
When problems persisted, Alabama filed a
complaint in state court on February 10, 2003
resulting in a consent decree which was
finalized on May 13, 2005. Alabama did not
wait until February 2005 (1095 days) to
The consent decree issued on May 13, 2005,
is an escalation of an existing action. Thus,
it is unclear if this escalation is timely
according to the EMS criteria. However, it
should be noted that the February 26, 2002,
action, which preceded our evaluation time
period, would be considered untimely since
it addressed 27 sanitary sewer overflows
reported from January 1999 through
October 2001 and 12 violations of
biochemical oxygen demand and total
suspended solids from June through
November 2001. This facility had 11
quarters of effluent violations from July
32

-------
#
OECA Response,
Section/Page
OECA Comments
(Attachment 1 of its response)
OIG Response


escalate formal enforcement when it believed
a stronger approach was necessary to assure
the facility will address its problems
expeditiously.
2002 through June 2005.
17
Chapter 2, page 6
Lafayette STP, TN- Tennessee issued an
administrative order against this facility in
April 2002 to address violations of effluent
limits for Nitrogen, Ammonia, TSS, fecal
coliform, and DO. The order required
expansion of the plant (completed in 2004) to
achieve compliance. The Lafayette STP was
not a major facility until the 3rd Quarter of
2004. The STP continued to have problems
with Nitrogen, Ammonia, and Settleable
Solids. It is not uncommon for violations to
occur during plant expansion and start-up
because it takes time for the activated sludge
to form, to establish optimum activated sludge
wasting rate, mix liquor concentration, and to
reach a steady state of operation. When
violations persisted after the start-up of the
new plant and allowing for a period of time to
reach steady state of operation, Tennessee
issued a second administrative order in May
2006.
The Facility Registry System, which relies
on PCS data, lists Lafayette as a major since
August 2002. (See Comment #23)
The April 2002 administrative order did not
address settleable solids. During our review
period, the facility was in SNC for seven
quarters for settleable solids that were not
addressed by formal enforcement actions.
Moreover, this facility had three
consecutive quarters of SNC effluent
violations for settleable solids after third
quarter 2004, when OECA claims this
facility became a major. Thus, even under
OECA's facility classification, this facility
should have received a formal enforcement
action before the end of second quarter
2005.
18
Chapter 2, page 6
Austin, IN- Per the PCS comment field for
this facility, the state's 2002 order specifically
addressed the NPDES schedule violations.
The only issue was that the order was not
properly linked in PCS to show that the
schedule violations were resolved pending.
Austin Municipal Wastewater Treatment
Plant had at least four consecutive quarters
of compliance schedule violations after the
February 2002 Consent Order. These SNC
violations were unaddressed by enforcement
actions. According to OECA, the state's
2002 Consent Order addressed the NPDES
schedule violations that occurred after the
order was issued. If issuing an
administrative order resolves future
compliance schedule problems, we do not
understand how OECA has any facilities in
SNC for compliance schedules violations
and do not understand why it would be a
category of SNC.
19
Chapter 2, page 6
Hillsboro, TX- The city of Hillsboro had
multiple effluent violations during 2002.
Texas asked Region 6 to issue an
administrative order addressing these
violations while the state developed an
enforcement action. An administrative order
was issued by EPA Region 6 on March 25,
2003. When the city failed to respond
adequately to the order, Region 6 issued
another administrative order on June 12, 2003,
which also addressed continuing effluent
violations. The city submitted an acceptable
compliance plan on July 17, 2003, which was
monitored closely while Texas continued to
OIG's analysis indicates that both of these
enforcement actions were untimely. The
March 2003 Administrative Order
addressed violations from January 2002 to
October 2002. The June 2003
Administrative Order addressed violations
from November 2002 to March 2003.
33

-------
#
OECA Response,
Section/Page
OECA Comments
(Attachment 1 of its response)
OIG Response


develop its enforcement action. The permittee
has been in resolved pending status from
April 2004 through the present except for the
quarter of April through June 2005 when they
had additional effluent violations. These
violations were addressed by a state
administrative order issued on July 14, 2006.
This action required the facility to come into
final compliance with effluent limits no later
than October 12, 2006. The facility complied
with this requirement and has had no further
violations to date.

