United States
Environmental Protection
Agency
Office of Water	EPA-821 -R-19-012
Washington, DC 20460 November 1, 2019
Regulatory Impact Analysis
for Proposed Revisions to
the Effluent Limitations
Guidelines and Standards
for the Steam Electric Power
Generating Point Source
Category

-------
United Stales
Environmental Protection
Ag«ncy
Regulatory Impact Analysis for Proposed
Revisions to the Effluent Limitations
Guidelines and Standards for the Steam
Electric Power Generating Point Source
Category
EPA-821-R-19-012
November 2019
U.S. Environmental Protection Agency
Office of Water (4303T)
Engineering and Analysis Division
1200 Pennsylvania Avenue, NW
Washington, DC 20460

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
Acknowledgements and Disclaimer
This report was prepared by the U.S. Environmental Protection Agency. Neither the United States
Government nor any of its employees, contractors, subcontractors, or their employees make any warrant,
expressed or implied, or assume any legal liability or responsibility for any third party's use of or the
results of such use of any information, apparatus, product, or process discussed in this report, or
represents that its use by such party would not infringe on privately owned rights.

-------
RIA for Proposed Revisions to Steam Electric Power Generating ELGs	Contents
Table of Contents
Table of Contents	i
List of Tables	v
List of Figures	vii
Abbreviations	viii
Executive Summary	1
1	Introduction	1-1
1.1	Background	1-1
1.2	Overview of the Costs and Economic Impacts Analysis	1-2
1.2.1	Main Regulatory Options Presented in the Proposed Rule	1-2
1.2.2	Baseline	1-4
1.2.3	Cost and Economic Analysis Requirements under the Clean Water Act	1-4
1.2.4	Analyses in Support of the Regulatory Options and Report Organization	1-5
2	Overview of the Steam Electric Industry	2-1
2.1	Steam Electric Industry	2-1
2.1.1	Owner Type and Size	2-2
2.1.2	Geographic Distribution of Steam Electric Power Plants	2-4
2.1.3	Electricity Generation	2-7
2.2	Other Environmental Regulations	2-8
2.2.1	Clean Power Plan (CPP) and Affordable Clean Energy (ACE) Regulations	2-8
2.2.2	Coal Combustion Residuals Rule	2-9
2.3	Market Conditions and Trends in the Electric Power Industry	2-9
3	Compliance Costs	3-1
3.1	Analysis Approach and Inputs	3-1
3.1.1	Plant-Specific Costs Approach	3-2
3.1.2	Plant-Level Costs	3-2
3.1.3	Technology Implementation Years	3-3
3.1.4	Total Compliance Costs	3-5
3.1.5	Voluntary Incentive Program	3-6
3.2	Key Findings for Regulatory Options	3-7
3.2.1	Estimated Industry-level Total Compliance Costs	3-7
3.2.2	Estimated Regional Distribution of Total Compliance Costs	3-8
3.3	Key Uncertainties and Limitations	3-10
EPA-821-R-19-012

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
Contents
4	Cost and Economic Impact Screening Analyses	4-1
4.1	Analysis Overview	4-1
4.2	Cost-to-Revenue Analysis: Plant-Level Screening Analysis	4-1
4.2.1	Analysis Approach and Data Inputs	4-2
4.2.2	Key Findings for Regulatory Options	4-3
4.2.3	Uncertainties and Limitations	4-5
4.3	Cost-to-Revenue Screening Analysis: Parent Entity-Level Analysis	4-5
4.3.1	Analysis Approach and Data Inputs	4-5
4.3.2	Key Findings for Regulatory Options	4-7
4.3.3	Uncertainties and Limitations	4-9
5	Assessment of the Impact of the Regulatory Options in the Context of National Electricity
Markets	5-1
5.1	Model Analysis Inputs and Outputs	5-3
5.1.1	Analysis Years	5-3
5.1.2	Key Inputs to IPM V6 for the Market Model Analysis of the Proposed ELG Revisions	5-4
5.1.3	Key Outputs of the Market Model Analysis Used in Assessing the Effects of the Regulatory
Options	5-5
5.2	Findings from the Market Model Analysis	5-5
5.2.1	National-level Analysis Results for Model Years 2021-2050 	5-5
5.2.2	Detailed Analysis Results for Model Year 2030	5-9
5.3	Estimated Effects of the Regulatory Options on New Capacity	5-22
5.4	Uncertainties and Limitations	5-23
6	Assessment of the Impact of the Regulatory Options on Employment	6-1
6.1	Background and Context	6-1
6.1.1	Employment Impacts of Environmental Regulations	6-1
6.1.2	Current State of Knowledge Based on the Peer-Reviewed Literature	6-2
6.1.3	Labor Supply and Macroeconomic Net Employment Effects	6-2
6.1.4	Distributional Considerations	6-3
6.2	Analysis Overview	6-3
6.2.1	Estimated Employment Effects in Coal-Fired Electric Power Plants Affected by the
Regulatory Options	6-3
6.2.2	Coal Mining and Other Energy Sources	6-4
6.3	Findings	6-5
7	Assessment of Potential Electricity Price Effects	7-1
7.1 Analysis Overview	7-1
EPA-821-R-19-012
ii

-------
RIA for Proposed Revisions to Steam Electric Power Generating ELGs	Contents
7.2	Assessment of Impact of Compliance Costs on Electricity Prices	7-2
7.2.1	Analysis Approach and Data Inputs	7-2
7.2.2	Key Findings for Regulatory Options	7-2
7.2.3	Uncertainties and Limitations	7-7
7.3	Assessment of Impact of Compliance Costs on Household Electricity Costs	7-7
7.3.1	Analysis Approach and Data Inputs	7-7
7.3.2	Key Findings for Regulatory Options	7-8
7.3.3	Uncertainties and Limitations	7-10
7.4	Distribution of Electricity Cost Impact on Household	7-10
8	Assessment of Potential Impact of the Regulatory Options on Small Entities - Regulatory
Flexibility Act (RFA) Analysis	8-1
8.1	Analysis Approach and Data Inputs	8-2
8.1.1	Determining Parent Entity of Steam Electric Power Plants	8-2
8.1.2	Determining Whether Parent Entities of Steam Electric Power Plants Are Small	8-2
8.1.3	Significant Impact Test for Small Entities	8-6
8.2	Key Findings for Regulatory options	8-6
8.3	Uncertainties and Limitations	8-9
8.4	Small Entity Considerations in the Development of Rule Options	8-10
9	Unfunded Mandates Reform Act (UMRA) Analysis	9-1
9.1	UMRA Analysis of Impact on Government Entities	9-2
9.2	UMRA Analysis of Impact on Small Governments	9-4
9.3	UMRA Analysis of Impact on the Private Sector	9-6
9.4	UMRA Analysis Summary	9-7
10	Other Administrative Requirements	10-1
10.1	Executive Order 12866: Regulatory Planning and Review and Executive Order 13563: Improving
Regulation and Regulatory Review	10-1
10.2	Executive Order 13771: Reducing Regulation and Controlling Regulatory Costs	10-2
10.3	Executive Order 12898: Federal Actions to Address Environmental Justice in Minority Populations
and Low-Income Populations	10-2
10.4	Executive Order 13045: Protection of Children from Environmental Health Risks and Safety Risks
	10-3
10.5	Executive Order 13132: Federalism	10-4
10.6	Executive Order 13175: Consultation and Coordination with Indian Tribal Governments	10-4
EPA-821-R-19-012
iii

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
Contents
10.7 Executive Order 13211: Actions Concerning Regulations That Significantly Affect Energy Supply,
Distribution, or Use	10-5
10.7.1 Impact on Electricity Generation	10-6
10.7.2Impact on Electricity Generating Capacity	10-6
10.7.3	Cost of Energy Production	10-6
10.7.4	Dependence on Foreign Supply of Energy	10-7
10.7.5	Overall E.O. 13211 Finding	10-8
10.8	Paperwork Reduction Act of 1995 	10-8
10.9	National Technology Transfer and Advancement Act	10-9
11	Cited References	11-1
A	Summary of Changes to Costs and Economic Impact Analysis	1
B	Comparison of Incremental Costs and Pollutant Removals	1
B.l	Methodology	1
B.2	Results	2
Toxic Weights of Pollutants and POTW Removal	2
Evaluated Options	2
Pollutant Removals and Pound Equivalent Calculations	2
Annualized Compliance Costs	2
C IPM Sensitivity Analysis Including ACE Rule	1
C.l	Baseline Changes	1
C.2 Market Level Impacts	3
Summary of Impacts Over Analysis Period	3
Detailed Market-level Impacts for Year 2030	5
EPA-821-R-19-012

-------
RIA for Proposed Revisions to Steam Electric Power Generating ELGs	Contents
List of Tables
Table 1-1: Regulatory Options	1-3
Table 2-1: Steam Electric Industry Share of Total Electric Power Generation Plants and Capacity in 2016
	2-2
Table 2-2: Existing Steam Electric Power Plants, Their Parent Entities, and Capacity by Ownership Type,
2016	2-2
Table 2-3: Parent Entities of Steam Electric Power Plants by Ownership Type and Size (assuming two
different ownership cases)a b	2-3
Table 2-4: Steam Electric Power Plants by Ownership Type and Size	2-4
Table 2-5: NERC regions	2-5
Table 2-6: Steam Electric Power Plants and Capacity by NERC Region, 2012a b	2-6
Table 2-7: Net Generation by Energy Source and Ownership Type, 2012-2016 (TWh)	2-7
Table 3-1: Compliance Deadlines for the Baseline and Regulatory Options	3-4
Table 3-2: Estimated Total Annualized Compliance Costs (in millions, 2018$, at 2020)	3-7
Table 3-3: Estimated Incremental Annualized Compliance Costs (in millions, 2018$, at 2020)	3-8
Table 3-4: Estimated Incremental Annualized Compliance Costs, by Wastestream (in millions, 2018$, at
2020)	3-8
Table 3-5: Estimated Annualized Incremental Compliance Costs by NERC Region (in millions, 2018$, at
2020)	3-9
Table 4-1: Plant-Level Cost-to-Revenue Analysis Results for the Baseline by Owner Type	4-3
Table 4-2: Plant-Level Incremental Cost-to-Revenue Analysis Results by Owner Type and Regulatory
Option	4-4
Table 4-3: Baseline Entity-Level Cost-to-Revenue Analysis Results	4-7
Table 4-4: Entity-Level Incremental Cost-to-Revenue Analysis Results	4-8
Table 5-1: IPM Run Years	5-3
Table 5-2: Baseline Projections, 2021-2050	5-6
Table 5-3: National Impact of Regulatory Options Relative to Baseline, 2021-2050	5-7
Table 5-4: Impact of Regulatory Options on National and Regional Markets at the Year 2030	5-10
Table 5-5: Impact of Regulatory Options on In-Scope Plants, as a Group, at the Year 2030a	5-16
Table 5-6: Impact of Regulatory Options on Individual In-Scope Plants at the Year 2030	5-22
Table 7-1: Compliance Cost per KWh Sales by NERC Region and Regulator Option in 2020 (2018$).. 7-3
Table 7-2: Projected 2020 Price (Cents per kWh of Sales) and Potential Price Increase Due to Compliance
Costs by NERC Region and Regulatory Option (2018$)	7-5
EPA-821-R-19-012
v

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
Contents
Table 7-3: Potential Incremental Price Changes Relative to Baseline Due to Compliance Costs by NERC
Region and Regulatory Option (2018$)	7-6
Table 7-4: Average Incremental Annual Cost per Household in 2020 by NERC Region and Regulatory
Option (2018$)	7-9
Table 8-1: NAICS Codes and SBA Size Standards for Non-government Majority Owners Entities of
Steam Electric Power Plants	8-3
Table 8-2: Number of Entities by Sector and Size (assuming two different ownership cases)	8-5
Table 8-3: Steam Electric Power Plants by Ownership Type and Size	8-5
Table 8-4: Estimated Baseline Cost-To-Revenue Impact on Small Parent Entities, by Entity Type and
Ownership Category	8-7
Table 8-5: Estimated Incremental Cost-To-Revenue Impact on Small Parent Entities, by Entity Type and
Ownership Category	8-8
Table 9-1: Government-Owned Steam Electric Power Plants and Their Parent Entities	9-2
Table 9-2: Estimated Compliance Costs to Government Entities Owning Steam Electric Power Plants
(Millions; 2018$)	9-3
Table 9-3: Estimated Incremental Compliance Costs to Government Entities Owning Steam Electric
Power Plants (Millions; 2018$)	9-4
Table 9-4: Counts of Government-Owned Plants and Their Parent Entities, by Size	9-5
Table 9-5: Estimated Incremental Compliance Costs for Electric Generators by Ownership Type and Size
(2018$)	9-5
Table 9-6: Compliance Costs for Electric Generators by Ownership Type (2018$)	9-7
Table 10-1: Total Market-Level Capacity and Generation by Type for Options 2 and 4 in 2030	10-7
Table 10-2: Total Market-Level Fuel Use by Fuel Type for Options 2 and 4 in 2030	10-8
EPA-821-R-19-012

-------
RIA for Proposed Revisions to Steam Electric Power Generating ELGs	Contents
List of Figures
Figure 2-1: North American Electric Reliability Corporation (NERC) Regions	2-6
Figure B-l: Estimated Removals and Costs of the Regulatory Options, Relative to Baseline	3
EPA-821-R-19-012
vii

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
Abbreviations
Abbreviations
ACE
Affordable Clean Energy
AEO
Annual Energy Outlook
ASCC
Alaska Systems Coordinating Council
BAT
Best available technology economically achievable
BCA
Benefit and Cost Analysis
BEA
U.S. Bureau of Economic Analysis
BLS
U.S. Bureau of Labor Statistics
BMP
Best management practice
BPT
Best practicable control technology currently available
BSER
Best system of emissions reduction
CAA
Clean Air Act
CCI
Construction cost index
CCR
Coal combustion residuals
CPP
Clean Power Plan
CSAPR
Cross-State Air Pollution Rule
CWA
Clean Water Act
DOE
Department of Energy
EA
Environmental Assessment
ECI
Employment Cost Index
EGU
Electricity generating units
EIA
Energy Information Administration
EJ
Environmental justice
ELGs
Effluent limitations guidelines and standards
EO
Executive Order
EPA
U.S. Environmental Protection Agency
FGD
Flue gas desulfurization
FOM
Fixed O&M
FR
Federal Register
FRCC
Florida Reliability Coordinating Council
GDP
Gross domestic product
HICC
Hawaii Coordinating Council
HRI
Heat rate improvement
HRTR
High Hydraulic Residence Time Reduction
IPM
Integrated Planning Model
LRTR
Low Hydraulic Residence Time Reduction
MATS
Mercury and Air Toxics Standards
MRO
Midwest Reliability Organization
NAICS
North American Industry Classification System
NERC
North American Electric Reliability Corporation
NPCC
Northeast Power Coordinating Council
NPDES
National Pollutant Discharge Elimination System
NSPS
New Source Performance Standards
EPA-821-R-19-012
viii

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
Abbreviations
O&M
Operation and maintenance
OMB
Office of Management and Budget
POTW
Publicly owned treatment works
PSES
Pretreatment Standards for Existing Sources
PSNS
Pretreatment Standards for New Sources
RFA
Regulatory Flexibility Act
RFC
Reliability First Corporation
RGGI
Regional Greenhouse Gas Initiative
SBA
Small Business Administration
SBREFA
Small Business Regulatory Enforcement Fairness Act
SERC
SERC Reliability Corporation
SISNOSE
Significant impact on a substantial number of small entities
SPP
Southwest Power Pool
TDD
Technical Development Document
TWPE
Toxic weighted pound equivalent
UMRA
Unfunded Mandates Reform Act
VOM
Variable O&M
WECC
Western Energy Electricity Coordinating Council
TRE
Texas Regional Reliability Entity
EPA-821-R-19-012
ix

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
Executive Summary
Executive Summary
The U.S. Environmental Protection Agency (EPA) is proposing a regulation that would revise the
technology-based effluent limitations guidelines and standards (ELGs) for the steam electric power
generating point source category, 40 CFR part 423, which the EPA promulgated in November 2015 (80
FR 67838). The regulatory options would revise certain best available technology (BAT) effluent
limitations and pretreatment standards for existing sources (PSES) for two wastestreams: flue gas
desulfurization (FGD) wastewater and bottom ash transport water.
This proposed action is an economically significant deregulatory action that was submitted to the Office
for Management and Budget (OMB) for interagency review. This Regulatory Impact Analysis (RIA)
presents an assessment of the compliance costs and impacts associated with this action and present
analyses to meet various statutory and Executive Order requirements. The accompanying Benefit Cost
Analysis (BCA) document presents social costs and benefits of the action, consistent with Executive
Orders 12866, 13563, and 13771.
Regulatory Options
The EPA analyzed four different regulatory options (Table ES-1). The baseline for the analyses reflects
2015 ELG requirements (in absence of any new final EPA action). The Agency calculated the difference
between the baseline and the regulatory options to determine the net incremental effect (as positive or
negative change) of the regulatory options. The EPA proposes to establish BAT effluent limitations based
on the technologies described in Option 2.
Table ES-1: Regulatory Options
Wastestream
Subcategory
Technology Basis for BAT/PSES Regulatory Options3
2015 Rule
(Baseline)
Option 1
Option 2
Option 3
Option 4
FGD
Wastewater
NAb
Chemical
Precipitation
+ Biological
Treatment
Chemical
Precipitation
Chemical
Precipitation
+ LRTR
Biological
Treatment
Chemical
Precipitation
+ LRTR
Biological
Treatment
Membrane
Filtration
High FGD Flow
Facilities: Plant-level
scrubber purge flow
>4 MGD
NS
NS
Chemical
Precipitation
Chemical
Precipitation
Chemical
Precipitation
Low Utilization
Boilers: All units have
net generation <
876,000 MWh
NS
NS
Chemical
Precipitation
NS
NS
Boilers retiring by
2028°
NS
Surface
Impoundment
Surface
Impoundment
Surface
Impoundment
Surface
Impoundment
FGD Wastewater Voluntary Incentives
Program (Direct Dischargers Only)
Chemical
Precipitation
+ Evaporation
Membrane
Filtration
Membrane
Filtration
Membrane
Filtration
NA
EPA-821-R-19-012
ES-1

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
Executive Summary
Table ES-1: Regulatory Options
Wastestream
Subcategory
Technology Basis for BAT/PSES Regulatory Options3
2015 Rule
(Baseline)
Option 1
Option 2
Option 3
Option 4
Bottom Ash
Transport
Water
NAb
Dry Handling /
Closed loop
Dry Handling
or High
Recycle Rate
Systems
Dry Handling
or High
Recycle Rate
Systems
Dry Handling
or High
Recycle Rate
Systems
Dry Handling
or High
Recycle Rate
Systems
Low Utilization
Boilers: All units have
net generation <
876,000 MWh
NS
NS
Surface
Impoundment
+ BMP Plan
NS
NS
Boilers retiring by
2028
NS
Surface
Impoundment
Surface
Impoundment
Surface
Impoundment
Surface
Impoundment
Abbreviations: BMP = Best Management Practice; LRTR = Low Hydraulic Residence Time; NS = Not subcategorized; NA = Not
applicable
a.	See Supplemental TDD for a description of these technologies
b.	The 2015 rule subcategorized units with nameplate capacity 50 MW or less and the EPA is not revising requirements for these
units in this proposal.
Source: U.S. EPA, 2019
Annualized Compliance Costs
The EPA estimates that the four options provide compliance cost savings when compared to the baseline
(Table ES-2). On an after-tax basis, the cost savings when compared to baseline compliance costs range
from $26.4 million to $146.5 million, depending on the option. The proposed option, Option 2, provides
the greatest cost savings, followed by Option 1, Option 3, and finally Option 4.
Table ES-2: Estimated Incremental Annualized After-tax Compliance Costs (in millions, 2018$,
discounted at 2020 using 7 percent)
Regulatory Option
Net Capital
Technology
Net Other Initial One-
Timea
Net Total O&M
Net Total Costs
Option 1
-$97.0
$0.0
-$39.6
-$136.6
Option 2
-$104.0
$0.1
-$42.5
-$146.5
Option 3
-$86.8
$0.0
-$19.0
-$105.9
Option 4
-$60.4
$0.0
$34.0
-$26.4
Source: U.S. EPA Analysis, 2019
Impacts on Steam Electric Industry and Electricity Market
The EPA assessed the impacts of the regulatory options on the steam electric industry and the electricity
market in two ways:
1. A screening-level assessment reflecting historical characteristics of steam electric power plants
and with assignment of estimated compliance costs to the plants and their owners. Specifically,
the EPA calculated cost-to-revenue ratios for individual steam electric power plants and for
domestic parent-entities owning these plants to assess the relative impact of compliance outlays.
Overall, this screening-level analysis shows that few entities are likely to experience significant
EPA-821-R-19-012
ES-2

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
Executive Summary
changes in compliance costs compared to revenues, and all four regulatory options further lessen
economic impacts to these entities. See Chapter 4 for details.
2. A broader electricity market-level analysis using the Integrated Planning Model (IPM), which
provides a more comprehensive indication of the economic impacts of the regulatory options,
including an assessment of changes in in the operating characteristics of steam electric power
plants and other electricity generators resulting from changes in electricity markets and the
regulatory options. The EPA conducted these IPM analyses on regulatory options 2 and 4 to
capture the range of potential impacts of this proposal.
Results across these analyses show that the proposed Option 2 would have small impacts on the steam
electric power plants, on the entities that own these plants, and on the electricity market as a whole. For
example, IPM results for the market show net changes in total generation capacity or generation costs of
less than 0.5 percent across economic measures for Option 2 in the model year 2030 after implementation
of the revised ELGs (see Table ES-3). The proposed option results in a small projected increase in
generation capacity (0.1 percent of the baseline), including net avoided early retirements of coal-fired
electricity generating units. Results for steam electric power plants (in Table ES-4), also show small
impacts, with a net increase in total capacity under Option 2 when compared to the baseline of
approximately 0.9 percent, and net increases in total generation by steam electric power plants of
0.3 percent for Option 2. These findings suggest that Option 2 in this proposal would have small
economic consequences for the steam electric power generating industry and the electricity market
overall. Looking specifically at plants with estimated compliance costs, the results for Option 2 shows no
change, or less than a one percent reduction or one percent increase in capacity utilization, electricity
generation, or variable production costs, providing further support the conclusion that the effects of
Option 2 in this proposed rule on the steam electric industry will be small. See Chapter 5 for details of
these analyses, including results by region and for different model years. Results for Option 4 show
greater impacts, but they are still considered small.
Table ES-3: Modeled Impact of Regulatory Options on National Electricity Market at the Year 2030
Economic Measures
Baseline
Option 2
Option 4
(all dollar values in 2018$)
Value
Value
Difference
% Change
Value
Difference
% Change
Total Domestic Capacity (GW)
1,142
1,143
0.6
0.1%
$1,144
1.4
0.1%
Existing
1 1 15
0.1%

2.0
0.2%
New Additions
1 1 "0.9
-0.1%

-0.6
-0.1%
Early Retirements

1 -1-5
-0.1%

-2.0
-0.2%
Generation (TWh)
4,286
4,287
0.1
0.0%
4,287
0.2
0.0%
Costs ($Millions)
$156,921
$156,781
-$140
-0.1%
$156,925
$4
0.0%
Fuel Cost
$69,971
$70,028
$57
0.1%
$69,991
$20
0.0%
Variable O&M
$10,261
$10,263
$2
0.0%
$10,307
$47
0.5%
Fixed O&M
$52,916
$52,834
-$82
-0.2%
$52,933
$17
0.0%
Capital Cost
$23,774
$23,657
-$117
-0.5%
$23,694
-$79
-0.3%
Variable Production Cost ($/MWh)
$18.72
$18.73
$0.01
0.1%
$18.73
$0.01
0.1%
C02 Emissions (Million Metric







Tons)
1,581
1,585
3.9
0.2%
1,582
1.2
0.1%
Mercury Emissions (Tons)
4
4
0.0
0.4%
4
0.0
0.1%
NOx Emissions (Million Tons)
1
1
0.0
0.5%
1
0.0
0.1%
EPA-821-R-19-012
ES-3

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
Executive Summary
Table ES-3: Modeled Impact of Regulatory Options on National Electricity Market at the Year 2030
Economic Measures
Baseline
Option 2
Option 4
(all dollar values in 2018$)
Value
Value
Difference
% Change
Value
Difference
% Change
S02 Emissions (Million Tons)
1
1
0.0
0.6%
1
0.0
0.2%
HCL Emissions (Million Tons)
0
0
0.0
0.5%
0
0.0
0.1%
Source: U.S. EPA Analysis, 2019
Table ES-4: Impact of Regulatory Options on Facilities in the Steam Electric Power Generating
Point Source Category, as a Group, at the Year 2030
Economic Measures
Baseline
Option 2
Option 4
(all dollar values in 2018$)
Value
Value
Difference
% Change
Value
Difference
% Change
Total Domestic Capacity
336,872
339,752
2,880
0.9%
340,066
3,194
0.9%
(MW)







Early Retirements -
79
79
0
0.0%
78
-1
-1.3%
Number of Plants







Full & Partial
58,192
55,312
-2,880
-4.9%
54,998
-3,194
-5.5%
Retirements - Capacity







(MW)







Generation (GWh)
1,570,513
1,575,189
4,676
0.3%
1,571,747
1,235
0.1%
Costs ($Millions)
$60,298
$60,397
$98
0.2%
$60,401
$103
0.2%
Fuel Cost
$34,842
$34,976
$134
0.4%
$34,893
$51
0.1%
Variable O&M
$5,987
$5,999
$12
0.2%
$6,040
$52
0.9%
Fixed O&M
$19,165
$19,117
-$48
-0.3%
$19,166
$1
0.0%
Capital Cost
$304
$304
$0
0.1%
$303
-$1
-0.3%
Variable Production Cost
$26.00
$26.01
$0.02
0.1%
$26.04
$0.05
0.2%
($/MWh)







Source: U.S. EPA Analysis, 2019
Potential Impacts on Employment
In addition to addressing the costs and impacts of the regulatory options, the EPA discusses the potential
impacts of this rulemaking on employment in Chapter 6. Overall, any job impacts of the regulatory
options, both positive and negative, are estimated to be small.
Potential Electricity Price Effects
The EPA also assessed the potential impacts of the regulatory options on electricity prices, assuming full
cost pass-through of compliance costs in electricity prices. The Agency conducted this analysis in two
parts: (1) an assessment of the potential annual changes in electricity costs per MWh of total electricity
sales; and (2) an assessment of the potential annual changes in household electricity costs. Chapter 7
details these analyses.
Changes in costs per MWh of total electricity sales are small for all regulatory options; the maximum
difference in price effect is a fraction of a cent per kWh. Overall across the United States, Option 2 results
in the highest cost savings of 0.0050 per kWh, and Option 4 results in the lowest cost savings of 0.0010
per kWh.
On the national level, cost savings relative to household electricity costs are greatest on average under
Option 2, with average cost savings of $0.49 per year per household; by region, cost savings range
EPA-821-R-19-012
ES-4

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
Executive Summary
between $0.03 and $1.20 per year per household. The least cost savings occur under Option 4, with
average cost savings per residential household of $0.07 per year; by region, cost savings range between
$0.01 and $0.21 per year. The average incremental annual cost savings per residential household is
greatest in the Southeastern Electric Reliability Council (SERC) region and the least in Western Energy
Coordinating Council (WECC) region under all options.
Potential Impacts on Small Entities
In accordance with the Regulatory Flexibility Act (RFA) requirements, the EPA assessed whether the
regulatory options would have "a significant impact on a substantial number of small entities"
(SISNOSE). The analysis is detailed in Chapter 8.
This involved analyzing the baseline, analyzing the four regulatory options, and then drawing conclusions
on the basis of the differences between the options and the baseline. Given net cost savings described
earlier, the proposed rule may also lessen impacts on small entities. The EPA estimates that 79 to 127
small entities own steam electric power plants that may incur compliance costs under the proposed option.
In the baseline, the EPA estimates that 4 small entities owning steam electric power plants would incur
costs exceeding one percent of revenue, and 2 of the 4 would incur costs exceeding three percent of
revenue. Under Option 2, relative to the baseline 2 fewer small entities would incur costs exceeding one
percent of revenue, and 1 fewer small entity would incur costs exceeding three percent of revenue. Under
the other three options, 1 fewer small entity would incur costs exceeding one percent of revenue, and no
change is estimated for the number of plants incurring costs greater than three percent of revenue. This
screening-level analysis suggests that the proposed option is estimated to reduce this impact further by
providing cost savings to many small entities.
Unfunded Mandate Reform Act
Under Title II of the Unfunded Mandates Reform Act (UMRA) of 1995 section 202, the EPA generally
must prepare a written statement, including a cost-benefit analysis, for proposed and final rules with
"Federal mandates" that might result in expenditures by State, local, and Tribal governments, in the
aggregate, or by the private sector, of $100 million (adjusted annually for inflation) or more in any one
year (i.e., $160 million in 2018 dollars). As discussed in Chapter 9, the EPA estimates that the proposed
option would not result in incremental expenditures of at least $160 million for State and local
government entities, in the aggregate, or for the private sector in any one year. In fact, Option 2 would
provide net cost savings when compared to the baseline. Furthermore, neither permitted plants nor
permitting authorities are estimated to incur significant additional administrative costs as the result of the
regulatory options. Consistent with Section 205 of UMRA, the EPA presents four regulatory options
which would all reduce impacts to governments and the private sector. The proposed option (Option 2) is
the least costly option presented, and thus would result in the lowest impacts to governments and the
private sector. Furthermore, several government and private sector plants would likely fall into
subcategories within Option 2 which would provide additional flexibility. Finally, the implementation
period built into Option 2 is another way for permit writers to consider the site-specific needs of steam
electric power plants.
EPA-821-R-19-012
ES-5

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
Executive Summary
Other Administrative Requirements
The EPA conducted analyses to address other administrative requirements. Key findings, which are
discussed further in Chapter 10, include:
•	Executive Order 12866: Regulatory Planning and Review and Executive Order 13563:
Improving Regulation and Regulatory Review: Pursuant to the terms of Executive Order
12866, this action is an "economically significant regulatory action" because the action is likely
to have an annual effect on the economy of $100 million or more, although the direction of the
effect is estimated to be a reduction in costs when compared to the baseline. As such, the action is
subject to review by the OMB under Executive Orders 12866 and 13563. Any changes made in
response to OMB suggestions or recommendations will be documented in the docket for this
action. The EPA prepared an analysis of the potential benefits and costs associated with this
action; this analysis is detailed in Chapter 13 of the BCA document (U.S. EPA, 2019b).
•	Executive Order 13771: Reducing Regulation and Controlling Regulatory Costs: The
proposed rule, if finalized, is expected to be a deregulatory action under E.O. 13771, Reducing
Regulation and Controlling Regulatory Costs. See Chapter 12 in the BCA document (U.S. EPA,
2019b) for details on the time profile of costs and annualized discounted costs.
•	Executive Order 13211: Actions Concerning Regulations That Significantly Affect Energy
Supply, Distribution, or Use: The EPA's analyses show that the proposed Option 2 would not
have a significant adverse effect at a national or regional level under Executive Order 13211.
Specifically, the Agency's analyses found that Option 2 would not reduce electricity production
in excess of 1 billion kilowatt hours per year or in excess of 500 megawatts of installed capacity
under either of the options analyzed, nor would the option increase U.S. dependence on foreign
supply of energy.
•	Executive Order 12898: Federal Actions to Address Environmental Justice (EJ) in Minority
Populations and Low-Income Populations: The EPA examined whether the benefits from the
regulatory options may be differentially distributed among population subgroups in the affected
areas. As described in Chapter 10 and detailed in Chapter 14 of the BCA document (U.S. EPA,
2019b), the EPA determined that the majority of impacted communities at the census block,
county, and tribal area levels are poorer and more minority than state averages. Therefore, the
regulatory options could benefit or harm populations with EJ concerns depending on each
option's pollutant exposure potential. The EPA determined that the regulatory options will would
not deny communities from the benefits of environmental improvements estimated to result from
compliance with the more stringent effluent limits, but the options may disproportionally affect
communities in cases where the proposed rule may result in small increases pollutant exposure.
•	Executive Order 13045: Protection of Children from Environmental Health Risks and
Safety Risks: As described in Chapter 10 and detailed in the BCA document (U.S. EPA, 2019b),
the EPA identified several ways in which Option 2 could affect children, including by potentially
increasing health risk from exposure to pollutants present in steam electric power plant
discharges. However, the EPA's analysis of the environmental health risks or safety risks
addressed by this action do not present a disproportionate risk to children.
EPA-821-R-19-012
ES-6

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
1: Introduction
1 Introduction
1.1 Background
The EPA is proposing a regulation that would revise the technology-based effluent limitations guidelines
and standards (ELGs) for the steam electric power generating point source category, 40 CFR part 423,
which the EPA promulgated in November 2015 (80 FR 67838). The regulatory options would revise
certain BAT effluent limitations and pretreatment standards for existing sources for two wastestreams:
bottom ash transport water and flue gas desulfiirization (FGD) wastewater.
This document describes the Agency's analysis of the costs and economic impacts of the proposed
regulatory option and the other options that were evaluated by EPA but are not proposed for the ELG. It
also provides information pertinent to meeting several legislative and administrative requirements.
This document complements and builds on information presented separately in other reports, including:
•	Supplemental Technical Development Document for the Reconsideration of the Effluent
Guidelines and Standards for the Steam Electric Power Generating Point Source Category
(Supplemental TDD) (U.S. EPA, 2019a). The Supplemental TDD provides background on the
regulatory options; applicability and summary of the regulatory options; industry description;
wastewater characterization and identifying pollutants; and treatment technologies and pollution
prevention techniques. It also documents the EPA's engineering analyses to support the
regulatory options including facility specific compliance cost estimates, pollutant loadings, and
non-water quality impact assessment.
•	Benefit and Cost Analysis for Proposed Revisions to the Effluent Limitations Guidelines and
Standards for the Steam Electric Power Generating Point Source Category (BCA) (U.S. EPA,
2019b). The BCA summarizes the societal benefits and costs estimated to result from
implementation of the regulatory options.
•	Supplemental Environmental Assessment for the Reconsideration of the Effluent Guidelines and
Standards for the Steam Electric Power Generating Point Source Category (Supplemental EA)
(U.S. EPA, 2019c). The Supplemental EA summarizes the environmental and human health
improvements that are estimated to result from implementation of the regulatory options.
The proposed revisions to the ELGs for the Steam Electric Power Generating Point Source Category are
based on data generated or obtained in accordance with EPA's Quality Policy and Information Quality
Guidelines. The EPA's quality assurance (QA) and quality control (QC) activities for this rulemaking
include the development, approval and implementation of Quality Assurance Project Plans for the use of
environmental data generated or collected from all sampling and analyses, existing databases and
literature searches, and for the development of any models which used environmental data. Unless
otherwise stated within this document, the data used and associated data analyses were evaluated as
described in these quality assurance documents to ensure they are of known and documented quality,
meet the EPA's requirements for objectivity, integrity and utility, and are appropriate for the intended use.
EPA-821-R-19-012
1-1

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
1: Introduction
1.2 Overview of the Costs and Economic Impacts Analysis
This section describes the key components of the analysis framework. The Agency's analysis generally
follows the methodology the EPA previously used to analyze the ELGs the Agency promulgated in 2015
(see RIA document at U.S. EPA (2015b). Appendix A describes the principal changes to the regulatory
options analysis, as compared to the 2015 rule analysis. These changes include:
•	Updating the information on the control and treatment technologies and associated costs for
bottom ash transport water and FGD wastewater (see Supplemental TDD for details).
•	Updating the universe of steam electric power plants and their wastestreams to account for major
changes such as additional retirements, fuel conversions, ash handling conversions, wastewater
treatment updates and updated information on capacity utilization.
•	Using the most recent Integrated Planning Model platform (IPM v6 vs. IPM v5.13) to evaluate
the impact of the ELG on the electricity markets. IPM v6 incorporates the effects of existing
regulations and programs or estimated to be in effect by the time the regulatory options are
implemented. See additional discussion in Chapter 5: Assessment of the Impact of the Regulatory
Options in the Context of National Electricity Markets.
•	Updating the analysis year (2020 vs. 2015) and dollar year (2018 dollars vs. 2013 dollars).
•	Updating electricity generation, sales, and electricity prices based on the most current data from
the Energy Information Administration (EIA) (e.g., 2016 vs. 2012).
•	Updating the SBA small business size thresholds (October 2017 standards vs. July 2014
standards), updating information about the entities that own steam electric generating units, based
on EIA data, and recategorizing these entities as small or large.
1.2.1 Main Reguia tory Options Presented in the Proposed Rule
The EPA is proposing one regulatory option, described further below. As part of its rule, EPA evaluated
three additional options, which are also presented in the preamble. Table 1-1 summarizes the four
regulatory options evaluated for the proposed rule. The table also shows the technology basis for the 2015
rule, which as discussed in Section 1.2.2 is used as baseline for the analysis. All options evaluated by
EPA include the same technology basis for bottom ash transport water. In general, each succeeding option
from Option 1 to 4 would achieve more reduction in FGD wastewater pollutant discharges.
EPA-821-R-19-012
1-2

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
1: Introduction
Table 1-1: Regulatory Options


Technology Basis for BAT/PSES Regulatory Options3
Wastestream
Subcategory
2015 Rule (Baseline)
Option 1
Option 2
Option 3
Option 4


Chemical
Chemical
Precipitation
Chemical
Chemical


NAb
Precipitation + HRTR
Biological Treatment
Precipitation + LRTR
Biological Treatment
Precipitation + LRTR
Biological Treatment
Membrane Filtration

High FGD Flow Facilities: Plant-
NS
NS
Chemical
Chemical
Chemical
FGD Wastewater
level scrubber purge flow >4 MGD
Precipitation
Precipitation
Precipitation
Low Utilization Boilers: All units


Chemical
Precipitation



have net generation < 876,000
MWh
NS
NS
NS
NS

Boilers retiring by 2028°
NS
Surface
Impoundment
Surface
Impoundment
Surface
Impoundment
Surface
Impoundment
FGD Wastewater Voluntary Incentives Program
(Direct Dischargers Only)
Chemical
Precipitation +
Evaporation
Membrane Filtration
Membrane Filtration
Membrane Filtration
NA

NAb
Dry Handling /
Closed loop
Dry Handling or High
Recycle Rate
Dry Handling or High
Recycle Rate
Dry Handling or High
Recycle Rate
Dry Handling or High
Recycle Rate


Systems
Systems
Systems
Systems
Bottom Ash
Low Utilization Boilers: All units


Surface


Transport Water
have net generation < 876,000
MWh
NS
NS
Impoundment +
BMP Plan
NS
NS

Boilers retiring by 2028
NS
Surface
Impoundment
Surface
Impoundment
Surface
Impoundment
Surface
Impoundment
Abbreviations: BMP = Best Management Practice; HRTR = High Hydraulic Residence Time; LRTR = Low Hydraulic Residence Time; NS = Not subcategorized; NA = Not applicable
a.	See Supplemental TDD for a description of these technologies
b.	The 2015 rule subcategorized units with nameplate capacity 50 MW or less and the EPA is not revising requirements for these units in this proposal.
Source: U.S. EPA Analysis, 2019
EPA-821-R-19-012
1-3

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
1: Introduction
1.2.2	Baseline
The baseline for the analyses supporting this proposed rule reflects the ELG requirements from the 2015
rule as well as the September 2017 postponement rule which delayed the earliest compliance date for the
ELGs applicable to FGD wastewater and bottom ash transport water (in absence of any new final EPA
action). The Agency estimated and presents in this report the compliance costs that plants could incur
under both this baseline and each of the four regulatory options presented in Table 1-1. The Agency
calculated the difference between the baseline and the regulatory options to determine the net effect (as
positive or negative change) of the regulatory options.
The EPA updated baseline information to incorporate major changes in the universe and operational
characteristics of steam electric power plants such as additional retirements and fuel conversions since the
analysis of the 2015 rule detailed in U.S. EPA (2015b). The EPA also incorporated updated information
on the technologies and other controls that plants employ. The current analysis focuses only on the two
wastestreams addressed in the regulatory options: bottom ash transport water and FGD wastewater.
Because of these updates, the costs and economic impacts of the baseline presented in this document are
estimated to differ from those presented in the RIA document for the 2015 rule (U.S. EPA, 2015b), and
better reflect actual costs of the 2015 rule today.
Unless otherwise specified, references to the 2015 rule baseline in the remainder of this document
includes both the technical requirements of the 2015 rule as well as the timing effects of the 2017
applicability date rule.
1.2.3	Cost and Economic Analysis Requirements under the Clean Water Act
The EPA's effluent limitations guidelines and standards for the steam electric industry are promulgated
under the authority of the CWA Sections 301, 304, 306, 307, 308, 402, and 501 (33 U.S.C. 1311, 1314,
1316, 1317, 1318, 1342, and 1361). These CWA sections require the EPA Administrator to publish
limitations and guidelines for controlling industrial effluent discharges consistent with the overall CWA
objective to "restore and maintain the chemical, physical, and biological integrity of the Nation's waters"
(33 U.S.C. 1251(a)). In establishing national effluent guidelines and pretreatment standards for pollutants,
the EPA considers the performance of control and treatment technologies and the cost and/or "economic
achievability" of the controls.
The EPA analyzed economic achievability; the cost and economic impact analysis for this rulemaking
also focuses on understanding the magnitude and distribution of compliance cost savings across the
industry, and the broader market impacts.1 This report also documents analyses required under other
legislative (e.g., Regulatory Flexibility Act, Unfunded Mandates Reform Act) and administrative
requirements (e.g., Executive Order 12866: Regulatory Planning and Review).
Since there have been many changes to the industry since the 2015 rule, the EPA also evaluates impacts in light of
these changes to confirm its findings that the costs are economically achievable.
EPA-821-R-19-012
1-4

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
1: Introduction
1.2.4 Analyses in Support of the Regula tory Options and Report Organiza tion
This document discusses the following analyses the EPA performed in support of the regulatory options
as compared to the baseline:
•	Overview of the steam electric industry (Chapter 2), which focuses on changes to the industry
since the 2015 rule.
•	Compliance cost assessment (Chapter 3), which describes the cost components and calculates
the industry-wide compliance costs for the baseline and regulatory options and estimates the
incremental costs attributable to the regulatory options.
•	Cost and economic impact screening analyses (Chapter 4), which evaluates the incremental
impacts of compliance on plants and their owning entities on a cost-to-revenue basis.
•	Assessment of impacts in the context of national electricity markets (Chapter 5), which
analyzes the impacts of the regulatory options using the Integrated Planning Model (IPM) and
provides insight into the incremental effects of the regulatory options on the steam electric power
generating industry and on national electricity markets, relative to the baseline.
•	Analysis of employment effects (Chapter 6), which assesses national-level changes in
employment in the steam electric industry, relative to the baseline.
•	Assessment of potential electricity price effects (Chapter 7), which looks at the incremental
impacts of compliance in terms of increased electricity prices for households and for other
consumers of electricity.
•	Regulatory Flexibility Act (RFA) analysis (Chapter 8) which assesses the change in impact of
the rule on small entities on the basis of a revenue test, i.e., cost-to-revenue comparison.
•	Unfunded Mandates Reform Act (UMRA) analysis (Chapter 9) which assesses the change in
impact on government entities, in terms of (1) compliance costs to government-owned plants and
(2) administrative costs to governments implementing the rule. The UMRA analysis also
compares the impacts to small governments with those of large governments and small private
entities.
•	Analyses to address other administrative requirements (Chapter 10), such as Executive Order
13211, which requires the EPA to determine if this action would have a significant effect on
energy supply, distribution, or use.
These analyses generally follow the same methodology used by the EPA for the analysis of the 2015 rule
and the discussion follows a presentation very similar to that in the RIA document for the 2015
rulemaking (U.S. EPA, 2015b).
Chapter 11 provides detailed information on sources cited in the text and three appendices provide
supporting information:
EPA-821-R-19-012
1-5

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
1: Introduction
•	Appendix A: Summary of Changes to Costs and Economic Impact Analysis lists the principal
changes the EPA made to its costs and economic impact analysis for the regulatory options,
relative to the methodology used to analyze the 2015 rule.
•	Appendix B: Cost Effectiveness describes the EPA's analysis of the cost-effectiveness of the
regulatory options.
EPA-821-R-19-012
1-6

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
2: Industry Overview
2 Overview of the Steam Electric Industry
This section provides a general description of the steam electric industry, focusing on changes to the
universe of plants and entities that own the plants as compared to the profile used for the 2015 rule (U.S.
EPA, 2015b). It also discusses the regulations applicable to the universe of plants that may be affected by
the regulatory options.
2.1	Steam Electric Industry
The proposed option would revise BAT limitations and pretreatment standards for bottom ash transport
water and FGD wastewater for existing sources in the steam electric industry. The Steam Electric Power
Generating Point Source Category covers "discharges resulting from the operation of a generating unit by
an establishment whose generation of electricity is the predominant source of revenue or principal reason
for operation, and whose generation of electricity results primarily from a process utilizing fossil-type
fuel (coal, oil, or gas), fuel derived from fossil fuel (e.g., petroleum coke, synthesis gas), or nuclear fuel in
conjunction with a thermal cycle employing the steam water system as the thermodynamic medium." (40
CFR 423.10)
The EPA had identified 1,080 steam electric power plants - including plants that operate coal, oil, gas,
and nuclear generating units - and used this universe in its analysis of the 2015 rule (U.S EPA, 2015b).
Review of more recent data revealed that some of the plants the EPA surveyed in 20102 have since retired
their coal steam units, converted to different fuels, or made other changes that affect discharge
characteristics. The Supplemental TDD describes the changes in the steam electric industry population
since the 2015 rule analysis, including retirements, fuel conversions, ash handling conversions,
wastewater treatment updates, and updated information on capacity utilization (U.S. EPA, 2019a).
The EPA adjusted the 2015 universe to remove coal steam plants that would no longer fit the definition of
the Steam Electric Power Generating point source category. As a result of these adjustments, the EPA
estimates that there are 951 plants in the steam electric power generating industry. As presented in Table
2-1 (next page), the 951 steam electric power plants represent approximately 10 percent of the total
number of plants in the power generation sector, but represent approximately 59 percent of the national
total electric generating capacity with 695,729 MW.
Of the estimated 951 steam electric power plants in the universe, only a subset may incur compliance
costs under the proposed option: those coal fired power plants that discharge bottom ash transport water
or FGD wastewater. As presented in Table 2-1, the EPA estimated that 114 plants may incur non-zero
compliance costs under either the baseline or any of the four regulatory options; these plants represent
1.2	percent of the total plants reported by EIA in 2016 and 13.5 percent of the total generating capacity.
2 See Questionnaire for the Steam Electric Power Generating Effluent Guidelines (Steam Electric Survey; U.S. EPA, 2010b)
EPA-821-R-19-012
2-1

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
2: Industry Overview
Table 2-1: Steam Electric Industry Share of Total Electric Power Generation Plants and Capacity
in 2016




Plants with Non-Zero Compliance




Costs for Baseline or Regulatory


Steam Electric Industry13
Optionsc

Total3
Number
% of Total
Number
% of Total
Plants
9,711
951
9.8%
114
1.2%
Capacity (MW)
1,177,183
695,729
59.1%
158,845
13.5%
a.	Data for total electric power generation industry are from the 2016 EIA-860 database (EIA, 2017a) and 2016 EIA-861
database (EIA, 2017b).
b.	Steam electric power plant count and capacity were calculated on a sample-weighted basis.
c.	See Chapter 3 for details on compliance cost estimates.
Source: U.S. EPA Analysis, 2019; EIA, 2017a; EIA, 2017b.
The following sections present information on ownership, physical, geographic and operating
characteristics of steam electric power plants.
2.1.1 Owner Type and Size
Entities that own electric power plants can be divided into seven major ownership categories: investor-
owned utilities, nonutilities, federally-owned utilities, State-owned utilities, municipalities, rural electric
cooperatives, and other political subdivisions. These categories are important because the EPA has to
assess the impact of the proposed option on State, local, and tribal governments in accordance with
UMRA of 1995 (see Chapter 9: Unfunded Mandates Reform Act (UMRA) Analysis).
Table 2-2 reports the number of parent entities, plants, and capacity by ownership type for the 951 steam
electric power plants (for details on determination of parent entities for steam electric power plants, see
Chapter 4: Cost and Economic Impact Screening Analyses). The majority of steam electric power plants
(54 percent of all steam electric power plants) are owned by investor-owned utilities, while nonutilities
make up the second largest category (21 percent of all steam electric power plants). In terms of steam
electric capacity, investor-owned utilities account for the largest share (67 percent) of total steam electric
capacity.
Table 2-2: Existing Steam Electric Power Plants, Their Parent Entities, and Capacity by
Ownership Type, 2016

