NEWTOWN CREEK/GREENPOINT
OIL SPILL STUDY
BROOKLYN, NEW YORK
September 12, 2007

-------
Table of Contents
Executive Summary:
Section 1:
Introduction	1
Legislative History	1
Area Characterization and Spill History	2
Spill Related Health Effects	4
Section 2:
USCG 1979 Report Review	5
Mitigation of Seeps Review	5
Extent & Mitigation of Free Product Plume Review	6
Extent & Mitigation of Dissolved Product Plume Review	7
Section 3:
Vapor Intrusion Document	7
Section 4:
Natural Resource Damages Assessment (NRDA) Document	8
Section 5:
EPA Recommendations	8
REAC	8
Vapor Intrusion	10
NRDA	11
Chapter 1:
REAC Report	13
Summary	17
Introduction	21
Geraghty & Miller Report	23
Newtown Creek Seeps	24
Free Product Plume	28
Dissolved Product Plume	40
Conclusions	41
Recommendations	43
References	45
Appendix	48
Tables	53
Figures	58
Chapter 2:
Vapor Intrusion	67
Figures	72
Figure 1 - Vapor Pathways into Buildings	73
Figure 2 - Site Plan	74
Figure 3 - Preliminary Phase IV Commercial Soil Vapor (Benzene Concentrations)	75
Figure 4 - Preliminary Phase IV Commercial Soil Vapor (Methane Concentrations)	76
Figure 5 - Benzene Concentrations in Soil Vapor (Jan 2007)	77
Figure 6 - Methane Concentrations in Soil Vapor(Jan 2007)	78
Figure 7 - Greenpoint Residential Vapor Intrusion Study Area	79
Chapter 3:
Natural Resource Damage Assessment.
81

-------
Executive Summary
Section 1: Introduction, Legislative & Historical Background
A.	Introduction: This study was compiled by a team of U.S. Environmental Protection
Agency (EPA) scientists, biologists, engineers, hydrogeologists, geologists, risk assessors,
attorneys and EPA contractor geologists and engineers. The study is based upon a review of
both public and private sector organizations. Methodologies, models, sampling data, and other
pertinent information from all discovered sources were reviewed and considered in making the
recommendations of this study. In order to produce the study in a timely manner, EPA
conducted no additional sampling. Instead, EPA focused on the reviews of existing documents
and previously collected sampling data. A conscious decision was made to limit the scope of the
study to the Newtown Creek oil spill and its petroleum based impacts on the Greenpoint
community. Because of the more than 140+ years of heavy industry in the area of Newtown
Creek, it would not be feasible in one year to evaluate potential health risks from a large number
and wide variety of possible industrial contamination. The oil seepage into the Creek seems to
be only one of many pollution issues impacting Newtown Creek. A potentially more significant
issue that appears to be having a major effect on the Creek is the ongoing discharge from the
New York City-Newtown Creek municipal wastewater treatment system, the combined sewer
overflows and the consequent zero oxygen levels. This in concert with a stagnated water flow in
the Creek will only exacerbate the Creek's future ability to recover. Plans to upgrade the New
York City-Newtown Creek municipal wastewater treatment system to secondary treatment are
currently underway pursuant to an enforcement agreement between the New York State
Department of Environmental Conservation (NYSDEC) and the New York City Department of
Environmental Protection (NYCDEP). In order to address the combined sewer overflow issues, a
Watershed/Waterbody Facility Plan will be submitted by NYCDEP to NYSDEC shortly which
will lay out the City's long term abatement program for managing the source of the
contamination.
B.	Legislative History: The Coast Guard and Maritime Transportation Act of 2006"
(Public Law No. 109-241)" was signed by the President on July 11, 2006. Section 410 of the
legislation set forth a requirement for EPA to conduct, within one year of enactment, a study of
the public health and safety concerns relating to the Newtown Creek oil spill. Section 410
(originally introduced as H.R. 109-889, and referred to below as "H.R. 889") was authored by
Representative Anthony Weiner (D-Brooklyn and Queens) and Representative Nydia Velazquez
(D-Manhattan, Brooklyn and Queens). Newtown Creek and the Greenpoint community are part
of their districts. [See "Conference Report on H.R. 889, Coast Guard and Maritime
Transportation Act of 2006" (remarks by Representative Weiner), 152 Cong. Rec. H4527-28,
June 26, 2006.]
SEC 410. NEWTOWN CREEK, NEW YORK CITY, NEW YORK.
(a) Study- Of the amounts provided under section 1012 of the Oil
Pollution Act of1990 (33 U.S.C. 2712), the Administrator of the
Environmental Protection Agency shall conduct a study of public health
and safety concerns related to the pollution of Newtown Creek, New York
1

-------
City, New York, caused by seepage of oil into Newtown Creek from
17,000,000 gallons of underground oil spills in Greenpoint, Brooklyn,
New York
(b) Report- Not later than one year after the date of enactment of this Act,
the Administrator shall submit a report containing the results of the study
to the Committee on Environment and Public Works and the Committee on
Commerce, Science, and Transportation of the Senate and the Committee
on Transportation and Infrastructure of the House of Representatives.
To meet this legislative mandate, EPA looked at the following main issues:
•	Review of the 1979 USCG Report;
•	Mitigation of seeps into Newtown Creek;
•	Extent and mitigation of the free product plume;
•	Extent and mitigation of the dissolved product plume;
•	Possible vapor intrusion/indoor air problems; and
•	Sediments/ecology of Newtown Creek.
Additionally, EPA has addressed in the study, as appropriate, the remarks of
Representative Weiner from the House floor concerning H.R. 889. Response to, and discussion
of, Representative Weiner's remarks have been included in the study's discussion of the six main
issues outlined above.
Shortly after passage of H.R. 889, a Memorandum of Understanding (which had been in
coordination for over a year) was signed between the USCG and EPA on July 21, 2006, which
transferred response authority for this area by adjusting the jurisdictional boundary from the
USCG to EPA.
C. Area Characterization and Spill History: The northeast area of Greenpoint, the
northwestern-most community in Brooklyn, New York has been heavily industrialized and the
site of various petroleum industries for more than 140 years. The industrial history of this
section of Brooklyn dates back to the 1830s. Large quantity petroleum storage and refining were
some of the predominant activities in this area in the 1860s. An 1844 map of the area shows
where Newtown Creek had been partially filled, and much of the area that has been historically
used for oil storage and refinery operations is located on this fill. Petroleum refining within the
Greenpoint area began in approximately 1866. By 1870 more than 50 refineries were located
along the banks of Newtown Creek. This tidal area of salt marshes along the creek was
reportedly severely impacted and saturated by the waste discharges of the industries and
refineries in the area in the late 1800s.
In 1892, the majority of the area refineries were purchased and consolidated into the
Standard Oil Trust. Following the breakup of the Trust in 1911, ownership of the refinery
property in Greenpoint reverted to the Standard Oil Company of New York (SOCONY), and
these operations became the SOCONY Brooklyn Refinery. SOCONY later became Mobil Oil
2

-------
Corporation, which later became Exxon/Mobil Corporation, referred to below as Exxon/Mobil.
Refinery operations at the former Mobil Brooklyn Refinery ceased in 1966. The refinery was
subsequently demolished, and significant portions of the refinery property were sold. Several of
the subdivided lots were retained by Mobil Oil Corporation, while the other lots were sold to
Amoco Oil Company and others. The lots retained by Mobil were utilized as a petroleum bulk
storage terminal until 1993, when storage operations ceased at the property. Amoco Oil
Company (currently BP, referred to below as BP/Amoco) constructed a bulk fuel storage
terminal on its portion of the property that began operation in late 1969 and which continues in
operation today. In addition to the petroleum facilities on the former Mobil site, the Paragon Oil
Company occupied a portion of the site. Paragon Oil was a wholly-owned subsidiary of Texaco
Oil, now Chevron Corporation (ChevronTexaco). Paragon operated an oil storage terminal at this
location until approximately 1969, when Peerless Importers purchased the property and
constructed a warehouse for its operations.
Prior to 1947, the ground water under Brooklyn was the sole source of the Brooklyn
Municipal Water System. This system pumped huge quantities of water and caused a significant
decline in ground water levels in that area. The pumping was so heavy that it created a large
"cone of depression" (an area where the ground water levels are depressed due to pumping) in
the ground water and is believed to have reversed the direction of flow of ground water away
from Newtown Creek toward the pumping station. In the past 60 years since the pumping station
closed down, the ground water levels have recovered and the direction of the flow has reversed
back toward Newtown Creek. Since 1947 the ground water in Brooklyn has not been used as a
source of public drinking water.
The U. S. Coast Guard first detected signs of an oil spill entering Newtown Creek in
1978. A subsequent investigation concluded that the area of the spill under the Greenpoint area
was in excess of 52 acres, and the total spill volume, as estimated in 1979, was approximately 17
million gallons (Mgal) of petroleum product.
Petroleum product recovery operations are currently in place within four distinct areas,
including the former Exxon/Mobil Brooklyn Terminal, the BP Brooklyn Terminal, the
commercial/industrial/residential area southwest of the BP Terminal known as the Off-Site Area,
and the site of the former Paragon Oil Terminal, which is currently the location of the Peerless
Importers facility. Product recovery systems have been in place on both the terminal properties
and in the Off-Site Area since 1979. In 1990, Mobil entered into two consent orders with
NYSDEC and began upgrades to its recovery systems, including the design and construction of a
new and expanded system to recover the free product from the Off-Site Area. Following the
discovery of free product seepage through the facility's bulkhead, Mobil also began recovery
activities at the Peerless Importers/former Paragon Oil site in 1990 and continued recovery
activities until 2005 when Chevron took over that portion of the project.
Of the four petroleum product recovery operations, three separate free product recovery
systems are currently operating in Greenpoint. These include the Exxon/Mobil Brooklyn
Terminal Recovery and Containment System (RCS), the BP Brooklyn Terminal Recovery
System, and the Exxon/Mobil Off-Site Free-Product Recovery System. Both Exxon/Mobil and
3

-------
BP have recently completed upgrades to their terminal recovery systems to increase the free
product recovery capacity and water treatment capabilities of their systems. Through these
combined efforts, a total of approximately 8.8 Mgal of product, or about half of the amount
estimated to have been spilled, has been recovered from the plume areas. (Much of this
historical summary came from the NYSDEC website found at:
http://www.dec.state.ny.us/website/der/projects/reg2/greenpoint.)
Depending on various estimates, approximately 17 to 30 millions of gallons of petroleum
were spilled in the area. Although some major fires and explosions occurred historically in the
storage areas, it is somewhat unclear:
•	How much petroleum actually is on the ground water;
•	Who are the responsible parties that caused the spill(s);
•	Whether the petroleum on the ground water is from one or two events or the
culmination of 140 years of spillage;
•	Whether other smaller Aboveground Storage Tanks (AST's) and Underground
Storage Tanks (UST's) in the area have contributed to the plume; and
•	What apportionment of the spill should be allocated to the different potential
responsible parties.
Circumstantial evidence points to Exxon/Mobil as the most likely responsible party based
on hydrocarbon forensics analysis, product thickness on the ground water, the direction of
ground water flow and the seeps originating at the bulkhead adjacent to their property. However,
some analysis also suggests that BP/Amoco has contributed significantly as well. In addition,
there have been many ASTs and USTs (both commercial and residential) historically in the area;
it is unknown how many of those may have leaked over the years. To date, approximately 8.8
Mgal of the projected 17 Mgal on the ground water have been recovered. Comparison of
product recovery volume of 8.8 Mgal to date with the original estimated 17 Mgal of product
volume and the present size of the plume also suggests that the original volume estimate may
have been low, or that recovery volumes may have been overestimated, or both.
D. Spill Related Health Effects: In general, EPA does not perform health effects studies;
EPA does conduct risk assessments at certain sites (e.g., those on the National Priorities List) to
estimate the potential health risks under current and future exposure scenarios assuming no
remedial action will be taken. With respect to the Newtown Creek/Greenpoint oil spill, the
determination that response actions are warranted has already been made, and these actions are
ongoing.
In light of the ongoing spill response actions, EPA made a determination to focus the
study on efforts to remediate and recover the petroleum products of the spill. EPA did, however,
review the potential risk pathways related to the spill to evaluate whether or not these were being
addressed. There are four possible primary public health exposure routes that are typically
associated with petroleum spills:
•	Vapor intrusion from the chemicals found in petroleum;
4

-------
•	Contaminated drinking water wells that provide a public drinking water source;
•	Ingestion of fish from contaminated waters or food products made from or with the
contaminated waters; and/or
•	Dermal contact from seeps which transport the petroleum to either the surface soil or
surface waters.
At the present time the greatest potential exposure pathway is possible vapor intrusion
into the residential properties. The efforts to address this pathway are reviewed in Chapter 2
of this report.
Potable water is provided to the Greenpoint community by the City of New York, from
water sources located in upstate New York, and is tested regularly to ensure that the quality
meets all necessary federal and state requirements. Therefore the drinking water in this area is
not impacted by the spill. Similarly, the ingestion pathway is limited due to the restricted nature
of access for fishing in the Creek and the issuance of fish advisories by the NYSDOH in the
East River and its tributaries.
The physical nature of the seeps entering Newtown Creek limits the possibility of dermal
contact to a member of the public. The Creek is not easily accessed by the public because of the
vertical nature of the Creek banks, the location of the seeps on private property, and the siting of
industrial facilities along the length of the creek. Although there is access to the Creek via boats,
the use of the Creek for recreational boating and/or swimming has not been reported. In the
unlikely event of dermal contact by the public with the seeps, the health effects of exposure to
the petroleum seeps would be minimal compared to those presented by exposure to sewage and
contamination from other historical industrial sources found in the Creek. The sewage and other
contamination not related to the oil spill are separate issues from the petroleum seeps and are not
evaluated in this report.
Section 2: Summary of Response, Engineering and Analytical Contract (REAC) Report:
As directed by Congress, EPA reviewed the Newtown Creek/Greenpoint oil spill report prepared
by government contractor Geraghty & Miller for the U.S. Coast Guard in 1979. At EPA's
request, EPA's Response, Engineering and Analytical Contract (REAC) contractor (Lockheed
Martin) produced a document entitled "Newtown Creek Oil Spill: A Review of Remedial
Progress (1979-2007) and Recommendations." This document, referred to as the "REAC
Report," is found in this report to Congress at Chapter 1. The REAC Report is based on the
review of the Geraghty & Miller report, as well as on the review and analysis of current technical
issues regarding the oil spill. The REAC Report's findings and recommendations are
summarized as follows:
A. USCG's 1979 Report: The 1979 USCG report focused mainly on the physical
parameter of defining the spill and establishing booming/collection strategies along
Newtown Creek. The report did not focus on extensive recommendations for a
comprehensive response to the spill, but rather recommends that cleanup efforts should
be based on a few recovery wells and then biodegradation techniques to finalize the
recovery. The report projects a total recovery of up to 70% within four years.
5

-------
This projected cleanup time has since been shown to be unrealistic, since the recovery
wells have been operating for more than 25 years. The recovery wells, grout wall,
booming and oil collection process did seem to minimize and contain the seeps along the
creek. However, it has done little to remediate the plume of oil. It should be noted that
the USCG study was based on 1979 technology, and many improvements to modeling,
recovery and remediation have been made since then.
B.	Mitigation of Seeps into Newtown Creek: Focusing the response and recovery on the
mitigation of the seeps into the creek would be ineffective without addressing the source.
While there are a number of systems currently in place which are property-specific stop
gap measures, there is no coordinated effort to attack the spill as a whole. As such, what
action one property undertakes to mitigate the seep can have an adverse impact on an
adjoining property. An example of this is the grout wall that was installed along the Steel
Equities property. This grout wall and its associated recovery wells located behind the
wall help to prevent seeps from continuing to occur. Eventually these recovery wells will
form a cone of depression which will draw more petroleum toward that area. When this
happens the oil will collect and find its way around the end of the wall onto the adjacent
property. Another example is the Peerless Recovery system which is currently
preventing large seeps from going into the creek. However, this system has the potential
to draw the free product plume across the property and may increase seepage in the creek.
C.	Extent & Mitigation of the Free Product Plume: At present, the extent of the free-
product plume is divided into four specific areas:
(1) the On-Site area which includes the Exxon/Mobil properties that overlie the northern
portion of the plume, (2) the BP/Amoco terminal that borders Newtown Creek to the
southeast of the Exxon/Mobil facility, (3) the Off-Site area which includes commercial
and residential areas in the central and southern portion of the plume for which
Exxon/Mobil has taken remedial responsibility, and (4) the former Paragon Oil Property
(now Peerless Importers and Steel Equities facilities) bordering Newtown Creek,
currently being remediated by Chevron/Texaco.
More than 200 monitor/observation wells and approximately 35 designated
recovery wells have been installed in the project area since 1978. Until recently,
approximately 23 recovery wells were active, including six monitor wells that have been
converted to recovery wells. However, in early March 2007, ground water pumping from
the On-Site and Off-Site recovery wells was suspended by Exxon/Mobil because of
uncertainty about the status of the State discharge permits and because of impending law
suits by the State and others concerning the discharge of the oil-stripped water into
Newtown Creek. As such, the product recovery will apparently continue via suction of
only the free product from recovery wells. This is a much more inefficient and much
slower process to recover only the free product without collecting water as well. This
will cause the cones of ground water depression developed around the recovery wells that
help control product movement to dissipate with time. It is not presently known when
ground water pumping will be reinstated.
6