20
Chapter 2, page 7
OIG's draft report still includes Michigan
facilities (e.g., Flint Ink and Great Lakes
Tissue) even though a known state-wide data
system problem, discussed at length with the
OIG in response to its August 2006 draft,
resulted in incorrect SNC determinations and
subsequent management decisions not to
respond to some effluent violations. DMR
data input issues in Michigan existed from
October 2003 through September 2005. As
such, reports of violations occurring during
this timeframe, including non-reporting
violations, are questionable. OECA believes
EPA Region 5 appropriately exercised its
enforcement discretion to make the decision
not to respond.
OECA's earlier comments only referred to
State-wide data system problems involving
DMRs and compliance schedule reporting.
As a result of those comments, we
eliminated 25 of the 30 Michigan facilities
from our timeliness assessment. We
retained five Michigan facilities that had
effluent violations in our timeliness review.
If PCS coding issues extend to effluent
violations, as OECA now suggests, we are
even more concerned about the integrity of
EPA's data systems. However, without
additional evidence of those newly reported
data problems, we are retaining these five
cases in the final report.
21
Chapter 2, page 7
• For example, the 12 consecutive quarters
of effluent violations cited in OIG's draft
report at Flint Ink were actually toxicity
violations that occurred for one quarter
(February and March 2000). As explained
to the OIG on several occasions, these
violations continued to appear due to
improper coding in PCS. Further,
Michigan worked with Flint Ink to find
the source of the toxicity and discovered
an issue with a water additive. Flint Ink's
permit was subsequently modified to
withdraw permission to use the additive
and the company ceased use. A multi-
media inspection conducted by Region 5
in 2006 confirmed cessation of the
additive and that the company was
moving a majority of its process out of
state thus eliminating all discharges to
surface waters. The toxicity violations
were addressed and resolved by state
action (compliance assistance and permit
modification), and the general non-
reporting violations were a direct result of
Michigan's data system issues.
OECA reported that the known State-wide
data system problems involved only
reporting issues such as discharge
monitoring reporting and compliance
schedule reporting. Flint had 12 quarters of
effluent violations during our review period.
Flint was still in SNC for effluents
violations in September 2006 according to
EPA's data system, ECHO. OECA's data
provided on November 16, 2006, did not
state that the 12 quarters of effluent
violations were toxicity violations from
February and March 2000. OECA's
response is contradictory. OECA states that
the violation is due to improper coding.
Then it states there was a toxicity problem,
and that it was addressed and resolved
through State action. From OECA's
response and our analysis, we believe Flint
was in SNC and did not receive timely
action.
34

-------
#
OECA Response,
Section/Page
OECA Comments
(Attachment 1 of its response)
OIG Response
22
Chapter 2, page 7
• The two consecutive quarters of mercury
violations at Great Lake's Tissue cited in
OIG's draft report were accurately
portrayed. However, since they occurred
at the very end of OIG's review period,
OECA does not understand how the
conclusion was reached that no action
was taken. PCS indicates, and the Region
has confirmed, that Michigan referred the
case to the state Attorney General in July
of 2005.
A timely enforcement action should have
been taken by Michigan to address the
mercury effluent violations at Great Lakes
Tissue by June 2005, which is prior to the
end of our evaluation period.
23
Chapter 2,
pages 7-9
OIG completely disregarded OECA's October
2006 comments to the August 2006 draft
report relating to a number of minor facilities
in Regions 4 and 6 that were inaccurately
included in his analysis as majors- these
facilities were not classified as majors during
the analysis and therefore not subject to SNC
screening during all or part of the OIG's
evaluation period.
Region 4 has reconfirmed that 3
facilities in Tennessee (Lafayette STP,
Decherd City STP and Munford Lagoon) were
not major facilities during all or part of the
OIG's 12 quarter review period. Lafayette did
not become a major facility until the 3rd
quarter of 2004 when the plant expanded.
Two other Region 4 facilities in TN (Decherd
City STP and Munford Lagoon) were not
classified as major facilities until the 4th
Quarter of 2004 and the 4th Quarter of 2005,
respectively. Neither of these facilities had
SNC violations reported in the QNCR during
the OIG evaluation period and therefore
should not have been subject to SNC
evaluation by the OIG (see attachment 2 for
letters from Region 4 files documenting status
change dates).
Region 6 has reconfirmed that 4
facilities in Texas (New Boston, SWS
Holdings, Texas Dept. of Criminal Justice,
and Windermere Utility) were not major
facilities during the OIG's 12 quarter review
period. Although PCS is the legal database of
record for the NPDES program, dates of status
change are not tracked in PCS - the date
associated with a change in facility status
from a minor to a major is manually tracked in
files at the Regional office. For three of the
four Texas facilities (New Boston, SWS
Holdings, Texas Dept. of Criminal Justice),
the OIG's conclusions were based on dates it
found in the Facility Registry System (FRS) -
an integrated, comprehensive, multi-media
We removed Decherd (TN0020508) from
our sample. We included Decherd, as well
as the other facilities OECA questions, in
our sample because EPA databases showed
that facility was a major facility in SNC
throughout our review period. However,
our findings regarding the other six facilities
are still valid.
We obtained data on the status of the six
facilities from the Facility Registry System.
According to Office of Environmental
Information staff and data documentation,
the Facility Registry System pulls
information from PCS. The Facility
Registry System would only show that a
facility is a major if PCS was updated and
also considered it a major. The Facility
Registry System shows the status of facility
(major or minor) and the date in which the
last change was made in the Facility
Registry System. Office of Environmental
Information staff verified that the date the
information was last updated would only
change if the data in PCS changed.
The Facility Registry System confirms that
Lafayette STP (TN0020877) has been a
major since August 2002. Even using
OECA's data interpretation, Lafayette had
three consecutive quarters of SNC effluent
violations for settleable solids after
becoming a major. This facility did not
receive a timely formal enforcement action
to address those SNC violations.
According to the Facility Registry System,
the Texas Dept. of Criminal Justice
(TX0031577) has been a major since
November 2001; New Boston (TX0026018)
has been a major since May 2002; SWS
Holdings (TX0070955) has been a major
since August 2002; Windermere
35

