U.S. ENVIRONMENTAL PROTECTION AGENCY
OFFICE OF INSPECTOR GENERAL
Catalyst for Improving the Environment
Audit Report
EPA Needs to Improve
Cost Controls for Equipment
Used during Emergencies
Report No. 10-P-0047
December 16, 2009

-------
Report Contributors:
Andres Calderon
Randy Holthaus
Les Partridge
Abbreviations
BPA
Blanket Purchase Agreement
ERRS
Emergency and Rapid Response Services
FAR
Federal Acquisition Regulation
MATS
Management Audit Tracking System
OAM
Office of Acquisition Management
OARM
Office of Administration and Resources Management
OSC
On-Scene Coordinator
OSWER
Office of Solid Waste and Emergency Response
RCMS
Removal Cost Management System
START
Superfund Technical Assessment and Response Team

-------

£
<

f
U.S. Environmental Protection Agency
Office of Inspector General
At a Glance
10-P-0047
December 16, 2009
Catalyst for Improving the Environment
Why We Did This Review
The Office of Inspector
General (OIG) sought to
determine whether the U.S.
Environmental Protection
Agency (EPA) had the
controls and processes in place
during its responses to
Hurricanes Gustav and Ike to
timely obtain goods and
services it needed at
reasonable prices. We also
followed up on actions EPA
committed to take after
Hurricane Katrina.
Background
In 2006, the OIG issued a
report titled Existing
Contracts Enabled EPA to
Quickly Respond to Hurricane
Katrina: Future Improvement
Opportunities Exist.
Hurricanes Gustav and Ike
made landfall in Louisiana and
Texas in September 2008 and
caused significant damage.
For further information,
contact our Office of
Congressional, Public Affairs
and Management at
(202) 566-2391.
To view the full report,
click on the following link:
www.epa.qov/oiq/reports/2010/
20091216-10-P-0047.pdf
EPA Needs to Improve Cost Controls for
Equipment Used during Emergencies
What We Found
EPA did not monitor costs paid for equipment used during its responses to
Hurricanes Gustav and Ike against average purchase prices. In our sample of 97
equipment items, with usage charges of $4,399, EPA may have paid a total of
$2,048 more than the average purchase price for 22 items. EPA did not require
the contractor to submit average purchase price information as required in the
contract. While EPA had controls to monitor equipment charges, it did not use the
tools effectively. EPA could have mitigated the risk of excessive charges for
equipment rentals by using the Removal Cost Management System for all
emergency response contracts, and tracking equipment rental costs by contract.
Improvements are needed so that EPA can better control equipment costs.
Using lessons learned from Hurricane Katrina, EPA established additional
emergency response contracting mechanisms to meet the Agency's needs during
future emergencies. EPA implemented the corrective actions it agreed to take in
response to recommendations in our 2006 report on Katrina contracting issues.
However, EPA never established a review board for Hurricanes Gustav and Ike;
review boards can help improve future emergency contracting procedures.
EPA did not notify the OIG as required that several corrective actions were going
to be delayed by more than 6 months. This can impact the completeness and
accuracy of reports to Congress.
What We Recommend
We recommend that EPA review equipment charges for Hurricanes Gustav and
Ike for usage fees that exceeded average purchase price, negotiate new rates, and
amend contract language. We also recommend that EPA develop a system or
process to identify and prevent overcharges for all emergency response contracts,
and notify the OIG when corrective actions are delayed more than 6 months. EPA
agreed with our recommendations or proposed acceptable alternative corrective
actions that, when implemented, should adequately address the findings.

-------
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
WASHINGTON, D.C. 20460
OFFICE OF
INSPECTOR GENERAL
December 16, 2009
MEMORANDUM
SUBJECT: EPA Needs to Improve Cost Controls for Equipment Used during Emergencies
Report No. 10-P-0047
Assistant Administrator
Office of Administration and Resources Management
Mathy Stanislaus
Assistant Administrator
Office of Solid Waste and Emergency Response
A1 Armendariz
Regional Administrator, Region 6
This is our report on the subject audit conducted by the Office of Inspector General (OIG) of the
U.S. Environmental Protection Agency (EPA). This report contains findings that describe the
problems the OIG has identified and corrective actions the OIG recommends. This report
represents the opinion of the OIG and does not necessarily represent the final EPA position.
Final determinations on matters in this report will be made by EPA managers in accordance with
established audit resolution procedures.
The estimated cost of this report - calculated by multiplying the project's staff days by the
applicable daily full cost billing rates in effect at the time - is $395,481.
Action Required
In accordance with EPA Manual 2750, the Office of Administration and Resources Management
is required to provide a consolidated written response for the Agency within 90 calendar days.
The response should include a corrective actions plan for agreed upon actions, including

FROM: Melissa M. Heist
Assistant Inspector General for Audit
TO:
Craig E. Hooks

-------
milestone dates. We have no objections to the further release of this report to the public. This
report will be available at http://www.epa.gov/oig.
If you or your staff have any questions, please contact Janet Kasper, Director, Contracts and
Assistance Agreement Audits, at 312-886-3059 or kasper.ianet@epa.gov.

