Community Update #95—Final Update
Pompton Lakes Study Area
Pompton Lakes, New Jersey
Pompton Lake Dredging/Restoration
Community Update
August 2018
EPA CLEANUP ACTIVITIES
Basic Site Information—2018
The scope of work in 2018 involved
placement of the eco-layer in the
Island Area and the ABD as well as
site restoration. Hydraulic dredging,
processing and off-site disposal of
sediment containing mainly mercury
and lead in a 36-acre area within
Pompton Lake called the Acid
Brook Delta (ABD) is complete.
The work was performed by The
Chemours Company FC, LLC.,
through its contractor, Sevenson
Environmental Services with EPA/
NJDEP oversight.
Further information/contacts:
Boron ph of Pompton Lakes
http: //www .pomptonlake sgov .com
EPA Remedial Project Manager
Perry Katz
(212) 637-4426
katz.ira-perry@epa.gov
EPA Community Involvement
Coordinator
Pat Seppi
(646) 369-0068
seppi .pat@epa.gov
EPA's 95th and final update is to inform the community of the progress of
activities related to the dredging and restoration performed on the 36-acre
portion of the Pompton Lake Study Area known as the Acid Brook Delta
(ABD). Two other areas that comprise the Pompton Lake Study Area
(Area A and the Island Area) were also dredged and restored.
Activities performed (week of August 20th):
~	Completed restoration work associated with Island Area, Uplands Soil
Areas, ABD shoreline and Acid Brook.
~	Completed demobilization of equipment from the site.
~	Lake turbidity/ perimeter air (dust) monitoring is complete as water
work is complete and there is no impacted material on-site.
~	Monitoring data posted at www.pomptonlakesworks.com/pompton-lake-
proj ect/environmental -monitoring
DREDGING/RESTORATION WORK IS NOW COMPLETE!!!
NOTES:
You will periodically see personnel on-site performing activi-
ties including: inspecting plants/fencing and making repairs,
as needed; watering plants, as necessary; inspecting the site
per permit requirements and installing water monitoring
points in compliance with permit requirements and
PHOTOS: THE FIRST PHOTO IS A WEST TO EAST VIEW OF
THE NEWLY INSTALLED WALKWAY ALONG LAKESIDE AVE-
NUE. THE SECOND PHOTO SHOWS SOME OF THE NEWLY IN-
STALLED AMENITIES AND PLANTINGS IN ROTARY PARK
WE THANK YOU FOR YOUR PATIENCE, SUPPORT AND COOP-
ERATION DURING THE IMPLEMENTATION OF THIS PROJECT!
EPA CONTINUES ITS PRESENCE AT BOROUGH HALL THURS-
DAYS FROM 10A.M. TILL 4P.M.
ENJOY THE UPCOMING POMPTON DAY FESTIVITIES!!

-------