Parent Entitiesa bc
Plantsabd
Capacity (MW)a d

Lower Bound
Upper Bound



% of
Ownership Type
Number
% of Total
Number
% of Total
Numberc
% of Total
Numberc
Total
Cooperative
28
11.5%
50
10.5%
64
6.7%
38,416
5.5%
Federal
1
0.4%
3
0.7%
20
2.1%
27,022
3.9%
Investor-owned
69
28.4%
157
32.8%
509
53.5%
465,410
66.9%
Municipality
59
24.3%
94
19.8%
123
12.9%
45,934
6.6%
Nonutility
74
30.5%
150
31.4%
198
20.8%
87,639
12.6%
Other Political
Subdivisions
10
4.1%
21
4.5%
34
3.5%
26,525
3.8%
State
2
0.8%
2
0.4%
4
0.4%
4,784
0.7%
EPA-821-R-19-012
2-2

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
2: Industry Overview
Table 2-2: Existing Steam Electric Power Plants, Their Parent Entities, and Capacity by
Ownership Type, 2016

Parent Entitiesa bc
Plantsabd
Capacity (MW)a d

Lower Bound
Upper Bound



% of
Ownership Type
Number
% of Total
Number
% of Total
Numberc
% of Total
Numberc
Total
Total
243
100.0%
478
100.0%
951
100.0%
695,729
100.0%
a.	Numbers may not add up to totals due to independent rounding.
b.	Ownership information on steam electric power plants and their parent entities is based on information gathered through
the Steam Electric Survey (U.S. EPA, 2010b) and additional research of publicly available information.
c.	Parent entity counts are calculated on a sample-weighted basis and represent the lower and upper bound estimates of the
number of entities owning steam electric power plants. For details see Chapter 4.
d.	Steam electric power plant count and capacity were calculated on a sample-weighted basis. For details on sample weights,
see Supplemental TDD.
Source: U.S. EPA Analysis, 2019; EIA, 2017a
The EPA estimates that between 27 percent and 33 percent of entities owning steam electric power plants
are small (Table 2-3), according to Small Business Administration (SBA) (2017) business size criteria.
By definition, states and the federal government are considered large entities.
The size distribution of parent entities owning steam electric power plants varies by ownership type.
Under the lower bound estimate, the lowest share of small entities is in the other political subdivision3
category (10 percent), while cooperatives and small municipalities make up the largest share of small
entities (75 percent and 49 percent, respectively). The pattern is similar under the upper bound estimate,
but small entities representing 5 percent of other political subdivision entities, 72 percent of cooperatives,
and 39 percent of municipalities.
The EPA estimates that out of 951 steam electric power plants, 139 (15 percent) are owned by small
entities (Table 2-4). Cooperatives own the largest share (30 percent) of steam electric power plants owned
by small entities, while investor-owned utilities, nonutilities, municipalities, and other political
subdivisions own the remaining 70 percent. For a detailed discussion of the identification and size
determination of parent entities of steam electric power plants, see Chapter 4 and Chapter 8.
Table 2-3: Parent Entities of Steam Electric Power Plants by Ownership Type and Size (assuming
two different ownership cases)a b
Lower bound estimate of number of entities
owning steam electric power plants
Ownership Type
Small
Large
Total
% Small
Small
Large
Total
% Small
Cooperative
21
7
28
75.0%
36
14
50
72.2%
Federal
0
1
1
0.0%
0
3
3
0.0%
Investor-owned
9
60
69
13.0%
20
136
157
13.0%
Municipality
29
30
59
49.2%
37
57
94
39.1%
Nonutility
19
55
74
25.7%
33
117
150
22.0%
Other Political
Subdivision
1
9
10
10.0%
1
20
21
4.7%
Upper bound estimate of number of entities
owning steam electric power plants
Other political subdivisions include public power districts and irrigation projects.
EPA-821-R-19-012
2-3

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
2: Industry Overview
Table 2-3: Parent Entities of Steam Electric Power Plants by Ownership Type and Size (assuming
two different ownership cases)a b
Lower bound estimate of number of entities
owning steam electric power plants
Ownership Type
Small
Large
Total
% Small
Small
Large
Total
% Small
State
0
2
2
0.0%
0
2
2
0.0%
Total
79
164
243
32.5%
127
350
478
26.6%
Upper bound estimate of number of entities
owning steam electric power plants
a.	Numbers may not add up to totals due to independent rounding.
b.	For details on estimates of the number of majority owners of steam electric power plants see Chapter 4 and Chapter 8.
Source: U.S. EPA Analysis, 2019
Table 2-4: Steam Electric Power Plants by Ownership Type and Size

Number of Steam Electric Power Plantsa b c
Ownership Type
Small
Large
Total
% Small
Cooperative
41
23
64
64.2%
Federal
0
20
20
0.0%
Investor-owned
22
487
509
4.4%
Municipality
37
86
123
30.1%
Nonutility
38
160
198
19.2%
Other Political Subdivisions
1
33
34
3.0%
State
0
4
4
0.0%
Total
139
811
951
14.7%
a.	Numbers may not sum to totals due to independent rounding.
b.	Plant counts are sample-weighted estimates.
c.	Plant size was determined based on the size of majority owners. In case of multiple owners with equal
ownership shares, a plant was assumed to be small if it is owned by at least one small entity.
Source: U.S. EPA Analysis, 2019
2.1.2 Geographic Distribution of Steam Electric Power Plants
The U.S. bulk power system is composed of three major networks, or power grids, subdivided into
several smaller North American Electric Reliability Corporation (NERC) regions:
•	The Eastern Interconnected System covers the largest portion of the United States, from the
eastern end of the Rocky Mountains and the northern borders to the Gulf of Mexico states
(including parts of northern Texas) on to the Atlantic seaboard.
•	The Western Interconnected System covers nearly all of areas west of the Rocky Mountains,
including the Southwest.
•	The Texas Interconnected System, the smallest of the three major networks, covers the majority of
Texas.
The Texas system is not connected with the other two systems, while the other two have limited
interconnection to each other. The Eastern and Western systems are integrated with, or have links to, the
Canadian grid system. The Western and Texas systems have links with Mexico.
EPA-821-R-19-012
2-4

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
2: Industry Overview
These major networks contain extra-high voltage connections that allow for power transmission from one
part of the network to another. Wholesale transactions can take place within these networks to reduce
power costs, increase supply options, and ensure system reliability.
NERC is responsible for the overall reliability, planning, and coordination of the power grids. An
independent, not-for-profit organization, it has regulatory authority for ensuring electric reliability in the
United States, under the oversight of FERC. NERC is organized into seven regional entities that cover the
48 contiguous States, and two affiliated councils that cover Hawaii, part of Alaska, and portions of
Canada and Mexico.4 These regional organizations are responsible for the overall coordination of bulk
power policies that affect their regions" reliability and quality of service. Interconnection between the
bulk power networks is limited in comparison to the degree of interconnection within the major bulk
power systems. Further, the degree of interconnection between NERC regions even within the same bulk
power network is also limited. Consequently, each NERC region deals with electricity reliability issues in
its own region, based on available capacity and transmission constraints. The regional organizations also
facilitate the exchange of information among member utilities in each region and between regions.
Service areas of the member utilities determine the boundaries of the NERC regions. Though limited by
the larger bulk power grids described above, NERC regions do not necessarily follow any State
boundaries. Figure 2-1 provides a map of the NERC regions EPA used for the analysis of the regulatory
options, listed in Table 2-5. The map uses the same regional breakout used for the 2015 rule analysis,
which was based on the 2012 EIA data and separates out the Southwest Power Pool (SPP) region.5
Table 2-5: NERC regions
Bulk Power Network
NERC Region
NERC Entity

FRCC
Florida Reliability Coordinating Council

MRO
Midwest Reliability Organization
Eastern Interconnected System
NPCC
Northeast Power Coordinating Council (U.S.)
RFC
Reliability First Corporation

SERC
SERC Reliability Corporation

SPP
Southwest Power Pool
Western Interconnected System
WECC
Western Energy Electricity Coordinating Council (U.S.)
Texas Interconnected System
TRE
Texas Regional Reliability Entity

ASCC
Alaska Systems Coordinating Council

HICC
Hawaii Coordinating Council
Source: EIA, 2012
Energy concerns in the States of Alaska, Hawaii, the Dominion of Puerto Rico, and the Territories of American Samoa,
Guam, and the Virgin Islands are not under reliability oversight by NERC.
Some NERC regions have been re-defined/re-named over time. This chapter provides NERC region data by the 2012
NERC regions.
EPA-821-R-19-012
2-5

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
2: Industry Overview
Figure 2-1: North American Electric Reliability Corporation (NERC) Regions
NPCC
MRO i
'RFC
!cc
SPP
SERC
TRE
FRCC
Note: The ASCC and HICC regions are not shown.
Source: EIA, 2012.
The evaluated options are estimated to have a different effect on profitability, electricity prices, and other
impact measures across NERC regions. This is because of variations in the economic and operational
characteristics of steam electric and other power plants across NERC regions, including the share of the
region's electricity demand met by steam electnc power plants that may incur compliance costs under the
different options. Other factors include the baseline economic characteristics of the NERC regions,
together with market segmentation due to limited interconnectedness among NERC regions. To assess the
potential reliability impact of the regulatory options, the EPA assessed the distribution of steam electric
power plants and their capacity across NERC regions.
As reported in Table 2-6, NERC regions differ in terms of both the number of steam electric power plants
and their capacity. Steam electric power plants are somewhat concentrated in the RFC, SERC, and WECC
regions (21 percent, 20 percent, and 17 percent, respectively); these three regions also account for a
majority of the steam electric capacity in the United States (24 percent, 26 percent, and 15 percent,
respectively).
Tabie 2-6: Steam Electric Power Plants and Capacity by NERC Region, 2012ab

Plants
Capacity (MW)" b
NERC Region
Number
% of Total
MW
% of Total
ASCC
2
0.2%
118
0.0%
FRCC
50
5.2%
53,448
7.7%
HICC
10
1.0%
750
0.1%
MRO
77
8.1%
33,921
4.9%
EPA-821-R-19-012
2-6

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
2: Industry Overview
Table 2-6: Steam Electric Power Plants and Capacity by NERC Region, 2012a b

Plants
Capacity (MW)a b
NERC Region
Number
% of Total
MW
% of Total
NPCC
90
9.4%
35,025
5.0%
RFC
199
21.0%
163,646
23.5%
SERC
194
20.4%
181,545
26.1%
SPP
88
9.3%
60,524
8.7%
TRE
78
8.2%
61,792
8.9%
WECC
163
17.2%
104,962
15.1%
TOTAL
951
100.0%
695,729
100.0%
a. Numbers may not add up to totals due to independent rounding.
b. The numbers of plants and capacity are calculated on a sample-weighted basis.
Source: U.S. EPA Analysis, 2019; EIA, 2017a
2.1.3 Electricity Genera tion
Total net electricity generation in the United States for 2016 was 4,079 TWh.6 Coal accounted for 30
percent of total electricity generation, behind natural gas (34 percent), but ahead of nuclear power (20
percent). Other energy sources accounted for comparatively smaller shares of total generation, with
hydropower representing 7 percent; wind, solar and other renewable energy, 8 percent; and petroleum,
1 percent.
As presented in Table 2-7, the 5-year period of 2012 through 2016 saw total net generation increase by
approximately 0.8 percent, with the 274 TWh drop in generation from coal-fueled generators (18 percent)
offset by growth in generation from natural gas (154 TWh, 12.5 percent increase) and renewables (126
TWh, a 57 percent increase).
Between 2012 and 2016, the amount of electricity generated by utilities declined by 1.5 percent while that
generated by nonutilities rose by 3.9 percent. Comparing 2012 and 2016 values, across all fuel-source
categories, utilities generated a larger share of their electricity using natural gas (a 30 percent increase)
and renewables (a 53 percent increase) even as their overall generation declined. For nonutilities, the
largest percent increase in electricity generation (58 percent) occurred for renewables, whereas generation
from natural gas remained largely the same.
Table 2-7: Net Generation by Energy Source and Ownership Type, 2012-2016 (TWh)

Utilities
Nonutilities
Total
Energy Source
2012
2016
%
Change
2012
2016
%
Change
2012
2016
% Change
Coal
1,146
923
-19.5%
368
317
-13.8%
1,514
1,240
-18.1%
Hydropower
249
241
-3.1%
23
18
-19.7%
271
259
-4.5%
Nuclear
395
424
7.5%
375
381
1.7%
769
805
4.7%
Petroleum
16
18
12.8%
8
6
-16.8%
23
24
3.1%
Natural Gas
505
654
29.6%
721
726
0.7%
1,226
1,380
12.6%
Other Gases
0
0
NA
12
13
7.9%
12
13
9.3%
Renewables3
28
43
53.0%
190
301
58.0%
218
344
57.4%
One terawatt-hour is 1012 watt-hours.
EPA-821-R-19-012
2-7

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
2: Industry Overview
Table 2-7: Net Generation by Energy Source and Ownership Type, 2012-2016 (TWh)

Utilities
Nonutilities
Total
Energy Source
2012
2016
%
Change
2012
2016
%
Change
2012
2016
% Change
Other"
1
0
-48.3%
13
13
1.4%
14
14
-0.8%
Total
2,339
2,304
-1.5%
1,709
1,775
3.9%
4,048
4,079
0.8%
a.	Renewables include wood, black liquor, other wood waste, municipal solid waste, landfill gas, sludge waste, agriculture
byproducts, other biomass, geothermal, solar thermal, photovoltaic energy, and wind.
b.	Other includes batteries, hydrogen, purchased steam, sulfur, tire-derived fuels and other miscellaneous energy sources.
Source: EIA, 2017c
2.2 Other Environmental Regulations
The RIA report for the 2015 rule described factors, such as deregulation and environmental regulations
and programs, that have affected the steam electric power generating industry, and electrical power
generation more generally, over the last decades. See Chapter 2 in U.S. EPA (2015b). The sections below
provide updated discussions on changes to two environmental regulations since 2015.
2.2.1 Clean Power Plan (CPP) and Affordable Clean Energy (ACE) Regulations
The final 2015 CPP established carbon dioxide (CO2) emission guidelines for fossil-fuel fired power
plants based in part on shifting generation at the fleet-wide level from one type of energy source to
another. On February 9, 2016, the U.S. Supreme Court stayed implementation of the CPP pending
judicial review. West Virginia v. EPA, No. 15A773 (S.Ct. Feb. 9, 2016).
On June 19, 2019, the EPA issued the ACE rule, an effort to provide existing coal-fired electric utility
generating units (EGUs) with achievable and realistic standards for reducing greenhouse gas emissions.
This action was finalized in conjunction with two related, but separate and distinct rulemakings: (1) the
repeal of the CPP, and (2) revised implementing regulations for ACE, ongoing emission guidelines, and
all future emission guidelines for existing sources issued under the authority of Clean Air Act section
111(d). ACE provides states with new emission guidelines that will inform the state's development of
standards of performance to reduce CO2 emissions from existing coal-fired EGUs consistent with the
EPA's role as defined in the CAA.
ACE establishes heat rate improvement (HRI), or efficiency improvement, as the best system of
emissions reduction (BSER) for CO2 from coal-fired EGUs. By employing abroad range of HRI
technologies and techniques, EGUs can more efficiently generate electricity with less carbon intensity.
The BSER is the best technology or other measure that has been adequately demonstrated to improve
emissions performance for a specific industry or process (a "source category"). In determining the BSER,
the EPA considers technical feasibility, cost, non-air quality health and environmental impacts, and
energy requirements. The BSER must be applicable to, at, and on the premises of an affected facility.
ACE lists six HRI "candidate technologies," as well as additional operating and maintenance (O&M)
practices. For each candidate technology, the EPA has provided information regarding the degree of
emission limitation achievable through application of the BSER as ranges of expected improvement and
costs.
The 2015 rule analyses incorporated compliance costs associated with the 2015 CPP, resulting in, among
other things, baseline retirements associated with that rule in the Integrated Planning Model (IPM). Due
EPA-821-R-19-012
2-8

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
2: Industry Overview
to the final repeal of the CPP, the analyses supporting today's proposal no longer incorporates the 2015
CPP. However, the EPA does make use of IPM version 6 to be consistent with the base case analyses
done for the ACE final rule (U.S. EPA, 2019d). See additional discussion of IPM in Chapter 5:
Assessment of the Impact of the Regulatory Options in the Context of National Electricity Markets. The
EPA intends to perform IPM runs with the most up-to-date version of the model available for the final
rule.
2.2.2 Coal Combustion Residuals Rule
On April 17, 2015, the Agency published the Disposal of Coal Combustion Residuals from Electric
Utilities final rule. This rule finalized national regulations to provide a comprehensive set of requirements
for the safe disposal of CCRs, commonly known as coal ash, from coal-fired power plants. The final CCR
rule was the culmination of extensive study on the effects of coal ash on the environment and public
health. The rule established technical requirements for CCR landfills and surface impoundments under
subtitle D of the Resource Conservation and Recovery Act (RCRA), the nation's primary law for
regulating solid waste.
These regulations addressed coal ash disposal, including regulations designed to prevent leaking of
contaminants into ground water, blowing of contaminants into the air as dust, and the catastrophic failure
of coal ash surface impoundments. Additionally, the CCR rule set out recordkeeping and reporting
requirements as well as the requirement for each facility to establish and post specific information to a
publicly-accessible website. This final CCR rule also supported the responsible recycling of CCRs by
distinguishing safe, beneficial use from disposal.
As explained in the 2015 rule, the ELGs and CCR rules may affect the same unit or activity at a power
plant. As such, in finalizing both of those rules in 2015, the EPA coordinated the two rules to minimize
the overall complexity and to facilitate implementation of engineering, financial, and permitting activities.
The coordination of the two rules continues to be a consideration in the development of today's proposal.
The EPA's analysis of this proposal incorporates the same approach used in the 2015 rule to estimate how
the CCR rule may affect surface impoundments and the ash handling systems and FGD treatment systems
that send wastes to those impoundments. However, as a result of the DC Circuit Court rulings in USWAG
v. EPA, No. 15-1219 (DC Cir. 2018) and Waterkeeper Alliance Inc, et al v. EPA, No. 18-1289 (DC Cir.
2019), amendments to the CCR rule are being proposed which would establish a deadline of July 2020 by
which all unlined surface impoundments must cease receiving waste subject to certain exceptions.
See the Supplemental TDD for details on how the EPA accounted for the CCR rule effects as part of the
baseline for this analysis (U.S. EPA, 2019a).
2.3 Market Conditions and Trends in the Electric Power Industry
The 18 percent decline in coal-fueled electricity generation summarized in Table 2-7 for the period of
2012 through 2016 exemplifies an ongoing trend over the last decade: the progressive reduction in
generation capacity as coal units and plants retire. In 2018, EIA reported that nearly all of the utility-scale
power plants in the United States that were retired from 2008 through 2017 were fueled by fossil fuels,
with coal power plants accounting for 47 percent of the total retired capacity (EIA, 2018b). Capacity
additions in that same year primarily consisted of natural gas (62 percent), wind (21 percent), and solar
photovoltaic (16 percent) capacity (EIA, 2019). Multiple factors contribute to this trend.
EPA-821-R-19-012
2-9

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
2: Industry Overview
One factor in the decline in the coal-fueled power generation is the aging fleet of coal-fired power plants.
The life expectancy of coal plants is approximately 40 to 50 years, and almost all plants that retired in
2015 were more than 40 years old (Kolstad, 2017). Mills et al. (2017) also found that coal plants that
retired between 2010 and 2016 had an average age of 52 years, and plants with stated plans to retire were
not any younger on average. Coal plant retirements due to aging are likely to continue in the near future,
as the capacity-weighted average age of coal plants in operation as of 2017 is 39 years (EIA, 2017d).
The lower costs of natural gas, as well as technological advances in solar and wind power have also been
important market factors. Fell and Kaffine (2018) found negative impacts on coal-fired generation from
both lower natural gas prices and increased wind generation, with declining natural gas prices having a
stronger effect. Knittel et al. (2015) found that utilities invested more in natural gas capacity when the
prices dropped as a result of the boom in shale gas production, although the magnitude of their
investments differed depending on the structure of the electricity market in which they operated.
Changes in electricity generation have had impacts in fuel markets. Coal consumption in the electric
power industry has declined by about 40 percent between 2005 and 2017, whereas natural gas
consumption has increased by about 24 percent in the same time period, resulting in natural gas
consumption doubling coal consumption in 2017 (EIA, 2018c). Market conditions have also negatively
affected nuclear-powered generation, though this proposed rule has no effect on the nuclear-powered
sector, except as it affects relative prices through its impacts on coal-fired generation (Scott, 2018).
The decline in coal is not independent of environmental regulations affecting coal-fired electricity
generation, as power companies have cited regulations promulgated, particularly in the last decade, as
reasons for their decision when announcing unit or plant closures, fuel switching, or other operational
changes. However, fuel prices and trends toward alternative fuels also appear to be drivers in the shift
away from coal for electricity generation. Coglianese et al. (2018) found that the decrease in natural gas
prices accounted for 92 percent of the decline in coal production while environmental regulations
accounted for 6 percent. Linn and McCormack (2017) found that while air emissions regulations were
responsible for most reductions in nitrogen oxides from the electricity sector, they had only a small effect
on profitability and retirement at coal plants.
As the electric power infrastructure adjusts to market trends by moving toward optimal infrastructure and
operations to deliver the country's electricity, the EPA recognizes that the changes can have negative
effects for some communities and positive effects for others.
EPA-821-R-19-012
2-10

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
3: Compliance Costs
3 Compliance Costs
In developing the proposed rule, the EPA assessed the costs and economic impacts of each of the four
regulatory options described in Table 1-1. Key inputs for these analyses include the estimated costs to
steam electric power plants (and their business, government, or non-profit owners) for implementing
control technologies upon which the proposed BAT limitations and pretreatment standards are based,7
and to the state and federal government for administering this rule. This chapter summarizes the EPA
estimates of the incremental compliance costs attributable to the proposal, based on a comparison of
steam electric industry compliance costs for the baseline and four regulatory options.8 The EPA
determined that state and federal governments would not incur incremental administrative costs.9
The EPA applied the same methodology used to analyze the 2015 rule to calculate industry-level
annualized compliance costs. See Chapter 3 of the RIA for the 2015 rule for details (U.S. EPA, 2015b).
The Supplemental TDD describes the control technologies and their respective wastewater treatment
performance in greater detail (U.S. EPA, 2019a). The Supplemental TDD also describes how the EPA
estimated plant-specific capital and operation and maintenance (O&M) costs for meeting the BAT
limitations and pretreatment standards specified under each of the four regulatory options.
3.1 Analysis Approach and Inputs
The EPA estimated costs to plants for meeting the limitations of the regulatory options. There are four
principal steps to compliance cost development, the last two of which are the focus of the discussion
below:
1.	Determining the set of plants potentially implementing compliance technologies for each
regulatory option. See Supplemental TDD for details.
2.	Developing plant-level costs for each wastestream and regulatory option. See Supplemental TDD
for details.
3.	Estimating the year when each steam electric power plant would be required to meet new BAT
effluent limits and pretreatment standards. This schedule supports analysis of the timing of
compliance costs and benefits for analyses discussed in this document and in the BCA.
4.	Estimating total industry costs for all plants in the steam electric universe for each of the
regulatory options.
An additional step involves comparing the total industry costs from Step 4 to total industry costs similarly
obtained for the baseline to estimate the incremental costs attributable to each regulatory option.
Dischargers are not required to use the technologies specified as the basis for the rule. They are free to identify other
perhaps less expensive technologies as long as they meet the BAT limitations and pretreatment standards in the rule.
The regulatory options would apply only to existing sources, with new sources continuing to be subject to the New
Source Performance Standards (NSPS) and Pretreatment Standards for New Sources (PSNS) promulgated in the 2015
rule.
As discussed in Section 10.8: Paperwork Reduction Act of1995, the EPA estimates that the regulatory options would
not impose additional administrative cost to the State and federal governments.
EPA-821-R-19-012
3-1

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
3: Compliance Costs
The EPA reports costs in 2018 dollars and, because the revised ELGs would be effective at a future date,
generally discounted costs to 2020, which is the anticipated rule promulgation year.10
3.1.1	Plant-Specific Costs Approach
As detailed in the Supplemental TDD, the EPA developed costs for steam electric power plants to
implement treatment technologies or process changes to control the wastestreams addressed by the
regulatory options (i.e.. bottom ash transport water and FGD wastewater).
The EPA assessed the operations and treatment system components currently in place at a given unit (or
required to be in place to comply with other existing environmental regulations), identified equipment and
process changes that plants would likely make to meet the 2015 rule (for baseline) and each of the four
regulatory options presented in Table 1-1, and estimated the cost to implement those changes. Because
the 2015 rule11 is the baseline for analysis but is not yet effective for the two wastestreams addressed in
the proposal, the EPA first developed costs to meet the 2015 rule based on current plant equipment,
processes, and treatment technologies. The EPA then developed similar costs for the regulatory options
presented in this proposal. The difference between the baseline and regulatory option cost estimates
reflect the incremental costs attributable to the regulatory options. Plants that do not generate a
wastewater or that employ technologies which would already meet the given limitations or standards do
not incur costs. For several regulatory options, including the proposed option, the costs of meeting the
proposed BAT imitations or pretreatment standards are less than those estimated for meeting the 2015
rule, and the options therefore result in cost savings to the industry as compared to the baseline.
3.1.2	Plant-Level Costs
Following the approach used for the analysis of the 2015 rule (U.S. EPA, 2015b), the EPA estimated
compliance costs for all existing steam electric power plants, estimated to be a total 951 plants for the
point source category overall. The EPA assessed that only a fraction of the universe of steam electric
power plants - 479 plants - have the potential to incur any costs under the regulatory options based on
their wastestreams. Furthermore, out of these plants, only a subset would incur non-zero costs under any
of the scenarios analyzed for the regulatory options, based on existing control technologies: 114 plants
under the baseline and 108 plants under the four regulatory options. The Supplemental TDD provides
additional details on this analysis.
The major components of technology costs are:
• Capital costs include the cost of compliance technology equipment, installation, site preparation,
construction, and other upfront, non-annually recurring outlays associated with compliance with
the regulatory options. The EPA assumes that plants incur all capital costs in the year when their
permit is renewed to incorporate the new limitations or standards (see Technology
Implementation Years below). As explained in the 2015 TDD and Supplemental TDD, all
compliance technologies are assumed to have a useful life of 20 years.
In its analysis of the 2015 rule, the EPA presented costs in 2013 dollars and discounted these compliance costs to 2015
(see U.S. EPA, 2015b).
This includes the September 2017 postponement rule which delayed the earliest compliance date for the ELGs
applicable to FGD wastewater and bottom ash transport water.
EPA-821-R-19-012
3-2

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
3: Compliance Costs
•	Initial one-time costs (apart from capital costs, above), if applicable, consist of a one-time cost to
make the bottom ash system closed loop to eliminate discharges of bottom ash transport water
(e.g., under the baseline) or a one-time cost to develop a Best Management Practice (BMP) plan
to recycle bottom ash transport water (e.g., under Option 2). Steam electric power plants are
estimated to incur these costs only once during their technology implementation year.
•	Annual fixed O&M costs, if applicable, include regular annual monitoring. Plants incur these
costs each year.
•	Annual variable O&M costs, if applicable, include annual operating labor, maintenance labor and
materials, electricity required to operate wastewater treatment systems, chemicals, combustion
residual waste transport and disposal operation and maintenance, and savings from not operating
and maintaining ash/FGD pond systems. Plants incur these costs each year.
In addition to these initial one-time and annual outlays, certain other costs are estimated to be incurred on
a non-annual, periodic basis:
•	3-Yr fixed O&M costs, if applicable, include mechanical drag system (MDS) chain replacement
costs that plants are estimated to incur every three years, beginning three years after the
technology implementation year.
•	5-Yr fixed O&M costs, if applicable, include remote MDS chain replacement costs that plants are
estimated to incur every five years, beginning five years after the technology implementation
year.
•	6-Yr fixed O&M costs, if applicable, include mercury analyzer operating and maintenance costs
that plants are estimated to incur every six years, beginning in the technology implementation
year.
•	10-Yr fixed O&M costs, if applicable, include savings from not needing to periodically maintain
ash/FGD pond systems. Plants are estimated to incur savings every 10 years from not needing to
purchase earthmoving equipment for the pond systems, beginning 5 years after the technology
implementation year.
Based on information in the record concerning the normal downtime of electricity generating units, the
EPA estimated that plants would be able to coordinate the plants' implementation of wastewater treatment
systems during already scheduled downtime.
3.1.3 Technology Implementation Years
The years in which individual steam electric power plants are estimated to implement control
technologies are an important input to the time profile of costs that plants would incur due to the
regulatory options. This profile is used to estimate the change in the annualized costs to the steam electric
industry and society associated with the regulatory options in this proposal as compared to the baseline.
The EPA envisions that each plant to which the regulatory options would apply would study available
technologies and operational measures, and subsequently install, incorporate, and optimize the technology
most appropriate for each site. As part of its consideration of the technological availability and economic
EPA-821-R-19-012
3-3

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
3: Compliance Costs
achievability of the BAT limitations and pretreatment standards in the rule and following the approach the
Agency used for the 2015 rule, the EPA considered the magnitude and complexity of process changes and
new equipment installations that would be required at plants to meet the requirements of the regulatory
options in determining the time plant owners may need to comply with any revised limitations or
pretreatment standards. See discussion in the Supplemental TDD (U.S. EPA, 2019a).
As described in greater detail in the proposal, the EPA is proposing a deadline for meeting the BAT
limitations and pretreatment standards associated with the four regulatory options that differs across the
options, wastestreams, and whether a plant participates in the Voluntary Incentive Program (VIP). Table
3-1 summarizes the relevant deadlines for each regulatory option, based on the wastestream and plant
category.
Table 3-1: Compliance Deadlines for the Baseline and Regulatory Options
Wastestream
Plant Subset
Compliance "No Later Than" Deadline
(Technology Basis)
Baseline
Option 1
Option 2
Option 3
Option 4
Bottom Ash
Transport
Water
All3 plants unless
otherwise qualified
2023
2023
2023
2023
2023
FGD
Wastewater
All3 plants unless
otherwise qualified
2023
(CP +
Biological)
2023
(CP)
2025
(CP + LRTR)
2025
(CP + LRTR)
2028
(Membranes)
Unit-level net
generation
<876,000 MWh
Not applicable
Not applicable
2023
(CP)
Not applicable
Not applicable
Plant-level FGD
scrubber purge
flow > 4 MGD
2023
(CP)
2023
(CP)
VIP
2023
(CP +
Evaporation)
2028
(Membranes)
2028
(Membranes)
2028
(Membranes)
Not applicable
End of Life Boiler
2028
2028
2028
2028
2028
a. For units with nameplate capacity greater than 50 MW
CP = Chemical precipitation; LRTR = Low Hydraulic Residence Time.
The timing decision represents when the technologies are available, accounting for the need to provide
sufficient time for plant owners to raise capital, plan and design systems, procure equipment, and
construct and then test systems, recognizing that some plant owners have already met or taken steps to
meet the ELGs the EPA finalized in 2015. Moreover, specifying compliance deadlines in the future
enables plants to take advantage of planned shutdown or maintenance periods to install new pollution
control technologies. This allows for the coordination of generating unit outages in order to maintain grid
reliability and prevent any potential impacts on electricity availability caused by forced outages. It is not
possible to predict, for each plant, exactly what date any new ELGs would be incorporated into permits,
for purposes of determining exactly when plants would incur costs to meet any new requirements. Similar
to the approach used in analyzing the 2015 rule, the EPA generally expects plants to meet the new BAT
limitations and pretreatment standards in a somewhat staggered fashion, given that (1) for some
EPA-821-R-19-012
3-4

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
3: Compliance Costs
regulatory options, the permitting authority determines the date after considering certain specified factors,
and (2) all permits are not re-issued at the same time due to their 5-year permit term. Thus, for the cost
and economic impact analyses, the EPA assumed implementation over a 3- to 5-year period preceding
any proposed "no later than" date.12
3.1.4 Total Compliance Costs
The EPA used the following methodology and assumptions to aggregate compliance cost components,
described in the preceding sections, and develop total plant compliance costs for each regulatory option:
•	The EPA estimated compliance costs (including zero costs) for each of the 479 steam electric
power plants with the relevant wastestreams, i.e., coal-fired power plants (see Supplemental TDD
for details). All other plants covered by the steam electric power point source category would
incur zero costs.
•	The EPA restated compliance costs estimated in the preceding step, accounting for the specific
years in which each plant is assumed to undertake compliance-related activities and in 2018
dollars, using the Construction Cost Index (CCI) from McGraw Hill Construction (2017), the
Employment Cost Index (ECI) published by the Bureau of Labor Statistics (BLS) (2018), and the
Gross Domestic Product (GDP) deflator index published by the U.S. Bureau of Economic
Analysis (BEA) (2018).13
•	The EPA discounted all cost values to 2020, using a rate of 7 percent.14
•	The EPA annualized one-time costs and costs recurring on other than an annual basis over a
specific useful life, implementation, and/or event recurrence period, using a rate of 7 percent:14
For the purpose of the analysis, the EPA assigned an estimated compliance year to each of the 479 steam electric power
plants analyzed for this proposal based on each plant's estimated NPDES permit renewal year. The EPA projected
future NPDES permit years by assuming permits are renewed every 5 years, i.e., a permit expiring in 2020 would be
renewed in 2025 and 2030.
Specifically, the EPA brought all compliance costs to an estimated technology implementation year using the CCI from
McGraw Hill Construction (2017) or the ECI from the Bureau of Labor Statistics (2018), depending on the cost
component. The Agency used the average of the year-to-year changes in the CCI (or ECI) over the most recent ten-year
reporting period to bring these values to an estimated compliance year. Because the CCI (or ECI) is a nominal cost
adjustment index, the resulting technology cost values are as of the compliance year and in the dollars of the
technology implementation year. To restate compliance cost values in 2018 dollars, the Agency deflated the nominal
dollar values to 2018 using the average of the year-to-year changes in the GDP deflator index published by the BEA
over the most recent ten-year reporting period. As a result, all dollar values reported in this analysis are in constant
dollars of the year 2018.
The rate of 7 percent is used in the cost impact analysis as an estimate of the private opportunity cost of capital. For the
social cost analysis presented in Chapter 12 of the BCA document, the EPA uses both 3 percent and 7 percent discount
rates. The 3 percent discount rate reflects society's valuation of differences in the timing of consumption; the 7 percent
discount rate reflects the opportunity cost of capital to society. In Circular A-4, the Office of Management and Budget
(OMB) recommends that 3 percent be used when a regulation affects private consumption, and 7 percent in evaluating
a regulation that will mainly displace or alter the use of capital in the private sector (U.S. OMB, 2003; updated 2009).
The same discount rates are used for both benefits and costs in the BCA document.
EPA-821-R-19-012
3-5

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
3: Compliance Costs
-	Capital costs of each compliance technology: 20 years
-	Initial one-time costs: 20 years15
-	3-Yr O&M: 3 years
-	5-Yr O&M: 5 years
-	6-Yr O&M: 6 years
-	10-Yr O&M: 10 years
• The EPA added annualized capital, initial one-time costs, and annualized O&M costs recurring
on other than an annual basis to the annual O&M costs to derive total annualized compliance
costs.
For the assessment of compliance costs to steam electric power plants, the EPA considered costs on both
a pre-tax and after-tax basis. Pre-tax costs provide insight on the total expenditures as initially incurred by
the plants. After-tax costs are a more meaningful measure of compliance impact on privately owned for-
profit plants, and incorporate approximate capital depreciation and other relevant tax treatments in the
analysis. The EPA calculated the after-tax value of compliance costs by applying combined federal and
State tax rates to the pre-tax cost values for privately owned for-profit plants.16 For this adjustment, the
EPA used State corporate rates from the Federation of Tax Administrators (2018) combined with a 21
percent federal corporate tax rate.17 As discussed in the relevant sections of this document, the EPA uses
either pre- or after-tax compliance costs in different analyses, depending on the concept appropriate to
each analysis (e.g., cost-to-revenue screening-level analyses are conducted using after-tax compliance
costs). Note that for social costs, which are discussed and detailed in Chapter 12 of the BCA document,
the EPA uses pre-tax costs.18
3.1.5 Voluntary Incentive Program
As described in the proposal, under the VIP component of regulatory options 1, 2, and 3, plants can
voluntarily commit to meeting more stringent FGD limitations based on the membrane treatment
technology instead of limits based on CP or CP+LRTR technology. VIP participants would have more
time - until 2028 - to meet the lower limits based on membranes, as compared to having to meet the
limits based on CP in 2023 or CP+LRTR by 2025.
The EPA annualized these non-equipment outlays over 20 years to match the estimated performance life of compliance
technology components.
Government-owned entities and cooperatives are not subject to income taxes. To distinguish among the government-
owned, privately owned, and cooperative ownership categories, the EPA relied on the Steam Electric Survey and
additional research on parent entities using publicly available information. See Chapter 4: Economic Impact Screening
Analyses for further discussion of these determinations.
This federal tax rate reflects the Tax Cuts and Jobs Act of 2017 which changed the top corporate tax rate from 35
percent to one flat rate of 21 percent after January 1,2018.
As described in Chapter 12 of the BCA document, the EPA used costs incurred by steam electric power plants for the
labor, equipment, material, and other economic resources needed to comply with the regulatory options as a proxy for
social costs. The social cost analysis considers costs on an as-incurred, year-by-year basis. In the social cost analysis,
the EPA assumed that the market prices for labor, equipment, material, and other compliance resources represent the
opportunity costs to society for use of those resources in regulatory compliance. The EPA further assumed that the
regulatory options do not affect the aggregate quantity of electricity that would be sold to consumers and, thus, that the
rule's social cost would include no changes in consumer and producer surplus from changes in electricity sales by the
electricity industry in aggregate. Given the small impact of the regulatory options on electricity production cost for the
total industry (see Chapter 5), this is a reasonable assumption.
EPA-821-R-19-012
3-6

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
3: Compliance Costs
Because the VIP is voluntary, the set of plants participating in the program is uncertain. For the purpose
of the economic analysis, the EPA estimated VIP participants by comparing the estimated costs of the two
technologies for each affected facility and assuming that a plant owner would select the less costly of the
two. Specifically, the Agency compared the annualized and discounted cost of implementing CP+LRTR
between 2021 and 2025 (based on the plant-specific schedule described in Section 3.1.3) or implementing
membranes in 2028. Based on this analysis, the EPA estimated that 18 plants may choose to participate in
the VIP under Option 2 and 23 plants may choose to participate in the VIP under Option 3.
3.2 Key Findings for Regulatory Options
3.2.1 Estima ted Industry-level Total Compliance Costs
Table 3-2 presents compliance cost estimates for the baseline and each of the four regulatory options.
Table 3-3 summarizes incremental costs for each option as compared to the baseline. Table 3-4 shows the
breakout of incremental total compliance costs for each option by wastestream.
The EPA estimates that, on a pre-tax basis, steam electric power plants would incur annualized costs of
meeting the regulatory options ranging from $266.8 million under Option 2 to $416.9 million under
Option 4 compared to pre-tax costs of $442.4 million for the baseline. Thus, all four options analyzed
provide cost savings when compared to the 2015 rule, with pre-tax savings ranging from $25.5 million to
$175.6 million (cost savings are shown as negative values in Table 3-3 and Table 3-4). On an after-tax
basis, the total compliance costs range from $216.3 million to $336.3 million, and cost savings ranging
from $26.4 million and $146.5 million, depending on the option. On both the pre-and post-tax bases,
compliance costs are lowest, and savings greatest, for Option 2, followed by Option 1, Option 3, and
finally Option 4.
All four regulatory options yield annualized costs savings for the bottom ash transport water wastestream.
The greatest savings are achieved under Option 2 ($71.7 million after-tax), due to subcategorization of
low utilization units under Option 2. Options 1, 2, and 3 provide annualized cost savings for FGD
wastewater ranging between $72.1 million and $102.8 million on an after-tax basis, whereas Option 4
results in higher costs for FGD wastewater ($7.3 million on an annualized, after-tax basis), when
compared to the baseline.
Table 3-2: Estimated Total Annualized Compliance Costs (in millions, 2018$, at 2020)

Pre-Tax Compliance Costs
After-Tax Compliance Costs


Other



Other


Regulatory
Capital
Initial One-


Capital
Initial One-


Option
Technology
Time3
Total O&M
Total
Technology
Timea
Total O&M
Total
Baseline
$280.3
$0.01
$162.1
$442.4
$229.4
$0.0
$133.4
$362.8
Option 1
$162.9
$0.01
$113.8
$276.8
$132.3
$0.0
$93.8
$226.2
Option 2
$156.0
$0.08
$110.7
$266.8
$125.4
$0.1
$90.9
$216.3
Option 3
$176.9
$0.01
$139.2
$316.1
$142.5
$0.0
$114.4
$256.9
Option 4
$210.2
$0.01
$206.6
$416.9
$169.0
$0.0
$167.4
$336.3
Source: U.S. EPA Analysis, 2019
EPA-821-R-19-012
3-7

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
3: Compliance Costs
Table 3-3: Estimated Incremental Annualized Compliance Costs (in millions, 2018$, at 2020)

Pre-Tax Incremental Costs
After-Tax Incremental Costs


Net Other



Net Other


Regulatory
Net Capital
Initial One-
Net Total
Net Total
Net Capital
Initial One-
Net Total
Net Total
Option
Technology
Time3
O&M
Costs
Technology
Timea
O&M
Costs
Option 1
-$117.4
$0.00
-$48.2
-$165.6
-$97.0
$0.0
-$39.6
-$136.6
Option 2
-$124.3
$0.07
-$51.4
-$175.6
-$104.0
$0.1
-$42.5
-$146.5
Option 3
-$103.5
$0.00
-$22.9
-$126.3
-$86.8
$0.0
-$19.0
-$105.9
Option 4
-$70.1
$0.00
$44.5
-$25.5
-$60.4
$0.0
$34.0
-$26.4
Source: U.S. EPA Analysis, 2019
Table 3-4: Estimated Incremental Annualized Compliance Costs, by Wastestream (in millions,
2018$, at 2020)

Pre-Tax Incremental Costs
After-Tax Incremental Costs

Bottom Ash


Bottom Ash


Regulatory
Transport
FGD

Transport
FGD

Option
Water
Wastewater
Net Total Costs
Water
Wastewater
Net Total Costs
Option 1
-$42.8
-$122.9
-$165.6
-$33.8
-$102.8
-$136.6
Option 2
-$89.1
-$86.5
-$175.6
-$71.7
-$74.7
-$146.5
Option 3
-$42.8
-$83.6
-$126.3
-$33.8
-$72.1
-$105.9
Option 4
-$42.8
$17.2
-$25.5
-$33.8
$7.3
-$26.4
Source: U.S. EPA Analysis, 2019
3.2.2 Estima ted Regional Distribution of Total Compliance Costs
Table 3-5 reports incremental costs for each regulatory option at the level of a North American Electric
Reliability Corporation (NERC) region (see Table 2-5).19 As explained in Chapter 2 (Overview of the
Steam Electric Industry), because of differences in operating characteristics of steam electric power plants
across NERC regions, as well as differences in the economic and electric power system regulatory
circumstances of the NERC regions themselves, the regulatory options may affect costs, profitability,
electricity prices, and other impact measures differently across NERC regions.
Annualized after-tax compliance costs are highest in the SERC and RFC regions for all regulatory
options, and, as shown in Table 3-5, these regions also see the greatest incremental cost savings across
options 1, 2, and 3. SERC also has the largest cost savings under Option 4.
No steam electric power plant is estimated to incur compliance costs in the ASCC and HICC NERC regions and these
two regions are therefore omitted from the presentation of results.
EPA-821-R-19-012
3-8

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
3: Compliance Costs
Table 3-5: Estimated Annualized Incremental Compliance Costs by NERC Region (in millions,
2018$, at 2020)
Pre-Tax Incremental Compliance Costs
After-Tax Incremental Compliance Costs


Other



Other


NERC
Capital
Initial One-


Capital
Initial One-


Region3
Technology
Time
Total O&M
Total
Technology
Time
Total O&M
Total
Option 1
FRCC
-$6.4
$0.0
-$2.2
-$8.5
-$5.1
$0.0
-$1.8
-$7.0
MRO
-$3.1
$0.0
-$1.3
-$4.4
-$2.8
$0.0
-$1.2
-$4.0
NPCC
-$1.2
$0.0
-$0.6
-$1.8
-$0.9
$0.0
-$0.5
-$1.3
RFC
-$40.9
$0.0
-$18.8
-$59.8
-$31.3
$0.0
-$14.3
-$45.6
SERC
-$59.7
$0.0
-$22.5
-$82.2
-$52.1
$0.0
-$19.5
-$71.6
SPP
-$4.2
$0.0
-$1.8
-$6.1
-$3.3
$0.0
-$1.4
-$4.7
TRE
-$1.6
$0.0
-$0.9
-$2.4
-$1.4
$0.0
-$0.8
-$2.1
WECC
-$0.3
$0.0
-$0.1
-$0.4
-$0.3
$0.0
-$0.1
-$0.3
Total
-$117.4
$0.0
-$48.2
-$165.6
-$97.0
$0.0
-$39.6
-$136.6
Option 2
FRCC
-$3.7
$0.0
-$0.2
-$3.9
-$3.0
$0.0
-$0.2
-$3.2
MRO
-$7.1
$0.0
-$5.0
-$12.1
-$6.6
$0.0
-$4.7
-$11.3
NPCC
-$3.7
$0.0
-$3.1
-$6.8
-$2.7
$0.0
-$2.3
-$5.0
RFC
-$39.4
$0.0
-$14.7
-$54.1
-$30.1
$0.0
-$11.2
-$41.3
SERC
-$61.6
$0.0
-$25.2
-$86.8
-$54.2
$0.0
-$21.4
-$75.6
SPP
-$4.4
$0.0
-$1.9
-$6.3
-$3.4
$0.0
-$1.5
-$4.9
TRE
-$2.6
$0.0
-$0.6
-$3.2
-$2.3
$0.0
-$0.5
-$2.8
WECC
-$1.8
$0.0
-$0.7
-$2.5
-$1.7
$0.0
-$0.7
-$2.4
Total
-$124.3
$0.1
-$51.4
-$175.6
-$104.0
$0.1
-$42.5
-$146.5
Option 3
FRCC
-$3.7
$0.0
-$0.2
-$3.9
-$3.0
$0.0
-$0.2
-$3.2
MRO
-$4.0
$0.0
-$1.0
-$5.1
-$3.7
$0.0
-$0.9
-$4.7
NPCC
-$0.9
$0.0
-$0.3
-$1.3
-$0.7
$0.0
-$0.2
-$0.9
RFC
-$32.9
$0.0
-$8.3
-$41.3
-$25.2
$0.0
-$6.2
-$31.4
SERC
-$55.0
$0.0
-$11.1
-$66.1
-$48.6
$0.0
-$9.9
-$58.5
SPP
-$3.9
$0.0
-$1.2
-$5.2
-$3.0
$0.0
-$1.0
-$4.0
TRE
-$2.6
$0.0
-$0.6
-$3.2
-$2.3
$0.0
-$0.5
-$2.8
WECC
-$0.3
$0.0
-$0.1
-$0.4
-$0.3
$0.0
-$0.1
-$0.3
Total
-$103.5
$0.0
-$22.9
-$126.3
-$86.8
$0.0
-$19.0
-$105.9
Option 4
FRCC
-$0.1
$0.0
$5.5
$5.4
-$0.3
$0.0
$4.2
$3.9
MRO
-$4.0
$0.0
-$0.9
-$4.9
-$3.7
$0.0
-$0.8
-$4.5
NPCC
-$1.0
$0.0
$0.0
-$1.0
-$0.8
$0.0
$0.0
-$0.7
RFC
-$24.3
$0.0
$20.5
-$3.8
-$18.5
$0.0
$15.8
-$2.7
SERC
-$35.1
$0.0
$19.6
-$15.5
-$32.6
$0.0
$15.0
-$17.6
SPP
-$2.8
$0.0
$0.4
-$2.4
-$2.2
$0.0
$0.3
-$1.9
TRE
-$2.5
$0.0
-$0.5
-$2.9
-$2.2
$0.0
-$0.4
-$2.6
WECC
-$0.3
$0.0
-$0.1
-$0.4
-$0.3
$0.0
-$0.1
-$0.3
Total
-$70.1
$0.0
$44.5
-$25.5
-$60.4
$0.0
$34.0
-$26.4
a. The EPA estimated zero ELG compliance costs in the ASCC and HICC regions. These two regions are omitted from the table
presentation. This omission does not affect totals.
Source: U.S. EPA Analysis, 2019
EPA-821-R-19-012
3-9