-------
Numerical modeling in 2001 has indicated that it may take up to 25 years to
recover up to an estimated maximum of 70% of the free product in the Off-Site plume.
No model estimate appears to be available for recovery time of the On-Site plume
beneath the Exxon/Mobil facilities. The On-Site plume exhibits the greatest apparent
free-product thickness but also appears to have the lowest recovery rate for the On-Site
and Off-Site plume designations.
D. Extent and Mitigation of the Dissolved Product Plume: To date, very little data have
been collected concerning the dissolved plume. Most of these data on the dissolved
product plume have been collected around the margins of the free-product plume. As
stated earlier, only about 70% of the petroleum on the ground water is recoverable. The
other 30%) potentially could contribute to a dissolved-phase plume and also could be a
source of soil vapors.
Section 3: Vapor Intrusion Document:
High levels of methane gas concentrations have been found during vapor intrusion
sampling in some commercial establishments. These levels were found to be above the Upper
Explosive Limit (UEL). This methane has been found to be both biogenic (derived from the by-
products of the petroleum spill) and thermogenic (from leaking Key Span Energy's methane
pipes in the area). Exxon/Mobil has established 3 pilot units to conduct vapor extraction and
flaring of the methane and other petroleum vapors from above the groundwater. These pilot
systems have been in place for the past few months and proved to significantly reduce these
methane levels to acceptable levels. In instances when these systems have operated and the
methane levels have not been reduced, sampling has then identified thermogenic methane. Once
identified, KeySpan is notified and they repair the leaking piping.
As part of the ongoing investigation and remediation activities for the Greenpoint
Remediation Project, the NYSDEC determined that an investigation of potential vapor intrusion
into residential structures was warranted. The vapor intrusion pathway accounts for the
migration of contaminants from one medium (i.e., ground water or soil) to a vapor phase that can
collect underneath building foundations (e.g., sub-slab), and finally enter through building
foundations into indoor air. This investigation began during the 2006-2007 winter heating
season.
NYSDEC, in conjunction with the New York State Department of Health (NYSDOH), is
continuing to assess the data that were collected from this investigation. To date, EPA has
received analytic results from 45 properties. EPA is providing several recommendations in this
report to assist the NYSDEC with this ongoing effort including: additional sampling of area
homes to close existing data gaps, providing information to the community on how risk
management decisions are being made, and a continued evaluation of ground water data to
ensure that the vapor intrusion study provides full coverage of both free product and dissolved
phase plume areas. The ability to close data gaps is dependent on obtaining access to residential
properties. In spite of considerable outreach by the NYSDEC, participation in this program has
been low. Access to homes for sampling purposes may continue to be an issue for the NYSDEC.
7

-------
Section 4: Natural Resource Damages Assessment (NRDA) Document:
While EPA has a large role in protecting the environment, EPA is not a natural resource
trustee. As a result, EPA does not have authority to assess the extent of natural resource
damages, recover for lost or diminished natural resources, or restore the natural resources
themselves. In matters such as the Newtown Creek/Greenpoint oil spill, EPA's regulatory role is
to support the designated Federal natural resource trustee for coastal and marine resources,
namely the National Oceanic and Atmospheric Administration (NOAA) and the designated State
natural resource trustee, namely the NYSDEC through the New York State Department of Law
(NYSDOL). In this matter, EPA has referred the natural resources issues with the site to NOAA
which is the lead Federal trustee for coastal and marine resources. Coordination has taken place
between NOAA and the Department of the Interior U.S. Fish and Wildlife Service (another
Federal trustee), and it was decided that NOAA would retain the Federal trustee lead in this case.
In regard to the Newtown Creek/Greenpoint oil spill, the Federal and State Trustees have
recently begun to focus on the extent of natural resource losses in this ecosystem and the
relationship of such losses to the releases of petroleum in the Greenpoint community and the into
the Creek.. It is anticipated in the next several years that the Federal and State trustees will
conduct an assessment of the natural resources damaged by the release of petroleum into
Newtown Creek and around the Greenpoint community.
Section 5: EPA Recommendations:
As noted above, EPA revisited the U.S. Coast Guard's 1979 Geraghty & Miller report via
EPA's REAC contractor. Based on that review as well as a review of the actions taken to date
and other technical issues regarding the oil spill, the following recommendations contained in the
REAC Report have been concurred on and approved by EPA:
1.	Review of 1979 USCG Report:
•	The 1979 Geraghty & Miller report is fairly comprehensive for the relatively short
period of investigation that led to this report. However, the northern portion of the
plume was not entirely delineated because of the lack of monitoring well coverage.
Additional monitoring wells need to be installed to delineate the northern portion of
the plume.
2.	Response and Recovery:
•	A comprehensive area-wide feasibility study that includes coordination among all
responsible parties is needed. NYSDEC appears to be working toward this goal, but
competing interests among the multiple responsible parties hinder this effort.
•	Other remedial technologies (e.g., injection of surfactants or biological remedial
compounds, bioslurping, vacuum enhanced recovery, steam or hot water injection,
and electrical heating) should be considered for recovering additional product once
8

-------
the bulk of free-product is recovered.
•	Due to logistical and regulatory restrictions, the feasibility of specific recovery and/or
remediation techniques should be determined prior to any in-depth analysis of their
applicability to the spill. For instance, the presence of utilities, buildings and other
constraints imposed by the urban setting may restrict recovery well placement to less
than preferred locations. Furthermore, the use of injection wells and the re-injection
or discharge of recovered ground water is subject to New York City, State, and
Federal regulations and policies.
3.	Seep Mitigation:
•	It is recommended that the spill response focus more intensively on remediation of
the source of the petroleum (i.e., the free product) to the extent technology allows,
rather than on controlling or mitigating the seeps into the Creek.
•	The present boom and well recovery system appears to be minimizing and containing
product discharges into Newtown Creek from the Peerless property, but not
remediating them completely. While we recommend an overall long term strategy of
plume removal instead of plume containment (with its inherent weaknesses), we also
recognize that interim measures may also be required. As an interim measure, the
planned installation of recovery wells along the grout wall on the Peerless property
should proceed, if the petroleum finds its way around the wall.
•	A combined effort by all property owners is needed to develop an overall site-wide
plume strategy. A coordinated effort will maximize recovery efforts while preventing
unintended consequences in other areas.
•	Background water levels need to be established to determine if the water table is
actually increasing because of increased precipitation, the cessation of pumping in the
1940s, or other factors. Because monitoring wells within the plume area are likely to
be affected by variations in the water table, an ongoing effort should be made to
monitor an existing observation well and study the long term ground water levels. A
rising water level could have a significant impact on the movement of the plume
toward the Creek.
4.	Extent and Mitigation of Free Product Plume:
•	The entire regional area, covering both the free-product and dissolved plume, should
be evaluated using three-phase numerical modeling techniques. The term "three-
phase modeling" refers to simulating the movement and interaction of water, oil, and
vapor in a geologic medium. In addition, this model can better determine the length
of time that will be required to recover free product from both the Off-Site and On-
Site plumes. To date, there is only an estimated 25 to 30 years (from 2001) of
product recovery time for the Off-Site plume (based on a 2001 numerical model). It is
9

-------
important that the modeling be approached as one unified effort, as opposed to
individual models for each property or by each responsible party.
•	Product thickness, as indicated on most maps presented in the various reports, should
be considered only an approximation. True product thickness is often difficult to
determine but is usually less than the apparent thickness measured in the wells. A
reevaluation of remaining plume volume across the entire project area, using
corrected product thickness values, is warranted.
•	The original 17 Mgal product volume estimate should be used with caution.
Comparison of the 8.8 Mgal product recovery volume with the apparent static size of
the plume suggests that the original volume estimate may have been low, or that
recovery volumes are optimistic, or both.
•	Additional geologic investigation in the area of the Exxon/Mobil On-Site plume
appears warranted. This area exhibits the thickest product accumulations, but also the
lowest product recovery rates. This information is also necessary for construction of
the numerical model.
•	The continued use of dual-phase recovery as the primary remedial method is
recommended. This has been used by most of the responsible parties through 2006
and appears to be the most efficient procedure at present, given the extent and volume
of recoverable free product. However, these recovery systems were put on hold
because of impending lawsuits concerning the extent to which the discharges of
treated effluent are permitted by the State. (As of June 28, 2007, Exxon/Mobil has
restarted both the On-Site and Off-Site groundwater pumping, recovery pumping and
treatment systems. Preliminary feedback indicated that the pumping is operating
between 150-220 gpm. The BP system is undergoing final systems checks and will
initiate pumping soon. NYSDEC representatives have been present during the system
startups and have sampled the discharges to ensure they have met the State Pollutant
Discharge Elimination System (SPDES) Equivalents. Additional sampling and
monitoring will occur over the near term.)
5.	Extent and Mitigation of Dissolved Product Plume:
•	NYSDEC should investigate, and collect additional data on, the extent of the
dissolved plume. Very little data have been collected to date in reference to the
dissolved phase of the plume.
6.	Vapor Intrusion:
•	NYSDEC should continue investigations based on results from houses with elevated
subslab and indoor air concentrations along Meeker Avenue.
•	NYSDEC has and should continue to attempt to get access to additional homes along
10

-------
Kingsland Avenue, Van Dam Street, Meeker Avenue, and South of the Brooklyn
Queens Expressway (BQE) for further sub slab and indoor air sampling to close
existing data gaps.
•	NYSDEC should make readily available a decision matrix/flowchart for the
Greenpoint community that clearly explains how data are being evaluated and how
risk management decisions are being made regarding subslab, indoor, and ambient
concentrations.
•	NYSDEC should continue outreach to commercial facilities which are located within
the residential areas (delicatessens, shops, etc.) to get access, so that vapor intrusion
data can be collected.
•	NYSDEC should continue to evaluate ground water data for both the free product
plume and the dissolved phase plume to determine if boundaries of the vapor
investigation should be revised.
•	NYSDEC should evaluate its ambient air monitoring program to investigate potential
confounding sources to indoor air.
•	Naphthalene should be added to the analytical suite of subslab sampling data.
•	NYSDEC should evaluate existing databases for background air concentrations in
similar communities for comparison against the Greenpoint community.
7. Natural Resource Damages:
•	EPA, as the co-chair of the Regional Response Team (RRT), should continue to
monitor progress relating to the Newtown Creek/Greenpoint oil spill. EPA should
also assist the natural resource damage trustees, as appropriate, under Federal laws
and regulations.
11

-------
Chapter 1
12

-------
NEWTOWN CREEK OIL SPILL
A REVIEW OF REMEDIAL PROGRESS (1979-2007)
AND RECOMMENDATIONS
NEWTOWN CREEK OIL SPILL SITE
BROOKLYN, NEW YORK
MAY 2007
U. S. EPA Work Assignment No. 0-228
Lockheed Martin Work Order No. EAC00228
U. S. EPA Contract No. EP-C-04-032
Prepared by;
Prepared for:
Lockheed Martin/REAC
U. S. EPA/ERT
Ken Woodruff 1
Donald T, Bussey. Hydrogeologist, Technical
Advisor
Andre' P. Zownir. Work Assignment Manager

mis A, Miller
Program Manager
13

-------
CHAPTER 1
TABLE OF CONTENTS
LIST 01 ACRONYMS AM) ABBREVIATIONS	16
SUMMARY	17
1.0	INTRODUCTION	21
1.1	Purpose	21
1.2	Background	21
1.2.1	Spill Discovery	21
1.2.2	Historical Land User and Property Ownership	23
2.0 GERAGHTY & MILLER 1979 REPORT	23
3.0	NEWTOWN CREEK SEEPS	24
3.1	Seep Areas	24
3.2	Present Recovery Techniques and Effectiveness	25
3.3	Technology Advances	26
3.4	Data Acquisition and Deficiencies	26
3.5	Recommendations and Conclusions	27
3.5.1	Peerless Recovery System	27
3.5.2	Grout Wall Performance	27
3.5.3	Additional Recovery Wells	27
4.0	FREE-PRODUCT PLUME	28
4.1	Plume Extent	28
4.2	Plume Thickness	29
4.3	Plume Volume	30
4.4	Recovery/Mitigation Techniques	31
4.4.1	History	31
4.4.2	Effectiveness of Recovery 	33
4.4.3	Mitigation/Recovery Time	35
4.5	Data Deficiencies	35
4.6	Recommendations and Conclusions	36
4.6.1	Well Redevelopment	36
4.6.2	Re-injection of Treated Water	36
4.6.3	Additional Recovery Wells	37
4.6.4	Bioslurping/Vacuum Enhanced Recovery	38
4.6.5	Steam/Hot Water Injection	39
4.6.6	Electrical Heating	39
4.6.7	Bioremediation	39
5.0	DISSOLVED-PRODUCT PLUME	40
5.1	Data Acquisition and Deficiencies	40
5.2	Recommendations and Conclusions	41
6.0 CONCLUSIONS	41
7.0 RECOMMENDATIONS	43
8.0 REFERENCES	45
APPENDIX A	48
Diagram of Current Seep Containment System	49
14

-------
Diagram of Containment Booms on Newtown Creek	50
APPENDIX B	51
Unadjusted Product Thickness Contour Map (Delta, 2002)	52
LIST OF TABLES	53
Table 1-1 Product Well Volume and Recovery Estimates	54
Table 1-2 Recovery Well Data	55
Table 1-3 Free-Product Potential Remedial Methods	57
LIST OF FIGURES	58
Figure 1 Index Map	59
Figure 2 Property and Seep Locations	60
Figure 3 Product Extent and Thickness as Mapped by Geraghty & Miller (1979)	61
Figure 4 Regional Aquifer Apparent Free Product Thickness	62
Figure 5 Recovery Well Locations	63
Figure 6 Monitor Well Locations	64
Figure 7 Generalized Groundwater Flow Directions - May/November 2006	65
Figure 8 Dissolved Groundwater Analytical Data	66
15

-------
LIST OF ACRONYMS AND ABBREVIATIONS
AOC - Administrative Order on Consent
API - American Petroleum Institute
AST - above ground storage tank
Delta - Delta Environmental Consultants
E&E- Ecology and Environment
ERT - Environmental Response Team
IT - International Technology Corporation
LB&G - Leggette, Brashears & Graham, Inc.
MATF - Meeker Avenue Task Force
Mgal - million gallons
MTBE - methyl tertiary-butyl ether
NYSDEC - New York State Department of Environmental Conservation
PRP - Principal Responsible Party
REAC - Response Engineering Analytical Contract Roux- Roux Associates
SAIC - Science Applications International Corporation
SOCONY - Standard Oil of New York
SPDES - State Pollutant Discharge Elimination System
USCS - United States Coast Guard
U. S. EPA - Environmental Protection Agency
USGS - United States Geological Survey
VER - vacuum enhanced recovery WA - Work Assignment
16

-------
SUMMARY
Under Work Assignment No. 0-228, the U. S. Environmental Protection Agency/Environmental
Response Team (EPA/ERT) has requested personnel of the Response Engineering and
Analytical Contract (REAC) to review industry reports pertaining to investigations undertaken
for the Newtown Creek site located in the Greenpoint area of Brooklyn, New York (Figure 1-1).
The site covers approximately 55 to 60 acres and is underlain by a plume of mostly petroleum
distillates that rest on top of the groundwater column. The spill was first discovered in 1978 by a
routine U. S. Coast Guard (USCG) patrol that observed a seep into Newtown Creek at the foot of
Meeker Avenue (Figure 1-2). The firm of Geraghty & Miller completed the initial investigation
of the spill extent in 1979 for the USCG and produced the first map of the spill extent (Figure 1-
3). They indicated that the minimum spill volume was probably about 17 million gallons (Mgal).
Product recovery estimates and the present free-product extent suggest that the 1979 estimate
may have been somewhat low. Smaller additional spills have occurred after the discovery of the
Meeker Avenue seep and have been documented in various consulting reports (e.g., Delta
Environmental Consultants, 2000).
Primarily in response to directives from the New York State Department of Environmental
Conservation (NYSDEC), over 20 additional investigative studies have been completed and
numerous work plans, progress reports, and information packages issued since 1979. Some of
these investigations have resulted in periodic remapping of the plume extent and the apparent
thickness (Figure 1-4). Approximately 35 product and groundwater recovery wells (Figure 1-5)
and over 200 monitor or observation wells (Figure 1-6) have been installed since 1978. Parties
to the investigations have included major petroleum companies that have operated terminals or
other facilities in the area for several decades, both before and after the spill discovery.
At present, the extent of the free-product plume is divided into four specific areas of
responsibility (Figure 1-2): (1) the "On-Site" area which includes the ExxonMobil properties
that overlie the northern portion of the plume, (2) the BP Amoco terminal that borders
Newtown Creek to the southeast of the Exxon/Mobil facility (3) the "off-site" area which
includes commercial and residential areas in the central and southern portion of the plume for
which Exxon/Mobil has taken remedial responsibility, and (4) the former Paragon Oil Property
(now Peerless Importers™ and Steel Equities facilities) bordering Newtown Creek, now being
remediated by Chevron Texaco . Over 200 monitor/observation wells and approximately 35
designated recovery wells have been installed in the project area since 1978. Until recently,
approximately 23 recovery wells were active, including six monitor wells that have been
converted to recovery wells. However, in early March 2007, groundwater pumping from the On-
Site and off-site dual phase (ground water and product) recovery wells was suspended by the
principal responsible party (PRP). Product recovery will apparently continue, but the cones of
groundwater depression developed around the recovery wells (Figure 1-7) that help control
product movement will dissipate with time. It is not presently known when groundwater
pumping will be reinstated.
Numerical modeling has indicated that it may take up to approximately 25 years (from 2001) to
recover up to an estimated maximum of about 70 percent (%) of the free product in the off-site
17