-------
EPA Needs to Improve Cost Controls
for Equipment Used during Emergencies
10-P-0047
Table of C
Chapters
1	Introduction		1
Purpose		1
Background		1
Noteworthy Achievements		2
Scope and Methodology		2
2	Improvements Needed to Ensure EPA Pays Reasonable Prices
for Equipment		4
EPA Did Not Monitor Equipment Usage Costs Against Average
Purchase Prices		4
EPA Did Not Require Contractor to Comply With Contract Terms		5
EPA Did Not Make Full Use of Available Internal Controls		6
Conclusion		7
Recommendations		7
Agency Comments and OIG Evaluation		7
3	EPA Incorporated Lessons Learned after Hurricane Katrina		9
EPA Awarded Two BPAs and an Additional Logistics Support Contract		9
Enhancing Control Board Procedures Would Further Minimize Risk		9
Recommendation		10
Agency Comments and OIG Evaluation		11
4	OIG Not Notified of Delays in Corrective Actions		12
EPA Manual Provides Guidance on Notifying OIG		12
EPA Did Not Notify OIG of Delayed Corrective Actions		13
EPA Offices Unsure Who Is Responsible for Updating Tracking System		13
Recommendation		14
Agency Comments and OIG Evaluation		14
Status of Recommendations and Potential Monetary Benefits		15
- continued -

-------
EPA Needs to Improve Cost Controls
for Equipment Used during Emergencies
10-P-0047
Appendices
A Details on Scope and Methodology		16
B Equipment Spreadsheet		17
C Corrective Actions Delayed More than 6 Months		18
D Agency Response		19
E Distribution		22

-------
10-P-0047
Chapter 1
Introduction
Purpose
The Office of Inspector General (OIG) reviewed how the U.S. Environmental
Protection Agency (EPA) responded to Hurricane Katrina and in 2006 issued the
report Existing Contracts Enabled EPA to Quickly Respond to Hurricane Katrina;
Future Improvement Opportunities Exist (Report No. 2006-P-00038). In October
2008, we began a follow-up review of EPA's actions in response to our 2006
report. The objectives of our review were to determine whether EPA:
•	Paid reasonable prices for equipment when responding to Hurricanes
Gustav and Ike.
•	Established Blanket Purchase Agreements (BPAs) to provide emergency
response technical support and logistical services and such agreements
incorporated lessons learned from the Hurricane Katrina response and met
the Agency's needs when responding to Hurricanes Gustav and Ike.
•	Implemented the corrective actions it agreed to take in response to our
2006 report on Hurricane Katrina regarding contract management.
Background
Part of EPA's mission is to respond to emergencies that threaten our environment
and human health. In September 2008, two hurricanes struck the Louisiana and
Texas coasts. Hurricane Gustav made landfall in Louisiana on September 1,
2008, triggering the largest evacuation in U.S. history; over 3 million people fled
the oncoming hurricane. Hurricane Ike made landfall in Texas on September 13,
2008. Ike was the third most destructive hurricane to ever make landfall in the
United States, with damages estimated in 2008 at $22.4 billion.
EPA's role under the national response system is to respond to emergencies with
respect to the release or threat of release of oil, hazardous substances, pollutants,
contaminants, or fire or explosion hazard. To accomplish its role, EPA uses
contracts with specialized contractors, including the following types of contracts:
•	Superfund Technical Assessment and Response Team (START).
Typically, START contractors arrive at the scene of an emergency first.
START contracts are used to provide technical support to EPA On-Scene
Coordinators (OSCs) and other federal officials implementing EPA's
responsibilities.
•	Emergency and Rapid Response Services (ERRS). Next on the scene
of an emergency typically are ERRS contractors. ERRS contracts are used
1

-------
10-P-0047
to provide responsive environmental clean-up services for releases of
hazardous substances, wastes, contaminants, materials, and petroleum
products that are harmful to human health and the environment.
The START and ERRS contracts are (a) cost reimbursement, (b) indefinite-
delivery indefinite-quantity, (c) fixed-rate, and (d) time-and-materials contracts.
Time-and-materials contracts include materials at cost, including handling costs,
fixed hourly labor rates plus general and administrative costs, and profit. If EPA
needs goods or services from those contractors, EPA orders the goods using
delivery orders, task orders, and/or technical direction documents. The contractor
submits an invoice to EPA for reimbursement.
Indefinite-delivery indefinite-quantity, time-and-materials contracts expose the
government to risk and should be subject to strict controls to prevent contractors
from overcharging. The Federal Acquisition Regulation (FAR) states, "A time-
and-materials contract provides no positive profit incentive to the contractor for
cost control or labor efficiency. Therefore, appropriate Government surveillance
of contractor performance is required to give reasonable assurance that efficient
methods and effective cost controls are being used."
A March 4, 2009, presidential memorandum to all federal agencies on contracting
stated that excessive reliance on cost reimbursable contracts creates a risk that
taxpayer funds will be spent on contracts that are wasteful, inefficient, subject to
misuse, or otherwise not well designed. The memorandum calls on federal
agencies to manage the risk associated with the goods and services being procured
to ensure that taxpayer funds are not subject to excessive risk.
Noteworthy Achievements
EPA regional personnel initiated internal meetings after specific emergencies to
identify and use lessons learned from responding to those emergencies. Regions
called these "Hotwash" meetings, and the meetings included open discussions
among managers and staff who directly participated in the emergency responses.
The purpose was to respond more effectively to future emergencies. These efforts
indicate EPA's desire to continuously improve its processes for responding to
emergencies.
Scope and Methodology
We conducted this performance audit in accordance with generally accepted
government auditing standards. Those standards require that we plan and perform
the audit to obtain sufficient, appropriate evidence to provide a reasonable basis
for our findings and conclusions based on our audit objectives. We believe that
the evidence obtained provides a reasonable basis for our findings and
conclusions based on our audit objectives.
2

-------
10-P-0047
We performed audit field work from October 2008 to October 2009. We
followed up on recommendations made in our 2006 report on Hurricane Katrina
contracting issues. We also conducted Headquarters and regional interviews to
determine how the emergency acquisition process is implemented and what
controls are in place for emergency acquisitions. Regional interviews included
officials in Region 6, which is responsible for both Louisiana and Texas.
We reviewed the ERRS, START, and logistics contracts and the two BP As
available for emergency acquisitions on Hurricanes Gustav and Ike. We
conducted analyses to determine whether the prices EPA paid were reasonable for
particular items of equipment used during emergency operations. For additional
details on our scope and methodology, see Appendix A.
3