-------
#
OECA Response,
Section/Page
OECA Comments
(Attachment 1 of its response)
OIG Response


data system maintained by EPA's Office of
Environmental Information (OEI). OEI staff
confirmed that FRS does not track dates
associated with a change in facility status - it
tracks dates of permit application receipt and
issuance. Thus, it is not possible to determine
when a facility became a major by looking in
the FRS. For example, the August 30, 2002
date that the IG based its conclusion on for
SWS Holdings was the date the permit
application was received, not the date the
facility became a major. FRS is not the legal
database of record for NPDES program. It
should be noted that the new ICIS-NPDES
data system will improve on the current
functionality available in PCS by providing a
"begin date" and "end date" to track the
conversion. In addition, as a result of the State
Review Framework project, the Integrated
Data for Enforcement Analysis System
(IDEA) now contains quarterly "snapshots" of
the major/minor and active/inactive facility
status of the NPDES permitted universe. This
feature is an additional source of historical
information that OECA now can access as
needed.
For one of the four Texas facilities
(Windermere Utility), the OIG based its
conclusion that the facility was a major on the
fact that the facility has a design flow of 2
MGD. EPA's definition of a major municipal
facility is a facility with a design flow > 1
MGD, however, this facility is not a
municipality. It has an SIC code of 6552 and
is therefore subject to EPA's definition of
major (which is a complex formula
considering a number of factors) for an
industrial facility (see attachment 2 for letters
from Region 6's files documenting status
change dates).
(TX0074853) has been a major since March
2004; and Munford Lagoon (TN0062499)
has been a major since September 2004.
Windermere had three consecutive quarters
of SNC violations after March 2004 that
were not addressed with formal
enforcement actions so it did not receive
timely action. Similarly, Munford Lagoon
had three consecutive quarters of SNC
violations after September 2004 that were
not addressed with formal enforcement
actions.
As additional evidence, we spoke with the
consulting engineer for the City of New
Boston, who stated that New Boston has
been a major for at least 10 years.
24
Chapter 2, page 9
Untimely Enforcement at 30 Facilities, p. 8 -
9: OECA is reluctant to accept this finding
because of OIG's misinterpretation of the
EMS timeliness standard.
See comments 25 to 27 below.
25
Chapter 2, page 9
As noted above, the OIG relies on a 1999
memorandum in spite of OECA's explanation
that the timely standard in the memorandum is
not being implemented. OECA stated in
October 2006 that the timely standard needs to
be clarified and we will rescind the 1999
memo.
We relied on the 1999 memorandum
because it provides the Water Enforcement
Division's official interpretation of the EMS
language concerning timely and appropriate
enforcement. OIG does not believe
rescinding the memo will clarify the
timeliness standard. On the contrary,
rescinding the memo will make the
timeliness standard open to interpretation.
36