-------
plume. No model estimate appears to be available for recovery time of the On-Site plume
beneath the Exxon/Mobil facilities. The On-Site plume exhibits the greatest apparent free-
product thickness but also appears to have the lowest apparent recovery rate for the On-Site and
off-site plume designations.
In addition to the general document review, specific goals of the study were: (1) review the 1979
Geraghty & Miller U. S. Coast Guard report for conclusions and recommendations, (2) assess
the extent of the free-product plume, (3) determine the presence and extent of a dissolved
product plume outside of the area underlain by the free-product plume, (4) determine the
adequacy of current remedial measures, both for recovering product in the subsurface and for
preventing seeps into Newtown Creek, and (5) present recommendations for enhancing or
accelerating product recovery. Findings included the following:
•	The 1979 Geraghty & Miller report can be considered fairly comprehensive for
the relatively short period of investigation that led to this report. However, the
northern portion of the plume (Figure 1-3) was not entirely delineated because of
the lack of monitor well coverage. Later investigations (Figurel-4) indicate that
the northern extent of the plume was larger than originally mapped in 1979. The
thickness of the original free-product plume, as mapped by Geraghty & Miller,
was also based on uncorrected product thickness as measured in monitor wells.
Using uncorrected thickness would normally give larger than actual plume
volumes. However, because the spatial extent of free product was not entirely
defined, the free-product volume estimate may have been low. Comparison of
product recovery volume (8.8 Mgal) to date with the original 17 Mgal estimate of
product volume and to the present size of the plume also suggests that the original
volume estimate may have been low, or that recovery volumes are optimistic, or
both.
•	The Geraghty & Miller report focuses largely on defining the geology, spill
extent, and source area but does not include extensive recommendations for a
comprehensive response to the spill. The report recommends recovery wells
should be installed initially at three sites with two years of pumping projected for
a free-product recovery of approximately 50 percent (%). Pumping would then be
followed by two years of biodegradation techniques for a total product removal of
approximately 70 %. This projected clean-up time has since been shown to be
overly optimistic as discussed above, although the report indicated that additional
recovery wells might be required. Also, additional techniques for recovery or
remediation of petroleum-contaminated sites have been developed or improved
since 1979.
•	The present boom and well recovery system appears to be minimizing and
containing product discharges into Newtown Creek from the Peerless property,
but not remediating them completely. The recently installed grout wall along the
Creek should help prevent further seeps in the short term, although it is too early
to judge its long-term effectiveness. In the long-term, it is likely to be a temporary
containment measure. It is possible that product will eventually find a path
18

-------
around the end of the grout wall until product can be permanently removed, or
induced to flow away from the creek by additional recovery wells.
Until recently, product beneath Peerless Importers, bordering Newtown Creek,
was considered to be separate from the larger main free-product plume and had
been recovered by vacuum trucks or skimming methods, rather than by water-
level depression. This prevented the recovery of unwanted creek water and the
initiation of product movement beneath Peerless Importers towards Newtown
Creek, but provided no control of groundwater levels in the immediate vicinity of
the recovery wells. The main free-product plume has since been shown to be
contiguous with the product beneath the Peerless facility (SAIC, 2007) and,
therefore, remains a continuing source of potential seeps. Moreover, following the
completion of the grout wall, dual-phase extraction pumps were installed in the
Peerless recovery wells. These wells have the potential to accelerate product
movement beneath Peerless, and therefore, their effect on migration of the off-site
plume should be assessed.
The present extent of free product is generally well mapped (Figure 1-4), given
present monitor well coverage (Figurel-6) and additional wells that are planned
for installation in 2007. Variations in plume extent, however, can be expected
over time as remediation continues. Minor differences in plume extent (and
thickness) among various reports can also be expected depending on the time of
field measurements and the specific mapping procedures employed. Product
thickness, as indicated on most maps presented in the various reports, should be
considered only an approximation. True product thickness, as measured in
monitor wells, is often difficult to consistently determine but is usually greater
than actual thickness for reasons related to differences in density between the
ground water and product.
The greatest apparent (uncorrected) product thickness, approximately 15 to 20
feet, underlies the Exxon/Mobil North Henry Street Terminal. It is possible that
confined hydrologic conditions and/or fine-grained soils are exaggerating product
thickness, a common phenomena affecting measurements made in monitor wells.
Recovery well yields in this area appear to be less than might intuitively be
expected and product thickness has not appeared to decrease significantly. In
particular, recovery well RW-20, located in this area (Figurel-5) pumps little
product. Exxon/Mobil is apparently replacing neighboring recovery well RW-19
that appears to be pumping approximately 25 gallons of product per day, but no
plans are indicated for RW-20. Numerical modeling methods, similar to those
completed for the off-site area (Roux, 2003) are recommended to better determine
true free-product thickness in the Exxon/Mobil On-Site area.
The primary remedial method used by most parties through 2006 was wells with
dual pumping systems that lower water levels and recover water and product in
separate systems. This method continues to be effective at the moment, given the
extent and volume of recoverable free product. Synthesis from various reports
indicates that approximately 8.8 million gallons of product have been recovered.
19

-------
An estimate derived from a numerical model of approximately 25 to 30 additional
years (from 2001) to recover free product from the off-site plume appears
reasonable based on the present approach of using dual-phase recovery wells
(Roux, 2003). Recently proposed additional recovery wells, not included in the
model, may shorten this time. This is the most aggressive and technically feasible
method to recover the bulk of free product. No estimate of product recovery time
appears to be available which incorporates both the On-Site and off-site free-
product volume. However, as more product is recovered, the recovered volume
will decrease, therefore increasing recovery time. Not all product can be
recovered without a large scale removal action. A removal action of this scale
that would be logistically and economically unfeasible. Ultimately, up to perhaps
70% of the total volume of the plume may be recovered by wells. The impact of
the remaining product is difficult to predict with certainty. The remaining product
would potentially contribute to a dissolved-phase plume and could also remain a
potential source of soil vapors.
Other remedial technologies may be applicable for recovering additional product
once the bulk of free-product has been recovered. These include injection of
surfactants or biological remedial compounds, bioslurping, vacuum enhanced
recovery, steam or hot water injection, and electrical heating. All of these
methods would require detailed study prior to implementation and their use will
be constrained by the urban setting and infrastructure. Injection methods using
chemicals, for example, generally require an organized grid of wells and have the
potential to move product outside of the project area. No significant discussion of
other remedial methods and their potential application or rejection was found in
those reports, mainly produced by or for principal responsible parties, and made
available to REAC.
Some data on the dissolved product plume are available (Figure 1-8) just outside
the margins of the free-product plume and indicate concentrations of primary
gasoline compounds in groundwater are orders of magnitude lower than
groundwater samples from within the free-product plume.
Remedial activities for the various areas of responsibility on the Newtown Creek
site have been carried out independently by multiple responsible parties with no
apparent coordination. A site-wide feasibility study is needed that addresses
issues such as the total effect of recovery wells on site-wide plume movement,
evaluates all potential remedial options, and recommends site-wide long-term
remedial plans. NYSDEC efforts in this direction may be hindered by statutory
limitations and the presence of multiple responsible parties.
Both present recovery techniques and those indicated in this report as possible
alternatives will be affected to various degrees by both logistical and
administrative restrictions. For instance, the presence of utilities, buildings and
other constraints imposed by the urban setting may limit recovery well placement
to less than preferred locations. The use of injection wells and the re-injection or
discharge of recovered groundwater are subject to State and Federal regulations or
20

-------
policies. Thus, targeted feasibility studies are necessary before the applicability
of specific techniques can be determined.
1.0 INTRODUCTION
1.1 Purpose
This report is provided under Work Assignment (WA) No. 0-228, issued by the
staff of the Environmental Protection Agency/Environmental Response Team
(EPA/ERT) to personnel of the Response Engineering and Analytical Contract
(REAC). The WA was issued in response to a congressional-mandated study by
EPA of an historic oil spill adjacent to Newtown Creek in the Greenpoint section
of Brooklyn, New York. Elements of the study that were considered to meet the
congressional directive in this report include (1) reviewing the 1979 Geraghty &
Miller U. S. Coast Guard report for conclusions and recommendations, (2)
assessing the extent of the free-product plume, (3) determining the presence and
extent of a dissolved product plume outside of the area underlain by the free-
product plume, (4) determining the adequacy of current remedial measures, both
for recovering product in the subsurface and for preventing seeps into Newtown
Creek, and (5) recommending ways to enhance or accelerate mitigation measures
for free product and the seeps into Newtown Creek. The study was carried out
through a general review of existing documents generated by the principal
responsible parties (PRPs) and their consultants as provided by the NYSDEC
through EPA to REAC.
1.2 Background
1.2.1 Spill Discovery
The Newtown Creek oil spill was discovered in September 1978 by a United
States Coast Guard (USCG) routine patrol (Geraghty & Miller, 1979; Delta
Environmental Consultants [Delta], 2000). Oil was observed on Newtown Creek
that on further investigation was found to be seeping from a bulkhead at the foot
of Meeker Avenue (Figure 1-2). Preliminary investigations were conducted by the
USCG, the City of New York, and various companies with properties adjacent to
the spill area, including several major oil companies. In early 1979, an industry
advisory committee was established with technical assistance and advice provided
by the American Petroleum Institute (API). The advisory committee included
representatives from local government and state agencies, the U. S. Geological
Survey (USGS), and the firms of Amoco (now BP Amoco), Exxon (now
Exxon/Mobil), Gulf, Mobil (now Exxon/Mobil), Shell, Texaco (now Chevron
Texaco), and Buckeye Pipeline . In August 1979, the USCG withdrew from
active participation in cleaning up the spill, based on the premise that the State oil
spill program fund was established in April 1978, after the spill occurred.
Subsequently, the Meeker Avenue Task Force (MATF) was formed that included
21

-------
the participation of the City of New York, Amoco, Mobil, Texaco, and other local
and state regulatory agencies (Delta Environmental Consultants, Inc [Delta],
TM
2000; Science Applications International Corporation [SAIC], 2006). The
MATF recovered nearly 230,000 gallons of product by recovery wells installed
near the foot of Meeker Avenue before being disbanded in 1990 (Delta, 2000). In
February 1990, Mobil agreed to remediate the "On-Site" free- phase plume under
an Administrative Order on Consent (AOC), and in June 1990 also agreed to
remediate the "off-site" portion of the plume. The "On-Site" plume includes that
portion of the free-product plume beneath the existing Exxon/Mobil facilities
(Figure 1-2), whereas the term "off-site", refers to the remaining portion of the
plume, except that beneath the BP Amoco facilities. These terms are used in this
report in order to be consistent with the terminology consistently used in the
reports of the various responsible parties or their consultants. It should be noted
that the entire "off-site" study area, as defined by Roux (1991), encompasses
approximately 14 acres and extends from the North Henry Street Terminal on the
north, Newtown Creek to the east, Lombardy Street to the south, and Kingsland
Avenue to the west (Figure 1-2).
Early in the initial investigations, the USCG employed the firm of Geraghty &
Miller to conduct an investigation into the extent, thickness, and source of the
free-product plume. Their work resulted in a July 1979 report that outlined the
extent of free product (Figure 1-3) and formed much of the basis for later work by
other consulting firms. Based on analysis by various petroleum companies
involved in the investigation, Geraghty & Miller concluded that the product was
comprised of the various distillates including naptha, fuel oil, and a small
percentage of gasoline. They also estimated the total free-product volume to be
approximately 17 million gallons (Mgal), although they acknowledged that the
estimate might be low. The greatest apparent product thickness, about 20 feet,
occurred along Kingsland Avenue at the Mobil North Henry Street Terminal in
what was mapped by Geraghty & Miller as a separate plume. A second, more
extensive free-product plume, with a maximum apparent thickness of about six
feet, extended beneath the property now owned by BP Amoco to just south of
Meeker Avenue and was identified by Geraghty & Miller as the source of the
discharge to Newtown Creek. The Geraghty & Miller report indicated that the
source of both spills was probably leaking product storage tanks or leaking
pipelines on the former Mobil refinery. At the time, no connection was
established between the two sources. Later work, as discussed in the sections
following, has indicated that the two plumes described in the Geraghty & Miller
report are indeed a single plume.
It should be noted that hydrocarbon accumulations were being detected
throughout the Greenpoint area as early as the 1950s (Delta, 2000), generally
incidental to construction projects. Also, Leggette, Brashears & Graham, Inc.
(LB&G) conducted an extent of product investigation beneath the Mobil North
Henry Street Terminal in 1972 (LB&G, 1990) and had installed 85 observations
wells between 1972 and 1979 to monitor product accumulation. This effort also
22

-------
included the installation of one recovery well (Mobil RW-1) and two well-point
systems to recover product. Since 1978, smaller releases of various petroleum
products have occurred on the properties of Exxon/Mobil and BP Amoco and
from Buckeye Pipeline which served the Amoco terminal. These spills are listed
in detail by Delta (2000).
1.2.2 Historical Land Use and Property Ownership
The Greenpoint area has a history of oil refining or ownership by petroleum
companies dating back as early as 1834 (SAIC, 2006). The SAIC report provides
a particularly detailed history of land ownership in the area, in some cases by
individual blocks or lot, and presents a graphical time line of historic property
uses.
In the early 1900s, Standard Oil of New York (SOCONY) operated a major
refinery that included an area of approximately 79 acres, extending along
Newtown Creek from approximately Apollo Street, west beyond Kingsland
Avenue, and north again to Newtown Creek (SAIC, 2006). The refinery produced
fuel oils, gasoline, kerosene and solvents. Naptha and gas oil, secondary
products, were also stored in the refinery area. SOCONY later became Mobil, the
predecessor to Exxon/Mobil, and also operated a refinery on approximately 55
acres that constitutes the present area of investigation.
Mobil ceased operations in 1965 when the property was subdivided and sold. Ten
acres of the original refinery were purchased by Amoco (Figure 12) which
constructed a bulk storage facility on the property, whereas the remaining lots
were purchased by other non-petroleum businesses. Mobil retained the North
Henry Street 15 acre parcel. In addition, Paragon Oil Company, owned by
Texaco, operated a terminal just south of the Amoco Property until approximately
1964. Peerless Importers, a liquor distributor, then purchased the former Paragon
facility and presently operates a warehouse and distribution facility there
(Figurel-2). The area along Newtown Creek, adjacent to the Peerless property, is
the location of present day product seeps.
2.0 GERAGHTY & MILLER 1979 REPORT
The Geraghty & Miller report, prepared for the USCG, was the first report dealing with the
spill. The work was carried out over approximately ten months and included mapping the extent
of the spill, calculating the spill volume, describing the geology of the spill area, determining
the travel time of the product and determining the probable source. Except for the mapping of
the northern portion of the free product plume, which the report depicted as two smaller
separate plumes, the Geraghty & Miller work has remained basically sound. The bulk of the
report is descriptive but includes some recommendations for product recovery in the "Meeker
spill area." The Meeker spill area of Geraghty & Miller presently corresponds to the
Exxon/Mobil off-site area. An initial pilot recovery system consisting of one dual-phase well
23

-------
was recommended in the Meeker Avenue area, based on aquifer characteristics obtained from
pump tests in observation wells. One well would pump only ground water and lower the water
level, and an adjacent well would recover product from the top of the groundwater column.
This is essentially the same technique used by the dual-pump systems installed in the present
day recovery wells. The Geraghty & Miller pilot program would then be followed by at least
three other well pairs, with the implication that more well pairs may be needed. The location of
six possible recovery sites were shown in the report, based on plume thickness and accessibility.
Existing off-site recovery well locations are close to five of the original recommended locations
and BP Amoco Recovery Well 5 (ARW-5) is near the remaining location. Differences in the
original recommended locations and existing locations are probably due to changes in site
availability and plume thickness. During the initial spill investigation, New York City also
ordered a recovery system to be installed on the (then) Amoco property. Although the New
York City order is mentioned in the Geraghty & Miller report, no specific recommendations for
the installation of the system are provided except that its performance should be monitored.
Geraghty & Miller estimated that a maximum of 50% of initial product volume could be
recovered by wells. Tablel-1 suggests that indeed this amount has been recovered, assuming the
original product volume estimate was correct. Water flooding and biodegradation techniques
were suggested as methods to increase product recovery to 70% once the product thickness had
been reduced so that recovery by water-level depression was no longer efficient. Geraghty &
Miller also indicated that recovered ground water could be discharged to the storm sewer system,
or alternatively to Newtown Creek. Nevertheless, their cost estimate for a Meeker spill area
recovery system contains a line item for "re-injection of pumped water." There is no discussion
of this item in the text of their report, or in any later reports reviewed in this study, but it is
assumed that the reference is to re-injection of water into the aquifer.
There are no additional recommendations in the Geraghty & Miller 1979 report. Other
recommendations were made by LB&G in 1981 for installation of additional monitor wells in
the North Henry Street Terminal and in 1987 for various operational parameters of the existing
recovery wells. Five additional monitor wells were installed in 1982 (LB&G, 1990) in keeping
with the 1981 recommendation.
3.0 NEWTOWN CREEK SEEPS
3.1 Seep Areas
In 1978, when seepage of oil was first discovered in Newtown Creek, the
primary discharge point was around the bulkhead at the base of Meeker Avenue.
Identification of the former Mobil refinery property by Geraghty & Miller in
1979 as the source of the product was based on hydrocarbon forensics analysis,
free-product thickness in the subsurface, and groundwater flow directions
deduced from existing monitor wells.
Between 1979 and 1991, apparently no seepage was occurring off Peerless
Importers. However, in 1991, free-product seepage was discovered off the
24

