United States
Environmental Protection
mmu	Agency
INTERCONNECTION
Plugging RE-Powering Sites Into the Electric Grid
October 2019
RE-Powering America's Land Initiative
Explore important
interconnection factors:
•	Proximity
•	System Types
•	Costs
•	Anticipating the Process
Prepared under contract to EPA by:
ICF Incorporated, LLC

-------
Interconnection
Plugging RE-Powering Sites Into the Electric Grid

Contents
1.	What Is Interconnection and Why Is It Important for RE-Powering Sites?	1
2.	Interconnection Advantages	1
3.	Types of Interconnections	2
4.	Interconnection Review Process	4
5.	Interconnection Costs	8
6.	Tips to Minimize Interconnection Costs and Delays	11
7.	Conclusion and Key Takeaways	12
8.	More Information	13
Appendix A: Interconnection Queue Information for Selected U.S. Wholesale Electricity Markets ..14
Appendix B: Example Hosting Capacity Map	16
October 2019

-------
Interconnection
Plugging RE-Powering Sites Into the Electric Grid
1.	What Is Interconnection and Why Is It Important for
RE-Powering Sites?
EPA's RE-Powering America's Land initiative encourages the reuse of formerly contaminated lands,
landfills, and mine sites for renewable energy development, when such development is aligned with
a community's vision for the site. Renewable energy development on these properties requires
interconnection, a multistep technical, administrative, and financial process that enables a renewable
(or conventional) energy generator to interconnect to the electric grid and supply power.
Interconnection costs and development timelines can vary tremendously between projects—even
between projects that are seemingly very similar. The potential uncertainty and variability of
interconnection costs and timelines can become a deciding factor to the viability of a project.
Renewable energy project developers bear the primary responsibility for guiding their projects
through the interconnection process, but it is important for RE-Powering site owners, responsible
parties, and other stakeholders interested in sustainable site reuse to understand the interconnection
process and the factors that can delay or accelerate it.
This discussion paper provides RE-Powering stakeholders with information for efficiently proceeding
through the interconnection process for renewable energy projects connecting to the electric
transmission and distribution systems.
2.	Interconnection Advantages
The prior uses of the brownfield, Superfund,1 mining, and landfill sites that are the focus of the RE-
Powering Initiative may have rendered them unsuitable for most redevelopment options. But they can
offer several distinct advantages over greenfield sites for renewable power development, including
lower land acquisition costs, site exclusivity,2 expedited permitting, special tax incentives, and the
availability of existing infrastructure that would otherwise be very costly to construct.
This infrastructure may include:
•	Proximity to existing transmission or distribution electricity lines, as well as substations
•	Road, rail, or water access (critical for renewable project construction and regular maintenance
of projects)
•	Water supply infrastructure (critical for certain renewable energy projects, such as concentrating
solar power, biomass, and geothermal technologies)
1	EPA's Superfund program is responsible for cleaning up some of the nation's most contaminated land and responding to environmental
emergencies, oil spills, and natural disasters. Learn more < https://www.epa.gov/suDerfund
2	Generation interconnection processes can require evidence of site exclusivity, or exclusive site control by the project developer, for the
purposes of renewable development. This can be obtained from a lease, purchase agreement, or option to buy or lease. Due to the
history of designation and remediation at RE-Powering sites, establishing site exclusivity should be more straightforward than for many
greenfield renewable sites that may cross property boundaries and never have been part of an integrated permitting or regulatory
process.
October 2019
1

-------
Interconnection
Plugging RE-Powering Sites Into the Electric Grid
•	Physical security that can protect
renewable energy assets
•	Existing buildings, which can facilitate
renewable energy transactions behind
the customer meter that typically obtain
retail rates for the power produced
RE-Powering sites with some or all of these
features may offer meaningfully lower costs
and complexity for renewable energy
development and boost prospects for a
smooth interconnection process.
3. Types of
interconnections
Electricity is delivered from generators to
consumers via transmission and distribution
networks. Transmission networks are
operated by a regional transmission
organization (RTO), independent system
operator (ISO), or non-RTO/ISO operator
such as a utility.3 Transmission networks
consist of high-voltage power lines (typically
transmitting 100 kilovolts [kV] or more)
designed to carry power efficiently over long
distances. Distribution networks, operated
exclusively by utilities, deliver power at lower
voltages (typically transmitting 37 kV or less)
and over shorter distances to the consumer.
Generators may interconnect with the
electrical system at either the distribution or
transmission level, as described in Figure 1
Interconnection information on many of the
transmission systems that operate across the
U.S. is provided in Appendix A.
A RE-Powering Site With Interconnection
Advantages
The former Bethlehem Steel Plant in Lackawanna,
New York, is a RE-Powering site that was
developed in multiple stages for the 35 MW Steel
Winds (wind power) and 4 MW Steel Sun (solar)
projects. The availability of existing electric
infrastructure (including an on-site utility
substation)3 was an important, positive factor that
allowed such a large volume of renewable
generation to be safely and reliably interconnected
with the power grid.b
a A substation is an electrical facility that steps up or down the
voltage to either supply power to consumers or export power
back to the electric grid.
b EPA, Steel Winds, Lackawanna, New York: Development of
Wind Power Facility Helps Revitalize Rust Belt City,
https://www.epa.gov/sites/production/files/2015-
04/documents/success steelwinds nv.pdf [accessed
September 2019], and The Buffalo News, "Steel Sun" Project
Would Add Solar Panels Near Wind Turbines at Former
Bethlehem Site in Lackawanna, July 13, 2014
http://buffalonews.com/2014/07/13/steel-sun-proiect-would-
add-solar-panels-near-wind-turbines-at-former-bethlehem-
steel-site-in-lackawanna/ [accessed September 2019],
3 RTOs and ISOs are functionally similar entities responsible for transmission planning, operations, and the use of an electric grid
on a regional and interregional basis. A map of RTO/ISO regions is available from the Federal Energy Regulatory Commission at
https://www.ferc.aov/industries/electric/indus-act/rto.asp [accessed September 2019],
October 2019
2