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
3: Compliance Costs
3.3 Key Uncertainties and Limitations
Economic analyses are not perfect predictions and thus, like all such analyses, this analysis has some
uncertainties and limitations.
•	The compliance costs used in this analysis reflect unit retirements, conversions, and repowerings
announced through October 2018 and scheduled to occur by the end of 2028. For details, see
memorandum entitled "Changes to Industry Profile for Coal-Fired Generating Units for the
Steam Electric Effluent Guidelines Proposed Rule" (DCN SE07207 in the rule docket). To the
extent that actual unit retirements, conversions, and repowerings at steam electric power plants
differ from announced changes, estimated annualized compliance costs may differ from actual
costs.
•	The EPA assumed that the equipment installed to meet any new limitations could reasonably be
estimated to operate for 20 years or more, based on a review of reported performance
characteristics of the equipment components. The EPA thus used 20 years as the basis for the cost
and economic impact analyses that account for the estimated operating life of compliance
technology. To the extent that the actual service life is longer or shorter than 20 years, costs
presented on annual equivalent basis would be over- or under-stated.
•	Annualized compliance costs depend on the assumed technology implementation year. For the
purpose of the cost and economic impact analyses, the EPA determined years in which
technology implementation would reasonably be estimated to occur across the universe of steam
electric power plants, based on plant-specific information about existing NPDES permits and
extrapolating future permit issuance dates assuming permits are renewed every five years. To the
extent that compliance costs are incurred in an earlier or later year, the annualized values
presented in this section may under or overstate the annualized total costs of the regulatory
options.
•	The EPA estimated VIP participants for options 2 and 3 based on the lowest cost technology on
an annualized and discounted basis, but plant owners may consider other factors in deciding
whether to participate in the VIP so actual participation may be higher or lower than projected.
EPA-821-R-19-012
3-10

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
4: Screening-Level Economic Impacts
4 Cost and Economic Impact Screening Analyses
4.1	Analysis Overview
Following the same methodology used for the 2015 rule analysis (U.S. EPA, 2015b), the EPA assessed
the costs and economic impacts of the regulatory options in two ways:
1.	A screening-level assessment reflecting current operating characteristics of steam electric power
plants and with assignment of estimated compliance costs to those plants. This analysis assumes
no changes in operating characteristics - e.g., quantity of generated electricity and revenue - as a
result of the regulatory options. This screening-level assessment, which is documented in this
chapter, includes two specific analyses:
-	A cost-to-revenue screening analysis to assess the impact of compliance outlays on
individual steam electric power plants (Section 4.2)
-	A cost-to-revenue screening analysis to assess the impact of compliance outlays on
domestic parent-entities owning steam electric power plants (Section 4.3)
2.	A broader electricity market-level analysis based on IPM (the Market Model Analysis). This
analysis, which provides a more comprehensive indication of the economic achievability of the
regulatory options that the EPA evaluated, including an assessment of incremental plant closures
(or avoided closures), is discussed in Chapter 5. Unlike the preceding analysis discussed in this
chapter, the Market Model Analysis accounts for estimated changes in the operating
characteristics of plants from both estimated changes in electricity markets and operating
characteristics of plants independent of and as a result of the regulatory options.
4.2	Cost-to-Revenue Analysis: Plant-Level Screening Analysis
The cost-to-revenue measure compares the cost of implementing and operating compliance technologies
with the plant's operating revenue and provides a screening-level assessment of the impact that might be
estimated of the regulatory options. As discussed in U.S. EPA (2015b; see Chapter 2), the majority of
steam electric power plants operate in states with regulated electricity markets. The EPA estimates that
plants located in these states may be able to recover any compliance cost-based increases in their
production costs through increased electricity prices, depending on the business operation model of the
plant owner(s), the ownership and operating structure of the plant itself, and the role of market
mechanisms used to sell electricity. In contrast, in states in which electric power generation has been
deregulated, cost recovery is not guaranteed. While plants operating within deregulated electricity
markets may be able to recover some of their additional production costs through increased revenue, it is
not possible to determine the extent of cost recovery ability for each plant.20 Note that the EPA estimates
that the converse also applies - plants operating in regulated markets are more likely to pass on any
decline in production costs to their customer as reduced rates, whereas customer savings are not
guaranteed in deregulated markets.
While the regulatory status in a given state affects the ability of electric power plants and their parent entities to recover
electricity generation costs, it is not the only factor and should not be used solely as the basis for cost-pass-through
determination.
EPA-821-R-19-012
4-1

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
4: Screening-Level Economic Impacts
In assessing the cost impact of the baseline and four regulatory options on steam electric power plants in
this screening-level analysis, the Agency assumed that the plants would not be able to pass any of the
change in their production costs to consumers (zero cost pass-through). This assumption is used for
analytic convenience and provides a worst-case scenario of regulatory impacts to steam electric power
plants.21
4.2.1 Analysis Approach and Data Inputs
As described in Chapter 1 as proposed, the EPA estimates all steam electric power plants to meet any
new requirements for bottom ash transport water and FGD wastewater beginning in 2021, with
compliance occurring as late as 2028 for certain plants, wastestreams, and regulatory options.
Using the same approach as used for the 2015 rule (U.S. EPA, 2015b), the EPA analyzed the impacts of
the baseline first, and then conducted the same analysis for each of the four regulatory options. The
difference in findings between the regulatory options and baseline provides insight into the potential
impacts of the regulatory options.
The EPA updated the approach used for the 2015 rule to incorporate more recent data. For the current
analysis, the EPA used 2020 as the basis for comparing after-tax compliance costs (see Chapter 3) to
revenue at the plant level.22' For this comparison, the EPA developed plant-level revenue values for all
steam electric power plants using data from the Department of Energy's Energy Information
Administration (EIA) on electricity generation by prime mover, and utility/operator-level electricity
prices and disposition. Specifically, the EPA multiplied the 6-year average of electricity generation values
over the period 2011 to 2016 from the EIA-923 database by 6-year average electricity prices over the
period 2011 to 2016 from the EIA-861 database (EIA, 2017b; EIA, 2017c).23,24 The EPA estimated
compliance costs in 2018 dollars. To provide cost and revenue comparisons on a consistent analysis-year
(2020) and dollar-year (2018) basis, the EPA adjusted the EIA electricity price data, which are reported in
nominal dollars of each year.
Cost-to-revenue ratios are used to describe impacts to entities because they provide screening-level
indicators of potential economic impacts. Just as for the plants owned by small entities under guidance in
Even though the majority of steam electric power plants may be able to pass increases in production costs to consumers
through increased electricity prices, it is difficult to determine exactly which plants would be able to do so.
Consequently, the EPA concluded that assuming zero cost pass-through is appropriate as a screening-level, upper
bound estimate of the potential impact of compliance expenditures on steam electric power plants and their parent
entities. The analysis, while helpful to understand potential cost impact, does not generally indicate whether
profitability is jeopardized, cash flow is affected, or risk of financial distress is increased.
For private, tax-paying entities, after-tax costs are a more relevant measure of potential private cost burden than pre-tax
costs. For non-tax-paying entities (e.g., State government and municipality owners of steam electric power plants), the
estimated costs used in this calculation include no adjustment for taxes.
In using the year-by-year revenue values to develop an average over the data years, the EPA set aside from the average
calculation any generation values that are anomalously low. Such low generating output likely results from temporary
disruption in operation, such as a generating unit being out of service for maintenance.
EPA's first step in calculating plant revenue was to restate electricity prices in 2018 dollars using the Gross Domestic
Product (GDP) deflator index published by the U.S. Bureau of Economic Analysis (BEA) (2018). These individual
yearly values were then averaged and brought forward to 2020 using electricity price projections from the Annual
Energy Outlook publication for 2018 (AEO2018) (EIA, 2018a). AEO2018 contains projections and analysis of U.S.
energy supply, demand, and prices through 2050. AEO2018 electricity price projections are in constant dollars;
therefore, these adjustments yield 2020 revenue values in dollars of the year 2018.
EPA-821-R-19-012
4-2

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
4: Screening-Level Economic Impacts
U.S. EPA (2006), and the approach EPA has used previously in analyses of the 2015 ELG rule (U.S.
EPA, 2015b) and 316(b) Existing Facilities Rule (U.S. EPA, 2014), the EPA assesses plants incurring
costs below one percent of revenue as unlikely to face material economic impacts, plants with costs of at
least one percent but less than three percent of revenue as having a higher chance of facing material
economic impacts, and plants incurring costs of at least three percent of revenue as having a still higher
probability of material economic impacts.
4.2.2 Key Findings for Regulatory Options
The EPA estimates that for 930 steam electric power plants, including those estimated to incur zero
compliance costs, costs would not exceed the one percent of revenue threshold under the baseline. Table
4-1 presents cost-to-revenue analysis results for the baseline, while Table 4-2 presents results for the four
regulatory options relative to the baseline. Under all four regulatory options, most plants would not
experience significant changes in their cost-to-revenue ratios compared to baseline costs. However,
additional plants would fall under the one percent of revenue threshold, as shown in Table 4-2, which
reports changes in plant-level cost-to-revenue results by owner type and regulatory option. Under Option
4, one investor-owned plant moves up one cost-to-revenue threshold, from less than one percent under the
baseline scenario to between one and three percent, while 7 other plants move to lower cost-to-revenue
thresholds. Of these 7 plants, 6 plants incur no additional costs compared to baseline,25 and one
municipality-owned plant moves from the greater than three percent threshold under baseline to between
one and three percent. As for Options 1, 2, and 3, all plants that experience changes in cost-to-revenue
thresholds shift downwards. For details on cost-to-revenue results for small entities, see Section 8.2.
Table 4-1: Plant-Level Cost-to-Revenue Analysis Results for the Baseline by Owner Type
Owner Type
Total Number of
Plants3
Number of Plants with a Ratio of
0%a'b
#0 and <1%
>1 and 3%
>3%
Baseline
Cooperative
64
54
7
3
0
Federal
20
14
4
2
0
Investor-owned
509
429
75
4
1
Municipality
123
108
6
2
5
Nonutility
198
195
2
0
0
Political Subdivision
34
33
0
1
0
State
4
2
2
0
0
Total
951
834
96
12
6
a.	Plant counts are weighted estimates
b.	These plants already meet discharge requirements for the wastestreams controlled by a given regulatory option and
therefore are not estimated to incur compliance costs.
Source: U.S. EPA Analysis, 2019.
The six plants would incur costs to meet bottom ash transport water requirements under the baseline, based on dry
handling / closed loop system, but would not incur costs under the regulatory options, based on High Recycle Rate
Systems.
EPA-821-R-19-012
4-3

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
4: Screening-Level Economic Impacts
Table 4-2: Plant-Level Incremental Cost-to-Revenue Analysis Results by Owner Type and
Regulatory Option
Owner Type
A Total
Number of
Plants3
A Number of Plants with a Ratio of
0%a'b
#0 and <1%
>1 and 3%
>3%
Option 1
Cooperative
0
0
0
0
0
Federal
0
2
-2
0
0
Investor-owned
0
4
-3
0
-1
Municipality
0
0
1
0
-1
Nonutility
0
0
0
0
0
Political Subdivision
0
0
0
0
0
State
0
0
0
0
0
Total
0
6
-4
0
-2
Option 2
Cooperative
0
0
1
-1
0
Federal
0
2
-2
0
0
Investor-owned
0
4
-1
-3
0
Municipality
0
0
5
-1
-4
Nonutility
0
0
0
0
0
Political Subdivision
0
0
1
-1
0
State
0
0
0
0
0
Total
0
6
4
-6
-4
Option 3
Cooperative
0
0
0
0
0
Federal
0
2
-2
0
0
Investor-owned
0
4
-4
0
0
Municipality
0
0
1
0
-1
Nonutility
0
0
0
0
0
Political Subdivision
0
0
0
0
0
State
0
0
0
0
0
Total
0
6
-5
0
-1
Option 4
Cooperative
0
0
0
0
0
Federal
0
2
-2
0
0
Investor-owned
0
4
-5
1
0
Municipality
0
0
0
1
-1
Nonutility
0
0
0
0
0
Political Subdivision
0
0
0
0
0
State
0
0
0
0
0
Total
0
6
-7
2
-1
a.	Plant counts are weighted estimates
b.	These plants already meet discharge requirements for the wastestreams controlled by a given regulatory option and
therefore are not estimated to incur compliance costs.
Source: U.S. EPA Analysis, 2019.
EPA-821-R-19-012
4-4

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
4: Screening-Level Economic Impacts
4.2.3 Uncertainties and Limita tions
Despite the EPA's use of the best available information and data, this analysis of plant-level impacts has
uncertainties and limitations, including:
•	The impact of the regulatory options may be over- or under-estimated as a result of differences
between actual 2020 plant revenue and those estimated using EIA databases for 2011 through
2016.
•	As noted above, the zero cost pass-through assumption represents a worst-case scenario from the
perspective of the plant owner. To the extent that companies are able to pass some compliance
costs on to consumers through higher electricity prices, this analysis overstates the potential
impact of the baseline and regulatory options on steam electric power plants.
4.3 Cost-to-Revenue Screening Analysis: Parent Entity-Level Analysis
Following the methodology the EPA used for the analysis of the 2015 rule (U.S. EPA, 2015b), the EPA
also assessed the economic impact of the regulatory options at the parent entity level. The cost-to-revenue
screening analysis at the entity level adds particular insight on the impact of compliance requirements on
those entities that own multiple plants.
The EPA conducted this screening analysis at the highest level of domestic ownership, referred to as the
"domestic parent entity." For this analysis, the Agency considered only entities with the largest share of
ownership (e.g., majority owner) in at least one surveyed steam electric power plant.26'27 The entity-level
analysis maintains the worst-case analytical assumption of no pass-through of compliance costs to
electricity consumers used for the plant-level cost-to-revenue analysis in Section 4.2.
4.3.1 Analysis Approach and Data Inputs
Following the approach used in the 2015 rule (U.S. EPA, 2015b), to assess the entity-level
economic/financial impact of compliance requirements, the EPA summed plant-level annualized after-tax
compliance costs calculated in Section 3.2 to the level of the steam electric power plant owning entity and
compared these costs to parent entity revenue.
Similar to the plant-level analysis, the EPA used cost-to-revenue ratios of one and three percent as
markers of potential impact for this analysis. Also similar to the assumptions made for the plant-level
analysis, for this entity-level analysis the Agency assumed that entities incurring costs below one percent
of revenue are unlikely to face significant economic impacts, while entities with costs of at least one
percent but less than three percent of revenue have a higher chance of facing significant economic
impacts, and entities incurring costs of at least three percent of revenue have a still higher probability of
significant economic impacts.
Throughout these analyses, the EPA refers to the owner with the largest ownership share as the "majority owner" even
when the ownership share is less than 51 percent.
When two entities have equal ownership shares in a plant (e.g., 50 percent each), the EPA analyzed both entities and
allocated plant-level compliance costs to each entity.
EPA-821-R-19-012
4-5

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
4: Screening-Level Economic Impacts
Following the approach used in in the 2015 rule (2015b; see Section 4.3), the EPA analyzed two cases
that provide approximate upper and lower bound estimates on: (1) the number of entities incurring
compliance costs and (2) the costs incurred by any entity owning one or more steam electric power plant.
This entity-level cost-to-revenue analysis involved the following steps: (1) Determining the parent entity;
(2) Determining the parent entity revenue; and (3) Estimating compliance costs at the level of the parent
entity. The sections below highlight updates to incorporate more recent data than were used in U.S. EPA
(2015b).
Determining the Parent Entity
The EPA used information from the 2016 EIA-860 database which provides owners and the share of
ownership in electric generating units (EIA, 2017a) to determine ownership of each coal-fired steam
electric power plant and surveyed non-coal steam electric power plants (see U.S. EPA, 2015b for
discussion of how non-coal steam electric power plants are incorporated in the analysis). The EPA
supplemented this information with data from corporate/financial websites and from the Steam Electric
Survey to identify the highest level domestic parent entity for each plant.
Determining Parent Entity Revenue
For each parent entity identified in the preceding step, the EPA determined revenue values based on
information from corporate or financial websites, if those values were available. The EPA tried to obtain
revenue for as many years within 2015 through 2017 and used the average of reported values. If revenue
values were not reported on corporate/financial websites, the Agency used 2013-2016 average revenue
values from the EIA-861 database (EIA, 2017b).
The EPA restated entity revenue values in 2018 dollars using the GDP Deflator. For this analysis, the
Agency assumed that these average historical revenue values are representative of revenues as of 2020.
Although the entity-level revenue values might reasonably be estimated to change by 2020 (i.e.. have
increased or decreased relative to average historical revenue), the EPA was less confident in the reliability
of projecting revenue values at the entity level than in that of projecting plant-level revenue values to
reflect changes in generation. For the entity-level analysis, therefore, the EPA did not project or further
adjust revenue values developed using the sources and methodology described above but used these
values as is. In effect, plants and their parent entities are assumed to be the same 'business entities' in
terms of constant dollar revenue in 2020 as they were in the year for which revenue were reported.
Estimating Compliance Costs at the Level of the Parent Entity
Following the approach used in the analysis of the 2015 rule, to account for the parent entities of all 951
steam electric power plants, the EPA analyzed two approximate bounding cases that provide a range of
estimates for the number of entities incurring compliance costs and the costs incurred by any entity
owning a steam electric power plant: (1) A lower bound estimate that assumes that the surveyed owners
represent all owners, which effectively assumes that any non-surveyed plants are owned by the same
surveyed entities and maximizes the number of plants owned by any given entity; and (2) An upper bound
estimate that assumes that the non-surveyed owners are different from those surveyed but have similar
EPA-821-R-19-012
4-6

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
4: Screening-Level Economic Impacts
characteristics, which results in a greater number of owners but minimizes the number of plants owned by
each. See Chapter 4 in U.S. EPA (2015b) for details.
4.3.2 Key Findings for Regula tory Options
Table 4-3 and Table 4-4 summarize the results from the entity-level impact analysis under the lower
bound (Case 1) and upper bound (Case 2) estimates of the number of entities incurring costs. Table 4-3
presents results under the baseline, while Table 4-4 presents results under the four regulatory options
relative to the baseline. The tables show the number of entities that incur costs in four ranges: no cost,
non-zero costs less than one percent of an entity's revenue, at least one percent but less than three percent
of revenue, and at least three percent of revenue.
The EPA estimates that between 243 and 478 parent entities own steam electric power plants based on the
range indicated by Case 1 and Case 2, respectively. Under the baseline in Case 1, 236 parent entities are
estimated to incur costs less than one percent of revenue, and in Case 2, this number is 470 parent entities.
When examining changes in number of parent entities that shift across cost-to-revenue thresholds, as
shown in Table 4-4, most entities stay within the same threshold.28 However, where there are changes
across thresholds, these changes all move downward, i.e., smaller impacts relative to revenue. Under the
most stringent regulatory option the EPA analyzed, Option 4, one municipality-owned entity moves down
one impact threshold, from between one and three percent to less than one percent, and one investor-
owned entity also moves down one threshold, from between one and three percent to incurring no costs.
Overall, this screening-level analysis shows that few entities are likely to experience significant changes
in compliance costs compared to revenues, and economic impacts to these entities would be lessened
across all options.
Table 4-3: Baseline Entity-Level Cost-to-Revenue Analysis Results

Case 1: Lower bound estimate of number of firms
Case 2: Upper bound estimate of number of firms

owning plants that face requirements under the
owning plants that face requirements under the


regulatory analysis


regulatory analysis


Total
Number of Entities with a Ratio of
Total
Number of Entities with a Ratio of

Number





Number






of

*0 and
>1 and


of

*0 and
>1 and


Entity Type
Entities
0%a
<1%
3%
>3%
Unknown
Entities
0%a
<1%
3%
>3%
Unknown13
Baseline
Cooperative
28
18
10
0
0
0
50
40
10
0
0
0
Federal
1
0
1
0
0
0
3
2
1
0
0
0
Investor-












owned
69
38
30
1
0
0
157
126
30
1
0
0
Municipality
59
46
7
4
2
0
94
81
7
4
2
0
Nonutility
74
72
2
0
0
0
150
147
2
0
0
1
Other












Political












Subdivision
10
9
1
0
0
0
21
20
1
0
0
0
The results include entities that own only steam electric power plants that already meet discharge requirements for the
wastestreams addressed by a given regulatory option and are therefore not estimated to incur any compliance
technology costs.
EPA-821-R-19-012	4-7

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
4: Screening-Level Economic Impacts
Table 4-3: Baseline Entity-Level Cost-to-Revenue Analysis Results
Case 1: Lower bound estimate of number of firms
owning plants that face requirements under the
regulatory analysis

Total
Number of Entities with a Ratio of
Total
Number of Entities with a Ratio of

Number





Number






of

*0 and
>1 and


of

*0 and
>1 and


Entity Type
Entities
0%a
<1%
3%
>3%
Unknown
Entities
0%a
<1%
3%
>3%
Unknown13
State
2
1
1
0
0
0
2
1
1
0
0
0
Total
243
184
52
5
2
0
478
418
52
5
2
1
Case 2: Upper bound estimate of number of firms
owning plants that face requirements under the
regulatory analysis
a.	These entities own only plants that already meet discharge requirements for the wastestreams addressed by a given
regulatory option and are therefore not estimated to incur any compliance technology costs.
b.	The EPA was unable to determine revenues for one parent entity under Case 2.
Source: U.S. EPA Analysis, 2019.
Table 4-4: Entity-Level Incremental Cost-to-Revenue Analysis Results
Case 1: Lower bound estimate of change in	Case 2: Upper bound estimate of change in
number of firms owning plants that face	number of firms owning plants that face
requirements under the regulatory analysis	requirements under the regulatory analysis

A Total
Number
A Number of Entities with a Ratio of
A Total
Number
of
Entities
A Number of Entities with a Ratio of
Entity Type
of
Entities
0%a
*0 and
<1%
>1 and
3%
>3%
Unknown

0%a
*0 and
<1%
>1 and
3%
>3%
Unknown
Option 1
Cooperative
0
0
0
0
0
0
0
0
0
0
0
0
Federal
0
0
0
0
0
0
0
0
0
0
0
0
Investor-
owned
0
1
-1
0
0
0
0
1
-1
0
0
0
Municipality
0
0
2
-2
0
0
0
0
2
-2
0
0
Nonutility
0
0
0
0
0
0
0
0
0
0
0
0
Other"
0
0
0
0
0
0
0
0
0
0
0
0
State
0
0
0
0
0
0
0
0
0
0
0
0
Total
0
1
1
-2
0
0
0
1
1
-2
0
0
Option 2
Cooperative
0
0
0
0
0
0
0
0
0
0
0
0
Federal
0
0
0
0
0
0
0
0
0
0
0
0
Investor-
owned
0
1
0
-1
0
0
0
1
0
-1
0
0
Municipality
0
0
4
-3
-1
0
0
0
4
-3
-1
0
Nonutility
0
0
0
0
0
0
0
0
0
0
0
0
Other"
0
0
0
0
0
0
0
0
0
0
0
0
State
0
0
0
0
0
0
0
0
0
0
0
0
Total
0
1
4
-4
-1
0
0
1
4
-4
-1
0
EPA-821-R-19-012
4-8

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
4: Screening-Level Economic Impacts
Table 4-4: Entity-Level Incremental Cost-to-Revenue Analysis Results
Case 1: Lower bound estimate of change in	Case 2: Upper bound estimate of change in
number of firms owning plants that face	number of firms owning plants that face
requirements under the regulatory analysis	requirements under the regulatory analysis

A Total
Number
A Number of Entities with a Ratio of
A Total
Number
of
Entities
A Number of Entities with a Ratio of
Entity Type
of
Entities
0%a
*0 and
<1%
>1 and
3%
>3%
Unknown

0%a
*0 and
<1%
>1 and
3%
>3%
Unknown
Option 3
Cooperative
0
0
0
0
0
0
0
0
0
0
0
0
Federal
0
0
0
0
0
0
0
0
0
0
0
0
Investor-
owned
0
1
-1
0
0
0
0
1
-1
0
0
0
Municipality
0
0
2
-2
0
0
0
0
2
-2
0
0
Nonutility
0
0
0
0
0
0
0
0
0
0
0
0
Other"
0
0
0
0
0
0
0
0
0
0
0
0
State
0
0
0
0
0
0
0
0
0
0
0
0
Total
0
1
1
-2
0
0
0
1
1
-2
0
0
Option 4
Cooperative
0
0
0
0
0
0
0
0
0
0
0
0
Federal
0
0
0
0
0
0
0
0
0
0
0
0
Investor-
owned
0
1
-1
0
0
0
0
1
-1
0
0
0
Municipality
0
0
1
-1
0
0
0
0
1
-1
0
0
Nonutility
0
0
0
0
0
0
0
0
0
0
0
0
Other"
0
0
0
0
0
0
0
0
0
0
0
0
State
0
0
0
0
0
0
0
0
0
0
0
0
Total
0
1
0
-1
0
0
0
1
0
-1
0
0
a.	These entities own only plants that already meet discharge requirements for the wastestreams addressed by a given regulatory
option and are therefore not estimated to incur any compliance technology costs.
b.	Other political subdivision.
Source: U.S. EPA Analysis, 2019.
4.3.3 Uncertainties and Limita Hons
Despite the EPA's use of the best available information and data, this analysis of entity-level impacts has
uncertainties and limitations, including:
•	The entity-level revenue values obtained from the corporate and financial websites or EIA
databases are for 2015 through 2017. To the extent that actual 2020 entity revenue values are
different, on a constant dollar basis, from those estimated using historical data, the cost-to-
revenue measure for parent entities of steam electric power plants may be over- or under-
estimated.
•	The assessment of entity-level impacts relies on approximate upper and lower bound estimates of
the number of parent entities and the numbers of steam electric power plants that these entities
EPA-821-R-19-012
4-9

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
4: Screening-Level Economic Impacts
own. The EPA expects that the range of results from these analyses provides appropriate insight
into the overall extent of entity-level effects.
• As is the case with the plant-level analysis discussed in Section 4.2, the zero cost pass-through
assumption represents a worst-case scenario from the perspective of the plant owner. To the
extent that companies are able to pass some compliance costs on to consumers through higher
electricity prices, this analysis overstates the potential impact of the baseline and regulatory
options on steam electric power plants.
EPA-821-R-19-012
4-10

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
5: Electricity Market Analyses
5 Assessment of the Impact of the Regulatory Options in the Context
of National Electricity Markets
Following the approach used to analyze the impacts of the 2015 rule and other various regulatory actions
affecting the electric power sector over the last decade, the EPA used the Integrated Planning Model
(IPM®), a comprehensive electricity market optimization model that can evaluate such impacts within the
context of regional and national electricity markets. To assess plant- and market-level effects of the
regulatory options considered for the proposed rule, the EPA used the latest version of this analytic
system: Integrated Planning Model Version 6 (IPM V6) (U.S. EPA, 2018a).29
The market model analysis is a more comprehensive analysis compared to the screening-level analyses
discussed in Chapter 4: Cost and Economic Impact Screening Analyses', it is meant to inform the EPA's
assessment of whether the regulatory options would result in any capacity retirements (full or partial plant
closures)30 and to provide insight on the impact of the regulatory options on the overall electricity market,
including to assess whether the regulatory options may significantly affect the energy supply, distribution
or use under Executive Order 13211 (see Section 10.7). In allocating resources to analytical effort, the
EPA chose to run IPM for Options 2 and 4 because these two options bound the costs of the proposal and
IPM results therefore capture the range of impacts that may result from the four regulatory options.
In contrast to the screening-level analyses, which are static analyses and do not account for
interdependence of electric generating units in supplying power to the electric transmission grid, IPM
accounts for potential changes in the generation profile of steam electric and other units and consequent
changes in market-level generation costs, as the electric power market responds to changes in generation
costs for steam electric units due to the regulatory options. IPM is also dynamic in that it is capable of
using forecasts of future conditions to make decisions for the present. Additionally, in contrast to the
screening-level analyses in which EPA assumed no pass through of compliance costs, IPM depicts
production activity in wholesale electricity markets where some recovery of compliance costs through
increased electricity prices is possible but not guaranteed. Finally, IPM incorporates electricity demand
growth assumptions from the Department of Energy's Annual Energy Outlook 2018 (AEO2018), whereas
the screening-level analyses discussed in other chapters of this report assume that plants would generate
approximately the same quantity of electricity in 2020 as they did on average during 2011-2016.
Changes in electricity production costs and potential associated changes in electricity output at steam
electric power plants can have a range of broader market impacts that extend beyond the effect on steam
electric power plants. In addition, the impact of compliance requirements on steam electric power plants
may be seen differently when the analysis considers the impact on those plants in the context of the
broader electricity market instead of looking at the impact on a standalone, single-plant basis. Therefore,
use of a comprehensive, market model analysis system that accounts for interdependence of electric
generating units is important in assessing regulatory impacts on the electric power industry as a whole.
For more information on IPM, see https://www.epa.gov/airmarkets/clean-air-markets-power-sector-modeling. The
version of IPM used for this analysis incorporate the effects of the December 2017 tax law which reduced corporate tax
rates from 35 percent to 21 percent, along with other changes (see U.S. EPA, 2018b).
For the 2015 rule analysis, the EPA used IPM to inform assessment of the economic achievability of the ELG options
under CWA Sections 301(b)(2)(A) and 304(b)(2) (see U.S. EPA, 2015b).
EPA-821-R-19-012
5-1

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
5: Electricity Market Analyses
The EPA's use of IPM V6 for this analysis is consistent with the intended use of the model to evaluate the
effects of changes in electricity production costs, on electricity generation costs, subject to specified
demand and emissions constraints. As discussed in greater detail in U.S. EPA (2018a), IPM generates
least-cost resource dispatch decisions based on user-specified constraints such as environmental, demand,
and other operational constraints. The model can be used to analyze a wide range of electric power market
scenarios at the plant, regional, and national levels. Applications of IPM have included capacity planning,
environmental policy analysis and compliance planning, wholesale price forecasting, and asset valuation.
IPM uses a long-term dynamic linear programming framework that simulates the dispatch of generating
capacity to achieve a demand-supply equilibrium on a seasonal basis and by region. The model computes
optimal capacity that combines short-term dispatch decisions with long-term investment decisions.
Specifically, IPM seeks the optimal solution to an "objective function," which is the summation of all the
costs incurred by the electric power sector, i.e., capital costs, fixed and variable operation and
maintenance (O&M) costs, and fuel costs, on a net present value basis over the entire evaluated time
horizon. The objective function is minimized subject to a series of supply and demand constraints.
Supply-side constraints include capacity constraints, availability of generation resources, plant minimum
operating constraints, transmission constraints, fuel supply constraints, and environmental constraints.
Demand-side constraints include reserve margin constraints and minimum system-wide load
requirements.
The final difference between the EPA's electricity market optimization model analysis and the screening-
level analyses in Chapter 4: Cost and Economic Impact Screening Analyses is the inclusion of estimated
market-level impacts of environmental rules in the analysis baseline. Notably, for this current proposal,
the EPA started from an electricity market "base case" that includes market-level impacts of the Cross-
State Air Pollution Rule (CSAPR and CSAPR Update), Mercury and Air Toxics Standards (MATS),
CWA section 316(b) rule, and the final CCR rule, among others. The base case includes the effects of the
Regional Greenhouse Gas Initiative (RGGI) and California's Global Warming Solutions Act, but
excludes the federal Clean Power Plan (CPP) given ongoing litigation, a Supreme Court stay, and
regulatory review.31 The EPA also conducted a sensitivity analysis of proposed Option 2 that includes
market-level impacts of the ACE rule finalized in June 19, 2019 (see Section 2.2.1). Appendix C
summarize the results of this sensitivity analysis.
In analyzing the effect of the regulatory options using IPM V6, the EPA first specified a base case that
incorporates fixed and variable costs that are estimated to be incurred by steam electric power plants and
generating units to comply with the 2015 rule requirements for fly ash transport water, bottom ash
transport water, and FGD wastewater (in the IPM documentation, these costs are referred to as "FOM and
VOM adders" and correspond to fixed O&M [FOM] and variable O&M [VOM]). Results for this first
model run provide the baseline against which to compare outputs for regulatory options runs. In analyzing
Options 2 and 4, the EPA modified the associated fixed and variable costs to reflect the difference
between the bottom ash transport water and FGD wastewater compliance costs under the 2015 rule and
those for the regulatory options in this proposal. The EPA ran IPM to simulate the dispatch of electricity
31	On October 16,2017, the EPA proposed to repeal the Carbon Pollution Emission Guidelines for Existing Stationary
Sources: Electric Utility Generating Units (EGUs), (82 FR 48035).
EPA-821-R-19-012	5-2

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
5: Electricity Market Analyses
generating units that would meet projected demand at the lowest costs subject to the same constraints as
those present in the analysis baseline.
The rest of this chapter is organized as follows:
•	Section 5.1 summarizes the key inputs to IPM for performing the analyses of the regulatory
options and the key outputs reviewed as indicators of the effect of the regulatory options.
•	Section 5.2 provides the findings from the market model analysis.
•	Section 5.3 discusses the effects of the regulatory options on new coal capacity.
•	Section 5.4 identifies key uncertainties and limitations in the market model analysis.
5.1 Model Analysis Inputs and Outputs
To assess the impact of the regulatory options, the EPA compared each of two policy runs (Option 2 and
Option 4) to an IPM V6 Base Case projection of electricity markets and plant operations that includes the
modeled effects of the 2015 rule, among existing environmental regulations.
5.1.1 Analysis Years
As described in U.S. EPA (2018a), IPM V6 models the electric power market over the 34-year period
from 2021 to 2054, breaking this period into the eight representative run years shown in Table 5-1. As
discussed in Chapter 1 steam electric power plants are estimated to implement control technologies to
meet the regulatory option requirements starting in 2021 and as late as 2028. This technology
implementation window primarily falls within the time periods captured by the 2021, 2023 and 2025 run
years {i.e., 2021-2027). The 2030 run year includes the last year of technology implementation, 2028, and
goes through 2032.
Table 5-1: IPM Run Years
Run Year
Years Represented
2021
2021
2023
2022-2023
2025
2024-2027
2030
2028-2032
2035
2033-2037
2040
2038-2042
2045
2043-2047
2050
2048-2054
Source: U.S. EPA, 2018a.
To assess the effect of the regulatory options on electricity markets during the period after technology
implementation by all steam electric power plants - the steady state post-compliance period - the EPA
analyzed results reported for the IPM 2030 run year.32 As discussed in Chapter 3, under the regulatory
Although all rim years are reported in the IPM results, for the 2015 rule the EPA focused on two run years to cover the
range of potentially significant changes: one run year representing the period when plants would be in the process of
EPA-821-R-19-012
5-3

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
5: Electricity Market Analyses
option specifications considered for this analysis, this steady state period is estimated to begin in the last
year of the technology implementation window, i.e., 2028, and continue into the future. The 2028 analysis
year is captured in the IPM 2030 run year. Because the model run year 2030, captures mostly calendar
years {i.e., 2028-2033) that fall outside the technology implementation window of 2021 through 2028, the
EPA determined that 2030 is an appropriate run year to capture steady-state regulatory effects. Plants that
implement changes in 2028 will have begun planning prior to this year, such that the period covers years
that reflect full implementation of the rule. Effects that may occur during the post-compliance "steady
state" include potential permanent changes in generating capacity from changes in early retirement
(closure) of generating units, long-term changes in electricity production costs due to changes in
operating expenses, permanent changes in electric generating capability and production efficiency at
steam electric power plants, and, as described above, changes in dispatches of other generating units
resulting from the changes in electric generating capacity.
5.1.2 Key Inputs to IPM V6 for the Market Model Analysis of the Proposed ELG Revisions
5.1.2.1 Existing Plants
The inputs for the electricity market analyses include compliance costs and the technology
implementation year. IPM models the entire electric power generating industry using a total of 18,742
generating units at 7,642 plants. The EPA estimated that up to 121 steam electric power plants may incur
non-zero compliance costs under any of the regulatory options, based on the costing methodologies
described in the Supplemental TDD; (U.S. EPA, 2019a).33
The EPA input the ELG capital, initial one-time costs, annual fixed O&M (FOM), and annual variable
O&M (VOM) costs, as well as costs incurred on a non-annual, periodic basis (3-year, 5-year, 6-year, 10-
year) into IPM as FOM and VOM cost adders. IPM modelers calculated the net present value of
annualized costs using IPM's conventional framework for recognizing costs incurred overtime, by
assigning to each cost the same technology implementation years discussed in Chapter 3.34
implementing technologies, and one run year falling after the compliance period. The regulatory options of this
proposal were analyzed using the run year 2030 only because unlike the 2015 rule analysis, the impacts associated with
these regulatory options were too small to warrant reporting based on two run years.
117 of these 121 plants are modeled in IPM. Coal generating units at the four remaining plants are not included in IPM,
due to retirements (see Chapter 2 for discussion of retirements). For example, one plant decommissioned its coal-fired
generating units in 2018 in anticipation of repowering to natural gas combustion turbines and IPM therefore does not
include these units. These retirements were not captured in updates to the universe of plants for which EPA estimated
costs. The costs described earlier in Chapters 3 and 4 accordingly overstate compliance costs ultimately modeled in
IPM. Estimated pre-tax compliance costs for the four plants omitted from IPM are $14.8 million under Option 4, or
3.6 percent of the total pre-tax costs for this option of $416.9 million. Omissions are smaller for Option 2, with omitted
pre-tax compliance costs of $7.6 million, or 2.9 percent of the total pre-tax costs for this option of $266.8 million.
IPM seeks to minimize the total, discounted net present value, of the costs of meeting demand, accounting for power
operation constraints, and environmental regulations over the entire planning horizon. These costs include the cost of
any new plant, pollution control construction, fixed and variable operating and maintenance costs, and fuel costs. As
described in the IPM documentation, "Capital costs in IPM's objective function are represented as the net present
value of levelized stream of annual capital outlays, not as a one-time total investment cost. The payment period used in
calculating the levelized annual outlays never extends beyond the model's planning horizon: it is either the book life of
the investment or the years remaining in the planning horizon, whichever is shorter. This approach avoids presenting
artificially lower capital costs for investment decisions taken closer to the model's time horizon boundary simply
because some of that cost would typically be serviced in years beyond the model's view. This treatment of capital costs
EPA-821-R-19-012
5-4

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
5: Electricity Market Analyses
5.1.2.2 New Capacity
The EPA did not specify ELG compliance costs for new coal capacity. IPM projections include new
generating capacity as needed to meet demand. As described below, IPM projects no new coal capacity
under the baseline or under the regulatory options.
5.1.3 Key Outputs of the Market Model Analysis Used in Assessing the Effects of the Regulatory Options
IPM generates a series of outputs at different levels of aggregation (model plant, region, and nation). For
this analysis, the EPA used a subset of the available IPM output for each model run (base case and each
analyzed regulatory option), focusing on metrics that quantify projected changes in capacity (including
early retirements and new capacity), generation, production costs, electricity prices, and emissions. See
Chapter 5 in the RIA document for the 2015 rule (U.S. EPA, 2015b) for descriptions of the IPM
variables.
The EPA compared national-level outputs for selected IPM run years (2021, 2023, 2025, 2030, 2040, and
2050).35 EPA then looked at changes in more detailed regional and plant-level outputs for the 2030 run
year. Comparison of these outputs for the baseline and policy cases provides insight into the incremental
effect of the regulatory options on steam electric power plants and the broader electric power markets.36
5.2 Findings from the Market Model Analysis
The impacts of the regulatory options are assessed as the difference between key economic and
operational impact metrics that compare the results for the policy cases to the baseline case. This section
presents two sets of analysis:
•	Analysis of national-level impacts: The EPA compared baseline and policy IPM results reported
for a series of run years to provide insight on the direction and magnitude of market-level changes
attributable to the regulatory options over time.
•	Analysis of long-term regulatory impacts: As discussed earlier, to assess the long-term impact of
the regulatory options, the EPA compared baseline and policy IPM results reported for 2030.
These results provide insight on the effect of the regulatory options both for the entire electricity
market and for steam electric power plants specifically.
5.2.1 National-level Analysis Results for Model Years 2021-2050
Table 5-2 shows baseline values of total costs to electric power plants, wholesale electricity price, total
existing capacity, new capacity, plant retirements, and generation mix at the national-level based on IPM
results for the Base Case. The baseline projections show a progressive decline in total coal generation
capacity during the period (from 176.4 GW in 2021 to 144.5 GW in 2050; 18 percent reduction) and
nuclear generation capacity (17 percent reduction), and increases in generation capacity from renewables,
natural gas, and other sources. These projections are consistent with the market trends discussed in
Section 2.3. Table 5-3 provides incremental changes in these measures for Options 2 and 4, relative to the
ensures both realism and consistency in accounting for the full cost of each of the investment options in the model."
(U.S. EPA, 2018a, page 2-7).
IPM also provides estimates for four additional run years: 2023, 2025, 2035, and 2045.
IPM output also includes total fuel usage, which is not part of the analysis discussed in this Chapter.
EPA-821-R-19-012
5-5

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
5: Electricity Market Analyses
baseline (negative values represent decreases relative to the baseline). For conciseness, the tables show
results for the years 2021, 2023, 2025, 2030, 2040, and 2050, but IPM V6 also provides projections for
model years 2035 and 2045.
Table 5-2: Baseline Projections, 2021-2050
Economic Measures
Baseline

2021
2023
2025
2030
2040
2050
Total Costs
Total Costs (million 2018$)
$135,820
$141,458
$145,980
$156,921
$179,174
$188,890
Prices
National Wholesale Electricity
33.40
38.39
39.22
42.96
44.79
45.28
Price (mills/kWh)






Total Capacity (Cumulative GW)
Renewables3
290.3
302.5
321.1
376.8
383.3
435.2
Coal
176.4
172.3
171.8
169.9
161.5
144.5
Nuclear
88.4
82.4
81.3
76.6
75.4
73.3
Natural Gas
407.7
414.9
415.5
425.8
509.6
622.0
Oil/Gas Steam
71.3
71.5
71.7
71.7
71.3
67.2
Other
9.6
9.6
11.1
12.5
12.5
12.8
Grand Total
1,043.7
1,053.3
1,072.6
1,133.3
1,213.7
1,355.1
New Capacity (Cumulative GW)
Renewables3
66.8
79.1
97.7
153.4
159.9
211.8
Coal
0.0
0.0
0.0
0.0
0.0
0.0
Nuclear
0.0
0.0
0.0
0.0
0.0
0.0
Natural Gas
2.2
9.5
10.1
20.7
104.5
217.0
Other
2.5
2.5
4.0
5.4
5.4
5.7
Grand Total
71.6
91.1
111.9
179.5
269.8
434.5
Retirements (GW)b
Combined Cycle Retirements
2.9
2.9
2.9
2.9
2.9
2.9
Coal Retirements
48.3
49.3
49.3
51.0
59.4
75.8
Combustion Turbine
1.6
1.6
1.6
1.9
1.9
1.9
Retirements






Nuclear Retirements
3.9
11.1
12.2
17.0
18.1
20.2
Oil/Gas Retirements
6.0
6.0
5.9
6.0
6.3
10.5
Grand Total
67.0
75.2
76.4
83.2
93.1
116.3
Generation Mix (thousand GWh

Renewables3
842.6
872.2
906.6
1,056.3
1,076.2
1,252.8
Coal
867.1
914.5
919.1
882.2
790.4
716.5
Nuclear
694.3
651.5
642.7
604.0
596.6
579.4
Natural Gas
1,576.1
1,593.5
1,613.8
1,656.4
2,026.8
2,303.3
Oil/Gas Steam
62.9
60.4
60.8
56.9
43.9
15.7
Other
35.3
35.8
36.3
37.0
37.5
37.6
Grand Total
4,078.4
4,127.8
4,179.2
4,292.8
4,571.3
4,905.2
a.	Renewables include hydropower and non-hydropower renewables.
b.	There were no changes in projected retirements for IGCC, biomass, fuel cell, other fossil fuel, geothermal, hydropower,
landfill gas, other non-fossil fuel, and energy storage plants.
Source: U.S. EPA Analysis, 2019
EPA-821-R-19-012
5-6

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
5: Electricity Market Analyses
Table 5-3: National Impact of Regulatory Options Relative to Baseline, 2021-2050
Economic
Option 2 Changes Relative to Baseline
Option 4 Changes Relative to Baseline
Measures
2021
2023
2025
2030
2040
2050
2021
2023
2025
2030
2040
2050
Total Costs
Total Costs (million
$)
-$193
-$260
-$187
-$140
-$53
$14
-$229
-$195
-$56
$4
$68
$24
Prices
National Wholesale
Electricity Price
(mills/kWh)
-0.08
-0.04
-0.02
-0.05
-0.01
0.01
-0.08
0.02
-0.03
-0.05
0.01
0.01
Total Capacity (Cumulative GW)
Renewables3
0.0
-1.1
-1.1
-0.4
-0.3
-0.4
0.0
-0.9
-0.9
-0.1
0.0
-0.3
Coal
1.2
1.2
1.2
1.1
0.7
0.8
0.8
0.8
0.8
0.7
0.4
0.9
Nuclear
0.0
0.0
0.0
-0.1
-0.1
-0.1
0.0
0.0
0.0
0.1
0.1
0.1
Natural Gas
0.0
0.0
0.1
-0.5
-0.3
-0.5
0.0
0.0
0.3
-0.5
-0.3
-0.9
Oil/Gas Steam
-0.2
-0.2
-0.2
-0.2
0.0
0.0
0.0
0.0
-0.1
-0.1
0.0
0.0
Other
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
Grand Total
1.1
-0.1
0.0
0.0
-0.1
-0.2
0.8
-0.1
0.1
0.1
0.1
-0.2
New Capacity (Cumulative GW)
Renewables3
0.0
-1.1
-1.1
-0.4
-0.3
-0.4
0.0
-0.9
-0.9
-0.1
0.0
-0.3
Coal
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
Nuclear
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
Natural Gas
0.0
-0.1
0.1
-0.6
-0.3
-0.5
0.0
0.0
0.3
-0.5
-0.3
-0.9
Other
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
Grand Total
0.0
-1.2
-1.1
-0.9
-0.7
-0.9
0.0
-0.9
-0.6
-0.6
-0.4
-1.2
Retirements
GW)b
Combined Cycle
Retirements
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
Coal Retirements
-1.2
-1.2
-1.2
-1.1
-0.7
-0.8
-0.8
-0.8
-0.8
-0.7
-0.4
-0.9
Combustion
Turbine
Retirements
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
Nuclear
Retirements
0.0
0.0
0.0
0.1
0.1
0.1
0.0
0.0
0.0
-0.1
-0.1
-0.1
Oil/Gas Retirements
0.2
0.2
0.2
0.2
0.0
0.0
0.0
0.0
0.1
0.1
0.0
0.0
Grand Total
-1.1
-1.1
-1.1
-0.9
-0.6
-0.7
-0.8
-0.8
-0.8
-0.7
-0.5
-1.0
Generation Mix (thousand GWh)
Renewables3
-0.1
-1.9
-1.8
-0.9
-0.8
-0.5
0.0
-1.6
-1.5
-0.4
0.0
-0.4
Coal
1.6
2.4
2.2
4.9
1.8
0.9
0.6
1.9
-0.9
1.4
-0.7
-1.6
Nuclear
0.0
0.0
0.0
-0.7
-0.7
-0.7
0.0
0.0
0.0
0.7
0.7
0.7
Natural Gas
-1.1
-0.2
-0.1
-3.3
0.0
0.4
-0.2
-0.2
2.4
-1.8
0.1
1.4
Oil/Gas Steam
-0.2
-0.1
-0.3
0.1
0.0
0.1
-0.2
-0.1
0.0
0.2
0.0
0.2
Other
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
-0.1
0.0
Grand Total
0.2
0.2
0.1
0.1
0.3
0.1
0.2
0.1
0.0
0.2
0.0
0.2
a.	Renewables include hydropower and non-hydropower renewables.
b.	There were no changes in projected retirements for IGCC, biomass, fuel cell, other fossil fuel, geothermal, hydropower,
landfill gas, other non-fossil fuel, and energy storage plants.
Source: U.S. EPA Analysis, 2019
EPA-821-R-19-012
5-7