-------
Peerless waterfront. From 1991 to 2002, Exxon/Mobil contained and recovered
the product and in 2002 a steel sheeting bulkhead, approximately 650 feet long,
was installed on the Peerless property along the Newtown Creek shoreline (Figure
1-1, Appendix 1-A). Another 500 feet of older concrete and wooden bulkhead is
present to the east of the steel bulkhead. In 2004, Exxon/Mobil conducted a site
investigation and concluded that the product seeping into the waterway off the
Peerless property was not related to Exxon/Mobil's larger 55-acre free-product
plume. This conclusion, however, may be questioned as discussed in later sections
of this report. At present, seepage continues into Newtown Creek along a portion
of the steel bulkhead.
3.2 Present Recovery Techniques and Effectiveness
From 1993 through mid-2005, Exxon/Mobil collected approximately 29,000 gallons of
free product from Newtown Creek, primarily through the use of containment booms and
free-product skimmers. Diagrams of the containment booms from SAIC (2006) are
provided in Appendix 1-A. In addition, the Meeker Avenue seep recovery system that
operated through 1998, collected another approximately 800,000 gallons of free product
from the north end of Meeker Avenue.
Since 2005, Texaco, Inc., (SAIC, 2006) has taken over the remedial activities at the
Peerless site, and has been conducting both site characterization and free product
recovery activities. Remedial activities have involved seep containment using (1) a
boom system and (2) product removal by extraction from several monitoring wells
immediately landside of the steel bulkhead, initially using vacuum trucks.
In July 2005, the containment boom system on the creek at the current seep area was
upgraded to reduce sheen bypassing the boom due to wake spillage. The new hard
containment boom (a globe boom) was installed and stabilized (using a series of I-beams
and stabilizer bars) approximately 2-feet away from the bulkhead. The new globe boom
is comprised of a continuous PVC coated conveyor belt with molded high-density
polyethylene float shells filled with foam. This boom has twelve inches of free board
(portion above the water) and twelve inches of draft (portion below the water surface).
The globe boom has underwater ballasts to keep it upright in order to provide a greater
degree of product containment. Two rows of soft adsorbent booms are presently in place
within the "globe boom" and help collect product sheen and droplets. The globe boom
and the soft booms are attached to the steel bulkhead at the east end but extend onto the
Steel Equities property at the west end.
In March 2006, a product sheen was noticed seeping into Newtown Creek west of the
hard globe boom, behind the Steel Equities property at 110-120 Apollo Street. In
response, Texaco, Inc. installed an additional 100 feet of hard and soft booms to contain
this seep.
25

-------
In June 2006, an additional hard containment boom (a fence boom) was installed 10 to 20
feet farther away from the steel bulkhead to provide secondary containment for the
product seep. The fence boom consists of an impermeable polyester-polyurethane
composite fabric with extra wide outrigger floatation supports. The fence boom has 24
inches of free board and 24 inches of underwater draft. A row of soft adsorbent boom is
presently in place to capture sheens that spill over the globe boom system. At present,
approximately 1,750 feet of soft adsorbent boom is apparently being replaced every two
weeks. Since July 2005, when the weekly vacuum extraction of free product was
initiated, the amount of free product seeping into the Creek off the former Paragon Oil
facility has apparently been reduced to sheens and discrete droplets.
3.3	Technology Advances
As discussed below, Texaco, Inc. has replaced the periodic vacuum extraction from
selected monitor wells located immediately behind the bulkhead with a total fluids
recovery system which collects both ground water and product. The primary objective of
this system is to intercept and collect free product before it seeps into Newtown Creek. In
addition, a grout wall was completed in November 2006 immediately landside of the
entire bulkhead frontage (Figure 1-2) to impede the migration of product into Newtown
Creek.
The product and ground water extracted from the subsurface behind the bulkhead is first
treated by an oil water separator. Product from the oil water separator is temporarily
stored in a 1,000-gallon above ground storage tank (AST) before it is transported off-site
for disposal or recycling. The water from the oil water separator is transferred to a 6,500-
gallon insulated above ground storage tank (AST). This water is then transferred to the
existing Exxon/Mobil treatment plant on Meeker Avenue for treatment.
3.4	Data Acquisition and Deficiencies
In recent years, SAIC on behalf of Texaco, Inc., has collected a significant amount of site
characterization data for the Peerless property and adjacent areas. Based on its findings,
SAIC (2006) indicates that the free product that was originally mapped at the steel
bulkhead (primarily on the western portion of the Peerless property and on the 110-120
Apollo Street properties) as two separate plumes, now in fact appears to be one plume
that is contiguous with the much larger off-site plume. REAC believes it is necessary to
determine how the recently installed total-fluids extraction system would impact the
movement of the off-site plume. The new remedial system extracts both ground water
and product and thus induces a cone of depression in the groundwater system that would
move product beneath the Peerless facility and towards Newtown Creek. The analysis
could best be done with a multi-phase numerical model although field pumping tests and
analytical methods might also provide good estimates.
No definitive data is presently available on the relationship of the free-product plume and
the seep at the Steel Equities property. However, in January 2007 the NYSDEC issued a
26

-------
work assignment to Ecology and Environment™ (E&E) for a remedial investigation at this
property. The work is expected to address this issue and is scheduled for completion in
late 2007.
Recommendations and Conclusions
Based on the review of data and reports available to date, the following conclusions can
be drawn with respect to the seepage along Newtown Creek:
3.5.1	Peerless Recovery System
The present containment and recovery system appears to be preventing gross
contamination of Newtown Creek. However, the total-fluids well recovery
system now in use on the Peerless property has the potential to induce migration
of free product from the larger off-site plume across the Peerless property,
thereby increasing the potential for continued seepage into Newtown Creek.
3.5.2	Grout Wall Performance
The extended grout wall should provide short term benefit by slowing down the
migration of free product into Newtown Creek. However, the presence of the
seeps suggests a northerly net groundwater flow pattern towards Newtown Creek,
even though this is not apparent in the generalized groundwater level data for
May 2006 (Figure 1-7), derived from the most recent site-wide map available.
Data for February 2006, (SAIC, 2006) more definitively suggests a northerly
flow. Small differences in direction of groundwater flow along Newtown Creek as
indicated by various data sets, probably depend on the tidal cycle when
measurements were taken. SAIC (2006) indicates that during high tides ground
water along Newtown Creek flows south, away from the stream but a northerly
flow towards the Creek develops during mid to low tide. Free-product may
therefore eventually find its way around the grout wall to an alternate seepage
point, unless intercepted by additional recovery wells. Indeed, seepage apparently
continues at the adjacent Steel Equities property (Figure 1-2).
3.5.3	Additional Recovery Wells
Apparent proposals to install additional recovery wells along Bridgewater Street
in front of the Peerless facility (Remedial Engineering and Roux Associates,
2007b) are timely, and, if implemented, will likely capture product moving
northeasterly beneath Peerless.
27

-------
4.0
FREE-PRODUCT PLUME
4.1 Plume Extent
As previously stated, the original extent of free product (Figure 1-3) was outlined
in the 1979 Geraghty & Miller report to the USCG, based upon measurements in
over 100 monitor wells installed during the initial investigations. The extent and
shape of the plume has gradually been refined through investigations by a number
of other consultants employed by the various responsible parties involved in
remedial activities. LB&G (1991) mapped free-product thickness in the shallow
aquifer underlying the North Henry Street Terminal and also outlined the free-
product plume extent in the deeper regional aquifer. A silt unit separates the two
water-bearing units beneath the North Henry Street Terminal area and acts as a
confining layer for the lower regional aquifer. The pathway by which product
migrated into the regional aquifer is uncertain. Geraghty & Miller (1979) allude to
a nearby industrial well in the regional aquifer that may have caused product
migration. In addition, more recent work has indicated that the silt layer is not
continuous across the project area.
Roux, in a 1991 report for Mobil, mapped the extent of free product in the off-site
area south of the Amoco property, whereas the free-product plume beneath the
Amoco facility was defined by International Technology Corporation (IT) in a
1993 report. The plume underlying the (now) BP Amoco property was remapped
by Delta in a 2002 report for BP Amoco. In the same report, Delta also mapped
the extent and thickness of the entire free-product plume.
The extent and thickness of the entire free-product plume was also mapped by
Roux in a 2003 report for Exxon/Mobil and again in 2005 (draft) and 2006. The
2003 report shows the plume superimposed on a historic map of the Greenpoint
area but details are difficult to discern because of the relatively small scale of the
map. However, the 2005 and 2006 reports shows the free-product extent
superimposed on a recent map of the area for November 2005 and February 2006
respectively. The 2006 SAIC Site Characterization Report for the former Paragon
Oil Terminal also includes a map of the extent of free product in July 2005 which
is nearly identical to that of the Roux maps.
The Roux November 2005 map, with modifications taken from the Roux
February 2006 map and September 2006 SAIC data, is presented here as Figure 1-
4. The major free-product plume is apparent with smaller separate thin plumes at
(1) the north end of Meeker Avenue, and (2) just east of the intersection of
Bridgewater Street and Kingsland Avenue. The plume at the north end of Meeker
Avenue is probably a remnant of the main plume, resulting from a hydraulic
divide formed between recovery wells RW-E and RW-F (Figure 1-5) and
recovery wells located further to the southwest. The small product accumulation
to the north, along Kingsland Avenue, may also be a remnant of the main On-Site
28

-------
plume and was mapped for the first time by Roux in 2005. A comparison of the
Roux maps with the earlier Delta 2001 plume maps shows some significant
differences in plume extent and thickness. Compared to the Roux mapping, Delta
indicates an expanded plume in the northwestern portion of the project area along
Kingsland Avenue and at the southern end of the plume along the Brooklyn
Queens Expressway. The reason for the difference is uncertain but is possibly a
consequence of what may be a computer generated Delta map as opposed to a
manually- drawn map. Computer generated maps often require manual editing,
based on professional judgment, to better represent actual field conditions.
The relationship of the Peerless free-product plume to the off-site plume was
initially not entirely clear. Based on the absence of product in monitor wells
MW76 and MW-77 (Figure 1-6), Roux (2005 draft) believed that the off-site
plume and the plume beneath the Peerless property were separate and therefore
the main plume was not the source of seeps into Newtown Creek. However, the
Roux February 2006 product thickness map shows detectable product thickness in
these latter two monitor wells. Moreover, the shape of the off-site plume in the
Roux 2005 and 2006 plume map, and more recent data by SAIC (2006, 2007)
indicates that the product beneath the Peerless property is contiguous with the off-
site plume and plume beneath the BP Amoco terminal.
The shape of the free-product plume (but not necessarily the extent) as mapped by
Geraghty & Miller, is generally similar to that in all of the later consulting reports,
with the exception that Geraghty & Miller depicted a large plume, generally
corresponding to the present off-site plume and that beneath a portion of BP
Amoco, and two smaller separate plumes beneath the Exxon/Mobil (Figurel-3).
The western portion of the plume as shown in later reports is somewhat expanded
from the original Geraghty & Miller mapping and the eastern portion appears to
be moving across the former Paragon property as discussed previously. The extent
of free-product should be well defined, given the present monitor well coverage
(Figure 1-6) and additional installations planned in 2007.
4.2 Plume Thickness
The original thickness of the entire free-product plume, as mapped by Geraghty &
Miller (Figure 1-3 ) for their 1979 report, was based upon measurements of
product thickness in existing monitor wells. Free-product thickness in monitor
wells is usually greater than the actual thickness in the aquifer. The difference
between measured and actual thickness varies, depending on the formation
material, the degree of aquifer confinement (e.g., water table or confined) and
fluid densities. A correction formula (dePastrovich et al.,1979) was applied by
LB&G (1991) to measured product thicknesses in their calculation of plume
thickness beneath the Mobil Kingsland Avenue Yard. Roux (1991), in a
numerical modeling approach to determine the effect of recovery wells on the
aquifer, indicated that the measured product thickness exceeded the actual product
29

-------
thickness by a factor of 3.85. They subsequently used this correction factor in
modeling the off-site spill volume. No correction appears to have been applied in
the Geraghty & Miller 1979 report, a procedure which would normally over-
estimate product volume. However, the extent of the northern section of the free-
product plume was not completely defined by Geraghty & Miller. This may
compensate to some degree for the use of uncorrected thickness measurements.
The thickest free product according to Geraghty & Miller was along Kingsland
Avenue at the North Henry Street Terminal, with uncorrected thicknesses
reaching 20 feet (Figure 1-3). However, because the plume at this location
appears to be confined or semi-confined, the apparent product thickness in wells
is much greater than actual thicknesses. Apparent maximum product
accumulation in the larger plume, located further to the south (now the "off-site"
and BP Amoco plume), was approximately six feet.
Both Delta (2002) and Roux (2005) present maps indicating that the greatest
apparent product thickness is in the northern portion of the plume area, beneath
the Exxon/Mobil property. The Delta map is included in this report as Appendix
1-B whereas the Roux map is shown as Figurel-4. There is a significant
difference, however, in uncorrected product thickness as shown on each of the
two maps. Roux indicates a maximum apparent thickness of slightly over 15 feet
whereas the earlier Delta map indicates a maximum thickness of only about seven
feet. The reason for the apparent difference is unknown. Free-product thicknesses
in the central portion of the plume beneath the BP Amoco Terminal appears to be
two to four feet less on the 2006 Roux map than on the Delta map and on the
Geraghty & Miller map, suggesting removal of product by recovery wells. The
Roux 2006 map was also reproduced by SAIC in their 2006 Site Characterization
Report for the former Paragon Oil Site.
Plume Volume
The most common method of determining free-product volume involves
measuring product thickness in observation wells, contouring the thickness over
the plume area, and then calculating the volume of product contained within the
plume area based on a given porosity. As indicated above, without correcting for
true product thickness in the formation, the volume estimate will likely be high,
assuming a reasonable porosity is used in the calculations. A more accurate
estimate of plume volume requires knowledge of several physical parameters of
both the formation and fluids. Because of their spatial variability, these
parameters are generally not known precisely so are often estimated and/or
averaged across the plume area. Except for the Geraghty & Miller 1979 report, no
calculations of total plume volume could be found in the documents available for
the REAC review. However, Roux (2003) indicates that various estimates have
placed the free-product volume between 10 Mgal and 17 Mgal, depending on the
assumptions made and the understanding of subsurface multiphase fluid behavior.
30

-------
Estimates have been made by various consulting groups for different portions of
the plume. For example, LB&G (1991) estimated the volume of the On-Site
plume beneath the present Exxon/Mobil facility to be approximately 1.6 to 2.5
Mgal (Tablel-1), based on corrected product thickness. This appears to agree with
the Geraghty & Miller estimate of approximately 1.9 Mgal for the same area,
even though Geraghty & Miller envisioned only two isolated plumes beneath the
(then) Mobil property.
The free-product volume beneath BP Amoco was calculated by Geraghty &
Miller to be 0.1 Mgal but IT (1993) estimated it to be approximately 1 Mgal,
using a hydrocarbon density of 0.75 grams/cubic centimeter (gr/cm ) and a
formation porosity of 30 percent (%). Using the numerical model SPILLVOL™,
Roux (1991) concluded that the off-site product volume was between
approximately 2.8 Mgal and 4 Mgal. These figures were revised by Roux in 2003,
based on the use of the BIOSLURP™ multi-phase flow model that indicated
approximately 5.3 Mgal of free product remained in the off-site plume. The Roux
2003 estimate appears to be based on more recently measured and estimated soil
and fluid properties, and is therefore probably the most accurate estimate of the
off-site plume volume. No estimates have been made of product volume beneath
the Peerless or Steel Equities properties. Product thickness is relatively thin
beneath these properties and the volume is not expected to be significant
compared to that of the overall plume volume. Thus, the total probable maximum
free-product volume remaining in approximately 2003 appears to be slightly less
than 9 Mgal (Table 1-1).
4.4 Recovery/Mitigation Techniques
4.4.1 History
The bulk of product recovered to date has been based almost exclusively on the
use of dual-phase pumping systems. In this system, a lower pump withdraws
ground water, creating a cone of depression in the groundwater system; a second
pump, placed at a shallower depth in the well, removes the induced product that is
floating on top of the water column. Because both water and product are
recovered from a dual-pump system, treatment and/or disposal is necessary for
both fluids. Figure 1-5 shows the location of both active and inactive recovery
wells in the Greenpoint area. Table 1-2 indicates the free-product yield of the
recovery wells, where known, as extracted from various reports.
The initial remedial efforts began in September 1978 with the installation of two
sumps at the foot of Meeker Avenue to intercept the seep into Newtown Creek.
By December 1978, two additional sumps had been installed along or near
Meeker Avenue. The first three sumps consisted of perforated drums that were
installed with a backhoe, whereas the fourth sump was a large diameter shallow
well with torched slots in the casing. By 1979, Mobil had also installed six
31