-------
Interconnection
Plugging RE-Powering Sites Into the Electric Grid
Figure 1: Types of Distribution and Transmission Interconnections
Type of Interconnection
Typical
Interconnection
Voltage4
Typical Project
Generation
Capacity (AC)5
Primary Electricity
Markets6
Distribution export: Direct
connection7
4 kV-37 kV
Some 60 kV-
115 kV
50 kilowatts (kW)—
5 megawatts
(MW)
Wholesale markets under
Federal Energy Regulatory
Commission (FERC)
jurisdiction and/or retail
markets under state utility
commission, municipal, or
cooperative jurisdiction
Distribution: Net metered8
4 kV-37 kV
Some 60 kV-
115 kV
1 kW-2 MW
Retail markets under state
utility commission,
municipal, or cooperative
jurisdiction
Distribution: Virtual net
metered and community
renewables9
Usually
4 kV-37 kV
Some 60 kV-
115 kV
20 kW-5 MW
Retail markets under state
utility commission,
municipal, or cooperative
jurisdiction; sometimes
direct connection to a utility
Transmission
Some 60 kV-
115 kV
220 kV-765 kV
> 5 MW
Wholesale markets under
FERC jurisdiction
4	Voltage is the characteristic of an electric system that makes electricity move through transmission and distribution lines. It is typically
measured in kV across the transmission and distribution grid.
5	Capacity is the maximum power a generator can produce, commonly measured in kilowatts (k.W) and megawatts (MW).
1 MW = 1,000 kW. For interconnection purposes, capacity is typically expressed in alternating current (AC). The AC capacity of a solar
photovoltaic (PV) project will generally be 15% to 35% less than its direct current (DC) capacity, depending on how the project is
configured.
6	Wholesale markets are regulated by FERC and provide access to a variety of local and regional customers. Retail markets are under
the purview of state utility regulatory commissions (for investor-owned utilities), the municipal government (for municipal utilities), or an
oversight board (for electric cooperatives) and allow access to local utility markets. The retail prices of electricity are often higher than
wholesale prices due to additional charges, such as local distribution and pertinent taxes. In some cases, even projects that are
interconnected as net energy metered, virtual net metered, or community renewables may participate in some wholesale markets.
However, wholesale markets would not commonly be the only revenue source for such projects.
7	Distribution interconnection projects with "direct connection" typically do not interact with retail (electricity end-user) facilities or
electricity bills.
8	Net metering is a mechanism that allows behind-the-meter (i.e., residential, commercial, industrial, and institutional) generation projects
to sell the power they generate in excess of their meter's requirements back to the grid. This mechanism determines the compensation
for the excess power sales.
9	Virtual net metering (also called meter aggregation) is a mechanism for allocating net metering credits to utility electricity customers that
are not directly connected to an on-site generation project. Community renewable programs (usually focused on solar) also allocate off-
site renewable production to customers. Each utility with virtual net metering or community renewables programs will have specific rules
on customer eligibility and electricity allocations. Because virtual net metering and community solar projects are often between 500 kW
and 5 MW in capacity, they align well with the renewable potential of RE-Powering sites. The RE-Powering program published a
discussion paper on community solar, available at https://www.epa.gov/sites/production/files/2016-
12/documents/epa repowering community solar discussion paper final 120716 508.pdf [accessed September 2019].
October 2019
3

-------
Interconnection
Plugging RE-Powering Sites Into the Electric Grid
4. Interconnection Review Process
When individual interconnection applications are evaluated, statewide regulatory policies can have
substantial impacts on the cost, duration, and complexity of the process. For example, many states
limit the maximum capacity of generators that can net meter (sell excess power not consumed on-
site to the grid).10 Some states provide streamlined interconnection processes for systems below a
certain capacity threshold or that pass certain analytic tests or "screens."
Although interconnection review processes can differ depending upon the state, as well as the utility
and RTO/ISO, most processes include the broad steps depicted in Figure 2.
Figure 2: The Interconnection Review Process
11
ACCESS HOSTING
CAPACITY INFORMATION
REVIEW INTERCONNECTION
QUEUE
PRE-APPLICATION
REPORT
01

