Third Annual Report Regarding Progress in
Developing a Dredged Material Management Plan
for the Long Island Sound Region
For the Period July 6, 2007 - July 5,2008
U.S. Environmental Protection Agency, Region 1
October 2008
CT
New
London
New
Haven
Clintoi
Central
Satin
Stam ford
A TLAN TI C
OCEAN

-------
INTRODUCTION
This is the third annual report by the U.S. Environmental Protection Agency (EPA) on progress toward
completion of a dredged material management plan (DMMP) for the Long Island Sound region, and
related efforts to "reduce or eliminate" the need for open-water disposal of dredged material in Long
Island Sound.
BACKGROUND
EPA Regulatory Requirements
On June 3, 2005, EPA issued a final rule to designate two open-water dredged material disposal sites,
Central Long Island Sound and Western Long Island Sound, for the placement of dredged material
from harbors and navigation channels in the Long Island Sound vicinity in the states of Connecticut
and New York [40 CFR Part 228.15(b)(4) and (b)(5)].
The use of these two sites is subject to restrictions that are described in the site designation rule and
are intended to reduce or eliminate the disposal of dredged material in Long Island Sound. Use of the
sites pursuant to these designations may be suspended or terminated in accordance with these
restrictions.
One of these restrictions links continued use of the sites to the completion of a regional dredged
material management plan (DMMP) for Long Island Sound. A DMMP is a comprehensive planning
process and decision-making tool to address the management of dredged material for a specific harbor
or navigation project, group of related projects, or geographic area. Additional detail on the DMMP is
provided in the next section.
A related restriction requires EPA to conduct an annual review of progress toward completion of the
DMMP. EPA is complying with this requirement by producing an annual report on or about the
anniversary of the effective date of the site designations (July 5, 2005), and making the report
available to the general public.
Another restriction is intended to ensure progress toward reducing or eliminating open-water disposal
in Long Island Sound pending completion of the DMMP by requiring the formation of an interagency
Long Island Sound Regional Dredging Team (RDT). The RDT reviews dredging projects to ensure
that a thorough effort has been conducted to identify practicable alternatives to open-water disposal
and ensure the use of those alternatives to the maximum extent practicable. In addition to information
on the status of the DMMP, this EPA annual report includes information on RDT deliberations
conducted in the preceding year, and on the quantity of dredged material and its final placement or
disposal location. Additional detail on the form and function of the RDT is provided in a later section.
Dredged Material Management Plans
The U.S. Army Corps of Engineers (USACE) regulations require each of its district offices to develop
a DMMP for all Federal Navigation Projects for which there is an indication of insufficient placement
or disposal capacity to accommodate maintenance dredging for the next 20 years. A DMMP addresses
1

-------
a wide range of environmentally acceptable, cost-effective, and practicable alternatives for the
management of dredged material, culminating with the selection of a base plan and a recommended
plan that ensures that sufficient capacity for dredged material placement exists for a project or group
of projects for the required 20-year planning period. The range of alternatives includes those that may
provide environmental or commercial benefits through beneficial use of dredged material. The scope
of a DMMP may also include private dredging projects that are geographically related to the federal
project(s), which may require the sponsors of those projects to provide non-federal funds to support
the additional work.
The DMMP process involves a phased approach. The first phase, a Preliminary Assessment, draws on
existing information to: (1) determine the economic and engineering need for dredging according to
existing and reasonably prospective navigation traffic; (2) identify the anticipated locations and
volumes of dredged material to be generated within the study area; (3) examine existing dredged
material disposal sites and management practices to determine if shortfalls in capacity or opportunities
for better management exist; and (4) provide an estimate of the cost of completing the DMMP. The
Preliminary Assessment determines whether a federal interest exists in participating in a feasibility-
level DMMP study and also identifies potential non-federal sponsor(s) of the DMMP.
After the PA phase is completed, the DMMP is initiated. The first step is development of a Project
Management Plan (PMP) that describes: (1) the scope of the DMMP; (2) the sequence of the studies;
(3) a plan for acquisition management covering the various study tasks (labor, contracts, other agency
contributions); (4) a plan for public involvement and participation; and (5) an estimated budget,
organized by federal fiscal year budget cycle.
Following review and acceptance of the PMP by the cooperating federal and state agencies, feasibility-
level study efforts would commence, subject to the availability of staff and funding. These studies
generally focus on the following topics: (1) dredging needs; (2) management options; (3) capacities of
placement sites; (4) environmental compliance requirements; (5) potential for beneficial use of
dredged material; and (6) indicators of continued economic justification. The PMP is considered a
"living document," subject to change based on new information and input from the public and other
agencies.
The management structure for a typical DMMP comprises the following components:
•	Project Manager: Individual responsible for day-to-day management of project.
•	Project Delivery Team (PDT): The interagency working group that will assist with the
development of the DMMP.
•	Agency Technical Review Team: Required by the USACE to review the plan for technical
merit and cost-effectiveness.
•	Technical working groups: These may be formed to provide assistance to the Project Delivery
Team, with representation from other federal and state agencies, and sometimes non-
government organizations and private citizens.
For compliance with the National Environmental Policy Act (NEPA), the USACE prepares a
Programmatic Environmental Impact Statement (PEIS) that evaluates the analyses and
recommendations of the DMMP.
2