-------
recovery wells at the North Henry Street Terminal and by 1981 had ten recovery
wells in operation (LB&G, 1990). Up to 20 recovery wells have subsequently
been installed in the On-Site plume by Exxon/Mobil with the latest wells (RW-19,
RW-20) installed in October 2005 (Tablel-2). However, many of the earliest
wells are not in active service, mainly because of the lack of sufficient free-
product thickness to support recovery. Until recently, dual-pump systems were
used in all of the On-Site recovery wells. In June 2005, Xitech™ product-only
skimmer recovery systems were installed in recovery wells RW-19 and RW-20
and have continued to operate through 2006 (Remedial Engineering, 2006a).
Product-only systems skim oil from the top of the water table and thus do not
remove ground water which must usually be treated before disposal. Remedial
Engineering and Roux (2007a) indicate that recovery well RW-19 will be
replaced and, to increase the efficiency, a dual-pump system will be installed in
the replacement well. A dual-pump system usually increases the capture area of
the recovery well compared to a skimmer-only system.
Eight recovery wells have been installed on the BP Amoco property and seven
recovery wells have been installed in the off-site plume in the vicinity of Meeker
Avenue. Three of the BP Amoco wells and one of the off-site wells do not appear
to be active because of insufficient free product. Up until August 2005, all of
these recovery wells appeared to also operate using a dual-pump system.
Exxon/Mobil, with excess groundwater treatment capacity, has agreed to treat the
ground water recovered from its remedial systems and from the BP Amoco
system. In return, BP Amoco stores and disposes of the product recovered from
the systems of both companies (Delta, 2006). The ground water is treated On-Site
using an oil-water separator, an air stripper, and carbon adsorption units before
being discharged to Newtown Creek. The vapor phase is further processed
through a catalytic oxidizer unit, which according to Remedial Engineering and
Roux Associates (2007b) achieves complete destruction of volatile compounds.
In August 2005, Exxon/Mobil initiated a pilot study with a SpillBuster™ product-
only recovery system in off-site recovery well RW-B (Remedial Engineering,
2006b). The study was later expanded to include a portable system in four
additional monitor wells located near recovery wells RW-E and RW-F (Figure 1-
5). Remedial Engineering (2007b) also indicates that locations have been selected
for up to 10 additional recovery wells in the Exxon/Mobil off-site area (Figure 1-
5). Exxon/Mobil is reportedly negotiating with property owners for access to and
use of their property for these wells. Installation is expected in 2007 with start-up
in 2008.
In addition to the operation of the dual-pumping system recovery wells, six
monitor wells (Tablel-2, Figure 1-5) had been used at the Peerless Importers
facility for product recovery until October 1, 2006. Up to several times each
week, a vacuum truck was used to remove product from four wells, whereas
pneumatic pumps appeared to be used in the same manner on two other monitor
32

-------
wells. The cone of depression induced by water-level depression methods would
likely intercept Newtown Creek, drawing in surface water and limiting the extent
of the cone in the groundwater system. Roux (1995) discussed the use of
removing product only on the Peerless property and indicated that significant free
product could accumulate at low tide and be most efficiently removed by
skimming methods. Roux likewise concluded that the use of a groundwater
depression method at this location would be inefficient because of the existing
hydraulic continuity between Newtown Creek and the location of these wells
directly behind the Peerless bulkhead. However in November 2006, the grout wall
landside of the existing bulkhead was completed and a total fluids extraction
system was installed in the wells, replacing vacuum extraction. The new system
became operational on November 20, 2006 (SAIC, 2006 [sic]).
All of the recovery systems discussed above have been in various stages of
operation through early March 2007. However, on March 9, 2007, in a letter to the
NYSDEC, Exxon/Mobil indicated they were no longer going to recover ground water
from either their On-Site or off-site recovery systems. The action was based on the
revocation of the discharge permits issued by the NYSDEC to Exxon/Mobil and a
subsequent notice of intent to sue. Exxon/Mobil treats ground water for BP Amoco,
and therefore the shut-down would likely affect the recovery systems at BP
Amoco as well. The duration of the shut-down is unknown. If the shut-down
continues any appreciable time (e.g., several weeks), the cone of depression
developed around the recovery wells will dissipate and control on free-product
movement will be lost.
4.4.2 Effectiveness of Recovery
To assess the general effectiveness of the recovery efforts, REAC sought to
determine the amount of the estimated spill volume of approximately 17 Mgal
that had been recovered. Recovered volumes of product are given in various
reports for each of the separate recovery systems, but no report provides a site-
wide estimate of total volume recovered. A site-wide compilation of the product
recovered through approximately December 2006 is therefore provided in Table
1-1. The largest volume, 3.8 Mgal, has been recovered from the off-site plume as
reflected by the relatively high product yields of recovery wells RW-A, RW-C,
and RW-D. The approximate total volume recovered from all portions of the
plume appears to be 9.4 Mgal. A comparison of this volume to the estimated 17.0
Mgal in the original plume suggests that approximately 7.6 Mgal should be
remaining in the subsurface at the end of 2006. The latest product volume
calculations, made from 1991 to 1993 (Tablel-1), indicate that approximately 8.8
Mgal remained in 1993, suggesting that only about 1.2 Mgal was recovered
between 1993 and 2006. However, the actual volume recovered between 1993
and December 2006 appears to be on the order of 5.9 Mgal. These calculations,
and the maximum plume thicknesses remaining, particularly in the North Henry
Street Terminal area, suggest that previous volume estimates may have been
33

-------
somewhat low, or that recovery rates may be reported too high, or both. Although
Geraghty & Miller, used uncorrected thickness measurements in calculating free-
product volume, they did not have the data at the time to map the complete plume
extent.
Nevertheless, free-product thickness as mapped by Geraghty & Miller has
decreased noticeably when compared to the more recent product thickness maps
of Roux (2006), shown here as Figure 1-4. In the thick free-product section
underlying the North Henry Street Terminal for instance, apparent product
thickness has decreased by about five feet (from 20 feet to 15 feet) since 1979.
Beneath the BP Amoco property and the off-site areas, apparent free-product
thickness appears to have decreased by approximately two to four feet in the
center of the plume (not necessarily in the thickest plume section) since 1979.
Also, along Meeker Avenue, a small thin plume has separated from the main
plume with no apparent free product between the two areas, and along the western
side of the BP Amoco property a semicircular area of no free product is apparent
on the Roux map. Again, such comparisons should be considered only estimates
because of the uncertainties in using uncorrected product thicknesses.
The configuration of the local groundwater levels (in areas not affected by large
tidal variations) may also be an indication of the effectiveness of the recovery
systems in preventing the migration of product. Ideally, cones of depression
developed by individual wells should prevent product from migrating off site
without creating excessive drawdown. Excessive drawdown may produce a large
smear zone or limit recovery of product. A May 2006 groundwater elevation
contour map by SAIC (2006) shows cones of depressions that have developed
around some recovery wells. The largest cone appears to be centered around off-
site recovery well RW- A (Figure 17) and measures approximately 500 feet by
350 feet. Smaller cones are also evident around off-site recovery wells RW-D and
RW-E. Exxon/Mobil On-Site recovery well RW-14 also shows a distinct cone of
depression measuring approximately 200 by 100 feet. On-Site recovery well RW-
18 appears to be producing a large asymmetric but shallow groundwater cone
with an aerial extent of approximately 500 feet by 200 feet.
The size of the groundwater cone of depression is not necessarily indicative of the
extent of the free product cone which, because of the differences in fluid
properties, is usually more shallow and limited in extent than the groundwater
cone. Delta (2002) mapped the corrected product elevation for May 2001 and
showed distinct cones of depression in the free product around off-site recovery
wells RW-A, RW-B, and RW-D. The extent and shape of the cones suggested
that the wells were effective in controlling the off-site plume at its southern end.
Recovery well performance could also be assessed by plotting cumulative
recovery amounts with time. A significant decrease in cumulative recovery
volumes suggests either fouling of the well screen or that product thickness has
been reduced to the point where the well is no longer effective.
34

-------
4.4.3 Mitigation/Recovery Time
The first definitive attempt to determine the probable free-product recovery time
was by Roux (2003) in which they used the BIOSLURP model to estimate
recovery times for the off-site plume. The results indicated that under the
optimum arrangement of recovery wells, it would take approximately 25 to 30
years (from 2001) to recover product to the point where a free-product gradient,
and therefore recovery, could no longer be sustained. The modeling results
assumed, and also suggested, the installation of one to three additional recovery
wells. At the time of the study, four off-site wells were in operation. The report
also suggested that recovery could be optimized in existing wells by (1)
increasing the groundwater pumping rates or (2) shortening the screen lengths in
the wells to increase drawdown. These two alternatives were not necessarily
simulated by the model and specific predictions as to their effect are not available.
Roux indicates that shortening the recovery well screen length would provide the
same effect as increasing the pumping rate, but without producing more ground
water that would need treatment and disposal. Although acknowledged in the
report, the effect of recovery efforts at BP Amoco and the Exxon/Mobil On-Site
area were not considered in the model simulations. The 10 additional off-site
recovery wells that have since been proposed should shorten recovery time, but a
detailed analysis is apparently yet to be completed.
The time predicted by the 2003 Roux modeling effort is not necessarily the time
for complete site remediation. Once the free product is removed to where it can
no longer be efficiently recovered by wells, the remaining thin product volume
must be handled by other methods as indicated in the following
Recommendations and Conclusions section. In addition, a spatially broad smear
zone caused by recovery of groundwater levels since 1947, and possible a more
localized smear zone due to tidal effects in Newtown Creek may also have to be
remediated.
4.5 Data Deficiencies
The extent of the free-product plume appears to be well-defined with the existing
network of over 200 monitor wells which includes 25 additional monitor wells that were
added to the Exxon/Mobil On-Site network in 2006 (Remedial Engineering, 2006b,
2007a) and 42 additional wells that were installed at the Peerless and Steel Equities
properties in 2005 and 2006 (SAIC, 2006).
As previously discussed, plume thickness determinations, in most cases, are based on
uncorrected product thickness measurements in monitor wells, and thus probably
overestimates the actual product thickness in the formation. This fact is recognized in the
various reports reviewed by REAC. Comparing uncorrected thickness maps of various
dates, however, provides an indication of relative changes in product thickness and is
therefore a useful exercise. Nevertheless, a better estimate of product thickness beneath
35

-------
the North Henry Street Terminal seems especially warranted, given the apparent thick
section of product but relatively low product recovery from recovery well RW-20 located
in this area (Figure 1-5).
Except for some of the earlier Exxon/Mobil recovery wells, there appears to be little or
no information in the reviewed reports on screen settings for the recovery wells.
Knowledge of screened settings would be most helpful in those recovery wells exhibiting
poor performance to determine if the screened interval remains optimum for product
recovery.
Recommendations and Conclusions
Overall, the documents reviewed are concerned mainly with the near-term operation of
dual-pump systems. Roux (1991) discusses the use of dual-pump systems as an
aggressive approach to control product migration through the development of cones of
depression in the aquifer. This appears to be the most appropriate method to date, given
the apparent mass of product still unrecovered. However, with the exception of a brief
mention of other technologies by Geraghty & Miller and the Roux (1995) discussion on
skimming methods in use at the Peerless property, there is little discussion in the reports
reviewed by REAC concerning the use of other remedial technologies. Other
technologies may indeed have been considered, but updated documentation or discussion
is needed concerning their applicability or rejection. In particular, long-term plans are
needed for final recovery methods once recovery wells are no longer efficient. Other
possible technologies that could have limited application, once the bulk of mobile free-
product has been removed, include those discussed in the next section and are
summarized in Tablel-3. Without feasibility studies in specific areas of the site, it is not
possible to determine which of these methods might be most applicable. Variables
affecting the success of any one method include the geology, above ground space
available, nature and thickness of remaining product, depth of target zone, presence of
underground utilities, and cost. REAC recognizes that the logistics presented by the urban
environment are formidable and may limit the use of some technologies, such as:
4.6.1	Well Redevelopment
LB&G (1991), in work for Mobil, redeveloped several existing recovery wells
and reported significant improvements in yield. There is no indication that any
recovery wells have been redeveloped since that time. Wells with low yields but
with sufficient product thickness for continued operation may benefit from
redevelopment to remediate possible fouling of well screens.
4.6.2	Re-injection of Treated Water
Until recently, recovered groundwater was presently treated and discharged back
to Newtown Creek under a State Pollutant Discharge Elimination System
(SPDES) permit. As discussed in Section 4.4.1, Exxon/Mobil has since indicated
36

-------
that as of early March 2007, they were no longer going to pump and treat ground
water from either their On-Site or off-site recovery system. If groundwater
pumping is reinstated, consideration should be given to re-injection of this water
in selected areas where product recovery might be enhanced by increasing
hydraulic gradients, or where hydraulic barriers might be useful in preventing
migration of the free-product plume. The most efficient method would be to
reinject the recovered water directly after separation from the product.
Technically, treatment should not be necessary because the same water is being
returned to the aquifer. However, State and Federal policy may require treatment.
During injection, it may be possible to add surfactants or biological remedial
compounds to promote product release and/or breakdown. It is critical that
product not be moved to areas beyond the present plume extent or outside the
control of recovery wells. Optimal areas for injection and their effects on
hydraulic gradients can best be determined by computer modeling methods.
4.6.3 Additional Recovery Wells
Additional recovery wells were considered by Roux (1993) in their numerical
modeling study of product recovery in the off-site plume; one to two additional
off-site wells were recommended as a result of the study. As indicated previously,
Remedial Engineering and Roux (2007b) has recently proposed locations for 10
additional off-site recovery wells. Two of these wells are located along
Bridgewater Street which would potentially intercept product moving northeast
towards Peerless.
The thick section of free product beneath the Exxon/Mobil North Henry Street
Terminal is also an area where additional recovery is needed. On-Site recovery
wells RW-19 and RW-20 were recently installed by Exxon/Mobil in this area
(Figure 5) but recovery well RW-20, in particular, shows relatively poor product
recovery in what appears to be the thickest portion of free product. This suggests
that (1) actual product thickness is not sufficient to support water-table depression
recovery methods, (2) the geologic formation is too fine-grained to allow efficient
product movement, or (3) a problem exists with well construction. An additional
effort, such as numerical modeling may be necessary to determine true product
thickness and resolve the problem. Updating the Roux Bioslurp model, to include
a study of optimum recovery well locations and performance across the entire
project area is recommended. The various companies within the project area
generally confine their investigations to the properties for which they have
assumed responsibility, and therefore the mechanism for a coordinated site-wide
study is yet to be determined.
Additional recovery wells will enhance free-product recovery and are necessary to
help control seeps, but the extent to which this option can be used is limited.
Wells that are spaced too closely to each other may create overlapping cones of
depression and lower groundwater levels excessively. This in turn reduces the
37

-------
amount of product recovered by each well and also creates a smear zone that has
the potential to become a continuing source of groundwater contamination.
Likewise, increasing pumping rates does not necessarily improve long-term
product recovery. An excessively high pumping rate produces the same results as
recovery wells that are spaced too closely. Thus, the installation and operation of
additional recovery wells, and the selection of pumping rates must be carefully
considered. Recovery wells also need additional space or corridors for
transporting recovered fluids and must be accessible for maintenance. Again, a
site-wide numerical model that includes all existing and proposed recovery wells
would ensure that optimum well locations were selected, and that changes in
locations necessitated by logistical problems could be rapidly assessed.
Not all product can be removed by recovery well and a certain amount of residual
product will remain trapped in the soil pore spaces. The residual product cannot
be mobilized by pumping because the small individual oil pockets are held in
place by capillary pressure and no longer connected. Remediation must therefore
be completed with other technologies as suggested in the current section of this
report.
4.6.4 Bioslurping/Vacuum Enhanced Recovery
Bioslurping, a dual-or multi-phase extraction technique, recovers both liquids and
vapors at the same time using a single vacuum pump with the drop tube set at the
air/product interface. Place and others (2001), in a review of bioslurping
performance, indicate that the product recovery rate with bioslurping is
significantly greater than with dual-phase drawdown pumping but that less ground
water is recovered, thus lowering groundwater treatment costs. Smear zones are
also reduced as compared with the water-level depression method now in use.
Proper placement of the drop tube and well screen is generally critical to the
operation of a bioslurping system. Significantly fluctuating water levels, such as
tidal variations also impair system operations. The effect of tidal influence from
Newtown Creek on groundwater levels has been documented in a number of
reports. A tidal study by Roux (2005 draft) for the Peerless property indicates a
tidal range of approximately four feet in monitor wells directly behind the
bulkhead. The tidal influence decreases to approximately 0.1 feet at Bridgewater
Street, about 470 feet south. SAIC (2006) shows much the same results but with
additional detail showing that the tidal fluctuation is considerably less than one
foot at a distance of about 100 feet south of Newtown Creek.
In the vacuum enhanced recovery (VER) system, a dual or single pumping system
recovers both product and ground water but a vacuum is also applied to the well
which causes upwelling of the product/water interface. Bioslurping and VER
appear to have potential across portions of the study area and may be most
efficient after much of the product has been removed and there is no longer a
38

-------
major need to control hydraulic gradients. However, capital costs are high and it
is usually necessary to treat recovered vapors. Additional maintenance, permits,
and space for trenching and piping will be required. Pilot studies can be
conducted using mobile systems.
4.6.5	Steam / Hot Water Injection
Steam or hot water flushing has been an experimental technology in the
environmental field (Newell and others, 1995), but in the last few years some
small scale or pilot remedial projects have been attempted (e.g. Kemper and
others, 2005). Most work to date has been concerned with relatively high
viscosity products but there may be limited application to selected portions of the
plume in the Greenpoint area. The objectives would be to (1) reduce the
viscosity of any remaining movable free product by raising the temperature, and
(2) enhance phase transfer to the water and vapor phases which are more easily
recovered. Hot water injection is probably the more preferred method because of
lower temperatures and operating costs than steam injection. Both steam and hot
water systems require injection and recovery wells to be located in a fairly
specific pattern for best efficiency. This may be logistically difficult in the
project area. As with groundwater injection, similar precautions are necessary to
ensure that product remains On-Site. Again, this technology may be more
applicable once existing recovery wells can no longer operate efficiently.
4.6.6	Electrical Heating
Electrical heating methods might best be applied to selected small areas underlain
by low permeability soils that resist more conventional treatment. The method
would be impractical for the large area of the site-wide free-product plume. Soils
are heated by a low frequency electrical current that is applied through a grid of
electrodes. Reduction of product viscosity and also partitioning of product into
the water and vapor occurs, similar to the effects produced by steam or hot water
injection. Accompanying vapors and free product can be extracted by recovery
wells that are co-located with the electrodes. Lower temperature electrical
heating, between 30 and 40 centigrade (C), may also enhance biodegradation and
would not require treatment of vapors.
4.6.7	Bioremediation
Bioremediation techniques would be most applicable after the bulk of free-
product was removed. Geraghty & Miller briefly mention biodegradation as a
means of remediating "residual oil absorbed in sediments" and include a line item
for the technique in their proposed clean-up budget. In active bioremediation,
nutrients are added to either the soil above the water table by infiltration galleries
or to the underlying aquifer though injection wells depending on the amount and
location of residual contamination. Supplying sufficient oxygen to support the
39