COMPLETE

APPLICATION
FAIL |
SUPPLEMENTAL
FAIL

REVIEW


DETAILED
~	*|
ANALYSIS
10	The Database of State Incentives for Renewables & Efficiencyฎ (DSIREฎ) provides descriptions of net metering policies in each state
and summary maps of national policies. See, for example, Customer Credits for Monthly Net Excess Generation (NEG) Under Net
Meterinc https://www.dsireusa.ora/resources/detailed-summarv-maps accessed September 2019], DSIREฎ is operated by the NC Clean
Energy Technology Center at North Carolina State University and is funded by the U.S. Department of Energy (DOE).
11	This figure is adapted from the Office of Energy Efficiency and Renewable Energy, DOE, On the Path to SunShot - Interconnection
Process http://enerav.aov/eere/sunshot/downloads/path-sunshot-interconnection-process ^accessed September 2019],
October 2019
4

-------
Interconnection
Plugging RE-Powering Sites Into the Electric Grid
This section describes seven of the general steps depicted in Figure 2 and explains what
developers of projects at RE-Powering sites can expect to provide and receive during each step.
Seven Interconnection Steps
1.	Request a pre-application report At the developer's request, the transmission or distribution
system operator may provide a pre-application report detailing a variety of information relevant
to the proposed generation project. This may include information about the substation and
voltage available at the proposed point of interconnection (POI), the closest feeders,12 the
circuit distance between the project and POI, any capacity estimates of relevant line sections,
and the availability of three-phase electric power (a common method of alternating-current
electric power generation, transmission, and distribution).13 The pre-application report, which
typically has a fee of between $300 and $1,300,14 allows the developer to assess the project's
interconnection prospects and risks before filing an actual interconnection application. Pre-
application reports are often available within two to four weeks of request and payment.15
A representative list of the data fields in a pre-application report is shown in Figure 3.
2.	Review the interconnection queue. At approximately the same time as when the developer
reviews the pre-application report, it will typically attempt to gather information on all other
generation projects that a transmission or distribution system operator is considering for
interconnection at the same POI as the developer's project. The first-to-last order of projects
seeking to interconnect at a POI is called the "interconnection queue." Queue information may
include the size and type of each project and where each project stands in the review process.
12	Feeders or "circuits" are distribution lines that transport power from a substation to consumer facilities.
13	While many utilities and other system operators offer pre-application reports, not all do. A sample pre-application report request from
the utility Southern California Edison is available at Rule 21 - Optional Pre-Application Report Request,
https://www1.sce.com/nrc/AboutSCE/requlatorv/Openaccess/forms/FORM Rule21 PreApplicationReauest Form 19-922.pdf [accessed
September 2019].
14	For example, Pacific Gas and Electric (PG&E) in California has reports that range from $300 to $1,325, and Central Hudson Gas &
Electric in New York has a report fee of $750, consistent with New York State interconnection requirements. In New York, the pre-
application report fee is applied to the cost of the interconnection application itself if an application is filed promptly after receipt of the
pre-application report. See PG&E's Pre-Application Report Request,
https://www.pqe.com/includes/docs/pdfs/mvbusiness/save/solar/Pre App.pdf [accessed September 2019]; and Central Hudson Gas &
Electric, Distributed Generation FAQ, https://www.cenhud.eom/dq/dq-faQ#6afce7e913b66510VqnVCM1000001600020aRCRD [accessed
September 2019],
15	FERC's model interconnection standards require utilities to provide pre-application reports within 20 business days. See FERC, Small
Generator Interconnection Agreements and Procedures, November 22, 2013, page 34 https://www.T~erc.gov/whats-new/comm-
meet/2013/112113/E-1.pdf [accessed September 2019], For investor-owned utilities in New York State, the pre-application reports must
be provided to developers within 10 business days. See New York State Public Service Commission (NYSPSC), New York State
Standardized Interconnection Requirements and Application Process for New Distributed Generators and Energy Storage Systems 5
MW or Less Connected in Parallel With Utility Distribution Systems, October 2018, page 9,
http://www3.dps.nv.gOv/W/PSCWeb.nsf/96f0fec0b45a3c64S5257688006a701a/dcf68efca391 ad6085257687006f396b/$FILE/Qctober%2
0SIR%20Appendix%20A%20-%20Final%2010-3-18.pdf [accessed September 2019].
October 2019
5

-------
Interconnection
Plugging RE-Powering Sites Into the Electric Grid
Figure 3: Components of Pre-Application Report for Distributed Generation of 5 MW
or Less in New York State16
Project Data Provided to Utility With Pre-Application Request
Customer name (arid date of pre-application
request)
Distributed generation fuel source/configuration
Location of project (address and/or global
positioning satellite [GPS] coordinates)
Proposed project size in kW-AC
Distribution generation technology type

Pre-Application Report Data Elements Provided Back to the Applicant
Operating voltage of closest distribution line
Approximate distance (miles) between serving substation
and project site
Phasing at site
Number of substation banks
Approximate distance to 3-phase (if only 1 or 2
phases nearby)
Total substation bank capacity (MW)
Circuit capacity (MW)
Total substation peak load (MW)
Fault current availability, if readily obtained
Aggregate existing distributed generation on the circuit
(kW)
Circuit peak load for the previous calendar year
Aggregate queued distributed generation on the circuit
(kW)
Circuit minimum load for the previous calendar year