-------
LONG ISLAND SOUND DREDGED MATERIAL MANAGEMENT PLAN
Management Structure
The USACE is the lead agency for development of the Long Island Sound Dredged Material
Management Plan (LIS DMMP). The New England District and New York District, with oversight by
the North Atlantic Division, are developing the DMMP in cooperation with EPA Regions 1 and 2, the
National Oceanic and Atmospheric Administration (NOAA), the New York State Department of State
(NYS DOS), the New York State Department of Environmental Conservation (NYS DEC), the
Connecticut Department of Environmental Protection (CT DEP), the Connecticut Department of
Transportation (CT DOT) and the Rhode Island Coastal Resources Management Council (RI CRMC).
Management of the LIS DMMP was assigned to the USACE New England District, which has
assigned a project manager. The participating agencies agreed to adopt the traditional management
structure by establishing and assigning representatives to a LIS DMMP Project Delivery Team (PDT).
Although not a standard component of the DMMP management structure, due to the large scope of the
project and strong public interest, the agencies also formed a Steering Committee of higher level
agency officials to facilitate communication, priority-setting, and the commitment of resources for the
LIS DMMP.
During the reporting period, the Steering Committee held monthly teleconferences to provide direction
to the PDT, resolve outstanding issues, and track progress on the DMMP. The PDT met twice during
this reporting period, and many of its members also participated in the monthly Steering Committee
calls. The meetings were held on August 27-29, 2007, in Newington, CT to finalize comments on the
LIS DMMP PMP, and on April 29, 2008, in Newington, CT to discuss DMMP work efforts, including
the Dredging Needs Survey and Upland Placement Inventory, project budget, and proposed schedule
for future work tasks. The current rosters for the Steering Committee and PDT are attached as
Appendices A and B.
Planning Process
The overarching goal of the LIS DMMP is to develop a comprehensive plan for dredged material
management in Long Island Sound that ensures federal dredging needs are met, and that will lead,
over time, to the reduction or elimination of open-water disposal in the Sound. The DMMP will try to
meet this goal by using a broad-based, public process that protects the environment based on best
scientific data and analysis, while meeting society's need for safe and economically viable navigation
for water based commerce, transportation, national security, and other public purposes. Recognizing
that there are numerous institutional, regulatory, social, and financial barriers to utilizing dredged
material beneficially, one purpose of the DMMP is to document these barriers and recommend plans
to overcome them.
For the Long Island Sound DMMP, it should be noted that the site designation restrictions apply to all
federal projects, and non-federal projects generating more than 25,000 cubic yards of dredged material
in the region. The LIS DMMP will identify potential environmentally acceptable, practicable
management alternatives that can be utilized by various dredging proponents in their analysis of
options to manage their dredging projects. The DMMP will provide its users with an array of
3