-------
growth of microbes is also essential. Below the water table this can be done
though air injection wells or by lowering the water table with extraction wells that
allows air to circulate through the denatured area. The use of extraction wells
also may call for groundwater treatment facilities and satisfying permit
requirements for discharge or re-injection of the treated water.
DISSOLVED PRODUCT PLUME
5.1 Data Acquisition and Deficiencies
Nearly all of the work in the project area has focused on characterizing the
composition and extent of the free product and composition of the ground water
from within the plume area. A limited amount of data, generally within a few
hundred feet of the margins of the free-product plume, are available on the
dissolved phase plume and have been plotted by Roux {in Remedial Engineering
and Roux Associates, 2006). The Roux map is included here as Figure 1-8.
Concentrations of primary gasoline compounds in groundwater samples from
outside the extent of the free-product plume range from non-detect to orders of
magnitude lower than for groundwater samples within the free-product plume.
However, the gasoline additive methyl tertiary-butyl ether (MTBE), which was
not used until the 1990's, was found in most samples, both within and outside of
the free-product plume. Higher concentrations, particularly within the BP Amoco
property, suggest more recent releases. Because of the prevalence of MTBE in
ground water, especially in urban areas, it is not possible to attribute a source to
the relatively low concentrations of the compound found outside of the free-
product plume.
Remedial Engineering and Roux (2007b) refer to sampling ground water
"upgradient" of the off-site plume and indicate that they plan a "full evaluation
of the groundwater quality in the Off-Site Area" in 2007. It is unclear how far
the investigation will extend beyond the margins of the free-phase product. The
extent and composition of a dissolved-phase plume is important in assessing the
threat to possible groundwater supply wells located outside of the project area
and in determining the potential for vapor intrusion.
A dissolved-phase plume will migrate in the direction of groundwater flow. The
more recent groundwater data (e.g. Roux, 2005; SAIC, 2006) indicate that ground
water generally flows into the project area from the south and western portions of
the area (Figure 1-7). However, groundwater elevation maps compiled by
Cartwright (2002) indicate that groundwater flow was formerly towards a center
of municipal pumping, located approximately 1.5 miles to the southwest of the
Greenpoint area. The southwesterly flow apparently persisted until about the early
1970s, despite the cessation of pumping in 1947. By the mid-1970s, groundwater
levels had recovered to those observed in 1903 with ground water flowing
generally northerly and easterly towards the Greenpoint area and Newtown Creek.
40

-------
Remedial Engineering and Roux (2007a) indicate that a shallow ground water
component presently leaves the site to the northeast, north, and northwest. The
groundwater flow regime in the deeper regional aquifer is altered by the active
recovery wells but a component of flow is probably also discharging to Newtown
Creek along the northeast side of the site. This is not immediately evident on
Figure 1-7 which represents an approximation of ground water levels at a given
time; however, the tidal range in Newtown Creek near the site has been measured
at approximately five feet (Roux, 2005). A regional aquifer flow component
leaving the northwestern portion of the site was also indicated by Roux (in
Remedial Engineering and Roux, 2007a) and has been depicted on Figure 1-6 of
this report. The potential for ground water in the regional aquifer to migrate
beneath Newtown Creek is unknown and depends on groundwater levels on the
opposite side of the Creek.
5.2 Recommendations and Conclusions
Determining the extent of a dissolved-phase plume is needed to assess the
potential for vapor intrusion adjacent to the free-phase plume and for possible
threats to other wells. However, given the urban setting of the area, it may be
difficult to determine the source of dissolved constituents at any appreciable
distance from the site. Oil and chemical fingerprinting and/or isotopic analyses
may be necessary to identify compounds that can be statistically related to the
spill area or portions of the area.
Because of permit requirements and the logistics involved, an inordinate amount
of time may also be required to install enough wells to provide statistically
significant coverage. Soil gas analyses and/or the installation of temporary
borings in conjunction with in-hole groundwater collection techniques may be
the most rapid and viable methods for obtaining preliminary data on a dissolved
plume.
CONCLUSIONS
•	The 1979 Geraghty & Miller report provided a firm historic and hydrogeologic
basis for further work, but was largely investigative in scope and did not set forth
substantial long-term recommendations for remediating the plume.
•	The reports provided by the various consulting groups working for the potentially
responsible parties appeared to be effective in exchanging technical information.
However, there is no evidence of a coordinated approach for product recovery
efforts. Because investigations on both the On-Site and off-site free-product
plume are being conducted for Exxon/Mobil by the same firm (Roux Associates),
there may indeed be internal coordination for these two phases of the remedial
efforts but documentation is lacking.
41

-------
The existing remedial measures along the Peerless Importers waterfront, including
booms, a grout wall, and recovery wells, appear to be minimizing, but not
completely remediating, discharges to Newtown Creek. The lasting effect of the
grout wall remains to be assessed. However, the potential for seeps will remain
until the free-product plume is remediated or controlled by reversing the net
hydraulic gradient towards Newtown Creek.
The extent of the free-product plume is fairly well-defined; however, the
thickness of the plume is uncertain because of the use of uncorrected thickness
measurements. This may lead to large errors in estimating plume volume,
particularly in thicker areas of product. Determining corrected (true) free-product
thickness is difficult because of the number of physical parameters that must be
known or the number of tests that must be made. Because of the area involved in
the Greenpoint spill, even corrected product thickness should probably be
considered as only an approximation.
Groundwater depression, using recovery wells with both water and oil recovery
pumps (dual-extraction system) has been the major technique to capture free
product. This appears to be the most efficient recovery method at the moment,
given the extent and apparent thickness of free product and the urban working
environment with its inherent limitations. However, as free product thickness
declines, recovery by wells will become less efficient and other remedial methods
may be needed. To date, there has been no apparent discussion of the viability of
other methods, except for product skimming.
The presence and extent of a dissolved product plume, extending beyond the
perimeter of the free-product plume has only been partially determined. Assessing
the extent and composition of a dissolved plume is important in determining the
potential for vapor intrusion.
The installation of a product-only recovery system in recovery well B and its
possible use in other off-site recovery wells will reduce the amount of ground
water that needs to be treated. However, this needs to be weighed against the
reduction in the radius of influence of these wells.
The present cessation of the groundwater off-site and On-Site recovery systems
will lead to a decay in the cones of depression developed around the recovery
wells and to a possible loss of hydraulic heads that have acted to some degree to
contain free-product.
The Roux (2003) estimate of approximately 25 to 30 years (from 2001) to
complete recovery of the off-site plume by pumping techniques appears to be
reasonable for the scenarios proposed in the Roux report. Physical limitations are
imposed on recovery techniques by the geology, fluid characteristics and the
general behavior of fluids in subsurface environments. However, the addition of
up to 10 proposed new recovery wells is expected to decrease the recovery time.
42

-------
New pumping scenarios that include the proposed wells should be tested by
means of additional numerical modeling techniques.
•	It will not be possible to recover all of the free product, both because of logistical
limitations imposed by the urban setting and physical limitations imposed by
capillary forces which trap free product within the soil matrix. This residual
product cannot be moved by recovery wells. Also, portions of a probable smear
zone that likewise cannot be treated efficiently by pumping may continue to act as
a source of ground water contamination in the future. For instance, the American
Petroleum Institute (2002) indicates that 40% to 80% of a product spill may be
retained in soils as residual product. Phase transfer technologies, which would
convert free-product from a liquid to a vapor-phase, or into the water phase, may then be
necessary in the final stages of remediation, depending on costs, accessibility, and clean-
up guidelines. Such methods may include steam or hot water injection and electrical
heating.
•	Final clean-up goals do not appear to have been discussed or set forth in any of
the reports available to REAC.
RECOMMENDATIONS
o • A reevaluation of remaining plume volume across the entire
project area, using corrected product thickness values, appears warranted,
particularly in the North Henry Street Terminal area, where much of the
free product is under confined conditions. In particular, the apparent
discrepancy between product thickness in the North Henry Street Terminal
area and the relatively low recovery of product by recovery wells RW-19
and RW-20 should be resolved.
•	Installation of one or more additional recovery wells is recommended along
Bridgewater Street, southwest of the Peerless facility, to control what appears to
be product gradually moving northeast beneath the Peerless and Steel equities
properties. At least two additional recovery wells have been proposed by Roux
(2007) for this area, and if installed, should meet this recommendation.
•	The effect of the Peerless total fluids recovery system on the migration of the off-
site and/or the free-product plume beneath the BP Amoco property towards the
Peerless property should be assessed. The main plume will remain a potential
source of seeps if it migrates beneath the Peerless facility.
•	Once recovery wells become inefficient because of declining free-product
thickness, other recovery methods may be necessary. These methods may include
re-injection of recovered ground water, bioslurping or vacuum enhanced
recovery, steam or hot water injection, or electrical heating. The use of some
methods, such as direct re-injection of ground water without treatment, may be
infeasible because of logistical and/or policy limitations. In any case, detailed
feasibility studies would be necessary to determine the most viable method.
43

-------
•	No numerical modeling of the On-Site free product thickness and recovery time is
documented in the report made available for this review. A site-wide model that
includes a corrected product thickness estimate and a product recovery time
projection, incorporating all existing and proposed recovery wells is
recommended.
•	A long-term comprehensive site-wide feasibility study that includes coordination
among all responsible parties is needed. NYSDEC appears to be working towards
this goal but statutory limitations and multiple PRPs hinder this effort. Such an
approach does not necessarily mean that actual remedial objectives will be
achieved faster than the current 25-year estimate, due to uncertainty in the data. It
would, however, ensure that recovery efforts by one party enhances, or at least
does not hinder, efforts by other parties.
44

-------
8.0 REFERENCES
American Petroleum Institute. 2002. Evaluating hydrocarbon removal from source zones and
its effect on dissolved plume longevity and magnitude. Publication Number 4715. 15 pp.
Cartwright, Richard A. 2002. History and hydrologic effects of groundwater use in Kings,
Queens, and western Nassau counties, Long Island, New York, 1800's through 1997: U. S.
Geological Survey Water -Resources Investigations Report 01-4096, in cooperation with the
New York City Department of Environmental Protection. 79 pp.
Delta Environmental Consultants, Inc. 2000. The Greenpoint oil spill: a detailed history.
Prepared for BP Amoco Oil Company.
Delta Environmental Consultants, Inc. 2002. Subsurface hydrocarbon assessment report,
BP petroleum bulk storage terminal, 125 Apollo Street, Brooklyn, New York. Prepared for
BP Products, North America, Inc.
DePastrovich, T. L. And others. 1979. Protection of groundwater from oil pollution.
Concawe Water Pollution Special Task Force No. 11 Report Nr 3/79.
Geraghty & Miller, Inc. 1979. Investigation of underground accumulation of hydrocarbons
along Newtown Creek, Brooklyn, New York. Prepared for the U. S. Coast Guard.
International Technology Corporation. 1993. Monitoring and proposed enhanced
remediation program, Amoco Oil Company, Brooklyn, New York. Prepared for Amoco Oil
Company Remediation Services.
Kemper, T. and others. 2005. Steam injection expedites removal of viscous NAPL at a
manufacturing complex. Poster session - The Annual International Conference on Soils,
Sediments and Water.
Leggette, Brashears & Graham, Inc 1990. Mobil Oil Corporation investigation of free-phase
product beneath the North Henry Street Terminal, Brooklyn, New York. Remedial
Engineering. 2006b
Leggette, Brashears & Graham, Inc. 1991. Mobil Oil Corporation evaluation of free-phase
product recovery from the regional aquifer and calculation of the approximate volume of product
beneath the North Henry Street terminal, Brooklyn, New York.
Newell, Charles J. and others. 1995. Light nonaqueous phase liquids. EPA Ground Water
Issue. EPA/540/S-95/500. U. S. EPA R. S. Kerr Environmental Research Laboratory, Ada,
Oklahoma.
Place, Matthew C. and others. 2001. Principles and practices of bioslurping. Battelle
Press. Columbus, Ohio. 175 pp.
45

-------
Remedial Engineering. 2006a. First quarter 2006 progress report, off-site free-product
recovery system, Greenpoint, Brooklyn, New York. Prepared for Exxon/Mobil Refining &
Supply Company.
Remedial Engineering. 2006b. Second quarter 2006 progress report, recovery and
containment system, former Brooklyn terminal, Greenpoint, Brooklyn New York. Prepared
for Exxon/Mobil Refining & Supply Company.
Remedial Engineering and Roux Associates. 2006. Third quarter 2006 progress report,
Brooklyn Terminal free-product recovery system (RCS) operation and maintenance (OEM).
Remedial Engineering and Roux Associates. 2007a. 2006 annual remedial status report,
Brooklyn Terminal (On-Site) free-product recovery system, Greenpoint, Brooklyn, New York.
Prepared for Exxon/Mobil Refining and Supply Company.
Remedial Engineering and Roux Associates. 2007b. 2006 annual remedial status report, off-
site free-product recovery system, Greenpoint, Brooklyn, New York. Prepared for
Exxon/Mobil Refining and Supply Company.
Roux Associates, Inc. 1991. Remedial plan for the recovery of the off-site free-product
plume, Greenpoint, New York. Prepared for Mobil Oil Corporation.
Roux Associates, Inc. 2003. Supplemental investigation of the off-site free-product
plume. Prepared for Exxon/Mobil Refining & Supply Company.
Roux Associates, Inc. 2005. Peerless Importers remedial investigation (draft). Prepared
for Exxon/Mobil Refining & Supply Company.
Roux Associates, Inc. 2006. Peerless Importers remedial investigation. Prepared for
Exxon/Mobil Refining & Supply Company.
Science Applications International Corporation. 2006. Site characterization report for the
former Paragon oil terminal and adjacent areas, Greenpoint section, Brooklyn, New York.
Prepared for Texaco, Inc.(October 2006).
Science Applications International Corporation 2006 (sic). Status report - October 1, 2006
through December 31, 2006. Prepared for: New York State Department of Environmental
Conservation. (January 24, 2006 [sic]).
Science Applications International Corporation. 2007. Supplemental site characterization report
for the former Paragon Oil Terminal and adjacent areas, Greenpoint Section, Brooklyn, New
York. Prepared for Texaco, Inc. (February 2007).
Science Applications International Corporation 2006 (sic). Status report - October 1, 2006
through December 31, 2006. Prepared for: New York State Department of Environmental
Conservation. (January 24, 2006 [sic]).
46

-------
Science Applications International Corporation. 2007. Supplemental site characterization report
for the former Paragon Oil Terminal and adjacent areas, Greenpoint Section, Brooklyn, New
York. Prepared for Texaco, Inc. (February 2007).
47

-------
APPENDIX A
DIAGRAMS SHOWING CONTAINMENT BOOMS,
BULKHEAD, AND GROUT WALL (SAIC; 2006, 2007)
NEWTOWN CREEK SITE
BROOKLYN, NEW YORK
0228-DFR-05070
48

-------
Diagram of Current Seep Containment System
PEERLESS PROPERTY
tyiyw
NOTE;
TWO ROWS OF A8SOR8OTT BOOMS ARE DEPLOYED ON THE 8ULKHEAD
SIDE OF THE GLOBE BOOM AND ONE ROW OF ABSORBENT BOOM
IS DEPLOYED ON THE BULKHEAD SIDE OF THE FENCE BOOM
CURRENT SEEP CONTAINMENT
SYSTEM
NOT TO SCALE
	texaso inc.	
FORMER PARAGON OIL TERMINAL
0228-DFR-05070
49

-------
Diagram of Historical Booming on Newtown Creek
110-120 APOLLO
STREET TEMPORARY
RIVER BOOM
FENCE BOOM
I CNJM a r
ABSORBENT BOOM
GLOBE BOOM*
WEST END
OF 800M
2 ROWS OF
ABSORBENT BOOM
EXISTING
CONCRETE WALL J
WESTERN /
BOUNDARY OF
FORMER PARAGON
OIL TERMINAL AND
STEEL BULKHEAD
NEW GROUT
WALL
EXISTING
STEEL
BULKHEAD
0228-DFR-05070
50

-------
APPENDIX B
FREE-PRODUCT THICKNESS (DELTA, 2002)
NEWTOWN CREEK SITE
BROOKLYN, NEW YORK
0228-DFR-05070
51

-------
Unadjusted Product Thickness Contour Map
REGIONAL UNADJUSTED PRODUCT
THICKNESS CONTOUR MAP
(MAY 24, 2001)
0228-DFR-05070

-------
Tables
0228-DFR-05070
53

-------
TABLE 1-1
PRODUCT VOLUME AND RECOVERY ESTIMATES
NEWTOWN CREEK SITE
BROOKLYN, NEW YORK
REMAINING VOLUME ESTIMATES (Mgal) - REGIONAL AQUIFER
Off-Site Plume (Exxon/Mobil)
On-Site Plume (Exxon/Mobil)
BP Amoco
Roux 5/91
Roux 10/91
Roux 1/03
3.4
3.1
5.3
LB&G 8/81 1.4 to 2.4
LB&G 6/91 1.6 to 2.5*
IT 6/93 1.0
Approximate Total remaining January 1993: (5.3 + 2.5 +1.0) = 8.8 Mgal (maximum)
PRODUCT RECOVERY ESTIMATES
Off-Site Plume (EM)
MATF
On-Site Plume (Exxon/Mobil)
BP Amoco
Former Paragon
Roux 10/06 3.8
Roux 1/05 0.7
RE 1/07 1.7
Delta 1/07 3.19
SAIC 1/07 0.013
Approximate total recovered from start-up to December 31. 2006 (3.8 + 0.7 + 1.7 + 3.19 + 0.013)= 9.4 Mgal
Approximate total recovered from January 1. 2003 to December 31. 2006 = 5.9 Mgal
Approximate volume remaining (8.8 - 5.9) = 2.8 Mgal	
Mgal = million gallons
IT = International Technology Corp.
LB&G = Leggette Brashears & Graham
MATF = Meeker Avenue Task Force
RE = Remedial Engineering
Dates refer to the report providing the indicated data.
* recalculation based on new data
0228-DFR-05070
54