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
5: Electricity Market Analyses
5.2.1.1	Findings for Regula tory Option 2
Under Option 2, total costs to electric power plants are projected to be lower than the baseline from 2021
to around 2040. The reduction in costs is greatest in the early years of the modeling period (e.g., by
$193.5 million in 2021), which is consistent with the timing of ELG implementation under the baseline
and the regulatory options. By the end of the modeling period in 2050, costs are projected to increase by
$13.6 million (0.01 percent of baseline costs). Similar to total costs relative to the baseline, IPM projects
changes in wholesale electricity prices between 2021 and 2040 between 0.0 and 0.1 mills per kWh.
Looking at results for total capacity by energy source, coal capacity is estimated to increase for all years
from 2021 to 2050 by 0.7 to 1.2 GW. The additional capacity under Option 2 is projected to come from
avoided retirements of existing units. As is the case of the baseline, no new coal capacity is projected.
Meanwhile, decreases in capacity from renewables, natural gas, and nuclear are estimated to occur from
around 2030 to 2050. Capacity from renewables is estimated to decrease by 0.3 to 0.4 GW, and natural
gas capacity is estimated to decrease by 0.3 to 0.5 GW, with both of these changes due to avoided new
capacity additions. The reduction in nuclear capacity in 2030-2050, by contrast, is projected to result from
incremental retirements of nuclear generation units, as they become relatively less economical to operate.
Avoided coal retirements are estimated for all years, ranging between 0.7 to 1.2 GW of the 1.8 GW
estimated to retire in the baseline. This accounts for most of the avoided retirements in the electric market
as a whole, which ranges between 0.6 to 1.1 GW.
Lastly, examining results for generation by energy source, generation from coal is estimated to increase
from 2021 to 2050 by 0.9 to 4.9 GWh, offset in part by a decline in generation by renewables (0.1 to 0.9
GW reduction) and natural gas generation, which decreases from 2021 to 2030 by 1.1 to 3.3 GW, then
increases after 2040 by 0.0 to 0.4.
5.2.1.2	Findings for Regula tory Option 4
Under Option 4, the reduction in total costs does not extend as long as under Option 2, which is consistent
with the timing and magnitude of compliance expenditures for this option as compared to the baseline.
Total costs for Option 4 decrease in 2021 by $228.6 million, then increase from 2030 to 2050 by
$4.0 million to $67.8 million. The decrease in wholesale electricity prices is similar in magnitude ($0.0 to
$0.1 per kWh) as Option 2, though it occurs for a shorter time period (2021-2030) before higher costs are
incurred.
As for total capacity by energy source, coal capacity is estimated to increase for all years, similar to
Option 2, but at lesser magnitudes of 0.4 to 0.9 GW. This increase is the result of avoided retirements (0.4
to 0.9 GW) since no new coal capacity is estimated under Option 4 from 2021-2030, and negligible new
capacity is estimated afterwards. Balancing out the increase in coal capacity, capacity from renewables
and natural gas are estimated to avoid 0.0 to 0.3 GW and 0.3 to 0.9 GW of new capacity between 2030
and 2050, respectively. For renewables, the decline is uniformly less than under Option 2 (0.0 to 0.3 GW
between 2030 and 2050). Avoided new capacity from natural gas shows similar trends, except for 2050
when natural gas is estimated to have greater avoided new capacity of 0.9 GW.
Coal generation increases from 2021-2030 by 0.6 to 1.4 GWh then decreases from 2040 to 2050 by 0.7 to
1.6 GWh. This is offset by a reduction in generation from renewables in all years by 0.0-0.4 GWh, and
EPA-821-R-19-012
5-8

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
5: Electricity Market Analyses
from natural gas from 2021 to 2030 by 0.2 to 1.8 GW, although natural gas then increases after 2040 by
0.1 to 1.4 GWh.
5.2.2 Detailed Analysis Results for Model Year2030
In the following results which reflect conditions in the period of 2028 through 2033, all plants are
estimated to meet the revised BAT limits and pretreatment standards associated with each analyzed
regulatory options. Forthis more detailed analysis, following the approach used for the 2015 rule (U.S.
EPA, 2015b), the EPA used parsed IPM outputs and considered impact metrics of interest at three levels
of aggregation:
•	Impact on national and regional electricity markets (Section 5.2.2.1),
•	Impact on steam electric power plants as a group (Section 5.2.2.2), and
•	Impact on individual steam electric power plants (Section 5.2.2.3).
5.2.2.1 Impact on National and Regional Electricity Markets
The market-level analysis assesses national and regional changes as a result of the regulatory
requirements. The EPA analyzed six measures:
•	Changes in available capacity. This measure analyzes changes in the nameplate capacity
available to generate electricity. A long-term reduction in available capacity may result from
partial or full closures of steam electric power plants. Conversely, increased capacity may result
from avoided partial or full closure of the plants or the addition of new capacity. Only capacity
that is projected to remain operational in the baseline case but is closed in the policy case is
considered a closure attributable to the regulatory option. The Market Model Analysis may
project partial (i.e.. unit) or full plant early retirements (closures) for a given regulatory option. It
may also project partial or full avoided closures in which a unit or plant that is estimated to close
in the baseline is estimated to continue operation in the policy case. Avoided closures may occur,
in particular, when the option results in lower costs for a given plant.
•	Changes in the wholesale price of electricity. This measure represents the change in the annual
average energy price (the marginal cost of meeting demand in each time segment, averaged
annually) plus any capacity prices associated with maintaining a reserve margin. In the long term,
electricity prices may change as a result of changes in generation costs at steam electric power
plants or due to generating unit and/or plant closures.
•	Changes in generation: This measure considers the amount of electricity generated. At a regional
level, long-term changes in generation may result from plant closures or a change in the amount
of electricity traded between regions. At the national level, the demand for electricity does not
change between the baseline and the analyzed policy options (generation within the regions is
allowed to vary) because meeting demand is an exogenous constraint imposed by the model.
However, demand for electricity does vary across the modeling horizon according to the model's
underlying electricity demand growth assumptions.
EPA-821-R-19-012
5-9

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
5: Electricity Market Analyses
•	Changes in costs: This measure considers changes in the overall cost of generating electricity,
including fuel costs, variable and fixed O&M costs, and capital costs. These costs are not limited
to steam electric generating units or to compliance costs of the regulatory options, but more
broadly reflect changes in the cost of generating electricity across all units. Fuel costs and
variable O&M costs are production costs that vary with the level of generation. Fuel costs
generally account for the single largest share of production costs. Fixed O&M costs and capital
costs do not vary with generation. They are fixed in the short-term and therefore do not affect the
dispatch decision of a unit (given sufficient demand, a unit will dispatch as long as the price of
electricity is at least equal to its per MWh production costs). However, in the long-run, these
costs need to be recovered for a unit to remain economically viable.
•	Changes in variable production costs per MWh: This measure considers the change in average
variable production cost per MWh. Variable production costs are a subset of the costs in the
bullet above and include fuel costs and other variable O&M costs but exclude fixed O&M costs
and capital costs. Production cost per MWh is a primary determinant of how often a generating
unit is dispatched. This measure presents similar information to total fuel and variable O&M
costs, but normalized for changes in generation.
•	Changes in CO2, NOx, SO2, Hg, andHCL emissions: This measure considers the change in
emissions resulting from electricity generation, for example due to changes in the fuel mix.
Compliance with the regulatory options is estimated to reduce generation costs when compared to
the baseline and make electricity generated by some steam electric units less expensive compared
to that generated at other steam electric or non-steam electric units. These changes may in turn
result in changes in air pollutant emissions, depending on the emissions profile of dispatched
units. Projected changes in air emissions are used as inputs for the analysis of air-related benefits
of the regulatory options (see Chapter 7 in the BCA document [U.S. EPA, 2019b]).
Table 5-4 summarizes IPM results for regulatory options at the level of the national market and also for
regional electricity markets defined on the basis of NERC regions. All of the impact metrics described
above are reported at both the national and NERC level except electricity prices, which are calculated in
IPM only at the regional level (i.e.. not aggregated to national level). Differences in the relative
magnitude of impacts across the NERC regions largely reflect regional differences in compliance costs
for the regulatory options as compared to the baseline (i.e., number of plants incurring costs and the
magnitude of these costs) and the generation mix.
Table 5-4: Impact of Regulatory Options on National and Regional Markets at the Year 2030
Economic Measures
(all dollar values in 2018$)
Baseline
Value
Option 2
Option 4
Value
Difference
% Change
Value
Difference
% Change
Nationa
Totals
Total Domestic Capacity (GW)
1,142
1,143
0.6
0.1%
1,144
1.4
0.1%
Existing

1.5
0.1%

2.0
0.2%
New Additions

-0.9
-0.1%

-0.6
-0.1%
Early Retirements

-1.5
-0.14%

-2.0
-0.2%
Wholesale Price ($/MWh)
$42.96
$42.90
-$0.05
-0.1%
$42.91
-$0.05
-0.1%
Generation (TWh)
4,286
4,287
0.1
0.0%
4,287
0.2
0.0%
EPA-821-R-19-012
5-10

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
5: Electricity Market Analyses
Table 5-4: Impact of Regulatory Options on National and Regional Markets at the Year 2030
Economic Measures
Baseline
Option 2
Option 4
(all dollar values in 2018$)
Value
Value
Difference
% Change
Value
Difference
% Change
Costs ($Millions)
$156,921
$156,781
-$140
-0.1%
$156,925
$4
0.0%
Fuel Cost
$69,971
$70,028
$57
0.1%
$69,991
$20
0.0%
Variable O&M
$10,261
$10,263
$2
0.0%
$10,307
$47
0.5%
Fixed O&M
$52,916
$52,834
-$82
-0.2%
$52,933
$17
0.0%
Capital Cost
$23,774
$23,657
-$117
-0.5%
$23,694
-$79
-0.3%
Variable Production Cost ($/MWh)
$18.72
$18.73
$0.01
0.1%
$18.73
$0.01
0.1%
C02 Emissions (Million Metric







Tons)
1,581
1,585
3.9
0.2%
1,582
1.2
0.1%
Mercury Emissions (Tons)
4
4
0.0
0.4%
4
0.0
0.1%
NOx Emissions (Million Tons)
1
1
0.0
0.5%
1
0.0
0.1%
S02 Emissions (Million Tons)
1
1
0.0
0.6%
1
0.0
0.2%
HCL Emissions (Million Tons)
0
0
0.0
0.5%
0
0.0
0.1%
Florida Reliability Coordinating Council (FRCC)
Total Domestic Capacity (GW)
59
59
0.0
0.0%
59
0.0
-0.1%
Existing
1 1 °'°
0.0%

0.0
0.0%
New Additions
00
0.0%

0.0
-0.1%
Early Retirements
1 1 o.o
0.0%

0.0
0.0%
Wholesale Price ($/MWh)
$46.41
$46.41
$0.00
0.0%
$46.42
$0.01
0.0%
Generation (TWh)
256
256
0
0.0%
256
0
-0.1%
Costs ($Millions)
$10,411
$10,404
-$7
-0.1%
$10,409
-$2
0.0%
Fuel Cost
$6,662
$6,661
-$1
0.0%
$6,659
-$3
0.0%
Variable O&M
$605
$605
$0
0.1%
$608
$4
0.6%
Fixed O&M
$2,643
$2,638
-$4
-0.2%
$2,646
$3
0.1%
Capital Cost
$502
$499
-$3
-0.6%
$496
-$5
-1.1%
Variable Production Cost ($/MWh)
$28.39
$28.40
$0.01
0.0%
$28.42
$0.02
0.1%
C02 Emissions (Million Metric







Tons)
97
97
-0.1
-0.1%
97
-0.1
-0.1%
Mercury Emissions (Tons)
0
0
0.0
-0.1%
0
0.0
-0.1%
NOx Emissions (Million Tons)
0
0
0.0
0.0%
0
0.0
-0.1%
S02 Emissions (Million Tons)
0
0
0.0
-0.7%
0
0.0
-1.2%
HCL Emissions (Million Tons)
0
0
0.0
-0.4%
0
0.0
-0.4%
Midwest Reliability Organization (MRO)
Total Domestic Capacity (GW)
68
68
-0.1
-0.1%
68
-0.1
-0.1%
Existing
1 1 °'°
0.0%

0.0
0.0%
New Additions
"01
-0.1%

-0.1
-0.1%
Early Retirements
1 1 o.o
0.0%

0.0
0.0%
Wholesale Price ($/MWh)
$40.89
$40.76
-$0.13
-0.3%
$40.76
-$0.14
-0.3%
Generation (TWh)
272
272
0
0.1%
272
0
0.0%
Costs ($Millions)
$8,822
$8,821
-$2
0.0%
$8,826
$3
0.0%
Fuel Cost
$3,651
$3,659
$8
0.2%
$3,655
$4
0.1%
Variable O&M
$763
$761
-$2
-0.2%
$766
$3
0.4%
Fixed O&M
$2,890
$2,887
-$3
-0.1%
$2,892
$2
0.1%
Capital Cost
$1,518
$1,513
-$5
-0.3%
$1,513
-$5
-0.4%
Variable Production Cost ($/MWh)
$16.23
$16.24
$0.01
0.1%
$16.25
$0.02
0.1%
C02 Emissions (Million Metric







Tons)
134
134
0.4
0.3%
134
0.2
0.2%
Mercury Emissions (Tons)
0
0
0.0
0.3%
0
0.0
0.2%
NOx Emissions (Million Tons)
0
0
0.0
1.1%
0
0.0
0.1%
EPA-821-R-19-012
5-11

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
5: Electricity Market Analyses
Table 5-4: Impact of Regulatory Options on National and Regional Markets at the Year 2030
Economic Measures
Baseline
Option 2
Option 4
(all dollar values in 2018$)
Value
Value
Difference
% Change
Value
Difference
% Change
S02 Emissions (Million Tons)
0
0
0.0
0.7%
0
0.0
0.1%
HCL Emissions (Million Tons)
0
0
0.0
0.3%
0
0.0
0.2%
Northeast Power Coordinating Council (NPCC)
Total Domestic Capacity (GW)
80
80
-0.1
-0.2%
80
0.0
0.0%
Existing

| -0.1
-0.2%

0.0
0.0%
New Additions
1 1 00
0.0%|
0.0
0.0%
Early Retirements
1 1 o.i
0.2%|
0.0
0.0%
Wholesale Price ($/MWh)
$42.47
$42.48
$0.00
0.0%
$42.46
-$0.01
0.0%
Generation (TWh)
238
238
0
0.0%
238
0
0.0%
Costs ($Millions)
$9,840
$9,841
$1
0.0%
$9,842
$2
0.0%
Fuel Cost
$3,343
$3,345
$2
0.1%
$3,346
$2
0.1%
Variable O&M
$390
$391
$0
0.1%
$391
$0
0.1%
Fixed O&M
$3,748
$3,747
-$1
0.0%
$3,749
$0
0.0%
Capital Cost
$2,359
$2,358
-$1
0.0%
$2,358
-$1
0.0%
Variable Production Cost ($/MWh)
$15.67
$15.68
$0.01
0.0%
$15.68
$0.01
0.0%
C02 Emissions (Million Metric







Tons)
47
47
0.0
0.1%
47
0
0.1%
Mercury Emissions (Tons)
0
0
0.0
0.0%
0
0
0.0%
NOx Emissions (Million Tons)
0
0
0.0
0.0%
0
0
0.1%
S02 Emissions (Million Tons)
0
0
0.0
0.0%
0
0
0.0%
HCL Emissions (Million Tons)
0
0
0.0
0.0%
0
0
0.0%
ReliabilityFirst Corporation (RFC)
Total Domestic Capacity (GW)
223
223
-0.4
-0.2%
223
0.0
0.0%
Existing
1 1 o.o
0.0%

0.3
0.1%
New Additions
-0.5
-0.2%|
-0.4
-0.2%
Early Retirements
1 1 o.o
0.0%|
-0.3
-0.1%
Wholesale Price ($/MWh)
$41.07
$41.04
-$0.03
-0.1%
$41.07
-$0.01
0.0%
Generation (TWh)
928
927
-1
-0.1%
927
-1
-0.1%
Costs ($Millions)
$35,545
$35,434
-$111
-0.3%
$35,469
-$77
-0.2%
Fuel Cost
$15,878
$15,882
$3
0.0%
$15,850
-$28
-0.2%
Variable O&M
$2,470
$2,469
-$1
0.0%
$2,480
$11
0.4%
Fixed O&M
$12,112
$12,047
-$65
-0.5%
$12,088
-$25
-0.2%
Capital Cost
$5,085
$5,036
-$49
-1.0%
$5,050
-$35
-0.7%
Variable Production Cost ($/MWh)
$19.78
$19.80
$0.02
0.1%
$19.78
$0.01
0.0%
C02 Emissions (Million Metric







Tons)
404
405
0.9
0.2%
403
-1
-0.3%
Mercury Emissions (Tons)
1
1
0.0
0.5%
1
0
-0.4%
NOx Emissions (Million Tons)
0
0
0.0
0.1%
0
0
-0.4%
S02 Emissions (Million Tons)
0
0
0.0
0.1%
0
0
-0.3%
HCL Emissions (Million Tons)
0
0
0.0
0.3%
0
0
-0.8%
Southeast Electric Reliability Council (SERC)
Total Domestic Capacity (GW)
273
274
1.4
0.5%
275
1.6
0.6%
Existing

1.7
0.6%

1.7
0.6%
New Additions

-0.3
-0.1%

0.0
0.0%
Early Retirements

-1.7
-0.6%

-1.7
-0.6%
Wholesale Price ($/MWh)
$43.72
$43.56
-$0.16
-0.4%
$43.56
-$0.16
-0.4%
Generation (TWh)
1,132
1,133
1
0.1%
1,134
1
0.1%
EPA-821-R-19-012
5-12

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
5: Electricity Market Analyses
Table 5-4: Impact of Regulatory Options on National and Regional Markets at the Year 2030
Economic Measures
Baseline
Option 2
Option 4
(all dollar values in 2018$)
Value
Value
Difference
% Change
Value
Difference
% Change
Costs ($Millions)
$43,758
$43,756
-$3
0.0%
$43,838
$79
0.2%
Fuel Cost
$21,512
$21,537
$25
0.1%
$21,536
$23
0.1%
Variable O&M
$2,684
$2,688
$4
0.2%
$2,712
$28
1.0%
Fixed O&M
$15,895
$15,901
$5
0.0%
$15,939
$43
0.3%
Capital Cost
$3,667
$3,630
-$37
-1.0%
$3,652
-$15
-0.4%
Variable Production Cost ($/MWh)
$21.37
$21.38
$0.01
0.0%
$21.39
$0.02
0.1%
C02 Emissions (Million Metric







Tons)
419
421
2.2
0.5%
421
2
0.5%
Mercury Emissions (Tons)
1
1
0.0
1.3%
1
0
0.9%
NOx Emissions (Million Tons)
0
0
0.0
1.1%
0
0
0.9%
S02 Emissions (Million Tons)
0
0
0.0
0.9%
0
0
0.9%
HCL Emissions (Million Tons)
0
0
0.0
1.8%
0
0
1.6%
Southwest Power Pool (SPP)
Total Domestic Capacity (GW)
79
79
-0.1
-0.1%
79
0.0
0.0%
Existing
1 1 °'°
0.0%

0.0
0.0%
New Additions
"01
-0.1%

0.0
0.0%
Early Retirements
1 1 o.o
0.0%

0.0
0.0%
Wholesale Price ($/MWh)
$40.81
$40.79
-$0.02
-0.1%
$40.77
-$0.04
-0.1%
Generation (TWh)
269
269
0
0.0%
269
0
0.0%
Costs ($Millions)
$8,476
$8,460
-$16
-0.2%
$8,473
-$3
0.0%
Fuel Cost
$4,135
$4,144
$9
0.2%
$4,135
$0
0.0%
Variable O&M
$765
$765
$1
0.1%
$766
$1
0.2%
Fixed O&M
$2,658
$2,647
-$10
-0.4%
$2,654
-$4
-0.2%
Capital Cost
$918
$903
-$15
-1.7%
$918
-$1
-0.1%
Variable Production Cost ($/MWh)
$18.22
$18.26
$0.04
0.2%
$18.22
$0.01
0.0%
C02 Emissions (Million Metric







Tons)
132
132
0.3
0.2%
132
0
0.0%
Mercury Emissions (Tons)
0
0
0.0
0.2%
0
0
0.0%
NOx Emissions (Million Tons)
0
0
0.0
0.3%
0
0
0.1%
S02 Emissions (Million Tons)
0
0
0.0
0.1%
0
0
0.0%
HCL Emissions (Million Tons)
0
0
0.0
0.2%
0
0
0.0%
Electric Reliability Organization of Texas (TRE)
Total Domestic Capacity (GW)
119
119
0.0
0.0%
119
-0.1
-0.1%
Existing
1 1 °'°
0.0%

0.0
0.0%
New Additions
0.0
0.0%

-0.1
-0.1%
Early Retirements
1 1 0.0
0.0%

0.0
0.0%
Wholesale Price ($/MWh)
$40.69
$40.69
$0.00
0.0%
$40.69
-$0.01
0.0%
Generation (TWh)
416
416
0
0.0%
416
0
0.0%
Costs ($Millions)
$14,535
$14,531
-$4
0.0%
$14,529
-$6
0.0%
Fuel Cost
$7,121
$7,127
$6
0.1%
$7,136
$15
0.2%
Variable O&M
$855
$856
$1
0.1%
$857
$1
0.2%
Fixed O&M
$4,690
$4,686
-$4
-0.1%
$4,685
-$5
-0.1%
Capital Cost
$1,869
$1,862
-$7
-0.4%
$1,852
-$17
-0.9%
Variable Production Cost ($/MWh)
$19.16
$19.17
$0.01
0.1%
$19.19
$0.04
0.2%
C02 Emissions (Million Metric







Tons)
149
149
0.1
0.1%
149
0
0.2%
Mercury Emissions (Tons)
0
0
0.0
0.1%
0
0
0.1%
NOx Emissions (Million Tons)
0
0
0.0
0.1%
0
0
0.2%
EPA-821-R-19-012
5-13

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
5: Electricity Market Analyses
Table 5-4: Impact of Regulatory Options on National and Regional Markets at the Year 2030
Economic Measures
Baseline
Option 2
Option 4
(all dollar values in 2018$)
Value
Value
Difference
% Change
Value
Difference
% Change
S02 Emissions (Million Tons)
0
0
0.0
2.8%
0
0
0.0%
HCL Emissions (Million Tons)
0
0
0.0
0.2%
0
0
0.1%
Western Electricity Coordinating Council (WECC)
Total Domestic Capacity (GW)
241
241
0.0
0.0%
241
0.0
0.0%
Existing

| 0.0
0.0%

0.0
0.0%
New Additions
1 1 00
0.0%|
0.0
0.0%
Early Retirements
1 1 0.0
0.0%|
0.0
0.0%
Wholesale Price ($/MWh)
$46.53
$46.55
$0.02
0.0%
$46.53
$0.00
0.0%
Generation (TWh)
775
775
0
0.0%
775
0
0.0%
Costs ($Millions)
$25,533
$25,536
$3
0.0%
$25,540
$7
0.0%
Fuel Cost
$7,668
$7,673
$4
0.1%
$7,674
$6
0.1%
Variable O&M
$1,729
$1,728
-$1
-0.1%
$1,728
-$1
-0.1%
Fixed O&M
$8,279
$8,279
$0
0.0%
$8,282
$3
0.0%
Capital Cost
$7,857
$7,856
$0
0.0%
$7,856
$0
0.0%
Variable Production Cost ($/MWh)
$12.12
$12.13
$0.00
0.0%
$12.13
$0.01
0.0%
C02 Emissions (Million Metric







Tons)
199
199
0.0
0.0%
199
0
0.0%
Mercury Emissions (Tons)
1
1
0.0
0.0%
1
0
0.1%
NOx Emissions (Million Tons)
0
0
0.0
0.1%
0
0
0.0%
S02 Emissions (Million Tons)
0
0
0.0
-0.1%
0
0
-0.1%
HCL Emissions (Million Tons)
0
0
0.0
0.0%
0
0
-0.1%
a. Numbers may not add up due to rounding.
Source: U.S. EPA Analysis, 2019
5.2.2.1.1 Findings for Regulatory Option 2
As reported in Table 5-4, the Market Model Analysis indicates that Option 2 would have small effects on
the electricity market, relative to the baseline, on both a national and regional sub-market basis, in the
year 2030.
At the national level, total annual costs decrease by an estimated $140 million (approximately 0.1
percent) relative to baseline. Total costs in the RFC region decline by the largest amount, $111 million
(0.3 percent), followed by the SPCC region with decreases of $16 million (0.2 percent); changes in
estimated total annual costs in the other regions range between savings of $7 million (FRCC) to increases
of $3 million (WECC). Overall at the national level, the net change in total capacity, including increases
in existing capacity (which includes avoided early retirements) and reductions in new plants/units, is an
increase of approximately 0.6 GW in capacity, which is about 0.1 percent of total market capacity.
Although effects differ geographically, Option 2 is estimated to have minimal effect on capacity
availability and supply reliability at the national level. Thus, the net capacity increase is a result of a gain
in capacity in the SERC region of about 1.4 GW (0.5 percent of SERC region capacity) due to a
combination of avoided early retirements and reduced new capacity additions, as well as losses in
capacity in the MRO, NPCC, RFC, and SPP totaling about 0.7 GW (ranging between 0.1 and 0.2 percent
of their regional capacities). The net losses in the MRO, RFC, and SPP regions are primarily due to the
avoided addition of new capacity. Overall impacts on wholesale electricity prices are similarly minimal.
Wholesale electricity prices are estimated to increase in some NERC regions, and fall in others. Price
EPA-821-R-19-012
5-14

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
5: Electricity Market Analyses
changes in individual regions range from -$0.16 per MWh (-0.4 percent) in SERC to $0.02 per MWh
(less than 0.1 percent) in WECC. Finally, at the national level, total costs decrease by approximately 0.1
percent. Total costs are estimated to decrease most in RFC, by 0.3 percent.
At the national level, there are increases in emissions among all air pollutants modeled. NOx emissions
increase by 0.5 percent; SO2 emissions increase by 0.6 percent; CO2 emissions increase by 0.2 percent,
mercury emissions increase by 0.4 percent; and HCL emissions increase by 0.5 percent. The impact on
emissions varies across regions and by pollutant. Emissions increase in some and decrease in other NERC
regions.37
5.2.2.1.2 Findings for Regulatory Option 4
Similar to the results for Option 2, Option 4 has small effects on the electricity market, on both a national
and regional sub-market basis, in the year 2030, despite higher compliance costs than under Option 2.
At the national level, total annual costs increase by $4 million (less than 0.1 percent) relative to baseline.
Most regions do not experience much change in costs, but total costs in RFC decrease by $77 million
(0.2 percent) while total costs in SERC increase by $79 million (0.2 percent). The net increase in total
capacity under Option 4 is 1.4 GW (0.1 percent of total market capacity). This increase is driven mainly
by the increase in capacity in SERC of 1.6 GW (0.6 percent of regional capacity), due to avoided
retirements. There are decreases in capacity of 0.1 GW in MRO (0.1 percent of regional capacity) and 0.1
GW in TRE (0.1 percent of regional capacity). Overall impact on wholesale electricity prices are also
small across NERC regions, with price changes ranging from -$0.16 per MWh (-0.1 percent) in SERC to
$0.01 per MWh (less than 0.1 percent) in FRCC.
The increase in emissions at the national level is smaller than under Option 2. NOx, CO2, mercury, and
HCL emissions all increase by 0.1 percent, and SO2 emissions increase by 0.2 percent. The impact on
emissions varies across regions and pollutants. Emissions increase in some and decrease in other NERC
regions.37
5.2.2.2 Impact on Steam Electric Power Plants as a Group
For the analysis of impact on steam electric power plants as a group, the EPA used the same IPM V6
results for 2030 used above to analyze the impact on national and regional electricity markets; however,
this analysis considers the effect of the regulatory options on the subset of plants to which the ELGs
apply, i.e., steam electric power plants. The purpose of the previously described electricity market-level
analysis is to assess the impact of the options analyzed in support of the regulatory options on the entire
electric power sector, i. e., including generators such as combustion turbines, wind or solar to which the
ELGs do not apply. By contrast, the purpose of this analysis is to assess the impact of the regulatory
options specifically on steam electric power plants. The analysis results for the group of steam electric
power plants overall show a slightly greater impact on a percentage basis than that observed over all
generating units in the IPM universe (i.e., market-level analysis discussed in the preceding section
[Impact on National and Regional Electricity Markets])', this is because, at the market level, impacts on
The changes in emissions only accounts for changes in the profile of electricity generation, and do not include
emissions associated with transportation or auxiliary power, which EPA analyzed separately (see Supplemental TDD
for details).
EPA-821-R-19-012
5-15

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
5: Electricity Market Analyses
steam electric units are offset by changes in capacity and energy production in the non-steam electric
units.
The metrics of interest are largely the same as those presented above in assessing the effect of the
regulatory options for the aggregate of the 686 steam electric power plants explicitly represented in IPM
(as opposed to additional steam electric power plants that were not surveyed by EPA in the Steam Electric
Survey[see U.S. EPA, 2015b]). In addition, a few measures differ: (1) new market-wide capacity
additions and prices are not relevant at the level of steam electric power plants, (2) changes in emissions
at only the 686 steam electric power plants provide incomplete insight for the overall estimated effect of
the rule on emissions and are therefore not presented, and (3) the number of steam electric power plants
with projected closure (or avoided closure) is presented.
The following four measures are reported in the analysis of steam electric power plants as a group. In all
instances, the measures are tabulated for 686 steam electric power plants explicitly included in the EPA's
Steam Electric Survey and analyzed in the Market Model Analysis (note that steam electric power plants
not included in the tabulation incur no compliance costs for the options the EPA analyzed in IPM):
•	Changes in available capacity: These changes are defined in the same way as in the preceding
section (Impact on National and Regional Electricity Markets), with the exception of the units
used (MW).
•	Changes in generation: Long-term changes in generation may result from either changes in
available capacity (see discussion above) or in the dispatch of a plant due to changes in
production cost resulting from compliance response.
•	Changes in costs: These changes are defined in the same way as in the preceding section (Impact
on National and Regional Electricity Markets).
•	Changes in variable production costs per MWh\ These changes are defined in the same way as in
the preceding section (Impact on National and Regional Electricity Markets).
Table 5-5 reports results of the Market Impact Analysis for steam electric power plants, as a group.
The impacts of the regulatory options on steam electric power plants differ from the total market impacts
as these plants become more competitive compared to plants that see no savings under the regulatory
options. As a result, capacity and generation impacts are greater for this set of plants than for the entire
electricity market, relative to the baseline, but absolute differences are still small. As described above for
the market-level analysis, those impacts vary across the NERC regions.
Table 5-5: Impact of Regulatory Options on In-Scope Plants, as a Group, at the Year 2030a
Economic Measures
Baseline
Option 2
Option 4
(all dollar values in 2018$)
Value
Value
Difference
% Change
Value
Difference
% Change
National Totals
Total Domestic Capacity
336,872
339,752
2,880
0.9%
340,066
3,194
0.9%
(MW)







Early Retirements -
79
79
0
0.0%
78
-1
-1.3%
Number of Plants







EPA-821-R-19-012
5-16

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
5: Electricity Market Analyses
Table 5-5: Impact of Regulatory Options on In-Scope Plants, as a Group, at the Year 2030a
Economic Measures
Baseline
Option 2
Option 4
(all dollar values in 2018$)
Value
Value
Difference
% Change
Value
Difference
% Change
Full & Partial Retirements
58,192
55,312
-2,880
-4.9%
54,998
-3,194
-5.5%
- Capacity (MW)







Generation (GWh)
1,570,513
1,575,189
4,676
0.3%
1,571,747
1,235
0.1%
Costs ($Millions)
$60,298
$60,397
$98
0.2%
$60,401
$103
0.2%
Fuel Cost
$34,842
$34,976
$134
0.4%
$34,893
$51
0.1%
Variable O&M
$5,987
$5,999
$12
0.2%
$6,040
$52
0.9%
Fixed O&M
$19,165
$19,117
-$48
-0.3%
$19,166
$1
0.0%
Capital Cost
$304
$304
$0
0.1%
$303
-$1
-0.3%
Variable Production Cost
$26.00
$26.01
$0.02
0.1%
$26.04
$0.05
0.2%
($/MWh)







Florida Reliability Coordinating Council (FRCC)
Total Domestic Capacity
27,584
27,584
0
0.0%
27,584
0
0.0%
(MW)







Early Retirements -
1
1
0
0.0%
1
0
0.0%
Number of Plants







Full & Partial Retirements
869
869
0
0.0%
869
0
0.0%
- Capacity (MW)







Generation (GWh)
126,731
126,692
-39
0.0%
126,676
-55
0.0%
Costs ($Millions)
$5,271
$5,266
-$5
-0.1%
$5,276
$5
0.1%
Fuel Cost
$3,631
$3,630
-$1
0.0%
$3,630
-$1
0.0%
Variable O&M
$317
$317
$0
0.0%
$320
$3
1.0%
Fixed O&M
$1,323
$1,319
-$4
-0.3%
$1,326
$3
0.2%
Capital Cost
$0
$0
$0
NA
$0
$0
NA
Variable Production Cost
$31.15
$31.15
$0.00
0.0%
$31.18
$0.03
0.1%
($/MWh)







Midwest Reliability Organization (MRO)
Total Domestic Capacity
24,324
24,324
0
0.0%
24,324
0
0.0%
(MW)







Early Retirements -
7
7
0
0.0%
7
0
0.0%
Number of Plants







Full & Partial Retirements
4,402
4,402
0
0.0%
4,402
0
0.0%
- Capacity (MW)







Generation (GWh)
139,319
139,622
303
0.2%
139,474
155
0.1%
Costs ($Millions)
$4,828
$4,832
$4
0.1%
$4,837
$9
0.2%
Fuel Cost
$2,760
$2,768
$8
0.3%
$2,764
$4
0.2%
Variable O&M
$647
$645
-$2
-0.3%
$650
$3
0.5%
Fixed O&M
$1,345
$1,343
-$3
-0.2%
$1,347
$2
0.2%
Capital Cost
$76
$76
$0
0.0%
$76
$0
-0.3%
Variable Production Cost
$24.45
$24.45
-$0.01
0.0%
$24.48
$0.02
0.1%
($/MWh)







Northeast Power Coordinating Council (NPCC)
Total Domestic Capacity
11,120
11,120
0
0.0%
11,120
0
0.0%
(MW)







Early Retirements -
3
3
0
0.0%
3
0
0.0%
Number of Plants







Full & Partial Retirements
2,708
2,708
0
0.0%
2,708
0
0.0%
- Capacity (MW)







Generation (GWh)
27,573
27,606
34
0.1%
27,614
41
0.1%
EPA-821-R-19-012
5-17

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
5: Electricity Market Analyses
Table 5-5: Impact of Regulatory Options on In-Scope Plants, as a Group, at the Year 2030a
Economic Measures
Baseline
Option 2
Option 4
(all dollar values in 2018$)
Value
Value
Difference
% Change
Value
Difference
% Change
Costs ($Millions)
$1,309
$1,310
$1
0.1%
$1,311
$1
0.1%
Fuel Cost
$608
$609
$1
0.1%
$609
$1
0.1%
Variable O&M
$43
$43
$0
0.1%
$43
$0
0.2%
Fixed O&M
$658
$658
$0
0.0%
$658
$0
0.1%
Capital Cost
$0
$0
$0
NA
$0
$0
NA
Variable Production Cost
$23.62
$23.63
$0.00
0.0%
$23.62
$0.00
0.0%
($/MWh)







ReliabilityFirst Corporation (RFC)
Total Domestic Capacity
76,002
76,016
14
0.0%
76,330
328
0.4%
(MW)







Early Retirements -
35
36
1
2.9%
35
0
0.0%
Number of Plants







Full & Partial Retirements
21,956
21,942
-14
-0.1%
21,628
-328
-1.5%
- Capacity (MW)







Generation (GWh)
364,667
365,423
756
0.2%
362,764
-1,903
-0.5%
Costs ($Millions)
$13,982
$13,951
-$30
-0.2%
$13,894
-$87
-0.6%
Fuel Cost
$8,038
$8,046
$8
0.1%
$7,983
-$54
-0.7%
Variable O&M
$1,606
$1,605
-$1
-0.1%
$1,614
$8
0.5%
Fixed O&M
$4,304
$4,265
-$38
-0.9%
$4,262
-$42
-1.0%
Capital Cost
$35
$36
$1
2.8%
$35
$1
2.1%
Variable Production Cost
$26.44
$26.41
-$0.04
-0.1%
$26.45
$0.01
0.0%
($/MWh)







Southeast Electric Reliability Council (SERC)
Total Domestic Capacity
103,935
106,801
2,866
2.8%
106,801
2,866
2.8%
(MW)







Early Retirements -
17
16
-1
-5.9%
16
-1
-5.9%
Number of Plants







Full & Partial Retirements
20,836
17,970
-2,866
-13.8%
17,970
-2,866
-13.8%
- Capacity (MW)







Generation (GWh)
479,646
482,880
3,235
0.7%
482,597
2,952
0.6%
Costs ($Millions)
$19,139
$19,265
$126
0.7%
$19,313
$173
0.9%
Fuel Cost
$11,129
$11,232
$103
0.9%
$11,222
$93
0.8%
Variable O&M
$1,630
$1,646
$15
0.9%
$1,668
$38
2.3%
Fixed O&M
$6,313
$6,320
$7
0.1%
$6,355
$42
0.7%
Capital Cost
$67
$67
$0
0.0%
$67
$0
0.0%
Variable Production Cost
$26.60
$26.67
$0.07
0.3%
$26.71
$0.11
0.4%
($/MWh)







Southwest Power Pool (SPP)
Total Domestic Capacity
26,885
26,885
0
0.0%
26,885
0
0.0%
(MW)







Early Retirements -
3
3
0
0.0%
3
0
0.0%
Number of Plants







Full & Partial Retirements
1,879
1,879
0
0.0%
1,879
0
0.0%
- Capacity (MW)







Generation (GWh)
116,430
116,717
288
0.2%
116,338
-91
-0.1%
EPA-821-R-19-012
5-18

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
5: Electricity Market Analyses
Table 5-5: Impact of Regulatory Options on In-Scope Plants, as a Group, at the Year 2030a
Economic Measures
Baseline
Option 2
Option 4
(all dollar values in 2018$)
Value
Value
Difference
% Change
Value
Difference
% Change
Costs ($Millions)
$4,394
$4,395
$1
0.0%
$4,388
-$6
-0.1%
Fuel Cost
$2,635
$2,642
$7
0.3%
$2,633
-$3
-0.1%
Variable O&M
$582
$582
$0
0.1%
$583
$1
0.1%
Fixed O&M
$1,163
$1,156
-$6
-0.5%
$1,158
-$4
-0.4%
Capital Cost
$15
$15
$0
0.4%
$14
$0
-1.1%
Variable Production Cost
$27.63
$27.63
$0.00
0.0%
$27.64
$0.01
0.0%
($/MWh)







Texas Regional Entity
(TRE)
Total Domestic Capacity
25,945
25,945
0
0.0%
25,945
0
0.0%
(MW)







Early Retirements -
1
1
0
0.0%
1
0
0.0%
Number of Plants







Full & Partial Retirements
391
391
0
0.0%
391
0
0.0%
- Capacity (MW)







Generation (GWh)
114,229
114,369
140
0.1%
114,411
183
0.2%
Costs ($Millions)
$4,497
$4,498
$1
0.0%
$4,501
$3
0.1%
Fuel Cost
$2,499
$2,504
$4
0.2%
$2,506
$6
0.2%
Variable O&M
$441
$441
$1
0.1%
$442
$1
0.1%
Fixed O&M
$1,557
$1,553
-$3
-0.2%
$1,553
-$3
-0.2%
Capital Cost
$0
$0
$0
NA
$0
$0
NA
Variable Production Cost
$25.74
$25.75
$0.01
0.0%
$25.76
$0.02
0.1%
($/MWh)







Western Electricity Coordinating Council (WECC)
Total Domestic Capacity
41,077
41,077
0
0.0%
41,077
0
0.0%
(MW)







Early Retirements -
12
12
0
0.0%
12
0
0.0%
Number of Plants







Full & Partial Retirements
5,151
5,151
0
0.0%
5,151
0
0.0%
- Capacity (MW)







Generation (GWh)
201,919
201,879
-40
0.0%
201,872
-47
0.0%
Costs ($Millions)
$6,877
$6,878
$1
0.0%
$6,882
$5
0.1%
Fuel Cost
$3,541
$3,545
$4
0.1%
$3,547
$5
0.2%
Variable O&M
$721
$720
-$1
-0.2%
$720
-$1
-0.1%
Fixed O&M
$2,502
$2,502
$0
0.0%
$2,504
$2
0.1%
Capital Cost
$112
$111
-$1
-0.6%
$110
-$1
-1.2%
Variable Production Cost
$21.11
$21.13
$0.01
0.1%
$21.14
$0.03
0.1%
($/MWh)







a. Numbers may not add up due to rounding.
Source: U.S. EPA Analysis, 2019.
5.2.2.2.1 Findings for Regulatory Option 2 in the 2030 Model Year
Under Option 2, the magnitude of the net increase in steam electric capacity is greater than the capacity
increase for the electricity market as a whole, although the change in capacity for the group of steam
electric power plants is still small at less than one percent.
EPA-821-R-19-012
5-19

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
5: Electricity Market Analyses
For the group of steam electric power plants, total capacity increases by 2,880 MW or approximately
0.9 percent of the 336,872 MW in baseline capacity. This increase is almost entirely attributable to
avoided retirements in the SERC region of 2,866 MW (13.8 percent), and also avoided retirements in
RFC of 14 MW (0.1 percent). RFC is the only region where a plant is projected to close under Option 2
(though this impact is indirectly the result of the regulatory option since the affected plant does not incur
ELG compliance costs under this option), and one plant in SERC is estimated to avoid a full retirement,
resulting in no net change in early full retirements at the national level.
The change in total generation is an indicator of how steam electric power plants fare, relative to the rest
of the electricity market. While at the market level there is essentially no projected change in total
electricity generation,38 for steam electric power plants, total generation is estimated to increase by 4,676
GWh (0.3 percent). SERC is projected to experience the largest increase in generation, 3,235 GWh (0.7
percent), while MRO, NPCC, RFC, SPP, and TRE are estimated to experience increases of 0.1 to 0.2
percent. FRCC and WECC are projected to experience negligible decreases in generation.
Unlike the results for the whole electricity market, where total costs are estimated to decrease under
Option 2 at the national level, the results for the group of steam electric power plants show a net increase
in total costs of $98 million (0.2 percent), which is estimated given the increase in electricity generated by
the group of plants. Total costs in the regions also follow the increases in electricity generation with costs
in SERC increasing the most, by $126 million (0.7 percent), MRO and NPCC experiencing smaller
increases of 0.1 percent, and FRCC and RFC experiencing decreases of 0.1 and 0.2 percent respectively.
At the national level, variable production costs for steam electric power plants increase by $0.02 per
MWh (0.1 percent). Effects vary by region, with changes ranging from -$0.04 per MWh in RFC to $0.07
per MWh in SERC.
5.2.2.2.2 Findings for Regulatory Option 4 in the 2030 Model Year
Results at the national level for steam electric power plants under Option 4 show an increase in total
capacity of 3,194 MW (0.9 percent), slightly higher than the increase under Option 2. Unlike under
Option 2, no plants are estimated to undergo a full retirement in any region, while there is still one plant
estimated to avoid retirement in SERC (same as under Option 2), resulting in the net avoided closure of
one plant at the national level. This avoided closure combined with capacity from avoided partial
retirements in SERC and RFC comprise the increase in capacity at the national level.
There is an increase in total generation at the national level under Option 4 of 1,235 GWh (0.1 percent),
which is smaller in magnitude than the increase under Option 2. There is more variability across the
regions in the changes in generation under Option 4 than Option 2. Total generation is projected to
decrease by 1,903 GWh (0.5 percent) in RFC, whereas it is projected to increase by 2,952 GWh (0.6
percent) in SERC. SPP is also projected to experience a decrease in generation of 91 GWh (0.1 percent).
MRO and NPCC are estimated to experience increases in generation of 0.1-0.2 percent. As in Option 2,
FRCC and WECC are estimated to experience negligible declines in generation.
At the national level, the demand for electricity does not change between the baseline and the analyzed regulatory
options (generation within the regions is allowed to vary) because meeting demand is an exogenous constraint imposed
by the model.
EPA-821-R-19-012
5-20

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
5: Electricity Market Analyses
At the national level, the magnitude in the net increase in total costs under Option 4, $103 million (0.2
percent), is similar to the magnitude under Option 2 and follows changes in generation. Total costs in the
SERC regions increase of the most with $173 million (0.9 percent) and RFC costs show the decrease with
$87 million (0.6 percent). Variable production costs at the national level are estimated to increase by
$0.05 per MWh (0.2 percent), which is slightly higher than under Option 2. The highest increase is in
SERC, with an increase of $0.11 per MWh (0.4 percent), whereas the other NERC regions experience
increases between zero and 0.1 percent.
5.2.2.3 Impact on Individual Steam Electric Power Plants
Results for the group of steam electric power plants as a whole may mask shifts in economic performance
among individual steam electric power plants. To assess potential plant-level effects, the EPA analyzed
the distribution of plant-specific changes between the baseline and the regulatory options for three
metrics: capacity utilization,39 electricity generation, and variable production costs per MWh.40
Table 5-6 presents the estimated number of steam electric power plants with specific degrees of change in
operations and financial performance as a result of the regulatory options. Metrics of greatest interest for
assessing the adverse impacts of the regulatory options on steam electric power plants include the number
of plants with reductions in capacity utilization or generation (on the left side of the table), and the
number of plants with increases in variable production costs (on the right side of the table).
This table excludes steam electric power plants with estimated significant status changes in 2030 that
render these metrics of change not meaningful - i.e., a plant is assessed as either a full, partial, or avoided
closure in either the baseline or the regulatory option. The measures presented in Table 5-5, such as
change in electricity generation, are not meaningful for these plants. For example, for a plant that is
projected to close in the baseline but avoids closure under the regulatory option, the percent change in
electricity generation relative to baseline cannot be calculated. On this basis, 281 and 280 plants are
excluded from assessment of effects on individual steam electric power plants under Options 2 and 4,
respectively. In addition, the change in variable production cost per MWh of generation could not be
developed for 38 plants with zero generation in either the baseline or under Options 2 and 4 (because the
divisor, MWh, is zero). For change in variable production cost per MWh, these plants are recorded in the
"N/A" column.
Capacity utilization is defined as generation divided by capacity times 8,760 hours.
Variable production costs per MWh is defined as variable O&M cost plus fuel cost divided by net generation projected
inlPM.
EPA-821-R-19-012
5-21

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
5: Electricity Market Analyses
Table 5-6: Impact of Regulatory Options on Individual In-Scope Plants at the Year 2030


Reduction

Increase



>1% and



>1% and


Economic Measures
>3%
<3%
<1%
No Change
<1%
<3%
>3%
N/Abc
Option 2
Change in Capacity