-------
10-P-0047
Chapter 2
Improvements Needed to Ensure EPA Pays
Reasonable Prices for Equipment
EPA did not monitor costs paid for equipment used during its responses to
Hurricanes Gustav and Ike against average contractor purchase prices. In our
sample of 97 equipment items, with usage charges totaling $4,399, EPA may have
paid a total of $2,048 more than the average purchase prices for 22 items. EPA
did not require the contractor to submit average purchase price information as
required in the contract. EPA was using time-and-materials contracts and the
FAR instructs federal agencies to closely monitor this type of contract to provide
a reasonable assurance of effective cost controls. While EPA had controls to
monitor equipment charges, it did not make full use of those controls. EPA could
have mitigated the risk of excessive charges for equipment rentals by using the
Removal Cost Management System (RCMS) for all emergency response
contracts, and tracking equipment rental costs by contract. Improvements are
needed so that EPA can better control equipment costs.
EPA Did Not Monitor Equipment Usage Costs Against Average
Purchase Prices
In responding to Hurricanes Gustav and Ike, EPA may have paid more in usage
fees for some equipment than the contractor's average purchase price. Federal
contracting regulations define a cost as being reasonable if it does not exceed that
which would be incurred by a prudent person in the conduct of competitive
business. EPA paid about $3.5 million to rent equipment to respond to
Hurricanes Gustav and Ike. In our sample of 97 items with usage charges totaling
$4,399, EPA may have paid contractors more than the average purchase price for
22 of those 97 pieces of equipment (23 percent), representing a total overcharge
of $2,048. See Appendix B for details.
EPA agreed to limit charges on contractor-owned equipment in its response to our
2006 report on Katrina contracting issues. EPA stated that the Office of
Administration and Resources Management (OARM) and its Office of
Acquisition Management (OAM) would review all current and future contracts to
ensure that flow-down clauses are included to prevent contractor overcharging.
The existing contract clause limiting equipment charges in the ERRS contracts
(Section B.6(4)(a)) states that, "The maximum charge for each contractor-owned
specific equipment item used on this contract shall not exceed the contractor's
average purchase price/average capital value for all pieces of equipment in that
category in his inventory." The clause goes on to say that if the average purchase
price is reached, "[A] usage rate must be negotiated with the Contracting Officer
before any additional costs are incurred." That new usage rate is intended to
4

-------
10-P-0047
reimburse the contractor for operating costs such as maintenance, license, and
insurance.
Not all the equipment used in the hurricane responses was contractor-owned. For
example, contractors rented items such as cameras, printers, and wireless cards.
EPA told us that for this equipment the contract clause limiting charges to average
purchase prices would not apply. Even if the contract clause limiting charges to
average purchase prices would not apply to this equipment, FAR provisions on
cost reasonableness would still apply. FAR 31.201-3 states a cost is reasonable if
it does not exceed what a prudent person would incur in the conduct of a
competitive business.
The contractor is entitled to costs in excess of the average purchase price to
compensate for maintenance of the equipment and indirect costs, but EPA has not
computed what the additional costs would be. The contract allows the contractor
to negotiate a maintenance fee once the usage fees exceed the average purchase
price. Neither EPA nor the contractor negotiated maintenance fees for the items
in our sample. EPA Region 6 staff said usage rates in the contract include general
and administrative costs and profit. Region 6 and OAM stated that to obtain the
actual purchase price the invoiced cost would have to be reduced by a percentage
to reflect cost factors such as general and administrative fees and profit. They
explained that those calculations would have to be made to make valid
comparisons between total rental costs to average purchase prices. Since
Region 6 has not made those calculations, Region 6 personnel stated that they are
not sure whether they have paid more than the average purchase price for the
equipment in our sample.
EPA Did Not Require Contractor to Comply With Contract Terms
The ERRS contractor for Region 6 did not submit average purchase price
information until almost 2 years after the contract was signed. According to the
contract, the contractor shall supply the contractor's average purchase
price/average capital value for all pieces of equipment that have fixed rates to the
contracting officer. The ERRS contracts were signed in May 2007 but the
contractor did not submit the average purchase price information until April 2009.
Region 6's Procurement Chief and her contracting staff acknowledged they had
not obtained the data and it had been an oversight on the Region's part. While the
contract required the contractor to supply information on average purchase price,
it did not include a timeframe for providing, or penalties for not providing, the
information. Without average purchase price information, EPA could not enter
the information into RCMS for the ERRS contracts.1 As a result, EPA could not
determine whether the limit for rental charges on any particular piece of
equipment was being approached or exceeded.
1 A separate EPA contractor in Edison, New Jersey, enters average purchase price information into RCMS.
5