-------
suitable/feasible options that they could use in their alternatives analyses that will meet or exceed their
needs.
The Preliminary Assessment for the LIS DMMP was completed and approved by the US ACE in June
2006. The Project Management Plan, which serves as the initial work plan for the LIS DMMP, was
completed and approved by the US ACE, in consultation with the PDT, in October 2007. As
previously noted, the PMP is subject to change based on new information and input from the public
and other agencies. The initiation of the actual DMMP studies is dependent on the appropriation of
federal funding to the US ACE by Congress.
As previously noted, the US ACE will be preparing a Programmatic Environmental Impact Statement
(PEIS) in conjunction with the LIS DMMP to ensure compliance with NEPA. The USACE published
the Notice of Intent to develop a PEIS for the LIS DMMP in the Federal Register on August 31, 2007
(72 FR 50332). EPA, the USACE, and state agencies conducted a series of six public information and
NEPA scoping meetings to kick off the LIS DMMP and PEIS process on November 26-29, 2007. The
agencies held three meetings in each of the two states to present progress on the planning for the LIS
DMMP and solicit public input on both the scope and process of the LIS DMMP and PEIS. Public
comments will be considered in identifying and developing the activities and investigations to be
performed in the LIS DMMP and PEIS effort. The presentations from the public meetings and other
related documents are available on the USACE LIS DMMP Project website, which was established in
August 2007 (http://www.nae.usace.armv.mil/proiects/ri/LISDMMP/LISDMMP.htmn.
On March 24, 2008, the USACE contracted for the first two LIS DMMP study efforts. The Dredging
Needs Survey, which is to estimate how much dredging will occur and how much dredged material
will be generated in the entire region over a 20-year planning horizon, was initiated in June 2008. The
Upland Placement Inventory, which is to identify and catalog potential upland placement alternatives
for the entire region over a 20-year planning horizon, as well as the inventory of possible shore-side
transfer sites, was initiated in August 2008. Both studies will build upon information collected for the
Environmental Impact Statement for the Designation of Dredged Material Disposal Sites in Central
and Western Long Island Sound, April 2004.
Funding
The PDT estimates that it will cost $12 million and take 5-6 years to complete the LIS DMMP. In
February 2005, the governors of the two states sent a joint letter to the USACE requesting its
assistance with the development of the DMMP and, in separate letters, asked members of their
respective congressional delegations to seek appropriation of federal funds to initiate the DMMP. The
USACE agreed to work with the states on the DMMP and requests for funds have been included in the
President's budget for federal fiscal years (FY) 2007 and 2008. In FY07, $1.7 million was included in
the President's proposed budget, but this was eliminated by passage of a Continuing Resolution that
was based on the FY06 federal budget.
On December 26, 2007, the President signed the 2008 Consolidated Appropriations Act, which
included $3,525 million for the LIS DMMP. In June 2008, the USACE contracted approximately
$300,000 of the $3,525 million to conduct the first two studies.
4

-------
LONG ISLAND SOUND REGIONAL DREDGING TEAM
Purpose
As described above, the site designation rule contemplated that a Regional Dredging Team would be
established to review dredging proponents' alternative's analysis to ensure that they conducted a
comprehensive analysis for practicable alternatives to open-water disposal and recommend their use
to the maximum extent practicable, to ensure progress toward reducing or eliminating open-water
disposal in Long Island Sound pending completion of the DMMP. The following excerpt from the
RDT guidance describes its primary function:
The RDT is charged with reviewing all permit applications and authorizations subject
to the ... site designation rule restrictions and is not precluded from voluntarily
providing advice to any other dredging project to help achieve the goal of reducing or
eliminating the need for open water disposal in Long Island Sound. The RDT will
work to identify all practicable alternatives to open water disposal and to advise
regarding their use to the maximum extent practicable. Further, those identified
practicable alternative use opportunities will be advanced through the appropriate state
and federal authorities. All agencies will retain their respective final regulatory
decision-making authority and regulatory time frames for project review.
In July 5, 2006, EPA, USACE, NOAA, and the states agreed to form an RDT and assigned
representatives. The RDT began drafting a charter to describe the procedures the RDT would
use to review the alternatives analyses developed by dredging project proponents, determine
the adequacy of the analyses, and make recommendations on alternative dredged material
placement options that should be considered by the USACE and other regulatory agencies.
The RDT charter was approved by the Steering Committee in March 2007. The charter
describes how the RDT will enhance communication and discussion among the participating
agencies to facilitate the timely review and presentation of recommendations on the placement
of dredged material from Long Island Sound dredging projects. Through the review process,
the RDT will become aware of possible alternatives to open-water disposal that it can
communicate to potential applicants as well as appropriate state and federal authorities.
Current Status
During this reporting period, the RDT met once, on August 28, 2007, in conjunction with the
previously noted PDT meeting on August 27-29 in Newington, CT. The purpose of the meeting was
to review a proposal by several consultants for private marinas and boat yards to combine upward of
20 permitted private dredging projects to share capping material required by their permits. The RDT
members also participated in the public scoping meetings in NY and CT in November 26-29, 2007.
Dredged Material Disposal in Long Island Sound
It is the stated goal of the states of Connecticut and New York to reduce or eliminate the disposal of
dredged material in Long Island Sound. To determine if this goal is being met will require measuring
and tracking the amount of dredged material being disposed of or placed in the Sound and other
5