Utilization3
4
5
44
277
63
9
3
281
Change in Generation
17
9
27
277
43
14
18
281
Change in Variable








Production Costs/MWh
2
7
94
197
64
2
1
319
Option 4
Change in Capacity








Utilization3
5
8
50
278
54
8
3
280
Change in Generation
23
10
30
278
35
14
16
280
Change in Variable








Production Costs/MWh
0
5
75
208
70
9
1
318
a.	The change in capacity utilization is the difference between the capacity utilization percentages in the baseline and policy
cases. For all other measures, the change is expressed as the percentage change between the baseline and policy values.
b.	Plants with operating status changes in either baseline or policy scenario have been excluded from general table calculations.
Thus, for Option 2, "N/A" reports 224 full and 52 partial baseline closures; 1 additional full closure as a result of the regulatory
option; and 1 avoided full and 3 avoided partial closures as a result of the regulatory option. For Option 4, "N/A" reports 224 full
and 52 partial baseline closures, and 1 avoided full and 3 avoided partial closures resulting from the option.
c.	The change in variable production cost per MWh could not be developed for 38 plants with zero generation in either the
baseline case or Options 2 or 4 policy cases.
Source: U.S. EPA Analysis, 2019
5.2.2.3.1	Findings for Regulatory Option 2 in Model Year 2030
For Option 2, the analysis of changes in individual plants indicates that most plants experience only slight
effects - i.e., no change or less than a one percent reduction or one percent increase. Only 9 plants (2
percent) are estimated to incur a reduction in capacity utilization of at least one percent and 26 plants (6
percent) incur a reduction in generation of at least one percent. Finally, only 3 plants (0.8 percent) are
estimated incur an increase in variable production costs of at least one percent.
5.2.2.3.2	Findings for Regulatory Option 4 in Model Year 2030
Under Option 4, the analysis indicates that most plants experience only slight effects, though these effects
are greater than for Option 2. Option 4 shows small reductions in capacity utilization and generation; only
13 plants (3 percent) incur more than a one percent reduction in capacity utilization and 33 plants (8
percent) experience a reduction in generation of at least one percent. Impacts on variable costs are larger
than for Option 2, but also modest. The increase in variable production costs is estimated to exceed one
percent for 10 plants (3 percent), 9 of which have an increase of at least one percent but less than three
percent. The vast majority of steam electric power plants have variable production costs that either don't
change or change by less than one percent.
5.3 Estimated Effects of the Regulatory Options on New Capacity
IPM results show no new coal-fired capacity projected during the analysis period. This continues to be the
case for Option 2 and Option 4.
EPA-821-R-19-012
5-22

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
5: Electricity Market Analyses
5.4 Uncertainties and Limitations
Despite the EPA's use of the best available information and data, the EPA's analyses of the electric power
market and the overall economic impacts of the regulatory options involve several sources of uncertainty:
•	Steam electric power plant response to changes in production costs: IPM includes information
about announced retirements only to the extent that there is a high degree of certainty about the
future implementation of the announced action (U.S. EPA, 2018a). To the extent that some
utilities' business strategy and integrated resource plans call for the retirement of coal generation
assets and transition toward other sources of energy such as renewables or natural gas that is
separate from the factors modeled in IPM, then IPM may overstate avoided retirements resulting
from cost savings under the regulatory options.
•	Demand for electricity. IPM assumes that electricity demand at the national level will not change
between the baseline and the analyzed options (generation within the regions is allowed to vary);
this constraint is exogenous to the model. IPM V6 embeds a baseline energy demand forecast that
is derived from the Department of Energy's Annual Energy Outlook 2018 (AEO2018). IPM does
not capture changes in demand that may result from electricity price changes associated with the
regulatory options (i.e.. demand is inelastic with respect to price). While this constraint may
underestimate total demand in policy options that have lower compliance costs relative to the
baseline, the EPA takes the position that relaxing the constraint would not affect the results
analyzed. As described in Section 5.2.1 and Section 5.2.2, the price changes associated with the
analyzed regulatory options in most NERC regions are less than $0.30 per MWh (0.5 percent).
The EPA therefore concludes that the assumption of inelastic demand-responses over these
changes in prices is reasonable.
•	Fuel prices: Prices of fuels (e.g., natural gas and coal) are determined endogenously within IPM.
IPM modeling of fuel prices uses both short- and long-term price signals to balance supply of,
and demand in, competitive markets for the fuel across the modeled time horizon. The model
relies on AEO2018's electric demand forecast for the US and employs a set of EPA assumptions
regarding fuel supplies and the performance and cost of electric generation technologies as well
as pollution controls. Differences in actual fuel prices relative to those modeled by IPM, such as
lower natural gas prices that may result from increased domestic production, would be estimated
to affect the cost of electricity generation and therefore the amount of electricity generated by
steam electric power plants, irrespective of the regulatory options. More generally, differences in
fuel prices, and related changes in electricity production costs, can affect the modeled dispatch
profiles, planning for new/repowered capacity, and contribute to differences in a number of
policy-relevant parameters such as electricity production costs, prices, and emission changes.
? International imports: IPM assumes that imports from Canada and Mexico do not change
between the baseline and the options. Holding international imports fixed potentially understates
the impacts of changes in production costs and electricity prices in U.S. domestic markets. The
EPA does not expect that this assumption materially affects results, however, since IPM projects
that only one of the eight NERC regions will import electricity (WECC) in 2030, and the level of
imports compared to domestic generation in this region is very small (about 0.8 percent).
EPA-821-R-19-012
5-23

-------
RIA for Proposed Revisions to Steam Electric Power Generating ELGs
6: Employment Effects
6 Assessment of the Impact of the Regulatory Options on
Employment
6.1 Background and Context
In addition to addressing the costs and impacts of the regulatory options, the EPA discusses the potential
impacts of this rulemaking on employment in this section. Such an analysis is of interest given the broad
policy objective stated in Executive Order 13563: "Our regulatory system must protect public health,
welfare, safety, and our environment while promoting economic growth, innovation, competitiveness, and
job creation." A discussion of compliance costs is included in Chapter 3 of this RIA.
In this Chapter, the EPA first provides an overview of the various ways that environmental regulation can
affect employment. The EPA then qualitatively describes potential employment impacts for coal-fired
steam electric power plants and pollution control suppliers. In addition, the EPA discusses labor effects
for coal mining and other energy sources.
6.1.1 Employment Impacts of Environmental Regulations
Employment impacts of environmental regulations are composed of a mix of potential declines and gains
in different sectors of the economy over time. Impacts on employment can vary according to labor market
conditions and may differ across occupations, industries, and regions. Isolating employment impacts of
regulation is a challenge, as they are difficult to disentangle from employment impacts caused by a wide
variety of ongoing concurrent economic changes.
If the U.S. economy is at full employment, even a large-scale environmental regulation is unlikely to have
a noticeable impact on aggregate net employment. Instead, labor in affected sectors would primarily be
reallocated from one productive use to another (e.g., from producing electricity or steel to producing high
efficiency equipment), and net national employment effects from environmental regulation would be
small and transitory (e.g., as workers move from one job to another). There may still be employment
effects, negative and positive, for groups of affected workers, even if the overall net effect is small or
zero. Some workers may retrain or relocate in anticipation of new requirements or require time to search
for new jobs, while shortages in some sectors or regions could bid up wages to attract workers. These
adjustment costs can lead to local labor disruptions in the short term. Although the net change in the
national workforce is estimated to be small under conditions of full employment, localized reductions in
employment may adversely impact individuals and communities just as localized increases may have
positive impacts.
An environmental regulation affecting the steam electric industry is estimated to have a variety of
employment impacts. Transitional impacts include reduced employment at retiring coal-fired plants, as
well as increased employment for the manufacture, installation, and operation of pollution control
equipment and construction of new generation sources to replace retiring units (Schmalensee and Stavins,
2011). Other employment impacts include effects on labor supply and productivity resulting from changes
in pollution, as well as effects on labor demand in generation of energy from other sources, such as
natural gas and renewable energy.
EPA-821-R-19-012
6-1

-------
RIA for Proposed Revisions to Steam Electric Power Generating ELGs
6: Employment Effects
6.1.2	Current State of Knowledge Based on the Peer-Reviewed Literature
While there is an extensive empirical, peer-reviewed literature analyzing the effect of environmental
regulations on various economic outcomes including productivity, investment, competitiveness as well as
environmental performance, there are no known studies on environmental deregulation's effects on
employment, and only a few papers that examine the impact of more stringent environmental regulation
on employment. However, this area of the literature has been growing. Berman and Bui (2001) suggest
that new or more stringent environmental regulations do not have a substantial impact on net employment
(either negative or positive) in the regulated sector. Similarly, Ferris, Shadbegian, and Wolverton (2014)
also find that regulation-induced net employment impacts are close to zero in the regulated sector.
Furthermore, Gray et al. (2014) find that pulp mills that had to comply with both the air and water
regulations in EPA's 1998 "Cluster Rule" experienced relatively small and not always statistically
significant, decreases in employment. Nevertheless, other empirical research suggests that regulation can
have negative impacts on jobs. Sheriff et al. (2019) find negative impacts on employment at electric
utilities from ozone regulations, but without changes in electricity generation, suggesting a labor-saving
technical change. Results from Greenstone (2002) and Walker (2011, 2013) also suggest that more highly
regulated counties may generate fewer jobs than less regulated ones. However, the methodology used in
these two studies cannot estimate whether aggregate employment is lower or higher due to more stringent
environmental regulation, it can only imply that relative employment growth in some sectors differs
between more and less regulated areas. List et al. (2003) find some evidence that this type of geographic
relocation, from more regulated areas to less regulated areas may be occurring. Overall, the peer-reviewed
literature does not contain evidence that environmental regulation has a large impact on net employment
(either negative or positive) in the long run across the whole economy.
6.1.3	Labor Supply and Macroeconomic Net Employment Effects
As described above, the small empirical literature on employment effects of environmental regulations
focuses primarily on labor demand impacts. However, there is nascent literature focusing on regulation-
induced effects on labor supply, though this literature remains very limited due to empirical challenges.
This new research uses innovative methods and new data, and indicates that there may be observable
impacts of environmental regulation on labor supply, even at pollution levels below mandated regulatory
thresholds. Many researchers have found that lost workdays and sick days as well as mortality are
reduced when pollution is reduced, although the studies focus specifically on air quality. Another
literature estimates how worker productivity declines at the work site when pollution increases. Graff
Zivin and Neidell (2013) review the work in this literature, focusing on how health and human capital
may be affected by environmental quality, particularly air pollution. In previous research, Graff Zivin and
Neidell (2012) use detailed worker-level productivity data paired with local ozone air quality monitoring
data for one large California farm. They find "that ozone levels well below federal air quality standards
have a significant impact on productivity," with results showing that a 10 parts per billion (ppb) increase
in ozone concentrations decreases worker productivity by 5.5 percent. (Graff Zivin and Neidell, 2012, p.
3654). More recently, Chang et al. (2016) find that PM2 5 levels have significant effects on the
productivity of indoor workers. Their study examines workers at a pear packing factory in California and
find that a 10-unit change in PM2 5 leads to a decrease in worker productivity by about 6 percent. As most
of the economic output in the U.S. is produced indoors, the implications of this study are of potentially
greater magnitude than the earlier study on outdoor agricultural workers. Such studies are a compelling
start to exploring this new area of research, considering the benefits of improved environmental quality on
EPA-821-R-19-012
6-2

-------
RIA for Proposed Revisions to Steam Electric Power Generating ELGs
6: Employment Effects
productivity, alongside the existing literature exploring the labor demand effects of environmental
regulations.
The preceding has outlined the challenges associated with estimating net employment effects within the
regulated sector, in the environmental protection sector, and labor supply impacts. These challenges make
it difficult to accurately produce net employment estimates for the whole economy that would
appropriately capture the way in which costs, compliance spending, and environmental benefits propagate
through the macro-economy.
6.1.4 Distributional Considers Hons
In addition to macroeconomic considerations, the extent to which workers in declining industries will be
significantly affected by the proposed action, depends on such factors as the transferability of affected
workers' skills with shifting labor demand in different sectors due to the action, the availability of local
employment opportunities for affected workers in communities or industries with high unemployment,
and the extent to which migration costs serve as barriers to job search. This latter factor is a bigger
concern in areas with historically low migration rates.
On the other hand, dislocated workers operating in tight labor markets may have experienced relatively
brief periods of transitional unemployment. Some job seekers may find new employment opportunities
due to this proposed rule; for example, if their skill set qualified them for new jobs implementing heat rate
improvements.
Speaking more generally, localized reductions in employment may adversely affect individuals and
communities, just as localized increases may have positive effects (U.S. EPA, 2015a; p. 6-5). If
potentially dislocated workers are vulnerable, for example as those in Appalachia likely are, besides
experiencing persistent job loss as already mentioned, earnings can be permanently lowered, and the
wider community may be negatively affected. Communitywide effects can include effects on the local tax
base, the provision and quality of local public goods, and changes in demand for local goods and services.
Neighborhood effects, when people influence neighbors' behaviors, may be possible. As an example,
consider the influence that social networks can have on job acquisition. Many job vacancies are filled by
people who know an employee at the firm with the vacancy. This type of networking is weakened by high
unemployment rates (Durlauf, 2004).
6.2 Analysis Overview
6.2.1 Estimated Employment Effects in Coal-Fired Electric Power Plants Affected by the Regulatory
Options
The regulatory options would have two broad categories of effect on the coal-fired power plants:
1.	Coal-fired plants that are affected by the rule are estimated to install and operate compliance
technology that is less costly than the ELGs technology bases in the 2015 rule. To the extent that
some of these costs are driven by labor inputs, the savings may lead to decreased employment in
these plants compared to the baseline.
2.	Coal-fired plants may generate more electricity than would otherwise occur in the absence of the rule
due to decreased production costs. In addition, some plants may avoid retirement that would
EPA-821-R-19-012
6-3

-------
RIA for Proposed Revisions to Steam Electric Power Generating ELGs
6: Employment Effects
otherwise occur. These effects may lead to increased employment at coal fired power plants
compared to the baseline.
The EPA estimates that changes in employment may occur due to incorporation of different pollution
controls. As summarized in Chapter 3, the EPA estimated that annualized capital costs would be lower
under all four regulatory options compared to the baseline. Approximately 50-59 percent of the
annualized compliance costs for the regulatory options are annualized capital costs. These capital cost
savings are not estimated to significantly affect employment at steam electric power plants themselves,
but could decrease employment in industries that manufacture and install pollution control equipment.
The remaining cost savings consist of wastewater treatment O&M costs, including labor costs for the
maintenance, repair, and operations of treatment equipment. Options 1, 2, and 3 yield O&M cost savings
ranging from $19.0 million per year (Option 3) to $42.5 million per year (Option 2), on an after-tax basis.
Option 4 actually increases annualized O&M costs by $34 million. Some of these changes in O&M costs
savings could potentially affect employment in the steam electric power generating industry, but the
changes are small relative to overall electricity production costs.41
IPM projects that total coal-fired generating capacity is estimated to increase between 2021 and 2050 by
approximately 0.4-0.7 percent under Option 2 and 0.2-0.6 percent under Option 4.42 In addition, IPM
projects that in 2030, Option 2, would lead to avoided retirement of 1.1 GW (2.2 percent) of coal-fired
capacity, and Option 4 would lead to avoided retirement of 0.7 GW (1.4 percent). The direction of
estimated changes in coal-fired generation capacity projected by IPM indicates potential increase in total
O&M labor at coal-fired electricity plants, compared to the baseline. However, given the relatively small
effect of the regulatory options on total capacity and avoided generating unit retirements described above,
the EPA estimates any increase in labor in the steam electric generating industry to be small.
6.2.2 Coal Mining and Other Energy Sources
This analysis uses the results from IPM to discuss potential labor effects in the coal mining, natural gas
extraction, and non-hydro renewable generation. The IPM analysis of regulatory options provides
estimates of the changes in coal usage (in million short tons per year, or MT), natural gas usage (in trillion
cubic feet), and non-hydro renewable generation (in thousand GWh) in 2021-2050. IPM provides changes
in coal demand (in short tons) in three coal supply regions: Appalachia (Pennsylvania through
Mississippi), Interior (Indiana through Texas), and the West (North Dakota through Arizona).
IPM projects that coal use would increase by 0.1-0.4 percent under Option 2 from 2021-2050 relative to
the baseline. This could lead to a small overall increase in coal mining employment. However, changes in
coal use vary by region, with the West estimated to experience consistent increases over the period of
analysis (0.2 percent to 0.6 percent), while Appalachia and the Interior are estimated to experience
changes in coal use ranging from -0.5 percent to 1.7 percent and -0.3 percent to 0.4 percent, respectively,
during that period. Natural gas usage and non-hydro renewable generation is estimated to slightly
As summarized in Table 5-5, IPM projections for the model year 2030 show net reductions of 0.3 percent in fixed
O&M costs by steam electric power plants for Option 2 as compared to the baseline, and negligible changes (less than
0.1 percent) for Option 4.
See Chapter 5 for a description of the IPM analysis and results.
EPA-821-R-19-012
6-4

-------
RIA for Proposed Revisions to Steam Electric Power Generating ELGs
6: Employment Effects
decrease overall under Option 2 relative to the baseline, which may lead to declines in employment in the
extraction and generation of energy from these other sources.
Under Option 4, IPM projects that the direction of coal use changes would vary, with changes ranging
between -0.2 percent and 0.2 percent. Effects vary by region, with fluctuations between negative and
positive in Appalachia, the Interior, and the West. As a result, it is unclear what the employment impact
on coal mining would be under Option 4. Since natural gas usage and non-hydro renewable generation
similarly fluctuate, it is also unclear what to expect regarding employment impacts in these other sectors.
6.3 Findings
In conclusion, analyzing how environmental regulations will impact net employment is a difficult task,
requiring consideration of labor demand in both the regulated and environmental protection sectors.
Economic theory predicts that the total effect of an environmental regulation on labor demand in
regulated sectors is not necessarily positive or negative. Peer-reviewed econometric studies that use a
structural approach, applicable to overall net effects in the regulated sectors, converge on the finding that
such effects, whether positive or negative, have been small and have not affected employment in the
national economy in a significant way. Overall, effects of the regulatory options on O&M labor demand
at coal-fired steam electric power plants seem likely to be positive given the net increase in capacity and
generation in the steam electric power sector.
EPA-821-R-19-012
6-5

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
7: Electricity Price Effects
7 Assessment of Potential Electricity Price Effects
7.1 Analysis Overview
The EPA assessed the potential impacts of the regulatory options on electricity prices. Following the
methodology the EPA used to analyze the 2015 rule (U.S. EPA, 2015b), the Agency conducted this
analysis for the baseline and each of the four regulatory options in two parts:
•	An assessment of the potential annual increase in electricity costs per MWh of total electricity
sales (Section 7.2)
•	An assessment of the potential annual increase in household electricity costs (Section 7.3).
As is the case with the plant-level and parent entity-level cost-to-revenue screening analyses discussed in
Chapter 4 (Economic Impact Screening Analyses), this analysis of electricity price effects uses a
historical snapshot of electricity generation against which to assess the relative impacts of the regulatory
options. However, unlike the plant- and entity-level screening analyses which assume that steam electric
power plants and their parent entities would absorb 100 percent of the compliance burden (zero cost pass-
through), this electricity price impact assessment assumes the opposite: 100 percent pass-through of
compliance costs through electricity prices (i.e., full cost pass-through).
Although this convenient analytical simplification does not reflect actual market conditions,43 the EPA
judges this assumption appropriate for two reasons: (1) the majority of steam electric power plants
operate in the cost-of-service framework and may be able to recover increases in their production costs
through increased electricity prices and (2) for plants operating in states where electric power generation
has been deregulated, it would not be possible to estimate this consumer price effect at the state level.
Thus, this 100 percent cost pass-through assumption represents a "worst-case" impact scenario from the
perspective of the electricity consumers. To the extent that all compliance-related costs are not passed
forward to consumers but are absorbed, at least in part, by electric power generators, this analysis
overstates consumer impacts.
It is also important to note that, if the full cost pass-through condition assumed in this analysis were to
occur, then the screening analyses assessed in Chapter 4 would overstate the impacts to plants and owners
of these plants because the two conditions (full cost pass-through and no cost pass-through) could not
simultaneously occur for the same steam electric power plant.
Plants located in states where electricity prices remain regulated under the traditional cost-of-service rate regulation
framework may be able to recover compliance cost-based increases in their production costs through increased
electricity rates, depending on the business operation model of the plant owner(s), the ownership and operating
structure of the plant itself, and the role of market mechanisms used to sell electricity. In contrast, in states in which
electric power generation has been deregulated, cost recovery is not guaranteed. While plants operating within
deregulated electricity markets may be able to recover some of their additional production costs in increased revenue, it
is not possible to determine the extent of cost recovery ability for each plant. Moreover, even though individual plants
may not be able to recover all of their compliance costs through increased revenues, the market-level effect may still be
that consumers would see higher overall electricity prices because of changes in the cost structure of electricity supply
and resulting changes in market-clearing prices in deregulated generation markets.
EPA-821-R-19-012
7-1

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
7: Electricity Price Effects
7.2 Assessment of Impact of Compliance Costs on Electricity Prices
The EPA assessed the potential increase in electricity prices to the four electricity consumer groups:
residential, commercial, industrial, and transportation.
7.2.1	Analysis Approach and Data Inputs
For this analysis, the EPA assumed that compliance costs would be fully passed through as increased
electricity prices and allocated these costs among consumer groups (residential, commercial, industrial,
and transportation) in proportion to the historical quantity of electricity consumed by each group. The
EPA performed this analysis at the level of the North American Electric Reliability Corporation (NERC)
region. Using the NERC region as the basis for this analysis is appropriate given the structure and
functioning of sub-national electricity markets, around which NERC regions are defined. The analysis,
which uses the exact same approach as used for the 2015 rule analysis (see Chapter 7 in the 2015 RIA
document [U.S. EPA, 2015b]), involves the following steps:
•	The EPA summed weighted pre-tax plant-level annualized compliance costs by NERC region.44'
45
•	The EPA estimated the approximate average price impact per unit of electricity consumption by
dividing total annualized compliance costs by the projected total MWh of sales in 2020 by NERC
region, from AEO2018.
•	The EPA compared the estimated average price effect to the projected electricity price by
consumer group and NERC region for 2020 from AEO2018.
7.2.2	Key Findings for Regulatory Options
As reported in Table 7-1, changes are very small for all regulatory options; the maximum difference in
price effect is a fraction of a cent per kWh. Under Options 1, 2, and 3, the regions with the greatest cost
savings per unit of electricity are SERC and RFC, whereas under Option 4, SERC and MRO are the
regions with the greatest cost savings. Overall across the United States, Option 2 results in the highest
cost savings of 0.0050 per kWh, and Option 4 results in the lowest cost savings of 0.0010 per kWh.
These compliance costs are in 2018 dollars as of a given technology implementation year (2021 through 2028) and
discounted to 2020 at 7 percent. This analysis accounts for the different years in which plants are estimated to
implement the compliance technologies in order to reflect the effect of differences in timing of these electricity price
impacts in terms of cost to household ratepayers and society. Costs and ratepayer effects occurring farther in the future
(e.g., in the last year of the technology implementation period) have a lower present value of impact than those that
occur sooner following rule promulgation. Estimating the cost and ratepayer effect as of the assumed technology
implementation year (2021through 2028) and then discounting these effects to a single analysis year (2020) accounts
for this consideration.
For this analysis, the EPA brought compliance costs forward to a given compliance year using the CCI and ECI.
EPA-821-R-19-012
7-2

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
7: Electricity Price Effects
Table 7-1: Compliance Cost per KWh Sales by NERC Region and Regulator Option in 2020
(2018$)



Costs per Unit
Incremental
Incremental Costs

Total Electricity
National Pre-Tax
of Sales
Annualized Pre-Tax
per Unit of Sales

Sales
Compliance Costs
(2018C/kWh
Compliance Costs
(2018C/kWh
NERCa
(at 2020; MWh)
(at 2020; 2018$)
Sales)
(at 2020; 2018$)
Sales)
Baseline
FRCC
222,490,204
$9,560,479
CO.004
N/A
N/A
MRO
223,130,516
$18,527,879
CO.008
N/A
N/A
NPCC
262,100,581
$7,180,479
CO.003
N/A
N/A
RFC
833,731,788
$166,206,817
CO.020
N/A
N/A
SERC
992,215,820
$204,589,668
CO.021
N/A
N/A
SPP
205,244,514
$24,666,017
CO.012
N/A
N/A
TRE
357,430,000
$6,680,661
CO.002
N/A
N/A
WECC
694,787,895
$4,982,032
C0.001
N/A
N/A
usa
3,806,416,322
$442,394,030
CO.012
N/A
N/A
Option 1
FRCC
222,490,204
$1,020,938
C0.000
-$8,539,541
-CO.004
MRO
223,130,516
$14,147,566
CO.006
-$4,380,313
-CO.002
NPCC
262,100,581
$5,371,158
CO.002
-$1,809,321
-C0.001
RFC
833,731,788
$106,415,315
CO.013
-$59,791,502
-CO.007
SERC
992,215,820
$122,399,799
CO.012
-$82,189,869
-CO.008
SPP
205,244,514
$18,614,853
CO.009
-$6,051,164
-CO.003
TRE
357,430,000
$4,252,972
C0.001
-$2,427,689
-C0.001
WECC
694,787,895
$4,555,803
C0.001
-$426,229
C0.000
usa
3,806,416,322
$276,778,404
C0.007
-$165,615,626
-C0.004
Option 2
FRCC
222,490,204
$5,648,017
CO.003
-$3,912,461
-CO.002
MRO
223,130,516
$6,443,047
CO.003
-$12,084,832
-CO.005
NPCC
262,100,581
$357,706
C0.000
-$6,822,773
-CO.003
RFC
833,731,788
$112,152,958
CO.013
-$54,053,859
-CO.006
SERC
992,215,820
$117,774,447
CO.012
-$86,815,222
-CO.009
SPP
205,244,514
$18,378,460
CO.009
-$6,287,557
-CO.003
TRE
357,430,000
$3,508,153
C0.001
-$3,172,508
-C0.001
WECC
694,787,895
$2,491,442
C0.000
-$2,490,590
C0.000
usa
3,806,416,322
$266,754,229
C0.007
-$175,639,801
-C0.005
Option 3
FRCC
222,490,204
$5,648,017
CO.003
-$3,912,461
-CO.002
MRO
223,130,516
$13,454,178
CO.006
-$5,073,701
-CO.002
NPCC
262,100,581
$5,925,643
CO.002
-$1,254,836
C0.000
RFC
833,731,788
$124,950,189
CO.015
-$41,256,628
-CO.005
SERC
992,215,820
$138,504,202
CO.014
-$66,085,466
-CO.007
SPP
205,244,514
$19,511,015
C0.010
-$5,155,002
-CO.003
TRE
357,430,000
$3,508,153
C0.001
-$3,172,508
-C0.001
WECC
694,787,895
$4,555,803
C0.001
-$426,229
C0.000
usa
3,806,416,322
$316,057,199
CO.008
-$126,336,831
-C0.003
Option 4
FRCC
222,490,204
$14,931,818
CO.007
$5,371,340
CO.002
MRO
223,130,516
$13,655,562
CO.006
-$4,872,316
-CO.002
NPCC
262,100,581
$6,162,717
CO.002
-$1,017,762
C0.000
RFC
833,731,788
$162,382,386
CO.019
-$3,824,430
C0.000
EPA-821-R-19-012
7-3

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
7: Electricity Price Effects
Table 7-1: Compliance Cost per KWh Sales by NERC Region and Regulator Option in 2020
(2018$)



Costs per Unit
Incremental
Incremental Costs

Total Electricity
National Pre-Tax
of Sales
Annualized Pre-Tax
per Unit of Sales

Sales
Compliance Costs
(2018C/kWh
Compliance Costs
(2018C/kWh
NERCa
(at 2020; MWh)
(at 2020; 2018$)
Sales)
(at 2020; 2018$)
Sales)
SERC
992,215,820
$189,131,490
CO.018
-$15,458,178
-CO.002
SPP
205,244,514
$22,303,439
C0.011
-$2,362,578
-C0.001
TRE
357,430,000
$3,760,141
C0.001
-$2,920,520
-C0.001
WECC
694,787,895
$4,555,803
C0.001
-$426,229
C0.000
usa
3,806,416,322
$416,883,357
C0.011
-$25,510,674
-C0.001
a. ELG compliance costs are zero in the AK and HICC regions and these regions are therefore omitted from the presentation.
Because of this, the sum of electricity sales for all regions do not sum to the total for the United States. Total electricity sales
are 6,000,581 MWh and 9,284,423 MWh in AK and HICC, respectively.
Source: U.S. EPA Analysis, 2019
To determine the relative significance of compliance costs on electricity prices across consumer groups,
the EPA compared the per kWh compliance cost to retail electricity prices projected by EIA (AEO2018;
EIA, 2018a) by consuming group and for the average of the groups. As reported in Table 7-2, across the
United States, the baseline is estimated to result in an average electricity price increase for all sectors of
0.012 cents per kWh (0.11 percent of the average price of 10.8 cents per kWh). Table 7-3 presents
incremental impacts on electricity prices under the four regulatory options relative to the baseline. Across
all options, average electricity price increases are less than under the baseline, with cost savings ranging
from 0.001 cents per kWh (0.1 percent) under Option 4, to 0.005 cents per kWh (0.4 percent) under
Option 2.
Looking across the four consumer groups and assuming that any price change would apply equally to all
consumer groups, under all scenarios industrial consumers are estimated to experience the highest price
changes relative to the electricity price basis, while residential consumers are estimated to experience the
lowest price changes, shown in Table 7-2. As with the average national results for all sectors, industrial
and residential price increases under all four options are less than under the baseline, yielding estimated
cost savings to these consumer groups when compared to the 2015 rule. As presented in Table 7-3,
industrial consumers and residential consumers are estimated to experience cost savings of 0.06 percent
and 0.04 percent, respectively under Option 2. Under Option 4, industrial and residential consumers are
estimated to experience cost savings of 0.01 percent under Option 4. The higher relative price effect to
industrial consumers is due to their lower electricity rates and EPA's assumption of uniform changes
across all consumer groups; it does not reflect differential distribution of the incremental costs across
consumer groups.
EPA-821-R-19-012
7-4

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
7: Electricity Price Effects
Table 7-2: Projected 2020 Price (Cents per kWh of Sales) and Potential Price Increase Due to
Compliance Costs by NERC Region and Regulatory Option (2018$)


Residential
Commercial
Industrial
Transportation
All Sectors
Average


EIA

EIA



EIA

EIA


Compliance
Price

Price

EIA Price

Price

Price


Costs
Basis
%
Basis
%
Basis
%
Basis
%
Basis


(2018<
(2018<
Change
(2018<
Change
(2018<
Change
(2018<
Change
(2018<
% Change
NERCb
/kWh)
/kWh)
a
/kWh)
a
/kWh)
a
/kWh)
a
/kWh)
a
Baseline
FRCC
CO.004
C11.7
0.04%
C9.6
0.04%
C8.2
0.05%
CIO.8
0.04%
CIO.6
0.04%
MRO
CO.008
C12.1
0.07%
C9.7
0.09%
C7.2
0.12%
C12.5
0.07%
C9.5
0.09%
NPCC
CO.003
C19.1
0.01%
C13.4
0.02%
C13.5
0.02%
C12.0
0.02%
C15.5
0.02%
RFC
CO.020
C14.5
0.14%
CIO.8
0.18%
C7.8
0.26%
C10.0
0.20%
C11.2
0.18%
SERC
CO.021
C12.2
0.17%
CIO.4
0.20%
C6.5
0.32%
C12.1
0.17%
C10.0
0.21%
SPP
CO.012
C11.9
0.10%
C10.0
0.12%
C6.7
0.18%
C12.3
0.10%
C9.7
0.12%
TRE
CO.002
C9.6
0.02%
C8.8
0.02%
C5.8
0.03%
C7.8
0.02%
C8.3
0.02%
WECC
C0.001
C13.8
0.01%
C12.2
0.01%
C7.6
0.01%
C13.0
0.01%
C11.6
0.01%
US
CO.012
(13.1
0.09%
CIO.9
0.11%
C7.3
0.16%
<11.4
0.10%
<10.8
0.11%
Option 1
FRCC
C0.000
C11.7
0.00%
C9.6
0.00%
C8.2
0.01%
CIO.8
0.00%
CIO.6
0.00%
MRO
CO.006
C12.1
0.05%
C9.7
0.07%
C7.2
0.09%
C12.5
0.05%
C9.5
0.07%
NPCC
CO.002
C19.1
0.01%
C13.4
0.02%
C13.5
0.02%
C12.0
0.02%
C15.5
0.01%
RFC
CO.013
C14.5
0.09%
CIO.8
0.12%
C7.8
0.16%
C10.0
0.13%
C11.2
0.11%
SERC
CO.012
C12.2
0.10%
CIO.4
0.12%
C6.5
0.19%
C12.1
0.10%
C10.0
0.12%
SPP
CO.009
C11.9
0.08%
C10.0
0.09%
C6.7
0.14%
C12.3
0.07%
C9.7
0.09%
TRE
C0.001
C9.6
0.01%
C8.8
0.01%
C5.8
0.02%
C7.8
0.02%
C8.3
0.01%
WECC
C0.001
C13.8
0.00%
C12.2
0.01%
C7.6
0.01%
C13.0
0.01%
C11.6
0.01%
US
<0.007
(13.1
0.06%
CIO.9
0.07%
C7.3
0.10%
<11.4
0.06%
<10.8
0.07%
Option 2
FRCC
CO.003
C11.7
0.02%
C9.6
0.03%
C8.2
0.03%
CIO.8
0.02%
CIO.6
0.02%
MRO
CO.003
C12.1
0.02%
C9.7
0.03%
C7.2
0.04%
C12.5
0.02%
C9.5
0.03%
NPCC
C0.000
C19.1
0.00%
C13.4
0.00%
C13.5
0.00%
C12.0
0.00%
C15.5
0.00%
RFC
CO.013
C14.5
0.09%
CIO.8
0.12%
C7.8
0.17%
C10.0
0.13%
C11.2
0.12%
SERC
CO.012
C12.2
0.10%
CIO.4
0.11%
C6.5
0.18%
C12.1
0.10%
C10.0
0.12%
SPP
CO.009
C11.9
0.08%
C10.0
0.09%
C6.7
0.13%
C12.3
0.07%
C9.7
0.09%
TRE
C0.001
C9.6
0.01%
C8.8
0.01%
C5.8
0.02%
C7.8
0.01%
C8.3
0.01%
WECC
C0.000
C13.8
0.00%
C12.2
0.00%
C7.6
0.00%
C13.0
0.00%
C11.6
0.00%
US
<0.007
<13.1
0.05%
<10.9
0.06%
<7.3
0.10%
<11.4
0.06%
<10.8
0.06%
Option 3
FRCC
CO.003
C11.7
0.02%
C9.6
0.03%
C8.2
0.03%
CIO.8
0.02%
CIO.6
0.02%
MRO
CO.006
C12.1
0.05%
C9.7
0.06%
C7.2
0.08%
C12.5
0.05%
C9.5
0.06%
NPCC
CO.002
C19.1
0.01%
C13.4
0.02%
C13.5
0.02%
C12.0
0.02%
C15.5
0.01%
RFC
CO.015
C14.5
0.10%
CIO.8
0.14%
C7.8
0.19%
C10.0
0.15%
C11.2
0.13%
SERC
CO.014
C12.2
0.11%
CIO.4
0.13%
C6.5
0.22%
C12.1
0.12%
C10.0
0.14%
SPP
C0.010
C11.9
0.08%
C10.0
0.09%
C6.7
0.14%
C12.3
0.08%
C9.7
0.10%
TRE
C0.001
C9.6
0.01%
C8.8
0.01%
C5.8
0.02%
C7.8
0.01%
C8.3
0.01%
WECC
C0.001
C13.8
0.00%
C12.2
0.01%
C7.6
0.01%
C13.0
0.01%
C11.6
0.01%
US
<0.008
<13.1
0.06%
<10.9
0.08%
<7.3
0.11%
<11.4
0.07%
<10.8
0.08%
EPA-821-R-19-012
7-5

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
7: Electricity Price Effects
Table 7-2: Projected 2020 Price (Cents per kWh of Sales) and Potential Price Increase Due to
Compliance Costs by NERC Region and Regulatory Option (2018$)










All Sectors


Residential
Commercial
Industrial
Transportation
Average


EIA

EIA



EIA

EIA


Compliance
Price

Price

EIA Price

Price

Price


Costs
Basis
%
Basis
%
Basis
%
Basis
%
Basis


(2018C
(2018C
Change
(2018<
Change
(2018<
Change
(2018<
Change
(2018<
% Change
NERCb
/kWh)
/kWh)
a
/kWh)
a
/kWh)
a
/kWh)
a
/kWh)
a
Option 4
FRCC
CO.007
C11.7
0.06%
C9.6
0.07%
C8.2
0.08%
C10.8
0.06%
C10.6
0.06%
MRO
CO.006
C12.1
0.05%
C9.7
0.06%
C7.2
0.09%
C12.5
0.05%
C9.5
0.06%
NPCC
CO.002
C19.1
0.01%
C13.4
0.02%
C13.5
0.02%
C12.0
0.02%
C15.5
0.02%
RFC
CO.019
C14.5
0.13%
C10.8
0.18%
C7.8
0.25%
C10.0
0.19%
C11.2
0.17%
SERC
CO.019
C12.2
0.16%
C10.4
0.18%
C6.5
0.30%
C12.1
0.16%
C10.0
0.19%
SPP
C0.011
C11.9
0.09%
C10.0
0.11%
C6.7
0.16%
C12.3
0.09%
C9.7
0.11%
TRE
C0.001
C9.6
0.01%
C8.8
0.01%
C5.8
0.02%
C7.8
0.01%
C8.3
0.01%
WECC
C0.001
C13.8
0.00%
C12.2
0.01%
C7.6
0.01%
C13.0
0.01%
C11.6
0.01%
US
C0.011
<13.1
0.08%
C10.9
0.10%
<7.3
0.15%
<11.4
0.10%
C10.8
0.10%
a. The rate impact analysis assumes full pass-through of all compliance costs to electricity consumers.
b. ELG compliance costs are zero in the AK and HICC regions and these regions are therefore omitted from the presentation.
Sources: U.S. EPA Analysis, 2019; EIA, 2017b; EIA, 2018a
Table 7-3: Potential Incremental Price Changes Relative to Baseline Due to Compliance Costs by
NERC Region and Regulatory Option (2018$)

A Compliance



A


Costs (2018C/
A Residential
A Commercial
A Industrial
Transportation
A All Sectors
NERCb
kWh)
Price3
Price3
Price3
Price3
Average Price3
Option 1
FRCC
-CO.004
-0.03%
-0.04%
-0.05%
-0.04%
-0.04%
MRO
-CO.002
-0.02%
-0.02%
-0.03%
-0.02%
-0.02%
NPCC
-C0.001
0.00%
-0.01%
-0.01%
-0.01%
0.00%
RFC
-CO.007
-0.05%
-0.07%
-0.09%
-0.07%
-0.06%
SERC
-CO.008
-0.07%
-0.08%
-0.13%
-0.07%
-0.08%
SPP
-CO.003
-0.02%
-0.03%
-0.04%
-0.02%
-0.03%
TRE
-C0.001
-0.01%
-0.01%
-0.01%
-0.01%
-0.01%
WECC
C0.000
0.00%
0.00%
0.00%
0.00%
0.00%
US
-C0.004
-0.03%
-0.04%
-0.06%
-0.04%
-0.04%
Option 2
FRCC
-CO.002
-0.02%
-0.02%
-0.02%
-0.02%
-0.02%
MRO
-CO.005
-0.04%
-0.06%
-0.08%
-0.04%
-0.06%
NPCC
-CO.003
-0.01%
-0.02%
-0.02%
-0.02%
-0.02%
RFC
-CO.006
-0.04%
-0.06%
-0.08%
-0.06%
-0.06%
SERC
-CO.009
-0.07%
-0.08%
-0.14%
-0.07%
-0.09%
SPP
-CO.003
-0.03%
-0.03%
-0.05%
-0.02%
-0.03%
TRE
-C0.001
-0.01%
-0.01%
-0.02%
-0.01%
-0.01%
WECC
C0.000
0.00%
0.00%
0.00%
0.00%
0.00%
US
-C0.005
-0.04%
-0.04%
-0.06%
-0.04%
-0.04%
EPA-821-R-19-012
7-6

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
7: Electricity Price Effects
Table 7-3: Potential Incremental Price Changes Relative to Baseline Due to Compliance Costs by
NERC Region and Regulatory Option (2018$)

A Compliance



A


Costs (2018C/
A Residential
A Commercial
A Industrial
Transportation
A All Sectors
NERCb
kWh)
Price3
Price3
Price3
Price3
Average Price3
Option 3
FRCC
-CO.002
-0.02%
-0.02%
-0.02%
-0.02%
-0.02%
MRO
-CO.002
-0.02%
-0.02%
-0.03%
-0.02%
-0.02%
NPCC
C0.000
0.00%
0.00%
0.00%
0.00%
0.00%
RFC
-CO.005
-0.03%
-0.05%
-0.06%
-0.05%
-0.04%
SERC
-CO.007
-0.05%
-0.06%
-0.10%
-0.06%
-0.07%
SPP
-CO.003
-0.02%
-0.03%
-0.04%
-0.02%
-0.03%
TRE
-C0.001
-0.01%
-0.01%
-0.02%
-0.01%
-0.01%
WECC
C0.000
0.00%
0.00%
0.00%
0.00%
0.00%
US
-C0.003
-0.03%
-0.03%
-0.05%
-0.03%
-0.03%
Option 4
FRCC
CO.002
0.02%
0.03%
0.03%
0.02%
0.02%
MRO
-CO.002
-0.02%
-0.02%
-0.03%
-0.02%
-0.02%
NPCC
C0.000
0.00%
0.00%
0.00%
0.00%
0.00%
RFC
C0.000
0.00%
0.00%
-0.01%
0.00%
0.00%
SERC
-CO.002
-0.01%
-0.01%
-0.02%
-0.01%
-0.02%
SPP
-C0.001
-0.01%
-0.01%
-0.02%
-0.01%
-0.01%
TRE
-C0.001
-0.01%
-0.01%
-0.01%
-0.01%
-0.01%
WECC
C0.000
0.00%
0.00%
0.00%
0.00%
0.00%
US
-C0.001
-0.01%
-0.01%
-0.01%
-0.01%
-0.01%
a.	The rate impact analysis assumes full pass-through of all compliance costs to electricity consumers.
b.	ELG compliance costs are zero in the AK and HICC regions and these regions are therefore omitted from the presentation.
Sources: U.S. EPA Analysis, 2019; EIA, 2017b; EIA, 2018a
7.2.3 Uncertainties and Limita tions
As noted above, the assumption of 100 percent pass-through of compliance costs to electricity prices
represents a worst-case scenario from the perspective of consumers. To the extent that some steam
electric power plants are not able to pass their compliance costs to consumers through higher electricity
rates, this analysis overstates the potential impact of the baseline and regulatory options on electricity
consumers.
In addition, this analysis assumes that costs would be passed on in the form of a flat-rate price increase
per unit of electricity, to be applied equally to all consumer groups. This assumption is appropriate to
assess the general magnitude of potential price increases. The allocation of costs to different consumer
groups could be higher or lower than estimated by this approach.
7.3 Assessment of Impact of Compliance Costs on Household Electricity Costs
The EPA also assessed the potential increases in the cost of electricity to residential households.
7.3.1 Analysis Approach and Data Inputs
For this analysis, the EPA again assumed that compliance costs would be fully passed through as
increased electricity prices and allocated these costs to residential households in proportion to the baseline
EPA-821-R-19-012
7-7

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
7: Electricity Price Effects
electricity consumption. The EPA analyzed the potential impact on annual electricity costs at the level of
the 'average' household, using the estimated household electricity consumption quantity by NERC
region. Following the approach used in analyzing the 2015 rule (U.S. EPA, 2015b), the steps in this
calculation are as follows:
•	As done for the electricity price analysis discussed in Section 7.2, to estimate total annual cost in
each NERC region, the EPA summed weighted pre-tax, plant-level annualized compliance costs
by NERC region.46
•	As was done for the analysis of impact of compliance costs on electricity prices, the EPA divided
total compliance costs by the total MWh of sales reported for each NERC region. The EPA used
electricity sales (in MWh) for 2020 from AEO2018.47
•	To calculate average annual electricity sales per household, the EPA divided the total quantity of
residential sales (in MWh) for 2016 in each NERC region by the number of households in that
region; the Agency obtained both the quantity of residential sales and the number of households
from the 2016 EIA-861 database (EIA, 2017b). For this analysis, the EPA assumed that the
average quantity of electricity sales per household by NERC region would remain the same in
2020 as in 2016.
•	To assess the potential annual cost impact per household, the EPA multiplied the estimated
average price impact by the average quantity of electricity sales per household in 2016 by NERC
region.
7.3.2 Key Findings for Reguia tory Options
Table 7-4 reports the results of this analysis by NERC region for each option, and overall for the United
States.48
The average incremental annual cost savings per residential household is greatest in SERC and the least in
WECC under all options. On the national level, cost savings are greatest on average under Option 2, with
average cost savings per residential household of $0.49 per year; by region, cost savings range between
$0.03-$ 1.20 per year. The least cost savings occur under Option 4, with average cost savings per
residential household of $0.07 per year; by region, cost savings range between $0.01-$0.21 per year, with
one region (FRCC) projected to see an increase in average cost per household of $0.33.
Compliance costs in the ASCC and HICC regions are zero and EPA therefore did not include these regions in its
analysis.
AEO does not provide information for HICC and ASSC. None of the plants estimated to incur compliance costs as a
result of the proposed ELG, however, are located in these two NERC regions.
Average annual cost per residential household is zero in ASCC and HICC for the baseline and the four options and
these regions are therefore omitted from the details. They are included in the U.S. totals.
EPA-821-R-19-012
7-8

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
7: Electricity Price Effects
Table 7-4: Average Incremental Annual Cost per Household in 2020 by NERC Region and
Regulatory Option (2018$)