-------
10-P-0047
EPA Did Not Make Full Use of Available Internal Controls
EPA needs to strengthen its internal controls over equipment charges during
emergencies. Internal controls are tools that program and financial managers use
to safeguard the integrity of Agency programs. While EPA has controls that it
could use to monitor equipment charges, it has not always used the tools
effectively. Region 6 personnel told us that they believe the risk of being
overcharged is low and that EPA can collect overcharges before contract close-
out. Although EPA might be able to recover overcharges if it performs checks on
invoices after the fact, relying on this method constitutes an ineffective and labor-
intensive method.
EPA uses the RCMS for some but not all emergency response contracts. RCMS
enables EPA to track equipment costs against average purchase prices for
individual pieces of equipment. EPA requires ERRS contractors to input daily
actual cost data to RCMS during emergency responses. However, EPA does not
require START contractors and Region 6's logistics contractor to use RCMS in
that way or to provide average purchase price information. However, an OSC
may elect to use RCMS for a START contract if the OSC believes it would be a
cost-effective method of tracking equipment costs.
RCMS is currently set up to track costs by task order, not by contract. As a result,
contractors have the ability to spread equipment rental costs out over different
task orders, and EPA will not be able to identify instances where the combined
cost exceeded the average purchase price. For example, the pressure washer EPA
rented appeared in two different task orders (042-003 and 045-003). If equipment
rental charges are only tracked by task order, each time there is a new task order
the equipment rental charge accruals start over. Region 6 officials told us that
they are working with EPA's RCMS expert to fix this problem.
EPA reviewed affected contracts before April 7, 2007, but did not ensure that
future procurement vehicles (such as Region 6's logistics contract) contained the
flow-down clause. The clause stipulates that maximum charges for contractor-
owned equipment "[Apply] to team subcontractors and tier subcontractors." Not
having flow-down clauses puts EPA at risk of being overcharged for equipment
EPA contractors rent from subcontractors, and the clause gives EPA the legal
grounds to recover overcharges. When we asked Region 6's Procurement Section
Chief in December 2008 about the flow-down clause, the Chief acknowledged
that it was not in the logistics contract awarded in July 2008 and should have
been. EPA modified the contract to include the flow-down clause effective
May 8, 2009. EPA also modified one of the BP As to include the flow-down
clause effective July 14, 2009.
6

-------
10-P-0047
Conclusion
Federal agencies should manage the risk associated with the goods and services
being procured to ensure that taxpayer funds are not subject to excessive risk.
Region 6's START, ERRS, and logistics contracts are all cost reimbursable
contracts. There are internal controls available to EPA to reduce the risk of such
contracts - for example, the ability of the RCMS system to identify when contract
charges exceed average purchase prices. However, EPA did not fully use these
internal controls. As a result, EPA may have paid more to rent equipment than
was reasonable and may continue to do so.
Recommendations
We recommend that the Regional Administrator for Region 6:
2-1 Review all equipment charges for responding to Hurricanes Gustav and
Ike and identify any items where the usage fees exceeded the average
purchase price. For these equipment items, the contracting officer should
negotiate maintenance rates for the equipment and then require the
contractor to repay any charges in excess of negotiated rates.
2-2 Amend the ERRS contract to require the contractor to provide average
purchase price information within a specific timeframe.
We recommend that the Assistant Administrator for Solid Waste and Emergency
Response:
2-3 Develop a system or process to identify and prevent overcharges for
contractor-owned equipment for START and emergency logistics
contracts. If RCMS is not used, provide policies and procedures for how
to track equipment costs.
2-4 Modify RCMS so that it tracks equipment charges by contract rather than
just task order.
Agency Comments and OIG Evaluation
EPA concurred with Recommendations 2-1, 2-2, and 2-3. While it did not agree
with Recommendation 2-4, EPA proposed an alternative corrective action. This
corrective action would not modify RCMS, but would provide project officers and
contracting officers with the ability to query the system.
Regarding our audit finding related to overcharged equipment items, EPA
requested that the OIG examine new data related to the pressure washer and
generator. EPA explained that during our audit it initially provided inaccurate
7

-------
10-P-0047
data to us because the contractor "inadvertently reported" incorrect average
purchase prices for those two items. We reviewed additional cost documentation
that EPA provided and revised our report based on the new data. As a result, we
are no longer including the pressure washer and generator in our list of items that
had costs exceeding average purchase prices.
In its response to Recommendation 2-1, EPA did not provide details on how it
would address the finding. While EPA stated that it has started taking corrective
actions, it also did not provide a completion date. When responding to the final
report, EPA needs to provide details on how it would address the finding and
provide a completion date.
For Recommendation 2-2, in its response EPA stated that it had already
implemented the suggested corrective action. EPA has required both ERRS
contractors to provide average purchase price information in RCMS within
60 working days after the initial award and on each anniversary date of the
contract. Region 6 provided copies of the contract modifications that were
approved for both of the ERRS contracts after our draft report was issued. We
believe EPA's actions adequately address our recommendation.
For Recommendation 2-3, EPA agreed that either a system or process needs to be
developed to prevent overcharging of rented equipment. EPA stated that to
develop such a process will require coordination with all regional stakeholders.
EPA plans to complete this corrective action by December 2010. EPA stated that
until then, the regions will continue to perform invoice reviews to ensure the
government is not overcharged for equipment. This corrective action will
adequately address our recommendation. Upon completion of the action, the OIG
requests EPA provide documentation of the new process.
EPA did not agree with Recommendation 2-4. However, it proposed to train
project officers and contracting officers on how to query RCMS by July 2010.
These queries will enable project officers and contracting officers to capture
individual equipment costs so that they can be tracked by contract, not just by task
order. We believe EPA's actions adequately address our recommendation.
The full text of the Agency response is in Appendix D.
8