-------
locations. Currently, most open-water disposal in the Sound occurs at one of the four dredged material
disposal sites in the Sound: Western Long Island Sound (WLIS), Central Long Island Sound (CLIS),
Cornfield Shoals (CSDS), and New London (NLDS).
Alternatives include: upland placement or disposal; beach nourishment (depositing sand on or near an
eroding beach); habitat restoration (e.g., depositing dredged material in sub-tidal areas to raise
elevation and restore or create wetlands); confined aquatic disposal (CAD) cells (depositing unsuitable
dredge material in a pit excavated below the floor of the harbor or navigation channel, and covering
with clean material); and confined disposal facilities (using dredged material to increase the size of or
create islands, e.g., to expand port facilities). Some of these alternatives, including beach
nourishment, habitat creation/restoration, and capping (for both upland and aquatic habitat remediation
purposes, in certain circumstances) are considered beneficial to the environment (i.e., beneficial uses).
The following excerpt from the RDT guidance describes this process:
The RDT will track and document the volume of dredged material approved for open
water disposal as well as other alternative disposal methods, and submit this
information for inclusion in the annual report on progress of the DMMP. This
information will be part of the annual report on the progress of the DMMP to be issued
by the EPA.
EPA is complying with this guidance by working with the RDT to compile dredged material
disposal records on an annual basis, and reporting this data in an annual report for a one-year
period ending July 5 each year. The data in the annual report will be compared with dredged
material disposal data from all disposal activity in Long Island Sound averaged over the period
from 1982-2004. This is the third annual report.
Dredged Material Disposal in Long Island Sound, 1982-2004 (in cubic yards [c.y.])
Disposal Site
Total Dredged Material Disposal
Avg. Annual Dredged Material
Disposal
NLDS
3,069,546
133,459
CSDS
1,295,998
56,348
CLIS
8,019,678
348,682
WLIS
1,870,921
81,344
Totals
14,256,143
619,833
Overall, there was a total of 101,010 c.y. of dredged material generated in the Long Island Sound
vicinity for the period July 6, 2007 - July 5, 2008, of which:
•	46,010 c.y. were disposed at open-water disposal sites in Long Island Sound;
•	50,000 c.y. were placed at an upland containment site; and
•	5,000 c.y. were used beneficially for beach nourishment.
Of the 46,010 c.y. disposed in the Sound:
•	24,575 c.y. went to CLIS (vs. historical annual average of 348,682 c.y.);
•	10,135 c.y. went to WLIS (vs. historical annual average of 81,344 c.y.);
•	0 c.y. went to NLDS (vs. historical annual average of 133,459 c.y.); and
•	11,300 c.y. went to CSDS (vs. a historical annual average of 56,348 c.y.).
6

