Community Update #89
Pompton Lakes Study Area
Pompton Lakes, New Jersey
Pompton Lake Dredging
Community Update
July 2018
EPA CLEANUP ACTIVITIES
Basic Site Information—2018
The scope of work in 2018 involves
placement of the eco-layer in the
Island Area and the ABD as well as
site restoration. Hydraulic dredging,
processing and off-site disposal of
sediment containing mainly mercury
and lead in a 36-acre area within
Pompton Lake called the Acid
Brook Delta (ABD) is complete.
The work will be performed by The
Chemours Company FC, LLC.,
through its contractor, Sevenson
Environmental Services with EPA/
NJDEP oversight.
Further information/contacts:
Boroiiph of Pompton Lakes
http: //www .pomptonlake sgov .com
EPA Remedial Project Manager
Perry Katz
(212) 637-4426
katz.ira-perry@epa.gov
EPA Community Involvement
Coordinator
Pat Seppi
(646) 369-0068
seppi .pat@epa.gov
EPA continues its presence at
Borough Hall Thursdays from
10a. nt till 4p.m.
EPA's 89th update is to inform the community of the progress of activities
related to the dredging performed on the 36-acre portion of the Pompton
Lake Study Area known as the Acid Brook Delta (ABD).
Activities performed (week of July 9th):
~	Completed mechanical placement of the eco-layer (i.e. sand) material
in the ABD.
~	Continued restoration work associated with Uplands Soil Areas, ABD
shoreline and Acid Brook.
~	Removed turbidity curtain in the ABD.
~	Completed plantings in Island Area.
~	Continued demobilization of equipment no longer needed on-site.
~	Completion of lake turbidity/ perimeter air (dust) monitoring as water
work is complete and there is no impacted material on-site.
~	Monitoring data posted at www.pomptonlakesworks.com/pompton-
lake-project/environmental-monitoring
Activities scheduled (week of July 16th):
~	Continue activities on-site for restoration of Upland Soil Areas, ABD
shoreline, and Acid Brook.
~	Continue demobilization equipment.
~	Receive trucks daily for delivery of eco-layer, backfill, top soil.
~	Continue routine inspection of site work areas per approved permits
and for safety purposes.
Notes:
WORK ON SATURDAY, JULY 14TH (8 A.M. TILL 5 P.M.) IN-
VOLVES WATERING OF PLANTS, AS NEEDED. GATES WILL
BE CLOSED TO THE EXTENT PRACTICABLE.
PHOTOS: THE FIRST PHOTO IS THE PLANTING OF TREES
ON THE SOUTHWESTERN SIDE OF ACID BROOK. THE SEC-
OND PHOTO SHOWS THE POURING OF CONCRETE FOR THE
SIDEWALK ALONG LAKESIDE AVENUE.

-------