-------
#
OECA Response,
Section/Page
OECA Comments
(Attachment 1 of its response)
OIG Response
26
Chapter 2, page 9
The OIG ignores flexibility in the EMS
language regarding timeliness (see Chapter II,
Attachment B). The purpose of guidance, such
as the EMS, is to provide recommendations
and set program expectations - not establish
regulatory requirements (see Appalachian
Power Co. v. EPA, 208 F. 3d -1015 (D.C.
Cir. 2000) and Barrick Goldstrike Mines Inc .
v. Browner, 215 F.3d 45 (D C . Cir. 2000),
finding that EPA guidance cannot have the
binding effect of a rulemaking). The OIG
continues, however, to treat the
recommendations in the EMS as rigid
requirements on the Agency.
Our evaluation does not advocate using the
EMS as regulatory requirements. It simply
uses OECA's own program principles to
assess how well the Agency is issuing
timely and appropriate formal enforcement
actions for long-term SNC violations. In
our view, OECA needs to have criteria in
place so that it can provide adequate
oversight to region and State programs.
27
Chapter 2,
pages 9-10
The OIG fails to take into account the time
needed to work with a state, gather more
evidence to support a case, allocate resources
to an action and negotiate complex corrective
measures to resolve noncompliance. The OIG
does not acknowledge that state enforcement
processes and timelines must be considered in
determining reasonable timeliness. To
illustrate, many states have the authority to
issue monetary penalties within a compliance
order. Issuance of such an order may require
longer time frames than in the EMS due to
public comment and participation
requirements, or because a hearing is
scheduled, or because of complex negotiation
schedules. Thus, judgments on what is a
reasonable time table for action must
ultimately be case-specific in consideration of
complex compliance problems that may
require long term studies and complex
injunctive relief (see Barnes Memo, Criteria
for Direct Federal Enforcement in Delegated
States, at pages 21 - 25).
See OIG response to comments 7 and 10
above.
The OIG's evaluation applies the
programmatic principles set forth in the
EMS to determine how well EPA regions
and States are fulfilling their enforcement
responsibilities. The EMS represents
OECA's own enforcement principles for
EPA regions and States. The EMS also
provides the flexibility for each
administering agency to develop
management procedures which are best
suited to its operations and resources with
the goal of most efficiently translating
compliance information into timely and
appropriate enforcement action. Thus, the
flexibility desired by OECA, to consider
many of the issues mentioned, is implicitly
considered in the EMS. We appreciate the
need for flexibility; however, we believe
that OECA needs to have criteria in place so
that it can provide appropriate oversight to
region and State programs.
28
Chapter 2,
page 10
• For example, it is incorrect for OIG to
conclude on page 8 of the draft report that
EPA's Administrative Order against
ConocoPhillips was untimely. There are
complex selenium water quality standard
and permitting issues associated with this
facility. EPA was in extensive
negotiations with state partners, as well as
Fish and Wildlife Service and the facility
to resolve the complex permitting issues.
The flexibility inherent in EPA's
enforcement guidance is critical to being
able to account for such complex
circumstances.
EPA issued an Administrative Order against
ConocoPhillips Company on August 14,
2003, to address effluent violations for
selenium beginning July 2002. The action
was untimely because it was not taken by
December 2002 (the end of the next
quarter), as required by EMS. According to
PCS, the facility continued to exceed
selenium permit limits through June 2005.
37