3. Access hosting capacity information. When possible, the developer also could obtain free
information about the hosting capacity of the distribution circuit. Hosting capacity maps, an
example of which is in Appendix B, give developers a good indication of how far their projects
are from the closest distribution infrastructure and how much new generation capacity might
be accommodated at various nearby locations on a distribution system. This information will
give the developer insight into whether the interconnection review process might be delayed
and whether costly system upgrades are likely. In addition to obtaining a pre-appiication
report, analyzing any available hosting capacity data, and reviewing the interconnection
16 Appendix D: Pre-Application Report for the Connection of Parallel Generation Equipment to the Utility Distribution System of the
NYSPSC, Standardized Interconnection Requirements and Application Process for New Distributed Generators and Energy Storage
Systems 5 MW or Less Connected in Parallel With Utility Distribution Systems, October 2018, PDF page 61,
http://www3.dps.nv.gOv/W/PSCWeb.nsf/96f0fec0b45a3c6485257688006a701a/dcf68efca391 ad60852576S7006f396b/$FILE/Qctober%2
0SIR%20Appendix%20A%20-%20Final%2010-3-18.pdf [accessed September 2019], SCE and the other two California investor-owned
utilities also offer a presentation on How to Read a Pre-Application Report at
https://www.pge.com/includes/docs/pdfs/b2b/newqenerator/retailgenerators/Pre-AppiicationReport.pdf [accessed September 2019],
October 2019
6

-------
Interconnection
Plugging RE-Powering Sites Into the Electric Grid
queue, developers should conduct detailed technical due diligence on potential projects.
Additional technical due diligence on interconnections can be conducted by reviewing prior
interconnection studies from nearby sites, researching land use permits and right of way
processes from local and state agencies, and seeking guidance from renewable energy
installation firms experienced in the local market.
4.	Complete the interconnection application. Assuming the developer's review of the pre-
application report, interconnection queue, and hosting capacity data does not dissuade it from
pursuing the project further, the developer will next complete an interconnection application.
Applications may require detailed technical information about the project, including its
generator type, proposed interconnection type and location, and documentation that the
developer has appropriate land use rights as well as appropriate licenses or certificates to
participate in the renewable energy industry in the jurisdiction.
5.	Request a streamlined interconnection review (fast tracking). Many utilities have fast
track processes for generation projects of 5 MW or less in capacity, if they meet certain
requirements that expedite interconnection review while protecting against negative grid
impacts.'17 Fast tracking can substantially reduce the time, often by eight or more weeks, and
complexity of interconnection processes for qualifying generation projects. In jurisdictions that
have adopted FERC model standards, meeting the criteria presented in Figure 4 provides
potential fast track eligibility for inverter-based projects.18 More than 80% of completed RE-
Powering projects are 5 MW or less in capacity and, therefore, may be candidates for fast
track review in certain jurisdictions.19
Figure 4: Fast Track Capacity Eligibility for Inverter-Based Systems Under FERC
Model Standards20
Line Voltage
Eligibility Regardless
of Location
Eligibility on a Mainline and
Within 2.5 Electrical Circuit
Miles of a Substation
< 5 kV
< 500 kW
< 500 kW
>5 kVand < 15 kV
<2 MW
<3 MW
> 15 kVand < 30 kV
<3 MW
<4 MW
> 30 kV and < 69 kV
<4 MW
<5 MW
17	Fast track eligibility is often determined by a combination of renewable project capacity, distance from the project to the nearest
substation, and voltage and available capacity of the transmission or distribution facility to which the project is seeking to interconnect.
Potential negative grid impacts include voltage, thermal, protection, and other power quality violations.
18	inverters convert the variable direct current (DC) output of PV into an alternating current (AC) frequency that can be fed into building
electricity use or the commercial electrical grid.
19	These data are calculated from the list of completed projects in the RE-Powering America's Land Initiative's Project Tracking Matrix,
published in January 2019, https://www.epa.gov/sites/production/files/2019-02/documents/re tracking matrix 508 final 013119a.pdf
[accessed September 2019],
20	FERC, Small Generator Interconnection Procedures (SGIP), August 27, 2018, pages 7-8,
https;//www fere.aov/industries/electric/indus-act/ai/small-aen/sm-gen-procedures.pdf accessed September 2019],
October 2019
7

