EPA issued Administrative Order on Consent to Amphenol 1990 and 1998 Groundwater recovery system installed, upgraded & expanded 1995 I 1999 | 2010 Sub-slab depressurization 1 system (SSDS) installed in building on-site In-situ chemical oxidation treatment of soil below former plating room Ambient air sampling at site perimeter Public Meeting with IDEM, ISDH EPA announces plan to review site conditions May 2011 July 2011 July 2018 August 2018 EPA Public Information Session at Franklin High School (with ATSDR, IDEM) November 2018 Soil gas sampling October 2018 6 SSDS installed in homes Plumbing repairs in 9 homes Plumbing repairs in 9 homes 37 homes sampled for vapor intrusion Off-site groundwater sampled Sewer gas sampling September 2018 - August 2019 September 2018 Indoor air tested at \\ Soil sampling to building occupying )) support sewer former Amphenol Site // remedy design December 2018 February/March 2019 Off-site groundwater sampled March 2019 I 2nd ambient air study at site perimeter EPA Public Information Session (with ATSDR, IDEM) Stakeholder Information Plan to public Off-site groundwater sampled May 2019 June 2019 July 2019 Sewer replacement and soil remedy completed Street re-paving begins I November 2019 I 5 new off-site monitoring wells installed EPA begins Pilot study of stakeholders groundwater treatment group calls study begins EPA Open House at Franklin Library Sewer/Soil remedy begins October 2019 August 2019 Construction Air Monitoring Sewer re-lining scheduled to begin EPA hosts Open House Evaluation of groundwater treatment Groundwater remedy selection On-site source evaluation Continued re-testing of air in homes December 2019 Sewer remedy monitoring Public Meetings Completion of street and yard restoration Sewer Gas Sampling ------- |