-------
10-P-0047
Chapter 3
EPA Incorporated Lessons Learned
after Hurricane Katrina
Using lessons learned from Hurricane Katrina, EPA established additional
emergency response contracting mechanisms to meet Agency needs during future
emergencies. EPA developed and awarded two national BP As and a logistics
support contract that met Region 6's needs during Hurricanes Gustav and Ike.
EPA procedures require that OAM establish a review board to assess internal
controls and the execution of contracts and purchase card actions for significant
emergency responses, and discussions on convening a board began 5 months after
the hurricanes made landfall. However, OAM never established a review board
for Hurricanes Gustav and Ike. EPA can enhance its emergency contracting
procedures to clarify when OAM is to establish the review board.
EPA Awarded Two BPAs and an Additional Logistics Support Contract
Following lessons learned from Hurricane Katrina, EPA developed two BPAs and
a logistics contract for Region 6 that met EPA needs during emergency responses.
One BPA required the vendor to provide housing/lodging services to support
EPA's OSCs and other federal officials implementing EPA's responsibilities in all
EPA regions. The other BPA required the vendor to provide an Incident
Command Post and associated services to support Agency emergency actions.
The logistics contract included providing and coordinating logistical support
services that address Region 6's immediate and high priority needs for lodging
and support services.
The BPAs addressed the OIG recommendation in our 2006 audit report that EPA
establish advance agreements with vendors that are flexible and detailed for the
items EPA used substantially during its Katrina response, such as housing and
food services. The BPAs also specifically addressed prior OIG concerns
regarding such issues as whether all office space needed to be under one roof and
the definition of private bedroom areas. Personnel from the three EPA regions we
spoke with believed they had more control and alternatives now to procure goods
and services during emergency actions; they believe that there are mechanisms
now in place to handle any kind of situation.
Enhancing Control Board Procedures Would Further Minimize Risk
EPA did not establish a control board to review contracts and purchase card
actions for Hurricanes Gustav and Ike. According to Section 1.5.4.1 of OAM's
Emergency Contracting Procedures, a contract control review board comprised of
9

-------
10-P-0047
management level officials from OAM, the Office of General Counsel, and the
Office of the Chief Financial Officer will assess the effectiveness of internal
controls and execution of contracts and purchase card actions. Representatives
from these three offices will ensure that emergency funds are used in support of
the Agency's mission and are protected from fraud, waste, and abuse.
The Office of Federal Procurement Policy's Emergency Acquisitions guide, dated
May 2007, states:
Agencies should consider the creation of a mitigation board to
control the increased risks during an emergency. Such boards
allow for increased communication, clear policy direction, and
effective resource utilization.
EPA's response action for Hurricanes Gustav and Ike started in August 2008.
Five months after the two hurricanes made landfall, EPA attempted to convene a
review board but never did. According to the OAM Acting Director, Gustav and
Ike were nowhere near the "magnitude" of Katrina and initially they were not
even sure they would need to establish a contracts control board. OAM said that
within 2 weeks of Gustav and Ike making landfall OAM was tracking purchases
to stay on top of issues and was totally aware of what was happening.
While EPA may have been tracking purchases, current Agency procedures require
that a control review board be established. EPA established a control review
board for Hurricane Katrina in 2005 while the response action was on-going, and
it enabled EPA to reduce the risk of overcharging and manage problems as they
occurred.
EPA needs to clarify the emergency contracting procedures to specify for what
type of emergencies the control board is to be established, how soon after the
emergency it is to be established, and how long the board is to remain active.
Updating the procedures will ensure that contract funds will continue to be
safeguarded during future emergencies.
Recommendation
We recommend that the Assistant Administrator for Administration and
Resources Management:
3-1 Expand the Emergency Contracting Procedures to describe when EPA
should convene a control review board, what offices should participate in
board meetings, and how long the board should remain active.
10

-------
10-P-0047
Agency Comments and OIG Evaluation
EPA concurred with Recommendation 3-1 and agreed to modify its emergency
contracting procedures related to convening a contract control review board. EPA
stated it will complete the revision by October 2010. This corrective action will
adequately address our recommendation. Upon completion of the action, the OIG
requests EPA to provide the OIG with documentation of the new process.
11

-------
10-P-0047
Chapter 4
OIG Not Notified of Delays in Corrective Actions
EPA did not notify the OIG when corrective actions were delayed more than
6 months after agreed to milestone dates. EPA implemented the corrective
actions it agreed to take in response to our 2006 report on Katrina contracting
issues, but there is one effort that EPA still needs to complete. EPA Manual 2750
requires the Agency to notify the OIG when EPA anticipates delays of more than
6 months in implementing corrective actions. OARM acknowledged that it forgot
to notify the OIG. When EPA does not properly notify the OIG of delays in
corrective actions, EPA hinders communication with the OIG on the effectiveness
of Agency programs and may impact the completeness and accuracy of reports to
Congress.
EPA Manual Provides Guidance on Notifying OIG
Action officials (usually Assistant and Regional Administrators) and audit
follow-up coordinators have specific audit management responsibilities, as shown
in Table 4-1. According to EPA Manual 2750, one of the responsibilities of
action officials is to notify the OIG when planned milestones for corrective
actions are going to be delayed more than 6 months.
Table 4-1: Audit Management Responsibilities
Title
Duties



• Ensures that corrective actions are documented,
Action Officials
tracked, and implemented
• Certifies that corrective actions are complete (or

designates a certifying official to do so)

•	Provides guidance and ensures that responses to OIG
reports are complete and timely
•	Maintains official files containing the record of
management decisions and certifications of completed
corrective actions
•	Provides status reports to the Agency Audit Follow-up
Coordinator on corrective actions and audit resolution,
and tracks reasons for delay
•	Prepares reports to Congress
Audit Follow-up
Coordinators