-------
#
OECA Response,
Section/Page
OECA Comments
(Attachment 1 of its response)
OIG Response
29
Chapter 2,
page 10
• For example, the OIG states on page 8 of
the draft report that it could not determine
timeliness of 12 formal actions involving
10 facilities because the available
information was not adequate.
Furthermore, the OIG states on page 9 of
the draft report that for Columbiana
WWTP, AL, timeliness could not be
assessed because the action was not
linked to the violation. OECA does not
understand this statement given that
Alabama provided compliance and
enforcement files containing a copy of a
Consent Order, Complaint and Consent
Decree for this facility to the OIG during
its onsite file review on February 6-7,
2006 and the OIG indicates that
Alabama's files were 100% complete in
Table 3-1 on page 11 of the draft report.
As stated in the report, we could not
determine the timeliness of the remaining
12 formal actions at 10 facilities because
available information was not sufficient.
Specifically, the enforcement actions were
not directly linked to the SNC violation
addressed or when the SNC violations
occurred. Without this information, we
could not determine whether the action was
timely.
Alabama did have files on all eight facilities
from our sample. The Consent Decree was
in the file. However, the Consent Decree
simply accelerates an existing compliance
schedule for a Consent Order issued on
March 21, 2002. The language in the
document does not directly link the action
to an SNC violation. Therefore, we could
not address timeliness.
30
Chapter 2,
page 10
It is not clear why the IG did not take
advantage of the Watch List for its analysis.
The Watch list and associated data provides
much better insight related to case-specific
circumstances and OECA's tracking of
enforcement timeliness. The OIG was
provided access to the Watch List, but it is
unclear whether it was used.
The OIG evaluated whether EPA conducted
(1) timely enforcement on NPDES major
facilities in SNC, and (2) proper oversight
over regions and States. The Watch List is
derived from EPA's data systems. To avoid
errors, we utilized the original data in
EPA's data systems. Our methodology is
presented in Appendix A.
31
Chapter 2,
page 10
Timely Enforcement Helps Minimize Excess
Pollutant Discharges, p. 9: See OECA
response at page 3, At A Glance, concerning
the accuracy of the pollutant reduction
estimate presented here.
See OIG response to comment 2 above.
32
Chapter 2,
pageslO-11
Recommendation 2-1, p. 9: Clarify and
enforce EMS guidance to ensure that timely
and appropriate formal enforcement actions
are taken against NPDES facilities in SNC.
OECA Response: OECA concurs with the
recommendation to clarify its NPDES
timeliness guidance. As discussed with OIG,
OECA will rescind the 1999 OECA
memorandum in conflict with the EMS and
will discuss this with the Regional NPDES
Enforcement Branch Chiefs at the national
NPDES meeting in April, 2007. OECA
disagrees, however, with the OIG's
commendation to "enforce EMS guidance."
The EMS is a management tool which
facilitates evaluation and performance review.
It is not a set of rigid regulatory requirements
which EPA imposes on the states or Regions
as the use of the term "enforce" suggests.
Rescinding the guidance without a
satisfactory replacement will not "ensure
that timely and appropriate formal
enforcement actions are taken against
NPDES facilities in SNC." If OECA
rescinds the 1999 memorandum, it will need
to explain how it will unambiguously define
timely and appropriate enforcement.
We understand OECA's concerns about the
use of the word "enforce" in the
recommendation. We will change the word
"enforce" to "implement" in the final report.
38

-------
#
OECA Response,
Section/Page
OECA Comments
(Attachment 1 of its response)
OIG Response
33
Chapter 3,
page 11
Chapter 3: Inadequate Records and Reporting
Inhibit EPA Oversight of NPDES Major
Facilities, p. 10 - 13. Compliance and
Enforcement Files Are Incomplete, p. 10: The
authorized states are responsible for keeping
accurate records. As such, EPA does not
require that all information be stored in
duplicate in the Regional offices. The OIG
appears to assume that EPA should have hard
copies of all state files. This redundancy is
neither practical nor efficient. EPA has the
ability to request information at any time and
has the ability to audit state files. The State
Review Framework (SRF) established a file
review protocol that will be implemented in
all 50 states by the end of FY 2007. When a
state is not keeping accurate records (e.g.,
inspection reports or enforcement actions), the
SRF process will identify this and formal
recommendations and milestones will be
made to ensure better file management. To the
extent that violations or problems noted in
files are not in the databases, the SRF process
will also address this.
An accurate history of the compliance and
enforcement activities at a facility is
important for oversight and making future
enforcement decisions. The lack of
accurate information inhibits EPA's ability
to provide effective oversight to NPDES
major facilities and thus protect human
health and the environment from excess
levels of toxic or harmful pollutants.
We recognize that the State Review
Framework may help address file
deficiencies at States noted in this report.
However, only the active oversight and
management of the State Review
Framework process will result in
improvements. It is not clear what steps
EPA plans to take to improve its oversight
and management in this area.
34
Chapter 3,
page 11
EPA's Enforcement Data Systems Are
Inaccurate, p. 11 - 12: OECA does not agree
with the statement that EPA's data systems are
inaccurate. The OIG provides no context
supporting this broad statement but rather
appears to make this statement based upon a
specific, known problem in one state
(Michigan). The OIG should indicate that
EPA requires states to enter at least 95% of
discharge monitoring report (DMR) and
effluent limit data (which generate SNC
status). Historically there are only two states
that do not meet or come very close to this
goal - Michigan, and Oregon. As EPA
provides CWA data to hundreds of thousands
of users via the ECHO web site, it is
unfortunate that the OIG report classifies the
data systems as inaccurate because there are
data translation issues in two of fifty states.
The ECHO web site clearly caveats these
problems. These caveats should have first
alerted OIG staff that Michigan data should be
avoided and could not be used to draw
accurate conclusions about facility SNC
status. In addition, OECA, and the Regional
office pointed out to the OIG staff on
numerous occasions that the Michigan data
should not be used in the OIG study; however,
the OIG decided to include the flawed data
anyway. In regard to the SNC status in other
Our findings about NPDES program
enforcement data systems being inaccurate
go well beyond our findings in Michigan.
Our report contains several examples of
EPA's data system problems, including
several that EPA has acknowledged
elsewhere.
EPA's data systems do not accurately
reflect the SNC status of facilities. Once a
formal enforcement action is issued for an
SNC violation, a facility should be
designated as "resolved pending" for that
violation, according to Title 40, Code of
Federal Regulations, Section 123.45.
However, OECA states that Regions 4, 5,
and 6 (the three regions reviewed) do not
designate facilities in "resolved pending."
Thus, facilities in these regions may appear
to remain in SNC status in EPA's data
systems for a long time despite operating
with an existing enforcement action.
EPA staff also stated that once a facility
receives a violation for submitting DMRs
late, that violation will continually show as
a violation in EPA's data systems until
regions or States manually correct the
problem.
39