-------
Interconnection
Plugging RE-Powering Sites Into the Electric Grid
6.	Request a standard review. If a renewable project either does not qualify for fast track
review, or qualifies but fails fast track analytic screens, it will need to proceed through the
standard interconnection process. This involves the transmission or distribution system
operator performing detailed computer simulations of how electricity would flow from the
proposed project through all relevant components of its system. The simulations are intended
to reveal new facilities and upgrades needed to maintain system safety and reliability under
all conditions and to produce project cost estimates.
If new facilities or system upgrades are required, the transmission or distribution operator will
provide the developer with cost estimates to implement the necessary system enhancements.
Such costs are borne by the proposed project or shared with other projects, depending on
how the grid operator manages group studies and interconnection queues.
The renewable developer can request that utilities provide further details on technical
requirements and costs and may redesign its project accordingly to reduce interconnection
costs. The developer may also be able to use a dispute resolution processes (e.g., with access
to an independent engineer or other arbitrator) to address remaining concerns.
7.	Execute the interconnection agreement after project approval. If the developer decides
to move forward with the project, it will execute an interconnection agreement with the
transmission or distribution grid operator that details the responsibilities of each party.
5. Interconnection Costs
As previously noted, developers are typically responsible for all costs incurred for interconnection
reviews, as well as for the material and labor costs for new transmission or distribution facilities and
grid upgrades required to physically connect the generator to the grid. Below, the costs of an
interconnection review or "study" are described first, followed by the typically much larger material
and labor costs of interconnection.
The costs of an interconnection review will vary widely, depending upon factors such as project size
and location, position in the interconnection queue, interconnection voltage, and eligibility for fast
tracking. Smaller distribution-level projects eligible for fast tracking may only pay study fees of
$2,500 or less,21 while the fee for a standard interconnection review of proposed transmission
projects greater than 20 MW can often exceed $150,000.22
21	For example, see Southern California Edison, Rule 21: Generating Facility Interconnections, Section E.2, Effective June 8, 2017,
https://librarv.sce.com/content/dam/sce-dociib/public/regulatorv/tariff/electric/rules/ELECTRIC RULES 21 .pdf laccessed September
2019],
22	For example, see California ISO, Appendix DD: Generation Interconnection andDeliverability Allocation Procedures, Section 3.5.1,
April 1, 2019, http://www.caiso.com/Documents/AppendixDD-Generatorlnterconnection-DeliverabilitvAllocationProcedures-asof-Apr1 -
2019.pdf#search=appendix%20dd [accessed September 2019].
October 2019
8

-------
Interconnection
Plugging RE-Powering Sites Into the Electric Grid
For projects on distribution systems, the total cost of interconnection itself wiil depend on the utility's
requirements (monitoring and control equipment, system protection devices, etc.) and the cost of
mitigating system violations identified by the utility. In Xcel Energy Minnesota's popular community
solar program, typical interconnection costs range widely from $2,000 to $150,000 for projects
between 250 kW and 1 MW in
capacity, and from $5,000 to $1
million for projects larger than 1
MW.23
The actual project
interconnection costs required
to maintain grid safety and
reliability are primarily driven by
the grid impact studies
performed during the standard
review process and can vary
significantly based on the
common cost drivers such as
project size, interconnection
options, findings from the
impact study process, and
applicable utility tariff rules.
Some transmission operators,
such as California ISO, provide
interconnection unit cost guides
for use in estimating the cost of
facilities required to
interconnect	generation.
Selected data from that cost
guide are summarized in the
text box on the prior page.
Project-level data on the
estimated interconnection costs
of RE-Powering projects can
also be obtained in some cases
from the grid operator, such as
from PJM for the Mid-Atlantic
and Ohio Valley transmission
Transmission interconnection
Per Unit Cost Guide
California ISO's annual per unit cost guide for transmission
upgrades is particularly useful both because more than one-
third of all U.S. solar generation projects and 9% of all
renewable energy capacity of RE-Powering projects are In
California,0 and because the data are a good reference point
for the rest of the nation. The estimated interconnection costs
range from $0.9 million to $2.5 million per mile to
"reconductor" a typical 69-kV single circuit line to upgrade its
carrying capability. New substation equipment can range from
$12.5 million for a 69-kV substation to $15 million for a
230-kV substation for a single existing transmission line.
These cost estimates for transmission lines are based on flat
land and rural settings and do not reflect permitting and right-
of-way costs. Transmission line costs can vary significantly
due to other factors, such as the type of terrain (cost multiplier
of 1.3 for hilly terrain) and population density (cost multiplier
of 1.5 for urban populations).01
c U.S. solar generation data from Solar Energy Industries Association,
https://www.seia.orq/states-map; and RE-Powering program data from
https://www.epa.gov/sites/production/files/2019-
02/documents/re tracking matrix 508 final CS13119a.pdf [both accessed
September 2019],
11 See PG&E 2019 Final Per Unit Cost Guide at
https://www.caiso.com/informed/Pages/StakeholderProcesses/Participating
TransmissionOwnerPerUnitCosts.aspx [accessed September 2019],
23 Xcel Energy Minnesota, Solar*Rewardsฎ Communityฎ -Engineering Frequently Asked Questions, updated January 31, 2017,
https://www.xcelenergv.com/staticfiles/xe-responsive/Admin/l\/lanaqed%20Documents%20&%20PDFs/MN-SRC-Engineering-FAQs.pdf
[accessed September 2019],
October 2019

