US EPA Superfund Task Force: Superfund Sites Targeted for Immediate, Intense Action - December 8, 2017
Site
EPA
Region
City
State
NPL
Issue/Upcoming Milestone
Mohawk Tannery
1
Nashua
New
Hampshire
P
Finalize Non-Time Critical Removal Action and facilitate
redevelopment with interested developers.
Centredale Manor
Restoration Project
1
North
Providence
Rhode
Island
F
On the NPL for an extended period of time. Litigation with
Potentially Responsible Party has delayed implementation of the
remedy.
American Cyanamid Co.
2
Bound Brook
New Jersey
F
Issue Proposed Plan for public comment.
Diamond Alkali Co. (aka
Upper Lower Passaic)
2
Newark
New Jersey
F
Finalize the Remedial Investigation and consider taking early
actions.
Ventron/Velsicol (aka
Berry's Creek)
2
Wood Ridge
Borough
New Jersey
F
Issue Proposed Plan for public comment.
L. A. Clarke & Son
3
Spotsylvania
Virginia
F
On the NPL for an extended period of time. Dispute with
Potentially Responsible Party regarding OU2 work plan for
groundwater. Need resolution on issue to determine if party will
perform work, or if formal dispute resolution is invoked.
1
12/7/2018

-------
US EPA Superfund Task Force: Superfund Sites Targeted for Immediate, Intense Action - December 8, 2017
Site
EPA
Region
City
State
NPL
Issue/Upcoming Milestone
B.F. Goodrich
4
Calvert City
Kentucky
F
Proposed remedy out for comment. Comments will be
considered and addressed in the Record of Decision.
Mississippi Phosphates
Corporation
4
Pascagoula
Mississippi
P
Potential release of hazardous waste to environmentally
sensitive area/NPL listing for remedial takeover.
U.S. Smelter and Lead
Refinery, Inc. (aka USS
Lead or East Chicago)
5
East Chicago
Indiana
F
In Operable Unit 1-Zone 1 land use decision/Proposed Plan
release. Complete all soil remediation in Operable Unit 1-Zones
2 and 3.
Allied Paper, Inc./Portage
Creek/Kalamazoo River
5
Kalamazoo
Michigan
F
Remedial Investigation/Feasibility Study delays caused by
litigation. Resolve issues expeditiously.
Tar Creek (Ottawa County)
6
Ottawa
County
Oklahoma
F
Long term stewardship/Implement institutional controls to
protect cleanup.
San Jacinto Waste Pits
6
Channelview
Texas
F
Initiate and complete Remedial Design/Remedial Action
negotiations and sign Consent Decree.
2
12/7/2018

-------
US EPA Superfund Task Force: Superfund Sites Targeted for Immediate, Intense Action - December 8, 2017
Site
EPA
Region
City
State
NPL
Issue/Upcoming Milestone
Des Moines TCE (aka Dico
Company)
7
Des Moines
Iowa
F
Delayed by litigation. Initiate actions to allow revitalization of the
site.
West Lake Landfill
7
Bridgeton
Missouri
F
Develop a preferred alternative and issue Proposed Plan.
Bonita Peak Mining District
8
San Juan
County
Colorado
F
Remediation plan with short- and long-term objectives.
Anaconda Co. Smelter
8
Anaconda
Montana
F
Initiate and complete negotiations to begin implementation of
early actions to address human health exposure, followed by site
wide work.
Silver Bow Creek/Butte
Area
8
Butte
Montana
F
Administrator's site visit pending in 2018. State disagreement
with Potentially Responsible Party on implementation of the
remedy. Region facilitating discussions to reach agreement to
implement remedy.
Orange County North
Basin
9
Fullerton
California
Pre-
NPL
Basin-wide groundwater cleanup needed quickly to protect
drinking water for millions of Californians/NPL proposal, then
listing.
3
12/7/2018

-------
US EPA Superfund Task Force: Superfund Sites Targeted for Immediate, Intense Action - December 8, 2017
Site
EPA
Region
City
State
NPL
Issue/Upcoming Milestone
Anaconda Copper Mine
9
Yerington
Nevada
P
State request for deferral of final NPL listing decision. Pursue
agreement on deferral decision.
Portland Harbor
10
Portland
Oregon
F
Negotiating multiple agreements for design of cleanup and
baseline sampling.
Quendall Terminal
10
Renton
Washington
F
Substantial redevelopment opportunity. Determine preferred
alternative and issue the Proposed Plan for public comment.
NPL Status Codes
Pre-NPL = Under consideration to be proposed to the NPL
P = Proposed to the NPL
F = Final on the NPL
D = Deleted from the NPL