-------
#
OECA Response,
Section/Page
OECA Comments
(Attachment 1 of its response)
OIG Response


states evaluated, the OIG audit points out that
many facilities that are flagged in the data
systems as having SNC violations are actually
covered under enforcement orders (thus are
technically "resolved pending"). EPA is aware
that many Regions and states prefer to keep
the SNC flag on to keep pressure on the
facility to complete enforcement order
milestones. OECA believes that states should
have the flexibility to manage SNC data as the
states determine is appropriate. Keeping the
SNC flag on is more informative to the public
(e.g., it puts more pressure on the
owner/operator of the plant to come back into
compliance).
• Revise the title of this section to read
"SNC and violation data are inaccurate in
Michigan" - this revised language is
consistent with what OECA has already
posted on its web site.
The State of Michigan has had data
problems. We could not evaluate the
timeliness of enforcement actions at 25 of
the 30 Michigan facilities due to the State-
wide data problem. Even though we did not
evaluate timeliness of enforcement actions
at the 25 facilities, we did report on the
obvious oversight problems that exist from
a State having system problems for years.
The ECHO Website notes the following
data accuracy issues.
1.	A number of EPA-authorized
NPDES facilities in Region 10 do
not have up-to-date permit limits
entered in PCS.
2.	DMR non-receipt is not being
tracked for California Clean Water
Act NPDES permits.
3.	In Indiana, many non-receipt
violations are erroneous and are
currently being investigated with
resolution pending.
4.	In Delaware, Virginia, and West
Virginia, some pH violations are in
error.
No revision is necessary.
35
Chapter 3,
page 12
Many Violations Found During Inspections
not Reported in PCS, p. 12: This is an issue
that has concerned OECA, and we have been
working with the Regions and states to
improve such reporting since 2003. As noted
in OECA's October 2006 response, the
number of reported violations rose from 220
in 2003 to 4,441 in 2005. The OIG Report
fails to acknowledge substantial progress
made by OECA in this area. EPA has also
been responsive to state requests for
clarification on reporting standards by
finalizing more clear guidelines in regard to
how such information should be reported to
PCS. To ensure EPA has a full record of
violations found, EPA has also proposed to
the states that violation reporting be expanded
to non-major facilities.
The steps taken by OECA are encouraging;
however, OECA must implement a quality
assurance program to ensure that violations
found during inspections are reported in
PCS.
36
Chapter 3,
page 12
Bacteria not Reported as SNC, p. 12: The
permit parameters that are "eligible" to be
automatically tracked are specifically noted in
the RNC regulation, so EPA would be unable
to simply begin tracking these as RNC or
SNC without a regulatory change. Despite this
obstacle, OECA has piloted additional
See OIG response to comment 38 below.
40