Constant values
Incremental values3





Total

Incremental




Residential
Incremental
Incremental
Compliance




Sales per
P re-Tax
Compliance
Costs per

Total
Residential

Residential
Compliance
Costs per Unit
Residential

Electricity
Electricity
Number of
Household
Costs (at 2020;
of Sales
Household
NERCb
Sales (MWh)
Sales (MWh)
Households
(MWh)
2018$)
(2018$ /MWh)
(2018$)
Option 1
FRCC
222,490,204
123,474,310
9,157,068
13.48
-$8,539,541
-$0.04
-$0.52
MRO
223,130,516
61,667,737
6,157,998
10.01
-$4,380,313
-$0.02
-$0.20
NPCC
262,100,581
148,760,464
18,761,676
7.93
-$1,809,321
-$0.01
-$0.05
RFC
833,731,788
352,481,555
35,967,640
9.80
-$59,791,502
-$0.07
-$0.70
SERC
992,215,820
403,431,581
29,294,201
13.77
-$82,189,869
-$0.08
-$1.14
SPP
205,244,514
28,987,604
2,451,321
11.83
-$6,051,164
-$0.03
-$0.35
TRE
357,430,000
113,645,980
8,236,191
13.80
-$2,427,689
-$0.01
-$0.09
WECC
694,787,895
255,116,789
29,814,787
8.56
-$426,229
$0.00
-$0.01
usb
3,806,416,322
1,492,029,155
140,547,123
10.62
-$165,615,626
-$0.04
-$0.46
Option 2
FRCC
222,490,204
123,474,310
9,157,068
13.48
-$3,912,461
-$0.02
-$0.24
MRO
223,130,516
61,667,737
6,157,998
10.01
-$12,084,832
-$0.05
-$0.54
NPCC
262,100,581
148,760,464
18,761,676
7.93
-$6,822,773
-$0.03
-$0.21
RFC
833,731,788
352,481,555
35,967,640
9.80
-$54,053,859
-$0.06
-$0.64
SERC
992,215,820
403,431,581
29,294,201
13.77
-$86,815,222
-$0.09
-$1.20
SPP
205,244,514
28,987,604
2,451,321
11.83
-$6,287,557
-$0.03
-$0.36
TRE
357,430,000
113,645,980
8,236,191
13.80
-$3,172,508
-$0.01
-$0.12
WECC
694,787,895
255,116,789
29,814,787
8.56
-$2,490,590
$0.00
-$0.03
usb
3,806,416,322
1,492,029,155
140,547,123
10.62
-$175,639,801
-$0.05
-$0.49
Option 3
FRCC
222,490,204
123,474,310
9,157,068
13.48
-$3,912,461
-$0.02
-$0.24
MRO
223,130,516
61,667,737
6,157,998
10.01
-$5,073,701
-$0.02
-$0.23
NPCC
262,100,581
148,760,464
18,761,676
7.93
-$1,254,836
$0.00
-$0.04
RFC
833,731,788
352,481,555
35,967,640
9.80
-$41,256,628
-$0.05
-$0.48
SERC
992,215,820
403,431,581
29,294,201
13.77
-$66,085,466
-$0.07
-$0.92
SPP
205,244,514
28,987,604
2,451,321
11.83
-$5,155,002
-$0.03
-$0.30
TRE
357,430,000
113,645,980
8,236,191
13.80
-$3,172,508
-$0.01
-$0.12
WECC
694,787,895
255,116,789
29,814,787
8.56
-$426,229
$0.00
-$0.01
usb
3,806,416,322
1,492,029,155
140,547,123
10.62
-$126,336,831
-$0.03
-$0.35
Option 4
FRCC
222,490,204
123,474,310
9,157,068
13.48
$5,371,340
$0.02
$0.33
MRO
223,130,516
61,667,737
6,157,998
10.01
-$4,872,316
-$0.02
-$0.22
NPCC
262,100,581
148,760,464
18,761,676
7.93
-$1,017,762
$0.00
-$0.03
RFC
833,731,788
352,481,555
35,967,640
9.80
-$3,824,430
$0.00
-$0.04
SERC
992,215,820
403,431,581
29,294,201
13.77
-$15,458,178
-$0.02
-$0.21
SPP
205,244,514
28,987,604
2,451,321
11.83
-$2,362,578
-$0.01
-$0.14
TRE
357,430,000
113,645,980
8,236,191
13.80
-$2,920,520
-$0.01
-$0.11
WECC
694,787,895
255,116,789
29,814,787
8.56
-$426,229
$0.00
-$0.01
EPA-821-R-19-012
7-9

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
7: Electricity Price Effects
Table 7-4: Average Incremental Annual Cost per Household in 2020 by NERC Region and
Regulatory Option (2018$)
usb
3,806,416,322
1,492,029,155
140,547,123
10.62
-$25,510,674
-$0.01
-$0.07
a.	The rate impact analysis assumes full pass-through of all compliance costs to electricity consumers.
b.	ELG compliance costs are zero in the AK and HICC regions and these regions are therefore omitted from the presentation.
For this reason, electricity sales shown for the United States is greater than the total for NERC regions included in the table.
Sources: U.S. EPA Analysis, 2019; EIA, 2018; EIA, 2016
7.3.3 Uncertainties and Limita tions
As noted above, the assumption of 100 percent pass-through of compliance costs to electricity prices
represents a worst-case scenario from the perspective of households. To the extent that some steam
electric power plants are not able to pass their compliance costs to consumers through higher electricity
rates, this analysis overstates the potential impact of the regulatory options on households.
This analysis also assumes that costs would be passed on in the form of a flat-rate price increase per unit
of electricity, an assumption the EPA deems reasonable to characterize the magnitude of compliance costs
relative to household electricity consumption. The allocation of costs to the residential class could be
higher or lower than estimated by this approach.
7.4 Distribution of Electricity Cost Impact on Household
In general, lower-income households spend less, in the absolute, on energy than do higher-income
households, but energy expenditures represent a larger share of their income. Therefore, electricity price
increases tend to have a relatively larger effect on lower-income households, compared to higher-income
households. In analyzing the impacts of the 2015 rule, the EPA conducted a distributional analysis of the
final rule to assess (1) whether an increase in electricity rates that may occur under the final rule would
disproportionately affect lower-income households and (2) whether households would be able to pay for
these electricity rate increases without experiencing economic hardship {i.e., whether the increase is
affordable). The analysis provided additional insight on the distribution of impacts among residential
electricity consumers to help respond to concerns regarding the impacts of the rule on utilities and
cooperatives in service areas that include a relatively high proportion of low-income households.
In the 2015 analysis, the EPA had concluded that even when looking at a worst-case scenario of 100
percent pass through of the compliance costs, the "incremental economic burden of any final rule based
on the regulatory options in the proposal on households is small both relative to income and relative to the
baseline energy burden of households in different income ranges. While the incremental burden relative
to income is not distributionally neutral, i.e., any increase would affect lower-income households to a
greater extent than higher-income households, the small impacts may be further moderated by existing
pricing structures (see Section 7.4 in U.S. EPA, 2015b)/' As presented in the preceding sections, the EPA
estimates that the four regulatory options would reduce compliance costs for FGD wastewater and bottom
ash transport water when compared to the baseline. To the extent that these savings are in turn passed
through to electricity consumers in the form of lower prices, the resulting lower electricity prices may
have a larger positive effect on lower-income households. The EPA finds that the earlier conclusion of
small impacts from the 2015 ELG still holds given the lower compliance costs of the four regulatory
options, relative to the baseline.
EPA-821-R-19-012
7-10

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
8: RFA
8 Assessment of Potential Impact of the Regulatory Options on Small
Entities - Regulatory Flexibility Act (RFA) Analysis
The Regulatory Flexibility Act (RFA) of 1980, as amended by the Small Business Regulatory
Enforcement Fairness Act (SBREFA) of 1996, requires federal agencies to consider the impact of their
rules on small entities, to analyze alternatives that minimize those impacts,49 and to make their analyses
available for public comments. The RFA is concerned with three types of small entities: small businesses,
small nonprofits, and small government jurisdictions.
The RFA describes the regulatory flexibility analyses and procedures that must be completed by federal
agencies unless they certify that the rule, if promulgated, would not have a significant economic impact
on a substantial number of small entities. This certification must be supported by a statement of factual
basis, e.g., addressing the number of small entities affected by the proposed action, estimated cost impacts
on these entities, and evaluation of the economic impacts.
In accordance with RFA requirements and as it has consistently done in developing effluent limitations
guidelines and standards, the EPA assessed whether the regulatory options would have "a significant
impact on a substantial number of small entities" (SISNOSE). Following the approach used in the
analysis of the 2015 rule (U.S. EPA, 2015b), this assessment involved the following steps:
•	Identifying the domestic parent entities of steam electric power plants.
•	Determining which of those domestic parent entities are small entities, based on Small Business
Administration (SBA) size criteria.
•	Assessing the change in potential impact of the regulatory options on those small entities by
comparing the estimated entity-level annualized compliance cost to entity-level revenue; the cost-
to-revenue ratio indicates the magnitude of economic impacts. Following EPA guidance (U.S.
EPA, 2006), the EPA used threshold compliance costs of one percent or three percent of entity-
level revenue to categorize the degree of significance of the economic impacts on small entities.
•	Assessing the change in whether those small entities incurring potentially significant impacts
represent a substantial number of small entities. Following EPA guidance (U.S. EPA, 2006), the
EPA determined whether the number of small entities impacted is substantial based on (1) the
estimated absolute numbers of small entities incurring potentially significant impacts according
to the two cost impact criteria, and (2) the percentage of small entities in the relevant entity
categories that are estimated to incur these impacts.
The EPA performed this assessment for the baseline and each of the regulatory options, with the
differences between the findings indicative of the impacts of the options on small entities. This chapter
describes the analytic approach (Section 8.1), summarizes the findings of the EPA's RFA assessment
Section 603(c) of the RFA provides examples of such alternatives as: (1) the establishment of differing compliance or
reporting requirements or timetables that take into account the resources available to small entities; (2) the clarification,
consolidation, or simplification of compliance and reporting requirements under the rule for such small entities; (3) the
use of performance rather than design standards; and (4) an exemption from coverage of the rule, or any part thereof,
for such small entities.
EPA-821-R-19-012
8-1

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
8: RFA
(Section 8.2), and reviews uncertainties and limitations in the analysis (Section 8.3). The Chapter also
discusses how regulatory options developed by the EPA served to mitigate the impact of the regulatory
options on small entities (Section 8.4).
8.1 Analysis Approach and Data Inputs
The EPA used the same methodology and assumptions used for the analysis of the 2015 rule (U.S. EPA,
2015b), but updated input data to reflect more recent information about plant ownership, entity size, and
compliance costs as described in the sections below.
One difference from the approach used for the 2015 rule analysis is the explicit analysis of the impacts of
the baseline on small entities, which serves as contrast for analyzed impacts of the regulatory options.
This two-part analysis enables the Agency to understand how the regulatory options mitigate any impacts
to small entities projected under the baseline.
8.1.1	Determining Parent Entity of Steam Electric Power Plants
Consistent with the entity-level cost-to-revenue analysis (Chapter 4: Economic Impact Screening
Analyses), the EPA conducted the RFA analysis at the highest level of domestic ownership, referred to as
the "domestic parent entity" or "domestic parent firm", including only entities with the largest share of
ownership (majority owner)50 in at least one of the estimated 951 steam electric power plants in the steam
electric point source category. As was done for the entity-level cost-to-revenue analysis in Section 4.3, the
EPA identified the majority owner for each plant using 2016 databases published by the Department of
Energy's Energy Information Administration (EIA) (EIA, 2017a), corporate and financial websites, and
the Steam Electric Survey (U.S. EPA, 2010b).
8.1.2	Determining Whether Parent Entities of Steam Electric Power Plants Are Small
The EPA identified the size of each parent entity using the SBA size threshold guidelines in effect as of
October 1, 2017 (SBA, 2017). The criteria for entity size determination vary by the
organization/operation category of the parent entity, as follows:
•	Privately owned (non-government) entities: Privately owned entities include investor-owned
utilities, non-utility entities, and entities with a primary business other than electric power
generation. For entities with electric power generation as a primary business, small entities are
those with less than the threshold number of employees specified by SBA for each of the relevant
North American Industry Classification System (NAICS) sectors (NAICS 2211) (see Table 8-1).
For entities with a primary business other than electric power generation, the relevant size criteria
are based on revenue or number of employees by NAICS sector.51
•	Publicly owned entities: Publicly owned entities include federal, State, municipal, and other
political subdivision entities. The federal and State governments were considered to be large;
municipalities and other political units with population less than 50,000 were considered to be
small.
Throughout the analyses, the EPA refers to the owner with the largest ownership share as the "majority owner" even
when the ownership share is less than 51 percent.
Certain steam electric power plants are owned by entities whose primary business is not electric power generation.
EPA-821-R-19-012
8-2

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
8: RFA
• Rural Electric Cooperatives: Small entities are those with less than the threshold number of
employees specified by SB A for each of the relevant NAICS sectors, depending on the type of
electricity generation (see Table 8-1).
Table 8-1: NAICS Codes and SBA Size Standards for Non-government Majority Owners Entities of
Steam Electric Power Plants

NAICS Code3
NAICS Description
SBA Size Standard13
212111
Bituminous Coal and Lignite Surface Mining
1250 Employees
221111
Hydroelectric Power Generation
500 Employees
221112
Fossil Fuel Electric Power Generation
750 Employees
221113
Nuclear Electric Power Generation
750 Employees
221114°
Solar Electric Power Generation
250 Employees
221115°
Wind Electric Power Generation
250 Employees
221116°
Geothermal Electric Power Generation
250 Employees
221117°
Biomass Electric Power Generation
250 Employees
221118°
Other Electric Power Generation
250 Employees
221121
Electric Bulk Power Transmission and Control
500 Employees
221122
Electric Power Distribution
1,000 Employees
221210
Natural Gas Distribution
1,000 Employees
221310
Water Supply and Irrigation Systems
$27.5 million in revenue
237130
Power and Communication Line and Related Structures
Construction
$36.5 million in revenue
332410
Power Boiler and Heat Exchanger Manufacturing
750 Employees
333611
Turbine and Turbine Generator Set Unit Manufacturing
1,500 Employees
523920
Portfolio Management
$37.7 million in revenue
524113
Direct Life Insurance Carriers
$37.7 million in revenue
524126
Direct Property and Casualty Insurance Carriers
1,500 employees
541614
Process, Physical Distribution and Logistics Consulting Services
$15 million in revenue
551112
Offices of Other Holding Companies
$20.5 million in revenue
562219
Other Nonhazardous Waste Treatment and Disposal
$38.5 million in revenue
a.	Certain plants affected by this rulemaking are owned by non-government entities whose primary business is not electric
power generation.
b.	Based on size standards effective at the time EPA conducted this analysis (SBA size standards, effective October 1, 2017).
c.	NAICS code used as proxy for determining size threshold for entities categorized in NAICS 221119.
Source: SBA, 2017
To determine whether a majority owner is a small entity according to these criteria, the EPA compared
the relevant entity size criterion value estimated for each parent entity to the SBA threshold value. The
EPA used the following data sources and methodology to estimate the relevant size criterion values for
each parent entity:
• Employment: The EPA used entity-level employment values from corporate/financial websites,
if those values were available, or from the Steam Electric Survey if more recent data were not
available.
EPA-821-R-19-012
8-3

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
8: RFA
•	Revenue: The EPA used entity-level revenue values described in Section 4.3.1. For entities with
values reported for more than one year, the EPA used the average of reported values.
•	Population: Population data for municipalities and other non-state political subdivisions were
obtained from the U.S. Census Bureau (estimated population for 2016) (U.S. DOC, 2016).
Parent entities for which the relevant measure is less than the SBA size criterion were identified as small
entities and carried forward in the RFA analysis.
As discussed in Chapter 4 (Economic Impact Screening Analyses), the EPA estimated the number of
small entities owning steam electric power plants as a range, based on alternative assumptions about the
possible ownership of electric power plants that fall within the definition of the point source category.
Following the approach used in the analysis of the 2015 rule, the EPA analyzed two cases that provide a
range of estimates for (1) the number of firms incurring compliance costs and (2) the costs incurred by
any firm owning a regulated plant (U.S. EPA, 2015b).
Table 8-2 presents the total number of entities with steam electric power plants as well as the number and
percentage of those entities determined to be small. Table 8-3 presents the distribution of steam electric
power plants by ownership type and owner size. Analysis results are presented by ownership type for the
baseline and the four analyzed regulatory options under the lower (Case 1) and upper (Case 2) bound
estimates of the number of entities owning steam electric power plants.
As reported in Table 8-2 and Table 8-3, the EPA estimates that between 243 and 478 entities own 951
steam electric power plants (for Case 1 and Case 2, respectively).52 A typical parent entity on average is
estimated to own four steam electric power plants (for both Case 1 and Case 2). The Agency estimates
that between 79 (36 percent) and 127 (27 percent) parent entities are small (Table 8-2), and these small
entities own 139 steam electric power plants (Table 8-3), or approximately 15 percent of all steam electric
power plants. Across ownership types, cooperatives represent the largest share of small entities (75 and
72 percent, for Case 1 and Case 2 respectively); cooperatives account for the largest share of steam
electric power plants owned by small entities (64 percent).
As described in Chapter 8 in the 2015 RIA document (U.S. EPA, 2015b), Case 1 assumed that any entity owning a
surveyed plant(s) owns the known surveyed plant(s) and all of the sample weight associated with the surveyed plant(s).
This case minimizes the count of affected entities, while tending to maximize the potential cost burden to any single
entity. Case 2 assumed (1) that an entity owns only the surveyed plant(s) that it is known to own from the Steam
Electric Survey and (2) that this pattern of ownership, observed for surveyed plants and their owning entities, extends
over the entire plant population. This case minimizes the possibility of multi-plant ownership by a single entity and
thus maximizes the count of affected entities, but also minimizes the potential cost burden to any single entity.
EPA-821-R-19-012
8-4

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
8: RFA
Table 8-2: Number of Entities by Sector and Size (assuming two different ownership cases)


Case 1: Lower bound estimate of
Case 2: Upper bound estimate


number of entities owning steam
of number of entities owning

Small Entity Size
electric power plantsa b
steam electric power plantsa b
Ownership Type
Standard
Total
Small
% Small
Total
Small
% Small
Cooperative
number of employees
28
21
75.0%
50
36
72.2%
Federal
assumed large
1
0
0.0%
3
0
0.0%
Investor-owned
number of employeesd
69
9
13.0%
157
20
13.0%
Municipality
50,000 population served
59
29
49.2%
94
37
39.1%
Nonutility
number of employeesd
74
19
25.7%
150
33
22.0%
Other Political
Subdivision0
50,000 population served
10
1
10.0%
21
1
4.7%
State
assumed large
2
0
0.0%
2
0
0.0%
Total
243
79
32.5%
478
127
26.6%
a.	Thirteen plants are owned by a joint venture of two entities.
b.	Of these, 58 entities, 15 of which are small, own steam electric power plants that are estimated to incur compliance
technology costs under regulatory options under both Case 1 and Case 2.
c.	The EPA was unable to determine the size of one parent entity owned by a political subdivision; for this analysis, this entity is
assumed to be large.
d.	Entity size may be based on revenue, depending on the NAICS sector (see Table 8-1).
Source: U.S. EPA Analysis, 2019.
Table 8-3: Steam Electric Power Plants by Ownership Type and Size
Ownership Type
Small Entity Size
Standard
Number of Steam Electric Power Plantsa b c d
Total
Small
% Small
Cooperative
number of employees
64
41
64.2%
Federal
assumed large
20
0
0.0%
Investor-owned
number of employees6
509
22
4.4%
Municipality
50,000 population served
123
37
30.1%
Nonutility
number of employees6
198
38
19.2%
Other Political Subdivisions
50,000 population served
34
1
3.0%
State
assumed large
4
0
0.0%
Total
951
139
14.7%
a.	Numbers may not add up to totals due to independent rounding.
b.	The numbers of plants and capacity are calculated on a sample-weighted basis.
c.	Plant size was determined based on the size of the owner with the largest share in the plant. In case of multiple
owners with equal ownership shares (e.g., two entities with 50/50 shares), a plant was assumed to be small if it is
owned by at least one small entity.
d.	Of these, 114 steam electric power plants are estimated to incur compliance costs under the baseline, whereas 108
plants incur compliance costs under the regulatory options; 15 of the 108 steam electric power plants are owned by
small entities.
e.	Entity size may be based on revenue, depending on the NAICS sector (see Table 8-1).
Source: U.S. EPA Analysis, 2019.
EPA-821-R-19-012
8-5

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
8: RFA
8.1.3 Significant impact Test for Small Entities
As outlined in the introduction to this chapter, two criteria are assessed in determining whether the
regulatory options would qualify for a no-SISNOSE finding:
•	Is the absolute number of small entities estimated to incur a potentially significant impact, as
described above, substantial?
and
•	Do these significant impact entities represent a substantial fraction of small entities in the electric
power industry that could potentially be within the scope of a regulation?
A measure of the potential impact of the regulatory options on small entities is the fraction of small
entities that have the potential to incur a significant impact. For example, if a high percentage of
potentially small entities incur significant impacts even though the absolute number of significant impact
entities is low, then the rule could represent a substantial burden on small entities.
To assess the extent of economic/financial impact on small entities, the EPA compared estimated
compliance costs to estimated entity revenue (also referred to as the "sales test"). The analysis is based on
the ratio of estimated annualized after-tax compliance costs to annual revenue of the entity. For this
analysis, the EPA categorized entities according to the magnitude of economic impacts that entities would
incur as a result of the regulatory options. The EPA identified entities for which annualized compliance
costs are at least one percent and three percent of revenue. The EPA then evaluated the absolute number
and the percent of entities in each impact category, and by type of ownership. The Agency assumed that
entities incurring costs below one percent of revenue are unlikely to face significant economic impacts,
while entities with costs of at least one percent of revenue have a higher chance of facing significant
economic impacts, and entities incurring costs of at least three percent of revenue have a still higher
probability of significant economic impacts. Consistent with the parent-level cost-to-revenue analysis
discussed in Chapter 4, the EPA assumed that steam electric power plants, and consequently, their
parents, would not be able to pass any of the increase in their production costs to consumers (zero cost
pass-through). This assumption is used for analytic convenience and provides a worst-case scenario of
regulatory impacts to steam electric power plants.
A detailed summary of how EPA developed these entity-level compliance cost and revenue values is
presented in Chapter 3 and Chapter 4.
8.2 Key Findings for Regulatory options
As described above, the EPA developed estimates of the number of small parent entities in the specified
cost-to-revenue impact ranges. Table 8-4 and Table 8-5 summarize the results of the analysis, with Table
8-4 showing baseline results and Table 8-5 showing incremental results of the four options relative to this
baseline. In terms of number of entities in each of the impact categories, analysis results for each option
are the same under Case 1 and Case 2; however, these numbers represent different percentages of all
small entities owning steam electric power plants under each weighting case.
In the baseline, the EPA estimates that 4 small entities owning steam electric power plants, all small
municipalities, would incur costs exceeding one percent of revenue (Table 8-4). The analysis shows no
EPA-821-R-19-012
8-6

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
8: RFA
small business entity or small entity in other categories incurring costs greater than one percent of revenue
under the baseline. On the basis of percentage, the four small municipalities represent approximately 11
to 14 percent of the number of small municipalities owning steam electric power plants and 3 to 5 percent
of the total number of small entities owning steam electric power plants. For 2 of the 4 municipalities (5
to 7 percent of the number of small municipalities owning steam electric power plants) costs are estimated
to exceed three percent of revenue.
Under Option 2, relative to the baseline 2 fewer small entities would incur costs exceeding one percent of
revenue, and 1 fewer small entity would incur costs exceeding three percent of revenue (Table 8-5).
Under the other three options, 1 fewer small entity would incur costs exceeding one percent of revenue,
and no change is estimated for the number of plants incurring costs greater than three percent of revenue.
On the basis of percentage of small entities by entity type across the range of owning entities, the analysis
of Option 2, shows 5 to 7 percent fewer small government entities incurring costs greater than one percent
of revenue, while under the other three options, which have the same results, approximately 3 percent
fewer small government entities incur costs greater than one percent of revenue (Table 8-5).
This screening-level analysis suggests that the baseline is unlikely to have a significant economic impact
on a substantial impact on small entities. And because the regulatory options reduce this impact further by
providing cost savings to many small entities, the same conclusion can be reached for the four regulatory
options the EPA analyzed.
Table 8-4: Estimated Baseline Cost-To-Revenue Impact on Small Parent Entities, by Entity Type
and Ownership Category

Case 1: Lower bound estimate of number of
Case 2: Upper bound estimate of number of

entities owning steam electric power plants
entities owning steam electric power plants

(out of total of 79 small entities)
(out of total of 127 small entities)

>1%
>3%a
>1%
>3%a
Entity
Number
% of all
Number
% of all
Number
% of all
Number
% of all
Type/Ownership
of small
small
of small
small
of small
small
of small
small
Category
entities
entities'5
entities
entities'5
entities
entities'5
entities
entities'5
E
Saseline
Small Business

Cooperative
0
0.0%
0
0.0%
0
0.0%
0
0.0%
Investor-Owned
0
0.0%
0
0.0%
0
0.0%
0
0.0%
Nonutility
0
0.0%
0
0.0%
0
0.0%
0
0.0%
Small Government

Municipality
4
13.8%
2
6.9%
4
10.8%
2
5.4%
Political
0
0.0%
0
0.0%
0
0.0%
0
0.0%
Subdivision








Total
4
5.1%
2
2.5%
4
3.1%
2
1.6%
a.	The number of entities with cost-to-revenue impact of at least three percent is a subset of the number of entities with such
ratios exceeding one percent.
b.	Percentage values were calculated relative to the total of 79 (Case 1) and 127 (Case 2) small entities owning steam electric
power plants regardless of whether these plants are estimated to incur compliance technology costs under any of the
regulatory options.
Source: U.S. EPA Analysis, 2019
EPA-821-R-19-012
8-7

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
8: RFA
Table 8-5: Estimated Incremental Cost-To-Revenue Impact on Small Parent Entities, by Entity
Type and Ownership Category

Case 1: Lower bound estimate of number
Case 2: Upper bound estimate of number

of entities owning steam electric power
of entities owning steam electric power


plants


plants


(out of total of 79 small entities)
(out of total of 127 small entities)

>1%
>3%a
>1%
>3%a
Entity
ANumber
A% of all
ANumber
A% of all
ANumber
A% of all
ANumber
A% of all
Type/Ownership
of small
small
of small
small
of small
small
of small
small
Category
entities
entities'5
entities
entities'5
entities
entities'5
entities
entities'5
Option 1
Small Business

Cooperative
0
0.0%
0
0.0%
0
0.0%
0
0.0%
Investor-Owned
0
0.0%
0
0.0%
0
0.0%
0
0.0%
Nonutility
0
0.0%
0
0.0%
0
0.0%
0
0.0%
Small Government

Municipality
-1
-3.4%
0
0.0%
-1
-2.7%
0
0.0%
Political Subdivision
0
0.0%
0
0.0%
0
0.0%
0
0.0%
Total
-1
-1.3%
0
0.0%
-1
-0.8%
0
0.0%
Option 2
Small Business

Cooperative
0
0.0%
0
0.0%
0
0.0%
0
0.0%
Investor-Owned
0
0.0%
0
0.0%
0
0.0%
0
0.0%
Nonutility
0
0.0%
0
0.0%
0
0.0%
0
0.0%
Small Government

Municipality
-2
-6.9%
-1
-3.4%
-2
-5.4%
-1
-2.7%
Political Subdivision
0
0.0%
0
0.0%
0
0.0%
0
0.0%
Total
-2
-2.5%
-1
-1.3%
-2
-1.6%
-1
-0.8%
Option 3
Small Business

Cooperative
0
0.0%
0
0.0%
0
0.0%
0
0.0%
Investor-Owned
0
0.0%
0
0.0%
0
0.0%
0
0.0%
Nonutility
0
0.0%
0
0.0%
0
0.0%
0
0.0%
Small Government

Municipality
-1
-3.4%
0
0.0%
-1
-2.7%
0
0.0%
Political Subdivision
0
0.0%
0
0.0%
0
0.0%
0
0.0%
Total
-1
-1.3%
0
0.0%
-1
-0.8%
0
0.0%
EPA-821-R-19-012
8-8

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
8: RFA
Table 8-5: Estimated Incremental Cost-To-Revenue Impact on Small Parent Entities, by Entity
Type and Ownership Category

Case 1: Lower bound estimate of number
Case 2: Upper bound estimate of number

of entities owning steam electric power
of entities owning steam electric power


plants


plants


(out of total of 79 small entities)
(out of total of 127 small entities)

>1%
>3%a
>1%
>3%a
Entity
ANumber
A% of all
ANumber
A% of all
ANumber
A% of all
ANumber
A% of all
Type/Ownership
of small
small
of small
small
of small
small
of small
small
Category
entities
entities'5
entities
entities'5
entities
entities'5
entities
entities'5
Option 4
Small Business

Cooperative
0
0.0%
0
0.0%
0
0.0%
0
0.0%
Investor-Owned
0
0.0%
0
0.0%
0
0.0%
0
0.0%
Nonutility
0
0.0%
0
0.0%
0
0.0%
0
0.0%
Small Government

Municipality
-1
-3.4%
0
0.0%
-1
-2.7%
0
0.0%
Political Subdivision
0
0.0%
0
0.0%
0
0.0%
0
0.0%
Total
-1
-1.3%
0
0.0%
-1
-0.8%
0
0.0%
a.	The number of entities with cost-to-revenue impact of at least three percent is a subset of the number of entities with such
ratios exceeding one percent.
b.	Percentage values were calculated relative to the total of 79 (Case 1) and 127 (Case 2) small entities owning steam electric
power plants regardless of whether these plants are estimated to incur compliance technology costs under any of the
regulatory options.
Source: U.S. EPA Analysis, 2019
8.3 Uncertainties and Limitations
Despite the EPA's use of the best available information and data, the RFA analysis discussed in this
chapter has sources of uncertainty, including:
•	None of the sample-weighting approaches used for this analysis accounts precisely for the
number of parent-entities and compliance costs assigned to those entities simultaneously. The
EPA assesses the values presented in this chapter as reasonable estimates of the numbers of small
entities that could incur a significant impact according to the cost-to-revenue metric.
•	In cases where available information was insufficient to determine the size of an entity, the
Agency generally assumed the entity to be small, with one exception. As noted in Table 8-2, the
EPA assumed one entity owned by a political subdivision to be large based on publicly available
information about the entity's identified assets. However, this large entity does not incur
compliance costs under the baseline or any of the four regulatory options and therefore the
assumption only affects the total number of entities in each size category {i.e., denominator used
to estimate the percent of entities).
•	As discussed in Chapter 4, the zero cost pass-through assumption represents a worst-case scenario
from the perspective of the plants and parent entities. To the extent that some entities are able to
pass at least some compliance costs to consumers through higher electricity prices, this analysis
EPA-821-R-19-012
8-9

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
8: RFA
overstates potential impact of the regulatory options on small entities and affect the assessment of
incremental effects of the regulatory options, although it would not affect the direction of those
effects.
8.4 Small Entity Considerations in the Development of Rule Options
As described in the introduction to this Chapter, the RFA requires federal agencies to consider the impact
of their regulatory actions on small entities and to analyze alternatives that minimize those impacts.
Although the EPA presents four regulatory options which would all reduce impacts to small entities, the
proposed option is the least costly option presented, and thus would result in the lowest impacts to small
entities. Furthermore, subcategories for low utilization and end of life units include units owned by small
entities. Furthermore, as the EPA explicitly states in the proposal, the implementation period built into the
regulatory options is another way for permit writers to consider the needs of small entities, as these
entities may need additional time to plan and finance capital improvements.
EPA-821-R-19-012
8-10

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
9: UMRA
3 Unfunded Mandates Reform Act (UMRA) Analysis
Title II of the Unfunded Mandates Reform Act of 1995, Pub. L. 104-4, requires that federal agencies
assess the effects of their regulatory actions on State, local, and Tribal governments and the private sector.
Under UMRA section 202, the EPA generally must prepare a written statement, including a cost-benefit
analysis, for proposed and final rules with "Federal mandates" that might result in expenditures by State,
local, and Tribal governments, in the aggregate, or by the private sector, of $100 million (adjusted
annually for inflation) or more in any one year (i.e., $160 million in 2018 dollars). Before promulgating a
regulation for which a written statement is needed, UMRA section 205 generally requires the EPA to
"identify and consider a reasonable number of regulatory alternatives and adopt the least costly, most
cost-effective, or least burdensome alternative that achieves the objectives of the rule." (2 U.S.C. 1535(a)
The provisions of section 205 do not apply when they are inconsistent with applicable law. Moreover,
section 205 allows the EPA to adopt an alternative other than the least costly, most cost-effective, or least
burdensome alternative, if the Administrator publishes with the rule an explanation of why that alternative
was not adopted. Before the EPA establishes any regulatory requirements that might significantly or
uniquely affect small governments, including Tribal governments, it must develop a small government
agency plan, under UMRA section 203. The plan must provide for notifying potentially affected small
governments, enabling officials of affected small governments to have meaningful and timely input in the
development of the EPA regulatory proposals with significant intergovernmental mandates, and
informing, educating, and advising small governments on compliance with regulatory requirements.
The EPA estimated the incremental costs for compliance with the regulatory options for different
categories of entities. All four regulatory options analyzed by the EPA result in lower compliance costs
(cost savings) when compared to the baseline. The Agency estimates that the maximum incremental cost
in any one year to government entities (excluding federal government) range from -$23.5 million under
Option 1 to -$6.0 million under Option 4.53'54 The maximum incremental cost in any given year to the
private sector range from -$444.5 million under Option 4 to -$327.5 million under Option 1. From these
incremental cost values, the EPA determined that the proposed rule does not contain a federal mandate
that may result in expenditures of $160 million (in 2018 dollars) or more for State, local, and Tribal
governments, in the aggregate, or the private sector in any one year, and in any case the proposed option
(Option 2) is the least costly option presented.
This chapter contains additional information to support that statement, including information on
compliance and administrative costs, and on impacts to small governments. Following the approach used
for the analysis of the 2015 rule (see Chapter 9 in U.S. EPA, 2015b), the annualized costs presented in
this UMRA analysis are calculated using the social cost framework presented in Chapter 12 of the BCA
document (U.S. EPA, 2019b). Specifically, this analysis uses costs in 2020 stated in 2018 dollars and
accounts for costs in the year they are anticipated to be incurred between 2021 and 2047. Non-recurring
costs are annualized over a 27-year period. As discussed in Chapter 10 (Other Administrative
Requirements; see Section 10.7) in this document, the regulatory options would not change the reporting
and recordkeeping burden for the review, oversight, and administration of the rule relative to baseline
53	Maximum costs are costs incurred by the entire universe of steam electric power plants in a given year of occurrence
under a given regulatory option. For all regulatory options, these maximum costs are smaller than the maximum costs
projected under the baseline, resulting in net cost savings.
54	For this analysis, rural electric cooperatives are considered to be a part of the private sector.
EPA-821-R-19-012
9-1

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
9: UMRA
requirements; consequently, NPDES permitting authorities are estimated to see no change in costs to
administer this rule. The only change in cost that government entities would potentially incur as the result
of this rule is that associated with the cost to implement control technologies at power plants they own.
For more details on how social costs were developed, see Chapter 12 in the BCA document.
9.1 UMRA Analysis of Impact on Government Entities
This part of the UMRA analysis assesses the compliance cost burden to State, local, and Tribal
governments that own existing steam electric power plants. The use of the phrase "government entities"
in this section does not include the federal government, which owns 20 of the 951 steam electric power
plants; four of these plants incur compliance costs under the regulatory options. Additionally, in
evaluating the magnitude of the impact of the options on government entities, the EPA considered only
compliance costs incurred by government entities owning steam electric power plants. Government
entities would not incur significant incremental administrative costs to implement the rule, regardless of
whether or not they own steam electric power plants.
Table 9-1 summarizes the number of State, local and Tribal government entities and the number of steam
electric power plants they own. The determination of owning entities, their type, and their size is detailed
in Chapter 4 (Cost and Economic Impact Screening Analyses) and Chapter 8 (Assessment of Potential
Impact of the Regulatory Options on Small Entities - Regulatory Flexibility Act (RFA) Analysis).
Table 9-1: Government-Owned Steam Electric Power Plants and Their Parent
Entities
Entity Type
Parent Entities3
Steam electric power plantsb
Municipality
59
123
Other Political Subdivision
10
34
State
2
4
Tribal
0
0
Total
71
160
a.	Counts of entities under weighting Case 1, which provides an upper bound of total compliance costs for
any given parent entity. For details see Chapter 8.
b.	Plant counts are relative to the estimated 951 plants covered under the point source category.
Source: U.S. EPA Analysis, 2019
Out of 951 steam electric power plants, 160 are owned by 71 government entities.55 The majority
(77 percent) of these government-owned plants are owned by municipalities, followed by other political
subdivisions (21 percent), and State governments (2 percent).
All four regulatory options result in government entities incurring lower compliance costs compared to
the baseline. Table 9-2 shows compliance costs for government entities owning steam electric power
plants. Compliance costs to government entities under the baseline are approximately $37.8 million in the
aggregate, with an average of $0.2 million per plant. As shown in Table 9-3, which shows the difference
between the options and the baseline, all four regulatory options by comparison provide cost savings to
Counts exclude federal government entities and steam electric power plants they own. The owning entity is determined
based on the entity with the largest ownership share in each plant, as described in Chapter 4.
EPA-821-R-19-012
9-2

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
9: UMRA
government owned plants. The estimated pre-tax savings range from $5.5 million (Option 4) to
$24.9 million (Option 2), with most of the aggregate savings going to municipalities. The maximum
annualized compliance costs estimated to be incurred by any single government-owned plant is also
generally lower under the regulatory options, with the sole exceptions being municipality and state-owned
plants under Option 4 which have greater maximum costs, at $6.2 million and $4.0 million respectively,
than the maximum costs projected under the baseline ($4.7 million and $3.8 million).
Table 9-2: Estimated Compliance Costs to Government Entities Owning Steam Electric Power
Plants (Millions; 2018$

Number of

Average



Steam Electric
Total Weighted,
Annualized Cost
Average
Maximum

Power Plants
Annualized Pre-
per MW of
Annualized Cost
Annualized Cost
Ownership Type
(weighted)3
Tax Cost3
Capacity13
per Plantc
per Plantd
Baseline
Municipality
123
$29.5
$643
$0.2
$4.7
Other Political Subdivision
34
$1.5
$53
$0.0
$1.5
State
4
$6.7
$1,405
$1.7
$3.8
Total
160
$37.8
$476
$0.2
$4.7
Option 1
Municipality
123
$19.0
$414
$0.2
$3.1
Other Political Subdivision
34
$1.2
$41
$0.0
$1.2
State
4
$2.4
$499
$0.6
$2.3
Total
160
$22.6
$285
$0.1
$3.1
Option 2
Municipality
123
$11.0
$240
$0.1
$3.2
Other Political Subdivision
34
$0.0
$1
$0.0
$0.0
State
4
$1.9
$387
$0.5
$1.8
Total
160
$12.9
$163
$0.1
$3.2
Option 3
Municipality
123
$21.0
$457
$0.2
$3.2
Other Political Subdivision
34
$1.2
$41
$0.0
$1.2
State
4
$3.0
$635
$0.8
$1.8
Total
160
$25.2
$318
$0.2
$3.2
Option 4
Municipality
123
$25.1
$547
$0.2
$6.2
Other Political Subdivision
34
$1.2
$41
$0.0
$1.2
State
4
$6.0
$1,258
$1.5
$4.0
Total
160
$32.3
$408
$0.2
$6.2
a. Plant counts are relative to the estimated 951 plants covered under the point source category.
b.	Average cost per MW values were calculated using total compliance costs and capacity for all steam electric power plants
owned by entities in a given ownership category. In case of multiple ownership structure where parent entities of a given
plant have equal ownership shares and are in different ownership categories, compliance costs and capacity were allocated to
appropriate ownership categories in accordance with ownership shares.
c.	Average cost per plant values were calculated using the total number of steam electric power plants owned by entities in a
given ownership category.
d.	Reflects maximum of un-weighted costs to surveyed plants only.
Source: U.S. EPA Analysis, 2019.
EPA-821-R-19-012
9-3

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
9: UMRA
Table 9-3: Estimated Incremental Compliance Costs to Government Entities Owning Steam
Electric Power Plants (Millions; 2018$

Number of

Average



Steam Electric
Total Weighted,
Annualized Cost
Average
Maximum

Power Plants
Annualized Pre-
per MW of
Annualized Cost
Annualized Cost
Ownership Type
(weighted)3
Tax Cost3
Capacity13
per Plantc
per Plantd
Option 1
Municipality
123
-$10.5
-$230
-$0.1
-$1.6
Other Political Subdivision
34
-$0.3
-$12
$0.0
-$0.3
State
4
-$4.3
-$906
-$1.1
-$1.5
Total
160
-$15.2
-$192
-$0.1
-$1.6
Option 2
Municipality
123
-$18.5
-$403
-$0.2
-$1.5
Other Political Subdivision
34
-$1.5
-$52
$0.0
-$1.5
State
4
-$4.9
-$1,018
-$1.2
-$2.0
Total
160
-$24.9
-$314
-$0.2
-$1.5
Option 3
Municipality
123
-$8.5
-$186
-$0.1
-$1.5
Other Political Subdivision
34
-$0.3
-$12
$0.0
-$0.3
State
4
-$3.7
-$769
-$0.9
-$2.0
Total
160
-$12.6
-$158
-$0.1
-$1.5
Option 4
Municipality
123
-$4.4
-$96
$0.0
$1.5
Other Political Subdivision
34
-$0.3
-$12
$0.0
-$0.3
State
4
-$0.7
-$146
-$0.2
$0.2
Total
160
-$5.5
-$69
$0.0
$1.5
a. Plant counts are relative to the estimated 951 plants covered under the point source category.
b.	Average cost per MW values were calculated using total compliance costs and capacity for all steam electric power plants
owned by entities in a given ownership category. In case of multiple ownership structure where parent entities of a given
plant have equal ownership shares and are in different ownership categories, compliance costs and capacity were allocated to
appropriate ownership categories in accordance with ownership shares.
c.	Average cost per plant values were calculated using the total number of steam electric power plants owned by entities in a
given ownership category.
d.	Reflects maximum of un-weighted costs to surveyed plants only.
Source: U.S. EPA Analysis, 2019.
9.2 UMRA Analysis of Impact on Small Governments
As part of the UMRA analysis, the EPA also assessed whether the regulatory options would significantly
and uniquely affect small governments. To assess whether the regulatory options would affect small
governments in a way that is disproportionately burdensome in comparison to the effect on large
governments, the EPA compared total incremental costs and costs per plant estimated to be incurred by
small governments with those values estimated to be incurred by large governments. The EPA also
compared the changes in per plant costs incurred for small government-owned plants with those incurred
by non-government-owned plants. The Agency evaluated costs per plant on the basis of both average and
maximum annualized incremental cost per plant.
EPA-821-R-19-012
9-4

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
9: UMRA
Out of 161 government-owned steam electric power plants, the EPA identified 38 plants that are owned
by 30 small government entities. These 38 plants constitute approximately 24 percent of all government-
owned plants.56
Table 9-4: Counts of Government-Owned Plants and Their Parent Entities, by Size

Entities3
Steam Electric Power Plantsb
Entity Type
Large
Small
Total
Large
Small
Total
Municipality
30
29
59
86
37
123
Other Political Subdivision
9
1
10
33
1
34
State
2
0
2
4
0
4
Total
41
30
71
123
38
161
a.	Counts of entities under weighting Case 1, which provides an upper bound of total compliance costs for any given parent
entity. For details see Chapter 8.
b.	Plant counts are relative to the estimated 951 plants covered under the point source category.
Source: U.S. EPA Analysis, 2019.
All four regulatory options result in small government entities incurring lower compliance costs
compared to the baseline. As presented in Table 9-5, overall compliance cost savings are greatest under
Option 2 and smallest under Option 4, but the distribution of cost savings among different entity
categories and sizes is not uniform. For Options 1, 2, and 3, aggregate compliance cost savings are the
largest for large private entities, followed by large governments, small private entities, and small
governments. Option 4, by contrast, results in lower costs incurred by governments (large and small) and
small private entities, but increased compliance costs for large private entities. On a per MW basis, small
governments are projected to see larger cost savings - as much as $2,103 per MW under Option 2 - than
large governments or private entities. Because plants owned by small governments tend to be smaller
compared to those owned by large governments or small private entities, the same is not necessarily true
on a per plant basis under Options 1 and 3. Given these results, the EPA finds that small governments
would not be significantly or uniquely affected by the regulatory options.
Table 9-5: Estimated Incremental Compliance Costs for Electric Generators by Ownership Type
and Size (2018$)




Average
Average
Maximum



Total Annualized
Annualized Pre-
Annualized Pre-
Annualized Pre-

Entity
Number of
Pre-Tax Costs
tax Cost per MW
tax Cost per
tax Cost per
Ownership Type
Size
Plantsa
(Millions)"
of Capacity13
Plant (Millions)c
Plant (Millions)
Option 1
Government
(excl. federal)
Small
38
1A
NJ
00
-$627
-$0.07
-$1.0
Large
122
-$12.4
-$166
-$0.10
-$2.4
Private
Small
101
-$8.6
-$252
-$0.08
-$1.7
Large
669
-$105.4
-$186
-$0.14
-$2.9
All Plants
951
-$154.0
-$218
-$0.15
-$15.7
Counts exclude federal government entities and steam electric power plants they own.
EPA-821-R-19-012
9-5

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
9: UMRA
Table 9-5: Estimated Incremental Compliance Costs for Electric Generators by Ownership Type
and Size (2018$)




Average
Average
Maximum



Total Annualized
Annualized Pre-
Annualized Pre-
Annualized Pre-

Entity
Number of
Pre-Tax Costs
tax Cost per MW
tax Cost per
tax Cost per
Ownership Type
Size
Plantsa
(Millions)"
of Capacity13
Plant (Millions)c
Plant (Millions)
Option 2
Government
(excl. federal)
Small
38
-$9.4
-$2,103
-$0.25
-$2.4
Large
122
-$15.4
-$206
-$0.13
-$1.5
Private
Small
101
-$11.0
-$320
-$0.10
-$2.5
Large
669
-$106.1
-$187
-$0.14
-$1.7
All Plants
951
-$166.2
-$235
-$0.16
-$15.7
Option 3
Government
(excl. federal)
Small
38
-$3.6
-$792
-$0.09
-$1.3
Large
122
-$9.0
-$120
-$0.07
-$1.5
Private
Small
101
-$7.4
-$217
-$0.07
-$2.2
Large
669
-$75.4
-$133
-$0.10
-$1.7
All Plants
951
-$119.5
-$169
-$0.12
-$15.7
Option 4
Government
(excl. federal)
Small
38
-$3.2
-$712
-$0.08
-$1.2
Large
122
-$2.3
-$30
-$0.02
$1.5
Private
Small
101
-$4.0
-$116
-$0.04
-$2.0
Large
669
$1.6
$3
$0.00
$0.6
All Plants
951
-$27.3
-$39
-$0.03
-$15.7
a. Plant counts are relative to the estimated 951 plants covered under the point source category.
b.	Average cost per MW values were calculated using total compliance costs and capacity for all steam electric power plants
owned by entities in a given ownership category, including plants that incur zero costs. In case of multiple ownership structure
where parent entities of a given plant have equal ownership shares and are in different ownership categories, compliance costs
and capacity were allocated to appropriate ownership categories in accordance with ownership shares.
c.	Average cost per plant values were calculated using total number of steam electric power plants owned by entities in a given
ownership category. As a result, plants with multiple majority owners are represented more than once in the denominator of
relevant cost per plant calculations.
Source: U.S. EPA Analysis, 2019.
9.3 UMRA Analysis of Impact on the Private Sector
As the final part of the UMRA analysis, this section reports the compliance costs projected to be incurred
by private entities.
Table 9-6 summarizes the total annualized costs, maximum one-year costs, and the year when maximum
costs are incurred by type of owner. As shown in the last two columns of the table, the four options result
in cost savings, both on an annualized basis and for the maximum one-year costs, when compared to the
baseline. The EPA estimates the incremental annualized pre-tax compliance costs for private entities to
range from -$ 117.0 million under Option 2 to -$2.4 million under Option 4.
EPA-821-R-19-012
9-6

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
9: UMRA
Table 9-6: Compliance Costs for Electric Generators by Ownership Type (2018$)





Incremental




Incremental
Maximum One-

Total

Year of
Annualized
Year Costs

Annualized
Maximum One-
Maximum
Costs Relative to
Relative to
Ownership Type
Costs
Year Costs
Costs3
Baseline
Baselineb
Baseline
Government (excl. federal)
$37.8
$44.1
2022
NA
NA
Private
$311.0
$841.3
2023
NA
NA
Option 1
Government (excl. federal)
$22.6
$20.5
2021
-$15.2
-$23.5
Private
$197.0
$513.8
2023
-$114.0
-$327.5
Option 2
Government (excl. federal)
$12.9
$21.1
2028
-$24.9
-$23.0
Private
$194.0
$436.4
2023
-$117.0
-$405.0
Option 3
Government (excl. federal)
$25.2
$22.5
2028
-$12.6
-$21.6
Private
$228.2
$438.2
2023
-$82.8
-$403.1
Option 4
Government (excl. federal)
$32.3
$38.1
2027
-$5.5
-$6.0
Private
$308.6
$396.8
2023
-$2.4
-$444.5
NA: Not applicable for the baseline.
a.	The year when the maximum cost occurs is driven by the modeled technology implementation schedule and is determined
based on the renewal of individual NPDES permits for plants owned by the different categories of entities. See Section 3.1.3 in
this report and BCA Chapter 11 for more details on the technology implementation years and assumptions on the timing of cost
incurrence.
b.	The maximum one-year cost does not necessarily occur on the same year for a given plant across all the options analyzed. For
the purpose of comparing the regulatory options to the baseline, the EPA used the maximum costs in any year rather than
comparing costs on a year-to-year basis to obtain the maximum difference.
Source: U.S. EPA Analysis, 2019.
9.4 UMRA Analysis Summary
The EPA estimates that none of the regulatory options would result in incremental expenditures of at least
$160 million for State and local government entities, in the aggregate, or for the private sector in any one
year. In fact, all four regulatory options provide net cost savings when compared to the baseline.
Furthermore, as discussed above, neither permitted plants nor permitting authorities are estimated to incur
significant additional administrative costs as the result of the regulatory options.
Consistent with Section 205, the EPA presents four regulatory options which would all reduce impacts to
governments and the private sector. The proposed option (Option 2) is the least costly option presented,
and thus would result in the lowest impacts to governments and the private sector. Furthermore, several
government and private sector plants would likely fall into subcategories which would provide additional
flexibility. Finally, the implementation period built into the regulatory options is another way for permit
writers to consider the site-specific needs of steam electric power plants.
EPA-821-R-19-012
9-7