-------
TABLE 1-2
RECOVERY WELL STATUS
NEWTOWN CREEK SITE
BROOKLYN, NEW YORK
Well No.
Aquifer
Status
F. P. Yield GPD
Screen Setting
Comments


Mobil Onsite

ARW-1
Shallow
I (Insufficient free product)
NA

Installed 1979
ARW-2
Shallow
I (Insufficient free product)
NA

Installed 1979
ARW-3
Sallow/Regional
I (Insufficient free product)
NA
0 to 38 ft bgs
Installed 1979
ARW-4R
Regional
I (Insufficient free product)
NA

Installed 1988
ARW-5
Shallow
I (Insufficient free product)
NA

no record
ARW-6
Shallow
I (Insufficient free product)
NA

Installed 1979
ARW-7

I (Insufficient free product)
NA

no record
ARW-8
Shallow
I (Insufficient free product)
NA
Oto 18 ft bgs (?)
Installed 1980
ARW-9
Shallow
I (Insufficient free product)
NA
0.5 to 12 ft bgs
no record
ARW-10
Shallow
I (Insufficient free product)
NA
0 to 12 ft bgs
Removed from service 1981
ARW-11
Shallow
I (Insufficient free product)
NA
0 to 15.5 ft bgs
24-inch diam., installed 1980
ARW-12
Shallow/Regional
I
NA

Installed 1982
ARW-13
Shallow/Regional
I
NA

Installed 1982
ARW-14
Regional
A
-20

Installed 1985
ARW-15

A


Installed 1988
ARW-16

I
NA

Installed 1993
ARW-17

A
-55

Installed Nov. 2004
ARW-18

A
-185

Installed Nov. 2004
ARW-19

A
-27

Installed Oct. 2005
ARW-20

A Low Yield
>1

Installed Oct. 2005


Mobil Offsite

ARW-A
Regional
A
-575 - 600

10-inch diam. steel
ARW-B
Regional
A
-6

10-inch diam. steel
ARW-C
Regional
A
-80-105

10-inch diam. steel
ARW-D
Regional
A
-185

10-inch diam. steel
ARW-E
Regional
A
-21 - 23

10-inch diam. steel
ARW-F
Regional
A (negligible free product)
NA

10-inch diam. steel
ARW-G
Regional
I (Insufficient free product)
NA

12-inch diam, steel
0228-DFR-05070
55

-------
TABLE 1-2 (continued)
RECOVERY WELL STATUS
NEWTOWN CREEK SITE
BROOKLYN, NEW YORK
Well No.
Aquifer
Status
F. P. Yield GPD
Screen Setting
Comments
BP Amoco
ARW-1
Regional
A

51*


ARW-2
Regional
I
(Insufficient free product)
NA

24-inch diam. steel -34 ft deep
ARW-3
Regional
A

~ 1*

4-inch diam. steel - 35 ft deep
ARW-4
Regional
A

6*

14-inch diam. steel -35 ft deep
ARW-5
Regional
A

110*

10-inch diam., installed June
2004
ARW-6
Regional
A

153*

10-inch diam., installed June
2004
ARW-7
Regional
I
insufficient free product**
NA

10-inch diam., installed June
2004
ARW-8
Regional
I
insufficient free product**
NA

10-inch diam., installed June
2004



Peerless Importers (Formerly Paragon Oil)


"Lower Bulkhead Wells"
MW-68
Shallow
A

4.4 (stressed)
5 to 20 ft bgs
periodic vacuum extraction
MW-69
Shallow
A

6.9 (stressed)
5 to 20 ft bgs
periodic vacuum extraction
MW-70
Shallow
A

9.5 (stressed)
5 to 20 ft bgs
periodic vacuum extraction
"Upper Bulkhead Wells"
MW-73
Shallow
A

11.3 (stressed)
4 to 14 ft bgs
total fluids extraction
MW-74
Shallow
A

56.5 (stressed)
5 to 17 ft bgs
total fluids extraction
MW-75
Shallow
A

33.5 (stressed)
5 to 20 ft bgs
total fluids extraction
A = Active
bgs = below ground surface
I = Inactive
FP = Free Product
GPD = gallons/day
NA = not applicable
LB&G = Leggette Brashears & Graham
~ approximately
* average from August 2005 through September 2006	** contingency well
0228-DFR-05070	56

-------
TABLE 1-3
FREE-PRODUCT POTENTIAL REMEDIAL METHODS
NEWTOWN CREEK SITE
BROOKLYN, NEW YORK
METHOD
APPLICATION
DISADVANTAGES
Recovery Well
Redevelopment
Relatively inexpensive, no additional
construction or support facilities required.
Review of well performance history necessary.
Results not always certain
Treated Ground Water
Re-injection
Increases hydraulic gradient to improve
product capture; opportunity for addition
of surfactants.
May need space for grid of wells; product
movement needs to be controlled by optimal
placement of recovery wells. Permits usually
required for injection; uniform and moderate
to high formation permeability needed.
Additional Recovery Wells
Aggressive method to increase product
capture rate in thick sections of free-product.
A dual-phase system (water and product)
creates ground water cone of depression,
thus increasing radius of capture zone.
Efficiency deceases as free-product thickness
decreases. Requires collection and/or treatment
facilities for recovered fluids; usually produces
smear zone.
Bioslurping/Vacuum
Enhanced Recovery
Multi-phase extraction with relatively high
free-product recovery rate. Minimizes
smear zone.
High capital costs; treatment usually necessary
for recovered ground water and vapors, thus
requiring permits.
Steam/Hot Water Injection
Reduces product viscosity, promotes phase
transfer where water and vapor phases are
more easily recovered.
A pilot technology; space needed for grid of
injection and recovery wells; need to maintain
control of product in urban area.
Electrical Heating
Relatively fast method with product capture
enhanced by phase transfer.
Relatively high cost, best applied to small areas;
space needed for electrode grid.
Bioremediation
Most applicable as a polishing step after
Both injection and extraction wells may be

bulk of free product has been removed.
needed; treatment facilities may be required.
Low permeability soils limits effectiveness
0228-DFR-05070
57

-------
FIGURES
58

-------
Figure 1 - Index Map
LY-.. ^



&.NJ*
tfVH ', -,
.a pp v rssk1-
^.V /f
$
S
r>*r *
\, VRafij::
%w*n»ia»miii mt#r4»4»rinf
U. _eIjii J MhiUf* Xm J
UkJat'i]
^-,4-.si I u'.-r &inL H i£ -3* iL i .9 F—
''	«r~.



..- avxkfi. K«* .'Cri I
i «•
IA /
fl
A-J 1
I f, qu 3A-=;-Mcnj|. rturw.; |HN
K£hJiE iMAhfM*, mL
-------
Figure 2 - Property and Seep Locations
0228-DFR-05070
60

-------
Figure 3 - Product Extent and Thickness
mML

FH3JB_ I-.3

= i7-:-,i - r -•—• - .'i - - • <; rv'.
J.3X"» UWItOWOflW. T3T0WK1Wi
MAPPED BV at (WEHTV & yi-LLB (IB fa:
ttfcspm=E±=i-Mrfc-*MC. Ale wutd-iliw. „-4' MCI
NEWTOAfc C=?E£S STC

aman.vN neffrcmK
miu I U
f	-r ¦rv«tq.®»T« - • L':f SCOWPV i'*: i
^	>¦ | ! rJ. it- i k«-
0	l|y|tll V ,|ini#1kfa|'|H f
f	torcri Ml !L. 2* l-EL-U
¦* ™ -	»T .1
HW
*t f. •
¦Aki adil'-in'^l MS HIi
j	| 11 f #1* K *1
WSI 1VN *¦* -
~rwrco err- iulms lurssor
n-oocsFSE n d-jtclus F^zMaaawaHFi1 a mi i fr r ett-.
.j, .|- ,1W» j ¦ JBJ- — l"lrJ	|Al~n, | Ull Ci-*>CifcU4l- j, Jftlii
0228-DFR-05070	61

-------
Figure 4 - Apparent Free-Product Thickness
0228-DFR-05070
62

-------
Figure 5 - Recovery Well Locations
IJEUSMQ
1*EticrtAt ruAtw^
P* J* rtTT^r AXa kCii
¦¦ ?T3i *¦#£ HI nw«CSE8~l
J HfHfi-WM M- -sr»h*-= ?r
"Jdf««l£ 'Mil lETX-fcH Men JKT
§ frsniiQ. . sti-ns-i b*t
"»* - pubis-Oof
•* ,T - n- .r|w.^| .4;|r«-v
^ mm i ,u »! .icj|i mu
r* ' -' I m ¦ H -
til . urr-.-i v.
u(V.FTFCEy RFT H'.V iUtf
Mr •,!¦' n:-vtww< waaq^awmwr,m
FIGURE 1-5
RECOVERY WELL LOCATIONS
Pi t'.VIOWN CKfcfc* Silt
BHQOKi YN.Ht WTCJRK

ai mmm t xmivnuiM ihj
ternm tSL hut u aM KaH. v iua. 
-------
Figure 6 - Monitoring Well Locations
0228-DFR-05070
64

-------
Figure 7 - Generalized Groundwater Flow Direction Map
rfcLFT V
1 RESENM. ftQJFER C£*€EFV1EED
		JflftouMD-wATeftpt.ow cHttfcrr^s-
inn rm r t nrrnr ilm«	NAY I NOV=4.B=fl
.U-I--4 I	W WIUVYWCKfcfcKSIII
I BROCKL^N NET* YORK
tMtfruqii F*LJ* Bui:| -riiAHkiMMi I
%. V -H v.; T > ifl*i-M tt-u „c_ ofr*-**!!*. v , *
0228-DFR-05070
65

-------
Figure 8 - Dissolved Groundwater Analytical Data Map
• tv--V«P 4 *w> I
			gi If	_
BBB
Sml
0228-DFR-05070
66

-------
Chapter 2
67

-------
Vapor Intrusion Investigation - Greenpoint Petroleum Remediation Project
Background
As part of the ongoing investigation and remediation activities for the Greenpoint Remediation
Project, the New York State Department of Environmental Conservation (NYSDEC) determined
that an investigation of potential vapor intrusion into residential structures was warranted. The
vapor intrusion pathway accounts for the migration of contaminants from one medium (i.e.,
groundwater or soil) to a vapor phase that can collect underneath building foundations (e.g., sub-
slab), and finally enter through building foundations into indoor air (Figure 1).
The decision to conduct residential vapor intrusion sampling was based, in part, on soil gas
sampling performed in the area by Exxon/Mobil Refining & Supply Company ("Exxon/Mobil").
Exxon/Mobil sampled soil gas in the Greenpoint Area around the Off-Site product plume (Figure
2). The goal of the sampling was to determine if vapors from the product plume were attenuating
before impacting indoor air as believed from some earlier investigations. This investigation was
conducted in 2005, and a report was finalized in February 2006 and made available to the public
through the NYSDEC's Greenpoint website at
www.NY SPEC. state.nv.us/web site/der/proi ects/greenpoint.
The soil vapor investigation conducted by Exxon/Mobil in 2005 concluded that the free-product
plume was not contributing to concentrations of contaminants in residential indoor air.
According to the report the depth of the contamination allowing for biodegradation and presence
of a clay/silt layer to prevent migration are factors supporting this conclusion. The NYSDEC
reviewed the data and agreed that it supported Exxon/Mobil's conclusions, however, NYSDEC
concluded that a residential vapor intrusion/indoor air investigation to collect the data necessary
to verify or refute this conceptual model was needed. This work is described below.
Since the 2005 investigation indicated that further work was needed to delineate the areal and
vertical extent of potential soil vapor exceeding the screening criteria in the commercial and
industrial areas, Exxon/Mobil continued investigating soil vapor, especially methane and
benzene, in non-residential areas in 2006 (see Figure 3 and 4). The screening criterion for
benzene was 170,000 parts per billion volume in soil vapor beneath commercial areas. The
screening criterion for methane in soil vapor was set at 50,000 parts per million volume.
Exxon/Mobil concluded that the findings of this investigation were consistent with the earlier
2005 investigation; the presence of silt/clay layers when combined with increased depth
restricted the upward migration of soil vapor.
Biannual soil vapor sampling is conducted by Exxon/Mobil in both the residential and
commercial/industrial areas. This sampling is not the same as the residential vapor intrusion
study performed by the NYSDEC. Exxon/Mobil is not sampling the subslab and indoor air in
the residential area, rather it is sampling discrete locations which are part of a soil vapor
monitoring network. These monitoring points are generally located under area sidewalks. There
are twenty nested monitoring points, containing both a deep (7-8 feet below land surface) and a
shallow (2-3 feet below land surface) sampling point, for a total of forty points in the
68

-------
commercial/industrial area and ten deep (7-8 feet below land surface) monitoring points in the
residential area. The most recent sampling round was conducted from January to March 2007,
and results are presented in a March 30, 2007 letter report to the NYSDEC. Benzene and
methane results from this latest sampling round are presented in Figures 5 and 6. It should be
noted that there may be multiple sources of methane in the area, such as leaks of natural gas from
subsurface pipelines, which may be contributing to the methane detections reported in soil vapor.
Another investigation into soil vapor in the area included work performed on behalf of
Chevron-Texaco at a warehouse located on the former Paragon Oil Terminal (currently Peerless
Importers). This investigation included the installation of ground water monitoring wells inside
the warehouse in July 2005. Air monitoring was conducted primarily to assess worker health
and safety issues and as such has limited application to the residential vapor intrusion study
conducted by the NYSDEC.
Residential Vapor Intrusion Investigation
Although Exxon/Mobil was willing to perform an investigation of the vapor intrusion pathway
at the site, it had difficulty securing access from property owners. Therefore, NYSDEC opted
to conduct the study using NYSDEC personnel and contractors. The NYSDEC study targeted
residential structures over the current and historical free product plume (see Figure 7).
Investigation of residences over the dissolved phase plume was deferred pending the results of
the initial free product plume investigation. NYSDEC began soliciting participation from the
public in November 2006.
Methodology
To investigate vapor intrusion NYSDEC developed an initial work plan that was distributed to
both EPA and the public at an Information Session held on September 27, 2006. Key tasks
identified in the work plan included: 1) obtaining access, 2) conducting a building survey, 3)
conducting a product inventory within the structure for potential sources of indoor air
contamination, and 4) the collection and analysis of subslab, indoor air and outdoor (ambient) air
samples. This last task was conducted in accordance with the New York State Department of
Health ("DOH") "Guidance for Evaluating Soil Vapor Intrusion in the State of New York."
1. Access
Extensive outreach was conducted by the NYSDEC to obtain as many
access agreements as was possible. This outreach consisted of two
public information sessions held during the fall and winter of 2006 -
07. In addition, NYSDEC mailed 387 letters in English, Spanish and
Polish to area residents requesting their participation in the study.
Positive responses have been somewhat low. NYSDEC reports having
59 volunteers as of March 2007, possibly because of potential
litigation.
69

-------
2.
Building Surveys
NYSDEC contractors visited each property to be tested prior to
actual sampling. A building survey was conducted. This consisted of
evaluating the building type, floor layout, air flow/air flow patterns
and the physical condition of the building.
3.	Product Inventory
One of the factors that significantly affects indoor air sampling is the
presence of products within the residence that contain volatile
organic compounds (VOCs). These products may contain the same
chemicals that are the focus of the investigation. Even when
unopened, containers with these compounds can result in detectable
concentrations of volatile chemicals in indoor air. To evaluate this,
the NYSDEC contractors conducted an inventory of products in each
residence to be tested. This inventory lists the product name, its
chemical composition (when known) and the readings from this
product obtained using a sensitive handheld VOC monitor. These
readings were then recorded in the field notes.
4.	Sample Collection and Analysis
Sample collection was conducted during the winter of 2006 - 2007.
Samples were collected from beneath the building foundation (sub-
slab samples), the basement, the first floor and the outdoor air.
Samples were collected using Summa canisters, a sampling vessel
designed to collect air samples, over a 24-hour sampling period.
Analysis was conducted using EPA Method TO-15 for VOCs, and
EPA Method TO-3 for methane.
EPA reviewed and provided comments on the initial Work Plan to NYSDEC in November 2006.
In December 2006 NYSDEC provided EPA with two supplementary documents: "Standard
Operating Procedures: Soil Vapor Intrusion Investigation in New York State" and "Verification
and Validation of Chemical Analytical Data." A revised Work Plan was provided to EPA in
January 2007. In addition, NYSDEC provided EPA with a response to EPA's November
comments. EPA reviewed the Standard Operating Procedures and provided comments to
NYSDEC in February 2007.
Results
To date, EPA has received analytic results from 45 properties. Samples were collected at each
home from beneath the slab and in the basement (when available) and first floor living space
(when available). In addition, outdoor (ambient) air was collected at 44 of the 45 residences.
Typically, when vapor intrusion is occurring at a site, the concentrations in the subslab are
70