-------
#
OECA Response,
Section/Page
OECA Comments
(Attachment 1 of its response)
OIG Response


management controls to assist in tracking
bacteria violations at direct dischargers. For
direct discharge facilities, the Watch List
process provides Regions and states with the
capability to flag facilities that have
continuing exceedances - which includes
bacteria and other pollutants that are not
evaluated for SNC. While only some Regions
and states are required to report under this
pilot, other Regions and states use the Watch
List as way to monitor these other parameters
that are not included in the regulation. OECA
is considering whether this pilot should be
extended. OECA is also developing new
reporting capabilities that will enable users to
automatically access these violations. In
OECA's October 2006 comments to the OIG,
EPA's existing NPDES SNC policy was
described which includes the discretion to flag
"any other violation of concern" (such as
bacteria) as SNC. OECA is working with an
EPA-state advisory group to supplement the
existing NPDES SNC policy to address
significant violations from wet weather point
sources (Combined Sewer Overflows,
Sanitary Sewer Overflows, Concentrated
Animal Feeding Operations and stormwater)
which include the most significant sources of
pollutants (including bacteria) not covered by
the existing SNC Policy .

37
Chapter 3,
page 12
Recommendations 3-1, page 12: Implement a
quality assurance program addressing the
completeness of compliance and enforcement
files, accuracy of EPA data systems, and
reporting in PCS the violations found during
inspections.
• OECA Response: OECA concurs and
believes that its existing processes -
which include SRF, the Watch List and
ECHO - provide a reasonable amount of
quality assurance. These substantial
efforts were not discussed in the OIG
report. In regard to inspection-related
violations, EPA continues to negotiate
with states to obtain this reporting, and is
just beginning a new Regional pilot to
ensure that EPA-determined violations
are accurately tracked.
OECA's existing activities (State Review
Framework, the Watch List, and ECHO) do
not represent a quality assurance program.
The Watch List and ECHO do not appear
sufficient to address completeness of files,
data accuracy, and reporting inspection
violations. Moreover, the State Review
Framework may help States address these
issues, but not necessarily EPA regions.
OIG is not convinced that these existing
efforts will sufficiently address our
recommendation. OECA needs to
implement a quality assurance program
addressing the completeness of compliance
and enforcement files, accuracy of EPA
data systems, and reporting in PCS the
violations found during inspections.
38
Chapter 3,
pages 12-13
Recommendation 3-2, page 12: Establish
controls allowing EPA leadership to identify
significant noncompliance by bacteria-only
violators for enforcement action.
• OECA Response : OECA concurs and is
pursuing this in three other ways that may
If OECA believes these actions will
establish controls so EPA leadership can
identify SNC by bacteria-only violators for
enforcement action, we will accept their
response. We will need to obtain an action
41

-------
#
OECA Response,
Section/Page
OECA Comments
(Attachment 1 of its response)
OIG Response


have the same intended effect of
addressing bacteria without the
significant resource expenditure it would
take to re-open the table of parameters
found in the QNCR regulation at 40 CFR
Part 123 .45 : 1) use of Watch List pilot
criteria which includes bacteria, 2)
develop better analytical tools that can
assist the Regions and states in easily
flagging these problems and tying the
problems to watershed quality, and 3)
continue to provide discretion for
Regions and states to elevate serious
bacteria violations to SNC status via the
existing NPDES SNC policy . In addition,
to improve public access to information
about such violations, OECA will be
adding effluent report charting (including
bacteria violations) to its ECHO database
in 2007. In addition, the most significant
sources of bacteria (combined sewer
overflows, sanitary sewer overflows,
concentrated animal feeding operations,
and storm water) are included in an effort
underway by OECA's Office of Civil
Enforcement to develop a wet weather
SNC policy.
plan and milestone dates for when these
actions will occur.
42

-------
Appendix E
Distribution
Office of the Administrator
Assistant Administrator for Enforcement and Compliance Assurance
Regional Administrator, Region 4
Regional Administrator, Region 5
Regional Administrator, Region 6
Agency Followup Official (the CFO)
Agency Followup Coordinator
General Counsel
Principal Deputy Administrator for Enforcement and Compliance Assurance
Director, Office of Regional Operations
Director, Water Enforcement Division, Office of Enforcement and Compliance Assurance
Office of Enforcement and Compliance Assurance Followup Coordinator
Regional Audit Followup Coordinator, Region 4
Regional Audit Followup Coordinator, Region 5
Regional Audit Followup Coordinator, Region 6
Associate Administrator for Congressional and Intergovernmental Relations
Associate Administrator for Public Affairs
Acting Inspector General
43

-------