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
10: Other Administrative Requirements
10 Other Administrative Requirements
This chapter presents analyses conducted in support of the regulatory options to address the requirements
of applicable Executive Orders and Acts. These analyses complement EPA's assessment of the
compliance costs, economic impacts, and economic achievability of the proposed ELG revisions, and
other analyses done in accordance with the RFA and UMRA, presented in previous chapters.
10.1 Executive Order 12866: Regulatory Planning and Review and Executive Order 13563:
Improving Regulation and Regulatory Review
Under Executive Order (E.O.) 12866 (58 FR 51735, October 4, 1993), the EPA must determine whether
the regulatory action is "significant" and therefore subject to review by the Office of Management and
Budget (OMB) and other requirements of the Executive Order. The order defines a "significant regulatory
action" as one that is likely to result in a regulation that may:
•	Have an annual effect on the economy of $100 million or more, or adversely affect in a material
way the economy, a sector of the economy, productivity, competition, jobs, the environment,
public health or safety, or State, local, or Tribal governments or communities; or
•	Create a serious inconsistency or otherwise interfere with an action taken or planned by another
agency; or
•	Materially alter the budgetary impact of entitlements, grants, user fees, or loan programs or the
rights and obligations of recipients thereof; or
•	Raise novel legal or policy issues arising out of legal mandates, the President's priorities, or the
principles set forth in the Executive Order.
Executive Order 13563 (76 FR 3821, January 21, 2011) was issued on January 18, 2011. This Executive
Order supplements Executive Order 12866 by outlining the President's regulatory strategy to support
continued economic growth and job creation, while protecting the safety, health and rights of all
Americans. Executive Order 13563 requires considering costs, reducing burdens on businesses and
consumers, expanding opportunities for public involvement, designing flexible approaches, ensuring that
sound science forms the basis of decisions, and retrospectively reviewing existing regulations.
Pursuant to the terms of Executive Order 12866, the EPA determined that the proposed rule is an
"economically significant regulatory action" because the action is likely to have an annual effect on the
economy of $100 million or more, although the direction of the effect is estimated to be a reduction in
costs when compared to the baseline. As such, the action is subject to review by OMB under Executive
Orders 12866 and 13563. Any changes made in response to OMB suggestions or recommendations will
be documented in the docket for this action.
The EPA prepared an analysis of the potential benefits and costs associated with this action; this analysis
is described in Chapter 13 of the BCA document (U.S. EPA, 2019b).
EPA-821-R-19-012
10-1

-------
Regulatory Impact Analysis for Steam Electric Power Generating ELGs
10: Other Administrative Requirements
As detailed in earlier chapters of this report, the EPA also assessed the impacts of the regulatory options
on the wholesale price of electricity (Chapter 5: Electricity Market Analyses), retail electricity prices by
consumer group (Chapter 7: Electricity Price Effects), and on employment or labor markets (Chapter 6:
Employment Effects).
10.2	Executive Order 13771: Reducing Regulation and Controlling Regulatory Costs
The proposed rule, when finalized, would be considered a deregulatory action under E.O. 13771,
Reducing Regulation and Controlling Regulatory Costs. As presented in Chapter 3 (Table 3-3), all four
regulatory options analyzed have total compliance costs less than zero, when compared to the baseline.
Accounting for the timing of the costs shows net social cost savings for all four options using a 7 percent
discount rate, and options 1, 2, and 3 using a 3 percent discount rate. See Chapter 12 in the BCA
document (U.S. EPA, 2019b) for details on the time profile of costs and annualized discounted costs.
10.3	Executive Order 12898: Federal Actions to Address Environmental Justice in Minority
Populations and Low-Income Populations
E.O. 12898 (59 FR 7629, February 11, 1994) requires that, to the greatest extent practicable and permitted
by law, each Federal agency must make the achievement of environmental justice (EJ) part of its mission.
E.O. 12898 provides that each Federal agency must conduct its programs, policies, and activities that
substantially affect human health or the environment in a manner that ensures such programs, policies,
and activities do not have the effect of (1) excluding persons (including populations) from participation
in, or (2) denying persons (including populations) the benefits of, or (3) subjecting persons (including
populations) to discrimination under such programs, policies, and activities because of their race, color, or
national origin.
To meet the objectives of E.O. 12898 and consistent with the EPA guidance on considering EJ in the
development of regulatory actions (U.S. EPA, 2015c), the EPA examined whether the benefits from the
regulatory options may be differentially distributed among population subgroups in the affected areas. As
described in Chapter 14 of the BCA document (U.S. EPA, 2019b) and building on the approach EPA
used in analyzing the 2015 rule, the EPA conducted three analyses to evaluate the EJ implications of the
proposed rule: (1) summarizing the demographic characteristics of individuals living in proximity to
steam electric power plants and thus are likely to be affected by the plant discharges and changes in air
emissions resulting from the proposed ELG (2) summarizing the demographic characteristics of
individuals served by public water systems (PWS) downstream from steam electric power plants and
potentially affected by bromide discharges, and (3) analyzing the human health impacts from consuming
self-caught fish on minority and/or low-income populations, as well as subsistence fishers.
Based on these EJ analyses, the EPA determined that the majority of impacted communities at the census
block, county, and tribal area levels are not poorer or more minority than national averages, but are when
compared to state averages. Therefore, the regulatory options could benefit or harm populations with EJ
concerns depending on each option's pollutant exposure potential. The EPA determined that the
regulatory options would not deny communities from the benefits of environmental improvements
estimated to result from compliance with the more stringent effluent limits, but the options may
EPA-821-R-19-012
10-2

-------
Regulatory Impact Analysis for Steam Electric Power Generating ELGs
10: Other Administrative Requirements
disproportionally affect communities in cases where the rule may result in small increases in pollutant
exposure compared to baseline.
10.4 Executive Order 13045: Protection of Children from Environmental Health Risks and
Safety Risks
Executive Order 13045 (62 FR 19885, April 23, 1997) applies to any rule that (1) is determined to be
"economically significant" as defined under Executive Order 12866 and (2) concerns an environmental
health or safety risk that the EPA has reason to believe might have a disproportionate effect on children.
If the regulatory action meets both criteria, the Agency must evaluate the environmental health and safety
effects of the planned rule on children and explain why the planned regulation is preferable to other
potentially effective and reasonably feasible alternatives considered by the Agency.
As detailed in the Supplemental EA and BCA document (U.S. EPA, 2019c; 2019b), the EPA identified
several ways in which the regulatory options would affect children, including by potentially increasing
health risk from exposure to pollutants present in steam electric power plant discharges. The potential
increases are estimated to be small and arise from less stringent limits or later deadlines for meeting
effluent limits under certain regulatory options as compared to the baseline. The EPA quantified the
changes in IQ losses from lead exposure among pre-school children and from mercury exposure in-utero
resulting from maternal fish consumption under the four regulatory options, as compared to the baseline.
The EPA also estimated changes in the number of children with very high blood lead concentrations
(above 20 ug/dL) and IQs less than 70 may requiring compensatory education tailored to their specific
needs.
The EPA estimated that the regulatory options could have a small impact on children. The analysis shows
small potential changes in lead exposure (from fish consumption) for an average of 1.5 million children
annually, and in mercury exposure (from maternal fish consumption) for an average of 203,000 infants
born annually. However, the EPA estimates the resulting health impacts to be small. The EPA estimated
that the regulatory options would lead to slight increases in lead and mercury exposure, increasing IQ
losses by approximately four points from lead exposure and between 400 and 3,800 points from mercury
exposure over the entire exposed population across all four options. The social welfare effects from
increased IQ loss associated with children's exposure to lead and mercury range from -$0.4 million to -
$3.3 million across all regulatory options, using a 3 percent discount rate. Chapter 5 in the BCA
document provides further details (U.S. EPA, 2019b). An estimated 7.2 million children aged 0 to 18
years live in households served by drinking water systems that use source waters downstream of steam
electric power plants. As detailed in Chapter 4 of the BCA document (U.S. EPA, 2019b), ELG regulatory
options may affect the quality of public water supplies by changing pollutant loads to source waters. In
particular, the EPA estimates that three of the four regulatory options may reduce children's exposure to
trihalomethanes and other disinfection byproducts in drinking water and thus reduce their lifetime risk of
developing bladder cancer. The EPA did not estimate children-specific risk since these adverse health
effects generally follow long-term exposure.
The EPA did not quantify additional benefits to children from changes in exposure to steam electric
pollutant discharges due to data limitations. These include changes in the incidence or severity of other
EPA-821-R-19-012
10-3

-------
Regulatory Impact Analysis for Steam Electric Power Generating ELGs
10: Other Administrative Requirements
health effects from exposure to lead, mercury, and other pollutants including arsenic, boron, cadmium,
copper, nickel, selenium, thallium, and zinc.
10.5	Executive Order 13132: Federalism
Executive Order 13132 (64 FR 43255, August 10, 1999) requires the EPA to develop an accountable
process to ensure "meaningful and timely input by State and local officials in the development of
regulatory policies that have federalism implications." Policies that have federalism implications are
defined in the Executive Order to include regulations that have "substantial direct effects on the States, on
the relationship between the national government and the States, or on the distribution of power and
responsibilities among the various levels of government."
Under section 6 of Executive Order 13132, the EPA may not issue a regulation that has federalism
implications, that imposes substantial direct compliance costs, and that is not required by statute unless
the federal government provides the funds necessary to pay the direct compliance costs incurred by State
and local governments or unless the EPA consults with State and local officials early in the process of
developing the regulation. The EPA also may not issue a regulation that has federalism implications and
that preempts State law, unless the Agency consults with State and local officials early in the process of
developing the regulation.
The EPA has concluded that this action would not have federalism implications. As discussed in earlier
chapters of this document, the EPA anticipates that this proposed action would not impose a significant
incremental administrative burden on States from issuing, reviewing, and overseeing compliance with
discharge requirements. With respect to direct compliance costs, while the regulatory options may impose
such costs on State or local governments that own steam electric power plants, and the Federal
government would not provide the funds necessary to pay those costs, the regulatory options are
estimated to provide savings to State or local governments when compared to the costs they would incur
under the baseline.
Specifically, the EPA has identified 160 steam electric power plants that are owned by State or local
government entities or other political subdivisions. The EPA estimates that the maximum compliance cost
in any one year to governments (excluding federal government) ranges from $20.5 million under Option 1
to $38.1 million under Option 4 (see Chapter 9: Unfunded Mandates Reform Act (UMRA) for details).
This is compared to a maximum compliance cost to governments of $44.1 million under the baseline.
Annualized cost savings to governments range from $5.5 million under Option 4 to $24.9 million under
Option 2.
10.6	Executive Order 13175: Consultation and Coordination with Indian Tribal Governments
Executive Order 13175 (65 FR 67249, November 6, 2000) requires the EPA to develop an accountable
process to ensure "meaningful and timely input by tribal officials in the development of regulatory
policies that have tribal implications." "Policies that have tribal implications" is defined in the Executive
Order to include regulations that have "substantial direct effects on one or more Indian Tribes, on the
relationship between the Federal government and the Indian Tribes, or on the distribution of power and
responsibilities between the federal government and Indian Tribes."
EPA-821-R-19-012
10-4

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
10: Other Administrative Requirements
The EPA assessed potential tribal implications for the regulatory options arising from three main changes,
as described below: (1) direct compliance costs incurred by plants; (2) impacts on drinking water systems
downstream from steam electric power plants; and (3) administrative burden on governments that
implement the NPDES program.
•	Direct compliance costs: The EPA's analyses show that no plant estimated to be affected by the
regulatory options is owned by tribal governments.
•	Impacts on drinking water systems: The EPA identified 15 public water systems operated by
tribal governments that may be affected by bromide discharges from steam electric power
plants.57 These systems serve a total of 18,917 people. This analysis finds small changes in
exposure between baseline and the evaluated options and therefore small changes in risk for this
population. The analysis is detailed in Chapter 4 of the BCA (U.S. EPA, 2019b).
•	Administrative burden: No tribal governments are currently authorized pursuant to section 402(b)
of the CWA to implement the NPDES program.
10.7 Executive Order 13211: Actions Concerning Regulations That Significantly Affect Energy
Supply, Distribution, or Use
Executive Order 13211 requires Agencies to prepare a Statement of Energy Effects when undertaking
certain agency actions. Such Statements of Energy Effects shall describe the effects of certain regulatory
actions on energy supply, distribution, or use, notably: (i) any adverse effects on energy supply,
distribution, or use (including a shortfall in supply, price increases, and increased use of foreign supplies)
should the proposal be implemented, and (ii) reasonable alternatives to the action with adverse energy
effects and the estimated effects of such alternatives on energy supply, distribution, and use.
The OMB implementation memorandum for Executive Order 13211 outlines specific criteria for
assessing whether a regulation constitutes a "significant energy action" and would have a "significant
adverse effect on the supply, distribution or use of energy."58 Those criteria include:
•	Reductions in crude oil supply in excess of 10,000 barrels per day;
•	Reductions in fuel production in excess of 4,000 barrels per day;
•	Reductions in coal production in excess of 5 million tons per year;
•	Reductions in natural gas production in excess of 25 million mcf per year;
•	Reductions in electricity production in excess of 1 billion kilowatt-hours per year, or in excess of
500 megawatts of installed capacity;
The EPA included public water systems identified in the EPA's Safe Drinking Water Information System as having a
tribe as the primacy agency and one tribe-operated system with the state of Oklahoma as the primacy agency.
Executive Order 13211 was issued May 18, 2002. The OMB later released an Implementation Guidance memorandum
on July 13,2002.
EPA-821-R-19-012
10-5

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
10: Other Administrative Requirements
•	Increases in the cost of energy production in excess of 1 percent;
•	Increases in the cost of energy distribution in excess of 1 percent;
•	Significant increases in dependence on foreign supplies of energy; or
•	Having other similar adverse outcomes, particularly unintended ones.
None of the criteria above regarding potential significant adverse effects on the supply, distribution, or
use of energy (listed above) apply to the proposed rule. While the regulatory options might affect (1) the
production of electricity, (2) the amount of installed capacity, (3) the cost of energy production, and (4)
the dependence on foreign supplies of energy, the four options analyzed by the EPA provide cost savings
when compared to the baseline, reducing electricity generation costs. As described below and
demonstrated by the results from the national electricity market analyses conducted for two regulatory
options (Options 2 and 4) (see Chapter 5: Electricity Market Analyses), changes for the first three factors
are in a direction than does not present a concern under this Executive Order or are smaller than the
thresholds of concern specified by OMB.
10.7.1	Impact on Electricity Generation
The electricity market analyses (Chapter J) estimate that under Option 2 coal-fired generation, including
generation from power plants to which the option applies, would increase by about 0.1 percent to 0.6
percent in 2030 through 2050, relative to baseline generation. Coal-fired generation under Option 4 would
change from a decline of 0.2 percent to an increase of 0.3 percent during that same period, depending on
the year. Under both options, the changes in coal-fired generation would be offset by roughly
corresponding changes in production from other plants, resulting in no net decrease in overall production;
electricity generated in 2030 increases by 95 GWh and 215 GWh respectively for Options 2 and 4 in
2030, which is less than 0.01 percent of baseline generation. These changes are very small, and
consequently, the EPA does not believe that the proposed rule constitutes a "significant energy action" in
terms of overall impact on electricity generation.
10.7.2	impact on Electricity Generating Capacity
As documented in Chapter 5, the Agency's electricity market analysis estimated that by 2030 Option 2
would result in net avoided retirement of 893 MW of generating capacity, whereas Option 4 would result
in net avoided retirement of 724 MW of generating capacity.
10.7.3	Cost of Energy Production
Based on the IPM analysis results, the EPA estimated that the regulatory options would not significantly
affect the total cost of electricity production. At the national level, total electricity generation costs (fuel,
variable O&M, fixed O&M and capital) under Option 2 are projected to decrease by 0.1 percent, whereas
production costs under Option 4 are essentially unchanged (less than 0.01 percent change). At the
regional level, the change in electricity generation costs varies. Table 5-4 in Chapter 5 summarizes
changes projected in IPM for the 2030 run year and shows range from a decrease of 0.3 percent in RFC
under Option 2 to negligible increases (less than 0.1 percent) in several regions under either Option 2 or
Option 4. None of the NERC regions show increases approaching 1 percent under either option.
EPA-821-R-19-012
10-6

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
10: Other Administrative Requirements
Consequently, no region would experience energy price increases greater than the 1 percent threshold as a
result of the regulatory options in either the short or the long run. Consequently, the EPA does not believe
that the proposed rule constitutes a "significant energy action" in terms of estimated potential effects on
the cost of energy production.
10.7.4 Dependence on Foreign Supply of Energy
The EPA's electricity market analyses did not support explicit consideration of the effects of the
regulatory options on foreign imports of energy. However, the regulatory options directly affect electric
power plants, which generally do not face significant foreign competition. Only Canada and Mexico are
connected to the U.S. electricity grid, and transmission losses are substantial when electricity is
transmitted over long distances. In addition, the effects on installed capacity and electricity prices are
estimated to be small.
Table 10-1 presents IPM projected generating capacity and generation by type in 2030 under the baseline
and for regulatory options 2 and 4. Under Option 2, coal-based electricity generation is projected to
increase by 0.6 percent, while generation using several other sources of energy is estimated to either
decrease (natural gas, biomass, solar) or increase (i.e., oil/gas steam, landfill gas) depending on the type.
Changes are less than 1 percent across all generation types.
Table 10-1: Total Market-Level Capacity and Generation by Type for Options 2 and 4 in 2030
Type
Generating Capacity (GW)
Electricity Generation (Thousand GWh)
Base
Case
Option 2
%
Change
Option 4
%
Change
Base
Case
Option 2
%
Change
Option 4
%
Change
Hydro
110.6
110.6
-0.03%
110.5
-0.08%
326.1
326.0
-0.05%
325.8
-0.11%
Biomass
0.4
0.4
0.00%
0.4
0.00%
2.1
2.1
-0.20%
2.1
-0.36%
Geothermal
3.0
3.0
0.00%
3.0
0.00%
21.2
21.2
0.00%
21.2
0.00%
Landfill Gas
1.9
1.9
0.00%
1.9
0.00%
9.9
9.9
0.02%
9.9
0.08%
Solar
110.8
110.6
-0.24%
110.8
-0.05%
202.3
201.9
-0.19%
202.2
-0.04%
Wind
149.9
149.8
-0.06%
149.9
0.01%
494.7
494.3
-0.08%
494.8
0.01%
Coal
169.9
171.0
0.65%
170.6
0.41%
882.2
887.1
0.56%
883.6
0.16%
Nuclear
76.6
76.5
-0.11%
76.7
0.10%
604.0
603.3
-0.12%
604.7
0.11%
Natural Gas
425.8
425.3
-0.12%
425.4
-0.11%
1,656.4
1,653.1
-0.20%
1,654.6
-0.11%
Oil/Gas
Steam
71.7
71.5
-0.22%
71.6
-0.08%
56.9
57.0
0.10%
57.1
0.37%
Others
12.5
12.5
0.00%
12.5
0.00%
37.0
37.0
0.09%
37.0
0.08%
Total3
1,133.3
1,133.2
0.00%
1,133.4
0.01%
4,292.8
4,292.8
0.00%
4,293.0
0.01%
a. Numbers may not add up due to rounding.
Source: U.S. EPA Analysis, 2019.
Table 10-2 presents the corresponding projections of the quantity of fuel used for power generation.
Changes are consistent with changes in generation presented in Table 10-1 with greater coal consumed
(0.5 percent and 0.1 percent for Options 2 and 4, respectively) and less natural gas (0.2 percent and 0.1
percent for Options 2 and 4, respectively). Changes are generally less than 1 percent, with the exception
of bituminous coal consumption which increases by 1.1 percent under Option 2.
EPA-821-R-19-012
10-7

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
10: Other Administrative Requirements
Table 10-2: Total Market-Level Fuel Use by Fuel Type for Options 2 and 4 in 2030
Fuel Consumption
Fuel Type
Baseline
Option 2
% Change
Option 4
% Change
Coal (million tons)
484
486
0.50%
484
0.14%
Bituminous Coal (million tons)
151
153
1.14%
152
0.54%
Subbituminous Coal (million
280
280
0.25%
280
-0.05%
tons)





Lignite (million tons)
53
53
-0.05%
53
0.01%
Natural Gas (trillion cubic feet)
12
12
-0.17%
12
-0.07%
Source: U.S. EPA Analysis, 2019.
Given the very small changes in coal and other fuels use under the two options, it is reasonable to assume
that any increase in demand for fuel used in electricity generation would be met through domestic supply,
thereby not increasing U.S. dependence on foreign supply of energy. Consequently, the EPA does not
believe that the proposed rule constitutes a "significant energy action" from the perspective of energy
independence.
10.7.5 Overall £. 0.13211 Finding
From these analyses and the electricity markets analysis in Chapter 5, the EPA concludes that the
regulatory options would not have a significant adverse effect at a national or regional level under
Executive Order 13211. Specifically, the Agency's analysis found that the regulatory options would not
reduce electricity production in excess of 1 billion kilowatt hours per year or in excess of 500 megawatts
of installed capacity under either of the options analyzed, nor would the option increase U.S. dependence
on foreign supply of energy. As such, the proposed ELG does not constitute a significant regulatory
action under Executive Order 13211 and the EPA did not prepare a Statement of Energy Effects.
10.8 Paperwork Reduction Act of 1995
The Paperwork Reduction Act of 1995 (PRA) (superseding the PRA of 1980) is implemented by OMB
and requires that agencies submit a supporting statement to OMB for any information collection that
solicits the same data from more than nine parties. The PRA seeks to ensure that Federal agencies balance
their need to collect information with the paperwork burden imposed on the public by the collection.
The definition of "information collection" includes activities required by regulations, such as permit
development, monitoring, record keeping, and reporting. The term "burden" refers to the "time, effort, or
financial resources" the public expends to provide information to or for a Federal agency, or to otherwise
fulfill statutory or regulatory requirements. PRA paperwork burden is measured in terms of annual time
and financial resources the public devotes to meet one-time and recurring information requests (44 U.S.C.
3502(2); 5 C.F.R. 1320.3(b)). Information collection activities may include:
•	reviewing instructions;
•	using technology to collect, process, and disclose information;
•	adjusting existing practices to comply with requirements;
•	searching data sources;
EPA-821-R-19-012
10-8

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
10: Other Administrative Requirements
•	completing and reviewing the response; and
•	transmitting or disclosing information.
Agencies must provide information to OMB on the parties affected, the annual reporting burden, the
annualized cost of responding to the information collection, and whether the request significantly impacts
a substantial number of small entities. An agency may not conduct or sponsor, and a person is not
required to respond to, an information collection unless it displays a currently valid OMB control number.
OMB has previously approved the information collection requirements contained in the existing
regulations 40 CFR part 423 under the provisions of the Paperwork Reduction Act.59
The regulatory options would not result in any significant change in the information collection
requirements associated with initial permit application, re-permitting activities, and activities associated
with monitoring and reporting after the permit is issued beyond those already required under the existing
NPDES program.
The EPA estimated small changes in monitoring costs due to changes in the number of pollutants for
which the EPA is proposing limits and standards, as well as monitoring of flow under the high recycle
rate systems for bottom ash; the Agency accounted for these costs as part of its analysis of the economic
impacts of the regulatory options (see Chapter 3: Compliance Costs). In some cases, in lieu of these
monitoring requirements, steam electric power plants would have additional paperwork burden such as
that associated with certifications and applicable BMP plans. However, plants would also realize savings,
relative to the baseline, by no longer monitoring pollutants for some subcategories (and because their
requirements are based on less costly technologies). The EPA projects that the burden associated with the
new proposed paperwork requirements would be largely offset by the reduced burden associated with less
monitoring; therefore, it projects that the proposal would have no net effect on the burden in the approved
information collection requirements.
With respect to permitting authorities, based on the information in its record, the EPA also does not
expect any of the regulatory options to increase or decrease their burden. The regulatory options would
not change permit application requirements or the associated review; they would not affect the number of
permits issued to steam electric power plants; nor would it change the efforts involved in developing or
reviewing such permits. Accordingly, the EPA estimated no net change (increase or decrease) in the cost
burden to federal or state governments or dischargers associated with any of the regulatory options in this
proposed rule.
10.9 National Technology Transfer and Advancement Act
Section 12(d) of the National Technology Transfer and Advancement Act (NTTAA) of 1995, Pub L. No.
104-113, Sec. 12(d) directs EPA to use voluntary consensus standards in its regulatory activities unless
doing so would be inconsistent with applicable law or otherwise impractical. Voluntary consensus
standards are technical standards (e.g., materials specifications, test methods, sampling procedures, and
business practices) that are developed or adopted by voluntary consensus standard bodies. The NTTAA
OMB has assigned control number 2040-0281 to the information collection requirements under 40 CFR part 423.
EPA-821-R-19-012
10-9

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
10: Other Administrative Requirements
directs the EPA to provide Congress, through the OMB, explanations when the Agency decides not to use
available and applicable voluntary consensus standards.
The regulatory options do not involve technical standards, for example in the measurement of pollutant
loads. Nothing in the regulatory options would prevent the use of voluntary consensus standards for such
measurement where available, and the EPA encourages permitting authorities and regulated entities to do
so. Therefore, the EPA is not considering the use of any voluntary consensus standards.
EPA-821-R-19-012
10-10

-------
RIA for Proposed Revisions to Steam Electric Power Generating ELGs
11: References
11 Cited References
Berman, E., & Bui, L. T. (2001). Environmental Regulation and Productivity: Evidence from Oil
Refineries. The Review of Economics and Statistics, 498-510.
Chang, T., J. Graff Zivin, T. Gross, and M. Neidell. 2016. Particulate Pollution and the Productivity of
Pear Packers. American Economic Journal, Vol. 8 No. 3. 141-169.
Coglianese, J., T. Gerarden, and J. H. Stock. 2018. The Effects of Fuel Prices, Regulations, and Other
Factors on U.S. Coal Production, 2008-2016.
Durlauf, S. 2004. "Neighborhood Effects." Handbook of Regional and Urban Economics, Vol. 4, J.V.
Henderson and J.F.Thisse, eds. Amsterdam: North Holland.
Federation of Tax Administrators. 2018. Range of State Corporate Income Tax Rates (for Tax Year 2018,
as of January 1, 2018).
Fell, H., and D. T. Kaffine. 2018. The Fall of Coal: Joint Impacts of Fuel Prices and Renewables on
Generation and Emissions. American Economic Journal: Economic Policy 2018, 10(2): 90-116
Ferris, A. E., Shadbegian, R. J., & Wolverton, A. (2014). The Effect of Environmental Regulation on
Power Sector Employment: Phase I of the Title IV S02 Trading Program. Journal of the
Association of Environmental and Resource Economists, 521-553.
Graff Zivin, J., & Neidell, M. (2012). The Impact of Pollution on Worker Productivity. American
Economic Review, 3652-73.
Graff Zivin, J., & Neidell, M. (2013). Environment, Health, and Human Capital. Journal of Economic
Literature, 689-730.
Gray, W. B., Shadbegian, R. J., Wang, C., & Cebi, M. (2014). Do EPA Regulations Affect Labor
Demand? Evidence from the Pulp and Paper Industry. Journal of Environmental Economics and
Management, 188-202.
Greenstone, M. (2002). The Impacts of Environmental Regulations on Industrial Activity: Evidence from
the 1970 and 1977 Clean Air Act Amendments and the Census of Manufactures. Journal of
Political Economy, 1175-1219.
Knittel, C. R., K. Metaxoglou, and A. Trindade. 2015. Natural Gas Prices and Coal Displacement:
Evidence from Electricity Markets. National Bureau of Economic Research Working Paper No.
21627.
Kolstad, C. D. (2017). What is Killing the U.S. Coal Industry. Retrieved from Stanford Institute for
Economic Policy Research: https://siepr.stanford.edu/research/publications/what-killing-us-coal-
industry
EPA-821-R-19-012
11-1

-------
RIA for Proposed Revisions to Steam Electric Power Generating ELGs
11: References
Linn, J., and K. McCormack. 2017. The Roles of Energy Markets and Environmental Regulation in
Reducing Coal-Fired Plant Profits and Electricity Sector Emissions. Resources for the
Future. October 23, 2017.
List, J. A., L., M. D., Fredriksson, P. G., & McHone, W. W. (2003). Effects of Environmental
Regulations on Manufacturing Plant Births: Evidence from a Propensity Score Matching
Estimator. The Review of Economics and Statistics, p.944-952.
McGraw Hill Construction. Engineering News-Record. 2018. Construction Cost Index (CCI).
Mills, A., R. Wiser, and J Seel. 2017. Power Plant Retirements: Trends and Possible Drivers. November
2017. Retrieved from Lawrence Berkeley National Laboratory:
https://emp.lbl.gov/sites/default/files/lbnl retirements data synthesis final.pdf
Schmalansee, R., and R. Stavins. 2011. "A Guide to Economic and Policy Analysis for the Transport
Rule." White Paper. Boston, MA. Exelon Corp.
Scott, M. 2018. Nuclear Power Outlook. Retrieved from EIA Annual Energy Outlook 2018:
https://www.eia.gov/outlooks/aeo/npo.php. May 7, 2018.
Sheriff, G., A.E. Ferris, and R.J. Shadbegian. 2019. How Did Air Quality Standards Affect Employment
at US Power Plants? The Importance of Timing, Geography, and Stringency. Journal of the
Association of Environmental and Resource Economists, Vol. 6, No. 1.111-149.
U.S. Bureau of Economic Analysis (U.S. BEA). 2018. Table 1.1.9 Implicit Price Deflators for Gross
Domestic Product (GDP Deflator).
U.S. Department of Commerce (U.S. DOC). U.S. Census Bureau. 2016. American Community Survey.
2012-2016 American Community Survey 5-Year Estimates.
U.S. Department of Labor. Bureau of Labor Statistics (BLS). 2018. Total compensation for All Civilian
workers in All industries and occupations, Index.
U.S. Department of Energy (U.S. DOE). 2012. North American Electric Reliability Corporation (NERC)
Regions. Available at: http://www.eia.gov/cneaf/electricity/chg_str_fuel/html/fig02.html.
U.S. Energy Information Administration (EIA). 2017a. Form EIA-860 Detailed Data: Final 2016 Data.
Released November 9, 2017.
U.S. Energy Information Administration (EIA). 2017b. Annual Electric Power Industry Report, Form
EIA-861 detailed data files: Final 2016 Data. Released November 9, 2017.
U.S. Energy Information Administration (EIA). 2017c. Form EIA-923 Detailed Data: Annual Release
2016 Final Data. Released November 9, 2017
U.S. Energy Information Adminstration (EIA). 2017d. Most coal plants in the United States were built
before 1990. April 17, 2017.
U.S. Energy Information Administration (EIA). 2018a. Annual Energy Outlook 2018. February 2018
EPA-821-R-19-012
11-2

-------
RIA for Proposed Revisions to Steam Electric Power Generating ELGs
11: References
U.S. Energy Information Administration (EIA). 2018b. Almost all power plants that retired in the past
decade were powered by fossil fuels. December 19, 2018.
U.S. Energy Information Administration (EIA). 2018c. Petroleum, natural gas, and coal still dominate
U.S. energy consumption. July 3, 2018.
U.S. Energy Information Administration (EIA). 2019. More than 60% of electric generating capacity
installed in 2018 was fueled by natural gas. March 11, 2019
U.S. Environmental Protection Agency (U.S. EPA). 2006. Final Guidance for EPA Rulewriters:
Regulatory Flexibility Act as Amended by the Small Business Regulatory Enforcement Fairness
Act. November 2006.
U.S. Environmental Protection Agency (U.S. EPA). 2010a. Guidelines for Preparing Economic Analyses.
December 17, 2010 (including May 2014 and March 2016 revisions).
U.S. Environmental Protection Agency (U.S. EPA). 2010b. Questionnaire for the Steam Electric Power
Generating Effluent Guidelines. June.
U.S. Environmental Protection Agency (U.S. EPA). 2014. Economic Analysis forthe Final Section
316(b) Existing Facilities Rule. EPA 821-R-14-001. U.S. EPA Office ofWater. May 2014.
U.S. Environmental Protection Agency (U.S. EPA). 2015a. Benefit and Cost Analysis for the Effluent
Limitations Guidelines and Standards for the Steam Electric Power Generating Point Source
Category. EPA 821-R-15-005. U.S. EPA Office ofWater.
U.S. Environmental Protection Agency (U.S. EPA). 2015b. Regulatory Impact Analysis forthe Effluent
Limitations Guidelines and Standards for the Steam Electric Power Generating Point Source
Category EPA-821-R-15-004. U.S. EPA Office ofWater.
U.S. Environmental Protection Agency (U.S. EPA). 2015c. Guidance on Considering Environmental
Justice during the Development of Regulatory Actions. May 2015. Available at
http://www.epa.gov/environmentaliustice/resources/policv/ei-rulemaking.html. Accessed June 22.
2015.
U.S. Environmental Protection Agency (U.S. EPA). 2018a. Documentation for EPA's Power Sector
Modeling Platform v6 Using the Integrated Planning Model. May 2018
U.S. Environmental Protection Agency (U.S. EPA). 2018b. Updates in EPA617_BC_461_No45Q.
Undated
U.S. Environmental Protection Agency (U.S. EPA). 2019a. Technical Development Document for
Proposed Revisions to Effluent Limitations Guidelines and Standards for the Steam Electric
Power Generating Point Source Category.
U.S. Environmental Protection Agency (U.S. EPA). 2019b. Benefit and Cost Analysis for Proposed
Revisions to Effluent Limitations Guidelines and Standards for the Steam Electric Power
Generating Point Source Category.
EPA-821-R-19-012
11-3

-------
RIA for Proposed Revisions to Steam Electric Power Generating ELGs
11: References
U.S. Environmental Protection Agency (U.S. EPA). 2019c. Environmental Assessment for Proposed
Revisions to Effluent Limitations Guidelines and Standards for the Steam Electric Power
Generating Point Source Category.
U.S. Environmental Protection Agency (U.S. EPA). 2019d. Regulatory Impact Analysis for Repeal of the
Clean Power Plan; Emission Guidelines for Greenhouse Gas Emissions from Existing Electric
Utility Generating Units; Revisions to Emission Guidelines Implementing Regulations. EPA-
452/R-19-003. June 2019.
U.S. Office of Management and Budget (U.S. OMB). 2003. Circular A-4. (Updated 2009).
U.S. Small Business Administration (SBA). 2017. Table of Small Business Size Standards Matched to
North American Industry Classification System Codes. Effective October 1, 2017
Walker, W. R. (2011). Environmental Regulation and Labor Reallocation: Evidence from the Clean Air
Act. American Economic Review, 442-447.
Walker, W. R. (2013). The Transitional Costs of Sectoral Reallocation: Evidence from the Clean Air Act
and the Workforce. Quarterly Journal of Economics, 1787-1835.
EPA-821-R-19-012
11-4

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
Appendix A: Summary of Changes
A Summary of Changes to Costs and Economic Impact Analysis
Table A-l summarizes the principal methodological changes the EPA made to analyses of the costs and
economic impacts of the proposed ELG reconsideration rule as compared to analysis of the 2015 rule
described in the 2015 RIA document (U.S. EPA, 2015b).
Table A-1: Changes to Costs and Economic Impacts Analysis Since Proposal
Cost or Impact Category
Analysis Component
Cost or Impact Category
General assumptions
Dollar year [all costs expressed in 2013
dollars]
Updated dollar year [2018]
Promulgation year [all costs and revenue
streams discounted back to 2015]
Updated promulgation year [2020]
Period of analysis [2019-2042]
Updated period of analysis [2021-2047]
Technology implementation years [2019-
2023]	
Technology implementation years
constant across the options for a given
plant
Updated technology implementation years
[2021-2028]
General inputs for
screening-level analyses
Generation, plant revenue, and estimated
electricity prices using EIA-861 and EIA-
923 databases; six-year (2007-2012)
average values
Updated with data from more current EIA-
861 and EIA-923 databases to use more
recent six-year [2011-2016] average values
Generating capacity from 2012 EIA-860
Updated using 2016 EIA-860
Electricity revenue, sales, and number of
consumers by consumer class (residential,
industrial, commercial, and
transportation) for ASCC and HICC regions
from EIA-861 for [2012]
Updated to use data from EIA-861 for
[2016]
Electricity revenue, sales, and number of
consumers by consumer class (residential,
industrial, commercial, and
transportation) for NERC regions other
than ASCC and HICC regions from [2013]
AEO projections
Updated using [2018] AEO projections
Industry profile
Total count of plants (1,080 plants)
Updated universe of 951 plants reflects
information on actual, planned, and
announced unit retirements through the
end of 2028.
Industry data (i.e., capacity, generation,
number of plants, etc.) from 2012 EIA
databases
Updated using 2016 EIA databases
Screening-level plant
impacts
Cost-to-revenue impact indicators (1% and
3%) based on 6-year (2007-2012) average
values of electricity generation and
electricity prices (to estimate plant-level
revenue)
Updated to use average electricity
generation and electricity prices for [2011-
2016]
Market-level impacts
(IPM)
IPM platform [v 5.13] which reflects
demand projections and other model
assumptions based on 2013 Annual Energy
Outlook.
IPM v.6 based on AEO 2018
EPA-821-R-19-012
A-1

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
Appendix A: Summary of Changes
Table A-1: Changes to Costs and Economic Impacts Analysis Since Proposal
Cost or Impact Category
Analysis Component
Cost or Impact Category

Existing regulations include proposed CPP
rule.
Existing regulations exclude CPP rule.
NEEDS V5.13 database
NEEDS v6 database
Impacts on employment
Estimate of total labor hours needed to
install the compliance technology or for
O&M
Discuss qualitatively (direction and relative
magnitude of potential changes), following
the general approach used in the CPP
repeal RIA
Impacts to wastewater treatment system
suppliers discussed qualitatively
Impacts to virgin material based on labor
intensity
Impacts to coal mining and natural gas
extraction sectors (as FTE) based on labor
productivity
Potential electricity
price effects
Simple assumption of 100 percent
compliance cost passthrough
No change
Projected total electricity sales in [2015]
from [AEO 2013]
Projected total electricity sales in [2020]
from [AEO 2018]
Electricity sales data by consumer group
from [2012] EIA-860 database
Electricity sales data by consumer group
from [2016] EIA-860 database
Evaluated differential impacts on
households by income level {i.e.,
distributional analysis)
Did not update this analysis: Cost savings
make differential burden on households
with different income levels less relevant
Owner-level impacts
and RFA/SBREFA
Owners identified in Steam Electric Survey
Owners identified in EIA-860 [2016]
Revenue from Steam Electric Survey
Revenue from Annual Reports and other
publicly available sources {e.g., company
websites), or estimated based on EIA
electricity sales data if unavailable
Small business size determination metrics
[mostly industry survey for private
entities; Census 2013 for governments]
Small business size determination metrics
[mostly publicly available sources for
private entities; Census ACS 2016 for
governments]
UMRA Analysis
Use the social cost framework to get
expenditures on a year-explicit basis for
each plant, by owner type
No change
EO 12866: Cost-benefits
Refer to BCA Chapter 12
No change
EO 12898: EJ
Refers to BCA Chapter 14. Qualitative
discussion draws on benefits analyses. See
Table 2 for details.
Presents profile of population in the
vicinity of steam electric power plants and
selected results of the benefits analyses by
income and minority status
Update profile and discussion of
distributional effects to reflect exposure
via drinking water
EO 13045: Children's
health
Qualitative discussion draws on benefits
analysis. See Table 2 for details.
No change
EO 13132: Federalism
Qualitative discussion draws on
compliance cost results
No change
EPA-821-R-19-012
A-2

-------
RIA for Proposed Revisions to Steam Electric Power Generating ELGs
Appendix B: Costs and Pollutant Removals
riparison of Incremental Costs and Pollutant Removals
This appendix describes the EPA's analysis of the incremental costs and pollutant removals of the
regulatory options. The information provides insight into how regulatory options compare to each other in
terms of reducing toxic pollutant discharges to surface waters.
B.1 Methodology
Cost-effectiveness is defined as the incremental annualized cost of a pollution control option in an
industry or industry subcategory per incremental pound equivalent of pollutant (i.e.. pound of pollutant
adjusted for toxicity) removed by that control option. The analysis compares removals for pollutants
directly regulated by the ELGs and incidentally removed along with regulated pollutants.
As described for the 2015 rule, the EPA's cost-effectiveness analysis involves the following steps to
generate input data and calculate the desired values (see Appendix F in U.S. EPA, 2015b):
1.	Determine the pollutants considered for regulation.
2.	For each pollutant, obtain relative toxic weights and POTW removal factors.
3.	Define the regulatory pollution control options.
4.	Calculate pollutant removals and toxic-weighted pollutant removals for each control option and
for each of direct and indirect discharges. For indirect dischargers, the calculations include
applying a factor that reflects the ability of a POTW or sewage treatment plant to remove
pollutants prior to discharge to water. See Supplemental TDD (2019a) for details.
5.	Determine the total annualized compliance cost for each control option and for direct and indirect
dischargers.
6.	Adjust the cost obtained in step 5 to 1981 dollars.
7.	Calculate the cost-effectiveness ratios for each control option and for direct and indirect
dischargers.
The four regulatory options represent only a subset of the requirements contained in the ELG for the
steam electric industry since they address only two of the relevant wastestreams. Accordingly, the EPA
did not calculate the cost-effectiveness ratios for the four regulatory options since these ratios would not
be comparable to cost-effectiveness values the EPA estimated for the 2015 rule (see Appendix F in U.S.
EPA, 2015b) or for ELGs for other point source categories. The next section provides results for steps 1
through 5, where the total annualized compliance costs calculated in step 5 are relative to the 2015 rule
baseline.60
Adjustment of costs to 1981 dollars is a convention to facilitate comparison of cost-effectiveness values across rules.
Since the EPA is not estimating cost-effectiveness ratios in this analysis, this adjustment was not needed.
EPA-821-R-19-012	B-1

-------
RIA for Proposed Revisions to Steam Electric Power Generating ELGs
Appendix B: Costs and Pollutant Removals
B.2 Results
Toxic Weights of Pollutants and POTW Removal
The Supplemental TDD provides information on the pollutants addressed by the regulatory options (U.S.
EPA, 2019a). The pollutants include several metals (e.g., arsenic, mercury, selenium), various non-metal
compounds (e.g., chloride, fluoride, sulfate), nutrients, and conventional pollutants (e.g., oil and grease,
biochemical oxygen demand.)
The toxic weighted pound equivalent (TWPE) analysis involves multiplying the changes in loadings of
each pollutant by a pollutant-specific toxic weighting factor (TWF) that represents the toxic effect level
relative to the toxicity of copper. For indirect dischargers, the changes are multiplied by a second factor
that reflects the ability of a POTW or sewage treatment plant to remove pollutants prior to discharge to
waters. For TWF and POTW removal factors, see Appendix F in U.S. EPA (2015b).
Evaluated Options
The EPA analyzed four options summarized in Table 1-1.
Pollutant Removals and Pound Equivalent Calculations
Table B-l, below, presents estimated annual reduction in the mass loading of pollutant anticipated from
direct and indirect dischargers for each regulatory option, relative to the baseline. The toxic weighted
removals account for pollutant toxicity and, for indirect dischargers, for POTW removals. The
calculations do not account for the removal of pollutants that do not have TWFs, either because data are
not available to set a TWF or toxicity is not the pollutant's primary environmental impact (e.g., nutrients
contributing to eutrophication, high BOD resulting in anoxia). Furthermore, the pound equivalent
pollutant removal analysis does not address routes of potential environmental damage and human
exposure, and therefore potential benefits from reducing pollutant exposure.
Annualized Compliance Costs
The EPA developed costs for technology controls to address each of the wastestreams present at each
steam electric power plant. The Supplemental TDD provides additional details on the methods used to
estimate the costs of meeting the limitations and standards under the baseline and each of the regulatory
options (U.S. EPA, 2019a). The method used to calculate the incremental annualized compliance costs is
described in greater detail in Chapter 3: Compliance Costs. The EPA categorized these annualized
compliance costs as either direct or indirect based on the discharge associated with each wastestream at
each plant.61 Table B-l summarizes the annualized compliance costs of the four regulatory options
relative to the 2015 rule baseline, whereas Figure B-l compares the pollutant removals and costs of the
four regulatory options graphically.
One plant has one of its wastestreams identified as discharged both directly and indirectly. For this plant and
wastestream, the EPA allocated compliance costs equally to the direct and indirect categories.
EPA-821-R-19-012
B-2

-------
RIA for Proposed Revisions to Steam Electric Power Generating ELGs
Appendix B: Costs and Pollutant Removals
Table B-1: Estimated Pollutant Removal and Costs of Regulatory Options by Discharger Category
Discharger

Total Annual TWF-Weighted
Pollutant Removals (Ib-eq.)
Total Annual Pre-tax Compliance
Costs
(million, 2018$)
Category
Option3
Totalb
Incremental
Totalb
Incremental

1
-87,291
-87,291
-$163.1
-$163.1
Direct
2
13,719
101,010
-$170.2
-$7.1
3
69,550
55,831
-$125.0
$45.2

4
394,012
324,462
-$25.0
$100.0

1
-526
-526
-$2.5
-$2.5
Indirect
3
68
594
-$5.5
-$2.9
2
-646
-714
-$1.4
$4.1

4
4,574
5,220
1A
O
In
$0.9
a. Options are listed in increasing order of pollutant removals, relative to the baseline.
b.	Total removals and costs are compared to those for the baseline.
c.	Incremental removals and costs are compared to those for the next least stringent option in the order listed in the table. For
direct dischargers, the incremental removals and costs under Option 1 are calculated relative to the baseline, the incremental
removals and costs for Option 2 are calculated relative to those of Option 1, etc.
Source: U.S. EPA Analysis, 2019
Figure B-1: Estimated Removals and Costs of the Regulatory Options, Relative to Baseline.
$10
& -100,000 _$10 0	100,000	200,000	300,000	400,000	500,000
o
-O
O
-$30
-$50
-$70
-$90
-$110
Option 4
E	-$130
0	Option 3
-o