Source: EPA Manual 2750.
12

-------
10-P-0047
EPA Did Not Notify OIG of Delayed Corrective Actions
EPA was more than 6 months late implementing the corrective actions for eight
recommendations and did not notify the OIG of the delays.2 For example, the
Emergency Contracting Procedures document (in response to Recommendation
2-1) was produced 11 months after the agreed-upon milestone date. The Incident
Management Handbook document (in response to Recommendation 4-1, Bullet 1)
was produced 9 months after the agreed-upon milestone date. See Appendix C
for a list of all the actions that were delayed.
During our audit, the Office of Solid Waste and Emergency Response (OSWER)
finalized guidance related to the Response Support Corps into an EPA Order to
address Recommendation 4-1, Bullet 2. The Order was effective August 4, 2009.
EPA still needs to finish implementing one corrective action. In its response to
our 2006 report on Katrina contracting issues, EPA pledged to deploy a national
inventory tracking system by December 31, 2006. EPA personnel have told us
that the roll-out is progressing and that the system should be fully deployed by the
end of December 2009. OSWER is already tracking this corrective action as a
result of an OIG report on emergency response equipment.3
EPA Offices Unsure Who Is Responsible for Updating Tracking
System
EPA did not notify the OIG of delayed corrective actions regarding our 2006
report on Katrina contracting issues because there was confusion between
OSWER and OARM as to who was ultimately responsible for updating EPA's
Management Audit Tracking System (MATS). OARM was listed as the action
official in MATS. The OAM Director signed a memorandum certifying that all
corrective actions in response to the OIG's 2006 report on Katrina contracting
issues were completed by June 30, 2008. However, some of the actions where
OSWER was taking the lead had not been completed. When we asked the audit
follow-up coordinators about the dates in MATS, the audit follow-up coordinator
for OSWER agreed to take the steps necessary to accurately update MATS. Not
properly tracking corrective actions in MATS may adversely affect the
completeness and accuracy of audit follow-up information and reports to
Congress.
2	Recommendation 4-1 had five parts (bullets). We are counting each of those five parts as a separate, individual
recommendation requiring one corrective action each.
3
EPA Plans for Managing Counter Terrorism/Emergency Response Equipment and Protecting Critical Assets Not
Fully Implemented, Report No. 09-P-0087, dated January 27, 2009.
13

-------
10-P-0047
Recommendation
We recommend that the Assistant Administrator for Administration and
Resources Management and the Assistant Administrator for Solid Waste and
Emergency Response:
4-1 Notify the OIG when planned milestones for corrective actions are going
to be delayed more than 6 months.
Agency Comments and OIG Evaluation
EPA concurred with Recommendation 4-1. EPA stated that it would comply with
the requirements of MATS and EPA Manual 2750 for notifying the OIG of
delayed corrective actions. OSWER also stated that it would check the status of
milestones on a quarterly basis. We agree with EPA's proposed corrective
actions.
14

-------
10-P-0047
Status of Recommendations and
Potential Monetary Benefits
RECOMMENDATIONS
POTENTIAL MONETARY
BENEFITS (In $000s)
Rec.
No.
Page
No.
Subject
Status1
Action Official
Planned
Completion
Date
Claimed
Amount
Agreed To
Amount
2-1 7 Review all equipment charges for responding to
Hurricanes Gustav and Ike and identify any items
where the usage fees exceeded the average
purchase price. For these equipment items, the
contracting officer should negotiate maintenance
rates for the equipment and then require the
contractor to repay any charges in excess of
negotiated rates.
2-2 7 Amend the ERRS contract to require the contractor
to provide average purchase price information
within a specific timeframe.
2-3 7 Develop a system or process to identify and
prevent overcharges for contractor-owned
equipment for START and emergency logistics
contracts. If RCMS is not used, provide policies
and procedures for how to track equipment costs.
2-4 7 Modify RCMS so that it tracks equipment charges
by contract rather than just task order.
3-1	10 Expand the Emergency Contracting Procedures to
describe when EPA should convene a control
review board, what offices should participate in
board meetings, and how long the board should
remain active.
4-1	14 Notify the OIG when planned milestones for
corrective actions are going to be delayed more
than 6 months.
Regional Administrator for
Region 6
Regional Administrator for 10/20/09
Region 6
Assistant Administrator for 12/31/10
Solid Waste and
Emergency Response
Assistant Administrator for 07/31/10
Solid Waste and
Emergency Response
Assistant Administrator for 10/31/10
Administration and
Resources Management
Assistant Administrator for 12/31/10
Administration and
Resources Management
and
Assistant Administrator for
Solid Waste and
Emergency Response
1 O = recommendation is open with agreed-to corrective actions pending
C = recommendation is closed with all agreed-to actions completed
U = recommendation is undecided with resolution efforts in progress
15

-------
10-P-0047
Appendix A
Details on Scope and Methodology
We analyzed the laws, regulations, and guidance pertaining to emergency response contracts.
We reviewed internal controls related to planning, organizing, directing, and controlling
acquisitions operations. We also reviewed controls for measuring, reporting, and monitoring
emergency acquisitions. We gained an understanding of internal controls by performing the
steps outlined below.
•	We interviewed OAM and OSWER managers and staff members in EPA Headquarters in
Washington, DC. We also interviewed EPA acquisitions personnel in Regions 6, 7, and
9; an OSWER Environmental Response Team RCMS equipment specialist in Cincinnati,
Ohio; and an OARM program analyst in Research Triangle Park, North Carolina.
•	We examined the Region 6 START and ERRS contracts and a logistics contract available
for emergency acquisitions during EPA's responses to Hurricanes Gustav and Ike. We
examined the two national BP As that EPA awarded after Hurricane Katrina.
•	We judgmentally selected 25 equipment categories of non-expendable personal property
that EPA rented during Gustav and Ike to determine whether the rental costs exceeded the
average purchase price of those items. The audit team selected equipment items to
review based on rental rates that seemed high and could likely be above purchase prices.
The 25 categories of items in our sample of equipment represented 97 individual pieces
of equipment rented under the START, ERRS, and Region 6 logistics contracts between
September and December 2008. The sample represented about 10 percent of the
equipment rented to respond to the Hurricanes. Our review focused on the costs for
equipment only and not other emergency response cost categories. Because we used a
non-statistical sample, the results of our review cannot be projected.
•	We reviewed relevant criteria documents, such as FAR Parts 16, 18, and 31; the Office of
Federal Procurement Policy's guidance on emergency acquisitions; and a presidential
memorandum calling for less reliance on cost-reimbursable contracts.
•	We reviewed numerous documents related to EPA's response to our 2006 report on
Katrina contracting issues to gain an understanding of EPA progress in completing the
related corrective action plan. We reviewed the MATS entry for that audit to determine
whether EPA had used the system to appropriately track and finalize proposed audit
response actions.
•	Besides the 2006 OIG Report No. 2006-P-00038, there was one other OIG report on
contracting during emergencies. That was Report No. 2007-P-00015, New Housing
Contract for Hurricane Katrina Command Post Reduced Costs but Limited Competition,
issued March 29, 2007. The report did not contain any recommendations.
16

