SEP A
United States
Environmental Protection
Agency
EPA Cleanup Activities
Continue at the
Tonawanda Coke Facility
Community Update
February 2019
Public participation is essential to the
success of EPA's community
involvement program. If you have
any questions, please contact:
Michael Basile
EPA Public Affairs Specialist
Western NY Public Information
Office
186 Exchange Street, Buffalo, NY
14204
(716) 551-4410 or
basile.michael@epa.gov
Introduction
The U.S. Environmental Protection Agency (EPA) is continuing to
make progress in its ongoing cleanup and assessment of the
Tonawanda Coke Corporation (TCC) facility in Tonawanda, N.Y.
TCC ceased operations at the facility on October 14, 2018 and has
permanently vacated the site. EPA, the lead agency responsible for the
site, is using its short-term authority under Superfund to assess the
TCC facility and perform cleanup activities. During the recent
government shutdown in January 2019, cleanup activities continued
without interruption because of the nature of the work that was being
performed and the need to keep certain systems operating at the
facility. EPA's current work at the site is expected to continue over-
many months due to the size and complexity of the facility. A site
contingency plan has been created and shared with first responders
and will be updated as site conditions change.
Assessing and Managing Risks
Some potential risks identified at the facility include flammable or potentially explosive substances stored
onsite, hazardous substances discharged onto the soil, and improperly stored materials including acids and
solvents. As part of the assessment, EPA has secured the site, managed utilities to the facility, found and
mitigated releases in specific areas, maintained and monitored the two systems that treat plant process water and
storm water generated at the site, inventoried all the bulk tanks and vessels onsite, winterized equipment and
pipes, and commenced an evaluation of additional cleanup needs that may be required in the short- or long-
term. EPA has also collected samples of contaminated media for analysis and continues to keep the facility
secure.
EPA Cleanup Activities to Date
In addition to continuing to assess conditions at the site, EPA has excavated and properly stored 83 cubic yards
of contaminated soil in preparation for shipping the material offsite for disposal. EPA has successfully treated
more than one million gallons of contaminated wastewater remaining from the plant shutdown, and has moved
and safely stored in secure areas over one hundred containers of chemicals found scattered throughout the site.
EPA continues to remove and clean contaminated sludge in sumps at the site, and take these sumps out of
service.
The shutdown of the boiler plant and amonia lines was completed in late December 2018. As part of the
shutdown process, EPA drained and emptied all tanks and lines associated with the boiler house operations,
including the water pretreament system and purged the amonia lines. EPA closed the boiler plant and had
domestic water service turned off to all structures on the facility except for the locker rooms, office area
(command post), and security facility.
EPA continues to remove coal and coke from the facility, with about 4,300 tons already removed. EPA cleaned
floors contaminated with chemicals in several buildings open to the elements and mitigated other areas
contaminated with chemicals to prevent the release of the contaminants to the environment.
For more information, visit: https://www.epa.gov/ny/tonawanda-coke-corporation-tcc-site
In May 201 7, EPA established a task force to restore the Superfund program to its rightful
place at the center of the Agency's core mission to protect health and the environment.
epa.gov/superfund/superfund-task-force

-------