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
Appendix C: IPM Sensitivity Analysis
1 Sensitivity Analysis Including ACE Rule
EPA promulgated the Affordable Clean Energy (ACE) final rule on June 19, 2019 (84 FR 32520). The
rule provides emission guidelines for greenhouse gas (GHG) emissions from existing electric utility
generating units (EGUs) under section 111(d) of the Clean Air Act. The guidelines inform states in the
development, submittal, and implementation of state plans that establish standards of performance for
CO2 from certain existing coal-fired EGUs within their jurisdictions. To analyze the regulatory impacts of
the ACE final rule, the Agency developed an illustrative policy scenario that models adoption of heat rate
improvement (HRI) measures at coal-fired EGUs and used this scenario to assess the emissions,
compliance costs, and other energy-sector effects of the ACE final rule.
The analysis of the proposed ELG options discussed in Chapter 5 was completed before the Agency
finalized the ACE rule, and therefore does not include the projected effects of the ACE rule. This
appendix complements the analysis detailed in Chapter 5 by providing information about the projected
impacts of the proposed ELG in the context of an electricity market that includes the effects of the ACE
final rule. Specifically, the EPA conducted a sensitivity analysis that uses the ACE illustrative scenario as
the basis against which to evaluate the impacts of proposed Option 2. In this appendix, we refer to the
ACE illustrative scenario as the "alternative baseline." The EPA used existing IPM results, that include
the ACE final rule, for this alternative baseline and ran an additional scenario that adds proposed Option 2
to this baseline for the purpose of determining the effect of proposed Option 2.
In the following sections, we first summarize differences between the baseline used for analyses
presented in Chapter 5 and the alternative baseline that includes the ACE final rule (Section C.l). We
then summarize the market-level impacts of proposed Option 2 (Section C.2). The market-level impacts
are addressed in two sets of analyses that parallel the analyses described in Chapter 5:
•	Analysis of national-level impacts: The EPA analyzed IPM results reported for a series of run
years to provide insight on the direction and magnitude of market-level changes attributable to the
ELG option over time.
•	Analysis of long-term regulatory impacts: The EPA analyzed IPM results for run year 2030 to
provide insight on post-compliance conditions for the entire electricity market and for steam
electric power plants specifically.
Overall, the sensitivity analysis with the ACE final rule shows impacts that are very similar to those
presented in Chapter 5 for the scenarios without the ACE final rule. The sensitivity analysis shows a
slightly greater reduction in steam electric capacity retirement resulting from proposed Option 2 than the
primary analysis, even though it also shows one net full-plant retirement versus no net full-plant
retirement for the primary analysis (see details in
Impacts on Steam Electric Power Plants as a Group below).
C.1 Baseline Changes
Table C-l summarizes the baseline used for the proposed rule and the alternative baseline IPM
projections of total costs to electric power plants, wholesale electricity price, total existing capacity, new
capacity, plant retirements, and generation mix at the national level. These baseline projections show a
EPA-821-R-19-012
C-1

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
Appendix C: IPM Sensitivity Analysis
progressive decline in total coal and nuclear generation capacities, and increases in generation capacity
from renewables, natural gas, and other sources. Changes over time are smaller in the alternative baseline;
the coal generation capacity declines by 13.5 GW (8 percent) between 2021 and 2040, as compared to a
31.9 GW (18 percent) decline for the baseline without the ACE final rule. Neither baseline shows coal
capacity additions during the period.
Table C-1: Baseline Projections Without and With ACE Final Rule
Economic
Baseline (Without ACE)
Alternative Baseline (With ACE)
Measures
2021
2025
2030
2040
2050
2021
2025
2030
2040
2050
Total Costs
Total Costs
$135,820
$145,980
$156,921
$179,174
$188,890
$135,781
$146,263
$157,189
$164,725
$178,811
(million










2018$)










Prices
National
33.40
39.22
42.96
44.79
45.28
33.45
39.15
42.93
43.08
44.66
Wholesale










Electricity










Price










(mills/kWh)










Total Capacity (Cumulative GW)
Renewables3
290.3
321.1
376.8
383.3
435.2
290.3
322.3
377.1
382.0
383.4
Coal
176.4
171.8
169.9
161.5
144.5
174.3
169.7
167.9
163.4
160.9
Nuclear
88.4
81.3
76.6
75.4
73.3
88.4
81.3
76.7
75.5
75.5
Natural Gas
407.7
415.5
425.8
509.6
622.0
407.9
416.4
427.2
464.8
509.8
Oil/Gas
Steam
71.3
71.7
71.7
71.3
67.2
71.7
72.1
72.1
72.0
71.6
Other
9.6
11.1
12.5
12.5
12.8
6.4
6.4
6.4
6.4
6.4
Grand Total
1,043.7
1,072.6
1,133.3
1,213.7
1,355.1
1,042.2
1,072.9
1,133.4
1,170.2
1,213.7
New Capacity (Cumulative GW)
Renewables3
66.8
97.7
153.4
159.9
211.8
66.8
98.9
153.7
158.6
160.1
Coal
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
Nuclear
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
Natural Gas
2.2
10.1
20.7
104.5
217.0
2.4
10.9
22.1
59.7
104.7
Other
2.5
4.0
5.4
5.4
5.7
0.0
0.0
0.0
0.0
0.0
Grand Total
71.6
111.9
179.5
269.8
434.5
71.7
113.8
181.2
223.7
270.2
Retirements (GW)b
Combined
Cycle
2.9
2.9
2.9
2.9
2.9
2.9
2.9
2.9
2.9
2.9
Coal
48.3
49.3
51.0
59.4
75.8
50.4
51.4
53.0
57.5
60.1
Combustion
Turbine
1.6
1.6
1.9
1.9
1.9
1.6
1.6
1.9
1.9
1.9
Nuclear
3.9
12.2
17.0
18.1
20.2
3.9
12.2
16.9
18.0
18.0
Oil/Gas
6.0
5.9
6.0
6.3
10.5
5.6
5.6
5.6
5.6
6.1
Grand Total
67.0
76.4
83.2
93.1
116.3
68.6
78.1
84.7
90.4
93.4
EPA-821-R-19-012
C-2

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
Appendix C: IPM Sensitivity Analysis
Table C-1: Baseline Projections Without and With ACE Final Rule
Economic
Baseline (Without ACE)
Alternative Baseline (With ACE)
Measures
2021
2025
2030
2040
2050
2021
2025
2030
2040
2050
Generation Mix (thousand GWh)
Renewables3
842.6
906.6
1,056.3
1,076.2
1,252.8
842.5
908.0
1,056.0
1,069.3
1,075.3
Coal
867.1
919.1
882.2
790.4
716.5
867.2
921.5
884.2
784.9
796.6
Nuclear
694.3
642.7
604.0
596.6
579.4
694.3
642.7
604.8
597.3
597.3
Natural Gas
1,576.1
1,613.8
1,656.4
2,026.8
2,303.3
1,576.1
1,610.7
1,655.0
1,865.1
2,020.6
Oil/Gas
62.9
60.8
56.9
43.9
15.7
62.8
59.9
56.1
61.0
44.3
Steam










Other
35.3
36.3
37.0
37.5
37.6
32.0
32.0
31.4
31.4
31.4
Grand Total
4,078.4
4,179.2
4,292.8
4,571.3
4,905.2
4,078.3
4,179.0
4,293.2
4,414.8
4,571.6
a. Renewables include hydropower and non-hydropower renewables.
b. There were no changes in projected retirements for IGCC, biomass, fuel cell, other fossil fuel, geothermal, hydropower,
landfill gas, other non-fossil fuel, and energy storage plants.
Source: U.S. EPA Analysis, 2019
C.2 Market Level Impacts
Summary of Impacts Over Analysis Period
The EPA compared the baseline and policy case (with proposed Option 2) IPM results reported for a
series of run years62 to provide insight on the direction and magnitude of market-level changes
attributable to the proposed ELG option overtime. Table C-2 provides incremental changes in these
measures for Option 2, relative to the baseline presented in Chapter 5 and relative to the alternative
baseline (negative values represent decreases relative to the baseline). The changes attributable to Option
2 are generally small under both baseline scenarios. For most economic measures and years analyzed, the
incremental impacts of Option 2 are larger when evaluated against the alternative baseline, but they
remain small relative to values summarized in Table C-1.
Table C-2: National Impact of Proposed Regulatory Option (Option 2) Relative to Baseline and
Alternative Baseline
Economic
Measures
Option 2 Changes Relative to Baseline
Option 2 Changes Relative to Alternative
Baseline
2021
2025
2030
2040
2050
2021
2025
2030
2040
2050
Total Costs
Total Costs
(million
2018$)
-$193.5
-$186.7
-$140.1
-$53.3
$13.6
-$219.9
-$182.4
-$125.7
-$93.1
-$17.5
For conciseness, the tables show results for the years 2021, 2025,2030, 2040, and 2050, but IPM V6 also provides
projections for model years 2023, 2035, and 2045.
EPA-821-R-19-012
C-3

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
Appendix C: IPM Sensitivity Analysis
Table C-2: National Impact of Proposed Regulatory Option (Option 2) Relative to Baseline and
Alternative Baseline
Economic
Measures
Option 2 Changes Relative to Baseline
Option 2 Changes Relative to Alternative
Baseline
2021
2025
2030
2040
2050
2021
2025
2030
2040
2050
Prices
National
Wholesale
Electricity
Price
(mills/kWh)
-0.08
-0.02
-0.05
-0.01
0.01
-0.09
-0.01
-0.02
0.01
0.01
Total Capacity (Cumulative GW)
Renewables3
0.0
-1.1
-0.4
-0.3
-0.4
0.0
-1.3
-0.1
0.0
-0.1
Coal
1.2
1.2
1.1
0.7
0.8
1.3
1.3
1.2
1.1
0.9
Nuclear
0.0
0.0
-0.1
-0.1
-0.1
0.0
0.0
-0.3
-0.3
-0.3
Natural Gas
0.0
0.1
-0.5
-0.3
-0.5
0.0
0.0
-0.7
-0.7
-0.4
Oil/Gas
Steam
-0.2
-0.2
-0.2
0.0
0.0
0.0
0.0
0.0
0.0
0.0
Other
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
Grand Total
1.1
0.0
0.0
-0.1
-0.2
1.3
0.0
0.0
0.0
-0.1
New Capacity (Cumulative GW)
Renewables3
0.0
-1.1
-0.4
-0.3
-0.4
0.0
-1.3
-0.1
0.0
-0.1
Coal
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
Nuclear
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
Natural Gas
0.0
0.1
-0.6
-0.3
-0.5
0.0
0.0
-0.8
-0.7
-0.5
Other
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
Grand Total
0.0
-1.1
-0.9
-0.7
-0.9
0.0
-1.3
-0.9
-0.8
-0.6
Retirements (GW)b
Combined
Cycle
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
Coal
-1.2
-1.2
-1.1
-0.7
-0.8
-1.3
-1.3
-1.2
-1.1
-0.9
Combustion
Turbine
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
Nuclear
0.0
0.0
0.1
0.1
0.1
0.0
0.0
0.3
0.3
0.3
Oil/Gas
0.2
0.2
0.2
0.0
0.0
0.0
0.0
0.0
0.0
0.0
Grand Total
-1.1
-1.1
-0.9
-0.6
-0.7
-1.3
-1.3
-0.9
-0.8
-0.5
Generation Mix (thousand GWh)
Renewables3
-0.1
-1.8
-0.9
-0.8
-0.5
0.0
-1.9
-0.5
-0.6
-0.6
Coal
1.6
2.2
4.9
1.8
0.9
0.2
4.2
6.3
5.2
3.5
Nuclear
0.0
0.0
-0.7
-0.7
-0.7
0.0
0.0
-2.8
-2.8
-2.8
Natural Gas
-1.1
-0.1
-3.3
0.0
0.4
0.0
-2.2
-3.2
-1.8
-0.5
Oil/Gas
Steam
-0.2
-0.3
0.1
0.0
0.1
0.0
0.1
0.4
-0.2
0.4
Other
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
Grand Total
0.2
0.1
0.1
0.3
0.1
0.3
0.2
0.1
-0.1
0.1
a.	Renewables include hydropower and non-hydropower renewables.
b.	There were no changes in projected retirements for IGCC, biomass, fuel cell, other fossil fuel, geothermal, hydropower,
landfill gas, other non-fossil fuel, and energy storage plants.
Source: U.S. EPA Analysis, 2019
EPA-821-R-19-012
C-4

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
Appendix C: IPM Sensitivity Analysis
Detailed Market-level Impacts for Year 2030
This analysis looks at conditions in the period of 2028 through 2033, when plants are estimated to meet
the revised BAT limits and pretreatment standards associated with each analyzed regulatory option.
Following the approach described in Section 5.2.2, the EPA used parsed IPM outputs and considered
impact metrics of interest at three levels of aggregation discussed below: (1) national and regional
electricity markets; (2) steam electric power plants as a group; and (3) individual steam electric power
plants.
Impacts on National and Regional Electricity Markets in 2030
Following the approach described in Chapter 5, EPA compared market-level outputs for the year 2030
relative to the alternative baseline. Table C-3 presents results at the level of the national market and for
regional electricity markets defined on the basis of NERC regions. For comparison purposes, the table
includes the results previously obtained for Option 2 relative to the baseline without ACE (as presented in
Table 5-4).
The impacts of the proposed Option 2 relative to the alternative baseline are very similar to those
discussed in Chapter 5 for the baseline that does not include ACE: Option 2 has small effects on the
electricity market relative to the baseline, on both a national and regional sub-market basis, in the year
2030.
At the national level, total annual costs decrease by an estimated $126 million (approximately
0.1 percent) relative to the alternative baseline. The results show a similar distribution of impacts across
regions with the RFC region having the largest decline in total costs, $155 million (0.4 percent), followed
by the SPP region with decreases of $16 million (0.2 percent). Whereas Option 2 resulted in cost savings
for the SERC region when compared to the baseline without ACE, the sensitivity analysis shows a small
increase in total costs for this region of $47 million (0.1 percent) relative to the alternative baseline.
Overall at the national level, the net change in total capacity, including increases in existing capacity
(which includes avoided early retirements) and reductions in new plants/units, is an increase of
approximately 2.4 GW in capacity, which is about 0.2 percent of total market capacity. Although effects
differ across the regions, Option 2 is estimated to have minimal effect on capacity availability and supply
reliability at the national level. The net capacity increase is primarily a result of a gain in capacity in the
SERC region of about 2.5 GW (0.9 percent of SERC region capacity) due to a combination of avoided
early retirements and reduced new capacity additions. Other regions projected to experience gains in
capacity are NPCC and SPP. IPM projects net losses in capacity in the RFC region of 0.4 GW (0.2
percent), as well as smaller losses in FRCC.
Similar to results presented in Chapter 5, overall impacts on wholesale electricity prices are small.
Wholesale electricity prices are estimated to increase in some NERC regions and fall in others. Price
changes in individual regions range from -$0.11 per MWh (-0.3 percent) in SERC to $0.12 per MWh
(0.3 percent) in NPCC.
At the national level, the sensitivity analysis shows increases in emissions for all air pollutants modeled,
as was the case for the baseline without ACE. These increases are greater than those predicted relative to
the baseline without ACE. NOx emissions increase by 0.6 percent; SO2 emissions increase by 0.6 percent;
EPA-821-R-19-012
C-5

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
Appendix C: IPM Sensitivity Analysis
CO2 emissions increase by 0.4 percent, mercury emissions increase by 0.5 percent; and HCL emissions
increase by 0.7 percent. The impact on emissions varies across regions and by pollutant.
Table C-3: Impact of Proposed ELG Option 2 on National and Regional Markets at the Year 2030,
Relative to Baseline and Alternative Baseline


Option 2 without ACE
Alternative
Option 2 with ACE
Economic Measures
(all dollar values in 2018$)







Baseline
Value
Diff.
Change
Baseline
Value
Diff.
% Change
National Totals
Total Domestic Capacity
1,142.5
1,143.1
0.6
0.1%
1,143.0
1,145.4
2.4
0.2%
(GW)








Existing
1 1 15
0.1%


3.2
0.3%
New Additions
1 1 -0.9
-0.1%


-0.9
-0.1%
Early Retirements

1 -1-5
-0.1% |
| -3.2
-0.3%
Wholesale Price ($/MWh)
$42.96
$42.90
-$0.05
-0.1%
$42.93
$42.91
-$0.02
0.0%
Generation (TWh)
4,286
4,287
0.1
0.0%
4,287
4,287
0.1
0.0%

$156,921
$156,78
-$140
-0.1%
$157,189
$157,06
-$126
-0.1%
Costs ($Millions)

1



4


Fuel Cost
$69,971
$70,028
$57
0.1%
$69,634
$69,763
$129
0.2%
Variable O&M
$10,261
$10,263
$2
0.0%
$10,276
$10,289
$13
0.1%
Fixed O&M
$52,916
$52,834
-$82
-0.2%
$53,334
$53,200
-$134
-0.3%
Capital Cost
$23,774
$23,657
-$117
-0.5%
$23,945
$23,812
-$134
-0.6%
Variable Production Cost
$18.72
$18.73
$0.01
0.1%
$18.64
$18.67
$0.03
0.2%
($/MWh)








C02 Emissions (Million
1,581.1
1,585.1
3.9
0.2%
1,570.9
1,576.5
5.7
0.4%
Metric Tons)








Mercury Emissions (Tons)
4.45
4.47
0.02
0.4%
4.43
4.45
0.02
0.5%
NOx Emissions (Million Tons)
0.810
0.814
0.004
0.5%
0.80
0.81
0.005
0.6%
S02 Emissions (Million Tons)
0.886
0.891
0.006
0.6%
0.88
0.88
0.005
0.6%
HCL Emissions (Million Tons)
0.004
0.005
0.000
0.5%
0.00
0.00
0.000
0.7%
Florida Reliability Coordinating Council (FRCC)
Total Domestic Capacity
59.5
59.5
0.0
0.0%
59.4
59.4
0.0
-0.1%
(GW)








Existing
1 1 °'°
0.0%


0.0
0.0%
New Additions
1 1 0.0
0.0%


0.0
-0.1%
Early Retirements




0.0%
Wholesale Price ($/MWh)
$46.41
$46.41
$0.00
0.0%
$46.31
$46.31
$0.00
0.0%
Generation (TWh)
256
256
-0.1
0.0%
256
256
0
0.0%
Costs ($Millions)
$10,411
$10,404
-$7
-0.1%
$10,414
$10,409
-$5
0.0%
Fuel Cost
$6,662
$6,661
-$1
0.0%
$6,647
$6,650
$3
0.0%
Variable O&M
$605
$605
$0
0.1%
$608
$610
$1
0.2%
Fixed O&M
$2,643
$2,638
-$4
-0.2%
$2,661
$2,656
-$5
-0.2%
Capital Cost
$502
$499
-$3
-0.6%
$498
$493
-$4
-0.9%
Variable Production Cost
$28.39
$28.40
$0.01
0.0%
$28.37
$28.39
$0.02
0.1%
($/MWh)








C02 Emissions (Million
97.0
96.9
-0.1
-0.1%
97.2
97.3
0.0
0.0%
Metric Tons)








Mercury Emissions (Tons)
0.22
0.22
0.00
-0.1%
0.22
0.22
0.00
0.0%
EPA-821-R-19-012
C-6

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
Appendix C: IPM Sensitivity Analysis
Table C-3: Impact of Proposed ELG Option 2 on National and Regional Markets at the Year 2030,
Relative to Baseline and Alternative Baseline


Option 2 without ACE
Alternative
Baseline
Option 2 with ACE
Economic Measures
(all dollar values in 2018$)
Baseline
Value
Diff.
%
Change
Value
Diff.
% Change
NOx Emissions (Million Tons)
0.036
0.036
0.000
0.0%
0.037
0.037
0.000
0.1%
S02 Emissions (Million Tons)
0.021
0.020
0.000
-0.7%
0.021
0.021
0.000
0.0%
HCL Emissions (Million Tons)
0.000
0.000
0.000
-0.4%
0.000
0.000
0.000
0.0%
Midwest Reliability Organization (MRO)
Total Domestic Capacity
67.7
67.6
-0.1
-0.1%
67.7
67.6
0.0
0.0%
(GW)








Existing


0.0
0.0%


0.0
0.0%
New Additions


-0.1
-0.1%


0.0
0.0%
Early Retirements


0.0
0.0%


0.0
0.0%
Wholesale Price ($/MWh)
$40.03
$39.88
-$0.15
-0.4%
$39.87
$39.84
-$0.03
-0.1%
Generation (TWh)
272
272
0.2
0.1%
272
273
0
0.1%
Costs ($Millions)
$8,822
$8,821
-$2
0.0%
$8,856
$8,857
$0
0.0%
Fuel Cost
$3,651
$3,659
$8
0.2%
$3,627
$3,637
$11
0.3%
Variable O&M
$763
$761
-$2
-0.2%
$770
$768
-$2
-0.2%
Fixed O&M
$2,890
$2,887
-$3
-0.1%
$2,943
$2,936
-$7
-0.2%
Capital Cost
$1,518
$1,513
-$5
-0.3%
$1,517
$1,515
-$2
-0.1%
Variable Production Cost
$16.23
$16.24
$0.01
0.1%
$16.14
$16.15
$0.01
0.1%
($/MWh)








C02 Emissions (Million
134.1
134.5
0.4
0.3%
133.4
133.8
0.4
0.3%
Metric Tons)








Mercury Emissions (Tons)
0.39
0.39
0.00
0.3%
0.39
0.39
0.00
0.3%
NOx Emissions (Million Tons)
0.090
0.091
0.001
1.1%
0.090
0.091
0.001
0.9%
S02 Emissions (Million Tons)
0.089
0.090
0.001
0.7%
0.089
0.090
0.001
0.6%
HCL Emissions (Million Tons)
0.001
0.001
0.000
0.3%
0.001
0.001
0.000
0.3%
Northeast Power Coordinating Council (NPCC)
Total Domestic Capacity
79.7
79.5
-0.1
-0.2%
79.6
79.9
0.3
0.3%
(GW)








Existing
1 1 "01
-0.2%


0.1
0.2%
New Additions
0.0
0.0%


0.1
0.1%
Early Retirements
1 1 0.1
0.2%


-0.1
-0.2%
Wholesale Price ($/MWh)
$42.62
$42.62
$0.00
0.0%
$42.47
$42.59
$0.12
0.3%
Generation (TWh)
238
238
0.0
0.0%
238
238
0
0.1%
Costs ($Millions)
$9,840
$9,841
$1
0.0%
$9,830
$9,842
$12
0.1%
Fuel Cost
$3,343
$3,345
$2
0.1%
$3,343
$3,346
$3
0.1%
Variable O&M
$390
$391
$0
0.1%
$391
$391
$0
-0.1%
Fixed O&M
$3,748
$3,747
-$1
0.0%
$3,749
$3,748
-$1
0.0%
Capital Cost
$2,359
$2,358
-$1
0.0%
$2,347
$2,357
$10
0.4%
Variable Production Cost
$15.67
$15.68
$0.01
0.0%
$15.68
$15.68
$0.00
0.0%
($/MWh)








C02 Emissions (Million
47.3
47.3
0.0
0.1%
47.3
47.3
0.0
0.1%
Metric Tons)








Mercury Emissions (Tons)
0.31
0.31
0.00
0.0%
0.31
0.31
0.00
0.0%
NOx Emissions (Million Tons)
0.029
0.029
0.000
0.0%
0.029
0.029
0.000
0.0%
S02 Emissions (Million Tons)
0.004
0.004
0.000
0.0%
0.004
0.004
0.000
0.0%
HCL Emissions (Million Tons)
0.000
0.000
0.000
0.0%
0.000
0.000
0.000
0.0%
EPA-821-R-19-012
C-7

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
Appendix C: IPM Sensitivity Analysis
Table C-3: Impact of Proposed ELG Option 2 on National and Regional Markets at the Year 2030,
Relative to Baseline and Alternative Baseline


Option 2 without ACE
Alternative
Option 2 with ACE
Economic Measures
(all dollar values in 2018$)







Baseline
Value
Diff.
Change
Baseline
Value
Diff.
% Change
ReliabilityFirst Corporation (RFC)
Total Domestic Capacity
223.4
222.9
-0.4
-0.2%
223.8
223.4
-0.4
-0.2%
(GW)








Existing


0.0
0.0%


0.0
0.0%
New Additions


-0.5
-0.2%


-0.5
-0.2%
Early Retirements


0.0
0.0%


0.0
0.0%
Wholesale Price ($/MWh)
$40.66
$40.62
-$0.04
-0.1%
$40.59
$40.61
$0.02
0.0%
Generation (TWh)
928
927
-0.9
-0.1%
929
927
-2
-0.2%
Costs ($Millions)
$35,545
$35,434
-$111
-0.3%
$35,679
$35,524
-$155
-0.4%
Fuel Cost
$15,878
$15,882
$3
0.0%
$15,796
$15,830
$34
0.2%
Variable O&M
$2,470
$2,469
-$1
0.0%
$2,459
$2,467
$8
0.3%
Fixed O&M
$12,112
$12,047
-$65
-0.5%
$12,233
$12,105
-$128
-1.1%
Capital Cost
$5,085
$5,036
-$49
-1.0%
$5,190
$5,122
-$68
-1.3%
Variable Production Cost
$19.78
$19.80
$0.02
0.1%
$19.64
$19.73
$0.09
0.4%
($/MWh)








C02 Emissions (Million
404.0
404.9
0.9
0.2%
399.9
402.1
2.2
0.6%
Metric Tons)








Mercury Emissions (Tons)
1.13
1.13
0.01
0.5%
1.11
1.12
0.01
1.1%
NOx Emissions (Million Tons)
0.219
0.219
0.000
0.1%
0.215
0.216
0.002
0.7%
S02 Emissions (Million Tons)
0.227
0.227
0.000
0.1%
0.224
0.226
0.001
0.5%
HCL Emissions (Million Tons)
0.001
0.001
0.000
0.3%
0.001
0.001
0.000
0.9%
Southeast Electric Reliability Council (SERC)
Total Domestic Capacity
272.9
274.3
1.4
0.5%
272.9
275.4
2.5
0.9%
(GW)








Existing
1 1 17
0.6%


2.8
1.0%
New Additions
1 1 "0.3
-0.1%


-0.3
-0.1%
Early Retirements
-1.7
-0.6%


-2.8
-1.0%
Wholesale Price ($/MWh)
$43.65
$43.52
-$0.14
-0.3%
$43.66
$43.54
-$0.11
-0.3%
Generation (TWh)
1,132
1,133
0.9
0.1%
1,131
1,133
2
0.2%
Costs ($Millions)
$43,758
$43,756
-$3
0.0%
$43,814
$43,861
$47
0.1%
Fuel Cost
$21,512
$21,537
$25
0.1%
$21,374
$21,436
$62
0.3%
Variable O&M
$2,684
$2,688
$4
0.2%
$2,682
$2,688
$7
0.2%
Fixed O&M
$15,895
$15,901
$5
0.0%
$15,990
$16,013
$23
0.1%
Capital Cost
$3,667
$3,630
-$37
-1.0%
$3,769
$3,724
-$45
-1.2%
Variable Production Cost
$21.37
$21.38
$0.01
0.0%
$21.27
$21.30
$0.03
0.1%
($/MWh)








C02 Emissions (Million
418.7
420.9
2.2
0.5%
415.4
418.2
2.8
0.7%
Metric Tons)








Mercury Emissions (Tons)
0.77
0.78
0.01
1.3%
0.76
0.77
0.01
1.2%
NOx Emissions (Million Tons)
0.197
0.199
0.002
1.1%
0.195
0.197
0.002
1.1%
S02 Emissions (Million Tons)
0.297
0.300
0.003
0.9%
0.294
0.298
0.004
1.4%
HCL Emissions (Million Tons)
0.001
0.001
0.000
1.8%
0.001
0.001
0.000
1.7%
EPA-821-R-19-012
C-8

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
Appendix C: IPM Sensitivity Analysis
Table C-3: Impact of Proposed ELG Option 2 on National and Regional Markets at the Year 2030,
Relative to Baseline and Alternative Baseline







Option 2 without ACE
Alternative
Option 2 with ACE
Economic Measures
(all dollar values in 2018$)







Baseline
Value
Diff.
/o
Change
Baseline
Value
Diff.
% Change
Southwest Power Pool (SPP

Total Domestic Capacity
79.2
79.1
-0.1
-0.1%
78.9
79.1
0.2
0.2%
(GW)








Existing


0.0
0.0%


0.2
0.3%
New Additions


-0.1
-0.1%


-0.1
-0.1%
Early Retirements


0.0
0.0%


-0.2
-0.3%
Wholesale Price ($/MWh)
$40.97
$40.96
-$0.01
0.0%
$41.05
$41.03
-$0.01
0.0%
Generation (TWh)
269
269
-0.1
0.0%
269
269
0
-0.1%
Costs ($Millions)
$8,476
$8,460
-$16
-0.2%
$8,469
$8,453
-$16
-0.2%
Fuel Cost
$4,135
$4,144
$9
0.2%
$4,124
$4,130
$6
0.2%
Variable O&M
$765
$765
$1
0.1%
$776
$776
$0
0.0%
Fixed O&M
$2,658
$2,647
-$10
-0.4%
$2,694
$2,684
-$10
-0.4%
Capital Cost
$918
$903
-$15
-1.7%
$875
$862
-$13
-1.5%
Variable Production Cost
$18.22
$18.26
$0.04
0.2%
$18.23
$18.26
$0.03
0.2%
($/MWh)








C02 Emissions (Million
132.1
132.3
0.3
0.2%
131.8
132.0
0.1
0.1%
Metric Tons)








Mercury Emissions (Tons)
0.32
0.32
0.00
0.2%
0.32
0.32
0.00
0.0%
NOx Emissions (Million Tons)
0.080
0.081
0.000
0.3%
0.080
0.080
0.000
0.1%
S02 Emissions (Million Tons)
0.112
0.112
0.000
0.1%
0.111
0.111
0.000
-0.1%
HCL Emissions (Million Tons)
0.000
0.000
0.000
0.2%
0.000
0.000
0.000
0.1%
Electric Reliability Organization of Texas (TRE)
Total Domestic Capacity
118.9
118.9
0.0
0.0%
119.1
119.0
0.0
0.0%
(GW)








Existing
1 1 00
0.0%


0.0
0.0%
New Additions
0.0
0.0%


0.0
0.0%
Early Retirements
1 1 0.0
0.0%


0.0
0.0%
Wholesale Price ($/MWh)
$40.69
$40.69
$0.00
0.0%
$40.72
$40.71
-$0.01
0.0%
Generation (TWh)
416
416
0.0
0.0%
416
416
0
0.0%
Costs ($Millions)
$14,535
$14,531
-$4
0.0%
$14,560
$14,552
-$7
-0.1%
Fuel Cost
$7,121
$7,127
$6
0.1%
$7,068
$7,075
$7
0.1%
Variable O&M
$855
$856
$1
0.1%
$860
$861
$1
0.1%
Fixed O&M
$4,690
$4,686
-$4
-0.1%
$4,734
$4,729
-$4
-0.1%
Capital Cost
$1,869
$1,862
-$7
-0.4%
$1,898
$1,887
-$11
-0.6%
Variable Production Cost
$19.16
$19.17
$0.01
0.1%
$19.04
$19.06
$0.02
0.1%
($/MWh)








C02 Emissions (Million
149.2
149.4
0.1
0.1%
148.3
148.4
0.2
0.1%
Metric Tons)








Mercury Emissions (Tons)
0.43
0.43
0.00
0.1%
0.43
0.43
0.00
0.1%
NOx Emissions (Million Tons)
0.064
0.065
0.000
0.1%
0.064
0.064
0.000
0.2%
S02 Emissions (Million Tons)
0.073
0.075
0.002
2.8%
0.073
0.073
-0.001
-0.8%
HCL Emissions (Million Tons)
0.000
0.000
0.000
0.2%
0.000
0.000
0.000
0.2%
EPA-821-R-19-012
C-9

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
Appendix C: IPM Sensitivity Analysis
Table C-3: Impact of Proposed ELG Option 2 on National and Regional Markets at the Year 2030,
Relative to Baseline and Alternative Baseline


Option 2 without ACE
Alternative
Option 2 with ACE
Economic Measures
(all dollar values in 2018$)







Baseline
Value
Diff.
Change
Baseline
Value
Diff.
% Change
Western Electricity Coordinating Council (WECC)
Total Domestic Capacity
241.2
241.2
0.0
0.0%
241.6
241.6
0.0
0.0%
(GW)








Existing


0.0
0.0% I
1 0.0
0.0%
New Additions


0.0
0.0% 1
| 0.0
0.0%
Early Retirements


0.0
0.0%


0.0
0.0%
Wholesale Price ($/MWh)
$46.53
$46.55
$0.02
0.0%
$46.53
$46.56
$0.04
0.1%
Generation (TWh)
775
775
0
0.0%
775
775
0
0.0%
Costs ($Millions)
$25,533
$25,536
$3
0.0%
$25,567
$25,565
-$2
0.0%
Fuel Cost
$7,668
$7,673
$4
0.1%
$7,654
$7,658
$4
0.1%
Variable O&M
$1,729
$1,728
-$1
-0.1%
$1,730
$1,728
-$2
-0.1%
Fixed O&M
$8,279
$8,279
$0
0.0%
$8,331
$8,328
-$3
0.0%
Capital Cost
$7,857
$7,856
$0
0.0%
$7,852
$7,851
-$1
0.0%
Variable Production Cost
$12.12
$12.13
$0.00
0.0%
$12.11
$12.11
$0.00
0.0%
($/MWh)








C02 Emissions (Million
198.8
198.8
0.0
0.0%
197.6
197.5
-0.1
-0.1%
Metric Tons)








Mercury Emissions (Tons)
0.89
0.89
0.00
0.0%
0.88
0.88
0.00
0.0%
NOx Emissions (Million Tons)
0.094
0.094
0.000
0.1%
0.093
0.093
0.000
-0.2%
S02 Emissions (Million Tons)
0.063
0.063
0.000
-0.1%
0.063
0.063
0.000
-0.1%
HCL Emissions (Million Tons)
0.001
0.001
0.000
0.0%
0.001
0.001
0.000
-0.2%
a. Numbers may not add up due to rounding.
Source: U.S. EPA Analysis, 2019
Impacts on Steam Electric Power Plants as a Group
Table C-4 summarizes the impact on the subset of plants to which the ELGs apply, i.e., steam electric
power plants. For the group of steam electric power plants, total capacity increases by 3,107 MW or
approximately 0.9 percent of the 336,547 MW in alternative baseline capacity. This increase is almost
entirely attributable to avoided retirements in the SERC region (2,815 MW, 13.5 percent), with additional
avoided retirements in the SPP and RFC regions. There is one net closure in the RFC region, which is no
longer offset by an avoided closure in the SERC region, yielding one net closure at the national level for
this sensitivity analysis.
Total generation by steam electric plants is estimated to increase by 7,345 GWh (0.5 percent), which is
slightly more than was predicted for the scenario detailed in Chapter 5. As was the case for the scenario
without ACE, steam electric plants in the SERC and RFC regions are projected to experience the largest
increases in generation under Option 2, while plants in other regions see smaller increases and those in
WECC experience negligible decreases in generation.
The increase in generation is accompanied by a net increase in total costs for steam electric plants of
$191 million at the national level (0.3 percent). The distribution of these cost increases is generally
consistent with results from the scenario detailed in Chapter 5. However, in the RFC region there is an
EPA-821-R-19-012
C-10

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
Appendix C: IPM Sensitivity Analysis
increase in costs of $51 million (0.4 percent) in the scenario with ACE compared to a decrease in costs of
$30 million (0.2 percent) relative to the baseline. At the national level, variable production costs for steam
electric power plants increase by $0.02 per MWh (0.1 percent), which is the same increase predicted for
the scenario without ACE. Effects vary by region, with changes ranging from -$0.01 per MWh in MRO
to $0.06 per MWh in SERC.
Table C-4: Impact of Proposed ELG Option 2 on In-Scope Plants, as a Group, at the Year 2030,
Relative to Baseline and Alternative Baseline
Economic Measures

Option 2 without ACE

Option 2 with ACE
(all dollar values in




Alternative



2018$)
Baseline
Value
Difference
% Change
Baseline
Value
Difference
% Change
National Totals
Total Domestic
336,872
339,752
2,880
0.9%
336,547
339,654
3,107
0.9%
Capacity (MW)








Early Retirements
79
79
0
0.0%
78
79
1
1.3%
- Number of Plants








Full & Partial
58,192
55,312
-2,880
-4.9%
58,518
55,411
-3,107
-5.3%
Retirements -








Capacity (MW)








Generation (GWh)
1,570,513
1,575,189
4,676
0.3%
1,569,109
1,576,455
7,345
0.5%
Costs ($Millions)
$60,298
$60,397
$98
0.2%
$60,387
$60,578
$191
0.3%
Fuel Cost
$34,842
$34,976
$134
0.4%
$34,557
$34,765
$208
0.6%
Variable O&M
$5,987
$5,999
$12
0.2%
$6,000
$6,020
$20
0.3%
Fixed O&M
$19,165
$19,117
-$48
-0.3%
$19,533
$19,497
-$36
-0.2%
Capital Cost
$304
$304
$0
0.1%
$297
$296
-$2
-0.6%
Variable Production
$26.00
$26.01
$0.02
0.1%
$25.85
$25.87
$0.02
0.1%
Cost ($/MWh)








Florida Reliability Coordinating Council (FRCC)
Total Domestic
27,584
27,584
0
0.0%
27,584
27,584
0
0.0%
Capacity (MW)








Early Retirements
1
1
0
0.0%
1
1
0
0.0%
- Number of Plants








Full & Partial
869
869
0
0.0%
869
869
0
0.0%
Retirements -








Capacity (MW)








Generation (GWh)
126,731
126,692
-39
0.0%
127,531
127,540
9
0.0%
Costs ($Millions)
$5,271
$5,266
-$5
-0.1%
$5,308
$5,305
-$3
-0.1%
Fuel Cost
$3,631
$3,630
-$1
0.0%
$3,645
$3,645
$1
0.0%
Variable O&M
$317
$317
$0
0.0%
$322
$322
$0
0.1%
Fixed O&M
$1,323
$1,319
-$4
-0.3%
$1,342
$1,338
-$4
-0.3%
Capital Cost
$0
$0
$0
NA
$0
$0
$0
NA
Variable Production
$31.15
$31.15
$0.00
0.0%
$31.10
$31.11
$0.01
0.0%
Cost ($/MWh)








EPA-821-R-19-012
C-11

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
Appendix C: IPM Sensitivity Analysis
Table C-4: Impact of Proposed ELG Option 2 on In-Scope Plants, as a Group, at the Year 2030,
Relative to Baseline and Alternative Baseline
Economic Measures

Option 2 without ACE

Option 2 with ACE
(all dollar values in
2018$)
Baseline
Value
Difference
% Change
Alternative
Baseline
Value
Difference
% Change
Midwest Reliability Organization (MRO)
Total Domestic
24,324
24,324
0
0.0%
24,308
24,308
0
0.0%
Capacity (MW)








Early Retirements
7
7
0
0.0%
7
7
0
0.0%
- Number of Plants








Full & Partial
4,402
4,402
0
0.0%
4,418
4,418
0
0.0%
Retirements -








Capacity (MW)








Generation (GWh)
139,319
139,622
303
0.2%
139,718
140,143
425
0.3%
Costs ($Millions)
$4,828
$4,832
$4
0.1%
$4,863
$4,865
$3
0.1%
Fuel Cost
$2,760
$2,768
$8
0.3%
$2,738
$2,749
$11
0.4%
Variable O&M
$647
$645
-$2
-0.3%
$654
$652
-$2
-0.3%
Fixed O&M
$1,345
$1,343
-$3
-0.2%
$1,395
$1,388
-$7
-0.5%
Capital Cost
$76
$76
$0
0.0%
$76
$76
$0
0.0%
Variable Production
$24.45
$24.45
-$0.01
0.0%
$24.28
$24.27
-$0.01
0.0%
Cost ($/MWh)








Northeast Power Coordinating Council (NPCC)
Total Domestic
11,120
11,120
0
0.0%
11,120
11,120
0
0.0%
Capacity (MW)








Early Retirements
3
3
0
0.0%
3
3
0
0.0%
- Number of Plants








Full & Partial
2,708
2,708
0
0.0%
2,708
2,708
0
0.0%
Retirements -








Capacity (MW)








Generation (GWh)
27,573
27,606
34
0.1%
27,592
27,652
60
0.2%
Costs ($Millions)
$1,309
$1,310
$1
0.1%
$1,310
$1,312
$2
0.2%
Fuel Cost
$608
$609
$1
0.1%
$609
$610
$2
0.3%
Variable O&M
$43
$43
$0
0.1%
$43
$43
$0
0.2%
Fixed O&M
$658
$658
$0
0.0%
$658
$658
$0
0.0%
Capital Cost
$0
$0
$0
NA
$0
$0
$0
NA
Variable Production
$23.62
$23.63
$0.00
0.0%
$23.62
$23.64
$0.02
0.1%
Cost ($/MWh)








ReliabilityFirst Corporation (RFC)
Total Domestic
76,002
76,016
14
0.0%
75,643
75,691
48
0.1%
Capacity (MW)








Early Retirements
35
36
1
2.9%
35
36
1
2.9%
- Number of Plants








Full & Partial
21,956
21,942
-14
-0.1%
22,317
22,269
-48
-0.2%
Retirements -








Capacity (MW)








Generation (GWh)
364,667
365,423
756
0.2%
361,432
364,656
3,224
0.9%
Costs ($Millions)
$13,982
$13,951
-$30
-0.2%
$13,907
$13,958
$51
0.4%
Fuel Cost
$8,038
$8,046
$8
0.1%
$7,902
$7,978
$77
1.0%
Variable O&M
$1,606
$1,605
-$1
-0.1%
$1,588
$1,599
$10
0.7%
Fixed O&M
$4,304
$4,265
-$38
-0.9%
$4,388
$4,352
-$37
-0.8%
Capital Cost
$35
$36
$1
2.8%
$29
$29
$0
0.6%
EPA-821-R-19-012
C-12

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
Appendix C: IPM Sensitivity Analysis
Table C-4: Impact of Proposed ELG Option 2 on In-Scope Plants, as a Group, at the Year 2030,
Relative to Baseline and Alternative Baseline
Economic Measures

Option 2 without ACE

Option 2 with ACE
(all dollar values in
2018$)
Baseline
Value
Difference
% Change
Alternative
Baseline
Value
Difference
% Change
Variable Production
Cost ($/MWh)
$26.44
$26.41
-$0.04
-0.1%
$26.26
$26.26
$0.01
0.0%
Southeast Electric Reliability Council (SERC)
Total Domestic
103,935
106,801
2,866
2.8%
103,986
106,801
2,815
2.7%
Capacity (MW)








Early Retirements
17
16
-1
-5.9%
16
16
0
0.0%
- Number of Plants








Full & Partial
20,836
17,970
-2,866
-13.8%
20,785
17,970
-2,815
-13.5%
Retirements -








Capacity (MW)








Generation (GWh)
479,646
482,880
3,235
0.7%
478,413
481,896
3,483
0.7%
Costs ($Millions)
$19,139
$19,265
$126
0.7%
$19,116
$19,265
$149
0.8%
Fuel Cost
$11,129
$11,232
$103
0.9%
$11,024
$11,133
$109
1.0%
Variable O&M
$1,630
$1,646
$15
0.9%
$1,629
$1,641
$13
0.8%
Fixed O&M
$6,313
$6,320
$7
0.1%
$6,396
$6,423
$28
0.4%
Capital Cost
$67
$67
$0
0.0%
$67
$67
$0
0.0%
Variable Production
$26.60
$26.67
$0.07
0.3%
$26.45
$26.51
$0.06
0.2%
Cost ($/MWh)








Southwest Power Pool (SPP)
Total Domestic
26,885
26,885
0
0.0%
26,885
27,129
244
0.9%
Capacity (MW)








Early Retirements
3
3
0
0.0%
3
3
0
0.0%
- Number of Plants








Full & Partial
1,879
1,879
0
0.0%
1,879
1,635
-244
-13.0%
Retirements -








Capacity (MW)








Generation (GWh)
116,430
116,717
288
0.2%
117,564
117,705
141
0.1%
Costs ($Millions)
$4,394
$4,395
$1
0.0%
$4,440
$4,438
-$2
-0.1%
Fuel Cost
$2,635
$2,642
$7
0.3%
$2,623
$2,627
$4
0.2%
Variable O&M
$582
$582
$0
0.1%
$592
$592
$0
0.0%
Fixed O&M
$1,163
$1,156
-$6
-0.5%
$1,210
$1,203
-$6
-0.5%
Capital Cost
$15
$15
$0
0.4%
$15
$15
$0
0.0%
Variable Production
$27.63
$27.63
$0.00
0.0%
$27.35
$27.35
$0.00
0.0%
Cost ($/MWh)








Texas Regional Entity (TRE)
Total Domestic
25,945
25,945
0
0.0%
25,945
25,945
0
0.0%
Capacity (MW)








Early Retirements
1
1
0
0.0%
1
1
0
0.0%
- Number of Plants








Full & Partial
391
391
0
0.0%
391
391
0
0.0%
Retirements -








Capacity (MW)








Generation (GWh)
114,229
114,369
140
0.1%
114,785
114,929
144
0.1%
Costs ($Millions)
$4,497
$4,498
$1
0.0%
$4,533
$4,534
$1
0.0%
Fuel Cost
$2,499
$2,504
$4
0.2%
$2,487
$2,490
$4
0.1%
Variable O&M
$441
$441
$1
0.1%
$448
$449
$1
0.2%
EPA-821-R-19-012
C-13

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
Appendix C: IPM Sensitivity Analysis
Table C-4: Impact of Proposed ELG Option 2 on In-Scope Plants, as a Group, at the Year 2030,
Relative to Baseline and Alternative Baseline
Economic Measures

Option 2 without ACE

Option 2 with ACE
(all dollar values in




Alternative



2018$)
Baseline
Value
Difference
% Change
Baseline
Value
Difference
% Change
Fixed O&M
$1,557
$1,553
-$3
-0.2%
$1,598
$1,594
-$3
-0.2%
Capital Cost
$0
$0
$0
NA
$0
$0
$0
NA
Variable Production
$25.74
$25.75
$0.01
0.0%
$25.57
$25.57
$0.01
0.0%
Cost ($/MWh)








Western Electricity Coordinating Council (WECC)
Total Domestic
41,077
41,077
0
0.0%
41,077
41,077
0
0.0%
Capacity (MW)








Early Retirements
12
12
0
0.0%
12
12
0
0.0%
- Number of Plants








Full & Partial
5,151
5,151
0
0.0%
5,151
5,151
0
0.0%
Retirements -








Capacity (MW)








Generation (GWh)
201,919
201,879
-40
0.0%
202,075
201,934
-141
-0.1%
Costs ($Millions)
$6,877
$6,878
$1
0.0%
$6,910
$6,901
-$9
-0.1%
Fuel Cost
$3,541
$3,545
$4
0.1%
$3,530
$3,531
$1
0.0%
Variable O&M
$721
$720
-$1
-0.2%
$723
$721
-$2
-0.2%
Fixed O&M
$2,502
$2,502
$0
0.0%
$2,547
$2,540
-$7
-0.3%
Capital Cost
$112
$111
-$1
-0.6%
$111
$109
-$2
-1.8%
Variable Production
$21.11
$21.13
$0.01
0.1%
$21.04
$21.06
$0.01
0.1%
Cost ($/MWh)








a. Numbers may not add up due to rounding.
Source: U.S. EPA Analysis, 2019.
Impacts on Individual Steam Electric Power Plants
Table C-5 presents the estimated number of steam electric power plants with specific degrees of change in
operations and financial performance as a result of proposed Option 2 when analyzed relative to the two
baselines.
The indicators of changes across individual steam electric plants are generally similar when assessed
against either baseline. The results indicate that most plants experience only slight effects - i.e., no
change or less than a one percent reduction or one percent increase. Six plants (1 percent) are estimated to
incur a reduction in capacity utilization of at least one percent and 28 plants (4 percent) incur a reduction
in generation of at least one percent. Finally, only 2 plants (0.3 percent) are estimated to incur an increase
in variable production costs of at least one percent.
EPA-821-R-19-012
C-14

-------
RIAfor Proposed Revisions to Steam Electric Power Generating ELGs
Appendix C: IPM Sensitivity Analysis
Table C-5: Impact of Proposed ELG Option 2 on Individual In-Scope Plants at the Year 2030,
Relative to Baseline and Alternative Baseline


Reduction

Increase



>1% and



>1% and


Economic Measures
>3%
<3%
<1%
No Change
<1%
<3%
>3%
N/Abc
Option 2 without ACE, Relative to Baseline
Change in Capacity








Utilization3
4
5
44
277
63
9
3
281
Change in Generation
17
9
27
277
43
14
18
281
Change in Variable








Production Costs/MWh
2
7
94
197
64
2
1
319
Option 2 with ACE, Relative to Alternative Baseline
Change in Capacity
2
4
48
271
55
18
6
282
Utilization3








Change in Generation
17
11
26
272
38
21
19
282
Change in Variable
2
10
81
191
81
2
0
319
Production Costs/MWh








a. The change in capacity utilization is the difference between the capacity utilization percentages in the baseline and policy
cases. For all other measures, the change is expressed as the percentage change between the baseline and policy values.
Source: U.S. EPA Analysis, 2019
EPA-821-R-19-012
C-15

-------