-------
10-P-0047
Appendix B
Equipment Spreadsheet








Average
Total



Contract
Purchase
Rental
Cost
Price
Item Name
Type
Price4
Cost
Overrun
Range
Camera (RFW21158)
START
$323.23
$361.53
$38.30
$237.90-497
Camera (RFW23609)
START
$323.23
$355.77
$32.54
$237.90-497
Camera (WSH00028)
START
$109.50
$253.93
$144.43
$66-153
Camera (WSH00025)
START
$109.50
$159.18
$49.68
$66-153
Camera (WSH00026)
START
$109.50
$159.18
$49.68
$66-153
Camera (WSH00027)
START
$109.50
$159.18
$49.68
$66-153
Camera (WSH00029)
START
$109.50
$159.18
$49.68
$66-153
Camera (WSH00030)
START
$109.50
$159.18
$49.68
$66-153
Camera (WSH00031)
START
$109.50
$159.18
$49.68
$66-153
Printer (WSH00048)
START
$347.00
$396.00
$49.00
$200-494
Printer (WSH00049)
START
$347.00
$396.00
$49.00
$200-494
Wireless Card
(WSH00075)
START
$22.24
$230.10
$207.86
$19.99-24.75
Wireless Card
(WSH00077)
START
$22.24
$230.10
$207.86
$19.99-24.75
Wreless Card
(WSH00078)
START
$22.24
$230.10
$207.86
$19.99-24.75
Wreless Card
(WSH00074)
START
$22.24
$214.50
$192.26
$19.99-24.75
Wreless Card
(WSH00144)
START
$22.24
$214.50
$192.26
$19.99-24.75
Wreless Card
(WSH00076)
START
$22.24
$171.60
$149.36
$19.99-24.75
Wreless Card
(WSH00222)
START
$22.24
$78.00
$55.76
$19.99-24.75
Wreless Card
(WSH00223)
START
$22.24
$78.00
$55.76
$19.99-24.75
Wreless Card
(WSH00224)
START
$22.24
$78.00
$55.76
$19.99-24.75
Wreless Card
(WSH00225)
START
$22.24
$78.00
$55.76
$19.99-24.75
Wreless Card
(WSH00226)
START
$22.24
$78.00
$55.76
$19.99-24.75
Totals

$2,351.60
$4,399.21
$2,047.61

Source: OIG analysis of EPA and market data.
4 The contractors did not provide the average purchase prices for the START equipment items; as a result, we
contacted vendors directly and did research via the Internet to obtain the purchase price data. The average purchase
prices for START items are what it would have cost to purchase the item and do not include overhead and
maintenance costs the contractor may incur. The average purchase prices for the wireless cards did not include
airtime, which was included in the contractor's fixed rate.
17

-------
10-P-0047
Appendix C
Corrective Actions Delayed More than 6 Months
(from OIG Report No. 2006-P-00038)


Agreed-Upon
Milestone
Completion
Date in
Actual
Completion
Recommendation #
Recommendation
Dates5
MATS
Date
Recommendation 2-1
Develop a
strategy/plan to
deploy sufficient
personnel to an
emergency response
area
Document
completed by
December 2006
December 6,
2007
November 7,
2007
Recommendation 2-3
Continue exploring
advance agreements
for support services
BP As
developed by
September 30,
2006
September 30,
2006
September 26,
2007 and
January 30, 2008
Recommendation 3-1
Establish a policy
and procedures for
adequate invoice
review
Handbook
completed by
December 31,
2006
December 31,
2007
Handbook
completed
September 2007;
Job Aid
completed
January 2009
Recommendation 3-2
Make sure
subcontractor
limitation clauses are
in contracts
Insert flow-down
clauses by
December 31,
2006
April 7, 2007
May 8, 2009
Recommendation 4-1,
Bullet 1
Centralize or reduce
the number of
locations for
equipment receipt
Handbook
completed by
December 31,
2006
December 31,
2006
September 2007
Recommendation 4-1,
Bullet 2
Provide a sufficient
number of property
specialists to the
emergency area
Guidance
document by
December 31,
2006
December 31,
2006
August 4, 2009
Recommendation 4-1,
Bullet 4
Develop a purchase
log system
Implemented in
Fiscal Year 2007
June 30,
2008
Deployed in June
2008
Recommendation 4-1,
Bullet 5
Establish a national
custodial area in
Fixed Asset System
Deployed by
December 31,
2006
December 31,
2006
Proposed
implementation
date December
2009
Source: OIG analysis of EPA data.
5 Milestone dates are the dates EPA inserted into its response to OIG's 2006 report on Katrina contracting issues.
18