-------
Interconnection
Plugging RE-Powering Sites Into the Electric Grid
system.24 For example, interconnection system impact studies for three
RE-Powering solar projects in New Jersey show interconnection cost estimates of:
•	Hackensack Brownfield: Up to 1.1 MWac project with cost estimate of $182,90025
•	Brick Township Landfill Superfund: Up to 5 MWac project with cost estimate of $291,07726
•	Kinsley Landfill: Up to 5 MWac project with cost estimate of $865,01927
Note that all of these interconnections are within the same transmission operator's territory and still
vary significantly in their costs per unit of solar capacity. This variation in interconnection costs is
driven by multiple factors, including length and complexity of electricity line extensions and system
upgrades required.
Scituate Solar Landfill Project: Interconnection Success Story
The town of Scituate, Massachusetts, investigated the potential for a 3 MW solar project on a closed
landfill, to complement a wind project on a nearby wastewater plant facility. The initial interconnection
cost estimate for the solar project was $900,000, due to utility concerns about the volume of variable
renewable power at the POI from this proposed solar project and an existing wind project. That cost
would have compromised the economics of the project.
However, the developer worked with National Renewable Energy Laboratory data and the utility to
conduct follow-up technical studies to show how timing of wind and solar power production would be
largely complementary. That analysis reduced utility interconnection concerns and ultimately resulted
in a successful interconnection outcome with much lower upgrade costs.ฎ This exemplifies the
benefits of RE-Powering parties viewing interconnection reviews as an Interactive process.
e EPA, An Old New England Town Lights the Way With Solar, https://vvvvvv.epa .gov/sites/production/files/2015-
04/documents/scituate landfill case studv.pdf [accessed September 2019],
24	PJM, New Services Queue, https://www.pim.com/plannina/services-reauests/interconnection-gueues.aspx [accessed September 2019].
25	PJM, Generator Interconnection Request Queue X1-072, Hackensack (Solar for All) 4kV, Feasibility/Impact Report, July 2011,
http://pim.com/pub/plannina/proiect-aueues/impact studies/x1072 imp.pdf accessed June 2019], Final (actual) interconnection costs from
invoices to project developers do not appear to be published by PJM, which is the reason that estimated costs are shown here.
26	PJM, Generation Interconnection Combined Feasibility/System Impact Study Report for PJM Generation Interconnection Request Queue
Position Y2-051, Brick-Lanes Mill 34.5kV, January 2013, http://pim.com/pub/plannina/proiect-gueues/impact studies/v2051 imp.pdf
[accessed September 2019], EPA published a case study of this solar project: EPA, Brick Township Goes Solar: Redevelopment of a
Superfund Site, https://semspub.epa.qov/work/02/372924.pdf [accessed September 2019],
27	PJM, Generation Interconnection System Impact Study Report for PJM Generation Interconnection Request Queue Position Y2-081.
Deptford (Kinsley Solar) 13kV, December 2013 http://pim.com/pub/planninq/proiect-queues/impact studies/v2081 imp.pdf accessed
September 2019], This development is likely connected to or dependent on another adjacent or nearby solar project as referenced by a
note on page 3 of the study: "If previous solar projects are not completed, the cost for feeder metering could increase..."
October 2019
10

-------
Interconnection
Plugging RE-Powering Sites Into the Electric Grid
6. Tips to Minimize Interconnection Costs and Delays
As RE-Powering stakeholders support developers in navigating the interconnection process, below
are 10 tips to improve outcomes.
1.	Explore any freely available online interconnection resources (e.g., interconnection
queues and hosting capacity maps of utilities).
2.	Request a pre-application report early in project planning.
3.	Come prepared with relevant information.28 29
4.	Stick to mandated interconnection timelines (an application can be rejected for non-
compliance).
5.	Align external approvals (e.g., easements, conditional use permits) with interconnection
timelines to keep the project on track.
6.	Obtain an independent expert's engineering review if the interconnection upgrade cost
seems unreasonable.
7.	Appeal if you receive late, incomplete, or questionable feedback from the utility or
ISO/RTO.30
8.	Point out special project design aspects, such as inverter features to control output from
solar PV projects, which may mitigate potentially adverse grid impacts.
9.	Be open to modifying your project to make it more interconnection-friendly (e.g., by reducing
generation capacity to eliminate the need for costly system upgrades).
10.	Constructively engage with all stakeholders. A successful interconnection process
requires frequent and close coordination between all stakeholders. Engaging with utilities as
project partners can be especially effective. This coordination begins with the pre-application
process and continues through the initial commercial operation of the project. Common
opportunities for engagement include:
• Scoping meetings after submitting the interconnection application
28	Most utilities also have a list of documentation that developers must submit for transmission and distribution interconnections. These
documents typically include the interconnection application, detailed site plans with the location of all relevant equipment, a certificate of
electrical inspection, proof of insurance, and a one-line diagram. In power engineering, a one-line or single-line diagram shows the
arrangement and connection of various equipment.
29	For a distribution utility example of required documentation, see Appendix F: Application Package Checklist of the NYSPSC,
Standardized Interconnection Requirements and Application Process for New Distributed Generators and Energy Storage Systems 5
MW or Less Connected in Parallel with Utility Distribution Systems, October 2018, PDF page 64.
http://www3.dps.nv.gOv/W/PSCWeb.nsf/96f0fec0b45a3c6485257688006a701a/dcf68efca391 ad6085257687006f396b/$FILE/Qctober%2
0SIR%20Appendix%20A%20-%20Final%2010-3-18.pdf [accessed September 2019]. For a transmission operator example, see the list of
resources the California ISO requests to begin an application: ISO Interconnection Request,
https://www.caiso.com/plannina/Paaes/Generatorlnterconnection/lnterconnectionReauest/Default.aspx [accessed September 2019].
30	Additionally, some jurisdictions have dispute resolution processes requiring that grid operators provide additional technical information
to the disputing party to justify proposed interconnection costs.
October 2019
11