-------
All 46,010 c.y. disposed in the Sound came from private projects.
Recent Dredged Material Disposal in Long Island Sound Compared with Historic Averages
(in cubic yards [c.y.])
Disposal
Site
Avg.
Annual
Dredged
Material
Disposal
2006
2007
2008
Change from Previous
Reporting Period
(2007) c.y.
Change compared to
Avg. Annual Disposal
(1982-2004) c.y.
NLDS
133,459
0
369,635
0
-369,635
-133,459
CSDS
56,348
0
9,470
11,300
1,830
-45,048
CLIS
348,682
208,410
64,970
24,575
-40,395
-324,107
WLIS
81,344
15,550
3,600
10,135
6,535
-71,209
Totals
619,833
223,960
447,675
46,010
-401,665
-573,823
Compared with the average annual amount of dredged material disposed at the four open-water sites in
the Sound from 1982-2004, which was 619,833 c.y. for the period July 6, 2007 - July 5, 2008, there
was a total of 46,010 c.y., or about 7.4 percent of the historical annual average. For further details,
see Appendix D.
While there is generally some variability from one year to the next in the amount of dredged material
disposed of in the Sound, and there are many factors influencing this variability, reductions in the
federal budget again may have been one of the largest factors in the lower amount of disposal over the
past year. Regardless, it is too early to determine any kind of long-term trend. The amount of dredged
material disposed in the Sound during the current reporting period of July 6, 2007 - July 5, 2008 was
less than the amount disposed during the prior reporting period of July 6, 2006-July 5, 2007 (46,010
c.y. vs. 447,675 c.y. respectively); this appears to have resulted from variability in the size of projects
rather than from any difference in analysis of alternatives.
EPA will continue to report on an annual basis about the LIS RDT deliberations as well as each
dredging project that was completed in the preceding year, including the name of the applicant, the
alternatives that were evaluated, the volume of dredged material, and its final placement or disposal
location. For further information, please contact:
Jean Brochi
U.S. Environmental Protection Agency
One Congress Street, Suite 1100 (COP)
Boston, MA 02114
Telephone: (617) 918-1536
Fax: (617)918-0536
brochi.jean@epa.gov
7

-------
Appendix A
LONG ISLAND SOUND DREDGED MATERIAL MANAGEMENT PLAN
STEERING COMMITTEE
AGENCY
MEMBER
ALTERNATE
NOAA
David Kaiser, Senior Policy Analyst
Office of Ocean and Coastal Resource
Management, NOAA
603-862-2719 Fax: 603-862-3957
david.kaiser®,noaa. ao v

Corps
North Atlantic
Division (NAD)
Joe Vietri, Chief
Planning Division
718-765-7070
joseph.r.vietri@usace.army.mil

Corps
New England
District (NAE)
Bill Scully, Deputy District Engineer
Programs and Project Management
978-318-8230
william. c. scullv (3),usace. armv. mil
Robert (Bobby) Byrne, Chief
Programs & Project Management Division
978-318-8509
robert. h. by rne@usace. army. mil
Corps
New York District
(NAN)
Frank Santomauro, Chief
Planning Division
917-790-8700
frank, santomauro @usace. army. mil

EPA
Region I
Stephen Perkins, Director
Office of Ecosystem Protection
617-918-1501
perkins. stephen@epa. gov
Lynne Hamjian, Chief
Office of Ecosystem Protection
Surface Water Branch
617-918-1601
hamiian.lvnnefSteDa.aov
EPA
Region II
Kevin Bricke, Deputy Director
Division of Environmental Planning and
Protection
212-637-3736
bricke.kevin@epa.gov
Jeff Grata, Chief
Clean Water Regulatory Branch
Division of Environmental Planning and
Protection
Telephone: 212-637-3873
email: gratz.jeff@epa.gov
New York State
Dept. of State
George Stafford, Deputy Secretary of State
for Coastal Resources
518-473-2459
g staffor@dos. state. ny .us
Fred Anders, Chief
Natural Resource Management Bureau
Division of Coastal Resources
518-473-2477
fanders(5)dos.state.nv.us
New York State
Dept. of
Environmental
Conservation
James Gilmore, Chief, Bureau of Marine
Resources
518-402-8924
j gilmor@gw. dec. state.ny .us

Connecticut
Dept. of
Environmental
Protection
Betsey Wingfield, Chief
Bureau of Water Management
860-424-3704
betsey.wingfield@po. state.ct.us
Brian Thompson, Director
Office of Long Island Sound Programs
(860)424-3034
brian. thompson@po. state. ct. us
8

-------
Appendix B
LONG ISLAND SOUND DREDGED MATERIAL MANAGEMENT PLAN
PROJECT DELIVERY TEAM
AGENCY
MEMBER
MEMBER
Corps
New England
District (NAE)
Mike Keegan, Project Manager
978-318-8087
michael. f,keegan@usace. army. mil
Mark Habel
978-318-8871
mark.l.habel@usace.army.mil
Corps
New York District
(NAN)
Chris Ricciardi
917-790-8630
Christopher.g ,ricciardi@usace. army .mil
Nancy Brighton
917-790-8703
nancy. j. brighton@usace. army .mil
EPA
Region I
Mel Cote
617-918-1553
cote.mel@epa.gov
Jean Brochi
617-918-1536
brochi.iean@eDa.aov
EPA
Region II
Doug Pabst
212-637-3797
pabst.douglas@epa.gov
Patricia Pechko
212-637-3796
Dechko .Datricia(S),eDa. aov
National Marine
Fisheries Service
Diane Rusanowsky
203-882-2671
drusano@clam.mi.nmfs.gov