-------
10-P-0047
Appendix D
Agency Response
November 5, 2009
MEMORANDUM
SUBJECT: Response to Draft Audit Report: EPA Needs to Improve Cost Controls for
Equipment Used during Emergencies
FROM: Craig E. Hooks
Assistant Administrator
TO:	Janet Kasper
Director of Contracts and Assistance Agreement Audits
Thank you for the opportunity to comment on the draft report entitled, "EPA Needs to
Improve Cost Controls for Equipment Used during Emergencies." We are in general agreement
with the findings and recommendations. However, we offer the following specific and detailed
comments below.
General Comments on Report/Findings:
Report Title - The original report entitled, "EPA Is Better Prepared to Respond to Emergencies,
Yet Areas for Improvement Exist," does not have the negative impact the new title "EPA Needs
to Improve Cost Controls for Equipment Used during Emergencies," infers. We recommend
using the original title.
Chapter 2, Page 4 - Improvements Needed to Ensure EPA Pays Reasonable Prices for Equipment
- Paragraph 2 states, "In our sample of 97 items, with usages charges totaling $15,399, EPA may
have paid $4,532 more than the average purchase price of the equipment." The language is
misleading. We suggest changing the language to read, "In our sample of 97 items with usages
charges totaling $15,399, EPA may have paid contractors more than the average purchase price
for 24 of those 97 individual pieces of equipment (25 percent), representing a total overcharge of
$4,532."
Comments on Recommendations:
Recommendation 2-1: Review all equipment charges for responding to Hurricanes Gustav
and Ike and identify any items where the usage fees exceeded the average purchase price.
For these equipment items, the contracting officer should negotiate maintenance rates for
the equipment and then require the contractor to repay any charges in excess of negotiated
rates.
19

-------
10-P-0047
Region 6 Response: We concur with the findings and have started taking corrective actions. All
equipment charges for Emergency Rapid Response Services (ERRS) contracts have been
reviewed and are being discussed with the contractors. Based on our review of recent data
provided by the contractor, the pressure washer and generator identified in Appendix B of the
report did not exceed the purchase price as stated in the report. The contractor inadvertently
reported an incorrect purchase price of $5,885.38 for the pressure washer and $2,630.83 for the
generator. The correct price for the pressure washer is $8,276.46 and $3,601.98 for the generator.
We recommend that the OIG upon verification of the data reflect these changes in the final
report.
Recommendation 2-2: Amend the ERRS contract to require the contractor to provide
average purchase price information within a specific timeframe.
Region 6 Response: We concur with the finding and have implemented the suggested
corrective action to require both ERRS contractors to provide average purchase price information
in the Removal Cost Management System (RCMS) within sixty (60) working days after the
initial award and on each anniversary date of the contract.
Recommendation 2-3: Develop a system or process to identify and prevent overcharges
for contractor owned equipment for START and emergency logistics contracts. If RCMS
is not used, provide policies and procedures for how to track equipment costs.
OSWER Response: Although we concur with the findings, the current Superfund Technical
Assessment and Response Team (START) and National Logistics contracts do not contain
contractor owned equipment. The contractors either rent or lease equipment from commercial
vendors to support emergency efforts. We agree that either a system needs to be developed, a
process indentified or RCMS utilized to prevent overcharging of rented equipment. Determining
which system or process will be utilized will require coordination with all regional stakeholders
and will be a focus for Headquarters and START contracts in FY10. We anticipate this effort
being completed by December 2010. In the interim, the regions will continue to perform invoice
reviews to ensure the Government is not overcharged for equipment.
Recommendation 2-4: Modify RCMS so that it tracks equipment charges by contract
rather than just task order.
OSWER Response: The RCMS system has a data mining feature that enables users to query
the system and capture individual equipment cost. While we do not concur with this finding, we
will provide training on how to query the system at the On-Scene Coordinator Readiness
Conference in February 2010 and the Superfund Project Officer/Contracting Officer Conference
in July 2010.
Recommendation 3-1: Expand the Emergency Contracting Procedures to describe when
EPA should convene a Control Review Board, what offices should participate in board
meetings, and how long the board should remain active.
20

-------
10-P-0047
OAM Response: We concur with the finding and will modify the Acquisition Handbook,
Chapter 18, "Emergency Contracting Procedures", to address the requirements to convene a
Control Review Board; who will participate; and how long the board will remain active. Draft
procedures will be completed for internal review by November 2009 and the final revision will
be completed by October 2010.
Recommendation 3-1 [sic]: Notify the OIG when planned milestones for corrective actions
are going to be delayed more than 6 months.
OAM Response: We concur with the finding and will update and utilize the audit tracking
system that is currently in place to ensure compliance with the Agency's Management Audit
Tracking System (MATS) and EPA Manual 2750 which requires the Agency to notify the OIG
of anticipated delays of more than 6 months in implementing corrective actions.
OSWER Response: We concur with the finding and will continue working with respective
Audit Coordinators to ensure compliance with MATS and EPA Manual 2750 requirements for
changing corrective action plans. We will also check the status of milestones on a quarterly basis
and have the Audit Coordinators notify the OIG of any changes that are going to be delayed
more than 6 months.
We look forward to receiving the final report. Should you have any questions or
comments, please contact John Gherardini, Acting Director, Office of Acquisition Management,
at 564-4310.
21

-------
10-P-0047
Appendix E
Distribution
Office of the Administrator
Assistant Administrator, Office of Administration and Resources Management
Assistant Administrator, Office of Solid Waste and Emergency Response
Chief Financial Officer
Regional Administrator, Region 6
Agency Follow-up Official (the CFO)
Agency Follow-up Coordinator
General Counsel
Associate Administrator for Congressional and Intergovernmental Relations
Associate Administrator for Public Affairs
Acting Director, Office of Acquisition Management, Office of Administration and Resources
Management
Director, Office of Budget, Office of the Chief Financial Officer
Director, Office of Regional Operations
Audit Follow-up Coordinator, Office of Administration and Resources Management
Audit Follow-up Coordinator, Office of Solid Waste and Emergency Response
Audit Follow-up Coordinator, Region 6
Acting Inspector General
22

-------