-------
Interconnection
Plugging RE-Powering Sites Into the Electric Grid
•	Results meetings after interconnection screenings or computer simulations
•	Contract negotiations when finalizing the interconnection agreement
•	Project testing prior to commercial operation
7. Conclusion and Key Takeaways
By understanding the factors that influence interconnection costs and review cycles, RE-Powering
site owners, responsible parties, state and local government agencies, and other stakeholders will be
in a better position to (i) understand which sites have the best opportunities for development, (ii)
support developers through the interconnection process at high-potential sites, and (iii) avoid
spending time and resources on sites with low potential. The important interconnection factors
considered in this paper include:
•	Distance to the nearest transmission or distribution system point of interconnection
•	Distinctions between transmission and distribution systems
•	The generation capacity of a renewable project affecting transmission and distribution operator
evaluations of project impacts on their grids
•	Hosting capacity, pre-application reports, and other ways of estimating the ability of existing grid
infrastructure to accommodate more generation without costly upgrades
•	Access to fast track interconnection review processes for small to mid-sized projects meeting
certain conditions
•	The wide range of interconnection costs for new facilities and system upgrades on distribution or
transmission systems that may be required
•	The benefits of being proactive and organized in approaching interconnection applications
•	The interactive nature of many interconnection reviews
Developers bear the ultimate responsibility for submitting the interconnection application and
engaging with the transmission or distribution grid operator. Developers must ensure that the project
details are properly conveyed, that the project design is optimized to minimize interconnection costs
and shorten development timelines, and that viable RE-Powering sites have the best opportunity for
renewable energy deployment. With this information, RE-Powering stakeholders can support the
project developers during this process.
October 2019
12

-------
Interconnection
Plugging RE-Powering Sites Into the Electric Grid

8. More Information
EPA offers a comprehensive list of resources for developers to learn more about its RE-Powering
America's Land Initiative. The RE-Powering Mapper database offers a list of potential redevelopment
sites, noting proximity of electrical infrastructure, site access, and other information. Visit
https://www.epa.aov/re-powering to learn more. Also, EPA has a network of RE-Powering contacts
across its regional offices (visit https://www.epa.gov/re-powering/forms/contact-us-about-re-
powering-americas-land;
Additional information sources specific to interconnections are provided below.
Interconnection Process Overviews
Midwest ISO Generator Interconnection Process (flow chart):
https://cdn.misoenergv.org/GI%20Process%20Flow%20Diagram106549.pdf
California ISO Interconnection Timeline and Process:
http://www.caiso.com/Documents/2-2018Studies-StudvResults-ProiectCostResponsibilitv.pdf
Southern California Edison Fast Track Interconnection Process:
https://www.enerqy-exchange.eom/wp-content/uploads/T 11S6 Giannotti.pdf (pages 28-31)
Interconnection Applications and Data Forms
California ISO Interconnection Request:
http://www.caiso.com/Documents/IRandStudvAgreement26Feb2019FINAL.docx
Interconnection Agreements
Many jurisdictions and utilities base their interconnection agreements on versions of the following
FERC materials:
FERC Standard Interconnection Agreements & Procedures for Small Generators:
https://www.ferc.gov/industries/electric/indus-act/gi/small-gen.asp
FERC Standard Interconnection Agreements & Procedures for Large Generators:
https://www.ferc.gov/industries/electric/indus-act/gi/stnd-gen.asp
Miscellaneous Information on Interconnection
EPA Toolbox for Renewable Energy Project Development - Solar Interconnection Standards &
Policies: https://www.epa.gov/repowertoolbox/solar-interconnection-standards-policies
October 2019
13

-------
Interconnection
Plugging RE-Powering Sites Into the Electric Grid
Appendix A: Interconnection Queue Information for
Selected U.S. Wholesale Electricity Markets
Figure 5: Region-Specific Data on Queues to Interconnect Generators to Wholesale
Electricity Markets
States
ISO or RTO
(Transmission
Operator) or
Utility
Resource
Name
Types of Data Available With
Resource
Website Link
CA
California ISO
(CAISO) -
Transmission
Operator
Resource
Interconnection
Management
System
•	Queue Position
•	Request Date
•	Application Status
•	Study Process
•	Generation/Fuel Type
MW
•	Utility
•	Section or Transmission Line
•	Projected Service Date
CAISO Resource Interconnection
Management System (Queue):
https://rimspub.caiso.com/rims5/loaon.do
CA
Southern
California Edison
(SCE) - Utility
Wholesale
Distribution
Access Tariff
(WDAT) Queue
•	Request Date
•	Application Status
•	Technology*
•	Type/Fuel Facility
•	Summer/Winter MW
SCE WDAT & Rule 21 Interconnection
Queue:
https://www.sce.com/nrc/aboutsce/reaulat
orv/openaccess/wdat/wdat aueue.xls
CA
Pacific Gas and
Electric (PG&E) -
Utility
Wholesale
Distribution
Access Tariff
(WDAT) Queue
•	Exports
•	County
•	Substation and Circuit
•	Proposed Online Date
•	Study Availability
•	Interconnection Process Type*
PG&E WDAT Interconnection Queue:
https://www.Dae.com/oae alobal/common
/word xls/for-our-business-
partners/interconnection-
renewables/enerav-transmission-and-
storaae/wholesale-aenerator-
interconnection/PublicQueuelnterconnecti
on.xls
CA
San Diego Gas
& Electric
(SDG&E) - Utility
Wholesale
Distribution
Access Tariff
(WDAT) Queue