New York State
Dept. of State
Jennifer Street
518-474-1737
Jennifer. Street@dos.state.ny .us
Fred Anders
518-473-2477
fanders(5)dos.state.nv.us
New York State
Dept. of
Environmental
Conservation
John Ferguson
518-402-8829
j fergus@g w. state .ny .us

Connecticut
Dept. of
Environmental
Protection
George Wisker
860-424-3034
george. wisker@po. state. ct. us
Diane Duva
860-424-3271
diane. duva(5),po. state. ct. us
Connecticut
Dept. of
Transportation
Joe Salvatore
860-594-2539
j o seph. salvatore@po. state. ct. us

Rhode Island
Coastal Resources
Management
Council
Dan Goulet
401-783-3370
dgoulet@crmc. state, ri. us

9

-------
Appendix C
LONG ISLAND SOUND REGIONAL DREDGING TEAM
AGENCY
MEMBER
ALTERNATE
Corps North
Atlantic Division
(NAD)
James Haggerty
718-765-7150
james.w.haggerty@usace.army.mil

Corps New England
District (NAE)
Robert DeSista
978-318-8879
robert.j .desista@usace.army.mil
Jay Mackay
978-318-8142
joseph.b.mackay@usace.army.mil
Corps New York
District (NAN)
Joe Seebode
917-790-8209
joseph.j. seebode@nan02 .usace. army .mil

EPA
Region I
Jean Brochi
617-918-1536
brochi.j ean@epa. gov
Mel Cote
617-918-1553
cote.mel(5)eDa. ao v
EPA
Region II
Patricia Pechko
212-637-3796
pechko.patricia@epa.gov
Doug Pabst
212-637-3797
Dabst.douelas®,eDa.20v
NOAA National
Marine Fisheries
Service
Diane Rusanowsky
203-882-2671
drusano@clam.mi.nmfs.gov

New York
Dept. of State
Jennifer Street
518-474-1737
Jennifer. Street@dos.state.ny .us

New York State
Dept. of
Environmental
Conservation
Chuck Hamilton
cthamilt@gw. dec. state.ny .us

Connecticut
Dept. of
Environmental
Protection
George Wisker
Office of Long Island Sound Programs
860-424-3034
george. wisker@po. state. ct. us

Diane Duva
Bureau of Waste Management
860-424-3271
diane. duva@po. state. ct. us
David McKeegan
Bureau of Waste Management
860-424-3313
david.mckeegan@po. state.ct.us
10

-------
Appendix D
Long Island Sound Annual Dredging Report - for the Dredging Year Ending 5 July 2008
Summary of All Dredging and Disposal Activities
Disposal Sites and Methods
Open Water Disposal
Confined Disposal
Beneficial Use
CLIS
WLIS
NLDS
CSDS
CAD Cells
Upland
Containment
Landfill
Treated Dredged Material
CAD Cap
Beach/Bar
Nourishment
Habitat
Creation/Enhance
Brownfield
Remediation
Upland Disposal
Commercial Use
CONNECTICUT
Federal
(Corps)
Navigation
Projects
Other
Federal
Projects
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
NEW YORK
Private Federal other Private
Permit N' P1"'3.. Federal Permit
Activities av|9a 'on projects Activities
Drniontc	J
Total All
Projects
0
0
0
0
0
0
0
0
0
0
0
37,825
24,575
1,950
0
11,300
0
0
0
0
0
0
0
0 0
0 0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
8,185
0
8,185
0
0
0
0
50,000
0
0
0
5,000
46,010
24,575
10,135
0
11,300
0
0
50,000
0
0
0
5,000
0
0
0
0
0
TOTAL ALL DISPOSAL
0 37,825
0 63,185 101,010
Note: There was no Federal Navigation dredging activity in the Long Island Sound region
during the reporting period.
11

-------