-------
highest, with decreasing concentrations as samples are collected in higher levels of a home;
outdoor (ambient) concentrations are usually quite low so that they would not serve as an
influence to vapors that are detected indoors. A review of the data collected by the NYSDEC
shows that, in general, chemicals were detected at all locations in each home, but not in a pattern
that would typically represent a vapor intrusion phenomenon. Chemicals were detected at
concentrations in the subslab soil gas and the indoor air (both the basement and the first floor
living space) but usually at concentrations that are consistent with outdoor (ambient) air results.
This pattern suggests that outdoor (ambient) air may be contributing to vapors that are detected
indoors. Data collected from a few residences do not follow this pattern and additional
investigation may be warranted to more fully understand how the vapors are migrating.
NYSDEC, in conjunction with the DOH, reviews the analytic results and DOH transmits the data
with an explanatory letter to the homeowners. This effort is ongoing.
Recommendations
As previously noted, NYSDEC in conjunction with the DOH, is continuing to assess the data
that were collected from this investigation. The following recommendations are provided to
assist with this effort.
•	Further investigate results from homes with elevated subslab and indoor air
concentrations along Meeker Avenue.
•	Based on existing information, data gaps exist. Continue to attempt to gain access
to additional homes along Kingsland Avenue, Van Dam Street, Meeker Avenue,
and South of the Brooklyn Queens Expressway. Access issues may interfere with
the NYSDEC's ability to close these data gaps.
•	Provide decision matrix/flowchart for community that clearly explains how data
are being evaluated and how risk management Decisions are being made
regarding subslab, indoor, and ambient concentrations.
•	Outreach to commercial facilities which are located within the residential areas
(delicatessens, shops, etc.) to get access so that vapor intrusion data can be
collected. These can be used to assess potential distribution across the plume.
•	Continue to evaluate ground water data for both the free product plume and the
dissolved phase plume to determine if boundaries of the vapor investigation
should be revised.
•	Develop ambient air monitoring program to investigate potential confounding
sources to indoor air.
•	Include naphthalene in the analytical suite.
•	Evaluate any potential existing databases for background air concentrations in
similar communities for comparison with
71

-------
Chapter 2 Figures
72

-------
Figure 1 - Vapor Pathways Into Buildings
Subslab soil gas
intruding into
interior space
Interior space
Ventilation
Ambient air
Ventilation
Ambient air
Vadose Zone
Soil or Groundwater Contamination
Vapor Pathway into Buildings
73

-------
Figure 2 - Site Plan
(Source - Exxon/Mobil Soil Vapor Investigation Feb. 2006)
EXPLANATtO N
BP AMOCO TERMINAL
FORMER PARAGON FACILITY	.
EXTENT OF RESIDENTIAL AREA	P J
— — — EXTENT OF SOIL VAPOR STUDY AREA
SITE PLAN
GREENPOINT
BROOKLYN. NEW YORK.
74

-------
Figure 3 - Benzene Concentrations in Soil Vapor
(Source - Preliminary Phase IV Commercial Soil Vapor Results)
BP AMOCO
TERMINAL

MP-8
fSG—10)
NASSAU
^"EXXONMOBIL REF1NINC & SUPPLY COMPANY
	INWOOD. NEW YORK	
liMIW
RQLH ASSOCBC.
C*n?ftrt bp CA/APX
W« 11AUCQ6
ru*c
3
M©f: JJMt
f*» Mfc l*307M0t
OfTteB- NT
I72J0E17
LEGEND
¦ ¦ ¦ EMSTNG fVKZ1*C
- 20	EXlSTPC IIKJOft CR0U» SURFACE ELWATOt
CONTOUR (INTEJNAL - 10 FI-AMSL)
E3QSTW5 ©WOE SPOT EUMCKW (FT-AMSL)
FEET A0WE WEAN SEA LEVB. (WW 29)
NO COMPOUND WAS MOT OGCTEO
MP—ffSG—f) 0CSWAT10N OF PHASE N PEmtUiEXT
K0WRMW3 POWl WITH CORRESPONDING
m«£ I / I SDL WOR SN4PUM6 WNT M
PN*D« hatwuu.
scoomc VERTiCAL DATUM Of '829 (NOW 28). THE Nd® 2S
OATUM IS KSS XMOm AJ WEU.5, COAST AMD CECOOC:
SURVEY (USt*C) MEAN SEA LEVEl DATUM OF 1929.
4. 1»€ BROOKLYN TOPQORARMC BUREAU DATUM IS J.58 FEET
A80VE TH£ K0\© 29 DATUM AT S««* HOOK, HE* JESSCf. TO
CONVERT THE ELEVATIONS S40MN TO MOOMLYK TOPOCRAPMC
BUREAU ELTVATWN4 SUBTRACT 2.56 FEEJ FROM THE CNE*
Rff® » aiVA-nONS.
100"	0	100'
BENZENE CONCENTRATIONS
IN SOIL VAPOR
AUGUST2008
OfF-S!TE SOIL VAPOR INVESTIGATION - PHASE N
Gasxt*5isn-, aROOKLYN, NO* YORK
l«STE2 PER**A»CNT PMASE N SOL VAPOR
M0WT0RN6 POINT (2 PER LOCATION)
SAJ^LWC KIOTttLS; 2-3 FOOT DEPTH
?-« FOOT DEPTH
bdsoc OMcevmsnoN w b*bv
SAUPU« KTDNAL5: 2-3 FOOT DEPTH
7-8 FOOT DEPTH
EJQSTH3 BUU»MQ / STRUCTURE
TilAPORAITY (ONE-HIE) 901,
PONT FROM 2005 PHASE I
3AMPLN6 KTERVAU 1-4
75

-------
Figure 4 - Methane Concentrations in Soil Vapor
(Source - Preliminary Phase IV Commercial Soil Vapor Results, August 2006)
BP AMOCO
TERMINAL

MP--5:
NASSAU
EXXONMOBIL REFINING it SUPPLY COMPANY
INWOOP, NEW YORK	
1
«W Assocurrs, NC
CamptMl or ZJ'JJJ'X,
M/uooe
4
P^iKt utn JPX
rai »a: IC307880J
OffS* NY
t723Cei?
LEGEND
¦ ¦ ¦ £»snw fencuwe
20	EHSTMS UA&ft WOUND 5UWACE EUVA3WM
contour {WTOwx. - 10 rr-AKSj
OCSTOC GRADE SPOT ELEVATION (FT-MSU
25.8
ft-amsl rurr *scvt mean sc* ism. (novo »}
„ , —,	TEVPOftW»T (WE-ffcO sot VAPOft SAMP-JN3
SB- J 9	POINT FROM 2C03 PHASE I / n XVESTCAnONS
SMPLN4 m/TOML: 7-9 FOOT DEPTH
MP-J	«5ttD POajANENT PHASE N SO*. V«P0«
MONTCHWC POMT (2 PEN LOCATION]
SANP'JHC WTEfMCS 2-3 FOOT DEPTH
7-e FOOT BOTH
METHANE CONCOiTSATKHt IN PPMV
SAMPLING WTEflVALS: 2-3 P3CT QCTW
7-a FOOT DOTH
WD COMMOta HAS NOT OCTCTED
WP-fCSC-lJ DCSttNATXX OF PHASE IV PERMANENT
MONfrOflWC POMT WIN COMESPONOMS
PHASE l / II Km. VAPOR SAMPUNO PONT l>
PAREWIHESE5
1.	BASE NAP PREPARED FROM AEHSAL SUHVEY PGWOflMED BY
ANGLE OF ATTACK LAW 3UWSCWHC LLC. MAY 200>. ALL
^OPOSIW»flq AN9 PLAWMCRW DETAILS HCRE FWEPARSD USNO
PHOTOCRAHMTTOC METHODS
2.	HORIZONTAL LOCATIONS AJ® COORDINATES A*E M US. FEET
RELATWt ro TK NEW TOW STATE PLANE COCttWUTE SYSTEV,
LOW ISLAND ZONE, NORTH AMERICAN DATUM OF IMS (HAD
asy
X ELEVATW5 APE IN OS- FEET RELATIVE TO TJC NATICWAi,
SEOCOC VERTICAL DATUM op 'S28 (NCVO 29X THE *CVO 2S
DATUM IS ALSO «*&** AS I>S tLS COAST AS5 OCOOC^C
SuBVFf {USC*® MEAN SEA IF®. DATUM OF !929.
4, THE BROOKLYN TOPOGRAPHIC BUftEAU DATUM IS 2-5# FTTT
ABOVE THE NOW 29 DATUM AT SANDY HOOK, NEW JERSEY. TO
CONVENT THE EIEVAT1CXS SW0»W TO BROOKLYN TWOCWAPWC
BUREAU ELEVATIONS, SUBTRACT 2.5fl FEET FSOM TVS OVEN
NOVO 29 DfVATONS-
100'	0	100'
METHANE CONCENTRATIONS
IN SOIL VAPOR
AUGUST 2006
OfT-STTE SOIL VAPOR IWESTKATVX - PHASE N
OSgWQIXT. BPQOKLY*. NEW YORK
76

-------
Figure 5 - Benzene Concentrations in Soil Vapor
(Source - January 2007 Soil Vapor Report Exxon/Mobil)
O
r.-
BENZENE CONCENTRATIONS
IN SOIL VAPOR
ROUND S
77

-------
Figure 6 - Methane Concentrations in Soil Vapor
(Source - January 2007 Soil Vapor Report Exxon/Mobil)
LEGEND
CSKNXK ONTWVW. - 10 FT-AMSO
COWIOSJR (INTtRVAL . 2 FT-AMSJ
txsruo cfuoc spot EuwnoN (rr-**iSL)
Exsrwo BUONG / STRUCTURE
• m

WOwrro«NG PONT (1 P£R U5CATKW)
CN 3/1/ttO? Q*-S3) WO J/'*/**"
2/1/2QD7 3/1/500? 3/14/3007
200'
200*
METHANE CONCENTRATIONS
IN SOIL VAPOR
ROUND 3
OFF-STE SOIL VAPOR ItftCSTWnON - PHASE f
CgCEMPOWT. BROOM.1H NEW TCRK
EXXONMOBIL REFINING & SUPPLY COMPANY
	INWOOD, NEW VQftK	
78

-------
Figure 7 - Greenpoint Residential Vapor Intrusion Study
(Source - New York State Department of Environmental Conservation)
Greenpoint Residential VI Study
Initial Study Area
N
NASSAU &VENU1
STUDY AREA
bounded in green
U NYS Department of Environmental Conservation
attachment 3.
79

-------
Chapter 3
80

-------
Natural Resource Damages Assessment - Greenpoint Petroleum Remediation Project
Background
As noted above, the legislative history of H.R. 889 is largely contained in remarks made by
Representative Anthony Weiner (D-NY) in the Congressional Record of June 26, 2006. In
Representative Weiner's remarks, he stated that in preparing the Newtown Creek/Greenpoint oil
spill study, EPA was to revisit the findings of the U.S. Coast Guard's July 1979 report entitled
"Investigation of Underground Accumulation of Hydrocarbons along Newtown Creek," and
more specifically, address the "extent to which the Spill has affected aquatic species in the Creek
and Harbor, and methods to prevent further harm."
The July 1979 report prepared for the U.S. Coast Guard made no findings concerning potential
natural resource impacts in the Greenpoint area and Newtown Creek caused by the oil spill.
Since 1979, however, a comprehensive framework for studying, assessing, recovering for, and
restoring lost or degraded natural resources has developed through Federal statutes and
regulations, case law, and science. This framework now includes the Oil Pollution Act (OPA90),
the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), and
their regulations (particularly the National Contingency Plan, or NCP).
EPA is not a Federal natural resource trustee. Two other Federal departments, namely the
Department of Commerce through the National Oceanic and Atmospheric Administration, and
the Department of the Interior through the U.S. Fish and Wildlife Service, have been designated
by the President as the leads in addressing most damaged natural resources for the Federal
government. The Departments of Defense, Agriculture, and Energy also have Federal trustee
status for various natural resources. Similarly, State and Tribal governments have been given
prominent roles by Congress in the Federal statutes and regulations that address the restoration
of and compensation for damaged natural resources.
The State of New York has led the response to this spill since the 1980's, when the USCG
determined under its authorities that the State was equipped to perform an adequate response.
After receiving the Federal spill response lead in 2006 from the USCG under OPA90, EPA has
served in a supporting role to the State, and has also commenced the study called for by
H.R.889. At this time, EPA believes that the State continues to have the capability to perform,
and is in fact performing, an adequate response to the spill. As discussed further below, among
the response actions planned by the State with respect to the spill is to perform, in conjunction
with NOAA, an expedited natural resource damage assessment of Newtown Creek.
81

-------
EPA's Limited Role in Addressing Natural Resource Damages
Even when EPA has been designated under OPA90 as the lead Federal response agency for
an onshore oil spill such as the Newtown Creek/Greenpoint spill, its involvement with natural
resource damages is limited. Section 1011 of OPA90 provides that the President "shall
consult with the affected trustees...on the appropriate removal action to be taken in connection
with any discharge of oil." 33 U.S.C. § 2711. Section 300.305(e) of the NCP provides that the
EPA On-Scene Coordinator "shall ensure that the natural resource trustees are promptly
notified in the event of any discharge of oil." Promptly after assuming the Federal lead for
the spill from the U.S. Coast Guard on July 21, 2006, EPA's On-Scene Coordinator for the
spill notified his counterparts within NOAA and the State of New York of the discharge of oil
in the Greenpoint community and into Newtown Creek. (Again, EPA made the determination
in July of 2006 that the response to the spill was being adequately managed by the State of
New York; EPA does not foresee taking a more active role in the spill response at this time.)
Section 300.305(e) of the NCP also provides that the "OSC and the trustees shall coordinate
assessments, evaluations, investigations, and planning with respect to appropriate removal
actions," and that the OSC "shall consult with the affected trustees on the appropriate removal
action to be taken." Since EPA's assumption of the Federal lead for the spill response, EPA's
OSC and other EPA personnel have coordinated and consulted with the affected trustees, in
particular the State of New York, concerning most aspects of EPA's involvement with the
spill.
Designation of Federal and State Trustees
OPA90's and CERCLA's natural resource damage provisions are similar in most respects.
CERCLA pre-dated OPA90, and therefore many of OPA90's natural resource damage
provisions are based on those in CERCLA. Given that the Newtown Creek/Greenpoint oil spill
is being addressed under OPA90, however, the H.R. 889 Report focuses on OPA90's natural
resource damage provisions. Under OPA90, the responsibility for protection of natural
resources rests in Federal, State, and Tribal trustees. Federal law in the U.S. incorporates the
English common law principle that natural resources are held in trust for the public by the
resources' trustees.
OPA90 requires the President to designate through the NCP the Federal officials who act on
behalf of the public as trustees for natural resources. OPA90 § 1006, 33 U.S.C. § 2706. The
President has not designated any EPA officials as Federal trustees under OPA90 or any
Federal statute.
Instead, the President has designated Secretaries of Commerce, Interior, Defense, Agriculture,
and Energy to act as Federal trustees for the nation's natural resources. In the case of the
Newtown Creek/Greenpoint oil spill, the Secretary of Commerce through the Administrator of
the National Oceanic and Atmospheric Administration is the lead Federal natural resource trustee
because of the coastal and marine resources of the Creek.
82

-------
Specifically, the Secretary of Commerce is by regulation the Federal trustee for "natural
resources managed or controlled by [the Department of Commerce] and for natural resources
managed or controlled by other Federal agencies and that are found in, under, or using waters
navigable by deep draft vessels, tidally influenced waters, or waters of the contiguous zone, the
exclusive economic zone, and the outer continental shelf." 40 C.F.R. Part 300.600(b)(1). The
regulations authorize the Secretary to pursue a claim for damages "when there is injury to,
destruction of, loss of, or threat to natural resources, including their supporting ecosystems, as a
result of a release of a hazardous substance or a discharge of oil." 40 C.F.R. Part 300.600(b).
Through a further delegation from the Secretary of Commerce, the trustee responsibility for the
natural resources found in our nation's coastal and marine environments rests in the NOAA
Administrator. Newtown Creek is part of the New York Harbor estuary system, a coastal and
marine environment.
The governor of each State appoints the trustee of natural resources. OPA90 § 1006(b)(3); 40
C.F.R. Part 300.605. The governor of New York has appointed the Commissioner of the New
York State Department of Environmental Conservation (NYSDEC) to serve as trustee of the
State's natural resources. For certain resources, the State trustee role can run concurrently
with Federal and Tribal trustee roles. In the case of Newtown Creek, both the Federal and
State governments have expressed their respective trustee interests in the natural resources
relating to the Creek.
Status of Natural Resource Actions Regarding Newtown Creek
In 2006, NYSDEC referred the State's potential natural resource damages claim for the Creek
to the New York State Department of Law (NYSDOL). Since then, NYSDOL has been
actively engaged in discussions with NOAA (in its role as Federal trustee), and Phelps Dodge
Corporation regarding a possible claim related to the effects of contamination from the former
Phelps Dodge facility on Newtown Creek. The former facility, located on the north side of
Newtown Creek immediately east of the Kosciusko Bridge, was the subject of an extensive
remediation under the State's hazardous waste site remediation program. NYSDOL has also
sought to enter into settlement negotiations with Exxon/Mobil. Such negotiations have
reportedly been unsuccessful.
Other than the sampling undertaken by Phelps Dodge in the sections of the Creek closest to its
facility, there has been very little sampling of conditions in the Creek, including surface waters,
sediments, and biota. No identification has been made of the natural resources in the Creek
damaged by discharges of petroleum products or hazardous substances. Accordingly, there has
been no assessment of such damages. NYSDOL and NOAA have entered into discussions with
Phelps Dodge regarding the performance of an expedited natural resource damages assessment
for the Creek. Such an expedited assessment would be similar to one that the State performed
recently for Lake Ontario.
83

-------