SDG&E WDAT Interconnection Queue:
https://www.sdae.eom/sites/default/files/d
ocuments/SDGE%20WDAT%20%26%20
Rule%2021%20Generation%20lnterconn
ection%20Queue%2005-20-19.pdf
TX
Electric
Reliability
Council of Texas
(ERCOT) -
Transmission
Operator
Transmission
Project
Information
Tracking
•	Project Number/Name
•	Queue Position
•	Request Date
•	Project Description
•	Location
•	Application Status
ERCOT Planning - Transmission Project
Information Tracking:
http://www.ercot.com/aridinfo/plannina
http://www.ercot.com/content/wcm/kev d
ocuments lists/89026/ERCOT February



•	Projected Service Date
•	Service Level
•	Circuit Miles
•	Autotransformer Capacity
TPIT No Cost 020119.xlsx
AR, KS, LA,
MN, MO,
MT, ND, NE,
Southwest
Power Pool -
Generation
Interconnection
•	Interconnection Number
•	Nearest Town/ State
•	Projected Service Date
•	Capacity
Southwest Power Pool Generation
Interconnection Active Requests:
October 2019
14

-------
Interconnection
Plugging RE-Powering Sites Into the Electric Grid
States
ISO or RTO
(Transmission
Operator) or
Utility
Resource
Name
Types of Data Available With
Resource
Website Link
NM, OK, SD,
TX, WY
Transmission
Operator
Active
Requests
•	Summer/Winter MW
•	Service Type
•	Generation Type
•	Substation or Line
•	Status
•	Studies (Feasibility/Impact)
http://opsportal.spp.ora/Studies/GIActive
AR, IL. IN,
IA, KS, KY,
LA, Ml, MN,
MS, MO,
MT. NE, NC,
ND, OH, PA,
SD, TX, Wl,
WY
Midwest ISO
(MISO) -
Transmission
Operator
Interconnection
Queue
•	Project Number
•	Queue Date
•	Transmission Owner
•	County/State
•	Summer/Winter MW
•	Projected Service Date
•	Facility/Fuel Type
•	Study/Request Status
•	Studies (Feasibility/Impact)
MISO Interconnection Queue:
https://www.misoenerqv.orq/planninq/qen
erator-interconnection/GI Queue
DC, DE, IL,
IN, KY, MD,
Ml, NC, NJ,
OH, PA, VA,
VW
PJM -
Transmission
Operator
Generation
Queues
•	Queue Number
•	Project Name
•	Capacity
•	Status
•	Projected Service Date
•	Fuel Type
•	State
•	Studies (Feasibility/Impact)
•	Transmission Owner
PJM Generation Queues:
https://www.pim.com/plannina/services-
reauests/interconnection-aueues.aspx
New York
New York ISO
(NYISO) -
Transmission
Operator
Interconnection
Queue
•	Queue Position
•	Developer Name
•	Project Name
•	Date of Request
•	Summer/Winter MW
•	Type/Fuel
•	Location
•	Interconnection Point
•	Utility
•	Studies
•	Projected Service Date
NYISO Interconnection Queue:
httos://www. nviso.com/interconnections
CT, MA, ME,
NH, Rl, VT
ISO New
England -
Transmission
Operator
Interconnection
Request Queue
•	Project Type
•	Location by State, County, and
Zone
•	Interconnection Point
•	Fuel Type & Renewable Sources
•	Proposed Net Change in MW and
Network Resource Capability
ISO New England Interconnection
Request Queue:
https://www.iso-ne.com/svstem-
plannina/transmission-
plannina/interconnection-request-queue
*Not provided by all utilities
October 2019
15

-------
Interconnection
Plugging RE-Powering Sites Into the Electric Grid
Appendix B: Example Hosting Capacity Map
Figure 6: Hosting Capacity Map From the California Utility Pacific Gas and Electric31
tnter an Address or Coordinate
' Color by Generic PVIC
1 Color by Generation IC w/out OpFlex i
Color by Generic PV IC w/out OpFlex
ฎ Color by Load IC
T'TColusa
Junytfp'r
Solution SetJ_
Map data ฎ2Q19 Terms of Use
4.16kV;


Feeder level/RAM (Lines)
• Line Level/ICA (Lines)
Color by Generation IC
Not Available
Phase (ICA Not Performed)
Three-Phase (Incomplete
31 Pacific Gas and Electric Company, View the Integration Capacity Analysis Map, https://www.pge.com/en US/for-our-business-
partners/distribution-resource-plannina/distribution-resource-plannina-data-portal.paae [accessed September 2019].
October 2019
16

-------